Evaluating The Criteria for Contractors’ Selection and Bid
Evaluation
1,
Dwarika Puri , 2,
S.Tiwari
1,
P. G. Student, Department of Civil Engineering, Madhav Institute of Technology & science, Gwalior
2,
Prof., Department of Civil Engineering, Madhav Institute of Technology & science, Gwalior
ABSTRACT : Construction contractors have big influences upon projects and their successes. Therefore, it is
quite critical to select a qualified contractor in the process of construction management. A competent
construction contractor is one of the indispensable conditions of a proper process and completion of a
construction project. There are several theoretical frameworks or models applied in the evaluation of
contractors. And there are some practical criteria for selecting an appropriate contractor. This paper analyzed
the relevant theoretical methods for contractor evaluation and examined the actual criteria for the selection of
contractors.This study aims at identifying the criteria for selection of contractor and bid evaluation means by
which different emphases can be recommended to suit the requirements of clients and projects. The research
was conducted by sending a questionnaire to different project managers in India and had an exceptionally high
rate of response of 72%. The analysis led to some interesting findings that reflect on the current practice. The
paper is concerned with providing construction contractors with recommendations in pursuit of better
evaluation of construction bids both technically and financially.
I. INTRODUCTION
Construction project must be managed in an effective manner. The demands from clients and
competition have been growing rapidly (Crowley and Hancher, 1995). These challenges present a paradox.
Few of these demands directly contribute to the physical construction of the project, however, a failure to
properly manage them can lead to problems for the entire project and construction team. The selection of a
proper construction contractor increases chances of successful completion of a construction project (Alhazmi
and McCaffer, 2000). It can also fulfill the client goals, and keep the schedule of the cost, time and quality. So it
is extremely critical to select an appropriate contractor in the process of construction management.
The selection of construction contractors are very often conducted during tendering. Tendering
definitely gives a client a choice in awarding contract a company which proposes the lowest price and short
construction cycles, but usually they do not allow to precisely evaluate a tender. At the same time there are more
and more procedures in which the decision criterion of choosing a tender is the price. In recent years, most
clients made use of such a method. On the other hand, the research results show that the cheapest tenderers often
have problems with completing the project. Accepting the lowest price is the basic cause of the project
completion problems because very often lowering the price means lowering the quality. It is true in some cases.
The above conditions make that it is especially important to properly evaluate the contactor’s capabilities. We
analyzed in Selecting the most suitable contractor for a construction project is a crucial decision for owners and
project managers. Therefore, this paper aims at selection of construction project contractors with
recommendations about the suitable criteria for better evaluation of construction bids both technically and
financially. Furthermore, it provides practitioners working or intending to work in the North East with better
insight due to the common trends.
The objectives of this paper are as follows:
• Reviewing the various criteria used for contractors pre-qualification and bid evaluation.
• Identifying the criteria that are actually used to evaluate contractors’ pre-qualification and bids in India.
• Introducing some recommendations for enhancing the contractors’ selection process.
II. LITERATURE REVIEW
Contractor pre-qualification and bid evaluation procedures are currently used in many countries, and it
involve the development and wide consideration of necessary and sufficient decision criteria to evaluate the
overall suitability of contractors. The literature review discovered the existence of various criteria, types of
information and methods of assessment.
Evaluating The Criteria For Contractors…
www.ijesi.org 45 | Page
Hatush and Skitmore (1997 a) pointed that the tender system of basing decisions on the minimum price
has been used in New York since 1848 for highway and bridge tenders. The main idea of such a method was to
save financial resources and create equal competition for all contractors by lowest bid.Hatush and Skitmore
(1997 a) recognized five main elements that was common factors in the contractor selection process for each
and every one types of procurement arrangements. These are project packaging, invitation, prequalification,
short listing and bid evaluation.Hatush and Skitmore (1997a) identified pre-qualification as a pre-tender process
used to investigate and assess the capabilities of contractors, hence providing the client with a list of potential
contractors to invite to tender. Bid evaluation despite involves similar process it is different in two aspects; it
occurs at the post tender stage and it considers both bid amount and the contractors’ capabilities.Russel and
Skibiniewski (1988) defined bid evaluation as a decision-making process that involves the development and
wide consideration of necessary and sufficient decision criteria used to assess the contractors’ capabilities. It
requires knowledge and experience from the project manager in order to use the appropriate criteria to insure the
selection of the most suitable contractor technically and financially for the project (Hatush and Skitmore (1997a)
III. BID EVALUATION
Bid evaluatation according to Herbsman and Ellis (1992), amount to the ‘major’ criteria of cost, time,
and quality as measured by the bid amount, time of execution, and quality of previous work respectively. This
implies that the winning bid is fully responsive to the contract in addition to the bidder’s being sufficiently well
qualified to undertake the contract (Hardy, 1978). Bid evaluation is used to indicate the procedure for strategic
assessment to tender bids submitted by pre-qualified contractors. The strategy used for bid evaluation should
reflect the client’s objectives (Hardy, 1978). In addition, Herbsman and Ellis (1992) have also further project-
specific criteria, including safety, durability, security, and maintenance. More objective methods have been
proposed by Moselhi and Martinelli (1990) and Diekmann (1981) by means of multi-attribute utility techniques
for combining the bid price and contractor selection criteria. The evaluation of bids by multi-attribute methods
may encounter some difficulties when comparing different criteria measured by different scales. Hence various
ways have been suggested for combining criterion values into a single scale. Herbsman and Ellis (1992), on the
other hand, proposed a time/cost approach to determine the winning bid in the highway construction contracts.
By converting the contract time to cost, a straightforward comparison can be made on a single criterion. Finally,
Holt et al. (1993) combine their P2 and P3 score into a simple index by assigning 60% weighting for the P3
score and 40% to the P2 score.
Hence, it could be concluded that there is no consensus as yet on a common set of selection criteria for
contractor selection. Selection criteria may vary in emphasis according to the characteristics of the project.
The Selection of Construction Project Contractors :It is problematical to select a suitable contractor. Bid
evaluation is one of the major challenges that face owners and consultants in the public and private sectors. On
the other hand, there are objective means to gauge the ability of a contractor to properly manage the business
aspects of the construction project. Some models and frameworks have been created to evaluate contractors’
bids and select the most suitable one.
The Cost Consideration : Among all factors the main evaluation factor is cost or price consideration that may
affect the selection of a contractor. Although the lowest bidder system protects the public from improper
practices, it has certain disadvantages. These include unreasonable low bids either accidentally or deliberately or
unqualified contractor which cause extensive delay, cost overrun, quality problems and increased number of
disputes. Over the years some modification to the lowest bidder system were made, such as reasonable bidder,
public interest and prequalification list which open the door to other evaluation methods to be adopted instead of
the single criterion system lowest bidder system.
The TOPSIS and SAW-G Grey Techniques :The grey theory is a new technique for performing prediction,
relational analysis and decision-making in many areas. The grey theory techniques were applied for defining the
utility of an alternative. Proposed assessment model covers well known method of TOPSIS (Technique for
Order Preference by Similarity to Ideal Solution), method with attributes values determined at intervals
(TOPSIS-grey) and a method of Simple Additive Weighting with Grey relations (SAW-G). The methods of grey
relations methodology can be implemented as an effective decision aid for tasks with uncertain data.
Pre-Qualification and Bid Evaluation Criteria : To ensure the quality of contractors, the valuation can be
done beforehand with a prequalification method. Facing the owner’s scrutiny regarding its competency to
handle the business aspects of the operation during prequalification allows the contractor to focus on the
specifics of the construction project once it has passed through prequalification and been short-listed. This also
Evaluating The Criteria For Contractors…
www.ijesi.org 46 | Page
allows the owner’s bid evaluation team to focus only on the specific elements of the project, without being
distracted by the other business considerations. In the simplest meaning prequalification is a before tendering
procedure which allows to choose the most appropriate candidates from amongst those declaring willingness to
participate in the tendering. Prequalification is defined by Moore (1985) as the screening of construction
contractors by project owners or their representatives according to a predetermined set of criteria deemed
necessary for successful project performance, in order to determine the contractor’s competence or ability to
participate in the project bid. Clough (1986) thinks that prequalification means that the firm which wants to
participate in the tendering needs to be qualified before it can be issued bidding documents or before it can
submit a proposal.Pre-qualification and bid evaluation procedures involve different types of criterion to evaluate
the overall suitability of contractors such as: General, technical, managerial, and financial criteria (Hunt et al.,
1966); Financial stability, managerial capability and organizational strength, technical expertise and experience
of comparable construction (Merna and Smith, 1990); Relevance of experience, size of firm, and safety record
(Moselhi and Martinelli, 1990).
Hatush and Skitmore (1997a) have identified five main criteria for contractor prequalification and bid evaluation
along with the information necessary to assess these criteria as shown in Table (1).
Table 1: Main Criteria and Sub-criteria for Contractors’ Prequalification
and Bid Evaluation
Financial soundness
Financial stability.
Credit rating.
Banking arrangements and bonding.
Financial status.
Technical ability
Experience.
Plant and equipment.
Personnel.
Ability.
Management
capability
Past performance and quality.
Project management organization
Experience of technical personnel.
Management knowledge.
Health and safety
Safety.
Experience modification rating.
OSHA Incident rate.
Management safety accountability.
Reputation
Past failures.
Length of time in business.
