SlideShare a Scribd company logo
1 of 82
Construction Crane Safety
Draft 12 14 2016
July 2016
• Tarrytown NY
• Cuomo said the crane
that collapsed had
been using a vibratory
hammer to drive in
pilings when it "had
an issue" that caused
its boom to fall onto
the existing bridge
nearby.
• Manitowoc MLC 300 Soft spot for the pile?
May 2016
• Court of Appeals affirm
Mountain States for a willful
violation of the Occupational
Safety and Health Act's wire
rope inspection standard.
• According to Category II of the
wire rope inspection standard,
a crane must be taken out of
service and repaired if a cable
has “visible broken wires.”
• Citation and assessed a
$60,000 penalty.
• 1926.1413(a)(2)(ii)(A)(1)
• In running wire ropes: Six
randomly distributed broken
wires in one rope lay or three
broken wires in one strand in
one rope lay, where a rope lay
is the length along the rope in
which one strand makes a
complete revolution around the
rope
February 2016
Aftermath
• "The new rules would require crawler cranes to stop
operating and go into safety mode under two scenarios:
when there is a forecast for steady wind speeds of 20
miles per hour or higher or gusts of at least 30 m.p.h.,
and when actual readings reach those levels.
• Previously, such cranes could operate until measured
wind speeds reached 30 m.p.h. or gusts increased to 40
m.p.h., though individual manufacturers sometimes set
stricter standards.“
• “Mr. Reilly had failed to secure the crane the night before the crash
and lowered the boom of the crane at an improper angle, causing
the crane to become unstable, officials said. “
Mar 2016
• Florida
• The crane tipped over, nose
forward, just before 2 p.m.
• A worker on site who
declined to give his name
said it snagged on
something as it drilled into
the ground.
• 130-foot crane.
Dec 2015
Plymouth MA Roof crushed
Oct 2015
• Atlanta GA
July 2015
• A Manhattan jury awarded
almost $50 million in damages
Thursday to the families of two
construction workers who died
in a May 30, 2008 crane
collapse on E. 91 St.
• An email from the Chinese
company, RTR Bearing, to one
of Mr. Lomma’s employees.
• “The email said RTR could not
stand behind the safety of the
bearing, especially a weld
holding it to a spacer ring.
“Honestly speaking, we don’t
have confidence on this
welding,”
Last August, DOB moved to shut him
down for a pattern of safety violations.
Lomma is fighting them.
May 2015
• Santa Clara CA
April 2015
• Milwaukee
• Officials with the
Wisconsin Department of
Transportation (WisDOT)
said the apparatus that
tipped over is a 25-ton
crane; it’s one of the
smallest pieces of
equipment on the
construction site.
• No Outriggers used
April 2015
• Cheshire NY
• A man was killed after a crane
lifting a steel beam hit
electrical wires shocking three
people.
• Deputies say the men were
delivering the beam to a
construction site on Coye
Road using the crane to lift the
beams.
• We're told the crane went too
high and hit the wires.
• Three men outside the crane
were shocked
April 2015
• Dallas TX
• “The operator was injured when the crane fell.
• He was ambulatory when the ambulance arrived on the scene,” the
museum said
January 2015
• Edwardsville IL
• Justin Jokerst was working on
a large Grove HL150T crane at
a building site at 3951
Lakeview Corporate Drive
about 11 a.m. when he was
crushed by the weight of the
crane's boom, authorities
said.
January 2015
• Elm and State,
Chicago
• Working on platform
of tower crane pinned
and died.
January 2015
• A man was airlifted Saturday
morning when the construction
crane he was operating in
a Garden State Parkway
construction zone overturned
and fell down an embankment,
ejecting him into water, State
Police said.
December 2014
• Elgin IL
• Mechanical engineer Rudolph
Das of Naperville spent nearly
three weeks in intensive care
at Advocate Lutheran General
Hospital in Park Ridge after he
was crushed by a Das was
crushed by a jib, a component
affixed to a crane, Dec. 1
while working on a barge
under the Jane Addams
Tollway bridge over the Fox
River
November 2014
• Duke Energy was
attempting to move
the billboard in order
to make way for new
power lines when the
mobile crane
overturned.
• The power lines were
not energized when
the accident
happened and no one
was injured during the
incident.
June 2014
• FL
• Moving crane on
unstable dirt
• Boom fell backwards
striking construction
worker
May 2014
• Milwaukee
• A crane was lifting about a
half-dozen beams when the
crane tipped over and its arm
landed on top of a car with two
occupants, witnesses said.
• "The crane began to lift the
metal beams straight up, and
the wind caught the beams
and started blowing it east
toward the woman with the
stroller.“
• $15,250 fine
One in black car, two in red car
Why?
• Crane accidents
killed an average of
78 people per year
between 2003 and
2005
• OSHA expects the
final standard to
prevent 22 fatalities
and 175 non-fatal
injuries each year.
May 2013
WI - Butte des Morts bridge
Lifting 52-ton concrete girder when crane fell into river
One dead, one hurt.
Elgin 2012
• Firefighters learned that a
miscalculation had been made
in putting down a track and
supports for the crane.
• A difference of about 6 feet too
close to the river meant the
crane wasn’t on solid ground,
and it broke through the
pavement and leaned slightly
toward the river, with its boom
over the water.
Crane Death
• Event Date:
2/22/1990
• 141 E Walton
9
10
11
12
18
1412(d)(1)
1412(e)(3)(i)
1417(c)(1)
1428(a)
1412(f)(1)
Cranes and Derricks in Construction
[1926.1400 – 1442]
25
INSPECTION DOCUMENTED &
MAINTAINED
SHIFT INSPECTIONS BY A COMPETENT PERSON
EQUIPMENT INSPECTION EVERY 12 MONTHS
SIGNAL PERSON QUALIFICATIONS
OPERATION PROCEDURES OF EQUIPMENT
SUBPARTCC
Timeline
• Intention to develop the rule in July
2002.
• Used negotiated rulemaking committee
consisting both industry and labor.
• The committee completed its work in
2004.
• Released – July 28, 2010
• Published – August 9, 2010
• Effective – November 8, 2010
• Phased in over four years – August 9,
2014
– Certification of operators phased in until Nov
2017
Key Hazards
• Four main causes of worker death and
injury:
• Electrocution, (CHST)
• Crushed by parts of the equipment,
• Struck-by the equipment/load, and
• Falls. (See Subpart M 1926.500-503)
Crane or Not Crane?
• Functional description
– Can hoist,
– Lower and
– Horizontally move a
suspended load
• Forklifts configured to hoist
and lower (by means of a
winch OR hook) and
horizontally move a suspended
load are covered
• Backhoes are excluded even if
used like a crane….1926.1400
(c)(2)
Forklift with attached
boom. 1926.1400 (c)(8)
See 1926.1441 if using
equipment with a rated
hoisting/lifting capacity of 2,000
pounds or less
Crane or Not Crane?
• Functional description
– Can hoist,
– Lower and
– Horizontally move a
suspended load
Spyder Crane with a work
platform
30
Operator Qualifications and
Certifications - 4 Options
• OPTION 1:
Accredited testing
organization
• OPTION 2:
Employer qualification
program
• OPTION 3:
U.S. military
• OPTION 4:
State/local gov’t
license
Many companies requiring
2010 certification in their
jobs.
31
Operator Qualifications and
Certifications (cont’d)
Accredited testing
organization
YES * 5 years
Employer Qualification
Program
NO 5 years
US Military license NO * Set by issuing
entity
State/local license NO *
Valid only
in entity’s
jurisdiction
Set by issuing
entity, not > 5
years
Portable Valid
Written Certification Tests
• Administered in any language understood
by the operator candidate.
• Test must cover:
– Controls/performance characteristics
– Calculate capacity (w/ or w/out calculator)
– Preventing power line contact
– Ground support
– Read and locate info in operating manual
– Appendix Q subjects
Practical Examination
• Must be well
designed and
sufficiently
comprehensive
• Must have the
demonstrated the
skills and knowledge
needed to operate the
equipment safely.
An operator's ability to handle
unusual worksite conditions, such as
adverse weather or working on
crowded jobsites, are hazards that
are not commonly part of this exam.
34
1926.1408 Power Lines
• Step 1: Identify Work
Zone
– Work Zone = Marking
boundaries OR
– 360 degrees around
crane up to maximum
working radius
– Make the power line
hazard assessment
35
Could you get within 20
feet of power line?
YES NO
Option #1
Deenergize &
Ground
Encroachment
Prevention measures
Option #3
Ask Utility for
Voltage and
Use Table A
(with minimum
clearance distance)
Option #2
20 foot
clearance
No further
action
• Planning meeting
• If tag lines used Non-conductive
• Elevated warning lines, barricade
or line of signs
•PLUS (Choose one):
• Proximity alarm, spotter, warning
device, range limiter, or insulating link
36
Table A – Minimum Clearance Distances
Voltage (nominal, kV,
alternating current)
Minimum clearance
distance (feet)
up to 50 10
over 50 to 200 15
over 200 to 350 20
over 350 to 500 25
over 500 to 750 35
over 750 to 1000 45
over 1000 (as established by the power line
owner/operator or registered
professional engineer who is a
