4. Task Name Duration Start Finish
Planning 4.57 days Thu 3/19/15 Mon 3/30/15
Meet with client 5 days Tue 3/31/15 Mon 4/6/15
Interview Contractors 2 days Tue 3/31/15 Wed 4/1/15
check references 1 day Thu 4/2/15 Thu 4/2/15
hire contractor 1 day Fri 4/3/15 Fri 4/3/15
Permits 1 day Mon 4/6/15 Mon 4/6/15
Designer 2 days Mon 4/6/15 Tue 4/7/15
sign off of design 0.25 days Tue 4/7/15 Tue 4/7/15
Order Material 1 day Tue 4/7/15 Tue 4/7/15
Kick Off Meeting 0.38 days Wed 4/8/15 Wed 4/8/15
client sign off 0.25 days Wed 4/8/15 Wed 4/8/15
Executing 37 days Wed 4/8/15 Mon 6/1/15
Frame 7 days Wed 4/8/15 Fri 4/17/15
framing 4 days Wed 4/8/15 Wed 4/15/15
insulation 1 day Thu 4/16/15 Thu 4/16/15
client sign off 1 day Fri 4/17/15 Fri 4/17/15
Electrical 3 days Tue 4/21/15 Thu 4/23/15
pull coaxed cable 0.38 days Tue 4/21/15 Tue 4/21/15
receptacle's and boxes 0.5 days Wed 4/22/15 Wed 4/22/15
circuit breaker box 0.5 days Wed 4/22/15 Wed 4/22/15
client sign off 0.5 days Thu 4/23/15 Thu 4/23/15
Plumbing 2 days Fri 4/24/15 Mon 4/27/15
hot and cold water 2 days Fri 4/24/15 Mon 4/27/15
client sign off 1 day Tue 4/28/15 Tue 4/28/15
Order Material 1 day Tue 4/28/15 Tue 4/28/15
WBS
5. Task Name Duration Start Finish
Drywall 9 days Wed 4/29/15 Mon 5/11/15
ceiling 2.5 days Wed 4/29/15 Fri 5/1/15
interior walls 2.5 days Mon 5/4/15 Wed 5/6/15
tapping 1 day Thu 5/7/15 Thu 5/7/15
sanding 1 day Fri 5/8/15 Mon 5/11/15
client sign off 0.25 days Mon 5/11/15 Mon 5/11/15
Paint 3 days Tue 5/12/15 Thu 5/14/15
paint 3 days Mon 5/11/15 Thu 5/14/15
client sign off 0.5 days Thu 5/14/15 Fri 5/15/15
Order material 0.35 days Fri 5/15/15 Fri 5/15/15
Flooring 3 days Mon 5/18/15 Wed 5/20/15
installation 2 days Fri 5/15/15 Wed 5/20/15
client sign off 0.5 days Wed 5/20/15 Wed 5/20/15
Installation 3.38 days Thu 5/21/15 Wed 5/27/15
TV 0.25 days Thu 5/21/15 Thu 5/21/15
surround system 0.25 days Thu 5/21/15 Thu 5/21/15
bar and back 0.25 days Thu 5/21/15 Fri 5/22/15
sink and cabinet / toilet 1 day Tue 5/26/15 Tue 5/26/15
put on cover and light fixture 0.25 days Tue 5/26/15 Tue 5/26/15
seating 1 day Tue 5/26/15 Tue 5/26/15
client sign off 0.5 days Wed 5/27/15 Wed 5/27/15
Training 1 day Thu 5/28/15 Thu 5/28/15
entertainment system 0.13 days Thu 5/28/15 Thu 5/28/15
lightning system 0.5 days Thu 5/28/15 Thu 5/28/15
client sign off 1.25 days Thu 5/28/15 Fri 5/29/15
Closing 1 day Mon 6/1/15 Tue 6/2/15
WBS
6. COST ESTIMATION
Before Change
Task Labor cost
Cost of
materials
Total price Share of cost (%)
FRAMMER $1,200.00 $191.00 $1,391.00 5%
DRYWALL $1,100.00 $580.00 $1,680.00 7%
ELECTRICIAN $1,200.00 $1,200.00 5%
PLUMBIMG $1,000.00 $0.00 $1,000.00 4%
DESIGNER $500.00 $500.00 2%
OTHER $13,138.00 $13,138.00 51%
INSTALLER $450.00 $450.00 2%
PROFESSIONAL SERVICE $3,500.00 $3,500.00 14%
TOTAL $10,720.00 $14,910.00 $25,630.00 100%
CONSTINENGCY 10% $2,563.00 $28,193.00
MAN CAVE COST BREAKDOWN CHART
FLOORING $1,020.00 $804.00 $1,824.00 7%
PAINTER $750.00 $197.00 $947.00 4%
7. ITEM: SIZE: LENGTH: NEEDED DESCRIPT PRICE TOTAL
PLUMBING
CONTRACTED OUT 0.00 ea. $0.00 $0.00
0.00 sf $0.00 $0.00
TOTAL MATERIALS $0.00 TOTAL
TOTAL LABOR HOUR 0.00 DAYS 2.00 HRS $500.00 $1,000.00 $1,000.00
FLOORING/contracted
dark floor 17.00 bx $35.00 $595.00
TRIM 11.00 BX $19.00 $209.00
$0.00 $0.00
TOTAL MATERIAL $804.00 TOTAL
