PROGRESS REPORT
THE EXAMPLE OF
WORKING PORTFOLIO - 01
RESPONSIBILITIES;
E&I INSTALLATION AND PRE-COMMISSIONING.
SUB-STRUCTURAL FABRICATION – JACKET AND PILE.
SUB-SEA PIPELINE FABRICATION.
KEY DOCUMENTS;
DASHBOARD
WPR, SUMARY STATUS AND KEY-DATES.
S-CURVE.
PROGRESS MEASUREMENT AND MONITORING.
E&I AND PRE-COMMISSIONING DASHBOARD
Project Completion Task Status Pre-Com and SAT Countdown
PF DAY
PF DAY
Plan & Actual Deviation INCOMING PRE-COM SAT CONTRACT
CVX-501 17-May-16A 30-May-16A 30-Jul-16
CVX-503 25-May-16A 6-Jun-16 13-Aug-16
CVX-504 28-May-16A 13-Jun-16 20-Aug-16
CVX-502 13-Jun-16 20-Jun-16 6-Aug-16
CVX-505 20-Jun-16 27-Jun-16 27-Aug-16
CVX-511 14-Nov-16 28-Nov-16 19-Feb-17
CVX-512 28-Nov-16 13-Dec-16 26-Feb-17
CVX-513 12-Dec-16 9-Jan-17 5-Mar-17
Cost and Budgets - Mhrs. Productivity Trend Highlight and Concerns
● Sub-contractor is under catching up the work progress.
To hand-over the installation package prior to
PF Pre-commissioning and SAT commencement.
112,100 42,629
61,371 33,590
103,870 10,005 *This productivity report DOES NOT included "MSL actual mhrs."
01-Jun-16
PRE-COM.
SAT.
502 12
503 5
20.79%
88.15%
PHASE 51
PHASE 50
38%
12%
50%
4%
76%
20%
Late Task
On-Time/ Early Task
Completed Task4.37%
-4.31%
-10.00% -5.00% 0.00% 5.00% 10.00%
PHASE 50 PHASE 51 0.00
1.00
2.00
PHASE 50 PHASE 51
PHASE 50
PHASE 51
KPI
PHASE 50 PHASE 51
Earned Mhrs.
Actual - CUEL
Actual - MSL
Prepared By: Nattakarn S.
Construction Planning Dept.
· This summary progress status is based on Phase 50 's Project Plan Rev.2 - Accelerate Plan.
· Overall actual progress of E&I and Pre-Commissioning works is 88.15% against overall planed 92.46%, variance is -4.31% (The last cut off, progress deviation is -4.58%).
· Highlight and Concern - Delayed of cables continuity check, tubing leak test and hook-up of field equipment. Potential to delay project completion.
· Continue submission of check sheet/IRV for all of activities which had been physical completed.
· Continue cables glanding and termination for CVX-505.
· Continue cable continuity check for CVX-502 to 505.
· Continue field installation of TPU JK tube for CVX-502, 504 and 505.
· Completed tube leak testing for CVX-503.
· Continue installation and hook-up of E&I tag item for CVX-501 to 505.
· Completed E&I loop and function test for CVX-501.
· Commenced E&I loop and function test for CVX-503 and 504.
· Commenced platform SAT for CVX-501.
· To catch up work progress which has been mention as a delayed/concerned activitie.
· All works to completed and align with the accelerate LO dates refer to ITC-620272/2809/PH50 : 6-May-16.
· Float = Accelerate Load-Out Dates - Forecast Fabrication completion Dates.
· This productivity report "does not includes" man-hours from onsite sub-contractors and all offsite sub-contractors.
Attachment : 1 Pre-Commissioning and SAT Timeline
Attachment : 2 Summary Progress Status by Platform
Attachment : 3 Site Narative Report - NA
Prepared by:
Nattakarn Sooksa-nguan
Construction Planner
G ATTACHMENT
14
16
20-Jun-16
13-Jun-16
25-Jun-16
18-Jun-163
CVX-502
CVX-504
CVX-505
F
E
Finish Start Finish
166-Jun-16
4-Jun-16
11-Jun-16
30-May-16A
18-Jun-16
11-Jun-16
A SUMMARY PROGRESS STATUS
No.
% Cum. Last Week % Achieved in Week % Cum. Up to Date
Plan Actual Var Plan Actual Plan Actual Var
WTGBudget Mhrs
Platforms
Name Type Var
2.14 2.58 0.44 88.80
5.20
85.71
1.84
87.303
2 Gas
1.14 1.06 -0.08
7.27 4.38 -2.90
90.57
-3.104 86.66 83.12 -3.5426,576 20.00%
WEEKLY PROGRESS REPORT
PHASE 50 : E&I AND PRE-COMMISSIONING WORKS
Cut off Date 01-Jun-16 Cut off Time 1700H No. of Pages 4
1 98.16 92.32 -5.8426,576 20.00%CVX-501 Gas
-3.27
91.41 -6.58
CVX-502 Gas
3.05 100.00 97.21 -2.794.89
89.43 86.24 -3.1926,576 20.00%CVX-504 Gas
97.9990.72 87.03 -3.6926,576 20.00%CVX-503
-5.815 79.74 73.08 -6.6626,576 20.00%CVX-505 Gas 6.06 0.85 84.94 79.13
OTHER CONCERN
Item Remarks/ StatusAction by TargetDescription / Action Required
1
Sub-contractor to expedite their works progress to ensure that all related work must be done
prior to platform pre-commissioning commencement.
MSL Continuous Under catching up work progress.
88.94 84.36 -4.58 3.52 3.79 0.27 92.46 88.15
Fab.
Priority Start
132,880 100.00%Overall Progress
B FABRICATION ACTIVITIES : DONE IN WEEK
C FABRICATION ACTIVITIES : PLANED IN NEXT WEEKS
D KEY DATES
Float Contractual
Sail-Away
Platform
Name
Pre-Commissioning
5,725 0.77
-4.31
Load-Out
22-Jun-16
27-Jun-16
9-Jul-16
26-Jun-16
4-Jul-16
18-Jul-16
30-Jul-16
1-Jul-16
13-Jul-16
8-Jul-16
22-Jul-16
13-Aug-16
6-Aug-16
20-Aug-16
27-Aug-16
ITC-620272/2809 - Accelerate
Remark
0.55
27-Jun-16
PRODUCTIVITY : KPI
29-May-16A
4-Jun-16
CVX-501
CVX-503
2-Jul-16
18
16
2
4
1 17-May-16A
25-May-16A
13-Jun-16
28-May-16A
20-Jun-16 25-Jun-16
Site Acceptance Test
10091.91.03.60.225 Pre-Comm. Instrument 6,205 237 0 0.00
10091.91.03.50.180 Check and Test 6,265 3,268 29 0.01
Pre-Commissioning and SAT 12,500 852 359 0.42
5
10091.91.03.60.220 Pre-Comm. Electrical 3,520 615
10091.91.03.50.165 Calibration
10091.91.03.50.170 Support 40,945 40,881
359 0.58
0.70
E&I Installation 120,380 111,248 61,012
6,340 6,340 4,442
10091.91.03.50.160 Rigging, Scaffolding and Transportation 8,055 7,390
42,740 1.05
10091.91.03.50.175 Installation 8,076 0.1558,775 53,369
Cost Code Work Detail
Budgeted
Labor Units - Mhrs
Productivity As of Date : 25-May-16
RemarksAccumulative
Earned Mhrs
Accumulative
Actual Mhrs
Productivity
(Target < 1.00)
10091.91.03.60.235 SAT - Site Acceptance Test 2,775 0
61,371 0.55Overall 132,880 112,100
0 -
Page 1 of 1 Prepared By : Nattakarn S.
11-Apr-16 18-Apr-16 25-Apr-16 02-May-16 09-May-16 16-May-16 23-May-16 30-May-16 06-Jun-16 13-Jun-16 20-Jun-16 27-Jun-16 04-Jul-16 11-Jul-16 18-Jul-16 25-Jul-16 01-Aug-16 08-Aug-16 15-Aug-16 22-Aug-16 29-Aug-16 05-Sep-16 12-Sep-16
Pre-Com 501 SAT 501 Potential L/O Current L/O Rev.21
Pre-Com 503 SAT 503 Potential L/O Current L/O Rev.21
Pre-Com 504 SAT 504 Potential L/O Current L/O Rev.21
Pre-Com 502 SAT 502 Potential L/O Current L/O Rev.21
Pre-Com 505 SAT 505 Potential L/O Current L/O Rev.21
1 CVX-501 30-Apr-16 12-May-16 2-Jun-16 28-Apr-16 7-May-16 13-May-16 23-Jun-16 1-Jul-16 -9 4 17-May-16A 29-May-16A 30-May-16A 4-Jun-16 18 31 30-Jul-16 5-Jul-16 9-Jul-16 22-Jun-16 26-Jun-16
2 CVX-503 17-May-16 27-May-16 16-Jun-16 7-May-16 13-May-16 21-May-16 7-Jul-16 15-Jul-16 -18 -4 25-May-16A 4-Jun-16 6-Jun-16 11-Jun-16 16 30 13-Aug-16 11-Jul-16 15-Jul-16 27-Jun-16 1-Jul-16
3 CVX-504 25-May-16 4-Jun-16 23-Jun-16 14-May-16 21-May-16 27-May-16 14-Jul-16 23-Jul-16 -19 -7 28-May-16A 11-Jun-16 13-Jun-16 18-Jun-16 16 28 20-Aug-16 16-Jul-16 20-Jul-16 4-Jul-16 8-Jul-16
4 CVX-502 10-May-16 19-May-16 9-Jun-16 21-May-16 27-May-16 3-Jun-16 30-Jun-16 8-Jul-16 1 13 13-Jun-16 18-Jun-16 20-Jun-16 25-Jun-16 14 26 6-Aug-16 21-Jul-16 25-Jul-16 9-Jul-16 13-Jul-16
5 CVX-505 2-Jun-16 11-Jun-16 4-Jul-16 28-May-16 3-Jun-16 10-Jun-16 28-Jul-16 5-Aug-16 -18 -7 20-Jun-16 25-Jun-16 27-Jun-16 2-Jul-16 16 27 27-Aug-16 29-Jul-16 2-Aug-16 18-Jul-16 22-Jul-16
Note
1. Float (1) = Accelerate Load-Out Dates - SAT Completion Date.
2. Float (2) = Current Load-Out Dates - SAT Completion Date.
Sail-Away
Start Finish Start Finish
Float(2)
SAT
Float(1) Load-Out Sail-Away Load-Out
Sequence
Platform
Name
PIPING WORKS E&I AND PRE-COMMISSIONING
Contractual
Completion
Installation
Completion
Hydro-Test
Completion
Service Test
Completion
Installation
Completion
Hydro-Test
Completion
Service Test
Completion
Pre-Com.
Completion
SAT
Completion
Float(1) Float(2)
Pre-Com.
LOAD-OUT AND SAIL-AWAY SCHEDULE
Piping Key Dates: Baseline Rev.0 Piping Key Dates: Committed Dates E&I and Pre-Com Key Dates: Baseline Rev.0 E&I And Pre-Com Key Dates: Rev.5_Accelerate Current Revision - Rev.21 ITC-620272/2809 - Accelerate
YEAR 2016
CVX-PHASE 50 : PLATFORM PRE-COMMISSIONING & SAT TIMELINE
ACCELERATE PLAN - ITC-620272/2809/PH50
REVISION Rev.5_Accelerate
ISSUED DATE 04-May-16
1-Jun-16
501 - Piping Service Test Completion
503 - Piping Service Test Completion
504 - Piping Service Test Completion
502 - Piping Service Test Completion
505 - Piping Service Test Completion
E&I Hook-Up Completion
E&I Hook-Up Completion
E&I Hook-Up Completion
E&I Hook-Up Completion
E&I Hook-Up Completion
Punch-list, touch-up and wash down
Punch-list, touch-up and wash down
Punch-list, touch-up and wash down
Punch-list, touch-up and wash down
Punch-list, touch-up and wash down
Page 1 of 1 Prepared By : Nattakarn S.
1-Jun-16
Budgeted Units % Actual
Plan Actual Var. Plan Actual Var. Plan Actual Var.
CVX-501 26576 20.00% 98.16 92.32 -5.84 1.84 4.89 3.05 100.00 97.21 -2.79
CVX-502 26576 20.00% 86.66 83.12 -3.54 2.14 2.58 0.44 88.80 85.71 -3.10
CVX-503 26576 20.00% 90.72 87.03 -3.69 7.27 4.38 -2.90 97.99 91.41 -6.58
CVX-504 26576 20.00% 89.43 86.24 -3.19 1.14 1.06 -0.08 90.57 87.30 -3.27
CVX-505 26576 20.00% 79.74 73.08 -6.66 5.20 6.06 0.85 84.94 79.13 -5.81
Overall 132880 100.00% 88.94 84.36 -4.58 3.52 3.79 0.27 92.46 88.15 -4.31
Budgeted Units % Plan-Wk % Actual -Wk % Actual
Plan Actual Var. Plan Actual Var. Plan Actual Var.
E&I Installation 24076 90.59% 100.00 98.37 -1.63 0.00 0.50 0.50 100.00 98.88 -1.12
Calibration of Instruments Tag 1294 5.37% 100.00 100.00 0.00 0.00 0.00 0.00 100.00 100.00 0.00
E&I Supports, Ladders and Trays 8442 35.06% 100.00 100.00 0.00 0.00 0.00 0.00 100.00 100.00 0.00
Fabrication of E&I Supports 3723 44.10% 100.00 100.00 0.00 0.00 0.00 0.00 100.00 100.00 0.00
Installation of E&I SupportS 3250 38.50% 100.00 100.00 0.00 0.00 0.00 0.00 100.00 100.00 0.00
Installation of E&I Trays and Ladders 1469 17.40% 100.00 100.00 0.00 0.00 0.00 0.00 100.00 100.00 0.00
Cables Installation 8282 34.40% 100.00 99.93 -0.07 0.00 0.00 0.00 100.00 99.93 -0.07
Tubings Installation 3986 16.56% 100.00 94.49 -5.51 0.00 1.35 1.35 100.00 95.84 -4.16
Hook-Up of E&I Tag Items 793 3.29% 100.00 91.75 -8.25 0.00 6.64 6.64 100.00 98.38 -1.62
Cable Continuity Check 995 4.13% 100.00 92.58 -7.42 0.00 0.00 0.00 100.00 92.58 -7.42
Tubing Leak Test 284 1.18% 100.00 90.39 -9.61 0.00 5.36 5.36 100.00 95.75 -4.25
E&I Pre-Commissioning 2500 9.41% 80.46 34.05 -46.41 19.54 47.07 27.53 100.00 81.12 -18.88
Loop/Function Test 1945 77.80% 100.00 43.76 -56.24 0.00 46.24 46.24 100.00 90.00 -10.00
Site Acceptance Test - SAT 555 22.20% 0.00 0.00 0.00 100.00 50.00 -50.00 100.00 50.00 -50.00
Total 26576 100.00% 98.16 92.32 -5.84 1.84 4.89 3.05 100.00 97.21 -2.79
Budgeted Units % Plan-Wk % Actual -Wk % Plan % Actual
Plan Actual Var. Plan Actual Var. Plan Actual Var.
E&I Installation 24076 90.59% 100.00 96.07 -3.93 0.00 1.72 1.72 100.00 97.79 -2.21
Calibration of Instruments Tag 1294 5.37% 100.00 100.00 0.00 0.00 0.00 0.00 100.00 100.00 0.00
E&I Supports, Ladders and Trays 8442 35.06% 100.00 100.00 0.00 0.00 0.00 0.00 100.00 100.00 0.00
Fabrication of E&I Supports 3723 44.10% 100.00 100.00 0.00 0.00 0.00 0.00 100.00 100.00 0.00
Installation of E&I SupportS 3250 38.50% 100.00 100.00 0.00 0.00 0.00 0.00 100.00 100.00 0.00
Installation of E&I Trays and Ladders 1469 17.40% 100.00 100.00 0.00 0.00 0.00 0.00 100.00 100.00 0.00
Cables Installation 8282 34.40% 100.00 99.58 -0.42 0.00 0.00 0.00 100.00 99.58 -0.42
Tubings Installation 3986 16.56% 100.00 92.81 -7.19 0.00 2.48 2.48 100.00 95.29 -4.71
Hook-Up of E&I Tag Items 793 3.29% 100.00 73.80 -26.20 0.00 5.69 5.69 100.00 79.49 -20.51
Cable Continuity Check 995 4.13% 100.00 86.63 -13.37 0.00 1.09 1.09 100.00 87.72 -12.28
Tubing Leak Test 284 1.18% 100.00 0.00 -100.00 0.00 91.12 91.12 100.00 91.12 -8.88
E&I Pre-Commissioning 2500 9.41% 0.00 0.00 0.00 78.66 29.98 -48.68 78.66 29.98 -48.68
Loop/Function Test 1945 77.80% 0.00 0.00 0.00 100.00 38.53 -61.47 100.00 38.53 -61.47
Site Acceptance Test - SAT 555 22.20% 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Total 26576 100.00% 90.72 87.03 -3.69 7.27 4.38 -2.90 97.99 91.41 -6.58
Budgeted Units % Plan-Wk % Actual -Wk % Plan % Actual
Plan Actual Var. Plan Actual Var. Plan Actual Var.
E&I Installation 24076 90.59% 98.72 95.20 -3.52 1.26 1.17 -0.09 99.97 96.37 -3.61
Calibration of Instruments Tag 1294 5.37% 100.00 100.00 0.00 0.00 0.00 0.00 100.00 100.00 0.00
E&I Supports, Ladders and Trays 8442 35.06% 100.00 100.00 0.00 0.00 0.00 0.00 100.00 100.00 0.00
Fabrication of E&I Supports 3723 44.10% 100.00 100.00 0.00 0.00 0.00 0.00 100.00 100.00 0.00
Installation of E&I SupportS 3250 38.50% 100.00 100.00 0.00 0.00 0.00 0.00 100.00 100.00 0.00
Installation of E&I Trays and Ladders 1469 17.40% 100.00 100.00 0.00 0.00 0.00 0.00 100.00 100.00 0.00
Cables Installation 8282 34.40% 100.00 99.58 -0.42 0.00 0.00 0.00 100.00 99.58 -0.42
Tubings Installation 3986 16.56% 100.00 91.20 -8.80 0.00 2.14 2.14 100.00 93.35 -6.65
Hook-Up of E&I Tag Items 793 3.29% 75.16 56.88 -18.28 24.84 24.49 -0.36 100.00 81.37 -18.63
Cable Continuity Check 995 4.13% 97.54 85.43 -12.11 2.46 0.15 -2.31 100.00 85.58 -14.42
Tubing Leak Test 284 1.18% 98.77 0.00 -98.77 1.23 0.00 -1.23 100.00 0.00 -100.00
E&I Pre-Commissioning 2500 9.41% 0.00 0.00 0.00 38.90 0.00 -38.90 38.90 0.00 -38.90
Loop/Function Test 1945 77.80% 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Site Acceptance Test - SAT 555 22.20% 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Total 26576 100.00% 89.43 86.24 -3.19 1.14 1.06 -0.08 90.57 87.30 -3.27
Budgeted Units % Plan-Wk % Actual -Wk % Plan % Actual
Plan Actual Var. Plan Actual Var. Plan Actual Var.
E&I Installation 24076 90.59% 95.66 91.75 -3.91 2.36 2.85 0.49 98.02 94.61 -3.42
Calibration of Instruments Tag 1294 5.37% 100.00 100.00 0.00 0.00 0.00 0.00 100.00 100.00 0.00
E&I Supports, Ladders and Trays 8442 35.06% 99.91 99.61 -0.29 0.09 0.39 0.29 100.00 100.00 0.00
Fabrication of E&I Supports 3723 44.10% 100.00 100.00 0.00 0.00 0.00 0.00 100.00 100.00 0.00
Installation of E&I SupportS 3250 38.50% 99.75 98.99 -0.77 0.25 1.01 0.77 100.00 100.00 0.00
Installation of E&I Trays and Ladders 1469 17.40% 100.00 100.00 0.00 0.00 0.00 0.00 100.00 100.00 0.00
Cables Installation 8282 34.40% 97.25 96.83 -0.42 2.75 1.75 -1.01 100.00 98.58 -1.42
Tubings Installation 3986 16.56% 99.65 87.17 -12.48 0.35 5.27 4.92 100.00 92.44 -7.56
Hook-Up of E&I Tag Items 793 3.29% 72.38 60.44 -11.95 9.08 0.00 -9.08 81.46 60.44 -21.03
Cable Continuity Check 995 4.13% 70.75 41.67 -29.09 20.45 30.01 9.55 91.21 71.67 -19.53
Tubing Leak Test 284 1.18% 0.00 0.00 0.00 46.48 0.00 -46.48 46.48 0.00 -46.48
E&I Pre-Commissioning 2500 9.41% 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Loop/Function Test 1945 77.80% 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Site Acceptance Test - SAT 555 22.20% 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Total 26576 100.00% 86.66 83.12 -3.54 2.14 2.58 0.44 88.80 85.71 -3.10
WHP 50/4 : GAS PLATFORM
Platform Budget Mhrs Weightage
% Last Week % Achieved This Week % Up To Date
WHP 50/3 : GAS PLATFORM
Platform Budget Mhrs Weightage
% Last Week % Achieved This Week % Up To Date
WHP 50/2 : GAS PLATFORM
Platform Budget Mhrs Weightage
% Last Week % Achieved This Week % Up To Date
WHP 50/1 : GAS PLATFORM
Platform Budget Mhrs Weightage
% Last Week % Achieved This Week % Up To Date
% Up To Date
CHEVRON : CVX-PHASE 50
PROGRESS STATUS OF E&I AND PRE-COMMISSIONING WORKS : BY PLATFORM
Cut Off Date
OVERALL : BY PLATFORM
Platform Budget Mhrs Weightage
% Last Week % Achieved This Week
Page 1 of 2 Prepared By : Nattakarn S.
1-Jun-16
CHEVRON : CVX-PHASE 50
PROGRESS STATUS OF E&I AND PRE-COMMISSIONING WORKS : BY PLATFORM
Cut Off Date
Budgeted Units % Plan-Wk % Actual -Wk % Plan % Actual
Plan Actual Var. Plan Actual Var. Plan Actual Var.
E&I Installation 24076 90.59% 88.02 80.67 -7.35 5.74 6.68 0.94 93.76 87.35 -6.41
Calibration of Instruments Tag 1294 5.37% 99.77 100.00 0.23 0.23 0.00 -0.23 100.00 100.00 0.00
E&I Supports, Ladders and Trays 8442 35.06% 99.99 99.61 -0.38 0.01 0.39 0.38 100.00 100.00 0.00
Fabrication of E&I Supports 3723 44.10% 100.00 100.00 0.00 0.00 0.00 0.00 100.00 100.00 0.00
Installation of E&I SupportS 3250 38.50% 99.97 98.98 -0.99 0.03 1.02 0.99 100.00 100.00 0.00
Installation of E&I Trays and Ladders 1469 17.40% 100.00 100.00 0.00 0.00 0.00 0.00 100.00 100.00 0.00
Cables Installation 8282 34.40% 91.54 80.79 -10.75 5.08 10.11 5.03 96.62 90.90 -5.72
Tubings Installation 3986 16.56% 67.22 65.39 -1.83 17.84 11.75 -6.09 85.06 77.14 -7.92
Hook-Up of E&I Tag Items 793 3.29% 55.74 49.19 -6.54 7.69 0.20 -7.49 63.43 49.40 -14.03
Cable Continuity Check 995 4.13% 58.79 3.12 -55.68 18.74 27.01 8.27 77.54 30.13 -47.41
Tubing Leak Test 284 1.18% 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
E&I Pre-Commissioning 2500 9.41% 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Loop/Function Test 1945 77.80% 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Site Acceptance Test - SAT 555 22.20% 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Total 26576 100.00% 79.74 73.08 -6.66 5.20 6.06 0.85 84.94 79.13 -5.81
WHP 50/5 : GAS PLATFORM
Platform Budget Mhrs Weightage
% Last Week % Achieved This Week % Up To Date
Page 2 of 2 Prepared By : Nattakarn S.
% Actual
% Plan % Actual % Var.
OVERALL 100.00% 92.46 88.15 -4.31
Noted :
1. This weekly progress status is based on Phase 50 : Project Accelerate Plan Rev.2
17.57 20.55 20.62 21.06 23.88 26.28
8.13 11.36 13.57
10-Aug 24-Aug27-Apr 4-May 11-May 13-Jul 20-Jul23-Dec 30-Dec 27-Jul13-Apr 20-Apr 3-Aug6-Apr
100.0048.87 50.69 74.05 100.0043.41
22-Jul 29-Jul
100.00 100.0039.37 41.31
18-May 25-May
90.59 97.70 100.00
33.09 33.43 34.16 36.87 39.05 40.73 42.27 43.81 46.65 50.01 51.82 51.82 52.61 56.45 56.66
26-Aug 2-Sep 9-Sep 9-Dec 16-Dec
56.72
31-Aug 7-Sep24-Feb 17-Aug2-Mar 9-Mar 16-Mar 23-Mar6-Jan 13-Jan28-Oct 20-Jan 27-Jan 3-Feb 10-Feb 17-Feb
2015
0.74 1.38 3.56 5.70
4.70 7.08 9.84 12.09 14.15
4-Nov 11-Nov 18-Nov 25-Nov 30-Mar
18.36 20.10 21.82
53.47 55.5430.83
23.48 24.64 25.73
56.72 79.13
23.48
29.22 30.23 30.7826.94
33.09 33.43 34.16 36.87 39.05 40.73 42.27 43.81 46.65
26.94
50.01 51.82 51.82 52.61 56.45 56.66
2-Dec
13.57 15.91 18.36 20.10 21.82
WHP 50/5 20.00% 84.94 79.13 -5.81
0.14 0.17 0.17 1.47 1.97 2.77
0.14 0.17 0.17 1.47 1.97 2.77
35.94 37.04 42.03 43.09 45.39 47.55 50.08 51.66 53.99 55.68 58.44 58.44 59.26 64.60 74.75 80.78 85.72 87.03 91.4113.20 15.01 17.02 20.19 21.13 22.65 23.80 25.39 25.83 26.20 28.12 28.81 28.81 29.31 29.50 31.71
4.70 7.08 9.84 12.09 14.15 17.57 20.55 20.62 21.06 23.88 26.28 26.94 26.94 29.22 30.23 30.78
53.99 55.68 58.44 58.44 59.26 64.60 74.75 80.78 88.61 90.72 97.99 100.0025.39 25.83 26.20 28.12 28.81 28.81 29.31 29.50 31.71 35.94 37.04 42.03 43.09 45.39 47.55 50.08 51.66
WHP 50/3 20.00% 97.99 91.41 -6.58
0.11 0.29 0.30 1.99 2.24 6.49 8.31
0.11 0.29 0.30 1.99 2.24 6.49 8.31
13.20 15.01 17.02 20.19 21.13 22.65 23.80
33.49 33.74 34.28 36.24 40.40 44.43 46.06 48.80 49.21 51.30 52.51 52.51 54.55 56.21 62.17 70.67 80.76 86.24 87.3021.06 22.54 25.75 26.09 27.34 28.42 28.42 29.83 30.27 31.70
52.51 52.51 54.55 56.21 62.17 70.6744.43 46.06 48.80 49.21 51.30 100.00
0.14 0.17 0.17 1.47 2.20 3.83 6.80 8.31 12.20 14.94 18.01 19.49
26.09 27.34 28.42 28.42 29.83 30.27 31.70 33.49 33.74 34.28 36.24 40.40
WHP 50/4 20.00% 90.57 87.30 -3.27
0.14 0.17 0.17 1.47 2.20 3.83 6.80 8.31 12.20 14.94 18.01 19.49 21.06 22.54 25.75
74.5345.93 48.34 50.18 53.53 55.07 56.99 59.2236.82 40.15 43.99 60.73 62.46 62.46 63.78 66.91 71.770.19 23.22 24.16 25.12 26.58 27.47 28.38 28.78 29.78 29.78 30.69 32.60
59.22 60.73 62.46 62.46 63.78 66.91 71.77 74.5340.15 43.9915.43
WHP 50/2 20.00% 88.80 85.71
29.78 45.93 48.34 50.18 53.53 55.07 56.9928.78 29.78 30.69 32.60 36.82
-3.10
0.91 1.52 2.09 5.83 8.46 11.97 18.51 19.24 20.80 23.22 24.16 25.12 26.58 27.47 28.38
0.91 1.52 2.09 5.83 8.46 11.97 15.43 18.51 19.24 20.80
0.19
9-Mar
CHEVRON : CVX-PHASE 50
E&I AND PRE-COMMISSIONING : OVERALL PROGRESS S-CURVE
1-Jun-16
WBS WTG
22-Jul 29-Jul 5-Aug 12-Aug 19-Aug 26-Aug 2-Sep 9-Sep 16-Sep 23-Sep 30-Sep 7-Oct 14-Oct 21-Oct 31-Aug 7-Sep17-Aug 24-Aug13-Jul16-Mar 23-Mar
Cumulative Progress
2-Mar 6-Jul1-Jun28-Oct 4-Nov 11-Nov 18-Nov 25-Nov 2-Dec 9-Dec 16-Dec 23-Dec 30-Dec 6-Jan 13-Jan 18-May 25-May 20-Jul 27-Jul 3-Aug 10-Aug13-Apr 20-Apr 27-Apr 4-May30-Mar 6-Apr20-Jan 27-Jan 3-Feb 10-Feb 17-Feb 24-Feb 11-May 15-Jun 22-Jun 29-Jun
WHP 50/1 20.00% 100.00 97.21 -2.79
0.19 1.08 1.52 2.48 6.77 9.36 13.75 16.69 18.93 21.23 23.78 23.99 25.23 26.86 28.10 50.17 52.5128.52 28.76 29.04 30.36 30.36 35.12 73.6273.62
0.19 1.08 1.52
44.99 48.6538.22 42.29
50.17 52.5128.52 28.76 29.04 30.36 30.36 35.12
54.27 58.10 59.99 66.08 68.61 69.60
2.48 6.77 9.36 13.75 16.69 18.93 21.23 23.78 23.99 25.23 26.86 38.22 42.29 44.99 48.65 54.27 58.10 73.62 75.71 80.95 84.43 87.55
0.51
0.51
0.74
75.71 80.95 84.43 87.55
59.99 66.08 68.61 69.60 73.6228.10
100.00100.00 100.00
32.16
45.8637.53
53.47 55.54 79.46 84.36 88.15CUMULATIVE
ACCELERATE PLAN 0.00 0.00 0.00 0.00 0.10
E&I AND PRE-COMMISSIONING WORKS PROGRESS
23-Sep 30-Sep 7-Oct 14-Oct 21-Oct5-Aug 12-Aug 19-Aug
ACTUAL 0.00 0.00 0.00 0.00 0.10
1.38 3.56 5.70
16-Sep
0.00 0.00 0.00
8.13
15.91
11.36
26.66 27.91 28.86 28.86 61.18 65.0241.31 69.95 74.05
27.91 28.8625.73 28.8626.66 59.77 61.18 69.95
39.37
57.46 59.77
50.6937.53
83.52 88.94 92.46 95.52 100.00 100.0065.02 100.0024.64
34.66 57.46 59.77 59.7743.41 45.86 48.87
100.0032.16 34.66
30.83
WEEKLY
PLANNED 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.000.00 0.00VARIANCE 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.000.00 0.00 0.00 0.00 -4.06 -4.58 -4.310.00 0.00 0.00 0.00 0.00 0.00
3.23 2.212.140.64
1.331.72 1.16 1.09 0.93 1.25
0.00 0.000.00 0.00 0.00 0.00
9.47
0.00
0.00 0.00 0.00 0.001.97
0.00
2.07 1.92 2.31 0.00 1.41
0.00 0.00 0.00
1.66
2.18
0.10 0.41 0.23 0.64 2.18 2.14 2.43 3.23 2.21
2.34 2.45 1.74 1.72
2.34 2.45 1.74
4.93 4.10
0.00 0.00 0.00 0.000.95 0.00
2.45 3.011.25 0.95 0.00 1.97 1.33 2.50
1.84 1.94 2.10 2.45 3.01 1.82 2.782.50 2.87 3.84 4.93 4.10
ACTUAL 0.00 0.00 0.00 0.23
0.00
0.00 0.00 0.00 0.00 0.00 0.00
1.92 2.31 0.00 1.41 3.84
0.000.00 0.00 0.00VARIANCE 0.00 0.000.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.00 0.000.000.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
1.66 1.16 1.09 0.930.00 0.10 0.41 2.87 1.84 1.94 2.10 1.82 2.78 2.07
0.00 0.00 0.00 0.00 0.000.00 0.00
2.43
0.00 0.00 0.00 0.00 0.00
98.05 100.00
8-Jun
90.59 98.16 100.00
88.18 92.32 97.21
83.52 86.66 88.80 90.59
2.21 1.81 0.46 0.00
71.25 79.74 84.94 88.97
64.69 73.08
15-Jun 22-Jun 29-Jun 6-Jul
2016
2015 2016
89.43 90.57 98.05
77.94
5.41 4.90 3.79
-4.06 -0.52 0.27
83.63
83.12 85.71
97.73 99.54
5.42 3.52 3.06
1-Jun 8-Jun
% REMAINING WORK
% ACTUAL PROGRESS
ACCELERATE PLAN REV.2
CUM. ACTUAL
ACCELERATE PLAN REV.2
CUM. ACTUAL
Page 1 of 6 Prepared By : Nattakarn S.
% Actual
% Plan % Actual % Var.
WHP 501 100.00% 100.00 97.21 -2.79
Noted :
1. This weekly progress status is based on Phase 50 : Project Accelerate Plan Rev.2
88.524.51 40.69 74.12
4.51 40.69 74.12 88.52
Cable Continuity Check 4.13% 100.00 92.58 -7.42
25.79 61.28 90.39 95.75
25.79
Tubing Leak Test 1.18% 100.00 95.75 -4.25
94.64 94.66 95.79 96.55 96.75 96.77 96.77 97.06 97.06 97.06 97.06 99.71 99.715.41 33.25 33.25 45.61 47.15 47.34 48.12 68.84 71.69 72.29 72.29 72.29 75.03 79.23 79.23 81.05 81.50 85.68 93.65 93.65 94.44
96.55 96.75 96.77 96.77 97.06 97.06 97.06 97.06 99.71 100.0068.84 71.69 72.29 72.29 72.29 75.03 79.23 79.23 81.05 81.50 85.68 93.65 93.65 94.44 94.64 94.66 95.79
99.59
Calibration of Instruments Tag 5.37% 100.00 100.00 0.00
5.41 33.25 33.25 45.61 47.15 47.34 48.12
20.44 29.65 36.28 47.69 51.68 58.40 62.64 67.09 71.66 80.56 87.15 88.14 92.02 92.02 92.11 97.11 99.091.17 2.12 2.12 2.29 2.29 3.86 3.86 12.99
47.69 51.68 58.40 62.64 67.09 71.66 80.56 87.15 88.14 92.02 92.02 92.11 97.11 99.09 100.001.17 2.12 2.12 2.29 2.29 3.86 3.86 12.99 20.44 29.65 36.28
Cables Installation
(Pulling, Glanding ,Termination)
34.40% 100.00 99.93 -0.07
81.6131.97 42.26 42.26 46.59 52.57 72.6029.40 29.42 30.19 30.30 31.09 31.9724.78 25.77 27.18 28.193.60 3.93 4.19 4.72 5.39 5.392.05 2.65 3.60
81.6131.97 42.26 42.26 46.59 52.57 72.6029.40 29.42 30.19 30.30
24.14 24.24
31.09 31.9724.14 24.24 24.78 25.77 27.18 28.193.60 3.93 4.19 4.72 5.39 5.392.05 2.65 3.60
Installation And Hook-Up of
E&I Tag Items
3.29% 100.00 98.38 -1.62
0.00 0.00
2.94
13.75 16.69
30-Sep 7-Oct
0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.00VARIANCE 0.00 0.00 0.00 0.00
3.48 3.122.53 0.99 4.02 0.00 2.09 5.241.52 2.34 1.76 3.83 1.89 6.090.00 4.76 3.10 4.07 2.70 3.661.63 1.24 0.42 0.24 0.28 1.322.24 2.30 2.55 0.21 1.240.89 0.44 0.96 4.29 2.59 4.39
0.00 0.00 0.00 0.00
ACTUAL 0.00 0.00 0.00 0.00 0.19
3.12 0.00 0.00 0.00 0.00 0.000.99 4.02 0.00 2.09 5.24 3.482.34 1.76 3.83 1.89 6.09 2.534.76 3.10 4.07 2.70 3.66 1.521.24 0.42 0.24 0.28 1.32 0.002.24 2.30 2.55 0.21 1.24 1.630.44 0.96 4.29 2.59 4.39 2.94
WEEKLY
PLANNED 0.00 0.00 0.00 0.00 0.19 0.89
0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.00
88.18 92.32 97.2173.62 73.6244.99 48.65 50.17 52.51
-2.41 -5.84 -2.79VARIANCE 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
75.71 80.9559.99 66.08 68.61 69.60 84.43 87.55
0.000.00 0.00 0.00 0.00 0.00 0.00
26.86 28.10 28.52 28.769.36 13.75 16.69 18.93 21.23 23.78
0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.00
0.00 0.19 1.08 1.52 2.48 6.77
25.23 26.86 28.10 28.52 28.76 29.04 100.00 100.00 100.00 100.00 100.000.19 1.08 1.52 2.48 6.77 9.36
54.27 58.1029.04 30.36 30.36 35.12 38.22 42.2925.23
100.0080.95 84.43 87.55 100.00 100.00 100.0066.08 68.61 69.60 73.62 73.62 75.71 100.00 100.00 100.00 100.0090.59 98.16 100.00 100.00
CUMULATIVE
ACCELERATE PLAN 0.00 0.00 0.00 0.00
ACTUAL 0.00 0.00 0.00 23.99
0.00 0.00
27-Apr 4-May 11-May 13-Jul
E&I AND PRE-COMMISSIONING WORKS PROGRESS
22-Jul 29-Jul 5-Aug 12-Aug 6-Jan 13-Jan 20-Jan 27-Jan11-Nov 18-Nov 25-Nov 2-Dec 9-Dec 16-Dec 16-Mar 23-Mar 30-Mar 6-Apr 13-Apr 20-Apr 18-May 25-May 1-Jun 8-Jun
18.93 21.23 23.78 23.99 48.65 50.17 52.51 54.27 58.10 59.9930.36 30.36 35.12 38.22 42.29 44.99
3-Feb 10-Feb23-Dec 30-Dec19-Aug 26-Aug 2-Sep 9-Sep 16-Sep 23-Sep 17-Feb 24-Feb 2-Mar 9-Mar14-Oct 21-Oct 28-Oct 4-Nov
Site Acceptance Test - SAT 22.20% 100.00 50.00 -50.00
Loop/Function Test 77.80% 100.00 90.00 -10.00
PRE-COMMISSIONING 9.41% 100.00 81.12 -18.88
50.04 50.04 61.00 74.68 80.52 92.464.65 5.42 8.10 26.48 29.40 33.480.80 2.04
50.04 50.04 61.00 74.68 80.52 100.004.65 5.42 8.10 26.48 29.40 33.480.80 2.04
Tubings Installation 16.56% 100.00 95.84 -4.16
99.02 99.02 99.38 99.71 99.71 100.0089.92 96.99 97.08 98.74 98.78 98.9985.50 88.58 89.28 89.46 89.74 89.7776.25 76.81 77.23 79.13 79.13 83.1459.61 67.59 67.96 68.62 72.09 74.957.80 21.33 28.64 38.19 47.44 52.590.61 3.41 4.79
99.02 99.02 99.38 99.717.80 21.33 28.64 38.19 47.44 52.590.61 3.41 4.79 99.71 100.0089.92 96.99 97.08 98.74 98.78 98.9985.50 88.58 89.28 89.46 89.74 89.7776.25 76.81 77.23 79.13 79.13 83.14
E&I Supports, Ladders and Trays 35.06% 100.00 100.00 0.00
59.61 67.59 67.96 68.62 72.09 74.95
E&I 90.59% 100.00 98.88 -1.12
23-Sep 30-Sep 7-Oct 14-Oct 24-Aug13-Jan 20-Jan 27-Jan 3-Feb 13-Jul 20-Jul 27-Jul 3-Aug 10-Aug 17-Aug6-Apr 13-Apr 20-Apr 27-Apr 4-May 11-May24-Feb 2-Mar 9-Mar 16-Mar 23-Mar 30-Mar29-Jul 5-Aug 12-Aug 19-Aug 26-Aug 2-Sep
CHEVRON : CVX-PHASE 50
E&I AND PRE-COMMISSIONING : WHP 501 PROGRESS S-CURVE
1-Jun-16
WBS WTG
Cumulative Progress
22-Jul 10-Feb 17-Feb2-Dec 9-Dec 16-Dec 23-Dec 30-Dec 6-Jan21-Oct 28-Oct 4-Nov 11-Nov 18-Nov 25-Nov9-Sep 16-Sep 31-Aug 7-Sep15-Jun 22-Jun 29-Jun 6-Jul
2015
15-Jun 22-Jun 29-Jun 6-Jul 3-Aug 10-Aug
0.00 0.00 0.00 0.00
17-Aug 24-Aug20-Jul 27-Jul 31-Aug 7-Sep
18-May 25-May 1-Jun 8-Jun
100.00
99.59 99.93 99.93
100.00
84.70 91.75 98.38
92.46 94.49 95.84
100.00
92.54 92.58 92.58
100.00
2016
2015 2016
3.04 7.57 1.84 0.00
0.63 4.14 4.89
-2.41 -3.43 3.05
100.00
43.76 90.00
100.00
50.00
% REMAINING WORK
% ACTUAL PROGRESS
ACCELERATE PLAN REV.2
CUM. ACTUAL
CUM. ACTUAL
ACCELERATE PLAN REV.2
Page 2 of 6 Prepared By : Nattakarn S.
% Actual
% Plan % Actual % Var.
WHP 503 100.00% 97.99 91.41 -6.58
Noted :
1. This weekly progress status is based on Phase 50 : Project Accelerate Plan Rev.2
0.00 0.00 0.00 -2.89 -0.80 -2.890.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.00
1.10 4.99 1.060.44 0.37 1.92 0.69 0.00 0.502.01 3.17 0.94 1.52 1.15 1.591.69 0.25 4.25 1.82 4.89 1.81
VARIANCE 0.00 0.00 0.00 0.00
4.94 1.31 4.382.76 0.00 0.82 5.34 10.15 6.032.30 2.16 2.53 1.58 2.33 1.690.19 2.21 4.23
0.00 0.00
ACTUAL 0.00 0.00 0.00 0.00 0.11 0.18 0.01
0.00 0.00 0.00 0.00 0.00 0.002.01 0.00 0.00 0.00 0.00 0.005.34 10.15 6.03 7.83 2.11 7.271.58 2.33 1.69 2.76 0.00 0.821.10 4.99 1.06 2.30 2.16 2.530.69 0.00 0.50 0.19 2.21 4.231.52 1.15 1.59 0.44 0.37 1.921.82 4.89 1.81 2.01 3.17 0.940.11 0.18 0.01 1.69 0.25 4.25
WEEKLY
PLANNED 0.00 0.00 0.00 0.00
-3.69 -6.580.00 0.00 0.00 0.00 0.00 -2.890.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.00VARIANCE 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
74.75 80.78 85.72 87.03 91.4153.99 55.68 58.44 58.44 59.26 64.6042.03 43.09 45.39 47.55 50.08 51.6628.81 29.31 29.50 31.71 35.94 37.0423.80 25.39 25.83 26.20 28.12 28.8113.20 15.01 17.02 20.19 21.13 22.650.29 0.30 1.99 2.24 6.49 8.31ACTUAL 0.00 0.00 0.00 0.00 0.11
100.00 100.00 100.00 100.00 100.00 100.00100.00 100.00 100.00 100.00 100.00 100.0080.78 88.61 90.72 97.99 100.00 100.0055.68 58.44 58.44 59.26 64.60 74.7543.09 45.39 47.55 50.08 51.66 53.9929.31 29.50 31.71 35.94 37.04 42.0325.39 25.83 26.20 28.12 28.81 28.8115.01 17.02 20.19 21.13 22.65 23.800.30 1.99 2.24 6.49 8.31 13.20
31-Aug 7-Sep
CUMULATIVE
ACCELERATE PLAN 0.00 0.00 0.00 0.00 0.11 0.29
20-Jul 27-Jul 3-Aug 10-Aug 17-Aug 24-Aug8-Jun 15-Jun 22-Jun 29-Jun 6-Jul 13-Jul27-Apr 4-May 11-May 18-May 25-May 1-Jun16-Mar 23-Mar 30-Mar 6-Apr 13-Apr 20-Apr3-Feb 10-Feb 17-Feb 24-Feb 2-Mar 9-Mar23-Dec 30-Dec 6-Jan 13-Jan 20-Jan 27-Jan11-Nov 18-Nov 25-Nov 2-Dec 9-Dec 16-Dec30-Sep 7-Oct 14-Oct 21-Oct 28-Oct 4-Nov19-Aug 26-Aug 2-Sep 9-Sep 16-Sep 23-Sep
E&I AND PRE-COMMISSIONING WORKS PROGRESS
22-Jul 29-Jul 5-Aug 12-Aug
100.00
0.00Site Acceptance Test - SAT 22.20% 0.00 0.00
38.53
100.00
Loop/Function Test 77.80% 100.00 38.53 -61.47
PRE-COMMISSIONING 9.41% 78.66 29.98 -48.68
91.12
100.00
-8.88Tubing Leak Test 1.18% 100.00 91.12
83.32 86.63 87.7234.70 52.22 74.36
34.70 52.22 74.36 95.58 100.00
Cable Continuity Check 4.13% 100.00 87.72 -12.28
45.55 48.95 72.07 73.80 79.4930.09 30.09 40.38 40.38 40.38 43.5626.66 26.96 27.10 27.16 27.41 28.224.79 5.60 5.60 20.20 25.44 25.772.38 3.31 3.31 3.31 4.51 4.79
25.77 26.66 26.963.31 3.31 4.51 4.79 4.79 5.602.38 3.31 77.68 100.0040.38 40.38 40.38 43.56 45.55 48.9527.10 27.16 27.41 28.22 30.09 30.095.60 20.20 25.44
Installation And Hook-Up of
E&I Tag Items
3.29% 100.00 79.49 -20.51
95.295.92 8.06 44.91 65.45 85.73 92.810.74 0.74 0.74 1.02 4.33 4.330.46 0.46 0.46 0.74
44.91 65.45 99.60 100.000.74 1.02 4.33 4.33 5.92 8.060.46 0.46 0.46 0.74 0.74 0.74
-4.71Tubings Installation 16.56% 100.00 95.29
99.33 99.58 99.5866.02 66.02 67.48 77.90 90.43 96.9437.05 40.86 48.24 50.74 57.61 61.874.02 4.02 10.25 12.22 27.45 30.790.61 1.56 3.76 4.00 4.00 4.020.61 0.61
67.48 77.90 90.43 96.94 99.94 100.0048.24 50.74 57.61 61.87 66.02 66.0210.25 12.22 27.45 30.79 37.05 40.863.76 4.00 4.00 4.02 4.02 4.020.61 0.61 0.61 1.56
Cables Installation
(Pulling, Glanding ,Termination)
34.40% 100.00 99.58 -0.42
100.0099.11 99.30 99.78 99.78 99.78 99.9878.07 80.86 81.12 81.19 96.19 98.3150.55 69.99 72.29 72.29 75.03 78.0733.76 36.87 36.87 46.31 47.09 48.140.78 6.01
98.31 99.11 99.3072.29 72.29 75.03 78.07 78.07 80.8636.87 46.31 47.09 48.14 50.55 69.99 99.78 99.78 99.78 99.98 100.0081.12 81.19 96.190.78 6.01 33.76 36.87
Calibration of Instruments Tag 5.37% 100.00 100.00 0.00
98.46 99.62 99.63 99.63 100.0092.12 94.53 94.95 95.93 98.04 98.0485.94 87.14 87.46 87.49 88.50 91.4172.91 74.35 74.35 75.41 75.95 81.5459.31 63.94 66.34 68.28 69.31 69.5620.30 25.23 36.39 41.61 47.94 56.460.33 0.91 0.95 6.28 7.04
99.63 100.0094.95 95.93 98.04 98.04 98.46 99.6287.46 87.49 88.50 91.41 92.12 94.5374.35 75.41 75.95 81.54 85.94 87.1466.34 68.28 69.31 69.56 72.91 74.3536.39 41.61 47.94 56.46 59.31 63.940.91 0.95 6.28 7.04 20.30 25.23
0.00
0.33
E&I Supports, Ladders and Trays 35.06% 100.00 100.00
23-Mar
E&I 90.59% 100.00 97.79 -2.21
22-Jun 24-Aug 31-Aug 7-Sep3-Feb 10-Feb 17-Feb2-Dec 9-Dec 16-Dec 23-Dec 30-Dec 6-Jan21-Oct 28-Oct 4-Nov 11-Nov 18-Nov 25-Nov 13-Jan 20-Jan 27-Jan 6-Apr 13-Apr 20-Apr 27-Apr 4-May 11-May24-Feb 2-Mar 9-Mar 16-Mar
CHEVRON : CVX-PHASE 50
E&I AND PRE-COMMISSIONING : WHP 503 PROGRESS S-CURVE
1-Jun-16
WBS WTG
Cumulative Progress
22-Jul 29-Jun 6-Jul 10-Aug 17-Aug
2015 2016
2015 2016
13-Jul30-Mar9-Sep 16-Sep 23-Sep 30-Sep 7-Oct 14-Oct29-Jul 5-Aug 12-Aug 19-Aug 26-Aug 2-Sep 20-Jul 27-Jul 3-Aug18-May 25-May 1-Jun 8-Jun 15-Jun
% REMAINING WORK
% ACTUAL PROGRESS
ACCELERATE PLAN REV.2
CUM. ACTUAL
CUM. ACTUAL
ACCELERATE PLAN REV.2
Page 3 of 6 Prepared By : Nattakarn S.
% Actual
% Plan % Actual % Var.
WHP 504 100.00% 94.23 87.30 -6.93
Noted :
1. This weekly progress status is based on Phase 50 : Project Accelerate Plan Rev.2
0.00 0.00 0.00 -2.87 -0.32 -0.080.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.00
0.25 0.54 1.963.21 0.34 1.25 1.08 0.00 1.413.89 2.74 3.07 1.48 1.57 1.480.00 1.30 0.73 1.63 2.97 1.51
VARIANCE 0.00 0.00 0.00 0.00
10.09 5.48 1.061.21 0.00 2.04 1.66 5.96 8.504.16 4.03 1.63 2.74 0.41 2.090.44 1.43 1.79
0.00 0.00
ACTUAL 0.00 0.00 0.00 0.00 0.00 0.14 0.03
0.00 0.00 0.00 0.00 0.00 0.007.48 1.95 0.00 0.00 0.00 0.001.66 5.96 8.50 12.96 5.80 1.142.74 0.41 2.09 1.21 0.00 2.040.25 0.54 1.96 4.16 4.03 1.631.08 0.00 1.41 0.44 1.43 1.791.48 1.57 1.48 3.21 0.34 1.251.63 2.97 1.51 3.89 2.74 3.070.00 0.14 0.03 0.00 1.30 0.73
WEEKLY
PLANNED 0.00 0.00 0.00 0.00
-3.19 -3.270.00 0.00 0.00 0.00 0.00 -2.870.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.00VARIANCE 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
62.17 70.67 80.76 86.24 87.3049.21 51.30 52.51 52.51 54.55 56.2134.28 36.24 40.40 44.43 46.06 48.8028.42 29.83 30.27 31.70 33.49 33.7421.06 22.54 25.75 26.09 27.34 28.426.80 8.31 12.20 14.94 18.01 19.490.14 0.17 0.17 1.47 2.20 3.83ACTUAL 0.00 0.00 0.00 0.00 0.00
100.00 100.00 100.00 100.00 100.00 100.00100.00 100.00 100.00 100.00 100.00 100.0070.67 83.63 89.43 90.57 98.05 100.0051.30 52.51 52.51 54.55 56.21 62.1736.24 40.40 44.43 46.06 48.80 49.2129.83 30.27 31.70 33.49 33.74 34.2822.54 25.75 26.09 27.34 28.42 28.428.31 12.20 14.94 18.01 19.49 21.060.17 0.17 1.47 2.20 3.83 6.80
31-Aug 7-Sep
CUMULATIVE
ACCELERATE PLAN 0.00 0.00 0.00 0.00 0.00 0.14
20-Jul 27-Jul 3-Aug 10-Aug 17-Aug 24-Aug8-Jun 15-Jun 22-Jun 29-Jun 6-Jul 13-Jul27-Apr 4-May 11-May 18-May 25-May 1-Jun16-Mar 23-Mar 30-Mar 6-Apr 13-Apr 20-Apr3-Feb 10-Feb 17-Feb 24-Feb 2-Mar 9-Mar23-Dec 30-Dec 6-Jan 13-Jan 20-Jan 27-Jan11-Nov 18-Nov 25-Nov 2-Dec 9-Dec 16-Dec30-Sep 7-Oct 14-Oct 21-Oct 28-Oct 4-Nov19-Aug 26-Aug 2-Sep 9-Sep 16-Sep 23-Sep
E&I AND PRE-COMMISSIONING WORKS PROGRESS
22-Jul 29-Jul 5-Aug 12-Aug
100.00
0.00Site Acceptance Test - SAT 22.20% 0.00 0.00
100.00
Loop/Function Test 77.80% 0.00 0.00 0.00
PRE-COMMISSIONING 9.41% 38.90 0.00 -38.90
98.77 100.00
-100.00Tubing Leak Test 1.18% 100.00 0.00
56.88 85.43 85.580.90 0.90 0.90
100.000.90 0.90 0.90 63.82 97.54
Cable Continuity Check 4.13% 100.00 85.58 -14.42
44.15 47.44 50.57 56.88 81.3728.03 29.68 40.29 40.29 40.29 43.2925.61 26.69 26.98 26.98 27.41 28.033.81 5.10 5.10 23.42 24.66 24.713.64 3.72 3.72 3.81
24.71 25.61 26.693.64 3.72 3.72 3.81 3.81 5.10 55.61 75.16 100.0040.29 40.29 40.29 43.29 44.15 47.4426.98 26.98 27.41 28.03 28.03 29.685.10 23.42 24.66
Installation And Hook-Up of
E&I Tag Items
3.29% 100.00 81.37 -18.63
93.350.77 0.86 32.65 61.61 80.91 91.200.48 0.48 0.48 0.64 0.77 0.770.48
32.65 61.61 92.15 100.000.48 0.64 0.77 0.77 0.77 0.860.48 0.48 0.48
-6.65Tubings Installation 16.56% 100.00 93.35
90.98 99.58 99.5850.31 50.31 55.92 58.53 62.30 75.3123.14 30.12 34.72 41.16 42.33 47.915.21 5.21 6.25 6.25 6.41 10.332.40 2.67 2.67 4.26 4.26 5.21
55.92 58.53 62.30 75.31 93.47 100.0034.72 41.16 42.33 47.91 50.31 50.316.25 6.25 6.41 10.33 23.14 30.122.67 4.26 4.26 5.21 5.21 5.212.40 2.67
Cables Installation
(Pulling, Glanding ,Termination)
34.40% 100.00 99.58 -0.42
99.78 99.78 99.98 100.0099.19 99.19 99.78 99.78 99.78 99.7893.53 94.63 95.29 98.44 99.19 99.1978.21 81.24 81.48 81.54 91.83 91.8350.16 50.53 62.12 62.51 73.06 78.2133.25 36.87 36.87 46.31 46.90 48.140.78 5.50
91.83 93.53 94.6362.12 62.51 73.06 78.21 78.21 81.2436.87 46.31 46.90 48.14 50.16 50.53 99.88 100.0099.78 99.78 99.78 99.78 99.78 99.7895.29 98.44 99.19 99.19 99.19 99.1981.48 81.54 91.830.78 5.50 33.25 36.87
Calibration of Instruments Tag 5.37% 100.00 100.00 0.00
97.44 99.65 99.65 99.65 100.0092.93 95.18 95.34 96.19 96.51 96.5182.91 83.69 84.89 86.94 87.34 92.4671.90 72.94 72.94 75.86 77.21 80.0049.50 53.97 58.60 63.20 68.85 69.596.82 11.21 16.31 20.50 32.77 39.930.44 0.52 0.52 4.63
99.65 100.0095.34 96.19 96.51 96.51 97.44 99.6584.89 86.94 87.34 92.46 92.93 95.1872.94 75.86 77.21 80.00 82.91 83.6958.60 63.20 68.85 69.59 71.90 72.9416.31 20.50 32.77 39.93 49.50 53.970.44 0.52 0.52 4.63 6.82 11.21
0.00E&I Supports, Ladders and Trays 35.06% 100.00 100.00
23-Mar
E&I 90.59% 99.97 96.37 -3.61
22-Jun 24-Aug 31-Aug 7-Sep3-Feb 10-Feb 17-Feb2-Dec 9-Dec 16-Dec 23-Dec 30-Dec 6-Jan21-Oct 28-Oct 4-Nov 11-Nov 18-Nov 25-Nov 13-Jan 20-Jan 27-Jan 6-Apr 13-Apr 20-Apr 27-Apr 4-May 11-May24-Feb 2-Mar 9-Mar 16-Mar
CHEVRON : CVX-PHASE 50
E&I AND PRE-COMMISSIONING : WHP 504 PROGRESS S-CURVE
1-Jun-16
WBS WTG
Cumulative Progress
22-Jul 29-Jun 6-Jul 10-Aug 17-Aug
2015 2016
2015 2016
13-Jul30-Mar9-Sep 16-Sep 23-Sep 30-Sep 7-Oct 14-Oct29-Jul 5-Aug 12-Aug 19-Aug 26-Aug 2-Sep 20-Jul 27-Jul 3-Aug18-May 25-May 1-Jun 8-Jun 15-Jun
% REMAINING WORK
% ACTUAL PROGRESS
ACCELERATE PLAN REV.2
CUM. ACTUAL
CUM. ACTUAL
ACCELERATE PLAN REV.2
Page 4 of 6 Prepared By : Nattakarn S.
% Actual
% Plan % Actual % Var.
WHP 502 100.00% 88.80 85.71 -3.10
Noted :
1. This weekly progress status is based on Phase 50 : Project Accelerate Plan Rev.2
0.00 0.00 0.00 -5.58 2.03 0.450.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.00
3.84 1.94 2.410.89 0.91 0.40 1.00 0.00 0.910.73 1.56 2.42 0.94 0.96 1.460.57 3.74 2.63 3.51 3.46 3.08
VARIANCE 0.00 0.00 0.00 0.00
3.41 5.18 2.591.73 0.00 1.32 3.13 4.86 2.761.84 3.35 1.54 1.92 2.23 1.511.91 4.22 3.33
0.00 0.00
ACTUAL 0.00 0.00 0.00 0.00 0.19 0.72 0.61
0.00 0.00 0.00 0.00 0.00 0.001.79 7.46 1.95 0.00 0.00 0.003.13 4.86 2.76 8.99 3.15 2.141.92 2.23 1.51 1.73 0.00 1.323.84 1.94 2.41 1.84 3.35 1.541.00 0.00 0.91 1.91 4.22 3.330.94 0.96 1.46 0.89 0.91 0.403.51 3.46 3.08 0.73 1.56 2.420.19 0.72 0.61 0.57 3.74 2.63
WEEKLY
PLANNED 0.00 0.00 0.00 0.00
-3.54 -3.090.00 0.00 0.00 0.00 0.00 -5.580.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.00VARIANCE 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
71.77 74.53 77.94 83.12 85.7159.22 60.73 62.46 62.46 63.78 66.9145.93 48.34 50.18 53.53 55.07 56.9929.78 30.69 32.60 36.82 40.15 43.9925.12 26.58 27.47 28.38 28.78 29.7815.43 18.51 19.24 20.80 23.22 24.160.91 1.52 2.09 5.83 8.46 11.97ACTUAL 0.00 0.00 0.00 0.00 0.19
100.00 100.00 100.00 100.00 100.00 100.00100.00 100.00 100.00 100.00 100.00 100.0074.53 83.52 86.66 88.80 90.59 98.0560.73 62.46 62.46 63.78 66.91 71.7748.34 50.18 53.53 55.07 56.99 59.2230.69 32.60 36.82 40.15 43.99 45.9326.58 27.47 28.38 28.78 29.78 29.7818.51 19.24 20.80 23.22 24.16 25.121.52 2.09 5.83 8.46 11.97 15.43
31-Aug 7-Sep
CUMULATIVE
ACCELERATE PLAN 0.00 0.00 0.00 0.00 0.19 0.91
20-Jul 27-Jul 3-Aug 10-Aug 17-Aug 24-Aug8-Jun 15-Jun 22-Jun 29-Jun 6-Jul 13-Jul27-Apr 4-May 11-May 18-May 25-May 1-Jun16-Mar 23-Mar 30-Mar 6-Apr 13-Apr 20-Apr3-Feb 10-Feb 17-Feb 24-Feb 2-Mar 9-Mar23-Dec 30-Dec 6-Jan 13-Jan 20-Jan 27-Jan11-Nov 18-Nov 25-Nov 2-Dec 9-Dec 16-Dec30-Sep 7-Oct 14-Oct 21-Oct 28-Oct 4-Nov19-Aug 26-Aug 2-Sep 9-Sep 16-Sep 23-Sep
E&I AND PRE-COMMISSIONING WORKS PROGRESS
22-Jul 29-Jul 5-Aug 12-Aug
100.00
0.00Site Acceptance Test - SAT 22.20% 0.00 0.00
100.00
Loop/Function Test 77.80% 0.00 0.00 0.00
PRE-COMMISSIONING 9.41% 0.00 0.00 0.00
46.48 100.00
-46.48Tubing Leak Test 1.18% 46.48 0.00
4.17 41.67 71.674.17 4.17
91.21 100.004.17 4.17 46.53 70.75
Cable Continuity Check 4.13% 91.21 71.67 -19.53
46.77 58.55 59.99 60.44 60.4430.75 30.75 41.15 41.15 41.15 42.1626.83 27.19 27.24 29.27 29.60 30.755.48 5.55 23.94 24.38 25.36 26.533.15 3.45 4.39 4.40 4.50 5.482.81 3.15
26.53 26.83 27.194.39 4.40 4.50 5.48 5.48 5.552.81 3.15 3.15 3.45 65.38 72.38 81.46 100.0041.15 41.15 41.15 42.16 46.77 58.5527.24 29.27 29.60 30.75 30.75 30.7523.94 24.38 25.36
Installation And Hook-Up of
E&I Tag Items
3.29% 81.46 60.44 -21.03
92.447.90 13.74 39.44 48.65 69.17 87.171.59 2.36 2.36 2.36 6.83 6.830.71 1.22 1.22 1.41
39.44 48.65 89.45 99.65 100.002.36 2.36 6.83 6.83 7.90 13.740.71 1.22 1.22 1.41 1.59 2.36
-7.56Tubings Installation 16.56% 100.00 92.44
93.40 96.83 98.5877.35 77.35 80.46 86.88 89.17 92.4753.17 55.31 59.90 63.92 70.98 75.314.16 15.22 23.21 34.88 40.40 47.801.09 2.70 2.70 4.14 4.14 4.160.61 0.84 1.09
100.0080.46 86.88 89.17 92.47 95.73 97.2559.90 63.92 70.98 75.31 77.35 77.3523.21 34.88 40.40 47.80 53.17 55.312.70 4.14 4.14 4.16 4.16 15.220.61 0.84 1.09 1.09 2.70
Cables Installation
(Pulling, Glanding ,Termination)
34.40% 100.00 98.58 -1.42
98.38 98.38 100.0093.83 94.02 94.39 96.65 98.16 98.3678.78 80.47 80.97 85.05 91.37 93.4961.43 70.22 71.77 71.77 74.52 78.7833.76 36.87 36.87 46.31 47.61 47.635.41 33.76
93.49 93.83 94.0271.77 71.77 74.52 78.78 78.78 80.4736.87 46.31 47.61 47.63 61.43 70.22 100.0094.39 96.65 98.16 98.36 98.38 98.3880.97 85.05 91.375.41 33.76 33.76 36.87
Calibration of Instruments Tag 5.37% 100.00 100.00 0.00
100.0098.92 99.61 99.61 99.61 99.61 99.6196.02 97.64 97.72 98.23 98.33 98.3387.23 87.44 87.73 87.75 88.22 96.0276.12 77.11 77.11 79.67 83.88 85.6665.55 67.85 68.55 71.53 73.99 75.2825.80 32.52 43.40 52.61 54.91 58.390.61 2.87 4.79 6.57 18.34
99.61 99.61 99.80 99.91 100.0097.72 98.23 98.33 98.33 98.92 99.6187.73 87.75 88.22 96.02 96.02 97.6477.11 79.67 83.88 85.66 87.23 87.4468.55 71.53 73.99 75.28 76.12 77.1143.40 52.61 54.91 58.39 65.55 67.852.87 4.79 6.57 18.34 25.80 32.52
0.00
0.61
E&I Supports, Ladders and Trays 35.06% 100.00 100.00
23-Mar
E&I 90.59% 98.02 94.61 -3.42
22-Jun 24-Aug 31-Aug 7-Sep3-Feb 10-Feb 17-Feb2-Dec 9-Dec 16-Dec 23-Dec 30-Dec 6-Jan21-Oct 28-Oct 4-Nov 11-Nov 18-Nov 25-Nov 13-Jan 20-Jan 27-Jan 6-Apr 13-Apr 20-Apr 27-Apr 4-May 11-May24-Feb 2-Mar 9-Mar 16-Mar
CHEVRON : CVX-PHASE 50
E&I AND PRE-COMMISSIONING : WHP 502 PROGRESS S-CURVE
1-Jun-16
WBS WTG
Cumulative Progress
22-Jul 29-Jun 6-Jul 10-Aug 17-Aug
2015 2016
2015 2016
13-Jul30-Mar9-Sep 16-Sep 23-Sep 30-Sep 7-Oct 14-Oct29-Jul 5-Aug 12-Aug 19-Aug 26-Aug 2-Sep 20-Jul 27-Jul 3-Aug18-May 25-May 1-Jun 8-Jun 15-Jun
% REMAINING WORK
% ACTUAL PROGRESS
ACCELERATE PLAN REV.2
CUM. ACTUAL
CUM. ACTUAL
ACCELERATE PLAN REV.2
Page 5 of 6 Prepared By : Nattakarn S.
% Actual
% Plan % Actual % Var.
WHP 505 100.00% 84.94 79.13 -5.81
Noted :
1. This weekly progress status is based on Phase 50 : Project Accelerate Plan Rev.2
0.00 0.00 0.00 -6.56 -0.10 0.850.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.00
0.34 0.73 2.710.44 2.82 2.40 0.66 0.00 2.282.76 2.25 2.06 1.42 4.98 0.070.00 1.30 0.50 0.80 1.93 2.38
VARIANCE 0.00 0.00 0.00 0.00
7.97 8.39 6.051.81 0.00 0.79 3.84 0.21 0.062.18 1.68 1.54 1.54 2.84 3.361.01 0.55 2.31
0.00 0.00
ACTUAL 0.00 0.00 0.00 0.00 0.00 0.14 0.03
0.00 0.00 0.00 0.00 0.00 0.004.03 1.62 7.10 2.30 0.00 0.003.84 0.21 0.06 14.53 8.49 5.201.54 2.84 3.36 1.81 0.00 0.790.34 0.73 2.71 2.18 1.68 1.540.66 0.00 2.28 1.01 0.55 2.311.42 4.98 0.07 0.44 2.82 2.400.80 1.93 2.38 2.76 2.25 2.060.00 0.14 0.03 0.00 1.30 0.50
WEEKLY
PLANNED 0.00 0.00 0.00 0.00
-6.66 -5.810.00 0.00 0.00 0.00 0.00 -6.560.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.00VARIANCE 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
56.66 56.72 64.69 73.08 79.1346.65 50.01 51.82 51.82 52.61 56.4534.16 36.87 39.05 40.73 42.27 43.8126.94 29.22 30.23 30.78 33.09 33.4320.55 20.62 21.06 23.88 26.28 26.944.70 7.08 9.84 12.09 14.15 15.570.14 0.17 0.17 1.47 1.97 2.77ACTUAL 0.00 0.00 0.00 0.00 0.00
100.00 100.00 100.00 100.00 100.00 100.0097.70 100.00 100.00 100.00 100.00 100.0056.72 71.25 79.74 84.94 88.97 90.5950.01 51.82 51.82 52.61 56.45 56.6636.87 39.05 40.73 42.27 43.81 46.6529.22 30.23 30.78 33.09 33.43 34.1620.62 21.06 23.88 26.28 26.94 26.947.08 9.84 12.09 14.15 15.57 20.550.17 0.17 1.47 1.97 2.77 4.70
31-Aug 7-Sep
CUMULATIVE
ACCELERATE PLAN 0.00 0.00 0.00 0.00 0.00 0.14
20-Jul 27-Jul 3-Aug 10-Aug 17-Aug 24-Aug8-Jun 15-Jun 22-Jun 29-Jun 6-Jul 13-Jul27-Apr 4-May 11-May 18-May 25-May 1-Jun16-Mar 23-Mar 30-Mar 6-Apr 13-Apr 20-Apr3-Feb 10-Feb 17-Feb 24-Feb 2-Mar 9-Mar23-Dec 30-Dec 6-Jan 13-Jan 20-Jan 27-Jan11-Nov 18-Nov 25-Nov 2-Dec 9-Dec 16-Dec30-Sep 7-Oct 14-Oct 21-Oct 28-Oct 4-Nov19-Aug 26-Aug 2-Sep 9-Sep 16-Sep 23-Sep
E&I AND PRE-COMMISSIONING WORKS PROGRESS
22-Jul 29-Jul 5-Aug 12-Aug
100.00
0.00Site Acceptance Test - SAT 22.20% 0.00 0.00
100.00
Loop/Function Test 77.80% 0.00 0.00 0.00
PRE-COMMISSIONING 9.41% 0.00 0.00 0.00
100.0071.13
0.00Tubing Leak Test 1.18% 0.00 0.00
3.12 3.12 30.133.12 3.12
77.54 94.52 100.003.12 3.12 34.82 58.79
Cable Continuity Check 4.13% 77.54 30.13 -47.41
41.79 43.44 46.19 49.19 49.4027.12 27.12 38.48 38.48 38.48 41.0424.90 24.90 26.07 26.11 26.25 27.123.88 5.12 5.12 5.12 21.07 23.820.44 3.88 3.88
23.82 24.90 24.900.44 3.88 3.88 3.88 5.12 48.99 55.74 63.43 79.26 100.0038.48 38.48 38.48 41.04 41.79 43.4426.07 26.11 26.25 27.12 27.12 27.125.12 5.12 21.07
Installation And Hook-Up of
E&I Tag Items
3.29% 63.43 49.40 -14.03
77.1442.79 65.39
36.73 67.22 85.06 100.00
-7.92Tubings Installation 16.56% 85.06 77.14
65.05 80.79 90.9048.02 48.02 50.47 60.14 60.36 60.3620.14 20.65 24.27 24.48 33.36 43.635.70 6.69 8.07 8.07 8.76 14.851.01 2.70 2.73 2.73 4.70
96.62 100.0050.47 60.14 60.36 60.36 83.20 91.5424.27 24.48 33.36 43.63 48.02 48.028.07 8.07 8.76 14.85 20.14 20.652.70 2.73 2.73 4.70 5.70 6.691.01
Cables Installation
(Pulling, Glanding ,Termination)
34.40% 96.62 90.90 -5.72
99.56 99.76 99.98 100.0098.08 98.34 99.13 99.13 99.13 99.5690.98 91.32 92.72 95.82 97.44 97.8772.95 76.38 76.99 77.06 86.96 86.9646.59 47.17 47.30 56.96 63.17 72.9533.25 36.89 36.89 37.08 44.60 44.820.78 5.50
86.96 90.98 91.3247.30 56.96 63.17 72.95 72.95 76.3836.89 37.08 44.60 44.82 46.59 47.17 99.77 99.77 100.0099.13 99.13 99.13 99.56 99.56 99.7692.72 95.82 97.44 97.87 98.08 98.3476.99 77.06 86.960.78 5.50 33.25 36.89
Calibration of Instruments Tag 5.37% 100.00 100.00 0.00
100.0097.30 99.61 99.61 99.61 99.61 99.6191.85 96.35 96.56 97.00 97.22 97.2280.96 81.77 82.66 85.16 86.52 90.8270.04 70.59 70.59 75.18 77.29 78.0437.70 48.44 57.56 57.68 59.06 65.416.08 7.88 9.69 16.63 25.32 32.370.44 0.52 0.52 4.63
99.61 99.61 99.99 99.99 100.0096.56 97.00 97.22 97.22 97.30 99.6182.66 85.16 86.52 90.82 91.85 96.3570.59 75.18 77.29 78.04 80.96 81.7757.56 57.68 59.06 65.41 70.04 70.599.69 16.63 25.32 32.37 37.70 48.440.44 0.52 0.52 4.63 6.08 7.88
0.00E&I Supports, Ladders and Trays 35.06% 100.00 100.00
23-Mar
E&I 90.59% 93.76 87.35 -6.41
22-Jun 24-Aug 31-Aug 7-Sep3-Feb 10-Feb 17-Feb2-Dec 9-Dec 16-Dec 23-Dec 30-Dec 6-Jan21-Oct 28-Oct 4-Nov 11-Nov 18-Nov 25-Nov 13-Jan 20-Jan 27-Jan 6-Apr 13-Apr 20-Apr 27-Apr 4-May 11-May24-Feb 2-Mar 9-Mar 16-Mar
CHEVRON : CVX-PHASE 50
E&I AND PRE-COMMISSIONING : WHP 505 PROGRESS S-CURVE
1-Jun-16
WBS WTG
Cumulative Progress
22-Jul 29-Jun 6-Jul 10-Aug 17-Aug
2015 2016
2015 2016
13-Jul30-Mar9-Sep 16-Sep 23-Sep 30-Sep 7-Oct 14-Oct29-Jul 5-Aug 12-Aug 19-Aug 26-Aug 2-Sep 20-Jul 27-Jul 3-Aug18-May 25-May 1-Jun 8-Jun 15-Jun
% REMAINING WORK
% ACTUAL PROGRESS
ACCELERATE PLAN REV.2
CUM. ACTUAL
CUM. ACTUAL
ACCELERATE PLAN REV.2
Page 6 of 6 Prepared By : Nattakarn S.
