SCOPE STATEMENT
I would like to build your garage at your standards.
That will include being built in a timely manner. Your
recommendations will be taken serious. We will try to
accommodate your request of changes to the best of
our ability, without changing the time line. We will
base the cost of the project to be set at around 12,000
dollars and take about 3 months to build giving the
weather is good .
Building a Garage step by step
PLANNING
Planning
1. Area
• look for flooding
• sloping of the land
• surveyed
2.Get permits
3.Order material
4.Hire workers
5.Get tools
Development
6.Layout the area with chalk
7.Dig holes (10)
Execution
8.Set poles with concrete
• Smooth put area
• Frame up the footer
• Lay wire mess
• Deliver concert
• Poor concrete
9. Put up trusses
• deliver trusses
• hang trusses
• lay plywood
• lay sheath
• lay felt
• put shingles on
10. Frame up the side
11. Put ply wood on outside walls
Final
12. Install window
13. Install electric
14. Install garage door and man door
Prints
COMMUNICATION PLAN
Communication Method Meduim Facilitator Participants Purpose Frequency
Weekly status report E-mail Project manager RB and BT
to update the status of
all activities,reports on
those activities
expected to be
accomplished in the
next week
Weekly
Project Meeting
Conference call
/face to face
Project manager
PM/RB
Supervisor/ET
to initiate the
eprojectand the
progress and
resolve any issues
Daily
Notification/Communication
s
E-mail Anyone Anyone
To maintain the
progress of the
implemention and
coordinate project
issues
As Required
End of day Meeting
Face to
Face/Phone call
Project manager Supervisor/ET
to discusse the
issues of the day
and where to start
tomorrow
Daily
RESOURCES
Unit of Cost
(hour,day,week
, month Fixed)
Level of
Risk High,
Medium,
or Low
Resource
skill level
or Material
Quality
Associated Tasks
Duration
Required
Available
Time
Required
Cost
HOURS
MIKE 15 yrs.
SUPERVISOR/WORKE
R 2 month 52.00 $20.00
$1,040.00 LOW
DAN 10yrs LEAD MAN 2 month 50.75 $18.00 $913.50 LOW
JOE 1yr LABOR 2 month 50.75 $15.00 $761.25 MEDIUM
JIM 1yr LABOR 2 month 50.75 $15.00 $761.25 MEDIUM
DOUG 1yr LABOR 2 month 50.75 $15.00 $761.25 MEDIUM
Total Labor 255.00 $83.00 $4,237.25
HOMDEPOT 30 yrs. Materials 1 Day $3,892.00 MEDIUM
Grays
Electrical 10 yrs.
Installation
1 Day 8 $55.00 $440.00
MEDIUM
Garage
Doors/Windo
w's R US
15 yrs. Installation 1 Day 8 $1,369.00 MEDIUM
twin city
concret Delivery/Materials 1 Day 2
$1,050.00
MEDIUM
stark trusses Delivery/Materials 1 Day 1 $300.00
MEDIUM
Total $11,288.25
RISK ANALYSIS
Risk Analysis
1 funding
2 weather
3 labor
4 on time delivery
likely hood
low med high
effect
low
med 3
high 1 4 2
I am excepting the risk.the highest one is the
weather so I will keep my eye on the weather and
purchase a tarp just in case.
WBS PHASE 1
FLOORING PHASE 1
WIRE MESS 6X6 W1.4XW1.4 576.00 sf $10.30 $206.00 576/SF7.25/42*84
POST 4X4 8’ 2.00 ea. $7.77 $15.54
POST 4X4 8’ 2.00 ea. $7.77 $15.54 2/EA7.77
POST 4X4 4’ 1.00 ea. $7.77 $7.77 1/EA7.77
