SlideShare a Scribd company logo
1 of 146
Rigging Safety
johnanewquist@gmail.com
Draft 3 12 2020
1
Hard Hats
• April 4, 2010
• “chain broke and whipped back”
• “scared the heck out of me”
• “that was a BUNCH of weight
hittin me”
• “hard hat saved me”
2
January 2015
• One company
• Two box knife cuts
• One stripping cable
• Another cutting open a
box toward him
3
June 2014
• Broken toes.
• Leather work boots.
• No safety toe
• Crane dropped load as
lifted
4
Oct 2015
• Steel Beam dropped on
foot.
• 6000 lbs
5
MATERIALS STORED TO PREVENT SLIDING FALLING, OR COLLAPSE
9
9
10
17
18
251(a)(2)(i)
250(a)(1)
251(b)(1)
251(a)(1)
252(a)
Materials Handling, Storage, Use & Disposal
[1926.250 – 252]
6
GENERAL RIGGING EQUIPMENT IDENTIFICATION
EXTERIOR DROP CHUTES
RIGGING EQUIPMENT INSPECTION & REMOVAL FROM SERVICE
WELDED ALLOY STEEL CHAIN SLING IDENTIFICATION
SUBPARTH
July 2019
Nov 2017
• Indicator that sling is
stretched.
• Slingmax.
8
Mar 2018
Officials said reinforcing steel that was being
moved by a crane fell and landed on Michael
Tolman, 56, who was taken to Orlando
Regional Medical Center in critical condition.
He later died
9
Spreader bars
10
Jan 2018
How would you lift?
4 x 11 foot
300 pounds
5/8 inch
11
Jan 2018
Duggan Steel
12
Dec 2017
Beaumont TX
24 inch "incident pipe" that killed
Espinoza was more than 25 feet long
and "may have" weighed more than
4,400 pounds.
He said that the strap and hoist
connected to the pipe during the
inspection indicated it could cause the
pipe to swing or rotate.
Yesenia Espinoza, 31, was working on new
construction when the "piping that was
improperly rigged and handled" fatally hit her
in the head, the lawsuit
13
Dec 2017 How would you rig?
14
May 2018
15
June
2019
16
Aug 2017
17
Jan 2017
Gunnebo Johnson Swivel eye hookCrosby Shur Loc
18
Chart
19
December 2016
• Chicago IL
• Two finger amputation
20
Dec 2016
Kenco Barrier Lift
21
Nov 2016
• New York City
• Crane operator George Smith,
47, and worker Elizandro
Ramos, 43, were killed when
the I-beam plummeted onto
the top of the cab in
Briarwood Tuesday.
• Winds were gusting at close to
40 mph at the time – above
the legal city limit of 30 mph
to operate –
• The city officials said that the
rigging rope may have failed.
22
Apr 2016
23
Feb 2016
• Two workers were killed
when a generator fell on
them at a construction site
in New Jersey Thursday
morning, officials said.
• The five-ton generator fell
on the workers at the site --
a future fire station -- after
a strap on the crane
lowering it snapped,
according to officials with
the Morris County
Prosecutor's Office.
24
Feb 2016
25
July 2015
• New Jersey Scaffold
• Photo Jimmy Cuellar
26
April 2015
• Cheshire NY
• Crane Operator died
• Two of the men working
at the construction site
were shocked by the
electric charge.
• Investigators said the two
men were measuring the
steel beam when the
crane hit the power lines.
27
Basic Rigger
• Safely uses and recognizes the limitations of chain, synthetic,
metal mesh, and wire rope slings
• Safely uses and recognizes the limitations of specific rigging
hardware to include: hooks and similar attaching devices,
shackles, wire rope clips, clamps, eyebolts, softeners, and
taglines.
• Identifies common load configurations and positioning and
demonstrates specific knowledge of crane operations
including voice and radio
• Understands personal fall protection methods, emergency
procedures, and hazards and restrictions with working in
proximity to overhead electric lines and equipment
• NCCER.org
28
April 2015
• Lifting a piece of pine
about 5 foot long 18
inches across
• “the load made it to the
ground ok the hook of
the biner caught the
strap and held till we
lowered it down.”
29
May 2014
• Providence RI
• 8 hurt in fall
• The US Occupational Safety and
Health Administration said the
rigging used put excessive weight
on a carabiner, causing the metal
loop to fail, and the acrobats, who
were hanging by their hair, to fall
15 to 20 feet to t
• According to OSHA, circus staff
violated both industry practice and
the manufacturer’s instructions for
using the carabiner by attaching it
so it was pulled in three directions,
rather than two.
30
Key Changes in Z359.1
• Section 3.2.1.4
• Gate face strength
requirements have
changed from 220 lbs.
(1kN) (old Standard) to
3,600 lbs. (16kN) (new
Standard).
31
April 2015
• Lifting a stump
grinder.
32
April 2015
• Schulyer OH
• The victim, whose name is
being withheld pending
family notification, was
driving a front end loader
while attempting to free a
cement truck that got stuck
by pulling the vehicle with a
chain.
• The chain snapped and
struck the victim.
• He was pronounced dead at
the scene.
How could you free this truck?
33
January 2015
• “This is how I read a
manual looking straight
up” – Ryan Ferguson
• “ i don't need to read a
book to know how it
works” – Caleb Pate
34
December 2014
• Rigging to move an
aerial lift
• Every lift aerial has
four designated pick
points.
35
November 2014
• What issues would a
rigger need to know?
36
September
2014
Germany
Lifting a trailer of scaffold
tubes
37
August 2014
• $15
• Sold as ½ inch alloy steel
• Supposed to lift 70,000
pounds
• Specifications
• 1) we are factory
2) from 3/8" to 1 3/8"
3) galvanized / red
painted
4) 40Cr steel / stainless
steel
5)mini order accepted
38
Nov 2015
39
July 2014
• 100,000
pound
transformer
• Each sling is
Kevlar
$90,000
40
Storage
• 1926.250(b)(1)
• Material stored inside
buildings under
construction shall not
be placed within 6 feet
of any hoistway or
inside floor openings,
nor within 10 feet of
an exterior wall which
does not extend above
the top of the material
stored
41
June 2013
• Officials canceled
work on the St.
Charles County
bridge after a 55-
gallon drum being
lifted by a crane fell
on 51-year-old
Jerseyville IL man.
• He was pronounced
dead at the scene.
42
Drums 2015
43
Drums 2015
44
Drums 2015
45
Mar 2018
Engineering debris boxes.
2500 pounds capacity.
Proof Tested.
Photo by Lee Jensen sales
46
Issues?
47
Hit by Pulley
• Event Date: 07/27/2010
• Inspection: 314807090
• Employee #1 was struck in the head by a metal
pulley when the nylon sling to which it was
connected broke.
• The pulley was being used to drag felled trees.
• When the rigging was put under tension, the
nylon sling broke, releasing the pulley, hitting the
employee in the head.
• 50 M
48
Jan 2018
• An employee was checking the
rigging on a rig.
• His hand was on a sling that was
lifting a piece of pipe when his right
hand was caught between the sling
and the pipe.
• His right little finger had to be
surgically amputated.
49
Pipe Fell
• Event Date: 04/29/2010
• Inspection: 314409277
• An employee was struck on the
head by a drilling pipe which
resulted in fatal injuries.
• The employee rigged a 20 foot
section of pipe and as it was
being lifted by the operator, the
pipe came loose from the rigging
and fell approximately 10 to 15
feet onto the head of the
employee.
• The employee died as a result of
his injuries.
• 50 M Fatality
•
50
Definitions
Birdcage damage
Definitions
Name Description Visual
Hitch “Basket” Loading with the sling
passed under the load
and both ends on the
hook or a single master
link.
Hitch “Choker” Loading with the sling
passed through one eye
and suspended by the
other.
Hitch “Vertical” Loading with the load
suspended vertically on
a single part or leg of
the sling.
Definitions
Master link – a steel link or ring used to support all
legs of a chain or wire rope sling.
Must have identifiers such as:
Grade: 800
Working Load Limit: 3,600 lbs
Size: 13/32"
Definitions
• Kinked Sling
54
Definitions
Rated capacity – the maximum allowable working load.
Definitions
Mechanical Splice 56
Definitions
Hand Tucked Eye Splice
57
Definitions
Swaged Forged Eye 58
Definitions
Wire rope – consists of many individual wires laid
into a number of strands which are in turn, laid
around a center core.
Definitions
• One wire rope lay
