Hwange Rehabilitation Monitoring Project
Hwange Coal Fired Power Station, Zimbabwe
Project Implementation Guideline
Hwange Rehabilitation Monitoring Project
Table of Contents
Rehabilitation Project Team – Organisation and TasksRehabilitation Project Team – Organisation and Tasks
Approach to the Hwange Rehabilitation Monitoring ProjectApproach to the Hwange Rehabilitation Monitoring Project
The Hwange Power Station Rehabilitation ProjectThe Hwange Power Station Rehabilitation Project
Purpose of the Project Implementation GuidelinePurpose of the Project Implementation Guideline
AppendicesAppendices
Purpose of the Project Implementation Guideline
This Project Implementation Guideline is to be considered as a high-level
project guideline for the parties involved (ZPC, NamPower and Lahmeyer
International).
The guideline reflects the common understanding of the project and its
implementation and describes the extent of envisaged measures and the
management of this measures.
Based on this Project Implementation Guideline a detailed Project Manual will
be prepared for the most efficient cooperation between the parties. Inter alia
the following issues will be addressed with such project manual:
- Project administration;
- Responsibilities;
- Communication;
- Project documentation and filing.
A table of contents for a typical project manual for such purpose is attached
as Appendix 1. The Project Manual will be prepared by the Rehabilitation
Monitoring Team.
Hwange Power Station, Zimbabwe - Rehabilitation Project
The current severe situation at the Hwange Power Station can be summarized as
follows:
I. Luck of local and foreign funds for maintenance and repairs;
II. Exceeded normal major overhaul running hours;
III. Overdue for mandatory maintenance work;
IV. Thus increasing the forced outage rates and accelerates equipment
deterioration;
V. Decreased unit efficiency and low plant load factor;
VI. Latent risk of enforced outages by inspection authorities;
VII. Increased risk of critical and severe failures.
Only for Stage II (unit 5 & 6) funds were available and overhauls have been carried
out. However, luck of financing substantially reduced the envisaged scope of work.
Hwange Power Station, Zimbabwe - Rehabilitation Project
Due to the situation described aforementioned the plant operating conditions are as
follows as per 31 January 2007:
Unit
no.:
Last major overhaul
Running hours
to next planned
major overhaul
Running hours
since last major
overhaul
Excess running
hours
1 23/03/1996 - 31/05/1996 50 000 74 266 24 266
2 06/10/1997 - 19/12/1997 50 000 66 608 16 608
3 13/11/1994 - 01/02/1995 50 000 71 009 21 009
4 09/12/1995 - 23/02/1996 50 000 70 859 20 859
5 06/09/2002 - 30/05/2003 50 000 17 476
6 25/11/2003 - 08/08/2004 50 000 9 272
Hwange Power Station, Zimbabwe - Rehabilitation Project
With the foreign currency funds made available by NamPower via a specific
Stanbic bank account it is envisaged to overcome the severe situation in the
operation and maintenance of the power plant.
With the decided Hwange Power Station Rehabilitation Project the following
targets shall be attained:
I. Recapturing of unit output of 4 x 120 MW;
II. Increase of operational reliability;
III. Reduction of forced outages;
IV. Improvement of unit efficiency;
V. Grid stability.
For the purpose of monitoring the project and assist and support ZPC with the
project implementation NamPower engaged Lahmeyer International and in
addition will provide own resources during the execution.
Hwange Power Station, Zimbabwe - Rehabilitation Project
For the successful project implementation the following key challenges have
been identified to overcome in course of the project:
I. Tight project implementation programme;
II. Assignment of experienced experts to the ZPC project team;
III. Reliable tendering process;
IV. Delivery time of manufacturer parts;
V. Availability of local funds.
The envisaged scope of rehabilitation works for Stage I, unit 1 – 4 is
summarized as follows:
I. Boiler and auxiliaries:
- Super heater, evaporator and economizer tubes;
- PF-burner repair;
- Start-up burner repair;
- Tubular air heater tube replacement;
