IT PROJECT MANAGEMENT:
INFAMOUS FAILURES, CLASSIC MISTAKES, AND BEST PRACTICES
Mahyar Teymournezhad
R. Ryan Nelson - University of Virginia
MANY ORGANIZATIONS
CONDUCT RETROSPECTIVES
AFTER A FAILURE TO AVOID
FUTURE DISASTERS.
An individual retrospective tells a unique story, but more
insight can be gained by examining multiple retrospectives.
99 retrospectives across 74 organizations were used to conduct
this research. From this research many common mistakes and
best practices can be extracted for better project management.
INFAMOUS FAILURES
MCDONALDS
This project aimed to create a real-time global
network to link over 30,000 stores in 121
countries to headquarters by Intranet. It would
have given executives a bird’s eye view of the
entire system at any minute of the day.
“INNOVATE” PROJECT (2001)
INFAMOUS FAILURES
MCDONALDS
At cost estimates of over $1 billion, Innovate
was the most expensive information technology
project in McDonalds’s history. Innovate project
failed before it even got off the ground.
McDonalds wrote off $170 million in the 2002
and Innovate was cancelled.
AN EPIC ‘MC-FAILURE’
INFAMOUS FAILURES
MCDONALDS
Scope Management: $1 billion would have
only covered the first 5 years of design and
implementation. Millions more would need to
be spent to maintaining the system.
Linking all 30,000+ locations via broadband
was impossible
WHY INNOVATE FAILED?
INFAMOUS FAILURES
MCDONALDS
Implementation: Attempted to go company wide in
a one fell swoop or big bang approach.
Acceptance: Franchisees reluctant to accept after
“Made For You” system in 1998 slowed service.
Senior executives also had a lack of IT knowledge.
Experience: No prior experience in large scale
software implementation.
WHY INNOVATE FAILED?
INFAMOUS FAILURES
MCDONALDS
• Project should have been broken down into
manageable chunks.
• Hired a project manager with large-scale
software implementation expertise.
• Eased concerns and discomfort of Senior
Management and Franchisees.
TAKEAWAYS
Classic
Mistakes
• “Ineffective project management practices that
were identified so often, by so many people,
with such predictable, negative results that they
deserve to be called “classic mistakes.”
-Steve McConell
Failure is generally rooted in errors by project
mangers and is rarely attributed to chance.
Definition
CLASSIC MISTAKES
DEFINED
People
IT Human Capital
Process
Management Processes and Technical
Methodologies
Product
Product Size and Product Characteristics
Technology
Use and Misuse of Modern Technology
CLASSIC MISTAKES
4 Categories of Mistakes
People
• Undermined Motivation
• Capabilities of the individual team members/ the
working relationship among the team members
• Leaders failure to take action to deal with a
problem employee
• Adding people to a late project
Process
• Wasted time in the “Fuzzy Front End”
• Underestimating and producing overly optimistic
schedules
• Insufficient Risk Management
• Contract Failure
Product
• Requirements Gold-Plating
• Feature Creep
• Developer Gold-Plating
• Research Oriented Development
Technology
• Silver-bullet syndrome
• Overestimated savings from new tools or methods
• Switching tools in the middle of a project
A Meta-Retrospective of 99 IT Projects
• 502 Masters level Mgmt Info Systems students were assigned to complete
retrospectives on completed IT projects of various magnitude.
• The IT projects were assessed under the following criteria:
1. Project Context and Description
2. Project Timeline
3. Lessons Learned (What Went Right vs. What Went Wrong)
4. Recommendations for the Future
5. Evaluation of Success/Failure
Overview
A Meta-Retrospective of 99 IT Projects
1. The majority of the classic mistakes were categorized as either
process or people mistakes.
2. Scope Creep did not make the top ten list.
3. The Top 3 Mistakes occurred in about 50% of all the projects
examined.
Case Findings
Summary
Project mangers should closely examine past mistakes
to determine which are the most common and search
for patterns that will help them avoid repeating these
mistakes.
BEST
PRACTICES
• One of the best advantages of uncovering what
went wrong in projects studied is to discover
what went right.
• Properly used methods, tools, and techniques
can help organizations avoid the classic
mistakes from occurring in the first place.
WIN WITHIN DEFEAT
• The Estimation and Scheduling Process
consists of:
• Sizing or scoping the project
• Estimating the Effort and Time Required
• Developing a Calendar
How to Avoid Poor Estimating
and/or Scheduling
1.Fewer Mistakes
2.Better Budgeting
3.Less Overtime
4.More Credibility for the Project Team
5.Less Schedule Pressure
6.Less Staff Turnover
Accurate Estimates Will Include
The IT field is betting somewhat better at
estimating cost but worse at estimating time.
In 1994, the average cost overrun was 180%. The
average dropped to 43% by 2003.
In 2000, average time overruns reached a low of
63% but have increased significantly to 82%.
The Current Pattern
Standish Group’s longitudinal findings show that:
• Using Developer-Based Estimates
• A modified Delphi Approach
• Historical Data
• Algorithms
• Estimation Software
• Estimate-Convergence Graphs
How To Improve Estimating and
Scheduling?
1. Time Box Development
2. Creating a Work Break Down Structure
3. Retrospectives to Capture Actual Size, Effort,
and Time
4. A Project Management Office
4 Valuable Approaches to
Improving Project Estimation and
Scheduling
Cone of uncertainty
1. Using a Stakeholder worksheets and
assessment graphs
2. Communication Plans
3. Creation of a Project Management Office
4. Portfolio Management
INEFFECTIVE STAKEHOLDER
MANAGEMENT IS THE 2ND LARGEST
CAUSE OF PROJECT FAILURE
“WITH GREATER POWER
COMES
GREATER RESPONSIBILITY”
How to Avoid
Insufficient Risk Management
• Risk Identification
• Analysis
• Prioritization
• Risk-Management
• Planning
• Resolution
• Monitoring
The Process of
Risk Management
Use a Risk Table
Best Practice For Avoiding Risk
• Comprehensive Project Charter
• Clearly Defined Project Governance
• Portfolio Management
How to Avoid Insufficient Planning
• Agile Development
• Joint Application Design Sessions
• Automated Testing Tools
• Daily Build-and Smoke Tests
How to Avoid Short changing
Quality Assurance
“One of the key problems during the development phase
of the project was the relatively low skill level of the
programmers assigned to the project. The weak
programming skills caused schedule lapses, poor quality,
and eventually caused changes in personnel.”
Get The Right Person For the Job
Reoccurring and Common Issues
Reduction in face-to-face meetings
Time-Zone Barriers
Language and Cultural Issues
WHO’S PAYING FOR THIS?
• A project must have the “Right” Sponsor. That means that a
project must have a sponsor who will be with the project from
the beginning, and managing the relationship throughout the life
of the project.
BUT SOME CHANGE CAN BE BETTER
• “There were CEOs on calls all the time. Nobody wanted to be
written up in the ‘Wall Street Journal.’That was what motivated
people to change. Fear that the stock price would get hammered
and fear that they would lose too much business.”
The End
Mahyar Teymournezhad

