1. ID
Task/Milestone Responsible Activity A - / + % Complete Start Finish Duration
1 CNO Advance Planning Process SEA 21 0%
2 Establish CNO/CM Availability Schedule TYCOM (CNSP) A‐720 100% Tue 4/8/14 Tue 4/8/14 0 days
3 Fund Modernization Procurement & Installation /
Decision Point 3 in the SCD Process
PARM/TYCOM Variable 100% Mon 3/28/16 Mon 3/28/16 0 days
4 Issue Execution Planning Hull Modernization Plan
(EPHMP)
SPM Variable 100% Mon 3/28/16 Mon 3/28/16 0 days
5 Issue 2 Year Rolling Advance Planning Hull
Modernization Plan (AHMP)
SPM Variable 100% Mon 3/28/16 Mon 3/28/16 0 days
6 Planning Yard (PY) Submit Funding Request for Work
Assigned
Planning Yard (PY) A‐480 100% Thu 12/4/14 Thu 12/4/14 0 days
7 SC Design/Planning Funds Provided PARM/SPM/TYCOM A‐425 100% Wed 1/28/15 Wed 1/28/15 0 days
8 Send Habitability Project Advance Planning Notice TYCOM N43 A‐420 100% Mon 2/2/15 Mon 2/2/15 0 days
9 Installation Control Drawings (ICDs) / Installation
Requirements Drawings / delivered to Alteration
Developer/Planning Yard (PY)
PARM A‐420 100% Mon 2/2/15 Mon 2/2/15 0 days
10 Issue request for the EP Proposal to the Planning
Activity. Notify each funding sponsor of the
requirement and amount of funding for Execution
Planning. Provide NLT date for required funding
RMC C300 A‐410 100% Thu 2/12/15 Thu 2/12/15 0 days
11 Accomplish SURFMEPP Mid‐Cycle Review SURFMEPP A‐410 100% Thu 2/12/15 Thu 2/12/15 0 days
12 Provide Funding for Execution Planning PARM/SPM/TYCOM A‐365 100% Sun 3/29/15 Sun 3/29/15 0 days
13 Provide Availability Financial Target Control SPM/TYCOM A‐360 100% Fri 4/3/15 Fri 4/3/15 0 days
14 Issue Initial Letter of Authorization (LOA) (Including
AITs)/Hull Modernization Plan
SPM/TYCOM A‐360 100% Fri 4/3/15 Fri 4/3/15 0 days
15 CNO Planning Process RMC 0%
16 Definitize Execution Planing RMC C400 A‐360 100% Fri 4/3/15 Fri 4/3/15 0 days
17 Establish Availability in the appropriate IT System RMC C300 A‐360 100% Fri 4/3/15 Fri 4/3/15 0 days
18 Advance Planning to Planning Event NRMC C300 A‐355 100% Wed 4/8/15 Wed 4/8/15 0 days
19 Task/Fund SID Development SPM/NSA/AIT/TYCOM A‐330 100% Sun 5/3/15 Sun 5/3/15 0 days
/14 100%
CM Availability Schedule
3/28/16 100%
Fund Modernization Procurement & Installation / Decision Point 3 in the SCD
3/28/16 100%
Issue Execution Planning Hull Modernization Plan (EPHMP)
3/28/16 100%
Issue 2 Year Rolling Advance Planning Hull Modernization Plan (AHMP
12/4/14 100%
g Yard (PY) Submit Funding Request for Work Assigned
1/28/15 100%
SC Design/Planning Funds Provided
2/2/15 100%
Send Habitability Project Advance Planning Notice
2/2/15 100%
) / Installation Requirements Drawings / delivered to Alteration Developer/Planning Yard (PY)
2/12/15 100%
ach funding sponsor of the requirement and amount of funding for Execution Planning. Provide N
2/12/15 100%
Accomplish SURFMEPP Mid-Cycle Review
3/29/15 100%
Provide Funding for Execution Planning
4/3/15 100%
Provide Availability Financial Target Control
4/3/15 100%
itial Letter of Authorization (LOA) (Including AITs)/Hull Modernization Plan
4/3/15 100%
Definitize Execution Planing
4/3/15 100%
Establish Availability in the appropriate IT System
4/8/15 100%
Advance Planning to Planning Event
5/3/15 100%
Task/Fund SID Development
Feb Jun Oct Feb Jun Oct Feb Jun Oct Feb
er 4th Quarter 3rd Quarter 2nd Quarter 1st Quarter
2nd Half 1st Half
Robert P. Irelan
Team Lead/LHD Hull Manager
LHD Maintenance and Modernization
Project Management Team (PMT)
PMS-407
Michael A. Esparza , PMP, DMBM
Version: 5/21/15 UNCLASSIFIED - PORTFOLIO EXAMPLE 1
2. ID
Task/Milestone Responsible Activity A - / + % Complete Start Finish Duration
20 Modernization Ship Checks Completed Planning Yard (PY) A‐300 0% Tue 6/2/15 Tue 6/2/15 0 days
21 Provide Incremental Funds for ordering LLTM for both
repair and Alt/Mod work to meet required dates
SYSCOM/SPM/TYCOM A‐270 0% Thu 7/2/15 Thu 7/2/15 0 days
22 50% of D Level Mainteance Work package
development; 2Ks have been screened based on target
control
TYCOM A‐240 0% Sat 8/1/15 Sat 8/1/15 0 days
23 Submit A‐240 Deferral Letter with Maintenance Team
Assist
TYCOM A‐240 0% Sat 8/1/15 Sat 8/1/15 0 days
24 TSRA‐1 Discrepancies Screened Ashore Ship's Maintenance
Manager
A‐240 0% Sat 8/1/15 Sat 8/1/15 0 days
25 Issue/Deliver SIDs to NSA for KTRs and AITs Planning Yard (PY) A‐210 0% Mon 8/31/15 Mon 8/31/15 0 days
26 IPTD Strategy Development NRMC C300 A‐190 0% Sun 9/20/15 Sun 9/20/15 0 days
27 Planning Activity complete planning and estimating of
work assigned as required by the 50% package
