SlideShare a Scribd company logo
1 of 33
Download to read offline
CASE STUDY ON
INCHEON INTERNATIONAL AIRPORT
TRANSPORTATION ENGINEERING – II
(CE 6003)
Submitted by,
Shubham Bathwal
BE/10585/2017
Semester - VI
INTRODUCTION
• Incheon International Airport (IIA) is the largest airport in South Korea,
the primary airport serving the Seoul Capital Area, and one of the largest
and busiest airports in the world. Since 2005, it has been rated the best
airport worldwide by Airports Council International every year. It is also
rated as the world's cleanest airport and the world's best international
transit airport by Skytrax.
• Incheon International Airport is located west of Incheon's city center, on
an artificially created piece of land between Yeongjong and Yongyu
Islands.
• The airport holds a record of being ranked the Best Airport Worldwide
for 11 consecutive years by the Airports Council International (ACI)'s
Airport Service Quality Award from 2005 to 2016.
• Incheon International Airport was named the winner of World’s Best
Transit Airport in 2020. Terminal 2 at Incheon International Airport was
named World’s Best Airport Terminal in 2020.
HISTORY
• After the 1988 Summer Olympics, international air traffic to Korea
increased. In the 1990s, it became apparent that Gimpo International
Airport could not cope with the increase in air traffic. To reduce the load
on Gimpo International Airport, the government decided to build a new
international airport.
• In November 1992, the construction of the Incheon airport began on
reclaimed land between Yeongjong Island and Youngyu Island, and took
eight years to finish, with an additional six months for testing.
Completion was initially scheduled for 1997 but delayed due to the
economic crisis.[12] The airport was officially opened on 21 March 2001.
• On 15 November 2006, the Airbus A380 landed at the airport as part of
the first leg of its certification trip. Tests on the runways, taxiways, and
ramps showed that the airport could handle the aircraft.
INFORMATION
• Located 48 km west of Seoul, the capital and the largest city of South
Korea.
• Airport is owned and operated by Incheon International Airport
Corporation.
2019 STATS
Total Flights – 360,000
Passenger Traffic – 71 million
Cargo – 2.9 million tonnes
Countries Served – 59
Airlines – 90
Construction phases
The airport was originally planned to be built in three phases, incrementally increasing airport
capacity as the demand grew. This was changed, however, to four phases after the airport was
opened.
Phase 1 (1992~2001)
1992.06.16 : Announcement of the new metropolitan
airport construction project
1996.05.23 : Commencement of Terminal 1
construction
2001.03.29 : Opening of Incheon International Airport
In this phase, a passenger terminal with a floor space of 496,000 square metres , two
parallel runways, a control tower, an administrative building, a transportation centre and
integrated operations centre, three cargo terminals, international business centre, and a
government office building were constructed.
Beginning of the construction project for Terminal 1 in 1996's
Construction of Runways 1 and 2 in 1996's
During this construction phase, a third parallel 4,000-
metre-long runway and a 13-hectare cargo terminal
area were added. A 16.5-hectare concourse connected
to the main passenger building via two parallel 870-
metre-long underground passageways was added, with
a Mitsubishi Crystal Mover shuttle train APM shuttling
passengers between the concourse and the main
terminal.
Phase 2 (2002~2008)
2004. 06. 28 Commencement of earthwork and piling
2007. 07. 30 Completion of Runway 3 paving
2008. 06. 20 Completion and opening of Phase 2 construction
Beginning of the concourse construction in 2002's
Beginning of Runway 3 construction in 2005's
Phase 3 (2009~2017)
The second passenger terminal was constructed in the
northern field of the airport, and its existing cargo
terminal and other infrastructures were expanded. The
terminals are connected to each other by the
underground "Starline" train.
After completion, Incheon International Airport is able
to handle 62 million passengers and 5.8 million tons of
cargo a year.
2009. 06. 30 Announcement of change in the initial plan
2013. 06. 14 Commencement of earthwork and piling for Terminal 2
2018. 01. 18 Opening of Incheon International Airport Terminal 2
