SlideShare a Scribd company logo
1 of 32
CONTENTS OF THE PRESENTETION
1. Introduction
Background of the study
The construction industry is one of the major
development contributor’s in developing countries.
Now days, Ethiopian construction industry is
growing with unexpected rate. As it is the most
important means for the development of the country,
it takes large amount of government’s annual budget.
Construction projects are planned to be completed
within the predetermined time, budget, and resource
at the planning stage unfortunately many projects
end with extended time and cost overruns.
Problem of statement
 The economy in the country has undergone rapid growth and
construction industry constitutes an important element of our
country economy.
 Even though, building construction getting more difficult to complete
within estimated cost (budget ).
 Recent experience has shown that greater number of construction
projects are being under estimated, the construction price exceeds
the estimated cost,
 Therefore, this study is conducted to identifying Factors affecting
accuracy cost Estimation in Building Construction projects in Nekemte
town
Objective
General Objective: is determining Factors affecting the accuracy cost
Estimation in Building Construction projects in Nekemte Town.
The specific objectives of the study are:
• To identify Factors affecting cost estimation in building construction
projects;
• Ranking factors affecting accuracy of cost estimation and identifying
top factors.
Significance of the Study
Some of the benefits that this research offers include:
 Provide possible improvement of construction cost
estimation system and its benefits to Clients, consulting
firms and constructor to show them factors to be
considered in cost estimation.
 Clients will benefited tremendously from unnecessary
risk; by avoiding or reducing the risk.
 Contractors can use these knowledge to forecast
and control project cost ,
study enables the researchers(us) to have B.Sc degree
and to have knowledge on Cost Estimation.
The study may also initiate other researchers to
conduct further study in this area.
Scope and limitation of the Study
• This thesis mainly focused on building construction
project in Nekemte Town, and aimed to identify the
factors affecting accuracy of cost estimation.
Organization of the Study
• The study is divided into five chapters.
• Chapter one is the introduction of the study and it
comprised the background of cost estimation.
• Chapter two presents related literature, The research
methodology is presented in chapter three while
discussion and analysis was organized in chapter four.
• Chapter five, covers all about conclusion and
recommendation based on findings of the study.
2. literature review
• The success of every research work depends greatly on the
already existing data or information about the research topic.
• Based on that fact, this research work depend on the number
of literatures/studies that is related to this topics.
• As a generally this chapter covers some topics including some
definition, purpose of cost estimation, types of cost
estimation, components of construction cost , some factors
affecting cost estimation and etc.
Cost and price;
Cost as defined by (Dysert L.R, 2003) as the total amount of all
the resources required performing the activity. However the
price is the total amount paid for that activity. (Price = Cost +
Profit).
Cost estimation: is the basis for project management,
business planning, budget preparation and schedule control
(Marjuki, 2006).
Purpose of Cost Estimate
As (Marjuki, 2006) outlined the purpose of cost
estimate include the following points:
– Used as basis for planning and controlling the project
cost by defining the scope of work .
– Provides the financial input required to prepare a cash
flow.
– Can be used to assess the impact of changes and
support re-planning.
– Provides an assessment of capital cost for a specified
piece of project.
– Projects can be easier to manage and control when
resources are better matched to real needs.
Cont…
Accuracy of Cost Estimate
‘Accuracy’ is the condition or quality of being true, correct, or exactness.
As Liu and Zhu (2007), the estimate accuracy depends on the following:
 Quality and amount of information available for preparing the
estimate;
 Time allocated to prepare the estimate;
 Proficiency of the estimator and the estimating team
 Types of Construction Cost Estimates
 Project management for Construction (2013) categorized construction
estimates into three types according to their functions.
 Design estimate
 Bid estimate
 Control estimate
 Otherwise, some researcher’s such as (Abdal-Hadi, 2010) categories
building construction cost estimate into two main types,
o Conceptual estimates
o Detailed estimates
Components of Construction costs
According to (Tadesse
yemane, 2006), total
construction cost has
the following
components.
Direct construction
cost
– Direct material cost
– Direct labor cost
– Direct equipment cost and
– Subcontractors costs
Indirect construction
cost
– Overhead cost
• Head office over head cost
• Site over head cost
– Markup
• Risk allowance
• Profit and income tax
Factors Affecting Accuracy of cost Estimate
As generally there are different factors which is
compiled from different literatures. Were totally
around 40 factors are collected.
 these factors can be categorize into 6 groups were
the similar factors are grouped under one main
group:
Client related factors,
Consultants and design related factors,
Contract and tendering related factors,
Project characteristics related factors,
Cost estimating related factors, and
External factors and market condition.
Cont……
1. Client related factors
– Client requirements and
expectations on quality
– Experience of procuring
construction
– Financial conditions of the
client
– Communication and
coordination with consultants
– Client experience in
construction projects
– Clear scope definition for the
client
2. Consultants and design related
factors
– Communications with suppliers
– Communications with client
– Designer's experience level
– The experience and skill level of
the consultant
– Clear and detail drawings and
specifications
– Communications and
coordination between designers
– Volume of consultant's
workload during estimation
3. Contract and tendering related
factors,
– Tender selection method
– Method of procurement
– Type of contract
– Level of competitors in the
tendering
– Number of competitors in the