Activity ID Activity Name Num. Budgeted Units Planned Start Planned Finish % Actual 1-Jun-16
L5 L4 L5 L4 L5 L4
1295 3723 14-Aug-15 9-Oct-15 57
501-FAEI-17840 Fabrication of E&I Supports for Sub-Cellar Deck 31 Ea. 50.170 98 2.63% 8-Sep-15 23-Sep-15 16 100.00% 100.00% Completed
501-FAEI-17850 Fabrication of E&I Supports for Cellar Deck 663 Ea. 50.170 1915 51.44% 14-Aug-15 9-Oct-15 57 100.00% 100.00% Completed
501-FAEI-17860 Fabrication of E&I Supports for Mezzanine Deck 243 Ea. 50.170 525 14.10% 2-Sep-15 3-Oct-15 32 100.00% 100.00% Completed
501-FAEI-17870 Fabrication of E&I Supports for Upper Deck 358 Ea. 50.170 1185 31.83% 24-Aug-15 2-Oct-15 40 100.00% 100.00% Completed
4719 9-Sep-15 8-Apr-16 213
1295 3250 9-Sep-15 25-Jan-16 139
31 106 3.26% 8-Dec-15 5-Jan-16 29 100.00% 100.00%
501-FAEI-17880 Installation of E&I Support at Sub-Cellar Deck - Assembly Bay 1 Ea. 50.170 12 11.32% 25-Dec-15 5-Jan-16 12 100.00% 100.00% Completed
501-FAEI-17890 Installation of E&I Support at Sub-Cellar Deck - Erection Area 30 Ea. 50.170 94 88.68% 8-Dec-15 25-Dec-15 18 100.00% 100.00% Completed
663 1614 49.66% 9-Sep-15 21-Nov-15 74 100.00% 100.00%
501-FAEI-17900 Installation of E&I Support at Cellar Deck - Assembly Bay 475 Ea. 50.170 1035 64.13% 9-Sep-15 2-Oct-15 24 100.00% 100.00% Completed
501-FAEI-17910 Installation of E&I Support at Cellar Deck - Erection Area 188 Ea. 50.170 579 35.87% 24-Oct-15 21-Nov-15 29 100.00% 100.00% Completed
243 546 16.80% 29-Sep-15 25-Jan-16 119 100.00% 100.00%
501-FAEI-17920 Installation of E&I Support at Mezzanine Deck - Assembly Bay 37 Ea. 50.170 118 21.61% 29-Sep-15 15-Oct-15 17 100.00% 100.00% Completed
501-FAEI-17930 Installation of E&I Support at Mezzanine Deck - Erection Area 206 Ea. 50.170 428 78.39% 29-Dec-15 25-Jan-16 28 100.00% 100.00% Completed
358 984 30.28% 16-Oct-15 11-Jan-16 88 100.00% 100.00%
501-FAEI-17940 Installation of E&I Support at UpperDeck - Assembly Bay 273 Ea. 50.170 662 67.28% 16-Oct-15 10-Nov-15 26 100.00% 100.00% Completed
501-FAEI-17950 Installation of E&I Support at UpperDeck - Erection Area 85 Ea. 50.170 322 32.72% 13-Nov-15 11-Jan-16 60 100.00% 100.00% Completed
779 1469 24-Oct-15 8-Apr-16 168
501-FAEI-17960 Installation of Cable Trays&Ladders 670 m. 50.170 942 64.13% 24-Oct-15 1-Feb-16 101 100.00% 100.00% Completed
501-FAEI-17970 Installation of Tubing Trays&Ladders 109 m. 50.170 527 35.87% 4-Mar-16 8-Apr-16 36 100.00% 100.00% Completed
8442 0.00%
L5 L4 L5 L4 L5 L4
312 905 24-Oct-15 19-Jan-16 88
312 905 24-Oct-15 19-Jan-16 88
501-FAEI-17980 Calibration of Instrument Tags - 01-I1: Process Production 193 Ea. 50.165 535 59.12% 24-Oct-15 18-Dec-15 56 100.00% 100.00% Completed
501-FAEI-17990 Calibration of Instrument Tags - 01-I2 : Production Header 28 Ea. 50.165 76 8.40% 11-Nov-15 24-Nov-15 14 100.00% 100.00% Completed
501-FAEI-18000 Calibration of Instrument Tags - 02-I1 : Test Separator 50 Ea. 50.165 140 15.47% 24-Nov-15 22-Dec-15 29 100.00% 100.00% Completed
501-FAEI-18010 Calibration of Instrument Tags - 03-I1 : Pig Luncher 1 Ea. 50.165 3 0.33% 12-Dec-15 15-Dec-15 4 100.00% 100.00% Completed
501-FAEI-18020 Calibration of Instrument Tags - 03-I2 : Pig Receiver - Option 14 Ea. 50.165 76 8.40% 15-Jan-16 19-Jan-16 5 100.00% 100.00% Completed
501-FAEI-18050 Calibration of Instrument Tags - 10-I1 : Booster Compressor 26 Ea. 50.165 75 8.29% 22-Dec-15 6-Jan-16 16 100.00% 100.00% Completed
14 38 24-Oct-15 13-Nov-15 21
8 22 24-Oct-15 27-Oct-15 4
501-FAEI-18060 Calibration of Instrument Tags - 08-I1 : Closed Drain System 8 Ea. 50.165 22 100.00% 24-Oct-15 27-Oct-15 4 100.00% 100.00% Completed
5 13 9-Nov-15 11-Nov-15 3
501-FAEI-18070 Calibration of Instrument Tags - 09-I1 : Open Drain System 5 Ea. 50.165 13 100.00% 9-Nov-15 11-Nov-15 3 100.00% 100.00% Completed
1 3 11-Nov-15 13-Nov-15 3
501-FAEI-18080 Calibration of Instrument Tags - 06-I1 : HP Vent / LP Vent 1 Ea. 50.165 3 100.00% 11-Nov-15 13-Nov-15 3 100.00% 100.00% Completed
24 68 3-Nov-15 25-Nov-15 23
14 40 13-Nov-15 20-Nov-15 8
501-FAEI-18090 Calibration of Instrument Tags - 04-I1 : Instrument Gas 14 Ea. 50.165 40 100.00% 13-Nov-15 20-Nov-15 8 100.00% 100.00% Completed
10 28 3-Nov-15 25-Nov-15 23
501-FAEI-18100 Calibration of Instrument Tags - 04-I2 : Utility Gas 10 Ea. 50.165 28 100.00% 20-Nov-15 25-Nov-15 6 100.00% 100.00% Completed
21 59 3-Oct-15 20-Oct-15 18
21 59 3-Oct-15 20-Oct-15 18
501-FAEI-18130 Calibration of Instrument Tags - 11-I1 : Chemical Injection 21 Ea. 50.165 59 100.00% 3-Oct-15 15-Oct-15 13 100.00% 100.00% Completed
57 224 25-Sep-15 30-Jan-16 128
51 208 25-Sep-15 12-Dec-15 79
501-FAEI-18150 Calibration of Instrument Tags - 13-C1 : Back Start 3 Ea. 50.165 8 3.85% 11-Dec-15 12-Dec-15 2 100.00% 100.00% Completed
501-FAEI-18160 Calibration of Instrument Tags - 13-C3 : Wellhead Control Panel 48 Ea. 50.165 200 96.15% 25-Sep-15 26-Oct-15 32 100.00% 100.00% Completed
1 3 14-Dec-15 15-Dec-15 2
501-FAEI-18180 Calibration of Instrument Tags - 14-E6 : TEG - Gas Platform 1 Ea. 50.165 3 100.00% 14-Dec-15 15-Dec-15 2 100.00% 100.00% Completed
5 13 29-Jan-16 30-Jan-16 2
501-FAEI-18190 Calibration of Instrument Tags - 17-S3 : Fire & Gas Detector 5 Ea. 50.165 13 100.00% 29-Jan-16 30-Jan-16 2 100.00% 100.00% Completed
428 1294 0.00%
1st 2nd 1st 2nd
L5 L4 20.0% 20.0% 7.5% 7.5% L5 L4 L5 L4
305 4601 24-Feb-16 26-Mar-16 32
305 4601 24-Feb-16 26-Mar-16 32
501-FAEI-18200 Cables Installation for 01-I1: Process Production 121 Sch. 50.175 1968 42.77% 29-Feb-16 15-Mar-16 16 121 121 121 121 100.00% 100.00% Completed
501-FAEI-18210 Cables Installation for 01-I2 : Production Header 50 Sch. 50.175 678 14.74% 3-Mar-16 10-Mar-16 8 50 50 50 50 100.00% 100.00% Completed
501-FAEI-18220 Cables Installation for 02-I1 : Test Separator 76 Sch. 50.175 1033 22.45% 8-Mar-16 15-Mar-16 8 76 76 76 76 100.00% 100.00% Completed
501-FAEI-18230 Cables Installation for 03-I2 : Pig Receiver - Option 10 Sch. 50.175 271 5.89% 18-Mar-16 26-Mar-16 9 10 10 10 10 100.00% 100.00% Completed
501-FAEI-18260 Cables Installation for 10-I1 : Booster Compressor 48 Sch. 50.175 651 14.15% 24-Feb-16 11-Mar-16 17 48 48 48 48 100.00% 100.00% Completed
9 124 25-Feb-16 21-Mar-16 26
6 82 17-Mar-16 21-Mar-16 5
501-FAEI-18270 Cables Installation for 08-I1 : Closed Drain System 6 Sch. 50.175 82 100.00% 17-Mar-16 21-Mar-16 5 6 6 6 6 100.00% 100.00% Completed
3 42 25-Feb-16 29-Feb-16 5
501-FAEI-18280 Cables Installation for 09-I1 : Open Drain System 3 Sch. 50.175 42 100.00% 25-Feb-16 29-Feb-16 5 3 3 3 3 100.00% 100.00% Completed
16 217 10-Mar-16 7-Apr-16 29
10 135 25-Mar-16 7-Apr-16 14
501-FAEI-18290 Cables Installation for 04-I1 : Instrument Gas 10 Sch. 50.175 135 100.00% 25-Mar-16 7-Apr-16 14 10 10 10 10 100.00% 100.00% Completed
6 82 10-Mar-16 7-Apr-16 29
501-FAEI-18300 Cables Installation for 04-I2 : Utility Gas 6 Sch. 50.175 82 100.00% 25-Mar-16 7-Apr-16 14 6 6 6 6 100.00% 100.00% Completed
9 125 4-Mar-16 25-Mar-16 22
9 125 4-Mar-16 25-Mar-16 22
501-FAEI-18330 Cables Installation for 11-I1 : Chemical Injection 9 Sch. 50.175 125 100.00% 19-Mar-16 25-Mar-16 7 9 9 9 9 100.00% 100.00% Completed
265 3215 6-Nov-15 16-Apr-16 163
65 776 6-Nov-15 5-Feb-16 92
501-FAEI-18350 Cables Installation for 13-C2 : PLC and Control system 65 Sch. 50.175 776 100.00% 22-Jan-16 5-Feb-16 15 65 65 65 65 100.00% 100.00% Completed
175 2139 13-Nov-15 16-Apr-16 156
501-FAEI-18380 Cables Installation for 14-E2 : AC Diesel Generators 1 Sch. 50.175 16 0.75% 26-Jan-16 2-Feb-16 8 1 1 1 1 100.00% 100.00% Completed
501-FAEI-18390 Cables Installation for 14-E3 : DC Supply 36 Sch. 50.175 368 17.20% 22-Jan-16 12-Feb-16 22 36 36 36 36 100.00% 100.00% Completed
501-FAEI-18400 Cables Installation for 14-E4 : Power & Lighting and Outlet 118 Sch. 50.175 1480 69.19% 13-Nov-15 9-Dec-15 27 118 118 118 118 100.00% 100.00% Completed
501-FAEI-18420 Cables Installation for 14-E6 : TEG - Gas Platform 9 Sch. 50.175 125 5.84% 3-Feb-16 18-Feb-16 16 9 9 9 9 100.00% 100.00% Completed
501-FAEI-18430 Cables Installation for 16-E1 : Navigation Aids System 11 Sch. 50.175 150 7.01% 22-Jan-16 10-Feb-16 20 11 11 11 11 100.00% 100.00% Completed
14 150 5-Feb-16 27-Feb-16 23
501-FAEI-18440 Cables Installation for 15-T1 : Comunication System 14 Sch. 50.175 150 100.00% 5-Feb-16 27-Feb-16 23 14 12 14 12 96.07% 100.00% Delayed
11 150 22-Jan-16 12-Feb-16 22
501-FAEI-18450 Cables Installation for 17-S2 : Emergency Shutdown 2 Sch. 50.175 27 18.00% 22-Jan-16 25-Jan-16 4 2 2 2 2 100.00% 100.00% Completed
501-FAEI-18460 Cables Installation for 17-S3 : Fire & Gas Detector 5 Sch. 50.175 68 45.33% 22-Jan-16 25-Jan-16 4 5 5 5 5 100.00% 100.00% Completed
501-FAEI-18470 Cables Installation for 17-S4 : Beacon Light & Siren 4 Sch. 50.175 55 36.67% 5-Feb-16 12-Feb-16 8 4 4 4 4 100.00% 100.00% Completed
604 8282 604 602 604 602 -0.07%
L5 L4 L5 L4 L5 L4
305 531 9-Apr-16 9-May-16 31
305 531 9-Apr-16 9-May-16 31
501-FAEI-18480 Cables Continuity Check for 01-I1: Process Production 121 Sch. 50.180 218 41.05% 29-Apr-16 9-May-16 11 99.94% 100.00% Delayed
501-FAEI-18490 Cables Continuity Check for 01-I2 : Production Header 50 Sch. 50.180 75 14.12% 29-Apr-16 3-May-16 5 92.65% 100.00% Delayed
501-FAEI-18500 Cables Continuity Check for 02-I1 : Test Separator 76 Sch. 50.180 135 25.42% 3-May-16 7-May-16 5 93.50% 100.00% Delayed
501-FAEI-18510 Cables Continuity Check for 03-I2 : Pig Receiver - Option 10 Sch. 50.180 31 5.84% 4-May-16 6-May-16 3 92.50% 100.00% Delayed
501-FAEI-18540 Cables Continuity Check for 10-I1 : Booster Compressor 48 Sch. 50.180 72 13.56% 6-May-16 9-May-16 4 92.50% 100.00% Delayed
9 13 29-Apr-16 3-May-16 5
6 9 29-Apr-16 3-May-16 5
501-FAEI-18550 Cables Continuity Check for 08-I1 : Closed Drain System 6 Sch. 50.180 9 100.00% 29-Apr-16 3-May-16 5 96.67% 100.00% Delayed
3 4 29-Apr-16 3-May-16 5
501-FAEI-18560 Cables Continuity Check for 09-I1 : Open Drain System 3 Sch. 50.180 4 100.00% 29-Apr-16 3-May-16 5 96.67% 100.00% Delayed
16 24 7-Apr-16 9-May-16 33
10 15 3-May-16 6-May-16 4
501-FAEI-18570 Cables Continuity Check for 04-I1 : Instrument Gas 10 Sch. 50.180 15 100.00% 3-May-16 6-May-16 4 98.50% 100.00% Delayed
6 9 7-Apr-16 9-May-16 33
501-FAEI-18580 Cables Continuity Check for 04-I2 : Utility Gas 6 Sch. 50.180 9 100.00% 6-May-16 9-May-16 4 92.17% 100.00% Delayed
9 18 9-Apr-16 10-May-16 32
9 18 9-Apr-16 10-May-16 32
501-FAEI-18610 Cables Continuity Check for 11-I1 : Chemical Injection 9 Sch. 50.180 18 100.00% 7-May-16 10-May-16 4 100.00% 100.00% Completed
265 409 26-Mar-16 7-May-16 43
65 59 30-Apr-16 6-May-16 7
501-FAEI-18630 Cables Continuity Check for 13-C2 : PLC and Control system 65 Sch. 50.180 59 100.00% 3-May-16 6-May-16 4 75.67% 100.00% Delayed
175 254 26-Mar-16 7-May-16 43
501-FAEI-18660 Cables Continuity Check for 14-E2 : AC Diesel Generators 1 Sch. 50.180 3 1.18% 4-May-16 6-May-16 3 100.00% 100.00% Completed
501-FAEI-18670 Cables Continuity Check for 14-E3 : DC Supply 36 Sch. 50.180 26 10.24% 26-Apr-16 28-Apr-16 3 100.00% 100.00% Completed
501-FAEI-18680 Cables Continuity Check for 14-E4 : Power & Lighting and Outlet 118 Sch. 50.180 196 77.17% 22-Apr-16 28-Apr-16 7 93.63% 100.00% Delayed
501-FAEI-18700 Cables Continuity Check for 14-E6 : TEG - Gas Platform 9 Sch. 50.180 13 5.12% 3-May-16 4-May-16 2 95.56% 100.00% Delayed
501-FAEI-18710 Cables Continuity Check for 16-E1 : Navigation Aids System 11 Sch. 50.180 16 6.30% 4-May-16 7-May-16 4 100.00% 100.00% Completed
14 74 4-May-16 7-May-16 4
501-FAEI-18720 Cables Continuity Check for 15-T1 : Comunication System 14 Sch. 50.180 74 100.00% 4-May-16 7-May-16 4 71.21% 100.00% Delayed
11 22 29-Apr-16 7-May-16 9
501-FAEI-18730 Cables Continuity Check for 17-S2 : Emergency Shutdown 2 Sch. 50.180 3 13.64% 29-Apr-16 30-Apr-16 2 92.50% 100.00% Delayed
501-FAEI-18740 Cables Continuity Check for 17-S3 : Fire & Gas Detector 5 Sch. 50.180 12 54.55% 4-May-16 7-May-16 4 92.50% 100.00% Delayed
501-FAEI-18750 Cables Continuity Check for 17-S4 : Beacon Light & Siren 4 Sch. 50.180 7 31.82% 4-May-16 7-May-16 4 92.50% 100.00% Delayed
604 995 -7.42%
L5 L4 L5 L4 L5 L4
339 508 29-Mar-16 3-May-16 36
72 112 1-Apr-16 4-Apr-16 4
72 112 1-Apr-16 4-Apr-16 4
501-FAEI-18760 Tubings Installation for 06-I1 : HP Vent / LP Vent 72 m. 50.175 112 100.00% 1-Apr-16 4-Apr-16 4 93.00% 100.00% Delayed
189 153 29-Mar-16 8-Apr-16 11
189 153 29-Mar-16 8-Apr-16 11
501-FAEI-18770 Tubings Installation for 11-I1 : Chemical Injection 189 m. 50.175 153 100.00% 7-Apr-16 8-Apr-16 2 93.00% 100.00% Delayed
78 243 9-Apr-16 3-May-16 25
69 122 9-Apr-16 12-Apr-16 4
501-FAEI-18790 Tubings Installation for 13-C1 : Back Start 69 m. 50.175 122 100.00% 9-Apr-16 12-Apr-16 4 90.00% 100.00% Delayed
9 121 29-Apr-16 3-May-16 5
501-FAEI-18800 Tubings Installation for 14-E6 : TEG - Gas Platform 9 m. 50.175 20 16.53% 29-Apr-16 29-Apr-16 1 91.50% 100.00% Delayed
3478 12-Feb-16 16-Apr-16 65
2874 870 12-Feb-16 26-Feb-16 15
501-FAEI-18820 Pre-Cutting and Pre-Bending 2874 m. 50.175 870 100.00% 12-Feb-16 26-Feb-16 15 100.00% 100.00% Completed
2535 2608 18-Mar-16 16-Apr-16 30
483 227 24-Mar-16 5-Apr-16 13
483 227 24-Mar-16 5-Apr-16 13
501-FAEI-18840 Tubings Installation for 01-I1: Process Production 456 m. 50.175 195 85.90% 24-Mar-16 26-Mar-16 3 91.50% 100.00% Delayed
501-FAEI-18850 Tubings Installation for 10-I1 : Booster Compressor 27 m. 50.175 32 14.10% 28-Mar-16 5-Apr-16 9 100.00% 100.00% Completed
2052 2381 18-Mar-16 16-Apr-16 30
1273 1529 18-Mar-16 16-Apr-16 30
501-FAEI-18860 Tubings Installation for 13-C3 : Wellhead Control Panel 1273 m. 50.175 1529 100.00% 18-Mar-16 16-Apr-16 30 93.25% 100.00% Delayed
779 852 18-Mar-16 11-Apr-16 25
501-FAEI-18870 Tubings Installation for 17-S1 : Fire Emergency Shutdown (FESD) 531 m. 50.175 579 67.96% 18-Mar-16 4-Apr-16 18 100.00% 100.00% Completed
501-FAEI-18880 Tubings Installation for 17-S2 : Emergency Shutdown 248 m. 50.175 273 32.04% 25-Mar-16 11-Apr-16 18 95.00% 100.00% Delayed
2874 3986 -4.16%
L5 L4 L5 L4 L5 L4
339 102 10-May-16 23-May-16 14
72 9 12-May-16 14-May-16 3
72 9 12-May-16 14-May-16 3
501-FAEI-18890 Tubings Leak Test for 06-I1 : HP Vent / LP Vent 72 m. 50.180 9 100.00% 12-May-16 14-May-16 3 100.00% 100.00% Completed
189 50 10-May-16 23-May-16 14
% Actual %Plan
L3 L3 L3
49.02% 95.33% 100.00%
100.00%
Status
Next 2 Wks
As Per Planed
RemarkL3
Start Finish Dur.
Tested Check Sheet : PLT-T L3 L3
90% 10%
Bare Tube Leak Test 35.92% 95.93% 100.00%
TUBINGS LEAK TEST QTY Unit Cost Code
Budgeted
Mhrs
WTG% Baseline Activity Milestones % Actual %Plan
100.00%
Sub-System - 2001 : Closed Drain (DC)
System - 2000 : Drains & Reliefs 8.82% 100.00%
Sub-System - 2500 : Blow Down (BD) 100.00% 100.00% 100.00%
72 100.00%
System - 7000 : Chemicals
Sub-System - 8000D : Safety Intrergrity System (SIS) 35.78% 98.40% 100.00%
531 100.00%
248 50.00%
SUB-TOTAL OF TUBINGS INSTALLATION 16.56% 2874 95.84% 100.00%
456 15.00%
27 100.00%
System - 8000 : Others 91.30% 95.09% 100.00%
Sub-System - 8000A : Process Control 64.22% 93.25% 100.00%
1273 32.50%
2874
Field Installation and Hook-Up 74.99% 94.88% 100.00%
System - 1000 : Process Production 8.70% 92.70% 100.00%
Sub-System - 1001 : Process Liquid & Vapour (P) 100.00% 92.70% 100.00%
98.60% 100.00%
9 15.00%
TPU Jacket Tube Installation 87.26% 96.16% 100.00%
Preparation Works 25.01% 100.00% 100.00%
93.00% 100.00%
189 30.00%
System - 8000 : Others 47.83% 94.28% 100.00%
Sub-System - 8000A : Process Control 50.21% 90.00% 100.00%
93.61% 100.00%
System - 2000 : Drains & Reliefs 22.05% 93.00% 100.00%
Sub-System - 2500 : Blow Down (BD) 100.00% 93.00% 100.00%
System - 7000 : Chemicals 30.12% 93.00% 100.00%
% Actual %Plan
Status
Next 2 Wks
As Per Planed
RemarkL3
Start Finish Dur.
Tube Running Check Sheet : PIC-T L3 L3
90% 10%
TUBINGS INSTALLATION QTY Unit Cost Code
Budgeted
Mhrs
WTG% Baseline Activity Milestones
Bare Tube Installation 12.74%
Sub-System - 7001 : Chemical (C) 100.00%
69
Sub-System - 8000B : Electrical Generation and Distribution 49.79%
11
2
4 25.00%
100.00%
3
6
99.38%
50 26.50%
76
110
121
% Actual
604
72 30.00%
100.00%
100.00%
6
Unit
Unit
Unit
TerminatedGlanded
45%
36
26 100.00%
8 100.00%
100.00%
48 100.00%
1 100.00%
5 100.00%
Tested Check Sheet : PLT-C
90% 10%
50.58%
3
579
1.31%
5
11
9 55.56%
11
65
193 100.00%
28 100.00%
1 100.00%
14 100.00%
14 100.00%
10 100.00%
10
9
48
206 206
9 100.00%
1 100.00%
66.67%
66.67%
85.00%
6 21.67%
100.00%
97.32%
3
50 100.00%
100.00%
1 100.00%
1
25.00%
5.00%
36
Budgeted
Mhrs
WTG% Baseline Activity Milestones
35.00%
10
25.00%
WHP 50/1 : GAS PLATFORM : E&I INSTALLATION
38.82%
System - 4000 : Utility Generals
Sub-System - 4400 : Gas Instrument (GI)
Sub-System - 4500 : Gas Utility (GU)
System - 8000 : Others
System - 7000 : Chemicals
Sub-System - 7001 : Chemical (C) 100.00%
37.79%
1.51%
System - 2000 : Drains & Reliefs
10
1.50% 100.00%
100.00%
100.00%
Sub-System - 2100 : Open Drain (DO)
Activity Milestones
System - 1000 : Process Production
CABLES INSTALLATION
Baseline
55.55%
50
76
Sub-System - 8000D : Safety Intrergrity System (SIS)
CHEVRON : CVX-PHASE 50
PROGRESS MEASUREMENT WORK SHEET FOR E&I AND PRE-COMMISSIONING WORKS
WHP 50/1 : GAS PLATFORM
Next 2 Wks
As Per Planed
Sub-System - 1001 : Process Liquid & Vapour (P)
Status Remark
100.00% 100.00%
100.00% 100.00%
100.00%
Fabricated/Installed
90%
Accepted /Painted/Cleaning
Status
Next 2 Wks
As Per Planed
RemarkL3
Start Finish Dur.
L3 L3
188 188
37
WTG% Baseline
100.00%
100.00%
100.00%
62.21%
100.00%
99.93%
Sub-System - 8000A : Process Control
Sub-System - 8000B : Electrical Generation and Distribution
SUB-TOTAL OF CABLES INSTALLATION
100.00%
100.00%
66.13%
33.87%
24.14%
Sub-System - 2001 : Closed Drain (DC)
118
9
2.62%
4
14
2
5
6
96.07%
34.40%
System - 1000 : Process Production 69.94%
Sub-System - 1001 : Process Liquid & Vapour (P) 100.00% 100.00% 100.00%
% Actual %Plan
CALIBRATION OF INSTRUMENTS TAG QTY
Budgeted
Mhrs
428
90% 10%
Calibrated Check Sheet : PCC
Sub-System - 2100 : Open Drain (DO) 34.21% 100.00% 100.00%
System - 2000 : Drains & Reliefs 2.94%
Sub-System - 2001 : Closed Drain (DC) 57.89% 100.00% 100.00%
Sub-System - 4400 : Gas Instrument (GI) 58.82% 100.00% 100.00%
System - 4000 : Utility Generals 5.26%
7.89%Sub-System - 2500 : Blow Down (BD) 100.00% 100.00%
100.00%
Sub-System - 4500 : Gas Utility (GU) 41.18% 100.00% 100.00%
System - 8000 : Others 17.31%
Sub-System - 8000A : Process Control 92.86% 100.00% 100.00%
System - 7000 : Chemicals 4.56%
Sub-System - 7001 : Chemical (C) 100.00% 100.00% 100.00%
100.00%
100.00%
100.00%
100.00%
21 100.00%
Sub-System - 8000D : Safety Intrergrity System (SIS) 5.80% 100.00% 100.00%
Sub-System - 8000B : Electrical Generation and Distribution 1.34% 100.00% 100.00%
100.00%SUB-TOTAL OF CALIBRATION OF INSTRUMENTS TAG 5.37% 100.00%
100.00%
Budgeted
Mhrs Dur.
QTY
100.00%
100.00%
100.00%
100.00%
121
Pulled
100.00%
100.00%
WTG%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
95.83%
Sub-System - 1001 : Process Liquid & Vapour (P) 100.00% 95.83% 100.00%
Sub-System - 2100 : Open Drain (DO) 30.77% 96.67%
System - 2000 : Drains & Reliefs
SUB-TOTAL OF CABLES CONTINUITY & INSULATION TEST 4.13% 92.58%
69.23% 96.67% 100.00%
10 25.00%
48
62.10%
5 25.00%
51
96.67%
Status
Next 2 Wks
As Per Planed
RemarkL3
Start Finish Dur.
L3 L3
%Plan
100.00%
Fabrication 44.10% 100.00% 100.00%
92.17% 100.00%
System - 4000 : Utility Generals 2.41% 96.13% 100.00%
Sub-System - 4400 : Gas Instrument (GI) 62.50% 98.50% 100.00%
4.67%
100.00%
E&I SUPPORTS, LADDERS AND TRAYS QTY
Budgeted
Mhrs
Cellar Deck
100.00%
Installation of E&I Supports
66.53%
4.67%
100.00%
100.00%
Start Finish
100.00%
99.82%
100.00%
68.87% 100.00% 100.00%
Sub-Cellar Deck
Installation 55.90% 100.00%
670 670
109 109
Sub-System - 8000C : Communication
100.00%
Status
Next 2 Wks
As Per Planed
% Actual
10%
31 31
663 663
243 243
358 358
%Plan
RemarkL3
Start Finish Dur.
L3 L3
WTG% Baseline Activity Milestones
100.00% 100.00%
Mezzanine Deck
Upper Deck
Installation of E&I Trays&Ladders 31.13% 100.00% 100.00%
QTY
SUB-TOTAL OF E&I SUPPORTS, LADDERS AND TRAYS 35.06%
System - 1000 : Process Production 53.37%
100.00%
100.00%Sub-System - 8000D : Safety Intrergrity System (SIS) 5.38% 92.50%
41.11%
94.86%
87.69% 100.00%
Sub-System - 8000A : Process Control 14.43% 75.67% 100.00%
Sub-System - 8000B : Electrical Generation and Distribution
Cost Code
Cost Code
Cost Code
Cost Code
100.00%
Sub-System - 8000C : Communication 18.09% 71.21% 100.00%
System - 7000 : Chemicals 1.81%
Sub-System - 4500 : Gas Utility (GU) 37.50%
100.00% 100.00%
Sub-System - 7001 : Chemical (C) 100.00% 100.00% 100.00%
System - 8000 : Others
CABLES CONTINUITY & INSULATION TEST
Unit
273 273
85 85
Activity Milestones
1 1
30 30
475 475
37
Page 1 of 10 Prepared By : Nattakarn S.
Activity ID Activity Name Num. Budgeted Units Planned Start Planned Finish % Actual 1-Jun-16
CHEVRON : CVX-PHASE 50
PROGRESS MEASUREMENT WORK SHEET FOR E&I AND PRE-COMMISSIONING WORKS
WHP 50/1 : GAS PLATFORM
189 50 10-May-16 23-May-16 14
501-FAEI-18900 Tubings Leak Test for 11-I1 : Chemical Injection 189 m. 50.180 50 100.00% 10-May-16 13-May-16 4 95.33% 100.00% Delayed
78 43 10-May-16 14-May-16 5
69 21 10-May-16 13-May-16 4
501-FAEI-18920 Tubings Leak Test for 13-C1 : Back Start 69 m. 50.180 21 100.00% 10-May-16 13-May-16 4 95.00% 100.00% Delayed
9 22 13-May-16 14-May-16 2
501-FAEI-18930 Tubings Leak Test for 14-E6 : TEG - Gas Platform 9 m. 50.180 11 50.00% 13-May-16 14-May-16 2 93.00% 100.00% Delayed
2535 182 10-May-16 16-May-16 7
483 56 13-May-16 16-May-16 4
483 56 13-May-16 16-May-16 4
501-FAEI-18950 Tubings Leak Test for 01-I1: Process Production 456 m. 50.180 45 80.36% 13-May-16 16-May-16 4 96.50% 100.00% Delayed
501-FAEI-18960 Tubings Leak Test for Booster Compressor 27 m. 50.180 11 19.64% 13-May-16 14-May-16 2 100.00% 100.00% Completed
2052 126 10-May-16 14-May-16 5
1273 90 10-May-16 13-May-16 4
501-FAEI-18970 Tubings Leak Test for 13-C3 : Wellhead Control Panel 1273 m. 50.180 90 100.00% 10-May-16 13-May-16 4 95.75% 100.00% Delayed
779 36 13-May-16 14-May-16 2
501-FAEI-18980 Tubings Leak Test for 17-S1 : Fire Emergency Shutdown (FESD) 531 m. 50.180 18 50.00% 13-May-16 14-May-16 2 93.00% 100.00% Delayed
501-FAEI-18990 Tubings Leak Test for 17-S2 : Emergency Shutdown 248 m. 50.180 18 50.00% 13-May-16 14-May-16 2 93.00% 100.00% Delayed
2874 284 -4.25%
L5 L4 L5 L4 L5 L4
271 363 31-Mar-16 31-May-16 62
271 363 31-Mar-16 31-May-16 62
501-FAEI-19000 Hook-Up of E&I Tags for 01-I1: Process Production 145 Ea. 50.175 148 40.77% 4-May-16 31-May-16 28 96.43% 100.00% Delayed
501-FAEI-19010 Hook-Up of E&I Tags for 01-I2 : Production Header 28 Ea. 50.175 43 11.85% 31-Mar-16 29-Apr-16 30 99.64% 100.00% Delayed
501-FAEI-19020 Hook-Up of E&I Tags for 02-I1 : Test Separator 52 Ea. 50.175 75 20.66% 20-Apr-16 9-May-16 20 99.60% 100.00% Delayed
501-FAEI-19030 Hook-Up of E&I Tags for 03-I1 : Pig Luncher 1 Ea. 50.175 1 0.28% 4-May-16 19-May-16 16 90.00% 100.00% Delayed
501-FAEI-19040 Hook-Up of E&I Tags for 03-I2 : Pig Receiver - Option 18 Ea. 50.175 55 15.15% 16-May-16 25-May-16 10 93.33% 100.00% Delayed
501-FAEI-19070 Hook-Up of E&I Tags for 10-I1 : Booster Compressor 27 Ea. 50.175 41 11.29% 7-Apr-16 27-Apr-16 21 99.62% 100.00% Delayed
15 22 16-Apr-16 19-May-16 34
9 13 16-Apr-16 25-Apr-16 10
501-FAEI-19080 Hook-Up of E&I Tags for 08-I1 : Closed Drain System 9 Ea. 50.175 13 100.00% 16-Apr-16 25-Apr-16 10 98.89% 100.00% Delayed
5 8 9-May-16 12-May-16 4
501-FAEI-19090 Hook-Up of E&I Tags for 09-I1 : Open Drain System 5 Ea. 50.175 8 100.00% 9-May-16 12-May-16 4 98.00% 100.00% Delayed
1 1 12-May-16 19-May-16 8
501-FAEI-19100 Hook-Up of E&I Tags for 06-I1 : HP Vent / LP Vent 1 Ea. 50.175 1 100.00% 12-May-16 19-May-16 8 90.00% 100.00% Delayed
28 41 30-Mar-16 9-Apr-16 11
17 23 30-Mar-16 7-Apr-16 9
501-FAEI-19110 Hook-Up of E&I Tags for 04-I1 : Instrument Gas 17 Ea. 50.175 23 100.00% 30-Mar-16 7-Apr-16 9 98.59% 100.00% Delayed
11 18 1-Apr-16 9-Apr-16 9
501-FAEI-19120 Hook-Up of E&I Tags for 04-I2 : Utility Gas 11 Ea. 50.175 18 100.00% 1-Apr-16 9-Apr-16 9 98.18% 100.00% Delayed
24 35 7-Apr-16 24-May-16 48
24 35 7-Apr-16 24-May-16 48
501-FAEI-19150 Hook-Up of E&I Tags for 11-I1 : Chemical Injection 24 Ea. 50.175 35 100.00% 7-Apr-16 18-Apr-16 12 98.48% 100.00% Delayed
230 332 26-Dec-15 13-May-16 140
67 226 26-Mar-16 11-May-16 47
501-FAEI-19170 Hook-Up of E&I Tags for 13-C1 : Back Start 4 Ea. 50.175 7 3.10% 26-Mar-16 31-Mar-16 6 100.00% 100.00% Completed
501-FAEI-19180 Hook-Up of E&I Tags for 13-C2 : PLC and Control system 14 Ea. 50.175 22 9.73% 23-Apr-16 7-May-16 15 99.53% 100.00% Delayed
501-FAEI-19190 Hook-Up of E&I Tags for 13-C3 : Wellhead Control Panel 49 Ea. 50.175 197 87.17% 23-Apr-16 11-May-16 19 100.00% 100.00% Completed
132 60 26-Dec-15 6-May-16 133
501-FAEI-19210 Hook-Up of E&I Tags for 14-E2 : AC Diesel Generators 1 Ea. 50.175 1 1.67% 26-Apr-16 4-May-16 9 100.00% 100.00% Completed
501-FAEI-19220 Hook-Up of E&I Tags for 14-E3 : DC Supply 7 Ea. 50.175 10 16.67% 17-Feb-16 25-Feb-16 9 98.60% 100.00% Delayed
501-FAEI-19230 Hook-Up of E&I Tags for 14-E4 : Power & Lighting and Outlet 110 Ea. 50.175 28 46.67% 26-Dec-15 2-Feb-16 39 96.86% 100.00% Delayed
501-FAEI-19250 Hook-Up of E&I Tags for 14-E6 : TEG - Gas Platform 5 Ea. 50.175 8 13.33% 5-Apr-16 18-Apr-16 14 97.50% 100.00% Delayed
501-FAEI-19260 Hook-Up of E&I Tags for 16-E1 : Navigation Aids System 9 Ea. 50.175 13 21.67% 25-Feb-16 4-Mar-16 9 100.00% 100.00% Completed
5 7 8-Feb-16 15-Feb-16 8
501-FAEI-19270 Hook-Up of E&I Tags for 15-T1 : Comunication System 5 Ea. 50.175 7 100.00% 8-Feb-16 15-Feb-16 8 100.00% 100.00% Completed
26 39 5-Apr-16 13-May-16 39
501-FAEI-19280 Hook-Up of E&I Tags for 17-S2 : Emergency Shutdown 10 Ea. 50.175 13 33.33% 25-Apr-16 7-May-16 13 98.89% 100.00% Delayed
501-FAEI-19290 Hook-Up of E&I Tags for 17-S3 : Fire & Gas Detector 5 Ea. 50.175 8 20.51% 5-Apr-16 12-Apr-16 8 98.60% 100.00% Delayed
501-FAEI-19300 Hook-Up of E&I Tags for 17-S4 : Beacon Light & Siren 11 Ea. 50.175 18 46.15% 4-May-16 13-May-16 10 100.00% 100.00% Completed
568 793 -1.62%
24076 -1.12%
L5 L4 L5 L4 L5 L4
704 24-May-16 27-May-16 4
61 704 24-May-16 27-May-16 4
61 704 24-May-16 27-May-16 4
501-FAPC-19910 Fuction Test of 14-E2 : AC Diesel Generators 4 Pac. 60.220 71 10.09% 24-May-16 25-May-16 2 90.00% 100.00% Delayed
501-FAPC-19920 Fuction Test of 14-E3 : DC Supply 19 Pac. 60.220 174 24.72% 24-May-16 25-May-16 2 90.00% 100.00% Delayed
501-FAPC-19930 Fuction Test of 14-E4 : Power & Lighting and Outlet 23 Pac. 60.220 322 45.74% 24-May-16 25-May-16 2 90.00% 100.00% Delayed
501-FAPC-19950 Fuction Test of 14-E6 : TEG - Gas Platform 7 Pac. 60.220 21 2.98% 26-May-16 26-May-16 1 90.00% 100.00% Delayed
501-FAPC-19960 Fuction Test of 16-E1 : Navigation Aids System 8 Pac. 60.220 116 16.48% 24-May-16 25-May-16 2 90.00% 100.00% Delayed
1241 24-May-16 28-May-16 5
205 823 25-May-16 28-May-16 4
205 823 25-May-16 28-May-16 4
501-FAPC-19980 Loop Test of 01-I1: Process Production 97 Pac. 60.225 340 41.31% 25-May-16 26-May-16 2 90.00% 100.00% Delayed
501-FAPC-19990 Loop Test of 01-I2 : Production Header 26 Pac. 60.225 94 11.42% 26-May-16 27-May-16 2 90.00% 100.00% Delayed
501-FAPC-20000 Loop Test of 02-I1 : Test Separator 45 Pac. 60.225 191 23.21% 26-May-16 27-May-16 2 90.00% 100.00% Delayed
501-FAPC-20010 Loop Test of 03-I2 : Pig Receiver - Option 6 Pac. 60.225 42 5.10% 26-May-16 26-May-16 1 90.00% 100.00% Delayed
501-FAPC-20040 Loop Test of 10-I1 : Booster Compressor 31 Pac. 60.225 156 18.96% 27-May-16 28-May-16 2 90.00% 100.00% Delayed
9 32 26-May-16 26-May-16 1
6 21 26-May-16 26-May-16 1
501-FAPC-20050 Loop Test of 08-I1 : Closed Drain System 6 Pac. 60.225 21 100.00% 26-May-16 26-May-16 1 90.00% 100.00% Delayed
3 11 26-May-16 26-May-16 1
501-FAPC-20060 Loop Test of 09-I1 : Open Drain System 3 Pac. 60.225 11 100.00% 26-May-16 26-May-16 1 90.00% 100.00% Delayed
14 32 26-May-16 26-May-16 1
9 21 26-May-16 26-May-16 1
501-FAPC-20070 Loop Test of 04-I1 : Instrument Gas 9 Pac. 60.225 21 100.00% 26-May-16 26-May-16 1 90.00% 100.00% Delayed
5 11 26-May-16 26-May-16 1
501-FAPC-20080 Loop Test of 04-I2 : Utility Gas 5 Pac. 60.225 11 100.00% 26-May-16 26-May-16 1 90.00% 100.00% Delayed
9 32 26-May-16 26-May-16 1
9 32 26-May-16 26-May-16 1
501-FAPC-20110 Loop Test of 11-I1 : Chemical Injection 9 Pac. 60.225 32 100.00% 26-May-16 26-May-16 1 90.00% 100.00% Delayed
97 322 24-May-16 25-May-16 2
81 187 25-May-16 25-May-16 1
501-FAPC-20130 Loop Test of 13-C3 : Wellhead Control Panel 81 Pac. 60.225 187 100.00% 25-May-16 25-May-16 1 90.00% 100.00% Delayed
1 4 24-May-16 24-May-16 1
501-FAPC-20140 Loop Test of 15-T1 : Comunication System 1 Pac. 60.225 4 100.00% 24-May-16 24-May-16 1 90.00% 100.00% Delayed
15 131 25-May-16 25-May-16 1
501-FAPC-20150 Loop Test of 17-S2 : Emergency Shutdown 3 Pac. 60.225 12 9.16% 25-May-16 25-May-16 1 90.00% 100.00% Delayed
501-FAPC-20160 Loop Test of 17-S3 : Fire & Gas Detector 5 Pac. 60.225 28 21.37% 25-May-16 25-May-16 1 90.00% 100.00% Delayed
501-FAPC-20170 Loop Test of 17-S4 : Beacon Light & Siren 7 Pac. 60.225 91 69.47% 25-May-16 25-May-16 1 90.00% 100.00% Delayed
395 1945 -10.00%
L5 L4 L5 L4 L5 L4
501-FAPC-20180 Platform Site Acceptance Test - SAT 100 Pac. 60.235 555 30-May-16 4-Jun-16 6 Delayed Should be finished
100 555 -50.00%
2500 -18.88%
-2.79%
System - 8000 : Others 69.23% 94.96% 100.00%
SUB-TOTAL OF TUBINGS LEAK TEST
Sub-System - 8000A : Process Control 71.43% 95.75% 100.00%
1273 57.50%
Sub-System - 8000D : Safety Intrergrity System (SIS) 28.57% 93.00% 100.00%
531 30.00%
248 30.00%
95.75% 100.00%
System - 1000 : Process Production 30.77% 97.19% 100.00%
Sub-System - 1001 : Process Liquid & Vapour (P) 100.00% 97.19% 100.00%
Sub-System - 8000A : Process Control 48.84% 95.00% 100.00%
69 50.00%
Sub-System - 8000B : Electrical Generation and Distribution 51.16% 96.50% 100.00%
TPU Jacket Tube Leak Test 64.08% 95.65% 100.00%
Sub-System - 7001 : Chemical (C) 100.00% 95.33% 100.00%
System - 8000 : Others 42.16% 95.77% 100.00%
SUB-TOTAL OF HOOK-UP OF E&I TAG ITEMS 98.38% 100.00%
100.00%
Sub-System - 8000D : Safety Intrergrity System (SIS) 99.34%
9 30.00%
456 65.00%
53.33%
11.75%
100.00%
Unit
189
28 96.43%
52
27
Unit
7
9
64.33%
28
18 18 33.33%
86.00%
5 5 86.00%
3.29%
4
90% 10%
4.55%
52 96.00%
1 1
9
31
6
5
81
27 27 96.15%
System - 1000 : Process Production 66.32%
System - 8000 : Others 41.87%
1.18%
90.00% 100.00%
Sub-System - 8000C : Communication 1.24% 90.00% 100.00%
Sub-System - 8000D : Safety Intrergrity System (SIS) 40.68% 90.00% 100.00%
395
1
3
5
SUB-TOTAL OF LOOP/ FUNCTION TEST 77.80%
90.00% 100.00%
System - 8000 : Others 25.95% 90.00% 100.00%
Sub-System - 8000A : Process Control 58.07% 90.00% 100.00%
System - 7000 : Chemicals 2.58% 90.00% 100.00%
Sub-System - 7001 : Chemical (C) 100.00%
90.00% 100.00%
Sub-System - 4400 : Gas Instrument (GI) 65.63% 90.00% 100.00%
Sub-System - 4500 : Gas Utility (GU) 34.38% 90.00% 100.00%
Sub-System - 2001 : Closed Drain (DC) 65.63% 90.00% 100.00%
Sub-System - 2100 : Open Drain (DO) 34.38% 90.00% 100.00%
3
System - 4000 : Utility Generals 2.58%
%Plan
90.00% 100.00%
Sub-System - 1001 : Process Liquid & Vapour (P) 100.00% 90.00% 100.00%
System - 2000 : Drains & Reliefs 2.58% 90.00% 100.00%
Status
97
26
45
6
Tested Check Sheet : PLT-L & PFTUnit
System - 8000 : Others
100.00%
Sub-System - 8000C : Communication 2.11% 100.00%
Sub-System - 8000B : Electrical Generation and Distribution 18.07% 97.97% 100.00%
Next 2 Wks
As Per Planed
RemarkL3
Start Finish Dur.
L3 L3LOOP/ FUNCTION TEST QTY
Budgeted
Mhrs
WTG% Baseline Activity Milestones % Actual
99.52% 100.00%
Sub-System - 8000A : Process Control 68.07% 99.95% 100.00%
System - 7000 : Chemicals 4.41% 98.48% 100.00%
Sub-System - 7001 : Chemical (C) 100.00% 98.48% 100.00%
24 24 84.78%
Sub-System - 4400 : Gas Instrument (GI) 56.10% 98.59% 100.00%
Sub-System - 4500 : Gas Utility (GU) 43.90% 98.18% 100.00%
17 17 85.88%
11 11 81.82%
90.00% 100.00%
System - 4000 : Utility Generals 5.17% 98.41% 100.00%
98.16% 100.00%
Sub-System - 2001 : Closed Drain (DC) 59.09% 98.89% 100.00%
Sub-System - 2100 : Open Drain (DO) 36.36% 98.00% 100.00%
System - 2000 : Drains & Reliefs 2.77%
1 1
9 9 88.89%
5 5 80.00%
Status
Next 2 Wks
As Per Planed
RemarkL3
Start Finish Dur.
L3 L3
WTG% Baseline Activity Milestones % Actual %Plan
60% 30% 10%
Installed Hook-Up Check Sheet : PIC-H
TOTAL OF WHP 50/1 : GAS PLATFORM : E&I INSTALLATION 90.59% 98.88% 100.00%
WHP 50/1 : GAS PLATFORM : E&I PRE-COMMISSIONING
System - 1000 : Process Production 45.78% 97.34%
QTY
Budgeted
Mhrs
81.12% 100.00%
50.00%
SUB-TOTAL OF SITE ACCEPTANC TEST - SAT 22.20% 50.00% 100.00%
50
100.00%
Sub-System - 1001 : Process Liquid & Vapour (P) 100.00% 97.34% 100.00%
HOOK-UP OF E&I TAG ITEMS
Sub-System - 2500 : Blow Down (BD)
Status
Next 2 Wks
As Per Planed
RemarkL3
Start Finish Dur.
L3 L3SAT Completion
100%
%PlanWTG% Baseline Activity Milestones % Actual
9.41%
SITE ACCEPTANC TEST - SAT QTY
Budgeted
Mhrs
100.00%
97.21% 100.00%26576
100.00%
OVERALL PROGRESS OF WHP 50/1 : GAS PLATFORM 100.00%
TOTAL OF WHP 50/1 : GAS PLATFORM : E&I PRE-COMMISSIONING
Instrumentation 63.80% 90.00% 100.00%
Electrical 90.00%
Cost Code
Cost Code
Cost Code
36.20% 100.00%
8
90.00% 100.00%
Sub-System - 8000B : Electrical Generation and Distribution 100.00% 90.00% 100.00%
7
19
23
100.00%
568 568
145 145
11 11 100.00%
110 110 68.63%
5 5 75.00%
9 9 100.00%
5 5 100.00%
1 1 100.00%
7 7
10 10 88.89%
4 4 100.00%
14 14 95.33%
49 49 100.00%
Page 2 of 10 Prepared By : Nattakarn S.
Activity ID Activity Name Num. Budgeted Units Planned Start Planned Finish % Actual 1-Jun-16
L5 L4 L5 L4 L5 L4
1284 3723 14-Aug-15 9-Oct-15 57
503-FAEI-20780 Fabrication of E&I Supports for Sub-Cellar Deck 31 Ea. 50.170 98 2.63% 24-Aug-15 8-Sep-15 16 100.00% 100.00% Completed
503-FAEI-20790 Fabrication of E&I Supports for Cellar Deck 636 Ea. 50.170 1915 51.44% 14-Aug-15 9-Oct-15 57 100.00% 100.00% Completed
503-FAEI-20800 Fabrication of E&I Supports for Mezzanine Deck 252 Ea. 50.170 525 14.10% 24-Aug-15 24-Sep-15 32 100.00% 100.00% Completed
503-FAEI-20810 Fabrication of E&I Supports for Upper Deck 365 Ea. 50.170 1185 31.83% 24-Aug-15 2-Oct-15 40 100.00% 100.00% Completed
4719 25-Sep-15 7-Apr-16 196
1284 3250 25-Sep-15 27-Feb-16 156
31 106 3.26% 25-Dec-15 18-Jan-16 25 100.00% 100.00%
503-FAEI-20820 Installation of E&I Support at Sub-Cellar Deck - Assembly Bay 1 Ea. 50.170 12 11.32% 25-Dec-15 5-Jan-16 12 100.00% 100.00% Completed
503-FAEI-20830 Installation of E&I Support at Sub-Cellar Deck - Erection Area 30 Ea. 50.170 94 88.68% 29-Dec-15 18-Jan-16 21 100.00% 100.00% Completed
636 1614 49.66% 25-Sep-15 15-Dec-15 82 100.00% 100.00%
503-FAEI-20840 Installation of E&I Support at Cellar Deck - Assembly Bay 475 Ea. 50.170 1035 64.13% 25-Sep-15 20-Oct-15 26 100.00% 100.00% Completed
503-FAEI-20850 Installation of E&I Support at Cellar Deck - Erection Area 161 Ea. 50.170 579 35.87% 13-Nov-15 15-Dec-15 33 100.00% 100.00% Completed
252 546 16.80% 27-Oct-15 27-Feb-16 124 100.00% 100.00%
503-FAEI-20860 Installation of E&I Support at Mezzanine Deck - Assembly Bay 37 Ea. 50.170 118 21.61% 27-Oct-15 12-Nov-15 17 100.00% 100.00% Completed
503-FAEI-20870 Installation of E&I Support at Mezzanine Deck - Erection Area 215 Ea. 50.170 428 78.39% 3-Feb-16 27-Feb-16 25 100.00% 100.00% Completed
365 984 30.28% 3-Nov-15 4-Feb-16 94 100.00% 100.00%
503-FAEI-20880 Installation of E&I Support at UpperDeck - Assembly Bay 273 Ea. 50.170 662 67.28% 3-Nov-15 27-Nov-15 25 100.00% 100.00% Completed
503-FAEI-20890 Installation of E&I Support at UpperDeck - Erection Area 92 Ea. 50.170 322 32.72% 11-Dec-15 4-Feb-16 56 100.00% 100.00% Completed
779 1469 23-Nov-15 7-Apr-16 137
503-FAEI-20900 Installation of Cable Trays&Ladders 670 m. 50.170 942 64.13% 23-Nov-15 7-Jan-16 46 100.00% 100.00% Completed
503-FAEI-20910 Installation of Tubing Trays&Ladders 109 m. 50.170 527 35.87% 4-Mar-16 7-Apr-16 35 100.00% 100.00% Completed
8442 0.00%
L5 L4 L5 L4 L5 L4
298 905 12-Oct-15 9-Feb-16 121
298 905 12-Oct-15 9-Feb-16 121
503-FAEI-20920 Calibration of Instrument Tags - 01-I1: Process Production 193 Ea. 50.165 535 59.12% 12-Oct-15 3-Dec-15 53 100.00% 100.00% Completed
503-FAEI-20930 Calibration of Instrument Tags - 01-I2 : Production Header 28 Ea. 50.165 76 8.40% 18-Nov-15 1-Dec-15 14 100.00% 100.00% Completed
503-FAEI-20940 Calibration of Instrument Tags - 02-I1 : Test Separator 50 Ea. 50.165 140 15.47% 1-Dec-15 29-Dec-15 29 100.00% 100.00% Completed
503-FAEI-20950 Calibration of Instrument Tags - 03-I1 : Pig Luncher 1 Ea. 50.165 3 0.33% 26-Dec-15 29-Dec-15 4 100.00% 100.00% Completed
503-FAEI-20990 Calibration of Instrument Tags - 10-I1 : Booster Compressor 26 Ea. 50.165 75 8.29% 29-Dec-15 13-Jan-16 16 100.00% 100.00% Completed
14 38 24-Oct-15 21-Nov-15 29
8 22 24-Oct-15 27-Oct-15 4
503-FAEI-21000 Calibration of Instrument Tags - 08-I1 : Closed Drain System 8 Ea. 50.165 22 100.00% 24-Oct-15 27-Oct-15 4 100.00% 100.00% Completed
5 13 20-Nov-15 21-Nov-15 2
503-FAEI-21010 Calibration of Instrument Tags - 09-I1 : Open Drain System 5 Ea. 50.165 13 100.00% 20-Nov-15 21-Nov-15 2 100.00% 100.00% Completed
1 3 20-Nov-15 21-Nov-15 2
503-FAEI-21020 Calibration of Instrument Tags - 06-I1 : HP Vent / LP Vent 1 Ea. 50.165 3 100.00% 20-Nov-15 21-Nov-15 2 100.00% 100.00% Completed
24 68 18-Nov-15 2-Dec-15 15
14 40 20-Nov-15 27-Nov-15 8
503-FAEI-21030 Calibration of Instrument Tags - 04-I1 : Instrument Gas 14 Ea. 50.165 40 100.00% 20-Nov-15 27-Nov-15 8 100.00% 100.00% Completed
10 28 18-Nov-15 2-Dec-15 15
503-FAEI-21040 Calibration of Instrument Tags - 04-I2 : Utility Gas 10 Ea. 50.165 28 100.00% 27-Nov-15 2-Dec-15 6 100.00% 100.00% Completed
21 59 2-Oct-15 15-Oct-15 14
21 59 2-Oct-15 15-Oct-15 14
503-FAEI-21070 Calibration of Instrument Tags - 11-I1 : Chemical Injection 21 Ea. 50.165 59 100.00% 3-Oct-15 15-Oct-15 13 100.00% 100.00% Completed
57 224 2-Oct-15 30-Jan-16 121
51 208 2-Oct-15 12-Dec-15 72
503-FAEI-21090 Calibration of Instrument Tags - 13-C1 : Back Start 3 Ea. 50.165 8 3.85% 11-Dec-15 12-Dec-15 2 100.00% 100.00% Completed
503-FAEI-21100 Calibration of Instrument Tags - 13-C3 : Wellhead Control Panel 48 Ea. 50.165 200 96.15% 2-Oct-15 2-Nov-15 32 100.00% 100.00% Completed
1 3 14-Dec-15 15-Dec-15 2
503-FAEI-21120 Calibration of Instrument Tags - 14-E6 : TEG - Gas Platform 1 Ea. 50.165 3 100.00% 14-Dec-15 15-Dec-15 2 100.00% 100.00% Completed
5 13 29-Jan-16 30-Jan-16 2
503-FAEI-21130 Calibration of Instrument Tags - 17-S3 : Fire & Gas Detector 5 Ea. 50.165 13 100.00% 29-Jan-16 30-Jan-16 2 100.00% 100.00% Completed
414 1294 0.00%
1st 2nd 1st 2nd
L5 L4 20.0% 20.0% 7.5% 7.5% L5 L4 L5 L4
295 4601 24-Mar-16 26-Apr-16 34
295 4601 24-Mar-16 26-Apr-16 34
503-FAEI-21140 Cables Installation for 01-I1: Process Production 121 Sch. 50.175 1968 42.77% 7-Apr-16 26-Apr-16 20 121 121 121 121 100.00% 100.00% Completed
503-FAEI-21150 Cables Installation for 01-I2 : Production Header 50 Sch. 50.175 678 14.74% 28-Mar-16 4-Apr-16 8 50 50 50 50 100.00% 100.00% Completed
503-FAEI-21160 Cables Installation for 02-I1 : Test Separator 76 Sch. 50.175 1033 22.45% 7-Apr-16 18-Apr-16 12 76 76 76 76 100.00% 100.00% Completed
503-FAEI-21200 Cables Installation for 10-I1 : Booster Compressor 48 Sch. 50.175 651 14.15% 24-Mar-16 31-Mar-16 8 48 48 48 48 100.00% 100.00% Completed
9 124 2-Apr-16 20-Apr-16 19
6 82 16-Apr-16 20-Apr-16 5
503-FAEI-21210 Cables Installation for 08-I1 : Closed Drain System 6 Sch. 50.175 82 100.00% 16-Apr-16 20-Apr-16 5 6 6 6 6 100.00% 100.00% Completed
3 42 2-Apr-16 12-Apr-16 11
503-FAEI-21220 Cables Installation for 09-I1 : Open Drain System 3 Sch. 50.175 42 100.00% 2-Apr-16 12-Apr-16 11 3 3 3 3 100.00% 100.00% Completed
16 217 26-Mar-16 16-Apr-16 22
10 135 1-Apr-16 16-Apr-16 16
503-FAEI-21230 Cables Installation for 04-I1 : Instrument Gas 10 Sch. 50.175 135 100.00% 1-Apr-16 16-Apr-16 16 10 10 10 10 100.00% 100.00% Completed
6 82 26-Mar-16 16-Apr-16 22
503-FAEI-21240 Cables Installation for 04-I2 : Utility Gas 6 Sch. 50.175 82 100.00% 1-Apr-16 16-Apr-16 16 6 6 6 6 100.00% 100.00% Completed
9 125 1-Apr-16 10-May-16 40
9 125 1-Apr-16 10-May-16 40
503-FAEI-21270 Cables Installation for 11-I1 : Chemical Injection 9 Sch. 50.175 125 100.00% 26-Apr-16 10-May-16 15 9 9 9 9 100.00% 100.00% Completed
262 3215 18-Nov-15 12-May-16 177
63 776 18-Nov-15 27-Feb-16 102
503-FAEI-21290 Cables Installation for 13-C2 : PLC and Control system 63 Sch. 50.175 776 100.00% 12-Feb-16 27-Feb-16 16 63 63 63 63 100.00% 100.00% Completed
175 2139 24-Nov-15 12-May-16 171
503-FAEI-21320 Cables Installation for 14-E2 : AC Diesel Generators 1 Sch. 50.175 16 0.75% 25-Mar-16 1-Apr-16 8 1 1 1 1 100.00% 100.00% Completed
503-FAEI-21330 Cables Installation for 14-E3 : DC Supply 36 Sch. 50.175 368 17.20% 12-Feb-16 5-Mar-16 23 26 36 26 36 92.36% 100.00% Delayed
503-FAEI-21340 Cables Installation for 14-E4 : Power & Lighting and Outlet 118 Sch. 50.175 1480 69.19% 24-Nov-15 22-Dec-15 29 118 118 118 118 100.00% 100.00% Completed
503-FAEI-21360 Cables Installation for 14-E6 : TEG - Gas Platform 9 Sch. 50.175 125 5.84% 20-Feb-16 8-Mar-16 18 9 9 9 9 100.00% 100.00% Completed
503-FAEI-21370 Cables Installation for 16-E1 : Navigation Aids System 11 Sch. 50.175 150 7.01% 12-Feb-16 3-Mar-16 21 11 11 11 11 100.00% 100.00% Completed
13 150 12-Feb-16 7-Apr-16 56
503-FAEI-21380 Cables Installation for 15-T1 : Comunication System 13 Sch. 50.175 150 100.00% 12-Feb-16 7-Apr-16 56 13 11 13 11 95.77% 100.00% Delayed
11 150 12-Feb-16 19-Mar-16 37
503-FAEI-21390 Cables Installation for 17-S2 : Emergency Shutdown 2 Sch. 50.175 27 18.00% 12-Feb-16 19-Feb-16 8 2 2 2 2 100.00% 100.00% Completed
503-FAEI-21400 Cables Installation for 17-S3 : Fire & Gas Detector 5 Sch. 50.175 68 45.33% 11-Mar-16 14-Mar-16 4 5 5 5 5 100.00% 100.00% Completed
503-FAEI-21410 Cables Installation for 17-S4 : Beacon Light & Siren 4 Sch. 50.175 55 36.67% 12-Mar-16 19-Mar-16 8 4 4 4 4 100.00% 100.00% Completed
591 8282 581 589 581 589 -0.42%
L5 L4 L5 L4 L5 L4
295 531 29-Apr-16 16-May-16 18
295 531 29-Apr-16 16-May-16 18
503-FAEI-21420 Cables Continuity Check for 01-I1: Process Production 121 Sch. 50.180 218 41.05% 4-May-16 12-May-16 9 92.41% 100.00% Delayed
503-FAEI-21430 Cables Continuity Check for 01-I2 : Production Header 50 Sch. 50.180 75 14.12% 4-May-16 7-May-16 4 90.40% 100.00% Delayed
503-FAEI-21440 Cables Continuity Check for 02-I1 : Test Separator 76 Sch. 50.180 135 25.42% 7-May-16 11-May-16 5 90.55% 100.00% Delayed
503-FAEI-21480 Cables Continuity Check for 10-I1 : Booster Compressor 48 Sch. 50.180 72 13.56% 13-May-16 16-May-16 4 90.08% 100.00% Delayed
9 13 6-May-16 23-May-16 18
6 9 6-May-16 21-May-16 16
503-FAEI-21490 Cables Continuity Check for 08-I1 : Closed Drain System 6 Sch. 50.180 9 100.00% 6-May-16 21-May-16 16 90.50% 100.00% Delayed
3 4 7-May-16 23-May-16 17
503-FAEI-21500 Cables Continuity Check for 09-I1 : Open Drain System 3 Sch. 50.180 4 100.00% 7-May-16 23-May-16 17 90.50% 100.00% Delayed
16 24 20-Apr-16 19-May-16 30
10 15 7-May-16 19-May-16 13
503-FAEI-21510 Cables Continuity Check for 04-I1 : Instrument Gas 10 Sch. 50.180 15 100.00% 7-May-16 19-May-16 13 90.75% 100.00% Delayed
6 9 20-Apr-16 18-May-16 29
503-FAEI-21520 Cables Continuity Check for 04-I2 : Utility Gas 6 Sch. 50.180 9 100.00% 9-May-16 18-May-16 10 90.92% 100.00% Delayed
9 18 12-May-16 11-Jun-16 31
9 18 12-May-16 11-Jun-16 31
503-FAEI-21550 Cables Continuity Check for 11-I1 : Chemical Injection 9 Sch. 50.180 18 100.00% 12-May-16 21-May-16 10 90.50% 100.00% Delayed
262 409 29-Apr-16 23-May-16 25
63 59 6-May-16 11-May-16 6
503-FAEI-21570 Cables Continuity Check for 13-C2 : PLC and Control system 63 Sch. 50.180 59 100.00% 6-May-16 9-May-16 4 72.14% 100.00% Delayed
175 254 29-Apr-16 23-May-16 25
503-FAEI-21600 Cables Continuity Check for 14-E2 : AC Diesel Generators 1 Sch. 50.180 3 1.18% 9-May-16 11-May-16 3 93.00% 100.00% Delayed
503-FAEI-21610 Cables Continuity Check for 14-E3 : DC Supply 36 Sch. 50.180 26 10.24% 13-May-16 16-May-16 4 72.48% 100.00% Delayed
503-FAEI-21620 Cables Continuity Check for 14-E4 : Power & Lighting and Outlet 118 Sch. 50.180 196 77.17% 29-Apr-16 7-May-16 9 87.17% 100.00% Delayed
503-FAEI-21640 Cables Continuity Check for 14-E6 : TEG - Gas Platform 9 Sch. 50.180 13 5.12% 13-May-16 16-May-16 4 92.72% 100.00% Delayed
503-FAEI-21650 Cables Continuity Check for 16-E1 : Navigation Aids System 11 Sch. 50.180 16 6.30% 6-May-16 9-May-16 4 92.73% 100.00% Delayed
13 74 6-May-16 9-May-16 4
503-FAEI-21660 Cables Continuity Check for 15-T1 : Comunication System 13 Sch. 50.180 74 100.00% 6-May-16 9-May-16 4 72.23% 100.00% Delayed
11 22 9-May-16 12-May-16 4
503-FAEI-21670 Cables Continuity Check for 17-S2 : Emergency Shutdown 2 Sch. 50.180 3 13.64% 9-May-16 11-May-16 3 93.00% 100.00% Delayed
503-FAEI-21680 Cables Continuity Check for 17-S3 : Fire & Gas Detector 5 Sch. 50.180 12 54.55% 10-May-16 12-May-16 3 92.50% 100.00% Delayed
503-FAEI-21690 Cables Continuity Check for 17-S4 : Beacon Light & Siren 4 Sch. 50.180 7 31.82% 10-May-16 12-May-16 3 90.50% 100.00% Delayed
591 995 -12.28%
L5 L4 L5 L4 L5 L4
339 508 4-May-16 6-Jun-16 34
72 112 4-May-16 7-May-16 4
72 112 4-May-16 7-May-16 4
503-FAEI-21700 Tubings Installation for 06-I1 : HP Vent / LP Vent 72 m. 50.175 112 100.00% 4-May-16 7-May-16 4 91.50% 100.00% Delayed
189 153 17-May-16 4-Jun-16 19
189 153 17-May-16 4-Jun-16 19
503-FAEI-21710 Tubings Installation for 11-I1 : Chemical Injection 189 m. 50.175 153 100.00% 31-May-16 4-Jun-16 5 91.50% 100.00% Delayed Should be finished
78 243 4-May-16 6-Jun-16 34
69 122 3-Jun-16 6-Jun-16 4
503-FAEI-21730 Tubings Installation for 13-C1 : Back Start 69 m. 50.175 122 100.00% 3-Jun-16 6-Jun-16 4 95.00% 100.00% Delayed
9 121 4-May-16 9-May-16 6
503-FAEI-21740 Tubings Installation for 14-E6 : TEG - Gas Platform 9 m. 50.175 20 16.53% 4-May-16 6-May-16 3 91.50% 100.00% Delayed
3478 12-Feb-16 13-Jun-16 123
2874 870 12-Feb-16 16-Mar-16 34
503-FAEI-21760 Pre-Cutting and Pre-Bending 2874 m. 50.175 870 100.00% 12-Feb-16 16-Mar-16 34 100.00% 100.00% Completed
2535 2608 4-May-16 13-Jun-16 41
483 227 11-May-16 8-Jun-16 29
483 227 11-May-16 8-Jun-16 29
503-FAEI-21780 Tubings Installation for 01-I1: Process Production 456 m. 50.175 195 85.90% 31-May-16 8-Jun-16 9 95.00% 100.00% Delayed Should be finished
503-FAEI-21790 Tubings Installation for 10-I1 : Booster Compressor 27 m. 50.175 32 14.10% 11-May-16 19-May-16 9 95.00% 100.00% Delayed
2052 2381 4-May-16 13-Jun-16 41
1273 1529 18-May-16 13-Jun-16 27
503-FAEI-21800 Tubings Installation for 13-C3 : Wellhead Control Panel 1273 m. 50.175 1529 100.00% 18-May-16 13-Jun-16 27 94.13% 100.00% Delayed Should be finished
779 852 4-May-16 4-Jun-16 32
503-FAEI-21810 Tubings Installation for 17-S1 : Fire Emergency Shutdown (FESD) 531 m. 50.175 579 67.96% 18-May-16 4-Jun-16 18 95.00% 100.00% Delayed Should be finished
503-FAEI-21820 Tubings Installation for 17-S2 : Emergency Shutdown 248 m. 50.175 273 32.04% 4-May-16 21-May-16 18 90.00% 100.00% Delayed
2874 3986 -4.71%
L5 L4 L5 L4 L5 L4
339 102 23-May-16 27-May-16 5
72 9 27-May-16 27-May-16 1
72 9 27-May-16 27-May-16 1
503-FAEI-21830 Tubings Leak Test for 06-I1 : HP Vent / LP Vent 72 m. 50.180 9 100.00% 27-May-16 27-May-16 1 90.00% 100.00% Delayed
189 50 26-May-16 26-May-16 1
189 50 26-May-16 26-May-16 1
503-FAEI-21840 Tubings Leak Test for 11-I1 : Chemical Injection 189 m. 50.180 50 100.00% 26-May-16 26-May-16 1 90.50% 100.00% Delayed
78 43 23-May-16 26-May-16 4
Sub-System - 7001 : Chemical (C) 100.00% 90.50% 100.00%
189 5.00%
System - 8000 : Others 42.16% 95.12% 100.00%
System - 2000 : Drains & Reliefs 8.82% 90.00% 100.00%
Sub-System - 2500 : Blow Down (BD) 100.00% 90.00% 100.00%
72
System - 7000 : Chemicals 49.02% 90.50% 100.00%
Status
Next 2 Wks
As Per Planed
RemarkL3
Start Finish Dur.
Tested Check Sheet : PLT-T L3 L3
90% 10%
Bare Tube Leak Test 35.92% 92.40% 100.00%
Sub-System - 8000D : Safety Intrergrity System (SIS) 35.78% 93.40% 100.00%
531 50.00%
248
SUB-TOTAL OF TUBINGS INSTALLATION 16.56% 2874 95.29% 100.00%
456 50.00%
27 50.00%
System - 8000 : Others 91.30% 93.86% 100.00%
Sub-System - 8000A : Process Control 64.22% 94.13% 100.00%
1273 41.25%
2874
Field Installation and Hook-Up 74.99% 93.96% 100.00%
System - 1000 : Process Production 8.70% 95.00% 100.00%
Sub-System - 1001 : Process Liquid & Vapour (P) 100.00% 95.00% 100.00%
Sub-System - 8000B : Electrical Generation and Distribution 49.79% 98.60% 100.00%
9 15.00%
TPU Jacket Tube Installation 87.26% 95.47% 100.00%
Preparation Works 25.01% 100.00% 100.00%
189 15.00%
System - 8000 : Others 47.83% 96.79% 100.00%
Sub-System - 8000A : Process Control 50.21% 95.00% 100.00%
69 50.00%
91.50% 100.00%
72 15.00%
System - 7000 : Chemicals 30.12% 91.50% 100.00%
System - 2000 : Drains & Reliefs 22.05%
Sub-System - 7001 : Chemical (C) 100.00% 91.50% 100.00%
Status
Next 2 Wks
As Per Planed
RemarkL3
Start Finish Dur.
Tube Running Check Sheet : PIC-T L3 L3
90% 10%
Bare Tube Installation 12.74% 94.03% 100.00%
100.00%SUB-TOTAL OF CABLES CONTINUITY & INSULATION TEST 4.13% 558 87.72%
2 30.00%
5 25.00%
4 5.00%
TUBINGS LEAK TEST QTY Unit Cost Code
Budgeted
Mhrs
WTG% Baseline Activity Milestones % Actual %Plan
91.50% 100.00%
Sub-System - 2500 : Blow Down (BD) 100.00%
72.23% 100.00%
10 30.00%
Sub-System - 8000D : Safety Intrergrity System (SIS) 5.38% 91.93% 100.00%
9 27.22%
11 27.27%
Sub-System - 8000C : Communication 18.09%
28 24.83%
110 32.68%
86.37% 100.00%
1 30.00%
49 21.36%
Sub-System - 8000B : Electrical Generation and Distribution 62.10%
82.06% 100.00%
Sub-System - 8000A : Process Control 14.43% 72.14% 100.00%
9 5.00%
System - 8000 : Others 41.11%
90.50% 100.00%
Sub-System - 7001 : Chemical (C) 100.00% 90.50% 100.00%
System - 7000 : Chemicals 1.81%
90.92% 100.00%
6 9.17%
10 7.50%
Sub-System - 4500 : Gas Utility (GU) 37.50%
Sub-System - 4400 : Gas Instrument (GI) 62.50% 90.75% 100.00%
24.05%
50 4.00%
76 5.53%
90.50%
3 5.00%
System - 4000 : Utility Generals 2.41% 90.81% 100.00%
6 5.00%
Sub-System - 2100 : Open Drain (DO) 30.77%
90.50% 100.00%
Sub-System - 2001 : Closed Drain (DC) 69.23% 90.50% 100.00%
RemarkL3
Start Finish Dur.
Tested Check Sheet : PLT-C
Activity Milestones % Actual %Plan
Status
Next 2 Wks
As Per Planed
L3 L3
90% 10%
CABLES CONTINUITY & INSULATION TEST QTY Unit Cost Code
Budgeted
Mhrs
WTG% Baseline
Sub-System - 1001 : Process Liquid & Vapour (P) 100.00% 91.78% 100.00%
System - 1000 : Process Production 53.37% 91.78% 100.00%
48 0.83%
99.58% 100.00%
2
5
4
SUB-TOTAL OF CABLES INSTALLATION 34.40%
TUBINGS INSTALLATION QTY Unit Cost Code
Budgeted
Mhrs
WTG% Baseline Activity Milestones % Actual %Plan
System - 2000 : Drains & Reliefs 1.31%
121
100.00%
13
Sub-System - 8000D : Safety Intrergrity System (SIS) 4.67% 100.00% 100.00%
9
11
Sub-System - 8000C : Communication 4.67% 95.77%
100.00%
1
36
118
63
Sub-System - 8000B : Electrical Generation and Distribution 66.53% 98.69%
100.00%
Sub-System - 8000A : Process Control 24.14% 100.00% 100.00%
9
System - 8000 : Others 38.82% 98.93%
System - 7000 : Chemicals 1.51% 100.00% 100.00%
Sub-System - 7001 : Chemical (C) 100.00% 100.00% 100.00%
Sub-System - 4500 : Gas Utility (GU) 37.79% 100.00% 100.00%
6
Sub-System - 4400 : Gas Instrument (GI) 62.21% 100.00% 100.00%
10
3
System - 4000 : Utility Generals 2.62% 100.00% 100.00%
6
Sub-System - 2100 : Open Drain (DO) 33.87% 100.00% 100.00%
System - 2000 : Drains & Reliefs 1.50% 100.00% 100.00%
Sub-System - 2001 : Closed Drain (DC) 66.13% 100.00% 100.00%
50
76
48
Sub-System - 1001 : Process Liquid & Vapour (P) 100.00% 100.00% 100.00%
121
45%
System - 1000 : Process Production 55.55% 100.00% 100.00%
Next 2 Wks
As Per Planed
Remark
Start Finish Dur.
Pulled
Activity Milestones
Status
Glanded Terminated
L3 L3
100.00% 100.00%
CABLES INSTALLATION QTY Unit Cost Code
Budgeted
Mhrs
Baseline
5 100.00%
SUB-TOTAL OF CALIBRATION OF INSTRUMENTS TAG 5.37%
100.00% 100.00%
1 100.00%
Sub-System - 8000D : Safety Intrergrity System (SIS) 5.80% 100.00% 100.00%
WTG% % Actual %Plan
L3
3 100.00%
48 100.00%
Sub-System - 8000B : Electrical Generation and Distribution 1.34%
100.00% 100.00%
Sub-System - 8000A : Process Control 92.86% 100.00% 100.00%
21 100.00%
System - 8000 : Others 17.31%
100.00% 100.00%
Sub-System - 7001 : Chemical (C) 100.00% 100.00% 100.00%
System - 7000 : Chemicals 4.56%
100.00% 100.00%
10 100.00%
14 100.00%
Sub-System - 4500 : Gas Utility (GU) 41.18%
100.00% 100.00%
Sub-System - 4400 : Gas Instrument (GI) 58.82% 100.00% 100.00%
1 100.00%
System - 4000 : Utility Generals 5.26%
100.00% 100.00%
5 100.00%
Sub-System - 2500 : Blow Down (BD) 7.89% 100.00% 100.00%
8 100.00%
Sub-System - 2100 : Open Drain (DO) 34.21%
100.00% 100.00%
Sub-System - 2001 : Closed Drain (DC) 57.89% 100.00% 100.00%
26 100.00%
System - 2000 : Drains & Reliefs 2.94%
1 100.00%
193 100.00%
28 100.00%
50 100.00%
100.00%
Sub-System - 1001 : Process Liquid & Vapour (P) 100.00% 100.00% 100.00%
System - 1000 : Process Production 69.94% 414 100.00%
Next 2 Wks
As Per Planed
RemarkL3
Start Finish Dur.
Calibrated
Activity Milestones % Actual %Plan
StatusCheck Sheet : PCC L3 L3
90%
100.00% 100.00%
CALIBRATION OF INSTRUMENTS TAG QTY Unit Cost Code
Budgeted
Mhrs
WTG% Baseline
670 670
109 109
SUB-TOTAL OF E&I SUPPORTS, LADDERS AND TRAYS 35.06%
10%
Installation of E&I Trays&Ladders 31.13% 100.00% 100.00%
Upper Deck
273 273
92 92
Mezzanine Deck
37 37
215 215
Cellar Deck
475 475
161 161
Sub-Cellar Deck
1 1
30 30
100.00% 100.00%
Installation of E&I Supports 68.87% 100.00% 100.00%
365 365
Installation 55.90%
31 31
636 636
252 252
L3
90% 10%
Fabrication 44.10% 100.00% 100.00%
CHEVRON : CVX-PHASE 50
PROGRESS MEASUREMENT WORK SHEET FOR E&I AND PRE-COMMISSIONING WORKS
WHP 50/3 : GAS PLATFORM
WHP 50/3 : GAS PLATFORM : E&I INSTALLATION
E&I SUPPORTS, LADDERS AND TRAYS QTY Unit Cost Code
Budgeted
Mhrs
%Plan
Status
Next 2 Wks
As Per Planed
RemarkL3
Start Finish Dur.
WTG% Baseline Activity Milestones % Actual
Fabricated/Installed Accepted /Painted/Cleaning L3
591
Page 3 of 10 Prepared By : Nattakarn S.
