Activity ID Activity Name Original
Duration
Start Finish BL Project
Start
BL Project
Finish
Zewail City of SciZewail City of Science and Technology B4 Contract 582 02-May-15 17-Nov-16 02-May-15 14-Apr-16
GeneralGeneral 582 02-May-15 17-Nov-16 02-May-15 14-Apr-16
ZB4G0010 Letter of Intent 0 02-May-15 02-May-15
ZB4G0020 Receive Final Design Drawings and Specifications 0 26-Oct-15 03-May-15
ZB4G0030 Down Payment 0 10-Feb-16 24-May-15
ZB4G0040 Letter of Award 0 16-Feb-16 24-May-15
ZB4G0060 Full Release Service Tunnel For MEP Works 0 05-Jul-15 06-Jun-15
ZB4G0062 Release Building B4-A For MEP Work ( Masonry Works ) 0 14-Jun-15 14-Jun-15
ZB4G0064 Release Building B4-B For MEPWork ( Masonry Works ) 0 16-Jul-15 14-Jun-15
ZB4G0050 Mobilization 15 17-Feb-16 05-Mar-16 30-May-15 15-Jun-15
ZB4G0066 Release Building B4-D For MEPWork ( Masonry Works ) 0 03-Sep-15 01-Jul-15
ZB4G0068 Release Building B4-E For MEPWork ( Masonry Works ) 0 27-Aug-15 01-Jul-15
ZB4G0070 Provide Permanent Electrical / Gas / Water / Drainage Sources 0 03-Sep-16 15-Aug-15
ZB4G0076 Release Building B4-D Finishing Work ( For Equipment Installation ) 0 05-May-16 18-Aug-15
ZB4G0074 Release Building B4-B Finishing Work ( For Equipment Installation ) 0 23-Mar-16 01-Sep-15
ZB4G0072 Release Building B4-A Finishing Work ( For Equipment Installation ) 0 03-Nov-15 05-Sep-15
ZB4G0078 Release Building B4-E Finishing Work ( For Equipment Installation ) 0 26-Apr-16 05-Sep-15
ZB4G0088 Release Site Layout For MEPWork ( MV, LV and SCADA Networks
Works )
0 09-Feb-16 04-Nov-15
ZB4G0098 Release Site Layout For MEPWork ( Solar LED Exterior Lighting
Works )
0 04-Jun-16 28-Feb-16
ZB4G0090 Project Hand Over 0 17-Nov-16 14-Apr-16
ZB4G0080 Project Testing & Commissioning 60 03-Sep-16 17-Nov-16 06-Feb-16 14-Apr-16
EngineeringEngineering 261 26-Oct-15 03-Nov-16 03-May-15 10-Jan-16
Building B4 - A (MBuilding B4 - A (Mechanical Utilities) 177 26-Oct-15 18-Aug-16 03-May-15 21-Oct-15
ZB4G000010 Basic Engineering Study 18 26-Oct-15 18-Nov-15 03-May-15 26-May-15
Basement FloorBasement Floor 90 19-Nov-15 11-May-16 27-May-15 20-Aug-15
Electrical SystemElectrical Systems 90 22-Dec-15 11-May-16 27-May-15 20-Aug-15
Power SystemPower System 15 11-Jan-16 18-Feb-16 01-Jul-15 14-Jul-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
2015 2016 2017
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings_1 18-Feb-16 09:32
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 1 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish BL Project
Start
BL Project
Finish
ZB4AEBEPS10 BASEMENT FLOOR POWER SYSTEM LAYOUT PLAN
SUBMITTAL
5 11-Jan-16 17-Jan-16 01-Jul-15 07-Jul-15
ZB4AEBEPA10 BASEMENT FLOOR POWER SYSTEM LAYOUT PLAN
APPROVAL
5 14-Feb-16 18-Feb-16 08-Jul-15 14-Jul-15
Lighting SystemLighting System 15 27-Dec-15 18-Feb-16 27-May-15 09-Jun-15
ZB4AEBELS10 BASEMENT FLOOR LIGHTING SYSTEM LAYOUT PLAN
SUBMITTAL
5 27-Dec-15 31-Dec-15 27-May-15 02-Jun-15
ZB4AEBELA10 BASEMENT FLOOR LIGHTING SYSTEM LAYOUT PLAN
APPROVAL
5 14-Feb-16 18-Feb-16 03-Jun-15 09-Jun-15
Cable Tray SysCable Tray System 15 27-Dec-15 18-Feb-16 01-Jul-15 14-Jul-15
ZB4AEBECS10 BASEMENT FLOOR CABLE TRAY SYSTEM LAYOUT PLAN
SUBMITTAL
5 27-Dec-15 31-Dec-15 01-Jul-15 07-Jul-15
ZB4AEBECA10 BASEMENT FLOOR CABLE TRAY SYSTEM LAYOUT PLAN
APPROVAL
5 14-Feb-16 18-Feb-16 08-Jul-15 14-Jul-15
Earthing SysteEarthing System 15 03-Jan-16 18-Feb-16 08-Jul-15 22-Jul-15
ZB4AEBEES10 BASEMENT FLOOR EARTHING SYSTEM LAYOUT PLAN
SUBMITTAL
5 03-Jan-16 10-Jan-16 08-Jul-15 14-Jul-15
ZB4AEBEEA10 BASEMENT FLOOR EARTHING SYSTEM LAYOUT PLAN
APPROVAL
5 14-Feb-16 18-Feb-16 15-Jul-15 22-Jul-15
Light Current SLight Current Systems 24 22-Dec-15 18-Feb-16 27-May-15 17-Jun-15
Fire Alarm SyFire Alarm System 15 22-Dec-15 18-Feb-16 27-May-15 09-Jun-15
ZB4AEBELFS10 BASEMENT FLOOR FIRE ALARM SYSTEM LAYOUT PLAN
SUBMITTAL
5 22-Dec-15 29-Dec-15 27-May-15 02-Jun-15
ZB4AEBELFA10BASEMENT FLOOR FIRE ALARM SYSTEM LAYOUT PLAN
APPROVAL
5 14-Feb-16 18-Feb-16 03-Jun-15 09-Jun-15
Security SystSecurity Systems 15 03-Jan-16 18-Feb-16 01-Jun-15 14-Jun-15
ZB4AEBELSS10 BASEMENT FLOOR SECURITY SYSTEMS LAYOUT PLAN
SUBMITTAL
5 03-Jan-16 10-Jan-16 01-Jun-15 07-Jun-15
ZB4AEBELSA10BASEMENT FLOOR SECURITY SYSTEMS LAYOUT PLAN
APPROVAL
5 14-Feb-16 18-Feb-16 08-Jun-15 14-Jun-15
CommunicatiCommunication Systems 15 07-Feb-16 18-Feb-16 04-Jun-15 17-Jun-15
ZB4AEBELCS10BASEMENT FLOOR COMMUNICATION SYSTEMS LAYOUT
PLAN SUBMITTAL
5 07-Feb-16 11-Feb-16 04-Jun-15 10-Jun-15
ZB4AEBELCA10BASEMENT FLOOR COMMUNICATION SYSTEMS LAYOUT
PLAN APPROVAL
5 14-Feb-16 18-Feb-16 11-Jun-15 17-Jun-15
SCADA SystemSCADA System 14 07-Mar-16 11-May-16 09-Aug-15 20-Aug-15
ZB4AEBEDS10 BASEMENT FLOOR SCADA SYSTEM LAYOUT PLAN
SUBMITTAL
5 07-Mar-16 13-Mar-16 09-Aug-15 13-Aug-15
ZB4AEBEDA10 BASEMENT FLOOR SCADA SYSTEM LAYOUT PLAN
APPROVAL
5 05-May-16 11-May-16 16-Aug-15 20-Aug-15
Mechanical SystMechanical Systems 30 19-Nov-15 03-Mar-16 27-May-15 23-Jun-15
HVAC SystemHVAC System 30 19-Nov-15 03-Mar-16 27-May-15 23-Jun-15
ZB4AEBMHS10 BASEMENT FLOOR HVAC SYSTEM LAYOUT PLAN
SUBMITTAL
15 19-Nov-15 09-Dec-15 27-May-15 16-Jun-15
ZB4AEBMHS20 BASEMENT FLOOR HVAC SECTIONS LAYOUT PLAN
SUBMITTAL
15 03-Dec-15 24-Dec-15 27-May-15 16-Jun-15
ZB4AEBMHA10 BASEMENT FLOOR HVAC SYSTEM LAYOUT PLAN APPROVAL 5 14-Feb-16 18-Feb-16 17-Jun-15 23-Jun-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
2015 2016 2017
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings_1 18-Feb-16 09:32
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 2 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish BL Project
Start
BL Project
Finish
ZB4AEBMHA20 BASEMENT FLOOR HVAC SYSTEM LAYOUT PLAN APPROVAL 5 28-Feb-16 03-Mar-16 17-Jun-15 23-Jun-15
Fire ProtectionFire Protection Systems 22 18-Jan-16 18-Feb-16 27-May-15 16-Jun-15
ZB4AEBMFS10 BASEMENT FLOOR FIRE PROTECTION SYSTEM LAYOUT
PLAN SUBMITTAL
10 18-Jan-16 01-Feb-16 27-May-15 09-Jun-15
ZB4AEBMFA10 BASEMENT FLOOR FIRE PROTECTION SYSTEM LAYOUT
PLAN APPROVAL
5 14-Feb-16 18-Feb-16 10-Jun-15 16-Jun-15
Plumbing SystPlumbing System 30 27-Dec-15 03-Mar-16 27-May-15 23-Jun-15
ZB4AEBMWS10 BASEMENT FLOOR WATER SUPPLY SYSTEM LAYOUT PLAN
SUBMITTAL
5 02-Feb-16 08-Feb-16 27-May-15 02-Jun-15
ZB4AEBMDS10 BASEMENT FLOOR DRAINAGE SYSTEM LAYOUT PLAN
SUBMITTAL
5 27-Dec-15 31-Dec-15 27-May-15 02-Jun-15
ZB4AEBMWA10 BASEMENT FLOOR WATER SUPPLY SYSTEM LAYOUT PLAN
APPROVAL
5 14-Feb-16 18-Feb-16 03-Jun-15 09-Jun-15
ZB4AEBMDA10 BASEMENT FLOOR DRAINAGE SYSTEM LAYOUT PLAN
APPROVAL
5 14-Feb-16 18-Feb-16 03-Jun-15 09-Jun-15
ZB4AEBMWS20 WATER SUPPLY PUMP ROOM DETAILS & SECTIONS
SUBMITTAL
15 07-Feb-16 25-Feb-16 27-May-15 16-Jun-15
ZB4AEBMWA20 WATER SUPPLY PUMP ROOM DETAILS & SECTIONS
APPROVAL
5 28-Feb-16 03-Mar-16 17-Jun-15 23-Jun-15
Composite DrawComposite Drawing 14 21-Feb-16 03-Mar-16 26-Jul-15 06-Aug-15
ZB4AEBCS10 BASEMENT FLOOR COMPOSITE LAYOUT PLAN SUBMITTAL 5 21-Feb-16 25-Feb-16 26-Jul-15 30-Jul-15
ZB4AEBCA10 BASEMENT FLOOR COMPOSITE LAYOUT PLAN APPROVAL 5 28-Feb-16 03-Mar-16 02-Aug-15 06-Aug-15
Ground FloorGround Floor 90 10-Dec-15 18-Aug-16 03-Jun-15 27-Aug-15
ZB4AEGGBS10 Ground Floor Builder Work Submittal 5 31-Mar-16 06-Apr-16 02-Aug-15 06-Aug-15
ZB4AEGGBA10 Ground Floor Builder Work Approval 5 07-Apr-16 13-Apr-16 09-Aug-15 13-Aug-15
Electrical SystemElectrical Systems 90 30-Dec-15 11-May-16 03-Jun-15 27-Aug-15
Power SystemPower System 15 18-Jan-16 28-Feb-16 08-Jul-15 22-Jul-15
ZB4AEGEPS10 GROUND FLOOR POWER SYSTEM LAYOUT PLAN SUBMITTAL 5 18-Jan-16 24-Jan-16 08-Jul-15 14-Jul-15
ZB4AEGEPA10 GROUND FLOOR POWER SYSTEM LAYOUT PLAN APPROVAL 5 22-Feb-16 28-Feb-16 15-Jul-15 22-Jul-15
Lighting SystemLighting System 15 03-Jan-16 07-Mar-16 03-Jun-15 16-Jun-15
ZB4AEGELS10 GROUND FLOOR LIGHTING SYSTEM LAYOUT PLAN
SUBMITTAL
5 03-Jan-16 10-Jan-16 03-Jun-15 09-Jun-15
ZB4AEGELA10 GROUND FLOOR LIGHTING SYSTEM LAYOUT PLAN
APPROVAL
5 01-Mar-16 07-Mar-16 10-Jun-15 16-Jun-15
Cable Tray SysCable Tray System 15 05-Jan-16 07-Mar-16 08-Jul-15 22-Jul-15
ZB4AEGECS10 GROUND FLOOR CABLE TRAY SYSTEM LAYOUT PLAN
SUBMITTAL
5 05-Jan-16 12-Jan-16 08-Jul-15 14-Jul-15
ZB4AEGECA10 GROUND FLOOR CABLE TRAY SYSTEM LAYOUT PLAN
APPROVAL
5 01-Mar-16 07-Mar-16 15-Jul-15 22-Jul-15
Earthing SysteEarthing System 15 11-Jan-16 07-Mar-16 15-Jul-15 30-Jul-15
ZB4AEGEES10 GROUND FLOOR EARTHING SYSTEM LAYOUT PLAN
SUBMITTAL
5 11-Jan-16 17-Jan-16 15-Jul-15 22-Jul-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
2015 2016 2017
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings_1 18-Feb-16 09:32
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 3 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish BL Project
Start
BL Project
Finish
ZB4AEGEEA10 GROUND FLOOR EARTHING SYSTEM LAYOUT PLAN
APPROVAL
5 01-Mar-16 07-Mar-16 26-Jul-15 30-Jul-15
Light Current SLight Current Systems 24 30-Dec-15 07-Mar-16 03-Jun-15 24-Jun-15
Fire Alarm SyFire Alarm System 15 30-Dec-15 07-Mar-16 03-Jun-15 16-Jun-15
ZB4AEGELFS10GROUND FLOOR FIRE ALARM SYSTEM LAYOUT PLAN
SUBMITTAL
5 30-Dec-15 05-Jan-16 03-Jun-15 09-Jun-15
ZB4AEGELFA10GROUND FLOOR FIRE ALARM SYSTEM LAYOUT PLAN
APPROVAL
5 01-Mar-16 07-Mar-16 10-Jun-15 16-Jun-15
Security SystSecurity Systems 15 11-Jan-16 07-Mar-16 08-Jun-15 21-Jun-15
ZB4AEGELSS10 GROUND FLOOR SECURITY SYSTEMS LAYOUT PLAN
SUBMITTAL
5 11-Jan-16 17-Jan-16 08-Jun-15 14-Jun-15
ZB4AEGELSA10GROUND FLOOR SECURITY SYSTEMS LAYOUT PLAN
APPROVAL
5 01-Mar-16 07-Mar-16 15-Jun-15 21-Jun-15
CommunicatiCommunication Systems 15 23-Feb-16 07-Mar-16 11-Jun-15 24-Jun-15
ZB4AEGELCS10GROUND FLOOR COMMUNICATION SYSTEMS LAYOUT PLAN
SUBMITTAL
5 23-Feb-16 29-Feb-16 11-Jun-15 17-Jun-15
ZB4AEGELCA10GROUND FLOOR COMMUNICATION SYSTEMS LAYOUT PLAN
APPROVAL
5 01-Mar-16 07-Mar-16 18-Jun-15 24-Jun-15
SCADA SystemSCADA System 14 14-Mar-16 11-May-16 16-Aug-15 27-Aug-15
ZB4AEGEDS10 GROUND FLOOR SCADA SYSTEM LAYOUT PLAN SUBMITTAL 5 14-Mar-16 20-Mar-16 16-Aug-15 20-Aug-15
ZB4AEGEDA10 GROUND FLOOR SCADA SYSTEM LAYOUT PLAN APPROVAL 5 05-May-16 11-May-16 23-Aug-15 27-Aug-15
Mechanical SystMechanical Systems 45 10-Dec-15 18-Aug-16 03-Jun-15 14-Jul-15
HVAC SystemHVAC System 30 10-Dec-15 14-Jun-16 17-Jun-15 14-Jul-15
ZB4AEGMHS10 GROUND FLOOR HVAC SYSTEM LAYOUT PLAN SUBMITTAL 15 10-Dec-15 31-Dec-15 17-Jun-15 07-Jul-15
ZB4AEGMHS20 GROUND FLOOR HVAC SECTIONS LAYOUT PLAN SUBMITTAL 15 27-Dec-15 17-Jan-16 17-Jun-15 07-Jul-15
ZB4AEGMHA10 GROUND FLOOR HVAC SYSTEM LAYOUT PLAN APPROVAL 5 01-Mar-16 07-Mar-16 08-Jul-15 14-Jul-15
ZB4AEGMHA20 GROUND FLOOR HVAC SYSTEM LAYOUT PLAN APPROVAL 5 08-Jun-16 14-Jun-16 08-Jul-15 14-Jul-15
Fire ProtectionFire Protection Systems 22 02-Feb-16 18-Aug-16 10-Jun-15 30-Jun-15
ZB4AEGMFS10 GROUND FLOOR FIRE PROTECTION SYSTEM LAYOUT PLAN
SUBMITTAL
5 02-Feb-16 08-Feb-16 10-Jun-15 16-Jun-15
ZB4AEGMFA10 GROUND FLOOR FIRE PROTECTION SYSTEM LAYOUT PLAN
APPROVAL
5 23-Feb-16 29-Feb-16 17-Jun-15 23-Jun-15
ZB4AEGMFS20 FIRE PROTECTION WORK - SPECIAL SYSTEM DETAILS
SUBMITTAL
5 07-Aug-16 11-Aug-16 17-Jun-15 23-Jun-15
ZB4AEGMFA20 FIRE PROTECTION WORK - SPECIAL SYSTEM DETAILS
APPROVAL
5 14-Aug-16 18-Aug-16 24-Jun-15 30-Jun-15
Plumbing SystPlumbing System 15 03-Jan-16 07-Mar-16 03-Jun-15 16-Jun-15
ZB4AEGMWS10 GROUND FLOOR WATER SUPPLY SYSTEM LAYOUT PLAN
SUBMITTAL
5 09-Feb-16 15-Feb-16 03-Jun-15 09-Jun-15
ZB4AEGMDS10 GROUND FLOOR DRAINAGE SYSTEM LAYOUT PLAN
SUBMITTAL
5 03-Jan-16 10-Jan-16 03-Jun-15 09-Jun-15
ZB4AEGMWA10 GROUND FLOOR WATER SUPPLY SYSTEM LAYOUT PLAN
APPROVAL
5 01-Mar-16 07-Mar-16 10-Jun-15 16-Jun-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
2015 2016 2017
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings_1 18-Feb-16 09:32
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 4 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish BL Project
Start
BL Project
Finish
ZB4AEGMDA10 GROUND FLOOR DRAINAGE SYSTEM LAYOUT PLAN
APPROVAL
5 01-Mar-16 07-Mar-16 10-Jun-15 16-Jun-15
Composite DrawComposite Drawing 14 08-Mar-16 21-Mar-16 02-Aug-15 13-Aug-15
ZB4AEGCS10 GROUND FLOOR COMPOSITE LAYOUT PLAN SUBMITTAL 5 08-Mar-16 14-Mar-16 02-Aug-15 06-Aug-15
ZB4AEGCA10 GROUND FLOOR COMPOSITE LAYOUT PLAN APPROVAL 5 15-Mar-16 21-Mar-16 09-Aug-15 13-Aug-15
Roof 1Roof 1 90 03-Jan-16 11-May-16 10-Jun-15 03-Sep-15
ZB4AERGBS10 Roof 1 Builder Work Submittal 5 31-Mar-16 06-Apr-16 09-Aug-15 13-Aug-15
ZB4AERGBA10 Roof 1 Builder Work Approval 5 07-Apr-16 13-Apr-16 16-Aug-15 20-Aug-15
Electrical SystemElectrical Systems 90 06-Jan-16 11-May-16 10-Jun-15 03-Sep-15
Power SystemPower System 7 26-Jan-16 28-Feb-16 15-Jul-15 22-Jul-15
ZB4AEREPS10 ROOF 1 FLOOR POWER SYSTEM LAYOUT PLAN SUBMITTAL 5 26-Jan-16 01-Feb-16 15-Jul-15 22-Jul-15
ZB4AEREPA10 ROOF 1 FLOOR POWER SYSTEM LAYOUT PLAN APPROVAL 5 22-Feb-16 28-Feb-16 15-Jul-15 22-Jul-15
Lighting SystemLighting System 15 11-Jan-16 07-Mar-16 10-Jun-15 23-Jun-15
ZB4AERELS10 ROOF 1 FLOOR LIGHTING SYSTEM LAYOUT PLAN
SUBMITTAL
5 11-Jan-16 17-Jan-16 10-Jun-15 16-Jun-15
ZB4AERELA10 ROOF 1 FLOOR LIGHTING SYSTEM LAYOUT PLAN APPROVAL 5 01-Mar-16 07-Mar-16 17-Jun-15 23-Jun-15
Cable Tray SysCable Tray System 15 13-Jan-16 07-Mar-16 15-Jul-15 30-Jul-15
ZB4AERECS10 ROOF 1 FLOOR CABLE TRAY SYSTEM LAYOUT PLAN
SUBMITTAL
5 13-Jan-16 19-Jan-16 15-Jul-15 22-Jul-15
ZB4AERECA10 ROOF 1 FLOOR CABLE TRAY SYSTEM LAYOUT PLAN
APPROVAL
5 01-Mar-16 07-Mar-16 26-Jul-15 30-Jul-15
Lightning SystLightning System 14 18-Jan-16 07-Mar-16 26-Jul-15 06-Aug-15
ZB4AEREHS10 ROOF 1 FLOOR LIGHTNING SYSTEM LAYOUT PLAN
SUBMITTAL
5 18-Jan-16 24-Jan-16 26-Jul-15 30-Jul-15
ZB4AEREHA10 ROOF 1 FLOOR LIGHTNING SYSTEM LAYOUT PLAN
APPROVAL
5 01-Mar-16 07-Mar-16 02-Aug-15 06-Aug-15
Light Current SLight Current Systems 20 06-Jan-16 07-Mar-16 10-Jun-15 28-Jun-15
Fire Alarm SyFire Alarm System 15 06-Jan-16 07-Mar-16 10-Jun-15 23-Jun-15
ZB4AERELFS10ROOF 1 FLOOR FIRE ALARM SYSTEM LAYOUT PLAN
SUBMITTAL
5 06-Jan-16 13-Jan-16 10-Jun-15 16-Jun-15
ZB4AERELFA10ROOF 1 FLOOR FIRE ALARM SYSTEM LAYOUT PLAN
APPROVAL
5 01-Mar-16 07-Mar-16 17-Jun-15 23-Jun-15
Security SystSecurity Systems 15 18-Jan-16 07-Mar-16 15-Jun-15 28-Jun-15
ZB4AERELSS10 ROOF 1 FLOOR SECURITY SYSTEMS LAYOUT PLAN
SUBMITTAL
5 18-Jan-16 24-Jan-16 15-Jun-15 21-Jun-15
ZB4AERELSA10ROOF 1 FLOOR SECURITY SYSTEMS LAYOUT PLAN
APPROVAL
5 01-Mar-16 07-Mar-16 22-Jun-15 28-Jun-15
SCADA SystemSCADA System 14 21-Mar-16 11-May-16 23-Aug-15 03-Sep-15
ZB4AEREDS10 ROOF 1 FLOOR SCADA SYSTEM LAYOUT PLAN SUBMITTAL 5 21-Mar-16 27-Mar-16 23-Aug-15 27-Aug-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
2015 2016 2017
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings_1 18-Feb-16 09:32
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 5 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish BL Project
Start
BL Project
Finish
ZB4AEREDA10 ROOF 1 FLOOR SCADA SYSTEM LAYOUT PLAN APPROVAL 5 05-May-16 11-May-16 30-Aug-15 03-Sep-15
Mechanical SystMechanical Systems 60 03-Jan-16 07-Mar-16 10-Jun-15 06-Aug-15
HVAC SystemHVAC System 30 03-Jan-16 07-Mar-16 08-Jul-15 06-Aug-15
ZB4AERMHS10 ROOF 1 FLOOR HVAC SYSTEM LAYOUT PLAN SUBMITTAL 15 03-Jan-16 24-Jan-16 08-Jul-15 30-Jul-15
ZB4AERMHS20 ROOF 1 FLOOR HVAC SECTIONS LAYOUT PLAN SUBMITTAL 15 18-Jan-16 08-Feb-16 08-Jul-15 30-Jul-15
ZB4AERMHA10 ROOF 1 FLOOR HVAC SYSTEM LAYOUT PLAN APPROVAL 5 01-Mar-16 07-Mar-16 02-Aug-15 06-Aug-15
ZB4AERMHA20 ROOF 1 FLOOR HVAC SECTIONS LAYOUT PLAN APPROVAL 5 01-Mar-16 07-Mar-16 02-Aug-15 06-Aug-15
Fire ProtectionFire Protection Systems 15 09-Feb-16 29-Feb-16 17-Jun-15 30-Jun-15
ZB4AERMFS10 ROOF 1 FLOOR FIRE PROTECTION SYSTEM LAYOUT PLAN
SUBMITTAL
5 09-Feb-16 15-Feb-16 17-Jun-15 23-Jun-15
ZB4AERMFA10 ROOF 1 FLOOR FIRE PROTECTION SYSTEM LAYOUT PLAN
APPROVAL
5 23-Feb-16 29-Feb-16 24-Jun-15 30-Jun-15
Plumbing SystPlumbing System 15 11-Jan-16 07-Mar-16 10-Jun-15 23-Jun-15
ZB4AERMWS10 ROOF 1 FLOOR WATER SUPPLY SYSTEM LAYOUT PLAN
SUBMITTAL
5 16-Feb-16 22-Feb-16 10-Jun-15 16-Jun-15
ZB4AERMDS10 ROOF 1 FLOOR DRAINAGE SYSTEM LAYOUT PLAN
SUBMITTAL
5 11-Jan-16 17-Jan-16 10-Jun-15 16-Jun-15
ZB4AERMWA10 ROOF 1 FLOOR WATER SUPPLY SYSTEM LAYOUT PLAN
APPROVAL
5 01-Mar-16 07-Mar-16 17-Jun-15 23-Jun-15
ZB4AERMDA10 ROOF 1 FLOOR DRAINAGE SYSTEM LAYOUT PLAN
APPROVAL
5 01-Mar-16 07-Mar-16 17-Jun-15 23-Jun-15
Composite DrawComposite Drawing 14 08-Mar-16 21-Mar-16 09-Aug-15 20-Aug-15
ZB4AERCS10 ROOF 1 FLOOR COMPOSITE LAYOUT PLAN SUBMITTAL 5 08-Mar-16 14-Mar-16 09-Aug-15 13-Aug-15
ZB4AERCA10 ROOF 1 FLOOR COMPOSITE LAYOUT PLAN APPROVAL 5 15-Mar-16 21-Mar-16 16-Aug-15 20-Aug-15
Roof 2Roof 2 90 14-Jan-16 11-May-16 17-Jun-15 10-Sep-15
ZB4AEUGBS10 Roof 2 Builder Work Submittal 5 31-Mar-16 06-Apr-16 30-Aug-15 03-Sep-15
ZB4AEUGBA10 Roof 2 Builder Work Approval 5 07-Apr-16 13-Apr-16 06-Sep-15 10-Sep-15
Electrical SystemElectrical Systems 90 14-Jan-16 11-May-16 17-Jun-15 10-Sep-15
Power SystemPower System 15 26-Jan-16 28-Feb-16 15-Jul-15 30-Jul-15
ZB4AEUEPS10 ROOF 2 FLOOR POWER SYSTEM LAYOUT PLAN SUBMITTAL 5 26-Jan-16 01-Feb-16 15-Jul-15 22-Jul-15
ZB4AEUEPA10 ROOF 2 FLOOR POWER SYSTEM LAYOUT PLAN APPROVAL 5 22-Feb-16 28-Feb-16 26-Jul-15 30-Jul-15
Lighting SystemLighting System 15 18-Jan-16 07-Mar-16 17-Jun-15 30-Jun-15
ZB4AEUELS10 ROOF 2 FLOOR LIGHTING SYSTEM LAYOUT PLAN
SUBMITTAL
5 18-Jan-16 24-Jan-16 17-Jun-15 23-Jun-15
ZB4AEUELA10 ROOF 2 FLOOR LIGHTING SYSTEM LAYOUT PLAN APPROVAL 5 01-Mar-16 07-Mar-16 24-Jun-15 30-Jun-15
Cable Tray SysCable Tray System 14 20-Jan-16 07-Mar-16 26-Jul-15 06-Aug-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
2015 2016 2017
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings_1 18-Feb-16 09:32
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 6 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish BL Project
Start
BL Project
Finish
ZB4AEUECS10 ROOF 2 FLOOR CABLE TRAY SYSTEM LAYOUT PLAN
SUBMITTAL
5 20-Jan-16 27-Jan-16 26-Jul-15 30-Jul-15
ZB4AEUECA10 ROOF 2 FLOOR CABLE TRAY SYSTEM LAYOUT PLAN
APPROVAL
5 01-Mar-16 07-Mar-16 02-Aug-15 06-Aug-15
Lightning SystLightning System 14 26-Jan-16 07-Mar-16 02-Aug-15 13-Aug-15
ZB4AEUEHS10 ROOF 2 FLOOR LIGHTNING SYSTEM LAYOUT PLAN
SUBMITTAL
5 26-Jan-16 01-Feb-16 02-Aug-15 06-Aug-15
ZB4AEUEHA10 ROOF 2 FLOOR LIGHTNING SYSTEM LAYOUT PLAN
APPROVAL
5 01-Mar-16 07-Mar-16 09-Aug-15 13-Aug-15
Light Current SLight Current Systems 20 14-Jan-16 07-Mar-16 17-Jun-15 05-Jul-15
Fire Alarm SyFire Alarm System 15 14-Jan-16 07-Mar-16 17-Jun-15 30-Jun-15
ZB4AEUELFS10ROOF 2 FLOOR FIRE ALARM SYSTEM LAYOUT PLAN
SUBMITTAL
5 14-Jan-16 20-Jan-16 17-Jun-15 23-Jun-15
ZB4AEUELFA10ROOF 2 FLOOR FIRE ALARM SYSTEM LAYOUT PLAN
APPROVAL
5 01-Mar-16 07-Mar-16 24-Jun-15 30-Jun-15
Security SystSecurity Systems 15 26-Jan-16 07-Mar-16 22-Jun-15 05-Jul-15
ZB4AEUELSS10 ROOF 2 FLOOR SECURITY SYSTEMS LAYOUT PLAN
SUBMITTAL
5 26-Jan-16 01-Feb-16 22-Jun-15 28-Jun-15
ZB4AEUELSA10ROOF 2 FLOOR SECURITY SYSTEMS LAYOUT PLAN
APPROVAL
5 01-Mar-16 07-Mar-16 29-Jun-15 05-Jul-15
SCADA SystemSCADA System 14 28-Mar-16 11-May-16 30-Aug-15 10-Sep-15
ZB4AEUEDS10 ROOF 2 FLOOR SCADA SYSTEM LAYOUT PLAN SUBMITTAL 5 28-Mar-16 03-Apr-16 30-Aug-15 03-Sep-15
ZB4AEUEDA10 ROOF 2 FLOOR SCADA SYSTEM LAYOUT PLAN APPROVAL 5 05-May-16 11-May-16 06-Sep-15 10-Sep-15
Mechanical SystMechanical Systems 75 18-Jan-16 07-Mar-16 17-Jun-15 27-Aug-15
HVAC SystemHVAC System 29 26-Jan-16 07-Mar-16 02-Aug-15 27-Aug-15
ZB4AEUMHS10 ROOF 2 FLOOR HVAC SYSTEM LAYOUT PLAN SUBMITTAL 15 26-Jan-16 15-Feb-16 02-Aug-15 20-Aug-15
ZB4AEUMHS20 ROOF 2 FLOOR HVAC SECTIONS LAYOUT PLAN SUBMITTAL 15 09-Feb-16 29-Feb-16 02-Aug-15 20-Aug-15
ZB4AEUMHA10 ROOF 2 FLOOR HVAC SYSTEM LAYOUT PLAN APPROVAL 5 01-Mar-16 07-Mar-16 23-Aug-15 27-Aug-15
ZB4AEUMHA20 ROOF 2 FLOOR HVAC SECTIONS LAYOUT PLAN APPROVAL 5 01-Mar-16 07-Mar-16 23-Aug-15 27-Aug-15
Fire ProtectionFire Protection Systems 15 16-Feb-16 29-Feb-16 24-Jun-15 07-Jul-15
ZB4AEUMFS10 ROOF 2 FLOOR FIRE PROTECTION SYSTEM LAYOUT PLAN
SUBMITTAL
5 16-Feb-16 22-Feb-16 24-Jun-15 30-Jun-15
ZB4AEUMFA10 ROOF 2 FLOOR FIRE PROTECTION SYSTEM LAYOUT PLAN
APPROVAL
5 23-Feb-16 29-Feb-16 01-Jul-15 07-Jul-15
Plumbing SystPlumbing System 15 18-Jan-16 07-Mar-16 17-Jun-15 30-Jun-15
ZB4AEUMWS10 ROOF 2 FLOOR WATER SUPPLY SYSTEM LAYOUT PLAN
SUBMITTAL
5 23-Feb-16 29-Feb-16 17-Jun-15 23-Jun-15
ZB4AEUMDS10 ROOF 2 FLOOR DRAINAGE SYSTEM LAYOUT PLAN
SUBMITTAL
5 18-Jan-16 24-Jan-16 17-Jun-15 23-Jun-15
ZB4AEUMWA10 ROOF 2 FLOOR WATER SUPPLY SYSTEM LAYOUT PLAN
APPROVAL
5 01-Mar-16 07-Mar-16 24-Jun-15 30-Jun-15
ZB4AEUMDA10 ROOF 2 FLOOR DRAINAGE SYSTEM LAYOUT PLAN
APPROVAL
5 01-Mar-16 07-Mar-16 24-Jun-15 30-Jun-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
2015 2016 2017
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings_1 18-Feb-16 09:32
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 7 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish BL Project
Start
BL Project
Finish
Composite DrawComposite Drawing 14 08-Mar-16 21-Mar-16 30-Aug-15 10-Sep-15
ZB4AEUCS10 ROOF 2 FLOOR COMPOSITE LAYOUT PLAN SUBMITTAL 5 08-Mar-16 14-Mar-16 30-Aug-15 03-Sep-15
ZB4AEUCA10 ROOF 2 FLOOR COMPOSITE LAYOUT PLAN APPROVAL 5 15-Mar-16 21-Mar-16 06-Sep-15 10-Sep-15
General Shop DGeneral Shop Drawings 151 21-Feb-16 28-Jun-16 27-May-15 21-Oct-15
Electrical SystemElectrical Systems 151 21-Feb-16 06-Jun-16 27-May-15 21-Oct-15
ZB4AETEGS10 ELECTRICAL INSTALLATION DETAILS SUBMITTAL 5 21-Feb-16 25-Feb-16 27-May-15 02-Jun-15
ZB4AETEGA10 ELECTRICAL INSTALLATION DETAILS APPROVAL 5 28-Feb-16 03-Mar-16 03-Jun-15 09-Jun-15
Power SystemPower System 29 29-Feb-16 27-Mar-16 02-Aug-15 27-Aug-15
ZB4AETEPS10 PANEL BOARD SCHEDULE SUBMITTAL 5 29-Feb-16 06-Mar-16 02-Aug-15 06-Aug-15
ZB4AETEPA10 PANEL BOARD SCHEDULE APPROVAL 5 07-Mar-16 13-Mar-16 09-Aug-15 13-Aug-15
ZB4AETEPS20 POWER S.L.D SUBMITTAL 5 14-Mar-16 20-Mar-16 16-Aug-15 20-Aug-15
ZB4AETEPA20 POWER S.L.D APPROVAL 5 21-Mar-16 27-Mar-16 23-Aug-15 27-Aug-15
Lighting SystemLighting System 114 28-Mar-16 19-May-16 01-Jul-15 21-Oct-15
ZB4AETELS10 LIGHTING FIXTURE SCHEDULE SUBMITTAL 5 28-Mar-16 03-Apr-16 01-Jul-15 07-Jul-15
ZB4AETELA10 LIGHTING FIXTURE SCHEDULE APPROVAL 5 04-Apr-16 10-Apr-16 08-Jul-15 14-Jul-15
ZB4AETELS20 CENTRAL MONITORING RISER DIAGRAM SUBMITTAL 5 27-Apr-16 05-May-16 29-Sep-15 05-Oct-15
ZB4AETELS30 KNX SYSTEM RISER DIAGRAM SUBMITTAL 5 08-May-16 12-May-16 07-Oct-15 13-Oct-15
ZB4AETELA20 CENTRAL MONITORING RISER DIAGRAM APPROVAL 5 08-May-16 12-May-16 07-Oct-15 13-Oct-15
ZB4AETELA30 KNX SYSTEM RISER DIAGRAM APPROVAL 5 15-May-16 19-May-16 15-Oct-15 21-Oct-15
Light Current SLight Current Systems 57 20-Mar-16 06-Jun-16 27-May-15 20-Jul-15
ZB4AETELGS10 LIGHT CURRENT TYPICAL INSTALLATION DETAILS
SUBMITTAL
5 03-May-16 09-May-16 27-May-15 02-Jun-15
ZB4AETELGA10 LIGHT CURRENT TYPICAL INSTALLATION DETAILS
APPROVAL
5 10-May-16 16-May-16 03-Jun-15 09-Jun-15
Fire Alarm SyFire Alarm System 15 20-Mar-16 31-Mar-16 01-Jul-15 14-Jul-15
ZB4AETELFS10 FIRE ALARM RISER DIAGRAM SUBMITTAL 5 20-Mar-16 24-Mar-16 01-Jul-15 07-Jul-15
ZB4AETELFA10FIRE ALARM RISER DIAGRAM APPROVAL 5 27-Mar-16 31-Mar-16 08-Jul-15 14-Jul-15
Security SystSecurity Systems 15 10-May-16 23-May-16 06-Jul-15 20-Jul-15
ZB4AETELSS10 IPCCTV RISER DIAGRAM SUBMITTAL (By Others) 5 10-May-16 16-May-16 06-Jul-15 12-Jul-15
ZB4AETELSA10IPCCTV RISER DIAGRAM APPROVAL (By Others) 5 17-May-16 23-May-16 13-Jul-15 20-Jul-15
CommunicatiCommunication Systems 15 24-May-16 06-Jun-16 25-Jun-15 08-Jul-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
2015 2016 2017
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings_1 18-Feb-16 09:32
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 8 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish BL Project
Start
BL Project
Finish
ZB4AETELCS10STRUCTURED CABLING RISER DIAGRAM SUBMITTAL (By
Others)
5 24-May-16 30-May-16 25-Jun-15 01-Jul-15
ZB4AETELCA10STRUCTURED CABLING RISER DIAGRAM APPROVAL (By
Others)
5 31-May-16 06-Jun-16 02-Jul-15 08-Jul-15
SCADA SystemSCADA System 15 12-May-16 01-Jun-16 13-Sep-15 28-Sep-15
ZB4AETEDS10 SCADA SYSTEM RISER DIAGRAM SUBMITTAL 5 12-May-16 18-May-16 13-Sep-15 17-Sep-15
ZB4AETEDA10 SCADA SYSTEM RISER DIAGRAM APPROVAL 5 26-May-16 01-Jun-16 20-Sep-15 28-Sep-15
Mechanical SystMechanical Systems 60 01-Mar-16 28-Jun-16 27-May-15 22-Jul-15
HVAC SystemHVAC System 15 08-May-16 19-May-16 27-May-15 09-Jun-15
ZB4AETMHS10 HVAC INSTALLATION DETAILS SUBMITTAL 5 08-May-16 12-May-16 27-May-15 02-Jun-15
ZB4AETMHA10 HVAC INSTALLATION DETAILS APPROVAL 5 15-May-16 19-May-16 03-Jun-15 09-Jun-15
Fire ProtectionFire Protection Systems 60 01-Mar-16 21-Apr-16 27-May-15 22-Jul-15
ZB4AETMFS10 FIRE PROTECTION INSTALLATION DETAILS SUBMITTAL 5 10-Apr-16 14-Apr-16 27-May-15 02-Jun-15
ZB4AETMFA10 FIRE PROTECTION INSTALLATION DETAILS APPROVAL 5 17-Apr-16 21-Apr-16 03-Jun-15 09-Jun-15
ZB4AETMFS20 FIRE PROTECTION RISER DIAGRAM SUBMITTAL 5 01-Mar-16 07-Mar-16 08-Jul-15 14-Jul-15
ZB4AETMFA20 FIRE PROTECTION RISER DIAGRAM APPROVAL 5 08-Mar-16 14-Mar-16 15-Jul-15 22-Jul-15
Plumbing SystPlumbing System 15 08-Jun-16 28-Jun-16 27-May-15 09-Jun-15
ZB4AETMWS10 WATER SUPPLY INSTALLATION DETAILS SUBMITTAL 5 15-Jun-16 21-Jun-16 27-May-15 02-Jun-15
ZB4AETMDS10 DRAINAGE SYSTEM INSTALLATION DETAILS SUBMITTAL 5 08-Jun-16 14-Jun-16 27-May-15 02-Jun-15
ZB4AETMWA10 WATER SUPPLY INSTALLATION DETAILS APPROVAL 5 22-Jun-16 28-Jun-16 03-Jun-15 09-Jun-15
ZB4AETMDA10 DRAINAGE SYSTEM INSTALLATION DETAILS APPROVAL 5 15-Jun-16 21-Jun-16 03-Jun-15 09-Jun-15
Building B4 - B (EBuilding B4 - B (Electrical Services) 144 21-Jan-16 25-Aug-16 24-Jun-15 11-Nov-15
Ground FloorGround Floor 129 21-Jan-16 06-Jun-16 24-Jun-15 28-Oct-15
ZB4BEGGBS10 Ground Floor Builder Work Submittal 5 24-May-16 30-May-16 23-Aug-15 27-Aug-15
ZB4BEGGBA10 Ground Floor Builder Work Approval 5 31-May-16 06-Jun-16 30-Aug-15 03-Sep-15
Electrical SystemElectrical Systems 82 21-Jan-16 11-May-16 24-Jun-15 10-Sep-15
Power SystemPower System 14 02-Feb-16 22-Feb-16 26-Jul-15 06-Aug-15
ZB4BEGEPS10 GROUND FLOOR POWER SYSTEM LAYOUT PLAN SUBMITTAL 5 02-Feb-16 08-Feb-16 26-Jul-15 30-Jul-15
ZB4BEGEPA10 GROUND FLOOR POWER SYSTEM LAYOUT PLAN APPROVAL 5 16-Feb-16 22-Feb-16 02-Aug-15 06-Aug-15
Lighting SystemLighting System 15 26-Jan-16 22-Feb-16 24-Jun-15 07-Jul-15
ZB4BEGELS10 GROUND FLOOR LIGHTING SYSTEM LAYOUT PLAN
SUBMITTAL
5 26-Jan-16 01-Feb-16 24-Jun-15 30-Jun-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
2015 2016 2017
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings_1 18-Feb-16 09:32
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 9 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish BL Project
Start
BL Project
Finish
ZB4BEGELA10 GROUND FLOOR LIGHTING SYSTEM LAYOUT PLAN
APPROVAL
5 16-Feb-16 22-Feb-16 01-Jul-15 07-Jul-15
Cable Tray SysCable Tray System 22 26-Jan-16 22-Feb-16 29-Jul-15 18-Aug-15
ZB4BEGECS10 GROUND FLOOR CABLE TRAY SYSTEM LAYOUT PLAN
SUBMITTAL
10 26-Jan-16 08-Feb-16 29-Jul-15 11-Aug-15
ZB4BEGECA10 GROUND FLOOR CABLE TRAY SYSTEM LAYOUT PLAN
APPROVAL
5 16-Feb-16 22-Feb-16 12-Aug-15 18-Aug-15
Earthing SysteEarthing System 14 02-Feb-16 22-Feb-16 09-Aug-15 20-Aug-15
ZB4BEGEES10 GROUND FLOOR EARTHING SYSTEM LAYOUT PLAN
SUBMITTAL
5 02-Feb-16 08-Feb-16 09-Aug-15 13-Aug-15
ZB4BEGEEA10 GROUND FLOOR EARTHING SYSTEM LAYOUT PLAN
APPROVAL
5 16-Feb-16 22-Feb-16 16-Aug-15 20-Aug-15
Light Current SLight Current Systems 60 21-Jan-16 22-Feb-16 24-Jun-15 20-Aug-15
Fire Alarm SyFire Alarm System 15 21-Jan-16 04-Feb-16 24-Jun-15 07-Jul-15
ZB4BEGELFS10 GROUND FLOOR FIRE ALARM SYSTEM LAYOUT PLAN
SUBMITTAL
5 21-Jan-16 28-Jan-16 24-Jun-15 30-Jun-15
ZB4BEGELFA10GROUND FLOOR FIRE ALARM SYSTEM LAYOUT PLAN
APPROVAL
5 31-Jan-16 04-Feb-16 01-Jul-15 07-Jul-15
Security SystSecurity Systems 55 02-Feb-16 22-Feb-16 29-Jun-15 20-Aug-15
ZB4BEGELSS10 GROUND FLOOR SECURITY SYSTEMS LAYOUT PLAN
SUBMITTAL
5 02-Feb-16 08-Feb-16 29-Jun-15 05-Jul-15
ZB4BEGELSA10GROUND FLOOR SECURITY SYSTEMS LAYOUT PLAN
APPROVAL
5 16-Feb-16 22-Feb-16 06-Jul-15 12-Jul-15
ZB4BEGELSA20Access Control System Approval and Approved Submittal (By Others) 0 22-Feb-16 20-Aug-15
CommunicatiCommunication Systems 15 09-Feb-16 22-Feb-16 06-Jul-15 20-Jul-15
ZB4BEGELCS10GROUND FLOOR COMMUNICATION SYSTEMS LAYOUT PLAN
SUBMITTAL
5 09-Feb-16 15-Feb-16 06-Jul-15 12-Jul-15
ZB4BEGELCA10GROUND FLOOR COMMUNICATION SYSTEMS LAYOUT PLAN
APPROVAL
5 16-Feb-16 22-Feb-16 13-Jul-15 20-Jul-15
SCADA SystemSCADA System 14 26-Apr-16 11-May-16 30-Aug-15 10-Sep-15
ZB4BEGEDS10 GROUND FLOOR SCADA SYSTEM LAYOUT PLAN SUBMITTAL 5 26-Apr-16 04-May-16 30-Aug-15 03-Sep-15
ZB4BEGEDA10 GROUND FLOOR SCADA SYSTEM LAYOUT PLAN APPROVAL 5 05-May-16 11-May-16 06-Sep-15 10-Sep-15
Mechanical SystMechanical Systems 129 26-Jan-16 26-May-16 24-Jun-15 28-Oct-15
HVAC SystemHVAC System 14 26-Jan-16 22-Feb-16 02-Aug-15 13-Aug-15
ZB4BEGMHS10 GROUND FLOOR HVAC SYSTEM LAYOUT PLAN SUBMITTAL 5 26-Jan-16 01-Feb-16 02-Aug-15 06-Aug-15
ZB4BEGMHA10 GROUND FLOOR HVAC SYSTEM LAYOUT PLAN APPROVAL 5 16-Feb-16 22-Feb-16 09-Aug-15 13-Aug-15
Fire ProtectionFire Protection Systems 22 08-May-16 26-May-16 07-Oct-15 28-Oct-15
ZB4BEGMFS20 FIRE PROTECTION WORK - SPECIAL SYSTEM DETAILS
SUBMITTAL
10 08-May-16 19-May-16 07-Oct-15 21-Oct-15
ZB4BEGMFA20 FIRE PROTECTION WORK - SPECIAL SYSTEM DETAILS
APPROVAL
5 22-May-16 26-May-16 22-Oct-15 28-Oct-15
Plumbing SystPlumbing System 15 26-Jan-16 22-Feb-16 24-Jun-15 07-Jul-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
2015 2016 2017
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings_1 18-Feb-16 09:32
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 10 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish BL Project
Start
BL Project
Finish
ZB4BEGMDS10 GROUND FLOOR DRAINAGE SYSTEM LAYOUT PLAN
SUBMITTAL
5 26-Jan-16 01-Feb-16 24-Jun-15 30-Jun-15
ZB4BEGMDA10 GROUND FLOOR DRAINAGE SYSTEM LAYOUT PLAN
APPROVAL
5 16-Feb-16 22-Feb-16 01-Jul-15 07-Jul-15
Composite DrawComposite Drawing 14 23-Feb-16 07-Mar-16 23-Aug-15 03-Sep-15
ZB4BEGCS10 GROUND FLOOR COMPOSITE LAYOUT PLAN SUBMITTAL 5 23-Feb-16 29-Feb-16 23-Aug-15 27-Aug-15
ZB4BEGCA10 GROUND FLOOR COMPOSITE LAYOUT PLAN APPROVAL 5 01-Mar-16 07-Mar-16 30-Aug-15 03-Sep-15
Roof 1Roof 1 82 21-Jan-16 06-Jun-16 24-Jun-15 10-Sep-15
ZB4BERGBS10 Roof 1 Builder Work Submittal 5 24-May-16 30-May-16 30-Aug-15 03-Sep-15
ZB4BERGBA10 Roof 1 Builder Work Approval 5 31-May-16 06-Jun-16 06-Sep-15 10-Sep-15
Electrical SystemElectrical Systems 65 21-Jan-16 22-Feb-16 24-Jun-15 25-Aug-15
Power SystemPower System 14 09-Feb-16 22-Feb-16 02-Aug-15 13-Aug-15
ZB4BEREPS10 ROOF 1 FLOOR POWER SYSTEM LAYOUT PLAN SUBMITTAL 5 09-Feb-16 15-Feb-16 02-Aug-15 06-Aug-15
ZB4BEREPA10 ROOF 1 FLOOR POWER SYSTEM LAYOUT PLAN APPROVAL 5 16-Feb-16 22-Feb-16 09-Aug-15 13-Aug-15
Lighting SystemLighting System 15 02-Feb-16 22-Feb-16 01-Jul-15 14-Jul-15
ZB4BERELS10 ROOF 1 FLOOR LIGHTING SYSTEM LAYOUT PLAN
SUBMITTAL
5 02-Feb-16 08-Feb-16 01-Jul-15 07-Jul-15
ZB4BERELA10 ROOF 1 FLOOR LIGHTING SYSTEM LAYOUT PLAN APPROVAL 5 16-Feb-16 22-Feb-16 08-Jul-15 14-Jul-15
Cable Tray SysCable Tray System 15 09-Feb-16 22-Feb-16 12-Aug-15 25-Aug-15
ZB4BERECS10 ROOF 1 FLOOR CABLE TRAY SYSTEM LAYOUT PLAN
SUBMITTAL
5 09-Feb-16 15-Feb-16 12-Aug-15 18-Aug-15
ZB4BERECA10 ROOF 1 FLOOR CABLE TRAY SYSTEM LAYOUT PLAN
APPROVAL
5 16-Feb-16 22-Feb-16 19-Aug-15 25-Aug-15
Light Current SLight Current Systems 15 21-Jan-16 04-Feb-16 24-Jun-15 07-Jul-15
Fire Alarm SyFire Alarm System 15 21-Jan-16 04-Feb-16 24-Jun-15 07-Jul-15
ZB4BERELFS10 ROOF 1 FLOOR FIRE ALARM SYSTEM LAYOUT PLAN
SUBMITTAL
5 21-Jan-16 28-Jan-16 24-Jun-15 30-Jun-15
ZB4BERELFA10ROOF 1 FLOOR FIRE ALARM SYSTEM LAYOUT PLAN
APPROVAL
5 31-Jan-16 04-Feb-16 01-Jul-15 07-Jul-15
Mechanical SystMechanical Systems 60 02-Feb-16 22-Feb-16 01-Jul-15 27-Aug-15
HVAC SystemHVAC System 21 02-Feb-16 22-Feb-16 09-Aug-15 27-Aug-15