KTR A‐190 0% Sun 9/20/15 Sun 9/20/15 0 days
28 IGE Submitted in support of 50% of package
development
RMC C300 A‐190 0% Sun 9/20/15 Sun 9/20/15 0 days
29 Estimate Comparison complete in support of 50%
package development
RMC C400/C300 A‐180 0% Wed 9/30/15 Wed 9/30/15 0 days
30 LOA Change 1 Issued SPM A‐180 0% Wed 9/30/15 Wed 9/30/15 0 days
31 A‐180 IPTD Event RMC A‐180 0% Wed 9/30/15 Wed 9/30/15 0 days
32 All Modernization Risk Assessments (Including
waivers)submitted
PARM/SPM/TYCOM A‐175 0% Mon 10/5/15 Mon 10/5/15 0 days
33 Risk Letter sent to CNRMC RMC Code 100 A‐170 0% Sat 10/10/15 Sat 10/10/15 0 days
34 80% of D‐Level Manitenance Work Package
Development 2K's have been screened based on target
control
TYCOM A‐155 0% Sun 10/25/15 Sun 10/25/15 0 days
35 All Modernization Risk Assessments (including Waivers)
approved
FLEET / TYCOM A‐150 0% Fri 10/30/15 Fri 10/30/15 0 days
36 Award AIT Contracts for work NOT being done by
Prime KTR / ID all outside activities participating in the
avail and associated support requirements
AIT Sponsor / TYCOM N43 / SEA
21
A‐150 0% Fri 10/30/15 Fri 10/30/15 0 days
37 ID of AIT Support Requirements and POA&M Provided AIT Manager A‐135 0% Sat 11/14/15 Sat 11/14/15 0 days
38 TSRA‐2 Discrepancies screened Ashore Ship Maintenance
Manager
A‐128 0% Sat 11/21/15 Sat 11/21/15 0 days
6/2/15 0%
Modernization Ship Checks Completed
7/2/15 0%
remental Funds for ordering LLTM for both repair and Alt/Mod work to meet required dates
8/1/15 0%
Level Mainteance Work package development; 2Ks have been screened based on target control
8/1/15 0%
Submit A-240 Deferral Letter with Maintenance Team Assist
8/1/15 0%
TSRA-1 Discrepancies Screened
8/31/15 0%
Issue/Deliver SIDs to NSA for KTRs and AITs
9/20/15 0%
IPTD Strategy Development
9/20/15 0%
nning Activity complete planning and estimating of work assigned as required by the 50% packag
9/20/15 0%
IGE Submitted in support of 50% of package development
9/30/15 0%
Estimate Comparison complete in support of 50% package development
9/30/15 0%
LOA Change 1 Issued
9/30/15 0%
A-180 IPTD Event
10/5/15 0%
All Modernization Risk Assessments (Including waivers)submitted
10/10/15 0%
Risk Letter sent to CNRMC
10/25/15 0%
% of D-Level Manitenance Work Package Development 2K's have been screened based on target c
10/30/15 0%
All Modernization Risk Assessments (including Waivers) approved
10/30/15 0%
work NOT being done by Prime KTR / ID all outside activities participating in the avail and assoc
11/14/15 0%
ID of AIT Support Requirements and POA&M Provided
11/21/15 0%
TSRA-2 Discrepancies screened
Feb Jun Oct Feb Jun Oct Feb Jun Oct Feb
er 4th Quarter 3rd Quarter 2nd Quarter 1st Quarter
2nd Half 1st Half
Robert P. Irelan
Team Lead/LHD Hull Manager
LHD Maintenance and Modernization
Project Management Team (PMT)
PMS-407
Michael A. Esparza , PMP, DMBM
Version: 5/21/15 UNCLASSIFIED - PORTFOLIO EXAMPLE 2
3. ID
Task/Milestone Responsible Activity A - / + % Complete Start Finish Duration
39 Conduct Work Package Integration Conference (WPIC) RMC C300 A‐120 0% Sun 11/29/15 Sun 11/29/15 0 days
40 LOA Change 2, 100% Modernization Lock SPM A‐120 0% Sun 11/29/15 Sun 11/29/15 0 days
41 Submit A‐120 Deferral Letter with Maintenance Team
Assist
TYCOM A‐120 0% Sun 11/29/15 Sun 11/29/15 0 days
42 Planning Activity complete planning and estimating of
work assigned as required by the 80% Package
Development (Event 32)
Planning Activity A‐120 0% Sun 11/29/15 Sun 11/29/15 0 days
43 IGE submitted ISO 80% package development RMC C300 A‐120 0% Sun 11/29/15 Sun 11/29/15 0 days
44 100% of D‐Level Maintenance Work Package 2K's
locked based on target control
Ashore Ship Maintenance
Manager
A‐120 0% Sun 11/29/15 Sun 11/29/15 0 days
45 Submit Execution Risk Letter RMC Code 100 A‐110 0% Wed 12/9/15 Wed 12/9/15 0 days
46 Estimate Comparison complete ISO 80% Package
Development
RMC C400 / C300 A‐110 0% Wed 12/9/15 Wed 12/9/15 0 days
47 100% of D‐Level maintenance work package 2Ks
planned and estimated
Planning Activity A‐106 0% Sun 12/13/15 Sun 12/13/15 0 days
48 Final Work Item Review / Approval RMC C300 A‐104 0% Tue 12/15/15 Tue 12/15/15 0 days
49 Planning Activity "Publish" package in the appropriate
IT System
Planning Activity A‐104 0% Tue 12/15/15 Tue 12/15/15 0 days
50 I‐Level Work Package FULLY brokered Ashore Ship Maintenance
Manager
A‐90 0% Tue 12/29/15 Tue 12/29/15 0 days
51 IGE Submitted ISO 100% Lock RMC C300 A‐78 0% Sun 1/10/16 Sun 1/10/16 0 days
