Activity ID Activity Name Original
Duration
Start Finish
SECO
SECON Nile Tower Project MEP Base Line 549 08-Jul-14 26-Apr-16
Gene
General 549 08-Jul-14 26-Apr-16
SSG10 Letter Of Award (L.O.A) 0 08-Jul-14
SSG20 Advanced Payment 0 14-Jul-14
SSG30 Mobilization at Site 26 14-Jul-14 13-Aug-14
SSG70 Permanent Source For Water Supply (By Others) 0 08-Oct-15
SSG50 Permanent Source For Electricity (By Others) 0 29-Nov-15
SSG60 Permanent Source For Telephone & Data and Active Switch (By Others) 0 29-Nov-15
SSG18 Testing & Commissioning and Start-Up 78 23-Jan-16 24-Apr-16
SSG20 Taking Over Certificate (T.O.C) 0 26-Apr-16
Engin
Engineering 375 08-Jul-14 28-Sep-15
Floo
Floors 375 08-Jul-14 28-Sep-15
Lo
Lower Basement B2 Shop Drawings 75 08-Jul-14 04-Oct-14
SS Receive Lower Basement MEP Design Package 0 08-Jul-14
SS Receive Lower Basement Approved Architecture Design Package 0 08-Jul-14
SS Receive Lower Basement Approved Structural Design Package 0 08-Jul-14
SS Receive Lower Basement Approved Architecture Shop Drawings 0 14-Jul-14
E
Electrical Systems Shop Drawings 38 13-Jul-14 27-Aug-14
Lighting System Shop Drawings 33 13-Jul-14 21-Aug-14
Lighting System Parking Floor Plan ( B-2 ) Rev 0 Submittal 5 13-Jul-14 20-Jul-14
Lighting System Parking Floor Plan ( B-2 ) Rev 0 Reply 14 20-Jul-14 06-Aug-14
Lighting System Parking Floor Plan ( B-2 ) Rev 1 Submittal 5 06-Aug-14 13-Aug-14
Lighting System Parking Floor Plan ( B-2 ) Rev 1 Approval 7 13-Aug-14 21-Aug-14
Power System Shop Drawings 33 15-Jul-14 23-Aug-14
Power System Parking Floor Plan ( B-2 ) Rev 0 Submittal 5 15-Jul-14 22-Jul-14
Power System Parking Floor Plan ( B-2 ) Rev 0 Reply 14 22-Jul-14 09-Aug-14
Power System Parking Floor Plan ( B-2 ) Rev 1 Submittal 5 10-Aug-14 14-Aug-14
Power System Parking Floor Plan ( B-2 ) Rev 1 Approval 7 16-Aug-14 23-Aug-14
Safety Lighting System Shop Drawings 34 17-Jul-14 27-Aug-14
Safety Lighting System Parking Floor Plan ( B-2 ) Rev 0 Submittal 5 17-Jul-14 27-Jul-14
Safety Lighting System Parking Floor Plan ( B-2 ) Rev 0 Reply 14 27-Jul-14 12-Aug-14
Safety Lighting System Parking Floor Plan ( B-2 ) Rev 1 Submittal 5 12-Aug-14 19-Aug-14
Safety Lighting System Parking Floor Plan ( B-2 ) Rev 1 Approval 7 19-Aug-14 27-Aug-14
Low Current Systems Shop Drawings 33 13-Jul-14 21-Aug-14
Fire Alarm System 33 13-Jul-14 21-Aug-14
Fire Alarm System Parking Floor Plan ( B-2 ) Rev 0 Submittal 5 13-Jul-14 20-Jul-14
Jun Jul Aug Sep Oct Nov Dec
Qtr 3 Qtr 4
2014
SECON Nile Tower Project MEP Base Line Secon Nile Tower Project Siemens Scope 21-Mar-16 17:19
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 1 of 1076 TASK filter: All Activities
© Primavera Systems, Inc
Activity ID Activity Name Original
Duration
Start Finish
Fire Alarm System Parking Floor Plan ( B-2 ) Rev 0 Reply 14 20-Jul-14 06-Aug-14
Fire Alarm System Parking Floor Plan ( B-2 ) Rev 1 Submittal 5 06-Aug-14 13-Aug-14
Fire Alarm System Parking Floor Plan ( B-2 ) Rev 1 Approval 7 13-Aug-14 21-Aug-14
Sound & Security systems 33 13-Jul-14 21-Aug-14
Sound & Security Systems Parking Floor Plan ( B-2 ) Rev 0 Submittal 5 13-Jul-14 20-Jul-14
Sound & Security Systems Parking Floor Plan ( B-2 ) Rev 0 Reply 14 20-Jul-14 06-Aug-14
Sound & Security Systems Parking Floor Plan ( B-2 ) Rev 1 Submittal 5 06-Aug-14 13-Aug-14
Sound & Security Systems Parking Floor Plan ( B-2 ) Rev 1 Approval 7 13-Aug-14 21-Aug-14
Voice,Data,IPTV systems 33 13-Jul-14 21-Aug-14
Voice, Data, IPTV Systems Parking Floor Plan ( B-2 ) Rev 0 Submittal 5 13-Jul-14 20-Jul-14
Voice, Data, IPTV Systems Parking Floor Plan ( B-2 ) Rev 0 Reply 14 20-Jul-14 06-Aug-14
Voice, Data, IPTV Systems Parking Floor Plan ( B-2 ) Rev 1 Submittal 5 06-Aug-14 13-Aug-14
Voice, Data, IPTV Systems Parking Floor Plan ( B-2 ) Rev 1 Approval 7 13-Aug-14 21-Aug-14
M
Mechanical Systems Shop Drawings 35 13-Jul-14 23-Aug-14
HVAC System Shop Drawings 33 13-Jul-14 21-Aug-14
HVAC System Parking Floor Plan ( B-2 ) Rev 0 Submittal 5 13-Jul-14 20-Jul-14
HVAC System Parking Floor Plan ( B-2 ) Rev 0 Reply 14 20-Jul-14 06-Aug-14
HVAC System Parking Floor Plan ( B-2 ) Rev 1 Submittal 5 06-Aug-14 13-Aug-14
HVAC System Parking Floor Plan ( B-2 ) Rev 1 Approval 7 13-Aug-14 21-Aug-14
Fire Fighting System Shop Drawings 33 13-Jul-14 21-Aug-14
Fire Fighting System Parking Floor Plan ( B-2 ) Rev 0 Submittal 5 13-Jul-14 20-Jul-14
Fire Fighting System Parking Floor Plan ( B-2 ) Rev 0 Reply 14 20-Jul-14 06-Aug-14
Fire Fighting System Parking Floor Plan ( B-2 ) Rev 1 Submittal 5 06-Aug-14 13-Aug-14
Fire Fighting System Parking Floor Plan ( B-2 ) Rev 1 Approval 7 13-Aug-14 21-Aug-14
Plumbing System Shop Drawings 35 13-Jul-14 23-Aug-14
Water Supply System Parking Floor Plan ( B-2 ) Rev 0 Submittal 5 13-Jul-14 20-Jul-14
Drainage System Parking Floor Plan ( B-2 ) Rev 0 Submittal 5 15-Jul-14 22-Jul-14
Water Supply System Parking Floor Plan ( B-2 ) Rev 0 Reply 14 20-Jul-14 06-Aug-14
Drainage System Parking Floor Plan ( B-2 ) Rev 0 Reply 14 22-Jul-14 09-Aug-14
Water Supply System Parking Floor Plan ( B-2 ) Rev 1 Submittal 5 06-Aug-14 13-Aug-14
Drainage System Parking Floor Plan ( B-2 ) Rev 1 Submittal 5 10-Aug-14 14-Aug-14
Water Supply System Parking Floor Plan ( B-2 ) Rev 1 Approval 7 13-Aug-14 21-Aug-14
Drainage System Parking Floor Plan ( B-2 ) Rev 1 Approval 7 16-Aug-14 23-Aug-14
C
Composite Shop Drawings 33 27-Aug-14 04-Oct-14
Composite Drawing for Lower Basement ( B-2 ) Rev 0 Submittal 5 27-Aug-14 03-Sep-14
Composite Drawing for Lower Basement ( B-2 ) Rev 0 Reply 14 03-Sep-14 20-Sep-14
Composite Drawing for Lower Basement ( B-2 ) Rev 1 Submittal 5 21-Sep-14 25-Sep-14
Composite Drawing for Lower Basement ( B-2 ) Rev 1 Approval 7 27-Sep-14 04-Oct-14
Jun Jul Aug Sep Oct Nov Dec
Qtr 3 Qtr 4
2014
SECON Nile Tower Project MEP Base Line Secon Nile Tower Project Siemens Scope 21-Mar-16 17:19
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 3 of 1076 TASK filter: All Activities
© Primavera Systems, Inc
Activity ID Activity Name Original
Duration
Start Finish
Up
Upper Basement B1 Shop Drawings 99 08-Jul-14 03-Nov-14
SS Receive Upper Basement MEP Design Package 0 08-Jul-14
SS Receive Upper Basement Approved Architecture Design Package 0 04-Aug-14
SS Receive Upper Basement Approved Structural Design Package 0 04-Aug-14
SS Receive Upper Basement Approved Architecture Shop Drawings 0 10-Aug-14
E
Electrical Systems Shop Drawings 37 10-Aug-14 22-Sep-14
Lighting System Shop Drawings 33 10-Aug-14 17-Sep-14
Lighting System Parking Floor Plan ( B-1 ) Rev 0 Submittal 5 10-Aug-14 17-Aug-14
Lighting System Parking Floor Plan ( B-1 ) Rev 0 Reply 14 17-Aug-14 02-Sep-14
Lighting System Parking Floor Plan ( B-1 ) Rev 1 Submittal 5 02-Sep-14 09-Sep-14
Lighting System Parking Floor Plan ( B-1 ) Rev 1 Approval 7 09-Sep-14 17-Sep-14
Power System Shop Drawings 33 12-Aug-14 20-Sep-14
Power System Parking Floor Plan ( B-1 ) Rev 0 Submittal 5 12-Aug-14 19-Aug-14
Power System Parking Floor Plan ( B-1 ) Rev 0 Reply 14 19-Aug-14 04-Sep-14
Power System Parking Floor Plan ( B-1 ) Rev 1 Submittal 5 04-Sep-14 11-Sep-14
Power System Parking Floor Plan ( B-1 ) Rev 1 Approval 7 11-Sep-14 20-Sep-14
Safety Lighting System Shop Drawings 33 14-Aug-14 22-Sep-14
Safety Lighting System Parking Floor Plan ( B-1 ) Rev 0 Submittal 5 14-Aug-14 21-Aug-14
Safety Lighting System Parking Floor Plan ( B-1 ) Rev 0 Reply 14 21-Aug-14 07-Sep-14
Safety Lighting System Parking Floor Plan ( B-1 ) Rev 1 Submittal 5 07-Sep-14 14-Sep-14
Safety Lighting System Parking Floor Plan ( B-1 ) Rev 1 Approval 7 14-Sep-14 22-Sep-14
Low Current Systems Shop Drawings 33 10-Aug-14 17-Sep-14
Fire Alarm System 33 10-Aug-14 17-Sep-14
Fire Alarm System Parking Floor Plan ( B-1 ) Rev 0 Submittal 5 10-Aug-14 17-Aug-14
Fire Alarm System Parking Floor Plan ( B-1 ) Rev 0 Reply 14 17-Aug-14 02-Sep-14
Fire Alarm System Parking Floor Plan ( B-1 ) Rev 1 Submittal 5 02-Sep-14 09-Sep-14
Fire Alarm System Parking Floor Plan ( B-1 ) Rev 1 Approval 7 09-Sep-14 17-Sep-14
Sound & Security systems 33 10-Aug-14 17-Sep-14
Sound & Security Systems Parking Floor Plan ( B-1 ) Rev 0 Submittal 5 10-Aug-14 17-Aug-14
Sound & Security Systems Parking Floor Plan ( B-1 ) Rev 0 Reply 14 17-Aug-14 02-Sep-14
Sound & Security Systems Parking Floor Plan ( B-1 ) Rev 1 Submittal 5 02-Sep-14 09-Sep-14
Sound & Security Systems Parking Floor Plan ( B-1 ) Rev 1 Approval 7 09-Sep-14 17-Sep-14
Voice,Data,IPTV systems 33 10-Aug-14 17-Sep-14
Voice, Data, IPTV Systems Parking Floor Plan ( B-1 ) Rev 0 Submittal 5 10-Aug-14 17-Aug-14
Voice, Data, IPTV Systems Parking Floor Plan ( B-1 ) Rev 0 Reply 14 17-Aug-14 02-Sep-14
Voice, Data, IPTV Systems Parking Floor Plan ( B-1 ) Rev 1 Submittal 5 02-Sep-14 09-Sep-14
Voice, Data, IPTV Systems Parking Floor Plan ( B-1 ) Rev 1 Approval 7 09-Sep-14 17-Sep-14
M
Mechanical Systems Shop Drawings 39 10-Aug-14 24-Sep-14
Jun Jul Aug Sep Oct Nov Dec
Qtr 3 Qtr 4
2014
SECON Nile Tower Project MEP Base Line Secon Nile Tower Project Siemens Scope 21-Mar-16 17:19
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 5 of 1076 TASK filter: All Activities
© Primavera Systems, Inc
Activity ID Activity Name Original
Duration
Start Finish
HVAC System Shop Drawings 33 10-Aug-14 17-Sep-14
HVAC System Parking Floor Plan ( B-1 ) Rev 0 Submittal 5 10-Aug-14 17-Aug-14
HVAC System Parking Floor Plan ( B-1 ) Rev 0 Reply 14 17-Aug-14 02-Sep-14
HVAC System Parking Floor Plan ( B-1 ) Rev 1 Submittal 5 02-Sep-14 09-Sep-14
HVAC System Parking Floor Plan ( B-1 ) Rev 1 Approval 7 09-Sep-14 17-Sep-14
Fire Fighting System Shop Drawings 33 10-Aug-14 17-Sep-14
Fire Fighting System Parking Floor Plan ( B-1 ) Rev 0 Submittal 5 10-Aug-14 17-Aug-14
Fire Fighting System Parking Floor Plan ( B-1 ) Rev 0 Reply 14 17-Aug-14 02-Sep-14
Fire Fighting System Parking Floor Plan ( B-1 ) Rev 1 Submittal 5 02-Sep-14 09-Sep-14
Fire Fighting System Parking Floor Plan ( B-1 ) Rev 1 Approval 7 09-Sep-14 17-Sep-14
Plumbing System Shop Drawings 36 13-Aug-14 24-Sep-14
Water Supply System Parking Floor Plan ( B-1 ) Rev 0 Submittal 5 13-Aug-14 20-Aug-14
Drainage System Parking Floor Plan ( B-1 ) Rev 0 Submittal 5 17-Aug-14 24-Aug-14
Water Supply System Parking Floor Plan ( B-1 ) Rev 0 Reply 14 20-Aug-14 06-Sep-14
Drainage System Parking Floor Plan ( B-1 ) Rev 0 Reply 14 24-Aug-14 09-Sep-14
Water Supply System Parking Floor Plan ( B-1 ) Rev 1 Submittal 5 07-Sep-14 11-Sep-14
Drainage System Parking Floor Plan ( B-1 ) Rev 1 Submittal 5 09-Sep-14 16-Sep-14
Water Supply System Parking Floor Plan ( B-1 ) Rev 1 Approval 7 13-Sep-14 20-Sep-14
Drainage System Parking Floor Plan ( B-1 ) Rev 1 Approval 7 16-Sep-14 24-Sep-14
C
Composite Shop Drawings 33 24-Sep-14 03-Nov-14
Composite Drawing for Upper Basement ( B-1 ) Rev 0 Submittal 5 24-Sep-14 01-Oct-14
Composite Drawing for Upper Basement ( B-1 ) Rev 0 Reply 14 01-Oct-14 19-Oct-14
Composite Drawing for Upper Basement ( B-1 ) Rev 1 Submittal 5 19-Oct-14 26-Oct-14
Composite Drawing for Upper Basement ( B-1 ) Rev 1 Approval 7 26-Oct-14 03-Nov-14
Lo
Lower Ground (BOH) Shop Drawings 168 08-Jul-14 24-Jan-15
SS Receive Lower Ground MEP Design Package 0 08-Jul-14
SS Receive Lower Ground Approved Architecture Design Package 0 30-Aug-14
SS Receive Lower Ground Approved Structural Design Package 0 30-Aug-14
SS Receive Lower Ground Approved Architecture Shop Drawings 0 04-Sep-14
SS Receive Lower Ground Approved Tiles Shop Drawings 0 25-Sep-14
E
Electrical Systems Shop Drawings 41 04-Sep-14 23-Oct-14
Lighting System Shop Drawings 33 04-Sep-14 14-Oct-14
Lighting System Lower Ground Floor Plan ( BOH ) Rev 0 Submittal 5 04-Sep-14 11-Sep-14
Lighting System Lower Ground Floor Plan ( BOH ) Rev 0 Reply 14 11-Sep-14 28-Sep-14
Lighting System Lower Ground Floor Plan ( BOH ) Rev 1 Submittal 5 28-Sep-14 05-Oct-14
Lighting System Lower Ground Floor Plan ( BOH ) Rev 1 Approval 7 05-Oct-14 14-Oct-14
Power System Shop Drawings 33 08-Sep-14 18-Oct-14
Power System Lower Ground Floor Plan ( BOH ) Rev 0 Submittal 5 08-Sep-14 15-Sep-14
Jun Jul Aug Sep Oct Nov Dec
Qtr 3 Qtr 4
2014
SECON Nile Tower Project MEP Base Line Secon Nile Tower Project Siemens Scope 21-Mar-16 17:19
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 7 of 1076 TASK filter: All Activities
© Primavera Systems, Inc
Activity ID Activity Name Original
Duration
Start Finish
Power System Lower Ground Floor Plan ( BOH ) Rev 0 Reply 14 15-Sep-14 01-Oct-14
Power System Lower Ground Floor Plan ( BOH ) Rev 1 Submittal 5 01-Oct-14 09-Oct-14
Power System Lower Ground Floor Plan ( BOH ) Rev 1 Approval 7 09-Oct-14 18-Oct-14
Safety Lighting System Shop Drawings 33 14-Sep-14 23-Oct-14
Safety Lighting System Lower Ground Floor Plan ( BOH ) Rev 0 Submittal 5 14-Sep-14 21-Sep-14
Safety Lighting System Lower Ground Floor Plan ( BOH ) Rev 0 Reply 14 21-Sep-14 08-Oct-14
Safety Lighting System Lower Ground Floor Plan ( BOH ) Rev 1 Submittal 5 08-Oct-14 15-Oct-14
Safety Lighting System Lower Ground Floor Plan ( BOH ) Rev 1 Approval 7 15-Oct-14 23-Oct-14
Low Current Systems Shop Drawings 33 04-Sep-14 14-Oct-14
Fire Alarm System 33 04-Sep-14 14-Oct-14
Fire Alarm System Lower Ground Floor Plan ( BOH ) Rev 0 Submittal 5 04-Sep-14 11-Sep-14
Fire Alarm System Lower Ground Floor Plan ( BOH ) Rev 0 Reply 14 11-Sep-14 28-Sep-14
Fire Alarm System Lower Ground Floor Plan ( BOH ) Rev 1 Submittal 5 28-Sep-14 05-Oct-14
Fire Alarm System Lower Ground Floor Plan ( BOH ) Rev 1 Approval 7 05-Oct-14 14-Oct-14
Sound & Security systems 33 04-Sep-14 14-Oct-14
Sound & Security Systems Lower Ground Floor Plan ( BOH ) Rev 0 Submittal 5 04-Sep-14 11-Sep-14
Sound & Security Systems Lower Ground Floor Plan ( BOH ) Rev 0 Reply 14 11-Sep-14 28-Sep-14
Sound & Security Systems Lower Ground Floor Plan ( BOH ) Rev 1 Submittal 5 28-Sep-14 05-Oct-14
Sound & Security Systems Lower Ground Floor Plan ( BOH ) Rev 1 Approval 7 05-Oct-14 14-Oct-14
Voice,Data,IPTV systems 33 04-Sep-14 14-Oct-14
Voice, Data, IPTV Systems Lower Ground Floor Plan ( BOH ) Rev 0 Submittal 5 04-Sep-14 11-Sep-14
Voice, Data, IPTV Systems Lower Ground Floor Plan ( BOH ) Rev 0 Reply 14 11-Sep-14 28-Sep-14
Voice, Data, IPTV Systems Lower Ground Floor Plan ( BOH ) Rev 1 Submittal 5 28-Sep-14 05-Oct-14
Voice, Data, IPTV Systems Lower Ground Floor Plan ( BOH ) Rev 1 Approval 7 05-Oct-14 14-Oct-14
M
Mechanical Systems Shop Drawings 86 04-Sep-14 15-Dec-14
HVAC System Shop Drawings 33 04-Sep-14 14-Oct-14
HVAC System Lower Ground Floor Plan ( BOH ) Rev 0 Submittal 5 04-Sep-14 11-Sep-14
HVAC System Lower Ground Floor Plan ( BOH ) Rev 0 Reply 14 11-Sep-14 28-Sep-14
HVAC System Lower Ground Floor Plan ( BOH ) Rev 1 Submittal 5 28-Sep-14 05-Oct-14
HVAC System Lower Ground Floor Plan ( BOH ) Rev 1 Approval 7 05-Oct-14 14-Oct-14
Fire Fighting System Shop Drawings 33 04-Sep-14 14-Oct-14
Fire Fighting System Lower Ground Floor Plan ( BOH ) Rev 0 Submittal 5 04-Sep-14 11-Sep-14
Fire Fighting System Lower Ground Floor Plan ( BOH ) Rev 0 Reply 14 11-Sep-14 28-Sep-14
Fire Fighting System Lower Ground Floor Plan ( BOH ) Rev 1 Submittal 5 28-Sep-14 05-Oct-14
Fire Fighting System Lower Ground Floor Plan ( BOH ) Rev 1 Approval 7 05-Oct-14 14-Oct-14
Plumbing System Shop Drawings 68 25-Sep-14 15-Dec-14
Toilet Details Types (T 28, T 29) Submittal Rev 0 5 25-Sep-14 02-Oct-14
Toilet Details Types (T 28, T 29) Reply Rev 0 14 02-Oct-14 20-Oct-14
Jun Jul Aug Sep Oct Nov Dec
Qtr 3 Qtr 4
2014
SECON Nile Tower Project MEP Base Line Secon Nile Tower Project Siemens Scope 21-Mar-16 17:19
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 9 of 1076 TASK filter: All Activities
© Primavera Systems, Inc
Activity ID Activity Name Original
Duration
Start Finish
Toilet Details Types (T 28, T 29) Submittal Rev 1 5 20-Oct-14 27-Oct-14
Toilet Details Types (T 28, T 29) Approval Rev 1 7 27-Oct-14 04-Nov-14
Water Supply System Lower Ground Floor Plan ( BOH ) Rev 0 Submittal 5 04-Nov-14 11-Nov-14
Drainage System Lower Ground Floor Plan ( BOH ) Rev 0 Submittal 5 06-Nov-14 13-Nov-14
Water Supply System Lower Ground Floor Plan ( BOH ) Rev 0 Reply 14 11-Nov-14 27-Nov-14
Drainage System Lower Ground Floor Plan ( BOH ) Rev 0 Reply 14 13-Nov-14 30-Nov-14
Water Supply System Lower Ground Floor Plan ( BOH ) Rev 1 Submittal 5 27-Nov-14 04-Dec-14
Drainage System Lower Ground Floor Plan ( BOH ) Rev 1 Submittal 5 30-Nov-14 07-Dec-14
Water Supply System Lower Ground Floor Plan ( BOH ) Rev 1 Approval 7 04-Dec-14 13-Dec-14
Drainage System Lower Ground Floor Plan ( BOH ) Rev 1 Approval 7 07-Dec-14 15-Dec-14
C
Composite Shop Drawings 33 15-Dec-14 24-Jan-15
Composite Drawing for Lower Ground Floor Plan ( BOH ) Rev 0 Submittal 5 15-Dec-14 22-Dec-14
Composite Drawing for Lower Ground Floor Plan ( BOH ) Rev 0 Reply 14 22-Dec-14 08-Jan-15
Composite Drawing for Lower Ground Floor Plan ( BOH ) Rev 1 Submittal 5 08-Jan-15 15-Jan-15
Composite Drawing for Lower Ground Floor Plan ( BOH ) Rev 1 Approval 7 15-Jan-15 24-Jan-15
Gr
Ground Floor Shop Drawings 195 08-Jul-14 24-Feb-15
SS Receive Ground Floor MEP Design Package 0 08-Jul-14
SS Receive Ground Floor Approved Architecture Design Package 0 24-Sep-14
SS Receive Ground Floor Approved Structural Design Package 0 24-Sep-14
SS Receive Ground Floor Approved Architecture Shop Drawings 0 30-Sep-14
SS Receive Ground Approved Tiles Shop Drawings 0 22-Oct-14
E
Electrical Systems Shop Drawings 45 30-Sep-14 22-Nov-14
Lighting System Shop Drawings 33 30-Sep-14 08-Nov-14
Lighting System Ground Floor Plan Rev 0 Submittal 5 30-Sep-14 08-Oct-14
Lighting System Ground Floor Plan Rev 0 Reply 14 08-Oct-14 25-Oct-14
Lighting System Ground Floor Plan Rev 1 Submittal 5 26-Oct-14 30-Oct-14
Lighting System Ground Floor Plan Rev 1 Approval 7 01-Nov-14 08-Nov-14
Power System Shop Drawings 33 05-Oct-14 13-Nov-14
Power System Ground Floor Plan Rev 0 Submittal 5 05-Oct-14 13-Oct-14
Power System Ground Floor Plan Rev 0 Reply 14 13-Oct-14 29-Oct-14
Power System Ground Floor Plan Rev 1 Submittal 5 29-Oct-14 05-Nov-14
Power System Ground Floor Plan Rev 1 Approval 7 05-Nov-14 13-Nov-14
Safety Lighting System Shop Drawings 33 15-Oct-14 22-Nov-14
Safety Lighting System Ground Floor Plan Rev 0 Submittal 5 15-Oct-14 22-Oct-14
Safety Lighting System Ground Floor Plan Rev 0 Reply 14 22-Oct-14 08-Nov-14
Safety Lighting System Ground Floor Plan Rev 1 Submittal 5 09-Nov-14 13-Nov-14
Safety Lighting System Ground Floor Plan Rev 1 Approval 7 15-Nov-14 22-Nov-14
Low Current Systems Shop Drawings 33 30-Sep-14 08-Nov-14
Jun Jul Aug Sep Oct Nov Dec
Qtr 3 Qtr 4
2014
SECON Nile Tower Project MEP Base Line Secon Nile Tower Project Siemens Scope 21-Mar-16 17:19
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 11 of 1076 TASK filter: All Activities
© Primavera Systems, Inc
Activity ID Activity Name Original
Duration
Start Finish
Fire Alarm System 33 30-Sep-14 08-Nov-14
Fire Alarm System Ground Floor Plan Rev 0 Submittal 5 30-Sep-14 08-Oct-14
Fire Alarm System Ground Floor Plan Rev 0 Reply 14 08-Oct-14 25-Oct-14
Fire Alarm System Ground Floor Plan Rev 1 Submittal 5 26-Oct-14 30-Oct-14
Fire Alarm System Ground Floor Plan Rev 1 Approval 7 01-Nov-14 08-Nov-14
Sound & Security systems 33 30-Sep-14 08-Nov-14
Sound & Security Systems Ground Floor Plan Rev 0 Submittal 5 30-Sep-14 08-Oct-14
Sound & Security Systems Ground Floor Plan Rev 0 Reply 14 08-Oct-14 25-Oct-14
Sound & Security Systems Ground Floor Plan Rev 1 Submittal 5 26-Oct-14 30-Oct-14
Sound & Security Systems Ground Floor Plan Rev 1 Approval 7 01-Nov-14 08-Nov-14
Voice,Data,IPTV systems 33 30-Sep-14 08-Nov-14
Voice, Data, IPTV Systems Ground Floor Plan Rev 0 Submittal 5 30-Sep-14 08-Oct-14
Voice, Data, IPTV Systems Ground Floor Plan Rev 0 Reply 14 08-Oct-14 25-Oct-14
Voice, Data, IPTV Systems Ground Floor Plan Rev 1 Submittal 5 26-Oct-14 30-Oct-14
Voice, Data, IPTV Systems Ground Floor Plan Rev 1 Approval 7 01-Nov-14 08-Nov-14
M
Mechanical Systems Shop Drawings 91 30-Sep-14 17-Jan-15
HVAC System Shop Drawings 33 30-Sep-14 08-Nov-14
HVAC System Ground Floor Plan Rev 0 Submittal 5 30-Sep-14 08-Oct-14
HVAC System Ground Floor Plan Rev 0 Reply 14 08-Oct-14 25-Oct-14
HVAC System Ground Floor Plan Rev 1 Submittal 5 26-Oct-14 30-Oct-14
HVAC System Ground Floor Plan Rev 1 Approval 7 01-Nov-14 08-Nov-14
Fire Fighting System Shop Drawings 33 30-Sep-14 08-Nov-14
Fire Fighting System Ground Floor Plan Rev 0 Submittal 5 30-Sep-14 08-Oct-14
Fire Fighting System Ground Floor Plan Rev 0 Reply 14 08-Oct-14 25-Oct-14
Fire Fighting System Ground Floor Plan Rev 1 Submittal 5 26-Oct-14 30-Oct-14
Fire Fighting System Ground Floor Plan Rev 1 Approval 7 01-Nov-14 08-Nov-14
Plumbing System Shop Drawings 69 27-Oct-14 17-Jan-15
Toilet Details Types (T10, T26 , T27, T31) Submittal Rev 0 5 27-Oct-14 03-Nov-14
Toilet Details Types (T10, T26 , T27, T31) Reply Rev 0 14 03-Nov-14 19-Nov-14
Toilet Details Types (T10, T26 , T27, T31) Submittal Rev 1 5 19-Nov-14 26-Nov-14
Toilet Details Types (T10, T26 , T27, T31) Approval Rev 1 7 26-Nov-14 04-Dec-14
Water Supply System Ground Floor Plan Rev 0 Submittal 5 04-Dec-14 11-Dec-14
Drainage System Ground Floor Plan Rev 0 Submittal 5 08-Dec-14 15-Dec-14
Water Supply System Ground Floor Plan Rev 0 Reply 14 11-Dec-14 28-Dec-14
Drainage System Ground Floor Plan Rev 0 Reply 14 15-Dec-14 31-Dec-14
Water Supply System Ground Floor Plan Rev 1 Submittal 5 28-Dec-14 04-Jan-15
Drainage System Ground Floor Plan Rev 1 Submittal 5 31-Dec-14 08-Jan-15
Water Supply System Ground Floor Plan Rev 1 Approval 7 04-Jan-15 13-Jan-15
Jun Jul Aug Sep Oct Nov Dec
Qtr 3 Qtr 4
2014
SECON Nile Tower Project MEP Base Line Secon Nile Tower Project Siemens Scope 21-Mar-16 17:19
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 13 of 1076 TASK filter: All Activities
© Primavera Systems, Inc
Activity ID Activity Name Original
Duration
Start Finish
Drainage System Ground Floor Plan Rev 1 Approval 7 08-Jan-15 17-Jan-15
C
Composite Shop Drawings 32 18-Jan-15 24-Feb-15
Composite Drawing for Ground Floor Plan Rev 0 Submittal 5 18-Jan-15 22-Jan-15
Composite Drawing for Ground Floor Plan Rev 0 Reply 14 24-Jan-15 09-Feb-15
Composite Drawing for Ground Floor Plan Rev 1 Submittal 5 10-Feb-15 16-Feb-15
Composite Drawing for Ground Floor Plan Rev 1 Approval 7 17-Feb-15 24-Feb-15
Fir
First Floor Shop Drawings 218 08-Jul-14 23-Mar-15
SS Receive First Floor MEP Design Package 0 08-Jul-14
SS Receive First Floor Approved Architecture Design Package 0 21-Oct-14
SS Receive First Floor Approved Structural Design Package 0 21-Oct-14
SS Receive First Floor Approved Architecture Shop Drawings 0 27-Oct-14
SS Receive First Floor Approved Tiles Shop Drawings 0 17-Nov-14
E
Electrical Systems Shop Drawings 48 28-Oct-14 22-Dec-14
Lighting System Shop Drawings 33 28-Oct-14 04-Dec-14
Lighting System First Floor Plan Rev 0 Submittal 5 28-Oct-14 03-Nov-14
Lighting System First Floor Plan Rev 0 Reply 14 04-Nov-14 19-Nov-14
Lighting System First Floor Plan Rev 1 Submittal 5 20-Nov-14 26-Nov-14
Lighting System First Floor Plan Rev 1 Approval 7 27-Nov-14 04-Dec-14
Power System Shop Drawings 33 02-Nov-14 10-Dec-14
Power System First Floor Plan Rev 0 Submittal 5 02-Nov-14 09-Nov-14
Power System First Floor Plan Rev 0 Reply 14 09-Nov-14 25-Nov-14
Power System First Floor Plan Rev 1 Submittal 5 25-Nov-14 02-Dec-14
Power System First Floor Plan Rev 1 Approval 7 02-Dec-14 10-Dec-14
Safety Lighting System Shop Drawings 32 16-Nov-14 22-Dec-14
Safety Lighting System First Floor Plan Rev 0 Submittal 5 16-Nov-14 20-Nov-14
Safety Lighting System First Floor Plan Rev 0 Reply 14 22-Nov-14 07-Dec-14
Safety Lighting System First Floor Plan Rev 1 Submittal 5 08-Dec-14 14-Dec-14
Safety Lighting System First Floor Plan Rev 1 Approval 7 15-Dec-14 22-Dec-14
Low Current Systems Shop Drawings 33 28-Oct-14 04-Dec-14
Fire Alarm System 33 28-Oct-14 04-Dec-14
Fire Alarm System First Floor Plan Rev 0 Submittal 5 28-Oct-14 03-Nov-14
Fire Alarm System First Floor Plan Rev 0 Reply 14 04-Nov-14 19-Nov-14
Fire Alarm System First Floor Plan Rev 1 Submittal 5 20-Nov-14 26-Nov-14
Fire Alarm System First Floor Plan Rev 1 Approval 7 27-Nov-14 04-Dec-14
Sound & Security systems 33 28-Oct-14 04-Dec-14
Sound & Security Systems First Floor Plan Rev 0 Submittal 5 28-Oct-14 03-Nov-14
Sound & Security Systems First Floor Plan Rev 0 Reply 14 04-Nov-14 19-Nov-14
Sound & Security Systems First Floor Plan Rev 1 Submittal 5 20-Nov-14 26-Nov-14
Jun Jul Aug Sep Oct Nov Dec
Qtr 3 Qtr 4
2014
SECON Nile Tower Project MEP Base Line Secon Nile Tower Project Siemens Scope 21-Mar-16 17:19
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 15 of 1076 TASK filter: All Activities
© Primavera Systems, Inc
Activity ID Activity Name Original
Duration
Start Finish
Sound & Security Systems First Floor Plan Rev 1 Approval 7 27-Nov-14 04-Dec-14
Voice,Data,IPTV systems 33 28-Oct-14 04-Dec-14
Voice, Data, IPTV Systems First Floor Plan Rev 0 Submittal 5 28-Oct-14 03-Nov-14
Voice, Data, IPTV Systems First Floor Plan Rev 0 Reply 14 04-Nov-14 19-Nov-14
Voice, Data, IPTV Systems First Floor Plan Rev 1 Submittal 5 20-Nov-14 26-Nov-14