Activity ID Activity Name Num. Budgeted Units Planned Start Planned Finish % Actual 1-Jun-16
CHEVRON : CVX-PHASE 50
PROGRESS MEASUREMENT WORK SHEET FOR E&I AND PRE-COMMISSIONING WORKS
WHP 50/3 : GAS PLATFORM
69 21 23-May-16 24-May-16 2
503-FAEI-21860 Tubings Leak Test for 13-C1 : Back Start 69 m. 50.180 21 100.00% 23-May-16 24-May-16 2 90.00% 100.00% Delayed
9 22 25-May-16 26-May-16 2
503-FAEI-21870 Tubings Leak Test for 14-E6 : TEG - Gas Platform 9 m. 50.180 11 50.00% 25-May-16 25-May-16 1 100.00% 100.00% Completed
2535 182 23-May-16 27-May-16 5
483 56 27-May-16 27-May-16 1
483 56 27-May-16 27-May-16 1
503-FAEI-21890 Tubings Leak Test for 01-I1: Process Production 456 m. 50.180 45 80.36% 27-May-16 27-May-16 1 90.25% 100.00% Delayed
503-FAEI-21900 Tubings Leak Test for Booster Compressor 27 m. 50.180 11 19.64% 27-May-16 27-May-16 1 90.00% 100.00% Delayed
2052 126 23-May-16 27-May-16 5
1273 90 23-May-16 24-May-16 2
503-FAEI-21910 Tubings Leak Test for 13-C3 : Wellhead Control Panel 1273 m. 50.180 90 100.00% 23-May-16 24-May-16 2 90.00% 100.00% Delayed
779 36 27-May-16 27-May-16 1
503-FAEI-21920 Tubings Leak Test for 17-S1 : Fire Emergency Shutdown (FESD) 531 m. 50.180 18 50.00% 27-May-16 27-May-16 1 93.00% 100.00% Delayed
503-FAEI-21930 Tubings Leak Test for 17-S2 : Emergency Shutdown 248 m. 50.180 18 50.00% 27-May-16 27-May-16 1 90.50% 100.00% Delayed
2874 284 -8.88%
L5 L4 L5 L4 L5 L4
271 363 6-May-16 20-Jun-16 46
271 363 6-May-16 20-Jun-16 46
503-FAEI-21940 Hook-Up of E&I Tags for 01-I1: Process Production 145 Ea. 50.175 148 40.77% 7-May-16 27-May-16 21 77.33% 100.00% Delayed
503-FAEI-21950 Hook-Up of E&I Tags for 01-I2 : Production Header 28 Ea. 50.175 43 11.85% 6-May-16 2-Jun-16 28 89.68% 100.00% Delayed Should be finished
503-FAEI-21960 Hook-Up of E&I Tags for 02-I1 : Test Separator 52 Ea. 50.175 75 20.66% 16-May-16 3-Jun-16 19 83.08% 100.00% Delayed Should be finished
503-FAEI-21970 Hook-Up of E&I Tags for 03-I1 : Pig Luncher 1 Ea. 50.175 1 0.28% 11-May-16 13-May-16 3 0.00% 100.00% Delayed & Not Start
503-FAEI-21980 Hook-Up of E&I Tags for 03-I2 : Pig Receiver - Option 18 Ea. 50.175 55 15.15% 11-May-16 19-May-16 9 0.00% 100.00% Delayed & Not Start
503-FAEI-22010 Hook-Up of E&I Tags for 10-I1 : Booster Compressor 27 Ea. 50.175 41 11.29% 3-Jun-16 20-Jun-16 18 84.99% 100.00% Delayed
15 22 30-Apr-16 27-May-16 28
9 13 30-Apr-16 11-May-16 12
503-FAEI-22020 Hook-Up of E&I Tags for 08-I1 : Closed Drain System 9 Ea. 50.175 13 100.00% 30-Apr-16 11-May-16 12 82.67% 100.00% Delayed
5 8 13-May-16 14-May-16 2
503-FAEI-22030 Hook-Up of E&I Tags for 09-I1 : Open Drain System 5 Ea. 50.175 8 100.00% 13-May-16 14-May-16 2 74.40% 100.00% Delayed
1 1 26-May-16 27-May-16 2
503-FAEI-22040 Hook-Up of E&I Tags for 06-I1 : HP Vent / LP Vent 1 Ea. 50.175 1 100.00% 26-May-16 27-May-16 2 0.00% 100.00% Delayed & Not Start
28 41 7-Apr-16 12-May-16 36
17 23 7-Apr-16 19-Apr-16 13
503-FAEI-22050 Hook-Up of E&I Tags for 04-I1 : Instrument Gas 17 Ea. 50.175 23 100.00% 7-Apr-16 19-Apr-16 13 81.88% 100.00% Delayed
11 18 9-Apr-16 12-May-16 34
503-FAEI-22060 Hook-Up of E&I Tags for 04-I2 : Utility Gas 11 Ea. 50.175 18 100.00% 9-Apr-16 21-Apr-16 13 76.09% 100.00% Delayed
24 35 21-May-16 10-Jun-16 21
24 35 21-May-16 10-Jun-16 21
503-FAEI-22090 Hook-Up of E&I Tags for 11-I1 : Chemical Injection 24 Ea. 50.175 35 100.00% 24-May-16 10-Jun-16 18 93.00% 100.00% Delayed Should be finished
231 332 6-Feb-16 23-Jun-16 139
67 226 21-Apr-16 16-May-16 26
503-FAEI-22110 Hook-Up of E&I Tags for 13-C1 : Back Start 4 Ea. 50.175 7 3.10% 21-Apr-16 26-Apr-16 6 92.50% 100.00% Delayed
503-FAEI-22120 Hook-Up of E&I Tags for 13-C2 : PLC and Control system 14 Ea. 50.175 22 9.73% 28-Apr-16 12-May-16 15 69.33% 100.00% Delayed
503-FAEI-22130 Hook-Up of E&I Tags for 13-C3 : Wellhead Control Panel 49 Ea. 50.175 197 87.17% 28-Apr-16 16-May-16 19 89.39% 100.00% Delayed
133 60 6-Feb-16 23-Jun-16 139
503-FAEI-22150 Hook-Up of E&I Tags for 14-E2 : AC Diesel Generators 1 Ea. 50.175 1 1.67% 14-Jun-16 22-Jun-16 9 100.00% 100.00% Completed
503-FAEI-22160 Hook-Up of E&I Tags for 14-E3 : DC Supply 8 Ea. 50.175 10 16.67% 7-Mar-16 15-Mar-16 9 100.00% 100.00% Completed
503-FAEI-22170 Hook-Up of E&I Tags for 14-E4 : Power & Lighting and Outlet 110 Ea. 50.175 28 46.67% 6-Feb-16 11-Mar-16 35 99.79% 100.00% Delayed
503-FAEI-22190 Hook-Up of E&I Tags for 14-E6 : TEG - Gas Platform 5 Ea. 50.175 8 13.33% 11-Apr-16 22-Apr-16 12 98.00% 100.00% Delayed
503-FAEI-22200 Hook-Up of E&I Tags for 16-E1 : Navigation Aids System 9 Ea. 50.175 13 21.67% 21-Mar-16 30-Mar-16 10 100.00% 100.00% Completed
5 7 21-Mar-16 30-Mar-16 10
503-FAEI-22210 Hook-Up of E&I Tags for 15-T1 : Comunication System 5 Ea. 50.175 7 100.00% 21-Mar-16 30-Mar-16 10 100.00% 100.00% Completed
26 39 7-May-16 3-Jun-16 28
503-FAEI-22220 Hook-Up of E&I Tags for 17-S2 : Emergency Shutdown 10 Ea. 50.175 13 33.33% 7-May-16 18-May-16 12 60.00% 100.00% Delayed
503-FAEI-22230 Hook-Up of E&I Tags for 17-S3 : Fire & Gas Detector 5 Ea. 50.175 8 20.51% 27-May-16 3-Jun-16 8 100.00% 100.00% Completed
503-FAEI-22240 Hook-Up of E&I Tags for 17-S4 : Beacon Light & Siren 11 Ea. 50.175 18 46.15% 7-May-16 11-May-16 5 100.00% 100.00% Completed
569 793 -20.51%
24076 -2.21%
L5 L4 L5 L4 L5 L4
704 31-May-16 4-Jun-16 5
61 704 31-May-16 4-Jun-16 5
61 704 31-May-16 4-Jun-16 5
503-FAPC-21030 Fuction Test of 14-E2 : AC Diesel Generators 4 Pac. 60.220 71 10.09% 31-May-16 2-Jun-16 3 90.00% 100.00% Delayed Should be finished
503-FAPC-21040 Fuction Test of 14-E3 : DC Supply 19 Pac. 60.220 174 24.72% 31-May-16 2-Jun-16 3 90.00% 100.00% Delayed Should be finished
503-FAPC-21050 Fuction Test of 14-E4 : Power & Lighting and Outlet 23 Pac. 60.220 322 45.74% 31-May-16 2-Jun-16 3 90.00% 100.00% Delayed Should be finished
503-FAPC-21070 Fuction Test of 14-E6 : TEG - Gas Platform 7 Pac. 60.220 21 2.98% 3-Jun-16 3-Jun-16 1 0.00% 100.00% Delayed & Not Start Should be started
503-FAPC-21080 Fuction Test of 16-E1 : Navigation Aids System 8 Pac. 60.220 116 16.48% 31-May-16 2-Jun-16 3 90.00% 100.00% Delayed Should be finished
1241 30-May-16 4-Jun-16 6
199 823 30-May-16 4-Jun-16 6
199 823 30-May-16 4-Jun-16 6
503-FAPC-21100 Loop Test of 01-I1: Process Production 97 Pac. 60.225 340 41.31% 30-May-16 3-Jun-16 5 0.00% 100.00% Delayed & Not Start Should be finished
503-FAPC-21110 Loop Test of 01-I2 : Production Header 26 Pac. 60.225 94 11.42% 31-May-16 3-Jun-16 4 0.00% 100.00% Delayed & Not Start Should be finished
503-FAPC-21120 Loop Test of 02-I1 : Test Separator 45 Pac. 60.225 191 23.21% 2-Jun-16 3-Jun-16 2 0.00% 100.00% Delayed & Not Start Should be started
503-FAPC-21160 Loop Test of 10-I1 : Booster Compressor 31 Pac. 60.225 156 18.96% 4-Jun-16 4-Jun-16 1 0.00% 90.06% Delayed & Not Start Should be started
9 32 31-May-16 2-Jun-16 3
6 21 31-May-16 2-Jun-16 3
503-FAPC-21170 Loop Test of 08-I1 : Closed Drain System 6 Pac. 60.225 21 100.00% 31-May-16 2-Jun-16 3 0.00% 100.00% Delayed & Not Start Should be finished
3 11 31-May-16 2-Jun-16 3
503-FAPC-21180 Loop Test of 09-I1 : Open Drain System 3 Pac. 60.225 11 100.00% 31-May-16 2-Jun-16 3 0.00% 100.00% Delayed & Not Start Should be finished
14 32 31-May-16 2-Jun-16 3
9 21 31-May-16 2-Jun-16 3
503-FAPC-21190 Loop Test of 04-I1 : Instrument Gas 9 Pac. 60.225 21 100.00% 31-May-16 2-Jun-16 3 0.00% 100.00% Delayed & Not Start Should be finished
5 11 31-May-16 2-Jun-16 3
503-FAPC-21200 Loop Test of 04-I2 : Utility Gas 5 Pac. 60.225 11 100.00% 31-May-16 2-Jun-16 3 0.00% 100.00% Delayed & Not Start Should be finished
9 32 31-May-16 2-Jun-16 3
9 32 31-May-16 2-Jun-16 3
503-FAPC-21230 Loop Test of 11-I1 : Chemical Injection 9 Pac. 60.225 32 100.00% 31-May-16 2-Jun-16 3 0.00% 100.00% Delayed & Not Start Should be finished
97 322 31-May-16 3-Jun-16 4
81 187 31-May-16 3-Jun-16 4
503-FAPC-21250 Loop Test of 13-C3 : Wellhead Control Panel 81 Pac. 60.225 187 100.00% 31-May-16 3-Jun-16 4 0.00% 100.00% Delayed & Not Start Should be finished
1 4 31-May-16 2-Jun-16 3
503-FAPC-21260 Loop Test of 15-T1 : Comunication System 1 Pac. 60.225 4 100.00% 31-May-16 2-Jun-16 3 0.00% 100.00% Delayed & Not Start Should be finished
15 131 31-May-16 2-Jun-16 3
503-FAPC-21270 Loop Test of 17-S2 : Emergency Shutdown 3 Pac. 60.225 12 9.16% 31-May-16 2-Jun-16 3 90.00% 100.00% Delayed Should be finished
503-FAPC-21280 Loop Test of 17-S3 : Fire & Gas Detector 5 Pac. 60.225 28 21.37% 31-May-16 2-Jun-16 3 0.00% 100.00% Delayed & Not Start Should be finished
503-FAPC-21290 Loop Test of 17-S4 : Beacon Light & Siren 7 Pac. 60.225 91 69.47% 31-May-16 2-Jun-16 3 90.00% 100.00% Delayed Should be finished
389 1945 -61.47%
L5 L4 L5 L4 L5 L4
503-FAPC-21300 Platform Site Acceptance Test - SAT 100 Pac. 60.235 555 6-Jun-16 11-Jun-16 6 Delayed & Not Start Should be started
100 555 0.00%
2500 -48.68%
-6.58%
SUB-TOTAL OF TUBINGS LEAK TEST 1.18% 91.12% 100.00%
Sub-System - 8000A : Process Control 71.43% 90.00% 100.00%
1273
Sub-System - 8000D : Safety Intrergrity System (SIS) 28.57% 91.75% 100.00%
531 30.00%
248 5.00%
100.00%
Sub-System - 1001 : Process Liquid & Vapour (P) 100.00% 90.20% 100.00%
456 2.50%
27
System - 8000 : Others 69.23% 90.50% 100.00%
System - 1000 : Process Production 30.77% 90.20%
69
Sub-System - 8000B : Electrical Generation and Distribution 51.16% 100.00% 100.00%
9 100.00%
TPU Jacket Tube Leak Test 64.08% 90.41% 100.00%
Sub-System - 8000A : Process Control 48.84% 90.00% 100.00%
91.41% 97.99%OVERALL PROGRESS OF WHP 50/3 : GAS PLATFORM 26576 100.00%
0.00%
TOTAL OF WHP 50/3 : GAS PLATFORM : E&I PRE-COMMISSIONING 9.41% 29.98% 78.66%
100.00% 0.00% 6.67%
SUB-TOTAL OF SITE ACCEPTANC TEST - SAT 22.20% 0.00%
RemarkL3
Start Finish Dur.
Activity Milestones % Actual %Plan
Status
Next 2 Wks
As Per Planed
SAT Completion L3 L3
100%
100.00%
SITE ACCEPTANC TEST - SAT QTY Unit Cost Code
Budgeted
Mhrs
WTG% Baseline
SUB-TOTAL OF LOOP/ FUNCTION TEST 77.80% 38.53%
3
7
0.00% 100.00%
Sub-System - 8000D : Safety Intrergrity System (SIS) 40.68% 70.76% 100.00%
Sub-System - 8000C : Communication 1.24%
28.79% 100.00%
Sub-System - 8000A : Process Control 58.07% 0.00% 100.00%
System - 8000 : Others 25.95%
0.00% 100.00%
Sub-System - 7001 : Chemical (C) 100.00% 0.00% 100.00%
System - 7000 : Chemicals 2.58%
0.00% 100.00%Sub-System - 4500 : Gas Utility (GU) 34.38%
Sub-System - 4400 : Gas Instrument (GI) 65.63% 0.00% 100.00%
0.00% 100.00%
System - 4000 : Utility Generals 2.58% 0.00% 100.00%
Sub-System - 2100 : Open Drain (DO) 34.38%
0.00% 100.00%
Sub-System - 2001 : Closed Drain (DC) 65.63% 0.00% 100.00%
System - 2000 : Drains & Reliefs 2.58%
Sub-System - 1001 : Process Liquid & Vapour (P) 100.00% 5.10% 98.12%
10.85% 98.75%
System - 1000 : Process Production 66.32% 5.10% 98.12%
8
Instrumentation 63.80%
23
4
19
Sub-System - 8000B : Electrical Generation and Distribution 100.00% 87.32% 100.00%
System - 8000 : Others 100.00% 87.32% 100.00%
Electrical 36.20% 87.32% 100.00%
%Plan
Status
Next 2 Wks
As Per Planed
RemarkL3
Start Finish Dur.
WTG% Baseline Activity Milestones % Actual
Tested Check Sheet : PLT-L & PFT
WHP 50/3 : GAS PLATFORM : E&I PRE-COMMISSIONING
LOOP/ FUNCTION TEST QTY Unit Cost Code
Budgeted
Mhrs
TOTAL OF WHP 50/3 : GAS PLATFORM : E&I INSTALLATION 90.59% 97.79% 100.00%
L3 L3
90% 10%
100.00%SUB-TOTAL OF HOOK-UP OF E&I TAG ITEMS 3.29% 79.49%
11 11 100.00%
Sub-System - 8000B : Electrical Generation and Distribution 18.07% 99.64% 100.00%
1 1 100.00%
8 8 100.00%
100.00% 100.00%
Sub-System - 8000D : Safety Intrergrity System (SIS) 11.75% 86.67% 100.00%
Sub-System - 8000C : Communication 2.11%
110 110 97.91%
5 5 80.00%
9
89.88% 100.00%
Sub-System - 8000A : Process Control 68.07% 87.53% 100.00%
System - 8000 : Others 41.87%
93.00% 100.00%
Sub-System - 7001 : Chemical (C) 100.00% 93.00% 100.00%
24 24 30.00%
76.09% 100.00%Sub-System - 4500 : Gas Utility (GU) 43.90%
79.34% 100.00%
Sub-System - 4400 : Gas Instrument (GI) 56.10% 81.88% 100.00%
9 9 24.55%
System - 7000 : Chemicals 4.41%
System - 4000 : Utility Generals 5.17%
74.40% 100.00%
Sub-System - 2500 : Blow Down (BD) 4.55% 0.00% 100.00%
Sub-System - 2100 : Open Drain (DO) 36.36%
8 8 26.67%
4 4 24.00%
75.90% 100.00%
Sub-System - 2001 : Closed Drain (DC) 59.09% 82.67% 100.00%
System - 2000 : Drains & Reliefs 2.77%
25 24 27.69%
100.00%
Sub-System - 1001 : Process Liquid & Vapour (P) 100.00% 68.92% 100.00%
System - 1000 : Process Production 45.78% 68.92%
HOOK-UP OF E&I TAG ITEMS QTY Unit Cost Code
Budgeted
Mhrs
512 486
Next 2 Wks
As Per Planed
RemarkL3
Start Finish Dur.
Activity Milestones % Actual %Plan
StatusL3 L3
WTG% Baseline
Installed Hook-Up Check Sheet : PIC-H
60% 30% 10%
22.27%
27 27 28.93%
48 48
121 121
4 4 25.00%
10
5 5 100.00%
14 93.33%
49 48
9 100.00%
5 5 100.00%
15 15 24.71%
Page 4 of 10 Prepared By : Nattakarn S.
Activity ID Activity Name Num. Budgeted Units Planned Start Planned Finish % Actual 1-Jun-16
L5 L4 L5 L4 L5 L4
1291 3723 21-Aug-15 28-Oct-15 69
504-FAEI-22250 Fabrication of E&I Supports for Sub-Cellar Deck 31 Ea. 50.170 98 2.63% 24-Aug-15 8-Sep-15 16 100.00% 100.00% Completed
504-FAEI-22260 Fabrication of E&I Supports for Cellar Deck 653 Ea. 50.170 1915 51.44% 21-Aug-15 16-Oct-15 57 100.00% 100.00% Completed
504-FAEI-22270 Fabrication of E&I Supports for Mezzanine Deck 243 Ea. 50.170 525 14.10% 25-Sep-15 28-Oct-15 34 100.00% 100.00% Completed
504-FAEI-22280 Fabrication of E&I Supports for Upper Deck 364 Ea. 50.170 1185 31.83% 24-Aug-15 2-Oct-15 40 100.00% 100.00% Completed
4719 16-Oct-15 7-May-16 205
1291 3250 16-Oct-15 11-Mar-16 148
31 106 3.26% 25-Dec-15 3-Feb-16 41 100.00% 100.00%
504-FAEI-22290 Installation of E&I Support at Sub-Cellar Deck - Assembly Bay 1 Ea. 50.170 12 11.32% 25-Dec-15 5-Jan-16 12 100.00% 100.00% Completed
504-FAEI-22300 Installation of E&I Support at Sub-Cellar Deck - Erection Area 30 Ea. 50.170 94 88.68% 18-Jan-16 3-Feb-16 17 100.00% 100.00% Completed
653 1614 49.66% 16-Oct-15 8-Feb-16 116 100.00% 100.00%
504-FAEI-22310 Installation of E&I Support at Cellar Deck - Assembly Bay 475 Ea. 50.170 1035 64.13% 16-Oct-15 11-Nov-15 27 100.00% 100.00% Completed
504-FAEI-22320 Installation of E&I Support at Cellar Deck - Erection Area 178 Ea. 50.170 579 35.87% 23-Nov-15 8-Feb-16 78 100.00% 100.00% Completed
243 546 16.80% 4-Nov-15 11-Mar-16 129 100.00% 100.00%
504-FAEI-22330 Installation of E&I Support at Mezzanine Deck - Assembly Bay 37 Ea. 50.170 118 21.61% 4-Nov-15 20-Nov-15 17 100.00% 100.00% Completed
504-FAEI-22340 Installation of E&I Support at Mezzanine Deck - Erection Area 206 Ea. 50.170 428 78.39% 16-Feb-16 11-Mar-16 25 100.00% 100.00% Completed
364 984 30.28% 13-Nov-15 6-Jan-16 55 100.00% 100.00%
504-FAEI-22350 Installation of E&I Support at UpperDeck - Assembly Bay 273 Ea. 50.170 662 67.28% 13-Nov-15 11-Dec-15 29 100.00% 100.00% Completed
504-FAEI-22360 Installation of E&I Support at UpperDeck - Erection Area 91 Ea. 50.170 322 32.72% 11-Dec-15 6-Jan-16 27 100.00% 100.00% Completed
779 1469 28-Nov-15 7-May-16 162
504-FAEI-22370 Installation of Cable Trays&Ladders 670 m. 50.170 942 64.13% 28-Nov-15 13-Jan-16 47 100.00% 100.00% Completed
504-FAEI-22380 Installation of Tubing Trays&Ladders 109 m. 50.170 527 35.87% 30-Mar-16 7-May-16 39 100.00% 100.00% Completed
8442 0.00%
L5 L4 L5 L4 L5 L4
305 905 27-Oct-15 17-Feb-16 114
305 905 27-Oct-15 17-Feb-16 114
504-FAEI-22390 Calibration of Instrument Tags - 01-I1: Process Production 193 Ea. 50.165 535 59.12% 27-Oct-15 21-Dec-15 56 100.00% 100.00% Completed
504-FAEI-22400 Calibration of Instrument Tags - 01-I2 : Production Header 28 Ea. 50.165 76 8.40% 18-Nov-15 1-Dec-15 14 100.00% 100.00% Completed
504-FAEI-22410 Calibration of Instrument Tags - 02-I1 : Test Separator 50 Ea. 50.165 140 15.47% 1-Dec-15 29-Dec-15 29 100.00% 100.00% Completed
504-FAEI-22420 Calibration of Instrument Tags - 03-I1 : Pig Luncher 1 Ea. 50.165 3 0.33% 11-Dec-15 12-Dec-15 2 100.00% 100.00% Completed
504-FAEI-22460 Calibration of Instrument Tags - 10-I1 : Booster Compressor 26 Ea. 50.165 75 8.29% 29-Dec-15 13-Jan-16 16 100.00% 100.00% Completed
14 38 24-Oct-15 12-Dec-15 50
8 22 24-Oct-15 27-Oct-15 4
504-FAEI-22470 Calibration of Instrument Tags - 08-I1 : Closed Drain System 8 Ea. 50.165 22 100.00% 24-Oct-15 27-Oct-15 4 100.00% 100.00% Completed
5 13 11-Dec-15 12-Dec-15 2
504-FAEI-22480 Calibration of Instrument Tags - 09-I1 : Open Drain System 5 Ea. 50.165 13 100.00% 11-Dec-15 12-Dec-15 2 100.00% 100.00% Completed
1 3 11-Dec-15 12-Dec-15 2
504-FAEI-22490 Calibration of Instrument Tags - 06-I1 : HP Vent / LP Vent 1 Ea. 50.165 3 100.00% 11-Dec-15 12-Dec-15 2 100.00% 100.00% Completed
24 68 27-Nov-15 4-Dec-15 8
14 40 27-Nov-15 3-Dec-15 7
504-FAEI-22500 Calibration of Instrument Tags - 04-I1 : Instrument Gas 14 Ea. 50.165 40 100.00% 27-Nov-15 3-Dec-15 7 100.00% 100.00% Completed
10 28 27-Nov-15 4-Dec-15 8
504-FAEI-22510 Calibration of Instrument Tags - 04-I2 : Utility Gas 10 Ea. 50.165 28 100.00% 27-Nov-15 2-Dec-15 6 100.00% 100.00% Completed
21 59 3-Oct-15 26-Oct-15 24
21 59 3-Oct-15 26-Oct-15 24
504-FAEI-22540 Calibration of Instrument Tags - 11-I1 : Chemical Injection 21 Ea. 50.165 59 100.00% 3-Oct-15 15-Oct-15 13 100.00% 100.00% Completed
57 224 2-Oct-15 30-Jan-16 121
51 208 2-Oct-15 19-Dec-15 79
504-FAEI-22560 Calibration of Instrument Tags - 13-C1 : Back Start 3 Ea. 50.165 8 3.85% 18-Dec-15 19-Dec-15 2 100.00% 100.00% Completed
504-FAEI-22570 Calibration of Instrument Tags - 13-C3 : Wellhead Control Panel 48 Ea. 50.165 200 96.15% 2-Oct-15 2-Nov-15 32 100.00% 100.00% Completed
1 3 21-Dec-15 22-Dec-15 2
504-FAEI-22590 Calibration of Instrument Tags - 14-E6 : TEG - Gas Platform 1 Ea. 50.165 3 100.00% 21-Dec-15 22-Dec-15 2 100.00% 100.00% Completed
5 13 29-Jan-16 30-Jan-16 2
504-FAEI-22600 Calibration of Instrument Tags - 17-S3 : Fire & Gas Detector 5 Ea. 50.165 13 100.00% 29-Jan-16 30-Jan-16 2 100.00% 100.00% Completed
421 1294 0.00%
1st 2nd 1st 2nd
L5 L4 20.0% 20.0% 7.5% 7.5% L5 L4 L5 L4
300 4601 23-Mar-16 26-May-16 65
300 4601 23-Mar-16 26-May-16 65
504-FAEI-22610 Cables Installation for 01-I1: Process Production 121 Sch. 50.175 1968 42.77% 10-May-16 26-May-16 17 121 121 121 121 100.00% 100.00% Completed
504-FAEI-22620 Cables Installation for 01-I2 : Production Header 50 Sch. 50.175 678 14.74% 10-May-16 17-May-16 8 50 50 50 50 100.00% 100.00% Completed
504-FAEI-22630 Cables Installation for 02-I1 : Test Separator 76 Sch. 50.175 1033 22.45% 18-May-16 26-May-16 9 76 76 76 76 100.00% 100.00% Completed
504-FAEI-22640 Cables Installation for 03-I2 : Pig Receiver - Option 5 Sch. 50.175 271 5.89% 29-Apr-16 9-May-16 11 5 5 5 5 100.00% 100.00% Completed
504-FAEI-22670 Cables Installation for 10-I1 : Booster Compressor 48 Sch. 50.175 651 14.15% 23-Mar-16 30-Mar-16 8 48 48 48 48 100.00% 100.00% Completed
9 124 21-Apr-16 4-May-16 14
6 82 21-Apr-16 29-Apr-16 9
504-FAEI-22680 Cables Installation for 08-I1 : Closed Drain System 6 Sch. 50.175 82 100.00% 21-Apr-16 29-Apr-16 9 6 6 6 6 100.00% 100.00% Completed
3 42 25-Apr-16 4-May-16 10
504-FAEI-22690 Cables Installation for 09-I1 : Open Drain System 3 Sch. 50.175 42 100.00% 25-Apr-16 4-May-16 10 3 3 3 3 100.00% 100.00% Completed
16 217 7-Apr-16 23-Apr-16 17
10 135 9-Apr-16 23-Apr-16 15
504-FAEI-22700 Cables Installation for 04-I1 : Instrument Gas 10 Sch. 50.175 135 100.00% 9-Apr-16 23-Apr-16 15 10 10 10 10 100.00% 100.00% Completed
6 82 7-Apr-16 23-Apr-16 17
504-FAEI-22710 Cables Installation for 04-I2 : Utility Gas 6 Sch. 50.175 82 100.00% 9-Apr-16 23-Apr-16 15 6 6 6 6 100.00% 100.00% Completed
9 125 19-Apr-16 23-May-16 35
9 125 19-Apr-16 23-May-16 35
504-FAEI-22740 Cables Installation for 11-I1 : Chemical Injection 9 Sch. 50.175 125 100.00% 18-May-16 23-May-16 6 9 9 9 9 100.00% 100.00% Completed
264 3215 27-Nov-15 16-May-16 172
65 776 27-Nov-15 26-Mar-16 121
504-FAEI-22760 Cables Installation for 13-C2 : PLC and Control system 65 Sch. 50.175 776 100.00% 19-Feb-16 26-Mar-16 37 65 65 65 65 100.00% 100.00% Completed
175 2139 30-Nov-15 16-May-16 169
504-FAEI-22790 Cables Installation for 14-E2 : AC Diesel Generators 1 Sch. 50.175 16 0.75% 25-Mar-16 1-Apr-16 8 1 1 1 1 100.00% 100.00% Completed
504-FAEI-22800 Cables Installation for 14-E3 : DC Supply 36 Sch. 50.175 368 17.20% 19-Feb-16 18-Apr-16 60 26 36 26 36 92.36% 100.00% Delayed
504-FAEI-22810 Cables Installation for 14-E4 : Power & Lighting and Outlet 118 Sch. 50.175 1480 69.19% 30-Nov-15 3-Feb-16 66 118 118 118 118 100.00% 100.00% Completed
504-FAEI-22830 Cables Installation for 14-E6 : TEG - Gas Platform 9 Sch. 50.175 125 5.84% 5-Mar-16 12-Mar-16 8 9 9 9 9 100.00% 100.00% Completed
504-FAEI-22840 Cables Installation for 16-E1 : Navigation Aids System 11 Sch. 50.175 150 7.01% 30-Nov-15 23-Dec-15 24 11 11 11 11 100.00% 100.00% Completed
13 150 19-Feb-16 18-Apr-16 60
504-FAEI-22850 Cables Installation for 15-T1 : Comunication System 13 Sch. 50.175 150 100.00% 19-Feb-16 18-Apr-16 60 13 11 13 11 95.77% 100.00% Delayed
11 150 18-Jan-16 27-Apr-16 101
504-FAEI-22860 Cables Installation for 17-S2 : Emergency Shutdown 2 Sch. 50.175 27 18.00% 18-Jan-16 26-Jan-16 9 2 2 2 2 100.00% 100.00% Completed
504-FAEI-22870 Cables Installation for 17-S3 : Fire & Gas Detector 5 Sch. 50.175 68 45.33% 1-Apr-16 9-Apr-16 9 5 5 5 5 100.00% 100.00% Completed
504-FAEI-22880 Cables Installation for 17-S4 : Beacon Light & Siren 4 Sch. 50.175 55 36.67% 20-Apr-16 27-Apr-16 8 4 4 4 4 100.00% 100.00% Completed
598 8282 588 596 588 596 -0.42%
L5 L4 L5 L4 L5 L4
300 531 9-May-16 21-May-16 13
300 531 9-May-16 21-May-16 13
504-FAEI-22890 Cables Continuity Check for 01-I1: Process Production 121 Sch. 50.180 218 41.05% 10-May-16 17-May-16 8 90.00% 100.00% Delayed
504-FAEI-22900 Cables Continuity Check for 01-I2 : Production Header 50 Sch. 50.180 75 14.12% 10-May-16 12-May-16 3 90.00% 100.00% Delayed
504-FAEI-22910 Cables Continuity Check for 02-I1 : Test Separator 76 Sch. 50.180 135 25.42% 12-May-16 16-May-16 5 90.00% 100.00% Delayed
504-FAEI-22920 Cables Continuity Check for 03-I2 : Pig Receiver - Option 5 Sch. 50.180 31 5.84% 9-May-16 11-May-16 3 90.00% 100.00% Delayed
504-FAEI-22950 Cables Continuity Check for 10-I1 : Booster Compressor 48 Sch. 50.180 72 13.56% 18-May-16 21-May-16 4 90.00% 100.00% Delayed
9 13 9-May-16 14-May-16 6
6 9 9-May-16 11-May-16 3
504-FAEI-22960 Cables Continuity Check for 08-I1 : Closed Drain System 6 Sch. 50.180 9 100.00% 9-May-16 11-May-16 3 90.00% 100.00% Delayed
3 4 12-May-16 14-May-16 3
504-FAEI-22970 Cables Continuity Check for 09-I1 : Open Drain System 3 Sch. 50.180 4 100.00% 12-May-16 14-May-16 3 90.00% 100.00% Delayed
16 24 14-May-16 28-May-16 15
10 15 14-May-16 17-May-16 4
504-FAEI-22980 Cables Continuity Check for 04-I1 : Instrument Gas 10 Sch. 50.180 15 100.00% 14-May-16 17-May-16 4 90.00% 100.00% Delayed
6 9 17-May-16 28-May-16 12
504-FAEI-22990 Cables Continuity Check for 04-I2 : Utility Gas 6 Sch. 50.180 9 100.00% 17-May-16 19-May-16 3 90.00% 100.00% Delayed
9 18 17-May-16 15-Jul-16 60
9 18 17-May-16 15-Jul-16 60
504-FAEI-23020 Cables Continuity Check for 11-I1 : Chemical Injection 9 Sch. 50.180 18 100.00% 17-May-16 19-May-16 3 90.00% 100.00% Delayed
264 409 4-May-16 6-Jun-16 34
65 59 25-May-16 31-May-16 7
504-FAEI-23040 Cables Continuity Check for 13-C2 : PLC and Control system 65 Sch. 50.180 59 100.00% 25-May-16 27-May-16 3 70.62% 100.00% Delayed
175 254 9-May-16 6-Jun-16 29
504-FAEI-23070 Cables Continuity Check for 14-E2 : AC Diesel Generators 1 Sch. 50.180 3 1.18% 9-May-16 11-May-16 3 90.00% 100.00% Delayed
504-FAEI-23080 Cables Continuity Check for 14-E3 : DC Supply 36 Sch. 50.180 26 10.24% 21-May-16 24-May-16 4 70.00% 100.00% Delayed
504-FAEI-23090 Cables Continuity Check for 14-E4 : Power & Lighting and Outlet 118 Sch. 50.180 196 77.17% 28-May-16 6-Jun-16 10 83.90% 100.00% Delayed Should be finished
504-FAEI-23110 Cables Continuity Check for 14-E6 : TEG - Gas Platform 9 Sch. 50.180 13 5.12% 13-May-16 16-May-16 4 90.00% 100.00% Delayed
504-FAEI-23120 Cables Continuity Check for 16-E1 : Navigation Aids System 11 Sch. 50.180 16 6.30% 25-May-16 27-May-16 3 90.00% 100.00% Delayed
13 74 4-May-16 6-May-16 3
504-FAEI-23130 Cables Continuity Check for 15-T1 : Comunication System 13 Sch. 50.180 74 100.00% 4-May-16 6-May-16 3 69.23% 100.00% Delayed
11 22 4-May-16 19-May-16 16
504-FAEI-23140 Cables Continuity Check for 17-S2 : Emergency Shutdown 2 Sch. 50.180 3 13.64% 4-May-16 6-May-16 3 90.00% 100.00% Delayed
504-FAEI-23150 Cables Continuity Check for 17-S3 : Fire & Gas Detector 5 Sch. 50.180 12 54.55% 17-May-16 19-May-16 3 90.00% 100.00% Delayed
504-FAEI-23160 Cables Continuity Check for 17-S4 : Beacon Light & Siren 4 Sch. 50.180 7 31.82% 17-May-16 19-May-16 3 90.00% 100.00% Delayed
598 995 -14.42%
L5 L4 L5 L4 L5 L4
340 508 16-May-16 2-Jun-16 18
72 112 17-May-16 18-May-16 2
72 112 17-May-16 18-May-16 2
504-FAEI-23170 Tubings Installation for 06-I1 : HP Vent / LP Vent 72 m. 50.175 112 100.00% 17-May-16 18-May-16 2 95.00% 100.00% Delayed
189 153 16-May-16 2-Jun-16 18
189 153 16-May-16 2-Jun-16 18
504-FAEI-23180 Tubings Installation for 11-I1 : Chemical Injection 189 m. 50.175 153 100.00% 16-May-16 19-May-16 4 95.00% 100.00% Delayed
79 243 17-May-16 21-May-16 5
70 122 18-May-16 21-May-16 4
504-FAEI-23200 Tubings Installation for 13-C1 : Back Start 70 m. 50.175 122 100.00% 18-May-16 21-May-16 4 95.00% 100.00% Delayed
9 121 17-May-16 19-May-16 3
504-FAEI-23210 Tubings Installation for 14-E6 : TEG - Gas Platform 9 m. 50.175 20 16.53% 17-May-16 17-May-16 1 95.00% 100.00% Delayed
3478 4-Mar-16 28-May-16 86
2874 870 4-Mar-16 7-Apr-16 35
504-FAEI-23230 Pre-Cutting and Pre-Bending 2874 m. 50.175 870 100.00% 4-Mar-16 7-Apr-16 35 100.00% 100.00% Completed
2535 2608 3-May-16 28-May-16 26
483 227 17-May-16 25-May-16 9
483 227 17-May-16 25-May-16 9
504-FAEI-23250 Tubings Installation for 01-I1: Process Production 456 m. 50.175 195 85.90% 17-May-16 25-May-16 9 95.00% 100.00% Delayed
504-FAEI-23260 Tubings Installation for 10-I1 : Booster Compressor 27 m. 50.175 32 14.10% 17-May-16 25-May-16 9 95.00% 100.00% Delayed
2052 2381 3-May-16 28-May-16 26
1273 1529 3-May-16 28-May-16 26
504-FAEI-23270 Tubings Installation for 13-C3 : Wellhead Control Panel 1273 m. 50.175 1529 100.00% 3-May-16 28-May-16 26 91.50% 100.00% Delayed
779 852 3-May-16 21-May-16 19
504-FAEI-23280 Tubings Installation for 17-S1 : Fire Emergency Shutdown (FESD) 531 m. 50.175 579 67.96% 3-May-16 19-May-16 17 89.92% 100.00% Delayed
504-FAEI-23290 Tubings Installation for 17-S2 : Emergency Shutdown 248 m. 50.175 273 32.04% 4-May-16 21-May-16 18 83.47% 100.00% Delayed
2875 3986 -6.65%
L5 L4 L5 L4 L5 L4
441 102 25-May-16 30-May-16 6
96 9 26-May-16 27-May-16 2
96 9 26-May-16 27-May-16 2
504-FAEI-23300 Tubings Leak Test for 06-I1 : HP Vent / LP Vent 96 m. 50.180 9 100.00% 26-May-16 27-May-16 2 0.00% 100.00% Delayed & Not Start
189 50 26-May-16 30-May-16 5
189 50 26-May-16 30-May-16 5Sub-System - 7001 : Chemical (C) 100.00% 0.00% 100.00%
System - 2000 : Drains & Reliefs 8.82% 0.00% 100.00%
Sub-System - 2500 : Blow Down (BD) 100.00% 0.00% 100.00%
System - 7000 : Chemicals 49.02% 0.00% 100.00%
Status
Next 2 Wks
As Per Planed
RemarkL3
Start Finish Dur.
Tested Check Sheet : PLT-T L3 L3
90% 10%
Bare Tube Leak Test 35.92% 0.00% 100.00%
Sub-System - 8000D : Safety Intrergrity System (SIS) 35.78% 87.85% 100.00%
501 50.00%
230
SUB-TOTAL OF TUBINGS INSTALLATION 16.56% 2827 93.35% 100.00%
456 50.00%
27 50.00%
System - 8000 : Others 91.30% 90.19% 100.00%
Sub-System - 8000A : Process Control 64.22% 91.50% 100.00%
1273 15.00%
2874
Field Installation and Hook-Up 74.99% 90.61% 100.00%
System - 1000 : Process Production 8.70% 95.00% 100.00%
Sub-System - 1001 : Process Liquid & Vapour (P) 100.00% 95.00% 100.00%
Sub-System - 8000B : Electrical Generation and Distribution 49.79% 99.17% 100.00%
9 50.00%
TPU Jacket Tube Installation 87.26% 92.96% 100.00%
Preparation Works 25.01% 100.00% 100.00%
189 50.00%
System - 8000 : Others 47.83% 97.08% 100.00%
Sub-System - 8000A : Process Control 50.21% 95.00% 100.00%
70 50.00%
95.00% 100.00%
72 50.00%
System - 7000 : Chemicals 30.12% 95.00% 100.00%
System - 2000 : Drains & Reliefs 22.05%
Sub-System - 7001 : Chemical (C) 100.00% 95.00% 100.00%
Status
Next 2 Wks
As Per Planed
RemarkL3
Start Finish Dur.
Tube Running Check Sheet : PIC-T L3 L3
90% 10%
Bare Tube Installation 12.74% 95.99% 100.00%
100.00%SUB-TOTAL OF CABLES CONTINUITY & INSULATION TEST 4.13% 565 85.58%
2
5
4
TUBINGS LEAK TEST QTY Unit Cost Code
Budgeted
Mhrs
WTG% Baseline Activity Milestones % Actual %Plan
95.00% 100.00%
Sub-System - 2500 : Blow Down (BD) 100.00%
69.23% 100.00%
10
Sub-System - 8000D : Safety Intrergrity System (SIS) 5.38% 90.00% 100.00%
9
11
Sub-System - 8000C : Communication 18.09%
28
110
83.24% 100.00%
1
51
Sub-System - 8000B : Electrical Generation and Distribution 62.10%
79.25% 100.00%
Sub-System - 8000A : Process Control 14.43% 70.62% 100.00%
9
System - 8000 : Others 41.11%
90.00% 100.00%
Sub-System - 7001 : Chemical (C) 100.00% 90.00% 100.00%
System - 7000 : Chemicals 1.81%
90.00% 100.00%
6
10
Sub-System - 4500 : Gas Utility (GU) 37.50%
Sub-System - 4400 : Gas Instrument (GI) 62.50% 90.00% 100.00%
50
76
90.00%
3
System - 4000 : Utility Generals 2.41% 90.00% 100.00%
6
Sub-System - 2100 : Open Drain (DO) 30.77%
90.00% 100.00%
Sub-System - 2001 : Closed Drain (DC) 69.23% 90.00% 100.00%
RemarkL3
Start Finish Dur.
Tested Check Sheet : PLT-C
Activity Milestones % Actual %Plan
Status
Next 2 Wks
As Per Planed
L3 L3
90% 10%
CABLES CONTINUITY & INSULATION TEST QTY Unit Cost Code
Budgeted
Mhrs
WTG% Baseline
Sub-System - 1001 : Process Liquid & Vapour (P) 100.00% 90.00% 100.00%
System - 1000 : Process Production 53.37% 90.00% 100.00%
48
99.58% 100.00%
2
5
4
SUB-TOTAL OF CABLES INSTALLATION 34.40%
TUBINGS INSTALLATION QTY Unit Cost Code
Budgeted
Mhrs
WTG% Baseline Activity Milestones % Actual %Plan
System - 2000 : Drains & Reliefs 1.31%
5
121
100.00%
13
Sub-System - 8000D : Safety Intrergrity System (SIS) 4.67% 100.00% 100.00%
9
11
Sub-System - 8000C : Communication 4.67% 95.77%
100.00%
1
36
118
65
Sub-System - 8000B : Electrical Generation and Distribution 66.53% 98.69%
100.00%
Sub-System - 8000A : Process Control 24.14% 100.00% 100.00%
9
System - 8000 : Others 38.82% 98.93%
System - 7000 : Chemicals 1.51% 100.00% 100.00%
Sub-System - 7001 : Chemical (C) 100.00% 100.00% 100.00%
Sub-System - 4500 : Gas Utility (GU) 37.79% 100.00% 100.00%
6
Sub-System - 4400 : Gas Instrument (GI) 62.21% 100.00% 100.00%
10
3
System - 4000 : Utility Generals 2.62% 100.00% 100.00%
6
Sub-System - 2100 : Open Drain (DO) 33.87% 100.00% 100.00%
System - 2000 : Drains & Reliefs 1.50% 100.00% 100.00%
Sub-System - 2001 : Closed Drain (DC) 66.13% 100.00% 100.00%
50
76
5
48
Sub-System - 1001 : Process Liquid & Vapour (P) 100.00% 100.00% 100.00%
121
45%
System - 1000 : Process Production 55.55% 100.00% 100.00%
Next 2 Wks
As Per Planed
Remark
Start Finish Dur.
Pulled
Activity Milestones
Status
Glanded Terminated
L3 L3
100.00% 100.00%
CABLES INSTALLATION QTY Unit Cost Code
Budgeted
Mhrs
Baseline
5 100.00%
SUB-TOTAL OF CALIBRATION OF INSTRUMENTS TAG 5.37%
100.00% 100.00%
1 100.00%
Sub-System - 8000D : Safety Intrergrity System (SIS) 5.80% 100.00% 100.00%
WTG% % Actual %Plan
L3
3 100.00%
48 100.00%
Sub-System - 8000B : Electrical Generation and Distribution 1.34%
100.00% 100.00%
Sub-System - 8000A : Process Control 92.86% 100.00% 100.00%
21 100.00%
System - 8000 : Others 17.31%
100.00% 100.00%
Sub-System - 7001 : Chemical (C) 100.00% 100.00% 100.00%
System - 7000 : Chemicals 4.56%
100.00% 100.00%
10 100.00%
14 100.00%
Sub-System - 4500 : Gas Utility (GU) 41.18%
100.00% 100.00%
Sub-System - 4400 : Gas Instrument (GI) 58.82% 100.00% 100.00%
1 100.00%
System - 4000 : Utility Generals 5.26%
100.00% 100.00%
5 100.00%
Sub-System - 2500 : Blow Down (BD) 7.89% 100.00% 100.00%
8 100.00%
Sub-System - 2100 : Open Drain (DO) 34.21%
100.00% 100.00%
Sub-System - 2001 : Closed Drain (DC) 57.89% 100.00% 100.00%
26 100.00%
System - 2000 : Drains & Reliefs 2.94%
1 100.00%
193 100.00%
28 100.00%
50 100.00%
100.00%
Sub-System - 1001 : Process Liquid & Vapour (P) 100.00% 100.00% 100.00%
System - 1000 : Process Production 69.94% 421 100.00%
Next 2 Wks
As Per Planed
RemarkL3
Start Finish Dur.
Calibrated
Activity Milestones % Actual %Plan
StatusCheck Sheet : PCC L3 L3
90%
100.00% 100.00%
CALIBRATION OF INSTRUMENTS TAG QTY Unit Cost Code
Budgeted
Mhrs
WTG% Baseline
670 670
109 109
SUB-TOTAL OF E&I SUPPORTS, LADDERS AND TRAYS 35.06%
10%
Installation of E&I Trays&Ladders 31.13% 100.00% 100.00%
Upper Deck
273 273
91 91
Mezzanine Deck
37 37
206 206
Cellar Deck
475 475
178 178
Sub-Cellar Deck
1 1
30 30
100.00% 100.00%
Installation of E&I Supports 68.87% 100.00% 100.00%
364 364
Installation 55.90%
31 31
653 653
243 243
L3
90% 10%
Fabrication 44.10% 100.00% 100.00%
CHEVRON : CVX-PHASE 50
PROGRESS MEASUREMENT WORK SHEET FOR E&I AND PRE-COMMISSIONING WORKS
WHP 50/4 : GAS PLATFORM
WHP 50/4 : GAS PLATFORM : E&I INSTALLATION
E&I SUPPORTS, LADDERS AND TRAYS QTY Unit Cost Code
Budgeted
Mhrs
%Plan
Status
Next 2 Wks
As Per Planed
RemarkL3
Start Finish Dur.
WTG% Baseline Activity Milestones % Actual
Fabricated/Installed Accepted /Painted/Cleaning L3
598
Page 5 of 10 Prepared By : Nattakarn S.
Activity ID Activity Name Num. Budgeted Units Planned Start Planned Finish % Actual 1-Jun-16
CHEVRON : CVX-PHASE 50
PROGRESS MEASUREMENT WORK SHEET FOR E&I AND PRE-COMMISSIONING WORKS
WHP 50/4 : GAS PLATFORM
504-FAEI-23310 Tubings Leak Test for 11-I1 : Chemical Injection 189 m. 50.180 50 100.00% 26-May-16 28-May-16 3 0.00% 100.00% Delayed & Not Start
156 43 25-May-16 28-May-16 4
84 21 25-May-16 28-May-16 4
504-FAEI-23330 Tubings Leak Test for 13-C1 : Back Start 84 m. 50.180 21 100.00% 25-May-16 28-May-16 4 0.00% 100.00% Delayed & Not Start
72 22 25-May-16 26-May-16 2
504-FAEI-23340 Tubings Leak Test for 14-E6 : TEG - Gas Platform 12 m. 50.180 11 50.00% 25-May-16 26-May-16 2 0.00% 100.00% Delayed & Not Start
504-FAEI-23350 Tubings Leak Test for 14-E7 : CO2 Skid - Option Gas Platform 60 m. 50.180 11 50.00% 25-May-16 26-May-16 2 0.00% 100.00% Delayed & Not Start
2535 182 26-May-16 28-May-16 3
483 56 26-May-16 27-May-16 2
483 56 26-May-16 27-May-16 2
504-FAEI-23360 Tubings Leak Test for 01-I1: Process Production 456 m. 50.180 45 80.36% 26-May-16 27-May-16 2 0.00% 100.00% Delayed & Not Start
504-FAEI-23370 Tubings Leak Test for Booster Compressor 27 m. 50.180 11 19.64% 26-May-16 26-May-16 1 0.00% 100.00% Delayed & Not Start
2052 126 26-May-16 28-May-16 3
1273 90 26-May-16 28-May-16 3
504-FAEI-23380 Tubings Leak Test for 13-C3 : Wellhead Control Panel 1273 m. 50.180 90 100.00% 26-May-16 28-May-16 3 0.00% 100.00% Delayed & Not Start
779 36 26-May-16 26-May-16 1
504-FAEI-23390 Tubings Leak Test for 17-S1 : Fire Emergency Shutdown (FESD) 531 m. 50.180 18 50.00% 26-May-16 26-May-16 1 0.00% 100.00% Delayed & Not Start
504-FAEI-23400 Tubings Leak Test for 17-S2 : Emergency Shutdown 248 m. 50.180 18 50.00% 26-May-16 26-May-16 1 0.00% 100.00% Delayed & Not Start
2976 284 -100.00%
L5 L4 L5 L4 L5 L4
262 363 25-Apr-16 8-Jul-16 75
262 363 25-Apr-16 8-Jul-16 75
504-FAEI-23410 Hook-Up of E&I Tags for 01-I1: Process Production 145 Ea. 50.175 148 40.77% 25-Apr-16 23-May-16 29 77.33% 100.00% Delayed
504-FAEI-23420 Hook-Up of E&I Tags for 01-I2 : Production Header 28 Ea. 50.175 43 11.85% 19-May-16 15-Jun-16 28 86.79% 100.00% Delayed Should be finished
504-FAEI-23430 Hook-Up of E&I Tags for 02-I1 : Test Separator 52 Ea. 50.175 75 20.66% 26-May-16 13-Jun-16 19 84.81% 100.00% Delayed Should be finished
504-FAEI-23440 Hook-Up of E&I Tags for 03-I1 : Pig Luncher 1 Ea. 50.175 1 0.28% 30-May-16 31-May-16 2 0.00% 100.00% Delayed & Not Start
504-FAEI-23450 Hook-Up of E&I Tags for 03-I2 : Pig Receiver - Option 9 Ea. 50.175 55 15.15% 30-May-16 4-Jun-16 6 40.00% 100.00% Delayed Should be finished
504-FAEI-23480 Hook-Up of E&I Tags for 10-I1 : Booster Compressor 27 Ea. 50.175 41 11.29% 23-Jun-16 8-Jul-16 16 83.33% 100.00% Delayed
15 22 23-May-16 2-Jun-16 11
9 13 23-May-16 30-May-16 8
504-FAEI-23490 Hook-Up of E&I Tags for 08-I1 : Closed Drain System 9 Ea. 50.175 13 100.00% 23-May-16 30-May-16 8 62.33% 100.00% Delayed
5 8 27-May-16 31-May-16 5
504-FAEI-23500 Hook-Up of E&I Tags for 09-I1 : Open Drain System 5 Ea. 50.175 8 100.00% 27-May-16 31-May-16 5 74.40% 100.00% Delayed
1 1 31-May-16 2-Jun-16 3
504-FAEI-23510 Hook-Up of E&I Tags for 06-I1 : HP Vent / LP Vent 1 Ea. 50.175 1 100.00% 31-May-16 2-Jun-16 3 0.00% 100.00% Delayed & Not Start Should be finished
28 41 19-Apr-16 18-May-16 30
17 23 19-Apr-16 27-Apr-16 9
504-FAEI-23520 Hook-Up of E&I Tags for 04-I1 : Instrument Gas 17 Ea. 50.175 23 100.00% 19-Apr-16 27-Apr-16 9 63.53% 100.00% Delayed
11 18 21-Apr-16 18-May-16 28
504-FAEI-23530 Hook-Up of E&I Tags for 04-I2 : Utility Gas 11 Ea. 50.175 18 100.00% 21-Apr-16 29-Apr-16 9 65.45% 100.00% Delayed
24 35 27-May-16 5-Jul-16 40
24 35 27-May-16 5-Jul-16 40
504-FAEI-23560 Hook-Up of E&I Tags for 11-I1 : Chemical Injection 24 Ea. 50.175 35 100.00% 18-Jun-16 5-Jul-16 18 90.00% 100.00% Delayed
231 332 12-Feb-16 7-Jul-16 147
67 226 29-Apr-16 31-May-16 33
504-FAEI-23580 Hook-Up of E&I Tags for 13-C1 : Back Start 4 Ea. 50.175 7 3.10% 29-Apr-16 6-May-16 8 90.00% 100.00% Delayed
504-FAEI-23590 Hook-Up of E&I Tags for 13-C2 : PLC and Control system 14 Ea. 50.175 22 9.73% 14-May-16 27-May-16 14 90.47% 100.00% Delayed
504-FAEI-23600 Hook-Up of E&I Tags for 13-C3 : Wellhead Control Panel 49 Ea. 50.175 197 87.17% 14-May-16 31-May-16 18 90.00% 100.00% Delayed
133 60 12-Feb-16 7-Jul-16 147
504-FAEI-23620 Hook-Up of E&I Tags for 14-E2 : AC Diesel Generators 1 Ea. 50.175 1 1.67% 27-Jun-16 4-Jul-16 8 90.00% 100.00% Delayed
504-FAEI-23630 Hook-Up of E&I Tags for 14-E3 : DC Supply 7 Ea. 50.175 10 16.67% 18-Mar-16 23-Mar-16 6 90.00% 100.00% Delayed
504-FAEI-23640 Hook-Up of E&I Tags for 14-E4 : Power & Lighting and Outlet 111 Ea. 50.175 28 46.67% 12-Feb-16 27-Feb-16 16 92.96% 100.00% Delayed
504-FAEI-23660 Hook-Up of E&I Tags for 14-E6 : TEG - Gas Platform 5 Ea. 50.175 8 13.33% 28-Apr-16 9-May-16 12 98.00% 100.00% Delayed
504-FAEI-23670 Hook-Up of E&I Tags for 16-E1 : Navigation Aids System 9 Ea. 50.175 13 21.67% 28-Mar-16 31-Mar-16 4 93.00% 100.00% Delayed
5 7 5-Apr-16 18-Apr-16 14
504-FAEI-23680 Hook-Up of E&I Tags for 15-T1 : Comunication System 5 Ea. 50.175 7 100.00% 5-Apr-16 18-Apr-16 14 93.00% 100.00% Delayed
26 39 14-May-16 11-Jun-16 29
504-FAEI-23690 Hook-Up of E&I Tags for 17-S2 : Emergency Shutdown 10 Ea. 50.175 13 33.33% 7-Jun-16 11-Jun-16 5 90.00% 100.00% Delayed
504-FAEI-23700 Hook-Up of E&I Tags for 17-S3 : Fire & Gas Detector 5 Ea. 50.175 8 20.51% 25-May-16 31-May-16 7 93.00% 100.00% Delayed
504-FAEI-23710 Hook-Up of E&I Tags for 17-S4 : Beacon Light & Siren 11 Ea. 50.175 18 46.15% 14-May-16 24-May-16 11 93.00% 100.00% Delayed
560 793 -18.63%
24076 -3.61%
L5 L4 L5 L4 L5 L4
704 7-Jun-16 9-Jun-16 3
84 704 7-Jun-16 9-Jun-16 3
84 704 7-Jun-16 9-Jun-16 3
504-FAPC-21590 Fuction Test of 14-E2 : AC Diesel Generators 10 Pac. 60.220 71 10.09% 8-Jun-16 8-Jun-16 1 0.00% 0.00% Should be started
504-FAPC-21600 Fuction Test of 14-E3 : DC Supply 21 Pac. 60.220 174 24.72% 8-Jun-16 8-Jun-16 1 0.00% 0.00% Should be started
504-FAPC-21610 Fuction Test of 14-E4 : Power & Lighting and Outlet 39 Pac. 60.220 322 45.74% 7-Jun-16 7-Jun-16 1 0.00% 0.00% Should be started
504-FAPC-21630 Fuction Test of 14-E6 : TEG - Gas Platform 6 Pac. 60.220 21 2.98% 9-Jun-16 9-Jun-16 1 0.00% 0.00% Should be started
504-FAPC-21640 Fuction Test of 16-E1 : Navigation Aids System 8 Pac. 60.220 116 16.48% 8-Jun-16 8-Jun-16 1 0.00% 0.00% Should be started
1241 6-Jun-16 11-Jun-16 6
237 823 6-Jun-16 10-Jun-16 5
237 823 6-Jun-16 10-Jun-16 5
504-FAPC-21660 Loop Test of 01-I1: Process Production 98 Pac. 60.225 340 41.31% 6-Jun-16 7-Jun-16 2 0.00% 0.00% Should be started
504-FAPC-21670 Loop Test of 01-I2 : Production Header 27 Pac. 60.225 94 11.42% 7-Jun-16 8-Jun-16 2 0.00% 0.00% Should be started
504-FAPC-21680 Loop Test of 02-I1 : Test Separator 55 Pac. 60.225 191 23.21% 8-Jun-16 9-Jun-16 2 0.00% 0.00% Should be started
504-FAPC-21690 Loop Test of 03-I2 : Pig Receiver - Option 12 Pac. 60.225 42 5.10% 8-Jun-16 8-Jun-16 1 0.00% 0.00% Should be started
504-FAPC-21720 Loop Test of 10-I1 : Booster Compressor 45 Pac. 60.225 156 18.96% 7-Jun-16 7-Jun-16 1 0.00% 0.00% Should be started
9 32 10-Jun-16 11-Jun-16 2
6 21 10-Jun-16 11-Jun-16 2
504-FAPC-21730 Loop Test of 08-I1 : Closed Drain System 6 Pac. 60.225 21 100.00% 10-Jun-16 11-Jun-16 2 0.00% 0.00% Should be started
3 11 10-Jun-16 10-Jun-16 1
504-FAPC-21740 Loop Test of 09-I1 : Open Drain System 3 Pac. 60.225 11 100.00% 10-Jun-16 10-Jun-16 1 0.00% 0.00% Should be started
13 32 10-Jun-16 10-Jun-16 1
9 21 10-Jun-16 10-Jun-16 1
504-FAPC-21750 Loop Test of 04-I1 : Instrument Gas 9 Pac. 60.225 21 100.00% 10-Jun-16 10-Jun-16 1 0.00% 0.00% Should be started
4 11 10-Jun-16 10-Jun-16 1
504-FAPC-21760 Loop Test of 04-I2 : Utility Gas 4 Pac. 60.225 11 100.00% 10-Jun-16 10-Jun-16 1 0.00% 0.00% Should be started
12 32 10-Jun-16 10-Jun-16 1
12 32 10-Jun-16 10-Jun-16 1
504-FAPC-21790 Loop Test of 11-I1 : Chemical Injection 12 Pac. 60.225 32 100.00% 10-Jun-16 10-Jun-16 1 0.00% 0.00% Should be started
49 322 9-Jun-16 10-Jun-16 2
30 187 10-Jun-16 10-Jun-16 1
504-FAPC-21810 Loop Test of 13-C3 : Wellhead Control Panel 30 Pac. 60.225 187 100.00% 10-Jun-16 10-Jun-16 1 0.00% 0.00% Should be started
1 4 9-Jun-16 9-Jun-16 1
504-FAPC-21820 Loop Test of 15-T1 : Comunication System 1 Pac. 60.225 4 100.00% 9-Jun-16 9-Jun-16 1 0.00% 0.00% Should be started
18 131 10-Jun-16 10-Jun-16 1
504-FAPC-21830 Loop Test of 17-S2 : Emergency Shutdown 3 Pac. 60.225 12 9.16% 10-Jun-16 10-Jun-16 1 0.00% 0.00% Should be started
504-FAPC-21840 Loop Test of 17-S3 : Fire & Gas Detector 8 Pac. 60.225 28 21.37% 10-Jun-16 10-Jun-16 1 0.00% 0.00% Should be started
504-FAPC-21850 Loop Test of 17-S4 : Beacon Light & Siren 7 Pac. 60.225 91 69.47% 10-Jun-16 10-Jun-16 1 0.00% 0.00% Should be started
404 1945 0.00%
L5 L4 L5 L4 L5 L4
504-FAPC-21860 Platform Site Acceptance Test - SAT 100 Pac. 60.235 555 13-Jun-16 18-Jun-16 6 Should be started
100 555 0.00%
2500 -38.90%
-3.27%
SUB-TOTAL OF TUBINGS LEAK TEST 1.18% 0.00% 100.00%
Sub-System - 8000A : Process Control 71.43% 0.00% 100.00%
Sub-System - 8000D : Safety Intrergrity System (SIS) 28.57% 0.00% 100.00%
100.00%
Sub-System - 1001 : Process Liquid & Vapour (P) 100.00% 0.00% 100.00%
System - 8000 : Others 69.23% 0.00% 100.00%
System - 1000 : Process Production 30.77% 0.00%
Sub-System - 8000B : Electrical Generation and Distribution 51.16% 0.00% 100.00%
TPU Jacket Tube Leak Test 64.08% 0.00% 100.00%
System - 8000 : Others 42.16% 0.00% 100.00%
Sub-System - 8000A : Process Control 48.84% 0.00% 100.00%
87.30% 90.57%OVERALL PROGRESS OF WHP 50/4 : GAS PLATFORM 26576 100.00%
0.00%
TOTAL OF WHP 50/4 : GAS PLATFORM : E&I PRE-COMMISSIONING 9.41% 0.00% 38.90%
100.00% 0.00% 0.00%
SUB-TOTAL OF SITE ACCEPTANC TEST - SAT 22.20% 0.00%
RemarkL3
Start Finish Dur.
Activity Milestones % Actual %Plan
Status
Next 2 Wks
As Per Planed
SAT Completion L3 L3
100%
0.00%
SITE ACCEPTANC TEST - SAT QTY Unit Cost Code
Budgeted
Mhrs
WTG% Baseline
SUB-TOTAL OF LOOP/ FUNCTION TEST 77.80% 0.00%
0.00% 0.00%
Sub-System - 8000D : Safety Intrergrity System (SIS) 40.68% 0.00% 0.00%
Sub-System - 8000C : Communication 1.24%
0.00% 0.00%
Sub-System - 8000A : Process Control 58.07% 0.00% 0.00%
System - 8000 : Others 25.95%
0.00% 0.00%
Sub-System - 7001 : Chemical (C) 100.00% 0.00% 0.00%
System - 7000 : Chemicals 2.58%
0.00% 0.00%Sub-System - 4500 : Gas Utility (GU) 34.38%
Sub-System - 4400 : Gas Instrument (GI) 65.63% 0.00% 0.00%
0.00% 0.00%
System - 4000 : Utility Generals 2.58% 0.00% 0.00%
Sub-System - 2100 : Open Drain (DO) 34.38%
0.00% 0.00%
Sub-System - 2001 : Closed Drain (DC) 65.63% 0.00% 0.00%
System - 2000 : Drains & Reliefs 2.58%
Sub-System - 1001 : Process Liquid & Vapour (P) 100.00% 0.00% 0.00%
0.00% 0.00%
System - 1000 : Process Production 66.32% 0.00% 0.00%
Instrumentation 63.80%
Sub-System - 8000B : Electrical Generation and Distribution 100.00% 0.00% 0.00%
System - 8000 : Others 100.00% 0.00% 0.00%
Electrical 36.20% 0.00% 0.00%
%Plan
Status
Next 2 Wks
As Per Planed
RemarkL3
Start Finish Dur.
WTG% Baseline Activity Milestones % Actual
Tested Check Sheet : PLT-L & PFT
WHP 50/4 : GAS PLATFORM : E&I PRE-COMMISSIONING
LOOP/ FUNCTION TEST QTY Unit Cost Code
Budgeted
Mhrs
TOTAL OF WHP 50/4 : GAS PLATFORM : E&I INSTALLATION 90.59% 96.37% 99.97%
L3 L3
90% 10%
100.00%SUB-TOTAL OF HOOK-UP OF E&I TAG ITEMS 3.29% 81.37%
11 11 30.00%
Sub-System - 8000B : Electrical Generation and Distribution 18.07% 93.10% 100.00%
1 1
7 7
93.00% 100.00%
Sub-System - 8000D : Safety Intrergrity System (SIS) 11.75% 92.00% 100.00%
Sub-System - 8000C : Communication 2.11%
111 111 29.55%
5 5 80.00%
9
90.89% 100.00%
Sub-System - 8000A : Process Control 68.07% 90.05% 100.00%
System - 8000 : Others 41.87%
90.00% 100.00%
Sub-System - 7001 : Chemical (C) 100.00% 90.00% 100.00%
24 24
65.45% 100.00%Sub-System - 4500 : Gas Utility (GU) 43.90%
64.37% 100.00%
Sub-System - 4400 : Gas Instrument (GI) 56.10% 63.53% 100.00%
8 8
System - 7000 : Chemicals 4.41%
System - 4000 : Utility Generals 5.17%
74.40% 100.00%
Sub-System - 2500 : Blow Down (BD) 4.55% 0.00% 100.00%
Sub-System - 2100 : Open Drain (DO) 36.36%
6 6 23.33%
4 4 24.00%
63.89% 100.00%
Sub-System - 2001 : Closed Drain (DC) 59.09% 62.33% 100.00%
System - 2000 : Drains & Reliefs 2.77%
25 25
100.00%
Sub-System - 1001 : Process Liquid & Vapour (P) 100.00% 74.80% 100.00%
System - 1000 : Process Production 45.78% 74.80%
HOOK-UP OF E&I TAG ITEMS QTY Unit Cost Code
Budgeted
Mhrs
511 511
Next 2 Wks
As Per Planed
RemarkL3
Start Finish Dur.
Activity Milestones % Actual %Plan
StatusL3 L3
WTG% Baseline
Installed Hook-Up Check Sheet : PIC-H
60% 30% 10%
22.27%
27 27
49 49
4 4
121 121
4 4
10 10
5 5 30.00%
14 14 4.67%
49 49
9 30.00%
5 5 30.00%
12 12
Page 6 of 10 Prepared By : Nattakarn S.
Activity ID Activity Name Num. Budgeted Units Planned Start Planned Finish % Actual 1-Jun-16
L5 L4 L5 L4 L5 L4
1298 3723 14-Aug-15 9-Oct-15 57
502-FAEI-19310 Fabrication of E&I Supports for Sub-Cellar Deck 31 Ea. 50.170 98 2.63% 8-Sep-15 23-Sep-15 16 100.00% 100.00% Completed
502-FAEI-19320 Fabrication of E&I Supports for Cellar Deck 651 Ea. 50.170 1915 51.44% 14-Aug-15 9-Oct-15 57 100.00% 100.00% Completed
502-FAEI-19330 Fabrication of E&I Supports for Mezzanine Deck 252 Ea. 50.170 525 14.10% 24-Aug-15 24-Sep-15 32 100.00% 100.00% Completed
502-FAEI-19340 Fabrication of E&I Supports for Upper Deck 364 Ea. 50.170 1185 31.83% 24-Aug-15 2-Oct-15 40 100.00% 100.00% Completed
4719 30-Sep-15 11-Apr-16 195
1298 3250 30-Sep-15 20-Feb-16 144
31 106 3.26% 23-Dec-15 12-Jan-16 21 100.00% 100.00%
502-FAEI-19350 Installation of E&I Support at Sub-Cellar Deck - Assembly Bay 1 Ea. 50.170 12 11.32% 25-Dec-15 5-Jan-16 12 100.00% 100.00% Completed
502-FAEI-19360 Installation of E&I Support at Sub-Cellar Deck - Erection Area 30 Ea. 50.170 94 88.68% 23-Dec-15 12-Jan-16 21 100.00% 100.00% Completed
651 1614 49.66% 30-Sep-15 16-Jan-16 109 100.00% 100.00%
502-FAEI-19370 Installation of E&I Support at Cellar Deck - Assembly Bay 475 Ea. 50.170 1035 64.13% 30-Sep-15 24-Oct-15 25 100.00% 100.00% Completed
502-FAEI-19380 Installation of E&I Support at Cellar Deck - Erection Area 176 Ea. 50.170 579 35.87% 31-Oct-15 16-Jan-16 78 100.00% 100.00% Completed
252 546 16.80% 16-Oct-15 20-Feb-16 128 100.00% 100.00%
502-FAEI-19390 Installation of E&I Support at Mezzanine Deck - Assembly Bay 37 Ea. 50.170 118 21.61% 16-Oct-15 3-Nov-15 19 100.00% 100.00% Completed
502-FAEI-19400 Installation of E&I Support at Mezzanine Deck - Erection Area 215 Ea. 50.170 428 78.39% 27-Jan-16 20-Feb-16 25 100.00% 100.00% Completed
364 984 30.28% 24-Oct-15 28-Jan-16 97 100.00% 100.00%
502-FAEI-19410 Installation of E&I Support at UpperDeck - Assembly Bay 273 Ea. 50.170 662 67.28% 24-Oct-15 17-Nov-15 25 100.00% 100.00% Completed
502-FAEI-19420 Installation of E&I Support at UpperDeck - Erection Area 91 Ea. 50.170 322 32.72% 30-Nov-15 28-Jan-16 60 100.00% 100.00% Completed
779 1469 4-Nov-15 11-Apr-16 160
502-FAEI-19430 Installation of Cable Trays&Ladders 670 m. 50.170 942 64.13% 4-Nov-15 12-Feb-16 101 100.00% 100.00% Completed
502-FAEI-19440 Installation of Tubing Trays&Ladders 109 m. 50.170 527 35.87% 7-Mar-16 11-Apr-16 36 100.00% 100.00% Completed
8442 0.00%
L5 L4 L5 L4 L5 L4
305 905 24-Oct-15 19-Jan-16 88
305 905 24-Oct-15 19-Jan-16 88
502-FAEI-19450 Calibration of Instrument Tags - 01-I1: Process Production 193 Ea. 50.165 535 59.12% 24-Oct-15 18-Dec-15 56 100.00% 100.00% Completed
502-FAEI-19460 Calibration of Instrument Tags - 01-I2 : Production Header 28 Ea. 50.165 76 8.40% 11-Nov-15 24-Nov-15 14 100.00% 100.00% Completed
502-FAEI-19470 Calibration of Instrument Tags - 02-I1 : Test Separator 50 Ea. 50.165 140 15.47% 24-Nov-15 22-Dec-15 29 100.00% 100.00% Completed
502-FAEI-19480 Calibration of Instrument Tags - 03-I1 : Pig Luncher 1 Ea. 50.165 3 0.33% 15-Dec-15 17-Dec-15 3 100.00% 100.00% Completed
502-FAEI-19520 Calibration of Instrument Tags - 10-I1 : Booster Compressor 26 Ea. 50.165 75 8.29% 22-Dec-15 6-Jan-16 16 100.00% 100.00% Completed
14 38 24-Oct-15 24-Nov-15 32
8 22 24-Oct-15 27-Oct-15 4
502-FAEI-19530 Calibration of Instrument Tags - 08-I1 : Closed Drain System 8 Ea. 50.165 22 100.00% 24-Oct-15 27-Oct-15 4 100.00% 100.00% Completed
5 13 21-Nov-15 24-Nov-15 4
502-FAEI-19540 Calibration of Instrument Tags - 09-I1 : Open Drain System 5 Ea. 50.165 13 100.00% 21-Nov-15 24-Nov-15 4 100.00% 100.00% Completed
1 3 21-Nov-15 24-Nov-15 4
502-FAEI-19550 Calibration of Instrument Tags - 06-I1 : HP Vent / LP Vent 1 Ea. 50.165 3 100.00% 21-Nov-15 24-Nov-15 4 100.00% 100.00% Completed
24 68 3-Nov-15 2-Dec-15 30
14 40 20-Nov-15 27-Nov-15 8
502-FAEI-19560 Calibration of Instrument Tags - 04-I1 : Instrument Gas 14 Ea. 50.165 40 100.00% 20-Nov-15 27-Nov-15 8 100.00% 100.00% Completed
10 28 3-Nov-15 2-Dec-15 30
502-FAEI-19570 Calibration of Instrument Tags - 04-I2 : Utility Gas 10 Ea. 50.165 28 100.00% 27-Nov-15 2-Dec-15 6 100.00% 100.00% Completed
21 59 3-Oct-15 20-Oct-15 18
21 59 3-Oct-15 20-Oct-15 18
502-FAEI-19600 Calibration of Instrument Tags - 11-I1 : Chemical Injection 21 Ea. 50.165 59 100.00% 3-Oct-15 15-Oct-15 13 100.00% 100.00% Completed
57 224 25-Sep-15 30-Jan-16 128
51 208 25-Sep-15 12-Dec-15 79
502-FAEI-19620 Calibration of Instrument Tags - 13-C1 : Back Start 3 Ea. 50.165 8 3.85% 11-Dec-15 12-Dec-15 2 100.00% 100.00% Completed
502-FAEI-19630 Calibration of Instrument Tags - 13-C3 : Wellhead Control Panel 48 Ea. 50.165 200 96.15% 25-Sep-15 26-Oct-15 32 100.00% 100.00% Completed
1 3 14-Dec-15 15-Dec-15 2
502-FAEI-19650 Calibration of Instrument Tags - 14-E6 : TEG - Gas Platform 1 Ea. 50.165 3 100.00% 14-Dec-15 15-Dec-15 2 100.00% 100.00% Completed
5 13 29-Jan-16 30-Jan-16 2
502-FAEI-19660 Calibration of Instrument Tags - 17-S3 : Fire & Gas Detector 5 Ea. 50.165 13 100.00% 29-Jan-16 30-Jan-16 2 100.00% 100.00% Completed
421 1294 0.00%
1st 2nd 1st 2nd
L5 L4 20.0% 20.0% 7.5% 7.5% L5 L4 L5 L4
295 4601 9-Mar-16 7-May-16 60
295 4601 9-Mar-16 7-May-16 60
502-FAEI-19670 Cables Installation for 01-I1: Process Production 121 Sch. 50.175 1968 42.77% 25-Mar-16 7-May-16 44 121 121 121 121 100.00% 100.00% Completed
502-FAEI-19680 Cables Installation for 01-I2 : Production Header 50 Sch. 50.175 678 14.74% 28-Mar-16 4-Apr-16 8 50 50 48 50 99.70% 100.00% Delayed
502-FAEI-19690 Cables Installation for 02-I1 : Test Separator 76 Sch. 50.175 1033 22.45% 2-Apr-16 9-Apr-16 8 76 76 64 76 98.82% 100.00% Delayed
502-FAEI-19730 Cables Installation for 10-I1 : Booster Compressor 48 Sch. 50.175 651 14.15% 9-Mar-16 16-Mar-16 8 48 48 48 48 100.00% 100.00% Completed
9 124 1-Mar-16 9-Apr-16 40
6 82 31-Mar-16 9-Apr-16 10
502-FAEI-19740 Cables Installation for 08-I1 : Closed Drain System 6 Sch. 50.175 82 100.00% 31-Mar-16 9-Apr-16 10 6 6 5 6 98.75% 100.00% Delayed
3 42 1-Mar-16 9-Mar-16 9
502-FAEI-19750 Cables Installation for 09-I1 : Open Drain System 3 Sch. 50.175 42 100.00% 1-Mar-16 9-Mar-16 9 3 3 2 3 97.50% 100.00% Delayed
16 217 24-Mar-16 21-Apr-16 29
10 135 25-Mar-16 5-Apr-16 12
502-FAEI-19760 Cables Installation for 04-I1 : Instrument Gas 10 Sch. 50.175 135 100.00% 25-Mar-16 5-Apr-16 12 10 10 6 10 97.00% 100.00% Delayed
6 82 24-Mar-16 21-Apr-16 29
502-FAEI-19770 Cables Installation for 04-I2 : Utility Gas 6 Sch. 50.175 82 100.00% 5-Apr-16 21-Apr-16 17 6 6 3 6 96.25% 100.00% Delayed
18 125 29-Apr-16 14-May-16 16
18 125 29-Apr-16 14-May-16 16
502-FAEI-19800 Cables Installation for 11-I1 : Chemical Injection 18 Sch. 50.175 125 100.00% 3-May-16 14-May-16 12 18 18 18 18 100.00% 100.00% Completed
266 3215 6-Nov-15 25-Apr-16 172
67 776 6-Nov-15 19-Feb-16 106
502-FAEI-19820 Cables Installation for 13-C2 : PLC and Control system 67 Sch. 50.175 776 100.00% 5-Feb-16 19-Feb-16 15 67 67 47 59 96.87% 100.00% Delayed
175 2139 6-Nov-15 25-Apr-16 172
502-FAEI-19850 Cables Installation for 14-E2 : AC Diesel Generators 1 Sch. 50.175 16 0.75% 22-Jan-16 26-Jan-16 5 1 1 1 1 100.00% 100.00% Completed
502-FAEI-19860 Cables Installation for 14-E3 : DC Supply 36 Sch. 50.175 368 17.20% 5-Feb-16 27-Feb-16 23 26 36 26 36 92.36% 100.00% Delayed
502-FAEI-19870 Cables Installation for 14-E4 : Power & Lighting and Outlet 118 Sch. 50.175 1480 69.19% 6-Nov-15 30-Nov-15 25 118 118 118 118 100.00% 100.00% Completed
502-FAEI-19890 Cables Installation for 14-E6 : TEG - Gas Platform 9 Sch. 50.175 125 5.84% 9-Feb-16 16-Feb-16 8 9 9 9 92.50% 100.00% Delayed
502-FAEI-19900 Cables Installation for 16-E1 : Navigation Aids System 11 Sch. 50.175 150 7.01% 13-Nov-15 2-Dec-15 20 11 11 11 92.50% 100.00% Delayed
13 150 5-Feb-16 27-Feb-16 23
502-FAEI-19910 Cables Installation for 15-T1 : Comunication System 13 Sch. 50.175 150 100.00% 5-Feb-16 27-Feb-16 23 13 11 7 8 90.58% 100.00% Delayed
11 150 5-Feb-16 12-Feb-16 8
502-FAEI-19920 Cables Installation for 17-S2 : Emergency Shutdown 2 Sch. 50.175 27 18.00% 5-Feb-16 8-Feb-16 4 2 2 2 92.50% 100.00% Delayed
502-FAEI-19930 Cables Installation for 17-S3 : Fire & Gas Detector 5 Sch. 50.175 68 45.33% 5-Feb-16 12-Feb-16 8 5 5 5 92.50% 100.00% Delayed
502-FAEI-19940 Cables Installation for 17-S4 : Beacon Light & Siren 4 Sch. 50.175 55 36.67% 5-Feb-16 12-Feb-16 8 4 4 4 4 100.00% 100.00% Completed
604 8282 594 602 518 591 -1.42%
L5 L4 L5 L4 L5 L4
295 531 29-Apr-16 28-May-16 30
295 531 29-Apr-16 28-May-16 30
502-FAEI-19950 Cables Continuity Check for 01-I1: Process Production 121 Sch. 50.180 218 41.05% 4-May-16 21-May-16 18 90.00% 100.00% Delayed
502-FAEI-19960 Cables Continuity Check for 01-I2 : Production Header 50 Sch. 50.180 75 14.12% 4-May-16 21-May-16 18 86.40% 100.00% Delayed
502-FAEI-19970 Cables Continuity Check for 02-I1 : Test Separator 76 Sch. 50.180 135 25.42% 23-May-16 26-May-16 4 90.00% 85.19% Ahead
502-FAEI-20010 Cables Continuity Check for 10-I1 : Booster Compressor 48 Sch. 50.180 72 13.56% 27-May-16 28-May-16 2 90.00% 50.00% Ahead
9 13 4-May-16 21-May-16 18
6 9 4-May-16 21-May-16 18
502-FAEI-20020 Cables Continuity Check for 08-I1 : Closed Drain System 6 Sch. 50.180 9 100.00% 4-May-16 21-May-16 18 90.00% 100.00% Delayed
3 4 6-May-16 21-May-16 16
502-FAEI-20030 Cables Continuity Check for 09-I1 : Open Drain System 3 Sch. 50.180 4 100.00% 6-May-16 21-May-16 16 90.00% 100.00% Delayed
16 24 16-Apr-16 28-May-16 43
10 15 23-May-16 28-May-16 6
502-FAEI-20040 Cables Continuity Check for 04-I1 : Instrument Gas 10 Sch. 50.180 15 100.00% 23-May-16 28-May-16 6 90.00% 100.00% Delayed
6 9 16-Apr-16 27-May-16 42
502-FAEI-20050 Cables Continuity Check for 04-I2 : Utility Gas 6 Sch. 50.180 9 100.00% 23-May-16 27-May-16 5 90.00% 50.00% Ahead
18 18 9-Apr-16 11-May-16 33
18 18 9-Apr-16 11-May-16 33
502-FAEI-20080 Cables Continuity Check for 11-I1 : Chemical Injection 18 Sch. 50.180 18 100.00% 9-May-16 11-May-16 3 90.00% 50.00% Ahead
266 409 16-Feb-16 11-May-16 86
67 59 29-Apr-16 6-May-16 8
502-FAEI-20100 Cables Continuity Check for 13-C2 : PLC and Control system 67 Sch. 50.180 59 100.00% 4-May-16 6-May-16 3 0.00% 100.00% Delayed & Not Start
175 254 16-Feb-16 11-May-16 86
502-FAEI-20130 Cables Continuity Check for 14-E2 : AC Diesel Generators 1 Sch. 50.180 3 1.18% 4-May-16 7-May-16 4 90.00% 100.00% Delayed
502-FAEI-20140 Cables Continuity Check for 14-E3 : DC Supply 36 Sch. 50.180 26 10.24% 9-May-16 11-May-16 3 25.00% 50.00% Delayed
502-FAEI-20150 Cables Continuity Check for 14-E4 : Power & Lighting and Outlet 118 Sch. 50.180 196 77.17% 29-Apr-16 7-May-16 9 83.90% 100.00% Delayed
502-FAEI-20170 Cables Continuity Check for 14-E6 : TEG - Gas Platform 9 Sch. 50.180 13 5.12% 7-May-16 10-May-16 4 90.00% 100.00% Delayed
502-FAEI-20180 Cables Continuity Check for 16-E1 : Navigation Aids System 11 Sch. 50.180 16 6.30% 4-May-16 6-May-16 3 0.00% 100.00% Delayed & Not Start
13 74 4-May-16 6-May-16 3
502-FAEI-20190 Cables Continuity Check for 15-T1 : Comunication System 13 Sch. 50.180 74 100.00% 4-May-16 6-May-16 3 0.00% 100.00% Delayed & Not Start
11 22 4-May-16 9-May-16 6
502-FAEI-20200 Cables Continuity Check for 17-S2 : Emergency Shutdown 2 Sch. 50.180 3 13.64% 4-May-16 6-May-16 3 0.00% 100.00% Delayed & Not Start
502-FAEI-20210 Cables Continuity Check for 17-S3 : Fire & Gas Detector 5 Sch. 50.180 12 54.55% 6-May-16 9-May-16 4 0.00% 75.00% Delayed & Not Start
502-FAEI-20220 Cables Continuity Check for 17-S4 : Beacon Light & Siren 4 Sch. 50.180 7 31.82% 6-May-16 9-May-16 4 0.00% 78.57% Delayed & Not Start
604 995 -19.53%
L5 L4 L5 L4 L5 L4
339 508 29-Apr-16 28-May-16 30
72 112 23-May-16 26-May-16 4
72 112 23-May-16 26-May-16 4
502-FAEI-20230 Tubings Installation for 06-I1 : HP Vent / LP Vent 72 m. 50.175 112 100.00% 23-May-16 26-May-16 4 90.00% 100.00% Delayed
189 153 3-May-16 14-May-16 12
189 153 3-May-16 14-May-16 12
502-FAEI-20240 Tubings Installation for 11-I1 : Chemical Injection 189 m. 50.175 153 100.00% 3-May-16 9-May-16 7 90.00% 100.00% Delayed
78 243 29-Apr-16 28-May-16 30
69 122 6-May-16 9-May-16 4
502-FAEI-20260 Tubings Installation for 13-C1 : Back Start 69 m. 50.175 122 100.00% 6-May-16 9-May-16 4 90.00% 100.00% Delayed
9 121 29-Apr-16 28-May-16 30
502-FAEI-20270 Tubings Installation for 14-E6 : TEG - Gas Platform 9 m. 50.175 20 16.53% 29-Apr-16 30-Apr-16 2 90.00% 100.00% Delayed
3478 12-Feb-16 30-May-16 109
2874 870 12-Feb-16 26-Feb-16 15
502-FAEI-20290 Pre-Cutting and Pre-Bending 2874 m. 50.175 870 100.00% 12-Feb-16 26-Feb-16 15 100.00% 100.00% Completed
2535 2608 11-Apr-16 30-May-16 50
483 227 11-Apr-16 30-May-16 50
483 227 11-Apr-16 30-May-16 50
502-FAEI-20310 Tubings Installation for 01-I1: Process Production 456 m. 50.175 195 85.90% 11-Apr-16 21-Apr-16 11 90.00% 100.00% Delayed
502-FAEI-20320 Tubings Installation for 10-I1 : Booster Compressor 27 m. 50.175 32 14.10% 23-May-16 30-May-16 8 90.00% 100.00% Delayed
2052 2381 11-Apr-16 18-May-16 38
1273 1529 29-Apr-16 18-May-16 20
502-FAEI-20330 Tubings Installation for 13-C3 : Wellhead Control Panel 1273 m. 50.175 1529 100.00% 29-Apr-16 18-May-16 20 90.00% 100.00% Delayed
779 852 11-Apr-16 29-Apr-16 19
502-FAEI-20340 Tubings Installation for 17-S1 : Fire Emergency Shutdown (FESD) 531 m. 50.175 579 67.96% 11-Apr-16 29-Apr-16 19 90.00% 100.00% Delayed
502-FAEI-20350 Tubings Installation for 17-S2 : Emergency Shutdown 248 m. 50.175 273 32.04% 11-Apr-16 29-Apr-16 19 90.00% 100.00% Delayed
2874 3986 -7.56%
L5 L4 L5 L4 L5 L4
438 102 31-May-16 10-Jun-16 11
96 9 31-May-16 2-Jun-16 3
96 9 31-May-16 2-Jun-16 3
502-FAEI-20360 Tubings Leak Test for 06-I1 : HP Vent / LP Vent 96 m. 50.180 9 100.00% 31-May-16 2-Jun-16 3 0.00% 72.22% Delayed & Not Start Should be finished
189 50 31-May-16 10-Jun-16 11
189 50 31-May-16 10-Jun-16 11
502-FAEI-20370 Tubings Leak Test for 11-I1 : Chemical Injection 189 m. 50.180 50 100.00% 31-May-16 3-Jun-16 4 0.00% 50.00% Delayed & Not Start Should be finished
153 43 31-May-16 6-Jun-16 7
Sub-System - 7001 : Chemical (C) 100.00% 0.00% 50.00%
System - 8000 : Others 42.16% 0.00% 84.88%
System - 2000 : Drains & Reliefs 8.82% 0.00% 72.22%
Sub-System - 2500 : Blow Down (BD) 100.00% 0.00% 72.22%
System - 7000 : Chemicals 49.02% 0.00% 50.00%
Status
Next 2 Wks
As Per Planed
RemarkL3
Start Finish Dur.