- Coal mill overhaul.
II. Steam turbine/generator and auxiliaries:
- Extensive turbine overhaul;
- Generator excitation system overhaul.
III. Ancillary systems:
- Station coal conveyer system overhaul;
- Ash disposal system;
- Water treatment plant;
- Transformer repair;
- Switchgear (LV,HV) replacement;
- Control system, unit instrumentation;
- Compressor station.
Hwange Power Station, Zimbabwe - Rehabilitation Project
Appendix 2 to this Project Implementation Guideline outlines a more detailed
summary of the envisaged scope of rehabilitation works prepared by ZPC.
The preliminary planning for the execution of works is listed below.
However, the detailed planning for the execution of the rehabilitation works
is subject to the next steps, the priorities of measures and the feedback from
the contractors and/or equipment manufactures:
Hwange Power Station, Zimbabwe - Rehabilitation Project
Unit Preliminary planning for rehabilitation works
Unit no.: 3 01/11/2007 - 31/12/2007
Unit no.: 1 01/01/2008 - 31/03/2008
Unit no.: 4 01/05/2008 - 30/06/2008
Unit no.: 2 01/07/2008 - 31/08/2008
Auxiliary systems 01/04/2007 - 31/10/2007
Based on the envisaged scope of rehabilitation works ZPC worked out a
preliminary break down of the rehabilitation works costs compiled in the
following table:
Hwange Power Station, Zimbabwe - Rehabilitation Project
Item Local currency (Mio. Z$)
(as at Mid Feb 2007)
Foreign expenditures
(Mio. US$)
Aux Plant 770.0 6.5
Unit 3 Major Overhaul 1 410.0 7.1
Unit 1 Major Overhaul 1 290.0 7.3
Unit 4 Major Overhaul 1 225.0 7.1
Unit 2 Major Overhaul 1 125.0 6.8
Contingencies 1 164.0 5.2
Total 5 823.0 40.0
NamPower / LI
Monitoring Team
ZPC
Managing Director
Hwange Power Station
General Manager
Hwange Power Station
Project Manager
Accounting
Quality &
Engineering
Procurement
& Stores
Works
Supervision
Contracts
Management
For the success of this project it is mandatory that ZPC’s Rehabilitation Project
Team is equipped with capable manpower during the complete project execution
period. Particular the positions for “Quality & Engineering” and “Works
Supervision” shall be continuously assigned to experienced engineers, capable of
providing the mandatory services for planning, scheduling, tendering and works
supervision.
Rehabilitation Project Team - Organisation and Tasks
NamPower
Lahmeyer
International
ZPC
Rehabilitation Monitoring Team (RMT) Rehabilitation Project Team
Rehabilitation Project Team - Organisation and Tasks
NamPower Tasks:
• Requirements from
PPA
• Funding of bank account
• Loan management
• Release of payment
ZPC Tasks:
• Tender documents
• Contract award
• Scheduling
• Utilities
• Works supervision
• Acceptance tests
• Works certificates
RMT Tasks:
• Support and assistance
in tendering and
evaluation
• Project monitoring
• Payment release
certificates
Project Preparation and Implementation Phase – Coordination between ZPC / RMT
Award of contract (ZPC)
Document distribution (ZPC)
Evaluation of bidders’ proposals
(ZPC)
RMT to support and assist in the
evaluation process
RMT to recommend contract
award
RMT to monitor the progress
Hwange Rehabilitation Monitoring Project – Task Structure
Clarification for scope of work
(ZPC)
Compilation of tender docs.
(ZPC)
RMT to support and assist in the
tender process
Issuance of request for proposal
(ZPC)
RMT to monitor the progress
Evaluation Process
Implementation
Process
Tendering Process
Project scheduling (ZPC)
Project supervision (ZPC)
Project progress meetings with
ZPC project team
Acceptance tests and certificates
(ZPC)
Project support for utilities and
resources (ZPC)
RMT to monitor the progress
Payment Release Certificate
Hwange Rehabilitation Monitoring Project – Approach
Stage 1- Project Preparation:
I. ZPC defined / will define the scope of rehabilitation work for
Unit 1 - 4 and ancillary systems:
- RMT will compare the suggested scope of work with the recommended measures
from the assessment report and discuss with the ZPC-Rehabilitation Project Team
the prioritised measures for:
Boiler, turbine, generator, switch yard, ancillary system rehabilitation.
II. Preparation of project time schedule for all activities:
- Priorities;