ZB4BERMHS10 ROOF 1 FLOOR HVAC SYSTEM LAYOUT PLAN SUBMITTAL 10 02-Feb-16 15-Feb-16 09-Aug-15 20-Aug-15
ZB4BERMHS20 ROOF 1 FLOOR HVAC SECTIONS LAYOUT PLAN SUBMITTAL 10 02-Feb-16 15-Feb-16 09-Aug-15 20-Aug-15
ZB4BERMHA10 ROOF 1 FLOOR HVAC SYSTEM LAYOUT PLAN APPROVAL 5 16-Feb-16 22-Feb-16 23-Aug-15 27-Aug-15
ZB4BERMHA20 ROOF 1 FLOOR HVAC SECTIONS LAYOUT PLAN APPROVAL 5 16-Feb-16 22-Feb-16 23-Aug-15 27-Aug-15
Plumbing SystPlumbing System 15 02-Feb-16 22-Feb-16 01-Jul-15 14-Jul-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
2015 2016 2017
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings_1 18-Feb-16 09:32
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 11 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish BL Project
Start
BL Project
Finish
ZB4BERMDS10 ROOF 1 FLOOR DRAINAGE SYSTEM LAYOUT PLAN
SUBMITTAL
5 02-Feb-16 08-Feb-16 01-Jul-15 07-Jul-15
ZB4BERMDA10 ROOF 1 FLOOR DRAINAGE SYSTEM LAYOUT PLAN
APPROVAL
5 16-Feb-16 22-Feb-16 08-Jul-15 14-Jul-15
Composite DrawComposite Drawing 14 23-Feb-16 07-Mar-16 30-Aug-15 10-Sep-15
ZB4BERCS10 ROOF 1 FLOOR COMPOSITE LAYOUT PLAN SUBMITTAL 5 23-Feb-16 29-Feb-16 30-Aug-15 03-Sep-15
ZB4BERCA10 ROOF 1 FLOOR COMPOSITE LAYOUT PLAN APPROVAL 5 01-Mar-16 07-Mar-16 06-Sep-15 10-Sep-15
Roof 2Roof 2 82 31-Jan-16 06-Jun-16 24-Jun-15 10-Sep-15
ZB4BEUGBS10 Roof 2 Builder Work Submittal 5 24-May-16 30-May-16 30-Aug-15 03-Sep-15
ZB4BEUGBA10 Roof 2 Builder Work Approval 5 31-May-16 06-Jun-16 06-Sep-15 10-Sep-15
Electrical SystemElectrical Systems 67 31-Jan-16 22-Feb-16 24-Jun-15 27-Aug-15
Power SystemPower System 14 09-Feb-16 22-Feb-16 02-Aug-15 13-Aug-15
ZB4BEUEPS10 ROOF 2 FLOOR POWER SYSTEM LAYOUT PLAN SUBMITTAL 5 09-Feb-16 15-Feb-16 02-Aug-15 06-Aug-15
ZB4BEUEPA10 ROOF 2 FLOOR POWER SYSTEM LAYOUT PLAN APPROVAL 5 16-Feb-16 22-Feb-16 09-Aug-15 13-Aug-15
Lighting SystemLighting System 15 09-Feb-16 22-Feb-16 08-Jul-15 22-Jul-15
ZB4BEUELS10 ROOF 2 FLOOR LIGHTING SYSTEM LAYOUT PLAN
SUBMITTAL
5 09-Feb-16 15-Feb-16 08-Jul-15 14-Jul-15
ZB4BEUELA10 ROOF 2 FLOOR LIGHTING SYSTEM LAYOUT PLAN APPROVAL 5 16-Feb-16 22-Feb-16 15-Jul-15 22-Jul-15
Cable Tray SysCable Tray System 15 09-Feb-16 22-Feb-16 12-Aug-15 25-Aug-15
ZB4BEUECS10 ROOF 2 FLOOR CABLE TRAY SYSTEM LAYOUT PLAN
SUBMITTAL
5 09-Feb-16 15-Feb-16 12-Aug-15 18-Aug-15
ZB4BEUECA10 ROOF 2 FLOOR CABLE TRAY SYSTEM LAYOUT PLAN
APPROVAL
5 16-Feb-16 22-Feb-16 19-Aug-15 25-Aug-15
Lightning SystLightning System 14 09-Feb-16 22-Feb-16 16-Aug-15 27-Aug-15
ZB4BEUEHS10 ROOF 2 FLOOR LIGHTNING SYSTEM LAYOUT PLAN
SUBMITTAL
5 09-Feb-16 15-Feb-16 16-Aug-15 20-Aug-15
ZB4BEUEHA10 ROOF 2 FLOOR LIGHTNING SYSTEM LAYOUT PLAN
APPROVAL
5 16-Feb-16 22-Feb-16 23-Aug-15 27-Aug-15
Light Current SLight Current Systems 7 31-Jan-16 04-Feb-16 24-Jun-15 30-Jun-15
Fire Alarm SyFire Alarm System 7 31-Jan-16 04-Feb-16 24-Jun-15 30-Jun-15
ZB4BEUELFS10 ROOF 2 FLOOR FIRE ALARM SYSTEM LAYOUT PLAN
SUBMITTAL
5 31-Jan-16 04-Feb-16 24-Jun-15 30-Jun-15
ZB4BEUELFA10ROOF 2 FLOOR FIRE ALARM SYSTEM LAYOUT PLAN
APPROVAL
5 31-Jan-16 04-Feb-16 24-Jun-15 30-Jun-15
Mechanical SystMechanical Systems 52 02-Feb-16 22-Feb-16 08-Jul-15 27-Aug-15
HVAC SystemHVAC System 21 02-Feb-16 22-Feb-16 09-Aug-15 27-Aug-15
ZB4BEUMHS10 ROOF 2 FLOOR HVAC SYSTEM LAYOUT PLAN SUBMITTAL 10 02-Feb-16 15-Feb-16 09-Aug-15 20-Aug-15
ZB4BEUMHS20 ROOF 2 FLOOR HVAC SECTIONS LAYOUT PLAN SUBMITTAL 10 02-Feb-16 15-Feb-16 09-Aug-15 20-Aug-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
2015 2016 2017
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings_1 18-Feb-16 09:32
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 12 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish BL Project
Start
BL Project
Finish
ZB4BEUMHA10 ROOF 2 FLOOR HVAC SYSTEM LAYOUT PLAN APPROVAL 5 16-Feb-16 22-Feb-16 23-Aug-15 27-Aug-15
ZB4BEUMHA20 ROOF 2 FLOOR HVAC SECTIONS LAYOUT PLAN APPROVAL 5 16-Feb-16 22-Feb-16 23-Aug-15 27-Aug-15
Plumbing SystPlumbing System 15 09-Feb-16 22-Feb-16 08-Jul-15 22-Jul-15
ZB4BEUMDS10 ROOF 2 FLOOR DRAINAGE SYSTEM LAYOUT PLAN
SUBMITTAL
5 09-Feb-16 15-Feb-16 08-Jul-15 14-Jul-15
ZB4BEUMDA10 ROOF 2 FLOOR DRAINAGE SYSTEM LAYOUT PLAN
APPROVAL
5 16-Feb-16 22-Feb-16 15-Jul-15 22-Jul-15
Composite DrawComposite Drawing 14 23-Feb-16 07-Mar-16 30-Aug-15 10-Sep-15
ZB4BEUCS10 ROOF 2 FLOOR COMPOSITE LAYOUT PLAN SUBMITTAL 5 23-Feb-16 29-Feb-16 30-Aug-15 03-Sep-15
ZB4BEUCA10 ROOF 2 FLOOR COMPOSITE LAYOUT PLAN APPROVAL 5 01-Mar-16 07-Mar-16 06-Sep-15 10-Sep-15
General Shop DGeneral Shop Drawings 144 07-Feb-16 25-Aug-16 24-Jun-15 11-Nov-15
Electrical SystemElectrical Systems 144 07-Feb-16 25-Aug-16 24-Jun-15 11-Nov-15
ZB4BETEGS10 ELECTRICAL INSTALLATION DETAILS SUBMITTAL 5 10-Mar-16 16-Mar-16 26-Jul-15 30-Jul-15
ZB4BETEGA10 ELECTRICAL INSTALLATION DETAILS APPROVAL 5 17-Mar-16 23-Mar-16 02-Aug-15 06-Aug-15
Power SystemPower System 60 08-Mar-16 05-May-16 13-Sep-15 11-Nov-15
ZB4BETEPS10 PANEL BOARD SCHEDULE SUBMITTAL 5 08-Mar-16 14-Mar-16 13-Sep-15 17-Sep-15
ZB4BETEPA10 PANEL BOARD SCHEDULE APPROVAL 5 15-Mar-16 21-Mar-16 20-Sep-15 28-Sep-15
ZB4BETEPS20 POWER S.L.D SUBMITTAL 5 22-Mar-16 28-Mar-16 29-Sep-15 05-Oct-15
ZB4BETEPA20 POWER S.L.D APPROVAL 5 29-Mar-16 04-Apr-16 07-Oct-15 13-Oct-15
ZB4BETEPS30 BUILDING POWER S.L.D SUBMITTAL 5 05-Apr-16 11-Apr-16 15-Oct-15 21-Oct-15
ZB4BETEPA30 BUILDING POWER S.L.D APPROVAL 5 12-Apr-16 18-Apr-16 22-Oct-15 28-Oct-15
ZB4BETEPS40 CAMPUS POWER S.L.D SUBMITTAL 5 19-Apr-16 26-Apr-16 29-Oct-15 04-Nov-15
ZB4BETEPA40 CAMPUS POWER S.L.D APPROVAL 5 27-Apr-16 05-May-16 05-Nov-15 11-Nov-15
Lighting SystemLighting System 21 23-Feb-16 10-Apr-16 26-Jul-15 13-Aug-15
ZB4BETELS10 LIGHTING FIXTURE SCHEDULE SUBMITTAL 5 23-Feb-16 29-Feb-16 26-Jul-15 30-Jul-15
ZB4BETELA10 LIGHTING FIXTURE SCHEDULE APPROVAL 5 04-Apr-16 10-Apr-16 02-Aug-15 06-Aug-15
ZB4BETELS20 KNX SYSTEM RISER DIAGRAM SUBMITTAL 5 08-Mar-16 14-Mar-16 02-Aug-15 06-Aug-15
ZB4BETELS30 CENTRAL MONITORING RISER DIAGRAM SUBMITTAL 5 01-Mar-16 07-Mar-16 02-Aug-15 06-Aug-15
ZB4BETELA20 KNX SYSTEM RISER DIAGRAM APPROVAL 5 15-Mar-16 21-Mar-16 09-Aug-15 13-Aug-15
ZB4BETELA30 CENTRAL MONITORING RISER DIAGRAM APPROVAL 5 08-Mar-16 14-Mar-16 09-Aug-15 13-Aug-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
2015 2016 2017
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings_1 18-Feb-16 09:32
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 13 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish BL Project
Start
BL Project
Finish
Light Current SLight Current Systems 42 07-Feb-16 25-Aug-16 24-Jun-15 04-Aug-15
ZB4BETELGS10 LIGHT CURRENT TYPICAL INSTALLATION DETAILS
SUBMITTAL
5 24-Apr-16 03-May-16 24-Jun-15 30-Jun-15
ZB4BETELGA10 LIGHT CURRENT TYPICAL INSTALLATION DETAILS
APPROVAL
5 04-May-16 10-May-16 01-Jul-15 07-Jul-15
Fire Alarm SyFire Alarm System 15 07-Feb-16 18-Feb-16 08-Jul-15 22-Jul-15
ZB4BETELFS10 FIRE ALARM RISER DIAGRAM SUBMITTAL 5 07-Feb-16 11-Feb-16 08-Jul-15 14-Jul-15
ZB4BETELFA10FIRE ALARM RISER DIAGRAM APPROVAL 5 14-Feb-16 18-Feb-16 15-Jul-15 22-Jul-15
Security SystSecurity Systems 15 14-Aug-16 25-Aug-16 13-Jul-15 28-Jul-15
ZB4BETELSS10 IPCCTV RISER DIAGRAM SUBMITTAL (By Others) 5 14-Aug-16 18-Aug-16 13-Jul-15 20-Jul-15
ZB4BETELSA10IPCCTV RISER DIAGRAM APPROVAL (By Others) 5 21-Aug-16 25-Aug-16 21-Jul-15 28-Jul-15
CommunicatiCommunication Systems 15 04-May-16 17-May-16 21-Jul-15 04-Aug-15
ZB4BETELCS10STRUCTURED CABLING RISER DIAGRAM SUBMITTAL (By
Others)
5 04-May-16 10-May-16 21-Jul-15 28-Jul-15
ZB4BETELCA10STRUCTURED CABLING RISER DIAGRAM APPROVAL (By
Others)
5 11-May-16 17-May-16 29-Jul-15 04-Aug-15
SCADA SystemSCADA System 15 12-May-16 01-Jun-16 13-Sep-15 28-Sep-15
ZB4BETEDS10 SCADA SYSTEM RISER DIAGRAM SUBMITTAL 5 12-May-16 18-May-16 13-Sep-15 17-Sep-15
ZB4BETEDA10 SCADA SYSTEM RISER DIAGRAM APPROVAL 5 26-May-16 01-Jun-16 20-Sep-15 28-Sep-15
Mechanical SystMechanical Systems 75 18-May-16 25-Aug-16 24-Jun-15 03-Sep-15
HVAC SystemHVAC System 14 18-May-16 31-May-16 23-Aug-15 03-Sep-15
ZB4BETMHS10 HVAC INSTALLATION DETAILS SUBMITTAL 5 18-May-16 24-May-16 23-Aug-15 27-Aug-15
ZB4BETMHA10 HVAC INSTALLATION DETAILS APPROVAL 5 25-May-16 31-May-16 30-Aug-15 03-Sep-15
Fire ProtectionFire Protection Systems 15 20-Jul-16 02-Aug-16 01-Jul-15 14-Jul-15
ZB4BETMFS10 FIRE PROTECTION INSTALLATION DETAILS SUBMITTAL 5 20-Jul-16 26-Jul-16 01-Jul-15 07-Jul-15
ZB4BETMFA10 FIRE PROTECTION INSTALLATION DETAILS APPROVAL 5 27-Jul-16 02-Aug-16 08-Jul-15 14-Jul-15
Plumbing SystPlumbing System 15 14-Aug-16 25-Aug-16 24-Jun-15 07-Jul-15
ZB4BETMPDS10 DRAINAGE SYSTEM INSTALLATION DETAILS SUBMITTAL 5 14-Aug-16 18-Aug-16 24-Jun-15 30-Jun-15
ZB4BETMPDA10 DRAINAGE SYSTEM INSTALLATION DETAILS APPROVAL 5 21-Aug-16 25-Aug-16 01-Jul-15 07-Jul-15
Building B4 - D (FBuilding B4 - D (Fuel Tank) 106 21-Jan-16 25-Aug-16 24-Jun-15 05-Oct-15
Ground FloorGround Floor 106 21-Jan-16 27-Jul-16 24-Jun-15 05-Oct-15
ZB4DEGGBS30 Ground Floor Builder Work Submittal 5 14-Jul-16 20-Jul-16 23-Aug-15 27-Aug-15
ZB4DEGGBA30 Ground Floor Builder Work Approval 5 21-Jul-16 27-Jul-16 30-Aug-15 03-Sep-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
2015 2016 2017
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings_1 18-Feb-16 09:32
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 14 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish BL Project
Start
BL Project
Finish
Electrical SystemElectrical Systems 60 21-Jan-16 20-Mar-16 24-Jun-15 20-Aug-15
Power SystemPower System 14 07-Mar-16 20-Mar-16 26-Jul-15 06-Aug-15
ZB4DEGEPS30 GROUND & ROOF 1 FLOOR POWER SYSTEM LAYOUTS PLAN
SUBMITTAL
5 07-Mar-16 13-Mar-16 26-Jul-15 30-Jul-15
ZB4DEGEPA30 GROUND & ROOF 1 FLOOR POWER SYSTEM LAYOUTS PLAN
APPROVAL
5 14-Mar-16 20-Mar-16 02-Aug-15 06-Aug-15
Lighting SystemLighting System 15 16-Feb-16 29-Feb-16 24-Jun-15 07-Jul-15
ZB4DEGELS30 GROUND FLOOR LIGHTING SYSTEM LAYOUT PLAN
SUBMITTAL
5 16-Feb-16 22-Feb-16 24-Jun-15 30-Jun-15
ZB4DEGELA30 GROUND FLOOR LIGHTING SYSTEM LAYOUT PLAN
APPROVAL
5 23-Feb-16 29-Feb-16 01-Jul-15 07-Jul-15
Cable Tray SysCable Tray System 22 29-Feb-16 20-Mar-16 29-Jul-15 18-Aug-15
ZB4DEGECS30 GROUND FLOOR CABLE TRAY SYSTEM LAYOUT PLAN
SUBMITTAL
10 29-Feb-16 13-Mar-16 29-Jul-15 11-Aug-15
ZB4DEGECA30 GROUND FLOOR CABLE TRAY SYSTEM LAYOUT PLAN
APPROVAL
5 14-Mar-16 20-Mar-16 12-Aug-15 18-Aug-15
Earthing SysteEarthing System 14 07-Mar-16 20-Mar-16 09-Aug-15 20-Aug-15
ZB4DEGEES30 GROUND FLOOR EARTHING SYSTEM LAYOUT PLAN
SUBMITTAL
5 07-Mar-16 13-Mar-16 09-Aug-15 13-Aug-15
ZB4DEGEEA30 GROUND FLOOR EARTHING SYSTEM LAYOUT PLAN
APPROVAL
5 14-Mar-16 20-Mar-16 16-Aug-15 20-Aug-15
Light Current SLight Current Systems 60 21-Jan-16 20-Mar-16 24-Jun-15 20-Aug-15
Fire Alarm SyFire Alarm System 15 21-Jan-16 04-Feb-16 24-Jun-15 07-Jul-15
ZB4DEGELFS30GROUND FLOOR FIRE ALARM SYSTEM LAYOUT PLAN
SUBMITTAL
5 21-Jan-16 28-Jan-16 24-Jun-15 30-Jun-15
ZB4DEGELFA30GROUND FLOOR FIRE ALARM SYSTEM LAYOUT PLAN
APPROVAL
5 31-Jan-16 04-Feb-16 01-Jul-15 07-Jul-15
Security SystSecurity Systems 0 20-Mar-16 20-Mar-16 20-Aug-15 20-Aug-15
ZB4DEGELSA80Access Control System Approval and Approved Submittal (By Others) 0 20-Mar-16 20-Aug-15
Mechanical SystMechanical Systems 106 07-Mar-16 31-May-16 24-Jun-15 05-Oct-15
HVAC SystemHVAC System 14 07-Mar-16 20-Mar-16 02-Aug-15 13-Aug-15
ZB4DEGMHS30 GROUND FLOOR HVAC SYSTEM LAYOUT PLAN SUBMITTAL 5 07-Mar-16 13-Mar-16 02-Aug-15 06-Aug-15
ZB4DEGMHA30 GROUND FLOOR HVAC SYSTEM LAYOUT PLAN APPROVAL 5 14-Mar-16 20-Mar-16 09-Aug-15 13-Aug-15
Fire ProtectionFire Protection Systems 22 11-May-16 31-May-16 13-Sep-15 05-Oct-15
ZB4DEGMFS40 FIRE PROTECTION WORK - SPECIAL SYSTEM DETAILS
SUBMITTAL
10 11-May-16 24-May-16 13-Sep-15 28-Sep-15
ZB4DEGMFA40 FIRE PROTECTION WORK - SPECIAL SYSTEM DETAILS
APPROVAL
5 25-May-16 31-May-16 29-Sep-15 05-Oct-15
Plumbing SystPlumbing System 15 07-Mar-16 20-Mar-16 24-Jun-15 07-Jul-15
ZB4DEGMDS30 GROUND FLOOR DRAINAGE SYSTEM LAYOUT PLAN
SUBMITTAL
5 07-Mar-16 13-Mar-16 24-Jun-15 30-Jun-15
ZB4DEGMDA30 GROUND FLOOR DRAINAGE SYSTEM LAYOUT PLAN
APPROVAL
5 14-Mar-16 20-Mar-16 01-Jul-15 07-Jul-15
Composite DrawComposite Drawing 14 21-Mar-16 03-Apr-16 23-Aug-15 03-Sep-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
2015 2016 2017
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings_1 18-Feb-16 09:32
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 15 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish BL Project
Start
BL Project
Finish
ZB4DEGCS30 GROUND FLOOR COMPOSITE LAYOUT PLAN SUBMITTAL 5 21-Mar-16 27-Mar-16 23-Aug-15 27-Aug-15
ZB4DEGCA30 GROUND FLOOR COMPOSITE LAYOUT PLAN APPROVAL 5 28-Mar-16 03-Apr-16 30-Aug-15 03-Sep-15
Roof 1Roof 1 75 31-Jan-16 25-Aug-16 24-Jun-15 03-Sep-15
Electrical SystemElectrical Systems 75 31-Jan-16 18-Aug-16 24-Jun-15 03-Sep-15
Light Current SLight Current Systems 20 31-Jan-16 20-Mar-16 24-Jun-15 12-Jul-15
Fire Alarm SyFire Alarm System 7 31-Jan-16 04-Feb-16 24-Jun-15 30-Jun-15
ZB4DEUELFS20ROOF 1 FLOOR FIRE ALARM SYSTEM LAYOUT PLAN
SUBMITTAL
5 31-Jan-16 04-Feb-16 24-Jun-15 30-Jun-15
ZB4DEUELFA20ROOF 1 FLOOR FIRE ALARM SYSTEM LAYOUT PLAN
APPROVAL
5 31-Jan-16 04-Feb-16 24-Jun-15 30-Jun-15
Security SystSecurity Systems 15 07-Mar-16 20-Mar-16 29-Jun-15 12-Jul-15
ZB4DEGELSS30 ROOF 1 FLOOR SECURITY SYSTEMS LAYOUT PLAN
SUBMITTAL
5 07-Mar-16 13-Mar-16 29-Jun-15 05-Jul-15
ZB4DEGELSA50ROOF 1 FLOOR SECURITY SYSTEMS LAYOUT PLAN
APPROVAL
5 14-Mar-16 20-Mar-16 06-Jul-15 12-Jul-15
Lightning SystLightning System 14 07-Aug-16 18-Aug-16 23-Aug-15 03-Sep-15
ZB4DEUEHS20 ROOF 1 FLOOR LIGHTNING SYSTEM LAYOUT PLAN
SUBMITTAL
5 07-Aug-16 11-Aug-16 23-Aug-15 27-Aug-15
ZB4DEUEHA20 ROOF 1 FLOOR LIGHTNING SYSTEM LAYOUT PLAN
APPROVAL
5 14-Aug-16 18-Aug-16 30-Aug-15 03-Sep-15
Mechanical SystMechanical Systems 15 14-Aug-16 25-Aug-16 01-Jul-15 14-Jul-15
Plumbing SystPlumbing System 15 14-Aug-16 25-Aug-16 01-Jul-15 14-Jul-15
ZB4DERMDS30 ROOF 1 FLOOR DRAINAGE SYSTEM LAYOUT PLAN
SUBMITTAL
5 14-Aug-16 18-Aug-16 01-Jul-15 07-Jul-15
ZB4DERMDA30 ROOF 1 FLOOR DRAINAGE SYSTEM LAYOUT PLAN
APPROVAL
5 21-Aug-16 25-Aug-16 08-Jul-15 14-Jul-15
General Shop DGeneral Shop Drawings 106 07-Feb-16 03-Jul-16 24-Jun-15 05-Oct-15
Electrical SystemElectrical Systems 106 07-Feb-16 03-Jul-16 24-Jun-15 05-Oct-15
ZB4DETEGS30 ELECTRICAL INSTALLATION DETAILS SUBMITTAL 5 19-Apr-16 26-Apr-16 26-Jul-15 30-Jul-15
ZB4DETEGA30 ELECTRICAL INSTALLATION DETAILS APPROVAL 5 27-Apr-16 05-May-16 02-Aug-15 06-Aug-15
Power SystemPower System 30 04-Apr-16 04-May-16 06-Sep-15 05-Oct-15
ZB4DETEPS60 POWER S.L.D SUBMITTAL 15 04-Apr-16 24-Apr-16 06-Sep-15 28-Sep-15
ZB4DETEPA60 POWER S.L.D APPROVAL 5 26-Apr-16 04-May-16 29-Sep-15 05-Oct-15
Lighting SystemLighting System 22 01-Mar-16 10-Apr-16 08-Jul-15 30-Jul-15
ZB4DETELS60 LIGHTING FIXTURE SCHEDULE SUBMITTAL 5 01-Mar-16 07-Mar-16 08-Jul-15 14-Jul-15
ZB4DETELA60 LIGHTING FIXTURE SCHEDULE APPROVAL 5 04-Apr-16 10-Apr-16 15-Jul-15 22-Jul-15
ZB4DETELS70 KNX SYSTEM RISER DIAGRAM SUBMITTAL 5 08-Mar-16 14-Mar-16 15-Jul-15 22-Jul-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
2015 2016 2017
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings_1 18-Feb-16 09:32
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 16 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish BL Project
Start
BL Project
Finish
ZB4DETELA70 KNX SYSTEM RISER DIAGRAM APPROVAL 5 15-Mar-16 21-Mar-16 26-Jul-15 30-Jul-15
Light Current SLight Current Systems 35 07-Feb-16 03-Jul-16 24-Jun-15 28-Jul-15
ZB4DETELGS30 LIGHT CURRENT TYPICAL INSTALLATION DETAILS
SUBMITTAL
5 13-Jun-16 19-Jun-16 24-Jun-15 30-Jun-15
ZB4DETELGA30 LIGHT CURRENT TYPICAL INSTALLATION DETAILS
APPROVAL
5 20-Jun-16 26-Jun-16 01-Jul-15 07-Jul-15
Fire Alarm SyFire Alarm System 15 07-Feb-16 18-Feb-16 08-Jul-15 22-Jul-15
ZB4DETELFS30 FIRE ALARM RISER DIAGRAM SUBMITTAL 5 07-Feb-16 11-Feb-16 08-Jul-15 14-Jul-15
ZB4DETELFA30FIRE ALARM RISER DIAGRAM APPROVAL 5 14-Feb-16 18-Feb-16 15-Jul-15 22-Jul-15
Security SystSecurity Systems 15 20-Jun-16 03-Jul-16 13-Jul-15 28-Jul-15
ZB4DETELSS30 IPCCTV RISER DIAGRAM SUBMITTAL (By Others) 5 20-Jun-16 26-Jun-16 13-Jul-15 20-Jul-15
ZB4DETELSA30IPCCTV RISER DIAGRAM APPROVAL (By Others) 5 27-Jun-16 03-Jul-16 21-Jul-15 28-Jul-15
Building B4 - E (EBuilding B4 - E (EDC Building) 106 21-Jan-16 28-Aug-16 24-Jun-15 05-Oct-15
Ground FloorGround Floor 90 21-Jan-16 28-Aug-16 24-Jun-15 17-Sep-15
ZB4EEGGBS20 Ground Floor Builder Work Submittal 5 15-Aug-16 21-Aug-16 23-Aug-15 27-Aug-15
ZB4EEGGBA20 Ground Floor Builder Work Approval 5 22-Aug-16 28-Aug-16 30-Aug-15 03-Sep-15
Electrical SystemElectrical Systems 82 21-Jan-16 10-Apr-16 24-Jun-15 10-Sep-15
Power SystemPower System 14 08-Mar-16 21-Mar-16 26-Jul-15 06-Aug-15
ZB4EEGEPS20 GROUND FLOOR POWER SYSTEM LAYOUT PLAN SUBMITTAL 5 08-Mar-16 14-Mar-16 26-Jul-15 30-Jul-15
ZB4EEGEPA20 GROUND FLOOR POWER SYSTEM LAYOUT PLAN APPROVAL 5 15-Mar-16 21-Mar-16 02-Aug-15 06-Aug-15
Lighting SystemLighting System 15 02-Feb-16 15-Feb-16 24-Jun-15 07-Jul-15
ZB4EEGELS20 GROUND FLOOR LIGHTING SYSTEM LAYOUT PLAN
SUBMITTAL
5 02-Feb-16 08-Feb-16 24-Jun-15 30-Jun-15
ZB4EEGELA20 GROUND FLOOR LIGHTING SYSTEM LAYOUT PLAN
APPROVAL
5 09-Feb-16 15-Feb-16 01-Jul-15 07-Jul-15
Cable Tray SysCable Tray System 22 01-Mar-16 21-Mar-16 29-Jul-15 18-Aug-15
ZB4EEGECS20 GROUND FLOOR CABLE TRAY SYSTEM LAYOUT PLAN
SUBMITTAL
10 01-Mar-16 14-Mar-16 29-Jul-15 11-Aug-15
ZB4EEGECA20 GROUND FLOOR CABLE TRAY SYSTEM LAYOUT PLAN
APPROVAL
5 15-Mar-16 21-Mar-16 12-Aug-15 18-Aug-15
Earthing SysteEarthing System 14 08-Mar-16 21-Mar-16 09-Aug-15 20-Aug-15
ZB4EEGEES20 GROUND FLOOR EARTHING SYSTEM LAYOUT PLAN
SUBMITTAL
5 08-Mar-16 14-Mar-16 09-Aug-15 13-Aug-15
ZB4EEGEEA20 GROUND FLOOR EARTHING SYSTEM LAYOUT PLAN
APPROVAL
5 15-Mar-16 21-Mar-16 16-Aug-15 20-Aug-15
Light Current SLight Current Systems 60 21-Jan-16 21-Mar-16 24-Jun-15 20-Aug-15
Fire Alarm SyFire Alarm System 15 21-Jan-16 04-Feb-16 24-Jun-15 07-Jul-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
2015 2016 2017
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings_1 18-Feb-16 09:32
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 17 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish BL Project
Start
BL Project
Finish
ZB4EEGELFS20 GROUND FLOOR FIRE ALARM SYSTEM LAYOUT PLAN
SUBMITTAL
5 21-Jan-16 28-Jan-16 24-Jun-15 30-Jun-15
ZB4EEGELFA20GROUND FLOOR FIRE ALARM SYSTEM LAYOUT PLAN
APPROVAL
5 31-Jan-16 04-Feb-16 01-Jul-15 07-Jul-15
Security SystSecurity Systems 55 01-Mar-16 21-Mar-16 29-Jun-15 20-Aug-15
ZB4EEGELSS20 GROUND FLOOR SECURITY SYSTEMS LAYOUT PLAN
SUBMITTAL
5 01-Mar-16 07-Mar-16 29-Jun-15 05-Jul-15
ZB4EEGELSA30GROUND FLOOR SECURITY SYSTEMS LAYOUT PLAN
APPROVAL
5 15-Mar-16 21-Mar-16 06-Jul-15 12-Jul-15
ZB4EEGELSA40Access Control System Approval and Approved Submittal (By Others) 0 21-Mar-16 20-Aug-15
CommunicatiCommunication Systems 15 08-Mar-16 21-Mar-16 06-Jul-15 20-Jul-15
ZB4EEGELCS20GROUND FLOOR COMMUNICATION SYSTEMS LAYOUT PLAN
SUBMITTAL
5 08-Mar-16 14-Mar-16 06-Jul-15 12-Jul-15
ZB4EEGELCA20GROUND FLOOR COMMUNICATION SYSTEMS LAYOUT PLAN
APPROVAL
5 15-Mar-16 21-Mar-16 13-Jul-15 20-Jul-15
SCADA SystemSCADA System 14 28-Mar-16 10-Apr-16 30-Aug-15 10-Sep-15
ZB4EEGEDS20 GROUND FLOOR SCADA SYSTEM LAYOUT PLAN SUBMITTAL 5 28-Mar-16 03-Apr-16 30-Aug-15 03-Sep-15
ZB4EEGEDA20 GROUND FLOOR SCADA SYSTEM LAYOUT PLAN APPROVAL 5 04-Apr-16 10-Apr-16 06-Sep-15 10-Sep-15
Mechanical SystMechanical Systems 90 08-Mar-16 19-May-16 24-Jun-15 17-Sep-15
HVAC SystemHVAC System 14 08-Mar-16 21-Mar-16 02-Aug-15 13-Aug-15
ZB4EEGMHS20 GROUND FLOOR HVAC SYSTEM LAYOUT PLAN SUBMITTAL 5 08-Mar-16 14-Mar-16 02-Aug-15 06-Aug-15
ZB4EEGMHA20 GROUND FLOOR HVAC SYSTEM LAYOUT PLAN APPROVAL 5 15-Mar-16 21-Mar-16 09-Aug-15 13-Aug-15
Fire ProtectionFire Protection Systems 21 27-Apr-16 19-May-16 30-Aug-15 17-Sep-15
ZB4EEGMFS30 FIRE PROTECTION WORK - SPECIAL SYSTEM DETAILS
SUBMITTAL
10 27-Apr-16 12-May-16 30-Aug-15 10-Sep-15
ZB4EEGMFA30 FIRE PROTECTION WORK - SPECIAL SYSTEM DETAILS
APPROVAL
5 15-May-16 19-May-16 13-Sep-15 17-Sep-15
Plumbing SystPlumbing System 15 08-Mar-16 21-Mar-16 24-Jun-15 07-Jul-15
ZB4EEGMDS20 GROUND FLOOR DRAINAGE SYSTEM LAYOUT PLAN
SUBMITTAL
5 08-Mar-16 14-Mar-16 24-Jun-15 30-Jun-15
ZB4EEGMDA20 GROUND FLOOR DRAINAGE SYSTEM LAYOUT PLAN
APPROVAL
5 15-Mar-16 21-Mar-16 01-Jul-15 07-Jul-15
Composite DrawComposite Drawing 14 22-Mar-16 04-Apr-16 23-Aug-15 03-Sep-15
ZB4EEGCS20 GROUND FLOOR COMPOSITE LAYOUT PLAN SUBMITTAL 5 22-Mar-16 28-Mar-16 23-Aug-15 27-Aug-15
ZB4EEGCA20 GROUND FLOOR COMPOSITE LAYOUT PLAN APPROVAL 5 29-Mar-16 04-Apr-16 30-Aug-15 03-Sep-15
Roof 1Roof 1 15 14-Aug-16 25-Aug-16 01-Jul-15 14-Jul-15
Mechanical SystMechanical Systems 15 14-Aug-16 25-Aug-16 01-Jul-15 14-Jul-15
Plumbing SystPlumbing System 15 14-Aug-16 25-Aug-16 01-Jul-15 14-Jul-15
ZB4EERMDS20 ROOF 1 FLOOR DRAINAGE SYSTEM LAYOUT PLAN
SUBMITTAL
5 14-Aug-16 18-Aug-16 01-Jul-15 07-Jul-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
2015 2016 2017
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings_1 18-Feb-16 09:32
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 18 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish BL Project
Start
BL Project
Finish
ZB4EERMDA20 ROOF 1 FLOOR DRAINAGE SYSTEM LAYOUT PLAN
APPROVAL
5 21-Aug-16 25-Aug-16 08-Jul-15 14-Jul-15
General Shop DGeneral Shop Drawings 106 07-Feb-16 04-Jul-16 24-Jun-15 05-Oct-15
Electrical SystemElectrical Systems 106 07-Feb-16 04-Jul-16 24-Jun-15 05-Oct-15
ZB4EETEGS20 ELECTRICAL INSTALLATION DETAILS SUBMITTAL 5 12-Apr-16 18-Apr-16 26-Jul-15 30-Jul-15
ZB4EETEGA20 ELECTRICAL INSTALLATION DETAILS APPROVAL 5 19-Apr-16 26-Apr-16 02-Aug-15 06-Aug-15
Power SystemPower System 30 05-Apr-16 05-May-16 06-Sep-15 05-Oct-15
ZB4EETEPS50 POWER S.L.D SUBMITTAL 15 05-Apr-16 26-Apr-16 06-Sep-15 28-Sep-15
ZB4EETEPA50 POWER S.L.D APPROVAL 5 27-Apr-16 05-May-16 29-Sep-15 05-Oct-15
Lighting SystemLighting System 22 01-Mar-16 10-Apr-16 08-Jul-15 30-Jul-15
ZB4EETELS40 LIGHTING FIXTURE SCHEDULE SUBMITTAL 5 01-Mar-16 07-Mar-16 08-Jul-15 14-Jul-15
ZB4EETELA40 LIGHTING FIXTURE SCHEDULE APPROVAL 5 04-Apr-16 10-Apr-16 15-Jul-15 22-Jul-15
ZB4EETELS50 KNX SYSTEM RISER DIAGRAM SUBMITTAL 5 08-Mar-16 14-Mar-16 15-Jul-15 22-Jul-15
ZB4EETELA50 KNX SYSTEM RISER DIAGRAM APPROVAL 5 15-Mar-16 21-Mar-16 26-Jul-15 30-Jul-15
Light Current SLight Current Systems 35 07-Feb-16 04-Jul-16 24-Jun-15 28-Jul-15
ZB4EETELGS20 LIGHT CURRENT TYPICAL INSTALLATION DETAILS
SUBMITTAL
5 14-Jun-16 20-Jun-16 24-Jun-15 30-Jun-15
ZB4EETELGA20 LIGHT CURRENT TYPICAL INSTALLATION DETAILS
APPROVAL
5 21-Jun-16 27-Jun-16 01-Jul-15 07-Jul-15
Fire Alarm SyFire Alarm System 15 07-Feb-16 18-Feb-16 08-Jul-15 22-Jul-15
ZB4EETELFS20 FIRE ALARM RISER DIAGRAM SUBMITTAL 5 07-Feb-16 11-Feb-16 08-Jul-15 14-Jul-15
ZB4EETELFA20FIRE ALARM RISER DIAGRAM APPROVAL 5 14-Feb-16 18-Feb-16 15-Jul-15 22-Jul-15
Security SystSecurity Systems 15 21-Jun-16 04-Jul-16 13-Jul-15 28-Jul-15
ZB4EETELSS20 IPCCTV RISER DIAGRAM SUBMITTAL (By Others) 5 21-Jun-16 27-Jun-16 13-Jul-15 20-Jul-15
ZB4EETELSA20IPCCTV RISER DIAGRAM APPROVAL (By Others) 5 28-Jun-16 04-Jul-16 21-Jul-15 28-Jul-15
SCADA SystemSCADA System 15 12-May-16 01-Jun-16 13-Sep-15 28-Sep-15
ZB4EETEDS20 SCADA SYSTEM RISER DIAGRAM SUBMITTAL 5 12-May-16 18-May-16 13-Sep-15 17-Sep-15
ZB4EETEDA20 SCADA SYSTEM RISER DIAGRAM APPROVAL 5 26-May-16 01-Jun-16 20-Sep-15 28-Sep-15
Tunnel & Site LayTunnel & Site Layout 235 07-Feb-16 03-Nov-16 26-May-15 10-Jan-16
ZB4LEB460 Receive Approved Site Layout (Architecture & Structural & Roads
Sections and Levels)
0 27-Mar-16 26-May-15
ZB4LEB650 Receive Approved Site Layout (MEP Networks out of Siemens Scope) 0 27-Mar-16 26-May-15
Service TunnelService Tunnel 204 07-Feb-16 03-Nov-16 26-May-15 09-Dec-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
2015 2016 2017
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings_1 18-Feb-16 09:32
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 19 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish BL Project
Start
BL Project
Finish
Electrical SystemElectrical Systems 204 10-Mar-16 03-Nov-16 26-May-15 09-Dec-15
Tunnel MediumTunnel Medium Voltage Network 30 26-Jun-16 25-Jul-16 12-Nov-15 09-Dec-15
ZB4TEBEPS30 BASEMENT FLOOR MV NETWORK LAYOUT PLAN
SUBMITTAL
15 26-Jun-16 18-Jul-16 12-Nov-15 02-Dec-15
ZB4TEBEPA30 BASEMENT FLOOR MV NETWORK LAYOUT PLAN APPROVAL 5 19-Jul-16 25-Jul-16 03-Dec-15 09-Dec-15
Tunnel Low VoTunnel Low Voltage Network 0 03-Nov-16 03-Nov-16 26-May-15 26-May-15
ZB4TEBELA30 BASEMENT FLOOR LV NETWORK LAYOUT PLAN APPROVAL
(BY OTHERS)
0 03-Nov-16 26-May-15
Power SystemPower System 14 13-Mar-16 24-Mar-16 02-Aug-15 13-Aug-15
ZB4TEBEPS20 BASEMENT FLOOR POWER SYSTEM LAYOUT PLAN
SUBMITTAL
5 13-Mar-16 17-Mar-16 02-Aug-15 06-Aug-15
ZB4TEBEPA20 BASEMENT FLOOR POWER SYSTEM LAYOUT PLAN
APPROVAL
5 20-Mar-16 24-Mar-16 09-Aug-15 13-Aug-15
Lighting SystemLighting System 15 13-Mar-16 24-Mar-16 02-Jul-15 15-Jul-15
ZB4TEBELS20 BASEMENT FLOOR LIGHTING SYSTEM LAYOUT PLAN
SUBMITTAL
5 13-Mar-16 17-Mar-16 02-Jul-15 08-Jul-15
ZB4TEBELA20 BASEMENT FLOOR LIGHTING SYSTEM LAYOUT PLAN
APPROVAL
5 20-Mar-16 24-Mar-16 09-Jul-15 15-Jul-15
Light Current SLight Current Systems 83 10-Mar-16 24-Mar-16 26-May-15 13-Aug-15
Fire Alarm SyFire Alarm System 83 10-Mar-16 24-Mar-16 26-May-15 13-Aug-15
ZB4TEBELFA30INFRASTRUCTURE FIRE ALARM SERVICE CORRIDOR
APPROVAL (BY OTHERS)
0 10-Mar-16 26-May-15
ZB4TEBELFS20 BASEMENT FLOOR FIRE ALARM SYSTEM PLAN SUBMITTAL 5 13-Mar-16 17-Mar-16 02-Aug-15 06-Aug-15
ZB4TEBELFA20BASEMENT FLOOR FIRE ALARM SYSTEM PLAN APPROVAL 5 20-Mar-16 24-Mar-16 09-Aug-15 13-Aug-15
Security SystSecurity Systems 0 24-Mar-16 24-Mar-16 26-May-15 26-May-15
ZB4TEBELSA20CCTV SYSTEM - SERVICE CORRIDOR APPROVAL (BY
OTHERS)
0 24-Mar-16 26-May-15
CommunicatiCommunication Systems 0 24-Mar-16 24-Mar-16 26-May-15 26-May-15
ZB4TEBELCA20TELECOMMUNICATION INFRASTRUCTURE CABLING
APPROVAL (BY OTHERS)
0 24-Mar-16 26-May-15
SCADA SystemSCADA System 14 18-Jul-16 31-Jul-16 06-Sep-15 17-Sep-15
ZB4TEBEDS20 BASEMENT FLOOR SCADA SYSTEM LAYOUT PLAN
SUBMITTAL
5 18-Jul-16 24-Jul-16 06-Sep-15 10-Sep-15
ZB4TEBEDA20 BASEMENT FLOOR SCADA SYSTEM LAYOUT PLAN
APPROVAL
5 25-Jul-16 31-Jul-16 13-Sep-15 17-Sep-15
Mechanical SystMechanical Systems 60 28-Feb-16 03-Nov-16 10-Jun-15 06-Aug-15
HVAC SystemHVAC System 47 28-Feb-16 24-Mar-16 22-Jun-15 06-Aug-15
ZB4TEBMHS40 BASEMENT FLOOR HVAC PIPING LAYOUT PLAN SUBMITTAL 15 28-Feb-16 17-Mar-16 22-Jun-15 12-Jul-15
ZB4TEBMHA40 BASEMENT FLOOR HVAC PIPING LAYOUT PLAN APPROVAL 5 20-Mar-16 24-Mar-16 13-Jul-15 20-Jul-15
ZB4TEBMHS30 BASEMENT FLOOR HVAC DUCT SYSTEM LAYOUT PLAN
SUBMITTAL
10 06-Mar-16 17-Mar-16 15-Jul-15 30-Jul-15
ZB4TEBMHA30 BASEMENT FLOOR HVAC DUCT SYSTEM LAYOUT PLAN
APPROVAL
5 20-Mar-16 24-Mar-16 02-Aug-15 06-Aug-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
2015 2016 2017
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings_1 18-Feb-16 09:32
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 20 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish BL Project
Start
BL Project
Finish
Fire ProtectionFire Protection Systems 22 06-Mar-16 24-Mar-16 10-Jun-15 30-Jun-15
ZB4TEBMFS20 FIRE PROTECTION WORK -SERVICE TUNNEL- OVERALL
PLAN SUBMITTAL
10 06-Mar-16 17-Mar-16 10-Jun-15 23-Jun-15
ZB4TEBMFA20 FIRE PROTECTION WORK -SERVICE TUNNEL- OVERALL
PLAN APPROVAL
5 20-Mar-16 24-Mar-16 24-Jun-15 30-Jun-15
Plumbing SystPlumbing System 52 28-Feb-16 03-Nov-16 17-Jun-15 06-Aug-15
ZB4TEBMWS30 BASEMENT FLOOR WATER SUPPLY SYSTEM LAYOUT PLAN
SUBMITTAL
15 28-Feb-16 17-Mar-16 17-Jun-15 07-Jul-15
ZB4TEBMDS20 BASEMENT FLOOR DRAINAGE SYSTEM LAYOUT PLAN
SUBMITTAL
15 31-May-16 20-Jun-16 17-Jun-15 07-Jul-15
ZB4TEBMWA30 BASEMENT FLOOR WATER SUPPLY SYSTEM LAYOUT PLAN
APPROVAL
5 20-Mar-16 24-Mar-16 08-Jul-15 14-Jul-15
ZB4TEBMDA20 BASEMENT FLOOR DRAINAGE SYSTEM LAYOUT PLAN
APPROVAL
5 30-Oct-16 03-Nov-16 08-Jul-15 14-Jul-15
ZB4TEBMWS40 SUMP PIT DETAILS & SECTIONS SUBMITTAL 15 21-Jun-16 13-Jul-16 08-Jul-15 30-Jul-15
ZB4TEBMWA40 SUMP PIT DETAILS & SECTIONS APPROVAL 5 14-Jul-16 20-Jul-16 02-Aug-15 06-Aug-15
Composite DrawComposite Drawing 21 27-Mar-16 14-Apr-16 16-Aug-15 03-Sep-15
ZB4TEBCS20 SERVICE TUNNEL COMPOSITE LAYOUT PLAN SUBMITTAL 10 27-Mar-16 07-Apr-16 16-Aug-15 27-Aug-15
ZB4TEBCA20 SERVICE TUNNEL COMPOSITE LAYOUT PLAN APPROVAL 5 10-Apr-16 14-Apr-16 30-Aug-15 03-Sep-15
General Shop DrGeneral Shop Drawings 99 07-Feb-16 04-Jul-16 24-Jun-15 28-Sep-15
Electrical SysteElectrical Systems 99 07-Feb-16 04-Jul-16 24-Jun-15 28-Sep-15
ZB4TETEGS40 ELECTRICAL INSTALLATION DETAILS SUBMITTAL 5 11-May-16 17-May-16 26-Jul-15 30-Jul-15
ZB4TETEGA40 ELECTRICAL INSTALLATION DETAILS APPROVAL 5 18-May-16 24-May-16 02-Aug-15 06-Aug-15
Power SystemPower System 14 07-Apr-16 20-Apr-16 16-Aug-15 27-Aug-15
ZB4TETEPS70 POWER S.L.D AND PANEL BOARD SCHEDULE SUBMITTAL 5 07-Apr-16 13-Apr-16 16-Aug-15 20-Aug-15
ZB4TETEPA70 POWER S.L.D AND PANEL BOARD SCHEDULE APPROVAL 5 14-Apr-16 20-Apr-16 23-Aug-15 27-Aug-15
Lighting SystLighting System 22 01-Mar-16 10-Apr-16 08-Jul-15 30-Jul-15
ZB4TETELS80 LIGHTING FIXTURE SCHEDULE SUBMITTAL 5 01-Mar-16 07-Mar-16 08-Jul-15 14-Jul-15
ZB4TETELA80 LIGHTING FIXTURE SCHEDULE APPROVAL 5 04-Apr-16 10-Apr-16 15-Jul-15 22-Jul-15
ZB4TETELS90 KNX SYSTEM RISER DIAGRAM SUBMITTAL 5 08-Mar-16 14-Mar-16 15-Jul-15 22-Jul-15
ZB4TETELA90 KNX SYSTEM RISER DIAGRAM APPROVAL 5 15-Mar-16 21-Mar-16 26-Jul-15 30-Jul-15
Light CurrentLight Current Systems 35 07-Feb-16 04-Jul-16 24-Jun-15 28-Jul-15
ZB4TETELGS40LIGHT CURRENT TYPICAL INSTALLATION DETAILS
SUBMITTAL
5 03-Apr-16 07-Apr-16 24-Jun-15 30-Jun-15
ZB4TETELGA40LIGHT CURRENT TYPICAL INSTALLATION DETAILS
APPROVAL
5 10-Apr-16 14-Apr-16 01-Jul-15 07-Jul-15
Fire Alarm SysFire Alarm System 15 07-Feb-16 18-Feb-16 08-Jul-15 22-Jul-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
2015 2016 2017
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings_1 18-Feb-16 09:32
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 21 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish BL Project
Start
BL Project
Finish
ZB4TETELFS4FIRE ALARM RISER DIAGRAM SUBMITTAL 5 07-Feb-16 11-Feb-16 08-Jul-15 14-Jul-15
ZB4TETELFA4FIRE ALARM RISER DIAGRAM APPROVAL 5 14-Feb-16 18-Feb-16 15-Jul-15 22-Jul-15
Security SysteSecurity Systems 15 21-Jun-16 04-Jul-16 13-Jul-15 28-Jul-15
ZB4TETELSS4IPCCTV RISER DIAGRAM SUBMITTAL (By Others) 5 21-Jun-16 27-Jun-16 13-Jul-15 20-Jul-15
ZB4TETELSA4IPCCTV RISER DIAGRAM APPROVAL (By Others) 5 28-Jun-16 04-Jul-16 21-Jul-15 28-Jul-15
SCADA SysteSCADA System 15 12-May-16 01-Jun-16 13-Sep-15 28-Sep-15
ZB4TETEDS30 SCADA SYSTEM RISER DIAGRAM SUBMITTAL 5 12-May-16 18-May-16 13-Sep-15 17-Sep-15
ZB4TETEDA30 SCADA SYSTEM RISER DIAGRAM APPROVAL 5 26-May-16 01-Jun-16 20-Sep-15 28-Sep-15
Site LayoutSite Layout 235 16-Feb-16 14-Aug-16 27-May-15 10-Jan-16
Electrical SystemElectrical Systems 196 28-Mar-16 29-Jun-16 27-May-15 02-Dec-15
Tunnel MediumTunnel Medium Voltage Network 22 09-Jun-16 29-Jun-16 12-Nov-15 02-Dec-15
ZB4LEBEPS50 GROUND FLOOR MV NETWORK LAYOUT PLAN SUBMITTAL 10 09-Jun-16 22-Jun-16 12-Nov-15 25-Nov-15
ZB4LEBEPA50 GROUND FLOOR MV NETWORK LAYOUT PLAN APPROVAL 5 23-Jun-16 29-Jun-16 26-Nov-15 02-Dec-15
Tunnel Low VoTunnel Low Voltage Network 52 12-May-16 29-Jun-16 27-May-15 14-Jul-15
ZB4LEBELS50 GROUND FLOOR LV NETWORK LAYOUT PLAN SUBMITTAL 25 12-May-16 15-Jun-16 27-May-15 30-Jun-15
ZB4LEBELA50 GROUND FLOOR LV NETWORK LAYOUT PLAN APPROVAL 10 16-Jun-16 29-Jun-16 01-Jul-15 14-Jul-15
Power SystemPower System 52 12-May-16 29-Jun-16 06-Sep-15 28-Oct-15
ZB4LEBEPS40 GROUND FLOOR POWER SYSTEM LAYOUT PLAN SUBMITTAL 25 12-May-16 15-Jun-16 06-Sep-15 13-Oct-15