POST 4X4 9’ 1.00 ea. $12.70 $12.70 1/EA12.70
POST 4X4 11’ 1.00 ea. $14.20 $14.20 1/EA
CONCRETE (FOOTING) 12”X6” 1.78 cy $90.00 $160.20
CONCRETE (STEM) 6”X 20” 2.96 cy $90.00 $266.40
CONC. FTING(DOORWAY SLAB)(1) 48”X48”X4” DP 0.20 cy $90.00 $18.00
2*4 2*4 12' 100.00 ft $0.89 $89.00
CONC. FTING (RIDGE SUPPORT)(1) 26”X 26” X 12” DP 0.17 cy $75.00 $12.75
CONC. FTING (GARAGE DOOR)(2) 20”X20”X10” DP 0.17 cy $75.00 $12.75
CONCRETE (FLOOR) 4” 7.11 cy $75.00 $533.25
TOTAL MATERIAL $1,364.10 TOTAL
TOTAL LABOR HOUR 5.00 DAYS 16.00 2DAYS $83.00 $1,577.00 $2,941.10
WBS PHASE 2
ITEM: SIZE: LENGTH: NEEDED DESCRIPT PRICE TOTAL
ROOF PHASE 2
H2.5 RAFTER TIE 16’ 38.00 ea. $0.84 $31.92
ROOF SHEATH 1/2” CDX 956.00 sf $0.11 $154.00 700sf roll
ROOF FELT 30# FELT 956.00 sf $0.11 $118.80 216 sf roll
2*4 2*4 12' 50.00 ft $0.89 $44.50
ROOFING shingles 956.00 sf $10.26 $307.80 956/SF/27.0 21/bundle 3bundle per 100sf
BARGE RAFTERS 2X6 19’ 4.00 ea. $6.97 $27.88
HEADER (INT MAIN DOOR) 4X8 1.00 ea. $45.00 $45.00
HEADER (MAIN WINDOW) 4X10 7’ 1.00 ea. $55.00 $55.00
TRUSSES 38.00 ea. $4.50 $171.00
TOTAL MATERIALS $955.90 TOTAL
TOTAL LABOR HOUR 5.00 DAYS 14.00 HRS $83.00 $1,162.00 $2,117.90
WBS PHASE 3 &4
ITEM: SIZE: LENGTH: NEEDED DESCRIPT PRICE TOTAL PHASE 3
FRAMING PHASE3
EXT WALL SHEATH ½” CDX 981.00 sf $0.11 $154.00 981/SF.11/700sf
EXT WALL VAPOR 15# FELT 981.00 sf $0.12 $155.52 981/SF15.15 432sf
MAIN EXT STUDS 2X6 95.13 57.00 ea. $2.49 $141.93
UPPER INT PLATES 2X4 144.00 lf $0.15 $21.60
Cement 60lb 10.00 bg $3.99 $39.90
UPPER INT WALL STUDS 2X4 5’ 37.00 EA $4.05 $149.85
PLYWOOD 4*8 150.00 EA $1.25 $187.50
HEADER(MAIN GAR DOOR) 5-1/8X15 GLB 17’ 1.00 EA $54.56 $54.56
2*4 2*4 12' 75.00 ft $0.89 $66.75
JOISTS 16 TJI 360 24’ 19.00 ea. $3.00 $57.00
RIM JOIST 96.00 lf $0.86 $82.56 96/LF19.0
TOTAL MATERIALS $1,111.17 TOTAL
TOTAL LABOR HOUR 5.00 DAYS 19.00 HR $83.00 $1,577.00 $2,688.17
ELECTRICIAN PHASE 4
install electricity and run power 8.00 hr. $55.00 $440.00
install electricity out lets TOTAL
TOTAL LABOR HOUR 8.00 hr. $55.00 $440.00 440.00
WBS 4.5
INSTALLATION/WORKERS
Installation PHASE 4.5
Garage door installation $1,030.00
window installation $495.00 TOTAL
Man door $590.00 $2,115.00
WORKERS RATE/HR T/H T/C
SPONSER BT
PM RB
SUPERVISOR/WORKER MIKE $20.00 52.00 $1,040.00
LEAD MAN DAN $18.00 50.75 $913.50
LABOR JOE $15.00 50.75 $761.25
LABOR JIM $15.00 50.75 $761.25
LABOR DOUG $15.00 50.75 $761.25
TOTAL $83.00 255.00 $4,237.25
COSTS BREAKDOWN CHART
Task Laborcost Cost of materials Totalprice Share of cost (%)
Roof(asphaltshingles) $1,162.00 $955.90 $2,117.90 19%
Framing $1,577.00 $1,111.17 $2,688.17 24%
Electricity $440.00 $440.00 4%
Delivery $525.00 5%
Other $461.44 $461.44 4%
TOTAL $6,871.00 $3,892.61 $11,288.61 100%
Garage constructioncosts breakdownchart1
Concrete and foundation $1,577.00 $1,364.10 $2,941.10 26%
Garage door (1) window(1)
ManDoor (1)
$2,115.00 $2,115.00 19%
TASK USAGE
TASK USAGE
TASK USAGE
TASK SHEET
GANTT CHART
Finished Product

