DYNAMICS OF GOVERNMENT CONTRACTING: PROPOSALS FOR
EFFICIENCY AND SATISFACTION OF PUBLIC NEEDS
1
Felipe Di Stefano Pereira, 2
Tito Livio Medeiros Cardoso, 3
Erica Braga, 4
Debora Francisco Lalo
1,2,3
BRG Berkeley Research Group, São Paulo, Brazil
4
Department of Mechanical Engineering, University Center of FEI, São Bernardo do Campo, São Paulo
Email: 1
fpereira@thinkbrg.com, 2
tcardoso@thinkbrg.com, 3
ebraga@thinkbrg.com 4
dflalo@fei.edu.br
Abstract: The present article aims to present a proposal for efficiency and satisfaction of public needs related to
government contracting, given the notorious cases of low efficiency in investments of public interest around the
world. To understand the various factors involved, a comparative study was first carried out between public
procurement processes and their requirements in different countries. A generic and hypothetical case was then
modeled in the form of a simple dynamic system related to government contracting. This way, the authors suggest
that, even in a selection system based on the lowest price, it is possible to obtain design and construction quality
since some conditions, which will be presented throughout the article, are implemented.
Index terms: Government Contracting, Public Investment, Public Projects, Infrastructure.
I. INTRODUCTION
Infrastructure projects are of broad
interest to society for achieving the objectives, such as
meeting the growing demand for services by the
population, implementing public policies, increasing
efficiency in the use of resources (financial and
natural), improving regional competitiveness and
national attraction of foreign capital, development of
sectors such as tourism and lodging, generation of
jobs, among others.
In spite of this relevance, the cases of low
efficiency in the investments of public interest are
notorious, as shown in Figure 1.
Figure 1: Significant cost overruns and delays in various public
interest projects [1]
Low efficiency in public investments are
observed in locations as diverse as the US, where road
projects in 2009 were executed 40% above bid
amounts (equivalent to USD 1.2 billion overflow), as
in Canada, where a sample of 50 road projects had a
cost overrun of 82% in 2006 [8], Nigeria, where 92.3%
of building projects in a sample of 2017 showed
average growth of 20% in relation to contracted budget
[2] and Palestine, where , in a sample of 169 road
projects, 76% presented construction cost increases in
relation to the budget [3]. In other countries, the
problems extend to the operational phase. As an
example, in 2016, 78.4% of 105,814 km of Brazilian
federal highways presented conditions that
compromise transportation performance and driver
safety, with 42% of the extension having pavement
problems and 55% signaling problems [4].
A set of statistical analyses and research
indicate that project changes during execution are a
factor which influences project cost deviations [5, 8]
and the relative deviations may be even greater in
projects of smaller extent than in larger ones [6].
Locational factors are also identified [5, 6]. These
factors, in turn, refer to the planning deficiency in the
pre-construction phase and insufficient feasibility
studies, including estimation errors and scope
definition gaps [8].
A comparison between studies conducted in
developing and Asian countries shows agreement on
factors related to inadequate initial planning, financial
constraints, cash flow problems of management and
poor contract management [5]. Due to these problems
the contracting systems of public projects in the
various countries have frequently been the subject of
comparisons and analyses [9,10,11,12].
Table 1 presents a summary of the processes
for contracting consultancies and public works in
several countries. The systems used by the countries
present important differences.
Public works contracting systems differ
widely between countries and, in particular, we note
the differences between the criteria for qualification of
tenderers and evaluation of tenders. In spite of
differences in details and nomenclatures, two central
lines of reasoning stand out: one objective is the
"lowest price" (USA, Japan, India, Brazil) and the
other "highest value" (US, UK, France, Germany,
Sweden).
Dynamics of Government Contracting: Proposals for Efficiency and Satisfaction of Public Needs
523rd International Conference on Science, Technology, Engineering and Management (ICSTEM), 12th-13th Jan. Paris. ISBN: XX
XX
Table 1- Comparative summary of public procurement processes and their requirements in different countries. Based on [9] and [10]
Dynamics of Government Contracting: Proposals for Efficiency and Satisfaction of Public Needs
523rd International Conference on Science, Technology, Engineering and Management (ICSTEM), 12th-13th Jan. Paris. ISBN: XX
XX
The "highest value" evaluation covers several
methods ranging from the most objective, in the
economic quantification of Value for Money (VFM),
to a system of weights and factor scores, which in
many cases includes the price of service, to more
subjective analyses, consolidated in the form of
descriptive narratives.
According to the OECD, Value for Money
(VMF) is the ideal combination of cost and quality
over the life of the asset (or suitability for the purpose)
to meet user needs. It can be evaluated using the
criteria of economy, efficiency and effectiveness [15].
The World Bank guides the use of the factor
and weighting system to achieve Value for Money in
contracting works, [16] but, interestingly, we see
countries that predominantly contract for the lowest
price criterion and in general, good performance of
contracted services is obtained - as the case of Japan –
on the other hand, when the best value evaluation
systems are used, not always the good cost and time
performance of works are obtained - as the case of US.
In the details the differences are shown even
in the more objective or more bureaucratic way, in
which public administrations are issuing notices to the
market. As an example, Figure 2 shows an example of
an edict focusing on the results previously obtained by
the proposer in previous projects - note that there are
no criteria as to where the results were obtained. In
other situations, we observed a notice for the hiring of
the same service that included in the requirements, a
technical file registered in an organization of the
country, that the collection should refer to services
performed in the country, establishing requirements of
the profession of the team that would conduct the work
("only engineers", etc.) - and with all this, without
establishing a single line on the actual results obtained
by the company in past jobs, in the country or in the
world. In their comparison of the qualification criteria
used for contracting public works in the Czech
Republic and Poland, the authors stated:
“Qualification criteria (QC) can be identified as an
important risk of corruption. For instance,
methodology for local governments notes, that
determination of unnecessarily strict QC for suppliers
to the subject of the contract results in the elimination
of effective competition and contracts can be even
tailored to pre-selected contractor.” [12]
These differences indicate that there are
multiple factors and differences influencing the
performance of public projects.
Figure 2: Requirements for qualification of tenderers in public
tender for contracting planning of public sanitation
infrastructure projects. Banning, California (USA) [14]
II. UNDERSTANDING THE
CONTRACTING OF PUBLIC
PROJECTS AS A DYNAMIC SYSTEM
To understand the various factors involved in
contracting a public project, let us model a generic and
hypothetical case in the form of a simple dynamic
system.
The system in Figure 3 describes the
following case:
 A locality with an infrastructure deficit
generates a flow of annual demand for project
bids in the design-bid-build format to meet
the public needs;
 A certain technically qualified constructor
competes for projects by proposing a
construction price that determines their
success rate in these bids - the negative sign
in the relationship between "construction
price" and "bid success rate" identifies that
the lower the price the higher the success
rate);
 The number of annual bids and the success
rate determine the number of projects under
construction, which accumulates at each
annual round of new bids;
 For simplicity, the builder is paid monthly
(fixed installments of the constructions price
in stock, divided by the construction period),
a fraction of this amount being his profit;
 The stock of projects under construction
decreases as a result of the projects flow that
were completed - which depends on the
construction period;
 Completed projects increase the satisfaction
of public needs, decreasing the flow of new
bids for the following year - characterized by
Dynamics of Government Contracting: Proposals for Efficiency and Satisfaction of Public Needs
523rd International Conference on Science, Technology, Engineering and Management (ICSTEM), 12th-13th Jan. Paris. ISBN: XX
XX
a negative sign in the relationship between
