1. Activity ID Activity Name Original
Duration
Early Start Early Finish Total
Float
0001-1 CONSTRUCTION OF LEYTE COLLEGES SCHOOL BUILDING0001-1 CONSTRUCTION OF LEYTE COLLEGES SCHOOL BUILDING381 01-Jul-15 08:00 AM 22-Sep-16 04:00 PM -1
0001-1.4 PROJECT MILESTONES0001-1.4 PROJECT MILESTONES 381 01-Jul-15 08:00 AM 22-Sep-16 04:00 PM -1
A1810 BEGINNING OF PROJECT CONSTRUCTION 0 01-Jul-15 08:00 AM 380
A1820 1ST FLOOR SLAB DONE 0 21-Dec-15 04:00 PM 232
A1830 2ND FLOOR SLAB DONE 0 08-Feb-16 04:00 PM 194
A1840 ROOF DECK SLAB DONE 0 05-May-16 04:00 PM 119
A1850 END OF PROJECT 0 22-Sep-16 04:00 PM -1
A1970 3RD FLOOR SLAB DONE 0 11-Apr-16 04:00 PM 140
0001-1.1 PRELIMINARY ACTIVITES0001-1.1 PRELIMINARY ACTIVITES 74 01-Jul-15 08:00 AM 24-Sep-15 04:00 PM 17
A1000 PROCESSING OF PERMITS 30 01-Jul-15 08:00 AM 08-Sep-15 04:00 PM -1
A1010 BAR CUTTING AND BENDING 30 21-Aug-15 08:00
AM
24-Sep-15 04:00 PM -1
A1020 FABRICATION OF FORMS 30 21-Aug-15 08:00
AM
24-Sep-15 04:00 PM 17
0001-1.2 PROCUREMENT OF MATERIALS0001-1.2 PROCUREMENT OF MATERIALS 134 03-Jul-15 08:00 AM 07-Dec-15 04:00 PM 164
A1030 PROCUREMENT OF REBARS, STEEL DECK AND FORMS 60 03-Jul-15 08:00 AM 10-Sep-15 04:00 PM -1
A1040 PROCUREMENT OF MASONRY MATERIALS 30 03-Aug-15 08:00
AM
05-Sep-15 04:00 PM 114
A1050 PROCUREMENT OF STEEL WORKS MATERIALS 15 30-Sep-15 08:00
AM
16-Oct-15 04:00 PM 124
A1060 PROCUREMENT AND DELIVERY OF TILES 30 03-Nov-15 08:00
AM
07-Dec-15 04:00 PM 164
A1070 PROCUREMENT OF MEP MATERIALS AND ACESSORIES 15 01-Sep-15 08:00
AM
17-Sep-15 04:00 PM 157
A1080 PROCUREMENT OF DOORS AND JAMBS 20 08-Sep-15 08:00
AM
30-Sep-15 04:00 PM 130
A1090 PROCUREMENT AND DELIVERY OF PAINT MATERIALS 30 01-Oct-15 08:00
AM
05-Nov-15 04:00 PM 181
0001-1.3 CONSTRUCTION0001-1.3 CONSTRUCTION 381 01-Jul-15 08:00 AM 22-Sep-16 04:00 PM -1
0001-1.3.1 GROUND FLOOR0001-1.3.1 GROUND FLOOR 247 01-Jul-15 08:00 AM 19-Apr-16 02:00 PM 133
0001-1.3.1.2 EARTHWORKS0001-1.3.1.2 EARTHWORKS 40 01-Jul-15 08:00 AM 15-Aug-15 04:00 PM 33
A1110 EXCAVATION 30 01-Jul-15 08:00 AM 04-Aug-15 04:00 PM 33
A1370 SITE CLEARING AND DEMOLITION 25 18-Jul-15 08:00 AM 15-Aug-15 04:00 PM 33
0001-1.3.1.1 STRUCTURAL WORKS0001-1.3.1.1 STRUCTURAL WORKS 76 25-Sep-15 08:00
AM
24-Dec-15 04:00 PM 154
A1120 INSTALLATION OF REBARS FOR FOOTINGS, TIE BEAMS AND COLUMNS 15 25-Sep-15 08:00
AM
12-Oct-15 04:00 PM -1
A1130 CONCRETING OF FOOTINGS AND TIE BEAMS 3 13-Oct-15 08:00
AM
15-Oct-15 04:00 PM -1
A1140 INSTALLATION OF FORMS AND SCAFFOLDINGS FOR COLUMNS 5 16-Oct-15 08:00
AM
21-Oct-15 04:00 PM -1
A1150 CONCRETING OF COLUMN 10 22-Oct-15 08:00