TOTAL CONTRACTOR 0.00 DAYS 340.00 3 DAYS $3.00 $1,020.00 $1,824.00
FRAMING/CONTRACTED
2*4*8 52.00 $3.00 $156.00 CONTRACT
INSULATION 5.00 $3.00 $15.00 $1,200.00
NAILS/FRAMMING 5.00 $4.00 $20.00 $191.00
TOTAL COST $1,391.00
DRYWALL/CONTRACTOR
WALLS 5/8 THICK 25.00 $10.00 $250.00 CONTRACT
CEILING 1/4 THICK 30.00 $10.00 $300.00 $1,100.00
NAILS DRYWALL 1.00 $14.00 $14.00 $580.00
MUDD 5GAL BUCKET 1.00 $10.00 $10.00
TAPE 3.00 $2.00 $6.00 $1,680.00
PAINT/CONTRACTOR $0.00 $0.00
PAINT 4.00 $30.00 $120.00 CONTRACT
PRIMER 5 GAL 1.00 $77.00 $77.00 $750.00
$0.00 $0.00 $197.00
TOTAL COST $947.00
ELECTRICIAN/CONTRACTOR
CONTRACTED OUT 2.00 Day $600.00 $1,200.00
TOTAL
TOTAL LABOR HOUR 0.00 hr. $1,200.00
MATERIAL
BREAKDOWN
8. OTHER MATERIALS
TV 1.00 ea. $2,700.00 $2,700.00
SURROUND SYSTEM 1.00 ea. $430.00 $430.00
PERMITS 1.00 ea. $500.00 $500.00
BAR 1.00 ea. $5,009.00 $5,009.00
BAR BAK 1.00 ea. $2,154.00 $2,154.00
SINK AND CABINET 459.0/39.00 1.00 ea. $498.00 $498.00
TOILET 1.00 sf $100.00 $100.00
LIGHT COVERS 15.00 ea. $2.00 $30.00
SAND PAPER 1.00 RL $3.00 $3.00
COUCH 1.00 box $1,500.00 $1,500.00
LIGHTS 2.00 box $107.00 $214.00
TOTAL ########
Installation
TECHNOLOGY/LIGHT $250.00 TOTAL
BAR $200.00 $450.00
WORKERS 1.00 ea. $0.00
PM $3,500.00
DESIGNER $500.00 $500.00
TOTAL 0.00 ########
MATERIAL
BREAKDOWN
9. MATERIALS LABOR TOTAL T/T T/L T/M
PLUMBING $0.00 $1,000.00 $1,000.00
FLO O RING $804.00 $1,020.00 $1,824.00
FRAMING $191.00 $1,200.00 $1,391.00
DRYWALL $580.00 $1,100.00 $1,680.00
PAINTER $197.00 $750.00 $947.00
PRO FESSIO NAL SERVICE $3,500.00 $3,500.00
DESIGNER $500.00 $500.00
ELECTRICIAN $1,200.00 $1,200.00
O THER MATERIALS $13,138.00 $13,138.00
INSTALLATIO N $450.00 $450.00
$25,630.00 $10,720.00 ########
WO RKERS RATE
SPONSER MR.JONES
PM RB $3,500.00 15.00%
$0.00
DRYWALL INSTALLER/FINISHER DAN $1,100.00
PLUMBER JOE $1,000.00
PAINTER JIM $750.00
FLOORING DAVE $1,020.00
DESIGNER PEGGY $500.00
ELECTRICAL DOUG $1,200.00
TV/SURROUND INSTALLER HH GREGG $250.00
FRAMMER DON $1,200.00
GENERAL INSTALLER $200.00
TOTAL ########
MATERIAL
BREAKDOWN
10. COST ESTIMATION
After the Change
Task Labor cost
Cost of
materials
Total price Share of cost (%)
FRAMMER $1,200.00 $191.00 $1,391.00 5%
DRYWALL $1,100.00 $580.00 $1,680.00 6%
ELECTRICIAN $1,200.00 $1,200.00 4%
PLUMBIMG $1,000.00 $0.00 $1,000.00 3%
DESIGNER $500.00 $500.00 2%
OTHER $16,438.00 $16,438.00 57%
INSTALLER $450.00 $450.00 2%
PROFESSIONAL SERVICE $3,500.00 $3,500.00 12%
TOTAL $10,720.00 $18,210.00 $28,930.00 100%
CONSTINENGCY 10% $2,893.00 $31,823.00
MAN CAVE COST BREAKDOWN CHART
FLOORING $1,020.00 $804.00 $1,824.00 6%
PAINTER $750.00 $197.00 $947.00 3%
11. CHANGE REQUEST
Reese Boone
PM3320
May26, 2015
Unit 10 Project 1: Change Request
RABI Consulting
Project: Man Cave Change No.: 1
Submitted by: Reese Boone Date: May 26, 2015
Title: Change of T.V
Description of the change: Mr. Jones requested that he wanted a different T.V.
Level of impact: Quality Nil
Current contract value $2,700.00
Value of this change: $3,300.00 Current completion to date: 5/26/15
Revised contract value $6,000.00 Revised completion date : 5/27/2015
Comments/Rationale:
Found T.V. that Mr. Jones wanted at a far price.
Approved:
RABI Consulting, Reese Boone:_______xxx__________________________________
Home Owner, Mike Jones: _______xxxx______________________________