Past owner/contractor relationship.
Other relationships.
Russel (1996) put forward some other simple contractor prequalification criteria. He distinguishes three
basic groups of criteria: _ Preliminary screening criteria (among others: references, reputation, past
performance, _ Constructor resources (financial, technical, status of current work program), _ Other items
(project specific criteria). Quite interesting are the criteria presented by the Palaneeswaran and Kumaraswamy
(2001). The following groups of criteria have been suggested: (1) Responsiveness, promptness, realism,
completeness. (2) Meeting deadlines, correctness and valid information, totality in providing information. (3)
Responsibility, obeying the law and complying with local government regulations, standards and bylaws,
quality system, safety system. (4) Competence, recourse (financial, machinery, plant and equipment, human
resources), experience, constraints (current workload, subcontracts, guarantees).
Information
It is necessary to collect and investigate information to quantify objectively the criteria for bid evaluation. This
information includes that relating to the (1)contractor’s permanent place of business; (2) capability of plant and
equipment to do the work properly and expeditiously; (3)suitability of financial capability to meet obligations
required by the work; (4)appropriateness of technical ability and experience; (5)adequate experience in similar
projects regarding type and size; (6) the current position of the contractor to perform the contract well; the
contractor’s relationship with subcontractors, or employees. In total, the information used for the assessment of
Evaluating The Criteria For Contractors…
www.ijesi.org 47 | Page
criteria for pre-qualification and bid evaluation falls into five groups: general information that is used mainly for
administrative purposes, financial information, technical information, managerial information, and safety
information (Hatush and Skitmore; 1997a).
Assessment :The information concerning to the criteria can be assessed in various ways. This can be done by
assigning a maximum point value for each used criterion. These values are then weighted to their relative
importance on the overall project delivery strategy. When a criterion is made up of sub-criteria, the weighed
value scores of the sub criteria are added to calculate the total value for the category. To avoid biases, it is
recommended that a minimum of three evaluators is required for each scoring activity.
Holt et al. (1993) have planned a modified quantitative model for selecting contractors. This model comprises a
three-stage process requiring the calculation of what is called P1 scale index to investigate the more general
areas surrounding potential bidders. A P2 scale index is calculated for the second stage to assess the contractor
further in the light of specific factors. Finally a P3 scale index is calculated to compare the bid prices amongst
the invited bidders.
The Construction Management at Risk Method : The Construction Management at Risk method was
introduced in the 1980s. Construction management at risk (CMAR) as a project delivery method was created to
provide input to the designer to increase constructability of designs and to decrease schedule duration through
overlapping of the design. Kknocherand Sanvido (1998) emphasized that the contractor usually has a significant
input in the design process. In general, CMAR creates a collaborative environment that uses the wisdom,
experience, and creativity of the architect and the CM.
Construction Management at Risk or CMAR is gaining popularity, especially in the construction of the large
projects such as schools, airports, and sports arenas.
The CMAR method aims to reduce the risk of cost overrun and schedule creep and to expedite the construction
process without compromising quality. The construction manager works with the designer as a team during the
design phase. There are some advantages to the owner from using the CMAR delivery method are-
[1] Risk is reduced for the architect and owner.
[2] Produce a more manageable and predictable project cost and schedule outcomes.
[3] Centralizes responsibilities.
[4] The owner benefits from the CM’s experience both during design and construction.
[5] Allow for an early start to construction by phasing the work.
[6] Results in better quality construction
The Multi Criteria Evaluation Models : It can be stated that contractor’s selection problem is a multi-criteria
problem in most cases. Many multi-criteria techniques are proposed and applied (Goicoechea et al. 1992,
Zavadskas et al. 2008). Skibniewski and Chao (1992), Banaitis and Banaitiene (2006), Mitkus and Trinkuniene
(2006), Ginevicius and Podvezko (2008), Turskis (2008) and Zavadskas et al. (2008), Plebankiewicz (2009)
investigated assessment of construction firms and contractors evaluation problems. There is a Multi Criteria
Bidding System which is an evaluation method that considers not only the cost as the awarding reason, but also
considers other important attributes. The key of Multi attributes system is that the selection process of the
contractors is based on more attributes such as, bid price or cost, time, quality, managerial safety accountability,
competence and sufficiency of contractors (Liu et al., 2000). The main concept of the Multi Attributes Bidding
System is that the selection process of the contractors will be based on more attributes than just the price, and
the successful bidder will be the one who has the highest combined bidding value of the multiple attributes. The
scores of those attributes are transformed into values and those values of all the attributes are totaled to give the
combined bidding value.
Some Actual Criteria for the Selection of Construction Project Contractors :In actuality, contractor
evaluation is regularly performed by industry professionals using their accumulated experience and judgment.
There are variations in the amount of effort expended in the process. An important step in evaluation is to
examine the contractor’s system for handling project information regarding work tasks. The contractor’s
approach to safety and what actions it takes to achieve desired results should be closely scrutinized.Many factors
should be considered during the contractors’ qualification screening. The following list includes most of the
components that should be examined when conducting a contractor qualification. (1) Financial standing, such as
financial stability, turnover, profit, obligations, amounts due, and owned financial funds. (2) Technical ability,
such as experience, plant and equipment, and personnel. (3) Management capability, such as past performance
and quality, quality control policy, quality management system, project management system, experience of
technical personnel, and management knowledge. (4) Quality, safety, senior management, including experience,
Evaluating The Criteria For Contractors…
www.ijesi.org 48 | Page
tenure with firm, and division of responsibilities. (5) Current projects/backlog, including number, size, and
location of projects, percent of capacity being utilized, and status and expected completion, past failures in
completed projects, number of years in construction, past client relationships and cooperation with contactors.
One way to collecting the data necessary to perform contractor evaluations is to conduct questionnaires. But in
this way, contractors will be tempted to answer in a way that puts them in the best light. For instance, one
commonly used questionnaire asks contractors if safety is a priority in their business.
IV. CONCLUSIONS
This paper proposed criteria to evaluate contractors and bid selection based on chosen criteria. The
objective of this paper is to deliver a completed project that serves the intentional function. Some clients may
choose to use just one of the criteria used to qualify a candidate to the stage of tendering procedure and it is
usually the contractor’s experience. Majority of studied clients evaluate contractor companies after having
completed their cooperation, they keep their data and also declare giving preferences for those companies with
which their cooperation was successful. This proves that they pay great attention to reliability and competence
of the contractors. One important step that can be taken to ensure project success in safety is to prequalify and
select only those contractors who are fully qualified by virtue of their safety programs and performance. A good
safety record reduces the cost of construction and helps to support the desired attitude toward quality and
productivity. Comprehensive contractor evaluations conducted prior to selection can significantly reduce the
risks faced by a construction project.
REFERENCES
[1] Alhazmi, T., & McCaffer, R. (2000). Project procurement system selection model. Journal of Construction Engineering and
Management, 126, 176–184.
[2] Banaitiene, Banaitis. (2006). Analysis of criteria for contractors’ qualification evaluation, Technological and Economic. Development
of Economy, 12(4), 276–282.Clough, R. (1986). Construction contracting. New York, NY, Wiley.
[3] Crowley, L., & Hancher, D. (1995). Risk assessment of competitive procurement. Journal of ConstructionEngineering and
Management, 121, 241–248.
[4] Ginevicius, R., & Podvezko, V. (2008). Multicriteria graphicalanalytical evaluation of the financial state of construction enterprises.
Technological and Economic Development of Economy, 14(4), 452–461.
[5] Goicoechea, A., Kenneth, H.M., & Edward, A.W. (1992). Multiple criteria decision making. In: Proceedings of the 9th International
Conference: Theory and Application in Business, Industry, and Government. Springer-Verlag, New York, USA.
[6] Hardy, S C (1978), Bid Evaluation Study for the World Bank, 1, University of Manchester
a. Institute of Science and Technology, UK.
[7] Hatush, Z., & Skitmore, M. (1997). Evaluating contractor prequalification data: selection criteria and project success factors.
Construction Management and Economics, 15: 129–147.
[8] Herbsman, Z and Ellis, R, (1992), Multi-parameter Bidding System-innovation in Contract Administration, Construction Engineering
and Management, 118(1), 142-150.
[9] Holt, G D, Olomolaiye, P O and Harris, F C (1993) A conceptual alternative to current tendering practice. Building Research and
Information, 21(3), 167-72.
[10] Merna, A and Smith, N J, (1990), Bid Evaluation for UK Public Sector Construction Contracts, Proceedings of the Institution of Civil
Engineers, Pt 1 88, Feb., 91-105.
[11] Moselhi, O and Martinelli, A (1990), Analysis of Bids Using Multi-attribute Utility Theory in Transactions, The International Council
for Construction Research Studies and documentation. CIB W-65, Sydney, Austalia, 335-345.
[12] Mitkus, S., & Trinkuniene, E. (2008). Reasoned decisions in construction contracts evaluation. Technological and Economic
Development of Economy, 14(3), 402–416.
[13] Moore, M. J. (1985). Selecting a contractor for fast-track projects: Part I, principles of contractor evaluation. Plant Engineering, 39,
74–75.
[14] Plebankiewicz, E. (2009). Contractor prequalification model using fuzzy sets. Journal of Civil Engineering and Management, 15(4),
377–385
[15] Russell, J. S. and Skibniewski, M. J. (1988), Decision Criteria in Contractor Pre-qualification, Journal of Management in Engineering,
ASCE, 4(2), 148-164.
[16] Skibniewski, M., & Chao, L. (1992). Evaluation of advanced construction technology with AHP method.
Journal of Construction Engineering and Management, ASCE, 118, 255–261.
[17] Turskis, Z. (2008). Multi-attribute contractors ranking method by applying ordering of feasible alternatives of solutions in terms of
preferability technique. Technological and Economic Development of Economy, 14(2), 224–239.
[18] Zavadskas, E. K., Liias, R., & Turskis, Z. (2008).
[19] Multi-attribute decision-making methods for assessment of quality in bridges and road construction: state-of-the-art surveys. The
Baltic Journal of Road and Bridge Engineering, 3(3), 152–160.

