Mahi hydro power plant summer industrial training presentaion
1. A Presentation On
Mahi Hydel Power House
1
PRESENTED TO
Department of Mechanical Engg.
PRESENTED BY
Abhimanyu Singh Bhati
13EGBME300
B.Tech. IV Yr. VII Sem.
2. About Mahi Hydro Power Project
Development of the
multistate Mahi Bajaj
Sager Project started with
laying of the foundation
stone in 1960. The project
is named after national
leader Shri Jamnala Bajaj.
Major construction
activities started in 1972
and the PH-I was
dedicated by Chief
Minister Haridev Joshi in
Feb 1983
3. Feature of Mahi – I Power House
Name of the Powerhouse Mahi - Power House I
Year Commissioned 1986
Total Installed Capacity (MW) Sum of IC of
all turbines
2 X 25 MW
Type of Turbines Francis
Speed (rpm) 150
Number of Penstocks 2
Size of Penstocks 4.2m dia
Full Reservoir Level (m) 281.5
4. Components of Hydroelectric Power Plants
DAM
RESERVOIR
CONTROL GATE
PENSTOCK
TURBINE
GENERATOR
TRANSFORMER
SWITCH YARD