- Delivery times;
- Operational constrains.
III. Compilation of tender documents by ZPC, supported by RMT:
- Technical specification (system description, data sheets, extract from drawings,
documents, manuals etc.);
- Financial specification (to be discussed and agreed upon between the parties);
- Contractual terms and conditions (to be discussed and agreed upon between the
parties);
- Instructions to bidders (to be discussed and agreed upon between the parties).
Hwange Rehabilitation Monitoring Project – Approach
Stage 1- Project Preparation:
IV. Evaluation of bidders’ proposals by ZPC, supported by RMT:
- Completeness and responsiveness of submitted proposals;
- Technical evaluation to verify compliance with technical specification and QA
requirements, review of provided technical information;
- Commercial evaluation to verify the compliance with the dedicated budget and
financial requirements;
- Contractual evaluation to verify the compliance with the terms and conditions and
time schedule;
- Considerable deviations;
- Recommendation from RMT for the contract award.
V. Award of contract to successful bidders by ZPC:
- ZPC and RMT to agree on the conditions for contract award;
- RMT will confirm the contract award to NamPower and bank;
- ZPC will award the contract to the successful bidders.
VI. Project progress monitoring by RMT:
- Regular reporting to NamPower to compile status and outlook on tenders,
contracts, supplies, services and works, budget forecast and cash flow, noticeable
events.
Hwange Rehabilitation Monitoring Project – Approach
Stage 1- Project Preparation:
The tendering process shall be in compliance with ZPC’s tendering and
purchasing procedure which is attached as Appendix 3. ZPC’s tendering and
purchasing procedure compiles the following:
- Raising and authorisation of purchasing requisitions;
- Foreign purchases;
- Floating of direct enquiries and order placement;
- Informal tender floating and order placement.
For an effective tendering process it is mandatory that a standard procedure
will be implemented to compile the technical specifications, financial and
contractual conditions.
Hwange Rehabilitation Monitoring Project – Approach
Stage 2 - Project Implementation:
I. Project supervision by ZPC:
- Regular meetings with the ZPC rehabilitation project team (status, scheduling, site
activities, inspections, tests and necessary actions);
- Rehabilitation works supervised by ZPC;
- Acceptance tests verified by ZPC and witnessed by RMT (major contracts);
- ZPC will issue the acceptance certificates (PAC/FAC);
- Mandatory update of As-build drawings, documents, manuals by ZPC.
II. Project progress monitoring by RMT:
- Verification and approval of contractors’ request for payment (Payment Release
Certificate);
- Regular reports to compile status and outlook on supplies, works and services,
budget forecast and cash flow, noticeable events;
- Clarification on discrepancies between the parties;
- Recommendation on measures to be taken to ZPC and NamPower;
- RMT will monitor rehabilitation works and completion (commissioning, acceptance
tests and recommendation for completion).
Hwange Rehabilitation Monitoring Project – Approach
PAYMENT RELEASE CERTIFICATE
Stanbic Bank,
Botswana
NamPower PM
approves
Instruction for Payment
Payment release from
Stanbic Bank to Contractors
Contractors’
payment request
RMT verifies
and approves
Feedback on transactions to
ZPC, NamPower and RMT
ZPC approves
and signs
NamPower
Treasury releases
Process for the release of payment
PAYMENT RELEASE CERTIFICATE
ZPC order no.: Date of issue:
Beneficiary:
Reference no.:
Scope of work:
Approved invoice no.: Attachments:
Requested payment: - Payment instructions
Total amount to be released: (- Letter of award)
(- Contract)
Stanbic Bank, Botswana
Bank account no.:
Approved by:
NamPower ZPC Lahmeyer International
Name: Name: Name:
Signature: Signature: Signature:
Appendix 1 – Table of contents for a typical project manual;
Appendix 2 - Outline of the envisaged scope of rehabilitation works prepared by ZPC;
Appendix 3 – ZPC’s tendering and purchasing procedure.
Project Implementation Guideline - Appendices