More Related Content

What's hot

Project management in construction
Project management in constructionProject management in construction
Project management in constructionNAVNEET KUMAR JHA
 
Complete design of r.c.c over head tank & boq estimate
Complete design of r.c.c over head tank & boq estimateComplete design of r.c.c over head tank & boq estimate
Complete design of r.c.c over head tank & boq estimateHarish Mahavar
 
5 Steps Of Project Scheduling Process For Absolute Beginners
5 Steps Of Project Scheduling Process For Absolute Beginners5 Steps Of Project Scheduling Process For Absolute Beginners
5 Steps Of Project Scheduling Process For Absolute BeginnersPraveen Malik, PMP
 
Practical Project Cost Control for Large Complex Projects
Practical Project Cost Control for Large Complex ProjectsPractical Project Cost Control for Large Complex Projects
Practical Project Cost Control for Large Complex ProjectsJeremie Averous
 
8. implementation (2) cost management
8. implementation (2)   cost management8. implementation (2)   cost management
8. implementation (2) cost managementDania Abdel-aziz
 
HydroMax™ Siphonic (Syphonic) Roof Drainage
HydroMax™ Siphonic (Syphonic) Roof DrainageHydroMax™ Siphonic (Syphonic) Roof Drainage
HydroMax™ Siphonic (Syphonic) Roof DrainageHydroMax Inc. Limited
 
Interceptors and manholes
Interceptors and manholesInterceptors and manholes
Interceptors and manholesJem Ganacia
 
What is a Work Breakdown Structure?
What is a Work Breakdown Structure?What is a Work Breakdown Structure?
What is a Work Breakdown Structure?Kenny Hirschmann
 
204310 use of unifier with primavera
204310 use of unifier with primavera204310 use of unifier with primavera
204310 use of unifier with primaverap6academy
 
Construction Project Management Class Project Presentation
Construction Project Management Class Project PresentationConstruction Project Management Class Project Presentation
Construction Project Management Class Project PresentationWayne Holley
 
Caissons_Advanced Construction Technology (Semester-6), Civil Engineering
Caissons_Advanced Construction Technology (Semester-6), Civil EngineeringCaissons_Advanced Construction Technology (Semester-6), Civil Engineering
Caissons_Advanced Construction Technology (Semester-6), Civil EngineeringA Makwana
 
Plumbing presentation by Jose Anacleto Soberano
Plumbing presentation by Jose Anacleto SoberanoPlumbing presentation by Jose Anacleto Soberano
Plumbing presentation by Jose Anacleto SoberanoEsOj Soberano
 
Cast Iron and Galvanized Iron Pipes
Cast Iron and Galvanized Iron PipesCast Iron and Galvanized Iron Pipes
Cast Iron and Galvanized Iron PipesAkshay Dhimate
 
Preliminary Scope Statement Template
Preliminary Scope Statement TemplatePreliminary Scope Statement Template
Preliminary Scope Statement TemplateMelanieRos
 
CE223-%20plumbing%20fixtures.pptx
CE223-%20plumbing%20fixtures.pptxCE223-%20plumbing%20fixtures.pptx
CE223-%20plumbing%20fixtures.pptxSabreDButito
 
Construction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project ManagementConstruction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project Managementsrinivas2036
 

What's hot (20)

Project management in construction
Project management in constructionProject management in construction
Project management in construction
 
Complete design of r.c.c over head tank & boq estimate
Complete design of r.c.c over head tank & boq estimateComplete design of r.c.c over head tank & boq estimate
Complete design of r.c.c over head tank & boq estimate
 
5 Steps Of Project Scheduling Process For Absolute Beginners
5 Steps Of Project Scheduling Process For Absolute Beginners5 Steps Of Project Scheduling Process For Absolute Beginners
5 Steps Of Project Scheduling Process For Absolute Beginners
 
Practical Project Cost Control for Large Complex Projects
Practical Project Cost Control for Large Complex ProjectsPractical Project Cost Control for Large Complex Projects
Practical Project Cost Control for Large Complex Projects
 
House plumbing
House plumbingHouse plumbing
House plumbing
 
Project Charter
Project CharterProject Charter
Project Charter
 
Work Breakdown Structure
Work Breakdown StructureWork Breakdown Structure
Work Breakdown Structure
 
