- 1. Activity ID Activity Name Original
Duration
Start Finish
14234-3 Eg14234-3 Egbaoma Gas Processing Plant - New 586 05-Aug-14 A 04-Apr-16
14234-3.Co14234-3.Contract About Contract 459 05-Aug-14 A 04-Apr-16
A21270 Kick Off Meeting 0 05-Aug-14 A
A21280 Commencement of Project Work 0 05-Aug-14 A
A21790 HAZOP 8 17-Dec-14 A 24-Dec-14 A
A21800 Engineering Completion 0 21-Sep-15
A21810 Procurement Completion 0 26-Oct-15
A21820 Site Modification, Construction & Erection Works Completion 0 24-Feb-16
A21830 Pre-Commissioning & Commissioning Works Completion 0 29-Feb-16
A21840 First Gas In & Successful Test Run 0 29-Feb-16
A21940 Performance Test 3 29-Feb-16 03-Mar-16
A21950 Reliability Test 30 03-Mar-16 04-Apr-16
A21960 Project Closing 0 04-Apr-16
14234-3.En14234-3.Engineering Engineering 398 18-Aug-14 A 02-Oct-15
14234-3.En14234-3.Engineering.1 Process 341 18-Aug-14 A 19-Apr-15 A
A21350 Process Design Completion 0 19-Apr-15 A
14234-3.E14234-3.Engineering.1.1 Documents and Reports 341 18-Aug-14 A 19-Apr-15 A
14234-3.E14234-3.Engineering.1.2 Drawings 326 27-Aug-14 A 25-Mar-15 A
14234-3.En14234-3.Engineering.2 Mechanical Static 377 21-Aug-14 A 15-Apr-15 A
A21360 Mechanical Static Design Completion 0 15-Apr-15 A
14234-3.E14234-3.Engineering.2.2 Design Calculation Book 286 17-Sep-14 A 15-Apr-15 A
14234-3.E14234-3.Engineering.2.3 Drawings 367 21-Aug-14 A 09-Apr-15 A
14234-3.E14234-3.Engineering.2.4 Datasheet 295 17-Sep-14 A 09-Apr-15 A
14234-3.E14234-3.Engineering.2.1 Documents 277 11-Sep-14 A 10-Mar-15 A
14234-3.En14234-3.Engineering.4 Piping 366 11-Sep-14 A 04-May-15 A
A21380 Piping Design Start 0 11-Sep-14 A
A21670 Piping Design Completion 0 30-Mar-15 A
14234-3.E14234-3.Engineering.4.3 Skid General Arrangement Drawing 366 02-Oct-14 A 30-Mar-15 A
14234-3.E14234-3.Engineering.4.1 Documents 81 03-Nov-14 A 04-Feb-15 A
14234-3.E14234-3.Engineering.4.2 General Drawings 292 11-Sep-14 A 04-May-15 A
14234-3.En14234-3.Engineering.3 Mechanical Rotating 177 06-Jan-15 A 19-Apr-15 A
A21370 Mechanical Rotating Design Completion 0 19-Apr-15 A
14234-3.E14234-3.Engineering.3.1 Datasheets 177 06-Jan-15 A 19-Apr-15 A
14234-3.En14234-3.Engineering.5 Electrical 202 02-Oct-14 A 02-Oct-15 A
A21390 Electrical System Design Completion 0 14-Apr-15 A
14234-3.E14234-3.Engineering.5.2 Documents 194 02-Oct-14 A 02-Oct-15 A
14234-3.E14234-3.Engineering.5.1 Data Sheets 101 07-Jan-15 A 03-Feb-15 A
14234-3.E14234-3.Engineering.5.3 Drawings 103 26-Jan-15 A 14-Apr-15 A
14234-3.En14234-3.Engineering.6 Instrumentation 314 05-Nov-14 A 09-Jul-15 A
A21400 Instrumentation System Design Completion 0 15-Apr-15 A
14234-3.E14234-3.Engineering.6.2 Documents 186 05-Nov-14 A 09-Jul-15 A
14234-3.E14234-3.Engineering.6.1 Data Sheets 176 07-Jan-15 A 12-May-15 A
14234-3.E14234-3.Engineering.6.30 Layouts & Drawings 183 25-Feb-15 A 22-Apr-15 A
14234-3.En14234-3.Engineering.7 Civil & Structure 360 21-Aug-14 A 12-Aug-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
2014 2015 2016
04-Apr-16,
04-Apr-16,
Kick Off Meeting, 05-Aug-14 A
Commencement of Project Work, 05-Aug-14 A
HAZOP
Engineering Completion,
Procurement Completion,
Site Modification
Pre-Commissio
First Gas In &
Performance T
Reliability T
Project Clo
02-Oct-15, 14234-3.Engineering
19-Apr-15 A, 14234-3.Engineering.1 Process
Process Design Completion,
19-Apr-15 A, 14234-3.Engineering.1.1 Documents a
25-Mar-15 A, 14234-3.Engineering.1.2 Drawings
15-Apr-15 A, 14234-3.Engineering.2 Mechanical Stat
Mechanical Static Design Completion,
15-Apr-15 A, 14234-3.Engineering.2.2 Design Calcul
09-Apr-15 A, 14234-3.Engineering.2.3 Drawings
09-Apr-15 A, 14234-3.Engineering.2.4 Datasheet
10-Mar-15 A, 14234-3.Engineering.2.1 Documents
04-May-15 A, 14234-3.Engineering.4 Piping
Piping Design Start, 11-Sep-14 A
Piping Design Completion,
30-Mar-15 A, 14234-3.Engineering.4.3 Skid General Ar
04-Feb-15 A, 14234-3.Engineering.4.1 Documents
04-May-15 A, 14234-3.Engineering.4.2 General Dr
19-Apr-15 A, 14234-3.Engineering.3 Mechanical Rot
Mechanical Rotating Design Completion,
19-Apr-15 A, 14234-3.Engineering.3.1 Datasheets
02-Oct-15 A, 14234-3.Engineerin
Electrical System Design Completion,
02-Oct-15 A, 14234-3.Engineerin
03-Feb-15 A, 14234-3.Engineering.5.1 Data Sheets
14-Apr-15 A, 14234-3.Engineering.5.3 Drawings
09-Jul-15 A, 14234-3.Engineering.6 Instrum
Instrumentation System Design Completion,
09-Jul-15 A, 14234-3.Engineering.6.2 Docu
12-May-15 A, 14234-3.Engineering.6.1 Data Shee
22-Apr-15 A, 14234-3.Engineering.6.30 Layouts & D
12-Aug-15, 14234-3.Engineering.7 Civ
Egbaoma Gas Processing Plant - New Level IV Schedule-latest 16-Jul-15 15:25
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaini...
