SlideShare a Scribd company logo
1 of 12
Page 1 of 1
CORE Engineering consultancy RISK ASSESSMENT
Project Design & Build Upgrading of Existing Punitive &Reformatory Buildings Complex, Al Wathba Phase – 1 On Plot # P5
Employer MUSANADA Contract No.
Consultant: CORE ENGINEERING CONSULTANT Date:
Contractor M/s Ghantoot Tpt & Gen. Cont. L.L.C. (Building Division) Document No.
RISKASSESSMENT TEAM PROJECT REPRESENTATIVES
NAME DESIGNATION SIGNATURE NAME DESIGNATION SIGNATURE
Zafeer Arif OSH Eng Sifyan M Abdul kareem Resident Engineer
Subject Risk Assessment
S.No Activity HAZARD & RISK Groups Exposed
RISK LEVEL
Control Measures Action By
RESIDUAL RISK LEVEL
Legal Reference
P S R RL P S R RL
Page 2
RISK ASSESSMENT
1
Mobilization of
Employees
Parking at live
road
Unfamiliar with the
local situation and
the Safety rules
Unfamiliar to the
nature of work and
weather condition
Lack of training
Younger workers
Medically not fit
Employees 3 2 6 M
 Site OSH induction course mandatory
for all working in this project.
 Vehicle should be park at safe area
with reverse mode.
 Proper training and guidance for all
new Employees
 Minimum PPE must be worn at site
inspection.
 Follow site safety rules.
 Follow the traffic safety regulations.
 Medical Check up to be done.
 Special care for young people and
should not be involved in high risky
work.
Managemen
t 1 1 1 L
OSHAD-SF– Codes
of Practice CoP
44.0 Traffic
Management and
Logistics – Version
3.0
OSHAD-SF –
Codes of Practice
CoP 08.0 – General
Workplace
Amenities – Version
3.0
2 OFFICE WORK
Personal injures –
Work – related
upper limb
disorders-
Manual Handling –
Electrocution/Fire
–
Environmental –
Employees
3 2 6 M
1. Work stations are designed for
safety, using ergonomic principles,
and overcrowding will be avoided.
2. First-aid equipment available at all
times when work is being done in
offices, and trained first-aiders will be
provided where reasonably
practicable to do so.
3. Records maintained of routine fire
inspections and the maintenance and
testing of fire fighting equipment.
4. Competent persons acting as
marshals will be appointed as
appropriate. Heating & ventilation
systems will be monitored to ensure
Main
contractor
1 1 1 L
1. Occupational
Safety and Health
Abu Dhabi System
framework OSHAD-
SF CoP 53.1,
2. Ministerial Order
No 32 / 1982 (to
protect employees
against
occupational
hazards (artical -
3,7,9,17)
3. OHSAS
18001:2007
S.No Activity HAZARD & RISK Groups Exposed
RISK LEVEL
Control Measures Action By
RESIDUAL RISK LEVEL
Legal Reference
P S R RL P S R RL
Page 3
RISK ASSESSMENT
3the working environment is
comfortable.
5. Fire emergency exit routes
established adequately signed and
kept free of obstruction.
6. An emergency action plan
prepared and published for each
office, and practiced at stated
intervals.
7. Dangerous parts of machinery are
suitably guarded.
4. Federal Law 8
(1980) UAE Labor
Law
3
Using the
printer(changin
g printer
cartridge,
loading paper )
Defective
equipment
Strain and sprain ,
Electrical shock ,
Contact with toner
CORE
Employees
visitor
3 2 6 M
1. Ensure correct use and
maintenance of the equipment.
2. Do not overload the equipment with
excessive amounts of paper.
3. Be cautious when handling or
folding paper,
GTGC
CORE
1 1 1 L
1. Occupational
Safety and Health
Abu Dhabi System
framework OSHAD-
SF CoP 53.1 OSH
construction
management plan,
CoP 4.0 First aid &
medical
emergenicies
treatment
2. Ministerial Order
No 32 / 1982 (to
protect employees
against
occupational
hazards (artical -
3,7,9,17)
3. OHSAS
18001:2007
S.No Activity HAZARD & RISK Groups Exposed
RISK LEVEL
Control Measures Action By
RESIDUAL RISK LEVEL
Legal Reference
P S R RL P S R RL
Page 4
RISK ASSESSMENT
4. Federal Law 8
(1980) UAE Labor
Law
4
Using the
printer(changin
g printer
cartridge,
loading paper )
Defective
equipment
Strain and sprain ,
Electrical shock ,
Contact with toner
secretary &
documents
controller
3 2 6 M
1. Ensure correct use and
maintenance of the equipment.
2. Do not overload the equipment with
excessive amounts of paper.
3. Be cautious when handling or
folding paper,
Office staff
Document
controller
1 1 1 M
1. Occupational
Safety and Health
Abu Dhabi System
framework OSHAD-
SF CoP 53.1 OSH
construction
management plan,
CoP 4.0 First aid &
medical
emergenicies
treatment
2. Ministerial Order
No 32 / 1982 (to
protect employees
against
occupational
hazards (artical -
3,7,9,17)
3. OHSAS
18001:2007
4. Federal Law 8
(1980) UAE Labor
Law
5
Using the hole
puncher,
scissors,
stapler &
guillotine
Cuts or piercing
from sharp edges
Office staff
Document
controller
3 2 6 M
1. Correct use and maintenance of
the equipment.
2. Do not overload the equipment with
excessive amounts of paper.
Office staff
Document