52 KTR submit final package cost proposal KTR A‐76 0% Tue 1/12/16 Tue 1/12/16 0 days
53 I‐Level Work Package FULLY Accepted RMC Code 900 A‐75 0% Wed 1/13/16 Wed 1/13/16 0 days
54 100% of O‐Level maintenance work package locked Ship's Force A‐75 0% Wed 1/13/16 Wed 1/13/16 0 days
55 Submit I‐Level work package and schedule model for
integration
RMC C900 A‐60 0% Thu 1/28/16 Thu 1/28/16 0 days
56 Complete TAR RMC C400 A‐55 0% Tue 2/2/16 Tue 2/2/16 0 days
57 Establish Prorate based on final cost proposal RMC C400 / RMC C300 / SEA 21
/ PMR / TYCOM N43
A‐55 0% Tue 2/2/16 Tue 2/2/16 0 days
58 Submit Funding Request to Funding Sponsors RMC C300 A‐55 0% Tue 2/2/16 Tue 2/2/16 0 days
11/29/15 0%
Conduct Work Package Integration Conference (WPIC)
11/29/15 0%
LOA Change 2, 100% Modernization Lock
11/29/15 0%
Submit A-120 Deferral Letter with Maintenance Team Assist
11/29/15 0%
ctivity complete planning and estimating of work assigned as required by the 80% Package Deve
11/29/15 0%
IGE submitted ISO 80% package development
11/29/15 0%
100% of D-Level Maintenance Work Package 2K's locked based on target control
12/9/15 0%
Submit Execution Risk Letter
12/9/15 0%
Estimate Comparison complete ISO 80% Package Development
12/13/15 0%
100% of D-Level maintenance work package 2Ks planned and estimated
12/15/15 0%
Final Work Item Review / Approval
12/15/15 0%
Planning Activity "Publish" package in the appropriate IT System
12/29/15 0%
I-Level Work Package FULLY brokered
1/10/16 0%
IGE Submitted ISO 100% Lock
1/12/16 0%
KTR submit final package cost proposal
1/13/16 0%
I-Level Work Package FULLY Accepted
1/13/16 0%
100% of O-Level maintenance work package locked
1/28/16 0%
Submit I-Level work package and schedule model for integration
2/2/16 0%
Complete TAR
2/2/16 0%
Establish Prorate based on final cost proposal
2/2/16 0%
Submit Funding Request to Funding Sponsors
Feb Jun Oct Feb Jun Oct Feb Jun Oct Feb
er 4th Quarter 3rd Quarter 2nd Quarter 1st Quarter
2nd Half 1st Half
Robert P. Irelan
Team Lead/LHD Hull Manager
LHD Maintenance and Modernization
Project Management Team (PMT)
PMS-407
Michael A. Esparza , PMP, DMBM
Version: 5/21/15 UNCLASSIFIED - PORTFOLIO EXAMPLE 3
4. ID
Task/Milestone Responsible Activity A - / + % Complete Start Finish Duration
59 Pre‐Business Clearance Approved within C400 RMC C400 A‐45 0% Fri 2/12/16 Fri 2/12/16 0 days
60 Provide Availability Funding for Repair and
Modernization to RMC
SYSCOMS / SPM / TYCOM A‐45 0% Fri 2/12/16 Fri 2/12/16 0 days
61 Pre‐BCM routed and approved through SEA 02 RMC C400 / SEA 02 A‐40 0% Wed 2/17/16 Wed 2/17/16 0 days
62 Final Negotiations RMC C400 / SEA 02 A‐38 0% Fri 2/19/16 Fri 2/19/16 0 days
63 Post BCM drafted within C400 RMC C400 A‐35 0% Mon 2/22/16 Mon 2/22/16 0 days
64 CHINFO Release RMC C400 A‐32 0% Thu 2/25/16 Thu 2/25/16 0 days
65 Post BCM routed and approved through SEA 02 RMC C400 / SEA 02 A‐30 0% Sat 2/27/16 Sat 2/27/16 0 days
66 Definitize Work Package RMC C400 A‐30 0% Sat 2/27/16 Sat 2/27/16 0 days
67 Deliver Material (LLTM and kitted materials) to
executing activity
Planning Yard (PY) / PARMS A‐30 0% Sat 2/27/16 Sat 2/27/16 0 days
68 Conduct Work Package Execution Review (WPER) RMC C300 A‐30 0% Sat 2/27/16 Sat 2/27/16 0 days
69 LHD‐2 FY‐16 Availability Execution 0%
70 USS ESSEX (LHD‐2) PMA 3‐1 FY‐16 Ship's Force / MT / Industrial
Activity
A‐0 0% Mon 3/28/16 Fri 2/24/17 333 days
71 Start of Availability (SOA) Ship's Force / MT / Industrial
Activity
A+0 0% Mon 3/28/16 Mon 3/28/16 0 days
72 Avail Start: Start ILO and Combat Systems Technical
Training
Ship's Force / MT / Industrial
Activity
A+0 0% Mon 3/28/16 Mon 3/28/16 0 days
73 Send Start Message to Fleet Commander Ship's Force / MT / Industrial
Activity
A+0 0% Mon 3/28/16 Mon 3/28/16 0 days
74 Cancel all OUTSTANDING CASREPS which are scheduled
to be corrected during the avail
Ship's Force / MT / Industrial
Activity
A+0 0% Mon 3/28/16 Thu 3/31/16 3 days
75 USS ESSEX (LHD‐2) transit to designated Industrial
Facility/Pier
Ship's Force / MT / Industrial
Activity
A+7 0% Mon 4/4/16 Mon 4/4/16 0 days
76 Arrival Conference Ship's Force / MT / Industrial
Activity
A+8 0% Tue 4/5/16 Fri 4/8/16 3 days
77 Crew Move Ashore Ship's Force / MT / Industrial
Activity
A+8 0% Tue 4/5/16 Tue 4/5/16 0 days
78 LAN Migration Ship's Force / MT / Industrial
Activity
A+8 0% Tue 4/5/16 Tue 4/12/16 7 days
2/12/16 0%
Pre-Business Clearance Approved within C400
2/12/16 0%
Provide Availability Funding for Repair and Modernization to RMC
2/17/16 0%
Pre-BCM routed and approved through SEA 02
2/19/16 0%
Final Negotiations
