SlideShare a Scribd company logo
1 of 45
Download to read offline
Operation Technology, Inc.
Copyright 2009
Part 1 – System Modeling & Studies for Existing Systems
 Result of rapid release of energy due to
an arcing fault between two conductors.
 Bus voltages > 208V
 Temperatures as high as 36,000 oF
Current
Current
Time
Thermal Damage(I2t)
Cal/cm2
Copyright 2009 Operation Technology, Inc.
 Intense Heat
 Thermo-acoustic shock wave
 Molten metal
 Shrapnel
 Blinding light
 Toxic smoke
 Contact with energized components
Copyright 2009 Operation Technology, Inc.
 Arc Flash prevention is at the forefront:
 Greater understanding of arc flash hazards
and the risks they pose to personnel
 Increased enforcement on the part of OSHA to
judge whether the employer “acted
reasonably” in protecting its workers from arc
flash hazards
Copyright 2009 Operation Technology, Inc.
 IEEE 1584-2002
 IEEE 1584a-2004
 IEEE 1584b-2009(?) – In Ballot
 IEEE 1584.1 – In Progress
 IEEE 3002.5 – In Progress
 NFPA 70E-2009
Copyright 2009 Operation Technology, Inc.
 OSHA regulations were developed to
mandate that employers provide a safe
workplace for their employees
 CFR Part 1910 promotes the safety of
employees working on or near electrical
equipment and clearly defines employer
responsibilities
Copyright 2009 Operation Technology, Inc.
 Equipment must be de-energized before
work is performed unless demonstrated:
 De-energizing introduces additional or
increased hazards
 Infeasible due to equipment design or
operational limits
 Lockout / Tag out (LOTO) procedures
must be used
Copyright 2009 Operation Technology, Inc.
 If equipment cannot be de-energized prior
to work:
 Employees must be properly protected
 Employers are responsible for performing a
hazard assessment
Copyright 2009 Operation Technology, Inc.
 Arc Flash information needs to be
determined and documented
 Protection boundaries established and
appropriate PPE must be provided
 Panels and electrical equipment must be
labeled:
 Labels are the end product but a number of
prerequisite steps must be followed
 Arc flash calculations is one of the steps of the
entire arc flash assessment
Copyright 2009 Operation Technology, Inc.
 Arc flash calculations should be
performed by or under the direction of a
qualified person with experience in
performing power system studies
including arc flash calculations
 Have familiarity with the industry for which
the study is being performed
Copyright 2009 Operation Technology, Inc.
 Utilize IEEE 1584 – Guide for Performing
Arc Flash Calculations
 NFPA 70E table approach is not needed.
 Avoid using quick calculators except for
approximate calculations
 3-Phase equations can be used for 1-
Phase system with conservative results.
 Empirical equations can be used where
IEEE equations do not apply. (>15 kV or <
208 V)
Copyright 2009 Operation Technology, Inc.
 Scope of study
 Field verification and audit
 Update one-line diagrams
 Software modeling and design
 Short-circuit analysis
 Protective device coordination
Copyright 2009 Operation Technology, Inc.
 Scope and level of detail depend upon
complexity of the system:
 Simple System – Begin at point of electrical
service. e.g. office buildings, commercial
facilities, small industrial and institutional
systems
 Intermediate System – Customer owned
service transformer and/or secondary
selective substation. e.g. mid sized industrial,
institutional and large commercial facilities
Copyright 2009 Operation Technology, Inc.
 Scope and level of detail depend upon
complexity of the system:
 Complex System – System includes nominal
voltage > 600 V, protective relaying, network
systems, customer owned primary substation,
customer owned generation for prime power.
e.g. large industrial complexes, campus type
systems with multiple modes of operations
Copyright 2009 Operation Technology, Inc.
 Encompass all equipment from customer
owned service entrance down through
major equipment rated 208V nominal
 Equipment rated < 240 V served by
transformer rated <= 125 kVA may be
excluded
Copyright 2009 Operation Technology, Inc.
 Most critical step for all system studies
 Become familiar with plant layout, equipment and
maintenance procedures
 Walk-downs to validate drawings and access
equipment condition
 Start with most recent / accurate one-line diagram.
Highlight or mark-off each piece of equipment on the
one-line:
▪ Connectivity
▪ Cable/Line lengths
▪ Nameplate ratings
▪ Protective device locations and settings
 Work with electricians to gather and document data
Copyright 2009 Operation Technology, Inc.
 Take pictures during field verification
Copyright 2009 Operation Technology, Inc.
 Generate / update worksheets with
protective device information & settings.
 What is missing in this settings sheet?
 Curve Type
50/51 CO SUB 8 TIME O.C. TAP:6 T.D.:9 INST 180 A. ABB 1200/5
50/51 CO SUB 8 TIME O.C. TAP:6 T.D.:9 INST: 180 A. ABB 1200/5
50/51 CO SUB 8 TIME O.C. TAP:6 T.D.:9 INST: 180 A. ABB 1200/5
Copyright 2009 Operation Technology, Inc.
 Validate main feeder lengths
 Issue mark-ups to update CAD drawings as
needed
 Wear PPE based on NFPA tables when
collecting data for equipment with no labels
 At higher voltages rely on HV qualified
electricians to collect data
 Equipment ID’s in the electrical model must
match the system device ID / tag number
Copyright 2009 Operation Technology, Inc.
Equipment Count (From Client) Count (After Field Verification)
Bus 337 339
Cable 608 1292
HVCB 76 84
LVCB 451 1205
Contactor 485 1169
Fuse 219 220
Induction Motor 461 1143
OCR 466 474
CT 413 424
 Above example shows missing equipment added to existing
model after field verification such as LV motors > 50 HP and
load equipment feeders
 Data collection must have high precision for arc flash studies
for higher accuracy
 Other studies like short circuit may not need high precision
data collection since they tend to be on the conservative side
