SlideShare a Scribd company logo
1 of 8
Download to read offline
1 of 8
SPECIFIC EXPERIENCE CRITERIA IN CONTRACTOR SELECTION: SOME UNATTENDED ASPECTS
1
Ajay Adhikari2
ABSTRACT
Assessment of specific experience of the contractor through qualification criteria in bidding
documents plays a crucial role in the selection of qualified contractor. Prevailing procurement Act
and Regulation of the Government of Nepal requires that two items, i.e. projects of similar size
and nature and production capacity of key activities of the contractor are examined under this
criterion. Though, both the items have their own specific meanings, these are interpreted in many
ways as per the evaluator of different public entities. This paper tries to define the meanings of
both items and to briefly discuss about how these are interpreted in evaluation by public
organizations in Nepal. For this, example of technical evaluation in irrigation project has been
taken in this paper. It comes up with some suggestions to harmonize the meaning of these items
and their interpretation during evaluation for the selection of qualified contractors.
Keywords: Specific Experience Criteria, Project of Similar Size and Nature, Production Rate of
Key Activities (Key Production Rates).
INTRODUCTION
To get the construction project completed within stipulated quality, time and cost, it is most
essential that the work is contracted out to the capable contractor. Capability of contractors is
assessed during the procurement stage, which is based on the pre-set qualification criteria in
the bidding documents. In Nepal as per the prevailing rules, however, the contractor need not to
have any prior construction experience to take part in the procurement proceedings of works of
value up to NRs. 20 million. For more than NRs. 20 million, contractors should be qualified to
bid. Such qualifications are assessed as per the specific work experience criterion, besides
other criteria such as general construction experience, average annual turnover, cash flow
requirement and availability of personnel and equipment required for smooth execution of the
work (PPA, 2007).
Specific work experience criterion evaluates the qualification of the contractor using two items:
a) experience in the construction project of similar size and nature; and b) production capacity of
key construction activities (key production rate) (PPMO, 2014) and (PPMO, 2009). This criterion
plays significant role in selecting the qualified contractor. However, the author has observed that
its use in the selection of contractors in irrigation projects has not always been clear and
consistent. Many times, amendments to the specific experience mentioned in the bidding
documents are published. This has unnecessarily increased the number of bids submission
thereby increasing the time and resources employed in procurement proceedings. This paper
tries to briefly review the meaning and importance of two items under the specific work
experience criterion. It discusses on the practices of using it in irrigation projects in Nepal and
suggests some ways to using these items as per their essence. This paper comes up with the
conclusion that the qualitative and quantitative meaning of both the items, i.e. similar nature of
works and key production rate under the specific experience criterion have to be first well
understood and evaluated accordingly for the selection of qualified contractor.
METHODOLOGY OF THE STUDY
This study is based on the secondary and primary information. Meaning and importance of
similar nature of work and key production rate are defined first. Rates of some item works for the
1
Views expressed in this paper are personal.
2
Email: ajay3adhikari@gmail.com
2 of 8
construction of the irrigation project will be analyzed to review the requirements to be asked
under the item “project of similar size and nature”. Furthermore, key activities to be included and
the method of calculation of their production capacity under the item “key production rate” will be
discussed. This study has been carried out based on the discussion with procurement/ contract
management experts and analysis and judgment made by the author from his personal
experience.
PROJECT OF SIMILAR SIZE AND NATURE
General Instruction to Applicants (GITA) Section 4.8 (a) of standard Prequalification document
(PPMO, 2009) states that “the applicant shall provide evidence that it has successfully
completed or substantially completed at least the number of contracts stated in the Particular
Instruction to Applicants (PITA), of contract amount, nature, complexity, and requiring
construction technology similar to the proposed contract, within the time specified in the PITA.
The works may have been executed by the applicant as a prime contractor or as management
contractor, or as member of a joint venture or as subcontractor with reference being submitted
to confirm satisfactory performance”.
Under this item of specific work experience criterion, two basic properties, i.e. (i) the
characteristic and (ii) the cost of the project completed by the contractor are evaluated. Here, we
first discuss the characteristics of the project and later, the cost of the project mentioned under
the evaluation criteria of the bidding documents.
While assessing the technical qualification, bidding document requires that the contractor has
successfully completed similar nature of work. Here, similar nature of work refers to the similarity
in the nature, size, locality and employed technology of the completed project to the project to
be constructed for which bid has been invited. In case of any irrigation project, nature in terms of
surface or ground water project, size in terms of design discharge & command area, locality in
terms of Terai, Hill and Mountain project and requiring construction technology for furrow,
boarder, micro irrigation or for tunnel works should be evaluated under this criterion. Almost all
bidding documents for the construction of irrigation project in Nepal states which resembles to
the features of the project to be developed. However, many times there are modifications in
those statements. For e.g., criterion specific to construction of irrigation project in initial bidding
documents is amended to construction of any civil engineering works. This kind of amendment
provides opportunity for all contractors to bid even if they had no previous experience at all of
the construction of irrigation project and discourages the qualified contractor to participate in
bidding process. Furthermore, it deprives the employer of the qualified contractor selection.
Therefore, some suggestions, as examples, are made here for the statement of similarity to be
written in the bidding documents in case of the selection of contractors in irrigation project
construction in the Table 1:
Table 1: Nature of the Project and Similarity to be defined in the Bidding Document
Nature of Irrigation Project Similarity to be defined in the Bidding Document3
Construction of head works Construction of irrigation project head works
Construction of bridge
Construction of cross drainage structures of irrigation
