Kansai International Airport is located on an artificial island in Osaka Bay, Japan. It was an ambitious $14 billion project constructed between 1987 and 1994 to serve the major cities of Osaka, Kobe, and their surrounding regions. The airport was built offshore due to a lack of available land near existing airports and public opposition to expansion. However, the soft clay soils beneath the new island caused significant sinking issues, with the island settling over 27 feet instead of the predicted 19-25 feet. Engineers had to install hydraulic jacks and take other measures to stabilize the passenger terminal building. Future expansion plans aim to apply lessons learned to better predict and manage further soil consolidation.
Case study on the kansai international airportAglaia Connect
CASE STUDY ON THE KANSAI INTERNATIONAL AIRPORT
Kansai International Airport: Structural Case Study The components that make up this airport include a 3,000 meter long asphalt runway that receives almost 150 planes a day. This runway is open 24/7, something that would've been a concern if located in the mainland urban fabric.
interesting civil engineering topics
civil engineering topics for presentation
civil seminar topics ppt
civil engineering seminar topics 2018
best seminar topics for civil engineering
seminar topics pdf
seminar topics for mechanical engineers
seminar topic for civil engineering pdf
Harbour engineering - Railways, airports, docks and harbour engineering (RAHE)Shanmugasundaram N
Definition of Basic Terms: Harbour, Port, Satellite Port, Docks, Waves and Tides – Planning and Design of Harbours: Harbour Layout and Terminal Facilities – Coastal Structures: Piers, Break waters, Wharves, Jetties, Quays, Spring Fenders, Dolphins and Floating Landing Stage – Inland Water Transport – Wave action on Coastal Structures and Coastal Protection Works – Coastal Regulation Zone, 2011
Kansai International Airport (KIX) is an international airport located on an artificial island in the middle of Osaka Bay
First 24-hour operational airport in Japan
Opened on 4 September 1994
Constructed 5km offshore in Osaka bay as a man-made island
Diverse accesses by highway, railways and high-speed ferry are provided
Airport design - Railways, airports, docks and harbour engineering (RAHE)Shanmugasundaram N
Runway Design: Orientation, Wind Rose Diagram, Problems on basic and Actual Length, Geometric Design – Elements of Taxiway Design – Airport Zones – Passenger Facilities and Services – Runway and Taxiway Markings.
Case study on the kansai international airportAglaia Connect
CASE STUDY ON THE KANSAI INTERNATIONAL AIRPORT
Kansai International Airport: Structural Case Study The components that make up this airport include a 3,000 meter long asphalt runway that receives almost 150 planes a day. This runway is open 24/7, something that would've been a concern if located in the mainland urban fabric.
interesting civil engineering topics
civil engineering topics for presentation
civil seminar topics ppt
civil engineering seminar topics 2018
best seminar topics for civil engineering
seminar topics pdf
seminar topics for mechanical engineers
seminar topic for civil engineering pdf
Harbour engineering - Railways, airports, docks and harbour engineering (RAHE)Shanmugasundaram N
Definition of Basic Terms: Harbour, Port, Satellite Port, Docks, Waves and Tides – Planning and Design of Harbours: Harbour Layout and Terminal Facilities – Coastal Structures: Piers, Break waters, Wharves, Jetties, Quays, Spring Fenders, Dolphins and Floating Landing Stage – Inland Water Transport – Wave action on Coastal Structures and Coastal Protection Works – Coastal Regulation Zone, 2011
Kansai International Airport (KIX) is an international airport located on an artificial island in the middle of Osaka Bay
First 24-hour operational airport in Japan
Opened on 4 September 1994
Constructed 5km offshore in Osaka bay as a man-made island
Diverse accesses by highway, railways and high-speed ferry are provided
Airport design - Railways, airports, docks and harbour engineering (RAHE)Shanmugasundaram N
Runway Design: Orientation, Wind Rose Diagram, Problems on basic and Actual Length, Geometric Design – Elements of Taxiway Design – Airport Zones – Passenger Facilities and Services – Runway and Taxiway Markings.
Airport planning - Railways, airports, docks and harbour engineering (RAHE)Shanmugasundaram N
Air transport characteristics - airport classification – ICAO - airport planning: Site selection typical Airport Layouts, Case Studies, parking and Circulation Area
Aviation engineering is a branch of engineering which deals with airspace development, airport design, aircraft navigation technologies, and aerodrome planning. It also involves the formulation of public policy, regulations, aviation laws pertaining to airspace, airlines, airports, aerodromes and the conduct of air services agreements through treaty.