8. implementation (2) cost management
8. implementation (2)   cost management8. implementation (2)   cost management
8. implementation (2) cost management
 
HydroMax™ Siphonic (Syphonic) Roof Drainage
HydroMax™ Siphonic (Syphonic) Roof DrainageHydroMax™ Siphonic (Syphonic) Roof Drainage
HydroMax™ Siphonic (Syphonic) Roof Drainage
 
Shallow foundation
Shallow foundationShallow foundation
Shallow foundation
 
Interceptors and manholes
Interceptors and manholesInterceptors and manholes
Interceptors and manholes
 
What is a Work Breakdown Structure?
What is a Work Breakdown Structure?What is a Work Breakdown Structure?
What is a Work Breakdown Structure?
 
204310 use of unifier with primavera
204310 use of unifier with primavera204310 use of unifier with primavera
204310 use of unifier with primavera
 
Construction Project Management Class Project Presentation
Construction Project Management Class Project PresentationConstruction Project Management Class Project Presentation
Construction Project Management Class Project Presentation
 
Caissons_Advanced Construction Technology (Semester-6), Civil Engineering
Caissons_Advanced Construction Technology (Semester-6), Civil EngineeringCaissons_Advanced Construction Technology (Semester-6), Civil Engineering
Caissons_Advanced Construction Technology (Semester-6), Civil Engineering
 
Plumbing presentation by Jose Anacleto Soberano
Plumbing presentation by Jose Anacleto SoberanoPlumbing presentation by Jose Anacleto Soberano
Plumbing presentation by Jose Anacleto Soberano
 
Cast Iron and Galvanized Iron Pipes
Cast Iron and Galvanized Iron PipesCast Iron and Galvanized Iron Pipes
Cast Iron and Galvanized Iron Pipes
 
Preliminary Scope Statement Template
Preliminary Scope Statement TemplatePreliminary Scope Statement Template
Preliminary Scope Statement Template
 
CE223-%20plumbing%20fixtures.pptx
CE223-%20plumbing%20fixtures.pptxCE223-%20plumbing%20fixtures.pptx
CE223-%20plumbing%20fixtures.pptx
 
Construction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project ManagementConstruction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project Management
 

Similar to Building a garage

Capstone Presentation
Capstone PresentationCapstone Presentation
Capstone PresentationJosue Campos
 
Best practices day one new morning
Best practices day one new morningBest practices day one new morning
Best practices day one new morningAhmed Radwan
 
Best practices day 1 am new
Best practices day 1 am newBest practices day 1 am new
Best practices day 1 am newAhmed Radwan
 
This One House Project Group 4
This One House Project Group 4This One House Project Group 4
This One House Project Group 4Nicky Chao
 
Project 3 - Costing
Project 3 - CostingProject 3 - Costing
Project 3 - CostingKai Yun Pang
 
Final project Estimating
Final project EstimatingFinal project Estimating
Final project EstimatingRonald Rhodes
 
UG191079_Pruthviraj Vaghela_Midterm Assignment.pptx
UG191079_Pruthviraj Vaghela_Midterm Assignment.pptxUG191079_Pruthviraj Vaghela_Midterm Assignment.pptx
UG191079_Pruthviraj Vaghela_Midterm Assignment.pptxPruthvirajsinhVaghel2
 
Friend's School of Portland: Passive House Integrated Design
Friend's School of Portland: Passive House Integrated DesignFriend's School of Portland: Passive House Integrated Design
Friend's School of Portland: Passive House Integrated Designkaplanthompson
 
Laboratory Instruction Manual for Civil Engineers
Laboratory Instruction Manual for Civil EngineersLaboratory Instruction Manual for Civil Engineers
Laboratory Instruction Manual for Civil EngineersPhurba Tamang
 
Jeep Contaminant Reduction- Phosphate Pretreatment
Jeep Contaminant Reduction- Phosphate PretreatmentJeep Contaminant Reduction- Phosphate Pretreatment
Jeep Contaminant Reduction- Phosphate PretreatmentJustin Stevenor
 
Creative Ways To Get New Athletic Fields
Creative Ways To Get New Athletic FieldsCreative Ways To Get New Athletic Fields
Creative Ways To Get New Athletic FieldsTom O'Rourke
 