60
10 Rules for Rigging Safety #1
• Know the weight of the load
• Concrete slab
• Steel Beam
• Concrete form
• Tree
61
Bulk Density
• Building material Unit weight
– Aluminum: 171 pounds per cubic foot
– Cast Iron: 450 pounds per cubic foot
– Cement: 94 pounds per cubic foot
– Concrete: 150 pounds per cubic foot
– Crushed Stone: 2,500 pounds per cubic yard
– Gravel: 2,700 pounds per cubic yard
62
Bulk Density
• Steel plate thickness is
One inch to 40#/square
foot
• What would this plate
weigh?
63
64
Volume & Area Formulas
2013
• The NRC has now concluded that
Entergy "approved a design for
the temporary hoisting assembly
that was not supported by
detailed drawings, specifications,
evaluations and/or certifications.“
• In addition, Entergy failed to
review associated calculations to
ensure that the assembly was
designed to support the
projected load.
• It also failed to carry out a load
test on the lifting assembly in all
configurations for which it would
be used.
The stator weighed 525
tons.
66
10 Rules for Rigging Safety #2
• Know the center of
gravity of the load.
67
Center of Gravity
A load is stable when:
– The hook is directly above the center of gravity of the
load
Estimate the center of gravity
Lift the load just enough to clear the ground
If the hook is not over the center of gravity the hook
will travel to the center of gravity
CG?
68
Center of Gravity
If necessary, set the load down and adjust the
rigging
If the load tips more than 3°, the rigging should be
adjusted
The longer the sling legs, the more stable the load
will be
The longer set of sling
legs (B) will improve load
stability
B
A
69
In this situation, before raising the section, all
personnel are kept clear of the section and the
section is first raised a few inches to determine
whether it tips when raised (if it did tip,
it would indicate it is not rigged over the
center of gravity). If this occurs, the hoist line is
repositioned and the procedure repeated (with
employees kept clear of the section while it is
raised) until the A/D director determines that
it is rigged over the center of gravity and can
be moved into place without dangerous
movement. App C of Crane Std
70
May 2015
Issues?
71
May 2015
• Amesbury MA bridge
72
How Would You Rig This?
Would it matter if
the tank were full
or empty?
How would you rig
this?
Rules for Rigging Safety
• Know the rated capacity
of slings and hardware.
74
Rules for Rigging Safety
• Inspect all rigging
before use.
1926.251(a)(6) shall be
inspected for damage or
defects by a competent
person every shift (CHST)
75
Crosby
76
June 2016
Photo Mike Parnell 77
November 2014
• Crane next to sheeting
• 8 foot x 8 foot pads
with max load of
125,000 pounds per
pad
• 164,000 pounds max
load per chart
• What information is
needed?
78
Rigging equipment for material handling
• Synthetic webbing (nylon, polyester, and
polypropylene)
• Remove from service immediately if:
– Acid or caustic burns
– Melting or charring of any
part of the sling surface
– Snags, punctures, tears
or cuts
– Broken or worn stitches
– Distortion of fittings
79
Synthetic Slings
Sling capacity varies from manufacturer to
manufacturer.
Competent person must look at Individual Sling
Capacity Tag to determine Safe Lifting Capacity of
that sling.
If the Tag is not readable or is missing, Do not
use it!
Inspect sling before each days use, and as often
as necessary during the day to assure safety of
sling!
Sharp edges can slice a sling in two without
warning as the load is tensioned. Use softeners or
padding on corners.
“If you see red, the sling is dead.”
Synthetic Slings
Holes, tears, cuts or snags
81
Synthetic Slings
Knots
82
Synthetic Slings
Cuts
83
Inspection
• Wire rope and synthetic slings
addressed in the B30.9 ASME
standard require:
• 1. Documented periodic
inspection at least annually, but
condition of individual slings not
required..
• 2. Periodic inspection at least
annually but written records not
required
• 3. Visual Inspection minimum of
weekly
• 4. None of the above
• 9-6.9.3 Periodic Inspection
• (d) Documentation that the most
recent periodic inspection was
performed and shall be maintained.
• (e) Inspection records of individual
slings are not required.
84
Rigging Safety
• Allow for D/d ratio on all wire rope slings.
85
Rigging equipment for material handling
D
d
D/d Ratio
D - is diameter around
which sling is bent.
d - is diameter of the
sling.
86
D/d Ratio
Some wire rope sling manufacturers require a D/d ratio of
25 for a basket hitch.
87
D/d ratio hooks
• What D/d ratio would
you use?
88
D/d Ratio Snatch Blocks
The minimum D/d ratio
for snatch blocks per
ASME B30.26 is:
• 1. 6 to 1
• 2. 8 to 1
• 3. 10 to 1.
• 4. 15 to 1
89
Wire Rope Sling Choker Adjustments
90
Thimbles
• Can be ordered
91
Rigging
• Protect sling from sharp surfaces
• Dekalb accident 1997
• Employees were positioning a 22,000 pound
generator with the use of a truck-mounted
crane and four synthetic web slings.
• While the employees were moving the
generator, the slings contacted a steel purlin
and were cut.
• The generator fell and rolled onto the
employees.
• Employee #1 suffered fatal internal injuries.
• Employee #2 suffered back injuries and was
hospitalized.
• Photo is an example
92
Rigging Safety
• Know the proper crane signals
• A signal person is required
when:
• The point of operation is not in
full view of the operator
(1926.1419(a)).
• The operator’s view is
obstructed in the direction the
equipment is traveling.
• Either the operator or the
person handling the load
determines that a signal
person is needed because of
site-specific safety concerns.
93
Rigging Protection From
Cutting or Slipping
Softeners, padding or use of blocking..
Softeners
95
Note: A good operating practice is to keep sling angles from
going below 60 degrees
1000 LBS 1000 LBS 1000 LBS 1000 LBS
500LBS
500LBS
1000 LBS 1000 LBS
90 60° 45° 30°
Rigging Safety
Proper calculation of increased tension caused by
sling angles (on all rigging components!).
96
Loss Factor
97
Rigging Safety
• Keep personnel clear
from lift area.
• 1926.953(d) requires
taglines on any load
“where hazards to
employees exist” in
order to keep the loads
under control
98
Rigging Safety
• Calculate reductions
when using choker hitch
99
Bridle Slings
As a general industry practice,
a four-legged wire rope or
synthetic bridle assembly is
usually tagged with the
capacity based on:
• 1. Three of the four legs
carrying the load
• 2. Two of the four legs
carrying the load
• 3. All four legs carrying the
load…
• 4. None of the above
100
Bridle Slings
• Four-legged chain sling
bridle assemblies
generally have a capacity
on their tag based on:
• 1. Three of the four legs
carrying the load..
• 2. Two of the four legs
carrying the load
• 3. All four legs carrying
the load
• 4. None of the above
101
Chain Slings
Only Grade 8 or better Alloy Chain can be used for overhead lifting
purposes! All chain is not rated the same!
Chain must have a capacity tag attached to it.
Chains will withstand more rough handling and abuse, but a chain
with the same rated lifting capacity of wire rope will be much
larger in diameter and heavier in weight
Chain Slings 2015
103
Chain Slings
• Four grades:
– Grade 28 General Utility Chain
– Grade 43 High Test Chain
– Grade 70 Binding Chain
– Grade 80 Alloy Steel Chain: The only one used for overhead
lifting
G 80
104
Chain Minimum Thickness
• Table H-1 in
1926.251
• Use Mfr if
available.
105
Alloy Steel Chain Slings
• All Slings
Permanently affixed durable
identification stating
• Size
• Grade
• Rated capacity
• Sling manufacturer
• Table H-1 for wear
106
Wire Rope
107
Wire Rope
• 1926.251(c)(4)(iv)
• Wire rope shall not be
used if, in any length of
eight diameters, the
total number of visible
broken wires exceeds 10
percent of the total
number of wires, or if
the rope shows other
signs of excessive wear,
corrosion, or defect.
108
Wire Rope Slings Industry
• For 6-strand wire rope
