Activity Name Original
Duration
Start Finish
Preparation and processing of the twelvth floor of th 76 31-Mar-15 14-Jun-15
General 76 31-Mar-15 14-Jun-15
Dates (Milestones) 76 31-Mar-15 14-Jun-15
Project Start 0 31-Mar-15
Establishing ELEC., Plumbing and HVAC 0 24-Apr-15
50% Of Work Done 0 16-May-15
80% Of Work Done (Painting Finished) 0 04-Jun-15
Project End 0 14-Jun-15
General Works 76 31-Mar-15 14-Jun-15
Site Mobilization 3 31-Mar-15 02-Apr-15
Demolish & Dismantle Works 3 31-Mar-15 02-Apr-15
Licenses and Permissions 7 31-Mar-15 06-Apr-15
Delivering Project 1 14-Jun-15 14-Jun-15
Surveying Works 1 03-Apr-15 03-Apr-15
Surveying Works 1 03-Apr-15 03-Apr-15
Technical Office Works 5 04-Apr-15 09-Apr-15
Arch WSD 5 04-Apr-15 09-Apr-15
Prepare & Submit Arch WSD 5 04-Apr-15 08-Apr-15
Material Submittal 5 04-Apr-15 08-Apr-15
Arch WSD approval 0 09-Apr-15 09-Apr-15
Material Approval 0 09-Apr-15 09-Apr-15
Elec. WSD 5 04-Apr-15 09-Apr-15
Prepare & Submit Elec. WSD 5 04-Apr-15 08-Apr-15
Material Submittal 5 04-Apr-15 08-Apr-15
Electrical WSD approval 0 09-Apr-15 09-Apr-15
Material Approval 0 09-Apr-15 09-Apr-15
HVAC WSD 5 04-Apr-15 09-Apr-15
Prepare & Submit HVAC WSD 5 04-Apr-15 08-Apr-15
Material Submittal 5 04-Apr-15 08-Apr-15
HVAC WSD approval 0 09-Apr-15 09-Apr-15
Material Approval 0 09-Apr-15 09-Apr-15
Plum. WSD 5 04-Apr-15 09-Apr-15
Prepare & Submit Plumping WSD 5 04-Apr-15 08-Apr-15
Material Submittal 5 04-Apr-15 08-Apr-15
Plumbing WSD approval 0 09-Apr-15 09-Apr-15
Material Approval 0 09-Apr-15 09-Apr-15
Architectural Work 66 09-Apr-15 13-Jun-15
Masonary Work 3 09-Apr-15 11-Apr-15
Kitchen & Bathrooms Insulation 1 12-Apr-15 12-Apr-15
Plastering 3 27-Apr-15 29-Apr-15
Files Room Strengthening 4 30-Apr-15 03-May-15
Floor Work 43 30-Apr-15 11-Jun-15
Mosaic Tiles Flooring Installation 5 30-Apr-15 04-May-15
28 04 11 18 25 02 09 16 23 30 06 13 20
April 2015 May 2015 June 2015
14-Jun-15
14-Jun-15
14-Jun-15
Project Start
Establishing ELEC., Plumbing and HVAC
50% Of Work Done
80% Of Work Done (Painti
Project E
14-Jun-15
Site Mobilization
Demolish & Dismantle Works
Licenses and Permissions
Deliverin
03-Apr-15, Surveying Works
Surveying Works
09-Apr-15, Technical Office Works
09-Apr-15, Arch WSD
Prepare & Submit Arch WSD
Material Submittal
Arch WSD approval
Material Approval
09-Apr-15, Elec. WSD
Prepare & Submit Elec. WSD
Material Submittal
Electrical WSD approval
Material Approval
09-Apr-15, HVAC WSD
Prepare & Submit HVAC WSD
Material Submittal
HVAC WSD approval
Material Approval
09-Apr-15, Plum. WSD
Prepare & Submit Plumping WSD
Material Submittal
Plumbing WSD approval
Material Approval
13-Jun-15,
Masonary Work
Kitchen & Bathrooms Insulation
Plastering
Files Room Strengthening
11-Jun-15, Flo
Mosaic Tiles Flooring Installation
Preparation and processing of the
twelvth floor of the headquarters in
Garden City
Master Schedule
ADIB Time Schedule V4 03-APR-2015 Page 1 of 3 Project Management Department
Misr Contraco Group
Activity Name Original
Duration
Start Finish
Ceramic Flooring Installation 5 30-Apr-15 04-May-15
Marble Flooring Installation 5 30-Apr-15 04-May-15
HDF Flooring Installation 4 06-Jun-15 09-Jun-15
HPL Flooring Installation 4 06-Jun-15 09-Jun-15
Finishing Marble Flooring 4 06-Jun-15 09-Jun-15
Vinyl Flooring 4 06-Jun-15 09-Jun-15
Carpet Installation 2 10-Jun-15 11-Jun-15
Wall Work 26 30-Apr-15 25-May-15
Marble Walls Installation 4 30-Apr-15 03-May-15
MDF Walls Installation 4 30-Apr-15 03-May-15
Ceramic Cladding Installation 4 30-Apr-15 03-May-15
Gypsum Galvanized Studs 4 05-May-15 08-May-15
Gypsum Cladding Installation 3 09-May-15 11-May-15
Skirting Installation 2 24-May-15 25-May-15
Partitions 32 09-May-15 09-Jun-15
Gypsum Partitions Installation 4 09-May-15 12-May-15
Bathroom Partitions Installation 4 09-May-15 12-May-15
Wooden Partitions Installation 3 24-May-15 26-May-15
Glass Partitions Installation (Securit) 3 31-May-15 02-Jun-15
HPL Bathroom Partitions Installation 3 07-Jun-15 09-Jun-15
Doors & Windows 6 24-May-15 29-May-15
Metal Doors Installation 3 24-May-15 26-May-15
Wooden Doors Installation 3 24-May-15 26-May-15
Wooden Frames Installation 2 25-May-15 26-May-15
Wooden Crossings Installation 2 25-May-15 26-May-15
Alumital Windows Installation 2 28-May-15 29-May-15
