Activity ID Activity Name Remaining
Duration
Original
Duration
Schedule %
Complete
Start Finish Total
Float
floor type of
work
lab2- Nbourdier Condo schedulelab2- Nbourdier Condo schedule 306 306 0% 01-Apr-15 01-Jun-16 30
lab2- Nbourdier.1 milestoneslab2- Nbourdier.1 milestones 295 295 0% 01-Apr-15 31-May-16 0
A1030 building watertight 0 0 0% 24-Sep-15 24-Sep-15 25 const
A1000 contract award 0 0 0% 01-Apr-15 0 pre con
A1060 final completion 20 20 0% 03-May-16 31-May-16 0 const
A1010 NTP 0 0 0% 10-Apr-15* 0 pre con
A1040 permanent power available 7 7 0% 26-Jun-15 06-Jul-15 152 u
A1050 substantial completion 25 25 0% 15-Feb-16 21-Mar-16 0 const
lab2- Nbourdier.1.4 mobilizationlab2- Nbourdier.1.4 mobilization 14 14 0% 10-Apr-15 29-Apr-15 0
A1180 MOB 14 14 0% 10-Apr-15 29-Apr-15 0 pre con
lab2- Nbourdier.2 procurementlab2- Nbourdier.2 procurement 0 0 0% 0
lab2- Nbourdier.5 submittalslab2- Nbourdier.5 submittals 15 15 0% 30-Apr-15 20-May-15 0
A1220 prepare and submit shop drawings and material data15 15 0% 30-Apr-15 20-May-15 0 Procure
lab2- Nbourdier.7 fabricate and deliverlab2- Nbourdier.7 fabricate and deliver 45 45 0% 12-Jun-15 13-Aug-15 109
A1210 fabricate and deliver concrete panels 45 45 0% 12-Jun-15 13-Aug-15 109 Procure
A1160 fabricate and deliver framing 30 30 0% 12-Jun-15 23-Jul-15 37 Procure
A1200 fabricate and deliver steel 35 35 0% 12-Jun-15 30-Jul-15 0 Procure
A1150 order & deliver roofing 40 40 0% 12-Jun-15 06-Aug-15 50 Procure
A1110 order and deliver A/C system 20 20 0% 12-Jun-15 09-Jul-15 66 Procure
A1120 order and deliver ceilings 20 20 0% 12-Jun-15 09-Jul-15 96 Procure
A1090 order and deliver doors 20 20 0% 12-Jun-15 09-Jul-15 89 Procure
A1100 order and deliver flooring 15 15 0% 12-Jun-15 02-Jul-15 112 Procure
A1130 order and deliver plumbing 30 30 0% 12-Jun-15 23-Jul-15 42 Procure
A1140 order electrical 20 20 0% 12-Jun-15 09-Jul-15 78 Procure
lab2- Nbourdier.6 approvalslab2- Nbourdier.6 approvals 15 15 0% 21-May-15 11-Jun-15 0
A1070 review & approve shop drawings & material data 15 15 0% 21-May-15 11-Jun-15 0 Procure
lab2- Nbourdier.4 constructionlab2- Nbourdier.4 construction 199 199 0% 30-Apr-15 12-Feb-16 105
lab2- Nbourdier.4.1 site worklab2- Nbourdier.4.1 site work 109 109 0% 30-Apr-15 01-Oct-15 90
lab2- Nbourdier.4.1.1 site work & utilitieslab2- Nbourdier.4.1.1 site work & utilities 40 40 0% 30-Apr-15 25-Jun-15 152
A1240 install erosion control 3 3 0% 07-May-15 11-May-15 37 site
A1230 rough grading 5 5 0% 30-Apr-15 06-May-15 37 site
A1250 utility installation 15 15 0% 05-Jun-15 25-Jun-15 152 u
lab2- Nbourdier.4.1.2 landscaping/ parking lotlab2- Nbourdier.4.1.2 landscaping/ parking lot 84 84 0% 05-Jun-15 01-Oct-15 90
A1310 curbs and sidewalks 13 13 0% 11-Aug-15 27-Aug-15 90 site
A1260 fine grading 25 25 0% 16-Jun-15 20-Jul-15 90 site
A1930 install exterior signage 4 4 0% 28-Sep-15 01-Oct-15 90 const
A1270 install parking lot drainage 7 7 0% 05-Jun-15 15-Jun-15 90 u
A1320 landscaping 20 20 0% 28-Aug-15 25-Sep-15 90 site
A1280 parking lot pavement 10 10 0% 28-Jul-15 10-Aug-15 90 site
A1290 pavement striping 5 5 0% 21-Jul-15 27-Jul-15 90 site
A1300 site lighting 5 5 0% 11-Aug-15 17-Aug-15 98 u
lab2- Nbourdier.4.4 FDN constructionlab2- Nbourdier.4.4 FDN construction 69 69 0% 12-May-15 17-Aug-15 20
A1380 Backfill 3 3 0% 13-Aug-15 17-Aug-15 20 site
A1360 construct basement slab-FRPC 5 5 0% 04-Aug-15 10-Aug-15 20 bas const
A1350 construct concrete FDN walls 10 10 0% 03-Jun-15 16-Jun-15 37 const
A1340 construct footings 7 7 0% 22-May-15 02-Jun-15 37 const
A1330 excavate for foundation 17 17 0% 12-May-15 04-Jun-15 37 const
A2110 FRPC transformer pad 3 3 0% 05-Jun-15 09-Jun-15 59 const
A1370 waterproofing FDN walls 2 2 0% 11-Aug-15 12-Aug-15 20 const
lab2- Nbourdier.4.2 structurelab2- Nbourdier.4.2 structure 30 30 0% 31-Jul-15 11-Sep-15 25
A1440 construct interior CMU wall for stair at 2nd floor 1 1 0% 19-Aug-15 19-Aug-15 0 2 const
A1470 construct interior CMU wall for stair at 3rd floor 1 1 0% 28-Aug-15 28-Aug-15 0 3 const
A1500 construct interior CMU wall for stair at 4th floor 1 1 0% 09-Sep-15 09-Sep-15 25 4 const