Tested Check Sheet : PLT-T L3 L3
90% 10%
Bare Tube Leak Test 35.92% 0.00% 66.18%
Sub-System - 8000D : Safety Intrergrity System (SIS) 35.78% 90.00% 100.00%
531
248
SUB-TOTAL OF TUBINGS INSTALLATION 16.56% 2874 92.44% 100.00%
456
27
System - 8000 : Others 91.30% 90.00% 100.00%
Sub-System - 8000A : Process Control 64.22% 90.00% 100.00%
1273
2874
Field Installation and Hook-Up 74.99% 90.00% 100.00%
System - 1000 : Process Production 8.70% 90.00% 100.00%
Sub-System - 1001 : Process Liquid & Vapour (P) 100.00% 90.00% 100.00%
Sub-System - 8000B : Electrical Generation and Distribution 49.79% 98.35% 100.00%
9
TPU Jacket Tube Installation 87.26% 92.50% 100.00%
Preparation Works 25.01% 100.00% 100.00%
189
System - 8000 : Others 47.83% 94.16% 100.00%
Sub-System - 8000A : Process Control 50.21% 90.00% 100.00%
69
90.00% 100.00%
72
System - 7000 : Chemicals 30.12% 90.00% 100.00%
System - 2000 : Drains & Reliefs 22.05%
Sub-System - 7001 : Chemical (C) 100.00% 90.00% 100.00%
Status
Next 2 Wks
As Per Planed
RemarkL3
Start Finish Dur.
Tube Running Check Sheet : PIC-T L3 L3
90% 10%
Bare Tube Installation 12.74% 91.99% 100.00%
91.21%SUB-TOTAL OF CABLES CONTINUITY & INSULATION TEST 4.13% 466 71.67%
TUBINGS LEAK TEST QTY Unit Cost Code
Budgeted
Mhrs
WTG% Baseline Activity Milestones % Actual %Plan
90.00% 100.00%
Sub-System - 2500 : Blow Down (BD) 100.00%
0.00% 100.00%
Sub-System - 8000D : Safety Intrergrity System (SIS) 5.38% 0.00% 79.55%
9
Sub-System - 8000C : Communication 18.09%
10
110
72.97% 94.88%
1
Sub-System - 8000B : Electrical Generation and Distribution 62.10%
45.32% 95.72%
Sub-System - 8000A : Process Control 14.43% 0.00% 100.00%
18
System - 8000 : Others 41.11%
90.00% 50.00%
Sub-System - 7001 : Chemical (C) 100.00% 90.00% 50.00%
System - 7000 : Chemicals 1.81%
90.00% 50.00%
6
10
Sub-System - 4500 : Gas Utility (GU) 37.50%
Sub-System - 4400 : Gas Instrument (GI) 62.50% 90.00% 100.00%
48
76
90.00%
3
System - 4000 : Utility Generals 2.41% 90.00% 81.25%
6
Sub-System - 2100 : Open Drain (DO) 30.77%
90.00% 100.00%
Sub-System - 2001 : Closed Drain (DC) 69.23% 90.00% 100.00%
RemarkL3
Start Finish Dur.
Tested Check Sheet : PLT-C
Activity Milestones % Actual %Plan
Status
Next 2 Wks
As Per Planed
L3 L3
90% 10%
CABLES CONTINUITY & INSULATION TEST QTY Unit Cost Code
Budgeted
Mhrs
WTG% Baseline
Sub-System - 1001 : Process Liquid & Vapour (P) 100.00% 90.08% 89.45%
System - 1000 : Process Production 53.37% 90.08% 89.45%
48
98.58% 100.00%
2
5
4
SUB-TOTAL OF CABLES INSTALLATION 34.40%
TUBINGS INSTALLATION QTY Unit Cost Code
Budgeted
Mhrs
WTG% Baseline Activity Milestones % Actual %Plan
System - 2000 : Drains & Reliefs 1.31%
121
100.00%
13
Sub-System - 8000D : Safety Intrergrity System (SIS) 4.67% 95.25% 100.00%
9
11
Sub-System - 8000C : Communication 4.67% 90.58%
100.00%
1
36
118
67
Sub-System - 8000B : Electrical Generation and Distribution 66.53% 97.72%
100.00%
Sub-System - 8000A : Process Control 24.14% 96.87% 100.00%
18
System - 8000 : Others 38.82% 97.07%
System - 7000 : Chemicals 1.51% 100.00% 100.00%
Sub-System - 7001 : Chemical (C) 100.00% 100.00% 100.00%
Sub-System - 4500 : Gas Utility (GU) 37.79% 96.25% 100.00%
6
Sub-System - 4400 : Gas Instrument (GI) 62.21% 97.00% 100.00%
10
3
System - 4000 : Utility Generals 2.62% 96.72% 100.00%
6
Sub-System - 2100 : Open Drain (DO) 33.87% 97.50% 100.00%
System - 2000 : Drains & Reliefs 1.50% 98.33% 100.00%
Sub-System - 2001 : Closed Drain (DC) 66.13% 98.75% 100.00%
50
76
48
Sub-System - 1001 : Process Liquid & Vapour (P) 100.00% 99.69% 100.00%
121
45%
System - 1000 : Process Production 55.55% 99.69% 100.00%
Next 2 Wks
As Per Planed
Remark
Start Finish Dur.
Pulled
Activity Milestones
Status
Glanded Terminated
L3 L3
100.00% 100.00%
CABLES INSTALLATION QTY Unit Cost Code
Budgeted
Mhrs
Baseline
5 100.00%
SUB-TOTAL OF CALIBRATION OF INSTRUMENTS TAG 5.37%
100.00% 100.00%
1 100.00%
Sub-System - 8000D : Safety Intrergrity System (SIS) 5.80% 100.00% 100.00%
WTG% % Actual %Plan
L3
3 100.00%
48 100.00%
Sub-System - 8000B : Electrical Generation and Distribution 1.34%
100.00% 100.00%
Sub-System - 8000A : Process Control 92.86% 100.00% 100.00%
21 100.00%
System - 8000 : Others 17.31%
100.00% 100.00%
Sub-System - 7001 : Chemical (C) 100.00% 100.00% 100.00%
System - 7000 : Chemicals 4.56%
100.00% 100.00%
10 100.00%
14 100.00%
Sub-System - 4500 : Gas Utility (GU) 41.18%
100.00% 100.00%
Sub-System - 4400 : Gas Instrument (GI) 58.82% 100.00% 100.00%
1 100.00%
System - 4000 : Utility Generals 5.26%
100.00% 100.00%
5 100.00%
Sub-System - 2500 : Blow Down (BD) 7.89% 100.00% 100.00%
8 100.00%
Sub-System - 2100 : Open Drain (DO) 34.21%
100.00% 100.00%
Sub-System - 2001 : Closed Drain (DC) 57.89% 100.00% 100.00%
26 100.00%
System - 2000 : Drains & Reliefs 2.94%
1 100.00%
193 100.00%
28 100.00%
50 100.00%
100.00%
Sub-System - 1001 : Process Liquid & Vapour (P) 100.00% 100.00% 100.00%
System - 1000 : Process Production 69.94% 421 100.00%
Next 2 Wks
As Per Planed
RemarkL3
Start Finish Dur.
Calibrated
Activity Milestones % Actual %Plan
StatusCheck Sheet : PCC L3 L3
90%
100.00% 100.00%
CALIBRATION OF INSTRUMENTS TAG QTY Unit Cost Code
Budgeted
Mhrs
WTG% Baseline
670 670
109 109
SUB-TOTAL OF E&I SUPPORTS, LADDERS AND TRAYS 35.06%
10%
Installation of E&I Trays&Ladders 31.13% 100.00% 100.00%
Upper Deck
273 273
91 91
Mezzanine Deck
37 37
215 215
Cellar Deck
475 475
176 176
Sub-Cellar Deck
1 1
30 30
100.00% 100.00%
Installation of E&I Supports 68.87% 100.00% 100.00%
364 364
Installation 55.90%
31 31
651 651
252 252
L3
90% 10%
Fabrication 44.10% 100.00% 100.00%
CHEVRON : CVX-PHASE 50
PROGRESS MEASUREMENT WORK SHEET FOR E&I AND PRE-COMMISSIONING WORKS
WHP 50/2 : GAS PLATFORM
WHP 50/2 : GAS PLATFORM : E&I INSTALLATION
E&I SUPPORTS, LADDERS AND TRAYS QTY Unit Cost Code
Budgeted
Mhrs
%Plan
Status
Next 2 Wks
As Per Planed
RemarkL3
Start Finish Dur.
WTG% Baseline Activity Milestones % Actual
Fabricated/Installed Accepted /Painted/Cleaning L3
604
Page 7 of 10 Prepared By : Nattakarn S.
Activity ID Activity Name Num. Budgeted Units Planned Start Planned Finish % Actual 1-Jun-16
CHEVRON : CVX-PHASE 50
PROGRESS MEASUREMENT WORK SHEET FOR E&I AND PRE-COMMISSIONING WORKS
WHP 50/2 : GAS PLATFORM
84 21 31-May-16 3-Jun-16 4
502-FAEI-20390 Tubings Leak Test for 13-C1 : Back Start 84 m. 50.180 21 100.00% 31-May-16 3-Jun-16 4 0.00% 100.00% Delayed & Not Start Should be finished
69 22 4-Jun-16 6-Jun-16 3
502-FAEI-20400 Tubings Leak Test for 14-E6 : TEG - Gas Platform 9 m. 50.180 11 50.00% 4-Jun-16 4-Jun-16 1 0.00% 100.00% Delayed & Not Start Should be started
502-FAEI-20410 Tubings Leak Test for 14-E7 : CO2 Skid - Option Gas Platform 60 m. 50.180 11 50.00% 6-Jun-16 6-Jun-16 1 0.00% 40.91% Delayed & Not Start Should be started
2535 182 31-May-16 9-Jun-16 10
483 56 8-Jun-16 9-Jun-16 2
483 56 8-Jun-16 9-Jun-16 2
502-FAEI-20420 Tubings Leak Test for 01-I1: Process Production 456 m. 50.180 45 80.36% 8-Jun-16 9-Jun-16 2 0.00% 0.00% Should be started
502-FAEI-20430 Tubings Leak Test for Booster Compressor 27 m. 50.180 11 19.64% 8-Jun-16 8-Jun-16 1 0.00% 0.00% Should be started
2052 126 31-May-16 7-Jun-16 8
1273 90 31-May-16 3-Jun-16 4
502-FAEI-20440 Tubings Leak Test for 13-C3 : Wellhead Control Panel 1273 m. 50.180 90 100.00% 31-May-16 3-Jun-16 4 0.00% 63.33% Delayed & Not Start Should be finished
779 36 6-Jun-16 7-Jun-16 2
502-FAEI-20450 Tubings Leak Test for 17-S1 : Fire Emergency Shutdown (FESD) 531 m. 50.180 18 50.00% 7-Jun-16 7-Jun-16 1 0.00% 0.00% Should be started
502-FAEI-20460 Tubings Leak Test for 17-S2 : Emergency Shutdown 248 m. 50.180 18 50.00% 6-Jun-16 6-Jun-16 1 0.00% 38.89% Delayed & Not Start Should be started
2973 284 -46.48%
L5 L4 L5 L4 L5 L4
253 363 25-Apr-16 13-Jun-16 50
253 363 25-Apr-16 13-Jun-16 50
502-FAEI-20470 Hook-Up of E&I Tags for 01-I1: Process Production 145 Ea. 50.175 148 40.77% 29-Apr-16 27-May-16 29 50.07% 87.84% Delayed
502-FAEI-20480 Hook-Up of E&I Tags for 01-I2 : Production Header 28 Ea. 50.175 43 11.85% 25-Apr-16 23-May-16 29 57.86% 87.21% Delayed
502-FAEI-20490 Hook-Up of E&I Tags for 02-I1 : Test Separator 52 Ea. 50.175 75 20.66% 3-May-16 19-May-16 17 55.38% 81.33% Delayed
502-FAEI-20500 Hook-Up of E&I Tags for 03-I1 : Pig Luncher 1 Ea. 50.175 1 0.28% 18-May-16 21-May-16 4 0.00% 100.00% Delayed & Not Start
502-FAEI-20540 Hook-Up of E&I Tags for 10-I1 : Booster Compressor 27 Ea. 50.175 41 11.29% 14-May-16 2-Jun-16 20 55.56% 56.10% Delayed Should be finished
15 22 23-Apr-16 7-Jun-16 46
9 13 23-Apr-16 3-May-16 11
502-FAEI-20550 Hook-Up of E&I Tags for 08-I1 : Closed Drain System 9 Ea. 50.175 13 100.00% 23-Apr-16 3-May-16 11 53.33% 76.92% Delayed
5 8 17-May-16 21-May-16 5
502-FAEI-20560 Hook-Up of E&I Tags for 09-I1 : Open Drain System 5 Ea. 50.175 8 100.00% 17-May-16 21-May-16 5 48.00% 68.75% Delayed
1 1 6-Jun-16 7-Jun-16 2
502-FAEI-20570 Hook-Up of E&I Tags for 06-I1 : HP Vent / LP Vent 1 Ea. 50.175 1 100.00% 6-Jun-16 7-Jun-16 2 0.00% 0.00% Should be started
28 41 30-Mar-16 26-Apr-16 28
17 23 30-Mar-16 8-Apr-16 10
502-FAEI-20580 Hook-Up of E&I Tags for 04-I1 : Instrument Gas 17 Ea. 50.175 23 100.00% 30-Mar-16 8-Apr-16 10 42.35% 56.52% Delayed
11 18 1-Apr-16 26-Apr-16 26
502-FAEI-20590 Hook-Up of E&I Tags for 04-I2 : Utility Gas 11 Ea. 50.175 18 100.00% 1-Apr-16 11-Apr-16 11 43.64% 55.56% Delayed
24 35 10-May-16 14-Jun-16 36
24 35 10-May-16 14-Jun-16 36
502-FAEI-20620 Hook-Up of E&I Tags for 11-I1 : Chemical Injection 24 Ea. 50.175 35 100.00% 10-May-16 16-May-16 7 90.00% 78.57% Ahead
230 332 20-Jan-16 11-Jun-16 144
67 226 11-Apr-16 18-May-16 38
502-FAEI-20640 Hook-Up of E&I Tags for 13-C1 : Back Start 4 Ea. 50.175 7 3.10% 11-Apr-16 19-Apr-16 9 90.00% 78.57% Ahead
502-FAEI-20650 Hook-Up of E&I Tags for 13-C2 : PLC and Control system 14 Ea. 50.175 22 9.73% 30-Apr-16 14-May-16 15 62.14% 95.45% Delayed
502-FAEI-20660 Hook-Up of E&I Tags for 13-C3 : Wellhead Control Panel 49 Ea. 50.175 197 87.17% 30-Apr-16 18-May-16 19 60.00% 91.37% Delayed
132 60 20-Jan-16 11-Jun-16 144
502-FAEI-20680 Hook-Up of E&I Tags for 14-E2 : AC Diesel Generators 1 Ea. 50.175 1 1.67% 26-Apr-16 4-May-16 9 60.00% 100.00% Delayed
502-FAEI-20690 Hook-Up of E&I Tags for 14-E3 : DC Supply 7 Ea. 50.175 10 16.67% 23-Feb-16 26-Feb-16 4 55.71% 70.00% Delayed
502-FAEI-20700 Hook-Up of E&I Tags for 14-E4 : Power & Lighting and Outlet 110 Ea. 50.175 28 46.67% 20-Jan-16 24-Feb-16 36 62.18% 91.07% Delayed
502-FAEI-20720 Hook-Up of E&I Tags for 14-E6 : TEG - Gas Platform 5 Ea. 50.175 8 13.33% 16-Apr-16 25-Apr-16 10 60.00% 81.25% Delayed
502-FAEI-20730 Hook-Up of E&I Tags for 16-E1 : Navigation Aids System 9 Ea. 50.175 13 21.67% 2-Mar-16 10-Mar-16 9 53.33% 76.92% Delayed
5 7 10-Mar-16 18-Mar-16 9
502-FAEI-20740 Hook-Up of E&I Tags for 15-T1 : Comunication System 5 Ea. 50.175 7 100.00% 10-Mar-16 18-Mar-16 9 60.00% 78.57% Delayed
26 39 3-May-16 24-May-16 22
502-FAEI-20750 Hook-Up of E&I Tags for 17-S2 : Emergency Shutdown 10 Ea. 50.175 13 33.33% 3-May-16 14-May-16 12 60.00% 80.77% Delayed
502-FAEI-20760 Hook-Up of E&I Tags for 17-S3 : Fire & Gas Detector 5 Ea. 50.175 8 20.51% 17-May-16 24-May-16 8 60.00% 81.25% Delayed
502-FAEI-20770 Hook-Up of E&I Tags for 17-S4 : Beacon Light & Siren 11 Ea. 50.175 18 46.15% 3-May-16 7-May-16 5 60.00% 80.56% Delayed
550 793 -21.03%
24076 -3.42%
L5 L4 L5 L4 L5 L4
704 14-Jun-16 18-Jun-16 5
84 704 14-Jun-16 18-Jun-16 5
84 704 14-Jun-16 18-Jun-16 5
502-FAPC-20470 Fuction Test of 14-E2 : AC Diesel Generators 10 Pac. 60.220 71 10.09% 16-Jun-16 17-Jun-16 2 0.00% 0.00%
502-FAPC-20480 Fuction Test of 14-E3 : DC Supply 21 Pac. 60.220 174 24.72% 16-Jun-16 17-Jun-16 2 0.00% 0.00%
502-FAPC-20490 Fuction Test of 14-E4 : Power & Lighting and Outlet 39 Pac. 60.220 322 45.74% 14-Jun-16 15-Jun-16 2 0.00% 0.00% Should be started
502-FAPC-20510 Fuction Test of 14-E6 : TEG - Gas Platform 6 Pac. 60.220 21 2.98% 18-Jun-16 18-Jun-16 1 0.00% 0.00%
502-FAPC-20520 Fuction Test of 16-E1 : Navigation Aids System 8 Pac. 60.220 116 16.48% 16-Jun-16 17-Jun-16 2 0.00% 0.00%
1241 15-Jun-16 18-Jun-16 4
237 823 15-Jun-16 18-Jun-16 4
237 823 15-Jun-16 18-Jun-16 4
502-FAPC-20540 Loop Test of 01-I1: Process Production 98 Pac. 60.225 340 41.31% 15-Jun-16 16-Jun-16 2 0.00% 0.00% Should be started
502-FAPC-20550 Loop Test of 01-I2 : Production Header 27 Pac. 60.225 94 11.42% 16-Jun-16 17-Jun-16 2 0.00% 0.00%
502-FAPC-20560 Loop Test of 02-I1 : Test Separator 55 Pac. 60.225 191 23.21% 17-Jun-16 18-Jun-16 2 0.00% 0.00%
502-FAPC-20570 Loop Test of 03-I2 : Pig Receiver - Option 12 Pac. 60.225 42 5.10% 17-Jun-16 18-Jun-16 2 0.00% 0.00%
502-FAPC-20600 Loop Test of 10-I1 : Booster Compressor 45 Pac. 60.225 156 18.96% 16-Jun-16 17-Jun-16 2 0.00% 0.00%
9 32 16-Jun-16 17-Jun-16 2
6 21 16-Jun-16 17-Jun-16 2
502-FAPC-20610 Loop Test of 08-I1 : Closed Drain System 6 Pac. 60.225 21 100.00% 16-Jun-16 17-Jun-16 2 0.00% 0.00%
3 11 16-Jun-16 17-Jun-16 2
502-FAPC-20620 Loop Test of 09-I1 : Open Drain System 3 Pac. 60.225 11 100.00% 16-Jun-16 17-Jun-16 2 0.00% 0.00%
13 32 16-Jun-16 17-Jun-16 2
9 21 16-Jun-16 17-Jun-16 2
502-FAPC-20630 Loop Test of 04-I1 : Instrument Gas 9 Pac. 60.225 21 100.00% 16-Jun-16 17-Jun-16 2 0.00% 0.00%
4 11 16-Jun-16 17-Jun-16 2
502-FAPC-20640 Loop Test of 04-I2 : Utility Gas 4 Pac. 60.225 11 100.00% 16-Jun-16 17-Jun-16 2 0.00% 0.00%
12 32 16-Jun-16 16-Jun-16 1
12 32 16-Jun-16 16-Jun-16 1
502-FAPC-20670 Loop Test of 11-I1 : Chemical Injection 12 Pac. 60.225 32 100.00% 16-Jun-16 16-Jun-16 1 0.00% 0.00%
49 322 16-Jun-16 17-Jun-16 2
30 187 16-Jun-16 17-Jun-16 2
502-FAPC-20690 Loop Test of 13-C3 : Wellhead Control Panel 30 Pac. 60.225 187 100.00% 16-Jun-16 17-Jun-16 2 0.00% 0.00%
1 4 16-Jun-16 17-Jun-16 2
502-FAPC-20700 Loop Test of 15-T1 : Comunication System 1 Pac. 60.225 4 100.00% 16-Jun-16 17-Jun-16 2 0.00% 0.00%
18 131 16-Jun-16 16-Jun-16 1
502-FAPC-20710 Loop Test of 17-S2 : Emergency Shutdown 3 Pac. 60.225 12 9.16% 16-Jun-16 16-Jun-16 1 0.00% 0.00%
502-FAPC-20720 Loop Test of 17-S3 : Fire & Gas Detector 8 Pac. 60.225 28 21.37% 16-Jun-16 16-Jun-16 1 0.00% 0.00%
502-FAPC-20730 Loop Test of 17-S4 : Beacon Light & Siren 7 Pac. 60.225 91 69.47% 16-Jun-16 16-Jun-16 1 0.00% 0.00%
404 1945 0.00%
L5 L4 L5 L4 L5 L4
502-FAPC-20740 Platform Site Acceptance Test - SAT 100 Pac. 60.235 555 20-Jun-16 25-Jun-16 6
100 555 0.00%
2500 0.00%
-3.10%
SUB-TOTAL OF TUBINGS LEAK TEST 1.18% 0.00% 46.48%
Sub-System - 8000A : Process Control 71.43% 0.00% 63.33%
Sub-System - 8000D : Safety Intrergrity System (SIS) 28.57% 0.00% 19.44%
0.00%
Sub-System - 1001 : Process Liquid & Vapour (P) 100.00% 0.00% 0.00%
System - 8000 : Others 69.23% 0.00% 50.79%
System - 1000 : Process Production 30.77% 0.00%
Sub-System - 8000B : Electrical Generation and Distribution 51.16% 0.00% 70.45%
TPU Jacket Tube Leak Test 64.08% 0.00% 35.16%
Sub-System - 8000A : Process Control 48.84% 0.00% 100.00%
85.71% 88.80%OVERALL PROGRESS OF WHP 50/2 : GAS PLATFORM 26576 100.00%
0.00%
TOTAL OF WHP 50/2 : GAS PLATFORM : E&I PRE-COMMISSIONING 9.41% 0.00% 0.00%
100.00% 0.00% 0.00%
SUB-TOTAL OF SITE ACCEPTANC TEST - SAT 22.20% 0.00%
RemarkL3
Start Finish Dur.
Activity Milestones % Actual %Plan
Status
Next 2 Wks
As Per Planed
SAT Completion L3 L3
100%
0.00%
SITE ACCEPTANC TEST - SAT QTY Unit Cost Code
Budgeted
Mhrs
WTG% Baseline
SUB-TOTAL OF LOOP/ FUNCTION TEST 77.80% 0.00%
0.00% 0.00%
Sub-System - 8000D : Safety Intrergrity System (SIS) 40.68% 0.00% 0.00%
Sub-System - 8000C : Communication 1.24%
0.00% 0.00%
Sub-System - 8000A : Process Control 58.07% 0.00% 0.00%
System - 8000 : Others 25.95%
0.00% 0.00%
Sub-System - 7001 : Chemical (C) 100.00% 0.00% 0.00%
System - 7000 : Chemicals 2.58%
0.00% 0.00%Sub-System - 4500 : Gas Utility (GU) 34.38%
Sub-System - 4400 : Gas Instrument (GI) 65.63% 0.00% 0.00%
0.00% 0.00%
System - 4000 : Utility Generals 2.58% 0.00% 0.00%
Sub-System - 2100 : Open Drain (DO) 34.38%
0.00% 0.00%
Sub-System - 2001 : Closed Drain (DC) 65.63% 0.00% 0.00%
System - 2000 : Drains & Reliefs 2.58%
Sub-System - 1001 : Process Liquid & Vapour (P) 100.00% 0.00% 0.00%
0.00% 0.00%
System - 1000 : Process Production 66.32% 0.00% 0.00%
Instrumentation 63.80%
Sub-System - 8000B : Electrical Generation and Distribution 100.00% 0.00% 0.00%
System - 8000 : Others 100.00% 0.00% 0.00%
Electrical 36.20% 0.00% 0.00%
%Plan
Status
Next 2 Wks
As Per Planed
RemarkL3
Start Finish Dur.
WTG% Baseline Activity Milestones % Actual
Tested Check Sheet : PLT-L & PFT
WHP 50/2 : GAS PLATFORM : E&I PRE-COMMISSIONING
LOOP/ FUNCTION TEST QTY Unit Cost Code
Budgeted
Mhrs
TOTAL OF WHP 50/2 : GAS PLATFORM : E&I INSTALLATION 90.59% 94.61% 98.02%
L3 L3
90% 10%
81.46%SUB-TOTAL OF HOOK-UP OF E&I TAG ITEMS 3.29% 60.44%
11
Sub-System - 8000B : Electrical Generation and Distribution 18.07% 58.86% 83.33%
1
6 1
60.00% 78.57%
Sub-System - 8000D : Safety Intrergrity System (SIS) 11.75% 60.00% 79.49%
Sub-System - 8000C : Communication 2.11%
110 8
5
8
60.57% 88.40%
Sub-System - 8000A : Process Control 68.07% 61.14% 91.59%
System - 8000 : Others 41.87%
90.00% 78.57%
Sub-System - 7001 : Chemical (C) 100.00% 90.00% 78.57%
24 24
43.64% 55.56%Sub-System - 4500 : Gas Utility (GU) 43.90%
42.92% 54.88%
Sub-System - 4400 : Gas Instrument (GI) 56.10% 42.35% 56.52%
8
System - 7000 : Chemicals 4.41%
System - 4000 : Utility Generals 5.17%
48.00% 68.75%
Sub-System - 2500 : Blow Down (BD) 4.55% 0.00% 0.00%
Sub-System - 2100 : Open Drain (DO) 36.36%
8
4
48.97% 70.45%
Sub-System - 2001 : Closed Drain (DC) 59.09% 53.33% 76.92%
System - 2000 : Drains & Reliefs 2.77%
25
79.06%
Sub-System - 1001 : Process Liquid & Vapour (P) 100.00% 60.14% 79.06%
System - 1000 : Process Production 45.78% 60.14%
HOOK-UP OF E&I TAG ITEMS QTY Unit Cost Code
Budgeted
Mhrs
505 38
Next 2 Wks
As Per Planed
RemarkL3
Start Finish Dur.
Activity Milestones % Actual %Plan
StatusL3 L3
WTG% Baseline
Installed Hook-Up Check Sheet : PIC-H
60% 30% 10%
27
48
121
4 4
10
5
14 1
49
5
12
Page 8 of 10 Prepared By : Nattakarn S.
Activity ID Activity Name Num. Budgeted Units Planned Start Planned Finish % Actual 1-Jun-16
L5 L4 L5 L4 L5 L4
1327 3723 21-Aug-15 28-Oct-15 69
505-FAEI-23720 Fabrication of E&I Supports for Sub-Cellar Deck 31 Ea. 50.170 98 2.63% 24-Aug-15 8-Sep-15 16 100.00% 100.00% Completed
505-FAEI-23730 Fabrication of E&I Supports for Cellar Deck 667 Ea. 50.170 1915 51.44% 21-Aug-15 16-Oct-15 57 100.00% 100.00% Completed
505-FAEI-23740 Fabrication of E&I Supports for Mezzanine Deck 250 Ea. 50.170 525 14.10% 25-Sep-15 28-Oct-15 34 100.00% 100.00% Completed
505-FAEI-23750 Fabrication of E&I Supports for Upper Deck 379 Ea. 50.170 1185 31.83% 24-Aug-15 2-Oct-15 40 100.00% 100.00% Completed
4719 30-Oct-15 16-Apr-16 170
1327 3250 30-Oct-15 21-Mar-16 144
31 106 3.26% 25-Dec-15 10-Feb-16 48 100.00% 100.00%
505-FAEI-23760 Installation of E&I Support at Sub-Cellar Deck - Assembly Bay 1 Ea. 50.170 12 11.32% 25-Dec-15 5-Jan-16 12 100.00% 100.00% Completed
505-FAEI-23770 Installation of E&I Support at Sub-Cellar Deck - Erection Area 30 Ea. 50.170 94 88.68% 25-Jan-16 10-Feb-16 17 100.00% 100.00% Completed
667 1614 49.66% 30-Oct-15 20-Feb-16 114 100.00% 100.00%
505-FAEI-23780 Installation of E&I Support at Cellar Deck - Assembly Bay 481 Ea. 50.170 1035 64.13% 30-Oct-15 23-Nov-15 25 100.00% 100.00% Completed
505-FAEI-23790 Installation of E&I Support at Cellar Deck - Erection Area 186 Ea. 50.170 579 35.87% 8-Dec-15 20-Feb-16 75 100.00% 100.00% Completed
250 546 16.80% 20-Nov-15 21-Mar-16 123 100.00% 100.00%
505-FAEI-23800 Installation of E&I Support at Mezzanine Deck - Assembly Bay 37 Ea. 50.170 118 21.61% 20-Nov-15 9-Dec-15 20 100.00% 100.00% Completed
505-FAEI-23810 Installation of E&I Support at Mezzanine Deck - Erection Area 213 Ea. 50.170 428 78.39% 25-Feb-16 21-Mar-16 26 100.00% 100.00% Completed
379 984 30.28% 27-Nov-15 28-Jan-16 63 100.00% 100.00%
505-FAEI-23820 Installation of E&I Support at UpperDeck - Assembly Bay 282 Ea. 50.170 662 67.28% 27-Nov-15 24-Dec-15 28 100.00% 100.00% Completed
505-FAEI-23830 Installation of E&I Support at UpperDeck - Erection Area 97 Ea. 50.170 322 32.72% 7-Jan-16 28-Jan-16 22 100.00% 100.00% Completed
779 1469 18-Dec-15 16-Apr-16 121
505-FAEI-23840 Installation of Cable Trays&Ladders 670 m. 50.170 942 64.13% 18-Dec-15 29-Jan-16 43 100.00% 100.00% Completed
505-FAEI-23850 Installation of Tubing Trays&Ladders 109 m. 50.170 527 35.87% 30-Mar-16 16-Apr-16 18 100.00% 100.00% Completed
8442 0.00%
L5 L4 L5 L4 L5 L4
305 905 2-Nov-15 2-Mar-16 122
305 905 2-Nov-15 2-Mar-16 122
505-FAEI-23860 Calibration of Instrument Tags - 01-I1: Process Production 193 Ea. 50.165 535 59.12% 2-Nov-15 26-Dec-15 55 100.00% 100.00% Completed
505-FAEI-23870 Calibration of Instrument Tags - 01-I2 : Production Header 28 Ea. 50.165 76 8.40% 18-Nov-15 1-Dec-15 14 100.00% 100.00% Completed
505-FAEI-23880 Calibration of Instrument Tags - 02-I1 : Test Separator 50 Ea. 50.165 140 15.47% 1-Dec-15 29-Dec-15 29 100.00% 100.00% Completed
505-FAEI-23890 Calibration of Instrument Tags - 03-I1 : Pig Luncher 1 Ea. 50.165 3 0.33% 8-Jan-16 11-Jan-16 4 100.00% 100.00% Completed
505-FAEI-23930 Calibration of Instrument Tags - 10-I1 : Booster Compressor 26 Ea. 50.165 75 8.29% 29-Dec-15 13-Jan-16 16 100.00% 100.00% Completed
14 38 24-Oct-15 18-Dec-15 56
8 22 24-Oct-15 24-Oct-15 1
505-FAEI-23940 Calibration of Instrument Tags - 08-I1 : Closed Drain System 8 Ea. 50.165 22 100.00% 24-Oct-15 24-Oct-15 1 100.00% 100.00% Completed
5 13 14-Dec-15 15-Dec-15 2
505-FAEI-23950 Calibration of Instrument Tags - 09-I1 : Open Drain System 5 Ea. 50.165 13 100.00% 14-Dec-15 15-Dec-15 2 100.00% 100.00% Completed
1 3 16-Dec-15 18-Dec-15 3
505-FAEI-23960 Calibration of Instrument Tags - 06-I1 : HP Vent / LP Vent 1 Ea. 50.165 3 100.00% 16-Dec-15 18-Dec-15 3 100.00% 100.00% Completed
24 68 12-Dec-15 26-Dec-15 15
14 40 15-Dec-15 18-Dec-15 4
505-FAEI-23970 Calibration of Instrument Tags - 04-I1 : Instrument Gas 14 Ea. 50.165 40 100.00% 15-Dec-15 18-Dec-15 4 100.00% 100.00% Completed
10 28 12-Dec-15 26-Dec-15 15
505-FAEI-23980 Calibration of Instrument Tags - 04-I2 : Utility Gas 10 Ea. 50.165 28 100.00% 22-Dec-15 26-Dec-15 5 100.00% 100.00% Completed
21 59 3-Oct-15 7-Nov-15 36
21 59 3-Oct-15 7-Nov-15 36
505-FAEI-24010 Calibration of Instrument Tags - 11-I1 : Chemical Injection 21 Ea. 50.165 59 100.00% 3-Oct-15 15-Oct-15 13 100.00% 100.00% Completed
57 224 8-Oct-15 30-Jan-16 115
51 208 8-Oct-15 19-Dec-15 73
505-FAEI-24030 Calibration of Instrument Tags - 13-C1 : Back Start 3 Ea. 50.165 8 3.85% 18-Dec-15 19-Dec-15 2 100.00% 100.00% Completed
505-FAEI-24040 Calibration of Instrument Tags - 13-C3 : Wellhead Control Panel 48 Ea. 50.165 200 96.15% 8-Oct-15 7-Nov-15 31 100.00% 100.00% Completed
1 3 21-Dec-15 22-Dec-15 2
505-FAEI-24060 Calibration of Instrument Tags - 14-E6 : TEG - Gas Platform 1 Ea. 50.165 3 100.00% 21-Dec-15 22-Dec-15 2 100.00% 100.00% Completed
5 13 29-Jan-16 30-Jan-16 2
505-FAEI-24070 Calibration of Instrument Tags - 17-S3 : Fire & Gas Detector 5 Ea. 50.165 13 100.00% 29-Jan-16 30-Jan-16 2 100.00% 100.00% Completed
421 1294 0.00%
1st 2nd 1st 2nd
L5 L4 20.0% 20.0% 7.5% 7.5% L5 L4 L5 L4
253 4601 10-Mar-16 19-May-16 71
253 4601 10-Mar-16 19-May-16 71
505-FAEI-24080 Cables Installation for 01-I1: Process Production 115 Sch. 50.175 1968 42.77% 10-Mar-16 22-Apr-16 44 115 115 115 92.50% 97.38% Delayed
505-FAEI-24090 Cables Installation for 01-I2 : Production Header 38 Sch. 50.175 678 14.74% 19-Apr-16 7-May-16 19 36 38 38 91.45% 100.00% Delayed
505-FAEI-24100 Cables Installation for 02-I1 : Test Separator 64 Sch. 50.175 1033 22.45% 27-Apr-16 16-May-16 20 43 64 64 85.94% 100.00% Delayed
505-FAEI-24140 Cables Installation for 10-I1 : Booster Compressor 36 Sch. 50.175 651 14.15% 21-Apr-16 10-May-16 20 36 36 36 92.50% 82.49% Ahead
9 124 18-Apr-16 2-Jun-16 46
6 82 24-May-16 2-Jun-16 10
505-FAEI-24150 Cables Installation for 08-I1 : Closed Drain System 6 Sch. 50.175 82 100.00% 24-May-16 2-Jun-16 10 6 6 6 92.50% 100.00% Delayed Should be finished
3 42 18-Apr-16 26-Apr-16 9
505-FAEI-24160 Cables Installation for 09-I1 : Open Drain System 3 Sch. 50.175 42 100.00% 18-Apr-16 26-Apr-16 9 3 3 3 92.50% 100.00% Delayed
16 217 25-Mar-16 23-Apr-16 30
10 135 9-Apr-16 23-Apr-16 15
505-FAEI-24170 Cables Installation for 04-I1 : Instrument Gas 10 Sch. 50.175 135 100.00% 9-Apr-16 23-Apr-16 15 6 10 10 84.50% 100.00% Delayed
6 82 25-Mar-16 23-Apr-16 30
505-FAEI-24180 Cables Installation for 04-I2 : Utility Gas 6 Sch. 50.175 82 100.00% 9-Apr-16 23-Apr-16 15 3 6 6 82.50% 100.00% Delayed
9 125 1-Apr-16 19-May-16 49
9 125 1-Apr-16 19-May-16 49
505-FAEI-24210 Cables Installation for 11-I1 : Chemical Injection 9 Sch. 50.175 125 100.00% 1-Apr-16 7-Apr-16 7 9 9 9 92.50% 72.40% Ahead
264 3215 14-Dec-15 24-May-16 163
65 776 14-Dec-15 5-Mar-16 83
505-FAEI-24230 Cables Installation for 13-C2 : PLC and Control system 65 Sch. 50.175 776 100.00% 19-Feb-16 5-Mar-16 16 52 65 14 27 85.73% 100.00% Delayed
175 2139 19-Dec-15 24-May-16 158
505-FAEI-24260 Cables Installation for 14-E2 : AC Diesel Generators 1 Sch. 50.175 16 0.75% 11-Mar-16 14-Mar-16 4 1 1 85.00% 100.00% Delayed
505-FAEI-24270 Cables Installation for 14-E3 : DC Supply 36 Sch. 50.175 368 17.20% 19-Feb-16 12-Mar-16 23 23 32 21 20 84.10% 94.29% Delayed
505-FAEI-24280 Cables Installation for 14-E4 : Power & Lighting and Outlet 118 Sch. 50.175 1480 69.19% 19-Dec-15 16-Jan-16 29 118 118 104 99 97.90% 100.00% Delayed
505-FAEI-24300 Cables Installation for 14-E6 : TEG - Gas Platform 9 Sch. 50.175 125 5.84% 19-Mar-16 26-Mar-16 8 9 9 85.00% 100.00% Delayed
505-FAEI-24310 Cables Installation for 16-E1 : Navigation Aids System 11 Sch. 50.175 150 7.01% 25-Dec-15 16-Jan-16 23 11 11 85.00% 93.33% Delayed
13 150 19-Feb-16 18-Apr-16 60
505-FAEI-24320 Cables Installation for 15-T1 : Comunication System 13 Sch. 50.175 150 100.00% 19-Feb-16 18-Apr-16 60 8 6 3 3 70.00% 94.00% Delayed
11 150 30-Jan-16 19-Apr-16 81
505-FAEI-24330 Cables Installation for 17-S2 : Emergency Shutdown 2 Sch. 50.175 27 18.00% 30-Jan-16 6-Feb-16 8 2 2 2 92.50% 72.22% Ahead
505-FAEI-24340 Cables Installation for 17-S3 : Fire & Gas Detector 5 Sch. 50.175 68 45.33% 11-Mar-16 14-Mar-16 4 5 5 5 92.50% 72.79% Ahead
505-FAEI-24350 Cables Installation for 17-S4 : Beacon Light & Siren 4 Sch. 50.175 55 36.67% 8-Apr-16 19-Apr-16 12 4 4 4 92.50% 72.73% Ahead
551 8282 490 540 142 447 -5.72%
L5 L4 L5 L4 L5 L4
253 531 29-Apr-16 30-May-16 32
253 531 29-Apr-16 30-May-16 32
505-FAEI-24360 Cables Continuity Check for 01-I1: Process Production 115 Sch. 50.180 218 41.05% 6-May-16 13-May-16 8 32.87% 96.10% Delayed
505-FAEI-24370 Cables Continuity Check for 01-I2 : Production Header 38 Sch. 50.180 75 14.12% 12-May-16 14-May-16 3 85.26% 100.00% Delayed
505-FAEI-24380 Cables Continuity Check for 02-I1 : Test Separator 64 Sch. 50.180 135 25.42% 21-May-16 25-May-16 5 50.63% 69.63% Delayed
505-FAEI-24420 Cables Continuity Check for 10-I1 : Booster Compressor 36 Sch. 50.180 72 13.56% 27-May-16 30-May-16 4 90.00% 50.00% Ahead
9 13 9-May-16 13-May-16 5
6 9 9-May-16 11-May-16 3
505-FAEI-24430 Cables Continuity Check for 08-I1 : Closed Drain System 6 Sch. 50.180 9 100.00% 9-May-16 11-May-16 3 0.00% 100.00% Delayed & Not Start
3 4 11-May-16 13-May-16 3
505-FAEI-24440 Cables Continuity Check for 09-I1 : Open Drain System 3 Sch. 50.180 4 100.00% 11-May-16 13-May-16 3 0.00% 100.00% Delayed & Not Start
16 24 13-May-16 13-Jun-16 32
10 15 13-May-16 16-May-16 4
505-FAEI-24450 Cables Continuity Check for 04-I1 : Instrument Gas 10 Sch. 50.180 15 100.00% 13-May-16 16-May-16 4 0.00% 100.00% Delayed & Not Start
6 9 16-May-16 13-Jun-16 29
505-FAEI-24460 Cables Continuity Check for 04-I2 : Utility Gas 6 Sch. 50.180 9 100.00% 16-May-16 18-May-16 3 0.00% 61.11% Delayed & Not Start
9 18 24-May-16 11-Jun-16 19
9 18 24-May-16 11-Jun-16 19
505-FAEI-24490 Cables Continuity Check for 11-I1 : Chemical Injection 9 Sch. 50.180 18 100.00% 9-Jun-16 11-Jun-16 3 0.00% 0.00% Should be started
264 409 4-Apr-16 11-Jun-16 69
65 59 14-May-16 23-May-16 10
505-FAEI-24510 Cables Continuity Check for 13-C2 : PLC and Control system 65 Sch. 50.180 59 100.00% 14-May-16 17-May-16 4 0.00% 100.00% Delayed & Not Start
175 254 4-Apr-16 31-May-16 58
505-FAEI-24540 Cables Continuity Check for 14-E2 : AC Diesel Generators 1 Sch. 50.180 3 1.18% 14-May-16 17-May-16 4 0.00% 100.00% Delayed & Not Start
505-FAEI-24550 Cables Continuity Check for 14-E3 : DC Supply 36 Sch. 50.180 26 10.24% 21-May-16 24-May-16 4 0.00% 50.00% Delayed & Not Start
505-FAEI-24560 Cables Continuity Check for 14-E4 : Power & Lighting and Outlet 118 Sch. 50.180 196 77.17% 14-May-16 23-May-16 10 0.00% 100.00% Delayed & Not Start
505-FAEI-24580 Cables Continuity Check for 14-E6 : TEG - Gas Platform 9 Sch. 50.180 13 5.12% 17-May-16 19-May-16 3 0.00% 100.00% Delayed & Not Start
505-FAEI-24590 Cables Continuity Check for 16-E1 : Navigation Aids System 11 Sch. 50.180 16 6.30% 19-May-16 23-May-16 5 0.00% 50.00% Delayed & Not Start
13 74 8-Jun-16 10-Jun-16 3
505-FAEI-24600 Cables Continuity Check for 15-T1 : Comunication System 13 Sch. 50.180 74 100.00% 8-Jun-16 10-Jun-16 3 0.00% 0.00% Should be started
11 22 8-Jun-16 11-Jun-16 4
505-FAEI-24610 Cables Continuity Check for 17-S2 : Emergency Shutdown 2 Sch. 50.180 3 13.64% 8-Jun-16 10-Jun-16 3 0.00% 0.00% Should be started
505-FAEI-24620 Cables Continuity Check for 17-S3 : Fire & Gas Detector 5 Sch. 50.180 12 54.55% 9-Jun-16 11-Jun-16 3 0.00% 0.00% Should be started
505-FAEI-24630 Cables Continuity Check for 17-S4 : Beacon Light & Siren 4 Sch. 50.180 7 31.82% 9-Jun-16 11-Jun-16 3 0.00% 0.00% Should be started
551 995 -47.41%
L5 L4 L5 L4 L5 L4
378 508 12-May-16 15-Jun-16 35
96 112 12-May-16 13-May-16 2
96 112 12-May-16 13-May-16 2
505-FAEI-24640 Tubings Installation for 06-I1 : HP Vent / LP Vent 96 m. 50.175 112 100.00% 12-May-16 13-May-16 2 0.00% 50.00% Delayed & Not Start
189 153 12-May-16 15-Jun-16 35
189 153 12-May-16 15-Jun-16 35
505-FAEI-24650 Tubings Installation for 11-I1 : Chemical Injection 189 m. 50.175 153 100.00% 12-May-16 16-May-16 5 74.76% 100.00% Delayed
93 243 12-May-16 16-May-16 5
84 122 12-May-16 14-May-16 3
505-FAEI-24670 Tubings Installation for 13-C1 : Back Start 84 m. 50.175 122 100.00% 12-May-16 14-May-16 3 54.64% 100.00% Delayed
9 121 13-May-16 16-May-16 4
505-FAEI-24680 Tubings Installation for 14-E6 : TEG - Gas Platform 9 m. 50.175 20 16.53% 13-May-16 13-May-16 1 90.00% 100.00% Delayed
3478 4-May-16 8-Jun-16 36
2913 870 4-May-16 8-Jun-16 36
505-FAEI-24700 Pre-Cutting and Pre-Bending 2913 m. 50.175 870 100.00% 4-May-16 8-Jun-16 36 90.35% 85.34% Ahead Should be finished
2535 2608 12-May-16 7-Jun-16 27
483 227 12-May-16 28-May-16 17
483 227 12-May-16 28-May-16 17
505-FAEI-24720 Tubings Installation for 01-I1: Process Production 456 m. 50.175 195 85.90% 12-May-16 19-May-16 8 75.20% 100.00% Delayed
505-FAEI-24730 Tubings Installation for 10-I1 : Booster Compressor 27 m. 50.175 32 14.10% 21-May-16 28-May-16 8 90.00% 62.50% Ahead
2052 2381 12-May-16 7-Jun-16 27
1273 1529 12-May-16 7-Jun-16 27
505-FAEI-24740 Tubings Installation for 13-C3 : Wellhead Control Panel 1273 m. 50.175 1529 100.00% 12-May-16 7-Jun-16 27 90.00% 82.83% Ahead Should be finished
779 852 12-May-16 28-May-16 17
505-FAEI-24750 Tubings Installation for 17-S1 : Fire Emergency Shutdown (FESD) 531 m. 50.175 579 67.96% 12-May-16 28-May-16 17 49.83% 83.77% Delayed
505-FAEI-24760 Tubings Installation for 17-S2 : Emergency Shutdown 248 m. 50.175 273 32.04% 12-May-16 28-May-16 17 54.44% 83.70% Delayed
2913 3986 -7.92%
L5 L4 L5 L4 L5 L4
344 102 14-May-16 14-Jun-16 32
96 9 9-Jun-16 10-Jun-16 2
96 9 9-Jun-16 10-Jun-16 2
505-FAEI-24770 Tubings Leak Test for 06-I1 : HP Vent / LP Vent 96 m. 50.180 9 100.00% 9-Jun-16 10-Jun-16 2 0.00% 0.00% Should be started
92 50 9-Jun-16 14-Jun-16 6
92 50 9-Jun-16 14-Jun-16 6
505-FAEI-24780 Tubings Leak Test for 11-I1 : Chemical Injection 92 m. 50.180 50 100.00% 9-Jun-16 13-Jun-16 5 0.00% 0.00% Should be started
156 43 14-May-16 18-May-16 5
Sub-System - 7001 : Chemical (C) 100.00% 0.00% 0.00%
System - 8000 : Others 42.16% 0.00% 0.00%
System - 2000 : Drains & Reliefs 8.82% 0.00% 0.00%
Sub-System - 2500 : Blow Down (BD) 100.00% 0.00% 0.00%
System - 7000 : Chemicals 49.02% 0.00% 0.00%
Status
Next 2 Wks
As Per Planed
RemarkL3
Start Finish Dur.
Tested Check Sheet : PLT-T L3 L3
90% 10%
Bare Tube Leak Test 35.92% 0.00% 0.00%
Sub-System - 8000D : Safety Intrergrity System (SIS) 35.78% 51.31% 83.80%
294
150
SUB-TOTAL OF TUBINGS INSTALLATION 16.56% 2342 77.14% 85.06%
381
27
System - 8000 : Others 91.30% 76.15% 83.18%
Sub-System - 8000A : Process Control 64.22% 90.00% 82.83%
1273
Field Installation and Hook-Up 74.99% 76.25% 84.18%
System - 1000 : Process Production 8.70% 77.28% 94.71%
2632
Sub-System - 1001 : Process Liquid & Vapour (P) 100.00% 77.28% 94.71%
Sub-System - 8000B : Electrical Generation and Distribution 49.79% 98.35% 100.00%
9
TPU Jacket Tube Installation 87.26% 79.78% 84.49%
Preparation Works 25.01% 90.35% 85.34%
157
System - 8000 : Others 47.83% 76.41% 100.00%
Sub-System - 8000A : Process Control 50.21% 54.64% 100.00%
51
0.00% 50.00%
System - 7000 : Chemicals 30.12% 74.76% 100.00%
System - 2000 : Drains & Reliefs 22.05%
Sub-System - 7001 : Chemical (C) 100.00% 74.76% 100.00%
Status
Next 2 Wks
As Per Planed
RemarkL3
Start Finish Dur.
Tube Running Check Sheet : PIC-T L3 L3
90% 10%
Bare Tube Installation 12.74% 59.06% 88.98%
77.54%SUB-TOTAL OF CABLES CONTINUITY & INSULATION TEST 4.13% 150 30.13%
TUBINGS LEAK TEST QTY Unit Cost Code
Budgeted
Mhrs
WTG% Baseline Activity Milestones % Actual %Plan
0.00% 50.00%
Sub-System - 2500 : Blow Down (BD) 100.00%
0.00% 0.00%
Sub-System - 8000D : Safety Intrergrity System (SIS) 5.38% 0.00% 0.00%
Sub-System - 8000C : Communication 18.09%
0.00% 91.73%Sub-System - 8000B : Electrical Generation and Distribution 62.10%
0.00% 71.39%
Sub-System - 8000A : Process Control 14.43% 0.00% 100.00%
System - 8000 : Others 41.11%
0.00% 0.00%
Sub-System - 7001 : Chemical (C) 100.00% 0.00% 0.00%
System - 7000 : Chemicals 1.81%
0.00% 61.11%Sub-System - 4500 : Gas Utility (GU) 37.50%
Sub-System - 4400 : Gas Instrument (GI) 62.50% 0.00% 100.00%
36
36
0.00%
System - 4000 : Utility Generals 2.41% 0.00% 85.42%
Sub-System - 2100 : Open Drain (DO) 30.77%
0.00% 100.00%
Sub-System - 2001 : Closed Drain (DC) 69.23% 0.00% 100.00%
RemarkL3
Start Finish Dur.
Tested Check Sheet : PLT-C
Activity Milestones % Actual %Plan
Status
Next 2 Wks
As Per Planed
L3 L3
90% 10%
CABLES CONTINUITY & INSULATION TEST QTY Unit Cost Code
Budgeted
Mhrs
WTG% Baseline
Sub-System - 1001 : Process Liquid & Vapour (P) 100.00% 56.45% 83.90%
System - 1000 : Process Production 53.37% 56.45% 83.90%
36
90.90% 96.62%
2
5
4
SUB-TOTAL OF CABLES INSTALLATION 34.40%
TUBINGS INSTALLATION QTY Unit Cost Code
Budgeted
Mhrs
WTG% Baseline Activity Milestones % Actual %Plan
System - 2000 : Drains & Reliefs 1.31%
42
94.00%
13
Sub-System - 8000D : Safety Intrergrity System (SIS) 4.67% 92.50% 72.33%
9
11
Sub-System - 8000C : Communication 4.67% 70.00%
98.57%
1
36
118
65
Sub-System - 8000B : Electrical Generation and Distribution 66.53% 93.77%
97.50%
Sub-System - 8000A : Process Control 24.14% 85.73% 100.00%
9
System - 8000 : Others 38.82% 90.66%
System - 7000 : Chemicals 1.51% 92.50% 72.40%
Sub-System - 7001 : Chemical (C) 100.00% 92.50% 72.40%
Sub-System - 4500 : Gas Utility (GU) 37.79% 82.50% 100.00%
6
Sub-System - 4400 : Gas Instrument (GI) 62.21% 84.50% 100.00%
10
3
System - 4000 : Utility Generals 2.62% 83.74% 100.00%
6
Sub-System - 2100 : Open Drain (DO) 33.87% 92.50% 100.00%
System - 2000 : Drains & Reliefs 1.50% 92.50% 100.00%
Sub-System - 2001 : Closed Drain (DC) 66.13% 92.50% 100.00%
38
64
36
Sub-System - 1001 : Process Liquid & Vapour (P) 100.00% 91.31% 96.41%
115
45%
System - 1000 : Process Production 55.55% 91.31% 96.41%
Next 2 Wks
As Per Planed
Remark
Start Finish Dur.
Pulled
Activity Milestones
Status
Glanded Terminated
L3 L3
100.00% 100.00%
CABLES INSTALLATION QTY Unit Cost Code
Budgeted
Mhrs
Baseline
5 100.00%
SUB-TOTAL OF CALIBRATION OF INSTRUMENTS TAG 5.37%
100.00% 100.00%
1 100.00%
Sub-System - 8000D : Safety Intrergrity System (SIS) 5.80% 100.00% 100.00%
WTG% % Actual %Plan
L3
3 100.00%
48 100.00%
Sub-System - 8000B : Electrical Generation and Distribution 1.34%
100.00% 100.00%
Sub-System - 8000A : Process Control 92.86% 100.00% 100.00%
21 100.00%
System - 8000 : Others 17.31%
100.00% 100.00%
Sub-System - 7001 : Chemical (C) 100.00% 100.00% 100.00%
System - 7000 : Chemicals 4.56%
100.00% 100.00%
10 100.00%
14 100.00%
Sub-System - 4500 : Gas Utility (GU) 41.18%
100.00% 100.00%
Sub-System - 4400 : Gas Instrument (GI) 58.82% 100.00% 100.00%
1 100.00%
System - 4000 : Utility Generals 5.26%
100.00% 100.00%
5 100.00%
Sub-System - 2500 : Blow Down (BD) 7.89% 100.00% 100.00%
8 100.00%
Sub-System - 2100 : Open Drain (DO) 34.21%
100.00% 100.00%
Sub-System - 2001 : Closed Drain (DC) 57.89% 100.00% 100.00%
26 100.00%
System - 2000 : Drains & Reliefs 2.94%
1 100.00%
193 100.00%
28 100.00%
50 100.00%
100.00%
Sub-System - 1001 : Process Liquid & Vapour (P) 100.00% 100.00% 100.00%
System - 1000 : Process Production 69.94% 421 100.00%
Next 2 Wks
As Per Planed
RemarkL3
Start Finish Dur.
Calibrated
Activity Milestones % Actual %Plan
StatusCheck Sheet : PCC L3 L3
90%
100.00% 100.00%
CALIBRATION OF INSTRUMENTS TAG QTY Unit Cost Code
Budgeted
Mhrs
WTG% Baseline
670 670
109 109
SUB-TOTAL OF E&I SUPPORTS, LADDERS AND TRAYS 35.06%
10%
Installation of E&I Trays&Ladders 31.13% 100.00% 100.00%
Upper Deck
282 282
97 97
Mezzanine Deck
37 37
213 213
Cellar Deck
481 481
186 186
Sub-Cellar Deck
1 1
30 30
100.00% 100.00%
Installation of E&I Supports 68.87% 100.00% 100.00%
379 379
Installation 55.90%
31 31
667 667
250 250
L3
90% 10%
Fabrication 44.10% 100.00% 100.00%
CHEVRON : CVX-PHASE 50
PROGRESS MEASUREMENT WORK SHEET FOR E&I AND PRE-COMMISSIONING WORKS
WHP 50/5 : GAS PLATFORM
WHP 50/5 : GAS PLATFORM : E&I INSTALLATION
E&I SUPPORTS, LADDERS AND TRAYS QTY Unit Cost Code
Budgeted
Mhrs
%Plan
Status
Next 2 Wks
As Per Planed
RemarkL3
Start Finish Dur.
WTG% Baseline Activity Milestones % Actual
Fabricated/Installed Accepted /Painted/Cleaning L3
551
Page 9 of 10 Prepared By : Nattakarn S.
Activity ID Activity Name Num. Budgeted Units Planned Start Planned Finish % Actual 1-Jun-16
CHEVRON : CVX-PHASE 50
PROGRESS MEASUREMENT WORK SHEET FOR E&I AND PRE-COMMISSIONING WORKS
WHP 50/5 : GAS PLATFORM
84 21 14-May-16 18-May-16 5
505-FAEI-24800 Tubings Leak Test for 13-C1 : Back Start 84 m. 50.180 21 100.00% 14-May-16 18-May-16 5 0.00% 0.00%
72 22 17-May-16 18-May-16 2
505-FAEI-24810 Tubings Leak Test for 14-E6 : TEG - Gas Platform 12 m. 50.180 11 50.00% 17-May-16 18-May-16 2 0.00% 0.00%
505-FAEI-24820 Tubings Leak Test for 14-E7 : CO2 Skid - Option Gas Platform 60 m. 50.180 11 50.00% 17-May-16 18-May-16 2 0.00% 0.00%
2535 182 14-May-16 21-May-16 8
483 56 17-May-16 21-May-16 5
483 56 17-May-16 21-May-16 5
505-FAEI-24830 Tubings Leak Test for 01-I1: Process Production 456 m. 50.180 45 80.36% 17-May-16 19-May-16 3 0.00% 0.00%
505-FAEI-24840 Tubings Leak Test for Booster Compressor 27 m. 50.180 11 19.64% 21-May-16 21-May-16 1 0.00% 0.00%
2052 126 14-May-16 18-May-16 5
1273 90 14-May-16 18-May-16 5
505-FAEI-24850 Tubings Leak Test for 13-C3 : Wellhead Control Panel 1273 m. 50.180 90 100.00% 14-May-16 18-May-16 5 0.00% 0.00%
779 36 17-May-16 18-May-16 2
505-FAEI-24860 Tubings Leak Test for 17-S1 : Fire Emergency Shutdown (FESD) 531 m. 50.180 18 50.00% 17-May-16 18-May-16 2 0.00% 0.00%
505-FAEI-24870 Tubings Leak Test for 17-S2 : Emergency Shutdown 248 m. 50.180 18 50.00% 17-May-16 18-May-16 2 0.00% 0.00%
2879 284 0.00%
L5 L4 L5 L4 L5 L4
271 363 11-May-16 14-Jun-16 35
271 363 11-May-16 14-Jun-16 35
505-FAEI-24880 Hook-Up of E&I Tags for 01-I1: Process Production 145 Ea. 50.175 148 40.77% 11-May-16 7-Jun-16 28 30.21% 62.84% Delayed Should be finished
505-FAEI-24890 Hook-Up of E&I Tags for 01-I2 : Production Header 28 Ea. 50.175 43 11.85% 14-May-16 10-Jun-16 28 55.71% 76.74% Delayed Should be finished
505-FAEI-24900 Hook-Up of E&I Tags for 02-I1 : Test Separator 52 Ea. 50.175 75 20.66% 21-May-16 8-Jun-16 19 55.38% 71.33% Delayed Should be finished
505-FAEI-24910 Hook-Up of E&I Tags for 03-I1 : Pig Luncher 1 Ea. 50.175 1 0.28% 7-Jun-16 8-Jun-16 2 0.00% 0.00% Should be started
505-FAEI-24920 Hook-Up of E&I Tags for 03-I2 : Pig Receiver - Option 18 Ea. 50.175 55 15.15% 7-Jun-16 14-Jun-16 8 0.00% 0.00% Should be started
505-FAEI-24950 Hook-Up of E&I Tags for 10-I1 : Booster Compressor 27 Ea. 50.175 41 11.29% 28-May-16 14-Jun-16 18 55.56% 57.32% Delayed Should be finished
15 22 11-May-16 15-Jun-16 36
9 13 11-May-16 18-May-16 8
505-FAEI-24960 Hook-Up of E&I Tags for 08-I1 : Closed Drain System 9 Ea. 50.175 13 100.00% 11-May-16 18-May-16 8 33.33% 61.54% Delayed
5 8 21-May-16 25-May-16 5
505-FAEI-24970 Hook-Up of E&I Tags for 09-I1 : Open Drain System 5 Ea. 50.175 8 100.00% 21-May-16 25-May-16 5 48.00% 50.00% Delayed
1 1 14-Jun-16 15-Jun-16 2
505-FAEI-24980 Hook-Up of E&I Tags for 06-I1 : HP Vent / LP Vent 1 Ea. 50.175 1 100.00% 14-Jun-16 15-Jun-16 2 0.00% 0.00% Should be started
28 41 7-Apr-16 21-Jun-16 76
17 23 7-Apr-16 19-Apr-16 13
505-FAEI-24990 Hook-Up of E&I Tags for 04-I1 : Instrument Gas 17 Ea. 50.175 23 100.00% 7-Apr-16 19-Apr-16 13 42.35% 69.57% Delayed
11 18 9-Apr-16 21-Jun-16 74
505-FAEI-25000 Hook-Up of E&I Tags for 04-I2 : Utility Gas 11 Ea. 50.175 18 100.00% 9-Apr-16 21-Apr-16 13 43.64% 66.67% Delayed
24 35 26-May-16 14-Jun-16 20
24 35 26-May-16 14-Jun-16 20
505-FAEI-25030 Hook-Up of E&I Tags for 11-I1 : Chemical Injection 24 Ea. 50.175 35 100.00% 26-May-16 13-Jun-16 19 90.00% 35.71% Ahead Should be finished
231 332 29-Feb-16 9-Jun-16 102
67 226 31-Mar-16 7-Jun-16 69
505-FAEI-25050 Hook-Up of E&I Tags for 13-C1 : Back Start 4 Ea. 50.175 7 3.10% 31-Mar-16 5-Apr-16 6 90.00% 78.57% Ahead
505-FAEI-25060 Hook-Up of E&I Tags for 13-C2 : PLC and Control system 14 Ea. 50.175 22 9.73% 21-May-16 3-Jun-16 14 62.14% 79.55% Delayed Should be finished
505-FAEI-25070 Hook-Up of E&I Tags for 13-C3 : Wellhead Control Panel 49 Ea. 50.175 197 87.17% 21-May-16 7-Jun-16 18 60.00% 79.95% Delayed Should be finished
133 60 29-Feb-16 9-Jun-16 102
505-FAEI-25090 Hook-Up of E&I Tags for 14-E2 : AC Diesel Generators 1 Ea. 50.175 1 1.67% 22-Apr-16 30-Apr-16 9 60.00% 100.00% Delayed
505-FAEI-25100 Hook-Up of E&I Tags for 14-E3 : DC Supply 8 Ea. 50.175 10 16.67% 25-Mar-16 2-Apr-16 9 56.25% 70.00% Delayed
505-FAEI-25110 Hook-Up of E&I Tags for 14-E4 : Power & Lighting and Outlet 110 Ea. 50.175 28 46.67% 29-Feb-16 5-Apr-16 37 60.27% 82.14% Delayed
505-FAEI-25130 Hook-Up of E&I Tags for 14-E6 : TEG - Gas Platform 5 Ea. 50.175 8 13.33% 6-May-16 14-May-16 9 60.00% 75.00% Delayed
505-FAEI-25140 Hook-Up of E&I Tags for 16-E1 : Navigation Aids System 9 Ea. 50.175 13 21.67% 2-Apr-16 12-Apr-16 11 60.00% 76.92% Delayed
5 7 12-Apr-16 23-Apr-16 12
505-FAEI-25150 Hook-Up of E&I Tags for 15-T1 : Comunication System 5 Ea. 50.175 7 100.00% 12-Apr-16 23-Apr-16 12 60.00% 57.14% Ahead
26 39 25-Apr-16 17-May-16 23
505-FAEI-25160 Hook-Up of E&I Tags for 17-S2 : Emergency Shutdown 10 Ea. 50.175 13 33.33% 6-May-16 17-May-16 12 60.00% 100.00% Delayed
505-FAEI-25170 Hook-Up of E&I Tags for 17-S3 : Fire & Gas Detector 5 Ea. 50.175 8 20.51% 25-Apr-16 30-Apr-16 6 60.00% 62.50% Delayed
505-FAEI-25180 Hook-Up of E&I Tags for 17-S4 : Beacon Light & Siren 11 Ea. 50.175 18 46.15% 25-Apr-16 28-Apr-16 4 60.00% 61.11% Delayed
569 793 -14.03%
24076 -6.41%
L5 L4 L5 L4 L5 L4
704 21-Jun-16 25-Jun-16 5
84 704 21-Jun-16 25-Jun-16 5
84 704 21-Jun-16 25-Jun-16 5
505-FAPC-22150 Fuction Test of 14-E2 : AC Diesel Generators 10 Pac. 60.220 71 10.09% 21-Jun-16 22-Jun-16 2 0.00% 0.00%
505-FAPC-22160 Fuction Test of 14-E3 : DC Supply 21 Pac. 60.220 174 24.72% 23-Jun-16 24-Jun-16 2 0.00% 0.00%
505-FAPC-22170 Fuction Test of 14-E4 : Power & Lighting and Outlet 39 Pac. 60.220 322 45.74% 21-Jun-16 22-Jun-16 2 0.00% 0.00%
505-FAPC-22190 Fuction Test of 14-E6 : TEG - Gas Platform 6 Pac. 60.220 21 2.98% 25-Jun-16 25-Jun-16 1 0.00% 0.00%
505-FAPC-22200 Fuction Test of 16-E1 : Navigation Aids System 8 Pac. 60.220 116 16.48% 23-Jun-16 24-Jun-16 2 0.00% 0.00%
1241 22-Jun-16 25-Jun-16 4
237 823 22-Jun-16 25-Jun-16 4
237 823 22-Jun-16 25-Jun-16 4
505-FAPC-22220 Loop Test of 01-I1: Process Production 98 Pac. 60.225 340 41.31% 22-Jun-16 23-Jun-16 2 0.00% 0.00%
505-FAPC-22230 Loop Test of 01-I2 : Production Header 27 Pac. 60.225 94 11.42% 23-Jun-16 23-Jun-16 1 0.00% 0.00%
505-FAPC-22240 Loop Test of 02-I1 : Test Separator 55 Pac. 60.225 191 23.21% 24-Jun-16 25-Jun-16 2 0.00% 0.00%
505-FAPC-22250 Loop Test of 03-I2 : Pig Receiver - Option 12 Pac. 60.225 42 5.10% 24-Jun-16 24-Jun-16 1 0.00% 0.00%
505-FAPC-22280 Loop Test of 10-I1 : Booster Compressor 45 Pac. 60.225 156 18.96% 24-Jun-16 24-Jun-16 1 0.00% 0.00%
9 32 25-Jun-16 25-Jun-16 1
6 21 25-Jun-16 25-Jun-16 1
505-FAPC-22290 Loop Test of 08-I1 : Closed Drain System 6 Pac. 60.225 21 100.00% 25-Jun-16 25-Jun-16 1 0.00% 0.00%
3 11 25-Jun-16 25-Jun-16 1
505-FAPC-22300 Loop Test of 09-I1 : Open Drain System 3 Pac. 60.225 11 100.00% 25-Jun-16 25-Jun-16 1 0.00% 0.00%
13 32 25-Jun-16 25-Jun-16 1
9 21 25-Jun-16 25-Jun-16 1
505-FAPC-22310 Loop Test of 04-I1 : Instrument Gas 9 Pac. 60.225 21 100.00% 25-Jun-16 25-Jun-16 1 0.00% 0.00%
4 11 25-Jun-16 25-Jun-16 1
505-FAPC-22320 Loop Test of 04-I2 : Utility Gas 4 Pac. 60.225 11 100.00% 25-Jun-16 25-Jun-16 1 0.00% 0.00%
12 32 25-Jun-16 25-Jun-16 1
12 32 25-Jun-16 25-Jun-16 1
505-FAPC-22350 Loop Test of 11-I1 : Chemical Injection 12 Pac. 60.225 32 100.00% 25-Jun-16 25-Jun-16 1 0.00% 0.00%
49 322 23-Jun-16 25-Jun-16 3
30 187 23-Jun-16 24-Jun-16 2
505-FAPC-22370 Loop Test of 13-C3 : Wellhead Control Panel 30 Pac. 60.225 187 100.00% 23-Jun-16 24-Jun-16 2 0.00% 0.00%
1 4 23-Jun-16 23-Jun-16 1
505-FAPC-22380 Loop Test of 15-T1 : Comunication System 1 Pac. 60.225 4 100.00% 23-Jun-16 23-Jun-16 1 0.00% 0.00%
18 131 24-Jun-16 25-Jun-16 2
505-FAPC-22390 Loop Test of 17-S2 : Emergency Shutdown 3 Pac. 60.225 12 9.16% 24-Jun-16 24-Jun-16 1 0.00% 0.00%
505-FAPC-22400 Loop Test of 17-S3 : Fire & Gas Detector 8 Pac. 60.225 28 21.37% 25-Jun-16 25-Jun-16 1 0.00% 0.00%
505-FAPC-22410 Loop Test of 17-S4 : Beacon Light & Siren 7 Pac. 60.225 91 69.47% 25-Jun-16 25-Jun-16 1 0.00% 0.00%
404 1945 0.00%
L5 L4 L5 L4 L5 L4
505-FAPC-22420 Platform Site Acceptance Test - SAT 100 Pac. 60.235 555 27-Jun-16 2-Jul-16 6
100 555 0.00%
2500 0.00%
-5.81%
SUB-TOTAL OF TUBINGS LEAK TEST 1.18% 0.00% 0.00%
Sub-System - 8000A : Process Control 71.43% 0.00% 0.00%
Sub-System - 8000D : Safety Intrergrity System (SIS) 28.57% 0.00% 0.00%
0.00%
Sub-System - 1001 : Process Liquid & Vapour (P) 100.00% 0.00% 0.00%
System - 8000 : Others 69.23% 0.00% 0.00%
System - 1000 : Process Production 30.77% 0.00%
Sub-System - 8000B : Electrical Generation and Distribution 51.16% 0.00% 0.00%
TPU Jacket Tube Leak Test 64.08% 0.00% 0.00%
Sub-System - 8000A : Process Control 48.84% 0.00% 0.00%
79.13% 84.94%OVERALL PROGRESS OF WHP 50/5 : GAS PLATFORM 26576 100.00%
0.00%
TOTAL OF WHP 50/5 : GAS PLATFORM : E&I PRE-COMMISSIONING 9.41% 0.00% 0.00%
100.00% 0.00% 0.00%
SUB-TOTAL OF SITE ACCEPTANC TEST - SAT 22.20% 0.00%
RemarkL3
Start Finish Dur.
Activity Milestones % Actual %Plan
Status
Next 2 Wks
As Per Planed
SAT Completion L3 L3
100%
0.00%
SITE ACCEPTANC TEST - SAT QTY Unit Cost Code
Budgeted
Mhrs
WTG% Baseline
SUB-TOTAL OF LOOP/ FUNCTION TEST 77.80% 0.00%
0.00% 0.00%
Sub-System - 8000D : Safety Intrergrity System (SIS) 40.68% 0.00% 0.00%
Sub-System - 8000C : Communication 1.24%
0.00% 0.00%
Sub-System - 8000A : Process Control 58.07% 0.00% 0.00%
System - 8000 : Others 25.95%
0.00% 0.00%
Sub-System - 7001 : Chemical (C) 100.00% 0.00% 0.00%
System - 7000 : Chemicals 2.58%
0.00% 0.00%Sub-System - 4500 : Gas Utility (GU) 34.38%
Sub-System - 4400 : Gas Instrument (GI) 65.63% 0.00% 0.00%
0.00% 0.00%
System - 4000 : Utility Generals 2.58% 0.00% 0.00%
Sub-System - 2100 : Open Drain (DO) 34.38%
0.00% 0.00%
Sub-System - 2001 : Closed Drain (DC) 65.63% 0.00% 0.00%
System - 2000 : Drains & Reliefs 2.58%
Sub-System - 1001 : Process Liquid & Vapour (P) 100.00% 0.00% 0.00%
0.00% 0.00%
System - 1000 : Process Production 66.32% 0.00% 0.00%
Instrumentation 63.80%
Sub-System - 8000B : Electrical Generation and Distribution 100.00% 0.00% 0.00%
System - 8000 : Others 100.00% 0.00% 0.00%
Electrical 36.20% 0.00% 0.00%
%Plan
Status
Next 2 Wks
As Per Planed
RemarkL3
Start Finish Dur.