AM
03-Nov-15 04:00 PM -1
A1160 REMOVAL OF FORMS AND SCAFFOLDING FOR COLUMN,BEAMS AND SLAB AT GROUND FLOOR LEVEL3 06-Nov-15 08:00
AM
09-Nov-15 04:00 PM -1
A1170 BACKFILLING 14 10-Nov-15 08:00
AM
25-Nov-15 04:00 PM -1
A1180 PREPARATION OF GROUND SURFACE FOR GROUND SLAB 5 26-Nov-15 08:00
AM
01-Dec-15 04:00 PM -1
A1190 CONCRETING OF GROUND SLAB 2 02-Dec-15 08:00
AM
03-Dec-15 04:00 PM -1
A1460 CONTRUCTION OF STAIRS FROM GROUND FLOOR TO 1ST LEVEL 15 04-Dec-15 08:00
AM
24-Dec-15 04:00 PM 131
0001-1.3.1.3 ARCHITECTURAL WORKS0001-1.3.1.3 ARCHITECTURAL WORKS 136 09-Nov-15 08:00
AM
19-Apr-16 02:00 PM 133
A1200 MASONRY WORKS AT GROUND FLOOR LEVEL 45 07-Dec-15 08:00
AM
01-Feb-16 04:00 PM 27
A1210 INSTALLATION OF DOORS AND JAMBS AT GROUND FLOOR 15 04-Feb-16 08:00
AM
20-Feb-16 04:00 PM 27
A1220 INSTALLATION OF WINDOWS AND GATES 15 13-Feb-16 08:00
AM
01-Mar-16 04:00 PM 27
A1230 CARPENTRY WORKS AT GROUND FLOOR 20 25-Feb-16 08:00
AM
18-Mar-16 04:00 PM 27
A1240 CONTRUCTION OF LEDGE AT GROUND FLOOR 15 02-Mar-16 08:00
AM
18-Mar-16 04:00 PM 160
A1360 PAINTINGS AT GROUND FLOOR 30 09-Nov-15 08:00
AM
12-Dec-15 04:00 PM 164
A1250 TILE WORKS AT GROUND FLOOR 30 14-Mar-16 08:00
AM
19-Apr-16 02:00 PM 26
0001-1.3.1.4 MEP WORKS0001-1.3.1.4 MEP WORKS 113 18-Sep-15 08:00
AM
02-Feb-16 04:00 PM 195
A1260 MEP ROUGHINS INSTALLATIONS ON STRUCTURAL CONCRETE AT GROUND FLOOR5 18-Sep-15 08:00
AM
23-Sep-15 04:00 PM 157
A1270 MEP ROUGHINS INSTALLATIONS ON MASONRY WALLS AT GROUND FLOOR5 21-Jan-16 08:00
AM
26-Jan-16 04:00 PM 195
A1280 CABLE PULLING AND FINISHES FOR ELECTRICAL AT GROUND FLOOR 2 24-Sep-15 08:00
AM
25-Sep-15 04:00 PM 281
A1290 LEAK TEST FOR DRAINAGE AT GROUND FLOOR 2 27-Jan-16 08:00
AM
28-Jan-16 04:00 PM 195
A1480 PRESSURE TEST FOR WATER SUPPLY LINES AT GROUND FLOOR 2 27-Jan-16 08:00
AM
28-Jan-16 04:00 PM 195
A1490 INSTALLATION OF PLUMBING ACCESSORIES AT GROUND FLOOR 4 29-Jan-16 08:00
AM
02-Feb-16 04:00 PM 195
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
2015 2016
22-Sep-16 04:00 PM, 0001-1 C
22-Sep-16 04:00 PM, 0001-1.4
BEGINNING OF PROJECT CONSTRUCTION, 01-Jul-15 08:00 AM
1ST FLOOR SLAB DONE,
2ND FLOOR SLAB DONE,
ROOF DECK SLAB DONE,
END OF PROJECT,
3RD FLOOR SLAB DONE,
24-Sep-15 04:00 PM, 0001-1.1 PRELIMINARY ACTIVITES
PROCESSING OF PERMITS
BAR CUTTING AND BENDING
FABRICATION OF FORMS
07-Dec-15 04:00 PM, 0001-1.2 PROCUREMENT OF MATERIALS
PROCUREMENT OF REBARS, STEEL DECK AND FORMS
PROCUREMENT OF MASONRY MATERIALS
PROCUREMENT OF STEEL WORKS MATERIALS
PROCUREMENT AND DELIVERY OF TILES
PROCUREMENT OF MEP MATERIALS AND ACESSORIES