slings, 10 randomly
distributed broken
wires in one rope lay, or
five broken wires in one
strand of one rope lay
• ASME B30.9
Many are going lower for broken
wire!!!
6 is a removal criteria for some.
109
Wire Rope
• 1926.251(c)(2) Protruding ends of strands in
splices on slings and bridles shall be covered
or blunted
110
Wire Rope
• 1926.251(c)(4)(iii) Eyes
in wire rope bridles,
slings, or bull wires shall
not be formed by wire
rope clips or knots
111
Wire Rope
• 1926.251(c)(16)
• Wire rope slings shall
have permanently affixed,
legible identification
markings stating size,
rated capacity for the
type(s) of hitch(es) used
and the angle upon which
it is based, and the
number of legs if more
than one.
112
Hooks
Check for
Cracks and
Twisting
Check for Wear and Cracks
Check for Wear and
Deformation
Signs of
“Opening Up”
Check that
Hook is Not
Twisted
15% 10º
113
Shackles
Never replace a shackle
pin with a bolt.
The load will bend the
bolt. 114
Shackles
How tight do you tighten a
screw pin shackle?
• 1. Hand tight and back
off ¼ turn
• 2. Hand tight and back
off ½ turn
• 3. Minimum of hand
tight with pin fully
engaged…
• 4. None of the above
115
Shackles
Check wear
Check cracks,
bending and
twisting
Check wear and
straightness
Pin always seated
Check opening
width
116
Shackles
117
Shackles Pins
118
Rigging equipment for material handling
Bad Good
Avoid eccentric
loads.
GoodBad
Proper chocking of
shackles.
119
Shackles
• In rigging applications,
the maximum included
angle at the top, if a
shackle is used would
be:
• 1. 90 Degrees
• 2. 120 Degrees
• 3. 180 Degrees
• 4. 360 Degrees
120
TAGLINES?
1926.953(d)
• Tag line. Where hazards to employees exist
tag lines or other suitable devices shall be
used to control loads being handled by
hoisting equipment.
• Windy conditions.
• To keep long materials from swinging into
the crane booms.
• To keep loads/materials from swinging into
power lines.
• Maneuvering loads through or around tight
spaces.
• Anytime when working around traffic and
pedestrians.
• When performing steel erection.
• When hoisting close to or onto scaffolds.
• When hoisting suspended personnel
platforms, if appropriate.
• Tag lines are particularly
important on large objects
that can catch a lot of wind
and cause the load to rotate.
• When a rotation of the load
would be hazardous.
• When working on any site
when MSHA rules apply (tag
lines on all loads). 121
Taglines
TYPES OF MATERIALS USED AS
TAGLINES:
• Nonconductive line: dry
polypropylene rope only (when
used around power lines).
• Do not use electrical extension
cords, wire, air hoses or lanyards
used for fall protection.
• No loops, hooks or knots on the
ends of taglines (they tend to
catch on items).
LENGTH OF TAGLINES:
• Short enough so as not to get
tangled on items being lifted over.
• Long enough to handle
bulky/long loads from the ground
(100% control).
• Long enough to control a load
when landing.
•Never work under the load. Stay clear
until the load is at work level
Do not wrap the tagline around your
hands, arms or body
122
Taglines
• Never wrap tagline
around your wrist
123
Spreader Bars
• Capacity marked
• Designed for 3x the
marked capacity.
• Proof tested at 125% of
marked capacity.
124
IDOT
• The erection plan will also
describe the rigging
attachment points and pre-
attached elements such as
cross frames, diaphragms,
or splice plates.
• The approximate center of
gravity location points
should be provided.
• The type, configuration,
weight, capacity, and
arrangement of all rigging
components should be
described.
• This includes slings, chains,
beam clamps, lifting hooks
and spreader, lifting beams,
or frames.
• Lifting beams when
required should be clearly
detailed, including limiting
angles for cables or slings.
125
High Wind
• A wind of such velocity that one
or more of the following hazards
would be present:
• The wind could blow an
employee from an elevated
location,
• The wind could cause an
employee or equipment handling
material to lose control of the
material, or
• The wind would expose an
employee to other hazards not
controlled by the standard
involved.
• Note to the definition of "high
wind": The Occupational Safety
and Health Administration
normally considers winds
exceeding 64.4 kilometers per
hour (40 miles per hour), or 48.3
kilometers per hour (30 miles per
hour) if the work involves
material handling, as meeting this
criteria, unless the employer
takes precautions to protect
employees from the hazardous
effects of the wind.
126
Slab Lifting Devices
• Hazards?
127
Inspection
• 1926.251(a)(1)
• Rigging equipment for
material handling shall
be inspected prior to
use on each shift and as
necessary during its use
to ensure that it is safe.
• Defective rigging
equipment shall be
removed from service
128
Eyebolts
• Eyebolts with shoulder
can be used for vertical
lifts as well as angular lifts
up to 45°.
• However, angular lifts
significantly reduce the
work load.
• For angular lifts,
recommend using
hoist rings.
• Eyebolts without shoulder
are for vertical lifts only.
Sample strength of eyebolt w
shoulder from manufacturer
1/2" 2,400 lbs
A= 1 3/16" B = 1 1/2"
1/2" 2,600 lbs
A = 1 3/16" B = 2 1/2"
129
Hoist Rings
• Used when lifting in
several directions.
130
Eyebolts
In order to use lift the load in a
two legged rigging triangle
application at 75 degrees, which
of the following would be a true
statement?
• 1. Can use eye bolts if angle is
45 degrees or better.
• 2. All eyebolts must have the
proper capacity
• 3. Use of Hoist Rings is
required.
• 4. Can use shouldered eye
bolts.
131
ANSI standards
• ASME non-inspection standards
• ASME B30.5: Mobile and Locomotive Crane
• ASME B30.9: Slings
• ASME B30.10: Hooks
• ASME B30.20: Below-the-Hook Lifting Devices
• ASME B30.26: Rigging Hardware
132
Quick Disconnect
• Bucket has no quick
disconnect that locks
• No hard hats worn
despite being only
inches away from the
bucket.
Quick Disconnect
• Buckets are falling onto
employees
• Must have a pinned
connection if hydraulic
fails that prevents the
bucket from falling.
134
Excavator Lifting
Must follow mfr manual chart 135
1999
136
Multiple Lifts
• 1926.753
• Maximum of 5 pieces
• Similar pieces (no
deck bundles)
• Trained rigger
• Crane manufacturer
must not prohibit it
• 7 foot spacing
Wrong
138
Mar 2014
• Cedar Rapids IA
• Jacob B. "Jake"
Harper, 28, died
Friday after steel
pipes slipped off of a
trailer, struck him
and caused fatal
injuries
CERTIFIED RIGGER LEVEL I
• NCCCO.org identified the following job duties for Rigger Level I
certification. A Certified Rigger Level I can perform simple,
repetitive rigging tasks when the load weight, center of gravity, the
rigging, and rigging configuration are provided or known by the
rigger through experience or on-the-job training prior to the rigging
activities. Specifically, Level I Riggers should be able to demonstrate
or have knowledge of how to:
• Inspect rigging before use
• Identify and attach rigging with basic knowledge of hitch
configurations, capacities, and basic knots
• Recognize associated hazards
• Signal operations
• Use various types of rigging equipment and basic hitches and their
applications
140
Knots
• Candidates must
demonstrate the
following basic knots:
• Sheet bend
• Clove hitch
• Inside bowline
• Square/reef
• Two half hitches
Two half hitches
141
142
November 2014
143
Oct 2013
• Oct 2006 incident
• Carriedo was asked to load
materials onto a crane, which was
lifting concrete forms.
• The crane lifted two loads of the
concrete form, which were
stacked one on top of the other.
When the top load was 25 feet
into the air, material from the
load fell off of the crane,
striking Carriedo.
• He sustained injuries to his head
and stomach, as well as other
injuries.
• After four days of trial, the parties
agreed to a settlement of $13
million
Concrete forms in a stack.
144
How Many Load Carrying
Components?
145
Questions?
146