More Related Content

What's hot

IT PMO Charter (Linkedin)
IT PMO Charter (Linkedin)IT PMO Charter (Linkedin)
IT PMO Charter (Linkedin)
jimmcdonaldpmp
 

What's hot (20)

PMP_Project Communication Management
PMP_Project Communication ManagementPMP_Project Communication Management
PMP_Project Communication Management
 
Project team management
Project team managementProject team management
Project team management
 
project management
project managementproject management
project management
 
Project Scheduling, Planning and Risk Management
Project Scheduling, Planning and Risk ManagementProject Scheduling, Planning and Risk Management
Project Scheduling, Planning and Risk Management
 
IT PMO Charter (Linkedin)
IT PMO Charter (Linkedin)IT PMO Charter (Linkedin)
IT PMO Charter (Linkedin)
 
Introduction to Project Management by Javid Hamdard
Introduction to Project Management by Javid HamdardIntroduction to Project Management by Javid Hamdard
Introduction to Project Management by Javid Hamdard
 
Pmp hr chapter 9
Pmp hr chapter 9Pmp hr chapter 9
Pmp hr chapter 9
 
06 project time management
06  project time management06  project time management
06 project time management
 
Project management IT Project Management
Project management IT Project Management Project management IT Project Management
Project management IT Project Management
 
10 causes of project failure.
10 causes of project failure.10 causes of project failure.
10 causes of project failure.
 