A1410 construct interior CMU wall for stair at first floor 1 1 0% 10-Aug-15 10-Aug-15 0 1 const
A1390 construct metal deck and concrete slab for 1st floor 2 2 0% 31-Jul-15 03-Aug-15 0 1 const
A1420 construct metal deck and concrete slab for 2nd floor 2 2 0% 11-Aug-15 12-Aug-15 0 2 const
A1450 construct metal deck and concrete slab for 3rd floor 2 2 0% 20-Aug-15 21-Aug-15 0 3 const
A1480 construct metal deck and concrete slab for 4th floor 2 2 0% 31-Aug-15 01-Sep-15 0 4 const
29 05 12 19 26 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20
April 2015 May 2015 June 2015 July 2015 August 2015 September 2015
contract award, 01-Apr-15
NTP, 10-Apr-15*
permanent power available
29-Apr-15, lab2- Nbourdier.1.4 mobilization
MOB
20-May-15, lab2- Nbourdier.5 submittals
prepare and submit shop drawings and material data
13-Aug-15, lab2- Nbourdier.7 fabricate
fabricate and deliver concrete panels
fabricate and deliver framing
fabricate and deliver steel
order & deliver roofing
order and deliver A/C system
order and deliver ceilings
order and deliver doors
order and deliver flooring
order and deliver plumbing
order electrical
11-Jun-15, lab2- Nbourdier.6 approvals
review & approve shop drawings & material data
25-Jun-15, lab2- Nbourdier.4.1.1 site work & utilities
install erosion control
rough grading
utility installation
curbs and sidewalks
fine grading
install parking lot drainage
parking lot pavement
pavement striping
site lighting
17-Aug-15, lab2- Nbourdier.4.4 FD
Backfill
construct basement slab-FRPC
construct concrete FDN walls
construct footings
excavate for foundation
FRPC transformer pad
waterproofing FDN walls
11-Sep-15
construct interior CMU wall for s
construct interior CMU
construct in
construct interior CMU wall for stair at fir
construct metal deck and concrete slab for 1st
construct metal deck and concrete slab
construct metal deck and conc
construct metal dec
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
summary
Page 1 of 3 TASK filter: All Activities
© Oracle Corporation
Activity ID Activity Name Remaining
Duration
Original
Duration
Schedule %
Complete
Start Finish Total
Float
floor type of
work
A1510 install roof framing 2 2 0% 10-Sep-15 11-Sep-15 25 5 const
A1400 steel framing for 1st floor 4 4 0% 04-Aug-15 07-Aug-15 0 1 const
A1430 steel framing for 2nd floor 4 4 0% 13-Aug-15 18-Aug-15 0 2 const
A1460 steel framing for 3rd floor 4 4 0% 24-Aug-15 27-Aug-15 0 3 const
A1490 steel framing for 4th floor 4 4 0% 02-Sep-15 08-Sep-15 0 4 const
lab2- Nbourdier.4.3 building enclosurelab2- Nbourdier.4.3 building enclosure 23 23 0% 14-Sep-15 15-Oct-15 81
A1540 install curtain walls and windows 10 10 0% 24-Sep-15 07-Oct-15 86 const
A1560 install exterior doors 2 2 0% 24-Sep-15 25-Sep-15 36 1 const
A1550 install precast concrete panels 15 15 0% 24-Sep-15 15-Oct-15 81 const
A1530 install roof 5 5 0% 17-Sep-15 23-Sep-15 25 5 const
A1520 install roof sheathing 3 3 0% 14-Sep-15 16-Sep-15 25 5 const
lab2- Nbourdier.4.5 interior constructionlab2- Nbourdier.4.5 interior construction 125 125 0% 13-Aug-15 12-Feb-16 105
A1740 finish ceilings- 1st floor 3 3 0% 24-Nov-15 27-Nov-15 7 1 const
A1750 finish ceilings- 2nd floor 3 3 0% 03-Dec-15 07-Dec-15 10 2 const
A1760 finish ceilings- 3rd floor 3 3 0% 08-Dec-15 10-Dec-15 16 3 const
A1770 finish ceilings- 4th floor 3 3 0% 11-Dec-15 15-Dec-15 35 4 const
A1730 finish ceilings- basement 2 2 0% 18-Nov-15 19-Nov-15 5 bas const
A2100 install AC on roof 5 5 0% 24-Sep-15 30-Sep-15 196 5 const
A1690 install doors and door frames- 1st floor 3 3 0% 24-Nov-15 27-Nov-15 0 1 const
A1700 install doors and door frames- 2nd floor 3 3 0% 30-Nov-15 02-Dec-15 0 2 const
A1710 install doors and door frames- 3rd floor 3 3 0% 03-Dec-15 07-Dec-15 0 3 const
A1720 install doors and door frames- 4th floor 3 3 0% 08-Dec-15 10-Dec-15 0 4 const
A1680.1 install doors and frames - basement 3 3 0% 18-Nov-15 23-Nov-15 0 bas const
A1620 install drywall basement 3 3 0% 13-Nov-15 17-Nov-15 0 bas const
A1630 install drywall first floor 5 5 0% 13-Oct-15 19-Oct-15 24 1 const
A1660 install drywall fourth floor 5 5 0% 11-Nov-15 17-Nov-15 12 4 const