"satisfying the public needs" and "bidding";
 The inventory of projects under construction
can also be reduced by the cancellation flow
of contracts. In this case, however, public
needs are not met.
Figure 3 - Simple dynamic system representing a hypothetical
case of contracting public projects
Even such a simple model exposes a conflict
from the outset, the relationship between price, success
rate in bidding and profit is the opposite, that is, lower
prices increase the success rate, but reduce the amount
of profit.
In Figure 4 we observe at least two forms,
which are not mutually exclusive, for the constructor
to increase his profit in the same conditions presented
in the case:
i. If there are delays in construction, the builder
will submit claims on schedule extension and
the delay period will add up to the initial
construction period, increasing the billing
period so that the total cost of the work
exceeds the bid price - as if observed in the
United States and, previously, in the United
Kingdom (see table 1). According to the
referenced research and studies, the poor
quality of engineering and planning projects
is a source of delays in the construction of
public works. In Figure 4 this relation is
evidenced by the negative sign between "
project quality" and "delays": the lower the
quality of the project, the greater the delays.
ii. If the construction quality is lower, the
builder's profit is higher, regardless of the
project quality (for example, by using lower
materials or smaller quantities than
engineering project size). Figure 4 shows that
as a side effect, since the relationship is
positive, low quality of construction reduces
the satisfaction of public needs, which in turn
increases the demand for bids, forming a
vicious cycle that repeats itself.
Figure 4 - Dynamic system, now considering the quality of the
engineering design and the quality of the construction (in red)
Figure 5 presents the same dynamic system
where management now responds to the delays and
poor quality of construction through the application of
fines and contracts cancellation. The negative
relationship indicates that more fines reduce the
builder's profit as well, contracts cancellation reduces
the inventory of projects under construction which
directly reduces profit.
Figure 5 - Dynamic system, now considering responses in the
form of fines and cancellation of contracts
However, this set of responses has at least
two drawbacks:
 Cancellation of contracts reduces the
inventory of projects under construction
before they are completed, preventing the
fulfillment of the public needs.
 In practice, in many administrations, there is
a delay between the time of delays and loss
of quality in the construction and the
instant of penalties application - the
questioning occurs after construction,
reducing or canceling its effect as corrective
action.
Dynamics of Government Contracting: Proposals for Efficiency and Satisfaction of Public Needs
523rd International Conference on Science, Technology, Engineering and Management (ICSTEM), 12th-13th Jan. Paris. ISBN: XX
XX
Figure 6 presents another response to the
problem in the form of a negative feedback loop where
delays and quality of construction reduce the success
rate of the builder in the new bids. At the same time,
proactive management action in attracting other
builders and new entrants to the local market will
further dilute the contractor's success rate unless it
builds good quality projects without delays breaking
the vicious cycle of feedback.
This approach is a long-term solution with a
focus on the wide competition and is part of the
concept of layered antifragility, exposed by Table [13],
as the ability of a system to acquire resilience and
evolve from the confrontation experienced by the
subunits that comprise it. For example, when local
restaurants compete between themselves it results in
the antifragility of the collective in the local sector. If
the restaurants were individually robust, the overall
business would either be stagnant or weak and offer
nothing more than standard meals. The sector would
also be more exposed to systemic crises.
Figure 6 - Dynamic system, now considering a negative process
feedback cycle (in green).
CONCLUSION
The comparison of consulting and works
contracting systems by the administrations of several
countries demonstrates that the achievement of
efficiency and satisfaction of the public needs present
several underlying factors that prevent the reduction of
the problem to a trivial definition of criteria for the
qualification and selection of bidders, such as "lower
price" versus "higher value".
The present work, through the study of
dynamics in a simple hypothetical case, suggests that
even in a selection system based on the lowest price, it
is possible to obtain design and construction quality
since some conditions are provided:
 Criteria for qualification and selection based
on the performance of the company in
previous projects, objectively characterized.
 Encouraging layered antifragility by
expanding the supplier market and diluting
the relative importance of larger local players
by encouraging new or local suppliers to
enter.
 To enable this, proactive actions by the local
public administration may include:
o the bilingual bidding, considering
more universalized criteria and
nomenclatures;
o International presentation of the
pipeline of public projects;
o Exclusion of bureaucratic
requirements for registration in local
organizations, or previous
experience in the field.
 Real-time control of the building's physical
progress. Transparency and publicity of the
performance of projects under construction.
 Bids based only on engineering executive
projects, including definitive construction
plan.
These conclusions were derived directly from
the dynamic system analyzed, respectively, acting on
the variables "Other constructors and new entrants",
"construction quality " and "design quality" in the
complete model of Figure 5. Extensions of this work
can be done detailing the steps which precede the
bidding, as well as the systematic control of public
administration, among other possibilities.
ACKNOWLEDGMENTS
The authors acknowledge Claudio Graeff
(Construction Director of BRG Brazil) and University
Center of FEI.
REFERENCES
[1] “The century’s most troublesome construction projects”,
accessed in: 11/06/18, http://www.globalconstructionreview.
com/perspectives/centurys-most-troublesome-construction-
pr8oje8ct8s/
[2] KADIRI, Dele S.; ONABANJO, Babajide O. “Cost and Time
Overruns in Building Projects Procured Using Traditional
Contracts in Nigeria.” Journal of Sustainable Development,
v. 10, n. 5, p. 234, 2017.
[3] MAHAMID, Ibrahim. “Analysis of cost deviations in road
construction activities: A case study from Palestine.” Jordan
Journal of Civil Engineering, v. 5, n. 4, p. 552-567, 2011.
[4] CNT (Confederação Nacional do Transporte) “Transporte
rodoviário: desempenho do setor, infraestrutura e
investimentos”, Brasília, 2017.
[5] SWEIS, Ghaleb J. et al. “Cost overruns in public construction
projects: the case of Jordan.” Journal of American Science, v.
9, n. 7, p. 134-141, 2013.
[6] ODECK, James. “Cost overruns in road construction—what
are their sizes and determinants?” Transport policy, v. 11, n.
1, p. 43-53, 2004.
Dynamics of Government Contracting: Proposals for Efficiency and Satisfaction of Public Needs
523rd International Conference on Science, Technology, Engineering and Management (ICSTEM), 12th-13th Jan. Paris. ISBN: XX
XX
[7] RAMABHADRAN, Muralidaran. “An Investigation into
Cost Overrun in Construction Projects in United Arab
Emirates.” International Journal of Construction Engineering
and Management, v. 7, n. 1, p. 1-21, 2018.
[8] SAIDU, Ibrahim; SHAKANTU, Winston. “An investigation
into cost overruns for ongoing building projects in Abuja,
Nigeria.” Acta Structilia, v. 24, n. 1, p. 53-72, 2017.
[9] OHNO, Taishi; HARADA, Yuhei. “A Comparison of
tendering and contracting systems for public works between
Japan, the United States and EU countries.” Government
Auditing Review, v. 13, p. 49-71, 2006.
[10] GAZULA, Sriharsha; VADALI, Anil Kumar. “Comparison
of Public Tender Process between Sweden and India.” 2012.
[11] PETRISOR, Mihai-Bogdan. “Comparison of the Public
Procurement System in Romania and the UK.” EIRP
Proceedings, v. 10, 2015.
[12] KORYTÁROVÁ, Jana et al. “Exploring the contractors’
qualification process in public works contracts.” Procedia
Engineering, v. 123, p. 276-283, 2015.
[13] TALEB, Nassim Nicholas. “Antifragile: Things that gain
from disorder”, 2012.
[14] “RFP 2016-009, Request for proposal (RFP) for integrated
master plan for water, wastewater and recycled water
systems”, City of Banning, Public Works Department.
September 16, 2016.
[15] JACKSON, Penny. “Value for money and international
development: Deconstructing myths to promote a more
constructive discussion.” Organization for Economic
Cooperation and Development, 2012.
[16] “Procurement Guidance - Use of evaluation criteria for
procurement of Goods, Works, and Non-Consulting Services
using RFB and RFP”, World Bank, July 2016.