qualified person with respect to
electrical power transmission and
distribution)
July 2013
• Loading from Trailer
to roof.
• 80 foot of boom
• Center point of crane
18 feet from lower line
• What needs to be
done?
Intentionally Working Closer
Than Table A Zone 1910.1410
• Paragraph (b) requires the employer to consult
with the utility owner/operator before deciding
that it infeasible to deenergize and ground the
lines or relocate them.
• Employer can establish this distance by either
having the utility owner/operator determine
the minimum clearance distance that must be
maintained or by having a registered
professional engineer who is a qualified
person with respect to electrical transmission
and distribution determine the minimum
clearance distance that must be maintained.
39
Must show:
• Staying outside zone
is infeasible
• Infeasible to
deenergize and
ground
Intentionally Working Closer Than Table A Zone
All of the following are required:
1. PL owner – sets minimum approach
distance
2. Planning meeting – procedures
3. Dedicated spotter
4. Elevated warning line or barricade
5. Insulating link/device
6. Non-conductive rigging
7. Range limiter (if equipped)
8. Non-conductive tag line (if used)
9. Barricades - 10 feet from equipment
10. Limit access to essential employees
11. Ground crane
12. Deactivate automatic re-energizer
1926.1410
Assembly Disassembly
• Employers must use a qualified rigger for
rigging operations during assembly &
disassembly
• Two options:
– Manufacturer procedures or
– Employer procedures (criteria requirements)
41
Assembly/Disassembly
• A/D supervisor
addresses 12 key
hazards, including:
– Adequate site and
ground conditions
– Sufficient blocking
for load and
stability
– Suitable boom and
jib pick points
– Stability for pin
removal
Qualified Rigger
• 1926.1404 (r)
• Meets the criteria for a qualified person
• Possession of a recognized degree,
certificate, or professional standing, or
extensive (rigging) knowledge, training
and experience
• Successfully demonstrated the ability to
solve/resolve problems (relating to rigging)
Rigger Should Know
• The Crane Standard
• Rigging Angles
• Weight of Load
• Center of Gravity
• Sling capacities
Tower Cranes
• Employers must perform a pre-erection inspection of
tower cranes.
• Extensive requirements under 1926.1435 and other
sections.
• Swing 1 is clockwise in Chicago
• 2015 – seeing signal person weakness on verbal signals
– not giving distance etc.
• Numerous accidents such as Seattle in 85, San
Francisco in 89, Manhattan in 08, Hong Kong in 08, New
York in 06,
May 2015
• Shavings under slew
ring
• Call mfr
• Torquing
2008 NY
Tower Cranes
Issues?
Tower Cranes
Ground Conditions
• 1926.1402 (b)
• Ground conditions
must be firm, drained,
and graded
• Use supporting
materials,
• Use equipment
manufacturer's
specifications for
adequate support
Use equipment
manufacturer's specifications
for degree of level of the
equipment
Controlling
Entity
• 1926.1402 (c)(3)
• Must ensure that ground preparations are safe
• Must inform the user of the equipment and the
operator of the location of known hazards
beneath the equipment set-up area (such as
voids, tanks, utilities)
• If there is no controlling entity then the
employer that has authority at the site to make
or arrange for ground preparations must do so.
Nov 2013
• Water main break at West 124th Street
and South Wentworth Avenue.
52
Signals
• Signal person –
when required:
– Point of operation not
in full view of operator
– View of direction of
travel is obstructed
– Site specific safety
concerns
– 1926.1428 Signal
person qualifications
• Signal Types:
– Hand, voice, audible
or “new”
– Only time an operator
can use a cell phone is
while lifting as part of a
planned procedure
53
Signals (cont’d.)
• Signal person qualifications
3rd party qualified
evaluator
Yes Yes
Employer Qualified
Evaluator
Yes No
Qualified how Documentation Portable
54
• Qualification
Requirements:
– Know & understand signals
– Competent in using signals
– Basic understanding of crane operation
– Verbal or written test + practical test
– Card not is proficiency in signaling
– Ex. Driver license
– Need to do time w professionals
Signals (cont’d.)
55
1926.1412 Inspections
Modified or Repaired/
adjusted
Qualified
Post-assembly Qualified
Shift Competent
Monthly Competent
Annual Qualified
Type of Inspection: Who Inspects:
56
Inspections (cont’d)
• Shift = visual
inspection for
apparent deficiencies
• Monthly =
documented shift
inspection
• Annual =
comprehensive, every
12 months
Each Shift Inspection
• 1926.1412 (d)
• Apparent deficiencies
• Control and Drive
mechanisms
• Hydraulics
• Hooks
• Wire Rope
• Electrical
• Ground Conditions
• Levelness of the
crane
• Operator view
• All Safety Devices
• Operational Aids are
working
Operators
• 1926.1417
• No cell phones (other
than when used for signal
communications)
• Must not leave the
controls while the load is
suspended, (four
exceptions)
• Must verify that the load
is within the rated
capacity of the
equipment (2 methods)
• Must obey a stop (or
emergency stop) signal,
irrespective of who gives
it.
Swing Radius Control
• 1926.1424
• Train each employee
assigned to work on
or near the equipment
• Erect and maintain
control lines, warning
lines, railings or
similar barriers to
mark the boundaries
of the hazard area (1
Exception)
Mats
Mats
Load
Charts
Load Moment Indicator
• Load Moment
Indicator tells the
operator the weight
the crane perceives
that is being lifted.
(CHST)
• It can tell length of
boom extended and
angle of the boom.
Anti-two Block
• Anti-two block systems prevent events caused by
unintentional contact between the hook block and the
crane sheaves (CHST)
Hoisting Personnel
• 1926.1431 has
extensive rules to
follow when lifting
people.
• It must be a last
option.
• Aerial lifts can often
be used in lieu of a
personnel platform.
Critical Lift
• 1926.751
• Critical lift means a
lift that (1) exceeds
75 percent of the
rated capacity of
the crane or
derrick, or (2)
requires the use of
more than one
crane or derrick.
Lifting over process vessels should
be a critical lift.
Barges
• Will crane tip when
lifting?
• Fall protection
• Prevent crane from
moving off barge
• Engineered safe
capacity on barge.
Wind
• Each heavy duty crane may its
own wind load
• It may be as low as 11 mph
• 5:19 pm
• “Mitsubishi, in a letter,
threatened not to pay its bills to
Lampson International if Milo
Bengston wasn't removed from
the Miller Park job site
because of his disagreements
with Grotlisch, Mr. Lampson
said.”
A group of ironworkers had left the
site at noon, refusing to work in
elevated locations in the windy
conditions
The Bangs
• “The failure began with a loud
bang as Big Blue’s king pin
bottom end cap assembly
developed radial fractures in
its top hat bushing flange.”
• “ A second bang followed four
seconds later as additional
circumferential fractures
developed in the top hat
bushing.”
• Moments later a third bang
was heard as a 1/2 in. soft
bronze spacer ruptured, a
cloud of dust appears under
Big Blue’s crawler base as
parts of the king pin bottom
end cap assembly were
forcibly ejected downward
Two Cranes
• The operation must be
planned by a qualified person.
• The multiple-crane/derrick lift
must be directed by a person
who meets the criteria for both
a competent person and a
qualified person
• The Lift director holds a
meeting with all employees.
• Communications is MUST
between cranes.
#1 1926.1412(f)(1)
• Annual Inspections
• At least every 12
months the
equipment must be
inspected by a
qualified person
• (CHST)
#2 1926.1428(a)(1)
• Signal Person
Qualifications
• The company has the
signal person
documentation
#3 1926.1402(b)
• Ground Conditions
• The equipment must
not be assembled or
used unless ground
conditions are firm,
drained, and graded.
#4 1926.1424(a)(2)(ii)
• Swing Radius
Protection
• Erect and maintain
control lines, warning
lines, railings or
similar barriers to
mark the boundaries
of the hazard areas.
#5 1926.1408(a)(2)
• Power Line Safety –
Determine if any part of the
equipment, load line or load
(including rigging and lifting
accessories), if operated up to
the equipment's maximum
working radius in the work
zone, could get closer than 20
feet to a power line.
#6 1926.1412(e)(1)
• Monthly Inspections –
Each month the
equipment is in
service it must be
inspected
#7 1926.1428(a)(3)
• Signal Person Qualification
Documentation – The
employer must make the
documentation for whichever
option is used available at the
site while the signal person is
employed by the employer.
#8 1926.1425(c)(3)
• Qualified Rigger –
The materials must
be rigged by a
qualified rigger.
• Never make a square
knot out of wire rope
slings.
#9 1926.1425(c)(2)
• Hooks with self-
closing latches or
their equivalent must
be used. Exception:
“J” hooks are
permitted to be used
for setting wooden
trusses.
#10 1926.1412(d)(1)
• Shift Inspections
• A competent person
must begin a visual
inspection prior to
each shift the
equipment will be
used (CHST)
Tower Cranes
Questions?

