More Related Content Similar to TWR Presentation for Foam Proportioner.pptx (20) TWR Presentation for Foam Proportioner.pptx1. PT. TRIMITRA WUJUD REKANUSA
PEKERJAAN REPLACING FOAM
PROPORTIONER DI FT TASIKMALAYA
© Copyright 2023
Greetings to Our Clients
2. © Copyright 2023
ABOUT US
OIL AND GAS
INDUSTRIAL MANUFACTURING
POWER PLANT
BUILDING AND STORAGE
01
02
03
04
ANGGOTAAN NFPA DENGAN PRODUK SERTIFIKASI
BIDANG SUPPLAI
SEJAK 1990 HINGGA SAAT INI KAMI MERUPAKAN
PT. Trimitra Wujud Rekanusa
General Supplier, Contractor, and Engineering
3. OUR PRODUCT
PT. Trimitra Wujud Rekanusa
General Supplier, Contractor, and Engineering
© Copyright 2023
01
02
03
04
05
06 FIRE EQUIPMENT CABINET
Brand Prancis spesialis
Fire Hose
Brand Singapura spesialis
Peralatan Hydrant Pillar
Brand India spesialis Fire Fighting
Equipment
Brand India spesialis Peralatan
Fire Protection
Brand Jerman spesialis Peralatan
Foam Proportioner & Monitor
Brand Local, Indonesia
Trimitra Design Cabinet
SOLE AGENT BEBERAPA BRAND PRODUK
4. OUR PRODUCT
PT. Trimitra Wujud Rekanusa
General Supplier, Contractor, and Engineering
© Copyright 2023
Foam Proportioner Pump
Foam Proportioner Pump for Brigade
Fire Foam/Water Monitor
APPROVAL PRODUK
5. EXIST DATA
PT. Trimitra Wujud Rekanusa
General Supplier, Contractor, and Engineering
© Copyright 2023
Posisi Pompa Foam
Proportioner Existing
6. EXIST DATA
PT. Trimitra Wujud Rekanusa
General Supplier, Contractor, and Engineering
© Copyright 2023
Parameter Design Kebutuhan Foam Proportioner :
Kebutuhan berdasarkan Tanki/Hazard terbesar yang ada,
(Butuh Data : Ukuran Diamater dan Tinggi Tanki terbesar)
Jenis material yang diproteksi,
Material Hydrocarbon menggunakan Foam Concentrate AFFF, AR-AFFF, FP, and
FFFP types dianjurkan AFFF 3%. (Reff. NFPA 11 & UL168)
Kapasitas Fire Pump yang ada,
Kapasitas fire pump dapat mengakomodir unit foam proportioner yang ada.
(Reff. NFPA 11)
Posisi Foam Proportioner harus lebih dekat dengan area Hazard,
Menghindari pengoperasian atau HAZOP yang lama dan seharusnya sesuai
kapasitas yang disediakan. (Reff. NFPA 11 & NFPA 16)
Tekanan dan Laju Aliran tidak melebihi kapasitas yang dibutuhkan
Aliran yang mengalir tidak melebihi kecepatan 3 m/s, dengan tekanan max.
pada 7bar (Hydraulic Calculation by Client)
7. EXIST DATA
PT. Trimitra Wujud Rekanusa
General Supplier, Contractor, and Engineering
© Copyright 2023
Spesifikasi sementara untuk unit Foam Proportioner :
Pipe Size menuju unit Foam Chamber adalah 6inch dari Header 8inch
Jumlah Outlet Foam Discharge berdasarkan Layout 3 line
8. SPECIFICATION OF UNIT
PT. Trimitra Wujud Rekanusa
General Supplier, Contractor, and Engineering
© Copyright 2023
Type : FD6000/3-S GEN III
Flowrate : 550 – 6000 LPM
Proportioning Rate : Fixed 3% AFFF
Rotating Rate : 750 RPM (8L per Rotasi)
Oil Type : SAE 10W40 (±3 liter)
Cap. To Filling Shed : 3 ea of Foam Chamber inlet 3inch (80NB) or FCA-80
or 1 ea of Foam Chamber inlet 6inch (150NB – FCA-150)
9. METHOD OF WORK
PT. Trimitra Wujud Rekanusa
General Supplier, Contractor, and Engineering
© Copyright 2023
1) Pembongkaran unit existing Inline Balance Proportioner (IBP), Electric Motor, dan piping ke Foam Tank.
2) Pembongkaran piping yang ada hingga tie-in dengan size 8” (Y-Strainer dan Gate Valve size 8inch layak dipakai)
3) Pesiapkan pondasi pompa unit FireDos dan Piping dari Hydrant Ring-Inlet menuju Outlet-Header Foam size 8inch.