WTG% Baseline Activity Milestones % Actual
Tested Check Sheet : PLT-L & PFT
WHP 50/5 : GAS PLATFORM : E&I PRE-COMMISSIONING
LOOP/ FUNCTION TEST QTY Unit Cost Code
Budgeted
Mhrs
TOTAL OF WHP 50/5 : GAS PLATFORM : E&I INSTALLATION 90.59% 87.35% 93.76%
L3 L3
90% 10%
63.43%SUB-TOTAL OF HOOK-UP OF E&I TAG ITEMS 3.29% 49.40%
11
Sub-System - 8000B : Electrical Generation and Distribution 18.07% 59.50% 78.33%
1
7 1
60.00% 57.14%
Sub-System - 8000D : Safety Intrergrity System (SIS) 11.75% 60.00% 41.03%
Sub-System - 8000C : Communication 2.11%
110 1
5
9
60.68% 74.85%
Sub-System - 8000A : Process Control 68.07% 61.14% 80.09%
System - 8000 : Others 41.87%
90.00% 35.71%
Sub-System - 7001 : Chemical (C) 100.00% 90.00% 35.71%
24 24
43.64% 66.67%Sub-System - 4500 : Gas Utility (GU) 43.90%
42.92% 68.29%
Sub-System - 4400 : Gas Instrument (GI) 56.10% 42.35% 69.57%
8
System - 7000 : Chemicals 4.41%
System - 4000 : Utility Generals 5.17%
48.00% 50.00%
Sub-System - 2500 : Blow Down (BD) 4.55% 0.00% 0.00%
Sub-System - 2100 : Open Drain (DO) 36.36%
5
4
37.15% 54.55%
Sub-System - 2001 : Closed Drain (DC) 59.09% 33.33% 61.54%
System - 2000 : Drains & Reliefs 2.77%
25
55.92%
Sub-System - 1001 : Process Liquid & Vapour (P) 100.00% 36.63% 55.92%
System - 1000 : Process Production 45.78% 36.63%
HOOK-UP OF E&I TAG ITEMS QTY Unit Cost Code
Budgeted
Mhrs
455 31
Next 2 Wks
As Per Planed
RemarkL3
Start Finish Dur.
Activity Milestones % Actual %Plan
StatusL3 L3
WTG% Baseline
Installed Hook-Up Check Sheet : PIC-H
60% 30% 10%
26
48
73
4 4
10
5
14 1
49
5
12
Page 10 of 10 Prepared By : Nattakarn S.

WORKING PORTFOLIO - 01

  • 1.
    PROGRESS REPORT THE EXAMPLEOF WORKING PORTFOLIO - 01 RESPONSIBILITIES; E&I INSTALLATION AND PRE-COMMISSIONING. SUB-STRUCTURAL FABRICATION – JACKET AND PILE. SUB-SEA PIPELINE FABRICATION. KEY DOCUMENTS; DASHBOARD WPR, SUMARY STATUS AND KEY-DATES. S-CURVE. PROGRESS MEASUREMENT AND MONITORING.
  • 2.
    E&I AND PRE-COMMISSIONINGDASHBOARD Project Completion Task Status Pre-Com and SAT Countdown PF DAY PF DAY Plan & Actual Deviation INCOMING PRE-COM SAT CONTRACT CVX-501 17-May-16A 30-May-16A 30-Jul-16 CVX-503 25-May-16A 6-Jun-16 13-Aug-16 CVX-504 28-May-16A 13-Jun-16 20-Aug-16 CVX-502 13-Jun-16 20-Jun-16 6-Aug-16 CVX-505 20-Jun-16 27-Jun-16 27-Aug-16 CVX-511 14-Nov-16 28-Nov-16 19-Feb-17 CVX-512 28-Nov-16 13-Dec-16 26-Feb-17 CVX-513 12-Dec-16 9-Jan-17 5-Mar-17 Cost and Budgets - Mhrs. Productivity Trend Highlight and Concerns ● Sub-contractor is under catching up the work progress. To hand-over the installation package prior to PF Pre-commissioning and SAT commencement. 112,100 42,629 61,371 33,590 103,870 10,005 *This productivity report DOES NOT included "MSL actual mhrs." 01-Jun-16 PRE-COM. SAT. 502 12 503 5 20.79% 88.15% PHASE 51 PHASE 50 38% 12% 50% 4% 76% 20% Late Task On-Time/ Early Task Completed Task4.37% -4.31% -10.00% -5.00% 0.00% 5.00% 10.00% PHASE 50 PHASE 51 0.00 1.00 2.00 PHASE 50 PHASE 51 PHASE 50 PHASE 51 KPI PHASE 50 PHASE 51 Earned Mhrs. Actual - CUEL Actual - MSL Prepared By: Nattakarn S. Construction Planning Dept.
  • 3.
    · This summaryprogress status is based on Phase 50 's Project Plan Rev.2 - Accelerate Plan. · Overall actual progress of E&I and Pre-Commissioning works is 88.15% against overall planed 92.46%, variance is -4.31% (The last cut off, progress deviation is -4.58%). · Highlight and Concern - Delayed of cables continuity check, tubing leak test and hook-up of field equipment. Potential to delay project completion. · Continue submission of check sheet/IRV for all of activities which had been physical completed. · Continue cables glanding and termination for CVX-505. · Continue cable continuity check for CVX-502 to 505. · Continue field installation of TPU JK tube for CVX-502, 504 and 505. · Completed tube leak testing for CVX-503. · Continue installation and hook-up of E&I tag item for CVX-501 to 505. · Completed E&I loop and function test for CVX-501. · Commenced E&I loop and function test for CVX-503 and 504. · Commenced platform SAT for CVX-501. · To catch up work progress which has been mention as a delayed/concerned activitie. · All works to completed and align with the accelerate LO dates refer to ITC-620272/2809/PH50 : 6-May-16. · Float = Accelerate Load-Out Dates - Forecast Fabrication completion Dates. · This productivity report "does not includes" man-hours from onsite sub-contractors and all offsite sub-contractors. Attachment : 1 Pre-Commissioning and SAT Timeline Attachment : 2 Summary Progress Status by Platform Attachment : 3 Site Narative Report - NA Prepared by: Nattakarn Sooksa-nguan Construction Planner G ATTACHMENT 14 16 20-Jun-16 13-Jun-16 25-Jun-16 18-Jun-163 CVX-502 CVX-504 CVX-505 F E Finish Start Finish 166-Jun-16 4-Jun-16 11-Jun-16 30-May-16A 18-Jun-16 11-Jun-16 A SUMMARY PROGRESS STATUS No. % Cum. Last Week % Achieved in Week % Cum. Up to Date Plan Actual Var Plan Actual Plan Actual Var WTGBudget Mhrs Platforms Name Type Var 2.14 2.58 0.44 88.80 5.20 85.71 1.84 87.303 2 Gas 1.14 1.06 -0.08 7.27 4.38 -2.90 90.57 -3.104 86.66 83.12 -3.5426,576 20.00% WEEKLY PROGRESS REPORT PHASE 50 : E&I AND PRE-COMMISSIONING WORKS Cut off Date 01-Jun-16 Cut off Time 1700H No. of Pages 4 1 98.16 92.32 -5.8426,576 20.00%CVX-501 Gas -3.27 91.41 -6.58 CVX-502 Gas 3.05 100.00 97.21 -2.794.89 89.43 86.24 -3.1926,576 20.00%CVX-504 Gas 97.9990.72 87.03 -3.6926,576 20.00%CVX-503 -5.815 79.74 73.08 -6.6626,576 20.00%CVX-505 Gas 6.06 0.85 84.94 79.13 OTHER CONCERN Item Remarks/ StatusAction by TargetDescription / Action Required 1 Sub-contractor to expedite their works progress to ensure that all related work must be done prior to platform pre-commissioning commencement. MSL Continuous Under catching up work progress. 88.94 84.36 -4.58 3.52 3.79 0.27 92.46 88.15 Fab. Priority Start 132,880 100.00%Overall Progress B FABRICATION ACTIVITIES : DONE IN WEEK C FABRICATION ACTIVITIES : PLANED IN NEXT WEEKS D KEY DATES Float Contractual Sail-Away Platform Name Pre-Commissioning 5,725 0.77 -4.31 Load-Out 22-Jun-16 27-Jun-16 9-Jul-16 26-Jun-16 4-Jul-16 18-Jul-16 30-Jul-16 1-Jul-16 13-Jul-16 8-Jul-16 22-Jul-16 13-Aug-16 6-Aug-16 20-Aug-16 27-Aug-16 ITC-620272/2809 - Accelerate Remark 0.55 27-Jun-16 PRODUCTIVITY : KPI 29-May-16A 4-Jun-16 CVX-501 CVX-503 2-Jul-16 18 16 2 4 1 17-May-16A 25-May-16A 13-Jun-16 28-May-16A 20-Jun-16 25-Jun-16 Site Acceptance Test 10091.91.03.60.225 Pre-Comm. Instrument 6,205 237 0 0.00 10091.91.03.50.180 Check and Test 6,265 3,268 29 0.01 Pre-Commissioning and SAT 12,500 852 359 0.42 5 10091.91.03.60.220 Pre-Comm. Electrical 3,520 615 10091.91.03.50.165 Calibration 10091.91.03.50.170 Support 40,945 40,881 359 0.58 0.70 E&I Installation 120,380 111,248 61,012 6,340 6,340 4,442 10091.91.03.50.160 Rigging, Scaffolding and Transportation 8,055 7,390 42,740 1.05 10091.91.03.50.175 Installation 8,076 0.1558,775 53,369 Cost Code Work Detail Budgeted Labor Units - Mhrs Productivity As of Date : 25-May-16 RemarksAccumulative Earned Mhrs Accumulative Actual Mhrs Productivity (Target < 1.00) 10091.91.03.60.235 SAT - Site Acceptance Test 2,775 0 61,371 0.55Overall 132,880 112,100 0 - Page 1 of 1 Prepared By : Nattakarn S.
  • 4.
    11-Apr-16 18-Apr-16 25-Apr-1602-May-16 09-May-16 16-May-16 23-May-16 30-May-16 06-Jun-16 13-Jun-16 20-Jun-16 27-Jun-16 04-Jul-16 11-Jul-16 18-Jul-16 25-Jul-16 01-Aug-16 08-Aug-16 15-Aug-16 22-Aug-16 29-Aug-16 05-Sep-16 12-Sep-16 Pre-Com 501 SAT 501 Potential L/O Current L/O Rev.21 Pre-Com 503 SAT 503 Potential L/O Current L/O Rev.21 Pre-Com 504 SAT 504 Potential L/O Current L/O Rev.21 Pre-Com 502 SAT 502 Potential L/O Current L/O Rev.21 Pre-Com 505 SAT 505 Potential L/O Current L/O Rev.21 1 CVX-501 30-Apr-16 12-May-16 2-Jun-16 28-Apr-16 7-May-16 13-May-16 23-Jun-16 1-Jul-16 -9 4 17-May-16A 29-May-16A 30-May-16A 4-Jun-16 18 31 30-Jul-16 5-Jul-16 9-Jul-16 22-Jun-16 26-Jun-16 2 CVX-503 17-May-16 27-May-16 16-Jun-16 7-May-16 13-May-16 21-May-16 7-Jul-16 15-Jul-16 -18 -4 25-May-16A 4-Jun-16 6-Jun-16 11-Jun-16 16 30 13-Aug-16 11-Jul-16 15-Jul-16 27-Jun-16 1-Jul-16 3 CVX-504 25-May-16 4-Jun-16 23-Jun-16 14-May-16 21-May-16 27-May-16 14-Jul-16 23-Jul-16 -19 -7 28-May-16A 11-Jun-16 13-Jun-16 18-Jun-16 16 28 20-Aug-16 16-Jul-16 20-Jul-16 4-Jul-16 8-Jul-16 4 CVX-502 10-May-16 19-May-16 9-Jun-16 21-May-16 27-May-16 3-Jun-16 30-Jun-16 8-Jul-16 1 13 13-Jun-16 18-Jun-16 20-Jun-16 25-Jun-16 14 26 6-Aug-16 21-Jul-16 25-Jul-16 9-Jul-16 13-Jul-16 5 CVX-505 2-Jun-16 11-Jun-16 4-Jul-16 28-May-16 3-Jun-16 10-Jun-16 28-Jul-16 5-Aug-16 -18 -7 20-Jun-16 25-Jun-16 27-Jun-16 2-Jul-16 16 27 27-Aug-16 29-Jul-16 2-Aug-16 18-Jul-16 22-Jul-16 Note 1. Float (1) = Accelerate Load-Out Dates - SAT Completion Date. 2. Float (2) = Current Load-Out Dates - SAT Completion Date. Sail-Away Start Finish Start Finish Float(2) SAT Float(1) Load-Out Sail-Away Load-Out Sequence Platform Name PIPING WORKS E&I AND PRE-COMMISSIONING Contractual Completion Installation Completion Hydro-Test Completion Service Test Completion Installation Completion Hydro-Test Completion Service Test Completion Pre-Com. Completion SAT Completion Float(1) Float(2) Pre-Com. LOAD-OUT AND SAIL-AWAY SCHEDULE Piping Key Dates: Baseline Rev.0 Piping Key Dates: Committed Dates E&I and Pre-Com Key Dates: Baseline Rev.0 E&I And Pre-Com Key Dates: Rev.5_Accelerate Current Revision - Rev.21 ITC-620272/2809 - Accelerate YEAR 2016 CVX-PHASE 50 : PLATFORM PRE-COMMISSIONING & SAT TIMELINE ACCELERATE PLAN - ITC-620272/2809/PH50 REVISION Rev.5_Accelerate ISSUED DATE 04-May-16 1-Jun-16 501 - Piping Service Test Completion 503 - Piping Service Test Completion 504 - Piping Service Test Completion 502 - Piping Service Test Completion 505 - Piping Service Test Completion E&I Hook-Up Completion E&I Hook-Up Completion E&I Hook-Up Completion E&I Hook-Up Completion E&I Hook-Up Completion Punch-list, touch-up and wash down Punch-list, touch-up and wash down Punch-list, touch-up and wash down Punch-list, touch-up and wash down Punch-list, touch-up and wash down Page 1 of 1 Prepared By : Nattakarn S.
  • 5.
    1-Jun-16 Budgeted Units %Actual Plan Actual Var. Plan Actual Var. Plan Actual Var. CVX-501 26576 20.00% 98.16 92.32 -5.84 1.84 4.89 3.05 100.00 97.21 -2.79 CVX-502 26576 20.00% 86.66 83.12 -3.54 2.14 2.58 0.44 88.80 85.71 -3.10 CVX-503 26576 20.00% 90.72 87.03 -3.69 7.27 4.38 -2.90 97.99 91.41 -6.58 CVX-504 26576 20.00% 89.43 86.24 -3.19 1.14 1.06 -0.08 90.57 87.30 -3.27 CVX-505 26576 20.00% 79.74 73.08 -6.66 5.20 6.06 0.85 84.94 79.13 -5.81 Overall 132880 100.00% 88.94 84.36 -4.58 3.52 3.79 0.27 92.46 88.15 -4.31 Budgeted Units % Plan-Wk % Actual -Wk % Actual Plan Actual Var. Plan Actual Var. Plan Actual Var. E&I Installation 24076 90.59% 100.00 98.37 -1.63 0.00 0.50 0.50 100.00 98.88 -1.12 Calibration of Instruments Tag 1294 5.37% 100.00 100.00 0.00 0.00 0.00 0.00 100.00 100.00 0.00 E&I Supports, Ladders and Trays 8442 35.06% 100.00 100.00 0.00 0.00 0.00 0.00 100.00 100.00 0.00 Fabrication of E&I Supports 3723 44.10% 100.00 100.00 0.00 0.00 0.00 0.00 100.00 100.00 0.00 Installation of E&I SupportS 3250 38.50% 100.00 100.00 0.00 0.00 0.00 0.00 100.00 100.00 0.00 Installation of E&I Trays and Ladders 1469 17.40% 100.00 100.00 0.00 0.00 0.00 0.00 100.00 100.00 0.00 Cables Installation 8282 34.40% 100.00 99.93 -0.07 0.00 0.00 0.00 100.00 99.93 -0.07 Tubings Installation 3986 16.56% 100.00 94.49 -5.51 0.00 1.35 1.35 100.00 95.84 -4.16 Hook-Up of E&I Tag Items 793 3.29% 100.00 91.75 -8.25 0.00 6.64 6.64 100.00 98.38 -1.62 Cable Continuity Check 995 4.13% 100.00 92.58 -7.42 0.00 0.00 0.00 100.00 92.58 -7.42 Tubing Leak Test 284 1.18% 100.00 90.39 -9.61 0.00 5.36 5.36 100.00 95.75 -4.25 E&I Pre-Commissioning 2500 9.41% 80.46 34.05 -46.41 19.54 47.07 27.53 100.00 81.12 -18.88 Loop/Function Test 1945 77.80% 100.00 43.76 -56.24 0.00 46.24 46.24 100.00 90.00 -10.00 Site Acceptance Test - SAT 555 22.20% 0.00 0.00 0.00 100.00 50.00 -50.00 100.00 50.00 -50.00 Total 26576 100.00% 98.16 92.32 -5.84 1.84 4.89 3.05 100.00 97.21 -2.79 Budgeted Units % Plan-Wk % Actual -Wk % Plan % Actual Plan Actual Var. Plan Actual Var. Plan Actual Var. E&I Installation 24076 90.59% 100.00 96.07 -3.93 0.00 1.72 1.72 100.00 97.79 -2.21 Calibration of Instruments Tag 1294 5.37% 100.00 100.00 0.00 0.00 0.00 0.00 100.00 100.00 0.00 E&I Supports, Ladders and Trays 8442 35.06% 100.00 100.00 0.00 0.00 0.00 0.00 100.00 100.00 0.00 Fabrication of E&I Supports 3723 44.10% 100.00 100.00 0.00 0.00 0.00 0.00 100.00 100.00 0.00 Installation of E&I SupportS 3250 38.50% 100.00 100.00 0.00 0.00 0.00 0.00 100.00 100.00 0.00 Installation of E&I Trays and Ladders 1469 17.40% 100.00 100.00 0.00 0.00 0.00 0.00 100.00 100.00 0.00 Cables Installation 8282 34.40% 100.00 99.58 -0.42 0.00 0.00 0.00 100.00 99.58 -0.42 Tubings Installation 3986 16.56% 100.00 92.81 -7.19 0.00 2.48 2.48 100.00 95.29 -4.71 Hook-Up of E&I Tag Items 793 3.29% 100.00 73.80 -26.20 0.00 5.69 5.69 100.00 79.49 -20.51 Cable Continuity Check 995 4.13% 100.00 86.63 -13.37 0.00 1.09 1.09 100.00 87.72 -12.28 Tubing Leak Test 284 1.18% 100.00 0.00 -100.00 0.00 91.12 91.12 100.00 91.12 -8.88 E&I Pre-Commissioning 2500 9.41% 0.00 0.00 0.00 78.66 29.98 -48.68 78.66 29.98 -48.68 Loop/Function Test 1945 77.80% 0.00 0.00 0.00 100.00 38.53 -61.47 100.00 38.53 -61.47 Site Acceptance Test - SAT 555 22.20% 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Total 26576 100.00% 90.72 87.03 -3.69 7.27 4.38 -2.90 97.99 91.41 -6.58 Budgeted Units % Plan-Wk % Actual -Wk % Plan % Actual Plan Actual Var. Plan Actual Var. Plan Actual Var. E&I Installation 24076 90.59% 98.72 95.20 -3.52 1.26 1.17 -0.09 99.97 96.37 -3.61 Calibration of Instruments Tag 1294 5.37% 100.00 100.00 0.00 0.00 0.00 0.00 100.00 100.00 0.00 E&I Supports, Ladders and Trays 8442 35.06% 100.00 100.00 0.00 0.00 0.00 0.00 100.00 100.00 0.00 Fabrication of E&I Supports 3723 44.10% 100.00 100.00 0.00 0.00 0.00 0.00 100.00 100.00 0.00 Installation of E&I SupportS 3250 38.50% 100.00 100.00 0.00 0.00 0.00 0.00 100.00 100.00 0.00 Installation of E&I Trays and Ladders 1469 17.40% 100.00 100.00 0.00 0.00 0.00 0.00 100.00 100.00 0.00 Cables Installation 8282 34.40% 100.00 99.58 -0.42 0.00 0.00 0.00 100.00 99.58 -0.42 Tubings Installation 3986 16.56% 100.00 91.20 -8.80 0.00 2.14 2.14 100.00 93.35 -6.65 Hook-Up of E&I Tag Items 793 3.29% 75.16 56.88 -18.28 24.84 24.49 -0.36 100.00 81.37 -18.63 Cable Continuity Check 995 4.13% 97.54 85.43 -12.11 2.46 0.15 -2.31 100.00 85.58 -14.42 Tubing Leak Test 284 1.18% 98.77 0.00 -98.77 1.23 0.00 -1.23 100.00 0.00 -100.00 E&I Pre-Commissioning 2500 9.41% 0.00 0.00 0.00 38.90 0.00 -38.90 38.90 0.00 -38.90 Loop/Function Test 1945 77.80% 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Site Acceptance Test - SAT 555 22.20% 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Total 26576 100.00% 89.43 86.24 -3.19 1.14 1.06 -0.08 90.57 87.30 -3.27 Budgeted Units % Plan-Wk % Actual -Wk % Plan % Actual Plan Actual Var. Plan Actual Var. Plan Actual Var. E&I Installation 24076 90.59% 95.66 91.75 -3.91 2.36 2.85 0.49 98.02 94.61 -3.42 Calibration of Instruments Tag 1294 5.37% 100.00 100.00 0.00 0.00 0.00 0.00 100.00 100.00 0.00 E&I Supports, Ladders and Trays 8442 35.06% 99.91 99.61 -0.29 0.09 0.39 0.29 100.00 100.00 0.00 Fabrication of E&I Supports 3723 44.10% 100.00 100.00 0.00 0.00 0.00 0.00 100.00 100.00 0.00 Installation of E&I SupportS 3250 38.50% 99.75 98.99 -0.77 0.25 1.01 0.77 100.00 100.00 0.00 Installation of E&I Trays and Ladders 1469 17.40% 100.00 100.00 0.00 0.00 0.00 0.00 100.00 100.00 0.00 Cables Installation 8282 34.40% 97.25 96.83 -0.42 2.75 1.75 -1.01 100.00 98.58 -1.42 Tubings Installation 3986 16.56% 99.65 87.17 -12.48 0.35 5.27 4.92 100.00 92.44 -7.56 Hook-Up of E&I Tag Items 793 3.29% 72.38 60.44 -11.95 9.08 0.00 -9.08 81.46 60.44 -21.03 Cable Continuity Check 995 4.13% 70.75 41.67 -29.09 20.45 30.01 9.55 91.21 71.67 -19.53 Tubing Leak Test 284 1.18% 0.00 0.00 0.00 46.48 0.00 -46.48 46.48 0.00 -46.48 E&I Pre-Commissioning 2500 9.41% 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Loop/Function Test 1945 77.80% 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Site Acceptance Test - SAT 555 22.20% 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Total 26576 100.00% 86.66 83.12 -3.54 2.14 2.58 0.44 88.80 85.71 -3.10 WHP 50/4 : GAS PLATFORM Platform Budget Mhrs Weightage % Last Week % Achieved This Week % Up To Date WHP 50/3 : GAS PLATFORM Platform Budget Mhrs Weightage % Last Week % Achieved This Week % Up To Date WHP 50/2 : GAS PLATFORM Platform Budget Mhrs Weightage % Last Week % Achieved This Week % Up To Date WHP 50/1 : GAS PLATFORM Platform Budget Mhrs Weightage % Last Week % Achieved This Week % Up To Date % Up To Date CHEVRON : CVX-PHASE 50 PROGRESS STATUS OF E&I AND PRE-COMMISSIONING WORKS : BY PLATFORM Cut Off Date OVERALL : BY PLATFORM Platform Budget Mhrs Weightage % Last Week % Achieved This Week Page 1 of 2 Prepared By : Nattakarn S.
  • 6.
    1-Jun-16 CHEVRON : CVX-PHASE50 PROGRESS STATUS OF E&I AND PRE-COMMISSIONING WORKS : BY PLATFORM Cut Off Date Budgeted Units % Plan-Wk % Actual -Wk % Plan % Actual Plan Actual Var. Plan Actual Var. Plan Actual Var. E&I Installation 24076 90.59% 88.02 80.67 -7.35 5.74 6.68 0.94 93.76 87.35 -6.41 Calibration of Instruments Tag 1294 5.37% 99.77 100.00 0.23 0.23 0.00 -0.23 100.00 100.00 0.00 E&I Supports, Ladders and Trays 8442 35.06% 99.99 99.61 -0.38 0.01 0.39 0.38 100.00 100.00 0.00 Fabrication of E&I Supports 3723 44.10% 100.00 100.00 0.00 0.00 0.00 0.00 100.00 100.00 0.00 Installation of E&I SupportS 3250 38.50% 99.97 98.98 -0.99 0.03 1.02 0.99 100.00 100.00 0.00 Installation of E&I Trays and Ladders 1469 17.40% 100.00 100.00 0.00 0.00 0.00 0.00 100.00 100.00 0.00 Cables Installation 8282 34.40% 91.54 80.79 -10.75 5.08 10.11 5.03 96.62 90.90 -5.72 Tubings Installation 3986 16.56% 67.22 65.39 -1.83 17.84 11.75 -6.09 85.06 77.14 -7.92 Hook-Up of E&I Tag Items 793 3.29% 55.74 49.19 -6.54 7.69 0.20 -7.49 63.43 49.40 -14.03 Cable Continuity Check 995 4.13% 58.79 3.12 -55.68 18.74 27.01 8.27 77.54 30.13 -47.41 Tubing Leak Test 284 1.18% 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 E&I Pre-Commissioning 2500 9.41% 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Loop/Function Test 1945 77.80% 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Site Acceptance Test - SAT 555 22.20% 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Total 26576 100.00% 79.74 73.08 -6.66 5.20 6.06 0.85 84.94 79.13 -5.81 WHP 50/5 : GAS PLATFORM Platform Budget Mhrs Weightage % Last Week % Achieved This Week % Up To Date Page 2 of 2 Prepared By : Nattakarn S.
  • 7.
    % Actual % Plan% Actual % Var. OVERALL 100.00% 92.46 88.15 -4.31 Noted : 1. This weekly progress status is based on Phase 50 : Project Accelerate Plan Rev.2 17.57 20.55 20.62 21.06 23.88 26.28 8.13 11.36 13.57 10-Aug 24-Aug27-Apr 4-May 11-May 13-Jul 20-Jul23-Dec 30-Dec 27-Jul13-Apr 20-Apr 3-Aug6-Apr 100.0048.87 50.69 74.05 100.0043.41 22-Jul 29-Jul 100.00 100.0039.37 41.31 18-May 25-May 90.59 97.70 100.00 33.09 33.43 34.16 36.87 39.05 40.73 42.27 43.81 46.65 50.01 51.82 51.82 52.61 56.45 56.66 26-Aug 2-Sep 9-Sep 9-Dec 16-Dec 56.72 31-Aug 7-Sep24-Feb 17-Aug2-Mar 9-Mar 16-Mar 23-Mar6-Jan 13-Jan28-Oct 20-Jan 27-Jan 3-Feb 10-Feb 17-Feb 2015 0.74 1.38 3.56 5.70 4.70 7.08 9.84 12.09 14.15 4-Nov 11-Nov 18-Nov 25-Nov 30-Mar 18.36 20.10 21.82 53.47 55.5430.83 23.48 24.64 25.73 56.72 79.13 23.48 29.22 30.23 30.7826.94 33.09 33.43 34.16 36.87 39.05 40.73 42.27 43.81 46.65 26.94 50.01 51.82 51.82 52.61 56.45 56.66 2-Dec 13.57 15.91 18.36 20.10 21.82 WHP 50/5 20.00% 84.94 79.13 -5.81 0.14 0.17 0.17 1.47 1.97 2.77 0.14 0.17 0.17 1.47 1.97 2.77 35.94 37.04 42.03 43.09 45.39 47.55 50.08 51.66 53.99 55.68 58.44 58.44 59.26 64.60 74.75 80.78 85.72 87.03 91.4113.20 15.01 17.02 20.19 21.13 22.65 23.80 25.39 25.83 26.20 28.12 28.81 28.81 29.31 29.50 31.71 4.70 7.08 9.84 12.09 14.15 17.57 20.55 20.62 21.06 23.88 26.28 26.94 26.94 29.22 30.23 30.78 53.99 55.68 58.44 58.44 59.26 64.60 74.75 80.78 88.61 90.72 97.99 100.0025.39 25.83 26.20 28.12 28.81 28.81 29.31 29.50 31.71 35.94 37.04 42.03 43.09 45.39 47.55 50.08 51.66 WHP 50/3 20.00% 97.99 91.41 -6.58 0.11 0.29 0.30 1.99 2.24 6.49 8.31 0.11 0.29 0.30 1.99 2.24 6.49 8.31 13.20 15.01 17.02 20.19 21.13 22.65 23.80 33.49 33.74 34.28 36.24 40.40 44.43 46.06 48.80 49.21 51.30 52.51 52.51 54.55 56.21 62.17 70.67 80.76 86.24 87.3021.06 22.54 25.75 26.09 27.34 28.42 28.42 29.83 30.27 31.70 52.51 52.51 54.55 56.21 62.17 70.6744.43 46.06 48.80 49.21 51.30 100.00 0.14 0.17 0.17 1.47 2.20 3.83 6.80 8.31 12.20 14.94 18.01 19.49 26.09 27.34 28.42 28.42 29.83 30.27 31.70 33.49 33.74 34.28 36.24 40.40 WHP 50/4 20.00% 90.57 87.30 -3.27 0.14 0.17 0.17 1.47 2.20 3.83 6.80 8.31 12.20 14.94 18.01 19.49 21.06 22.54 25.75 74.5345.93 48.34 50.18 53.53 55.07 56.99 59.2236.82 40.15 43.99 60.73 62.46 62.46 63.78 66.91 71.770.19 23.22 24.16 25.12 26.58 27.47 28.38 28.78 29.78 29.78 30.69 32.60 59.22 60.73 62.46 62.46 63.78 66.91 71.77 74.5340.15 43.9915.43 WHP 50/2 20.00% 88.80 85.71 29.78 45.93 48.34 50.18 53.53 55.07 56.9928.78 29.78 30.69 32.60 36.82 -3.10 0.91 1.52 2.09 5.83 8.46 11.97 18.51 19.24 20.80 23.22 24.16 25.12 26.58 27.47 28.38 0.91 1.52 2.09 5.83 8.46 11.97 15.43 18.51 19.24 20.80 0.19 9-Mar CHEVRON : CVX-PHASE 50 E&I AND PRE-COMMISSIONING : OVERALL PROGRESS S-CURVE 1-Jun-16 WBS WTG 22-Jul 29-Jul 5-Aug 12-Aug 19-Aug 26-Aug 2-Sep 9-Sep 16-Sep 23-Sep 30-Sep 7-Oct 14-Oct 21-Oct 31-Aug 7-Sep17-Aug 24-Aug13-Jul16-Mar 23-Mar Cumulative Progress 2-Mar 6-Jul1-Jun28-Oct 4-Nov 11-Nov 18-Nov 25-Nov 2-Dec 9-Dec 16-Dec 23-Dec 30-Dec 6-Jan 13-Jan 18-May 25-May 20-Jul 27-Jul 3-Aug 10-Aug13-Apr 20-Apr 27-Apr 4-May30-Mar 6-Apr20-Jan 27-Jan 3-Feb 10-Feb 17-Feb 24-Feb 11-May 15-Jun 22-Jun 29-Jun WHP 50/1 20.00% 100.00 97.21 -2.79 0.19 1.08 1.52 2.48 6.77 9.36 13.75 16.69 18.93 21.23 23.78 23.99 25.23 26.86 28.10 50.17 52.5128.52 28.76 29.04 30.36 30.36 35.12 73.6273.62 0.19 1.08 1.52 44.99 48.6538.22 42.29 50.17 52.5128.52 28.76 29.04 30.36 30.36 35.12 54.27 58.10 59.99 66.08 68.61 69.60 2.48 6.77 9.36 13.75 16.69 18.93 21.23 23.78 23.99 25.23 26.86 38.22 42.29 44.99 48.65 54.27 58.10 73.62 75.71 80.95 84.43 87.55 0.51 0.51 0.74 75.71 80.95 84.43 87.55 59.99 66.08 68.61 69.60 73.6228.10 100.00100.00 100.00 32.16 45.8637.53 53.47 55.54 79.46 84.36 88.15CUMULATIVE ACCELERATE PLAN 0.00 0.00 0.00 0.00 0.10 E&I AND PRE-COMMISSIONING WORKS PROGRESS 23-Sep 30-Sep 7-Oct 14-Oct 21-Oct5-Aug 12-Aug 19-Aug ACTUAL 0.00 0.00 0.00 0.00 0.10 1.38 3.56 5.70 16-Sep 0.00 0.00 0.00 8.13 15.91 11.36 26.66 27.91 28.86 28.86 61.18 65.0241.31 69.95 74.05 27.91 28.8625.73 28.8626.66 59.77 61.18 69.95 39.37 57.46 59.77 50.6937.53 83.52 88.94 92.46 95.52 100.00 100.0065.02 100.0024.64 34.66 57.46 59.77 59.7743.41 45.86 48.87 100.0032.16 34.66 30.83 WEEKLY PLANNED 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.000.00 0.00VARIANCE 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.000.00 0.00 0.00 0.00 -4.06 -4.58 -4.310.00 0.00 0.00 0.00 0.00 0.00 3.23 2.212.140.64 1.331.72 1.16 1.09 0.93 1.25 0.00 0.000.00 0.00 0.00 0.00 9.47 0.00 0.00 0.00 0.00 0.001.97 0.00 2.07 1.92 2.31 0.00 1.41 0.00 0.00 0.00 1.66 2.18 0.10 0.41 0.23 0.64 2.18 2.14 2.43 3.23 2.21 2.34 2.45 1.74 1.72 2.34 2.45 1.74 4.93 4.10 0.00 0.00 0.00 0.000.95 0.00 2.45 3.011.25 0.95 0.00 1.97 1.33 2.50 1.84 1.94 2.10 2.45 3.01 1.82 2.782.50 2.87 3.84 4.93 4.10 ACTUAL 0.00 0.00 0.00 0.23 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.92 2.31 0.00 1.41 3.84 0.000.00 0.00 0.00VARIANCE 0.00 0.000.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.00 0.000.000.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.66 1.16 1.09 0.930.00 0.10 0.41 2.87 1.84 1.94 2.10 1.82 2.78 2.07 0.00 0.00 0.00 0.00 0.000.00 0.00 2.43 0.00 0.00 0.00 0.00 0.00 98.05 100.00 8-Jun 90.59 98.16 100.00 88.18 92.32 97.21 83.52 86.66 88.80 90.59 2.21 1.81 0.46 0.00 71.25 79.74 84.94 88.97 64.69 73.08 15-Jun 22-Jun 29-Jun 6-Jul 2016 2015 2016 89.43 90.57 98.05 77.94 5.41 4.90 3.79 -4.06 -0.52 0.27 83.63 83.12 85.71 97.73 99.54 5.42 3.52 3.06 1-Jun 8-Jun % REMAINING WORK % ACTUAL PROGRESS ACCELERATE PLAN REV.2 CUM. ACTUAL ACCELERATE PLAN REV.2 CUM. ACTUAL Page 1 of 6 Prepared By : Nattakarn S.
  • 8.
    % Actual % Plan% Actual % Var. WHP 501 100.00% 100.00 97.21 -2.79 Noted : 1. This weekly progress status is based on Phase 50 : Project Accelerate Plan Rev.2 88.524.51 40.69 74.12 4.51 40.69 74.12 88.52 Cable Continuity Check 4.13% 100.00 92.58 -7.42 25.79 61.28 90.39 95.75 25.79 Tubing Leak Test 1.18% 100.00 95.75 -4.25 94.64 94.66 95.79 96.55 96.75 96.77 96.77 97.06 97.06 97.06 97.06 99.71 99.715.41 33.25 33.25 45.61 47.15 47.34 48.12 68.84 71.69 72.29 72.29 72.29 75.03 79.23 79.23 81.05 81.50 85.68 93.65 93.65 94.44 96.55 96.75 96.77 96.77 97.06 97.06 97.06 97.06 99.71 100.0068.84 71.69 72.29 72.29 72.29 75.03 79.23 79.23 81.05 81.50 85.68 93.65 93.65 94.44 94.64 94.66 95.79 99.59 Calibration of Instruments Tag 5.37% 100.00 100.00 0.00 5.41 33.25 33.25 45.61 47.15 47.34 48.12 20.44 29.65 36.28 47.69 51.68 58.40 62.64 67.09 71.66 80.56 87.15 88.14 92.02 92.02 92.11 97.11 99.091.17 2.12 2.12 2.29 2.29 3.86 3.86 12.99 47.69 51.68 58.40 62.64 67.09 71.66 80.56 87.15 88.14 92.02 92.02 92.11 97.11 99.09 100.001.17 2.12 2.12 2.29 2.29 3.86 3.86 12.99 20.44 29.65 36.28 Cables Installation (Pulling, Glanding ,Termination) 34.40% 100.00 99.93 -0.07 81.6131.97 42.26 42.26 46.59 52.57 72.6029.40 29.42 30.19 30.30 31.09 31.9724.78 25.77 27.18 28.193.60 3.93 4.19 4.72 5.39 5.392.05 2.65 3.60 81.6131.97 42.26 42.26 46.59 52.57 72.6029.40 29.42 30.19 30.30 24.14 24.24 31.09 31.9724.14 24.24 24.78 25.77 27.18 28.193.60 3.93 4.19 4.72 5.39 5.392.05 2.65 3.60 Installation And Hook-Up of E&I Tag Items 3.29% 100.00 98.38 -1.62 0.00 0.00 2.94 13.75 16.69 30-Sep 7-Oct 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.00VARIANCE 0.00 0.00 0.00 0.00 3.48 3.122.53 0.99 4.02 0.00 2.09 5.241.52 2.34 1.76 3.83 1.89 6.090.00 4.76 3.10 4.07 2.70 3.661.63 1.24 0.42 0.24 0.28 1.322.24 2.30 2.55 0.21 1.240.89 0.44 0.96 4.29 2.59 4.39 0.00 0.00 0.00 0.00 ACTUAL 0.00 0.00 0.00 0.00 0.19 3.12 0.00 0.00 0.00 0.00 0.000.99 4.02 0.00 2.09 5.24 3.482.34 1.76 3.83 1.89 6.09 2.534.76 3.10 4.07 2.70 3.66 1.521.24 0.42 0.24 0.28 1.32 0.002.24 2.30 2.55 0.21 1.24 1.630.44 0.96 4.29 2.59 4.39 2.94 WEEKLY PLANNED 0.00 0.00 0.00 0.00 0.19 0.89 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.00 88.18 92.32 97.2173.62 73.6244.99 48.65 50.17 52.51 -2.41 -5.84 -2.79VARIANCE 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 75.71 80.9559.99 66.08 68.61 69.60 84.43 87.55 0.000.00 0.00 0.00 0.00 0.00 0.00 26.86 28.10 28.52 28.769.36 13.75 16.69 18.93 21.23 23.78 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.00 0.00 0.19 1.08 1.52 2.48 6.77 25.23 26.86 28.10 28.52 28.76 29.04 100.00 100.00 100.00 100.00 100.000.19 1.08 1.52 2.48 6.77 9.36 54.27 58.1029.04 30.36 30.36 35.12 38.22 42.2925.23 100.0080.95 84.43 87.55 100.00 100.00 100.0066.08 68.61 69.60 73.62 73.62 75.71 100.00 100.00 100.00 100.0090.59 98.16 100.00 100.00 CUMULATIVE ACCELERATE PLAN 0.00 0.00 0.00 0.00 ACTUAL 0.00 0.00 0.00 23.99 0.00 0.00 27-Apr 4-May 11-May 13-Jul E&I AND PRE-COMMISSIONING WORKS PROGRESS 22-Jul 29-Jul 5-Aug 12-Aug 6-Jan 13-Jan 20-Jan 27-Jan11-Nov 18-Nov 25-Nov 2-Dec 9-Dec 16-Dec 16-Mar 23-Mar 30-Mar 6-Apr 13-Apr 20-Apr 18-May 25-May 1-Jun 8-Jun 18.93 21.23 23.78 23.99 48.65 50.17 52.51 54.27 58.10 59.9930.36 30.36 35.12 38.22 42.29 44.99 3-Feb 10-Feb23-Dec 30-Dec19-Aug 26-Aug 2-Sep 9-Sep 16-Sep 23-Sep 17-Feb 24-Feb 2-Mar 9-Mar14-Oct 21-Oct 28-Oct 4-Nov Site Acceptance Test - SAT 22.20% 100.00 50.00 -50.00 Loop/Function Test 77.80% 100.00 90.00 -10.00 PRE-COMMISSIONING 9.41% 100.00 81.12 -18.88 50.04 50.04 61.00 74.68 80.52 92.464.65 5.42 8.10 26.48 29.40 33.480.80 2.04 50.04 50.04 61.00 74.68 80.52 100.004.65 5.42 8.10 26.48 29.40 33.480.80 2.04 Tubings Installation 16.56% 100.00 95.84 -4.16 99.02 99.02 99.38 99.71 99.71 100.0089.92 96.99 97.08 98.74 98.78 98.9985.50 88.58 89.28 89.46 89.74 89.7776.25 76.81 77.23 79.13 79.13 83.1459.61 67.59 67.96 68.62 72.09 74.957.80 21.33 28.64 38.19 47.44 52.590.61 3.41 4.79 99.02 99.02 99.38 99.717.80 21.33 28.64 38.19 47.44 52.590.61 3.41 4.79 99.71 100.0089.92 96.99 97.08 98.74 98.78 98.9985.50 88.58 89.28 89.46 89.74 89.7776.25 76.81 77.23 79.13 79.13 83.14 E&I Supports, Ladders and Trays 35.06% 100.00 100.00 0.00 59.61 67.59 67.96 68.62 72.09 74.95 E&I 90.59% 100.00 98.88 -1.12 23-Sep 30-Sep 7-Oct 14-Oct 24-Aug13-Jan 20-Jan 27-Jan 3-Feb 13-Jul 20-Jul 27-Jul 3-Aug 10-Aug 17-Aug6-Apr 13-Apr 20-Apr 27-Apr 4-May 11-May24-Feb 2-Mar 9-Mar 16-Mar 23-Mar 30-Mar29-Jul 5-Aug 12-Aug 19-Aug 26-Aug 2-Sep CHEVRON : CVX-PHASE 50 E&I AND PRE-COMMISSIONING : WHP 501 PROGRESS S-CURVE 1-Jun-16 WBS WTG Cumulative Progress 22-Jul 10-Feb 17-Feb2-Dec 9-Dec 16-Dec 23-Dec 30-Dec 6-Jan21-Oct 28-Oct 4-Nov 11-Nov 18-Nov 25-Nov9-Sep 16-Sep 31-Aug 7-Sep15-Jun 22-Jun 29-Jun 6-Jul 2015 15-Jun 22-Jun 29-Jun 6-Jul 3-Aug 10-Aug 0.00 0.00 0.00 0.00 17-Aug 24-Aug20-Jul 27-Jul 31-Aug 7-Sep 18-May 25-May 1-Jun 8-Jun 100.00 99.59 99.93 99.93 100.00 84.70 91.75 98.38 92.46 94.49 95.84 100.00 92.54 92.58 92.58 100.00 2016 2015 2016 3.04 7.57 1.84 0.00 0.63 4.14 4.89 -2.41 -3.43 3.05 100.00 43.76 90.00 100.00 50.00 % REMAINING WORK % ACTUAL PROGRESS ACCELERATE PLAN REV.2 CUM. ACTUAL CUM. ACTUAL ACCELERATE PLAN REV.2 Page 2 of 6 Prepared By : Nattakarn S.
  • 9.
    % Actual % Plan% Actual % Var. WHP 503 100.00% 97.99 91.41 -6.58 Noted : 1. This weekly progress status is based on Phase 50 : Project Accelerate Plan Rev.2 0.00 0.00 0.00 -2.89 -0.80 -2.890.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.00 1.10 4.99 1.060.44 0.37 1.92 0.69 0.00 0.502.01 3.17 0.94 1.52 1.15 1.591.69 0.25 4.25 1.82 4.89 1.81 VARIANCE 0.00 0.00 0.00 0.00 4.94 1.31 4.382.76 0.00 0.82 5.34 10.15 6.032.30 2.16 2.53 1.58 2.33 1.690.19 2.21 4.23 0.00 0.00 ACTUAL 0.00 0.00 0.00 0.00 0.11 0.18 0.01 0.00 0.00 0.00 0.00 0.00 0.002.01 0.00 0.00 0.00 0.00 0.005.34 10.15 6.03 7.83 2.11 7.271.58 2.33 1.69 2.76 0.00 0.821.10 4.99 1.06 2.30 2.16 2.530.69 0.00 0.50 0.19 2.21 4.231.52 1.15 1.59 0.44 0.37 1.921.82 4.89 1.81 2.01 3.17 0.940.11 0.18 0.01 1.69 0.25 4.25 WEEKLY PLANNED 0.00 0.00 0.00 0.00 -3.69 -6.580.00 0.00 0.00 0.00 0.00 -2.890.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.00VARIANCE 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 74.75 80.78 85.72 87.03 91.4153.99 55.68 58.44 58.44 59.26 64.6042.03 43.09 45.39 47.55 50.08 51.6628.81 29.31 29.50 31.71 35.94 37.0423.80 25.39 25.83 26.20 28.12 28.8113.20 15.01 17.02 20.19 21.13 22.650.29 0.30 1.99 2.24 6.49 8.31ACTUAL 0.00 0.00 0.00 0.00 0.11 100.00 100.00 100.00 100.00 100.00 100.00100.00 100.00 100.00 100.00 100.00 100.0080.78 88.61 90.72 97.99 100.00 100.0055.68 58.44 58.44 59.26 64.60 74.7543.09 45.39 47.55 50.08 51.66 53.9929.31 29.50 31.71 35.94 37.04 42.0325.39 25.83 26.20 28.12 28.81 28.8115.01 17.02 20.19 21.13 22.65 23.800.30 1.99 2.24 6.49 8.31 13.20 31-Aug 7-Sep CUMULATIVE ACCELERATE PLAN 0.00 0.00 0.00 0.00 0.11 0.29 20-Jul 27-Jul 3-Aug 10-Aug 17-Aug 24-Aug8-Jun 15-Jun 22-Jun 29-Jun 6-Jul 13-Jul27-Apr 4-May 11-May 18-May 25-May 1-Jun16-Mar 23-Mar 30-Mar 6-Apr 13-Apr 20-Apr3-Feb 10-Feb 17-Feb 24-Feb 2-Mar 9-Mar23-Dec 30-Dec 6-Jan 13-Jan 20-Jan 27-Jan11-Nov 18-Nov 25-Nov 2-Dec 9-Dec 16-Dec30-Sep 7-Oct 14-Oct 21-Oct 28-Oct 4-Nov19-Aug 26-Aug 2-Sep 9-Sep 16-Sep 23-Sep E&I AND PRE-COMMISSIONING WORKS PROGRESS 22-Jul 29-Jul 5-Aug 12-Aug 100.00 0.00Site Acceptance Test - SAT 22.20% 0.00 0.00 38.53 100.00 Loop/Function Test 77.80% 100.00 38.53 -61.47 PRE-COMMISSIONING 9.41% 78.66 29.98 -48.68 91.12 100.00 -8.88Tubing Leak Test 1.18% 100.00 91.12 83.32 86.63 87.7234.70 52.22 74.36 34.70 52.22 74.36 95.58 100.00 Cable Continuity Check 4.13% 100.00 87.72 -12.28 45.55 48.95 72.07 73.80 79.4930.09 30.09 40.38 40.38 40.38 43.5626.66 26.96 27.10 27.16 27.41 28.224.79 5.60 5.60 20.20 25.44 25.772.38 3.31 3.31 3.31 4.51 4.79 25.77 26.66 26.963.31 3.31 4.51 4.79 4.79 5.602.38 3.31 77.68 100.0040.38 40.38 40.38 43.56 45.55 48.9527.10 27.16 27.41 28.22 30.09 30.095.60 20.20 25.44 Installation And Hook-Up of E&I Tag Items 3.29% 100.00 79.49 -20.51 95.295.92 8.06 44.91 65.45 85.73 92.810.74 0.74 0.74 1.02 4.33 4.330.46 0.46 0.46 0.74 44.91 65.45 99.60 100.000.74 1.02 4.33 4.33 5.92 8.060.46 0.46 0.46 0.74 0.74 0.74 -4.71Tubings Installation 16.56% 100.00 95.29 99.33 99.58 99.5866.02 66.02 67.48 77.90 90.43 96.9437.05 40.86 48.24 50.74 57.61 61.874.02 4.02 10.25 12.22 27.45 30.790.61 1.56 3.76 4.00 4.00 4.020.61 0.61 67.48 77.90 90.43 96.94 99.94 100.0048.24 50.74 57.61 61.87 66.02 66.0210.25 12.22 27.45 30.79 37.05 40.863.76 4.00 4.00 4.02 4.02 4.020.61 0.61 0.61 1.56 Cables Installation (Pulling, Glanding ,Termination) 34.40% 100.00 99.58 -0.42 100.0099.11 99.30 99.78 99.78 99.78 99.9878.07 80.86 81.12 81.19 96.19 98.3150.55 69.99 72.29 72.29 75.03 78.0733.76 36.87 36.87 46.31 47.09 48.140.78 6.01 98.31 99.11 99.3072.29 72.29 75.03 78.07 78.07 80.8636.87 46.31 47.09 48.14 50.55 69.99 99.78 99.78 99.78 99.98 100.0081.12 81.19 96.190.78 6.01 33.76 36.87 Calibration of Instruments Tag 5.37% 100.00 100.00 0.00 98.46 99.62 99.63 99.63 100.0092.12 94.53 94.95 95.93 98.04 98.0485.94 87.14 87.46 87.49 88.50 91.4172.91 74.35 74.35 75.41 75.95 81.5459.31 63.94 66.34 68.28 69.31 69.5620.30 25.23 36.39 41.61 47.94 56.460.33 0.91 0.95 6.28 7.04 99.63 100.0094.95 95.93 98.04 98.04 98.46 99.6287.46 87.49 88.50 91.41 92.12 94.5374.35 75.41 75.95 81.54 85.94 87.1466.34 68.28 69.31 69.56 72.91 74.3536.39 41.61 47.94 56.46 59.31 63.940.91 0.95 6.28 7.04 20.30 25.23 0.00 0.33 E&I Supports, Ladders and Trays 35.06% 100.00 100.00 23-Mar E&I 90.59% 100.00 97.79 -2.21 22-Jun 24-Aug 31-Aug 7-Sep3-Feb 10-Feb 17-Feb2-Dec 9-Dec 16-Dec 23-Dec 30-Dec 6-Jan21-Oct 28-Oct 4-Nov 11-Nov 18-Nov 25-Nov 13-Jan 20-Jan 27-Jan 6-Apr 13-Apr 20-Apr 27-Apr 4-May 11-May24-Feb 2-Mar 9-Mar 16-Mar CHEVRON : CVX-PHASE 50 E&I AND PRE-COMMISSIONING : WHP 503 PROGRESS S-CURVE 1-Jun-16 WBS WTG Cumulative Progress 22-Jul 29-Jun 6-Jul 10-Aug 17-Aug 2015 2016 2015 2016 13-Jul30-Mar9-Sep 16-Sep 23-Sep 30-Sep 7-Oct 14-Oct29-Jul 5-Aug 12-Aug 19-Aug 26-Aug 2-Sep 20-Jul 27-Jul 3-Aug18-May 25-May 1-Jun 8-Jun 15-Jun % REMAINING WORK % ACTUAL PROGRESS ACCELERATE PLAN REV.2 CUM. ACTUAL CUM. ACTUAL ACCELERATE PLAN REV.2 Page 3 of 6 Prepared By : Nattakarn S.
  • 10.
    % Actual % Plan% Actual % Var. WHP 504 100.00% 94.23 87.30 -6.93 Noted : 1. This weekly progress status is based on Phase 50 : Project Accelerate Plan Rev.2 0.00 0.00 0.00 -2.87 -0.32 -0.080.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.00 0.25 0.54 1.963.21 0.34 1.25 1.08 0.00 1.413.89 2.74 3.07 1.48 1.57 1.480.00 1.30 0.73 1.63 2.97 1.51 VARIANCE 0.00 0.00 0.00 0.00 10.09 5.48 1.061.21 0.00 2.04 1.66 5.96 8.504.16 4.03 1.63 2.74 0.41 2.090.44 1.43 1.79 0.00 0.00 ACTUAL 0.00 0.00 0.00 0.00 0.00 0.14 0.03 0.00 0.00 0.00 0.00 0.00 0.007.48 1.95 0.00 0.00 0.00 0.001.66 5.96 8.50 12.96 5.80 1.142.74 0.41 2.09 1.21 0.00 2.040.25 0.54 1.96 4.16 4.03 1.631.08 0.00 1.41 0.44 1.43 1.791.48 1.57 1.48 3.21 0.34 1.251.63 2.97 1.51 3.89 2.74 3.070.00 0.14 0.03 0.00 1.30 0.73 WEEKLY PLANNED 0.00 0.00 0.00 0.00 -3.19 -3.270.00 0.00 0.00 0.00 0.00 -2.870.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.00VARIANCE 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 62.17 70.67 80.76 86.24 87.3049.21 51.30 52.51 52.51 54.55 56.2134.28 36.24 40.40 44.43 46.06 48.8028.42 29.83 30.27 31.70 33.49 33.7421.06 22.54 25.75 26.09 27.34 28.426.80 8.31 12.20 14.94 18.01 19.490.14 0.17 0.17 1.47 2.20 3.83ACTUAL 0.00 0.00 0.00 0.00 0.00 100.00 100.00 100.00 100.00 100.00 100.00100.00 100.00 100.00 100.00 100.00 100.0070.67 83.63 89.43 90.57 98.05 100.0051.30 52.51 52.51 54.55 56.21 62.1736.24 40.40 44.43 46.06 48.80 49.2129.83 30.27 31.70 33.49 33.74 34.2822.54 25.75 26.09 27.34 28.42 28.428.31 12.20 14.94 18.01 19.49 21.060.17 0.17 1.47 2.20 3.83 6.80 31-Aug 7-Sep CUMULATIVE ACCELERATE PLAN 0.00 0.00 0.00 0.00 0.00 0.14 20-Jul 27-Jul 3-Aug 10-Aug 17-Aug 24-Aug8-Jun 15-Jun 22-Jun 29-Jun 6-Jul 13-Jul27-Apr 4-May 11-May 18-May 25-May 1-Jun16-Mar 23-Mar 30-Mar 6-Apr 13-Apr 20-Apr3-Feb 10-Feb 17-Feb 24-Feb 2-Mar 9-Mar23-Dec 30-Dec 6-Jan 13-Jan 20-Jan 27-Jan11-Nov 18-Nov 25-Nov 2-Dec 9-Dec 16-Dec30-Sep 7-Oct 14-Oct 21-Oct 28-Oct 4-Nov19-Aug 26-Aug 2-Sep 9-Sep 16-Sep 23-Sep E&I AND PRE-COMMISSIONING WORKS PROGRESS 22-Jul 29-Jul 5-Aug 12-Aug 100.00 0.00Site Acceptance Test - SAT 22.20% 0.00 0.00 100.00 Loop/Function Test 77.80% 0.00 0.00 0.00 PRE-COMMISSIONING 9.41% 38.90 0.00 -38.90 98.77 100.00 -100.00Tubing Leak Test 1.18% 100.00 0.00 56.88 85.43 85.580.90 0.90 0.90 100.000.90 0.90 0.90 63.82 97.54 Cable Continuity Check 4.13% 100.00 85.58 -14.42 44.15 47.44 50.57 56.88 81.3728.03 29.68 40.29 40.29 40.29 43.2925.61 26.69 26.98 26.98 27.41 28.033.81 5.10 5.10 23.42 24.66 24.713.64 3.72 3.72 3.81 24.71 25.61 26.693.64 3.72 3.72 3.81 3.81 5.10 55.61 75.16 100.0040.29 40.29 40.29 43.29 44.15 47.4426.98 26.98 27.41 28.03 28.03 29.685.10 23.42 24.66 Installation And Hook-Up of E&I Tag Items 3.29% 100.00 81.37 -18.63 93.350.77 0.86 32.65 61.61 80.91 91.200.48 0.48 0.48 0.64 0.77 0.770.48 32.65 61.61 92.15 100.000.48 0.64 0.77 0.77 0.77 0.860.48 0.48 0.48 -6.65Tubings Installation 16.56% 100.00 93.35 90.98 99.58 99.5850.31 50.31 55.92 58.53 62.30 75.3123.14 30.12 34.72 41.16 42.33 47.915.21 5.21 6.25 6.25 6.41 10.332.40 2.67 2.67 4.26 4.26 5.21 55.92 58.53 62.30 75.31 93.47 100.0034.72 41.16 42.33 47.91 50.31 50.316.25 6.25 6.41 10.33 23.14 30.122.67 4.26 4.26 5.21 5.21 5.212.40 2.67 Cables Installation (Pulling, Glanding ,Termination) 34.40% 100.00 99.58 -0.42 99.78 99.78 99.98 100.0099.19 99.19 99.78 99.78 99.78 99.7893.53 94.63 95.29 98.44 99.19 99.1978.21 81.24 81.48 81.54 91.83 91.8350.16 50.53 62.12 62.51 73.06 78.2133.25 36.87 36.87 46.31 46.90 48.140.78 5.50 91.83 93.53 94.6362.12 62.51 73.06 78.21 78.21 81.2436.87 46.31 46.90 48.14 50.16 50.53 99.88 100.0099.78 99.78 99.78 99.78 99.78 99.7895.29 98.44 99.19 99.19 99.19 99.1981.48 81.54 91.830.78 5.50 33.25 36.87 Calibration of Instruments Tag 5.37% 100.00 100.00 0.00 97.44 99.65 99.65 99.65 100.0092.93 95.18 95.34 96.19 96.51 96.5182.91 83.69 84.89 86.94 87.34 92.4671.90 72.94 72.94 75.86 77.21 80.0049.50 53.97 58.60 63.20 68.85 69.596.82 11.21 16.31 20.50 32.77 39.930.44 0.52 0.52 4.63 99.65 100.0095.34 96.19 96.51 96.51 97.44 99.6584.89 86.94 87.34 92.46 92.93 95.1872.94 75.86 77.21 80.00 82.91 83.6958.60 63.20 68.85 69.59 71.90 72.9416.31 20.50 32.77 39.93 49.50 53.970.44 0.52 0.52 4.63 6.82 11.21 0.00E&I Supports, Ladders and Trays 35.06% 100.00 100.00 23-Mar E&I 90.59% 99.97 96.37 -3.61 22-Jun 24-Aug 31-Aug 7-Sep3-Feb 10-Feb 17-Feb2-Dec 9-Dec 16-Dec 23-Dec 30-Dec 6-Jan21-Oct 28-Oct 4-Nov 11-Nov 18-Nov 25-Nov 13-Jan 20-Jan 27-Jan 6-Apr 13-Apr 20-Apr 27-Apr 4-May 11-May24-Feb 2-Mar 9-Mar 16-Mar CHEVRON : CVX-PHASE 50 E&I AND PRE-COMMISSIONING : WHP 504 PROGRESS S-CURVE 1-Jun-16 WBS WTG Cumulative Progress 22-Jul 29-Jun 6-Jul 10-Aug 17-Aug 2015 2016 2015 2016 13-Jul30-Mar9-Sep 16-Sep 23-Sep 30-Sep 7-Oct 14-Oct29-Jul 5-Aug 12-Aug 19-Aug 26-Aug 2-Sep 20-Jul 27-Jul 3-Aug18-May 25-May 1-Jun 8-Jun 15-Jun % REMAINING WORK % ACTUAL PROGRESS ACCELERATE PLAN REV.2 CUM. ACTUAL CUM. ACTUAL ACCELERATE PLAN REV.2 Page 4 of 6 Prepared By : Nattakarn S.
  • 11.
    % Actual % Plan% Actual % Var. WHP 502 100.00% 88.80 85.71 -3.10 Noted : 1. This weekly progress status is based on Phase 50 : Project Accelerate Plan Rev.2 0.00 0.00 0.00 -5.58 2.03 0.450.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.00 3.84 1.94 2.410.89 0.91 0.40 1.00 0.00 0.910.73 1.56 2.42 0.94 0.96 1.460.57 3.74 2.63 3.51 3.46 3.08 VARIANCE 0.00 0.00 0.00 0.00 3.41 5.18 2.591.73 0.00 1.32 3.13 4.86 2.761.84 3.35 1.54 1.92 2.23 1.511.91 4.22 3.33 0.00 0.00 ACTUAL 0.00 0.00 0.00 0.00 0.19 0.72 0.61 0.00 0.00 0.00 0.00 0.00 0.001.79 7.46 1.95 0.00 0.00 0.003.13 4.86 2.76 8.99 3.15 2.141.92 2.23 1.51 1.73 0.00 1.323.84 1.94 2.41 1.84 3.35 1.541.00 0.00 0.91 1.91 4.22 3.330.94 0.96 1.46 0.89 0.91 0.403.51 3.46 3.08 0.73 1.56 2.420.19 0.72 0.61 0.57 3.74 2.63 WEEKLY PLANNED 0.00 0.00 0.00 0.00 -3.54 -3.090.00 0.00 0.00 0.00 0.00 -5.580.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.00VARIANCE 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 71.77 74.53 77.94 83.12 85.7159.22 60.73 62.46 62.46 63.78 66.9145.93 48.34 50.18 53.53 55.07 56.9929.78 30.69 32.60 36.82 40.15 43.9925.12 26.58 27.47 28.38 28.78 29.7815.43 18.51 19.24 20.80 23.22 24.160.91 1.52 2.09 5.83 8.46 11.97ACTUAL 0.00 0.00 0.00 0.00 0.19 100.00 100.00 100.00 100.00 100.00 100.00100.00 100.00 100.00 100.00 100.00 100.0074.53 83.52 86.66 88.80 90.59 98.0560.73 62.46 62.46 63.78 66.91 71.7748.34 50.18 53.53 55.07 56.99 59.2230.69 32.60 36.82 40.15 43.99 45.9326.58 27.47 28.38 28.78 29.78 29.7818.51 19.24 20.80 23.22 24.16 25.121.52 2.09 5.83 8.46 11.97 15.43 31-Aug 7-Sep CUMULATIVE ACCELERATE PLAN 0.00 0.00 0.00 0.00 0.19 0.91 20-Jul 27-Jul 3-Aug 10-Aug 17-Aug 24-Aug8-Jun 15-Jun 22-Jun 29-Jun 6-Jul 13-Jul27-Apr 4-May 11-May 18-May 25-May 1-Jun16-Mar 23-Mar 30-Mar 6-Apr 13-Apr 20-Apr3-Feb 10-Feb 17-Feb 24-Feb 2-Mar 9-Mar23-Dec 30-Dec 6-Jan 13-Jan 20-Jan 27-Jan11-Nov 18-Nov 25-Nov 2-Dec 9-Dec 16-Dec30-Sep 7-Oct 14-Oct 21-Oct 28-Oct 4-Nov19-Aug 26-Aug 2-Sep 9-Sep 16-Sep 23-Sep E&I AND PRE-COMMISSIONING WORKS PROGRESS 22-Jul 29-Jul 5-Aug 12-Aug 100.00 0.00Site Acceptance Test - SAT 22.20% 0.00 0.00 100.00 Loop/Function Test 77.80% 0.00 0.00 0.00 PRE-COMMISSIONING 9.41% 0.00 0.00 0.00 46.48 100.00 -46.48Tubing Leak Test 1.18% 46.48 0.00 4.17 41.67 71.674.17 4.17 91.21 100.004.17 4.17 46.53 70.75 Cable Continuity Check 4.13% 91.21 71.67 -19.53 46.77 58.55 59.99 60.44 60.4430.75 30.75 41.15 41.15 41.15 42.1626.83 27.19 27.24 29.27 29.60 30.755.48 5.55 23.94 24.38 25.36 26.533.15 3.45 4.39 4.40 4.50 5.482.81 3.15 26.53 26.83 27.194.39 4.40 4.50 5.48 5.48 5.552.81 3.15 3.15 3.45 65.38 72.38 81.46 100.0041.15 41.15 41.15 42.16 46.77 58.5527.24 29.27 29.60 30.75 30.75 30.7523.94 24.38 25.36 Installation And Hook-Up of E&I Tag Items 3.29% 81.46 60.44 -21.03 92.447.90 13.74 39.44 48.65 69.17 87.171.59 2.36 2.36 2.36 6.83 6.830.71 1.22 1.22 1.41 39.44 48.65 89.45 99.65 100.002.36 2.36 6.83 6.83 7.90 13.740.71 1.22 1.22 1.41 1.59 2.36 -7.56Tubings Installation 16.56% 100.00 92.44 93.40 96.83 98.5877.35 77.35 80.46 86.88 89.17 92.4753.17 55.31 59.90 63.92 70.98 75.314.16 15.22 23.21 34.88 40.40 47.801.09 2.70 2.70 4.14 4.14 4.160.61 0.84 1.09 100.0080.46 86.88 89.17 92.47 95.73 97.2559.90 63.92 70.98 75.31 77.35 77.3523.21 34.88 40.40 47.80 53.17 55.312.70 4.14 4.14 4.16 4.16 15.220.61 0.84 1.09 1.09 2.70 Cables Installation (Pulling, Glanding ,Termination) 34.40% 100.00 98.58 -1.42 98.38 98.38 100.0093.83 94.02 94.39 96.65 98.16 98.3678.78 80.47 80.97 85.05 91.37 93.4961.43 70.22 71.77 71.77 74.52 78.7833.76 36.87 36.87 46.31 47.61 47.635.41 33.76 93.49 93.83 94.0271.77 71.77 74.52 78.78 78.78 80.4736.87 46.31 47.61 47.63 61.43 70.22 100.0094.39 96.65 98.16 98.36 98.38 98.3880.97 85.05 91.375.41 33.76 33.76 36.87 Calibration of Instruments Tag 5.37% 100.00 100.00 0.00 100.0098.92 99.61 99.61 99.61 99.61 99.6196.02 97.64 97.72 98.23 98.33 98.3387.23 87.44 87.73 87.75 88.22 96.0276.12 77.11 77.11 79.67 83.88 85.6665.55 67.85 68.55 71.53 73.99 75.2825.80 32.52 43.40 52.61 54.91 58.390.61 2.87 4.79 6.57 18.34 99.61 99.61 99.80 99.91 100.0097.72 98.23 98.33 98.33 98.92 99.6187.73 87.75 88.22 96.02 96.02 97.6477.11 79.67 83.88 85.66 87.23 87.4468.55 71.53 73.99 75.28 76.12 77.1143.40 52.61 54.91 58.39 65.55 67.852.87 4.79 6.57 18.34 25.80 32.52 0.00 0.61 E&I Supports, Ladders and Trays 35.06% 100.00 100.00 23-Mar E&I 90.59% 98.02 94.61 -3.42 22-Jun 24-Aug 31-Aug 7-Sep3-Feb 10-Feb 17-Feb2-Dec 9-Dec 16-Dec 23-Dec 30-Dec 6-Jan21-Oct 28-Oct 4-Nov 11-Nov 18-Nov 25-Nov 13-Jan 20-Jan 27-Jan 6-Apr 13-Apr 20-Apr 27-Apr 4-May 11-May24-Feb 2-Mar 9-Mar 16-Mar CHEVRON : CVX-PHASE 50 E&I AND PRE-COMMISSIONING : WHP 502 PROGRESS S-CURVE 1-Jun-16 WBS WTG Cumulative Progress 22-Jul 29-Jun 6-Jul 10-Aug 17-Aug 2015 2016 2015 2016 13-Jul30-Mar9-Sep 16-Sep 23-Sep 30-Sep 7-Oct 14-Oct29-Jul 5-Aug 12-Aug 19-Aug 26-Aug 2-Sep 20-Jul 27-Jul 3-Aug18-May 25-May 1-Jun 8-Jun 15-Jun % REMAINING WORK % ACTUAL PROGRESS ACCELERATE PLAN REV.2 CUM. ACTUAL CUM. ACTUAL ACCELERATE PLAN REV.2 Page 5 of 6 Prepared By : Nattakarn S.
  • 12.
    % Actual % Plan% Actual % Var. WHP 505 100.00% 84.94 79.13 -5.81 Noted : 1. This weekly progress status is based on Phase 50 : Project Accelerate Plan Rev.2 0.00 0.00 0.00 -6.56 -0.10 0.850.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.00 0.34 0.73 2.710.44 2.82 2.40 0.66 0.00 2.282.76 2.25 2.06 1.42 4.98 0.070.00 1.30 0.50 0.80 1.93 2.38 VARIANCE 0.00 0.00 0.00 0.00 7.97 8.39 6.051.81 0.00 0.79 3.84 0.21 0.062.18 1.68 1.54 1.54 2.84 3.361.01 0.55 2.31 0.00 0.00 ACTUAL 0.00 0.00 0.00 0.00 0.00 0.14 0.03 0.00 0.00 0.00 0.00 0.00 0.004.03 1.62 7.10 2.30 0.00 0.003.84 0.21 0.06 14.53 8.49 5.201.54 2.84 3.36 1.81 0.00 0.790.34 0.73 2.71 2.18 1.68 1.540.66 0.00 2.28 1.01 0.55 2.311.42 4.98 0.07 0.44 2.82 2.400.80 1.93 2.38 2.76 2.25 2.060.00 0.14 0.03 0.00 1.30 0.50 WEEKLY PLANNED 0.00 0.00 0.00 0.00 -6.66 -5.810.00 0.00 0.00 0.00 0.00 -6.560.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.00VARIANCE 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 56.66 56.72 64.69 73.08 79.1346.65 50.01 51.82 51.82 52.61 56.4534.16 36.87 39.05 40.73 42.27 43.8126.94 29.22 30.23 30.78 33.09 33.4320.55 20.62 21.06 23.88 26.28 26.944.70 7.08 9.84 12.09 14.15 15.570.14 0.17 0.17 1.47 1.97 2.77ACTUAL 0.00 0.00 0.00 0.00 0.00 100.00 100.00 100.00 100.00 100.00 100.0097.70 100.00 100.00 100.00 100.00 100.0056.72 71.25 79.74 84.94 88.97 90.5950.01 51.82 51.82 52.61 56.45 56.6636.87 39.05 40.73 42.27 43.81 46.6529.22 30.23 30.78 33.09 33.43 34.1620.62 21.06 23.88 26.28 26.94 26.947.08 9.84 12.09 14.15 15.57 20.550.17 0.17 1.47 1.97 2.77 4.70 31-Aug 7-Sep CUMULATIVE ACCELERATE PLAN 0.00 0.00 0.00 0.00 0.00 0.14 20-Jul 27-Jul 3-Aug 10-Aug 17-Aug 24-Aug8-Jun 15-Jun 22-Jun 29-Jun 6-Jul 13-Jul27-Apr 4-May 11-May 18-May 25-May 1-Jun16-Mar 23-Mar 30-Mar 6-Apr 13-Apr 20-Apr3-Feb 10-Feb 17-Feb 24-Feb 2-Mar 9-Mar23-Dec 30-Dec 6-Jan 13-Jan 20-Jan 27-Jan11-Nov 18-Nov 25-Nov 2-Dec 9-Dec 16-Dec30-Sep 7-Oct 14-Oct 21-Oct 28-Oct 4-Nov19-Aug 26-Aug 2-Sep 9-Sep 16-Sep 23-Sep E&I AND PRE-COMMISSIONING WORKS PROGRESS 22-Jul 29-Jul 5-Aug 12-Aug 100.00 0.00Site Acceptance Test - SAT 22.20% 0.00 0.00 100.00 Loop/Function Test 77.80% 0.00 0.00 0.00 PRE-COMMISSIONING 9.41% 0.00 0.00 0.00 100.0071.13 0.00Tubing Leak Test 1.18% 0.00 0.00 3.12 3.12 30.133.12 3.12 77.54 94.52 100.003.12 3.12 34.82 58.79 Cable Continuity Check 4.13% 77.54 30.13 -47.41 41.79 43.44 46.19 49.19 49.4027.12 27.12 38.48 38.48 38.48 41.0424.90 24.90 26.07 26.11 26.25 27.123.88 5.12 5.12 5.12 21.07 23.820.44 3.88 3.88 23.82 24.90 24.900.44 3.88 3.88 3.88 5.12 48.99 55.74 63.43 79.26 100.0038.48 38.48 38.48 41.04 41.79 43.4426.07 26.11 26.25 27.12 27.12 27.125.12 5.12 21.07 Installation And Hook-Up of E&I Tag Items 3.29% 63.43 49.40 -14.03 77.1442.79 65.39 36.73 67.22 85.06 100.00 -7.92Tubings Installation 16.56% 85.06 77.14 65.05 80.79 90.9048.02 48.02 50.47 60.14 60.36 60.3620.14 20.65 24.27 24.48 33.36 43.635.70 6.69 8.07 8.07 8.76 14.851.01 2.70 2.73 2.73 4.70 96.62 100.0050.47 60.14 60.36 60.36 83.20 91.5424.27 24.48 33.36 43.63 48.02 48.028.07 8.07 8.76 14.85 20.14 20.652.70 2.73 2.73 4.70 5.70 6.691.01 Cables Installation (Pulling, Glanding ,Termination) 34.40% 96.62 90.90 -5.72 99.56 99.76 99.98 100.0098.08 98.34 99.13 99.13 99.13 99.5690.98 91.32 92.72 95.82 97.44 97.8772.95 76.38 76.99 77.06 86.96 86.9646.59 47.17 47.30 56.96 63.17 72.9533.25 36.89 36.89 37.08 44.60 44.820.78 5.50 86.96 90.98 91.3247.30 56.96 63.17 72.95 72.95 76.3836.89 37.08 44.60 44.82 46.59 47.17 99.77 99.77 100.0099.13 99.13 99.13 99.56 99.56 99.7692.72 95.82 97.44 97.87 98.08 98.3476.99 77.06 86.960.78 5.50 33.25 36.89 Calibration of Instruments Tag 5.37% 100.00 100.00 0.00 100.0097.30 99.61 99.61 99.61 99.61 99.6191.85 96.35 96.56 97.00 97.22 97.2280.96 81.77 82.66 85.16 86.52 90.8270.04 70.59 70.59 75.18 77.29 78.0437.70 48.44 57.56 57.68 59.06 65.416.08 7.88 9.69 16.63 25.32 32.370.44 0.52 0.52 4.63 99.61 99.61 99.99 99.99 100.0096.56 97.00 97.22 97.22 97.30 99.6182.66 85.16 86.52 90.82 91.85 96.3570.59 75.18 77.29 78.04 80.96 81.7757.56 57.68 59.06 65.41 70.04 70.599.69 16.63 25.32 32.37 37.70 48.440.44 0.52 0.52 4.63 6.08 7.88 0.00E&I Supports, Ladders and Trays 35.06% 100.00 100.00 23-Mar E&I 90.59% 93.76 87.35 -6.41 22-Jun 24-Aug 31-Aug 7-Sep3-Feb 10-Feb 17-Feb2-Dec 9-Dec 16-Dec 23-Dec 30-Dec 6-Jan21-Oct 28-Oct 4-Nov 11-Nov 18-Nov 25-Nov 13-Jan 20-Jan 27-Jan 6-Apr 13-Apr 20-Apr 27-Apr 4-May 11-May24-Feb 2-Mar 9-Mar 16-Mar CHEVRON : CVX-PHASE 50 E&I AND PRE-COMMISSIONING : WHP 505 PROGRESS S-CURVE 1-Jun-16 WBS WTG Cumulative Progress 22-Jul 29-Jun 6-Jul 10-Aug 17-Aug 2015 2016 2015 2016 13-Jul30-Mar9-Sep 16-Sep 23-Sep 30-Sep 7-Oct 14-Oct29-Jul 5-Aug 12-Aug 19-Aug 26-Aug 2-Sep 20-Jul 27-Jul 3-Aug18-May 25-May 1-Jun 8-Jun 15-Jun % REMAINING WORK % ACTUAL PROGRESS ACCELERATE PLAN REV.2 CUM. ACTUAL CUM. ACTUAL ACCELERATE PLAN REV.2 Page 6 of 6 Prepared By : Nattakarn S.
  • 13.