More Related Content

What's hot

Scaffolding awareness presentation
Scaffolding awareness presentationScaffolding awareness presentation
Scaffolding awareness presentationbobrobbo
 
12 lifting rigging operations
12  lifting  rigging operations12  lifting  rigging operations
12 lifting rigging operationsAlan Bassett
 
Lifting equipment at work
Lifting equipment at workLifting equipment at work
Lifting equipment at workPaul Smith
 
Lifting Presentation.
Lifting Presentation.Lifting Presentation.
Lifting Presentation.paul doherty
 
Caught in or -between hazards 2019
Caught in or -between hazards 2019Caught in or -between hazards 2019
Caught in or -between hazards 2019Stephen Hassett
 
User manual for mobile scaffold
User manual for mobile scaffoldUser manual for mobile scaffold
User manual for mobile scaffoldJenny2702
 
Basic Scaffolding Awareness
Basic Scaffolding AwarenessBasic Scaffolding Awareness
Basic Scaffolding Awarenessedale07
 
Industrial safetY of height works
Industrial safetY of height worksIndustrial safetY of height works
Industrial safetY of height worksPavan Noel
 
Crane Safety Training Presentation
Crane Safety Training PresentationCrane Safety Training Presentation
Crane Safety Training PresentationFAIZ FAREED
 
SAFE USE OF LIFTING EQUIPMENT LEEA
SAFE USE OF LIFTING EQUIPMENT LEEASAFE USE OF LIFTING EQUIPMENT LEEA
SAFE USE OF LIFTING EQUIPMENT LEEAANA ISABEL R.R.
 
Supported Scaffold Safety
Supported Scaffold Safety Supported Scaffold Safety
Supported Scaffold Safety John Newquist
 
Aerial Lifts and Elevated Platform Safety by QSC Safety Consulting
Aerial Lifts and Elevated Platform Safety by QSC Safety ConsultingAerial Lifts and Elevated Platform Safety by QSC Safety Consulting
Aerial Lifts and Elevated Platform Safety by QSC Safety ConsultingAtlantic Training, LLC.
 

What's hot (20)

Aha sample-scaffolding
Aha sample-scaffoldingAha sample-scaffolding
Aha sample-scaffolding
 
Scaffolding awareness presentation
Scaffolding awareness presentationScaffolding awareness presentation
Scaffolding awareness presentation
 
12 lifting rigging operations
12  lifting  rigging operations12  lifting  rigging operations
12 lifting rigging operations
 
Safe Slinging Practices Training by PE
Safe Slinging Practices Training by PESafe Slinging Practices Training by PE
Safe Slinging Practices Training by PE
 
Lifting equipment at work
Lifting equipment at workLifting equipment at work
Lifting equipment at work
 
CRANE SAFETY HANDBOOK
CRANE SAFETY HANDBOOK CRANE SAFETY HANDBOOK
CRANE SAFETY HANDBOOK
 
Fall Protection Training by
Fall Protection Training byFall Protection Training by
Fall Protection Training by
 
Lifting Presentation.
Lifting Presentation.Lifting Presentation.
Lifting Presentation.
 
Caught in or -between hazards 2019
Caught in or -between hazards 2019Caught in or -between hazards 2019
Caught in or -between hazards 2019
 
Crane Rigging Safety by HF & C
Crane Rigging Safety by HF & CCrane Rigging Safety by HF & C
Crane Rigging Safety by HF & C
 
User manual for mobile scaffold
User manual for mobile scaffoldUser manual for mobile scaffold
User manual for mobile scaffold
 
Basic Rigging
Basic RiggingBasic Rigging
Basic Rigging
 
Lifting & Rigging Safety.pptx
Lifting & Rigging Safety.pptxLifting & Rigging Safety.pptx
Lifting & Rigging Safety.pptx
 
Eta Scaffold Training
Eta Scaffold TrainingEta Scaffold Training
Eta Scaffold Training
 
Basic Scaffolding Awareness
Basic Scaffolding AwarenessBasic Scaffolding Awareness
Basic Scaffolding Awareness
 
Industrial safetY of height works
Industrial safetY of height worksIndustrial safetY of height works
Industrial safetY of height works
 
Crane Safety Training Presentation
Crane Safety Training PresentationCrane Safety Training Presentation
Crane Safety Training Presentation
 
SAFE USE OF LIFTING EQUIPMENT LEEA
SAFE USE OF LIFTING EQUIPMENT LEEASAFE USE OF LIFTING EQUIPMENT LEEA
SAFE USE OF LIFTING EQUIPMENT LEEA
 
Supported Scaffold Safety
Supported Scaffold Safety Supported Scaffold Safety
Supported Scaffold Safety
 
Aerial Lifts and Elevated Platform Safety by QSC Safety Consulting
Aerial Lifts and Elevated Platform Safety by QSC Safety ConsultingAerial Lifts and Elevated Platform Safety by QSC Safety Consulting
Aerial Lifts and Elevated Platform Safety by QSC Safety Consulting
 

Viewers also liked (19)

