This document provides a summary of activities and schedules for a small residential building project taking place from November 2016 to April 2017. It includes a table listing 22 activities related to securing permits and site preparation scheduled to take place from November to January. It also includes tables scheduling 42 foundation-related activities from November to January, 22 framing activities from January to February, and 22 exterior closure activities from February to March. It summarizes inspections and rough-in of utilities planned from February to March.
1. CE 561
Construction Project Management
Small Residential Building Project
FALL - 2016
ABHISHEK KUMAR SINGH
200116822
2. Table of Contents
SL No. Report Name
1 Grouped by Project and Sorted by Activity ID
2 Gantt Chart for activities grouped by WBS and Sorted by Activity ID
3 Activity Network Layout of the Project
4 Activity Table & Gantt Chart Schedule for Critical Activities
5 Gantt Chart Schedule for Critical Activities
6 Gantt Chart Schedule for activities Sorted by Early Start & Free Float
7 Report for Budgeted Cost
8 Daily Histogram and cumulative curve for Labor cost
9 Daily Histogram and cumulative curve for Material Cost
10 Monthly Histogram and Cumulative curve for Total Cost
11 Updated Schedule Report and Gantt Chart Table