More Related Content

What's hot

Best value contracting
Best value contractingBest value contracting
Best value contractingahmed saeed
 
Guide to Construction Procurement Strategies
Guide to Construction Procurement StrategiesGuide to Construction Procurement Strategies
Guide to Construction Procurement StrategiesSarah Fox
 
time-cost-quality.pdf
time-cost-quality.pdftime-cost-quality.pdf
time-cost-quality.pdfsam26a
 
A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 Pang Khai Shuen
 
IRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building ProjectIRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building ProjectIRJET Journal
 
Towards Innovate Methods of Construction Cost Management and Control
Towards Innovate Methods of Construction Cost Management and ControlTowards Innovate Methods of Construction Cost Management and Control
Towards Innovate Methods of Construction Cost Management and Controlcivej
 
Professional practice 1 (QS)
Professional practice 1 (QS)Professional practice 1 (QS)
Professional practice 1 (QS)Hasif Alias
 
5.0 Subcontractor Selection Ass3 Sem2 '09
5.0 Subcontractor Selection Ass3 Sem2 '095.0 Subcontractor Selection Ass3 Sem2 '09
5.0 Subcontractor Selection Ass3 Sem2 '09Praveen Premkumar
 
Professional Practice 1 Assignment
Professional Practice 1 AssignmentProfessional Practice 1 Assignment
Professional Practice 1 AssignmentMelvin Lim
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1Lee Pei Gie
 
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...World-Academic Journal
 
Alternative Contractual Models of Dredging Projects to Avoid Disputes (A Case...
Alternative Contractual Models of Dredging Projects to Avoid Disputes (A Case...Alternative Contractual Models of Dredging Projects to Avoid Disputes (A Case...
Alternative Contractual Models of Dredging Projects to Avoid Disputes (A Case...theijes
 
Lecture 1 introduction to construction procurement process.
Lecture 1   introduction to construction procurement process.Lecture 1   introduction to construction procurement process.
Lecture 1 introduction to construction procurement process.Aszahari Aie
 
Winning tenders / securing tenderers in a competitive construction market - N...
Winning tenders / securing tenderers in a competitive construction market - N...Winning tenders / securing tenderers in a competitive construction market - N...
Winning tenders / securing tenderers in a competitive construction market - N...Browne Jacobson LLP
 