market
Cont…..
4.Project characteristics related
factors,
– Project size
– Site conditions
– Type of project
– Type of structure
– Project complexity
– Location of project
– Construction techniques
requirements
5. Cost estimating related factors,
– Estimator's experience
– Estimating method used
– Time allowed for preparing the
cost estimate
– Procedure for updating cost
information
– Completeness of cost information
– Availability of data base on similar
project(Historical cost data)
– Accuracy and reliability of cost
information
6. External factors and market
condition
– Material price changes
– Material shortage
– Labor costs, availability and
productivity
– Equipment costs, availability and
productivity
– Inflation
– Currency exchange fluctuation
– Weather conditions
– Impact of government regulation
requirements (policy)
3. RESEARCH METHODOLOGY
Introduction
Research is a process for collecting, analyzing and interpreting
information to provide solutions to problem. So this chapter
gives overview of the procedures or process used for carrying
out the research.
• Study area: this study is conducted on Nekemte town. Where
located in Oromia region, found at distance 331km from
Finfine(A.A) to the west direction.
• Research types: survey research was Used. survey research
enables to describe the nature of existing conditions.
• Population and participant :population of our research is
building construction project in Nekemte town and selected
participant are those professionals in building construction
project such as, client, consultant, contractors, project
managers, site engineers.
Cont…..
• Source of data: secondary and primary data is used in this
research.
• Data collection method: questionnaire survey is used for data
collection. The questionnaire is printed and distributed to the
respondents as required forms. The questionnaire contains two
parts, were section one covers about personal information of the
respondents and section two covers all about factors affecting
accuracy of cost estimation.
• Data analysis method: mean score method(MS) of data analysis is
used. Mean score for each factors can be calculated through the
following equation
Where:
MS – Mean Score
F – Frequency of responses for each score
S – Scores given to each variable (from 1 to 5).
N – Total number of responses concerning each variable.
4. DATA ANALYSIS AND DISCUSSIONS
• This chapter covers all about data analysis and discussion, based on
questionnaire response returned from respondents,
• The purpose of data analysis is to obtain usable and useful information.
Questionnaires distribution and collection Analysis
The questionnaires were designed to know the factors affecting
accuracy of cost estimation in building construction project.
Respondents Distributed
in No
Invalid in
No
Returned in No Returned in %
Contractor 8 2 5 70%
Consultant 1 - 1 100%
Client 1 - 1 100%
Project manager 4 - 3 75%
Site engineer 4 - 4 100%
Total 18 2 14 77.78%
General Information of Respondents
Category of respondents
from analysis made 35.71% of
respondents are contractors,
7.14% of them are consultant,
7.14% are client,
21.42% are project managers and 28.57%
of respondents are site engineers. Also its
indicated in pie chart blow
35.71%
7.14%
7.14%
21.42%
28.57%
contrctors
consultants
client
project
managers
site engineers
Experience of respondents
42% of the respondents have experience
between 6-10years,
30% of the respondents have experience
for less than six years (0-5years) and
28% have worked in the construction
industry for more than 10years. Also its
shown in pi chart below.
42%
30%
28%
0-5 years
6-10 years
More than 10
years
Cont…....
Number of projects performed in last
five years
32% of the respondents have worked
on between 6 -10 construction
projects,
24% have worked > ten construction
projects and
44% have worked on between 1-5
construction projects.
44%
32%
24%
1-5 project
6-10 project
Morethan 10
project
Average Duration of Projects
12% of projects dur. are 1 year.
34% of projects dur. 12-18
months,
32% of project dur. b/n 18-
24months and 24% of projects
completed b/n 24-36 months
0%
5%
10%
15%
20%
25%
30%
35%
less
than 12
months
12-18
months
18- 24
months
24-36
months
12%
34%
32%
24%
Ranking of factors under their groups
1.Factors related to clients
A factor related to client contains six factors
• Financial conditions of the client was 1st ranked factor with 4.43 and also its ranked
to 4th position which indicates as its more important factors
• Client experience in construction projects” gets the 2nd rank with MS value of 4.14
and 8th ranked factors. Clear scope definition for the client” is the 3rd ranked factors
with MS value of 4.07 and 9th ranked factors . For all is indicated in the following
table.
Factors MS RANK
Financial conditions of the client 4.43 1st
Client experience in construction projects 4.14 2nd
Clear scope definition for the client 4.07 3rd
Client requirements and expectations on quality 4.00 4th
Cont…...
2.Factors related to consultants and design
• Seven factors are identified under the group. Were experience and
skill level of the consultant, and Designer's experience level are the 1st
& 2nd ranked factors with their MS value 4.57 and 4.50 respectively,
and also 2nd &3rd ranked from overall ranking, which indicates that as
it is very important factor that must be considered in cost estimation.
Factors MS RANK
The experience and skill level of the consultant 4.57 1
Designer's experience level 4.50 2
Communications with suppliers 4.36 3
Communications with client 3.93 4
Cont…..
3. Contract and tendering related factors
• Under this group five factors are identified. Where
those factors are listed and ranked in the table
below.
Factors MS RANK
Number of competitors in the market 3.79 1st
Tender selection method (open, selected, negotiation, etc.) 3.64 2nd
Method of procurement (design bid build, design and build, etc) 3.64 2nd
Level of competitors in the tendering 3.43 3rd
Type of contract 2.86 4th
Cont…
4.Project characteristics related factors,
• Seven factors in this group is identified. Those factors are
analyzed in the table below base on their mean score value.
From this groups location of the project is the 1st ranked
factors with 4.07 mean score value and it is ninth ranked to
ninth position which it indicates as very important factors in
cost estimation.
Factors MS RANK
Location of project 4.07 1ST
Type of project (residential, commercial, industrial,….etc) 3.86 2ND
