SlideShare a Scribd company logo
1 of 39
Download to read offline
Activity ID Activity Name Original
Duration
Start Finish Consultant Contractor Total
Float
Majarrah BusinessMajarrah Business Complex 164 15-Jun-15 31-Dec-15 0
Stage IStage I 164 15-Jun-15 31-Dec-15 0
M10000000 Project Data Date 0 15-Jun-15 0
M90000000 Stage 1 Ready for Operation 0 01-Dec-15 0
M90000010 Stage I Soft Opening 0 31-Dec-15 0
Plaza LevelPlaza Level 138 15-Jun-15 30-Nov-15 1
GeneralGeneral 16 25-Jun-15 14-Jul-15 83
M10000100 Sign a Contract with Fountains and Water Fall Contractor 0 25-Jun-15 C/SCG N/A 33
M10000200 Sign a Contract with Hardscape Contractor for Plaza 0 25-Jun-15 C/TB N/A 13
M10000300 Sign a Contract with Public Address Supplier for Plaza 0 25-Jun-15 C/SCG N/A 33
M10000400 Sign a Contract with CCTV Supplier for Plaza 0 25-Jun-15 C/SCG N/A 16
M10000410 Sign a Contract with External Plaza Lighting Fixture Suppl 0 02-Jul-15 C/SCG N/A 39
M10000440 Sign a Contract with Gas Company for Gas Facility 0 14-Jul-15 Client Gas 83
DesignDesign 22 15-Jun-15 09-Jul-15 33
Architectural DesArchitectural Design 10 15-Jun-15 25-Jun-15 1
M11000100 Final Architectural Design for Plaza level 10 15-Jun-15 25-Jun-15 T.B 1
Structural DesignStructural Design 12 27-Jun-15 09-Jul-15 3
M11000200 Structural Design for Demolishing works 12 27-Jun-15 09-Jul-15 HW 3
MEP DesignMEP Design 6 27-Jun-15 02-Jul-15 39
Electrical SystemsElectrical Systems 6 27-Jun-15 02-Jul-15 39
Power SystemPower System 6 27-Jun-15 02-Jul-15 37
M11000300 Power System Update for Plaza Level 6 27-Jun-15 02-Jul-15 SCG 37
Lighting SystemLighting System 6 27-Jun-15 02-Jul-15 39
M11000400 Lighting System for External Lighting By LCD 6 27-Jun-15 02-Jul-15 LCD 39
Public Address SysPublic Address System 6 27-Jun-15 02-Jul-15 39
M11000500 Public Address System Update for Plaza Level 6 27-Jun-15 02-Jul-15 SCG 39
CCTV SystemCCTV System 6 27-Jun-15 02-Jul-15 30
M11000600 CCTV System Update for Plaza Level 6 27-Jun-15 02-Jul-15 SCG 30
Data SystemData System 6 27-Jun-15 02-Jul-15 37
M11000700 Data System Update for Plaza Level 6 27-Jun-15 02-Jul-15 SCG 37
Mechanical SystemsMechanical Systems 6 27-Jun-15 02-Jul-15 35
Fire Fighting SysteFire Fighting System 6 27-Jun-15 02-Jul-15 35
M11000800 Fire Fighting System Update for Plaza Level 6 27-Jun-15 02-Jul-15 SCG 35
Plumbing SystemPlumbing System 6 27-Jun-15 02-Jul-15 26
Drainage SystemDrainage System 6 27-Jun-15 02-Jul-15 1
M11000900 Drainage System Update for Plaza Level 6 27-Jun-15 02-Jul-15 SCG 1
Irrigation SystemIrrigation System 6 27-Jun-15 02-Jul-15 24
Jun Jul Aug Sep Oct Nov Dec Jan eb
2015 2016
31-Dec-
31-Dec-
30-Nov-15, Pla
14-Jul-15, General
09-Jul-15, Design
25-Jun-15, Architectural Design
09-Jul-15, Structural Design
02-Jul-15, MEP Design
02-Jul-15, Electrical Systems
02-Jul-15, Power System
02-Jul-15, Lighting System
02-Jul-15, Public Address System
02-Jul-15, CCTV System
02-Jul-15, Data System
02-Jul-15, Mechanical Systems
02-Jul-15, Fire Fighting System
02-Jul-15, Plumbing System
02-Jul-15, Drainage System
02-Jul-15, Irrigation System
Majarrah Business Complex Classic Schedule Layout 22-Jun-15 14:36
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 1 of 39 TASK filter: All Activities
© Primavera Systems, Inc.
Activity ID Activity Name Original
Duration
Start Finish Consultant Contractor Total
Float
M110001000 Irrigation System Layout for Plaza Level 6 27-Jun-15 02-Jul-15 SCG 24
Fountains and WateFountains and Water Fall 6 27-Jun-15 02-Jul-15 26
M110001004 Water Fall Design 6 27-Jun-15 02-Jul-15 SCG 26
M110001002 Fountains Design 6 27-Jun-15 02-Jul-15 SCG 26
Shop DrawingsShop Drawings 28 27-Jun-15 30-Jul-15 29
Architectural ShoArchitectural Shop Drawing 12 27-Jun-15 09-Jul-15 13
M110001006 Plaza Architecture Layout Shop Drawing Submittal 6 27-Jun-15 02-Jul-15 N/A 13
M110001008 Plaza Architecture Layout Shop Drawing Approval 6 04-Jul-15 09-Jul-15 T.B 13
Structural Shop DStructural Shop Drawing 16 11-Jul-15 30-Jul-15 3
M110001010 Plaza Structural Modifications Layout Submittal 10 11-Jul-15 22-Jul-15 ECIP 3
M110001012 Plaza Structural Modifications Layout Approval 6 25-Jul-15 30-Jul-15 HW 3
Electrical SystemsElectrical Systems 18 04-Jul-15 26-Jul-15 33
Power SystemPower System 12 04-Jul-15 16-Jul-15 37
M110001014 Power System for Plaza Level Submittal 6 04-Jul-15 09-Jul-15 Ofoq 37
M110001016 Power System for Plaza Level Approval 6 11-Jul-15 16-Jul-15 SCG 37
Lighting SystemLighting System 12 04-Jul-15 16-Jul-15 39
M110001018 Lighting System for External Lighting Submittal 6 04-Jul-15 09-Jul-15 Ofoq 39
M110001020 Lighting System for External Lighting Approval 6 11-Jul-15 16-Jul-15 SCG 39
Public Address SysPublic Address System 12 11-Jul-15 26-Jul-15 33
M110001022 Public Address System for External Lighting Submittal 6 11-Jul-15 16-Jul-15 Ofoq 33
M110001024 Public Address System for External Lighting Approval 6 19-Jul-15 26-Jul-15 SCG 33
CCTV SystemCCTV System 12 04-Jul-15 16-Jul-15 30
M1PS1360 CCTV System for External Lighting Submittal 6 04-Jul-15 09-Jul-15 Ofoq 30
M1PS1370 CCTV System for External Lighting Approval 6 11-Jul-15 16-Jul-15 SCG 30
Data SystemData System 12 04-Jul-15 16-Jul-15 37
M110001026 Data System for Plaza Level Submittal 6 04-Jul-15 09-Jul-15 Ofoq 37
M110001028 Data System for Plaza Level Approval 6 11-Jul-15 16-Jul-15 SCG 37
Mechanical SysteMechanical Systems 21 04-Jul-15 29-Jul-15 29
Fire Fighting SystemFire Fighting System 12 04-Jul-15 16-Jul-15 35
M110001030 Fire Fighting System for Plaza Level Submittal 6 04-Jul-15 09-Jul-15 Ofoq 35
M110001032 Fire Fighting System for Plaza Level Approval 6 11-Jul-15 16-Jul-15 SCG 35
Plumbing SystemPlumbing System 21 04-Jul-15 29-Jul-15 29
Drainage SystemDrainage System 21 04-Jul-15 29-Jul-15 24
M110001034 Drainage System for Plaza Level Submittal 6 04-Jul-15 09-Jul-15 Ofoq 1
M110001036 Drainage System for Plaza Level Approval 6 11-Jul-15 16-Jul-15 SCG 1
M110001038 Builder Work and Core drill openings for Floor drains
Submittal
3 19-Jul-15 21-Jul-15 Ofoq 24
M110001040 Builder Work and Core drill openings for Floor drains Appr 6 22-Jul-15 29-Jul-15 HW 24
Jun Jul Aug Sep Oct Nov Dec Jan eb
2015 2016
02-Jul-15, Fountains and Water Fall
30-Jul-15, Shop Drawings
09-Jul-15, Architectural Shop Drawing
30-Jul-15, Structural Shop Drawing
26-Jul-15, Electrical Systems
16-Jul-15, Power System
16-Jul-15, Lighting System
26-Jul-15, Public Address System
16-Jul-15, CCTV System
16-Jul-15, Data System
29-Jul-15, Mechanical Systems
16-Jul-15, Fire Fighting System
29-Jul-15, Plumbing System
29-Jul-15, Drainage System
Majarrah Business Complex Classic Schedule Layout 22-Jun-15 14:36
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 2 of 39 TASK filter: All Activities
© Primavera Systems, Inc.
Activity ID Activity Name Original
Duration
Start Finish Consultant Contractor Total
Float
Irrigation SystemIrrigation System 21 04-Jul-15 29-Jul-15 24
M110001042 Irrigation System Layout for Plaza Level Submittal 15 04-Jul-15 21-Jul-15 Ofoq 24
M110001044 Irrigation System Layout for Plaza Level Approval 6 22-Jul-15 29-Jul-15 SCG 24
Fountains and WateFountains and Water Fall 18 04-Jul-15 26-Jul-15 32
M110001048 Water Fall Shop drawing Submittal 12 04-Jul-15 16-Jul-15 Ofoq 27
M110001046 Fountains Shop drawing Submittal 12 04-Jul-15 16-Jul-15 Ofoq 32
M110001052 Water Fall Shop drawing Approval 6 19-Jul-15 26-Jul-15 SCG 27
M110001050 Fountains Shop drawing Approval 6 19-Jul-15 26-Jul-15 SCG 32
MaterialsMaterials 103 15-Jun-15 20-Oct-15 34
Structural MateriaStructural Materials 36 15-Jun-15 28-Jul-15 12
Structural Material SStructural Material Submittal 6 15-Jun-15 21-Jun-15 12
M110001166 Expansion Joints Submittal 6 15-Jun-15 21-Jun-15 ECIP 12
Structural Material AStructural Material Approval 6 22-Jun-15 28-Jun-15 12
M110001176 Expansion Joints Approval 6 22-Jun-15 28-Jun-15 ECIP 12
Structural Material PStructural Material P.O 6 29-Jun-15 05-Jul-15 12
M110001186 Expansion Joints PO 6 29-Jun-15 05-Jul-15 ECIP 12
Structural Material DStructural Material Delivery 18 06-Jul-15 28-Jul-15 12
M110001196 Expansion Joints Delivery to Site 18 06-Jul-15 28-Jul-15 ECIP 12
Finishing MateriaFinishing Materials 76 11-Jul-15 13-Oct-15 37
Finishing Material SFinishing Material Submittal 26 11-Jul-15 11-Aug-15 52
M110001054 Plaza Flooring Filling (M-01&M-02&M-03) Material Submi 6 11-Jul-15 16-Jul-15 N/A 13
M110001056 Plaza Walkway Filling (M-04) Material Submittal 6 11-Jul-15 16-Jul-15 N/A 61
M110001058 Plaza Driveway Filling (M-05 & M-06) Material Submittal 6 11-Jul-15 16-Jul-15 N/A 64
M110001060 Fountain Area M-07 Material Submittal 6 11-Jul-15 16-Jul-15 N/A 54
M110001062 Plaza Borders B-01 Material Submittal 6 11-Jul-15 16-Jul-15 N/A 64
M110001064 Building Borders B-02 Material Submittal 6 11-Jul-15 16-Jul-15 N/A 64
M110001068 Drive Borders B-03 Material Submittal 6 11-Jul-15 16-Jul-15 N/A 64
M110001070 Planters Copping (C-01 & C-02 & C-03) Material Submittal 6 11-Jul-15 16-Jul-15 N/A 64
M110001072 Stairs (ST-01 &ST-02&ST-03&ST-04&ST-05) Material Subm 6 11-Jul-15 16-Jul-15 N/A 70
M110001074 Loose Gravel GR-01 Material Submittal 6 11-Jul-15 16-Jul-15 N/A 72
M110001078 Pre-Cast Concrete Curb CB-01 Material Submittal 6 11-Jul-15 16-Jul-15 N/A 65
M110001080 Soft Scape Material Submittal 26 11-Jul-15 11-Aug-15 MIAC 35
Finishing Material AFinishing Material Approval 26 19-Jul-15 18-Aug-15 52
M110001082 Plaza Flooring Filling (M-01&M-02&M-03) Material Appro 6 19-Jul-15 26-Jul-15 T.B 13
M110001084 Plaza Walkway Filling (M-04) Material Approval 6 19-Jul-15 26-Jul-15 T.B 61
M110001086 Plaza Driveway Filling (M-05 & M-06) Material Approval 6 19-Jul-15 26-Jul-15 T.B 64
M110001088 Fountain Area M-07 Material Approval 6 19-Jul-15 26-Jul-15 T.B 54
M110001090 Plaza Borders B-01 Material Approval 6 19-Jul-15 26-Jul-15 T.B 64
Jun Jul Aug Sep Oct Nov Dec Jan eb
2015 2016
29-Jul-15, Irrigation System
26-Jul-15, Fountains and Water Fall
20-Oct-15, Materials
28-Jul-15, Structural Materials
21-Jun-15, Structural Material Submittal
28-Jun-15, Structural Material Approval
05-Jul-15, Structural Material P.O
28-Jul-15, Structural Material Delivery
13-Oct-15, Finishing Mat
11-Aug-15, Finishing Material Submitta
18-Aug-15, Finishing Material Appro
Majarrah Business Complex Classic Schedule Layout 22-Jun-15 14:36
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 3 of 39 TASK filter: All Activities
© Primavera Systems, Inc.
Activity ID Activity Name Original
Duration
Start Finish Consultant Contractor Total
Float
M110001092 Building Borders B-02 Material Approval 6 19-Jul-15 26-Jul-15 T.B 64
M110001094 Drive Borders B-03 Material Approval 6 19-Jul-15 26-Jul-15 T.B 64
M110001096 Planters Copping (C-01 & C-02 & C-03) Material Approval 6 19-Jul-15 26-Jul-15 T.B 64
M110001098 Stairs (ST-01 &ST-02&ST-03&ST-04&ST-05) Material Appr 6 19-Jul-15 26-Jul-15 T.B 70
M1100010100 Loose Gravel GR-01 Material Approval 6 19-Jul-15 26-Jul-15 T.B 72
M1100010102 Pre-Cast Concrete Curb CB-01 Material Approval 6 19-Jul-15 26-Jul-15 T.B 65
M1100010104 Soft Scape Material Approval 6 12-Aug-15 18-Aug-15 T.B 35
Finishing Material PFinishing Material P.O 46 27-Jul-15 17-Sep-15 35
M1100010106 Plaza Flooring Filling (M-01&M-02&M-03) Material P.O 3 27-Jul-15 29-Jul-15 N/A 13
M1100010108 Plaza Walkaway Filling (M-04) Material P.O 3 27-Jul-15 29-Jul-15 N/A 61
M11000101010 Plaza Driveway Filling (M-05 & M-06) Material P.O 3 27-Jul-15 29-Jul-15 N/A 64
M11000101012 Fountain Area M-07 Material P.O 3 27-Jul-15 29-Jul-15 N/A 54
M11000101014 Plaza Borders B-01 Material P.O 3 27-Jul-15 29-Jul-15 N/A 64
M11000101016 Building Borders B-02 Material P.O 3 27-Jul-15 29-Jul-15 N/A 64
M11000101018 Drive Borders B-03 Material P.O 3 27-Jul-15 29-Jul-15 N/A 64
M11000101020 Planters Copping (C-01 & C-02 & C-03) Material P.O 3 27-Jul-15 29-Jul-15 N/A 64
M11000101022 Stairs (ST-01 &ST-02&ST-03&ST-04&ST-05) Material P.O 3 27-Jul-15 29-Jul-15 N/A 70
M11000101024 Loose Gravel GR-01 Material P.O 3 27-Jul-15 29-Jul-15 N/A 72
M11000101026 Pre-Cast Concrete Curb CB-01 Material P.O 3 27-Jul-15 29-Jul-15 N/A 65
M11000101028 Soft Scape Material P.O 26 19-Aug-15 17-Sep-15 MIAC 35
Finishing Material DFinishing Material Delivery 61 30-Jul-15 13-Oct-15 37
M11000101030 Plaza Walkaway Filling (M-04) Material Delivery 26 30-Jul-15 29-Aug-15 N/A 61
M11000101032 Plaza Driveway Filling (M-05 & M-06) Material Delivery 26 30-Jul-15 29-Aug-15 N/A 64
M11000101034 Fountain Area M-07 Material Delivery 26 30-Jul-15 29-Aug-15 N/A 54
M11000101036 Plaza Borders B-01 Material Delivery 26 30-Jul-15 29-Aug-15 N/A 64
M11000101038 Building Borders B-02 Material Delivery 26 30-Jul-15 29-Aug-15 N/A 64
M11000101040 Drive Borders B-03 Material Delivery 26 30-Jul-15 29-Aug-15 N/A 64
M11000101042 Planters Copping (C-01 & C-02 & C-03) Material Delivery 26 30-Jul-15 29-Aug-15 N/A 64
M11000101044 Stairs (ST-01 &ST-02&ST-03&ST-04&ST-05) Material Deliv 26 30-Jul-15 29-Aug-15 N/A 70
M11000101046 Loose Gravel GR-01 Material Delivery 26 30-Jul-15 29-Aug-15 N/A 72
M11000101048 Pre-Cast Concrete Curb CB-01 Material Delivery 26 30-Jul-15 29-Aug-15 N/A 65
M11000101050 Plaza Flooring Filling (M-01&M-02&M-03) Material Deliver 52 30-Jul-15 01-Oct-15 N/A 13
M11000101052 Soft Scape Material Delivery 18 19-Sep-15 13-Oct-15 MIAC 35
MEP MaterialsMEP Materials 103 15-Jun-15 20-Oct-15 34
Material SubmittalMaterial Submittal 52 15-Jun-15 16-Aug-15 55
Electrical Material SElectrical Material Submittal 52 15-Jun-15 16-Aug-15 55
M11000101054 PVC Conduit Material Submittal 3 15-Jun-15 17-Jun-15 Ofoq 50
M11000101056 Wires for Power and Lighting Material Submittal 10 19-Jul-15 30-Jul-15 Ofoq 69
M11000101058 External & Facade Lighting Fixture Material Submittal 12 19-Jul-15 02-Aug-15 N/A 46
Jun Jul Aug Sep Oct Nov Dec Jan eb
2015 2016
17-Sep-15, Finishing Material
13-Oct-15, Finishing Mat
20-Oct-15, MEP Materi
16-Aug-15, Material Submittal
16-Aug-15, Electrical Material Submit
Majarrah Business Complex Classic Schedule Layout 22-Jun-15 14:36
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 4 of 39 TASK filter: All Activities
© Primavera Systems, Inc.
Activity ID Activity Name Original
Duration
Start Finish Consultant Contractor Total
Float
M11000101060 Structured Cable for Data System Material Submittal 18 19-Jul-15 09-Aug-15 Ofoq 49
M11000101062 Distribution Board DB1, DB4 Material Submittal 18 19-Jul-15 09-Aug-15 Ofoq 46
M11000101064 CCTV Cameras Material Submittal 18 19-Jul-15 09-Aug-15 N/A 30
M11000101066 Floor Box Submittal 18 27-Jul-15 16-Aug-15 Ofoq 40
M11000101068 Public Address Loud Speaker Material Submittal 18 27-Jul-15 16-Aug-15 N/A 36
Mechanical MateriaMechanical Material Submittal 12 19-Jul-15 02-Aug-15 32
M11000101070 FD,AD, PD Material Submittal 6 19-Jul-15 26-Jul-15 Ofoq 1
M11000101072 Fire Hydrant Material Submittal 6 19-Jul-15 26-Jul-15 Ofoq 38
M11000101074 Siamese Connection Material Submittal 6 19-Jul-15 26-Jul-15 Ofoq 35
M11000101076 Fountains and Water Fall Accessories Material Submittal 6 27-Jul-15 02-Aug-15 N/A 32
Material ApprovalMaterial Approval 55 18-Jun-15 23-Aug-15 55
Electrical Material AElectrical Material Approval 55 18-Jun-15 23-Aug-15 55
M11000101078 PVC Conduit Material Approval 6 18-Jun-15 24-Jun-15 SCG 50
M11000101080 Wires for Power and Lighting Material Approval 6 01-Aug-15 06-Aug-15 SCG 69
M11000101082 External & Facade Lighting Fixture Material Approval 6 03-Aug-15 09-Aug-15 SCG 46
M11000101084 Structured Cable for Data System Material Approval 6 10-Aug-15 16-Aug-15 SCG 49
M11000101086 Distribution Board DB1, DB4 Material Approval 6 10-Aug-15 16-Aug-15 SCG 46
M11000101088 CCTV Cameras Material Approval 6 10-Aug-15 16-Aug-15 SCG 30
M11000101090 Floor Box Material Approval 6 17-Aug-15 23-Aug-15 SCG 40
M11000101092 Public Address Loud Speaker Material Approval 6 17-Aug-15 23-Aug-15 SCG 36
Mechanical MateriaMechanical Material Approval 12 27-Jul-15 09-Aug-15 32
M11000101094 FD,AD, PD Material Approval 6 27-Jul-15 02-Aug-15 SCG 1
M11000101096 Fire Hydrant Material Approval 6 27-Jul-15 02-Aug-15 SCG 38
M11000101098 Siamese Connection Material Approval 6 27-Jul-15 02-Aug-15 SCG 35
M11000101100 Fountains and Water Fall Accessories Material Approval 6 03-Aug-15 09-Aug-15 SCG 32
Material P.OMaterial P.O 52 25-Jun-15 26-Aug-15 55
Electrical MaterialElectrical Material P.O 52 25-Jun-15 26-Aug-15 55
M110001010102 PVC Conduit Material P.O 3 25-Jun-15 28-Jun-15 Ofoq 50
M110001010104 Wires for Power and Lighting Material P.O 3 08-Aug-15 10-Aug-15 Ofoq 69
M110001010106 External & Facade Lighting Fixture Material P.O 3 10-Aug-15 12-Aug-15 N/A 46
M110001010108 Structured Cable for Data System Material P.O 3 17-Aug-15 19-Aug-15 Ofoq 49
M110001010110 Distribution Board DB1, DB4 Material P.O 3 17-Aug-15 19-Aug-15 Ofoq 46
M110001010112 CCTV Cameras Material P.O 3 17-Aug-15 19-Aug-15 N/A 30
M110001010114 Floor Box Material P.O 3 24-Aug-15 26-Aug-15 Ofoq 40
M110001010116 Public Address Loud Speaker Material P.O 3 24-Aug-15 26-Aug-15 N/A 36
Mechanical MateriaMechanical Material P.O 12 03-Aug-15 16-Aug-15 32
M110001010118 FD,AD, PD Material P.O 6 03-Aug-15 09-Aug-15 Ofoq 1
M110001010120 Fire Hydrant Material P.O 6 03-Aug-15 09-Aug-15 Ofoq 38
M110001010122 Siamese Connection Material P.O 6 03-Aug-15 09-Aug-15 Ofoq 35
Jun Jul Aug Sep Oct Nov Dec Jan eb
2015 2016
02-Aug-15, Mechanical Material Submitta
23-Aug-15, Material Approval
23-Aug-15, Electrical Material Appr
09-Aug-15, Mechanical Material Appr
26-Aug-15, Material P.O
26-Aug-15, Electrical Material P.O
16-Aug-15, Mechanical Material P.O
Majarrah Business Complex Classic Schedule Layout 22-Jun-15 14:36
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 5 of 39 TASK filter: All Activities
© Primavera Systems, Inc.
Activity ID Activity Name Original
Duration
Start Finish Consultant Contractor Total
Float
M110001010124 Fountains and Water Accessories Fall Material P.O 6 10-Aug-15 16-Aug-15 N/A 32
Material DeliveryMaterial Delivery 91 29-Jun-15 20-Oct-15 34
Electrical MaterialElectrical Material Delivery 91 29-Jun-15 20-Oct-15 34
M110001010126 PVC Conduit Material Delivery 3 29-Jun-15 01-Jul-15 Ofoq 50
M110001010128 Wires for Power and Lighting Material Delivery 12 11-Aug-15 24-Aug-15 Ofoq 69
M110001010130 Structured Cable for Data System Material Delivery 26 20-Aug-15 19-Sep-15 Ofoq 49
M110001010132 External & Facade Lighting Fixture Material Delivery 36 13-Aug-15 27-Sep-15 N/A 46
M110001010134 Distribution Board DB1, DB4 Material Delivery 36 20-Aug-15 04-Oct-15 Ofoq 46
M110001010136 Floor Box Material Delivery 36 27-Aug-15 12-Oct-15 Ofoq 40
M110001010138 Public Address Loud Speaker Material Delivery 36 27-Aug-15 12-Oct-15 N/A 36
M110001010140 CCTV Cameras Material Delivery 48 20-Aug-15 20-Oct-15 N/A 30
Mechanical MateriaMechanical Material Delivery 52 10-Aug-15 13-Oct-15 38
M110001010144 FD,AD, PD Material Delivery 20 10-Aug-15 01-Sep-15 Ofoq 1
M110001010142 Fountains and Water Fall Accessories Material Delivery 45 17-Aug-15 12-Oct-15 N/A 32
M110001010146 Fire Hydrant Material Delivery 52 10-Aug-15 13-Oct-15 Ofoq 38
M110001010148 Siamese Connection Material Delivery 52 10-Aug-15 13-Oct-15 Ofoq 35
ConstructionConstruction 112 15-Jul-15 30-Nov-15 1
M1P1000 Removal of Temporary offices 6 22-Aug-15 27-Aug-15 HW ECIP 3
Structural WorkStructural Work 36 15-Jul-15 27-Aug-15 65
M110001010150 Existing Planters to be demolished 6 01-Aug-15 06-Aug-15 HW ECIP 21
M110001010350 Gas Room Ready to Receive Gas Facility 18 15-Jul-15 06-Aug-15 HW ECIP 83
M110001010152 Stair form Upper Basement to Plaza Level to be demolished 12 01-Aug-15 13-Aug-15 HW ECIP 3
M110001010154 Planters to be added above existing stair 12 01-Aug-15 13-Aug-15 HW ECIP 15
M110001010156 Slab to be removed 12 01-Aug-15 13-Aug-15 HW ECIP 3
M110001010158 New Planters to be added 12 01-Aug-15 13-Aug-15 HW ECIP 12
M110001010160 Existing Slab to be opened 3 15-Aug-15 17-Aug-15 HW ECIP 12
M110001010270 Expansion Joints 18 29-Jul-15 18-Aug-15 HW ECIP 12
M110001010162 New Slab to be added 18 01-Aug-15 20-Aug-15 HW ECIP 9
M110001010164 Two opening has been canceled and to be closed 18 01-Aug-15 20-Aug-15 HW ECIP 9
M110001010166 Concrete slab to be added instead of demolished stair 12 15-Aug-15 27-Aug-15 HW ECIP 3
M110001010168 Two New Stairs with a Ramp To Be Added 12 15-Aug-15 27-Aug-15 HW ECIP 3
MEP WorkMEP Work 87 30-Jul-15 14-Nov-15 15
Electrical WorksElectrical Works 62 29-Aug-15 14-Nov-15 15
M110001010170 PVC conduits Raceway for Electrical Power outlets 6 29-Aug-15 03-Sep-15 SCG Ofoq 3
M110001010174 PVC conduits Raceway for Data System 6 29-Aug-15 03-Sep-15 SCG Ofoq 3
M110001010172 PVC conduits Raceway for External Lighting Fixture 6 29-Aug-15 03-Sep-15 SCG Ofoq 5
M110001010176 PVC conduits Raceway for Public Address System (Sound
System)
6 29-Aug-15 03-Sep-15 SCG Ofoq 5
Jun Jul Aug Sep Oct Nov Dec Jan eb
2015 2016
20-Oct-15, Material De
20-Oct-15, Electrical Ma
13-Oct-15, Mechanical M
30-Nov-15, Co
27-Aug-15, Structural Work
14-Nov-15, MEP W
14-Nov-15, Electri
Majarrah Business Complex Classic Schedule Layout 22-Jun-15 14:36
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 6 of 39 TASK filter: All Activities
© Primavera Systems, Inc.
Activity ID Activity Name Original
Duration
Start Finish Consultant Contractor Total
Float
M110001010178 PVC conduits Raceway for CCTV System 6 29-Aug-15 03-Sep-15 SCG Ofoq 5
M110001010180 Back Box for Floor Box 2 05-Sep-15 06-Sep-15 SCG Ofoq 3
M110001010182 Wires for External Lighting Fixture 3 05-Sep-15 07-Sep-15 SCG Ofoq 60
M110001010184 Wires for Electrical Power outlets 3 07-Sep-15 09-Sep-15 SCG Ofoq 64
M110001010186 Structured Cable for Data System 3 20-Sep-15 26-Sep-15 SCG Ofoq 49
M110001010192 Facade Lighting Fixtures Erection 6 29-Sep-15 05-Oct-15 SCG Ofoq 47
M110001010188 Floor Box erection 2 05-Nov-15 07-Nov-15 SCG Ofoq 21
M110001010190 External Lighting Fixture Erection 6 05-Nov-15 11-Nov-15 SCG Ofoq 15
M110001010194 Public Address (Sound System) Erection 6 05-Nov-15 11-Nov-15 SCG Ofoq 17
M110001010196 CCTV Erection 6 05-Nov-15 11-Nov-15 SCG Ofoq 17
M110001010198 Distribution Board DB1, DB4 Erection 2 12-Nov-15 14-Nov-15 SCG Ofoq 15
Mechanical WorksMechanical Works 86 30-Jul-15 12-Nov-15 16
M110001010200 Builder Work And Core Drill for Drainage 6 30-Jul-15 05-Aug-15 SCG Ofoq 24
M110001010260 Gas Facility Network 12 08-Aug-15 20-Aug-15 SCG Gas 83
M110001010202 Floor Drains first fix 6 02-Sep-15 08-Sep-15 SCG Ofoq 1
M110001010204 Floor Drains second fix 3 04-Oct-15 07-Oct-15 SCG Ofoq 44
M110001010208 Fire Hydrant 3 19-Oct-15 21-Oct-15 SCG Ofoq 35
M110001010210 Siamese Connection 6 15-Oct-15 21-Oct-15 SCG Ofoq 35
M110001010206 Floor Drains final fix 2 05-Nov-15 07-Nov-15 SCG Ofoq 21
M110001010212 Irrigation for Main Road Island landscape 2 11-Nov-15 12-Nov-15 SCG Ofoq 12
Finishing WorkFinishing Work 76 29-Aug-15 30-Nov-15 1
M110001010214 Boundary wall (Travco Side) 18 29-Aug-15 17-Sep-15 HW ECIP 59
M110001010216 Temporary Fence 10 05-Nov-15 16-Nov-15 T.B N/A 13
Hard scapeHard scape 66 09-Sep-15 30-Nov-15 1
M110001010218 Insulation work for Plaza 18 09-Sep-15 03-Oct-15 HW ECIP 1
M110001010300 Remove Facade Cladding for Facade Lighting Fixture Erec 7 28-Sep-15 05-Oct-15 T.B Kemet 47
M110001010224 Walkways Filling Interlock 12 03-Oct-15 18-Oct-15 T.B N/A 35
M110001010232 Driveway Filling Interlock & Bazalt Tiles 12 03-Oct-15 18-Oct-15 T.B N/A 38
M110001010234 Driveway Boarders Bazalt tiles 12 03-Oct-15 18-Oct-15 T.B N/A 38
M110001010220 Screed over Insulation 12 04-Oct-15 19-Oct-15 HW ECIP 1
M110001010222 Flooring Filling Engineered Stone / Porcelain / Granite 15 19-Oct-15 04-Nov-15 T.B N/A 1
M110001010238 Main Road Island hardscape 5 05-Nov-15 10-Nov-15 T.B N/A 12
M110001010240 Planter Copping 6 05-Nov-15 11-Nov-15 T.B N/A 11
M110001010242 Stairs Covering 6 05-Nov-15 11-Nov-15 T.B N/A 17
M110001010228 Building Boarders Granite 12 05-Nov-15 18-Nov-15 T.B N/A 11
M110001010230 Plaza Boarders Granite 12 05-Nov-15 18-Nov-15 T.B N/A 11
M110001010226 Granite for Fountains 12 05-Nov-15 18-Nov-15 T.B N/A 1
M110001010236 Fountains and Water Fall Accessories Erection 10 19-Nov-15 30-Nov-15 T.B N/A 1
Soft scapeSoft scape 6 12-Nov-15 18-Nov-15 11
Jun Jul Aug Sep Oct Nov Dec Jan eb
2015 2016
12-Nov-15, Mecha
30-Nov-15, Fin
30-Nov-15, Ha
18-Nov-15, Soft s
Majarrah Business Complex Classic Schedule Layout 22-Jun-15 14:36
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 7 of 39 TASK filter: All Activities
© Primavera Systems, Inc.
Activity ID Activity Name Original
Duration
Start Finish Consultant Contractor Total
Float
M110001010246 Main Road Island softscape 4 14-Nov-15 17-Nov-15 T.B MIAC 12
M110001010244 Plaza softscape 6 12-Nov-15 18-Nov-15 T.B MIAC 11
Upper BasementUpper Basement 164 15-Jun-15 31-Dec-15 0
GeneralGeneral 0 07-Jul-15 07-Jul-15 15
M1P2760 Client Clear Vision about Security Issues as (CCTV, Access
Control...)
0 07-Jul-15 Client 6
M1P2770 Client Clear Vision about Data Issues as (Central, IT
requirements...)
0 07-Jul-15 Client 15
DesignDesign 78 15-Jun-15 15-Sep-15 17
Architectural DesArchitectural Design 24 15-Jun-15 12-Jul-15 0
M1P1020 Final Architectural Dimensional Plan for Upper Basement 6 15-Jun-15 21-Jun-15 T.B 0
M1P1010 Final Parking Layout for Upper Basement 0 28-Jun-15 Client 0
M1P1030 Final Architectural Package for Upper Basement 12 29-Jun-15 12-Jul-15 HW 0
Structural DesignStructural Design 6 09-Sep-15 15-Sep-15 17
M1P2750 Structural Design for Equipment Foundation (Child Pump ,
Supply and Exhaust Fans........)
6 09-Sep-15 15-Sep-15 HW 17
MEP DesignMEP Design 30 22-Jun-15 28-Jul-15 6
Electrical SystemsElectrical Systems 24 29-Jun-15 28-Jul-15 6
Power SystemPower System 6 29-Jun-15 05-Jul-15 4
M1P1060 Updated Design for Power System 6 29-Jun-15 05-Jul-15 SCG 4
Lighting SystemLighting System 6 29-Jun-15 05-Jul-15 4
M1P1070 Updated Design for Lighting System 6 29-Jun-15 05-Jul-15 SCG 4
Fire Alarm SystemFire Alarm System 6 13-Jul-15 20-Jul-15 0
M1P1680 Updated Design for Fire Alarm System 6 13-Jul-15 20-Jul-15 C/SCG 0
Parking SystemParking System 18 29-Jun-15 20-Jul-15 0
M1P1450 Updated Design for Parking System 18 29-Jun-15 20-Jul-15 C/SCG 0
CCTV SystemCCTV System 6 13-Jul-15 20-Jul-15 2
M1P1040 Updated Design for CCTV System 6 13-Jul-15 20-Jul-15 C/SCG 2
Data SystemData System 6 13-Jul-15 20-Jul-15 11
M1P1050 Updated Design for Data System 6 13-Jul-15 20-Jul-15 C/SCG 11
BMS SystemBMS System 6 21-Jul-15 28-Jul-15 6
M1P2000 Updated Design for BMS System 6 21-Jul-15 28-Jul-15 SCG 6
Mechanical SystemsMechanical Systems 24 22-Jun-15 20-Jul-15 12
HVAC SystemHVAC System 6 13-Jul-15 20-Jul-15 0
M1P1080 HVAC Updated Design for Upper Basement 6 13-Jul-15 20-Jul-15 SCG 0
Fire Fighting SysteFire Fighting System 6 22-Jun-15 28-Jun-15 19
M1P1130 Fire Fighting Updated Design for Upper Basement 6 22-Jun-15 28-Jun-15 SCG 19
Plumbing SystemPlumbing System 6 27-Jun-15 02-Jul-15 26
Jun Jul Aug Sep Oct Nov Dec Jan eb
2015 2016
31-Dec-
07-Jul-15, General
15-Sep-15, Design
12-Jul-15, Architectural Design
15-Sep-15, Structural Design
28-Jul-15, MEP Design
28-Jul-15, Electrical Systems
05-Jul-15, Power System
05-Jul-15, Lighting System
20-Jul-15, Fire Alarm System
20-Jul-15, Parking System
20-Jul-15, CCTV System
20-Jul-15, Data System
28-Jul-15, BMS System
20-Jul-15, Mechanical Systems
20-Jul-15, HVAC System
28-Jun-15, Fire Fighting System
02-Jul-15, Plumbing System
Majarrah Business Complex Classic Schedule Layout 22-Jun-15 14:36
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 8 of 39 TASK filter: All Activities
© Primavera Systems, Inc.
Activity ID Activity Name Original
Duration
Start Finish Consultant Contractor Total
Float
Drainage SystemDrainage System 6 27-Jun-15 02-Jul-15 20
M1P1090 Final Update for Upper Basement Drainage System 6 27-Jun-15 02-Jul-15 SCG 20
Irrigation SystemIrrigation System 6 27-Jun-15 02-Jul-15 26
M1P1100 Final Update for Plaza Irrigation System 6 27-Jun-15 02-Jul-15 SCG 26
Fountains and WateFountains and Water Fall 6 27-Jun-15 02-Jul-15 26
M1P1110 Fountains Design 6 27-Jun-15 02-Jul-15 SCG 26
M1P1120 Water Fall Design 6 27-Jun-15 02-Jul-15 SCG 26
Shop DrawingsShop Drawings 84 22-Jun-15 03-Oct-15 17
Architectural ShoArchitectural Shop Drawing 12 13-Jul-15 28-Jul-15 0
M1P1140 Upper Basement Architectural Shop Drawing Submittal 6 13-Jul-15 20-Jul-15 ECIP 0
M1P1150 Upper Basement Architectural Shop Drawing Approval 6 21-Jul-15 28-Jul-15 HW 0
Structural Shop DStructural Shop Drawing 68 11-Jul-15 03-Oct-15 17
M1P1160 Upper Basement Construction , Expansion Joints Details
Shop Drawing Submittal
6 11-Jul-15 16-Jul-15 ECIP 60
M1P1170 Upper Basement Construction , Expansion Joints Details
Shop Drawing Approval
6 19-Jul-15 26-Jul-15 HW 60
M1P2780 Upper Basement Equipment Foundations shop drawings
Submittal
6 16-Sep-15 26-Sep-15 ECIP 17
M1P2790 Upper Basement Equipment Foundations shop drawings
Approval
6 27-Sep-15 03-Oct-15 HW 17
Electrical SystemsElectrical Systems 36 06-Jul-15 18-Aug-15 0
Power SystemPower System 12 06-Jul-15 20-Jul-15 4
M1P1180 Upper Basement Power System Layout Submittal 6 06-Jul-15 12-Jul-15 Ofoq 4
M1P1190 Upper Basement Power System Layout Approval 6 13-Jul-15 20-Jul-15 SCG 4
Lighting SystemLighting System 12 06-Jul-15 20-Jul-15 4
M1P1200 Upper Basement Lighting System Layout Submittal 6 06-Jul-15 12-Jul-15 Ofoq 4
M1P1210 Upper Basement Lighting System Layout Approval 6 13-Jul-15 20-Jul-15 SCG 4
Fire Alarm SystemFire Alarm System 12 21-Jul-15 04-Aug-15 12
M1P1690 Upper Basement Fire Alarm System Layout Submittal 6 21-Jul-15 28-Jul-15 Ofoq 12
M1P1700 Upper Basement Fire Alarm System Layout Approval 6 29-Jul-15 04-Aug-15 SCG 12
Parking SystemParking System 12 21-Jul-15 04-Aug-15 0
M1P1430 Upper Basement Parking System Layout Submittal 6 21-Jul-15 28-Jul-15 Ofoq 0
M1P1440 Upper Basement Parking System Layout Approval 6 29-Jul-15 04-Aug-15 SCG 0
CCTV SystemCCTV System 12 21-Jul-15 04-Aug-15 2
M1P1220 Upper Basement CCTV System Layout Submittal 6 21-Jul-15 28-Jul-15 Ofoq 2
M1P1230 Upper Basement CCTV System Layout Approval 6 29-Jul-15 04-Aug-15 SCG 2
Data SystemData System 12 21-Jul-15 04-Aug-15 11
M1P1240 Upper Basement Data System Layout Submittal 6 21-Jul-15 28-Jul-15 Ofoq 11
M1P1250 Upper Basement Data System Layout Approval 6 29-Jul-15 04-Aug-15 SCG 11
Jun Jul Aug Sep Oct Nov Dec Jan eb
2015 2016
02-Jul-15, Drainage System
02-Jul-15, Irrigation System
02-Jul-15, Fountains and Water Fall
03-Oct-15, Shop Drawings
28-Jul-15, Architectural Shop Drawing
03-Oct-15, Structural Shop
18-Aug-15, Electrical Systems
20-Jul-15, Power System
20-Jul-15, Lighting System
04-Aug-15, Fire Alarm System
04-Aug-15, Parking System
04-Aug-15, CCTV System
04-Aug-15, Data System
Majarrah Business Complex Classic Schedule Layout 22-Jun-15 14:36
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 9 of 39 TASK filter: All Activities
© Primavera Systems, Inc.
Activity ID Activity Name Original
Duration
Start Finish Consultant Contractor Total
Float
BMS SystemBMS System 12 05-Aug-15 18-Aug-15 0
M1P2010 Upper Basement BMS System Layout Submittal 6 05-Aug-15 11-Aug-15 Ofoq 0
M1P2020 Upper Basement BMS System Layout Approval 6 12-Aug-15 18-Aug-15 SCG 0
Mechanical SysteMechanical Systems 66 22-Jun-15 08-Sep-15 17
HVAC SystemHVAC System 66 22-Jun-15 08-Sep-15 17
M1P2210 HVAC Static Calculations for Child Water Pump Submittal 6 22-Jun-15 28-Jun-15 Ofoq 0
M1P2230 Fans Static Pressure Calculations Submittal 6 22-Jun-15 28-Jun-15 Ofoq 28
M1P2220 HVAC Static Calculations for Child Water Pump Approval 6 29-Jun-15 05-Jul-15 SCG 0
M1P2240 Fans Static Pressure Calculations Approval 6 29-Jun-15 05-Jul-15 SCG 28
M1P3560 Builder Work for Shaft Opening Layout Submittal 3 06-Jul-15 08-Jul-15 Ofoq 28
M1P3570 Builder Work for Shaft Opening Layout Approval 6 09-Jul-15 15-Jul-15 HW 28
M1P1260 Upper Basement HVAC System Layout Submittal 6 21-Jul-15 28-Jul-15 Ofoq 0
M1P1270 Upper Basement HVAC System Layout Approval 6 29-Jul-15 04-Aug-15 SCG 0
M1P2730 Upper Basement Fan Room Details Submittal 6 29-Jul-15 04-Aug-15 Ofoq 41
M1P2740 Upper Basement Fan Room Details Approval 6 05-Aug-15 11-Aug-15 SCG 41
M1P2190 Upper Basement Plant Room Details Submittal 6 26-Aug-15 01-Sep-15 Ofoq 17
M1P2200 Upper Basement Plant Room Details Approval 6 02-Sep-15 08-Sep-15 SCG 17
Fire Fighting SystemFire Fighting System 12 29-Jun-15 12-Jul-15 19
M1P1280 Upper Basement Fire Fighting System Layout Submittal 6 29-Jun-15 05-Jul-15 Ofoq 19
M1P1290 Upper Basement Fire Fighting System Layout Approval 6 06-Jul-15 12-Jul-15 SCG 19
Plumbing SystemPlumbing System 12 04-Jul-15 16-Jul-15 26
Drainage SystemDrainage System 12 04-Jul-15 16-Jul-15 26
M1P1300 Upper Basement Drainage System Layout Submittal 6 04-Jul-15 09-Jul-15 Ofoq 26
M1P1310 Upper Basement Drainage System Layout Approval 6 11-Jul-15 16-Jul-15 SCG 26
Irrigation SystemIrrigation System 12 04-Jul-15 16-Jul-15 26
