ADIB Time Schedule V4.0
- 1. Activity Name Original
Duration
Start Finish
Preparation and processing of the twelvth floor of th 76 31-Mar-15 14-Jun-15
General 76 31-Mar-15 14-Jun-15
Dates (Milestones) 76 31-Mar-15 14-Jun-15
Project Start 0 31-Mar-15
Establishing ELEC., Plumbing and HVAC 0 24-Apr-15
50% Of Work Done 0 16-May-15
80% Of Work Done (Painting Finished) 0 04-Jun-15
Project End 0 14-Jun-15
General Works 76 31-Mar-15 14-Jun-15
Site Mobilization 3 31-Mar-15 02-Apr-15
Demolish & Dismantle Works 3 31-Mar-15 02-Apr-15
Licenses and Permissions 7 31-Mar-15 06-Apr-15
Delivering Project 1 14-Jun-15 14-Jun-15
Surveying Works 1 03-Apr-15 03-Apr-15
Surveying Works 1 03-Apr-15 03-Apr-15
Technical Office Works 5 04-Apr-15 09-Apr-15
Arch WSD 5 04-Apr-15 09-Apr-15
Prepare & Submit Arch WSD 5 04-Apr-15 08-Apr-15
Material Submittal 5 04-Apr-15 08-Apr-15
Arch WSD approval 0 09-Apr-15 09-Apr-15
Material Approval 0 09-Apr-15 09-Apr-15
Elec. WSD 5 04-Apr-15 09-Apr-15
Prepare & Submit Elec. WSD 5 04-Apr-15 08-Apr-15
Material Submittal 5 04-Apr-15 08-Apr-15
Electrical WSD approval 0 09-Apr-15 09-Apr-15
Material Approval 0 09-Apr-15 09-Apr-15
HVAC WSD 5 04-Apr-15 09-Apr-15
Prepare & Submit HVAC WSD 5 04-Apr-15 08-Apr-15
Material Submittal 5 04-Apr-15 08-Apr-15
HVAC WSD approval 0 09-Apr-15 09-Apr-15
Material Approval 0 09-Apr-15 09-Apr-15
Plum. WSD 5 04-Apr-15 09-Apr-15
Prepare & Submit Plumping WSD 5 04-Apr-15 08-Apr-15
Material Submittal 5 04-Apr-15 08-Apr-15
Plumbing WSD approval 0 09-Apr-15 09-Apr-15
Material Approval 0 09-Apr-15 09-Apr-15
Architectural Work 66 09-Apr-15 13-Jun-15
Masonary Work 3 09-Apr-15 11-Apr-15
Kitchen & Bathrooms Insulation 1 12-Apr-15 12-Apr-15
Plastering 3 27-Apr-15 29-Apr-15
Files Room Strengthening 4 30-Apr-15 03-May-15
Floor Work 43 30-Apr-15 11-Jun-15
Mosaic Tiles Flooring Installation 5 30-Apr-15 04-May-15
28 04 11 18 25 02 09 16 23 30 06 13 20
April 2015 May 2015 June 2015
14-Jun-15
14-Jun-15
14-Jun-15
Project Start
Establishing ELEC., Plumbing and HVAC
50% Of Work Done
80% Of Work Done (Painti
Project E
14-Jun-15
Site Mobilization
Demolish & Dismantle Works
Licenses and Permissions
Deliverin
03-Apr-15, Surveying Works
Surveying Works
09-Apr-15, Technical Office Works
09-Apr-15, Arch WSD
Prepare & Submit Arch WSD
Material Submittal
Arch WSD approval
Material Approval
09-Apr-15, Elec. WSD
Prepare & Submit Elec. WSD
Material Submittal
Electrical WSD approval
Material Approval
09-Apr-15, HVAC WSD
Prepare & Submit HVAC WSD
Material Submittal
HVAC WSD approval
Material Approval
09-Apr-15, Plum. WSD
Prepare & Submit Plumping WSD
Material Submittal
Plumbing WSD approval
Material Approval
13-Jun-15,
Masonary Work
Kitchen & Bathrooms Insulation
Plastering
Files Room Strengthening
11-Jun-15, Flo
Mosaic Tiles Flooring Installation
Preparation and processing of the