A1640 install drywall second floor 5 5 0% 22-Oct-15 28-Oct-15 20 2 const
A1650 install drywall third floor 5 5 0% 02-Nov-15 06-Nov-15 16 3 const
A1680 install elevator cab & machinery 18 18 0% 10-Sep-15 05-Oct-15 68 const
A1830 install floor tiles- basement 6 6 0% 14-Dec-15 21-Dec-15 0 bas const
A1840 install floor tiles- first floor 9 9 0% 22-Dec-15 05-Jan-16 0 1 const
A1870 install floor tiles- fourth floor 9 9 0% 02-Feb-16 12-Feb-16 0 4 const
A1850 install floor tiles- second floor 9 9 0% 06-Jan-16 18-Jan-16 0 2 const
A1860 install floor tiles- third floor 9 9 0% 20-Jan-16 01-Feb-16 0 3 const
A2120 install hot water heater 2 2 0% 09-Oct-15* 13-Oct-15 0 bas u
A1940 install kitchens 25 25 0% 09-Oct-15 13-Nov-15 60 const
A1570 interior framing basement 7 7 0% 18-Aug-15 26-Aug-15 20 bas const
A1580 interior framing first floor 7 7 0% 13-Aug-15 21-Aug-15 24 1 const
A1610 interior framing fourth floor 7 7 0% 14-Sep-15 22-Sep-15 0 4 const
A1590 interior framing second floor 7 7 0% 24-Aug-15 01-Sep-15 20 2 const
A1600 interior framing third floor 7 7 0% 02-Sep-15 11-Sep-15 0 3 const
A1890 MEP finishes 1st floor 5 5 0% 30-Nov-15 04-Dec-15 7 1 const
A1900 MEP finishes 2nd floor 5 5 0% 08-Dec-15 14-Dec-15 10 2 const
A1910 MEP finishes 3rd floor 5 5 0% 11-Dec-15 17-Dec-15 16 3 const
A1920 MEP finishes 4th floor 5 5 0% 16-Dec-15 22-Dec-15 35 4 const
A1880 MEP finishes basement 5 5 0% 23-Nov-15 30-Nov-15 5 bas const
A1780 paint basement 4 4 0% 08-Dec-15 11-Dec-15 0 bas const
A1790 paint first floor 4 4 0% 14-Dec-15 17-Dec-15 2 1 const
A1820 paint fourth floor 4 4 0% 31-Dec-15 06-Jan-16 17 4 const
A1800 paint second floor 4 4 0% 18-Dec-15 23-Dec-15 7 2 const
A1810 paint third floor 4 4 0% 24-Dec-15 30-Dec-15 12 3 const
A1670 stairs and railings 20 20 0% 06-Oct-15 03-Nov-15 68 const
lab2- Nbourdier.4.5.1 Rough-in worklab2- Nbourdier.4.5.1 Rough-in work 57 57 0% 24-Aug-15 12-Nov-15 10
A1950 rough in electric basement 10 10 0% 30-Oct-15 12-Nov-15 0 bas const
A1960 rough in electric first floor 10 10 0% 28-Sep-15 09-Oct-15 24 1 const
A1990 rough in electric fourth floor 10 10 0% 28-Oct-15 10-Nov-15 12 4 const
A1970 rough in electric second floor 10 10 0% 07-Oct-15 21-Oct-15 20 2 const
A1980 rough in electric third floor 10 10 0% 19-Oct-15 30-Oct-15 16 3 const
A2020 rough in HVAC 2nd floor 12 12 0% 21-Sep-15 06-Oct-15 20 2 const
A2030 rough in HVAC 3rd floor 12 12 0% 30-Sep-15 16-Oct-15 16 3 const
29 05 12 19 26 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20
April 2015 May 2015 June 2015 July 2015 August 2015 September 2015
install roof
steel framing for 1st floor
steel framing for 2nd floor
steel framing for 3rd floo
steel framing
instal
interior framing basement
interior framing first floor
interior framing seco
interior fra
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
summary
Page 2 of 3 TASK filter: All Activities
© Oracle Corporation
Activity ID Activity Name Remaining
Duration
Original
Duration
Schedule %
Complete
Start Finish Total
Float
floor type of
work
A2040 rough in HVAC 4th floor 12 12 0% 09-Oct-15 27-Oct-15 12 4 const
A2000 rough in HVAC basement 12 12 0% 14-Oct-15 29-Oct-15 0 bas const
A2010 rough in HVAC first floor 12 12 0% 10-Sep-15 25-Sep-15 24 1 const
A2050 rough in plumbing basement 12 12 0% 24-Aug-15*09-Sep-15 20 bas const
A2060 rough in plumbing first floor 12 12 0% 27-Aug-15*14-Sep-15 24 1 const
A2090 rough in plumbing fourth floor 12 12 0% 23-Sep-15 08-Oct-15 0 4 const
A2070 rough in plumbing second floor 12 12 0% 02-Sep-15 18-Sep-15 20 2 const
A2080 rough in plumbing third floor 12 12 0% 14-Sep-15 29-Sep-15 16 3 const
lab2- Nbourdier.3 post constructionlab2- Nbourdier.3 post construction 51 51 0% 22-Mar-16 01-Jun-16 0
A1170 obtain certificate of occupancy 0 0 0% 01-Jun-16 0 Post Co
A1080 punchlist 30 30 0% 22-Mar-16 02-May-16 0 Post Co
29 05 12 19 26 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20
April 2015 May 2015 June 2015 July 2015 August 2015 September 2015
rough in plum
rough in
rou
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
summary
Page 3 of 3 TASK filter: All Activities
© Oracle Corporation