Page 1 of 7 TASK filter: All Activities
© Oracle Corporation
- 2. Activity ID Activity Name Original
Duration
Start Finish
A21410 Civil & Structure Design Completion 0 12-Aug-15
14234-3.E14234-3.Engineering.7.2 Drawings 360 21-Aug-14 A 12-Aug-15
14234-3.E14234-3.Engineering.7.1 Document 78 03-Nov-14 A 29-Jan-15 A
14234-3.En14234-3.Engineering.8 HSE 306 20-Aug-14 A 22-Jun-15 A
A21420 HSE Documentation Completion 0 22-Jun-15 A
14234-3.E14234-3.Engineering.8.1 Document 306 20-Aug-14 A 22-Jun-15 A
14234-3.En14234-3.Engineering.9 QAQC 147 20-Aug-14 A 10-Mar-15 A
A21430 QAQC Documentation Completion 0 10-Mar-15 A
14234-3.E14234-3.Engineering.9.1 Document 59 20-Aug-14 A 10-Mar-15 A
14234-3.En14234-3.Engineering.10 Commissioning 244 05-Nov-14 A 21-Sep-15
A21440 Commissioning Documentation Completion 0 21-Sep-15
14234-3.E14234-3.Engineering.10.1 Documents 244 05-Nov-14 A 21-Sep-15
14234-3.En14234-3.Engineering.11 General 194 15-Sep-14 A 25-Mar-15 A
A21450 General Documentation Completion 0 25-Mar-15 A
14234-3.E14234-3.Engineering.11.1 Documents 107 15-Sep-14 A 25-Mar-15 A
14234-3.Pr14234-3.Procourment Procurement 310 19-Oct-14 A 26-Oct-15
A21460 Procurement Completion 0 26-Oct-15
14234-3.Pr14234-3.Procourment.1 Issuance of PO for major buyout Items 216 19-Oct-14 A 22-Jan-15 A
A21570 PO Placed for all Major Items 0 22-Jan-15 A
14234-3.P14234-3.Procourment.1.2 Deethanizer OH Condenser E-401 71 19-Oct-14 A 19-Oct-14 A
14234-3.P14234-3.Procourment.1.3 Condensate Stabilization Column C-3001 7 19-Oct-14 A 19-Oct-14 A
14234-3.P14234-3.Procourment.1.6 Gas/Gas Exchanger E-300A 7 19-Oct-14 A 19-Oct-14 A
14234-3.P14234-3.Procourment.1.7 Gas/Gas Exchanger E-300B 7 19-Oct-14 A 19-Oct-14 A
14234-3.P14234-3.Procourment.1.8 Gas/Liquid Exchanger E-302A 54 19-Oct-14 A 08-Dec-14 A
14234-3.P14234-3.Procourment.1.10 Regeneration Gas Cooler E-303 54 19-Oct-14 A 04-Jan-15 A
14234-3.P14234-3.Procourment.1.11 Water Degassing Boot V-3401 7 19-Oct-14 A 19-Oct-14 A
14234-3.P14234-3.Procourment.1.12 CPI Separator V-3402 7 19-Oct-14 A 19-Oct-14 A
14234-3.P14234-3.Procourment.1.13 On Spec Condensate Storage Tank T-3301 7 21-Jan-15 A 22-Jan-15 A
14234-3.P14234-3.Procourment.1.14 Off Spec Condensate Storage Tank T-3302 7 21-Jan-15 A 22-Jan-15 A
14234-3.P14234-3.Procourment.1.15 Bulk Materials 17 08-Dec-14 A 08-Dec-14 A
14234-3.P14234-3.Procourment.1.9 Gas/Liquid Exchanger E-302B 54 19-Oct-14 A 08-Dec-14 A
14234-3.P14234-3.Procourment.1.1 Chiller E-301 46 19-Oct-14 A 19-Oct-14 A
14234-3.P14234-3.Procourment.1.5 Condensate Reboiler E-3001 7 19-Oct-14 A 19-Oct-14 A
14234-3.P14234-3.Procourment.1.4 Propane Receiver V-706 7 19-Oct-14 A 19-Oct-14 A
14234-3.Pr14234-3.Procourment.2 Receipt of Head & Shell Materials at SPEC Facility 253 19-Oct-14 A 22-Feb-15 A
A21560 Fabrication Material Received @ SPEC Fabrication Facility 0 22-Feb-15 A
14234-3.P14234-3.Procourment.2.1 Chiller E-301 17 19-Oct-14 A 02-Dec-14 A
14234-3.P14234-3.Procourment.2.2 Deethanizer OH Condenser E-401 17 19-Oct-14 A 02-Dec-14 A
14234-3.P14234-3.Procourment.2.3 Condensate Stabilization Column C-3001 17 19-Oct-14 A 02-Dec-14 A
14234-3.P14234-3.Procourment.2.4 Propane Receiver V-706 17 19-Oct-14 A 02-Dec-14 A
14234-3.P14234-3.Procourment.2.5 Condensate Reboiler E-3001 17 19-Oct-14 A 02-Nov-14 A
14234-3.P14234-3.Procourment.2.6 Gas/Gas Exchanger E-300A 40 19-Oct-14 A 02-Dec-14 A
14234-3.P14234-3.Procourment.2.7 Gas/Gas Exchanger E-300B 40 19-Oct-14 A 02-Dec-14 A
14234-3.P14234-3.Procourment.2.8 Gas/Liquid Exchanger E-302A 47 19-Oct-14 A 30-Dec-14 A
14234-3.P14234-3.Procourment.2.9 Gas/Liquid Exchanger E-302B 47 19-Oct-14 A 30-Dec-14 A
14234-3.P14234-3.Procourment.2.10 Regeneration Gas Cooler E-303 47 19-Oct-14 A 05-Jan-15 A
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
2014 2015 2016
Civil & Structure Design Completion,
12-Aug-15, 14234-3.Engineering.7.2 D
29-Jan-15 A, 14234-3.Engineering.7.1 Document
22-Jun-15 A, 14234-3.Engineering.8 HSE
HSE Documentation Completion,