Top Ten Reasons For Project Failure - PMP Webinar
Top Ten Reasons For Project Failure - PMP WebinarTop Ten Reasons For Project Failure - PMP Webinar
Top Ten Reasons For Project Failure - PMP Webinar
 
Chap03 the project management process groups
Chap03 the project management process groupsChap03 the project management process groups
Chap03 the project management process groups
 
Project Management Framework
Project Management FrameworkProject Management Framework
Project Management Framework
 
2. project initiation
2. project initiation2. project initiation
2. project initiation
 
PMO Charter Template
PMO Charter TemplatePMO Charter Template
PMO Charter Template
 
Chapter 01 - Introduction to Software Project Management
Chapter 01 - Introduction to Software Project ManagementChapter 01 - Introduction to Software Project Management
Chapter 01 - Introduction to Software Project Management
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project Management
 
Project Management Office (PMO): Characteristics, Roles, Functions, Transform...
Project Management Office (PMO): Characteristics, Roles, Functions, Transform...Project Management Office (PMO): Characteristics, Roles, Functions, Transform...
Project Management Office (PMO): Characteristics, Roles, Functions, Transform...
 
06. Project Management Process Groups
06. Project Management Process Groups06. Project Management Process Groups
06. Project Management Process Groups
 
An Introduction to Project Management
An Introduction to Project Management An Introduction to Project Management
An Introduction to Project Management
 

Similar to It project management infamous failures, classic mistakes, and best practices

It failures final
It failures finalIt failures final
It failures final
imslfmade
 
importance of resources allocation in formal method of software engineering ...
 importance of resources allocation in formal method of software engineering ... importance of resources allocation in formal method of software engineering ...
importance of resources allocation in formal method of software engineering ...
Abdul Naqashbandi
 
Project failure reason 1
Project failure reason 1Project failure reason 1
Project failure reason 1
Arash Moto
 

Similar to It project management infamous failures, classic mistakes, and best practices (20)

It failures final
It failures finalIt failures final
It failures final
 
Another Agile Intro
Another Agile IntroAnother Agile Intro
Another Agile Intro
 
Good Projects Gone Bad: an Introduction to Process Maturity
Good Projects Gone Bad: an Introduction to Process MaturityGood Projects Gone Bad: an Introduction to Process Maturity
Good Projects Gone Bad: an Introduction to Process Maturity
 
Mega project not mega problems session 1
Mega project not mega problems session 1Mega project not mega problems session 1
Mega project not mega problems session 1
 
Managing international software projects interactively using scrum
Managing international software projects interactively using scrumManaging international software projects interactively using scrum
Managing international software projects interactively using scrum
 
Project management and Success Criteria
Project management and Success Criteria Project management and Success Criteria
Project management and Success Criteria
 
Project managemen concept
Project managemen conceptProject managemen concept
Project managemen concept
 
Agile in a nutshell
Agile in a nutshellAgile in a nutshell
Agile in a nutshell
 
importance of resources allocation in formal method of software engineering ...
 importance of resources allocation in formal method of software engineering ... importance of resources allocation in formal method of software engineering ...
importance of resources allocation in formal method of software engineering ...
 
Project management 02112009
Project management 02112009Project management 02112009
Project management 02112009
 
Agile project management and normative
Agile project management and normativeAgile project management and normative
Agile project management and normative
 
PROJECT MANAGEMENT all given chapters-1.pdf
PROJECT MANAGEMENT all given chapters-1.pdfPROJECT MANAGEMENT all given chapters-1.pdf
PROJECT MANAGEMENT all given chapters-1.pdf
 
10 Ways to Increase Your Project's Success
10 Ways to Increase Your Project's Success10 Ways to Increase Your Project's Success
10 Ways to Increase Your Project's Success
 
MCP1
MCP1MCP1
MCP1
 
Agile Localization and Leadership Styles
Agile Localization and Leadership StylesAgile Localization and Leadership Styles
Agile Localization and Leadership Styles
 
Project failure reason 1
Project failure reason 1Project failure reason 1
Project failure reason 1
 
project influnceing
project influnceingproject influnceing
project influnceing
 
28.Causes of project failure A Lecture By Mr Allah Dad Khan Visiting Profes...
28.Causes of project failure   A Lecture By Mr Allah Dad Khan Visiting Profes...28.Causes of project failure   A Lecture By Mr Allah Dad Khan Visiting Profes...
28.Causes of project failure A Lecture By Mr Allah Dad Khan Visiting Profes...
 
4 Keys to successful project management software implementation in big organ...
4 Keys to successful project management software implementation  in big organ...4 Keys to successful project management software implementation  in big organ...
4 Keys to successful project management software implementation in big organ...
 