More Related Content

Similar to DYNAMICS OF GOVERNMENT CONTRACTING: PROPOSALS FOR EFFICIENCY AND SATISFACTION OF PUBLIC NEEDS

Quantity Surveyor’s Impact: A Panacea to achieving Critical Success Factors i...
Quantity Surveyor’s Impact: A Panacea to achieving Critical Success Factors i...Quantity Surveyor’s Impact: A Panacea to achieving Critical Success Factors i...
Quantity Surveyor’s Impact: A Panacea to achieving Critical Success Factors i...
inventionjournals
 
Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...
Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...
Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...
IJMREMJournal
 
P3CostOfCapitalPaperMarch2015
P3CostOfCapitalPaperMarch2015P3CostOfCapitalPaperMarch2015
P3CostOfCapitalPaperMarch2015
Sarina Juanzi Li
 
1_PPP paper_FINAL 05 17 16
1_PPP paper_FINAL 05 17 161_PPP paper_FINAL 05 17 16
1_PPP paper_FINAL 05 17 16
stolleman
 
A Multi-Objective Fuzzy Linear Programming Model for Cash Flow Management
A Multi-Objective Fuzzy Linear Programming Model for Cash Flow ManagementA Multi-Objective Fuzzy Linear Programming Model for Cash Flow Management
A Multi-Objective Fuzzy Linear Programming Model for Cash Flow Management
IJERA Editor
 

Similar to DYNAMICS OF GOVERNMENT CONTRACTING: PROPOSALS FOR EFFICIENCY AND SATISFACTION OF PUBLIC NEEDS (20)

Study of Influencing Factors of Tender Evaluation: An Evidential Reasoning Ap...
Study of Influencing Factors of Tender Evaluation: An Evidential Reasoning Ap...Study of Influencing Factors of Tender Evaluation: An Evidential Reasoning Ap...
Study of Influencing Factors of Tender Evaluation: An Evidential Reasoning Ap...
 