More Related Content

What's hot

Niu prevention through design newquist 2019
Niu prevention through design newquist 2019Niu prevention through design newquist 2019
Niu prevention through design newquist 2019John Newquist
 
Excavation Safety Training Module 1
Excavation Safety Training Module 1Excavation Safety Training Module 1
Excavation Safety Training Module 1Melissa Lewis
 
20150119-Tightening Bolts
20150119-Tightening Bolts20150119-Tightening Bolts
20150119-Tightening BoltsAllan Phillips
 
Excavation, Trenching, and Soil Mechanics by FHM
Excavation, Trenching, and Soil Mechanics by FHMExcavation, Trenching, and Soil Mechanics by FHM
Excavation, Trenching, and Soil Mechanics by FHMAtlantic Training, LLC.
 
Excavation & trenching
Excavation & trenchingExcavation & trenching
Excavation & trenchingWaseem1212
 

What's hot (9)

osha3252.pdf
osha3252.pdfosha3252.pdf
osha3252.pdf
 
1926 fall 2017
1926 fall 20171926 fall 2017
1926 fall 2017
 
Niu prevention through design newquist 2019
Niu prevention through design newquist 2019Niu prevention through design newquist 2019
Niu prevention through design newquist 2019
 
Ansi z359 2017
Ansi z359 2017Ansi z359 2017
Ansi z359 2017
 
Excavation Safety Training Module 1
Excavation Safety Training Module 1Excavation Safety Training Module 1
Excavation Safety Training Module 1
 
20150119-Tightening Bolts
20150119-Tightening Bolts20150119-Tightening Bolts
20150119-Tightening Bolts
 
Excavation, Trenching, and Soil Mechanics by FHM
Excavation, Trenching, and Soil Mechanics by FHMExcavation, Trenching, and Soil Mechanics by FHM
Excavation, Trenching, and Soil Mechanics by FHM
 
Excavation & trenching
Excavation & trenchingExcavation & trenching
Excavation & trenching
 
OSHA Trenching and Excavation Requirements
OSHA Trenching and Excavation Requirements OSHA Trenching and Excavation Requirements
OSHA Trenching and Excavation Requirements
 

Similar to Rrigging Safety 2020

Gi 2016 industrial rigging safety
Gi 2016 industrial rigging safetyGi 2016 industrial rigging safety
Gi 2016 industrial rigging safetyJohn Newquist
 
Gi forklift and mat handling 2015
Gi forklift and mat handling 2015Gi forklift and mat handling 2015
Gi forklift and mat handling 2015vtsiri
 
Gi forklift and material handling 2015
Gi forklift and material handling 2015Gi forklift and material handling 2015
Gi forklift and material handling 2015John Newquist
 
Construction issues for 2015
Construction issues for 2015Construction issues for 2015
Construction issues for 2015vtsiri
 
Rigging safety 7
Rigging safety 7Rigging safety 7
Rigging safety 7vtsiri
 
1926 concrete safety 2018
1926 concrete safety 20181926 concrete safety 2018
1926 concrete safety 2018John Newquist
 
1926 concrete safety 2017
1926 concrete safety 20171926 concrete safety 2017
1926 concrete safety 2017John Newquist
 
RUDDER TRUNK MISMATCH
RUDDER TRUNK MISMATCHRUDDER TRUNK MISMATCH
RUDDER TRUNK MISMATCHApoorv Dhawan
 
Trenching 2014 year in review
Trenching 2014 year in reviewTrenching 2014 year in review
Trenching 2014 year in reviewJohn Newquist
 
Trenching 2014 year in review
Trenching 2014 year in reviewTrenching 2014 year in review
Trenching 2014 year in reviewvtsiri
 
Peabody_Rigging_Program.ppt
Peabody_Rigging_Program.pptPeabody_Rigging_Program.ppt
Peabody_Rigging_Program.pptAdnanZafar88
 
1926 motor vechicles and struck by 2021
1926 motor vechicles and struck by 20211926 motor vechicles and struck by 2021
1926 motor vechicles and struck by 2021John Newquist
 
2003 Seven Mile Dam Ph 2 Presentation, Karen and Ajay
2003 Seven Mile Dam Ph 2 Presentation, Karen and Ajay2003 Seven Mile Dam Ph 2 Presentation, Karen and Ajay
2003 Seven Mile Dam Ph 2 Presentation, Karen and AjayDario Gnoato
 

Similar to Rrigging Safety 2020 (20)

Gi 2016 industrial rigging safety
Gi 2016 industrial rigging safetyGi 2016 industrial rigging safety
Gi 2016 industrial rigging safety
 
Gi forklift and mat handling 2015
Gi forklift and mat handling 2015Gi forklift and mat handling 2015
Gi forklift and mat handling 2015
 
Gi forklift and material handling 2015
Gi forklift and material handling 2015Gi forklift and material handling 2015
Gi forklift and material handling 2015
 
Construction issues for 2015
Construction issues for 2015Construction issues for 2015
Construction issues for 2015
 
Bobby's Resume
Bobby's ResumeBobby's Resume
Bobby's Resume
 
Rigging safety 7
Rigging safety 7Rigging safety 7
Rigging safety 7
 
1926 concrete safety 2018
1926 concrete safety 20181926 concrete safety 2018
1926 concrete safety 2018
 
Asse may 2016
Asse may 2016Asse may 2016
Asse may 2016
 
1926 concrete safety 2017
1926 concrete safety 20171926 concrete safety 2017
1926 concrete safety 2017
 
