2. SANJAY GANDHI POLYTECHNIC
PROFESSIONAL PRACTICE
SEMINARON INTERNATIONALAIRPORT
PRESENTED BY
MOHAMMED ASIF
5TH DCE, 3RD YEAR
REG NO:- 459CE17028
UNDER THE GUIDANCE
MR.ZAMMER BASHA
4. INFORMATION
• NAME: KANSAI INTERNATIONAL AIRPORT
• PLACE: OSAKA PREFECTURE, JAPAN
• AREA: 10 km2 ( 4 km × 2.5 km )
• TOTAL COST: 20 BILLION ( INCLUDING BOTH PHASES )
• COMMENCEMENT OF PROJECT: 1986
• PUBLIC OPENING: 4TH SEPTEMBER, 1994
• TERMINALS: 2
• RUNWAYS : 2
• OPENED:
• 4TH SEPTEMBER 1994 (1ST RUNWAY)
• 2ND AUGUST 2007 (2ND RUNWAY)
6. INTRODUCTION
• KANSAI INTERNATIONAL AIRPORT (KIA) is the first
man made offshore
• Structure in the world
• Airport was designed by an Italian architect- RENZO
PIANO
• The airport is situated in the middle of Osaka Bay as an
ARTIFICAL ISLAND
• It was the first round the clock airport in Japan
• KIA became the landmark of Japan and inspired many
more to construct offshore structures
7. History
• In the 1960s, when the Kansai region was rapidly losing trade
to Tokyo
planners proposed a new airport near Kobe and Osaka. Osaka
International Airport, located in the densely populated suburbs
of itami, and Toyonaka, was surrounded by buildings; it could
not be expanded, and many of its neighbours had filed
complaints because of noise pollution problems.
• After the protests surrounding New Tokyo International Airport
(now Narita International Airport), which was built with
expropriated land in a rural part of Chiba Prefecture, planners
decided to build the airport offshore. The new airport was part
of a number of new developments to revitalize Osaka, which
had lost economic and cultural ground to Tokyo for most of
the century.
9. Construction Timeline
• 1987- Start of the airport island seawall construction
• Airport island seawall construction (January)
10. METHODS
• SURVEY
• SAND DRAIN METHOD
• SEA WALL CONSTRUCTION
• LAND FILL
• SKY GATE BRIGE CONSTRUCTION
• TERMINAL BUILDING
• 1ST PHASE COMPLETED
SECOND RUNWAY
SECOND TERMINAL BUILDING
• 2ND Kanai International Airport PHASE COMPLETED
11. 1994
• Completion of Passenger Terminal Building (June)
• Opening of the Airport (September 4)
12. Second phase KIA
• The second runway opened on 2 August 2007, but without the originally
planned terminal portion Second phase has expanded the airport size to
10.5 sq. km, now postponed to a later date.
• Further into the future, the airport is planning to construct a new terminal
building (scheduled to open in late 2012), a third runway with a length of
3,500 m, a new cargo terminal and expanding the airport size to 13 km2.