twelvth floor of the headquarters in
Garden City
Master Schedule
ADIB Time Schedule V4 03-APR-2015 Page 1 of 3 Project Management Department
Misr Contraco Group
- 2. Activity Name Original
Duration
Start Finish
Ceramic Flooring Installation 5 30-Apr-15 04-May-15
Marble Flooring Installation 5 30-Apr-15 04-May-15
HDF Flooring Installation 4 06-Jun-15 09-Jun-15
HPL Flooring Installation 4 06-Jun-15 09-Jun-15
Finishing Marble Flooring 4 06-Jun-15 09-Jun-15
Vinyl Flooring 4 06-Jun-15 09-Jun-15
Carpet Installation 2 10-Jun-15 11-Jun-15
Wall Work 26 30-Apr-15 25-May-15
Marble Walls Installation 4 30-Apr-15 03-May-15
MDF Walls Installation 4 30-Apr-15 03-May-15
Ceramic Cladding Installation 4 30-Apr-15 03-May-15
Gypsum Galvanized Studs 4 05-May-15 08-May-15
Gypsum Cladding Installation 3 09-May-15 11-May-15
Skirting Installation 2 24-May-15 25-May-15
Partitions 32 09-May-15 09-Jun-15
Gypsum Partitions Installation 4 09-May-15 12-May-15
Bathroom Partitions Installation 4 09-May-15 12-May-15
Wooden Partitions Installation 3 24-May-15 26-May-15
Glass Partitions Installation (Securit) 3 31-May-15 02-Jun-15
HPL Bathroom Partitions Installation 3 07-Jun-15 09-Jun-15
Doors & Windows 6 24-May-15 29-May-15
Metal Doors Installation 3 24-May-15 26-May-15
Wooden Doors Installation 3 24-May-15 26-May-15
Wooden Frames Installation 2 25-May-15 26-May-15
Wooden Crossings Installation 2 25-May-15 26-May-15
Alumital Windows Installation 2 28-May-15 29-May-15
Ceiling Work 25 12-May-15 05-Jun-15
Galvanized Steel Sub-structure for Gypsum Board 5 12-May-15 16-May-15
Gypsum Board Installation 4 17-May-15 20-May-15
Ceiling Tiles Installation 4 17-May-15 20-May-15
Finishing Plastic Painting for Ceiling 4 02-Jun-15 05-Jun-15
Stairs Work 39 30-Apr-15 07-Jun-15
Stairs Marble Installation 4 30-Apr-15 03-May-15
Stairs Marble Finishing 1 04-May-15 04-May-15
Handrail Installation 2 06-Jun-15 07-Jun-15
Painting 24 21-May-15 13-Jun-15
Establishing Painting 7 21-May-15 27-May-15
Finishing Walls Painting 3 02-Jun-15 04-Jun-15
Accessories & Wallpaper Works 2 12-Jun-15 13-Jun-15
External Work 6 09-May-15 14-May-15
Rolling Shutter 6 09-May-15 14-May-15
Rolling Shutter Installation 5 09-May-15 13-May-15
Rolling Shutter Testing 1 14-May-15 14-May-15
28 04 11 18 25 02 09 16 23 30 06 13 20
April 2015 May 2015 June 2015
Ceramic Flooring Installation
Marble Flooring Installation
HDF Flooring Inst
HPL Flooring Inst
Finishing Marble
Vinyl Flooring
Carpet Installa
25-May-15, Wall Work
Marble Walls Installation
MDF Walls Installation
Ceramic Cladding Installation
Gypsum Galvanized Studs
Gypsum Cladding Installation
Skirting Installation
09-Jun-15, Partitio
Gypsum Partitions Installation
Bathroom Partitions Installation
Wooden Partitions Installation
Glass Partitions Installation (
HPL Bathroom Pa
29-May-15, Doors & Windows
Metal Doors Installation