Quantity Surveyor’s Impact: A Panacea to achieving Critical Success Factors i...
Quantity Surveyor’s Impact: A Panacea to achieving Critical Success Factors i...Quantity Surveyor’s Impact: A Panacea to achieving Critical Success Factors i...
Quantity Surveyor’s Impact: A Panacea to achieving Critical Success Factors i...
 
Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...
Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...
Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...
 
P3CostOfCapitalPaperMarch2015
P3CostOfCapitalPaperMarch2015P3CostOfCapitalPaperMarch2015
P3CostOfCapitalPaperMarch2015
 
1_PPP paper_FINAL 05 17 16
1_PPP paper_FINAL 05 17 161_PPP paper_FINAL 05 17 16
1_PPP paper_FINAL 05 17 16
 
A COMPARATIVE STUDY ON PPP AND BOT MODEL OF WORKING CAPITAL MANAGEMENT IN MET...
A COMPARATIVE STUDY ON PPP AND BOT MODEL OF WORKING CAPITAL MANAGEMENT IN MET...A COMPARATIVE STUDY ON PPP AND BOT MODEL OF WORKING CAPITAL MANAGEMENT IN MET...
A COMPARATIVE STUDY ON PPP AND BOT MODEL OF WORKING CAPITAL MANAGEMENT IN MET...
 
Development of tendering duration models for federal government building proj...
Development of tendering duration models for federal government building proj...Development of tendering duration models for federal government building proj...
Development of tendering duration models for federal government building proj...
 
Strengthen outcome based capital project delivery
Strengthen outcome based capital project deliveryStrengthen outcome based capital project delivery
Strengthen outcome based capital project delivery
 
Summary of the OECD expert meeting: Construction Risk Management in Infrastru...
Summary of the OECD expert meeting: Construction Risk Management in Infrastru...Summary of the OECD expert meeting: Construction Risk Management in Infrastru...
Summary of the OECD expert meeting: Construction Risk Management in Infrastru...
 
Abt ppp
Abt pppAbt ppp
Abt ppp
 
IRJET- Factor Analysis of the Significant Drivers Causing Cost Variation in B...
IRJET- Factor Analysis of the Significant Drivers Causing Cost Variation in B...IRJET- Factor Analysis of the Significant Drivers Causing Cost Variation in B...
IRJET- Factor Analysis of the Significant Drivers Causing Cost Variation in B...
 
Ijetr042339
Ijetr042339Ijetr042339
Ijetr042339
 
Claims Management And Assessment Through Documentation
Claims Management And Assessment Through DocumentationClaims Management And Assessment Through Documentation
Claims Management And Assessment Through Documentation
 
A Multi-Objective Fuzzy Linear Programming Model for Cash Flow Management
A Multi-Objective Fuzzy Linear Programming Model for Cash Flow ManagementA Multi-Objective Fuzzy Linear Programming Model for Cash Flow Management
A Multi-Objective Fuzzy Linear Programming Model for Cash Flow Management
 
Pgpm14 infrastructure development
Pgpm14 infrastructure developmentPgpm14 infrastructure development
Pgpm14 infrastructure development
 
IRJET - Causes, Effects and Minimizing Methods of Construction Projects D...
IRJET -  	  Causes, Effects and Minimizing Methods of Construction Projects D...IRJET -  	  Causes, Effects and Minimizing Methods of Construction Projects D...
IRJET - Causes, Effects and Minimizing Methods of Construction Projects D...
 
Charging Ahead | Making Road User Pricing Work
Charging Ahead | Making Road User Pricing WorkCharging Ahead | Making Road User Pricing Work
Charging Ahead | Making Road User Pricing Work
 
Ippc seattle usa 2012
Ippc seattle usa  2012Ippc seattle usa  2012
Ippc seattle usa 2012
 
A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...
  A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...  A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...
A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...
 
Ijciet 08 02_005
Ijciet 08 02_005Ijciet 08 02_005
Ijciet 08 02_005
 

More from Tito Livio M. Cardoso

Probable Maximum Loss (PML) Evaluation
Probable Maximum Loss (PML) EvaluationProbable Maximum Loss (PML) Evaluation
Probable Maximum Loss (PML) Evaluation
Tito Livio M. Cardoso
 

More from Tito Livio M. Cardoso (20)

Tito Cardoso - Resumo - EN Junho-2023
Tito Cardoso - Resumo - EN Junho-2023Tito Cardoso - Resumo - EN Junho-2023
Tito Cardoso - Resumo - EN Junho-2023
 
Tito Cardoso - Resumo - PT Junho-2023
Tito Cardoso - Resumo - PT Junho-2023Tito Cardoso - Resumo - PT Junho-2023
Tito Cardoso - Resumo - PT Junho-2023
 
Probable Maximum Loss (PML) Evaluation
Probable Maximum Loss (PML) EvaluationProbable Maximum Loss (PML) Evaluation
Probable Maximum Loss (PML) Evaluation
 
Estimativa Parametrica de Custo de Transportador de Correia
Estimativa Parametrica de Custo de Transportador de CorreiaEstimativa Parametrica de Custo de Transportador de Correia
Estimativa Parametrica de Custo de Transportador de Correia
 
Use of the Bowtie Tool to Develop Regulatory Standards Focusing on Process Sa...
Use of the Bowtie Tool to Develop Regulatory Standards Focusing on Process Sa...Use of the Bowtie Tool to Develop Regulatory Standards Focusing on Process Sa...
Use of the Bowtie Tool to Develop Regulatory Standards Focusing on Process Sa...
 