PROCUREMENT OF DOORS AND JAMBS
PROCUREMENT AND DELIVERY OF PAINT MATERIALS
22-Sep-16 04:00 PM, 0001-1.3
19-Apr-16 02:00 PM, 0001-1.3.1 GROUND FLOOR
15-Aug-15 04:00 PM, 0001-1.3.1.2 EARTHWORKS
EXCAVATION
SITE CLEARING AND DEMOLITION
24-Dec-15 04:00 PM, 0001-1.3.1.1 STRUCTURAL WORKS
INSTALLATION OF REBARS FOR FOOTINGS, TIE BEAMS AND COLUMNS
CONCRETING OF FOOTINGS AND TIE BEAMS
INSTALLATION OF FORMS AND SCAFFOLDINGS FOR COLUMNS
CONCRETING OF COLUMN
REMOVAL OF FORMS AND SCAFFOLDING FOR COLUMN,BEAMS AND SLAB AT GROUND FLOOR LEVEL
BACKFILLING
PREPARATION OF GROUND SURFACE FOR GROUND SLAB
CONCRETING OF GROUND SLAB
CONTRUCTION OF STAIRS FROM GROUND FLOOR TO 1ST LEVEL
19-Apr-16 02:00 PM, 0001-1.3.1.3 ARCHITECTURAL WORKS
MASONRY WORKS AT GROUND FLOOR LEVEL
INSTALLATION OF DOORS AND JAMBS AT GROUND FLOOR
INSTALLATION OF WINDOWS AND GATES
CARPENTRY WORKS AT GROUND FLOOR
CONTRUCTION OF LEDGE AT GROUND FLOOR
PAINTINGS AT GROUND FLOOR
TILE WORKS AT GROUND FLOOR
02-Feb-16 04:00 PM, 0001-1.3.1.4 MEP WORKS
MEP ROUGHINS INSTALLATIONS ON STRUCTURAL CONCRETE AT GROUND FLOOR
MEP ROUGHINS INSTALLATIONS ON MASONRY WALLS AT GROUND FLOOR
CABLE PULLING AND FINISHES FOR ELECTRICAL AT GROUND FLOOR
LEAK TEST FOR DRAINAGE AT GROUND FLOOR
PRESSURE TEST FOR WATER SUPPLY LINES AT GROUND FLOOR
INSTALLATION OF PLUMBING ACCESSORIES AT GROUND FLOOR
CONSTRUCTION OF LEYTE COLLEGES SCHOOL BUILDING
Baseline Programme ( Rev 02 )
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
summary
CONSTRUCTION OF LEYTE COLLEGES SCHOOL BUILDING
Baseline Programme ( Revision 02 )
Date Revision Checked Approved
07-Jun-15 Baseline Programme ( Rev 02 )
1of3
2. Activity ID Activity Name Original
Duration
Early Start Early Finish Total
Float
0001-1.3.2 1ST FLOOR LEVEL0001-1.3.2 1ST FLOOR LEVEL 174 04-Dec-15 08:00
AM
28-Jun-16 02:00 PM 73
0001-1.3.2.1 STRUCTURAL WORKS0001-1.3.2.1 STRUCTURAL WORKS 45 04-Dec-15 08:00
AM
29-Jan-16 04:00 PM 142
A1300 INSTALLATIONS OF FORMS AND SCAFFOLDINGS FOR BEAMS AND SLABS - 1ST FLOOR LEVEL7 04-Dec-15 08:00
AM
11-Dec-15 04:00 PM -1
A1310 INSTALLATIONS OF REBARS , STEEL DECK FOR BEAMS AND SLABS 1ST FLOOR LEVEL5 12-Dec-15 08:00
AM
17-Dec-15 04:00 PM -1
A1320 CONCRETING OF 1ST FLOOR BEAMS AND SLABS 1ST FLOOR LEVEL 3 18-Dec-15 08:00
AM
21-Dec-15 04:00 PM -1
A1330 INSTALLATION OF REBARS FOR COLUMNS 1ST FLOOR LEVEL 5 22-Dec-15 08:00
AM
29-Dec-15 04:00 PM 24
A1340 INSTALLATION OF FORMS AND SCAFFOLDINGS FOR COLUMNS 1ST FLOOR LEVEL5 22-Dec-15 08:00
AM
29-Dec-15 04:00 PM -1
A1350 CONCRETING OF COLUMNS 1ST FLOOR LEVEL 3 30-Dec-15 08:00
AM
04-Jan-16 04:00 PM -1