Pp 1-report-complete
Pp 1-report-completePp 1-report-complete
Pp 1-report-completeYong Sy
 
Professional practice-1-presentation
Professional practice-1-presentationProfessional practice-1-presentation
Professional practice-1-presentationTimun Loh
 

What's hot (20)

Purpose
PurposePurpose
Purpose
 
Procurement system
Procurement systemProcurement system
Procurement system
 
Best value contracting
Best value contractingBest value contracting
Best value contracting
 
Guide to Construction Procurement Strategies
Guide to Construction Procurement StrategiesGuide to Construction Procurement Strategies
Guide to Construction Procurement Strategies
 
time-cost-quality.pdf
time-cost-quality.pdftime-cost-quality.pdf
time-cost-quality.pdf
 
A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1
 
IRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building ProjectIRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building Project
 
Towards Innovate Methods of Construction Cost Management and Control
Towards Innovate Methods of Construction Cost Management and ControlTowards Innovate Methods of Construction Cost Management and Control
Towards Innovate Methods of Construction Cost Management and Control
 
Professional practice 1 (QS)
Professional practice 1 (QS)Professional practice 1 (QS)
Professional practice 1 (QS)
 
5.0 Subcontractor Selection Ass3 Sem2 '09
5.0 Subcontractor Selection Ass3 Sem2 '095.0 Subcontractor Selection Ass3 Sem2 '09
5.0 Subcontractor Selection Ass3 Sem2 '09
 
Professional Practice 1 Assignment
Professional Practice 1 AssignmentProfessional Practice 1 Assignment
Professional Practice 1 Assignment
 
Procurement Methods
Procurement MethodsProcurement Methods
Procurement Methods
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1
 
Procurement- Contract Management
Procurement- Contract ManagementProcurement- Contract Management
Procurement- Contract Management
 
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
 
Alternative Contractual Models of Dredging Projects to Avoid Disputes (A Case...
Alternative Contractual Models of Dredging Projects to Avoid Disputes (A Case...Alternative Contractual Models of Dredging Projects to Avoid Disputes (A Case...
Alternative Contractual Models of Dredging Projects to Avoid Disputes (A Case...
 
Lecture 1 introduction to construction procurement process.
Lecture 1   introduction to construction procurement process.Lecture 1   introduction to construction procurement process.
Lecture 1 introduction to construction procurement process.
 
Winning tenders / securing tenderers in a competitive construction market - N...
Winning tenders / securing tenderers in a competitive construction market - N...Winning tenders / securing tenderers in a competitive construction market - N...
Winning tenders / securing tenderers in a competitive construction market - N...
 
Pp 1-report-complete
Pp 1-report-completePp 1-report-complete
Pp 1-report-complete
 
Professional practice-1-presentation
Professional practice-1-presentationProfessional practice-1-presentation
Professional practice-1-presentation
 

Viewers also liked

Mbs hot digital tips presentation slideshare
Mbs hot digital tips presentation slideshareMbs hot digital tips presentation slideshare
Mbs hot digital tips presentation slideshareMark Muggeridge
 
Nvh flyer apr 2011 final1
Nvh flyer apr 2011 final1Nvh flyer apr 2011 final1
Nvh flyer apr 2011 final1alangrinnell
 
вх об утв. порядка изм.типа авт.учр
вх об утв. порядка изм.типа авт.учрвх об утв. порядка изм.типа авт.учр
вх об утв. порядка изм.типа авт.учрnslipina
 
iTRADE presentation 12 May, 2010
iTRADE presentation 12 May, 2010iTRADE presentation 12 May, 2010
iTRADE presentation 12 May, 2010guest72edb4
 
Properties of Water
Properties of WaterProperties of Water
Properties of Waterlegoscience
 
Pony对Qq Mail的邮件摘录
Pony对Qq Mail的邮件摘录Pony对Qq Mail的邮件摘录
Pony对Qq Mail的邮件摘录eRay Jiang
 
Skagen global noviembre 14
Skagen global noviembre 14Skagen global noviembre 14
Skagen global noviembre 14Frank Ragol
 

Viewers also liked (10)

Mbs hot digital tips presentation slideshare
Mbs hot digital tips presentation slideshareMbs hot digital tips presentation slideshare
Mbs hot digital tips presentation slideshare
 
лососевые
лососевыелососевые
лососевые
 
Nvh flyer apr 2011 final1
Nvh flyer apr 2011 final1Nvh flyer apr 2011 final1
Nvh flyer apr 2011 final1
 
вх об утв. порядка изм.типа авт.учр
вх об утв. порядка изм.типа авт.учрвх об утв. порядка изм.типа авт.учр
вх об утв. порядка изм.типа авт.учр
 
iTRADE presentation 12 May, 2010
iTRADE presentation 12 May, 2010iTRADE presentation 12 May, 2010
iTRADE presentation 12 May, 2010
 
Properties of Water
Properties of WaterProperties of Water
Properties of Water
 
Chicas Nfl
Chicas NflChicas Nfl
Chicas Nfl
 
Pony对Qq Mail的邮件摘录
Pony对Qq Mail的邮件摘录Pony对Qq Mail的邮件摘录
Pony对Qq Mail的邮件摘录
 
Skagen global noviembre 14
Skagen global noviembre 14Skagen global noviembre 14
Skagen global noviembre 14
 
моє життя
моє життямоє життя
моє життя
 

Similar to I0372044048

Construction Contract Relationships Presentation.pptx
Construction Contract Relationships Presentation.pptxConstruction Contract Relationships Presentation.pptx
Construction Contract Relationships Presentation.pptxIsmailFakhro1
 
Analysis of Optimum Bid and Contractor’s Effort in Obtaining Profit
Analysis of Optimum Bid and Contractor’s Effort in Obtaining ProfitAnalysis of Optimum Bid and Contractor’s Effort in Obtaining Profit
Analysis of Optimum Bid and Contractor’s Effort in Obtaining ProfitAI Publications
 
Study on Procurement Method Selection Procedure in Construction Industry
Study on Procurement Method Selection Procedure in Construction IndustryStudy on Procurement Method Selection Procedure in Construction Industry
Study on Procurement Method Selection Procedure in Construction IndustryIRJET Journal
 
IRJET- Decision Making in Construction Management using AHP and Expert Choice...
IRJET- Decision Making in Construction Management using AHP and Expert Choice...IRJET- Decision Making in Construction Management using AHP and Expert Choice...
IRJET- Decision Making in Construction Management using AHP and Expert Choice...IRJET Journal
 
Towards Innovate Methods of Construction Cost Management and Control
Towards Innovate Methods of Construction Cost Management and ControlTowards Innovate Methods of Construction Cost Management and Control
Towards Innovate Methods of Construction Cost Management and Controlcivejjour
 
Cost Based Consultant Evaluation and Selection under FIDIC QCBS 1st Edt - Wit...
Cost Based Consultant Evaluation and Selection under FIDIC QCBS 1st Edt - Wit...Cost Based Consultant Evaluation and Selection under FIDIC QCBS 1st Edt - Wit...
Cost Based Consultant Evaluation and Selection under FIDIC QCBS 1st Edt - Wit...ssusered96e2
 