More Related Content

What's hot

Resume David Young
Resume David YoungResume David Young
Resume David Young
David Young
 
CV PTM ALNG Site Coordinator Giovanni KOOLMAN REV 1
CV PTM ALNG Site Coordinator Giovanni KOOLMAN REV 1CV PTM ALNG Site Coordinator Giovanni KOOLMAN REV 1
CV PTM ALNG Site Coordinator Giovanni KOOLMAN REV 1
Giovanni Silvio Koolman
 
03-2004PDS_Technology_Isom
03-2004PDS_Technology_Isom03-2004PDS_Technology_Isom
03-2004PDS_Technology_Isom
John Isom
 
Resume for Kenneth Peartree (Full)
Resume for Kenneth Peartree (Full)Resume for Kenneth Peartree (Full)
Resume for Kenneth Peartree (Full)
Ken Peartree
 
Peter White CV - Latest
Peter White CV - LatestPeter White CV - Latest
Peter White CV - Latest
Peter White
 
Leon Chacon Resume_Sept2016R
Leon Chacon Resume_Sept2016RLeon Chacon Resume_Sept2016R
Leon Chacon Resume_Sept2016R
Leon Chacon
 
1-2 Broadgate Final Project Report
1-2 Broadgate Final Project Report1-2 Broadgate Final Project Report
1-2 Broadgate Final Project Report
Paul Warrington
 

What's hot (20)

Cv s.sankarasubramanian - senior planning engineer
Cv   s.sankarasubramanian - senior planning engineerCv   s.sankarasubramanian - senior planning engineer
Cv s.sankarasubramanian - senior planning engineer
 
Monthly Progress Report - September 2014
Monthly Progress Report - September 2014Monthly Progress Report - September 2014
Monthly Progress Report - September 2014
 
Resume David Young
Resume David YoungResume David Young
Resume David Young
 
2015 03 31 cv giovanni koolman.docx lattes update jan 2016
2015 03 31 cv giovanni koolman.docx lattes update jan 20162015 03 31 cv giovanni koolman.docx lattes update jan 2016
2015 03 31 cv giovanni koolman.docx lattes update jan 2016
 
Hossam CV-FEB2016
Hossam CV-FEB2016Hossam CV-FEB2016
Hossam CV-FEB2016
 
Case studies: Predictive maintenance in the petrochemical industry
Case studies: Predictive maintenance in the petrochemical industryCase studies: Predictive maintenance in the petrochemical industry
Case studies: Predictive maintenance in the petrochemical industry
 
CV PTM ALNG Site Coordinator Giovanni KOOLMAN REV 1
CV PTM ALNG Site Coordinator Giovanni KOOLMAN REV 1CV PTM ALNG Site Coordinator Giovanni KOOLMAN REV 1
CV PTM ALNG Site Coordinator Giovanni KOOLMAN REV 1
 
AWI20202 commercial
AWI20202 commercialAWI20202 commercial
AWI20202 commercial
 
MNC-14
MNC-14MNC-14
MNC-14
 
03-2004PDS_Technology_Isom
03-2004PDS_Technology_Isom03-2004PDS_Technology_Isom
03-2004PDS_Technology_Isom
 
Allwyn Leo CV
Allwyn Leo CVAllwyn Leo CV
Allwyn Leo CV
 
Allwyn-PE-CV
Allwyn-PE-CVAllwyn-PE-CV
Allwyn-PE-CV
 
Resume for Kenneth Peartree (Full)
Resume for Kenneth Peartree (Full)Resume for Kenneth Peartree (Full)
Resume for Kenneth Peartree (Full)
 
VanAssche, James, GHD Services, Rice MACT and Boiler MACT Common Compliance C...
VanAssche, James, GHD Services, Rice MACT and Boiler MACT Common Compliance C...VanAssche, James, GHD Services, Rice MACT and Boiler MACT Common Compliance C...
VanAssche, James, GHD Services, Rice MACT and Boiler MACT Common Compliance C...
 
Peter White CV - Latest
Peter White CV - LatestPeter White CV - Latest
Peter White CV - Latest
 
USMC Shops PM Project-Dec 3, 2008
USMC Shops PM Project-Dec 3, 2008USMC Shops PM Project-Dec 3, 2008
USMC Shops PM Project-Dec 3, 2008
 
Venkatesh narasimhan
Venkatesh narasimhan Venkatesh narasimhan
Venkatesh narasimhan
 
Teekay Offshore Partners Q1-2015 Earnings Presentation
Teekay Offshore Partners Q1-2015 Earnings PresentationTeekay Offshore Partners Q1-2015 Earnings Presentation
Teekay Offshore Partners Q1-2015 Earnings Presentation
 
Leon Chacon Resume_Sept2016R
Leon Chacon Resume_Sept2016RLeon Chacon Resume_Sept2016R
Leon Chacon Resume_Sept2016R
 