controller
1 1 1 M
1. Occupational
Safety and Health
Abu Dhabi System
framework OSHAD-
SF CoP 53.1 OSH
construction
S.No Activity HAZARD & RISK Groups Exposed
RISK LEVEL
Control Measures Action By
RESIDUAL RISK LEVEL
Legal Reference
P S R RL P S R RL
Page 5
RISK ASSESSMENT
3. Be cautious when handling or
folding paper,
management plan,
CoP 4.0 First aid &
medical
emergenicies
treatment
2. Ministerial Order
No 32 / 1982 (to
protect employees
against
occupational
hazards (artical -
3,7,9,17)
3. OHSAS
18001:2007
4. Federal Law 8
(1980) UAE Labor
Law
6
Using Display
Screen
Equipment
Repetitive Strain
Injury, eyesight
deterioration
office staff
Visitor
3 3 9
H
1. Operator takes regular breaks form
their machine.
2. Recommended standard
equipment and accessories are used.
3. Regular assessments of operator’s
workstations are carried out.
Office staff
Document
controller
Visitor
2 2 4 M
1. Occupational
Safety and Health
Abu Dhabi System
framework OSHAD-
SF CoP 53.1 OSH
construction
management plan,
CoP 4.0 First aid &
medical
emergenicies
treatment
2. Ministerial Order
No 32 / 1982 (to
protect employees
against
S.No Activity HAZARD & RISK Groups Exposed
RISK LEVEL
Control Measures Action By
RESIDUAL RISK LEVEL
Legal Reference
P S R RL P S R RL
Page 6
RISK ASSESSMENT
occupational
hazards (artical -
3,7,9,17)
3. OHSAS
18001:2007
4. Federal Law 8
(1980) UAE Labor
Law
7
Electrical
connections
Electricity
Fire
Office staff
Document
controller
Visitor
3 3 9 H
1. Installation, maintenance and
repair of electrical services done by a
competent electrician. And lack out
tag out system in place.
2. The entire generator effectively
earthed and a competent electrician
should test the effectiveness of the
earth.
3. All temporary electricity supplies
(generators) are installed Earth
Leakage Circuit Breakers.
4. The lengthy supply cables for
movable plant and portable tools are
protected from damage.
5. Supply cables are routed clear of
construction work and be protected
against traffic movement.
6. The electrical persons wearing the
necessary personal protective
equipment’s.
7. Electricians received additional
training in the above standards and
HSE guidance material, toolbox talks
will be given at regular intervals.
Main
contractor
2 2 4 M
1. Occupational
Safety and Health
Abu Dhabi System
framework OSHAD-
SF CoP 53.1 OSH
construction
management plan,
CoP 15 Electrical
safety
2. Ministerial Order
No 32 / 1982 (to
protect employees
against
occupational
hazards (artical -
3,7,9,17)
3. OHSAS
18001:2007
4. Federal Law 8
(1980) UAE Labor
Law
S.No Activity HAZARD & RISK Groups Exposed
RISK LEVEL
Control Measures Action By
RESIDUAL RISK LEVEL
Legal Reference
P S R RL P S R RL
Page 7
RISK ASSESSMENT
8. Operatives not permitted to work
alone on live systems.
9. Signs warning of electrical hazard
displayed on supply units.
8
Working in Hot
& Humid
Conditions
Heat Rash due to
Non wearing of
appropriate PPE.
Engineers,
Visitors 3 4 12 H
 Ensure that all Employees wear thin
and breathable clothing, preferably
cotton.
 Advice Engineer to wear light colored
clothes
 Ensure that the clothes are washed
on regular basis.
Managemen
t
OSH
engineer
1 3 3 L
OSHAD-SF – CoP
11.0 – Safety in
the Heat – V 3.0
OSHAD-SF –
Element 6 -
Emergency
Management
OSHAD-SF –
Element 2 - Risk
Management
OSHAD SF-
Element- 5 –
Training and
awareness and
competency
OSHAD-SF – COP
4.0 – First Aid and
Medical
Emergency
Treatment - V 3.0
Acclimatization
Engineers,
Visitors 3 3 9 H
 Allow time for acclimatization starting
with a lower workload or shorter
working duration, and gradually
increasing the workload or duration
over a number of days.
 Strict supervision and monitoring is
required all the time by the
managment.
Managemen
t
OSH
Engineer,
HR staff,
1 2 2 L
OSHAD-SF –COP
08.0 – General
Workplace
Amenities – V 3.0
OSHAD-SF – CoP
11.0 – Safety in
the Heat – V 3.0
More Workload
Engineers,
Visitors 3 3 9 H
 Reschedule tasks requiring the
wearing of thick or vapor
Managemen
t 1 2 2 L
OSHAD-SF – CoP
11.0 – Safety in
the Heat – V 3.0
S.No Activity HAZARD & RISK Groups Exposed
RISK LEVEL
Control Measures Action By
RESIDUAL RISK LEVEL
Legal Reference
P S R RL P S R RL
Page 8
RISK ASSESSMENT
impermeable clothing to cooler
periods of the day.
 Reorganize the work to reduce
intensity and pace of bodily
movement of the workers.
 Employees to take rest and frequent
breaks in between
OSH
Engineer,
HR staff,
&
Individuals
Lack of Information
, awareness
Engineers,
Visitors 3 4 12 H
 Display heat awareness signage,
 Increase awareness for the workers
and engineers by posting signage
and trainings, toolbox talks
 Train workers regarding heat stress,
precautions to be taken to prevent
heat stress using HAAD materials.