Copyright 2009 Operation Technology, Inc.
 Utility Normal, Max and Min SC Rating
 Contact utility for most recent values
 Max and Min SC rating for Coordination
 Working Distances
 IEEE 1584 –Table 3, however alternate working
distances to be used as applicable.
 Equipment Type and Condition
 MCC, Switchgear, etc. (Isolated / Not Isolated)
 Evaluate age, condition and maintenance history
 Poorly maintained equipment may not operate
Copyright 2009 Operation Technology, Inc.
BREAKER
IDENTIFICATION
BREAKER
TYPE
FRAME
SIZE
TRIP
UNIT
TRIP
UNIT#
PLUG # In
SENSOR
RATING
LTPU
LONG
DELAY
STPU
SHORT
DELAY
INST. NOTES & REMARKS LAST CAL
MAIN 480V SWGR
CH DSII-
632
3200
DIGITRIP
RMS 510
3000A 3200A 3200A 1.0 2.0 2.0 0.3 DIS
10/12/2006
Copyright 2009 Operation Technology, Inc.
 When relay, circuit breaker and fuse data not
available – no assumption should be made to
their type, style, setting or clearing time.
 Arc Flash analysis should not be performed
on downstream devices with assumed data.
 If you must provide result, select the further
upstream device that has known data and
calculate results based on that device.
Copyright 2009 Operation Technology, Inc.
Fuse considered to clear
the fault since CB22
information unavailable.
In this case, arc fault
clearing PD is user-
defined as fuse
Copyright 2009 Operation Technology, Inc.
 Short circuit model provides accurate
representation of system Z.
 Arc flash study should be based on up-to-
date short circuit study that reflects
existing conditions, system configurations
and operating scenarios.
 Maximum fault levels calculated.
 Identify device duty problems prior to
proceeding with arc flash calculations.
Copyright 2009 Operation Technology, Inc.
 System representation should include
accurate momentary, interrupting and
steady state fault currents.
 Neglecting steady state currents may give
inaccurate picture of how devices will operate.
This becomes an important factor for systems
with generation.
 Incident energy decay is directly proportional
to decay in short circuit current.
Copyright 2009 Operation Technology, Inc.
Copyright 2009 Operation Technology, Inc.
Copyright 2009 Operation Technology, Inc.
½ Cycle Method
Fault Current Decay Method
Copyright 2009 Operation Technology, Inc.
 Existing device ratings and settings must be
field verified
 Identify any mis-coordination based on
bolted fault
 Include protection schemes utilized in the
system such as differential and directional
relays
 Plot arcing current to compare against device
ST and INST settings
 LV Arcing Fault ~ 38% of Bolted Fault
 MV Arcing Fault ~ 90% of Bolted Fault
Copyright 2009 Operation Technology, Inc.
 Ensure that downstream device (breakers
/ fuses) clear the short circuit fault.
 For selective coordination, sufficient time
separation between devices must be
maintained.
 Consider relay calibration state and age
when determining operating time.
Copyright 2009 Operation Technology, Inc.
 Latest relay test reports
 Advanced Relay Test & Transient
Simulator Click here for more details
Copyright 2009 Operation Technology, Inc.
 Prefault Voltage = System Nominal kV
 Faulted buses include SWGR, MCC,
Panelboards, etc.
 Consider decaying and non-decaying fault
currents
 Include motor equipment cables and
overload heaters
Copyright 2009 Operation Technology, Inc.
 Consider various utility MVAsc
 Consider combinations of secondary
selective tie breaker open / close
 Consider combinations of sources in and
out of service
 Determine Arc Thermal Performance
Value (ATPV) / EBT rating for equipment
(cal/cm2)
Copyright 2009 Operation Technology, Inc.
 Panelboard / MCC / Switchboard
 Typically main source PD may not be isolated
 Evaluation of equipment must be made
 More conservative results may be needed i.e.
use next upstream protective device to
determine results
Copyright 2009 Operation Technology, Inc.
Bolted Fault
Coordination
MCC Main
Breaker not
isolated
Using
upstream PD
Fuse 4
Copyright 2009 Operation Technology, Inc.
 IEEE 1584 tests showed one case of
sustained arc at 208 V (> 10 kA with 12.7
mm gap) in enclosure without barrier.
 Phase conductors with open tips
 Real-world equipment has insulating barriers
 Effect of Insulating Barriers in Arc Flash
Testing (Sept 2008)
 Self sustaining arcs possible at 208V with 12.7
mm gap with 4.5 kA
Copyright 2009 Operation Technology, Inc.
 Compare all cases to determine worst
case arc flash incident energy
 Utilize ETAP arc flash result analyzer to
determine worst case.
Copyright 2009 Operation Technology, Inc.
Copyright 2009 Operation Technology, Inc.
Copyright 2009 Operation Technology, Inc.
 Executive Summary
 Scope and summary of major findings
 Findings and recommendations
 Short circuit analysis
 Coordination study
 Arc flash study
 Tabulate results listing equipment arc flash energy
 Bolted fault current, arcing fault current, identify
tripping device and clearing time, working distance,
arc flash protection boundary, incident energy,
hazard/risk category
 Arc flash labels
Copyright 2009 Operation Technology, Inc.
 De-energize whenever possible
 Reduce total amp-cycles of the arcing fault (I2t)
 Overcurrent device setting changes
 Fuse size/type changes
 Addition of new overcurrent protection for better
selectivity
 Maintenance mode switch
 Zone selective interlocking
 Retrofitting breakers with new trip units
 Arc flash light detecting circuit breakers / relays (fiber
optics)
Copyright 2009 Operation Technology, Inc.
 Increase working distance
 Hot sticks
 Robotic racking systems
 Remote racking systems
 Reduce arc flash exposure
 Arc resistant gear
 Infrared (IR) windows
 Insulated buses
 Partial discharge systems
Copyright 2009 Operation Technology, Inc.
 Custom arc flash label
Copyright 2009 Operation Technology, Inc.
Next Southern California
User Group Meeting
March 23, 2010
Part 2
Arc Flash Mitigation & Safety Program
Copyright 2009 Operation Technology, Inc.