M1P1320 Upper Basement Irrigation System for Plaza Layout Submit 6 04-Jul-15 09-Jul-15 Ofoq 26
M1P1330 Upper Basement Irrigation System for Plaza Layout Appro 6 11-Jul-15 16-Jul-15 SCG 26
Fountains and WateFountains and Water Fall 12 04-Jul-15 16-Jul-15 26
M1P1340 Upper Basement Fountains and Water Fall System Layout
Submittal
6 04-Jul-15 09-Jul-15 Ofoq 26
M1P1350 Upper Basement Fountains and Water Fall System Layout
Approval
6 11-Jul-15 16-Jul-15 SCG 26
Composite DrawiComposite Drawing 12 19-Aug-15 01-Sep-15 0
M1P1360 Upper Basement MEP Composite Drawing Submittal 6 19-Aug-15 25-Aug-15 Ofoq 0
M1P1370 Upper Basement MEP Composite Drawing Approval 6 26-Aug-15 01-Sep-15 SCG 0
MaterialsMaterials 146 15-Jun-15 09-Dec-15 6
Finishing MateriaFinishing Materials 35 27-Jul-15 05-Sep-15 58
Material SubmittalMaterial Submittal 20 27-Jul-15 18-Aug-15 58
Jun Jul Aug Sep Oct Nov Dec Jan eb
2015 2016
18-Aug-15, BMS System
08-Sep-15, Mechanical Systems
08-Sep-15, HVAC System
12-Jul-15, Fire Fighting System
16-Jul-15, Plumbing System
16-Jul-15, Drainage System
16-Jul-15, Irrigation System
16-Jul-15, Fountains and Water Fall
01-Sep-15, Composite Drawing
09-Dec-15, M
05-Sep-15, Finishing Materials
18-Aug-15, Material Submittal
Majarrah Business Complex Classic Schedule Layout 22-Jun-15 14:36
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 10 of 39 TASK filter: All Activities
© Primavera Systems, Inc.
Activity ID Activity Name Original
Duration
Start Finish Consultant Contractor Total
Float
M110001206 Expansion Joints Submittal 6 27-Jul-15 02-Aug-15 ECIP 60
M1P1380 False Ceiling Material Submittal 18 29-Jul-15 18-Aug-15 ECIP 17
M1P1390 Flooring Tiles Material Submittal 18 29-Jul-15 18-Aug-15 ECIP 41
M1P1400 Paint Material Submittal 18 29-Jul-15 18-Aug-15 ECIP 29
M1P1410 Curb Stone Material Submittal 18 29-Jul-15 18-Aug-15 ECIP 46
M1P1420 Interlock Material Submittal 18 29-Jul-15 18-Aug-15 ECIP 58
M1P3920 Doors Submittal 18 29-Jul-15 18-Aug-15 ECIP 58
M1P3930 Raised Floor Submittal (Expected in IT & Main IT Room) 18 29-Jul-15 18-Aug-15 ECIP 47
Material ApprovalMaterial Approval 20 03-Aug-15 25-Aug-15 58
M110001216 Expansion Joints Approval 6 03-Aug-15 09-Aug-15 HW 60
M1P1460 False Ceiling Material Approval 6 19-Aug-15 25-Aug-15 HW 17
M1P1470 Flooring Tiles Material Approval 6 19-Aug-15 25-Aug-15 HW 41
M1P1480 Paint Material Approval 6 19-Aug-15 25-Aug-15 HW 29
M1P1490 Curb Stone Material Approval 6 19-Aug-15 25-Aug-15 HW 46
M1P1500 Interlock Material Approval 6 19-Aug-15 25-Aug-15 HW 58
M1P3940 Doors Approval 6 19-Aug-15 25-Aug-15 HW 58
M1P3950 Raised Floor Approval (Expected in IT & Main IT Room) 6 19-Aug-15 25-Aug-15 HW 47
Material P.OMaterial P.O 17 10-Aug-15 29-Aug-15 58
M110001226 Expansion Joints P.O 3 10-Aug-15 12-Aug-15 ECIP 60
M1P1510 False Ceiling Material P.O 3 26-Aug-15 29-Aug-15 ECIP 17
M1P1520 Flooring Tiles Material P.O 3 26-Aug-15 29-Aug-15 ECIP 41
M1P1530 Paint Material P.O 3 26-Aug-15 29-Aug-15 ECIP 29
M1P1540 Curb Stone Material P.O 3 26-Aug-15 29-Aug-15 ECIP 46
M1P1550 Interlock Material P.O 3 26-Aug-15 29-Aug-15 ECIP 58
M1P3960 Doors P.O 3 26-Aug-15 29-Aug-15 ECIP 58
M1P3970 Raised Floor P.O (Expected in IT & Main IT Room) 3 26-Aug-15 29-Aug-15 ECIP 47
Material DeliveryMaterial Delivery 20 13-Aug-15 05-Sep-15 58
M110001236 Expansion Joints Delivery 6 13-Aug-15 19-Aug-15 ECIP 60
M1P1560 False Ceiling Material Delivery 6 30-Aug-15 05-Sep-15 ECIP 17
M1P1570 Flooring Tiles Material Delivery 6 30-Aug-15 05-Sep-15 ECIP 41
M1P1580 Paint Material Delivery 6 30-Aug-15 05-Sep-15 ECIP 29
M1P1590 Curb Stone Material Delivery 6 30-Aug-15 05-Sep-15 ECIP 46
M1P1600 Interlock Material Delivery 6 30-Aug-15 05-Sep-15 ECIP 58
M1P3980 Doors Delivery 6 30-Aug-15 05-Sep-15 ECIP 58
M1P3990 Raised Floor Delivery (Expected in IT & Main IT Room) 6 30-Aug-15 05-Sep-15 ECIP 47
MEP MaterialsMEP Materials 146 15-Jun-15 09-Dec-15 6
Material SubmittalMaterial Submittal 72 15-Jun-15 08-Sep-15 46
Electrical Material SElectrical Material Submittal 72 15-Jun-15 08-Sep-15 20
M10 PVC , EMT Conduit with Accessories Material Submittal 3 15-Jun-15 17-Jun-15 Ofoq 48
Jun Jul Aug Sep Oct Nov Dec Jan eb
2015 2016
25-Aug-15, Material Approval
29-Aug-15, Material P.O
05-Sep-15, Material Delivery
09-Dec-15, M
08-Sep-15, Material Submittal
08-Sep-15, Electrical Material Su
Majarrah Business Complex Classic Schedule Layout 22-Jun-15 14:36
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 11 of 39 TASK filter: All Activities
© Primavera Systems, Inc.
Activity ID Activity Name Original
Duration
Start Finish Consultant Contractor Total
Float
M100 Cable Trays Submittal 6 15-Jun-15 21-Jun-15 Ofoq 86
M20 Wires for Power and Lighting Material Submittal 6 21-Jul-15 28-Jul-15 Ofoq 52
M30 Lighting Fixture Material Submittal 12 21-Jul-15 04-Aug-15 Ofoq 40
M90 Wiring Devices Submittal 12 21-Jul-15 04-Aug-15 Ofoq 15
M110 Fire Alarm Material Submittal 12 21-Jul-15 04-Aug-15 Ofoq 0
M40 Structured Cable for Data System Material Submittal 4 05-Aug-15 09-Aug-15 Ofoq 11
M50 Distribution Board Material Submittal 16 21-Jul-15 09-Aug-15 Ofoq 4
M60 CCTV Cameras Material Submittal 4 05-Aug-15 09-Aug-15 N/A 2
M80 Parking System Material Submittal 18 05-Aug-15 25-Aug-15 N/A 0
M420 LV Cables Submittal 6 02-Sep-15 08-Sep-15 Ofoq 12
M450 BMS Submittal 18 19-Aug-15 08-Sep-15 Ofoq 1
Electrical EquipmentElectrical Equipment 54 15-Jun-15 18-Aug-15 10
M1P1620 R.M.U Submittal 18 15-Jun-15 05-Jul-15 Ofoq 34
M1P1630 MVSG Submittal 18 15-Jun-15 05-Jul-15 Ofoq 34
M1P1710 UPS Submittal 26 15-Jun-15 14-Jul-15 Ofoq 12
M1P1610 Generator Submittal 18 29-Jun-15 20-Jul-15 Ofoq 2
M1P1640 Transformer Submittal 18 29-Jun-15 20-Jul-15 Ofoq 22
M1P1650 MDB Submittal 18 21-Jul-15 11-Aug-15 Ofoq 4
M1P1660 EMDB Submittal 18 21-Jul-15 11-Aug-15 Ofoq 4
M1P1720 MCC Submittal 18 21-Jul-15 11-Aug-15 Ofoq 10
M1P1670 ATS Submittal 6 12-Aug-15 18-Aug-15 Ofoq 10
Mechanical MateriaMechanical Material Submittal 72 15-Jun-15 08-Sep-15 46
HVAC System SubmHVAC System Submittal 54 15-Jun-15 18-Aug-15 58
M1P2030 Galvanized Duct Submittal 6 15-Jun-15 21-Jun-15 Ofoq 46
M1P2070 Child Water Pipes Submittal 6 15-Jun-15 21-Jun-15 Ofoq 76
M1P2080 Child Water Insulation Submittal 6 15-Jun-15 21-Jun-15 Ofoq 106
M1P2040 Volume Dampers Submittal 12 05-Aug-15 18-Aug-15 Ofoq 10
M1P2050 Fire Dampers Submittal 12 05-Aug-15 18-Aug-15 Ofoq 10
M1P2060 Fire Smoke Dampers Submittal 12 05-Aug-15 18-Aug-15 Ofoq 10
M1P2090 Supply Air Grill Submittal 12 05-Aug-15 18-Aug-15 Ofoq 46
M1P2100 Exhaust Air Grill Submittal 12 05-Aug-15 18-Aug-15 Ofoq 46
Fire Fighting SystemFire Fighting System Submittal 48 13-Jul-15 08-Sep-15 3
M1P2800 Seamless Black Steel Pipes Submittal 3 13-Jul-15 15-Jul-15 Ofoq 26
M1P2810 Fire Fighting Network Valves (O.S&Y gate valve, Check
valve, Alarm Check Valve) Submittal
6 13-Jul-15 20-Jul-15 Ofoq 29
M1P2820 Sprinklers Submittal 6 13-Jul-15 20-Jul-15 Ofoq 20
M1P2850 Fire Hose Stations Submittal 6 13-Jul-15 20-Jul-15 Ofoq 28
M1P2860 Fire Hose Real Stations Submittal 6 13-Jul-15 20-Jul-15 Ofoq 28
M1P2870 Fire Extinguishers Submittal 6 13-Jul-15 20-Jul-15 Ofoq 19
Jun Jul Aug Sep Oct Nov Dec Jan eb
2015 2016
18-Aug-15, Electrical Equipment
08-Sep-15, Mechanical Material S
18-Aug-15, HVAC System Submittal
08-Sep-15, Fire Fighting System S
Majarrah Business Complex Classic Schedule Layout 22-Jun-15 14:36
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 12 of 39 TASK filter: All Activities
© Primavera Systems, Inc.
Activity ID Activity Name Original
Duration
Start Finish Consultant Contractor Total
Float
M1P2830 FM200 System for (MVSG Room, RMU Room,
Transformer Room, Telecom Room, Security Room,LV
Room, IT&Main IT Room)Submittal
12 19-Aug-15 01-Sep-15 Ofoq 4
M1P2840 Foam Fire System for (Generator Room, Feul Tank Room)
Submittal
12 26-Aug-15 08-Sep-15 Ofoq 3
Plumbing System SPlumbing System Submittal 18 19-Jul-15 09-Aug-15 72
M1P3150 PPR Domestic Water Pipes Submittal 6 19-Jul-15 26-Jul-15 Ofoq 54
M1P3170 UPVC for Drainage System Submittal 6 19-Jul-15 26-Jul-15 Ofoq 48
M1P3180 PVC for Forced Main Line Submittal 6 19-Jul-15 26-Jul-15 Ofoq 66
M1P3190 Irrigation System PVC Submittal 6 19-Jul-15 26-Jul-15 Ofoq 66
M1P3200 Valves Submittal 6 19-Jul-15 26-Jul-15 Ofoq 72
M1P3210 F.D , F.F.D , P.D , F.C.O , A.D , G.D , T.D Submittal 6 19-Jul-15 26-Jul-15 Ofoq 36
M1P3220 Hose Bibbs Submittal 6 19-Jul-15 26-Jul-15 Ofoq 84
M1P3140 HDPE Domestic Water Pipes Submittal 12 19-Jul-15 02-Aug-15 Ofoq 72
M1P3160 HDPE for Drainage , Waste , Vent, Storm Systems Submitta 12 19-Jul-15 02-Aug-15 Ofoq 72
M1P3120 Fountains Tank Submittal 18 19-Jul-15 09-Aug-15 N/A 40
M1P3130 Water Fall Tank Submittal 18 19-Jul-15 09-Aug-15 N/A 40
Mechanical EquipmMechanical Equipment Submittal 36 06-Jul-15 18-Aug-15 60
HVAC EquipmentHVAC Equipment Submittal 36 06-Jul-15 18-Aug-15 60
M1P2150 Child Water Pumps Submittal 12 06-Jul-15 20-Jul-15 Ofoq 0
M1P2160 Exhaust Fans Submittal 12 06-Jul-15 20-Jul-15 Ofoq 41
M1P2170 Supply Fans Submittal 12 06-Jul-15 20-Jul-15 Ofoq 41
M1P2110 Fuel Oil Storage Tank Submittal 12 05-Aug-15 18-Aug-15 Ofoq 2
M1P2120 AC DX Split Units Submittal 12 05-Aug-15 18-Aug-15 Ofoq 60
M1P2130 Heat Exchangers Submittal 12 05-Aug-15 18-Aug-15 Ofoq 2
M1P2140 Expansion and Compression Tanks Submittal 12 05-Aug-15 18-Aug-15 Ofoq 2
M1P2180 Fan Coil Units Submittal 12 05-Aug-15 18-Aug-15 Ofoq 17
Material ApprovalMaterial Approval 87 18-Jun-15 03-Oct-15 34
Electrical Material AElectrical Material Approval 87 18-Jun-15 03-Oct-15 8
M70 PVC , EMT Conduit with Accessories Conduit Material
Approval
6 18-Jun-15 24-Jun-15 SCG 48
M120 Cable Trays Approval 6 22-Jun-15 28-Jun-15 SCG 86
M130 Wires for Power and Lighting Material Approval 6 29-Jul-15 04-Aug-15 SCG 52
M140 Lighting Fixture Material Approval 6 05-Aug-15 11-Aug-15 SCG 40
M150 Wiring Devices Approval 6 05-Aug-15 11-Aug-15 SCG 15
M160 Fire Alarm Material Approval 6 05-Aug-15 11-Aug-15 SCG 0
M170 Structured Cable for Data System Material Approval 6 10-Aug-15 16-Aug-15 SCG 11
M180 Distribution Board Material Approval 6 10-Aug-15 16-Aug-15 SCG 24
M190 CCTV Cameras Material Approval 6 10-Aug-15 16-Aug-15 SCG 2
Jun Jul Aug Sep Oct Nov Dec Jan eb
2015 2016
09-Aug-15, Plumbing System Submittal
18-Aug-15, Mechanical Equipment Su
18-Aug-15, HVAC Equipment Submi
03-Oct-15, Material Appro
03-Oct-15, Electrical Mater
Majarrah Business Complex Classic Schedule Layout 22-Jun-15 14:36
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 13 of 39 TASK filter: All Activities
© Primavera Systems, Inc.
Activity ID Activity Name Original
Duration
Start Finish Consultant Contractor Total
Float
M200 Parking System Material Approval 6 26-Aug-15 01-Sep-15 SCG 0
M410 LV Cables Approval 6 09-Sep-15 15-Sep-15 SCG 12
M460 BMS Approval 18 09-Sep-15 03-Oct-15 SCG 1
Electrical EquipmentElectrical Equipment 42 06-Jul-15 25-Aug-15 10
M1P1740 R.M.U Approval 6 06-Jul-15 12-Jul-15 SCG 34
M1P1750 MVSG Approval 6 06-Jul-15 12-Jul-15 SCG 34
M1P1800 UPS Approval 6 15-Jul-15 22-Jul-15 SCG 12
M1P1730 Generator Approval 6 21-Jul-15 28-Jul-15 SCG 2
M1P1760 Transformer Approval 6 21-Jul-15 28-Jul-15 SCG 22
M1P1770 MDB Approval 6 12-Aug-15 18-Aug-15 SCG 4
M1P1780 EMDB Approval 6 12-Aug-15 18-Aug-15 SCG 4
M1P1810 MCC Approval 6 12-Aug-15 18-Aug-15 SCG 16
M1P1790 ATS Approval 6 19-Aug-15 25-Aug-15 SCG 10
Mechanical MateriaMechanical Material Approval 72 22-Jun-15 15-Sep-15 46
HVAC System ApproHVAC System Approval 54 22-Jun-15 25-Aug-15 58
M1P2250 Galvanized Duct Approval 6 22-Jun-15 28-Jun-15 SCG 46
M1P2290 Child Water Pipes Approval 6 22-Jun-15 28-Jun-15 SCG 76
M1P2300 Child Water Insulation Approval 6 22-Jun-15 28-Jun-15 SCG 106
M1P2260 Volume Dampers Approval 6 19-Aug-15 25-Aug-15 SCG 10
M1P2270 Fire Dampers Approval 6 19-Aug-15 25-Aug-15 SCG 10
M1P2280 Fire Smoke Dampers Approval 6 19-Aug-15 25-Aug-15 SCG 10
M1P2310 Supply Air Grill Approval 6 19-Aug-15 25-Aug-15 SCG 46
M1P2320 Exhaust Air Grill Approval 6 19-Aug-15 25-Aug-15 SCG 46
Fire Fighting SystemFire Fighting System Approval 51 16-Jul-15 15-Sep-15 3
M1P2880 Seamless Black Steel Pipes Approval 6 16-Jul-15 25-Jul-15 SCG 26
M1P2890 Fire Fighting Network Valves (O.S&Y gate valve, Check
valve, Alarm Check Valve) Approval
6 21-Jul-15 28-Jul-15 SCG 29
M1P2900 Sprinklers Approval 6 21-Jul-15 28-Jul-15 SCG 20
M1P2910 Fire Hose Stations Approval 6 21-Jul-15 28-Jul-15 SCG 28
M1P2920 Fire Hose Real Stations Approval 6 21-Jul-15 28-Jul-15 SCG 28
M1P2930 Fire Extinguishers Approval 6 21-Jul-15 28-Jul-15 SCG 19
M1P2940 FM200 System for (MVSG Room, RMU Room,
Transformer Room, Telecom Room, Security Room,LV
Room, IT&Main IT Room)Approval
6 02-Sep-15 08-Sep-15 SCG 4
M1P2950 Foam Fire System for (Generator Room, Feul Tank Room)
Approval
6 09-Sep-15 15-Sep-15 SCG 3
Plumbing System APlumbing System Approval 18 27-Jul-15 16-Aug-15 72
M1P3230 PPR Domestic Water Pipes Approval 6 27-Jul-15 02-Aug-15 SCG 54
M1P3240 UPVC for Drainage System Approval 6 27-Jul-15 02-Aug-15 SCG 48
Jun Jul Aug Sep Oct Nov Dec Jan eb
2015 2016
25-Aug-15, Electrical Equipment
15-Sep-15, Mechanical Materia
25-Aug-15, HVAC System Approval
15-Sep-15, Fire Fighting System
16-Aug-15, Plumbing System Approva
Majarrah Business Complex Classic Schedule Layout 22-Jun-15 14:36
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 14 of 39 TASK filter: All Activities
© Primavera Systems, Inc.
Activity ID Activity Name Original
Duration
Start Finish Consultant Contractor Total
Float
M1P3250 PVC for Forced Main Line Approval 6 27-Jul-15 02-Aug-15 SCG 66
M1P3260 Irrigation System PVC Approval 6 27-Jul-15 02-Aug-15 SCG 66
M1P3270 Valves Approval 6 27-Jul-15 02-Aug-15 SCG 72
M1P3280 F.D , F.F.D , P.D , F.C.O , A.D , G.D , T.D Approval 6 27-Jul-15 02-Aug-15 SCG 36
M1P3290 Hose Bibbs Approval 6 27-Jul-15 02-Aug-15 SCG 84
M1P3300 HDPE Domestic Water Pipes Approval 6 03-Aug-15 09-Aug-15 SCG 72
M1P3310 HDPE for Drainage , Waste , Vent, Storm Systems Approval 6 03-Aug-15 09-Aug-15 SCG 72
M1P3320 Fountains Tank Approval 6 10-Aug-15 16-Aug-15 SCG 40
M1P3330 Water Fall Tank Approval 6 10-Aug-15 16-Aug-15 SCG 40
Mechanical EquipmMechanical Equipment Approval 30 21-Jul-15 25-Aug-15 60
HVAC EquipmentHVAC Equipment Approval 30 21-Jul-15 25-Aug-15 60
M1P2370 Child Water Pumps Approval 6 21-Jul-15 28-Jul-15 SCG 0
M1P2380 Exhaust Fans Approval 6 21-Jul-15 28-Jul-15 SCG 41
M1P2390 Supply Fans Approval 6 21-Jul-15 28-Jul-15 SCG 41
M1P2330 Fuel Oil Storage Tank Approval 6 19-Aug-15 25-Aug-15 SCG 2
M1P2340 AC DX Split Units Approval 6 19-Aug-15 25-Aug-15 SCG 60
M1P2350 Heat Exchangers Approval 6 19-Aug-15 25-Aug-15 SCG 2
M1P2360 Expansion and Compression Tanks Approval 6 19-Aug-15 25-Aug-15 SCG 2
M1P2400 Fan Coil Units Approval 6 19-Aug-15 25-Aug-15 SCG 17
Material P.OMaterial P.O 84 25-Jun-15 07-Oct-15 34
Electrical MaterialElectrical Material P.O 84 25-Jun-15 07-Oct-15 12
M210 PVC , EMT Conduit with Accessories Conduit Material P.O 3 25-Jun-15 28-Jun-15 Ofoq 48
M220 Cable Trays P.O 3 29-Jun-15 01-Jul-15 Ofoq 86
M230 Wires for Power and Lighting Material P.O 3 05-Aug-15 08-Aug-15 Ofoq 52
M240 Lighting Fixture Material P.O 3 12-Aug-15 15-Aug-15 Ofoq 40
M250 Wiring Devices P.O 3 12-Aug-15 15-Aug-15 Ofoq 15
M260 Fire Alarm Material P.O 3 12-Aug-15 15-Aug-15 Ofoq 0
M270 Structured Cable for Data System Material P.O 3 17-Aug-15 19-Aug-15 Ofoq 11
M280 Distribution Board Material P.O 3 17-Aug-15 19-Aug-15 Ofoq 24
M290 CCTV Cameras Material P.O 3 17-Aug-15 19-Aug-15 N/A 2
M300 Parking System Material P.O 3 02-Sep-15 05-Sep-15 N/A 0
M430 LV Cables P.O 3 16-Sep-15 19-Sep-15 Ofoq 12
M470 BMS P.O 3 04-Oct-15 07-Oct-15 Ofoq 1
Electrical EquipmentElectrical Equipment 39 13-Jul-15 29-Aug-15 42
M1P1830 R.M.U P.O 3 13-Jul-15 15-Jul-15 Ofoq 78
M1P1840 MVSG P.O 3 13-Jul-15 15-Jul-15 Ofoq 40
M1P1890 UPS P.O 3 25-Jul-15 27-Jul-15 Ofoq 12
M1P1820 Generator P.O 3 29-Jul-15 01-Aug-15 Ofoq 2
M1P1850 Transformer P.O 3 29-Jul-15 01-Aug-15 Ofoq 60
Jun Jul Aug Sep Oct Nov Dec Jan eb
2015 2016
25-Aug-15, Mechanical Equipment A
25-Aug-15, HVAC Equipment Appr
07-Oct-15, Material P.O
07-Oct-15, Electrical Mater
29-Aug-15, Electrical Equipment
Majarrah Business Complex Classic Schedule Layout 22-Jun-15 14:36
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 15 of 39 TASK filter: All Activities
© Primavera Systems, Inc.
Activity ID Activity Name Original
Duration
Start Finish Consultant Contractor Total
Float
M1P1860 MDB P.O 3 19-Aug-15 22-Aug-15 Ofoq 10
M1P1870 EMDB P.O 3 19-Aug-15 22-Aug-15 Ofoq 16
M1P1900 MCC P.O 3 19-Aug-15 22-Aug-15 Ofoq 16
M1P1880 ATS P.O 3 26-Aug-15 29-Aug-15 Ofoq 10
Mechanical MateriaMechanical Material P.O 69 29-Jun-15 19-Sep-15 46
HVAC System P.OHVAC System P.O 51 29-Jun-15 29-Aug-15 58
M1P2410 Galvanized Duct P.O 3 29-Jun-15 01-Jul-15 Ofoq 46
M1P2450 Child Water Pipes P.O 3 29-Jun-15 01-Jul-15 Ofoq 76
M1P2460 Child Water Insulation P.O 3 29-Jun-15 01-Jul-15 Ofoq 106
M1P2420 Volume Dampers P.O 3 26-Aug-15 29-Aug-15 Ofoq 10
M1P2430 Fire Dampers P.O 3 26-Aug-15 29-Aug-15 Ofoq 10
M1P2440 Fire Smoke Dampers P.O 3 26-Aug-15 29-Aug-15 Ofoq 10
M1P2470 Supply Air Grill P.O 3 26-Aug-15 29-Aug-15 Ofoq 46
M1P2480 Exhaust Air Grill P.O 3 26-Aug-15 29-Aug-15 Ofoq 46
Fire Fighting SystemFire Fighting System P.O 48 26-Jul-15 19-Sep-15 3
M1P2960 Seamless Black Steel Pipes P.O 3 26-Jul-15 28-Jul-15 Ofoq 26
M1P2970 Fire Fighting Network Valves (O.S&Y gate valve, Check
valve, Alarm Check Valve) P.O
3 29-Jul-15 01-Aug-15 Ofoq 29
M1P2980 Sprinklers P.O 3 29-Jul-15 01-Aug-15 Ofoq 20
M1P2990 Fire Hose Stations P.O 3 29-Jul-15 01-Aug-15 Ofoq 28
M1P3000 Fire Hose Real Stations P.O 3 29-Jul-15 01-Aug-15 Ofoq 28
M1P3010 Fire Extinguishers P.O 3 29-Jul-15 01-Aug-15 Ofoq 19
M1P3020 FM200 System for (MVSG Room, RMU Room,
Transformer Room, Telecom Room, Security Room,LV
Room, IT&Main IT Room)P.O
3 09-Sep-15 12-Sep-15 Ofoq 4
M1P3030 Foam Fire System for (Generator Room, Feul Tank Room) P 3 16-Sep-15 19-Sep-15 Ofoq 3
Plumbing System PPlumbing System P.O 15 03-Aug-15 19-Aug-15 72
M1P3340 PPR Domestic Water Pipes P.O 3 03-Aug-15 05-Aug-15 Ofoq 54
M1P3350 UPVC for Drainage System P.O 3 03-Aug-15 05-Aug-15 Ofoq 48
M1P3360 PVC for Forced Main Line P.O 3 03-Aug-15 05-Aug-15 Ofoq 66
M1P3370 Irrigation System PVC P.O 3 03-Aug-15 05-Aug-15 Ofoq 66
M1P3380 Valves P.O 3 03-Aug-15 05-Aug-15 Ofoq 72
M1P3390 F.D , F.F.D , P.D , F.C.O , A.D , G.D , T.D P.O 3 03-Aug-15 05-Aug-15 Ofoq 36
M1P3400 Hose Bibbs P.O 3 03-Aug-15 05-Aug-15 Ofoq 84
M1P3410 HDPE Domestic Water Pipes P.O 3 10-Aug-15 12-Aug-15 Ofoq 72
M1P3420 HDPE for Drainage , Waste , Vent, Storm Systems P.O 3 10-Aug-15 12-Aug-15 Ofoq 72
M1P3430 Fountains Tank P.O 3 17-Aug-15 19-Aug-15 N/A 40
M1P3440 Water Fall Tank P.O 3 17-Aug-15 19-Aug-15 N/A 40
Mechanical EquipmMechanical Equipment P.O 30 29-Jul-15 01-Sep-15 60
Jun Jul Aug Sep Oct Nov Dec Jan eb
2015 2016
19-Sep-15, Mechanical Materi
29-Aug-15, HVAC System P.O
19-Sep-15, Fire Fighting System
19-Aug-15, Plumbing System P.O
01-Sep-15, Mechanical Equipment
Majarrah Business Complex Classic Schedule Layout 22-Jun-15 14:36
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 16 of 39 TASK filter: All Activities
© Primavera Systems, Inc.
Activity ID Activity Name Original
Duration
Start Finish Consultant Contractor Total
Float
HVAC EquipmentHVAC Equipment P.O 30 29-Jul-15 01-Sep-15 60
M1P2530 Child Water Pumps P.O 6 29-Jul-15 04-Aug-15 Ofoq 0
M1P2540 Exhaust Fans P.O 6 29-Jul-15 04-Aug-15 Ofoq 52
M1P2550 Supply Fans P.O 6 29-Jul-15 04-Aug-15 Ofoq 52
M1P2490 Fuel Oil Storage Tank P.O 6 26-Aug-15 01-Sep-15 Ofoq 2
M1P2500 AC DX Split Units P.O 6 26-Aug-15 01-Sep-15 Ofoq 60
M1P2510 Heat Exchangers P.O 6 26-Aug-15 01-Sep-15 Ofoq 2
M1P2520 Expansion and Compression Tanks P.O 6 26-Aug-15 01-Sep-15 Ofoq 2
M1P2560 Fan Coil Units P.O 6 26-Aug-15 01-Sep-15 Ofoq 17
Material DeliveryMaterial Delivery 134 29-Jun-15 09-Dec-15 6
Electrical MaterialElectrical Material Delivery 121 29-Jun-15 24-Nov-15 1
M310 PVC , EMT Conduit with Accessories Conduit Material
Delivery
6 29-Jun-15 05-Jul-15 Ofoq 48
M320 Cable Trays Delivery 6 02-Jul-15 08-Jul-15 Ofoq 86
M330 Wires for Power and Lighting Material Delivery 6 09-Aug-15 15-Aug-15 Ofoq 52
M340 Lighting Fixture Material Delivery 18 16-Aug-15 05-Sep-15 N/A 40
M370 Structured Cable for Data System Material Delivery 18 20-Aug-15 09-Sep-15 Ofoq 11
M350 Wiring Devices Delivery 36 16-Aug-15 29-Sep-15 Ofoq 15
M390 CCTV Cameras Material Delivery 45 20-Aug-15 17-Oct-15 N/A 2
M360 Fire Alarm Material Delivery 52 16-Aug-15 20-Oct-15 Ofoq 0
M380 Distribution Board Material Delivery 52 20-Aug-15 25-Oct-15 Ofoq 24
M440 LV Cables Delivery 26 20-Sep-15 25-Oct-15 Ofoq 12
M400 Parking System Material Delivery 45 06-Sep-15 02-Nov-15 N/A 0
M480 BMS Delivery 40 08-Oct-15 24-Nov-15 Ofoq 1
Electrical EquipmentElectrical Equipment 90 16-Jul-15 05-Nov-15 14
M1P1920 R.M.U Delivery 26 16-Jul-15 17-Aug-15 Ofoq 78
M1P1940 Transformer Delivery 26 02-Aug-15 31-Aug-15 Ofoq 60
M1P1930 MVSG Delivery 52 16-Jul-15 16-Sep-15 Ofoq 40
M1P1950 MDB Delivery 52 23-Aug-15 27-Oct-15 Ofoq 10
M1P1960 EMDB Delivery 52 23-Aug-15 27-Oct-15 Ofoq 16
M1P1990 MCC Delivery 52 23-Aug-15 27-Oct-15 Ofoq 16
M1P1980 UPS Delivery 78 28-Jul-15 01-Nov-15 Ofoq 12
M1P1970 ATS Delivery 52 30-Aug-15 03-Nov-15 Ofoq 10
M1P1910 Generator Delivery 78 02-Aug-15 05-Nov-15 Ofoq 2
Mechanical MateriaMechanical Material Delivery 131 02-Jul-15 09-Dec-15 6
HVAC System DelivHVAC System Delivery 60 02-Jul-15 12-Sep-15 52
M1P2570 Galvanized Duct Delivery 6 02-Jul-15 08-Jul-15 Ofoq 46
M1P2610 Child Water Pipes Delivery 6 02-Jul-15 08-Jul-15 Ofoq 76
M1P2620 Child Water Insulation Delivery 6 02-Jul-15 08-Jul-15 Ofoq 106
M1P2580 Volume Dampers Delivery 12 30-Aug-15 12-Sep-15 Ofoq 10
Jun Jul Aug Sep Oct Nov Dec Jan eb
2015 2016
01-Sep-15, HVAC Equipment P.O
09-Dec-15, M
24-Nov-15, Elec
05-Nov-15, Electrica
09-Dec-15, M
12-Sep-15, HVAC System Delive
Majarrah Business Complex Classic Schedule Layout 22-Jun-15 14:36
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 17 of 39 TASK filter: All Activities
© Primavera Systems, Inc.
Activity ID Activity Name Original
Duration
Start Finish Consultant Contractor Total
Float
M1P2590 Fire Dampers Delivery 12 30-Aug-15 12-Sep-15 Ofoq 10
M1P2600 Fire Smoke Dampers Delivery 12 30-Aug-15 12-Sep-15 Ofoq 10
M1P2630 Supply Air Grill Delivery 12 30-Aug-15 12-Sep-15 Ofoq 46
M1P2640 Exhaust Air Grill Delivery 12 30-Aug-15 12-Sep-15 Ofoq 46
Fire Fighting SystemFire Fighting System Delivery 85 29-Jul-15 10-Nov-15 15
M1P3040 Seamless Black Steel Pipes Delivery 6 29-Jul-15 04-Aug-15 Ofoq 26
M1P3050 Fire Fighting Network Valves (O.S&Y gate valve, Check
valve, Alarm Check Valve) Delivery
18 02-Aug-15 22-Aug-15 Ofoq 29
M1P3070 Fire Hose Stations Delivery 36 02-Aug-15 12-Sep-15 Ofoq 28
M1P3080 Fire Hose Real Stations Delivery 36 02-Aug-15 12-Sep-15 Ofoq 28
M1P3060 Sprinklers Delivery 45 02-Aug-15 26-Sep-15 Ofoq 20
M1P3090 Fire Extinguishers Delivery 78 02-Aug-15 05-Nov-15 Ofoq 19
M1P3100 FM200 System for (MVSG Room, RMU Room,
Transformer Room, Telecom Room, Security Room,LV
Room, IT&Main IT Room)Delivery
45 13-Sep-15 09-Nov-15 Ofoq 4
M1P3110 Foam Fire System for (Generator Room, Feul Tank Room)
Delivery
40 20-Sep-15 10-Nov-15 Ofoq 3
Plumbing System DPlumbing System Delivery 30 06-Aug-15 09-Sep-15 60
M1P3450 PPR Domestic Water Pipes Delivery 6 06-Aug-15 12-Aug-15 Ofoq 54
M1P3460 UPVC for Drainage System Delivery 6 06-Aug-15 12-Aug-15 Ofoq 48
M1P3470 PVC for Forced Main Line Delivery 6 06-Aug-15 12-Aug-15 Ofoq 66
M1P3480 Irrigation System PVC Delivery 6 06-Aug-15 12-Aug-15 Ofoq 66
M1P3490 Valves Delivery 6 06-Aug-15 12-Aug-15 Ofoq 72
M1P3500 F.D , F.F.D , P.D , F.C.O , A.D , G.D , T.D Delivery 6 06-Aug-15 12-Aug-15 Ofoq 36
M1P3510 Hose Bibbs Delivery 6 06-Aug-15 12-Aug-15 Ofoq 84
M1P3520 HDPE Domestic Water Pipes Delivery 12 13-Aug-15 26-Aug-15 Ofoq 72
M1P3530 HDPE for Drainage , Waste , Vent, Storm Systems Delivery 12 13-Aug-15 26-Aug-15 Ofoq 72
M1P3540 Fountains Tank Delivery 18 20-Aug-15 09-Sep-15 N/A 40
M1P3550 Water Fall Tank Delivery 18 20-Aug-15 09-Sep-15 N/A 40
Mechanical EquipmMechanical Equipment Delivery 104 05-Aug-15 09-Dec-15 6
HVAC EquipmentHVAC Equipment Delivery 104 05-Aug-15 09-Dec-15 6
M1P2660 AC DX Split Units Delivery 26 02-Sep-15 05-Oct-15 Ofoq 60
M1P2720 Fan Coil Units Delivery 26 02-Sep-15 05-Oct-15 Ofoq 17
M1P2700 Exhaust Fans Delivery 52 05-Aug-15 08-Oct-15 Ofoq 52
M1P2710 Supply Fans Delivery 52 05-Aug-15 08-Oct-15 Ofoq 52
M1P2650 Fuel Oil Storage Tank Delivery 78 02-Sep-15 07-Dec-15 Ofoq 2
M1P2670 Heat Exchangers Delivery 78 02-Sep-15 07-Dec-15 Ofoq 2
M1P2680 Expansion and Compression Tanks Delivery 78 02-Sep-15 07-Dec-15 Ofoq 2
M1P2690 Child Water Pumps Delivery 104 05-Aug-15 09-Dec-15 Ofoq 0
Jun Jul Aug Sep Oct Nov Dec Jan eb
2015 2016
10-Nov-15, Fire Fig
09-Sep-15, Plumbing System Del
09-Dec-15, M
09-Dec-15, H
Majarrah Business Complex Classic Schedule Layout 22-Jun-15 14:36
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 18 of 39 TASK filter: All Activities
© Primavera Systems, Inc.
Activity ID Activity Name Original
Duration
Start Finish Consultant Contractor Total
Float
ConstructionConstruction 137 16-Jul-15 31-Dec-15 0
Structural WorkStructural Work 112 16-Jul-15 01-Dec-15 0
M1P3580 Openings for Duct Shafts 12 16-Jul-15 01-Aug-15 HW ECIP 28
M1P3590 Completion of All demolishing and remodeling in Plaza Leve 0 27-Aug-15 HW ECIP 53
M1P3600 Expansion Joints 12 29-Aug-15 10-Sep-15 HW ECIP 53
M1P3890 Equipments Concrete Foundations 12 04-Oct-15 19-Oct-15 HW ECIP 17
M1P4000 Upper Basement Screed 12 18-Nov-15 01-Dec-15 HW ECIP 0
MEP WorkMEP Work 98 02-Sep-15 31-Dec-15 0
Electrical WorksElectrical Works 98 02-Sep-15 31-Dec-15 0
Power SystemPower System 71 02-Sep-15 29-Nov-15 2
M1P3610 Upper Basement PVC Conduites for Power Outlets 12 02-Sep-15 15-Sep-15 SCG Ofoq 41
M1P3620 Upper Basement EMT Conduites for Power Outlets 12 02-Sep-15 15-Sep-15 SCG Ofoq 41
M1P3630 Upper Basement Cable Trays for LV Cables 12 02-Sep-15 15-Sep-15 SCG Ofoq 41
M1P3640 Wires for Upper Basement Power Outlets 6 16-Sep-15 26-Sep-15 SCG Ofoq 41
M1P3660 Laying Upper Basement DB Panels 2 26-Oct-15 27-Oct-15 SCG Ofoq 24
M1P3650 Laying Upper Basement LV Cables 6 26-Oct-15 01-Nov-15 SCG Ofoq 12
M1P3790 Wiring Devices Erection and termination 12 02-Nov-15 15-Nov-15 SCG Ofoq 12
M1P3670 Termination Upper Basement DB Panels 6 11-Nov-15 17-Nov-15 SCG Ofoq 12
Power EquipmentPower Equipment 35 20-Oct-15 29-Nov-15 2
M1P3700 Laying Upper Basement Transformer 2 20-Oct-15 21-Oct-15 SCG Ofoq 23
M1P3720 Laying R.M.U 2 20-Oct-15 21-Oct-15 SCG Ofoq 29
M1P3740 Laying MVSG 2 20-Oct-15 21-Oct-15 SCG Ofoq 17
M1P3730 Termination R.M.U 6 22-Oct-15 28-Oct-15 SCG Ofoq 29
M1P3680 Laying Upper Basement MCC's 2 28-Oct-15 29-Oct-15 SCG Ofoq 16
M1P3830 Laying EMDB 2 28-Oct-15 29-Oct-15 SCG Ofoq 16
M1P3900 Laying MDB 2 28-Oct-15 29-Oct-15 SCG Ofoq 10
M1P3860 Laying UPS 2 02-Nov-15 03-Nov-15 SCG Ofoq 12
M1P3710 Termination Upper Basement Transformer 12 22-Oct-15 04-Nov-15 SCG Ofoq 23
M1P3850 Laying ATS 2 04-Nov-15 05-Nov-15 SCG Ofoq 10
M1P3760 Laying Generator Package 2 07-Nov-15 08-Nov-15 SCG Ofoq 2
M1P3750 Termination MVSG 18 22-Oct-15 11-Nov-15 SCG Ofoq 17
M1P3690 Termination Upper Basement MCC's 12 31-Oct-15 12-Nov-15 SCG Ofoq 16
M1P3840 Termination EMDB 12 31-Oct-15 12-Nov-15 SCG Ofoq 16
M1P3880 Termination UPS 12 04-Nov-15 17-Nov-15 SCG Ofoq 12
M1P3870 Termination ATS 12 07-Nov-15 19-Nov-15 SCG Ofoq 10
M1P3910 Termination MDB 18 31-Oct-15 19-Nov-15 SCG Ofoq 10
M1P3770 Termination of Generator 18 09-Nov-15 29-Nov-15 SCG Ofoq 2
Lighting SystemLighting System 36 02-Sep-15 19-Oct-15 25
Jun Jul Aug Sep Oct Nov Dec Jan eb
2015 2016
31-Dec-
01-Dec-15, Str
31-Dec-
31-Dec-
29-Nov-15, Pow
29-Nov-15, Pow
19-Oct-15, Lighting Sys
Majarrah Business Complex Classic Schedule Layout 22-Jun-15 14:36
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 19 of 39 TASK filter: All Activities
© Primavera Systems, Inc.
Activity ID Activity Name Original
Duration
Start Finish Consultant Contractor Total
Float
M1P3800 Upper Basement PVC Conduites for Lighting Outlets 12 02-Sep-15 15-Sep-15 SCG Ofoq 25
M1P3810 Upper Basement EMT Conduites for Lighting Outlets 12 02-Sep-15 15-Sep-15 SCG Ofoq 25
M1P3820 Wires for Upper Basement Lighting Outlets 6 16-Sep-15 26-Sep-15 SCG Ofoq 25
M1P3780 Lighting Fixture Erection and termination 18 27-Sep-15 19-Oct-15 SCG Ofoq 25
Low Current SysteLow Current Systems 98 02-Sep-15 31-Dec-15 0
Fire Alarm SystemFire Alarm System 98 02-Sep-15 31-Dec-15 0
M1P4010 EMT Conduites 18 02-Sep-15 26-Sep-15 SCG Ofoq 19
M1P4020 Fire Alarm Cable 18 21-Oct-15 10-Nov-15 SCG Ofoq 0
M1P4030 Fire Alarm Devices 18 11-Nov-15 01-Dec-15 SCG Ofoq 0
M1P4040 Testing And Precommissioning 25 02-Dec-15 31-Dec-15 SCG Ofoq 0
Data SystemData System 98 02-Sep-15 31-Dec-15 0
M1P4050 EMT Conduites 18 02-Sep-15 26-Sep-15 SCG Ofoq 0
M1P4060 Structured Data Cable 18 27-Sep-15 19-Oct-15 SCG Ofoq 0
M1P4070 Face Plates Devices 18 20-Oct-15 09-Nov-15 SCG Ofoq 0
M1P4080 Testing And Precommissioning 44 10-Nov-15 31-Dec-15 SCG Ofoq 0
CCTV SystemCCTV System 98 02-Sep-15 31-Dec-15 0
M1P4090 EMT Conduites 18 02-Sep-15 26-Sep-15 SCG Ofoq 0
M1P4100 Structured Data Cable 18 27-Sep-15 19-Oct-15 SCG Ofoq 0
M1P4110 Cameras Devices 18 20-Oct-15 09-Nov-15 SCG Ofoq 0
M1P4120 Testing And Precommissioning 44 10-Nov-15 31-Dec-15 SCG Ofoq 0
BMS SystemBMS System 97 02-Sep-15 30-Dec-15 1
M1P4130 EMT Conduites 18 02-Sep-15 26-Sep-15 SCG Ofoq 32
M1P4140 Structured Data Cable 18 27-Sep-15 19-Oct-15 SCG Ofoq 32
M1P4150 BMS System with FACP Termination 12 25-Nov-15 08-Dec-15 SCG Ofoq 1
M1P4160 Testing And Precommissioning 18 09-Dec-15 30-Dec-15 SCG Ofoq 1
Parking SystemParking System 98 02-Sep-15 31-Dec-15 0
M1P4170 EMT Conduites 18 02-Sep-15 26-Sep-15 SCG Ofoq 12
M1P4180 Structured Data Cable 18 27-Sep-15 19-Oct-15 SCG Ofoq 12
M1P4190 Parking System 20 03-Nov-15 25-Nov-15 SCG Ofoq 0
M1P4200 Testing And Precommissioning 30 26-Nov-15 31-Dec-15 SCG Ofoq 0
Mechanical WorksMechanical Works 98 02-Sep-15 31-Dec-15 0
HVAC SystemHVAC System 98 02-Sep-15 31-Dec-15 0
M1P4210 Galvanized Duct Erection 18 02-Sep-15 26-Sep-15 SCG Ofoq 1
M1P4230 Child Water Pipes Erection 18 02-Sep-15 26-Sep-15 SCG Ofoq 31
M1P4220 Volume Dampers , Fire Dampers and Fire Smoke Dampers
Erection
12 27-Sep-15 11-Oct-15 SCG Ofoq 1
M1P4250 Child Water Pipes Test and Flushing 12 27-Sep-15 11-Oct-15 SCG Ofoq 31
M1P4290 Fan Coil Unit Erection 12 07-Oct-15 21-Oct-15 SCG Ofoq 17
M1P4240 Duct Smoke Test 12 12-Oct-15 26-Oct-15 SCG Ofoq 1
M1P4270 Child Water Pipes Insulation 12 12-Oct-15 26-Oct-15 SCG Ofoq 31
Jun Jul Aug Sep Oct Nov Dec Jan eb
2015 2016
31-Dec-
31-Dec-
31-Dec-
31-Dec-
30-Dec-
31-Dec-
31-Dec-
31-Dec-
Majarrah Business Complex Classic Schedule Layout 22-Jun-15 14:36
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 20 of 39 TASK filter: All Activities
© Primavera Systems, Inc.
Activity ID Activity Name Original
Duration
Start Finish Consultant Contractor Total
Float
M1P4260 Duct Insulation 12 27-Oct-15 09-Nov-15 SCG Ofoq 1
M1P4280 Air Grill Supply and Exhaust 18 10-Nov-15 30-Nov-15 SCG Ofoq 1
HVAC EquipmentHVAC Equipment 72 07-Oct-15 31-Dec-15 0
M1P4300 AC DX Split Units Erection 12 07-Oct-15 21-Oct-15 SCG Ofoq 60
M1P4310 Exhaust Fans Erection 18 10-Oct-15 31-Oct-15 SCG Ofoq 52
M1P4320 Supply Fans Erection 18 10-Oct-15 31-Oct-15 SCG Ofoq 52
M1P4330 Fuel Oil Storage Tank Erection 18 08-Dec-15 29-Dec-15 SCG Ofoq 2
M1P4340 Heat Exchangers Erection 18 08-Dec-15 29-Dec-15 SCG Ofoq 2
M1P4350 Expansion and Compression Tanks Erection 18 08-Dec-15 29-Dec-15 SCG Ofoq 2
M1P4360 Child Water Pumps Erection 18 10-Dec-15 31-Dec-15 SCG Ofoq 0
Fire Fighting SysteFire Fighting System 95 02-Sep-15 28-Dec-15 3
M1P4370 Seamless Black Steel Pipes Erection 18 02-Sep-15 26-Sep-15 SCG Ofoq 2
M1P4380 Fire Fighting Network Valves (O.S&Y gate valve, Check
valve, Alarm Check Valve) Erection
6 27-Sep-15 03-Oct-15 SCG Ofoq 2
M1P4450 Pipe Testing and Flushing 12 04-Oct-15 19-Oct-15 SCG Ofoq 2
M1P4390 Fire Hose Stations Erection 36 13-Sep-15 29-Oct-15 SCG Ofoq 28
M1P4400 Fire Hose Real Stations Erection 36 13-Sep-15 29-Oct-15 SCG Ofoq 28
M1P4420 Fire Extinguishers 3 07-Nov-15 09-Nov-15 SCG Ofoq 19
M1P4410 Sprinklers Erection 45 20-Oct-15 10-Dec-15 SCG Ofoq 2
M1P4430 FM200 System for (MVSG Room, RMU Room,
Transformer Room, Telecom Room, Security Room,LV
Room, IT&Main IT Room)
40 10-Nov-15 27-Dec-15 SCG Ofoq 4
M1P4440 Foam Fire System for (Generator Room, Feul Tank Room)
Erection
40 11-Nov-15 28-Dec-15 SCG Ofoq 3
Plumbing SystemPlumbing System 54 02-Sep-15 09-Nov-15 19
M1P4510 F.D , F.F.D , P.D , F.C.O , A.D , G.D , T.D Erection 12 02-Sep-15 15-Sep-15 SCG Ofoq 19
M1P4460 PPR Domestic Water Pipes Erection 18 02-Sep-15 26-Sep-15 SCG Ofoq 37
M1P4490 Irrigation System PVC Erection 18 02-Sep-15 26-Sep-15 SCG Ofoq 49
M1P4500 Valves Erection 6 27-Sep-15 03-Oct-15 SCG Ofoq 37
M1P4520 Hose Bibbs Erection 6 27-Sep-15 03-Oct-15 SCG Ofoq 49