Ceiling Work 25 12-May-15 05-Jun-15
Galvanized Steel Sub-structure for Gypsum Board 5 12-May-15 16-May-15
Gypsum Board Installation 4 17-May-15 20-May-15
Ceiling Tiles Installation 4 17-May-15 20-May-15
Finishing Plastic Painting for Ceiling 4 02-Jun-15 05-Jun-15
Stairs Work 39 30-Apr-15 07-Jun-15
Stairs Marble Installation 4 30-Apr-15 03-May-15
Stairs Marble Finishing 1 04-May-15 04-May-15
Handrail Installation 2 06-Jun-15 07-Jun-15
Painting 24 21-May-15 13-Jun-15
Establishing Painting 7 21-May-15 27-May-15
Finishing Walls Painting 3 02-Jun-15 04-Jun-15
Accessories & Wallpaper Works 2 12-Jun-15 13-Jun-15
External Work 6 09-May-15 14-May-15
Rolling Shutter 6 09-May-15 14-May-15
Rolling Shutter Installation 5 09-May-15 13-May-15
Rolling Shutter Testing 1 14-May-15 14-May-15
28 04 11 18 25 02 09 16 23 30 06 13 20
April 2015 May 2015 June 2015
Ceramic Flooring Installation
Marble Flooring Installation
HDF Flooring Inst
HPL Flooring Inst
Finishing Marble
Vinyl Flooring
Carpet Installa
25-May-15, Wall Work
Marble Walls Installation
MDF Walls Installation
Ceramic Cladding Installation
Gypsum Galvanized Studs
Gypsum Cladding Installation
Skirting Installation
09-Jun-15, Partitio
Gypsum Partitions Installation
Bathroom Partitions Installation
Wooden Partitions Installation
Glass Partitions Installation (
HPL Bathroom Pa
29-May-15, Doors & Windows
Metal Doors Installation
Wooden Doors Installation
Wooden Frames Installation
Wooden Crossings Installation
Alumital Windows Installation
05-Jun-15, Ceiling Work
Galvanized Steel Sub-structure for Gypsum Board
Gypsum Board Installation
Ceiling Tiles Installation
Finishing Plastic Paintin
07-Jun-15, Stairs Wor
Stairs Marble Installation
Stairs Marble Finishing
Handrail Installation
13-Jun-15,
Establishing Painting
Finishing Walls Painting
Accessorie
14-May-15, External Work
14-May-15, Rolling Shutter
Rolling Shutter Installation
Rolling Shutter Testing
Preparation and processing of the
twelvth floor of the headquarters in
Garden City
Master Schedule
ADIB Time Schedule V4 03-APR-2015 Page 2 of 3 Project Management Department
Misr Contraco Group
Activity Name Original
Duration
Start Finish
MEP 53 13-Apr-15 04-Jun-15
Plumping 50 13-Apr-15 01-Jun-15
Fixing Drainage & Feeding pipes 2 13-Apr-15 14-Apr-15
Testing Pipes 1 15-Apr-15 15-Apr-15
Sanitary Fixtures Installation 1 31-May-15 31-May-15
Testing & Commisioning 1 01-Jun-15 01-Jun-15
Electrical Works 53 13-Apr-15 04-Jun-15
Main Power Feeder 2 13-Apr-15 14-Apr-15
1st. Fix Installation (Pipes Installation) 12 15-Apr-15 26-Apr-15
2nd Fix Installation (Wire Pulling) 12 15-Apr-15 26-Apr-15
Cable Tray Installation 5 21-Apr-15 25-Apr-15
Distribution Pannels Installation 3 31-May-15 02-Jun-15
Sockets Installation (including data & telephone) 1 31-May-15 31-May-15
Lighting Fixture Installation 2 02-Jun-15 03-Jun-15
Testing & Commisioning 1 04-Jun-15 04-Jun-15
HVAC 52 13-Apr-15 03-Jun-15
Indoor Units 2 13-Apr-15 14-Apr-15
Duct Work & Insulation 2 15-Apr-15 16-Apr-15
Freon Installation 2 17-Apr-15 18-Apr-15
Drainage System 2 19-Apr-15 20-Apr-15
Fresh Air & Exhaust Air Fans Installation 2 21-Apr-15 22-Apr-15
Outdoor Units Connection 2 23-Apr-15 24-Apr-15
Grills Installation 2 31-May-15 01-Jun-15
Thermostate Installation 1 02-Jun-15 02-Jun-15
Testing & Commisioning 1 03-Jun-15 03-Jun-15
28 04 11 18 25 02 09 16 23 30 06 13 20
April 2015 May 2015 June 2015
04-Jun-15, MEP
01-Jun-15, Plumping
Fixing Drainage & Feeding pipes
Testing Pipes
Sanitary Fixtures Installation
Testing & Commisioning
04-Jun-15, Electrical Work
Main Power Feeder
1st. Fix Installation (Pipes Installation)
2nd Fix Installation (Wire Pulling)
Cable Tray Installation
Distribution Pannels Installat
Sockets Installation (including d
Lighting Fixture Installation
Testing & Commisioning
03-Jun-15, HVAC
Indoor Units
Duct Work & Insulation
Freon Installation
Drainage System
Fresh Air & Exhaust Air Fans Installation
Outdoor Units Connection
Grills Installation
Thermostate Installation
Testing & Commisioning
Preparation and processing of the
twelvth floor of the headquarters in
Garden City
Master Schedule
ADIB Time Schedule V4 03-APR-2015 Page 3 of 3 Project Management Department
Misr Contraco Group