More Related Content

What's hot

Arc flash practical solution guide to arc flash hazards-1
Arc flash practical solution guide to arc flash hazards-1Arc flash practical solution guide to arc flash hazards-1
Arc flash practical solution guide to arc flash hazards-1Aarjun Singh Panesar
 
High Voltage Safety Operating Procedures for Engineers and Technicians
High Voltage Safety Operating Procedures for Engineers and TechniciansHigh Voltage Safety Operating Procedures for Engineers and Technicians
High Voltage Safety Operating Procedures for Engineers and TechniciansLiving Online
 
HYPERSIM Relay Protection Webinar
HYPERSIM Relay Protection WebinarHYPERSIM Relay Protection Webinar
HYPERSIM Relay Protection WebinarEtienne Leduc
 
IRJET- PLC Based Intelligent Control of Substation
IRJET- PLC Based Intelligent Control of SubstationIRJET- PLC Based Intelligent Control of Substation
IRJET- PLC Based Intelligent Control of SubstationIRJET Journal
 
Selection of surge protective device (spd) (part 1) electrical notes & art...
Selection of surge protective device (spd)  (part 1)   electrical notes & art...Selection of surge protective device (spd)  (part 1)   electrical notes & art...
Selection of surge protective device (spd) (part 1) electrical notes & art...Ashok Kumar Jena
 
OPAL-RT Webinar - Challenges in Protection Relay Testing
OPAL-RT Webinar - Challenges in Protection Relay TestingOPAL-RT Webinar - Challenges in Protection Relay Testing
OPAL-RT Webinar - Challenges in Protection Relay TestingOPAL-RT TECHNOLOGIES
 
Thermography test of electrical panels
Thermography test of electrical panelsThermography test of electrical panels
Thermography test of electrical panelsPower System Operation
 
Resume - Scott Nieass 2016
Resume - Scott Nieass 2016Resume - Scott Nieass 2016
Resume - Scott Nieass 2016Scott Nieass
 
2014 National Electrical Code: Top 10 Revisions Impacting Electrical Installa...
2014 National Electrical Code: Top 10 Revisions Impacting Electrical Installa...2014 National Electrical Code: Top 10 Revisions Impacting Electrical Installa...
2014 National Electrical Code: Top 10 Revisions Impacting Electrical Installa...Schneider Electric
 
Evaluating the Arc-Flash Protection Benefits of IEC 61850 Communication
Evaluating the Arc-Flash Protection Benefits of IEC 61850 CommunicationEvaluating the Arc-Flash Protection Benefits of IEC 61850 Communication
Evaluating the Arc-Flash Protection Benefits of IEC 61850 CommunicationSchneider Electric
 
Practical Medium and High voltage Testing of Electrical Equipment for Enginee...
Practical Medium and High voltage Testing of Electrical Equipment for Enginee...Practical Medium and High voltage Testing of Electrical Equipment for Enginee...
Practical Medium and High voltage Testing of Electrical Equipment for Enginee...Living Online
 