4) Instalasi pipe fitting sesuai kebutuhan FireDos (DWG atas). Penggunaan part Y-Strainer, Gate Valve, spool test line,
Pressure Gauge, Flexible Joint, material Carbon Steel, ANSI #150, ASME A53 GrB, etc.
5) Pemeriksaan kondisi Foam Storage (nozzle Tanki sesuai kebutuhan) dan kualitas Foam, dan koneksi foam piping ke
unit FireDos. Penggunaan part untuk Inlet dan Return line, material min. SS304, welded or BSP Threaded, complete
with Ball Valve 2.5” & 1.5”.
- Pastikan dilakukan NDT Dye Pentrant untuk joint weld dan hydrotest, tidak terdapat kebocoran.
- Lakukan flushing dahulu sebelum pengoperasian atau commissioning
10. METHOD OF WORK
PT. Trimitra Wujud Rekanusa
General Supplier, Contractor, and Engineering
© Copyright 2023
Detail Size dan kebutuhan dapat diperoleh setelah
pelaksanaan Survey on Site
11. PRODUCT OF FIREDOS FIXED PROP.
PT. Trimitra Wujud Rekanusa
General Supplier, Contractor, and Engineering
© Copyright 2023
WATERMOTOR
flange ASME B16.5, 8" Class 150
12. PRODUCT OF FIREDOS FIXED PROP.
PT. Trimitra Wujud Rekanusa
General Supplier, Contractor, and Engineering
© Copyright 2023
COUPLING
13. PRODUCT OF FIREDOS FIXED PROP.
PT. Trimitra Wujud Rekanusa
General Supplier, Contractor, and Engineering
© Copyright 2023
PROPORTIONING PUMP
2.1/2" FT BSP
14. PRODUCT OF FIREDOS FIXED PROP.
PT. Trimitra Wujud Rekanusa
General Supplier, Contractor, and Engineering
© Copyright 2023
PIPING
1.1/2" FT BSP
15. CARA KERJA FIREDOS
PT. Trimitra Wujud Rekanusa
General Supplier, Contractor, and Engineering
© Copyright 2023
16. SAMPLE OF INSTALLATION
PT. Trimitra Wujud Rekanusa
General Supplier, Contractor, and Engineering
© Copyright 2023
V1
V4
V3
V5
V6 V2
17. FOAM PACKAGE OPERATION
PT. Trimitra Wujud Rekanusa
General Supplier, Contractor, and Engineering
© Copyright 2023
No. Item STAND BY MAINTENANCE EMERGENCY
V1 Ball Valve size 4inch sebelum unit Firedos NO NO NO
V2 Flushing Valve NC NC NC
V3 3-Ways Ball FireDos R R P
V4 Foam Tank Ball Valve NO NO NO
V5 Ball Valve size 4inch sesudah unit Firedos NO NO NO
V6 Ball Valve size 4inch sebelum Filling Shed NC NO NO
NO : Normally Open
NC : Normally Closed
R : Return To Foam Tank
P : Priming Inject Foam
18. TEST & COMMISSIONING
PT. Trimitra Wujud Rekanusa
General Supplier, Contractor, and Engineering
© Copyright 2023
1. Pre-Test Commissioning akan dilaksanakan sesuai dokumen prosedur yang akan diberikan dan
telah approved. Pengoperasian sistem akan memastikan unit mampu beroperasi dan telah
diintegrasikan dengan sistem hydrant pipe ring yang ada.
Pada tahapan ini, pengoperasian hanya menggunakan air (Water Only) tanpa Foam
Concentrate
2. Test Commissioning akan dilaksanakan sesuai dengan dokumen prosedur yang akan diberikan dan
telah approved. Kegiatan akan dilakasanakan dengan menggunakan Foam Concentrate AFFF 3%
existing yang disediakan oleh pihak USER (PT PERTAMINA PATRA NIAGA – FT TASIKMALAYA)
Adapun parameter ACCEPTANCE CRITERIA sistem nantinya, unit dapat menghasilkan Foam lulus uji,
yaitu metode Metode Refference NFPA 11 – PERCENTAGE RATE 3% dengan Pengoperasian
Kondisi Emergency
19. PT. TRIMITRA WUJUD REKANUSA
© Copyright 2023
MAIN OFFICE PT. TRIMITRA WUJUD REKANUSA
Jl. Gunung Sahari Raya No. 51/8
Jakarta 10610 - INDONESIA
Phone : +62 21 422 7632
Fax : +62 21 422 7647
Email : admin@trimitragroup.co.id
Website : www.trimitragroup.co.id
SALES &
MARKETING email : sales@trimitragroup.co.id
TECHNICAL &
ENGINEERING email : engineering@trimitragroup.co.id
Hubungi kami di,