project
Construction of Canal Construction canal
Construction of embankment for guide bund, road, railway
3
Size of the project of experience should be based on size of project to be constructed. However, it is
suggested that the size of completed project should never be less than 25% of size of the project to be
developed.
3 of 8
Nature of Irrigation Project Similarity to be defined in the Bidding Document3
Construction of cross
drainage structures
Construction of cross drainage structures of irrigation
projects
Construction of irrigation project head works
Construction of bridge
Construction of cross drainage structures of highway
project
All kind of irrigation project Above mentioned experience along with the experience in
similar terrain
It is required that such similarity of projects has to be approved by the head of department and
be circulated to the field offices. This eases the procurement proceedings in field offices where
capability of the personnel involved in public procurement is still questionable.
Another part of this item to be evaluated is contract amount. It requires that the completed
project of the contractor should be equal to or more than the amount as stated in the bidding
document. However, according to the definition of experience in similar nature and size of the
work, this is the technical criteria for contractor‟s selection. Applicant contractor must have
experience in the similar nature and size of the work, whatever the form of association to the
completed project. Since this is the technical qualification criteria, the term „contract amount’
here is inconsistent to the essence of this criterion. Contract amount does not necessarily reflect
the nature and size of the project, since cost of the project is substantially differed by the
geographical location. Furthermore, PITA 4.8 (a) of Standard Prequalification Document
(PPMO, 2009) has not mentioned anything about the value of similar contracts completed,
except the time period of completion. This argument about the value of work is further discussed
here based on the rate analyses of item works of irrigation projects in Terai, Hill and Mountain.
Here, Kapilvastu, Surkhet and Darchula are taken as representative districts of Terai, Hill and
Mountain, respectively.
*NRs. refers to Nepalese Rupees
Figure 1 Cement Concreting of Foundations (as per Rate Analysis Norms of Department of
Irrigation, Nepal, Item 7.2)
Figure 1 shows rates of PCC item of two different concrete mixes for foundation works. In case
of PCC 1:3:6, unit rate (Nepalese Rupees per m3
) in Hill is 37.12% more than that in Terai
whereas unit rate in Mountain is 33.06% more than that in Hill. Furthermore, In case of PCC
1:2:4, unit rate in Hill is 33.47% more than that in Terai whereas unit rate in Mountain is 35.97%
more than that in Hill. This shows that higher the location of the project with respect to the
6,121.07
7,240.38
8,393.50
9,663.75
11,168.68
13,139.58
-
2,000
4,000
6,000
8,000
10,000
12,000
14,000
PCC 1:3:6, NRs./m3 PCC 1:2:4, NRs./m3
Kapilvastu (Terai) Surkhet (Hill) Darchula (Mountain)
4 of 8
altitude, higher will be the unit rate of item works. This shows that the unit rate of items of works
is higher in the mountains than in the hills and the Terai.
Figure 2 Cement Concreting of Superstructure (as per Rate Analysis Norms of Department
of Irrigation, Nepal, Item 7.4)
Same kind of rate analysis for item works has been carried out as shown in the Figure 2 for
cement concreting of superstructure, taking three concrete mixes, i.e. PCC 1:2:4, PCC 1:1.5:3,
PCC 1:1:2. Here, unit rate of PCC 1:2:4 in Hill is 42.68% more than that in Terai whereas unit
rate in mountain is 23.97% more than that in Hill. Similarly, unit rate of PCC 1:1.5:3 in Hill is
31.07% more than that in Terai whereas unit rate in mountain is 45.53% more than that in Hill.
Furthermore, unit rate of PCC 1:1:2 in Hill is 27.12% more than that in Terai whereas unit rate in
mountain is 42.29% more than that in Hill. Same conclusion as in the case of cement concreting
in foundation can be made here that the unit rate of items of works is more in the mountain
region than in the hills and the Terai.
Based on the unit rates of above work items, it is vividly clear that the costs of Terai, Hill and
Mountain irrigation projects with same nature, size and technology are different. As we move
from Terai through Hill and Mountain, rate of PCC is in increasing order. Such increment is due
mainly to increasing cost of the construction materials and labors as per the geographical
locations4
. If the value of completed work is taken in combination with the similar nature of work
criteria, Terai and/ or Hill irrigation project may be disqualified whereas hill and/ or Mountain
irrigation project is qualified even if projects‟ (located in Terai, Hill and Mountain) size, nature
and technology employed are same. Furthermore, assessing the financial management capacity
of the contractors through the cost of the completed project is not deemed appropriate, because
financial capacity is better evaluated through annual turnover, cash flow and bid capacity
criteria. It clearly shows that the contract amount makes the evaluation bias to the geographical
locations. To avoid this conflict, experience of the project in geographical location similar to the
project has to be included under this item. Geographical experience here assesses the
management capacity of the contractor in such locations. While doing so, some attributes of
geographical location have to be so signposted that the bidders get clear idea of this item of
evaluation criteria. Furthermore, value of the project has to be associated with experience of
similar geographical location to assure that such experience of the contractor is not of very small
value. For example, any contractor may have the experience of similar geographical location
with the project cost NRs. 2 million, whereas project to be constructed may be of value greater
than NRs. 1 billion. Therefore, the contract amount has to be so associated with geographical
4
Rates are presented in Annex 1
8,042.38 8,988.30
11,548.5411,474.75 11,780.75
14,680.7514,225.58
17,144.70
20,889.70
-
5,000
10,000
15,000
20,000
25,000
PCC 1:2:4, NRs./m3 PCC 1:1.5:3, NRs./m3 PCC 1:1:2, NRs./m3
Kapilvastu (Terai) Surkhet (Hill) Darchula (Mountain)
5 of 8
location in a proper manner that technical qualification is only the governing factor thereby
fulfilling the essence of similar nature and size of the project criteria.
PRODUCTION RATES OF KEY ACTIVITIES
Key production rate, another item to be assessed under the specific experience criteria, is the
productivity as a ratio of output produced and with respect to time devoted for production.
According to the definition of (Hanna & Heale, 1994), number of units produced over a given
period of time divided by the number of man-hours to do so is the productivity. According to this
concept, key production rate refers to the managerial capacity of the contractor to accomplish a
job, provided the inputs are available5
. Input factors basically constitutes materials purchased,