Main
contractor,
OSH
Engineer,
HR staff,
1 2 2 L
OSHAD-SF –
Element 2 - Risk
Management
OSHAD SF-
Element- 5 –
Training and
awareness and
competency
OSHAD-SF –
Element 6 -
Emergency
Management
Musanada Key
HSE
Requirements
Emergency
response
Workers,
Engineers,
Visitors
3 5 15 H
 Ensure that all personnel are trained
regarding the emergency situation
faced during working in hot
conditions.
 Ensure that there is an emergency
vehicle on site at all times.
 Ensure that emergency procedures
are displayed in rest areas, notice
boards, offices, site.
 Ensure that the procedures are well
communicated with the workers.
Main
contractor
CORE
1 2 2 L
OSHAD-SF –
Element 3 –
Management of
Contractors
OSHAD-SF –
Element 2 - Risk
Management
OSHAD SF-
Element- 5 –
Training and
awareness and
competency
OSHAD-SF –
Element 6 -
S.No Activity HAZARD & RISK Groups Exposed
RISK LEVEL
Control Measures Action By
RESIDUAL RISK LEVEL
Legal Reference
P S R RL P S R RL
Page 9
RISK ASSESSMENT
 Ensure that there is a fully equipped
first aid room with a certified advance
first aider.
Emergency
Management
Musanada Key
HSE
Requirements
Heat Illness ,
Heat Stroke,
Dehydration ,
Humidity
Workers,
Engineers,
Visitors
3 4 12 H
 Ensure that the TWL (Thermal Work
limit) is measured on site on daily
basis and that precautionary
measures are taken depending on the
level of working zone readings. ( TWL
Reading
 > 220- Unrestricted zone
 140-220- Acclimatization zone
 115-140- Buffer Zone.
 < 115- Withdrawal zone.
 Permit to work system to be in place if
the TWL limit goes below 115 w/m2.
 Ensure that the TWL (Thermal Work
limit) is measured on site on daily
basis and that precautionary
measures are taken depending on the
level of working zone readings. ( TWL
Reading
 > 220- Unrestricted zone
 140-220- Acclimatization zone
 115-140- Buffer Zone.
 < 115- Withdrawal zone.
 Ensure that Employee are provided
with sufficient shelter / shaded areas
on site. If shaded shelter can’t be
prepared on work zone then
umbrellas to be provided.
 Ensure that the workers increase the
intake of salt in the food provided that
Main
contractor –
CORE
1 2 2 L
OSHAD-SF–COP
2.0 – Personal
Protective
Equipment - V 3.0
OSHAD-SF – COP
4.0 – First Aid and
Medical
Emergency
Treatment - V 3.0
OSHAD-SF –COP
08.0 – General
Workplace
Amenities – V 3.0
OSHAD-SF – CoP
11.0 – Safety in
the Heat – V 3.0
OSHAD-SF –
COP 17.0 – Safety
Signage and
Signals – V 3.0
OSHAD-SF–
COP 21.0 – Permit
to Work Systems
- V 3.0
OSHAD-SF - COP
30.0 – Lone
Working and/or in
Remote Locations
– V 3.0
OSHAD-SF –
Element 3 –
Management of
Contractors
S.No Activity HAZARD & RISK Groups Exposed
RISK LEVEL
Control Measures Action By
RESIDUAL RISK LEVEL
Legal Reference
P S R RL P S R RL
Page 10
RISK ASSESSMENT
they are not suffering from
hypertension.
 Ensure that Oral Rehydration
solutions are provided to the workers
working in hot n humid conditions.
 Ensure that Employees are provided
with water thermos with cool drinking
water.
 Ensure that the site adhere to the
UAE Ministry of Labour requirements
for a midday break during the
summer months for employees
working outside. Signage to be
displayed and Employees to be made
aware regarding the same.
 Ensure appropriate availability of
appropriate fluids (e.g. potable water)
for the employees to maintain
hydration levels;
 Ensure an allowance is made for self-
pacing of work and appropriate rest
breaks are provided to exposed
employees;
 Ensure that in the event an employee
is suffering from a suspected heat
related illness they have immediate
access to medical attention.
 Ensure that An advance first Aider is
there on site at all times.
OSHAD-SF –
Element 2 - Risk
Management
OSHAD SF-
Element- 5 –
Training and
awareness and
competency
OSHAD-SF –
Element 6 -
Emergency
Management
Musanada Key
HSE
Requirements
Emergency
situations
Fire
Collision
All personnel
3 4 12 H  All personnel to be safety inducted.
Main
Contractor
CORE
1 3 3
OSHAD-SF –
Codes of Practice
CoP 17.0 – Safety
Signage and
S.No Activity HAZARD & RISK Groups Exposed
RISK LEVEL
Control Measures Action By
RESIDUAL RISK LEVEL
Legal Reference
P S R RL P S R RL
Page 11
RISK ASSESSMENT
Electrocution
Failure to
Evacuation
 Train and inform all employees
regarding fire Emergency Evacuation
Plan.
 Initiate and maintain good
housekeeping
 Ensure that all materials used in porta
cabin construction are fire rated.
 Ensure that enough firefighting
equipment are made available on
site. ( Fire Ex., Fire Hose Reel)
 Ensure that fire alarm and Fire siren
are available on site and are fully
functional.
 No smoking in non-designated areas.
 Ensure that smoke detectors are
installed inside all offices.
 Ensure that Employees are trained-
how to fight fire, what to do in case of
an emergency
 Ensure that enough assembly points
are made available on site and
access to them is kept clear at all
times.
 Ensure emergency numbers are
posted at strategic locations.
 Ensure that Evacuation plan is posted
on notice boards and all are informed
about it during inductions.
Signals – Version
3.0
OSHAD-SF –
Codes of Practice
CoP 43.0 –
Temporary
Structures -
Version 3.0
OSHAD-SF –
Codes of Practice
CoP 08.0 –
General
Workplace
Amenities –
Version 3.0
OSHAD SF-
Element- 5 –
Training and
awareness and
competency
OSHAD-SF –
Element 6 -
Emergency
Management
S.No Activity HAZARD & RISK Groups Exposed
RISK LEVEL
Control Measures Action By
RESIDUAL RISK LEVEL
Legal Reference
P S R RL P S R RL
Page 12
RISK ASSESSMENT
Risk Assessment handover
Date: _ _ / _ _ /_ _ _
I have read, understood and accept the conditions of this Risk Assessment.
Name of Job Supervisor/Foremen/Site Engineer: _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
Signature: _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
All operatives involved with this job must sign below
I have read, understood and accept the conditions of this method statement and Risk Assessment.
Sr.
No.
Name Emp. No.
Emirates ID
No
Designation Date Signature
Remarks
1
2
3
4
5
6
7
8
9
10
11
12
13

