SlideShare a Scribd company logo
1 of 39
Download to read offline
CE 561
Construction Project Management
Small Residential Building Project
FALL - 2016
ABHISHEK KUMAR SINGH
200116822
Table of Contents
SL No. Report Name
1 Grouped by Project and Sorted by Activity ID
2 Gantt Chart for activities grouped by WBS and Sorted by Activity ID
3 Activity Network Layout of the Project
4 Activity Table & Gantt Chart Schedule for Critical Activities
5 Gantt Chart Schedule for Critical Activities
6 Gantt Chart Schedule for activities Sorted by Early Start & Free Float
7 Report for Budgeted Cost
8 Daily Histogram and cumulative curve for Labor cost
9 Daily Histogram and cumulative curve for Material Cost
10 Monthly Histogram and Cumulative curve for Total Cost
11 Updated Schedule Report and Gantt Chart Table
Grouped by WBS and Sorted by Activity ID
WBS
Activity ID Activity Name Predecessors Original
Duration
Early
Start
Early
Finish
Late Start Late
Finish
Total Float Free Float
R
R.1
A1000 Finalize Plans & Develop
estimate with owner, architect
20.00 01-Nov-16
08:00 AM
23-Nov-16
05:00 PM
01-Nov-16
08:00 AM
23-Nov-16
05:00 PM
0.00 0.00
A1010 Sign Contract & Notice to
proceed
A1000 1.00 24-Nov-16
08:00 AM
24-Nov-16
05:00 PM
24-Nov-16
08:00 AM
24-Nov-16
05:00 PM
0.00 0.00
R.1.1
A1110 Secure Foundation Permit A1010 1.00 25-Nov-16
08:00 AM
25-Nov-16
05:00 PM
25-Nov-16
08:00 AM
25-Nov-16
05:00 PM
0.00 0.00
A1120 Secure Framing Permit A1010 1.00 25-Nov-16
08:00 AM
25-Nov-16
05:00 PM
25-Nov-16
08:00 AM
25-Nov-16
05:00 PM
0.00 0.00
A1130 Secure Electrical Permit A1010 1.00 25-Nov-16
08:00 AM
25-Nov-16
05:00 PM
25-Nov-16
08:00 AM
25-Nov-16
05:00 PM
0.00 0.00
A1140 Secure Plumbing Permit A1010 1.00 25-Nov-16
08:00 AM
25-Nov-16
05:00 PM
25-Nov-16
08:00 AM
25-Nov-16
05:00 PM
0.00 0.00
A1150 Secure HVAC Permit A1010 1.00 25-Nov-16
08:00 AM
25-Nov-16
05:00 PM
25-Nov-16
08:00 AM
25-Nov-16
05:00 PM
0.00 0.00
A1160 Secure miscellaneous permits A1010 1.00 25-Nov-16
08:00 AM
25-Nov-16
05:00 PM
25-Nov-16
08:00 AM
25-Nov-16
05:00 PM
0.00 0.00
Subtotal 1.00 25-Nov-16
08:00 AM
25-Nov-16
05:00 PM
25-Nov-16
08:00 AM
25-Nov-16
05:00 PM
0.00 0.00
Subtotal 22.00 01-Nov-16
08:00 AM
25-Nov-16
05:00 PM
01-Nov-16
08:00 AM
25-Nov-16
05:00 PM
0.00 0.00
R.S
A1020 Clear and grub lot A1110,
A1120,
A1130,
A1140,
A1150,
1.00 26-Nov-16
08:00 AM
26-Nov-16
05:00 PM
26-Nov-16
08:00 AM
26-Nov-16
05:00 PM
0.00 0.00
Abhishek Singh
© Oracle Corporation Page 1 of 9
Grouped by WBS and Sorted by Activity ID
WBS
Activity ID Activity Name Predecessors Original
Duration
Early
Start
Early
Finish
Late Start Late
Finish
Total Float Free Float
A1030 Install temporary power service A1020 1.00 28-Nov-16
08:00 AM
28-Nov-16
05:00 PM
28-Nov-16
08:00 AM
28-Nov-16
05:00 PM
0.00 0.00
A1040 Install underground utilities A1030 1.00 29-Nov-16
08:00 AM
29-Nov-16
05:00 PM
29-Nov-16
08:00 AM
29-Nov-16
05:00 PM
0.00 0.00
Subtotal 3.00 26-Nov-16
08:00 AM
29-Nov-16
05:00 PM
26-Nov-16
08:00 AM
29-Nov-16
05:00 PM
0.00 0.00
R.2
A1170 Excavate for foundations A1040 3.00 30-Nov-16
08:00 AM
02-Dec-16
05:00 PM
30-Nov-16
08:00 AM
02-Dec-16
05:00 PM
0.00 0.00
A1180 Form basement walls A1170 13.00 03-Dec-16
08:00 AM
17-Dec-16
05:00 PM
03-Dec-16
08:00 AM
17-Dec-16
05:00 PM
0.00 0.00
A1190 Place concrete for foundations &
basement walls
A1180 12.00 19-Dec-16
08:00 AM
31-Dec-16
05:00 PM
19-Dec-16
08:00 AM
31-Dec-16
05:00 PM
0.00 0.00
A1200 Cure basement walls for 7 days A1190 7.00 02-Jan-17
08:00 AM
09-Jan-17
05:00 PM
02-Jan-17
08:00 AM
09-Jan-17
05:00 PM
0.00 0.00
A1210 Strip basement wall forms A1200 2.00 10-Jan-17
08:00 AM
11-Jan-17
05:00 PM
10-Jan-17
08:00 AM
11-Jan-17
05:00 PM
0.00 0.00
A1220 Waterproof / insulate bsement
walls
A1210 2.00 12-Jan-17
08:00 AM
13-Jan-17
05:00 PM
12-Jan-17
08:00 AM
13-Jan-17
05:00 PM
0.00 0.00
A1230 Perform foundation inspection A1170,
A1220
1.00 14-Jan-17
08:00 AM
14-Jan-17
05:00 PM
14-Jan-17
08:00 AM
14-Jan-17
05:00 PM
0.00 0.00
A1240 Backfill foundation A1230 2.00 16-Jan-17
08:00 AM
17-Jan-17
05:00 PM
16-Jan-17
08:00 AM
17-Jan-17
05:00 PM
0.00 0.00
Subtotal 42.00 30-Nov-16
08:00 AM
17-Jan-17
05:00 PM
30-Nov-16
08:00 AM
17-Jan-17
05:00 PM
0.00 0.00
R.3
A1250 Install 1st floor joists A1240 2.00 18-Jan-17
08:00 AM
19-Jan-17
05:00 PM
18-Jan-17
08:00 AM
19-Jan-17
05:00 PM
0.00 0.00
Abhishek Singh
© Oracle Corporation Page 2 of 9
Grouped by WBS and Sorted by Activity ID
WBS
Activity ID Activity Name Predecessors Original
Duration
Early
Start
Early
Finish
Late Start Late
Finish
Total Float Free Float
A1260 Lay 1st floor decking A1250 2.00 20-Jan-17
08:00 AM
21-Jan-17
05:00 PM
20-Jan-17
08:00 AM
21-Jan-17
05:00 PM
0.00 0.00
A1270 Frame 1st floor walls A1260 4.00 23-Jan-17
08:00 AM
26-Jan-17
05:00 PM
23-Jan-17
08:00 AM
26-Jan-17
05:00 PM
0.00 0.00
A1280 Frame 1st floor corners A1270 1.00 27-Jan-17
08:00 AM
27-Jan-17
05:00 PM
27-Jan-17
08:00 AM
27-Jan-17
05:00 PM
0.00 0.00
A1290 Install 2nd floor joist A1280 2.00 28-Jan-17
08:00 AM
30-Jan-17
05:00 PM
28-Jan-17
08:00 AM
30-Jan-17
05:00 PM
0.00 0.00
A1300 Frame 2nd Floor decking A1290 2.00 31-Jan-17
08:00 AM
01-Feb-17
05:00 PM
31-Jan-17
08:00 AM
01-Feb-17
05:00 PM
0.00 0.00
A1310 Frame 2nd floor walls A1300 3.00 02-Feb-17
08:00 AM
04-Feb-17
05:00 PM
02-Feb-17
08:00 AM
04-Feb-17
05:00 PM
0.00 0.00
A1320 Frame 2nd floor corners A1310 2.00 06-Feb-17
08:00 AM
07-Feb-17
05:00 PM
06-Feb-17
08:00 AM
07-Feb-17
05:00 PM
0.00 0.00
A1330 Complete roof framing A1320 3.00 08-Feb-17
08:00 AM
10-Feb-17
05:00 PM
08-Feb-17
08:00 AM
10-Feb-17
05:00 PM
0.00 0.00
A1340 Conduct framing inspection A1330 1.00 11-Feb-17
08:00 AM
11-Feb-17
05:00 PM
11-Feb-17
08:00 AM
11-Feb-17
05:00 PM
0.00 0.00
Subtotal 22.00 18-Jan-17
08:00 AM
11-Feb-17
05:00 PM
18-Jan-17
08:00 AM
11-Feb-17
05:00 PM
0.00 0.00
R.4
A1350 Install 1st Floor Sheathing A1340 3.00 13-Feb-17
08:00 AM
15-Feb-17
05:00 PM
13-Feb-17
08:00 AM
15-Feb-17
05:00 PM
0.00 0.00
A1360 Install 2nd Floor Sheathing A1350 3.00 16-Feb-17
08:00 AM
18-Feb-17
05:00 PM
16-Feb-17
08:00 AM
18-Feb-17
05:00 PM
0.00 0.00
A1370 Install roof decking A1330 3.00 11-Feb-17
08:00 AM
14-Feb-17
05:00 PM
16-Feb-17
08:00 AM
18-Feb-17
05:00 PM
4.00 0.00
A1380 Install felt, flashing, and shingles A1440 3.00 25-Feb-17
08:00 AM
28-Feb-17
05:00 PM
25-Feb-17
08:00 AM
28-Feb-17
05:00 PM
0.00 0.00
A1390 Hang 1st floor exterior doors A1380 1.00 01-Mar-17
08:00 AM
01-Mar-17
05:00 PM
01-Mar-17
08:00 AM
01-Mar-17
05:00 PM
0.00 0.00
Abhishek Singh
© Oracle Corporation Page 3 of 9
Grouped by WBS and Sorted by Activity ID
WBS
Activity ID Activity Name Predecessors Original
Duration
Early
Start
Early
Finish
Late Start Late
Finish
Total Float Free Float
A1400 Install 1st floor windows A1390 3.00 02-Mar-17
08:00 AM
04-Mar-17
05:00 PM
02-Mar-17
08:00 AM
04-Mar-17
05:00 PM
0.00 0.00
A1410 Install 2nd floor windows A1400 3.00 06-Mar-17
08:00 AM
08-Mar-17
05:00 PM
06-Mar-17
08:00 AM
08-Mar-17
05:00 PM
0.00 0.00
Subtotal 22.00 11-Feb-17
08:00 AM
08-Mar-17
05:00 PM
13-Feb-17
08:00 AM
08-Mar-17
05:00 PM
0.00 0.00
R.6
A1420 Complete Exterior Brick A1410 16.00 09-Mar-17
08:00 AM
27-Mar-17
05:00 PM
13-Mar-17
08:00 AM
30-Mar-17
05:00 PM
3.00 0.00
A1430 Complete exterior siding A1420 3.00 28-Mar-17
08:00 AM
30-Mar-17
05:00 PM
31-Mar-17
08:00 AM
03-Apr-17
05:00 PM
3.00 0.00
Subtotal 19.00 09-Mar-17
08:00 AM
30-Mar-17
05:00 PM
13-Mar-17
08:00 AM
03-Apr-17
05:00 PM
3.00 0.00
R.7
A1440 Rough-in-plumbing A1370,
A1360
5.00 20-Feb-17
08:00 AM
24-Feb-17
05:00 PM
20-Feb-17
08:00 AM
24-Feb-17
05:00 PM
0.00 0.00
A1450 Conduct Rough-in-plumbing
inspection
A1440 1.00 25-Feb-17
08:00 AM
25-Feb-17
05:00 PM
18-Mar-17
08:00 AM
18-Mar-17
05:00 PM
18.00 0.00
A1460 Place concrete for basement
floor
A1450 11.00 27-Feb-17
08:00 AM
10-Mar-17
05:00 PM
04-Apr-17
08:00 AM
15-Apr-17
05:00 PM
31.00 31.00
A1470 Rough-in electrical A1370,
A1360
5.00 20-Feb-17
08:00 AM
24-Feb-17
05:00 PM
27-Feb-17
08:00 AM
03-Mar-17
05:00 PM
6.00 0.00
A1480 Conduct Rough-in-electrical
inspection
A1470 1.00 25-Feb-17
08:00 AM
25-Feb-17
05:00 PM
04-Mar-17
08:00 AM
04-Mar-17
05:00 PM
6.00 0.00
A1490 Rough-in HVAC A1480 3.00 27-Feb-17
08:00 AM
01-Mar-17
05:00 PM
06-Mar-17
08:00 AM
08-Mar-17
05:00 PM
6.00 0.00
A1500 Conduct Rough-in-HVAC
inspection
A1490 1.00 02-Mar-17
08:00 AM
02-Mar-17
05:00 PM
28-Mar-17
08:00 AM
28-Mar-17
05:00 PM
22.00 22.00
Abhishek Singh
© Oracle Corporation Page 4 of 9
Grouped by WBS and Sorted by Activity ID
WBS
Activity ID Activity Name Predecessors Original
Duration
Early
Start
Early
Finish
Late Start Late
Finish
Total Float Free Float
A1510 Rough-in communication -
phone, cables, computer, alarm
A1370 2.00 15-Feb-17
08:00 AM
16-Feb-17
05:00 PM
07-Mar-17
08:00 AM
08-Mar-17
05:00 PM
17.00 17.00
Subtotal 21.00 15-Feb-17
08:00 AM
10-Mar-17
05:00 PM
20-Feb-17
08:00 AM
15-Apr-17
05:00 PM
31.00 0.00
R.8
R.8.1
A1520 Place wall insulation - 1st floor A1350,
A1360,
A1470,
A1490,
A1510,
A1410
1.00 09-Mar-17
08:00 AM
09-Mar-17
05:00 PM
09-Mar-17
08:00 AM
09-Mar-17
05:00 PM
0.00 0.00
A1530 Place wall insulation - 2nd floor A1520 1.00 10-Mar-17
08:00 AM
10-Mar-17
05:00 PM
08-Apr-17
08:00 AM
08-Apr-17
05:00 PM
25.00 1.00
A1540 Place ceiling insulation - 2nd floor A1530,
A1590
1.00 17-Mar-17
08:00 AM
17-Mar-17
05:00 PM
14-Apr-17
08:00 AM
14-Apr-17
05:00 PM
24.00 0.00
A1550 Conduct insulation inspection A1540 1.00 18-Mar-17
08:00 AM
18-Mar-17
05:00 PM
15-Apr-17
08:00 AM
15-Apr-17
05:00 PM
24.00 24.00
Subtotal 9.00 09-Mar-17
08:00 AM
18-Mar-17
05:00 PM
09-Mar-17
08:00 AM
15-Apr-17
05:00 PM
24.00 0.00
R.8.2
A1560 Install Drywall - 1st floor walls A1520 2.00 08-Mar-17
08:00 AM
09-Mar-17
05:00 PM
08-Mar-17
08:00 AM
09-Mar-17
05:00 PM
0.00 0.00
A1570 Install drywall - 1st floor
overhead
A1560 2.00 10-Mar-17
08:00 AM
11-Mar-17
05:00 PM
10-Mar-17
08:00 AM
11-Mar-17
05:00 PM
0.00 0.00
A1580 Install drywall 2nd floor walls A1570,
A1530
2.00 13-Mar-17
08:00 AM
14-Mar-17
05:00 PM
10-Apr-17
08:00 AM
11-Apr-17
05:00 PM
24.00 0.00
A1590 Install drywall 2nd floor overhead A1580 2.00 15-Mar-17
08:00 AM
16-Mar-17
05:00 PM
12-Apr-17
08:00 AM
13-Apr-17
05:00 PM
24.00 0.00
Abhishek Singh
© Oracle Corporation Page 5 of 9
Grouped by WBS and Sorted by Activity ID
WBS
Activity ID Activity Name Predecessors Original
Duration
Early
Start
Early
Finish
Late Start Late
Finish
Total Float Free Float
A1600 Tape & Float 1st floor drywall A1570 1.00 13-Mar-17
08:00 AM
13-Mar-17
05:00 PM
13-Mar-17
08:00 AM
13-Mar-17
05:00 PM
0.00 0.00
A1610 Tape & Float 2nd floor drywall A1600,
A1590
1.00 17-Mar-17
08:00 AM
17-Mar-17
05:00 PM
25-Apr-17
08:00 AM
25-Apr-17
05:00 PM
33.00 33.00
Subtotal 9.00 08-Mar-17
08:00 AM
17-Mar-17
05:00 PM
08-Mar-17
08:00 AM
25-Apr-17
05:00 PM
33.00 0.00
R.8.3
A1620 Texture all except entry & kitchen
- 1st floor
A1600 1.00 14-Mar-17
08:00 AM
14-Mar-17
05:00 PM
14-Mar-17
08:00 AM
14-Mar-17
05:00 PM
0.00 0.00
A1630 Paint all except entry & kitchen -
1st floor
A1620 1.00 15-Mar-17
08:00 AM
15-Mar-17
05:00 PM
15-Mar-17
08:00 AM
15-Mar-17
05:00 PM
0.00 0.00
A1640 Hang wallpaper entry & kitchen -
1st floor
A1630 1.00 16-Mar-17
08:00 AM
16-Mar-17
05:00 PM
16-Mar-17
08:00 AM
16-Mar-17
05:00 PM
0.00 0.00
A1650 Texture all - 2nd floor A1620 1.00 15-Mar-17
08:00 AM
15-Mar-17
05:00 PM
24-Apr-17
08:00 AM
24-Apr-17
05:00 PM
34.00 0.00
A1660 Paint all - 2nd floor A1650 1.00 16-Mar-17
08:00 AM
16-Mar-17
05:00 PM
25-Apr-17
08:00 AM
25-Apr-17
05:00 PM
34.00 34.00
A1670 Paint exterior siding & trim work A1430 4.00 31-Mar-17
08:00 AM
04-Apr-17
05:00 PM
04-Apr-17
08:00 AM
07-Apr-17
05:00 PM
3.00 0.00
Subtotal 19.00 14-Mar-17
08:00 AM
04-Apr-17
05:00 PM
14-Mar-17
08:00 AM
25-Apr-17
05:00 PM
18.00 0.00
R.8.4
A1680 Install 1st floor - kitchen cabinets A1640 2.00 17-Mar-17
08:00 AM
18-Mar-17
05:00 PM
17-Mar-17
08:00 AM
18-Mar-17
05:00 PM
0.00 0.00
A1690 Install 1st floor - master bath &
guest cabinets
A1680 1.00 20-Mar-17
08:00 AM
20-Mar-17
05:00 PM
20-Mar-17
08:00 AM
20-Mar-17
05:00 PM
0.00 0.00
A1700 Install 2nd floor - hall bath &
provate bath cabinets
A1690 1.00 21-Mar-17
08:00 AM
21-Mar-17
05:00 PM
22-Mar-17
08:00 AM
22-Mar-17
05:00 PM
1.00 0.00
Abhishek Singh
© Oracle Corporation Page 6 of 9
Grouped by WBS and Sorted by Activity ID
WBS
Activity ID Activity Name Predecessors Original
Duration
Early
Start
Early
Finish
Late Start Late
Finish
Total Float Free Float
A1710 install chair rails, crown moldings,
trim
A1700 2.00 22-Mar-17
08:00 AM
23-Mar-17
05:00 PM
14-Apr-17
08:00 AM
15-Apr-17
05:00 PM
20.00 20.00
Subtotal 6.00 17-Mar-17
08:00 AM
23-Mar-17
05:00 PM
17-Mar-17
08:00 AM
15-Apr-17
05:00 PM
20.00 0.00
R.8.5
A1720 Complete 1st floor - kitchen
plumbing
A1450,
A1680
1.00 20-Mar-17
08:00 AM
20-Mar-17
05:00 PM
20-Mar-17
08:00 AM
20-Mar-17
05:00 PM
0.00 0.00
A1730 Complete 1st floor - master bath
& guest plumbing
A1690,
A1720
2.00 21-Mar-17
08:00 AM
22-Mar-17
05:00 PM
21-Mar-17
08:00 AM
22-Mar-17
05:00 PM
0.00 0.00
A1740 Complete 2nd floor - hall bath &
private bath plumbing
A1730,
A1700
2.00 23-Mar-17
08:00 AM
24-Mar-17
05:00 PM
23-Mar-17
08:00 AM
24-Mar-17
05:00 PM
0.00 0.00
A1750 Conduct finish plumbing
inspection
A1740 1.00 25-Mar-17
08:00 AM
25-Mar-17
05:00 PM
25-Mar-17
08:00 AM
25-Mar-17
05:00 PM
0.00 0.00
Subtotal 6.00 20-Mar-17
08:00 AM
25-Mar-17
05:00 PM
20-Mar-17
08:00 AM
25-Mar-17
05:00 PM
0.00 0.00
R.8.6
A1760 Complete 1st Floor circuits to
service panel
A1480,
A1740
1.00 25-Mar-17
08:00 AM
25-Mar-17
05:00 PM
29-Mar-17
08:00 AM
29-Mar-17
05:00 PM
3.00 0.00
A1770 Complete 2nd Floor circuits to
service panel
A1760 1.00 27-Mar-17
08:00 AM
27-Mar-17
05:00 PM
30-Mar-17
08:00 AM
30-Mar-17
05:00 PM
3.00 0.00
A1780 Conduct finish electrical
inspection
A1770 1.00 28-Mar-17
08:00 AM
28-Mar-17
05:00 PM
31-Mar-17
08:00 AM
31-Mar-17
05:00 PM
3.00 3.00
A1790 Complete communications wiring
- phone, cable, computer alarm
A1750 2.00 27-Mar-17
08:00 AM
28-Mar-17
05:00 PM
27-Mar-17
08:00 AM
28-Mar-17
05:00 PM
0.00 0.00
Subtotal 3.00 25-Mar-17
08:00 AM
28-Mar-17
05:00 PM
27-Mar-17
08:00 AM
31-Mar-17
05:00 PM
3.00 0.00
Abhishek Singh
© Oracle Corporation Page 7 of 9
Grouped by WBS and Sorted by Activity ID
WBS
Activity ID Activity Name Predecessors Original
Duration
Early
Start
Early
Finish
Late Start Late
Finish
Total Float Free Float
R.8.7
A1800 Complete 1st floor - zone 1
HVAC
A1500,
A1790
1.00 29-Mar-17
08:00 AM
29-Mar-17
05:00 PM
29-Mar-17
08:00 AM
29-Mar-17
05:00 PM
0.00 0.00
A1810 Complete 2nd floor - zone 2
HVAC
A1800 1.00 30-Mar-17
08:00 AM
30-Mar-17
05:00 PM
30-Mar-17
08:00 AM
30-Mar-17
05:00 PM
0.00 0.00
A1820 Conduct HVAC inspection A1810 1.00 31-Mar-17
08:00 AM
31-Mar-17
05:00 PM
31-Mar-17
08:00 AM
31-Mar-17
05:00 PM
0.00 0.00
Subtotal 3.00 29-Mar-17
08:00 AM
31-Mar-17
05:00 PM
29-Mar-17
08:00 AM
31-Mar-17
05:00 PM
0.00 0.00
R.8.8
A1830 Tile entry, kitchen & bath A1780,
A1820
3.00 01-Apr-17
08:00 AM
04-Apr-17
05:00 PM
01-Apr-17
08:00 AM
04-Apr-17
05:00 PM
0.00 0.00
A1840 Carpet 1st floor A1830 2.00 05-Apr-17
08:00 AM
06-Apr-17
05:00 PM
05-Apr-17
08:00 AM
06-Apr-17
05:00 PM
0.00 0.00
A1850 Carpet 2nd floor A1840 2.00 07-Apr-17
08:00 AM
08-Apr-17
05:00 PM
07-Apr-17
08:00 AM
08-Apr-17
05:00 PM
0.00 0.00
A1860 InstallAppliances A1850 1.00 10-Apr-17
08:00 AM
10-Apr-17
05:00 PM
10-Apr-17
08:00 AM
10-Apr-17
05:00 PM
0.00 0.00
Subtotal 8.00 01-Apr-17
08:00 AM
10-Apr-17
05:00 PM
01-Apr-17
08:00 AM
10-Apr-17
05:00 PM
0.00 0.00
Subtotal 29.00 08-Mar-17
08:00 AM
10-Apr-17
05:00 PM
08-Mar-17
08:00 AM
25-Apr-17
05:00 PM
13.00 0.00
R.9
A1870 Pour concrete driveway and
sidewalks
A1670 2.00 05-Apr-17
08:00 AM
06-Apr-17
05:00 PM
08-Apr-17
08:00 AM
10-Apr-17
05:00 PM
3.00 3.00
A1880 Install backyard fence A1870,
A1860
2.00 11-Apr-17
08:00 AM
12-Apr-17
05:00 PM
11-Apr-17
08:00 AM
12-Apr-17
05:00 PM
0.00 0.00
Abhishek Singh
© Oracle Corporation Page 8 of 9
Grouped by WBS and Sorted by Activity ID
WBS
Activity ID Activity Name Predecessors Original
Duration
Early
Start
Early
Finish
Late Start Late
Finish
Total Float Free Float
A1890 Sod & complete plantings -
frontyard
A1880 2.00 13-Apr-17
08:00 AM
14-Apr-17
05:00 PM
13-Apr-17
08:00 AM
14-Apr-17
05:00 PM
0.00 0.00
A1900 Sod & complete plantings -
backyard
A1890 1.00 15-Apr-17
08:00 AM
15-Apr-17
05:00 PM
15-Apr-17
08:00 AM
15-Apr-17
05:00 PM
0.00 0.00
Subtotal 10.00 05-Apr-17
08:00 AM
15-Apr-17
05:00 PM
08-Apr-17
08:00 AM
15-Apr-17
05:00 PM
0.00 0.00
R.5
A1910 Complete final inspection for
certificate of occupancy
A1900,
A1820,
A1780,
A1750,
A1710,
A1550,
A1460
1.00 17-Apr-17
08:00 AM
17-Apr-17
05:00 PM
17-Apr-17
08:00 AM
17-Apr-17
05:00 PM
0.00 0.00
A1920 Cleanup for occupancy A1860,
A1910
1.00 18-Apr-17
08:00 AM
18-Apr-17
05:00 PM
18-Apr-17
08:00 AM
18-Apr-17
05:00 PM
0.00 0.00
A1930 Perform final walk - through
inspection
A1920 1.00 19-Apr-17
08:00 AM
19-Apr-17
05:00 PM
19-Apr-17
08:00 AM
19-Apr-17
05:00 PM
0.00 0.00
A1940 Complete punch list items A1930 5.00 20-Apr-17
08:00 AM
25-Apr-17
05:00 PM
20-Apr-17
08:00 AM
25-Apr-17
05:00 PM
0.00 0.00
Subtotal 8.00 17-Apr-17
08:00 AM
25-Apr-17
05:00 PM
17-Apr-17
08:00 AM
25-Apr-17
05:00 PM
0.00 0.00
Subtotal 151.00 01-Nov-16
08:00 AM
25-Apr-17
05:00 PM
01-Nov-16
08:00 AM
25-Apr-17
05:00 PM
0.00 0.00
Abhishek Singh
© Oracle Corporation Page 9 of 9
17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08
October 2016 November 2016 December 2016 January 2017 February 2017 March 2017 April 2017 May 2017
25-Apr-17 05:00 PM, Residential Constructio
25-Nov-16 05:00 PM, General Conditions
Finalize Plans & Develop estimate with owner, architect
Sign Contract & Notice to proceed
25-Nov-16 05:00 PM, Apply For Permits
Secure Foundation Permit
Secure Framing Permit
Secure Electrical Permit
Secure Plumbing Permit
Secure HVAC Permit
Secure miscellaneous permits
29-Nov-16 05:00 PM, Site Work
Clear and grub lot
Install temporary power service
Install underground utilities
17-Jan-17 05:00 PM, Foundation
Excavate for foundations
Form basement walls
Place concrete for foundations & basement walls
Cure basement walls for 7 days
Strip basement wall forms
Waterproof / insulate bsement walls
Perform foundation inspection
Backfill foundation
11-Feb-17 05:00 PM, Framing
Install 1st floor joists
Lay 1st floor decking
Frame 1st floor walls
Frame 1st floor corners
Install 2nd floor joist
Frame 2nd Floor decking
Frame 2nd floor walls
Frame 2nd floor corners
Complete roof framing
Conduct framing inspection
08-Mar-17 05:00 PM, Dry In
Install 1st Floor Sheathing
Install 2nd Floor Sheathing
Install roof decking
Install felt, flashing, and shingles
Hang 1st floor exterior doors
Install 1st floor windows
Install 2nd floor windows
30-Mar-17 05:00 PM, Exterior Finishes
Complete Exterior Brick
Complete exterior siding
10-Mar-17 05:00 PM, Utility Rough B97Ins and Complete Concrete
Rough-in-plumbing
Abhishek Singh Gantt Chart for Activities Grouped by WBS and Sorted by Activity ID
Actual Level of Effort
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 1 of 3 TASK filter: All Activities
© Oracle Corporation
17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08
October 2016 November 2016 December 2016 January 2017 February 2017 March 2017 April 2017 May 2017
Conduct Rough-in-plumbing inspection
Place concrete for basement floor
Rough-in electrical
Conduct Rough-in-electrical inspection
Rough-in HVAC
Conduct Rough-in-HVAC inspection
Rough-in communication - phone, cables, computer, alarm
10-Apr-17 05:00 PM, Interior Finishes
18-Mar-17 05:00 PM, Insulation
Place wall insulation - 1st floor
Place wall insulation - 2nd floor
Place ceiling insulation - 2nd floor
Conduct insulation inspection
17-Mar-17 05:00 PM, Drywall
Install Drywall - 1st floor walls
Install drywall - 1st floor overhead
Install drywall 2nd floor walls
Install drywall 2nd floor overhead
Tape & Float 1st floor drywall
Tape & Float 2nd floor drywall
04-Apr-17 05:00 PM, Paint & Wall Paper
Texture all except entry & kitchen - 1st floor
Paint all except entry & kitchen - 1st floor
Hang wallpaper entry & kitchen - 1st floor
Texture all - 2nd floor
Paint all - 2nd floor
Paint exterior siding & trim work
23-Mar-17 05:00 PM, Cabinets
Install 1st floor - kitchen cabinets
Install 1st floor - master bath & guest cabinets
Install 2nd floor - hall bath & provate bath cabinets
install chair rails, crown moldings, trim
25-Mar-17 05:00 PM, Finish Plumbing
Complete 1st floor - kitchen plumbing
Complete 1st floor - master bath & guest plumbing
Complete 2nd floor - hall bath & private bath plumbing
Conduct finish plumbing inspection
28-Mar-17 05:00 PM, FInish Electrical
Complete 1st Floor circuits to service panel
Complete 2nd Floor circuits to service panel
Conduct finish electrical inspection
Complete communications wiring - phone, cable, computer alarm
31-Mar-17 05:00 PM, Finish HVAC
Complete 1st floor - zone 1 HVAC
Complete 2nd floor - zone 2 HVAC
Conduct HVAC inspection
10-Apr-17 05:00 PM, Carpet, Tile & Appliances
Tile entry, kitchen & bath
Carpet 1st floor
Carpet 2nd floor
Abhishek Singh Gantt Chart for Activities Grouped by WBS and Sorted by Activity ID
Actual Level of Effort
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 2 of 3 TASK filter: All Activities
© Oracle Corporation
17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08
October 2016 November 2016 December 2016 January 2017 February 2017 March 2017 April 2017 May 2017
InstallAppliances
15-Apr-17 05:00 PM, Landscping and Grounds Work
Pour concrete driveway and sidewalks
Install backyard fence
Sod & complete plantings - frontyard
Sod & complete plantings - backyard
25-Apr-17 05:00 PM, FinalAcceptance
Complete final inspection for certificate of occupancy
Cleanup for occupancy
Perform final walk - through inspection
Complete punch list items
Abhishek Singh Gantt Chart for Activities Grouped by WBS and Sorted by Activity ID
Actual Level of Effort
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 3 of 3 TASK filter: All Activities
© Oracle Corporation
Project: R Residential Construction
WBS: R.1 General Conditions
WBS: R.S Site Work
WBS: R.2 Foundation
WBS: R.3 Framing
WBS: R.4 Dry In
WBS: R.6 Exterior Finishes
WBS: R.7 Utility Rough B97Ins and Complete Concrete
WBS: R.8 Interior Finishes
WBS: R.9 Landscping and Grounds Work
WBS: R.5 Final Acceptance
WBS: R.1.1 Apply For Permits
WBS: R.8.1 Insulation
WBS: R.8.2 Drywall
WBS: R.8.3 Paint & Wall Paper
WBS: R.8.4 Cabinets
WBS: R.8.5 Finish Plumbing
WBS: R.8.6 FInish Electrical
WBS: R.8.7 Finish HVAC
WBS: R.8.8 Carpet, Tile &Appliances
A1010
Sign Cont ract & Notice
to proc eed
A 1000
F inalize P lans &
Dev elop estimate with
owner, arc hitect
A1160
Secure miscellaneous
perm its
A1150
Secure HVA C Permit
A1140
Secure Plum bing
Permit
A1130
Secure Elec trical
Permit
A1120
Secure Fr aming Permit
A1110
Secure Foundat ion
Permit
A1040
Inst all underground
utilities
A1030
Inst all temporary
power serv ice
A1020
Clear and grublot
A1240
Backf ill f oundation
A1230
Perf orm f oundation
inspect ion
A1220
Waterproof / ins ulate
bsement walls
A 1210
S trip basement wall
f orm s
A 1200
Cure basement walls
f or 7 day s
A1190
Pl ace concr et e f or
f oundations &
basem ent walls
A1180
Form basement walls
A1170
Excav ate f or
f oundations
A1340
Conduct f raming
inspect ion
A1330
Com plete roof f raming
A1320
Frame 2nd f loor
corners
A 1310
F rame 2nd f loor walls
A 1300
F rame 2nd Floor
decking
A1290
Inst all 2nd f loor joist
A1280
Frame 1st f loor
corners
A1270
Frame 1st f loor walls
A1260
Lay 1st f loor decking
A1250
Inst all 1st f loor joists
A 1410
I nst all 2nd f loor
windows
A 1400
Inst all 1st f loor
windows
A1390
Hang 1s t f loor exterior
doors
A1380
Inst all f elt, fl ashing,
and shingles
A1360
Inst all 2nd Floor
Sheathing
A1350
Inst all 1st Floor
Sheathing
A1370
Inst all roof decking
A1430
Com plete ext erior
siding
A1420
Com plete Exterior
Brick
A1440
Rough-in-plumbing
A1510
Rough-in
communication -
phone, cables,
A 1500
Conduct
Rough-in-HVA C
inspection
A1490
Rough-in HVA C
A1480
Conduct
Rough-in-electrical
inspection
A1470
Rough-in elect rical
A1460
Pl ace concr et e f or
basem ent f loor
A1450
Conduct
Rough-in-plumbing
inspection
A1520
Place wall ins ulat ion -
1st f loor
A1550
Conduct insulation
inspection
A1540
Place ceiling insulation
- 2nd f loor
A1530
Place wall ins ulation -
2nd f loor
A1600
Tape & F loat 1st f loor
dry wall
A1570
Inst all dry wall - 1st
f loor over head
A1560
Inst all Drywall - 1st
f loor walls
A1610
Tape & Float 2nd floor
dry wall
A1590
Inst all dry wall 2nd
f loor ov erhead
A1580
Inst all dry wall 2nd
f loor walls
A1640
Hang wallpaper entry &
kitchen - 1s t f loor
A1630
Paint all except entry
& kit chen - 1st f loor
A1620
Texture all except entry
& kit chen - 1st f loor
A1670
Paint exteri or siding &
trim wor k
A1660
Paint all - 2nd f loor
A1650
Texture all - 2nd f loor
A 1690
Inst all 1st f loor -
mas ter bath & gues t
cabinets
A 1680
Inst all 1st f loor -
kitchen cabinets
A1710
install chair rails ,
crown moldings, trim
A 1700
I nst all 2nd f loor - hall
bath & prov ate bath
cabinets
A1750
Conduct f inish
plum bing inspect ion
A1740
Com plete 2nd f loor -
hall bath & pr iv at e bath
plum bing
A 1730
Com plete 1st f loor -
mas ter bath & gues t
plum bing
A 1720
Com plete 1st f loor -
kitchen plumbing
A1790
Com plete
communications wiring
- phone, cable,
A1780
Conduct f inish
elect rical inspection
A1770
Com plete 2nd F loor
circuits to servi ce
panel
A1760
Com plete 1st F loor
circuit s t o service
panel
A1820
Conduct HVAC
inspection
A1810
Complete 2nd f loor -
zone 2 HVAC
A1800
Complete 1st floor -
zone 1 HVAC
A 1860
I nst all Appliances
A 1850
Carpet 2nd floor
A 1840
Carpet 1st f loor
A1830
Tile entry, kitchen &
bath
A1900
Sod & com plete
plant ings - backy ard
A1890
Sod & com plete
plant ings - f ronty ard
A1880
Inst all bac ky ard f enc e
A1870
Pour concrete
driv eway and
sidewalks
A1940
Complete punch list
items
A1930
Perf orm f inal walk -
through inspection
A1920
Cleanup f or occupancy
A1910
Complete f inal
inspection f or
cert if icate of
Abhishek Singh Activity Network Layout
Activity ID
Activity Name Page 1 of 2 © Oracle Corporation
Activity ID Activity Name Original
Duration
Residential ConstructionResidential Construction 151.00
General ConditionsGeneral Conditions 22.00
A1000 Finalize Plans & Develop estimate with owner, architect20.00
A1010 Sign Contract & Notice to proceed 1.00
Apply For PermitsApply For Permits 1.00
A1110 Secure Foundation Permit 1.00
A1120 Secure Framing Permit 1.00
A1130 Secure Electrical Permit 1.00
A1140 Secure Plumbing Permit 1.00
A1150 Secure HVAC Permit 1.00
A1160 Secure miscellaneous permits 1.00
Site WorkSite Work 3.00
A1020 Clear and grub lot 1.00
A1030 Install temporary power service 1.00
A1040 Install underground utilities 1.00
FoundationFoundation 42.00
A1170 Excavate for foundations 3.00
A1180 Form basement walls 13.00
A1190 Place concrete for foundations & basement walls12.00
A1200 Cure basement walls for 7 days 7.00
A1210 Strip basement wall forms 2.00
A1220 Waterproof / insulate bsement walls 2.00
A1230 Perform foundation inspection 1.00
A1240 Backfill foundation 2.00
FramingFraming 22.00
A1250 Install 1st floor joists 2.00
A1260 Lay 1st floor decking 2.00
A1270 Frame 1st floor walls 4.00
A1280 Frame 1st floor corners 1.00
A1290 Install 2nd floor joist 2.00