Beginning of Terminal 2 construction in 2013's
Opening of Terminal 2 in 2018's
TERMINALS
TERMINAL 1
• Terminal 1 (measuring 496,000 square meters) is the largest airport terminal in area in
South Korea.
• Terminal 1 was designed by Curtis W. Fentress, FAIA, RIBA of Fentress Architects.
• It is 1,060 metres (3,480 ft) long, 149 metres (489 ft) wide, and 33 metres (108 ft) high.
• Its construction cost was 1.3816 trillion South Korean Won.
• The terminal has 44 boarding ports (all of which can accommodate the Airbus A380),
50 customs inspection ports, 2 biological quarantine counters, 6 stationary and 14
portable passenger quarantine counters, 120 arrival passport inspection counters, 8
arrival security ports, 28 departure security ports, 252 check in counters, and 120
departure passport inspection counters.
CONCOURSE
The passenger concourse was completed at the end of May 2008. It is connected to
Terminal 1 by two parallel 870-metre-long (2,850 ft) underground passageways equipped
with IATs (Intra Airport Transit). It has 30 gates and six lounges(Asiana Airlines/Star
Alliance, Singapore Airlines/Star Alliance, Japan Airlines/Oneworld, Korean Air/SkyTeam,
and China Eastern Airlines/SkyTeam).
TERMINAL 2
• Terminal 2 which was constructed into the scale of 388,000㎡ (38.8 ha) in total floor
area and 23 mil. in annual passenger capacity was opened on 18 Jan 2018.
• Korean Air, KLM, Delta Air Lines, and Air France flights were relocated from Terminal 1
to Terminal 2. Many other SkyTeam members started serving the Terminal 2 on 28
October 2018.
• The terminal will be expanded into a mega-size terminal with a total floor area of
735,000㎡ (73.5 ha) and annual passenger capacity of 52 mil. through the phase 4
construction.
RUNWAY
• The airport consists of three functional runway and a fourth runway under construction.
• The airport configuration of ICN is shown in Fig. There are three parallel runways at ICN.
Runway 33R/15L and 33L/15R are two parallel runways with the distance of 400m
between them. Runway 33R/15L is used primarily for arrivals and 33L/15R is primarily
for departures. Runway 34/16 is used for both departures and arrivals, and the usage is
changed several times a day depending on the departure and arrival traffic
demands. All cargo flights takeoff and land using the runways 33R/15L and 33L/15R,
exclusively, whereas the passenger flights can use all three runways.
DIRECTION WIDTH
(M)
LENGTH
(M)
STRENGTH(PCN) AND SURFACE OF RWY AND SWY
RUNWAY
1
15R/33L 60 3750 ㆍ88/F/B/X/T Asphalt ㆍSWY and 300 m RWY ends
are 86/R/B/X/T Concrete
RUNWAY
2
15L/33R 60 3750 88/F/B/X/T Asphalt ㆍSWY and 300 m RWY ends
are 86/R/B/X/T Concrete
RUNWAY
3
16/34 60 4000 75/F/B/X/T Asphalt SWY and 700 m RWY ends
are 85/R/B/X/T Concrete
RUNWAY
RUNWAY NAVIGATIONAL AIDS
Instrument landing system (ILS) provides guidance and distance information so that
airplanes can safely navigate through bad weather (fog, etc.). It is a landing guidance
system that enables the pilot to land the plane following only the instrument.
Aeronautical light facilities, which include approach lighting system, runway lighting
system, etc., provide visual information needed for airplanes to safely make the landing.
Uses facilities suited for CAT-III, provides a precision system that makes landing possible
even when the visual range is only 75m.
Lights
- Edge lights are installed at 60 m intervals on all runways.
- Centerline lights are installed at 15 m intervals on all
runways.
Markings : Runway Edges, Touchdown Zones, Aiming Points
and Center line.
Glide Path Provides
landing angle (3˚)
information to
airplanes
Marker(Inner/Middle)
Provides position
information of the
designated space with
runway thresholds
Localizer
Provides runway
center line
information to
airplanes taking
off and landing
Wind Rose Diagram
In the case of take – off operations, the head wind will help us in generating the lift,
whereas during the landing operations the same wind will help in generating the drag,
so as to stop the landing aircraft. So wind rose diagram provides data which is essential
in determining the direction of the runaway.
TAXIWAY
TAXIWAY WIDTH, SURFACE AND STRENGTH:
Width : 30 m
1.- Shoulder of TWY A/B/C/D : 15 m (Paved 12
m, Turfed 3m)
2.- Shoulder of TWY M/N : 15 m (Paved)
Surface : Asphalt, Concrete
Strength
1.TWY A, D : Concrete PCN 86/R/B/X/T
2.TWY B, C : Asphalt PCN 88/F/B/X/T