ZB4LEBEPA40 GROUND FLOOR POWER SYSTEM LAYOUT PLAN APPROVAL 10 16-Jun-16 29-Jun-16 15-Oct-15 28-Oct-15
Lighting SystemLighting System 44 28-Mar-16 11-May-16 26-Jul-15 03-Sep-15
ZB4LEBELS30 GROUND FLOOR LIGHTING SYSTEM LAYOUT PLAN
SUBMITTAL
25 28-Mar-16 04-May-16 26-Jul-15 27-Aug-15
ZB4LEBELA40 GROUND FLOOR LIGHTING SYSTEM LAYOUT PLAN
APPROVAL
5 05-May-16 11-May-16 30-Aug-15 03-Sep-15
SCADA SystemSCADA System 15 19-May-16 01-Jun-16 20-Sep-15 05-Oct-15
ZB4LEBEDS30 GROUND FLOOR SCADA SYSTEM LAYOUT PLAN SUBMITTAL 5 19-May-16 25-May-16 20-Sep-15 28-Sep-15
ZB4LEBEDA30 GROUND FLOOR SCADA SYSTEM LAYOUT PLAN APPROVAL 5 26-May-16 01-Jun-16 29-Sep-15 05-Oct-15
Composite DrawComposite Drawing 22 30-Jun-16 24-Jul-16 03-Dec-15 24-Dec-15
ZB4LEBCS30 SITE LAY OUT COMPOSITE LAYOUT PLAN SUBMITTAL 10 30-Jun-16 17-Jul-16 03-Dec-15 16-Dec-15
ZB4LEBCA30 SITE LAY OUT COMPOSITE LAYOUT PLAN APPROVAL 5 18-Jul-16 24-Jul-16 17-Dec-15 24-Dec-15
General Shop DrGeneral Shop Drawings 190 16-Feb-16 14-Aug-16 08-Jul-15 10-Jan-16
Electrical SysteElectrical Systems 190 16-Feb-16 14-Aug-16 08-Jul-15 10-Jan-16
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
2015 2016 2017
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings_1 18-Feb-16 09:32
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 22 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish BL Project
Start
BL Project
Finish
ZB4LETEGS50 ELECTRICAL INSTALLATION DETAILS SUBMITTAL 25 28-Mar-16 04-May-16 26-Jul-15 27-Aug-15
ZB4LETEGA50 ELECTRICAL INSTALLATION DETAILS APPROVAL 5 26-May-16 01-Jun-16 30-Aug-15 03-Sep-15
Power SystemPower System 15 01-Aug-16 14-Aug-16 27-Dec-15 10-Jan-16
ZB4LETEPS80 POWER S.L.D AND PANEL BOARD SCHEDULE SUBMITTAL 5 01-Aug-16 07-Aug-16 27-Dec-15 31-Dec-15
ZB4LETEPA80 POWER S.L.D AND PANEL BOARD SCHEDULE APPROVAL 5 08-Aug-16 14-Aug-16 03-Jan-16 10-Jan-16
Lighting SystLighting System 37 16-Feb-16 10-Apr-16 08-Jul-15 13-Aug-15
ZB4LETELS100 LIGHTING FIXTURE SCHEDULE SUBMITTAL 10 16-Feb-16 29-Feb-16 08-Jul-15 22-Jul-15
ZB4LETELA100 LIGHTING FIXTURE SCHEDULE APPROVAL 5 04-Apr-16 10-Apr-16 26-Jul-15 30-Jul-15
ZB4LETELS110 LIGHTING FIXTURES DETAILS ON STREET SECTIONS
SUBMITTAL
10 01-Mar-16 14-Mar-16 26-Jul-15 06-Aug-15
ZB4LETELA110 LIGHTING FIXTURES DETAILS ON STREET SECTIONS
APPROVAL
5 15-Mar-16 21-Mar-16 09-Aug-15 13-Aug-15
SCADA SysteSCADA System 52 11-Apr-16 01-Jun-16 13-Sep-15 04-Nov-15
ZB4LETEDS40 SCADA SYSTEM HAND HOLE LAYOUT SUBMITTAL 25 11-Apr-16 18-May-16 13-Sep-15 21-Oct-15
ZB4LETEDA40 SCADA SYSTEM HAND HOLE LAYOUTAPPROVAL 10 19-May-16 01-Jun-16 22-Oct-15 04-Nov-15
MaterialsMaterials 322 19-Nov-15 17-Nov-16 27-May-15 02-Apr-16
Building B4 - A (MBuilding B4 - A (Mechanical Utilities) 292 19-Nov-15 17-Nov-16 27-May-15 05-Mar-16
Electrical SystemElectrical Systems 285 20-Dec-15 26-Oct-16 03-Jun-15 05-Mar-16
Power SystemPower System 285 20-Dec-15 26-Oct-16 03-Jun-15 05-Mar-16
Material SubmiMaterial Submittal 144 20-Dec-15 08-Jun-16 03-Jun-15 21-Oct-15
ZB4EEMS080 EMT Material Submittal 10 18-Jan-16 01-Feb-16 03-Jun-15 16-Jun-15
ZB4EEMS090 IMC Material Submittal 10 18-Jan-16 01-Feb-16 03-Jun-15 16-Jun-15
ZB4EEMS040 Cable Trays and Ladders Material Submittal 10 20-Dec-15 03-Jan-16 10-Jun-15 23-Jun-15
ZB4EEMS110 B4-A Building ERMU Material Submittal 10 22-Mar-16 04-Apr-16 21-Jul-15 04-Aug-15
ZB4EEMS050 LV Cables Fire Resistant Material Submittal 20 09-Feb-16 07-Mar-16 08-Jul-15 06-Aug-15
ZB4EEMS030 LV Cables Material Submittal 7 14-Mar-16 22-Mar-16 16-Aug-15 24-Aug-15
ZB4EEMS180 B4-A Building MCC's Material Submittal 10 14-Mar-16 27-Mar-16 12-Aug-15 25-Aug-15
ZB4EEMS120 B4-A Building Transformers Material Submittal 20 29-Feb-16 27-Mar-16 02-Aug-15 27-Aug-15
ZB4EEMS100 B4-A Building UPS Material Submittal 20 27-Mar-16 21-Apr-16 09-Aug-15 03-Sep-15
ZB4EEMS070 MV Cables Material Submittal 7 28-Mar-16 05-Apr-16 30-Aug-15 07-Sep-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
2015 2016 2017
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings_1 18-Feb-16 09:32
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 23 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish BL Project
Start
BL Project
Finish
ZB4EEMS150 B4-A Building EMDB & EDB Material Submittal 10 28-Mar-16 10-Apr-16 30-Aug-15 10-Sep-15
ZB4EEMS160 B4-A Building Distribution Panels Material Submittal 10 04-Apr-16 17-Apr-16 30-Aug-15 10-Sep-15
ZB4EEMS170 B4-A Building Bus Bar Material Submittal 10 29-Mar-16 11-Apr-16 30-Aug-15 10-Sep-15
ZB4EEMS060 LV Earthing Cables Material Submittal 20 29-Mar-16 26-Apr-16 23-Aug-15 17-Sep-15
ZB4EEMS130 Disconnecting Switch Material Submittal 20 27-Mar-16 21-Apr-16 23-Aug-15 17-Sep-15
ZB4EEMS140 Wiring Devices Material Submittal 20 27-Mar-16 21-Apr-16 23-Aug-15 17-Sep-15
ZB4EEMS190 B4-A Building VSD Material Submittal 20 12-May-16 08-Jun-16 20-Sep-15 21-Oct-15
ZB4EEMS200 B4-A Building Soft Starter Material Submittal 20 12-May-16 08-Jun-16 20-Sep-15 21-Oct-15
Material ApproMaterial Approvals 136 04-Jan-16 15-Jun-16 17-Jun-15 28-Oct-15
ZB4EEMA080 EMT Material Approval 5 02-Feb-16 08-Feb-16 17-Jun-15 23-Jun-15
ZB4EEMA090 IMC Material Approval 5 02-Feb-16 08-Feb-16 17-Jun-15 23-Jun-15
ZB4EEMA040 Cable Trays and Ladders Material Approval 5 04-Jan-16 11-Jan-16 24-Jun-15 30-Jun-15
ZB4EEMA110 B4-A Building ERMU Material Approval 5 05-Apr-16 11-Apr-16 05-Aug-15 11-Aug-15
ZB4EEMA050 LV Cables Fire Resistant Material Approval 5 08-Mar-16 14-Mar-16 09-Aug-15 13-Aug-15
ZB4EEMA030 LV Cables Material Approval 5 23-Mar-16 29-Mar-16 25-Aug-15 31-Aug-15
ZB4EEMA180 B4-A Building MCC's Material Approval 5 28-Mar-16 03-Apr-16 26-Aug-15 01-Sep-15
ZB4EEMA120 B4-A Building Transformers Material Approval 5 28-Mar-16 03-Apr-16 30-Aug-15 03-Sep-15
ZB4EEMA100 B4-A Building UPS Material Approval 5 24-Apr-16 03-May-16 06-Sep-15 10-Sep-15
ZB4EEMA070 MV Cables Material Approval 5 20-Apr-16 27-Apr-16 08-Sep-15 14-Sep-15
ZB4EEMA150 B4-A Building EMDB & EDB Material Approval 5 11-Apr-16 17-Apr-16 13-Sep-15 17-Sep-15
ZB4EEMA160 B4-A Building Distribution Panels Material Approval 5 18-Apr-16 24-Apr-16 13-Sep-15 17-Sep-15
ZB4EEMA170 B4-A Building Bus Bar Material Approval 5 12-Apr-16 18-Apr-16 13-Sep-15 17-Sep-15
ZB4EEMA060 LV Earthing Cables Material Approval 5 27-Apr-16 05-May-16 20-Sep-15 28-Sep-15
ZB4EEMA130 Disconnecting Switch Material Approval 5 26-Apr-16 04-May-16 20-Sep-15 28-Sep-15
ZB4EEMA140 Wiring Devices Material Approval 5 26-Apr-16 04-May-16 20-Sep-15 28-Sep-15
ZB4EEMA190 B4-A Building VSD Material Approval 5 09-Jun-16 15-Jun-16 22-Oct-15 28-Oct-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
2015 2016 2017
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings_1 18-Feb-16 09:32
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 24 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish BL Project
Start
BL Project
Finish
ZB4EEMA200 B4-A Building Soft Starter Material Approval 5 09-Jun-16 15-Jun-16 22-Oct-15 28-Oct-15
Material PO'sMaterial PO's 170 16-Feb-16 02-Aug-16 01-Jul-15 13-Dec-15
ZB4EEMP080 EMT Material PO 5 16-Feb-16 22-Feb-16 01-Jul-15 07-Jul-15
ZB4EEMP090 IMC Material PO 5 16-Feb-16 22-Feb-16 01-Jul-15 07-Jul-15
ZB4EEMP040 Cable Trays and Ladders Material PO 10 29-Feb-16 13-Mar-16 15-Jul-15 30-Jul-15
ZB4EEMP110 B4-A Building ERMU Material PO 10 12-Apr-16 26-Apr-16 12-Aug-15 25-Aug-15
ZB4EEMP030 LV Cables Material PO 10 30-Mar-16 12-Apr-16 01-Sep-15 14-Sep-15
ZB4EEMP180 B4-A Building MCC's Material PO 10 04-Apr-16 17-Apr-16 02-Sep-15 15-Sep-15
ZB4EEMP050 LV Cables Fire Resistant Material PO 10 05-Apr-16 18-Apr-16 06-Sep-15 17-Sep-15
ZB4EEMP0300 Power Circuits Cables and Wires PO 5 22-Mar-16 28-Mar-16 13-Sep-15 17-Sep-15
ZB4EEMP150 B4-A Building EMDB & EDB Material PO 10 18-Apr-16 04-May-16 20-Sep-15 05-Oct-15
ZB4EEMP160 B4-A Building Distribution Panels Material PO 10 26-Apr-16 11-May-16 20-Sep-15 05-Oct-15
ZB4EEMP170 B4-A Building Bus Bar Material PO 10 19-Apr-16 05-May-16 20-Sep-15 05-Oct-15
ZB4EEMP130 Disconnecting Switch Material PO 10 05-May-16 18-May-16 29-Sep-15 13-Oct-15
ZB4EEMP140 Wiring Devices Material PO 10 05-May-16 18-May-16 29-Sep-15 13-Oct-15
ZB4EEMP120 B4-A Building Transformers Material PO 10 09-May-16 22-May-16 11-Oct-15 25-Oct-15
ZB4EEMP100 B4-A Building UPS Material PO 10 05-Jun-16 16-Jun-16 19-Oct-15 01-Nov-15
ZB4EEMP070 MV Cables Material PO 10 01-Jun-16 14-Jun-16 21-Oct-15 03-Nov-15
ZB4EEMP060 LV Earthing Cables Material PO 10 07-Jun-16 20-Jun-16 02-Nov-15 15-Nov-15
ZB4EEMP190 B4-A Building VSD Material PO 10 20-Jul-16 02-Aug-16 30-Nov-15 13-Dec-15
ZB4EEMP200 B4-A Building Soft Starter Material PO 10 20-Jul-16 02-Aug-16 30-Nov-15 13-Dec-15
Material DeliveMaterial Delivery at Site 247 23-Feb-16 26-Oct-16 08-Jul-15 05-Mar-16
ZB4EEMD080 EMT Material Delivery 10 23-Feb-16 05-Mar-16 08-Jul-15 20-Jul-15
ZB4EEMD090 IMC Material Delivery 10 23-Feb-16 05-Mar-16 08-Jul-15 20-Jul-15
ZB4EEMD0300 Power Circuits Cables and Wires Partial Delivery 52 23-Apr-16 25-Jun-16 19-Sep-15 22-Nov-15
ZB4EEMD030 LV Cables Material Delivery 60 13-Apr-16 25-Jun-16 15-Sep-15 28-Nov-15
ZB4EEMD110 B4-A Building ERMU Material Delivery 78 27-Apr-16 01-Aug-16 26-Aug-15 29-Nov-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
2015 2016 2017
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings_1 18-Feb-16 09:32
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 25 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish BL Project
Start
BL Project
Finish
ZB4EEMD180 B4-A Building MCC's Material Delivery 70 18-Apr-16 13-Jul-16 16-Sep-15 10-Dec-15
ZB4EEMD160 B4-A Building Distribution Panels Material Delivery 60 12-May-16 24-Jul-16 07-Oct-15 16-Dec-15
ZB4EEMD040 Cable Trays and Ladders Material Partial Delivery 120 14-Mar-16 07-Aug-16 01-Aug-15 22-Dec-15
ZB4EEMD120 B4-A Building Transformers Material Delivery 60 23-May-16 03-Aug-16 26-Oct-15 04-Jan-16
ZB4EEMD050 LV Cables Fire Resistant Material Delivery 90 19-Apr-16 08-Aug-16 19-Sep-15 06-Jan-16
ZB4EEMD150 B4-A Building EMDB & EDB Material Delivery 78 05-May-16 07-Aug-16 07-Oct-15 09-Jan-16
ZB4EEMD170 B4-A Building Bus Bar Material Delivery 78 08-May-16 09-Aug-16 07-Oct-15 09-Jan-16
ZB4EEMD070 MV Cables Material Delivery 60 15-Jun-16 27-Aug-16 04-Nov-15 14-Jan-16
ZB4EEMD130 Disconnecting Switch Material Delivery 78 19-May-16 21-Aug-16 15-Oct-15 16-Jan-16
ZB4EEMD140 Wiring Devices Material Delivery 78 19-May-16 21-Aug-16 15-Oct-15 16-Jan-16
ZB4EEMD060 LV Earthing Cables Material Partial Delivery 60 21-Jun-16 01-Sep-16 16-Nov-15 27-Jan-16
ZB4EEMD190 B4-A Building VSD Material Delivery 60 03-Aug-16 17-Oct-16 14-Dec-15 24-Feb-16
ZB4EEMD200 B4-A Building Soft Starter Material Delivery 60 03-Aug-16 17-Oct-16 14-Dec-15 24-Feb-16
ZB4EEMD100 B4-A Building UPS Material Delivery 104 19-Jun-16 26-Oct-16 02-Nov-15 05-Mar-16
Lighting SystemLighting System 157 15-Mar-16 22-Aug-16 16-Aug-15 16-Jan-16
Material SubmiMaterial Submittal 36 15-Mar-16 11-May-16 16-Aug-15 17-Sep-15
ZB4EEMS210 B4 Buildings Lighting Fixtures Material Submittal 20 11-Apr-16 11-May-16 16-Aug-15 10-Sep-15
ZB4EEMS220 B4 Buildings CENTRAL MONITORING SYSTEM Material Submittal 20 15-Mar-16 11-Apr-16 16-Aug-15 10-Sep-15
ZB4EEMS230 B4 Buildings KNX/EIP SYSTEM Material Submittal 20 22-Mar-16 18-Apr-16 23-Aug-15 17-Sep-15
Material ApproMaterial Approvals 22 12-Apr-16 05-Jun-16 13-Sep-15 05-Oct-15
ZB4EEMA210 B4 Buildings Lighting Fixtures Material Approval 10 23-May-16 05-Jun-16 13-Sep-15 28-Sep-15
ZB4EEMA220 B4 Buildings CENTRAL MONITORING SYSTEM Material Approval 10 12-Apr-16 26-Apr-16 13-Sep-15 28-Sep-15
ZB4EEMA230 B4 Buildings KNX/EIP SYSTEM Material Approval 10 19-Apr-16 05-May-16 20-Sep-15 05-Oct-15
Material PO'sMaterial PO's 52 11-Apr-16 27-Jun-16 13-Sep-15 04-Nov-15
ZB4EEMP240 B4A Building Lighting Wires Material PO 10 11-Apr-16 24-Apr-16 13-Sep-15 28-Sep-15
ZB4EEMP210 B4A Building Lighting Fixtures Material PO 10 14-Jun-16 27-Jun-16 08-Oct-15 22-Oct-15
ZB4EEMP220 B4A Building CENTRAL MONITORING SYSTEM Material PO 10 15-May-16 26-May-16 15-Oct-15 28-Oct-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
2015 2016 2017
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings_1 18-Feb-16 09:32
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 26 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish BL Project
Start
BL Project
Finish
ZB4EEMP230 B4A Building KNX/EIP SYSTEM Material PO 10 22-May-16 02-Jun-16 22-Oct-15 04-Nov-15
Material DeliveMaterial Delivery at Site 112 28-May-16 22-Aug-16 29-Sep-15 16-Jan-16
ZB4EEMD240 B4A Building Lighting Wires Material Partial Delivery 10 14-Jun-16 25-Jun-16 29-Sep-15 11-Oct-15
ZB4EEMD210 B4A Building Lighting Fixtures Material Delivery 45 28-Jun-16 22-Aug-16 24-Oct-15 14-Dec-15
ZB4EEMD220 B4A Building CENTRAL MONITORING SYSTEM Material Delivery 65 28-May-16 14-Aug-16 29-Oct-15 14-Jan-16
ZB4EEMD230 B4A Building KNX/EIP SYSTEM Material Delivery 60 05-Jun-16 16-Aug-16 05-Nov-15 16-Jan-16
Cable Tray SysteCable Tray System 179 08-May-16 14-Aug-16 15-Jul-15 05-Jan-16
Material PO'sMaterial PO's 91 08-May-16 23-Jun-16 15-Jul-15 13-Oct-15
ZB4EEMP250 Cable Trays and Ladders For Equipments Material PO 10 12-Jun-16 23-Jun-16 15-Jul-15 30-Jul-15
ZB4EEMP260 LV Cables For Equipments Material PO 10 09-May-16 22-May-16 01-Sep-15 14-Sep-15
ZB4EEMP270 LV Earthing For Equipments Cables Material PO 10 08-May-16 19-May-16 29-Sep-15 13-Oct-15
Material DeliveMaterial Delivery at Site 164 22-May-16 14-Aug-16 01-Aug-15 05-Jan-16
ZB4EEMD250 Cable Trays and Ladders Material Delivery 10 25-Jun-16 07-Jul-16 01-Aug-15 11-Aug-15
ZB4EEMD260 LV Cables Material Delivery 60 23-May-16 03-Aug-16 15-Sep-15 28-Nov-15
ZB4EEMD270 LV Earthing Cables Material Delivery 70 22-May-16 14-Aug-16 15-Oct-15 05-Jan-16
Earthing SystemEarthing System 206 09-Feb-16 25-Aug-16 10-Jun-15 27-Dec-15
Material SubmiMaterial Submittal 30 09-Feb-16 07-Mar-16 10-Jun-15 07-Jul-15
ZB4EEMS010 Earthing System Material Submittal 20 09-Feb-16 07-Mar-16 10-Jun-15 07-Jul-15
Material ApproMaterial Approvals 15 08-Mar-16 21-Mar-16 08-Jul-15 22-Jul-15
ZB4EEMA010 Earthing System Material Approval 10 08-Mar-16 21-Mar-16 08-Jul-15 22-Jul-15
Material PO'sMaterial PO's 15 21-Apr-16 09-May-16 25-Aug-15 07-Sep-15
ZB4EEMP010 Earthing System Material PO 10 21-Apr-16 09-May-16 25-Aug-15 07-Sep-15
Material DeliveMaterial Delivery at Site 112 10-May-16 25-Aug-16 08-Sep-15 27-Dec-15
ZB4EEMD010 Earthing System Material Delivery 90 10-May-16 25-Aug-16 08-Sep-15 27-Dec-15
Lightning SystemLightning System 205 03-Feb-16 18-Aug-16 10-Jun-15 26-Dec-15
Material SubmiMaterial Submittal 30 03-Feb-16 01-Mar-16 10-Jun-15 07-Jul-15
ZB4EEMS020 LIGHTNING System Material Submittal 20 03-Feb-16 01-Mar-16 10-Jun-15 07-Jul-15
Material ApproMaterial Approvals 15 02-Mar-16 15-Mar-16 08-Jul-15 22-Jul-15
ZB4EEMA020 LIGHTNING System Material Approval 10 02-Mar-16 15-Mar-16 08-Jul-15 22-Jul-15
Material PO'sMaterial PO's 14 30-Mar-16 12-Apr-16 09-Aug-15 20-Aug-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
2015 2016 2017
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings_1 18-Feb-16 09:32
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 27 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish BL Project
Start
BL Project
Finish
ZB4EEMP020 LIGHTNING System Material PO 10 30-Mar-16 12-Apr-16 09-Aug-15 20-Aug-15
Material DeliveMaterial Delivery at Site 130 13-Apr-16 18-Aug-16 22-Aug-15 26-Dec-15
ZB4EEMD020 LIGHTNING System Material Delivery 104 13-Apr-16 18-Aug-16 22-Aug-15 26-Dec-15
Light Current SyLight Current Systems 156 21-Feb-16 18-Aug-16 26-Jul-15 22-Dec-15
Fire Alarm SystFire Alarm System 156 21-Feb-16 18-Aug-16 26-Jul-15 22-Dec-15
Material SubmMaterial Submittal 29 21-Feb-16 17-Mar-16 26-Jul-15 20-Aug-15
ZB4EEMS240 Fire Alarm System Material Submittal 20 21-Feb-16 17-Mar-16 26-Jul-15 20-Aug-15
Material ApprMaterial Approvals 14 20-Mar-16 31-Mar-16 23-Aug-15 03-Sep-15
ZB4EEMA240 Fire Alarm System Material Approval 10 20-Mar-16 31-Mar-16 23-Aug-15 03-Sep-15
Material PO'sMaterial PO's 14 03-Apr-16 16-May-16 06-Sep-15 17-Sep-15
ZB4EEMP280 Fire Alarm System Devices Material PO 10 03-Apr-16 14-Apr-16 06-Sep-15 17-Sep-15
ZB4EEMP290 Fire Alarm System Fire Alarm Cable Material PO 10 03-Apr-16 14-Apr-16 06-Sep-15 17-Sep-15
ZB4EEMP300 Fire Alarm System FACP Material PO 10 03-May-16 16-May-16 06-Sep-15 17-Sep-15
Material DelivMaterial Delivery at Site 97 17-Apr-16 18-Aug-16 19-Sep-15 22-Dec-15
ZB4EEMD280 Fire Alarm System Devices Material Delivery 78 17-Apr-16 21-Jul-16 19-Sep-15 22-Dec-15
ZB4EEMD290 Fire Alarm System Fire Alarm Cable Material Delivery 78 17-Apr-16 21-Jul-16 19-Sep-15 22-Dec-15
ZB4EEMD300 Fire Alarm System FACP Material Delivery 78 17-May-16 18-Aug-16 19-Sep-15 22-Dec-15
SCADA SystemSCADA System 120 02-Jun-16 28-Sep-16 05-Nov-15 28-Feb-16
Material SubmiMaterial Submittal 7 02-Jun-16 08-Jun-16 05-Nov-15 11-Nov-15
ZB4EEMS250 SCADA System Material Submittal 5 02-Jun-16 08-Jun-16 05-Nov-15 11-Nov-15
Material ApproMaterial Approvals 7 09-Jun-16 15-Jun-16 12-Nov-15 18-Nov-15
ZB4EEMA250 SCADA System Material Approval 5 09-Jun-16 15-Jun-16 12-Nov-15 18-Nov-15
Material PO'sMaterial PO's 7 16-Jun-16 22-Jun-16 19-Nov-15 25-Nov-15
ZB4EEMP310 SCADA System Material PO 5 16-Jun-16 22-Jun-16 19-Nov-15 25-Nov-15
Material DeliveMaterial Delivery at Site 97 23-Jun-16 28-Sep-16 26-Nov-15 28-Feb-16
ZB4EEMD310 SCADA System Material Delivery 78 23-Jun-16 28-Sep-16 26-Nov-15 28-Feb-16
Mechanical SystMechanical Systems 265 19-Nov-15 17-Nov-16 27-May-15 08-Feb-16
HVAC SystemHVAC System 260 10-Dec-15 28-Sep-16 27-May-15 04-Feb-16
Material SubmiMaterial Submittal 155 10-Dec-15 15-Jun-16 27-May-15 25-Oct-15
ZB4EEMS390 Black welded (ERW) steel piping Material Submittal 5 30-Dec-15 05-Jan-16 01-Jun-15 07-Jun-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
2015 2016 2017
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings_1 18-Feb-16 09:32
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 28 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish BL Project
Start
BL Project
Finish
ZB4EEMS440 Variable Air Volume (VAV) Boxes Material Submittal 15 10-Dec-15 31-Dec-15 27-May-15 16-Jun-15
ZB4EEMS260 Chillers Material Submittal 12 03-Jan-16 19-Jan-16 04-Jun-15 21-Jun-15
ZB4EEMS270 Cooling Towers Material Submittal 10 27-Jan-16 09-Feb-16 28-Jun-15 09-Jul-15
ZB4EEMS310 AHU Material Submittal 12 10-Jan-16 26-Jan-16 28-Jun-15 13-Jul-15
ZB4EEMS410 Chilled Water Valves Material Submittal 22 13-Jan-16 14-Feb-16 14-Jun-15 13-Jul-15
ZB4EEMS380 Child pipe hangers and support Material Submittal 15 31-Jan-16 18-Feb-16 28-Jun-15 19-Jul-15
ZB4EEMS280 Child Water Pumps Material Submittal 22 17-Jan-16 16-Feb-16 02-Jul-15 04-Aug-15
ZB4EEMS315 Expansion Tanks Material Submittal 12 25-Feb-16 13-Mar-16 19-Jul-15 04-Aug-15
ZB4EEMS370 Black seamless steel piping Material Submittal 15 17-Feb-16 08-Mar-16 19-Jul-15 09-Aug-15
ZB4EEMS300 Heat Exchangers Material Submittal 22 04-Feb-16 06-Mar-16 08-Jul-15 10-Aug-15
ZB4EEMS320 Metal Sheet Duct Material Submittal 15 07-Feb-16 25-Feb-16 26-Jul-15 13-Aug-15
ZB4EEMS400 UPVC piping (16 bar) Material Submittal 22 30-Mar-16 03-May-16 26-Jul-15 24-Aug-15
ZB4EEMS340 Chimney Black Steel Sheet Material Sample Submittal 18 20-Mar-16 12-Apr-16 02-Aug-15 25-Aug-15
ZB4EEMS330 FD & VD Material Submittal 22 03-Mar-16 03-Apr-16 02-Aug-15 31-Aug-15
ZB4EEMS350 Fire Smoke Dampers Material Submittal 22 07-Mar-16 05-Apr-16 09-Aug-15 07-Sep-15
ZB4EEMS360 Duct Insulation Material Submittal 22 07-Apr-16 11-May-16 11-Aug-15 09-Sep-15
ZB4EEMS430 Air Separators Material Submittal 22 22-Mar-16 20-Apr-16 16-Aug-15 14-Sep-15
ZB4EEMS420 Chilled Water Piping Insulation Material Submittal 22 22-Mar-16 20-Apr-16 23-Aug-15 21-Sep-15
ZB4EEMS450 Air Outlets Material Submittal 22 28-Mar-16 27-Apr-16 30-Aug-15 30-Sep-15
ZB4EEMS460 Water Treatment and Chemical Cleaning System Material Submittal 22 10-Apr-16 12-May-16 06-Sep-15 08-Oct-15
ZB4EEMS470 Over Head Crane Material Submittal 22 03-May-16 01-Jun-16 06-Sep-15 08-Oct-15
ZB4EEMS480 Monorail Crane Material Submittal 22 17-May-16 15-Jun-16 06-Sep-15 08-Oct-15
ZB4EEMS290 Testing, Balancing & Commisioning system Third Part Submittal 22 19-Apr-16 23-May-16 20-Sep-15 25-Oct-15
Material ApproMaterial Approvals 150 03-Jan-16 22-Jun-16 08-Jun-15 01-Nov-15
ZB4EEMA390 Black welded (ERW) steel piping Material Approval 5 20-Jan-16 27-Jan-16 08-Jun-15 14-Jun-15
ZB4EEMA440 Variable Air Volume (VAV) Boxes Material Approval 5 03-Jan-16 10-Jan-16 17-Jun-15 23-Jun-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
2015 2016 2017
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings_1 18-Feb-16 09:32
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 29 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish BL Project
Start
BL Project
Finish
ZB4EEMA260 Chillers System Material Approval 5 20-Jan-16 27-Jan-16 22-Jun-15 28-Jun-15
ZB4EEMA270 Cooling Towers System Material Approval 5 10-Feb-16 16-Feb-16 12-Jul-15 19-Jul-15
ZB4EEMA310 AHU System Material Approval 5 27-Jan-16 02-Feb-16 14-Jul-15 21-Jul-15
ZB4EEMA410 Chilled Water Valves Material Approval 5 10-Mar-16 16-Mar-16 14-Jul-15 21-Jul-15
ZB4EEMA380 Child pipe hangers and support Material Approval 5 27-Mar-16 31-Mar-16 20-Jul-15 27-Jul-15
ZB4EEMA280 Child Water Pumps Material Approval 5 17-Feb-16 23-Feb-16 05-Aug-15 11-Aug-15
ZB4EEMA315 Expansion Tanks Material Approval 5 14-Mar-16 20-Mar-16 05-Aug-15 11-Aug-15
ZB4EEMA370 Black seamless steel piping Material Approval 5 03-Apr-16 07-Apr-16 10-Aug-15 16-Aug-15
ZB4EEMA300 Heat Exchangers System Material Approval 5 07-Mar-16 13-Mar-16 11-Aug-15 17-Aug-15
ZB4EEMA320 Metal Sheet Duct System Material Approval 5 28-Feb-16 03-Mar-16 16-Aug-15 20-Aug-15
ZB4EEMA400 UPVC piping (16 bar) Material Approval 5 04-May-16 10-May-16 25-Aug-15 31-Aug-15
ZB4EEMA340 Chimney Black Steel Sheet Material Sample Approval 5 13-Apr-16 19-Apr-16 26-Aug-15 01-Sep-15
ZB4EEMA330 FD & VD Material Approval 5 05-Apr-16 11-Apr-16 01-Sep-15 07-Sep-15
ZB4EEMA350 Fire Smoke Dampers Material Approval 5 07-Apr-16 13-Apr-16 08-Sep-15 14-Sep-15
ZB4EEMA360 Duct Insulation Material Approval 5 12-May-16 18-May-16 10-Sep-15 16-Sep-15
ZB4EEMA430 Air Separators Material Approval 5 21-Apr-16 28-Apr-16 15-Sep-15 21-Sep-15
ZB4EEMA420 Chilled Water Piping Insulation Material Approval 5 27-Apr-16 05-May-16 22-Sep-15 30-Sep-15
ZB4EEMA450 Air Outlets Material Approval 5 28-Apr-16 08-May-16 01-Oct-15 08-Oct-15
ZB4EEMA460 Water Treatment and Chemical Cleaning System Material Approval 5 15-May-16 19-May-16 11-Oct-15 18-Oct-15
ZB4EEMA470 Over Head Crane Material Approval 5 02-Jun-16 08-Jun-16 11-Oct-15 18-Oct-15
ZB4EEMA480 Monorail Crane Material Approval 5 16-Jun-16 22-Jun-16 11-Oct-15 18-Oct-15
ZB4EEMA290 Testing, Balancing & Commisioning system Third Part Approval 5 24-May-16 30-May-16 26-Oct-15 01-Nov-15
Material PO'sMaterial PO's 142 28-Jan-16 10-Jul-16 15-Jun-15 01-Nov-15
ZB4EEMP450 Black welded (ERW) steel piping Material PO 10 28-Jan-16 10-Feb-16 15-Jun-15 28-Jun-15
ZB4EEMP320 Chillers System Material PO 10 28-Jan-16 10-Feb-16 29-Jun-15 12-Jul-15
ZB4EEMP330 Cooling Towers System Material PO 10 17-Feb-16 01-Mar-16 20-Jul-15 03-Aug-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
2015 2016 2017
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings_1 18-Feb-16 09:32
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 30 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish BL Project
Start
BL Project
Finish
ZB4EEMP370 AHU System Material PO 10 03-Feb-16 16-Feb-16 22-Jul-15 05-Aug-15
ZB4EEMP470 Chilled Water Valves Material PO 10 17-Mar-16 30-Mar-16 22-Jul-15 05-Aug-15
ZB4EEMP440 Child pipe hangers and support Material PO 10 17-Apr-16 03-May-16 28-Jul-15 10-Aug-15
ZB4EEMP500 Variable Air Volume (VAV) Boxes Material PO 10 15-Mar-16 28-Mar-16 28-Jul-15 10-Aug-15
ZB4EEMP340 Child Water Pumps Material PO 10 24-Feb-16 08-Mar-16 12-Aug-15 25-Aug-15
ZB4EEMP315 Expansion Tanks Material PO 10 21-Mar-16 03-Apr-16 12-Aug-15 25-Aug-15
ZB4EEMP430 Black seamless steel piping Material PO 10 18-May-16 31-May-16 17-Aug-15 30-Aug-15
ZB4EEMP360 Heat Exchangers System Material PO 10 14-Mar-16 27-Mar-16 18-Aug-15 31-Aug-15
ZB4EEMP380 Metal Sheet Duct System Material PO 10 27-Apr-16 12-May-16 23-Aug-15 03-Sep-15
ZB4EEMP460 UPVC piping (16 bar) Material PO 10 11-May-16 24-May-16 01-Sep-15 14-Sep-15
ZB4EEMP390 FD & VD Material PO 10 12-Apr-16 26-Apr-16 08-Sep-15 21-Sep-15
ZB4EEMP410 Fire Smoke Dampers Material PO 10 14-Apr-16 28-Apr-16 15-Sep-15 30-Sep-15
ZB4EEMP420 Duct Insulation Material PO 10 19-May-16 01-Jun-16 17-Sep-15 04-Oct-15
ZB4EEMP490 Air Separators Material PO 10 03-May-16 16-May-16 22-Sep-15 08-Oct-15
ZB4EEMP480 Chilled Water Piping Insulation Material PO 10 25-May-16 07-Jun-16 01-Oct-15 18-Oct-15
ZB4EEMP400 Chimney Black Steel Sheet Material PO 10 25-May-16 07-Jun-16 07-Oct-15 21-Oct-15
ZB4EEMP510 Air Outlets Material PO 10 09-May-16 22-May-16 11-Oct-15 25-Oct-15
ZB4EEMP520 Water Treatment and Chemical Cleaning System Material PO 10 22-May-16 02-Jun-16 19-Oct-15 01-Nov-15
ZB4EEMP530 Over Head Crane Material PO 10 09-Jun-16 22-Jun-16 19-Oct-15 01-Nov-15
ZB4EEMP540 Monorail Crane Material PO 10 23-Jun-16 10-Jul-16 19-Oct-15 01-Nov-15
Material DeliveMaterial Delivery at Site 225 11-Feb-16 28-Sep-16 29-Jun-15 04-Feb-16
ZB4EEMD440 Child pipe hangers and support Material ( Partial )Delivery 36 04-May-16 14-Jun-16 11-Aug-15 21-Sep-15
ZB4EEMD450 Black welded (ERW) steel piping Material ( Partial )Delivery 104 11-Feb-16 14-Jun-16 29-Jun-15 03-Nov-15
ZB4EEMD330 Cooling Towers System Material Delivery 78 02-Mar-16 04-Jun-16 04-Aug-15 07-Nov-15
ZB4EEMD370 AHU System Material Delivery 78 17-Feb-16 21-May-16 06-Aug-15 09-Nov-15
ZB4EEMD320 Chillers Material Delivery 104 11-Feb-16 14-Jun-16 13-Jul-15 17-Nov-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
2015 2016 2017
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings_1 18-Feb-16 09:32
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 31 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish BL Project
Start
BL Project
Finish
ZB4EEMD380 Metal Sheet Duct System Partial Material Delivery / Fabrication 65 14-May-16 31-Jul-16 05-Sep-15 23-Nov-15
ZB4EEMD315 Expansion Tanks Material Delivery 78 04-Apr-16 09-Jul-16 26-Aug-15 29-Nov-15
ZB4EEMD430 Black seamless steel piping Material ( Partial )Delivery 78 01-Jun-16 03-Sep-16 31-Aug-15 03-Dec-15
ZB4EEMD420 Duct Insulation Material Delivery 52 02-Jun-16 04-Aug-16 05-Oct-15 06-Dec-15
ZB4EEMD470 Chilled Water Valves Material ( Partial )Delivery 104 31-Mar-16 06-Aug-16 06-Aug-15 09-Dec-15
ZB4EEMD400 Chimney Material Fabrication / Delivery 45 08-Jun-16 02-Aug-16 22-Oct-15 13-Dec-15
ZB4EEMD500 Variable Air Volume (VAV) Boxes Material Delivery 104 29-Mar-16 03-Aug-16 11-Aug-15 14-Dec-15
ZB4EEMD360 Heat Exchangers System Material Delivery 90 28-Mar-16 16-Jul-16 01-Sep-15 19-Dec-15
ZB4EEMD460 UPVC piping (16 bar) Material ( Partial )Delivery 78 25-May-16 27-Aug-16 15-Sep-15 19-Dec-15
ZB4EEMD390 FD & VD Material Delivery 80 27-Apr-16 03-Aug-16 22-Sep-15 29-Dec-15
ZB4EEMD340 Child Water Pumps Material Delivery 104 09-Mar-16 13-Jul-16 26-Aug-15 30-Dec-15
ZB4EEMD410 Fire Smoke Dampers Material Delivery 78 03-May-16 04-Aug-16 01-Oct-15 03-Jan-16
ZB4EEMD520 Water Treatment and Chemical Cleaning System Material Delivery On
Site
60 05-Jun-16 16-Aug-16 02-Nov-15 12-Jan-16
ZB4EEMD480 Chilled Water Piping Insulation Material ( Partial ) Delivery 75 08-Jun-16 06-Sep-16 19-Oct-15 16-Jan-16
ZB4EEMD540 Monorail Crane Material Delivery On Site 65 11-Jul-16 28-Sep-16 02-Nov-15 18-Jan-16
ZB4EEMD490 Air Separators Material Delivery 90 17-May-16 01-Sep-16 10-Oct-15 26-Jan-16
ZB4EEMD510 Air Outlets Material Delivery 78 23-May-16 24-Aug-16 26-Oct-15 27-Jan-16
ZB4EEMD530 Over Head Crane Material Delivery On Site 78 23-Jun-16 28-Sep-16 02-Nov-15 03-Feb-16
ZB4EEMD350 Testing, Balancing & Commisioning system Third Part On Site 0 01-Sep-16 04-Feb-16
Fire Protection SFire Protection Systems 245 26-Nov-15 28-Aug-16 27-May-15 19-Jan-16
Material SubmiMaterial Submittal 157 26-Nov-15 02-Jun-16 27-May-15 27-Oct-15
ZB4EEMS560 Black Seamless Schedule 40 Material Submittal 10 18-Jan-16 01-Feb-16 27-May-15 09-Jun-15
ZB4EEMS580 Electrical Fire Pump Material Submittal 15 26-Nov-15 16-Dec-15 27-May-15 16-Jun-15
ZB4EEMS590 Diesel Fire Pump Material Submittal 15 26-Nov-15 16-Dec-15 27-May-15 16-Jun-15
ZB4EEMS600 Jockey Pump Material Submittal 15 26-Nov-15 16-Dec-15 27-May-15 16-Jun-15
ZB4EEMS570 VALVES Material Submittal 10 11-Apr-16 24-Apr-16 22-Jun-15 05-Jul-15
ZB4EEMS610 Water Flow Switches Material Submittal 18 01-Mar-16 24-Mar-16 22-Jun-15 15-Jul-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
2015 2016 2017
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings_1 18-Feb-16 09:32
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 32 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish BL Project
Start
BL Project
Finish
ZB4EEMS620 Upright Sprinkler Heads Material Submittal 18 21-Mar-16 13-Apr-16 08-Jul-15 04-Aug-15
ZB4EEMS640 Fire Hose Stations Material Submittal 22 15-Mar-16 13-Apr-16 02-Aug-15 31-Aug-15
ZB4EEMS650 Dry Powder Manual Fire Extinguishers Material Submittal 22 22-Mar-16 20-Apr-16 23-Aug-15 21-Sep-15
ZB4EEMS670 Roof Manifold Material Submittal 22 31-Mar-16 04-May-16 23-Aug-15 21-Sep-15
ZB4EEMS630 CO2 System Material Submittal 12 10-May-16 25-May-16 11-Oct-15 27-Oct-15
ZB4EEMS660 Automatic Dry Powder Fire Extinguishers Material Submittal 12 18-May-16 02-Jun-16 11-Oct-15 27-Oct-15
Material ApproMaterial Approvals 150 17-Dec-15 09-Jun-16 10-Jun-15 03-Nov-15
ZB4EEMA560 Black Seamless Schedule 40 Material Approval 5 02-Feb-16 08-Feb-16 10-Jun-15 16-Jun-15
ZB4EEMA580 Electrical Fire Pump Material Approval 5 17-Dec-15 24-Dec-15 17-Jun-15 23-Jun-15
ZB4EEMA590 Diesel Fire Pump Material Approval 5 17-Dec-15 24-Dec-15 17-Jun-15 23-Jun-15
ZB4EEMA600 Jockey Pump Material Approval 5 17-Dec-15 24-Dec-15 17-Jun-15 23-Jun-15
ZB4EEMA570 VALVES Material Approval 5 26-Apr-16 04-May-16 06-Jul-15 12-Jul-15
ZB4EEMA610 Water Flow Switches Material Approval 5 27-Mar-16 31-Mar-16 19-Jul-15 26-Jul-15
ZB4EEMA620 Upright Sprinkler Heads Material Approval 5 14-Apr-16 20-Apr-16 05-Aug-15 11-Aug-15
ZB4EEMA640 Fire Hose Stations Material Approval 5 14-Apr-16 20-Apr-16 01-Sep-15 07-Sep-15
ZB4EEMA650 Dry Powder Manual Fire Extinguishers Material Approval 5 03-May-16 09-May-16 22-Sep-15 30-Sep-15
ZB4EEMA670 Roof Manifold Material Approval 5 05-May-16 11-May-16 22-Sep-15 30-Sep-15
ZB4EEMA630 CO2 System Material Approval 5 26-May-16 01-Jun-16 28-Oct-15 03-Nov-15
ZB4EEMA660 Automatic Dry Powder Fire Extinguishers Material Approval 5 05-Jun-16 09-Jun-16 28-Oct-15 03-Nov-15
Material PO'sMaterial PO's 157 09-Feb-16 23-Jun-16 17-Jun-15 17-Nov-15
ZB4EEMP560 Black Seamless Schedule 40 Material PO 10 09-Feb-16 22-Feb-16 17-Jun-15 30-Jun-15
ZB4EEMP580 Electrical Fire Pump Material PO 10 09-Feb-16 22-Feb-16 24-Jun-15 07-Jul-15
ZB4EEMP590 Diesel Fire Pump Material PO 10 09-Feb-16 22-Feb-16 24-Jun-15 07-Jul-15
ZB4EEMP600 Jockey Pump Material PO 10 09-Feb-16 22-Feb-16 24-Jun-15 07-Jul-15
ZB4EEMP570 VALVES Material PO 10 05-May-16 18-May-16 13-Jul-15 28-Jul-15
ZB4EEMP610 Water Flow Switches Material PO 10 03-Apr-16 14-Apr-16 27-Jul-15 09-Aug-15
ZB4EEMP620 Upright Sprinkler Heads Material PO 10 21-Apr-16 09-May-16 12-Aug-15 25-Aug-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
2015 2016 2017
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings_1 18-Feb-16 09:32
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 33 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016