More Related Content

Viewers also liked

Noe Guevara Resume
Noe Guevara ResumeNoe Guevara Resume
Noe Guevara Resumenoe guevara
 
Genetic engineering Admissions
Genetic engineering AdmissionsGenetic engineering Admissions
Genetic engineering Admissionsprovostseo
 
La función pública y la modernización del Estado
La función pública y la modernización del EstadoLa función pública y la modernización del Estado
La función pública y la modernización del EstadoJosé Marinero Cortés
 
HalcrowSustainability2010_lowres[1]
HalcrowSustainability2010_lowres[1]HalcrowSustainability2010_lowres[1]
HalcrowSustainability2010_lowres[1]Richard Rhydderch
 
ឧបសម្ព័ន្ធទី១
ឧបសម្ព័ន្ធទី១ឧបសម្ព័ន្ធទី១
ឧបសម្ព័ន្ធទី១nhongsim
 
Kenapa Saya Bangga Menjadi Orang Indonesia?
Kenapa Saya Bangga Menjadi Orang Indonesia?Kenapa Saya Bangga Menjadi Orang Indonesia?
Kenapa Saya Bangga Menjadi Orang Indonesia?rcvaganza
 
Evaluación de impacto ambiental de los equipos de perforación
Evaluación de impacto ambiental de los equipos de perforaciónEvaluación de impacto ambiental de los equipos de perforación
Evaluación de impacto ambiental de los equipos de perforaciónjsaldari
 
Simile presentation
Simile presentationSimile presentation
Simile presentationsonigillette
 
Diskusi kelompok pemetaan2
Diskusi kelompok pemetaan2Diskusi kelompok pemetaan2
Diskusi kelompok pemetaan2Nurdiana Sofiani
 
Market Segmentation
Market SegmentationMarket Segmentation
Market SegmentationMunna Islam
 
Displaying quantitative data with graphs
 Displaying quantitative data with graphs Displaying quantitative data with graphs
Displaying quantitative data with graphsKimmie Patricio
 
RL.11-12.2 assessment11
RL.11-12.2 assessment11 RL.11-12.2 assessment11
RL.11-12.2 assessment11 Jkeigher
 

Viewers also liked (19)

Noe Guevara Resume
Noe Guevara ResumeNoe Guevara Resume
Noe Guevara Resume
 
Yercaaud Trip!
Yercaaud Trip!Yercaaud Trip!
Yercaaud Trip!
 
Simon CV June 2015
Simon CV June 2015Simon CV June 2015
Simon CV June 2015
 
Genetic engineering Admissions
Genetic engineering AdmissionsGenetic engineering Admissions
Genetic engineering Admissions
 
La función pública y la modernización del Estado
La función pública y la modernización del EstadoLa función pública y la modernización del Estado
La función pública y la modernización del Estado
 
bharti
bhartibharti
bharti
 
HalcrowSustainability2010_lowres[1]
HalcrowSustainability2010_lowres[1]HalcrowSustainability2010_lowres[1]
HalcrowSustainability2010_lowres[1]
 
farhan scan dco
farhan scan dcofarhan scan dco
farhan scan dco
 
ឧបសម្ព័ន្ធទី១
ឧបសម្ព័ន្ធទី១ឧបសម្ព័ន្ធទី១
ឧបសម្ព័ន្ធទី១
 
Kenapa Saya Bangga Menjadi Orang Indonesia?
Kenapa Saya Bangga Menjadi Orang Indonesia?Kenapa Saya Bangga Menjadi Orang Indonesia?
Kenapa Saya Bangga Menjadi Orang Indonesia?
 