22-Jun-15 A, 14234-3.Engineering.8.1 Docum
10-Mar-15 A, 14234-3.Engineering.9 QAQC
QAQC Documentation Completion,
10-Mar-15 A, 14234-3.Engineering.9.1 Document
21-Sep-15, 14234-3.Engineering.1
Commissioning Documentation Co
21-Sep-15, 14234-3.Engineering.1
25-Mar-15 A, 14234-3.Engineering.11 General
General Documentation Completion,
25-Mar-15 A, 14234-3.Engineering.11.1 Documents
26-Oct-15, 14234-3.Procourm
Procurement Completion,
22-Jan-15 A, 14234-3.Procourment.1 Issuance of PO for majo
PO Placed for all Major Items,
19-Oct-14 A, 14234-3.Procourment.1.2 Deethanizer OH Condenser E-40
19-Oct-14 A, 14234-3.Procourment.1.3 Condensate Stabilization Column
19-Oct-14 A, 14234-3.Procourment.1.6 Gas/Gas Exchanger E-300A
19-Oct-14 A, 14234-3.Procourment.1.7 Gas/Gas Exchanger E-300B
08-Dec-14 A, 14234-3.Procourment.1.8 Gas/Liquid Exchanger E-30
04-Jan-15 A, 14234-3.Procourment.1.10 Regeneration Gas Coo
19-Oct-14 A, 14234-3.Procourment.1.11 Water Degassing Boot V-3401
19-Oct-14 A, 14234-3.Procourment.1.12 CPI Separator V-3402
22-Jan-15 A, 14234-3.Procourment.1.13 On Spec Condensate
22-Jan-15 A, 14234-3.Procourment.1.14 Off Spec Condensate
08-Dec-14 A, 14234-3.Procourment.1.15 Bulk Materials
08-Dec-14 A, 14234-3.Procourment.1.9 Gas/Liquid Exchanger E-30
19-Oct-14 A, 14234-3.Procourment.1.1 Chiller E-301
19-Oct-14 A, 14234-3.Procourment.1.5 Condensate Reboiler E-3001
19-Oct-14 A, 14234-3.Procourment.1.4 Propane Receiver V-706
22-Feb-15 A, 14234-3.Procourment.2 Receipt of Head & S
Fabrication Material Received @ SPEC Fabrication Facility,
02-Dec-14 A, 14234-3.Procourment.2.1 Chiller E-301
02-Dec-14 A, 14234-3.Procourment.2.2 Deethanizer OH Condenser
02-Dec-14 A, 14234-3.Procourment.2.3 Condensate Stabilization Co
02-Dec-14 A, 14234-3.Procourment.2.4 Propane Receiver V-706
02-Nov-14 A, 14234-3.Procourment.2.5 Condensate Reboiler E-3001
02-Dec-14 A, 14234-3.Procourment.2.6 Gas/Gas Exchanger E-300A
02-Dec-14 A, 14234-3.Procourment.2.7 Gas/Gas Exchanger E-300B
30-Dec-14 A, 14234-3.Procourment.2.8 Gas/Liquid Exchanger E
30-Dec-14 A, 14234-3.Procourment.2.9 Gas/Liquid Exchanger E
05-Jan-15 A, 14234-3.Procourment.2.10 Regeneration Gas Coo
Egbaoma Gas Processing Plant - New Level IV Schedule-latest 16-Jul-15 15:25
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaini...
Page 2 of 7 TASK filter: All Activities
© Oracle Corporation
- 3. Activity ID Activity Name Original
Duration
Start Finish
14234-3.P14234-3.Procourment.2.11 Water Degassing Boot V-3401 21 19-Oct-14 A 07-Dec-14 A
14234-3.P14234-3.Procourment.2.12 CPI Separator V-3402 21 19-Oct-14 A 07-Dec-14 A
14234-3.P14234-3.Procourment.2.13 On Spec Condensate Storage Tank T-3301 49 22-Jan-15 A 22-Feb-15 A
14234-3.P14234-3.Procourment.2.14 Off Spec Condensate Storage Tank T-3302 49 22-Jan-15 A 22-Feb-15 A
14234-3.P14234-3.Procourment.2.15 Bulk Materials 21 08-Dec-14 A 30-Dec-14 A
14234-3.Pr14234-3.Procourment.3 Successful Vessel Hydro Test 22 02-Apr-15 A 16-Aug-15
A21550 Hydrotesting of Vessels Completion 0 16-Aug-15
14234-3.P14234-3.Procourment.3.1 Chiller E-301 1 16-Aug-15 16-Aug-15
14234-3.P14234-3.Procourment.3.2 Deethanizer OH Condenser E-401 1 16-Aug-15 16-Aug-15
14234-3.P14234-3.Procourment.3.3 Condensate Stabilization Column C-3001 1 03-Apr-15 A 03-Apr-15 A
14234-3.P14234-3.Procourment.3.4 Propane Receiver V-706 1 03-Apr-15 A 03-Apr-15 A
14234-3.P14234-3.Procourment.3.5 Condensate Reboiler E-3001 1 03-Apr-15 A 03-Apr-15 A
14234-3.P14234-3.Procourment.3.6 Gas/Gas Exchanger E-300A 1 16-Aug-15 16-Aug-15
14234-3.P14234-3.Procourment.3.7 Gas/Gas Exchanger E-300B 1 16-Aug-15 16-Aug-15
14234-3.P14234-3.Procourment.3.8 Gas/Liquid Exchanger E-302A 1 16-Aug-15 16-Aug-15
14234-3.P14234-3.Procourment.3.9 Gas/Liquid Exchanger E-302B 1 16-Aug-15 16-Aug-15
14234-3.P14234-3.Procourment.3.10 Regeneration Gas Cooler E-303 1 16-Aug-15 16-Aug-15
14234-3.P14234-3.Procourment.3.11 Water Degassing Boot V-3401 1 02-Apr-15 A 02-Apr-15 A
14234-3.P14234-3.Procourment.3.12 CPI Separator V-3402 1 02-Apr-15 A 02-Apr-15 A