Cool roof - How to choose one ?
Cool roof - How to choose one ?Cool roof - How to choose one ?
Cool roof - How to choose one ?Ranjan Aggarwal
 
Team Clean Machine Final
Team Clean Machine FinalTeam Clean Machine Final
Team Clean Machine Finaltaralv
 
Power point Burnt Inverted Earthen Pots Final 2018 01-3-18 Junaid.pptx
Power point  Burnt Inverted Earthen Pots Final 2018 01-3-18 Junaid.pptxPower point  Burnt Inverted Earthen Pots Final 2018 01-3-18 Junaid.pptx
Power point Burnt Inverted Earthen Pots Final 2018 01-3-18 Junaid.pptxhassanalizafar
 

Similar to Building a garage (20)

Man cave
Man caveMan cave
Man cave
 
Capstone Presentation
Capstone PresentationCapstone Presentation
Capstone Presentation
 
Best practices day one new morning
Best practices day one new morningBest practices day one new morning
Best practices day one new morning
 
Best practices day 1 am new
Best practices day 1 am newBest practices day 1 am new
Best practices day 1 am new
 
Cost Reduction Project
Cost Reduction ProjectCost Reduction Project
Cost Reduction Project
 
Bill Of Quantities
Bill Of QuantitiesBill Of Quantities
Bill Of Quantities
 
This One House Project Group 4
This One House Project Group 4This One House Project Group 4
This One House Project Group 4
 
Project 3 - Costing
Project 3 - CostingProject 3 - Costing
Project 3 - Costing
 
Final project Estimating
Final project EstimatingFinal project Estimating
Final project Estimating
 
UG191079_Pruthviraj Vaghela_Midterm Assignment.pptx
UG191079_Pruthviraj Vaghela_Midterm Assignment.pptxUG191079_Pruthviraj Vaghela_Midterm Assignment.pptx
UG191079_Pruthviraj Vaghela_Midterm Assignment.pptx
 
Transitional refugee housing
Transitional refugee housingTransitional refugee housing
Transitional refugee housing
 
Friend's School of Portland: Passive House Integrated Design
Friend's School of Portland: Passive House Integrated DesignFriend's School of Portland: Passive House Integrated Design
Friend's School of Portland: Passive House Integrated Design
 
Laboratory Instruction Manual for Civil Engineers
Laboratory Instruction Manual for Civil EngineersLaboratory Instruction Manual for Civil Engineers
Laboratory Instruction Manual for Civil Engineers
 
Jeep Contaminant Reduction- Phosphate Pretreatment
Jeep Contaminant Reduction- Phosphate PretreatmentJeep Contaminant Reduction- Phosphate Pretreatment
Jeep Contaminant Reduction- Phosphate Pretreatment
 
Creative Ways To Get New Athletic Fields
Creative Ways To Get New Athletic FieldsCreative Ways To Get New Athletic Fields
Creative Ways To Get New Athletic Fields
 
Cool roof - How to choose one ?
Cool roof - How to choose one ?Cool roof - How to choose one ?
Cool roof - How to choose one ?
 
Heat Transfer Project
Heat Transfer ProjectHeat Transfer Project
Heat Transfer Project
 
Team Clean Machine Final
Team Clean Machine FinalTeam Clean Machine Final
Team Clean Machine Final
 
PARADISE ESTIMATING
PARADISE ESTIMATINGPARADISE ESTIMATING
PARADISE ESTIMATING
 
Power point Burnt Inverted Earthen Pots Final 2018 01-3-18 Junaid.pptx
Power point  Burnt Inverted Earthen Pots Final 2018 01-3-18 Junaid.pptxPower point  Burnt Inverted Earthen Pots Final 2018 01-3-18 Junaid.pptx
Power point Burnt Inverted Earthen Pots Final 2018 01-3-18 Junaid.pptx
 

More from Reese Boone

Leadership manual presentation
Leadership manual presentationLeadership manual presentation
Leadership manual presentationReese Boone
 
PROJECT RISK MANAGEMENT
PROJECT RISK MANAGEMENTPROJECT RISK MANAGEMENT
PROJECT RISK MANAGEMENTReese Boone
 
Project Situation
Project SituationProject Situation
Project SituationReese Boone
 
Project global systems development corporation
Project global systems development corporationProject global systems development corporation
Project global systems development corporationReese Boone
 
Darpa final paper
Darpa final paperDarpa final paper
Darpa final paperReese Boone
 