More Related Content

Similar to ADIB Time Schedule V4.0

Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016Ahmed Mehrem
 
WC-14-NXE-007-00-Sch Rev 0.0 (29 May,2015)
WC-14-NXE-007-00-Sch Rev 0.0  (29 May,2015)  WC-14-NXE-007-00-Sch Rev 0.0  (29 May,2015)
WC-14-NXE-007-00-Sch Rev 0.0 (29 May,2015) Ali Yousef
 
Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdfZewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdfAhmed Mehrem
 
Single Family Gantt Chart-John Mueller
Single Family Gantt Chart-John MuellerSingle Family Gantt Chart-John Mueller
Single Family Gantt Chart-John MuellerJohn Mueller
 
Presentation
PresentationPresentation
PresentationKrm Chari
 
Final Majarrah rev 0
Final Majarrah rev 0Final Majarrah rev 0
Final Majarrah rev 0Ahmed Mehrem
 
ABC_3rd Progress Mtg Briefing_050115_draft.ppt
ABC_3rd Progress Mtg Briefing_050115_draft.pptABC_3rd Progress Mtg Briefing_050115_draft.ppt
ABC_3rd Progress Mtg Briefing_050115_draft.pptKingHaroldDeLeon
 
Naperville Woman’s Club Landmark Remodeling Project
Naperville Woman’s Club Landmark Remodeling ProjectNaperville Woman’s Club Landmark Remodeling Project
Naperville Woman’s Club Landmark Remodeling ProjectGeorgiann Baldino
 