14234-3.Pr14234-3.Procourment.4 Equipment FAT at SPEC Facility 41 16-Aug-15 25-Oct-15
A21540 Equipment FAT Completion 0 25-Oct-15
14234-3.P14234-3.Procourment.4.1 Gas/Gas Exchanger (E-300A/B) Skid 1 10-Sep-15 13-Sep-15
14234-3.P14234-3.Procourment.4.2 Gas Liquid Exchanger (E-302A/B) Skid 1 27-Aug-15 30-Aug-15
14234-3.P14234-3.Procourment.4.3 Regeneration Gas Cooler (E-303) Skid 1 10-Sep-15 13-Sep-15
14234-3.P14234-3.Procourment.4.4 Gas Metering Package 1 25-Oct-15 25-Oct-15
14234-3.P14234-3.Procourment.4.5 NGL Stabilization Package 1 25-Oct-15 25-Oct-15
14234-3.P14234-3.Procourment.4.6 NGL Loading Pump Package 1 30-Aug-15 30-Aug-15
14234-3.P14234-3.Procourment.4.7 Water Degassing Boot & CPI Separator Package 1 16-Aug-15 16-Aug-15
14234-3.P14234-3.Procourment.4.8 ESD/FGS Panel 2 27-Sep-15 28-Sep-15
14234-3.Pr14234-3.Procourment.5 Shipping Readiness of Materials from SPEC Facility 41 17-Aug-15 26-Oct-15
A21530 Shipping Readiness of Materials @ SPEC Facility 0 26-Oct-15
14234-3.P14234-3.Procourment.5.1 Gas/Gas & Gas/Liquid Exchangers Package 2 13-Sep-15 16-Sep-15
14234-3.P14234-3.Procourment.5.2 Gas Metering Package 1 26-Oct-15 26-Oct-15
14234-3.P14234-3.Procourment.5.3 Condensate Stabilization Package 1 26-Oct-15 26-Oct-15
14234-3.P14234-3.Procourment.5.4 Condensate Loading Pump Package 1 31-Aug-15 31-Aug-15
14234-3.P14234-3.Procourment.5.5 Water Degassing Boot & CPI Separator Package 1 17-Aug-15 17-Aug-15
14234-3.P14234-3.Procourment.5.6 ESD/FGS Panel 1 29-Sep-15 29-Sep-15
14234-3.Pr14234-3.Project Constraints Project Constraints 137 09-Jul-15 27-Nov-15
A23989 Project Activities Resumed 0 09-Jul-15
A23990 First Shipment Despatch from HFZ 5 15-Aug-15* 20-Aug-15
A24000 First Shipment Receiving on Site 65 20-Aug-15 27-Oct-15
A24040 Overhaul of Compressors & Generators 80 15-Aug-15* 06-Nov-15
A24050 Procurement of MCC Enclosure & Component 5 15-Jul-15* 20-Jul-15
A24060 Material Deliveries, Assembly, & FAT 65 20-Jul-15 25-Sep-15
A24080 Procurement of Synchornization Controller + Delivery to HFZ 25 15-Aug-15* 10-Sep-15
A24100 Pumps Receiving in HFZ 45 09-Jul-15 24-Aug-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
2014 2015 2016
07-Dec-14 A, 14234-3.Procourment.2.11 Water Degassing Boot V-3
07-Dec-14 A, 14234-3.Procourment.2.12 CPI Separator V-3402
22-Feb-15 A, 14234-3.Procourment.2.13 On Spec Conden
22-Feb-15 A, 14234-3.Procourment.2.14 Off Spec Conden
30-Dec-14 A, 14234-3.Procourment.2.15 Bulk Materials
16-Aug-15, 14234-3.Procourment.3 S
Hydrotesting of Vessels Completion,
16-Aug-15, 14234-3.Procourment.3.1
16-Aug-15, 14234-3.Procourment.3.2
03-Apr-15 A, 14234-3.Procourment.3.3 Condensate S
03-Apr-15 A, 14234-3.Procourment.3.4 Propane Rece
03-Apr-15 A, 14234-3.Procourment.3.5 Condensate R
16-Aug-15, 14234-3.Procourment.3.6
16-Aug-15, 14234-3.Procourment.3.7
16-Aug-15, 14234-3.Procourment.3.8
16-Aug-15, 14234-3.Procourment.3.9
16-Aug-15, 14234-3.Procourment.3.10
02-Apr-15 A, 14234-3.Procourment.3.11 Water Degas
02-Apr-15 A, 14234-3.Procourment.3.12 CPI Separato
25-Oct-15, 14234-3.Procourm
Equipment FAT Completion,
13-Sep-15, 14234-3.Procourment.4
30-Aug-15, 14234-3.Procourment.4.2
13-Sep-15, 14234-3.Procourment.4
25-Oct-15, 14234-3.Procourm
25-Oct-15, 14234-3.Procourm
30-Aug-15, 14234-3.Procourment.4.6
16-Aug-15, 14234-3.Procourment.4.7
28-Sep-15, 14234-3.Procourmen
26-Oct-15, 14234-3.Procourm
Shipping Readiness of Materia
16-Sep-15, 14234-3.Procourment.
26-Oct-15, 14234-3.Procourm
26-Oct-15, 14234-3.Procourm
31-Aug-15, 14234-3.Procourment.5.
17-Aug-15, 14234-3.Procourment.5.5
29-Sep-15, 14234-3.Procourmen
27-Nov-15, 14234-3.Proje
Project Activities Resumed, 09-Jul-15
First Shipment Despatch from HFZ
First Shipment Receiving on S
Overhaul of Compressors &
Procurement of MCC Enclosure & Compo
Material Deliveries, Assembly, & F
Procurement of Synchornization Co
Pumps Receiving in HFZ
Egbaoma Gas Processing Plant - New Level IV Schedule-latest 16-Jul-15 15:25
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaini...