Final research paper
Final research paperFinal research paper
Final research paperReese Boone
 
Project Machine Shop
Project Machine ShopProject Machine Shop
Project Machine ShopReese Boone
 
Updating Equipment
Updating EquipmentUpdating Equipment
Updating EquipmentReese Boone
 

More from Reese Boone (9)

TEAM LEADERSHIP
TEAM LEADERSHIPTEAM LEADERSHIP
TEAM LEADERSHIP
 
Leadership manual presentation
Leadership manual presentationLeadership manual presentation
Leadership manual presentation
 
PROJECT RISK MANAGEMENT
PROJECT RISK MANAGEMENTPROJECT RISK MANAGEMENT
PROJECT RISK MANAGEMENT
 
Project Situation
Project SituationProject Situation
Project Situation
 
Project global systems development corporation
Project global systems development corporationProject global systems development corporation
Project global systems development corporation
 
Darpa final paper
Darpa final paperDarpa final paper
Darpa final paper
 
Final research paper
Final research paperFinal research paper
Final research paper
 
Project Machine Shop
Project Machine ShopProject Machine Shop
Project Machine Shop
 
Updating Equipment
Updating EquipmentUpdating Equipment
Updating Equipment
 

Recently uploaded

Digital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxDigital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxpritamlangde
 
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...ronahami
 
8086 Microprocessor Architecture: 16-bit microprocessor
8086 Microprocessor Architecture: 16-bit microprocessor8086 Microprocessor Architecture: 16-bit microprocessor
8086 Microprocessor Architecture: 16-bit microprocessorAshwiniTodkar4
 
Post office management system project ..pdf
Post office management system project ..pdfPost office management system project ..pdf
Post office management system project ..pdfKamal Acharya
 
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...HenryBriggs2
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startQuintin Balsdon
 
Memory Interfacing of 8086 with DMA 8257
Memory Interfacing of 8086 with DMA 8257Memory Interfacing of 8086 with DMA 8257
Memory Interfacing of 8086 with DMA 8257subhasishdas79
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdfKamal Acharya
 
Introduction to Geographic Information Systems
Introduction to Geographic Information SystemsIntroduction to Geographic Information Systems
Introduction to Geographic Information SystemsAnge Felix NSANZIYERA
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.Kamal Acharya
 
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwaitjaanualu31
 
fitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .pptfitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .pptAfnanAhmad53
 
👉 Yavatmal Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top Class Call Girl S...
👉 Yavatmal Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top Class Call Girl S...👉 Yavatmal Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top Class Call Girl S...
👉 Yavatmal Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top Class Call Girl S...manju garg
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"mphochane1998
 
Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network DevicesChandrakantDivate1
 
Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...
Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...
Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...ssuserdfc773
 
Electromagnetic relays used for power system .pptx
Electromagnetic relays used for power system .pptxElectromagnetic relays used for power system .pptx
Electromagnetic relays used for power system .pptxNANDHAKUMARA10
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdfKamal Acharya
 

Recently uploaded (20)

Digital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxDigital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptx
 
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...
 
8086 Microprocessor Architecture: 16-bit microprocessor
8086 Microprocessor Architecture: 16-bit microprocessor8086 Microprocessor Architecture: 16-bit microprocessor
8086 Microprocessor Architecture: 16-bit microprocessor
 
Post office management system project ..pdf
Post office management system project ..pdfPost office management system project ..pdf
Post office management system project ..pdf
 
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
Memory Interfacing of 8086 with DMA 8257
Memory Interfacing of 8086 with DMA 8257Memory Interfacing of 8086 with DMA 8257
Memory Interfacing of 8086 with DMA 8257
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdf
 
Introduction to Geographic Information Systems
Introduction to Geographic Information SystemsIntroduction to Geographic Information Systems
Introduction to Geographic Information Systems
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.
 
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
 
fitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .pptfitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .ppt
 
👉 Yavatmal Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top Class Call Girl S...
👉 Yavatmal Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top Class Call Girl S...👉 Yavatmal Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top Class Call Girl S...
👉 Yavatmal Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top Class Call Girl S...
 
Signal Processing and Linear System Analysis
Signal Processing and Linear System AnalysisSignal Processing and Linear System Analysis
Signal Processing and Linear System Analysis
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
 
Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network Devices
 
Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...
Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...
Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...
 