Steel truss ppt
Steel truss pptSteel truss ppt
Steel truss ppt
 
RUDDER TRUNK MISMATCH
RUDDER TRUNK MISMATCHRUDDER TRUNK MISMATCH
RUDDER TRUNK MISMATCH
 
Trenching 2014 year in review
Trenching 2014 year in reviewTrenching 2014 year in review
Trenching 2014 year in review
 
Trenching 2014 year in review
Trenching 2014 year in reviewTrenching 2014 year in review
Trenching 2014 year in review
 
ABC in Nebraska
ABC in NebraskaABC in Nebraska
ABC in Nebraska
 
Special structure
Special structureSpecial structure
Special structure
 
510 cranes 2018
510 cranes 2018510 cranes 2018
510 cranes 2018
 
Peabody_Rigging_Program.ppt
Peabody_Rigging_Program.pptPeabody_Rigging_Program.ppt
Peabody_Rigging_Program.ppt
 
1926 motor vechicles and struck by 2021
1926 motor vechicles and struck by 20211926 motor vechicles and struck by 2021
1926 motor vechicles and struck by 2021
 
2003 Seven Mile Dam Ph 2 Presentation, Karen and Ajay
2003 Seven Mile Dam Ph 2 Presentation, Karen and Ajay2003 Seven Mile Dam Ph 2 Presentation, Karen and Ajay
2003 Seven Mile Dam Ph 2 Presentation, Karen and Ajay
 
510 demolition 2018
510 demolition 2018510 demolition 2018
510 demolition 2018
 

More from John Newquist

Industrial Fall protection 2021
Industrial Fall protection 2021Industrial Fall protection 2021
Industrial Fall protection 2021John Newquist
 
Industrial Hygiene 2021
Industrial Hygiene 2021Industrial Hygiene 2021
Industrial Hygiene 2021John Newquist
 
Supervisor reasonable suspicion training sl 2020
Supervisor reasonable suspicion training sl 2020Supervisor reasonable suspicion training sl 2020
Supervisor reasonable suspicion training sl 2020John Newquist
 
Mechanical contractor lockout confined space awareness ppt 2021
Mechanical contractor lockout confined space awareness ppt 2021Mechanical contractor lockout confined space awareness ppt 2021
Mechanical contractor lockout confined space awareness ppt 2021John Newquist
 
Trenching Safety 2020
Trenching Safety 2020Trenching Safety 2020
Trenching Safety 2020John Newquist
 
Incident Investigation Newquist 2020
Incident Investigation Newquist 2020Incident Investigation Newquist 2020
Incident Investigation Newquist 2020John Newquist
 
Noise and Hearing Conservation 2020
Noise and Hearing Conservation  2020Noise and Hearing Conservation  2020
Noise and Hearing Conservation 2020John Newquist
 
OSHA Written HAzard Commnication Written Program
OSHA Written HAzard Commnication Written ProgramOSHA Written HAzard Commnication Written Program
OSHA Written HAzard Commnication Written ProgramJohn Newquist
 
Caught in or between hazards 2020
Caught in or between hazards 2020 Caught in or between hazards 2020
Caught in or between hazards 2020 John Newquist
 
Introduction to OSHA
Introduction to OSHAIntroduction to OSHA
Introduction to OSHAJohn Newquist
 
Covid19 webinar final
Covid19 webinar finalCovid19 webinar final
Covid19 webinar finalJohn Newquist
 
Coronavirus Covid March 2020
Coronavirus Covid March 2020 Coronavirus Covid March 2020
Coronavirus Covid March 2020 John Newquist
 
511 ghs 2020 one hour
511 ghs 2020 one hour511 ghs 2020 one hour
511 ghs 2020 one hourJohn Newquist
 
Construction Most Cited FY2019 OSHA
Construction Most Cited FY2019 OSHAConstruction Most Cited FY2019 OSHA
Construction Most Cited FY2019 OSHAJohn Newquist
 
Osha respirator fit test protocol 2019
Osha respirator fit test protocol  2019Osha respirator fit test protocol  2019
Osha respirator fit test protocol 2019John Newquist
 
Industrial safety management 7500 2019
Industrial safety management 7500 2019Industrial safety management 7500 2019
Industrial safety management 7500 2019John Newquist
 

More from John Newquist (20)

Industrial Fall protection 2021
Industrial Fall protection 2021Industrial Fall protection 2021
Industrial Fall protection 2021
 
Industrial Hygiene 2021
Industrial Hygiene 2021Industrial Hygiene 2021
Industrial Hygiene 2021
 
Supervisor reasonable suspicion training sl 2020
Supervisor reasonable suspicion training sl 2020Supervisor reasonable suspicion training sl 2020
Supervisor reasonable suspicion training sl 2020
 
Mechanical contractor lockout confined space awareness ppt 2021
Mechanical contractor lockout confined space awareness ppt 2021Mechanical contractor lockout confined space awareness ppt 2021
Mechanical contractor lockout confined space awareness ppt 2021
 
Trenching Safety 2020
Trenching Safety 2020Trenching Safety 2020
Trenching Safety 2020
 
Incident Investigation Newquist 2020
Incident Investigation Newquist 2020Incident Investigation Newquist 2020
Incident Investigation Newquist 2020
 
Noise and Hearing Conservation 2020
Noise and Hearing Conservation  2020Noise and Hearing Conservation  2020
Noise and Hearing Conservation 2020
 
PPE Safety
PPE SafetyPPE Safety
PPE Safety
 
OSHA Written HAzard Commnication Written Program
OSHA Written HAzard Commnication Written ProgramOSHA Written HAzard Commnication Written Program
OSHA Written HAzard Commnication Written Program
 
Caught in or between hazards 2020
Caught in or between hazards 2020 Caught in or between hazards 2020
Caught in or between hazards 2020
 
Introduction to OSHA
Introduction to OSHAIntroduction to OSHA
Introduction to OSHA
 
Hand safety 2020
Hand safety 2020Hand safety 2020
Hand safety 2020
 
Covid19 webinar final
Covid19 webinar finalCovid19 webinar final
Covid19 webinar final
 
Coronavirus Covid March 2020
Coronavirus Covid March 2020 Coronavirus Covid March 2020
Coronavirus Covid March 2020
 
Hand Safety 2020
Hand Safety 2020Hand Safety 2020
Hand Safety 2020
 
Ghs 2020 one hour
Ghs 2020 one hourGhs 2020 one hour
Ghs 2020 one hour
 
511 ghs 2020 one hour
511 ghs 2020 one hour511 ghs 2020 one hour
511 ghs 2020 one hour
 
Construction Most Cited FY2019 OSHA
Construction Most Cited FY2019 OSHAConstruction Most Cited FY2019 OSHA
Construction Most Cited FY2019 OSHA
 
Osha respirator fit test protocol 2019
Osha respirator fit test protocol  2019Osha respirator fit test protocol  2019
Osha respirator fit test protocol 2019
 
Industrial safety management 7500 2019
Industrial safety management 7500 2019Industrial safety management 7500 2019
Industrial safety management 7500 2019
 

Recently uploaded

College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...ranjana rawat
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxhumanexperienceaaa
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 

Recently uploaded (20)