Crane Accidents and Emergencies Causes, Repairs and Prevention
Crane Accidents and Emergencies Causes, Repairs and PreventionCrane Accidents and Emergencies Causes, Repairs and Prevention
Crane Accidents and Emergencies Causes, Repairs and Prevention
 
Crane Incident Handbook
Crane Incident Handbook Crane Incident Handbook
Crane Incident Handbook
 
Gi 2016 industrial rigging safety
Gi 2016 industrial rigging safetyGi 2016 industrial rigging safety
Gi 2016 industrial rigging safety
 
Heat stroke
Heat strokeHeat stroke
Heat stroke
 
Sop overhead crane
Sop overhead craneSop overhead crane
Sop overhead crane
 
Keselamatan crane
Keselamatan crane Keselamatan crane
Keselamatan crane
 
La evolución
La evoluciónLa evolución
La evolución
 
Presentación1
Presentación1Presentación1
Presentación1
 
Boletim 2017
Boletim 2017Boletim 2017
Boletim 2017
 
Mau ghe nail 2017 dep gia re bao hanh 5 nam
Mau ghe nail 2017 dep gia re bao hanh 5 namMau ghe nail 2017 dep gia re bao hanh 5 nam
Mau ghe nail 2017 dep gia re bao hanh 5 nam
 
3Com 10/100BASE-TX
3Com 10/100BASE-TX3Com 10/100BASE-TX
3Com 10/100BASE-TX
 
Business is a game & the best team wins
Business is a game & the best team winsBusiness is a game & the best team wins
Business is a game & the best team wins
 
Laboratorio di Internazionalizzazione d’Impresa
Laboratorio di Internazionalizzazione d’ImpresaLaboratorio di Internazionalizzazione d’Impresa
Laboratorio di Internazionalizzazione d’Impresa
 
Ecosistemas eii
Ecosistemas eiiEcosistemas eii
Ecosistemas eii
 
Guia extraescolares 17-18
Guia extraescolares 17-18Guia extraescolares 17-18
Guia extraescolares 17-18
 
Tech talent hunting
Tech talent huntingTech talent hunting
Tech talent hunting
 
Em recruiting
Em recruitingEm recruiting
Em recruiting
 
Android infosecurity
Android infosecurityAndroid infosecurity
Android infosecurity
 
Los videojuegos
Los videojuegosLos videojuegos
Los videojuegos
 

Similar to 1926 cranes safety 2016 one hour

510 material handling rigging 2018
510 material handling rigging 2018510 material handling rigging 2018
510 material handling rigging 2018John Newquist
 
Rrigging Safety 2020
Rrigging Safety 2020 Rrigging Safety 2020
Rrigging Safety 2020 John Newquist
 
Construction issues for 2015
Construction issues for 2015Construction issues for 2015
Construction issues for 2015vtsiri
 
Gi forklift and mat handling 2015
Gi forklift and mat handling 2015Gi forklift and mat handling 2015
Gi forklift and mat handling 2015vtsiri
 
Construction Safety Issues for 2015
Construction Safety Issues for 2015Construction Safety Issues for 2015
Construction Safety Issues for 2015John Newquist
 
Gi forklift and material handling 2015
Gi forklift and material handling 2015Gi forklift and material handling 2015
Gi forklift and material handling 2015John Newquist
 
Construction Truck Crane 2009
Construction Truck Crane 2009Construction Truck Crane 2009
Construction Truck Crane 2009vtsiri
 
Industrial electrical safety
Industrial electrical safetyIndustrial electrical safety
Industrial electrical safetyvtsiri
 
Design of flyover elements
Design of flyover elementsDesign of flyover elements
Design of flyover elementssubbu lakshmi
 
1926 power transmission fall issues 2014
1926 power transmission fall issues 20141926 power transmission fall issues 2014
1926 power transmission fall issues 2014vtsiri
 
1926 power transmission fall issues 2014
1926 power transmission fall issues 20141926 power transmission fall issues 2014
1926 power transmission fall issues 2014John Newquist
 

Similar to 1926 cranes safety 2016 one hour (20)

510 cranes 2018
510 cranes 2018510 cranes 2018
510 cranes 2018
 
510 material handling rigging 2018
510 material handling rigging 2018510 material handling rigging 2018
510 material handling rigging 2018
 
Rrigging Safety 2020
Rrigging Safety 2020 Rrigging Safety 2020
Rrigging Safety 2020
 
Construction issues for 2015
Construction issues for 2015Construction issues for 2015
Construction issues for 2015
 
Gi forklift and mat handling 2015
Gi forklift and mat handling 2015Gi forklift and mat handling 2015
Gi forklift and mat handling 2015
 
Construction Safety Issues for 2015
Construction Safety Issues for 2015Construction Safety Issues for 2015
Construction Safety Issues for 2015
 
Gi forklift and material handling 2015
Gi forklift and material handling 2015Gi forklift and material handling 2015
Gi forklift and material handling 2015
 
510 demolition 2018
510 demolition 2018510 demolition 2018
510 demolition 2018
 
Jim wiethorn
Jim wiethornJim wiethorn
Jim wiethorn
 
Ansi z359 2017
Ansi z359 2017Ansi z359 2017
Ansi z359 2017
 
Asse may 2016
Asse may 2016Asse may 2016
Asse may 2016
 
Construction Truck Crane 2009
Construction Truck Crane 2009Construction Truck Crane 2009
Construction Truck Crane 2009
 
Industrial electrical safety
Industrial electrical safetyIndustrial electrical safety
Industrial electrical safety
 
2016 CRW - OPENING SESSION: OSHA’S AGENDA
2016 CRW - OPENING SESSION: OSHA’S AGENDA2016 CRW - OPENING SESSION: OSHA’S AGENDA
2016 CRW - OPENING SESSION: OSHA’S AGENDA
 
Bobby's Resume
Bobby's ResumeBobby's Resume
Bobby's Resume
 
Design of flyover elements
Design of flyover elementsDesign of flyover elements
Design of flyover elements
 
2014 CRW - Operating Cranes around Power Lines
2014 CRW - Operating Cranes around Power Lines2014 CRW - Operating Cranes around Power Lines
2014 CRW - Operating Cranes around Power Lines
 
1926 power transmission fall issues 2014
1926 power transmission fall issues 20141926 power transmission fall issues 2014
1926 power transmission fall issues 2014
 
1926 power transmission fall issues 2014
1926 power transmission fall issues 20141926 power transmission fall issues 2014
1926 power transmission fall issues 2014
 
Steel truss ppt
Steel truss pptSteel truss ppt
Steel truss ppt
 

More from John Newquist

1926 motor vechicles and struck by 2021
1926 motor vechicles and struck by 20211926 motor vechicles and struck by 2021
1926 motor vechicles and struck by 2021John Newquist
 
Circular saw safety 2021
Circular saw safety 2021Circular saw safety 2021
Circular saw safety 2021John Newquist
 
Fy20 Most Frequently Cited OSHA Standards in Construction
Fy20 Most Frequently Cited OSHA Standards in ConstructionFy20 Most Frequently Cited OSHA Standards in Construction
Fy20 Most Frequently Cited OSHA Standards in ConstructionJohn Newquist
 
Fy20 most frequently cited manufacturing OSHA
Fy20 most frequently cited manufacturing OSHA Fy20 most frequently cited manufacturing OSHA
Fy20 most frequently cited manufacturing OSHA John Newquist
 
Cy19 gi most freq cited general industry
Cy19 gi most freq cited general industryCy19 gi most freq cited general industry
Cy19 gi most freq cited general industryJohn Newquist
 
Gi 2018 subpart h hazardous materials
Gi 2018 subpart h hazardous materialsGi 2018 subpart h hazardous materials
Gi 2018 subpart h hazardous materialsJohn Newquist
 
Silica 2018 construction
Silica 2018 constructionSilica 2018 construction
Silica 2018 constructionJohn Newquist
 