Voice, Data, IPTV Systems First Floor Plan Rev 1 Approval 7 27-Nov-14 04-Dec-14
M
Mechanical Systems Shop Drawings 92 28-Oct-14 14-Feb-15
HVAC System Shop Drawings 33 28-Oct-14 04-Dec-14
HVAC System First Floor Plan Rev 0 Submittal 5 28-Oct-14 03-Nov-14
HVAC System First Floor Plan Rev 0 Reply 14 04-Nov-14 19-Nov-14
HVAC System First Floor Plan Rev 1 Submittal 5 20-Nov-14 26-Nov-14
HVAC System First Floor Plan Rev 1 Approval 7 27-Nov-14 04-Dec-14
Fire Fighting System Shop Drawings 33 28-Oct-14 04-Dec-14
Fire Fighting System First Floor Plan Rev 0 Submittal 5 28-Oct-14 03-Nov-14
Fire Fighting System First Floor Plan Rev 0 Reply 14 04-Nov-14 19-Nov-14
Fire Fighting System First Floor Plan Rev 1 Submittal 5 20-Nov-14 26-Nov-14
Fire Fighting System First Floor Plan Rev 1 Approval 7 27-Nov-14 04-Dec-14
Plumbing System Shop Drawings 67 26-Nov-14 14-Feb-15
Toilet Details Types (T1, T6 , T24, T25) Submittal Rev 0 5 26-Nov-14 03-Dec-14
Toilet Details Types (T1, T6 , T24, T25) Reply Rev 0 14 03-Dec-14 20-Dec-14
Toilet Details Types (T1, T6 , T24, T25) Submittal Rev 1 5 21-Dec-14 25-Dec-14
Toilet Details Types (T1, T6 , T24, T25) Approval Rev 1 7 27-Dec-14 03-Jan-15
Water Supply System First Floor Plan Rev 0 Submittal 5 04-Jan-15 11-Jan-15
Drainage System First Floor Plan Rev 0 Submittal 5 06-Jan-15 13-Jan-15
Water Supply System First Floor Plan Rev 0 Reply 14 12-Jan-15 28-Jan-15
Drainage System First Floor Plan Rev 0 Reply 14 14-Jan-15 31-Jan-15
Water Supply System First Floor Plan Rev 1 Submittal 5 29-Jan-15 04-Feb-15
Drainage System First Floor Plan Rev 1 Submittal 5 01-Feb-15 05-Feb-15
Water Supply System First Floor Plan Rev 1 Approval 7 05-Feb-15 12-Feb-15
Drainage System First Floor Plan Rev 1 Approval 7 07-Feb-15 14-Feb-15
C
Composite Shop Drawings 32 15-Feb-15 23-Mar-15
Composite Drawing for First Floor Plan Rev 0 Submittal 5 15-Feb-15 19-Feb-15
Composite Drawing for First Floor Plan Rev 0 Reply 14 21-Feb-15 08-Mar-15
Composite Drawing for First Floor Plan Rev 1 Submittal 5 09-Mar-15 15-Mar-15
Composite Drawing for First Floor Plan Rev 1 Approval 7 16-Mar-15 23-Mar-15
Se
Second Floor Shop Drawings 246 08-Jul-14 26-Apr-15
SS Receive Second Floor MEP Design Package 0 08-Jul-14
SS Receive Second Floor Approved Architecture Design Package 0 16-Nov-14
Jun Jul Aug Sep Oct Nov Dec
Qtr 3 Qtr 4
2014
SECON Nile Tower Project MEP Base Line Secon Nile Tower Project Siemens Scope 21-Mar-16 17:19
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 17 of 1076 TASK filter: All Activities
© Primavera Systems, Inc
Activity ID Activity Name Original
Duration
Start Finish
SS Receive Second Floor Approved Structural Design Package 0 16-Nov-14
SS Receive Second Floor Approved Architecture Shop Drawings 0 22-Nov-14
SS Receive Second Floor Approved Tiles Shop Drawings 0 13-Dec-14
E
Electrical Systems Shop Drawings 51 24-Nov-14 22-Jan-15
Lighting System Shop Drawings 33 24-Nov-14 31-Dec-14
Lighting System Second Floor Plan Rev 0 Submittal 5 24-Nov-14 30-Nov-14
Lighting System Second Floor Plan Rev 0 Reply 14 01-Dec-14 16-Dec-14
Lighting System Second Floor Plan Rev 1 Submittal 5 17-Dec-14 23-Dec-14
Lighting System Second Floor Plan Rev 1 Approval 7 24-Dec-14 31-Dec-14
Power System Shop Drawings 33 27-Nov-14 05-Jan-15
Power System Second Floor Plan Rev 0 Submittal 5 27-Nov-14 04-Dec-14
Power System Second Floor Plan Rev 0 Reply 14 04-Dec-14 21-Dec-14
Power System Second Floor Plan Rev 1 Submittal 5 21-Dec-14 28-Dec-14
Power System Second Floor Plan Rev 1 Approval 7 28-Dec-14 05-Jan-15
Safety Lighting System Shop Drawings 33 15-Dec-14 22-Jan-15
Safety Lighting System Second Floor Plan Rev 0 Submittal 5 15-Dec-14 21-Dec-14
Safety Lighting System Second Floor Plan Rev 0 Reply 14 22-Dec-14 06-Jan-15
Safety Lighting System Second Floor Plan Rev 1 Submittal 5 08-Jan-15 14-Jan-15
Safety Lighting System Second Floor Plan Rev 1 Approval 7 15-Jan-15 22-Jan-15
Low Current Systems Shop Drawings 33 24-Nov-14 31-Dec-14
Fire Alarm System 33 24-Nov-14 31-Dec-14
Fire Alarm System Second Floor Plan Rev 0 Submittal 5 24-Nov-14 30-Nov-14
Fire Alarm System Second Floor Plan Rev 0 Reply 14 01-Dec-14 16-Dec-14
Fire Alarm System Second Floor Plan Rev 1 Submittal 5 17-Dec-14 23-Dec-14
Fire Alarm System Second Floor Plan Rev 1 Approval 7 24-Dec-14 31-Dec-14
Sound & Security systems 33 24-Nov-14 31-Dec-14
Sound & Security Systems Second Floor Plan Rev 0 Submittal 5 24-Nov-14 30-Nov-14
Sound & Security Systems Second Floor Plan Rev 0 Reply 14 01-Dec-14 16-Dec-14
Sound & Security Systems Second Floor Plan Rev 1 Submittal 5 17-Dec-14 23-Dec-14
Sound & Security Systems Second Floor Plan Rev 1 Approval 7 24-Dec-14 31-Dec-14
Voice,Data,IPTV systems 33 24-Nov-14 31-Dec-14
Voice, Data, IPTV Systems Second Floor Plan Rev 0 Submittal 5 24-Nov-14 30-Nov-14
Voice, Data, IPTV Systems Second Floor Plan Rev 0 Reply 14 01-Dec-14 16-Dec-14
Voice, Data, IPTV Systems Second Floor Plan Rev 1 Submittal 5 17-Dec-14 23-Dec-14
Voice, Data, IPTV Systems Second Floor Plan Rev 1 Approval 7 24-Dec-14 31-Dec-14
M
Mechanical Systems Shop Drawings 97 24-Nov-14 18-Mar-15
HVAC System Shop Drawings 33 24-Nov-14 31-Dec-14
HVAC System Second Floor Plan Rev 0 Submittal 5 24-Nov-14 30-Nov-14
Jun Jul Aug Sep Oct Nov Dec
Qtr 3 Qtr 4
2014
SECON Nile Tower Project MEP Base Line Secon Nile Tower Project Siemens Scope 21-Mar-16 17:19
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 19 of 1076 TASK filter: All Activities
© Primavera Systems, Inc
Activity ID Activity Name Original
Duration
Start Finish
HVAC System Second Floor Plan Rev 0 Reply 14 01-Dec-14 16-Dec-14
HVAC System Second Floor Plan Rev 1 Submittal 5 17-Dec-14 23-Dec-14
HVAC System Second Floor Plan Rev 1 Approval 7 24-Dec-14 31-Dec-14
Fire Fighting System Shop Drawings 33 24-Nov-14 31-Dec-14
Fire Fighting System Second Floor Plan Rev 0 Submittal 5 24-Nov-14 30-Nov-14
Fire Fighting System Second Floor Plan Rev 0 Reply 14 01-Dec-14 16-Dec-14
Fire Fighting System Second Floor Plan Rev 1 Submittal 5 17-Dec-14 23-Dec-14
Fire Fighting System Second Floor Plan Rev 1 Approval 7 24-Dec-14 31-Dec-14
Plumbing System Shop Drawings 68 28-Dec-14 18-Mar-15
Toilet Details (T1, T6 , T24, T25, T35, T36, T37, T38) Submittal Rev 0 5 28-Dec-14 01-Jan-15
Toilet Details (T1, T6 , T24, T25, T35, T36, T37, T38) Reply Rev 0 14 03-Jan-15 19-Jan-15
Toilet Details (T1, T6 , T24, T25, T35, T36, T37, T38) Submittal Rev 1 5 20-Jan-15 27-Jan-15
Toilet Details (T1, T6 , T24, T25, T35, T36, T37, T38) Approval Rev 1 7 28-Jan-15 04-Feb-15
Water Supply System Second Floor Plan Rev 0 Submittal 5 05-Feb-15 11-Feb-15
Drainage System Second Floor Plan Rev 0 Submittal 5 09-Feb-15 15-Feb-15
Water Supply System Second Floor Plan Rev 0 Reply 14 12-Feb-15 28-Feb-15
Drainage System Second Floor Plan Rev 0 Reply 14 16-Feb-15 03-Mar-15
Water Supply System Second Floor Plan Rev 1 Submittal 5 01-Mar-15 05-Mar-15
Drainage System Second Floor Plan Rev 1 Submittal 5 04-Mar-15 10-Mar-15
Water Supply System Second Floor Plan Rev 1 Approval 7 07-Mar-15 14-Mar-15
Drainage System Second Floor Plan Rev 1 Approval 7 11-Mar-15 18-Mar-15
C
Composite Shop Drawings 32 19-Mar-15 26-Apr-15
Composite Drawing for Second Floor Plan Rev 0 Submittal 5 19-Mar-15 25-Mar-15
Composite Drawing for Second Floor Plan Rev 0 Reply 14 26-Mar-15 11-Apr-15
Composite Drawing for Second Floor Plan Rev 1 Submittal 5 12-Apr-15 16-Apr-15
Composite Drawing for Second Floor Plan Rev 1 Approval 7 18-Apr-15 26-Apr-15
Th
Third Floor Shop Drawings 272 08-Jul-14 26-May-15
SS Receive Third Floor MEP Design Package 0 08-Jul-14
SS Receive Third Floor Approved Architecture Design Package 0 11-Dec-14
SS Receive Third Floor Approved Structural Design Package 0 11-Dec-14
SS Receive Third Floor Approved Architecture Shop Drawings 0 17-Dec-14
SS Receive Third Floor Approved Tiles Shop Drawings 0 08-Jan-15
E
Electrical Systems Shop Drawings 54 21-Dec-14 23-Feb-15
Lighting System Shop Drawings 32 21-Dec-14 28-Jan-15
Lighting System Third Floor Plan Rev 0 Submittal 5 21-Dec-14 25-Dec-14
Lighting System Third Floor Plan Rev 0 Reply 14 27-Dec-14 12-Jan-15
Lighting System Third Floor Plan Rev 1 Submittal 5 13-Jan-15 19-Jan-15
Lighting System Third Floor Plan Rev 1 Approval 7 20-Jan-15 28-Jan-15
Jun Jul Aug Sep Oct Nov Dec
Qtr 3 Qtr 4
2014
SECON Nile Tower Project MEP Base Line Secon Nile Tower Project Siemens Scope 21-Mar-16 17:19
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 21 of 1076 TASK filter: All Activities
© Primavera Systems, Inc
Activity ID Activity Name Original
Duration
Start Finish
Power System Shop Drawings 33 23-Dec-14 01-Feb-15
Power System Third Floor Plan Rev 0 Submittal 5 23-Dec-14 30-Dec-14
Power System Third Floor Plan Rev 0 Reply 14 30-Dec-14 17-Jan-15
Power System Third Floor Plan Rev 1 Submittal 5 18-Jan-15 22-Jan-15
Power System Third Floor Plan Rev 1 Approval 7 24-Jan-15 01-Feb-15
Safety Lighting System Shop Drawings 33 15-Jan-15 23-Feb-15
Safety Lighting System Third Floor Plan Rev 0 Submittal 5 15-Jan-15 21-Jan-15
Safety Lighting System Third Floor Plan Rev 0 Reply 14 22-Jan-15 08-Feb-15
Safety Lighting System Third Floor Plan Rev 1 Submittal 5 09-Feb-15 15-Feb-15
Safety Lighting System Third Floor Plan Rev 1 Approval 7 16-Feb-15 23-Feb-15
Low Current Systems Shop Drawings 32 21-Dec-14 28-Jan-15
Fire Alarm System 32 21-Dec-14 28-Jan-15
Fire Alarm System Third Floor Plan Rev 0 Submittal 5 21-Dec-14 25-Dec-14
Fire Alarm System Third Floor Plan Rev 0 Reply 14 27-Dec-14 12-Jan-15
Fire Alarm System Third Floor Plan Rev 1 Submittal 5 13-Jan-15 19-Jan-15
Fire Alarm System Third Floor Plan Rev 1 Approval 7 20-Jan-15 28-Jan-15
Sound & Security systems 32 21-Dec-14 28-Jan-15
Sound & Security Systems Third Floor Plan Rev 0 Submittal 5 21-Dec-14 25-Dec-14
Sound & Security Systems Third Floor Plan Rev 0 Reply 14 27-Dec-14 12-Jan-15
Sound & Security Systems Third Floor Plan Rev 1 Submittal 5 13-Jan-15 19-Jan-15
Sound & Security Systems Third Floor Plan Rev 1 Approval 7 20-Jan-15 28-Jan-15
Voice,Data,IPTV systems 32 21-Dec-14 28-Jan-15
Voice, Data, IPTV Systems Third Floor Plan Rev 0 Submittal 5 21-Dec-14 25-Dec-14
Voice, Data, IPTV Systems Third Floor Plan Rev 0 Reply 14 27-Dec-14 12-Jan-15
Voice, Data, IPTV Systems Third Floor Plan Rev 1 Submittal 5 13-Jan-15 19-Jan-15
Voice, Data, IPTV Systems Third Floor Plan Rev 1 Approval 7 20-Jan-15 28-Jan-15
M
Mechanical Systems Shop Drawings 99 21-Dec-14 16-Apr-15
HVAC System Shop Drawings 32 21-Dec-14 28-Jan-15
HVAC System Third Floor Plan Rev 0 Submittal 5 21-Dec-14 25-Dec-14
HVAC System Third Floor Plan Rev 0 Reply 14 27-Dec-14 12-Jan-15
HVAC System Third Floor Plan Rev 1 Submittal 5 13-Jan-15 19-Jan-15
HVAC System Third Floor Plan Rev 1 Approval 7 20-Jan-15 28-Jan-15
Fire Fighting System Shop Drawings 32 21-Dec-14 28-Jan-15
Fire Fighting System Third Floor Plan Rev 0 Submittal 5 21-Dec-14 25-Dec-14
Fire Fighting System Third Floor Plan Rev 0 Reply 14 27-Dec-14 12-Jan-15
Fire Fighting System Third Floor Plan Rev 1 Submittal 5 13-Jan-15 19-Jan-15
Fire Fighting System Third Floor Plan Rev 1 Approval 7 20-Jan-15 28-Jan-15
Plumbing System Shop Drawings 68 28-Jan-15 16-Apr-15
Jun Jul Aug Sep Oct Nov Dec
Qtr 3 Qtr 4
2014
SECON Nile Tower Project MEP Base Line Secon Nile Tower Project Siemens Scope 21-Mar-16 17:19
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 23 of 1076 TASK filter: All Activities
© Primavera Systems, Inc
Activity ID Activity Name Original
Duration
Start Finish
Toilet Details (T 1, 3, 6, 8, 9, 24, 25, 30, 40 ) Submittal Rev 0 5 28-Jan-15 03-Feb-15
Toilet Details (T 1, 3, 6, 8, 9, 24, 25, 30, 40 ) Reply Rev 0 14 04-Feb-15 19-Feb-15
Toilet Details (T 1, 3, 6, 8, 9, 24, 25, 30, 40 ) Submittal Rev 1 5 22-Feb-15 26-Feb-15
Toilet Details (T 1, 3, 6, 8, 9, 24, 25, 30, 40 ) Approval Rev 1 7 28-Feb-15 07-Mar-15
Water Supply System Third Floor Plan Rev 0 Submittal 5 08-Mar-15 12-Mar-15
Drainage System Third Floor Plan Rev 0 Submittal 5 10-Mar-15 16-Mar-15
Water Supply System Third Floor Plan Rev 0 Reply 14 14-Mar-15 29-Mar-15
Drainage System Third Floor Plan Rev 0 Reply 14 17-Mar-15 01-Apr-15
Water Supply System Third Floor Plan Rev 1 Submittal 5 30-Mar-15 05-Apr-15
Drainage System Third Floor Plan Rev 1 Submittal 5 02-Apr-15 08-Apr-15
Water Supply System Third Floor Plan Rev 1 Approval 7 06-Apr-15 13-Apr-15
Drainage System Third Floor Plan Rev 1 Approval 7 09-Apr-15 16-Apr-15
C
Composite Shop Drawings 32 19-Apr-15 26-May-15
Composite Drawing for Third Floor Plan Rev 0 Submittal 5 19-Apr-15 23-Apr-15
Composite Drawing for Third Floor Plan Rev 0 Reply 14 26-Apr-15 11-May-15
Composite Drawing for Third Floor Plan Rev 1 Submittal 5 12-May-15 18-May-15
Composite Drawing for Third Floor Plan Rev 1 Approval 7 19-May-15 26-May-15
Ty
Typical Floor (4 : 20) Shop Drawings 298 08-Jul-14 25-Jun-15
SS Receive Typical Floor (4:20) MEP Design Package 0 08-Jul-14
SS Receive Typical Floor (4:20) Approved Architecture Design Package 0 06-Jan-15
SS Receive Typical Floor (4:20) Approved Structural Design Package 0 06-Jan-15
SS Receive Typical Floor (4:20) Approved Architecture Shop Drawings 0 13-Jan-15
SS Receive Typical Floor (4:20) Approved Tiles Shop Drawings 0 04-Feb-15
E
Electrical Systems Shop Drawings 59 15-Jan-15 25-Mar-15
Lighting System Shop Drawings 33 15-Jan-15 23-Feb-15
Lighting System Typical Floor Plan (4:20) Rev 0 Submittal 5 15-Jan-15 21-Jan-15
Lighting System Typical Floors Plan (4:20) Rev 0 Reply 14 22-Jan-15 08-Feb-15
Lighting System Typical Floors Plan (4:20) Rev 1 Submittal 5 09-Feb-15 15-Feb-15
Lighting System Typical Floors Plan (4:20) Rev 1 Approval 7 16-Feb-15 23-Feb-15
Power System Shop Drawings 33 20-Jan-15 28-Feb-15
Power System Typical Floors Plan (4:20) Rev 0 Submittal 5 20-Jan-15 27-Jan-15
Power System Typical Floors Plan (4:20) Rev 0 Reply 14 28-Jan-15 12-Feb-15
Power System Typical Floors Plan (4:20) Rev 1 Submittal 5 15-Feb-15 19-Feb-15
Power System Typical Floors Plan (4:20) Rev 1 Approval 7 21-Feb-15 28-Feb-15
Safety Lighting System Shop Drawings 33 16-Feb-15 25-Mar-15
Safety Lighting System Typical Floors Plan (4:20) Rev 0 Submittal 5 16-Feb-15 22-Feb-15
Safety Lighting System Typical Floors Plan (4:20) Rev 0 Reply 14 23-Feb-15 10-Mar-15
Safety Lighting System Typical Floors Plan (4:20) Rev 1 Submittal 5 11-Mar-15 17-Mar-15
Jun Jul Aug Sep Oct Nov Dec
Qtr 3 Qtr 4
2014
SECON Nile Tower Project MEP Base Line Secon Nile Tower Project Siemens Scope 21-Mar-16 17:19
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 25 of 1076 TASK filter: All Activities
© Primavera Systems, Inc
Activity ID Activity Name Original
Duration
Start Finish
Safety Lighting System Typical Floors Plan (4:20) Rev 1 Approval 7 18-Mar-15 25-Mar-15
Low Current Systems Shop Drawings 33 15-Jan-15 23-Feb-15
Fire Alarm System 33 15-Jan-15 23-Feb-15
Fire Alarm System Typical Floors Plan (4:20) Rev 0 Submittal 5 15-Jan-15 21-Jan-15
Fire Alarm System Typical Floors Plan (4:20) Rev 0 Reply 14 22-Jan-15 08-Feb-15
Fire Alarm System Typical Floors Plan (4:20) Rev 1 Submittal 5 09-Feb-15 15-Feb-15
Fire Alarm System Typical Floors Plan (4:20) Rev 1 Approval 7 16-Feb-15 23-Feb-15
Sound & Security systems 33 15-Jan-15 23-Feb-15
Sound & Security Systems Typical Floors Plan (4:20) Rev 0 Submittal 5 15-Jan-15 21-Jan-15
Sound & Security Systems Typical Floors Plan (4:20) Rev 0 Reply 14 22-Jan-15 08-Feb-15
Sound & Security Systems Typical Floors Plan (4:20) Rev 1 Submittal 5 09-Feb-15 15-Feb-15
Sound & Security Systems Typical Floors Plan (4:20) Rev 1 Approval 7 16-Feb-15 23-Feb-15
Voice,Data,IPTV systems 33 15-Jan-15 23-Feb-15
Voice, Data, IPTV Systems Typical Floors Plan (4:20) Rev 0 Submittal 5 15-Jan-15 21-Jan-15
Voice, Data, IPTV Systems Typical Floors Plan (4:20) Rev 0 Reply 14 22-Jan-15 08-Feb-15
Voice, Data, IPTV Systems Typical Floors Plan (4:20) Rev 1 Submittal 5 09-Feb-15 15-Feb-15
Voice, Data, IPTV Systems Typical Floors Plan (4:20) Rev 1 Approval 7 16-Feb-15 23-Feb-15
M
Mechanical Systems Shop Drawings 104 15-Jan-15 18-May-15
HVAC System Shop Drawings 33 15-Jan-15 23-Feb-15
HVAC System Typical Floors Plan (4:20) Rev 0 Submittal 5 15-Jan-15 21-Jan-15
HVAC System Typical Floors Plan (4:20) Rev 0 Reply 14 22-Jan-15 08-Feb-15
HVAC System Typical Floors Plan (4:20) Rev 1 Submittal 5 09-Feb-15 15-Feb-15
HVAC System Typical Floors Plan (4:20) Rev 1 Approval 7 16-Feb-15 23-Feb-15
Fire Fighting System Shop Drawings 33 15-Jan-15 23-Feb-15
Fire Fighting System Typical Floors Plan (4:20) Rev 0 Submittal 5 15-Jan-15 21-Jan-15
Fire Fighting System Typical Floors Plan (4:20) Rev 0 Reply 14 22-Jan-15 08-Feb-15
Fire Fighting System Typical Floors Plan (4:20) Rev 1 Submittal 5 09-Feb-15 15-Feb-15
Fire Fighting System Typical Floors Plan (4:20) Rev 1 Approval 7 16-Feb-15 23-Feb-15
Plumbing System Shop Drawings 67 01-Mar-15 18-May-15
Toilet Details (T 3, 8, 9, 30 ,40 ) Submittal Rev 0 5 01-Mar-15 05-Mar-15
Toilet Details (T 3, 8, 9, 30 ,40 ) Reply Rev 0 14 07-Mar-15 22-Mar-15
Toilet Details (T 3, 8, 9, 30 ,40 ) Submittal Rev 1 5 23-Mar-15 29-Mar-15
Toilet Details (T 3, 8, 9, 30 ,40 ) Approval Rev 1 7 30-Mar-15 06-Apr-15
Water Supply System Typical Floors Plan (4:20) Rev 0 Submittal 5 07-Apr-15 13-Apr-15
Drainage System Typical Floors Plan (4:20) Rev 0 Submittal 5 09-Apr-15 15-Apr-15
Water Supply System Typical Floors Plan (4:20) Rev 0 Reply 14 14-Apr-15 30-Apr-15
Drainage System Typical Floors Plan (4:20) Rev 0 Reply 14 16-Apr-15 03-May-15
Water Supply System Typical Floors Plan (4:20) Rev 1 Submittal 5 03-May-15 07-May-15
Jun Jul Aug Sep Oct Nov Dec
Qtr 3 Qtr 4
2014
SECON Nile Tower Project MEP Base Line Secon Nile Tower Project Siemens Scope 21-Mar-16 17:19
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 27 of 1076 TASK filter: All Activities
© Primavera Systems, Inc
Activity ID Activity Name Original
Duration
Start Finish
Drainage System Typical Floors Plan (4:20) Rev 1 Submittal 5 04-May-15 10-May-15
Water Supply System Typical Floors Plan (4:20) Rev 1 Approval 7 09-May-15 16-May-15
Drainage System Typical Floors Plan (4:20) Rev 1 Approval 7 11-May-15 18-May-15
C
Composite Shop Drawings 33 19-May-15 25-Jun-15
Composite Drawing for Typical Floors Plan (4:20) Rev 0 Submittal 5 19-May-15 25-May-15
Composite Drawing for Typical Floors Plan (4:20) Rev 0 Reply 14 26-May-15 10-Jun-15
Composite Drawing for Typical Floors Plan (4:20) Rev 1 Submittal 5 11-Jun-15 17-Jun-15
Composite Drawing for Typical Floors Plan (4:20) Rev 1 Approval 7 18-Jun-15 25-Jun-15
21
21st Floor Shop Drawings 324 08-Jul-14 28-Jul-15
SS Receive 21st Floor MEP Design Package 0 08-Jul-14
SS Receive 21st Floor Approved Architecture Design Package 0 03-Feb-15
SS Receive 21st Floor Approved Structural Design Package 0 03-Feb-15
SS Receive 21st Floor Approved Architecture Shop Drawings 0 09-Feb-15
SS Receive 21st Floor Approved Tiles Shop Drawings 0 02-Mar-15
E
Electrical Systems Shop Drawings 63 11-Feb-15 26-Apr-15
Lighting System Shop Drawings 33 11-Feb-15 21-Mar-15
Lighting System 21st Floor Plan Rev 0 Submittal 5 11-Feb-15 17-Feb-15
Lighting System 21st Floor Plan Rev 0 Reply 14 18-Feb-15 05-Mar-15
Lighting System 21st Floor Plan Rev 1 Submittal 5 08-Mar-15 12-Mar-15
Lighting System 21st Floor Plan Rev 1 Approval 7 14-Mar-15 21-Mar-15
Power System Shop Drawings 33 17-Feb-15 26-Mar-15
Power System 21st Floor Plan Rev 0 Submittal 5 17-Feb-15 23-Feb-15
Power System 21st Floor Plan Rev 0 Reply 14 24-Feb-15 11-Mar-15
Power System 21st Floor Plan Rev 1 Submittal 5 12-Mar-15 18-Mar-15
Power System 21st Floor Plan Rev 1 Approval 7 19-Mar-15 26-Mar-15
Safety Lighting System Shop Drawings 33 18-Mar-15 26-Apr-15
Safety Lighting System 21st Floor Plan Rev 0 Submittal 5 18-Mar-15 24-Mar-15
Safety Lighting System 21st Floor Plan Rev 0 Reply 14 25-Mar-15 09-Apr-15
Safety Lighting System 21st Floor Plan Rev 1 Submittal 5 12-Apr-15 16-Apr-15
Safety Lighting System 21st Floor Plan Rev 1 Approval 7 18-Apr-15 26-Apr-15
Low Current Systems Shop Drawings 33 11-Feb-15 21-Mar-15
Fire Alarm System 33 11-Feb-15 21-Mar-15
Fire Alarm System 21st Floor Plan Rev 0 Submittal 5 11-Feb-15 17-Feb-15
Fire Alarm System 21st Floor Plan Rev 0 Reply 14 18-Feb-15 05-Mar-15
Fire Alarm System 21st Floor Plan Rev 1 Submittal 5 08-Mar-15 12-Mar-15
Fire Alarm System 21st Floor Plan Rev 1 Approval 7 14-Mar-15 21-Mar-15
Sound & Security systems 33 11-Feb-15 21-Mar-15
Sound & Security Systems 21st Floor Plan Rev 0 Submittal 5 11-Feb-15 17-Feb-15
Jun Jul Aug Sep Oct Nov Dec
Qtr 3 Qtr 4
2014
SECON Nile Tower Project MEP Base Line Secon Nile Tower Project Siemens Scope 21-Mar-16 17:19
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 29 of 1076 TASK filter: All Activities
© Primavera Systems, Inc
Activity ID Activity Name Original
Duration
Start Finish
Sound & Security Systems 21st Floor Plan Rev 0 Reply 14 18-Feb-15 05-Mar-15
Sound & Security Systems 21st Floor Plan Rev 1 Submittal 5 08-Mar-15 12-Mar-15
Sound & Security Systems 21st Floor Plan Rev 1 Approval 7 14-Mar-15 21-Mar-15
Voice,Data,IPTV systems 33 11-Feb-15 21-Mar-15
Voice, Data, IPTV Systems 21st Floor Plan Rev 0 Submittal 5 11-Feb-15 17-Feb-15
Voice, Data, IPTV Systems 21st Floor Plan Rev 0 Reply 14 18-Feb-15 05-Mar-15
Voice, Data, IPTV Systems 21st Floor Plan Rev 1 Submittal 5 08-Mar-15 12-Mar-15
Voice, Data, IPTV Systems 21st Floor Plan Rev 1 Approval 7 14-Mar-15 21-Mar-15
M
Mechanical Systems Shop Drawings 108 11-Feb-15 17-Jun-15
HVAC System Shop Drawings 33 11-Feb-15 21-Mar-15
HVAC System 21st Floor Plan Rev 0 Submittal 5 11-Feb-15 17-Feb-15
HVAC System 21st Floor Plan Rev 0 Reply 14 18-Feb-15 05-Mar-15
HVAC System 21st Floor Plan Rev 1 Submittal 5 08-Mar-15 12-Mar-15
HVAC System 21st Floor Plan Rev 1 Approval 7 14-Mar-15 21-Mar-15
Fire Fighting System Shop Drawings 33 11-Feb-15 21-Mar-15
Fire Fighting System 21st Floor Plan Rev 0 Submittal 5 11-Feb-15 17-Feb-15
Fire Fighting System 21st Floor Plan Rev 0 Reply 14 18-Feb-15 05-Mar-15
Fire Fighting System 21st Floor Plan Rev 1 Submittal 5 08-Mar-15 12-Mar-15
Fire Fighting System 21st Floor Plan Rev 1 Approval 7 14-Mar-15 21-Mar-15
Plumbing System Shop Drawings 68 30-Mar-15 17-Jun-15
Toilet Details (T 3, 8, 9, 40 ) Submittal Rev 0 5 30-Mar-15 05-Apr-15
Toilet Details (T 3, 8, 9, 40 ) Reply Rev 0 14 06-Apr-15 21-Apr-15
Toilet Details (T 3, 8, 9, 40 ) Submittal Rev 1 5 22-Apr-15 28-Apr-15
Toilet Details (T 3, 8, 9, 40 ) Approval Rev 1 7 29-Apr-15 06-May-15
Water Supply System 21st Floor Plan Rev 0 Submittal 5 07-May-15 13-May-15
Drainage System 21st Floor Plan Rev 0 Submittal 5 11-May-15 17-May-15
Water Supply System 21st Floor Plan Rev 0 Reply 14 14-May-15 30-May-15
Drainage System 21st Floor Plan Rev 0 Reply 14 18-May-15 02-Jun-15
Water Supply System 21st Floor Plan Rev 1 Submittal 5 31-May-15 04-Jun-15
Drainage System 21st Floor Plan Rev 1 Submittal 5 03-Jun-15 09-Jun-15
Water Supply System 21st Floor Plan Rev 1 Approval 7 06-Jun-15 13-Jun-15
Drainage System 21st Floor Plan Rev 1 Approval 7 10-Jun-15 17-Jun-15
C
Composite Shop Drawings 33 18-Jun-15 28-Jul-15
Composite Drawing for 21st Floor Plan Rev 0 Submittal 5 18-Jun-15 24-Jun-15
Composite Drawing for 21st Floor Plan Rev 0 Reply 14 25-Jun-15 11-Jul-15
Composite Drawing for 21st Floor Plan Rev 1 Submittal 5 12-Jul-15 19-Jul-15
Composite Drawing for 21st Floor Plan Rev 1 Approval 7 20-Jul-15 28-Jul-15
22
22nd Floor Shop Drawings 349 08-Jul-14 26-Aug-15
Jun Jul Aug Sep Oct Nov Dec
Qtr 3 Qtr 4
2014
SECON Nile Tower Project MEP Base Line Secon Nile Tower Project Siemens Scope 21-Mar-16 17:19
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 31 of 1076 TASK filter: All Activities
© Primavera Systems, Inc
Activity ID Activity Name Original
Duration
Start Finish
SS Receive 22nd Floor MEP Design Package 0 08-Jul-14
SS Receive 22nd Floor Approved Architecture Design Package 0 01-Mar-15
SS Receive 22nd Floor Approved Structural Design Package 0 01-Mar-15
SS Receive 22nd Floor Approved Architecture Shop Drawings 0 07-Mar-15
SS Receive 22nd Floor Approved Tiles Shop Drawings 0 28-Mar-15
E
Electrical Systems Shop Drawings 66 10-Mar-15 26-May-15
Lighting System Shop Drawings 33 10-Mar-15 16-Apr-15
Lighting System 22nd Floor Plan Rev 0 Submittal 5 10-Mar-15 16-Mar-15
Lighting System 22nd Floor Plan Rev 0 Reply 14 17-Mar-15 01-Apr-15
Lighting System 22nd Floor Plan Rev 1 Submittal 5 02-Apr-15 08-Apr-15
Lighting System 22nd Floor Plan Rev 1 Approval 7 09-Apr-15 16-Apr-15
Power System Shop Drawings 33 16-Mar-15 22-Apr-15
Power System 22nd Floor Plan Rev 0 Submittal 5 16-Mar-15 22-Mar-15
Power System 22nd Floor Plan Rev 0 Reply 14 23-Mar-15 07-Apr-15
Power System 22nd Floor Plan Rev 1 Submittal 5 08-Apr-15 14-Apr-15
Power System 22nd Floor Plan Rev 1 Approval 7 15-Apr-15 22-Apr-15
Safety Lighting System Shop Drawings 32 19-Apr-15 26-May-15
Safety Lighting System 22nd Floor Plan Rev 0 Submittal 5 19-Apr-15 23-Apr-15
Safety Lighting System 22nd Floor Plan Rev 0 Reply 14 26-Apr-15 11-May-15
Safety Lighting System 22nd Floor Plan Rev 1 Submittal 5 12-May-15 18-May-15
Safety Lighting System 22nd Floor Plan Rev 1 Approval 7 19-May-15 26-May-15