3.TWY M : Concrete PCN 85/R/B/W/T
4.TWY N : Asphalt PCN 75/F/B/W/T
TAXIWAY
LIGHTS
- Edge lights are installed at 15 m intervals on all TWY curved
areas and 60 m intervals of markers are in the rest of areas.
- Centerline Lights are installed at 3.75∼7.5 m intervals on all TWY
curved areas and 15 m intervals in the rest of areas.
MARKINGS
- TWY & taxi lane centerline markings are marked with a yellow solid
line on the black base on all specified taxiways designated as the
SMGCS (Surface Movement Guidance & Control System) taxiway
routes
APRONS
1.Apron1 : Concrete PCN 86/R/B/X/T
2.Apron2 : Concrete PCN 86/R/B/X/T
3.Apron3 : Concrete PCN 85/R/B/X/T
4.Cargo Apron1 : Concrete PCN 86/R/B/X/T
5.Cargo Apron2 : Concrete PCN 85/R/B/X/T
6.Maintenance Apron : Concrete PCN 86/R/B/X/T
Attached Apron Remote Aprons
Cargo
Apron
APRONS
Type Phases 1, 2 Phase 3
Phase 4 (Net
Increase)
Total
Attached
Aprons
74 37 34 145
Remote Aprons 35 17 28 13
Cargo Aprons 36 11 13 60
Total 145 65 75 285
HANGAR
Seoul Incheon Airport - Asiana Airlines
MRO (Maintenance Repair and Overhaul)
Hangar
Basic technical specifications of the hangar,
constructed as a landmark for the leading
Korean carrier Asiana Airlines are:
•Hangar area 60.000 m²
•Length 175 + 29 m, Width 97 + 24 m
•Height 41 m
•Capable of storing 2 jumbo and 1 smaller
aircraft at the same time
•Energy saving design, providing an inviting
work environment for the staff
Ongoing Development
PHASE 4 (2017 – 2024)
The demand for aviation market is expected to increase by at least twofold in the next
15 years (average annual growth rate of 4.4%). Incheon Airport has constantly grown
at the average annual growth rate of around 7% after its opening.
Construction Period 2017. 11 - 2024. 12 (7.5 years)
Construction Items
Expansion of Terminal 2 (+29 mil.
PAX/year)
One runway (Runway 4: 3,750m) (2.3
miles)
Aprons, parking lots, roads, etc.
Project Cost About 4.8 trillion won (412 mil. USD)
CONSTRUCTION CONCEPT
Green : Terminal 2 will be an eco-friendly airport that lives and breathes in nature
utilizing a variety of plants to maintain freshness of indoor spaces.
Also, the airport will maximize the production of new renewable energy in various ways
including fuel cell in order to be reborn as the most environmentally-friendly airport in
the world.
Art : Various structures in the form of the sky will be built inside Terminal 2, creating
artistic spaces that together form an art airport. Such artistic elements will provide a
brighter and more open experience to the passengers and users.
Smart :
• Self Check – in ,Self Bag Drop
• Speech recognition information Service
• Biology Intelligence
• AI-based intelligent CCTV
• Passenger service using IoT technologies
• Media art integrated into the building
ACCOLADES
Incheon International airport has been the recipient of a number of awards since its opening,
including:
•Best Airport Worldwide at the first Airport Service Quality Awards in 2007.
•Won the GT Tested Award for Best Airport in the World in January 2007.
•Named by Global Traveler (GT) as the Best Airport in the World for the second straight year in
January 2008.
•Named World's Best Airport for 2009, in the World Airport Survey results published by
Skytrax.
•In 2012 it was ranked the best airport in the world by Skytrax
ACCIDENT
UPS flight 5X61 suffered a runway excursion and nose gear collapse on take-off on 6 June
2016. The flight was cleared for takeoff from runway 33L. The aircraft reached V1 speed
after a ground run of 6413 feet. About that time the crew heard a noise, originating from
the failure of the no.9 tire (the left-hand tire on the central landing gear). The no.10 tire
on the same landing gear also ruptured. Vibration and torsion forces then caused the
lower drag brace of the central landing gear to break. The drag brace then hit the body
several times. This caused a rupture of the hydraulic system of brake system 1, reducing
the total brake efficiency to about 48% as the crew rejected the takeoff. With 4,635 feet
of runway remaining the aircraft began to decelerate.
The aircraft required a deceleration distance of at least about 5,550ft from the position
where the takeoff was rejected. As a result, the MD-11 stopped at approximately 1,591 ft
(485 m) past the end of the runway 33L. The nose gear collapsed and the no. 1 and 3
engines contacted the grass.
THANK YOU!!!