A1300 Frame 2nd Floor decking 2.00
A1310 Frame 2nd floor walls 3.00
A1320 Frame 2nd floor corners 2.00
A1330 Complete roof framing 3.00
A1340 Conduct framing inspection 1.00
Dry InDry In 21.00
A1350 Install 1st Floor Sheathing 3.00
A1360 Install 2nd Floor Sheathing 3.00
A1380 Install felt, flashing, and shingles 3.00
A1390 Hang 1st floor exterior doors 1.00
A1400 Install 1st floor windows 3.00
A1410 Install 2nd floor windows 3.00
Exterior FinishesExterior Finishes 0.00
Utility Rough B97Ins and Complete ConcreteUtility Rough B97Ins and Complete Concrete5.00
A1440 Rough-in-plumbing 5.00
Interior FinishesInterior Finishes 29.00
InsulationInsulation 1.00
A1520 Place wall insulation - 1st floor 1.00
17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08
October 2016 November 2016 December 2016 January 2017 February 2017 March 2017 April 2017 May 2017
25-Apr-17 05:00 PM, Residential Cons
25-Nov-16 05:00 PM, General Conditions
Finalize Plans & Develop estimate with owner, architect
Sign Contract & Notice to proceed
25-Nov-16 05:00 PM, Apply For Permits
Secure Foundation Permit
Secure Framing Permit
Secure Electrical Permit
Secure Plumbing Permit
Secure HVAC Permit
Secure miscellaneous permits
29-Nov-16 05:00 PM, Site Work
Clear and grub lot
Install temporary power service
Install underground utilities
17-Jan-17 05:00 PM, Foundation
Excavate for foundations
Form basement walls
Place concrete for foundations & basement walls
Cure basement walls for 7 days
Strip basement wall forms
Waterproof / insulate bsement walls
Perform foundation inspection
Backfill foundation
11-Feb-17 05:00 PM, Framing
Install 1st floor joists
Lay 1st floor decking
Frame 1st floor walls
Frame 1st floor corners
Install 2nd floor joist
Frame 2nd Floor decking
Frame 2nd floor walls
Frame 2nd floor corners
Complete roof framing
Conduct framing inspection
08-Mar-17 05:00 PM, Dry In
Install 1st Floor Sheathing
Install 2nd Floor Sheathing
Install felt, flashing, and shingles
Hang 1st floor exterior doors
Install 1st floor windows
Install 2nd floor windows
24-Feb-17 05:00 PM, Utility Rough B97Ins and Complete Concrete
Rough-in-plumbing
10-Apr-17 05:00 PM, Interior Finishes
09-Mar-17 05:00 PM, Insulation
Place wall insulation - 1st floor
Abhishek Singh Activity Table and Gantt Chart for Critical Path Activities
Page 1 of 2 TASK filter: Critical.
© Oracle Corporation
Activity ID Activity Name Original
Duration
DrywallDrywall 5.00
A1560 Install Drywall - 1st floor walls 2.00
A1570 Install drywall - 1st floor overhead 2.00
A1600 Tape & Float 1st floor drywall 1.00
Paint & Wall PaperPaint & Wall Paper 3.00
A1620 Texture all except entry & kitchen - 1st floor 1.00
A1630 Paint all except entry & kitchen - 1st floor 1.00
A1640 Hang wallpaper entry & kitchen - 1st floor 1.00
CabinetsCabinets 3.00
A1680 Install 1st floor - kitchen cabinets 2.00
A1690 Install 1st floor - master bath & guest cabinets 1.00
Finish PlumbingFinish Plumbing 6.00
A1720 Complete 1st floor - kitchen plumbing 1.00
A1730 Complete 1st floor - master bath & guest plumbing2.00
A1740 Complete 2nd floor - hall bath & private bath plumbing2.00
A1750 Conduct finish plumbing inspection 1.00
FInish ElectricalFInish Electrical 2.00
A1790 Complete communications wiring - phone, cable, computer alarm2.00
Finish HVACFinish HVAC 3.00
A1800 Complete 1st floor - zone 1 HVAC 1.00
A1810 Complete 2nd floor - zone 2 HVAC 1.00
A1820 Conduct HVAC inspection 1.00
Carpet, Tile & AppliancesCarpet, Tile & Appliances 8.00
A1830 Tile entry, kitchen & bath 3.00
A1840 Carpet 1st floor 2.00
A1850 Carpet 2nd floor 2.00
A1860 InstallAppliances 1.00
Landscping and Grounds WorkLandscping and Grounds Work 5.00
A1880 Install backyard fence 2.00
A1890 Sod & complete plantings - frontyard 2.00
A1900 Sod & complete plantings - backyard 1.00
Final AcceptanceFinal Acceptance 8.00
A1910 Complete final inspection for certificate of occupancy1.00
A1920 Cleanup for occupancy 1.00
A1930 Perform final walk - through inspection 1.00
A1940 Complete punch list items 5.00
17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08
October 2016 November 2016 December 2016 January 2017 February 2017 March 2017 April 2017 May 2017
13-Mar-17 05:00 PM, Drywall
Install Drywall - 1st floor walls
Install drywall - 1st floor overhead
Tape & Float 1st floor drywall
16-Mar-17 05:00 PM, Paint & Wall Paper
Texture all except entry & kitchen - 1st floor
Paint all except entry & kitchen - 1st floor
Hang wallpaper entry & kitchen - 1st floor
20-Mar-17 05:00 PM, Cabinets
Install 1st floor - kitchen cabinets
Install 1st floor - master bath & guest cabinets
25-Mar-17 05:00 PM, Finish Plumbing
Complete 1st floor - kitchen plumbing
Complete 1st floor - master bath & guest plumbing
Complete 2nd floor - hall bath & private bath plumbing
Conduct finish plumbing inspection
28-Mar-17 05:00 PM, FInish Electrical
Complete communications wiring - phone, cable, computer alarm
31-Mar-17 05:00 PM, Finish HVAC
Complete 1st floor - zone 1 HVAC
Complete 2nd floor - zone 2 HVAC
Conduct HVAC inspection
10-Apr-17 05:00 PM, Carpet, Tile & Appliances
Tile entry, kitchen & bath
Carpet 1st floor
Carpet 2nd floor
InstallAppliances
15-Apr-17 05:00 PM, Landscping and Grounds Wo
Install backyard fence
Sod & complete plantings - frontyard
Sod & complete plantings - backyard
25-Apr-17 05:00 PM, FinalAcceptance
Complete final inspection for certificate of occupa
Cleanup for occupancy
Perform final walk - through inspection
Complete punch list items
Abhishek Singh Activity Table and Gantt Chart for Critical Path Activities
Page 2 of 2 TASK filter: Critical.
© Oracle Corporation
17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08
October 2016 November 2016 December 2016 January 2017 February 2017 March 2017 April 2017 May 2017
25-Apr-17 05:00 PM, Residential Constructio
25-Nov-16 05:00 PM, General Conditions
Finalize Plans & Develop estimate with owner, architect
Sign Contract & Notice to proceed
25-Nov-16 05:00 PM, Apply For Permits
Secure Foundation Permit
Secure Framing Permit
Secure Electrical Permit
Secure Plumbing Permit
Secure HVAC Permit
Secure miscellaneous permits
29-Nov-16 05:00 PM, Site Work
Clear and grub lot
Install temporary power service
Install underground utilities
17-Jan-17 05:00 PM, Foundation
Excavate for foundations
Form basement walls
Place concrete for foundations & basement walls
Cure basement walls for 7 days
Strip basement wall forms
Waterproof / insulate bsement walls
Perform foundation inspection
Backfill foundation
11-Feb-17 05:00 PM, Framing
Install 1st floor joists
Lay 1st floor decking
Frame 1st floor walls
Frame 1st floor corners
Install 2nd floor joist
Frame 2nd Floor decking
Frame 2nd floor walls
Frame 2nd floor corners
Complete roof framing
Conduct framing inspection
08-Mar-17 05:00 PM, Dry In
Install 1st Floor Sheathing
Install 2nd Floor Sheathing
Install felt, flashing, and shingles
Hang 1st floor exterior doors
Install 1st floor windows
Install 2nd floor windows
24-Feb-17 05:00 PM, Utility Rough B97Ins and Complete Concrete
Rough-in-plumbing
10-Apr-17 05:00 PM, Interior Finishes
09-Mar-17 05:00 PM, Insulation
Place wall insulation - 1st floor
Abhishek Singh Critical Path Activities
Page 1 of 2 TASK filter: Critical.
© Oracle Corporation
17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08
October 2016 November 2016 December 2016 January 2017 February 2017 March 2017 April 2017 May 2017
13-Mar-17 05:00 PM, Drywall
Install Drywall - 1st floor walls
Install drywall - 1st floor overhead
Tape & Float 1st floor drywall
16-Mar-17 05:00 PM, Paint & Wall Paper
Texture all except entry & kitchen - 1st floor
Paint all except entry & kitchen - 1st floor
Hang wallpaper entry & kitchen - 1st floor
20-Mar-17 05:00 PM, Cabinets
Install 1st floor - kitchen cabinets
Install 1st floor - master bath & guest cabinets
25-Mar-17 05:00 PM, Finish Plumbing
Complete 1st floor - kitchen plumbing
Complete 1st floor - master bath & guest plumbing
Complete 2nd floor - hall bath & private bath plumbing
Conduct finish plumbing inspection
28-Mar-17 05:00 PM, FInish Electrical
Complete communications wiring - phone, cable, computer alarm
31-Mar-17 05:00 PM, Finish HVAC
Complete 1st floor - zone 1 HVAC
Complete 2nd floor - zone 2 HVAC
Conduct HVAC inspection
10-Apr-17 05:00 PM, Carpet, Tile & Appliances
Tile entry, kitchen & bath
Carpet 1st floor
Carpet 2nd floor
InstallAppliances
15-Apr-17 05:00 PM, Landscping and Grounds Work
Install backyard fence
Sod & complete plantings - frontyard
Sod & complete plantings - backyard
25-Apr-17 05:00 PM, FinalAcceptance
Complete final inspection for certificate of occupancy
Cleanup for occupancy
Perform final walk - through inspection
Complete punch list items
Abhishek Singh Critical Path Activities
Page 2 of 2 TASK filter: Critical.
© Oracle Corporation
Activity ID Activity Name Original
Duration
Free FloatRemaining
Duration
Residential ConstructionResidential Construction 151.00 0.00151.00
General ConditionsGeneral Conditions 22.00 0.0022.00
A1000 Finalize Plans & Develop estimate with owner, architect20.00 0.0020.00
A1010 Sign Contract & Notice to proceed 1.00 0.00 1.00
Apply For PermitsApply For Permits 1.00 0.00 1.00
A1110Secure Foundation Permit 1.00 0.00 1.00
A1120Secure Framing Permit 1.00 0.00 1.00
A1130Secure Electrical Permit 1.00 0.00 1.00
A1140Secure Plumbing Permit 1.00 0.00 1.00
A1150Secure HVAC Permit 1.00 0.00 1.00
A1160Secure miscellaneous permits 1.00 0.00 1.00
Site WorkSite Work 3.00 0.00 3.00
A1020 Clear and grub lot 1.00 0.00 1.00
A1030 Install temporary power service 1.00 0.00 1.00
A1040 Install underground utilities 1.00 0.00 1.00
FoundationFoundation 42.00 0.0042.00
A1170 Excavate for foundations 3.00 0.00 3.00
A1180 Form basement walls 13.00 0.0013.00
A1190 Place concrete for foundations & basement walls12.00 0.0012.00
A1200 Cure basement walls for 7 days 7.00 0.00 7.00
A1210 Strip basement wall forms 2.00 0.00 2.00
A1220 Waterproof / insulate bsement walls 2.00 0.00 2.00
A1230 Perform foundation inspection 1.00 0.00 1.00
A1240 Backfill foundation 2.00 0.00 2.00
FramingFraming 22.00 0.0022.00
A1250 Install 1st floor joists 2.00 0.00 2.00
A1260 Lay 1st floor decking 2.00 0.00 2.00
A1270 Frame 1st floor walls 4.00 0.00 4.00
A1280 Frame 1st floor corners 1.00 0.00 1.00
A1290 Install 2nd floor joist 2.00 0.00 2.00
A1300 Frame 2nd Floor decking 2.00 0.00 2.00
A1310 Frame 2nd floor walls 3.00 0.00 3.00
A1320 Frame 2nd floor corners 2.00 0.00 2.00
A1330 Complete roof framing 3.00 0.00 3.00
A1340 Conduct framing inspection 1.00 0.00 1.00
Dry InDry In 22.00 0.0022.00
A1370 Install roof decking 3.00 0.00 3.00
A1350 Install 1st Floor Sheathing 3.00 0.00 3.00
A1360 Install 2nd Floor Sheathing 3.00 0.00 3.00
A1380 Install felt, flashing, and shingles 3.00 0.00 3.00
A1390 Hang 1st floor exterior doors 1.00 0.00 1.00
A1400 Install 1st floor windows 3.00 0.00 3.00
A1410 Install 2nd floor windows 3.00 0.00 3.00
Exterior FinishesExterior Finishes 19.00 0.0019.00
A1420 Complete Exterior Brick 16.00 0.0016.00
A1430 Complete exterior siding 3.00 0.00 3.00
Utility Rough B97Ins and Complete ConcreteUtility Rough B97Ins and Complete Concrete21.00 0.0021.00
A1510 Rough-in communication - phone, cables, computer, alarm2.00 17.00 2.00
17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08
October 2016 November 2016 December 2016 January 2017 February 2017 March 2017 April 2017 May 2017
25-Apr-17 05:00 PM, Residential Cons
25-Nov-16 05:00 PM, General Conditions
Finalize Plans & Develop estimate with owner, architect
Sign Contract & Notice to proceed
25-Nov-16 05:00 PM, Apply For Permits
Secure Foundation Permit
Secure Framing Permit
Secure Electrical Permit
Secure Plumbing Permit
Secure HVAC Permit
Secure miscellaneous permits
29-Nov-16 05:00 PM, Site Work
Clear and grub lot
Install temporary power service
Install underground utilities
17-Jan-17 05:00 PM, Foundation
Excavate for foundations
Form basement walls
Place concrete for foundations & basement walls
Cure basement walls for 7 days
Strip basement wall forms
Waterproof / insulate bsement walls
Perform foundation inspection
Backfill foundation
11-Feb-17 05:00 PM, Framing
Install 1st floor joists
Lay 1st floor decking
Frame 1st floor walls
Frame 1st floor corners
Install 2nd floor joist
Frame 2nd Floor decking
Frame 2nd floor walls
Frame 2nd floor corners
Complete roof framing
Conduct framing inspection
08-Mar-17 05:00 PM, Dry In
Install roof decking
Install 1st Floor Sheathing
Install 2nd Floor Sheathing
Install felt, flashing, and shingles
Hang 1st floor exterior doors
Install 1st floor windows
Install 2nd floor windows
30-Mar-17 05:00 PM, Exterior Finishes
Complete Exterior Brick
Complete exterior siding
10-Mar-17 05:00 PM, Utility Rough B97Ins and Complete Concrete
Rough-in communication - phone, cables, computer, alarm
Abhishek Singh Gantt Chart Schedule for Activities Grouped by WBS and Sorted by Early Start and Free Float
Actual Level of Effort
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 1 of 3 TASK filter: All Activities
© Oracle Corporation
Activity ID Activity Name Original
Duration
Free FloatRemaining
Duration
A1440 Rough-in-plumbing 5.00 0.00 5.00
A1470 Rough-in electrical 5.00 0.00 5.00
A1450 Conduct Rough-in-plumbing inspection 1.00 0.00 1.00
A1480 Conduct Rough-in-electrical inspection 1.00 0.00 1.00
A1490 Rough-in HVAC 3.00 0.00 3.00
A1460 Place concrete for basement floor 11.00 31.0011.00
A1500 Conduct Rough-in-HVAC inspection 1.00 22.00 1.00
Interior FinishesInterior Finishes 29.00 0.0029.00
InsulationInsulation 9.00 0.00 9.00
A1520Place wall insulation - 1st floor 1.00 0.00 1.00
A1530Place wall insulation - 2nd floor 1.00 1.00 1.00
A1540Place ceiling insulation - 2nd floor 1.00 0.00 1.00
A1550Conduct insulation inspection 1.00 24.00 1.00
DrywallDrywall 9.00 0.00 9.00
A1560Install Drywall - 1st floor walls 2.00 0.00 2.00
A1570Install drywall - 1st floor overhead 2.00 0.00 2.00
A1580Install drywall 2nd floor walls 2.00 0.00 2.00
A1600Tape & Float 1st floor drywall 1.00 0.00 1.00
A1590Install drywall 2nd floor overhead 2.00 0.00 2.00
A1610Tape & Float 2nd floor drywall 1.00 33.00 1.00
Paint & Wall PaperPaint & Wall Paper 19.00 0.0019.00
A1620Texture all except entry & kitchen - 1st floor1.00 0.00 1.00
A1630Paint all except entry & kitchen - 1st floor 1.00 0.00 1.00
A1650Texture all - 2nd floor 1.00 0.00 1.00
A1640Hang wallpaper entry & kitchen - 1st floor1.00 0.00 1.00
A1660Paint all - 2nd floor 1.00 34.00 1.00
A1670Paint exterior siding & trim work 4.00 0.00 4.00
CabinetsCabinets 6.00 0.00 6.00
A1680Install 1st floor - kitchen cabinets 2.00 0.00 2.00
A1690Install 1st floor - master bath & guest cabinets1.00 0.00 1.00
A1700Install 2nd floor - hall bath & provate bath cabinets1.00 0.00 1.00
A1710install chair rails, crown moldings, trim 2.00 20.00 2.00
Finish PlumbingFinish Plumbing 6.00 0.00 6.00
A1720Complete 1st floor - kitchen plumbing 1.00 0.00 1.00
A1730Complete 1st floor - master bath & guest plumbing2.00 0.00 2.00
A1740Complete 2nd floor - hall bath & private bath plumbing2.00 0.00 2.00
A1750Conduct finish plumbing inspection 1.00 0.00 1.00
FInish ElectricalFInish Electrical 3.00 0.00 3.00
A1760Complete 1st Floor circuits to service panel1.00 0.00 1.00
A1770Complete 2nd Floor circuits to service panel1.00 0.00 1.00
A1790Complete communications wiring - phone, cable, computer alarm2.00 0.00 2.00
A1780Conduct finish electrical inspection 1.00 3.00 1.00
Finish HVACFinish HVAC 3.00 0.00 3.00
A1800Complete 1st floor - zone 1 HVAC 1.00 0.00 1.00
A1810Complete 2nd floor - zone 2 HVAC 1.00 0.00 1.00
A1820Conduct HVAC inspection 1.00 0.00 1.00
Carpet, Tile & AppliancesCarpet, Tile & Appliances 8.00 0.00 8.00
A1830Tile entry, kitchen & bath 3.00 0.00 3.00
A1840Carpet 1st floor 2.00 0.00 2.00
A1850Carpet 2nd floor 2.00 0.00 2.00
17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08
October 2016 November 2016 December 2016 January 2017 February 2017 March 2017 April 2017 May 2017
Rough-in-plumbing
Rough-in electrical
Conduct Rough-in-plumbing inspection
Conduct Rough-in-electrical inspection
Rough-in HVAC
Place concrete for basement floor
Conduct Rough-in-HVAC inspection
10-Apr-17 05:00 PM, Interior Finishes
18-Mar-17 05:00 PM, Insulation
Place wall insulation - 1st floor
Place wall insulation - 2nd floor
Place ceiling insulation - 2nd floor
Conduct insulation inspection
17-Mar-17 05:00 PM, Drywall
Install Drywall - 1st floor walls
Install drywall - 1st floor overhead
Install drywall 2nd floor walls
Tape & Float 1st floor drywall
Install drywall 2nd floor overhead
Tape & Float 2nd floor drywall
04-Apr-17 05:00 PM, Paint & Wall Paper
Texture all except entry & kitchen - 1st floor
Paint all except entry & kitchen - 1st floor
Texture all - 2nd floor
Hang wallpaper entry & kitchen - 1st floor
Paint all - 2nd floor
Paint exterior siding & trim work
23-Mar-17 05:00 PM, Cabinets
Install 1st floor - kitchen cabinets
Install 1st floor - master bath & guest cabinets
Install 2nd floor - hall bath & provate bath cabinets
install chair rails, crown moldings, trim
25-Mar-17 05:00 PM, Finish Plumbing
Complete 1st floor - kitchen plumbing
Complete 1st floor - master bath & guest plumbing
Complete 2nd floor - hall bath & private bath plumbing
Conduct finish plumbing inspection
28-Mar-17 05:00 PM, FInish Electrical
Complete 1st Floor circuits to service panel
Complete 2nd Floor circuits to service panel
Complete communications wiring - phone, cable, computer alarm
Conduct finish electrical inspection
31-Mar-17 05:00 PM, Finish HVAC
Complete 1st floor - zone 1 HVAC
Complete 2nd floor - zone 2 HVAC
Conduct HVAC inspection
10-Apr-17 05:00 PM, Carpet, Tile & Appliances
Tile entry, kitchen & bath
Carpet 1st floor
Carpet 2nd floor
Abhishek Singh Gantt Chart Schedule for Activities Grouped by WBS and Sorted by Early Start and Free Float
Actual Level of Effort
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 2 of 3 TASK filter: All Activities
© Oracle Corporation
Activity ID Activity Name Original
Duration
Free FloatRemaining
Duration
A1860InstallAppliances 1.00 0.00 1.00
Landscping and Grounds WorkLandscping and Grounds Work 10.00 0.0010.00
A1870 Pour concrete driveway and sidewalks 2.00 3.00 2.00
A1880 Install backyard fence 2.00 0.00 2.00
A1890 Sod & complete plantings - frontyard 2.00 0.00 2.00
A1900 Sod & complete plantings - backyard 1.00 0.00 1.00
Final AcceptanceFinal Acceptance 8.00 0.00 8.00
A1910 Complete final inspection for certificate of occupancy1.00 0.00 1.00
A1920 Cleanup for occupancy 1.00 0.00 1.00
A1930 Perform final walk - through inspection 1.00 0.00 1.00
A1940 Complete punch list items 5.00 0.00 5.00
17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08
October 2016 November 2016 December 2016 January 2017 February 2017 March 2017 April 2017 May 2017
InstallAppliances
15-Apr-17 05:00 PM, Landscping and Grounds W
Pour concrete driveway and sidewalks
Install backyard fence
Sod & complete plantings - frontyard
Sod & complete plantings - backyard
25-Apr-17 05:00 PM, FinalAcceptance
Complete final inspection for certificate of occup
Cleanup for occupancy
Perform final walk - through inspection
Complete punch list items
Abhishek Singh Gantt Chart Schedule for Activities Grouped by WBS and Sorted by Early Start and Free Float
Actual Level of Effort
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 3 of 3 TASK filter: All Activities
© Oracle Corporation
Report for the Budgeted Cost
WBS
Activity ID Activity Name Original
Duration
Budgeted
Labor Cost
Budgeted
Material Cost
Budgeted Total
Cost
R Residential Construction
R.1 General Conditions
A1000 Finalize Plans & Develop
estimate with owner, architect
20.00 $5,220.00 $0.00 $5,220.00
A1010 Sign Contract & Notice to
proceed
1.00 $750.00 $0.00 $750.00
R.1.1 Apply For Permits
A1110 Secure Foundation Permit 1.00 $0.00 $0.00 $0.00
A1120 Secure Framing Permit 1.00 $0.00 $0.00 $0.00
A1130 Secure Electrical Permit 1.00 $0.00 $0.00 $0.00
A1140 Secure Plumbing Permit 1.00 $0.00 $0.00 $0.00
A1150 Secure HVAC Permit 1.00 $0.00 $0.00 $0.00
A1160 Secure miscellaneous permits 1.00 $0.00 $0.00 $0.00
Subtotal 1.00 $0.00 $0.00 $0.00
Subtotal 22.00 $5,970.00 $0.00 $5,970.00
R.S Site Work
A1020 Clear and grub lot 1.00 $150.00 $0.00 $150.00
A1030 Install temporary power service 1.00 $150.00 $0.00 $150.00
A1040 Install underground utilities 1.00 $450.00 $0.00 $450.00
Subtotal 3.00 $750.00 $0.00 $750.00
R.2 Foundation
Abhishek Singh Residential Building Project
© Oracle Corporation Page 1 of 8
Report for the Budgeted Cost
WBS
Activity ID Activity Name Original
Duration
Budgeted
Labor Cost
Budgeted
Material Cost
Budgeted Total
Cost
A1170 Excavate for foundations 3.00 $450.00 $0.00 $450.00
A1180 Form basement walls 13.00 $2,600.00 $0.00 $2,600.00
A1190 Place concrete for foundations &
basement walls
12.00 $2,400.00 $0.00 $2,400.00
A1200 Cure basement walls for 7 days 7.00 $0.00 $0.00 $0.00
A1210 Strip basement wall forms 2.00 $400.00 $0.00 $400.00
A1220 Waterproof / insulate bsement
walls
2.00 $400.00 $0.00 $400.00
A1230 Perform foundation inspection 1.00 $0.00 $500.00 $500.00
A1240 Backfill foundation 2.00 $300.00 $0.00 $300.00
Subtotal 42.00 $6,550.00 $500.00 $7,050.00
R.3 Framing
A1250 Install 1st floor joists 2.00 $400.00 $0.00 $400.00
A1260 Lay 1st floor decking 2.00 $400.00 $0.00 $400.00
A1270 Frame 1st floor walls 4.00 $800.00 $0.00 $800.00
A1280 Frame 1st floor corners 1.00 $200.00 $0.00 $200.00
A1290 Install 2nd floor joist 2.00 $400.00 $0.00 $400.00
A1300 Frame 2nd Floor decking 2.00 $400.00 $0.00 $400.00
A1310 Frame 2nd floor walls 3.00 $600.00 $0.00 $600.00
A1320 Frame 2nd floor corners 2.00 $400.00 $0.00 $400.00
A1330 Complete roof framing 3.00 $600.00 $0.00 $600.00
A1340 Conduct framing inspection 1.00 $0.00 $500.00 $500.00
Subtotal 22.00 $4,200.00 $500.00 $4,700.00
Abhishek Singh Residential Building Project
© Oracle Corporation Page 2 of 8
Report for the Budgeted Cost
WBS
Activity ID Activity Name Original
Duration
Budgeted
Labor Cost
Budgeted
Material Cost
Budgeted Total
Cost
R.4 Dry In
A1350 Install 1st Floor Sheathing 3.00 $600.00 $0.00 $600.00
A1360 Install 2nd Floor Sheathing 3.00 $600.00 $0.00 $600.00
A1370 Install roof decking 3.00 $600.00 $0.00 $600.00
A1380 Install felt, flashing, and shingles 3.00 $300.00 $0.00 $300.00
A1390 Hang 1st floor exterior doors 1.00 $200.00 $0.00 $200.00
A1400 Install 1st floor windows 3.00 $600.00 $0.00 $600.00
A1410 Install 2nd floor windows 3.00 $600.00 $0.00 $600.00
Subtotal 22.00 $3,500.00 $0.00 $3,500.00
R.6 Exterior Finishes
A1420 Complete Exterior Brick 16.00 $2,400.00 $0.00 $2,400.00
A1430 Complete exterior siding 3.00 $600.00 $0.00 $600.00
Subtotal 19.00 $3,000.00 $0.00 $3,000.00
R.7 Utility Rough B97Ins and Complete Concrete
A1440 Rough-in-plumbing 5.00 $1,500.00 $0.00 $1,500.00
A1450 Conduct Rough-in-plumbing
inspection
1.00 $0.00 $500.00 $500.00
A1460 Place concrete for basement
floor
11.00 $2,200.00 $0.00 $2,200.00
A1470 Rough-in electrical 5.00 $750.00 $0.00 $750.00
A1480 Conduct Rough-in-electrical
inspection
1.00 $0.00 $500.00 $500.00
Abhishek Singh Residential Building Project
© Oracle Corporation Page 3 of 8
Report for the Budgeted Cost
WBS
Activity ID Activity Name Original
Duration
Budgeted
Labor Cost
Budgeted
Material Cost
Budgeted Total
Cost
A1490 Rough-in HVAC 3.00 $450.00 $0.00 $450.00
A1500 Conduct Rough-in-HVAC
inspection
1.00 $0.00 $500.00 $500.00
A1510 Rough-in communication -
phone, cables, computer, alarm
2.00 $300.00 $0.00 $300.00
Subtotal 21.00 $5,200.00 $1,500.00 $6,700.00
R.8 Interior Finishes
R.8.1 Insulation
A1520 Place wall insulation - 1st floor 1.00 $300.00 $0.00 $300.00
A1530 Place wall insulation - 2nd floor 1.00 $300.00 $0.00 $300.00
A1540 Place ceiling insulation - 2nd floor 1.00 $300.00 $0.00 $300.00
A1550 Conduct insulation inspection 1.00 $0.00 $500.00 $500.00
Subtotal 9.00 $900.00 $500.00 $1,400.00
R.8.2 Drywall
A1560 Install Drywall - 1st floor walls 2.00 $400.00 $0.00 $400.00
A1570 Install drywall - 1st floor
overhead
2.00 $400.00 $0.00 $400.00
A1580 Install drywall 2nd floor walls 2.00 $400.00 $0.00 $400.00
A1590 Install drywall 2nd floor overhead 2.00 $400.00 $0.00 $400.00
A1600 Tape & Float 1st floor drywall 1.00 $200.00 $0.00 $200.00
A1610 Tape & Float 2nd floor drywall 1.00 $200.00 $0.00 $200.00
Abhishek Singh Residential Building Project
© Oracle Corporation Page 4 of 8
Report for the Budgeted Cost
WBS
Activity ID Activity Name Original
Duration
Budgeted
Labor Cost
Budgeted
Material Cost
Budgeted Total
Cost
Subtotal 9.00 $2,000.00 $0.00 $2,000.00
R.8.3 Paint & Wall Paper
A1620 Texture all except entry & kitchen
- 1st floor
1.00 $100.00 $0.00 $100.00
A1630 Paint all except entry & kitchen -
1st floor
1.00 $100.00 $0.00 $100.00
A1640 Hang wallpaper entry & kitchen -
1st floor
1.00 $100.00 $0.00 $100.00
A1650 Texture all - 2nd floor 1.00 $100.00 $0.00 $100.00
A1660 Paint all - 2nd floor 1.00 $100.00 $0.00 $100.00
A1670 Paint exterior siding & trim work 4.00 $400.00 $0.00 $400.00
Subtotal 19.00 $900.00 $0.00 $900.00
R.8.4 Cabinets
A1680 Install 1st floor - kitchen cabinets 2.00 $300.00 $0.00 $300.00
A1690 Install 1st floor - master bath &
guest cabinets
1.00 $150.00 $0.00 $150.00
A1700 Install 2nd floor - hall bath &
provate bath cabinets
1.00 $150.00 $0.00 $150.00
A1710 install chair rails, crown moldings,
trim
2.00 $300.00 $0.00 $300.00
Subtotal 6.00 $900.00 $0.00 $900.00
R.8.5 Finish Plumbing
A1720 Complete 1st floor - kitchen
plumbing
1.00 $300.00 $0.00 $300.00
Abhishek Singh Residential Building Project
© Oracle Corporation Page 5 of 8
Report for the Budgeted Cost
WBS
Activity ID Activity Name Original
Duration
Budgeted
Labor Cost
Budgeted
Material Cost
Budgeted Total
Cost
A1730 Complete 1st floor - master bath
& guest plumbing
2.00 $600.00 $0.00 $600.00
A1740 Complete 2nd floor - hall bath &
private bath plumbing
2.00 $600.00 $0.00 $600.00
A1750 Conduct finish plumbing
inspection
1.00 $0.00 $500.00 $500.00
Subtotal 6.00 $1,500.00 $500.00 $2,000.00
R.8.6 FInish Electrical
A1760 Complete 1st Floor circuits to
service panel
1.00 $150.00 $0.00 $150.00
A1770 Complete 2nd Floor circuits to
service panel
1.00 $150.00 $0.00 $150.00
A1780 Conduct finish electrical
inspection
1.00 $0.00 $500.00 $500.00
A1790 Complete communications wiring
- phone, cable, computer alarm
2.00 $300.00 $0.00 $300.00
Subtotal 3.00 $600.00 $500.00 $1,100.00
R.8.7 Finish HVAC
A1800 Complete 1st floor - zone 1
HVAC
1.00 $150.00 $0.00 $150.00
A1810 Complete 2nd floor - zone 2
HVAC
1.00 $150.00 $0.00 $150.00
A1820 Conduct HVAC inspection 1.00 $0.00 $500.00 $500.00
Subtotal 3.00 $300.00 $500.00 $800.00
Abhishek Singh Residential Building Project
© Oracle Corporation Page 6 of 8
Report for the Budgeted Cost
WBS
Activity ID Activity Name Original
Duration
Budgeted
Labor Cost
Budgeted
Material Cost
Budgeted Total
Cost
R.8.8 Carpet, Tile & Appliances
A1830 Tile entry, kitchen & bath 3.00 $450.00 $0.00 $450.00
A1840 Carpet 1st floor 2.00 $300.00 $0.00 $300.00
A1850 Carpet 2nd floor 2.00 $300.00 $0.00 $300.00
A1860 InstallAppliances 1.00 $150.00 $0.00 $150.00
Subtotal 8.00 $1,200.00 $0.00 $1,200.00
Subtotal 29.00 $8,300.00 $2,000.00 $10,300.00