Page 3 of 7 TASK filter: All Activities
© Oracle Corporation
- 4. Activity ID Activity Name Original
Duration
Start Finish
A24101 Procurement of Commissioning Spare 5 01-Sep-15* 05-Sep-15
A24102 Commissioning Spares Receiving In HFZ 25 05-Sep-15 01-Oct-15
A24150 Procurement of Electrical & Instrumentation Cables 5 30-Jul-15* 04-Aug-15
A24160 Electrical & Instrumentation Cables Ex. Works Readiness & Receiving on Site 92 04-Aug-15 07-Nov-15
A24161 DPR Visit - Hydro for 2nd Lot of Vessels and FAT for 1st lot Skid Packages 14 25-Aug-15* 08-Sep-15
A24162 Punch List Close Out + Shipping Readiness 3 08-Sep-15 11-Sep-15
A24170 2nd Shipment Dispatch from UAE 5 11-Sep-15 16-Sep-15
A24180 2nd Shipment Receiving on Site 50 16-Sep-15 06-Nov-15
A24181 DPR Visit - FAT for 2nd Lot of Skid Packages 13 15-Sep-15* 28-Sep-15
A24182 Punch List Close Out + Shipping Readiness 3 28-Sep-15 01-Oct-15
A24190 3rd Shipment Dispatch from UAE 5 01-Oct-15 07-Oct-15
A24200 3rd Shipment Receiving on Site 50 07-Oct-15 27-Nov-15
14234-3.Co14234-3.Construction Site Modification, Construction & Erection W 222 21-Jan-15 A 24-Feb-16
A21880 Site Modification, Construction & Erection Completion 0 24-Feb-16
14234-3.C14234-3.Construction.2 Site Construction & Erection Works 222 21-Jan-15 A 24-Feb-16
A21510 Site Construction & Erection Works Completion 0 24-Feb-16
14234-3.C14234-3.Construction.2.1 Foundation for Gas Metering Package 56 12-Aug-15 09-Oct-15
14234-3.C14234-3.Construction.2.2 Foundation for Water Degassing Boot & CPI Separator Sk 56 12-Aug-15 09-Oct-15
14234-3.C14234-3.Construction.2.3 Foundation for NGL Storage Tank T-3101 56 21-Jan-15 A 05-Sep-15
14234-3.C14234-3.Construction.2.4 Foundation for Condensate Stabilization Skid 56 12-Aug-15 09-Oct-15
14234-3.C14234-3.Construction.2.5 Foundation for Condensate Transfer Pump Skid 56 12-Aug-15 09-Oct-15
14234-3.C14234-3.Construction.2.6 Foundation for Gas/Gas Exchanger (E-300A/B) Skid 42 21-Sep-15 03-Nov-15
14234-3.C14234-3.Construction.2.7 Foundation for Gas Liquid Exchanger (E-302(A/B Skid 56 12-Aug-15 09-Oct-15
14234-3.C14234-3.Construction.2.8 Foundation for Regeneration Gas Cooler (E-303) Skid 42 21-Sep-15 04-Nov-15
14234-3.C14234-3.Construction.2.9 Foundation for Lighting Poles 56 12-Aug-15 09-Oct-15
14234-3.C14234-3.Construction.2.26 Erection of Gas Metering Skid 5 14-Nov-15 20-Nov-15
14234-3.C14234-3.Construction.2.10 Foundation for NGL Storage Tank T-3102 56 09-Jul-15 05-Sep-15
14234-3.C14234-3.Construction.2.28 Erection of NGL Storage Tank T-3101 126 09-Jul-15 16-Nov-15
14234-3.C14234-3.Construction.2.27 Erection of NGL Storage Tank T-3102 126 09-Jul-15 16-Nov-15
14234-3.C14234-3.Construction.2.11 Erection of Water Degassing Boot & CPI Separator Skid 7 14-Nov-15 23-Nov-15
14234-3.C14234-3.Construction.2.12 Erection of Condensate Stabilization Skid 14 27-Nov-15 11-Dec-15
14234-3.C14234-3.Construction.2.13 Erection of NGL Transfer Pump Skid 7 27-Nov-15 04-Dec-15
14234-3.C14234-3.Construction.2.14 Erection of Gas/Gas Exchanger (E-300A/B) Skid 7 09-Dec-15 17-Dec-15
14234-3.C14234-3.Construction.2.15 Erection of Gas Liquid Exchanger (E-302(A/B Skid 7 27-Nov-15 04-Dec-15
14234-3.C14234-3.Construction.2.16 Erection of Regeneration Gas Cooler (E-303) Skid 7 10-Dec-15 17-Dec-15
14234-3.C14234-3.Construction.2.17 Erection of Lighting Poles 7 14-Nov-15 23-Nov-15
14234-3.C14234-3.Construction.2.18 Cable Pulling - Instrument Cables 21 07-Nov-15 28-Nov-15
14234-3.C14234-3.Construction.2.19 Cable Pulling - Electrical Cables 21 07-Nov-15 28-Nov-15
14234-3.C14234-3.Construction.2.20 Electrical Cables Termination in MCC 14 19-Jan-16 02-Feb-16
14234-3.C14234-3.Construction.2.21 Erection of ESD/FGS Panel 7 27-Nov-15 04-Dec-15
14234-3.C14234-3.Construction.2.22 Instruments Cable Termination in DCS Panel 14 04-Dec-15 19-Dec-15
14234-3.C14234-3.Construction.2.23 Instruments Cable Termination in ESD/FGS Panel 14 07-Nov-15 21-Nov-15
14234-3.C14234-3.Construction.2.24 Interconnecting Cables - DCS to ESD/FGS Panel 14 19-Dec-15 02-Jan-16
14234-3.C14234-3.Construction.2.25 Interconnecting Piping Works 64 19-Dec-15 24-Feb-16
14234-3.C14234-3.Construction.1 Site Modification Works 103 04-Sep-15 19-Dec-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
2014 2015 2016
Procurement of Commissioning Spa
Commissioning Spares Receiving
Procurement of Electrical & Instrumenta
Electrical & Instrumentation C
DPR Visit - Hydro for 2nd Lot of Ves
Punch List Close Out + Shipping Re
2nd Shipment Dispatch from UAE
2nd Shipment Receiving on S
DPR Visit - FAT for 2nd Lot of Ski
Punch List Close Out + Shipping
3rd Shipment Dispatch from UAE
3rd Shipment Receiving on
24-Feb-16, 142
Site Modification
24-Feb-16, 142
Site Constructio
09-Oct-15, 14234-3.Constructio
09-Oct-15, 14234-3.Constructio
05-Sep-15, 14234-3.Construction.2
09-Oct-15, 14234-3.Constructio
09-Oct-15, 14234-3.Constructio
03-Nov-15, 14234-3.Constru
09-Oct-15, 14234-3.Constructio
04-Nov-15, 14234-3.Constru
09-Oct-15, 14234-3.Constructio
20-Nov-15, 14234-3.Const
05-Sep-15, 14234-3.Construction.2
16-Nov-15, 14234-3.Constr
16-Nov-15, 14234-3.Constr
23-Nov-15, 14234-3.Cons
11-Dec-15, 14234-3.Con
04-Dec-15, 14234-3.Con
17-Dec-15, 14234-3.Co
04-Dec-15, 14234-3.Con
17-Dec-15, 14234-3.Co
23-Nov-15, 14234-3.Cons
28-Nov-15, 14234-3.Cons
28-Nov-15, 14234-3.Cons
02-Feb-16, 14234
04-Dec-15, 14234-3.Con
19-Dec-15, 14234-3.Co
21-Nov-15, 14234-3.Const
02-Jan-16, 14234-3.C
24-Feb-16, 142
19-Dec-15, 14234-3.Co
Egbaoma Gas Processing Plant - New Level IV Schedule-latest 16-Jul-15 15:25
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaini...