Low Current Systems Shop Drawings 33 10-Mar-15 16-Apr-15
Fire Alarm System 33 10-Mar-15 16-Apr-15
Fire Alarm System 22nd Floor Plan Rev 0 Submittal 5 10-Mar-15 16-Mar-15
Fire Alarm System 22nd Floor Plan Rev 0 Reply 14 17-Mar-15 01-Apr-15
Fire Alarm System 22nd Floor Plan Rev 1 Submittal 5 02-Apr-15 08-Apr-15
Fire Alarm System 22nd Floor Plan Rev 1 Approval 7 09-Apr-15 16-Apr-15
Sound & Security systems 33 10-Mar-15 16-Apr-15
Sound & Security Systems 22nd Floor Plan Rev 0 Submittal 5 10-Mar-15 16-Mar-15
Sound & Security Systems 22nd Floor Plan Rev 0 Reply 14 17-Mar-15 01-Apr-15
Sound & Security Systems 22nd Floor Plan Rev 1 Submittal 5 02-Apr-15 08-Apr-15
Sound & Security Systems 22nd Floor Plan Rev 1 Approval 7 09-Apr-15 16-Apr-15
Voice,Data,IPTV systems 33 10-Mar-15 16-Apr-15
Voice, Data, IPTV Systems 22nd Floor Plan Rev 0 Submittal 5 10-Mar-15 16-Mar-15
Voice, Data, IPTV Systems 22nd Floor Plan Rev 0 Reply 14 17-Mar-15 01-Apr-15
Voice, Data, IPTV Systems 22nd Floor Plan Rev 1 Submittal 5 02-Apr-15 08-Apr-15
Voice, Data, IPTV Systems 22nd Floor Plan Rev 1 Approval 7 09-Apr-15 16-Apr-15
M
Mechanical Systems Shop Drawings 110 10-Mar-15 16-Jul-15
Jun Jul Aug Sep Oct Nov Dec
Qtr 3 Qtr 4
2014
SECON Nile Tower Project MEP Base Line Secon Nile Tower Project Siemens Scope 21-Mar-16 17:19
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 33 of 1076 TASK filter: All Activities
© Primavera Systems, Inc
Activity ID Activity Name Original
Duration
Start Finish
HVAC System Shop Drawings 33 10-Mar-15 16-Apr-15
HVAC System 22nd Floor Plan Rev 0 Submittal 5 10-Mar-15 16-Mar-15
HVAC System 22nd Floor Plan Rev 0 Reply 14 17-Mar-15 01-Apr-15
HVAC System 22nd Floor Plan Rev 1 Submittal 5 02-Apr-15 08-Apr-15
HVAC System 22nd Floor Plan Rev 1 Approval 7 09-Apr-15 16-Apr-15
Fire Fighting System Shop Drawings 33 10-Mar-15 16-Apr-15
Fire Fighting System 22nd Floor Plan Rev 0 Submittal 5 10-Mar-15 16-Mar-15
Fire Fighting System 22nd Floor Plan Rev 0 Reply 14 17-Mar-15 01-Apr-15
Fire Fighting System 22nd Floor Plan Rev 1 Submittal 5 02-Apr-15 08-Apr-15
Fire Fighting System 22nd Floor Plan Rev 1 Approval 7 09-Apr-15 16-Apr-15
Plumbing System Shop Drawings 68 29-Apr-15 16-Jul-15
Toilet Details (T3,8,9,11,12,13,14,15,16,17,18,19,20,21,22,23) Submittal Rev 0 5 29-Apr-15 05-May-15
Toilet Details (T3,8,9,11,12,13,14,15,16,17,18,19,20,21,22,23) Reply Rev 0 14 06-May-15 21-May-15
Toilet Details (T3,8,9,11,12,13,14,15,16,17,18,19,20,21,22,23) Submittal Rev 1 5 24-May-15 28-May-15
Toilet Details (T3,8,9,11,12,13,14,15,16,17,18,19,20,21,22,23) Approval Rev 1 7 30-May-15 06-Jun-15
Water Supply System 22nd Floor Plan Rev 0 Submittal 5 07-Jun-15 11-Jun-15
Drainage System 22nd Floor Plan Rev 0 Submittal 5 09-Jun-15 15-Jun-15
Water Supply System 22nd Floor Plan Rev 0 Reply 14 13-Jun-15 28-Jun-15
Drainage System 22nd Floor Plan Rev 0 Reply 14 16-Jun-15 01-Jul-15
Water Supply System 22nd Floor Plan Rev 1 Submittal 5 29-Jun-15 05-Jul-15
Drainage System 22nd Floor Plan Rev 1 Submittal 5 02-Jul-15 08-Jul-15
Water Supply System 22nd Floor Plan Rev 1 Approval 7 06-Jul-15 13-Jul-15
Drainage System 22nd Floor Plan Rev 1 Approval 7 09-Jul-15 16-Jul-15
C
Composite Shop Drawings 33 19-Jul-15 26-Aug-15
Composite Drawing for 22nd Floor Plan Rev 0 Submittal 5 19-Jul-15 26-Jul-15
Composite Drawing for 22nd Floor Plan Rev 0 Reply 14 27-Jul-15 11-Aug-15
Composite Drawing for 22nd Floor Plan Rev 1 Submittal 5 12-Aug-15 18-Aug-15
Composite Drawing for 22nd Floor Plan Rev 1 Approval 7 19-Aug-15 26-Aug-15
Ro
Roof Floor Shop Drawings 375 08-Jul-14 28-Sep-15
SS Receive Roof Floor MEP Design Package 0 08-Jul-14
SS Receive Roof Floor Approved Architecture Design Package 0 26-Mar-15
SS Receive Roof Floor Approved Structural Design Package 0 26-Mar-15
SS Receive Roof Floor Approved Architecture Shop Drawings 0 01-Apr-15
E
Electrical Systems Shop Drawings 69 06-Apr-15 25-Jun-15
Lighting System Shop Drawings 33 06-Apr-15 14-May-15
Lighting System Roof Floor Plan Rev 0 Submittal 5 06-Apr-15 12-Apr-15
Lighting System Roof Floor Plan Rev 0 Reply 14 13-Apr-15 29-Apr-15
Lighting System Roof Floor Plan Rev 1 Submittal 5 30-Apr-15 06-May-15
Jun Jul Aug Sep Oct Nov Dec
Qtr 3 Qtr 4
2014
SECON Nile Tower Project MEP Base Line Secon Nile Tower Project Siemens Scope 21-Mar-16 17:19
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 35 of 1076 TASK filter: All Activities
© Primavera Systems, Inc
Activity ID Activity Name Original
Duration
Start Finish
Lighting System Roof Floor Plan Rev 1 Approval 7 07-May-15 14-May-15
Power System Shop Drawings 32 12-Apr-15 19-May-15
Power System Roof Floor Plan Rev 0 Submittal 5 12-Apr-15 16-Apr-15
Power System Roof Floor Plan Rev 0 Reply 14 18-Apr-15 04-May-15
Power System Roof Floor Plan Rev 1 Submittal 5 05-May-15 11-May-15
Power System Roof Floor Plan Rev 1 Approval 7 12-May-15 19-May-15
Safety Lighting System Shop Drawings 33 19-May-15 25-Jun-15
Safety Lighting System Roof Floor Plan Rev 0 Submittal 5 19-May-15 25-May-15
Safety Lighting System Roof Floor Plan Rev 0 Reply 14 26-May-15 10-Jun-15
Safety Lighting System Roof Floor Plan Rev 1 Submittal 5 11-Jun-15 17-Jun-15
Safety Lighting System Roof Floor Plan Rev 1 Approval 7 18-Jun-15 25-Jun-15
Low Current Systems Shop Drawings 33 06-Apr-15 14-May-15
Fire Alarm System 33 06-Apr-15 14-May-15
Fire Alarm System Roof Floor Plan Rev 0 Submittal 5 06-Apr-15 12-Apr-15
Fire Alarm System Roof Floor Plan Rev 0 Reply 14 13-Apr-15 29-Apr-15
Fire Alarm System Roof Floor Plan Rev 1 Submittal 5 30-Apr-15 06-May-15
Fire Alarm System Roof Floor Plan Rev 1 Approval 7 07-May-15 14-May-15
Sound & Security systems 33 06-Apr-15 14-May-15
Sound & Security Systems Roof Floor Plan Rev 0 Submittal 5 06-Apr-15 12-Apr-15
Sound & Security Systems Roof Floor Plan Rev 0 Reply 14 13-Apr-15 29-Apr-15
Sound & Security Systems Roof Floor Plan Rev 1 Submittal 5 30-Apr-15 06-May-15
Sound & Security Systems Roof Floor Plan Rev 1 Approval 7 07-May-15 14-May-15
Voice,Data,IPTV systems 33 06-Apr-15 14-May-15
Voice, Data, IPTV Systems Roof Floor Plan Rev 0 Submittal 5 06-Apr-15 12-Apr-15
Voice, Data, IPTV Systems Roof Floor Plan Rev 0 Reply 14 13-Apr-15 29-Apr-15
Voice, Data, IPTV Systems Roof Floor Plan Rev 1 Submittal 5 30-Apr-15 06-May-15
Voice, Data, IPTV Systems Roof Floor Plan Rev 1 Approval 7 07-May-15 14-May-15
M
Mechanical Systems Shop Drawings 113 06-Apr-15 18-Aug-15
HVAC System Shop Drawings 33 06-Apr-15 14-May-15
HVAC System Roof Floor Plan Rev 0 Submittal 5 06-Apr-15 12-Apr-15
HVAC System Roof Floor Plan Rev 0 Reply 14 13-Apr-15 29-Apr-15
HVAC System Roof Floor Plan Rev 1 Submittal 5 30-Apr-15 06-May-15
HVAC System Roof Floor Plan Rev 1 Approval 7 07-May-15 14-May-15
Fire Fighting System Shop Drawings 33 06-Apr-15 14-May-15
Fire Fighting System Roof Floor Plan Rev 0 Submittal 5 06-Apr-15 12-Apr-15
Fire Fighting System Roof Floor Plan Rev 0 Reply 14 13-Apr-15 29-Apr-15
Fire Fighting System Roof Floor Plan Rev 1 Submittal 5 30-Apr-15 06-May-15
Fire Fighting System Roof Floor Plan Rev 1 Approval 7 07-May-15 14-May-15
Jun Jul Aug Sep Oct Nov Dec
Qtr 3 Qtr 4
2014
SECON Nile Tower Project MEP Base Line Secon Nile Tower Project Siemens Scope 21-Mar-16 17:19
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 37 of 1076 TASK filter: All Activities
© Primavera Systems, Inc
Activity ID Activity Name Original
Duration
Start Finish
Plumbing System Shop Drawings 36 06-Jul-15 18-Aug-15
Water Supply System Roof Floor Plan Rev 0 Submittal 5 06-Jul-15 12-Jul-15
Drainage System Roof Floor Plan Rev 0 Submittal 5 09-Jul-15 15-Jul-15
Water Supply System Roof Floor Plan Rev 0 Reply 14 13-Jul-15 30-Jul-15
Drainage System Roof Floor Plan Rev 0 Reply 14 16-Jul-15 03-Aug-15
Water Supply System Roof Floor Plan Rev 1 Submittal 5 02-Aug-15 06-Aug-15
Drainage System Roof Floor Plan Rev 1 Submittal 5 04-Aug-15 10-Aug-15
Water Supply System Roof Floor Plan Rev 1 Approval 7 08-Aug-15 15-Aug-15
Drainage System Roof Floor Plan Rev 1 Approval 7 11-Aug-15 18-Aug-15
C
Composite Shop Drawings 33 19-Aug-15 28-Sep-15
Composite Drawing for Roof Floor Plan Rev 0 Submittal 5 19-Aug-15 25-Aug-15
Composite Drawing for Roof Floor Plan Rev 0 Reply 14 26-Aug-15 10-Sep-15
Composite Drawing for Roof Floor Plan Rev 1 Submittal 5 13-Sep-15 17-Sep-15
Composite Drawing for Roof Floor Plan Rev 1 Approval 7 19-Sep-15 28-Sep-15
Gen
General 371 13-Jul-14 28-Sep-15
Ele
Electrical 333 13-Jul-14 12-Aug-15
E
Electrical Typical Installation Details 303 13-Jul-14 06-Jul-15
Submittal of Lighting System Typical Installation Details Rev 0 5 13-Jul-14 20-Jul-14
Submittal of Low Current Systems Typical Installation Details Rev 0 5 13-Jul-14 20-Jul-14
Submittal of Power System Typical Installation Details Rev 0 5 15-Jul-14 22-Jul-14
Reply of Lighting System Typical Installation Details Rev 0 14 20-Jul-14 06-Aug-14
Reply of Low Current Systems Typical Installation Details Rev 0 14 20-Jul-14 06-Aug-14
Reply of Power System Typical Installation Details Rev 0 14 22-Jul-14 09-Aug-14
Submittal of Lighting System Typical Installation Details Rev 1 5 06-Aug-14 13-Aug-14
Submittal of Low Current Systems Typical Installation Details Rev 1 5 06-Aug-14 13-Aug-14
Submittal of Power System Typical Installation Details Rev 1 5 10-Aug-14 14-Aug-14
Approval of Lighting System Typical Installation Details Rev 1 7 13-Aug-14 21-Aug-14
Approval of Low Current Systems Typical Installation Details Rev 1 7 13-Aug-14 21-Aug-14
Approval of Power System Typical Installation Details Rev 1 7 16-Aug-14 23-Aug-14
Electrical Enlarge Plans 67 19-Apr-15 06-Jul-15
Submittal of Guest Rooms Lighting System Rev 0 5 19-Apr-15 23-Apr-15
Submittal of Guest Rooms IT System Rev 0 5 19-Apr-15 23-Apr-15
Submittal of Guest Rooms Power System Rev 0 5 23-Apr-15 29-Apr-15
Reply of Guest Rooms Lighting System Rev 0 14 26-Apr-15 11-May-15
Reply of Guest Rooms IT System Rev 0 14 26-Apr-15 11-May-15
Reply of Guest Rooms Power System Rev 0 14 30-Apr-15 16-May-15
Submittal of Guest Rooms Lighting System Rev 1 5 12-May-15 18-May-15
Jun Jul Aug Sep Oct Nov Dec
Qtr 3 Qtr 4
2014
SECON Nile Tower Project MEP Base Line Secon Nile Tower Project Siemens Scope 21-Mar-16 17:19
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 39 of 1076 TASK filter: All Activities
© Primavera Systems, Inc
Activity ID Activity Name Original
Duration
Start Finish
Submittal of Guest Rooms IT System Rev 1 5 12-May-15 18-May-15
Submittal of Guest Rooms Power System Rev 1 5 17-May-15 21-May-15
Approval of Guest Rooms Lighting System Rev 1 7 19-May-15 26-May-15
Approval of Guest Rooms IT System Rev 1 7 19-May-15 26-May-15
Approval of Guest Rooms Power System Rev 1 7 23-May-15 30-May-15
Submittal of Room Management System Rev 0 5 31-May-15 04-Jun-15
Reply of Room Management System Rev 0 14 06-Jun-15 21-Jun-15
Submittal of Room Management System Rev 1 5 22-Jun-15 28-Jun-15
Approval of Room Management System Rev 1 7 29-Jun-15 06-Jul-15
E
Electrical Single Line Diagrams 97 19-Apr-15 12-Aug-15
Power System 33 20-May-15 27-Jun-15
Power Single Line Diagram Submittal Rev 0 5 20-May-15 26-May-15
LVP, MDB's and Floors Panel Boards Submittal Rev 0 5 20-May-15 26-May-15
Power Risers (Bus Bar Details) Submittal Rev 0 5 20-May-15 26-May-15
Power Single Line Diagram Reply Rev 0 14 27-May-15 11-Jun-15
LVP, MDB's and Floors Panel Boards Reply Rev 0 14 27-May-15 11-Jun-15
Power Risers (Bus Bar Details) Reply Rev 0 14 27-May-15 11-Jun-15
Power Single Line Diagram Submittal Rev 1 5 14-Jun-15 18-Jun-15
LVP, MDB's and Floors Panel Boards Submittal Rev 1 5 14-Jun-15 18-Jun-15
Power Risers (Bus Bar Details) Submittal Rev 1 5 14-Jun-15 18-Jun-15
Power Single Line Diagram Approval Rev 1 7 20-Jun-15 27-Jun-15
LVP, MDB's and Floors Panel Boards Approval Rev 1 7 20-Jun-15 27-Jun-15
Power Risers (Bus Bar Details) Approval Rev 1 7 20-Jun-15 27-Jun-15
Lighting System 91 19-Apr-15 05-Aug-15
Dimming Control Schematic Diagram Submittal Rev 0 5 19-Apr-15 23-Apr-15
Dimming Control Schematic Diagram Reply Rev 0 14 26-Apr-15 11-May-15
Dimming Control Schematic Diagram Submittal Rev 1 5 12-May-15 18-May-15
Dimming Control Schematic Diagram Approval Rev 1 7 19-May-15 26-May-15
Central Battery Schematic Diagram Submittal Rev 0 5 28-Jun-15 02-Jul-15
Central Battery Schematic Diagram Reply Rev 0 14 04-Jul-15 20-Jul-15
Central Battery Schematic Diagram Submittal Rev 1 5 21-Jul-15 28-Jul-15
Central Battery Schematic Diagram Approval Rev 1 7 29-Jul-15 05-Aug-15
Low Current Systems 97 19-Apr-15 12-Aug-15
IPTV, Data , IPTEL S.L.D 32 19-Apr-15 26-May-15
IPTV, Data, IPTEL Single Line Diagram Submittal Rev 0 5 19-Apr-15 23-Apr-15
IPTV, Data, IPTEL Single Line Diagram Reply Rev 0 14 26-Apr-15 11-May-15
IPTV, Data, IPTEL Single Line Diagram Submittal Rev 1 5 12-May-15 18-May-15
IPTV, Data, IPTEL Single Line Diagram Approval Rev 1 7 19-May-15 26-May-15
Jun Jul Aug Sep Oct Nov Dec
Qtr 3 Qtr 4
2014
SECON Nile Tower Project MEP Base Line Secon Nile Tower Project Siemens Scope 21-Mar-16 17:19
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 41 of 1076 TASK filter: All Activities
© Primavera Systems, Inc
Activity ID Activity Name Original
Duration
Start Finish
TEL System S.L.D 32 19-Apr-15 26-May-15
Telephone System Single Line Diagram Submittal Rev 0 5 19-Apr-15 23-Apr-15
Telephone System Single Line Diagram Reply Rev 0 14 26-Apr-15 11-May-15
Telephone System Single Line Diagram Submittal Rev 1 5 12-May-15 18-May-15
Telephone System Single Line Diagram Approval Rev 1 7 19-May-15 26-May-15
MATV System S.L.D 33 19-May-15 25-Jun-15
MATV Single Line Diagram Submittal Rev 0 5 19-May-15 25-May-15
MATV Single Line Diagram Reply Rev 0 14 26-May-15 10-Jun-15
MATV Single Line Diagram Submittal Rev 1 5 11-Jun-15 17-Jun-15
MATV Single Line Diagram Approval Rev 1 7 18-Jun-15 25-Jun-15
Sound System S.L.D 32 17-May-15 22-Jun-15
Sound System Single Line Diagram Submittal Rev 0 5 17-May-15 21-May-15
Sound System Single Line Diagram Reply Rev 0 14 23-May-15 07-Jun-15
Sound System Single Line Diagram Submittal Rev 1 5 08-Jun-15 14-Jun-15
Sound System Single Line Diagram Approval Rev 1 7 15-Jun-15 22-Jun-15
CCTV System S.L.D 33 15-Jun-15 25-Jul-15
CCTV System Single Line Diagram Submittal Rev 0 5 15-Jun-15 21-Jun-15
CCTV System Single Line Diagram Reply Rev 0 14 22-Jun-15 07-Jul-15
CCTV System Single Line Diagram Submittal Rev 1 5 08-Jul-15 14-Jul-15
CCTV System Single Line Diagram Approval Rev 1 7 15-Jul-15 25-Jul-15
Parking System S.L.D 33 27-May-15 04-Jul-15
Parking System Single Line Diagram Submittal Rev 0 5 27-May-15 02-Jun-15
Parking System Single Line Diagram Reply Rev 0 14 03-Jun-15 18-Jun-15
Parking System Single Line Diagram Submittal Rev 1 5 21-Jun-15 25-Jun-15
Parking System Single Line Diagram Approval Rev 1 7 27-Jun-15 04-Jul-15
Audio Video Intercom S.L.D 32 05-Jul-15 12-Aug-15
Audio Video Intercom System Single Line Diagram Submittal Rev 0 5 05-Jul-15 09-Jul-15
Audio Video Intercom System Single Line Diagram Reply Rev 0 14 11-Jul-15 28-Jul-15
Audio Video Intercom System Single Line Diagram Submittal Rev 1 5 29-Jul-15 04-Aug-15
Audio Video Intercom System Single Line Diagram Approval Rev 1 7 05-Aug-15 12-Aug-15
Fire Alarm S.L.D 32 17-May-15 22-Jun-15
Fire Alarm System Single Line Diagram Submittal Rev 0 5 17-May-15 21-May-15
Fire Alarm System Single Line Diagram Reply Rev 0 14 23-May-15 07-Jun-15
Fire Alarm System Single Line Diagram Submittal Rev 1 5 08-Jun-15 14-Jun-15
Fire Alarm System Single Line Diagram Approval Rev 1 7 15-Jun-15 22-Jun-15
E
Electrical Rooms / Electrical Equipments Rooms 160 26-Jan-15 03-Aug-15
Electrical Rooms Layout 33 23-Feb-15 02-Apr-15
Submittal of Electrical Rooms Layout Rev 0 5 23-Feb-15 02-Mar-15
Reply of Electrical Rooms Layout Rev 0 14 02-Mar-15 18-Mar-15
Jun Jul Aug Sep Oct Nov Dec
Qtr 3 Qtr 4
2014
SECON Nile Tower Project MEP Base Line Secon Nile Tower Project Siemens Scope 21-Mar-16 17:20
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 43 of 1076 TASK filter: All Activities
© Primavera Systems, Inc
Activity ID Activity Name Original
Duration
Start Finish
Submittal of Electrical Rooms Layout Rev 1 5 18-Mar-15 25-Mar-15
Approval of Electrical Rooms Layout Rev 1 7 25-Mar-15 02-Apr-15
RMU Room Layout 33 23-Feb-15 02-Apr-15
Submittal of RMU Room Layout Rev 0 5 23-Feb-15 02-Mar-15
Reply of RMU Room Layout Rev 0 14 02-Mar-15 18-Mar-15
Submittal of RMU Room Layout Rev 1 5 18-Mar-15 25-Mar-15
Approval of RMU Room Layout Rev 1 7 25-Mar-15 02-Apr-15
Medium Voltage Distributor (MVSG) Room Layout 33 23-Feb-15 02-Apr-15
Submittal of MVSG Room Layout Rev 0 5 23-Feb-15 02-Mar-15
Reply of MVSG Room Layout Rev 0 14 02-Mar-15 18-Mar-15
Submittal of MVSG Room Layout Rev 1 5 18-Mar-15 25-Mar-15
Approval of MVSG Room Layout Rev 1 7 25-Mar-15 02-Apr-15
Transformers Room Layout 33 26-Jan-15 04-Mar-15
Submittal of Transformers Room Layout Rev 0 5 26-Jan-15 01-Feb-15
Reply of Transformers Room Layout Rev 0 14 02-Feb-15 17-Feb-15
Submittal of Transformers Room Layout Rev 1 5 18-Feb-15 24-Feb-15
Approval of Transformers Room Layout Rev 1 7 25-Feb-15 04-Mar-15
Generator Room Layout 33 10-Mar-15 16-Apr-15
Submittal of Generator Room Layout Rev 0 5 10-Mar-15 16-Mar-15
Reply of Generator Room Layout Rev 0 14 17-Mar-15 01-Apr-15
Submittal of Generator Room Layout Rev 1 5 02-Apr-15 08-Apr-15
Approval of Generator Room Layout Rev 1 7 09-Apr-15 16-Apr-15
IT Rooms (IDF) Layout 33 26-Jan-15 04-Mar-15
Submittal of IT Rooms Layout Rev 0 5 26-Jan-15 01-Feb-15
Reply of IT Rooms Layout Rev 0 14 02-Feb-15 17-Feb-15
Submittal of IT Rooms Layout Rev 1 5 18-Feb-15 24-Feb-15
Approval of IT Rooms Layout Rev 1 7 25-Feb-15 04-Mar-15
Security Room Layout 34 23-Jun-15 03-Aug-15
Submittal of Security Room Layout Rev 0 5 23-Jun-15 29-Jun-15
Reply of Security Room Layout Rev 0 14 30-Jun-15 15-Jul-15
Submittal of Security Room Layout Rev 1 5 19-Jul-15 26-Jul-15
Approval of Security Room Layout Rev 1 7 27-Jul-15 03-Aug-15
Me
Mechanical 371 13-Jul-14 28-Sep-15
M
Mechanical Typical Installation Details 35 13-Jul-14 23-Aug-14
HVAC Typical Installation Details 33 13-Jul-14 21-Aug-14
Submittal of HVAC System Typical Installation Details Rev 0 5 13-Jul-14 20-Jul-14
Reply of HVAC System Typical Installation Details Rev 0 14 20-Jul-14 06-Aug-14
Submittal of HVAC System Typical Installation Details Rev 1 5 06-Aug-14 13-Aug-14
Jun Jul Aug Sep Oct Nov Dec
Qtr 3 Qtr 4
2014
SECON Nile Tower Project MEP Base Line Secon Nile Tower Project Siemens Scope 21-Mar-16 17:20
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 45 of 1076 TASK filter: All Activities
© Primavera Systems, Inc
Activity ID Activity Name Original
Duration
Start Finish
Approval of HVAC System Typical Installation Details Rev 1 7 13-Aug-14 21-Aug-14
Fire Fighting Typical Installation Details 33 13-Jul-14 21-Aug-14
Submittal of Fire Fighting System Typical Installation Details Rev 0 5 13-Jul-14 20-Jul-14
Reply of Fire Fighting System Typical Installation Details Rev 0 14 20-Jul-14 06-Aug-14
Submittal of Fire Fighting System Typical Installation Details Rev 1 5 06-Aug-14 13-Aug-14
Approval of Fire Fighting System Typical Installation Details Rev 1 7 13-Aug-14 21-Aug-14
Plumbing Typical Installation Details 35 13-Jul-14 23-Aug-14
Submittal of Water Supply System Typical Installation Details Rev 0 5 13-Jul-14 20-Jul-14
Submittal of Drainage System Typical Installation Details Rev 0 5 15-Jul-14 22-Jul-14
Reply of Water Supply System Typical Installation Details Rev 0 14 20-Jul-14 06-Aug-14
Reply of Drainage System Typical Installation Details Rev 0 14 22-Jul-14 09-Aug-14
Submittal of Water Supply System Typical Installation Details Rev 1 5 06-Aug-14 13-Aug-14
Submittal of Drainage System Typical Installation Details Rev 1 5 10-Aug-14 14-Aug-14
Approval of Water Supply System Typical Installation Details Rev 1 7 13-Aug-14 21-Aug-14
Approval of Drainage System Typical Installation Details Rev 1 7 16-Aug-14 23-Aug-14
M
Mechanical Risers 112 17-May-15 28-Sep-15
HVAC Risers 32 17-May-15 22-Jun-15
Chilled Water Riser Diagram Submittal Rev 0 5 17-May-15 21-May-15
Fresh Air Riser Diagram Submittal Rev 0 5 17-May-15 21-May-15
Exhaust Air Riser Diagram Submittal Rev 0 5 17-May-15 21-May-15
A.H.U Riser Diagram Submittal Rev 0 5 17-May-15 21-May-15
Chilled Water Riser Diagram Reply Rev 0 14 23-May-15 07-Jun-15
Fresh Air Riser Diagram Reply Rev 0 14 23-May-15 07-Jun-15
Exhaust Air Riser Diagram Reply Rev 0 14 23-May-15 07-Jun-15
A.H.U Riser Diagram Reply Rev 0 14 23-May-15 07-Jun-15
Chilled Water Riser Diagram Submittal Rev 1 5 08-Jun-15 14-Jun-15
Fresh Air Riser Diagram Submittal Rev 1 5 08-Jun-15 14-Jun-15
Exhaust Air Riser Diagram Submittal Rev 1 5 08-Jun-15 14-Jun-15
A.H.U Riser Diagram Submittal Rev 1 5 08-Jun-15 14-Jun-15
Chilled Water Riser Diagram Approval Rev 1 7 15-Jun-15 22-Jun-15
Fresh Air Riser Diagram Approval Rev 1 7 15-Jun-15 22-Jun-15
Exhaust Air Riser Diagram Approval Rev 1 7 15-Jun-15 22-Jun-15
A.H.U Riser Diagram Approval Rev 1 7 15-Jun-15 22-Jun-15
Fire Fighting Risers 32 17-May-15 22-Jun-15
Fire Fighting Riser Diagram Submittal Rev 0 5 17-May-15 21-May-15
Fire Fighting Riser Diagram Reply Rev 0 14 23-May-15 07-Jun-15
Fire Fighting Riser Diagram Submittal Rev 1 5 08-Jun-15 14-Jun-15
Fire Fighting Riser Diagram Approval Rev 1 7 15-Jun-15 22-Jun-15
Jun Jul Aug Sep Oct Nov Dec
Qtr 3 Qtr 4
2014
SECON Nile Tower Project MEP Base Line Secon Nile Tower Project Siemens Scope 21-Mar-16 17:20
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 47 of 1076 TASK filter: All Activities
© Primavera Systems, Inc
Activity ID Activity Name Original
Duration
Start Finish
Drainage Risers 33 19-Aug-15 28-Sep-15
Drainage Riser Diagram Submittal Rev 0 5 19-Aug-15 25-Aug-15
Drainage Riser Diagram Reply Rev 0 14 26-Aug-15 10-Sep-15
Drainage Riser Diagram Submittal Rev 1 5 13-Sep-15 17-Sep-15
Drainage Riser Diagram Approval Rev 1 7 19-Sep-15 28-Sep-15
Water Supply Risers 32 16-Aug-15 21-Sep-15
Water Supply Riser Diagram Submittal Rev 0 5 16-Aug-15 20-Aug-15
Water Supply Riser Diagram Reply Rev 0 14 22-Aug-15 06-Sep-15
Water Supply Riser Diagram Submittal Rev 1 5 07-Sep-15 13-Sep-15
Water Supply Riser Diagram Approval Rev 1 7 14-Sep-15 21-Sep-15
M
Mechanical Equipments Rooms & Calcluations 184 17-Sep-14 23-Apr-15
HVAC System Calculations 109 22-Sep-14 31-Jan-15
Chilled Water Pumps Head Calculations Submittal Rev 0 15 22-Sep-14 14-Oct-14
F.C.U Static Head Calculations Submittal Rev 0 15 02-Oct-14 26-Oct-14
Chilled Water Pumps Head Calculations Reply Rev 0 14 14-Oct-14 30-Oct-14
Cooling Tower Capacity & Pumps Head Calculations Submittal Rev 0 15 13-Oct-14 03-Nov-14
F.C.U Static Head Calculations Reply Rev 0 14 26-Oct-14 11-Nov-14
Expansion Tank Calculations Submittal Rev 0 15 27-Oct-14 17-Nov-14
Cooling Tower Capacity & Pumps Head Calculations Reply Rev 0 14 03-Nov-14 19-Nov-14
Chilled Water Pumps Head Calculations Submittal Rev 1 15 30-Oct-14 20-Nov-14
Chilled Water Pumps Head Calculations Approval Rev 1 7 20-Nov-14 29-Nov-14
F.C.U Static Head Calculations Submittal Rev 1 15 11-Nov-14 02-Dec-14
Expansion Tank Calculations Reply Rev 0 14 17-Nov-14 03-Dec-14
Cooling Tower Capacity & Pumps Head Calculations Submittal Rev 1 15 19-Nov-14 10-Dec-14
F.C.U Static Head Calculations Approval Rev 1 7 02-Dec-14 10-Dec-14
Supply & Exhaust Fans Static Head Calculations Submittal Rev 0 15 23-Nov-14 14-Dec-14
A.H.U Static Head Calculations Submittal Rev 0 15 23-Nov-14 14-Dec-14
Cooling Tower Capacity & Pumps Head Calculations Approval Rev 1 7 10-Dec-14 18-Dec-14
Expansion Tank Calculations Submittal Rev 1 15 03-Dec-14 24-Dec-14
Supply & Exhaust Fans Static Head Calculations Reply Rev 0 14 14-Dec-14 30-Dec-14
A.H.U Static Head Calculations Reply Rev 0 14 14-Dec-14 30-Dec-14
Expansion Tank Calculations Approval Rev 1 7 24-Dec-14 01-Jan-15
Supply & Exhaust Fans Static Head Calculations Submittal Rev 1 15 30-Dec-14 21-Jan-15
A.H.U Static Head Calculations Submittal Rev 1 15 30-Dec-14 21-Jan-15
Supply & Exhaust Fans Static Head Calculations Approval Rev 1 7 21-Jan-15 31-Jan-15
A.H.U Static Head Calculations Approval Rev 1 7 21-Jan-15 31-Jan-15
HVAC System Equipments 60 30-Nov-14 10-Feb-15
Chiller Plant & AHU Sections and Details Submittal Rev. 0 10 30-Nov-14 11-Dec-14
Jun Jul Aug Sep Oct Nov Dec
Qtr 3 Qtr 4
2014
SECON Nile Tower Project MEP Base Line Secon Nile Tower Project Siemens Scope 21-Mar-16 17:20
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 49 of 1076 TASK filter: All Activities
© Primavera Systems, Inc
Activity ID Activity Name Original
Duration
Start Finish
Chiller Plant & AHU Sections and Details Approval Rev. 0 10 13-Dec-14 23-Dec-14
Cooling Tower Plant Sections and Details Submittal Rev.0 10 18-Dec-14 01-Jan-15
Chiller Plant & AHU Sections and Details Submittal Rev. 1 10 24-Dec-14 06-Jan-15
Cooling Tower Plant Sections and Details Approval Rev.0 10 01-Jan-15 14-Jan-15
Chiller Plant & AHU Sections and Details Approval Rev. 1 10 08-Jan-15 19-Jan-15
Cooling Tower Plant Sections and Details Submittal Rev.1 10 14-Jan-15 29-Jan-15
Cooling Tower Plant Sections and Details Approval Rev.1 10 29-Jan-15 10-Feb-15