R.9 Landscping and Grounds Work
A1870 Pour concrete driveway and
sidewalks
2.00 $400.00 $0.00 $400.00
A1880 Install backyard fence 2.00 $300.00 $0.00 $300.00
A1890 Sod & complete plantings -
frontyard
2.00 $600.00 $0.00 $600.00
A1900 Sod & complete plantings -
backyard
1.00 $300.00 $0.00 $300.00
Subtotal 10.00 $1,600.00 $0.00 $1,600.00
R.5 FinalAcceptance
A1910 Complete final inspection for
certificate of occupancy
1.00 $0.00 $500.00 $500.00
A1920 Cleanup for occupancy 1.00 $0.00 $0.00 $200.00
A1930 Perform final walk - through
inspection
1.00 $200.00 $0.00 $200.00
Abhishek Singh Residential Building Project
© Oracle Corporation Page 7 of 8
Report for the Budgeted Cost
WBS
Activity ID Activity Name Original
Duration
Budgeted
Labor Cost
Budgeted
Material Cost
Budgeted Total
Cost
A1940 Complete punch list items 5.00 $750.00 $0.00 $750.00
Subtotal 8.00 $950.00 $500.00 $1,650.00
Subtotal 151.00 $40,020.00 $5,000.00 $45,220.00
Abhishek Singh Residential Building Project
© Oracle Corporation Page 8 of 8
Oct 17 Oct 24 Oct 31 Nov 07 Nov 14 Nov 21 Nov 28 Dec 05 Dec 12 Dec 19 Dec 26 Jan 02 Jan 09 Jan 16 Jan 23 Jan 30 Feb 06 Feb 13 Feb 20 Feb 27 Mar 06 Mar 13 Mar 20 Mar 27 Apr 03 Apr 10 Apr 17 Apr 24 May 01 May 08 May 15May 22
$200.00
$400.00
$600.00
$800.00
$1,000.00
$9,000.00
$18,000.00
$27,000.00
$36,000.00
$45,000.00
Abhishek Singh Daily Histogram and Cumulative curve for Labor cost
Budgeted Labor Cost Page 1 of 1 TASK filter: All Activities
© Oracle Corporation
Oct 17 Oct 24 Oct 31 Nov 07 Nov 14 Nov 21 Nov 28 Dec 05 Dec 12 Dec 19 Dec 26 Jan 02 Jan 09 Jan 16 Jan 23 Jan 30 Feb 06 Feb 13 Feb 20 Feb 27 Mar 06 Mar 13 Mar 20 Mar 27 Apr 03 Apr 10 Apr 17 Apr 24 May 01 May 08 May 15May 22
$200.00
$400.00
$600.00
$800.00
$1,000.00
$2,000.00
$4,000.00
$6,000.00
$8,000.00
$10,000.00
Abhishek Singh Daily Histogram and Cumulative curve for Material cost
Budgeted Material Cost Page 1 of 1 TASK filter: All Activities
© Oracle Corporation
17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08 15 22
October 2016 November 2016 December 2016 January 2017 February 2017 March 2017 April 2017 May 2017
$800.00
$1,600.00
$2,400.00
$3,200.00
$4,000.00
$10,000.00
$20,000.00
$30,000.00
$40,000.00
$50,000.00
Abhishek Singh Monthly Histogram and Cumulative curve for Total Cost
Budgeted Total Cost Page 1 of 1 TASK filter: All Activities
© Oracle Corporation
Activity ID Activity Name
Residential ConstructionResidential Construction
General ConditionsGeneral Conditions
A1000 Finalize Plans & Develop estimate with owner, architect
A1010 Sign Contract & Notice to proceed
Apply For PermitsApply For Permits
A1110 Secure Foundation Permit
A1120 Secure Framing Permit
A1130 Secure Electrical Permit
A1140 Secure Plumbing Permit
A1150 Secure HVAC Permit
A1160 Secure miscellaneous permits
Site WorkSite Work
A1020 Clear and grub lot
A1030 Install temporary power service
A1040 Install underground utilities
FoundationFoundation
A1170 Excavate for foundations
A1180 Form basement walls
A1190 Place concrete for foundations & basement walls
A1200 Cure basement walls for 7 days
A1210 Strip basement wall forms
A1220 Waterproof / insulate bsement walls
A1230 Perform foundation inspection
A1240 Backfill foundation
FramingFraming
A1250 Install 1st floor joists
A1260 Lay 1st floor decking
A1270 Frame 1st floor walls
A1280 Frame 1st floor corners
A1290 Install 2nd floor joist
A1300 Frame 2nd Floor decking
A1310 Frame 2nd floor walls
A1320 Frame 2nd floor corners
A1330 Complete roof framing
A1340 Conduct framing inspection
Dry InDry In
A1350 Install 1st Floor Sheathing
A1360 Install 2nd Floor Sheathing
A1370 Install roof decking
A1380 Install felt, flashing, and shingles
A1390 Hang 1st floor exterior doors
A1400 Install 1st floor windows
A1410 Install 2nd floor windows
Exterior FinishesExterior Finishes
A1420 Complete Exterior Brick
A1430 Complete exterior siding
Utility Rough B97Ins and Complete ConcreteUtility Rough B97Ins and Complete Concrete
A1440 Rough-in-plumbing
17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08 15 22
October 2016 November 2016 December 2016 January 2017 February 2017 March 2017 April 2017 May 2017
10-May-17 05:00 PM, Residential Con
10-Dec-16 05:00 PM, General Conditions
Finalize Plans & Develop estimate with owner, architect
Sign Contract & Notice to proceed
10-Dec-16 05:00 PM, Apply For Permits
Secure Foundation Permit
Secure Framing Permit
Secure Electrical Permit
Secure Plumbing Permit
Secure HVAC Permit
Secure miscellaneous permits
14-Dec-16 05:00 PM, Site Work
Clear and grub lot
Install temporary power service
Install underground utilities
01-Feb-17 05:00 PM, Foundation
Excavate for foundations
Form basement walls
Place concrete for foundations & basement walls
Cure basement walls for 7 days
Strip basement wall forms
Waterproof / insulate bsement walls
Perform foundation inspection
Backfill foundation
27-Feb-17 05:00 PM, Framing
Install 1st floor joists
Lay 1st floor decking
Frame 1st floor walls
Frame 1st floor corners
Install 2nd floor joist
Frame 2nd Floor decking
Frame 2nd floor walls
Frame 2nd floor corners
Complete roof framing
Conduct framing inspection
23-Mar-17 05:00 PM, Dry In
Install 1st Floor Sheathing
Install 2nd Floor Sheathing
Install roof decking
Install felt, flashing, and shingles
Hang 1st floor exterior doors
Install 1st floor windows
Install 2nd floor windows
14-Apr-17 05:00 PM, Exterior Finishes
Complete Exterior Brick
Complete exterior siding
25-Mar-17 05:00 PM, Utility Rough B97Ins and Complete Concrete
Rough-in-plumbing
Actual Level of Effort Primary Baseline Actual Work R... Updated Project Schedule with Activity Table
Actual Level of Effort
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 1 of 3 TASK filter: All Activities
© Oracle Corporation
Activity ID Activity Name
A1450 Conduct Rough-in-plumbing inspection
A1460 Place concrete for basement floor
A1470 Rough-in electrical
A1480 Conduct Rough-in-electrical inspection
A1490 Rough-in HVAC
A1500 Conduct Rough-in-HVAC inspection
A1510 Rough-in communication - phone, cables, computer, alarm
Interior FinishesInterior Finishes
InsulationInsulation
A1520 Place wall insulation - 1st floor
A1530 Place wall insulation - 2nd floor
A1540 Place ceiling insulation - 2nd floor
A1550 Conduct insulation inspection
DrywallDrywall
A1560 Install Drywall - 1st floor walls
A1570 Install drywall - 1st floor overhead
A1580 Install drywall 2nd floor walls
A1590 Install drywall 2nd floor overhead
A1600 Tape & Float 1st floor drywall
A1610 Tape & Float 2nd floor drywall
Paint & Wall PaperPaint & Wall Paper
A1620 Texture all except entry & kitchen - 1st floor
A1630 Paint all except entry & kitchen - 1st floor
A1640 Hang wallpaper entry & kitchen - 1st floor
A1650 Texture all - 2nd floor
A1660 Paint all - 2nd floor
A1670 Paint exterior siding & trim work
CabinetsCabinets
A1680 Install 1st floor - kitchen cabinets
A1690 Install 1st floor - master bath & guest cabinets
A1700 Install 2nd floor - hall bath & provate bath cabinets
A1710 install chair rails, crown moldings, trim
Finish PlumbingFinish Plumbing
A1720 Complete 1st floor - kitchen plumbing
A1730 Complete 1st floor - master bath & guest plumbing
A1740 Complete 2nd floor - hall bath & private bath plumbing
A1750 Conduct finish plumbing inspection
FInish ElectricalFInish Electrical
A1760 Complete 1st Floor circuits to service panel
A1770 Complete 2nd Floor circuits to service panel
A1780 Conduct finish electrical inspection
A1790 Complete communications wiring - phone, cable, computer alarm
Finish HVACFinish HVAC
A1800 Complete 1st floor - zone 1 HVAC
A1810 Complete 2nd floor - zone 2 HVAC
A1820 Conduct HVAC inspection
Carpet, Tile & AppliancesCarpet, Tile & Appliances
A1830 Tile entry, kitchen & bath
A1840 Carpet 1st floor
A1850 Carpet 2nd floor
17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08 15 22
October 2016 November 2016 December 2016 January 2017 February 2017 March 2017 April 2017 May 2017
Conduct Rough-in-plumbing inspection
Place concrete for basement floor
Rough-in electrical
Conduct Rough-in-electrical inspection
Rough-in HVAC
Conduct Rough-in-HVAC inspection
Rough-in communication - phone, cables, computer, alarm
25-Apr-17 05:00 PM, Interior Finishes
03-Apr-17 05:00 PM, Insulation
Place wall insulation - 1st floor
Place wall insulation - 2nd floor
Place ceiling insulation - 2nd floor
Conduct insulation inspection
01-Apr-17 05:00 PM, Drywall
Install Drywall - 1st floor walls
Install drywall - 1st floor overhead
Install drywall 2nd floor walls
Install drywall 2nd floor overhead
Tape & Float 1st floor drywall
Tape & Float 2nd floor drywall
19-Apr-17 05:00 PM, Paint & Wall Paper
Texture all except entry & kitchen - 1st floor
Paint all except entry & kitchen - 1st floor
Hang wallpaper entry & kitchen - 1st floor
Texture all - 2nd floor
Paint all - 2nd floor
Paint exterior siding & trim work
07-Apr-17 05:00 PM, Cabinets
Install 1st floor - kitchen cabinets
Install 1st floor - master bath & guest cabinets
Install 2nd floor - hall bath & provate bath cabinets
install chair rails, crown moldings, trim
10-Apr-17 05:00 PM, Finish Plumbing
Complete 1st floor - kitchen plumbing
Complete 1st floor - master bath & guest plumbing
Complete 2nd floor - hall bath & private bath plumbing
Conduct finish plumbing inspection
12-Apr-17 05:00 PM, FInish Electrical
Complete 1st Floor circuits to service panel
Complete 2nd Floor circuits to service panel
Conduct finish electrical inspection
Complete communications wiring - phone, cable, computer alarm
15-Apr-17 05:00 PM, Finish HVAC
Complete 1st floor - zone 1 HVAC
Complete 2nd floor - zone 2 HVAC
Conduct HVAC inspection
25-Apr-17 05:00 PM, Carpet, Tile & Appliances
Tile entry, kitchen & bath
Carpet 1st floor
Carpet 2nd floor
Actual Level of Effort Primary Baseline Actual Work R... Updated Project Schedule with Activity Table
Actual Level of Effort
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 2 of 3 TASK filter: All Activities
© Oracle Corporation
Activity ID Activity Name
A1860 InstallAppliances
Landscping and Grounds WorkLandscping and Grounds Work
A1870 Pour concrete driveway and sidewalks
A1880 Install backyard fence
A1890 Sod & complete plantings - frontyard
A1900 Sod & complete plantings - backyard
Final AcceptanceFinal Acceptance
A1910 Complete final inspection for certificate of occupancy
A1920 Cleanup for occupancy
A1930 Perform final walk - through inspection
A1940 Complete punch list items
17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08 15 22
October 2016 November 2016 December 2016 January 2017 February 2017 March 2017 April 2017 May 2017
InstallAppliances
01-May-17 05:00 PM, Landscping and Grounds
Pour concrete driveway and sidewalks
Install backyard fence
Sod & complete plantings - frontyard
Sod & complete plantings - backyard
10-May-17 05:00 PM, FinalAcceptanc
Complete final inspection for certificate of occup
Cleanup for occupancy
Perform final walk - through inspection
Complete punch list items
Actual Level of Effort Primary Baseline Actual Work R... Updated Project Schedule with Activity Table
Actual Level of Effort
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 3 of 3 TASK filter: All Activities
© Oracle Corporation
Activity ID Activity Name Original Duration Remaining Duration BL Project Start BL Project Finish Start Finish Variance - BL1 Finish Date Budgeted Total Cost
R Residential ConstructionR Residential Construction 164.00 139.00 01-Nov-16 08:00 AM 25-Apr-17 05:00 PM 02-Nov-16 08:00 AM
A
10-May-17 05:00 PM 0.00 $45,220.00
R.1 General ConditionsR.1 General Conditions 35.00 10.00 01-Nov-16 08:00 AM 25-Nov-16 05:00 PM 02-Nov-16 08:00 AM A10-Dec-16 05:00 PM 0.00 $5,970.00
A1010 Sign Contract & Notice to proceed 1.00 1.00 24-Nov-16 08:00 AM 24-Nov-16 05:00 PM 09-Dec-16 08:00 AM 09-Dec-16 05:00 PM 0.00 $750.00
A1000 Finalize Plans & Develop estimate with owner, architect 20.00 8.00 01-Nov-16 08:00 AM 23-Nov-16 05:00 PM 02-Nov-16 08:00 AM A08-Dec-16 05:00 PM -13.00 $5,220.00
R.1.1 Apply For PermitsR.1.1 Apply For Permits 1.00 1.00 25-Nov-16 08:00 AM 25-Nov-16 05:00 PM 10-Dec-16 08:00 AM 10-Dec-16 05:00 PM 0.00 $0.00
A1160 Secure miscellaneous permits 1.00 1.00 25-Nov-16 08:00 AM 25-Nov-16 05:00 PM 10-Dec-16 08:00 AM 10-Dec-16 05:00 PM 0.00 $0.00
A1150 Secure HVAC Permit 1.00 1.00 25-Nov-16 08:00 AM 25-Nov-16 05:00 PM 10-Dec-16 08:00 AM 10-Dec-16 05:00 PM 0.00 $0.00
A1140 Secure Plumbing Permit 1.00 1.00 25-Nov-16 08:00 AM 25-Nov-16 05:00 PM 10-Dec-16 08:00 AM 10-Dec-16 05:00 PM 0.00 $0.00
A1130 Secure Electrical Permit 1.00 1.00 25-Nov-16 08:00 AM 25-Nov-16 05:00 PM 10-Dec-16 08:00 AM 10-Dec-16 05:00 PM 0.00 $0.00
A1120 Secure Framing Permit 1.00 1.00 25-Nov-16 08:00 AM 25-Nov-16 05:00 PM 10-Dec-16 08:00 AM 10-Dec-16 05:00 PM 0.00 $0.00
A1110 Secure Foundation Permit 1.00 1.00 25-Nov-16 08:00 AM 25-Nov-16 05:00 PM 10-Dec-16 08:00 AM 10-Dec-16 05:00 PM 0.00 $0.00
R.S Site WorkR.S Site Work 3.00 3.00 26-Nov-16 08:00 AM 29-Nov-16 05:00 PM 12-Dec-16 08:00 AM 14-Dec-16 05:00 PM 0.00 $750.00
A1040 Install underground utilities 1.00 1.00 29-Nov-16 08:00 AM 29-Nov-16 05:00 PM 14-Dec-16 08:00 AM 14-Dec-16 05:00 PM 0.00 $450.00
A1030 Install temporary power service 1.00 1.00 28-Nov-16 08:00 AM 28-Nov-16 05:00 PM 13-Dec-16 08:00 AM 13-Dec-16 05:00 PM 0.00 $150.00
A1020 Clear and grub lot 1.00 1.00 26-Nov-16 08:00 AM 26-Nov-16 05:00 PM 12-Dec-16 08:00 AM 12-Dec-16 05:00 PM 0.00 $150.00
R.2 FoundationR.2 Foundation 42.00 42.00 30-Nov-16 08:00 AM 17-Jan-17 05:00 PM 15-Dec-16 08:00 AM 01-Feb-17 05:00 PM 0.00 $7,050.00
A1240 Backfill foundation 2.00 2.00 16-Jan-17 08:00 AM 17-Jan-17 05:00 PM 31-Jan-17 08:00 AM 01-Feb-17 05:00 PM 0.00 $300.00
A1230 Perform foundation inspection 1.00 1.00 14-Jan-17 08:00 AM 14-Jan-17 05:00 PM 30-Jan-17 08:00 AM 30-Jan-17 05:00 PM 0.00 $500.00
A1220 Waterproof / insulate bsement walls 2.00 2.00 12-Jan-17 08:00 AM 13-Jan-17 05:00 PM 27-Jan-17 08:00 AM 28-Jan-17 05:00 PM 0.00 $400.00
A1210 Strip basement wall forms 2.00 2.00 10-Jan-17 08:00 AM 11-Jan-17 05:00 PM 25-Jan-17 08:00 AM 26-Jan-17 05:00 PM 0.00 $400.00
A1200 Cure basement walls for 7 days 7.00 7.00 02-Jan-17 08:00 AM 09-Jan-17 05:00 PM 17-Jan-17 08:00 AM 24-Jan-17 05:00 PM 0.00 $0.00
A1190 Place concrete for foundations & basement walls 12.00 12.00 19-Dec-16 08:00 AM 31-Dec-16 05:00 PM 03-Jan-17 08:00 AM 16-Jan-17 05:00 PM 0.00 $2,400.00
A1180 Form basement walls 13.00 13.00 03-Dec-16 08:00 AM 17-Dec-16 05:00 PM 19-Dec-16 08:00 AM 02-Jan-17 05:00 PM 0.00 $2,600.00
A1170 Excavate for foundations 3.00 3.00 30-Nov-16 08:00 AM 02-Dec-16 05:00 PM 15-Dec-16 08:00 AM 17-Dec-16 05:00 PM 0.00 $450.00
R.3 FramingR.3 Framing 22.00 22.00 18-Jan-17 08:00 AM 11-Feb-17 05:00 PM 02-Feb-17 08:00 AM 27-Feb-17 05:00 PM 0.00 $4,700.00
A1340 Conduct framing inspection 1.00 1.00 11-Feb-17 08:00 AM 11-Feb-17 05:00 PM 27-Feb-17 08:00 AM 27-Feb-17 05:00 PM 0.00 $500.00
A1330 Complete roof framing 3.00 3.00 08-Feb-17 08:00 AM 10-Feb-17 05:00 PM 23-Feb-17 08:00 AM 25-Feb-17 05:00 PM 0.00 $600.00
A1320 Frame 2nd floor corners 2.00 2.00 06-Feb-17 08:00 AM 07-Feb-17 05:00 PM 21-Feb-17 08:00 AM 22-Feb-17 05:00 PM 0.00 $400.00
A1310 Frame 2nd floor walls 3.00 3.00 02-Feb-17 08:00 AM 04-Feb-17 05:00 PM 17-Feb-17 08:00 AM 20-Feb-17 05:00 PM 0.00 $600.00
A1300 Frame 2nd Floor decking 2.00 2.00 31-Jan-17 08:00 AM 01-Feb-17 05:00 PM 15-Feb-17 08:00 AM 16-Feb-17 05:00 PM 0.00 $400.00
A1290 Install 2nd floor joist 2.00 2.00 28-Jan-17 08:00 AM 30-Jan-17 05:00 PM 13-Feb-17 08:00 AM 14-Feb-17 05:00 PM 0.00 $400.00
A1280 Frame 1st floor corners 1.00 1.00 27-Jan-17 08:00 AM 27-Jan-17 05:00 PM 11-Feb-17 08:00 AM 11-Feb-17 05:00 PM 0.00 $200.00
A1270 Frame 1st floor walls 4.00 4.00 23-Jan-17 08:00 AM 26-Jan-17 05:00 PM 07-Feb-17 08:00 AM 10-Feb-17 05:00 PM 0.00 $800.00
A1260 Lay 1st floor decking 2.00 2.00 20-Jan-17 08:00 AM 21-Jan-17 05:00 PM 04-Feb-17 08:00 AM 06-Feb-17 05:00 PM 0.00 $400.00
A1250 Install 1st floor joists 2.00 2.00 18-Jan-17 08:00 AM 19-Jan-17 05:00 PM 02-Feb-17 08:00 AM 03-Feb-17 05:00 PM 0.00 $400.00
R.4 Dry InR.4 Dry In 22.00 22.00 11-Feb-17 08:00 AM 08-Mar-17 05:00 PM 27-Feb-17 08:00 AM 23-Mar-17 05:00 PM 0.00 $3,500.00
A1410 Install 2nd floor windows 3.00 3.00 06-Mar-17 08:00 AM 08-Mar-17 05:00 PM 21-Mar-17 08:00 AM 23-Mar-17 05:00 PM 0.00 $600.00
A1400 Install 1st floor windows 3.00 3.00 02-Mar-17 08:00 AM 04-Mar-17 05:00 PM 17-Mar-17 08:00 AM 20-Mar-17 05:00 PM 0.00 $600.00
A1390 Hang 1st floor exterior doors 1.00 1.00 01-Mar-17 08:00 AM 01-Mar-17 05:00 PM 16-Mar-17 08:00 AM 16-Mar-17 05:00 PM 0.00 $200.00
A1380 Install felt, flashing, and shingles 3.00 3.00 25-Feb-17 08:00 AM 28-Feb-17 05:00 PM 13-Mar-17 08:00 AM 15-Mar-17 05:00 PM 0.00 $300.00
A1360 Install 2nd Floor Sheathing 3.00 3.00 16-Feb-17 08:00 AM 18-Feb-17 05:00 PM 03-Mar-17 08:00 AM 06-Mar-17 05:00 PM 0.00 $600.00
A1350 Install 1st Floor Sheathing 3.00 3.00 13-Feb-17 08:00 AM 15-Feb-17 05:00 PM 28-Feb-17 08:00 AM 02-Mar-17 05:00 PM 0.00 $600.00
A1370 Install roof decking 3.00 3.00 11-Feb-17 08:00 AM 14-Feb-17 05:00 PM 27-Feb-17 08:00 AM 01-Mar-17 05:00 PM 0.00 $600.00
R.6 Exterior FinishesR.6 Exterior Finishes 19.00 19.00 09-Mar-17 08:00 AM 30-Mar-17 05:00 PM 24-Mar-17 08:00 AM 14-Apr-17 05:00 PM 0.00 $3,000.00
A1430 Complete exterior siding 3.00 3.00 28-Mar-17 08:00 AM 30-Mar-17 05:00 PM 12-Apr-17 08:00 AM 14-Apr-17 05:00 PM 0.00 $600.00
A1420 Complete Exterior Brick 16.00 16.00 09-Mar-17 08:00 AM 27-Mar-17 05:00 PM 24-Mar-17 08:00 AM 11-Apr-17 05:00 PM 0.00 $2,400.00
R.7 Utility Rough B97Ins and Complete ConcreteR.7 Utility Rough B97Ins and Complete Concrete 21.00 21.00 15-Feb-17 08:00 AM 10-Mar-17 05:00 PM 02-Mar-17 08:00 AM 25-Mar-17 05:00 PM 0.00 $6,700.00
A1460 Place concrete for basement floor 11.00 11.00 27-Feb-17 08:00 AM 10-Mar-17 05:00 PM 14-Mar-17 08:00 AM 25-Mar-17 05:00 PM 0.00 $2,200.00
Abhishek Singh Updated Project Schedule with Activity Table
Page 1 of 3 TASK filter: All Activities
© Oracle Corporation
Activity ID Activity Name Original Duration Remaining Duration BL Project Start BL Project Finish Start Finish Variance - BL1 Finish Date Budgeted Total Cost
A1500 Conduct Rough-in-HVAC inspection 1.00 1.00 02-Mar-17 08:00 AM 02-Mar-17 05:00 PM 17-Mar-17 08:00 AM 17-Mar-17 05:00 PM 0.00 $500.00
A1490 Rough-in HVAC 3.00 3.00 27-Feb-17 08:00 AM 01-Mar-17 05:00 PM 14-Mar-17 08:00 AM 16-Mar-17 05:00 PM 0.00 $450.00
A1480 Conduct Rough-in-electrical inspection 1.00 1.00 25-Feb-17 08:00 AM 25-Feb-17 05:00 PM 13-Mar-17 08:00 AM 13-Mar-17 05:00 PM 0.00 $500.00
A1450 Conduct Rough-in-plumbing inspection 1.00 1.00 25-Feb-17 08:00 AM 25-Feb-17 05:00 PM 13-Mar-17 08:00 AM 13-Mar-17 05:00 PM 0.00 $500.00
A1470 Rough-in electrical 5.00 5.00 20-Feb-17 08:00 AM 24-Feb-17 05:00 PM 07-Mar-17 08:00 AM 11-Mar-17 05:00 PM 0.00 $750.00
A1440 Rough-in-plumbing 5.00 5.00 20-Feb-17 08:00 AM 24-Feb-17 05:00 PM 07-Mar-17 08:00 AM 11-Mar-17 05:00 PM 0.00 $1,500.00
A1510 Rough-in communication - phone, cables, computer, alarm 2.00 2.00 15-Feb-17 08:00 AM 16-Feb-17 05:00 PM 02-Mar-17 08:00 AM 03-Mar-17 05:00 PM 0.00 $300.00
R.8 Interior FinishesR.8 Interior Finishes 29.00 29.00 08-Mar-17 08:00 AM 10-Apr-17 05:00 PM 23-Mar-17 08:00 AM 25-Apr-17 05:00 PM 0.00 $10,300.00
R.8.1 InsulationR.8.1 Insulation 9.00 9.00 09-Mar-17 08:00 AM 18-Mar-17 05:00 PM 24-Mar-17 08:00 AM 03-Apr-17 05:00 PM 0.00 $1,400.00
A1550 Conduct insulation inspection 1.00 1.00 18-Mar-17 08:00 AM 18-Mar-17 05:00 PM 03-Apr-17 08:00 AM 03-Apr-17 05:00 PM 0.00 $500.00
A1540 Place ceiling insulation - 2nd floor 1.00 1.00 17-Mar-17 08:00 AM 17-Mar-17 05:00 PM 01-Apr-17 08:00 AM 01-Apr-17 05:00 PM 0.00 $300.00
A1530 Place wall insulation - 2nd floor 1.00 1.00 10-Mar-17 08:00 AM 10-Mar-17 05:00 PM 25-Mar-17 08:00 AM 25-Mar-17 05:00 PM 0.00 $300.00
A1520 Place wall insulation - 1st floor 1.00 1.00 09-Mar-17 08:00 AM 09-Mar-17 05:00 PM 24-Mar-17 08:00 AM 24-Mar-17 05:00 PM 0.00 $300.00
R.8.2 DrywallR.8.2 Drywall 9.00 9.00 08-Mar-17 08:00 AM 17-Mar-17 05:00 PM 23-Mar-17 08:00 AM 01-Apr-17 05:00 PM 0.00 $2,000.00
A1610 Tape & Float 2nd floor drywall 1.00 1.00 17-Mar-17 08:00 AM 17-Mar-17 05:00 PM 01-Apr-17 08:00 AM 01-Apr-17 05:00 PM 0.00 $200.00
A1590 Install drywall 2nd floor overhead 2.00 2.00 15-Mar-17 08:00 AM 16-Mar-17 05:00 PM 30-Mar-17 08:00 AM 31-Mar-17 05:00 PM 0.00 $400.00
A1580 Install drywall 2nd floor walls 2.00 2.00 13-Mar-17 08:00 AM 14-Mar-17 05:00 PM 28-Mar-17 08:00 AM 29-Mar-17 05:00 PM 0.00 $400.00
A1600 Tape & Float 1st floor drywall 1.00 1.00 13-Mar-17 08:00 AM 13-Mar-17 05:00 PM 28-Mar-17 08:00 AM 28-Mar-17 05:00 PM 0.00 $200.00
A1570 Install drywall - 1st floor overhead 2.00 2.00 10-Mar-17 08:00 AM 11-Mar-17 05:00 PM 25-Mar-17 08:00 AM 27-Mar-17 05:00 PM 0.00 $400.00
A1560 Install Drywall - 1st floor walls 2.00 2.00 08-Mar-17 08:00 AM 09-Mar-17 05:00 PM 23-Mar-17 08:00 AM 24-Mar-17 05:00 PM 0.00 $400.00
R.8.3 Paint & Wall PaperR.8.3 Paint & Wall Paper 19.00 19.00 14-Mar-17 08:00 AM 04-Apr-17 05:00 PM 29-Mar-17 08:00 AM 19-Apr-17 05:00 PM 0.00 $900.00
A1670 Paint exterior siding & trim work 4.00 4.00 31-Mar-17 08:00 AM 04-Apr-17 05:00 PM 15-Apr-17 08:00 AM 19-Apr-17 05:00 PM 0.00 $400.00
A1660 Paint all - 2nd floor 1.00 1.00 16-Mar-17 08:00 AM 16-Mar-17 05:00 PM 31-Mar-17 08:00 AM 31-Mar-17 05:00 PM 0.00 $100.00
A1640 Hang wallpaper entry & kitchen - 1st floor 1.00 1.00 16-Mar-17 08:00 AM 16-Mar-17 05:00 PM 31-Mar-17 08:00 AM 31-Mar-17 05:00 PM 0.00 $100.00
A1650 Texture all - 2nd floor 1.00 1.00 15-Mar-17 08:00 AM 15-Mar-17 05:00 PM 30-Mar-17 08:00 AM 30-Mar-17 05:00 PM 0.00 $100.00
A1630 Paint all except entry & kitchen - 1st floor 1.00 1.00 15-Mar-17 08:00 AM 15-Mar-17 05:00 PM 30-Mar-17 08:00 AM 30-Mar-17 05:00 PM 0.00 $100.00
A1620 Texture all except entry & kitchen - 1st floor 1.00 1.00 14-Mar-17 08:00 AM 14-Mar-17 05:00 PM 29-Mar-17 08:00 AM 29-Mar-17 05:00 PM 0.00 $100.00
R.8.4 CabinetsR.8.4 Cabinets 6.00 6.00 17-Mar-17 08:00 AM 23-Mar-17 05:00 PM 01-Apr-17 08:00 AM 07-Apr-17 05:00 PM 0.00 $900.00
A1710 install chair rails, crown moldings, trim 2.00 2.00 22-Mar-17 08:00 AM 23-Mar-17 05:00 PM 06-Apr-17 08:00 AM 07-Apr-17 05:00 PM 0.00 $300.00
A1700 Install 2nd floor - hall bath & provate bath cabinets 1.00 1.00 21-Mar-17 08:00 AM 21-Mar-17 05:00 PM 05-Apr-17 08:00 AM 05-Apr-17 05:00 PM 0.00 $150.00
A1690 Install 1st floor - master bath & guest cabinets 1.00 1.00 20-Mar-17 08:00 AM 20-Mar-17 05:00 PM 04-Apr-17 08:00 AM 04-Apr-17 05:00 PM 0.00 $150.00
A1680 Install 1st floor - kitchen cabinets 2.00 2.00 17-Mar-17 08:00 AM 18-Mar-17 05:00 PM 01-Apr-17 08:00 AM 03-Apr-17 05:00 PM 0.00 $300.00
R.8.5 Finish PlumbingR.8.5 Finish Plumbing 6.00 6.00 20-Mar-17 08:00 AM 25-Mar-17 05:00 PM 04-Apr-17 08:00 AM 10-Apr-17 05:00 PM 0.00 $2,000.00
A1750 Conduct finish plumbing inspection 1.00 1.00 25-Mar-17 08:00 AM 25-Mar-17 05:00 PM 10-Apr-17 08:00 AM 10-Apr-17 05:00 PM 0.00 $500.00
A1740 Complete 2nd floor - hall bath & private bath plumbing 2.00 2.00 23-Mar-17 08:00 AM 24-Mar-17 05:00 PM 07-Apr-17 08:00 AM 08-Apr-17 05:00 PM 0.00 $600.00
A1730 Complete 1st floor - master bath & guest plumbing 2.00 2.00 21-Mar-17 08:00 AM 22-Mar-17 05:00 PM 05-Apr-17 08:00 AM 06-Apr-17 05:00 PM 0.00 $600.00
A1720 Complete 1st floor - kitchen plumbing 1.00 1.00 20-Mar-17 08:00 AM 20-Mar-17 05:00 PM 04-Apr-17 08:00 AM 04-Apr-17 05:00 PM 0.00 $300.00
R.8.6 FInish ElectricalR.8.6 FInish Electrical 3.00 3.00 25-Mar-17 08:00 AM 28-Mar-17 05:00 PM 10-Apr-17 08:00 AM 12-Apr-17 05:00 PM 0.00 $1,100.00
A1790 Complete communications wiring - phone, cable, computer alarm 2.00 2.00 27-Mar-17 08:00 AM 28-Mar-17 05:00 PM 11-Apr-17 08:00 AM 12-Apr-17 05:00 PM 0.00 $300.00
A1780 Conduct finish electrical inspection 1.00 1.00 28-Mar-17 08:00 AM 28-Mar-17 05:00 PM 12-Apr-17 08:00 AM 12-Apr-17 05:00 PM 0.00 $500.00
A1770 Complete 2nd Floor circuits to service panel 1.00 1.00 27-Mar-17 08:00 AM 27-Mar-17 05:00 PM 11-Apr-17 08:00 AM 11-Apr-17 05:00 PM 0.00 $150.00
A1760 Complete 1st Floor circuits to service panel 1.00 1.00 25-Mar-17 08:00 AM 25-Mar-17 05:00 PM 10-Apr-17 08:00 AM 10-Apr-17 05:00 PM 0.00 $150.00
R.8.7 Finish HVACR.8.7 Finish HVAC 3.00 3.00 29-Mar-17 08:00 AM 31-Mar-17 05:00 PM 13-Apr-17 08:00 AM 15-Apr-17 05:00 PM 0.00 $800.00
A1820 Conduct HVAC inspection 1.00 1.00 31-Mar-17 08:00 AM 31-Mar-17 05:00 PM 15-Apr-17 08:00 AM 15-Apr-17 05:00 PM 0.00 $500.00
A1810 Complete 2nd floor - zone 2 HVAC 1.00 1.00 30-Mar-17 08:00 AM 30-Mar-17 05:00 PM 14-Apr-17 08:00 AM 14-Apr-17 05:00 PM 0.00 $150.00
A1800 Complete 1st floor - zone 1 HVAC 1.00 1.00 29-Mar-17 08:00 AM 29-Mar-17 05:00 PM 13-Apr-17 08:00 AM 13-Apr-17 05:00 PM 0.00 $150.00
R.8.8 Carpet, Tile & AppliancesR.8.8 Carpet, Tile & Appliances 8.00 8.00 01-Apr-17 08:00 AM 10-Apr-17 05:00 PM 17-Apr-17 08:00 AM 25-Apr-17 05:00 PM 0.00 $1,200.00
A1860 InstallAppliances 1.00 1.00 10-Apr-17 08:00 AM 10-Apr-17 05:00 PM 25-Apr-17 08:00 AM 25-Apr-17 05:00 PM 0.00 $150.00
A1850 Carpet 2nd floor 2.00 2.00 07-Apr-17 08:00 AM 08-Apr-17 05:00 PM 22-Apr-17 08:00 AM 24-Apr-17 05:00 PM 0.00 $300.00
A1840 Carpet 1st floor 2.00 2.00 05-Apr-17 08:00 AM 06-Apr-17 05:00 PM 20-Apr-17 08:00 AM 21-Apr-17 05:00 PM 0.00 $300.00
Abhishek Singh Updated Project Schedule with Activity Table
Page 2 of 3 TASK filter: All Activities
© Oracle Corporation
Activity ID Activity Name Original Duration Remaining Duration BL Project Start BL Project Finish Start Finish Variance - BL1 Finish Date Budgeted Total Cost
A1830 Tile entry, kitchen & bath 3.00 3.00 01-Apr-17 08:00 AM 04-Apr-17 05:00 PM 17-Apr-17 08:00 AM 19-Apr-17 05:00 PM 0.00 $450.00
R.9 Landscping and Grounds WorkR.9 Landscping and Grounds Work 10.00 10.00 05-Apr-17 08:00 AM 15-Apr-17 05:00 PM 20-Apr-17 08:00 AM 01-May-17 05:00 PM 0.00 $1,600.00
A1900 Sod & complete plantings - backyard 1.00 1.00 15-Apr-17 08:00 AM 15-Apr-17 05:00 PM 01-May-17 08:00 AM 01-May-17 05:00 PM 0.00 $300.00
A1890 Sod & complete plantings - frontyard 2.00 2.00 13-Apr-17 08:00 AM 14-Apr-17 05:00 PM 28-Apr-17 08:00 AM 29-Apr-17 05:00 PM 0.00 $600.00
A1880 Install backyard fence 2.00 2.00 11-Apr-17 08:00 AM 12-Apr-17 05:00 PM 26-Apr-17 08:00 AM 27-Apr-17 05:00 PM 0.00 $300.00
A1870 Pour concrete driveway and sidewalks 2.00 2.00 05-Apr-17 08:00 AM 06-Apr-17 05:00 PM 20-Apr-17 08:00 AM 21-Apr-17 05:00 PM 0.00 $400.00
R.5 Final AcceptanceR.5 Final Acceptance 8.00 8.00 17-Apr-17 08:00 AM 25-Apr-17 05:00 PM 02-May-17 08:00 AM 10-May-17 05:00 PM 0.00 $1,650.00
A1940 Complete punch list items 5.00 5.00 20-Apr-17 08:00 AM 25-Apr-17 05:00 PM 05-May-17 08:00 AM 10-May-17 05:00 PM 0.00 $750.00
A1930 Perform final walk - through inspection 1.00 1.00 19-Apr-17 08:00 AM 19-Apr-17 05:00 PM 04-May-17 08:00 AM 04-May-17 05:00 PM 0.00 $200.00
A1920 Cleanup for occupancy 1.00 1.00 18-Apr-17 08:00 AM 18-Apr-17 05:00 PM 03-May-17 08:00 AM 03-May-17 05:00 PM 0.00 $200.00
A1910 Complete final inspection for certificate of occupancy 1.00 1.00 17-Apr-17 08:00 AM 17-Apr-17 05:00 PM 02-May-17 08:00 AM 02-May-17 05:00 PM 0.00 $500.00
Abhishek Singh Updated Project Schedule with Activity Table
Page 3 of 3 TASK filter: All Activities
© Oracle Corporation