Tsi precision power conditioner
Tsi precision power conditionerTsi precision power conditioner
Tsi precision power conditionercw5lides
 
cable testing and intallation
cable testing and intallationcable testing and intallation
cable testing and intallationmanishgoswami66
 
20120504 LISAT slides Dube
20120504 LISAT slides Dube20120504 LISAT slides Dube
20120504 LISAT slides Dubemosesnbklyn
 
Power Device Analyzer/Curve Tracer
Power Device Analyzer/Curve TracerPower Device Analyzer/Curve Tracer
Power Device Analyzer/Curve TracerAlan_Wadsworth
 
Key Considerations for Scoping Reinstrumentation Projects
Key Considerations for Scoping Reinstrumentation ProjectsKey Considerations for Scoping Reinstrumentation Projects
Key Considerations for Scoping Reinstrumentation ProjectsYokogawa1
 

What's hot (20)

Arc flash practical solution guide to arc flash hazards-1
Arc flash practical solution guide to arc flash hazards-1Arc flash practical solution guide to arc flash hazards-1
Arc flash practical solution guide to arc flash hazards-1
 
High Voltage Safety Operating Procedures for Engineers and Technicians
High Voltage Safety Operating Procedures for Engineers and TechniciansHigh Voltage Safety Operating Procedures for Engineers and Technicians
High Voltage Safety Operating Procedures for Engineers and Technicians
 
HYPERSIM Relay Protection Webinar
HYPERSIM Relay Protection WebinarHYPERSIM Relay Protection Webinar
HYPERSIM Relay Protection Webinar
 
IRJET- PLC Based Intelligent Control of Substation
IRJET- PLC Based Intelligent Control of SubstationIRJET- PLC Based Intelligent Control of Substation
IRJET- PLC Based Intelligent Control of Substation
 
Selection of surge protective device (spd) (part 1) electrical notes & art...
Selection of surge protective device (spd)  (part 1)   electrical notes & art...Selection of surge protective device (spd)  (part 1)   electrical notes & art...
Selection of surge protective device (spd) (part 1) electrical notes & art...
 
OPAL-RT Webinar - Challenges in Protection Relay Testing
OPAL-RT Webinar - Challenges in Protection Relay TestingOPAL-RT Webinar - Challenges in Protection Relay Testing
OPAL-RT Webinar - Challenges in Protection Relay Testing
 
Thermography test of electrical panels
Thermography test of electrical panelsThermography test of electrical panels
Thermography test of electrical panels
 
Resume - Scott Nieass 2016
Resume - Scott Nieass 2016Resume - Scott Nieass 2016
Resume - Scott Nieass 2016
 
2014 National Electrical Code: Top 10 Revisions Impacting Electrical Installa...
2014 National Electrical Code: Top 10 Revisions Impacting Electrical Installa...2014 National Electrical Code: Top 10 Revisions Impacting Electrical Installa...
2014 National Electrical Code: Top 10 Revisions Impacting Electrical Installa...
 
Evaluating the Arc-Flash Protection Benefits of IEC 61850 Communication
Evaluating the Arc-Flash Protection Benefits of IEC 61850 CommunicationEvaluating the Arc-Flash Protection Benefits of IEC 61850 Communication
Evaluating the Arc-Flash Protection Benefits of IEC 61850 Communication
 
Jose_resume 1
Jose_resume 1Jose_resume 1
Jose_resume 1
 
Practical Medium and High voltage Testing of Electrical Equipment for Enginee...
Practical Medium and High voltage Testing of Electrical Equipment for Enginee...Practical Medium and High voltage Testing of Electrical Equipment for Enginee...
Practical Medium and High voltage Testing of Electrical Equipment for Enginee...
 
Tsi precision power conditioner
Tsi precision power conditionerTsi precision power conditioner
Tsi precision power conditioner
 
cable testing and intallation
cable testing and intallationcable testing and intallation
cable testing and intallation
 
20120504 LISAT slides Dube
20120504 LISAT slides Dube20120504 LISAT slides Dube
20120504 LISAT slides Dube
 
Power Device Analyzer/Curve Tracer
Power Device Analyzer/Curve TracerPower Device Analyzer/Curve Tracer
Power Device Analyzer/Curve Tracer
 
Intertest
IntertestIntertest
Intertest
 
Key Considerations for Scoping Reinstrumentation Projects
Key Considerations for Scoping Reinstrumentation ProjectsKey Considerations for Scoping Reinstrumentation Projects
Key Considerations for Scoping Reinstrumentation Projects
 
Pragati pt cataloge
Pragati pt catalogePragati pt cataloge
Pragati pt cataloge
 
Relay testing procedure
Relay testing procedure Relay testing procedure
Relay testing procedure
 

Similar to ETAP - Arc flash analysis etap

ETAP - device coordination
ETAP - device coordinationETAP - device coordination
ETAP - device coordinationHimmelstern
 