This branch of engineering is distinct from aerospace engineering which deals with the development of aircraft and spacecraft.
Bangalore International Airport Limited (BIAL) is a Build-Own-Operate-Transfer (BOOT) model. • The first phase of the airport consist of a 4000-metre long runway, taxiways and an apron area with aircraft stands and a terminal building. • The concession agreement between the Government of India and BIAL was signed in July 2004 and the airport became operational in May 2008. • Private promoters hold 74% stake in BIAL while the state holds the remaining 26%
Institute:- Agragami college
Name:- Amal Tom
Class:- 4th Semester BBA Aviation.
Roll No:- G1811009 OR 09
Subject:- Aviation
Topic:- Airport Planning.and Design
www.jetlinemarvel.net
This paper aims to review one of the valuable large scale architectural/structural projects, Kansai International Airport, that may provide insights for some of the large scale developments today.
Aims
To gain a better understanding of land reclamation process as one of the cutting edge techniques for gaining land for human to live on the earth
To acquire better knowledge about some of the engineering advancements in the world
To get a deeper understanding of the process of problem-solving in planning and design of large scale projects
To develop our knowledge about inter-disciplinary design among architecture and civil engineering
Airport planning - Railways, airports, docks and harbour engineering (RAHE)Shanmugasundaram N
Air transport characteristics - airport classification – ICAO - airport planning: Site selection typical Airport Layouts, Case Studies, parking and Circulation Area
Aviation engineering is a branch of engineering which deals with airspace development, airport design, aircraft navigation technologies, and aerodrome planning. It also involves the formulation of public policy, regulations, aviation laws pertaining to airspace, airlines, airports, aerodromes and the conduct of air services agreements through treaty.
This branch of engineering is distinct from aerospace engineering which deals with the development of aircraft and spacecraft.
Bangalore International Airport Limited (BIAL) is a Build-Own-Operate-Transfer (BOOT) model. • The first phase of the airport consist of a 4000-metre long runway, taxiways and an apron area with aircraft stands and a terminal building. • The concession agreement between the Government of India and BIAL was signed in July 2004 and the airport became operational in May 2008. • Private promoters hold 74% stake in BIAL while the state holds the remaining 26%
Institute:- Agragami college
Name:- Amal Tom
Class:- 4th Semester BBA Aviation.
Roll No:- G1811009 OR 09
Subject:- Aviation
Topic:- Airport Planning.and Design
www.jetlinemarvel.net
This paper aims to review one of the valuable large scale architectural/structural projects, Kansai International Airport, that may provide insights for some of the large scale developments today.
Aims
To gain a better understanding of land reclamation process as one of the cutting edge techniques for gaining land for human to live on the earth
To acquire better knowledge about some of the engineering advancements in the world
To get a deeper understanding of the process of problem-solving in planning and design of large scale projects
To develop our knowledge about inter-disciplinary design among architecture and civil engineering
Incheon International Airport is the largest airport in South Korea and is one of the largest airports in the world. It is located on an artificially created piece of land between two islands.
The airport is equipped with the latest technology and follows the concept of Green, Art, and Smart.
This slide is a case study of the airport to detail about the structures present in the airport from the Civil Engineering aspect.
Kansai International AirportOpened on 4 September 1994, the airp.docxcareyshaunda
Kansai International Airport
Opened on 4 September 1994, the airport serves as a hub for several airlines such as All Nippon Airways, Japan Airlines, and Nippon Cargo Airlines. It is the international gateway for Japan's
Kansai region
, which contains the major cities of
Kyoto
, Kobe, and Osaka. Other Kansai
DOMESTIC FLIGHTS
fly from the older but more conveniently located Osaka International Airport in
Itami
, or from the newer Kobe Airport.
The airport had been deeply in debt, losing $560 million in interest every year. Airlines had been kept away by high landing fees (about $7,500 for a
Boeing 747
), the second most expensive in the world after Narita's. In the early years of the airport's operation, excessive terminal rent and
UTILITY BILLS
for on-site concessions also drove up operating costs: some estimates before opening held that a cup of coffee would have to cost US$10.