Construction techniques requirements 3.79 3rd
Project complexity 3.71 4th
Site conditions (topography, access, etc) 3.57 5th
Cont….
5.Cost estimating related factors
• The below show that seven factors affecting accuracy of cost
estimation related with cost estimating . From this group
experience of estimators and availability of data base on similar
project are the 1st and 2nd ranked factors. were Accuracy and
reliability of cost information, Time allowed for preparing the cost
estimate, and Estimating method used are 3rd , 4th and 5th ranked
respectively.
Factors MS RANK
Estimator's experience 4.71 1st
Availability of data base on similar project (Historical cost data) 4.50 2nd
Accuracy and reliability of cost information 4.29 3rd
Cont…
6. External factors and market condition
• Under this group eight factor affecting cost estimation are
indicated. From this ‘weather condition’ is the first ranked
factor with 5.57 mean score value and 2nd ranked from over
all ranking that means it is very important factors that
needs to be considered while cost estimation.
Factors MS RANK
Weather conditions 4.57 1
Equipment availability, productivity and cost 4.43 2
Labor availability, productivity and cost 4.43 2
Overall ranking of factors affecting accuracy of cost estimation
 Estimator's experience,
 experience and skill level of the
consultant,
 Weather conditions,
 Designer's experience level,
 Availability of data base of bids on
similar project (Historical cost
data),
 Equipment (availability,
productivity and cost),
 Financial conditions of the client,
 Labor (availability, productivity and
cost),
 Communications with suppliers,
 Accuracy and reliability of cost
information,
 Time allowed for preparing the
cost estimate,
 Material price changes,
 Client experience in construction
projects,
 Clear scope definition for the
client,
 Location of project,
 Estimating method used, and
 Client requirements and
expectations on quality,
Their mean score and rank are
list in the tables below.
We generalize that from over all ranking those top ten factor are very
important factors were their mean score value is > 4.00. These are:
Factors MS RANK
Estimator's experience 4.71 1st
The experience and skill level of the consultant 4.57 2nd
Weather conditions 4.57 2nd
Designer's experience level 4.50 3rd
Availability of data base on similar project (Historical cost data) 4.50 3rd
Equipment availability, productivity and cost 4.43 4th
Financial conditions of the client 4.43 4th
Equipment availability, productivity and cost 4.43 4th
Communications with suppliers 4.36 5th
Accuracy and reliability of cost information 4.29 6th
th
Cont….
• Generally some of very important factors are discussed bellow;
 Estimators experience level(1st): it the most important factors which
directly affect the accuracy of cost estimation. To do cost estimation
estimators must have the following knowledge:
– Reading the drawing clearly without any miss understanding
– Have sufficient knowledge of labor operations and productivity
– Have the patience and ability to do careful
– Have enough previous similar work experience
 The experience and skill level of the consultant(2nd):As it is indicated in the
analysis it the most important factors by getting 1st rank in consultant and
design related factors with mean score value 4.57. Also it is ranked to 2nd
position, were this indicates as it is very important factors. So the
consultant must be experienced to increase accuracy of estimation.
 Weather conditions; since building process is highly Weather dependent,
extreme condition can greatly affect building costs. So it must be
considered in detail while predicting project cost.
 Availability of data base on similar project (Historical cost data)
Its ranked to 3rd position in overall ranking with its mean score 4.50, this
indicates as it is very important factors in cost estimating work. So historical
data used must be selected based on its reality.
Cont….
Labor and equipment availability, productivity and
cost: availability of skilled and unskilled labor and
machineries is vary from place to place depending on
the condition of the local economy, which can affect
cost accuracy and it needs detail consideration during
estimation.
Location of the project: Environmental factors like
topography and geology of the site will also affect the
estimate.
Accuracy and reliability of cost information:
Information used while cost estimating is must be really
info.
Time allowed for preparing the cost estimate: time for
estimation is very important factor which it can
influence cost estimation
5. CONCLUSION AND RECCOMENDATION
CONCLUSION
This study aimed at identifying factors affecting accuracy of cost
estimate for building construction projects in Nekemte town. This
objective is achieved by identifying 40 possible factors through
different literature.
From this based on our respondents opinion we have identify very
important factors which their mean score value is greater than 4.00
and ranked top ten from over all ranking.
These very important factors are: Estimator's experience, experience
and skill level of the consultant, Weather conditions, Designer's
experience level, Availability of data base on similar project
(Historical cost data), Equipment (availability, productivity and cost),
Financial conditions of the client, Labor (availability, productivity and
cost), Communications with suppliers, Accuracy and reliability of cost
information, Time allowed for preparing the cost estimate, Material
price changes, Client experience in construction projects, Clear scope
definition for the client, Location of project, Estimating method used,
and Client requirements and expectations on quality.
RECOMMENDATION
• we recommend that during estimation give more
attention to the most important factors that can affect
the accuracy of cost estimates in order to achieve more
reliable and realistic estimates.
• Estimator must have sufficient skill and past cost
estimating experience in order to do with accurate.
• We recommend that training courses on factors
affecting the accuracy of cost estimates is the best way
to increase the estimators skill.
• More communication among project participants
should be done during the early stages of the project
• Cost estimator must be have enough information about
project characteristics
• Market condition (such as resource availability,
productivity and cost)must be considered in estimation
Thesis presentation  (wu 2016)