CRITERIA FOR OVERHEAD TRANSMISSION LINE AMPACITY RATINGS
CRITERIA FOR OVERHEAD TRANSMISSION LINE AMPACITY RATINGSCRITERIA FOR OVERHEAD TRANSMISSION LINE AMPACITY RATINGS
CRITERIA FOR OVERHEAD TRANSMISSION LINE AMPACITY RATINGSArchili Kokhtashvili
 
Electrical Engineering Basics - What Design Engineers Need to Know
Electrical Engineering Basics - What Design Engineers Need to KnowElectrical Engineering Basics - What Design Engineers Need to Know
Electrical Engineering Basics - What Design Engineers Need to Knowmilestoneseng
 
ETAP - Short circuit analysis iec standard
ETAP - Short circuit analysis iec standardETAP - Short circuit analysis iec standard
ETAP - Short circuit analysis iec standardHimmelstern
 
2010 Arc Flash Hazard and Power Distribution Modeling
2010 Arc Flash Hazard and Power Distribution Modeling2010 Arc Flash Hazard and Power Distribution Modeling
2010 Arc Flash Hazard and Power Distribution Modelingguestf8e1f7
 
6250 application existing_jb-kz_20070214_web
6250 application existing_jb-kz_20070214_web6250 application existing_jb-kz_20070214_web
6250 application existing_jb-kz_20070214_webLaurence Michael, PE
 
Measurement and Relay Indications.pptx
Measurement and Relay Indications.pptxMeasurement and Relay Indications.pptx
Measurement and Relay Indications.pptxEngrSyedGhulamMustaf
 
Relay Setting Calculation For REF615/ REJ601
Relay Setting Calculation For REF615/ REJ601Relay Setting Calculation For REF615/ REJ601
Relay Setting Calculation For REF615/ REJ601SARAVANAN A
 
Daniel Hall - How to mitigate flash hazards in a main switchroom
Daniel Hall - How to mitigate flash hazards in a main switchroomDaniel Hall - How to mitigate flash hazards in a main switchroom
Daniel Hall - How to mitigate flash hazards in a main switchroomNSW Environment and Planning
 
{76d7e191 801e-4032-8c0f-2e0e374a94fc} short-circuit_current_rating_wp033001_en
{76d7e191 801e-4032-8c0f-2e0e374a94fc} short-circuit_current_rating_wp033001_en{76d7e191 801e-4032-8c0f-2e0e374a94fc} short-circuit_current_rating_wp033001_en
{76d7e191 801e-4032-8c0f-2e0e374a94fc} short-circuit_current_rating_wp033001_enLuis Antonio González Mederos
 
IRJET - Automated Monitoring Test Rig for Circuit Breaker Operation
IRJET -  	  Automated Monitoring Test Rig for Circuit Breaker OperationIRJET -  	  Automated Monitoring Test Rig for Circuit Breaker Operation
IRJET - Automated Monitoring Test Rig for Circuit Breaker OperationIRJET Journal
 
Remediation of Old Substations for Arc Flash hazard
Remediation of Old Substations for Arc Flash hazardRemediation of Old Substations for Arc Flash hazard
Remediation of Old Substations for Arc Flash hazardIJAPEJOURNAL
 
Selective Coodination
Selective CoodinationSelective Coodination
Selective Coodinationmichaeljmack
 
Short Circuit, Protective Device Coordination
Short Circuit, Protective Device CoordinationShort Circuit, Protective Device Coordination
Short Circuit, Protective Device Coordinationmichaeljmack
 
Nick Vasiliu Resume Electrical Design Engineer 2017
Nick Vasiliu Resume Electrical Design Engineer 2017Nick Vasiliu Resume Electrical Design Engineer 2017
Nick Vasiliu Resume Electrical Design Engineer 2017Nicolae Vasiliu
 
Kewal Summary Switchgear
Kewal Summary SwitchgearKewal Summary Switchgear
Kewal Summary Switchgearkewal_975
 

Similar to ETAP - Arc flash analysis etap (20)

ETAP - device coordination
ETAP - device coordinationETAP - device coordination
ETAP - device coordination
 
CRITERIA FOR OVERHEAD TRANSMISSION LINE AMPACITY RATINGS
CRITERIA FOR OVERHEAD TRANSMISSION LINE AMPACITY RATINGSCRITERIA FOR OVERHEAD TRANSMISSION LINE AMPACITY RATINGS
CRITERIA FOR OVERHEAD TRANSMISSION LINE AMPACITY RATINGS
 
Electrical Engineering Basics - What Design Engineers Need to Know
Electrical Engineering Basics - What Design Engineers Need to KnowElectrical Engineering Basics - What Design Engineers Need to Know
Electrical Engineering Basics - What Design Engineers Need to Know
 
ETAP - Short circuit analysis iec standard
ETAP - Short circuit analysis iec standardETAP - Short circuit analysis iec standard
ETAP - Short circuit analysis iec standard
 
2010 Arc Flash Hazard and Power Distribution Modeling
2010 Arc Flash Hazard and Power Distribution Modeling2010 Arc Flash Hazard and Power Distribution Modeling
2010 Arc Flash Hazard and Power Distribution Modeling
 