A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...
  A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...  A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...
A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...IAEME Publication
 
Study of Influencing Factors of Tender Evaluation: An Evidential Reasoning Ap...
Study of Influencing Factors of Tender Evaluation: An Evidential Reasoning Ap...Study of Influencing Factors of Tender Evaluation: An Evidential Reasoning Ap...
Study of Influencing Factors of Tender Evaluation: An Evidential Reasoning Ap...IJORCS
 
A Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project ManagementA Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project Managementijsrd.com
 
IRJET- Decision Making in Construction Management using AHP and Expert Ch...
IRJET-  	  Decision Making in Construction Management using AHP and Expert Ch...IRJET-  	  Decision Making in Construction Management using AHP and Expert Ch...
IRJET- Decision Making in Construction Management using AHP and Expert Ch...IRJET Journal
 
IRJET- The Systematic Procedure to Sort Out Contractor in Construction Field
IRJET- The Systematic Procedure to Sort Out Contractor in Construction FieldIRJET- The Systematic Procedure to Sort Out Contractor in Construction Field
IRJET- The Systematic Procedure to Sort Out Contractor in Construction FieldIRJET Journal
 
AN APPRAISAL OF VALUE ENGINEERING AND THE AWARENESS LEVEL AMONGST NIGERIAN CO...
AN APPRAISAL OF VALUE ENGINEERING AND THE AWARENESS LEVEL AMONGST NIGERIAN CO...AN APPRAISAL OF VALUE ENGINEERING AND THE AWARENESS LEVEL AMONGST NIGERIAN CO...
AN APPRAISAL OF VALUE ENGINEERING AND THE AWARENESS LEVEL AMONGST NIGERIAN CO...Babatunde55
 
Utilitas mathematica
Utilitas mathematicaUtilitas mathematica
Utilitas mathematicarikaseorika
 
mathematica journal
mathematica journal mathematica journal
mathematica journal rikaseorika
 

Similar to I0372044048 (20)

Construction Contract Relationships Presentation.pptx
Construction Contract Relationships Presentation.pptxConstruction Contract Relationships Presentation.pptx
Construction Contract Relationships Presentation.pptx
 
Tendering-professional practices-jamia millia islamia
Tendering-professional practices-jamia millia islamiaTendering-professional practices-jamia millia islamia
Tendering-professional practices-jamia millia islamia
 
Analysis of Optimum Bid and Contractor’s Effort in Obtaining Profit
Analysis of Optimum Bid and Contractor’s Effort in Obtaining ProfitAnalysis of Optimum Bid and Contractor’s Effort in Obtaining Profit
Analysis of Optimum Bid and Contractor’s Effort in Obtaining Profit
 
Study on Procurement Method Selection Procedure in Construction Industry
Study on Procurement Method Selection Procedure in Construction IndustryStudy on Procurement Method Selection Procedure in Construction Industry
Study on Procurement Method Selection Procedure in Construction Industry
 
IRJET- Decision Making in Construction Management using AHP and Expert Choice...
IRJET- Decision Making in Construction Management using AHP and Expert Choice...IRJET- Decision Making in Construction Management using AHP and Expert Choice...
IRJET- Decision Making in Construction Management using AHP and Expert Choice...
 
Research-Cycle-Group
Research-Cycle-GroupResearch-Cycle-Group
Research-Cycle-Group
 
Towards Innovate Methods of Construction Cost Management and Control
Towards Innovate Methods of Construction Cost Management and ControlTowards Innovate Methods of Construction Cost Management and Control
Towards Innovate Methods of Construction Cost Management and Control
 
Cost Based Consultant Evaluation and Selection under FIDIC QCBS 1st Edt - Wit...
Cost Based Consultant Evaluation and Selection under FIDIC QCBS 1st Edt - Wit...Cost Based Consultant Evaluation and Selection under FIDIC QCBS 1st Edt - Wit...
Cost Based Consultant Evaluation and Selection under FIDIC QCBS 1st Edt - Wit...
 
Ijciet 08 02_005
Ijciet 08 02_005Ijciet 08 02_005
Ijciet 08 02_005
 
A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...
  A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...  A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...
A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...
 
Study of Influencing Factors of Tender Evaluation: An Evidential Reasoning Ap...
Study of Influencing Factors of Tender Evaluation: An Evidential Reasoning Ap...Study of Influencing Factors of Tender Evaluation: An Evidential Reasoning Ap...
Study of Influencing Factors of Tender Evaluation: An Evidential Reasoning Ap...
 
Thesis proposal
Thesis proposalThesis proposal
Thesis proposal
 
Dariusz Koba, Poland, third regional conference on public procurement for ENP...
Dariusz Koba, Poland, third regional conference on public procurement for ENP...Dariusz Koba, Poland, third regional conference on public procurement for ENP...
Dariusz Koba, Poland, third regional conference on public procurement for ENP...
 
A Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project ManagementA Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project Management
 
IRJET- Decision Making in Construction Management using AHP and Expert Ch...
IRJET-  	  Decision Making in Construction Management using AHP and Expert Ch...IRJET-  	  Decision Making in Construction Management using AHP and Expert Ch...
IRJET- Decision Making in Construction Management using AHP and Expert Ch...
 
IRJET- The Systematic Procedure to Sort Out Contractor in Construction Field
IRJET- The Systematic Procedure to Sort Out Contractor in Construction FieldIRJET- The Systematic Procedure to Sort Out Contractor in Construction Field
IRJET- The Systematic Procedure to Sort Out Contractor in Construction Field
 
AN APPRAISAL OF VALUE ENGINEERING AND THE AWARENESS LEVEL AMONGST NIGERIAN CO...
AN APPRAISAL OF VALUE ENGINEERING AND THE AWARENESS LEVEL AMONGST NIGERIAN CO...AN APPRAISAL OF VALUE ENGINEERING AND THE AWARENESS LEVEL AMONGST NIGERIAN CO...
AN APPRAISAL OF VALUE ENGINEERING AND THE AWARENESS LEVEL AMONGST NIGERIAN CO...
 
journal research paper
journal research paperjournal research paper
journal research paper
 
Utilitas mathematica
Utilitas mathematicaUtilitas mathematica
Utilitas mathematica
 
mathematica journal
mathematica journal mathematica journal
mathematica journal
 

Recently uploaded

Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 3652toLead Limited
 
Unraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfUnraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfAlex Barbosa Coqueiro
 
Streamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupStreamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupFlorian Wilhelm
 
AI as an Interface for Commercial Buildings
AI as an Interface for Commercial BuildingsAI as an Interface for Commercial Buildings
AI as an Interface for Commercial BuildingsMemoori
 
Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 3652toLead Limited
 
WordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your BrandWordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your Brandgvaughan
 
"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii SoldatenkoFwdays
 
Install Stable Diffusion in windows machine
Install Stable Diffusion in windows machineInstall Stable Diffusion in windows machine
Install Stable Diffusion in windows machinePadma Pradeep
 
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...shyamraj55
 
Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!Commit University
 
"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr BaganFwdays
 
My INSURER PTE LTD - Insurtech Innovation Award 2024
My INSURER PTE LTD - Insurtech Innovation Award 2024My INSURER PTE LTD - Insurtech Innovation Award 2024
My INSURER PTE LTD - Insurtech Innovation Award 2024The Digital Insurer
 
