SlideShare a Scribd company logo
1 of 30
Most Expensive
Construction Projects
Completed
Nishchal Khatri
THE CHANNEL TUNNEL
(UK / FRANCE)
US $22.4 Billion
• 50.5 KM Rail Tunnel which
carries high-speed Eurostar
passenger trains
• Also a Eurotunnel Shuttle for
road vehicles
• Crossing takes 35 minutes.
• Construction began in 1988
and opened in 1994.
• Was the most expensive
construction project in the
world in 1988 at £5.5 billion
• The cost finally in 1994
amounted to £9 billion
($13.5 billion), well over its
predicted budget
Eurotunnel Shuttle
THE BIG DIG (USA)
US $23 Billion
*2019 Adjusted for Inflation
• Re-routing some major
highways in the Boston area
(built in the 1930s) to go directly
beneath the heart of the city via
a Tunnel
• Plagued by cost overruns,
delays, leaks, design flaws,
charges of poor execution and
use of substandard materials,
criminal arrests and one death.
• Scheduled to be completed in
1998.
• Completed 10 years behind
schedule in 2008.
• The Big Dig was the most expensive and toughest highway project in the US.
• Officially called Central Artery/Tunnel Project (CA/T)
• The project replaced Boston’s six-lane elevated Highway that ran
through the center of downtown with an underground eight to
ten-lane highway, and added two new bridges over the Charles
River.
• The Project cost was estimated at $2.8 billion (in 1982 dollars,
US$6.0 billion adjusted for inflation as of 2006). However, the
project was completed in December 2007 at a cost of over $14.6
billion ($8.08 billion in 1982 dollars, meaning a cost overrun of
about 190%) as of 2006. The project cost $23 Billion including
interest.
Kansai International
Airport (Japan)
US $25 Billion
*2019 Adjusted for Inflation
• BUILT ON RECLAIMED LAND 4 km
LONG and 2.5 km WIDE
CONSTRUCTED TO RESIST SEMI
FREQUENT EARTHQUAKES and
AVOID NOISE COMPLAINTS.
• ISLAND HAS SUNK 8.2M SINCE
COMPLETION
• SUPPORT COLUMNS AND PIERS
ADDED TO REDUCE SINKING
• THE AIRPORT IS IN DEBT.
• 3RD BUSIEST AIRPORT IN JAPAN
30TH BUSIEST IN THE WORLD
• HAS THE LONGEST AIRPORT
TERMINAL IN THE WORLD AT 1.7
KMS
Progress From April 1978 To June 2008
Hong Kong International
Airport (Hong Kong)
US $31 Billion
*2019 Adjusted for Inflation
• BUILT ON RECLAIMED LAND
• WORLD'S LARGEST PASSENGER
TERMINAL BUILDINGS
• WORLD'S BUSIEST AIRPORT BY
CARGO TRAFFIC
• TWO RUNWAYS
• 3.8 KM LONG
• COMMENCED IN 1998
• 1,255 HECTARES
• OF SITE AREA
• NIJGADH
• (2500HECTARES)
Beijing – Shanghai High
Speed Railway (China)
US $38 Billion
*2019 Adjusted for Inflation
• 1,318 KM Long High speed
Railway
• Connects Beijing and Shanghai
• Two types of trains FAST
(300kmph) taking 4hr 48mins
and SLOW (250kmph) making
affordability with more stops
• Construction began in 2008
and completed in 2011
• 130,000 construction workers
and engineers were at work at
the peak of the construction
THREE GORGES DAM
(China)
US$43 Billion
*2019 Adjusted for Inflation
• World’s LARGEST Hydroelectric Dam produces 22,500 MW
• Produces energy of more than 5 nuclear power plants
• Took 16years of construction and has 26 generators. There are 32 main turbines
• Each Turbine has the capacity of 700MW
• There are 32 main turbines
• Cost US$37 Billion to build (2009)
• Area Flooded 1084 km2 Length 2.36KM
ITAIPU DAM
(Brazil/Paraguay)
US $47.3 Billion
*2019 Adjusted for Inflation
• Height: 738 feet (225m)
• Length: 4.8 miles (7.2km)
• Finished: May 5, 1984
• Cost: $18 billon ($47 billion) in
2019
• Capacity of 14000 MW
• Location: Paraná River
between Brazil and Paraguay
• Largest power plant in terms of
Annual Production 103.1 TWhr
• Area Flooded: 1350 km2
• (Kathmandu Area 570 km2)
KASHAGAN OIL FIELDS
(Kazakhstan)
US $128 Billion
*2019 Adjusted for Inflation
• GIANT OFFSHORE OIL
FIELD IN THE CASPIAN SEA
• CONTROLLED BY
KAZHAKHISTAN
• LARGEST OIL FIELD
DISCOVERY OF THE PAST 40
YEARS
• ESTIMATED 13 BILLION
BARRELS OF RECOVERABLE
RESERVES OF CRUDE OIL
(11TH HIGHEST)
• CHINA’S 1ST DIRECT OIL
IMPORT FROM THIS FIELD
INTERNATIONAL SPACE
STATION (ISS)
US $175 Billion
*2019 Adjusted for Inflation
• MOST EXPENSIVE SINGLE ITEM EVER BUILT
• ORBITS AT AN ALTITUDE OF OVER 300KM AT A SPEED OF 28,000 KMPH
• 16 COUNTRIES INVOLVED IN CONSTRUCTION
• US, RUSSIA,JAPAN,EU AND CANADA ARE MAJOR PARTNERS
• HOLDS 6 CREW MEMBERS
• ASSEMBLED PIECE BY PIECE IN ORBIT
US INTERSTATE HIGHWAY
SYSTEM (USA)
$521 Billion (2018)
*2018 Adjusted for Inflation
• NETWORK OF CONTROLLED-ACCESS
HIGHWAYS THAT FORMS PART OF
THE NATIONAL HIGHWAY SYSTEM IN
THE UNITED STATES
• TOTAL LENGTH OF 77,540 KMS
• STARTED IN 1956 AND TOOK 35
YEARS FOR CONSTRUCTION
• THE INITIAL COST ESTIMATE FOR THE
SYSTEM WAS $25 BILLION OVER 12
YEARS; IT ENDED UP COSTING $114
BILLION OVER BUDGET
END OF SLIDE
THANK YOU
NISHCHAL KHATRI
khatri.nishchal@gmail.com

