SlideShare a Scribd company logo
1 of 25
KALIA BHOMARA SETU
ROAD BRIDGE ON THE RIVER
BRAHMAPUTRA
TEZPUR,ASSAM
By : Vishweshwar Rao Narla
KALIA BHOMARA SETU
1 INTRODUCTION
 The River having a catchment area of
3.8lakh sq.km flows in the most
unpredictable manners, occupying space.
 The Project Connects NH 52 & NH 37 on
south bank, through a 23km long link.
2 FOUNDATION
 Out of 27 foundations 25 are Open Wells
 The North Abutment and Pier No.1 are on Raft
Foundations.
 The Wells have been Sunk to 56m LWL, mainly
from scour and seismic considerations.
 The strata encountered were dense sand mixed
with pebbles.
 With elaborate monitoring at each stages of
sinking, it has been possible to position all the
wells within permissible limits of the Tilt & Shift
each well costing of Rs.80 Lakh and involving
5000m of concrete was completed within an
average period of 90 days.
WELL WORK IN PROGRESS FOR THE BRIDGE PILLAR
3 WELL FOUNDATION
 Two of the Well-Foundations required of
caissons in depth of water ranging from 8m to
12m 290t of steel was required to be fabricated
for these caissons.
 Water ballasting of sinking-pontoons to ferry
across the construction materials, for
simultaneous working on a number of
foundations, a large fleet of marine craft was
deployed it consisted of tugs.
 20 barges and a number of country boats for
concreting, batching plants of 950cu.m/day
ccapacity were installed.
 9 SLD cranes, 3 Crawler cranes and stand
cutter dredger pumps were used for sinking
Well Foundations.
WELL WORK IN PROGRESS FOR THE BRIDGE PILLAR
4 PILE DRIVING
 Pier No.1 founded on a 2m thick RCC Raft which is
held down with 96 rock-anchors on North and 6 RCC
bored piles of 1.5m dia on South.
 These piles are driven with CASSAGRADE pile-
driving equipment.
 Substructure is hollow circular RCC piers of 12.5m
height constructed with concrete of grade M-300. it
being a navigable river, the height of the piers has
been determined to Cater to the navigational
clearances.
 RCC feeders have been provided to protect the piers
from any possible damage due to stray vessels.
 The pier-cap is made 6.5m square to facilitate the
construction pier-head.
5 CAISSON GROUNDING
 While sinking the Well for Pier No. 2 near
Bhomoraguri Hill, boulder stratum at a depth
of 26m below LWL was met with services
deep sea divers were utilized for sinking the
Ell through this stratum, by under water
blasting.
6 SUPER STRUCTURE
 The distance of 120m between consequence
pier-center is spanned by two 52.5 long
balanced Cantilever from the piers and a 15m
long suspended span in the middle.
 The cantilever portion is a single-cell PSC Box
Girder in concrete of grade M-425 using special
cement, post tensioned with 90nos of 24x8mm
dia HTS cables.
 The cantilever arm has been constructed in 11
segments of different lengths.
THE 15 METER SECTION IN BETWEEN TWO CANTILEVER OF 52.5
METERS BEING FITTED IN PLACE
CANTILEVER SECTION WORK UNDER PROGRESS
VIEW OF WORK INSIDE A BOX SECTION OF CANTILEVER
7 MASTIC SURFACE
 For the construction o the cantilevers, the Bridge-
Builder system has been imported from Norway for
the first time in India.
 An average cycle of 5days has been achieved here
for segment construction, as against the accepted
international average of 7days; FREYSSINET
system has been adopted for pre-stressing.
 For manufacture and placing of large volumes of
high grade concrete, electrically controlled automatic
ELBA batching plants along with concrete pumps
were imported from West Germany.
 The total installed concreting capacity was of the
order of 1000cu.m/day.
THE JOINTS BETWEEN TWO SECTION OF CANTILEVER
8 GIRDER LAUNCHING
 The Bearing at the interface of a cantilever
and a suspended span is specially
designed to cater to complex seismic
movements.
 These consists of a combination of
spherical knuckle and PTFE stainless steel
sliding surface for surface for free end
bearings and spherical knuckle cum
electromeric pad for fixed end bearings.
 The majestic deck is provided with 25mm
thick layer of Mastic Asphalt.
THE HOLLOW CANTILEVER BOX SECTION , INSIDE VIEW
9 RIVERINE QUARRY
 The requirements of aggregates for the