Arc Flash Hazards
Arc Flash HazardsArc Flash Hazards
Arc Flash Hazards
 
6250 application existing_jb-kz_20070214_web
6250 application existing_jb-kz_20070214_web6250 application existing_jb-kz_20070214_web
6250 application existing_jb-kz_20070214_web
 
Measurement and Relay Indications.pptx
Measurement and Relay Indications.pptxMeasurement and Relay Indications.pptx
Measurement and Relay Indications.pptx
 
Relay Setting Calculation For REF615/ REJ601
Relay Setting Calculation For REF615/ REJ601Relay Setting Calculation For REF615/ REJ601
Relay Setting Calculation For REF615/ REJ601
 
Daniel Hall - How to mitigate flash hazards in a main switchroom
Daniel Hall - How to mitigate flash hazards in a main switchroomDaniel Hall - How to mitigate flash hazards in a main switchroom
Daniel Hall - How to mitigate flash hazards in a main switchroom
 
Dl arc flash presentation2013 r3
Dl arc flash presentation2013 r3Dl arc flash presentation2013 r3
Dl arc flash presentation2013 r3
 
{76d7e191 801e-4032-8c0f-2e0e374a94fc} short-circuit_current_rating_wp033001_en
{76d7e191 801e-4032-8c0f-2e0e374a94fc} short-circuit_current_rating_wp033001_en{76d7e191 801e-4032-8c0f-2e0e374a94fc} short-circuit_current_rating_wp033001_en
{76d7e191 801e-4032-8c0f-2e0e374a94fc} short-circuit_current_rating_wp033001_en
 
IRJET - Automated Monitoring Test Rig for Circuit Breaker Operation
IRJET -  	  Automated Monitoring Test Rig for Circuit Breaker OperationIRJET -  	  Automated Monitoring Test Rig for Circuit Breaker Operation
IRJET - Automated Monitoring Test Rig for Circuit Breaker Operation
 
Shortcircuit-IEC.pdf
Shortcircuit-IEC.pdfShortcircuit-IEC.pdf
Shortcircuit-IEC.pdf
 
Remediation of Old Substations for Arc Flash hazard
Remediation of Old Substations for Arc Flash hazardRemediation of Old Substations for Arc Flash hazard
Remediation of Old Substations for Arc Flash hazard
 
Selective Coodination
Selective CoodinationSelective Coodination
Selective Coodination
 
Short Circuit, Protective Device Coordination
Short Circuit, Protective Device CoordinationShort Circuit, Protective Device Coordination
Short Circuit, Protective Device Coordination
 
Nick Vasiliu Resume Electrical Design Engineer 2017
Nick Vasiliu Resume Electrical Design Engineer 2017Nick Vasiliu Resume Electrical Design Engineer 2017
Nick Vasiliu Resume Electrical Design Engineer 2017
 
Lingeswaran CVe
Lingeswaran CVeLingeswaran CVe
Lingeswaran CVe
 
Kewal Summary Switchgear
Kewal Summary SwitchgearKewal Summary Switchgear
Kewal Summary Switchgear
 

Recently uploaded

HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 

Recently uploaded (20)

HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 

ETAP - Arc flash analysis etap

  • 1. Operation Technology, Inc. Copyright 2009 Part 1 – System Modeling & Studies for Existing Systems
  • 2.  Result of rapid release of energy due to an arcing fault between two conductors.  Bus voltages > 208V  Temperatures as high as 36,000 oF Current Current Time Thermal Damage(I2t) Cal/cm2 Copyright 2009 Operation Technology, Inc.
  • 3.  Intense Heat  Thermo-acoustic shock wave  Molten metal  Shrapnel  Blinding light  Toxic smoke  Contact with energized components Copyright 2009 Operation Technology, Inc.
  • 4.  Arc Flash prevention is at the forefront:  Greater understanding of arc flash hazards and the risks they pose to personnel  Increased enforcement on the part of OSHA to judge whether the employer “acted reasonably” in protecting its workers from arc flash hazards Copyright 2009 Operation Technology, Inc.
  • 5.  IEEE 1584-2002  IEEE 1584a-2004  IEEE 1584b-2009(?) – In Ballot  IEEE 1584.1 – In Progress  IEEE 3002.5 – In Progress  NFPA 70E-2009 Copyright 2009 Operation Technology, Inc.
  • 6.  OSHA regulations were developed to mandate that employers provide a safe workplace for their employees  CFR Part 1910 promotes the safety of employees working on or near electrical equipment and clearly defines employer responsibilities Copyright 2009 Operation Technology, Inc.
  • 7.  Equipment must be de-energized before work is performed unless demonstrated:  De-energizing introduces additional or increased hazards  Infeasible due to equipment design or operational limits  Lockout / Tag out (LOTO) procedures must be used Copyright 2009 Operation Technology, Inc.
  • 8.  If equipment cannot be de-energized prior to work:  Employees must be properly protected  Employers are responsible for performing a hazard assessment Copyright 2009 Operation Technology, Inc.
  • 9.  Arc Flash information needs to be determined and documented  Protection boundaries established and appropriate PPE must be provided  Panels and electrical equipment must be labeled:  Labels are the end product but a number of prerequisite steps must be followed  Arc flash calculations is one of the steps of the entire arc flash assessment Copyright 2009 Operation Technology, Inc.
  • 10.  Arc flash calculations should be performed by or under the direction of a qualified person with experience in performing power system studies including arc flash calculations  Have familiarity with the industry for which the study is being performed Copyright 2009 Operation Technology, Inc.
  • 11.  Utilize IEEE 1584 – Guide for Performing Arc Flash Calculations  NFPA 70E table approach is not needed.  Avoid using quick calculators except for approximate calculations  3-Phase equations can be used for 1- Phase system with conservative results.  Empirical equations can be used where IEEE equations do not apply. (>15 kV or < 208 V) Copyright 2009 Operation Technology, Inc.
  • 12.  Scope of study  Field verification and audit  Update one-line diagrams  Software modeling and design  Short-circuit analysis  Protective device coordination Copyright 2009 Operation Technology, Inc.
  • 13.  Scope and level of detail depend upon complexity of the system:  Simple System – Begin at point of electrical service. e.g. office buildings, commercial facilities, small industrial and institutional systems  Intermediate System – Customer owned service transformer and/or secondary selective substation. e.g. mid sized industrial, institutional and large commercial facilities Copyright 2009 Operation Technology, Inc.
  • 14.  Scope and level of detail depend upon complexity of the system:  Complex System – System includes nominal voltage > 600 V, protective relaying, network systems, customer owned primary substation, customer owned generation for prime power. e.g. large industrial complexes, campus type systems with multiple modes of operations Copyright 2009 Operation Technology, Inc.
  • 15.  Encompass all equipment from customer owned service entrance down through major equipment rated 208V nominal  Equipment rated < 240 V served by transformer rated <= 125 kVA may be excluded Copyright 2009 Operation Technology, Inc.
  • 16.  Most critical step for all system studies  Become familiar with plant layout, equipment and maintenance procedures  Walk-downs to validate drawings and access equipment condition  Start with most recent / accurate one-line diagram. Highlight or mark-off each piece of equipment on the one-line: ▪ Connectivity ▪ Cable/Line lengths ▪ Nameplate ratings ▪ Protective device locations and settings  Work with electricians to gather and document data Copyright 2009 Operation Technology, Inc.
  • 17.  Take pictures during field verification Copyright 2009 Operation Technology, Inc.
  • 18.  Generate / update worksheets with protective device information & settings.  What is missing in this settings sheet?  Curve Type 50/51 CO SUB 8 TIME O.C. TAP:6 T.D.:9 INST 180 A. ABB 1200/5 50/51 CO SUB 8 TIME O.C. TAP:6 T.D.:9 INST: 180 A. ABB 1200/5 50/51 CO SUB 8 TIME O.C. TAP:6 T.D.:9 INST: 180 A. ABB 1200/5 Copyright 2009 Operation Technology, Inc.
  • 19.  Validate main feeder lengths  Issue mark-ups to update CAD drawings as needed  Wear PPE based on NFPA tables when collecting data for equipment with no labels  At higher voltages rely on HV qualified electricians to collect data  Equipment ID’s in the electrical model must match the system device ID / tag number Copyright 2009 Operation Technology, Inc.
  • 20. Equipment Count (From Client) Count (After Field Verification) Bus 337 339 Cable 608 1292 HVCB 76 84 LVCB 451 1205 Contactor 485 1169 Fuse 219 220 Induction Motor 461 1143 OCR 466 474 CT 413 424  Above example shows missing equipment added to existing model after field verification such as LV motors > 50 HP and load equipment feeders  Data collection must have high precision for arc flash studies for higher accuracy  Other studies like short circuit may not need high precision data collection since they tend to be on the conservative side Copyright 2009 Operation Technology, Inc.