More Related Content

Similar to Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016

12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...
12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...
12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...Rodger McKinley
 
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule finalSeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule finalAhmed Mehrem
 
ADIB Time Schedule V4.0
ADIB Time Schedule V4.0ADIB Time Schedule V4.0
ADIB Time Schedule V4.0Ahmed Khaled
 
ICOM Schedule & Logistics (1)
ICOM Schedule & Logistics (1)ICOM Schedule & Logistics (1)
ICOM Schedule & Logistics (1)Jamal Nelson, CCM
 
CICPA Updated Schedule Dtd 130816
CICPA Updated Schedule Dtd 130816CICPA Updated Schedule Dtd 130816
CICPA Updated Schedule Dtd 130816Manish Shah
 
Equipment Arrival Status.pptx
Equipment Arrival Status.pptxEquipment Arrival Status.pptx
Equipment Arrival Status.pptxMehmanNasibov1
 
OHL1.pdf ejehejeur iurrrj iiuj4j4i4 jrj4
OHL1.pdf ejehejeur iurrrj iiuj4j4i4 jrj4OHL1.pdf ejehejeur iurrrj iiuj4j4i4 jrj4
OHL1.pdf ejehejeur iurrrj iiuj4j4i4 jrj4AhmedSaidGhonemy
 
Activities - Presentation (NESPAK) v1.6
Activities - Presentation (NESPAK) v1.6Activities - Presentation (NESPAK) v1.6
Activities - Presentation (NESPAK) v1.6MUHAMMAD SALEEM
 
Torkham Project Work Plan (18-Apr-2019).pdf
Torkham Project Work Plan (18-Apr-2019).pdfTorkham Project Work Plan (18-Apr-2019).pdf
Torkham Project Work Plan (18-Apr-2019).pdfSajidMumtazGurmani
 
MONTHLY REPORT_MARITIM PRIMA 1
MONTHLY REPORT_MARITIM PRIMA 1MONTHLY REPORT_MARITIM PRIMA 1
MONTHLY REPORT_MARITIM PRIMA 1Eko Untung
 
Sample Project Monitoring-EVM Analysis
Sample Project Monitoring-EVM Analysis Sample Project Monitoring-EVM Analysis
Sample Project Monitoring-EVM Analysis Ayon Pal
 
Project Monitoring with EVM Analysis
Project Monitoring with EVM Analysis Project Monitoring with EVM Analysis
Project Monitoring with EVM Analysis ayonpal
 

Similar to Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016 (20)

12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...
12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...
12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...
 