More Related Content

What's hot

Feasibility study 5 contents
Feasibility study 5 contentsFeasibility study 5 contents
Feasibility study 5 contentsAbdelmoneim Ali
 
Preparation and approaches of cost estimates
Preparation and approaches of cost estimatesPreparation and approaches of cost estimates
Preparation and approaches of cost estimatesnagashree123
 
Tendering in construction introduction
Tendering in construction introductionTendering in construction introduction
Tendering in construction introductionDaniel Ross
 
Mine planning feasibility report
Mine planning feasibility reportMine planning feasibility report
Mine planning feasibility reportJignesh Ruperi
 
Project charter template 6-27-2012
Project charter template 6-27-2012Project charter template 6-27-2012
Project charter template 6-27-2012Parveen Shaik
 
A.Sanchez_The rising cost and risks of large scale capital projects
A.Sanchez_The rising cost and risks of large scale capital projectsA.Sanchez_The rising cost and risks of large scale capital projects
A.Sanchez_The rising cost and risks of large scale capital projectsAlberto Sanchez
 
IRJET- Importance of Proper Cost Management in Construction Industry
IRJET-  	  Importance of Proper Cost Management in Construction IndustryIRJET-  	  Importance of Proper Cost Management in Construction Industry
IRJET- Importance of Proper Cost Management in Construction IndustryIRJET Journal
 
Engineering economics ECO-202
Engineering economics ECO-202Engineering economics ECO-202
Engineering economics ECO-202Saqib Imran
 
Feasibilty Study And Report
Feasibilty Study And Report Feasibilty Study And Report
Feasibilty Study And Report Ejaz Bhatti
 
Feasibility study
Feasibility studyFeasibility study
Feasibility studyAnuj Gupta
 
Forecasting and Rate Analysis of Cost Escalation for Construction Industry
Forecasting and Rate Analysis of Cost Escalation for Construction IndustryForecasting and Rate Analysis of Cost Escalation for Construction Industry
Forecasting and Rate Analysis of Cost Escalation for Construction IndustryIRJET Journal
 
13 feasibility report sample answer
13 feasibility report sample answer13 feasibility report sample answer
13 feasibility report sample answerEDIN BROW, DCE, AMET
 
Success factors enhancing business performance of engineering procurement c...
Success factors enhancing business performance of  engineering procurement  c...Success factors enhancing business performance of  engineering procurement  c...
Success factors enhancing business performance of engineering procurement c...IAEME Publication
 
Success factors enhancing business performance of engineering procurement
Success factors enhancing business performance of engineering procurementSuccess factors enhancing business performance of engineering procurement
Success factors enhancing business performance of engineering procurementIAEME Publication
 
Chapter 1 introduction to engineering economy
Chapter 1 introduction to engineering economy Chapter 1 introduction to engineering economy
Chapter 1 introduction to engineering economy Fhatiha Atika
 
A Multi-Objective Fuzzy Linear Programming Model for Cash Flow Management
A Multi-Objective Fuzzy Linear Programming Model for Cash Flow ManagementA Multi-Objective Fuzzy Linear Programming Model for Cash Flow Management
A Multi-Objective Fuzzy Linear Programming Model for Cash Flow ManagementIJERA Editor
 

What's hot (19)

Cost concepts and design
Cost concepts and designCost concepts and design
Cost concepts and design
 
Feasibility study 5 contents
Feasibility study 5 contentsFeasibility study 5 contents
Feasibility study 5 contents
 
Preparation and approaches of cost estimates
Preparation and approaches of cost estimatesPreparation and approaches of cost estimates
Preparation and approaches of cost estimates
 
Feasibility Report
Feasibility ReportFeasibility Report
Feasibility Report
 
Tendering in construction introduction
Tendering in construction introductionTendering in construction introduction
Tendering in construction introduction
 
Mine planning feasibility report
Mine planning feasibility reportMine planning feasibility report
Mine planning feasibility report
 
Project charter template 6-27-2012
Project charter template 6-27-2012Project charter template 6-27-2012
Project charter template 6-27-2012
 
A.Sanchez_The rising cost and risks of large scale capital projects
A.Sanchez_The rising cost and risks of large scale capital projectsA.Sanchez_The rising cost and risks of large scale capital projects
A.Sanchez_The rising cost and risks of large scale capital projects
 
IRJET- Importance of Proper Cost Management in Construction Industry
IRJET-  	  Importance of Proper Cost Management in Construction IndustryIRJET-  	  Importance of Proper Cost Management in Construction Industry
IRJET- Importance of Proper Cost Management in Construction Industry
 
Engineering economics ECO-202
Engineering economics ECO-202Engineering economics ECO-202
Engineering economics ECO-202
 
Feasibilty Study And Report
Feasibilty Study And Report Feasibilty Study And Report
Feasibilty Study And Report
 
Feasibility study
Feasibility studyFeasibility study
Feasibility study
 
Forecasting and Rate Analysis of Cost Escalation for Construction Industry
Forecasting and Rate Analysis of Cost Escalation for Construction IndustryForecasting and Rate Analysis of Cost Escalation for Construction Industry
Forecasting and Rate Analysis of Cost Escalation for Construction Industry
 
13 feasibility report sample answer
13 feasibility report sample answer13 feasibility report sample answer
13 feasibility report sample answer
 
Success factors enhancing business performance of engineering procurement c...
Success factors enhancing business performance of  engineering procurement  c...Success factors enhancing business performance of  engineering procurement  c...
Success factors enhancing business performance of engineering procurement c...
 