A1420 REMOVAL OF FORM FOR COLUMNS,BEAMS AND SLAB 1ST FLOOR 5 07-Jan-16 08:00
AM
12-Jan-16 04:00 PM -1
A1470 WATERPROOFING AND LEAK TESTING OF WET AREAS -1ST FLOOR 3 13-Jan-16 08:00
AM
15-Jan-16 04:00 PM 109
A1650 CONSTRUCTION OF STAIRS FROM 1ST TO 2ND FLOOR 15 13-Jan-16 08:00
AM
29-Jan-16 04:00 PM 142
0001-1.3.2.2 ARCHITECTURAL WORKS0001-1.3.2.2 ARCHITECTURAL WORKS 127 02-Feb-16 08:00
AM
28-Jun-16 02:00 PM 28
A1380 MASONRY WORKS 1ST FLOOR 45 02-Feb-16 08:00
AM
24-Mar-16 04:00 PM 50
A1390 INSTALLATION OF DOORS AND JAMBS 1ST FLOOR 15 25-Mar-16 08:00
AM
11-Apr-16 04:00 PM 65
A1400 INSTALLATION OF WINDOWS 1ST FLOOR 15 25-Mar-16 08:00
AM
11-Apr-16 04:00 PM 65
A1410 CARPENTRY WORKS 1ST FLOOR 20 25-Mar-16 08:00
AM
16-Apr-16 04:00 PM 60
A1430 TILE WORKS 1ST FLOOR 30 19-Apr-16 02:00
PM
24-May-16 02:00 PM 28
A1440 CONSTRUCTION OF LEDGE 1ST FLOOR 15 25-Mar-16 08:00
AM
11-Apr-16 04:00 PM 65
A1450 PAINTING WORKS 1ST FLOOR 30 24-May-16 02:00
PM
28-Jun-16 02:00 PM 28
0001-1.3.2.3 MEP WORKS0001-1.3.2.3 MEP WORKS 87 12-Dec-15 08:00
AM
26-Mar-16 04:00 PM 153
A1500 MEP ROUGHINS INSTALLATIONS ON STRUCTURAL CONCRETE 1ST FLOOR5 12-Dec-15 08:00
AM
17-Dec-15 04:00 PM 211
A1510 MEP ROUGHINS INSTALLATIONS ON MASONRY WALLS 1ST FLOOR 5 14-Mar-16 08:00
AM
18-Mar-16 04:00 PM 136
A1520 CABLE PULLING AND FINISHES FOR ELECTRICAL 1ST FLOOR 2 19-Mar-16 08:00
AM
21-Mar-16 04:00 PM 136
A1530 LEAK TESTS FOR DRAINAGE 1ST FLOOR 3 19-Mar-16 08:00
AM
22-Mar-16 04:00 PM 153
A1540 PRESSURE TESTS FOR WATERLINE 1ST FLOOR 3 19-Mar-16 08:00
AM
22-Mar-16 04:00 PM 153
A1630 INSTALLATION OF PLUMBING ACCESSORIES 1ST FLOOR 4 23-Mar-16 08:00
AM
26-Mar-16 04:00 PM 153
0001-1.3.3 2ND FLOOR LEVEL0001-1.3.3 2ND FLOOR LEVEL 174 13-Jan-16 08:00
AM
02-Aug-16 02:00 PM 28
0001-1.3.3.1 STRUCTURAL WORKS0001-1.3.3.1 STRUCTURAL WORKS 60 13-Jan-16 08:00
AM
22-Mar-16 04:00 PM 112
A1550 INSTALLATIONS OF FORMS AND SCAFFOLDINGS FOR BEAMS AND SLABS 2ND FLOOR15 13-Jan-16 08:00
AM
29-Jan-16 04:00 PM -1
A1560 INSTALLATIONS OF REBARS, STEEL DECK FOR BEAMS AND SLABS 2ND FLOOR5 30-Jan-16 08:00
AM
04-Feb-16 04:00 PM -1
A1570 CONCRETING OF 2ND FLOOR BEAMS AND SLABS 2ND FLOOR 3 05-Feb-16 08:00
AM
08-Feb-16 04:00 PM -1
A1580 INSTALLATION OF FORMS AND SCAFFOLDINGS FOR 2ND FLOOR COLUMNS 2ND FLOOR5 11-Feb-16 08:00
AM
16-Feb-16 04:00 PM -1
A1590 CONCRETING OF 2ND FLOOR COLUMNS 2ND FLOOR 3 19-Feb-16 08:00
AM
22-Feb-16 04:00 PM -1
A1600 REMOVAL OF FORMS AND SCAFFOLDINGS COLUMN, BEAMS AND SLAB 2ND FLOOR5 25-Feb-16 08:00
AM
01-Mar-16 04:00 PM -1
A1610 CONSTRUCTION OF STAIRS 2ND TO 3RD FLOOR LEVEL 15 05-Mar-16 08:00
AM