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule finalSeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
 
ARB JANADREA 25.01.16 UPDATE PM
ARB JANADREA 25.01.16 UPDATE  PMARB JANADREA 25.01.16 UPDATE  PM
ARB JANADREA 25.01.16 UPDATE PM
 
ADIB Time Schedule V4.0
ADIB Time Schedule V4.0ADIB Time Schedule V4.0
ADIB Time Schedule V4.0
 
ICOM Schedule & Logistics (1)
ICOM Schedule & Logistics (1)ICOM Schedule & Logistics (1)
ICOM Schedule & Logistics (1)
 
Leyet Colleges Schedule
Leyet Colleges ScheduleLeyet Colleges Schedule
Leyet Colleges Schedule
 
CICPA Updated Schedule Dtd 130816
CICPA Updated Schedule Dtd 130816CICPA Updated Schedule Dtd 130816
CICPA Updated Schedule Dtd 130816
 
2 l 65z
2 l 65z2 l 65z
2 l 65z
 
Weekly report no 19
Weekly report no 19Weekly report no 19
Weekly report no 19
 
Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13
 
Equipment Arrival Status.pptx
Equipment Arrival Status.pptxEquipment Arrival Status.pptx
Equipment Arrival Status.pptx
 
Project Schedule - Level IV Schedule
Project Schedule - Level IV ScheduleProject Schedule - Level IV Schedule
Project Schedule - Level IV Schedule
 
OHL1.pdf ejehejeur iurrrj iiuj4j4i4 jrj4
OHL1.pdf ejehejeur iurrrj iiuj4j4i4 jrj4OHL1.pdf ejehejeur iurrrj iiuj4j4i4 jrj4
OHL1.pdf ejehejeur iurrrj iiuj4j4i4 jrj4
 
Activities - Presentation (NESPAK) v1.6
Activities - Presentation (NESPAK) v1.6Activities - Presentation (NESPAK) v1.6
Activities - Presentation (NESPAK) v1.6
 
Torkham Project Work Plan (18-Apr-2019).pdf
Torkham Project Work Plan (18-Apr-2019).pdfTorkham Project Work Plan (18-Apr-2019).pdf
Torkham Project Work Plan (18-Apr-2019).pdf
 
MONTHLY REPORT_MARITIM PRIMA 1
MONTHLY REPORT_MARITIM PRIMA 1MONTHLY REPORT_MARITIM PRIMA 1
MONTHLY REPORT_MARITIM PRIMA 1
 
10. Overall Implementation Programme
10. Overall Implementation Programme10. Overall Implementation Programme
10. Overall Implementation Programme
 
ScheduleRev- 6
ScheduleRev- 6ScheduleRev- 6
ScheduleRev- 6
 
Sample Project Monitoring-EVM Analysis
Sample Project Monitoring-EVM Analysis Sample Project Monitoring-EVM Analysis
Sample Project Monitoring-EVM Analysis
 
Project Monitoring with EVM Analysis
Project Monitoring with EVM Analysis Project Monitoring with EVM Analysis
Project Monitoring with EVM Analysis
 

More from Ahmed Mehrem

020614_letter for Ahmed Mehrem Recommendation letter.pdf
020614_letter for Ahmed Mehrem Recommendation letter.pdf020614_letter for Ahmed Mehrem Recommendation letter.pdf
020614_letter for Ahmed Mehrem Recommendation letter.pdfAhmed Mehrem
 
Al aziza jotun products and services 2019 qr
Al aziza jotun products and services 2019 qrAl aziza jotun products and services 2019 qr
Al aziza jotun products and services 2019 qrAhmed Mehrem
 
Al-Aziza for paints and decoration Ahmed Mehrem business card 2
Al-Aziza for paints and decoration Ahmed Mehrem business card 2Al-Aziza for paints and decoration Ahmed Mehrem business card 2
Al-Aziza for paints and decoration Ahmed Mehrem business card 2Ahmed Mehrem
 
Al-Aziza For Paints Ahmed Mehrem business card
Al-Aziza For Paints Ahmed Mehrem business card Al-Aziza For Paints Ahmed Mehrem business card
Al-Aziza For Paints Ahmed Mehrem business card Ahmed Mehrem
 
Mtwara power plant 2007
Mtwara power plant 2007Mtwara power plant 2007
Mtwara power plant 2007Ahmed Mehrem
 
Admin Building For Sphinx Glass Factory In Sadat
Admin Building For Sphinx Glass Factory In SadatAdmin Building For Sphinx Glass Factory In Sadat
Admin Building For Sphinx Glass Factory In SadatAhmed Mehrem
 
Sphinx Glass Factory comp 1-1
Sphinx Glass Factory comp 1-1Sphinx Glass Factory comp 1-1
Sphinx Glass Factory comp 1-1Ahmed Mehrem
 

More from Ahmed Mehrem (10)

020614_letter for Ahmed Mehrem Recommendation letter.pdf
020614_letter for Ahmed Mehrem Recommendation letter.pdf020614_letter for Ahmed Mehrem Recommendation letter.pdf
020614_letter for Ahmed Mehrem Recommendation letter.pdf
 
Al aziza jotun products and services 2019 qr
Al aziza jotun products and services 2019 qrAl aziza jotun products and services 2019 qr
Al aziza jotun products and services 2019 qr
 
Al-Aziza for paints and decoration Ahmed Mehrem business card 2
Al-Aziza for paints and decoration Ahmed Mehrem business card 2Al-Aziza for paints and decoration Ahmed Mehrem business card 2
Al-Aziza for paints and decoration Ahmed Mehrem business card 2
 
Al-Aziza For Paints Ahmed Mehrem business card
Al-Aziza For Paints Ahmed Mehrem business card Al-Aziza For Paints Ahmed Mehrem business card
Al-Aziza For Paints Ahmed Mehrem business card
 
For Our Mothers
For Our MothersFor Our Mothers
For Our Mothers
 
Majarrah data
Majarrah dataMajarrah data
Majarrah data
 
001
001001
001
 
Mtwara power plant 2007
Mtwara power plant 2007Mtwara power plant 2007
Mtwara power plant 2007
 
Admin Building For Sphinx Glass Factory In Sadat
Admin Building For Sphinx Glass Factory In SadatAdmin Building For Sphinx Glass Factory In Sadat
Admin Building For Sphinx Glass Factory In Sadat
 
Sphinx Glass Factory comp 1-1
Sphinx Glass Factory comp 1-1Sphinx Glass Factory comp 1-1
Sphinx Glass Factory comp 1-1
 

Recently uploaded

Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 

Recently uploaded (20)

Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 

Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016

  • 1. Activity ID Activity Name Original Duration Start Finish BL Project Start BL Project Finish Zewail City of SciZewail City of Science and Technology B4 Contract 582 02-May-15 17-Nov-16 02-May-15 14-Apr-16 GeneralGeneral 582 02-May-15 17-Nov-16 02-May-15 14-Apr-16 ZB4G0010 Letter of Intent 0 02-May-15 02-May-15 ZB4G0020 Receive Final Design Drawings and Specifications 0 26-Oct-15 03-May-15 ZB4G0030 Down Payment 0 10-Feb-16 24-May-15 ZB4G0040 Letter of Award 0 16-Feb-16 24-May-15 ZB4G0060 Full Release Service Tunnel For MEP Works 0 05-Jul-15 06-Jun-15 ZB4G0062 Release Building B4-A For MEP Work ( Masonry Works ) 0 14-Jun-15 14-Jun-15 ZB4G0064 Release Building B4-B For MEPWork ( Masonry Works ) 0 16-Jul-15 14-Jun-15 ZB4G0050 Mobilization 15 17-Feb-16 05-Mar-16 30-May-15 15-Jun-15 ZB4G0066 Release Building B4-D For MEPWork ( Masonry Works ) 0 03-Sep-15 01-Jul-15 ZB4G0068 Release Building B4-E For MEPWork ( Masonry Works ) 0 27-Aug-15 01-Jul-15 ZB4G0070 Provide Permanent Electrical / Gas / Water / Drainage Sources 0 03-Sep-16 15-Aug-15 ZB4G0076 Release Building B4-D Finishing Work ( For Equipment Installation ) 0 05-May-16 18-Aug-15 ZB4G0074 Release Building B4-B Finishing Work ( For Equipment Installation ) 0 23-Mar-16 01-Sep-15 ZB4G0072 Release Building B4-A Finishing Work ( For Equipment Installation ) 0 03-Nov-15 05-Sep-15 ZB4G0078 Release Building B4-E Finishing Work ( For Equipment Installation ) 0 26-Apr-16 05-Sep-15 ZB4G0088 Release Site Layout For MEPWork ( MV, LV and SCADA Networks Works ) 0 09-Feb-16 04-Nov-15 ZB4G0098 Release Site Layout For MEPWork ( Solar LED Exterior Lighting Works ) 0 04-Jun-16 28-Feb-16 ZB4G0090 Project Hand Over 0 17-Nov-16 14-Apr-16 ZB4G0080 Project Testing & Commissioning 60 03-Sep-16 17-Nov-16 06-Feb-16 14-Apr-16 EngineeringEngineering 261 26-Oct-15 03-Nov-16 03-May-15 10-Jan-16 Building B4 - A (MBuilding B4 - A (Mechanical Utilities) 177 26-Oct-15 18-Aug-16 03-May-15 21-Oct-15 ZB4G000010 Basic Engineering Study 18 26-Oct-15 18-Nov-15 03-May-15 26-May-15 Basement FloorBasement Floor 90 19-Nov-15 11-May-16 27-May-15 20-Aug-15 Electrical SystemElectrical Systems 90 22-Dec-15 11-May-16 27-May-15 20-Aug-15 Power SystemPower System 15 11-Jan-16 18-Feb-16 01-Jul-15 14-Jul-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2015 2016 2017 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings_1 18-Feb-16 09:32 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 1 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 2. Activity ID Activity Name Original Duration Start Finish BL Project Start BL Project Finish ZB4AEBEPS10 BASEMENT FLOOR POWER SYSTEM LAYOUT PLAN SUBMITTAL 5 11-Jan-16 17-Jan-16 01-Jul-15 07-Jul-15 ZB4AEBEPA10 BASEMENT FLOOR POWER SYSTEM LAYOUT PLAN APPROVAL 5 14-Feb-16 18-Feb-16 08-Jul-15 14-Jul-15 Lighting SystemLighting System 15 27-Dec-15 18-Feb-16 27-May-15 09-Jun-15 ZB4AEBELS10 BASEMENT FLOOR LIGHTING SYSTEM LAYOUT PLAN SUBMITTAL 5 27-Dec-15 31-Dec-15 27-May-15 02-Jun-15 ZB4AEBELA10 BASEMENT FLOOR LIGHTING SYSTEM LAYOUT PLAN APPROVAL 5 14-Feb-16 18-Feb-16 03-Jun-15 09-Jun-15 Cable Tray SysCable Tray System 15 27-Dec-15 18-Feb-16 01-Jul-15 14-Jul-15 ZB4AEBECS10 BASEMENT FLOOR CABLE TRAY SYSTEM LAYOUT PLAN SUBMITTAL 5 27-Dec-15 31-Dec-15 01-Jul-15 07-Jul-15 ZB4AEBECA10 BASEMENT FLOOR CABLE TRAY SYSTEM LAYOUT PLAN APPROVAL 5 14-Feb-16 18-Feb-16 08-Jul-15 14-Jul-15 Earthing SysteEarthing System 15 03-Jan-16 18-Feb-16 08-Jul-15 22-Jul-15 ZB4AEBEES10 BASEMENT FLOOR EARTHING SYSTEM LAYOUT PLAN SUBMITTAL 5 03-Jan-16 10-Jan-16 08-Jul-15 14-Jul-15 ZB4AEBEEA10 BASEMENT FLOOR EARTHING SYSTEM LAYOUT PLAN APPROVAL 5 14-Feb-16 18-Feb-16 15-Jul-15 22-Jul-15 Light Current SLight Current Systems 24 22-Dec-15 18-Feb-16 27-May-15 17-Jun-15 Fire Alarm SyFire Alarm System 15 22-Dec-15 18-Feb-16 27-May-15 09-Jun-15 ZB4AEBELFS10 BASEMENT FLOOR FIRE ALARM SYSTEM LAYOUT PLAN SUBMITTAL 5 22-Dec-15 29-Dec-15 27-May-15 02-Jun-15 ZB4AEBELFA10BASEMENT FLOOR FIRE ALARM SYSTEM LAYOUT PLAN APPROVAL 5 14-Feb-16 18-Feb-16 03-Jun-15 09-Jun-15 Security SystSecurity Systems 15 03-Jan-16 18-Feb-16 01-Jun-15 14-Jun-15 ZB4AEBELSS10 BASEMENT FLOOR SECURITY SYSTEMS LAYOUT PLAN SUBMITTAL 5 03-Jan-16 10-Jan-16 01-Jun-15 07-Jun-15 ZB4AEBELSA10BASEMENT FLOOR SECURITY SYSTEMS LAYOUT PLAN APPROVAL 5 14-Feb-16 18-Feb-16 08-Jun-15 14-Jun-15 CommunicatiCommunication Systems 15 07-Feb-16 18-Feb-16 04-Jun-15 17-Jun-15 ZB4AEBELCS10BASEMENT FLOOR COMMUNICATION SYSTEMS LAYOUT PLAN SUBMITTAL 5 07-Feb-16 11-Feb-16 04-Jun-15 10-Jun-15 ZB4AEBELCA10BASEMENT FLOOR COMMUNICATION SYSTEMS LAYOUT PLAN APPROVAL 5 14-Feb-16 18-Feb-16 11-Jun-15 17-Jun-15 SCADA SystemSCADA System 14 07-Mar-16 11-May-16 09-Aug-15 20-Aug-15 ZB4AEBEDS10 BASEMENT FLOOR SCADA SYSTEM LAYOUT PLAN SUBMITTAL 5 07-Mar-16 13-Mar-16 09-Aug-15 13-Aug-15 ZB4AEBEDA10 BASEMENT FLOOR SCADA SYSTEM LAYOUT PLAN APPROVAL 5 05-May-16 11-May-16 16-Aug-15 20-Aug-15 Mechanical SystMechanical Systems 30 19-Nov-15 03-Mar-16 27-May-15 23-Jun-15 HVAC SystemHVAC System 30 19-Nov-15 03-Mar-16 27-May-15 23-Jun-15 ZB4AEBMHS10 BASEMENT FLOOR HVAC SYSTEM LAYOUT PLAN SUBMITTAL 15 19-Nov-15 09-Dec-15 27-May-15 16-Jun-15 ZB4AEBMHS20 BASEMENT FLOOR HVAC SECTIONS LAYOUT PLAN SUBMITTAL 15 03-Dec-15 24-Dec-15 27-May-15 16-Jun-15 ZB4AEBMHA10 BASEMENT FLOOR HVAC SYSTEM LAYOUT PLAN APPROVAL 5 14-Feb-16 18-Feb-16 17-Jun-15 23-Jun-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2015 2016 2017 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings_1 18-Feb-16 09:32 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 2 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 3. Activity ID Activity Name Original Duration Start Finish BL Project Start BL Project Finish ZB4AEBMHA20 BASEMENT FLOOR HVAC SYSTEM LAYOUT PLAN APPROVAL 5 28-Feb-16 03-Mar-16 17-Jun-15 23-Jun-15 Fire ProtectionFire Protection Systems 22 18-Jan-16 18-Feb-16 27-May-15 16-Jun-15 ZB4AEBMFS10 BASEMENT FLOOR FIRE PROTECTION SYSTEM LAYOUT PLAN SUBMITTAL 10 18-Jan-16 01-Feb-16 27-May-15 09-Jun-15 ZB4AEBMFA10 BASEMENT FLOOR FIRE PROTECTION SYSTEM LAYOUT PLAN APPROVAL 5 14-Feb-16 18-Feb-16 10-Jun-15 16-Jun-15 Plumbing SystPlumbing System 30 27-Dec-15 03-Mar-16 27-May-15 23-Jun-15 ZB4AEBMWS10 BASEMENT FLOOR WATER SUPPLY SYSTEM LAYOUT PLAN SUBMITTAL 5 02-Feb-16 08-Feb-16 27-May-15 02-Jun-15 ZB4AEBMDS10 BASEMENT FLOOR DRAINAGE SYSTEM LAYOUT PLAN SUBMITTAL 5 27-Dec-15 31-Dec-15 27-May-15 02-Jun-15 ZB4AEBMWA10 BASEMENT FLOOR WATER SUPPLY SYSTEM LAYOUT PLAN APPROVAL 5 14-Feb-16 18-Feb-16 03-Jun-15 09-Jun-15 ZB4AEBMDA10 BASEMENT FLOOR DRAINAGE SYSTEM LAYOUT PLAN APPROVAL 5 14-Feb-16 18-Feb-16 03-Jun-15 09-Jun-15 ZB4AEBMWS20 WATER SUPPLY PUMP ROOM DETAILS & SECTIONS SUBMITTAL 15 07-Feb-16 25-Feb-16 27-May-15 16-Jun-15 ZB4AEBMWA20 WATER SUPPLY PUMP ROOM DETAILS & SECTIONS APPROVAL 5 28-Feb-16 03-Mar-16 17-Jun-15 23-Jun-15 Composite DrawComposite Drawing 14 21-Feb-16 03-Mar-16 26-Jul-15 06-Aug-15 ZB4AEBCS10 BASEMENT FLOOR COMPOSITE LAYOUT PLAN SUBMITTAL 5 21-Feb-16 25-Feb-16 26-Jul-15 30-Jul-15 ZB4AEBCA10 BASEMENT FLOOR COMPOSITE LAYOUT PLAN APPROVAL 5 28-Feb-16 03-Mar-16 02-Aug-15 06-Aug-15 Ground FloorGround Floor 90 10-Dec-15 18-Aug-16 03-Jun-15 27-Aug-15 ZB4AEGGBS10 Ground Floor Builder Work Submittal 5 31-Mar-16 06-Apr-16 02-Aug-15 06-Aug-15 ZB4AEGGBA10 Ground Floor Builder Work Approval 5 07-Apr-16 13-Apr-16 09-Aug-15 13-Aug-15 Electrical SystemElectrical Systems 90 30-Dec-15 11-May-16 03-Jun-15 27-Aug-15 Power SystemPower System 15 18-Jan-16 28-Feb-16 08-Jul-15 22-Jul-15 ZB4AEGEPS10 GROUND FLOOR POWER SYSTEM LAYOUT PLAN SUBMITTAL 5 18-Jan-16 24-Jan-16 08-Jul-15 14-Jul-15 ZB4AEGEPA10 GROUND FLOOR POWER SYSTEM LAYOUT PLAN APPROVAL 5 22-Feb-16 28-Feb-16 15-Jul-15 22-Jul-15 Lighting SystemLighting System 15 03-Jan-16 07-Mar-16 03-Jun-15 16-Jun-15 ZB4AEGELS10 GROUND FLOOR LIGHTING SYSTEM LAYOUT PLAN SUBMITTAL 5 03-Jan-16 10-Jan-16 03-Jun-15 09-Jun-15 ZB4AEGELA10 GROUND FLOOR LIGHTING SYSTEM LAYOUT PLAN APPROVAL 5 01-Mar-16 07-Mar-16 10-Jun-15 16-Jun-15 Cable Tray SysCable Tray System 15 05-Jan-16 07-Mar-16 08-Jul-15 22-Jul-15 ZB4AEGECS10 GROUND FLOOR CABLE TRAY SYSTEM LAYOUT PLAN SUBMITTAL 5 05-Jan-16 12-Jan-16 08-Jul-15 14-Jul-15 ZB4AEGECA10 GROUND FLOOR CABLE TRAY SYSTEM LAYOUT PLAN APPROVAL 5 01-Mar-16 07-Mar-16 15-Jul-15 22-Jul-15 Earthing SysteEarthing System 15 11-Jan-16 07-Mar-16 15-Jul-15 30-Jul-15 ZB4AEGEES10 GROUND FLOOR EARTHING SYSTEM LAYOUT PLAN SUBMITTAL 5 11-Jan-16 17-Jan-16 15-Jul-15 22-Jul-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2015 2016 2017 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings_1 18-Feb-16 09:32 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 3 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 4. Activity ID Activity Name Original Duration Start Finish BL Project Start BL Project Finish ZB4AEGEEA10 GROUND FLOOR EARTHING SYSTEM LAYOUT PLAN APPROVAL 5 01-Mar-16 07-Mar-16 26-Jul-15 30-Jul-15 Light Current SLight Current Systems 24 30-Dec-15 07-Mar-16 03-Jun-15 24-Jun-15 Fire Alarm SyFire Alarm System 15 30-Dec-15 07-Mar-16 03-Jun-15 16-Jun-15 ZB4AEGELFS10GROUND FLOOR FIRE ALARM SYSTEM LAYOUT PLAN SUBMITTAL 5 30-Dec-15 05-Jan-16 03-Jun-15 09-Jun-15 ZB4AEGELFA10GROUND FLOOR FIRE ALARM SYSTEM LAYOUT PLAN APPROVAL 5 01-Mar-16 07-Mar-16 10-Jun-15 16-Jun-15 Security SystSecurity Systems 15 11-Jan-16 07-Mar-16 08-Jun-15 21-Jun-15 ZB4AEGELSS10 GROUND FLOOR SECURITY SYSTEMS LAYOUT PLAN SUBMITTAL 5 11-Jan-16 17-Jan-16 08-Jun-15 14-Jun-15 ZB4AEGELSA10GROUND FLOOR SECURITY SYSTEMS LAYOUT PLAN APPROVAL 5 01-Mar-16 07-Mar-16 15-Jun-15 21-Jun-15 CommunicatiCommunication Systems 15 23-Feb-16 07-Mar-16 11-Jun-15 24-Jun-15 ZB4AEGELCS10GROUND FLOOR COMMUNICATION SYSTEMS LAYOUT PLAN SUBMITTAL 5 23-Feb-16 29-Feb-16 11-Jun-15 17-Jun-15 ZB4AEGELCA10GROUND FLOOR COMMUNICATION SYSTEMS LAYOUT PLAN APPROVAL 5 01-Mar-16 07-Mar-16 18-Jun-15 24-Jun-15 SCADA SystemSCADA System 14 14-Mar-16 11-May-16 16-Aug-15 27-Aug-15 ZB4AEGEDS10 GROUND FLOOR SCADA SYSTEM LAYOUT PLAN SUBMITTAL 5 14-Mar-16 20-Mar-16 16-Aug-15 20-Aug-15 ZB4AEGEDA10 GROUND FLOOR SCADA SYSTEM LAYOUT PLAN APPROVAL 5 05-May-16 11-May-16 23-Aug-15 27-Aug-15 Mechanical SystMechanical Systems 45 10-Dec-15 18-Aug-16 03-Jun-15 14-Jul-15 HVAC SystemHVAC System 30 10-Dec-15 14-Jun-16 17-Jun-15 14-Jul-15 ZB4AEGMHS10 GROUND FLOOR HVAC SYSTEM LAYOUT PLAN SUBMITTAL 15 10-Dec-15 31-Dec-15 17-Jun-15 07-Jul-15 ZB4AEGMHS20 GROUND FLOOR HVAC SECTIONS LAYOUT PLAN SUBMITTAL 15 27-Dec-15 17-Jan-16 17-Jun-15 07-Jul-15 ZB4AEGMHA10 GROUND FLOOR HVAC SYSTEM LAYOUT PLAN APPROVAL 5 01-Mar-16 07-Mar-16 08-Jul-15 14-Jul-15 ZB4AEGMHA20 GROUND FLOOR HVAC SYSTEM LAYOUT PLAN APPROVAL 5 08-Jun-16 14-Jun-16 08-Jul-15 14-Jul-15 Fire ProtectionFire Protection Systems 22 02-Feb-16 18-Aug-16 10-Jun-15 30-Jun-15 ZB4AEGMFS10 GROUND FLOOR FIRE PROTECTION SYSTEM LAYOUT PLAN SUBMITTAL 5 02-Feb-16 08-Feb-16 10-Jun-15 16-Jun-15 ZB4AEGMFA10 GROUND FLOOR FIRE PROTECTION SYSTEM LAYOUT PLAN APPROVAL 5 23-Feb-16 29-Feb-16 17-Jun-15 23-Jun-15 ZB4AEGMFS20 FIRE PROTECTION WORK - SPECIAL SYSTEM DETAILS SUBMITTAL 5 07-Aug-16 11-Aug-16 17-Jun-15 23-Jun-15 ZB4AEGMFA20 FIRE PROTECTION WORK - SPECIAL SYSTEM DETAILS APPROVAL 5 14-Aug-16 18-Aug-16 24-Jun-15 30-Jun-15 Plumbing SystPlumbing System 15 03-Jan-16 07-Mar-16 03-Jun-15 16-Jun-15 ZB4AEGMWS10 GROUND FLOOR WATER SUPPLY SYSTEM LAYOUT PLAN SUBMITTAL 5 09-Feb-16 15-Feb-16 03-Jun-15 09-Jun-15 ZB4AEGMDS10 GROUND FLOOR DRAINAGE SYSTEM LAYOUT PLAN SUBMITTAL 5 03-Jan-16 10-Jan-16 03-Jun-15 09-Jun-15 ZB4AEGMWA10 GROUND FLOOR WATER SUPPLY SYSTEM LAYOUT PLAN APPROVAL 5 01-Mar-16 07-Mar-16 10-Jun-15 16-Jun-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2015 2016 2017 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings_1 18-Feb-16 09:32 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 4 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 5. Activity ID Activity Name Original Duration Start Finish BL Project Start BL Project Finish ZB4AEGMDA10 GROUND FLOOR DRAINAGE SYSTEM LAYOUT PLAN APPROVAL 5 01-Mar-16 07-Mar-16 10-Jun-15 16-Jun-15 Composite DrawComposite Drawing 14 08-Mar-16 21-Mar-16 02-Aug-15 13-Aug-15 ZB4AEGCS10 GROUND FLOOR COMPOSITE LAYOUT PLAN SUBMITTAL 5 08-Mar-16 14-Mar-16 02-Aug-15 06-Aug-15 ZB4AEGCA10 GROUND FLOOR COMPOSITE LAYOUT PLAN APPROVAL 5 15-Mar-16 21-Mar-16 09-Aug-15 13-Aug-15 Roof 1Roof 1 90 03-Jan-16 11-May-16 10-Jun-15 03-Sep-15 ZB4AERGBS10 Roof 1 Builder Work Submittal 5 31-Mar-16 06-Apr-16 09-Aug-15 13-Aug-15 ZB4AERGBA10 Roof 1 Builder Work Approval 5 07-Apr-16 13-Apr-16 16-Aug-15 20-Aug-15 Electrical SystemElectrical Systems 90 06-Jan-16 11-May-16 10-Jun-15 03-Sep-15 Power SystemPower System 7 26-Jan-16 28-Feb-16 15-Jul-15 22-Jul-15 ZB4AEREPS10 ROOF 1 FLOOR POWER SYSTEM LAYOUT PLAN SUBMITTAL 5 26-Jan-16 01-Feb-16 15-Jul-15 22-Jul-15 ZB4AEREPA10 ROOF 1 FLOOR POWER SYSTEM LAYOUT PLAN APPROVAL 5 22-Feb-16 28-Feb-16 15-Jul-15 22-Jul-15 Lighting SystemLighting System 15 11-Jan-16 07-Mar-16 10-Jun-15 23-Jun-15 ZB4AERELS10 ROOF 1 FLOOR LIGHTING SYSTEM LAYOUT PLAN SUBMITTAL 5 11-Jan-16 17-Jan-16 10-Jun-15 16-Jun-15 ZB4AERELA10 ROOF 1 FLOOR LIGHTING SYSTEM LAYOUT PLAN APPROVAL 5 01-Mar-16 07-Mar-16 17-Jun-15 23-Jun-15 Cable Tray SysCable Tray System 15 13-Jan-16 07-Mar-16 15-Jul-15 30-Jul-15 ZB4AERECS10 ROOF 1 FLOOR CABLE TRAY SYSTEM LAYOUT PLAN SUBMITTAL 5 13-Jan-16 19-Jan-16 15-Jul-15 22-Jul-15 ZB4AERECA10 ROOF 1 FLOOR CABLE TRAY SYSTEM LAYOUT PLAN APPROVAL 5 01-Mar-16 07-Mar-16 26-Jul-15 30-Jul-15 Lightning SystLightning System 14 18-Jan-16 07-Mar-16 26-Jul-15 06-Aug-15 ZB4AEREHS10 ROOF 1 FLOOR LIGHTNING SYSTEM LAYOUT PLAN SUBMITTAL 5 18-Jan-16 24-Jan-16 26-Jul-15 30-Jul-15 ZB4AEREHA10 ROOF 1 FLOOR LIGHTNING SYSTEM LAYOUT PLAN APPROVAL 5 01-Mar-16 07-Mar-16 02-Aug-15 06-Aug-15 Light Current SLight Current Systems 20 06-Jan-16 07-Mar-16 10-Jun-15 28-Jun-15 Fire Alarm SyFire Alarm System 15 06-Jan-16 07-Mar-16 10-Jun-15 23-Jun-15 ZB4AERELFS10ROOF 1 FLOOR FIRE ALARM SYSTEM LAYOUT PLAN SUBMITTAL 5 06-Jan-16 13-Jan-16 10-Jun-15 16-Jun-15 ZB4AERELFA10ROOF 1 FLOOR FIRE ALARM SYSTEM LAYOUT PLAN APPROVAL 5 01-Mar-16 07-Mar-16 17-Jun-15 23-Jun-15 Security SystSecurity Systems 15 18-Jan-16 07-Mar-16 15-Jun-15 28-Jun-15 ZB4AERELSS10 ROOF 1 FLOOR SECURITY SYSTEMS LAYOUT PLAN SUBMITTAL 5 18-Jan-16 24-Jan-16 15-Jun-15 21-Jun-15 ZB4AERELSA10ROOF 1 FLOOR SECURITY SYSTEMS LAYOUT PLAN APPROVAL 5 01-Mar-16 07-Mar-16 22-Jun-15 28-Jun-15 SCADA SystemSCADA System 14 21-Mar-16 11-May-16 23-Aug-15 03-Sep-15 ZB4AEREDS10 ROOF 1 FLOOR SCADA SYSTEM LAYOUT PLAN SUBMITTAL 5 21-Mar-16 27-Mar-16 23-Aug-15 27-Aug-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2015 2016 2017 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings_1 18-Feb-16 09:32 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 5 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 6. Activity ID Activity Name Original Duration Start Finish BL Project Start BL Project Finish ZB4AEREDA10 ROOF 1 FLOOR SCADA SYSTEM LAYOUT PLAN APPROVAL 5 05-May-16 11-May-16 30-Aug-15 03-Sep-15 Mechanical SystMechanical Systems 60 03-Jan-16 07-Mar-16 10-Jun-15 06-Aug-15 HVAC SystemHVAC System 30 03-Jan-16 07-Mar-16 08-Jul-15 06-Aug-15 ZB4AERMHS10 ROOF 1 FLOOR HVAC SYSTEM LAYOUT PLAN SUBMITTAL 15 03-Jan-16 24-Jan-16 08-Jul-15 30-Jul-15 ZB4AERMHS20 ROOF 1 FLOOR HVAC SECTIONS LAYOUT PLAN SUBMITTAL 15 18-Jan-16 08-Feb-16 08-Jul-15 30-Jul-15 ZB4AERMHA10 ROOF 1 FLOOR HVAC SYSTEM LAYOUT PLAN APPROVAL 5 01-Mar-16 07-Mar-16 02-Aug-15 06-Aug-15 ZB4AERMHA20 ROOF 1 FLOOR HVAC SECTIONS LAYOUT PLAN APPROVAL 5 01-Mar-16 07-Mar-16 02-Aug-15 06-Aug-15 Fire ProtectionFire Protection Systems 15 09-Feb-16 29-Feb-16 17-Jun-15 30-Jun-15 ZB4AERMFS10 ROOF 1 FLOOR FIRE PROTECTION SYSTEM LAYOUT PLAN SUBMITTAL 5 09-Feb-16 15-Feb-16 17-Jun-15 23-Jun-15 ZB4AERMFA10 ROOF 1 FLOOR FIRE PROTECTION SYSTEM LAYOUT PLAN APPROVAL 5 23-Feb-16 29-Feb-16 24-Jun-15 30-Jun-15 Plumbing SystPlumbing System 15 11-Jan-16 07-Mar-16 10-Jun-15 23-Jun-15 ZB4AERMWS10 ROOF 1 FLOOR WATER SUPPLY SYSTEM LAYOUT PLAN SUBMITTAL 5 16-Feb-16 22-Feb-16 10-Jun-15 16-Jun-15 ZB4AERMDS10 ROOF 1 FLOOR DRAINAGE SYSTEM LAYOUT PLAN SUBMITTAL 5 11-Jan-16 17-Jan-16 10-Jun-15 16-Jun-15 ZB4AERMWA10 ROOF 1 FLOOR WATER SUPPLY SYSTEM LAYOUT PLAN APPROVAL 5 01-Mar-16 07-Mar-16 17-Jun-15 23-Jun-15 ZB4AERMDA10 ROOF 1 FLOOR DRAINAGE SYSTEM LAYOUT PLAN APPROVAL 5 01-Mar-16 07-Mar-16 17-Jun-15 23-Jun-15 Composite DrawComposite Drawing 14 08-Mar-16 21-Mar-16 09-Aug-15 20-Aug-15 ZB4AERCS10 ROOF 1 FLOOR COMPOSITE LAYOUT PLAN SUBMITTAL 5 08-Mar-16 14-Mar-16 09-Aug-15 13-Aug-15 ZB4AERCA10 ROOF 1 FLOOR COMPOSITE LAYOUT PLAN APPROVAL 5 15-Mar-16 21-Mar-16 16-Aug-15 20-Aug-15 Roof 2Roof 2 90 14-Jan-16 11-May-16 17-Jun-15 10-Sep-15 ZB4AEUGBS10 Roof 2 Builder Work Submittal 5 31-Mar-16 06-Apr-16 30-Aug-15 03-Sep-15 ZB4AEUGBA10 Roof 2 Builder Work Approval 5 07-Apr-16 13-Apr-16 06-Sep-15 10-Sep-15 Electrical SystemElectrical Systems 90 14-Jan-16 11-May-16 17-Jun-15 10-Sep-15 Power SystemPower System 15 26-Jan-16 28-Feb-16 15-Jul-15 30-Jul-15 ZB4AEUEPS10 ROOF 2 FLOOR POWER SYSTEM LAYOUT PLAN SUBMITTAL 5 26-Jan-16 01-Feb-16 15-Jul-15 22-Jul-15 ZB4AEUEPA10 ROOF 2 FLOOR POWER SYSTEM LAYOUT PLAN APPROVAL 5 22-Feb-16 28-Feb-16 26-Jul-15 30-Jul-15 Lighting SystemLighting System 15 18-Jan-16 07-Mar-16 17-Jun-15 30-Jun-15 ZB4AEUELS10 ROOF 2 FLOOR LIGHTING SYSTEM LAYOUT PLAN SUBMITTAL 5 18-Jan-16 24-Jan-16 17-Jun-15 23-Jun-15 ZB4AEUELA10 ROOF 2 FLOOR LIGHTING SYSTEM LAYOUT PLAN APPROVAL 5 01-Mar-16 07-Mar-16 24-Jun-15 30-Jun-15 Cable Tray SysCable Tray System 14 20-Jan-16 07-Mar-16 26-Jul-15 06-Aug-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2015 2016 2017 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings_1 18-Feb-16 09:32 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 6 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 7. Activity ID Activity Name Original Duration Start Finish BL Project Start BL Project Finish ZB4AEUECS10 ROOF 2 FLOOR CABLE TRAY SYSTEM LAYOUT PLAN SUBMITTAL 5 20-Jan-16 27-Jan-16 26-Jul-15 30-Jul-15 ZB4AEUECA10 ROOF 2 FLOOR CABLE TRAY SYSTEM LAYOUT PLAN APPROVAL 5 01-Mar-16 07-Mar-16 02-Aug-15 06-Aug-15 Lightning SystLightning System 14 26-Jan-16 07-Mar-16 02-Aug-15 13-Aug-15 ZB4AEUEHS10 ROOF 2 FLOOR LIGHTNING SYSTEM LAYOUT PLAN SUBMITTAL 5 26-Jan-16 01-Feb-16 02-Aug-15 06-Aug-15 ZB4AEUEHA10 ROOF 2 FLOOR LIGHTNING SYSTEM LAYOUT PLAN APPROVAL 5 01-Mar-16 07-Mar-16 09-Aug-15 13-Aug-15 Light Current SLight Current Systems 20 14-Jan-16 07-Mar-16 17-Jun-15 05-Jul-15 Fire Alarm SyFire Alarm System 15 14-Jan-16 07-Mar-16 17-Jun-15 30-Jun-15 ZB4AEUELFS10ROOF 2 FLOOR FIRE ALARM SYSTEM LAYOUT PLAN SUBMITTAL 5 14-Jan-16 20-Jan-16 17-Jun-15 23-Jun-15 ZB4AEUELFA10ROOF 2 FLOOR FIRE ALARM SYSTEM LAYOUT PLAN APPROVAL 5 01-Mar-16 07-Mar-16 24-Jun-15 30-Jun-15 Security SystSecurity Systems 15 26-Jan-16 07-Mar-16 22-Jun-15 05-Jul-15 ZB4AEUELSS10 ROOF 2 FLOOR SECURITY SYSTEMS LAYOUT PLAN SUBMITTAL 5 26-Jan-16 01-Feb-16 22-Jun-15 28-Jun-15 ZB4AEUELSA10ROOF 2 FLOOR SECURITY SYSTEMS LAYOUT PLAN APPROVAL 5 01-Mar-16 07-Mar-16 29-Jun-15 05-Jul-15 SCADA SystemSCADA System 14 28-Mar-16 11-May-16 30-Aug-15 10-Sep-15 ZB4AEUEDS10 ROOF 2 FLOOR SCADA SYSTEM LAYOUT PLAN SUBMITTAL 5 28-Mar-16 03-Apr-16 30-Aug-15 03-Sep-15 ZB4AEUEDA10 ROOF 2 FLOOR SCADA SYSTEM LAYOUT PLAN APPROVAL 5 05-May-16 11-May-16 06-Sep-15 10-Sep-15 Mechanical SystMechanical Systems 75 18-Jan-16 07-Mar-16 17-Jun-15 27-Aug-15 HVAC SystemHVAC System 29 26-Jan-16 07-Mar-16 02-Aug-15 27-Aug-15 ZB4AEUMHS10 ROOF 2 FLOOR HVAC SYSTEM LAYOUT PLAN SUBMITTAL 15 26-Jan-16 15-Feb-16 02-Aug-15 20-Aug-15 ZB4AEUMHS20 ROOF 2 FLOOR HVAC SECTIONS LAYOUT PLAN SUBMITTAL 15 09-Feb-16 29-Feb-16 02-Aug-15 20-Aug-15 ZB4AEUMHA10 ROOF 2 FLOOR HVAC SYSTEM LAYOUT PLAN APPROVAL 5 01-Mar-16 07-Mar-16 23-Aug-15 27-Aug-15 ZB4AEUMHA20 ROOF 2 FLOOR HVAC SECTIONS LAYOUT PLAN APPROVAL 5 01-Mar-16 07-Mar-16 23-Aug-15 27-Aug-15 Fire ProtectionFire Protection Systems 15 16-Feb-16 29-Feb-16 24-Jun-15 07-Jul-15 ZB4AEUMFS10 ROOF 2 FLOOR FIRE PROTECTION SYSTEM LAYOUT PLAN SUBMITTAL 5 16-Feb-16 22-Feb-16 24-Jun-15 30-Jun-15 ZB4AEUMFA10 ROOF 2 FLOOR FIRE PROTECTION SYSTEM LAYOUT PLAN APPROVAL 5 23-Feb-16 29-Feb-16 01-Jul-15 07-Jul-15 Plumbing SystPlumbing System 15 18-Jan-16 07-Mar-16 17-Jun-15 30-Jun-15 ZB4AEUMWS10 ROOF 2 FLOOR WATER SUPPLY SYSTEM LAYOUT PLAN SUBMITTAL 5 23-Feb-16 29-Feb-16 17-Jun-15 23-Jun-15 ZB4AEUMDS10 ROOF 2 FLOOR DRAINAGE SYSTEM LAYOUT PLAN SUBMITTAL 5 18-Jan-16 24-Jan-16 17-Jun-15 23-Jun-15 ZB4AEUMWA10 ROOF 2 FLOOR WATER SUPPLY SYSTEM LAYOUT PLAN APPROVAL 5 01-Mar-16 07-Mar-16 24-Jun-15 30-Jun-15 ZB4AEUMDA10 ROOF 2 FLOOR DRAINAGE SYSTEM LAYOUT PLAN APPROVAL 5 01-Mar-16 07-Mar-16 24-Jun-15 30-Jun-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2015 2016 2017 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings_1 18-Feb-16 09:32 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 7 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 8. Activity ID Activity Name Original Duration Start Finish BL Project Start BL Project Finish Composite DrawComposite Drawing 14 08-Mar-16 21-Mar-16 30-Aug-15 10-Sep-15 ZB4AEUCS10 ROOF 2 FLOOR COMPOSITE LAYOUT PLAN SUBMITTAL 5 08-Mar-16 14-Mar-16 30-Aug-15 03-Sep-15 ZB4AEUCA10 ROOF 2 FLOOR COMPOSITE LAYOUT PLAN APPROVAL 5 15-Mar-16 21-Mar-16 06-Sep-15 10-Sep-15 General Shop DGeneral Shop Drawings 151 21-Feb-16 28-Jun-16 27-May-15 21-Oct-15 Electrical SystemElectrical Systems 151 21-Feb-16 06-Jun-16 27-May-15 21-Oct-15 ZB4AETEGS10 ELECTRICAL INSTALLATION DETAILS SUBMITTAL 5 21-Feb-16 25-Feb-16 27-May-15 02-Jun-15 ZB4AETEGA10 ELECTRICAL INSTALLATION DETAILS APPROVAL 5 28-Feb-16 03-Mar-16 03-Jun-15 09-Jun-15 Power SystemPower System 29 29-Feb-16 27-Mar-16 02-Aug-15 27-Aug-15 ZB4AETEPS10 PANEL BOARD SCHEDULE SUBMITTAL 5 29-Feb-16 06-Mar-16 02-Aug-15 06-Aug-15 ZB4AETEPA10 PANEL BOARD SCHEDULE APPROVAL 5 07-Mar-16 13-Mar-16 09-Aug-15 13-Aug-15 ZB4AETEPS20 POWER S.L.D SUBMITTAL 5 14-Mar-16 20-Mar-16 16-Aug-15 20-Aug-15 ZB4AETEPA20 POWER S.L.D APPROVAL 5 21-Mar-16 27-Mar-16 23-Aug-15 27-Aug-15 Lighting SystemLighting System 114 28-Mar-16 19-May-16 01-Jul-15 21-Oct-15 ZB4AETELS10 LIGHTING FIXTURE SCHEDULE SUBMITTAL 5 28-Mar-16 03-Apr-16 01-Jul-15 07-Jul-15 ZB4AETELA10 LIGHTING FIXTURE SCHEDULE APPROVAL 5 04-Apr-16 10-Apr-16 08-Jul-15 14-Jul-15 ZB4AETELS20 CENTRAL MONITORING RISER DIAGRAM SUBMITTAL 5 27-Apr-16 05-May-16 29-Sep-15 05-Oct-15 ZB4AETELS30 KNX SYSTEM RISER DIAGRAM SUBMITTAL 5 08-May-16 12-May-16 07-Oct-15 13-Oct-15 ZB4AETELA20 CENTRAL MONITORING RISER DIAGRAM APPROVAL 5 08-May-16 12-May-16 07-Oct-15 13-Oct-15 ZB4AETELA30 KNX SYSTEM RISER DIAGRAM APPROVAL 5 15-May-16 19-May-16 15-Oct-15 21-Oct-15 Light Current SLight Current Systems 57 20-Mar-16 06-Jun-16 27-May-15 20-Jul-15 ZB4AETELGS10 LIGHT CURRENT TYPICAL INSTALLATION DETAILS SUBMITTAL 5 03-May-16 09-May-16 27-May-15 02-Jun-15 ZB4AETELGA10 LIGHT CURRENT TYPICAL INSTALLATION DETAILS APPROVAL 5 10-May-16 16-May-16 03-Jun-15 09-Jun-15 Fire Alarm SyFire Alarm System 15 20-Mar-16 31-Mar-16 01-Jul-15 14-Jul-15 ZB4AETELFS10 FIRE ALARM RISER DIAGRAM SUBMITTAL 5 20-Mar-16 24-Mar-16 01-Jul-15 07-Jul-15 ZB4AETELFA10FIRE ALARM RISER DIAGRAM APPROVAL 5 27-Mar-16 31-Mar-16 08-Jul-15 14-Jul-15 Security SystSecurity Systems 15 10-May-16 23-May-16 06-Jul-15 20-Jul-15 ZB4AETELSS10 IPCCTV RISER DIAGRAM SUBMITTAL (By Others) 5 10-May-16 16-May-16 06-Jul-15 12-Jul-15 ZB4AETELSA10IPCCTV RISER DIAGRAM APPROVAL (By Others) 5 17-May-16 23-May-16 13-Jul-15 20-Jul-15 CommunicatiCommunication Systems 15 24-May-16 06-Jun-16 25-Jun-15 08-Jul-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2015 2016 2017 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings_1 18-Feb-16 09:32 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 8 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 9. Activity ID Activity Name Original Duration Start Finish BL Project Start BL Project Finish ZB4AETELCS10STRUCTURED CABLING RISER DIAGRAM SUBMITTAL (By Others) 5 24-May-16 30-May-16 25-Jun-15 01-Jul-15 ZB4AETELCA10STRUCTURED CABLING RISER DIAGRAM APPROVAL (By Others) 5 31-May-16 06-Jun-16 02-Jul-15 08-Jul-15 SCADA SystemSCADA System 15 12-May-16 01-Jun-16 13-Sep-15 28-Sep-15 ZB4AETEDS10 SCADA SYSTEM RISER DIAGRAM SUBMITTAL 5 12-May-16 18-May-16 13-Sep-15 17-Sep-15 ZB4AETEDA10 SCADA SYSTEM RISER DIAGRAM APPROVAL 5 26-May-16 01-Jun-16 20-Sep-15 28-Sep-15 Mechanical SystMechanical Systems 60 01-Mar-16 28-Jun-16 27-May-15 22-Jul-15 HVAC SystemHVAC System 15 08-May-16 19-May-16 27-May-15 09-Jun-15 ZB4AETMHS10 HVAC INSTALLATION DETAILS SUBMITTAL 5 08-May-16 12-May-16 27-May-15 02-Jun-15 ZB4AETMHA10 HVAC INSTALLATION DETAILS APPROVAL 5 15-May-16 19-May-16 03-Jun-15 09-Jun-15 Fire ProtectionFire Protection Systems 60 01-Mar-16 21-Apr-16 27-May-15 22-Jul-15 ZB4AETMFS10 FIRE PROTECTION INSTALLATION DETAILS SUBMITTAL 5 10-Apr-16 14-Apr-16 27-May-15 02-Jun-15 ZB4AETMFA10 FIRE PROTECTION INSTALLATION DETAILS APPROVAL 5 17-Apr-16 21-Apr-16 03-Jun-15 09-Jun-15 ZB4AETMFS20 FIRE PROTECTION RISER DIAGRAM SUBMITTAL 5 01-Mar-16 07-Mar-16 08-Jul-15 14-Jul-15 ZB4AETMFA20 FIRE PROTECTION RISER DIAGRAM APPROVAL 5 08-Mar-16 14-Mar-16 15-Jul-15 22-Jul-15 Plumbing SystPlumbing System 15 08-Jun-16 28-Jun-16 27-May-15 09-Jun-15 ZB4AETMWS10 WATER SUPPLY INSTALLATION DETAILS SUBMITTAL 5 15-Jun-16 21-Jun-16 27-May-15 02-Jun-15 ZB4AETMDS10 DRAINAGE SYSTEM INSTALLATION DETAILS SUBMITTAL 5 08-Jun-16 14-Jun-16 27-May-15 02-Jun-15 ZB4AETMWA10 WATER SUPPLY INSTALLATION DETAILS APPROVAL 5 22-Jun-16 28-Jun-16 03-Jun-15 09-Jun-15 ZB4AETMDA10 DRAINAGE SYSTEM INSTALLATION DETAILS APPROVAL 5 15-Jun-16 21-Jun-16 03-Jun-15 09-Jun-15 Building B4 - B (EBuilding B4 - B (Electrical Services) 144 21-Jan-16 25-Aug-16 24-Jun-15 11-Nov-15 Ground FloorGround Floor 129 21-Jan-16 06-Jun-16 24-Jun-15 28-Oct-15 ZB4BEGGBS10 Ground Floor Builder Work Submittal 5 24-May-16 30-May-16 23-Aug-15 27-Aug-15 ZB4BEGGBA10 Ground Floor Builder Work Approval 5 31-May-16 06-Jun-16 30-Aug-15 03-Sep-15 Electrical SystemElectrical Systems 82 21-Jan-16 11-May-16 24-Jun-15 10-Sep-15 Power SystemPower System 14 02-Feb-16 22-Feb-16 26-Jul-15 06-Aug-15 ZB4BEGEPS10 GROUND FLOOR POWER SYSTEM LAYOUT PLAN SUBMITTAL 5 02-Feb-16 08-Feb-16 26-Jul-15 30-Jul-15 ZB4BEGEPA10 GROUND FLOOR POWER SYSTEM LAYOUT PLAN APPROVAL 5 16-Feb-16 22-Feb-16 02-Aug-15 06-Aug-15 Lighting SystemLighting System 15 26-Jan-16 22-Feb-16 24-Jun-15 07-Jul-15 ZB4BEGELS10 GROUND FLOOR LIGHTING SYSTEM LAYOUT PLAN SUBMITTAL 5 26-Jan-16 01-Feb-16 24-Jun-15 30-Jun-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2015 2016 2017 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings_1 18-Feb-16 09:32 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 9 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 10. Activity ID Activity Name Original Duration Start Finish BL Project Start BL Project Finish ZB4BEGELA10 GROUND FLOOR LIGHTING SYSTEM LAYOUT PLAN APPROVAL 5 16-Feb-16 22-Feb-16 01-Jul-15 07-Jul-15 Cable Tray SysCable Tray System 22 26-Jan-16 22-Feb-16 29-Jul-15 18-Aug-15 ZB4BEGECS10 GROUND FLOOR CABLE TRAY SYSTEM LAYOUT PLAN SUBMITTAL 10 26-Jan-16 08-Feb-16 29-Jul-15 11-Aug-15 ZB4BEGECA10 GROUND FLOOR CABLE TRAY SYSTEM LAYOUT PLAN APPROVAL 5 16-Feb-16 22-Feb-16 12-Aug-15 18-Aug-15 Earthing SysteEarthing System 14 02-Feb-16 22-Feb-16 09-Aug-15 20-Aug-15 ZB4BEGEES10 GROUND FLOOR EARTHING SYSTEM LAYOUT PLAN SUBMITTAL 5 02-Feb-16 08-Feb-16 09-Aug-15 13-Aug-15 ZB4BEGEEA10 GROUND FLOOR EARTHING SYSTEM LAYOUT PLAN APPROVAL 5 16-Feb-16 22-Feb-16 16-Aug-15 20-Aug-15 Light Current SLight Current Systems 60 21-Jan-16 22-Feb-16 24-Jun-15 20-Aug-15 Fire Alarm SyFire Alarm System 15 21-Jan-16 04-Feb-16 24-Jun-15 07-Jul-15 ZB4BEGELFS10 GROUND FLOOR FIRE ALARM SYSTEM LAYOUT PLAN SUBMITTAL 5 21-Jan-16 28-Jan-16 24-Jun-15 30-Jun-15 ZB4BEGELFA10GROUND FLOOR FIRE ALARM SYSTEM LAYOUT PLAN APPROVAL 5 31-Jan-16 04-Feb-16 01-Jul-15 07-Jul-15 Security SystSecurity Systems 55 02-Feb-16 22-Feb-16 29-Jun-15 20-Aug-15 ZB4BEGELSS10 GROUND FLOOR SECURITY SYSTEMS LAYOUT PLAN SUBMITTAL 5 02-Feb-16 08-Feb-16 29-Jun-15 05-Jul-15 ZB4BEGELSA10GROUND FLOOR SECURITY SYSTEMS LAYOUT PLAN APPROVAL 5 16-Feb-16 22-Feb-16 06-Jul-15 12-Jul-15 ZB4BEGELSA20Access Control System Approval and Approved Submittal (By Others) 0 22-Feb-16 20-Aug-15 CommunicatiCommunication Systems 15 09-Feb-16 22-Feb-16 06-Jul-15 20-Jul-15 ZB4BEGELCS10GROUND FLOOR COMMUNICATION SYSTEMS LAYOUT PLAN SUBMITTAL 5 09-Feb-16 15-Feb-16 06-Jul-15 12-Jul-15 ZB4BEGELCA10GROUND FLOOR COMMUNICATION SYSTEMS LAYOUT PLAN APPROVAL 5 16-Feb-16 22-Feb-16 13-Jul-15 20-Jul-15 SCADA SystemSCADA System 14 26-Apr-16 11-May-16 30-Aug-15 10-Sep-15 ZB4BEGEDS10 GROUND FLOOR SCADA SYSTEM LAYOUT PLAN SUBMITTAL 5 26-Apr-16 04-May-16 30-Aug-15 03-Sep-15 ZB4BEGEDA10 GROUND FLOOR SCADA SYSTEM LAYOUT PLAN APPROVAL 5 05-May-16 11-May-16 06-Sep-15 10-Sep-15 Mechanical SystMechanical Systems 129 26-Jan-16 26-May-16 24-Jun-15 28-Oct-15 HVAC SystemHVAC System 14 26-Jan-16 22-Feb-16 02-Aug-15 13-Aug-15 ZB4BEGMHS10 GROUND FLOOR HVAC SYSTEM LAYOUT PLAN SUBMITTAL 5 26-Jan-16 01-Feb-16 02-Aug-15 06-Aug-15 ZB4BEGMHA10 GROUND FLOOR HVAC SYSTEM LAYOUT PLAN APPROVAL 5 16-Feb-16 22-Feb-16 09-Aug-15 13-Aug-15 Fire ProtectionFire Protection Systems 22 08-May-16 26-May-16 07-Oct-15 28-Oct-15 ZB4BEGMFS20 FIRE PROTECTION WORK - SPECIAL SYSTEM DETAILS SUBMITTAL 10 08-May-16 19-May-16 07-Oct-15 21-Oct-15 ZB4BEGMFA20 FIRE PROTECTION WORK - SPECIAL SYSTEM DETAILS APPROVAL 5 22-May-16 26-May-16 22-Oct-15 28-Oct-15 Plumbing SystPlumbing System 15 26-Jan-16 22-Feb-16 24-Jun-15 07-Jul-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2015 2016 2017 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings_1 18-Feb-16 09:32 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 10 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 11. Activity ID Activity Name Original Duration Start Finish BL Project Start BL Project Finish ZB4BEGMDS10 GROUND FLOOR DRAINAGE SYSTEM LAYOUT PLAN SUBMITTAL 5 26-Jan-16 01-Feb-16 24-Jun-15 30-Jun-15 ZB4BEGMDA10 GROUND FLOOR DRAINAGE SYSTEM LAYOUT PLAN APPROVAL 5 16-Feb-16 22-Feb-16 01-Jul-15 07-Jul-15 Composite DrawComposite Drawing 14 23-Feb-16 07-Mar-16 23-Aug-15 03-Sep-15 ZB4BEGCS10 GROUND FLOOR COMPOSITE LAYOUT PLAN SUBMITTAL 5 23-Feb-16 29-Feb-16 23-Aug-15 27-Aug-15 ZB4BEGCA10 GROUND FLOOR COMPOSITE LAYOUT PLAN APPROVAL 5 01-Mar-16 07-Mar-16 30-Aug-15 03-Sep-15 Roof 1Roof 1 82 21-Jan-16 06-Jun-16 24-Jun-15 10-Sep-15 ZB4BERGBS10 Roof 1 Builder Work Submittal 5 24-May-16 30-May-16 30-Aug-15 03-Sep-15 ZB4BERGBA10 Roof 1 Builder Work Approval 5 31-May-16 06-Jun-16 06-Sep-15 10-Sep-15 Electrical SystemElectrical Systems 65 21-Jan-16 22-Feb-16 24-Jun-15 25-Aug-15 Power SystemPower System 14 09-Feb-16 22-Feb-16 02-Aug-15 13-Aug-15 ZB4BEREPS10 ROOF 1 FLOOR POWER SYSTEM LAYOUT PLAN SUBMITTAL 5 09-Feb-16 15-Feb-16 02-Aug-15 06-Aug-15 ZB4BEREPA10 ROOF 1 FLOOR POWER SYSTEM LAYOUT PLAN APPROVAL 5 16-Feb-16 22-Feb-16 09-Aug-15 13-Aug-15 Lighting SystemLighting System 15 02-Feb-16 22-Feb-16 01-Jul-15 14-Jul-15 ZB4BERELS10 ROOF 1 FLOOR LIGHTING SYSTEM LAYOUT PLAN SUBMITTAL 5 02-Feb-16 08-Feb-16 01-Jul-15 07-Jul-15 ZB4BERELA10 ROOF 1 FLOOR LIGHTING SYSTEM LAYOUT PLAN APPROVAL 5 16-Feb-16 22-Feb-16 08-Jul-15 14-Jul-15 Cable Tray SysCable Tray System 15 09-Feb-16 22-Feb-16 12-Aug-15 25-Aug-15 ZB4BERECS10 ROOF 1 FLOOR CABLE TRAY SYSTEM LAYOUT PLAN SUBMITTAL 5 09-Feb-16 15-Feb-16 12-Aug-15 18-Aug-15 ZB4BERECA10 ROOF 1 FLOOR CABLE TRAY SYSTEM LAYOUT PLAN APPROVAL 5 16-Feb-16 22-Feb-16 19-Aug-15 25-Aug-15 Light Current SLight Current Systems 15 21-Jan-16 04-Feb-16 24-Jun-15 07-Jul-15 Fire Alarm SyFire Alarm System 15 21-Jan-16 04-Feb-16 24-Jun-15 07-Jul-15 ZB4BERELFS10 ROOF 1 FLOOR FIRE ALARM SYSTEM LAYOUT PLAN SUBMITTAL 5 21-Jan-16 28-Jan-16 24-Jun-15 30-Jun-15 ZB4BERELFA10ROOF 1 FLOOR FIRE ALARM SYSTEM LAYOUT PLAN APPROVAL 5 31-Jan-16 04-Feb-16 01-Jul-15 07-Jul-15 Mechanical SystMechanical Systems 60 02-Feb-16 22-Feb-16 01-Jul-15 27-Aug-15 HVAC SystemHVAC System 