2/22/16 0%
Post BCM drafted within C400
2/25/16 0%
CHINFO Release
2/27/16 0%
Post BCM routed and approved through SEA 02
2/27/16 0%
Definitize Work Package
2/27/16 0%
Deliver Material (LLTM and kitted materials) to executing activity
2/27/16 0%
Conduct Work Package Execution Review (WPER)
3/28/16 2/24/1
USS ESSEX (LHD-2) PMA 3-1 FY-16
3/28/16 0%
Start of Availability (SOA)
3/28/16 0%
Avail Start: Start ILO and Combat Systems Technical Training
3/28/16 0%
Send Start Message to Fleet Commander
3/28/16 3/31/16
Cancel all OUTSTANDING CASREPS which are scheduled to be corrected during
4/4/16 0%
USS ESSEX (LHD-2) transit to designated Industrial Facility/Pier
4/5/16 4/8/16
Arrival Conference
4/5/16 0%
Crew Move Ashore
4/5/16 0%
LAN Migration
Feb Jun Oct Feb Jun Oct Feb Jun Oct Feb
er 4th Quarter 3rd Quarter 2nd Quarter 1st Quarter
2nd Half 1st Half
Robert P. Irelan
Team Lead/LHD Hull Manager
LHD Maintenance and Modernization
Project Management Team (PMT)
PMS-407
Michael A. Esparza , PMP, DMBM
Version: 5/21/15 UNCLASSIFIED - PORTFOLIO EXAMPLE 4
5. ID
Task/Milestone Responsible Activity A - / + % Complete Start Finish Duration
79 25% Conference Ship's Force / MT / Industrial
Activity
A+83 0% Wed 7/20/16 Wed 7/20/16 0 days
80 Light Off Assessment (LOA) Ship's Force / MT / Industrial
Activity
A+147 0% Mon 8/22/16 Sat 8/27/16 5 days
81 Combat Systems Light Off (CSLO) Ship's Force / MT / Industrial
Activity
A+163 0% Wed 9/7/16 Wed 9/7/16 0 days
82 50% Conference Ship's Force / MT / Industrial
Activity
A+166 0% Sat 9/10/16 Sat 9/10/16 0 days
83 Production Completion Date (PCD) Ship's Force / MT / Industrial
Activity
A+231 0% Mon 11/14/16 Mon 11/14/16 0 days
84 Crew Move Aboard Ship's Force / MT / Industrial
Activity
A+244 0% Sun 11/27/16 Sun 11/27/16 0 days
85 75% Conference Ship's Force / MT / Industrial
Activity
A+250 0% Sat 12/3/16 Sat 12/3/16 0 days
86 Fuel Onload Ship's Force / MT / Industrial
Activity
A+274 0% Tue 12/27/16 Thu 12/29/16 2 days
87 NAVCERT Ship's Force / MT / Industrial
Activity
A+306 0% Sat 1/28/17 Tue 2/7/17 10 days
88 Fast Cruise Ship's Force / MT / Industrial
Activity
A+318 0% Wed 2/8/17 Thu 2/9/17 1 day
89 Sea Trials Ship's Force / MT / Industrial
Activity
A+292 0% Fri 2/10/17 Mon 2/13/17 3 days
90 MSMO/KTR Warranty Period Ship's Force / MT / Industrial
Activity
A+323 0% Tue 2/14/17 Fri 2/24/17 10 days
91 End of Availability (EOA) Ship's Force / MT / Industrial
Activity
C=333 0% Fri 2/24/17 Fri 2/24/17 0 days
92 SCDs /Alts 0%
93 SCD 5091 RHIB Davit Industrial Activty 0% Mon 3/28/16 Fri 7/22/16 116 days
94 SCD 6060 ‐ Variable Speed Drive Fire Pumps Industrial Activty 0% Sat 7/16/16 Sun 11/13/16 120 days
95 SCD 11159 LHD‐2 SSTG Replacement Production
Schedule
Industrial Activty 0% Mon 3/28/16 Thu 9/29/16 185 days
96 SCD 12035 Joint Strike Fighter (JSF)
Modernization/Production (Restoraton of Services)
Industrial Activty 0% Mon 3/28/16 Sat 6/11/16 75 days
97 SCD 71516 F‐35 Autonomic Logistics Information
System (ALIS)
Industrial Activty 0% Mon 3/28/16 Mon 3/28/16 0 days
98 SCD 1492 HESS (400 Hz) Industrial Activty 0% Mon 3/28/16 Sun 9/18/16 174 days
7/20/16 0%
25% Conference
8/22/16 8/27/16
Light Off Assessment (LOA)
9/7/16 0%
Combat Systems Light Off (CSLO)
9/10/16 0%
50% Conference
11/14/16 0%
Production Completion Date (PCD
11/27/16 0%
Crew Move Aboard
12/3/16 0%
75% Conference
12/27/16 12/29/16
Fuel Onload
1/28/17 2/7/17
NAVCERT
2/8/17 2/9/17
Fast Cruise
2/10/17 2/13/1
Sea Trials
2/14/17 2/24/1
MSMO/KTR Warranty
2/24/1
End of Availability (E
3/28/16 7/22/16
SCD 5091 RHIB Davit
7/16/16 11/13/16
SCD 6060 - Variable Speed Drive Fire Pump
3/28/16 9/29/16
SCD 11159 LHD-2 SSTG Replacement Production Schedu
3/28/16 6/11/16
SCD 12035 Joint Strike Fighter (JSF) Modernization/Production (Restoraton
3/28/16 0%
SCD 71516 F-35 Autonomic Logistics Information System (ALIS)
3/28/16 9/18/16
SCD 1492 HESS (400 Hz)
Feb Jun Oct Feb Jun Oct Feb Jun Oct Feb
er 4th Quarter 3rd Quarter 2nd Quarter 1st Quarter
2nd Half 1st Half
Robert P. Irelan
Team Lead/LHD Hull Manager
LHD Maintenance and Modernization
Project Management Team (PMT)
PMS-407
Michael A. Esparza , PMP, DMBM
Version: 5/21/15 UNCLASSIFIED - PORTFOLIO EXAMPLE 5
6. ID
Task/Milestone Responsible Activity A - / + % Complete Start Finish Duration
99 SCD 1497 AESS (270VDC) Industrial Activty 0% Mon 3/28/16 Sun 9/18/16 174 days
100 SCD 1563 JSF Weapons Support (F‐35) Industrial Activty 0% Mon 3/28/16 Sun 9/11/16 167 days
101 SCD 1575 JSF Tramline Relocation Industrial Activty 0% Mon 3/28/16 Tue 7/26/16 120 days