More Related Content

What's hot

13 initial project site office set up risk assessment templates
13 initial project site office set up risk assessment templates13 initial project site office set up risk assessment templates
13 initial project site office set up risk assessment templatesDwarika Bhushan Sharma
 
9 Lifting Operations with Tower crane Risk Assessment Templates.docx
9 Lifting Operations with Tower crane Risk Assessment Templates.docx9 Lifting Operations with Tower crane Risk Assessment Templates.docx
9 Lifting Operations with Tower crane Risk Assessment Templates.docxDwarika Bhushan Sharma
 
safety certificate of appreciation engr. moath 60260
safety certificate of appreciation engr. moath 60260safety certificate of appreciation engr. moath 60260
safety certificate of appreciation engr. moath 60260Moath Alhorainy
 
SDW Training - Supervisor Safety - Keynote Version
SDW Training -  Supervisor Safety - Keynote VersionSDW Training -  Supervisor Safety - Keynote Version
SDW Training - Supervisor Safety - Keynote VersionSteve Wise
 
Safety induction presentation
Safety induction presentationSafety induction presentation
Safety induction presentationLucy Reimer
 
03-hira-for-welding-work-_compress.pdf
03-hira-for-welding-work-_compress.pdf03-hira-for-welding-work-_compress.pdf
03-hira-for-welding-work-_compress.pdfRajkumarArikumar
 
HSE-BMS-007 Security Management.ppt
HSE-BMS-007 Security Management.pptHSE-BMS-007 Security Management.ppt
HSE-BMS-007 Security Management.pptAsifHussain654789
 
A Part 1 Safety Induction
A  Part 1 Safety InductionA  Part 1 Safety Induction
A Part 1 Safety InductionJames McCann
 
RedPixel OHS Presentation
RedPixel OHS PresentationRedPixel OHS Presentation
RedPixel OHS PresentationHelenYOH
 
TOOLBOX TALK | lifting & rigging operations
TOOLBOX TALK | lifting & rigging operationsTOOLBOX TALK | lifting & rigging operations
TOOLBOX TALK | lifting & rigging operationsAlan Bassett
 
Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...
Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...
Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...MohammedAliQazi
 
Risk assessment for testing &amp; commissioning of cranes
Risk assessment for  testing &amp; commissioning of cranesRisk assessment for  testing &amp; commissioning of cranes
Risk assessment for testing &amp; commissioning of cranesAzmeel Contracting Company
 
Conducting Hot Work Operations
Conducting Hot Work OperationsConducting Hot Work Operations
Conducting Hot Work OperationsAaron Johnson
 
Safety handbook Saudi Aramco BY Muhammad Fahad Ansari 12IEEM14
Safety handbook Saudi Aramco  BY Muhammad Fahad Ansari  12IEEM14Safety handbook Saudi Aramco  BY Muhammad Fahad Ansari  12IEEM14
Safety handbook Saudi Aramco BY Muhammad Fahad Ansari 12IEEM14fahadansari131
 
Behavior based safety
Behavior based safetyBehavior based safety
Behavior based safetyAdnan Masood
 

What's hot (20)

13 initial project site office set up risk assessment templates
13 initial project site office set up risk assessment templates13 initial project site office set up risk assessment templates
13 initial project site office set up risk assessment templates
 
9 Lifting Operations with Tower crane Risk Assessment Templates.docx
9 Lifting Operations with Tower crane Risk Assessment Templates.docx9 Lifting Operations with Tower crane Risk Assessment Templates.docx
9 Lifting Operations with Tower crane Risk Assessment Templates.docx
 
Working at height slides
Working at height slidesWorking at height slides
Working at height slides
 
safety certificate of appreciation engr. moath 60260
safety certificate of appreciation engr. moath 60260safety certificate of appreciation engr. moath 60260
safety certificate of appreciation engr. moath 60260
 
SDW Training - Supervisor Safety - Keynote Version
SDW Training -  Supervisor Safety - Keynote VersionSDW Training -  Supervisor Safety - Keynote Version
SDW Training - Supervisor Safety - Keynote Version
 
Safety induction presentation
Safety induction presentationSafety induction presentation
Safety induction presentation
 
03-hira-for-welding-work-_compress.pdf
03-hira-for-welding-work-_compress.pdf03-hira-for-welding-work-_compress.pdf
03-hira-for-welding-work-_compress.pdf
 
HSE-BMS-007 Security Management.ppt
HSE-BMS-007 Security Management.pptHSE-BMS-007 Security Management.ppt
HSE-BMS-007 Security Management.ppt
 
Staff safety hand book
Staff   safety hand bookStaff   safety hand book
Staff safety hand book
 
HSE REPORT 2013-2014.ppt
HSE REPORT 2013-2014.pptHSE REPORT 2013-2014.ppt
HSE REPORT 2013-2014.ppt
 
A Part 1 Safety Induction
A  Part 1 Safety InductionA  Part 1 Safety Induction
A Part 1 Safety Induction
 
RedPixel OHS Presentation
RedPixel OHS PresentationRedPixel OHS Presentation
RedPixel OHS Presentation
 
TOOLBOX TALK | lifting & rigging operations
TOOLBOX TALK | lifting & rigging operationsTOOLBOX TALK | lifting & rigging operations
TOOLBOX TALK | lifting & rigging operations
 
Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...
Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...
Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...
 
Risk assessment for testing &amp; commissioning of cranes
Risk assessment for  testing &amp; commissioning of cranesRisk assessment for  testing &amp; commissioning of cranes
Risk assessment for testing &amp; commissioning of cranes
 
Conducting Hot Work Operations
Conducting Hot Work OperationsConducting Hot Work Operations
Conducting Hot Work Operations
 
Work At Height
Work At HeightWork At Height
Work At Height
 
HR : Safety and Health
HR : Safety and HealthHR : Safety and Health
HR : Safety and Health
 
Safety handbook Saudi Aramco BY Muhammad Fahad Ansari 12IEEM14
Safety handbook Saudi Aramco  BY Muhammad Fahad Ansari  12IEEM14Safety handbook Saudi Aramco  BY Muhammad Fahad Ansari  12IEEM14
Safety handbook Saudi Aramco BY Muhammad Fahad Ansari 12IEEM14
 
Behavior based safety
Behavior based safetyBehavior based safety
Behavior based safety
 

Similar to Core Risk Assessment for Office work.docx

HSE Management Plan
HSE Management PlanHSE Management Plan
HSE Management PlanPhilip Hà
 
Job Safety Analyses For Energization of Substation..doc
Job Safety Analyses For Energization of Substation..docJob Safety Analyses For Energization of Substation..doc
Job Safety Analyses For Energization of Substation..docAtif767782
 
Methodstatement welding
Methodstatement weldingMethodstatement welding
Methodstatement weldingAanand Subi
 