22-Mar-16 04:00 PM 112
A1620 WATERPROOFING AND LEAK TESTING OF WET AREAS 2ND FLOOR 3 12-Feb-16 08:00
AM
15-Feb-16 04:00 PM 83
0001-1.3.3.2 ARCHITECTURAL WORKS0001-1.3.3.2 ARCHITECTURAL WORKS 138 24-Feb-16 08:00
AM
02-Aug-16 02:00 PM 28
A1700 MASONRY WORKS 2ND FLOOR 45 24-Feb-16 08:00
AM
15-Apr-16 04:00 PM 11
A1710 INSTALLATION OF DOORS AND JAMBS 2ND FLOOR 15 16-Apr-16 08:00 AM 03-May-16 04:00 PM 76
A1720 INSTALLATION OF WINDOWS 2ND FLOOR 15 16-Apr-16 08:00 AM 03-May-16 04:00 PM 76
A1730 CARPENTRY WORKS 2ND FLOOR 20 16-Apr-16 08:00 AM 09-May-16 04:00 PM 11
A1740 TILE WORKS 2ND FLOOR 30 10-May-16 08:00
AM
13-Jun-16 04:00 PM 11
A1750 CONSTRUCTION OF LEDGE 2ND FLOOR 15 10-May-16 08:00
AM
26-May-16 04:00 PM 56
A1760 PAINTING WORKS 2ND FLOOR 30 28-Jun-16 02:00
PM
02-Aug-16 02:00 PM 28
0001-1.3.3.3 MEP WORKS0001-1.3.3.3 MEP WORKS 73 19-Jan-16 08:00
AM
12-Apr-16 04:00 PM 119
A1870 MEP ROUGHINS INSTALLATIONS ON STRUCTURAL CONCRETE 2ND FLOOR5 19-Jan-16 08:00
AM
23-Jan-16 04:00 PM 185
A1880 MEP ROUGHINS INSTALLATIONS ON MASONRY WALLS 2ND FLOOR 5 05-Apr-16 08:00 AM 09-Apr-16 04:00 PM 119
A1890 CABLE PULLING AND FINISHES FOR ELECTRICAL 2ND FLOOR 2 11-Apr-16 08:00 AM 12-Apr-16 04:00 PM 119
A1900 LEAK TESTS FOR DRAINAGE 2ND FLOOR 3 09-Feb-16 08:00
AM
11-Feb-16 04:00 PM 136
A1910 PRESSURE TESTS FOR WATERLINE 2ND FLOOR 3 09-Feb-16 08:00
AM
11-Feb-16 04:00 PM 136
A1920 INSTALLATION OF PLUMBING ACCESSORIES 2ND FLOOR 5 12-Feb-16 08:00
AM
17-Feb-16 04:00 PM 136
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
2015 2016
28-Jun-16 02:00 PM, 0001-1.3.2 1ST FLOOR LEVEL
29-Jan-16 04:00 PM, 0001-1.3.2.1 STRUCTURAL WORKS
INSTALLATIONS OF FORMS AND SCAFFOLDINGS FOR BEAMS AND SLABS - 1ST FLOOR LEVEL
INSTALLATIONS OF REBARS , STEEL DECK FOR BEAMS AND SLABS 1ST FLOOR LEVEL
CONCRETING OF 1ST FLOOR BEAMS AND SLABS 1ST FLOOR LEVEL
INSTALLATION OF REBARS FOR COLUMNS 1ST FLOOR LEVEL
INSTALLATION OF FORMS AND SCAFFOLDINGS FOR COLUMNS 1ST FLOOR LEVEL
CONCRETING OF COLUMNS 1ST FLOOR LEVEL
REMOVAL OF FORM FOR COLUMNS,BEAMS AND SLAB 1ST FLOOR
WATERPROOFING AND LEAK TESTING OF WET AREAS -1ST FLOOR
CONSTRUCTION OF STAIRS FROM 1ST TO 2ND FLOOR
28-Jun-16 02:00 PM, 0001-1.3.2.2 ARCHITECTURAL WO
MASONRY WORKS 1ST FLOOR
INSTALLATION OF DOORS AND JAMBS 1ST FLOOR
INSTALLATION OF WINDOWS 1ST FLOOR
CARPENTRY WORKS 1ST FLOOR
TILE WORKS 1ST FLOOR
CONSTRUCTION OF LEDGE 1ST FLOOR
PAINTING WORKS 1ST FLOOR
26-Mar-16 04:00 PM, 0001-1.3.2.3 MEP WORKS
MEP ROUGHINS INSTALLATIONS ON STRUCTURAL CONCRETE 1ST FLOOR
MEP ROUGHINS INSTALLATIONS ON MASONRY WALLS 1ST FLOOR