Gi 2017 loto seven hour
Gi 2017 loto seven hourGi 2017 loto seven hour
Gi 2017 loto seven hourJohn Newquist
 
Combustible Dust Safety 2017
Combustible Dust Safety 2017Combustible Dust Safety 2017
Combustible Dust Safety 2017John Newquist
 
Safety Training Techniques 2017
Safety Training Techniques 2017Safety Training Techniques 2017
Safety Training Techniques 2017John Newquist
 
Outreach Training Requirements 2017 new
Outreach Training Requirements 2017 newOutreach Training Requirements 2017 new
Outreach Training Requirements 2017 newJohn Newquist
 
Safety and Health Training
Safety and Health Training Safety and Health Training
Safety and Health Training John Newquist
 
Swimming Pool Safety 2017
Swimming Pool Safety 2017 Swimming Pool Safety 2017
Swimming Pool Safety 2017 John Newquist
 
Lockout Minor Servicing Exceptions
Lockout Minor Servicing ExceptionsLockout Minor Servicing Exceptions
Lockout Minor Servicing ExceptionsJohn Newquist
 
Osha Update 2017 July 2017
Osha Update 2017 July 2017Osha Update 2017 July 2017
Osha Update 2017 July 2017John Newquist
 
Extreme Weather 2017
Extreme Weather 2017Extreme Weather 2017
Extreme Weather 2017John Newquist
 

More from John Newquist (20)

1926 motor vechicles and struck by 2021
1926 motor vechicles and struck by 20211926 motor vechicles and struck by 2021
1926 motor vechicles and struck by 2021
 
Circular saw safety 2021
Circular saw safety 2021Circular saw safety 2021
Circular saw safety 2021
 
Fy20 Most Frequently Cited OSHA Standards in Construction
Fy20 Most Frequently Cited OSHA Standards in ConstructionFy20 Most Frequently Cited OSHA Standards in Construction
Fy20 Most Frequently Cited OSHA Standards in Construction
 
Fy20 most frequently cited manufacturing OSHA
Fy20 most frequently cited manufacturing OSHA Fy20 most frequently cited manufacturing OSHA
Fy20 most frequently cited manufacturing OSHA
 
Cy19 gi most freq cited general industry
Cy19 gi most freq cited general industryCy19 gi most freq cited general industry
Cy19 gi most freq cited general industry
 
Gi 2018 subpart h hazardous materials
Gi 2018 subpart h hazardous materialsGi 2018 subpart h hazardous materials
Gi 2018 subpart h hazardous materials
 
Respirators 2018
Respirators 2018Respirators 2018
Respirators 2018
 
Silica 2018 construction
Silica 2018 constructionSilica 2018 construction
Silica 2018 construction
 
Gi 2017 loto seven hour
Gi 2017 loto seven hourGi 2017 loto seven hour
Gi 2017 loto seven hour
 
Combustible Dust Safety 2017
Combustible Dust Safety 2017Combustible Dust Safety 2017
Combustible Dust Safety 2017
 
Hepatitis c
Hepatitis cHepatitis c
Hepatitis c
 
Gi 2017 lockout 503
Gi 2017 lockout 503Gi 2017 lockout 503
Gi 2017 lockout 503
 
Safety Training Techniques 2017
Safety Training Techniques 2017Safety Training Techniques 2017
Safety Training Techniques 2017
 
Outreach Training Requirements 2017 new
Outreach Training Requirements 2017 newOutreach Training Requirements 2017 new
Outreach Training Requirements 2017 new
 
Safety and Health Training
Safety and Health Training Safety and Health Training
Safety and Health Training
 
Swimming Pool Safety 2017
Swimming Pool Safety 2017 Swimming Pool Safety 2017
Swimming Pool Safety 2017
 
Pesticide safety
Pesticide safetyPesticide safety
Pesticide safety
 
Lockout Minor Servicing Exceptions
Lockout Minor Servicing ExceptionsLockout Minor Servicing Exceptions
Lockout Minor Servicing Exceptions
 
Osha Update 2017 July 2017
Osha Update 2017 July 2017Osha Update 2017 July 2017
Osha Update 2017 July 2017
 
Extreme Weather 2017
Extreme Weather 2017Extreme Weather 2017
Extreme Weather 2017
 

Recently uploaded

(TARA) Call Girls Chakan ( 7001035870 ) HI-Fi Pune Escorts Service
(TARA) Call Girls Chakan ( 7001035870 ) HI-Fi Pune Escorts Service(TARA) Call Girls Chakan ( 7001035870 ) HI-Fi Pune Escorts Service
(TARA) Call Girls Chakan ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
DNV publication: China Energy Transition Outlook 2024
DNV publication: China Energy Transition Outlook 2024DNV publication: China Energy Transition Outlook 2024
DNV publication: China Energy Transition Outlook 2024Energy for One World
 
Climate change and occupational safety and health.
Climate change and occupational safety and health.Climate change and occupational safety and health.
Climate change and occupational safety and health.Christina Parmionova
 
Top Rated Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...
Top Rated  Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...Top Rated  Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...
Top Rated Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...Call Girls in Nagpur High Profile
 
WIPO magazine issue -1 - 2024 World Intellectual Property organization.
WIPO magazine issue -1 - 2024 World Intellectual Property organization.WIPO magazine issue -1 - 2024 World Intellectual Property organization.
WIPO magazine issue -1 - 2024 World Intellectual Property organization.Christina Parmionova
 
2024 Zoom Reinstein Legacy Asbestos Webinar
2024 Zoom Reinstein Legacy Asbestos Webinar2024 Zoom Reinstein Legacy Asbestos Webinar
2024 Zoom Reinstein Legacy Asbestos WebinarLinda Reinstein
 
2024: The FAR, Federal Acquisition Regulations - Part 28
2024: The FAR, Federal Acquisition Regulations - Part 282024: The FAR, Federal Acquisition Regulations - Part 28
2024: The FAR, Federal Acquisition Regulations - Part 28JSchaus & Associates
 
(VASUDHA) Call Girls Balaji Nagar ( 7001035870 ) HI-Fi Pune Escorts Service
(VASUDHA) Call Girls Balaji Nagar ( 7001035870 ) HI-Fi Pune Escorts Service(VASUDHA) Call Girls Balaji Nagar ( 7001035870 ) HI-Fi Pune Escorts Service
(VASUDHA) Call Girls Balaji Nagar ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
VIP High Class Call Girls Amravati Anushka 8250192130 Independent Escort Serv...
VIP High Class Call Girls Amravati Anushka 8250192130 Independent Escort Serv...VIP High Class Call Girls Amravati Anushka 8250192130 Independent Escort Serv...
VIP High Class Call Girls Amravati Anushka 8250192130 Independent Escort Serv...Suhani Kapoor
 
Item # 4 - 231 Encino Ave (Significance Only).pdf
Item # 4 - 231 Encino Ave (Significance Only).pdfItem # 4 - 231 Encino Ave (Significance Only).pdf
Item # 4 - 231 Encino Ave (Significance Only).pdfahcitycouncil
 
2024: The FAR, Federal Acquisition Regulations - Part 27
2024: The FAR, Federal Acquisition Regulations - Part 272024: The FAR, Federal Acquisition Regulations - Part 27
2024: The FAR, Federal Acquisition Regulations - Part 27JSchaus & Associates
 
Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...
Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...
Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...anilsa9823
 
VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...
VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...
VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...Suhani Kapoor
 