More Related Content

Similar to CE 561 - Term Project on Primavera P6

Bridge project
Bridge projectBridge project
Bridge projectVivek John
 
Nbourdier-lab2-gantt chart with activities-
Nbourdier-lab2-gantt chart with activities-Nbourdier-lab2-gantt chart with activities-
Nbourdier-lab2-gantt chart with activities-Nixzalis Bourdier
 
12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...
12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...
12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...Rodger McKinley
 
HSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activityHSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activityRoumik Mukherjee
 
-The PERT Chart-The tendering time schedule for Adar Produced Water Re-injec...
-The PERT Chart-The tendering time schedule for Adar Produced  Water Re-injec...-The PERT Chart-The tendering time schedule for Adar Produced  Water Re-injec...
-The PERT Chart-The tendering time schedule for Adar Produced Water Re-injec...yang lu
 
Equipment Arrival Status.pptx
Equipment Arrival Status.pptxEquipment Arrival Status.pptx
Equipment Arrival Status.pptxMehmanNasibov1
 
SAMPLE PROJECT P6 PROFESSIONAL R16.2
SAMPLE PROJECT P6 PROFESSIONAL R16.2SAMPLE PROJECT P6 PROFESSIONAL R16.2
SAMPLE PROJECT P6 PROFESSIONAL R16.2Aqeel Imran
 
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)Allan Leyte
 
Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdfZewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdfAhmed Mehrem
 
Sample Project Monitoring-EVM Analysis
Sample Project Monitoring-EVM Analysis Sample Project Monitoring-EVM Analysis
Sample Project Monitoring-EVM Analysis Ayon Pal
 

Similar to CE 561 - Term Project on Primavera P6 (20)

Leyet Colleges Schedule
Leyet Colleges ScheduleLeyet Colleges Schedule
Leyet Colleges Schedule
 
Bridge project
Bridge projectBridge project
Bridge project
 
ARB JANADREA 25.01.16 UPDATE PM
ARB JANADREA 25.01.16 UPDATE  PMARB JANADREA 25.01.16 UPDATE  PM
ARB JANADREA 25.01.16 UPDATE PM
 
Nbourdier-lab2-gantt chart with activities-
Nbourdier-lab2-gantt chart with activities-Nbourdier-lab2-gantt chart with activities-
Nbourdier-lab2-gantt chart with activities-
 
01. P269 - Project Implementation Programme - Rev 00
01. P269 - Project Implementation Programme -  Rev 0001. P269 - Project Implementation Programme -  Rev 00
01. P269 - Project Implementation Programme - Rev 00
 
200040 CSJ.pdf
200040 CSJ.pdf200040 CSJ.pdf
200040 CSJ.pdf
 
12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...
12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...
12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...
 