1-2 Broadgate Final Project Report
1-2 Broadgate Final Project Report1-2 Broadgate Final Project Report
1-2 Broadgate Final Project Report
 

Similar to Hwange Project Implementation Guidelines (Nampower Presentation)

PROJECT MGT. PRESENTATION
PROJECT MGT. PRESENTATIONPROJECT MGT. PRESENTATION
PROJECT MGT. PRESENTATION
maheshvkat1972
 
Attachement 3 61T01411 - Construction Execution Plan
Attachement 3 61T01411 - Construction Execution PlanAttachement 3 61T01411 - Construction Execution Plan
Attachement 3 61T01411 - Construction Execution Plan
James Zhang (Chi, Zhang)
 
CV - S.Sankarasubramanian - Senior Planning Engineer
CV - S.Sankarasubramanian - Senior Planning EngineerCV - S.Sankarasubramanian - Senior Planning Engineer
CV - S.Sankarasubramanian - Senior Planning Engineer
Sankar Sundaram PMP
 
Lead Process Engineer
Lead Process EngineerLead Process Engineer
Lead Process Engineer
Juber Loharia
 
Gensolownersengineerservices 140323094758-phpapp02
Gensolownersengineerservices 140323094758-phpapp02Gensolownersengineerservices 140323094758-phpapp02
Gensolownersengineerservices 140323094758-phpapp02
jitendra kumar biswas
 
LarrySmock Resume 3_24_2015
LarrySmock Resume 3_24_2015LarrySmock Resume 3_24_2015
LarrySmock Resume 3_24_2015
Larry Smock
 

Similar to Hwange Project Implementation Guidelines (Nampower Presentation) (20)

Neelum Jhelum Hydropower Project (NJHP)
Neelum Jhelum Hydropower Project (NJHP)Neelum Jhelum Hydropower Project (NJHP)
Neelum Jhelum Hydropower Project (NJHP)
 
PROJECT MGT. PRESENTATION
PROJECT MGT. PRESENTATIONPROJECT MGT. PRESENTATION
PROJECT MGT. PRESENTATION
 
Rihan Height Project Execution Plan-Rev00
Rihan Height Project Execution Plan-Rev00Rihan Height Project Execution Plan-Rev00
Rihan Height Project Execution Plan-Rev00
 
Attachement 3 61T01411 - Construction Execution Plan
Attachement 3 61T01411 - Construction Execution PlanAttachement 3 61T01411 - Construction Execution Plan
Attachement 3 61T01411 - Construction Execution Plan
 
Owner's engineer services - statement of capabilities
Owner's engineer services - statement of capabilitiesOwner's engineer services - statement of capabilities
Owner's engineer services - statement of capabilities
 
CV - S.Sankarasubramanian - Senior Planning Engineer
CV - S.Sankarasubramanian - Senior Planning EngineerCV - S.Sankarasubramanian - Senior Planning Engineer
CV - S.Sankarasubramanian - Senior Planning Engineer
 
MOHANNAD CV
MOHANNAD  CVMOHANNAD  CV
MOHANNAD CV
 
Lead Process Engineer
Lead Process EngineerLead Process Engineer
Lead Process Engineer
 
CV
CVCV
CV
 
Gensolownersengineerservices 140323094758-phpapp02
Gensolownersengineerservices 140323094758-phpapp02Gensolownersengineerservices 140323094758-phpapp02
Gensolownersengineerservices 140323094758-phpapp02
 
LarrySmock Resume 3_24_2015
LarrySmock Resume 3_24_2015LarrySmock Resume 3_24_2015
LarrySmock Resume 3_24_2015
 
Watlow Malaysia - Monthly 4 BR September 2023.pptx
Watlow Malaysia - Monthly 4 BR September 2023.pptxWatlow Malaysia - Monthly 4 BR September 2023.pptx
Watlow Malaysia - Monthly 4 BR September 2023.pptx
 
Boo wind power in egypt
Boo wind power in egyptBoo wind power in egypt
Boo wind power in egypt
 
SHP development in India - A roadmap
SHP development in India - A roadmapSHP development in India - A roadmap
SHP development in India - A roadmap
 
German perez lifes50+ design summary - deep wind 2018
German perez   lifes50+ design summary - deep wind 2018German perez   lifes50+ design summary - deep wind 2018
German perez lifes50+ design summary - deep wind 2018
 
MO7SEN FAROUK.
MO7SEN FAROUK.MO7SEN FAROUK.
MO7SEN FAROUK.
 