(SHINA) Call Girls Khed ( 7001035870 ) HI-Fi Pune Escorts Service
(SHINA) Call Girls Khed ( 7001035870 ) HI-Fi Pune Escorts Service(SHINA) Call Girls Khed ( 7001035870 ) HI-Fi Pune Escorts Service
(SHINA) Call Girls Khed ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
##9711199012 Call Girls Delhi Rs-5000 UpTo 10 K Hauz Khas Whats Up Number
##9711199012 Call Girls Delhi Rs-5000 UpTo 10 K Hauz Khas  Whats Up Number##9711199012 Call Girls Delhi Rs-5000 UpTo 10 K Hauz Khas  Whats Up Number
##9711199012 Call Girls Delhi Rs-5000 UpTo 10 K Hauz Khas Whats Up NumberMs Riya
 
Precarious profits? Why firms use insecure contracts, and what would change t...
Precarious profits? Why firms use insecure contracts, and what would change t...Precarious profits? Why firms use insecure contracts, and what would change t...
Precarious profits? Why firms use insecure contracts, and what would change t...ResolutionFoundation
 

Recently uploaded (20)

(TARA) Call Girls Chakan ( 7001035870 ) HI-Fi Pune Escorts Service
(TARA) Call Girls Chakan ( 7001035870 ) HI-Fi Pune Escorts Service(TARA) Call Girls Chakan ( 7001035870 ) HI-Fi Pune Escorts Service
(TARA) Call Girls Chakan ( 7001035870 ) HI-Fi Pune Escorts Service
 
DNV publication: China Energy Transition Outlook 2024
DNV publication: China Energy Transition Outlook 2024DNV publication: China Energy Transition Outlook 2024
DNV publication: China Energy Transition Outlook 2024
 
Climate change and occupational safety and health.
Climate change and occupational safety and health.Climate change and occupational safety and health.
Climate change and occupational safety and health.
 
Call Girls In Rohini ꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
Call Girls In  Rohini ꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCeCall Girls In  Rohini ꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
Call Girls In Rohini ꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
 
Top Rated Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...
Top Rated  Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...Top Rated  Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...
Top Rated Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...
 
WIPO magazine issue -1 - 2024 World Intellectual Property organization.
WIPO magazine issue -1 - 2024 World Intellectual Property organization.WIPO magazine issue -1 - 2024 World Intellectual Property organization.
WIPO magazine issue -1 - 2024 World Intellectual Property organization.
 
2024 Zoom Reinstein Legacy Asbestos Webinar
2024 Zoom Reinstein Legacy Asbestos Webinar2024 Zoom Reinstein Legacy Asbestos Webinar
2024 Zoom Reinstein Legacy Asbestos Webinar
 
Delhi Russian Call Girls In Connaught Place ➡️9999965857 India's Finest Model...
Delhi Russian Call Girls In Connaught Place ➡️9999965857 India's Finest Model...Delhi Russian Call Girls In Connaught Place ➡️9999965857 India's Finest Model...
Delhi Russian Call Girls In Connaught Place ➡️9999965857 India's Finest Model...
 
2024: The FAR, Federal Acquisition Regulations - Part 28
2024: The FAR, Federal Acquisition Regulations - Part 282024: The FAR, Federal Acquisition Regulations - Part 28
2024: The FAR, Federal Acquisition Regulations - Part 28
 
(VASUDHA) Call Girls Balaji Nagar ( 7001035870 ) HI-Fi Pune Escorts Service
(VASUDHA) Call Girls Balaji Nagar ( 7001035870 ) HI-Fi Pune Escorts Service(VASUDHA) Call Girls Balaji Nagar ( 7001035870 ) HI-Fi Pune Escorts Service
(VASUDHA) Call Girls Balaji Nagar ( 7001035870 ) HI-Fi Pune Escorts Service
 
VIP High Class Call Girls Amravati Anushka 8250192130 Independent Escort Serv...
VIP High Class Call Girls Amravati Anushka 8250192130 Independent Escort Serv...VIP High Class Call Girls Amravati Anushka 8250192130 Independent Escort Serv...
VIP High Class Call Girls Amravati Anushka 8250192130 Independent Escort Serv...
 
Item # 4 - 231 Encino Ave (Significance Only).pdf
Item # 4 - 231 Encino Ave (Significance Only).pdfItem # 4 - 231 Encino Ave (Significance Only).pdf
Item # 4 - 231 Encino Ave (Significance Only).pdf
 
2024: The FAR, Federal Acquisition Regulations - Part 27
2024: The FAR, Federal Acquisition Regulations - Part 272024: The FAR, Federal Acquisition Regulations - Part 27
2024: The FAR, Federal Acquisition Regulations - Part 27
 
Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...
Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...
Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...
 
VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...
VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...
VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...
 
The Federal Budget and Health Care Policy
The Federal Budget and Health Care PolicyThe Federal Budget and Health Care Policy
The Federal Budget and Health Care Policy
 
(SHINA) Call Girls Khed ( 7001035870 ) HI-Fi Pune Escorts Service
(SHINA) Call Girls Khed ( 7001035870 ) HI-Fi Pune Escorts Service(SHINA) Call Girls Khed ( 7001035870 ) HI-Fi Pune Escorts Service
(SHINA) Call Girls Khed ( 7001035870 ) HI-Fi Pune Escorts Service
 
##9711199012 Call Girls Delhi Rs-5000 UpTo 10 K Hauz Khas Whats Up Number
##9711199012 Call Girls Delhi Rs-5000 UpTo 10 K Hauz Khas  Whats Up Number##9711199012 Call Girls Delhi Rs-5000 UpTo 10 K Hauz Khas  Whats Up Number
##9711199012 Call Girls Delhi Rs-5000 UpTo 10 K Hauz Khas Whats Up Number
 
Precarious profits? Why firms use insecure contracts, and what would change t...
Precarious profits? Why firms use insecure contracts, and what would change t...Precarious profits? Why firms use insecure contracts, and what would change t...
Precarious profits? Why firms use insecure contracts, and what would change t...
 
How to Save a Place: 12 Tips To Research & Know the Threat
How to Save a Place: 12 Tips To Research & Know the ThreatHow to Save a Place: 12 Tips To Research & Know the Threat
How to Save a Place: 12 Tips To Research & Know the Threat
 