102 SCD 1621 JSF Pyro Prep and AECM Room Relocation Industrial Activty 0% Mon 3/28/16 Sun 9/11/16 167 days
103 SCD 1743 JSF DMRT/OMS Industrial Activty 0% Mon 3/28/16 Sun 9/11/16 167 days
104 SCD 11531 JSF AFFF Staging Area Industrial Activty 0% Mon 3/28/16 Fri 10/28/16 214 days
105 SCD 12034 JSF Topside Mods: C5I Systems Industrial Activty 0% Mon 3/28/16 Tue 8/9/16 134 days
106 SCD 12035 JSF Topside Mods: Warfare Systems Industrial Activty 0% Mon 3/28/16 Sat 6/11/16 75 days
107 SCD 12036 JSF Topside Mods: Firefighting Industrial Activty 0% Mon 3/28/16 Thu 9/29/16 185 days
108 SCD 12038 JSF Topside Mods: HVAC Supply Industrial Activty 0% Mon 3/28/16 Sun 1/22/17 300 days
109 SCD 12040 JSF Topside Mods: JP‐5 Fuel Stations Industrial Activty 0% Mon 3/28/16 Wed 4/27/16 30 days
110 SCD 12041 JSF Topside Mods: Short Take Off (STO)
Lights
Industrial Activty 0% Mon 3/28/16 Tue 7/26/16 120 days
111 SCD 12042 JSF Topside Mods: Flight Deck Industrial Activty 0% Mon 3/28/16 Mon 1/9/17 287 days
112 SCD 12043 JSF Topside Mods: Liferaft Stations Industrial Activty 0% Mon 3/28/16 Tue 7/26/16 120 days
113 SCD 12044 JSF Aviation Weapons Support Industrial Activty 0% Mon 3/28/16 Sat 10/15/16 201 days
114 SCD 12046 JSF Shops and Services Industrial Activty 0% Mon 3/28/16 Wed 9/7/16 163 days
115 SCD 12047 JSF Personnel Safety ‐ Safety Industrial Activty 0% Mon 3/28/16 Thu 7/14/16 108 days
116 SCD 12876 Common Munitions BIT / R (CMBRE) Industrial Activty 0% Mon 3/28/16 Tue 11/22/16 239 days
117 SCD 13220 Lithium Ion Battery Shop Industrial Activty 0% Mon 3/28/16 Fri 2/24/17 333 days
118 SCD 13021 CANES Industrial Activty 0% Mon 3/28/16
3/28/16 9/18/16
SCD 1497 AESS (270VDC)
3/28/16 9/11/16
SCD 1563 JSF Weapons Support (F-35)
3/28/16 7/26/16
SCD 1575 JSF Tramline Relocation
3/28/16 9/11/16
SCD 1621 JSF Pyro Prep and AECM Room Relocation
3/28/16 9/11/16
SCD 1743 JSF DMRT/OMS
3/28/16 10/28/16
SCD 11531 JSF AFFF Staging Area
3/28/16 8/9/16
SCD 12034 JSF Topside Mods: C5I Systems
3/28/16 6/11/16
SCD 12035 JSF Topside Mods: Warfare Systems
3/28/16 9/29/16
SCD 12036 JSF Topside Mods: Firefighting
3/28/16 1/22/17
SCD 12038 JSF Topside Mods: HVAC Supply
3/28/16 4/27/16
SCD 12040 JSF Topside Mods: JP-5 Fuel Stations
3/28/16 7/26/16
SCD 12041 JSF Topside Mods: Short Take Off (STO) Lights
3/28/16 1/9/17
SCD 12042 JSF Topside Mods: Flight Deck
3/28/16 7/26/16
SCD 12043 JSF Topside Mods: Liferaft Stations
3/28/16 10/15/16
SCD 12044 JSF Aviation Weapons Support
3/28/16 9/7/16
SCD 12046 JSF Shops and Services
3/28/16 7/14/16
SCD 12047 JSF Personnel Safety - Safety
3/28/16 11/22/16
SCD 12876 Common Munitions BIT / R (CMBRE)
3/28/16 2/24/1
SCD 13220 Lithium Ion Battery Shop
3/28/16
SCD 13021 CANES
Feb Jun Oct Feb Jun Oct Feb Jun Oct Feb
er 4th Quarter 3rd Quarter 2nd Quarter 1st Quarter
2nd Half 1st Half
Robert P. Irelan
Team Lead/LHD Hull Manager
LHD Maintenance and Modernization
Project Management Team (PMT)
PMS-407
Michael A. Esparza , PMP, DMBM
Version: 5/21/15 UNCLASSIFIED - PORTFOLIO EXAMPLE 6
7. ID
Task/Milestone Responsible Activity A - / + % Complete Start Finish Duration
119 CANES Production Industrial Activty 0% Mon 3/28/16 Tue 8/16/16 141 days
120 CANES Cold Checks Industrial Activty 0% Mon 11/14/16 Sat 12/3/16 19 days
121 CANES Software Load and Testing Industrial Activty 0% Sat 12/3/16 Fri 2/24/17 83 days
122 SCD 15037 SSDS MK II LHD HW UPGRADE ACDS BLK 0
to MKII Mod 3C
Industrial Activty 0% Mon 3/28/16
123 SCD 12483 CIC Space Rearrangement Industrial Activty 0% Mon 3/28/16 Sun 7/31/16 125 days
124 CAPSTONE Production Industrial Activty 0% Mon 8/1/16 Fri 9/30/16 60 days
125 CAPSTONE Testing Industrial Activty 0% Sun 11/13/16 Sat 2/11/17 90 days
126 SCD 15173 Reverse Osmosis (RO) Unit Install Industrial Activty 0% Mon 3/28/16 Fri 12/23/16 270 days
127 SCD 16402 Thermal Management Industrial Activty 0% Mon 3/28/16 Tue 7/26/16 120 days
128 SCD XXXXX Vent Plenums (see Note) Industrial Activty 0% Mon 3/28/16
129 I. AUTHORIZED SHIP CHANGES (GREEN ZONE)
PMS‐407 LTR SER 407/038 DTD 17 APR 15
Industrial Activty 0% Mon 3/28/16
130 OA 76626 CIWS Replacement of obsolete L Industrial Activty 0% Mon 3/28/16
131 OA 76982 CIWS Mount Resolver Redesign Industrial Activty 0% Mon 3/28/16
132 OA 78881 CIWS WNI CCA Firmware Update Industrial Activty 0% Mon 3/28/16
133 OA 80141 CIWS 1B B/L 2 Test Control Uni Industrial Activty 0% Mon 3/28/16
134 OA 80535 CIWS WADs ADA Filter Addition Industrial Activty 0% Mon 3/28/16