Pre bid meeting presentation
Pre bid meeting presentationPre bid meeting presentation
Pre bid meeting presentation
 
Episode 30 : Project Execution ( Part 1 )
Episode 30 :  Project Execution ( Part 1 ) Episode 30 :  Project Execution ( Part 1 )
Episode 30 : Project Execution ( Part 1 )
 
Vinoth
VinothVinoth
Vinoth
 
DAMMAM SECOND INDUSTRIAL CITY - IPS REHABILITATION WORKS
DAMMAM SECOND INDUSTRIAL CITY - IPS REHABILITATION WORKSDAMMAM SECOND INDUSTRIAL CITY - IPS REHABILITATION WORKS
DAMMAM SECOND INDUSTRIAL CITY - IPS REHABILITATION WORKS
 

Hwange Project Implementation Guidelines (Nampower Presentation)

  • 1. Hwange Rehabilitation Monitoring Project Hwange Coal Fired Power Station, Zimbabwe Project Implementation Guideline
  • 2. Hwange Rehabilitation Monitoring Project Table of Contents Rehabilitation Project Team – Organisation and TasksRehabilitation Project Team – Organisation and Tasks Approach to the Hwange Rehabilitation Monitoring ProjectApproach to the Hwange Rehabilitation Monitoring Project The Hwange Power Station Rehabilitation ProjectThe Hwange Power Station Rehabilitation Project Purpose of the Project Implementation GuidelinePurpose of the Project Implementation Guideline AppendicesAppendices
  • 3. Purpose of the Project Implementation Guideline This Project Implementation Guideline is to be considered as a high-level project guideline for the parties involved (ZPC, NamPower and Lahmeyer International). The guideline reflects the common understanding of the project and its implementation and describes the extent of envisaged measures and the management of this measures. Based on this Project Implementation Guideline a detailed Project Manual will be prepared for the most efficient cooperation between the parties. Inter alia the following issues will be addressed with such project manual: - Project administration; - Responsibilities; - Communication; - Project documentation and filing. A table of contents for a typical project manual for such purpose is attached as Appendix 1. The Project Manual will be prepared by the Rehabilitation Monitoring Team.
  • 4. Hwange Power Station, Zimbabwe - Rehabilitation Project The current severe situation at the Hwange Power Station can be summarized as follows: I. Luck of local and foreign funds for maintenance and repairs; II. Exceeded normal major overhaul running hours; III. Overdue for mandatory maintenance work; IV. Thus increasing the forced outage rates and accelerates equipment deterioration; V. Decreased unit efficiency and low plant load factor; VI. Latent risk of enforced outages by inspection authorities; VII. Increased risk of critical and severe failures. Only for Stage II (unit 5 & 6) funds were available and overhauls have been carried out. However, luck of financing substantially reduced the envisaged scope of work.
  • 5. Hwange Power Station, Zimbabwe - Rehabilitation Project Due to the situation described aforementioned the plant operating conditions are as follows as per 31 January 2007: Unit no.: Last major overhaul Running hours to next planned major overhaul Running hours since last major overhaul Excess running hours 1 23/03/1996 - 31/05/1996 50 000 74 266 24 266 2 06/10/1997 - 19/12/1997 50 000 66 608 16 608 3 13/11/1994 - 01/02/1995 50 000 71 009 21 009 4 09/12/1995 - 23/02/1996 50 000 70 859 20 859 5 06/09/2002 - 30/05/2003 50 000 17 476 6 25/11/2003 - 08/08/2004 50 000 9 272
  • 6. Hwange Power Station, Zimbabwe - Rehabilitation Project With the foreign currency funds made available by NamPower via a specific Stanbic bank account it is envisaged to overcome the severe situation in the operation and maintenance of the power plant. With the decided Hwange Power Station Rehabilitation Project the following targets shall be attained: I. Recapturing of unit output of 4 x 120 MW; II. Increase of operational reliability; III. Reduction of forced outages; IV. Improvement of unit efficiency; V. Grid stability. For the purpose of monitoring the project and assist and support ZPC with the project implementation NamPower engaged Lahmeyer International and in addition will provide own resources during the execution.
  • 7. Hwange Power Station, Zimbabwe - Rehabilitation Project For the successful project implementation the following key challenges have been identified to overcome in course of the project: I. Tight project implementation programme; II. Assignment of experienced experts to the ZPC project team; III. Reliable tendering process; IV. Delivery time of manufacturer parts; V. Availability of local funds.