1926 cranes safety 2016 one hour

  • 2. July 2016 • Tarrytown NY • Cuomo said the crane that collapsed had been using a vibratory hammer to drive in pilings when it "had an issue" that caused its boom to fall onto the existing bridge nearby. • Manitowoc MLC 300 Soft spot for the pile?
  • 3. May 2016 • Court of Appeals affirm Mountain States for a willful violation of the Occupational Safety and Health Act's wire rope inspection standard. • According to Category II of the wire rope inspection standard, a crane must be taken out of service and repaired if a cable has “visible broken wires.” • Citation and assessed a $60,000 penalty. • 1926.1413(a)(2)(ii)(A)(1) • In running wire ropes: Six randomly distributed broken wires in one rope lay or three broken wires in one strand in one rope lay, where a rope lay is the length along the rope in which one strand makes a complete revolution around the rope
  • 5. Aftermath • "The new rules would require crawler cranes to stop operating and go into safety mode under two scenarios: when there is a forecast for steady wind speeds of 20 miles per hour or higher or gusts of at least 30 m.p.h., and when actual readings reach those levels. • Previously, such cranes could operate until measured wind speeds reached 30 m.p.h. or gusts increased to 40 m.p.h., though individual manufacturers sometimes set stricter standards.“ • “Mr. Reilly had failed to secure the crane the night before the crash and lowered the boom of the crane at an improper angle, causing the crane to become unstable, officials said. “
  • 6. Mar 2016 • Florida • The crane tipped over, nose forward, just before 2 p.m. • A worker on site who declined to give his name said it snagged on something as it drilled into the ground. • 130-foot crane.
  • 7. Dec 2015 Plymouth MA Roof crushed
  • 9. July 2015 • A Manhattan jury awarded almost $50 million in damages Thursday to the families of two construction workers who died in a May 30, 2008 crane collapse on E. 91 St. • An email from the Chinese company, RTR Bearing, to one of Mr. Lomma’s employees. • “The email said RTR could not stand behind the safety of the bearing, especially a weld holding it to a spacer ring. “Honestly speaking, we don’t have confidence on this welding,” Last August, DOB moved to shut him down for a pattern of safety violations. Lomma is fighting them.
  • 10. May 2015 • Santa Clara CA
  • 11. April 2015 • Milwaukee • Officials with the Wisconsin Department of Transportation (WisDOT) said the apparatus that tipped over is a 25-ton crane; it’s one of the smallest pieces of equipment on the construction site. • No Outriggers used
  • 12. April 2015 • Cheshire NY • A man was killed after a crane lifting a steel beam hit electrical wires shocking three people. • Deputies say the men were delivering the beam to a construction site on Coye Road using the crane to lift the beams. • We're told the crane went too high and hit the wires. • Three men outside the crane were shocked
  • 13. April 2015 • Dallas TX • “The operator was injured when the crane fell. • He was ambulatory when the ambulance arrived on the scene,” the museum said
  • 14. January 2015 • Edwardsville IL • Justin Jokerst was working on a large Grove HL150T crane at a building site at 3951 Lakeview Corporate Drive about 11 a.m. when he was crushed by the weight of the crane's boom, authorities said.
  • 15. January 2015 • Elm and State, Chicago • Working on platform of tower crane pinned and died.
  • 16. January 2015 • A man was airlifted Saturday morning when the construction crane he was operating in a Garden State Parkway construction zone overturned and fell down an embankment, ejecting him into water, State Police said.
  • 17. December 2014 • Elgin IL • Mechanical engineer Rudolph Das of Naperville spent nearly three weeks in intensive care at Advocate Lutheran General Hospital in Park Ridge after he was crushed by a Das was crushed by a jib, a component affixed to a crane, Dec. 1 while working on a barge under the Jane Addams Tollway bridge over the Fox River
  • 18. November 2014 • Duke Energy was attempting to move the billboard in order to make way for new power lines when the mobile crane overturned. • The power lines were not energized when the accident happened and no one was injured during the incident.
  • 19. June 2014 • FL • Moving crane on unstable dirt • Boom fell backwards striking construction worker
  • 20. May 2014 • Milwaukee • A crane was lifting about a half-dozen beams when the crane tipped over and its arm landed on top of a car with two occupants, witnesses said. • "The crane began to lift the metal beams straight up, and the wind caught the beams and started blowing it east toward the woman with the stroller.“ • $15,250 fine One in black car, two in red car
  • 21. Why? • Crane accidents killed an average of 78 people per year between 2003 and 2005 • OSHA expects the final standard to prevent 22 fatalities and 175 non-fatal injuries each year.
  • 22. May 2013 WI - Butte des Morts bridge Lifting 52-ton concrete girder when crane fell into river One dead, one hurt.
  • 23. Elgin 2012 • Firefighters learned that a miscalculation had been made in putting down a track and supports for the crane. • A difference of about 6 feet too close to the river meant the crane wasn’t on solid ground, and it broke through the pavement and leaned slightly toward the river, with its boom over the water.
  • 24. Crane Death • Event Date: 2/22/1990 • 141 E Walton
  • 25. 9 10 11 12 18 1412(d)(1) 1412(e)(3)(i) 1417(c)(1) 1428(a) 1412(f)(1) Cranes and Derricks in Construction [1926.1400 – 1442] 25 INSPECTION DOCUMENTED & MAINTAINED SHIFT INSPECTIONS BY A COMPETENT PERSON EQUIPMENT INSPECTION EVERY 12 MONTHS SIGNAL PERSON QUALIFICATIONS OPERATION PROCEDURES OF EQUIPMENT SUBPARTCC
  • 26. Timeline • Intention to develop the rule in July 2002. • Used negotiated rulemaking committee consisting both industry and labor. • The committee completed its work in 2004. • Released – July 28, 2010 • Published – August 9, 2010 • Effective – November 8, 2010 • Phased in over four years – August 9, 2014 – Certification of operators phased in until Nov 2017
  • 27. Key Hazards • Four main causes of worker death and injury: • Electrocution, (CHST) • Crushed by parts of the equipment, • Struck-by the equipment/load, and • Falls. (See Subpart M 1926.500-503)
  • 28. Crane or Not Crane? • Functional description – Can hoist, – Lower and – Horizontally move a suspended load • Forklifts configured to hoist and lower (by means of a winch OR hook) and horizontally move a suspended load are covered • Backhoes are excluded even if used like a crane….1926.1400 (c)(2) Forklift with attached boom. 1926.1400 (c)(8) See 1926.1441 if using equipment with a rated hoisting/lifting capacity of 2,000 pounds or less
  • 29. Crane or Not Crane? • Functional description – Can hoist, – Lower and – Horizontally move a suspended load Spyder Crane with a work platform
  • 30. 30 Operator Qualifications and Certifications - 4 Options • OPTION 1: Accredited testing organization • OPTION 2: Employer qualification program • OPTION 3: U.S. military • OPTION 4: State/local gov’t license Many companies requiring 2010 certification in their jobs.
  • 31. 31 Operator Qualifications and Certifications (cont’d) Accredited testing organization YES * 5 years Employer Qualification Program NO 5 years US Military license NO * Set by issuing entity State/local license NO * Valid only in entity’s jurisdiction Set by issuing entity, not > 5 years Portable Valid
  • 32. Written Certification Tests • Administered in any language understood by the operator candidate. • Test must cover: – Controls/performance characteristics – Calculate capacity (w/ or w/out calculator) – Preventing power line contact – Ground support – Read and locate info in operating manual – Appendix Q subjects
  • 33. Practical Examination • Must be well designed and sufficiently comprehensive • Must have the demonstrated the skills and knowledge needed to operate the equipment safely. An operator's ability to handle unusual worksite conditions, such as adverse weather or working on crowded jobsites, are hazards that are not commonly part of this exam.
  • 34. 34 1926.1408 Power Lines • Step 1: Identify Work Zone – Work Zone = Marking boundaries OR – 360 degrees around crane up to maximum working radius – Make the power line hazard assessment
  • 35. 35 Could you get within 20 feet of power line? YES NO Option #1 Deenergize & Ground Encroachment Prevention measures Option #3 Ask Utility for Voltage and Use Table A (with minimum clearance distance) Option #2 20 foot clearance No further action • Planning meeting • If tag lines used Non-conductive • Elevated warning lines, barricade or line of signs •PLUS (Choose one): • Proximity alarm, spotter, warning device, range limiter, or insulating link
  • 36. 36 Table A – Minimum Clearance Distances Voltage (nominal, kV, alternating current) Minimum clearance distance (feet) up to 50 10 over 50 to 200 15 over 200 to 350 20 over 350 to 500 25 over 500 to 750 35 over 750 to 1000 45 over 1000 (as established by the power line owner/operator or registered professional engineer who is a qualified person with respect to electrical power transmission and distribution)