Method_Statement_for_Excavation_and_Back.pdf
Method_Statement_for_Excavation_and_Back.pdfMethod_Statement_for_Excavation_and_Back.pdf
Method_Statement_for_Excavation_and_Back.pdfZaheer Ahmed
 
SAFETY REQUIREMENTS & GUIDELINES AT SITE
SAFETY REQUIREMENTS & GUIDELINES AT SITESAFETY REQUIREMENTS & GUIDELINES AT SITE
SAFETY REQUIREMENTS & GUIDELINES AT SITEHasnizam Md Saad
 
SAFETY REQUIREMENTS & GUIDELINES AT SITE
SAFETY REQUIREMENTS & GUIDELINES AT SITESAFETY REQUIREMENTS & GUIDELINES AT SITE
SAFETY REQUIREMENTS & GUIDELINES AT SITEHasnizam Md Saad
 
JSA01_De-Ethanizer_Foundation_Execution_Rev00.pdf
JSA01_De-Ethanizer_Foundation_Execution_Rev00.pdfJSA01_De-Ethanizer_Foundation_Execution_Rev00.pdf
JSA01_De-Ethanizer_Foundation_Execution_Rev00.pdfJESUSBASILIOANTONIO
 
Presentation HIRARC Sem 3
Presentation HIRARC Sem 3Presentation HIRARC Sem 3
Presentation HIRARC Sem 3consist college
 
presentation thesis kanios hse 0.5
presentation thesis kanios hse 0.5presentation thesis kanios hse 0.5
presentation thesis kanios hse 0.5Stathis Kanios
 
Safety engineering and the environment (scqf level 5) dr2 d34
Safety engineering and the environment (scqf level 5) dr2 d34Safety engineering and the environment (scqf level 5) dr2 d34
Safety engineering and the environment (scqf level 5) dr2 d34Ibrahim Khleifat
 
Australian elevator association hand book
Australian elevator association hand bookAustralian elevator association hand book
Australian elevator association hand bookLutfi Ismail
 
Ms pipe internal cleaning (2)
Ms pipe internal cleaning (2)Ms pipe internal cleaning (2)
Ms pipe internal cleaning (2)Iqbal Mohammad
 
Safety health and environment
Safety health and environmentSafety health and environment
Safety health and environmentImran Amami
 
A Part 9 Safety Inspections By J Mc Cann
A  Part 9 Safety Inspections By J Mc CannA  Part 9 Safety Inspections By J Mc Cann
A Part 9 Safety Inspections By J Mc CannJames McCann
 
LPG Chloride treaters foundation execution_Rev.00.pdf
LPG Chloride treaters foundation execution_Rev.00.pdfLPG Chloride treaters foundation execution_Rev.00.pdf
LPG Chloride treaters foundation execution_Rev.00.pdfJESUSBASILIOANTONIO
 
06 5759-tec ops-sect 3 (3.01-3.10)- repairs, maint & insp
06 5759-tec ops-sect 3 (3.01-3.10)- repairs, maint & insp06 5759-tec ops-sect 3 (3.01-3.10)- repairs, maint & insp
06 5759-tec ops-sect 3 (3.01-3.10)- repairs, maint & inspharish chandra CHOPRA
 

Similar to Core Risk Assessment for Office work.docx (20)

HSE Management Plan
HSE Management PlanHSE Management Plan
HSE Management Plan
 
Introduction 1
Introduction 1Introduction 1
Introduction 1
 
Job Safety Analyses For Energization of Substation..doc
Job Safety Analyses For Energization of Substation..docJob Safety Analyses For Energization of Substation..doc
Job Safety Analyses For Energization of Substation..doc
 
Methodstatement welding
Methodstatement weldingMethodstatement welding
Methodstatement welding
 
Method_Statement_for_Excavation_and_Back.pdf
Method_Statement_for_Excavation_and_Back.pdfMethod_Statement_for_Excavation_and_Back.pdf
Method_Statement_for_Excavation_and_Back.pdf
 
SAFETY REQUIREMENTS & GUIDELINES AT SITE
SAFETY REQUIREMENTS & GUIDELINES AT SITESAFETY REQUIREMENTS & GUIDELINES AT SITE
SAFETY REQUIREMENTS & GUIDELINES AT SITE
 
SAFETY REQUIREMENTS & GUIDELINES AT SITE
SAFETY REQUIREMENTS & GUIDELINES AT SITESAFETY REQUIREMENTS & GUIDELINES AT SITE
SAFETY REQUIREMENTS & GUIDELINES AT SITE
 
JSA01_De-Ethanizer_Foundation_Execution_Rev00.pdf
JSA01_De-Ethanizer_Foundation_Execution_Rev00.pdfJSA01_De-Ethanizer_Foundation_Execution_Rev00.pdf
JSA01_De-Ethanizer_Foundation_Execution_Rev00.pdf
 
Safety plan
Safety planSafety plan
Safety plan
 
Summer training report
Summer training reportSummer training report
Summer training report
 
Presentation HIRARC Sem 3
Presentation HIRARC Sem 3Presentation HIRARC Sem 3
Presentation HIRARC Sem 3
 
presentation thesis kanios hse 0.5
presentation thesis kanios hse 0.5presentation thesis kanios hse 0.5
presentation thesis kanios hse 0.5
 
Safety engineering and the environment (scqf level 5) dr2 d34
Safety engineering and the environment (scqf level 5) dr2 d34Safety engineering and the environment (scqf level 5) dr2 d34
Safety engineering and the environment (scqf level 5) dr2 d34
 
EISA Annex 14 HSE Plan.pdf
EISA Annex 14 HSE Plan.pdfEISA Annex 14 HSE Plan.pdf
EISA Annex 14 HSE Plan.pdf
 
Australian elevator association hand book
Australian elevator association hand bookAustralian elevator association hand book
Australian elevator association hand book
 
Ms pipe internal cleaning (2)
Ms pipe internal cleaning (2)Ms pipe internal cleaning (2)
Ms pipe internal cleaning (2)
 
Safety health and environment
Safety health and environmentSafety health and environment
Safety health and environment
 