21 02-Feb-16 22-Feb-16 09-Aug-15 27-Aug-15 ZB4BERMHS10 ROOF 1 FLOOR HVAC SYSTEM LAYOUT PLAN SUBMITTAL 10 02-Feb-16 15-Feb-16 09-Aug-15 20-Aug-15 ZB4BERMHS20 ROOF 1 FLOOR HVAC SECTIONS LAYOUT PLAN SUBMITTAL 10 02-Feb-16 15-Feb-16 09-Aug-15 20-Aug-15 ZB4BERMHA10 ROOF 1 FLOOR HVAC SYSTEM LAYOUT PLAN APPROVAL 5 16-Feb-16 22-Feb-16 23-Aug-15 27-Aug-15 ZB4BERMHA20 ROOF 1 FLOOR HVAC SECTIONS LAYOUT PLAN APPROVAL 5 16-Feb-16 22-Feb-16 23-Aug-15 27-Aug-15 Plumbing SystPlumbing System 15 02-Feb-16 22-Feb-16 01-Jul-15 14-Jul-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2015 2016 2017 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings_1 18-Feb-16 09:32 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 11 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 12. Activity ID Activity Name Original Duration Start Finish BL Project Start BL Project Finish ZB4BERMDS10 ROOF 1 FLOOR DRAINAGE SYSTEM LAYOUT PLAN SUBMITTAL 5 02-Feb-16 08-Feb-16 01-Jul-15 07-Jul-15 ZB4BERMDA10 ROOF 1 FLOOR DRAINAGE SYSTEM LAYOUT PLAN APPROVAL 5 16-Feb-16 22-Feb-16 08-Jul-15 14-Jul-15 Composite DrawComposite Drawing 14 23-Feb-16 07-Mar-16 30-Aug-15 10-Sep-15 ZB4BERCS10 ROOF 1 FLOOR COMPOSITE LAYOUT PLAN SUBMITTAL 5 23-Feb-16 29-Feb-16 30-Aug-15 03-Sep-15 ZB4BERCA10 ROOF 1 FLOOR COMPOSITE LAYOUT PLAN APPROVAL 5 01-Mar-16 07-Mar-16 06-Sep-15 10-Sep-15 Roof 2Roof 2 82 31-Jan-16 06-Jun-16 24-Jun-15 10-Sep-15 ZB4BEUGBS10 Roof 2 Builder Work Submittal 5 24-May-16 30-May-16 30-Aug-15 03-Sep-15 ZB4BEUGBA10 Roof 2 Builder Work Approval 5 31-May-16 06-Jun-16 06-Sep-15 10-Sep-15 Electrical SystemElectrical Systems 67 31-Jan-16 22-Feb-16 24-Jun-15 27-Aug-15 Power SystemPower System 14 09-Feb-16 22-Feb-16 02-Aug-15 13-Aug-15 ZB4BEUEPS10 ROOF 2 FLOOR POWER SYSTEM LAYOUT PLAN SUBMITTAL 5 09-Feb-16 15-Feb-16 02-Aug-15 06-Aug-15 ZB4BEUEPA10 ROOF 2 FLOOR POWER SYSTEM LAYOUT PLAN APPROVAL 5 16-Feb-16 22-Feb-16 09-Aug-15 13-Aug-15 Lighting SystemLighting System 15 09-Feb-16 22-Feb-16 08-Jul-15 22-Jul-15 ZB4BEUELS10 ROOF 2 FLOOR LIGHTING SYSTEM LAYOUT PLAN SUBMITTAL 5 09-Feb-16 15-Feb-16 08-Jul-15 14-Jul-15 ZB4BEUELA10 ROOF 2 FLOOR LIGHTING SYSTEM LAYOUT PLAN APPROVAL 5 16-Feb-16 22-Feb-16 15-Jul-15 22-Jul-15 Cable Tray SysCable Tray System 15 09-Feb-16 22-Feb-16 12-Aug-15 25-Aug-15 ZB4BEUECS10 ROOF 2 FLOOR CABLE TRAY SYSTEM LAYOUT PLAN SUBMITTAL 5 09-Feb-16 15-Feb-16 12-Aug-15 18-Aug-15 ZB4BEUECA10 ROOF 2 FLOOR CABLE TRAY SYSTEM LAYOUT PLAN APPROVAL 5 16-Feb-16 22-Feb-16 19-Aug-15 25-Aug-15 Lightning SystLightning System 14 09-Feb-16 22-Feb-16 16-Aug-15 27-Aug-15 ZB4BEUEHS10 ROOF 2 FLOOR LIGHTNING SYSTEM LAYOUT PLAN SUBMITTAL 5 09-Feb-16 15-Feb-16 16-Aug-15 20-Aug-15 ZB4BEUEHA10 ROOF 2 FLOOR LIGHTNING SYSTEM LAYOUT PLAN APPROVAL 5 16-Feb-16 22-Feb-16 23-Aug-15 27-Aug-15 Light Current SLight Current Systems 7 31-Jan-16 04-Feb-16 24-Jun-15 30-Jun-15 Fire Alarm SyFire Alarm System 7 31-Jan-16 04-Feb-16 24-Jun-15 30-Jun-15 ZB4BEUELFS10 ROOF 2 FLOOR FIRE ALARM SYSTEM LAYOUT PLAN SUBMITTAL 5 31-Jan-16 04-Feb-16 24-Jun-15 30-Jun-15 ZB4BEUELFA10ROOF 2 FLOOR FIRE ALARM SYSTEM LAYOUT PLAN APPROVAL 5 31-Jan-16 04-Feb-16 24-Jun-15 30-Jun-15 Mechanical SystMechanical Systems 52 02-Feb-16 22-Feb-16 08-Jul-15 27-Aug-15 HVAC SystemHVAC System 21 02-Feb-16 22-Feb-16 09-Aug-15 27-Aug-15 ZB4BEUMHS10 ROOF 2 FLOOR HVAC SYSTEM LAYOUT PLAN SUBMITTAL 10 02-Feb-16 15-Feb-16 09-Aug-15 20-Aug-15 ZB4BEUMHS20 ROOF 2 FLOOR HVAC SECTIONS LAYOUT PLAN SUBMITTAL 10 02-Feb-16 15-Feb-16 09-Aug-15 20-Aug-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2015 2016 2017 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings_1 18-Feb-16 09:32 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 12 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 13. Activity ID Activity Name Original Duration Start Finish BL Project Start BL Project Finish ZB4BEUMHA10 ROOF 2 FLOOR HVAC SYSTEM LAYOUT PLAN APPROVAL 5 16-Feb-16 22-Feb-16 23-Aug-15 27-Aug-15 ZB4BEUMHA20 ROOF 2 FLOOR HVAC SECTIONS LAYOUT PLAN APPROVAL 5 16-Feb-16 22-Feb-16 23-Aug-15 27-Aug-15 Plumbing SystPlumbing System 15 09-Feb-16 22-Feb-16 08-Jul-15 22-Jul-15 ZB4BEUMDS10 ROOF 2 FLOOR DRAINAGE SYSTEM LAYOUT PLAN SUBMITTAL 5 09-Feb-16 15-Feb-16 08-Jul-15 14-Jul-15 ZB4BEUMDA10 ROOF 2 FLOOR DRAINAGE SYSTEM LAYOUT PLAN APPROVAL 5 16-Feb-16 22-Feb-16 15-Jul-15 22-Jul-15 Composite DrawComposite Drawing 14 23-Feb-16 07-Mar-16 30-Aug-15 10-Sep-15 ZB4BEUCS10 ROOF 2 FLOOR COMPOSITE LAYOUT PLAN SUBMITTAL 5 23-Feb-16 29-Feb-16 30-Aug-15 03-Sep-15 ZB4BEUCA10 ROOF 2 FLOOR COMPOSITE LAYOUT PLAN APPROVAL 5 01-Mar-16 07-Mar-16 06-Sep-15 10-Sep-15 General Shop DGeneral Shop Drawings 144 07-Feb-16 25-Aug-16 24-Jun-15 11-Nov-15 Electrical SystemElectrical Systems 144 07-Feb-16 25-Aug-16 24-Jun-15 11-Nov-15 ZB4BETEGS10 ELECTRICAL INSTALLATION DETAILS SUBMITTAL 5 10-Mar-16 16-Mar-16 26-Jul-15 30-Jul-15 ZB4BETEGA10 ELECTRICAL INSTALLATION DETAILS APPROVAL 5 17-Mar-16 23-Mar-16 02-Aug-15 06-Aug-15 Power SystemPower System 60 08-Mar-16 05-May-16 13-Sep-15 11-Nov-15 ZB4BETEPS10 PANEL BOARD SCHEDULE SUBMITTAL 5 08-Mar-16 14-Mar-16 13-Sep-15 17-Sep-15 ZB4BETEPA10 PANEL BOARD SCHEDULE APPROVAL 5 15-Mar-16 21-Mar-16 20-Sep-15 28-Sep-15 ZB4BETEPS20 POWER S.L.D SUBMITTAL 5 22-Mar-16 28-Mar-16 29-Sep-15 05-Oct-15 ZB4BETEPA20 POWER S.L.D APPROVAL 5 29-Mar-16 04-Apr-16 07-Oct-15 13-Oct-15 ZB4BETEPS30 BUILDING POWER S.L.D SUBMITTAL 5 05-Apr-16 11-Apr-16 15-Oct-15 21-Oct-15 ZB4BETEPA30 BUILDING POWER S.L.D APPROVAL 5 12-Apr-16 18-Apr-16 22-Oct-15 28-Oct-15 ZB4BETEPS40 CAMPUS POWER S.L.D SUBMITTAL 5 19-Apr-16 26-Apr-16 29-Oct-15 04-Nov-15 ZB4BETEPA40 CAMPUS POWER S.L.D APPROVAL 5 27-Apr-16 05-May-16 05-Nov-15 11-Nov-15 Lighting SystemLighting System 21 23-Feb-16 10-Apr-16 26-Jul-15 13-Aug-15 ZB4BETELS10 LIGHTING FIXTURE SCHEDULE SUBMITTAL 5 23-Feb-16 29-Feb-16 26-Jul-15 30-Jul-15 ZB4BETELA10 LIGHTING FIXTURE SCHEDULE APPROVAL 5 04-Apr-16 10-Apr-16 02-Aug-15 06-Aug-15 ZB4BETELS20 KNX SYSTEM RISER DIAGRAM SUBMITTAL 5 08-Mar-16 14-Mar-16 02-Aug-15 06-Aug-15 ZB4BETELS30 CENTRAL MONITORING RISER DIAGRAM SUBMITTAL 5 01-Mar-16 07-Mar-16 02-Aug-15 06-Aug-15 ZB4BETELA20 KNX SYSTEM RISER DIAGRAM APPROVAL 5 15-Mar-16 21-Mar-16 09-Aug-15 13-Aug-15 ZB4BETELA30 CENTRAL MONITORING RISER DIAGRAM APPROVAL 5 08-Mar-16 14-Mar-16 09-Aug-15 13-Aug-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2015 2016 2017 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings_1 18-Feb-16 09:32 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 13 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 14. Activity ID Activity Name Original Duration Start Finish BL Project Start BL Project Finish Light Current SLight Current Systems 42 07-Feb-16 25-Aug-16 24-Jun-15 04-Aug-15 ZB4BETELGS10 LIGHT CURRENT TYPICAL INSTALLATION DETAILS SUBMITTAL 5 24-Apr-16 03-May-16 24-Jun-15 30-Jun-15 ZB4BETELGA10 LIGHT CURRENT TYPICAL INSTALLATION DETAILS APPROVAL 5 04-May-16 10-May-16 01-Jul-15 07-Jul-15 Fire Alarm SyFire Alarm System 15 07-Feb-16 18-Feb-16 08-Jul-15 22-Jul-15 ZB4BETELFS10 FIRE ALARM RISER DIAGRAM SUBMITTAL 5 07-Feb-16 11-Feb-16 08-Jul-15 14-Jul-15 ZB4BETELFA10FIRE ALARM RISER DIAGRAM APPROVAL 5 14-Feb-16 18-Feb-16 15-Jul-15 22-Jul-15 Security SystSecurity Systems 15 14-Aug-16 25-Aug-16 13-Jul-15 28-Jul-15 ZB4BETELSS10 IPCCTV RISER DIAGRAM SUBMITTAL (By Others) 5 14-Aug-16 18-Aug-16 13-Jul-15 20-Jul-15 ZB4BETELSA10IPCCTV RISER DIAGRAM APPROVAL (By Others) 5 21-Aug-16 25-Aug-16 21-Jul-15 28-Jul-15 CommunicatiCommunication Systems 15 04-May-16 17-May-16 21-Jul-15 04-Aug-15 ZB4BETELCS10STRUCTURED CABLING RISER DIAGRAM SUBMITTAL (By Others) 5 04-May-16 10-May-16 21-Jul-15 28-Jul-15 ZB4BETELCA10STRUCTURED CABLING RISER DIAGRAM APPROVAL (By Others) 5 11-May-16 17-May-16 29-Jul-15 04-Aug-15 SCADA SystemSCADA System 15 12-May-16 01-Jun-16 13-Sep-15 28-Sep-15 ZB4BETEDS10 SCADA SYSTEM RISER DIAGRAM SUBMITTAL 5 12-May-16 18-May-16 13-Sep-15 17-Sep-15 ZB4BETEDA10 SCADA SYSTEM RISER DIAGRAM APPROVAL 5 26-May-16 01-Jun-16 20-Sep-15 28-Sep-15 Mechanical SystMechanical Systems 75 18-May-16 25-Aug-16 24-Jun-15 03-Sep-15 HVAC SystemHVAC System 14 18-May-16 31-May-16 23-Aug-15 03-Sep-15 ZB4BETMHS10 HVAC INSTALLATION DETAILS SUBMITTAL 5 18-May-16 24-May-16 23-Aug-15 27-Aug-15 ZB4BETMHA10 HVAC INSTALLATION DETAILS APPROVAL 5 25-May-16 31-May-16 30-Aug-15 03-Sep-15 Fire ProtectionFire Protection Systems 15 20-Jul-16 02-Aug-16 01-Jul-15 14-Jul-15 ZB4BETMFS10 FIRE PROTECTION INSTALLATION DETAILS SUBMITTAL 5 20-Jul-16 26-Jul-16 01-Jul-15 07-Jul-15 ZB4BETMFA10 FIRE PROTECTION INSTALLATION DETAILS APPROVAL 5 27-Jul-16 02-Aug-16 08-Jul-15 14-Jul-15 Plumbing SystPlumbing System 15 14-Aug-16 25-Aug-16 24-Jun-15 07-Jul-15 ZB4BETMPDS10 DRAINAGE SYSTEM INSTALLATION DETAILS SUBMITTAL 5 14-Aug-16 18-Aug-16 24-Jun-15 30-Jun-15 ZB4BETMPDA10 DRAINAGE SYSTEM INSTALLATION DETAILS APPROVAL 5 21-Aug-16 25-Aug-16 01-Jul-15 07-Jul-15 Building B4 - D (FBuilding B4 - D (Fuel Tank) 106 21-Jan-16 25-Aug-16 24-Jun-15 05-Oct-15 Ground FloorGround Floor 106 21-Jan-16 27-Jul-16 24-Jun-15 05-Oct-15 ZB4DEGGBS30 Ground Floor Builder Work Submittal 5 14-Jul-16 20-Jul-16 23-Aug-15 27-Aug-15 ZB4DEGGBA30 Ground Floor Builder Work Approval 5 21-Jul-16 27-Jul-16 30-Aug-15 03-Sep-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2015 2016 2017 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings_1 18-Feb-16 09:32 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 14 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 15. Activity ID Activity Name Original Duration Start Finish BL Project Start BL Project Finish Electrical SystemElectrical Systems 60 21-Jan-16 20-Mar-16 24-Jun-15 20-Aug-15 Power SystemPower System 14 07-Mar-16 20-Mar-16 26-Jul-15 06-Aug-15 ZB4DEGEPS30 GROUND & ROOF 1 FLOOR POWER SYSTEM LAYOUTS PLAN SUBMITTAL 5 07-Mar-16 13-Mar-16 26-Jul-15 30-Jul-15 ZB4DEGEPA30 GROUND & ROOF 1 FLOOR POWER SYSTEM LAYOUTS PLAN APPROVAL 5 14-Mar-16 20-Mar-16 02-Aug-15 06-Aug-15 Lighting SystemLighting System 15 16-Feb-16 29-Feb-16 24-Jun-15 07-Jul-15 ZB4DEGELS30 GROUND FLOOR LIGHTING SYSTEM LAYOUT PLAN SUBMITTAL 5 16-Feb-16 22-Feb-16 24-Jun-15 30-Jun-15 ZB4DEGELA30 GROUND FLOOR LIGHTING SYSTEM LAYOUT PLAN APPROVAL 5 23-Feb-16 29-Feb-16 01-Jul-15 07-Jul-15 Cable Tray SysCable Tray System 22 29-Feb-16 20-Mar-16 29-Jul-15 18-Aug-15 ZB4DEGECS30 GROUND FLOOR CABLE TRAY SYSTEM LAYOUT PLAN SUBMITTAL 10 29-Feb-16 13-Mar-16 29-Jul-15 11-Aug-15 ZB4DEGECA30 GROUND FLOOR CABLE TRAY SYSTEM LAYOUT PLAN APPROVAL 5 14-Mar-16 20-Mar-16 12-Aug-15 18-Aug-15 Earthing SysteEarthing System 14 07-Mar-16 20-Mar-16 09-Aug-15 20-Aug-15 ZB4DEGEES30 GROUND FLOOR EARTHING SYSTEM LAYOUT PLAN SUBMITTAL 5 07-Mar-16 13-Mar-16 09-Aug-15 13-Aug-15 ZB4DEGEEA30 GROUND FLOOR EARTHING SYSTEM LAYOUT PLAN APPROVAL 5 14-Mar-16 20-Mar-16 16-Aug-15 20-Aug-15 Light Current SLight Current Systems 60 21-Jan-16 20-Mar-16 24-Jun-15 20-Aug-15 Fire Alarm SyFire Alarm System 15 21-Jan-16 04-Feb-16 24-Jun-15 07-Jul-15 ZB4DEGELFS30GROUND FLOOR FIRE ALARM SYSTEM LAYOUT PLAN SUBMITTAL 5 21-Jan-16 28-Jan-16 24-Jun-15 30-Jun-15 ZB4DEGELFA30GROUND FLOOR FIRE ALARM SYSTEM LAYOUT PLAN APPROVAL 5 31-Jan-16 04-Feb-16 01-Jul-15 07-Jul-15 Security SystSecurity Systems 0 20-Mar-16 20-Mar-16 20-Aug-15 20-Aug-15 ZB4DEGELSA80Access Control System Approval and Approved Submittal (By Others) 0 20-Mar-16 20-Aug-15 Mechanical SystMechanical Systems 106 07-Mar-16 31-May-16 24-Jun-15 05-Oct-15 HVAC SystemHVAC System 14 07-Mar-16 20-Mar-16 02-Aug-15 13-Aug-15 ZB4DEGMHS30 GROUND FLOOR HVAC SYSTEM LAYOUT PLAN SUBMITTAL 5 07-Mar-16 13-Mar-16 02-Aug-15 06-Aug-15 ZB4DEGMHA30 GROUND FLOOR HVAC SYSTEM LAYOUT PLAN APPROVAL 5 14-Mar-16 20-Mar-16 09-Aug-15 13-Aug-15 Fire ProtectionFire Protection Systems 22 11-May-16 31-May-16 13-Sep-15 05-Oct-15 ZB4DEGMFS40 FIRE PROTECTION WORK - SPECIAL SYSTEM DETAILS SUBMITTAL 10 11-May-16 24-May-16 13-Sep-15 28-Sep-15 ZB4DEGMFA40 FIRE PROTECTION WORK - SPECIAL SYSTEM DETAILS APPROVAL 5 25-May-16 31-May-16 29-Sep-15 05-Oct-15 Plumbing SystPlumbing System 15 07-Mar-16 20-Mar-16 24-Jun-15 07-Jul-15 ZB4DEGMDS30 GROUND FLOOR DRAINAGE SYSTEM LAYOUT PLAN SUBMITTAL 5 07-Mar-16 13-Mar-16 24-Jun-15 30-Jun-15 ZB4DEGMDA30 GROUND FLOOR DRAINAGE SYSTEM LAYOUT PLAN APPROVAL 5 14-Mar-16 20-Mar-16 01-Jul-15 07-Jul-15 Composite DrawComposite Drawing 14 21-Mar-16 03-Apr-16 23-Aug-15 03-Sep-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2015 2016 2017 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings_1 18-Feb-16 09:32 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 15 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 16. Activity ID Activity Name Original Duration Start Finish BL Project Start BL Project Finish ZB4DEGCS30 GROUND FLOOR COMPOSITE LAYOUT PLAN SUBMITTAL 5 21-Mar-16 27-Mar-16 23-Aug-15 27-Aug-15 ZB4DEGCA30 GROUND FLOOR COMPOSITE LAYOUT PLAN APPROVAL 5 28-Mar-16 03-Apr-16 30-Aug-15 03-Sep-15 Roof 1Roof 1 75 31-Jan-16 25-Aug-16 24-Jun-15 03-Sep-15 Electrical SystemElectrical Systems 75 31-Jan-16 18-Aug-16 24-Jun-15 03-Sep-15 Light Current SLight Current Systems 20 31-Jan-16 20-Mar-16 24-Jun-15 12-Jul-15 Fire Alarm SyFire Alarm System 7 31-Jan-16 04-Feb-16 24-Jun-15 30-Jun-15 ZB4DEUELFS20ROOF 1 FLOOR FIRE ALARM SYSTEM LAYOUT PLAN SUBMITTAL 5 31-Jan-16 04-Feb-16 24-Jun-15 30-Jun-15 ZB4DEUELFA20ROOF 1 FLOOR FIRE ALARM SYSTEM LAYOUT PLAN APPROVAL 5 31-Jan-16 04-Feb-16 24-Jun-15 30-Jun-15 Security SystSecurity Systems 15 07-Mar-16 20-Mar-16 29-Jun-15 12-Jul-15 ZB4DEGELSS30 ROOF 1 FLOOR SECURITY SYSTEMS LAYOUT PLAN SUBMITTAL 5 07-Mar-16 13-Mar-16 29-Jun-15 05-Jul-15 ZB4DEGELSA50ROOF 1 FLOOR SECURITY SYSTEMS LAYOUT PLAN APPROVAL 5 14-Mar-16 20-Mar-16 06-Jul-15 12-Jul-15 Lightning SystLightning System 14 07-Aug-16 18-Aug-16 23-Aug-15 03-Sep-15 ZB4DEUEHS20 ROOF 1 FLOOR LIGHTNING SYSTEM LAYOUT PLAN SUBMITTAL 5 07-Aug-16 11-Aug-16 23-Aug-15 27-Aug-15 ZB4DEUEHA20 ROOF 1 FLOOR LIGHTNING SYSTEM LAYOUT PLAN APPROVAL 5 14-Aug-16 18-Aug-16 30-Aug-15 03-Sep-15 Mechanical SystMechanical Systems 15 14-Aug-16 25-Aug-16 01-Jul-15 14-Jul-15 Plumbing SystPlumbing System 15 14-Aug-16 25-Aug-16 01-Jul-15 14-Jul-15 ZB4DERMDS30 ROOF 1 FLOOR DRAINAGE SYSTEM LAYOUT PLAN SUBMITTAL 5 14-Aug-16 18-Aug-16 01-Jul-15 07-Jul-15 ZB4DERMDA30 ROOF 1 FLOOR DRAINAGE SYSTEM LAYOUT PLAN APPROVAL 5 21-Aug-16 25-Aug-16 08-Jul-15 14-Jul-15 General Shop DGeneral Shop Drawings 106 07-Feb-16 03-Jul-16 24-Jun-15 05-Oct-15 Electrical SystemElectrical Systems 106 07-Feb-16 03-Jul-16 24-Jun-15 05-Oct-15 ZB4DETEGS30 ELECTRICAL INSTALLATION DETAILS SUBMITTAL 5 19-Apr-16 26-Apr-16 26-Jul-15 30-Jul-15 ZB4DETEGA30 ELECTRICAL INSTALLATION DETAILS APPROVAL 5 27-Apr-16 05-May-16 02-Aug-15 06-Aug-15 Power SystemPower System 30 04-Apr-16 04-May-16 06-Sep-15 05-Oct-15 ZB4DETEPS60 POWER S.L.D SUBMITTAL 15 04-Apr-16 24-Apr-16 06-Sep-15 28-Sep-15 ZB4DETEPA60 POWER S.L.D APPROVAL 5 26-Apr-16 04-May-16 29-Sep-15 05-Oct-15 Lighting SystemLighting System 22 01-Mar-16 10-Apr-16 08-Jul-15 30-Jul-15 ZB4DETELS60 LIGHTING FIXTURE SCHEDULE SUBMITTAL 5 01-Mar-16 07-Mar-16 08-Jul-15 14-Jul-15 ZB4DETELA60 LIGHTING FIXTURE SCHEDULE APPROVAL 5 04-Apr-16 10-Apr-16 15-Jul-15 22-Jul-15 ZB4DETELS70 KNX SYSTEM RISER DIAGRAM SUBMITTAL 5 08-Mar-16 14-Mar-16 15-Jul-15 22-Jul-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2015 2016 2017 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings_1 18-Feb-16 09:32 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 16 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 17. Activity ID Activity Name Original Duration Start Finish BL Project Start BL Project Finish ZB4DETELA70 KNX SYSTEM RISER DIAGRAM APPROVAL 5 15-Mar-16 21-Mar-16 26-Jul-15 30-Jul-15 Light Current SLight Current Systems 35 07-Feb-16 03-Jul-16 24-Jun-15 28-Jul-15 ZB4DETELGS30 LIGHT CURRENT TYPICAL INSTALLATION DETAILS SUBMITTAL 5 13-Jun-16 19-Jun-16 24-Jun-15 30-Jun-15 ZB4DETELGA30 LIGHT CURRENT TYPICAL INSTALLATION DETAILS APPROVAL 5 20-Jun-16 26-Jun-16 01-Jul-15 07-Jul-15 Fire Alarm SyFire Alarm System 15 07-Feb-16 18-Feb-16 08-Jul-15 22-Jul-15 ZB4DETELFS30 FIRE ALARM RISER DIAGRAM SUBMITTAL 5 07-Feb-16 11-Feb-16 08-Jul-15 14-Jul-15 ZB4DETELFA30FIRE ALARM RISER DIAGRAM APPROVAL 5 14-Feb-16 18-Feb-16 15-Jul-15 22-Jul-15 Security SystSecurity Systems 15 20-Jun-16 03-Jul-16 13-Jul-15 28-Jul-15 ZB4DETELSS30 IPCCTV RISER DIAGRAM SUBMITTAL (By Others) 5 20-Jun-16 26-Jun-16 13-Jul-15 20-Jul-15 ZB4DETELSA30IPCCTV RISER DIAGRAM APPROVAL (By Others) 5 27-Jun-16 03-Jul-16 21-Jul-15 28-Jul-15 Building B4 - E (EBuilding B4 - E (EDC Building) 106 21-Jan-16 28-Aug-16 24-Jun-15 05-Oct-15 Ground FloorGround Floor 90 21-Jan-16 28-Aug-16 24-Jun-15 17-Sep-15 ZB4EEGGBS20 Ground Floor Builder Work Submittal 5 15-Aug-16 21-Aug-16 23-Aug-15 27-Aug-15 ZB4EEGGBA20 Ground Floor Builder Work Approval 5 22-Aug-16 28-Aug-16 30-Aug-15 03-Sep-15 Electrical SystemElectrical Systems 82 21-Jan-16 10-Apr-16 24-Jun-15 10-Sep-15 Power SystemPower System 14 08-Mar-16 21-Mar-16 26-Jul-15 06-Aug-15 ZB4EEGEPS20 GROUND FLOOR POWER SYSTEM LAYOUT PLAN SUBMITTAL 5 08-Mar-16 14-Mar-16 26-Jul-15 30-Jul-15 ZB4EEGEPA20 GROUND FLOOR POWER SYSTEM LAYOUT PLAN APPROVAL 5 15-Mar-16 21-Mar-16 02-Aug-15 06-Aug-15 Lighting SystemLighting System 15 02-Feb-16 15-Feb-16 24-Jun-15 07-Jul-15 ZB4EEGELS20 GROUND FLOOR LIGHTING SYSTEM LAYOUT PLAN SUBMITTAL 5 02-Feb-16 08-Feb-16 24-Jun-15 30-Jun-15 ZB4EEGELA20 GROUND FLOOR LIGHTING SYSTEM LAYOUT PLAN APPROVAL 5 09-Feb-16 15-Feb-16 01-Jul-15 07-Jul-15 Cable Tray SysCable Tray System 22 01-Mar-16 21-Mar-16 29-Jul-15 18-Aug-15 ZB4EEGECS20 GROUND FLOOR CABLE TRAY SYSTEM LAYOUT PLAN SUBMITTAL 10 01-Mar-16 14-Mar-16 29-Jul-15 11-Aug-15 ZB4EEGECA20 GROUND FLOOR CABLE TRAY SYSTEM LAYOUT PLAN APPROVAL 5 15-Mar-16 21-Mar-16 12-Aug-15 18-Aug-15 Earthing SysteEarthing System 14 08-Mar-16 21-Mar-16 09-Aug-15 20-Aug-15 ZB4EEGEES20 GROUND FLOOR EARTHING SYSTEM LAYOUT PLAN SUBMITTAL 5 08-Mar-16 14-Mar-16 09-Aug-15 13-Aug-15 ZB4EEGEEA20 GROUND FLOOR EARTHING SYSTEM LAYOUT PLAN APPROVAL 5 15-Mar-16 21-Mar-16 16-Aug-15 20-Aug-15 Light Current SLight Current Systems 60 21-Jan-16 21-Mar-16 24-Jun-15 20-Aug-15 Fire Alarm SyFire Alarm System 15 21-Jan-16 04-Feb-16 24-Jun-15 07-Jul-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2015 2016 2017 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings_1 18-Feb-16 09:32 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 17 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 18. Activity ID Activity Name Original Duration Start Finish BL Project Start BL Project Finish ZB4EEGELFS20 GROUND FLOOR FIRE ALARM SYSTEM LAYOUT PLAN SUBMITTAL 5 21-Jan-16 28-Jan-16 24-Jun-15 30-Jun-15 ZB4EEGELFA20GROUND FLOOR FIRE ALARM SYSTEM LAYOUT PLAN APPROVAL 5 31-Jan-16 04-Feb-16 01-Jul-15 07-Jul-15 Security SystSecurity Systems 55 01-Mar-16 21-Mar-16 29-Jun-15 20-Aug-15 ZB4EEGELSS20 GROUND FLOOR SECURITY SYSTEMS LAYOUT PLAN SUBMITTAL 5 01-Mar-16 07-Mar-16 29-Jun-15 05-Jul-15 ZB4EEGELSA30GROUND FLOOR SECURITY SYSTEMS LAYOUT PLAN APPROVAL 5 15-Mar-16 21-Mar-16 06-Jul-15 12-Jul-15 ZB4EEGELSA40Access Control System Approval and Approved Submittal (By Others) 0 21-Mar-16 20-Aug-15 CommunicatiCommunication Systems 15 08-Mar-16 21-Mar-16 06-Jul-15 20-Jul-15 ZB4EEGELCS20GROUND FLOOR COMMUNICATION SYSTEMS LAYOUT PLAN SUBMITTAL 5 08-Mar-16 14-Mar-16 06-Jul-15 12-Jul-15 ZB4EEGELCA20GROUND FLOOR COMMUNICATION SYSTEMS LAYOUT PLAN APPROVAL 5 15-Mar-16 21-Mar-16 13-Jul-15 20-Jul-15 SCADA SystemSCADA System 14 28-Mar-16 10-Apr-16 30-Aug-15 10-Sep-15 ZB4EEGEDS20 GROUND FLOOR SCADA SYSTEM LAYOUT PLAN SUBMITTAL 5 28-Mar-16 03-Apr-16 30-Aug-15 03-Sep-15 ZB4EEGEDA20 GROUND FLOOR SCADA SYSTEM LAYOUT PLAN APPROVAL 5 04-Apr-16 10-Apr-16 06-Sep-15 10-Sep-15 Mechanical SystMechanical Systems 90 08-Mar-16 19-May-16 24-Jun-15 17-Sep-15 HVAC SystemHVAC System 14 08-Mar-16 21-Mar-16 02-Aug-15 13-Aug-15 ZB4EEGMHS20 GROUND FLOOR HVAC SYSTEM LAYOUT PLAN SUBMITTAL 5 08-Mar-16 14-Mar-16 02-Aug-15 06-Aug-15 ZB4EEGMHA20 GROUND FLOOR HVAC SYSTEM LAYOUT PLAN APPROVAL 5 15-Mar-16 21-Mar-16 09-Aug-15 13-Aug-15 Fire ProtectionFire Protection Systems 21 27-Apr-16 19-May-16 30-Aug-15 17-Sep-15 ZB4EEGMFS30 FIRE PROTECTION WORK - SPECIAL SYSTEM DETAILS SUBMITTAL 10 27-Apr-16 12-May-16 30-Aug-15 10-Sep-15 ZB4EEGMFA30 FIRE PROTECTION WORK - SPECIAL SYSTEM DETAILS APPROVAL 5 15-May-16 19-May-16 13-Sep-15 17-Sep-15 Plumbing SystPlumbing System 15 08-Mar-16 21-Mar-16 24-Jun-15 07-Jul-15 ZB4EEGMDS20 GROUND FLOOR DRAINAGE SYSTEM LAYOUT PLAN SUBMITTAL 5 08-Mar-16 14-Mar-16 24-Jun-15 30-Jun-15 ZB4EEGMDA20 GROUND FLOOR DRAINAGE SYSTEM LAYOUT PLAN APPROVAL 5 15-Mar-16 21-Mar-16 01-Jul-15 07-Jul-15 Composite DrawComposite Drawing 14 22-Mar-16 04-Apr-16 23-Aug-15 03-Sep-15 ZB4EEGCS20 GROUND FLOOR COMPOSITE LAYOUT PLAN SUBMITTAL 5 22-Mar-16 28-Mar-16 23-Aug-15 27-Aug-15 ZB4EEGCA20 GROUND FLOOR COMPOSITE LAYOUT PLAN APPROVAL 5 29-Mar-16 04-Apr-16 30-Aug-15 03-Sep-15 Roof 1Roof 1 15 14-Aug-16 25-Aug-16 01-Jul-15 14-Jul-15 Mechanical SystMechanical Systems 15 14-Aug-16 25-Aug-16 01-Jul-15 14-Jul-15 Plumbing SystPlumbing System 15 14-Aug-16 25-Aug-16 01-Jul-15 14-Jul-15 ZB4EERMDS20 ROOF 1 FLOOR DRAINAGE SYSTEM LAYOUT PLAN SUBMITTAL 5 14-Aug-16 18-Aug-16 01-Jul-15 07-Jul-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2015 2016 2017 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings_1 18-Feb-16 09:32 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 18 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 19. Activity ID Activity Name Original Duration Start Finish BL Project Start BL Project Finish ZB4EERMDA20 ROOF 1 FLOOR DRAINAGE SYSTEM LAYOUT PLAN APPROVAL 5 21-Aug-16 25-Aug-16 08-Jul-15 14-Jul-15 General Shop DGeneral Shop Drawings 106 07-Feb-16 04-Jul-16 24-Jun-15 05-Oct-15 Electrical SystemElectrical Systems 106 07-Feb-16 04-Jul-16 24-Jun-15 05-Oct-15 ZB4EETEGS20 ELECTRICAL INSTALLATION DETAILS SUBMITTAL 5 12-Apr-16 18-Apr-16 26-Jul-15 30-Jul-15 ZB4EETEGA20 ELECTRICAL INSTALLATION DETAILS APPROVAL 5 19-Apr-16 26-Apr-16 02-Aug-15 06-Aug-15 Power SystemPower System 30 05-Apr-16 05-May-16 06-Sep-15 05-Oct-15 ZB4EETEPS50 POWER S.L.D SUBMITTAL 15 05-Apr-16 26-Apr-16 06-Sep-15 28-Sep-15 ZB4EETEPA50 POWER S.L.D APPROVAL 5 27-Apr-16 05-May-16 29-Sep-15 05-Oct-15 Lighting SystemLighting System 22 01-Mar-16 10-Apr-16 08-Jul-15 30-Jul-15 ZB4EETELS40 LIGHTING FIXTURE SCHEDULE SUBMITTAL 5 01-Mar-16 07-Mar-16 08-Jul-15 14-Jul-15 ZB4EETELA40 LIGHTING FIXTURE SCHEDULE APPROVAL 5 04-Apr-16 10-Apr-16 15-Jul-15 22-Jul-15 ZB4EETELS50 KNX SYSTEM RISER DIAGRAM SUBMITTAL 5 08-Mar-16 14-Mar-16 15-Jul-15 22-Jul-15 ZB4EETELA50 KNX SYSTEM RISER DIAGRAM APPROVAL 5 15-Mar-16 21-Mar-16 26-Jul-15 30-Jul-15 Light Current SLight Current Systems 35 07-Feb-16 04-Jul-16 24-Jun-15 28-Jul-15 ZB4EETELGS20 LIGHT CURRENT TYPICAL INSTALLATION DETAILS SUBMITTAL 5 14-Jun-16 20-Jun-16 24-Jun-15 30-Jun-15 ZB4EETELGA20 LIGHT CURRENT TYPICAL INSTALLATION DETAILS APPROVAL 5 21-Jun-16 27-Jun-16 01-Jul-15 07-Jul-15 Fire Alarm SyFire Alarm System 15 07-Feb-16 18-Feb-16 08-Jul-15 22-Jul-15 ZB4EETELFS20 FIRE ALARM RISER DIAGRAM SUBMITTAL 5 07-Feb-16 11-Feb-16 08-Jul-15 14-Jul-15 ZB4EETELFA20FIRE ALARM RISER DIAGRAM APPROVAL 5 14-Feb-16 18-Feb-16 15-Jul-15 22-Jul-15 Security SystSecurity Systems 15 21-Jun-16 04-Jul-16 13-Jul-15 28-Jul-15 ZB4EETELSS20 IPCCTV RISER DIAGRAM SUBMITTAL (By Others) 5 21-Jun-16 27-Jun-16 13-Jul-15 20-Jul-15 ZB4EETELSA20IPCCTV RISER DIAGRAM APPROVAL (By Others) 5 28-Jun-16 04-Jul-16 21-Jul-15 28-Jul-15 SCADA SystemSCADA System 15 12-May-16 01-Jun-16 13-Sep-15 28-Sep-15 ZB4EETEDS20 SCADA SYSTEM RISER DIAGRAM SUBMITTAL 5 12-May-16 18-May-16 13-Sep-15 17-Sep-15 ZB4EETEDA20 SCADA SYSTEM RISER DIAGRAM APPROVAL 5 26-May-16 01-Jun-16 20-Sep-15 28-Sep-15 Tunnel & Site LayTunnel & Site Layout 235 07-Feb-16 03-Nov-16 26-May-15 10-Jan-16 ZB4LEB460 Receive Approved Site Layout (Architecture & Structural & Roads Sections and Levels) 0 27-Mar-16 26-May-15 ZB4LEB650 Receive Approved Site Layout (MEP Networks out of Siemens Scope) 0 27-Mar-16 26-May-15 Service TunnelService Tunnel 204 07-Feb-16 03-Nov-16 26-May-15 09-Dec-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2015 2016 2017 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings_1 18-Feb-16 09:32 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 19 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 20. Activity ID Activity Name Original Duration Start Finish BL Project Start BL Project Finish Electrical SystemElectrical Systems 204 10-Mar-16 03-Nov-16 26-May-15 09-Dec-15 Tunnel MediumTunnel Medium Voltage Network 30 26-Jun-16 25-Jul-16 12-Nov-15 09-Dec-15 ZB4TEBEPS30 BASEMENT FLOOR MV NETWORK LAYOUT PLAN SUBMITTAL 15 26-Jun-16 18-Jul-16 12-Nov-15 02-Dec-15 ZB4TEBEPA30 BASEMENT FLOOR MV NETWORK LAYOUT PLAN APPROVAL 5 19-Jul-16 25-Jul-16 03-Dec-15 09-Dec-15 Tunnel Low VoTunnel Low Voltage Network 0 03-Nov-16 03-Nov-16 26-May-15 26-May-15 ZB4TEBELA30 BASEMENT FLOOR LV NETWORK LAYOUT PLAN APPROVAL (BY OTHERS) 0 03-Nov-16 26-May-15 Power SystemPower System 14 13-Mar-16 24-Mar-16 02-Aug-15 13-Aug-15 ZB4TEBEPS20 BASEMENT FLOOR POWER SYSTEM LAYOUT PLAN SUBMITTAL 5 13-Mar-16 17-Mar-16 02-Aug-15 06-Aug-15 ZB4TEBEPA20 BASEMENT FLOOR POWER SYSTEM LAYOUT PLAN APPROVAL 5 20-Mar-16 24-Mar-16 09-Aug-15 13-Aug-15 Lighting SystemLighting System 15 13-Mar-16 24-Mar-16 02-Jul-15 15-Jul-15 ZB4TEBELS20 BASEMENT FLOOR LIGHTING SYSTEM LAYOUT PLAN SUBMITTAL 5 13-Mar-16 17-Mar-16 02-Jul-15 08-Jul-15 ZB4TEBELA20 BASEMENT FLOOR LIGHTING SYSTEM LAYOUT PLAN APPROVAL 5 20-Mar-16 24-Mar-16 09-Jul-15 15-Jul-15 Light Current SLight Current Systems 83 10-Mar-16 24-Mar-16 26-May-15 13-Aug-15 Fire Alarm SyFire Alarm System 83 10-Mar-16 24-Mar-16 26-May-15 13-Aug-15 ZB4TEBELFA30INFRASTRUCTURE FIRE ALARM SERVICE CORRIDOR APPROVAL (BY OTHERS) 0 10-Mar-16 26-May-15 ZB4TEBELFS20 BASEMENT FLOOR FIRE ALARM SYSTEM PLAN SUBMITTAL 5 13-Mar-16 17-Mar-16 02-Aug-15 06-Aug-15 ZB4TEBELFA20BASEMENT FLOOR FIRE ALARM SYSTEM PLAN APPROVAL 5 20-Mar-16 24-Mar-16 09-Aug-15 13-Aug-15 Security SystSecurity Systems 0 24-Mar-16 24-Mar-16 26-May-15 26-May-15 ZB4TEBELSA20CCTV SYSTEM - SERVICE CORRIDOR APPROVAL (BY OTHERS) 0 24-Mar-16 26-May-15 CommunicatiCommunication Systems 0 24-Mar-16 24-Mar-16 26-May-15 26-May-15 ZB4TEBELCA20TELECOMMUNICATION INFRASTRUCTURE CABLING APPROVAL (BY OTHERS) 0 24-Mar-16 26-May-15 SCADA SystemSCADA System 14 18-Jul-16 31-Jul-16 06-Sep-15 17-Sep-15 ZB4TEBEDS20 BASEMENT FLOOR SCADA SYSTEM LAYOUT PLAN SUBMITTAL 5 18-Jul-16 24-Jul-16 06-Sep-15 10-Sep-15 ZB4TEBEDA20 BASEMENT FLOOR SCADA SYSTEM LAYOUT PLAN APPROVAL 5 25-Jul-16 31-Jul-16 13-Sep-15 17-Sep-15 Mechanical SystMechanical Systems 60 28-Feb-16 03-Nov-16 10-Jun-15 06-Aug-15 HVAC SystemHVAC System 47 28-Feb-16 24-Mar-16 22-Jun-15 06-Aug-15 ZB4TEBMHS40 BASEMENT FLOOR HVAC PIPING LAYOUT PLAN SUBMITTAL 15 28-Feb-16 17-Mar-16 22-Jun-15 12-Jul-15 ZB4TEBMHA40 BASEMENT FLOOR HVAC PIPING LAYOUT PLAN APPROVAL 5 20-Mar-16 24-Mar-16 13-Jul-15 20-Jul-15 ZB4TEBMHS30 BASEMENT FLOOR HVAC DUCT SYSTEM LAYOUT PLAN SUBMITTAL 10 06-Mar-16 17-Mar-16 15-Jul-15 30-Jul-15 ZB4TEBMHA30 BASEMENT FLOOR HVAC DUCT SYSTEM LAYOUT PLAN APPROVAL 5 20-Mar-16 24-Mar-16 02-Aug-15 06-Aug-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2015 2016 2017 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings_1 18-Feb-16 09:32 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 20 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 21. Activity ID Activity Name Original Duration Start Finish BL Project Start BL Project Finish Fire ProtectionFire Protection Systems 22 06-Mar-16 24-Mar-16 10-Jun-15 30-Jun-15 ZB4TEBMFS20 FIRE PROTECTION WORK -SERVICE TUNNEL- OVERALL PLAN SUBMITTAL 10 06-Mar-16 17-Mar-16 10-Jun-15 23-Jun-15 ZB4TEBMFA20 FIRE PROTECTION WORK -SERVICE TUNNEL- OVERALL PLAN APPROVAL 5 20-Mar-16 24-Mar-16 24-Jun-15 30-Jun-15 Plumbing SystPlumbing System 52 28-Feb-16 03-Nov-16 17-Jun-15 06-Aug-15 ZB4TEBMWS30 BASEMENT FLOOR WATER SUPPLY SYSTEM LAYOUT PLAN SUBMITTAL 15 28-Feb-16 17-Mar-16 17-Jun-15 07-Jul-15 ZB4TEBMDS20 BASEMENT FLOOR DRAINAGE SYSTEM LAYOUT PLAN SUBMITTAL 15 31-May-16 20-Jun-16 17-Jun-15 07-Jul-15 ZB4TEBMWA30 BASEMENT FLOOR WATER SUPPLY SYSTEM LAYOUT PLAN APPROVAL 5 20-Mar-16 24-Mar-16 08-Jul-15 14-Jul-15 ZB4TEBMDA20 BASEMENT FLOOR DRAINAGE SYSTEM LAYOUT PLAN APPROVAL 5 30-Oct-16 03-Nov-16 08-Jul-15 14-Jul-15 ZB4TEBMWS40 SUMP PIT DETAILS & SECTIONS SUBMITTAL 15 21-Jun-16 13-Jul-16 08-Jul-15 30-Jul-15 ZB4TEBMWA40 SUMP PIT DETAILS & SECTIONS APPROVAL 5 14-Jul-16 20-Jul-16 02-Aug-15 06-Aug-15 Composite DrawComposite Drawing 21 27-Mar-16 14-Apr-16 16-Aug-15 03-Sep-15 ZB4TEBCS20 SERVICE TUNNEL COMPOSITE LAYOUT PLAN SUBMITTAL 10 27-Mar-16 07-Apr-16 16-Aug-15 27-Aug-15 ZB4TEBCA20 SERVICE TUNNEL COMPOSITE LAYOUT PLAN APPROVAL 5 10-Apr-16 14-Apr-16 30-Aug-15 03-Sep-15 General Shop DrGeneral Shop Drawings 99 07-Feb-16 04-Jul-16 24-Jun-15 28-Sep-15 Electrical SysteElectrical Systems 99 07-Feb-16 04-Jul-16 24-Jun-15 28-Sep-15 ZB4TETEGS40 ELECTRICAL INSTALLATION DETAILS SUBMITTAL 5 11-May-16 17-May-16 26-Jul-15 30-Jul-15 ZB4TETEGA40 ELECTRICAL INSTALLATION DETAILS APPROVAL 5 18-May-16 24-May-16 02-Aug-15 06-Aug-15 Power SystemPower System 14 07-Apr-16 20-Apr-16 16-Aug-15 27-Aug-15 ZB4TETEPS70 POWER S.L.D AND PANEL BOARD SCHEDULE SUBMITTAL 5 07-Apr-16 13-Apr-16 16-Aug-15 20-Aug-15 ZB4TETEPA70 POWER S.L.D AND PANEL BOARD SCHEDULE APPROVAL 5 14-Apr-16 20-Apr-16 23-Aug-15 27-Aug-15 Lighting SystLighting System 22 01-Mar-16 10-Apr-16 08-Jul-15 30-Jul-15 ZB4TETELS80 LIGHTING FIXTURE SCHEDULE SUBMITTAL 5 01-Mar-16 07-Mar-16 08-Jul-15 14-Jul-15 ZB4TETELA80 LIGHTING FIXTURE SCHEDULE APPROVAL 5 04-Apr-16 10-Apr-16 15-Jul-15 22-Jul-15 ZB4TETELS90 KNX SYSTEM RISER DIAGRAM SUBMITTAL 5 08-Mar-16 14-Mar-16 15-Jul-15 22-Jul-15 ZB4TETELA90 KNX SYSTEM RISER DIAGRAM APPROVAL 5 15-Mar-16 21-Mar-16 26-Jul-15 30-Jul-15 Light CurrentLight Current Systems 35 07-Feb-16 04-Jul-16 24-Jun-15 28-Jul-15 ZB4TETELGS40LIGHT CURRENT TYPICAL INSTALLATION DETAILS SUBMITTAL 5 03-Apr-16 07-Apr-16 24-Jun-15 30-Jun-15 ZB4TETELGA40LIGHT CURRENT TYPICAL INSTALLATION DETAILS APPROVAL 5 10-Apr-16 14-Apr-16 01-Jul-15 07-Jul-15 Fire Alarm SysFire Alarm System 15 07-Feb-16 18-Feb-16 08-Jul-15 22-Jul-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2015 2016 2017 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings_1 18-Feb-16 09:32 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 21 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 22. Activity ID Activity Name Original Duration Start Finish BL Project Start BL Project Finish ZB4TETELFS4FIRE ALARM RISER DIAGRAM SUBMITTAL 5 07-Feb-16 11-Feb-16 08-Jul-15 14-Jul-15 ZB4TETELFA4FIRE ALARM RISER DIAGRAM APPROVAL 5 14-Feb-16 18-Feb-16 15-Jul-15 22-Jul-15 Security SysteSecurity Systems 15 21-Jun-16 04-Jul-16 13-Jul-15 28-Jul-15 ZB4TETELSS4IPCCTV RISER DIAGRAM SUBMITTAL (By Others) 5 21-Jun-16 27-Jun-16 13-Jul-15 20-Jul-15 ZB4TETELSA4IPCCTV RISER DIAGRAM APPROVAL (By Others) 5 28-Jun-16 04-Jul-16 21-Jul-15 28-Jul-15 SCADA SysteSCADA System 15 12-May-16 01-Jun-16 13-Sep-15 28-Sep-15 ZB4TETEDS30 SCADA SYSTEM RISER DIAGRAM SUBMITTAL 5 12-May-16 18-May-16 13-Sep-15 17-Sep-15 ZB4TETEDA30 SCADA SYSTEM RISER DIAGRAM APPROVAL 5 26-May-16 01-Jun-16 20-Sep-15 28-Sep-15 Site LayoutSite Layout 235 16-Feb-16 14-Aug-16 27-May-15 10-Jan-16 Electrical SystemElectrical Systems 196 28-Mar-16 29-Jun-16 27-May-15 02-Dec-15 Tunnel MediumTunnel Medium Voltage Network 22 09-Jun-16 29-Jun-16 12-Nov-15 02-Dec-15 ZB4LEBEPS50 GROUND FLOOR MV NETWORK LAYOUT PLAN SUBMITTAL 10 09-Jun-16 22-Jun-16 12-Nov-15 25-Nov-15 ZB4LEBEPA50 GROUND FLOOR MV NETWORK LAYOUT PLAN APPROVAL 5 23-Jun-16 29-Jun-16 26-Nov-15 02-Dec-15 Tunnel Low VoTunnel Low Voltage Network 52 12-May-16 29-Jun-16 27-May-15 14-Jul-15 ZB4LEBELS50 GROUND FLOOR LV NETWORK LAYOUT PLAN SUBMITTAL 25 12-May-16 15-Jun-16 27-May-15 30-Jun-15 ZB4LEBELA50 GROUND FLOOR LV NETWORK LAYOUT PLAN APPROVAL 10 16-Jun-16 29-Jun-16 01-Jul-15 14-Jul-15 Power SystemPower System 52 12-May-16 29-Jun-16 06-Sep-15 28-Oct-15 ZB4LEBEPS40 GROUND FLOOR POWER SYSTEM LAYOUT PLAN SUBMITTAL 25 12-May-16 15-Jun-16 06-Sep-15 13-Oct-15 ZB4LEBEPA40 