    Activity ID ActivityName Num. Budgeted Units Planned Start Planned Finish % Actual 1-Jun-16 L5 L4 L5 L4 L5 L4 1295 3723 14-Aug-15 9-Oct-15 57 501-FAEI-17840 Fabrication of E&I Supports for Sub-Cellar Deck 31 Ea. 50.170 98 2.63% 8-Sep-15 23-Sep-15 16 100.00% 100.00% Completed 501-FAEI-17850 Fabrication of E&I Supports for Cellar Deck 663 Ea. 50.170 1915 51.44% 14-Aug-15 9-Oct-15 57 100.00% 100.00% Completed 501-FAEI-17860 Fabrication of E&I Supports for Mezzanine Deck 243 Ea. 50.170 525 14.10% 2-Sep-15 3-Oct-15 32 100.00% 100.00% Completed 501-FAEI-17870 Fabrication of E&I Supports for Upper Deck 358 Ea. 50.170 1185 31.83% 24-Aug-15 2-Oct-15 40 100.00% 100.00% Completed 4719 9-Sep-15 8-Apr-16 213 1295 3250 9-Sep-15 25-Jan-16 139 31 106 3.26% 8-Dec-15 5-Jan-16 29 100.00% 100.00% 501-FAEI-17880 Installation of E&I Support at Sub-Cellar Deck - Assembly Bay 1 Ea. 50.170 12 11.32% 25-Dec-15 5-Jan-16 12 100.00% 100.00% Completed 501-FAEI-17890 Installation of E&I Support at Sub-Cellar Deck - Erection Area 30 Ea. 50.170 94 88.68% 8-Dec-15 25-Dec-15 18 100.00% 100.00% Completed 663 1614 49.66% 9-Sep-15 21-Nov-15 74 100.00% 100.00% 501-FAEI-17900 Installation of E&I Support at Cellar Deck - Assembly Bay 475 Ea. 50.170 1035 64.13% 9-Sep-15 2-Oct-15 24 100.00% 100.00% Completed 501-FAEI-17910 Installation of E&I Support at Cellar Deck - Erection Area 188 Ea. 50.170 579 35.87% 24-Oct-15 21-Nov-15 29 100.00% 100.00% Completed 243 546 16.80% 29-Sep-15 25-Jan-16 119 100.00% 100.00% 501-FAEI-17920 Installation of E&I Support at Mezzanine Deck - Assembly Bay 37 Ea. 50.170 118 21.61% 29-Sep-15 15-Oct-15 17 100.00% 100.00% Completed 501-FAEI-17930 Installation of E&I Support at Mezzanine Deck - Erection Area 206 Ea. 50.170 428 78.39% 29-Dec-15 25-Jan-16 28 100.00% 100.00% Completed 358 984 30.28% 16-Oct-15 11-Jan-16 88 100.00% 100.00% 501-FAEI-17940 Installation of E&I Support at UpperDeck - Assembly Bay 273 Ea. 50.170 662 67.28% 16-Oct-15 10-Nov-15 26 100.00% 100.00% Completed 501-FAEI-17950 Installation of E&I Support at UpperDeck - Erection Area 85 Ea. 50.170 322 32.72% 13-Nov-15 11-Jan-16 60 100.00% 100.00% Completed 779 1469 24-Oct-15 8-Apr-16 168 501-FAEI-17960 Installation of Cable Trays&Ladders 670 m. 50.170 942 64.13% 24-Oct-15 1-Feb-16 101 100.00% 100.00% Completed 501-FAEI-17970 Installation of Tubing Trays&Ladders 109 m. 50.170 527 35.87% 4-Mar-16 8-Apr-16 36 100.00% 100.00% Completed 8442 0.00% L5 L4 L5 L4 L5 L4 312 905 24-Oct-15 19-Jan-16 88 312 905 24-Oct-15 19-Jan-16 88 501-FAEI-17980 Calibration of Instrument Tags - 01-I1: Process Production 193 Ea. 50.165 535 59.12% 24-Oct-15 18-Dec-15 56 100.00% 100.00% Completed 501-FAEI-17990 Calibration of Instrument Tags - 01-I2 : Production Header 28 Ea. 50.165 76 8.40% 11-Nov-15 24-Nov-15 14 100.00% 100.00% Completed 501-FAEI-18000 Calibration of Instrument Tags - 02-I1 : Test Separator 50 Ea. 50.165 140 15.47% 24-Nov-15 22-Dec-15 29 100.00% 100.00% Completed 501-FAEI-18010 Calibration of Instrument Tags - 03-I1 : Pig Luncher 1 Ea. 50.165 3 0.33% 12-Dec-15 15-Dec-15 4 100.00% 100.00% Completed 501-FAEI-18020 Calibration of Instrument Tags - 03-I2 : Pig Receiver - Option 14 Ea. 50.165 76 8.40% 15-Jan-16 19-Jan-16 5 100.00% 100.00% Completed 501-FAEI-18050 Calibration of Instrument Tags - 10-I1 : Booster Compressor 26 Ea. 50.165 75 8.29% 22-Dec-15 6-Jan-16 16 100.00% 100.00% Completed 14 38 24-Oct-15 13-Nov-15 21 8 22 24-Oct-15 27-Oct-15 4 501-FAEI-18060 Calibration of Instrument Tags - 08-I1 : Closed Drain System 8 Ea. 50.165 22 100.00% 24-Oct-15 27-Oct-15 4 100.00% 100.00% Completed 5 13 9-Nov-15 11-Nov-15 3 501-FAEI-18070 Calibration of Instrument Tags - 09-I1 : Open Drain System 5 Ea. 50.165 13 100.00% 9-Nov-15 11-Nov-15 3 100.00% 100.00% Completed 1 3 11-Nov-15 13-Nov-15 3 501-FAEI-18080 Calibration of Instrument Tags - 06-I1 : HP Vent / LP Vent 1 Ea. 50.165 3 100.00% 11-Nov-15 13-Nov-15 3 100.00% 100.00% Completed 24 68 3-Nov-15 25-Nov-15 23 14 40 13-Nov-15 20-Nov-15 8 501-FAEI-18090 Calibration of Instrument Tags - 04-I1 : Instrument Gas 14 Ea. 50.165 40 100.00% 13-Nov-15 20-Nov-15 8 100.00% 100.00% Completed 10 28 3-Nov-15 25-Nov-15 23 501-FAEI-18100 Calibration of Instrument Tags - 04-I2 : Utility Gas 10 Ea. 50.165 28 100.00% 20-Nov-15 25-Nov-15 6 100.00% 100.00% Completed 21 59 3-Oct-15 20-Oct-15 18 21 59 3-Oct-15 20-Oct-15 18 501-FAEI-18130 Calibration of Instrument Tags - 11-I1 : Chemical Injection 21 Ea. 50.165 59 100.00% 3-Oct-15 15-Oct-15 13 100.00% 100.00% Completed 57 224 25-Sep-15 30-Jan-16 128 51 208 25-Sep-15 12-Dec-15 79 501-FAEI-18150 Calibration of Instrument Tags - 13-C1 : Back Start 3 Ea. 50.165 8 3.85% 11-Dec-15 12-Dec-15 2 100.00% 100.00% Completed 501-FAEI-18160 Calibration of Instrument Tags - 13-C3 : Wellhead Control Panel 48 Ea. 50.165 200 96.15% 25-Sep-15 26-Oct-15 32 100.00% 100.00% Completed 1 3 14-Dec-15 15-Dec-15 2 501-FAEI-18180 Calibration of Instrument Tags - 14-E6 : TEG - Gas Platform 1 Ea. 50.165 3 100.00% 14-Dec-15 15-Dec-15 2 100.00% 100.00% Completed 5 13 29-Jan-16 30-Jan-16 2 501-FAEI-18190 Calibration of Instrument Tags - 17-S3 : Fire & Gas Detector 5 Ea. 50.165 13 100.00% 29-Jan-16 30-Jan-16 2 100.00% 100.00% Completed 428 1294 0.00% 1st 2nd 1st 2nd L5 L4 20.0% 20.0% 7.5% 7.5% L5 L4 L5 L4 305 4601 24-Feb-16 26-Mar-16 32 305 4601 24-Feb-16 26-Mar-16 32 501-FAEI-18200 Cables Installation for 01-I1: Process Production 121 Sch. 50.175 1968 42.77% 29-Feb-16 15-Mar-16 16 121 121 121 121 100.00% 100.00% Completed 501-FAEI-18210 Cables Installation for 01-I2 : Production Header 50 Sch. 50.175 678 14.74% 3-Mar-16 10-Mar-16 8 50 50 50 50 100.00% 100.00% Completed 501-FAEI-18220 Cables Installation for 02-I1 : Test Separator 76 Sch. 50.175 1033 22.45% 8-Mar-16 15-Mar-16 8 76 76 76 76 100.00% 100.00% Completed 501-FAEI-18230 Cables Installation for 03-I2 : Pig Receiver - Option 10 Sch. 50.175 271 5.89% 18-Mar-16 26-Mar-16 9 10 10 10 10 100.00% 100.00% Completed 501-FAEI-18260 Cables Installation for 10-I1 : Booster Compressor 48 Sch. 50.175 651 14.15% 24-Feb-16 11-Mar-16 17 48 48 48 48 100.00% 100.00% Completed 9 124 25-Feb-16 21-Mar-16 26 6 82 17-Mar-16 21-Mar-16 5 501-FAEI-18270 Cables Installation for 08-I1 : Closed Drain System 6 Sch. 50.175 82 100.00% 17-Mar-16 21-Mar-16 5 6 6 6 6 100.00% 100.00% Completed 3 42 25-Feb-16 29-Feb-16 5 501-FAEI-18280 Cables Installation for 09-I1 : Open Drain System 3 Sch. 50.175 42 100.00% 25-Feb-16 29-Feb-16 5 3 3 3 3 100.00% 100.00% Completed 16 217 10-Mar-16 7-Apr-16 29 10 135 25-Mar-16 7-Apr-16 14 501-FAEI-18290 Cables Installation for 04-I1 : Instrument Gas 10 Sch. 50.175 135 100.00% 25-Mar-16 7-Apr-16 14 10 10 10 10 100.00% 100.00% Completed 6 82 10-Mar-16 7-Apr-16 29 501-FAEI-18300 Cables Installation for 04-I2 : Utility Gas 6 Sch. 50.175 82 100.00% 25-Mar-16 7-Apr-16 14 6 6 6 6 100.00% 100.00% Completed 9 125 4-Mar-16 25-Mar-16 22 9 125 4-Mar-16 25-Mar-16 22 501-FAEI-18330 Cables Installation for 11-I1 : Chemical Injection 9 Sch. 50.175 125 100.00% 19-Mar-16 25-Mar-16 7 9 9 9 9 100.00% 100.00% Completed 265 3215 6-Nov-15 16-Apr-16 163 65 776 6-Nov-15 5-Feb-16 92 501-FAEI-18350 Cables Installation for 13-C2 : PLC and Control system 65 Sch. 50.175 776 100.00% 22-Jan-16 5-Feb-16 15 65 65 65 65 100.00% 100.00% Completed 175 2139 13-Nov-15 16-Apr-16 156 501-FAEI-18380 Cables Installation for 14-E2 : AC Diesel Generators 1 Sch. 50.175 16 0.75% 26-Jan-16 2-Feb-16 8 1 1 1 1 100.00% 100.00% Completed 501-FAEI-18390 Cables Installation for 14-E3 : DC Supply 36 Sch. 50.175 368 17.20% 22-Jan-16 12-Feb-16 22 36 36 36 36 100.00% 100.00% Completed 501-FAEI-18400 Cables Installation for 14-E4 : Power & Lighting and Outlet 118 Sch. 50.175 1480 69.19% 13-Nov-15 9-Dec-15 27 118 118 118 118 100.00% 100.00% Completed 501-FAEI-18420 Cables Installation for 14-E6 : TEG - Gas Platform 9 Sch. 50.175 125 5.84% 3-Feb-16 18-Feb-16 16 9 9 9 9 100.00% 100.00% Completed 501-FAEI-18430 Cables Installation for 16-E1 : Navigation Aids System 11 Sch. 50.175 150 7.01% 22-Jan-16 10-Feb-16 20 11 11 11 11 100.00% 100.00% Completed 14 150 5-Feb-16 27-Feb-16 23 501-FAEI-18440 Cables Installation for 15-T1 : Comunication System 14 Sch. 50.175 150 100.00% 5-Feb-16 27-Feb-16 23 14 12 14 12 96.07% 100.00% Delayed 11 150 22-Jan-16 12-Feb-16 22 501-FAEI-18450 Cables Installation for 17-S2 : Emergency Shutdown 2 Sch. 50.175 27 18.00% 22-Jan-16 25-Jan-16 4 2 2 2 2 100.00% 100.00% Completed 501-FAEI-18460 Cables Installation for 17-S3 : Fire & Gas Detector 5 Sch. 50.175 68 45.33% 22-Jan-16 25-Jan-16 4 5 5 5 5 100.00% 100.00% Completed 501-FAEI-18470 Cables Installation for 17-S4 : Beacon Light & Siren 4 Sch. 50.175 55 36.67% 5-Feb-16 12-Feb-16 8 4 4 4 4 100.00% 100.00% Completed 604 8282 604 602 604 602 -0.07% L5 L4 L5 L4 L5 L4 305 531 9-Apr-16 9-May-16 31 305 531 9-Apr-16 9-May-16 31 501-FAEI-18480 Cables Continuity Check for 01-I1: Process Production 121 Sch. 50.180 218 41.05% 29-Apr-16 9-May-16 11 99.94% 100.00% Delayed 501-FAEI-18490 Cables Continuity Check for 01-I2 : Production Header 50 Sch. 50.180 75 14.12% 29-Apr-16 3-May-16 5 92.65% 100.00% Delayed 501-FAEI-18500 Cables Continuity Check for 02-I1 : Test Separator 76 Sch. 50.180 135 25.42% 3-May-16 7-May-16 5 93.50% 100.00% Delayed 501-FAEI-18510 Cables Continuity Check for 03-I2 : Pig Receiver - Option 10 Sch. 50.180 31 5.84% 4-May-16 6-May-16 3 92.50% 100.00% Delayed 501-FAEI-18540 Cables Continuity Check for 10-I1 : Booster Compressor 48 Sch. 50.180 72 13.56% 6-May-16 9-May-16 4 92.50% 100.00% Delayed 9 13 29-Apr-16 3-May-16 5 6 9 29-Apr-16 3-May-16 5 501-FAEI-18550 Cables Continuity Check for 08-I1 : Closed Drain System 6 Sch. 50.180 9 100.00% 29-Apr-16 3-May-16 5 96.67% 100.00% Delayed 3 4 29-Apr-16 3-May-16 5 501-FAEI-18560 Cables Continuity Check for 09-I1 : Open Drain System 3 Sch. 50.180 4 100.00% 29-Apr-16 3-May-16 5 96.67% 100.00% Delayed 16 24 7-Apr-16 9-May-16 33 10 15 3-May-16 6-May-16 4 501-FAEI-18570 Cables Continuity Check for 04-I1 : Instrument Gas 10 Sch. 50.180 15 100.00% 3-May-16 6-May-16 4 98.50% 100.00% Delayed 6 9 7-Apr-16 9-May-16 33 501-FAEI-18580 Cables Continuity Check for 04-I2 : Utility Gas 6 Sch. 50.180 9 100.00% 6-May-16 9-May-16 4 92.17% 100.00% Delayed 9 18 9-Apr-16 10-May-16 32 9 18 9-Apr-16 10-May-16 32 501-FAEI-18610 Cables Continuity Check for 11-I1 : Chemical Injection 9 Sch. 50.180 18 100.00% 7-May-16 10-May-16 4 100.00% 100.00% Completed 265 409 26-Mar-16 7-May-16 43 65 59 30-Apr-16 6-May-16 7 501-FAEI-18630 Cables Continuity Check for 13-C2 : PLC and Control system 65 Sch. 50.180 59 100.00% 3-May-16 6-May-16 4 75.67% 100.00% Delayed 175 254 26-Mar-16 7-May-16 43 501-FAEI-18660 Cables Continuity Check for 14-E2 : AC Diesel Generators 1 Sch. 50.180 3 1.18% 4-May-16 6-May-16 3 100.00% 100.00% Completed 501-FAEI-18670 Cables Continuity Check for 14-E3 : DC Supply 36 Sch. 50.180 26 10.24% 26-Apr-16 28-Apr-16 3 100.00% 100.00% Completed 501-FAEI-18680 Cables Continuity Check for 14-E4 : Power & Lighting and Outlet 118 Sch. 50.180 196 77.17% 22-Apr-16 28-Apr-16 7 93.63% 100.00% Delayed 501-FAEI-18700 Cables Continuity Check for 14-E6 : TEG - Gas Platform 9 Sch. 50.180 13 5.12% 3-May-16 4-May-16 2 95.56% 100.00% Delayed 501-FAEI-18710 Cables Continuity Check for 16-E1 : Navigation Aids System 11 Sch. 50.180 16 6.30% 4-May-16 7-May-16 4 100.00% 100.00% Completed 14 74 4-May-16 7-May-16 4 501-FAEI-18720 Cables Continuity Check for 15-T1 : Comunication System 14 Sch. 50.180 74 100.00% 4-May-16 7-May-16 4 71.21% 100.00% Delayed 11 22 29-Apr-16 7-May-16 9 501-FAEI-18730 Cables Continuity Check for 17-S2 : Emergency Shutdown 2 Sch. 50.180 3 13.64% 29-Apr-16 30-Apr-16 2 92.50% 100.00% Delayed 501-FAEI-18740 Cables Continuity Check for 17-S3 : Fire & Gas Detector 5 Sch. 50.180 12 54.55% 4-May-16 7-May-16 4 92.50% 100.00% Delayed 501-FAEI-18750 Cables Continuity Check for 17-S4 : Beacon Light & Siren 4 Sch. 50.180 7 31.82% 4-May-16 7-May-16 4 92.50% 100.00% Delayed 604 995 -7.42% L5 L4 L5 L4 L5 L4 339 508 29-Mar-16 3-May-16 36 72 112 1-Apr-16 4-Apr-16 4 72 112 1-Apr-16 4-Apr-16 4 501-FAEI-18760 Tubings Installation for 06-I1 : HP Vent / LP Vent 72 m. 50.175 112 100.00% 1-Apr-16 4-Apr-16 4 93.00% 100.00% Delayed 189 153 29-Mar-16 8-Apr-16 11 189 153 29-Mar-16 8-Apr-16 11 501-FAEI-18770 Tubings Installation for 11-I1 : Chemical Injection 189 m. 50.175 153 100.00% 7-Apr-16 8-Apr-16 2 93.00% 100.00% Delayed 78 243 9-Apr-16 3-May-16 25 69 122 9-Apr-16 12-Apr-16 4 501-FAEI-18790 Tubings Installation for 13-C1 : Back Start 69 m. 50.175 122 100.00% 9-Apr-16 12-Apr-16 4 90.00% 100.00% Delayed 9 121 29-Apr-16 3-May-16 5 501-FAEI-18800 Tubings Installation for 14-E6 : TEG - Gas Platform 9 m. 50.175 20 16.53% 29-Apr-16 29-Apr-16 1 91.50% 100.00% Delayed 3478 12-Feb-16 16-Apr-16 65 2874 870 12-Feb-16 26-Feb-16 15 501-FAEI-18820 Pre-Cutting and Pre-Bending 2874 m. 50.175 870 100.00% 12-Feb-16 26-Feb-16 15 100.00% 100.00% Completed 2535 2608 18-Mar-16 16-Apr-16 30 483 227 24-Mar-16 5-Apr-16 13 483 227 24-Mar-16 5-Apr-16 13 501-FAEI-18840 Tubings Installation for 01-I1: Process Production 456 m. 50.175 195 85.90% 24-Mar-16 26-Mar-16 3 91.50% 100.00% Delayed 501-FAEI-18850 Tubings Installation for 10-I1 : Booster Compressor 27 m. 50.175 32 14.10% 28-Mar-16 5-Apr-16 9 100.00% 100.00% Completed 2052 2381 18-Mar-16 16-Apr-16 30 1273 1529 18-Mar-16 16-Apr-16 30 501-FAEI-18860 Tubings Installation for 13-C3 : Wellhead Control Panel 1273 m. 50.175 1529 100.00% 18-Mar-16 16-Apr-16 30 93.25% 100.00% Delayed 779 852 18-Mar-16 11-Apr-16 25 501-FAEI-18870 Tubings Installation for 17-S1 : Fire Emergency Shutdown (FESD) 531 m. 50.175 579 67.96% 18-Mar-16 4-Apr-16 18 100.00% 100.00% Completed 501-FAEI-18880 Tubings Installation for 17-S2 : Emergency Shutdown 248 m. 50.175 273 32.04% 25-Mar-16 11-Apr-16 18 95.00% 100.00% Delayed 2874 3986 -4.16% L5 L4 L5 L4 L5 L4 339 102 10-May-16 23-May-16 14 72 9 12-May-16 14-May-16 3 72 9 12-May-16 14-May-16 3 501-FAEI-18890 Tubings Leak Test for 06-I1 : HP Vent / LP Vent 72 m. 50.180 9 100.00% 12-May-16 14-May-16 3 100.00% 100.00% Completed 189 50 10-May-16 23-May-16 14 % Actual %Plan L3 L3 L3 49.02% 95.33% 100.00% 100.00% Status Next 2 Wks As Per Planed RemarkL3 Start Finish Dur. Tested Check Sheet : PLT-T L3 L3 90% 10% Bare Tube Leak Test 35.92% 95.93% 100.00% TUBINGS LEAK TEST QTY Unit Cost Code Budgeted Mhrs WTG% Baseline Activity Milestones % Actual %Plan 100.00% Sub-System - 2001 : Closed Drain (DC) System - 2000 : Drains & Reliefs 8.82% 100.00% Sub-System - 2500 : Blow Down (BD) 100.00% 100.00% 100.00% 72 100.00% System - 7000 : Chemicals Sub-System - 8000D : Safety Intrergrity System (SIS) 35.78% 98.40% 100.00% 531 100.00% 248 50.00% SUB-TOTAL OF TUBINGS INSTALLATION 16.56% 2874 95.84% 100.00% 456 15.00% 27 100.00% System - 8000 : Others 91.30% 95.09% 100.00% Sub-System - 8000A : Process Control 64.22% 93.25% 100.00% 1273 32.50% 2874 Field Installation and Hook-Up 74.99% 94.88% 100.00% System - 1000 : Process Production 8.70% 92.70% 100.00% Sub-System - 1001 : Process Liquid & Vapour (P) 100.00% 92.70% 100.00% 98.60% 100.00% 9 15.00% TPU Jacket Tube Installation 87.26% 96.16% 100.00% Preparation Works 25.01% 100.00% 100.00% 93.00% 100.00% 189 30.00% System - 8000 : Others 47.83% 94.28% 100.00% Sub-System - 8000A : Process Control 50.21% 90.00% 100.00% 93.61% 100.00% System - 2000 : Drains & Reliefs 22.05% 93.00% 100.00% Sub-System - 2500 : Blow Down (BD) 100.00% 93.00% 100.00% System - 7000 : Chemicals 30.12% 93.00% 100.00% % Actual %Plan Status Next 2 Wks As Per Planed RemarkL3 Start Finish Dur. Tube Running Check Sheet : PIC-T L3 L3 90% 10% TUBINGS INSTALLATION QTY Unit Cost Code Budgeted Mhrs WTG% Baseline Activity Milestones Bare Tube Installation 12.74% Sub-System - 7001 : Chemical (C) 100.00% 69 Sub-System - 8000B : Electrical Generation and Distribution 49.79% 11 2 4 25.00% 100.00% 3 6 99.38% 50 26.50% 76 110 121 % Actual 604 72 30.00% 100.00% 100.00% 6 Unit Unit Unit TerminatedGlanded 45% 36 26 100.00% 8 100.00% 100.00% 48 100.00% 1 100.00% 5 100.00% Tested Check Sheet : PLT-C 90% 10% 50.58% 3 579 1.31% 5 11 9 55.56% 11 65 193 100.00% 28 100.00% 1 100.00% 14 100.00% 14 100.00% 10 100.00% 10 9 48 206 206 9 100.00% 1 100.00% 66.67% 66.67% 85.00% 6 21.67% 100.00% 97.32% 3 50 100.00% 100.00% 1 100.00% 1 25.00% 5.00% 36 Budgeted Mhrs WTG% Baseline Activity Milestones 35.00% 10 25.00% WHP 50/1 : GAS PLATFORM : E&I INSTALLATION 38.82% System - 4000 : Utility Generals Sub-System - 4400 : Gas Instrument (GI) Sub-System - 4500 : Gas Utility (GU) System - 8000 : Others System - 7000 : Chemicals Sub-System - 7001 : Chemical (C) 100.00% 37.79% 1.51% System - 2000 : Drains & Reliefs 10 1.50% 100.00% 100.00% 100.00% Sub-System - 2100 : Open Drain (DO) Activity Milestones System - 1000 : Process Production CABLES INSTALLATION Baseline 55.55% 50 76 Sub-System - 8000D : Safety Intrergrity System (SIS) CHEVRON : CVX-PHASE 50 PROGRESS MEASUREMENT WORK SHEET FOR E&I AND PRE-COMMISSIONING WORKS WHP 50/1 : GAS PLATFORM Next 2 Wks As Per Planed Sub-System - 1001 : Process Liquid & Vapour (P) Status Remark 100.00% 100.00% 100.00% 100.00% 100.00% Fabricated/Installed 90% Accepted /Painted/Cleaning Status Next 2 Wks As Per Planed RemarkL3 Start Finish Dur. L3 L3 188 188 37 WTG% Baseline 100.00% 100.00% 100.00% 62.21% 100.00% 99.93% Sub-System - 8000A : Process Control Sub-System - 8000B : Electrical Generation and Distribution SUB-TOTAL OF CABLES INSTALLATION 100.00% 100.00% 66.13% 33.87% 24.14% Sub-System - 2001 : Closed Drain (DC) 118 9 2.62% 4 14 2 5 6 96.07% 34.40% System - 1000 : Process Production 69.94% Sub-System - 1001 : Process Liquid & Vapour (P) 100.00% 100.00% 100.00% % Actual %Plan CALIBRATION OF INSTRUMENTS TAG QTY Budgeted Mhrs 428 90% 10% Calibrated Check Sheet : PCC Sub-System - 2100 : Open Drain (DO) 34.21% 100.00% 100.00% System - 2000 : Drains & Reliefs 2.94% Sub-System - 2001 : Closed Drain (DC) 57.89% 100.00% 100.00% Sub-System - 4400 : Gas Instrument (GI) 58.82% 100.00% 100.00% System - 4000 : Utility Generals 5.26% 7.89%Sub-System - 2500 : Blow Down (BD) 100.00% 100.00% 100.00% Sub-System - 4500 : Gas Utility (GU) 41.18% 100.00% 100.00% System - 8000 : Others 17.31% Sub-System - 8000A : Process Control 92.86% 100.00% 100.00% System - 7000 : Chemicals 4.56% Sub-System - 7001 : Chemical (C) 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 21 100.00% Sub-System - 8000D : Safety Intrergrity System (SIS) 5.80% 100.00% 100.00% Sub-System - 8000B : Electrical Generation and Distribution 1.34% 100.00% 100.00% 100.00%SUB-TOTAL OF CALIBRATION OF INSTRUMENTS TAG 5.37% 100.00% 100.00% Budgeted Mhrs Dur. QTY 100.00% 100.00% 100.00% 100.00% 121 Pulled 100.00% 100.00% WTG% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 95.83% Sub-System - 1001 : Process Liquid & Vapour (P) 100.00% 95.83% 100.00% Sub-System - 2100 : Open Drain (DO) 30.77% 96.67% System - 2000 : Drains & Reliefs SUB-TOTAL OF CABLES CONTINUITY & INSULATION TEST 4.13% 92.58% 69.23% 96.67% 100.00% 10 25.00% 48 62.10% 5 25.00% 51 96.67% Status Next 2 Wks As Per Planed RemarkL3 Start Finish Dur. L3 L3 %Plan 100.00% Fabrication 44.10% 100.00% 100.00% 92.17% 100.00% System - 4000 : Utility Generals 2.41% 96.13% 100.00% Sub-System - 4400 : Gas Instrument (GI) 62.50% 98.50% 100.00% 4.67% 100.00% E&I SUPPORTS, LADDERS AND TRAYS QTY Budgeted Mhrs Cellar Deck 100.00% Installation of E&I Supports 66.53% 4.67% 100.00% 100.00% Start Finish 100.00% 99.82% 100.00% 68.87% 100.00% 100.00% Sub-Cellar Deck Installation 55.90% 100.00% 670 670 109 109 Sub-System - 8000C : Communication 100.00% Status Next 2 Wks As Per Planed % Actual 10% 31 31 663 663 243 243 358 358 %Plan RemarkL3 Start Finish Dur. L3 L3 WTG% Baseline Activity Milestones 100.00% 100.00% Mezzanine Deck Upper Deck Installation of E&I Trays&Ladders 31.13% 100.00% 100.00% QTY SUB-TOTAL OF E&I SUPPORTS, LADDERS AND TRAYS 35.06% System - 1000 : Process Production 53.37% 100.00% 100.00%Sub-System - 8000D : Safety Intrergrity System (SIS) 5.38% 92.50% 41.11% 94.86% 87.69% 100.00% Sub-System - 8000A : Process Control 14.43% 75.67% 100.00% Sub-System - 8000B : Electrical Generation and Distribution Cost Code Cost Code Cost Code Cost Code 100.00% Sub-System - 8000C : Communication 18.09% 71.21% 100.00% System - 7000 : Chemicals 1.81% Sub-System - 4500 : Gas Utility (GU) 37.50% 100.00% 100.00% Sub-System - 7001 : Chemical (C) 100.00% 100.00% 100.00% System - 8000 : Others CABLES CONTINUITY & INSULATION TEST Unit 273 273 85 85 Activity Milestones 1 1 30 30 475 475 37 Page 1 of 10 Prepared By : Nattakarn S.
  • 14.
    Activity ID ActivityName Num. Budgeted Units Planned Start Planned Finish % Actual 1-Jun-16 CHEVRON : CVX-PHASE 50 PROGRESS MEASUREMENT WORK SHEET FOR E&I AND PRE-COMMISSIONING WORKS WHP 50/1 : GAS PLATFORM 189 50 10-May-16 23-May-16 14 501-FAEI-18900 Tubings Leak Test for 11-I1 : Chemical Injection 189 m. 50.180 50 100.00% 10-May-16 13-May-16 4 95.33% 100.00% Delayed 78 43 10-May-16 14-May-16 5 69 21 10-May-16 13-May-16 4 501-FAEI-18920 Tubings Leak Test for 13-C1 : Back Start 69 m. 50.180 21 100.00% 10-May-16 13-May-16 4 95.00% 100.00% Delayed 9 22 13-May-16 14-May-16 2 501-FAEI-18930 Tubings Leak Test for 14-E6 : TEG - Gas Platform 9 m. 50.180 11 50.00% 13-May-16 14-May-16 2 93.00% 100.00% Delayed 2535 182 10-May-16 16-May-16 7 483 56 13-May-16 16-May-16 4 483 56 13-May-16 16-May-16 4 501-FAEI-18950 Tubings Leak Test for 01-I1: Process Production 456 m. 50.180 45 80.36% 13-May-16 16-May-16 4 96.50% 100.00% Delayed 501-FAEI-18960 Tubings Leak Test for Booster Compressor 27 m. 50.180 11 19.64% 13-May-16 14-May-16 2 100.00% 100.00% Completed 2052 126 10-May-16 14-May-16 5 1273 90 10-May-16 13-May-16 4 501-FAEI-18970 Tubings Leak Test for 13-C3 : Wellhead Control Panel 1273 m. 50.180 90 100.00% 10-May-16 13-May-16 4 95.75% 100.00% Delayed 779 36 13-May-16 14-May-16 2 501-FAEI-18980 Tubings Leak Test for 17-S1 : Fire Emergency Shutdown (FESD) 531 m. 50.180 18 50.00% 13-May-16 14-May-16 2 93.00% 100.00% Delayed 501-FAEI-18990 Tubings Leak Test for 17-S2 : Emergency Shutdown 248 m. 50.180 18 50.00% 13-May-16 14-May-16 2 93.00% 100.00% Delayed 2874 284 -4.25% L5 L4 L5 L4 L5 L4 271 363 31-Mar-16 31-May-16 62 271 363 31-Mar-16 31-May-16 62 501-FAEI-19000 Hook-Up of E&I Tags for 01-I1: Process Production 145 Ea. 50.175 148 40.77% 4-May-16 31-May-16 28 96.43% 100.00% Delayed 501-FAEI-19010 Hook-Up of E&I Tags for 01-I2 : Production Header 28 Ea. 50.175 43 11.85% 31-Mar-16 29-Apr-16 30 99.64% 100.00% Delayed 501-FAEI-19020 Hook-Up of E&I Tags for 02-I1 : Test Separator 52 Ea. 50.175 75 20.66% 20-Apr-16 9-May-16 20 99.60% 100.00% Delayed 501-FAEI-19030 Hook-Up of E&I Tags for 03-I1 : Pig Luncher 1 Ea. 50.175 1 0.28% 4-May-16 19-May-16 16 90.00% 100.00% Delayed 501-FAEI-19040 Hook-Up of E&I Tags for 03-I2 : Pig Receiver - Option 18 Ea. 50.175 55 15.15% 16-May-16 25-May-16 10 93.33% 100.00% Delayed 501-FAEI-19070 Hook-Up of E&I Tags for 10-I1 : Booster Compressor 27 Ea. 50.175 41 11.29% 7-Apr-16 27-Apr-16 21 99.62% 100.00% Delayed 15 22 16-Apr-16 19-May-16 34 9 13 16-Apr-16 25-Apr-16 10 501-FAEI-19080 Hook-Up of E&I Tags for 08-I1 : Closed Drain System 9 Ea. 50.175 13 100.00% 16-Apr-16 25-Apr-16 10 98.89% 100.00% Delayed 5 8 9-May-16 12-May-16 4 501-FAEI-19090 Hook-Up of E&I Tags for 09-I1 : Open Drain System 5 Ea. 50.175 8 100.00% 9-May-16 12-May-16 4 98.00% 100.00% Delayed 1 1 12-May-16 19-May-16 8 501-FAEI-19100 Hook-Up of E&I Tags for 06-I1 : HP Vent / LP Vent 1 Ea. 50.175 1 100.00% 12-May-16 19-May-16 8 90.00% 100.00% Delayed 28 41 30-Mar-16 9-Apr-16 11 17 23 30-Mar-16 7-Apr-16 9 501-FAEI-19110 Hook-Up of E&I Tags for 04-I1 : Instrument Gas 17 Ea. 50.175 23 100.00% 30-Mar-16 7-Apr-16 9 98.59% 100.00% Delayed 11 18 1-Apr-16 9-Apr-16 9 501-FAEI-19120 Hook-Up of E&I Tags for 04-I2 : Utility Gas 11 Ea. 50.175 18 100.00% 1-Apr-16 9-Apr-16 9 98.18% 100.00% Delayed 24 35 7-Apr-16 24-May-16 48 24 35 7-Apr-16 24-May-16 48 501-FAEI-19150 Hook-Up of E&I Tags for 11-I1 : Chemical Injection 24 Ea. 50.175 35 100.00% 7-Apr-16 18-Apr-16 12 98.48% 100.00% Delayed 230 332 26-Dec-15 13-May-16 140 67 226 26-Mar-16 11-May-16 47 501-FAEI-19170 Hook-Up of E&I Tags for 13-C1 : Back Start 4 Ea. 50.175 7 3.10% 26-Mar-16 31-Mar-16 6 100.00% 100.00% Completed 501-FAEI-19180 Hook-Up of E&I Tags for 13-C2 : PLC and Control system 14 Ea. 50.175 22 9.73% 23-Apr-16 7-May-16 15 99.53% 100.00% Delayed 501-FAEI-19190 Hook-Up of E&I Tags for 13-C3 : Wellhead Control Panel 49 Ea. 50.175 197 87.17% 23-Apr-16 11-May-16 19 100.00% 100.00% Completed 132 60 26-Dec-15 6-May-16 133 501-FAEI-19210 Hook-Up of E&I Tags for 14-E2 : AC Diesel Generators 1 Ea. 50.175 1 1.67% 26-Apr-16 4-May-16 9 100.00% 100.00% Completed 501-FAEI-19220 Hook-Up of E&I Tags for 14-E3 : DC Supply 7 Ea. 50.175 10 16.67% 17-Feb-16 25-Feb-16 9 98.60% 100.00% Delayed 501-FAEI-19230 Hook-Up of E&I Tags for 14-E4 : Power & Lighting and Outlet 110 Ea. 50.175 28 46.67% 26-Dec-15 2-Feb-16 39 96.86% 100.00% Delayed 501-FAEI-19250 Hook-Up of E&I Tags for 14-E6 : TEG - Gas Platform 5 Ea. 50.175 8 13.33% 5-Apr-16 18-Apr-16 14 97.50% 100.00% Delayed 501-FAEI-19260 Hook-Up of E&I Tags for 16-E1 : Navigation Aids System 9 Ea. 50.175 13 21.67% 25-Feb-16 4-Mar-16 9 100.00% 100.00% Completed 5 7 8-Feb-16 15-Feb-16 8 501-FAEI-19270 Hook-Up of E&I Tags for 15-T1 : Comunication System 5 Ea. 50.175 7 100.00% 8-Feb-16 15-Feb-16 8 100.00% 100.00% Completed 26 39 5-Apr-16 13-May-16 39 501-FAEI-19280 Hook-Up of E&I Tags for 17-S2 : Emergency Shutdown 10 Ea. 50.175 13 33.33% 25-Apr-16 7-May-16 13 98.89% 100.00% Delayed 501-FAEI-19290 Hook-Up of E&I Tags for 17-S3 : Fire & Gas Detector 5 Ea. 50.175 8 20.51% 5-Apr-16 12-Apr-16 8 98.60% 100.00% Delayed 501-FAEI-19300 Hook-Up of E&I Tags for 17-S4 : Beacon Light & Siren 11 Ea. 50.175 18 46.15% 4-May-16 13-May-16 10 100.00% 100.00% Completed 568 793 -1.62% 24076 -1.12% L5 L4 L5 L4 L5 L4 704 24-May-16 27-May-16 4 61 704 24-May-16 27-May-16 4 61 704 24-May-16 27-May-16 4 501-FAPC-19910 Fuction Test of 14-E2 : AC Diesel Generators 4 Pac. 60.220 71 10.09% 24-May-16 25-May-16 2 90.00% 100.00% Delayed 501-FAPC-19920 Fuction Test of 14-E3 : DC Supply 19 Pac. 60.220 174 24.72% 24-May-16 25-May-16 2 90.00% 100.00% Delayed 501-FAPC-19930 Fuction Test of 14-E4 : Power & Lighting and Outlet 23 Pac. 60.220 322 45.74% 24-May-16 25-May-16 2 90.00% 100.00% Delayed 501-FAPC-19950 Fuction Test of 14-E6 : TEG - Gas Platform 7 Pac. 60.220 21 2.98% 26-May-16 26-May-16 1 90.00% 100.00% Delayed 501-FAPC-19960 Fuction Test of 16-E1 : Navigation Aids System 8 Pac. 60.220 116 16.48% 24-May-16 25-May-16 2 90.00% 100.00% Delayed 1241 24-May-16 28-May-16 5 205 823 25-May-16 28-May-16 4 205 823 25-May-16 28-May-16 4 501-FAPC-19980 Loop Test of 01-I1: Process Production 97 Pac. 60.225 340 41.31% 25-May-16 26-May-16 2 90.00% 100.00% Delayed 501-FAPC-19990 Loop Test of 01-I2 : Production Header 26 Pac. 60.225 94 11.42% 26-May-16 27-May-16 2 90.00% 100.00% Delayed 501-FAPC-20000 Loop Test of 02-I1 : Test Separator 45 Pac. 60.225 191 23.21% 26-May-16 27-May-16 2 90.00% 100.00% Delayed 501-FAPC-20010 Loop Test of 03-I2 : Pig Receiver - Option 6 Pac. 60.225 42 5.10% 26-May-16 26-May-16 1 90.00% 100.00% Delayed 501-FAPC-20040 Loop Test of 10-I1 : Booster Compressor 31 Pac. 60.225 156 18.96% 27-May-16 28-May-16 2 90.00% 100.00% Delayed 9 32 26-May-16 26-May-16 1 6 21 26-May-16 26-May-16 1 501-FAPC-20050 Loop Test of 08-I1 : Closed Drain System 6 Pac. 60.225 21 100.00% 26-May-16 26-May-16 1 90.00% 100.00% Delayed 3 11 26-May-16 26-May-16 1 501-FAPC-20060 Loop Test of 09-I1 : Open Drain System 3 Pac. 60.225 11 100.00% 26-May-16 26-May-16 1 90.00% 100.00% Delayed 14 32 26-May-16 26-May-16 1 9 21 26-May-16 26-May-16 1 501-FAPC-20070 Loop Test of 04-I1 : Instrument Gas 9 Pac. 60.225 21 100.00% 26-May-16 26-May-16 1 90.00% 100.00% Delayed 5 11 26-May-16 26-May-16 1 501-FAPC-20080 Loop Test of 04-I2 : Utility Gas 5 Pac. 60.225 11 100.00% 26-May-16 26-May-16 1 90.00% 100.00% Delayed 9 32 26-May-16 26-May-16 1 9 32 26-May-16 26-May-16 1 501-FAPC-20110 Loop Test of 11-I1 : Chemical Injection 9 Pac. 60.225 32 100.00% 26-May-16 26-May-16 1 90.00% 100.00% Delayed 97 322 24-May-16 25-May-16 2 81 187 25-May-16 25-May-16 1 501-FAPC-20130 Loop Test of 13-C3 : Wellhead Control Panel 81 Pac. 60.225 187 100.00% 25-May-16 25-May-16 1 90.00% 100.00% Delayed 1 4 24-May-16 24-May-16 1 501-FAPC-20140 Loop Test of 15-T1 : Comunication System 1 Pac. 60.225 4 100.00% 24-May-16 24-May-16 1 90.00% 100.00% Delayed 15 131 25-May-16 25-May-16 1 501-FAPC-20150 Loop Test of 17-S2 : Emergency Shutdown 3 Pac. 60.225 12 9.16% 25-May-16 25-May-16 1 90.00% 100.00% Delayed 501-FAPC-20160 Loop Test of 17-S3 : Fire & Gas Detector 5 Pac. 60.225 28 21.37% 25-May-16 25-May-16 1 90.00% 100.00% Delayed 501-FAPC-20170 Loop Test of 17-S4 : Beacon Light & Siren 7 Pac. 60.225 91 69.47% 25-May-16 25-May-16 1 90.00% 100.00% Delayed 395 1945 -10.00% L5 L4 L5 L4 L5 L4 501-FAPC-20180 Platform Site Acceptance Test - SAT 100 Pac. 60.235 555 30-May-16 4-Jun-16 6 Delayed Should be finished 100 555 -50.00% 2500 -18.88% -2.79% System - 8000 : Others 69.23% 94.96% 100.00% SUB-TOTAL OF TUBINGS LEAK TEST Sub-System - 8000A : Process Control 71.43% 95.75% 100.00% 1273 57.50% Sub-System - 8000D : Safety Intrergrity System (SIS) 28.57% 93.00% 100.00% 531 30.00% 248 30.00% 95.75% 100.00% System - 1000 : Process Production 30.77% 97.19% 100.00% Sub-System - 1001 : Process Liquid & Vapour (P) 100.00% 97.19% 100.00% Sub-System - 8000A : Process Control 48.84% 95.00% 100.00% 69 50.00% Sub-System - 8000B : Electrical Generation and Distribution 51.16% 96.50% 100.00% TPU Jacket Tube Leak Test 64.08% 95.65% 100.00% Sub-System - 7001 : Chemical (C) 100.00% 95.33% 100.00% System - 8000 : Others 42.16% 95.77% 100.00% SUB-TOTAL OF HOOK-UP OF E&I TAG ITEMS 98.38% 100.00% 100.00% Sub-System - 8000D : Safety Intrergrity System (SIS) 99.34% 9 30.00% 456 65.00% 53.33% 11.75% 100.00% Unit 189 28 96.43% 52 27 Unit 7 9 64.33% 28 18 18 33.33% 86.00% 5 5 86.00% 3.29% 4 90% 10% 4.55% 52 96.00% 1 1 9 31 6 5 81 27 27 96.15% System - 1000 : Process Production 66.32% System - 8000 : Others 41.87% 1.18% 90.00% 100.00% Sub-System - 8000C : Communication 1.24% 90.00% 100.00% Sub-System - 8000D : Safety Intrergrity System (SIS) 40.68% 90.00% 100.00% 395 1 3 5 SUB-TOTAL OF LOOP/ FUNCTION TEST 77.80% 90.00% 100.00% System - 8000 : Others 25.95% 90.00% 100.00% Sub-System - 8000A : Process Control 58.07% 90.00% 100.00% System - 7000 : Chemicals 2.58% 90.00% 100.00% Sub-System - 7001 : Chemical (C) 100.00% 90.00% 100.00% Sub-System - 4400 : Gas Instrument (GI) 65.63% 90.00% 100.00% Sub-System - 4500 : Gas Utility (GU) 34.38% 90.00% 100.00% Sub-System - 2001 : Closed Drain (DC) 65.63% 90.00% 100.00% Sub-System - 2100 : Open Drain (DO) 34.38% 90.00% 100.00% 3 System - 4000 : Utility Generals 2.58% %Plan 90.00% 100.00% Sub-System - 1001 : Process Liquid & Vapour (P) 100.00% 90.00% 100.00% System - 2000 : Drains & Reliefs 2.58% 90.00% 100.00% Status 97 26 45 6 Tested Check Sheet : PLT-L & PFTUnit System - 8000 : Others 100.00% Sub-System - 8000C : Communication 2.11% 100.00% Sub-System - 8000B : Electrical Generation and Distribution 18.07% 97.97% 100.00% Next 2 Wks As Per Planed RemarkL3 Start Finish Dur. L3 L3LOOP/ FUNCTION TEST QTY Budgeted Mhrs WTG% Baseline Activity Milestones % Actual 99.52% 100.00% Sub-System - 8000A : Process Control 68.07% 99.95% 100.00% System - 7000 : Chemicals 4.41% 98.48% 100.00% Sub-System - 7001 : Chemical (C) 100.00% 98.48% 100.00% 24 24 84.78% Sub-System - 4400 : Gas Instrument (GI) 56.10% 98.59% 100.00% Sub-System - 4500 : Gas Utility (GU) 43.90% 98.18% 100.00% 17 17 85.88% 11 11 81.82% 90.00% 100.00% System - 4000 : Utility Generals 5.17% 98.41% 100.00% 98.16% 100.00% Sub-System - 2001 : Closed Drain (DC) 59.09% 98.89% 100.00% Sub-System - 2100 : Open Drain (DO) 36.36% 98.00% 100.00% System - 2000 : Drains & Reliefs 2.77% 1 1 9 9 88.89% 5 5 80.00% Status Next 2 Wks As Per Planed RemarkL3 Start Finish Dur. L3 L3 WTG% Baseline Activity Milestones % Actual %Plan 60% 30% 10% Installed Hook-Up Check Sheet : PIC-H TOTAL OF WHP 50/1 : GAS PLATFORM : E&I INSTALLATION 90.59% 98.88% 100.00% WHP 50/1 : GAS PLATFORM : E&I PRE-COMMISSIONING System - 1000 : Process Production 45.78% 97.34% QTY Budgeted Mhrs 81.12% 100.00% 50.00% SUB-TOTAL OF SITE ACCEPTANC TEST - SAT 22.20% 50.00% 100.00% 50 100.00% Sub-System - 1001 : Process Liquid & Vapour (P) 100.00% 97.34% 100.00% HOOK-UP OF E&I TAG ITEMS Sub-System - 2500 : Blow Down (BD) Status Next 2 Wks As Per Planed RemarkL3 Start Finish Dur. L3 L3SAT Completion 100% %PlanWTG% Baseline Activity Milestones % Actual 9.41% SITE ACCEPTANC TEST - SAT QTY Budgeted Mhrs 100.00% 97.21% 100.00%26576 100.00% OVERALL PROGRESS OF WHP 50/1 : GAS PLATFORM 100.00% TOTAL OF WHP 50/1 : GAS PLATFORM : E&I PRE-COMMISSIONING Instrumentation 63.80% 90.00% 100.00% Electrical 90.00% Cost Code Cost Code Cost Code 36.20% 100.00% 8 90.00% 100.00% Sub-System - 8000B : Electrical Generation and Distribution 100.00% 90.00% 100.00% 7 19 23 100.00% 568 568 145 145 11 11 100.00% 110 110 68.63% 5 5 75.00% 9 9 100.00% 5 5 100.00% 1 1 100.00% 7 7 10 10 88.89% 4 4 100.00% 14 14 95.33% 49 49 100.00% Page 2 of 10 Prepared By : Nattakarn S.
  • 15.
    Activity ID ActivityName Num. Budgeted Units Planned Start Planned Finish % Actual 1-Jun-16 L5 L4 L5 L4 L5 L4 1284 3723 14-Aug-15 9-Oct-15 57 503-FAEI-20780 Fabrication of E&I Supports for Sub-Cellar Deck 31 Ea. 50.170 98 2.63% 24-Aug-15 8-Sep-15 16 100.00% 100.00% Completed 503-FAEI-20790 Fabrication of E&I Supports for Cellar Deck 636 Ea. 50.170 1915 51.44% 14-Aug-15 9-Oct-15 57 100.00% 100.00% Completed 503-FAEI-20800 Fabrication of E&I Supports for Mezzanine Deck 252 Ea. 50.170 525 14.10% 24-Aug-15 24-Sep-15 32 100.00% 100.00% Completed 503-FAEI-20810 Fabrication of E&I Supports for Upper Deck 365 Ea. 50.170 1185 31.83% 24-Aug-15 2-Oct-15 40 100.00% 100.00% Completed 4719 25-Sep-15 7-Apr-16 196 1284 3250 25-Sep-15 27-Feb-16 156 31 106 3.26% 25-Dec-15 18-Jan-16 25 100.00% 100.00% 503-FAEI-20820 Installation of E&I Support at Sub-Cellar Deck - Assembly Bay 1 Ea. 50.170 12 11.32% 25-Dec-15 5-Jan-16 12 100.00% 100.00% Completed 503-FAEI-20830 Installation of E&I Support at Sub-Cellar Deck - Erection Area 30 Ea. 50.170 94 88.68% 29-Dec-15 18-Jan-16 21 100.00% 100.00% Completed 636 1614 49.66% 25-Sep-15 15-Dec-15 82 100.00% 100.00% 503-FAEI-20840 Installation of E&I Support at Cellar Deck - Assembly Bay 475 Ea. 50.170 1035 64.13% 25-Sep-15 20-Oct-15 26 100.00% 100.00% Completed 503-FAEI-20850 Installation of E&I Support at Cellar Deck - Erection Area 161 Ea. 50.170 579 35.87% 13-Nov-15 15-Dec-15 33 100.00% 100.00% Completed 252 546 16.80% 27-Oct-15 27-Feb-16 124 100.00% 100.00% 503-FAEI-20860 Installation of E&I Support at Mezzanine Deck - Assembly Bay 37 Ea. 50.170 118 21.61% 27-Oct-15 12-Nov-15 17 100.00% 100.00% Completed 503-FAEI-20870 Installation of E&I Support at Mezzanine Deck - Erection Area 215 Ea. 50.170 428 78.39% 3-Feb-16 27-Feb-16 25 100.00% 100.00% Completed 365 984 30.28% 3-Nov-15 4-Feb-16 94 100.00% 100.00% 503-FAEI-20880 Installation of E&I Support at UpperDeck - Assembly Bay 273 Ea. 50.170 662 67.28% 3-Nov-15 27-Nov-15 25 100.00% 100.00% Completed 503-FAEI-20890 Installation of E&I Support at UpperDeck - Erection Area 92 Ea. 50.170 322 32.72% 11-Dec-15 4-Feb-16 56 100.00% 100.00% Completed 779 1469 23-Nov-15 7-Apr-16 137 503-FAEI-20900 Installation of Cable Trays&Ladders 670 m. 50.170 942 64.13% 23-Nov-15 7-Jan-16 46 100.00% 100.00% Completed 503-FAEI-20910 Installation of Tubing Trays&Ladders 109 m. 50.170 527 35.87% 4-Mar-16 7-Apr-16 35 100.00% 100.00% Completed 8442 0.00% L5 L4 L5 L4 L5 L4 298 905 12-Oct-15 9-Feb-16 121 298 905 12-Oct-15 9-Feb-16 121 503-FAEI-20920 Calibration of Instrument Tags - 01-I1: Process Production 193 Ea. 50.165 535 59.12% 12-Oct-15 3-Dec-15 53 100.00% 100.00% Completed 503-FAEI-20930 Calibration of Instrument Tags - 01-I2 : Production Header 28 Ea. 50.165 76 8.40% 18-Nov-15 1-Dec-15 14 100.00% 100.00% Completed 503-FAEI-20940 Calibration of Instrument Tags - 02-I1 : Test Separator 50 Ea. 50.165 140 15.47% 1-Dec-15 29-Dec-15 29 100.00% 100.00% Completed 503-FAEI-20950 Calibration of Instrument Tags - 03-I1 : Pig Luncher 1 Ea. 50.165 3 0.33% 26-Dec-15 29-Dec-15 4 100.00% 100.00% Completed 503-FAEI-20990 Calibration of Instrument Tags - 10-I1 : Booster Compressor 26 Ea. 50.165 75 8.29% 29-Dec-15 13-Jan-16 16 100.00% 100.00% Completed 14 38 24-Oct-15 21-Nov-15 29 8 22 24-Oct-15 27-Oct-15 4 503-FAEI-21000 Calibration of Instrument Tags - 08-I1 : Closed Drain System 8 Ea. 50.165 22 100.00% 24-Oct-15 27-Oct-15 4 100.00% 100.00% Completed 5 13 20-Nov-15 21-Nov-15 2 503-FAEI-21010 Calibration of Instrument Tags - 09-I1 : Open Drain System 5 Ea. 50.165 13 100.00% 20-Nov-15 21-Nov-15 2 100.00% 100.00% Completed 1 3 20-Nov-15 21-Nov-15 2 503-FAEI-21020 Calibration of Instrument Tags - 06-I1 : HP Vent / LP Vent 1 Ea. 50.165 3 100.00% 20-Nov-15 21-Nov-15 2 100.00% 100.00% Completed 24 68 18-Nov-15 2-Dec-15 15 14 40 20-Nov-15 27-Nov-15 8 503-FAEI-21030 Calibration of Instrument Tags - 04-I1 : Instrument Gas 14 Ea. 50.165 40 100.00% 20-Nov-15 27-Nov-15 8 100.00% 100.00% Completed 10 28 18-Nov-15 2-Dec-15 15 503-FAEI-21040 Calibration of Instrument Tags - 04-I2 : Utility Gas 10 Ea. 50.165 28 100.00% 27-Nov-15 2-Dec-15 6 100.00% 100.00% Completed 21 59 2-Oct-15 15-Oct-15 14 21 59 2-Oct-15 15-Oct-15 14 503-FAEI-21070 Calibration of Instrument Tags - 11-I1 : Chemical Injection 21 Ea. 50.165 59 100.00% 3-Oct-15 15-Oct-15 13 100.00% 100.00% Completed 57 224 2-Oct-15 30-Jan-16 121 51 208 2-Oct-15 12-Dec-15 72 503-FAEI-21090 Calibration of Instrument Tags - 13-C1 : Back Start 3 Ea. 50.165 8 3.85% 11-Dec-15 12-Dec-15 2 100.00% 100.00% Completed 503-FAEI-21100 Calibration of Instrument Tags - 13-C3 : Wellhead Control Panel 48 Ea. 50.165 200 96.15% 2-Oct-15 2-Nov-15 32 100.00% 100.00% Completed 1 3 14-Dec-15 15-Dec-15 2 503-FAEI-21120 Calibration of Instrument Tags - 14-E6 : TEG - Gas Platform 1 Ea. 50.165 3 100.00% 14-Dec-15 15-Dec-15 2 100.00% 100.00% Completed 5 13 29-Jan-16 30-Jan-16 2 503-FAEI-21130 Calibration of Instrument Tags - 17-S3 : Fire & Gas Detector 5 Ea. 50.165 13 100.00% 29-Jan-16 30-Jan-16 2 100.00% 100.00% Completed 414 1294 0.00% 1st 2nd 1st 2nd L5 L4 20.0% 20.0% 7.5% 7.5% L5 L4 L5 L4 295 4601 24-Mar-16 26-Apr-16 34 295 4601 24-Mar-16 26-Apr-16 34 503-FAEI-21140 Cables Installation for 01-I1: Process Production 121 Sch. 50.175 1968 42.77% 7-Apr-16 26-Apr-16 20 121 121 121 121 100.00% 100.00% Completed 503-FAEI-21150 Cables Installation for 01-I2 : Production Header 50 Sch. 50.175 678 14.74% 28-Mar-16 4-Apr-16 8 50 50 50 50 100.00% 100.00% Completed 503-FAEI-21160 Cables Installation for 02-I1 : Test Separator 76 Sch. 50.175 1033 22.45% 7-Apr-16 18-Apr-16 12 76 76 76 76 100.00% 100.00% Completed 503-FAEI-21200 Cables Installation for 10-I1 : Booster Compressor 48 Sch. 50.175 651 14.15% 24-Mar-16 31-Mar-16 8 48 48 48 48 100.00% 100.00% Completed 9 124 2-Apr-16 20-Apr-16 19 6 82 16-Apr-16 20-Apr-16 5 503-FAEI-21210 Cables Installation for 08-I1 : Closed Drain System 6 Sch. 50.175 82 100.00% 16-Apr-16 20-Apr-16 5 6 6 6 6 100.00% 100.00% Completed 3 42 2-Apr-16 12-Apr-16 11 503-FAEI-21220 Cables Installation for 09-I1 : Open Drain System 3 Sch. 50.175 42 100.00% 2-Apr-16 12-Apr-16 11 3 3 3 3 100.00% 100.00% Completed 16 217 26-Mar-16 16-Apr-16 22 10 135 1-Apr-16 16-Apr-16 16 503-FAEI-21230 Cables Installation for 04-I1 : Instrument Gas 10 Sch. 50.175 135 100.00% 1-Apr-16 16-Apr-16 16 10 10 10 10 100.00% 100.00% Completed 6 82 26-Mar-16 16-Apr-16 22 503-FAEI-21240 Cables Installation for 04-I2 : Utility Gas 6 Sch. 50.175 82 100.00% 1-Apr-16 16-Apr-16 16 6 6 6 6 100.00% 100.00% Completed 9 125 1-Apr-16 10-May-16 40 9 125 1-Apr-16 10-May-16 40 503-FAEI-21270 Cables Installation for 11-I1 : Chemical Injection 9 Sch. 50.175 125 100.00% 26-Apr-16 10-May-16 15 9 9 9 9 100.00% 100.00% Completed 262 3215 18-Nov-15 12-May-16 177 63 776 18-Nov-15 27-Feb-16 102 503-FAEI-21290 Cables Installation for 13-C2 : PLC and Control system 63 Sch. 50.175 776 100.00% 12-Feb-16 27-Feb-16 16 63 63 63 63 100.00% 100.00% Completed 175 2139 24-Nov-15 12-May-16 171 503-FAEI-21320 Cables Installation for 14-E2 : AC Diesel Generators 1 Sch. 50.175 16 0.75% 25-Mar-16 1-Apr-16 8 1 1 1 1 100.00% 100.00% Completed 503-FAEI-21330 Cables Installation for 14-E3 : DC Supply 36 Sch. 50.175 368 17.20% 12-Feb-16 5-Mar-16 23 26 36 26 36 92.36% 100.00% Delayed 503-FAEI-21340 Cables Installation for 14-E4 : Power & Lighting and Outlet 118 Sch. 50.175 1480 69.19% 24-Nov-15 22-Dec-15 29 118 118 118 118 100.00% 100.00% Completed 503-FAEI-21360 Cables Installation for 14-E6 : TEG - Gas Platform 9 Sch. 50.175 125 5.84% 20-Feb-16 8-Mar-16 18 9 9 9 9 100.00% 100.00% Completed 503-FAEI-21370 Cables Installation for 16-E1 : Navigation Aids System 11 Sch. 50.175 150 7.01% 12-Feb-16 3-Mar-16 21 11 11 11 11 100.00% 100.00% Completed 13 150 12-Feb-16 7-Apr-16 56 503-FAEI-21380 Cables Installation for 15-T1 : Comunication System 13 Sch. 50.175 150 100.00% 12-Feb-16 7-Apr-16 56 13 11 13 11 95.77% 100.00% Delayed 11 150 12-Feb-16 19-Mar-16 37 503-FAEI-21390 Cables Installation for 17-S2 : Emergency Shutdown 2 Sch. 50.175 27 18.00% 12-Feb-16 19-Feb-16 8 2 2 2 2 100.00% 100.00% Completed 503-FAEI-21400 Cables Installation for 17-S3 : Fire & Gas Detector 5 Sch. 50.175 68 45.33% 11-Mar-16 14-Mar-16 4 5 5 5 5 100.00% 100.00% Completed 503-FAEI-21410 Cables Installation for 17-S4 : Beacon Light & Siren 4 Sch. 50.175 55 36.67% 12-Mar-16 19-Mar-16 8 4 4 4 4 100.00% 100.00% Completed 591 8282 581 589 581 589 -0.42% L5 L4 L5 L4 L5 L4 295 531 29-Apr-16 16-May-16 18 295 531 29-Apr-16 16-May-16 18 503-FAEI-21420 Cables Continuity Check for 01-I1: Process Production 121 Sch. 50.180 218 41.05% 4-May-16 12-May-16 9 92.41% 100.00% Delayed 503-FAEI-21430 Cables Continuity Check for 01-I2 : Production Header 50 Sch. 50.180 75 14.12% 4-May-16 7-May-16 4 90.40% 100.00% Delayed 503-FAEI-21440 Cables Continuity Check for 02-I1 : Test Separator 76 Sch. 50.180 135 25.42% 7-May-16 11-May-16 5 90.55% 100.00% Delayed 503-FAEI-21480 Cables Continuity Check for 10-I1 : Booster Compressor 48 Sch. 50.180 72 13.56% 13-May-16 16-May-16 4 90.08% 100.00% Delayed 9 13 6-May-16 23-May-16 18 6 9 6-May-16 21-May-16 16 503-FAEI-21490 Cables Continuity Check for 08-I1 : Closed Drain System 6 Sch. 50.180 9 100.00% 6-May-16 21-May-16 16 90.50% 100.00% Delayed 3 4 7-May-16 23-May-16 17 503-FAEI-21500 Cables Continuity Check for 09-I1 : Open Drain System 3 Sch. 50.180 4 100.00% 7-May-16 23-May-16 17 90.50% 100.00% Delayed 16 24 20-Apr-16 19-May-16 30 10 15 7-May-16 19-May-16 13 503-FAEI-21510 Cables Continuity Check for 04-I1 : Instrument Gas 10 Sch. 50.180 15 100.00% 7-May-16 19-May-16 13 90.75% 100.00% Delayed 6 9 20-Apr-16 18-May-16 29 503-FAEI-21520 Cables Continuity Check for 04-I2 : Utility Gas 6 Sch. 50.180 9 100.00% 9-May-16 18-May-16 10 90.92% 100.00% Delayed 9 18 12-May-16 11-Jun-16 31 9 18 12-May-16 11-Jun-16 31 503-FAEI-21550 Cables Continuity Check for 11-I1 : Chemical Injection 9 Sch. 50.180 18 100.00% 12-May-16 21-May-16 10 90.50% 100.00% Delayed 262 409 29-Apr-16 23-May-16 25 63 59 6-May-16 11-May-16 6 503-FAEI-21570 Cables Continuity Check for 13-C2 : PLC and Control system 63 Sch. 50.180 59 100.00% 6-May-16 9-May-16 4 72.14% 100.00% Delayed 175 254 29-Apr-16 23-May-16 25 503-FAEI-21600 Cables Continuity Check for 14-E2 : AC Diesel Generators 1 Sch. 50.180 3 1.18% 9-May-16 11-May-16 3 93.00% 100.00% Delayed 503-FAEI-21610 Cables Continuity Check for 14-E3 : DC Supply 36 Sch. 50.180 26 10.24% 13-May-16 16-May-16 4 72.48% 100.00% Delayed 503-FAEI-21620 Cables Continuity Check for 14-E4 : Power & Lighting and Outlet 118 Sch. 50.180 196 77.17% 29-Apr-16 7-May-16 9 87.17% 100.00% Delayed 503-FAEI-21640 Cables Continuity Check for 14-E6 : TEG - Gas Platform 9 Sch. 50.180 13 5.12% 13-May-16 16-May-16 4 92.72% 100.00% Delayed 503-FAEI-21650 Cables Continuity Check for 16-E1 : Navigation Aids System 11 Sch. 50.180 16 6.30% 6-May-16 9-May-16 4 92.73% 100.00% Delayed 13 74 6-May-16 9-May-16 4 503-FAEI-21660 Cables Continuity Check for 15-T1 : Comunication System 13 Sch. 50.180 74 100.00% 6-May-16 9-May-16 4 72.23% 100.00% Delayed 11 22 9-May-16 12-May-16 4 503-FAEI-21670 Cables Continuity Check for 17-S2 : Emergency Shutdown 2 Sch. 50.180 3 13.64% 9-May-16 11-May-16 3 93.00% 100.00% Delayed 503-FAEI-21680 Cables Continuity Check for 17-S3 : Fire & Gas Detector 5 Sch. 50.180 12 54.55% 10-May-16 12-May-16 3 92.50% 100.00% Delayed 503-FAEI-21690 Cables Continuity Check for 17-S4 : Beacon Light & Siren 4 Sch. 50.180 7 31.82% 10-May-16 12-May-16 3 90.50% 100.00% Delayed 591 995 -12.28% L5 L4 L5 L4 L5 L4 339 508 4-May-16 6-Jun-16 34 72 112 4-May-16 7-May-16 4 72 112 4-May-16 7-May-16 4 503-FAEI-21700 Tubings Installation for 06-I1 : HP Vent / LP Vent 72 m. 50.175 112 100.00% 4-May-16 7-May-16 4 91.50% 100.00% Delayed 189 153 17-May-16 4-Jun-16 19 189 153 17-May-16 4-Jun-16 19 503-FAEI-21710 Tubings Installation for 11-I1 : Chemical Injection 189 m. 50.175 153 100.00% 31-May-16 4-Jun-16 5 91.50% 100.00% Delayed Should be finished 78 243 4-May-16 6-Jun-16 34 69 122 3-Jun-16 6-Jun-16 4 503-FAEI-21730 Tubings Installation for 13-C1 : Back Start 69 m. 50.175 122 100.00% 3-Jun-16 6-Jun-16 4 95.00% 100.00% Delayed 9 121 4-May-16 9-May-16 6 503-FAEI-21740 Tubings Installation for 14-E6 : TEG - Gas Platform 9 m. 50.175 20 16.53% 4-May-16 6-May-16 3 91.50% 100.00% Delayed 3478 12-Feb-16 13-Jun-16 123 2874 870 12-Feb-16 16-Mar-16 34 503-FAEI-21760 Pre-Cutting and Pre-Bending 2874 m. 50.175 870 100.00% 12-Feb-16 16-Mar-16 34 100.00% 100.00% Completed 2535 2608 4-May-16 13-Jun-16 41 483 227 11-May-16 8-Jun-16 29 483 227 11-May-16 8-Jun-16 29 503-FAEI-21780 Tubings Installation for 01-I1: Process Production 456 m. 50.175 195 85.90% 31-May-16 8-Jun-16 9 95.00% 100.00% Delayed Should be finished 503-FAEI-21790 Tubings Installation for 10-I1 : Booster Compressor 27 m. 50.175 32 14.10% 11-May-16 19-May-16 9 95.00% 100.00% Delayed 2052 2381 4-May-16 13-Jun-16 41 1273 1529 18-May-16 13-Jun-16 27 503-FAEI-21800 Tubings Installation for 13-C3 : Wellhead Control Panel 1273 m. 50.175 1529 100.00% 18-May-16 13-Jun-16 27 94.13% 100.00% Delayed Should be finished 779 852 4-May-16 4-Jun-16 32 503-FAEI-21810 Tubings Installation for 17-S1 : Fire Emergency Shutdown (FESD) 531 m. 50.175 579 67.96% 18-May-16 4-Jun-16 18 95.00% 100.00% Delayed Should be finished 503-FAEI-21820 Tubings Installation for 17-S2 : Emergency Shutdown 248 m. 50.175 273 32.04% 4-May-16 21-May-16 18 90.00% 100.00% Delayed 2874 3986 -4.71% L5 L4 L5 L4 L5 L4 339 102 23-May-16 27-May-16 5 72 9 27-May-16 27-May-16 1 72 9 27-May-16 27-May-16 1 503-FAEI-21830 Tubings Leak Test for 06-I1 : HP Vent / LP Vent 72 m. 50.180 9 100.00% 27-May-16 27-May-16 1 90.00% 100.00% Delayed 189 50 26-May-16 26-May-16 1 189 50 26-May-16 26-May-16 1 503-FAEI-21840 Tubings Leak Test for 11-I1 : Chemical Injection 189 m. 50.180 50 100.00% 26-May-16 26-May-16 1 90.50% 100.00% Delayed 78 43 23-May-16 26-May-16 4 Sub-System - 7001 : Chemical (C) 100.00% 90.50% 100.00% 189 5.00% System - 8000 : Others 42.16% 95.12% 100.00% System - 2000 : Drains & Reliefs 8.82% 90.00% 100.00% Sub-System - 2500 : Blow Down (BD) 100.00% 90.00% 100.00% 72 System - 7000 : Chemicals 49.02% 90.50% 100.00% Status Next 2 Wks As Per Planed RemarkL3 Start Finish Dur. Tested Check Sheet : PLT-T L3 L3 90% 10% Bare Tube Leak Test 35.92% 92.40% 100.00% Sub-System - 8000D : Safety Intrergrity System (SIS) 35.78% 93.40% 100.00% 531 50.00% 248 SUB-TOTAL OF TUBINGS INSTALLATION 16.56% 2874 95.29% 100.00% 456 50.00% 27 50.00% System - 8000 : Others 91.30% 93.86% 100.00% Sub-System - 8000A : Process Control 64.22% 94.13% 100.00% 1273 41.25% 2874 Field Installation and Hook-Up 74.99% 93.96% 100.00% System - 1000 : Process Production 8.70% 95.00% 100.00% Sub-System - 1001 : Process Liquid & Vapour (P) 100.00% 95.00% 100.00% Sub-System - 8000B : Electrical Generation and Distribution 49.79% 98.60% 100.00% 9 15.00% TPU Jacket Tube Installation 87.26% 95.47% 100.00% Preparation Works 25.01% 100.00% 100.00% 189 15.00% System - 8000 : Others 47.83% 96.79% 100.00% Sub-System - 8000A : Process Control 50.21% 95.00% 100.00% 69 50.00% 91.50% 100.00% 72 15.00% System - 7000 : Chemicals 30.12% 91.50% 100.00% System - 2000 : Drains & Reliefs 22.05% Sub-System - 7001 : Chemical (C) 100.00% 91.50% 100.00% Status Next 2 Wks As Per Planed RemarkL3 Start Finish Dur. Tube Running Check Sheet : PIC-T L3 L3 90% 10% Bare Tube Installation 12.74% 94.03% 100.00% 100.00%SUB-TOTAL OF CABLES CONTINUITY & INSULATION TEST 4.13% 558 87.72% 2 30.00% 5 25.00% 4 5.00% TUBINGS LEAK TEST QTY Unit Cost Code Budgeted Mhrs WTG% Baseline Activity Milestones % Actual %Plan 91.50% 100.00% Sub-System - 2500 : Blow Down (BD) 100.00% 72.23% 100.00% 10 30.00% Sub-System - 8000D : Safety Intrergrity System (SIS) 5.38% 91.93% 100.00% 9 27.22% 11 27.27% Sub-System - 8000C : Communication 18.09% 28 24.83% 110 32.68% 86.37% 100.00% 1 30.00% 49 21.36% Sub-System - 8000B : Electrical Generation and Distribution 62.10% 82.06% 100.00% Sub-System - 8000A : Process Control 14.43% 72.14% 100.00% 9 5.00% System - 8000 : Others 41.11% 90.50% 100.00% Sub-System - 7001 : Chemical (C) 100.00% 90.50% 100.00% System - 7000 : Chemicals 1.81% 90.92% 100.00% 6 9.17% 10 7.50% Sub-System - 4500 : Gas Utility (GU) 37.50% Sub-System - 4400 : Gas Instrument (GI) 62.50% 90.75% 100.00% 24.05% 50 4.00% 76 5.53% 90.50% 3 5.00% System - 4000 : Utility Generals 2.41% 90.81% 100.00% 6 5.00% Sub-System - 2100 : Open Drain (DO) 30.77% 90.50% 100.00% Sub-System - 2001 : Closed Drain (DC) 69.23% 90.50% 100.00% RemarkL3 Start Finish Dur. Tested Check Sheet : PLT-C Activity Milestones % Actual %Plan Status Next 2 Wks As Per Planed L3 L3 90% 10% CABLES CONTINUITY & INSULATION TEST QTY Unit Cost Code Budgeted Mhrs WTG% Baseline Sub-System - 1001 : Process Liquid & Vapour (P) 100.00% 91.78% 100.00% System - 1000 : Process Production 53.37% 91.78% 100.00% 48 0.83% 99.58% 100.00% 2 5 4 SUB-TOTAL OF CABLES INSTALLATION 34.40% TUBINGS INSTALLATION QTY Unit Cost Code Budgeted Mhrs WTG% Baseline Activity Milestones % Actual %Plan System - 2000 : Drains & Reliefs 1.31% 121 100.00% 13 Sub-System - 8000D : Safety Intrergrity System (SIS) 4.67% 100.00% 100.00% 9 11 Sub-System - 8000C : Communication 4.67% 95.77% 100.00% 1 36 118 63 Sub-System - 8000B : Electrical Generation and Distribution 66.53% 98.69% 100.00% Sub-System - 8000A : Process Control 24.14% 100.00% 100.00% 9 System - 8000 : Others 38.82% 98.93% System - 7000 : Chemicals 1.51% 100.00% 100.00% Sub-System - 7001 : Chemical (C) 100.00% 100.00% 100.00% Sub-System - 4500 : Gas Utility (GU) 37.79% 100.00% 100.00% 6 Sub-System - 4400 : Gas Instrument (GI) 62.21% 100.00% 100.00% 10 3 System - 4000 : Utility Generals 2.62% 100.00% 100.00% 6 Sub-System - 2100 : Open Drain (DO) 33.87% 100.00% 100.00% System - 2000 : Drains & Reliefs 1.50% 100.00% 100.00% Sub-System - 2001 : Closed Drain (DC) 66.13% 100.00% 100.00% 50 76 48 Sub-System - 1001 : Process Liquid & Vapour (P) 100.00% 100.00% 100.00% 121 45% System - 1000 : Process Production 55.55% 100.00% 100.00% Next 2 Wks As Per Planed Remark Start Finish Dur. Pulled Activity Milestones Status Glanded Terminated L3 L3 100.00% 100.00% CABLES INSTALLATION QTY Unit Cost Code Budgeted Mhrs Baseline 5 100.00% SUB-TOTAL OF CALIBRATION OF INSTRUMENTS TAG 5.37% 100.00% 100.00% 1 100.00% Sub-System - 8000D : Safety Intrergrity System (SIS) 5.80% 100.00% 100.00% WTG% % Actual %Plan L3 3 100.00% 48 100.00% Sub-System - 8000B : Electrical Generation and Distribution 1.34% 100.00% 100.00% Sub-System - 8000A : Process Control 92.86% 100.00% 100.00% 21 100.00% System - 8000 : Others 17.31% 100.00% 100.00% Sub-System - 7001 : Chemical (C) 100.00% 100.00% 100.00% System - 7000 : Chemicals 4.56% 100.00% 100.00% 10 100.00% 14 100.00% Sub-System - 4500 : Gas Utility (GU) 41.18% 100.00% 100.00% Sub-System - 4400 : Gas Instrument (GI) 58.82% 100.00% 100.00% 1 100.00% System - 4000 : Utility Generals 5.26% 100.00% 100.00% 5 100.00% Sub-System - 2500 : Blow Down (BD) 7.89% 100.00% 100.00% 8 100.00% Sub-System - 2100 : Open Drain (DO) 34.21% 100.00% 100.00% Sub-System - 2001 : Closed Drain (DC) 57.89% 100.00% 100.00% 26 100.00% System - 2000 : Drains & Reliefs 2.94% 1 100.00% 193 100.00% 28 100.00% 50 100.00% 100.00% Sub-System - 1001 : Process Liquid & Vapour (P) 100.00% 100.00% 100.00% System - 1000 : Process Production 69.94% 414 100.00% Next 2 Wks As Per Planed RemarkL3 Start Finish Dur. Calibrated Activity Milestones % Actual %Plan StatusCheck Sheet : PCC L3 L3 90% 100.00% 100.00% CALIBRATION OF INSTRUMENTS TAG QTY Unit Cost Code Budgeted Mhrs WTG% Baseline 670 670 109 109 SUB-TOTAL OF E&I SUPPORTS, LADDERS AND TRAYS 35.06% 10% Installation of E&I Trays&Ladders 31.13% 100.00% 100.00% Upper Deck 273 273 92 92 Mezzanine Deck 37 37 215 215 Cellar Deck 475 475 161 161 Sub-Cellar Deck 1 1 30 30 100.00% 100.00% Installation of E&I Supports 68.87% 100.00% 100.00% 365 365 Installation 55.90% 31 31 636 636 252 252 L3 90% 10% Fabrication 44.10% 100.00% 100.00% CHEVRON : CVX-PHASE 50 PROGRESS MEASUREMENT WORK SHEET FOR E&I AND PRE-COMMISSIONING WORKS WHP 50/3 : GAS PLATFORM WHP 50/3 : GAS PLATFORM : E&I INSTALLATION E&I SUPPORTS, LADDERS AND TRAYS QTY Unit Cost Code Budgeted Mhrs %Plan Status Next 2 Wks As Per Planed RemarkL3 Start Finish Dur. WTG% Baseline Activity Milestones % Actual Fabricated/Installed Accepted /Painted/Cleaning L3 591 Page 3 of 10 Prepared By : Nattakarn S.
  • 16.