Analise de riscos das alternativas
Analise de riscos das alternativasAnalise de riscos das alternativas
Analise de riscos das alternativas
 
Certificado DIO Especialaista Inovação Digital AD0B801B.pdf
Certificado DIO Especialaista Inovação Digital AD0B801B.pdfCertificado DIO Especialaista Inovação Digital AD0B801B.pdf
Certificado DIO Especialaista Inovação Digital AD0B801B.pdf
 
Certificado DIO Front-End Angular 1E8E60C7.pdf
Certificado DIO Front-End Angular 1E8E60C7.pdfCertificado DIO Front-End Angular 1E8E60C7.pdf
Certificado DIO Front-End Angular 1E8E60C7.pdf
 
Certificado DIO Fullstack developer - Banco carrefour 7B553D75.pdf
Certificado DIO Fullstack developer - Banco carrefour 7B553D75.pdfCertificado DIO Fullstack developer - Banco carrefour 7B553D75.pdf
Certificado DIO Fullstack developer - Banco carrefour 7B553D75.pdf
 
Dinâmica das contratações governamentais: Propostas para eficiência e satisfa...
Dinâmica das contratações governamentais: Propostas para eficiência e satisfa...Dinâmica das contratações governamentais: Propostas para eficiência e satisfa...
Dinâmica das contratações governamentais: Propostas para eficiência e satisfa...
 
Desenvolvimento de projetos em baixa das commodities
Desenvolvimento de projetos em baixa das commoditiesDesenvolvimento de projetos em baixa das commodities
Desenvolvimento de projetos em baixa das commodities
 
Riscos relacionadas a extensao de cronogramas - Schedule extension related risks
Riscos relacionadas a extensao de cronogramas - Schedule extension related risksRiscos relacionadas a extensao de cronogramas - Schedule extension related risks
Riscos relacionadas a extensao de cronogramas - Schedule extension related risks
 
Leasing de equipamentos industriais
Leasing de equipamentos industriaisLeasing de equipamentos industriais
Leasing de equipamentos industriais
 
Otimização da configuração do banco de baterias para navio híbrido
Otimização da configuração do banco de baterias para navio híbridoOtimização da configuração do banco de baterias para navio híbrido
Otimização da configuração do banco de baterias para navio híbrido
 
Utilizing a Self-Financing Strategy for Projects - BRG Review 7-1-2018
Utilizing a Self-Financing Strategy for Projects - BRG Review 7-1-2018Utilizing a Self-Financing Strategy for Projects - BRG Review 7-1-2018
Utilizing a Self-Financing Strategy for Projects - BRG Review 7-1-2018
 
Estratégia de Autofinanciamento de Projetos
Estratégia de Autofinanciamento de ProjetosEstratégia de Autofinanciamento de Projetos
Estratégia de Autofinanciamento de Projetos
 
Critério de decisão para implantação da infraestrutura em projetos implantado...
Critério de decisão para implantação da infraestrutura em projetos implantado...Critério de decisão para implantação da infraestrutura em projetos implantado...
Critério de decisão para implantação da infraestrutura em projetos implantado...
 
Decision criterion for anticipation of the infrastructure in staged projects
Decision criterion for anticipation of the infrastructure in staged projectsDecision criterion for anticipation of the infrastructure in staged projects
Decision criterion for anticipation of the infrastructure in staged projects
 
Analise de riscos da aplicação de novas tecnologias
Analise de riscos da aplicação de novas tecnologiasAnalise de riscos da aplicação de novas tecnologias
Analise de riscos da aplicação de novas tecnologias
 
Efeitos da incerteza na produtividade de serviços sobre o custo e prazo do pr...
Efeitos da incerteza na produtividade de serviços sobre o custo e prazo do pr...Efeitos da incerteza na produtividade de serviços sobre o custo e prazo do pr...
Efeitos da incerteza na produtividade de serviços sobre o custo e prazo do pr...
 

Recently uploaded

Call Girls In datia Escorts ☎️7427069034 🔝 💃 Enjoy 24/7 Escort Service Enjoy...
Call Girls In datia Escorts ☎️7427069034  🔝 💃 Enjoy 24/7 Escort Service Enjoy...Call Girls In datia Escorts ☎️7427069034  🔝 💃 Enjoy 24/7 Escort Service Enjoy...
Call Girls In datia Escorts ☎️7427069034 🔝 💃 Enjoy 24/7 Escort Service Enjoy...
nehasharma67844
 

Recently uploaded (20)

2024: The FAR, Federal Acquisition Regulations, Part 30
2024: The FAR, Federal Acquisition Regulations, Part 302024: The FAR, Federal Acquisition Regulations, Part 30
2024: The FAR, Federal Acquisition Regulations, Part 30
 
Sustainability by Design: Assessment Tool for Just Energy Transition Plans
Sustainability by Design: Assessment Tool for Just Energy Transition PlansSustainability by Design: Assessment Tool for Just Energy Transition Plans
Sustainability by Design: Assessment Tool for Just Energy Transition Plans
 
Pimpri Chinchwad ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi R...
Pimpri Chinchwad ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi R...Pimpri Chinchwad ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi R...
Pimpri Chinchwad ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi R...
 
The NAP process & South-South peer learning
The NAP process & South-South peer learningThe NAP process & South-South peer learning
The NAP process & South-South peer learning
 
Nanded City ? Russian Call Girls Pune - 450+ Call Girl Cash Payment 800573673...
Nanded City ? Russian Call Girls Pune - 450+ Call Girl Cash Payment 800573673...Nanded City ? Russian Call Girls Pune - 450+ Call Girl Cash Payment 800573673...
Nanded City ? Russian Call Girls Pune - 450+ Call Girl Cash Payment 800573673...
 
The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)
 
Call On 6297143586 Viman Nagar Call Girls In All Pune 24/7 Provide Call With...
Call On 6297143586  Viman Nagar Call Girls In All Pune 24/7 Provide Call With...Call On 6297143586  Viman Nagar Call Girls In All Pune 24/7 Provide Call With...
Call On 6297143586 Viman Nagar Call Girls In All Pune 24/7 Provide Call With...
 
Get Premium Budhwar Peth Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...
Get Premium Budhwar Peth Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...Get Premium Budhwar Peth Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...
Get Premium Budhwar Peth Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...
 