FF System Calculations 57 01-Oct-14 08-Dec-14
Fire Fighting Pumps Head Calculations Submittal Rev 0 15 01-Oct-14 23-Oct-14
Fire Fighting Pumps Head Calculations Reply Rev 0 14 23-Oct-14 09-Nov-14
Fire Fighting Pumps Head Calculations Submittal Rev 1 15 09-Nov-14 30-Nov-14
Fire Fighting Pumps Head Calculations Approval Rev 1 7 30-Nov-14 08-Dec-14
FF System Equipments 44 22-Dec-14 14-Feb-15
Fire Fighting Pumps Plant Sections and Details Submittal Rev.0 10 22-Dec-14 05-Jan-15
Fire Fighting Pumps Plant Sections and Details Approval Rev.0 10 05-Jan-15 18-Jan-15
Fire Fighting Pumps Plant Sections and Details Submittal Rev.1 10 18-Jan-15 02-Feb-15
Fire Fighting Pumps Plant Sections and Details Approval Rev.1 10 02-Feb-15 14-Feb-15
Plumbing System Calculations 121 17-Sep-14 09-Feb-15
Plumbing Pumps Head Calculations Approval Rev 1 7 17-Sep-14 25-Sep-14
Plumbing Pumps Head Calculations Submittal Rev 0 15 10-Dec-14 31-Dec-14
Plumbing Pumps Head Calculations Reply Rev 0 14 31-Dec-14 18-Jan-15
Plumbing Pumps Head Calculations Submittal Rev 1 15 18-Jan-15 09-Feb-15
Plumbing System Equipments 44 03-Mar-15 23-Apr-15
Plumbing Pumps Plant Sections and Details Submittal Rev.0 10 03-Mar-15 17-Mar-15
Plumbing Pumps Plant Sections and Details Approval Rev.0 10 17-Mar-15 29-Mar-15
Plumbing Pumps Plant Sections and Details Submittal Rev.1 10 29-Mar-15 12-Apr-15
Plumbing Pumps Plant Sections and Details Approval Rev.1 10 12-Apr-15 23-Apr-15
B
BMS System 137 31-Dec-14 13-Jun-15
Boiler Plant Sections and Details Submittal Rev.0 10 08-Feb-15 19-Feb-15
Boiler Pumps Plant Sections and Details Approval Rev.0 10 21-Feb-15 03-Mar-15
Boiler Pumps Plant Sections and Details Submittal Rev.1 10 04-Mar-15 17-Mar-15
Boiler Pumps Plant Sections and Details Approval Rev.1 10 18-Mar-15 29-Mar-15
BMS S.L.D 45 31-Dec-14 24-Feb-15
BMS S.L.D Submittal Rev 0 10 31-Dec-14 15-Jan-15
BMS S.L.D Reply Rev 0 14 15-Jan-15 02-Feb-15
BMS S.L.D Submittal Rev 1 10 02-Feb-15 16-Feb-15
BMS S.L.D Approval Rev 1 7 16-Feb-15 24-Feb-15
BMS For Floors 92 24-Feb-15 13-Jun-15
Jun Jul Aug Sep Oct Nov Dec
Qtr 3 Qtr 4
2014
SECON Nile Tower Project MEP Base Line Secon Nile Tower Project Siemens Scope 21-Mar-16 17:20
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 51 of 1076 TASK filter: All Activities
© Primavera Systems, Inc
Activity ID Activity Name Original
Duration
Start Finish
BMS Submittal Rev. 0 65 24-Feb-15 12-May-15
BMS Submittal For Lower Basement Floor Rev 0 5 24-Feb-15 03-Mar-15
BMS Submittal For Upper Basement Floor Rev 0 5 03-Mar-15 10-Mar-15
BMS Submittal For Lower Ground Floor Rev 0 5 10-Mar-15 17-Mar-15
BMS Submittal For Ground Floor Rev 0 5 17-Mar-15 24-Mar-15
BMS Submittal For First Floor Rev 0 5 24-Mar-15 31-Mar-15
BMS Submittal For Second Floor Rev 0 5 31-Mar-15 07-Apr-15
BMS Submittal For Third Floor Rev 0 5 07-Apr-15 14-Apr-15
BMS Submittal For Typical Floors (4:20) Rev 0 5 14-Apr-15 21-Apr-15
BMS Submittal For Twenty First Floor Rev 0 5 21-Apr-15 28-Apr-15
BMS Submittal For Twenty Second Floor Rev 0 5 28-Apr-15 05-May-15
BMS Submittal For Roof Floor Rev 0 5 05-May-15 12-May-15
BMS Submittal Rev. 1 65 19-Mar-15 04-Jun-15
BMS Submittal For Lower Basement Floor Rev 1 5 19-Mar-15 26-Mar-15
BMS Submittal For Upper Basement Floor Rev 1 5 26-Mar-15 02-Apr-15
BMS Submittal For Lower Ground Floor Rev 1 5 02-Apr-15 09-Apr-15
BMS Submittal For Ground Floor Rev 1 5 09-Apr-15 16-Apr-15
BMS Submittal For First Floor Rev 1 5 16-Apr-15 23-Apr-15
BMS Submittal For Second Floor Rev 1 5 23-Apr-15 30-Apr-15
BMS Submittal For Third Floor Rev 1 5 03-May-15 07-May-15
BMS Submittal For Typical Floors (4:20) Rev 1 5 10-May-15 14-May-15
BMS Submittal For Twenty First Floor Rev 1 5 14-May-15 21-May-15
BMS Submittal For Twenty Second Floor Rev 1 5 21-May-15 28-May-15
BMS Submittal For Roof Floor Rev 1 5 28-May-15 04-Jun-15
BMS Approval Rev. 0 73 03-Mar-15 28-May-15
BMS Reply For Lower Basement Floor Rev 0 14 03-Mar-15 19-Mar-15
BMS Reply For Upper Basement Floor Rev 0 14 10-Mar-15 26-Mar-15
BMS Reply For Lower Ground Floor Rev 0 14 17-Mar-15 02-Apr-15
BMS Reply For Ground Floor Rev 0 14 24-Mar-15 09-Apr-15
BMS Reply For First Floor Rev 0 14 31-Mar-15 16-Apr-15
BMS Reply For Second Floor Rev 0 14 07-Apr-15 23-Apr-15
BMS Reply For Third Floor Rev 0 14 14-Apr-15 02-May-15
BMS Reply For Typical Floors (4:20) Rev 0 14 21-Apr-15 09-May-15
BMS Reply For Twenty First Floor Rev 0 14 28-Apr-15 14-May-15
BMS Reply For Twenty Second Floor Rev 0 14 05-May-15 21-May-15
BMS Reply For Roof Floor Rev 0 14 12-May-15 28-May-15
BMS Approval Rev. 1 66 26-Mar-15 13-Jun-15
BMS Approval For Lower Basement Floor Rev 1 7 26-Mar-15 04-Apr-15
BMS Approval For Upper Basement Floor Rev 1 7 02-Apr-15 11-Apr-15
Jun Jul Aug Sep Oct Nov Dec
Qtr 3 Qtr 4
2014
SECON Nile Tower Project MEP Base Line Secon Nile Tower Project Siemens Scope 21-Mar-16 17:20
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 53 of 1076 TASK filter: All Activities
© Primavera Systems, Inc
Activity ID Activity Name Original
Duration
Start Finish
BMS Approval For Lower Ground Floor Rev 1 7 09-Apr-15 18-Apr-15
BMS Approval For Ground Floor Rev 1 7 16-Apr-15 26-Apr-15
BMS Approval For First Floor Rev 1 7 23-Apr-15 03-May-15
BMS Approval For Second Floor Rev 1 7 30-Apr-15 09-May-15
BMS Approval For Third Floor Rev 1 7 09-May-15 16-May-15
BMS Approval For Typical Floors (4:20) Rev 1 7 16-May-15 23-May-15
BMS Approval For Twenty First Floor Rev 1 7 21-May-15 30-May-15
BMS Approval For Twenty Second Floor Rev 1 7 28-May-15 06-Jun-15
BMS Approval For Roof Floor Rev 1 7 04-Jun-15 13-Jun-15
As B
As Built Drawings And Operation Manuals 0
Procu
Procurement 378 08-Jul-14 01-Oct-15
Elec
Electrical Systems 378 08-Jul-14 01-Oct-15
SSM Siemens Receive Final Electrical Specifications Including MCC's 0 08-Jul-14
SSM Siemens Receive Final Electrical Vendor List 0 08-Jul-14
Po
Power System 378 08-Jul-14 01-Oct-15
M
Material Submittal 199 08-Jul-14 02-Mar-15
Rev 0 178 08-Jul-14 05-Feb-15
CABLE TRAYS MATERIAL SUBMITTAL REV 0 10 08-Jul-14 22-Jul-14
PVC Conduits & Back Boxes Material Submittal Rev 0 10 08-Jul-14 22-Jul-14
MEDIUM VOLTAGE CABLES MATERIAL SUBMITTAL REV 0 20 07-Sep-14 05-Oct-14
LOW VOLTAGE CABLES MATERIAL SUBMITTAL REV 0 20 07-Sep-14 05-Oct-14
Fire Resistance Cables Material Submittal Rev 0 20 07-Sep-14 05-Oct-14
Copper Wires For Sockets and Lighting Outlets Material Submittal Rev 0 20 07-Sep-14 05-Oct-14
Cooper Cables For Small Power Outlets Material Submittal Rev 0 20 07-Sep-14 05-Oct-14
Cable Accessories Material Submittal Rev 0 20 07-Sep-14 05-Oct-14
UPS Material Submittal Rev 0 20 23-Sep-14 22-Oct-14
BUS BAR TRUNKING MATERIAL SUBMITTAL REV 0 20 09-Oct-14 06-Nov-14
DISTRIBUTION TRANSFORMER MATERIAL SUBMITTAL REV 0 20 23-Nov-14 21-Dec-14
Disconnect Switches & Power Accessories Material Submittal Rev 0 20 07-Dec-14 04-Jan-15
Floor Mounted Skirting Box Material Submittal Rev 0 20 07-Dec-14 04-Jan-15
MV RING MAIN UNIT MATERIAL SUBMITTAL REV 0 20 21-Dec-14 19-Jan-15
MV DISTRIBUTOR MATERIAL SUBMITTAL REV 0 20 21-Dec-14 19-Jan-15
LOW VOLTAGE SWITCH GEAR & SWITCH BOARDS MATERIAL SUBMITTAL
REV 0
20 21-Dec-14 19-Jan-15
DISTRIBUTION AND SUB DISTRIBUTION PANEL BOARD MATERIAL
SUBMITTAL REV 0
20 21-Dec-14 19-Jan-15
STANDBY GENERATOR SET MATERIAL SUBMITTAL REV 0 20 05-Jan-15 04-Feb-15
Jun Jul Aug Sep Oct Nov Dec
Qtr 3 Qtr 4
2014
SECON Nile Tower Project MEP Base Line Secon Nile Tower Project Siemens Scope 21-Mar-16 17:20
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 55 of 1076 TASK filter: All Activities
© Primavera Systems, Inc
Activity ID Activity Name Original
Duration
Start Finish
ATS MATERIAL SUBMITTAL REV 0 20 05-Jan-15 04-Feb-15
Guest Room Management System Material Submittal Rev 0 20 06-Jan-15 05-Feb-15
Rev 1 172 10-Aug-14 02-Mar-15
CABLE TRAYS MATERIAL SUBMITTAL REV 1 6 10-Aug-14 17-Aug-14
PVC Conduits & Back Boxes Material Submittal Rev 1 6 10-Aug-14 18-Aug-14
MEDIUM VOLTAGE CABLES MATERIAL SUBMITTAL REV 1 6 22-Oct-14 30-Oct-14
LOW VOLTAGE CABLES MATERIAL SUBMITTAL REV 1 6 22-Oct-14 30-Oct-14
Fire Resistance Cables Material Submittal Rev 1 6 22-Oct-14 30-Oct-14
Copper Wires Material Submittal Rev 1 6 22-Oct-14 30-Oct-14
Cooper Cables For Small Power Outlets Material Submittal Rev 1 6 22-Oct-14 30-Oct-14
Cable Accessories Material Submittal Rev 1 6 22-Oct-14 30-Oct-14
UPS Material Submittal Rev 1 6 09-Nov-14 16-Nov-14
BUS BAR TRUNKING MATERIAL SUBMITTAL REV 1 6 23-Nov-14 01-Dec-14
DISTRIBUTION TRANSFORMER MATERIAL SUBMITTAL REV 1 6 06-Jan-15 15-Jan-15
Disconnect Switches & Power Accessories Material Submittal Rev 1 6 21-Jan-15 01-Feb-15
Floor Mounted Skirting Box Material Submittal Rev 1 6 21-Jan-15 01-Feb-15
MV RING MAIN UNIT MATERIAL SUBMITTAL REV 1 6 05-Feb-15 15-Feb-15
MV DISTRIBUTOR MATERIAL SUBMITTAL REV 1 6 05-Feb-15 15-Feb-15
LOW VOLTAGE SWITCH GEAR & SWITCH BOARDS MATERIAL SUBMITTAL
REV 1
6 05-Feb-15 15-Feb-15
DISTRIBUTION AND SUB DISTRIBUTION PANEL BOARD MATERIAL
SUBMITTAL REV 1
6 05-Feb-15 15-Feb-15
STANDBY GENERATOR SET MATERIAL SUBMITTAL REV 1 6 22-Feb-15 01-Mar-15
ATS MATERIAL SUBMITTAL REV 1 6 22-Feb-15 01-Mar-15
Guest Room Management System Material Submittal Rev 1 6 22-Feb-15 02-Mar-15
M
Material Approvals 194 22-Jul-14 10-Mar-15
Rev 0 180 22-Jul-14 22-Feb-15
CABLE TRAYS MATERIAL REPLY REV 0 14 22-Jul-14 09-Aug-14
PVC Conduits & Back Boxes Material Reply Rev 0 14 22-Jul-14 09-Aug-14
MEDIUM VOLTAGE CABLES MATERIAL REPLY REV 0 14 05-Oct-14 22-Oct-14
LOW VOLTAGE CABLES MATERIAL REPLY REV 0 14 05-Oct-14 22-Oct-14
Fire Resistance Cables Material Reply Rev 0 14 05-Oct-14 22-Oct-14
Copper Wires Material Reply Rev 0 14 05-Oct-14 22-Oct-14
Cooper Cables For Small Power Outlets Material Reply Rev 0 14 05-Oct-14 22-Oct-14
Cable Accessories Material Reply Rev 0 14 05-Oct-14 22-Oct-14
UPS Material Reply Rev 0 14 22-Oct-14 08-Nov-14
BUS BAR TRUNKING MATERIAL REPLY REV 0 14 06-Nov-14 23-Nov-14
DISTRIBUTION TRANSFORMER MATERIAL REPLY REV 0 14 21-Dec-14 06-Jan-15
Disconnect Switches & Power Accessories Material Reply Rev 0 14 04-Jan-15 21-Jan-15
Jun Jul Aug Sep Oct Nov Dec
Qtr 3 Qtr 4
2014
SECON Nile Tower Project MEP Base Line Secon Nile Tower Project Siemens Scope 21-Mar-16 17:20
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 57 of 1076 TASK filter: All Activities
© Primavera Systems, Inc
Activity ID Activity Name Original
Duration
Start Finish
Floor Mounted Skirting Box Material Reply Rev 0 14 04-Jan-15 21-Jan-15
MV RING MAIN UNIT MATERIAL REPLY REV 0 14 19-Jan-15 05-Feb-15
MV DISTRIBUTOR MATERIAL REPLY REV 0 14 19-Jan-15 05-Feb-15
LOW VOLTAGE SWITCH GEAR & SWITCH BOARDS MATERIAL REPLY REV 0 14 19-Jan-15 05-Feb-15
DISTRIBUTION AND SUB DISTRIBUTION PANEL BOARD MATERIAL REPLY
REV 0
14 19-Jan-15 05-Feb-15
STANDBY GENERATOR SET MATERIAL REPLY REV 0 14 04-Feb-15 21-Feb-15
ATS MATERIAL REPLY REV 0 14 04-Feb-15 21-Feb-15
Guest Room Management System Material Reply Rev 0 14 05-Feb-15 22-Feb-15
Rev 1 172 18-Aug-14 10-Mar-15
CABLE TRAYS MATERIALAPPROVAL REV 1 7 18-Aug-14 25-Aug-14
PVC Conduits & Back Boxes Material Approval Rev 1 7 18-Aug-14 26-Aug-14
MEDIUM VOLTAGE CABLES MATERIALAPPROVAL REV 1 7 30-Oct-14 08-Nov-14
LOW VOLTAGE CABLES MATERIAL APPROVAL REV 1 7 30-Oct-14 08-Nov-14
Fire Resistance Cables Material Approval Rev 1 7 30-Oct-14 08-Nov-14
Copper Wires Material Approval Rev 1 7 30-Oct-14 08-Nov-14
Cooper Cables For Small Power Outlets Material Approval Rev 1 7 30-Oct-14 08-Nov-14
Cable Accessories Material Approval Rev 1 7 30-Oct-14 08-Nov-14
UPS Material Approval Rev 1 7 17-Nov-14 24-Nov-14
BUS BAR TRUNKING MATERIALAPPROVAL REV 1 7 01-Dec-14 09-Dec-14
DISTRIBUTION TRANSFORMER MATERIALAPPROVAL REV 1 7 15-Jan-15 24-Jan-15
Disconnect Switches & Power Accessories Material Approval Rev 1 7 01-Feb-15 09-Feb-15
Floor Mounted Skirting Box Material Approval Rev 1 7 01-Feb-15 09-Feb-15
MV RING MAIN UNIT MATERIAL APPROVAL REV 1 7 15-Feb-15 23-Feb-15
MV DISTRIBUTOR MATERIAL APPROVAL REV 1 7 15-Feb-15 23-Feb-15
LOW VOLTAGE SWITCH GEAR & SWITCH BOARDS MATERIAL APPROVAL 7 15-Feb-15 23-Feb-15
DISTRIBUTION AND SUB DISTRIBUTION PANEL BOARD MATERIAL
APPROVAL REV 1
7 15-Feb-15 23-Feb-15
STANDBY GENERATOR SET MATERIAL APPROVAL REV 1 7 02-Mar-15 09-Mar-15
ATS MATERIALAPPROVAL REV 1 7 02-Mar-15 09-Mar-15
Guest Room Management System Material Approval Rev 1 7 02-Mar-15 10-Mar-15
M
Material PO's 221 26-Aug-14 14-May-15
PVC Conduits & Back Boxes Material PO 25 26-Aug-14 30-Sep-14
CABLE TRAYS MATERIAL PO 25 10-Sep-14 15-Oct-14
MEDIUM VOLTAGE CABLES MATERIAL PO 25 10-Nov-14 15-Dec-14
LOW VOLTAGE CABLES MATERIAL PO 25 10-Nov-14 15-Dec-14
Fire Resistance Cables Material PO 25 10-Nov-14 15-Dec-14
Copper Wires Material PO 25 10-Nov-14 15-Dec-14
Cooper Cables For Small Power Outlets Material PO 25 10-Nov-14 15-Dec-14
Jun Jul Aug Sep Oct Nov Dec
Qtr 3 Qtr 4
2014
SECON Nile Tower Project MEP Base Line Secon Nile Tower Project Siemens Scope 21-Mar-16 17:20
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 59 of 1076 TASK filter: All Activities
© Primavera Systems, Inc
Activity ID Activity Name Original
Duration
Start Finish
Cable Accessories Material PO 25 10-Nov-14 15-Dec-14
UPS Material PO 25 11-Dec-14 15-Jan-15
BUS BAR TRUNKING MATERIAL PO 25 24-Dec-14 01-Feb-15
DISTRIBUTION TRANSFORMER MATERIAL PO 25 08-Feb-15 15-Mar-15
Disconnect Switches & Power Accessories Material PO 25 25-Feb-15 01-Apr-15
Floor Mounted Skirting Box Material PO 25 25-Feb-15 01-Apr-15
MV RING MAIN UNIT MATERIAL PO 25 11-Mar-15 15-Apr-15
MV DISTRIBUTOR MATERIAL PO 25 11-Mar-15 15-Apr-15
LOW VOLTAGE SWITCH GEAR & SWITCH BOARDS MATERIAL PO 25 11-Mar-15 15-Apr-15
DISTRIBUTION AND SUB DISTRIBUTION PANEL BOARD MATERIAL PO 25 11-Mar-15 15-Apr-15
STANDBY GENERATOR SET MATERIAL PO 25 29-Mar-15 30-Apr-15
ATS MATERIAL PO 25 29-Mar-15 30-Apr-15
Guest Room Management System Material PO 25 12-Apr-15 14-May-15
M
Material Delivery at Site 307 30-Sep-14 01-Oct-15
PVC Conduits & Back Boxes Material Delivery 14 30-Sep-14 18-Oct-14
CABLE TRAYS MATERIAL DELIVERY 40 16-Oct-14 01-Dec-14
MEDIUM VOLTAGE CABLES MATERIAL DELIVERY 75 15-Dec-14 15-Mar-15
LOW VOLTAGE CABLES MATERIAL DELIVERY 75 15-Dec-14 15-Mar-15
Fire Resistance Cables Material Delivery 75 15-Dec-14 15-Mar-15
Copper Wires Material Delivery 75 15-Dec-14 15-Mar-15
Cooper Cables For Small Power Outlets Material Delivery 75 15-Dec-14 15-Mar-15
Cable Accessories Material Delivery 75 15-Dec-14 15-Mar-15
UPS Material Delivery 76 17-Jan-15 15-Apr-15
BUS BAR TRUNKING MATERIAL DELIVERY 102 01-Feb-15 01-Jun-15
Disconnect Switches & Power Accessories Material Delivery 51 01-Apr-15 01-Jun-15
Floor Mounted Skirting Box Material Delivery 51 01-Apr-15 01-Jun-15
DISTRIBUTION TRANSFORMER MATERIAL DELIVERY 104 15-Mar-15 15-Jul-15
Guest Room Management System Material Delivery 77 16-May-15 15-Aug-15
MV RING MAIN UNIT MATERIAL DELIVERY 114 15-Apr-15 30-Aug-15
MV DISTRIBUTOR MATERIAL DELIVERY 114 15-Apr-15 30-Aug-15
LOW VOLTAGE SWITCH GEAR & SWITCH BOARDS MATERIAL DELIVERY 114 15-Apr-15 30-Aug-15
DISTRIBUTION AND SUB DISTRIBUTION PANEL BOARD MATERIAL DELIV 114 15-Apr-15 30-Aug-15
STANDBY GENERATOR SET MATERIAL DELIVERY 128 02-May-15 01-Oct-15
ATS MATERIAL DELIVERY 128 02-May-15 01-Oct-15
Lig
Lighting System 281 02-Oct-14 02-Sep-15
M
Material Submittal 126 02-Oct-14 02-Mar-15
Rev 0 105 02-Oct-14 05-Feb-15
Lighting Switches (Wiring Devices) Material Submittal Rev 0 20 02-Oct-14 02-Nov-14
Jun Jul Aug Sep Oct Nov Dec
Qtr 3 Qtr 4
2014
SECON Nile Tower Project MEP Base Line Secon Nile Tower Project Siemens Scope 21-Mar-16 17:20
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 61 of 1076 TASK filter: All Activities
© Primavera Systems, Inc
Activity ID Activity Name Original
Duration
Start Finish
Dimming System Material Submittal Rev 0 20 09-Oct-14 06-Nov-14
Lighting Fixtures Material Submittal Rev 0 20 10-Nov-14 08-Dec-14
Emergency Lighting Fixtures Material Submittal Rev 0 20 10-Nov-14 08-Dec-14
Addressable Central Battery Material Submittal Rev 0 20 06-Jan-15 05-Feb-15
Rev 1 87 18-Nov-14 02-Mar-15
Lighting Switches (Wiring Devices) Material Submittal Rev 1 6 18-Nov-14 26-Nov-14
Dimming System Material Submittal Rev 1 6 23-Nov-14 01-Dec-14
Lighting Fixtures Material Submittal Rev 1 6 24-Dec-14 01-Jan-15
Emergency Lighting Fixtures Material Submittal Rev 1 6 24-Dec-14 01-Jan-15
Addressable Central Battery Material Submittal Rev 1 6 22-Feb-15 02-Mar-15
M
Material Approvals 108 02-Nov-14 10-Mar-15
Rev 0 94 02-Nov-14 22-Feb-15
Lighting Switches (Wiring Devices) Material Reply Rev 0 14 02-Nov-14 18-Nov-14
Dimming System Material Reply Rev 0 14 06-Nov-14 23-Nov-14
Lighting Fixtures Material Reply Rev 0 14 08-Dec-14 24-Dec-14
Emergency Lighting Fixtures Material Reply Rev 0 14 08-Dec-14 24-Dec-14
Addressable Central Battery Material Reply Rev 0 14 05-Feb-15 22-Feb-15
Rev 1 87 26-Nov-14 10-Mar-15
Lighting Switches (Wiring Devices) Material Approval Rev 1 7 26-Nov-14 04-Dec-14
Dimming System Material Approval Rev 1 7 01-Dec-14 09-Dec-14
Lighting Fixtures Material Approval Rev 1 7 01-Jan-15 11-Jan-15
Emergency Lighting Fixtures Material Approval Rev 1 7 01-Jan-15 11-Jan-15
Addressable Central Battery Material Approval Rev 1 7 02-Mar-15 10-Mar-15
M
Material PO's 108 24-Dec-14 03-May-15
Dimming System Material PO 25 24-Dec-14 01-Feb-15
Lighting Fixtures Material PO 25 26-Jan-15 01-Mar-15
Emergency Lighting Fixtures Material PO 25 26-Jan-15 01-Mar-15
Lighting Switches (Wiring Devices) Material PO 25 25-Feb-15 01-Apr-15
Addressable Central Battery Material PO 25 29-Mar-15 03-May-15
M
Material Delivery at Site 180 01-Feb-15 02-Sep-15
Lighting Switches (Wiring Devices) Material Delivery 51 01-Apr-15 01-Jun-15
Dimming System Material Delivery 102 01-Feb-15 01-Jun-15
Lighting Fixtures Material Delivery 78 02-Mar-15 01-Jun-15
Emergency Lighting Fixtures Material Delivery 78 02-Mar-15 01-Jun-15
Addressable Central Battery Material Delivery 103 03-May-15 02-Sep-15
Lig
Light Current Systems 338 08-Jul-14 15-Aug-15
F
Fire Alarm System 217 17-Sep-14 01-Jun-15
Jun Jul Aug Sep Oct Nov Dec
Qtr 3 Qtr 4
2014
SECON Nile Tower Project MEP Base Line Secon Nile Tower Project Siemens Scope 21-Mar-16 17:20
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 63 of 1076 TASK filter: All Activities
© Primavera Systems, Inc
Activity ID Activity Name Original
Duration
Start Finish
Material Submittal 75 17-Sep-14 15-Dec-14
Rev 0 36 17-Sep-14 30-Oct-14
Fire Alarm System Material Submittal Rev 0 20 17-Sep-14 16-Oct-14
Fire Alarm Wiring Material Submittal Rev 0 20 01-Oct-14 30-Oct-14
Rev 1 36 03-Nov-14 15-Dec-14
Fire Alarm System Material Submittal Rev 1 20 03-Nov-14 01-Dec-14
Fire Alarm Wiring Material Submittal Rev 1 20 17-Nov-14 15-Dec-14
Material Approvals 58 16-Oct-14 23-Dec-14
Rev 0 26 16-Oct-14 16-Nov-14
Fire Alarm System Material Reply Rev 0 14 16-Oct-14 02-Nov-14
Fire Alarm Wiring Material Reply Rev 0 14 30-Oct-14 16-Nov-14
Rev 1 19 01-Dec-14 23-Dec-14
Fire Alarm System Material Approval Rev 1 7 01-Dec-14 09-Dec-14
Fire Alarm Wiring Material Approval Rev 1 7 15-Dec-14 23-Dec-14
Material PO's 56 24-Dec-14 01-Mar-15
Fire Alarm Wiring Material PO 25 24-Dec-14 01-Feb-15
Fire Alarm System Material PO 25 26-Jan-15 01-Mar-15
Material Delivery at Site 103 01-Feb-15 01-Jun-15
Fire Alarm Wiring Material Delivery 36 01-Feb-15 15-Mar-15
Fire Alarm System Material Delivery 78 02-Mar-15 01-Jun-15
S
Sound System Rack SSR 178 02-Nov-14 01-Jun-15
Material Submittal 71 02-Nov-14 26-Jan-15
Rev 0 31 02-Nov-14 08-Dec-14
Sound System Material Submittal Rev 0 20 02-Nov-14 30-Nov-14
Sound Wiring Material Submittal Rev 0 20 10-Nov-14 08-Dec-14
Rev 1 32 17-Dec-14 26-Jan-15
Sound System Material Submittal Rev 1 20 17-Dec-14 15-Jan-15
Sound Wiring Material Submittal Rev 1 20 25-Dec-14 26-Jan-15
Material Approvals 54 30-Nov-14 03-Feb-15
Rev 0 21 30-Nov-14 24-Dec-14
Sound System Material Reply Rev 0 14 30-Nov-14 16-Dec-14
Sound Wiring Material Reply Rev 0 14 08-Dec-14 24-Dec-14
Rev 1 15 15-Jan-15 03-Feb-15
Sound System Material Approval Rev 1 7 15-Jan-15 24-Jan-15
Sound Wiring Material Approval Rev 1 7 26-Jan-15 03-Feb-15
Material PO's 45 08-Feb-15 01-Apr-15
Sound System Material PO 25 08-Feb-15 15-Mar-15
Sound Wiring Material PO 25 25-Feb-15 01-Apr-15
Material Delivery at Site 65 16-Mar-15 01-Jun-15
Jun Jul Aug Sep Oct Nov Dec
Qtr 3 Qtr 4
2014
SECON Nile Tower Project MEP Base Line Secon Nile Tower Project Siemens Scope 21-Mar-16 17:20
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 65 of 1076 TASK filter: All Activities
© Primavera Systems, Inc
Activity ID Activity Name Original
Duration
Start Finish
Sound Wiring Material Delivery 35 02-Apr-15 14-May-15
Sound System Material Delivery 65 16-Mar-15 01-Jun-15
A
Audio Visual system for Multi Purpose Hall 176 18-Nov-14 15-Jun-15
Material Submittal 63 18-Nov-14 02-Feb-15
Rev 0 24 18-Nov-14 16-Dec-14
Audio Visual system Material Submittal Rev 0 20 18-Nov-14 16-Dec-14
Rev 1 25 01-Jan-15 02-Feb-15
Audio Visual system Material Submittal Rev 1 20 01-Jan-15 02-Feb-15
Material Approvals 46 16-Dec-14 10-Feb-15
Rev 0 14 16-Dec-14 01-Jan-15
Audio Visual system Material Reply Rev 0 14 16-Dec-14 01-Jan-15
Rev 1 7 02-Feb-15 10-Feb-15
Audio Visual system Material Approval Rev 1 7 02-Feb-15 10-Feb-15
Material PO's 30 25-Feb-15 01-Apr-15
Audio Visual system Material PO 25 25-Feb-15 01-Apr-15
Material Delivery at Site 62 02-Apr-15 15-Jun-15
Audio Visual system Material Delivery 62 02-Apr-15 15-Jun-15
C
CCTV System 178 02-Nov-14 01-Jun-15
Material Submittal 71 02-Nov-14 26-Jan-15
Rev 0 32 02-Nov-14 09-Dec-14
CCTV System Material Submittal Rev 0 20 02-Nov-14 30-Nov-14
CCTV Wiring Material Submittal Rev 0 20 11-Nov-14 09-Dec-14
Rev 1 33 16-Dec-14 26-Jan-15
CCTV System Material Submittal Rev 1 20 16-Dec-14 14-Jan-15
CCTV Wiring Material Submittal Rev 1 20 25-Dec-14 26-Jan-15
Material Approvals 54 30-Nov-14 03-Feb-15
Rev 0 22 30-Nov-14 25-Dec-14
CCTV System Material Reply Rev 0 14 30-Nov-14 16-Dec-14
CCTV Wiring Material Reply Rev 0 14 09-Dec-14 25-Dec-14
Rev 1 16 14-Jan-15 03-Feb-15
CCTV System Material Approval Rev 1 7 14-Jan-15 22-Jan-15
CCTV Wiring Material Approval Rev 1 7 26-Jan-15 03-Feb-15
Material PO's 30 08-Feb-15 15-Mar-15
CCTV System Material PO 25 08-Feb-15 15-Mar-15
CCTV Wiring Material PO 25 08-Feb-15 15-Mar-15
Material Delivery at Site 65 16-Mar-15 01-Jun-15
CCTV System Material Delivery 65 16-Mar-15 01-Jun-15
CCTV Wiring Material Delivery 65 16-Mar-15 01-Jun-15
Jun Jul Aug Sep Oct Nov Dec
Qtr 3 Qtr 4
2014
SECON Nile Tower Project MEP Base Line Secon Nile Tower Project Siemens Scope 21-Mar-16 17:20
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 67 of 1076 TASK filter: All Activities
© Primavera Systems, Inc
Activity ID Activity Name Original
Duration
Start Finish
L
Light Current Cable Tray 124 08-Jul-14 01-Dec-14
Material Submittal 34 08-Jul-14 17-Aug-14
Rev 0 12 08-Jul-14 22-Jul-14
Light Current Cable Tray Material Submittal Rev 0 10 08-Jul-14 22-Jul-14
Rev 1 7 10-Aug-14 17-Aug-14
Light Current Cable Tray Material Submittal Rev 1 6 10-Aug-14 17-Aug-14
Material Approvals 29 22-Jul-14 25-Aug-14
Rev 0 14 22-Jul-14 09-Aug-14
Light Current Cable Tray Material Reply Rev 0 14 22-Jul-14 09-Aug-14
Rev 1 7 18-Aug-14 25-Aug-14
Light Current Cable Tray Material Approval Rev 1 7 18-Aug-14 25-Aug-14
Material PO's 30 10-Sep-14 15-Oct-14
Light Current Cable Tray Material PO 25 10-Sep-14 15-Oct-14
Material Delivery at Site 40 16-Oct-14 01-Dec-14
Light Current Cable Tray Material Delivery 40 16-Oct-14 01-Dec-14
S
Structured Cabling system 173 22-Oct-14 14-May-15
Material Submittal 71 22-Oct-14 14-Jan-15
Rev 0 33 22-Oct-14 30-Nov-14
Structured Cabling System Material Submittal Rev 0 20 22-Oct-14 19-Nov-14
Structured Cabling Wiring Material Submittal Rev 0 20 02-Nov-14 30-Nov-14
Rev 1 32 07-Dec-14 14-Jan-15
Structured Cabling System Material Submittal Rev 1 20 07-Dec-14 01-Jan-15
Structured Cabling Wiring Material Submittal Rev 1 20 16-Dec-14 14-Jan-15
Material Approvals 54 19-Nov-14 22-Jan-15
Rev 0 23 19-Nov-14 16-Dec-14
Structured Cabling System Material Reply Rev 0 14 19-Nov-14 06-Dec-14
Structured Cabling Wiring Material Reply Rev 0 14 30-Nov-14 16-Dec-14
Rev 1 16 03-Jan-15 22-Jan-15
Structured Cabling System Material Approval Rev 1 7 03-Jan-15 11-Jan-15
Structured Cabling Wiring Material Approval Rev 1 7 14-Jan-15 22-Jan-15
Material PO's 44 22-Jan-15 15-Mar-15
Structured Cabling Wiring Material PO 25 22-Jan-15 01-Mar-15
Structured Cabling System Material PO 25 09-Feb-15 15-Mar-15
Material Delivery at Site 63 02-Mar-15 14-May-15
Structured Cabling Wiring Material Delivery 26 02-Mar-15 01-Apr-15
Structured Cabling System Material Delivery 50 17-Mar-15 14-May-15
T
Telephone system for Residential Building 213 03-Sep-14 14-May-15
Material Submittal 76 03-Sep-14 02-Dec-14
Jun Jul Aug Sep Oct Nov Dec
Qtr 3 Qtr 4
2014
SECON Nile Tower Project MEP Base Line Secon Nile Tower Project Siemens Scope 21-Mar-16 17:20
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 69 of 1076 TASK filter: All Activities
© Primavera Systems, Inc
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final