M1P4470 UPVC for Drainage System Erection 18 16-Sep-15 11-Oct-15 SCG Ofoq 19
M1P4570 Testing Domestic Network 6 04-Oct-15 11-Oct-15 SCG Ofoq 37
M1P4550 Fountains Tank Erection 26 10-Sep-15 15-Oct-15 SCG N/A 40
M1P4560 Water Fall Tank Erection 26 10-Sep-15 15-Oct-15 SCG N/A 40
M1P4530 HDPE Domestic Water Pipes Erection 6 12-Oct-15 19-Oct-15 SCG Ofoq 37
M1P4480 PVC for Forced Main Line Erection 12 12-Oct-15 26-Oct-15 SCG Ofoq 19
M1P4580 Testing for Drainage Network 6 27-Oct-15 02-Nov-15 SCG Ofoq 19
M1P4540 HDPE for Drainage , Waste , Vent, Storm Systems Erection 6 03-Nov-15 09-Nov-15 SCG Ofoq 19
Finishing WorkFinishing Work 126 29-Jul-15 29-Dec-15 2
Jun Jul Aug Sep Oct Nov Dec Jan eb
2015 2016
31-Dec-
28-Dec-
09-Nov-15, Plumbi
29-Dec-
Majarrah Business Complex Classic Schedule Layout 22-Jun-15 14:36
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 21 of 39 TASK filter: All Activities
© Primavera Systems, Inc.
Activity ID Activity Name Original
Duration
Start Finish Consultant Contractor Total
Float
M1P4660 Block Work Completion for Equipments / Service / Stores
Rooms
12 29-Jul-15 11-Aug-15 HW ECIP 0
M1P4670 Plaster Work Applied for Equipments / Service / Stores Roo 12 12-Aug-15 25-Aug-15 HW ECIP 0
M1P4620 Curb Stone Material Erection 12 06-Sep-15 19-Sep-15 HW ECIP 46
M1P4680 MEP 1st Fix for Equipments / Service / Stores Rooms 26 26-Aug-15 28-Sep-15 SCG Ofoq 0
M1P4630 Interlock Material Erection 12 20-Sep-15 07-Oct-15 HW ECIP 46
M1P8420 Paint 1st and 2nd Coat for Ceiling and Walls in Upper
Basement
26 06-Sep-15 10-Oct-15 HW ECIP 54
M1P4590 False Ceiling Erection for Equipments / Service / Stores
Rooms
12 29-Sep-15 13-Oct-15 HW ECIP 0
M1P4610 Paint Applied for Equipments / Service / Stores Rooms 12 15-Oct-15 28-Oct-15 HW ECIP 0
M1P4650 Raised Floor Erection (Expected in IT & Main IT Room) 6 29-Oct-15 04-Nov-15 HW ECIP 6
M1P4600 Flooring Tiles Applied for Equipments / Service / Stores Roo 12 29-Oct-15 11-Nov-15 HW ECIP 0
M1P4640 Doors Erection for Equipments / Service / Stores Rooms 12 12-Nov-15 25-Nov-15 HW ECIP 5
M1P4690 MEP Final Fix for Equipments / Service / Stores Rooms 12 12-Nov-15 25-Nov-15 SCG Ofoq 0
M1P8430 Final Coat of Paint for Walls and Ceiling 12 12-Dec-15 26-Dec-15 HW 2
M1P8440 Epoxi Paint for Flooring 12 15-Dec-15 29-Dec-15 HW 2
Lower BasementLower Basement 164 15-Jun-15 31-Dec-15 0
GeneralGeneral 0 07-Jul-15 07-Jul-15 15
M1P6450 Client Clear Vision about Secuirty Issues as (CCTV, Access
Control...)
0 07-Jul-15 Client 6
M1P6460 Client Clear Vision about Data Issues as (Central, IT
requirements...)
0 07-Jul-15 Client 15
DesignDesign 60 15-Jun-15 25-Aug-15 41
Architectural DesArchitectural Design 24 15-Jun-15 12-Jul-15 0
M1P4700 Final Parking Layout for Lower Basement 0 28-Jun-15 Client 0
M1P4710 Final Architectural Dimensional Plan for Lower Basement 12 15-Jun-15 28-Jun-15 T.B 0
M1P4720 Final Architectural Package for Lower Basement 12 29-Jun-15 12-Jul-15 HW 0
Structural DesignStructural Design 6 19-Aug-15 25-Aug-15 41
M1P6440 Structural Design for Equipment Foundation (Fire Pump ,
Supply and Exhaust Fans........)
6 19-Aug-15 25-Aug-15 HW 41
MEP DesignMEP Design 24 29-Jun-15 28-Jul-15 6
Electrical SystemsElectrical Systems 24 29-Jun-15 28-Jul-15 6
Power SystemPower System 6 29-Jun-15 05-Jul-15 15
M1P4750 Updated Design for Power System 6 29-Jun-15 05-Jul-15 SCG 15
Lighting SystemLighting System 6 29-Jun-15 05-Jul-15 15
M1P4760 Updated Design for Lighting System 6 29-Jun-15 05-Jul-15 SCG 15
Fire Alarm SystemFire Alarm System 6 13-Jul-15 20-Jul-15 0
Jun Jul Aug Sep Oct Nov Dec Jan eb
2015 2016
31-Dec-
07-Jul-15, General
25-Aug-15, Design
12-Jul-15, Architectural Design
25-Aug-15, Structural Design
28-Jul-15, MEP Design
28-Jul-15, Electrical Systems
05-Jul-15, Power System
05-Jul-15, Lighting System
20-Jul-15, Fire Alarm System
Majarrah Business Complex Classic Schedule Layout 22-Jun-15 14:36
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 22 of 39 TASK filter: All Activities
© Primavera Systems, Inc.
Activity ID Activity Name Original
Duration
Start Finish Consultant Contractor Total
Float
M1P5370 Updated Design for Fire Alarm System 6 13-Jul-15 20-Jul-15 C/SCG 0
Parking SystemParking System 18 29-Jun-15 20-Jul-15 0
M1P5140 Updated Design for Parking System 18 29-Jun-15 20-Jul-15 C/SCG 0
CCTV SystemCCTV System 6 13-Jul-15 20-Jul-15 2
M1P4730 Updated Design for CCTV System 6 13-Jul-15 20-Jul-15 C/SCG 2
Data SystemData System 6 13-Jul-15 20-Jul-15 11
M1P4740 Updated Design for Data System 6 13-Jul-15 20-Jul-15 C/SCG 11
BMS SystemBMS System 6 21-Jul-15 28-Jul-15 6
M1P5690 Updated Design for BMS System 6 21-Jul-15 28-Jul-15 SCG 6
Mechanical SystemsMechanical Systems 18 29-Jun-15 20-Jul-15 6
HVAC SystemHVAC System 6 13-Jul-15 20-Jul-15 0
M1P4770 HVAC Updated Design for Lower Basement 6 13-Jul-15 20-Jul-15 SCG 0
Fire Fighting SysteFire Fighting System 6 29-Jun-15 05-Jul-15 3
M1P4820 Fire Fighting Updated Design for Lower Basement 6 29-Jun-15 05-Jul-15 SCG 3
Plumbing SystemPlumbing System 6 13-Jul-15 20-Jul-15 6
Drainage SystemDrainage System 6 13-Jul-15 20-Jul-15 6
M1P4780 Final Update for Lower Basement Drainage System 6 13-Jul-15 20-Jul-15 SCG 6
Shop DrawingsShop Drawings 60 29-Jun-15 08-Sep-15 41
Architectural ShoArchitectural Shop Drawing 12 13-Jul-15 28-Jul-15 4
M1P4830 Lower Basement Architectural Shop Drawing Submittal 6 13-Jul-15 20-Jul-15 ECIP 4
M1P4840 Lower Basement Architectural Shop Drawing Approval 6 21-Jul-15 28-Jul-15 HW 4
Structural Shop DStructural Shop Drawing 50 11-Jul-15 08-Sep-15 41
M1P4850 Lower Basement Construction , Expansion Joints Details
Shop Drawing Submittal
6 11-Jul-15 16-Jul-15 ECIP 64
M1P4860 Lower Basement Construction , Expansion Joints Details
Shop Drawing Approval
6 19-Jul-15 26-Jul-15 HW 64
M1P6470 Lower Basement Equipments Foundations shop drawings
Submittal
6 26-Aug-15 01-Sep-15 ECIP 41
M1P6480 Lower Basement Equipments Foundations shop drawings
Approval
6 02-Sep-15 08-Sep-15 HW 41
Electrical SystemsElectrical Systems 36 06-Jul-15 18-Aug-15 0
Power SystemPower System 12 06-Jul-15 20-Jul-15 15
M1P4870 Lower Basement Power System Layout Submittal 6 06-Jul-15 12-Jul-15 Ofoq 15
M1P4880 Lower Basement Power System Layout Approval 6 13-Jul-15 20-Jul-15 SCG 15
Lighting SystemLighting System 12 06-Jul-15 20-Jul-15 15
M1P4890 Lower Basement Lighting System Layout Submittal 6 06-Jul-15 12-Jul-15 Ofoq 15
M1P4900 Lower Basement Lighting System Layout Approval 6 13-Jul-15 20-Jul-15 SCG 15
Fire Alarm SystemFire Alarm System 12 21-Jul-15 04-Aug-15 12
M1P5380 Lower Basement Fire Alarm System Layout Submittal 6 21-Jul-15 28-Jul-15 Ofoq 12
Jun Jul Aug Sep Oct Nov Dec Jan eb
2015 2016
20-Jul-15, Parking System
20-Jul-15, CCTV System
20-Jul-15, Data System
28-Jul-15, BMS System
20-Jul-15, Mechanical Systems
20-Jul-15, HVAC System
05-Jul-15, Fire Fighting System
20-Jul-15, Plumbing System
20-Jul-15, Drainage System
08-Sep-15, Shop Drawings
28-Jul-15, Architectural Shop Drawing
08-Sep-15, Structural Shop Draw
18-Aug-15, Electrical Systems
20-Jul-15, Power System
20-Jul-15, Lighting System
04-Aug-15, Fire Alarm System
Majarrah Business Complex Classic Schedule Layout 22-Jun-15 14:36
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 23 of 39 TASK filter: All Activities
© Primavera Systems, Inc.
Activity ID Activity Name Original
Duration
Start Finish Consultant Contractor Total
Float
M1P5390 Lower Basement Fire Alarm System Layout Approval 6 29-Jul-15 04-Aug-15 SCG 12
Parking SystemParking System 12 21-Jul-15 04-Aug-15 0
M1P5120 Lower Basement Parking System Layout Submittal 6 21-Jul-15 28-Jul-15 Ofoq 0
M1P5130 Lower Basement Parking System Layout Approval 6 29-Jul-15 04-Aug-15 SCG 0
CCTV SystemCCTV System 12 21-Jul-15 04-Aug-15 2
M1P4910 Lower Basement CCTV System Layout Submittal 6 21-Jul-15 28-Jul-15 Ofoq 2
M1P4920 Lower Basement CCTV System Layout Approval 6 29-Jul-15 04-Aug-15 SCG 2
Data SystemData System 12 21-Jul-15 04-Aug-15 11
M1P4930 Lower Basement Data System Layout Submittal 6 21-Jul-15 28-Jul-15 Ofoq 11
M1P4940 Lower Basement Data System Layout Approval 6 29-Jul-15 04-Aug-15 SCG 11
BMS SystemBMS System 12 05-Aug-15 18-Aug-15 0
M1P5700 Lower Basement BMS System Layout Submittal 6 05-Aug-15 11-Aug-15 Ofoq 0
M1P5710 Lower Basement BMS System Layout Approval 6 12-Aug-15 18-Aug-15 SCG 0
Mechanical SysteMechanical Systems 42 29-Jun-15 18-Aug-15 41
HVAC SystemHVAC System 42 29-Jun-15 18-Aug-15 41
M1P5920 Fans Static Pressure Calculations Submittal 6 29-Jun-15 05-Jul-15 Ofoq 21
M1P5930 Fans Static Pressure Calculations Approval 6 06-Jul-15 12-Jul-15 SCG 21
M1P7250 Builder Work for Shaft Opening Layout Submittal 3 13-Jul-15 15-Jul-15 Ofoq 22
M1P7260 Builder Work for Shaft Opening Layout Approval 6 16-Jul-15 25-Jul-15 HW 22
M1P4950 Lower Basement HVAC System Layout Submittal 6 21-Jul-15 28-Jul-15 Ofoq 0
M1P4960 Lower Basement HVAC System Layout Approval 6 29-Jul-15 04-Aug-15 SCG 0
M1P6420 Lower Basement Fan Room Details Submittal 6 05-Aug-15 11-Aug-15 Ofoq 41
M1P6430 Lower Basement Fan Room Details Approval 6 12-Aug-15 18-Aug-15 SCG 41
Fire Fighting SystemFire Fighting System 12 06-Jul-15 20-Jul-15 3
M1P4970 Lower Basement Fire Fighting System Layout Submittal 6 06-Jul-15 12-Jul-15 Ofoq 3
M1P4980 Lower Basement Fire Fighting System Layout Approval 6 13-Jul-15 20-Jul-15 SCG 3
Plumbing SystemPlumbing System 12 21-Jul-15 04-Aug-15 11
Drainage SystemDrainage System 12 21-Jul-15 04-Aug-15 11
M1P4990 Lower Basement Drainage System Layout Submittal 6 21-Jul-15 28-Jul-15 Ofoq 11
M1P5000 Lower Basement Drainage System Layout Approval 6 29-Jul-15 04-Aug-15 SCG 11
Composite DrawiComposite Drawing 12 19-Aug-15 01-Sep-15 0
M1P5050 Lower Basement MEP Composite Drawing Submittal 6 19-Aug-15 25-Aug-15 Ofoq 0
M1P5060 Lower Basement MEP Composite Drawing Approval 6 26-Aug-15 01-Sep-15 SCG 0
MaterialsMaterials 149 15-Jun-15 13-Dec-15 3
Finishing MateriaFinishing Materials 35 27-Jul-15 05-Sep-15 58
Material SubmittalMaterial Submittal 20 27-Jul-15 18-Aug-15 58
M110001246 Expansion Joints Submittal 6 27-Jul-15 02-Aug-15 ECIP 64
M1P5070 False Ceiling Material Submittal 18 29-Jul-15 18-Aug-15 ECIP 21
Jun Jul Aug Sep Oct Nov Dec Jan eb
2015 2016
04-Aug-15, Parking System
04-Aug-15, CCTV System
04-Aug-15, Data System
18-Aug-15, BMS System
18-Aug-15, Mechanical Systems
18-Aug-15, HVAC System
20-Jul-15, Fire Fighting System
04-Aug-15, Plumbing System
04-Aug-15, Drainage System
01-Sep-15, Composite Drawing
13-Dec-15,
05-Sep-15, Finishing Materials
18-Aug-15, Material Submittal
Majarrah Business Complex Classic Schedule Layout 22-Jun-15 14:36
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 24 of 39 TASK filter: All Activities
© Primavera Systems, Inc.
Activity ID Activity Name Original
Duration
Start Finish Consultant Contractor Total
Float
M1P5080 Flooring Tiles Material Submittal 18 29-Jul-15 18-Aug-15 ECIP 45
M1P5090 Paint Material Submittal 18 29-Jul-15 18-Aug-15 ECIP 33
M1P5100 Curb Stone Material Submittal 18 29-Jul-15 18-Aug-15 ECIP 46
M1P5110 Interlock Material Submittal 18 29-Jul-15 18-Aug-15 ECIP 58
M1P7610 Doors Submittal 18 29-Jul-15 18-Aug-15 ECIP 58
Material ApprovalMaterial Approval 20 03-Aug-15 25-Aug-15 58
M110001256 Expansion Joints Approval 6 03-Aug-15 09-Aug-15 HW 64
M1P5150 False Ceiling Material Approval 6 19-Aug-15 25-Aug-15 HW 21
M1P5160 Flooring Tiles Material Approval 6 19-Aug-15 25-Aug-15 HW 45
M1P5170 Paint Material Approval 6 19-Aug-15 25-Aug-15 HW 33
M1P5180 Curb Stone Material Approval 6 19-Aug-15 25-Aug-15 HW 46
M1P5190 Interlock Material Approval 6 19-Aug-15 25-Aug-15 HW 58
M1P7630 Doors Approval 6 19-Aug-15 25-Aug-15 HW 58
Material P.OMaterial P.O 17 10-Aug-15 29-Aug-15 58
M110001266 Expansion Joints P.O 3 10-Aug-15 12-Aug-15 ECIP 64
M1P5200 False Ceiling Material P.O 3 26-Aug-15 29-Aug-15 ECIP 21
M1P5210 Flooring Tiles Material P.O 3 26-Aug-15 29-Aug-15 ECIP 45
M1P5220 Paint Material P.O 3 26-Aug-15 29-Aug-15 ECIP 33
M1P5230 Curb Stone Material P.O 3 26-Aug-15 29-Aug-15 ECIP 46
M1P5240 Interlock Material P.O 3 26-Aug-15 29-Aug-15 ECIP 58
M1P7650 Doors P.O 3 26-Aug-15 29-Aug-15 ECIP 58
Material DeliveryMaterial Delivery 20 13-Aug-15 05-Sep-15 58
M110001276 Expansion Joints Delivery 6 13-Aug-15 19-Aug-15 ECIP 64
M1P5250 False Ceiling Material Delivery 6 30-Aug-15 05-Sep-15 ECIP 21
M1P5260 Flooring Tiles Material Delivery 6 30-Aug-15 05-Sep-15 ECIP 45
M1P5270 Paint Material Delivery 6 30-Aug-15 05-Sep-15 ECIP 33
M1P5280 Curb Stone Material Delivery 6 30-Aug-15 05-Sep-15 ECIP 46
M1P5290 Interlock Material Delivery 6 30-Aug-15 05-Sep-15 ECIP 58
M1P7670 Doors Delivery 6 30-Aug-15 05-Sep-15 ECIP 58
MEP MaterialsMEP Materials 149 15-Jun-15 13-Dec-15 3
Material SubmittalMaterial Submittal 72 15-Jun-15 08-Sep-15 40
Electrical Material SElectrical Material Submittal 72 15-Jun-15 08-Sep-15 20
M490 PVC , EMT Conduit with Accessories Material Submittal 3 15-Jun-15 17-Jun-15 Ofoq 48
M570 Cable Trays Submittal 6 15-Jun-15 21-Jun-15 Ofoq 86
M530 Wires for Power and Lighting Material Submittal 6 21-Jul-15 28-Jul-15 Ofoq 56
M520 Lighting Fixture Material Submittal 12 21-Jul-15 04-Aug-15 Ofoq 44
M560 Wiring Devices Submittal 12 21-Jul-15 04-Aug-15 Ofoq 15
M580 Fire Alarm Material Submittal 12 21-Jul-15 04-Aug-15 Ofoq 0
M500 Structured Cable for Data System Material Submittal 4 05-Aug-15 09-Aug-15 Ofoq 11
Jun Jul Aug Sep Oct Nov Dec Jan eb
2015 2016
25-Aug-15, Material Approval
29-Aug-15, Material P.O
05-Sep-15, Material Delivery
13-Dec-15,
08-Sep-15, Material Submittal
08-Sep-15, Electrical Material Su
Majarrah Business Complex Classic Schedule Layout 22-Jun-15 14:36
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 25 of 39 TASK filter: All Activities
© Primavera Systems, Inc.
Activity ID Activity Name Original
Duration
Start Finish Consultant Contractor Total
Float
M510 Distribution Board Material Submittal 16 21-Jul-15 09-Aug-15 Ofoq 24
M540 CCTV Cameras Material Submittal 4 05-Aug-15 09-Aug-15 N/A 2
M550 Parking System Material Submittal 18 05-Aug-15 25-Aug-15 N/A 0
M900 LV Cables Submittal 6 02-Sep-15 08-Sep-15 Ofoq 12
M930 BMS Submittal 18 19-Aug-15 08-Sep-15 Ofoq 1
Electrical EquipmentElectrical Equipment 18 21-Jul-15 11-Aug-15 16
M1P5410 MCC Submittal 18 21-Jul-15 11-Aug-15 Ofoq 16
Mechanical MateriaMechanical Material Submittal 30 13-Jul-15 18-Aug-15 58
HVAC System SubmHVAC System Submittal 12 05-Aug-15 18-Aug-15 58
M1P5720 Galvanized Duct Submittal 6 05-Aug-15 11-Aug-15 Ofoq 4
M1P5760 Child Water Pipes Submittal 6 05-Aug-15 11-Aug-15 Ofoq 34
M1P5770 Child Water Insulation Submittal 6 05-Aug-15 11-Aug-15 Ofoq 64
M1P5730 Volume Dampers Submittal 12 05-Aug-15 18-Aug-15 Ofoq 10
M1P5740 Fire Dampers Submittal 12 05-Aug-15 18-Aug-15 Ofoq 10
M1P5750 Fire Smoke Dampers Submittal 12 05-Aug-15 18-Aug-15 Ofoq 10
M1P5780 Supply Air Grill Submittal 12 05-Aug-15 18-Aug-15 Ofoq 46
M1P5790 Exhaust Air Grill Submittal 12 05-Aug-15 18-Aug-15 Ofoq 46
Fire Fighting SystemFire Fighting System Submittal 6 21-Jul-15 28-Jul-15 23
M1P6490 Seamless Black Steel Pipes Submittal 3 21-Jul-15 25-Jul-15 Ofoq 20
M1P6500 Fire Fighting Network Valves (O.S&Y gate valve, Check
valve, Alarm Check Valve) Submittal
6 21-Jul-15 28-Jul-15 Ofoq 23
M1P6510 Sprinklers Submittal 6 21-Jul-15 28-Jul-15 Ofoq 14
M1P6540 Fire Hose Stations Submittal 6 21-Jul-15 28-Jul-15 Ofoq 22
M1P6550 Fire Hose Real Stations Submittal 6 21-Jul-15 28-Jul-15 Ofoq 22
M1P6560 Fire Extinguishers Submittal 6 21-Jul-15 28-Jul-15 Ofoq 13
Plumbing System SPlumbing System Submittal 6 05-Aug-15 11-Aug-15 64
M1P6840 PPR Domestic Water Pipes Submittal 6 05-Aug-15 11-Aug-15 Ofoq 46
M1P6860 UPVC for Drainage System Submittal 6 05-Aug-15 11-Aug-15 Ofoq 40
M1P6870 PVC for Forced Main Line Submittal 6 05-Aug-15 11-Aug-15 Ofoq 58
M1P6890 Valves Submittal 6 05-Aug-15 11-Aug-15 Ofoq 64
M1P6900 F.D , F.F.D , P.D , F.C.O , A.D , G.D , T.D Submittal 6 05-Aug-15 11-Aug-15 Ofoq 28
Mechanical EquipmMechanical Equipment Submittal 30 13-Jul-15 18-Aug-15 35
HVAC EquipmentHVAC Equipment Submittal 30 13-Jul-15 18-Aug-15 35
M1P5850 Exhaust Fans Submittal 12 13-Jul-15 28-Jul-15 Ofoq 21
M1P5860 Supply Fans Submittal 12 13-Jul-15 28-Jul-15 Ofoq 21
M1P5810 AC DX Split Units Submittal 12 05-Aug-15 18-Aug-15 Ofoq 35
M1P5870 Fan Coil Units Submittal 12 05-Aug-15 18-Aug-15 Ofoq 17
Fire Fighting EquFire Fighting Equipment Submittal 6 21-Jul-15 28-Jul-15 3
M1P8450 Fire Pumps Submittal 6 21-Jul-15 28-Jul-15 Ofoq 3
Plumbing EquipmPlumbing Equipment Submittal 6 05-Aug-15 11-Aug-15 11
Jun Jul Aug Sep Oct Nov Dec Jan eb
2015 2016
11-Aug-15, Electrical Equipment
18-Aug-15, Mechanical Material Subm
18-Aug-15, HVAC System Submittal
28-Jul-15, Fire Fighting System Submittal
11-Aug-15, Plumbing System Submittal
18-Aug-15, Mechanical Equipment Su
18-Aug-15, HVAC Equipment Submi
28-Jul-15, Fire Fighting Equipment Submi
11-Aug-15, Plumbing Equipment Subm
Majarrah Business Complex Classic Schedule Layout 22-Jun-15 14:36
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 26 of 39 TASK filter: All Activities
© Primavera Systems, Inc.
Activity ID Activity Name Original
Duration
Start Finish Consultant Contractor Total
Float
M1P8460 Domestic Water Pump Submittal 6 05-Aug-15 11-Aug-15 Ofoq 11
M1P8470 Irrigation Pump Submittal 6 05-Aug-15 11-Aug-15 Ofoq 11
M1P8480 Waste Water Submersible Pumps Submittal 6 05-Aug-15 11-Aug-15 Ofoq 11
M1P8490 Sewage Water Submersible Pumps Submittal 6 05-Aug-15 11-Aug-15 Ofoq 11
Material ApprovalMaterial Approval 87 18-Jun-15 03-Oct-15 28
Electrical Material AElectrical Material Approval 87 18-Jun-15 03-Oct-15 8
M590 PVC , EMT Conduit with Accessories Conduit Material
Approval
6 18-Jun-15 24-Jun-15 SCG 48
M670 Cable Trays Approval 6 22-Jun-15 28-Jun-15 SCG 86
M630 Wires for Power and Lighting Material Approval 6 29-Jul-15 04-Aug-15 SCG 56
M620 Lighting Fixture Material Approval 6 05-Aug-15 11-Aug-15 SCG 44
M660 Wiring Devices Approval 6 05-Aug-15 11-Aug-15 SCG 15
M680 Fire Alarm Material Approval 6 05-Aug-15 11-Aug-15 SCG 0
M600 Structured Cable for Data System Material Approval 6 10-Aug-15 16-Aug-15 SCG 11
M610 Distribution Board Material Approval 6 10-Aug-15 16-Aug-15 SCG 24
M640 CCTV Cameras Material Approval 6 10-Aug-15 16-Aug-15 SCG 2
M650 Parking System Material Approval 6 26-Aug-15 01-Sep-15 SCG 0
M890 LV Cables Approval 6 09-Sep-15 15-Sep-15 SCG 12
M940 BMS Approval 18 09-Sep-15 03-Oct-15 SCG 1
Electrical EquipmentElectrical Equipment 6 12-Aug-15 18-Aug-15 16
M1P5500 MCC Approval 6 12-Aug-15 18-Aug-15 SCG 16
Mechanical MateriaMechanical Material Approval 27 26-Jul-15 25-Aug-15 58
HVAC System ApproHVAC System Approval 12 12-Aug-15 25-Aug-15 58
M1P5940 Galvanized Duct Approval 6 12-Aug-15 18-Aug-15 SCG 4
M1P5980 Child Water Pipes Approval 6 12-Aug-15 18-Aug-15 SCG 34
M1P5990 Child Water Insulation Approval 6 12-Aug-15 18-Aug-15 SCG 64
M1P5950 Volume Dampers Approval 6 19-Aug-15 25-Aug-15 SCG 10
M1P5960 Fire Dampers Approval 6 19-Aug-15 25-Aug-15 SCG 10
M1P5970 Fire Smoke Dampers Approval 6 19-Aug-15 25-Aug-15 SCG 10
M1P6000 Supply Air Grill Approval 6 19-Aug-15 25-Aug-15 SCG 46
M1P6010 Exhaust Air Grill Approval 6 19-Aug-15 25-Aug-15 SCG 46
Fire Fighting SystemFire Fighting System Approval 9 26-Jul-15 04-Aug-15 23
M1P6570 Seamless Black Steel Pipes Approval 6 26-Jul-15 01-Aug-15 SCG 20
M1P6580 Fire Fighting Network Valves (O.S&Y gate valve, Check
valve, Alarm Check Valve) Approval
6 29-Jul-15 04-Aug-15 SCG 23
M1P6590 Sprinklers Approval 6 29-Jul-15 04-Aug-15 SCG 14
M1P6620 Fire Hose Stations Approval 6 29-Jul-15 04-Aug-15 SCG 22
M1P6630 Fire Hose Real Stations Approval 6 29-Jul-15 04-Aug-15 SCG 22
M1P6640 Fire Extinguishers Approval 6 29-Jul-15 04-Aug-15 SCG 13
Plumbing System APlumbing System Approval 6 12-Aug-15 18-Aug-15 64
Jun Jul Aug Sep Oct Nov Dec Jan eb
2015 2016
03-Oct-15, Material Appro
03-Oct-15, Electrical Mater
18-Aug-15, Electrical Equipment
25-Aug-15, Mechanical Material Ap
25-Aug-15, HVAC System Approval
04-Aug-15, Fire Fighting System Approv
18-Aug-15, Plumbing System Approv
Majarrah Business Complex Classic Schedule Layout 22-Jun-15 14:36
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 27 of 39 TASK filter: All Activities
© Primavera Systems, Inc.
Activity ID Activity Name Original
Duration
Start Finish Consultant Contractor Total
Float
M1P6950 PPR Domestic Water Pipes Approval 6 12-Aug-15 18-Aug-15 SCG 46
M1P6970 UPVC for Drainage System Approval 6 12-Aug-15 18-Aug-15 SCG 40
M1P6980 PVC for Forced Main Line Approval 6 12-Aug-15 18-Aug-15 SCG 58
M1P7000 Valves Approval 6 12-Aug-15 18-Aug-15 SCG 64
M1P7010 F.D , F.F.D , P.D , F.C.O , A.D , G.D , T.D Approval 6 12-Aug-15 18-Aug-15 SCG 28
Mechanical EquipmMechanical Equipment Approval 24 29-Jul-15 25-Aug-15 35
HVAC EquipmentHVAC Equipment Approval 24 29-Jul-15 25-Aug-15 35
M1P6070 Exhaust Fans Approval 6 29-Jul-15 04-Aug-15 SCG 21
M1P6080 Supply Fans Approval 6 29-Jul-15 04-Aug-15 SCG 21
M1P6030 AC DX Split Units Approval 6 19-Aug-15 25-Aug-15 SCG 35
M1P6090 Fan Coil Units Approval 6 19-Aug-15 25-Aug-15 SCG 17
Fire Fighting EquFire Fighting Equipment Approval 6 29-Jul-15 04-Aug-15 3
M1P8500 Fire Pumps Approval 6 29-Jul-15 04-Aug-15 SCG 3
Plumbing EquipmPlumbing Equipment Approval 6 12-Aug-15 18-Aug-15 11
M1P8540 Domestic Water Pump Approval 6 12-Aug-15 18-Aug-15 SCG 11
M1P8550 Irrigation Pump Approval 6 12-Aug-15 18-Aug-15 SCG 11
M1P8560 Waste Water Submersible Pumps Approval 6 12-Aug-15 18-Aug-15 SCG 11
M1P8570 Sewage Water Submersible Pumps Approval 6 12-Aug-15 18-Aug-15 SCG 11
Material P.OMaterial P.O 84 25-Jun-15 07-Oct-15 28
Electrical MaterialElectrical Material P.O 84 25-Jun-15 07-Oct-15 8
M690 PVC , EMT Conduit with Accessories Conduit Material P.O 3 25-Jun-15 28-Jun-15 Ofoq 48
M770 Cable Trays P.O 3 29-Jun-15 01-Jul-15 Ofoq 86
M730 Wires for Power and Lighting Material P.O 3 05-Aug-15 08-Aug-15 Ofoq 56
M720 Lighting Fixture Material P.O 3 12-Aug-15 15-Aug-15 Ofoq 44
M760 Wiring Devices P.O 3 12-Aug-15 15-Aug-15 Ofoq 15
M780 Fire Alarm Material P.O 3 12-Aug-15 15-Aug-15 Ofoq 0
M700 Structured Cable for Data System Material P.O 3 17-Aug-15 19-Aug-15 Ofoq 11
M710 Distribution Board Material P.O 3 17-Aug-15 19-Aug-15 Ofoq 24
M740 CCTV Cameras Material P.O 3 17-Aug-15 19-Aug-15 N/A 2
M750 Parking System Material P.O 3 02-Sep-15 05-Sep-15 N/A 0
M910 LV Cables P.O 3 16-Sep-15 19-Sep-15 Ofoq 12
M950 BMS P.O 3 04-Oct-15 07-Oct-15 Ofoq 1
Electrical EquipmentElectrical Equipment 3 19-Aug-15 22-Aug-15 16
M1P5590 MCC P.O 3 19-Aug-15 22-Aug-15 Ofoq 16
Mechanical MateriaMechanical Material P.O 27 02-Aug-15 01-Sep-15 55
HVAC System P.OHVAC System P.O 9 19-Aug-15 29-Aug-15 58
M1P6100 Galvanized Duct P.O 3 19-Aug-15 22-Aug-15 Ofoq 4
M1P6140 Child Water Pipes P.O 3 19-Aug-15 22-Aug-15 Ofoq 34
M1P6150 Child Water Insulation P.O 3 19-Aug-15 22-Aug-15 Ofoq 64
M1P6110 Volume Dampers P.O 3 26-Aug-15 29-Aug-15 Ofoq 10
Jun Jul Aug Sep Oct Nov Dec Jan eb
2015 2016
25-Aug-15, Mechanical Equipment A
25-Aug-15, HVAC Equipment Appr
04-Aug-15, Fire Fighting Equipment App
18-Aug-15, Plumbing Equipment App
07-Oct-15, Material P.O
07-Oct-15, Electrical Mater
22-Aug-15, Electrical Equipment
01-Sep-15, Mechanical Material P
29-Aug-15, HVAC System P.O
Majarrah Business Complex Classic Schedule Layout 22-Jun-15 14:36
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 28 of 39 TASK filter: All Activities
© Primavera Systems, Inc.
Activity ID Activity Name Original
Duration
Start Finish Consultant Contractor Total
Float
M1P6120 Fire Dampers P.O 3 26-Aug-15 29-Aug-15 Ofoq 10
M1P6130 Fire Smoke Dampers P.O 3 26-Aug-15 29-Aug-15 Ofoq 10
M1P6160 Supply Air Grill P.O 3 26-Aug-15 29-Aug-15 Ofoq 46
M1P6170 Exhaust Air Grill P.O 3 26-Aug-15 29-Aug-15 Ofoq 46
Fire Fighting SystemFire Fighting System P.O 6 02-Aug-15 08-Aug-15 23
M1P6650 Seamless Black Steel Pipes P.O 3 02-Aug-15 04-Aug-15 Ofoq 20
M1P6660 Fire Fighting Network Valves (O.S&Y gate valve, Check
valve, Alarm Check Valve) P.O
3 05-Aug-15 08-Aug-15 Ofoq 23
M1P6670 Sprinklers P.O 3 05-Aug-15 08-Aug-15 Ofoq 14
M1P6700 Fire Hose Stations P.O 3 05-Aug-15 08-Aug-15 Ofoq 22
M1P6710 Fire Hose Real Stations P.O 3 05-Aug-15 08-Aug-15 Ofoq 22
M1P6720 Fire Extinguishers P.O 3 05-Aug-15 08-Aug-15 Ofoq 13
Plumbing System PPlumbing System P.O 3 19-Aug-15 22-Aug-15 64
M1P7060 PPR Domestic Water Pipes P.O 3 19-Aug-15 22-Aug-15 Ofoq 46
M1P7080 UPVC for Drainage System P.O 3 19-Aug-15 22-Aug-15 Ofoq 40
M1P7090 PVC for Forced Main Line P.O 3 19-Aug-15 22-Aug-15 Ofoq 58
M1P7110 Valves P.O 3 19-Aug-15 22-Aug-15 Ofoq 64
M1P7120 F.D , F.F.D , P.D , F.C.O , A.D , G.D , T.D P.O 3 19-Aug-15 22-Aug-15 Ofoq 28
Mechanical EquipmMechanical Equipment P.O 24 05-Aug-15 01-Sep-15 35
HVAC EquipmentHVAC Equipment P.O 24 05-Aug-15 01-Sep-15 35
M1P6230 Exhaust Fans P.O 6 05-Aug-15 11-Aug-15 Ofoq 21
M1P6240 Supply Fans P.O 6 05-Aug-15 11-Aug-15 Ofoq 21
M1P6190 AC DX Split Units P.O 6 26-Aug-15 01-Sep-15 Ofoq 35
M1P6250 Fan Coil Units P.O 6 26-Aug-15 01-Sep-15 Ofoq 17
Fire Fighting EquFire Fighting Equipment P.O 3 05-Aug-15 08-Aug-15 3
M1P8510 Fire Pumps P.O 3 05-Aug-15 08-Aug-15 Ofoq 3
Plumbing EquipmPlumbing Equipment P.O 3 19-Aug-15 22-Aug-15 11
M1P8580 Domestic Water Pump P.O 3 19-Aug-15 22-Aug-15 Ofoq 11
M1P8590 Irrigation Pump P.O 3 19-Aug-15 22-Aug-15 Ofoq 11
M1P8600 Waste Water Submersible Pumps P.O 3 19-Aug-15 22-Aug-15 Ofoq 11
M1P8610 Sewage Water Submersible Pumps P.O 3 19-Aug-15 22-Aug-15 Ofoq 11
Material DeliveryMaterial Delivery 137 29-Jun-15 13-Dec-15 3
Electrical MaterialElectrical Material Delivery 121 29-Jun-15 24-Nov-15 1
M790 PVC , EMT Conduit with Accessories Conduit Material
Delivery
6 29-Jun-15 05-Jul-15 Ofoq 48
M870 Cable Trays Delivery 6 02-Jul-15 08-Jul-15 Ofoq 86
M830 Wires for Power and Lighting Material Delivery 6 09-Aug-15 15-Aug-15 Ofoq 56
M820 Lighting Fixture Material Delivery 18 16-Aug-15 05-Sep-15 N/A 44
M800 Structured Cable for Data System Material Delivery 18 20-Aug-15 09-Sep-15 Ofoq 11
M860 Wiring Devices Delivery 36 16-Aug-15 29-Sep-15 Ofoq 15
Jun Jul Aug Sep Oct Nov Dec Jan eb
2015 2016
08-Aug-15, Fire Fighting System P.O
22-Aug-15, Plumbing System P.O
01-Sep-15, Mechanical Equipment
01-Sep-15, HVAC Equipment P.O
08-Aug-15, Fire Fighting Equipment P.O
22-Aug-15, Plumbing Equipment P.O
13-Dec-15,
24-Nov-15, Elec
Majarrah Business Complex Classic Schedule Layout 22-Jun-15 14:36
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 29 of 39 TASK filter: All Activities
© Primavera Systems, Inc.
Activity ID Activity Name Original
Duration
Start Finish Consultant Contractor Total
Float
M840 CCTV Cameras Material Delivery 45 20-Aug-15 17-Oct-15 N/A 2
M880 Fire Alarm Material Delivery 52 16-Aug-15 20-Oct-15 Ofoq 0
M810 Distribution Board Material Delivery 52 20-Aug-15 25-Oct-15 Ofoq 24
M920 LV Cables Delivery 26 20-Sep-15 25-Oct-15 Ofoq 12
M850 Parking System Material Delivery 45 06-Sep-15 02-Nov-15 N/A 0
M960 BMS Delivery 40 08-Oct-15 24-Nov-15 Ofoq 1
Electrical EquipmentElectrical Equipment 52 23-Aug-15 27-Oct-15 16
M1P5680 MCC Delivery 52 23-Aug-15 27-Oct-15 Ofoq 16
Mechanical MateriaMechanical Material Delivery 107 05-Aug-15 13-Dec-15 3
HVAC System DelivHVAC System Delivery 18 23-Aug-15 12-Sep-15 52
M1P6260 Galvanized Duct Delivery 6 23-Aug-15 29-Aug-15 Ofoq 4
M1P6300 Child Water Pipes Delivery 6 23-Aug-15 29-Aug-15 Ofoq 34
M1P6310 Child Water Insulation Delivery 6 23-Aug-15 29-Aug-15 Ofoq 64
M1P6270 Volume Dampers Delivery 12 30-Aug-15 12-Sep-15 Ofoq 10
M1P6280 Fire Dampers Delivery 12 30-Aug-15 12-Sep-15 Ofoq 10
M1P6290 Fire Smoke Dampers Delivery 12 30-Aug-15 12-Sep-15 Ofoq 10
M1P6320 Supply Air Grill Delivery 12 30-Aug-15 12-Sep-15 Ofoq 46
M1P6330 Exhaust Air Grill Delivery 12 30-Aug-15 12-Sep-15 Ofoq 46
Fire Fighting SystemFire Fighting System Delivery 81 05-Aug-15 12-Nov-15 13
M1P6730 Seamless Black Steel Pipes Delivery 6 05-Aug-15 11-Aug-15 Ofoq 20
M1P6740 Fire Fighting Network Valves (O.S&Y gate valve, Check
valve, Alarm Check Valve) Delivery
18 09-Aug-15 29-Aug-15 Ofoq 23
M1P6780 Fire Hose Stations Delivery 36 09-Aug-15 19-Sep-15 Ofoq 22
M1P6790 Fire Hose Real Stations Delivery 36 09-Aug-15 19-Sep-15 Ofoq 22
M1P6750 Sprinklers Delivery 45 09-Aug-15 03-Oct-15 Ofoq 14
M1P6800 Fire Extinguishers Delivery 78 09-Aug-15 12-Nov-15 Ofoq 13
Plumbing System DPlumbing System Delivery 6 23-Aug-15 29-Aug-15 64
M1P7170 PPR Domestic Water Pipes Delivery 6 23-Aug-15 29-Aug-15 Ofoq 46
M1P7190 UPVC for Drainage System Delivery 6 23-Aug-15 29-Aug-15 Ofoq 40
M1P7200 PVC for Forced Main Line Delivery 6 23-Aug-15 29-Aug-15 Ofoq 58
M1P7220 Valves Delivery 6 23-Aug-15 29-Aug-15 Ofoq 64
M1P7230 F.D , F.F.D , P.D , F.C.O , A.D , G.D , T.D Delivery 6 23-Aug-15 29-Aug-15 Ofoq 28
Mechanical EquipmMechanical Equipment Delivery 104 09-Aug-15 13-Dec-15 3
HVAC EquipmentHVAC Equipment Delivery 52 12-Aug-15 17-Oct-15 27
M1P6350 AC DX Split Units Delivery 26 02-Sep-15 05-Oct-15 Ofoq 35
M1P6410 Fan Coil Units Delivery 26 02-Sep-15 05-Oct-15 Ofoq 17
M1P6390 Exhaust Fans Delivery 52 12-Aug-15 17-Oct-15 Ofoq 21
M1P6400 Supply Fans Delivery 52 12-Aug-15 17-Oct-15 Ofoq 21
Fire Fighting EquFire Fighting Equipment Delivery 104 09-Aug-15 13-Dec-15 3
M1P8520 Fire Pumps Delivery 104 09-Aug-15 13-Dec-15 Ofoq 3
Jun Jul Aug Sep Oct Nov Dec Jan eb
2015 2016
27-Oct-15, Electrical E
13-Dec-15,
12-Sep-15, HVAC System Delive
12-Nov-15, Fire Fi
29-Aug-15, Plumbing System Delive
13-Dec-15,
17-Oct-15, HVAC Equip
13-Dec-15,
Majarrah Business Complex Classic Schedule Layout 22-Jun-15 14:36
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 30 of 39 TASK filter: All Activities
© Primavera Systems, Inc.
Activity ID Activity Name Original
Duration
Start Finish Consultant Contractor Total
Float
Plumbing EquipmPlumbing Equipment Delivery 78 23-Aug-15 26-Nov-15 11
M1P8620 Domestic Water Pump Delivery 78 23-Aug-15 26-Nov-15 Ofoq 11
M1P8630 Irrigation Pump Delivery 78 23-Aug-15 26-Nov-15 Ofoq 11
M1P8640 Waste Water Submersible Pumps Delivery 78 23-Aug-15 26-Nov-15 Ofoq 11
M1P8650 Sewage Water Submersible Pumps Delivery 78 23-Aug-15 26-Nov-15 Ofoq 11
ConstructionConstruction 138 15-Jul-15 31-Dec-15 0
Structural WorkStructural Work 119 15-Jul-15 08-Dec-15 4
M1P8340 Lower Basement PC Slab On Grade 18 15-Jul-15 06-Aug-15 HW ECIP 71
M1P7270 Openings for Duct Shafts 12 26-Jul-15 08-Aug-15 HW ECIP 22
M1P7290 Expansion Joints 12 20-Aug-15 02-Sep-15 HW ECIP 64
M1P7580 Equipments Concrete Foundations 12 09-Sep-15 26-Sep-15 HW ECIP 41
M1P7690 Lower Basement RC Slab On Grade 18 18-Nov-15 08-Dec-15 HW ECIP 4
MEP WorkMEP Work 98 02-Sep-15 31-Dec-15 0
Electrical WorksElectrical Works 98 02-Sep-15 31-Dec-15 0
Power SystemPower System 61 02-Sep-15 17-Nov-15 12
M1P7300 Lower Basement PVC Conduites for Power Outlets 12 02-Sep-15 15-Sep-15 SCG Ofoq 41
M1P7310 Lower Basement EMT Conduites for Power Outlets 12 02-Sep-15 15-Sep-15 SCG Ofoq 41
M1P7320 Lower Basement Cable Trays for LV Cables 12 02-Sep-15 15-Sep-15 SCG Ofoq 41
M1P7330 Wires for Lower Basement Power Outlets 6 16-Sep-15 26-Sep-15 SCG Ofoq 41
M1P7350 Laying Lower Basement DB Panels 2 26-Oct-15 27-Oct-15 SCG Ofoq 24
M1P7340 Laying Lower Basement LV Cables 6 26-Oct-15 01-Nov-15 SCG Ofoq 12
M1P7480 Wiring Devices Erection and termination 12 02-Nov-15 15-Nov-15 SCG Ofoq 12
M1P7360 Termination Lower Basement DB Panels 6 11-Nov-15 17-Nov-15 SCG Ofoq 12
Power EquipmentPower Equipment 14 28-Oct-15 12-Nov-15 16
M1P7370 Laying Lower Basement MCC's 2 28-Oct-15 29-Oct-15 SCG Ofoq 16
M1P7380 Termination Lower Basement MCC's 12 31-Oct-15 12-Nov-15 SCG Ofoq 16
Lighting SystemLighting System 36 02-Sep-15 19-Oct-15 29
M1P7490 Lower Basement PVC Conduites for Lighting Outlets 12 02-Sep-15 15-Sep-15 SCG Ofoq 29
M1P7500 Lower Basement EMT Conduites for Lighting Outlets 12 02-Sep-15 15-Sep-15 SCG Ofoq 29
M1P7510 Wires for Lower Basement Lighting Outlets 6 16-Sep-15 26-Sep-15 SCG Ofoq 29
M1P7470 Lighting Fixture Erection and termination 18 27-Sep-15 19-Oct-15 SCG Ofoq 29
Low Current SysteLow Current Systems 98 02-Sep-15 31-Dec-15 0
Fire Alarm SystemFire Alarm System 98 02-Sep-15 31-Dec-15 0
M1P7700 EMT Conduites 18 02-Sep-15 26-Sep-15 SCG Ofoq 19
M1P7710 Fire Alarm Cable 18 21-Oct-15 10-Nov-15 SCG Ofoq 0
M1P7720 Fire Alarm Devices 18 11-Nov-15 01-Dec-15 SCG Ofoq 0
M1P7730 Testing And Precommissioning 25 02-Dec-15 31-Dec-15 SCG Ofoq 0
Data SystemData System 98 02-Sep-15 31-Dec-15 0
M1P7740 EMT Conduites 18 02-Sep-15 26-Sep-15 SCG Ofoq 0
Jun Jul Aug Sep Oct Nov Dec Jan eb
2015 2016
26-Nov-15, Plum
31-Dec-
08-Dec-15, S
31-Dec-
31-Dec-
17-Nov-15, Power
12-Nov-15, Power
19-Oct-15, Lighting Sys
31-Dec-
31-Dec-
31-Dec-
Majarrah Business Complex Classic Schedule Layout 22-Jun-15 14:36
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 31 of 39 TASK filter: All Activities
© Primavera Systems, Inc.
Final Majarrah rev 0
Final Majarrah rev 0
Final Majarrah rev 0
Final Majarrah rev 0
Final Majarrah rev 0
Final Majarrah rev 0
Final Majarrah rev 0
Final Majarrah rev 0