bridgework met with from a reverine quarry on
the North bank.
 For the Guide-Bund the required quantity of
man-size boulders was collected from hill quarry
on the south bank for which 30t of explosives
were used.
 Both these quarries were 50-60km away from
the work site and this necessitated deployment
of a large for verifying grades of concrete, a fully
mechanized aggregate processing plant of 150
t/hours capacity was set-up.
10 CRUSHING PLANT
 The project site is situated in a remote corner of
the country.
 Due to non-availability adequate quality of steel
and cement in the proximity, their procurement
involved long leads in distance and time.
 Therefore large storage capacity to the tune of
24000t for cement and 14000t for steel, had to be
developed.
 To feed electrical power to the work site, power
supply network was developed consisting of
33KVA overhead transmission lines for a length of
30km along with four sub-stations.
 River crossing was arranged by laying under water
XLPE Cables. Necessary infrastructure was
developed at work site, to house 4000 workmen
including Engineers and Supervisors.
11 TECHNICAL DETAILS
Structural details :-
a) Bridge:
1) Spans : 24 spans of 120m
and two shore-spans discharge
of 67.5 m
2) Total length : 3015m
3) Main span : Balanced
cantilever Pre Stressed concrete
box �girder of 52.5m site with
central R. C. C suspended span
of 15 Meter.
4)Clear carriage way : 7.5m
5)Footpath :1.5m wide on either
side.
6) Sub-structure: : 12.5m high
hollow Circular R.C.C pier with
Square pier-cap.
7)Navigational clearance :
12.0m for central 90m.
8) Foundation : 56 m deep 12m
dia.
b) Guide-bund :
 1) Length : 1633m on U/s and
405 m on D/S.
 2) Shape : Elliptical
 3) Sausage crate size : 2.55m x
1.5 m (0.90 to 1.05)
 4) Top level : R.L 71.10 m
 5)Top width : 9.0 m
 6) Side slopes : 2.5 : 1.
 7) Pitching on front slop : 1.2 m
thick grouted with 1:3:6
concrete over 0.3 m thickfilter.
 8) Pitching on rear slope : 0.3 m
thick boulders over 0.15 m
c) South Approach Bank :
i) Length : 1678 m
ii) Top width : 12.0 m
iii) Side slopes : 2.5: 1
11 TECHNICAL DETAILS
Hydraulic data :-
1) Maximum design : 92,278
Cumecs.
2) Minimum discharge : 4,000
cumecs.
3) Design H.F.L : R.L.67.5m
4) Maximum mean Velocity :
4m/sec.
5) Average L.W.L : R.L 610m.
6) River width at bridge : 4,683m
7) Maximum design scour level a)
Normal condition : R.L.24.76m b)
Seismic condition : R.L.29.03m
Material consumed:
a) Bridge :
1) Total concrete quality : 1,70,000
m3
2) Total reinforcing steel : 12,000
mt
3) Cement : 82,000 mt
4) Coarse aggregate : 1,50,000m3
5) Sand :75,000m3
b) Guide-bund and South
Approach Bank
1) Earth-work : 19 lakh m3
2) Stone �work : 8.2 lakh m3
3) G.I wire : 5300mt
12 CONSTRUCTION SHEDULE
 The river offers only 135 days for normal river-
bed working, as compared to 180-210 days for
other major rivers of India. This necessitated
large-scale mechanization for foundations and
elaborate arrangements for superstructure
works even during high-floods. The Guide-bund,
involving 19 lakh m3 of earth-work and 8.2 lakh
m3 of boulder-work, was required to be
completed within 135 days and needed
deployment of machinery worth Rs.11 Crores for
the work. The actual time of completion of each
work, is as follows : -
12 CONSTRUCTION SHEDULE
12 CONSTRUCTION SHEDULE
 Maximum concreting done in one day 950 M3
 Maximum sinking done in one day 19 Meter
 Average rate of sinking of wells 1.3 M/day
 Max amnt of work done for bridge in one day Rs.6.5 lakh
 Maximum concreting done in one season 71,000 M3
 Maximum cement consumed in one season
23,800mt
 Maximum sinking done in one season 703m
 Max no. of cantilever segments done in one month 28
 Maximum amount of earth-work done in one day
16,800m3
 Max amount of boulder-work done in the one day 9,350m3
 Max amt of work done for Guide-bund in one day Rs.11.6
Lakh.
13 CONTRACTORS
 a) Main Bridge :
M/S Hindustan Construction Company Ltd,
Bombay.
 b) Guide-bund and South Approach
Bank : M/s. Jai Prakash Associates, New
Delhi.
 c) Bridge bearings and Expansion
joints :
M/S Metal Engineering & Treatment
Co.(P) Ltd, Calcutta.