Page 4 of 7 TASK filter: All Activities
© Oracle Corporation
- 5. Activity ID Activity Name Original
Duration
Start Finish
A21520 Site Modification Works Completion 0 19-Dec-15
14234-3.C14234-3.Construction.1.1 Three Phase Separator Package 18 27-Nov-15 16-Dec-15
14234-3.C14234-3.Construction.1.14 Heat Medium Expansion Tank/Pumps Skid 26 27-Oct-15 23-Nov-15
14234-3.C14234-3.Construction.1.19 LPG Bullets Control Station Skid 26 27-Oct-15 23-Nov-15
14234-3.C14234-3.Construction.1.26 LPG Loading Arm Skid 18 27-Nov-15 16-Dec-15
14234-3.C14234-3.Construction.1.27 Distributed Control System (DCS) 35 27-Oct-15 02-Dec-15
14234-3.C14234-3.Construction.1.28 Power Generators 19 06-Nov-15 25-Nov-15
14234-3.C14234-3.Construction.1.29 LV Switchgear & MCC 15 27-Nov-15 12-Dec-15
14234-3.C14234-3.Construction.1.23 Heat Medium Heater Skid 12Mmbtu 26 27-Oct-15 23-Nov-15
14234-3.C14234-3.Construction.1.24 Flare KO Drum Skid 26 27-Oct-15 23-Nov-15
14234-3.C14234-3.Construction.1.25 Propane Loading Arm Skid 18 27-Nov-15 16-Dec-15
14234-3.C14234-3.Construction.1.15 Fuel Gas Conditioning Skid 25 27-Oct-15 21-Nov-15
14234-3.C14234-3.Construction.1.16 Instrument Air Package 26 27-Oct-15 23-Nov-15
14234-3.C14234-3.Construction.1.17 Depropanizer Reboiler Skid 26 27-Oct-15 23-Nov-15
14234-3.C14234-3.Construction.1.18 Debutanizer Reboiler Skid 26 27-Oct-15 23-Nov-15
14234-3.C14234-3.Construction.1.30 Synchronization Panel 15 07-Nov-15 23-Nov-15
14234-3.C14234-3.Construction.1.13 Deethanizer Reboiler Skid 26 27-Oct-15 23-Nov-15
14234-3.C14234-3.Construction.1.3 Inlet Compressor Package - A 26 06-Nov-15 03-Dec-15
14234-3.C14234-3.Construction.1.5 Inlet Compressor Package - C 26 06-Nov-15 03-Dec-15
14234-3.C14234-3.Construction.1.7 Regeneration Heater Skid 26 27-Oct-15 23-Nov-15
14234-3.C14234-3.Construction.1.8 Deethanizer Reflux Accumulator Skid 26 27-Oct-15 23-Nov-15
14234-3.C14234-3.Construction.1.9 Depropanizer Reflux Accumulator Skid 26 27-Oct-15 23-Nov-15
14234-3.C14234-3.Construction.1.10 Debutanizer Reflux Accumulator Skid 26 27-Oct-15 23-Nov-15
14234-3.C14234-3.Construction.1.11 Condensate Flash Tank Skid 26 27-Oct-15 23-Nov-15
14234-3.C14234-3.Construction.1.12 Cold & LP Separator Skid 26 27-Oct-15 23-Nov-15
14234-3.C14234-3.Construction.1.20 Propane Bullets Control Staion Skid 26 27-Oct-15 23-Nov-15
14234-3.C14234-3.Construction.1.21 LPG Loading Pumps Skid 18 27-Nov-15 16-Dec-15
14234-3.C14234-3.Construction.1.22 Heat Medium Heater Skid 6Mmbtu 26 27-Oct-15 23-Nov-15
14234-3.C14234-3.Construction.1.4 Inlet Compressor Package - B 26 06-Nov-15 03-Dec-15
14234-3.C14234-3.Construction.1.6 Molecular Sieve Filters Package 26 20-Oct-15 16-Nov-15
14234-3.C14234-3.Construction.1.2 Booster Compressor Package 42 06-Nov-15 19-Dec-15
14234-3.C14234-3.Construction.1.31 UPS System 67 04-Sep-15 12-Nov-15
14234-3.Co14234-3.Commissioning Precommissioning & Commissioning Wo 105 12-Nov-15 29-Feb-16
A21480 Precommissioning & Commissioning Completion 0 29-Feb-16
14234-3.C14234-3.Commissioning.1 Pre-Commissioning Works 57 12-Nov-15 09-Jan-16
A21500 Pre-Commissioning Completion 0 09-Jan-16
14234-3.C14234-3.Commissioning.1.1 Three Phase Separator Package 7 11-Dec-15 18-Dec-15
14234-3.C14234-3.Commissioning.1.2 Booster Compressor Package 7 19-Dec-15 26-Dec-15
14234-3.C14234-3.Commissioning.1.3 Inlet Compressor Package - A 7 03-Dec-15 10-Dec-15
14234-3.C14234-3.Commissioning.1.4 Inlet Compressor Package - B 7 03-Dec-15 10-Dec-15
14234-3.C14234-3.Commissioning.1.5 Inlet Compressor Package - C 7 03-Dec-15 10-Dec-15
14234-3.C14234-3.Commissioning.1.6 Molecular Sieve Filters Package 7 19-Dec-15 26-Dec-15
14234-3.C14234-3.Commissioning.1.7 Regeneration Heater Skid 7 02-Jan-16 09-Jan-16
14234-3.C14234-3.Commissioning.1.8 Deethanizer Reflux Accumulator Skid 7 02-Jan-16 09-Jan-16
14234-3.C14234-3.Commissioning.1.9 Depropanizer Reflux Accumulator Skid 7 02-Jan-16 09-Jan-16
14234-3.C14234-3.Commissioning.1.10 Debutanizer Reflux Accumulator Skid 7 02-Jan-16 09-Jan-16
14234-3.C14234-3.Commissioning.1.11 Condensate Flash Tank Skid 7 02-Jan-16 09-Jan-16
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
2014 2015 2016
Site Modification Works
16-Dec-15, 14234-3.Co
23-Nov-15, 14234-3.Cons
23-Nov-15, 14234-3.Cons
16-Dec-15, 14234-3.Co
02-Dec-15, 14234-3.Cons
25-Nov-15, 14234-3.Cons
12-Dec-15, 14234-3.Con
23-Nov-15, 14234-3.Cons
23-Nov-15, 14234-3.Cons
16-Dec-15, 14234-3.Co
21-Nov-15, 14234-3.Const
23-Nov-15, 14234-3.Cons
23-Nov-15, 14234-3.Cons
23-Nov-15, 14234-3.Cons
23-Nov-15, 14234-3.Cons
23-Nov-15, 14234-3.Cons
03-Dec-15, 14234-3.Cons