  • 8. The envisaged scope of rehabilitation works for Stage I, unit 1 – 4 is summarized as follows: I. Boiler and auxiliaries: - Super heater, evaporator and economizer tubes; - PF-burner repair; - Start-up burner repair; - Tubular air heater tube replacement; - Coal mill overhaul. II. Steam turbine/generator and auxiliaries: - Extensive turbine overhaul; - Generator excitation system overhaul. III. Ancillary systems: - Station coal conveyer system overhaul; - Ash disposal system; - Water treatment plant; - Transformer repair; - Switchgear (LV,HV) replacement; - Control system, unit instrumentation; - Compressor station. Hwange Power Station, Zimbabwe - Rehabilitation Project
  • 9. Appendix 2 to this Project Implementation Guideline outlines a more detailed summary of the envisaged scope of rehabilitation works prepared by ZPC. The preliminary planning for the execution of works is listed below. However, the detailed planning for the execution of the rehabilitation works is subject to the next steps, the priorities of measures and the feedback from the contractors and/or equipment manufactures: Hwange Power Station, Zimbabwe - Rehabilitation Project Unit Preliminary planning for rehabilitation works Unit no.: 3 01/11/2007 - 31/12/2007 Unit no.: 1 01/01/2008 - 31/03/2008 Unit no.: 4 01/05/2008 - 30/06/2008 Unit no.: 2 01/07/2008 - 31/08/2008 Auxiliary systems 01/04/2007 - 31/10/2007
  • 10. Based on the envisaged scope of rehabilitation works ZPC worked out a preliminary break down of the rehabilitation works costs compiled in the following table: Hwange Power Station, Zimbabwe - Rehabilitation Project Item Local currency (Mio. Z$) (as at Mid Feb 2007) Foreign expenditures (Mio. US$) Aux Plant 770.0 6.5 Unit 3 Major Overhaul 1 410.0 7.1 Unit 1 Major Overhaul 1 290.0 7.3 Unit 4 Major Overhaul 1 225.0 7.1 Unit 2 Major Overhaul 1 125.0 6.8 Contingencies 1 164.0 5.2 Total 5 823.0 40.0
  • 11. NamPower / LI Monitoring Team ZPC Managing Director Hwange Power Station General Manager Hwange Power Station Project Manager Accounting Quality & Engineering Procurement & Stores Works Supervision Contracts Management For the success of this project it is mandatory that ZPC’s Rehabilitation Project Team is equipped with capable manpower during the complete project execution period. Particular the positions for “Quality & Engineering” and “Works Supervision” shall be continuously assigned to experienced engineers, capable of providing the mandatory services for planning, scheduling, tendering and works supervision. Rehabilitation Project Team - Organisation and Tasks
  • 12. NamPower Lahmeyer International ZPC Rehabilitation Monitoring Team (RMT) Rehabilitation Project Team Rehabilitation Project Team - Organisation and Tasks NamPower Tasks: • Requirements from PPA • Funding of bank account • Loan management • Release of payment ZPC Tasks: • Tender documents • Contract award • Scheduling • Utilities • Works supervision • Acceptance tests • Works certificates RMT Tasks: • Support and assistance in tendering and evaluation • Project monitoring • Payment release certificates
  • 13. Project Preparation and Implementation Phase – Coordination between ZPC / RMT Award of contract (ZPC) Document distribution (ZPC) Evaluation of bidders’ proposals (ZPC) RMT to support and assist in the evaluation process RMT to recommend contract award RMT to monitor the progress Hwange Rehabilitation Monitoring Project – Task Structure Clarification for scope of work (ZPC) Compilation of tender docs. (ZPC) RMT to support and assist in the tender process Issuance of request for proposal (ZPC) RMT to monitor the progress Evaluation Process Implementation Process Tendering Process Project scheduling (ZPC) Project supervision (ZPC) Project progress meetings with ZPC project team Acceptance tests and certificates (ZPC) Project support for utilities and resources (ZPC) RMT to monitor the progress Payment Release Certificate