Wooden Doors Installation
Wooden Frames Installation
Wooden Crossings Installation
Alumital Windows Installation
05-Jun-15, Ceiling Work
Galvanized Steel Sub-structure for Gypsum Board
Gypsum Board Installation
Ceiling Tiles Installation
Finishing Plastic Paintin
07-Jun-15, Stairs Wor
Stairs Marble Installation
Stairs Marble Finishing
Handrail Installation
13-Jun-15,
Establishing Painting
Finishing Walls Painting
Accessorie
14-May-15, External Work
14-May-15, Rolling Shutter
Rolling Shutter Installation
Rolling Shutter Testing
Preparation and processing of the
twelvth floor of the headquarters in
Garden City
Master Schedule
ADIB Time Schedule V4 03-APR-2015 Page 2 of 3 Project Management Department
Misr Contraco Group
- 3. Activity Name Original
Duration
Start Finish
MEP 53 13-Apr-15 04-Jun-15
Plumping 50 13-Apr-15 01-Jun-15
Fixing Drainage & Feeding pipes 2 13-Apr-15 14-Apr-15
Testing Pipes 1 15-Apr-15 15-Apr-15
Sanitary Fixtures Installation 1 31-May-15 31-May-15
Testing & Commisioning 1 01-Jun-15 01-Jun-15
Electrical Works 53 13-Apr-15 04-Jun-15
Main Power Feeder 2 13-Apr-15 14-Apr-15
1st. Fix Installation (Pipes Installation) 12 15-Apr-15 26-Apr-15
2nd Fix Installation (Wire Pulling) 12 15-Apr-15 26-Apr-15
Cable Tray Installation 5 21-Apr-15 25-Apr-15
Distribution Pannels Installation 3 31-May-15 02-Jun-15
Sockets Installation (including data & telephone) 1 31-May-15 31-May-15
Lighting Fixture Installation 2 02-Jun-15 03-Jun-15
Testing & Commisioning 1 04-Jun-15 04-Jun-15
HVAC 52 13-Apr-15 03-Jun-15
Indoor Units 2 13-Apr-15 14-Apr-15
Duct Work & Insulation 2 15-Apr-15 16-Apr-15
Freon Installation 2 17-Apr-15 18-Apr-15
Drainage System 2 19-Apr-15 20-Apr-15
Fresh Air & Exhaust Air Fans Installation 2 21-Apr-15 22-Apr-15
Outdoor Units Connection 2 23-Apr-15 24-Apr-15
Grills Installation 2 31-May-15 01-Jun-15
Thermostate Installation 1 02-Jun-15 02-Jun-15
Testing & Commisioning 1 03-Jun-15 03-Jun-15
28 04 11 18 25 02 09 16 23 30 06 13 20
April 2015 May 2015 June 2015
04-Jun-15, MEP
01-Jun-15, Plumping
Fixing Drainage & Feeding pipes
Testing Pipes
Sanitary Fixtures Installation
Testing & Commisioning
04-Jun-15, Electrical Work
Main Power Feeder
1st. Fix Installation (Pipes Installation)
2nd Fix Installation (Wire Pulling)
Cable Tray Installation
Distribution Pannels Installat
Sockets Installation (including d
Lighting Fixture Installation
Testing & Commisioning
03-Jun-15, HVAC
Indoor Units
Duct Work & Insulation
Freon Installation
Drainage System
Fresh Air & Exhaust Air Fans Installation
Outdoor Units Connection
Grills Installation
Thermostate Installation
Testing & Commisioning
Preparation and processing of the
twelvth floor of the headquarters in
Garden City
Master Schedule
ADIB Time Schedule V4 03-APR-2015 Page 3 of 3 Project Management Department
Misr Contraco Group