More Related Content

Similar to SeconTowers MEP Time Schedule final

12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...
12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...
12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...Rodger McKinley
 
HSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activityHSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activityRoumik Mukherjee
 
OHL1.pdf ejehejeur iurrrj iiuj4j4i4 jrj4
OHL1.pdf ejehejeur iurrrj iiuj4j4i4 jrj4OHL1.pdf ejehejeur iurrrj iiuj4j4i4 jrj4
OHL1.pdf ejehejeur iurrrj iiuj4j4i4 jrj4AhmedSaidGhonemy
 
Nbourdier-lab2-gantt chart with activities-
Nbourdier-lab2-gantt chart with activities-Nbourdier-lab2-gantt chart with activities-
Nbourdier-lab2-gantt chart with activities-Nixzalis Bourdier
 
CICPA Updated Schedule Dtd 130816
CICPA Updated Schedule Dtd 130816CICPA Updated Schedule Dtd 130816
CICPA Updated Schedule Dtd 130816Manish Shah
 
ICOM Schedule & Logistics (1)
ICOM Schedule & Logistics (1)ICOM Schedule & Logistics (1)
ICOM Schedule & Logistics (1)Jamal Nelson, CCM
 
Mechanical Engineering Seminar 2017_2
Mechanical Engineering Seminar 2017_2Mechanical Engineering Seminar 2017_2
Mechanical Engineering Seminar 2017_2Nicholas Naing
 
Torkham Project Work Plan (18-Apr-2019).pdf
Torkham Project Work Plan (18-Apr-2019).pdfTorkham Project Work Plan (18-Apr-2019).pdf
Torkham Project Work Plan (18-Apr-2019).pdfSajidMumtazGurmani
 
Document Transmittal form of a construction
Document Transmittal form of a constructionDocument Transmittal form of a construction
Document Transmittal form of a constructionZumraOzdemir
 
Section 1 SSP NRY Open Item Slide 27 July 2023.pptx
Section 1 SSP NRY Open Item Slide 27 July 2023.pptxSection 1 SSP NRY Open Item Slide 27 July 2023.pptx
Section 1 SSP NRY Open Item Slide 27 July 2023.pptxAisyahAdha1
 
23. CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)
23.  CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)23.  CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)
23. CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)hepemod733
 
Activities - Presentation (NESPAK) v1.6
Activities - Presentation (NESPAK) v1.6Activities - Presentation (NESPAK) v1.6
Activities - Presentation (NESPAK) v1.6MUHAMMAD SALEEM
 
Project Review Meeting - 14.02.23.ppt
Project Review Meeting - 14.02.23.pptProject Review Meeting - 14.02.23.ppt
Project Review Meeting - 14.02.23.pptAkdDeshmukh
 

Similar to SeconTowers MEP Time Schedule final (20)

12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...
12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...
12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...
 
HSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activityHSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activity
 
aaa.pptx
aaa.pptxaaa.pptx
aaa.pptx
 
OHL1.pdf ejehejeur iurrrj iiuj4j4i4 jrj4
OHL1.pdf ejehejeur iurrrj iiuj4j4i4 jrj4OHL1.pdf ejehejeur iurrrj iiuj4j4i4 jrj4
OHL1.pdf ejehejeur iurrrj iiuj4j4i4 jrj4
 
01. P269 - Project Implementation Programme - Rev 00
01. P269 - Project Implementation Programme -  Rev 0001. P269 - Project Implementation Programme -  Rev 00
01. P269 - Project Implementation Programme - Rev 00
 
Nbourdier-lab2-gantt chart with activities-
Nbourdier-lab2-gantt chart with activities-Nbourdier-lab2-gantt chart with activities-
Nbourdier-lab2-gantt chart with activities-
 
Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13
 
CICPA Updated Schedule Dtd 130816
CICPA Updated Schedule Dtd 130816CICPA Updated Schedule Dtd 130816
CICPA Updated Schedule Dtd 130816
 
Monthly Progress Report No.13 - September 2011
Monthly Progress Report No.13 - September 2011Monthly Progress Report No.13 - September 2011
Monthly Progress Report No.13 - September 2011
 
ICOM Schedule & Logistics (1)
ICOM Schedule & Logistics (1)ICOM Schedule & Logistics (1)
ICOM Schedule & Logistics (1)
 
Mechanical Engineering Seminar 2017_2
Mechanical Engineering Seminar 2017_2Mechanical Engineering Seminar 2017_2
Mechanical Engineering Seminar 2017_2
 
Torkham Project Work Plan (18-Apr-2019).pdf
Torkham Project Work Plan (18-Apr-2019).pdfTorkham Project Work Plan (18-Apr-2019).pdf
Torkham Project Work Plan (18-Apr-2019).pdf
 
Document Transmittal form of a construction
Document Transmittal form of a constructionDocument Transmittal form of a construction
Document Transmittal form of a construction
 
ARB JANADREA 25.01.16 UPDATE PM
ARB JANADREA 25.01.16 UPDATE  PMARB JANADREA 25.01.16 UPDATE  PM
ARB JANADREA 25.01.16 UPDATE PM
 
Project Schedule - Level IV Schedule
Project Schedule - Level IV ScheduleProject Schedule - Level IV Schedule
Project Schedule - Level IV Schedule
 
Section 1 SSP NRY Open Item Slide 27 July 2023.pptx
Section 1 SSP NRY Open Item Slide 27 July 2023.pptxSection 1 SSP NRY Open Item Slide 27 July 2023.pptx
Section 1 SSP NRY Open Item Slide 27 July 2023.pptx
 
MICC Acquisition Forecast
MICC Acquisition ForecastMICC Acquisition Forecast
MICC Acquisition Forecast
 
23. CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)
23.  CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)23.  CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)
23. CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)
 
Activities - Presentation (NESPAK) v1.6
Activities - Presentation (NESPAK) v1.6Activities - Presentation (NESPAK) v1.6
Activities - Presentation (NESPAK) v1.6
 
Project Review Meeting - 14.02.23.ppt
Project Review Meeting - 14.02.23.pptProject Review Meeting - 14.02.23.ppt
Project Review Meeting - 14.02.23.ppt
 

More from Ahmed Mehrem

020614_letter for Ahmed Mehrem Recommendation letter.pdf
020614_letter for Ahmed Mehrem Recommendation letter.pdf020614_letter for Ahmed Mehrem Recommendation letter.pdf
020614_letter for Ahmed Mehrem Recommendation letter.pdfAhmed Mehrem
 
Al aziza jotun products and services 2019 qr
Al aziza jotun products and services 2019 qrAl aziza jotun products and services 2019 qr
Al aziza jotun products and services 2019 qrAhmed Mehrem
 
Al-Aziza for paints and decoration Ahmed Mehrem business card 2
Al-Aziza for paints and decoration Ahmed Mehrem business card 2Al-Aziza for paints and decoration Ahmed Mehrem business card 2
Al-Aziza for paints and decoration Ahmed Mehrem business card 2Ahmed Mehrem
 
Al-Aziza For Paints Ahmed Mehrem business card
Al-Aziza For Paints Ahmed Mehrem business card Al-Aziza For Paints Ahmed Mehrem business card
Al-Aziza For Paints Ahmed Mehrem business card Ahmed Mehrem
 
Mtwara power plant 2007
Mtwara power plant 2007Mtwara power plant 2007
Mtwara power plant 2007Ahmed Mehrem
 
Admin Building For Sphinx Glass Factory In Sadat
Admin Building For Sphinx Glass Factory In SadatAdmin Building For Sphinx Glass Factory In Sadat
Admin Building For Sphinx Glass Factory In SadatAhmed Mehrem
 
Sphinx Glass Factory comp 1-1
Sphinx Glass Factory comp 1-1Sphinx Glass Factory comp 1-1
Sphinx Glass Factory comp 1-1Ahmed Mehrem
 

More from Ahmed Mehrem (10)

020614_letter for Ahmed Mehrem Recommendation letter.pdf
020614_letter for Ahmed Mehrem Recommendation letter.pdf020614_letter for Ahmed Mehrem Recommendation letter.pdf
020614_letter for Ahmed Mehrem Recommendation letter.pdf
 
Al aziza jotun products and services 2019 qr
Al aziza jotun products and services 2019 qrAl aziza jotun products and services 2019 qr
Al aziza jotun products and services 2019 qr
 
Al-Aziza for paints and decoration Ahmed Mehrem business card 2
Al-Aziza for paints and decoration Ahmed Mehrem business card 2Al-Aziza for paints and decoration Ahmed Mehrem business card 2
Al-Aziza for paints and decoration Ahmed Mehrem business card 2
 
Al-Aziza For Paints Ahmed Mehrem business card
Al-Aziza For Paints Ahmed Mehrem business card Al-Aziza For Paints Ahmed Mehrem business card
Al-Aziza For Paints Ahmed Mehrem business card
 
For Our Mothers
For Our MothersFor Our Mothers
For Our Mothers
 
Majarrah data
Majarrah dataMajarrah data
Majarrah data
 
001
001001
001
 
Mtwara power plant 2007
Mtwara power plant 2007Mtwara power plant 2007
Mtwara power plant 2007
 
Admin Building For Sphinx Glass Factory In Sadat
Admin Building For Sphinx Glass Factory In SadatAdmin Building For Sphinx Glass Factory In Sadat
Admin Building For Sphinx Glass Factory In Sadat
 
Sphinx Glass Factory comp 1-1
Sphinx Glass Factory comp 1-1Sphinx Glass Factory comp 1-1
Sphinx Glass Factory comp 1-1
 

Recently uploaded

Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 

Recently uploaded (20)

Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 

SeconTowers MEP Time Schedule final

  • 1. Activity ID Activity Name Original Duration Start Finish SECO SECON Nile Tower Project MEP Base Line 549 08-Jul-14 26-Apr-16 Gene General 549 08-Jul-14 26-Apr-16 SSG10 Letter Of Award (L.O.A) 0 08-Jul-14 SSG20 Advanced Payment 0 14-Jul-14 SSG30 Mobilization at Site 26 14-Jul-14 13-Aug-14 SSG70 Permanent Source For Water Supply (By Others) 0 08-Oct-15 SSG50 Permanent Source For Electricity (By Others) 0 29-Nov-15 SSG60 Permanent Source For Telephone & Data and Active Switch (By Others) 0 29-Nov-15 SSG18 Testing & Commissioning and Start-Up 78 23-Jan-16 24-Apr-16 SSG20 Taking Over Certificate (T.O.C) 0 26-Apr-16 Engin Engineering 375 08-Jul-14 28-Sep-15 Floo Floors 375 08-Jul-14 28-Sep-15 Lo Lower Basement B2 Shop Drawings 75 08-Jul-14 04-Oct-14 SS Receive Lower Basement MEP Design Package 0 08-Jul-14 SS Receive Lower Basement Approved Architecture Design Package 0 08-Jul-14 SS Receive Lower Basement Approved Structural Design Package 0 08-Jul-14 SS Receive Lower Basement Approved Architecture Shop Drawings 0 14-Jul-14 E Electrical Systems Shop Drawings 38 13-Jul-14 27-Aug-14 Lighting System Shop Drawings 33 13-Jul-14 21-Aug-14 Lighting System Parking Floor Plan ( B-2 ) Rev 0 Submittal 5 13-Jul-14 20-Jul-14 Lighting System Parking Floor Plan ( B-2 ) Rev 0 Reply 14 20-Jul-14 06-Aug-14 Lighting System Parking Floor Plan ( B-2 ) Rev 1 Submittal 5 06-Aug-14 13-Aug-14 Lighting System Parking Floor Plan ( B-2 ) Rev 1 Approval 7 13-Aug-14 21-Aug-14 Power System Shop Drawings 33 15-Jul-14 23-Aug-14 Power System Parking Floor Plan ( B-2 ) Rev 0 Submittal 5 15-Jul-14 22-Jul-14 Power System Parking Floor Plan ( B-2 ) Rev 0 Reply 14 22-Jul-14 09-Aug-14 Power System Parking Floor Plan ( B-2 ) Rev 1 Submittal 5 10-Aug-14 14-Aug-14 Power System Parking Floor Plan ( B-2 ) Rev 1 Approval 7 16-Aug-14 23-Aug-14 Safety Lighting System Shop Drawings 34 17-Jul-14 27-Aug-14 Safety Lighting System Parking Floor Plan ( B-2 ) Rev 0 Submittal 5 17-Jul-14 27-Jul-14 Safety Lighting System Parking Floor Plan ( B-2 ) Rev 0 Reply 14 27-Jul-14 12-Aug-14 Safety Lighting System Parking Floor Plan ( B-2 ) Rev 1 Submittal 5 12-Aug-14 19-Aug-14 Safety Lighting System Parking Floor Plan ( B-2 ) Rev 1 Approval 7 19-Aug-14 27-Aug-14 Low Current Systems Shop Drawings 33 13-Jul-14 21-Aug-14 Fire Alarm System 33 13-Jul-14 21-Aug-14 Fire Alarm System Parking Floor Plan ( B-2 ) Rev 0 Submittal 5 13-Jul-14 20-Jul-14 Jun Jul Aug Sep Oct Nov Dec Qtr 3 Qtr 4 2014 SECON Nile Tower Project MEP Base Line Secon Nile Tower Project Siemens Scope 21-Mar-16 17:19 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 1 of 1076 TASK filter: All Activities © Primavera Systems, Inc
  • 2. Activity ID Activity Name Original Duration Start Finish Fire Alarm System Parking Floor Plan ( B-2 ) Rev 0 Reply 14 20-Jul-14 06-Aug-14 Fire Alarm System Parking Floor Plan ( B-2 ) Rev 1 Submittal 5 06-Aug-14 13-Aug-14 Fire Alarm System Parking Floor Plan ( B-2 ) Rev 1 Approval 7 13-Aug-14 21-Aug-14 Sound & Security systems 33 13-Jul-14 21-Aug-14 Sound & Security Systems Parking Floor Plan ( B-2 ) Rev 0 Submittal 5 13-Jul-14 20-Jul-14 Sound & Security Systems Parking Floor Plan ( B-2 ) Rev 0 Reply 14 20-Jul-14 06-Aug-14 Sound & Security Systems Parking Floor Plan ( B-2 ) Rev 1 Submittal 5 06-Aug-14 13-Aug-14 Sound & Security Systems Parking Floor Plan ( B-2 ) Rev 1 Approval 7 13-Aug-14 21-Aug-14 Voice,Data,IPTV systems 33 13-Jul-14 21-Aug-14 Voice, Data, IPTV Systems Parking Floor Plan ( B-2 ) Rev 0 Submittal 5 13-Jul-14 20-Jul-14 Voice, Data, IPTV Systems Parking Floor Plan ( B-2 ) Rev 0 Reply 14 20-Jul-14 06-Aug-14 Voice, Data, IPTV Systems Parking Floor Plan ( B-2 ) Rev 1 Submittal 5 06-Aug-14 13-Aug-14 Voice, Data, IPTV Systems Parking Floor Plan ( B-2 ) Rev 1 Approval 7 13-Aug-14 21-Aug-14 M Mechanical Systems Shop Drawings 35 13-Jul-14 23-Aug-14 HVAC System Shop Drawings 33 13-Jul-14 21-Aug-14 HVAC System Parking Floor Plan ( B-2 ) Rev 0 Submittal 5 13-Jul-14 20-Jul-14 HVAC System Parking Floor Plan ( B-2 ) Rev 0 Reply 14 20-Jul-14 06-Aug-14 HVAC System Parking Floor Plan ( B-2 ) Rev 1 Submittal 5 06-Aug-14 13-Aug-14 HVAC System Parking Floor Plan ( B-2 ) Rev 1 Approval 7 13-Aug-14 21-Aug-14 Fire Fighting System Shop Drawings 33 13-Jul-14 21-Aug-14 Fire Fighting System Parking Floor Plan ( B-2 ) Rev 0 Submittal 5 13-Jul-14 20-Jul-14 Fire Fighting System Parking Floor Plan ( B-2 ) Rev 0 Reply 14 20-Jul-14 06-Aug-14 Fire Fighting System Parking Floor Plan ( B-2 ) Rev 1 Submittal 5 06-Aug-14 13-Aug-14 Fire Fighting System Parking Floor Plan ( B-2 ) Rev 1 Approval 7 13-Aug-14 21-Aug-14 Plumbing System Shop Drawings 35 13-Jul-14 23-Aug-14 Water Supply System Parking Floor Plan ( B-2 ) Rev 0 Submittal 5 13-Jul-14 20-Jul-14 Drainage System Parking Floor Plan ( B-2 ) Rev 0 Submittal 5 15-Jul-14 22-Jul-14 Water Supply System Parking Floor Plan ( B-2 ) Rev 0 Reply 14 20-Jul-14 06-Aug-14 Drainage System Parking Floor Plan ( B-2 ) Rev 0 Reply 14 22-Jul-14 09-Aug-14 Water Supply System Parking Floor Plan ( B-2 ) Rev 1 Submittal 5 06-Aug-14 13-Aug-14 Drainage System Parking Floor Plan ( B-2 ) Rev 1 Submittal 5 10-Aug-14 14-Aug-14 Water Supply System Parking Floor Plan ( B-2 ) Rev 1 Approval 7 13-Aug-14 21-Aug-14 Drainage System Parking Floor Plan ( B-2 ) Rev 1 Approval 7 16-Aug-14 23-Aug-14 C Composite Shop Drawings 33 27-Aug-14 04-Oct-14 Composite Drawing for Lower Basement ( B-2 ) Rev 0 Submittal 5 27-Aug-14 03-Sep-14 Composite Drawing for Lower Basement ( B-2 ) Rev 0 Reply 14 03-Sep-14 20-Sep-14 Composite Drawing for Lower Basement ( B-2 ) Rev 1 Submittal 5 21-Sep-14 25-Sep-14 Composite Drawing for Lower Basement ( B-2 ) Rev 1 Approval 7 27-Sep-14 04-Oct-14 Jun Jul Aug Sep Oct Nov Dec Qtr 3 Qtr 4 2014 SECON Nile Tower Project MEP Base Line Secon Nile Tower Project Siemens Scope 21-Mar-16 17:19 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 3 of 1076 TASK filter: All Activities © Primavera Systems, Inc
  • 3. Activity ID Activity Name Original Duration Start Finish Up Upper Basement B1 Shop Drawings 99 08-Jul-14 03-Nov-14 SS Receive Upper Basement MEP Design Package 0 08-Jul-14 SS Receive Upper Basement Approved Architecture Design Package 0 04-Aug-14 SS Receive Upper Basement Approved Structural Design Package 0 04-Aug-14 SS Receive Upper Basement Approved Architecture Shop Drawings 0 10-Aug-14 E Electrical Systems Shop Drawings 37 10-Aug-14 22-Sep-14 Lighting System Shop Drawings 33 10-Aug-14 17-Sep-14 Lighting System Parking Floor Plan ( B-1 ) Rev 0 Submittal 5 10-Aug-14 17-Aug-14 Lighting System Parking Floor Plan ( B-1 ) Rev 0 Reply 14 17-Aug-14 02-Sep-14 Lighting System Parking Floor Plan ( B-1 ) Rev 1 Submittal 5 02-Sep-14 09-Sep-14 Lighting System Parking Floor Plan ( B-1 ) Rev 1 Approval 7 09-Sep-14 17-Sep-14 Power System Shop Drawings 33 12-Aug-14 20-Sep-14 Power System Parking Floor Plan ( B-1 ) Rev 0 Submittal 5 12-Aug-14 19-Aug-14 Power System Parking Floor Plan ( B-1 ) Rev 0 Reply 14 19-Aug-14 04-Sep-14 Power System Parking Floor Plan ( B-1 ) Rev 1 Submittal 5 04-Sep-14 11-Sep-14 Power System Parking Floor Plan ( B-1 ) Rev 1 Approval 7 11-Sep-14 20-Sep-14 Safety Lighting System Shop Drawings 33 14-Aug-14 22-Sep-14 Safety Lighting System Parking Floor Plan ( B-1 ) Rev 0 Submittal 5 14-Aug-14 21-Aug-14 Safety Lighting System Parking Floor Plan ( B-1 ) Rev 0 Reply 14 21-Aug-14 07-Sep-14 Safety Lighting System Parking Floor Plan ( B-1 ) Rev 1 Submittal 5 07-Sep-14 14-Sep-14 Safety Lighting System Parking Floor Plan ( B-1 ) Rev 1 Approval 7 14-Sep-14 22-Sep-14 Low Current Systems Shop Drawings 33 10-Aug-14 17-Sep-14 Fire Alarm System 33 10-Aug-14 17-Sep-14 Fire Alarm System Parking Floor Plan ( B-1 ) Rev 0 Submittal 5 10-Aug-14 17-Aug-14 Fire Alarm System Parking Floor Plan ( B-1 ) Rev 0 Reply 14 17-Aug-14 02-Sep-14 Fire Alarm System Parking Floor Plan ( B-1 ) Rev 1 Submittal 5 02-Sep-14 09-Sep-14 Fire Alarm System Parking Floor Plan ( B-1 ) Rev 1 Approval 7 09-Sep-14 17-Sep-14 Sound & Security systems 33 10-Aug-14 17-Sep-14 Sound & Security Systems Parking Floor Plan ( B-1 ) Rev 0 Submittal 5 10-Aug-14 17-Aug-14 Sound & Security Systems Parking Floor Plan ( B-1 ) Rev 0 Reply 14 17-Aug-14 02-Sep-14 Sound & Security Systems Parking Floor Plan ( B-1 ) Rev 1 Submittal 5 02-Sep-14 09-Sep-14 Sound & Security Systems Parking Floor Plan ( B-1 ) Rev 1 Approval 7 09-Sep-14 17-Sep-14 Voice,Data,IPTV systems 33 10-Aug-14 17-Sep-14 Voice, Data, IPTV Systems Parking Floor Plan ( B-1 ) Rev 0 Submittal 5 10-Aug-14 17-Aug-14 Voice, Data, IPTV Systems Parking Floor Plan ( B-1 ) Rev 0 Reply 14 17-Aug-14 02-Sep-14 Voice, Data, IPTV Systems Parking Floor Plan ( B-1 ) Rev 1 Submittal 5 02-Sep-14 09-Sep-14 Voice, Data, IPTV Systems Parking Floor Plan ( B-1 ) Rev 1 Approval 7 09-Sep-14 17-Sep-14 M Mechanical Systems Shop Drawings 39 10-Aug-14 24-Sep-14 Jun Jul Aug Sep Oct Nov Dec Qtr 3 Qtr 4 2014 SECON Nile Tower Project MEP Base Line Secon Nile Tower Project Siemens Scope 21-Mar-16 17:19 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 5 of 1076 TASK filter: All Activities © Primavera Systems, Inc
  • 4. Activity ID Activity Name Original Duration Start Finish HVAC System Shop Drawings 33 10-Aug-14 17-Sep-14 HVAC System Parking Floor Plan ( B-1 ) Rev 0 Submittal 5 10-Aug-14 17-Aug-14 HVAC System Parking Floor Plan ( B-1 ) Rev 0 Reply 14 17-Aug-14 02-Sep-14 HVAC System Parking Floor Plan ( B-1 ) Rev 1 Submittal 5 02-Sep-14 09-Sep-14 HVAC System Parking Floor Plan ( B-1 ) Rev 1 Approval 7 09-Sep-14 17-Sep-14 Fire Fighting System Shop Drawings 33 10-Aug-14 17-Sep-14 Fire Fighting System Parking Floor Plan ( B-1 ) Rev 0 Submittal 5 10-Aug-14 17-Aug-14 Fire Fighting System Parking Floor Plan ( B-1 ) Rev 0 Reply 14 17-Aug-14 02-Sep-14 Fire Fighting System Parking Floor Plan ( B-1 ) Rev 1 Submittal 5 02-Sep-14 09-Sep-14 Fire Fighting System Parking Floor Plan ( B-1 ) Rev 1 Approval 7 09-Sep-14 17-Sep-14 Plumbing System Shop Drawings 36 13-Aug-14 24-Sep-14 Water Supply System Parking Floor Plan ( B-1 ) Rev 0 Submittal 5 13-Aug-14 20-Aug-14 Drainage System Parking Floor Plan ( B-1 ) Rev 0 Submittal 5 17-Aug-14 24-Aug-14 Water Supply System Parking Floor Plan ( B-1 ) Rev 0 Reply 14 20-Aug-14 06-Sep-14 Drainage System Parking Floor Plan ( B-1 ) Rev 0 Reply 14 24-Aug-14 09-Sep-14 Water Supply System Parking Floor Plan ( B-1 ) Rev 1 Submittal 5 07-Sep-14 11-Sep-14 Drainage System Parking Floor Plan ( B-1 ) Rev 1 Submittal 5 09-Sep-14 16-Sep-14 Water Supply System Parking Floor Plan ( B-1 ) Rev 1 Approval 7 13-Sep-14 20-Sep-14 Drainage System Parking Floor Plan ( B-1 ) Rev 1 Approval 7 16-Sep-14 24-Sep-14 C Composite Shop Drawings 33 24-Sep-14 03-Nov-14 Composite Drawing for Upper Basement ( B-1 ) Rev 0 Submittal 5 24-Sep-14 01-Oct-14 Composite Drawing for Upper Basement ( B-1 ) Rev 0 Reply 14 01-Oct-14 19-Oct-14 Composite Drawing for Upper Basement ( B-1 ) Rev 1 Submittal 5 19-Oct-14 26-Oct-14 Composite Drawing for Upper Basement ( B-1 ) Rev 1 Approval 7 26-Oct-14 03-Nov-14 Lo Lower Ground (BOH) Shop Drawings 168 08-Jul-14 24-Jan-15 SS Receive Lower Ground MEP Design Package 0 08-Jul-14 SS Receive Lower Ground Approved Architecture Design Package 0 30-Aug-14 SS Receive Lower Ground Approved Structural Design Package 0 30-Aug-14 SS Receive Lower Ground Approved Architecture Shop Drawings 0 04-Sep-14 SS Receive Lower Ground Approved Tiles Shop Drawings 0 25-Sep-14 E Electrical Systems Shop Drawings 41 04-Sep-14 23-Oct-14 Lighting System Shop Drawings 33 04-Sep-14 14-Oct-14 Lighting System Lower Ground Floor Plan ( BOH ) Rev 0 Submittal 5 04-Sep-14 11-Sep-14 Lighting System Lower Ground Floor Plan ( BOH ) Rev 0 Reply 14 11-Sep-14 28-Sep-14 Lighting System Lower Ground Floor Plan ( BOH ) Rev 1 Submittal 5 28-Sep-14 05-Oct-14 Lighting System Lower Ground Floor Plan ( BOH ) Rev 1 Approval 7 05-Oct-14 14-Oct-14 Power System Shop Drawings 33 08-Sep-14 18-Oct-14 Power System Lower Ground Floor Plan ( BOH ) Rev 0 Submittal 5 08-Sep-14 15-Sep-14 Jun Jul Aug Sep Oct Nov Dec Qtr 3 Qtr 4 2014 SECON Nile Tower Project MEP Base Line Secon Nile Tower Project Siemens Scope 21-Mar-16 17:19 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 7 of 1076 TASK filter: All Activities © Primavera Systems, Inc
  • 5. Activity ID Activity Name Original Duration Start Finish Power System Lower Ground Floor Plan ( BOH ) Rev 0 Reply 14 15-Sep-14 01-Oct-14 Power System Lower Ground Floor Plan ( BOH ) Rev 1 Submittal 5 01-Oct-14 09-Oct-14 Power System Lower Ground Floor Plan ( BOH ) Rev 1 Approval 7 09-Oct-14 18-Oct-14 Safety Lighting System Shop Drawings 33 14-Sep-14 23-Oct-14 Safety Lighting System Lower Ground Floor Plan ( BOH ) Rev 0 Submittal 5 14-Sep-14 21-Sep-14 Safety Lighting System Lower Ground Floor Plan ( BOH ) Rev 0 Reply 14 21-Sep-14 08-Oct-14 Safety Lighting System Lower Ground Floor Plan ( BOH ) Rev 1 Submittal 5 08-Oct-14 15-Oct-14 Safety Lighting System Lower Ground Floor Plan ( BOH ) Rev 1 Approval 7 15-Oct-14 23-Oct-14 Low Current Systems Shop Drawings 33 04-Sep-14 14-Oct-14 Fire Alarm System 33 04-Sep-14 14-Oct-14 Fire Alarm System Lower Ground Floor Plan ( BOH ) Rev 0 Submittal 5 04-Sep-14 11-Sep-14 Fire Alarm System Lower Ground Floor Plan ( BOH ) Rev 0 Reply 14 11-Sep-14 28-Sep-14 Fire Alarm System Lower Ground Floor Plan ( BOH ) Rev 1 Submittal 5 28-Sep-14 05-Oct-14 Fire Alarm System Lower Ground Floor Plan ( BOH ) Rev 1 Approval 7 05-Oct-14 14-Oct-14 Sound & Security systems 33 04-Sep-14 14-Oct-14 Sound & Security Systems Lower Ground Floor Plan ( BOH ) Rev 0 Submittal 5 04-Sep-14 11-Sep-14 Sound & Security Systems Lower Ground Floor Plan ( BOH ) Rev 0 Reply 14 11-Sep-14 28-Sep-14 Sound & Security Systems Lower Ground Floor Plan ( BOH ) Rev 1 Submittal 5 28-Sep-14 05-Oct-14 Sound & Security Systems Lower Ground Floor Plan ( BOH ) Rev 1 Approval 7 05-Oct-14 14-Oct-14 Voice,Data,IPTV systems 33 04-Sep-14 14-Oct-14 Voice, Data, IPTV Systems Lower Ground Floor Plan ( BOH ) Rev 0 Submittal 5 04-Sep-14 11-Sep-14 Voice, Data, IPTV Systems Lower Ground Floor Plan ( BOH ) Rev 0 Reply 14 11-Sep-14 28-Sep-14 Voice, Data, IPTV Systems Lower Ground Floor Plan ( BOH ) Rev 1 Submittal 5 28-Sep-14 05-Oct-14 Voice, Data, IPTV Systems Lower Ground Floor Plan ( BOH ) Rev 1 Approval 7 05-Oct-14 14-Oct-14 M Mechanical Systems Shop Drawings 86 04-Sep-14 15-Dec-14 HVAC System Shop Drawings 33 04-Sep-14 14-Oct-14 HVAC System Lower Ground Floor Plan ( BOH ) Rev 0 Submittal 5 04-Sep-14 11-Sep-14 HVAC System Lower Ground Floor Plan ( BOH ) Rev 0 Reply 14 11-Sep-14 28-Sep-14 HVAC System Lower Ground Floor Plan ( BOH ) Rev 1 Submittal 5 28-Sep-14 05-Oct-14 HVAC System Lower Ground Floor Plan ( BOH ) Rev 1 Approval 7 05-Oct-14 14-Oct-14 Fire Fighting System Shop Drawings 33 04-Sep-14 14-Oct-14 Fire Fighting System Lower Ground Floor Plan ( BOH ) Rev 0 Submittal 5 04-Sep-14 11-Sep-14 Fire Fighting System Lower Ground Floor Plan ( BOH ) Rev 0 Reply 14 11-Sep-14 28-Sep-14 Fire Fighting System Lower Ground Floor Plan ( BOH ) Rev 1 Submittal 5 28-Sep-14 05-Oct-14 Fire Fighting System Lower Ground Floor Plan ( BOH ) Rev 1 Approval 7 05-Oct-14 14-Oct-14 Plumbing System Shop Drawings 68 25-Sep-14 15-Dec-14 Toilet Details Types (T 28, T 29) Submittal Rev 0 5 25-Sep-14 02-Oct-14 Toilet Details Types (T 28, T 29) Reply Rev 0 14 02-Oct-14 20-Oct-14 Jun Jul Aug Sep Oct Nov Dec Qtr 3 Qtr 4 2014 SECON Nile Tower Project MEP Base Line Secon Nile Tower Project Siemens Scope 21-Mar-16 17:19 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 9 of 1076 TASK filter: All Activities © Primavera Systems, Inc
  • 6. Activity ID Activity Name Original Duration Start Finish Toilet Details Types (T 28, T 29) Submittal Rev 1 5 20-Oct-14 27-Oct-14 Toilet Details Types (T 28, T 29) Approval Rev 1 7 27-Oct-14 04-Nov-14 Water Supply System Lower Ground Floor Plan ( BOH ) Rev 0 Submittal 5 04-Nov-14 11-Nov-14 Drainage System Lower Ground Floor Plan ( BOH ) Rev 0 Submittal 5 06-Nov-14 13-Nov-14 Water Supply System Lower Ground Floor Plan ( BOH ) Rev 0 Reply 14 11-Nov-14 27-Nov-14 Drainage System Lower Ground Floor Plan ( BOH ) Rev 0 Reply 14 13-Nov-14 30-Nov-14 Water Supply System Lower Ground Floor Plan ( BOH ) Rev 1 Submittal 5 27-Nov-14 04-Dec-14 Drainage System Lower Ground Floor Plan ( BOH ) Rev 1 Submittal 5 30-Nov-14 07-Dec-14 Water Supply System Lower Ground Floor Plan ( BOH ) Rev 1 Approval 7 04-Dec-14 13-Dec-14 Drainage System Lower Ground Floor Plan ( BOH ) Rev 1 Approval 7 07-Dec-14 15-Dec-14 C Composite Shop Drawings 33 15-Dec-14 24-Jan-15 Composite Drawing for Lower Ground Floor Plan ( BOH ) Rev 0 Submittal 5 15-Dec-14 22-Dec-14 Composite Drawing for Lower Ground Floor Plan ( BOH ) Rev 0 Reply 14 22-Dec-14 08-Jan-15 Composite Drawing for Lower Ground Floor Plan ( BOH ) Rev 1 Submittal 5 08-Jan-15 15-Jan-15 Composite Drawing for Lower Ground Floor Plan ( BOH ) Rev 1 Approval 7 15-Jan-15 24-Jan-15 Gr Ground Floor Shop Drawings 195 08-Jul-14 24-Feb-15 SS Receive Ground Floor MEP Design Package 0 08-Jul-14 SS Receive Ground Floor Approved Architecture Design Package 0 24-Sep-14 SS Receive Ground Floor Approved Structural Design Package 0 24-Sep-14 SS Receive Ground Floor Approved Architecture Shop Drawings 0 30-Sep-14 SS Receive Ground Approved Tiles Shop Drawings 0 22-Oct-14 E Electrical Systems Shop Drawings 45 30-Sep-14 22-Nov-14 Lighting System Shop Drawings 33 30-Sep-14 08-Nov-14 Lighting System Ground Floor Plan Rev 0 Submittal 5 30-Sep-14 08-Oct-14 Lighting System Ground Floor Plan Rev 0 Reply 14 08-Oct-14 25-Oct-14 Lighting System Ground Floor Plan Rev 1 Submittal 5 26-Oct-14 30-Oct-14 Lighting System Ground Floor Plan Rev 1 Approval 7 01-Nov-14 08-Nov-14 Power System Shop Drawings 33 05-Oct-14 13-Nov-14 Power System Ground Floor Plan Rev 0 Submittal 5 05-Oct-14 13-Oct-14 Power System Ground Floor Plan Rev 0 Reply 14 13-Oct-14 29-Oct-14 Power System Ground Floor Plan Rev 1 Submittal 5 29-Oct-14 05-Nov-14 Power System Ground Floor Plan Rev 1 Approval 7 05-Nov-14 13-Nov-14 Safety Lighting System Shop Drawings 33 15-Oct-14 22-Nov-14 Safety Lighting System Ground Floor Plan Rev 0 Submittal 5 15-Oct-14 22-Oct-14 Safety Lighting System Ground Floor Plan Rev 0 Reply 14 22-Oct-14 08-Nov-14 Safety Lighting System Ground Floor Plan Rev 1 Submittal 5 09-Nov-14 13-Nov-14 Safety Lighting System Ground Floor Plan Rev 1 Approval 7 15-Nov-14 22-Nov-14 Low Current Systems Shop Drawings 33 30-Sep-14 08-Nov-14 Jun Jul Aug Sep Oct Nov Dec Qtr 3 Qtr 4 2014 SECON Nile Tower Project MEP Base Line Secon Nile Tower Project Siemens Scope 21-Mar-16 17:19 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 11 of 1076 TASK filter: All Activities © Primavera Systems, Inc
  • 7. Activity ID Activity Name Original Duration Start Finish Fire Alarm System 33 30-Sep-14 08-Nov-14 Fire Alarm System Ground Floor Plan Rev 0 Submittal 5 30-Sep-14 08-Oct-14 Fire Alarm System Ground Floor Plan Rev 0 Reply 14 08-Oct-14 25-Oct-14 Fire Alarm System Ground Floor Plan Rev 1 Submittal 5 26-Oct-14 30-Oct-14 Fire Alarm System Ground Floor Plan Rev 1 Approval 7 01-Nov-14 08-Nov-14 Sound & Security systems 33 30-Sep-14 08-Nov-14 Sound & Security Systems Ground Floor Plan Rev 0 Submittal 5 30-Sep-14 08-Oct-14 Sound & Security Systems Ground Floor Plan Rev 0 Reply 14 08-Oct-14 25-Oct-14 Sound & Security Systems Ground Floor Plan Rev 1 Submittal 5 26-Oct-14 30-Oct-14 Sound & Security Systems Ground Floor Plan Rev 1 Approval 7 01-Nov-14 08-Nov-14 Voice,Data,IPTV systems 33 30-Sep-14 08-Nov-14 Voice, Data, IPTV Systems Ground Floor Plan Rev 0 Submittal 5 30-Sep-14 08-Oct-14 Voice, Data, IPTV Systems Ground Floor Plan Rev 0 Reply 14 08-Oct-14 25-Oct-14 Voice, Data, IPTV Systems Ground Floor Plan Rev 1 Submittal 5 26-Oct-14 30-Oct-14 Voice, Data, IPTV Systems Ground Floor Plan Rev 1 Approval 7 01-Nov-14 08-Nov-14 M Mechanical Systems Shop Drawings 91 30-Sep-14 17-Jan-15 HVAC System Shop Drawings 33 30-Sep-14 08-Nov-14 HVAC System Ground Floor Plan Rev 0 Submittal 5 30-Sep-14 08-Oct-14 HVAC System Ground Floor Plan Rev 0 Reply 14 08-Oct-14 25-Oct-14 HVAC System Ground Floor Plan Rev 1 Submittal 5 26-Oct-14 30-Oct-14 HVAC System Ground Floor Plan Rev 1 Approval 7 01-Nov-14 08-Nov-14 Fire Fighting System Shop Drawings 33 30-Sep-14 08-Nov-14 Fire Fighting System Ground Floor Plan Rev 0 Submittal 5 30-Sep-14 08-Oct-14 Fire Fighting System Ground Floor Plan Rev 0 Reply 14 08-Oct-14 25-Oct-14 Fire Fighting System Ground Floor Plan Rev 1 Submittal 5 26-Oct-14 30-Oct-14 Fire Fighting System Ground Floor Plan Rev 1 Approval 7 01-Nov-14 08-Nov-14 Plumbing System Shop Drawings 69 27-Oct-14 17-Jan-15 Toilet Details Types (T10, T26 , T27, T31) Submittal Rev 0 5 27-Oct-14 03-Nov-14 Toilet Details Types (T10, T26 , T27, T31) Reply Rev 0 14 03-Nov-14 19-Nov-14 Toilet Details Types (T10, T26 , T27, T31) Submittal Rev 1 5 19-Nov-14 26-Nov-14 Toilet Details Types (T10, T26 , T27, T31) Approval Rev 1 7 26-Nov-14 04-Dec-14 Water Supply System Ground Floor Plan Rev 0 Submittal 5 04-Dec-14 11-Dec-14 Drainage System Ground Floor Plan Rev 0 Submittal 5 08-Dec-14 15-Dec-14 Water Supply System Ground Floor Plan Rev 0 Reply 14 11-Dec-14 28-Dec-14 Drainage System Ground Floor Plan Rev 0 Reply 14 15-Dec-14 31-Dec-14 Water Supply System Ground Floor Plan Rev 1 Submittal 5 28-Dec-14 04-Jan-15 Drainage System Ground Floor Plan Rev 1 Submittal 5 31-Dec-14 08-Jan-15 Water Supply System Ground Floor Plan Rev 1 Approval 7 04-Jan-15 13-Jan-15 Jun Jul Aug Sep Oct Nov Dec Qtr 3 Qtr 4 2014 SECON Nile Tower Project MEP Base Line Secon Nile Tower Project Siemens Scope 21-Mar-16 17:19 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 13 of 1076 TASK filter: All Activities © Primavera Systems, Inc
  • 8. Activity ID Activity Name Original Duration Start Finish Drainage System Ground Floor Plan Rev 1 Approval 7 08-Jan-15 17-Jan-15 C Composite Shop Drawings 32 18-Jan-15 24-Feb-15 Composite Drawing for Ground Floor Plan Rev 0 Submittal 5 18-Jan-15 22-Jan-15 Composite Drawing for Ground Floor Plan Rev 0 Reply 14 24-Jan-15 09-Feb-15 Composite Drawing for Ground Floor Plan Rev 1 Submittal 5 10-Feb-15 16-Feb-15 Composite Drawing for Ground Floor Plan Rev 1 Approval 7 17-Feb-15 24-Feb-15 Fir First Floor Shop Drawings 218 08-Jul-14 23-Mar-15 SS Receive First Floor MEP Design Package 0 08-Jul-14 SS Receive First Floor Approved Architecture Design Package 0 21-Oct-14 SS Receive First Floor Approved Structural Design Package 0 21-Oct-14 SS Receive First Floor Approved Architecture Shop Drawings 0 27-Oct-14 SS Receive First Floor Approved Tiles Shop Drawings 0 17-Nov-14 E Electrical Systems Shop Drawings 48 28-Oct-14 22-Dec-14 Lighting System Shop Drawings 33 28-Oct-14 04-Dec-14 Lighting System First Floor Plan Rev 0 Submittal 5 28-Oct-14 03-Nov-14 Lighting System First Floor Plan Rev 0 Reply 14 04-Nov-14 19-Nov-14 Lighting System First Floor Plan Rev 1 Submittal 5 20-Nov-14 26-Nov-14 Lighting System First Floor Plan Rev 1 Approval 7 27-Nov-14 04-Dec-14 Power System Shop Drawings 33 02-Nov-14 10-Dec-14 Power System First Floor Plan Rev 0 Submittal 5 02-Nov-14 09-Nov-14 Power System First Floor Plan Rev 0 Reply 14 09-Nov-14 25-Nov-14 Power System First Floor Plan Rev 1 Submittal 5 25-Nov-14 02-Dec-14 Power System First Floor Plan Rev 1 Approval 7 02-Dec-14 10-Dec-14 Safety Lighting System Shop Drawings 32 16-Nov-14 22-Dec-14 Safety Lighting System First Floor Plan Rev 0 Submittal 5 16-Nov-14 20-Nov-14 Safety Lighting System First Floor Plan Rev 0 Reply 14 22-Nov-14 07-Dec-14 Safety Lighting System First Floor Plan Rev 1 Submittal 5 08-Dec-14 14-Dec-14 Safety Lighting System First Floor Plan Rev 1 Approval 7 15-Dec-14 22-Dec-14 Low Current Systems Shop Drawings 33 28-Oct-14 04-Dec-14 Fire Alarm System 33 28-Oct-14 04-Dec-14 Fire Alarm System First Floor Plan Rev 0 Submittal 5 28-Oct-14 03-Nov-14 Fire Alarm System First Floor Plan Rev 0 Reply 14 04-Nov-14 19-Nov-14 Fire Alarm System First Floor Plan Rev 1 Submittal 5 20-Nov-14 26-Nov-14 Fire Alarm System First Floor Plan Rev 1 Approval 7 27-Nov-14 04-Dec-14 Sound & Security systems 33 28-Oct-14 04-Dec-14 Sound & Security Systems First Floor Plan Rev 0 Submittal 5 28-Oct-14 03-Nov-14 Sound & Security Systems First Floor Plan Rev 0 Reply 14 04-Nov-14 19-Nov-14 Sound & Security Systems First Floor Plan Rev 1 Submittal 5 20-Nov-14 26-Nov-14 Jun Jul Aug Sep Oct Nov Dec Qtr 3 Qtr 4 2014 SECON Nile Tower Project MEP Base Line Secon Nile Tower Project Siemens Scope 21-Mar-16 17:19 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 15 of 1076 TASK filter: All Activities © Primavera Systems, Inc
  • 9. Activity ID Activity Name Original Duration Start Finish Sound & Security Systems First Floor Plan Rev 1 Approval 7 27-Nov-14 04-Dec-14 Voice,Data,IPTV systems 33 28-Oct-14 04-Dec-14 Voice, Data, IPTV Systems First Floor Plan Rev 0 Submittal 5 28-Oct-14 03-Nov-14 Voice, Data, IPTV Systems First Floor Plan Rev 0 Reply 14 04-Nov-14 19-Nov-14 Voice, Data, IPTV Systems First Floor Plan Rev 1 Submittal 5 20-Nov-14 26-Nov-14 Voice, Data, IPTV Systems First Floor Plan Rev 1 Approval 7 27-Nov-14 04-Dec-14 M Mechanical Systems Shop Drawings 92 28-Oct-14 14-Feb-15 HVAC System Shop Drawings 33 28-Oct-14 04-Dec-14 HVAC System First Floor Plan Rev 0 Submittal 5 28-Oct-14 03-Nov-14 HVAC System First Floor Plan Rev 0 Reply 14 04-Nov-14 19-Nov-14 HVAC System First Floor Plan Rev 1 Submittal 5 20-Nov-14 26-Nov-14 HVAC System First Floor Plan Rev 1 Approval 7 27-Nov-14 04-Dec-14 Fire Fighting System Shop Drawings 33 28-Oct-14 04-Dec-14 Fire Fighting System First Floor Plan Rev 0 Submittal 5 28-Oct-14 03-Nov-14 Fire Fighting System First Floor Plan Rev 0 Reply 14 04-Nov-14 19-Nov-14 Fire Fighting System First Floor Plan Rev 1 Submittal 5 20-Nov-14 26-Nov-14 Fire Fighting System First Floor Plan Rev 1 Approval 7 27-Nov-14 04-Dec-14 Plumbing System Shop Drawings 67 26-Nov-14 14-Feb-15 Toilet Details Types (T1, T6 , T24, T25) Submittal Rev 0 5 26-Nov-14 03-Dec-14 Toilet Details Types (T1, T6 , T24, T25) Reply Rev 0 14 03-Dec-14 20-Dec-14 Toilet Details Types (T1, T6 , T24, T25) Submittal Rev 1 5 21-Dec-14 25-Dec-14 Toilet Details Types (T1, T6 , T24, T25) Approval Rev 1 7 27-Dec-14 03-Jan-15 Water Supply System First Floor Plan Rev 0 Submittal 5 04-Jan-15 11-Jan-15 Drainage System First Floor Plan Rev 0 Submittal 5 06-Jan-15 13-Jan-15 Water Supply System First Floor Plan Rev 0 Reply 14 12-Jan-15 28-Jan-15 Drainage System First Floor Plan Rev 0 Reply 14 14-Jan-15 31-Jan-15 Water Supply System First Floor Plan Rev 1 Submittal 5 29-Jan-15 04-Feb-15 Drainage System First Floor Plan Rev 1 Submittal 5 01-Feb-15 05-Feb-15 Water Supply System First Floor Plan Rev 1 Approval 7 05-Feb-15 12-Feb-15 Drainage System First Floor Plan Rev 1 Approval 7 07-Feb-15 14-Feb-15 C Composite Shop Drawings 32 15-Feb-15 23-Mar-15 Composite Drawing for First Floor Plan Rev 0 Submittal 5 15-Feb-15 19-Feb-15 Composite Drawing for First Floor Plan Rev 0 Reply 14 21-Feb-15 08-Mar-15 Composite Drawing for First Floor Plan Rev 1 Submittal 5 09-Mar-15 15-Mar-15 Composite Drawing for First Floor Plan Rev 1 Approval 7 16-Mar-15 23-Mar-15 Se Second Floor Shop Drawings 246 08-Jul-14 26-Apr-15 SS Receive Second Floor MEP Design Package 0 08-Jul-14 SS Receive Second Floor Approved Architecture Design Package 0 16-Nov-14 Jun Jul Aug Sep Oct Nov Dec Qtr 3 Qtr 4 2014 SECON Nile Tower Project MEP Base Line Secon Nile Tower Project Siemens Scope 21-Mar-16 17:19 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 17 of 1076 TASK filter: All Activities © Primavera Systems, Inc