Evaluación de impacto ambiental de los equipos de perforación
Evaluación de impacto ambiental de los equipos de perforaciónEvaluación de impacto ambiental de los equipos de perforación
Evaluación de impacto ambiental de los equipos de perforación
 
RR_2011
RR_2011RR_2011
RR_2011
 
Media theories
Media theoriesMedia theories
Media theories
 
Simile presentation
Simile presentationSimile presentation
Simile presentation
 
Diskusi kelompok pemetaan2
Diskusi kelompok pemetaan2Diskusi kelompok pemetaan2
Diskusi kelompok pemetaan2
 
Market Segmentation
Market SegmentationMarket Segmentation
Market Segmentation
 
Displaying quantitative data with graphs
 Displaying quantitative data with graphs Displaying quantitative data with graphs
Displaying quantitative data with graphs
 
RESUME
RESUMERESUME
RESUME
 
RL.11-12.2 assessment11
RL.11-12.2 assessment11 RL.11-12.2 assessment11
RL.11-12.2 assessment11
 

Similar to Nbourdier-lab2-gantt chart with activities-

12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...
12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...
12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...Rodger McKinley
 
HSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activityHSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activityRoumik Mukherjee
 
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016Ahmed Mehrem
 
Spindrift-cinematique-traduit
Spindrift-cinematique-traduitSpindrift-cinematique-traduit
Spindrift-cinematique-traduitEmilie Guichard
 
Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdfZewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdfAhmed Mehrem
 
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)Allan Leyte
 
CICPA Updated Schedule Dtd 130816
CICPA Updated Schedule Dtd 130816CICPA Updated Schedule Dtd 130816
CICPA Updated Schedule Dtd 130816Manish Shah
 
Final Majarrah rev 0
Final Majarrah rev 0Final Majarrah rev 0
Final Majarrah rev 0Ahmed Mehrem
 
Sunshine_ W2 Dec'23_09.12.23.pptx
Sunshine_ W2 Dec'23_09.12.23.pptxSunshine_ W2 Dec'23_09.12.23.pptx
Sunshine_ W2 Dec'23_09.12.23.pptxabirsengupta9
 
Single Family Gantt Chart-John Mueller
Single Family Gantt Chart-John MuellerSingle Family Gantt Chart-John Mueller
Single Family Gantt Chart-John MuellerJohn Mueller
 

Similar to Nbourdier-lab2-gantt chart with activities- (20)

01. P269 - Project Implementation Programme - Rev 00
01. P269 - Project Implementation Programme -  Rev 0001. P269 - Project Implementation Programme -  Rev 00
01. P269 - Project Implementation Programme - Rev 00
 
IHH Healthcare Tender Programme.pdf
IHH Healthcare Tender Programme.pdfIHH Healthcare Tender Programme.pdf
IHH Healthcare Tender Programme.pdf
 
12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...
12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...
12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...
 
HSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activityHSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activity
 
Project Schedule - Level IV Schedule
Project Schedule - Level IV ScheduleProject Schedule - Level IV Schedule
Project Schedule - Level IV Schedule
 
Weekly report no 19
Weekly report no 19Weekly report no 19
Weekly report no 19
 
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
 
Spindrift-cinematique-traduit
Spindrift-cinematique-traduitSpindrift-cinematique-traduit
Spindrift-cinematique-traduit
 
Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdfZewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdf
 
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
 
10. Overall Implementation Programme
10. Overall Implementation Programme10. Overall Implementation Programme
10. Overall Implementation Programme
 
HOP Yick BD Ltd SMED
HOP Yick BD Ltd SMEDHOP Yick BD Ltd SMED
HOP Yick BD Ltd SMED
 
CICPA Updated Schedule Dtd 130816
CICPA Updated Schedule Dtd 130816CICPA Updated Schedule Dtd 130816
CICPA Updated Schedule Dtd 130816
 
ERUP WBS
ERUP WBSERUP WBS
ERUP WBS
 
Final Majarrah rev 0
Final Majarrah rev 0Final Majarrah rev 0
Final Majarrah rev 0
 
W15 Weekly Report RME
W15 Weekly Report RMEW15 Weekly Report RME
W15 Weekly Report RME
 
ARB JANADREA 25.01.16 UPDATE PM
ARB JANADREA 25.01.16 UPDATE  PMARB JANADREA 25.01.16 UPDATE  PM
ARB JANADREA 25.01.16 UPDATE PM
 
Sunshine_ W2 Dec'23_09.12.23.pptx
Sunshine_ W2 Dec'23_09.12.23.pptxSunshine_ W2 Dec'23_09.12.23.pptx
Sunshine_ W2 Dec'23_09.12.23.pptx
 
Monthly Progress Report No.13 - September 2011
Monthly Progress Report No.13 - September 2011Monthly Progress Report No.13 - September 2011
Monthly Progress Report No.13 - September 2011
 
Single Family Gantt Chart-John Mueller
Single Family Gantt Chart-John MuellerSingle Family Gantt Chart-John Mueller
Single Family Gantt Chart-John Mueller
 