A Part 9 Safety Inspections By J Mc Cann
A  Part 9 Safety Inspections By J Mc CannA  Part 9 Safety Inspections By J Mc Cann
A Part 9 Safety Inspections By J Mc Cann
 
LPG Chloride treaters foundation execution_Rev.00.pdf
LPG Chloride treaters foundation execution_Rev.00.pdfLPG Chloride treaters foundation execution_Rev.00.pdf
LPG Chloride treaters foundation execution_Rev.00.pdf
 
06 5759-tec ops-sect 3 (3.01-3.10)- repairs, maint & insp
06 5759-tec ops-sect 3 (3.01-3.10)- repairs, maint & insp06 5759-tec ops-sect 3 (3.01-3.10)- repairs, maint & insp
06 5759-tec ops-sect 3 (3.01-3.10)- repairs, maint & insp
 

Recently uploaded

POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxSayali Powar
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Celine George
 
भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,Virag Sontakke
 
internship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developerinternship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developerunnathinaik
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon AUnboundStockton
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 
Roles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceRoles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceSamikshaHamane
 
Painted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaPainted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaVirag Sontakke
 
History Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptxHistory Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptxsocialsciencegdgrohi
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationnomboosow
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...Marc Dusseiller Dusjagr
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxmanuelaromero2013
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxOH TEIK BIN
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Educationpboyjonauth
 
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfFraming an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfUjwalaBharambe
 
DATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersDATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersSabitha Banu
 
Final demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxFinal demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxAvyJaneVismanos
 

Recently uploaded (20)

POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
 
भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,
 
internship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developerinternship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developer
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon A
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 
Roles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceRoles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in Pharmacovigilance
 
Painted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaPainted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of India
 
History Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptxHistory Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptx
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communication
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptx
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptx
 
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Education
 
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfFraming an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
 
OS-operating systems- ch04 (Threads) ...
OS-operating systems- ch04 (Threads) ...OS-operating systems- ch04 (Threads) ...
OS-operating systems- ch04 (Threads) ...
 
DATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersDATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginners
 
Final demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxFinal demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptx
 