More Related Content

Viewers also liked

Presentation plumbing
Presentation plumbingPresentation plumbing
Presentation plumbingLiguidliguid
 
IS 4985 : 2000
IS 4985 : 2000IS 4985 : 2000
IS 4985 : 2000Jisha John
 
Construction Photo Essay Project
Construction Photo Essay ProjectConstruction Photo Essay Project
Construction Photo Essay ProjectTimothy Shih
 
J press Stainless Steel piping
J press Stainless Steel pipingJ press Stainless Steel piping
J press Stainless Steel pipingPravin Goel
 
World of bathrooms 2010 - Villeroy & Boch | Hùng Hiền Luxury Co., Ltd
World of bathrooms 2010 - Villeroy & Boch | Hùng Hiền Luxury Co., LtdWorld of bathrooms 2010 - Villeroy & Boch | Hùng Hiền Luxury Co., Ltd
World of bathrooms 2010 - Villeroy & Boch | Hùng Hiền Luxury Co., LtdHùng Hiền Luxury
 
Vacuum Plumbing Systems - Future Frontiers for Plumbing Design
Vacuum Plumbing Systems - Future Frontiers for Plumbing DesignVacuum Plumbing Systems - Future Frontiers for Plumbing Design
Vacuum Plumbing Systems - Future Frontiers for Plumbing DesignMorris Group International
 
ASPE CEU Pipe Hangers and Supports
ASPE CEU Pipe Hangers and SupportsASPE CEU Pipe Hangers and Supports
ASPE CEU Pipe Hangers and SupportsJim LeStage
 
In-Place Pipe Support Load Testing and Hanger Surveys_Part of a Best in Class...
In-Place Pipe Support Load Testing and Hanger Surveys_Part of a Best in Class...In-Place Pipe Support Load Testing and Hanger Surveys_Part of a Best in Class...
In-Place Pipe Support Load Testing and Hanger Surveys_Part of a Best in Class...Britt Bettell
 
Hydrant flushing programs
Hydrant flushing programsHydrant flushing programs
Hydrant flushing programsBrian Gongol
 
2 louis p. pollono - 4046169- pipe support for use in a nuclear system
2   louis p. pollono - 4046169-  pipe support for use in a nuclear system2   louis p. pollono - 4046169-  pipe support for use in a nuclear system
2 louis p. pollono - 4046169- pipe support for use in a nuclear systemMello_Patent_Registry
 

Viewers also liked (11)

Presentation plumbing
Presentation plumbingPresentation plumbing
Presentation plumbing
 
IS 4985 : 2000
IS 4985 : 2000IS 4985 : 2000
IS 4985 : 2000
 
Construction Photo Essay Project
Construction Photo Essay ProjectConstruction Photo Essay Project
Construction Photo Essay Project
 
J press Stainless Steel piping
J press Stainless Steel pipingJ press Stainless Steel piping
J press Stainless Steel piping
 
World of bathrooms 2010 - Villeroy & Boch | Hùng Hiền Luxury Co., Ltd
World of bathrooms 2010 - Villeroy & Boch | Hùng Hiền Luxury Co., LtdWorld of bathrooms 2010 - Villeroy & Boch | Hùng Hiền Luxury Co., Ltd
World of bathrooms 2010 - Villeroy & Boch | Hùng Hiền Luxury Co., Ltd
 
Vacuum Plumbing Systems - Future Frontiers for Plumbing Design
Vacuum Plumbing Systems - Future Frontiers for Plumbing DesignVacuum Plumbing Systems - Future Frontiers for Plumbing Design
Vacuum Plumbing Systems - Future Frontiers for Plumbing Design
 
ASPE CEU Pipe Hangers and Supports
ASPE CEU Pipe Hangers and SupportsASPE CEU Pipe Hangers and Supports
ASPE CEU Pipe Hangers and Supports
 
In-Place Pipe Support Load Testing and Hanger Surveys_Part of a Best in Class...
In-Place Pipe Support Load Testing and Hanger Surveys_Part of a Best in Class...In-Place Pipe Support Load Testing and Hanger Surveys_Part of a Best in Class...
In-Place Pipe Support Load Testing and Hanger Surveys_Part of a Best in Class...
 
Hydrant flushing programs
Hydrant flushing programsHydrant flushing programs
Hydrant flushing programs
 
2 louis p. pollono - 4046169- pipe support for use in a nuclear system
2   louis p. pollono - 4046169-  pipe support for use in a nuclear system2   louis p. pollono - 4046169-  pipe support for use in a nuclear system
2 louis p. pollono - 4046169- pipe support for use in a nuclear system
 
Vietnam Auto Expo 2016
Vietnam Auto Expo 2016Vietnam Auto Expo 2016
Vietnam Auto Expo 2016
 

Similar to Final Majarrah rev 0

Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdfZewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdfAhmed Mehrem
 
12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...
12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...
12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...Rodger McKinley
 
CICPA Updated Schedule Dtd 130816
CICPA Updated Schedule Dtd 130816CICPA Updated Schedule Dtd 130816
CICPA Updated Schedule Dtd 130816Manish Shah
 
Nbourdier-lab2-gantt chart with activities-
Nbourdier-lab2-gantt chart with activities-Nbourdier-lab2-gantt chart with activities-
Nbourdier-lab2-gantt chart with activities-Nixzalis Bourdier
 
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule finalSeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule finalAhmed Mehrem
 
HSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activityHSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activityRoumik Mukherjee
 
II B.TECH I SEM R07 SUPPLE APRIL/MAY 2013
II B.TECH I SEM R07 SUPPLE APRIL/MAY 2013II B.TECH I SEM R07 SUPPLE APRIL/MAY 2013
II B.TECH I SEM R07 SUPPLE APRIL/MAY 2013P.G.GOPI NATH
 
C&ess presentation drm (30.10.13)
C&ess presentation drm (30.10.13)C&ess presentation drm (30.10.13)
C&ess presentation drm (30.10.13)Baig Ali
 
ADIB Time Schedule V4.0
ADIB Time Schedule V4.0ADIB Time Schedule V4.0
ADIB Time Schedule V4.0Ahmed Khaled
 
B tech ii yr i sem r9 supplementary may 2013 examinations results
B tech ii yr i sem r9 supplementary may 2013 examinations resultsB tech ii yr i sem r9 supplementary may 2013 examinations results
B tech ii yr i sem r9 supplementary may 2013 examinations resultsVARIGONDA GOPI
 
III B.TECH. I SEM R09 SUPPLE MAY 2013
III B.TECH. I SEM R09 SUPPLE MAY 2013III B.TECH. I SEM R09 SUPPLE MAY 2013
III B.TECH. I SEM R09 SUPPLE MAY 2013P.G.GOPI NATH
 
Epc for module mm1 mm2 baseline schedule level 3
Epc for module mm1  mm2  baseline schedule level 3Epc for module mm1  mm2  baseline schedule level 3
Epc for module mm1 mm2 baseline schedule level 3robotbietcuoi
 
3 u b tech ii year i (r09) semester supplementary examinations november 2011 ...
3 u b tech ii year i (r09) semester supplementary examinations november 2011 ...3 u b tech ii year i (r09) semester supplementary examinations november 2011 ...
3 u b tech ii year i (r09) semester supplementary examinations november 2011 ...Karthik Kumar
 

Similar to Final Majarrah rev 0 (20)

Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdfZewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdf
 
01. P269 - Project Implementation Programme - Rev 00
01. P269 - Project Implementation Programme -  Rev 0001. P269 - Project Implementation Programme -  Rev 00
01. P269 - Project Implementation Programme - Rev 00
 
2 l 65z
2 l 65z2 l 65z
2 l 65z
 
Weekly report no 19
Weekly report no 19Weekly report no 19
Weekly report no 19
 
12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...
12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...
12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...
 