More Related Content

What's hot

Kansai international airport
Kansai international airport Kansai international airport
Kansai international airport Fatih Taylı
 
Interstate act of 1956 semi trucks outline
Interstate act of 1956  semi trucks outlineInterstate act of 1956  semi trucks outline
Interstate act of 1956 semi trucks outlineHenri Scordato
 
Cambridge - 2
Cambridge - 2Cambridge - 2
Cambridge - 2ce4710
 
Case study on the kansai international airport
Case study on the kansai international airportCase study on the kansai international airport
Case study on the kansai international airportAglaia Connect
 
The great manmade river project
The great manmade river projectThe great manmade river project
The great manmade river projectup1239
 
Libya great man made river project
Libya   great man made river projectLibya   great man made river project
Libya great man made river projectissa ibrahim
 
The Great Manmade River Project
The Great Manmade River ProjectThe Great Manmade River Project
The Great Manmade River ProjectLF68
 
Woods Square - A rare office strata titled office building
Woods Square - A rare office strata titled office buildingWoods Square - A rare office strata titled office building
Woods Square - A rare office strata titled office buildingMichael Chan
 

What's hot (10)

Kurram garhi Dam
Kurram garhi DamKurram garhi Dam
Kurram garhi Dam
 
Kansai international airport
Kansai international airport Kansai international airport
Kansai international airport
 
Interstate act of 1956 semi trucks outline
Interstate act of 1956  semi trucks outlineInterstate act of 1956  semi trucks outline
Interstate act of 1956 semi trucks outline
 
Great man-made-river
Great man-made-riverGreat man-made-river
Great man-made-river
 
Cambridge - 2
Cambridge - 2Cambridge - 2
Cambridge - 2
 
Case study on the kansai international airport
Case study on the kansai international airportCase study on the kansai international airport
Case study on the kansai international airport
 
The great manmade river project
The great manmade river projectThe great manmade river project
The great manmade river project
 
Libya great man made river project
Libya   great man made river projectLibya   great man made river project
Libya great man made river project
 
The Great Manmade River Project
The Great Manmade River ProjectThe Great Manmade River Project
The Great Manmade River Project
 
Woods Square - A rare office strata titled office building
Woods Square - A rare office strata titled office buildingWoods Square - A rare office strata titled office building
Woods Square - A rare office strata titled office building
 