Weekly report no 19
Weekly report no 19Weekly report no 19
Weekly report no 19
 
HSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activityHSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activity
 
-The PERT Chart-The tendering time schedule for Adar Produced Water Re-injec...
-The PERT Chart-The tendering time schedule for Adar Produced  Water Re-injec...-The PERT Chart-The tendering time schedule for Adar Produced  Water Re-injec...
-The PERT Chart-The tendering time schedule for Adar Produced Water Re-injec...
 
Equipment Arrival Status.pptx
Equipment Arrival Status.pptxEquipment Arrival Status.pptx
Equipment Arrival Status.pptx
 
Monthly Progress Report No.13 - September 2011
Monthly Progress Report No.13 - September 2011Monthly Progress Report No.13 - September 2011
Monthly Progress Report No.13 - September 2011
 
SAMPLE PROJECT P6 PROFESSIONAL R16.2
SAMPLE PROJECT P6 PROFESSIONAL R16.2SAMPLE PROJECT P6 PROFESSIONAL R16.2
SAMPLE PROJECT P6 PROFESSIONAL R16.2
 
IHH Healthcare Tender Programme.pdf
IHH Healthcare Tender Programme.pdfIHH Healthcare Tender Programme.pdf
IHH Healthcare Tender Programme.pdf
 
10. Overall Implementation Programme
10. Overall Implementation Programme10. Overall Implementation Programme
10. Overall Implementation Programme
 
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
 
Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdfZewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdf
 
Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13
 
Praktek1
Praktek1Praktek1
Praktek1
 
Sample Project Monitoring-EVM Analysis
Sample Project Monitoring-EVM Analysis Sample Project Monitoring-EVM Analysis
Sample Project Monitoring-EVM Analysis
 

More from Abhishek Singh

CE 592 - Estimation Planning & Control Term Project
CE 592 - Estimation Planning & Control Term ProjectCE 592 - Estimation Planning & Control Term Project
CE 592 - Estimation Planning & Control Term ProjectAbhishek Singh
 
Appreciation certificate by Boieng for OHT
Appreciation certificate by Boieng for OHTAppreciation certificate by Boieng for OHT
Appreciation certificate by Boieng for OHTAbhishek Singh
 
Appreciation certi by USACE
Appreciation certi by USACEAppreciation certi by USACE
Appreciation certi by USACEAbhishek Singh
 
Abhishek-LEED Green Associate (1)
Abhishek-LEED Green Associate (1)Abhishek-LEED Green Associate (1)
Abhishek-LEED Green Associate (1)Abhishek Singh
 

More from Abhishek Singh (7)

CE 592 - Estimation Planning & Control Term Project
CE 592 - Estimation Planning & Control Term ProjectCE 592 - Estimation Planning & Control Term Project
CE 592 - Estimation Planning & Control Term Project
 
Appreciation certificate by Boieng for OHT
Appreciation certificate by Boieng for OHTAppreciation certificate by Boieng for OHT
Appreciation certificate by Boieng for OHT
 
Appreciation certi by USACE
Appreciation certi by USACEAppreciation certi by USACE
Appreciation certi by USACE
 
CMIT Certificate
CMIT CertificateCMIT Certificate
CMIT Certificate
 
Abhishek-LEED Green Associate (1)
Abhishek-LEED Green Associate (1)Abhishek-LEED Green Associate (1)
Abhishek-LEED Green Associate (1)
 