Electromagnetic relays used for power system .pptx
Electromagnetic relays used for power system .pptxElectromagnetic relays used for power system .pptx
Electromagnetic relays used for power system .pptx
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdf
 

Building a garage

  • 2. SCOPE STATEMENT I would like to build your garage at your standards. That will include being built in a timely manner. Your recommendations will be taken serious. We will try to accommodate your request of changes to the best of our ability, without changing the time line. We will base the cost of the project to be set at around 12,000 dollars and take about 3 months to build giving the weather is good .
  • 3. Building a Garage step by step PLANNING Planning 1. Area • look for flooding • sloping of the land • surveyed 2.Get permits 3.Order material 4.Hire workers 5.Get tools Development 6.Layout the area with chalk 7.Dig holes (10) Execution 8.Set poles with concrete • Smooth put area • Frame up the footer • Lay wire mess • Deliver concert • Poor concrete 9. Put up trusses • deliver trusses • hang trusses • lay plywood • lay sheath • lay felt • put shingles on 10. Frame up the side 11. Put ply wood on outside walls Final 12. Install window 13. Install electric 14. Install garage door and man door
  • 5. COMMUNICATION PLAN Communication Method Meduim Facilitator Participants Purpose Frequency Weekly status report E-mail Project manager RB and BT to update the status of all activities,reports on those activities expected to be accomplished in the next week Weekly Project Meeting Conference call /face to face Project manager PM/RB Supervisor/ET to initiate the eprojectand the progress and resolve any issues Daily Notification/Communication s E-mail Anyone Anyone To maintain the progress of the implemention and coordinate project issues As Required End of day Meeting Face to Face/Phone call Project manager Supervisor/ET to discusse the issues of the day and where to start tomorrow Daily
  • 6. RESOURCES Unit of Cost (hour,day,week , month Fixed) Level of Risk High, Medium, or Low Resource skill level or Material Quality Associated Tasks Duration Required Available Time Required Cost HOURS MIKE 15 yrs. SUPERVISOR/WORKE R 2 month 52.00 $20.00 $1,040.00 LOW DAN 10yrs LEAD MAN 2 month 50.75 $18.00 $913.50 LOW JOE 1yr LABOR 2 month 50.75 $15.00 $761.25 MEDIUM JIM 1yr LABOR 2 month 50.75 $15.00 $761.25 MEDIUM DOUG 1yr LABOR 2 month 50.75 $15.00 $761.25 MEDIUM Total Labor 255.00 $83.00 $4,237.25 HOMDEPOT 30 yrs. Materials 1 Day $3,892.00 MEDIUM Grays Electrical 10 yrs. Installation 1 Day 8 $55.00 $440.00 MEDIUM Garage Doors/Windo w's R US 15 yrs. Installation 1 Day 8 $1,369.00 MEDIUM twin city concret Delivery/Materials 1 Day 2 $1,050.00 MEDIUM stark trusses Delivery/Materials 1 Day 1 $300.00 MEDIUM Total $11,288.25
  • 7. RISK ANALYSIS Risk Analysis 1 funding 2 weather 3 labor 4 on time delivery likely hood low med high effect low med 3 high 1 4 2 I am excepting the risk.the highest one is the weather so I will keep my eye on the weather and purchase a tarp just in case.