Jadwal Pelaksanaan PPI.pdf
Jadwal Pelaksanaan PPI.pdfJadwal Pelaksanaan PPI.pdf
Jadwal Pelaksanaan PPI.pdfGaluhWulandari10
 
Sample Project Monitoring-EVM Analysis
Sample Project Monitoring-EVM Analysis Sample Project Monitoring-EVM Analysis
Sample Project Monitoring-EVM Analysis Ayon Pal
 
Project Monitoring with EVM Analysis
Project Monitoring with EVM Analysis Project Monitoring with EVM Analysis
Project Monitoring with EVM Analysis ayonpal
 
Cedarvale & Forest Hill Construction Liaison Committee Meeting - Jan 29, 2020
Cedarvale & Forest Hill Construction Liaison Committee Meeting - Jan 29, 2020Cedarvale & Forest Hill Construction Liaison Committee Meeting - Jan 29, 2020
Cedarvale & Forest Hill Construction Liaison Committee Meeting - Jan 29, 2020Crosstown TO
 
Spindrift-cinematique-traduit
Spindrift-cinematique-traduitSpindrift-cinematique-traduit
Spindrift-cinematique-traduitEmilie Guichard
 
Cedarvale & Forest Hill Construction Update - May 27, 2020
Cedarvale & Forest Hill Construction Update - May 27, 2020Cedarvale & Forest Hill Construction Update - May 27, 2020
Cedarvale & Forest Hill Construction Update - May 27, 2020Crosstown TO
 
Cedarvale & Forest Hill Construction Liaison Committee Meeting - Mar 25, 2020
Cedarvale & Forest Hill Construction Liaison Committee Meeting - Mar 25, 2020Cedarvale & Forest Hill Construction Liaison Committee Meeting - Mar 25, 2020
Cedarvale & Forest Hill Construction Liaison Committee Meeting - Mar 25, 2020Crosstown TO
 
Portfolio Dec 22-min
Portfolio Dec 22-minPortfolio Dec 22-min
Portfolio Dec 22-minYi Liang Yew
 

Similar to ADIB Time Schedule V4.0 (20)

Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
 
WC-14-NXE-007-00-Sch Rev 0.0 (29 May,2015)
WC-14-NXE-007-00-Sch Rev 0.0  (29 May,2015)  WC-14-NXE-007-00-Sch Rev 0.0  (29 May,2015)
WC-14-NXE-007-00-Sch Rev 0.0 (29 May,2015)
 
Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdfZewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdf
 
Project Schedule - Level IV Schedule
Project Schedule - Level IV ScheduleProject Schedule - Level IV Schedule
Project Schedule - Level IV Schedule
 
MS project Sample gantt chart
MS project Sample  gantt chartMS project Sample  gantt chart
MS project Sample gantt chart
 
Single Family Gantt Chart-John Mueller
Single Family Gantt Chart-John MuellerSingle Family Gantt Chart-John Mueller
Single Family Gantt Chart-John Mueller
 
Presentation
PresentationPresentation
Presentation
 
Final Majarrah rev 0
Final Majarrah rev 0Final Majarrah rev 0
Final Majarrah rev 0
 
ABC_3rd Progress Mtg Briefing_050115_draft.ppt
ABC_3rd Progress Mtg Briefing_050115_draft.pptABC_3rd Progress Mtg Briefing_050115_draft.ppt
ABC_3rd Progress Mtg Briefing_050115_draft.ppt
 
Naperville Woman’s Club Landmark Remodeling Project
Naperville Woman’s Club Landmark Remodeling ProjectNaperville Woman’s Club Landmark Remodeling Project
Naperville Woman’s Club Landmark Remodeling Project
 
Jadwal Pelaksanaan PPI.pdf
Jadwal Pelaksanaan PPI.pdfJadwal Pelaksanaan PPI.pdf
Jadwal Pelaksanaan PPI.pdf
 
Project master schedule daughter station cng mini plant
Project master schedule daughter station cng mini plantProject master schedule daughter station cng mini plant
Project master schedule daughter station cng mini plant
 
Sample Project Monitoring-EVM Analysis
Sample Project Monitoring-EVM Analysis Sample Project Monitoring-EVM Analysis
Sample Project Monitoring-EVM Analysis
 