Nbourdier-lab2-gantt chart with activities-

  • 1. Activity ID Activity Name Remaining Duration Original Duration Schedule % Complete Start Finish Total Float floor type of work lab2- Nbourdier Condo schedulelab2- Nbourdier Condo schedule 306 306 0% 01-Apr-15 01-Jun-16 30 lab2- Nbourdier.1 milestoneslab2- Nbourdier.1 milestones 295 295 0% 01-Apr-15 31-May-16 0 A1030 building watertight 0 0 0% 24-Sep-15 24-Sep-15 25 const A1000 contract award 0 0 0% 01-Apr-15 0 pre con A1060 final completion 20 20 0% 03-May-16 31-May-16 0 const A1010 NTP 0 0 0% 10-Apr-15* 0 pre con A1040 permanent power available 7 7 0% 26-Jun-15 06-Jul-15 152 u A1050 substantial completion 25 25 0% 15-Feb-16 21-Mar-16 0 const lab2- Nbourdier.1.4 mobilizationlab2- Nbourdier.1.4 mobilization 14 14 0% 10-Apr-15 29-Apr-15 0 A1180 MOB 14 14 0% 10-Apr-15 29-Apr-15 0 pre con lab2- Nbourdier.2 procurementlab2- Nbourdier.2 procurement 0 0 0% 0 lab2- Nbourdier.5 submittalslab2- Nbourdier.5 submittals 15 15 0% 30-Apr-15 20-May-15 0 A1220 prepare and submit shop drawings and material data15 15 0% 30-Apr-15 20-May-15 0 Procure lab2- Nbourdier.7 fabricate and deliverlab2- Nbourdier.7 fabricate and deliver 45 45 0% 12-Jun-15 13-Aug-15 109 A1210 fabricate and deliver concrete panels 45 45 0% 12-Jun-15 13-Aug-15 109 Procure A1160 fabricate and deliver framing 30 30 0% 12-Jun-15 23-Jul-15 37 Procure A1200 fabricate and deliver steel 35 35 0% 12-Jun-15 30-Jul-15 0 Procure A1150 order & deliver roofing 40 40 0% 12-Jun-15 06-Aug-15 50 Procure A1110 order and deliver A/C system 20 20 0% 12-Jun-15 09-Jul-15 66 Procure A1120 order and deliver ceilings 20 20 0% 12-Jun-15 09-Jul-15 96 Procure A1090 order and deliver doors 20 20 0% 12-Jun-15 09-Jul-15 89 Procure A1100 order and deliver flooring 15 15 0% 12-Jun-15 02-Jul-15 112 Procure A1130 order and deliver plumbing 30 30 0% 12-Jun-15 23-Jul-15 42 Procure A1140 order electrical 20 20 0% 12-Jun-15 09-Jul-15 78 Procure lab2- Nbourdier.6 approvalslab2- Nbourdier.6 approvals 15 15 0% 21-May-15 11-Jun-15 0 A1070 review & approve shop drawings & material data 15 15 0% 21-May-15 11-Jun-15 0 Procure lab2- Nbourdier.4 constructionlab2- Nbourdier.4 construction 199 199 0% 30-Apr-15 12-Feb-16 105 lab2- Nbourdier.4.1 site worklab2- Nbourdier.4.1 site work 109 109 0% 30-Apr-15 01-Oct-15 90 lab2- Nbourdier.4.1.1 site work & utilitieslab2- Nbourdier.4.1.1 site work & utilities 40 40 0% 30-Apr-15 25-Jun-15 152 A1240 install erosion control 3 3 0% 07-May-15 11-May-15 37 site A1230 rough grading 5 5 0% 30-Apr-15 06-May-15 37 site A1250 utility installation 15 15 0% 05-Jun-15 25-Jun-15 152 u lab2- Nbourdier.4.1.2 landscaping/ parking lotlab2- Nbourdier.4.1.2 landscaping/ parking lot 84 84 0% 05-Jun-15 01-Oct-15 90 A1310 curbs and sidewalks 13 13 0% 11-Aug-15 27-Aug-15 90 site A1260 fine grading 25 25 0% 16-Jun-15 20-Jul-15 90 site A1930 install exterior signage 4 4 0% 28-Sep-15 01-Oct-15 90 const A1270 install parking lot drainage 7 7 0% 05-Jun-15 15-Jun-15 90 u A1320 landscaping 20 20 0% 28-Aug-15 25-Sep-15 90 site A1280 parking lot pavement 10 10 0% 28-Jul-15 10-Aug-15 90 site A1290 pavement striping 5 5 0% 21-Jul-15 27-Jul-15 90 site A1300 site lighting 5 5 0% 11-Aug-15 17-Aug-15 98 u lab2- Nbourdier.4.4 FDN constructionlab2- Nbourdier.4.4 FDN construction 69 69 0% 12-May-15 17-Aug-15 20 A1380 Backfill 3 3 0% 13-Aug-15 17-Aug-15 20 site A1360 construct basement slab-FRPC 5 5 0% 04-Aug-15 10-Aug-15 20 bas const A1350 construct concrete FDN walls 10 10 0% 03-Jun-15 16-Jun-15 37 const A1340 construct footings 7 7 0% 22-May-15 02-Jun-15 37 const A1330 excavate for foundation 17 17 0% 12-May-15 04-Jun-15 37 const A2110 FRPC transformer pad 3 3 0% 05-Jun-15 09-Jun-15 59 const A1370 waterproofing FDN walls 2 2 0% 11-Aug-15 12-Aug-15 20 const lab2- Nbourdier.4.2 structurelab2- Nbourdier.4.2 structure 30 30 0% 31-Jul-15 11-Sep-15 25 A1440 construct interior CMU wall for stair at 2nd floor 1 1 0% 19-Aug-15 19-Aug-15 0 2 const A1470 construct interior CMU wall for stair at 3rd floor 1 1 0% 28-Aug-15 28-Aug-15 0 3 const A1500 construct interior CMU wall for stair at 4th floor 1 1 0% 09-Sep-15 09-Sep-15 