More Related Content

What's hot

Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...
Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...
Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...Mohit Shukla
 
Extending Open Cast Mine to Underground Mine Planning
Extending Open Cast Mine to Underground Mine PlanningExtending Open Cast Mine to Underground Mine Planning
Extending Open Cast Mine to Underground Mine PlanningJasmeet Singh Saluja
 
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAMNhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAMIshant Gautam.
 
Atal Rohtang Tunnel - construction process ,challenges and features
Atal Rohtang Tunnel - construction process ,challenges and featuresAtal Rohtang Tunnel - construction process ,challenges and features
Atal Rohtang Tunnel - construction process ,challenges and featuresBimenpreet Kaur
 
Tunneling by tunnel boring machine
Tunneling by tunnel boring machineTunneling by tunnel boring machine
Tunneling by tunnel boring machineVISHAL KUMAR SINGH
 
Design of concrete Gravity Dam_Project B.E final
Design of concrete Gravity Dam_Project B.E finalDesign of concrete Gravity Dam_Project B.E final
Design of concrete Gravity Dam_Project B.E finalSyed Salman
 
Tunnel constructions
Tunnel constructionsTunnel constructions
Tunnel constructionsVinay Vb
 
Underground Coal Mining Study
Underground Coal Mining StudyUnderground Coal Mining Study
Underground Coal Mining StudyOnur Tuncay
 
Longwall - China & India
Longwall - China & IndiaLongwall - China & India
Longwall - China & IndiaVR M
 
Study of tunnel engineering
Study of tunnel engineeringStudy of tunnel engineering
Study of tunnel engineeringAdil Shaikh
 
20150421031337318
2015042103133731820150421031337318
20150421031337318James Prs
 
tunnel boring machine
tunnel boring machinetunnel boring machine
tunnel boring machineNaquiakhter
 
Worldhighestrailwaybridge
Worldhighestrailwaybridge Worldhighestrailwaybridge
Worldhighestrailwaybridge Hakkim Shajahan
 
(2010) - Yates M, Krzeminski M, Berthier D, Hamidi B - The Application of Jet...
(2010) - Yates M, Krzeminski M, Berthier D, Hamidi B - The Application of Jet...(2010) - Yates M, Krzeminski M, Berthier D, Hamidi B - The Application of Jet...
(2010) - Yates M, Krzeminski M, Berthier D, Hamidi B - The Application of Jet...Michal Krzeminski
 
Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...
Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...
Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...Hitesh Khanna
 
Presentation on Flyover at Aziz Cross on GT Road Gujranwala
Presentation on Flyover at Aziz Cross on GT Road GujranwalaPresentation on Flyover at Aziz Cross on GT Road Gujranwala
Presentation on Flyover at Aziz Cross on GT Road GujranwalaRubnawaz Bhatti
 

What's hot (20)

Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...
Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...
Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...
 