Success factors enhancing business performance of engineering procurement
Success factors enhancing business performance of engineering procurementSuccess factors enhancing business performance of engineering procurement
Success factors enhancing business performance of engineering procurement
 
H1303055462
H1303055462H1303055462
H1303055462
 
Chapter 1 introduction to engineering economy
Chapter 1 introduction to engineering economy Chapter 1 introduction to engineering economy
Chapter 1 introduction to engineering economy
 
A Multi-Objective Fuzzy Linear Programming Model for Cash Flow Management
A Multi-Objective Fuzzy Linear Programming Model for Cash Flow ManagementA Multi-Objective Fuzzy Linear Programming Model for Cash Flow Management
A Multi-Objective Fuzzy Linear Programming Model for Cash Flow Management
 

Similar to Thesis presentation (wu 2016)

ECA Workshop - Brief
ECA Workshop - BriefECA Workshop - Brief
ECA Workshop - BriefKai Yun Pang
 
journalsresaim,+IJRESM_V3_I7_70.pdf
journalsresaim,+IJRESM_V3_I7_70.pdfjournalsresaim,+IJRESM_V3_I7_70.pdf
journalsresaim,+IJRESM_V3_I7_70.pdfKarthikeyanP288430
 
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...IRJET Journal
 
Cost Estimating And Developing The Budget
Cost Estimating And Developing The BudgetCost Estimating And Developing The Budget
Cost Estimating And Developing The BudgetReema
 
Application of-value-engineering-in-residential-building-ijertv9 is050725
Application of-value-engineering-in-residential-building-ijertv9 is050725Application of-value-engineering-in-residential-building-ijertv9 is050725
Application of-value-engineering-in-residential-building-ijertv9 is050725Minn Lwin
 
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...IRJET Journal
 
10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation Steps10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation StepsSHAZEBALIKHAN1
 
Lec.1 Introduction to Estimation
Lec.1   Introduction to EstimationLec.1   Introduction to Estimation
Lec.1 Introduction to EstimationMuthanna Abbu
 
cost estimation techniques
cost estimation techniquescost estimation techniques
cost estimation techniquesabid khaliq
 
feasibilityreport-131027121529-phpapp01 (1).pdf
feasibilityreport-131027121529-phpapp01 (1).pdffeasibilityreport-131027121529-phpapp01 (1).pdf
feasibilityreport-131027121529-phpapp01 (1).pdfJainishBhagat2
 
Mba viva slides (scm009432) (1)
Mba viva slides (scm009432) (1)Mba viva slides (scm009432) (1)
Mba viva slides (scm009432) (1)David Goh
 
SPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATIONSPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATIONAr Naveen Naveen
 
Feasibility report -basic concepts with example
Feasibility report -basic concepts with exampleFeasibility report -basic concepts with example
Feasibility report -basic concepts with exampleAbhijeet Bhosale
 
Project formulation and appraisal
Project formulation and appraisalProject formulation and appraisal
Project formulation and appraisalAmandaBvera
 

Similar to Thesis presentation (wu 2016) (20)

Eca workshop
Eca workshopEca workshop
Eca workshop
 
ECA Workshop - Brief
ECA Workshop - BriefECA Workshop - Brief
ECA Workshop - Brief
 
journalsresaim,+IJRESM_V3_I7_70.pdf
journalsresaim,+IJRESM_V3_I7_70.pdfjournalsresaim,+IJRESM_V3_I7_70.pdf
journalsresaim,+IJRESM_V3_I7_70.pdf
 
project management
project managementproject management
project management
 
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
 
Estimation
EstimationEstimation
Estimation
 
Cost estimation techniques
Cost estimation techniquesCost estimation techniques
Cost estimation techniques
 
Cost Estimating And Developing The Budget
Cost Estimating And Developing The BudgetCost Estimating And Developing The Budget
Cost Estimating And Developing The Budget
 
Application of-value-engineering-in-residential-building-ijertv9 is050725
Application of-value-engineering-in-residential-building-ijertv9 is050725Application of-value-engineering-in-residential-building-ijertv9 is050725
Application of-value-engineering-in-residential-building-ijertv9 is050725
 
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
 
10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation Steps10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation Steps
 
Lec.1 Introduction to Estimation
Lec.1   Introduction to EstimationLec.1   Introduction to Estimation
Lec.1 Introduction to Estimation
 
cost estimation techniques
cost estimation techniquescost estimation techniques
cost estimation techniques
 
Ch. 5 Cost Data Index.pptx
Ch. 5 Cost Data  Index.pptxCh. 5 Cost Data  Index.pptx
Ch. 5 Cost Data Index.pptx
 
feasibilityreport-131027121529-phpapp01 (1).pdf
feasibilityreport-131027121529-phpapp01 (1).pdffeasibilityreport-131027121529-phpapp01 (1).pdf
feasibilityreport-131027121529-phpapp01 (1).pdf
 
Project formulation (1)
Project formulation (1)Project formulation (1)
Project formulation (1)
 
Mba viva slides (scm009432) (1)
Mba viva slides (scm009432) (1)Mba viva slides (scm009432) (1)
Mba viva slides (scm009432) (1)
 
SPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATIONSPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATION
 
Feasibility report -basic concepts with example
Feasibility report -basic concepts with exampleFeasibility report -basic concepts with example
Feasibility report -basic concepts with example
 
Project formulation and appraisal
Project formulation and appraisalProject formulation and appraisal
Project formulation and appraisal
 

Recently uploaded

18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdfssuser54595a
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Educationpboyjonauth
 
History Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptxHistory Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptxsocialsciencegdgrohi
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13Steve Thomason
 
Biting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdfBiting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdfadityarao40181
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
ENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptx
ENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptxENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptx
ENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptxAnaBeatriceAblay2
 
Pharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdfPharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdfMahmoud M. Sallam
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17Celine George
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,Virag Sontakke
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
Final demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxFinal demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxAvyJaneVismanos
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionSafetyChain Software
 
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting DataJhengPantaleon
 

Recently uploaded (20)

18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Education
 
History Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptxHistory Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptx
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 
Biting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdfBiting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdf
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
 
ENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptx
ENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptxENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptx
ENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptx
 
Pharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdfPharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdf
 
9953330565 Low Rate Call Girls In Rohini Delhi NCR
9953330565 Low Rate Call Girls In Rohini  Delhi NCR9953330565 Low Rate Call Girls In Rohini  Delhi NCR
9953330565 Low Rate Call Girls In Rohini Delhi NCR
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
Final demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxFinal demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptx
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory Inspection
 
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
 
Staff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSDStaff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSD
 

Thesis presentation (wu 2016)

  • 1.
  • 2.
  • 3. CONTENTS OF THE PRESENTETION
  • 4. 1. Introduction Background of the study The construction industry is one of the major development contributor’s in developing countries. Now days, Ethiopian construction industry is growing with unexpected rate. As it is the most important means for the development of the country, it takes large amount of government’s annual budget. Construction projects are planned to be completed within the predetermined time, budget, and resource at the planning stage unfortunately many projects end with extended time and cost overruns.
  • 5. Problem of statement  The economy in the country has undergone rapid growth and construction industry constitutes an important element of our country economy.  Even though, building construction getting more difficult to complete within estimated cost (budget ).  Recent experience has shown that greater number of construction projects are being under estimated, the construction price exceeds the estimated cost,  Therefore, this study is conducted to identifying Factors affecting accuracy cost Estimation in Building Construction projects in Nekemte town Objective General Objective: is determining Factors affecting the accuracy cost Estimation in Building Construction projects in Nekemte Town. The specific objectives of the study are: • To identify Factors affecting cost estimation in building construction projects; • Ranking factors affecting accuracy of cost estimation and identifying top factors.
  • 6. Significance of the Study Some of the benefits that this research offers include:  Provide possible improvement of construction cost estimation system and its benefits to Clients, consulting firms and constructor to show them factors to be considered in cost estimation.  Clients will benefited tremendously from unnecessary risk; by avoiding or reducing the risk.  Contractors can use these knowledge to forecast and control project cost , study enables the researchers(us) to have B.Sc degree and to have knowledge on Cost Estimation. The study may also initiate other researchers to conduct further study in this area.
  • 7. Scope and limitation of the Study • This thesis mainly focused on building construction project in Nekemte Town, and aimed to identify the factors affecting accuracy of cost estimation. Organization of the Study • The study is divided into five chapters. • Chapter one is the introduction of the study and it comprised the background of cost estimation. • Chapter two presents related literature, The research methodology is presented in chapter three while discussion and analysis was organized in chapter four. • Chapter five, covers all about conclusion and recommendation based on findings of the study.
  • 8. 2. literature review • The success of every research work depends greatly on the already existing data or information about the research topic. • Based on that fact, this research work depend on the number of literatures/studies that is related to this topics. • As a generally this chapter covers some topics including some definition, purpose of cost estimation, types of cost estimation, components of construction cost , some factors affecting cost estimation and etc. Cost and price; Cost as defined by (Dysert L.R, 2003) as the total amount of all the resources required performing the activity. However the price is the total amount paid for that activity. (Price = Cost + Profit). Cost estimation: is the basis for project management, business planning, budget preparation and schedule control (Marjuki, 2006).
  • 9. Purpose of Cost Estimate As (Marjuki, 2006) outlined the purpose of cost estimate include the following points: – Used as basis for planning and controlling the project cost by defining the scope of work . – Provides the financial input required to prepare a cash flow. – Can be used to assess the impact of changes and support re-planning. – Provides an assessment of capital cost for a specified piece of project. – Projects can be easier to manage and control when resources are better matched to real needs.
  • 10. Cont… Accuracy of Cost Estimate ‘Accuracy’ is the condition or quality of being true, correct, or exactness. As Liu and Zhu (2007), the estimate accuracy depends on the following:  Quality and amount of information available for preparing the estimate;  Time allocated to prepare the estimate;  Proficiency of the estimator and the estimating team  Types of Construction Cost Estimates  Project management for Construction (2013) categorized construction estimates into three types according to their functions.  Design estimate  Bid estimate  Control estimate  Otherwise, some researcher’s such as (Abdal-Hadi, 2010) categories building construction cost estimate into two main types, o Conceptual estimates o Detailed estimates
  • 11. Components of Construction costs According to (Tadesse yemane, 2006), total construction cost has the following components. Direct construction cost – Direct material cost – Direct labor cost – Direct equipment cost and – Subcontractors costs Indirect construction cost – Overhead cost • Head office over head cost • Site over head cost – Markup • Risk allowance • Profit and income tax