Project Monitoring with EVM Analysis
Project Monitoring with EVM Analysis Project Monitoring with EVM Analysis
Project Monitoring with EVM Analysis
 
2 l 65z
2 l 65z2 l 65z
2 l 65z
 
Cedarvale & Forest Hill Construction Liaison Committee Meeting - Jan 29, 2020
Cedarvale & Forest Hill Construction Liaison Committee Meeting - Jan 29, 2020Cedarvale & Forest Hill Construction Liaison Committee Meeting - Jan 29, 2020
Cedarvale & Forest Hill Construction Liaison Committee Meeting - Jan 29, 2020
 
Spindrift-cinematique-traduit
Spindrift-cinematique-traduitSpindrift-cinematique-traduit
Spindrift-cinematique-traduit
 
Cedarvale & Forest Hill Construction Update - May 27, 2020
Cedarvale & Forest Hill Construction Update - May 27, 2020Cedarvale & Forest Hill Construction Update - May 27, 2020
Cedarvale & Forest Hill Construction Update - May 27, 2020
 
Cedarvale & Forest Hill Construction Liaison Committee Meeting - Mar 25, 2020
Cedarvale & Forest Hill Construction Liaison Committee Meeting - Mar 25, 2020Cedarvale & Forest Hill Construction Liaison Committee Meeting - Mar 25, 2020
Cedarvale & Forest Hill Construction Liaison Committee Meeting - Mar 25, 2020
 
Portfolio Dec 22-min
Portfolio Dec 22-minPortfolio Dec 22-min
Portfolio Dec 22-min
 