More Related Content

What's hot

Airport terminal planning and design
Airport terminal planning and designAirport terminal planning and design
Airport terminal planning and designJetline Marvel
 
Layout of Airport Planning
Layout of Airport PlanningLayout of Airport Planning
Layout of Airport PlanningManoharanM12
 
Airport planning and Design
Airport planning and DesignAirport planning and Design
Airport planning and Designsrinivas2036
 
Chhatrapati Shivaji International Airport, Mumbai - Terminal 2
Chhatrapati Shivaji International Airport, Mumbai - Terminal 2Chhatrapati Shivaji International Airport, Mumbai - Terminal 2
Chhatrapati Shivaji International Airport, Mumbai - Terminal 2Mitesh Gupta
 
Terminal Design
Terminal DesignTerminal Design
Terminal DesignMal Mai
 
AIRPORT PLANNING AND DESIGN
AIRPORT PLANNING AND DESIGNAIRPORT PLANNING AND DESIGN
AIRPORT PLANNING AND DESIGNNiranjan Varma
 
Flexible digital approach to airport terminal design
Flexible digital approach to airport terminal designFlexible digital approach to airport terminal design
Flexible digital approach to airport terminal designSarah Shuchi
 
Standards of Cruise Terminal
Standards of Cruise Terminal Standards of Cruise Terminal
Standards of Cruise Terminal Amr Samir Shaban
 
Airport apron and holding bays
Airport apron and holding baysAirport apron and holding bays
Airport apron and holding bayssrinivas2036
 
Airport capacity and_delay
Airport capacity and_delayAirport capacity and_delay
Airport capacity and_delaynobel56
 
PPP Bangalore airport presentation
PPP Bangalore airport presentationPPP Bangalore airport presentation
PPP Bangalore airport presentationSreethu Sriniwas
 
Air port presentation 6th unit
Air port presentation 6th unitAir port presentation 6th unit
Air port presentation 6th unitT.Naga Anusha
 
Airport master plan
Airport master planAirport master plan
Airport master planAravind Raj
 

What's hot (20)

Airport terminal planning and design
Airport terminal planning and designAirport terminal planning and design
Airport terminal planning and design
 
Layout of Airport Planning
Layout of Airport PlanningLayout of Airport Planning
Layout of Airport Planning
 
Airport Architecture
Airport ArchitectureAirport Architecture
Airport Architecture
 
Airport planning and Design
Airport planning and DesignAirport planning and Design
Airport planning and Design
 
Chhatrapati Shivaji International Airport, Mumbai - Terminal 2
Chhatrapati Shivaji International Airport, Mumbai - Terminal 2Chhatrapati Shivaji International Airport, Mumbai - Terminal 2
Chhatrapati Shivaji International Airport, Mumbai - Terminal 2
 
Terminal Design
Terminal DesignTerminal Design
Terminal Design
 
Terminal area
Terminal areaTerminal area
Terminal area
 
Airports presentation
Airports presentationAirports presentation
Airports presentation
 
Airport planning and design
Airport planning and designAirport planning and design
Airport planning and design
 
AIRPORT PLANNING AND DESIGN
AIRPORT PLANNING AND DESIGNAIRPORT PLANNING AND DESIGN
AIRPORT PLANNING AND DESIGN
 
Flexible digital approach to airport terminal design
Flexible digital approach to airport terminal designFlexible digital approach to airport terminal design
Flexible digital approach to airport terminal design
 
Airport
AirportAirport
Airport
 
Standards of Cruise Terminal
Standards of Cruise Terminal Standards of Cruise Terminal
Standards of Cruise Terminal
 
Airport apron and holding bays
Airport apron and holding baysAirport apron and holding bays
Airport apron and holding bays
 
Airport layout
Airport layoutAirport layout
Airport layout
 
Airport capacity and_delay
Airport capacity and_delayAirport capacity and_delay
Airport capacity and_delay
 
PPP Bangalore airport presentation
PPP Bangalore airport presentationPPP Bangalore airport presentation
PPP Bangalore airport presentation
 
Air port presentation 6th unit
Air port presentation 6th unitAir port presentation 6th unit
Air port presentation 6th unit
 
CSIA
CSIACSIA
CSIA
 
Airport master plan
Airport master planAirport master plan
Airport master plan
 

Similar to Incheon international airport

Master thesis - Executive Report
Master thesis - Executive ReportMaster thesis - Executive Report
Master thesis - Executive ReportBojan Besednik
 
Zhytomyr International Airport
Zhytomyr International Airport Zhytomyr International Airport
Zhytomyr International Airport Taras Strygunenko
 
The Project Model, Engineering challenges and Performance Measurement of HK A...
The Project Model, Engineering challenges and Performance Measurement of HK A...The Project Model, Engineering challenges and Performance Measurement of HK A...
The Project Model, Engineering challenges and Performance Measurement of HK A...Chun Wing Daniel Tsang
 
Airport Planning & Terminal Building Design
Airport Planning & Terminal Building DesignAirport Planning & Terminal Building Design
Airport Planning & Terminal Building DesignSiniša Prvanov
 
Agresh shrivastava places to move
Agresh shrivastava places to moveAgresh shrivastava places to move
Agresh shrivastava places to moveKumar Snehansu
 