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
"Federated learning: out of reach no matter how close",Oleksandr LapshynFwdays
 
Commit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easyCommit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easyAlfredo García Lavilla
 
My Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationMy Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationRidwan Fadjar
 
Pigging Solutions in Pet Food Manufacturing
Pigging Solutions in Pet Food ManufacturingPigging Solutions in Pet Food Manufacturing
Pigging Solutions in Pet Food ManufacturingPigging Solutions
 
Connect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationConnect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationSlibray Presentation
 
Unleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding ClubUnleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding ClubKalema Edgar
 
Vertex AI Gemini Prompt Engineering Tips
Vertex AI Gemini Prompt Engineering TipsVertex AI Gemini Prompt Engineering Tips
Vertex AI Gemini Prompt Engineering TipsMiki Katsuragi
 

Recently uploaded (20)

Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
 
Unraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfUnraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdf
 
Streamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupStreamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project Setup
 
AI as an Interface for Commercial Buildings
AI as an Interface for Commercial BuildingsAI as an Interface for Commercial Buildings
AI as an Interface for Commercial Buildings
 
Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365
 
WordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your BrandWordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your Brand
 
"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko
 
Install Stable Diffusion in windows machine
Install Stable Diffusion in windows machineInstall Stable Diffusion in windows machine
Install Stable Diffusion in windows machine
 
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
 
Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!
 
"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan
 
My INSURER PTE LTD - Insurtech Innovation Award 2024
My INSURER PTE LTD - Insurtech Innovation Award 2024My INSURER PTE LTD - Insurtech Innovation Award 2024
My INSURER PTE LTD - Insurtech Innovation Award 2024
 
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
 
DMCC Future of Trade Web3 - Special Edition
DMCC Future of Trade Web3 - Special EditionDMCC Future of Trade Web3 - Special Edition
DMCC Future of Trade Web3 - Special Edition
 
Commit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easyCommit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easy
 
My Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationMy Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 Presentation
 
Pigging Solutions in Pet Food Manufacturing
Pigging Solutions in Pet Food ManufacturingPigging Solutions in Pet Food Manufacturing
Pigging Solutions in Pet Food Manufacturing
 
Connect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationConnect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck Presentation
 
Unleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding ClubUnleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding Club
 
Vertex AI Gemini Prompt Engineering Tips
Vertex AI Gemini Prompt Engineering TipsVertex AI Gemini Prompt Engineering Tips
Vertex AI Gemini Prompt Engineering Tips
 