Tuvalu Coastal Adaptation Project (TCAP)
Tuvalu Coastal Adaptation Project (TCAP)Tuvalu Coastal Adaptation Project (TCAP)
Tuvalu Coastal Adaptation Project (TCAP)
 
Top Rated Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...
Top Rated  Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...Top Rated  Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...
Top Rated Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...
 
Call Girls In datia Escorts ☎️7427069034 🔝 💃 Enjoy 24/7 Escort Service Enjoy...
Call Girls In datia Escorts ☎️7427069034  🔝 💃 Enjoy 24/7 Escort Service Enjoy...Call Girls In datia Escorts ☎️7427069034  🔝 💃 Enjoy 24/7 Escort Service Enjoy...
Call Girls In datia Escorts ☎️7427069034 🔝 💃 Enjoy 24/7 Escort Service Enjoy...
 
World Press Freedom Day 2024; May 3rd - Poster
World Press Freedom Day 2024; May 3rd - PosterWorld Press Freedom Day 2024; May 3rd - Poster
World Press Freedom Day 2024; May 3rd - Poster
 
Top Rated Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...
Top Rated  Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...Top Rated  Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...
Top Rated Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...
 
Night 7k to 12k Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...
Night 7k to 12k  Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...Night 7k to 12k  Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...
Night 7k to 12k Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...
 
(NEHA) Call Girls Nagpur Call Now 8250077686 Nagpur Escorts 24x7
(NEHA) Call Girls Nagpur Call Now 8250077686 Nagpur Escorts 24x7(NEHA) Call Girls Nagpur Call Now 8250077686 Nagpur Escorts 24x7
(NEHA) Call Girls Nagpur Call Now 8250077686 Nagpur Escorts 24x7
 
Call On 6297143586 Yerwada Call Girls In All Pune 24/7 Provide Call With Bes...
Call On 6297143586  Yerwada Call Girls In All Pune 24/7 Provide Call With Bes...Call On 6297143586  Yerwada Call Girls In All Pune 24/7 Provide Call With Bes...
Call On 6297143586 Yerwada Call Girls In All Pune 24/7 Provide Call With Bes...
 
Postal Ballots-For home voting step by step process 2024.pptx
Postal Ballots-For home voting step by step process 2024.pptxPostal Ballots-For home voting step by step process 2024.pptx
Postal Ballots-For home voting step by step process 2024.pptx
 
An Atoll Futures Research Institute? Presentation for CANCC
An Atoll Futures Research Institute? Presentation for CANCCAn Atoll Futures Research Institute? Presentation for CANCC
An Atoll Futures Research Institute? Presentation for CANCC
 
Financing strategies for adaptation. Presentation for CANCC
Financing strategies for adaptation. Presentation for CANCCFinancing strategies for adaptation. Presentation for CANCC
Financing strategies for adaptation. Presentation for CANCC
 