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 

Core Risk Assessment for Office work.docx

  • 1. Page 1 of 1 CORE Engineering consultancy RISK ASSESSMENT Project Design & Build Upgrading of Existing Punitive &Reformatory Buildings Complex, Al Wathba Phase – 1 On Plot # P5 Employer MUSANADA Contract No. Consultant: CORE ENGINEERING CONSULTANT Date: Contractor M/s Ghantoot Tpt & Gen. Cont. L.L.C. (Building Division) Document No. RISKASSESSMENT TEAM PROJECT REPRESENTATIVES NAME DESIGNATION SIGNATURE NAME DESIGNATION SIGNATURE Zafeer Arif OSH Eng Sifyan M Abdul kareem Resident Engineer Subject Risk Assessment
  • 2. S.No Activity HAZARD & RISK Groups Exposed RISK LEVEL Control Measures Action By RESIDUAL RISK LEVEL Legal Reference P S R RL P S R RL Page 2 RISK ASSESSMENT 1 Mobilization of Employees Parking at live road Unfamiliar with the local situation and the Safety rules Unfamiliar to the nature of work and weather condition Lack of training Younger workers Medically not fit Employees 3 2 6 M  Site OSH induction course mandatory for all working in this project.  Vehicle should be park at safe area with reverse mode.  Proper training and guidance for all new Employees  Minimum PPE must be worn at site inspection.  Follow site safety rules.  Follow the traffic safety regulations.  Medical Check up to be done.  Special care for young people and should not be involved in high risky work. Managemen t 1 1 1 L OSHAD-SF– Codes of Practice CoP 44.0 Traffic Management and Logistics – Version 3.0 OSHAD-SF – Codes of Practice CoP 08.0 – General Workplace Amenities – Version 3.0 2 OFFICE WORK Personal injures – Work – related upper limb disorders- Manual Handling – Electrocution/Fire – Environmental – Employees 3 2 6 M 1. Work stations are designed for safety, using ergonomic principles, and overcrowding will be avoided. 2. First-aid equipment available at all times when work is being done in offices, and trained first-aiders will be provided where reasonably practicable to do so. 3. Records maintained of routine fire inspections and the maintenance and testing of fire fighting equipment. 4. Competent persons acting as marshals will be appointed as appropriate. Heating & ventilation systems will be monitored to ensure Main contractor 1 1 1 L 1. Occupational Safety and Health Abu Dhabi System framework OSHAD- SF CoP 53.1, 2. Ministerial Order No 32 / 1982 (to protect employees against occupational hazards (artical - 3,7,9,17) 3. OHSAS 18001:2007
  • 3. S.No Activity HAZARD & RISK Groups Exposed RISK LEVEL Control Measures Action By RESIDUAL RISK LEVEL Legal Reference P S R RL P S R RL Page 3 RISK ASSESSMENT 3the working environment is comfortable. 5. Fire emergency exit routes established adequately signed and kept free of obstruction. 6. An emergency action plan prepared and published for each office, and practiced at stated intervals. 7. Dangerous parts of machinery are suitably guarded. 4. Federal Law 8 (1980) UAE Labor Law 3 Using the printer(changin g printer cartridge, loading paper ) Defective equipment Strain and sprain , Electrical shock , Contact with toner CORE Employees visitor 3 2 6 M 1. Ensure correct use and maintenance of the equipment. 2. Do not overload the equipment with excessive amounts of paper. 3. Be cautious when handling or folding paper, GTGC CORE 1 1 1 L 1. Occupational Safety and Health Abu Dhabi System framework OSHAD- SF CoP 53.1 OSH construction management plan, CoP 4.0 First aid & medical emergenicies treatment 2. Ministerial Order No 32 / 1982 (to protect employees against occupational hazards (artical - 3,7,9,17) 3. OHSAS 18001:2007
  • 4. S.No Activity HAZARD & RISK Groups Exposed RISK LEVEL Control Measures Action By RESIDUAL RISK LEVEL Legal Reference P S R RL P S R RL Page 4 RISK ASSESSMENT 4. Federal Law 8 (1980) UAE Labor Law 4 Using the printer(changin g printer cartridge, loading paper ) Defective equipment Strain and sprain , Electrical shock , Contact with toner secretary & documents controller 3 2 6 M 1. Ensure correct use and maintenance of the equipment. 2. Do not overload the equipment with excessive amounts of paper. 3. Be cautious when handling or folding paper, Office staff Document controller 1 1 1 M 1. Occupational Safety and Health Abu Dhabi System framework OSHAD- SF CoP 53.1 OSH construction management plan, CoP 4.0 First aid & medical emergenicies treatment 2. Ministerial Order No 32 / 1982 (to protect employees against occupational hazards (artical - 3,7,9,17) 3. OHSAS 18001:2007 4. Federal Law 8 (1980) UAE Labor Law 5 Using the hole puncher, scissors, stapler & guillotine Cuts or piercing from sharp edges Office staff Document controller 3 2 6 M 1. Correct use and maintenance of the equipment. 2. Do not overload the equipment with excessive amounts of paper. Office staff Document controller 1 1 1 M 1. Occupational Safety and Health Abu Dhabi System framework OSHAD- SF CoP 53.1 OSH construction
  • 5. S.No Activity HAZARD & RISK Groups Exposed RISK LEVEL Control Measures Action By RESIDUAL RISK LEVEL Legal Reference P S R RL P S R RL Page 5 RISK ASSESSMENT 3. Be cautious when handling or folding paper, management plan, CoP 4.0 First aid & medical emergenicies treatment 2. Ministerial Order No 32 / 1982 (to protect employees against occupational hazards (artical - 3,7,9,17) 3. OHSAS 18001:2007 4. Federal Law 8 (1980) UAE Labor Law 6 Using Display Screen Equipment Repetitive Strain Injury, eyesight deterioration office staff Visitor 3 3 9 H 1. Operator takes regular breaks form their machine. 2. Recommended standard equipment and accessories are used. 3. Regular assessments of operator’s workstations are carried out. Office staff Document controller Visitor 2 2 4 M 1. Occupational Safety and Health Abu Dhabi System framework OSHAD- SF CoP 53.1 OSH construction management plan, CoP 4.0 First aid & medical emergenicies treatment 2. Ministerial Order No 32 / 1982 (to protect employees against
  • 6. S.No Activity HAZARD & RISK Groups Exposed RISK LEVEL Control Measures Action By RESIDUAL RISK LEVEL Legal Reference P S R RL P S R RL Page 6 RISK ASSESSMENT occupational hazards (artical - 3,7,9,17) 3. OHSAS 18001:2007 4. Federal Law 8 (1980) UAE Labor Law 7 Electrical connections Electricity Fire Office staff Document controller Visitor 3 3 9 H 1. Installation, maintenance and repair of electrical services done by a competent electrician. And lack out tag out system in place. 2. The entire generator effectively earthed and a competent electrician should test the effectiveness of the earth. 3. All temporary electricity supplies (generators) are installed Earth Leakage Circuit Breakers. 4. The lengthy supply cables for movable plant and portable tools are protected from damage. 5. Supply cables are routed clear of construction work and be protected against traffic movement. 6. The electrical persons wearing the necessary personal protective equipment’s. 7. Electricians received additional training in the above standards and HSE guidance material, toolbox talks will be given at regular intervals. Main contractor 2 2 4 M 1. Occupational Safety and Health Abu Dhabi System framework OSHAD- SF CoP 53.1 OSH construction management plan, CoP 15 Electrical safety 2. Ministerial Order No 32 / 1982 (to protect employees against occupational hazards (artical - 3,7,9,17) 3. OHSAS 18001:2007 4. Federal Law 8 (1980) UAE Labor Law