AAI NSCBI Electrical Vocational Training Report
AAI NSCBI Electrical Vocational Training ReportAAI NSCBI Electrical Vocational Training Report
AAI NSCBI Electrical Vocational Training Reportju_ee_19
 
London heathrow airport
London heathrow airportLondon heathrow airport
London heathrow airportZaheer Minhas
 
An Analysis of Runway Capacity at International Airport Sultan Aji Sulaiman B...
An Analysis of Runway Capacity at International Airport Sultan Aji Sulaiman B...An Analysis of Runway Capacity at International Airport Sultan Aji Sulaiman B...
An Analysis of Runway Capacity at International Airport Sultan Aji Sulaiman B...irjes
 
Istanbul New Airport (İstanbul Yeni Havalimanı)
Istanbul New Airport (İstanbul Yeni Havalimanı)Istanbul New Airport (İstanbul Yeni Havalimanı)
Istanbul New Airport (İstanbul Yeni Havalimanı)BME
 
Heathrow airport Presentation by Ayisha Irshad
Heathrow airport Presentation by Ayisha IrshadHeathrow airport Presentation by Ayisha Irshad
Heathrow airport Presentation by Ayisha Irshadayishairshad
 
Airport & railways engineering ce467 pdf
Airport & railways engineering   ce467 pdfAirport & railways engineering   ce467 pdf
Airport & railways engineering ce467 pdfSaqib Imran
 
Copy of Jaipur Airport Study.pdf
Copy of Jaipur Airport Study.pdfCopy of Jaipur Airport Study.pdf
Copy of Jaipur Airport Study.pdfThirumeni Madavan
 
Project brief updated_aug081
Project brief updated_aug081Project brief updated_aug081
Project brief updated_aug081Anush verma
 
IRJET- Design of Runway for Navi-Mumbai International Airport
IRJET-  	  Design of Runway for Navi-Mumbai International AirportIRJET-  	  Design of Runway for Navi-Mumbai International Airport
IRJET- Design of Runway for Navi-Mumbai International AirportIRJET Journal
 

Similar to Incheon international airport (20)

VKO Tech'16
VKO Tech'16VKO Tech'16
VKO Tech'16
 
Study Tour Airport
Study Tour AirportStudy Tour Airport
Study Tour Airport
 
Master thesis - Executive Report
Master thesis - Executive ReportMaster thesis - Executive Report
Master thesis - Executive Report
 
Zhytomyr International Airport
Zhytomyr International Airport Zhytomyr International Airport
Zhytomyr International Airport
 
The Project Model, Engineering challenges and Performance Measurement of HK A...
The Project Model, Engineering challenges and Performance Measurement of HK A...The Project Model, Engineering challenges and Performance Measurement of HK A...
The Project Model, Engineering challenges and Performance Measurement of HK A...
 
Bangalore kochi airport
Bangalore kochi airportBangalore kochi airport
Bangalore kochi airport
 
Airport Planning & Terminal Building Design
Airport Planning & Terminal Building DesignAirport Planning & Terminal Building Design
Airport Planning & Terminal Building Design
 
Agresh shrivastava places to move
Agresh shrivastava places to moveAgresh shrivastava places to move
Agresh shrivastava places to move
 
Railtel
RailtelRailtel
Railtel
 
Airport.pptx
Airport.pptxAirport.pptx
Airport.pptx
 
AAI NSCBI Electrical Vocational Training Report
AAI NSCBI Electrical Vocational Training ReportAAI NSCBI Electrical Vocational Training Report
AAI NSCBI Electrical Vocational Training Report
 
London heathrow airport
London heathrow airportLondon heathrow airport
London heathrow airport
 
An Analysis of Runway Capacity at International Airport Sultan Aji Sulaiman B...
An Analysis of Runway Capacity at International Airport Sultan Aji Sulaiman B...An Analysis of Runway Capacity at International Airport Sultan Aji Sulaiman B...
An Analysis of Runway Capacity at International Airport Sultan Aji Sulaiman B...
 