  • 14. Hwange Rehabilitation Monitoring Project – Approach Stage 1- Project Preparation: I. ZPC defined / will define the scope of rehabilitation work for Unit 1 - 4 and ancillary systems: - RMT will compare the suggested scope of work with the recommended measures from the assessment report and discuss with the ZPC-Rehabilitation Project Team the prioritised measures for: Boiler, turbine, generator, switch yard, ancillary system rehabilitation. II. Preparation of project time schedule for all activities: - Priorities; - Delivery times; - Operational constrains. III. Compilation of tender documents by ZPC, supported by RMT: - Technical specification (system description, data sheets, extract from drawings, documents, manuals etc.); - Financial specification (to be discussed and agreed upon between the parties); - Contractual terms and conditions (to be discussed and agreed upon between the parties); - Instructions to bidders (to be discussed and agreed upon between the parties).
  • 15. Hwange Rehabilitation Monitoring Project – Approach Stage 1- Project Preparation: IV. Evaluation of bidders’ proposals by ZPC, supported by RMT: - Completeness and responsiveness of submitted proposals; - Technical evaluation to verify compliance with technical specification and QA requirements, review of provided technical information; - Commercial evaluation to verify the compliance with the dedicated budget and financial requirements; - Contractual evaluation to verify the compliance with the terms and conditions and time schedule; - Considerable deviations; - Recommendation from RMT for the contract award. V. Award of contract to successful bidders by ZPC: - ZPC and RMT to agree on the conditions for contract award; - RMT will confirm the contract award to NamPower and bank; - ZPC will award the contract to the successful bidders. VI. Project progress monitoring by RMT: - Regular reporting to NamPower to compile status and outlook on tenders, contracts, supplies, services and works, budget forecast and cash flow, noticeable events.
  • 16. Hwange Rehabilitation Monitoring Project – Approach Stage 1- Project Preparation: The tendering process shall be in compliance with ZPC’s tendering and purchasing procedure which is attached as Appendix 3. ZPC’s tendering and purchasing procedure compiles the following: - Raising and authorisation of purchasing requisitions; - Foreign purchases; - Floating of direct enquiries and order placement; - Informal tender floating and order placement. For an effective tendering process it is mandatory that a standard procedure will be implemented to compile the technical specifications, financial and contractual conditions.
  • 17. Hwange Rehabilitation Monitoring Project – Approach Stage 2 - Project Implementation: I. Project supervision by ZPC: - Regular meetings with the ZPC rehabilitation project team (status, scheduling, site activities, inspections, tests and necessary actions); - Rehabilitation works supervised by ZPC; - Acceptance tests verified by ZPC and witnessed by RMT (major contracts); - ZPC will issue the acceptance certificates (PAC/FAC); - Mandatory update of As-build drawings, documents, manuals by ZPC. II. Project progress monitoring by RMT: - Verification and approval of contractors’ request for payment (Payment Release Certificate); - Regular reports to compile status and outlook on supplies, works and services, budget forecast and cash flow, noticeable events; - Clarification on discrepancies between the parties; - Recommendation on measures to be taken to ZPC and NamPower; - RMT will monitor rehabilitation works and completion (commissioning, acceptance tests and recommendation for completion).
  • 18. Hwange Rehabilitation Monitoring Project – Approach PAYMENT RELEASE CERTIFICATE Stanbic Bank, Botswana NamPower PM approves Instruction for Payment Payment release from Stanbic Bank to Contractors Contractors’ payment request RMT verifies and approves Feedback on transactions to ZPC, NamPower and RMT ZPC approves and signs NamPower Treasury releases Process for the release of payment
  • 19. PAYMENT RELEASE CERTIFICATE ZPC order no.: Date of issue: Beneficiary: Reference no.: Scope of work: Approved invoice no.: Attachments: Requested payment: - Payment instructions Total amount to be released: (- Letter of award) (- Contract) Stanbic Bank, Botswana Bank account no.: Approved by: NamPower ZPC Lahmeyer International Name: Name: Name: Signature: Signature: Signature:
  • 20. Appendix 1 – Table of contents for a typical project manual; Appendix 2 - Outline of the envisaged scope of rehabilitation works prepared by ZPC; Appendix 3 – ZPC’s tendering and purchasing procedure. Project Implementation Guideline - Appendices