Extending Open Cast Mine to Underground Mine Planning
Extending Open Cast Mine to Underground Mine PlanningExtending Open Cast Mine to Underground Mine Planning
Extending Open Cast Mine to Underground Mine Planning
 
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAMNhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
 
Atal Rohtang Tunnel - construction process ,challenges and features
Atal Rohtang Tunnel - construction process ,challenges and featuresAtal Rohtang Tunnel - construction process ,challenges and features
Atal Rohtang Tunnel - construction process ,challenges and features
 
Tunneling by tunnel boring machine
Tunneling by tunnel boring machineTunneling by tunnel boring machine
Tunneling by tunnel boring machine
 
Design of concrete Gravity Dam_Project B.E final
Design of concrete Gravity Dam_Project B.E finalDesign of concrete Gravity Dam_Project B.E final
Design of concrete Gravity Dam_Project B.E final
 
Tunnel boring machine
Tunnel boring machineTunnel boring machine
Tunnel boring machine
 
5878 5
5878 55878 5
5878 5
 
Tunnel constructions
Tunnel constructionsTunnel constructions
Tunnel constructions
 
Underground Coal Mining Study
Underground Coal Mining StudyUnderground Coal Mining Study
Underground Coal Mining Study
 
Longwall - China & India
Longwall - China & IndiaLongwall - China & India
Longwall - China & India
 
Study of tunnel engineering
Study of tunnel engineeringStudy of tunnel engineering
Study of tunnel engineering
 
20150421031337318
2015042103133731820150421031337318
20150421031337318
 
tunnel boring machine
tunnel boring machinetunnel boring machine
tunnel boring machine
 
tunneling & its effects
tunneling & its effectstunneling & its effects
tunneling & its effects
 
Worldhighestrailwaybridge
Worldhighestrailwaybridge Worldhighestrailwaybridge
Worldhighestrailwaybridge
 
(2010) - Yates M, Krzeminski M, Berthier D, Hamidi B - The Application of Jet...
(2010) - Yates M, Krzeminski M, Berthier D, Hamidi B - The Application of Jet...(2010) - Yates M, Krzeminski M, Berthier D, Hamidi B - The Application of Jet...
(2010) - Yates M, Krzeminski M, Berthier D, Hamidi B - The Application of Jet...
 
Tunnel construction
Tunnel constructionTunnel construction
Tunnel construction
 
Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...
Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...
Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...
 
Presentation on Flyover at Aziz Cross on GT Road Gujranwala
Presentation on Flyover at Aziz Cross on GT Road GujranwalaPresentation on Flyover at Aziz Cross on GT Road Gujranwala
Presentation on Flyover at Aziz Cross on GT Road Gujranwala
 

Similar to KALIA BHOMARA SETU - THE BRIDGE OVER BRAHMAPUTRA RIVER

internship report on NJHPP
internship report on NJHPPinternship report on NJHPP
internship report on NJHPPSaad Raja
 
Busan geoje fixed link
Busan   geoje fixed linkBusan   geoje fixed link
Busan geoje fixed linkVicky Matwan
 
Chenab Bridge.pdf
Chenab Bridge.pdfChenab Bridge.pdf
Chenab Bridge.pdfPpt Creater
 
Megastructures design pdf
Megastructures design pdfMegastructures design pdf
Megastructures design pdfSaqib Imran
 
Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...Rajesh Prasad
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptxAditya Mane
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptxAditya Mane
 
Bandra Worli sea link
Bandra Worli sea linkBandra Worli sea link
Bandra Worli sea linkKAVYA H
 
Neelum Jhelum Hydropower Internship Report
Neelum Jhelum Hydropower Internship Report Neelum Jhelum Hydropower Internship Report
Neelum Jhelum Hydropower Internship Report muhammad khurram
 
Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Rajesh Prasad
 
Design of earth dam at gorukallu
Design of earth dam at gorukalluDesign of earth dam at gorukallu
Design of earth dam at gorukallurohinibjn
 
Ailments of the First Concrete Dam in Sri Lanka
Ailments of the First Concrete Dam in Sri LankaAilments of the First Concrete Dam in Sri Lanka
Ailments of the First Concrete Dam in Sri LankaNihal Vitharana
 