10. Overall Implementation Programme
10. Overall Implementation Programme10. Overall Implementation Programme
10. Overall Implementation Programme
 
CICPA Updated Schedule Dtd 130816
CICPA Updated Schedule Dtd 130816CICPA Updated Schedule Dtd 130816
CICPA Updated Schedule Dtd 130816
 
ARB JANADREA 25.01.16 UPDATE PM
ARB JANADREA 25.01.16 UPDATE  PMARB JANADREA 25.01.16 UPDATE  PM
ARB JANADREA 25.01.16 UPDATE PM
 
Nbourdier-lab2-gantt chart with activities-
Nbourdier-lab2-gantt chart with activities-Nbourdier-lab2-gantt chart with activities-
Nbourdier-lab2-gantt chart with activities-
 
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule finalSeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
 
HSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activityHSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activity
 
II B.TECH I SEM R07 SUPPLE APRIL/MAY 2013
II B.TECH I SEM R07 SUPPLE APRIL/MAY 2013II B.TECH I SEM R07 SUPPLE APRIL/MAY 2013
II B.TECH I SEM R07 SUPPLE APRIL/MAY 2013
 
ERUP WBS
ERUP WBSERUP WBS
ERUP WBS
 
C&ess presentation drm (30.10.13)
C&ess presentation drm (30.10.13)C&ess presentation drm (30.10.13)
C&ess presentation drm (30.10.13)
 
ADIB Time Schedule V4.0
ADIB Time Schedule V4.0ADIB Time Schedule V4.0
ADIB Time Schedule V4.0
 
B tech ii yr i sem r9 supplementary may 2013 examinations results
B tech ii yr i sem r9 supplementary may 2013 examinations resultsB tech ii yr i sem r9 supplementary may 2013 examinations results
B tech ii yr i sem r9 supplementary may 2013 examinations results
 
Monthly Progress Report No.13 - September 2011
Monthly Progress Report No.13 - September 2011Monthly Progress Report No.13 - September 2011
Monthly Progress Report No.13 - September 2011
 
III B.TECH. I SEM R09 SUPPLE MAY 2013
III B.TECH. I SEM R09 SUPPLE MAY 2013III B.TECH. I SEM R09 SUPPLE MAY 2013
III B.TECH. I SEM R09 SUPPLE MAY 2013
 
Epc for module mm1 mm2 baseline schedule level 3
Epc for module mm1  mm2  baseline schedule level 3Epc for module mm1  mm2  baseline schedule level 3
Epc for module mm1 mm2 baseline schedule level 3
 
3 u b tech ii year i (r09) semester supplementary examinations november 2011 ...
3 u b tech ii year i (r09) semester supplementary examinations november 2011 ...3 u b tech ii year i (r09) semester supplementary examinations november 2011 ...
3 u b tech ii year i (r09) semester supplementary examinations november 2011 ...
 

More from Ahmed Mehrem

020614_letter for Ahmed Mehrem Recommendation letter.pdf
020614_letter for Ahmed Mehrem Recommendation letter.pdf020614_letter for Ahmed Mehrem Recommendation letter.pdf
020614_letter for Ahmed Mehrem Recommendation letter.pdfAhmed Mehrem
 
Al aziza jotun products and services 2019 qr
Al aziza jotun products and services 2019 qrAl aziza jotun products and services 2019 qr
Al aziza jotun products and services 2019 qrAhmed Mehrem
 
Al-Aziza for paints and decoration Ahmed Mehrem business card 2
Al-Aziza for paints and decoration Ahmed Mehrem business card 2Al-Aziza for paints and decoration Ahmed Mehrem business card 2
Al-Aziza for paints and decoration Ahmed Mehrem business card 2Ahmed Mehrem
 
Al-Aziza For Paints Ahmed Mehrem business card
Al-Aziza For Paints Ahmed Mehrem business card Al-Aziza For Paints Ahmed Mehrem business card
Al-Aziza For Paints Ahmed Mehrem business card Ahmed Mehrem
 
Mtwara power plant 2007
Mtwara power plant 2007Mtwara power plant 2007
Mtwara power plant 2007Ahmed Mehrem
 
Admin Building For Sphinx Glass Factory In Sadat
Admin Building For Sphinx Glass Factory In SadatAdmin Building For Sphinx Glass Factory In Sadat
Admin Building For Sphinx Glass Factory In SadatAhmed Mehrem
 
Sphinx Glass Factory comp 1-1
Sphinx Glass Factory comp 1-1Sphinx Glass Factory comp 1-1
Sphinx Glass Factory comp 1-1Ahmed Mehrem
 

More from Ahmed Mehrem (10)

020614_letter for Ahmed Mehrem Recommendation letter.pdf
020614_letter for Ahmed Mehrem Recommendation letter.pdf020614_letter for Ahmed Mehrem Recommendation letter.pdf
020614_letter for Ahmed Mehrem Recommendation letter.pdf
 
Al aziza jotun products and services 2019 qr
Al aziza jotun products and services 2019 qrAl aziza jotun products and services 2019 qr
Al aziza jotun products and services 2019 qr
 
Al-Aziza for paints and decoration Ahmed Mehrem business card 2
Al-Aziza for paints and decoration Ahmed Mehrem business card 2Al-Aziza for paints and decoration Ahmed Mehrem business card 2
Al-Aziza for paints and decoration Ahmed Mehrem business card 2
 
Al-Aziza For Paints Ahmed Mehrem business card
Al-Aziza For Paints Ahmed Mehrem business card Al-Aziza For Paints Ahmed Mehrem business card
Al-Aziza For Paints Ahmed Mehrem business card
 
For Our Mothers
For Our MothersFor Our Mothers
For Our Mothers
 
Majarrah data
Majarrah dataMajarrah data
Majarrah data
 
001
001001
001
 
Mtwara power plant 2007
Mtwara power plant 2007Mtwara power plant 2007
Mtwara power plant 2007
 
Admin Building For Sphinx Glass Factory In Sadat
Admin Building For Sphinx Glass Factory In SadatAdmin Building For Sphinx Glass Factory In Sadat
Admin Building For Sphinx Glass Factory In Sadat
 
Sphinx Glass Factory comp 1-1
Sphinx Glass Factory comp 1-1Sphinx Glass Factory comp 1-1
Sphinx Glass Factory comp 1-1
 