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
 

DYNAMICS OF GOVERNMENT CONTRACTING: PROPOSALS FOR EFFICIENCY AND SATISFACTION OF PUBLIC NEEDS

  • 1. XX DYNAMICS OF GOVERNMENT CONTRACTING: PROPOSALS FOR EFFICIENCY AND SATISFACTION OF PUBLIC NEEDS 1 Felipe Di Stefano Pereira, 2 Tito Livio Medeiros Cardoso, 3 Erica Braga, 4 Debora Francisco Lalo 1,2,3 BRG Berkeley Research Group, São Paulo, Brazil 4 Department of Mechanical Engineering, University Center of FEI, São Bernardo do Campo, São Paulo Email: 1 fpereira@thinkbrg.com, 2 tcardoso@thinkbrg.com, 3 ebraga@thinkbrg.com 4 dflalo@fei.edu.br Abstract: The present article aims to present a proposal for efficiency and satisfaction of public needs related to government contracting, given the notorious cases of low efficiency in investments of public interest around the world. To understand the various factors involved, a comparative study was first carried out between public procurement processes and their requirements in different countries. A generic and hypothetical case was then modeled in the form of a simple dynamic system related to government contracting. This way, the authors suggest that, even in a selection system based on the lowest price, it is possible to obtain design and construction quality since some conditions, which will be presented throughout the article, are implemented. Index terms: Government Contracting, Public Investment, Public Projects, Infrastructure. I. INTRODUCTION Infrastructure projects are of broad interest to society for achieving the objectives, such as meeting the growing demand for services by the population, implementing public policies, increasing efficiency in the use of resources (financial and natural), improving regional competitiveness and national attraction of foreign capital, development of sectors such as tourism and lodging, generation of jobs, among others. In spite of this relevance, the cases of low efficiency in the investments of public interest are notorious, as shown in Figure 1. Figure 1: Significant cost overruns and delays in various public interest projects [1] Low efficiency in public investments are observed in locations as diverse as the US, where road projects in 2009 were executed 40% above bid amounts (equivalent to USD 1.2 billion overflow), as in Canada, where a sample of 50 road projects had a cost overrun of 82% in 2006 [8], Nigeria, where 92.3% of building projects in a sample of 2017 showed average growth of 20% in relation to contracted budget [2] and Palestine, where , in a sample of 169 road projects, 76% presented construction cost increases in relation to the budget [3]. In other countries, the problems extend to the operational phase. As an example, in 2016, 78.4% of 105,814 km of Brazilian federal highways presented conditions that compromise transportation performance and driver safety, with 42% of the extension having pavement problems and 55% signaling problems [4]. A set of statistical analyses and research indicate that project changes during execution are a factor which influences project cost deviations [5, 8] and the relative deviations may be even greater in projects of smaller extent than in larger ones [6]. Locational factors are also identified [5, 6]. These factors, in turn, refer to the planning deficiency in the pre-construction phase and insufficient feasibility studies, including estimation errors and scope definition gaps [8]. A comparison between studies conducted in developing and Asian countries shows agreement on factors related to inadequate initial planning, financial constraints, cash flow problems of management and poor contract management [5]. Due to these problems the contracting systems of public projects in the various countries have frequently been the subject of comparisons and analyses [9,10,11,12]. Table 1 presents a summary of the processes for contracting consultancies and public works in several countries. The systems used by the countries present important differences. Public works contracting systems differ widely between countries and, in particular, we note the differences between the criteria for qualification of tenderers and evaluation of tenders. In spite of differences in details and nomenclatures, two central lines of reasoning stand out: one objective is the "lowest price" (USA, Japan, India, Brazil) and the other "highest value" (US, UK, France, Germany, Sweden).
  • 2. Dynamics of Government Contracting: Proposals for Efficiency and Satisfaction of Public Needs 523rd International Conference on Science, Technology, Engineering and Management (ICSTEM), 12th-13th Jan. Paris. ISBN: XX XX Table 1- Comparative summary of public procurement processes and their requirements in different countries. Based on [9] and [10]
  • 3. Dynamics of Government Contracting: Proposals for Efficiency and Satisfaction of Public Needs 523rd International Conference on Science, Technology, Engineering and Management (ICSTEM), 12th-13th Jan. Paris. ISBN: XX XX The "highest value" evaluation covers several methods ranging from the most objective, in the economic quantification of Value for Money (VFM), to a system of weights and factor scores, which in many cases includes the price of service, to more subjective analyses, consolidated in the form of descriptive narratives. According to the OECD, Value for Money (VMF) is the ideal combination of cost and quality over the life of the asset (or suitability for the purpose) to meet user needs. It can be evaluated using the criteria of economy, efficiency and effectiveness [15]. The World Bank guides the use of the factor and weighting system to achieve Value for Money in contracting works, [16] but, interestingly, we see countries that predominantly contract for the lowest price criterion and in general, good performance of contracted services is obtained - as the case of Japan – on the other hand, when the best value evaluation systems are used, not always the good cost and time performance of works are obtained - as the case of US. In the details the differences are shown even in the more objective or more bureaucratic way, in which public administrations are issuing notices to the market. As an example, Figure 2 shows an example of an edict focusing on the results previously obtained by the proposer in previous projects - note that there are no criteria as to where the results were obtained. In other situations, we observed a notice for the hiring of the same service that included in the requirements, a technical file registered in an organization of the country, that the collection should refer to services performed in the country, establishing requirements of the profession of the team that would conduct the work ("only engineers", etc.) - and with all this, without establishing a single line on the actual results obtained by the company in past jobs, in the country or in the world. In their comparison of the qualification criteria used for contracting public works in the Czech Republic and Poland, the authors stated: “Qualification criteria (QC) can be identified as an important risk of corruption. For instance, methodology for local governments notes, that determination of unnecessarily strict QC for suppliers to the subject of the contract results in the elimination of effective competition and contracts can be even tailored to pre-selected contractor.” [12] These differences indicate that there are multiple factors and differences influencing the performance of public projects. Figure 2: Requirements for qualification of tenderers in public tender for contracting planning of public sanitation infrastructure projects. Banning, California (USA) [14] II. UNDERSTANDING THE CONTRACTING OF PUBLIC PROJECTS AS A DYNAMIC SYSTEM To understand the various factors involved in contracting a public project, let us model a generic and hypothetical case in the form of a simple dynamic system. The system in Figure 3 describes the following case:  A locality with an infrastructure deficit generates a flow of annual demand for project bids in the design-bid-build format to meet the public needs;  A certain technically qualified constructor competes for projects by proposing a construction price that determines their success rate in these bids - the negative sign in the relationship between "construction price" and "bid success rate" identifies that the lower the price the higher the success rate);  The number of annual bids and the success rate determine the number of projects under construction, which accumulates at each annual round of new bids;  For simplicity, the builder is paid monthly (fixed installments of the constructions price in stock, divided by the construction period), a fraction of this amount being his profit;  The stock of projects under construction decreases as a result of the projects flow that were completed - which depends on the construction period;  Completed projects increase the satisfaction of public needs, decreasing the flow of new bids for the following year - characterized by