Similar to Most Expensive Construction Projects Around the World

Kansai International Airport.pptx
Kansai International Airport.pptxKansai International Airport.pptx
Kansai International Airport.pptxShivang Pandey
 
PPT on kansai International
PPT on kansai InternationalPPT on kansai International
PPT on kansai InternationalMohammedAsif256
 
Concorde flys again - fact or fancy ?? - Zewail City
Concorde flys again - fact or fancy ?? - Zewail CityConcorde flys again - fact or fancy ?? - Zewail City
Concorde flys again - fact or fancy ?? - Zewail CityAmr Mousa
 
tarbela-dam-project97-2003.ppt
tarbela-dam-project97-2003.ppttarbela-dam-project97-2003.ppt
tarbela-dam-project97-2003.pptLeenaMujahed
 
International currents Affairs
International currents AffairsInternational currents Affairs
International currents Affairsalimohsen08
 
1915Canakkale Bridge
1915Canakkale Bridge1915Canakkale Bridge
1915Canakkale BridgeZeynepUla2
 
tarbela-dam-project.pptx
tarbela-dam-project.pptxtarbela-dam-project.pptx
tarbela-dam-project.pptxLeenaMujahed
 
THE EAST AND CENTRAL AFRICA REGIONAL DEVELOPMENT. Why Kenya remain the hegemo...
THE EAST AND CENTRAL AFRICA REGIONAL DEVELOPMENT. Why Kenya remain the hegemo...THE EAST AND CENTRAL AFRICA REGIONAL DEVELOPMENT. Why Kenya remain the hegemo...
THE EAST AND CENTRAL AFRICA REGIONAL DEVELOPMENT. Why Kenya remain the hegemo...Caroline Kinya Ikiriinya
 
PLAN B NO BS - M. IV REPLACE CARBON Sprint toward Wind and Sun, Eliminating E...
PLAN B NO BS - M. IV REPLACE CARBON Sprint toward Wind and Sun, Eliminating E...PLAN B NO BS - M. IV REPLACE CARBON Sprint toward Wind and Sun, Eliminating E...
PLAN B NO BS - M. IV REPLACE CARBON Sprint toward Wind and Sun, Eliminating E...Start Loving
 
Jawaharlal Nehru Port Trust JNPT
Jawaharlal Nehru Port Trust JNPTJawaharlal Nehru Port Trust JNPT
Jawaharlal Nehru Port Trust JNPTManas Tripathy
 
Top 3 Asia Oil & Gas Pipelines
Top 3 Asia Oil & Gas PipelinesTop 3 Asia Oil & Gas Pipelines
Top 3 Asia Oil & Gas PipelinesNES Global Talent
 
Civil engineering Seminar on G cans project japan.
Civil engineering Seminar on G cans project japan.Civil engineering Seminar on G cans project japan.
Civil engineering Seminar on G cans project japan.Mayur Rahangdale
 
Buddh international circuit
Buddh international circuitBuddh international circuit
Buddh international circuitSumit Gupta
 

Similar to Most Expensive Construction Projects Around the World (20)

Kansai International Airport.pptx
Kansai International Airport.pptxKansai International Airport.pptx
Kansai International Airport.pptx
 
PPT on kansai International
PPT on kansai InternationalPPT on kansai International
PPT on kansai International
 
Concorde flys again - fact or fancy ?? - Zewail City
Concorde flys again - fact or fancy ?? - Zewail CityConcorde flys again - fact or fancy ?? - Zewail City
Concorde flys again - fact or fancy ?? - Zewail City
 
Padma bridgeg
Padma bridgegPadma bridgeg
Padma bridgeg
 
tarbela-dam-project97-2003.ppt
tarbela-dam-project97-2003.ppttarbela-dam-project97-2003.ppt
tarbela-dam-project97-2003.ppt
 
International currents Affairs
International currents AffairsInternational currents Affairs
International currents Affairs
 
1915Canakkale Bridge
1915Canakkale Bridge1915Canakkale Bridge
1915Canakkale Bridge
 
Session 11 – site visits port of maputo
Session 11  – site visits  port of maputoSession 11  – site visits  port of maputo
Session 11 – site visits port of maputo
 
tarbela-dam-project.pptx
tarbela-dam-project.pptxtarbela-dam-project.pptx
tarbela-dam-project.pptx
 