Final Majarrah rev 0

  • 1. Activity ID Activity Name Original Duration Start Finish Consultant Contractor Total Float Majarrah BusinessMajarrah Business Complex 164 15-Jun-15 31-Dec-15 0 Stage IStage I 164 15-Jun-15 31-Dec-15 0 M10000000 Project Data Date 0 15-Jun-15 0 M90000000 Stage 1 Ready for Operation 0 01-Dec-15 0 M90000010 Stage I Soft Opening 0 31-Dec-15 0 Plaza LevelPlaza Level 138 15-Jun-15 30-Nov-15 1 GeneralGeneral 16 25-Jun-15 14-Jul-15 83 M10000100 Sign a Contract with Fountains and Water Fall Contractor 0 25-Jun-15 C/SCG N/A 33 M10000200 Sign a Contract with Hardscape Contractor for Plaza 0 25-Jun-15 C/TB N/A 13 M10000300 Sign a Contract with Public Address Supplier for Plaza 0 25-Jun-15 C/SCG N/A 33 M10000400 Sign a Contract with CCTV Supplier for Plaza 0 25-Jun-15 C/SCG N/A 16 M10000410 Sign a Contract with External Plaza Lighting Fixture Suppl 0 02-Jul-15 C/SCG N/A 39 M10000440 Sign a Contract with Gas Company for Gas Facility 0 14-Jul-15 Client Gas 83 DesignDesign 22 15-Jun-15 09-Jul-15 33 Architectural DesArchitectural Design 10 15-Jun-15 25-Jun-15 1 M11000100 Final Architectural Design for Plaza level 10 15-Jun-15 25-Jun-15 T.B 1 Structural DesignStructural Design 12 27-Jun-15 09-Jul-15 3 M11000200 Structural Design for Demolishing works 12 27-Jun-15 09-Jul-15 HW 3 MEP DesignMEP Design 6 27-Jun-15 02-Jul-15 39 Electrical SystemsElectrical Systems 6 27-Jun-15 02-Jul-15 39 Power SystemPower System 6 27-Jun-15 02-Jul-15 37 M11000300 Power System Update for Plaza Level 6 27-Jun-15 02-Jul-15 SCG 37 Lighting SystemLighting System 6 27-Jun-15 02-Jul-15 39 M11000400 Lighting System for External Lighting By LCD 6 27-Jun-15 02-Jul-15 LCD 39 Public Address SysPublic Address System 6 27-Jun-15 02-Jul-15 39 M11000500 Public Address System Update for Plaza Level 6 27-Jun-15 02-Jul-15 SCG 39 CCTV SystemCCTV System 6 27-Jun-15 02-Jul-15 30 M11000600 CCTV System Update for Plaza Level 6 27-Jun-15 02-Jul-15 SCG 30 Data SystemData System 6 27-Jun-15 02-Jul-15 37 M11000700 Data System Update for Plaza Level 6 27-Jun-15 02-Jul-15 SCG 37 Mechanical SystemsMechanical Systems 6 27-Jun-15 02-Jul-15 35 Fire Fighting SysteFire Fighting System 6 27-Jun-15 02-Jul-15 35 M11000800 Fire Fighting System Update for Plaza Level 6 27-Jun-15 02-Jul-15 SCG 35 Plumbing SystemPlumbing System 6 27-Jun-15 02-Jul-15 26 Drainage SystemDrainage System 6 27-Jun-15 02-Jul-15 1 M11000900 Drainage System Update for Plaza Level 6 27-Jun-15 02-Jul-15 SCG 1 Irrigation SystemIrrigation System 6 27-Jun-15 02-Jul-15 24 Jun Jul Aug Sep Oct Nov Dec Jan eb 2015 2016 31-Dec- 31-Dec- 30-Nov-15, Pla 14-Jul-15, General 09-Jul-15, Design 25-Jun-15, Architectural Design 09-Jul-15, Structural Design 02-Jul-15, MEP Design 02-Jul-15, Electrical Systems 02-Jul-15, Power System 02-Jul-15, Lighting System 02-Jul-15, Public Address System 02-Jul-15, CCTV System 02-Jul-15, Data System 02-Jul-15, Mechanical Systems 02-Jul-15, Fire Fighting System 02-Jul-15, Plumbing System 02-Jul-15, Drainage System 02-Jul-15, Irrigation System Majarrah Business Complex Classic Schedule Layout 22-Jun-15 14:36 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 1 of 39 TASK filter: All Activities © Primavera Systems, Inc.
  • 2. Activity ID Activity Name Original Duration Start Finish Consultant Contractor Total Float M110001000 Irrigation System Layout for Plaza Level 6 27-Jun-15 02-Jul-15 SCG 24 Fountains and WateFountains and Water Fall 6 27-Jun-15 02-Jul-15 26 M110001004 Water Fall Design 6 27-Jun-15 02-Jul-15 SCG 26 M110001002 Fountains Design 6 27-Jun-15 02-Jul-15 SCG 26 Shop DrawingsShop Drawings 28 27-Jun-15 30-Jul-15 29 Architectural ShoArchitectural Shop Drawing 12 27-Jun-15 09-Jul-15 13 M110001006 Plaza Architecture Layout Shop Drawing Submittal 6 27-Jun-15 02-Jul-15 N/A 13 M110001008 Plaza Architecture Layout Shop Drawing Approval 6 04-Jul-15 09-Jul-15 T.B 13 Structural Shop DStructural Shop Drawing 16 11-Jul-15 30-Jul-15 3 M110001010 Plaza Structural Modifications Layout Submittal 10 11-Jul-15 22-Jul-15 ECIP 3 M110001012 Plaza Structural Modifications Layout Approval 6 25-Jul-15 30-Jul-15 HW 3 Electrical SystemsElectrical Systems 18 04-Jul-15 26-Jul-15 33 Power SystemPower System 12 04-Jul-15 16-Jul-15 37 M110001014 Power System for Plaza Level Submittal 6 04-Jul-15 09-Jul-15 Ofoq 37 M110001016 Power System for Plaza Level Approval 6 11-Jul-15 16-Jul-15 SCG 37 Lighting SystemLighting System 12 04-Jul-15 16-Jul-15 39 M110001018 Lighting System for External Lighting Submittal 6 04-Jul-15 09-Jul-15 Ofoq 39 M110001020 Lighting System for External Lighting Approval 6 11-Jul-15 16-Jul-15 SCG 39 Public Address SysPublic Address System 12 11-Jul-15 26-Jul-15 33 M110001022 Public Address System for External Lighting Submittal 6 11-Jul-15 16-Jul-15 Ofoq 33 M110001024 Public Address System for External Lighting Approval 6 19-Jul-15 26-Jul-15 SCG 33 CCTV SystemCCTV System 12 04-Jul-15 16-Jul-15 30 M1PS1360 CCTV System for External Lighting Submittal 6 04-Jul-15 09-Jul-15 Ofoq 30 M1PS1370 CCTV System for External Lighting Approval 6 11-Jul-15 16-Jul-15 SCG 30 Data SystemData System 12 04-Jul-15 16-Jul-15 37 M110001026 Data System for Plaza Level Submittal 6 04-Jul-15 09-Jul-15 Ofoq 37 M110001028 Data System for Plaza Level Approval 6 11-Jul-15 16-Jul-15 SCG 37 Mechanical SysteMechanical Systems 21 04-Jul-15 29-Jul-15 29 Fire Fighting SystemFire Fighting System 12 04-Jul-15 16-Jul-15 35 M110001030 Fire Fighting System for Plaza Level Submittal 6 04-Jul-15 09-Jul-15 Ofoq 35 M110001032 Fire Fighting System for Plaza Level Approval 6 11-Jul-15 16-Jul-15 SCG 35 Plumbing SystemPlumbing System 21 04-Jul-15 29-Jul-15 29 Drainage SystemDrainage System 21 04-Jul-15 29-Jul-15 24 M110001034 Drainage System for Plaza Level Submittal 6 04-Jul-15 09-Jul-15 Ofoq 1 M110001036 Drainage System for Plaza Level Approval 6 11-Jul-15 16-Jul-15 SCG 1 M110001038 Builder Work and Core drill openings for Floor drains Submittal 3 19-Jul-15 21-Jul-15 Ofoq 24 M110001040 Builder Work and Core drill openings for Floor drains Appr 6 22-Jul-15 29-Jul-15 HW 24 Jun Jul Aug Sep Oct Nov Dec Jan eb 2015 2016 02-Jul-15, Fountains and Water Fall 30-Jul-15, Shop Drawings 09-Jul-15, Architectural Shop Drawing 30-Jul-15, Structural Shop Drawing 26-Jul-15, Electrical Systems 16-Jul-15, Power System 16-Jul-15, Lighting System 26-Jul-15, Public Address System 16-Jul-15, CCTV System 16-Jul-15, Data System 29-Jul-15, Mechanical Systems 16-Jul-15, Fire Fighting System 29-Jul-15, Plumbing System 29-Jul-15, Drainage System Majarrah Business Complex Classic Schedule Layout 22-Jun-15 14:36 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 2 of 39 TASK filter: All Activities © Primavera Systems, Inc.
  • 3. Activity ID Activity Name Original Duration Start Finish Consultant Contractor Total Float Irrigation SystemIrrigation System 21 04-Jul-15 29-Jul-15 24 M110001042 Irrigation System Layout for Plaza Level Submittal 15 04-Jul-15 21-Jul-15 Ofoq 24 M110001044 Irrigation System Layout for Plaza Level Approval 6 22-Jul-15 29-Jul-15 SCG 24 Fountains and WateFountains and Water Fall 18 04-Jul-15 26-Jul-15 32 M110001048 Water Fall Shop drawing Submittal 12 04-Jul-15 16-Jul-15 Ofoq 27 M110001046 Fountains Shop drawing Submittal 12 04-Jul-15 16-Jul-15 Ofoq 32 M110001052 Water Fall Shop drawing Approval 6 19-Jul-15 26-Jul-15 SCG 27 M110001050 Fountains Shop drawing Approval 6 19-Jul-15 26-Jul-15 SCG 32 MaterialsMaterials 103 15-Jun-15 20-Oct-15 34 Structural MateriaStructural Materials 36 15-Jun-15 28-Jul-15 12 Structural Material SStructural Material Submittal 6 15-Jun-15 21-Jun-15 12 M110001166 Expansion Joints Submittal 6 15-Jun-15 21-Jun-15 ECIP 12 Structural Material AStructural Material Approval 6 22-Jun-15 28-Jun-15 12 M110001176 Expansion Joints Approval 6 22-Jun-15 28-Jun-15 ECIP 12 Structural Material PStructural Material P.O 6 29-Jun-15 05-Jul-15 12 M110001186 Expansion Joints PO 6 29-Jun-15 05-Jul-15 ECIP 12 Structural Material DStructural Material Delivery 18 06-Jul-15 28-Jul-15 12 M110001196 Expansion Joints Delivery to Site 18 06-Jul-15 28-Jul-15 ECIP 12 Finishing MateriaFinishing Materials 76 11-Jul-15 13-Oct-15 37 Finishing Material SFinishing Material Submittal 26 11-Jul-15 11-Aug-15 52 M110001054 Plaza Flooring Filling (M-01&M-02&M-03) Material Submi 6 11-Jul-15 16-Jul-15 N/A 13 M110001056 Plaza Walkway Filling (M-04) Material Submittal 6 11-Jul-15 16-Jul-15 N/A 61 M110001058 Plaza Driveway Filling (M-05 & M-06) Material Submittal 6 11-Jul-15 16-Jul-15 N/A 64 M110001060 Fountain Area M-07 Material Submittal 6 11-Jul-15 16-Jul-15 N/A 54 M110001062 Plaza Borders B-01 Material Submittal 6 11-Jul-15 16-Jul-15 N/A 64 M110001064 Building Borders B-02 Material Submittal 6 11-Jul-15 16-Jul-15 N/A 64 M110001068 Drive Borders B-03 Material Submittal 6 11-Jul-15 16-Jul-15 N/A 64 M110001070 Planters Copping (C-01 & C-02 & C-03) Material Submittal 6 11-Jul-15 16-Jul-15 N/A 64 M110001072 Stairs (ST-01 &ST-02&ST-03&ST-04&ST-05) Material Subm 6 11-Jul-15 16-Jul-15 N/A 70 M110001074 Loose Gravel GR-01 Material Submittal 6 11-Jul-15 16-Jul-15 N/A 72 M110001078 Pre-Cast Concrete Curb CB-01 Material Submittal 6 11-Jul-15 16-Jul-15 N/A 65 M110001080 Soft Scape Material Submittal 26 11-Jul-15 11-Aug-15 MIAC 35 Finishing Material AFinishing Material Approval 26 19-Jul-15 18-Aug-15 52 M110001082 Plaza Flooring Filling (M-01&M-02&M-03) Material Appro 6 19-Jul-15 26-Jul-15 T.B 13 M110001084 Plaza Walkway Filling (M-04) Material Approval 6 19-Jul-15 26-Jul-15 T.B 61 M110001086 Plaza Driveway Filling (M-05 & M-06) Material Approval 6 19-Jul-15 26-Jul-15 T.B 64 M110001088 Fountain Area M-07 Material Approval 6 19-Jul-15 26-Jul-15 T.B 54 M110001090 Plaza Borders B-01 Material Approval 6 19-Jul-15 26-Jul-15 T.B 64 Jun Jul Aug Sep Oct Nov Dec Jan eb 2015 2016 29-Jul-15, Irrigation System 26-Jul-15, Fountains and Water Fall 20-Oct-15, Materials 28-Jul-15, Structural Materials 21-Jun-15, Structural Material Submittal 28-Jun-15, Structural Material Approval 05-Jul-15, Structural Material P.O 28-Jul-15, Structural Material Delivery 13-Oct-15, Finishing Mat 11-Aug-15, Finishing Material Submitta 18-Aug-15, Finishing Material Appro Majarrah Business Complex Classic Schedule Layout 22-Jun-15 14:36 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 3 of 39 TASK filter: All Activities © Primavera Systems, Inc.
  • 4. Activity ID Activity Name Original Duration Start Finish Consultant Contractor Total Float M110001092 Building Borders B-02 Material Approval 6 19-Jul-15 26-Jul-15 T.B 64 M110001094 Drive Borders B-03 Material Approval 6 19-Jul-15 26-Jul-15 T.B 64 M110001096 Planters Copping (C-01 & C-02 & C-03) Material Approval 6 19-Jul-15 26-Jul-15 T.B 64 M110001098 Stairs (ST-01 &ST-02&ST-03&ST-04&ST-05) Material Appr 6 19-Jul-15 26-Jul-15 T.B 70 M1100010100 Loose Gravel GR-01 Material Approval 6 19-Jul-15 26-Jul-15 T.B 72 M1100010102 Pre-Cast Concrete Curb CB-01 Material Approval 6 19-Jul-15 26-Jul-15 T.B 65 M1100010104 Soft Scape Material Approval 6 12-Aug-15 18-Aug-15 T.B 35 Finishing Material PFinishing Material P.O 46 27-Jul-15 17-Sep-15 35 M1100010106 Plaza Flooring Filling (M-01&M-02&M-03) Material P.O 3 27-Jul-15 29-Jul-15 N/A 13 M1100010108 Plaza Walkaway Filling (M-04) Material P.O 3 27-Jul-15 29-Jul-15 N/A 61 M11000101010 Plaza Driveway Filling (M-05 & M-06) Material P.O 3 27-Jul-15 29-Jul-15 N/A 64 M11000101012 Fountain Area M-07 Material P.O 3 27-Jul-15 29-Jul-15 N/A 54 M11000101014 Plaza Borders B-01 Material P.O 3 27-Jul-15 29-Jul-15 N/A 64 M11000101016 Building Borders B-02 Material P.O 3 27-Jul-15 29-Jul-15 N/A 64 M11000101018 Drive Borders B-03 Material P.O 3 27-Jul-15 29-Jul-15 N/A 64 M11000101020 Planters Copping (C-01 & C-02 & C-03) Material P.O 3 27-Jul-15 29-Jul-15 N/A 64 M11000101022 Stairs (ST-01 &ST-02&ST-03&ST-04&ST-05) Material P.O 3 27-Jul-15 29-Jul-15 N/A 70 M11000101024 Loose Gravel GR-01 Material P.O 3 27-Jul-15 29-Jul-15 N/A 72 M11000101026 Pre-Cast Concrete Curb CB-01 Material P.O 3 27-Jul-15 29-Jul-15 N/A 65 M11000101028 Soft Scape Material P.O 26 19-Aug-15 17-Sep-15 MIAC 35 Finishing Material DFinishing Material Delivery 61 30-Jul-15 13-Oct-15 37 M11000101030 Plaza Walkaway Filling (M-04) Material Delivery 26 30-Jul-15 29-Aug-15 N/A 61 M11000101032 Plaza Driveway Filling (M-05 & M-06) Material Delivery 26 30-Jul-15 29-Aug-15 N/A 64 M11000101034 Fountain Area M-07 Material Delivery 26 30-Jul-15 29-Aug-15 N/A 54 M11000101036 Plaza Borders B-01 Material Delivery 26 30-Jul-15 29-Aug-15 N/A 64 M11000101038 Building Borders B-02 Material Delivery 26 30-Jul-15 29-Aug-15 N/A 64 M11000101040 Drive Borders B-03 Material Delivery 26 30-Jul-15 29-Aug-15 N/A 64 M11000101042 Planters Copping (C-01 & C-02 & C-03) Material Delivery 26 30-Jul-15 29-Aug-15 N/A 64 M11000101044 Stairs (ST-01 &ST-02&ST-03&ST-04&ST-05) Material Deliv 26 30-Jul-15 29-Aug-15 N/A 70 M11000101046 Loose Gravel GR-01 Material Delivery 26 30-Jul-15 29-Aug-15 N/A 72 M11000101048 Pre-Cast Concrete Curb CB-01 Material Delivery 26 30-Jul-15 29-Aug-15 N/A 65 M11000101050 Plaza Flooring Filling (M-01&M-02&M-03) Material Deliver 52 30-Jul-15 01-Oct-15 N/A 13 M11000101052 Soft Scape Material Delivery 18 19-Sep-15 13-Oct-15 MIAC 35 MEP MaterialsMEP Materials 103 15-Jun-15 20-Oct-15 34 Material SubmittalMaterial Submittal 52 15-Jun-15 16-Aug-15 55 Electrical Material SElectrical Material Submittal 52 15-Jun-15 16-Aug-15 55 M11000101054 PVC Conduit Material Submittal 3 15-Jun-15 17-Jun-15 Ofoq 50 M11000101056 Wires for Power and Lighting Material Submittal 10 19-Jul-15 30-Jul-15 Ofoq 69 M11000101058 External & Facade Lighting Fixture Material Submittal 12 19-Jul-15 02-Aug-15 N/A 46 Jun Jul Aug Sep Oct Nov Dec Jan eb 2015 2016 17-Sep-15, Finishing Material 13-Oct-15, Finishing Mat 20-Oct-15, MEP Materi 16-Aug-15, Material Submittal 16-Aug-15, Electrical Material Submit Majarrah Business Complex Classic Schedule Layout 22-Jun-15 14:36 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 4 of 39 TASK filter: All Activities © Primavera Systems, Inc.
  • 5. Activity ID Activity Name Original Duration Start Finish Consultant Contractor Total Float M11000101060 Structured Cable for Data System Material Submittal 18 19-Jul-15 09-Aug-15 Ofoq 49 M11000101062 Distribution Board DB1, DB4 Material Submittal 18 19-Jul-15 09-Aug-15 Ofoq 46 M11000101064 CCTV Cameras Material Submittal 18 19-Jul-15 09-Aug-15 N/A 30 M11000101066 Floor Box Submittal 18 27-Jul-15 16-Aug-15 Ofoq 40 M11000101068 Public Address Loud Speaker Material Submittal 18 27-Jul-15 16-Aug-15 N/A 36 Mechanical MateriaMechanical Material Submittal 12 19-Jul-15 02-Aug-15 32 M11000101070 FD,AD, PD Material Submittal 6 19-Jul-15 26-Jul-15 Ofoq 1 M11000101072 Fire Hydrant Material Submittal 6 19-Jul-15 26-Jul-15 Ofoq 38 M11000101074 Siamese Connection Material Submittal 6 19-Jul-15 26-Jul-15 Ofoq 35 M11000101076 Fountains and Water Fall Accessories Material Submittal 6 27-Jul-15 02-Aug-15 N/A 32 Material ApprovalMaterial Approval 55 18-Jun-15 23-Aug-15 55 Electrical Material AElectrical Material Approval 55 18-Jun-15 23-Aug-15 55 M11000101078 PVC Conduit Material Approval 6 18-Jun-15 24-Jun-15 SCG 50 M11000101080 Wires for Power and Lighting Material Approval 6 01-Aug-15 06-Aug-15 SCG 69 M11000101082 External & Facade Lighting Fixture Material Approval 6 03-Aug-15 09-Aug-15 SCG 46 M11000101084 Structured Cable for Data System Material Approval 6 10-Aug-15 16-Aug-15 SCG 49 M11000101086 Distribution Board DB1, DB4 Material Approval 6 10-Aug-15 16-Aug-15 SCG 46 M11000101088 CCTV Cameras Material Approval 6 10-Aug-15 16-Aug-15 SCG 30 M11000101090 Floor Box Material Approval 6 17-Aug-15 23-Aug-15 SCG 40 M11000101092 Public Address Loud Speaker Material Approval 6 17-Aug-15 23-Aug-15 SCG 36 Mechanical MateriaMechanical Material Approval 12 27-Jul-15 09-Aug-15 32 M11000101094 FD,AD, PD Material Approval 6 27-Jul-15 02-Aug-15 SCG 1 M11000101096 Fire Hydrant Material Approval 6 27-Jul-15 02-Aug-15 SCG 38 M11000101098 Siamese Connection Material Approval 6 27-Jul-15 02-Aug-15 SCG 35 M11000101100 Fountains and Water Fall Accessories Material Approval 6 03-Aug-15 09-Aug-15 SCG 32 Material P.OMaterial P.O 52 25-Jun-15 26-Aug-15 55 Electrical MaterialElectrical Material P.O 52 25-Jun-15 26-Aug-15 55 M110001010102 PVC Conduit Material P.O 3 25-Jun-15 28-Jun-15 Ofoq 50 M110001010104 Wires for Power and Lighting Material P.O 3 08-Aug-15 10-Aug-15 Ofoq 69 M110001010106 External & Facade Lighting Fixture Material P.O 3 10-Aug-15 12-Aug-15 N/A 46 M110001010108 Structured Cable for Data System Material P.O 3 17-Aug-15 19-Aug-15 Ofoq 49 M110001010110 Distribution Board DB1, DB4 Material P.O 3 17-Aug-15 19-Aug-15 Ofoq 46 M110001010112 CCTV Cameras Material P.O 3 17-Aug-15 19-Aug-15 N/A 30 M110001010114 Floor Box Material P.O 3 24-Aug-15 26-Aug-15 Ofoq 40 M110001010116 Public Address Loud Speaker Material P.O 3 24-Aug-15 26-Aug-15 N/A 36 Mechanical MateriaMechanical Material P.O 12 03-Aug-15 16-Aug-15 32 M110001010118 FD,AD, PD Material P.O 6 03-Aug-15 09-Aug-15 Ofoq 1 M110001010120 Fire Hydrant Material P.O 6 03-Aug-15 09-Aug-15 Ofoq 38 M110001010122 Siamese Connection Material P.O 6 03-Aug-15 09-Aug-15 Ofoq 35 Jun Jul Aug Sep Oct Nov Dec Jan eb 2015 2016 02-Aug-15, Mechanical Material Submitta 23-Aug-15, Material Approval 23-Aug-15, Electrical Material Appr 09-Aug-15, Mechanical Material Appr 26-Aug-15, Material P.O 26-Aug-15, Electrical Material P.O 16-Aug-15, Mechanical Material P.O Majarrah Business Complex Classic Schedule Layout 22-Jun-15 14:36 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 5 of 39 TASK filter: All Activities © Primavera Systems, Inc.
  • 6. Activity ID Activity Name Original Duration Start Finish Consultant Contractor Total Float M110001010124 Fountains and Water Accessories Fall Material P.O 6 10-Aug-15 16-Aug-15 N/A 32 Material DeliveryMaterial Delivery 91 29-Jun-15 20-Oct-15 34 Electrical MaterialElectrical Material Delivery 91 29-Jun-15 20-Oct-15 34 M110001010126 PVC Conduit Material Delivery 3 29-Jun-15 01-Jul-15 Ofoq 50 M110001010128 Wires for Power and Lighting Material Delivery 12 11-Aug-15 24-Aug-15 Ofoq 69 M110001010130 Structured Cable for Data System Material Delivery 26 20-Aug-15 19-Sep-15 Ofoq 49 M110001010132 External & Facade Lighting Fixture Material Delivery 36 13-Aug-15 27-Sep-15 N/A 46 M110001010134 Distribution Board DB1, DB4 Material Delivery 36 20-Aug-15 04-Oct-15 Ofoq 46 M110001010136 Floor Box Material Delivery 36 27-Aug-15 12-Oct-15 Ofoq 40 M110001010138 Public Address Loud Speaker Material Delivery 36 27-Aug-15 12-Oct-15 N/A 36 M110001010140 CCTV Cameras Material Delivery 48 20-Aug-15 20-Oct-15 N/A 30 Mechanical MateriaMechanical Material Delivery 52 10-Aug-15 13-Oct-15 38 M110001010144 FD,AD, PD Material Delivery 20 10-Aug-15 01-Sep-15 Ofoq 1 M110001010142 Fountains and Water Fall Accessories Material Delivery 45 17-Aug-15 12-Oct-15 N/A 32 M110001010146 Fire Hydrant Material Delivery 52 10-Aug-15 13-Oct-15 Ofoq 38 M110001010148 Siamese Connection Material Delivery 52 10-Aug-15 13-Oct-15 Ofoq 35 ConstructionConstruction 112 15-Jul-15 30-Nov-15 1 M1P1000 Removal of Temporary offices 6 22-Aug-15 27-Aug-15 HW ECIP 3 Structural WorkStructural Work 36 15-Jul-15 27-Aug-15 65 M110001010150 Existing Planters to be demolished 6 01-Aug-15 06-Aug-15 HW ECIP 21 M110001010350 Gas Room Ready to Receive Gas Facility 18 15-Jul-15 06-Aug-15 HW ECIP 83 M110001010152 Stair form Upper Basement to Plaza Level to be demolished 12 01-Aug-15 13-Aug-15 HW ECIP 3 M110001010154 Planters to be added above existing stair 12 01-Aug-15 13-Aug-15 HW ECIP 15 M110001010156 Slab to be removed 12 01-Aug-15 13-Aug-15 HW ECIP 3 M110001010158 New Planters to be added 12 01-Aug-15 13-Aug-15 HW ECIP 12 M110001010160 Existing Slab to be opened 3 15-Aug-15 17-Aug-15 HW ECIP 12 M110001010270 Expansion Joints 18 29-Jul-15 18-Aug-15 HW ECIP 12 M110001010162 New Slab to be added 18 01-Aug-15 20-Aug-15 HW ECIP 9 M110001010164 Two opening has been canceled and to be closed 18 01-Aug-15 20-Aug-15 HW ECIP 9 M110001010166 Concrete slab to be added instead of demolished stair 12 15-Aug-15 27-Aug-15 HW ECIP 3 M110001010168 Two New Stairs with a Ramp To Be Added 12 15-Aug-15 27-Aug-15 HW ECIP 3 MEP WorkMEP Work 87 30-Jul-15 14-Nov-15 15 Electrical WorksElectrical Works 62 29-Aug-15 14-Nov-15 15 M110001010170 PVC conduits Raceway for Electrical Power outlets 6 29-Aug-15 03-Sep-15 SCG Ofoq 3 M110001010174 PVC conduits Raceway for Data System 6 29-Aug-15 03-Sep-15 SCG Ofoq 3 M110001010172 PVC conduits Raceway for External Lighting Fixture 6 29-Aug-15 03-Sep-15 SCG Ofoq 5 M110001010176 PVC conduits Raceway for Public Address System (Sound System) 6 29-Aug-15 03-Sep-15 SCG Ofoq 5 Jun Jul Aug Sep Oct Nov Dec Jan eb 2015 2016 20-Oct-15, Material De 20-Oct-15, Electrical Ma 13-Oct-15, Mechanical M 30-Nov-15, Co 27-Aug-15, Structural Work 14-Nov-15, MEP W 14-Nov-15, Electri Majarrah Business Complex Classic Schedule Layout 22-Jun-15 14:36 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 6 of 39 TASK filter: All Activities © Primavera Systems, Inc.
  • 7. Activity ID Activity Name Original Duration Start Finish Consultant Contractor Total Float M110001010178 PVC conduits Raceway for CCTV System 6 29-Aug-15 03-Sep-15 SCG Ofoq 5 M110001010180 Back Box for Floor Box 2 05-Sep-15 06-Sep-15 SCG Ofoq 3 M110001010182 Wires for External Lighting Fixture 3 05-Sep-15 07-Sep-15 SCG Ofoq 60 M110001010184 Wires for Electrical Power outlets 3 07-Sep-15 09-Sep-15 SCG Ofoq 64 M110001010186 Structured Cable for Data System 3 20-Sep-15 26-Sep-15 SCG Ofoq 49 M110001010192 Facade Lighting Fixtures Erection 6 29-Sep-15 05-Oct-15 SCG Ofoq 47 M110001010188 Floor Box erection 2 05-Nov-15 07-Nov-15 SCG Ofoq 21 M110001010190 External Lighting Fixture Erection 6 05-Nov-15 11-Nov-15 SCG Ofoq 15 M110001010194 Public Address (Sound System) Erection 6 05-Nov-15 11-Nov-15 SCG Ofoq 17 M110001010196 CCTV Erection 6 05-Nov-15 11-Nov-15 SCG Ofoq 17 M110001010198 Distribution Board DB1, DB4 Erection 2 12-Nov-15 14-Nov-15 SCG Ofoq 15 Mechanical WorksMechanical Works 86 30-Jul-15 12-Nov-15 16 M110001010200 Builder Work And Core Drill for Drainage 6 30-Jul-15 05-Aug-15 SCG Ofoq 24 M110001010260 Gas Facility Network 12 08-Aug-15 20-Aug-15 SCG Gas 83 M110001010202 Floor Drains first fix 6 02-Sep-15 08-Sep-15 SCG Ofoq 1 M110001010204 Floor Drains second fix 3 04-Oct-15 07-Oct-15 SCG Ofoq 44 M110001010208 Fire Hydrant 3 19-Oct-15 21-Oct-15 SCG Ofoq 35 M110001010210 Siamese Connection 6 15-Oct-15 21-Oct-15 SCG Ofoq 35 M110001010206 Floor Drains final fix 2 05-Nov-15 07-Nov-15 SCG Ofoq 21 M110001010212 Irrigation for Main Road Island landscape 2 11-Nov-15 12-Nov-15 SCG Ofoq 12 Finishing WorkFinishing Work 76 29-Aug-15 30-Nov-15 1 M110001010214 Boundary wall (Travco Side) 18 29-Aug-15 17-Sep-15 HW ECIP 59 M110001010216 Temporary Fence 10 05-Nov-15 16-Nov-15 T.B N/A 13 Hard scapeHard scape 66 09-Sep-15 30-Nov-15 1 M110001010218 Insulation work for Plaza 18 09-Sep-15 03-Oct-15 HW ECIP 1 M110001010300 Remove Facade Cladding for Facade Lighting Fixture Erec 7 28-Sep-15 05-Oct-15 T.B Kemet 47 M110001010224 Walkways Filling Interlock 12 03-Oct-15 18-Oct-15 T.B N/A 35 M110001010232 Driveway Filling Interlock & Bazalt Tiles 12 03-Oct-15 18-Oct-15 T.B N/A 38 M110001010234 Driveway Boarders Bazalt tiles 12 03-Oct-15 18-Oct-15 T.B N/A 38 M110001010220 Screed over Insulation 12 04-Oct-15 19-Oct-15 HW ECIP 1 M110001010222 Flooring Filling Engineered Stone / Porcelain / Granite 15 19-Oct-15 04-Nov-15 T.B N/A 1 M110001010238 Main Road Island hardscape 5 05-Nov-15 10-Nov-15 T.B N/A 12 M110001010240 Planter Copping 6 05-Nov-15 11-Nov-15 T.B N/A 11 M110001010242 Stairs Covering 6 05-Nov-15 11-Nov-15 T.B N/A 17 M110001010228 Building Boarders Granite 12 05-Nov-15 18-Nov-15 T.B N/A 11 M110001010230 Plaza Boarders Granite 12 05-Nov-15 18-Nov-15 T.B N/A 11 M110001010226 Granite for Fountains 12 05-Nov-15 18-Nov-15 T.B N/A 1 M110001010236 Fountains and Water Fall Accessories Erection 10 19-Nov-15 30-Nov-15 T.B N/A 1 Soft scapeSoft scape 6 12-Nov-15 18-Nov-15 11 Jun Jul Aug Sep Oct Nov Dec Jan eb 2015 2016 12-Nov-15, Mecha 30-Nov-15, Fin 30-Nov-15, Ha 18-Nov-15, Soft s Majarrah Business Complex Classic Schedule Layout 22-Jun-15 14:36 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 7 of 39 TASK filter: All Activities © Primavera Systems, Inc.
  • 8. Activity ID Activity Name Original Duration Start Finish Consultant Contractor Total Float M110001010246 Main Road Island softscape 4 14-Nov-15 17-Nov-15 T.B MIAC 12 M110001010244 Plaza softscape 6 12-Nov-15 18-Nov-15 T.B MIAC 11 Upper BasementUpper Basement 164 15-Jun-15 31-Dec-15 0 GeneralGeneral 0 07-Jul-15 07-Jul-15 15 M1P2760 Client Clear Vision about Security Issues as (CCTV, Access Control...) 0 07-Jul-15 Client 6 M1P2770 Client Clear Vision about Data Issues as (Central, IT requirements...) 0 07-Jul-15 Client 15 DesignDesign 78 15-Jun-15 15-Sep-15 17 Architectural DesArchitectural Design 24 15-Jun-15 12-Jul-15 0 M1P1020 Final Architectural Dimensional Plan for Upper Basement 6 15-Jun-15 21-Jun-15 T.B 0 M1P1010 Final Parking Layout for Upper Basement 0 28-Jun-15 Client 0 M1P1030 Final Architectural Package for Upper Basement 12 29-Jun-15 12-Jul-15 HW 0 Structural DesignStructural Design 6 09-Sep-15 15-Sep-15 17 M1P2750 Structural Design for Equipment Foundation (Child Pump , Supply and Exhaust Fans........) 6 09-Sep-15 15-Sep-15 HW 17 MEP DesignMEP Design 30 22-Jun-15 28-Jul-15 6 Electrical SystemsElectrical Systems 24 29-Jun-15 28-Jul-15 6 Power SystemPower System 6 29-Jun-15 05-Jul-15 4 M1P1060 Updated Design for Power System 6 29-Jun-15 05-Jul-15 SCG 4 Lighting SystemLighting System 6 29-Jun-15 05-Jul-15 4 M1P1070 Updated Design for Lighting System 6 29-Jun-15 05-Jul-15 SCG 4 Fire Alarm SystemFire Alarm System 6 13-Jul-15 20-Jul-15 0 M1P1680 Updated Design for Fire Alarm System 6 13-Jul-15 20-Jul-15 C/SCG 0 Parking SystemParking System 18 29-Jun-15 20-Jul-15 0 M1P1450 Updated Design for Parking System 18 29-Jun-15 20-Jul-15 C/SCG 0 CCTV SystemCCTV System 6 13-Jul-15 20-Jul-15 2 M1P1040 Updated Design for CCTV System 6 13-Jul-15 20-Jul-15 C/SCG 2 Data SystemData System 6 13-Jul-15 20-Jul-15 11 M1P1050 Updated Design for Data System 6 13-Jul-15 20-Jul-15 C/SCG 11 BMS SystemBMS System 6 21-Jul-15 28-Jul-15 6 M1P2000 Updated Design for BMS System 6 21-Jul-15 28-Jul-15 SCG 6 Mechanical SystemsMechanical Systems 24 22-Jun-15 20-Jul-15 12 HVAC SystemHVAC System 6 13-Jul-15 20-Jul-15 0 M1P1080 HVAC Updated Design for Upper Basement 6 13-Jul-15 20-Jul-15 SCG 0 Fire Fighting SysteFire Fighting System 6 22-Jun-15 28-Jun-15 19 M1P1130 Fire Fighting Updated Design for Upper Basement 6 22-Jun-15 28-Jun-15 SCG 19 Plumbing SystemPlumbing System 6 27-Jun-15 02-Jul-15 26 Jun Jul Aug Sep Oct Nov Dec Jan eb 2015 2016 31-Dec- 07-Jul-15, General 15-Sep-15, Design 12-Jul-15, Architectural Design 15-Sep-15, Structural Design 28-Jul-15, MEP Design 28-Jul-15, Electrical Systems 05-Jul-15, Power System 05-Jul-15, Lighting System 20-Jul-15, Fire Alarm System 20-Jul-15, Parking System 20-Jul-15, CCTV System 20-Jul-15, Data System 28-Jul-15, BMS System 20-Jul-15, Mechanical Systems 20-Jul-15, HVAC System 28-Jun-15, Fire Fighting System 02-Jul-15, Plumbing System Majarrah Business Complex Classic Schedule Layout 22-Jun-15 14:36 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 8 of 39 TASK filter: All Activities © Primavera Systems, Inc.
  • 9. Activity ID Activity Name Original Duration Start Finish Consultant Contractor Total Float Drainage SystemDrainage System 6 27-Jun-15 02-Jul-15 20 M1P1090 Final Update for Upper Basement Drainage System 6 27-Jun-15 02-Jul-15 SCG 20 Irrigation SystemIrrigation System 6 27-Jun-15 02-Jul-15 26 M1P1100 Final Update for Plaza Irrigation System 6 27-Jun-15 02-Jul-15 SCG 26 Fountains and WateFountains and Water Fall 6 27-Jun-15 02-Jul-15 26 M1P1110 Fountains Design 6 27-Jun-15 02-Jul-15 SCG 26 M1P1120 Water Fall Design 6 27-Jun-15 02-Jul-15 SCG 26 Shop DrawingsShop Drawings 84 22-Jun-15 03-Oct-15 17 Architectural ShoArchitectural Shop Drawing 12 13-Jul-15 28-Jul-15 0 M1P1140 Upper Basement Architectural Shop Drawing Submittal 6 13-Jul-15 20-Jul-15 ECIP 0 M1P1150 Upper Basement Architectural Shop Drawing Approval 6 21-Jul-15 28-Jul-15 HW 0 Structural Shop DStructural Shop Drawing 68 11-Jul-15 03-Oct-15 17 M1P1160 Upper Basement Construction , Expansion Joints Details Shop Drawing Submittal 6 11-Jul-15 16-Jul-15 ECIP 60 M1P1170 Upper Basement Construction , Expansion Joints Details Shop Drawing Approval 6 19-Jul-15 26-Jul-15 HW 60 M1P2780 Upper Basement Equipment Foundations shop drawings Submittal 6 16-Sep-15 26-Sep-15 ECIP 17 M1P2790 Upper Basement Equipment Foundations shop drawings Approval 6 27-Sep-15 03-Oct-15 HW 17 Electrical SystemsElectrical Systems 36 06-Jul-15 18-Aug-15 0 Power SystemPower System 12 06-Jul-15 20-Jul-15 4 M1P1180 Upper Basement Power System Layout Submittal 6 06-Jul-15 12-Jul-15 Ofoq 4 M1P1190 Upper Basement Power System Layout Approval 6 13-Jul-15 20-Jul-15 SCG 4 Lighting SystemLighting System 12 06-Jul-15 20-Jul-15 4 M1P1200 Upper Basement Lighting System Layout Submittal 6 06-Jul-15 12-Jul-15 Ofoq 4 M1P1210 Upper Basement Lighting System Layout Approval 6 13-Jul-15 20-Jul-15 SCG 4 Fire Alarm SystemFire Alarm System 12 21-Jul-15 04-Aug-15 12 M1P1690 Upper Basement Fire Alarm System Layout Submittal 6 21-Jul-15 28-Jul-15 Ofoq 12 M1P1700 Upper Basement Fire Alarm System Layout Approval 6 29-Jul-15 04-Aug-15 SCG 12 Parking SystemParking System 12 21-Jul-15 04-Aug-15 0 M1P1430 Upper Basement Parking System Layout Submittal 6 21-Jul-15 28-Jul-15 Ofoq 0 M1P1440 Upper Basement Parking System Layout Approval 6 29-Jul-15 04-Aug-15 SCG 0 CCTV SystemCCTV System 12 21-Jul-15 04-Aug-15 2 M1P1220 Upper Basement CCTV System Layout Submittal 6 21-Jul-15 28-Jul-15 Ofoq 2 M1P1230 Upper Basement CCTV System Layout Approval 6 29-Jul-15 04-Aug-15 SCG 2 Data SystemData System 12 21-Jul-15 04-Aug-15 11 M1P1240 Upper Basement Data System Layout Submittal 6 21-Jul-15 28-Jul-15 Ofoq 11 M1P1250 Upper Basement Data System Layout Approval 6 29-Jul-15 04-Aug-15 SCG 11 Jun Jul Aug Sep Oct Nov Dec Jan eb 2015 2016 02-Jul-15, Drainage System 02-Jul-15, Irrigation System 02-Jul-15, Fountains and Water Fall 03-Oct-15, Shop Drawings 28-Jul-15, Architectural Shop Drawing 03-Oct-15, Structural Shop 18-Aug-15, Electrical Systems 20-Jul-15, Power System 20-Jul-15, Lighting System 04-Aug-15, Fire Alarm System 04-Aug-15, Parking System 04-Aug-15, CCTV System 04-Aug-15, Data System Majarrah Business Complex Classic Schedule Layout 22-Jun-15 14:36 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 9 of 39 TASK filter: All Activities © Primavera Systems, Inc.
  • 10. Activity ID Activity Name Original Duration Start Finish Consultant Contractor Total Float BMS SystemBMS System 12 05-Aug-15 18-Aug-15 0 M1P2010 Upper Basement BMS System Layout Submittal 6 05-Aug-15 11-Aug-15 Ofoq 0 M1P2020 Upper Basement BMS System Layout Approval 6 12-Aug-15 18-Aug-15 SCG 0 Mechanical SysteMechanical Systems 66 22-Jun-15 08-Sep-15 17 HVAC SystemHVAC System 66 22-Jun-15 08-Sep-15 17 M1P2210 HVAC Static Calculations for Child Water Pump Submittal 6 22-Jun-15 28-Jun-15 Ofoq 0 M1P2230 Fans Static Pressure Calculations Submittal 6 22-Jun-15 28-Jun-15 Ofoq 28 M1P2220 HVAC Static Calculations for Child Water Pump Approval 6 29-Jun-15 05-Jul-15 SCG 0 M1P2240 Fans Static Pressure Calculations Approval 6 29-Jun-15 05-Jul-15 SCG 28 M1P3560 Builder Work for Shaft Opening Layout Submittal 3 06-Jul-15 08-Jul-15 Ofoq 28 M1P3570 Builder Work for Shaft Opening Layout Approval 6 09-Jul-15 15-Jul-15 HW 28 M1P1260 Upper Basement HVAC System Layout Submittal 6 21-Jul-15 28-Jul-15 Ofoq 0 M1P1270 Upper Basement HVAC System Layout Approval 6 29-Jul-15 04-Aug-15 SCG 0 M1P2730 Upper Basement Fan Room Details Submittal 6 29-Jul-15 04-Aug-15 Ofoq 41 M1P2740 Upper Basement Fan Room Details Approval 6 05-Aug-15 11-Aug-15 SCG 41 M1P2190 Upper Basement Plant Room Details Submittal 6 26-Aug-15 01-Sep-15 Ofoq 17 M1P2200 Upper Basement Plant Room Details Approval 6 02-Sep-15 08-Sep-15 SCG 17 Fire Fighting SystemFire Fighting System 12 29-Jun-15 12-Jul-15 19 M1P1280 Upper Basement Fire Fighting System Layout Submittal 6 29-Jun-15 05-Jul-15 Ofoq 19 M1P1290 Upper Basement Fire Fighting System Layout Approval 6 06-Jul-15 12-Jul-15 SCG 19 Plumbing SystemPlumbing System 12 04-Jul-15 16-Jul-15 26 Drainage SystemDrainage System 12 04-Jul-15 16-Jul-15 26 M1P1300 Upper Basement Drainage System Layout Submittal 6 04-Jul-15 09-Jul-15 Ofoq 26 M1P1310 Upper Basement Drainage System Layout Approval 6 11-Jul-15 16-Jul-15 SCG 26 Irrigation SystemIrrigation System 12 04-Jul-15 16-Jul-15 26 M1P1320 Upper Basement Irrigation System for Plaza Layout Submit 6 04-Jul-15 09-Jul-15 Ofoq 26 M1P1330 Upper Basement Irrigation System for Plaza Layout Appro 6 11-Jul-15 16-Jul-15 SCG 26 Fountains and WateFountains and Water Fall 12 04-Jul-15 16-Jul-15 26 M1P1340 Upper Basement Fountains and Water Fall System Layout Submittal 6 04-Jul-15 09-Jul-15 Ofoq 26 M1P1350 Upper Basement Fountains and Water Fall System Layout Approval 6 11-Jul-15 16-Jul-15 SCG 26 Composite DrawiComposite Drawing 12 19-Aug-15 01-Sep-15 0 M1P1360 Upper Basement MEP Composite Drawing Submittal 6 19-Aug-15 25-Aug-15 Ofoq 0 M1P1370 Upper Basement MEP Composite Drawing Approval 6 26-Aug-15 01-Sep-15 SCG 0 MaterialsMaterials 146 15-Jun-15 09-Dec-15 6 Finishing MateriaFinishing Materials 35 27-Jul-15 05-Sep-15 58 Material SubmittalMaterial Submittal 20 27-Jul-15 18-Aug-15 58 Jun Jul Aug Sep Oct Nov Dec Jan eb 2015 2016 18-Aug-15, BMS System 08-Sep-15, Mechanical Systems 08-Sep-15, HVAC System 12-Jul-15, Fire Fighting System 16-Jul-15, Plumbing System 16-Jul-15, Drainage System 16-Jul-15, Irrigation System 16-Jul-15, Fountains and Water Fall 01-Sep-15, Composite Drawing 09-Dec-15, M 05-Sep-15, Finishing Materials 18-Aug-15, Material Submittal Majarrah Business Complex Classic Schedule Layout 22-Jun-15 14:36 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 10 of 39 TASK filter: All Activities © Primavera Systems, Inc.