[19]
Osaka business owners pressed the government to take a greater burden of the construction cost to keep the airport attractive to passengers and airlines.
[20]
On 17 February 2005,
Chubu Centrair International Airport
opened in
Nagoya
, just east of Osaka. The opening of the airport was expected to increase competition between Japan's international airports. Despite this, passenger totals were up 11% in 2005 over 2004, and international passengers increased to 3.06 million in 2006, up 10% over 2005. Adding to the competition was the opening of Kobe Airport, less than 25 km (16 mi) away, in 2006 and the lengthening of the runway at
Tokushima Airport
in
Shikoku
in 2007. The main rationale behind the expansions was to compete with
Incheon International Airport
and
Hong Kong International Airport
as a gateway to Asia, as Tokyo area airports were severely congested. Kansai saw an 5% year-on-year increase in international traffic in summer 2013, largely supported by
low-cost carrier
traffic to
Taiwan
and Southeast Asia overcoming a decrease in traffic to China and
South Korea
.
[21]
The airport authority was allotted 4 billion yen in government support for fiscal year 2013, and the Ministry of Land, Infrastructure and Transport and Ministry of Finance have agreed to reduce this amount in stages through fiscal year 2015, although local governments in the Kansai region have pressed for
CONTINUED
subsidies.
[22]
Kansai has been marketed as an alternative to Narita Airport for international travelers from the
Greater Tokyo Area
. By flying to Kansai from
Haneda Airport
and connecting to
INTERNATIONAL FLIGHTS
there, travelers can save the additional time required to get to Narita: up to one and a half hours for many residents of
Kanagawa Prefecture
and southern Tokyo.
.
Kansai International Airport (KIX) is an international airport located on an artificial island in the middle of Osaka Bay, 38 km (24 mi) southwest of Osaka Station, located within three municipalities, including Izumisano (north), Sennan (south), and Tajiri (central), in Osaka prefecture, Japan. It is the first 24-hour operational airport in Japan and constructed 5km offshore in Osaka bay as a man-made island in order to avoid the impact of aircraft noise on residential areas (Figure 1.1). Kansai opened 4 September 1994 to relieve overcrowding at Osaka International Airport. An artificial island, 4 km (2.5 mi) long and 2.5 km (1.6 mi) wide, was proposed.Kansai International airport features 24-hour operability, convenience of transfer between international and domestic flights, and diverse accesses by highway, railways and high-speed ferry.
Aviation engineering is a branch of engineering which deals with airspace development, airport design, aircraft navigation technologies, and aerodrome planning. It also involves the formulation of public policy, regulations, aviation laws pertaining to airspace, airlines, airports, aerodromes and the conduct of air services agreements through treaty.
This branch of engineering is distinct from aerospace engineering which deals with the development of aircraft and spacecraft.
Unit 8 - Information and Communication Technology (Paper I).pdfThiyagu K
This slides describes the basic concepts of ICT, basics of Email, Emerging Technology and Digital Initiatives in Education. This presentations aligns with the UGC Paper I syllabus.
The French Revolution, which began in 1789, was a period of radical social and political upheaval in France. It marked the decline of absolute monarchies, the rise of secular and democratic republics, and the eventual rise of Napoleon Bonaparte. This revolutionary period is crucial in understanding the transition from feudalism to modernity in Europe.
For more information, visit-www.vavaclasses.com
Model Attribute Check Company Auto PropertyCeline George
In Odoo, the multi-company feature allows you to manage multiple companies within a single Odoo database instance. Each company can have its own configurations while still sharing common resources such as products, customers, and suppliers.
Introduction to AI for Nonprofits with Tapp NetworkTechSoup
Dive into the world of AI! Experts Jon Hill and Tareq Monaur will guide you through AI's role in enhancing nonprofit websites and basic marketing strategies, making it easy to understand and apply.
Palestine last event orientationfvgnh .pptxRaedMohamed3
An EFL lesson about the current events in Palestine. It is intended to be for intermediate students who wish to increase their listening skills through a short lesson in power point.
Operation “Blue Star” is the only event in the history of Independent India where the state went into war with its own people. Even after about 40 years it is not clear if it was culmination of states anger over people of the region, a political game of power or start of dictatorial chapter in the democratic setup.