Istanbul New Airport (İstanbul Yeni Havalimanı)
Istanbul New Airport (İstanbul Yeni Havalimanı)Istanbul New Airport (İstanbul Yeni Havalimanı)
Istanbul New Airport (İstanbul Yeni Havalimanı)
 
Heathrow airport Presentation by Ayisha Irshad
Heathrow airport Presentation by Ayisha IrshadHeathrow airport Presentation by Ayisha Irshad
Heathrow airport Presentation by Ayisha Irshad
 
Airport & railways engineering ce467 pdf
Airport & railways engineering   ce467 pdfAirport & railways engineering   ce467 pdf
Airport & railways engineering ce467 pdf
 
Copy of Jaipur Airport Study.pdf
Copy of Jaipur Airport Study.pdfCopy of Jaipur Airport Study.pdf
Copy of Jaipur Airport Study.pdf
 
Project brief updated_aug081
Project brief updated_aug081Project brief updated_aug081
Project brief updated_aug081
 
IRJET- Design of Runway for Navi-Mumbai International Airport
IRJET-  	  Design of Runway for Navi-Mumbai International AirportIRJET-  	  Design of Runway for Navi-Mumbai International Airport
IRJET- Design of Runway for Navi-Mumbai International Airport
 
Circular Runway
Circular RunwayCircular Runway
Circular Runway
 

Recently uploaded

What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 

Recently uploaded (20)