  • 4. Dynamics of Government Contracting: Proposals for Efficiency and Satisfaction of Public Needs 523rd International Conference on Science, Technology, Engineering and Management (ICSTEM), 12th-13th Jan. Paris. ISBN: XX XX a negative sign in the relationship between "satisfying the public needs" and "bidding";  The inventory of projects under construction can also be reduced by the cancellation flow of contracts. In this case, however, public needs are not met. Figure 3 - Simple dynamic system representing a hypothetical case of contracting public projects Even such a simple model exposes a conflict from the outset, the relationship between price, success rate in bidding and profit is the opposite, that is, lower prices increase the success rate, but reduce the amount of profit. In Figure 4 we observe at least two forms, which are not mutually exclusive, for the constructor to increase his profit in the same conditions presented in the case: i. If there are delays in construction, the builder will submit claims on schedule extension and the delay period will add up to the initial construction period, increasing the billing period so that the total cost of the work exceeds the bid price - as if observed in the United States and, previously, in the United Kingdom (see table 1). According to the referenced research and studies, the poor quality of engineering and planning projects is a source of delays in the construction of public works. In Figure 4 this relation is evidenced by the negative sign between " project quality" and "delays": the lower the quality of the project, the greater the delays. ii. If the construction quality is lower, the builder's profit is higher, regardless of the project quality (for example, by using lower materials or smaller quantities than engineering project size). Figure 4 shows that as a side effect, since the relationship is positive, low quality of construction reduces the satisfaction of public needs, which in turn increases the demand for bids, forming a vicious cycle that repeats itself. Figure 4 - Dynamic system, now considering the quality of the engineering design and the quality of the construction (in red) Figure 5 presents the same dynamic system where management now responds to the delays and poor quality of construction through the application of fines and contracts cancellation. The negative relationship indicates that more fines reduce the builder's profit as well, contracts cancellation reduces the inventory of projects under construction which directly reduces profit. Figure 5 - Dynamic system, now considering responses in the form of fines and cancellation of contracts However, this set of responses has at least two drawbacks:  Cancellation of contracts reduces the inventory of projects under construction before they are completed, preventing the fulfillment of the public needs.  In practice, in many administrations, there is a delay between the time of delays and loss of quality in the construction and the instant of penalties application - the questioning occurs after construction, reducing or canceling its effect as corrective action.
  • 5. Dynamics of Government Contracting: Proposals for Efficiency and Satisfaction of Public Needs 523rd International Conference on Science, Technology, Engineering and Management (ICSTEM), 12th-13th Jan. Paris. ISBN: XX XX Figure 6 presents another response to the problem in the form of a negative feedback loop where delays and quality of construction reduce the success rate of the builder in the new bids. At the same time, proactive management action in attracting other builders and new entrants to the local market will further dilute the contractor's success rate unless it builds good quality projects without delays breaking the vicious cycle of feedback. This approach is a long-term solution with a focus on the wide competition and is part of the concept of layered antifragility, exposed by Table [13], as the ability of a system to acquire resilience and evolve from the confrontation experienced by the subunits that comprise it. For example, when local restaurants compete between themselves it results in the antifragility of the collective in the local sector. If the restaurants were individually robust, the overall business would either be stagnant or weak and offer nothing more than standard meals. The sector would also be more exposed to systemic crises. Figure 6 - Dynamic system, now considering a negative process feedback cycle (in green). CONCLUSION The comparison of consulting and works contracting systems by the administrations of several countries demonstrates that the achievement of efficiency and satisfaction of the public needs present several underlying factors that prevent the reduction of the problem to a trivial definition of criteria for the qualification and selection of bidders, such as "lower price" versus "higher value". The present work, through the study of dynamics in a simple hypothetical case, suggests that even in a selection system based on the lowest price, it is possible to obtain design and construction quality since some conditions are provided:  Criteria for qualification and selection based on the performance of the company in previous projects, objectively characterized.  Encouraging layered antifragility by expanding the supplier market and diluting the relative importance of larger local players by encouraging new or local suppliers to enter.  To enable this, proactive actions by the local public administration may include: o the bilingual bidding, considering more universalized criteria and nomenclatures; o International presentation of the pipeline of public projects; o Exclusion of bureaucratic requirements for registration in local organizations, or previous experience in the field.  Real-time control of the building's physical progress. Transparency and publicity of the performance of projects under construction.  Bids based only on engineering executive projects, including definitive construction plan. These conclusions were derived directly from the dynamic system analyzed, respectively, acting on the variables "Other constructors and new entrants", "construction quality " and "design quality" in the complete model of Figure 5. Extensions of this work can be done detailing the steps which precede the bidding, as well as the systematic control of public administration, among other possibilities. ACKNOWLEDGMENTS The authors acknowledge Claudio Graeff (Construction Director of BRG Brazil) and University Center of FEI. REFERENCES [1] “The century’s most troublesome construction projects”, accessed in: 11/06/18, http://www.globalconstructionreview. com/perspectives/centurys-most-troublesome-construction- pr8oje8ct8s/ [2] KADIRI, Dele S.; ONABANJO, Babajide O. “Cost and Time Overruns in Building Projects Procured Using Traditional Contracts in Nigeria.” Journal of Sustainable Development, v. 10, n. 5, p. 234, 2017. [3] MAHAMID, Ibrahim. “Analysis of cost deviations in road construction activities: A case study from Palestine.” Jordan Journal of Civil Engineering, v. 5, n. 4, p. 552-567, 2011. [4] CNT (Confederação Nacional do Transporte) “Transporte rodoviário: desempenho do setor, infraestrutura e investimentos”, Brasília, 2017. [5] SWEIS, Ghaleb J. et al. “Cost overruns in public construction projects: the case of Jordan.” Journal of American Science, v. 9, n. 7, p. 134-141, 2013. [6] ODECK, James. “Cost overruns in road construction—what are their sizes and determinants?” Transport policy, v. 11, n. 1, p. 43-53, 2004.
  • 6. Dynamics of Government Contracting: Proposals for Efficiency and Satisfaction of Public Needs 523rd International Conference on Science, Technology, Engineering and Management (ICSTEM), 12th-13th Jan. Paris. ISBN: XX XX [7] RAMABHADRAN, Muralidaran. “An Investigation into Cost Overrun in Construction Projects in United Arab Emirates.” International Journal of Construction Engineering and Management, v. 7, n. 1, p. 1-21, 2018. [8] SAIDU, Ibrahim; SHAKANTU, Winston. “An investigation into cost overruns for ongoing building projects in Abuja, Nigeria.” Acta Structilia, v. 24, n. 1, p. 53-72, 2017. [9] OHNO, Taishi; HARADA, Yuhei. “A Comparison of tendering and contracting systems for public works between Japan, the United States and EU countries.” Government Auditing Review, v. 13, p. 49-71, 2006. [10] GAZULA, Sriharsha; VADALI, Anil Kumar. “Comparison of Public Tender Process between Sweden and India.” 2012. [11] PETRISOR, Mihai-Bogdan. “Comparison of the Public Procurement System in Romania and the UK.” EIRP Proceedings, v. 10, 2015. [12] KORYTÁROVÁ, Jana et al. “Exploring the contractors’ qualification process in public works contracts.” Procedia Engineering, v. 123, p. 276-283, 2015. [13] TALEB, Nassim Nicholas. “Antifragile: Things that gain from disorder”, 2012. [14] “RFP 2016-009, Request for proposal (RFP) for integrated master plan for water, wastewater and recycled water systems”, City of Banning, Public Works Department. September 16, 2016. [15] JACKSON, Penny. “Value for money and international development: Deconstructing myths to promote a more constructive discussion.” Organization for Economic Cooperation and Development, 2012. [16] “Procurement Guidance - Use of evaluation criteria for procurement of Goods, Works, and Non-Consulting Services using RFB and RFP”, World Bank, July 2016. 