★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 

Rrigging Safety 2020

  • 2. Hard Hats • April 4, 2010 • “chain broke and whipped back” • “scared the heck out of me” • “that was a BUNCH of weight hittin me” • “hard hat saved me” 2
  • 3. January 2015 • One company • Two box knife cuts • One stripping cable • Another cutting open a box toward him 3
  • 4. June 2014 • Broken toes. • Leather work boots. • No safety toe • Crane dropped load as lifted 4
  • 5. Oct 2015 • Steel Beam dropped on foot. • 6000 lbs 5
  • 6. MATERIALS STORED TO PREVENT SLIDING FALLING, OR COLLAPSE 9 9 10 17 18 251(a)(2)(i) 250(a)(1) 251(b)(1) 251(a)(1) 252(a) Materials Handling, Storage, Use & Disposal [1926.250 – 252] 6 GENERAL RIGGING EQUIPMENT IDENTIFICATION EXTERIOR DROP CHUTES RIGGING EQUIPMENT INSPECTION & REMOVAL FROM SERVICE WELDED ALLOY STEEL CHAIN SLING IDENTIFICATION SUBPARTH
  • 8. Nov 2017 • Indicator that sling is stretched. • Slingmax. 8
  • 9. Mar 2018 Officials said reinforcing steel that was being moved by a crane fell and landed on Michael Tolman, 56, who was taken to Orlando Regional Medical Center in critical condition. He later died 9
  • 11. Jan 2018 How would you lift? 4 x 11 foot 300 pounds 5/8 inch 11
  • 13. Dec 2017 Beaumont TX 24 inch "incident pipe" that killed Espinoza was more than 25 feet long and "may have" weighed more than 4,400 pounds. He said that the strap and hoist connected to the pipe during the inspection indicated it could cause the pipe to swing or rotate. Yesenia Espinoza, 31, was working on new construction when the "piping that was improperly rigged and handled" fatally hit her in the head, the lawsuit 13
  • 14. Dec 2017 How would you rig? 14
  • 18. Jan 2017 Gunnebo Johnson Swivel eye hookCrosby Shur Loc 18
  • 20. December 2016 • Chicago IL • Two finger amputation 20
  • 22. Nov 2016 • New York City • Crane operator George Smith, 47, and worker Elizandro Ramos, 43, were killed when the I-beam plummeted onto the top of the cab in Briarwood Tuesday. • Winds were gusting at close to 40 mph at the time – above the legal city limit of 30 mph to operate – • The city officials said that the rigging rope may have failed. 22
  • 24. Feb 2016 • Two workers were killed when a generator fell on them at a construction site in New Jersey Thursday morning, officials said. • The five-ton generator fell on the workers at the site -- a future fire station -- after a strap on the crane lowering it snapped, according to officials with the Morris County Prosecutor's Office. 24
  • 26. July 2015 • New Jersey Scaffold • Photo Jimmy Cuellar 26
  • 27. April 2015 • Cheshire NY • Crane Operator died • Two of the men working at the construction site were shocked by the electric charge. • Investigators said the two men were measuring the steel beam when the crane hit the power lines. 27
  • 28. Basic Rigger • Safely uses and recognizes the limitations of chain, synthetic, metal mesh, and wire rope slings • Safely uses and recognizes the limitations of specific rigging hardware to include: hooks and similar attaching devices, shackles, wire rope clips, clamps, eyebolts, softeners, and taglines. • Identifies common load configurations and positioning and demonstrates specific knowledge of crane operations including voice and radio • Understands personal fall protection methods, emergency procedures, and hazards and restrictions with working in proximity to overhead electric lines and equipment • NCCER.org 28
  • 29. April 2015 • Lifting a piece of pine about 5 foot long 18 inches across • “the load made it to the ground ok the hook of the biner caught the strap and held till we lowered it down.” 29
  • 30. May 2014 • Providence RI • 8 hurt in fall • The US Occupational Safety and Health Administration said the rigging used put excessive weight on a carabiner, causing the metal loop to fail, and the acrobats, who were hanging by their hair, to fall 15 to 20 feet to t • According to OSHA, circus staff violated both industry practice and the manufacturer’s instructions for using the carabiner by attaching it so it was pulled in three directions, rather than two. 30
  • 31. Key Changes in Z359.1 • Section 3.2.1.4 • Gate face strength requirements have changed from 220 lbs. (1kN) (old Standard) to 3,600 lbs. (16kN) (new Standard). 31
  • 32. April 2015 • Lifting a stump grinder. 32
  • 33. April 2015 • Schulyer OH • The victim, whose name is being withheld pending family notification, was driving a front end loader while attempting to free a cement truck that got stuck by pulling the vehicle with a chain. • The chain snapped and struck the victim. • He was pronounced dead at the scene. How could you free this truck? 33
  • 34. January 2015 • “This is how I read a manual looking straight up” – Ryan Ferguson • “ i don't need to read a book to know how it works” – Caleb Pate 34
  • 35. December 2014 • Rigging to move an aerial lift • Every lift aerial has four designated pick points. 35
  • 36. November 2014 • What issues would a rigger need to know? 36
  • 38. August 2014 • $15 • Sold as ½ inch alloy steel • Supposed to lift 70,000 pounds • Specifications • 1) we are factory 2) from 3/8" to 1 3/8" 3) galvanized / red painted 4) 40Cr steel / stainless steel 5)mini order accepted 38
  • 40. July 2014 • 100,000 pound transformer • Each sling is Kevlar $90,000 40
  • 41. Storage • 1926.250(b)(1) • Material stored inside buildings under construction shall not be placed within 6 feet of any hoistway or inside floor openings, nor within 10 feet of an exterior wall which does not extend above the top of the material stored 41
  • 42. June 2013 • Officials canceled work on the St. Charles County bridge after a 55- gallon drum being lifted by a crane fell on 51-year-old Jerseyville IL man. • He was pronounced dead at the scene. 42
  • 46. Mar 2018 Engineering debris boxes. 2500 pounds capacity. Proof Tested. Photo by Lee Jensen sales 46
  • 48. Hit by Pulley • Event Date: 07/27/2010 • Inspection: 314807090 • Employee #1 was struck in the head by a metal pulley when the nylon sling to which it was connected broke. • The pulley was being used to drag felled trees. • When the rigging was put under tension, the nylon sling broke, releasing the pulley, hitting the employee in the head. • 50 M 48
  • 49. Jan 2018 • An employee was checking the rigging on a rig. • His hand was on a sling that was lifting a piece of pipe when his right hand was caught between the sling and the pipe. • His right little finger had to be surgically amputated. 49
  • 50. Pipe Fell • Event Date: 04/29/2010 • Inspection: 314409277 • An employee was struck on the head by a drilling pipe which resulted in fatal injuries. • The employee rigged a 20 foot section of pipe and as it was being lifted by the operator, the pipe came loose from the rigging and fell approximately 10 to 15 feet onto the head of the employee. • The employee died as a result of his injuries. • 50 M Fatality • 50
  • 52. Definitions Name Description Visual Hitch “Basket” Loading with the sling passed under the load and both ends on the hook or a single master link. Hitch “Choker” Loading with the sling passed through one eye and suspended by the other. Hitch “Vertical” Loading with the load suspended vertically on a single part or leg of the sling.
  • 53. Definitions Master link – a steel link or ring used to support all legs of a chain or wire rope sling. Must have identifiers such as: Grade: 800 Working Load Limit: 3,600 lbs Size: 13/32"
  • 55. Definitions Rated capacity – the maximum allowable working load.
  • 59. Definitions Wire rope – consists of many individual wires laid into a number of strands which are in turn, laid around a center core.
  • 61. 10 Rules for Rigging Safety #1 • Know the weight of the load • Concrete slab • Steel Beam • Concrete form • Tree 61