Shaft sinking
Shaft sinking Shaft sinking
Shaft sinking OmKaitade
 
Neelum jehlum hydropower project
Neelum jehlum hydropower projectNeelum jehlum hydropower project
Neelum jehlum hydropower projectMuhammad Aqeel
 
Cut and cover_sections
Cut and cover_sectionsCut and cover_sections
Cut and cover_sectionsjuwes
 
Report on Neelum Jhelum Hyrdoelectic project
Report on Neelum Jhelum Hyrdoelectic projectReport on Neelum Jhelum Hyrdoelectic project
Report on Neelum Jhelum Hyrdoelectic projectRubnawaz Bhatti
 

Similar to KALIA BHOMARA SETU - THE BRIDGE OVER BRAHMAPUTRA RIVER (20)

Project report
Project reportProject report
Project report
 
internship report on NJHPP
internship report on NJHPPinternship report on NJHPP
internship report on NJHPP
 
Busan geoje fixed link
Busan   geoje fixed linkBusan   geoje fixed link
Busan geoje fixed link
 
Chenab Bridge.pdf
Chenab Bridge.pdfChenab Bridge.pdf
Chenab Bridge.pdf
 
Megastructures design pdf
Megastructures design pdfMegastructures design pdf
Megastructures design pdf
 
Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
 
Bandra Worli sea link
Bandra Worli sea linkBandra Worli sea link
Bandra Worli sea link
 
Neelum Jhelum Hydropower Internship Report
Neelum Jhelum Hydropower Internship Report Neelum Jhelum Hydropower Internship Report
Neelum Jhelum Hydropower Internship Report
 
Jamrani dam ppt
Jamrani dam pptJamrani dam ppt
Jamrani dam ppt
 
Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...
 
Design of earth dam at gorukallu
Design of earth dam at gorukalluDesign of earth dam at gorukallu
Design of earth dam at gorukallu
 
Ailments of the First Concrete Dam in Sri Lanka
Ailments of the First Concrete Dam in Sri LankaAilments of the First Concrete Dam in Sri Lanka
Ailments of the First Concrete Dam in Sri Lanka
 
Shaft sinking
Shaft sinking Shaft sinking
Shaft sinking
 
Neelum jehlum hydropower project
Neelum jehlum hydropower projectNeelum jehlum hydropower project
Neelum jehlum hydropower project
 
Cut and cover_sections
Cut and cover_sectionsCut and cover_sections
Cut and cover_sections
 
Millau viaduct
Millau viaductMillau viaduct
Millau viaduct
 
Srisailam project final
Srisailam project finalSrisailam project final
Srisailam project final
 
Report on Neelum Jhelum Hyrdoelectic project
Report on Neelum Jhelum Hyrdoelectic projectReport on Neelum Jhelum Hyrdoelectic project
Report on Neelum Jhelum Hyrdoelectic project
 

Recently uploaded

Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEroselinkalist12
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 

Recently uploaded (20)

Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 

KALIA BHOMARA SETU - THE BRIDGE OVER BRAHMAPUTRA RIVER

  • 1. KALIA BHOMARA SETU ROAD BRIDGE ON THE RIVER BRAHMAPUTRA TEZPUR,ASSAM By : Vishweshwar Rao Narla
  • 3. 1 INTRODUCTION  The River having a catchment area of 3.8lakh sq.km flows in the most unpredictable manners, occupying space.  The Project Connects NH 52 & NH 37 on south bank, through a 23km long link.
  • 4. 2 FOUNDATION  Out of 27 foundations 25 are Open Wells  The North Abutment and Pier No.1 are on Raft Foundations.  The Wells have been Sunk to 56m LWL, mainly from scour and seismic considerations.  The strata encountered were dense sand mixed with pebbles.  With elaborate monitoring at each stages of sinking, it has been possible to position all the wells within permissible limits of the Tilt & Shift each well costing of Rs.80 Lakh and involving 5000m of concrete was completed within an average period of 90 days.
  • 5. WELL WORK IN PROGRESS FOR THE BRIDGE PILLAR
  • 6. 3 WELL FOUNDATION  Two of the Well-Foundations required of caissons in depth of water ranging from 8m to 12m 290t of steel was required to be fabricated for these caissons.  Water ballasting of sinking-pontoons to ferry across the construction materials, for simultaneous working on a number of foundations, a large fleet of marine craft was deployed it consisted of tugs.  20 barges and a number of country boats for concreting, batching plants of 950cu.m/day ccapacity were installed.  9 SLD cranes, 3 Crawler cranes and stand cutter dredger pumps were used for sinking Well Foundations.
  • 7. WELL WORK IN PROGRESS FOR THE BRIDGE PILLAR
  • 8. 4 PILE DRIVING  Pier No.1 founded on a 2m thick RCC Raft which is held down with 96 rock-anchors on North and 6 RCC bored piles of 1.5m dia on South.  These piles are driven with CASSAGRADE pile- driving equipment.  Substructure is hollow circular RCC piers of 12.5m height constructed with concrete of grade M-300. it being a navigable river, the height of the piers has been determined to Cater to the navigational clearances.  RCC feeders have been provided to protect the piers from any possible damage due to stray vessels.  The pier-cap is made 6.5m square to facilitate the construction pier-head.
  • 9. 5 CAISSON GROUNDING  While sinking the Well for Pier No. 2 near Bhomoraguri Hill, boulder stratum at a depth of 26m below LWL was met with services deep sea divers were utilized for sinking the Ell through this stratum, by under water blasting.
  • 10. 6 SUPER STRUCTURE  The distance of 120m between consequence pier-center is spanned by two 52.5 long balanced Cantilever from the piers and a 15m long suspended span in the middle.  The cantilever portion is a single-cell PSC Box Girder in concrete of grade M-425 using special cement, post tensioned with 90nos of 24x8mm dia HTS cables.  The cantilever arm has been constructed in 11 segments of different lengths.
  • 11. THE 15 METER SECTION IN BETWEEN TWO CANTILEVER OF 52.5 METERS BEING FITTED IN PLACE
  • 12. CANTILEVER SECTION WORK UNDER PROGRESS
  • 13. VIEW OF WORK INSIDE A BOX SECTION OF CANTILEVER
  • 14. 7 MASTIC SURFACE  For the construction o the cantilevers, the Bridge- Builder system has been imported from Norway for the first time in India.  An average cycle of 5days has been achieved here for segment construction, as against the accepted international average of 7days; FREYSSINET system has been adopted for pre-stressing.  For manufacture and placing of large volumes of high grade concrete, electrically controlled automatic ELBA batching plants along with concrete pumps were imported from West Germany.  The total installed concreting capacity was of the order of 1000cu.m/day.
  • 15. THE JOINTS BETWEEN TWO SECTION OF CANTILEVER
  • 16. 8 GIRDER LAUNCHING  The Bearing at the interface of a cantilever and a suspended span is specially designed to cater to complex seismic movements.  These consists of a combination of spherical knuckle and PTFE stainless steel sliding surface for surface for free end bearings and spherical knuckle cum electromeric pad for fixed end bearings.  The majestic deck is provided with 25mm thick layer of Mastic Asphalt.
  • 17. THE HOLLOW CANTILEVER BOX SECTION , INSIDE VIEW