equipment hired and labors employed to produce output in the form of products or structure in
case of construction industry. Evaluation criteria have been set in the standard procurement
documents of PPMO in Nepal which are modified in the bidding documents by the public entity
according to the need of the project.
Section 4.8 (b) of GITA of Standard PQ documents requires an experience of achieved
minimum monthly or annual working capacity in the form of production rates as specified in the
PITA of the same document. Many public entities have made decisions by allocating key
production capacity to the contractor as per their joint venture share in a completed project.
However, definition of key production rate emphasizes the need of managerial capacity of the
contractor to mobilize labor and equipment for the efficient use of other input factors of
production. Being a managerial capacity, key production rate has to be considered as a
qualitative capacity of the contractor. Therefore, experience of key production rate could not be
divided among each partner as per their share in case of joint venture agreement and has to be
taken 100% for all partners. This is substantiated by the decision made by the PPMO, dated 1
May 2014. Key production rate is significant item for the selection of contractor in countries like
Nepal, where performance of contractor with respect to completion time is not satisfactory.
Other issues under this criterion are the items for the evaluation of key production capacity of
the contractor to be included in bidding documents and method of calculation of key production
capacity of the contractor from the experience certificate submitted along with the bid.
In general, it is observed that a bidding document of the project involving reinforced concrete
structure demands for reinforcement in terms of tonnes/ month, which is calculated by dividing
total quantity of reinforcement to be used in the project by total project period. Here, we need to
understand that the key production rate is the capacity of the contractor for the production of
structure by using construction materials and not merely the capacity of supplying such material.
Keeping reinforcement item under the key production rate criterion only assesses the capacity of
the contractor of buying/ supplying reinforcement, which is not the essence of this criterion. So,
only those items which are produced by the contractor himself have to be included in this
criterion.
Furthermore, key production rate itself implies to the rate of production of part or whole of the
structure. Items to be produced/ constructed by the contractor are assessed here. In practice,
total quantity of the production of any item work is divided by the total project period in terms of
month to compute production rate of item work per month. Quantity and the project period as
per the estimate are used to mention required key production rates under evaluation criteria in
the bidding document. Similarly, to assess the production capacity of the contractor, total
quantity of the item work done is divided by the whole project period which is taken from the
project completion certificate issued by the employer. This method of computation implies that
the item work is executed throughout the project period, which is basically wrong. So,
requirement of key production rates in bidding documents should be calculated based on the
volume of item work and time to be devoted to execute it. Work schedule in this regard could be
5
Availability of the input factors is addressed in other clauses of contract document.
6 of 8
very useful. Furthermore, project completion certificate issued in the name of the contractor
should clearly mention the volume of work executed along with the time period devoted for it.
CONCLUSION
Similar experience criterion has been proved to be very much useful in qualified contractor
selection so far. Under this, experience of the contractor in the project of similar size and nature
and production capacity of key construction activities are assessed as per the requirements
mentioned in the bidding documents. To maintain consistency in evaluation of similar nature of
work for the selection of qualified contractor, it would be very much necessary to list out what
kind of project experience a contractor should have to be qualified. Contract amount in case of
project of similar nature and size is not suitable as it is biased as per the geographical locations
of the project. Rather, it is suggested that criteria should include the experience of the contractor
in the project of similar size and nature on the one hand and on the other hand, experience in
any civil engineering project of appropriate value in the similar terrain. Furthermore, production
capacity in key construction activities should be evaluated on qualitative basis and not be
divided proportionately based on the joint venture share. It should always be kept in mind during
the preparation of bidding document that key production rates need the production capacity of
the contractor for the construction of new structure, but not supplying the construction material.
Hence, only the required items under this criterion should be kept in the bidding documents.
While calculating key production rate, either as a requirement of the new project or the
experience of the contractor, it should be based on the volume to be executed and actual time to
be devoted for this execution. Use of project schedule is of high importance in this regard. Both
criteria represent qualitative as well as quantitative assessment of the contractor. Thus,
straightforward valuation and quantification of such experience in a mechanical manner have to
be avoided, rather qualitative and quantitative assessments have to be carried out as explained
in this paper for the selection of the qualified contractor.
7 of 8
REFERENCES
Hanna, A., & Heale, D. (1994). Factors affecting construction productivity: Newfoundland versus
rest of Canada. Canadian Journal of Civil Engineering, Vol. 21, 663-673.
PPA. (2007). Public Procurement Act. Kathmandu: Government of Nepal.
PPMO. (2009). Standard Prequalification Document. Kathmandu: Public Procurement
Monitoring Office.
PPMO. (2014). Standard Bidding Document (for above NRs. 6 million). Kathmandu: Public
Procurement Monitoring Office.
8 of 8
ANNEX 1: RATES OF LABOR AND CONSTRUCTION MATERIAL AT DISTRICT HEADQUARTERS
S.N. Material/ Labor Unit
Unit Rate for FY 2071-72, NRs.
Remarks
Kapilvastu Surkhet Darchula
Materials
1 Cement 43 grade (Nepali Cement)* mt. 12,200.00 14,000.00 18,500.00
2 Aggregates (from Crusher)**
40 mm m3
1,587.94 2,300.00 3,600.00
20 mm m3
1,587.94 2,400.00 6,000.00
10 mm m3
1,411.50 2,600.00 7,000.00
3 Coarse Sand m3
710.21 2,750.00 2,444.00
Labor
4 Skilled Labor m-day 490.00 550.00 570.00
5 Unskilled Labor m-day 300.00 350.00 400.00
Notes:
* 43 grade Nepali Cement has been taken for analysis due to availability of only this rate in Darchula
district
** Crusher Aggregates has been taken for analysis due to availability of only this rate in Darchula
district