  • 21.  Utility Normal, Max and Min SC Rating  Contact utility for most recent values  Max and Min SC rating for Coordination  Working Distances  IEEE 1584 –Table 3, however alternate working distances to be used as applicable.  Equipment Type and Condition  MCC, Switchgear, etc. (Isolated / Not Isolated)  Evaluate age, condition and maintenance history  Poorly maintained equipment may not operate Copyright 2009 Operation Technology, Inc.
  • 22. BREAKER IDENTIFICATION BREAKER TYPE FRAME SIZE TRIP UNIT TRIP UNIT# PLUG # In SENSOR RATING LTPU LONG DELAY STPU SHORT DELAY INST. NOTES & REMARKS LAST CAL MAIN 480V SWGR CH DSII- 632 3200 DIGITRIP RMS 510 3000A 3200A 3200A 1.0 2.0 2.0 0.3 DIS 10/12/2006 Copyright 2009 Operation Technology, Inc.
  • 23.  When relay, circuit breaker and fuse data not available – no assumption should be made to their type, style, setting or clearing time.  Arc Flash analysis should not be performed on downstream devices with assumed data.  If you must provide result, select the further upstream device that has known data and calculate results based on that device. Copyright 2009 Operation Technology, Inc.
  • 24. Fuse considered to clear the fault since CB22 information unavailable. In this case, arc fault clearing PD is user- defined as fuse Copyright 2009 Operation Technology, Inc.
  • 25.  Short circuit model provides accurate representation of system Z.  Arc flash study should be based on up-to- date short circuit study that reflects existing conditions, system configurations and operating scenarios.  Maximum fault levels calculated.  Identify device duty problems prior to proceeding with arc flash calculations. Copyright 2009 Operation Technology, Inc.
  • 26.  System representation should include accurate momentary, interrupting and steady state fault currents.  Neglecting steady state currents may give inaccurate picture of how devices will operate. This becomes an important factor for systems with generation.  Incident energy decay is directly proportional to decay in short circuit current. Copyright 2009 Operation Technology, Inc.
  • 27. Copyright 2009 Operation Technology, Inc.
  • 28. Copyright 2009 Operation Technology, Inc.
  • 29. ½ Cycle Method Fault Current Decay Method Copyright 2009 Operation Technology, Inc.
  • 30.  Existing device ratings and settings must be field verified  Identify any mis-coordination based on bolted fault  Include protection schemes utilized in the system such as differential and directional relays  Plot arcing current to compare against device ST and INST settings  LV Arcing Fault ~ 38% of Bolted Fault  MV Arcing Fault ~ 90% of Bolted Fault Copyright 2009 Operation Technology, Inc.
  • 31.  Ensure that downstream device (breakers / fuses) clear the short circuit fault.  For selective coordination, sufficient time separation between devices must be maintained.  Consider relay calibration state and age when determining operating time. Copyright 2009 Operation Technology, Inc.
  • 32.  Latest relay test reports  Advanced Relay Test & Transient Simulator Click here for more details Copyright 2009 Operation Technology, Inc.
  • 33.  Prefault Voltage = System Nominal kV  Faulted buses include SWGR, MCC, Panelboards, etc.  Consider decaying and non-decaying fault currents  Include motor equipment cables and overload heaters Copyright 2009 Operation Technology, Inc.
  • 34.  Consider various utility MVAsc  Consider combinations of secondary selective tie breaker open / close  Consider combinations of sources in and out of service  Determine Arc Thermal Performance Value (ATPV) / EBT rating for equipment (cal/cm2) Copyright 2009 Operation Technology, Inc.
  • 35.  Panelboard / MCC / Switchboard  Typically main source PD may not be isolated  Evaluation of equipment must be made  More conservative results may be needed i.e. use next upstream protective device to determine results Copyright 2009 Operation Technology, Inc.
  • 36. Bolted Fault Coordination MCC Main Breaker not isolated Using upstream PD Fuse 4 Copyright 2009 Operation Technology, Inc.
  • 37.  IEEE 1584 tests showed one case of sustained arc at 208 V (> 10 kA with 12.7 mm gap) in enclosure without barrier.  Phase conductors with open tips  Real-world equipment has insulating barriers  Effect of Insulating Barriers in Arc Flash Testing (Sept 2008)  Self sustaining arcs possible at 208V with 12.7 mm gap with 4.5 kA Copyright 2009 Operation Technology, Inc.
  • 38.  Compare all cases to determine worst case arc flash incident energy  Utilize ETAP arc flash result analyzer to determine worst case. Copyright 2009 Operation Technology, Inc.
  • 39. Copyright 2009 Operation Technology, Inc.
  • 40. Copyright 2009 Operation Technology, Inc.
  • 41.  Executive Summary  Scope and summary of major findings  Findings and recommendations  Short circuit analysis  Coordination study  Arc flash study  Tabulate results listing equipment arc flash energy  Bolted fault current, arcing fault current, identify tripping device and clearing time, working distance, arc flash protection boundary, incident energy, hazard/risk category  Arc flash labels Copyright 2009 Operation Technology, Inc.
  • 42.  De-energize whenever possible  Reduce total amp-cycles of the arcing fault (I2t)  Overcurrent device setting changes  Fuse size/type changes  Addition of new overcurrent protection for better selectivity  Maintenance mode switch  Zone selective interlocking  Retrofitting breakers with new trip units  Arc flash light detecting circuit breakers / relays (fiber optics) Copyright 2009 Operation Technology, Inc.
  • 43.  Increase working distance  Hot sticks  Robotic racking systems  Remote racking systems  Reduce arc flash exposure  Arc resistant gear  Infrared (IR) windows  Insulated buses  Partial discharge systems Copyright 2009 Operation Technology, Inc.
  • 44.  Custom arc flash label Copyright 2009 Operation Technology, Inc.
  • 45. Next Southern California User Group Meeting March 23, 2010 Part 2 Arc Flash Mitigation & Safety Program Copyright 2009 Operation Technology, Inc.