PMC4
PMC4PMC4
PMC4
 

Recently uploaded

Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
Epec Engineered Technologies
 
Introduction to Robotics in Mechanical Engineering.pptx
Introduction to Robotics in Mechanical Engineering.pptxIntroduction to Robotics in Mechanical Engineering.pptx
Introduction to Robotics in Mechanical Engineering.pptx
hublikarsn
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Kandungan 087776558899
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
ssuser89054b
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdf
Kamal Acharya
 

Recently uploaded (20)

Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
Introduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdfIntroduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdf
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdf
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 
Introduction to Robotics in Mechanical Engineering.pptx
Introduction to Robotics in Mechanical Engineering.pptxIntroduction to Robotics in Mechanical Engineering.pptx
Introduction to Robotics in Mechanical Engineering.pptx
 
Path loss model, OKUMURA Model, Hata Model
Path loss model, OKUMURA Model, Hata ModelPath loss model, OKUMURA Model, Hata Model
Path loss model, OKUMURA Model, Hata Model
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdf
 
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
 
PE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiesPE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and properties
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
Linux Systems Programming: Inter Process Communication (IPC) using Pipes
Linux Systems Programming: Inter Process Communication (IPC) using PipesLinux Systems Programming: Inter Process Communication (IPC) using Pipes
Linux Systems Programming: Inter Process Communication (IPC) using Pipes
 
8th International Conference on Soft Computing, Mathematics and Control (SMC ...
8th International Conference on Soft Computing, Mathematics and Control (SMC ...8th International Conference on Soft Computing, Mathematics and Control (SMC ...
8th International Conference on Soft Computing, Mathematics and Control (SMC ...
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdf
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
Post office management system project ..pdf
Post office management system project ..pdfPost office management system project ..pdf
Post office management system project ..pdf
 
UNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptxUNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptx
 
Computer Graphics Introduction To Curves
Computer Graphics Introduction To CurvesComputer Graphics Introduction To Curves
Computer Graphics Introduction To Curves
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdf
 
Memory Interfacing of 8086 with DMA 8257
Memory Interfacing of 8086 with DMA 8257Memory Interfacing of 8086 with DMA 8257
Memory Interfacing of 8086 with DMA 8257
 