Tarbela dam project
Tarbela dam projectTarbela dam project
Tarbela dam project
 
Kansai airport ppt
Kansai airport pptKansai airport ppt
Kansai airport ppt
 
THE EAST AND CENTRAL AFRICA REGIONAL DEVELOPMENT. Why Kenya remain the hegemo...
THE EAST AND CENTRAL AFRICA REGIONAL DEVELOPMENT. Why Kenya remain the hegemo...THE EAST AND CENTRAL AFRICA REGIONAL DEVELOPMENT. Why Kenya remain the hegemo...
THE EAST AND CENTRAL AFRICA REGIONAL DEVELOPMENT. Why Kenya remain the hegemo...
 
PLAN B NO BS - M. IV REPLACE CARBON Sprint toward Wind and Sun, Eliminating E...
PLAN B NO BS - M. IV REPLACE CARBON Sprint toward Wind and Sun, Eliminating E...PLAN B NO BS - M. IV REPLACE CARBON Sprint toward Wind and Sun, Eliminating E...
PLAN B NO BS - M. IV REPLACE CARBON Sprint toward Wind and Sun, Eliminating E...
 
Jawaharlal Nehru Port Trust JNPT
Jawaharlal Nehru Port Trust JNPTJawaharlal Nehru Port Trust JNPT
Jawaharlal Nehru Port Trust JNPT
 
Top 3 Asia Oil & Gas Pipelines
Top 3 Asia Oil & Gas PipelinesTop 3 Asia Oil & Gas Pipelines
Top 3 Asia Oil & Gas Pipelines
 
Civil engineering Seminar on G cans project japan.
Civil engineering Seminar on G cans project japan.Civil engineering Seminar on G cans project japan.
Civil engineering Seminar on G cans project japan.
 
Channel capacity by Peter Keyte
Channel capacity by Peter KeyteChannel capacity by Peter Keyte
Channel capacity by Peter Keyte
 
Buddh international circuit
Buddh international circuitBuddh international circuit
Buddh international circuit
 
Cpec
CpecCpec
Cpec
 
2015 STS - Port Upgrades Will Change Your Operations
2015 STS - Port Upgrades Will Change Your Operations 2015 STS - Port Upgrades Will Change Your Operations
2015 STS - Port Upgrades Will Change Your Operations
 

Recently uploaded

OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 

Recently uploaded (20)

OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 

Most Expensive Construction Projects Around the World

  • 2. THE CHANNEL TUNNEL (UK / FRANCE) US $22.4 Billion
  • 3. • 50.5 KM Rail Tunnel which carries high-speed Eurostar passenger trains • Also a Eurotunnel Shuttle for road vehicles • Crossing takes 35 minutes. • Construction began in 1988 and opened in 1994. • Was the most expensive construction project in the world in 1988 at £5.5 billion • The cost finally in 1994 amounted to £9 billion ($13.5 billion), well over its predicted budget
  • 5. THE BIG DIG (USA) US $23 Billion *2019 Adjusted for Inflation
  • 6. • Re-routing some major highways in the Boston area (built in the 1930s) to go directly beneath the heart of the city via a Tunnel • Plagued by cost overruns, delays, leaks, design flaws, charges of poor execution and use of substandard materials, criminal arrests and one death. • Scheduled to be completed in 1998. • Completed 10 years behind schedule in 2008. • The Big Dig was the most expensive and toughest highway project in the US. • Officially called Central Artery/Tunnel Project (CA/T)
  • 7. • The project replaced Boston’s six-lane elevated Highway that ran through the center of downtown with an underground eight to ten-lane highway, and added two new bridges over the Charles River. • The Project cost was estimated at $2.8 billion (in 1982 dollars, US$6.0 billion adjusted for inflation as of 2006). However, the project was completed in December 2007 at a cost of over $14.6 billion ($8.08 billion in 1982 dollars, meaning a cost overrun of about 190%) as of 2006. The project cost $23 Billion including interest.
  • 8. Kansai International Airport (Japan) US $25 Billion *2019 Adjusted for Inflation
  • 9. • BUILT ON RECLAIMED LAND 4 km LONG and 2.5 km WIDE CONSTRUCTED TO RESIST SEMI FREQUENT EARTHQUAKES and AVOID NOISE COMPLAINTS. • ISLAND HAS SUNK 8.2M SINCE COMPLETION • SUPPORT COLUMNS AND PIERS ADDED TO REDUCE SINKING • THE AIRPORT IS IN DEBT. • 3RD BUSIEST AIRPORT IN JAPAN 30TH BUSIEST IN THE WORLD • HAS THE LONGEST AIRPORT TERMINAL IN THE WORLD AT 1.7 KMS Progress From April 1978 To June 2008
  • 10. Hong Kong International Airport (Hong Kong) US $31 Billion *2019 Adjusted for Inflation
  • 11. • BUILT ON RECLAIMED LAND • WORLD'S LARGEST PASSENGER TERMINAL BUILDINGS • WORLD'S BUSIEST AIRPORT BY CARGO TRAFFIC • TWO RUNWAYS • 3.8 KM LONG • COMMENCED IN 1998 • 1,255 HECTARES • OF SITE AREA • NIJGADH • (2500HECTARES)
  • 12. Beijing – Shanghai High Speed Railway (China) US $38 Billion *2019 Adjusted for Inflation
  • 13. • 1,318 KM Long High speed Railway • Connects Beijing and Shanghai • Two types of trains FAST (300kmph) taking 4hr 48mins and SLOW (250kmph) making affordability with more stops • Construction began in 2008 and completed in 2011 • 130,000 construction workers and engineers were at work at the peak of the construction
  • 14. THREE GORGES DAM (China) US$43 Billion *2019 Adjusted for Inflation
  • 15. • World’s LARGEST Hydroelectric Dam produces 22,500 MW • Produces energy of more than 5 nuclear power plants • Took 16years of construction and has 26 generators. There are 32 main turbines • Each Turbine has the capacity of 700MW • There are 32 main turbines • Cost US$37 Billion to build (2009) • Area Flooded 1084 km2 Length 2.36KM
  • 16. ITAIPU DAM (Brazil/Paraguay) US $47.3 Billion *2019 Adjusted for Inflation
  • 17. • Height: 738 feet (225m) • Length: 4.8 miles (7.2km) • Finished: May 5, 1984 • Cost: $18 billon ($47 billion) in 2019 • Capacity of 14000 MW • Location: Paraná River between Brazil and Paraguay • Largest power plant in terms of Annual Production 103.1 TWhr • Area Flooded: 1350 km2 • (Kathmandu Area 570 km2)
  • 18. KASHAGAN OIL FIELDS (Kazakhstan) US $128 Billion *2019 Adjusted for Inflation
  • 19. • GIANT OFFSHORE OIL FIELD IN THE CASPIAN SEA • CONTROLLED BY KAZHAKHISTAN • LARGEST OIL FIELD DISCOVERY OF THE PAST 40 YEARS • ESTIMATED 13 BILLION BARRELS OF RECOVERABLE RESERVES OF CRUDE OIL (11TH HIGHEST) • CHINA’S 1ST DIRECT OIL IMPORT FROM THIS FIELD
  • 20. INTERNATIONAL SPACE STATION (ISS) US $175 Billion *2019 Adjusted for Inflation
  • 21. • MOST EXPENSIVE SINGLE ITEM EVER BUILT • ORBITS AT AN ALTITUDE OF OVER 300KM AT A SPEED OF 28,000 KMPH • 16 COUNTRIES INVOLVED IN CONSTRUCTION • US, RUSSIA,JAPAN,EU AND CANADA ARE MAJOR PARTNERS • HOLDS 6 CREW MEMBERS • ASSEMBLED PIECE BY PIECE IN ORBIT
  • 22. US INTERSTATE HIGHWAY SYSTEM (USA) $521 Billion (2018) *2018 Adjusted for Inflation
  • 23. • NETWORK OF CONTROLLED-ACCESS HIGHWAYS THAT FORMS PART OF THE NATIONAL HIGHWAY SYSTEM IN THE UNITED STATES • TOTAL LENGTH OF 77,540 KMS • STARTED IN 1956 AND TOOK 35 YEARS FOR CONSTRUCTION • THE INITIAL COST ESTIMATE FOR THE SYSTEM WAS $25 BILLION OVER 12 YEARS; IT ENDED UP COSTING $114 BILLION OVER BUDGET
  • 24.
  • 25.
  • 26.
  • 27.
  • 28.
  • 29.
  • 30. END OF SLIDE THANK YOU NISHCHAL KHATRI khatri.nishchal@gmail.com