Presentation on Flyover at Aziz Cross on GT Road Gujranwala. First project in the history of Pakistan where flyovers are constructed on different heights
3. February 2012
GOVERNMENT OF THE PUNJAB
COMMUNICATION & WORKS DEPARTMENT
Construction of Flyover on G.T Road
at Aziz Cross Gujranwala
4. February 2012
GOVERNMENT OF THE PUNJAB
CONSTRUCTION OF FLYOVER ON
G.T ROAD AT AZIZ CROSS GUJRANWALA
Construction of Flyover on G.T Road
at Aziz Cross Gujranwala
5. SALIENT FEATURE
ADP (2016-17) Gr. Sr. No. 2775
Approved Cost Rs. 6672 Million
Construction Cost Rs. 3435 M
Land Acquisition (80 Kanal) Rs. 2920 M
Miscellaneous Rs. 317 M
Consultant M/s NESPAK
Contract M/s NLC
Client C & W Dept
Agreement Amount Rs.3115 M (9.35% below Est.cost)
Date of Commencement 30.01.2016
Date of Completion 29.11.2016
6. INTRODUCTION
Aziz Cross project is a signal free interchange with partial clover
leaf system and two additional directional ramps.
Clover leaf interchange Partial Clover leaf
interchange with two
directional ramps instead
of loops
7. INTRODUCTION
There are normally 32 conflicts at any interchange which are
completely resolved at Aziz Cross.
32 No. Traffic Conflicts
Traffic Count 2014
9. BASIC COMPONENTS OF FLYOVER
Bridge cross-section can be divided
into two portions.
1. Super Structure
This portion receives the live load
directly. For example, Box Girder
2. Sub Structure
This Portion supports the entire
structure and live loads.
Piles
Pile cap
Piers
Abutments
Web
Web
Pier
Canopy
Pier
Shaft
Pile Cap
Pile
Pile
Pile
Super
Structure
Sub
Structure
10. CONCRETE PILES
A pile is a vertical structural element of a deep foundation which
transfers super structure loads to the earth farther down from the
surface to a subsurface layer.
11.
12.
13.
14. PILE CAP
PILE CAP
Pile cap is a thick
reinforced concrete mat that
rests on concrete piles that
have been casted into ground.
concrete pile cap distributes the
load of the superstructure (from
piers and abutments into the
piles.
Pile Cap
Piles
Pier
15.
16.
17.
18.
19.
20.
21. PILE CAP AND PIER
PIER
A pier is a reinforced,
raised structure in form of
pillars typically supported by
well-spaced pile caps. It
transfers the loads from deck to
pile caps.
For this project, special shape
of pier is adopted. It as two
components
1. Pier Shaft as column
2. Pier Canopy as transom
Pier Canopy
Pier Shaft
Box Girder
22.
23.
24.
25.
26. Abutment refers to the substructure at the ends of a bridge span. It
supports;
Super Structure load
Live Load
Lateral Earth Pressure
ABUTMENTS
Abutment
Pile Cap
Piles
27.
28.
29.
30. REINFORCED EARTH WORK
Reinforced earth wall is earth retaining structure and provided at
approaches (from road level to bridge level).
The key components of a Reinforced Earth wall are geo-strips,
granular backfill and precast concrete facing panels.
The frictional bond between the backfill supports the lateral earth
pressure and stresses induced due to traffic load.
33. PRE-STRESSED BOX GIRDERS
Bottom View of Box Girder
Piers
An optimal and most efficient design of beam is box girder. A box girder
consists of enclosed tube with multiple walls.
The advantage of a box girder is that it better resists torsion. Having
multiple vertical webs, it can also carry more load than an I-shape girder
of equal height.
Pre-stressing Mechanism
34.
35.
36.
37.
38.
39.
40.
41. SCOPE OF WORK
12/14/2016
Flyover 1
Length 301.5
Piles 80
P. Cap 15
Piers 15
Abt. 2
Spans 10Flyover 2
Length 301.5
Piles 66
P. Cap 11
Piers 12
Abt. 2
Spans 10
Flyover 5
Length 80.05
Piles 38
P. Cap 4
Piers 6
Abt. 2
Spans 3Flyover 3
Length 417.3
Piles 64
P. Cap 15
Piers 13
Abt. 2
Spans 14
Flyover 4
Length 564.41
Piles 84
P. Cap 20
Piers 18
Abt. 2
Spans 18
RWP
LHR
GRW
SKT
Pile= 332 Ramp 3 (L=361.14m) Ramp 6(L=369.39 m) Bridge approaches (841m)
Pile caps=65 Ramp 3A(L=573.11m) Ramp 7(L=369.39 m)
Abutment= 10 Ramp 4( L=379.35m) Loop 1(270.18m) Bridge Lengths(1664m)
Piers=60 Ramp 5 (L=846.94m) Loop 2(L=195.23) Road Length (4660m)
42. FLYOVER S– 1, 2, 3 & 4
Piles 100 % Completed (294 out of 294)
Pile Caps 100 % Completed (62 out of 62)
Piers 100 % Completed (62 out of 62)
Abutment 100 % Completed (8 out of 8)
Box Girders 20% in progress (4 out of 17)
Reinforce Earth Wall 50 % Completed (0.6 km out of 1.12 km)
At Grade Roads 60% up to WBM (3 Km out of 5 Km)
RAILWAY BRIDGE
Piles 100% Completed (38 out of 38)
Pile Caps 100% Completed (4 out of 4)
Piers 100% Completed (2 out of 2)
Transoms 50% Completed (1 out of 2)
Abutments 50% Completed (1 out of 2)
Pre-cast Girders 100% Completed (21 out of 21)
PHYSICAL PROGRESS
43. Year Release Expr. %age Remarks
2014-15 2500 2500 100%
Payment made for land
acquisition.
2015-16 1555 1555 100%
Rs. 400 M land acquisition.
Rs. 215 M shifting of
services.
Rs. 940 M paid to NLC.
2016-17 1000 510 51% Rs. 510 M paid to NLC.
FINANCIAL PROGRESS