  • 11. Activity ID Activity Name Original Duration Start Finish Consultant Contractor Total Float M110001206 Expansion Joints Submittal 6 27-Jul-15 02-Aug-15 ECIP 60 M1P1380 False Ceiling Material Submittal 18 29-Jul-15 18-Aug-15 ECIP 17 M1P1390 Flooring Tiles Material Submittal 18 29-Jul-15 18-Aug-15 ECIP 41 M1P1400 Paint Material Submittal 18 29-Jul-15 18-Aug-15 ECIP 29 M1P1410 Curb Stone Material Submittal 18 29-Jul-15 18-Aug-15 ECIP 46 M1P1420 Interlock Material Submittal 18 29-Jul-15 18-Aug-15 ECIP 58 M1P3920 Doors Submittal 18 29-Jul-15 18-Aug-15 ECIP 58 M1P3930 Raised Floor Submittal (Expected in IT & Main IT Room) 18 29-Jul-15 18-Aug-15 ECIP 47 Material ApprovalMaterial Approval 20 03-Aug-15 25-Aug-15 58 M110001216 Expansion Joints Approval 6 03-Aug-15 09-Aug-15 HW 60 M1P1460 False Ceiling Material Approval 6 19-Aug-15 25-Aug-15 HW 17 M1P1470 Flooring Tiles Material Approval 6 19-Aug-15 25-Aug-15 HW 41 M1P1480 Paint Material Approval 6 19-Aug-15 25-Aug-15 HW 29 M1P1490 Curb Stone Material Approval 6 19-Aug-15 25-Aug-15 HW 46 M1P1500 Interlock Material Approval 6 19-Aug-15 25-Aug-15 HW 58 M1P3940 Doors Approval 6 19-Aug-15 25-Aug-15 HW 58 M1P3950 Raised Floor Approval (Expected in IT & Main IT Room) 6 19-Aug-15 25-Aug-15 HW 47 Material P.OMaterial P.O 17 10-Aug-15 29-Aug-15 58 M110001226 Expansion Joints P.O 3 10-Aug-15 12-Aug-15 ECIP 60 M1P1510 False Ceiling Material P.O 3 26-Aug-15 29-Aug-15 ECIP 17 M1P1520 Flooring Tiles Material P.O 3 26-Aug-15 29-Aug-15 ECIP 41 M1P1530 Paint Material P.O 3 26-Aug-15 29-Aug-15 ECIP 29 M1P1540 Curb Stone Material P.O 3 26-Aug-15 29-Aug-15 ECIP 46 M1P1550 Interlock Material P.O 3 26-Aug-15 29-Aug-15 ECIP 58 M1P3960 Doors P.O 3 26-Aug-15 29-Aug-15 ECIP 58 M1P3970 Raised Floor P.O (Expected in IT & Main IT Room) 3 26-Aug-15 29-Aug-15 ECIP 47 Material DeliveryMaterial Delivery 20 13-Aug-15 05-Sep-15 58 M110001236 Expansion Joints Delivery 6 13-Aug-15 19-Aug-15 ECIP 60 M1P1560 False Ceiling Material Delivery 6 30-Aug-15 05-Sep-15 ECIP 17 M1P1570 Flooring Tiles Material Delivery 6 30-Aug-15 05-Sep-15 ECIP 41 M1P1580 Paint Material Delivery 6 30-Aug-15 05-Sep-15 ECIP 29 M1P1590 Curb Stone Material Delivery 6 30-Aug-15 05-Sep-15 ECIP 46 M1P1600 Interlock Material Delivery 6 30-Aug-15 05-Sep-15 ECIP 58 M1P3980 Doors Delivery 6 30-Aug-15 05-Sep-15 ECIP 58 M1P3990 Raised Floor Delivery (Expected in IT & Main IT Room) 6 30-Aug-15 05-Sep-15 ECIP 47 MEP MaterialsMEP Materials 146 15-Jun-15 09-Dec-15 6 Material SubmittalMaterial Submittal 72 15-Jun-15 08-Sep-15 46 Electrical Material SElectrical Material Submittal 72 15-Jun-15 08-Sep-15 20 M10 PVC , EMT Conduit with Accessories Material Submittal 3 15-Jun-15 17-Jun-15 Ofoq 48 Jun Jul Aug Sep Oct Nov Dec Jan eb 2015 2016 25-Aug-15, Material Approval 29-Aug-15, Material P.O 05-Sep-15, Material Delivery 09-Dec-15, M 08-Sep-15, Material Submittal 08-Sep-15, Electrical Material Su Majarrah Business Complex Classic Schedule Layout 22-Jun-15 14:36 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 11 of 39 TASK filter: All Activities © Primavera Systems, Inc.
  • 12. Activity ID Activity Name Original Duration Start Finish Consultant Contractor Total Float M100 Cable Trays Submittal 6 15-Jun-15 21-Jun-15 Ofoq 86 M20 Wires for Power and Lighting Material Submittal 6 21-Jul-15 28-Jul-15 Ofoq 52 M30 Lighting Fixture Material Submittal 12 21-Jul-15 04-Aug-15 Ofoq 40 M90 Wiring Devices Submittal 12 21-Jul-15 04-Aug-15 Ofoq 15 M110 Fire Alarm Material Submittal 12 21-Jul-15 04-Aug-15 Ofoq 0 M40 Structured Cable for Data System Material Submittal 4 05-Aug-15 09-Aug-15 Ofoq 11 M50 Distribution Board Material Submittal 16 21-Jul-15 09-Aug-15 Ofoq 4 M60 CCTV Cameras Material Submittal 4 05-Aug-15 09-Aug-15 N/A 2 M80 Parking System Material Submittal 18 05-Aug-15 25-Aug-15 N/A 0 M420 LV Cables Submittal 6 02-Sep-15 08-Sep-15 Ofoq 12 M450 BMS Submittal 18 19-Aug-15 08-Sep-15 Ofoq 1 Electrical EquipmentElectrical Equipment 54 15-Jun-15 18-Aug-15 10 M1P1620 R.M.U Submittal 18 15-Jun-15 05-Jul-15 Ofoq 34 M1P1630 MVSG Submittal 18 15-Jun-15 05-Jul-15 Ofoq 34 M1P1710 UPS Submittal 26 15-Jun-15 14-Jul-15 Ofoq 12 M1P1610 Generator Submittal 18 29-Jun-15 20-Jul-15 Ofoq 2 M1P1640 Transformer Submittal 18 29-Jun-15 20-Jul-15 Ofoq 22 M1P1650 MDB Submittal 18 21-Jul-15 11-Aug-15 Ofoq 4 M1P1660 EMDB Submittal 18 21-Jul-15 11-Aug-15 Ofoq 4 M1P1720 MCC Submittal 18 21-Jul-15 11-Aug-15 Ofoq 10 M1P1670 ATS Submittal 6 12-Aug-15 18-Aug-15 Ofoq 10 Mechanical MateriaMechanical Material Submittal 72 15-Jun-15 08-Sep-15 46 HVAC System SubmHVAC System Submittal 54 15-Jun-15 18-Aug-15 58 M1P2030 Galvanized Duct Submittal 6 15-Jun-15 21-Jun-15 Ofoq 46 M1P2070 Child Water Pipes Submittal 6 15-Jun-15 21-Jun-15 Ofoq 76 M1P2080 Child Water Insulation Submittal 6 15-Jun-15 21-Jun-15 Ofoq 106 M1P2040 Volume Dampers Submittal 12 05-Aug-15 18-Aug-15 Ofoq 10 M1P2050 Fire Dampers Submittal 12 05-Aug-15 18-Aug-15 Ofoq 10 M1P2060 Fire Smoke Dampers Submittal 12 05-Aug-15 18-Aug-15 Ofoq 10 M1P2090 Supply Air Grill Submittal 12 05-Aug-15 18-Aug-15 Ofoq 46 M1P2100 Exhaust Air Grill Submittal 12 05-Aug-15 18-Aug-15 Ofoq 46 Fire Fighting SystemFire Fighting System Submittal 48 13-Jul-15 08-Sep-15 3 M1P2800 Seamless Black Steel Pipes Submittal 3 13-Jul-15 15-Jul-15 Ofoq 26 M1P2810 Fire Fighting Network Valves (O.S&Y gate valve, Check valve, Alarm Check Valve) Submittal 6 13-Jul-15 20-Jul-15 Ofoq 29 M1P2820 Sprinklers Submittal 6 13-Jul-15 20-Jul-15 Ofoq 20 M1P2850 Fire Hose Stations Submittal 6 13-Jul-15 20-Jul-15 Ofoq 28 M1P2860 Fire Hose Real Stations Submittal 6 13-Jul-15 20-Jul-15 Ofoq 28 M1P2870 Fire Extinguishers Submittal 6 13-Jul-15 20-Jul-15 Ofoq 19 Jun Jul Aug Sep Oct Nov Dec Jan eb 2015 2016 18-Aug-15, Electrical Equipment 08-Sep-15, Mechanical Material S 18-Aug-15, HVAC System Submittal 08-Sep-15, Fire Fighting System S Majarrah Business Complex Classic Schedule Layout 22-Jun-15 14:36 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 12 of 39 TASK filter: All Activities © Primavera Systems, Inc.
  • 13. Activity ID Activity Name Original Duration Start Finish Consultant Contractor Total Float M1P2830 FM200 System for (MVSG Room, RMU Room, Transformer Room, Telecom Room, Security Room,LV Room, IT&Main IT Room)Submittal 12 19-Aug-15 01-Sep-15 Ofoq 4 M1P2840 Foam Fire System for (Generator Room, Feul Tank Room) Submittal 12 26-Aug-15 08-Sep-15 Ofoq 3 Plumbing System SPlumbing System Submittal 18 19-Jul-15 09-Aug-15 72 M1P3150 PPR Domestic Water Pipes Submittal 6 19-Jul-15 26-Jul-15 Ofoq 54 M1P3170 UPVC for Drainage System Submittal 6 19-Jul-15 26-Jul-15 Ofoq 48 M1P3180 PVC for Forced Main Line Submittal 6 19-Jul-15 26-Jul-15 Ofoq 66 M1P3190 Irrigation System PVC Submittal 6 19-Jul-15 26-Jul-15 Ofoq 66 M1P3200 Valves Submittal 6 19-Jul-15 26-Jul-15 Ofoq 72 M1P3210 F.D , F.F.D , P.D , F.C.O , A.D , G.D , T.D Submittal 6 19-Jul-15 26-Jul-15 Ofoq 36 M1P3220 Hose Bibbs Submittal 6 19-Jul-15 26-Jul-15 Ofoq 84 M1P3140 HDPE Domestic Water Pipes Submittal 12 19-Jul-15 02-Aug-15 Ofoq 72 M1P3160 HDPE for Drainage , Waste , Vent, Storm Systems Submitta 12 19-Jul-15 02-Aug-15 Ofoq 72 M1P3120 Fountains Tank Submittal 18 19-Jul-15 09-Aug-15 N/A 40 M1P3130 Water Fall Tank Submittal 18 19-Jul-15 09-Aug-15 N/A 40 Mechanical EquipmMechanical Equipment Submittal 36 06-Jul-15 18-Aug-15 60 HVAC EquipmentHVAC Equipment Submittal 36 06-Jul-15 18-Aug-15 60 M1P2150 Child Water Pumps Submittal 12 06-Jul-15 20-Jul-15 Ofoq 0 M1P2160 Exhaust Fans Submittal 12 06-Jul-15 20-Jul-15 Ofoq 41 M1P2170 Supply Fans Submittal 12 06-Jul-15 20-Jul-15 Ofoq 41 M1P2110 Fuel Oil Storage Tank Submittal 12 05-Aug-15 18-Aug-15 Ofoq 2 M1P2120 AC DX Split Units Submittal 12 05-Aug-15 18-Aug-15 Ofoq 60 M1P2130 Heat Exchangers Submittal 12 05-Aug-15 18-Aug-15 Ofoq 2 M1P2140 Expansion and Compression Tanks Submittal 12 05-Aug-15 18-Aug-15 Ofoq 2 M1P2180 Fan Coil Units Submittal 12 05-Aug-15 18-Aug-15 Ofoq 17 Material ApprovalMaterial Approval 87 18-Jun-15 03-Oct-15 34 Electrical Material AElectrical Material Approval 87 18-Jun-15 03-Oct-15 8 M70 PVC , EMT Conduit with Accessories Conduit Material Approval 6 18-Jun-15 24-Jun-15 SCG 48 M120 Cable Trays Approval 6 22-Jun-15 28-Jun-15 SCG 86 M130 Wires for Power and Lighting Material Approval 6 29-Jul-15 04-Aug-15 SCG 52 M140 Lighting Fixture Material Approval 6 05-Aug-15 11-Aug-15 SCG 40 M150 Wiring Devices Approval 6 05-Aug-15 11-Aug-15 SCG 15 M160 Fire Alarm Material Approval 6 05-Aug-15 11-Aug-15 SCG 0 M170 Structured Cable for Data System Material Approval 6 10-Aug-15 16-Aug-15 SCG 11 M180 Distribution Board Material Approval 6 10-Aug-15 16-Aug-15 SCG 24 M190 CCTV Cameras Material Approval 6 10-Aug-15 16-Aug-15 SCG 2 Jun Jul Aug Sep Oct Nov Dec Jan eb 2015 2016 09-Aug-15, Plumbing System Submittal 18-Aug-15, Mechanical Equipment Su 18-Aug-15, HVAC Equipment Submi 03-Oct-15, Material Appro 03-Oct-15, Electrical Mater Majarrah Business Complex Classic Schedule Layout 22-Jun-15 14:36 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 13 of 39 TASK filter: All Activities © Primavera Systems, Inc.
  • 14. Activity ID Activity Name Original Duration Start Finish Consultant Contractor Total Float M200 Parking System Material Approval 6 26-Aug-15 01-Sep-15 SCG 0 M410 LV Cables Approval 6 09-Sep-15 15-Sep-15 SCG 12 M460 BMS Approval 18 09-Sep-15 03-Oct-15 SCG 1 Electrical EquipmentElectrical Equipment 42 06-Jul-15 25-Aug-15 10 M1P1740 R.M.U Approval 6 06-Jul-15 12-Jul-15 SCG 34 M1P1750 MVSG Approval 6 06-Jul-15 12-Jul-15 SCG 34 M1P1800 UPS Approval 6 15-Jul-15 22-Jul-15 SCG 12 M1P1730 Generator Approval 6 21-Jul-15 28-Jul-15 SCG 2 M1P1760 Transformer Approval 6 21-Jul-15 28-Jul-15 SCG 22 M1P1770 MDB Approval 6 12-Aug-15 18-Aug-15 SCG 4 M1P1780 EMDB Approval 6 12-Aug-15 18-Aug-15 SCG 4 M1P1810 MCC Approval 6 12-Aug-15 18-Aug-15 SCG 16 M1P1790 ATS Approval 6 19-Aug-15 25-Aug-15 SCG 10 Mechanical MateriaMechanical Material Approval 72 22-Jun-15 15-Sep-15 46 HVAC System ApproHVAC System Approval 54 22-Jun-15 25-Aug-15 58 M1P2250 Galvanized Duct Approval 6 22-Jun-15 28-Jun-15 SCG 46 M1P2290 Child Water Pipes Approval 6 22-Jun-15 28-Jun-15 SCG 76 M1P2300 Child Water Insulation Approval 6 22-Jun-15 28-Jun-15 SCG 106 M1P2260 Volume Dampers Approval 6 19-Aug-15 25-Aug-15 SCG 10 M1P2270 Fire Dampers Approval 6 19-Aug-15 25-Aug-15 SCG 10 M1P2280 Fire Smoke Dampers Approval 6 19-Aug-15 25-Aug-15 SCG 10 M1P2310 Supply Air Grill Approval 6 19-Aug-15 25-Aug-15 SCG 46 M1P2320 Exhaust Air Grill Approval 6 19-Aug-15 25-Aug-15 SCG 46 Fire Fighting SystemFire Fighting System Approval 51 16-Jul-15 15-Sep-15 3 M1P2880 Seamless Black Steel Pipes Approval 6 16-Jul-15 25-Jul-15 SCG 26 M1P2890 Fire Fighting Network Valves (O.S&Y gate valve, Check valve, Alarm Check Valve) Approval 6 21-Jul-15 28-Jul-15 SCG 29 M1P2900 Sprinklers Approval 6 21-Jul-15 28-Jul-15 SCG 20 M1P2910 Fire Hose Stations Approval 6 21-Jul-15 28-Jul-15 SCG 28 M1P2920 Fire Hose Real Stations Approval 6 21-Jul-15 28-Jul-15 SCG 28 M1P2930 Fire Extinguishers Approval 6 21-Jul-15 28-Jul-15 SCG 19 M1P2940 FM200 System for (MVSG Room, RMU Room, Transformer Room, Telecom Room, Security Room,LV Room, IT&Main IT Room)Approval 6 02-Sep-15 08-Sep-15 SCG 4 M1P2950 Foam Fire System for (Generator Room, Feul Tank Room) Approval 6 09-Sep-15 15-Sep-15 SCG 3 Plumbing System APlumbing System Approval 18 27-Jul-15 16-Aug-15 72 M1P3230 PPR Domestic Water Pipes Approval 6 27-Jul-15 02-Aug-15 SCG 54 M1P3240 UPVC for Drainage System Approval 6 27-Jul-15 02-Aug-15 SCG 48 Jun Jul Aug Sep Oct Nov Dec Jan eb 2015 2016 25-Aug-15, Electrical Equipment 15-Sep-15, Mechanical Materia 25-Aug-15, HVAC System Approval 15-Sep-15, Fire Fighting System 16-Aug-15, Plumbing System Approva Majarrah Business Complex Classic Schedule Layout 22-Jun-15 14:36 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 14 of 39 TASK filter: All Activities © Primavera Systems, Inc.
  • 15. Activity ID Activity Name Original Duration Start Finish Consultant Contractor Total Float M1P3250 PVC for Forced Main Line Approval 6 27-Jul-15 02-Aug-15 SCG 66 M1P3260 Irrigation System PVC Approval 6 27-Jul-15 02-Aug-15 SCG 66 M1P3270 Valves Approval 6 27-Jul-15 02-Aug-15 SCG 72 M1P3280 F.D , F.F.D , P.D , F.C.O , A.D , G.D , T.D Approval 6 27-Jul-15 02-Aug-15 SCG 36 M1P3290 Hose Bibbs Approval 6 27-Jul-15 02-Aug-15 SCG 84 M1P3300 HDPE Domestic Water Pipes Approval 6 03-Aug-15 09-Aug-15 SCG 72 M1P3310 HDPE for Drainage , Waste , Vent, Storm Systems Approval 6 03-Aug-15 09-Aug-15 SCG 72 M1P3320 Fountains Tank Approval 6 10-Aug-15 16-Aug-15 SCG 40 M1P3330 Water Fall Tank Approval 6 10-Aug-15 16-Aug-15 SCG 40 Mechanical EquipmMechanical Equipment Approval 30 21-Jul-15 25-Aug-15 60 HVAC EquipmentHVAC Equipment Approval 30 21-Jul-15 25-Aug-15 60 M1P2370 Child Water Pumps Approval 6 21-Jul-15 28-Jul-15 SCG 0 M1P2380 Exhaust Fans Approval 6 21-Jul-15 28-Jul-15 SCG 41 M1P2390 Supply Fans Approval 6 21-Jul-15 28-Jul-15 SCG 41 M1P2330 Fuel Oil Storage Tank Approval 6 19-Aug-15 25-Aug-15 SCG 2 M1P2340 AC DX Split Units Approval 6 19-Aug-15 25-Aug-15 SCG 60 M1P2350 Heat Exchangers Approval 6 19-Aug-15 25-Aug-15 SCG 2 M1P2360 Expansion and Compression Tanks Approval 6 19-Aug-15 25-Aug-15 SCG 2 M1P2400 Fan Coil Units Approval 6 19-Aug-15 25-Aug-15 SCG 17 Material P.OMaterial P.O 84 25-Jun-15 07-Oct-15 34 Electrical MaterialElectrical Material P.O 84 25-Jun-15 07-Oct-15 12 M210 PVC , EMT Conduit with Accessories Conduit Material P.O 3 25-Jun-15 28-Jun-15 Ofoq 48 M220 Cable Trays P.O 3 29-Jun-15 01-Jul-15 Ofoq 86 M230 Wires for Power and Lighting Material P.O 3 05-Aug-15 08-Aug-15 Ofoq 52 M240 Lighting Fixture Material P.O 3 12-Aug-15 15-Aug-15 Ofoq 40 M250 Wiring Devices P.O 3 12-Aug-15 15-Aug-15 Ofoq 15 M260 Fire Alarm Material P.O 3 12-Aug-15 15-Aug-15 Ofoq 0 M270 Structured Cable for Data System Material P.O 3 17-Aug-15 19-Aug-15 Ofoq 11 M280 Distribution Board Material P.O 3 17-Aug-15 19-Aug-15 Ofoq 24 M290 CCTV Cameras Material P.O 3 17-Aug-15 19-Aug-15 N/A 2 M300 Parking System Material P.O 3 02-Sep-15 05-Sep-15 N/A 0 M430 LV Cables P.O 3 16-Sep-15 19-Sep-15 Ofoq 12 M470 BMS P.O 3 04-Oct-15 07-Oct-15 Ofoq 1 Electrical EquipmentElectrical Equipment 39 13-Jul-15 29-Aug-15 42 M1P1830 R.M.U P.O 3 13-Jul-15 15-Jul-15 Ofoq 78 M1P1840 MVSG P.O 3 13-Jul-15 15-Jul-15 Ofoq 40 M1P1890 UPS P.O 3 25-Jul-15 27-Jul-15 Ofoq 12 M1P1820 Generator P.O 3 29-Jul-15 01-Aug-15 Ofoq 2 M1P1850 Transformer P.O 3 29-Jul-15 01-Aug-15 Ofoq 60 Jun Jul Aug Sep Oct Nov Dec Jan eb 2015 2016 25-Aug-15, Mechanical Equipment A 25-Aug-15, HVAC Equipment Appr 07-Oct-15, Material P.O 07-Oct-15, Electrical Mater 29-Aug-15, Electrical Equipment Majarrah Business Complex Classic Schedule Layout 22-Jun-15 14:36 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 15 of 39 TASK filter: All Activities © Primavera Systems, Inc.
  • 16. Activity ID Activity Name Original Duration Start Finish Consultant Contractor Total Float M1P1860 MDB P.O 3 19-Aug-15 22-Aug-15 Ofoq 10 M1P1870 EMDB P.O 3 19-Aug-15 22-Aug-15 Ofoq 16 M1P1900 MCC P.O 3 19-Aug-15 22-Aug-15 Ofoq 16 M1P1880 ATS P.O 3 26-Aug-15 29-Aug-15 Ofoq 10 Mechanical MateriaMechanical Material P.O 69 29-Jun-15 19-Sep-15 46 HVAC System P.OHVAC System P.O 51 29-Jun-15 29-Aug-15 58 M1P2410 Galvanized Duct P.O 3 29-Jun-15 01-Jul-15 Ofoq 46 M1P2450 Child Water Pipes P.O 3 29-Jun-15 01-Jul-15 Ofoq 76 M1P2460 Child Water Insulation P.O 3 29-Jun-15 01-Jul-15 Ofoq 106 M1P2420 Volume Dampers P.O 3 26-Aug-15 29-Aug-15 Ofoq 10 M1P2430 Fire Dampers P.O 3 26-Aug-15 29-Aug-15 Ofoq 10 M1P2440 Fire Smoke Dampers P.O 3 26-Aug-15 29-Aug-15 Ofoq 10 M1P2470 Supply Air Grill P.O 3 26-Aug-15 29-Aug-15 Ofoq 46 M1P2480 Exhaust Air Grill P.O 3 26-Aug-15 29-Aug-15 Ofoq 46 Fire Fighting SystemFire Fighting System P.O 48 26-Jul-15 19-Sep-15 3 M1P2960 Seamless Black Steel Pipes P.O 3 26-Jul-15 28-Jul-15 Ofoq 26 M1P2970 Fire Fighting Network Valves (O.S&Y gate valve, Check valve, Alarm Check Valve) P.O 3 29-Jul-15 01-Aug-15 Ofoq 29 M1P2980 Sprinklers P.O 3 29-Jul-15 01-Aug-15 Ofoq 20 M1P2990 Fire Hose Stations P.O 3 29-Jul-15 01-Aug-15 Ofoq 28 M1P3000 Fire Hose Real Stations P.O 3 29-Jul-15 01-Aug-15 Ofoq 28 M1P3010 Fire Extinguishers P.O 3 29-Jul-15 01-Aug-15 Ofoq 19 M1P3020 FM200 System for (MVSG Room, RMU Room, Transformer Room, Telecom Room, Security Room,LV Room, IT&Main IT Room)P.O 3 09-Sep-15 12-Sep-15 Ofoq 4 M1P3030 Foam Fire System for (Generator Room, Feul Tank Room) P 3 16-Sep-15 19-Sep-15 Ofoq 3 Plumbing System PPlumbing System P.O 15 03-Aug-15 19-Aug-15 72 M1P3340 PPR Domestic Water Pipes P.O 3 03-Aug-15 05-Aug-15 Ofoq 54 M1P3350 UPVC for Drainage System P.O 3 03-Aug-15 05-Aug-15 Ofoq 48 M1P3360 PVC for Forced Main Line P.O 3 03-Aug-15 05-Aug-15 Ofoq 66 M1P3370 Irrigation System PVC P.O 3 03-Aug-15 05-Aug-15 Ofoq 66 M1P3380 Valves P.O 3 03-Aug-15 05-Aug-15 Ofoq 72 M1P3390 F.D , F.F.D , P.D , F.C.O , A.D , G.D , T.D P.O 3 03-Aug-15 05-Aug-15 Ofoq 36 M1P3400 Hose Bibbs P.O 3 03-Aug-15 05-Aug-15 Ofoq 84 M1P3410 HDPE Domestic Water Pipes P.O 3 10-Aug-15 12-Aug-15 Ofoq 72 M1P3420 HDPE for Drainage , Waste , Vent, Storm Systems P.O 3 10-Aug-15 12-Aug-15 Ofoq 72 M1P3430 Fountains Tank P.O 3 17-Aug-15 19-Aug-15 N/A 40 M1P3440 Water Fall Tank P.O 3 17-Aug-15 19-Aug-15 N/A 40 Mechanical EquipmMechanical Equipment P.O 30 29-Jul-15 01-Sep-15 60 Jun Jul Aug Sep Oct Nov Dec Jan eb 2015 2016 19-Sep-15, Mechanical Materi 29-Aug-15, HVAC System P.O 19-Sep-15, Fire Fighting System 19-Aug-15, Plumbing System P.O 01-Sep-15, Mechanical Equipment Majarrah Business Complex Classic Schedule Layout 22-Jun-15 14:36 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 16 of 39 TASK filter: All Activities © Primavera Systems, Inc.
  • 17. Activity ID Activity Name Original Duration Start Finish Consultant Contractor Total Float HVAC EquipmentHVAC Equipment P.O 30 29-Jul-15 01-Sep-15 60 M1P2530 Child Water Pumps P.O 6 29-Jul-15 04-Aug-15 Ofoq 0 M1P2540 Exhaust Fans P.O 6 29-Jul-15 04-Aug-15 Ofoq 52 M1P2550 Supply Fans P.O 6 29-Jul-15 04-Aug-15 Ofoq 52 M1P2490 Fuel Oil Storage Tank P.O 6 26-Aug-15 01-Sep-15 Ofoq 2 M1P2500 AC DX Split Units P.O 6 26-Aug-15 01-Sep-15 Ofoq 60 M1P2510 Heat Exchangers P.O 6 26-Aug-15 01-Sep-15 Ofoq 2 M1P2520 Expansion and Compression Tanks P.O 6 26-Aug-15 01-Sep-15 Ofoq 2 M1P2560 Fan Coil Units P.O 6 26-Aug-15 01-Sep-15 Ofoq 17 Material DeliveryMaterial Delivery 134 29-Jun-15 09-Dec-15 6 Electrical MaterialElectrical Material Delivery 121 29-Jun-15 24-Nov-15 1 M310 PVC , EMT Conduit with Accessories Conduit Material Delivery 6 29-Jun-15 05-Jul-15 Ofoq 48 M320 Cable Trays Delivery 6 02-Jul-15 08-Jul-15 Ofoq 86 M330 Wires for Power and Lighting Material Delivery 6 09-Aug-15 15-Aug-15 Ofoq 52 M340 Lighting Fixture Material Delivery 18 16-Aug-15 05-Sep-15 N/A 40 M370 Structured Cable for Data System Material Delivery 18 20-Aug-15 09-Sep-15 Ofoq 11 M350 Wiring Devices Delivery 36 16-Aug-15 29-Sep-15 Ofoq 15 M390 CCTV Cameras Material Delivery 45 20-Aug-15 17-Oct-15 N/A 2 M360 Fire Alarm Material Delivery 52 16-Aug-15 20-Oct-15 Ofoq 0 M380 Distribution Board Material Delivery 52 20-Aug-15 25-Oct-15 Ofoq 24 M440 LV Cables Delivery 26 20-Sep-15 25-Oct-15 Ofoq 12 M400 Parking System Material Delivery 45 06-Sep-15 02-Nov-15 N/A 0 M480 BMS Delivery 40 08-Oct-15 24-Nov-15 Ofoq 1 Electrical EquipmentElectrical Equipment 90 16-Jul-15 05-Nov-15 14 M1P1920 R.M.U Delivery 26 16-Jul-15 17-Aug-15 Ofoq 78 M1P1940 Transformer Delivery 26 02-Aug-15 31-Aug-15 Ofoq 60 M1P1930 MVSG Delivery 52 16-Jul-15 16-Sep-15 Ofoq 40 M1P1950 MDB Delivery 52 23-Aug-15 27-Oct-15 Ofoq 10 M1P1960 EMDB Delivery 52 23-Aug-15 27-Oct-15 Ofoq 16 M1P1990 MCC Delivery 52 23-Aug-15 27-Oct-15 Ofoq 16 M1P1980 UPS Delivery 78 28-Jul-15 01-Nov-15 Ofoq 12 M1P1970 ATS Delivery 52 30-Aug-15 03-Nov-15 Ofoq 10 M1P1910 Generator Delivery 78 02-Aug-15 05-Nov-15 Ofoq 2 Mechanical MateriaMechanical Material Delivery 131 02-Jul-15 09-Dec-15 6 HVAC System DelivHVAC System Delivery 60 02-Jul-15 12-Sep-15 52 M1P2570 Galvanized Duct Delivery 6 02-Jul-15 08-Jul-15 Ofoq 46 M1P2610 Child Water Pipes Delivery 6 02-Jul-15 08-Jul-15 Ofoq 76 M1P2620 Child Water Insulation Delivery 6 02-Jul-15 08-Jul-15 Ofoq 106 M1P2580 Volume Dampers Delivery 12 30-Aug-15 12-Sep-15 Ofoq 10 Jun Jul Aug Sep Oct Nov Dec Jan eb 2015 2016 01-Sep-15, HVAC Equipment P.O 09-Dec-15, M 24-Nov-15, Elec 05-Nov-15, Electrica 09-Dec-15, M 12-Sep-15, HVAC System Delive Majarrah Business Complex Classic Schedule Layout 22-Jun-15 14:36 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 17 of 39 TASK filter: All Activities © Primavera Systems, Inc.
  • 18. Activity ID Activity Name Original Duration Start Finish Consultant Contractor Total Float M1P2590 Fire Dampers Delivery 12 30-Aug-15 12-Sep-15 Ofoq 10 M1P2600 Fire Smoke Dampers Delivery 12 30-Aug-15 12-Sep-15 Ofoq 10 M1P2630 Supply Air Grill Delivery 12 30-Aug-15 12-Sep-15 Ofoq 46 M1P2640 Exhaust Air Grill Delivery 12 30-Aug-15 12-Sep-15 Ofoq 46 Fire Fighting SystemFire Fighting System Delivery 85 29-Jul-15 10-Nov-15 15 M1P3040 Seamless Black Steel Pipes Delivery 6 29-Jul-15 04-Aug-15 Ofoq 26 M1P3050 Fire Fighting Network Valves (O.S&Y gate valve, Check valve, Alarm Check Valve) Delivery 18 02-Aug-15 22-Aug-15 Ofoq 29 M1P3070 Fire Hose Stations Delivery 36 02-Aug-15 12-Sep-15 Ofoq 28 M1P3080 Fire Hose Real Stations Delivery 36 02-Aug-15 12-Sep-15 Ofoq 28 M1P3060 Sprinklers Delivery 45 02-Aug-15 26-Sep-15 Ofoq 20 M1P3090 Fire Extinguishers Delivery 78 02-Aug-15 05-Nov-15 Ofoq 19 M1P3100 FM200 System for (MVSG Room, RMU Room, Transformer Room, Telecom Room, Security Room,LV Room, IT&Main IT Room)Delivery 45 13-Sep-15 09-Nov-15 Ofoq 4 M1P3110 Foam Fire System for (Generator Room, Feul Tank Room) Delivery 40 20-Sep-15 10-Nov-15 Ofoq 3 Plumbing System DPlumbing System Delivery 30 06-Aug-15 09-Sep-15 60 M1P3450 PPR Domestic Water Pipes Delivery 6 06-Aug-15 12-Aug-15 Ofoq 54 M1P3460 UPVC for Drainage System Delivery 6 06-Aug-15 12-Aug-15 Ofoq 48 M1P3470 PVC for Forced Main Line Delivery 6 06-Aug-15 12-Aug-15 Ofoq 66 M1P3480 Irrigation System PVC Delivery 6 06-Aug-15 12-Aug-15 Ofoq 66 M1P3490 Valves Delivery 6 06-Aug-15 12-Aug-15 Ofoq 72 M1P3500 F.D , F.F.D , P.D , F.C.O , A.D , G.D , T.D Delivery 6 06-Aug-15 12-Aug-15 Ofoq 36 M1P3510 Hose Bibbs Delivery 6 06-Aug-15 12-Aug-15 Ofoq 84 M1P3520 HDPE Domestic Water Pipes Delivery 12 13-Aug-15 26-Aug-15 Ofoq 72 M1P3530 HDPE for Drainage , Waste , Vent, Storm Systems Delivery 12 13-Aug-15 26-Aug-15 Ofoq 72 M1P3540 Fountains Tank Delivery 18 20-Aug-15 09-Sep-15 N/A 40 M1P3550 Water Fall Tank Delivery 18 20-Aug-15 09-Sep-15 N/A 40 Mechanical EquipmMechanical Equipment Delivery 104 05-Aug-15 09-Dec-15 6 HVAC EquipmentHVAC Equipment Delivery 104 05-Aug-15 09-Dec-15 6 M1P2660 AC DX Split Units Delivery 26 02-Sep-15 05-Oct-15 Ofoq 60 M1P2720 Fan Coil Units Delivery 26 02-Sep-15 05-Oct-15 Ofoq 17 M1P2700 Exhaust Fans Delivery 52 05-Aug-15 08-Oct-15 Ofoq 52 M1P2710 Supply Fans Delivery 52 05-Aug-15 08-Oct-15 Ofoq 52 M1P2650 Fuel Oil Storage Tank Delivery 78 02-Sep-15 07-Dec-15 Ofoq 2 M1P2670 Heat Exchangers Delivery 78 02-Sep-15 07-Dec-15 Ofoq 2 M1P2680 Expansion and Compression Tanks Delivery 78 02-Sep-15 07-Dec-15 Ofoq 2 M1P2690 Child Water Pumps Delivery 104 05-Aug-15 09-Dec-15 Ofoq 0 Jun Jul Aug Sep Oct Nov Dec Jan eb 2015 2016 10-Nov-15, Fire Fig 09-Sep-15, Plumbing System Del 09-Dec-15, M 09-Dec-15, H Majarrah Business Complex Classic Schedule Layout 22-Jun-15 14:36 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 18 of 39 TASK filter: All Activities © Primavera Systems, Inc.
  • 19. Activity ID Activity Name Original Duration Start Finish Consultant Contractor Total Float ConstructionConstruction 137 16-Jul-15 31-Dec-15 0 Structural WorkStructural Work 112 16-Jul-15 01-Dec-15 0 M1P3580 Openings for Duct Shafts 12 16-Jul-15 01-Aug-15 HW ECIP 28 M1P3590 Completion of All demolishing and remodeling in Plaza Leve 0 27-Aug-15 HW ECIP 53 M1P3600 Expansion Joints 12 29-Aug-15 10-Sep-15 HW ECIP 53 M1P3890 Equipments Concrete Foundations 12 04-Oct-15 19-Oct-15 HW ECIP 17 M1P4000 Upper Basement Screed 12 18-Nov-15 01-Dec-15 HW ECIP 0 MEP WorkMEP Work 98 02-Sep-15 31-Dec-15 0 Electrical WorksElectrical Works 98 02-Sep-15 31-Dec-15 0 Power SystemPower System 71 02-Sep-15 29-Nov-15 2 M1P3610 Upper Basement PVC Conduites for Power Outlets 12 02-Sep-15 15-Sep-15 SCG Ofoq 41 M1P3620 Upper Basement EMT Conduites for Power Outlets 12 02-Sep-15 15-Sep-15 SCG Ofoq 41 M1P3630 Upper Basement Cable Trays for LV Cables 12 02-Sep-15 15-Sep-15 SCG Ofoq 41 M1P3640 Wires for Upper Basement Power Outlets 6 16-Sep-15 26-Sep-15 SCG Ofoq 41 M1P3660 Laying Upper Basement DB Panels 2 26-Oct-15 27-Oct-15 SCG Ofoq 24 M1P3650 Laying Upper Basement LV Cables 6 26-Oct-15 01-Nov-15 SCG Ofoq 12 M1P3790 Wiring Devices Erection and termination 12 02-Nov-15 15-Nov-15 SCG Ofoq 12 M1P3670 Termination Upper Basement DB Panels 6 11-Nov-15 17-Nov-15 SCG Ofoq 12 Power EquipmentPower Equipment 35 20-Oct-15 29-Nov-15 2 M1P3700 Laying Upper Basement Transformer 2 20-Oct-15 21-Oct-15 SCG Ofoq 23 M1P3720 Laying R.M.U 2 20-Oct-15 21-Oct-15 SCG Ofoq 29 M1P3740 Laying MVSG 2 20-Oct-15 21-Oct-15 SCG Ofoq 17 M1P3730 Termination R.M.U 6 22-Oct-15 28-Oct-15 SCG Ofoq 29 M1P3680 Laying Upper Basement MCC's 2 28-Oct-15 29-Oct-15 SCG Ofoq 16 M1P3830 Laying EMDB 2 28-Oct-15 29-Oct-15 SCG Ofoq 16 M1P3900 Laying MDB 2 28-Oct-15 29-Oct-15 SCG Ofoq 10 M1P3860 Laying UPS 2 02-Nov-15 03-Nov-15 SCG Ofoq 12 M1P3710 Termination Upper Basement Transformer 12 22-Oct-15 04-Nov-15 SCG Ofoq 23 M1P3850 Laying ATS 2 04-Nov-15 05-Nov-15 SCG Ofoq 10 M1P3760 Laying Generator Package 2 07-Nov-15 08-Nov-15 SCG Ofoq 2 M1P3750 Termination MVSG 18 22-Oct-15 11-Nov-15 SCG Ofoq 17 M1P3690 Termination Upper Basement MCC's 12 31-Oct-15 12-Nov-15 SCG Ofoq 16 M1P3840 Termination EMDB 12 31-Oct-15 12-Nov-15 SCG Ofoq 16 M1P3880 Termination UPS 12 04-Nov-15 17-Nov-15 SCG Ofoq 12 M1P3870 Termination ATS 12 07-Nov-15 19-Nov-15 SCG Ofoq 10 M1P3910 Termination MDB 18 31-Oct-15 19-Nov-15 SCG Ofoq 10 M1P3770 Termination of Generator 18 09-Nov-15 29-Nov-15 SCG Ofoq 2 Lighting SystemLighting System 36 02-Sep-15 19-Oct-15 25 Jun Jul Aug Sep Oct Nov Dec Jan eb 2015 2016 31-Dec- 01-Dec-15, Str 31-Dec- 31-Dec- 29-Nov-15, Pow 29-Nov-15, Pow 19-Oct-15, Lighting Sys Majarrah Business Complex Classic Schedule Layout 22-Jun-15 14:36 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 19 of 39 TASK filter: All Activities © Primavera Systems, Inc.
  • 20. Activity ID Activity Name Original Duration Start Finish Consultant Contractor Total Float M1P3800 Upper Basement PVC Conduites for Lighting Outlets 12 02-Sep-15 15-Sep-15 SCG Ofoq 25 M1P3810 Upper Basement EMT Conduites for Lighting Outlets 12 02-Sep-15 15-Sep-15 SCG Ofoq 25 M1P3820 Wires for Upper Basement Lighting Outlets 6 16-Sep-15 26-Sep-15 SCG Ofoq 25 M1P3780 Lighting Fixture Erection and termination 18 27-Sep-15 19-Oct-15 SCG Ofoq 25 Low Current SysteLow Current Systems 98 02-Sep-15 31-Dec-15 0 Fire Alarm SystemFire Alarm System 98 02-Sep-15 31-Dec-15 0 M1P4010 EMT Conduites 18 02-Sep-15 26-Sep-15 SCG Ofoq 19 M1P4020 Fire Alarm Cable 18 21-Oct-15 10-Nov-15 SCG Ofoq 0 M1P4030 Fire Alarm Devices 18 11-Nov-15 01-Dec-15 SCG Ofoq 0 M1P4040 Testing And Precommissioning 25 02-Dec-15 31-Dec-15 SCG Ofoq 0 Data SystemData System 98 02-Sep-15 31-Dec-15 0 M1P4050 EMT Conduites 18 02-Sep-15 26-Sep-15 SCG Ofoq 0 M1P4060 Structured Data Cable 18 27-Sep-15 19-Oct-15 SCG Ofoq 0 M1P4070 Face Plates Devices 18 20-Oct-15 09-Nov-15 SCG Ofoq 0 M1P4080 Testing And Precommissioning 44 10-Nov-15 31-Dec-15 SCG Ofoq 0 CCTV SystemCCTV System 98 02-Sep-15 31-Dec-15 0 M1P4090 EMT Conduites 18 02-Sep-15 26-Sep-15 SCG Ofoq 0 M1P4100 Structured Data Cable 18 27-Sep-15 19-Oct-15 SCG Ofoq 0 M1P4110 Cameras Devices 18 20-Oct-15 09-Nov-15 SCG Ofoq 0 M1P4120 Testing And Precommissioning 44 10-Nov-15 31-Dec-15 SCG Ofoq 0 BMS SystemBMS System 97 02-Sep-15 30-Dec-15 1 M1P4130 EMT Conduites 18 02-Sep-15 26-Sep-15 SCG Ofoq 32 M1P4140 Structured Data Cable 18 27-Sep-15 19-Oct-15 SCG Ofoq 32 M1P4150 BMS System with FACP Termination 12 25-Nov-15 08-Dec-15 SCG Ofoq 1 M1P4160 Testing And Precommissioning 18 09-Dec-15 30-Dec-15 SCG Ofoq 1 Parking SystemParking System 98 02-Sep-15 31-Dec-15 0 M1P4170 EMT Conduites 18 02-Sep-15 26-Sep-15 SCG Ofoq 12 M1P4180 Structured Data Cable 18 27-Sep-15 19-Oct-15 SCG Ofoq 12 M1P4190 Parking System 20 03-Nov-15 25-Nov-15 SCG Ofoq 0 M1P4200 Testing And Precommissioning 30 26-Nov-15 31-Dec-15 SCG Ofoq 0 Mechanical WorksMechanical Works 98 02-Sep-15 31-Dec-15 0 HVAC SystemHVAC System 98 02-Sep-15 31-Dec-15 0 M1P4210 Galvanized Duct Erection 18 02-Sep-15 26-Sep-15 SCG Ofoq 1 M1P4230 Child Water Pipes Erection 18 02-Sep-15 26-Sep-15 SCG Ofoq 31 M1P4220 Volume Dampers , Fire Dampers and Fire Smoke Dampers Erection 12 27-Sep-15 11-Oct-15 SCG Ofoq 1 M1P4250 Child Water Pipes Test and Flushing 12 27-Sep-15 11-Oct-15 SCG Ofoq 31 M1P4290 Fan Coil Unit Erection 12 07-Oct-15 21-Oct-15 SCG Ofoq 17 M1P4240 Duct Smoke Test 12 12-Oct-15 26-Oct-15 SCG Ofoq 1 M1P4270 Child Water Pipes Insulation 12 12-Oct-15 26-Oct-15 SCG Ofoq 31 Jun Jul Aug Sep Oct Nov Dec Jan eb 2015 2016 31-Dec- 31-Dec- 31-Dec- 31-Dec- 30-Dec- 31-Dec- 31-Dec- 31-Dec- Majarrah Business Complex Classic Schedule Layout 22-Jun-15 14:36 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 20 of 39 TASK filter: All Activities © Primavera Systems, Inc.
  • 21. Activity ID Activity Name Original Duration Start Finish Consultant Contractor Total Float M1P4260 Duct Insulation 12 27-Oct-15 09-Nov-15 SCG Ofoq 1 M1P4280 Air Grill Supply and Exhaust 18 10-Nov-15 30-Nov-15 SCG Ofoq 1 HVAC EquipmentHVAC Equipment 72 07-Oct-15 31-Dec-15 0 M1P4300 AC DX Split Units Erection 12 07-Oct-15 21-Oct-15 SCG Ofoq 60 M1P4310 Exhaust Fans Erection 18 10-Oct-15 31-Oct-15 SCG Ofoq 52 M1P4320 Supply Fans Erection 18 10-Oct-15 31-Oct-15 SCG Ofoq 52 M1P4330 Fuel Oil Storage Tank Erection 18 08-Dec-15 29-Dec-15 SCG Ofoq 2 M1P4340 Heat Exchangers Erection 18 08-Dec-15 29-Dec-15 SCG Ofoq 2 M1P4350 Expansion and Compression Tanks Erection 18 08-Dec-15 29-Dec-15 SCG Ofoq 2 M1P4360 Child Water Pumps Erection 18 10-Dec-15 31-Dec-15 SCG Ofoq 0 Fire Fighting SysteFire Fighting System 95 02-Sep-15 28-Dec-15 3 M1P4370 Seamless Black Steel Pipes Erection 18 02-Sep-15 26-Sep-15 SCG Ofoq 2 M1P4380 Fire Fighting Network Valves (O.S&Y gate valve, Check valve, Alarm Check Valve) Erection 6 27-Sep-15 03-Oct-15 SCG Ofoq 2 M1P4450 Pipe Testing and Flushing 12 04-Oct-15 19-Oct-15 SCG Ofoq 2 M1P4390 Fire Hose Stations Erection 36 13-Sep-15 29-Oct-15 SCG Ofoq 28 M1P4400 Fire Hose Real Stations Erection 36 13-Sep-15 29-Oct-15 SCG Ofoq 28 M1P4420 Fire Extinguishers 3 07-Nov-15 09-Nov-15 SCG Ofoq 19 M1P4410 Sprinklers Erection 45 20-Oct-15 10-Dec-15 SCG Ofoq 2 M1P4430 FM200 System for (MVSG Room, RMU Room, Transformer Room, Telecom Room, Security Room,LV Room, IT&Main IT Room) 40 10-Nov-15 27-Dec-15 SCG Ofoq 4 M1P4440 Foam Fire System for (Generator Room, Feul Tank Room) Erection 40 11-Nov-15 28-Dec-15 SCG Ofoq 3 Plumbing SystemPlumbing System 54 02-Sep-15 09-Nov-15 19 M1P4510 F.D , F.F.D , P.D , F.C.O , A.D , G.D , T.D Erection 12 02-Sep-15 15-Sep-15 SCG Ofoq 19 M1P4460 PPR Domestic Water Pipes Erection 18 02-Sep-15 26-Sep-15 SCG Ofoq 37 M1P4490 Irrigation System PVC Erection 18 02-Sep-15 26-Sep-15 SCG Ofoq 49 M1P4500 Valves Erection 6 27-Sep-15 03-Oct-15 SCG Ofoq 37 M1P4520 Hose Bibbs Erection 6 27-Sep-15 03-Oct-15 SCG Ofoq 49 M1P4470 UPVC for Drainage System Erection 18 16-Sep-15 11-Oct-15 SCG Ofoq 19 M1P4570 Testing Domestic Network 6 04-Oct-15 11-Oct-15 SCG Ofoq 37 M1P4550 Fountains Tank Erection 26 10-Sep-15 15-Oct-15 SCG N/A 40 M1P4560 Water Fall Tank Erection 26 10-Sep-15 15-Oct-15 SCG N/A 40 M1P4530 HDPE Domestic Water Pipes Erection 6 12-Oct-15 19-Oct-15 SCG Ofoq 37 M1P4480 PVC for Forced Main Line Erection 12 12-Oct-15 26-Oct-15 SCG Ofoq 19 M1P4580 Testing for Drainage Network 6 27-Oct-15 02-Nov-15 SCG Ofoq 19 M1P4540 HDPE for Drainage , Waste , Vent, Storm Systems Erection 6 03-Nov-15 09-Nov-15 SCG Ofoq 19 Finishing WorkFinishing Work 126 29-Jul-15 29-Dec-15 2 Jun Jul Aug Sep Oct Nov Dec Jan eb 2015 2016 31-Dec- 28-Dec- 09-Nov-15, Plumbi 29-Dec- Majarrah Business Complex Classic Schedule Layout 22-Jun-15 14:36 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 21 of 39 TASK filter: All Activities © Primavera Systems, Inc.