Resume
ResumeResume
Resume
 
Resume
ResumeResume
Resume
 

CE 561 - Term Project on Primavera P6

  • 1. CE 561 Construction Project Management Small Residential Building Project FALL - 2016 ABHISHEK KUMAR SINGH 200116822
  • 2. Table of Contents SL No. Report Name 1 Grouped by Project and Sorted by Activity ID 2 Gantt Chart for activities grouped by WBS and Sorted by Activity ID 3 Activity Network Layout of the Project 4 Activity Table & Gantt Chart Schedule for Critical Activities 5 Gantt Chart Schedule for Critical Activities 6 Gantt Chart Schedule for activities Sorted by Early Start & Free Float 7 Report for Budgeted Cost 8 Daily Histogram and cumulative curve for Labor cost 9 Daily Histogram and cumulative curve for Material Cost 10 Monthly Histogram and Cumulative curve for Total Cost 11 Updated Schedule Report and Gantt Chart Table
  • 3. Grouped by WBS and Sorted by Activity ID WBS Activity ID Activity Name Predecessors Original Duration Early Start Early Finish Late Start Late Finish Total Float Free Float R R.1 A1000 Finalize Plans & Develop estimate with owner, architect 20.00 01-Nov-16 08:00 AM 23-Nov-16 05:00 PM 01-Nov-16 08:00 AM 23-Nov-16 05:00 PM 0.00 0.00 A1010 Sign Contract & Notice to proceed A1000 1.00 24-Nov-16 08:00 AM 24-Nov-16 05:00 PM 24-Nov-16 08:00 AM 24-Nov-16 05:00 PM 0.00 0.00 R.1.1 A1110 Secure Foundation Permit A1010 1.00 25-Nov-16 08:00 AM 25-Nov-16 05:00 PM 25-Nov-16 08:00 AM 25-Nov-16 05:00 PM 0.00 0.00 A1120 Secure Framing Permit A1010 1.00 25-Nov-16 08:00 AM 25-Nov-16 05:00 PM 25-Nov-16 08:00 AM 25-Nov-16 05:00 PM 0.00 0.00 A1130 Secure Electrical Permit A1010 1.00 25-Nov-16 08:00 AM 25-Nov-16 05:00 PM 25-Nov-16 08:00 AM 25-Nov-16 05:00 PM 0.00 0.00 A1140 Secure Plumbing Permit A1010 1.00 25-Nov-16 08:00 AM 25-Nov-16 05:00 PM 25-Nov-16 08:00 AM 25-Nov-16 05:00 PM 0.00 0.00 A1150 Secure HVAC Permit A1010 1.00 25-Nov-16 08:00 AM 25-Nov-16 05:00 PM 25-Nov-16 08:00 AM 25-Nov-16 05:00 PM 0.00 0.00 A1160 Secure miscellaneous permits A1010 1.00 25-Nov-16 08:00 AM 25-Nov-16 05:00 PM 25-Nov-16 08:00 AM 25-Nov-16 05:00 PM 0.00 0.00 Subtotal 1.00 25-Nov-16 08:00 AM 25-Nov-16 05:00 PM 25-Nov-16 08:00 AM 25-Nov-16 05:00 PM 0.00 0.00 Subtotal 22.00 01-Nov-16 08:00 AM 25-Nov-16 05:00 PM 01-Nov-16 08:00 AM 25-Nov-16 05:00 PM 0.00 0.00 R.S A1020 Clear and grub lot A1110, A1120, A1130, A1140, A1150, 1.00 26-Nov-16 08:00 AM 26-Nov-16 05:00 PM 26-Nov-16 08:00 AM 26-Nov-16 05:00 PM 0.00 0.00 Abhishek Singh © Oracle Corporation Page 1 of 9
  • 4. Grouped by WBS and Sorted by Activity ID WBS Activity ID Activity Name Predecessors Original Duration Early Start Early Finish Late Start Late Finish Total Float Free Float A1030 Install temporary power service A1020 1.00 28-Nov-16 08:00 AM 28-Nov-16 05:00 PM 28-Nov-16 08:00 AM 28-Nov-16 05:00 PM 0.00 0.00 A1040 Install underground utilities A1030 1.00 29-Nov-16 08:00 AM 29-Nov-16 05:00 PM 29-Nov-16 08:00 AM 29-Nov-16 05:00 PM 0.00 0.00 Subtotal 3.00 26-Nov-16 08:00 AM 29-Nov-16 05:00 PM 26-Nov-16 08:00 AM 29-Nov-16 05:00 PM 0.00 0.00 R.2 A1170 Excavate for foundations A1040 3.00 30-Nov-16 08:00 AM 02-Dec-16 05:00 PM 30-Nov-16 08:00 AM 02-Dec-16 05:00 PM 0.00 0.00 A1180 Form basement walls A1170 13.00 03-Dec-16 08:00 AM 17-Dec-16 05:00 PM 03-Dec-16 08:00 AM 17-Dec-16 05:00 PM 0.00 0.00 A1190 Place concrete for foundations & basement walls A1180 12.00 19-Dec-16 08:00 AM 31-Dec-16 05:00 PM 19-Dec-16 08:00 AM 31-Dec-16 05:00 PM 0.00 0.00 A1200 Cure basement walls for 7 days A1190 7.00 02-Jan-17 08:00 AM 09-Jan-17 05:00 PM 02-Jan-17 08:00 AM 09-Jan-17 05:00 PM 0.00 0.00 A1210 Strip basement wall forms A1200 2.00 10-Jan-17 08:00 AM 11-Jan-17 05:00 PM 10-Jan-17 08:00 AM 11-Jan-17 05:00 PM 0.00 0.00 A1220 Waterproof / insulate bsement walls A1210 2.00 12-Jan-17 08:00 AM 13-Jan-17 05:00 PM 12-Jan-17 08:00 AM 13-Jan-17 05:00 PM 0.00 0.00 A1230 Perform foundation inspection A1170, A1220 1.00 14-Jan-17 08:00 AM 14-Jan-17 05:00 PM 14-Jan-17 08:00 AM 14-Jan-17 05:00 PM 0.00 0.00 A1240 Backfill foundation A1230 2.00 16-Jan-17 08:00 AM 17-Jan-17 05:00 PM 16-Jan-17 08:00 AM 17-Jan-17 05:00 PM 0.00 0.00 Subtotal 42.00 30-Nov-16 08:00 AM 17-Jan-17 05:00 PM 30-Nov-16 08:00 AM 17-Jan-17 05:00 PM 0.00 0.00 R.3 A1250 Install 1st floor joists A1240 2.00 18-Jan-17 08:00 AM 19-Jan-17 05:00 PM 18-Jan-17 08:00 AM 19-Jan-17 05:00 PM 0.00 0.00 Abhishek Singh © Oracle Corporation Page 2 of 9
  • 5. Grouped by WBS and Sorted by Activity ID WBS Activity ID Activity Name Predecessors Original Duration Early Start Early Finish Late Start Late Finish Total Float Free Float A1260 Lay 1st floor decking A1250 2.00 20-Jan-17 08:00 AM 21-Jan-17 05:00 PM 20-Jan-17 08:00 AM 21-Jan-17 05:00 PM 0.00 0.00 A1270 Frame 1st floor walls A1260 4.00 23-Jan-17 08:00 AM 26-Jan-17 05:00 PM 23-Jan-17 08:00 AM 26-Jan-17 05:00 PM 0.00 0.00 A1280 Frame 1st floor corners A1270 1.00 27-Jan-17 08:00 AM 27-Jan-17 05:00 PM 27-Jan-17 08:00 AM 27-Jan-17 05:00 PM 0.00 0.00 A1290 Install 2nd floor joist A1280 2.00 28-Jan-17 08:00 AM 30-Jan-17 05:00 PM 28-Jan-17 08:00 AM 30-Jan-17 05:00 PM 0.00 0.00 A1300 Frame 2nd Floor decking A1290 2.00 31-Jan-17 08:00 AM 01-Feb-17 05:00 PM 31-Jan-17 08:00 AM 01-Feb-17 05:00 PM 0.00 0.00 A1310 Frame 2nd floor walls A1300 3.00 02-Feb-17 08:00 AM 04-Feb-17 05:00 PM 02-Feb-17 08:00 AM 04-Feb-17 05:00 PM 0.00 0.00 A1320 Frame 2nd floor corners A1310 2.00 06-Feb-17 08:00 AM 07-Feb-17 05:00 PM 06-Feb-17 08:00 AM 07-Feb-17 05:00 PM 0.00 0.00 A1330 Complete roof framing A1320 3.00 08-Feb-17 08:00 AM 10-Feb-17 05:00 PM 08-Feb-17 08:00 AM 10-Feb-17 05:00 PM 0.00 0.00 A1340 Conduct framing inspection A1330 1.00 11-Feb-17 08:00 AM 11-Feb-17 05:00 PM 11-Feb-17 08:00 AM 11-Feb-17 05:00 PM 0.00 0.00 Subtotal 22.00 18-Jan-17 08:00 AM 11-Feb-17 05:00 PM 18-Jan-17 08:00 AM 11-Feb-17 05:00 PM 0.00 0.00 R.4 A1350 Install 1st Floor Sheathing A1340 3.00 13-Feb-17 08:00 AM 15-Feb-17 05:00 PM 13-Feb-17 08:00 AM 15-Feb-17 05:00 PM 0.00 0.00 A1360 Install 2nd Floor Sheathing A1350 3.00 16-Feb-17 08:00 AM 18-Feb-17 05:00 PM 16-Feb-17 08:00 AM 18-Feb-17 05:00 PM 0.00 0.00 A1370 Install roof decking A1330 3.00 11-Feb-17 08:00 AM 14-Feb-17 05:00 PM 16-Feb-17 08:00 AM 18-Feb-17 05:00 PM 4.00 0.00 A1380 Install felt, flashing, and shingles A1440 3.00 25-Feb-17 08:00 AM 28-Feb-17 05:00 PM 25-Feb-17 08:00 AM 28-Feb-17 05:00 PM 0.00 0.00 A1390 Hang 1st floor exterior doors A1380 1.00 01-Mar-17 08:00 AM 01-Mar-17 05:00 PM 01-Mar-17 08:00 AM 01-Mar-17 05:00 PM 0.00 0.00 Abhishek Singh © Oracle Corporation Page 3 of 9
  • 6. Grouped by WBS and Sorted by Activity ID WBS Activity ID Activity Name Predecessors Original Duration Early Start Early Finish Late Start Late Finish Total Float Free Float A1400 Install 1st floor windows A1390 3.00 02-Mar-17 08:00 AM 04-Mar-17 05:00 PM 02-Mar-17 08:00 AM 04-Mar-17 05:00 PM 0.00 0.00 A1410 Install 2nd floor windows A1400 3.00 06-Mar-17 08:00 AM 08-Mar-17 05:00 PM 06-Mar-17 08:00 AM 08-Mar-17 05:00 PM 0.00 0.00 Subtotal 22.00 11-Feb-17 08:00 AM 08-Mar-17 05:00 PM 13-Feb-17 08:00 AM 08-Mar-17 05:00 PM 0.00 0.00 R.6 A1420 Complete Exterior Brick A1410 16.00 09-Mar-17 08:00 AM 27-Mar-17 05:00 PM 13-Mar-17 08:00 AM 30-Mar-17 05:00 PM 3.00 0.00 A1430 Complete exterior siding A1420 3.00 28-Mar-17 08:00 AM 30-Mar-17 05:00 PM 31-Mar-17 08:00 AM 03-Apr-17 05:00 PM 3.00 0.00 Subtotal 19.00 09-Mar-17 08:00 AM 30-Mar-17 05:00 PM 13-Mar-17 08:00 AM 03-Apr-17 05:00 PM 3.00 0.00 R.7 A1440 Rough-in-plumbing A1370, A1360 5.00 20-Feb-17 08:00 AM 24-Feb-17 05:00 PM 20-Feb-17 08:00 AM 24-Feb-17 05:00 PM 0.00 0.00 A1450 Conduct Rough-in-plumbing inspection A1440 1.00 25-Feb-17 08:00 AM 25-Feb-17 05:00 PM 18-Mar-17 08:00 AM 18-Mar-17 05:00 PM 18.00 0.00 A1460 Place concrete for basement floor A1450 11.00 27-Feb-17 08:00 AM 10-Mar-17 05:00 PM 04-Apr-17 08:00 AM 15-Apr-17 05:00 PM 31.00 31.00 A1470 Rough-in electrical A1370, A1360 5.00 20-Feb-17 08:00 AM 24-Feb-17 05:00 PM 27-Feb-17 08:00 AM 03-Mar-17 05:00 PM 6.00 0.00 A1480 Conduct Rough-in-electrical inspection A1470 1.00 25-Feb-17 08:00 AM 25-Feb-17 05:00 PM 04-Mar-17 08:00 AM 04-Mar-17 05:00 PM 6.00 0.00 A1490 Rough-in HVAC A1480 3.00 27-Feb-17 08:00 AM 01-Mar-17 05:00 PM 06-Mar-17 08:00 AM 08-Mar-17 05:00 PM 6.00 0.00 A1500 Conduct Rough-in-HVAC inspection A1490 1.00 02-Mar-17 08:00 AM 02-Mar-17 05:00 PM 28-Mar-17 08:00 AM 28-Mar-17 05:00 PM 22.00 22.00 Abhishek Singh © Oracle Corporation Page 4 of 9
  • 7. Grouped by WBS and Sorted by Activity ID WBS Activity ID Activity Name Predecessors Original Duration Early Start Early Finish Late Start Late Finish Total Float Free Float A1510 Rough-in communication - phone, cables, computer, alarm A1370 2.00 15-Feb-17 08:00 AM 16-Feb-17 05:00 PM 07-Mar-17 08:00 AM 08-Mar-17 05:00 PM 17.00 17.00 Subtotal 21.00 15-Feb-17 08:00 AM 10-Mar-17 05:00 PM 20-Feb-17 08:00 AM 15-Apr-17 05:00 PM 31.00 0.00 R.8 R.8.1 A1520 Place wall insulation - 1st floor A1350, A1360, A1470, A1490, A1510, A1410 1.00 09-Mar-17 08:00 AM 09-Mar-17 05:00 PM 09-Mar-17 08:00 AM 09-Mar-17 05:00 PM 0.00 0.00 A1530 Place wall insulation - 2nd floor A1520 1.00 10-Mar-17 08:00 AM 10-Mar-17 05:00 PM 08-Apr-17 08:00 AM 08-Apr-17 05:00 PM 25.00 1.00 A1540 Place ceiling insulation - 2nd floor A1530, A1590 1.00 17-Mar-17 08:00 AM 17-Mar-17 05:00 PM 14-Apr-17 08:00 AM 14-Apr-17 05:00 PM 24.00 0.00 A1550 Conduct insulation inspection A1540 1.00 18-Mar-17 08:00 AM 18-Mar-17 05:00 PM 15-Apr-17 08:00 AM 15-Apr-17 05:00 PM 24.00 24.00 Subtotal 9.00 09-Mar-17 08:00 AM 18-Mar-17 05:00 PM 09-Mar-17 08:00 AM 15-Apr-17 05:00 PM 24.00 0.00 R.8.2 A1560 Install Drywall - 1st floor walls A1520 2.00 08-Mar-17 08:00 AM 09-Mar-17 05:00 PM 08-Mar-17 08:00 AM 09-Mar-17 05:00 PM 0.00 0.00 A1570 Install drywall - 1st floor overhead A1560 2.00 10-Mar-17 08:00 AM 11-Mar-17 05:00 PM 10-Mar-17 08:00 AM 11-Mar-17 05:00 PM 0.00 0.00 A1580 Install drywall 2nd floor walls A1570, A1530 2.00 13-Mar-17 08:00 AM 14-Mar-17 05:00 PM 10-Apr-17 08:00 AM 11-Apr-17 05:00 PM 24.00 0.00 A1590 Install drywall 2nd floor overhead A1580 2.00 15-Mar-17 08:00 AM 16-Mar-17 05:00 PM 12-Apr-17 08:00 AM 13-Apr-17 05:00 PM 24.00 0.00 Abhishek Singh © Oracle Corporation Page 5 of 9
  • 8. Grouped by WBS and Sorted by Activity ID WBS Activity ID Activity Name Predecessors Original Duration Early Start Early Finish Late Start Late Finish Total Float Free Float A1600 Tape & Float 1st floor drywall A1570 1.00 13-Mar-17 08:00 AM 13-Mar-17 05:00 PM 13-Mar-17 08:00 AM 13-Mar-17 05:00 PM 0.00 0.00 A1610 Tape & Float 2nd floor drywall A1600, A1590 1.00 17-Mar-17 08:00 AM 17-Mar-17 05:00 PM 25-Apr-17 08:00 AM 25-Apr-17 05:00 PM 33.00 33.00 Subtotal 9.00 08-Mar-17 08:00 AM 17-Mar-17 05:00 PM 08-Mar-17 08:00 AM 25-Apr-17 05:00 PM 33.00 0.00 R.8.3 A1620 Texture all except entry & kitchen - 1st floor A1600 1.00 14-Mar-17 08:00 AM 14-Mar-17 05:00 PM 14-Mar-17 08:00 AM 14-Mar-17 05:00 PM 0.00 0.00 A1630 Paint all except entry & kitchen - 1st floor A1620 1.00 15-Mar-17 08:00 AM 15-Mar-17 05:00 PM 15-Mar-17 08:00 AM 15-Mar-17 05:00 PM 0.00 0.00 A1640 Hang wallpaper entry & kitchen - 1st floor A1630 1.00 16-Mar-17 08:00 AM 16-Mar-17 05:00 PM 16-Mar-17 08:00 AM 16-Mar-17 05:00 PM 0.00 0.00 A1650 Texture all - 2nd floor A1620 1.00 15-Mar-17 08:00 AM 15-Mar-17 05:00 PM 24-Apr-17 08:00 AM 24-Apr-17 05:00 PM 34.00 0.00 A1660 Paint all - 2nd floor A1650 1.00 16-Mar-17 08:00 AM 16-Mar-17 05:00 PM 25-Apr-17 08:00 AM 25-Apr-17 05:00 PM 34.00 34.00 A1670 Paint exterior siding & trim work A1430 4.00 31-Mar-17 08:00 AM 04-Apr-17 05:00 PM 04-Apr-17 08:00 AM 07-Apr-17 05:00 PM 3.00 0.00 Subtotal 19.00 14-Mar-17 08:00 AM 04-Apr-17 05:00 PM 14-Mar-17 08:00 AM 25-Apr-17 05:00 PM 18.00 0.00 R.8.4 A1680 Install 1st floor - kitchen cabinets A1640 2.00 17-Mar-17 08:00 AM 18-Mar-17 05:00 PM 17-Mar-17 08:00 AM 18-Mar-17 05:00 PM 0.00 0.00 A1690 Install 1st floor - master bath & guest cabinets A1680 1.00 20-Mar-17 08:00 AM 20-Mar-17 05:00 PM 20-Mar-17 08:00 AM 20-Mar-17 05:00 PM 0.00 0.00 A1700 Install 2nd floor - hall bath & provate bath cabinets A1690 1.00 21-Mar-17 08:00 AM 21-Mar-17 05:00 PM 22-Mar-17 08:00 AM 22-Mar-17 05:00 PM 1.00 0.00 Abhishek Singh © Oracle Corporation Page 6 of 9
  • 9. Grouped by WBS and Sorted by Activity ID WBS Activity ID Activity Name Predecessors Original Duration Early Start Early Finish Late Start Late Finish Total Float Free Float A1710 install chair rails, crown moldings, trim A1700 2.00 22-Mar-17 08:00 AM 23-Mar-17 05:00 PM 14-Apr-17 08:00 AM 15-Apr-17 05:00 PM 20.00 20.00 Subtotal 6.00 17-Mar-17 08:00 AM 23-Mar-17 05:00 PM 17-Mar-17 08:00 AM 15-Apr-17 05:00 PM 20.00 0.00 R.8.5 A1720 Complete 1st floor - kitchen plumbing A1450, A1680 1.00 20-Mar-17 08:00 AM 20-Mar-17 05:00 PM 20-Mar-17 08:00 AM 20-Mar-17 05:00 PM 0.00 0.00 A1730 Complete 1st floor - master bath & guest plumbing A1690, A1720 2.00 21-Mar-17 08:00 AM 22-Mar-17 05:00 PM 21-Mar-17 08:00 AM 22-Mar-17 05:00 PM 0.00 0.00 A1740 Complete 2nd floor - hall bath & private bath plumbing A1730, A1700 2.00 23-Mar-17 08:00 AM 24-Mar-17 05:00 PM 23-Mar-17 08:00 AM 24-Mar-17 05:00 PM 0.00 0.00 A1750 Conduct finish plumbing inspection A1740 1.00 25-Mar-17 08:00 AM 25-Mar-17 05:00 PM 25-Mar-17 08:00 AM 25-Mar-17 05:00 PM 0.00 0.00 Subtotal 6.00 20-Mar-17 08:00 AM 25-Mar-17 05:00 PM 20-Mar-17 08:00 AM 25-Mar-17 05:00 PM 0.00 0.00 R.8.6 A1760 Complete 1st Floor circuits to service panel A1480, A1740 1.00 25-Mar-17 08:00 AM 25-Mar-17 05:00 PM 29-Mar-17 08:00 AM 29-Mar-17 05:00 PM 3.00 0.00 A1770 Complete 2nd Floor circuits to service panel A1760 1.00 27-Mar-17 08:00 AM 27-Mar-17 05:00 PM 30-Mar-17 08:00 AM 30-Mar-17 05:00 PM 3.00 0.00 A1780 Conduct finish electrical inspection A1770 1.00 28-Mar-17 08:00 AM 28-Mar-17 05:00 PM 31-Mar-17 08:00 AM 31-Mar-17 05:00 PM 3.00 3.00 A1790 Complete communications wiring - phone, cable, computer alarm A1750 2.00 27-Mar-17 08:00 AM 28-Mar-17 05:00 PM 27-Mar-17 08:00 AM 28-Mar-17 05:00 PM 0.00 0.00 Subtotal 3.00 25-Mar-17 08:00 AM 28-Mar-17 05:00 PM 27-Mar-17 08:00 AM 31-Mar-17 05:00 PM 3.00 0.00 Abhishek Singh © Oracle Corporation Page 7 of 9
  • 10. Grouped by WBS and Sorted by Activity ID WBS Activity ID Activity Name Predecessors Original Duration Early Start Early Finish Late Start Late Finish Total Float Free Float R.8.7 A1800 Complete 1st floor - zone 1 HVAC A1500, A1790 1.00 29-Mar-17 08:00 AM 29-Mar-17 05:00 PM 29-Mar-17 08:00 AM 29-Mar-17 05:00 PM 0.00 0.00 A1810 Complete 2nd floor - zone 2 HVAC A1800 1.00 30-Mar-17 08:00 AM 30-Mar-17 05:00 PM 30-Mar-17 08:00 AM 30-Mar-17 05:00 PM 0.00 0.00 A1820 Conduct HVAC inspection A1810 1.00 31-Mar-17 08:00 AM 31-Mar-17 05:00 PM 31-Mar-17 08:00 AM 31-Mar-17 05:00 PM 0.00 0.00 Subtotal 3.00 29-Mar-17 08:00 AM 31-Mar-17 05:00 PM 29-Mar-17 08:00 AM 31-Mar-17 05:00 PM 0.00 0.00 R.8.8 A1830 Tile entry, kitchen & bath A1780, A1820 3.00 01-Apr-17 08:00 AM 04-Apr-17 05:00 PM 01-Apr-17 08:00 AM 04-Apr-17 05:00 PM 0.00 0.00 A1840 Carpet 1st floor A1830 2.00 05-Apr-17 08:00 AM 06-Apr-17 05:00 PM 05-Apr-17 08:00 AM 06-Apr-17 05:00 PM 0.00 0.00 A1850 Carpet 2nd floor A1840 2.00 07-Apr-17 08:00 AM 08-Apr-17 05:00 PM 07-Apr-17 08:00 AM 08-Apr-17 05:00 PM 0.00 0.00 A1860 InstallAppliances A1850 1.00 10-Apr-17 08:00 AM 10-Apr-17 05:00 PM 10-Apr-17 08:00 AM 10-Apr-17 05:00 PM 0.00 0.00 Subtotal 8.00 01-Apr-17 08:00 AM 10-Apr-17 05:00 PM 01-Apr-17 08:00 AM 10-Apr-17 05:00 PM 0.00 0.00 Subtotal 29.00 08-Mar-17 08:00 AM 10-Apr-17 05:00 PM 08-Mar-17 08:00 AM 25-Apr-17 05:00 PM 13.00 0.00 R.9 A1870 Pour concrete driveway and sidewalks A1670 2.00 05-Apr-17 08:00 AM 06-Apr-17 05:00 PM 08-Apr-17 08:00 AM 10-Apr-17 05:00 PM 3.00 3.00 A1880 Install backyard fence A1870, A1860 2.00 11-Apr-17 08:00 AM 12-Apr-17 05:00 PM 11-Apr-17 08:00 AM 12-Apr-17 05:00 PM 0.00 0.00 Abhishek Singh © Oracle Corporation Page 8 of 9
  • 11. Grouped by WBS and Sorted by Activity ID WBS Activity ID Activity Name Predecessors Original Duration Early Start Early Finish Late Start Late Finish Total Float Free Float A1890 Sod & complete plantings - frontyard A1880 2.00 13-Apr-17 08:00 AM 14-Apr-17 05:00 PM 13-Apr-17 08:00 AM 14-Apr-17 05:00 PM 0.00 0.00 A1900 Sod & complete plantings - backyard A1890 1.00 15-Apr-17 08:00 AM 15-Apr-17 05:00 PM 15-Apr-17 08:00 AM 15-Apr-17 05:00 PM 0.00 0.00 Subtotal 10.00 05-Apr-17 08:00 AM 15-Apr-17 05:00 PM 08-Apr-17 08:00 AM 15-Apr-17 05:00 PM 0.00 0.00 R.5 A1910 Complete final inspection for certificate of occupancy A1900, A1820, A1780, A1750, A1710, A1550, A1460 1.00 17-Apr-17 08:00 AM 17-Apr-17 05:00 PM 17-Apr-17 08:00 AM 17-Apr-17 05:00 PM 0.00 0.00 A1920 Cleanup for occupancy A1860, A1910 1.00 18-Apr-17 08:00 AM 18-Apr-17 05:00 PM 18-Apr-17 08:00 AM 18-Apr-17 05:00 PM 0.00 0.00 A1930 Perform final walk - through inspection A1920 1.00 19-Apr-17 08:00 AM 19-Apr-17 05:00 PM 19-Apr-17 08:00 AM 19-Apr-17 05:00 PM 0.00 0.00 A1940 Complete punch list items A1930 5.00 20-Apr-17 08:00 AM 25-Apr-17 05:00 PM 20-Apr-17 08:00 AM 25-Apr-17 05:00 PM 0.00 0.00 Subtotal 8.00 17-Apr-17 08:00 AM 25-Apr-17 05:00 PM 17-Apr-17 08:00 AM 25-Apr-17 05:00 PM 0.00 0.00 Subtotal 151.00 01-Nov-16 08:00 AM 25-Apr-17 05:00 PM 01-Nov-16 08:00 AM 25-Apr-17 05:00 PM 0.00 0.00 Abhishek Singh © Oracle Corporation Page 9 of 9
  • 12. 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08 October 2016 November 2016 December 2016 January 2017 February 2017 March 2017 April 2017 May 2017 25-Apr-17 05:00 PM, Residential Constructio 25-Nov-16 05:00 PM, General Conditions Finalize Plans & Develop estimate with owner, architect Sign Contract & Notice to proceed 25-Nov-16 05:00 PM, Apply For Permits Secure Foundation Permit Secure Framing Permit Secure Electrical Permit Secure Plumbing Permit Secure HVAC Permit Secure miscellaneous permits 29-Nov-16 05:00 PM, Site Work Clear and grub lot Install temporary power service Install underground utilities 17-Jan-17 05:00 PM, Foundation Excavate for foundations Form basement walls Place concrete for foundations & basement walls Cure basement walls for 7 days Strip basement wall forms Waterproof / insulate bsement walls Perform foundation inspection Backfill foundation 11-Feb-17 05:00 PM, Framing Install 1st floor joists Lay 1st floor decking Frame 1st floor walls Frame 1st floor corners Install 2nd floor joist Frame 2nd Floor decking Frame 2nd floor walls Frame 2nd floor corners Complete roof framing Conduct framing inspection 08-Mar-17 05:00 PM, Dry In Install 1st Floor Sheathing Install 2nd Floor Sheathing Install roof decking Install felt, flashing, and shingles Hang 1st floor exterior doors Install 1st floor windows Install 2nd floor windows 30-Mar-17 05:00 PM, Exterior Finishes Complete Exterior Brick Complete exterior siding 10-Mar-17 05:00 PM, Utility Rough B97Ins and Complete Concrete Rough-in-plumbing Abhishek Singh Gantt Chart for Activities Grouped by WBS and Sorted by Activity ID Actual Level of Effort Primary Baseline Actual Work Remaining Work Critical Remaining Work Milestone Page 1 of 3 TASK filter: All Activities © Oracle Corporation
  • 13. 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08 October 2016 November 2016 December 2016 January 2017 February 2017 March 2017 April 2017 May 2017 Conduct Rough-in-plumbing inspection Place concrete for basement floor Rough-in electrical Conduct Rough-in-electrical inspection Rough-in HVAC Conduct Rough-in-HVAC inspection Rough-in communication - phone, cables, computer, alarm 10-Apr-17 05:00 PM, Interior Finishes 18-Mar-17 05:00 PM, Insulation Place wall insulation - 1st floor Place wall insulation - 2nd floor Place ceiling insulation - 2nd floor Conduct insulation inspection 17-Mar-17 05:00 PM, Drywall Install Drywall - 1st floor walls Install drywall - 1st floor overhead Install drywall 2nd floor walls Install drywall 2nd floor overhead Tape & Float 1st floor drywall Tape & Float 2nd floor drywall 04-Apr-17 05:00 PM, Paint & Wall Paper Texture all except entry & kitchen - 1st floor Paint all except entry & kitchen - 1st floor Hang wallpaper entry & kitchen - 1st floor Texture all - 2nd floor Paint all - 2nd floor Paint exterior siding & trim work 23-Mar-17 05:00 PM, Cabinets Install 1st floor - kitchen cabinets Install 1st floor - master bath & guest cabinets Install 2nd floor - hall bath & provate bath cabinets install chair rails, crown moldings, trim 25-Mar-17 05:00 PM, Finish Plumbing Complete 1st floor - kitchen plumbing Complete 1st floor - master bath & guest plumbing Complete 2nd floor - hall bath & private bath plumbing Conduct finish plumbing inspection 28-Mar-17 05:00 PM, FInish Electrical Complete 1st Floor circuits to service panel Complete 2nd Floor circuits to service panel Conduct finish electrical inspection Complete communications wiring - phone, cable, computer alarm 31-Mar-17 05:00 PM, Finish HVAC Complete 1st floor - zone 1 HVAC Complete 2nd floor - zone 2 HVAC Conduct HVAC inspection 10-Apr-17 05:00 PM, Carpet, Tile & Appliances Tile entry, kitchen & bath Carpet 1st floor Carpet 2nd floor Abhishek Singh Gantt Chart for Activities Grouped by WBS and Sorted by Activity ID Actual Level of Effort Primary Baseline Actual Work Remaining Work Critical Remaining Work Milestone Page 2 of 3 TASK filter: All Activities © Oracle Corporation
  • 14. 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08 October 2016 November 2016 December 2016 January 2017 February 2017 March 2017 April 2017 May 2017 InstallAppliances 15-Apr-17 05:00 PM, Landscping and Grounds Work Pour concrete driveway and sidewalks Install backyard fence Sod & complete plantings - frontyard Sod & complete plantings - backyard 25-Apr-17 05:00 PM, FinalAcceptance Complete final inspection for certificate of occupancy Cleanup for occupancy Perform final walk - through inspection Complete punch list items Abhishek Singh Gantt Chart for Activities Grouped by WBS and Sorted by Activity ID Actual Level of Effort Primary Baseline Actual Work Remaining Work Critical Remaining Work Milestone Page 3 of 3 TASK filter: All Activities © Oracle Corporation
  • 15. Project: R Residential Construction WBS: R.1 General Conditions WBS: R.S Site Work WBS: R.2 Foundation WBS: R.3 Framing WBS: R.4 Dry In WBS: R.6 Exterior Finishes WBS: R.7 Utility Rough B97Ins and Complete Concrete WBS: R.8 Interior Finishes WBS: R.9 Landscping and Grounds Work WBS: R.5 Final Acceptance WBS: R.1.1 Apply For Permits WBS: R.8.1 Insulation WBS: R.8.2 Drywall WBS: R.8.3 Paint & Wall Paper WBS: R.8.4 Cabinets WBS: R.8.5 Finish Plumbing WBS: R.8.6 FInish Electrical WBS: R.8.7 Finish HVAC WBS: R.8.8 Carpet, Tile &Appliances A1010 Sign Cont ract & Notice to proc eed A 1000 F inalize P lans & Dev elop estimate with owner, arc hitect A1160 Secure miscellaneous perm its A1150 Secure HVA C Permit A1140 Secure Plum bing Permit A1130 Secure Elec trical Permit A1120 Secure Fr aming Permit A1110 Secure Foundat ion Permit A1040 Inst all underground utilities A1030 Inst all temporary power serv ice A1020 Clear and grublot A1240 Backf ill f oundation A1230 Perf orm f oundation inspect ion A1220 Waterproof / ins ulate bsement walls A 1210 S trip basement wall f orm s A 1200 Cure basement walls f or 7 day s A1190 Pl ace concr et e f or f oundations & basem ent walls A1180 Form basement walls A1170 Excav ate f or f oundations A1340 Conduct f raming inspect ion A1330 Com plete roof f raming A1320 Frame 2nd f loor corners A 1310 F rame 2nd f loor walls A 1300 F rame 2nd Floor decking A1290 Inst all 2nd f loor joist A1280 Frame 1st f loor corners A1270 Frame 1st f loor walls A1260 Lay 1st f loor decking A1250 Inst all 1st f loor joists A 1410 I nst all 2nd f loor windows A 1400 Inst all 1st f loor windows A1390 Hang 1s t f loor exterior doors A1380 Inst all f elt, fl ashing, and shingles A1360 Inst all 2nd Floor Sheathing A1350 Inst all 1st Floor Sheathing A1370 Inst all roof decking A1430 Com plete ext erior siding A1420 Com plete Exterior Brick A1440 Rough-in-plumbing A1510 Rough-in communication - phone, cables, A 1500 Conduct Rough-in-HVA C inspection A1490 Rough-in HVA C A1480 Conduct Rough-in-electrical inspection A1470 Rough-in elect rical A1460 Pl ace concr et e f or basem ent f loor A1450 Conduct Rough-in-plumbing inspection A1520 Place wall ins ulat ion - 1st f loor A1550 Conduct insulation inspection A1540 Place ceiling insulation - 2nd f loor A1530 Place wall ins ulation - 2nd f loor A1600 Tape & F loat 1st f loor dry wall A1570 Inst all dry wall - 1st f loor over head A1560 Inst all Drywall - 1st f loor walls A1610 Tape & Float 2nd floor dry wall A1590 Inst all dry wall 2nd f loor ov erhead A1580 Inst all dry wall 2nd f loor walls A1640 Hang wallpaper entry & kitchen - 1s t f loor A1630 Paint all except entry & kit chen - 1st f loor A1620 Texture all except entry & kit chen - 1st f loor A1670 Paint exteri or siding & trim wor k A1660 Paint all - 2nd f loor A1650 Texture all - 2nd f loor A 1690 Inst all 1st f loor - mas ter bath & gues t cabinets A 1680 Inst all 1st f loor - kitchen cabinets A1710 install chair rails , crown moldings, trim A 1700 I nst all 2nd f loor - hall bath & prov ate bath cabinets A1750 Conduct f inish plum bing inspect ion A1740 Com plete 2nd f loor - hall bath & pr iv at e bath plum bing A 1730 Com plete 1st f loor - mas ter bath & gues t plum bing A 1720 Com plete 1st f loor - kitchen plumbing A1790 Com plete communications wiring - phone, cable, A1780 Conduct f inish elect rical inspection A1770 Com plete 2nd F loor circuits to servi ce panel A1760 Com plete 1st F loor circuit s t o service panel A1820 Conduct HVAC inspection A1810 Complete 2nd f loor - zone 2 HVAC A1800 Complete 1st floor - zone 1 HVAC A 1860 I nst all Appliances A 1850 Carpet 2nd floor A 1840 Carpet 1st f loor A1830 Tile entry, kitchen & bath A1900 Sod & com plete plant ings - backy ard A1890 Sod & com plete plant ings - f ronty ard A1880 Inst all bac ky ard f enc e A1870 Pour concrete driv eway and sidewalks A1940 Complete punch list items A1930 Perf orm f inal walk - through inspection A1920 Cleanup f or occupancy A1910 Complete f inal inspection f or cert if icate of Abhishek Singh Activity Network Layout Activity ID Activity Name Page 1 of 2 © Oracle Corporation