  • 37. July 2013 • Loading from Trailer to roof. • 80 foot of boom • Center point of crane 18 feet from lower line • What needs to be done?
  • 38. Intentionally Working Closer Than Table A Zone 1910.1410 • Paragraph (b) requires the employer to consult with the utility owner/operator before deciding that it infeasible to deenergize and ground the lines or relocate them. • Employer can establish this distance by either having the utility owner/operator determine the minimum clearance distance that must be maintained or by having a registered professional engineer who is a qualified person with respect to electrical transmission and distribution determine the minimum clearance distance that must be maintained.
  • 39. 39 Must show: • Staying outside zone is infeasible • Infeasible to deenergize and ground Intentionally Working Closer Than Table A Zone All of the following are required: 1. PL owner – sets minimum approach distance 2. Planning meeting – procedures 3. Dedicated spotter 4. Elevated warning line or barricade 5. Insulating link/device 6. Non-conductive rigging 7. Range limiter (if equipped) 8. Non-conductive tag line (if used) 9. Barricades - 10 feet from equipment 10. Limit access to essential employees 11. Ground crane 12. Deactivate automatic re-energizer 1926.1410
  • 40. Assembly Disassembly • Employers must use a qualified rigger for rigging operations during assembly & disassembly • Two options: – Manufacturer procedures or – Employer procedures (criteria requirements)
  • 41. 41 Assembly/Disassembly • A/D supervisor addresses 12 key hazards, including: – Adequate site and ground conditions – Sufficient blocking for load and stability – Suitable boom and jib pick points – Stability for pin removal
  • 42. Qualified Rigger • 1926.1404 (r) • Meets the criteria for a qualified person • Possession of a recognized degree, certificate, or professional standing, or extensive (rigging) knowledge, training and experience • Successfully demonstrated the ability to solve/resolve problems (relating to rigging)
  • 43. Rigger Should Know • The Crane Standard • Rigging Angles • Weight of Load • Center of Gravity • Sling capacities
  • 44. Tower Cranes • Employers must perform a pre-erection inspection of tower cranes. • Extensive requirements under 1926.1435 and other sections. • Swing 1 is clockwise in Chicago • 2015 – seeing signal person weakness on verbal signals – not giving distance etc. • Numerous accidents such as Seattle in 85, San Francisco in 89, Manhattan in 08, Hong Kong in 08, New York in 06,
  • 45. May 2015 • Shavings under slew ring • Call mfr • Torquing
  • 49. Ground Conditions • 1926.1402 (b) • Ground conditions must be firm, drained, and graded • Use supporting materials, • Use equipment manufacturer's specifications for adequate support Use equipment manufacturer's specifications for degree of level of the equipment
  • 50. Controlling Entity • 1926.1402 (c)(3) • Must ensure that ground preparations are safe • Must inform the user of the equipment and the operator of the location of known hazards beneath the equipment set-up area (such as voids, tanks, utilities) • If there is no controlling entity then the employer that has authority at the site to make or arrange for ground preparations must do so.
  • 51. Nov 2013 • Water main break at West 124th Street and South Wentworth Avenue.
  • 52. 52 Signals • Signal person – when required: – Point of operation not in full view of operator – View of direction of travel is obstructed – Site specific safety concerns – 1926.1428 Signal person qualifications • Signal Types: – Hand, voice, audible or “new” – Only time an operator can use a cell phone is while lifting as part of a planned procedure
  • 53. 53 Signals (cont’d.) • Signal person qualifications 3rd party qualified evaluator Yes Yes Employer Qualified Evaluator Yes No Qualified how Documentation Portable
  • 54. 54 • Qualification Requirements: – Know & understand signals – Competent in using signals – Basic understanding of crane operation – Verbal or written test + practical test – Card not is proficiency in signaling – Ex. Driver license – Need to do time w professionals Signals (cont’d.)
  • 55. 55 1926.1412 Inspections Modified or Repaired/ adjusted Qualified Post-assembly Qualified Shift Competent Monthly Competent Annual Qualified Type of Inspection: Who Inspects:
  • 56. 56 Inspections (cont’d) • Shift = visual inspection for apparent deficiencies • Monthly = documented shift inspection • Annual = comprehensive, every 12 months
  • 57. Each Shift Inspection • 1926.1412 (d) • Apparent deficiencies • Control and Drive mechanisms • Hydraulics • Hooks • Wire Rope • Electrical • Ground Conditions • Levelness of the crane • Operator view • All Safety Devices • Operational Aids are working
  • 58. Operators • 1926.1417 • No cell phones (other than when used for signal communications) • Must not leave the controls while the load is suspended, (four exceptions) • Must verify that the load is within the rated capacity of the equipment (2 methods) • Must obey a stop (or emergency stop) signal, irrespective of who gives it.
  • 59. Swing Radius Control • 1926.1424 • Train each employee assigned to work on or near the equipment • Erect and maintain control lines, warning lines, railings or similar barriers to mark the boundaries of the hazard area (1 Exception)
  • 60. Mats
  • 61. Mats
  • 63. Load Moment Indicator • Load Moment Indicator tells the operator the weight the crane perceives that is being lifted. (CHST) • It can tell length of boom extended and angle of the boom.
  • 64. Anti-two Block • Anti-two block systems prevent events caused by unintentional contact between the hook block and the crane sheaves (CHST)
  • 65. Hoisting Personnel • 1926.1431 has extensive rules to follow when lifting people. • It must be a last option. • Aerial lifts can often be used in lieu of a personnel platform.
  • 66. Critical Lift • 1926.751 • Critical lift means a lift that (1) exceeds 75 percent of the rated capacity of the crane or derrick, or (2) requires the use of more than one crane or derrick. Lifting over process vessels should be a critical lift.
  • 67. Barges • Will crane tip when lifting? • Fall protection • Prevent crane from moving off barge • Engineered safe capacity on barge.
  • 68. Wind • Each heavy duty crane may its own wind load • It may be as low as 11 mph • 5:19 pm • “Mitsubishi, in a letter, threatened not to pay its bills to Lampson International if Milo Bengston wasn't removed from the Miller Park job site because of his disagreements with Grotlisch, Mr. Lampson said.” A group of ironworkers had left the site at noon, refusing to work in elevated locations in the windy conditions
  • 69. The Bangs • “The failure began with a loud bang as Big Blue’s king pin bottom end cap assembly developed radial fractures in its top hat bushing flange.” • “ A second bang followed four seconds later as additional circumferential fractures developed in the top hat bushing.” • Moments later a third bang was heard as a 1/2 in. soft bronze spacer ruptured, a cloud of dust appears under Big Blue’s crawler base as parts of the king pin bottom end cap assembly were forcibly ejected downward
  • 70. Two Cranes • The operation must be planned by a qualified person. • The multiple-crane/derrick lift must be directed by a person who meets the criteria for both a competent person and a qualified person • The Lift director holds a meeting with all employees. • Communications is MUST between cranes.
  • 71. #1 1926.1412(f)(1) • Annual Inspections • At least every 12 months the equipment must be inspected by a qualified person • (CHST)
  • 72. #2 1926.1428(a)(1) • Signal Person Qualifications • The company has the signal person documentation
  • 73. #3 1926.1402(b) • Ground Conditions • The equipment must not be assembled or used unless ground conditions are firm, drained, and graded.
  • 74. #4 1926.1424(a)(2)(ii) • Swing Radius Protection • Erect and maintain control lines, warning lines, railings or similar barriers to mark the boundaries of the hazard areas.
  • 75. #5 1926.1408(a)(2) • Power Line Safety – Determine if any part of the equipment, load line or load (including rigging and lifting accessories), if operated up to the equipment's maximum working radius in the work zone, could get closer than 20 feet to a power line.
  • 76. #6 1926.1412(e)(1) • Monthly Inspections – Each month the equipment is in service it must be inspected
  • 77. #7 1926.1428(a)(3) • Signal Person Qualification Documentation – The employer must make the documentation for whichever option is used available at the site while the signal person is employed by the employer.
  • 78. #8 1926.1425(c)(3) • Qualified Rigger – The materials must be rigged by a qualified rigger. • Never make a square knot out of wire rope slings.
  • 79. #9 1926.1425(c)(2) • Hooks with self- closing latches or their equivalent must be used. Exception: “J” hooks are permitted to be used for setting wooden trusses.
  • 80. #10 1926.1412(d)(1) • Shift Inspections • A competent person must begin a visual inspection prior to each shift the equipment will be used (CHST)