CABLE PULLING AND FINISHES FOR ELECTRICAL 1ST FLOOR
LEAK TESTS FOR DRAINAGE 1ST FLOOR
PRESSURE TESTS FOR WATERLINE 1ST FLOOR
INSTALLATION OF PLUMBING ACCESSORIES 1ST FLOOR
02-Aug-16 02:00 PM, 0001-1.3.3 2ND FLOOR
22-Mar-16 04:00 PM, 0001-1.3.3.1 STRUCTURAL WORKS
INSTALLATIONS OF FORMS AND SCAFFOLDINGS FOR BEAMS AND SLABS 2ND FLOOR
INSTALLATIONS OF REBARS, STEEL DECK FOR BEAMS AND SLABS 2ND FLOOR
CONCRETING OF 2ND FLOOR BEAMS AND SLABS 2ND FLOOR
INSTALLATION OF FORMS AND SCAFFOLDINGS FOR 2ND FLOOR COLUMNS 2ND FLOOR
CONCRETING OF 2ND FLOOR COLUMNS 2ND FLOOR
REMOVAL OF FORMS AND SCAFFOLDINGS COLUMN, BEAMS AND SLAB 2ND FLOOR
CONSTRUCTION OF STAIRS 2ND TO 3RD FLOOR LEVEL
WATERPROOFING AND LEAK TESTING OF WET AREAS 2ND FLOOR
02-Aug-16 02:00 PM, 0001-1.3.3.2 ARCHITECT
MASONRY WORKS 2ND FLOOR
INSTALLATION OF DOORS AND JAMBS 2ND FLOOR
INSTALLATION OF WINDOWS 2ND FLOOR
CARPENTRY WORKS 2ND FLOOR
TILE WORKS 2ND FLOOR
CONSTRUCTION OF LEDGE 2ND FLOOR
PAINTING WORKS 2ND FLOOR
12-Apr-16 04:00 PM, 0001-1.3.3.3 MEP WORKS
MEP ROUGHINS INSTALLATIONS ON STRUCTURAL CONCRETE 2ND FLOOR
MEP ROUGHINS INSTALLATIONS ON MASONRY WALLS 2ND FLOOR
CABLE PULLING AND FINISHES FOR ELECTRICAL 2ND FLOOR
LEAK TESTS FOR DRAINAGE 2ND FLOOR
PRESSURE TESTS FOR WATERLINE 2ND FLOOR
INSTALLATION OF PLUMBING ACCESSORIES 2ND FLOOR
CONSTRUCTION OF LEYTE COLLEGES SCHOOL BUILDING
Baseline Programme ( Rev 02 )
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
summary
CONSTRUCTION OF LEYTE COLLEGES SCHOOL BUILDING
Baseline Programme ( Revision 02 )
Date Revision Checked Approved
07-Jun-15 Baseline Programme ( Rev 02 )
2of3
3. Activity ID Activity Name Original
Duration
Early Start Early Finish Total
Float
0001-1.3.6 3RD FLOOR LEVEL0001-1.3.6 3RD FLOOR LEVEL 131 02-Mar-16 08:00
AM
01-Aug-16 04:00 PM 29
0001-1.3.6.1 STRUCTURAL WORKS0001-1.3.6.1 STRUCTURAL WORKS 60 02-Mar-16 08:00
AM
10-May-16 04:00 PM 70
A2350 INSTALLATIONS OF FORMS AND SCAFFOLDINGS FOR BEAMS AND SLABS 3RD FLOOR15 02-Mar-16 08:00
AM
18-Mar-16 04:00 PM -1
A2360 INSTALLATIONS OF REBARS, STEEL DECK FOR BEAMS AND SLABS 3RD FLOOR5 19-Mar-16 08:00
AM
24-Mar-16 04:00 PM -1
A2370 CONCRETING OF 3RD FLOOR BEAMS AND SLABS 3 25-Mar-16 08:00
AM
28-Mar-16 04:00 PM -1
A2380 INSTALLATION OF FORMS AND SCAFFOLDINGS FOR 3RD FLOOR COLUMNS5 31-Mar-16 08:00
AM
05-Apr-16 04:00 PM -1
A2390 CONCRETING OF 3RD FLOOR COLUMNS 3 08-Apr-16 08:00 AM 11-Apr-16 04:00 PM -1
A2400 REMOVAL OF FORMS AND SCAFFOLDINGS COLUMN, BEAMS AND SLAB- 3RD FLOOR5 14-Apr-16 08:00 AM 19-Apr-16 04:00 PM 26
A2410 CONSTRUCTION OF STAIRS 3RD TO ROOF DECK 15 23-Apr-16 08:00 AM 10-May-16 04:00 PM 70