  • 16. Activity ID Activity Name Original Duration Residential ConstructionResidential Construction 151.00 General ConditionsGeneral Conditions 22.00 A1000 Finalize Plans & Develop estimate with owner, architect20.00 A1010 Sign Contract & Notice to proceed 1.00 Apply For PermitsApply For Permits 1.00 A1110 Secure Foundation Permit 1.00 A1120 Secure Framing Permit 1.00 A1130 Secure Electrical Permit 1.00 A1140 Secure Plumbing Permit 1.00 A1150 Secure HVAC Permit 1.00 A1160 Secure miscellaneous permits 1.00 Site WorkSite Work 3.00 A1020 Clear and grub lot 1.00 A1030 Install temporary power service 1.00 A1040 Install underground utilities 1.00 FoundationFoundation 42.00 A1170 Excavate for foundations 3.00 A1180 Form basement walls 13.00 A1190 Place concrete for foundations & basement walls12.00 A1200 Cure basement walls for 7 days 7.00 A1210 Strip basement wall forms 2.00 A1220 Waterproof / insulate bsement walls 2.00 A1230 Perform foundation inspection 1.00 A1240 Backfill foundation 2.00 FramingFraming 22.00 A1250 Install 1st floor joists 2.00 A1260 Lay 1st floor decking 2.00 A1270 Frame 1st floor walls 4.00 A1280 Frame 1st floor corners 1.00 A1290 Install 2nd floor joist 2.00 A1300 Frame 2nd Floor decking 2.00 A1310 Frame 2nd floor walls 3.00 A1320 Frame 2nd floor corners 2.00 A1330 Complete roof framing 3.00 A1340 Conduct framing inspection 1.00 Dry InDry In 21.00 A1350 Install 1st Floor Sheathing 3.00 A1360 Install 2nd Floor Sheathing 3.00 A1380 Install felt, flashing, and shingles 3.00 A1390 Hang 1st floor exterior doors 1.00 A1400 Install 1st floor windows 3.00 A1410 Install 2nd floor windows 3.00 Exterior FinishesExterior Finishes 0.00 Utility Rough B97Ins and Complete ConcreteUtility Rough B97Ins and Complete Concrete5.00 A1440 Rough-in-plumbing 5.00 Interior FinishesInterior Finishes 29.00 InsulationInsulation 1.00 A1520 Place wall insulation - 1st floor 1.00 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08 October 2016 November 2016 December 2016 January 2017 February 2017 March 2017 April 2017 May 2017 25-Apr-17 05:00 PM, Residential Cons 25-Nov-16 05:00 PM, General Conditions Finalize Plans & Develop estimate with owner, architect Sign Contract & Notice to proceed 25-Nov-16 05:00 PM, Apply For Permits Secure Foundation Permit Secure Framing Permit Secure Electrical Permit Secure Plumbing Permit Secure HVAC Permit Secure miscellaneous permits 29-Nov-16 05:00 PM, Site Work Clear and grub lot Install temporary power service Install underground utilities 17-Jan-17 05:00 PM, Foundation Excavate for foundations Form basement walls Place concrete for foundations & basement walls Cure basement walls for 7 days Strip basement wall forms Waterproof / insulate bsement walls Perform foundation inspection Backfill foundation 11-Feb-17 05:00 PM, Framing Install 1st floor joists Lay 1st floor decking Frame 1st floor walls Frame 1st floor corners Install 2nd floor joist Frame 2nd Floor decking Frame 2nd floor walls Frame 2nd floor corners Complete roof framing Conduct framing inspection 08-Mar-17 05:00 PM, Dry In Install 1st Floor Sheathing Install 2nd Floor Sheathing Install felt, flashing, and shingles Hang 1st floor exterior doors Install 1st floor windows Install 2nd floor windows 24-Feb-17 05:00 PM, Utility Rough B97Ins and Complete Concrete Rough-in-plumbing 10-Apr-17 05:00 PM, Interior Finishes 09-Mar-17 05:00 PM, Insulation Place wall insulation - 1st floor Abhishek Singh Activity Table and Gantt Chart for Critical Path Activities Page 1 of 2 TASK filter: Critical. © Oracle Corporation
  • 17. Activity ID Activity Name Original Duration DrywallDrywall 5.00 A1560 Install Drywall - 1st floor walls 2.00 A1570 Install drywall - 1st floor overhead 2.00 A1600 Tape & Float 1st floor drywall 1.00 Paint & Wall PaperPaint & Wall Paper 3.00 A1620 Texture all except entry & kitchen - 1st floor 1.00 A1630 Paint all except entry & kitchen - 1st floor 1.00 A1640 Hang wallpaper entry & kitchen - 1st floor 1.00 CabinetsCabinets 3.00 A1680 Install 1st floor - kitchen cabinets 2.00 A1690 Install 1st floor - master bath & guest cabinets 1.00 Finish PlumbingFinish Plumbing 6.00 A1720 Complete 1st floor - kitchen plumbing 1.00 A1730 Complete 1st floor - master bath & guest plumbing2.00 A1740 Complete 2nd floor - hall bath & private bath plumbing2.00 A1750 Conduct finish plumbing inspection 1.00 FInish ElectricalFInish Electrical 2.00 A1790 Complete communications wiring - phone, cable, computer alarm2.00 Finish HVACFinish HVAC 3.00 A1800 Complete 1st floor - zone 1 HVAC 1.00 A1810 Complete 2nd floor - zone 2 HVAC 1.00 A1820 Conduct HVAC inspection 1.00 Carpet, Tile & AppliancesCarpet, Tile & Appliances 8.00 A1830 Tile entry, kitchen & bath 3.00 A1840 Carpet 1st floor 2.00 A1850 Carpet 2nd floor 2.00 A1860 InstallAppliances 1.00 Landscping and Grounds WorkLandscping and Grounds Work 5.00 A1880 Install backyard fence 2.00 A1890 Sod & complete plantings - frontyard 2.00 A1900 Sod & complete plantings - backyard 1.00 Final AcceptanceFinal Acceptance 8.00 A1910 Complete final inspection for certificate of occupancy1.00 A1920 Cleanup for occupancy 1.00 A1930 Perform final walk - through inspection 1.00 A1940 Complete punch list items 5.00 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08 October 2016 November 2016 December 2016 January 2017 February 2017 March 2017 April 2017 May 2017 13-Mar-17 05:00 PM, Drywall Install Drywall - 1st floor walls Install drywall - 1st floor overhead Tape & Float 1st floor drywall 16-Mar-17 05:00 PM, Paint & Wall Paper Texture all except entry & kitchen - 1st floor Paint all except entry & kitchen - 1st floor Hang wallpaper entry & kitchen - 1st floor 20-Mar-17 05:00 PM, Cabinets Install 1st floor - kitchen cabinets Install 1st floor - master bath & guest cabinets 25-Mar-17 05:00 PM, Finish Plumbing Complete 1st floor - kitchen plumbing Complete 1st floor - master bath & guest plumbing Complete 2nd floor - hall bath & private bath plumbing Conduct finish plumbing inspection 28-Mar-17 05:00 PM, FInish Electrical Complete communications wiring - phone, cable, computer alarm 31-Mar-17 05:00 PM, Finish HVAC Complete 1st floor - zone 1 HVAC Complete 2nd floor - zone 2 HVAC Conduct HVAC inspection 10-Apr-17 05:00 PM, Carpet, Tile & Appliances Tile entry, kitchen & bath Carpet 1st floor Carpet 2nd floor InstallAppliances 15-Apr-17 05:00 PM, Landscping and Grounds Wo Install backyard fence Sod & complete plantings - frontyard Sod & complete plantings - backyard 25-Apr-17 05:00 PM, FinalAcceptance Complete final inspection for certificate of occupa Cleanup for occupancy Perform final walk - through inspection Complete punch list items Abhishek Singh Activity Table and Gantt Chart for Critical Path Activities Page 2 of 2 TASK filter: Critical. © Oracle Corporation
  • 18. 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08 October 2016 November 2016 December 2016 January 2017 February 2017 March 2017 April 2017 May 2017 25-Apr-17 05:00 PM, Residential Constructio 25-Nov-16 05:00 PM, General Conditions Finalize Plans & Develop estimate with owner, architect Sign Contract & Notice to proceed 25-Nov-16 05:00 PM, Apply For Permits Secure Foundation Permit Secure Framing Permit Secure Electrical Permit Secure Plumbing Permit Secure HVAC Permit Secure miscellaneous permits 29-Nov-16 05:00 PM, Site Work Clear and grub lot Install temporary power service Install underground utilities 17-Jan-17 05:00 PM, Foundation Excavate for foundations Form basement walls Place concrete for foundations & basement walls Cure basement walls for 7 days Strip basement wall forms Waterproof / insulate bsement walls Perform foundation inspection Backfill foundation 11-Feb-17 05:00 PM, Framing Install 1st floor joists Lay 1st floor decking Frame 1st floor walls Frame 1st floor corners Install 2nd floor joist Frame 2nd Floor decking Frame 2nd floor walls Frame 2nd floor corners Complete roof framing Conduct framing inspection 08-Mar-17 05:00 PM, Dry In Install 1st Floor Sheathing Install 2nd Floor Sheathing Install felt, flashing, and shingles Hang 1st floor exterior doors Install 1st floor windows Install 2nd floor windows 24-Feb-17 05:00 PM, Utility Rough B97Ins and Complete Concrete Rough-in-plumbing 10-Apr-17 05:00 PM, Interior Finishes 09-Mar-17 05:00 PM, Insulation Place wall insulation - 1st floor Abhishek Singh Critical Path Activities Page 1 of 2 TASK filter: Critical. © Oracle Corporation
  • 19. 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08 October 2016 November 2016 December 2016 January 2017 February 2017 March 2017 April 2017 May 2017 13-Mar-17 05:00 PM, Drywall Install Drywall - 1st floor walls Install drywall - 1st floor overhead Tape & Float 1st floor drywall 16-Mar-17 05:00 PM, Paint & Wall Paper Texture all except entry & kitchen - 1st floor Paint all except entry & kitchen - 1st floor Hang wallpaper entry & kitchen - 1st floor 20-Mar-17 05:00 PM, Cabinets Install 1st floor - kitchen cabinets Install 1st floor - master bath & guest cabinets 25-Mar-17 05:00 PM, Finish Plumbing Complete 1st floor - kitchen plumbing Complete 1st floor - master bath & guest plumbing Complete 2nd floor - hall bath & private bath plumbing Conduct finish plumbing inspection 28-Mar-17 05:00 PM, FInish Electrical Complete communications wiring - phone, cable, computer alarm 31-Mar-17 05:00 PM, Finish HVAC Complete 1st floor - zone 1 HVAC Complete 2nd floor - zone 2 HVAC Conduct HVAC inspection 10-Apr-17 05:00 PM, Carpet, Tile & Appliances Tile entry, kitchen & bath Carpet 1st floor Carpet 2nd floor InstallAppliances 15-Apr-17 05:00 PM, Landscping and Grounds Work Install backyard fence Sod & complete plantings - frontyard Sod & complete plantings - backyard 25-Apr-17 05:00 PM, FinalAcceptance Complete final inspection for certificate of occupancy Cleanup for occupancy Perform final walk - through inspection Complete punch list items Abhishek Singh Critical Path Activities Page 2 of 2 TASK filter: Critical. © Oracle Corporation
  • 20. Activity ID Activity Name Original Duration Free FloatRemaining Duration Residential ConstructionResidential Construction 151.00 0.00151.00 General ConditionsGeneral Conditions 22.00 0.0022.00 A1000 Finalize Plans & Develop estimate with owner, architect20.00 0.0020.00 A1010 Sign Contract & Notice to proceed 1.00 0.00 1.00 Apply For PermitsApply For Permits 1.00 0.00 1.00 A1110Secure Foundation Permit 1.00 0.00 1.00 A1120Secure Framing Permit 1.00 0.00 1.00 A1130Secure Electrical Permit 1.00 0.00 1.00 A1140Secure Plumbing Permit 1.00 0.00 1.00 A1150Secure HVAC Permit 1.00 0.00 1.00 A1160Secure miscellaneous permits 1.00 0.00 1.00 Site WorkSite Work 3.00 0.00 3.00 A1020 Clear and grub lot 1.00 0.00 1.00 A1030 Install temporary power service 1.00 0.00 1.00 A1040 Install underground utilities 1.00 0.00 1.00 FoundationFoundation 42.00 0.0042.00 A1170 Excavate for foundations 3.00 0.00 3.00 A1180 Form basement walls 13.00 0.0013.00 A1190 Place concrete for foundations & basement walls12.00 0.0012.00 A1200 Cure basement walls for 7 days 7.00 0.00 7.00 A1210 Strip basement wall forms 2.00 0.00 2.00 A1220 Waterproof / insulate bsement walls 2.00 0.00 2.00 A1230 Perform foundation inspection 1.00 0.00 1.00 A1240 Backfill foundation 2.00 0.00 2.00 FramingFraming 22.00 0.0022.00 A1250 Install 1st floor joists 2.00 0.00 2.00 A1260 Lay 1st floor decking 2.00 0.00 2.00 A1270 Frame 1st floor walls 4.00 0.00 4.00 A1280 Frame 1st floor corners 1.00 0.00 1.00 A1290 Install 2nd floor joist 2.00 0.00 2.00 A1300 Frame 2nd Floor decking 2.00 0.00 2.00 A1310 Frame 2nd floor walls 3.00 0.00 3.00 A1320 Frame 2nd floor corners 2.00 0.00 2.00 A1330 Complete roof framing 3.00 0.00 3.00 A1340 Conduct framing inspection 1.00 0.00 1.00 Dry InDry In 22.00 0.0022.00 A1370 Install roof decking 3.00 0.00 3.00 A1350 Install 1st Floor Sheathing 3.00 0.00 3.00 A1360 Install 2nd Floor Sheathing 3.00 0.00 3.00 A1380 Install felt, flashing, and shingles 3.00 0.00 3.00 A1390 Hang 1st floor exterior doors 1.00 0.00 1.00 A1400 Install 1st floor windows 3.00 0.00 3.00 A1410 Install 2nd floor windows 3.00 0.00 3.00 Exterior FinishesExterior Finishes 19.00 0.0019.00 A1420 Complete Exterior Brick 16.00 0.0016.00 A1430 Complete exterior siding 3.00 0.00 3.00 Utility Rough B97Ins and Complete ConcreteUtility Rough B97Ins and Complete Concrete21.00 0.0021.00 A1510 Rough-in communication - phone, cables, computer, alarm2.00 17.00 2.00 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08 October 2016 November 2016 December 2016 January 2017 February 2017 March 2017 April 2017 May 2017 25-Apr-17 05:00 PM, Residential Cons 25-Nov-16 05:00 PM, General Conditions Finalize Plans & Develop estimate with owner, architect Sign Contract & Notice to proceed 25-Nov-16 05:00 PM, Apply For Permits Secure Foundation Permit Secure Framing Permit Secure Electrical Permit Secure Plumbing Permit Secure HVAC Permit Secure miscellaneous permits 29-Nov-16 05:00 PM, Site Work Clear and grub lot Install temporary power service Install underground utilities 17-Jan-17 05:00 PM, Foundation Excavate for foundations Form basement walls Place concrete for foundations & basement walls Cure basement walls for 7 days Strip basement wall forms Waterproof / insulate bsement walls Perform foundation inspection Backfill foundation 11-Feb-17 05:00 PM, Framing Install 1st floor joists Lay 1st floor decking Frame 1st floor walls Frame 1st floor corners Install 2nd floor joist Frame 2nd Floor decking Frame 2nd floor walls Frame 2nd floor corners Complete roof framing Conduct framing inspection 08-Mar-17 05:00 PM, Dry In Install roof decking Install 1st Floor Sheathing Install 2nd Floor Sheathing Install felt, flashing, and shingles Hang 1st floor exterior doors Install 1st floor windows Install 2nd floor windows 30-Mar-17 05:00 PM, Exterior Finishes Complete Exterior Brick Complete exterior siding 10-Mar-17 05:00 PM, Utility Rough B97Ins and Complete Concrete Rough-in communication - phone, cables, computer, alarm Abhishek Singh Gantt Chart Schedule for Activities Grouped by WBS and Sorted by Early Start and Free Float Actual Level of Effort Primary Baseline Actual Work Remaining Work Critical Remaining Work Milestone Page 1 of 3 TASK filter: All Activities © Oracle Corporation
  • 21. Activity ID Activity Name Original Duration Free FloatRemaining Duration A1440 Rough-in-plumbing 5.00 0.00 5.00 A1470 Rough-in electrical 5.00 0.00 5.00 A1450 Conduct Rough-in-plumbing inspection 1.00 0.00 1.00 A1480 Conduct Rough-in-electrical inspection 1.00 0.00 1.00 A1490 Rough-in HVAC 3.00 0.00 3.00 A1460 Place concrete for basement floor 11.00 31.0011.00 A1500 Conduct Rough-in-HVAC inspection 1.00 22.00 1.00 Interior FinishesInterior Finishes 29.00 0.0029.00 InsulationInsulation 9.00 0.00 9.00 A1520Place wall insulation - 1st floor 1.00 0.00 1.00 A1530Place wall insulation - 2nd floor 1.00 1.00 1.00 A1540Place ceiling insulation - 2nd floor 1.00 0.00 1.00 A1550Conduct insulation inspection 1.00 24.00 1.00 DrywallDrywall 9.00 0.00 9.00 A1560Install Drywall - 1st floor walls 2.00 0.00 2.00 A1570Install drywall - 1st floor overhead 2.00 0.00 2.00 A1580Install drywall 2nd floor walls 2.00 0.00 2.00 A1600Tape & Float 1st floor drywall 1.00 0.00 1.00 A1590Install drywall 2nd floor overhead 2.00 0.00 2.00 A1610Tape & Float 2nd floor drywall 1.00 33.00 1.00 Paint & Wall PaperPaint & Wall Paper 19.00 0.0019.00 A1620Texture all except entry & kitchen - 1st floor1.00 0.00 1.00 A1630Paint all except entry & kitchen - 1st floor 1.00 0.00 1.00 A1650Texture all - 2nd floor 1.00 0.00 1.00 A1640Hang wallpaper entry & kitchen - 1st floor1.00 0.00 1.00 A1660Paint all - 2nd floor 1.00 34.00 1.00 A1670Paint exterior siding & trim work 4.00 0.00 4.00 CabinetsCabinets 6.00 0.00 6.00 A1680Install 1st floor - kitchen cabinets 2.00 0.00 2.00 A1690Install 1st floor - master bath & guest cabinets1.00 0.00 1.00 A1700Install 2nd floor - hall bath & provate bath cabinets1.00 0.00 1.00 A1710install chair rails, crown moldings, trim 2.00 20.00 2.00 Finish PlumbingFinish Plumbing 6.00 0.00 6.00 A1720Complete 1st floor - kitchen plumbing 1.00 0.00 1.00 A1730Complete 1st floor - master bath & guest plumbing2.00 0.00 2.00 A1740Complete 2nd floor - hall bath & private bath plumbing2.00 0.00 2.00 A1750Conduct finish plumbing inspection 1.00 0.00 1.00 FInish ElectricalFInish Electrical 3.00 0.00 3.00 A1760Complete 1st Floor circuits to service panel1.00 0.00 1.00 A1770Complete 2nd Floor circuits to service panel1.00 0.00 1.00 A1790Complete communications wiring - phone, cable, computer alarm2.00 0.00 2.00 A1780Conduct finish electrical inspection 1.00 3.00 1.00 Finish HVACFinish HVAC 3.00 0.00 3.00 A1800Complete 1st floor - zone 1 HVAC 1.00 0.00 1.00 A1810Complete 2nd floor - zone 2 HVAC 1.00 0.00 1.00 A1820Conduct HVAC inspection 1.00 0.00 1.00 Carpet, Tile & AppliancesCarpet, Tile & Appliances 8.00 0.00 8.00 A1830Tile entry, kitchen & bath 3.00 0.00 3.00 A1840Carpet 1st floor 2.00 0.00 2.00 A1850Carpet 2nd floor 2.00 0.00 2.00 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08 October 2016 November 2016 December 2016 January 2017 February 2017 March 2017 April 2017 May 2017 Rough-in-plumbing Rough-in electrical Conduct Rough-in-plumbing inspection Conduct Rough-in-electrical inspection Rough-in HVAC Place concrete for basement floor Conduct Rough-in-HVAC inspection 10-Apr-17 05:00 PM, Interior Finishes 18-Mar-17 05:00 PM, Insulation Place wall insulation - 1st floor Place wall insulation - 2nd floor Place ceiling insulation - 2nd floor Conduct insulation inspection 17-Mar-17 05:00 PM, Drywall Install Drywall - 1st floor walls Install drywall - 1st floor overhead Install drywall 2nd floor walls Tape & Float 1st floor drywall Install drywall 2nd floor overhead Tape & Float 2nd floor drywall 04-Apr-17 05:00 PM, Paint & Wall Paper Texture all except entry & kitchen - 1st floor Paint all except entry & kitchen - 1st floor Texture all - 2nd floor Hang wallpaper entry & kitchen - 1st floor Paint all - 2nd floor Paint exterior siding & trim work 23-Mar-17 05:00 PM, Cabinets Install 1st floor - kitchen cabinets Install 1st floor - master bath & guest cabinets Install 2nd floor - hall bath & provate bath cabinets install chair rails, crown moldings, trim 25-Mar-17 05:00 PM, Finish Plumbing Complete 1st floor - kitchen plumbing Complete 1st floor - master bath & guest plumbing Complete 2nd floor - hall bath & private bath plumbing Conduct finish plumbing inspection 28-Mar-17 05:00 PM, FInish Electrical Complete 1st Floor circuits to service panel Complete 2nd Floor circuits to service panel Complete communications wiring - phone, cable, computer alarm Conduct finish electrical inspection 31-Mar-17 05:00 PM, Finish HVAC Complete 1st floor - zone 1 HVAC Complete 2nd floor - zone 2 HVAC Conduct HVAC inspection 10-Apr-17 05:00 PM, Carpet, Tile & Appliances Tile entry, kitchen & bath Carpet 1st floor Carpet 2nd floor Abhishek Singh Gantt Chart Schedule for Activities Grouped by WBS and Sorted by Early Start and Free Float Actual Level of Effort Primary Baseline Actual Work Remaining Work Critical Remaining Work Milestone Page 2 of 3 TASK filter: All Activities © Oracle Corporation
  • 22. Activity ID Activity Name Original Duration Free FloatRemaining Duration A1860InstallAppliances 1.00 0.00 1.00 Landscping and Grounds WorkLandscping and Grounds Work 10.00 0.0010.00 A1870 Pour concrete driveway and sidewalks 2.00 3.00 2.00 A1880 Install backyard fence 2.00 0.00 2.00 A1890 Sod & complete plantings - frontyard 2.00 0.00 2.00 A1900 Sod & complete plantings - backyard 1.00 0.00 1.00 Final AcceptanceFinal Acceptance 8.00 0.00 8.00 A1910 Complete final inspection for certificate of occupancy1.00 0.00 1.00 A1920 Cleanup for occupancy 1.00 0.00 1.00 A1930 Perform final walk - through inspection 1.00 0.00 1.00 A1940 Complete punch list items 5.00 0.00 5.00 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08 October 2016 November 2016 December 2016 January 2017 February 2017 March 2017 April 2017 May 2017 InstallAppliances 15-Apr-17 05:00 PM, Landscping and Grounds W Pour concrete driveway and sidewalks Install backyard fence Sod & complete plantings - frontyard Sod & complete plantings - backyard 25-Apr-17 05:00 PM, FinalAcceptance Complete final inspection for certificate of occup Cleanup for occupancy Perform final walk - through inspection Complete punch list items Abhishek Singh Gantt Chart Schedule for Activities Grouped by WBS and Sorted by Early Start and Free Float Actual Level of Effort Primary Baseline Actual Work Remaining Work Critical Remaining Work Milestone Page 3 of 3 TASK filter: All Activities © Oracle Corporation
  • 23. Report for the Budgeted Cost WBS Activity ID Activity Name Original Duration Budgeted Labor Cost Budgeted Material Cost Budgeted Total Cost R Residential Construction R.1 General Conditions A1000 Finalize Plans & Develop estimate with owner, architect 20.00 $5,220.00 $0.00 $5,220.00 A1010 Sign Contract & Notice to proceed 1.00 $750.00 $0.00 $750.00 R.1.1 Apply For Permits A1110 Secure Foundation Permit 1.00 $0.00 $0.00 $0.00 A1120 Secure Framing Permit 1.00 $0.00 $0.00 $0.00 A1130 Secure Electrical Permit 1.00 $0.00 $0.00 $0.00 A1140 Secure Plumbing Permit 1.00 $0.00 $0.00 $0.00 A1150 Secure HVAC Permit 1.00 $0.00 $0.00 $0.00 A1160 Secure miscellaneous permits 1.00 $0.00 $0.00 $0.00 Subtotal 1.00 $0.00 $0.00 $0.00 Subtotal 22.00 $5,970.00 $0.00 $5,970.00 R.S Site Work A1020 Clear and grub lot 1.00 $150.00 $0.00 $150.00 A1030 Install temporary power service 1.00 $150.00 $0.00 $150.00 A1040 Install underground utilities 1.00 $450.00 $0.00 $450.00 Subtotal 3.00 $750.00 $0.00 $750.00 R.2 Foundation Abhishek Singh Residential Building Project © Oracle Corporation Page 1 of 8
  • 24. Report for the Budgeted Cost WBS Activity ID Activity Name Original Duration Budgeted Labor Cost Budgeted Material Cost Budgeted Total Cost A1170 Excavate for foundations 3.00 $450.00 $0.00 $450.00 A1180 Form basement walls 13.00 $2,600.00 $0.00 $2,600.00 A1190 Place concrete for foundations & basement walls 12.00 $2,400.00 $0.00 $2,400.00 A1200 Cure basement walls for 7 days 7.00 $0.00 $0.00 $0.00 A1210 Strip basement wall forms 2.00 $400.00 $0.00 $400.00 A1220 Waterproof / insulate bsement walls 2.00 $400.00 $0.00 $400.00 A1230 Perform foundation inspection 1.00 $0.00 $500.00 $500.00 A1240 Backfill foundation 2.00 $300.00 $0.00 $300.00 Subtotal 42.00 $6,550.00 $500.00 $7,050.00 R.3 Framing A1250 Install 1st floor joists 2.00 $400.00 $0.00 $400.00 A1260 Lay 1st floor decking 2.00 $400.00 $0.00 $400.00 A1270 Frame 1st floor walls 4.00 $800.00 $0.00 $800.00 A1280 Frame 1st floor corners 1.00 $200.00 $0.00 $200.00 A1290 Install 2nd floor joist 2.00 $400.00 $0.00 $400.00 A1300 Frame 2nd Floor decking 2.00 $400.00 $0.00 $400.00 A1310 Frame 2nd floor walls 3.00 $600.00 $0.00 $600.00 A1320 Frame 2nd floor corners 2.00 $400.00 $0.00 $400.00 A1330 Complete roof framing 3.00 $600.00 $0.00 $600.00 A1340 Conduct framing inspection 1.00 $0.00 $500.00 $500.00 Subtotal 22.00 $4,200.00 $500.00 $4,700.00 Abhishek Singh Residential Building Project © Oracle Corporation Page 2 of 8
  • 25. Report for the Budgeted Cost WBS Activity ID Activity Name Original Duration Budgeted Labor Cost Budgeted Material Cost Budgeted Total Cost R.4 Dry In A1350 Install 1st Floor Sheathing 3.00 $600.00 $0.00 $600.00 A1360 Install 2nd Floor Sheathing 3.00 $600.00 $0.00 $600.00 A1370 Install roof decking 3.00 $600.00 $0.00 $600.00 A1380 Install felt, flashing, and shingles 3.00 $300.00 $0.00 $300.00 A1390 Hang 1st floor exterior doors 1.00 $200.00 $0.00 $200.00 A1400 Install 1st floor windows 3.00 $600.00 $0.00 $600.00 A1410 Install 2nd floor windows 3.00 $600.00 $0.00 $600.00 Subtotal 22.00 $3,500.00 $0.00 $3,500.00 R.6 Exterior Finishes A1420 Complete Exterior Brick 16.00 $2,400.00 $0.00 $2,400.00 A1430 Complete exterior siding 3.00 $600.00 $0.00 $600.00 Subtotal 19.00 $3,000.00 $0.00 $3,000.00 R.7 Utility Rough B97Ins and Complete Concrete A1440 Rough-in-plumbing 5.00 $1,500.00 $0.00 $1,500.00 A1450 Conduct Rough-in-plumbing inspection 1.00 $0.00 $500.00 $500.00 A1460 Place concrete for basement floor 11.00 $2,200.00 $0.00 $2,200.00 A1470 Rough-in electrical 5.00 $750.00 $0.00 $750.00 A1480 Conduct Rough-in-electrical inspection 1.00 $0.00 $500.00 $500.00 Abhishek Singh Residential Building Project © Oracle Corporation Page 3 of 8
  • 26. Report for the Budgeted Cost WBS Activity ID Activity Name Original Duration Budgeted Labor Cost Budgeted Material Cost Budgeted Total Cost A1490 Rough-in HVAC 3.00 $450.00 $0.00 $450.00 A1500 Conduct Rough-in-HVAC inspection 1.00 $0.00 $500.00 $500.00 A1510 Rough-in communication - phone, cables, computer, alarm 2.00 $300.00 $0.00 $300.00 Subtotal 21.00 $5,200.00 $1,500.00 $6,700.00 R.8 Interior Finishes R.8.1 Insulation A1520 Place wall insulation - 1st floor 1.00 $300.00 $0.00 $300.00 A1530 Place wall insulation - 2nd floor 1.00 $300.00 $0.00 $300.00 A1540 Place ceiling insulation - 2nd floor 1.00 $300.00 $0.00 $300.00 A1550 Conduct insulation inspection 1.00 $0.00 $500.00 $500.00 Subtotal 9.00 $900.00 $500.00 $1,400.00 R.8.2 Drywall A1560 Install Drywall - 1st floor walls 2.00 $400.00 $0.00 $400.00 A1570 Install drywall - 1st floor overhead 2.00 $400.00 $0.00 $400.00 A1580 Install drywall 2nd floor walls 2.00 $400.00 $0.00 $400.00 A1590 Install drywall 2nd floor overhead 2.00 $400.00 $0.00 $400.00 A1600 Tape & Float 1st floor drywall 1.00 $200.00 $0.00 $200.00 A1610 Tape & Float 2nd floor drywall 1.00 $200.00 $0.00 $200.00 Abhishek Singh Residential Building Project © Oracle Corporation Page 4 of 8
  • 27. Report for the Budgeted Cost WBS Activity ID Activity Name Original Duration Budgeted Labor Cost Budgeted Material Cost Budgeted Total Cost Subtotal 9.00 $2,000.00 $0.00 $2,000.00 R.8.3 Paint & Wall Paper A1620 Texture all except entry & kitchen - 1st floor 1.00 $100.00 $0.00 $100.00 A1630 Paint all except entry & kitchen - 1st floor 1.00 $100.00 $0.00 $100.00 A1640 Hang wallpaper entry & kitchen - 1st floor 1.00 $100.00 $0.00 $100.00 A1650 Texture all - 2nd floor 1.00 $100.00 $0.00 $100.00 A1660 Paint all - 2nd floor 1.00 $100.00 $0.00 $100.00 A1670 Paint exterior siding & trim work 4.00 $400.00 $0.00 $400.00 Subtotal 19.00 $900.00 $0.00 $900.00 R.8.4 Cabinets A1680 Install 1st floor - kitchen cabinets 2.00 $300.00 $0.00 $300.00 A1690 Install 1st floor - master bath & guest cabinets 1.00 $150.00 $0.00 $150.00 A1700 Install 2nd floor - hall bath & provate bath cabinets 1.00 $150.00 $0.00 $150.00 A1710 install chair rails, crown moldings, trim 2.00 $300.00 $0.00 $300.00 Subtotal 6.00 $900.00 $0.00 $900.00 R.8.5 Finish Plumbing A1720 Complete 1st floor - kitchen plumbing 1.00 $300.00 $0.00 $300.00 Abhishek Singh Residential Building Project © Oracle Corporation Page 5 of 8
  • 28. Report for the Budgeted Cost WBS Activity ID Activity Name Original Duration Budgeted Labor Cost Budgeted Material Cost Budgeted Total Cost A1730 Complete 1st floor - master bath & guest plumbing 2.00 $600.00 $0.00 $600.00 A1740 Complete 2nd floor - hall bath & private bath plumbing 2.00 $600.00 $0.00 $600.00 A1750 Conduct finish plumbing inspection 1.00 $0.00 $500.00 $500.00 Subtotal 6.00 $1,500.00 $500.00 $2,000.00 R.8.6 FInish Electrical A1760 Complete 1st Floor circuits to service panel 1.00 $150.00 $0.00 $150.00 A1770 Complete 2nd Floor circuits to service panel 1.00 $150.00 $0.00 $150.00 A1780 Conduct finish electrical inspection 1.00 $0.00 $500.00 $500.00 A1790 Complete communications wiring - phone, cable, computer alarm 2.00 $300.00 $0.00 $300.00 Subtotal 3.00 $600.00 $500.00 $1,100.00 R.8.7 Finish HVAC A1800 Complete 1st floor - zone 1 HVAC 1.00 $150.00 $0.00 $150.00 A1810 Complete 2nd floor - zone 2 HVAC 1.00 $150.00 $0.00 $150.00 A1820 Conduct HVAC inspection 1.00 $0.00 $500.00 $500.00 Subtotal 3.00 $300.00 $500.00 $800.00 Abhishek Singh Residential Building Project © Oracle Corporation Page 6 of 8