GROUND FLOOR POWER SYSTEM LAYOUT PLAN APPROVAL 10 16-Jun-16 29-Jun-16 15-Oct-15 28-Oct-15 Lighting SystemLighting System 44 28-Mar-16 11-May-16 26-Jul-15 03-Sep-15 ZB4LEBELS30 GROUND FLOOR LIGHTING SYSTEM LAYOUT PLAN SUBMITTAL 25 28-Mar-16 04-May-16 26-Jul-15 27-Aug-15 ZB4LEBELA40 GROUND FLOOR LIGHTING SYSTEM LAYOUT PLAN APPROVAL 5 05-May-16 11-May-16 30-Aug-15 03-Sep-15 SCADA SystemSCADA System 15 19-May-16 01-Jun-16 20-Sep-15 05-Oct-15 ZB4LEBEDS30 GROUND FLOOR SCADA SYSTEM LAYOUT PLAN SUBMITTAL 5 19-May-16 25-May-16 20-Sep-15 28-Sep-15 ZB4LEBEDA30 GROUND FLOOR SCADA SYSTEM LAYOUT PLAN APPROVAL 5 26-May-16 01-Jun-16 29-Sep-15 05-Oct-15 Composite DrawComposite Drawing 22 30-Jun-16 24-Jul-16 03-Dec-15 24-Dec-15 ZB4LEBCS30 SITE LAY OUT COMPOSITE LAYOUT PLAN SUBMITTAL 10 30-Jun-16 17-Jul-16 03-Dec-15 16-Dec-15 ZB4LEBCA30 SITE LAY OUT COMPOSITE LAYOUT PLAN APPROVAL 5 18-Jul-16 24-Jul-16 17-Dec-15 24-Dec-15 General Shop DrGeneral Shop Drawings 190 16-Feb-16 14-Aug-16 08-Jul-15 10-Jan-16 Electrical SysteElectrical Systems 190 16-Feb-16 14-Aug-16 08-Jul-15 10-Jan-16 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2015 2016 2017 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings_1 18-Feb-16 09:32 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 22 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 23. Activity ID Activity Name Original Duration Start Finish BL Project Start BL Project Finish ZB4LETEGS50 ELECTRICAL INSTALLATION DETAILS SUBMITTAL 25 28-Mar-16 04-May-16 26-Jul-15 27-Aug-15 ZB4LETEGA50 ELECTRICAL INSTALLATION DETAILS APPROVAL 5 26-May-16 01-Jun-16 30-Aug-15 03-Sep-15 Power SystemPower System 15 01-Aug-16 14-Aug-16 27-Dec-15 10-Jan-16 ZB4LETEPS80 POWER S.L.D AND PANEL BOARD SCHEDULE SUBMITTAL 5 01-Aug-16 07-Aug-16 27-Dec-15 31-Dec-15 ZB4LETEPA80 POWER S.L.D AND PANEL BOARD SCHEDULE APPROVAL 5 08-Aug-16 14-Aug-16 03-Jan-16 10-Jan-16 Lighting SystLighting System 37 16-Feb-16 10-Apr-16 08-Jul-15 13-Aug-15 ZB4LETELS100 LIGHTING FIXTURE SCHEDULE SUBMITTAL 10 16-Feb-16 29-Feb-16 08-Jul-15 22-Jul-15 ZB4LETELA100 LIGHTING FIXTURE SCHEDULE APPROVAL 5 04-Apr-16 10-Apr-16 26-Jul-15 30-Jul-15 ZB4LETELS110 LIGHTING FIXTURES DETAILS ON STREET SECTIONS SUBMITTAL 10 01-Mar-16 14-Mar-16 26-Jul-15 06-Aug-15 ZB4LETELA110 LIGHTING FIXTURES DETAILS ON STREET SECTIONS APPROVAL 5 15-Mar-16 21-Mar-16 09-Aug-15 13-Aug-15 SCADA SysteSCADA System 52 11-Apr-16 01-Jun-16 13-Sep-15 04-Nov-15 ZB4LETEDS40 SCADA SYSTEM HAND HOLE LAYOUT SUBMITTAL 25 11-Apr-16 18-May-16 13-Sep-15 21-Oct-15 ZB4LETEDA40 SCADA SYSTEM HAND HOLE LAYOUTAPPROVAL 10 19-May-16 01-Jun-16 22-Oct-15 04-Nov-15 MaterialsMaterials 322 19-Nov-15 17-Nov-16 27-May-15 02-Apr-16 Building B4 - A (MBuilding B4 - A (Mechanical Utilities) 292 19-Nov-15 17-Nov-16 27-May-15 05-Mar-16 Electrical SystemElectrical Systems 285 20-Dec-15 26-Oct-16 03-Jun-15 05-Mar-16 Power SystemPower System 285 20-Dec-15 26-Oct-16 03-Jun-15 05-Mar-16 Material SubmiMaterial Submittal 144 20-Dec-15 08-Jun-16 03-Jun-15 21-Oct-15 ZB4EEMS080 EMT Material Submittal 10 18-Jan-16 01-Feb-16 03-Jun-15 16-Jun-15 ZB4EEMS090 IMC Material Submittal 10 18-Jan-16 01-Feb-16 03-Jun-15 16-Jun-15 ZB4EEMS040 Cable Trays and Ladders Material Submittal 10 20-Dec-15 03-Jan-16 10-Jun-15 23-Jun-15 ZB4EEMS110 B4-A Building ERMU Material Submittal 10 22-Mar-16 04-Apr-16 21-Jul-15 04-Aug-15 ZB4EEMS050 LV Cables Fire Resistant Material Submittal 20 09-Feb-16 07-Mar-16 08-Jul-15 06-Aug-15 ZB4EEMS030 LV Cables Material Submittal 7 14-Mar-16 22-Mar-16 16-Aug-15 24-Aug-15 ZB4EEMS180 B4-A Building MCC's Material Submittal 10 14-Mar-16 27-Mar-16 12-Aug-15 25-Aug-15 ZB4EEMS120 B4-A Building Transformers Material Submittal 20 29-Feb-16 27-Mar-16 02-Aug-15 27-Aug-15 ZB4EEMS100 B4-A Building UPS Material Submittal 20 27-Mar-16 21-Apr-16 09-Aug-15 03-Sep-15 ZB4EEMS070 MV Cables Material Submittal 7 28-Mar-16 05-Apr-16 30-Aug-15 07-Sep-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2015 2016 2017 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings_1 18-Feb-16 09:32 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 23 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 24. Activity ID Activity Name Original Duration Start Finish BL Project Start BL Project Finish ZB4EEMS150 B4-A Building EMDB & EDB Material Submittal 10 28-Mar-16 10-Apr-16 30-Aug-15 10-Sep-15 ZB4EEMS160 B4-A Building Distribution Panels Material Submittal 10 04-Apr-16 17-Apr-16 30-Aug-15 10-Sep-15 ZB4EEMS170 B4-A Building Bus Bar Material Submittal 10 29-Mar-16 11-Apr-16 30-Aug-15 10-Sep-15 ZB4EEMS060 LV Earthing Cables Material Submittal 20 29-Mar-16 26-Apr-16 23-Aug-15 17-Sep-15 ZB4EEMS130 Disconnecting Switch Material Submittal 20 27-Mar-16 21-Apr-16 23-Aug-15 17-Sep-15 ZB4EEMS140 Wiring Devices Material Submittal 20 27-Mar-16 21-Apr-16 23-Aug-15 17-Sep-15 ZB4EEMS190 B4-A Building VSD Material Submittal 20 12-May-16 08-Jun-16 20-Sep-15 21-Oct-15 ZB4EEMS200 B4-A Building Soft Starter Material Submittal 20 12-May-16 08-Jun-16 20-Sep-15 21-Oct-15 Material ApproMaterial Approvals 136 04-Jan-16 15-Jun-16 17-Jun-15 28-Oct-15 ZB4EEMA080 EMT Material Approval 5 02-Feb-16 08-Feb-16 17-Jun-15 23-Jun-15 ZB4EEMA090 IMC Material Approval 5 02-Feb-16 08-Feb-16 17-Jun-15 23-Jun-15 ZB4EEMA040 Cable Trays and Ladders Material Approval 5 04-Jan-16 11-Jan-16 24-Jun-15 30-Jun-15 ZB4EEMA110 B4-A Building ERMU Material Approval 5 05-Apr-16 11-Apr-16 05-Aug-15 11-Aug-15 ZB4EEMA050 LV Cables Fire Resistant Material Approval 5 08-Mar-16 14-Mar-16 09-Aug-15 13-Aug-15 ZB4EEMA030 LV Cables Material Approval 5 23-Mar-16 29-Mar-16 25-Aug-15 31-Aug-15 ZB4EEMA180 B4-A Building MCC's Material Approval 5 28-Mar-16 03-Apr-16 26-Aug-15 01-Sep-15 ZB4EEMA120 B4-A Building Transformers Material Approval 5 28-Mar-16 03-Apr-16 30-Aug-15 03-Sep-15 ZB4EEMA100 B4-A Building UPS Material Approval 5 24-Apr-16 03-May-16 06-Sep-15 10-Sep-15 ZB4EEMA070 MV Cables Material Approval 5 20-Apr-16 27-Apr-16 08-Sep-15 14-Sep-15 ZB4EEMA150 B4-A Building EMDB & EDB Material Approval 5 11-Apr-16 17-Apr-16 13-Sep-15 17-Sep-15 ZB4EEMA160 B4-A Building Distribution Panels Material Approval 5 18-Apr-16 24-Apr-16 13-Sep-15 17-Sep-15 ZB4EEMA170 B4-A Building Bus Bar Material Approval 5 12-Apr-16 18-Apr-16 13-Sep-15 17-Sep-15 ZB4EEMA060 LV Earthing Cables Material Approval 5 27-Apr-16 05-May-16 20-Sep-15 28-Sep-15 ZB4EEMA130 Disconnecting Switch Material Approval 5 26-Apr-16 04-May-16 20-Sep-15 28-Sep-15 ZB4EEMA140 Wiring Devices Material Approval 5 26-Apr-16 04-May-16 20-Sep-15 28-Sep-15 ZB4EEMA190 B4-A Building VSD Material Approval 5 09-Jun-16 15-Jun-16 22-Oct-15 28-Oct-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2015 2016 2017 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings_1 18-Feb-16 09:32 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 24 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 25. Activity ID Activity Name Original Duration Start Finish BL Project Start BL Project Finish ZB4EEMA200 B4-A Building Soft Starter Material Approval 5 09-Jun-16 15-Jun-16 22-Oct-15 28-Oct-15 Material PO'sMaterial PO's 170 16-Feb-16 02-Aug-16 01-Jul-15 13-Dec-15 ZB4EEMP080 EMT Material PO 5 16-Feb-16 22-Feb-16 01-Jul-15 07-Jul-15 ZB4EEMP090 IMC Material PO 5 16-Feb-16 22-Feb-16 01-Jul-15 07-Jul-15 ZB4EEMP040 Cable Trays and Ladders Material PO 10 29-Feb-16 13-Mar-16 15-Jul-15 30-Jul-15 ZB4EEMP110 B4-A Building ERMU Material PO 10 12-Apr-16 26-Apr-16 12-Aug-15 25-Aug-15 ZB4EEMP030 LV Cables Material PO 10 30-Mar-16 12-Apr-16 01-Sep-15 14-Sep-15 ZB4EEMP180 B4-A Building MCC's Material PO 10 04-Apr-16 17-Apr-16 02-Sep-15 15-Sep-15 ZB4EEMP050 LV Cables Fire Resistant Material PO 10 05-Apr-16 18-Apr-16 06-Sep-15 17-Sep-15 ZB4EEMP0300 Power Circuits Cables and Wires PO 5 22-Mar-16 28-Mar-16 13-Sep-15 17-Sep-15 ZB4EEMP150 B4-A Building EMDB & EDB Material PO 10 18-Apr-16 04-May-16 20-Sep-15 05-Oct-15 ZB4EEMP160 B4-A Building Distribution Panels Material PO 10 26-Apr-16 11-May-16 20-Sep-15 05-Oct-15 ZB4EEMP170 B4-A Building Bus Bar Material PO 10 19-Apr-16 05-May-16 20-Sep-15 05-Oct-15 ZB4EEMP130 Disconnecting Switch Material PO 10 05-May-16 18-May-16 29-Sep-15 13-Oct-15 ZB4EEMP140 Wiring Devices Material PO 10 05-May-16 18-May-16 29-Sep-15 13-Oct-15 ZB4EEMP120 B4-A Building Transformers Material PO 10 09-May-16 22-May-16 11-Oct-15 25-Oct-15 ZB4EEMP100 B4-A Building UPS Material PO 10 05-Jun-16 16-Jun-16 19-Oct-15 01-Nov-15 ZB4EEMP070 MV Cables Material PO 10 01-Jun-16 14-Jun-16 21-Oct-15 03-Nov-15 ZB4EEMP060 LV Earthing Cables Material PO 10 07-Jun-16 20-Jun-16 02-Nov-15 15-Nov-15 ZB4EEMP190 B4-A Building VSD Material PO 10 20-Jul-16 02-Aug-16 30-Nov-15 13-Dec-15 ZB4EEMP200 B4-A Building Soft Starter Material PO 10 20-Jul-16 02-Aug-16 30-Nov-15 13-Dec-15 Material DeliveMaterial Delivery at Site 247 23-Feb-16 26-Oct-16 08-Jul-15 05-Mar-16 ZB4EEMD080 EMT Material Delivery 10 23-Feb-16 05-Mar-16 08-Jul-15 20-Jul-15 ZB4EEMD090 IMC Material Delivery 10 23-Feb-16 05-Mar-16 08-Jul-15 20-Jul-15 ZB4EEMD0300 Power Circuits Cables and Wires Partial Delivery 52 23-Apr-16 25-Jun-16 19-Sep-15 22-Nov-15 ZB4EEMD030 LV Cables Material Delivery 60 13-Apr-16 25-Jun-16 15-Sep-15 28-Nov-15 ZB4EEMD110 B4-A Building ERMU Material Delivery 78 27-Apr-16 01-Aug-16 26-Aug-15 29-Nov-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2015 2016 2017 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings_1 18-Feb-16 09:32 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 25 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 26. Activity ID Activity Name Original Duration Start Finish BL Project Start BL Project Finish ZB4EEMD180 B4-A Building MCC's Material Delivery 70 18-Apr-16 13-Jul-16 16-Sep-15 10-Dec-15 ZB4EEMD160 B4-A Building Distribution Panels Material Delivery 60 12-May-16 24-Jul-16 07-Oct-15 16-Dec-15 ZB4EEMD040 Cable Trays and Ladders Material Partial Delivery 120 14-Mar-16 07-Aug-16 01-Aug-15 22-Dec-15 ZB4EEMD120 B4-A Building Transformers Material Delivery 60 23-May-16 03-Aug-16 26-Oct-15 04-Jan-16 ZB4EEMD050 LV Cables Fire Resistant Material Delivery 90 19-Apr-16 08-Aug-16 19-Sep-15 06-Jan-16 ZB4EEMD150 B4-A Building EMDB & EDB Material Delivery 78 05-May-16 07-Aug-16 07-Oct-15 09-Jan-16 ZB4EEMD170 B4-A Building Bus Bar Material Delivery 78 08-May-16 09-Aug-16 07-Oct-15 09-Jan-16 ZB4EEMD070 MV Cables Material Delivery 60 15-Jun-16 27-Aug-16 04-Nov-15 14-Jan-16 ZB4EEMD130 Disconnecting Switch Material Delivery 78 19-May-16 21-Aug-16 15-Oct-15 16-Jan-16 ZB4EEMD140 Wiring Devices Material Delivery 78 19-May-16 21-Aug-16 15-Oct-15 16-Jan-16 ZB4EEMD060 LV Earthing Cables Material Partial Delivery 60 21-Jun-16 01-Sep-16 16-Nov-15 27-Jan-16 ZB4EEMD190 B4-A Building VSD Material Delivery 60 03-Aug-16 17-Oct-16 14-Dec-15 24-Feb-16 ZB4EEMD200 B4-A Building Soft Starter Material Delivery 60 03-Aug-16 17-Oct-16 14-Dec-15 24-Feb-16 ZB4EEMD100 B4-A Building UPS Material Delivery 104 19-Jun-16 26-Oct-16 02-Nov-15 05-Mar-16 Lighting SystemLighting System 157 15-Mar-16 22-Aug-16 16-Aug-15 16-Jan-16 Material SubmiMaterial Submittal 36 15-Mar-16 11-May-16 16-Aug-15 17-Sep-15 ZB4EEMS210 B4 Buildings Lighting Fixtures Material Submittal 20 11-Apr-16 11-May-16 16-Aug-15 10-Sep-15 ZB4EEMS220 B4 Buildings CENTRAL MONITORING SYSTEM Material Submittal 20 15-Mar-16 11-Apr-16 16-Aug-15 10-Sep-15 ZB4EEMS230 B4 Buildings KNX/EIP SYSTEM Material Submittal 20 22-Mar-16 18-Apr-16 23-Aug-15 17-Sep-15 Material ApproMaterial Approvals 22 12-Apr-16 05-Jun-16 13-Sep-15 05-Oct-15 ZB4EEMA210 B4 Buildings Lighting Fixtures Material Approval 10 23-May-16 05-Jun-16 13-Sep-15 28-Sep-15 ZB4EEMA220 B4 Buildings CENTRAL MONITORING SYSTEM Material Approval 10 12-Apr-16 26-Apr-16 13-Sep-15 28-Sep-15 ZB4EEMA230 B4 Buildings KNX/EIP SYSTEM Material Approval 10 19-Apr-16 05-May-16 20-Sep-15 05-Oct-15 Material PO'sMaterial PO's 52 11-Apr-16 27-Jun-16 13-Sep-15 04-Nov-15 ZB4EEMP240 B4A Building Lighting Wires Material PO 10 11-Apr-16 24-Apr-16 13-Sep-15 28-Sep-15 ZB4EEMP210 B4A Building Lighting Fixtures Material PO 10 14-Jun-16 27-Jun-16 08-Oct-15 22-Oct-15 ZB4EEMP220 B4A Building CENTRAL MONITORING SYSTEM Material PO 10 15-May-16 26-May-16 15-Oct-15 28-Oct-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2015 2016 2017 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings_1 18-Feb-16 09:32 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 26 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 27. Activity ID Activity Name Original Duration Start Finish BL Project Start BL Project Finish ZB4EEMP230 B4A Building KNX/EIP SYSTEM Material PO 10 22-May-16 02-Jun-16 22-Oct-15 04-Nov-15 Material DeliveMaterial Delivery at Site 112 28-May-16 22-Aug-16 29-Sep-15 16-Jan-16 ZB4EEMD240 B4A Building Lighting Wires Material Partial Delivery 10 14-Jun-16 25-Jun-16 29-Sep-15 11-Oct-15 ZB4EEMD210 B4A Building Lighting Fixtures Material Delivery 45 28-Jun-16 22-Aug-16 24-Oct-15 14-Dec-15 ZB4EEMD220 B4A Building CENTRAL MONITORING SYSTEM Material Delivery 65 28-May-16 14-Aug-16 29-Oct-15 14-Jan-16 ZB4EEMD230 B4A Building KNX/EIP SYSTEM Material Delivery 60 05-Jun-16 16-Aug-16 05-Nov-15 16-Jan-16 Cable Tray SysteCable Tray System 179 08-May-16 14-Aug-16 15-Jul-15 05-Jan-16 Material PO'sMaterial PO's 91 08-May-16 23-Jun-16 15-Jul-15 13-Oct-15 ZB4EEMP250 Cable Trays and Ladders For Equipments Material PO 10 12-Jun-16 23-Jun-16 15-Jul-15 30-Jul-15 ZB4EEMP260 LV Cables For Equipments Material PO 10 09-May-16 22-May-16 01-Sep-15 14-Sep-15 ZB4EEMP270 LV Earthing For Equipments Cables Material PO 10 08-May-16 19-May-16 29-Sep-15 13-Oct-15 Material DeliveMaterial Delivery at Site 164 22-May-16 14-Aug-16 01-Aug-15 05-Jan-16 ZB4EEMD250 Cable Trays and Ladders Material Delivery 10 25-Jun-16 07-Jul-16 01-Aug-15 11-Aug-15 ZB4EEMD260 LV Cables Material Delivery 60 23-May-16 03-Aug-16 15-Sep-15 28-Nov-15 ZB4EEMD270 LV Earthing Cables Material Delivery 70 22-May-16 14-Aug-16 15-Oct-15 05-Jan-16 Earthing SystemEarthing System 206 09-Feb-16 25-Aug-16 10-Jun-15 27-Dec-15 Material SubmiMaterial Submittal 30 09-Feb-16 07-Mar-16 10-Jun-15 07-Jul-15 ZB4EEMS010 Earthing System Material Submittal 20 09-Feb-16 07-Mar-16 10-Jun-15 07-Jul-15 Material ApproMaterial Approvals 15 08-Mar-16 21-Mar-16 08-Jul-15 22-Jul-15 ZB4EEMA010 Earthing System Material Approval 10 08-Mar-16 21-Mar-16 08-Jul-15 22-Jul-15 Material PO'sMaterial PO's 15 21-Apr-16 09-May-16 25-Aug-15 07-Sep-15 ZB4EEMP010 Earthing System Material PO 10 21-Apr-16 09-May-16 25-Aug-15 07-Sep-15 Material DeliveMaterial Delivery at Site 112 10-May-16 25-Aug-16 08-Sep-15 27-Dec-15 ZB4EEMD010 Earthing System Material Delivery 90 10-May-16 25-Aug-16 08-Sep-15 27-Dec-15 Lightning SystemLightning System 205 03-Feb-16 18-Aug-16 10-Jun-15 26-Dec-15 Material SubmiMaterial Submittal 30 03-Feb-16 01-Mar-16 10-Jun-15 07-Jul-15 ZB4EEMS020 LIGHTNING System Material Submittal 20 03-Feb-16 01-Mar-16 10-Jun-15 07-Jul-15 Material ApproMaterial Approvals 15 02-Mar-16 15-Mar-16 08-Jul-15 22-Jul-15 ZB4EEMA020 LIGHTNING System Material Approval 10 02-Mar-16 15-Mar-16 08-Jul-15 22-Jul-15 Material PO'sMaterial PO's 14 30-Mar-16 12-Apr-16 09-Aug-15 20-Aug-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2015 2016 2017 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings_1 18-Feb-16 09:32 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 27 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 28. Activity ID Activity Name Original Duration Start Finish BL Project Start BL Project Finish ZB4EEMP020 LIGHTNING System Material PO 10 30-Mar-16 12-Apr-16 09-Aug-15 20-Aug-15 Material DeliveMaterial Delivery at Site 130 13-Apr-16 18-Aug-16 22-Aug-15 26-Dec-15 ZB4EEMD020 LIGHTNING System Material Delivery 104 13-Apr-16 18-Aug-16 22-Aug-15 26-Dec-15 Light Current SyLight Current Systems 156 21-Feb-16 18-Aug-16 26-Jul-15 22-Dec-15 Fire Alarm SystFire Alarm System 156 21-Feb-16 18-Aug-16 26-Jul-15 22-Dec-15 Material SubmMaterial Submittal 29 21-Feb-16 17-Mar-16 26-Jul-15 20-Aug-15 ZB4EEMS240 Fire Alarm System Material Submittal 20 21-Feb-16 17-Mar-16 26-Jul-15 20-Aug-15 Material ApprMaterial Approvals 14 20-Mar-16 31-Mar-16 23-Aug-15 03-Sep-15 ZB4EEMA240 Fire Alarm System Material Approval 10 20-Mar-16 31-Mar-16 23-Aug-15 03-Sep-15 Material PO'sMaterial PO's 14 03-Apr-16 16-May-16 06-Sep-15 17-Sep-15 ZB4EEMP280 Fire Alarm System Devices Material PO 10 03-Apr-16 14-Apr-16 06-Sep-15 17-Sep-15 ZB4EEMP290 Fire Alarm System Fire Alarm Cable Material PO 10 03-Apr-16 14-Apr-16 06-Sep-15 17-Sep-15 ZB4EEMP300 Fire Alarm System FACP Material PO 10 03-May-16 16-May-16 06-Sep-15 17-Sep-15 Material DelivMaterial Delivery at Site 97 17-Apr-16 18-Aug-16 19-Sep-15 22-Dec-15 ZB4EEMD280 Fire Alarm System Devices Material Delivery 78 17-Apr-16 21-Jul-16 19-Sep-15 22-Dec-15 ZB4EEMD290 Fire Alarm System Fire Alarm Cable Material Delivery 78 17-Apr-16 21-Jul-16 19-Sep-15 22-Dec-15 ZB4EEMD300 Fire Alarm System FACP Material Delivery 78 17-May-16 18-Aug-16 19-Sep-15 22-Dec-15 SCADA SystemSCADA System 120 02-Jun-16 28-Sep-16 05-Nov-15 28-Feb-16 Material SubmiMaterial Submittal 7 02-Jun-16 08-Jun-16 05-Nov-15 11-Nov-15 ZB4EEMS250 SCADA System Material Submittal 5 02-Jun-16 08-Jun-16 05-Nov-15 11-Nov-15 Material ApproMaterial Approvals 7 09-Jun-16 15-Jun-16 12-Nov-15 18-Nov-15 ZB4EEMA250 SCADA System Material Approval 5 09-Jun-16 15-Jun-16 12-Nov-15 18-Nov-15 Material PO'sMaterial PO's 7 16-Jun-16 22-Jun-16 19-Nov-15 25-Nov-15 ZB4EEMP310 SCADA System Material PO 5 16-Jun-16 22-Jun-16 19-Nov-15 25-Nov-15 Material DeliveMaterial Delivery at Site 97 23-Jun-16 28-Sep-16 26-Nov-15 28-Feb-16 ZB4EEMD310 SCADA System Material Delivery 78 23-Jun-16 28-Sep-16 26-Nov-15 28-Feb-16 Mechanical SystMechanical Systems 265 19-Nov-15 17-Nov-16 27-May-15 08-Feb-16 HVAC SystemHVAC System 260 10-Dec-15 28-Sep-16 27-May-15 04-Feb-16 Material SubmiMaterial Submittal 155 10-Dec-15 15-Jun-16 27-May-15 25-Oct-15 ZB4EEMS390 Black welded (ERW) steel piping Material Submittal 5 30-Dec-15 05-Jan-16 01-Jun-15 07-Jun-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2015 2016 2017 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings_1 18-Feb-16 09:32 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 28 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 29. Activity ID Activity Name Original Duration Start Finish BL Project Start BL Project Finish ZB4EEMS440 Variable Air Volume (VAV) Boxes Material Submittal 15 10-Dec-15 31-Dec-15 27-May-15 16-Jun-15 ZB4EEMS260 Chillers Material Submittal 12 03-Jan-16 19-Jan-16 04-Jun-15 21-Jun-15 ZB4EEMS270 Cooling Towers Material Submittal 10 27-Jan-16 09-Feb-16 28-Jun-15 09-Jul-15 ZB4EEMS310 AHU Material Submittal 12 10-Jan-16 26-Jan-16 28-Jun-15 13-Jul-15 ZB4EEMS410 Chilled Water Valves Material Submittal 22 13-Jan-16 14-Feb-16 14-Jun-15 13-Jul-15 ZB4EEMS380 Child pipe hangers and support Material Submittal 15 31-Jan-16 18-Feb-16 28-Jun-15 19-Jul-15 ZB4EEMS280 Child Water Pumps Material Submittal 22 17-Jan-16 16-Feb-16 02-Jul-15 04-Aug-15 ZB4EEMS315 Expansion Tanks Material Submittal 12 25-Feb-16 13-Mar-16 19-Jul-15 04-Aug-15 ZB4EEMS370 Black seamless steel piping Material Submittal 15 17-Feb-16 08-Mar-16 19-Jul-15 09-Aug-15 ZB4EEMS300 Heat Exchangers Material Submittal 22 04-Feb-16 06-Mar-16 08-Jul-15 10-Aug-15 ZB4EEMS320 Metal Sheet Duct Material Submittal 15 07-Feb-16 25-Feb-16 26-Jul-15 13-Aug-15 ZB4EEMS400 UPVC piping (16 bar) Material Submittal 22 30-Mar-16 03-May-16 26-Jul-15 24-Aug-15 ZB4EEMS340 Chimney Black Steel Sheet Material Sample Submittal 18 20-Mar-16 12-Apr-16 02-Aug-15 25-Aug-15 ZB4EEMS330 FD & VD Material Submittal 22 03-Mar-16 03-Apr-16 02-Aug-15 31-Aug-15 ZB4EEMS350 Fire Smoke Dampers Material Submittal 22 07-Mar-16 05-Apr-16 09-Aug-15 07-Sep-15 ZB4EEMS360 Duct Insulation Material Submittal 22 07-Apr-16 11-May-16 11-Aug-15 09-Sep-15 ZB4EEMS430 Air Separators Material Submittal 22 22-Mar-16 20-Apr-16 16-Aug-15 14-Sep-15 ZB4EEMS420 Chilled Water Piping Insulation Material Submittal 22 22-Mar-16 20-Apr-16 23-Aug-15 21-Sep-15 ZB4EEMS450 Air Outlets Material Submittal 22 28-Mar-16 27-Apr-16 30-Aug-15 30-Sep-15 ZB4EEMS460 Water Treatment and Chemical Cleaning System Material Submittal 22 10-Apr-16 12-May-16 06-Sep-15 08-Oct-15 ZB4EEMS470 Over Head Crane Material Submittal 22 03-May-16 01-Jun-16 06-Sep-15 08-Oct-15 ZB4EEMS480 Monorail Crane Material Submittal 22 17-May-16 15-Jun-16 06-Sep-15 08-Oct-15 ZB4EEMS290 Testing, Balancing & Commisioning system Third Part Submittal 22 19-Apr-16 23-May-16 20-Sep-15 25-Oct-15 Material ApproMaterial Approvals 150 03-Jan-16 22-Jun-16 08-Jun-15 01-Nov-15 ZB4EEMA390 Black welded (ERW) steel piping Material Approval 5 20-Jan-16 27-Jan-16 08-Jun-15 14-Jun-15 ZB4EEMA440 Variable Air Volume (VAV) Boxes Material Approval 5 03-Jan-16 10-Jan-16 17-Jun-15 23-Jun-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2015 2016 2017 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings_1 18-Feb-16 09:32 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 29 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 30. Activity ID Activity Name Original Duration Start Finish BL Project Start BL Project Finish ZB4EEMA260 Chillers System Material Approval 5 20-Jan-16 27-Jan-16 22-Jun-15 28-Jun-15 ZB4EEMA270 Cooling Towers System Material Approval 5 10-Feb-16 16-Feb-16 12-Jul-15 19-Jul-15 ZB4EEMA310 AHU System Material Approval 5 27-Jan-16 02-Feb-16 14-Jul-15 21-Jul-15 ZB4EEMA410 Chilled Water Valves Material Approval 5 10-Mar-16 16-Mar-16 14-Jul-15 21-Jul-15 ZB4EEMA380 Child pipe hangers and support Material Approval 5 27-Mar-16 31-Mar-16 20-Jul-15 27-Jul-15 ZB4EEMA280 Child Water Pumps Material Approval 5 17-Feb-16 23-Feb-16 05-Aug-15 11-Aug-15 ZB4EEMA315 Expansion Tanks Material Approval 5 14-Mar-16 20-Mar-16 05-Aug-15 11-Aug-15 ZB4EEMA370 Black seamless steel piping Material Approval 5 03-Apr-16 07-Apr-16 10-Aug-15 16-Aug-15 ZB4EEMA300 Heat Exchangers System Material Approval 5 07-Mar-16 13-Mar-16 11-Aug-15 17-Aug-15 ZB4EEMA320 Metal Sheet Duct System Material Approval 5 28-Feb-16 03-Mar-16 16-Aug-15 20-Aug-15 ZB4EEMA400 UPVC piping (16 bar) Material Approval 5 04-May-16 10-May-16 25-Aug-15 31-Aug-15 ZB4EEMA340 Chimney Black Steel Sheet Material Sample Approval 5 13-Apr-16 19-Apr-16 26-Aug-15 01-Sep-15 ZB4EEMA330 FD & VD Material Approval 5 05-Apr-16 11-Apr-16 01-Sep-15 07-Sep-15 ZB4EEMA350 Fire Smoke Dampers Material Approval 5 07-Apr-16 13-Apr-16 08-Sep-15 14-Sep-15 ZB4EEMA360 Duct Insulation Material Approval 5 12-May-16 18-May-16 10-Sep-15 16-Sep-15 ZB4EEMA430 Air Separators Material Approval 5 21-Apr-16 28-Apr-16 15-Sep-15 21-Sep-15 ZB4EEMA420 Chilled Water Piping Insulation Material Approval 5 27-Apr-16 05-May-16 22-Sep-15 30-Sep-15 ZB4EEMA450 Air Outlets Material Approval 5 28-Apr-16 08-May-16 01-Oct-15 08-Oct-15 ZB4EEMA460 Water Treatment and Chemical Cleaning System Material Approval 5 15-May-16 19-May-16 11-Oct-15 18-Oct-15 ZB4EEMA470 Over Head Crane Material Approval 5 02-Jun-16 08-Jun-16 11-Oct-15 18-Oct-15 ZB4EEMA480 Monorail Crane Material Approval 5 16-Jun-16 22-Jun-16 11-Oct-15 18-Oct-15 ZB4EEMA290 Testing, Balancing & Commisioning system Third Part Approval 5 24-May-16 30-May-16 26-Oct-15 01-Nov-15 Material PO'sMaterial PO's 142 28-Jan-16 10-Jul-16 15-Jun-15 01-Nov-15 ZB4EEMP450 Black welded (ERW) steel piping Material PO 10 28-Jan-16 10-Feb-16 15-Jun-15 28-Jun-15 ZB4EEMP320 Chillers System Material PO 10 28-Jan-16 10-Feb-16 29-Jun-15 12-Jul-15 ZB4EEMP330 Cooling Towers System Material PO 10 17-Feb-16 01-Mar-16 20-Jul-15 03-Aug-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2015 2016 2017 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings_1 18-Feb-16 09:32 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 30 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 31. Activity ID Activity Name Original Duration Start Finish BL Project Start BL Project Finish ZB4EEMP370 AHU System Material PO 10 03-Feb-16 16-Feb-16 22-Jul-15 05-Aug-15 ZB4EEMP470 Chilled Water Valves Material PO 10 17-Mar-16 30-Mar-16 22-Jul-15 05-Aug-15 ZB4EEMP440 Child pipe hangers and support Material PO 10 17-Apr-16 03-May-16 28-Jul-15 10-Aug-15 ZB4EEMP500 Variable Air Volume (VAV) Boxes Material PO 10 15-Mar-16 28-Mar-16 28-Jul-15 10-Aug-15 ZB4EEMP340 Child Water Pumps Material PO 10 24-Feb-16 08-Mar-16 12-Aug-15 25-Aug-15 ZB4EEMP315 Expansion Tanks Material PO 10 21-Mar-16 03-Apr-16 12-Aug-15 25-Aug-15 ZB4EEMP430 Black seamless steel piping Material PO 10 18-May-16 31-May-16 17-Aug-15 30-Aug-15 ZB4EEMP360 Heat Exchangers System Material PO 10 14-Mar-16 27-Mar-16 18-Aug-15 31-Aug-15 ZB4EEMP380 Metal Sheet Duct System Material PO 10 27-Apr-16 12-May-16 23-Aug-15 03-Sep-15 ZB4EEMP460 UPVC piping (16 bar) Material PO 10 11-May-16 24-May-16 01-Sep-15 14-Sep-15 ZB4EEMP390 FD & VD Material PO 10 12-Apr-16 26-Apr-16 08-Sep-15 21-Sep-15 ZB4EEMP410 Fire Smoke Dampers Material PO 10 14-Apr-16 28-Apr-16 15-Sep-15 30-Sep-15 ZB4EEMP420 Duct Insulation Material PO 10 19-May-16 01-Jun-16 17-Sep-15 04-Oct-15 ZB4EEMP490 Air Separators Material PO 10 03-May-16 16-May-16 22-Sep-15 08-Oct-15 ZB4EEMP480 Chilled Water Piping Insulation Material PO 10 25-May-16 07-Jun-16 01-Oct-15 18-Oct-15 ZB4EEMP400 Chimney Black Steel Sheet Material PO 10 25-May-16 07-Jun-16 07-Oct-15 21-Oct-15 ZB4EEMP510 Air Outlets Material PO 10 09-May-16 22-May-16 11-Oct-15 25-Oct-15 ZB4EEMP520 Water Treatment and Chemical Cleaning System Material PO 10 22-May-16 02-Jun-16 19-Oct-15 01-Nov-15 ZB4EEMP530 Over Head Crane Material PO 10 09-Jun-16 22-Jun-16 19-Oct-15 01-Nov-15 ZB4EEMP540 Monorail Crane Material PO 10 23-Jun-16 10-Jul-16 19-Oct-15 01-Nov-15 Material DeliveMaterial Delivery at Site 225 11-Feb-16 28-Sep-16 29-Jun-15 04-Feb-16 ZB4EEMD440 Child pipe hangers and support Material ( Partial )Delivery 36 04-May-16 14-Jun-16 11-Aug-15 21-Sep-15 ZB4EEMD450 Black welded (ERW) steel piping Material ( Partial )Delivery 104 11-Feb-16 14-Jun-16 29-Jun-15 03-Nov-15 ZB4EEMD330 Cooling Towers System Material Delivery 78 02-Mar-16 04-Jun-16 04-Aug-15 07-Nov-15 ZB4EEMD370 AHU System Material Delivery 78 17-Feb-16 21-May-16 06-Aug-15 09-Nov-15 ZB4EEMD320 Chillers Material Delivery 104 11-Feb-16 14-Jun-16 13-Jul-15 17-Nov-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2015 2016 2017 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings_1 18-Feb-16 09:32 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 31 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 32. Activity ID Activity Name Original Duration Start Finish BL Project Start BL Project Finish ZB4EEMD380 Metal Sheet Duct System Partial Material Delivery / Fabrication 65 14-May-16 31-Jul-16 05-Sep-15 23-Nov-15 ZB4EEMD315 Expansion Tanks Material Delivery 78 04-Apr-16 09-Jul-16 26-Aug-15 29-Nov-15 ZB4EEMD430 Black seamless steel piping Material ( Partial )Delivery 78 01-Jun-16 03-Sep-16 31-Aug-15 03-Dec-15 ZB4EEMD420 Duct Insulation Material Delivery 52 02-Jun-16 04-Aug-16 05-Oct-15 06-Dec-15 ZB4EEMD470 Chilled Water Valves Material ( Partial )Delivery 104 31-Mar-16 06-Aug-16 06-Aug-15 09-Dec-15 ZB4EEMD400 Chimney Material Fabrication / Delivery 45 08-Jun-16 02-Aug-16 22-Oct-15 13-Dec-15 ZB4EEMD500 Variable Air Volume (VAV) Boxes Material Delivery 104 29-Mar-16 03-Aug-16 11-Aug-15 14-Dec-15 ZB4EEMD360 Heat Exchangers System Material Delivery 90 28-Mar-16 16-Jul-16 01-Sep-15 19-Dec-15 ZB4EEMD460 UPVC piping (16 bar) Material ( Partial )Delivery 78 25-May-16 27-Aug-16 15-Sep-15 19-Dec-15 ZB4EEMD390 FD & VD Material Delivery 80 27-Apr-16 03-Aug-16 22-Sep-15 29-Dec-15 ZB4EEMD340 Child Water Pumps Material Delivery 104 09-Mar-16 13-Jul-16 26-Aug-15 30-Dec-15 ZB4EEMD410 Fire Smoke Dampers Material Delivery 78 03-May-16 04-Aug-16 01-Oct-15 03-Jan-16 ZB4EEMD520 Water Treatment and Chemical Cleaning System Material Delivery On Site 60 05-Jun-16 16-Aug-16 02-Nov-15 12-Jan-16 ZB4EEMD480 Chilled Water Piping Insulation Material ( Partial ) Delivery 75 08-Jun-16 06-Sep-16 19-Oct-15 16-Jan-16 ZB4EEMD540 Monorail Crane Material Delivery On Site 65 11-Jul-16 28-Sep-16 02-Nov-15 18-Jan-16 ZB4EEMD490 Air Separators Material Delivery 90 17-May-16 01-Sep-16 10-Oct-15 26-Jan-16 ZB4EEMD510 Air Outlets Material Delivery 78 23-May-16 24-Aug-16 26-Oct-15 27-Jan-16 ZB4EEMD530 Over Head Crane Material Delivery On Site 78 23-Jun-16 28-Sep-16 02-Nov-15 03-Feb-16 ZB4EEMD350 Testing, Balancing & Commisioning system Third Part On Site 0 01-Sep-16 04-Feb-16 Fire Protection SFire Protection Systems 245 26-Nov-15 28-Aug-16 27-May-15 19-Jan-16 Material SubmiMaterial Submittal 157 26-Nov-15 02-Jun-16 27-May-15 27-Oct-15 ZB4EEMS560 Black Seamless Schedule 40 Material Submittal 10 18-Jan-16 01-Feb-16 27-May-15 09-Jun-15 ZB4EEMS580 Electrical Fire Pump Material Submittal 15 26-Nov-15 16-Dec-15 27-May-15 16-Jun-15 ZB4EEMS590 Diesel Fire Pump Material Submittal 15 26-Nov-15 16-Dec-15 27-May-15 16-Jun-15 ZB4EEMS600 Jockey Pump Material Submittal 15 26-Nov-15 16-Dec-15 27-May-15 16-Jun-15 ZB4EEMS570 VALVES Material Submittal 10 11-Apr-16 24-Apr-16 22-Jun-15 05-Jul-15 ZB4EEMS610 Water Flow Switches Material Submittal 18 01-Mar-16 24-Mar-16 22-Jun-15 15-Jul-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2015 2016 2017 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings_1 18-Feb-16 09:32 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 32 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 33. Activity ID Activity Name Original Duration Start Finish BL Project Start BL Project Finish ZB4EEMS620 Upright Sprinkler Heads Material Submittal 18 21-Mar-16 13-Apr-16 08-Jul-15 04-Aug-15 ZB4EEMS640 Fire Hose Stations Material Submittal 22 15-Mar-16 13-Apr-16 02-Aug-15 31-Aug-15 ZB4EEMS650 Dry Powder Manual Fire Extinguishers Material Submittal 22 22-Mar-16 20-Apr-16 23-Aug-15 21-Sep-15 ZB4EEMS670 Roof Manifold Material Submittal 22 31-Mar-16 04-May-16 23-Aug-15 21-Sep-15 ZB4EEMS630 CO2 System Material Submittal 12 10-May-16 25-May-16 11-Oct-15 27-Oct-15 ZB4EEMS660 Automatic Dry Powder Fire Extinguishers Material Submittal 12 18-May-16 02-Jun-16 11-Oct-15 27-Oct-15 Material ApproMaterial Approvals 150 17-Dec-15 09-Jun-16 10-Jun-15 03-Nov-15 ZB4EEMA560 Black Seamless Schedule 40 Material Approval 5 02-Feb-16 08-Feb-16 10-Jun-15 16-Jun-15 ZB4EEMA580 Electrical Fire Pump Material Approval 5 17-Dec-15 24-Dec-15 17-Jun-15 23-Jun-15 ZB4EEMA590 Diesel Fire Pump Material Approval 5 17-Dec-15 24-Dec-15 17-Jun-15 23-Jun-15 ZB4EEMA600 Jockey Pump Material Approval 5 17-Dec-15 24-Dec-15 17-Jun-15 23-Jun-15 ZB4EEMA570 VALVES Material Approval 5 26-Apr-16 04-May-16 06-Jul-15 12-Jul-15 ZB4EEMA610 Water Flow Switches Material Approval 5 27-Mar-16 31-Mar-16 19-Jul-15 26-Jul-15 ZB4EEMA620 Upright Sprinkler Heads Material Approval 5 14-Apr-16 20-Apr-16 05-Aug-15 11-Aug-15 ZB4EEMA640 Fire Hose Stations Material Approval 5 14-Apr-16 20-Apr-16 01-Sep-15 07-Sep-15 ZB4EEMA650 Dry Powder Manual Fire Extinguishers Material Approval 5 03-May-16 09-May-16 22-Sep-15 30-Sep-15 ZB4EEMA670 Roof Manifold Material Approval 5 05-May-16 11-May-16 22-Sep-15 30-Sep-15 ZB4EEMA630 CO2 System Material Approval 5 26-May-16 01-Jun-16 28-Oct-15 03-Nov-15 ZB4EEMA660 Automatic Dry Powder Fire Extinguishers Material Approval 5 05-Jun-16 09-Jun-16 28-Oct-15 03-Nov-15 Material PO'sMaterial PO's 157 09-Feb-16 23-Jun-16 17-Jun-15 17-Nov-15 ZB4EEMP560 Black Seamless Schedule 40 Material PO 10 09-Feb-16 22-Feb-16 17-Jun-15 30-Jun-15 ZB4EEMP580 Electrical Fire Pump Material PO 10 09-Feb-16 22-Feb-16 24-Jun-15 07-Jul-15 ZB4EEMP590 Diesel Fire Pump Material PO 10 09-Feb-16 22-Feb-16 24-Jun-15 07-Jul-15 ZB4EEMP600 Jockey Pump Material PO 10 09-Feb-16 22-Feb-16 24-Jun-15 07-Jul-15 ZB4EEMP570 VALVES Material PO 10 05-May-16 18-May-16 13-Jul-15 28-Jul-15 ZB4EEMP610 Water Flow Switches Material PO 10 03-Apr-16 14-Apr-16 27-Jul-15 09-Aug-15 ZB4EEMP620 Upright Sprinkler Heads Material PO 10 21-Apr-16 09-May-16 12-Aug-15 25-Aug-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2015 2016 2017 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings_1 18-Feb-16 09:32 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 33 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2