I0372044048

  • 1. International Journal of Engineering Science Invention ISSN (Online): 2319 – 6734, ISSN (Print): 2319 – 6726 www.ijesi.org Volume 3 Issue 7 ǁ July 2014 ǁ PP.44-48 www.ijesi.org 44 | Page Evaluating The Criteria for Contractors’ Selection and Bid Evaluation 1, Dwarika Puri , 2, S.Tiwari 1, P. G. Student, Department of Civil Engineering, Madhav Institute of Technology & science, Gwalior 2, Prof., Department of Civil Engineering, Madhav Institute of Technology & science, Gwalior ABSTRACT : Construction contractors have big influences upon projects and their successes. Therefore, it is quite critical to select a qualified contractor in the process of construction management. A competent construction contractor is one of the indispensable conditions of a proper process and completion of a construction project. There are several theoretical frameworks or models applied in the evaluation of contractors. And there are some practical criteria for selecting an appropriate contractor. This paper analyzed the relevant theoretical methods for contractor evaluation and examined the actual criteria for the selection of contractors.This study aims at identifying the criteria for selection of contractor and bid evaluation means by which different emphases can be recommended to suit the requirements of clients and projects. The research was conducted by sending a questionnaire to different project managers in India and had an exceptionally high rate of response of 72%. The analysis led to some interesting findings that reflect on the current practice. The paper is concerned with providing construction contractors with recommendations in pursuit of better evaluation of construction bids both technically and financially. I. INTRODUCTION Construction project must be managed in an effective manner. The demands from clients and competition have been growing rapidly (Crowley and Hancher, 1995). These challenges present a paradox. Few of these demands directly contribute to the physical construction of the project, however, a failure to properly manage them can lead to problems for the entire project and construction team. The selection of a proper construction contractor increases chances of successful completion of a construction project (Alhazmi and McCaffer, 2000). It can also fulfill the client goals, and keep the schedule of the cost, time and quality. So it is extremely critical to select an appropriate contractor in the process of construction management. The selection of construction contractors are very often conducted during tendering. Tendering definitely gives a client a choice in awarding contract a company which proposes the lowest price and short construction cycles, but usually they do not allow to precisely evaluate a tender. At the same time there are more and more procedures in which the decision criterion of choosing a tender is the price. In recent years, most clients made use of such a method. On the other hand, the research results show that the cheapest tenderers often have problems with completing the project. Accepting the lowest price is the basic cause of the project completion problems because very often lowering the price means lowering the quality. It is true in some cases. The above conditions make that it is especially important to properly evaluate the contactor’s capabilities. We analyzed in Selecting the most suitable contractor for a construction project is a crucial decision for owners and project managers. Therefore, this paper aims at selection of construction project contractors with recommendations about the suitable criteria for better evaluation of construction bids both technically and financially. Furthermore, it provides practitioners working or intending to work in the North East with better insight due to the common trends. The objectives of this paper are as follows: • Reviewing the various criteria used for contractors pre-qualification and bid evaluation. • Identifying the criteria that are actually used to evaluate contractors’ pre-qualification and bids in India. • Introducing some recommendations for enhancing the contractors’ selection process. II. LITERATURE REVIEW Contractor pre-qualification and bid evaluation procedures are currently used in many countries, and it involve the development and wide consideration of necessary and sufficient decision criteria to evaluate the overall suitability of contractors. The literature review discovered the existence of various criteria, types of information and methods of assessment.
  • 2. Evaluating The Criteria For Contractors… www.ijesi.org 45 | Page Hatush and Skitmore (1997 a) pointed that the tender system of basing decisions on the minimum price has been used in New York since 1848 for highway and bridge tenders. The main idea of such a method was to save financial resources and create equal competition for all contractors by lowest bid.Hatush and Skitmore (1997 a) recognized five main elements that was common factors in the contractor selection process for each and every one types of procurement arrangements. These are project packaging, invitation, prequalification, short listing and bid evaluation.Hatush and Skitmore (1997a) identified pre-qualification as a pre-tender process used to investigate and assess the capabilities of contractors, hence providing the client with a list of potential contractors to invite to tender. Bid evaluation despite involves similar process it is different in two aspects; it occurs at the post tender stage and it considers both bid amount and the contractors’ capabilities.Russel and Skibiniewski (1988) defined bid evaluation as a decision-making process that involves the development and wide consideration of necessary and sufficient decision criteria used to assess the contractors’ capabilities. It requires knowledge and experience from the project manager in order to use the appropriate criteria to insure the selection of the most suitable contractor technically and financially for the project (Hatush and Skitmore (1997a) III. BID EVALUATION Bid evaluatation according to Herbsman and Ellis (1992), amount to the ‘major’ criteria of cost, time, and quality as measured by the bid amount, time of execution, and quality of previous work respectively. This implies that the winning bid is fully responsive to the contract in addition to the bidder’s being sufficiently well qualified to undertake the contract (Hardy, 1978). Bid evaluation is used to indicate the procedure for strategic assessment to tender bids submitted by pre-qualified contractors. The strategy used for bid evaluation should reflect the client’s objectives (Hardy, 1978). In addition, Herbsman and Ellis (1992) have also further project- specific criteria, including safety, durability, security, and maintenance. More objective methods have been proposed by Moselhi and Martinelli (1990) and Diekmann (1981) by means of multi-attribute utility techniques for combining the bid price and contractor selection criteria. The evaluation of bids by multi-attribute methods may encounter some difficulties when comparing different criteria measured by different scales. Hence various ways have been suggested for combining criterion values into a single scale. Herbsman and Ellis (1992), on the other hand, proposed a time/cost approach to determine the winning bid in the highway construction contracts. By converting the contract time to cost, a straightforward comparison can be made on a single criterion. Finally, Holt et al. (1993) combine their P2 and P3 score into a simple index by assigning 60% weighting for the P3 score and 40% to the P2 score. Hence, it could be concluded that there is no consensus as yet on a common set of selection criteria for contractor selection. Selection criteria may vary in emphasis according to the characteristics of the project. The Selection of Construction Project Contractors :It is problematical to select a suitable contractor. Bid evaluation is one of the major challenges that face owners and consultants in the public and private sectors. On the other hand, there are objective means to gauge the ability of a contractor to properly manage the business aspects of the construction project. Some models and frameworks have been created to evaluate contractors’ bids and select the most suitable one. The Cost Consideration : Among all factors the main evaluation factor is cost or price consideration that may affect the selection of a contractor. Although the lowest bidder system protects the public from improper practices, it has certain disadvantages. These include unreasonable low bids either accidentally or deliberately or unqualified contractor which cause extensive delay, cost overrun, quality problems and increased number of disputes. Over the years some modification to the lowest bidder system were made, such as reasonable bidder, public interest and prequalification list which open the door to other evaluation methods to be adopted instead of the single criterion system lowest bidder system. The TOPSIS and SAW-G Grey Techniques :The grey theory is a new technique for performing prediction, relational analysis and decision-making in many areas. The grey theory techniques were applied for defining the utility of an alternative. Proposed assessment model covers well known method of TOPSIS (Technique for Order Preference by Similarity to Ideal Solution), method with attributes values determined at intervals (TOPSIS-grey) and a method of Simple Additive Weighting with Grey relations (SAW-G). The methods of grey relations methodology can be implemented as an effective decision aid for tasks with uncertain data. Pre-Qualification and Bid Evaluation Criteria : To ensure the quality of contractors, the valuation can be done beforehand with a prequalification method. Facing the owner’s scrutiny regarding its competency to handle the business aspects of the operation during prequalification allows the contractor to focus on the specifics of the construction project once it has passed through prequalification and been short-listed. This also
  • 3. Evaluating The Criteria For Contractors… www.ijesi.org 46 | Page allows the owner’s bid evaluation team to focus only on the specific elements of the project, without being distracted by the other business considerations. In the simplest meaning prequalification is a before tendering procedure which allows to choose the most appropriate candidates from amongst those declaring willingness to participate in the tendering. Prequalification is defined by Moore (1985) as the screening of construction contractors by project owners or their representatives according to a predetermined set of criteria deemed necessary for successful project performance, in order to determine the contractor’s competence or ability to participate in the project bid. Clough (1986) thinks that prequalification means that the firm which wants to participate in the tendering needs to be qualified before it can be issued bidding documents or before it can submit a proposal.Pre-qualification and bid evaluation procedures involve different types of criterion to evaluate the overall suitability of contractors such as: General, technical, managerial, and financial criteria (Hunt et al., 1966); Financial stability, managerial capability and organizational strength, technical expertise and experience of comparable construction (Merna and Smith, 1990); Relevance of experience, size of firm, and safety record (Moselhi and Martinelli, 1990). Hatush and Skitmore (1997a) have identified five main criteria for contractor prequalification and bid evaluation along with the information necessary to assess these criteria as shown in Table (1). Table 1: Main Criteria and Sub-criteria for Contractors’ Prequalification and Bid Evaluation Financial soundness Financial stability. Credit rating. Banking arrangements and bonding. Financial status. Technical ability Experience. Plant and equipment. Personnel. Ability. Management capability Past performance and quality. Project management organization Experience of technical personnel. Management knowledge. Health and safety Safety. Experience modification rating. OSHA Incident rate. Management safety accountability. Reputation Past failures. Length of time in business. Past owner/contractor relationship. Other relationships. Russel (1996) put forward some other simple contractor prequalification criteria. He distinguishes three basic groups of criteria: _ Preliminary screening criteria (among others: references, reputation, past performance, _ Constructor resources (financial, technical, status of current work program), _ Other items (project specific criteria). Quite interesting are the criteria presented by the Palaneeswaran and Kumaraswamy (2001). The following groups of criteria have been suggested: (1) Responsiveness, promptness, realism, completeness. (2) Meeting deadlines, correctness and valid information, totality in providing information. (3) Responsibility, obeying the law and complying with local government regulations, standards and bylaws, quality system, safety system. (4) Competence, recourse (financial, machinery, plant and equipment, human resources), experience, constraints (current workload, subcontracts, guarantees). Information It is necessary to collect and investigate information to quantify objectively the criteria for bid evaluation. This information includes that relating to the (1)contractor’s permanent place of business; (2) capability of plant and equipment to do the work properly and expeditiously; (3)suitability of financial capability to meet obligations required by the work; (4)appropriateness of technical ability and experience; (5)adequate experience in similar projects regarding type and size; (6) the current position of the contractor to perform the contract well; the contractor’s relationship with subcontractors, or employees. In total, the information used for the assessment of