  • 8. WBS PHASE 1 FLOORING PHASE 1 WIRE MESS 6X6 W1.4XW1.4 576.00 sf $10.30 $206.00 576/SF7.25/42*84 POST 4X4 8’ 2.00 ea. $7.77 $15.54 POST 4X4 8’ 2.00 ea. $7.77 $15.54 2/EA7.77 POST 4X4 4’ 1.00 ea. $7.77 $7.77 1/EA7.77 POST 4X4 9’ 1.00 ea. $12.70 $12.70 1/EA12.70 POST 4X4 11’ 1.00 ea. $14.20 $14.20 1/EA CONCRETE (FOOTING) 12”X6” 1.78 cy $90.00 $160.20 CONCRETE (STEM) 6”X 20” 2.96 cy $90.00 $266.40 CONC. FTING(DOORWAY SLAB)(1) 48”X48”X4” DP 0.20 cy $90.00 $18.00 2*4 2*4 12' 100.00 ft $0.89 $89.00 CONC. FTING (RIDGE SUPPORT)(1) 26”X 26” X 12” DP 0.17 cy $75.00 $12.75 CONC. FTING (GARAGE DOOR)(2) 20”X20”X10” DP 0.17 cy $75.00 $12.75 CONCRETE (FLOOR) 4” 7.11 cy $75.00 $533.25 TOTAL MATERIAL $1,364.10 TOTAL TOTAL LABOR HOUR 5.00 DAYS 16.00 2DAYS $83.00 $1,577.00 $2,941.10
  • 9. WBS PHASE 2 ITEM: SIZE: LENGTH: NEEDED DESCRIPT PRICE TOTAL ROOF PHASE 2 H2.5 RAFTER TIE 16’ 38.00 ea. $0.84 $31.92 ROOF SHEATH 1/2” CDX 956.00 sf $0.11 $154.00 700sf roll ROOF FELT 30# FELT 956.00 sf $0.11 $118.80 216 sf roll 2*4 2*4 12' 50.00 ft $0.89 $44.50 ROOFING shingles 956.00 sf $10.26 $307.80 956/SF/27.0 21/bundle 3bundle per 100sf BARGE RAFTERS 2X6 19’ 4.00 ea. $6.97 $27.88 HEADER (INT MAIN DOOR) 4X8 1.00 ea. $45.00 $45.00 HEADER (MAIN WINDOW) 4X10 7’ 1.00 ea. $55.00 $55.00 TRUSSES 38.00 ea. $4.50 $171.00 TOTAL MATERIALS $955.90 TOTAL TOTAL LABOR HOUR 5.00 DAYS 14.00 HRS $83.00 $1,162.00 $2,117.90
  • 10. WBS PHASE 3 &4 ITEM: SIZE: LENGTH: NEEDED DESCRIPT PRICE TOTAL PHASE 3 FRAMING PHASE3 EXT WALL SHEATH ½” CDX 981.00 sf $0.11 $154.00 981/SF.11/700sf EXT WALL VAPOR 15# FELT 981.00 sf $0.12 $155.52 981/SF15.15 432sf MAIN EXT STUDS 2X6 95.13 57.00 ea. $2.49 $141.93 UPPER INT PLATES 2X4 144.00 lf $0.15 $21.60 Cement 60lb 10.00 bg $3.99 $39.90 UPPER INT WALL STUDS 2X4 5’ 37.00 EA $4.05 $149.85 PLYWOOD 4*8 150.00 EA $1.25 $187.50 HEADER(MAIN GAR DOOR) 5-1/8X15 GLB 17’ 1.00 EA $54.56 $54.56 2*4 2*4 12' 75.00 ft $0.89 $66.75 JOISTS 16 TJI 360 24’ 19.00 ea. $3.00 $57.00 RIM JOIST 96.00 lf $0.86 $82.56 96/LF19.0 TOTAL MATERIALS $1,111.17 TOTAL TOTAL LABOR HOUR 5.00 DAYS 19.00 HR $83.00 $1,577.00 $2,688.17 ELECTRICIAN PHASE 4 install electricity and run power 8.00 hr. $55.00 $440.00 install electricity out lets TOTAL TOTAL LABOR HOUR 8.00 hr. $55.00 $440.00 440.00
  • 11. WBS 4.5 INSTALLATION/WORKERS Installation PHASE 4.5 Garage door installation $1,030.00 window installation $495.00 TOTAL Man door $590.00 $2,115.00 WORKERS RATE/HR T/H T/C SPONSER BT PM RB SUPERVISOR/WORKER MIKE $20.00 52.00 $1,040.00 LEAD MAN DAN $18.00 50.75 $913.50 LABOR JOE $15.00 50.75 $761.25 LABOR JIM $15.00 50.75 $761.25 LABOR DOUG $15.00 50.75 $761.25 TOTAL $83.00 255.00 $4,237.25
  • 12. COSTS BREAKDOWN CHART Task Laborcost Cost of materials Totalprice Share of cost (%) Roof(asphaltshingles) $1,162.00 $955.90 $2,117.90 19% Framing $1,577.00 $1,111.17 $2,688.17 24% Electricity $440.00 $440.00 4% Delivery $525.00 5% Other $461.44 $461.44 4% TOTAL $6,871.00 $3,892.61 $11,288.61 100% Garage constructioncosts breakdownchart1 Concrete and foundation $1,577.00 $1,364.10 $2,941.10 26% Garage door (1) window(1) ManDoor (1) $2,115.00 $2,115.00 19%