4. Team Members
• Pm: Reese Boone
• Design: Jon Jon
• Accounting/Scheduling: Mary
• Maintenance: Ted
• Riggers(Contractor):Bill
5. LEADERSHIP DEVELOPMENT
PLAN
Design: Jon Jon
Accounting/Scheduling: Mary
Maintenance: Ted
watch training videos /
review and discuss other
styles
review last videos,
participate in real
communication examples
utilizing different methods
of communication tool on
the net
Session date Action to take Resources
Who's
Involved
videos
Reese,
Mary,
Jon, Ted
1 hour a
day for 1
week
employees show
that they can
utilize the tools
Demonstrate better
communication
styles
Pm: Reese Boone
9/7/12015 -
9/11/2015
9/14/2015 -
9/18/2015
Timeframe
Empowering
Benefits
better are
communication with
team members
YouTube video refer
to reference
Reese,
Mary,
Jon, Ted
1 hour a
day for 1
week
better interaction
with each other
Strategies
Area of focus are: Communication
Leadership Development Plan For US Plant.
A team evaluation will be conducted 2 weeks after the last class has been completed if does not improve then will continue
training
8. CHANGE CONTROL BOARD
Name Position CCB Role
B. Thomson US Project Sponsor CCB Chair
R. Boone US Project Manager CCB Member
T. Bones US Project Maintenance Lead CCB Co-Chair
M. Jones US Project Accounting Lead CCB Member
14. Human Resources
Required
Human Resource Requirements
Personnel Type / Role
Quantity Estimated Length of Time
1. PM /manage the project team (consulting firm) 1 5hrs day/23 days
2. Design / will provide floor plan to our spec 1 5 days 3hrs. Daily
3. Accounting / Scheduling 1 2hrs. daily / 23 days
4. Maintenance 2 1=3hrs.daily (10days)
10hrs=10 days/20 days,
1=10 days at 8hrs
5. Riggers (Contractor) 1 10 days
15. Estimated Project
Schedule
Estimated Project Schedule
Milestones
Estimated Date of
Completion
Start Project Started on June 15, 2015
1. Assemble team June 19, 2015
2. Design new floor plan / scheduling June 26, 2015
3. Cut power and move machines hook power pack up July 17, 2015
4. Closing/ accounting and lessons learned July 22, 2015
Total Estimated Length of Project 28 Days
16. Estimated Cost of Project
Expense Type Description Estimated Cost
Labor
Internal Maintenance / supervisor $28.0/110hrs.=$3,080
20*42= $840.0
Internal Maintenance / worker $24.0/80hrs=$1,920
Internal Accounting/scheduling $20.0/46hrs=$920
Internal Design $18.0/15hrs=$270
Hardware Conduit/wire $300.0
Other Contractor (Johns Heavy Movers) $10,000
Other Contractor (PM RABI CONSULTING) $30.0/115hrs=$3,450
Total Estimated Cost of Project $20,780
Estimated Cost of Project
17. Hours of the Project
Breakdown
0
10
20
30
40
50
60
hrs. hrs. hrs. hrs. hrs. hrs.
PM Accountant Designer Rigger Maintenance (Sup) Maintenance
(Worker)
Hours of the Project Breakdown
6/15-6/19
6/22-6/26
7/6-7/10
7/13-7/17
7/20-7/22
20. My Recommendation
• US Alloy has 12 employees on two shift 6 for
the lathes and 6 for the grinders on each shifts
(2)
• Take 3 employees off each cell and each shift
put them on the third shift.