The people of Punjab felt alienated from main stream due to denial of their just demands during a long democratic struggle since independence. As it happen all over the word, it led to militant struggle with great loss of lives of military, police and civilian personnel. Killing of Indira Gandhi and massacre of innocent Sikhs in Delhi and other India cities was also associated with this movement.
2024.06.01 Introducing a competency framework for languag learning materials ...Sandy Millin
http://sandymillin.wordpress.com/iateflwebinar2024
Published classroom materials form the basis of syllabuses, drive teacher professional development, and have a potentially huge influence on learners, teachers and education systems. All teachers also create their own materials, whether a few sentences on a blackboard, a highly-structured fully-realised online course, or anything in between. Despite this, the knowledge and skills needed to create effective language learning materials are rarely part of teacher training, and are mostly learnt by trial and error.
Knowledge and skills frameworks, generally called competency frameworks, for ELT teachers, trainers and managers have existed for a few years now. However, until I created one for my MA dissertation, there wasn’t one drawing together what we need to know and do to be able to effectively produce language learning materials.
This webinar will introduce you to my framework, highlighting the key competencies I identified from my research. It will also show how anybody involved in language teaching (any language, not just English!), teacher training, managing schools or developing language learning materials can benefit from using the framework.
3. Key Features
Located on a biggest man-made island in Osaka
Bay about 50km south of Osaka, Japan
Constructed cost over $14 billion
The island of 4km long and 2.5km wide, was
proposed
Project Started in 1987
Opened for flights in 1994
The ASCE named KIA the #2 civil engineering
project of the 20th century, second only to the
Panama Canal
4. History
In the 1960s, when the Kansai region was rapidly losing trade to Tokyo
, planners proposed a new airport near Kobe and Osaka. Osaka
International Airport, located in the densely populated suburbs of Itami
and Toyonaka, was surrounded by buildings; it could not be expanded,
and many of its neighbours had filed complaints because of noise
pollution problems.
After the protests surrounding New Tokyo International Airport (now
Narita International Airport), which was built with expropriated land in
a rural part of Chiba Prefecture, planners decided to build the airport
offshore. The new airport was part of a number of new developments to
revitalize Osaka, which had lost economic and cultural ground to
Tokyo for most of the century.
5. Initially, the airport was planned to be built near Kobe, but the city of
Kobe refused the plan, so the airport was moved to a more southerly
location on Osaka Bay.
KANSAI INTERNATIONAL AIRPORT
11. Second phase KIA
The second runway opened on 2 August 2007,
but without the originally planned terminal
portion, now postponed to a later date.
12. Second phase has expanded the airport size to
10.5 sq. km
Further into the future, the airport is planning to
construct a new terminal building (scheduled to
open in late 2012), a third runway with a length
of 3,500 m, a new cargo terminal and
expanding the airport size to 13 km2
.
15. FLIGHTS
Weekly international passenger flights: 710
Weekly international freighter flights: 152
Weekly domestic (passenger and freighter)
flights: 495
16. Problem caused after completion of
Airport
Airport goes on sinking, sinking prediction are
as follows:
Lack of experience with construction on deep
deposit of diluvial clay
Expected settlement = 19 to 25 ft.
Actual settlement = 27 ft. (by the end of island
construction in 1990)
It continued at the rate of 2 in/month
17. What Went Wrong in Predictions?
Un-conservative estimation of consolidation
settlement
Wrong estimate of the time required for
completion of consolidation settlement
Ineffectiveness of the sand drains in achieving
the required success 100%
18. Coping With The Problem of Continued
Settlement
Basement of the terminal was lined with a
quarter of a million tons of iron ore.
Result: Island sank faster than the building it is
trying to hold
Installation of hydraulic jacks under the
columns.
Result: No differential settlement between the
columns of entire building
19. Learning From Mistakes
Using data actual settlement data obtained from
1st
phase of project
Analysis of 400-m-deep boring exploration
State-of-the-art soil test methods
Expected Settlement = 18 m
20. Present
Kansai International Airport (KIX) is Japan's second
most important international airport.
Kansai Airport has two terminal buildings: the main
terminal building (terminal 1) serves international
and domestic flights by regular airlines, while a
second terminal building (terminal 2) serves
international and domestic flights by low-cost
airlines. Various train and bus lines connect the
airport with the nearby cities of Osaka, Kyoto, Kobe
and surroundings.