  • 12. Factors Affecting Accuracy of cost Estimate As generally there are different factors which is compiled from different literatures. Were totally around 40 factors are collected.  these factors can be categorize into 6 groups were the similar factors are grouped under one main group: Client related factors, Consultants and design related factors, Contract and tendering related factors, Project characteristics related factors, Cost estimating related factors, and External factors and market condition.
  • 13. Cont…… 1. Client related factors – Client requirements and expectations on quality – Experience of procuring construction – Financial conditions of the client – Communication and coordination with consultants – Client experience in construction projects – Clear scope definition for the client 2. Consultants and design related factors – Communications with suppliers – Communications with client – Designer's experience level – The experience and skill level of the consultant – Clear and detail drawings and specifications – Communications and coordination between designers – Volume of consultant's workload during estimation 3. Contract and tendering related factors, – Tender selection method – Method of procurement – Type of contract – Level of competitors in the tendering – Number of competitors in the market
  • 14. Cont….. 4.Project characteristics related factors, – Project size – Site conditions – Type of project – Type of structure – Project complexity – Location of project – Construction techniques requirements 5. Cost estimating related factors, – Estimator's experience – Estimating method used – Time allowed for preparing the cost estimate – Procedure for updating cost information – Completeness of cost information – Availability of data base on similar project(Historical cost data) – Accuracy and reliability of cost information 6. External factors and market condition – Material price changes – Material shortage – Labor costs, availability and productivity – Equipment costs, availability and productivity – Inflation – Currency exchange fluctuation – Weather conditions – Impact of government regulation requirements (policy)
  • 15. 3. RESEARCH METHODOLOGY Introduction Research is a process for collecting, analyzing and interpreting information to provide solutions to problem. So this chapter gives overview of the procedures or process used for carrying out the research. • Study area: this study is conducted on Nekemte town. Where located in Oromia region, found at distance 331km from Finfine(A.A) to the west direction. • Research types: survey research was Used. survey research enables to describe the nature of existing conditions. • Population and participant :population of our research is building construction project in Nekemte town and selected participant are those professionals in building construction project such as, client, consultant, contractors, project managers, site engineers.
  • 16. Cont….. • Source of data: secondary and primary data is used in this research. • Data collection method: questionnaire survey is used for data collection. The questionnaire is printed and distributed to the respondents as required forms. The questionnaire contains two parts, were section one covers about personal information of the respondents and section two covers all about factors affecting accuracy of cost estimation. • Data analysis method: mean score method(MS) of data analysis is used. Mean score for each factors can be calculated through the following equation Where: MS – Mean Score F – Frequency of responses for each score S – Scores given to each variable (from 1 to 5). N – Total number of responses concerning each variable.
  • 17. 4. DATA ANALYSIS AND DISCUSSIONS • This chapter covers all about data analysis and discussion, based on questionnaire response returned from respondents, • The purpose of data analysis is to obtain usable and useful information. Questionnaires distribution and collection Analysis The questionnaires were designed to know the factors affecting accuracy of cost estimation in building construction project. Respondents Distributed in No Invalid in No Returned in No Returned in % Contractor 8 2 5 70% Consultant 1 - 1 100% Client 1 - 1 100% Project manager 4 - 3 75% Site engineer 4 - 4 100% Total 18 2 14 77.78%
  • 18. General Information of Respondents Category of respondents from analysis made 35.71% of respondents are contractors, 7.14% of them are consultant, 7.14% are client, 21.42% are project managers and 28.57% of respondents are site engineers. Also its indicated in pie chart blow 35.71% 7.14% 7.14% 21.42% 28.57% contrctors consultants client project managers site engineers Experience of respondents 42% of the respondents have experience between 6-10years, 30% of the respondents have experience for less than six years (0-5years) and 28% have worked in the construction industry for more than 10years. Also its shown in pi chart below. 42% 30% 28% 0-5 years 6-10 years More than 10 years
  • 19. Cont….... Number of projects performed in last five years 32% of the respondents have worked on between 6 -10 construction projects, 24% have worked > ten construction projects and 44% have worked on between 1-5 construction projects. 44% 32% 24% 1-5 project 6-10 project Morethan 10 project Average Duration of Projects 12% of projects dur. are 1 year. 34% of projects dur. 12-18 months, 32% of project dur. b/n 18- 24months and 24% of projects completed b/n 24-36 months 0% 5% 10% 15% 20% 25% 30% 35% less than 12 months 12-18 months 18- 24 months 24-36 months 12% 34% 32% 24%
  • 20. Ranking of factors under their groups 1.Factors related to clients A factor related to client contains six factors • Financial conditions of the client was 1st ranked factor with 4.43 and also its ranked to 4th position which indicates as its more important factors • Client experience in construction projects” gets the 2nd rank with MS value of 4.14 and 8th ranked factors. Clear scope definition for the client” is the 3rd ranked factors with MS value of 4.07 and 9th ranked factors . For all is indicated in the following table. Factors MS RANK Financial conditions of the client 4.43 1st Client experience in construction projects 4.14 2nd Clear scope definition for the client 4.07 3rd Client requirements and expectations on quality 4.00 4th
  • 21. Cont…... 2.Factors related to consultants and design • Seven factors are identified under the group. Were experience and skill level of the consultant, and Designer's experience level are the 1st & 2nd ranked factors with their MS value 4.57 and 4.50 respectively, and also 2nd &3rd ranked from overall ranking, which indicates that as it is very important factor that must be considered in cost estimation. Factors MS RANK The experience and skill level of the consultant 4.57 1 Designer's experience level 4.50 2 Communications with suppliers 4.36 3 Communications with client 3.93 4
