1. Project Management
Extraction/Output
Action Type
Plant Layout/
Piping
Power & Controls
HVAC/Fire Protection
Plant Engineering
MTO/Stress/Pipe Supports
Mechanical/
Vessels
Architectural
Client
Construction
Commissioning/
Validation
Project Controls
Procurement
Project CIE/Design
Coordination
Detail Design
Process
Civil/Structural
Project Design Execution Process
Create Design Areas and Model Files for all Disciplines
Set -up Interference Management Program
Set-up Design Review by Systems and areas
Update Reference Database
Develop 3D Project Execution Plan to 3DProcedure
Plot Plans and GA’s for Review by
Project Team, Construction and Client
Plot Plan for Inter-Discipline
Design And Coordination
Concrete &
Steel MTO
Wall & Floor Openings
Offline Instrument Location Plan
HVAC Plans and Sections
Foundation Piling
Building / Structures Plan
Steel Plans and Elevations
Approved Plot Plans generated AFD &
Overall Plot Plan Issue AFC W/Holds
Overall Plot Plan for review by Project Team, Construction, and Client
Equipment GA’s
Approved for Design
INTERFERENCE CHECKING RESOLUTION BY DISCIPLINE
Set-up Defaults for Iso Extraction
Input New Specialty Items into Specifications
Extract Isometrics for Checking
Incorporate Vessel Orientation Comments Area Piping Input:
Lrg Bore & Small Bore Critical Lines
LB & SB Non-Critical Process Lines
Vessel and Equipment Trim
Annotate and Plot Equipment GA’s
Underground System Design
Preliminary stress
Review for LB and
SB Piping Input
Required Data/Details
Input Foundations, Bldg / Structural Steel,
Rack Steel, Stairs
and Ladders approved for Design
Start Instrument Location Plans &
Instrument Installation Details
Up-date equipment to AFD Vendor Info
Update Models from RDB
Interface with other Design Areas
Input Lighting Fixtures and Junction Boxes
Input Vessel Clips for Ladders
Input Ladders and latforms
Input Partition Heights
Add Louvres/ Locate Major
Wall Openings
Interior Details
Resolve all Interferences as Required
Input Preliminary Cable Tray Requirements
and Electrical Equipment Requirements
Mechanical Drawing Information
Dimensions and Information
Detail Exterior Envelope
Exterior Details
Update Equipment based on AFD Drawings
Input Offline Instrument Dimensional Data to Spec
Develop Main Duct Routing
Define Fire Deluge
Routing and Envelope
Update Equipment Based on Vendor Data
Input Duct and In-line Equipment
Certified Vendor Data
Incorporate Review
Comments
CONTINUED MAINTENANCE OF ARCHITECTURAL BACKROUND
Formal Review
Approve at 75%
Model Completion
(TIMING BASED ON JOB REQUIREMENTS)
Formal Constructability Review
Formal Review
Approve at 25%
Model Completion
Develop Vendor Matrix Drawing
Intersquad Vendor Drawings
Vendor Document Matrix
Vendor Document Status
Report
Foundation Drawings
Steel Drawings
Site Plans
Piling Plans
Paving / Coating Plans
Site Plans
Equipment
Foundation Plan
Misc Steel for Openings
AG Drainage System Design
AG FW Main Riser Header Installation
Establish Variation Procedures
Set-up Project Management System
Issue Project Controls Plan
Establish Trending DocumentRe Cast +/_10% In to Cost Management System
Establish Integrated Eng / Const Schedule
Project Closeout Documentation
Interactive Design / Engineering Audit
Issue Audit Report
Define Turnover
Sequence
Turnover Package
Developement
Develop Commissioning
Master Plan
Finalize Validation
Master Plan
cGMP Review
Develop Protocols
Develop SOP’s
Plot Plan
Equipment arrangements
Piping GA’s
Tie-in List
Clash check free Model
Final P&ID’s
Equipment List
Line List
“X” Item List
Equip & Inst. Specs
Electrical Single Lines
Area Classification Dwgs
Cable Schedule
Cable Routing Dwg
Sub Station Layout Dwgs
Lighting & Power Plans
Grounding Plans
HVAC Layouts
HVAC Equip List
Fire Protection drawings
Piping Specifications
Pipe support Details
Piping Speciality Details
Equipment Vendor
Drawings
Plans, elevations, & sections
Door and Room Schedules
Protocols
SOP’s
Final VMP
Final Commissioning Plan
Turn-over Packages
Deliverables
Determine all Penetrations
Ladders and Platforms
Platforms and
Pipe supports
Formal Review
Approve at 50%
Model Completion
Formal Review
Approve at 90%
Model Completion
Interference Checked
Model to prepare for
Final Design
Issue Inst. Specs
Issue Equip Specs
CP-3121 CP-3121
Update IFD P&ID’s
Ref. Doc.
REV 0