ADIB Time Schedule V4.0

  • 1. Activity Name Original Duration Start Finish Preparation and processing of the twelvth floor of th 76 31-Mar-15 14-Jun-15 General 76 31-Mar-15 14-Jun-15 Dates (Milestones) 76 31-Mar-15 14-Jun-15 Project Start 0 31-Mar-15 Establishing ELEC., Plumbing and HVAC 0 24-Apr-15 50% Of Work Done 0 16-May-15 80% Of Work Done (Painting Finished) 0 04-Jun-15 Project End 0 14-Jun-15 General Works 76 31-Mar-15 14-Jun-15 Site Mobilization 3 31-Mar-15 02-Apr-15 Demolish & Dismantle Works 3 31-Mar-15 02-Apr-15 Licenses and Permissions 7 31-Mar-15 06-Apr-15 Delivering Project 1 14-Jun-15 14-Jun-15 Surveying Works 1 03-Apr-15 03-Apr-15 Surveying Works 1 03-Apr-15 03-Apr-15 Technical Office Works 5 04-Apr-15 09-Apr-15 Arch WSD 5 04-Apr-15 09-Apr-15 Prepare & Submit Arch WSD 5 04-Apr-15 08-Apr-15 Material Submittal 5 04-Apr-15 08-Apr-15 Arch WSD approval 0 09-Apr-15 09-Apr-15 Material Approval 0 09-Apr-15 09-Apr-15 Elec. WSD 5 04-Apr-15 09-Apr-15 Prepare & Submit Elec. WSD 5 04-Apr-15 08-Apr-15 Material Submittal 5 04-Apr-15 08-Apr-15 Electrical WSD approval 0 09-Apr-15 09-Apr-15 Material Approval 0 09-Apr-15 09-Apr-15 HVAC WSD 5 04-Apr-15 09-Apr-15 Prepare & Submit HVAC WSD 5 04-Apr-15 08-Apr-15 Material Submittal 5 04-Apr-15 08-Apr-15 HVAC WSD approval 0 09-Apr-15 09-Apr-15 Material Approval 0 09-Apr-15 09-Apr-15 Plum. WSD 5 04-Apr-15 09-Apr-15 Prepare & Submit Plumping WSD 5 04-Apr-15 08-Apr-15 Material Submittal 5 04-Apr-15 08-Apr-15 Plumbing WSD approval 0 09-Apr-15 09-Apr-15 Material Approval 0 09-Apr-15 09-Apr-15 Architectural Work 66 09-Apr-15 13-Jun-15 Masonary Work 3 09-Apr-15 11-Apr-15 Kitchen & Bathrooms Insulation 1 12-Apr-15 12-Apr-15 Plastering 3 27-Apr-15 29-Apr-15 Files Room Strengthening 4 30-Apr-15 03-May-15 Floor Work 43 30-Apr-15 11-Jun-15 Mosaic Tiles Flooring Installation 5 30-Apr-15 04-May-15 28 04 11 18 25 02 09 16 23 30 06 13 20 April 2015 May 2015 June 2015 14-Jun-15 14-Jun-15 14-Jun-15 Project Start Establishing ELEC., Plumbing and HVAC 50% Of Work Done 80% Of Work Done (Painti Project E 14-Jun-15 Site Mobilization Demolish & Dismantle Works Licenses and Permissions Deliverin 03-Apr-15, Surveying Works Surveying Works 09-Apr-15, Technical Office Works 09-Apr-15, Arch WSD Prepare & Submit Arch WSD Material Submittal Arch WSD approval Material Approval 09-Apr-15, Elec. WSD Prepare & Submit Elec. WSD Material Submittal Electrical WSD approval Material Approval 09-Apr-15, HVAC WSD Prepare & Submit HVAC WSD Material Submittal HVAC WSD approval Material Approval 09-Apr-15, Plum. WSD Prepare & Submit Plumping WSD Material Submittal Plumbing WSD approval Material Approval 13-Jun-15, Masonary Work Kitchen & Bathrooms Insulation Plastering Files Room Strengthening 11-Jun-15, Flo Mosaic Tiles Flooring Installation Preparation and processing of the twelvth floor of the headquarters in Garden City Master Schedule ADIB Time Schedule V4 03-APR-2015 Page 1 of 3 Project Management Department Misr Contraco Group
  • 2. Activity Name Original Duration Start Finish Ceramic Flooring Installation 5 30-Apr-15 04-May-15 Marble Flooring Installation 5 30-Apr-15 04-May-15 HDF Flooring Installation 4 06-Jun-15 09-Jun-15 HPL Flooring Installation 4 06-Jun-15 09-Jun-15 Finishing Marble Flooring 4 06-Jun-15 09-Jun-15 Vinyl Flooring 4 06-Jun-15 09-Jun-15 Carpet Installation 2 10-Jun-15 11-Jun-15 Wall Work 26 30-Apr-15 25-May-15 Marble Walls Installation 4 30-Apr-15 03-May-15 MDF Walls Installation 4 30-Apr-15 03-May-15 Ceramic Cladding Installation 4 30-Apr-15 03-May-15 Gypsum Galvanized Studs 4 05-May-15 08-May-15 Gypsum Cladding Installation 3 09-May-15 11-May-15 Skirting Installation 2 24-May-15 25-May-15 Partitions 32 09-May-15 09-Jun-15 Gypsum Partitions Installation 4 09-May-15 12-May-15 Bathroom Partitions Installation 4 09-May-15 12-May-15 Wooden Partitions Installation 3 24-May-15 26-May-15 Glass Partitions Installation (Securit) 3 31-May-15 02-Jun-15 HPL Bathroom Partitions Installation 3 07-Jun-15 09-Jun-15 Doors & Windows 6 24-May-15 29-May-15 Metal Doors Installation 3 24-May-15 26-May-15 Wooden Doors Installation 3 24-May-15 26-May-15 Wooden Frames Installation 2 25-May-15 26-May-15 Wooden Crossings Installation 2 25-May-15 26-May-15 Alumital