More Related Content

What's hot

Ethics and Integated Design-Build services 062916
Ethics and Integated Design-Build services 062916Ethics and Integated Design-Build services 062916
Ethics and Integated Design-Build services 062916
George Wilkinson
 
Professional practice-1-presentation
Professional practice-1-presentationProfessional practice-1-presentation
Professional practice-1-presentation
Timun Loh
 
03 e measurement book-ver-1.0
03 e measurement book-ver-1.003 e measurement book-ver-1.0
03 e measurement book-ver-1.0
Amulie Jarjusey
 
Tendering in Construction
Tendering in ConstructionTendering in Construction
Tendering in Construction
shillier38
 
Professional Practice I Assignment
Professional Practice I AssignmentProfessional Practice I Assignment
Professional Practice I Assignment
ashleyyeap
 
Cv of Shadrul with Pic
Cv of Shadrul with PicCv of Shadrul with Pic
Cv of Shadrul with Pic
Shadrul Hasan
 
Procurement Strategies: A Seminar
Procurement Strategies: A SeminarProcurement Strategies: A Seminar
Procurement Strategies: A Seminar
Pang Khai Shuen
 

What's hot (20)

Alternative Contractual Models of Dredging Projects to Avoid Disputes (A Case...
Alternative Contractual Models of Dredging Projects to Avoid Disputes (A Case...Alternative Contractual Models of Dredging Projects to Avoid Disputes (A Case...
Alternative Contractual Models of Dredging Projects to Avoid Disputes (A Case...
 
Ethics and Integated Design-Build services 062916
Ethics and Integated Design-Build services 062916Ethics and Integated Design-Build services 062916
Ethics and Integated Design-Build services 062916
 
Pp1 final
Pp1 finalPp1 final
Pp1 final
 
Professional practice-1-presentation
Professional practice-1-presentationProfessional practice-1-presentation
Professional practice-1-presentation
 
03 e measurement book-ver-1.0
03 e measurement book-ver-1.003 e measurement book-ver-1.0
03 e measurement book-ver-1.0
 
Tendering in Construction
Tendering in ConstructionTendering in Construction
Tendering in Construction
 
Professional Practice 1 Assignment
Professional Practice 1 AssignmentProfessional Practice 1 Assignment
Professional Practice 1 Assignment
 
Pp1 assignment
Pp1 assignmentPp1 assignment
Pp1 assignment
 
Purpose
PurposePurpose
Purpose
 
Professional Practice I Assignment
Professional Practice I AssignmentProfessional Practice I Assignment
Professional Practice I Assignment
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1
 
Cv of Shadrul with Pic
Cv of Shadrul with PicCv of Shadrul with Pic
Cv of Shadrul with Pic
 
Resume111
Resume111Resume111
Resume111
 
“Investigation of Time-Cost Effectiveness on Construction Projects”
“Investigation of Time-Cost Effectiveness on Construction Projects”“Investigation of Time-Cost Effectiveness on Construction Projects”
“Investigation of Time-Cost Effectiveness on Construction Projects”
 
Chapter 2- Contract Management
Chapter 2- Contract ManagementChapter 2- Contract Management
Chapter 2- Contract Management
 
DESIGN & BUILD
DESIGN & BUILDDESIGN & BUILD
DESIGN & BUILD
 
Kona Rao -2015
Kona Rao  -2015Kona Rao  -2015
Kona Rao -2015
 
Procurement Strategies: A Seminar
Procurement Strategies: A SeminarProcurement Strategies: A Seminar
Procurement Strategies: A Seminar
 
Role of PMC in Construction of Collector Well Project, a Case Study
Role of PMC in Construction of Collector Well Project, a Case StudyRole of PMC in Construction of Collector Well Project, a Case Study
Role of PMC in Construction of Collector Well Project, a Case Study
 
cv.dchand copy
cv.dchand copycv.dchand copy
cv.dchand copy
 

Viewers also liked

мой класс
мой классмой класс
мой класс
SOSRuslana
 
New microsoft office word document
New microsoft office word documentNew microsoft office word document
New microsoft office word document
Aji Santoso
 
Analytic hierarchy process
Analytic hierarchy processAnalytic hierarchy process
Analytic hierarchy process
Ujjwal 'Shanu'
 

Viewers also liked (19)

@ Symbol
@ Symbol@ Symbol
@ Symbol
 
Sruthy
SruthySruthy
Sruthy
 
мой класс
мой классмой класс
мой класс
 
Walter Hurst - Sabbioneta, Italy, An Intersection of Shakespeare, A Midsummer...
Walter Hurst - Sabbioneta, Italy, An Intersection of Shakespeare, A Midsummer...Walter Hurst - Sabbioneta, Italy, An Intersection of Shakespeare, A Midsummer...
Walter Hurst - Sabbioneta, Italy, An Intersection of Shakespeare, A Midsummer...
 
