This progress report provides an overview of installation and pre-commissioning work for Phase 50. Key details include:
- Overall progress is 88.15%, slightly behind the planned 92.46% due to some delayed cable testing and equipment hook-ups.
- Pre-commissioning and SAT are underway for Platform CVX-501 and nearing completion for CVX-503. Later platforms like CVX-511 remain on schedule for late 2016 completion.
- Productivity is monitored through dashboards tracking tasks, budgets, and earned/actual manhours. Subcontractors are cautioned to expedite work to meet pre-commissioning dates.
- Attachments include a pre-commissioning/SAT