  • 62. Bulk Density • Building material Unit weight – Aluminum: 171 pounds per cubic foot – Cast Iron: 450 pounds per cubic foot – Cement: 94 pounds per cubic foot – Concrete: 150 pounds per cubic foot – Crushed Stone: 2,500 pounds per cubic yard – Gravel: 2,700 pounds per cubic yard 62
  • 63. Bulk Density • Steel plate thickness is One inch to 40#/square foot • What would this plate weigh? 63
  • 64. 64
  • 65. Volume & Area Formulas
  • 66. 2013 • The NRC has now concluded that Entergy "approved a design for the temporary hoisting assembly that was not supported by detailed drawings, specifications, evaluations and/or certifications.“ • In addition, Entergy failed to review associated calculations to ensure that the assembly was designed to support the projected load. • It also failed to carry out a load test on the lifting assembly in all configurations for which it would be used. The stator weighed 525 tons. 66
  • 67. 10 Rules for Rigging Safety #2 • Know the center of gravity of the load. 67
  • 68. Center of Gravity A load is stable when: – The hook is directly above the center of gravity of the load Estimate the center of gravity Lift the load just enough to clear the ground If the hook is not over the center of gravity the hook will travel to the center of gravity CG? 68
  • 69. Center of Gravity If necessary, set the load down and adjust the rigging If the load tips more than 3°, the rigging should be adjusted The longer the sling legs, the more stable the load will be The longer set of sling legs (B) will improve load stability B A 69
  • 70. In this situation, before raising the section, all personnel are kept clear of the section and the section is first raised a few inches to determine whether it tips when raised (if it did tip, it would indicate it is not rigged over the center of gravity). If this occurs, the hoist line is repositioned and the procedure repeated (with employees kept clear of the section while it is raised) until the A/D director determines that it is rigged over the center of gravity and can be moved into place without dangerous movement. App C of Crane Std 70
  • 72. May 2015 • Amesbury MA bridge 72
  • 73. How Would You Rig This? Would it matter if the tank were full or empty? How would you rig this?
  • 74. Rules for Rigging Safety • Know the rated capacity of slings and hardware. 74
  • 75. Rules for Rigging Safety • Inspect all rigging before use. 1926.251(a)(6) shall be inspected for damage or defects by a competent person every shift (CHST) 75
  • 77. June 2016 Photo Mike Parnell 77
  • 78. November 2014 • Crane next to sheeting • 8 foot x 8 foot pads with max load of 125,000 pounds per pad • 164,000 pounds max load per chart • What information is needed? 78
  • 79. Rigging equipment for material handling • Synthetic webbing (nylon, polyester, and polypropylene) • Remove from service immediately if: – Acid or caustic burns – Melting or charring of any part of the sling surface – Snags, punctures, tears or cuts – Broken or worn stitches – Distortion of fittings 79
  • 80. Synthetic Slings Sling capacity varies from manufacturer to manufacturer. Competent person must look at Individual Sling Capacity Tag to determine Safe Lifting Capacity of that sling. If the Tag is not readable or is missing, Do not use it! Inspect sling before each days use, and as often as necessary during the day to assure safety of sling! Sharp edges can slice a sling in two without warning as the load is tensioned. Use softeners or padding on corners. “If you see red, the sling is dead.”
  • 81. Synthetic Slings Holes, tears, cuts or snags 81
  • 84. Inspection • Wire rope and synthetic slings addressed in the B30.9 ASME standard require: • 1. Documented periodic inspection at least annually, but condition of individual slings not required.. • 2. Periodic inspection at least annually but written records not required • 3. Visual Inspection minimum of weekly • 4. None of the above • 9-6.9.3 Periodic Inspection • (d) Documentation that the most recent periodic inspection was performed and shall be maintained. • (e) Inspection records of individual slings are not required. 84
  • 85. Rigging Safety • Allow for D/d ratio on all wire rope slings. 85
  • 86. Rigging equipment for material handling D d D/d Ratio D - is diameter around which sling is bent. d - is diameter of the sling. 86
  • 87. D/d Ratio Some wire rope sling manufacturers require a D/d ratio of 25 for a basket hitch. 87
  • 88. D/d ratio hooks • What D/d ratio would you use? 88
  • 89. D/d Ratio Snatch Blocks The minimum D/d ratio for snatch blocks per ASME B30.26 is: • 1. 6 to 1 • 2. 8 to 1 • 3. 10 to 1. • 4. 15 to 1 89
  • 90. Wire Rope Sling Choker Adjustments 90
  • 91. Thimbles • Can be ordered 91
  • 92. Rigging • Protect sling from sharp surfaces • Dekalb accident 1997 • Employees were positioning a 22,000 pound generator with the use of a truck-mounted crane and four synthetic web slings. • While the employees were moving the generator, the slings contacted a steel purlin and were cut. • The generator fell and rolled onto the employees. • Employee #1 suffered fatal internal injuries. • Employee #2 suffered back injuries and was hospitalized. • Photo is an example 92
  • 93. Rigging Safety • Know the proper crane signals • A signal person is required when: • The point of operation is not in full view of the operator (1926.1419(a)). • The operator’s view is obstructed in the direction the equipment is traveling. • Either the operator or the person handling the load determines that a signal person is needed because of site-specific safety concerns. 93
  • 94. Rigging Protection From Cutting or Slipping Softeners, padding or use of blocking..
  • 96. Note: A good operating practice is to keep sling angles from going below 60 degrees 1000 LBS 1000 LBS 1000 LBS 1000 LBS 500LBS 500LBS 1000 LBS 1000 LBS 90 60° 45° 30° Rigging Safety Proper calculation of increased tension caused by sling angles (on all rigging components!). 96
  • 98. Rigging Safety • Keep personnel clear from lift area. • 1926.953(d) requires taglines on any load “where hazards to employees exist” in order to keep the loads under control 98
  • 99. Rigging Safety • Calculate reductions when using choker hitch 99
  • 100. Bridle Slings As a general industry practice, a four-legged wire rope or synthetic bridle assembly is usually tagged with the capacity based on: • 1. Three of the four legs carrying the load • 2. Two of the four legs carrying the load • 3. All four legs carrying the load… • 4. None of the above 100
  • 101. Bridle Slings • Four-legged chain sling bridle assemblies generally have a capacity on their tag based on: • 1. Three of the four legs carrying the load.. • 2. Two of the four legs carrying the load • 3. All four legs carrying the load • 4. None of the above 101
  • 102. Chain Slings Only Grade 8 or better Alloy Chain can be used for overhead lifting purposes! All chain is not rated the same! Chain must have a capacity tag attached to it. Chains will withstand more rough handling and abuse, but a chain with the same rated lifting capacity of wire rope will be much larger in diameter and heavier in weight
  • 104. Chain Slings • Four grades: – Grade 28 General Utility Chain – Grade 43 High Test Chain – Grade 70 Binding Chain – Grade 80 Alloy Steel Chain: The only one used for overhead lifting G 80 104
  • 105. Chain Minimum Thickness • Table H-1 in 1926.251 • Use Mfr if available. 105
  • 106. Alloy Steel Chain Slings • All Slings Permanently affixed durable identification stating • Size • Grade • Rated capacity • Sling manufacturer • Table H-1 for wear 106
  • 108. Wire Rope • 1926.251(c)(4)(iv) • Wire rope shall not be used if, in any length of eight diameters, the total number of visible broken wires exceeds 10 percent of the total number of wires, or if the rope shows other signs of excessive wear, corrosion, or defect. 108
  • 109. Wire Rope Slings Industry • For 6-strand wire rope slings, 10 randomly distributed broken wires in one rope lay, or five broken wires in one strand of one rope lay • ASME B30.9 Many are going lower for broken wire!!! 6 is a removal criteria for some. 109