Ethics in public procurement
Ethics in public procurementEthics in public procurement
Ethics in public procurement
 
New microsoft office word document
New microsoft office word documentNew microsoft office word document
New microsoft office word document
 
Air Pollution- Causes
Air Pollution- CausesAir Pollution- Causes
Air Pollution- Causes
 
Colours: Learn and enjoy
Colours: Learn and enjoyColours: Learn and enjoy
Colours: Learn and enjoy
 
Online assignment
Online assignmentOnline assignment
Online assignment
 
Volcano.ppt
Volcano.pptVolcano.ppt
Volcano.ppt
 
Earthquakes
EarthquakesEarthquakes
Earthquakes
 
Ascites in domestic animals
Ascites in domestic animalsAscites in domestic animals
Ascites in domestic animals
 
Past tense vs past continuous edited
Past tense vs past continuous editedPast tense vs past continuous edited
Past tense vs past continuous edited
 
Ascariasis in domestic animals
Ascariasis in domestic animalsAscariasis in domestic animals
Ascariasis in domestic animals
 
Cp 2 selection of contractor - pq and post q
Cp 2 selection of contractor - pq and post qCp 2 selection of contractor - pq and post q
Cp 2 selection of contractor - pq and post q
 
Using the Analytic Hierarchy Process (AHP) to Select and Prioritize Project...
Using the Analytic Hierarchy Process  (AHP) to Select and Prioritize  Project...Using the Analytic Hierarchy Process  (AHP) to Select and Prioritize  Project...
Using the Analytic Hierarchy Process (AHP) to Select and Prioritize Project...
 
Ahp
AhpAhp
Ahp
 
Analytic hierarchy process
Analytic hierarchy processAnalytic hierarchy process
Analytic hierarchy process
 
Contractor Prequalification Presentation
Contractor Prequalification PresentationContractor Prequalification Presentation
Contractor Prequalification Presentation
 

Similar to Specific experience criteria in contractor selection

Analysis of factors contributing delays and claims in construction projects
Analysis of factors contributing delays and claims in construction projectsAnalysis of factors contributing delays and claims in construction projects
Analysis of factors contributing delays and claims in construction projects
eSAT Journals
 
Analysis of factors contributing delays and claims in construction projects
Analysis of factors contributing delays and claims in construction projectsAnalysis of factors contributing delays and claims in construction projects
Analysis of factors contributing delays and claims in construction projects
eSAT Journals
 
CE-545_Fall 2015_TPG_03_Final_Report
CE-545_Fall 2015_TPG_03_Final_ReportCE-545_Fall 2015_TPG_03_Final_Report
CE-545_Fall 2015_TPG_03_Final_Report
Muhammad Daniyal
 

Similar to Specific experience criteria in contractor selection (20)

IRJET- Comperative Analysis of Three Major Type of Contracts with Case Study
IRJET- Comperative Analysis of Three Major Type of Contracts with Case StudyIRJET- Comperative Analysis of Three Major Type of Contracts with Case Study
IRJET- Comperative Analysis of Three Major Type of Contracts with Case Study
 
IRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building ProjectIRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building Project
 
Alternative Contractual Models of Dredging Projects to Avoid Disputes (A Case...
Alternative Contractual Models of Dredging Projects to Avoid Disputes (A Case...Alternative Contractual Models of Dredging Projects to Avoid Disputes (A Case...
Alternative Contractual Models of Dredging Projects to Avoid Disputes (A Case...
 
IRJET- A Study on Factors Affecting Estimation of Construction Project
IRJET- A Study on Factors Affecting Estimation of Construction ProjectIRJET- A Study on Factors Affecting Estimation of Construction Project
IRJET- A Study on Factors Affecting Estimation of Construction Project
 
Preparation of bill sandeep
Preparation of bill sandeepPreparation of bill sandeep
Preparation of bill sandeep
 
Procurement principle towards effective management of construction projects
Procurement principle towards effective management of construction projectsProcurement principle towards effective management of construction projects
Procurement principle towards effective management of construction projects
 
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...
 
Bills of quantities
Bills of quantitiesBills of quantities
Bills of quantities
 
Analysis of factors contributing delays and claims in construction projects
Analysis of factors contributing delays and claims in construction projectsAnalysis of factors contributing delays and claims in construction projects
Analysis of factors contributing delays and claims in construction projects
 
Analysis of factors contributing delays and claims in construction projects
Analysis of factors contributing delays and claims in construction projectsAnalysis of factors contributing delays and claims in construction projects
Analysis of factors contributing delays and claims in construction projects
 
Analysis of factors contributing delays and claims in
Analysis of factors contributing delays and claims inAnalysis of factors contributing delays and claims in
Analysis of factors contributing delays and claims in
 
Vetting of cost estimates for an underconstruction nh project
Vetting of cost estimates for an underconstruction nh projectVetting of cost estimates for an underconstruction nh project
Vetting of cost estimates for an underconstruction nh project
 
Claims Management And Assessment Through Documentation
Claims Management And Assessment Through DocumentationClaims Management And Assessment Through Documentation
Claims Management And Assessment Through Documentation
 
CE-545_Fall 2015_TPG_03_Final_Report
CE-545_Fall 2015_TPG_03_Final_ReportCE-545_Fall 2015_TPG_03_Final_Report
CE-545_Fall 2015_TPG_03_Final_Report
 
Quality – cost trade off (qct) for contractor selection
Quality – cost trade off (qct) for contractor selectionQuality – cost trade off (qct) for contractor selection
Quality – cost trade off (qct) for contractor selection
 
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
 
Q130302108111
Q130302108111Q130302108111
Q130302108111
 
Measuring tendering and estimating for CBE
Measuring tendering and estimating for CBEMeasuring tendering and estimating for CBE
Measuring tendering and estimating for CBE
 
DYNAMICS OF GOVERNMENT CONTRACTING: PROPOSALS FOR EFFICIENCY AND SATISFACTION...
DYNAMICS OF GOVERNMENT CONTRACTING: PROPOSALS FOR EFFICIENCY AND SATISFACTION...DYNAMICS OF GOVERNMENT CONTRACTING: PROPOSALS FOR EFFICIENCY AND SATISFACTION...
DYNAMICS OF GOVERNMENT CONTRACTING: PROPOSALS FOR EFFICIENCY AND SATISFACTION...
 