A2420 WATERPROOFING AND LEAK TESTING OF WET AREAS - 3RD FLOOR 3 01-Apr-16 08:00 AM 04-Apr-16 04:00 PM 71
0001-1.3.6.2 ARCHITECTURAL WORKS0001-1.3.6.2 ARCHITECTURAL WORKS 95 13-Apr-16 08:00 AM 01-Aug-16 04:00 PM 29
A2430 MASONRY WORKS - 3RD FLOOR 45 13-Apr-16 08:00 AM 03-Jun-16 04:00 PM -1
A2440 INSTALLATION OF DOORS AND JAMBS - 3RD FLOOR 15 04-Jun-16 08:00
AM
21-Jun-16 04:00 PM 34
A2450 INSTALLATION OF WINDOWS - 3RD FLOOR 15 04-Jun-16 08:00
AM
21-Jun-16 04:00 PM 34
A2460 CARPENTRY WORKS - 3RD FLOOR 20 04-Jun-16 08:00
AM
27-Jun-16 04:00 PM -1
A2470 TILE WORKS - 3RD FLOOR 30 28-Jun-16 08:00
AM
01-Aug-16 04:00 PM -1
A2480 CONSTRUCTION OF LEDGE - 3RD FLOOR 15 28-Jun-16 08:00
AM
14-Jul-16 04:00 PM 29
A2490 PAINTING WORKS - 3RD FLOOR 30 28-Jun-16 08:00
AM
01-Aug-16 04:00 PM 29
0001-1.3.6.3 MEP WORKS0001-1.3.6.3 MEP WORKS 73 08-Mar-16 08:00
AM
31-May-16 04:00 PM 79
A2500 MEP ROUGHINS INSTALLATIONS ON STRUCTURAL CONCRETE - 3RD FLOOR5 08-Mar-16 08:00
AM
12-Mar-16 04:00 PM 145
A2510 MEP ROUGHINS INSTALLATIONS ON MASONRY WALLS - 3RD FLOOR 5 24-May-16 08:00
AM
28-May-16 04:00 PM 79
A2520 CABLE PULLING AND FINISHES FOR ELECTRICAL - 3RD FLOOR 2 30-May-16 08:00
AM
31-May-16 04:00 PM 79
A2530 LEAK TESTS FOR DRAINAGE - 3RD FLOOR 3 29-Mar-16 08:00
AM
31-Mar-16 04:00 PM 99
A2540 PRESSURE TESTS FOR WATERLINE - 3RD FLOOR 3 29-Mar-16 08:00
AM
31-Mar-16 04:00 PM 99
A2550 INSTALLATION OF PLUMBING ACCESSORIES - 3RD FLOOR 5 01-Apr-16 08:00 AM 06-Apr-16 04:00 PM 99
0001-1.3.4 ROOF DECK LEVEL0001-1.3.4 ROOF DECK LEVEL 134 20-Apr-16 08:00 AM 22-Sep-16 04:00 PM -1
0001-1.3.4.1 STRUCTURAL WORKS0001-1.3.4.1 STRUCTURAL WORKS 22 20-Apr-16 08:00 AM 14-May-16 04:00 PM 96
A1770 INSTALLATION OF FORMS AND SCAFFOLDINGS FOR BEAMS AND SLAB - ROOF DECK LEVEL15 20-Apr-16 08:00 AM 06-May-16 04:00 PM 26
A1780 INSTALLATION OF REBARS FOR BEAMS AND SLABS - ROOF DECK LEVEL 5 26-Apr-16 08:00 AM 30-Apr-16 04:00 PM 26
A1790 CONCRETING OF ROOF DECK BEAMS AND SLABS - ROOF DECK LEVEL 3 03-May-16 08:00
AM
05-May-16 04:00 PM 26
A1800 REMOVAL OF FORMS AND SCAFFOLDINGS - ROOF DECK LEVEL 5 06-May-16 08:00
AM
11-May-16 04:00 PM 96
A1860 WATERPROOFING AND LEAK TEST OF ROOF DECK SLAB - ROOF DECK LEVEL3 12-May-16 08:00
AM
14-May-16 04:00 PM 96
0001-1.3.4.2 ARCHITECTURAL WORKS0001-1.3.4.2 ARCHITECTURAL WORKS 117 10-May-16 08:00
AM
22-Sep-16 04:00 PM -1
A1930 MASONRY WORKS 45 10-May-16 08:00
AM
30-Jun-16 04:00 PM 26
A1940 TILE WORKS 30 02-Aug-16 08:00
AM
05-Sep-16 04:00 PM -1
A1950 CONSTRUCTION OF LEDGE 15 15-Jul-16 08:00 AM 01-Aug-16 04:00 PM 29