  • 110. Wire Rope • 1926.251(c)(2) Protruding ends of strands in splices on slings and bridles shall be covered or blunted 110
  • 111. Wire Rope • 1926.251(c)(4)(iii) Eyes in wire rope bridles, slings, or bull wires shall not be formed by wire rope clips or knots 111
  • 112. Wire Rope • 1926.251(c)(16) • Wire rope slings shall have permanently affixed, legible identification markings stating size, rated capacity for the type(s) of hitch(es) used and the angle upon which it is based, and the number of legs if more than one. 112
  • 113. Hooks Check for Cracks and Twisting Check for Wear and Cracks Check for Wear and Deformation Signs of “Opening Up” Check that Hook is Not Twisted 15% 10º 113
  • 114. Shackles Never replace a shackle pin with a bolt. The load will bend the bolt. 114
  • 115. Shackles How tight do you tighten a screw pin shackle? • 1. Hand tight and back off ¼ turn • 2. Hand tight and back off ½ turn • 3. Minimum of hand tight with pin fully engaged… • 4. None of the above 115
  • 116. Shackles Check wear Check cracks, bending and twisting Check wear and straightness Pin always seated Check opening width 116
  • 119. Rigging equipment for material handling Bad Good Avoid eccentric loads. GoodBad Proper chocking of shackles. 119
  • 120. Shackles • In rigging applications, the maximum included angle at the top, if a shackle is used would be: • 1. 90 Degrees • 2. 120 Degrees • 3. 180 Degrees • 4. 360 Degrees 120
  • 121. TAGLINES? 1926.953(d) • Tag line. Where hazards to employees exist tag lines or other suitable devices shall be used to control loads being handled by hoisting equipment. • Windy conditions. • To keep long materials from swinging into the crane booms. • To keep loads/materials from swinging into power lines. • Maneuvering loads through or around tight spaces. • Anytime when working around traffic and pedestrians. • When performing steel erection. • When hoisting close to or onto scaffolds. • When hoisting suspended personnel platforms, if appropriate. • Tag lines are particularly important on large objects that can catch a lot of wind and cause the load to rotate. • When a rotation of the load would be hazardous. • When working on any site when MSHA rules apply (tag lines on all loads). 121
  • 122. Taglines TYPES OF MATERIALS USED AS TAGLINES: • Nonconductive line: dry polypropylene rope only (when used around power lines). • Do not use electrical extension cords, wire, air hoses or lanyards used for fall protection. • No loops, hooks or knots on the ends of taglines (they tend to catch on items). LENGTH OF TAGLINES: • Short enough so as not to get tangled on items being lifted over. • Long enough to handle bulky/long loads from the ground (100% control). • Long enough to control a load when landing. •Never work under the load. Stay clear until the load is at work level Do not wrap the tagline around your hands, arms or body 122
  • 123. Taglines • Never wrap tagline around your wrist 123
  • 124. Spreader Bars • Capacity marked • Designed for 3x the marked capacity. • Proof tested at 125% of marked capacity. 124
  • 125. IDOT • The erection plan will also describe the rigging attachment points and pre- attached elements such as cross frames, diaphragms, or splice plates. • The approximate center of gravity location points should be provided. • The type, configuration, weight, capacity, and arrangement of all rigging components should be described. • This includes slings, chains, beam clamps, lifting hooks and spreader, lifting beams, or frames. • Lifting beams when required should be clearly detailed, including limiting angles for cables or slings. 125
  • 126. High Wind • A wind of such velocity that one or more of the following hazards would be present: • The wind could blow an employee from an elevated location, • The wind could cause an employee or equipment handling material to lose control of the material, or • The wind would expose an employee to other hazards not controlled by the standard involved. • Note to the definition of "high wind": The Occupational Safety and Health Administration normally considers winds exceeding 64.4 kilometers per hour (40 miles per hour), or 48.3 kilometers per hour (30 miles per hour) if the work involves material handling, as meeting this criteria, unless the employer takes precautions to protect employees from the hazardous effects of the wind. 126
  • 127. Slab Lifting Devices • Hazards? 127
  • 128. Inspection • 1926.251(a)(1) • Rigging equipment for material handling shall be inspected prior to use on each shift and as necessary during its use to ensure that it is safe. • Defective rigging equipment shall be removed from service 128
  • 129. Eyebolts • Eyebolts with shoulder can be used for vertical lifts as well as angular lifts up to 45°. • However, angular lifts significantly reduce the work load. • For angular lifts, recommend using hoist rings. • Eyebolts without shoulder are for vertical lifts only. Sample strength of eyebolt w shoulder from manufacturer 1/2" 2,400 lbs A= 1 3/16" B = 1 1/2" 1/2" 2,600 lbs A = 1 3/16" B = 2 1/2" 129
  • 130. Hoist Rings • Used when lifting in several directions. 130
  • 131. Eyebolts In order to use lift the load in a two legged rigging triangle application at 75 degrees, which of the following would be a true statement? • 1. Can use eye bolts if angle is 45 degrees or better. • 2. All eyebolts must have the proper capacity • 3. Use of Hoist Rings is required. • 4. Can use shouldered eye bolts. 131
  • 132. ANSI standards • ASME non-inspection standards • ASME B30.5: Mobile and Locomotive Crane • ASME B30.9: Slings • ASME B30.10: Hooks • ASME B30.20: Below-the-Hook Lifting Devices • ASME B30.26: Rigging Hardware 132
  • 133. Quick Disconnect • Bucket has no quick disconnect that locks • No hard hats worn despite being only inches away from the bucket.
  • 134. Quick Disconnect • Buckets are falling onto employees • Must have a pinned connection if hydraulic fails that prevents the bucket from falling. 134
  • 135. Excavator Lifting Must follow mfr manual chart 135
  • 137. Multiple Lifts • 1926.753 • Maximum of 5 pieces • Similar pieces (no deck bundles) • Trained rigger • Crane manufacturer must not prohibit it • 7 foot spacing
  • 139. Mar 2014 • Cedar Rapids IA • Jacob B. "Jake" Harper, 28, died Friday after steel pipes slipped off of a trailer, struck him and caused fatal injuries
  • 140. CERTIFIED RIGGER LEVEL I • NCCCO.org identified the following job duties for Rigger Level I certification. A Certified Rigger Level I can perform simple, repetitive rigging tasks when the load weight, center of gravity, the rigging, and rigging configuration are provided or known by the rigger through experience or on-the-job training prior to the rigging activities. Specifically, Level I Riggers should be able to demonstrate or have knowledge of how to: • Inspect rigging before use • Identify and attach rigging with basic knowledge of hitch configurations, capacities, and basic knots • Recognize associated hazards • Signal operations • Use various types of rigging equipment and basic hitches and their applications 140
  • 141. Knots • Candidates must demonstrate the following basic knots: • Sheet bend • Clove hitch • Inside bowline • Square/reef • Two half hitches Two half hitches 141
  • 142. 142
  • 144. Oct 2013 • Oct 2006 incident • Carriedo was asked to load materials onto a crane, which was lifting concrete forms. • The crane lifted two loads of the concrete form, which were stacked one on top of the other. When the top load was 25 feet into the air, material from the load fell off of the crane, striking Carriedo. • He sustained injuries to his head and stomach, as well as other injuries. • After four days of trial, the parties agreed to a settlement of $13 million Concrete forms in a stack. 144
  • 145. How Many Load Carrying Components? 145