25 4 const A1410 construct interior CMU wall for stair at first floor 1 1 0% 10-Aug-15 10-Aug-15 0 1 const A1390 construct metal deck and concrete slab for 1st floor 2 2 0% 31-Jul-15 03-Aug-15 0 1 const A1420 construct metal deck and concrete slab for 2nd floor 2 2 0% 11-Aug-15 12-Aug-15 0 2 const A1450 construct metal deck and concrete slab for 3rd floor 2 2 0% 20-Aug-15 21-Aug-15 0 3 const A1480 construct metal deck and concrete slab for 4th floor 2 2 0% 31-Aug-15 01-Sep-15 0 4 const 29 05 12 19 26 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 April 2015 May 2015 June 2015 July 2015 August 2015 September 2015 contract award, 01-Apr-15 NTP, 10-Apr-15* permanent power available 29-Apr-15, lab2- Nbourdier.1.4 mobilization MOB 20-May-15, lab2- Nbourdier.5 submittals prepare and submit shop drawings and material data 13-Aug-15, lab2- Nbourdier.7 fabricate fabricate and deliver concrete panels fabricate and deliver framing fabricate and deliver steel order & deliver roofing order and deliver A/C system order and deliver ceilings order and deliver doors order and deliver flooring order and deliver plumbing order electrical 11-Jun-15, lab2- Nbourdier.6 approvals review & approve shop drawings & material data 25-Jun-15, lab2- Nbourdier.4.1.1 site work & utilities install erosion control rough grading utility installation curbs and sidewalks fine grading install parking lot drainage parking lot pavement pavement striping site lighting 17-Aug-15, lab2- Nbourdier.4.4 FD Backfill construct basement slab-FRPC construct concrete FDN walls construct footings excavate for foundation FRPC transformer pad waterproofing FDN walls 11-Sep-15 construct interior CMU wall for s construct interior CMU construct in construct interior CMU wall for stair at fir construct metal deck and concrete slab for 1st construct metal deck and concrete slab construct metal deck and conc construct metal dec Actual Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone summary Page 1 of 3 TASK filter: All Activities © Oracle Corporation
  • 2. Activity ID Activity Name Remaining Duration Original Duration Schedule % Complete Start Finish Total Float floor type of work A1510 install roof framing 2 2 0% 10-Sep-15 11-Sep-15 25 5 const A1400 steel framing for 1st floor 4 4 0% 04-Aug-15 07-Aug-15 0 1 const A1430 steel framing for 2nd floor 4 4 0% 13-Aug-15 18-Aug-15 0 2 const A1460 steel framing for 3rd floor 4 4 0% 24-Aug-15 27-Aug-15 0 3 const A1490 steel framing for 4th floor 4 4 0% 02-Sep-15 08-Sep-15 0 4 const lab2- Nbourdier.4.3 building enclosurelab2- Nbourdier.4.3 building enclosure 23 23 0% 14-Sep-15 15-Oct-15 81 A1540 install curtain walls and windows 10 10 0% 24-Sep-15 07-Oct-15 86 const A1560 install exterior doors 2 2 0% 24-Sep-15 25-Sep-15 36 1 const A1550 install precast concrete panels 15 15 0% 24-Sep-15 15-Oct-15 81 const A1530 install roof 5 5 0% 17-Sep-15 23-Sep-15 25 5 const A1520 install roof sheathing 3 3 0% 14-Sep-15 16-Sep-15 25 5 const lab2- Nbourdier.4.5 interior constructionlab2- Nbourdier.4.5 interior construction 125 125 0% 13-Aug-15 12-Feb-16 105 A1740 finish ceilings- 1st floor 3 3 0% 24-Nov-15 27-Nov-15 7 1 const A1750 finish ceilings- 2nd floor 3 3 0% 03-Dec-15 07-Dec-15 10 2 const A1760 finish ceilings- 3rd floor 3 3 0% 08-Dec-15 10-Dec-15 16 3 const A1770 finish ceilings- 4th floor 3 3 0% 11-Dec-15 15-Dec-15 35 4 const A1730 finish ceilings- basement 2 2 0% 18-Nov-15 19-Nov-15 5 bas const A2100 install AC on roof 5 5 0% 24-Sep-15 30-Sep-15 196 5 const A1690 install doors and door frames- 1st floor 3 3 0% 24-Nov-15 27-Nov-15 0 1 const A1700 install doors and door frames- 2nd floor 3 3 0% 30-Nov-15 02-Dec-15 0 2 const A1710 install doors and door frames- 3rd floor 3 3 0% 03-Dec-15 07-Dec-15 0 3 const A1720 install doors and door frames- 4th floor 3 3 0% 08-Dec-15 10-Dec-15 0 4 const A1680.1 install doors and frames - basement 3 3 0% 18-Nov-15 23-Nov-15 0 bas const A1620 install drywall basement 3 3 0% 13-Nov-15 17-Nov-15 0 bas const A1630 install drywall first floor 5 5 0% 13-Oct-15 19-Oct-15 24 1 const A1660 install drywall fourth floor 5 5 0% 11-Nov-15 17-Nov-15 12 4 