9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 

Incheon international airport

  • 1. CASE STUDY ON INCHEON INTERNATIONAL AIRPORT TRANSPORTATION ENGINEERING – II (CE 6003) Submitted by, Shubham Bathwal BE/10585/2017 Semester - VI
  • 2. INTRODUCTION • Incheon International Airport (IIA) is the largest airport in South Korea, the primary airport serving the Seoul Capital Area, and one of the largest and busiest airports in the world. Since 2005, it has been rated the best airport worldwide by Airports Council International every year. It is also rated as the world's cleanest airport and the world's best international transit airport by Skytrax. • Incheon International Airport is located west of Incheon's city center, on an artificially created piece of land between Yeongjong and Yongyu Islands. • The airport holds a record of being ranked the Best Airport Worldwide for 11 consecutive years by the Airports Council International (ACI)'s Airport Service Quality Award from 2005 to 2016. • Incheon International Airport was named the winner of World’s Best Transit Airport in 2020. Terminal 2 at Incheon International Airport was named World’s Best Airport Terminal in 2020.
  • 3. HISTORY • After the 1988 Summer Olympics, international air traffic to Korea increased. In the 1990s, it became apparent that Gimpo International Airport could not cope with the increase in air traffic. To reduce the load on Gimpo International Airport, the government decided to build a new international airport. • In November 1992, the construction of the Incheon airport began on reclaimed land between Yeongjong Island and Youngyu Island, and took eight years to finish, with an additional six months for testing. Completion was initially scheduled for 1997 but delayed due to the economic crisis.[12] The airport was officially opened on 21 March 2001. • On 15 November 2006, the Airbus A380 landed at the airport as part of the first leg of its certification trip. Tests on the runways, taxiways, and ramps showed that the airport could handle the aircraft.
  • 4. INFORMATION • Located 48 km west of Seoul, the capital and the largest city of South Korea. • Airport is owned and operated by Incheon International Airport Corporation. 2019 STATS Total Flights – 360,000 Passenger Traffic – 71 million Cargo – 2.9 million tonnes Countries Served – 59 Airlines – 90
  • 5. Construction phases The airport was originally planned to be built in three phases, incrementally increasing airport capacity as the demand grew. This was changed, however, to four phases after the airport was opened. Phase 1 (1992~2001) 1992.06.16 : Announcement of the new metropolitan airport construction project 1996.05.23 : Commencement of Terminal 1 construction 2001.03.29 : Opening of Incheon International Airport In this phase, a passenger terminal with a floor space of 496,000 square metres , two parallel runways, a control tower, an administrative building, a transportation centre and integrated operations centre, three cargo terminals, international business centre, and a government office building were constructed.
  • 6. Beginning of the construction project for Terminal 1 in 1996's Construction of Runways 1 and 2 in 1996's
  • 7. During this construction phase, a third parallel 4,000- metre-long runway and a 13-hectare cargo terminal area were added. A 16.5-hectare concourse connected to the main passenger building via two parallel 870- metre-long underground passageways was added, with a Mitsubishi Crystal Mover shuttle train APM shuttling passengers between the concourse and the main terminal. Phase 2 (2002~2008) 2004. 06. 28 Commencement of earthwork and piling 2007. 07. 30 Completion of Runway 3 paving 2008. 06. 20 Completion and opening of Phase 2 construction
  • 8. Beginning of the concourse construction in 2002's Beginning of Runway 3 construction in 2005's
  • 9. Phase 3 (2009~2017) The second passenger terminal was constructed in the northern field of the airport, and its existing cargo terminal and other infrastructures were expanded. The terminals are connected to each other by the underground "Starline" train. After completion, Incheon International Airport is able to handle 62 million passengers and 5.8 million tons of cargo a year. 2009. 06. 30 Announcement of change in the initial plan 2013. 06. 14 Commencement of earthwork and piling for Terminal 2 2018. 01. 18 Opening of Incheon International Airport Terminal 2
  • 10. Beginning of Terminal 2 construction in 2013's Opening of Terminal 2 in 2018's
  • 11. TERMINALS TERMINAL 1 • Terminal 1 (measuring 496,000 square meters) is the largest airport terminal in area in South Korea. • Terminal 1 was designed by Curtis W. Fentress, FAIA, RIBA of Fentress Architects. • It is 1,060 metres (3,480 ft) long, 149 metres (489 ft) wide, and 33 metres (108 ft) high. • Its construction cost was 1.3816 trillion South Korean Won. • The terminal has 44 boarding ports (all of which can accommodate the Airbus A380), 50 customs inspection ports, 2 biological quarantine counters, 6 stationary and 14 portable passenger quarantine counters, 120 arrival passport inspection counters, 8 arrival security ports, 28 departure security ports, 252 check in counters, and 120 departure passport inspection counters.
  • 12. CONCOURSE The passenger concourse was completed at the end of May 2008. It is connected to Terminal 1 by two parallel 870-metre-long (2,850 ft) underground passageways equipped with IATs (Intra Airport Transit). It has 30 gates and six lounges(Asiana Airlines/Star Alliance, Singapore Airlines/Star Alliance, Japan Airlines/Oneworld, Korean Air/SkyTeam, and China Eastern Airlines/SkyTeam). TERMINAL 2 • Terminal 2 which was constructed into the scale of 388,000㎡ (38.8 ha) in total floor area and 23 mil. in annual passenger capacity was opened on 18 Jan 2018. • Korean Air, KLM, Delta Air Lines, and Air France flights were relocated from Terminal 1 to Terminal 2. Many other SkyTeam members started serving the Terminal 2 on 28 October 2018. • The terminal will be expanded into a mega-size terminal with a total floor area of 735,000㎡ (73.5 ha) and annual passenger capacity of 52 mil. through the phase 4 construction.
  • 13.
  • 14. RUNWAY • The airport consists of three functional runway and a fourth runway under construction. • The airport configuration of ICN is shown in Fig. There are three parallel runways at ICN. Runway 33R/15L and 33L/15R are two parallel runways with the distance of 400m between them. Runway 33R/15L is used primarily for arrivals and 33L/15R is primarily for departures. Runway 34/16 is used for both departures and arrivals, and the usage is changed several times a day depending on the departure and arrival traffic demands. All cargo flights takeoff and land using the runways 33R/15L and 33L/15R, exclusively, whereas the passenger flights can use all three runways.