  • 18. 9 RIVERINE QUARRY  The requirements of aggregates for the bridgework met with from a reverine quarry on the North bank.  For the Guide-Bund the required quantity of man-size boulders was collected from hill quarry on the south bank for which 30t of explosives were used.  Both these quarries were 50-60km away from the work site and this necessitated deployment of a large for verifying grades of concrete, a fully mechanized aggregate processing plant of 150 t/hours capacity was set-up.
  • 19. 10 CRUSHING PLANT  The project site is situated in a remote corner of the country.  Due to non-availability adequate quality of steel and cement in the proximity, their procurement involved long leads in distance and time.  Therefore large storage capacity to the tune of 24000t for cement and 14000t for steel, had to be developed.  To feed electrical power to the work site, power supply network was developed consisting of 33KVA overhead transmission lines for a length of 30km along with four sub-stations.  River crossing was arranged by laying under water XLPE Cables. Necessary infrastructure was developed at work site, to house 4000 workmen including Engineers and Supervisors.
  • 20. 11 TECHNICAL DETAILS Structural details :- a) Bridge: 1) Spans : 24 spans of 120m and two shore-spans discharge of 67.5 m 2) Total length : 3015m 3) Main span : Balanced cantilever Pre Stressed concrete box �girder of 52.5m site with central R. C. C suspended span of 15 Meter. 4)Clear carriage way : 7.5m 5)Footpath :1.5m wide on either side. 6) Sub-structure: : 12.5m high hollow Circular R.C.C pier with Square pier-cap. 7)Navigational clearance : 12.0m for central 90m. 8) Foundation : 56 m deep 12m dia. b) Guide-bund :  1) Length : 1633m on U/s and 405 m on D/S.  2) Shape : Elliptical  3) Sausage crate size : 2.55m x 1.5 m (0.90 to 1.05)  4) Top level : R.L 71.10 m  5)Top width : 9.0 m  6) Side slopes : 2.5 : 1.  7) Pitching on front slop : 1.2 m thick grouted with 1:3:6 concrete over 0.3 m thickfilter.  8) Pitching on rear slope : 0.3 m thick boulders over 0.15 m c) South Approach Bank : i) Length : 1678 m ii) Top width : 12.0 m iii) Side slopes : 2.5: 1
  • 21. 11 TECHNICAL DETAILS Hydraulic data :- 1) Maximum design : 92,278 Cumecs. 2) Minimum discharge : 4,000 cumecs. 3) Design H.F.L : R.L.67.5m 4) Maximum mean Velocity : 4m/sec. 5) Average L.W.L : R.L 610m. 6) River width at bridge : 4,683m 7) Maximum design scour level a) Normal condition : R.L.24.76m b) Seismic condition : R.L.29.03m Material consumed: a) Bridge : 1) Total concrete quality : 1,70,000 m3 2) Total reinforcing steel : 12,000 mt 3) Cement : 82,000 mt 4) Coarse aggregate : 1,50,000m3 5) Sand :75,000m3 b) Guide-bund and South Approach Bank 1) Earth-work : 19 lakh m3 2) Stone �work : 8.2 lakh m3 3) G.I wire : 5300mt
  • 22. 12 CONSTRUCTION SHEDULE  The river offers only 135 days for normal river- bed working, as compared to 180-210 days for other major rivers of India. This necessitated large-scale mechanization for foundations and elaborate arrangements for superstructure works even during high-floods. The Guide-bund, involving 19 lakh m3 of earth-work and 8.2 lakh m3 of boulder-work, was required to be completed within 135 days and needed deployment of machinery worth Rs.11 Crores for the work. The actual time of completion of each work, is as follows : -
  • 24. 12 CONSTRUCTION SHEDULE  Maximum concreting done in one day 950 M3  Maximum sinking done in one day 19 Meter  Average rate of sinking of wells 1.3 M/day  Max amnt of work done for bridge in one day Rs.6.5 lakh  Maximum concreting done in one season 71,000 M3  Maximum cement consumed in one season 23,800mt  Maximum sinking done in one season 703m  Max no. of cantilever segments done in one month 28  Maximum amount of earth-work done in one day 16,800m3  Max amount of boulder-work done in the one day 9,350m3  Max amt of work done for Guide-bund in one day Rs.11.6 Lakh.
  • 25. 13 CONTRACTORS  a) Main Bridge : M/S Hindustan Construction Company Ltd, Bombay.  b) Guide-bund and South Approach Bank : M/s. Jai Prakash Associates, New Delhi.  c) Bridge bearings and Expansion joints : M/S Metal Engineering & Treatment Co.(P) Ltd, Calcutta.