Section 2 of Philippine Institute of Civil Engineers Manual
Section 2 of Philippine Institute of Civil Engineers ManualSection 2 of Philippine Institute of Civil Engineers Manual
Section 2 of Philippine Institute of Civil Engineers Manual
 

Recently uploaded

Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Christo Ananth
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
MsecMca
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
dharasingh5698
 
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Christo Ananth
 
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 

Recently uploaded (20)

Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineering
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
 

Specific experience criteria in contractor selection

  • 1. 1 of 8 SPECIFIC EXPERIENCE CRITERIA IN CONTRACTOR SELECTION: SOME UNATTENDED ASPECTS 1 Ajay Adhikari2 ABSTRACT Assessment of specific experience of the contractor through qualification criteria in bidding documents plays a crucial role in the selection of qualified contractor. Prevailing procurement Act and Regulation of the Government of Nepal requires that two items, i.e. projects of similar size and nature and production capacity of key activities of the contractor are examined under this criterion. Though, both the items have their own specific meanings, these are interpreted in many ways as per the evaluator of different public entities. This paper tries to define the meanings of both items and to briefly discuss about how these are interpreted in evaluation by public organizations in Nepal. For this, example of technical evaluation in irrigation project has been taken in this paper. It comes up with some suggestions to harmonize the meaning of these items and their interpretation during evaluation for the selection of qualified contractors. Keywords: Specific Experience Criteria, Project of Similar Size and Nature, Production Rate of Key Activities (Key Production Rates). INTRODUCTION To get the construction project completed within stipulated quality, time and cost, it is most essential that the work is contracted out to the capable contractor. Capability of contractors is assessed during the procurement stage, which is based on the pre-set qualification criteria in the bidding documents. In Nepal as per the prevailing rules, however, the contractor need not to have any prior construction experience to take part in the procurement proceedings of works of value up to NRs. 20 million. For more than NRs. 20 million, contractors should be qualified to bid. Such qualifications are assessed as per the specific work experience criterion, besides other criteria such as general construction experience, average annual turnover, cash flow requirement and availability of personnel and equipment required for smooth execution of the work (PPA, 2007). Specific work experience criterion evaluates the qualification of the contractor using two items: a) experience in the construction project of similar size and nature; and b) production capacity of key construction activities (key production rate) (PPMO, 2014) and (PPMO, 2009). This criterion plays significant role in selecting the qualified contractor. However, the author has observed that its use in the selection of contractors in irrigation projects has not always been clear and consistent. Many times, amendments to the specific experience mentioned in the bidding documents are published. This has unnecessarily increased the number of bids submission thereby increasing the time and resources employed in procurement proceedings. This paper tries to briefly review the meaning and importance of two items under the specific work experience criterion. It discusses on the practices of using it in irrigation projects in Nepal and suggests some ways to using these items as per their essence. This paper comes up with the conclusion that the qualitative and quantitative meaning of both the items, i.e. similar nature of works and key production rate under the specific experience criterion have to be first well understood and evaluated accordingly for the selection of qualified contractor. METHODOLOGY OF THE STUDY This study is based on the secondary and primary information. Meaning and importance of similar nature of work and key production rate are defined first. Rates of some item works for the 1 Views expressed in this paper are personal. 2 Email: ajay3adhikari@gmail.com
  • 2. 2 of 8 construction of the irrigation project will be analyzed to review the requirements to be asked under the item “project of similar size and nature”. Furthermore, key activities to be included and the method of calculation of their production capacity under the item “key production rate” will be discussed. This study has been carried out based on the discussion with procurement/ contract management experts and analysis and judgment made by the author from his personal experience. PROJECT OF SIMILAR SIZE AND NATURE General Instruction to Applicants (GITA) Section 4.8 (a) of standard Prequalification document (PPMO, 2009) states that “the applicant shall provide evidence that it has successfully completed or substantially completed at least the number of contracts stated in the Particular Instruction to Applicants (PITA), of contract amount, nature, complexity, and requiring construction technology similar to the proposed contract, within the time specified in the PITA. The works may have been executed by the applicant as a prime contractor or as management contractor, or as member of a joint venture or as subcontractor with reference being submitted to confirm satisfactory performance”. Under this item of specific work experience criterion, two basic properties, i.e. (i) the characteristic and (ii) the cost of the project completed by the contractor are evaluated. Here, we first discuss the characteristics of the project and later, the cost of the project mentioned under the evaluation criteria of the bidding documents. While assessing the technical qualification, bidding document requires that the contractor has successfully completed similar nature of work. Here, similar nature of work refers to the similarity in the nature, size, locality and employed technology of the completed project to the project to be constructed for which bid has been invited. In case of any irrigation project, nature in terms of surface or ground water project, size in terms of design discharge & command area, locality in terms of Terai, Hill and Mountain project and requiring construction technology for furrow, boarder, micro irrigation or for tunnel works should be evaluated under this criterion. Almost all bidding documents for the construction of irrigation project in Nepal states which resembles to the features of the project to be developed. However, many times there are modifications in those statements. For e.g., criterion specific to construction of irrigation project in initial bidding documents is amended to construction of any civil engineering works. This kind of amendment provides opportunity for all contractors to bid even if they had no previous experience at all of the construction of irrigation project and discourages the qualified contractor to participate in bidding process. Furthermore, it deprives the employer of the qualified contractor selection. Therefore, some suggestions, as examples, are made here for the statement of similarity to be written in the bidding documents in case of the selection of contractors in irrigation project construction in the Table 1: Table 1: Nature of the Project and Similarity to be defined in the Bidding Document Nature of Irrigation Project Similarity to be defined in the Bidding Document3 Construction of head works Construction of irrigation project head works Construction of bridge Construction of cross drainage structures of irrigation project Construction of Canal Construction canal Construction of embankment for guide bund, road, railway 3 Size of the project of experience should be based on size of project to be constructed. However, it is suggested that the size of completed project should never be less than 25% of size of the project to be developed.