  • 15.
  • 16. DIRECTION WIDTH (M) LENGTH (M) STRENGTH(PCN) AND SURFACE OF RWY AND SWY RUNWAY 1 15R/33L 60 3750 ㆍ88/F/B/X/T Asphalt ㆍSWY and 300 m RWY ends are 86/R/B/X/T Concrete RUNWAY 2 15L/33R 60 3750 88/F/B/X/T Asphalt ㆍSWY and 300 m RWY ends are 86/R/B/X/T Concrete RUNWAY 3 16/34 60 4000 75/F/B/X/T Asphalt SWY and 700 m RWY ends are 85/R/B/X/T Concrete
  • 17. RUNWAY RUNWAY NAVIGATIONAL AIDS Instrument landing system (ILS) provides guidance and distance information so that airplanes can safely navigate through bad weather (fog, etc.). It is a landing guidance system that enables the pilot to land the plane following only the instrument. Aeronautical light facilities, which include approach lighting system, runway lighting system, etc., provide visual information needed for airplanes to safely make the landing. Uses facilities suited for CAT-III, provides a precision system that makes landing possible even when the visual range is only 75m. Lights - Edge lights are installed at 60 m intervals on all runways. - Centerline lights are installed at 15 m intervals on all runways. Markings : Runway Edges, Touchdown Zones, Aiming Points and Center line.
  • 18. Glide Path Provides landing angle (3˚) information to airplanes Marker(Inner/Middle) Provides position information of the designated space with runway thresholds Localizer Provides runway center line information to airplanes taking off and landing
  • 19. Wind Rose Diagram In the case of take – off operations, the head wind will help us in generating the lift, whereas during the landing operations the same wind will help in generating the drag, so as to stop the landing aircraft. So wind rose diagram provides data which is essential in determining the direction of the runaway.
  • 20.
  • 21. TAXIWAY TAXIWAY WIDTH, SURFACE AND STRENGTH: Width : 30 m 1.- Shoulder of TWY A/B/C/D : 15 m (Paved 12 m, Turfed 3m) 2.- Shoulder of TWY M/N : 15 m (Paved) Surface : Asphalt, Concrete Strength 1.TWY A, D : Concrete PCN 86/R/B/X/T 2.TWY B, C : Asphalt PCN 88/F/B/X/T 3.TWY M : Concrete PCN 85/R/B/W/T 4.TWY N : Asphalt PCN 75/F/B/W/T
  • 22. TAXIWAY LIGHTS - Edge lights are installed at 15 m intervals on all TWY curved areas and 60 m intervals of markers are in the rest of areas. - Centerline Lights are installed at 3.75∼7.5 m intervals on all TWY curved areas and 15 m intervals in the rest of areas. MARKINGS - TWY & taxi lane centerline markings are marked with a yellow solid line on the black base on all specified taxiways designated as the SMGCS (Surface Movement Guidance & Control System) taxiway routes
  • 23. APRONS 1.Apron1 : Concrete PCN 86/R/B/X/T 2.Apron2 : Concrete PCN 86/R/B/X/T 3.Apron3 : Concrete PCN 85/R/B/X/T 4.Cargo Apron1 : Concrete PCN 86/R/B/X/T 5.Cargo Apron2 : Concrete PCN 85/R/B/X/T 6.Maintenance Apron : Concrete PCN 86/R/B/X/T Attached Apron Remote Aprons Cargo Apron
  • 24. APRONS Type Phases 1, 2 Phase 3 Phase 4 (Net Increase) Total Attached Aprons 74 37 34 145 Remote Aprons 35 17 28 13 Cargo Aprons 36 11 13 60 Total 145 65 75 285
  • 25. HANGAR Seoul Incheon Airport - Asiana Airlines MRO (Maintenance Repair and Overhaul) Hangar Basic technical specifications of the hangar, constructed as a landmark for the leading Korean carrier Asiana Airlines are: •Hangar area 60.000 m² •Length 175 + 29 m, Width 97 + 24 m •Height 41 m •Capable of storing 2 jumbo and 1 smaller aircraft at the same time •Energy saving design, providing an inviting work environment for the staff
  • 26. Ongoing Development PHASE 4 (2017 – 2024) The demand for aviation market is expected to increase by at least twofold in the next 15 years (average annual growth rate of 4.4%). Incheon Airport has constantly grown at the average annual growth rate of around 7% after its opening. Construction Period 2017. 11 - 2024. 12 (7.5 years) Construction Items Expansion of Terminal 2 (+29 mil. PAX/year) One runway (Runway 4: 3,750m) (2.3 miles) Aprons, parking lots, roads, etc. Project Cost About 4.8 trillion won (412 mil. USD)
  • 27. CONSTRUCTION CONCEPT Green : Terminal 2 will be an eco-friendly airport that lives and breathes in nature utilizing a variety of plants to maintain freshness of indoor spaces. Also, the airport will maximize the production of new renewable energy in various ways including fuel cell in order to be reborn as the most environmentally-friendly airport in the world. Art : Various structures in the form of the sky will be built inside Terminal 2, creating artistic spaces that together form an art airport. Such artistic elements will provide a brighter and more open experience to the passengers and users. Smart : • Self Check – in ,Self Bag Drop • Speech recognition information Service • Biology Intelligence • AI-based intelligent CCTV • Passenger service using IoT technologies • Media art integrated into the building
  • 28.
  • 29.
  • 30. ACCOLADES Incheon International airport has been the recipient of a number of awards since its opening, including: •Best Airport Worldwide at the first Airport Service Quality Awards in 2007. •Won the GT Tested Award for Best Airport in the World in January 2007. •Named by Global Traveler (GT) as the Best Airport in the World for the second straight year in January 2008. •Named World's Best Airport for 2009, in the World Airport Survey results published by Skytrax. •In 2012 it was ranked the best airport in the world by Skytrax
  • 31. ACCIDENT UPS flight 5X61 suffered a runway excursion and nose gear collapse on take-off on 6 June 2016. The flight was cleared for takeoff from runway 33L. The aircraft reached V1 speed after a ground run of 6413 feet. About that time the crew heard a noise, originating from the failure of the no.9 tire (the left-hand tire on the central landing gear). The no.10 tire on the same landing gear also ruptured. Vibration and torsion forces then caused the lower drag brace of the central landing gear to break. The drag brace then hit the body several times. This caused a rupture of the hydraulic system of brake system 1, reducing the total brake efficiency to about 48% as the crew rejected the takeoff. With 4,635 feet of runway remaining the aircraft began to decelerate. The aircraft required a deceleration distance of at least about 5,550ft from the position where the takeoff was rejected. As a result, the MD-11 stopped at approximately 1,591 ft (485 m) past the end of the runway 33L. The nose gear collapsed and the no. 1 and 3 engines contacted the grass.
  • 32.