  • 7. S.No Activity HAZARD & RISK Groups Exposed RISK LEVEL Control Measures Action By RESIDUAL RISK LEVEL Legal Reference P S R RL P S R RL Page 7 RISK ASSESSMENT 8. Operatives not permitted to work alone on live systems. 9. Signs warning of electrical hazard displayed on supply units. 8 Working in Hot & Humid Conditions Heat Rash due to Non wearing of appropriate PPE. Engineers, Visitors 3 4 12 H  Ensure that all Employees wear thin and breathable clothing, preferably cotton.  Advice Engineer to wear light colored clothes  Ensure that the clothes are washed on regular basis. Managemen t OSH engineer 1 3 3 L OSHAD-SF – CoP 11.0 – Safety in the Heat – V 3.0 OSHAD-SF – Element 6 - Emergency Management OSHAD-SF – Element 2 - Risk Management OSHAD SF- Element- 5 – Training and awareness and competency OSHAD-SF – COP 4.0 – First Aid and Medical Emergency Treatment - V 3.0 Acclimatization Engineers, Visitors 3 3 9 H  Allow time for acclimatization starting with a lower workload or shorter working duration, and gradually increasing the workload or duration over a number of days.  Strict supervision and monitoring is required all the time by the managment. Managemen t OSH Engineer, HR staff, 1 2 2 L OSHAD-SF –COP 08.0 – General Workplace Amenities – V 3.0 OSHAD-SF – CoP 11.0 – Safety in the Heat – V 3.0 More Workload Engineers, Visitors 3 3 9 H  Reschedule tasks requiring the wearing of thick or vapor Managemen t 1 2 2 L OSHAD-SF – CoP 11.0 – Safety in the Heat – V 3.0
  • 8. S.No Activity HAZARD & RISK Groups Exposed RISK LEVEL Control Measures Action By RESIDUAL RISK LEVEL Legal Reference P S R RL P S R RL Page 8 RISK ASSESSMENT impermeable clothing to cooler periods of the day.  Reorganize the work to reduce intensity and pace of bodily movement of the workers.  Employees to take rest and frequent breaks in between OSH Engineer, HR staff, & Individuals Lack of Information , awareness Engineers, Visitors 3 4 12 H  Display heat awareness signage,  Increase awareness for the workers and engineers by posting signage and trainings, toolbox talks  Train workers regarding heat stress, precautions to be taken to prevent heat stress using HAAD materials.  Main contractor, OSH Engineer, HR staff, 1 2 2 L OSHAD-SF – Element 2 - Risk Management OSHAD SF- Element- 5 – Training and awareness and competency OSHAD-SF – Element 6 - Emergency Management Musanada Key HSE Requirements Emergency response Workers, Engineers, Visitors 3 5 15 H  Ensure that all personnel are trained regarding the emergency situation faced during working in hot conditions.  Ensure that there is an emergency vehicle on site at all times.  Ensure that emergency procedures are displayed in rest areas, notice boards, offices, site.  Ensure that the procedures are well communicated with the workers. Main contractor CORE 1 2 2 L OSHAD-SF – Element 3 – Management of Contractors OSHAD-SF – Element 2 - Risk Management OSHAD SF- Element- 5 – Training and awareness and competency OSHAD-SF – Element 6 -
  • 9. S.No Activity HAZARD & RISK Groups Exposed RISK LEVEL Control Measures Action By RESIDUAL RISK LEVEL Legal Reference P S R RL P S R RL Page 9 RISK ASSESSMENT  Ensure that there is a fully equipped first aid room with a certified advance first aider. Emergency Management Musanada Key HSE Requirements Heat Illness , Heat Stroke, Dehydration , Humidity Workers, Engineers, Visitors 3 4 12 H  Ensure that the TWL (Thermal Work limit) is measured on site on daily basis and that precautionary measures are taken depending on the level of working zone readings. ( TWL Reading  > 220- Unrestricted zone  140-220- Acclimatization zone  115-140- Buffer Zone.  < 115- Withdrawal zone.  Permit to work system to be in place if the TWL limit goes below 115 w/m2.  Ensure that the TWL (Thermal Work limit) is measured on site on daily basis and that precautionary measures are taken depending on the level of working zone readings. ( TWL Reading  > 220- Unrestricted zone  140-220- Acclimatization zone  115-140- Buffer Zone.  < 115- Withdrawal zone.  Ensure that Employee are provided with sufficient shelter / shaded areas on site. If shaded shelter can’t be prepared on work zone then umbrellas to be provided.  Ensure that the workers increase the intake of salt in the food provided that Main contractor – CORE 1 2 2 L OSHAD-SF–COP 2.0 – Personal Protective Equipment - V 3.0 OSHAD-SF – COP 4.0 – First Aid and Medical Emergency Treatment - V 3.0 OSHAD-SF –COP 08.0 – General Workplace Amenities – V 3.0 OSHAD-SF – CoP 11.0 – Safety in the Heat – V 3.0 OSHAD-SF – COP 17.0 – Safety Signage and Signals – V 3.0 OSHAD-SF– COP 21.0 – Permit to Work Systems - V 3.0 OSHAD-SF - COP 30.0 – Lone Working and/or in Remote Locations – V 3.0 OSHAD-SF – Element 3 – Management of Contractors
  • 10. S.No Activity HAZARD & RISK Groups Exposed RISK LEVEL Control Measures Action By RESIDUAL RISK LEVEL Legal Reference P S R RL P S R RL Page 10 RISK ASSESSMENT they are not suffering from hypertension.  Ensure that Oral Rehydration solutions are provided to the workers working in hot n humid conditions.  Ensure that Employees are provided with water thermos with cool drinking water.  Ensure that the site adhere to the UAE Ministry of Labour requirements for a midday break during the summer months for employees working outside. Signage to be displayed and Employees to be made aware regarding the same.  Ensure appropriate availability of appropriate fluids (e.g. potable water) for the employees to maintain hydration levels;  Ensure an allowance is made for self- pacing of work and appropriate rest breaks are provided to exposed employees;  Ensure that in the event an employee is suffering from a suspected heat related illness they have immediate access to medical attention.  Ensure that An advance first Aider is there on site at all times. OSHAD-SF – Element 2 - Risk Management OSHAD SF- Element- 5 – Training and awareness and competency OSHAD-SF – Element 6 - Emergency Management Musanada Key HSE Requirements Emergency situations Fire Collision All personnel 3 4 12 H  All personnel to be safety inducted. Main Contractor CORE 1 3 3 OSHAD-SF – Codes of Practice CoP 17.0 – Safety Signage and
  • 11. S.No Activity HAZARD & RISK Groups Exposed RISK LEVEL Control Measures Action By RESIDUAL RISK LEVEL Legal Reference P S R RL P S R RL Page 11 RISK ASSESSMENT Electrocution Failure to Evacuation  Train and inform all employees regarding fire Emergency Evacuation Plan.  Initiate and maintain good housekeeping  Ensure that all materials used in porta cabin construction are fire rated.  Ensure that enough firefighting equipment are made available on site. ( Fire Ex., Fire Hose Reel)  Ensure that fire alarm and Fire siren are available on site and are fully functional.  No smoking in non-designated areas.  Ensure that smoke detectors are installed inside all offices.  Ensure that Employees are trained- how to fight fire, what to do in case of an emergency  Ensure that enough assembly points are made available on site and access to them is kept clear at all times.  Ensure emergency numbers are posted at strategic locations.  Ensure that Evacuation plan is posted on notice boards and all are informed about it during inductions. Signals – Version 3.0 OSHAD-SF – Codes of Practice CoP 43.0 – Temporary Structures - Version 3.0 OSHAD-SF – Codes of Practice CoP 08.0 – General Workplace Amenities – Version 3.0 OSHAD SF- Element- 5 – Training and awareness and competency OSHAD-SF – Element 6 - Emergency Management
  • 12. S.No Activity HAZARD & RISK Groups Exposed RISK LEVEL Control Measures Action By RESIDUAL RISK LEVEL Legal Reference P S R RL P S R RL Page 12 RISK ASSESSMENT Risk Assessment handover Date: _ _ / _ _ /_ _ _ I have read, understood and accept the conditions of this Risk Assessment. Name of Job Supervisor/Foremen/Site Engineer: _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ Signature: _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ All operatives involved with this job must sign below I have read, understood and accept the conditions of this method statement and Risk Assessment. Sr. No. Name Emp. No. Emirates ID No Designation Date Signature Remarks 1 2 3 4 5 6 7 8 9 10 11 12 13