  • 29. Report for the Budgeted Cost WBS Activity ID Activity Name Original Duration Budgeted Labor Cost Budgeted Material Cost Budgeted Total Cost R.8.8 Carpet, Tile & Appliances A1830 Tile entry, kitchen & bath 3.00 $450.00 $0.00 $450.00 A1840 Carpet 1st floor 2.00 $300.00 $0.00 $300.00 A1850 Carpet 2nd floor 2.00 $300.00 $0.00 $300.00 A1860 InstallAppliances 1.00 $150.00 $0.00 $150.00 Subtotal 8.00 $1,200.00 $0.00 $1,200.00 Subtotal 29.00 $8,300.00 $2,000.00 $10,300.00 R.9 Landscping and Grounds Work A1870 Pour concrete driveway and sidewalks 2.00 $400.00 $0.00 $400.00 A1880 Install backyard fence 2.00 $300.00 $0.00 $300.00 A1890 Sod & complete plantings - frontyard 2.00 $600.00 $0.00 $600.00 A1900 Sod & complete plantings - backyard 1.00 $300.00 $0.00 $300.00 Subtotal 10.00 $1,600.00 $0.00 $1,600.00 R.5 FinalAcceptance A1910 Complete final inspection for certificate of occupancy 1.00 $0.00 $500.00 $500.00 A1920 Cleanup for occupancy 1.00 $0.00 $0.00 $200.00 A1930 Perform final walk - through inspection 1.00 $200.00 $0.00 $200.00 Abhishek Singh Residential Building Project © Oracle Corporation Page 7 of 8
  • 30. Report for the Budgeted Cost WBS Activity ID Activity Name Original Duration Budgeted Labor Cost Budgeted Material Cost Budgeted Total Cost A1940 Complete punch list items 5.00 $750.00 $0.00 $750.00 Subtotal 8.00 $950.00 $500.00 $1,650.00 Subtotal 151.00 $40,020.00 $5,000.00 $45,220.00 Abhishek Singh Residential Building Project © Oracle Corporation Page 8 of 8
  • 31. Oct 17 Oct 24 Oct 31 Nov 07 Nov 14 Nov 21 Nov 28 Dec 05 Dec 12 Dec 19 Dec 26 Jan 02 Jan 09 Jan 16 Jan 23 Jan 30 Feb 06 Feb 13 Feb 20 Feb 27 Mar 06 Mar 13 Mar 20 Mar 27 Apr 03 Apr 10 Apr 17 Apr 24 May 01 May 08 May 15May 22 $200.00 $400.00 $600.00 $800.00 $1,000.00 $9,000.00 $18,000.00 $27,000.00 $36,000.00 $45,000.00 Abhishek Singh Daily Histogram and Cumulative curve for Labor cost Budgeted Labor Cost Page 1 of 1 TASK filter: All Activities © Oracle Corporation
  • 32. Oct 17 Oct 24 Oct 31 Nov 07 Nov 14 Nov 21 Nov 28 Dec 05 Dec 12 Dec 19 Dec 26 Jan 02 Jan 09 Jan 16 Jan 23 Jan 30 Feb 06 Feb 13 Feb 20 Feb 27 Mar 06 Mar 13 Mar 20 Mar 27 Apr 03 Apr 10 Apr 17 Apr 24 May 01 May 08 May 15May 22 $200.00 $400.00 $600.00 $800.00 $1,000.00 $2,000.00 $4,000.00 $6,000.00 $8,000.00 $10,000.00 Abhishek Singh Daily Histogram and Cumulative curve for Material cost Budgeted Material Cost Page 1 of 1 TASK filter: All Activities © Oracle Corporation
  • 33. 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08 15 22 October 2016 November 2016 December 2016 January 2017 February 2017 March 2017 April 2017 May 2017 $800.00 $1,600.00 $2,400.00 $3,200.00 $4,000.00 $10,000.00 $20,000.00 $30,000.00 $40,000.00 $50,000.00 Abhishek Singh Monthly Histogram and Cumulative curve for Total Cost Budgeted Total Cost Page 1 of 1 TASK filter: All Activities © Oracle Corporation
  • 34. Activity ID Activity Name Residential ConstructionResidential Construction General ConditionsGeneral Conditions A1000 Finalize Plans & Develop estimate with owner, architect A1010 Sign Contract & Notice to proceed Apply For PermitsApply For Permits A1110 Secure Foundation Permit A1120 Secure Framing Permit A1130 Secure Electrical Permit A1140 Secure Plumbing Permit A1150 Secure HVAC Permit A1160 Secure miscellaneous permits Site WorkSite Work A1020 Clear and grub lot A1030 Install temporary power service A1040 Install underground utilities FoundationFoundation A1170 Excavate for foundations A1180 Form basement walls A1190 Place concrete for foundations & basement walls A1200 Cure basement walls for 7 days A1210 Strip basement wall forms A1220 Waterproof / insulate bsement walls A1230 Perform foundation inspection A1240 Backfill foundation FramingFraming A1250 Install 1st floor joists A1260 Lay 1st floor decking A1270 Frame 1st floor walls A1280 Frame 1st floor corners A1290 Install 2nd floor joist A1300 Frame 2nd Floor decking A1310 Frame 2nd floor walls A1320 Frame 2nd floor corners A1330 Complete roof framing A1340 Conduct framing inspection Dry InDry In A1350 Install 1st Floor Sheathing A1360 Install 2nd Floor Sheathing A1370 Install roof decking A1380 Install felt, flashing, and shingles A1390 Hang 1st floor exterior doors A1400 Install 1st floor windows A1410 Install 2nd floor windows Exterior FinishesExterior Finishes A1420 Complete Exterior Brick A1430 Complete exterior siding Utility Rough B97Ins and Complete ConcreteUtility Rough B97Ins and Complete Concrete A1440 Rough-in-plumbing 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08 15 22 October 2016 November 2016 December 2016 January 2017 February 2017 March 2017 April 2017 May 2017 10-May-17 05:00 PM, Residential Con 10-Dec-16 05:00 PM, General Conditions Finalize Plans & Develop estimate with owner, architect Sign Contract & Notice to proceed 10-Dec-16 05:00 PM, Apply For Permits Secure Foundation Permit Secure Framing Permit Secure Electrical Permit Secure Plumbing Permit Secure HVAC Permit Secure miscellaneous permits 14-Dec-16 05:00 PM, Site Work Clear and grub lot Install temporary power service Install underground utilities 01-Feb-17 05:00 PM, Foundation Excavate for foundations Form basement walls Place concrete for foundations & basement walls Cure basement walls for 7 days Strip basement wall forms Waterproof / insulate bsement walls Perform foundation inspection Backfill foundation 27-Feb-17 05:00 PM, Framing Install 1st floor joists Lay 1st floor decking Frame 1st floor walls Frame 1st floor corners Install 2nd floor joist Frame 2nd Floor decking Frame 2nd floor walls Frame 2nd floor corners Complete roof framing Conduct framing inspection 23-Mar-17 05:00 PM, Dry In Install 1st Floor Sheathing Install 2nd Floor Sheathing Install roof decking Install felt, flashing, and shingles Hang 1st floor exterior doors Install 1st floor windows Install 2nd floor windows 14-Apr-17 05:00 PM, Exterior Finishes Complete Exterior Brick Complete exterior siding 25-Mar-17 05:00 PM, Utility Rough B97Ins and Complete Concrete Rough-in-plumbing Actual Level of Effort Primary Baseline Actual Work R... Updated Project Schedule with Activity Table Actual Level of Effort Primary Baseline Actual Work Remaining Work Critical Remaining Work Milestone Page 1 of 3 TASK filter: All Activities © Oracle Corporation
  • 35. Activity ID Activity Name A1450 Conduct Rough-in-plumbing inspection A1460 Place concrete for basement floor A1470 Rough-in electrical A1480 Conduct Rough-in-electrical inspection A1490 Rough-in HVAC A1500 Conduct Rough-in-HVAC inspection A1510 Rough-in communication - phone, cables, computer, alarm Interior FinishesInterior Finishes InsulationInsulation A1520 Place wall insulation - 1st floor A1530 Place wall insulation - 2nd floor A1540 Place ceiling insulation - 2nd floor A1550 Conduct insulation inspection DrywallDrywall A1560 Install Drywall - 1st floor walls A1570 Install drywall - 1st floor overhead A1580 Install drywall 2nd floor walls A1590 Install drywall 2nd floor overhead A1600 Tape & Float 1st floor drywall A1610 Tape & Float 2nd floor drywall Paint & Wall PaperPaint & Wall Paper A1620 Texture all except entry & kitchen - 1st floor A1630 Paint all except entry & kitchen - 1st floor A1640 Hang wallpaper entry & kitchen - 1st floor A1650 Texture all - 2nd floor A1660 Paint all - 2nd floor A1670 Paint exterior siding & trim work CabinetsCabinets A1680 Install 1st floor - kitchen cabinets A1690 Install 1st floor - master bath & guest cabinets A1700 Install 2nd floor - hall bath & provate bath cabinets A1710 install chair rails, crown moldings, trim Finish PlumbingFinish Plumbing A1720 Complete 1st floor - kitchen plumbing A1730 Complete 1st floor - master bath & guest plumbing A1740 Complete 2nd floor - hall bath & private bath plumbing A1750 Conduct finish plumbing inspection FInish ElectricalFInish Electrical A1760 Complete 1st Floor circuits to service panel A1770 Complete 2nd Floor circuits to service panel A1780 Conduct finish electrical inspection A1790 Complete communications wiring - phone, cable, computer alarm Finish HVACFinish HVAC A1800 Complete 1st floor - zone 1 HVAC A1810 Complete 2nd floor - zone 2 HVAC A1820 Conduct HVAC inspection Carpet, Tile & AppliancesCarpet, Tile & Appliances A1830 Tile entry, kitchen & bath A1840 Carpet 1st floor A1850 Carpet 2nd floor 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08 15 22 October 2016 November 2016 December 2016 January 2017 February 2017 March 2017 April 2017 May 2017 Conduct Rough-in-plumbing inspection Place concrete for basement floor Rough-in electrical Conduct Rough-in-electrical inspection Rough-in HVAC Conduct Rough-in-HVAC inspection Rough-in communication - phone, cables, computer, alarm 25-Apr-17 05:00 PM, Interior Finishes 03-Apr-17 05:00 PM, Insulation Place wall insulation - 1st floor Place wall insulation - 2nd floor Place ceiling insulation - 2nd floor Conduct insulation inspection 01-Apr-17 05:00 PM, Drywall Install Drywall - 1st floor walls Install drywall - 1st floor overhead Install drywall 2nd floor walls Install drywall 2nd floor overhead Tape & Float 1st floor drywall Tape & Float 2nd floor drywall 19-Apr-17 05:00 PM, Paint & Wall Paper Texture all except entry & kitchen - 1st floor Paint all except entry & kitchen - 1st floor Hang wallpaper entry & kitchen - 1st floor Texture all - 2nd floor Paint all - 2nd floor Paint exterior siding & trim work 07-Apr-17 05:00 PM, Cabinets Install 1st floor - kitchen cabinets Install 1st floor - master bath & guest cabinets Install 2nd floor - hall bath & provate bath cabinets install chair rails, crown moldings, trim 10-Apr-17 05:00 PM, Finish Plumbing Complete 1st floor - kitchen plumbing Complete 1st floor - master bath & guest plumbing Complete 2nd floor - hall bath & private bath plumbing Conduct finish plumbing inspection 12-Apr-17 05:00 PM, FInish Electrical Complete 1st Floor circuits to service panel Complete 2nd Floor circuits to service panel Conduct finish electrical inspection Complete communications wiring - phone, cable, computer alarm 15-Apr-17 05:00 PM, Finish HVAC Complete 1st floor - zone 1 HVAC Complete 2nd floor - zone 2 HVAC Conduct HVAC inspection 25-Apr-17 05:00 PM, Carpet, Tile & Appliances Tile entry, kitchen & bath Carpet 1st floor Carpet 2nd floor Actual Level of Effort Primary Baseline Actual Work R... Updated Project Schedule with Activity Table Actual Level of Effort Primary Baseline Actual Work Remaining Work Critical Remaining Work Milestone Page 2 of 3 TASK filter: All Activities © Oracle Corporation
  • 36. Activity ID Activity Name A1860 InstallAppliances Landscping and Grounds WorkLandscping and Grounds Work A1870 Pour concrete driveway and sidewalks A1880 Install backyard fence A1890 Sod & complete plantings - frontyard A1900 Sod & complete plantings - backyard Final AcceptanceFinal Acceptance A1910 Complete final inspection for certificate of occupancy A1920 Cleanup for occupancy A1930 Perform final walk - through inspection A1940 Complete punch list items 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08 15 22 October 2016 November 2016 December 2016 January 2017 February 2017 March 2017 April 2017 May 2017 InstallAppliances 01-May-17 05:00 PM, Landscping and Grounds Pour concrete driveway and sidewalks Install backyard fence Sod & complete plantings - frontyard Sod & complete plantings - backyard 10-May-17 05:00 PM, FinalAcceptanc Complete final inspection for certificate of occup Cleanup for occupancy Perform final walk - through inspection Complete punch list items Actual Level of Effort Primary Baseline Actual Work R... Updated Project Schedule with Activity Table Actual Level of Effort Primary Baseline Actual Work Remaining Work Critical Remaining Work Milestone Page 3 of 3 TASK filter: All Activities © Oracle Corporation
  • 37. Activity ID Activity Name Original Duration Remaining Duration BL Project Start BL Project Finish Start Finish Variance - BL1 Finish Date Budgeted Total Cost R Residential ConstructionR Residential Construction 164.00 139.00 01-Nov-16 08:00 AM 25-Apr-17 05:00 PM 02-Nov-16 08:00 AM A 10-May-17 05:00 PM 0.00 $45,220.00 R.1 General ConditionsR.1 General Conditions 35.00 10.00 01-Nov-16 08:00 AM 25-Nov-16 05:00 PM 02-Nov-16 08:00 AM A10-Dec-16 05:00 PM 0.00 $5,970.00 A1010 Sign Contract & Notice to proceed 1.00 1.00 24-Nov-16 08:00 AM 24-Nov-16 05:00 PM 09-Dec-16 08:00 AM 09-Dec-16 05:00 PM 0.00 $750.00 A1000 Finalize Plans & Develop estimate with owner, architect 20.00 8.00 01-Nov-16 08:00 AM 23-Nov-16 05:00 PM 02-Nov-16 08:00 AM A08-Dec-16 05:00 PM -13.00 $5,220.00 R.1.1 Apply For PermitsR.1.1 Apply For Permits 1.00 1.00 25-Nov-16 08:00 AM 25-Nov-16 05:00 PM 10-Dec-16 08:00 AM 10-Dec-16 05:00 PM 0.00 $0.00 A1160 Secure miscellaneous permits 1.00 1.00 25-Nov-16 08:00 AM 25-Nov-16 05:00 PM 10-Dec-16 08:00 AM 10-Dec-16 05:00 PM 0.00 $0.00 A1150 Secure HVAC Permit 1.00 1.00 25-Nov-16 08:00 AM 25-Nov-16 05:00 PM 10-Dec-16 08:00 AM 10-Dec-16 05:00 PM 0.00 $0.00 A1140 Secure Plumbing Permit 1.00 1.00 25-Nov-16 08:00 AM 25-Nov-16 05:00 PM 10-Dec-16 08:00 AM 10-Dec-16 05:00 PM 0.00 $0.00 A1130 Secure Electrical Permit 1.00 1.00 25-Nov-16 08:00 AM 25-Nov-16 05:00 PM 10-Dec-16 08:00 AM 10-Dec-16 05:00 PM 0.00 $0.00 A1120 Secure Framing Permit 1.00 1.00 25-Nov-16 08:00 AM 25-Nov-16 05:00 PM 10-Dec-16 08:00 AM 10-Dec-16 05:00 PM 0.00 $0.00 A1110 Secure Foundation Permit 1.00 1.00 25-Nov-16 08:00 AM 25-Nov-16 05:00 PM 10-Dec-16 08:00 AM 10-Dec-16 05:00 PM 0.00 $0.00 R.S Site WorkR.S Site Work 3.00 3.00 26-Nov-16 08:00 AM 29-Nov-16 05:00 PM 12-Dec-16 08:00 AM 14-Dec-16 05:00 PM 0.00 $750.00 A1040 Install underground utilities 1.00 1.00 29-Nov-16 08:00 AM 29-Nov-16 05:00 PM 14-Dec-16 08:00 AM 14-Dec-16 05:00 PM 0.00 $450.00 A1030 Install temporary power service 1.00 1.00 28-Nov-16 08:00 AM 28-Nov-16 05:00 PM 13-Dec-16 08:00 AM 13-Dec-16 05:00 PM 0.00 $150.00 A1020 Clear and grub lot 1.00 1.00 26-Nov-16 08:00 AM 26-Nov-16 05:00 PM 12-Dec-16 08:00 AM 12-Dec-16 05:00 PM 0.00 $150.00 R.2 FoundationR.2 Foundation 42.00 42.00 30-Nov-16 08:00 AM 17-Jan-17 05:00 PM 15-Dec-16 08:00 AM 01-Feb-17 05:00 PM 0.00 $7,050.00 A1240 Backfill foundation 2.00 2.00 16-Jan-17 08:00 AM 17-Jan-17 05:00 PM 31-Jan-17 08:00 AM 01-Feb-17 05:00 PM 0.00 $300.00 A1230 Perform foundation inspection 1.00 1.00 14-Jan-17 08:00 AM 14-Jan-17 05:00 PM 30-Jan-17 08:00 AM 30-Jan-17 05:00 PM 0.00 $500.00 A1220 Waterproof / insulate bsement walls 2.00 2.00 12-Jan-17 08:00 AM 13-Jan-17 05:00 PM 27-Jan-17 08:00 AM 28-Jan-17 05:00 PM 0.00 $400.00 A1210 Strip basement wall forms 2.00 2.00 10-Jan-17 08:00 AM 11-Jan-17 05:00 PM 25-Jan-17 08:00 AM 26-Jan-17 05:00 PM 0.00 $400.00 A1200 Cure basement walls for 7 days 7.00 7.00 02-Jan-17 08:00 AM 09-Jan-17 05:00 PM 17-Jan-17 08:00 AM 24-Jan-17 05:00 PM 0.00 $0.00 A1190 Place concrete for foundations & basement walls 12.00 12.00 19-Dec-16 08:00 AM 31-Dec-16 05:00 PM 03-Jan-17 08:00 AM 16-Jan-17 05:00 PM 0.00 $2,400.00 A1180 Form basement walls 13.00 13.00 03-Dec-16 08:00 AM 17-Dec-16 05:00 PM 19-Dec-16 08:00 AM 02-Jan-17 05:00 PM 0.00 $2,600.00 A1170 Excavate for foundations 3.00 3.00 30-Nov-16 08:00 AM 02-Dec-16 05:00 PM 15-Dec-16 08:00 AM 17-Dec-16 05:00 PM 0.00 $450.00 R.3 FramingR.3 Framing 22.00 22.00 18-Jan-17 08:00 AM 11-Feb-17 05:00 PM 02-Feb-17 08:00 AM 27-Feb-17 05:00 PM 0.00 $4,700.00 A1340 Conduct framing inspection 1.00 1.00 11-Feb-17 08:00 AM 11-Feb-17 05:00 PM 27-Feb-17 08:00 AM 27-Feb-17 05:00 PM 0.00 $500.00 A1330 Complete roof framing 3.00 3.00 08-Feb-17 08:00 AM 10-Feb-17 05:00 PM 23-Feb-17 08:00 AM 25-Feb-17 05:00 PM 0.00 $600.00 A1320 Frame 2nd floor corners 2.00 2.00 06-Feb-17 08:00 AM 07-Feb-17 05:00 PM 21-Feb-17 08:00 AM 22-Feb-17 05:00 PM 0.00 $400.00 A1310 Frame 2nd floor walls 3.00 3.00 02-Feb-17 08:00 AM 04-Feb-17 05:00 PM 17-Feb-17 08:00 AM 20-Feb-17 05:00 PM 0.00 $600.00 A1300 Frame 2nd Floor decking 2.00 2.00 31-Jan-17 08:00 AM 01-Feb-17 05:00 PM 15-Feb-17 08:00 AM 16-Feb-17 05:00 PM 0.00 $400.00 A1290 Install 2nd floor joist 2.00 2.00 28-Jan-17 08:00 AM 30-Jan-17 05:00 PM 13-Feb-17 08:00 AM 14-Feb-17 05:00 PM 0.00 $400.00 A1280 Frame 1st floor corners 1.00 1.00 27-Jan-17 08:00 AM 27-Jan-17 05:00 PM 11-Feb-17 08:00 AM 11-Feb-17 05:00 PM 0.00 $200.00 A1270 Frame 1st floor walls 4.00 4.00 23-Jan-17 08:00 AM 26-Jan-17 05:00 PM 07-Feb-17 08:00 AM 10-Feb-17 05:00 PM 0.00 $800.00 A1260 Lay 1st floor decking 2.00 2.00 20-Jan-17 08:00 AM 21-Jan-17 05:00 PM 04-Feb-17 08:00 AM 06-Feb-17 05:00 PM 0.00 $400.00 A1250 Install 1st floor joists 2.00 2.00 18-Jan-17 08:00 AM 19-Jan-17 05:00 PM 02-Feb-17 08:00 AM 03-Feb-17 05:00 PM 0.00 $400.00 R.4 Dry InR.4 Dry In 22.00 22.00 11-Feb-17 08:00 AM 08-Mar-17 05:00 PM 27-Feb-17 08:00 AM 23-Mar-17 05:00 PM 0.00 $3,500.00 A1410 Install 2nd floor windows 3.00 3.00 06-Mar-17 08:00 AM 08-Mar-17 05:00 PM 21-Mar-17 08:00 AM 23-Mar-17 05:00 PM 0.00 $600.00 A1400 Install 1st floor windows 3.00 3.00 02-Mar-17 08:00 AM 04-Mar-17 05:00 PM 17-Mar-17 08:00 AM 20-Mar-17 05:00 PM 0.00 $600.00 A1390 Hang 1st floor exterior doors 1.00 1.00 01-Mar-17 08:00 AM 01-Mar-17 05:00 PM 16-Mar-17 08:00 AM 16-Mar-17 05:00 PM 0.00 $200.00 A1380 Install felt, flashing, and shingles 3.00 3.00 25-Feb-17 08:00 AM 28-Feb-17 05:00 PM 13-Mar-17 08:00 AM 15-Mar-17 05:00 PM 0.00 $300.00 A1360 Install 2nd Floor Sheathing 3.00 3.00 16-Feb-17 08:00 AM 18-Feb-17 05:00 PM 03-Mar-17 08:00 AM 06-Mar-17 05:00 PM 0.00 $600.00 A1350 Install 1st Floor Sheathing 3.00 3.00 13-Feb-17 08:00 AM 15-Feb-17 05:00 PM 28-Feb-17 08:00 AM 02-Mar-17 05:00 PM 0.00 $600.00 A1370 Install roof decking 3.00 3.00 11-Feb-17 08:00 AM 14-Feb-17 05:00 PM 27-Feb-17 08:00 AM 01-Mar-17 05:00 PM 0.00 $600.00 R.6 Exterior FinishesR.6 Exterior Finishes 19.00 19.00 09-Mar-17 08:00 AM 30-Mar-17 05:00 PM 24-Mar-17 08:00 AM 14-Apr-17 05:00 PM 0.00 $3,000.00 A1430 Complete exterior siding 3.00 3.00 28-Mar-17 08:00 AM 30-Mar-17 05:00 PM 12-Apr-17 08:00 AM 14-Apr-17 05:00 PM 0.00 $600.00 A1420 Complete Exterior Brick 16.00 16.00 09-Mar-17 08:00 AM 27-Mar-17 05:00 PM 24-Mar-17 08:00 AM 11-Apr-17 05:00 PM 0.00 $2,400.00 R.7 Utility Rough B97Ins and Complete ConcreteR.7 Utility Rough B97Ins and Complete Concrete 21.00 21.00 15-Feb-17 08:00 AM 10-Mar-17 05:00 PM 02-Mar-17 08:00 AM 25-Mar-17 05:00 PM 0.00 $6,700.00 A1460 Place concrete for basement floor 11.00 11.00 27-Feb-17 08:00 AM 10-Mar-17 05:00 PM 14-Mar-17 08:00 AM 25-Mar-17 05:00 PM 0.00 $2,200.00 Abhishek Singh Updated Project Schedule with Activity Table Page 1 of 3 TASK filter: All Activities © Oracle Corporation
  • 38. Activity ID Activity Name Original Duration Remaining Duration BL Project Start BL Project Finish Start Finish Variance - BL1 Finish Date Budgeted Total Cost A1500 Conduct Rough-in-HVAC inspection 1.00 1.00 02-Mar-17 08:00 AM 02-Mar-17 05:00 PM 17-Mar-17 08:00 AM 17-Mar-17 05:00 PM 0.00 $500.00 A1490 Rough-in HVAC 3.00 3.00 27-Feb-17 08:00 AM 01-Mar-17 05:00 PM 14-Mar-17 08:00 AM 16-Mar-17 05:00 PM 0.00 $450.00 A1480 Conduct Rough-in-electrical inspection 1.00 1.00 25-Feb-17 08:00 AM 25-Feb-17 05:00 PM 13-Mar-17 08:00 AM 13-Mar-17 05:00 PM 0.00 $500.00 A1450 Conduct Rough-in-plumbing inspection 1.00 1.00 25-Feb-17 08:00 AM 25-Feb-17 05:00 PM 13-Mar-17 08:00 AM 13-Mar-17 05:00 PM 0.00 $500.00 A1470 Rough-in electrical 5.00 5.00 20-Feb-17 08:00 AM 24-Feb-17 05:00 PM 07-Mar-17 08:00 AM 11-Mar-17 05:00 PM 0.00 $750.00 A1440 Rough-in-plumbing 5.00 5.00 20-Feb-17 08:00 AM 24-Feb-17 05:00 PM 07-Mar-17 08:00 AM 11-Mar-17 05:00 PM 0.00 $1,500.00 A1510 Rough-in communication - phone, cables, computer, alarm 2.00 2.00 15-Feb-17 08:00 AM 16-Feb-17 05:00 PM 02-Mar-17 08:00 AM 03-Mar-17 05:00 PM 0.00 $300.00 R.8 Interior FinishesR.8 Interior Finishes 29.00 29.00 08-Mar-17 08:00 AM 10-Apr-17 05:00 PM 23-Mar-17 08:00 AM 25-Apr-17 05:00 PM 0.00 $10,300.00 R.8.1 InsulationR.8.1 Insulation 9.00 9.00 09-Mar-17 08:00 AM 18-Mar-17 05:00 PM 24-Mar-17 08:00 AM 03-Apr-17 05:00 PM 0.00 $1,400.00 A1550 Conduct insulation inspection 1.00 1.00 18-Mar-17 08:00 AM 18-Mar-17 05:00 PM 03-Apr-17 08:00 AM 03-Apr-17 05:00 PM 0.00 $500.00 A1540 Place ceiling insulation - 2nd floor 1.00 1.00 17-Mar-17 08:00 AM 17-Mar-17 05:00 PM 01-Apr-17 08:00 AM 01-Apr-17 05:00 PM 0.00 $300.00 A1530 Place wall insulation - 2nd floor 1.00 1.00 10-Mar-17 08:00 AM 10-Mar-17 05:00 PM 25-Mar-17 08:00 AM 25-Mar-17 05:00 PM 0.00 $300.00 A1520 Place wall insulation - 1st floor 1.00 1.00 09-Mar-17 08:00 AM 09-Mar-17 05:00 PM 24-Mar-17 08:00 AM 24-Mar-17 05:00 PM 0.00 $300.00 R.8.2 DrywallR.8.2 Drywall 9.00 9.00 08-Mar-17 08:00 AM 17-Mar-17 05:00 PM 23-Mar-17 08:00 AM 01-Apr-17 05:00 PM 0.00 $2,000.00 A1610 Tape & Float 2nd floor drywall 1.00 1.00 17-Mar-17 08:00 AM 17-Mar-17 05:00 PM 01-Apr-17 08:00 AM 01-Apr-17 05:00 PM 0.00 $200.00 A1590 Install drywall 2nd floor overhead 2.00 2.00 15-Mar-17 08:00 AM 16-Mar-17 05:00 PM 30-Mar-17 08:00 AM 31-Mar-17 05:00 PM 0.00 $400.00 A1580 Install drywall 2nd floor walls 2.00 2.00 13-Mar-17 08:00 AM 14-Mar-17 05:00 PM 28-Mar-17 08:00 AM 29-Mar-17 05:00 PM 0.00 $400.00 A1600 Tape & Float 1st floor drywall 1.00 1.00 13-Mar-17 08:00 AM 13-Mar-17 05:00 PM 28-Mar-17 08:00 AM 28-Mar-17 05:00 PM 0.00 $200.00 A1570 Install drywall - 1st floor overhead 2.00 2.00 10-Mar-17 08:00 AM 11-Mar-17 05:00 PM 25-Mar-17 08:00 AM 27-Mar-17 05:00 PM 0.00 $400.00 A1560 Install Drywall - 1st floor walls 2.00 2.00 08-Mar-17 08:00 AM 09-Mar-17 05:00 PM 23-Mar-17 08:00 AM 24-Mar-17 05:00 PM 0.00 $400.00 R.8.3 Paint & Wall PaperR.8.3 Paint & Wall Paper 19.00 19.00 14-Mar-17 08:00 AM 04-Apr-17 05:00 PM 29-Mar-17 08:00 AM 19-Apr-17 05:00 PM 0.00 $900.00 A1670 Paint exterior siding & trim work 4.00 4.00 31-Mar-17 08:00 AM 04-Apr-17 05:00 PM 15-Apr-17 08:00 AM 19-Apr-17 05:00 PM 0.00 $400.00 A1660 Paint all - 2nd floor 1.00 1.00 16-Mar-17 08:00 AM 16-Mar-17 05:00 PM 31-Mar-17 08:00 AM 31-Mar-17 05:00 PM 0.00 $100.00 A1640 Hang wallpaper entry & kitchen - 1st floor 1.00 1.00 16-Mar-17 08:00 AM 16-Mar-17 05:00 PM 31-Mar-17 08:00 AM 31-Mar-17 05:00 PM 0.00 $100.00 A1650 Texture all - 2nd floor 1.00 1.00 15-Mar-17 08:00 AM 15-Mar-17 05:00 PM 30-Mar-17 08:00 AM 30-Mar-17 05:00 PM 0.00 $100.00 A1630 Paint all except entry & kitchen - 1st floor 1.00 1.00 15-Mar-17 08:00 AM 15-Mar-17 05:00 PM 30-Mar-17 08:00 AM 30-Mar-17 05:00 PM 0.00 $100.00 A1620 Texture all except entry & kitchen - 1st floor 1.00 1.00 14-Mar-17 08:00 AM 14-Mar-17 05:00 PM 29-Mar-17 08:00 AM 29-Mar-17 05:00 PM 0.00 $100.00 R.8.4 CabinetsR.8.4 Cabinets 6.00 6.00 17-Mar-17 08:00 AM 23-Mar-17 05:00 PM 01-Apr-17 08:00 AM 07-Apr-17 05:00 PM 0.00 $900.00 A1710 install chair rails, crown moldings, trim 2.00 2.00 22-Mar-17 08:00 AM 23-Mar-17 05:00 PM 06-Apr-17 08:00 AM 07-Apr-17 05:00 PM 0.00 $300.00 A1700 Install 2nd floor - hall bath & provate bath cabinets 1.00 1.00 21-Mar-17 08:00 AM 21-Mar-17 05:00 PM 05-Apr-17 08:00 AM 05-Apr-17 05:00 PM 0.00 $150.00 A1690 Install 1st floor - master bath & guest cabinets 1.00 1.00 20-Mar-17 08:00 AM 20-Mar-17 05:00 PM 04-Apr-17 08:00 AM 04-Apr-17 05:00 PM 0.00 $150.00 A1680 Install 1st floor - kitchen cabinets 2.00 2.00 17-Mar-17 08:00 AM 18-Mar-17 05:00 PM 01-Apr-17 08:00 AM 03-Apr-17 05:00 PM 0.00 $300.00 R.8.5 Finish PlumbingR.8.5 Finish Plumbing 6.00 6.00 20-Mar-17 08:00 AM 25-Mar-17 05:00 PM 04-Apr-17 08:00 AM 10-Apr-17 05:00 PM 0.00 $2,000.00 A1750 Conduct finish plumbing inspection 1.00 1.00 25-Mar-17 08:00 AM 25-Mar-17 05:00 PM 10-Apr-17 08:00 AM 10-Apr-17 05:00 PM 0.00 $500.00 A1740 Complete 2nd floor - hall bath & private bath plumbing 2.00 2.00 23-Mar-17 08:00 AM 24-Mar-17 05:00 PM 07-Apr-17 08:00 AM 08-Apr-17 05:00 PM 0.00 $600.00 A1730 Complete 1st floor - master bath & guest plumbing 2.00 2.00 21-Mar-17 08:00 AM 22-Mar-17 05:00 PM 05-Apr-17 08:00 AM 06-Apr-17 05:00 PM 0.00 $600.00 A1720 Complete 1st floor - kitchen plumbing 1.00 1.00 20-Mar-17 08:00 AM 20-Mar-17 05:00 PM 04-Apr-17 08:00 AM 04-Apr-17 05:00 PM 0.00 $300.00 R.8.6 FInish ElectricalR.8.6 FInish Electrical 3.00 3.00 25-Mar-17 08:00 AM 28-Mar-17 05:00 PM 10-Apr-17 08:00 AM 12-Apr-17 05:00 PM 0.00 $1,100.00 A1790 Complete communications wiring - phone, cable, computer alarm 2.00 2.00 27-Mar-17 08:00 AM 28-Mar-17 05:00 PM 11-Apr-17 08:00 AM 12-Apr-17 05:00 PM 0.00 $300.00 A1780 Conduct finish electrical inspection 1.00 1.00 28-Mar-17 08:00 AM 28-Mar-17 05:00 PM 12-Apr-17 08:00 AM 12-Apr-17 05:00 PM 0.00 $500.00 A1770 Complete 2nd Floor circuits to service panel 1.00 1.00 27-Mar-17 08:00 AM 27-Mar-17 05:00 PM 11-Apr-17 08:00 AM 11-Apr-17 05:00 PM 0.00 $150.00 A1760 Complete 1st Floor circuits to service panel 1.00 1.00 25-Mar-17 08:00 AM 25-Mar-17 05:00 PM 10-Apr-17 08:00 AM 10-Apr-17 05:00 PM 0.00 $150.00 R.8.7 Finish HVACR.8.7 Finish HVAC 3.00 3.00 29-Mar-17 08:00 AM 31-Mar-17 05:00 PM 13-Apr-17 08:00 AM 15-Apr-17 05:00 PM 0.00 $800.00 A1820 Conduct HVAC inspection 1.00 1.00 31-Mar-17 08:00 AM 31-Mar-17 05:00 PM 15-Apr-17 08:00 AM 15-Apr-17 05:00 PM 0.00 $500.00 A1810 Complete 2nd floor - zone 2 HVAC 1.00 1.00 30-Mar-17 08:00 AM 30-Mar-17 05:00 PM 14-Apr-17 08:00 AM 14-Apr-17 05:00 PM 0.00 $150.00 A1800 Complete 1st floor - zone 1 HVAC 1.00 1.00 29-Mar-17 08:00 AM 29-Mar-17 05:00 PM 13-Apr-17 08:00 AM 13-Apr-17 05:00 PM 0.00 $150.00 R.8.8 Carpet, Tile & AppliancesR.8.8 Carpet, Tile & Appliances 8.00 8.00 01-Apr-17 08:00 AM 10-Apr-17 05:00 PM 17-Apr-17 08:00 AM 25-Apr-17 05:00 PM 0.00 $1,200.00 A1860 InstallAppliances 1.00 1.00 10-Apr-17 08:00 AM 10-Apr-17 05:00 PM 25-Apr-17 08:00 AM 25-Apr-17 05:00 PM 0.00 $150.00 A1850 Carpet 2nd floor 2.00 2.00 07-Apr-17 08:00 AM 08-Apr-17 05:00 PM 22-Apr-17 08:00 AM 24-Apr-17 05:00 PM 0.00 $300.00 A1840 Carpet 1st floor 2.00 2.00 05-Apr-17 08:00 AM 06-Apr-17 05:00 PM 20-Apr-17 08:00 AM 21-Apr-17 05:00 PM 0.00 $300.00 Abhishek Singh Updated Project Schedule with Activity Table Page 2 of 3 TASK filter: All Activities © Oracle Corporation
  • 39. Activity ID Activity Name Original Duration Remaining Duration BL Project Start BL Project Finish Start Finish Variance - BL1 Finish Date Budgeted Total Cost A1830 Tile entry, kitchen & bath 3.00 3.00 01-Apr-17 08:00 AM 04-Apr-17 05:00 PM 17-Apr-17 08:00 AM 19-Apr-17 05:00 PM 0.00 $450.00 R.9 Landscping and Grounds WorkR.9 Landscping and Grounds Work 10.00 10.00 05-Apr-17 08:00 AM 15-Apr-17 05:00 PM 20-Apr-17 08:00 AM 01-May-17 05:00 PM 0.00 $1,600.00 A1900 Sod & complete plantings - backyard 1.00 1.00 15-Apr-17 08:00 AM 15-Apr-17 05:00 PM 01-May-17 08:00 AM 01-May-17 05:00 PM 0.00 $300.00 A1890 Sod & complete plantings - frontyard 2.00 2.00 13-Apr-17 08:00 AM 14-Apr-17 05:00 PM 28-Apr-17 08:00 AM 29-Apr-17 05:00 PM 0.00 $600.00 A1880 Install backyard fence 2.00 2.00 11-Apr-17 08:00 AM 12-Apr-17 05:00 PM 26-Apr-17 08:00 AM 27-Apr-17 05:00 PM 0.00 $300.00 A1870 Pour concrete driveway and sidewalks 2.00 2.00 05-Apr-17 08:00 AM 06-Apr-17 05:00 PM 20-Apr-17 08:00 AM 21-Apr-17 05:00 PM 0.00 $400.00 R.5 Final AcceptanceR.5 Final Acceptance 8.00 8.00 17-Apr-17 08:00 AM 25-Apr-17 05:00 PM 02-May-17 08:00 AM 10-May-17 05:00 PM 0.00 $1,650.00 A1940 Complete punch list items 5.00 5.00 20-Apr-17 08:00 AM 25-Apr-17 05:00 PM 05-May-17 08:00 AM 10-May-17 05:00 PM 0.00 $750.00 A1930 Perform final walk - through inspection 1.00 1.00 19-Apr-17 08:00 AM 19-Apr-17 05:00 PM 04-May-17 08:00 AM 04-May-17 05:00 PM 0.00 $200.00 A1920 Cleanup for occupancy 1.00 1.00 18-Apr-17 08:00 AM 18-Apr-17 05:00 PM 03-May-17 08:00 AM 03-May-17 05:00 PM 0.00 $200.00 A1910 Complete final inspection for certificate of occupancy 1.00 1.00 17-Apr-17 08:00 AM 17-Apr-17 05:00 PM 02-May-17 08:00 AM 02-May-17 05:00 PM 0.00 $500.00 Abhishek Singh Updated Project Schedule with Activity Table Page 3 of 3 TASK filter: All Activities © Oracle Corporation