135 OA 80938 CIWS WADS Compressor Piston Repair Industrial Activty 0% Mon 3/28/16
136 OA 82478 NSSMS MK 37 MOD 3 Auxiliary Cab Industrial Activty 0% Mon 3/28/16
137 OA 83175 CIWS Rig Driver CCA Redesign Industrial Activty 0% Mon 3/28/16
138 SA 78358 K AN/SPN‐41/41A RADOME HARDWARE Industrial Activty 0% Mon 3/28/16
3/28/16 8/16/16
CANES Production
11/14/16 12/3/16
CANES Cold Checks
12/3/16 2/24/1
CANES Software Load and T
3/28/16
SCD 15037 SSDS MK II LHD HW UPGRADE ACDS BLK 0 to MKII Mod 3
3/28/16 7/31/16
SCD 12483 CIC Space Rearrangement
8/1/16 9/30/16
CAPSTONE Production
11/13/16 2/11/1
CAPSTONE Testing
3/28/16 12/23/16
SCD 15173 Reverse Osmosis (RO) Unit Install
3/28/16 7/26/16
SCD 16402 Thermal Management
3/28/16
SCD XXXXX Vent Plenums (see Note)
3/28/16
I. AUTHORIZED SHIP CHANGES (GREEN ZONE) PMS-407 LTR SER 407/038 DTD
3/28/16
OA 76626 CIWS Replacement of obsolete L
3/28/16
OA 76982 CIWS Mount Resolver Redesign
3/28/16
OA 78881 CIWS WNI CCA Firmware Update
3/28/16
OA 80141 CIWS 1B B/L 2 Test Control Uni
3/28/16
OA 80535 CIWS WADs ADA Filter Addition
3/28/16
OA 80938 CIWS WADS Compressor Piston Repair
3/28/16
OA 82478 NSSMS MK 37 MOD 3 Auxiliary Cab
3/28/16
OA 83175 CIWS Rig Driver CCA Redesign
3/28/16
SA 78358 K AN/SPN-41/41A RADOME HARDWARE
Feb Jun Oct Feb Jun Oct Feb Jun Oct Feb
er 4th Quarter 3rd Quarter 2nd Quarter 1st Quarter
2nd Half 1st Half
Robert P. Irelan
Team Lead/LHD Hull Manager
LHD Maintenance and Modernization
Project Management Team (PMT)
PMS-407
Michael A. Esparza , PMP, DMBM
Version: 5/21/15 UNCLASSIFIED - PORTFOLIO EXAMPLE 7
8. ID
Task/Milestone Responsible Activity A - / + % Complete Start Finish Duration
139 SA 81053 K AN/SPN‐41/41A TRANSMITTER UPGR Industrial Activty 0% Mon 3/28/16
140 II. PLANNED BUT NOT AUTHORIZED (PNA) (YELLOW
ZONE) PMS‐407 LTR SER 407/038 DTD 17 APR 15
Industrial Activty 0% Mon 3/28/16 Mon 3/28/16 0 days
141 EC 82208 ADNS K(V)2 SP2 ST1 Industrial Activty 0% Mon 3/28/16
142 EC 82498 PEOC4I SMQ11 SLEP SW 5.0.0 EC1
SPAWAR
Industrial Activty 0% Mon 3/28/16
143 EC 84363 PEOC4I ADSI 15 SPAWAR Industrial Activty 0% Mon 3/28/16
144 EC 85861 PEOC4I NMT SSHD UPG EC3 SPAWAR Industrial Activty 0% Mon 3/28/16
145 FC 78145 AN/SPQ‐9B TRANSMIT RECEIVE LIM
RADAR
Industrial Activty 0% Mon 3/28/16
146 FC 78162 AN/SPQ‐9B DSP RE‐HOST RADAR Industrial Activty 0% Mon 3/28/16
147 FC 78911 NAVY CASH TECH REFRESH Industrial Activty 0% Mon 3/28/16
148 FC 79817 AN/USQ‐T48(V) TSSS Fast Ethernet
Upgrade
Industrial Activty 0% Mon 3/28/16 Mon 3/28/16 0 days
149 FC 80506 NAVY CASH SERVER REFRESH ‐ SUR Industrial Activty 0% Mon 3/28/16
150 FC 81023 R3 TACTICAL AIR NAVIGATION ST2 Industrial Activty 0% Mon 3/28/16
151 FC 81300 UPG TSSS SPS49STIM FOR 49A(V)1
AN/USQ‐T48(V)
Industrial Activty 0% Mon 3/28/16
152 OA 73901 PHALANX ENGAGEMENT SIMULATOR Industrial Activty 0% Mon 3/28/16
153 OA 75359 SWBD UPGD TO SUPP PEOC4I CBSP Industrial Activty 0% Mon 3/28/16
154 OA 78221 CIWS BLK 1B B/L 2 Radar Upgrade Industrial Activty 0% Mon 3/28/16
155 OA 78389 SWBD UPGRD TO SUPP AN/SPN‐41/4 Industrial Activty 0% Mon 3/28/16
156 OA 79686 CIWS Block 1B Next Generation Industrial Activty 0% Mon 3/28/16
157 OA 80070 AN/TPX‐42AV(14) w/FC5 JPALS In Industrial Activty 0% Mon 3/28/16 Mon 3/28/16 0 days
158 OA 80190 CIWS Test Control Unit (TCU) E Industrial Activty 0% Mon 3/28/16
3/28/16
SA 81053 K AN/SPN-41/41A TRANSMITTER UPGR
3/28/16 0%
II. PLANNED BUT NOT AUTHORIZED (PNA) (YELLOW ZONE) PMS-407 LTR SER 407/03
3/28/16 3/28/16
II. PLANNED BUT NOT AUTHORIZED (PNA) (YELLOW ZONE) PMS-407 LTR SER 407/03
3/28/16
EC 82208 ADNS K(V)2 SP2 ST1
3/28/16
EC 82498 PEOC4I SMQ11 SLEP SW 5.0.0 EC1 SPAWAR
3/28/16
EC 84363 PEOC4I ADSI 15 SPAWAR
3/28/16
EC 85861 PEOC4I NMT SSHD UPG EC3 SPAWAR
3/28/16
FC 78145 AN/SPQ-9B TRANSMIT RECEIVE LIM RADAR
3/28/16
FC 78162 AN/SPQ-9B DSP RE-HOST RADAR
3/28/16
FC 78911 NAVY CASH TECH REFRESH
3/28/16 0%
FC 79817 AN/USQ-T48(V) TSSS Fast Ethernet Upgrade
3/28/16
FC 80506 NAVY CASH SERVER REFRESH - SUR
3/28/16
FC 81023 R3 TACTICAL AIR NAVIGATION ST2
3/28/16
FC 81300 UPG TSSS SPS49STIM FOR 49A(V)1 AN/USQ-T48(V)
3/28/16
OA 73901 PHALANX ENGAGEMENT SIMULATOR
3/28/16
OA 75359 SWBD UPGD TO SUPP PEOC4I CBSP
3/28/16
OA 78221 CIWS BLK 1B B/L 2 Radar Upgrade
3/28/16
OA 78389 SWBD UPGRD TO SUPP AN/SPN-41/4
3/28/16
OA 79686 CIWS Block 1B Next Generation
3/28/16 0%
OA 80070 AN/TPX-42AV(14) w/FC5 JPALS In
3/28/16
OA 80190 CIWS Test Control Unit (TCU) E
Feb Jun Oct Feb Jun Oct Feb Jun Oct Feb
er 4th Quarter 3rd Quarter 2nd Quarter 1st Quarter
2nd Half 1st Half
Robert P. Irelan