  • 22. Activity ID Activity Name Original Duration Start Finish Consultant Contractor Total Float M1P4660 Block Work Completion for Equipments / Service / Stores Rooms 12 29-Jul-15 11-Aug-15 HW ECIP 0 M1P4670 Plaster Work Applied for Equipments / Service / Stores Roo 12 12-Aug-15 25-Aug-15 HW ECIP 0 M1P4620 Curb Stone Material Erection 12 06-Sep-15 19-Sep-15 HW ECIP 46 M1P4680 MEP 1st Fix for Equipments / Service / Stores Rooms 26 26-Aug-15 28-Sep-15 SCG Ofoq 0 M1P4630 Interlock Material Erection 12 20-Sep-15 07-Oct-15 HW ECIP 46 M1P8420 Paint 1st and 2nd Coat for Ceiling and Walls in Upper Basement 26 06-Sep-15 10-Oct-15 HW ECIP 54 M1P4590 False Ceiling Erection for Equipments / Service / Stores Rooms 12 29-Sep-15 13-Oct-15 HW ECIP 0 M1P4610 Paint Applied for Equipments / Service / Stores Rooms 12 15-Oct-15 28-Oct-15 HW ECIP 0 M1P4650 Raised Floor Erection (Expected in IT & Main IT Room) 6 29-Oct-15 04-Nov-15 HW ECIP 6 M1P4600 Flooring Tiles Applied for Equipments / Service / Stores Roo 12 29-Oct-15 11-Nov-15 HW ECIP 0 M1P4640 Doors Erection for Equipments / Service / Stores Rooms 12 12-Nov-15 25-Nov-15 HW ECIP 5 M1P4690 MEP Final Fix for Equipments / Service / Stores Rooms 12 12-Nov-15 25-Nov-15 SCG Ofoq 0 M1P8430 Final Coat of Paint for Walls and Ceiling 12 12-Dec-15 26-Dec-15 HW 2 M1P8440 Epoxi Paint for Flooring 12 15-Dec-15 29-Dec-15 HW 2 Lower BasementLower Basement 164 15-Jun-15 31-Dec-15 0 GeneralGeneral 0 07-Jul-15 07-Jul-15 15 M1P6450 Client Clear Vision about Secuirty Issues as (CCTV, Access Control...) 0 07-Jul-15 Client 6 M1P6460 Client Clear Vision about Data Issues as (Central, IT requirements...) 0 07-Jul-15 Client 15 DesignDesign 60 15-Jun-15 25-Aug-15 41 Architectural DesArchitectural Design 24 15-Jun-15 12-Jul-15 0 M1P4700 Final Parking Layout for Lower Basement 0 28-Jun-15 Client 0 M1P4710 Final Architectural Dimensional Plan for Lower Basement 12 15-Jun-15 28-Jun-15 T.B 0 M1P4720 Final Architectural Package for Lower Basement 12 29-Jun-15 12-Jul-15 HW 0 Structural DesignStructural Design 6 19-Aug-15 25-Aug-15 41 M1P6440 Structural Design for Equipment Foundation (Fire Pump , Supply and Exhaust Fans........) 6 19-Aug-15 25-Aug-15 HW 41 MEP DesignMEP Design 24 29-Jun-15 28-Jul-15 6 Electrical SystemsElectrical Systems 24 29-Jun-15 28-Jul-15 6 Power SystemPower System 6 29-Jun-15 05-Jul-15 15 M1P4750 Updated Design for Power System 6 29-Jun-15 05-Jul-15 SCG 15 Lighting SystemLighting System 6 29-Jun-15 05-Jul-15 15 M1P4760 Updated Design for Lighting System 6 29-Jun-15 05-Jul-15 SCG 15 Fire Alarm SystemFire Alarm System 6 13-Jul-15 20-Jul-15 0 Jun Jul Aug Sep Oct Nov Dec Jan eb 2015 2016 31-Dec- 07-Jul-15, General 25-Aug-15, Design 12-Jul-15, Architectural Design 25-Aug-15, Structural Design 28-Jul-15, MEP Design 28-Jul-15, Electrical Systems 05-Jul-15, Power System 05-Jul-15, Lighting System 20-Jul-15, Fire Alarm System Majarrah Business Complex Classic Schedule Layout 22-Jun-15 14:36 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 22 of 39 TASK filter: All Activities © Primavera Systems, Inc.
  • 23. Activity ID Activity Name Original Duration Start Finish Consultant Contractor Total Float M1P5370 Updated Design for Fire Alarm System 6 13-Jul-15 20-Jul-15 C/SCG 0 Parking SystemParking System 18 29-Jun-15 20-Jul-15 0 M1P5140 Updated Design for Parking System 18 29-Jun-15 20-Jul-15 C/SCG 0 CCTV SystemCCTV System 6 13-Jul-15 20-Jul-15 2 M1P4730 Updated Design for CCTV System 6 13-Jul-15 20-Jul-15 C/SCG 2 Data SystemData System 6 13-Jul-15 20-Jul-15 11 M1P4740 Updated Design for Data System 6 13-Jul-15 20-Jul-15 C/SCG 11 BMS SystemBMS System 6 21-Jul-15 28-Jul-15 6 M1P5690 Updated Design for BMS System 6 21-Jul-15 28-Jul-15 SCG 6 Mechanical SystemsMechanical Systems 18 29-Jun-15 20-Jul-15 6 HVAC SystemHVAC System 6 13-Jul-15 20-Jul-15 0 M1P4770 HVAC Updated Design for Lower Basement 6 13-Jul-15 20-Jul-15 SCG 0 Fire Fighting SysteFire Fighting System 6 29-Jun-15 05-Jul-15 3 M1P4820 Fire Fighting Updated Design for Lower Basement 6 29-Jun-15 05-Jul-15 SCG 3 Plumbing SystemPlumbing System 6 13-Jul-15 20-Jul-15 6 Drainage SystemDrainage System 6 13-Jul-15 20-Jul-15 6 M1P4780 Final Update for Lower Basement Drainage System 6 13-Jul-15 20-Jul-15 SCG 6 Shop DrawingsShop Drawings 60 29-Jun-15 08-Sep-15 41 Architectural ShoArchitectural Shop Drawing 12 13-Jul-15 28-Jul-15 4 M1P4830 Lower Basement Architectural Shop Drawing Submittal 6 13-Jul-15 20-Jul-15 ECIP 4 M1P4840 Lower Basement Architectural Shop Drawing Approval 6 21-Jul-15 28-Jul-15 HW 4 Structural Shop DStructural Shop Drawing 50 11-Jul-15 08-Sep-15 41 M1P4850 Lower Basement Construction , Expansion Joints Details Shop Drawing Submittal 6 11-Jul-15 16-Jul-15 ECIP 64 M1P4860 Lower Basement Construction , Expansion Joints Details Shop Drawing Approval 6 19-Jul-15 26-Jul-15 HW 64 M1P6470 Lower Basement Equipments Foundations shop drawings Submittal 6 26-Aug-15 01-Sep-15 ECIP 41 M1P6480 Lower Basement Equipments Foundations shop drawings Approval 6 02-Sep-15 08-Sep-15 HW 41 Electrical SystemsElectrical Systems 36 06-Jul-15 18-Aug-15 0 Power SystemPower System 12 06-Jul-15 20-Jul-15 15 M1P4870 Lower Basement Power System Layout Submittal 6 06-Jul-15 12-Jul-15 Ofoq 15 M1P4880 Lower Basement Power System Layout Approval 6 13-Jul-15 20-Jul-15 SCG 15 Lighting SystemLighting System 12 06-Jul-15 20-Jul-15 15 M1P4890 Lower Basement Lighting System Layout Submittal 6 06-Jul-15 12-Jul-15 Ofoq 15 M1P4900 Lower Basement Lighting System Layout Approval 6 13-Jul-15 20-Jul-15 SCG 15 Fire Alarm SystemFire Alarm System 12 21-Jul-15 04-Aug-15 12 M1P5380 Lower Basement Fire Alarm System Layout Submittal 6 21-Jul-15 28-Jul-15 Ofoq 12 Jun Jul Aug Sep Oct Nov Dec Jan eb 2015 2016 20-Jul-15, Parking System 20-Jul-15, CCTV System 20-Jul-15, Data System 28-Jul-15, BMS System 20-Jul-15, Mechanical Systems 20-Jul-15, HVAC System 05-Jul-15, Fire Fighting System 20-Jul-15, Plumbing System 20-Jul-15, Drainage System 08-Sep-15, Shop Drawings 28-Jul-15, Architectural Shop Drawing 08-Sep-15, Structural Shop Draw 18-Aug-15, Electrical Systems 20-Jul-15, Power System 20-Jul-15, Lighting System 04-Aug-15, Fire Alarm System Majarrah Business Complex Classic Schedule Layout 22-Jun-15 14:36 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 23 of 39 TASK filter: All Activities © Primavera Systems, Inc.
  • 24. Activity ID Activity Name Original Duration Start Finish Consultant Contractor Total Float M1P5390 Lower Basement Fire Alarm System Layout Approval 6 29-Jul-15 04-Aug-15 SCG 12 Parking SystemParking System 12 21-Jul-15 04-Aug-15 0 M1P5120 Lower Basement Parking System Layout Submittal 6 21-Jul-15 28-Jul-15 Ofoq 0 M1P5130 Lower Basement Parking System Layout Approval 6 29-Jul-15 04-Aug-15 SCG 0 CCTV SystemCCTV System 12 21-Jul-15 04-Aug-15 2 M1P4910 Lower Basement CCTV System Layout Submittal 6 21-Jul-15 28-Jul-15 Ofoq 2 M1P4920 Lower Basement CCTV System Layout Approval 6 29-Jul-15 04-Aug-15 SCG 2 Data SystemData System 12 21-Jul-15 04-Aug-15 11 M1P4930 Lower Basement Data System Layout Submittal 6 21-Jul-15 28-Jul-15 Ofoq 11 M1P4940 Lower Basement Data System Layout Approval 6 29-Jul-15 04-Aug-15 SCG 11 BMS SystemBMS System 12 05-Aug-15 18-Aug-15 0 M1P5700 Lower Basement BMS System Layout Submittal 6 05-Aug-15 11-Aug-15 Ofoq 0 M1P5710 Lower Basement BMS System Layout Approval 6 12-Aug-15 18-Aug-15 SCG 0 Mechanical SysteMechanical Systems 42 29-Jun-15 18-Aug-15 41 HVAC SystemHVAC System 42 29-Jun-15 18-Aug-15 41 M1P5920 Fans Static Pressure Calculations Submittal 6 29-Jun-15 05-Jul-15 Ofoq 21 M1P5930 Fans Static Pressure Calculations Approval 6 06-Jul-15 12-Jul-15 SCG 21 M1P7250 Builder Work for Shaft Opening Layout Submittal 3 13-Jul-15 15-Jul-15 Ofoq 22 M1P7260 Builder Work for Shaft Opening Layout Approval 6 16-Jul-15 25-Jul-15 HW 22 M1P4950 Lower Basement HVAC System Layout Submittal 6 21-Jul-15 28-Jul-15 Ofoq 0 M1P4960 Lower Basement HVAC System Layout Approval 6 29-Jul-15 04-Aug-15 SCG 0 M1P6420 Lower Basement Fan Room Details Submittal 6 05-Aug-15 11-Aug-15 Ofoq 41 M1P6430 Lower Basement Fan Room Details Approval 6 12-Aug-15 18-Aug-15 SCG 41 Fire Fighting SystemFire Fighting System 12 06-Jul-15 20-Jul-15 3 M1P4970 Lower Basement Fire Fighting System Layout Submittal 6 06-Jul-15 12-Jul-15 Ofoq 3 M1P4980 Lower Basement Fire Fighting System Layout Approval 6 13-Jul-15 20-Jul-15 SCG 3 Plumbing SystemPlumbing System 12 21-Jul-15 04-Aug-15 11 Drainage SystemDrainage System 12 21-Jul-15 04-Aug-15 11 M1P4990 Lower Basement Drainage System Layout Submittal 6 21-Jul-15 28-Jul-15 Ofoq 11 M1P5000 Lower Basement Drainage System Layout Approval 6 29-Jul-15 04-Aug-15 SCG 11 Composite DrawiComposite Drawing 12 19-Aug-15 01-Sep-15 0 M1P5050 Lower Basement MEP Composite Drawing Submittal 6 19-Aug-15 25-Aug-15 Ofoq 0 M1P5060 Lower Basement MEP Composite Drawing Approval 6 26-Aug-15 01-Sep-15 SCG 0 MaterialsMaterials 149 15-Jun-15 13-Dec-15 3 Finishing MateriaFinishing Materials 35 27-Jul-15 05-Sep-15 58 Material SubmittalMaterial Submittal 20 27-Jul-15 18-Aug-15 58 M110001246 Expansion Joints Submittal 6 27-Jul-15 02-Aug-15 ECIP 64 M1P5070 False Ceiling Material Submittal 18 29-Jul-15 18-Aug-15 ECIP 21 Jun Jul Aug Sep Oct Nov Dec Jan eb 2015 2016 04-Aug-15, Parking System 04-Aug-15, CCTV System 04-Aug-15, Data System 18-Aug-15, BMS System 18-Aug-15, Mechanical Systems 18-Aug-15, HVAC System 20-Jul-15, Fire Fighting System 04-Aug-15, Plumbing System 04-Aug-15, Drainage System 01-Sep-15, Composite Drawing 13-Dec-15, 05-Sep-15, Finishing Materials 18-Aug-15, Material Submittal Majarrah Business Complex Classic Schedule Layout 22-Jun-15 14:36 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 24 of 39 TASK filter: All Activities © Primavera Systems, Inc.
  • 25. Activity ID Activity Name Original Duration Start Finish Consultant Contractor Total Float M1P5080 Flooring Tiles Material Submittal 18 29-Jul-15 18-Aug-15 ECIP 45 M1P5090 Paint Material Submittal 18 29-Jul-15 18-Aug-15 ECIP 33 M1P5100 Curb Stone Material Submittal 18 29-Jul-15 18-Aug-15 ECIP 46 M1P5110 Interlock Material Submittal 18 29-Jul-15 18-Aug-15 ECIP 58 M1P7610 Doors Submittal 18 29-Jul-15 18-Aug-15 ECIP 58 Material ApprovalMaterial Approval 20 03-Aug-15 25-Aug-15 58 M110001256 Expansion Joints Approval 6 03-Aug-15 09-Aug-15 HW 64 M1P5150 False Ceiling Material Approval 6 19-Aug-15 25-Aug-15 HW 21 M1P5160 Flooring Tiles Material Approval 6 19-Aug-15 25-Aug-15 HW 45 M1P5170 Paint Material Approval 6 19-Aug-15 25-Aug-15 HW 33 M1P5180 Curb Stone Material Approval 6 19-Aug-15 25-Aug-15 HW 46 M1P5190 Interlock Material Approval 6 19-Aug-15 25-Aug-15 HW 58 M1P7630 Doors Approval 6 19-Aug-15 25-Aug-15 HW 58 Material P.OMaterial P.O 17 10-Aug-15 29-Aug-15 58 M110001266 Expansion Joints P.O 3 10-Aug-15 12-Aug-15 ECIP 64 M1P5200 False Ceiling Material P.O 3 26-Aug-15 29-Aug-15 ECIP 21 M1P5210 Flooring Tiles Material P.O 3 26-Aug-15 29-Aug-15 ECIP 45 M1P5220 Paint Material P.O 3 26-Aug-15 29-Aug-15 ECIP 33 M1P5230 Curb Stone Material P.O 3 26-Aug-15 29-Aug-15 ECIP 46 M1P5240 Interlock Material P.O 3 26-Aug-15 29-Aug-15 ECIP 58 M1P7650 Doors P.O 3 26-Aug-15 29-Aug-15 ECIP 58 Material DeliveryMaterial Delivery 20 13-Aug-15 05-Sep-15 58 M110001276 Expansion Joints Delivery 6 13-Aug-15 19-Aug-15 ECIP 64 M1P5250 False Ceiling Material Delivery 6 30-Aug-15 05-Sep-15 ECIP 21 M1P5260 Flooring Tiles Material Delivery 6 30-Aug-15 05-Sep-15 ECIP 45 M1P5270 Paint Material Delivery 6 30-Aug-15 05-Sep-15 ECIP 33 M1P5280 Curb Stone Material Delivery 6 30-Aug-15 05-Sep-15 ECIP 46 M1P5290 Interlock Material Delivery 6 30-Aug-15 05-Sep-15 ECIP 58 M1P7670 Doors Delivery 6 30-Aug-15 05-Sep-15 ECIP 58 MEP MaterialsMEP Materials 149 15-Jun-15 13-Dec-15 3 Material SubmittalMaterial Submittal 72 15-Jun-15 08-Sep-15 40 Electrical Material SElectrical Material Submittal 72 15-Jun-15 08-Sep-15 20 M490 PVC , EMT Conduit with Accessories Material Submittal 3 15-Jun-15 17-Jun-15 Ofoq 48 M570 Cable Trays Submittal 6 15-Jun-15 21-Jun-15 Ofoq 86 M530 Wires for Power and Lighting Material Submittal 6 21-Jul-15 28-Jul-15 Ofoq 56 M520 Lighting Fixture Material Submittal 12 21-Jul-15 04-Aug-15 Ofoq 44 M560 Wiring Devices Submittal 12 21-Jul-15 04-Aug-15 Ofoq 15 M580 Fire Alarm Material Submittal 12 21-Jul-15 04-Aug-15 Ofoq 0 M500 Structured Cable for Data System Material Submittal 4 05-Aug-15 09-Aug-15 Ofoq 11 Jun Jul Aug Sep Oct Nov Dec Jan eb 2015 2016 25-Aug-15, Material Approval 29-Aug-15, Material P.O 05-Sep-15, Material Delivery 13-Dec-15, 08-Sep-15, Material Submittal 08-Sep-15, Electrical Material Su Majarrah Business Complex Classic Schedule Layout 22-Jun-15 14:36 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 25 of 39 TASK filter: All Activities © Primavera Systems, Inc.
  • 26. Activity ID Activity Name Original Duration Start Finish Consultant Contractor Total Float M510 Distribution Board Material Submittal 16 21-Jul-15 09-Aug-15 Ofoq 24 M540 CCTV Cameras Material Submittal 4 05-Aug-15 09-Aug-15 N/A 2 M550 Parking System Material Submittal 18 05-Aug-15 25-Aug-15 N/A 0 M900 LV Cables Submittal 6 02-Sep-15 08-Sep-15 Ofoq 12 M930 BMS Submittal 18 19-Aug-15 08-Sep-15 Ofoq 1 Electrical EquipmentElectrical Equipment 18 21-Jul-15 11-Aug-15 16 M1P5410 MCC Submittal 18 21-Jul-15 11-Aug-15 Ofoq 16 Mechanical MateriaMechanical Material Submittal 30 13-Jul-15 18-Aug-15 58 HVAC System SubmHVAC System Submittal 12 05-Aug-15 18-Aug-15 58 M1P5720 Galvanized Duct Submittal 6 05-Aug-15 11-Aug-15 Ofoq 4 M1P5760 Child Water Pipes Submittal 6 05-Aug-15 11-Aug-15 Ofoq 34 M1P5770 Child Water Insulation Submittal 6 05-Aug-15 11-Aug-15 Ofoq 64 M1P5730 Volume Dampers Submittal 12 05-Aug-15 18-Aug-15 Ofoq 10 M1P5740 Fire Dampers Submittal 12 05-Aug-15 18-Aug-15 Ofoq 10 M1P5750 Fire Smoke Dampers Submittal 12 05-Aug-15 18-Aug-15 Ofoq 10 M1P5780 Supply Air Grill Submittal 12 05-Aug-15 18-Aug-15 Ofoq 46 M1P5790 Exhaust Air Grill Submittal 12 05-Aug-15 18-Aug-15 Ofoq 46 Fire Fighting SystemFire Fighting System Submittal 6 21-Jul-15 28-Jul-15 23 M1P6490 Seamless Black Steel Pipes Submittal 3 21-Jul-15 25-Jul-15 Ofoq 20 M1P6500 Fire Fighting Network Valves (O.S&Y gate valve, Check valve, Alarm Check Valve) Submittal 6 21-Jul-15 28-Jul-15 Ofoq 23 M1P6510 Sprinklers Submittal 6 21-Jul-15 28-Jul-15 Ofoq 14 M1P6540 Fire Hose Stations Submittal 6 21-Jul-15 28-Jul-15 Ofoq 22 M1P6550 Fire Hose Real Stations Submittal 6 21-Jul-15 28-Jul-15 Ofoq 22 M1P6560 Fire Extinguishers Submittal 6 21-Jul-15 28-Jul-15 Ofoq 13 Plumbing System SPlumbing System Submittal 6 05-Aug-15 11-Aug-15 64 M1P6840 PPR Domestic Water Pipes Submittal 6 05-Aug-15 11-Aug-15 Ofoq 46 M1P6860 UPVC for Drainage System Submittal 6 05-Aug-15 11-Aug-15 Ofoq 40 M1P6870 PVC for Forced Main Line Submittal 6 05-Aug-15 11-Aug-15 Ofoq 58 M1P6890 Valves Submittal 6 05-Aug-15 11-Aug-15 Ofoq 64 M1P6900 F.D , F.F.D , P.D , F.C.O , A.D , G.D , T.D Submittal 6 05-Aug-15 11-Aug-15 Ofoq 28 Mechanical EquipmMechanical Equipment Submittal 30 13-Jul-15 18-Aug-15 35 HVAC EquipmentHVAC Equipment Submittal 30 13-Jul-15 18-Aug-15 35 M1P5850 Exhaust Fans Submittal 12 13-Jul-15 28-Jul-15 Ofoq 21 M1P5860 Supply Fans Submittal 12 13-Jul-15 28-Jul-15 Ofoq 21 M1P5810 AC DX Split Units Submittal 12 05-Aug-15 18-Aug-15 Ofoq 35 M1P5870 Fan Coil Units Submittal 12 05-Aug-15 18-Aug-15 Ofoq 17 Fire Fighting EquFire Fighting Equipment Submittal 6 21-Jul-15 28-Jul-15 3 M1P8450 Fire Pumps Submittal 6 21-Jul-15 28-Jul-15 Ofoq 3 Plumbing EquipmPlumbing Equipment Submittal 6 05-Aug-15 11-Aug-15 11 Jun Jul Aug Sep Oct Nov Dec Jan eb 2015 2016 11-Aug-15, Electrical Equipment 18-Aug-15, Mechanical Material Subm 18-Aug-15, HVAC System Submittal 28-Jul-15, Fire Fighting System Submittal 11-Aug-15, Plumbing System Submittal 18-Aug-15, Mechanical Equipment Su 18-Aug-15, HVAC Equipment Submi 28-Jul-15, Fire Fighting Equipment Submi 11-Aug-15, Plumbing Equipment Subm Majarrah Business Complex Classic Schedule Layout 22-Jun-15 14:36 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 26 of 39 TASK filter: All Activities © Primavera Systems, Inc.
  • 27. Activity ID Activity Name Original Duration Start Finish Consultant Contractor Total Float M1P8460 Domestic Water Pump Submittal 6 05-Aug-15 11-Aug-15 Ofoq 11 M1P8470 Irrigation Pump Submittal 6 05-Aug-15 11-Aug-15 Ofoq 11 M1P8480 Waste Water Submersible Pumps Submittal 6 05-Aug-15 11-Aug-15 Ofoq 11 M1P8490 Sewage Water Submersible Pumps Submittal 6 05-Aug-15 11-Aug-15 Ofoq 11 Material ApprovalMaterial Approval 87 18-Jun-15 03-Oct-15 28 Electrical Material AElectrical Material Approval 87 18-Jun-15 03-Oct-15 8 M590 PVC , EMT Conduit with Accessories Conduit Material Approval 6 18-Jun-15 24-Jun-15 SCG 48 M670 Cable Trays Approval 6 22-Jun-15 28-Jun-15 SCG 86 M630 Wires for Power and Lighting Material Approval 6 29-Jul-15 04-Aug-15 SCG 56 M620 Lighting Fixture Material Approval 6 05-Aug-15 11-Aug-15 SCG 44 M660 Wiring Devices Approval 6 05-Aug-15 11-Aug-15 SCG 15 M680 Fire Alarm Material Approval 6 05-Aug-15 11-Aug-15 SCG 0 M600 Structured Cable for Data System Material Approval 6 10-Aug-15 16-Aug-15 SCG 11 M610 Distribution Board Material Approval 6 10-Aug-15 16-Aug-15 SCG 24 M640 CCTV Cameras Material Approval 6 10-Aug-15 16-Aug-15 SCG 2 M650 Parking System Material Approval 6 26-Aug-15 01-Sep-15 SCG 0 M890 LV Cables Approval 6 09-Sep-15 15-Sep-15 SCG 12 M940 BMS Approval 18 09-Sep-15 03-Oct-15 SCG 1 Electrical EquipmentElectrical Equipment 6 12-Aug-15 18-Aug-15 16 M1P5500 MCC Approval 6 12-Aug-15 18-Aug-15 SCG 16 Mechanical MateriaMechanical Material Approval 27 26-Jul-15 25-Aug-15 58 HVAC System ApproHVAC System Approval 12 12-Aug-15 25-Aug-15 58 M1P5940 Galvanized Duct Approval 6 12-Aug-15 18-Aug-15 SCG 4 M1P5980 Child Water Pipes Approval 6 12-Aug-15 18-Aug-15 SCG 34 M1P5990 Child Water Insulation Approval 6 12-Aug-15 18-Aug-15 SCG 64 M1P5950 Volume Dampers Approval 6 19-Aug-15 25-Aug-15 SCG 10 M1P5960 Fire Dampers Approval 6 19-Aug-15 25-Aug-15 SCG 10 M1P5970 Fire Smoke Dampers Approval 6 19-Aug-15 25-Aug-15 SCG 10 M1P6000 Supply Air Grill Approval 6 19-Aug-15 25-Aug-15 SCG 46 M1P6010 Exhaust Air Grill Approval 6 19-Aug-15 25-Aug-15 SCG 46 Fire Fighting SystemFire Fighting System Approval 9 26-Jul-15 04-Aug-15 23 M1P6570 Seamless Black Steel Pipes Approval 6 26-Jul-15 01-Aug-15 SCG 20 M1P6580 Fire Fighting Network Valves (O.S&Y gate valve, Check valve, Alarm Check Valve) Approval 6 29-Jul-15 04-Aug-15 SCG 23 M1P6590 Sprinklers Approval 6 29-Jul-15 04-Aug-15 SCG 14 M1P6620 Fire Hose Stations Approval 6 29-Jul-15 04-Aug-15 SCG 22 M1P6630 Fire Hose Real Stations Approval 6 29-Jul-15 04-Aug-15 SCG 22 M1P6640 Fire Extinguishers Approval 6 29-Jul-15 04-Aug-15 SCG 13 Plumbing System APlumbing System Approval 6 12-Aug-15 18-Aug-15 64 Jun Jul Aug Sep Oct Nov Dec Jan eb 2015 2016 03-Oct-15, Material Appro 03-Oct-15, Electrical Mater 18-Aug-15, Electrical Equipment 25-Aug-15, Mechanical Material Ap 25-Aug-15, HVAC System Approval 04-Aug-15, Fire Fighting System Approv 18-Aug-15, Plumbing System Approv Majarrah Business Complex Classic Schedule Layout 22-Jun-15 14:36 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 27 of 39 TASK filter: All Activities © Primavera Systems, Inc.
  • 28. Activity ID Activity Name Original Duration Start Finish Consultant Contractor Total Float M1P6950 PPR Domestic Water Pipes Approval 6 12-Aug-15 18-Aug-15 SCG 46 M1P6970 UPVC for Drainage System Approval 6 12-Aug-15 18-Aug-15 SCG 40 M1P6980 PVC for Forced Main Line Approval 6 12-Aug-15 18-Aug-15 SCG 58 M1P7000 Valves Approval 6 12-Aug-15 18-Aug-15 SCG 64 M1P7010 F.D , F.F.D , P.D , F.C.O , A.D , G.D , T.D Approval 6 12-Aug-15 18-Aug-15 SCG 28 Mechanical EquipmMechanical Equipment Approval 24 29-Jul-15 25-Aug-15 35 HVAC EquipmentHVAC Equipment Approval 24 29-Jul-15 25-Aug-15 35 M1P6070 Exhaust Fans Approval 6 29-Jul-15 04-Aug-15 SCG 21 M1P6080 Supply Fans Approval 6 29-Jul-15 04-Aug-15 SCG 21 M1P6030 AC DX Split Units Approval 6 19-Aug-15 25-Aug-15 SCG 35 M1P6090 Fan Coil Units Approval 6 19-Aug-15 25-Aug-15 SCG 17 Fire Fighting EquFire Fighting Equipment Approval 6 29-Jul-15 04-Aug-15 3 M1P8500 Fire Pumps Approval 6 29-Jul-15 04-Aug-15 SCG 3 Plumbing EquipmPlumbing Equipment Approval 6 12-Aug-15 18-Aug-15 11 M1P8540 Domestic Water Pump Approval 6 12-Aug-15 18-Aug-15 SCG 11 M1P8550 Irrigation Pump Approval 6 12-Aug-15 18-Aug-15 SCG 11 M1P8560 Waste Water Submersible Pumps Approval 6 12-Aug-15 18-Aug-15 SCG 11 M1P8570 Sewage Water Submersible Pumps Approval 6 12-Aug-15 18-Aug-15 SCG 11 Material P.OMaterial P.O 84 25-Jun-15 07-Oct-15 28 Electrical MaterialElectrical Material P.O 84 25-Jun-15 07-Oct-15 8 M690 PVC , EMT Conduit with Accessories Conduit Material P.O 3 25-Jun-15 28-Jun-15 Ofoq 48 M770 Cable Trays P.O 3 29-Jun-15 01-Jul-15 Ofoq 86 M730 Wires for Power and Lighting Material P.O 3 05-Aug-15 08-Aug-15 Ofoq 56 M720 Lighting Fixture Material P.O 3 12-Aug-15 15-Aug-15 Ofoq 44 M760 Wiring Devices P.O 3 12-Aug-15 15-Aug-15 Ofoq 15 M780 Fire Alarm Material P.O 3 12-Aug-15 15-Aug-15 Ofoq 0 M700 Structured Cable for Data System Material P.O 3 17-Aug-15 19-Aug-15 Ofoq 11 M710 Distribution Board Material P.O 3 17-Aug-15 19-Aug-15 Ofoq 24 M740 CCTV Cameras Material P.O 3 17-Aug-15 19-Aug-15 N/A 2 M750 Parking System Material P.O 3 02-Sep-15 05-Sep-15 N/A 0 M910 LV Cables P.O 3 16-Sep-15 19-Sep-15 Ofoq 12 M950 BMS P.O 3 04-Oct-15 07-Oct-15 Ofoq 1 Electrical EquipmentElectrical Equipment 3 19-Aug-15 22-Aug-15 16 M1P5590 MCC P.O 3 19-Aug-15 22-Aug-15 Ofoq 16 Mechanical MateriaMechanical Material P.O 27 02-Aug-15 01-Sep-15 55 HVAC System P.OHVAC System P.O 9 19-Aug-15 29-Aug-15 58 M1P6100 Galvanized Duct P.O 3 19-Aug-15 22-Aug-15 Ofoq 4 M1P6140 Child Water Pipes P.O 3 19-Aug-15 22-Aug-15 Ofoq 34 M1P6150 Child Water Insulation P.O 3 19-Aug-15 22-Aug-15 Ofoq 64 M1P6110 Volume Dampers P.O 3 26-Aug-15 29-Aug-15 Ofoq 10 Jun Jul Aug Sep Oct Nov Dec Jan eb 2015 2016 25-Aug-15, Mechanical Equipment A 25-Aug-15, HVAC Equipment Appr 04-Aug-15, Fire Fighting Equipment App 18-Aug-15, Plumbing Equipment App 07-Oct-15, Material P.O 07-Oct-15, Electrical Mater 22-Aug-15, Electrical Equipment 01-Sep-15, Mechanical Material P 29-Aug-15, HVAC System P.O Majarrah Business Complex Classic Schedule Layout 22-Jun-15 14:36 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 28 of 39 TASK filter: All Activities © Primavera Systems, Inc.
  • 29. Activity ID Activity Name Original Duration Start Finish Consultant Contractor Total Float M1P6120 Fire Dampers P.O 3 26-Aug-15 29-Aug-15 Ofoq 10 M1P6130 Fire Smoke Dampers P.O 3 26-Aug-15 29-Aug-15 Ofoq 10 M1P6160 Supply Air Grill P.O 3 26-Aug-15 29-Aug-15 Ofoq 46 M1P6170 Exhaust Air Grill P.O 3 26-Aug-15 29-Aug-15 Ofoq 46 Fire Fighting SystemFire Fighting System P.O 6 02-Aug-15 08-Aug-15 23 M1P6650 Seamless Black Steel Pipes P.O 3 02-Aug-15 04-Aug-15 Ofoq 20 M1P6660 Fire Fighting Network Valves (O.S&Y gate valve, Check valve, Alarm Check Valve) P.O 3 05-Aug-15 08-Aug-15 Ofoq 23 M1P6670 Sprinklers P.O 3 05-Aug-15 08-Aug-15 Ofoq 14 M1P6700 Fire Hose Stations P.O 3 05-Aug-15 08-Aug-15 Ofoq 22 M1P6710 Fire Hose Real Stations P.O 3 05-Aug-15 08-Aug-15 Ofoq 22 M1P6720 Fire Extinguishers P.O 3 05-Aug-15 08-Aug-15 Ofoq 13 Plumbing System PPlumbing System P.O 3 19-Aug-15 22-Aug-15 64 M1P7060 PPR Domestic Water Pipes P.O 3 19-Aug-15 22-Aug-15 Ofoq 46 M1P7080 UPVC for Drainage System P.O 3 19-Aug-15 22-Aug-15 Ofoq 40 M1P7090 PVC for Forced Main Line P.O 3 19-Aug-15 22-Aug-15 Ofoq 58 M1P7110 Valves P.O 3 19-Aug-15 22-Aug-15 Ofoq 64 M1P7120 F.D , F.F.D , P.D , F.C.O , A.D , G.D , T.D P.O 3 19-Aug-15 22-Aug-15 Ofoq 28 Mechanical EquipmMechanical Equipment P.O 24 05-Aug-15 01-Sep-15 35 HVAC EquipmentHVAC Equipment P.O 24 05-Aug-15 01-Sep-15 35 M1P6230 Exhaust Fans P.O 6 05-Aug-15 11-Aug-15 Ofoq 21 M1P6240 Supply Fans P.O 6 05-Aug-15 11-Aug-15 Ofoq 21 M1P6190 AC DX Split Units P.O 6 26-Aug-15 01-Sep-15 Ofoq 35 M1P6250 Fan Coil Units P.O 6 26-Aug-15 01-Sep-15 Ofoq 17 Fire Fighting EquFire Fighting Equipment P.O 3 05-Aug-15 08-Aug-15 3 M1P8510 Fire Pumps P.O 3 05-Aug-15 08-Aug-15 Ofoq 3 Plumbing EquipmPlumbing Equipment P.O 3 19-Aug-15 22-Aug-15 11 M1P8580 Domestic Water Pump P.O 3 19-Aug-15 22-Aug-15 Ofoq 11 M1P8590 Irrigation Pump P.O 3 19-Aug-15 22-Aug-15 Ofoq 11 M1P8600 Waste Water Submersible Pumps P.O 3 19-Aug-15 22-Aug-15 Ofoq 11 M1P8610 Sewage Water Submersible Pumps P.O 3 19-Aug-15 22-Aug-15 Ofoq 11 Material DeliveryMaterial Delivery 137 29-Jun-15 13-Dec-15 3 Electrical MaterialElectrical Material Delivery 121 29-Jun-15 24-Nov-15 1 M790 PVC , EMT Conduit with Accessories Conduit Material Delivery 6 29-Jun-15 05-Jul-15 Ofoq 48 M870 Cable Trays Delivery 6 02-Jul-15 08-Jul-15 Ofoq 86 M830 Wires for Power and Lighting Material Delivery 6 09-Aug-15 15-Aug-15 Ofoq 56 M820 Lighting Fixture Material Delivery 18 16-Aug-15 05-Sep-15 N/A 44 M800 Structured Cable for Data System Material Delivery 18 20-Aug-15 09-Sep-15 Ofoq 11 M860 Wiring Devices Delivery 36 16-Aug-15 29-Sep-15 Ofoq 15 Jun Jul Aug Sep Oct Nov Dec Jan eb 2015 2016 08-Aug-15, Fire Fighting System P.O 22-Aug-15, Plumbing System P.O 01-Sep-15, Mechanical Equipment 01-Sep-15, HVAC Equipment P.O 08-Aug-15, Fire Fighting Equipment P.O 22-Aug-15, Plumbing Equipment P.O 13-Dec-15, 24-Nov-15, Elec Majarrah Business Complex Classic Schedule Layout 22-Jun-15 14:36 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 29 of 39 TASK filter: All Activities © Primavera Systems, Inc.
  • 30. Activity ID Activity Name Original Duration Start Finish Consultant Contractor Total Float M840 CCTV Cameras Material Delivery 45 20-Aug-15 17-Oct-15 N/A 2 M880 Fire Alarm Material Delivery 52 16-Aug-15 20-Oct-15 Ofoq 0 M810 Distribution Board Material Delivery 52 20-Aug-15 25-Oct-15 Ofoq 24 M920 LV Cables Delivery 26 20-Sep-15 25-Oct-15 Ofoq 12 M850 Parking System Material Delivery 45 06-Sep-15 02-Nov-15 N/A 0 M960 BMS Delivery 40 08-Oct-15 24-Nov-15 Ofoq 1 Electrical EquipmentElectrical Equipment 52 23-Aug-15 27-Oct-15 16 M1P5680 MCC Delivery 52 23-Aug-15 27-Oct-15 Ofoq 16 Mechanical MateriaMechanical Material Delivery 107 05-Aug-15 13-Dec-15 3 HVAC System DelivHVAC System Delivery 18 23-Aug-15 12-Sep-15 52 M1P6260 Galvanized Duct Delivery 6 23-Aug-15 29-Aug-15 Ofoq 4 M1P6300 Child Water Pipes Delivery 6 23-Aug-15 29-Aug-15 Ofoq 34 M1P6310 Child Water Insulation Delivery 6 23-Aug-15 29-Aug-15 Ofoq 64 M1P6270 Volume Dampers Delivery 12 30-Aug-15 12-Sep-15 Ofoq 10 M1P6280 Fire Dampers Delivery 12 30-Aug-15 12-Sep-15 Ofoq 10 M1P6290 Fire Smoke Dampers Delivery 12 30-Aug-15 12-Sep-15 Ofoq 10 M1P6320 Supply Air Grill Delivery 12 30-Aug-15 12-Sep-15 Ofoq 46 M1P6330 Exhaust Air Grill Delivery 12 30-Aug-15 12-Sep-15 Ofoq 46 Fire Fighting SystemFire Fighting System Delivery 81 05-Aug-15 12-Nov-15 13 M1P6730 Seamless Black Steel Pipes Delivery 6 05-Aug-15 11-Aug-15 Ofoq 20 M1P6740 Fire Fighting Network Valves (O.S&Y gate valve, Check valve, Alarm Check Valve) Delivery 18 09-Aug-15 29-Aug-15 Ofoq 23 M1P6780 Fire Hose Stations Delivery 36 09-Aug-15 19-Sep-15 Ofoq 22 M1P6790 Fire Hose Real Stations Delivery 36 09-Aug-15 19-Sep-15 Ofoq 22 M1P6750 Sprinklers Delivery 45 09-Aug-15 03-Oct-15 Ofoq 14 M1P6800 Fire Extinguishers Delivery 78 09-Aug-15 12-Nov-15 Ofoq 13 Plumbing System DPlumbing System Delivery 6 23-Aug-15 29-Aug-15 64 M1P7170 PPR Domestic Water Pipes Delivery 6 23-Aug-15 29-Aug-15 Ofoq 46 M1P7190 UPVC for Drainage System Delivery 6 23-Aug-15 29-Aug-15 Ofoq 40 M1P7200 PVC for Forced Main Line Delivery 6 23-Aug-15 29-Aug-15 Ofoq 58 M1P7220 Valves Delivery 6 23-Aug-15 29-Aug-15 Ofoq 64 M1P7230 F.D , F.F.D , P.D , F.C.O , A.D , G.D , T.D Delivery 6 23-Aug-15 29-Aug-15 Ofoq 28 Mechanical EquipmMechanical Equipment Delivery 104 09-Aug-15 13-Dec-15 3 HVAC EquipmentHVAC Equipment Delivery 52 12-Aug-15 17-Oct-15 27 M1P6350 AC DX Split Units Delivery 26 02-Sep-15 05-Oct-15 Ofoq 35 M1P6410 Fan Coil Units Delivery 26 02-Sep-15 05-Oct-15 Ofoq 17 M1P6390 Exhaust Fans Delivery 52 12-Aug-15 17-Oct-15 Ofoq 21 M1P6400 Supply Fans Delivery 52 12-Aug-15 17-Oct-15 Ofoq 21 Fire Fighting EquFire Fighting Equipment Delivery 104 09-Aug-15 13-Dec-15 3 M1P8520 Fire Pumps Delivery 104 09-Aug-15 13-Dec-15 Ofoq 3 Jun Jul Aug Sep Oct Nov Dec Jan eb 2015 2016 27-Oct-15, Electrical E 13-Dec-15, 12-Sep-15, HVAC System Delive 12-Nov-15, Fire Fi 29-Aug-15, Plumbing System Delive 13-Dec-15, 17-Oct-15, HVAC Equip 13-Dec-15, Majarrah Business Complex Classic Schedule Layout 22-Jun-15 14:36 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 30 of 39 TASK filter: All Activities © Primavera Systems, Inc.
  • 31. Activity ID Activity Name Original Duration Start Finish Consultant Contractor Total Float Plumbing EquipmPlumbing Equipment Delivery 78 23-Aug-15 26-Nov-15 11 M1P8620 Domestic Water Pump Delivery 78 23-Aug-15 26-Nov-15 Ofoq 11 M1P8630 Irrigation Pump Delivery 78 23-Aug-15 26-Nov-15 Ofoq 11 M1P8640 Waste Water Submersible Pumps Delivery 78 23-Aug-15 26-Nov-15 Ofoq 11 M1P8650 Sewage Water Submersible Pumps Delivery 78 23-Aug-15 26-Nov-15 Ofoq 11 ConstructionConstruction 138 15-Jul-15 31-Dec-15 0 Structural WorkStructural Work 119 15-Jul-15 08-Dec-15 4 M1P8340 Lower Basement PC Slab On Grade 18 15-Jul-15 06-Aug-15 HW ECIP 71 M1P7270 Openings for Duct Shafts 12 26-Jul-15 08-Aug-15 HW ECIP 22 M1P7290 Expansion Joints 12 20-Aug-15 02-Sep-15 HW ECIP 64 M1P7580 Equipments Concrete Foundations 12 09-Sep-15 26-Sep-15 HW ECIP 41 M1P7690 Lower Basement RC Slab On Grade 18 18-Nov-15 08-Dec-15 HW ECIP 4 MEP WorkMEP Work 98 02-Sep-15 31-Dec-15 0 Electrical WorksElectrical Works 98 02-Sep-15 31-Dec-15 0 Power SystemPower System 61 02-Sep-15 17-Nov-15 12 M1P7300 Lower Basement PVC Conduites for Power Outlets 12 02-Sep-15 15-Sep-15 SCG Ofoq 41 M1P7310 Lower Basement EMT Conduites for Power Outlets 12 02-Sep-15 15-Sep-15 SCG Ofoq 41 M1P7320 Lower Basement Cable Trays for LV Cables 12 02-Sep-15 15-Sep-15 SCG Ofoq 41 M1P7330 Wires for Lower Basement Power Outlets 6 16-Sep-15 26-Sep-15 SCG Ofoq 41 M1P7350 Laying Lower Basement DB Panels 2 26-Oct-15 27-Oct-15 SCG Ofoq 24 M1P7340 Laying Lower Basement LV Cables 6 26-Oct-15 01-Nov-15 SCG Ofoq 12 M1P7480 Wiring Devices Erection and termination 12 02-Nov-15 15-Nov-15 SCG Ofoq 12 M1P7360 Termination Lower Basement DB Panels 6 11-Nov-15 17-Nov-15 SCG Ofoq 12 Power EquipmentPower Equipment 14 28-Oct-15 12-Nov-15 16 M1P7370 Laying Lower Basement MCC's 2 28-Oct-15 29-Oct-15 SCG Ofoq 16 M1P7380 Termination Lower Basement MCC's 12 31-Oct-15 12-Nov-15 SCG Ofoq 16 Lighting SystemLighting System 36 02-Sep-15 19-Oct-15 29 M1P7490 Lower Basement PVC Conduites for Lighting Outlets 12 02-Sep-15 15-Sep-15 SCG Ofoq 29 M1P7500 Lower Basement EMT Conduites for Lighting Outlets 12 02-Sep-15 15-Sep-15 SCG Ofoq 29 M1P7510 Wires for Lower Basement Lighting Outlets 6 16-Sep-15 26-Sep-15 SCG Ofoq 29 M1P7470 Lighting Fixture Erection and termination 18 27-Sep-15 19-Oct-15 SCG Ofoq 29 Low Current SysteLow Current Systems 98 02-Sep-15 31-Dec-15 0 Fire Alarm SystemFire Alarm System 98 02-Sep-15 31-Dec-15 0 M1P7700 EMT Conduites 18 02-Sep-15 26-Sep-15 SCG Ofoq 19 M1P7710 Fire Alarm Cable 18 21-Oct-15 10-Nov-15 SCG Ofoq 0 M1P7720 Fire Alarm Devices 18 11-Nov-15 01-Dec-15 SCG Ofoq 0 M1P7730 Testing And Precommissioning 25 02-Dec-15 31-Dec-15 SCG Ofoq 0 Data SystemData System 98 02-Sep-15 31-Dec-15 0 M1P7740 EMT Conduites 18 02-Sep-15 26-Sep-15 SCG Ofoq 0 Jun Jul Aug Sep Oct Nov Dec Jan eb 2015 2016 26-Nov-15, Plum 31-Dec- 08-Dec-15, S 31-Dec- 31-Dec- 17-Nov-15, Power 12-Nov-15, Power 19-Oct-15, Lighting Sys 31-Dec- 31-Dec- 31-Dec- Majarrah Business Complex Classic Schedule Layout 22-Jun-15 14:36 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 31 of 39 TASK filter: All Activities © Primavera Systems, Inc.