const A1640 install drywall second floor 5 5 0% 22-Oct-15 28-Oct-15 20 2 const A1650 install drywall third floor 5 5 0% 02-Nov-15 06-Nov-15 16 3 const A1680 install elevator cab & machinery 18 18 0% 10-Sep-15 05-Oct-15 68 const A1830 install floor tiles- basement 6 6 0% 14-Dec-15 21-Dec-15 0 bas const A1840 install floor tiles- first floor 9 9 0% 22-Dec-15 05-Jan-16 0 1 const A1870 install floor tiles- fourth floor 9 9 0% 02-Feb-16 12-Feb-16 0 4 const A1850 install floor tiles- second floor 9 9 0% 06-Jan-16 18-Jan-16 0 2 const A1860 install floor tiles- third floor 9 9 0% 20-Jan-16 01-Feb-16 0 3 const A2120 install hot water heater 2 2 0% 09-Oct-15* 13-Oct-15 0 bas u A1940 install kitchens 25 25 0% 09-Oct-15 13-Nov-15 60 const A1570 interior framing basement 7 7 0% 18-Aug-15 26-Aug-15 20 bas const A1580 interior framing first floor 7 7 0% 13-Aug-15 21-Aug-15 24 1 const A1610 interior framing fourth floor 7 7 0% 14-Sep-15 22-Sep-15 0 4 const A1590 interior framing second floor 7 7 0% 24-Aug-15 01-Sep-15 20 2 const A1600 interior framing third floor 7 7 0% 02-Sep-15 11-Sep-15 0 3 const A1890 MEP finishes 1st floor 5 5 0% 30-Nov-15 04-Dec-15 7 1 const A1900 MEP finishes 2nd floor 5 5 0% 08-Dec-15 14-Dec-15 10 2 const A1910 MEP finishes 3rd floor 5 5 0% 11-Dec-15 17-Dec-15 16 3 const A1920 MEP finishes 4th floor 5 5 0% 16-Dec-15 22-Dec-15 35 4 const A1880 MEP finishes basement 5 5 0% 23-Nov-15 30-Nov-15 5 bas const A1780 paint basement 4 4 0% 08-Dec-15 11-Dec-15 0 bas const A1790 paint first floor 4 4 0% 14-Dec-15 17-Dec-15 2 1 const A1820 paint fourth floor 4 4 0% 31-Dec-15 06-Jan-16 17 4 const A1800 paint second floor 4 4 0% 18-Dec-15 23-Dec-15 7 2 const A1810 paint third floor 4 4 0% 24-Dec-15 30-Dec-15 12 3 const A1670 stairs and railings 20 20 0% 06-Oct-15 03-Nov-15 68 const lab2- Nbourdier.4.5.1 Rough-in worklab2- Nbourdier.4.5.1 Rough-in work 57 57 0% 24-Aug-15 12-Nov-15 10 A1950 rough in electric basement 10 10 0% 30-Oct-15 12-Nov-15 0 bas const A1960 rough in electric first floor 10 10 0% 28-Sep-15 09-Oct-15 24 1 const A1990 rough in electric fourth floor 10 10 0% 28-Oct-15 10-Nov-15 12 4 const A1970 rough in electric second floor 10 10 0% 07-Oct-15 21-Oct-15 20 2 const A1980 rough in electric third floor 10 10 0% 19-Oct-15 30-Oct-15 16 3 const A2020 rough in HVAC 2nd floor 12 12 0% 21-Sep-15 06-Oct-15 20 2 const A2030 rough in HVAC 3rd floor 12 12 0% 30-Sep-15 16-Oct-15 16 3 const 29 05 12 19 26 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 April 2015 May 2015 June 2015 July 2015 August 2015 September 2015 install roof steel framing for 1st floor steel framing for 2nd floor steel framing for 3rd floo steel framing instal interior framing basement interior framing first floor interior framing seco interior fra Actual Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone summary Page 2 of 3 TASK filter: All Activities © Oracle Corporation
  • 3. Activity ID Activity Name Remaining Duration Original Duration Schedule % Complete Start Finish Total Float floor type of work A2040 rough in HVAC 4th floor 12 12 0% 09-Oct-15 27-Oct-15 12 4 const A2000 rough in HVAC basement 12 12 0% 14-Oct-15 29-Oct-15 0 bas const A2010 rough in HVAC first floor 12 12 0% 10-Sep-15 25-Sep-15 24 1 const A2050 rough in plumbing basement 12 12 0% 24-Aug-15*09-Sep-15 20 bas const A2060 rough in plumbing first floor 12 12 0% 27-Aug-15*14-Sep-15 24 1 const A2090 rough in plumbing fourth floor 12 12 0% 23-Sep-15 08-Oct-15 0 4 const A2070 rough in plumbing second floor 12 12 0% 02-Sep-15 18-Sep-15 20 2 const A2080 rough in plumbing third floor 12 12 0% 14-Sep-15 29-Sep-15 16 3 const lab2- Nbourdier.3 post constructionlab2- Nbourdier.3 post construction 51 51 0% 22-Mar-16 01-Jun-16 0 A1170 obtain certificate of occupancy 0 0 0% 01-Jun-16 0 Post Co A1080 punchlist 30 30 0% 22-Mar-16 02-May-16 0 Post Co 29 05 12 19 26 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 April 2015 May 2015 June 2015 July 2015 August 2015 September 2015 rough in plum rough in rou Actual Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone summary Page 3 of 3 TASK filter: All Activities © Oracle Corporation