Team Lead/LHD Hull Manager
LHD Maintenance and Modernization
Project Management Team (PMT)
PMS-407
Michael A. Esparza , PMP, DMBM
Version: 5/21/15 UNCLASSIFIED - PORTFOLIO EXAMPLE 8
9. ID
Task/Milestone Responsible Activity A - / + % Complete Start Finish Duration
159 OA 80614 AN/SPQ‐9B TOUCH PANEL LAND MAP Industrial Activty 0% Mon 3/28/16
160 SA 80897 K SWBD UPGD TO SUPT AN/WSC‐9(V) Industrial Activty 0% Mon 3/28/16
161 OA 81963 AN/SLQ‐32 ESE FIRMWARE Industrial Activty 0% Mon 3/28/16
162 OA 82493 RAM MK31 Software Upgrade to B Industrial Activty 0% Mon 3/28/16
163 OA 85896 AN/TPX‐42A(V) EMBEDDED TRAINER Industrial Activty 0% Mon 3/28/16
164 SSA 339 K 00 MORIAH Wind System Instllation Industrial Activty 0% Mon 3/28/16
165 SA 70430 K Mark XIIA Mode 5 IFF System Industrial Activty 0% Mon 3/28/16
166 SA 70678 AN/SPS‐48G(V) ROAR (L‐Class) Industrial Activty 0% Mon 3/28/16
167 SA 71386 K PEOC4I Advanced Digital Antenn Industrial Activty 0% Mon 3/28/16 Mon 3/28/16 0 days
168 SA 71492 K HESS (400HZ) LINE VOLTAGE REGU Industrial Activty 0% Mon 3/28/16
169 SA 71497 K AESS (270VDC) FOR THE F‐35 JSF Industrial Activty 0% Mon 3/28/16
170 SA 71563 K JOINT STRIKE FIGHTER(F‐35) WEA Industrial Activty 0% Mon 3/28/16
171 SA 71575 K JSF TRAMLINE RELOCATION Industrial Activty 0% Mon 3/28/16
172 SA 71621 K JSF PYRO PREP AND AECM ROOM RE Industrial Activty 0% Mon 3/28/16
173 SA 71743 K JSF DMRT/OMS INSTALLATION Industrial Activty 0% Mon 3/28/16
174 SA 71827 K AN/SPQ‐9B INITIAL INSTALLATION Industrial Activty 0% Mon 3/28/16
175 SA 71947 K INSTALL TSSS SPQ‐9B STIMULATOR Industrial Activty 0% Mon 3/28/16
176 SA 75091 K LHA/LHD CLASS BOAT DAVIT REPLA Industrial Activty 0% Mon 3/28/16
177 SA 75736 K RAM GMLS MOD3 ETHERNET UPGRADE Industrial Activty 0% Mon 3/28/16
178 SA 78304 K REMOVE TSSS SPS‐48E STIMULATOR Industrial Activty 0% Mon 3/28/16
3/28/16
OA 80614 AN/SPQ-9B TOUCH PANEL LAND MAP
3/28/16
SA 80897 K SWBD UPGD TO SUPT AN/WSC-9(V)
3/28/16
OA 81963 AN/SLQ-32 ESE FIRMWARE
3/28/16
OA 82493 RAM MK31 Software Upgrade to B
3/28/16
OA 85896 AN/TPX-42A(V) EMBEDDED TRAINER
3/28/16
SSA 339 K 00 MORIAH Wind System Instllation
3/28/16
SA 70430 K Mark XIIA Mode 5 IFF System
3/28/16
SA 70678 AN/SPS-48G(V) ROAR (L-Class)
3/28/16 0%
SA 71386 K PEOC4I Advanced Digital Antenn
3/28/16
SA 71492 K HESS (400HZ) LINE VOLTAGE REGU
3/28/16
SA 71497 K AESS (270VDC) FOR THE F-35 JSF
3/28/16
SA 71563 K JOINT STRIKE FIGHTER(F-35) WEA
3/28/16
SA 71575 K JSF TRAMLINE RELOCATION
3/28/16
SA 71621 K JSF PYRO PREP AND AECM ROOM RE
3/28/16
SA 71743 K JSF DMRT/OMS INSTALLATION
3/28/16
SA 71827 K AN/SPQ-9B INITIAL INSTALLATION
3/28/16
SA 71947 K INSTALL TSSS SPQ-9B STIMULATOR
3/28/16
SA 75091 K LHA/LHD CLASS BOAT DAVIT REPLA
3/28/16
SA 75736 K RAM GMLS MOD3 ETHERNET UPGRADE
3/28/16
SA 78304 K REMOVE TSSS SPS-48E STIMULATOR
Feb Jun Oct Feb Jun Oct Feb Jun Oct Feb
er 4th Quarter 3rd Quarter 2nd Quarter 1st Quarter
2nd Half 1st Half
Robert P. Irelan
Team Lead/LHD Hull Manager
LHD Maintenance and Modernization
Project Management Team (PMT)
PMS-407
Michael A. Esparza , PMP, DMBM
Version: 5/21/15 UNCLASSIFIED - PORTFOLIO EXAMPLE 9
10. ID
Task/Milestone Responsible Activity A - / + % Complete Start Finish Duration
179 SA 78381 K AN/SPN‐41/41A CODER MONITOR Industrial Activty 0% Mon 3/28/16
180 SA 79371 K BFTT LHD HARDWARE BUILD 4.1 UP Industrial Activty 0% Mon 3/28/16
181 SA 80264 K PEOC4I SSEE INC E AN/SSQ‐137(V Industrial Activty 0% Mon 3/28/16
182 SA 80533 K NAVAIR FLT SYS ARRAY (NFSA) V3 Industrial Activty 0% Mon 3/28/16
183 SA 80897 PEOC4I NMT AN/WSC‐9(V)XX Q/KA/ Industrial Activty 0% Mon 3/28/16
184 SA 80934 K PEOC4I KMI AN/GYK‐72(V) Industrial Activty 0% Mon 3/28/16
185 SA 81301 K BEWT II HARDWARE INSTALL Industrial Activty 0% Mon 3/28/16
186 SA 81531 K JSF AFFF WEAPONS STAGING AREA Industrial Activty 0% Mon 3/28/16
187 SA 81750 K SOLID STATE LIGHTING Industrial Activty 0% Mon 3/28/16
188 SA 81866 K WET FILM PROCESSOR REMOVAL Industrial Activty 0% Mon 3/28/16
189 SA 82034 K JSF TOPSIDE MODS: C5I SYSTEMS Industrial Activty 0% Mon 3/28/16
190 SA 82035 K JSF TOPSIDE MODS: WARFARE SYST Industrial Activty 0% Mon 3/28/16
191 SA 82036 K JSF TOPSIDE MODS: FIRE FIGHTIN Industrial Activty 0% Mon 3/28/16
192 SA 82038 K JSF TOPSIDE MODS: HVAC SUPPLY Industrial Activty 0% Mon 3/28/16
193 SA 82040 K JSF TOPSIDE MODS: JP‐5 FUEL ST Industrial Activty 0% Mon 3/28/16
194 SA 82041 K JSF TOPSIDE MODS: SHORT TAKE‐O Industrial Activty 0% Mon 3/28/16
195 SA 82042 K JSF TOPSIDE MODS: FLIGHT DECK Industrial Activty 0% Mon 3/28/16