    Activity ID ActivityName Num. Budgeted Units Planned Start Planned Finish % Actual 1-Jun-16 CHEVRON : CVX-PHASE 50 PROGRESS MEASUREMENT WORK SHEET FOR E&I AND PRE-COMMISSIONING WORKS WHP 50/3 : GAS PLATFORM 69 21 23-May-16 24-May-16 2 503-FAEI-21860 Tubings Leak Test for 13-C1 : Back Start 69 m. 50.180 21 100.00% 23-May-16 24-May-16 2 90.00% 100.00% Delayed 9 22 25-May-16 26-May-16 2 503-FAEI-21870 Tubings Leak Test for 14-E6 : TEG - Gas Platform 9 m. 50.180 11 50.00% 25-May-16 25-May-16 1 100.00% 100.00% Completed 2535 182 23-May-16 27-May-16 5 483 56 27-May-16 27-May-16 1 483 56 27-May-16 27-May-16 1 503-FAEI-21890 Tubings Leak Test for 01-I1: Process Production 456 m. 50.180 45 80.36% 27-May-16 27-May-16 1 90.25% 100.00% Delayed 503-FAEI-21900 Tubings Leak Test for Booster Compressor 27 m. 50.180 11 19.64% 27-May-16 27-May-16 1 90.00% 100.00% Delayed 2052 126 23-May-16 27-May-16 5 1273 90 23-May-16 24-May-16 2 503-FAEI-21910 Tubings Leak Test for 13-C3 : Wellhead Control Panel 1273 m. 50.180 90 100.00% 23-May-16 24-May-16 2 90.00% 100.00% Delayed 779 36 27-May-16 27-May-16 1 503-FAEI-21920 Tubings Leak Test for 17-S1 : Fire Emergency Shutdown (FESD) 531 m. 50.180 18 50.00% 27-May-16 27-May-16 1 93.00% 100.00% Delayed 503-FAEI-21930 Tubings Leak Test for 17-S2 : Emergency Shutdown 248 m. 50.180 18 50.00% 27-May-16 27-May-16 1 90.50% 100.00% Delayed 2874 284 -8.88% L5 L4 L5 L4 L5 L4 271 363 6-May-16 20-Jun-16 46 271 363 6-May-16 20-Jun-16 46 503-FAEI-21940 Hook-Up of E&I Tags for 01-I1: Process Production 145 Ea. 50.175 148 40.77% 7-May-16 27-May-16 21 77.33% 100.00% Delayed 503-FAEI-21950 Hook-Up of E&I Tags for 01-I2 : Production Header 28 Ea. 50.175 43 11.85% 6-May-16 2-Jun-16 28 89.68% 100.00% Delayed Should be finished 503-FAEI-21960 Hook-Up of E&I Tags for 02-I1 : Test Separator 52 Ea. 50.175 75 20.66% 16-May-16 3-Jun-16 19 83.08% 100.00% Delayed Should be finished 503-FAEI-21970 Hook-Up of E&I Tags for 03-I1 : Pig Luncher 1 Ea. 50.175 1 0.28% 11-May-16 13-May-16 3 0.00% 100.00% Delayed & Not Start 503-FAEI-21980 Hook-Up of E&I Tags for 03-I2 : Pig Receiver - Option 18 Ea. 50.175 55 15.15% 11-May-16 19-May-16 9 0.00% 100.00% Delayed & Not Start 503-FAEI-22010 Hook-Up of E&I Tags for 10-I1 : Booster Compressor 27 Ea. 50.175 41 11.29% 3-Jun-16 20-Jun-16 18 84.99% 100.00% Delayed 15 22 30-Apr-16 27-May-16 28 9 13 30-Apr-16 11-May-16 12 503-FAEI-22020 Hook-Up of E&I Tags for 08-I1 : Closed Drain System 9 Ea. 50.175 13 100.00% 30-Apr-16 11-May-16 12 82.67% 100.00% Delayed 5 8 13-May-16 14-May-16 2 503-FAEI-22030 Hook-Up of E&I Tags for 09-I1 : Open Drain System 5 Ea. 50.175 8 100.00% 13-May-16 14-May-16 2 74.40% 100.00% Delayed 1 1 26-May-16 27-May-16 2 503-FAEI-22040 Hook-Up of E&I Tags for 06-I1 : HP Vent / LP Vent 1 Ea. 50.175 1 100.00% 26-May-16 27-May-16 2 0.00% 100.00% Delayed & Not Start 28 41 7-Apr-16 12-May-16 36 17 23 7-Apr-16 19-Apr-16 13 503-FAEI-22050 Hook-Up of E&I Tags for 04-I1 : Instrument Gas 17 Ea. 50.175 23 100.00% 7-Apr-16 19-Apr-16 13 81.88% 100.00% Delayed 11 18 9-Apr-16 12-May-16 34 503-FAEI-22060 Hook-Up of E&I Tags for 04-I2 : Utility Gas 11 Ea. 50.175 18 100.00% 9-Apr-16 21-Apr-16 13 76.09% 100.00% Delayed 24 35 21-May-16 10-Jun-16 21 24 35 21-May-16 10-Jun-16 21 503-FAEI-22090 Hook-Up of E&I Tags for 11-I1 : Chemical Injection 24 Ea. 50.175 35 100.00% 24-May-16 10-Jun-16 18 93.00% 100.00% Delayed Should be finished 231 332 6-Feb-16 23-Jun-16 139 67 226 21-Apr-16 16-May-16 26 503-FAEI-22110 Hook-Up of E&I Tags for 13-C1 : Back Start 4 Ea. 50.175 7 3.10% 21-Apr-16 26-Apr-16 6 92.50% 100.00% Delayed 503-FAEI-22120 Hook-Up of E&I Tags for 13-C2 : PLC and Control system 14 Ea. 50.175 22 9.73% 28-Apr-16 12-May-16 15 69.33% 100.00% Delayed 503-FAEI-22130 Hook-Up of E&I Tags for 13-C3 : Wellhead Control Panel 49 Ea. 50.175 197 87.17% 28-Apr-16 16-May-16 19 89.39% 100.00% Delayed 133 60 6-Feb-16 23-Jun-16 139 503-FAEI-22150 Hook-Up of E&I Tags for 14-E2 : AC Diesel Generators 1 Ea. 50.175 1 1.67% 14-Jun-16 22-Jun-16 9 100.00% 100.00% Completed 503-FAEI-22160 Hook-Up of E&I Tags for 14-E3 : DC Supply 8 Ea. 50.175 10 16.67% 7-Mar-16 15-Mar-16 9 100.00% 100.00% Completed 503-FAEI-22170 Hook-Up of E&I Tags for 14-E4 : Power & Lighting and Outlet 110 Ea. 50.175 28 46.67% 6-Feb-16 11-Mar-16 35 99.79% 100.00% Delayed 503-FAEI-22190 Hook-Up of E&I Tags for 14-E6 : TEG - Gas Platform 5 Ea. 50.175 8 13.33% 11-Apr-16 22-Apr-16 12 98.00% 100.00% Delayed 503-FAEI-22200 Hook-Up of E&I Tags for 16-E1 : Navigation Aids System 9 Ea. 50.175 13 21.67% 21-Mar-16 30-Mar-16 10 100.00% 100.00% Completed 5 7 21-Mar-16 30-Mar-16 10 503-FAEI-22210 Hook-Up of E&I Tags for 15-T1 : Comunication System 5 Ea. 50.175 7 100.00% 21-Mar-16 30-Mar-16 10 100.00% 100.00% Completed 26 39 7-May-16 3-Jun-16 28 503-FAEI-22220 Hook-Up of E&I Tags for 17-S2 : Emergency Shutdown 10 Ea. 50.175 13 33.33% 7-May-16 18-May-16 12 60.00% 100.00% Delayed 503-FAEI-22230 Hook-Up of E&I Tags for 17-S3 : Fire & Gas Detector 5 Ea. 50.175 8 20.51% 27-May-16 3-Jun-16 8 100.00% 100.00% Completed 503-FAEI-22240 Hook-Up of E&I Tags for 17-S4 : Beacon Light & Siren 11 Ea. 50.175 18 46.15% 7-May-16 11-May-16 5 100.00% 100.00% Completed 569 793 -20.51% 24076 -2.21% L5 L4 L5 L4 L5 L4 704 31-May-16 4-Jun-16 5 61 704 31-May-16 4-Jun-16 5 61 704 31-May-16 4-Jun-16 5 503-FAPC-21030 Fuction Test of 14-E2 : AC Diesel Generators 4 Pac. 60.220 71 10.09% 31-May-16 2-Jun-16 3 90.00% 100.00% Delayed Should be finished 503-FAPC-21040 Fuction Test of 14-E3 : DC Supply 19 Pac. 60.220 174 24.72% 31-May-16 2-Jun-16 3 90.00% 100.00% Delayed Should be finished 503-FAPC-21050 Fuction Test of 14-E4 : Power & Lighting and Outlet 23 Pac. 60.220 322 45.74% 31-May-16 2-Jun-16 3 90.00% 100.00% Delayed Should be finished 503-FAPC-21070 Fuction Test of 14-E6 : TEG - Gas Platform 7 Pac. 60.220 21 2.98% 3-Jun-16 3-Jun-16 1 0.00% 100.00% Delayed & Not Start Should be started 503-FAPC-21080 Fuction Test of 16-E1 : Navigation Aids System 8 Pac. 60.220 116 16.48% 31-May-16 2-Jun-16 3 90.00% 100.00% Delayed Should be finished 1241 30-May-16 4-Jun-16 6 199 823 30-May-16 4-Jun-16 6 199 823 30-May-16 4-Jun-16 6 503-FAPC-21100 Loop Test of 01-I1: Process Production 97 Pac. 60.225 340 41.31% 30-May-16 3-Jun-16 5 0.00% 100.00% Delayed & Not Start Should be finished 503-FAPC-21110 Loop Test of 01-I2 : Production Header 26 Pac. 60.225 94 11.42% 31-May-16 3-Jun-16 4 0.00% 100.00% Delayed & Not Start Should be finished 503-FAPC-21120 Loop Test of 02-I1 : Test Separator 45 Pac. 60.225 191 23.21% 2-Jun-16 3-Jun-16 2 0.00% 100.00% Delayed & Not Start Should be started 503-FAPC-21160 Loop Test of 10-I1 : Booster Compressor 31 Pac. 60.225 156 18.96% 4-Jun-16 4-Jun-16 1 0.00% 90.06% Delayed & Not Start Should be started 9 32 31-May-16 2-Jun-16 3 6 21 31-May-16 2-Jun-16 3 503-FAPC-21170 Loop Test of 08-I1 : Closed Drain System 6 Pac. 60.225 21 100.00% 31-May-16 2-Jun-16 3 0.00% 100.00% Delayed & Not Start Should be finished 3 11 31-May-16 2-Jun-16 3 503-FAPC-21180 Loop Test of 09-I1 : Open Drain System 3 Pac. 60.225 11 100.00% 31-May-16 2-Jun-16 3 0.00% 100.00% Delayed & Not Start Should be finished 14 32 31-May-16 2-Jun-16 3 9 21 31-May-16 2-Jun-16 3 503-FAPC-21190 Loop Test of 04-I1 : Instrument Gas 9 Pac. 60.225 21 100.00% 31-May-16 2-Jun-16 3 0.00% 100.00% Delayed & Not Start Should be finished 5 11 31-May-16 2-Jun-16 3 503-FAPC-21200 Loop Test of 04-I2 : Utility Gas 5 Pac. 60.225 11 100.00% 31-May-16 2-Jun-16 3 0.00% 100.00% Delayed & Not Start Should be finished 9 32 31-May-16 2-Jun-16 3 9 32 31-May-16 2-Jun-16 3 503-FAPC-21230 Loop Test of 11-I1 : Chemical Injection 9 Pac. 60.225 32 100.00% 31-May-16 2-Jun-16 3 0.00% 100.00% Delayed & Not Start Should be finished 97 322 31-May-16 3-Jun-16 4 81 187 31-May-16 3-Jun-16 4 503-FAPC-21250 Loop Test of 13-C3 : Wellhead Control Panel 81 Pac. 60.225 187 100.00% 31-May-16 3-Jun-16 4 0.00% 100.00% Delayed & Not Start Should be finished 1 4 31-May-16 2-Jun-16 3 503-FAPC-21260 Loop Test of 15-T1 : Comunication System 1 Pac. 60.225 4 100.00% 31-May-16 2-Jun-16 3 0.00% 100.00% Delayed & Not Start Should be finished 15 131 31-May-16 2-Jun-16 3 503-FAPC-21270 Loop Test of 17-S2 : Emergency Shutdown 3 Pac. 60.225 12 9.16% 31-May-16 2-Jun-16 3 90.00% 100.00% Delayed Should be finished 503-FAPC-21280 Loop Test of 17-S3 : Fire & Gas Detector 5 Pac. 60.225 28 21.37% 31-May-16 2-Jun-16 3 0.00% 100.00% Delayed & Not Start Should be finished 503-FAPC-21290 Loop Test of 17-S4 : Beacon Light & Siren 7 Pac. 60.225 91 69.47% 31-May-16 2-Jun-16 3 90.00% 100.00% Delayed Should be finished 389 1945 -61.47% L5 L4 L5 L4 L5 L4 503-FAPC-21300 Platform Site Acceptance Test - SAT 100 Pac. 60.235 555 6-Jun-16 11-Jun-16 6 Delayed & Not Start Should be started 100 555 0.00% 2500 -48.68% -6.58% SUB-TOTAL OF TUBINGS LEAK TEST 1.18% 91.12% 100.00% Sub-System - 8000A : Process Control 71.43% 90.00% 100.00% 1273 Sub-System - 8000D : Safety Intrergrity System (SIS) 28.57% 91.75% 100.00% 531 30.00% 248 5.00% 100.00% Sub-System - 1001 : Process Liquid & Vapour (P) 100.00% 90.20% 100.00% 456 2.50% 27 System - 8000 : Others 69.23% 90.50% 100.00% System - 1000 : Process Production 30.77% 90.20% 69 Sub-System - 8000B : Electrical Generation and Distribution 51.16% 100.00% 100.00% 9 100.00% TPU Jacket Tube Leak Test 64.08% 90.41% 100.00% Sub-System - 8000A : Process Control 48.84% 90.00% 100.00% 91.41% 97.99%OVERALL PROGRESS OF WHP 50/3 : GAS PLATFORM 26576 100.00% 0.00% TOTAL OF WHP 50/3 : GAS PLATFORM : E&I PRE-COMMISSIONING 9.41% 29.98% 78.66% 100.00% 0.00% 6.67% SUB-TOTAL OF SITE ACCEPTANC TEST - SAT 22.20% 0.00% RemarkL3 Start Finish Dur. Activity Milestones % Actual %Plan Status Next 2 Wks As Per Planed SAT Completion L3 L3 100% 100.00% SITE ACCEPTANC TEST - SAT QTY Unit Cost Code Budgeted Mhrs WTG% Baseline SUB-TOTAL OF LOOP/ FUNCTION TEST 77.80% 38.53% 3 7 0.00% 100.00% Sub-System - 8000D : Safety Intrergrity System (SIS) 40.68% 70.76% 100.00% Sub-System - 8000C : Communication 1.24% 28.79% 100.00% Sub-System - 8000A : Process Control 58.07% 0.00% 100.00% System - 8000 : Others 25.95% 0.00% 100.00% Sub-System - 7001 : Chemical (C) 100.00% 0.00% 100.00% System - 7000 : Chemicals 2.58% 0.00% 100.00%Sub-System - 4500 : Gas Utility (GU) 34.38% Sub-System - 4400 : Gas Instrument (GI) 65.63% 0.00% 100.00% 0.00% 100.00% System - 4000 : Utility Generals 2.58% 0.00% 100.00% Sub-System - 2100 : Open Drain (DO) 34.38% 0.00% 100.00% Sub-System - 2001 : Closed Drain (DC) 65.63% 0.00% 100.00% System - 2000 : Drains & Reliefs 2.58% Sub-System - 1001 : Process Liquid & Vapour (P) 100.00% 5.10% 98.12% 10.85% 98.75% System - 1000 : Process Production 66.32% 5.10% 98.12% 8 Instrumentation 63.80% 23 4 19 Sub-System - 8000B : Electrical Generation and Distribution 100.00% 87.32% 100.00% System - 8000 : Others 100.00% 87.32% 100.00% Electrical 36.20% 87.32% 100.00% %Plan Status Next 2 Wks As Per Planed RemarkL3 Start Finish Dur. WTG% Baseline Activity Milestones % Actual Tested Check Sheet : PLT-L & PFT WHP 50/3 : GAS PLATFORM : E&I PRE-COMMISSIONING LOOP/ FUNCTION TEST QTY Unit Cost Code Budgeted Mhrs TOTAL OF WHP 50/3 : GAS PLATFORM : E&I INSTALLATION 90.59% 97.79% 100.00% L3 L3 90% 10% 100.00%SUB-TOTAL OF HOOK-UP OF E&I TAG ITEMS 3.29% 79.49% 11 11 100.00% Sub-System - 8000B : Electrical Generation and Distribution 18.07% 99.64% 100.00% 1 1 100.00% 8 8 100.00% 100.00% 100.00% Sub-System - 8000D : Safety Intrergrity System (SIS) 11.75% 86.67% 100.00% Sub-System - 8000C : Communication 2.11% 110 110 97.91% 5 5 80.00% 9 89.88% 100.00% Sub-System - 8000A : Process Control 68.07% 87.53% 100.00% System - 8000 : Others 41.87% 93.00% 100.00% Sub-System - 7001 : Chemical (C) 100.00% 93.00% 100.00% 24 24 30.00% 76.09% 100.00%Sub-System - 4500 : Gas Utility (GU) 43.90% 79.34% 100.00% Sub-System - 4400 : Gas Instrument (GI) 56.10% 81.88% 100.00% 9 9 24.55% System - 7000 : Chemicals 4.41% System - 4000 : Utility Generals 5.17% 74.40% 100.00% Sub-System - 2500 : Blow Down (BD) 4.55% 0.00% 100.00% Sub-System - 2100 : Open Drain (DO) 36.36% 8 8 26.67% 4 4 24.00% 75.90% 100.00% Sub-System - 2001 : Closed Drain (DC) 59.09% 82.67% 100.00% System - 2000 : Drains & Reliefs 2.77% 25 24 27.69% 100.00% Sub-System - 1001 : Process Liquid & Vapour (P) 100.00% 68.92% 100.00% System - 1000 : Process Production 45.78% 68.92% HOOK-UP OF E&I TAG ITEMS QTY Unit Cost Code Budgeted Mhrs 512 486 Next 2 Wks As Per Planed RemarkL3 Start Finish Dur. Activity Milestones % Actual %Plan StatusL3 L3 WTG% Baseline Installed Hook-Up Check Sheet : PIC-H 60% 30% 10% 22.27% 27 27 28.93% 48 48 121 121 4 4 25.00% 10 5 5 100.00% 14 93.33% 49 48 9 100.00% 5 5 100.00% 15 15 24.71% Page 4 of 10 Prepared By : Nattakarn S.
  • 17.
    Activity ID ActivityName Num. Budgeted Units Planned Start Planned Finish % Actual 1-Jun-16 L5 L4 L5 L4 L5 L4 1291 3723 21-Aug-15 28-Oct-15 69 504-FAEI-22250 Fabrication of E&I Supports for Sub-Cellar Deck 31 Ea. 50.170 98 2.63% 24-Aug-15 8-Sep-15 16 100.00% 100.00% Completed 504-FAEI-22260 Fabrication of E&I Supports for Cellar Deck 653 Ea. 50.170 1915 51.44% 21-Aug-15 16-Oct-15 57 100.00% 100.00% Completed 504-FAEI-22270 Fabrication of E&I Supports for Mezzanine Deck 243 Ea. 50.170 525 14.10% 25-Sep-15 28-Oct-15 34 100.00% 100.00% Completed 504-FAEI-22280 Fabrication of E&I Supports for Upper Deck 364 Ea. 50.170 1185 31.83% 24-Aug-15 2-Oct-15 40 100.00% 100.00% Completed 4719 16-Oct-15 7-May-16 205 1291 3250 16-Oct-15 11-Mar-16 148 31 106 3.26% 25-Dec-15 3-Feb-16 41 100.00% 100.00% 504-FAEI-22290 Installation of E&I Support at Sub-Cellar Deck - Assembly Bay 1 Ea. 50.170 12 11.32% 25-Dec-15 5-Jan-16 12 100.00% 100.00% Completed 504-FAEI-22300 Installation of E&I Support at Sub-Cellar Deck - Erection Area 30 Ea. 50.170 94 88.68% 18-Jan-16 3-Feb-16 17 100.00% 100.00% Completed 653 1614 49.66% 16-Oct-15 8-Feb-16 116 100.00% 100.00% 504-FAEI-22310 Installation of E&I Support at Cellar Deck - Assembly Bay 475 Ea. 50.170 1035 64.13% 16-Oct-15 11-Nov-15 27 100.00% 100.00% Completed 504-FAEI-22320 Installation of E&I Support at Cellar Deck - Erection Area 178 Ea. 50.170 579 35.87% 23-Nov-15 8-Feb-16 78 100.00% 100.00% Completed 243 546 16.80% 4-Nov-15 11-Mar-16 129 100.00% 100.00% 504-FAEI-22330 Installation of E&I Support at Mezzanine Deck - Assembly Bay 37 Ea. 50.170 118 21.61% 4-Nov-15 20-Nov-15 17 100.00% 100.00% Completed 504-FAEI-22340 Installation of E&I Support at Mezzanine Deck - Erection Area 206 Ea. 50.170 428 78.39% 16-Feb-16 11-Mar-16 25 100.00% 100.00% Completed 364 984 30.28% 13-Nov-15 6-Jan-16 55 100.00% 100.00% 504-FAEI-22350 Installation of E&I Support at UpperDeck - Assembly Bay 273 Ea. 50.170 662 67.28% 13-Nov-15 11-Dec-15 29 100.00% 100.00% Completed 504-FAEI-22360 Installation of E&I Support at UpperDeck - Erection Area 91 Ea. 50.170 322 32.72% 11-Dec-15 6-Jan-16 27 100.00% 100.00% Completed 779 1469 28-Nov-15 7-May-16 162 504-FAEI-22370 Installation of Cable Trays&Ladders 670 m. 50.170 942 64.13% 28-Nov-15 13-Jan-16 47 100.00% 100.00% Completed 504-FAEI-22380 Installation of Tubing Trays&Ladders 109 m. 50.170 527 35.87% 30-Mar-16 7-May-16 39 100.00% 100.00% Completed 8442 0.00% L5 L4 L5 L4 L5 L4 305 905 27-Oct-15 17-Feb-16 114 305 905 27-Oct-15 17-Feb-16 114 504-FAEI-22390 Calibration of Instrument Tags - 01-I1: Process Production 193 Ea. 50.165 535 59.12% 27-Oct-15 21-Dec-15 56 100.00% 100.00% Completed 504-FAEI-22400 Calibration of Instrument Tags - 01-I2 : Production Header 28 Ea. 50.165 76 8.40% 18-Nov-15 1-Dec-15 14 100.00% 100.00% Completed 504-FAEI-22410 Calibration of Instrument Tags - 02-I1 : Test Separator 50 Ea. 50.165 140 15.47% 1-Dec-15 29-Dec-15 29 100.00% 100.00% Completed 504-FAEI-22420 Calibration of Instrument Tags - 03-I1 : Pig Luncher 1 Ea. 50.165 3 0.33% 11-Dec-15 12-Dec-15 2 100.00% 100.00% Completed 504-FAEI-22460 Calibration of Instrument Tags - 10-I1 : Booster Compressor 26 Ea. 50.165 75 8.29% 29-Dec-15 13-Jan-16 16 100.00% 100.00% Completed 14 38 24-Oct-15 12-Dec-15 50 8 22 24-Oct-15 27-Oct-15 4 504-FAEI-22470 Calibration of Instrument Tags - 08-I1 : Closed Drain System 8 Ea. 50.165 22 100.00% 24-Oct-15 27-Oct-15 4 100.00% 100.00% Completed 5 13 11-Dec-15 12-Dec-15 2 504-FAEI-22480 Calibration of Instrument Tags - 09-I1 : Open Drain System 5 Ea. 50.165 13 100.00% 11-Dec-15 12-Dec-15 2 100.00% 100.00% Completed 1 3 11-Dec-15 12-Dec-15 2 504-FAEI-22490 Calibration of Instrument Tags - 06-I1 : HP Vent / LP Vent 1 Ea. 50.165 3 100.00% 11-Dec-15 12-Dec-15 2 100.00% 100.00% Completed 24 68 27-Nov-15 4-Dec-15 8 14 40 27-Nov-15 3-Dec-15 7 504-FAEI-22500 Calibration of Instrument Tags - 04-I1 : Instrument Gas 14 Ea. 50.165 40 100.00% 27-Nov-15 3-Dec-15 7 100.00% 100.00% Completed 10 28 27-Nov-15 4-Dec-15 8 504-FAEI-22510 Calibration of Instrument Tags - 04-I2 : Utility Gas 10 Ea. 50.165 28 100.00% 27-Nov-15 2-Dec-15 6 100.00% 100.00% Completed 21 59 3-Oct-15 26-Oct-15 24 21 59 3-Oct-15 26-Oct-15 24 504-FAEI-22540 Calibration of Instrument Tags - 11-I1 : Chemical Injection 21 Ea. 50.165 59 100.00% 3-Oct-15 15-Oct-15 13 100.00% 100.00% Completed 57 224 2-Oct-15 30-Jan-16 121 51 208 2-Oct-15 19-Dec-15 79 504-FAEI-22560 Calibration of Instrument Tags - 13-C1 : Back Start 3 Ea. 50.165 8 3.85% 18-Dec-15 19-Dec-15 2 100.00% 100.00% Completed 504-FAEI-22570 Calibration of Instrument Tags - 13-C3 : Wellhead Control Panel 48 Ea. 50.165 200 96.15% 2-Oct-15 2-Nov-15 32 100.00% 100.00% Completed 1 3 21-Dec-15 22-Dec-15 2 504-FAEI-22590 Calibration of Instrument Tags - 14-E6 : TEG - Gas Platform 1 Ea. 50.165 3 100.00% 21-Dec-15 22-Dec-15 2 100.00% 100.00% Completed 5 13 29-Jan-16 30-Jan-16 2 504-FAEI-22600 Calibration of Instrument Tags - 17-S3 : Fire & Gas Detector 5 Ea. 50.165 13 100.00% 29-Jan-16 30-Jan-16 2 100.00% 100.00% Completed 421 1294 0.00% 1st 2nd 1st 2nd L5 L4 20.0% 20.0% 7.5% 7.5% L5 L4 L5 L4 300 4601 23-Mar-16 26-May-16 65 300 4601 23-Mar-16 26-May-16 65 504-FAEI-22610 Cables Installation for 01-I1: Process Production 121 Sch. 50.175 1968 42.77% 10-May-16 26-May-16 17 121 121 121 121 100.00% 100.00% Completed 504-FAEI-22620 Cables Installation for 01-I2 : Production Header 50 Sch. 50.175 678 14.74% 10-May-16 17-May-16 8 50 50 50 50 100.00% 100.00% Completed 504-FAEI-22630 Cables Installation for 02-I1 : Test Separator 76 Sch. 50.175 1033 22.45% 18-May-16 26-May-16 9 76 76 76 76 100.00% 100.00% Completed 504-FAEI-22640 Cables Installation for 03-I2 : Pig Receiver - Option 5 Sch. 50.175 271 5.89% 29-Apr-16 9-May-16 11 5 5 5 5 100.00% 100.00% Completed 504-FAEI-22670 Cables Installation for 10-I1 : Booster Compressor 48 Sch. 50.175 651 14.15% 23-Mar-16 30-Mar-16 8 48 48 48 48 100.00% 100.00% Completed 9 124 21-Apr-16 4-May-16 14 6 82 21-Apr-16 29-Apr-16 9 504-FAEI-22680 Cables Installation for 08-I1 : Closed Drain System 6 Sch. 50.175 82 100.00% 21-Apr-16 29-Apr-16 9 6 6 6 6 100.00% 100.00% Completed 3 42 25-Apr-16 4-May-16 10 504-FAEI-22690 Cables Installation for 09-I1 : Open Drain System 3 Sch. 50.175 42 100.00% 25-Apr-16 4-May-16 10 3 3 3 3 100.00% 100.00% Completed 16 217 7-Apr-16 23-Apr-16 17 10 135 9-Apr-16 23-Apr-16 15 504-FAEI-22700 Cables Installation for 04-I1 : Instrument Gas 10 Sch. 50.175 135 100.00% 9-Apr-16 23-Apr-16 15 10 10 10 10 100.00% 100.00% Completed 6 82 7-Apr-16 23-Apr-16 17 504-FAEI-22710 Cables Installation for 04-I2 : Utility Gas 6 Sch. 50.175 82 100.00% 9-Apr-16 23-Apr-16 15 6 6 6 6 100.00% 100.00% Completed 9 125 19-Apr-16 23-May-16 35 9 125 19-Apr-16 23-May-16 35 504-FAEI-22740 Cables Installation for 11-I1 : Chemical Injection 9 Sch. 50.175 125 100.00% 18-May-16 23-May-16 6 9 9 9 9 100.00% 100.00% Completed 264 3215 27-Nov-15 16-May-16 172 65 776 27-Nov-15 26-Mar-16 121 504-FAEI-22760 Cables Installation for 13-C2 : PLC and Control system 65 Sch. 50.175 776 100.00% 19-Feb-16 26-Mar-16 37 65 65 65 65 100.00% 100.00% Completed 175 2139 30-Nov-15 16-May-16 169 504-FAEI-22790 Cables Installation for 14-E2 : AC Diesel Generators 1 Sch. 50.175 16 0.75% 25-Mar-16 1-Apr-16 8 1 1 1 1 100.00% 100.00% Completed 504-FAEI-22800 Cables Installation for 14-E3 : DC Supply 36 Sch. 50.175 368 17.20% 19-Feb-16 18-Apr-16 60 26 36 26 36 92.36% 100.00% Delayed 504-FAEI-22810 Cables Installation for 14-E4 : Power & Lighting and Outlet 118 Sch. 50.175 1480 69.19% 30-Nov-15 3-Feb-16 66 118 118 118 118 100.00% 100.00% Completed 504-FAEI-22830 Cables Installation for 14-E6 : TEG - Gas Platform 9 Sch. 50.175 125 5.84% 5-Mar-16 12-Mar-16 8 9 9 9 9 100.00% 100.00% Completed 504-FAEI-22840 Cables Installation for 16-E1 : Navigation Aids System 11 Sch. 50.175 150 7.01% 30-Nov-15 23-Dec-15 24 11 11 11 11 100.00% 100.00% Completed 13 150 19-Feb-16 18-Apr-16 60 504-FAEI-22850 Cables Installation for 15-T1 : Comunication System 13 Sch. 50.175 150 100.00% 19-Feb-16 18-Apr-16 60 13 11 13 11 95.77% 100.00% Delayed 11 150 18-Jan-16 27-Apr-16 101 504-FAEI-22860 Cables Installation for 17-S2 : Emergency Shutdown 2 Sch. 50.175 27 18.00% 18-Jan-16 26-Jan-16 9 2 2 2 2 100.00% 100.00% Completed 504-FAEI-22870 Cables Installation for 17-S3 : Fire & Gas Detector 5 Sch. 50.175 68 45.33% 1-Apr-16 9-Apr-16 9 5 5 5 5 100.00% 100.00% Completed 504-FAEI-22880 Cables Installation for 17-S4 : Beacon Light & Siren 4 Sch. 50.175 55 36.67% 20-Apr-16 27-Apr-16 8 4 4 4 4 100.00% 100.00% Completed 598 8282 588 596 588 596 -0.42% L5 L4 L5 L4 L5 L4 300 531 9-May-16 21-May-16 13 300 531 9-May-16 21-May-16 13 504-FAEI-22890 Cables Continuity Check for 01-I1: Process Production 121 Sch. 50.180 218 41.05% 10-May-16 17-May-16 8 90.00% 100.00% Delayed 504-FAEI-22900 Cables Continuity Check for 01-I2 : Production Header 50 Sch. 50.180 75 14.12% 10-May-16 12-May-16 3 90.00% 100.00% Delayed 504-FAEI-22910 Cables Continuity Check for 02-I1 : Test Separator 76 Sch. 50.180 135 25.42% 12-May-16 16-May-16 5 90.00% 100.00% Delayed 504-FAEI-22920 Cables Continuity Check for 03-I2 : Pig Receiver - Option 5 Sch. 50.180 31 5.84% 9-May-16 11-May-16 3 90.00% 100.00% Delayed 504-FAEI-22950 Cables Continuity Check for 10-I1 : Booster Compressor 48 Sch. 50.180 72 13.56% 18-May-16 21-May-16 4 90.00% 100.00% Delayed 9 13 9-May-16 14-May-16 6 6 9 9-May-16 11-May-16 3 504-FAEI-22960 Cables Continuity Check for 08-I1 : Closed Drain System 6 Sch. 50.180 9 100.00% 9-May-16 11-May-16 3 90.00% 100.00% Delayed 3 4 12-May-16 14-May-16 3 504-FAEI-22970 Cables Continuity Check for 09-I1 : Open Drain System 3 Sch. 50.180 4 100.00% 12-May-16 14-May-16 3 90.00% 100.00% Delayed 16 24 14-May-16 28-May-16 15 10 15 14-May-16 17-May-16 4 504-FAEI-22980 Cables Continuity Check for 04-I1 : Instrument Gas 10 Sch. 50.180 15 100.00% 14-May-16 17-May-16 4 90.00% 100.00% Delayed 6 9 17-May-16 28-May-16 12 504-FAEI-22990 Cables Continuity Check for 04-I2 : Utility Gas 6 Sch. 50.180 9 100.00% 17-May-16 19-May-16 3 90.00% 100.00% Delayed 9 18 17-May-16 15-Jul-16 60 9 18 17-May-16 15-Jul-16 60 504-FAEI-23020 Cables Continuity Check for 11-I1 : Chemical Injection 9 Sch. 50.180 18 100.00% 17-May-16 19-May-16 3 90.00% 100.00% Delayed 264 409 4-May-16 6-Jun-16 34 65 59 25-May-16 31-May-16 7 504-FAEI-23040 Cables Continuity Check for 13-C2 : PLC and Control system 65 Sch. 50.180 59 100.00% 25-May-16 27-May-16 3 70.62% 100.00% Delayed 175 254 9-May-16 6-Jun-16 29 504-FAEI-23070 Cables Continuity Check for 14-E2 : AC Diesel Generators 1 Sch. 50.180 3 1.18% 9-May-16 11-May-16 3 90.00% 100.00% Delayed 504-FAEI-23080 Cables Continuity Check for 14-E3 : DC Supply 36 Sch. 50.180 26 10.24% 21-May-16 24-May-16 4 70.00% 100.00% Delayed 504-FAEI-23090 Cables Continuity Check for 14-E4 : Power & Lighting and Outlet 118 Sch. 50.180 196 77.17% 28-May-16 6-Jun-16 10 83.90% 100.00% Delayed Should be finished 504-FAEI-23110 Cables Continuity Check for 14-E6 : TEG - Gas Platform 9 Sch. 50.180 13 5.12% 13-May-16 16-May-16 4 90.00% 100.00% Delayed 504-FAEI-23120 Cables Continuity Check for 16-E1 : Navigation Aids System 11 Sch. 50.180 16 6.30% 25-May-16 27-May-16 3 90.00% 100.00% Delayed 13 74 4-May-16 6-May-16 3 504-FAEI-23130 Cables Continuity Check for 15-T1 : Comunication System 13 Sch. 50.180 74 100.00% 4-May-16 6-May-16 3 69.23% 100.00% Delayed 11 22 4-May-16 19-May-16 16 504-FAEI-23140 Cables Continuity Check for 17-S2 : Emergency Shutdown 2 Sch. 50.180 3 13.64% 4-May-16 6-May-16 3 90.00% 100.00% Delayed 504-FAEI-23150 Cables Continuity Check for 17-S3 : Fire & Gas Detector 5 Sch. 50.180 12 54.55% 17-May-16 19-May-16 3 90.00% 100.00% Delayed 504-FAEI-23160 Cables Continuity Check for 17-S4 : Beacon Light & Siren 4 Sch. 50.180 7 31.82% 17-May-16 19-May-16 3 90.00% 100.00% Delayed 598 995 -14.42% L5 L4 L5 L4 L5 L4 340 508 16-May-16 2-Jun-16 18 72 112 17-May-16 18-May-16 2 72 112 17-May-16 18-May-16 2 504-FAEI-23170 Tubings Installation for 06-I1 : HP Vent / LP Vent 72 m. 50.175 112 100.00% 17-May-16 18-May-16 2 95.00% 100.00% Delayed 189 153 16-May-16 2-Jun-16 18 189 153 16-May-16 2-Jun-16 18 504-FAEI-23180 Tubings Installation for 11-I1 : Chemical Injection 189 m. 50.175 153 100.00% 16-May-16 19-May-16 4 95.00% 100.00% Delayed 79 243 17-May-16 21-May-16 5 70 122 18-May-16 21-May-16 4 504-FAEI-23200 Tubings Installation for 13-C1 : Back Start 70 m. 50.175 122 100.00% 18-May-16 21-May-16 4 95.00% 100.00% Delayed 9 121 17-May-16 19-May-16 3 504-FAEI-23210 Tubings Installation for 14-E6 : TEG - Gas Platform 9 m. 50.175 20 16.53% 17-May-16 17-May-16 1 95.00% 100.00% Delayed 3478 4-Mar-16 28-May-16 86 2874 870 4-Mar-16 7-Apr-16 35 504-FAEI-23230 Pre-Cutting and Pre-Bending 2874 m. 50.175 870 100.00% 4-Mar-16 7-Apr-16 35 100.00% 100.00% Completed 2535 2608 3-May-16 28-May-16 26 483 227 17-May-16 25-May-16 9 483 227 17-May-16 25-May-16 9 504-FAEI-23250 Tubings Installation for 01-I1: Process Production 456 m. 50.175 195 85.90% 17-May-16 25-May-16 9 95.00% 100.00% Delayed 504-FAEI-23260 Tubings Installation for 10-I1 : Booster Compressor 27 m. 50.175 32 14.10% 17-May-16 25-May-16 9 95.00% 100.00% Delayed 2052 2381 3-May-16 28-May-16 26 1273 1529 3-May-16 28-May-16 26 504-FAEI-23270 Tubings Installation for 13-C3 : Wellhead Control Panel 1273 m. 50.175 1529 100.00% 3-May-16 28-May-16 26 91.50% 100.00% Delayed 779 852 3-May-16 21-May-16 19 504-FAEI-23280 Tubings Installation for 17-S1 : Fire Emergency Shutdown (FESD) 531 m. 50.175 579 67.96% 3-May-16 19-May-16 17 89.92% 100.00% Delayed 504-FAEI-23290 Tubings Installation for 17-S2 : Emergency Shutdown 248 m. 50.175 273 32.04% 4-May-16 21-May-16 18 83.47% 100.00% Delayed 2875 3986 -6.65% L5 L4 L5 L4 L5 L4 441 102 25-May-16 30-May-16 6 96 9 26-May-16 27-May-16 2 96 9 26-May-16 27-May-16 2 504-FAEI-23300 Tubings Leak Test for 06-I1 : HP Vent / LP Vent 96 m. 50.180 9 100.00% 26-May-16 27-May-16 2 0.00% 100.00% Delayed & Not Start 189 50 26-May-16 30-May-16 5 189 50 26-May-16 30-May-16 5Sub-System - 7001 : Chemical (C) 100.00% 0.00% 100.00% System - 2000 : Drains & Reliefs 8.82% 0.00% 100.00% Sub-System - 2500 : Blow Down (BD) 100.00% 0.00% 100.00% System - 7000 : Chemicals 49.02% 0.00% 100.00% Status Next 2 Wks As Per Planed RemarkL3 Start Finish Dur. Tested Check Sheet : PLT-T L3 L3 90% 10% Bare Tube Leak Test 35.92% 0.00% 100.00% Sub-System - 8000D : Safety Intrergrity System (SIS) 35.78% 87.85% 100.00% 501 50.00% 230 SUB-TOTAL OF TUBINGS INSTALLATION 16.56% 2827 93.35% 100.00% 456 50.00% 27 50.00% System - 8000 : Others 91.30% 90.19% 100.00% Sub-System - 8000A : Process Control 64.22% 91.50% 100.00% 1273 15.00% 2874 Field Installation and Hook-Up 74.99% 90.61% 100.00% System - 1000 : Process Production 8.70% 95.00% 100.00% Sub-System - 1001 : Process Liquid & Vapour (P) 100.00% 95.00% 100.00% Sub-System - 8000B : Electrical Generation and Distribution 49.79% 99.17% 100.00% 9 50.00% TPU Jacket Tube Installation 87.26% 92.96% 100.00% Preparation Works 25.01% 100.00% 100.00% 189 50.00% System - 8000 : Others 47.83% 97.08% 100.00% Sub-System - 8000A : Process Control 50.21% 95.00% 100.00% 70 50.00% 95.00% 100.00% 72 50.00% System - 7000 : Chemicals 30.12% 95.00% 100.00% System - 2000 : Drains & Reliefs 22.05% Sub-System - 7001 : Chemical (C) 100.00% 95.00% 100.00% Status Next 2 Wks As Per Planed RemarkL3 Start Finish Dur. Tube Running Check Sheet : PIC-T L3 L3 90% 10% Bare Tube Installation 12.74% 95.99% 100.00% 100.00%SUB-TOTAL OF CABLES CONTINUITY & INSULATION TEST 4.13% 565 85.58% 2 5 4 TUBINGS LEAK TEST QTY Unit Cost Code Budgeted Mhrs WTG% Baseline Activity Milestones % Actual %Plan 95.00% 100.00% Sub-System - 2500 : Blow Down (BD) 100.00% 69.23% 100.00% 10 Sub-System - 8000D : Safety Intrergrity System (SIS) 5.38% 90.00% 100.00% 9 11 Sub-System - 8000C : Communication 18.09% 28 110 83.24% 100.00% 1 51 Sub-System - 8000B : Electrical Generation and Distribution 62.10% 79.25% 100.00% Sub-System - 8000A : Process Control 14.43% 70.62% 100.00% 9 System - 8000 : Others 41.11% 90.00% 100.00% Sub-System - 7001 : Chemical (C) 100.00% 90.00% 100.00% System - 7000 : Chemicals 1.81% 90.00% 100.00% 6 10 Sub-System - 4500 : Gas Utility (GU) 37.50% Sub-System - 4400 : Gas Instrument (GI) 62.50% 90.00% 100.00% 50 76 90.00% 3 System - 4000 : Utility Generals 2.41% 90.00% 100.00% 6 Sub-System - 2100 : Open Drain (DO) 30.77% 90.00% 100.00% Sub-System - 2001 : Closed Drain (DC) 69.23% 90.00% 100.00% RemarkL3 Start Finish Dur. Tested Check Sheet : PLT-C Activity Milestones % Actual %Plan Status Next 2 Wks As Per Planed L3 L3 90% 10% CABLES CONTINUITY & INSULATION TEST QTY Unit Cost Code Budgeted Mhrs WTG% Baseline Sub-System - 1001 : Process Liquid & Vapour (P) 100.00% 90.00% 100.00% System - 1000 : Process Production 53.37% 90.00% 100.00% 48 99.58% 100.00% 2 5 4 SUB-TOTAL OF CABLES INSTALLATION 34.40% TUBINGS INSTALLATION QTY Unit Cost Code Budgeted Mhrs WTG% Baseline Activity Milestones % Actual %Plan System - 2000 : Drains & Reliefs 1.31% 5 121 100.00% 13 Sub-System - 8000D : Safety Intrergrity System (SIS) 4.67% 100.00% 100.00% 9 11 Sub-System - 8000C : Communication 4.67% 95.77% 100.00% 1 36 118 65 Sub-System - 8000B : Electrical Generation and Distribution 66.53% 98.69% 100.00% Sub-System - 8000A : Process Control 24.14% 100.00% 100.00% 9 System - 8000 : Others 38.82% 98.93% System - 7000 : Chemicals 1.51% 100.00% 100.00% Sub-System - 7001 : Chemical (C) 100.00% 100.00% 100.00% Sub-System - 4500 : Gas Utility (GU) 37.79% 100.00% 100.00% 6 Sub-System - 4400 : Gas Instrument (GI) 62.21% 100.00% 100.00% 10 3 System - 4000 : Utility Generals 2.62% 100.00% 100.00% 6 Sub-System - 2100 : Open Drain (DO) 33.87% 100.00% 100.00% System - 2000 : Drains & Reliefs 1.50% 100.00% 100.00% Sub-System - 2001 : Closed Drain (DC) 66.13% 100.00% 100.00% 50 76 5 48 Sub-System - 1001 : Process Liquid & Vapour (P) 100.00% 100.00% 100.00% 121 45% System - 1000 : Process Production 55.55% 100.00% 100.00% Next 2 Wks As Per Planed Remark Start Finish Dur. Pulled Activity Milestones Status Glanded Terminated L3 L3 100.00% 100.00% CABLES INSTALLATION QTY Unit Cost Code Budgeted Mhrs Baseline 5 100.00% SUB-TOTAL OF CALIBRATION OF INSTRUMENTS TAG 5.37% 100.00% 100.00% 1 100.00% Sub-System - 8000D : Safety Intrergrity System (SIS) 5.80% 100.00% 100.00% WTG% % Actual %Plan L3 3 100.00% 48 100.00% Sub-System - 8000B : Electrical Generation and Distribution 1.34% 100.00% 100.00% Sub-System - 8000A : Process Control 92.86% 100.00% 100.00% 21 100.00% System - 8000 : Others 17.31% 100.00% 100.00% Sub-System - 7001 : Chemical (C) 100.00% 100.00% 100.00% System - 7000 : Chemicals 4.56% 100.00% 100.00% 10 100.00% 14 100.00% Sub-System - 4500 : Gas Utility (GU) 41.18% 100.00% 100.00% Sub-System - 4400 : Gas Instrument (GI) 58.82% 100.00% 100.00% 1 100.00% System - 4000 : Utility Generals 5.26% 100.00% 100.00% 5 100.00% Sub-System - 2500 : Blow Down (BD) 7.89% 100.00% 100.00% 8 100.00% Sub-System - 2100 : Open Drain (DO) 34.21% 100.00% 100.00% Sub-System - 2001 : Closed Drain (DC) 57.89% 100.00% 100.00% 26 100.00% System - 2000 : Drains & Reliefs 2.94% 1 100.00% 193 100.00% 28 100.00% 50 100.00% 100.00% Sub-System - 1001 : Process Liquid & Vapour (P) 100.00% 100.00% 100.00% System - 1000 : Process Production 69.94% 421 100.00% Next 2 Wks As Per Planed RemarkL3 Start Finish Dur. Calibrated Activity Milestones % Actual %Plan StatusCheck Sheet : PCC L3 L3 90% 100.00% 100.00% CALIBRATION OF INSTRUMENTS TAG QTY Unit Cost Code Budgeted Mhrs WTG% Baseline 670 670 109 109 SUB-TOTAL OF E&I SUPPORTS, LADDERS AND TRAYS 35.06% 10% Installation of E&I Trays&Ladders 31.13% 100.00% 100.00% Upper Deck 273 273 91 91 Mezzanine Deck 37 37 206 206 Cellar Deck 475 475 178 178 Sub-Cellar Deck 1 1 30 30 100.00% 100.00% Installation of E&I Supports 68.87% 100.00% 100.00% 364 364 Installation 55.90% 31 31 653 653 243 243 L3 90% 10% Fabrication 44.10% 100.00% 100.00% CHEVRON : CVX-PHASE 50 PROGRESS MEASUREMENT WORK SHEET FOR E&I AND PRE-COMMISSIONING WORKS WHP 50/4 : GAS PLATFORM WHP 50/4 : GAS PLATFORM : E&I INSTALLATION E&I SUPPORTS, LADDERS AND TRAYS QTY Unit Cost Code Budgeted Mhrs %Plan Status Next 2 Wks As Per Planed RemarkL3 Start Finish Dur. WTG% Baseline Activity Milestones % Actual Fabricated/Installed Accepted /Painted/Cleaning L3 598 Page 5 of 10 Prepared By : Nattakarn S.
  • 18.
    Activity ID ActivityName Num. Budgeted Units Planned Start Planned Finish % Actual 1-Jun-16 CHEVRON : CVX-PHASE 50 PROGRESS MEASUREMENT WORK SHEET FOR E&I AND PRE-COMMISSIONING WORKS WHP 50/4 : GAS PLATFORM 504-FAEI-23310 Tubings Leak Test for 11-I1 : Chemical Injection 189 m. 50.180 50 100.00% 26-May-16 28-May-16 3 0.00% 100.00% Delayed & Not Start 156 43 25-May-16 28-May-16 4 84 21 25-May-16 28-May-16 4 504-FAEI-23330 Tubings Leak Test for 13-C1 : Back Start 84 m. 50.180 21 100.00% 25-May-16 28-May-16 4 0.00% 100.00% Delayed & Not Start 72 22 25-May-16 26-May-16 2 504-FAEI-23340 Tubings Leak Test for 14-E6 : TEG - Gas Platform 12 m. 50.180 11 50.00% 25-May-16 26-May-16 2 0.00% 100.00% Delayed & Not Start 504-FAEI-23350 Tubings Leak Test for 14-E7 : CO2 Skid - Option Gas Platform 60 m. 50.180 11 50.00% 25-May-16 26-May-16 2 0.00% 100.00% Delayed & Not Start 2535 182 26-May-16 28-May-16 3 483 56 26-May-16 27-May-16 2 483 56 26-May-16 27-May-16 2 504-FAEI-23360 Tubings Leak Test for 01-I1: Process Production 456 m. 50.180 45 80.36% 26-May-16 27-May-16 2 0.00% 100.00% Delayed & Not Start 504-FAEI-23370 Tubings Leak Test for Booster Compressor 27 m. 50.180 11 19.64% 26-May-16 26-May-16 1 0.00% 100.00% Delayed & Not Start 2052 126 26-May-16 28-May-16 3 1273 90 26-May-16 28-May-16 3 504-FAEI-23380 Tubings Leak Test for 13-C3 : Wellhead Control Panel 1273 m. 50.180 90 100.00% 26-May-16 28-May-16 3 0.00% 100.00% Delayed & Not Start 779 36 26-May-16 26-May-16 1 504-FAEI-23390 Tubings Leak Test for 17-S1 : Fire Emergency Shutdown (FESD) 531 m. 50.180 18 50.00% 26-May-16 26-May-16 1 0.00% 100.00% Delayed & Not Start 504-FAEI-23400 Tubings Leak Test for 17-S2 : Emergency Shutdown 248 m. 50.180 18 50.00% 26-May-16 26-May-16 1 0.00% 100.00% Delayed & Not Start 2976 284 -100.00% L5 L4 L5 L4 L5 L4 262 363 25-Apr-16 8-Jul-16 75 262 363 25-Apr-16 8-Jul-16 75 504-FAEI-23410 Hook-Up of E&I Tags for 01-I1: Process Production 145 Ea. 50.175 148 40.77% 25-Apr-16 23-May-16 29 77.33% 100.00% Delayed 504-FAEI-23420 Hook-Up of E&I Tags for 01-I2 : Production Header 28 Ea. 50.175 43 11.85% 19-May-16 15-Jun-16 28 86.79% 100.00% Delayed Should be finished 504-FAEI-23430 Hook-Up of E&I Tags for 02-I1 : Test Separator 52 Ea. 50.175 75 20.66% 26-May-16 13-Jun-16 19 84.81% 100.00% Delayed Should be finished 504-FAEI-23440 Hook-Up of E&I Tags for 03-I1 : Pig Luncher 1 Ea. 50.175 1 0.28% 30-May-16 31-May-16 2 0.00% 100.00% Delayed & Not Start 504-FAEI-23450 Hook-Up of E&I Tags for 03-I2 : Pig Receiver - Option 9 Ea. 50.175 55 15.15% 30-May-16 4-Jun-16 6 40.00% 100.00% Delayed Should be finished 504-FAEI-23480 Hook-Up of E&I Tags for 10-I1 : Booster Compressor 27 Ea. 50.175 41 11.29% 23-Jun-16 8-Jul-16 16 83.33% 100.00% Delayed 15 22 23-May-16 2-Jun-16 11 9 13 23-May-16 30-May-16 8 504-FAEI-23490 Hook-Up of E&I Tags for 08-I1 : Closed Drain System 9 Ea. 50.175 13 100.00% 23-May-16 30-May-16 8 62.33% 100.00% Delayed 5 8 27-May-16 31-May-16 5 504-FAEI-23500 Hook-Up of E&I Tags for 09-I1 : Open Drain System 5 Ea. 50.175 8 100.00% 27-May-16 31-May-16 5 74.40% 100.00% Delayed 1 1 31-May-16 2-Jun-16 3 504-FAEI-23510 Hook-Up of E&I Tags for 06-I1 : HP Vent / LP Vent 1 Ea. 50.175 1 100.00% 31-May-16 2-Jun-16 3 0.00% 100.00% Delayed & Not Start Should be finished 28 41 19-Apr-16 18-May-16 30 17 23 19-Apr-16 27-Apr-16 9 504-FAEI-23520 Hook-Up of E&I Tags for 04-I1 : Instrument Gas 17 Ea. 50.175 23 100.00% 19-Apr-16 27-Apr-16 9 63.53% 100.00% Delayed 11 18 21-Apr-16 18-May-16 28 504-FAEI-23530 Hook-Up of E&I Tags for 04-I2 : Utility Gas 11 Ea. 50.175 18 100.00% 21-Apr-16 29-Apr-16 9 65.45% 100.00% Delayed 24 35 27-May-16 5-Jul-16 40 24 35 27-May-16 5-Jul-16 40 504-FAEI-23560 Hook-Up of E&I Tags for 11-I1 : Chemical Injection 24 Ea. 50.175 35 100.00% 18-Jun-16 5-Jul-16 18 90.00% 100.00% Delayed 231 332 12-Feb-16 7-Jul-16 147 67 226 29-Apr-16 31-May-16 33 504-FAEI-23580 Hook-Up of E&I Tags for 13-C1 : Back Start 4 Ea. 50.175 7 3.10% 29-Apr-16 6-May-16 8 90.00% 100.00% Delayed 504-FAEI-23590 Hook-Up of E&I Tags for 13-C2 : PLC and Control system 14 Ea. 50.175 22 9.73% 14-May-16 27-May-16 14 90.47% 100.00% Delayed 504-FAEI-23600 Hook-Up of E&I Tags for 13-C3 : Wellhead Control Panel 49 Ea. 50.175 197 87.17% 14-May-16 31-May-16 18 90.00% 100.00% Delayed 133 60 12-Feb-16 7-Jul-16 147 504-FAEI-23620 Hook-Up of E&I Tags for 14-E2 : AC Diesel Generators 1 Ea. 50.175 1 1.67% 27-Jun-16 4-Jul-16 8 90.00% 100.00% Delayed 504-FAEI-23630 Hook-Up of E&I Tags for 14-E3 : DC Supply 7 Ea. 50.175 10 16.67% 18-Mar-16 23-Mar-16 6 90.00% 100.00% Delayed 504-FAEI-23640 Hook-Up of E&I Tags for 14-E4 : Power & Lighting and Outlet 111 Ea. 50.175 28 46.67% 12-Feb-16 27-Feb-16 16 92.96% 100.00% Delayed 504-FAEI-23660 Hook-Up of E&I Tags for 14-E6 : TEG - Gas Platform 5 Ea. 50.175 8 13.33% 28-Apr-16 9-May-16 12 98.00% 100.00% Delayed 504-FAEI-23670 Hook-Up of E&I Tags for 16-E1 : Navigation Aids System 9 Ea. 50.175 13 21.67% 28-Mar-16 31-Mar-16 4 93.00% 100.00% Delayed 5 7 5-Apr-16 18-Apr-16 14 504-FAEI-23680 Hook-Up of E&I Tags for 15-T1 : Comunication System 5 Ea. 50.175 7 100.00% 5-Apr-16 18-Apr-16 14 93.00% 100.00% Delayed 26 39 14-May-16 11-Jun-16 29 504-FAEI-23690 Hook-Up of E&I Tags for 17-S2 : Emergency Shutdown 10 Ea. 50.175 13 33.33% 7-Jun-16 11-Jun-16 5 90.00% 100.00% Delayed 504-FAEI-23700 Hook-Up of E&I Tags for 17-S3 : Fire & Gas Detector 5 Ea. 50.175 8 20.51% 25-May-16 31-May-16 7 93.00% 100.00% Delayed 504-FAEI-23710 Hook-Up of E&I Tags for 17-S4 : Beacon Light & Siren 11 Ea. 50.175 18 46.15% 14-May-16 24-May-16 11 93.00% 100.00% Delayed 560 793 -18.63% 24076 -3.61% L5 L4 L5 L4 L5 L4 704 7-Jun-16 9-Jun-16 3 84 704 7-Jun-16 9-Jun-16 3 84 704 7-Jun-16 9-Jun-16 3 504-FAPC-21590 Fuction Test of 14-E2 : AC Diesel Generators 10 Pac. 60.220 71 10.09% 8-Jun-16 8-Jun-16 1 0.00% 0.00% Should be started 504-FAPC-21600 Fuction Test of 14-E3 : DC Supply 21 Pac. 60.220 174 24.72% 8-Jun-16 8-Jun-16 1 0.00% 0.00% Should be started 504-FAPC-21610 Fuction Test of 14-E4 : Power & Lighting and Outlet 39 Pac. 60.220 322 45.74% 7-Jun-16 7-Jun-16 1 0.00% 0.00% Should be started 504-FAPC-21630 Fuction Test of 14-E6 : TEG - Gas Platform 6 Pac. 60.220 21 2.98% 9-Jun-16 9-Jun-16 1 0.00% 0.00% Should be started 504-FAPC-21640 Fuction Test of 16-E1 : Navigation Aids System 8 Pac. 60.220 116 16.48% 8-Jun-16 8-Jun-16 1 0.00% 0.00% Should be started 1241 6-Jun-16 11-Jun-16 6 237 823 6-Jun-16 10-Jun-16 5 237 823 6-Jun-16 10-Jun-16 5 504-FAPC-21660 Loop Test of 01-I1: Process Production 98 Pac. 60.225 340 41.31% 6-Jun-16 7-Jun-16 2 0.00% 0.00% Should be started 504-FAPC-21670 Loop Test of 01-I2 : Production Header 27 Pac. 60.225 94 11.42% 7-Jun-16 8-Jun-16 2 0.00% 0.00% Should be started 504-FAPC-21680 Loop Test of 02-I1 : Test Separator 55 Pac. 60.225 191 23.21% 8-Jun-16 9-Jun-16 2 0.00% 0.00% Should be started 504-FAPC-21690 Loop Test of 03-I2 : Pig Receiver - Option 12 Pac. 60.225 42 5.10% 8-Jun-16 8-Jun-16 1 0.00% 0.00% Should be started 504-FAPC-21720 Loop Test of 10-I1 : Booster Compressor 45 Pac. 60.225 156 18.96% 7-Jun-16 7-Jun-16 1 0.00% 0.00% Should be started 9 32 10-Jun-16 11-Jun-16 2 6 21 10-Jun-16 11-Jun-16 2 504-FAPC-21730 Loop Test of 08-I1 : Closed Drain System 6 Pac. 60.225 21 100.00% 10-Jun-16 11-Jun-16 2 0.00% 0.00% Should be started 3 11 10-Jun-16 10-Jun-16 1 504-FAPC-21740 Loop Test of 09-I1 : Open Drain System 3 Pac. 60.225 11 100.00% 10-Jun-16 10-Jun-16 1 0.00% 0.00% Should be started 13 32 10-Jun-16 10-Jun-16 1 9 21 10-Jun-16 10-Jun-16 1 504-FAPC-21750 Loop Test of 04-I1 : Instrument Gas 9 Pac. 60.225 21 100.00% 10-Jun-16 10-Jun-16 1 0.00% 0.00% Should be started 4 11 10-Jun-16 10-Jun-16 1 504-FAPC-21760 Loop Test of 04-I2 : Utility Gas 4 Pac. 60.225 11 100.00% 10-Jun-16 10-Jun-16 1 0.00% 0.00% Should be started 12 32 10-Jun-16 10-Jun-16 1 12 32 10-Jun-16 10-Jun-16 1 504-FAPC-21790 Loop Test of 11-I1 : Chemical Injection 12 Pac. 60.225 32 100.00% 10-Jun-16 10-Jun-16 1 0.00% 0.00% Should be started 49 322 9-Jun-16 10-Jun-16 2 30 187 10-Jun-16 10-Jun-16 1 504-FAPC-21810 Loop Test of 13-C3 : Wellhead Control Panel 30 Pac. 60.225 187 100.00% 10-Jun-16 10-Jun-16 1 0.00% 0.00% Should be started 1 4 9-Jun-16 9-Jun-16 1 504-FAPC-21820 Loop Test of 15-T1 : Comunication System 1 Pac. 60.225 4 100.00% 9-Jun-16 9-Jun-16 1 0.00% 0.00% Should be started 18 131 10-Jun-16 10-Jun-16 1 504-FAPC-21830 Loop Test of 17-S2 : Emergency Shutdown 3 Pac. 60.225 12 9.16% 10-Jun-16 10-Jun-16 1 0.00% 0.00% Should be started 504-FAPC-21840 Loop Test of 17-S3 : Fire & Gas Detector 8 Pac. 60.225 28 21.37% 10-Jun-16 10-Jun-16 1 0.00% 0.00% Should be started 504-FAPC-21850 Loop Test of 17-S4 : Beacon Light & Siren 7 Pac. 60.225 91 69.47% 10-Jun-16 10-Jun-16 1 0.00% 0.00% Should be started 404 1945 0.00% L5 L4 L5 L4 L5 L4 504-FAPC-21860 Platform Site Acceptance Test - SAT 100 Pac. 60.235 555 13-Jun-16 18-Jun-16 6 Should be started 100 555 0.00% 2500 -38.90% -3.27% SUB-TOTAL OF TUBINGS LEAK TEST 1.18% 0.00% 100.00% Sub-System - 8000A : Process Control 71.43% 0.00% 100.00% Sub-System - 8000D : Safety Intrergrity System (SIS) 28.57% 0.00% 100.00% 100.00% Sub-System - 1001 : Process Liquid & Vapour (P) 100.00% 0.00% 100.00% System - 8000 : Others 69.23% 0.00% 100.00% System - 1000 : Process Production 30.77% 0.00% Sub-System - 8000B : Electrical Generation and Distribution 51.16% 0.00% 100.00% TPU Jacket Tube Leak Test 64.08% 0.00% 100.00% System - 8000 : Others 42.16% 0.00% 100.00% Sub-System - 8000A : Process Control 48.84% 0.00% 100.00% 87.30% 90.57%OVERALL PROGRESS OF WHP 50/4 : GAS PLATFORM 26576 100.00% 0.00% TOTAL OF WHP 50/4 : GAS PLATFORM : E&I PRE-COMMISSIONING 9.41% 0.00% 38.90% 100.00% 0.00% 0.00% SUB-TOTAL OF SITE ACCEPTANC TEST - SAT 22.20% 0.00% RemarkL3 Start Finish Dur. Activity Milestones % Actual %Plan Status Next 2 Wks As Per Planed SAT Completion L3 L3 100% 0.00% SITE ACCEPTANC TEST - SAT QTY Unit Cost Code Budgeted Mhrs WTG% Baseline SUB-TOTAL OF LOOP/ FUNCTION TEST 77.80% 0.00% 0.00% 0.00% Sub-System - 8000D : Safety Intrergrity System (SIS) 40.68% 0.00% 0.00% Sub-System - 8000C : Communication 1.24% 0.00% 0.00% Sub-System - 8000A : Process Control 58.07% 0.00% 0.00% System - 8000 : Others 25.95% 0.00% 0.00% Sub-System - 7001 : Chemical (C) 100.00% 0.00% 0.00% System - 7000 : Chemicals 2.58% 0.00% 0.00%Sub-System - 4500 : Gas Utility (GU) 34.38% Sub-System - 4400 : Gas Instrument (GI) 65.63% 0.00% 0.00% 0.00% 0.00% System - 4000 : Utility Generals 2.58% 0.00% 0.00% Sub-System - 2100 : Open Drain (DO) 34.38% 0.00% 0.00% Sub-System - 2001 : Closed Drain (DC) 65.63% 0.00% 0.00% System - 2000 : Drains & Reliefs 2.58% Sub-System - 1001 : Process Liquid & Vapour (P) 100.00% 0.00% 0.00% 0.00% 0.00% System - 1000 : Process Production 66.32% 0.00% 0.00% Instrumentation 63.80% Sub-System - 8000B : Electrical Generation and Distribution 100.00% 0.00% 0.00% System - 8000 : Others 100.00% 0.00% 0.00% Electrical 36.20% 0.00% 0.00% %Plan Status Next 2 Wks As Per Planed RemarkL3 Start Finish Dur. WTG% Baseline Activity Milestones % Actual Tested Check Sheet : PLT-L & PFT WHP 50/4 : GAS PLATFORM : E&I PRE-COMMISSIONING LOOP/ FUNCTION TEST QTY Unit Cost Code Budgeted Mhrs TOTAL OF WHP 50/4 : GAS PLATFORM : E&I INSTALLATION 90.59% 96.37% 99.97% L3 L3 90% 10% 100.00%SUB-TOTAL OF HOOK-UP OF E&I TAG ITEMS 3.29% 81.37% 11 11 30.00% Sub-System - 8000B : Electrical Generation and Distribution 18.07% 93.10% 100.00% 1 1 7 7 93.00% 100.00% Sub-System - 8000D : Safety Intrergrity System (SIS) 11.75% 92.00% 100.00% Sub-System - 8000C : Communication 2.11% 111 111 29.55% 5 5 80.00% 9 90.89% 100.00% Sub-System - 8000A : Process Control 68.07% 90.05% 100.00% System - 8000 : Others 41.87% 90.00% 100.00% Sub-System - 7001 : Chemical (C) 100.00% 90.00% 100.00% 24 24 65.45% 100.00%Sub-System - 4500 : Gas Utility (GU) 43.90% 64.37% 100.00% Sub-System - 4400 : Gas Instrument (GI) 56.10% 63.53% 100.00% 8 8 System - 7000 : Chemicals 4.41% System - 4000 : Utility Generals 5.17% 74.40% 100.00% Sub-System - 2500 : Blow Down (BD) 4.55% 0.00% 100.00% Sub-System - 2100 : Open Drain (DO) 36.36% 6 6 23.33% 4 4 24.00% 63.89% 100.00% Sub-System - 2001 : Closed Drain (DC) 59.09% 62.33% 100.00% System - 2000 : Drains & Reliefs 2.77% 25 25 100.00% Sub-System - 1001 : Process Liquid & Vapour (P) 100.00% 74.80% 100.00% System - 1000 : Process Production 45.78% 74.80% HOOK-UP OF E&I TAG ITEMS QTY Unit Cost Code Budgeted Mhrs 511 511 Next 2 Wks As Per Planed RemarkL3 Start Finish Dur. Activity Milestones % Actual %Plan StatusL3 L3 WTG% Baseline Installed Hook-Up Check Sheet : PIC-H 60% 30% 10% 22.27% 27 27 49 49 4 4 121 121 4 4 10 10 5 5 30.00% 14 14 4.67% 49 49 9 30.00% 5 5 30.00% 12 12 Page 6 of 10 Prepared By : Nattakarn S.
  • 19.
    Activity ID ActivityName Num. Budgeted Units Planned Start Planned Finish % Actual 1-Jun-16 L5 L4 L5 L4 L5 L4 1298 3723 14-Aug-15 9-Oct-15 57 502-FAEI-19310 Fabrication of E&I Supports for Sub-Cellar Deck 31 Ea. 50.170 98 2.63% 8-Sep-15 23-Sep-15 16 100.00% 100.00% Completed 502-FAEI-19320 Fabrication of E&I Supports for Cellar Deck 651 Ea. 50.170 1915 51.44% 14-Aug-15 9-Oct-15 57 100.00% 100.00% Completed 502-FAEI-19330 Fabrication of E&I Supports for Mezzanine Deck 252 Ea. 50.170 525 14.10% 24-Aug-15 24-Sep-15 32 100.00% 100.00% Completed 502-FAEI-19340 Fabrication of E&I Supports for Upper Deck 364 Ea. 50.170 1185 31.83% 24-Aug-15 2-Oct-15 40 100.00% 100.00% Completed 4719 30-Sep-15 11-Apr-16 195 1298 3250 30-Sep-15 20-Feb-16 144 31 106 3.26% 23-Dec-15 12-Jan-16 21 100.00% 100.00% 502-FAEI-19350 Installation of E&I Support at Sub-Cellar Deck - Assembly Bay 1 Ea. 50.170 12 11.32% 25-Dec-15 5-Jan-16 12 100.00% 100.00% Completed 502-FAEI-19360 Installation of E&I Support at Sub-Cellar Deck - Erection Area 30 Ea. 50.170 94 88.68% 23-Dec-15 12-Jan-16 21 100.00% 100.00% Completed 651 1614 49.66% 30-Sep-15 16-Jan-16 109 100.00% 100.00% 502-FAEI-19370 Installation of E&I Support at Cellar Deck - Assembly Bay 475 Ea. 50.170 1035 64.13% 30-Sep-15 24-Oct-15 25 100.00% 100.00% Completed 502-FAEI-19380 Installation of E&I Support at Cellar Deck - Erection Area 176 Ea. 50.170 579 35.87% 31-Oct-15 16-Jan-16 78 100.00% 100.00% Completed 252 546 16.80% 16-Oct-15 20-Feb-16 128 100.00% 100.00% 502-FAEI-19390 Installation of E&I Support at Mezzanine Deck - Assembly Bay 37 Ea. 50.170 118 21.61% 16-Oct-15 3-Nov-15 19 100.00% 100.00% Completed 502-FAEI-19400 Installation of E&I Support at Mezzanine Deck - Erection Area 215 Ea. 50.170 428 78.39% 27-Jan-16 20-Feb-16 25 100.00% 100.00% Completed 364 984 30.28% 24-Oct-15 28-Jan-16 97 100.00% 100.00% 502-FAEI-19410 Installation of E&I Support at UpperDeck - Assembly Bay 273 Ea. 50.170 662 67.28% 24-Oct-15 17-Nov-15 25 100.00% 100.00% Completed 502-FAEI-19420 Installation of E&I Support at UpperDeck - Erection Area 91 Ea. 50.170 322 32.72% 30-Nov-15 28-Jan-16 60 100.00% 100.00% Completed 779 1469 4-Nov-15 11-Apr-16 160 502-FAEI-19430 Installation of Cable Trays&Ladders 670 m. 50.170 942 64.13% 4-Nov-15 12-Feb-16 101 100.00% 100.00% Completed 502-FAEI-19440 Installation of Tubing Trays&Ladders 109 m. 50.170 527 35.87% 7-Mar-16 11-Apr-16 36 100.00% 100.00% Completed 8442 0.00% L5 L4 L5 L4 L5 L4 305 905 24-Oct-15 19-Jan-16 88 305 905 24-Oct-15 19-Jan-16 88 502-FAEI-19450 Calibration of Instrument Tags - 01-I1: Process Production 193 Ea. 50.165 535 59.12% 24-Oct-15 18-Dec-15 56 100.00% 100.00% Completed 502-FAEI-19460 Calibration of Instrument Tags - 01-I2 : Production Header 28 Ea. 50.165 76 8.40% 11-Nov-15 24-Nov-15 14 100.00% 100.00% Completed 502-FAEI-19470 Calibration of Instrument Tags - 02-I1 : Test Separator 50 Ea. 50.165 140 15.47% 24-Nov-15 22-Dec-15 29 100.00% 100.00% Completed 502-FAEI-19480 Calibration of Instrument Tags - 03-I1 : Pig Luncher 1 Ea. 50.165 3 0.33% 15-Dec-15 17-Dec-15 3 100.00% 100.00% Completed 502-FAEI-19520 Calibration of Instrument Tags - 10-I1 : Booster Compressor 26 Ea. 50.165 75 8.29% 22-Dec-15 6-Jan-16 16 100.00% 100.00% Completed 14 38 24-Oct-15 24-Nov-15 32 8 22 24-Oct-15 27-Oct-15 4 502-FAEI-19530 Calibration of Instrument Tags - 08-I1 : Closed Drain System 8 Ea. 50.165 22 100.00% 24-Oct-15 27-Oct-15 4 100.00% 100.00% Completed 5 13 21-Nov-15 24-Nov-15 4 502-FAEI-19540 Calibration of Instrument Tags - 09-I1 : Open Drain System 5 Ea. 50.165 13 100.00% 21-Nov-15 24-Nov-15 4 100.00% 100.00% Completed 1 3 21-Nov-15 24-Nov-15 4 502-FAEI-19550 Calibration of Instrument Tags - 06-I1 : HP Vent / LP Vent 1 Ea. 50.165 3 100.00% 21-Nov-15 24-Nov-15 4 100.00% 100.00% Completed 24 68 3-Nov-15 2-Dec-15 30 14 40 20-Nov-15 27-Nov-15 8 502-FAEI-19560 Calibration of Instrument Tags - 04-I1 : Instrument Gas 14 Ea. 50.165 40 100.00% 20-Nov-15 27-Nov-15 8 100.00% 100.00% Completed 10 28 3-Nov-15 2-Dec-15 30 502-FAEI-19570 Calibration of Instrument Tags - 04-I2 : Utility Gas 10 Ea. 50.165 28 100.00% 27-Nov-15 2-Dec-15 6 100.00% 100.00% Completed 21 59 3-Oct-15 20-Oct-15 18 21 59 3-Oct-15 20-Oct-15 18 502-FAEI-19600 Calibration of Instrument Tags - 11-I1 : Chemical Injection 21 Ea. 50.165 59 100.00% 3-Oct-15 15-Oct-15 13 100.00% 100.00% Completed 57 224 25-Sep-15 30-Jan-16 128 51 208 25-Sep-15 12-Dec-15 79 502-FAEI-19620 Calibration of Instrument Tags - 13-C1 : Back Start 3 Ea. 50.165 8 3.85% 11-Dec-15 12-Dec-15 2 100.00% 100.00% Completed 502-FAEI-19630 Calibration of Instrument Tags - 13-C3 : Wellhead Control Panel 48 Ea. 50.165 200 96.15% 25-Sep-15 26-Oct-15 32 100.00% 100.00% Completed 1 3 14-Dec-15 15-Dec-15 2 502-FAEI-19650 Calibration of Instrument Tags - 14-E6 : TEG - Gas Platform 1 Ea. 50.165 3 100.00% 14-Dec-15 15-Dec-15 2 100.00% 100.00% Completed 5 13 29-Jan-16 30-Jan-16 2 502-FAEI-19660 Calibration of Instrument Tags - 17-S3 : Fire & Gas Detector 5 Ea. 50.165 13 100.00% 29-Jan-16 30-Jan-16 2 100.00% 100.00% Completed 421 1294 0.00% 1st 2nd 1st 2nd L5 L4 20.0% 20.0% 7.5% 7.5% L5 L4 L5 L4 295 4601 9-Mar-16 7-May-16 60 295 4601 9-Mar-16 7-May-16 60 502-FAEI-19670 Cables Installation for 01-I1: Process Production 121 Sch. 50.175 1968 42.77% 25-Mar-16 7-May-16 44 121 121 121 121 100.00% 100.00% Completed 502-FAEI-19680 Cables Installation for 01-I2 : Production Header 50 Sch. 50.175 678 14.74% 28-Mar-16 4-Apr-16 8 50 50 48 50 99.70% 100.00% Delayed 502-FAEI-19690 Cables Installation for 02-I1 : Test Separator 76 Sch. 50.175 1033 22.45% 2-Apr-16 9-Apr-16 8 76 76 64 76 98.82% 100.00% Delayed 502-FAEI-19730 Cables Installation for 10-I1 : Booster Compressor 48 Sch. 50.175 651 14.15% 9-Mar-16 16-Mar-16 8 48 48 48 48 100.00% 100.00% Completed 9 124 1-Mar-16 9-Apr-16 40 6 82 31-Mar-16 9-Apr-16 10 502-FAEI-19740 Cables Installation for 08-I1 : Closed Drain System 6 Sch. 50.175 82 100.00% 31-Mar-16 9-Apr-16 10 6 6 5 6 98.75% 100.00% Delayed 3 42 1-Mar-16 9-Mar-16 9 502-FAEI-19750 Cables Installation for 09-I1 : Open Drain System 3 Sch. 50.175 42 100.00% 1-Mar-16 9-Mar-16 9 3 3 2 3 97.50% 100.00% Delayed 16 217 24-Mar-16 21-Apr-16 29 10 135 25-Mar-16 5-Apr-16 12 502-FAEI-19760 Cables Installation for 04-I1 : Instrument Gas 10 Sch. 50.175 135 100.00% 25-Mar-16 5-Apr-16 12 10 10 6 10 97.00% 100.00% Delayed 6 82 24-Mar-16 21-Apr-16 29 502-FAEI-19770 Cables Installation for 04-I2 : Utility Gas 6 Sch. 50.175 82 100.00% 5-Apr-16 21-Apr-16 17 6 6 3 6 96.25% 100.00% Delayed 18 125 29-Apr-16 14-May-16 16 18 125 29-Apr-16 14-May-16 16 502-FAEI-19800 Cables Installation for 11-I1 : Chemical Injection 18 Sch. 50.175 125 100.00% 3-May-16 14-May-16 12 18 18 18 18 100.00% 100.00% Completed 266 3215 6-Nov-15 25-Apr-16 172 67 776 6-Nov-15 19-Feb-16 106 502-FAEI-19820 Cables Installation for 13-C2 : PLC and Control system 67 Sch. 50.175 776 100.00% 5-Feb-16 19-Feb-16 15 67 67 47 59 96.87% 100.00% Delayed 175 2139 6-Nov-15 25-Apr-16 172 502-FAEI-19850 Cables Installation for 14-E2 : AC Diesel Generators 1 Sch. 50.175 16 0.75% 22-Jan-16 26-Jan-16 5 1 1 1 1 100.00% 100.00% Completed 502-FAEI-19860 Cables Installation for 14-E3 : DC Supply 36 Sch. 50.175 368 17.20% 5-Feb-16 27-Feb-16 23 26 36 26 36 92.36% 100.00% Delayed 502-FAEI-19870 Cables Installation for 14-E4 : Power & Lighting and Outlet 118 Sch. 50.175 1480 69.19% 6-Nov-15 30-Nov-15 25 118 118 118 118 100.00% 100.00% Completed 502-FAEI-19890 Cables Installation for 14-E6 : TEG - Gas Platform 9 Sch. 50.175 125 5.84% 9-Feb-16 16-Feb-16 8 9 9 9 92.50% 100.00% Delayed 502-FAEI-19900 Cables Installation for 16-E1 : Navigation Aids System 11 Sch. 50.175 150 7.01% 13-Nov-15 2-Dec-15 20 11 11 11 92.50% 100.00% Delayed 13 150 5-Feb-16 27-Feb-16 23 502-FAEI-19910 Cables Installation for 15-T1 : Comunication System 13 Sch. 50.175 150 100.00% 5-Feb-16 27-Feb-16 23 13 11 7 8 90.58% 100.00% Delayed 11 150 5-Feb-16 12-Feb-16 8 502-FAEI-19920 Cables Installation for 17-S2 : Emergency Shutdown 2 Sch. 50.175 27 18.00% 5-Feb-16 8-Feb-16 4 2 2 2 92.50% 100.00% Delayed 502-FAEI-19930 Cables Installation for 17-S3 : Fire & Gas Detector 5 Sch. 50.175 68 45.33% 5-Feb-16 12-Feb-16 8 5 5 5 92.50% 100.00% Delayed 502-FAEI-19940 Cables Installation for 17-S4 : Beacon Light & Siren 4 Sch. 50.175 55 36.67% 5-Feb-16 12-Feb-16 8 4 4 4 4 100.00% 100.00% Completed 604 8282 594 602 518 591 -1.42% L5 L4 L5 L4 L5 L4 295 531 29-Apr-16 28-May-16 30 295 531 29-Apr-16 28-May-16 30 502-FAEI-19950 Cables Continuity Check for 01-I1: Process Production 121 Sch. 50.180 218 41.05% 4-May-16 21-May-16 18 90.00% 100.00% Delayed 502-FAEI-19960 Cables Continuity Check for 01-I2 : Production Header 50 Sch. 50.180 75 14.12% 4-May-16 21-May-16 18 86.40% 100.00% Delayed 502-FAEI-19970 Cables Continuity Check for 02-I1 : Test Separator 76 Sch. 50.180 135 25.42% 23-May-16 26-May-16 4 90.00% 85.19% Ahead 502-FAEI-20010 Cables Continuity Check for 10-I1 : Booster Compressor 48 Sch. 50.180 72 13.56% 27-May-16 28-May-16 2 90.00% 50.00% Ahead 9 13 4-May-16 21-May-16 18 6 9 4-May-16 21-May-16 18 502-FAEI-20020 Cables Continuity Check for 08-I1 : Closed Drain System 6 Sch. 50.180 9 100.00% 4-May-16 21-May-16 18 90.00% 100.00% Delayed 3 4 6-May-16 21-May-16 16 502-FAEI-20030 Cables Continuity Check for 09-I1 : Open Drain System 3 Sch. 50.180 4 100.00% 6-May-16 21-May-16 16 90.00% 100.00% Delayed 16 24 16-Apr-16 28-May-16 43 10 15 23-May-16 28-May-16 6 502-FAEI-20040 Cables Continuity Check for 04-I1 : Instrument Gas 10 Sch. 50.180 15 100.00% 23-May-16 28-May-16 6 90.00% 100.00% Delayed 6 9 16-Apr-16 27-May-16 42 502-FAEI-20050 Cables Continuity Check for 04-I2 : Utility Gas 6 Sch. 50.180 9 100.00% 23-May-16 27-May-16 5 90.00% 50.00% Ahead 18 18 9-Apr-16 11-May-16 33 18 18 9-Apr-16 11-May-16 33 502-FAEI-20080 Cables Continuity Check for 11-I1 : Chemical Injection 18 Sch. 50.180 18 100.00% 9-May-16 11-May-16 3 90.00% 50.00% Ahead 266 409 16-Feb-16 11-May-16 86 67 59 29-Apr-16 6-May-16 8 502-FAEI-20100 Cables Continuity Check for 13-C2 : PLC and Control system 67 Sch. 50.180 59 100.00% 4-May-16 6-May-16 3 0.00% 100.00% Delayed & Not Start 175 254 16-Feb-16 11-May-16 86 502-FAEI-20130 Cables Continuity Check for 14-E2 : AC Diesel Generators 1 Sch. 50.180 3 1.18% 4-May-16 7-May-16 4 90.00% 100.00% Delayed 502-FAEI-20140 Cables Continuity Check for 14-E3 : DC Supply 36 Sch. 50.180 26 10.24% 9-May-16 11-May-16 3 25.00% 50.00% Delayed 502-FAEI-20150 Cables Continuity Check for 14-E4 : Power & Lighting and Outlet 118 Sch. 50.180 196 77.17% 29-Apr-16 7-May-16 9 83.90% 100.00% Delayed 502-FAEI-20170 Cables Continuity Check for 14-E6 : TEG - Gas Platform 9 Sch. 50.180 13 5.12% 7-May-16 10-May-16 4 90.00% 100.00% Delayed 502-FAEI-20180 Cables Continuity Check for 16-E1 : Navigation Aids System 11 Sch. 50.180 16 6.30% 4-May-16 6-May-16 3 0.00% 100.00% Delayed & Not Start 13 74 4-May-16 6-May-16 3 502-FAEI-20190 Cables Continuity Check for 15-T1 : Comunication System 13 Sch. 50.180 74 100.00% 4-May-16 6-May-16 3 0.00% 100.00% Delayed & Not Start 11 22 4-May-16 9-May-16 6 502-FAEI-20200 Cables Continuity Check for 17-S2 : Emergency Shutdown 2 Sch. 50.180 3 13.64% 4-May-16 6-May-16 3 0.00% 100.00% Delayed & Not Start 502-FAEI-20210 Cables Continuity Check for 17-S3 : Fire & Gas Detector 5 Sch. 50.180 12 54.55% 6-May-16 9-May-16 4 0.00% 75.00% Delayed & Not Start 502-FAEI-20220 Cables Continuity Check for 17-S4 : Beacon Light & Siren 4 Sch. 50.180 7 31.82% 6-May-16 9-May-16 4 0.00% 78.57% Delayed & Not Start 604 995 -19.53% L5 L4 L5 L4 L5 L4 339 508 29-Apr-16 28-May-16 30 72 112 23-May-16 26-May-16 4 72 112 23-May-16 26-May-16 4 502-FAEI-20230 Tubings Installation for 06-I1 : HP Vent / LP Vent 72 m. 50.175 112 100.00% 23-May-16 26-May-16 4 90.00% 100.00% Delayed 189 153 3-May-16 14-May-16 12 189 153 3-May-16 14-May-16 12 502-FAEI-20240 Tubings Installation for 11-I1 : Chemical Injection 189 m. 50.175 153 100.00% 3-May-16 9-May-16 7 90.00% 100.00% Delayed 78 243 29-Apr-16 28-May-16 30 69 122 6-May-16 9-May-16 4 502-FAEI-20260 Tubings Installation for 13-C1 : Back Start 69 m. 50.175 122 100.00% 6-May-16 9-May-16 4 90.00% 100.00% Delayed 9 121 29-Apr-16 28-May-16 30 502-FAEI-20270 Tubings Installation for 14-E6 : TEG - Gas Platform 9 m. 50.175 20 16.53% 29-Apr-16 30-Apr-16 2 90.00% 100.00% Delayed 3478 12-Feb-16 30-May-16 109 2874 870 12-Feb-16 26-Feb-16 15 502-FAEI-20290 Pre-Cutting and Pre-Bending 2874 m. 50.175 870 100.00% 12-Feb-16 26-Feb-16 15 100.00% 100.00% Completed 2535 2608 11-Apr-16 30-May-16 50 483 227 11-Apr-16 30-May-16 50 483 227 11-Apr-16 30-May-16 50 502-FAEI-20310 Tubings Installation for 01-I1: Process Production 456 m. 50.175 195 85.90% 11-Apr-16 21-Apr-16 11 90.00% 100.00% Delayed 502-FAEI-20320 Tubings Installation for 10-I1 : Booster Compressor 27 m. 50.175 32 14.10% 23-May-16 30-May-16 8 90.00% 100.00% Delayed 2052 2381 11-Apr-16 18-May-16 38 1273 1529 29-Apr-16 18-May-16 20 502-FAEI-20330 Tubings Installation for 13-C3 : Wellhead Control Panel 1273 m. 50.175 1529 100.00% 29-Apr-16 18-May-16 20 90.00% 100.00% Delayed 779 852 11-Apr-16 29-Apr-16 19 502-FAEI-20340 Tubings Installation for 17-S1 : Fire Emergency Shutdown (FESD) 531 m. 50.175 579 67.96% 11-Apr-16 29-Apr-16 19 90.00% 100.00% Delayed 502-FAEI-20350 Tubings Installation for 17-S2 : Emergency Shutdown 248 m. 50.175 273 32.04% 11-Apr-16 29-Apr-16 19 90.00% 100.00% Delayed 2874 3986 -7.56% L5 L4 L5 L4 L5 L4 438 102 31-May-16 10-Jun-16 11 96 9 31-May-16 2-Jun-16 3 96 9 31-May-16 2-Jun-16 3 502-FAEI-20360 Tubings Leak Test for 06-I1 : HP Vent / LP Vent 96 m. 50.180 9 100.00% 31-May-16 2-Jun-16 3 0.00% 72.22% Delayed & Not Start Should be finished 189 50 31-May-16 10-Jun-16 11 189 50 31-May-16 10-Jun-16 11 502-FAEI-20370 Tubings Leak Test for 11-I1 : Chemical Injection 189 m. 50.180 50 100.00% 31-May-16 3-Jun-16 4 0.00% 50.00% Delayed & Not Start Should be finished 153 43 31-May-16 6-Jun-16 7 Sub-System - 7001 : Chemical (C) 100.00% 0.00% 50.00% System - 8000 : Others 42.16% 0.00% 84.88% System - 2000 : Drains & Reliefs 8.82% 0.00% 72.22% Sub-System - 2500 : Blow Down (BD) 100.00% 0.00% 72.22% System - 7000 : Chemicals 49.02% 0.00% 50.00% Status Next 2 Wks As Per Planed RemarkL3 Start Finish Dur. Tested Check Sheet : PLT-T L3 L3 90% 10% Bare Tube Leak Test 35.92% 0.00% 66.18% Sub-System - 8000D : Safety Intrergrity System (SIS) 35.78% 90.00% 100.00% 531 248 SUB-TOTAL OF TUBINGS INSTALLATION 16.56% 2874 92.44% 100.00% 456 27 System - 8000 : Others 91.30% 90.00% 100.00% Sub-System - 8000A : Process Control 64.22% 90.00% 100.00% 1273 2874 Field Installation and Hook-Up 74.99% 90.00% 100.00% System - 1000 : Process Production 8.70% 90.00% 100.00% Sub-System - 1001 : Process Liquid & Vapour (P) 100.00% 90.00% 100.00% Sub-System - 8000B : Electrical Generation and Distribution 49.79% 98.35% 100.00% 9 TPU Jacket Tube Installation 87.26% 92.50% 100.00% Preparation Works 25.01% 100.00% 100.00% 189 System - 8000 : Others 47.83% 94.16% 100.00% Sub-System - 8000A : Process Control 50.21% 90.00% 100.00% 69 90.00% 100.00% 72 System - 7000 : Chemicals 30.12% 90.00% 100.00% System - 2000 : Drains & Reliefs 22.05% Sub-System - 7001 : Chemical (C) 100.00% 90.00% 100.00% Status Next 2 Wks As Per Planed RemarkL3 Start Finish Dur. Tube Running Check Sheet : PIC-T L3 L3 90% 10% Bare Tube Installation 12.74% 91.99% 100.00% 91.21%SUB-TOTAL OF CABLES CONTINUITY & INSULATION TEST 4.13% 466 71.67% TUBINGS LEAK TEST QTY Unit Cost Code Budgeted Mhrs WTG% Baseline Activity Milestones % Actual %Plan 90.00% 100.00% Sub-System - 2500 : Blow Down (BD) 100.00% 0.00% 100.00% Sub-System - 8000D : Safety Intrergrity System (SIS) 5.38% 0.00% 79.55% 9 Sub-System - 8000C : Communication 18.09% 10 110 72.97% 94.88% 1 Sub-System - 8000B : Electrical Generation and Distribution 62.10% 45.32% 95.72% Sub-System - 8000A : Process Control 14.43% 0.00% 100.00% 18 System - 8000 : Others 41.11% 90.00% 50.00% Sub-System - 7001 : Chemical (C) 100.00% 90.00% 50.00% System - 7000 : Chemicals 1.81% 90.00% 50.00% 6 10 Sub-System - 4500 : Gas Utility (GU) 37.50% Sub-System - 4400 : Gas Instrument (GI) 62.50% 90.00% 100.00% 48 76 90.00% 3 System - 4000 : Utility Generals 2.41% 90.00% 81.25% 6 Sub-System - 2100 : Open Drain (DO) 30.77% 90.00% 100.00% Sub-System - 2001 : Closed Drain (DC) 69.23% 90.00% 100.00% RemarkL3 Start Finish Dur. Tested Check Sheet : PLT-C Activity Milestones % Actual %Plan Status Next 2 Wks As Per Planed L3 L3 90% 10% CABLES CONTINUITY & INSULATION TEST QTY Unit Cost Code Budgeted Mhrs WTG% Baseline Sub-System - 1001 : Process Liquid & Vapour (P) 100.00% 90.08% 89.45% System - 1000 : Process Production 53.37% 90.08% 89.45% 48 98.58% 100.00% 2 5 4 SUB-TOTAL OF CABLES INSTALLATION 34.40% TUBINGS INSTALLATION QTY Unit Cost Code Budgeted Mhrs WTG% Baseline Activity Milestones % Actual %Plan System - 2000 : Drains & Reliefs 1.31% 121 100.00% 13 Sub-System - 8000D : Safety Intrergrity System (SIS) 4.67% 95.25% 100.00% 9 11 Sub-System - 8000C : Communication 4.67% 90.58% 100.00% 1 36 118 67 Sub-System - 8000B : Electrical Generation and Distribution 66.53% 97.72% 100.00% Sub-System - 8000A : Process Control 24.14% 96.87% 100.00% 18 System - 8000 : Others 38.82% 97.07% System - 7000 : Chemicals 1.51% 100.00% 100.00% Sub-System - 7001 : Chemical (C) 100.00% 100.00% 100.00% Sub-System - 4500 : Gas Utility (GU) 37.79% 96.25% 100.00% 6 Sub-System - 4400 : Gas Instrument (GI) 62.21% 97.00% 100.00% 10 3 System - 4000 : Utility Generals 2.62% 96.72% 100.00% 6 Sub-System - 2100 : Open Drain (DO) 33.87% 97.50% 100.00% System - 2000 : Drains & Reliefs 1.50% 98.33% 100.00% Sub-System - 2001 : Closed Drain (DC) 66.13% 98.75% 100.00% 50 76 48 Sub-System - 1001 : Process Liquid & Vapour (P) 100.00% 99.69% 100.00% 121 45% System - 1000 : Process Production 55.55% 99.69% 100.00% Next 2 Wks As Per Planed Remark Start Finish Dur. Pulled Activity Milestones Status Glanded Terminated L3 L3 100.00% 100.00% CABLES INSTALLATION QTY Unit Cost Code Budgeted Mhrs Baseline 5 100.00% SUB-TOTAL OF CALIBRATION OF INSTRUMENTS TAG 5.37% 100.00% 100.00% 1 100.00% Sub-System - 8000D : Safety Intrergrity System (SIS) 5.80% 100.00% 100.00% WTG% % Actual %Plan L3 3 100.00% 48 100.00% Sub-System - 8000B : Electrical Generation and Distribution 1.34% 100.00% 100.00% Sub-System - 8000A : Process Control 92.86% 100.00% 100.00% 21 100.00% System - 8000 : Others 17.31% 100.00% 100.00% Sub-System - 7001 : Chemical (C) 100.00% 100.00% 100.00% System - 7000 : Chemicals 4.56% 100.00% 100.00% 10 100.00% 14 100.00% Sub-System - 4500 : Gas Utility (GU) 41.18% 100.00% 100.00% Sub-System - 4400 : Gas Instrument (GI) 58.82% 100.00% 100.00% 1 100.00% System - 4000 : Utility Generals 5.26% 100.00% 100.00% 5 100.00% Sub-System - 2500 : Blow Down (BD) 7.89% 100.00% 100.00% 8 100.00% Sub-System - 2100 : Open Drain (DO) 34.21% 100.00% 100.00% Sub-System - 2001 : Closed Drain (DC) 57.89% 100.00% 100.00% 26 100.00% System - 2000 : Drains & Reliefs 2.94% 1 100.00% 193 100.00% 28 100.00% 50 100.00% 100.00% Sub-System - 1001 : Process Liquid & Vapour (P) 100.00% 100.00% 100.00% System - 1000 : Process Production 69.94% 421 100.00% Next 2 Wks As Per Planed RemarkL3 Start Finish Dur. Calibrated Activity Milestones % Actual %Plan StatusCheck Sheet : PCC L3 L3 90% 100.00% 100.00% CALIBRATION OF INSTRUMENTS TAG QTY Unit Cost Code Budgeted Mhrs WTG% Baseline 670 670 109 109 SUB-TOTAL OF E&I SUPPORTS, LADDERS AND TRAYS 35.06% 10% Installation of E&I Trays&Ladders 31.13% 100.00% 100.00% Upper Deck 273 273 91 91 Mezzanine Deck 37 37 215 215 Cellar Deck 475 475 176 176 Sub-Cellar Deck 1 1 30 30 100.00% 100.00% Installation of E&I Supports 68.87% 100.00% 100.00% 364 364 Installation 55.90% 31 31 651 651 252 252 L3 90% 10% Fabrication 44.10% 100.00% 100.00% CHEVRON : CVX-PHASE 50 PROGRESS MEASUREMENT WORK SHEET FOR E&I AND PRE-COMMISSIONING WORKS WHP 50/2 : GAS PLATFORM WHP 50/2 : GAS PLATFORM : E&I INSTALLATION E&I SUPPORTS, LADDERS AND TRAYS QTY Unit Cost Code Budgeted Mhrs %Plan Status Next 2 Wks As Per Planed RemarkL3 Start Finish Dur. WTG% Baseline Activity Milestones % Actual Fabricated/Installed Accepted /Painted/Cleaning L3 604 Page 7 of 10 Prepared By : Nattakarn S.