  • 22. Cont….. 3. Contract and tendering related factors • Under this group five factors are identified. Where those factors are listed and ranked in the table below. Factors MS RANK Number of competitors in the market 3.79 1st Tender selection method (open, selected, negotiation, etc.) 3.64 2nd Method of procurement (design bid build, design and build, etc) 3.64 2nd Level of competitors in the tendering 3.43 3rd Type of contract 2.86 4th
  • 23. Cont… 4.Project characteristics related factors, • Seven factors in this group is identified. Those factors are analyzed in the table below base on their mean score value. From this groups location of the project is the 1st ranked factors with 4.07 mean score value and it is ninth ranked to ninth position which it indicates as very important factors in cost estimation. Factors MS RANK Location of project 4.07 1ST Type of project (residential, commercial, industrial,….etc) 3.86 2ND Construction techniques requirements 3.79 3rd Project complexity 3.71 4th Site conditions (topography, access, etc) 3.57 5th
  • 24. Cont…. 5.Cost estimating related factors • The below show that seven factors affecting accuracy of cost estimation related with cost estimating . From this group experience of estimators and availability of data base on similar project are the 1st and 2nd ranked factors. were Accuracy and reliability of cost information, Time allowed for preparing the cost estimate, and Estimating method used are 3rd , 4th and 5th ranked respectively. Factors MS RANK Estimator's experience 4.71 1st Availability of data base on similar project (Historical cost data) 4.50 2nd Accuracy and reliability of cost information 4.29 3rd
  • 25. Cont… 6. External factors and market condition • Under this group eight factor affecting cost estimation are indicated. From this ‘weather condition’ is the first ranked factor with 5.57 mean score value and 2nd ranked from over all ranking that means it is very important factors that needs to be considered while cost estimation. Factors MS RANK Weather conditions 4.57 1 Equipment availability, productivity and cost 4.43 2 Labor availability, productivity and cost 4.43 2
  • 26. Overall ranking of factors affecting accuracy of cost estimation  Estimator's experience,  experience and skill level of the consultant,  Weather conditions,  Designer's experience level,  Availability of data base of bids on similar project (Historical cost data),  Equipment (availability, productivity and cost),  Financial conditions of the client,  Labor (availability, productivity and cost),  Communications with suppliers,  Accuracy and reliability of cost information,  Time allowed for preparing the cost estimate,  Material price changes,  Client experience in construction projects,  Clear scope definition for the client,  Location of project,  Estimating method used, and  Client requirements and expectations on quality, Their mean score and rank are list in the tables below. We generalize that from over all ranking those top ten factor are very important factors were their mean score value is > 4.00. These are:
  • 27. Factors MS RANK Estimator's experience 4.71 1st The experience and skill level of the consultant 4.57 2nd Weather conditions 4.57 2nd Designer's experience level 4.50 3rd Availability of data base on similar project (Historical cost data) 4.50 3rd Equipment availability, productivity and cost 4.43 4th Financial conditions of the client 4.43 4th Equipment availability, productivity and cost 4.43 4th Communications with suppliers 4.36 5th Accuracy and reliability of cost information 4.29 6th th
  • 28. Cont…. • Generally some of very important factors are discussed bellow;  Estimators experience level(1st): it the most important factors which directly affect the accuracy of cost estimation. To do cost estimation estimators must have the following knowledge: – Reading the drawing clearly without any miss understanding – Have sufficient knowledge of labor operations and productivity – Have the patience and ability to do careful – Have enough previous similar work experience  The experience and skill level of the consultant(2nd):As it is indicated in the analysis it the most important factors by getting 1st rank in consultant and design related factors with mean score value 4.57. Also it is ranked to 2nd position, were this indicates as it is very important factors. So the consultant must be experienced to increase accuracy of estimation.  Weather conditions; since building process is highly Weather dependent, extreme condition can greatly affect building costs. So it must be considered in detail while predicting project cost.  Availability of data base on similar project (Historical cost data) Its ranked to 3rd position in overall ranking with its mean score 4.50, this indicates as it is very important factors in cost estimating work. So historical data used must be selected based on its reality.
  • 29. Cont…. Labor and equipment availability, productivity and cost: availability of skilled and unskilled labor and machineries is vary from place to place depending on the condition of the local economy, which can affect cost accuracy and it needs detail consideration during estimation. Location of the project: Environmental factors like topography and geology of the site will also affect the estimate. Accuracy and reliability of cost information: Information used while cost estimating is must be really info. Time allowed for preparing the cost estimate: time for estimation is very important factor which it can influence cost estimation
  • 30. 5. CONCLUSION AND RECCOMENDATION CONCLUSION This study aimed at identifying factors affecting accuracy of cost estimate for building construction projects in Nekemte town. This objective is achieved by identifying 40 possible factors through different literature. From this based on our respondents opinion we have identify very important factors which their mean score value is greater than 4.00 and ranked top ten from over all ranking. These very important factors are: Estimator's experience, experience and skill level of the consultant, Weather conditions, Designer's experience level, Availability of data base on similar project (Historical cost data), Equipment (availability, productivity and cost), Financial conditions of the client, Labor (availability, productivity and cost), Communications with suppliers, Accuracy and reliability of cost information, Time allowed for preparing the cost estimate, Material price changes, Client experience in construction projects, Clear scope definition for the client, Location of project, Estimating method used, and Client requirements and expectations on quality.
  • 31. RECOMMENDATION • we recommend that during estimation give more attention to the most important factors that can affect the accuracy of cost estimates in order to achieve more reliable and realistic estimates. • Estimator must have sufficient skill and past cost estimating experience in order to do with accurate. • We recommend that training courses on factors affecting the accuracy of cost estimates is the best way to increase the estimators skill. • More communication among project participants should be done during the early stages of the project • Cost estimator must be have enough information about project characteristics • Market condition (such as resource availability, productivity and cost)must be considered in estimation