A1960 PAINTING WORKS 15 06-Sep-16 08:00
AM
22-Sep-16 04:00 PM -1
0001-1.3.4.3 MEP0001-1.3.4.3 MEP 55 07-May-16 08:00
AM
09-Jul-16 04:00 PM 48
A1980 MEP ROUGHINS INSTALLATIONS ON STRUCTURAL CONCRETE 5 07-May-16 08:00
AM
12-May-16 04:00 PM 95
A1990 MEP ROUGHINS INSTALLATIONS ON MASONRY WALLS 5 01-Jul-16 08:00 AM 06-Jul-16 04:00 PM 48
A2000 CABLE PULLING FOR MEP 3 07-Jul-16 08:00 AM 09-Jul-16 04:00 PM 48
A2010 LEAK TEST FOR DRAINAGE 3 07-Jul-16 08:00 AM 09-Jul-16 04:00 PM 48
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
2015 2016
01-Aug-16 04:00 PM, 0001-1.3.6 3RD FLOOR
10-May-16 04:00 PM, 0001-1.3.6.1 STRUCTURAL WORKS
INSTALLATIONS OF FORMS AND SCAFFOLDINGS FOR BEAMS AND SLABS 3RD FLOO
INSTALLATIONS OF REBARS, STEEL DECK FOR BEAMS AND SLABS 3RD FLOOR
CONCRETING OF 3RD FLOOR BEAMS AND SLABS
INSTALLATION OF FORMS AND SCAFFOLDINGS FOR 3RD FLOOR COLUMNS
CONCRETING OF 3RD FLOOR COLUMNS
REMOVAL OF FORMS AND SCAFFOLDINGS COLUMN, BEAMS AND SLAB- 3R
CONSTRUCTION OF STAIRS 3RD TO ROOF DECK
WATERPROOFING AND LEAK TESTING OF WET AREAS - 3RD FLOOR
01-Aug-16 04:00 PM, 0001-1.3.6.2 ARCHITECT
MASONRY WORKS - 3RD FLOOR
INSTALLATION OF DOORS AND JAMBS - 3RD FLOOR
INSTALLATION OF WINDOWS - 3RD FLOOR
CARPENTRY WORKS - 3RD FLOOR
TILE WORKS - 3RD FLOOR
CONSTRUCTION OF LEDGE - 3RD FLOOR
PAINTING WORKS - 3RD FLOOR
31-May-16 04:00 PM, 0001-1.3.6.3 MEP WORKS
MEP ROUGHINS INSTALLATIONS ON STRUCTURAL CONCRETE - 3RD FLOOR
MEP ROUGHINS INSTALLATIONS ON MASONRY WALLS - 3RD F
CABLE PULLING AND FINISHES FOR ELECTRICAL - 3RD FLOO
LEAK TESTS FOR DRAINAGE - 3RD FLOOR
PRESSURE TESTS FOR WATERLINE - 3RD FLOOR
INSTALLATION OF PLUMBING ACCESSORIES - 3RD FLOOR
22-Sep-16 04:00 PM, 0001-1.3.
14-May-16 04:00 PM, 0001-1.3.4.1 STRUCTURAL WORKS
INSTALLATION OF FORMS AND SCAFFOLDINGS FOR BEAMS AND SLA
INSTALLATION OF REBARS FOR BEAMS AND SLABS - ROOF DECK LEVE
CONCRETING OF ROOF DECK BEAMS AND SLABS - ROOF DECK LEVE
REMOVAL OF FORMS AND SCAFFOLDINGS - ROOF DECK LEVEL
WATERPROOFING AND LEAK TEST OF ROOF DECK SLAB - ROOF D
22-Sep-16 04:00 PM, 0001-1.3.
MASONRY WORKS
TILE WORKS
CONSTRUCTION OF LEDGE
PAINTING WORKS
09-Jul-16 04:00 PM, 0001-1.3.4.3 MEP
MEP ROUGHINS INSTALLATIONS ON STRUCTURAL CONCRETE
MEP ROUGHINS INSTALLATIONS ON MASONRY WA
CABLE PULLING FOR MEP
LEAK TEST FOR DRAINAGE
CONSTRUCTION OF LEYTE COLLEGES SCHOOL BUILDING
Baseline Programme ( Rev 02 )
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
summary
CONSTRUCTION OF LEYTE COLLEGES SCHOOL BUILDING
Baseline Programme ( Revision 02 )
Date Revision Checked Approved
07-Jun-15 Baseline Programme ( Rev 02 )
3of3