  • 20.
    Activity ID ActivityName Num. Budgeted Units Planned Start Planned Finish % Actual 1-Jun-16 CHEVRON : CVX-PHASE 50 PROGRESS MEASUREMENT WORK SHEET FOR E&I AND PRE-COMMISSIONING WORKS WHP 50/2 : GAS PLATFORM 84 21 31-May-16 3-Jun-16 4 502-FAEI-20390 Tubings Leak Test for 13-C1 : Back Start 84 m. 50.180 21 100.00% 31-May-16 3-Jun-16 4 0.00% 100.00% Delayed & Not Start Should be finished 69 22 4-Jun-16 6-Jun-16 3 502-FAEI-20400 Tubings Leak Test for 14-E6 : TEG - Gas Platform 9 m. 50.180 11 50.00% 4-Jun-16 4-Jun-16 1 0.00% 100.00% Delayed & Not Start Should be started 502-FAEI-20410 Tubings Leak Test for 14-E7 : CO2 Skid - Option Gas Platform 60 m. 50.180 11 50.00% 6-Jun-16 6-Jun-16 1 0.00% 40.91% Delayed & Not Start Should be started 2535 182 31-May-16 9-Jun-16 10 483 56 8-Jun-16 9-Jun-16 2 483 56 8-Jun-16 9-Jun-16 2 502-FAEI-20420 Tubings Leak Test for 01-I1: Process Production 456 m. 50.180 45 80.36% 8-Jun-16 9-Jun-16 2 0.00% 0.00% Should be started 502-FAEI-20430 Tubings Leak Test for Booster Compressor 27 m. 50.180 11 19.64% 8-Jun-16 8-Jun-16 1 0.00% 0.00% Should be started 2052 126 31-May-16 7-Jun-16 8 1273 90 31-May-16 3-Jun-16 4 502-FAEI-20440 Tubings Leak Test for 13-C3 : Wellhead Control Panel 1273 m. 50.180 90 100.00% 31-May-16 3-Jun-16 4 0.00% 63.33% Delayed & Not Start Should be finished 779 36 6-Jun-16 7-Jun-16 2 502-FAEI-20450 Tubings Leak Test for 17-S1 : Fire Emergency Shutdown (FESD) 531 m. 50.180 18 50.00% 7-Jun-16 7-Jun-16 1 0.00% 0.00% Should be started 502-FAEI-20460 Tubings Leak Test for 17-S2 : Emergency Shutdown 248 m. 50.180 18 50.00% 6-Jun-16 6-Jun-16 1 0.00% 38.89% Delayed & Not Start Should be started 2973 284 -46.48% L5 L4 L5 L4 L5 L4 253 363 25-Apr-16 13-Jun-16 50 253 363 25-Apr-16 13-Jun-16 50 502-FAEI-20470 Hook-Up of E&I Tags for 01-I1: Process Production 145 Ea. 50.175 148 40.77% 29-Apr-16 27-May-16 29 50.07% 87.84% Delayed 502-FAEI-20480 Hook-Up of E&I Tags for 01-I2 : Production Header 28 Ea. 50.175 43 11.85% 25-Apr-16 23-May-16 29 57.86% 87.21% Delayed 502-FAEI-20490 Hook-Up of E&I Tags for 02-I1 : Test Separator 52 Ea. 50.175 75 20.66% 3-May-16 19-May-16 17 55.38% 81.33% Delayed 502-FAEI-20500 Hook-Up of E&I Tags for 03-I1 : Pig Luncher 1 Ea. 50.175 1 0.28% 18-May-16 21-May-16 4 0.00% 100.00% Delayed & Not Start 502-FAEI-20540 Hook-Up of E&I Tags for 10-I1 : Booster Compressor 27 Ea. 50.175 41 11.29% 14-May-16 2-Jun-16 20 55.56% 56.10% Delayed Should be finished 15 22 23-Apr-16 7-Jun-16 46 9 13 23-Apr-16 3-May-16 11 502-FAEI-20550 Hook-Up of E&I Tags for 08-I1 : Closed Drain System 9 Ea. 50.175 13 100.00% 23-Apr-16 3-May-16 11 53.33% 76.92% Delayed 5 8 17-May-16 21-May-16 5 502-FAEI-20560 Hook-Up of E&I Tags for 09-I1 : Open Drain System 5 Ea. 50.175 8 100.00% 17-May-16 21-May-16 5 48.00% 68.75% Delayed 1 1 6-Jun-16 7-Jun-16 2 502-FAEI-20570 Hook-Up of E&I Tags for 06-I1 : HP Vent / LP Vent 1 Ea. 50.175 1 100.00% 6-Jun-16 7-Jun-16 2 0.00% 0.00% Should be started 28 41 30-Mar-16 26-Apr-16 28 17 23 30-Mar-16 8-Apr-16 10 502-FAEI-20580 Hook-Up of E&I Tags for 04-I1 : Instrument Gas 17 Ea. 50.175 23 100.00% 30-Mar-16 8-Apr-16 10 42.35% 56.52% Delayed 11 18 1-Apr-16 26-Apr-16 26 502-FAEI-20590 Hook-Up of E&I Tags for 04-I2 : Utility Gas 11 Ea. 50.175 18 100.00% 1-Apr-16 11-Apr-16 11 43.64% 55.56% Delayed 24 35 10-May-16 14-Jun-16 36 24 35 10-May-16 14-Jun-16 36 502-FAEI-20620 Hook-Up of E&I Tags for 11-I1 : Chemical Injection 24 Ea. 50.175 35 100.00% 10-May-16 16-May-16 7 90.00% 78.57% Ahead 230 332 20-Jan-16 11-Jun-16 144 67 226 11-Apr-16 18-May-16 38 502-FAEI-20640 Hook-Up of E&I Tags for 13-C1 : Back Start 4 Ea. 50.175 7 3.10% 11-Apr-16 19-Apr-16 9 90.00% 78.57% Ahead 502-FAEI-20650 Hook-Up of E&I Tags for 13-C2 : PLC and Control system 14 Ea. 50.175 22 9.73% 30-Apr-16 14-May-16 15 62.14% 95.45% Delayed 502-FAEI-20660 Hook-Up of E&I Tags for 13-C3 : Wellhead Control Panel 49 Ea. 50.175 197 87.17% 30-Apr-16 18-May-16 19 60.00% 91.37% Delayed 132 60 20-Jan-16 11-Jun-16 144 502-FAEI-20680 Hook-Up of E&I Tags for 14-E2 : AC Diesel Generators 1 Ea. 50.175 1 1.67% 26-Apr-16 4-May-16 9 60.00% 100.00% Delayed 502-FAEI-20690 Hook-Up of E&I Tags for 14-E3 : DC Supply 7 Ea. 50.175 10 16.67% 23-Feb-16 26-Feb-16 4 55.71% 70.00% Delayed 502-FAEI-20700 Hook-Up of E&I Tags for 14-E4 : Power & Lighting and Outlet 110 Ea. 50.175 28 46.67% 20-Jan-16 24-Feb-16 36 62.18% 91.07% Delayed 502-FAEI-20720 Hook-Up of E&I Tags for 14-E6 : TEG - Gas Platform 5 Ea. 50.175 8 13.33% 16-Apr-16 25-Apr-16 10 60.00% 81.25% Delayed 502-FAEI-20730 Hook-Up of E&I Tags for 16-E1 : Navigation Aids System 9 Ea. 50.175 13 21.67% 2-Mar-16 10-Mar-16 9 53.33% 76.92% Delayed 5 7 10-Mar-16 18-Mar-16 9 502-FAEI-20740 Hook-Up of E&I Tags for 15-T1 : Comunication System 5 Ea. 50.175 7 100.00% 10-Mar-16 18-Mar-16 9 60.00% 78.57% Delayed 26 39 3-May-16 24-May-16 22 502-FAEI-20750 Hook-Up of E&I Tags for 17-S2 : Emergency Shutdown 10 Ea. 50.175 13 33.33% 3-May-16 14-May-16 12 60.00% 80.77% Delayed 502-FAEI-20760 Hook-Up of E&I Tags for 17-S3 : Fire & Gas Detector 5 Ea. 50.175 8 20.51% 17-May-16 24-May-16 8 60.00% 81.25% Delayed 502-FAEI-20770 Hook-Up of E&I Tags for 17-S4 : Beacon Light & Siren 11 Ea. 50.175 18 46.15% 3-May-16 7-May-16 5 60.00% 80.56% Delayed 550 793 -21.03% 24076 -3.42% L5 L4 L5 L4 L5 L4 704 14-Jun-16 18-Jun-16 5 84 704 14-Jun-16 18-Jun-16 5 84 704 14-Jun-16 18-Jun-16 5 502-FAPC-20470 Fuction Test of 14-E2 : AC Diesel Generators 10 Pac. 60.220 71 10.09% 16-Jun-16 17-Jun-16 2 0.00% 0.00% 502-FAPC-20480 Fuction Test of 14-E3 : DC Supply 21 Pac. 60.220 174 24.72% 16-Jun-16 17-Jun-16 2 0.00% 0.00% 502-FAPC-20490 Fuction Test of 14-E4 : Power & Lighting and Outlet 39 Pac. 60.220 322 45.74% 14-Jun-16 15-Jun-16 2 0.00% 0.00% Should be started 502-FAPC-20510 Fuction Test of 14-E6 : TEG - Gas Platform 6 Pac. 60.220 21 2.98% 18-Jun-16 18-Jun-16 1 0.00% 0.00% 502-FAPC-20520 Fuction Test of 16-E1 : Navigation Aids System 8 Pac. 60.220 116 16.48% 16-Jun-16 17-Jun-16 2 0.00% 0.00% 1241 15-Jun-16 18-Jun-16 4 237 823 15-Jun-16 18-Jun-16 4 237 823 15-Jun-16 18-Jun-16 4 502-FAPC-20540 Loop Test of 01-I1: Process Production 98 Pac. 60.225 340 41.31% 15-Jun-16 16-Jun-16 2 0.00% 0.00% Should be started 502-FAPC-20550 Loop Test of 01-I2 : Production Header 27 Pac. 60.225 94 11.42% 16-Jun-16 17-Jun-16 2 0.00% 0.00% 502-FAPC-20560 Loop Test of 02-I1 : Test Separator 55 Pac. 60.225 191 23.21% 17-Jun-16 18-Jun-16 2 0.00% 0.00% 502-FAPC-20570 Loop Test of 03-I2 : Pig Receiver - Option 12 Pac. 60.225 42 5.10% 17-Jun-16 18-Jun-16 2 0.00% 0.00% 502-FAPC-20600 Loop Test of 10-I1 : Booster Compressor 45 Pac. 60.225 156 18.96% 16-Jun-16 17-Jun-16 2 0.00% 0.00% 9 32 16-Jun-16 17-Jun-16 2 6 21 16-Jun-16 17-Jun-16 2 502-FAPC-20610 Loop Test of 08-I1 : Closed Drain System 6 Pac. 60.225 21 100.00% 16-Jun-16 17-Jun-16 2 0.00% 0.00% 3 11 16-Jun-16 17-Jun-16 2 502-FAPC-20620 Loop Test of 09-I1 : Open Drain System 3 Pac. 60.225 11 100.00% 16-Jun-16 17-Jun-16 2 0.00% 0.00% 13 32 16-Jun-16 17-Jun-16 2 9 21 16-Jun-16 17-Jun-16 2 502-FAPC-20630 Loop Test of 04-I1 : Instrument Gas 9 Pac. 60.225 21 100.00% 16-Jun-16 17-Jun-16 2 0.00% 0.00% 4 11 16-Jun-16 17-Jun-16 2 502-FAPC-20640 Loop Test of 04-I2 : Utility Gas 4 Pac. 60.225 11 100.00% 16-Jun-16 17-Jun-16 2 0.00% 0.00% 12 32 16-Jun-16 16-Jun-16 1 12 32 16-Jun-16 16-Jun-16 1 502-FAPC-20670 Loop Test of 11-I1 : Chemical Injection 12 Pac. 60.225 32 100.00% 16-Jun-16 16-Jun-16 1 0.00% 0.00% 49 322 16-Jun-16 17-Jun-16 2 30 187 16-Jun-16 17-Jun-16 2 502-FAPC-20690 Loop Test of 13-C3 : Wellhead Control Panel 30 Pac. 60.225 187 100.00% 16-Jun-16 17-Jun-16 2 0.00% 0.00% 1 4 16-Jun-16 17-Jun-16 2 502-FAPC-20700 Loop Test of 15-T1 : Comunication System 1 Pac. 60.225 4 100.00% 16-Jun-16 17-Jun-16 2 0.00% 0.00% 18 131 16-Jun-16 16-Jun-16 1 502-FAPC-20710 Loop Test of 17-S2 : Emergency Shutdown 3 Pac. 60.225 12 9.16% 16-Jun-16 16-Jun-16 1 0.00% 0.00% 502-FAPC-20720 Loop Test of 17-S3 : Fire & Gas Detector 8 Pac. 60.225 28 21.37% 16-Jun-16 16-Jun-16 1 0.00% 0.00% 502-FAPC-20730 Loop Test of 17-S4 : Beacon Light & Siren 7 Pac. 60.225 91 69.47% 16-Jun-16 16-Jun-16 1 0.00% 0.00% 404 1945 0.00% L5 L4 L5 L4 L5 L4 502-FAPC-20740 Platform Site Acceptance Test - SAT 100 Pac. 60.235 555 20-Jun-16 25-Jun-16 6 100 555 0.00% 2500 0.00% -3.10% SUB-TOTAL OF TUBINGS LEAK TEST 1.18% 0.00% 46.48% Sub-System - 8000A : Process Control 71.43% 0.00% 63.33% Sub-System - 8000D : Safety Intrergrity System (SIS) 28.57% 0.00% 19.44% 0.00% Sub-System - 1001 : Process Liquid & Vapour (P) 100.00% 0.00% 0.00% System - 8000 : Others 69.23% 0.00% 50.79% System - 1000 : Process Production 30.77% 0.00% Sub-System - 8000B : Electrical Generation and Distribution 51.16% 0.00% 70.45% TPU Jacket Tube Leak Test 64.08% 0.00% 35.16% Sub-System - 8000A : Process Control 48.84% 0.00% 100.00% 85.71% 88.80%OVERALL PROGRESS OF WHP 50/2 : GAS PLATFORM 26576 100.00% 0.00% TOTAL OF WHP 50/2 : GAS PLATFORM : E&I PRE-COMMISSIONING 9.41% 0.00% 0.00% 100.00% 0.00% 0.00% SUB-TOTAL OF SITE ACCEPTANC TEST - SAT 22.20% 0.00% RemarkL3 Start Finish Dur. Activity Milestones % Actual %Plan Status Next 2 Wks As Per Planed SAT Completion L3 L3 100% 0.00% SITE ACCEPTANC TEST - SAT QTY Unit Cost Code Budgeted Mhrs WTG% Baseline SUB-TOTAL OF LOOP/ FUNCTION TEST 77.80% 0.00% 0.00% 0.00% Sub-System - 8000D : Safety Intrergrity System (SIS) 40.68% 0.00% 0.00% Sub-System - 8000C : Communication 1.24% 0.00% 0.00% Sub-System - 8000A : Process Control 58.07% 0.00% 0.00% System - 8000 : Others 25.95% 0.00% 0.00% Sub-System - 7001 : Chemical (C) 100.00% 0.00% 0.00% System - 7000 : Chemicals 2.58% 0.00% 0.00%Sub-System - 4500 : Gas Utility (GU) 34.38% Sub-System - 4400 : Gas Instrument (GI) 65.63% 0.00% 0.00% 0.00% 0.00% System - 4000 : Utility Generals 2.58% 0.00% 0.00% Sub-System - 2100 : Open Drain (DO) 34.38% 0.00% 0.00% Sub-System - 2001 : Closed Drain (DC) 65.63% 0.00% 0.00% System - 2000 : Drains & Reliefs 2.58% Sub-System - 1001 : Process Liquid & Vapour (P) 100.00% 0.00% 0.00% 0.00% 0.00% System - 1000 : Process Production 66.32% 0.00% 0.00% Instrumentation 63.80% Sub-System - 8000B : Electrical Generation and Distribution 100.00% 0.00% 0.00% System - 8000 : Others 100.00% 0.00% 0.00% Electrical 36.20% 0.00% 0.00% %Plan Status Next 2 Wks As Per Planed RemarkL3 Start Finish Dur. WTG% Baseline Activity Milestones % Actual Tested Check Sheet : PLT-L & PFT WHP 50/2 : GAS PLATFORM : E&I PRE-COMMISSIONING LOOP/ FUNCTION TEST QTY Unit Cost Code Budgeted Mhrs TOTAL OF WHP 50/2 : GAS PLATFORM : E&I INSTALLATION 90.59% 94.61% 98.02% L3 L3 90% 10% 81.46%SUB-TOTAL OF HOOK-UP OF E&I TAG ITEMS 3.29% 60.44% 11 Sub-System - 8000B : Electrical Generation and Distribution 18.07% 58.86% 83.33% 1 6 1 60.00% 78.57% Sub-System - 8000D : Safety Intrergrity System (SIS) 11.75% 60.00% 79.49% Sub-System - 8000C : Communication 2.11% 110 8 5 8 60.57% 88.40% Sub-System - 8000A : Process Control 68.07% 61.14% 91.59% System - 8000 : Others 41.87% 90.00% 78.57% Sub-System - 7001 : Chemical (C) 100.00% 90.00% 78.57% 24 24 43.64% 55.56%Sub-System - 4500 : Gas Utility (GU) 43.90% 42.92% 54.88% Sub-System - 4400 : Gas Instrument (GI) 56.10% 42.35% 56.52% 8 System - 7000 : Chemicals 4.41% System - 4000 : Utility Generals 5.17% 48.00% 68.75% Sub-System - 2500 : Blow Down (BD) 4.55% 0.00% 0.00% Sub-System - 2100 : Open Drain (DO) 36.36% 8 4 48.97% 70.45% Sub-System - 2001 : Closed Drain (DC) 59.09% 53.33% 76.92% System - 2000 : Drains & Reliefs 2.77% 25 79.06% Sub-System - 1001 : Process Liquid & Vapour (P) 100.00% 60.14% 79.06% System - 1000 : Process Production 45.78% 60.14% HOOK-UP OF E&I TAG ITEMS QTY Unit Cost Code Budgeted Mhrs 505 38 Next 2 Wks As Per Planed RemarkL3 Start Finish Dur. Activity Milestones % Actual %Plan StatusL3 L3 WTG% Baseline Installed Hook-Up Check Sheet : PIC-H 60% 30% 10% 27 48 121 4 4 10 5 14 1 49 5 12 Page 8 of 10 Prepared By : Nattakarn S.
  • 21.
    Activity ID ActivityName Num. Budgeted Units Planned Start Planned Finish % Actual 1-Jun-16 L5 L4 L5 L4 L5 L4 1327 3723 21-Aug-15 28-Oct-15 69 505-FAEI-23720 Fabrication of E&I Supports for Sub-Cellar Deck 31 Ea. 50.170 98 2.63% 24-Aug-15 8-Sep-15 16 100.00% 100.00% Completed 505-FAEI-23730 Fabrication of E&I Supports for Cellar Deck 667 Ea. 50.170 1915 51.44% 21-Aug-15 16-Oct-15 57 100.00% 100.00% Completed 505-FAEI-23740 Fabrication of E&I Supports for Mezzanine Deck 250 Ea. 50.170 525 14.10% 25-Sep-15 28-Oct-15 34 100.00% 100.00% Completed 505-FAEI-23750 Fabrication of E&I Supports for Upper Deck 379 Ea. 50.170 1185 31.83% 24-Aug-15 2-Oct-15 40 100.00% 100.00% Completed 4719 30-Oct-15 16-Apr-16 170 1327 3250 30-Oct-15 21-Mar-16 144 31 106 3.26% 25-Dec-15 10-Feb-16 48 100.00% 100.00% 505-FAEI-23760 Installation of E&I Support at Sub-Cellar Deck - Assembly Bay 1 Ea. 50.170 12 11.32% 25-Dec-15 5-Jan-16 12 100.00% 100.00% Completed 505-FAEI-23770 Installation of E&I Support at Sub-Cellar Deck - Erection Area 30 Ea. 50.170 94 88.68% 25-Jan-16 10-Feb-16 17 100.00% 100.00% Completed 667 1614 49.66% 30-Oct-15 20-Feb-16 114 100.00% 100.00% 505-FAEI-23780 Installation of E&I Support at Cellar Deck - Assembly Bay 481 Ea. 50.170 1035 64.13% 30-Oct-15 23-Nov-15 25 100.00% 100.00% Completed 505-FAEI-23790 Installation of E&I Support at Cellar Deck - Erection Area 186 Ea. 50.170 579 35.87% 8-Dec-15 20-Feb-16 75 100.00% 100.00% Completed 250 546 16.80% 20-Nov-15 21-Mar-16 123 100.00% 100.00% 505-FAEI-23800 Installation of E&I Support at Mezzanine Deck - Assembly Bay 37 Ea. 50.170 118 21.61% 20-Nov-15 9-Dec-15 20 100.00% 100.00% Completed 505-FAEI-23810 Installation of E&I Support at Mezzanine Deck - Erection Area 213 Ea. 50.170 428 78.39% 25-Feb-16 21-Mar-16 26 100.00% 100.00% Completed 379 984 30.28% 27-Nov-15 28-Jan-16 63 100.00% 100.00% 505-FAEI-23820 Installation of E&I Support at UpperDeck - Assembly Bay 282 Ea. 50.170 662 67.28% 27-Nov-15 24-Dec-15 28 100.00% 100.00% Completed 505-FAEI-23830 Installation of E&I Support at UpperDeck - Erection Area 97 Ea. 50.170 322 32.72% 7-Jan-16 28-Jan-16 22 100.00% 100.00% Completed 779 1469 18-Dec-15 16-Apr-16 121 505-FAEI-23840 Installation of Cable Trays&Ladders 670 m. 50.170 942 64.13% 18-Dec-15 29-Jan-16 43 100.00% 100.00% Completed 505-FAEI-23850 Installation of Tubing Trays&Ladders 109 m. 50.170 527 35.87% 30-Mar-16 16-Apr-16 18 100.00% 100.00% Completed 8442 0.00% L5 L4 L5 L4 L5 L4 305 905 2-Nov-15 2-Mar-16 122 305 905 2-Nov-15 2-Mar-16 122 505-FAEI-23860 Calibration of Instrument Tags - 01-I1: Process Production 193 Ea. 50.165 535 59.12% 2-Nov-15 26-Dec-15 55 100.00% 100.00% Completed 505-FAEI-23870 Calibration of Instrument Tags - 01-I2 : Production Header 28 Ea. 50.165 76 8.40% 18-Nov-15 1-Dec-15 14 100.00% 100.00% Completed 505-FAEI-23880 Calibration of Instrument Tags - 02-I1 : Test Separator 50 Ea. 50.165 140 15.47% 1-Dec-15 29-Dec-15 29 100.00% 100.00% Completed 505-FAEI-23890 Calibration of Instrument Tags - 03-I1 : Pig Luncher 1 Ea. 50.165 3 0.33% 8-Jan-16 11-Jan-16 4 100.00% 100.00% Completed 505-FAEI-23930 Calibration of Instrument Tags - 10-I1 : Booster Compressor 26 Ea. 50.165 75 8.29% 29-Dec-15 13-Jan-16 16 100.00% 100.00% Completed 14 38 24-Oct-15 18-Dec-15 56 8 22 24-Oct-15 24-Oct-15 1 505-FAEI-23940 Calibration of Instrument Tags - 08-I1 : Closed Drain System 8 Ea. 50.165 22 100.00% 24-Oct-15 24-Oct-15 1 100.00% 100.00% Completed 5 13 14-Dec-15 15-Dec-15 2 505-FAEI-23950 Calibration of Instrument Tags - 09-I1 : Open Drain System 5 Ea. 50.165 13 100.00% 14-Dec-15 15-Dec-15 2 100.00% 100.00% Completed 1 3 16-Dec-15 18-Dec-15 3 505-FAEI-23960 Calibration of Instrument Tags - 06-I1 : HP Vent / LP Vent 1 Ea. 50.165 3 100.00% 16-Dec-15 18-Dec-15 3 100.00% 100.00% Completed 24 68 12-Dec-15 26-Dec-15 15 14 40 15-Dec-15 18-Dec-15 4 505-FAEI-23970 Calibration of Instrument Tags - 04-I1 : Instrument Gas 14 Ea. 50.165 40 100.00% 15-Dec-15 18-Dec-15 4 100.00% 100.00% Completed 10 28 12-Dec-15 26-Dec-15 15 505-FAEI-23980 Calibration of Instrument Tags - 04-I2 : Utility Gas 10 Ea. 50.165 28 100.00% 22-Dec-15 26-Dec-15 5 100.00% 100.00% Completed 21 59 3-Oct-15 7-Nov-15 36 21 59 3-Oct-15 7-Nov-15 36 505-FAEI-24010 Calibration of Instrument Tags - 11-I1 : Chemical Injection 21 Ea. 50.165 59 100.00% 3-Oct-15 15-Oct-15 13 100.00% 100.00% Completed 57 224 8-Oct-15 30-Jan-16 115 51 208 8-Oct-15 19-Dec-15 73 505-FAEI-24030 Calibration of Instrument Tags - 13-C1 : Back Start 3 Ea. 50.165 8 3.85% 18-Dec-15 19-Dec-15 2 100.00% 100.00% Completed 505-FAEI-24040 Calibration of Instrument Tags - 13-C3 : Wellhead Control Panel 48 Ea. 50.165 200 96.15% 8-Oct-15 7-Nov-15 31 100.00% 100.00% Completed 1 3 21-Dec-15 22-Dec-15 2 505-FAEI-24060 Calibration of Instrument Tags - 14-E6 : TEG - Gas Platform 1 Ea. 50.165 3 100.00% 21-Dec-15 22-Dec-15 2 100.00% 100.00% Completed 5 13 29-Jan-16 30-Jan-16 2 505-FAEI-24070 Calibration of Instrument Tags - 17-S3 : Fire & Gas Detector 5 Ea. 50.165 13 100.00% 29-Jan-16 30-Jan-16 2 100.00% 100.00% Completed 421 1294 0.00% 1st 2nd 1st 2nd L5 L4 20.0% 20.0% 7.5% 7.5% L5 L4 L5 L4 253 4601 10-Mar-16 19-May-16 71 253 4601 10-Mar-16 19-May-16 71 505-FAEI-24080 Cables Installation for 01-I1: Process Production 115 Sch. 50.175 1968 42.77% 10-Mar-16 22-Apr-16 44 115 115 115 92.50% 97.38% Delayed 505-FAEI-24090 Cables Installation for 01-I2 : Production Header 38 Sch. 50.175 678 14.74% 19-Apr-16 7-May-16 19 36 38 38 91.45% 100.00% Delayed 505-FAEI-24100 Cables Installation for 02-I1 : Test Separator 64 Sch. 50.175 1033 22.45% 27-Apr-16 16-May-16 20 43 64 64 85.94% 100.00% Delayed 505-FAEI-24140 Cables Installation for 10-I1 : Booster Compressor 36 Sch. 50.175 651 14.15% 21-Apr-16 10-May-16 20 36 36 36 92.50% 82.49% Ahead 9 124 18-Apr-16 2-Jun-16 46 6 82 24-May-16 2-Jun-16 10 505-FAEI-24150 Cables Installation for 08-I1 : Closed Drain System 6 Sch. 50.175 82 100.00% 24-May-16 2-Jun-16 10 6 6 6 92.50% 100.00% Delayed Should be finished 3 42 18-Apr-16 26-Apr-16 9 505-FAEI-24160 Cables Installation for 09-I1 : Open Drain System 3 Sch. 50.175 42 100.00% 18-Apr-16 26-Apr-16 9 3 3 3 92.50% 100.00% Delayed 16 217 25-Mar-16 23-Apr-16 30 10 135 9-Apr-16 23-Apr-16 15 505-FAEI-24170 Cables Installation for 04-I1 : Instrument Gas 10 Sch. 50.175 135 100.00% 9-Apr-16 23-Apr-16 15 6 10 10 84.50% 100.00% Delayed 6 82 25-Mar-16 23-Apr-16 30 505-FAEI-24180 Cables Installation for 04-I2 : Utility Gas 6 Sch. 50.175 82 100.00% 9-Apr-16 23-Apr-16 15 3 6 6 82.50% 100.00% Delayed 9 125 1-Apr-16 19-May-16 49 9 125 1-Apr-16 19-May-16 49 505-FAEI-24210 Cables Installation for 11-I1 : Chemical Injection 9 Sch. 50.175 125 100.00% 1-Apr-16 7-Apr-16 7 9 9 9 92.50% 72.40% Ahead 264 3215 14-Dec-15 24-May-16 163 65 776 14-Dec-15 5-Mar-16 83 505-FAEI-24230 Cables Installation for 13-C2 : PLC and Control system 65 Sch. 50.175 776 100.00% 19-Feb-16 5-Mar-16 16 52 65 14 27 85.73% 100.00% Delayed 175 2139 19-Dec-15 24-May-16 158 505-FAEI-24260 Cables Installation for 14-E2 : AC Diesel Generators 1 Sch. 50.175 16 0.75% 11-Mar-16 14-Mar-16 4 1 1 85.00% 100.00% Delayed 505-FAEI-24270 Cables Installation for 14-E3 : DC Supply 36 Sch. 50.175 368 17.20% 19-Feb-16 12-Mar-16 23 23 32 21 20 84.10% 94.29% Delayed 505-FAEI-24280 Cables Installation for 14-E4 : Power & Lighting and Outlet 118 Sch. 50.175 1480 69.19% 19-Dec-15 16-Jan-16 29 118 118 104 99 97.90% 100.00% Delayed 505-FAEI-24300 Cables Installation for 14-E6 : TEG - Gas Platform 9 Sch. 50.175 125 5.84% 19-Mar-16 26-Mar-16 8 9 9 85.00% 100.00% Delayed 505-FAEI-24310 Cables Installation for 16-E1 : Navigation Aids System 11 Sch. 50.175 150 7.01% 25-Dec-15 16-Jan-16 23 11 11 85.00% 93.33% Delayed 13 150 19-Feb-16 18-Apr-16 60 505-FAEI-24320 Cables Installation for 15-T1 : Comunication System 13 Sch. 50.175 150 100.00% 19-Feb-16 18-Apr-16 60 8 6 3 3 70.00% 94.00% Delayed 11 150 30-Jan-16 19-Apr-16 81 505-FAEI-24330 Cables Installation for 17-S2 : Emergency Shutdown 2 Sch. 50.175 27 18.00% 30-Jan-16 6-Feb-16 8 2 2 2 92.50% 72.22% Ahead 505-FAEI-24340 Cables Installation for 17-S3 : Fire & Gas Detector 5 Sch. 50.175 68 45.33% 11-Mar-16 14-Mar-16 4 5 5 5 92.50% 72.79% Ahead 505-FAEI-24350 Cables Installation for 17-S4 : Beacon Light & Siren 4 Sch. 50.175 55 36.67% 8-Apr-16 19-Apr-16 12 4 4 4 92.50% 72.73% Ahead 551 8282 490 540 142 447 -5.72% L5 L4 L5 L4 L5 L4 253 531 29-Apr-16 30-May-16 32 253 531 29-Apr-16 30-May-16 32 505-FAEI-24360 Cables Continuity Check for 01-I1: Process Production 115 Sch. 50.180 218 41.05% 6-May-16 13-May-16 8 32.87% 96.10% Delayed 505-FAEI-24370 Cables Continuity Check for 01-I2 : Production Header 38 Sch. 50.180 75 14.12% 12-May-16 14-May-16 3 85.26% 100.00% Delayed 505-FAEI-24380 Cables Continuity Check for 02-I1 : Test Separator 64 Sch. 50.180 135 25.42% 21-May-16 25-May-16 5 50.63% 69.63% Delayed 505-FAEI-24420 Cables Continuity Check for 10-I1 : Booster Compressor 36 Sch. 50.180 72 13.56% 27-May-16 30-May-16 4 90.00% 50.00% Ahead 9 13 9-May-16 13-May-16 5 6 9 9-May-16 11-May-16 3 505-FAEI-24430 Cables Continuity Check for 08-I1 : Closed Drain System 6 Sch. 50.180 9 100.00% 9-May-16 11-May-16 3 0.00% 100.00% Delayed & Not Start 3 4 11-May-16 13-May-16 3 505-FAEI-24440 Cables Continuity Check for 09-I1 : Open Drain System 3 Sch. 50.180 4 100.00% 11-May-16 13-May-16 3 0.00% 100.00% Delayed & Not Start 16 24 13-May-16 13-Jun-16 32 10 15 13-May-16 16-May-16 4 505-FAEI-24450 Cables Continuity Check for 04-I1 : Instrument Gas 10 Sch. 50.180 15 100.00% 13-May-16 16-May-16 4 0.00% 100.00% Delayed & Not Start 6 9 16-May-16 13-Jun-16 29 505-FAEI-24460 Cables Continuity Check for 04-I2 : Utility Gas 6 Sch. 50.180 9 100.00% 16-May-16 18-May-16 3 0.00% 61.11% Delayed & Not Start 9 18 24-May-16 11-Jun-16 19 9 18 24-May-16 11-Jun-16 19 505-FAEI-24490 Cables Continuity Check for 11-I1 : Chemical Injection 9 Sch. 50.180 18 100.00% 9-Jun-16 11-Jun-16 3 0.00% 0.00% Should be started 264 409 4-Apr-16 11-Jun-16 69 65 59 14-May-16 23-May-16 10 505-FAEI-24510 Cables Continuity Check for 13-C2 : PLC and Control system 65 Sch. 50.180 59 100.00% 14-May-16 17-May-16 4 0.00% 100.00% Delayed & Not Start 175 254 4-Apr-16 31-May-16 58 505-FAEI-24540 Cables Continuity Check for 14-E2 : AC Diesel Generators 1 Sch. 50.180 3 1.18% 14-May-16 17-May-16 4 0.00% 100.00% Delayed & Not Start 505-FAEI-24550 Cables Continuity Check for 14-E3 : DC Supply 36 Sch. 50.180 26 10.24% 21-May-16 24-May-16 4 0.00% 50.00% Delayed & Not Start 505-FAEI-24560 Cables Continuity Check for 14-E4 : Power & Lighting and Outlet 118 Sch. 50.180 196 77.17% 14-May-16 23-May-16 10 0.00% 100.00% Delayed & Not Start 505-FAEI-24580 Cables Continuity Check for 14-E6 : TEG - Gas Platform 9 Sch. 50.180 13 5.12% 17-May-16 19-May-16 3 0.00% 100.00% Delayed & Not Start 505-FAEI-24590 Cables Continuity Check for 16-E1 : Navigation Aids System 11 Sch. 50.180 16 6.30% 19-May-16 23-May-16 5 0.00% 50.00% Delayed & Not Start 13 74 8-Jun-16 10-Jun-16 3 505-FAEI-24600 Cables Continuity Check for 15-T1 : Comunication System 13 Sch. 50.180 74 100.00% 8-Jun-16 10-Jun-16 3 0.00% 0.00% Should be started 11 22 8-Jun-16 11-Jun-16 4 505-FAEI-24610 Cables Continuity Check for 17-S2 : Emergency Shutdown 2 Sch. 50.180 3 13.64% 8-Jun-16 10-Jun-16 3 0.00% 0.00% Should be started 505-FAEI-24620 Cables Continuity Check for 17-S3 : Fire & Gas Detector 5 Sch. 50.180 12 54.55% 9-Jun-16 11-Jun-16 3 0.00% 0.00% Should be started 505-FAEI-24630 Cables Continuity Check for 17-S4 : Beacon Light & Siren 4 Sch. 50.180 7 31.82% 9-Jun-16 11-Jun-16 3 0.00% 0.00% Should be started 551 995 -47.41% L5 L4 L5 L4 L5 L4 378 508 12-May-16 15-Jun-16 35 96 112 12-May-16 13-May-16 2 96 112 12-May-16 13-May-16 2 505-FAEI-24640 Tubings Installation for 06-I1 : HP Vent / LP Vent 96 m. 50.175 112 100.00% 12-May-16 13-May-16 2 0.00% 50.00% Delayed & Not Start 189 153 12-May-16 15-Jun-16 35 189 153 12-May-16 15-Jun-16 35 505-FAEI-24650 Tubings Installation for 11-I1 : Chemical Injection 189 m. 50.175 153 100.00% 12-May-16 16-May-16 5 74.76% 100.00% Delayed 93 243 12-May-16 16-May-16 5 84 122 12-May-16 14-May-16 3 505-FAEI-24670 Tubings Installation for 13-C1 : Back Start 84 m. 50.175 122 100.00% 12-May-16 14-May-16 3 54.64% 100.00% Delayed 9 121 13-May-16 16-May-16 4 505-FAEI-24680 Tubings Installation for 14-E6 : TEG - Gas Platform 9 m. 50.175 20 16.53% 13-May-16 13-May-16 1 90.00% 100.00% Delayed 3478 4-May-16 8-Jun-16 36 2913 870 4-May-16 8-Jun-16 36 505-FAEI-24700 Pre-Cutting and Pre-Bending 2913 m. 50.175 870 100.00% 4-May-16 8-Jun-16 36 90.35% 85.34% Ahead Should be finished 2535 2608 12-May-16 7-Jun-16 27 483 227 12-May-16 28-May-16 17 483 227 12-May-16 28-May-16 17 505-FAEI-24720 Tubings Installation for 01-I1: Process Production 456 m. 50.175 195 85.90% 12-May-16 19-May-16 8 75.20% 100.00% Delayed 505-FAEI-24730 Tubings Installation for 10-I1 : Booster Compressor 27 m. 50.175 32 14.10% 21-May-16 28-May-16 8 90.00% 62.50% Ahead 2052 2381 12-May-16 7-Jun-16 27 1273 1529 12-May-16 7-Jun-16 27 505-FAEI-24740 Tubings Installation for 13-C3 : Wellhead Control Panel 1273 m. 50.175 1529 100.00% 12-May-16 7-Jun-16 27 90.00% 82.83% Ahead Should be finished 779 852 12-May-16 28-May-16 17 505-FAEI-24750 Tubings Installation for 17-S1 : Fire Emergency Shutdown (FESD) 531 m. 50.175 579 67.96% 12-May-16 28-May-16 17 49.83% 83.77% Delayed 505-FAEI-24760 Tubings Installation for 17-S2 : Emergency Shutdown 248 m. 50.175 273 32.04% 12-May-16 28-May-16 17 54.44% 83.70% Delayed 2913 3986 -7.92% L5 L4 L5 L4 L5 L4 344 102 14-May-16 14-Jun-16 32 96 9 9-Jun-16 10-Jun-16 2 96 9 9-Jun-16 10-Jun-16 2 505-FAEI-24770 Tubings Leak Test for 06-I1 : HP Vent / LP Vent 96 m. 50.180 9 100.00% 9-Jun-16 10-Jun-16 2 0.00% 0.00% Should be started 92 50 9-Jun-16 14-Jun-16 6 92 50 9-Jun-16 14-Jun-16 6 505-FAEI-24780 Tubings Leak Test for 11-I1 : Chemical Injection 92 m. 50.180 50 100.00% 9-Jun-16 13-Jun-16 5 0.00% 0.00% Should be started 156 43 14-May-16 18-May-16 5 Sub-System - 7001 : Chemical (C) 100.00% 0.00% 0.00% System - 8000 : Others 42.16% 0.00% 0.00% System - 2000 : Drains & Reliefs 8.82% 0.00% 0.00% Sub-System - 2500 : Blow Down (BD) 100.00% 0.00% 0.00% System - 7000 : Chemicals 49.02% 0.00% 0.00% Status Next 2 Wks As Per Planed RemarkL3 Start Finish Dur. Tested Check Sheet : PLT-T L3 L3 90% 10% Bare Tube Leak Test 35.92% 0.00% 0.00% Sub-System - 8000D : Safety Intrergrity System (SIS) 35.78% 51.31% 83.80% 294 150 SUB-TOTAL OF TUBINGS INSTALLATION 16.56% 2342 77.14% 85.06% 381 27 System - 8000 : Others 91.30% 76.15% 83.18% Sub-System - 8000A : Process Control 64.22% 90.00% 82.83% 1273 Field Installation and Hook-Up 74.99% 76.25% 84.18% System - 1000 : Process Production 8.70% 77.28% 94.71% 2632 Sub-System - 1001 : Process Liquid & Vapour (P) 100.00% 77.28% 94.71% Sub-System - 8000B : Electrical Generation and Distribution 49.79% 98.35% 100.00% 9 TPU Jacket Tube Installation 87.26% 79.78% 84.49% Preparation Works 25.01% 90.35% 85.34% 157 System - 8000 : Others 47.83% 76.41% 100.00% Sub-System - 8000A : Process Control 50.21% 54.64% 100.00% 51 0.00% 50.00% System - 7000 : Chemicals 30.12% 74.76% 100.00% System - 2000 : Drains & Reliefs 22.05% Sub-System - 7001 : Chemical (C) 100.00% 74.76% 100.00% Status Next 2 Wks As Per Planed RemarkL3 Start Finish Dur. Tube Running Check Sheet : PIC-T L3 L3 90% 10% Bare Tube Installation 12.74% 59.06% 88.98% 77.54%SUB-TOTAL OF CABLES CONTINUITY & INSULATION TEST 4.13% 150 30.13% TUBINGS LEAK TEST QTY Unit Cost Code Budgeted Mhrs WTG% Baseline Activity Milestones % Actual %Plan 0.00% 50.00% Sub-System - 2500 : Blow Down (BD) 100.00% 0.00% 0.00% Sub-System - 8000D : Safety Intrergrity System (SIS) 5.38% 0.00% 0.00% Sub-System - 8000C : Communication 18.09% 0.00% 91.73%Sub-System - 8000B : Electrical Generation and Distribution 62.10% 0.00% 71.39% Sub-System - 8000A : Process Control 14.43% 0.00% 100.00% System - 8000 : Others 41.11% 0.00% 0.00% Sub-System - 7001 : Chemical (C) 100.00% 0.00% 0.00% System - 7000 : Chemicals 1.81% 0.00% 61.11%Sub-System - 4500 : Gas Utility (GU) 37.50% Sub-System - 4400 : Gas Instrument (GI) 62.50% 0.00% 100.00% 36 36 0.00% System - 4000 : Utility Generals 2.41% 0.00% 85.42% Sub-System - 2100 : Open Drain (DO) 30.77% 0.00% 100.00% Sub-System - 2001 : Closed Drain (DC) 69.23% 0.00% 100.00% RemarkL3 Start Finish Dur. Tested Check Sheet : PLT-C Activity Milestones % Actual %Plan Status Next 2 Wks As Per Planed L3 L3 90% 10% CABLES CONTINUITY & INSULATION TEST QTY Unit Cost Code Budgeted Mhrs WTG% Baseline Sub-System - 1001 : Process Liquid & Vapour (P) 100.00% 56.45% 83.90% System - 1000 : Process Production 53.37% 56.45% 83.90% 36 90.90% 96.62% 2 5 4 SUB-TOTAL OF CABLES INSTALLATION 34.40% TUBINGS INSTALLATION QTY Unit Cost Code Budgeted Mhrs WTG% Baseline Activity Milestones % Actual %Plan System - 2000 : Drains & Reliefs 1.31% 42 94.00% 13 Sub-System - 8000D : Safety Intrergrity System (SIS) 4.67% 92.50% 72.33% 9 11 Sub-System - 8000C : Communication 4.67% 70.00% 98.57% 1 36 118 65 Sub-System - 8000B : Electrical Generation and Distribution 66.53% 93.77% 97.50% Sub-System - 8000A : Process Control 24.14% 85.73% 100.00% 9 System - 8000 : Others 38.82% 90.66% System - 7000 : Chemicals 1.51% 92.50% 72.40% Sub-System - 7001 : Chemical (C) 100.00% 92.50% 72.40% Sub-System - 4500 : Gas Utility (GU) 37.79% 82.50% 100.00% 6 Sub-System - 4400 : Gas Instrument (GI) 62.21% 84.50% 100.00% 10 3 System - 4000 : Utility Generals 2.62% 83.74% 100.00% 6 Sub-System - 2100 : Open Drain (DO) 33.87% 92.50% 100.00% System - 2000 : Drains & Reliefs 1.50% 92.50% 100.00% Sub-System - 2001 : Closed Drain (DC) 66.13% 92.50% 100.00% 38 64 36 Sub-System - 1001 : Process Liquid & Vapour (P) 100.00% 91.31% 96.41% 115 45% System - 1000 : Process Production 55.55% 91.31% 96.41% Next 2 Wks As Per Planed Remark Start Finish Dur. Pulled Activity Milestones Status Glanded Terminated L3 L3 100.00% 100.00% CABLES INSTALLATION QTY Unit Cost Code Budgeted Mhrs Baseline 5 100.00% SUB-TOTAL OF CALIBRATION OF INSTRUMENTS TAG 5.37% 100.00% 100.00% 1 100.00% Sub-System - 8000D : Safety Intrergrity System (SIS) 5.80% 100.00% 100.00% WTG% % Actual %Plan L3 3 100.00% 48 100.00% Sub-System - 8000B : Electrical Generation and Distribution 1.34% 100.00% 100.00% Sub-System - 8000A : Process Control 92.86% 100.00% 100.00% 21 100.00% System - 8000 : Others 17.31% 100.00% 100.00% Sub-System - 7001 : Chemical (C) 100.00% 100.00% 100.00% System - 7000 : Chemicals 4.56% 100.00% 100.00% 10 100.00% 14 100.00% Sub-System - 4500 : Gas Utility (GU) 41.18% 100.00% 100.00% Sub-System - 4400 : Gas Instrument (GI) 58.82% 100.00% 100.00% 1 100.00% System - 4000 : Utility Generals 5.26% 100.00% 100.00% 5 100.00% Sub-System - 2500 : Blow Down (BD) 7.89% 100.00% 100.00% 8 100.00% Sub-System - 2100 : Open Drain (DO) 34.21% 100.00% 100.00% Sub-System - 2001 : Closed Drain (DC) 57.89% 100.00% 100.00% 26 100.00% System - 2000 : Drains & Reliefs 2.94% 1 100.00% 193 100.00% 28 100.00% 50 100.00% 100.00% Sub-System - 1001 : Process Liquid & Vapour (P) 100.00% 100.00% 100.00% System - 1000 : Process Production 69.94% 421 100.00% Next 2 Wks As Per Planed RemarkL3 Start Finish Dur. Calibrated Activity Milestones % Actual %Plan StatusCheck Sheet : PCC L3 L3 90% 100.00% 100.00% CALIBRATION OF INSTRUMENTS TAG QTY Unit Cost Code Budgeted Mhrs WTG% Baseline 670 670 109 109 SUB-TOTAL OF E&I SUPPORTS, LADDERS AND TRAYS 35.06% 10% Installation of E&I Trays&Ladders 31.13% 100.00% 100.00% Upper Deck 282 282 97 97 Mezzanine Deck 37 37 213 213 Cellar Deck 481 481 186 186 Sub-Cellar Deck 1 1 30 30 100.00% 100.00% Installation of E&I Supports 68.87% 100.00% 100.00% 379 379 Installation 55.90% 31 31 667 667 250 250 L3 90% 10% Fabrication 44.10% 100.00% 100.00% CHEVRON : CVX-PHASE 50 PROGRESS MEASUREMENT WORK SHEET FOR E&I AND PRE-COMMISSIONING WORKS WHP 50/5 : GAS PLATFORM WHP 50/5 : GAS PLATFORM : E&I INSTALLATION E&I SUPPORTS, LADDERS AND TRAYS QTY Unit Cost Code Budgeted Mhrs %Plan Status Next 2 Wks As Per Planed RemarkL3 Start Finish Dur. WTG% Baseline Activity Milestones % Actual Fabricated/Installed Accepted /Painted/Cleaning L3 551 Page 9 of 10 Prepared By : Nattakarn S.
  • 22.
    Activity ID ActivityName Num. Budgeted Units Planned Start Planned Finish % Actual 1-Jun-16 CHEVRON : CVX-PHASE 50 PROGRESS MEASUREMENT WORK SHEET FOR E&I AND PRE-COMMISSIONING WORKS WHP 50/5 : GAS PLATFORM 84 21 14-May-16 18-May-16 5 505-FAEI-24800 Tubings Leak Test for 13-C1 : Back Start 84 m. 50.180 21 100.00% 14-May-16 18-May-16 5 0.00% 0.00% 72 22 17-May-16 18-May-16 2 505-FAEI-24810 Tubings Leak Test for 14-E6 : TEG - Gas Platform 12 m. 50.180 11 50.00% 17-May-16 18-May-16 2 0.00% 0.00% 505-FAEI-24820 Tubings Leak Test for 14-E7 : CO2 Skid - Option Gas Platform 60 m. 50.180 11 50.00% 17-May-16 18-May-16 2 0.00% 0.00% 2535 182 14-May-16 21-May-16 8 483 56 17-May-16 21-May-16 5 483 56 17-May-16 21-May-16 5 505-FAEI-24830 Tubings Leak Test for 01-I1: Process Production 456 m. 50.180 45 80.36% 17-May-16 19-May-16 3 0.00% 0.00% 505-FAEI-24840 Tubings Leak Test for Booster Compressor 27 m. 50.180 11 19.64% 21-May-16 21-May-16 1 0.00% 0.00% 2052 126 14-May-16 18-May-16 5 1273 90 14-May-16 18-May-16 5 505-FAEI-24850 Tubings Leak Test for 13-C3 : Wellhead Control Panel 1273 m. 50.180 90 100.00% 14-May-16 18-May-16 5 0.00% 0.00% 779 36 17-May-16 18-May-16 2 505-FAEI-24860 Tubings Leak Test for 17-S1 : Fire Emergency Shutdown (FESD) 531 m. 50.180 18 50.00% 17-May-16 18-May-16 2 0.00% 0.00% 505-FAEI-24870 Tubings Leak Test for 17-S2 : Emergency Shutdown 248 m. 50.180 18 50.00% 17-May-16 18-May-16 2 0.00% 0.00% 2879 284 0.00% L5 L4 L5 L4 L5 L4 271 363 11-May-16 14-Jun-16 35 271 363 11-May-16 14-Jun-16 35 505-FAEI-24880 Hook-Up of E&I Tags for 01-I1: Process Production 145 Ea. 50.175 148 40.77% 11-May-16 7-Jun-16 28 30.21% 62.84% Delayed Should be finished 505-FAEI-24890 Hook-Up of E&I Tags for 01-I2 : Production Header 28 Ea. 50.175 43 11.85% 14-May-16 10-Jun-16 28 55.71% 76.74% Delayed Should be finished 505-FAEI-24900 Hook-Up of E&I Tags for 02-I1 : Test Separator 52 Ea. 50.175 75 20.66% 21-May-16 8-Jun-16 19 55.38% 71.33% Delayed Should be finished 505-FAEI-24910 Hook-Up of E&I Tags for 03-I1 : Pig Luncher 1 Ea. 50.175 1 0.28% 7-Jun-16 8-Jun-16 2 0.00% 0.00% Should be started 505-FAEI-24920 Hook-Up of E&I Tags for 03-I2 : Pig Receiver - Option 18 Ea. 50.175 55 15.15% 7-Jun-16 14-Jun-16 8 0.00% 0.00% Should be started 505-FAEI-24950 Hook-Up of E&I Tags for 10-I1 : Booster Compressor 27 Ea. 50.175 41 11.29% 28-May-16 14-Jun-16 18 55.56% 57.32% Delayed Should be finished 15 22 11-May-16 15-Jun-16 36 9 13 11-May-16 18-May-16 8 505-FAEI-24960 Hook-Up of E&I Tags for 08-I1 : Closed Drain System 9 Ea. 50.175 13 100.00% 11-May-16 18-May-16 8 33.33% 61.54% Delayed 5 8 21-May-16 25-May-16 5 505-FAEI-24970 Hook-Up of E&I Tags for 09-I1 : Open Drain System 5 Ea. 50.175 8 100.00% 21-May-16 25-May-16 5 48.00% 50.00% Delayed 1 1 14-Jun-16 15-Jun-16 2 505-FAEI-24980 Hook-Up of E&I Tags for 06-I1 : HP Vent / LP Vent 1 Ea. 50.175 1 100.00% 14-Jun-16 15-Jun-16 2 0.00% 0.00% Should be started 28 41 7-Apr-16 21-Jun-16 76 17 23 7-Apr-16 19-Apr-16 13 505-FAEI-24990 Hook-Up of E&I Tags for 04-I1 : Instrument Gas 17 Ea. 50.175 23 100.00% 7-Apr-16 19-Apr-16 13 42.35% 69.57% Delayed 11 18 9-Apr-16 21-Jun-16 74 505-FAEI-25000 Hook-Up of E&I Tags for 04-I2 : Utility Gas 11 Ea. 50.175 18 100.00% 9-Apr-16 21-Apr-16 13 43.64% 66.67% Delayed 24 35 26-May-16 14-Jun-16 20 24 35 26-May-16 14-Jun-16 20 505-FAEI-25030 Hook-Up of E&I Tags for 11-I1 : Chemical Injection 24 Ea. 50.175 35 100.00% 26-May-16 13-Jun-16 19 90.00% 35.71% Ahead Should be finished 231 332 29-Feb-16 9-Jun-16 102 67 226 31-Mar-16 7-Jun-16 69 505-FAEI-25050 Hook-Up of E&I Tags for 13-C1 : Back Start 4 Ea. 50.175 7 3.10% 31-Mar-16 5-Apr-16 6 90.00% 78.57% Ahead 505-FAEI-25060 Hook-Up of E&I Tags for 13-C2 : PLC and Control system 14 Ea. 50.175 22 9.73% 21-May-16 3-Jun-16 14 62.14% 79.55% Delayed Should be finished 505-FAEI-25070 Hook-Up of E&I Tags for 13-C3 : Wellhead Control Panel 49 Ea. 50.175 197 87.17% 21-May-16 7-Jun-16 18 60.00% 79.95% Delayed Should be finished 133 60 29-Feb-16 9-Jun-16 102 505-FAEI-25090 Hook-Up of E&I Tags for 14-E2 : AC Diesel Generators 1 Ea. 50.175 1 1.67% 22-Apr-16 30-Apr-16 9 60.00% 100.00% Delayed 505-FAEI-25100 Hook-Up of E&I Tags for 14-E3 : DC Supply 8 Ea. 50.175 10 16.67% 25-Mar-16 2-Apr-16 9 56.25% 70.00% Delayed 505-FAEI-25110 Hook-Up of E&I Tags for 14-E4 : Power & Lighting and Outlet 110 Ea. 50.175 28 46.67% 29-Feb-16 5-Apr-16 37 60.27% 82.14% Delayed 505-FAEI-25130 Hook-Up of E&I Tags for 14-E6 : TEG - Gas Platform 5 Ea. 50.175 8 13.33% 6-May-16 14-May-16 9 60.00% 75.00% Delayed 505-FAEI-25140 Hook-Up of E&I Tags for 16-E1 : Navigation Aids System 9 Ea. 50.175 13 21.67% 2-Apr-16 12-Apr-16 11 60.00% 76.92% Delayed 5 7 12-Apr-16 23-Apr-16 12 505-FAEI-25150 Hook-Up of E&I Tags for 15-T1 : Comunication System 5 Ea. 50.175 7 100.00% 12-Apr-16 23-Apr-16 12 60.00% 57.14% Ahead 26 39 25-Apr-16 17-May-16 23 505-FAEI-25160 Hook-Up of E&I Tags for 17-S2 : Emergency Shutdown 10 Ea. 50.175 13 33.33% 6-May-16 17-May-16 12 60.00% 100.00% Delayed 505-FAEI-25170 Hook-Up of E&I Tags for 17-S3 : Fire & Gas Detector 5 Ea. 50.175 8 20.51% 25-Apr-16 30-Apr-16 6 60.00% 62.50% Delayed 505-FAEI-25180 Hook-Up of E&I Tags for 17-S4 : Beacon Light & Siren 11 Ea. 50.175 18 46.15% 25-Apr-16 28-Apr-16 4 60.00% 61.11% Delayed 569 793 -14.03% 24076 -6.41% L5 L4 L5 L4 L5 L4 704 21-Jun-16 25-Jun-16 5 84 704 21-Jun-16 25-Jun-16 5 84 704 21-Jun-16 25-Jun-16 5 505-FAPC-22150 Fuction Test of 14-E2 : AC Diesel Generators 10 Pac. 60.220 71 10.09% 21-Jun-16 22-Jun-16 2 0.00% 0.00% 505-FAPC-22160 Fuction Test of 14-E3 : DC Supply 21 Pac. 60.220 174 24.72% 23-Jun-16 24-Jun-16 2 0.00% 0.00% 505-FAPC-22170 Fuction Test of 14-E4 : Power & Lighting and Outlet 39 Pac. 60.220 322 45.74% 21-Jun-16 22-Jun-16 2 0.00% 0.00% 505-FAPC-22190 Fuction Test of 14-E6 : TEG - Gas Platform 6 Pac. 60.220 21 2.98% 25-Jun-16 25-Jun-16 1 0.00% 0.00% 505-FAPC-22200 Fuction Test of 16-E1 : Navigation Aids System 8 Pac. 60.220 116 16.48% 23-Jun-16 24-Jun-16 2 0.00% 0.00% 1241 22-Jun-16 25-Jun-16 4 237 823 22-Jun-16 25-Jun-16 4 237 823 22-Jun-16 25-Jun-16 4 505-FAPC-22220 Loop Test of 01-I1: Process Production 98 Pac. 60.225 340 41.31% 22-Jun-16 23-Jun-16 2 0.00% 0.00% 505-FAPC-22230 Loop Test of 01-I2 : Production Header 27 Pac. 60.225 94 11.42% 23-Jun-16 23-Jun-16 1 0.00% 0.00% 505-FAPC-22240 Loop Test of 02-I1 : Test Separator 55 Pac. 60.225 191 23.21% 24-Jun-16 25-Jun-16 2 0.00% 0.00% 505-FAPC-22250 Loop Test of 03-I2 : Pig Receiver - Option 12 Pac. 60.225 42 5.10% 24-Jun-16 24-Jun-16 1 0.00% 0.00% 505-FAPC-22280 Loop Test of 10-I1 : Booster Compressor 45 Pac. 60.225 156 18.96% 24-Jun-16 24-Jun-16 1 0.00% 0.00% 9 32 25-Jun-16 25-Jun-16 1 6 21 25-Jun-16 25-Jun-16 1 505-FAPC-22290 Loop Test of 08-I1 : Closed Drain System 6 Pac. 60.225 21 100.00% 25-Jun-16 25-Jun-16 1 0.00% 0.00% 3 11 25-Jun-16 25-Jun-16 1 505-FAPC-22300 Loop Test of 09-I1 : Open Drain System 3 Pac. 60.225 11 100.00% 25-Jun-16 25-Jun-16 1 0.00% 0.00% 13 32 25-Jun-16 25-Jun-16 1 9 21 25-Jun-16 25-Jun-16 1 505-FAPC-22310 Loop Test of 04-I1 : Instrument Gas 9 Pac. 60.225 21 100.00% 25-Jun-16 25-Jun-16 1 0.00% 0.00% 4 11 25-Jun-16 25-Jun-16 1 505-FAPC-22320 Loop Test of 04-I2 : Utility Gas 4 Pac. 60.225 11 100.00% 25-Jun-16 25-Jun-16 1 0.00% 0.00% 12 32 25-Jun-16 25-Jun-16 1 12 32 25-Jun-16 25-Jun-16 1 505-FAPC-22350 Loop Test of 11-I1 : Chemical Injection 12 Pac. 60.225 32 100.00% 25-Jun-16 25-Jun-16 1 0.00% 0.00% 49 322 23-Jun-16 25-Jun-16 3 30 187 23-Jun-16 24-Jun-16 2 505-FAPC-22370 Loop Test of 13-C3 : Wellhead Control Panel 30 Pac. 60.225 187 100.00% 23-Jun-16 24-Jun-16 2 0.00% 0.00% 1 4 23-Jun-16 23-Jun-16 1 505-FAPC-22380 Loop Test of 15-T1 : Comunication System 1 Pac. 60.225 4 100.00% 23-Jun-16 23-Jun-16 1 0.00% 0.00% 18 131 24-Jun-16 25-Jun-16 2 505-FAPC-22390 Loop Test of 17-S2 : Emergency Shutdown 3 Pac. 60.225 12 9.16% 24-Jun-16 24-Jun-16 1 0.00% 0.00% 505-FAPC-22400 Loop Test of 17-S3 : Fire & Gas Detector 8 Pac. 60.225 28 21.37% 25-Jun-16 25-Jun-16 1 0.00% 0.00% 505-FAPC-22410 Loop Test of 17-S4 : Beacon Light & Siren 7 Pac. 60.225 91 69.47% 25-Jun-16 25-Jun-16 1 0.00% 0.00% 404 1945 0.00% L5 L4 L5 L4 L5 L4 505-FAPC-22420 Platform Site Acceptance Test - SAT 100 Pac. 60.235 555 27-Jun-16 2-Jul-16 6 100 555 0.00% 2500 0.00% -5.81% SUB-TOTAL OF TUBINGS LEAK TEST 1.18% 0.00% 0.00% Sub-System - 8000A : Process Control 71.43% 0.00% 0.00% Sub-System - 8000D : Safety Intrergrity System (SIS) 28.57% 0.00% 0.00% 0.00% Sub-System - 1001 : Process Liquid & Vapour (P) 100.00% 0.00% 0.00% System - 8000 : Others 69.23% 0.00% 0.00% System - 1000 : Process Production 30.77% 0.00% Sub-System - 8000B : Electrical Generation and Distribution 51.16% 0.00% 0.00% TPU Jacket Tube Leak Test 64.08% 0.00% 0.00% Sub-System - 8000A : Process Control 48.84% 0.00% 0.00% 79.13% 84.94%OVERALL PROGRESS OF WHP 50/5 : GAS PLATFORM 26576 100.00% 0.00% TOTAL OF WHP 50/5 : GAS PLATFORM : E&I PRE-COMMISSIONING 9.41% 0.00% 0.00% 100.00% 0.00% 0.00% SUB-TOTAL OF SITE ACCEPTANC TEST - SAT 22.20% 0.00% RemarkL3 Start Finish Dur. Activity Milestones % Actual %Plan Status Next 2 Wks As Per Planed SAT Completion L3 L3 100% 0.00% SITE ACCEPTANC TEST - SAT QTY Unit Cost Code Budgeted Mhrs WTG% Baseline SUB-TOTAL OF LOOP/ FUNCTION TEST 77.80% 0.00% 0.00% 0.00% Sub-System - 8000D : Safety Intrergrity System (SIS) 40.68% 0.00% 0.00% Sub-System - 8000C : Communication 1.24% 0.00% 0.00% Sub-System - 8000A : Process Control 58.07% 0.00% 0.00% System - 8000 : Others 25.95% 0.00% 0.00% Sub-System - 7001 : Chemical (C) 100.00% 0.00% 0.00% System - 7000 : Chemicals 2.58% 0.00% 0.00%Sub-System - 4500 : Gas Utility (GU) 34.38% Sub-System - 4400 : Gas Instrument (GI) 65.63% 0.00% 0.00% 0.00% 0.00% System - 4000 : Utility Generals 2.58% 0.00% 0.00% Sub-System - 2100 : Open Drain (DO) 34.38% 0.00% 0.00% Sub-System - 2001 : Closed Drain (DC) 65.63% 0.00% 0.00% System - 2000 : Drains & Reliefs 2.58% Sub-System - 1001 : Process Liquid & Vapour (P) 100.00% 0.00% 0.00% 0.00% 0.00% System - 1000 : Process Production 66.32% 0.00% 0.00% Instrumentation 63.80% Sub-System - 8000B : Electrical Generation and Distribution 100.00% 0.00% 0.00% System - 8000 : Others 100.00% 0.00% 0.00% Electrical 36.20% 0.00% 0.00% %Plan Status Next 2 Wks As Per Planed RemarkL3 Start Finish Dur. WTG% Baseline Activity Milestones % Actual Tested Check Sheet : PLT-L & PFT WHP 50/5 : GAS PLATFORM : E&I PRE-COMMISSIONING LOOP/ FUNCTION TEST QTY Unit Cost Code Budgeted Mhrs TOTAL OF WHP 50/5 : GAS PLATFORM : E&I INSTALLATION 90.59% 87.35% 93.76% L3 L3 90% 10% 63.43%SUB-TOTAL OF HOOK-UP OF E&I TAG ITEMS 3.29% 49.40% 11 Sub-System - 8000B : Electrical Generation and Distribution 18.07% 59.50% 78.33% 1 7 1 60.00% 57.14% Sub-System - 8000D : Safety Intrergrity System (SIS) 11.75% 60.00% 41.03% Sub-System - 8000C : Communication 2.11% 110 1 5 9 60.68% 74.85% Sub-System - 8000A : Process Control 68.07% 61.14% 80.09% System - 8000 : Others 41.87% 90.00% 35.71% Sub-System - 7001 : Chemical (C) 100.00% 90.00% 35.71% 24 24 43.64% 66.67%Sub-System - 4500 : Gas Utility (GU) 43.90% 42.92% 68.29% Sub-System - 4400 : Gas Instrument (GI) 56.10% 42.35% 69.57% 8 System - 7000 : Chemicals 4.41% System - 4000 : Utility Generals 5.17% 48.00% 50.00% Sub-System - 2500 : Blow Down (BD) 4.55% 0.00% 0.00% Sub-System - 2100 : Open Drain (DO) 36.36% 5 4 37.15% 54.55% Sub-System - 2001 : Closed Drain (DC) 59.09% 33.33% 61.54% System - 2000 : Drains & Reliefs 2.77% 25 55.92% Sub-System - 1001 : Process Liquid & Vapour (P) 100.00% 36.63% 55.92% System - 1000 : Process Production 45.78% 36.63% HOOK-UP OF E&I TAG ITEMS QTY Unit Cost Code Budgeted Mhrs 455 31 Next 2 Wks As Per Planed RemarkL3 Start Finish Dur. Activity Milestones % Actual %Plan StatusL3 L3 WTG% Baseline Installed Hook-Up Check Sheet : PIC-H 60% 30% 10% 26 48 73 4 4 10 5 14 1 49 5 12 Page 10 of 10 Prepared By : Nattakarn S.