  • 3. 3 of 8 Nature of Irrigation Project Similarity to be defined in the Bidding Document3 Construction of cross drainage structures Construction of cross drainage structures of irrigation projects Construction of irrigation project head works Construction of bridge Construction of cross drainage structures of highway project All kind of irrigation project Above mentioned experience along with the experience in similar terrain It is required that such similarity of projects has to be approved by the head of department and be circulated to the field offices. This eases the procurement proceedings in field offices where capability of the personnel involved in public procurement is still questionable. Another part of this item to be evaluated is contract amount. It requires that the completed project of the contractor should be equal to or more than the amount as stated in the bidding document. However, according to the definition of experience in similar nature and size of the work, this is the technical criteria for contractor‟s selection. Applicant contractor must have experience in the similar nature and size of the work, whatever the form of association to the completed project. Since this is the technical qualification criteria, the term „contract amount’ here is inconsistent to the essence of this criterion. Contract amount does not necessarily reflect the nature and size of the project, since cost of the project is substantially differed by the geographical location. Furthermore, PITA 4.8 (a) of Standard Prequalification Document (PPMO, 2009) has not mentioned anything about the value of similar contracts completed, except the time period of completion. This argument about the value of work is further discussed here based on the rate analyses of item works of irrigation projects in Terai, Hill and Mountain. Here, Kapilvastu, Surkhet and Darchula are taken as representative districts of Terai, Hill and Mountain, respectively. *NRs. refers to Nepalese Rupees Figure 1 Cement Concreting of Foundations (as per Rate Analysis Norms of Department of Irrigation, Nepal, Item 7.2) Figure 1 shows rates of PCC item of two different concrete mixes for foundation works. In case of PCC 1:3:6, unit rate (Nepalese Rupees per m3 ) in Hill is 37.12% more than that in Terai whereas unit rate in Mountain is 33.06% more than that in Hill. Furthermore, In case of PCC 1:2:4, unit rate in Hill is 33.47% more than that in Terai whereas unit rate in Mountain is 35.97% more than that in Hill. This shows that higher the location of the project with respect to the 6,121.07 7,240.38 8,393.50 9,663.75 11,168.68 13,139.58 - 2,000 4,000 6,000 8,000 10,000 12,000 14,000 PCC 1:3:6, NRs./m3 PCC 1:2:4, NRs./m3 Kapilvastu (Terai) Surkhet (Hill) Darchula (Mountain)
  • 4. 4 of 8 altitude, higher will be the unit rate of item works. This shows that the unit rate of items of works is higher in the mountains than in the hills and the Terai. Figure 2 Cement Concreting of Superstructure (as per Rate Analysis Norms of Department of Irrigation, Nepal, Item 7.4) Same kind of rate analysis for item works has been carried out as shown in the Figure 2 for cement concreting of superstructure, taking three concrete mixes, i.e. PCC 1:2:4, PCC 1:1.5:3, PCC 1:1:2. Here, unit rate of PCC 1:2:4 in Hill is 42.68% more than that in Terai whereas unit rate in mountain is 23.97% more than that in Hill. Similarly, unit rate of PCC 1:1.5:3 in Hill is 31.07% more than that in Terai whereas unit rate in mountain is 45.53% more than that in Hill. Furthermore, unit rate of PCC 1:1:2 in Hill is 27.12% more than that in Terai whereas unit rate in mountain is 42.29% more than that in Hill. Same conclusion as in the case of cement concreting in foundation can be made here that the unit rate of items of works is more in the mountain region than in the hills and the Terai. Based on the unit rates of above work items, it is vividly clear that the costs of Terai, Hill and Mountain irrigation projects with same nature, size and technology are different. As we move from Terai through Hill and Mountain, rate of PCC is in increasing order. Such increment is due mainly to increasing cost of the construction materials and labors as per the geographical locations4 . If the value of completed work is taken in combination with the similar nature of work criteria, Terai and/ or Hill irrigation project may be disqualified whereas hill and/ or Mountain irrigation project is qualified even if projects‟ (located in Terai, Hill and Mountain) size, nature and technology employed are same. Furthermore, assessing the financial management capacity of the contractors through the cost of the completed project is not deemed appropriate, because financial capacity is better evaluated through annual turnover, cash flow and bid capacity criteria. It clearly shows that the contract amount makes the evaluation bias to the geographical locations. To avoid this conflict, experience of the project in geographical location similar to the project has to be included under this item. Geographical experience here assesses the management capacity of the contractor in such locations. While doing so, some attributes of geographical location have to be so signposted that the bidders get clear idea of this item of evaluation criteria. Furthermore, value of the project has to be associated with experience of similar geographical location to assure that such experience of the contractor is not of very small value. For example, any contractor may have the experience of similar geographical location with the project cost NRs. 2 million, whereas project to be constructed may be of value greater than NRs. 1 billion. Therefore, the contract amount has to be so associated with geographical 4 Rates are presented in Annex 1 8,042.38 8,988.30 11,548.5411,474.75 11,780.75 14,680.7514,225.58 17,144.70 20,889.70 - 5,000 10,000 15,000 20,000 25,000 PCC 1:2:4, NRs./m3 PCC 1:1.5:3, NRs./m3 PCC 1:1:2, NRs./m3 Kapilvastu (Terai) Surkhet (Hill) Darchula (Mountain)