03-Dec-15, 14234-3.Cons
23-Nov-15, 14234-3.Cons
23-Nov-15, 14234-3.Cons
23-Nov-15, 14234-3.Cons
23-Nov-15, 14234-3.Cons
23-Nov-15, 14234-3.Cons
23-Nov-15, 14234-3.Cons
23-Nov-15, 14234-3.Cons
16-Dec-15, 14234-3.Co
23-Nov-15, 14234-3.Cons
03-Dec-15, 14234-3.Cons
16-Nov-15, 14234-3.Constr
19-Dec-15, 14234-3.Co
12-Nov-15, 14234-3.Constr
29-Feb-16, 142
Precommission
09-Jan-16, 14234-3.C
Pre-Commissioning C
18-Dec-15, 14234-3.Co
26-Dec-15, 14234-3.C
10-Dec-15, 14234-3.Com
10-Dec-15, 14234-3.Com
10-Dec-15, 14234-3.Com
26-Dec-15, 14234-3.C
09-Jan-16, 14234-3.C
09-Jan-16, 14234-3.C
09-Jan-16, 14234-3.C
09-Jan-16, 14234-3.C
09-Jan-16, 14234-3.C
Egbaoma Gas Processing Plant - New Level IV Schedule-latest 16-Jul-15 15:25
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaini...
Page 5 of 7 TASK filter: All Activities
© Oracle Corporation
- 6. Activity ID Activity Name Original
Duration
Start Finish
14234-3.C14234-3.Commissioning.1.12 Cold & LP Separator Skid 7 02-Jan-16 09-Jan-16
14234-3.C14234-3.Commissioning.1.13 Deethanizer Reboiler Skid 7 02-Jan-16 09-Jan-16
14234-3.C14234-3.Commissioning.1.14 Heat Medium Expansion Tank/Pumps Skid 7 02-Jan-16 09-Jan-16
14234-3.C14234-3.Commissioning.1.15 Fuel Gas Conditioning Skid 7 02-Jan-16 09-Jan-16
14234-3.C14234-3.Commissioning.1.16 Instrument Air Package 7 02-Jan-16 09-Jan-16
14234-3.C14234-3.Commissioning.1.17 Depropanizer Reboiler Skid 7 02-Jan-16 09-Jan-16
14234-3.C14234-3.Commissioning.1.18 Debutanizer Reboiler Skid 7 02-Jan-16 09-Jan-16
14234-3.C14234-3.Commissioning.1.19 LPG Bullets Control Station Skid 7 02-Jan-16 09-Jan-16
14234-3.C14234-3.Commissioning.1.20 Propane Bullets Control Staion Skid 7 02-Jan-16 09-Jan-16
14234-3.C14234-3.Commissioning.1.21 LPG Loading Pumps Skid 7 02-Jan-16 09-Jan-16
14234-3.C14234-3.Commissioning.1.22 Heat Medium Heater Skid 6Mmbtu 7 02-Jan-16 09-Jan-16
14234-3.C14234-3.Commissioning.1.23 Heat Medium Heater Skid 12Mmbtu 7 02-Jan-16 09-Jan-16
14234-3.C14234-3.Commissioning.1.24 Flare KO Drum Skid 7 02-Jan-16 09-Jan-16
14234-3.C14234-3.Commissioning.1.25 Propane Loading Arm Skid 7 02-Jan-16 09-Jan-16
14234-3.C14234-3.Commissioning.1.26 LPG Loading Arm Skid 7 02-Jan-16 09-Jan-16
14234-3.C14234-3.Commissioning.1.27 Gas Metering Skid 7 02-Jan-16 09-Jan-16
14234-3.C14234-3.Commissioning.1.28 Water Degassing Boot & CPI Separator Skid 7 02-Jan-16 09-Jan-16
14234-3.C14234-3.Commissioning.1.29 Condensate Stabilization Skid 7 02-Jan-16 09-Jan-16
14234-3.C14234-3.Commissioning.1.30 Condensate Transfer Pump Skid 7 02-Jan-16 09-Jan-16
14234-3.C14234-3.Commissioning.1.31 Gas/Gas Exchanger (E-300A/B) Skid 7 02-Jan-16 09-Jan-16
14234-3.C14234-3.Commissioning.1.36 Distributed Control System (DCS) 7 19-Dec-15 26-Dec-15
14234-3.C14234-3.Commissioning.1.37 Synchronization Panel 7 23-Nov-15 30-Nov-15
14234-3.C14234-3.Commissioning.1.32 Gas Liquid Exchanger (E-302(A/B Skid 7 02-Jan-16 09-Jan-16
14234-3.C14234-3.Commissioning.1.33 Regeneration Gas Cooler (E-303) Skid 7 02-Jan-16 09-Jan-16
14234-3.C14234-3.Commissioning.1.34 F&G System 7 02-Jan-16 09-Jan-16
14234-3.C14234-3.Commissioning.1.35 ESD/FGS System 7 02-Jan-16 09-Jan-16
14234-3.C14234-3.Commissioning.1.38 LV Switchgear & MCC 7 12-Dec-15 21-Dec-15
14234-3.C14234-3.Commissioning.1.39 UPS System 7 12-Nov-15 19-Nov-15
14234-3.C14234-3.Commissioning.1.40 Power Generators 7 26-Nov-15 03-Dec-15
14234-3.C14234-3.Commissioning.2 Commissioning Works 48 09-Jan-16 29-Feb-16
A21490 Commissioning Completion 0 29-Feb-16
14234-3.C14234-3.Commissioning.2.1 Three Phase Separator Package 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.2 Booster Compressor Package 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.3 Inlet Compressor Package - A 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.4 Inlet Compressor Package - B 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.5 Inlet Compressor Package - C 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.6 Molecular Sieve Filters Package 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.7 Regeneration Heater Skid 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.8 Deethanizer Reflux Accumulator Skid 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.9 Depropanizer Reflux Accumulator Skid 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.10 Debutanizer Reflux Accumulator Skid 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.11 Condensate Flash Tank Skid 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.12 Cold & LP Separator Skid 5 09-Jan-16 15-Jan-16