Windows Installation 2 28-May-15 29-May-15 Ceiling Work 25 12-May-15 05-Jun-15 Galvanized Steel Sub-structure for Gypsum Board 5 12-May-15 16-May-15 Gypsum Board Installation 4 17-May-15 20-May-15 Ceiling Tiles Installation 4 17-May-15 20-May-15 Finishing Plastic Painting for Ceiling 4 02-Jun-15 05-Jun-15 Stairs Work 39 30-Apr-15 07-Jun-15 Stairs Marble Installation 4 30-Apr-15 03-May-15 Stairs Marble Finishing 1 04-May-15 04-May-15 Handrail Installation 2 06-Jun-15 07-Jun-15 Painting 24 21-May-15 13-Jun-15 Establishing Painting 7 21-May-15 27-May-15 Finishing Walls Painting 3 02-Jun-15 04-Jun-15 Accessories & Wallpaper Works 2 12-Jun-15 13-Jun-15 External Work 6 09-May-15 14-May-15 Rolling Shutter 6 09-May-15 14-May-15 Rolling Shutter Installation 5 09-May-15 13-May-15 Rolling Shutter Testing 1 14-May-15 14-May-15 28 04 11 18 25 02 09 16 23 30 06 13 20 April 2015 May 2015 June 2015 Ceramic Flooring Installation Marble Flooring Installation HDF Flooring Inst HPL Flooring Inst Finishing Marble Vinyl Flooring Carpet Installa 25-May-15, Wall Work Marble Walls Installation MDF Walls Installation Ceramic Cladding Installation Gypsum Galvanized Studs Gypsum Cladding Installation Skirting Installation 09-Jun-15, Partitio Gypsum Partitions Installation Bathroom Partitions Installation Wooden Partitions Installation Glass Partitions Installation ( HPL Bathroom Pa 29-May-15, Doors & Windows Metal Doors Installation Wooden Doors Installation Wooden Frames Installation Wooden Crossings Installation Alumital Windows Installation 05-Jun-15, Ceiling Work Galvanized Steel Sub-structure for Gypsum Board Gypsum Board Installation Ceiling Tiles Installation Finishing Plastic Paintin 07-Jun-15, Stairs Wor Stairs Marble Installation Stairs Marble Finishing Handrail Installation 13-Jun-15, Establishing Painting Finishing Walls Painting Accessorie 14-May-15, External Work 14-May-15, Rolling Shutter Rolling Shutter Installation Rolling Shutter Testing Preparation and processing of the twelvth floor of the headquarters in Garden City Master Schedule ADIB Time Schedule V4 03-APR-2015 Page 2 of 3 Project Management Department Misr Contraco Group
  • 3. Activity Name Original Duration Start Finish MEP 53 13-Apr-15 04-Jun-15 Plumping 50 13-Apr-15 01-Jun-15 Fixing Drainage & Feeding pipes 2 13-Apr-15 14-Apr-15 Testing Pipes 1 15-Apr-15 15-Apr-15 Sanitary Fixtures Installation 1 31-May-15 31-May-15 Testing & Commisioning 1 01-Jun-15 01-Jun-15 Electrical Works 53 13-Apr-15 04-Jun-15 Main Power Feeder 2 13-Apr-15 14-Apr-15 1st. Fix Installation (Pipes Installation) 12 15-Apr-15 26-Apr-15 2nd Fix Installation (Wire Pulling) 12 15-Apr-15 26-Apr-15 Cable Tray Installation 5 21-Apr-15 25-Apr-15 Distribution Pannels Installation 3 31-May-15 02-Jun-15 Sockets Installation (including data & telephone) 1 31-May-15 31-May-15 Lighting Fixture Installation 2 02-Jun-15 03-Jun-15 Testing & Commisioning 1 04-Jun-15 04-Jun-15 HVAC 52 13-Apr-15 03-Jun-15 Indoor Units 2 13-Apr-15 14-Apr-15 Duct Work & Insulation 2 15-Apr-15 16-Apr-15 Freon Installation 2 17-Apr-15 18-Apr-15 Drainage System 2 19-Apr-15 20-Apr-15 Fresh Air & Exhaust Air Fans Installation 2 21-Apr-15 22-Apr-15 Outdoor Units Connection 2 23-Apr-15 24-Apr-15 Grills Installation 2 31-May-15 01-Jun-15 Thermostate Installation 1 02-Jun-15 02-Jun-15 Testing & Commisioning 1 03-Jun-15 03-Jun-15 28 04 11 18 25 02 09 16 23 30 06 13 20 April 2015 May 2015 June 2015 04-Jun-15, MEP 01-Jun-15, Plumping Fixing Drainage & Feeding pipes Testing Pipes Sanitary Fixtures Installation Testing & Commisioning 04-Jun-15, Electrical Work Main Power Feeder 1st. Fix Installation (Pipes Installation) 2nd Fix Installation (Wire Pulling) Cable Tray Installation Distribution Pannels Installat Sockets Installation (including d Lighting Fixture Installation Testing & Commisioning 03-Jun-15, HVAC Indoor Units Duct Work & Insulation Freon Installation Drainage System Fresh Air & Exhaust Air Fans Installation Outdoor Units Connection Grills Installation Thermostate Installation Testing & Commisioning Preparation and processing of the twelvth floor of the headquarters in Garden City Master Schedule ADIB Time Schedule V4 03-APR-2015 Page 3 of 3 Project Management Department Misr Contraco Group