It project management infamous failures, classic mistakes, and best practices

  • 1. IT PROJECT MANAGEMENT: INFAMOUS FAILURES, CLASSIC MISTAKES, AND BEST PRACTICES Mahyar Teymournezhad R. Ryan Nelson - University of Virginia
  • 2. MANY ORGANIZATIONS CONDUCT RETROSPECTIVES AFTER A FAILURE TO AVOID FUTURE DISASTERS. An individual retrospective tells a unique story, but more insight can be gained by examining multiple retrospectives. 99 retrospectives across 74 organizations were used to conduct this research. From this research many common mistakes and best practices can be extracted for better project management.
  • 3. INFAMOUS FAILURES MCDONALDS This project aimed to create a real-time global network to link over 30,000 stores in 121 countries to headquarters by Intranet. It would have given executives a bird’s eye view of the entire system at any minute of the day. “INNOVATE” PROJECT (2001)
  • 4. INFAMOUS FAILURES MCDONALDS At cost estimates of over $1 billion, Innovate was the most expensive information technology project in McDonalds’s history. Innovate project failed before it even got off the ground. McDonalds wrote off $170 million in the 2002 and Innovate was cancelled. AN EPIC ‘MC-FAILURE’
  • 5. INFAMOUS FAILURES MCDONALDS Scope Management: $1 billion would have only covered the first 5 years of design and implementation. Millions more would need to be spent to maintaining the system. Linking all 30,000+ locations via broadband was impossible WHY INNOVATE FAILED?
  • 6. INFAMOUS FAILURES MCDONALDS Implementation: Attempted to go company wide in a one fell swoop or big bang approach. Acceptance: Franchisees reluctant to accept after “Made For You” system in 1998 slowed service. Senior executives also had a lack of IT knowledge. Experience: No prior experience in large scale software implementation. WHY INNOVATE FAILED?
  • 7. INFAMOUS FAILURES MCDONALDS • Project should have been broken down into manageable chunks. • Hired a project manager with large-scale software implementation expertise. • Eased concerns and discomfort of Senior Management and Franchisees. TAKEAWAYS
  • 9. • “Ineffective project management practices that were identified so often, by so many people, with such predictable, negative results that they deserve to be called “classic mistakes.” -Steve McConell Failure is generally rooted in errors by project mangers and is rarely attributed to chance. Definition CLASSIC MISTAKES DEFINED
  • 10. People IT Human Capital Process Management Processes and Technical Methodologies Product Product Size and Product Characteristics Technology Use and Misuse of Modern Technology CLASSIC MISTAKES 4 Categories of Mistakes
  • 11. People • Undermined Motivation • Capabilities of the individual team members/ the working relationship among the team members • Leaders failure to take action to deal with a problem employee • Adding people to a late project
  • 12. Process • Wasted time in the “Fuzzy Front End” • Underestimating and producing overly optimistic schedules • Insufficient Risk Management • Contract Failure
  • 13. Product • Requirements Gold-Plating • Feature Creep • Developer Gold-Plating • Research Oriented Development
  • 14. Technology • Silver-bullet syndrome • Overestimated savings from new tools or methods • Switching tools in the middle of a project
  • 15. A Meta-Retrospective of 99 IT Projects • 502 Masters level Mgmt Info Systems students were assigned to complete retrospectives on completed IT projects of various magnitude. • The IT projects were assessed under the following criteria: 1. Project Context and Description 2. Project Timeline 3. Lessons Learned (What Went Right vs. What Went Wrong) 4. Recommendations for the Future 5. Evaluation of Success/Failure Overview
  • 16. A Meta-Retrospective of 99 IT Projects 1. The majority of the classic mistakes were categorized as either process or people mistakes. 2. Scope Creep did not make the top ten list. 3. The Top 3 Mistakes occurred in about 50% of all the projects examined. Case Findings
  • 17. Summary Project mangers should closely examine past mistakes to determine which are the most common and search for patterns that will help them avoid repeating these mistakes.
  • 19. • One of the best advantages of uncovering what went wrong in projects studied is to discover what went right. • Properly used methods, tools, and techniques can help organizations avoid the classic mistakes from occurring in the first place. WIN WITHIN DEFEAT
  • 20. • The Estimation and Scheduling Process consists of: • Sizing or scoping the project • Estimating the Effort and Time Required • Developing a Calendar How to Avoid Poor Estimating and/or Scheduling
  • 21. 1.Fewer Mistakes 2.Better Budgeting 3.Less Overtime 4.More Credibility for the Project Team 5.Less Schedule Pressure 6.Less Staff Turnover Accurate Estimates Will Include
  • 22. The IT field is betting somewhat better at estimating cost but worse at estimating time. In 1994, the average cost overrun was 180%. The average dropped to 43% by 2003. In 2000, average time overruns reached a low of 63% but have increased significantly to 82%. The Current Pattern Standish Group’s longitudinal findings show that:
  • 23. • Using Developer-Based Estimates • A modified Delphi Approach • Historical Data • Algorithms • Estimation Software • Estimate-Convergence Graphs How To Improve Estimating and Scheduling?
  • 24. 1. Time Box Development 2. Creating a Work Break Down Structure 3. Retrospectives to Capture Actual Size, Effort, and Time 4. A Project Management Office 4 Valuable Approaches to Improving Project Estimation and Scheduling
  • 26. 1. Using a Stakeholder worksheets and assessment graphs 2. Communication Plans 3. Creation of a Project Management Office 4. Portfolio Management INEFFECTIVE STAKEHOLDER MANAGEMENT IS THE 2ND LARGEST CAUSE OF PROJECT FAILURE
  • 27. “WITH GREATER POWER COMES GREATER RESPONSIBILITY” How to Avoid Insufficient Risk Management
  • 28. • Risk Identification • Analysis • Prioritization • Risk-Management • Planning • Resolution • Monitoring The Process of Risk Management
  • 29. Use a Risk Table Best Practice For Avoiding Risk
  • 30. • Comprehensive Project Charter • Clearly Defined Project Governance • Portfolio Management How to Avoid Insufficient Planning
  • 31. • Agile Development • Joint Application Design Sessions • Automated Testing Tools • Daily Build-and Smoke Tests How to Avoid Short changing Quality Assurance
  • 32. “One of the key problems during the development phase of the project was the relatively low skill level of the programmers assigned to the project. The weak programming skills caused schedule lapses, poor quality, and eventually caused changes in personnel.” Get The Right Person For the Job Reoccurring and Common Issues Reduction in face-to-face meetings Time-Zone Barriers Language and Cultural Issues
  • 33. WHO’S PAYING FOR THIS? • A project must have the “Right” Sponsor. That means that a project must have a sponsor who will be with the project from the beginning, and managing the relationship throughout the life of the project. BUT SOME CHANGE CAN BE BETTER • “There were CEOs on calls all the time. Nobody wanted to be written up in the ‘Wall Street Journal.’That was what motivated people to change. Fear that the stock price would get hammered and fear that they would lose too much business.”