14234-3.C14234-3.Commissioning.2.13 Deethanizer Reboiler Skid 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.14 Heat Medium Expansion Tank/Pumps Skid 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.15 Fuel Gas Conditioning Skid 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.16 Instrument Air Package 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.17 Depropanizer Reboiler Skid 5 24-Feb-16 29-Feb-16
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
2014 2015 2016
09-Jan-16, 14234-3.C
09-Jan-16, 14234-3.C
09-Jan-16, 14234-3.C
09-Jan-16, 14234-3.C
09-Jan-16, 14234-3.C
09-Jan-16, 14234-3.C
09-Jan-16, 14234-3.C
09-Jan-16, 14234-3.C
09-Jan-16, 14234-3.C
09-Jan-16, 14234-3.C
09-Jan-16, 14234-3.C
09-Jan-16, 14234-3.C
09-Jan-16, 14234-3.C
09-Jan-16, 14234-3.C
09-Jan-16, 14234-3.C
09-Jan-16, 14234-3.C
09-Jan-16, 14234-3.C
09-Jan-16, 14234-3.C
09-Jan-16, 14234-3.C
09-Jan-16, 14234-3.C
26-Dec-15, 14234-3.C
30-Nov-15, 14234-3.Com
09-Jan-16, 14234-3.C
09-Jan-16, 14234-3.C
09-Jan-16, 14234-3.C
09-Jan-16, 14234-3.C
21-Dec-15, 14234-3.Co
19-Nov-15, 14234-3.Comm
03-Dec-15, 14234-3.Com
29-Feb-16, 142
Commissioning
29-Feb-16, 142
29-Feb-16, 142
29-Feb-16, 142
29-Feb-16, 142
29-Feb-16, 142
29-Feb-16, 142
29-Feb-16, 142
29-Feb-16, 142
29-Feb-16, 142
29-Feb-16, 142
29-Feb-16, 142
15-Jan-16, 14234-3
29-Feb-16, 142
29-Feb-16, 142
29-Feb-16, 142
29-Feb-16, 142
29-Feb-16, 142
Egbaoma Gas Processing Plant - New Level IV Schedule-latest 16-Jul-15 15:25
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaini...
Page 6 of 7 TASK filter: All Activities
© Oracle Corporation
- 7. Activity ID Activity Name Original
Duration
Start Finish
14234-3.C14234-3.Commissioning.2.18 Debutanizer Reboiler Skid 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.19 LPG Bullets Control Station Skid 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.20 Propane Bullets Control Staion Skid 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.21 LPG Loading Pumps Skid 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.22 Heat Medium Heater Skid 6Mmbtu 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.23 Heat Medium Heater Skid 12Mmbtu 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.24 Flare KO Drum Skid 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.25 Propane Loading Arm Skid 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.26 LPG Loading Arm Skid 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.27 Gas Metering Skid 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.28 Water Degassing Boot & CPI Separator Skid 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.29 Condensate Stabilization Skid 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.30 Condensate Transfer Pump Skid 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.31 Gas/Gas Exchanger (E-300A/B) Skid 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.32 Gas Liquid Exchanger (E-302(A/B Skid 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.33 Regeneration Gas Cooler (E-303) Skid 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.34 F&G System 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.35 ESD/FGS System 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.36 Distributed Control System (DCS) 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.37 Synchronization Panel 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.38 LV Switchgear & MCC 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.39 Power Generators 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.40 UPS System 5 24-Feb-16 29-Feb-16
14234-3.Pe14234-3.Perf & Rel Test Performance and Reliability Test 33 29-Feb-16 04-Apr-16
14234-3.Pe14234-3.Perf & Rel Test.Perf Test Performance Test 3 29-Feb-16 03-Mar-16
A24210 Performance Test 3 29-Feb-16 03-Mar-16
14234-3.Pe14234-3.Perf & Rel Test.Rel. Test Reliability Test 30 03-Mar-16 04-Apr-16
A24220 Reliability Test 30 03-Mar-16 04-Apr-16
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
2014 2015 2016
29-Feb-16, 142
29-Feb-16, 142
29-Feb-16, 142
29-Feb-16, 142
29-Feb-16, 142
29-Feb-16, 142
29-Feb-16, 142
29-Feb-16, 142
29-Feb-16, 142
29-Feb-16, 142
29-Feb-16, 142
29-Feb-16, 142
29-Feb-16, 142
29-Feb-16, 142
29-Feb-16, 142
29-Feb-16, 142
29-Feb-16, 142
29-Feb-16, 142
29-Feb-16, 142
29-Feb-16, 142
29-Feb-16, 142
29-Feb-16, 142
29-Feb-16, 142
04-Apr-16,
03-Mar-16, 142
Performance T
04-Apr-16,
Reliability T
Egbaoma Gas Processing Plant - New Level IV Schedule-latest 16-Jul-15 15:25
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaini...
Page 7 of 7 TASK filter: All Activities