196 SA 82043 K JSF TOPSIDE MODS: LIFERAFTS ST Industrial Activty 0% Mon 3/28/16
197 SA 82044 K JSF AVIATION WEAPONS SUPPORT Industrial Activty 0% Mon 3/28/16
198 SA 82046 K JSF SHOPS AND SERVICES Industrial Activty 0% Mon 3/28/16
3/28/16
SA 78381 K AN/SPN-41/41A CODER MONITOR
3/28/16
SA 79371 K BFTT LHD HARDWARE BUILD 4.1 UP
3/28/16
SA 80264 K PEOC4I SSEE INC E AN/SSQ-137(V
3/28/16
SA 80533 K NAVAIR FLT SYS ARRAY (NFSA) V3
3/28/16
SA 80897 PEOC4I NMT AN/WSC-9(V)XX Q/KA/
3/28/16
SA 80934 K PEOC4I KMI AN/GYK-72(V)
3/28/16
SA 81301 K BEWT II HARDWARE INSTALL
3/28/16
SA 81531 K JSF AFFF WEAPONS STAGING AREA
3/28/16
SA 81750 K SOLID STATE LIGHTING
3/28/16
SA 81866 K WET FILM PROCESSOR REMOVAL
3/28/16
SA 82034 K JSF TOPSIDE MODS: C5I SYSTEMS
3/28/16
SA 82035 K JSF TOPSIDE MODS: WARFARE SYST
3/28/16
SA 82036 K JSF TOPSIDE MODS: FIRE FIGHTIN
3/28/16
SA 82038 K JSF TOPSIDE MODS: HVAC SUPPLY
3/28/16
SA 82040 K JSF TOPSIDE MODS: JP-5 FUEL ST
3/28/16
SA 82041 K JSF TOPSIDE MODS: SHORT TAKE-O
3/28/16
SA 82042 K JSF TOPSIDE MODS: FLIGHT DECK
3/28/16
SA 82043 K JSF TOPSIDE MODS: LIFERAFTS ST
3/28/16
SA 82044 K JSF AVIATION WEAPONS SUPPORT
3/28/16
SA 82046 K JSF SHOPS AND SERVICES
Feb Jun Oct Feb Jun Oct Feb Jun Oct Feb
er 4th Quarter 3rd Quarter 2nd Quarter 1st Quarter
2nd Half 1st Half
Robert P. Irelan
Team Lead/LHD Hull Manager
LHD Maintenance and Modernization
Project Management Team (PMT)
PMS-407
Michael A. Esparza , PMP, DMBM
Version: 5/21/15 UNCLASSIFIED - PORTFOLIO EXAMPLE 10
11. ID
Task/Milestone Responsible Activity A - / + % Complete Start Finish Duration
199 SA 82047 K JSF PERSONNEL SAFETY ‐ SAFETY Industrial Activty 0% Mon 3/28/16
200 SA 82156 K PEOC4I DCGS‐N INC 1 BLK 2 HW/S Industrial Activty 0% Mon 3/28/16 Mon 3/28/16 0 days
201 SA 82483 K LHD 1 ‐ 6 CAPSTONE SPACE ARRAN Industrial Activty 0% Mon 3/28/16
202 SA 82853 K PEOC4I COM SER CRYP REPL PH‐II Industrial Activty 0% Mon 3/28/16
203 SA 82876 K (CMBRE) COMMON MUNITIONS BIT/R Industrial Activty 0% Mon 3/28/16
204 SA 83201 K PEOC4I CANES ANUSQ‐208(V)6 LHD Industrial Activty 0% Mon 3/28/16
205 SA 83220 K LITHIUM‐ION BATTERY SHOP TO SU Industrial Activty 0% Mon 3/28/16
206 SA 83712 K PEOC4I COMSEC KW46 REPL Industrial Activty 0% Mon 3/28/16
207 SA 85027 K CEC AN/USG‐2B INSTALLATION ‐ LHDs Industrial Activty 0% Mon 3/28/16
208 SA 85037 K SSDS MK 2 LHD HW UPGRADE ACDS Industrial Activty 0% Mon 3/28/16
209 SA 85574 K PEOC4I AN/UYQ‐86(V)2 Upgrade Industrial Activty 0% Mon 3/28/16
210 SA 85742 K NSSMS MK57 MOD14 (OCP2) UPGRADE Industrial Activty 0% Mon 3/28/16
211 SWD 75397 R1 MWS SW *1.3 FOR L CLASS SHIPS
MORIAH WIND SYSTEM
Industrial Activty 0% Mon 3/28/16 Mon 3/28/16 0 days
212 SWD 78695 TSSS 2.4 SWD Industrial Activty 0% Mon 3/28/16
213 SWD 79228 BFTT 3.5.1 SWD Industrial Activty 0% Mon 3/28/16
214 SWD 79416 NAVY CASH SWD 1.4.7 ‐ SURFACE Industrial Activty 0% Mon 3/28/16
215 SWD 79816 MK XIIA MODE 5 UPX41(C) SW UPG IFF Industrial Activty 0% Mon 3/28/16
216 SWD 79820 MK XIIA MODE 5 APX‐123 SW UPG IFF Industrial Activty 0% Mon 3/28/16
217 SWD 80962 R1 AN/SPQ‐9B SWD 05.02.00 RADAR Industrial Activty 0% Mon 3/28/16
218 SWD 81302 BEWT II SOFTWARE CAPABILITY SW Industrial Activty 0% Mon 3/28/16
3/28/16
SA 82047 K JSF PERSONNEL SAFETY - SAFETY
3/28/16 0%
SA 82156 K PEOC4I DCGS-N INC 1 BLK 2 HW/S
3/28/16
SA 82483 K LHD 1 - 6 CAPSTONE SPACE ARRAN
3/28/16
SA 82853 K PEOC4I COM SER CRYP REPL PH-II
3/28/16
SA 82876 K (CMBRE) COMMON MUNITIONS BIT/R
3/28/16
SA 83201 K PEOC4I CANES ANUSQ-208(V)6 LHD
3/28/16
SA 83220 K LITHIUM-ION BATTERY SHOP TO SU
3/28/16
SA 83712 K PEOC4I COMSEC KW46 REPL
3/28/16
SA 85027 K CEC AN/USG-2B INSTALLATION - LHDs
3/28/16
SA 85037 K SSDS MK 2 LHD HW UPGRADE ACDS
3/28/16
SA 85574 K PEOC4I AN/UYQ-86(V)2 Upgrade
3/28/16
SA 85742 K NSSMS MK57 MOD14 (OCP2) UPGRADE
3/28/16 0%
SWD 75397 R1 MWS SW *1.3 FOR L CLASS SHIPS MORIAH WIND SYSTE
3/28/16
SWD 78695 TSSS 2.4 SWD
3/28/16
SWD 79228 BFTT 3.5.1 SWD
3/28/16
SWD 79416 NAVY CASH SWD 1.4.7 - SURFACE
3/28/16
SWD 79816 MK XIIA MODE 5 UPX41(C) SW UPG IFF
3/28/16
SWD 79820 MK XIIA MODE 5 APX-123 SW UPG IFF
3/28/16
SWD 80962 R1 AN/SPQ-9B SWD 05.02.00 RADAR
3/28/16
SWD 81302 BEWT II SOFTWARE CAPABILITY SW
Feb Jun Oct Feb Jun Oct Feb Jun Oct Feb
er 4th Quarter 3rd Quarter 2nd Quarter 1st Quarter
2nd Half 1st Half
Robert P. Irelan
Team Lead/LHD Hull Manager
LHD Maintenance and Modernization
Project Management Team (PMT)
PMS-407
Michael A. Esparza , PMP, DMBM
Version: 5/21/15 UNCLASSIFIED - PORTFOLIO EXAMPLE 11