  • 5. 5 of 8 location in a proper manner that technical qualification is only the governing factor thereby fulfilling the essence of similar nature and size of the project criteria. PRODUCTION RATES OF KEY ACTIVITIES Key production rate, another item to be assessed under the specific experience criteria, is the productivity as a ratio of output produced and with respect to time devoted for production. According to the definition of (Hanna & Heale, 1994), number of units produced over a given period of time divided by the number of man-hours to do so is the productivity. According to this concept, key production rate refers to the managerial capacity of the contractor to accomplish a job, provided the inputs are available5 . Input factors basically constitutes materials purchased, equipment hired and labors employed to produce output in the form of products or structure in case of construction industry. Evaluation criteria have been set in the standard procurement documents of PPMO in Nepal which are modified in the bidding documents by the public entity according to the need of the project. Section 4.8 (b) of GITA of Standard PQ documents requires an experience of achieved minimum monthly or annual working capacity in the form of production rates as specified in the PITA of the same document. Many public entities have made decisions by allocating key production capacity to the contractor as per their joint venture share in a completed project. However, definition of key production rate emphasizes the need of managerial capacity of the contractor to mobilize labor and equipment for the efficient use of other input factors of production. Being a managerial capacity, key production rate has to be considered as a qualitative capacity of the contractor. Therefore, experience of key production rate could not be divided among each partner as per their share in case of joint venture agreement and has to be taken 100% for all partners. This is substantiated by the decision made by the PPMO, dated 1 May 2014. Key production rate is significant item for the selection of contractor in countries like Nepal, where performance of contractor with respect to completion time is not satisfactory. Other issues under this criterion are the items for the evaluation of key production capacity of the contractor to be included in bidding documents and method of calculation of key production capacity of the contractor from the experience certificate submitted along with the bid. In general, it is observed that a bidding document of the project involving reinforced concrete structure demands for reinforcement in terms of tonnes/ month, which is calculated by dividing total quantity of reinforcement to be used in the project by total project period. Here, we need to understand that the key production rate is the capacity of the contractor for the production of structure by using construction materials and not merely the capacity of supplying such material. Keeping reinforcement item under the key production rate criterion only assesses the capacity of the contractor of buying/ supplying reinforcement, which is not the essence of this criterion. So, only those items which are produced by the contractor himself have to be included in this criterion. Furthermore, key production rate itself implies to the rate of production of part or whole of the structure. Items to be produced/ constructed by the contractor are assessed here. In practice, total quantity of the production of any item work is divided by the total project period in terms of month to compute production rate of item work per month. Quantity and the project period as per the estimate are used to mention required key production rates under evaluation criteria in the bidding document. Similarly, to assess the production capacity of the contractor, total quantity of the item work done is divided by the whole project period which is taken from the project completion certificate issued by the employer. This method of computation implies that the item work is executed throughout the project period, which is basically wrong. So, requirement of key production rates in bidding documents should be calculated based on the volume of item work and time to be devoted to execute it. Work schedule in this regard could be 5 Availability of the input factors is addressed in other clauses of contract document.
  • 6. 6 of 8 very useful. Furthermore, project completion certificate issued in the name of the contractor should clearly mention the volume of work executed along with the time period devoted for it. CONCLUSION Similar experience criterion has been proved to be very much useful in qualified contractor selection so far. Under this, experience of the contractor in the project of similar size and nature and production capacity of key construction activities are assessed as per the requirements mentioned in the bidding documents. To maintain consistency in evaluation of similar nature of work for the selection of qualified contractor, it would be very much necessary to list out what kind of project experience a contractor should have to be qualified. Contract amount in case of project of similar nature and size is not suitable as it is biased as per the geographical locations of the project. Rather, it is suggested that criteria should include the experience of the contractor in the project of similar size and nature on the one hand and on the other hand, experience in any civil engineering project of appropriate value in the similar terrain. Furthermore, production capacity in key construction activities should be evaluated on qualitative basis and not be divided proportionately based on the joint venture share. It should always be kept in mind during the preparation of bidding document that key production rates need the production capacity of the contractor for the construction of new structure, but not supplying the construction material. Hence, only the required items under this criterion should be kept in the bidding documents. While calculating key production rate, either as a requirement of the new project or the experience of the contractor, it should be based on the volume to be executed and actual time to be devoted for this execution. Use of project schedule is of high importance in this regard. Both criteria represent qualitative as well as quantitative assessment of the contractor. Thus, straightforward valuation and quantification of such experience in a mechanical manner have to be avoided, rather qualitative and quantitative assessments have to be carried out as explained in this paper for the selection of the qualified contractor.
  • 7. 7 of 8 REFERENCES Hanna, A., & Heale, D. (1994). Factors affecting construction productivity: Newfoundland versus rest of Canada. Canadian Journal of Civil Engineering, Vol. 21, 663-673. PPA. (2007). Public Procurement Act. Kathmandu: Government of Nepal. PPMO. (2009). Standard Prequalification Document. Kathmandu: Public Procurement Monitoring Office. PPMO. (2014). Standard Bidding Document (for above NRs. 6 million). Kathmandu: Public Procurement Monitoring Office.
  • 8. 8 of 8 ANNEX 1: RATES OF LABOR AND CONSTRUCTION MATERIAL AT DISTRICT HEADQUARTERS S.N. Material/ Labor Unit Unit Rate for FY 2071-72, NRs. Remarks Kapilvastu Surkhet Darchula Materials 1 Cement 43 grade (Nepali Cement)* mt. 12,200.00 14,000.00 18,500.00 2 Aggregates (from Crusher)** 40 mm m3 1,587.94 2,300.00 3,600.00 20 mm m3 1,587.94 2,400.00 6,000.00 10 mm m3 1,411.50 2,600.00 7,000.00 3 Coarse Sand m3 710.21 2,750.00 2,444.00 Labor 4 Skilled Labor m-day 490.00 550.00 570.00 5 Unskilled Labor m-day 300.00 350.00 400.00 Notes: * 43 grade Nepali Cement has been taken for analysis due to availability of only this rate in Darchula district ** Crusher Aggregates has been taken for analysis due to availability of only this rate in Darchula district