  • 4. Evaluating The Criteria For Contractors… www.ijesi.org 47 | Page criteria for pre-qualification and bid evaluation falls into five groups: general information that is used mainly for administrative purposes, financial information, technical information, managerial information, and safety information (Hatush and Skitmore; 1997a). Assessment :The information concerning to the criteria can be assessed in various ways. This can be done by assigning a maximum point value for each used criterion. These values are then weighted to their relative importance on the overall project delivery strategy. When a criterion is made up of sub-criteria, the weighed value scores of the sub criteria are added to calculate the total value for the category. To avoid biases, it is recommended that a minimum of three evaluators is required for each scoring activity. Holt et al. (1993) have planned a modified quantitative model for selecting contractors. This model comprises a three-stage process requiring the calculation of what is called P1 scale index to investigate the more general areas surrounding potential bidders. A P2 scale index is calculated for the second stage to assess the contractor further in the light of specific factors. Finally a P3 scale index is calculated to compare the bid prices amongst the invited bidders. The Construction Management at Risk Method : The Construction Management at Risk method was introduced in the 1980s. Construction management at risk (CMAR) as a project delivery method was created to provide input to the designer to increase constructability of designs and to decrease schedule duration through overlapping of the design. Kknocherand Sanvido (1998) emphasized that the contractor usually has a significant input in the design process. In general, CMAR creates a collaborative environment that uses the wisdom, experience, and creativity of the architect and the CM. Construction Management at Risk or CMAR is gaining popularity, especially in the construction of the large projects such as schools, airports, and sports arenas. The CMAR method aims to reduce the risk of cost overrun and schedule creep and to expedite the construction process without compromising quality. The construction manager works with the designer as a team during the design phase. There are some advantages to the owner from using the CMAR delivery method are- [1] Risk is reduced for the architect and owner. [2] Produce a more manageable and predictable project cost and schedule outcomes. [3] Centralizes responsibilities. [4] The owner benefits from the CM’s experience both during design and construction. [5] Allow for an early start to construction by phasing the work. [6] Results in better quality construction The Multi Criteria Evaluation Models : It can be stated that contractor’s selection problem is a multi-criteria problem in most cases. Many multi-criteria techniques are proposed and applied (Goicoechea et al. 1992, Zavadskas et al. 2008). Skibniewski and Chao (1992), Banaitis and Banaitiene (2006), Mitkus and Trinkuniene (2006), Ginevicius and Podvezko (2008), Turskis (2008) and Zavadskas et al. (2008), Plebankiewicz (2009) investigated assessment of construction firms and contractors evaluation problems. There is a Multi Criteria Bidding System which is an evaluation method that considers not only the cost as the awarding reason, but also considers other important attributes. The key of Multi attributes system is that the selection process of the contractors is based on more attributes such as, bid price or cost, time, quality, managerial safety accountability, competence and sufficiency of contractors (Liu et al., 2000). The main concept of the Multi Attributes Bidding System is that the selection process of the contractors will be based on more attributes than just the price, and the successful bidder will be the one who has the highest combined bidding value of the multiple attributes. The scores of those attributes are transformed into values and those values of all the attributes are totaled to give the combined bidding value. Some Actual Criteria for the Selection of Construction Project Contractors :In actuality, contractor evaluation is regularly performed by industry professionals using their accumulated experience and judgment. There are variations in the amount of effort expended in the process. An important step in evaluation is to examine the contractor’s system for handling project information regarding work tasks. The contractor’s approach to safety and what actions it takes to achieve desired results should be closely scrutinized.Many factors should be considered during the contractors’ qualification screening. The following list includes most of the components that should be examined when conducting a contractor qualification. (1) Financial standing, such as financial stability, turnover, profit, obligations, amounts due, and owned financial funds. (2) Technical ability, such as experience, plant and equipment, and personnel. (3) Management capability, such as past performance and quality, quality control policy, quality management system, project management system, experience of technical personnel, and management knowledge. (4) Quality, safety, senior management, including experience,
  • 5. Evaluating The Criteria For Contractors… www.ijesi.org 48 | Page tenure with firm, and division of responsibilities. (5) Current projects/backlog, including number, size, and location of projects, percent of capacity being utilized, and status and expected completion, past failures in completed projects, number of years in construction, past client relationships and cooperation with contactors. One way to collecting the data necessary to perform contractor evaluations is to conduct questionnaires. But in this way, contractors will be tempted to answer in a way that puts them in the best light. For instance, one commonly used questionnaire asks contractors if safety is a priority in their business. IV. CONCLUSIONS This paper proposed criteria to evaluate contractors and bid selection based on chosen criteria. The objective of this paper is to deliver a completed project that serves the intentional function. Some clients may choose to use just one of the criteria used to qualify a candidate to the stage of tendering procedure and it is usually the contractor’s experience. Majority of studied clients evaluate contractor companies after having completed their cooperation, they keep their data and also declare giving preferences for those companies with which their cooperation was successful. This proves that they pay great attention to reliability and competence of the contractors. One important step that can be taken to ensure project success in safety is to prequalify and select only those contractors who are fully qualified by virtue of their safety programs and performance. A good safety record reduces the cost of construction and helps to support the desired attitude toward quality and productivity. Comprehensive contractor evaluations conducted prior to selection can significantly reduce the risks faced by a construction project. REFERENCES [1] Alhazmi, T., & McCaffer, R. (2000). Project procurement system selection model. Journal of Construction Engineering and Management, 126, 176–184. [2] Banaitiene, Banaitis. (2006). Analysis of criteria for contractors’ qualification evaluation, Technological and Economic. Development of Economy, 12(4), 276–282.Clough, R. (1986). Construction contracting. New York, NY, Wiley. [3] Crowley, L., & Hancher, D. (1995). Risk assessment of competitive procurement. Journal of ConstructionEngineering and Management, 121, 241–248. [4] Ginevicius, R., & Podvezko, V. (2008). Multicriteria graphicalanalytical evaluation of the financial state of construction enterprises. Technological and Economic Development of Economy, 14(4), 452–461. [5] Goicoechea, A., Kenneth, H.M., & Edward, A.W. (1992). Multiple criteria decision making. In: Proceedings of the 9th International Conference: Theory and Application in Business, Industry, and Government. Springer-Verlag, New York, USA. [6] Hardy, S C (1978), Bid Evaluation Study for the World Bank, 1, University of Manchester a. Institute of Science and Technology, UK. [7] Hatush, Z., & Skitmore, M. (1997). Evaluating contractor prequalification data: selection criteria and project success factors. Construction Management and Economics, 15: 129–147. [8] Herbsman, Z and Ellis, R, (1992), Multi-parameter Bidding System-innovation in Contract Administration, Construction Engineering and Management, 118(1), 142-150. [9] Holt, G D, Olomolaiye, P O and Harris, F C (1993) A conceptual alternative to current tendering practice. Building Research and Information, 21(3), 167-72. [10] Merna, A and Smith, N J, (1990), Bid Evaluation for UK Public Sector Construction Contracts, Proceedings of the Institution of Civil Engineers, Pt 1 88, Feb., 91-105. [11] Moselhi, O and Martinelli, A (1990), Analysis of Bids Using Multi-attribute Utility Theory in Transactions, The International Council for Construction Research Studies and documentation. CIB W-65, Sydney, Austalia, 335-345. [12] Mitkus, S., & Trinkuniene, E. (2008). Reasoned decisions in construction contracts evaluation. Technological and Economic Development of Economy, 14(3), 402–416. [13] Moore, M. J. (1985). Selecting a contractor for fast-track projects: Part I, principles of contractor evaluation. Plant Engineering, 39, 74–75. [14] Plebankiewicz, E. (2009). Contractor prequalification model using fuzzy sets. Journal of Civil Engineering and Management, 15(4), 377–385 [15] Russell, J. S. and Skibniewski, M. J. (1988), Decision Criteria in Contractor Pre-qualification, Journal of Management in Engineering, ASCE, 4(2), 148-164. [16] Skibniewski, M., & Chao, L. (1992). Evaluation of advanced construction technology with AHP method. Journal of Construction Engineering and Management, ASCE, 118, 255–261. [17] Turskis, Z. (2008). Multi-attribute contractors ranking method by applying ordering of feasible alternatives of solutions in terms of preferability technique. Technological and Economic Development of Economy, 14(2), 224–239. [18] Zavadskas, E. K., Liias, R., & Turskis, Z. (2008). [19] Multi-attribute decision-making methods for assessment of quality in bridges and road construction: state-of-the-art surveys. The Baltic Journal of Road and Bridge Engineering, 3(3), 152–160.