  • 10. Activity ID Activity Name Original Duration Start Finish SS Receive Second Floor Approved Structural Design Package 0 16-Nov-14 SS Receive Second Floor Approved Architecture Shop Drawings 0 22-Nov-14 SS Receive Second Floor Approved Tiles Shop Drawings 0 13-Dec-14 E Electrical Systems Shop Drawings 51 24-Nov-14 22-Jan-15 Lighting System Shop Drawings 33 24-Nov-14 31-Dec-14 Lighting System Second Floor Plan Rev 0 Submittal 5 24-Nov-14 30-Nov-14 Lighting System Second Floor Plan Rev 0 Reply 14 01-Dec-14 16-Dec-14 Lighting System Second Floor Plan Rev 1 Submittal 5 17-Dec-14 23-Dec-14 Lighting System Second Floor Plan Rev 1 Approval 7 24-Dec-14 31-Dec-14 Power System Shop Drawings 33 27-Nov-14 05-Jan-15 Power System Second Floor Plan Rev 0 Submittal 5 27-Nov-14 04-Dec-14 Power System Second Floor Plan Rev 0 Reply 14 04-Dec-14 21-Dec-14 Power System Second Floor Plan Rev 1 Submittal 5 21-Dec-14 28-Dec-14 Power System Second Floor Plan Rev 1 Approval 7 28-Dec-14 05-Jan-15 Safety Lighting System Shop Drawings 33 15-Dec-14 22-Jan-15 Safety Lighting System Second Floor Plan Rev 0 Submittal 5 15-Dec-14 21-Dec-14 Safety Lighting System Second Floor Plan Rev 0 Reply 14 22-Dec-14 06-Jan-15 Safety Lighting System Second Floor Plan Rev 1 Submittal 5 08-Jan-15 14-Jan-15 Safety Lighting System Second Floor Plan Rev 1 Approval 7 15-Jan-15 22-Jan-15 Low Current Systems Shop Drawings 33 24-Nov-14 31-Dec-14 Fire Alarm System 33 24-Nov-14 31-Dec-14 Fire Alarm System Second Floor Plan Rev 0 Submittal 5 24-Nov-14 30-Nov-14 Fire Alarm System Second Floor Plan Rev 0 Reply 14 01-Dec-14 16-Dec-14 Fire Alarm System Second Floor Plan Rev 1 Submittal 5 17-Dec-14 23-Dec-14 Fire Alarm System Second Floor Plan Rev 1 Approval 7 24-Dec-14 31-Dec-14 Sound & Security systems 33 24-Nov-14 31-Dec-14 Sound & Security Systems Second Floor Plan Rev 0 Submittal 5 24-Nov-14 30-Nov-14 Sound & Security Systems Second Floor Plan Rev 0 Reply 14 01-Dec-14 16-Dec-14 Sound & Security Systems Second Floor Plan Rev 1 Submittal 5 17-Dec-14 23-Dec-14 Sound & Security Systems Second Floor Plan Rev 1 Approval 7 24-Dec-14 31-Dec-14 Voice,Data,IPTV systems 33 24-Nov-14 31-Dec-14 Voice, Data, IPTV Systems Second Floor Plan Rev 0 Submittal 5 24-Nov-14 30-Nov-14 Voice, Data, IPTV Systems Second Floor Plan Rev 0 Reply 14 01-Dec-14 16-Dec-14 Voice, Data, IPTV Systems Second Floor Plan Rev 1 Submittal 5 17-Dec-14 23-Dec-14 Voice, Data, IPTV Systems Second Floor Plan Rev 1 Approval 7 24-Dec-14 31-Dec-14 M Mechanical Systems Shop Drawings 97 24-Nov-14 18-Mar-15 HVAC System Shop Drawings 33 24-Nov-14 31-Dec-14 HVAC System Second Floor Plan Rev 0 Submittal 5 24-Nov-14 30-Nov-14 Jun Jul Aug Sep Oct Nov Dec Qtr 3 Qtr 4 2014 SECON Nile Tower Project MEP Base Line Secon Nile Tower Project Siemens Scope 21-Mar-16 17:19 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 19 of 1076 TASK filter: All Activities © Primavera Systems, Inc
  • 11. Activity ID Activity Name Original Duration Start Finish HVAC System Second Floor Plan Rev 0 Reply 14 01-Dec-14 16-Dec-14 HVAC System Second Floor Plan Rev 1 Submittal 5 17-Dec-14 23-Dec-14 HVAC System Second Floor Plan Rev 1 Approval 7 24-Dec-14 31-Dec-14 Fire Fighting System Shop Drawings 33 24-Nov-14 31-Dec-14 Fire Fighting System Second Floor Plan Rev 0 Submittal 5 24-Nov-14 30-Nov-14 Fire Fighting System Second Floor Plan Rev 0 Reply 14 01-Dec-14 16-Dec-14 Fire Fighting System Second Floor Plan Rev 1 Submittal 5 17-Dec-14 23-Dec-14 Fire Fighting System Second Floor Plan Rev 1 Approval 7 24-Dec-14 31-Dec-14 Plumbing System Shop Drawings 68 28-Dec-14 18-Mar-15 Toilet Details (T1, T6 , T24, T25, T35, T36, T37, T38) Submittal Rev 0 5 28-Dec-14 01-Jan-15 Toilet Details (T1, T6 , T24, T25, T35, T36, T37, T38) Reply Rev 0 14 03-Jan-15 19-Jan-15 Toilet Details (T1, T6 , T24, T25, T35, T36, T37, T38) Submittal Rev 1 5 20-Jan-15 27-Jan-15 Toilet Details (T1, T6 , T24, T25, T35, T36, T37, T38) Approval Rev 1 7 28-Jan-15 04-Feb-15 Water Supply System Second Floor Plan Rev 0 Submittal 5 05-Feb-15 11-Feb-15 Drainage System Second Floor Plan Rev 0 Submittal 5 09-Feb-15 15-Feb-15 Water Supply System Second Floor Plan Rev 0 Reply 14 12-Feb-15 28-Feb-15 Drainage System Second Floor Plan Rev 0 Reply 14 16-Feb-15 03-Mar-15 Water Supply System Second Floor Plan Rev 1 Submittal 5 01-Mar-15 05-Mar-15 Drainage System Second Floor Plan Rev 1 Submittal 5 04-Mar-15 10-Mar-15 Water Supply System Second Floor Plan Rev 1 Approval 7 07-Mar-15 14-Mar-15 Drainage System Second Floor Plan Rev 1 Approval 7 11-Mar-15 18-Mar-15 C Composite Shop Drawings 32 19-Mar-15 26-Apr-15 Composite Drawing for Second Floor Plan Rev 0 Submittal 5 19-Mar-15 25-Mar-15 Composite Drawing for Second Floor Plan Rev 0 Reply 14 26-Mar-15 11-Apr-15 Composite Drawing for Second Floor Plan Rev 1 Submittal 5 12-Apr-15 16-Apr-15 Composite Drawing for Second Floor Plan Rev 1 Approval 7 18-Apr-15 26-Apr-15 Th Third Floor Shop Drawings 272 08-Jul-14 26-May-15 SS Receive Third Floor MEP Design Package 0 08-Jul-14 SS Receive Third Floor Approved Architecture Design Package 0 11-Dec-14 SS Receive Third Floor Approved Structural Design Package 0 11-Dec-14 SS Receive Third Floor Approved Architecture Shop Drawings 0 17-Dec-14 SS Receive Third Floor Approved Tiles Shop Drawings 0 08-Jan-15 E Electrical Systems Shop Drawings 54 21-Dec-14 23-Feb-15 Lighting System Shop Drawings 32 21-Dec-14 28-Jan-15 Lighting System Third Floor Plan Rev 0 Submittal 5 21-Dec-14 25-Dec-14 Lighting System Third Floor Plan Rev 0 Reply 14 27-Dec-14 12-Jan-15 Lighting System Third Floor Plan Rev 1 Submittal 5 13-Jan-15 19-Jan-15 Lighting System Third Floor Plan Rev 1 Approval 7 20-Jan-15 28-Jan-15 Jun Jul Aug Sep Oct Nov Dec Qtr 3 Qtr 4 2014 SECON Nile Tower Project MEP Base Line Secon Nile Tower Project Siemens Scope 21-Mar-16 17:19 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 21 of 1076 TASK filter: All Activities © Primavera Systems, Inc
  • 12. Activity ID Activity Name Original Duration Start Finish Power System Shop Drawings 33 23-Dec-14 01-Feb-15 Power System Third Floor Plan Rev 0 Submittal 5 23-Dec-14 30-Dec-14 Power System Third Floor Plan Rev 0 Reply 14 30-Dec-14 17-Jan-15 Power System Third Floor Plan Rev 1 Submittal 5 18-Jan-15 22-Jan-15 Power System Third Floor Plan Rev 1 Approval 7 24-Jan-15 01-Feb-15 Safety Lighting System Shop Drawings 33 15-Jan-15 23-Feb-15 Safety Lighting System Third Floor Plan Rev 0 Submittal 5 15-Jan-15 21-Jan-15 Safety Lighting System Third Floor Plan Rev 0 Reply 14 22-Jan-15 08-Feb-15 Safety Lighting System Third Floor Plan Rev 1 Submittal 5 09-Feb-15 15-Feb-15 Safety Lighting System Third Floor Plan Rev 1 Approval 7 16-Feb-15 23-Feb-15 Low Current Systems Shop Drawings 32 21-Dec-14 28-Jan-15 Fire Alarm System 32 21-Dec-14 28-Jan-15 Fire Alarm System Third Floor Plan Rev 0 Submittal 5 21-Dec-14 25-Dec-14 Fire Alarm System Third Floor Plan Rev 0 Reply 14 27-Dec-14 12-Jan-15 Fire Alarm System Third Floor Plan Rev 1 Submittal 5 13-Jan-15 19-Jan-15 Fire Alarm System Third Floor Plan Rev 1 Approval 7 20-Jan-15 28-Jan-15 Sound & Security systems 32 21-Dec-14 28-Jan-15 Sound & Security Systems Third Floor Plan Rev 0 Submittal 5 21-Dec-14 25-Dec-14 Sound & Security Systems Third Floor Plan Rev 0 Reply 14 27-Dec-14 12-Jan-15 Sound & Security Systems Third Floor Plan Rev 1 Submittal 5 13-Jan-15 19-Jan-15 Sound & Security Systems Third Floor Plan Rev 1 Approval 7 20-Jan-15 28-Jan-15 Voice,Data,IPTV systems 32 21-Dec-14 28-Jan-15 Voice, Data, IPTV Systems Third Floor Plan Rev 0 Submittal 5 21-Dec-14 25-Dec-14 Voice, Data, IPTV Systems Third Floor Plan Rev 0 Reply 14 27-Dec-14 12-Jan-15 Voice, Data, IPTV Systems Third Floor Plan Rev 1 Submittal 5 13-Jan-15 19-Jan-15 Voice, Data, IPTV Systems Third Floor Plan Rev 1 Approval 7 20-Jan-15 28-Jan-15 M Mechanical Systems Shop Drawings 99 21-Dec-14 16-Apr-15 HVAC System Shop Drawings 32 21-Dec-14 28-Jan-15 HVAC System Third Floor Plan Rev 0 Submittal 5 21-Dec-14 25-Dec-14 HVAC System Third Floor Plan Rev 0 Reply 14 27-Dec-14 12-Jan-15 HVAC System Third Floor Plan Rev 1 Submittal 5 13-Jan-15 19-Jan-15 HVAC System Third Floor Plan Rev 1 Approval 7 20-Jan-15 28-Jan-15 Fire Fighting System Shop Drawings 32 21-Dec-14 28-Jan-15 Fire Fighting System Third Floor Plan Rev 0 Submittal 5 21-Dec-14 25-Dec-14 Fire Fighting System Third Floor Plan Rev 0 Reply 14 27-Dec-14 12-Jan-15 Fire Fighting System Third Floor Plan Rev 1 Submittal 5 13-Jan-15 19-Jan-15 Fire Fighting System Third Floor Plan Rev 1 Approval 7 20-Jan-15 28-Jan-15 Plumbing System Shop Drawings 68 28-Jan-15 16-Apr-15 Jun Jul Aug Sep Oct Nov Dec Qtr 3 Qtr 4 2014 SECON Nile Tower Project MEP Base Line Secon Nile Tower Project Siemens Scope 21-Mar-16 17:19 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 23 of 1076 TASK filter: All Activities © Primavera Systems, Inc
  • 13. Activity ID Activity Name Original Duration Start Finish Toilet Details (T 1, 3, 6, 8, 9, 24, 25, 30, 40 ) Submittal Rev 0 5 28-Jan-15 03-Feb-15 Toilet Details (T 1, 3, 6, 8, 9, 24, 25, 30, 40 ) Reply Rev 0 14 04-Feb-15 19-Feb-15 Toilet Details (T 1, 3, 6, 8, 9, 24, 25, 30, 40 ) Submittal Rev 1 5 22-Feb-15 26-Feb-15 Toilet Details (T 1, 3, 6, 8, 9, 24, 25, 30, 40 ) Approval Rev 1 7 28-Feb-15 07-Mar-15 Water Supply System Third Floor Plan Rev 0 Submittal 5 08-Mar-15 12-Mar-15 Drainage System Third Floor Plan Rev 0 Submittal 5 10-Mar-15 16-Mar-15 Water Supply System Third Floor Plan Rev 0 Reply 14 14-Mar-15 29-Mar-15 Drainage System Third Floor Plan Rev 0 Reply 14 17-Mar-15 01-Apr-15 Water Supply System Third Floor Plan Rev 1 Submittal 5 30-Mar-15 05-Apr-15 Drainage System Third Floor Plan Rev 1 Submittal 5 02-Apr-15 08-Apr-15 Water Supply System Third Floor Plan Rev 1 Approval 7 06-Apr-15 13-Apr-15 Drainage System Third Floor Plan Rev 1 Approval 7 09-Apr-15 16-Apr-15 C Composite Shop Drawings 32 19-Apr-15 26-May-15 Composite Drawing for Third Floor Plan Rev 0 Submittal 5 19-Apr-15 23-Apr-15 Composite Drawing for Third Floor Plan Rev 0 Reply 14 26-Apr-15 11-May-15 Composite Drawing for Third Floor Plan Rev 1 Submittal 5 12-May-15 18-May-15 Composite Drawing for Third Floor Plan Rev 1 Approval 7 19-May-15 26-May-15 Ty Typical Floor (4 : 20) Shop Drawings 298 08-Jul-14 25-Jun-15 SS Receive Typical Floor (4:20) MEP Design Package 0 08-Jul-14 SS Receive Typical Floor (4:20) Approved Architecture Design Package 0 06-Jan-15 SS Receive Typical Floor (4:20) Approved Structural Design Package 0 06-Jan-15 SS Receive Typical Floor (4:20) Approved Architecture Shop Drawings 0 13-Jan-15 SS Receive Typical Floor (4:20) Approved Tiles Shop Drawings 0 04-Feb-15 E Electrical Systems Shop Drawings 59 15-Jan-15 25-Mar-15 Lighting System Shop Drawings 33 15-Jan-15 23-Feb-15 Lighting System Typical Floor Plan (4:20) Rev 0 Submittal 5 15-Jan-15 21-Jan-15 Lighting System Typical Floors Plan (4:20) Rev 0 Reply 14 22-Jan-15 08-Feb-15 Lighting System Typical Floors Plan (4:20) Rev 1 Submittal 5 09-Feb-15 15-Feb-15 Lighting System Typical Floors Plan (4:20) Rev 1 Approval 7 16-Feb-15 23-Feb-15 Power System Shop Drawings 33 20-Jan-15 28-Feb-15 Power System Typical Floors Plan (4:20) Rev 0 Submittal 5 20-Jan-15 27-Jan-15 Power System Typical Floors Plan (4:20) Rev 0 Reply 14 28-Jan-15 12-Feb-15 Power System Typical Floors Plan (4:20) Rev 1 Submittal 5 15-Feb-15 19-Feb-15 Power System Typical Floors Plan (4:20) Rev 1 Approval 7 21-Feb-15 28-Feb-15 Safety Lighting System Shop Drawings 33 16-Feb-15 25-Mar-15 Safety Lighting System Typical Floors Plan (4:20) Rev 0 Submittal 5 16-Feb-15 22-Feb-15 Safety Lighting System Typical Floors Plan (4:20) Rev 0 Reply 14 23-Feb-15 10-Mar-15 Safety Lighting System Typical Floors Plan (4:20) Rev 1 Submittal 5 11-Mar-15 17-Mar-15 Jun Jul Aug Sep Oct Nov Dec Qtr 3 Qtr 4 2014 SECON Nile Tower Project MEP Base Line Secon Nile Tower Project Siemens Scope 21-Mar-16 17:19 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 25 of 1076 TASK filter: All Activities © Primavera Systems, Inc
  • 14. Activity ID Activity Name Original Duration Start Finish Safety Lighting System Typical Floors Plan (4:20) Rev 1 Approval 7 18-Mar-15 25-Mar-15 Low Current Systems Shop Drawings 33 15-Jan-15 23-Feb-15 Fire Alarm System 33 15-Jan-15 23-Feb-15 Fire Alarm System Typical Floors Plan (4:20) Rev 0 Submittal 5 15-Jan-15 21-Jan-15 Fire Alarm System Typical Floors Plan (4:20) Rev 0 Reply 14 22-Jan-15 08-Feb-15 Fire Alarm System Typical Floors Plan (4:20) Rev 1 Submittal 5 09-Feb-15 15-Feb-15 Fire Alarm System Typical Floors Plan (4:20) Rev 1 Approval 7 16-Feb-15 23-Feb-15 Sound & Security systems 33 15-Jan-15 23-Feb-15 Sound & Security Systems Typical Floors Plan (4:20) Rev 0 Submittal 5 15-Jan-15 21-Jan-15 Sound & Security Systems Typical Floors Plan (4:20) Rev 0 Reply 14 22-Jan-15 08-Feb-15 Sound & Security Systems Typical Floors Plan (4:20) Rev 1 Submittal 5 09-Feb-15 15-Feb-15 Sound & Security Systems Typical Floors Plan (4:20) Rev 1 Approval 7 16-Feb-15 23-Feb-15 Voice,Data,IPTV systems 33 15-Jan-15 23-Feb-15 Voice, Data, IPTV Systems Typical Floors Plan (4:20) Rev 0 Submittal 5 15-Jan-15 21-Jan-15 Voice, Data, IPTV Systems Typical Floors Plan (4:20) Rev 0 Reply 14 22-Jan-15 08-Feb-15 Voice, Data, IPTV Systems Typical Floors Plan (4:20) Rev 1 Submittal 5 09-Feb-15 15-Feb-15 Voice, Data, IPTV Systems Typical Floors Plan (4:20) Rev 1 Approval 7 16-Feb-15 23-Feb-15 M Mechanical Systems Shop Drawings 104 15-Jan-15 18-May-15 HVAC System Shop Drawings 33 15-Jan-15 23-Feb-15 HVAC System Typical Floors Plan (4:20) Rev 0 Submittal 5 15-Jan-15 21-Jan-15 HVAC System Typical Floors Plan (4:20) Rev 0 Reply 14 22-Jan-15 08-Feb-15 HVAC System Typical Floors Plan (4:20) Rev 1 Submittal 5 09-Feb-15 15-Feb-15 HVAC System Typical Floors Plan (4:20) Rev 1 Approval 7 16-Feb-15 23-Feb-15 Fire Fighting System Shop Drawings 33 15-Jan-15 23-Feb-15 Fire Fighting System Typical Floors Plan (4:20) Rev 0 Submittal 5 15-Jan-15 21-Jan-15 Fire Fighting System Typical Floors Plan (4:20) Rev 0 Reply 14 22-Jan-15 08-Feb-15 Fire Fighting System Typical Floors Plan (4:20) Rev 1 Submittal 5 09-Feb-15 15-Feb-15 Fire Fighting System Typical Floors Plan (4:20) Rev 1 Approval 7 16-Feb-15 23-Feb-15 Plumbing System Shop Drawings 67 01-Mar-15 18-May-15 Toilet Details (T 3, 8, 9, 30 ,40 ) Submittal Rev 0 5 01-Mar-15 05-Mar-15 Toilet Details (T 3, 8, 9, 30 ,40 ) Reply Rev 0 14 07-Mar-15 22-Mar-15 Toilet Details (T 3, 8, 9, 30 ,40 ) Submittal Rev 1 5 23-Mar-15 29-Mar-15 Toilet Details (T 3, 8, 9, 30 ,40 ) Approval Rev 1 7 30-Mar-15 06-Apr-15 Water Supply System Typical Floors Plan (4:20) Rev 0 Submittal 5 07-Apr-15 13-Apr-15 Drainage System Typical Floors Plan (4:20) Rev 0 Submittal 5 09-Apr-15 15-Apr-15 Water Supply System Typical Floors Plan (4:20) Rev 0 Reply 14 14-Apr-15 30-Apr-15 Drainage System Typical Floors Plan (4:20) Rev 0 Reply 14 16-Apr-15 03-May-15 Water Supply System Typical Floors Plan (4:20) Rev 1 Submittal 5 03-May-15 07-May-15 Jun Jul Aug Sep Oct Nov Dec Qtr 3 Qtr 4 2014 SECON Nile Tower Project MEP Base Line Secon Nile Tower Project Siemens Scope 21-Mar-16 17:19 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 27 of 1076 TASK filter: All Activities © Primavera Systems, Inc
  • 15. Activity ID Activity Name Original Duration Start Finish Drainage System Typical Floors Plan (4:20) Rev 1 Submittal 5 04-May-15 10-May-15 Water Supply System Typical Floors Plan (4:20) Rev 1 Approval 7 09-May-15 16-May-15 Drainage System Typical Floors Plan (4:20) Rev 1 Approval 7 11-May-15 18-May-15 C Composite Shop Drawings 33 19-May-15 25-Jun-15 Composite Drawing for Typical Floors Plan (4:20) Rev 0 Submittal 5 19-May-15 25-May-15 Composite Drawing for Typical Floors Plan (4:20) Rev 0 Reply 14 26-May-15 10-Jun-15 Composite Drawing for Typical Floors Plan (4:20) Rev 1 Submittal 5 11-Jun-15 17-Jun-15 Composite Drawing for Typical Floors Plan (4:20) Rev 1 Approval 7 18-Jun-15 25-Jun-15 21 21st Floor Shop Drawings 324 08-Jul-14 28-Jul-15 SS Receive 21st Floor MEP Design Package 0 08-Jul-14 SS Receive 21st Floor Approved Architecture Design Package 0 03-Feb-15 SS Receive 21st Floor Approved Structural Design Package 0 03-Feb-15 SS Receive 21st Floor Approved Architecture Shop Drawings 0 09-Feb-15 SS Receive 21st Floor Approved Tiles Shop Drawings 0 02-Mar-15 E Electrical Systems Shop Drawings 63 11-Feb-15 26-Apr-15 Lighting System Shop Drawings 33 11-Feb-15 21-Mar-15 Lighting System 21st Floor Plan Rev 0 Submittal 5 11-Feb-15 17-Feb-15 Lighting System 21st Floor Plan Rev 0 Reply 14 18-Feb-15 05-Mar-15 Lighting System 21st Floor Plan Rev 1 Submittal 5 08-Mar-15 12-Mar-15 Lighting System 21st Floor Plan Rev 1 Approval 7 14-Mar-15 21-Mar-15 Power System Shop Drawings 33 17-Feb-15 26-Mar-15 Power System 21st Floor Plan Rev 0 Submittal 5 17-Feb-15 23-Feb-15 Power System 21st Floor Plan Rev 0 Reply 14 24-Feb-15 11-Mar-15 Power System 21st Floor Plan Rev 1 Submittal 5 12-Mar-15 18-Mar-15 Power System 21st Floor Plan Rev 1 Approval 7 19-Mar-15 26-Mar-15 Safety Lighting System Shop Drawings 33 18-Mar-15 26-Apr-15 Safety Lighting System 21st Floor Plan Rev 0 Submittal 5 18-Mar-15 24-Mar-15 Safety Lighting System 21st Floor Plan Rev 0 Reply 14 25-Mar-15 09-Apr-15 Safety Lighting System 21st Floor Plan Rev 1 Submittal 5 12-Apr-15 16-Apr-15 Safety Lighting System 21st Floor Plan Rev 1 Approval 7 18-Apr-15 26-Apr-15 Low Current Systems Shop Drawings 33 11-Feb-15 21-Mar-15 Fire Alarm System 33 11-Feb-15 21-Mar-15 Fire Alarm System 21st Floor Plan Rev 0 Submittal 5 11-Feb-15 17-Feb-15 Fire Alarm System 21st Floor Plan Rev 0 Reply 14 18-Feb-15 05-Mar-15 Fire Alarm System 21st Floor Plan Rev 1 Submittal 5 08-Mar-15 12-Mar-15 Fire Alarm System 21st Floor Plan Rev 1 Approval 7 14-Mar-15 21-Mar-15 Sound & Security systems 33 11-Feb-15 21-Mar-15 Sound & Security Systems 21st Floor Plan Rev 0 Submittal 5 11-Feb-15 17-Feb-15 Jun Jul Aug Sep Oct Nov Dec Qtr 3 Qtr 4 2014 SECON Nile Tower Project MEP Base Line Secon Nile Tower Project Siemens Scope 21-Mar-16 17:19 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 29 of 1076 TASK filter: All Activities © Primavera Systems, Inc
  • 16. Activity ID Activity Name Original Duration Start Finish Sound & Security Systems 21st Floor Plan Rev 0 Reply 14 18-Feb-15 05-Mar-15 Sound & Security Systems 21st Floor Plan Rev 1 Submittal 5 08-Mar-15 12-Mar-15 Sound & Security Systems 21st Floor Plan Rev 1 Approval 7 14-Mar-15 21-Mar-15 Voice,Data,IPTV systems 33 11-Feb-15 21-Mar-15 Voice, Data, IPTV Systems 21st Floor Plan Rev 0 Submittal 5 11-Feb-15 17-Feb-15 Voice, Data, IPTV Systems 21st Floor Plan Rev 0 Reply 14 18-Feb-15 05-Mar-15 Voice, Data, IPTV Systems 21st Floor Plan Rev 1 Submittal 5 08-Mar-15 12-Mar-15 Voice, Data, IPTV Systems 21st Floor Plan Rev 1 Approval 7 14-Mar-15 21-Mar-15 M Mechanical Systems Shop Drawings 108 11-Feb-15 17-Jun-15 HVAC System Shop Drawings 33 11-Feb-15 21-Mar-15 HVAC System 21st Floor Plan Rev 0 Submittal 5 11-Feb-15 17-Feb-15 HVAC System 21st Floor Plan Rev 0 Reply 14 18-Feb-15 05-Mar-15 HVAC System 21st Floor Plan Rev 1 Submittal 5 08-Mar-15 12-Mar-15 HVAC System 21st Floor Plan Rev 1 Approval 7 14-Mar-15 21-Mar-15 Fire Fighting System Shop Drawings 33 11-Feb-15 21-Mar-15 Fire Fighting System 21st Floor Plan Rev 0 Submittal 5 11-Feb-15 17-Feb-15 Fire Fighting System 21st Floor Plan Rev 0 Reply 14 18-Feb-15 05-Mar-15 Fire Fighting System 21st Floor Plan Rev 1 Submittal 5 08-Mar-15 12-Mar-15 Fire Fighting System 21st Floor Plan Rev 1 Approval 7 14-Mar-15 21-Mar-15 Plumbing System Shop Drawings 68 30-Mar-15 17-Jun-15 Toilet Details (T 3, 8, 9, 40 ) Submittal Rev 0 5 30-Mar-15 05-Apr-15 Toilet Details (T 3, 8, 9, 40 ) Reply Rev 0 14 06-Apr-15 21-Apr-15 Toilet Details (T 3, 8, 9, 40 ) Submittal Rev 1 5 22-Apr-15 28-Apr-15 Toilet Details (T 3, 8, 9, 40 ) Approval Rev 1 7 29-Apr-15 06-May-15 Water Supply System 21st Floor Plan Rev 0 Submittal 5 07-May-15 13-May-15 Drainage System 21st Floor Plan Rev 0 Submittal 5 11-May-15 17-May-15 Water Supply System 21st Floor Plan Rev 0 Reply 14 14-May-15 30-May-15 Drainage System 21st Floor Plan Rev 0 Reply 14 18-May-15 02-Jun-15 Water Supply System 21st Floor Plan Rev 1 Submittal 5 31-May-15 04-Jun-15 Drainage System 21st Floor Plan Rev 1 Submittal 5 03-Jun-15 09-Jun-15 Water Supply System 21st Floor Plan Rev 1 Approval 7 06-Jun-15 13-Jun-15 Drainage System 21st Floor Plan Rev 1 Approval 7 10-Jun-15 17-Jun-15 C Composite Shop Drawings 33 18-Jun-15 28-Jul-15 Composite Drawing for 21st Floor Plan Rev 0 Submittal 5 18-Jun-15 24-Jun-15 Composite Drawing for 21st Floor Plan Rev 0 Reply 14 25-Jun-15 11-Jul-15 Composite Drawing for 21st Floor Plan Rev 1 Submittal 5 12-Jul-15 19-Jul-15 Composite Drawing for 21st Floor Plan Rev 1 Approval 7 20-Jul-15 28-Jul-15 22 22nd Floor Shop Drawings 349 08-Jul-14 26-Aug-15 Jun Jul Aug Sep Oct Nov Dec Qtr 3 Qtr 4 2014 SECON Nile Tower Project MEP Base Line Secon Nile Tower Project Siemens Scope 21-Mar-16 17:19 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 31 of 1076 TASK filter: All Activities © Primavera Systems, Inc
  • 17. Activity ID Activity Name Original Duration Start Finish SS Receive 22nd Floor MEP Design Package 0 08-Jul-14 SS Receive 22nd Floor Approved Architecture Design Package 0 01-Mar-15 SS Receive 22nd Floor Approved Structural Design Package 0 01-Mar-15 SS Receive 22nd Floor Approved Architecture Shop Drawings 0 07-Mar-15 SS Receive 22nd Floor Approved Tiles Shop Drawings 0 28-Mar-15 E Electrical Systems Shop Drawings 66 10-Mar-15 26-May-15 Lighting System Shop Drawings 33 10-Mar-15 16-Apr-15 Lighting System 22nd Floor Plan Rev 0 Submittal 5 10-Mar-15 16-Mar-15 Lighting System 22nd Floor Plan Rev 0 Reply 14 17-Mar-15 01-Apr-15 Lighting System 22nd Floor Plan Rev 1 Submittal 5 02-Apr-15 08-Apr-15 Lighting System 22nd Floor Plan Rev 1 Approval 7 09-Apr-15 16-Apr-15 Power System Shop Drawings 33 16-Mar-15 22-Apr-15 Power System 22nd Floor Plan Rev 0 Submittal 5 16-Mar-15 22-Mar-15 Power System 22nd Floor Plan Rev 0 Reply 14 23-Mar-15 07-Apr-15 Power System 22nd Floor Plan Rev 1 Submittal 5 08-Apr-15 14-Apr-15 Power System 22nd Floor Plan Rev 1 Approval 7 15-Apr-15 22-Apr-15 Safety Lighting System Shop Drawings 32 19-Apr-15 26-May-15 Safety Lighting System 22nd Floor Plan Rev 0 Submittal 5 19-Apr-15 23-Apr-15 Safety Lighting System 22nd Floor Plan Rev 0 Reply 14 26-Apr-15 11-May-15 Safety Lighting System 22nd Floor Plan Rev 1 Submittal 5 12-May-15 18-May-15 Safety Lighting System 22nd Floor Plan Rev 1 Approval 7 19-May-15 26-May-15 Low Current Systems Shop Drawings 33 10-Mar-15 16-Apr-15 Fire Alarm System 33 10-Mar-15 16-Apr-15 Fire Alarm System 22nd Floor Plan Rev 0 Submittal 5 10-Mar-15 16-Mar-15 Fire Alarm System 22nd Floor Plan Rev 0 Reply 14 17-Mar-15 01-Apr-15 Fire Alarm System 22nd Floor Plan Rev 1 Submittal 5 02-Apr-15 08-Apr-15 Fire Alarm System 22nd Floor Plan Rev 1 Approval 7 09-Apr-15 16-Apr-15 Sound & Security systems 33 10-Mar-15 16-Apr-15 Sound & Security Systems 22nd Floor Plan Rev 0 Submittal 5 10-Mar-15 16-Mar-15 Sound & Security Systems 22nd Floor Plan Rev 0 Reply 14 17-Mar-15 01-Apr-15 Sound & Security Systems 22nd Floor Plan Rev 1 Submittal 5 02-Apr-15 08-Apr-15 Sound & Security Systems 22nd Floor Plan Rev 1 Approval 7 09-Apr-15 16-Apr-15 Voice,Data,IPTV systems 33 10-Mar-15 16-Apr-15 Voice, Data, IPTV Systems 22nd Floor Plan Rev 0 Submittal 5 10-Mar-15 16-Mar-15 Voice, Data, IPTV Systems 22nd Floor Plan Rev 0 Reply 14 17-Mar-15 01-Apr-15 Voice, Data, IPTV Systems 22nd Floor Plan Rev 1 Submittal 5 02-Apr-15 08-Apr-15 Voice, Data, IPTV Systems 22nd Floor Plan Rev 1 Approval 7 09-Apr-15 16-Apr-15 M Mechanical Systems Shop Drawings 110 10-Mar-15 16-Jul-15 Jun Jul Aug Sep Oct Nov Dec Qtr 3 Qtr 4 2014 SECON Nile Tower Project MEP Base Line Secon Nile Tower Project Siemens Scope 21-Mar-16 17:19 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 33 of 1076 TASK filter: All Activities © Primavera Systems, Inc
  • 18. Activity ID Activity Name Original Duration Start Finish HVAC System Shop Drawings 33 10-Mar-15 16-Apr-15 HVAC System 22nd Floor Plan Rev 0 Submittal 5 10-Mar-15 16-Mar-15 HVAC System 22nd Floor Plan Rev 0 Reply 14 17-Mar-15 01-Apr-15 HVAC System 22nd Floor Plan Rev 1 Submittal 5 02-Apr-15 08-Apr-15 HVAC System 22nd Floor Plan Rev 1 Approval 7 09-Apr-15 16-Apr-15 Fire Fighting System Shop Drawings 33 10-Mar-15 16-Apr-15 Fire Fighting System 22nd Floor Plan Rev 0 Submittal 5 10-Mar-15 16-Mar-15 Fire Fighting System 22nd Floor Plan Rev 0 Reply 14 17-Mar-15 01-Apr-15 Fire Fighting System 22nd Floor Plan Rev 1 Submittal 5 02-Apr-15 08-Apr-15 Fire Fighting System 22nd Floor Plan Rev 1 Approval 7 09-Apr-15 16-Apr-15 Plumbing System Shop Drawings 68 29-Apr-15 16-Jul-15 Toilet Details (T3,8,9,11,12,13,14,15,16,17,18,19,20,21,22,23) Submittal Rev 0 5 29-Apr-15 05-May-15 Toilet Details (T3,8,9,11,12,13,14,15,16,17,18,19,20,21,22,23) Reply Rev 0 14 06-May-15 21-May-15 Toilet Details (T3,8,9,11,12,13,14,15,16,17,18,19,20,21,22,23) Submittal Rev 1 5 24-May-15 28-May-15 Toilet Details (T3,8,9,11,12,13,14,15,16,17,18,19,20,21,22,23) Approval Rev 1 7 30-May-15 06-Jun-15 Water Supply System 22nd Floor Plan Rev 0 Submittal 5 07-Jun-15 11-Jun-15 Drainage System 22nd Floor Plan Rev 0 Submittal 5 09-Jun-15 15-Jun-15 Water Supply System 22nd Floor Plan Rev 0 Reply 14 13-Jun-15 28-Jun-15 Drainage System 22nd Floor Plan Rev 0 Reply 14 16-Jun-15 01-Jul-15 Water Supply System 22nd Floor Plan Rev 1 Submittal 5 29-Jun-15 05-Jul-15 Drainage System 22nd Floor Plan Rev 1 Submittal 5 02-Jul-15 08-Jul-15 Water Supply System 22nd Floor Plan Rev 1 Approval 7 06-Jul-15 13-Jul-15 Drainage System 22nd Floor Plan Rev 1 Approval 7 09-Jul-15 16-Jul-15 C Composite Shop Drawings 33 19-Jul-15 26-Aug-15 Composite Drawing for 22nd Floor Plan Rev 0 Submittal 5 19-Jul-15 26-Jul-15 Composite Drawing for 22nd Floor Plan Rev 0 Reply 14 27-Jul-15 11-Aug-15 Composite Drawing for 22nd Floor Plan Rev 1 Submittal 5 12-Aug-15 18-Aug-15 Composite Drawing for 22nd Floor Plan Rev 1 Approval 7 19-Aug-15 26-Aug-15 Ro Roof Floor Shop Drawings 375 08-Jul-14 28-Sep-15 SS Receive Roof Floor MEP Design Package 0 08-Jul-14 SS Receive Roof Floor Approved Architecture Design Package 0 26-Mar-15 SS Receive Roof Floor Approved Structural Design Package 0 26-Mar-15 SS Receive Roof Floor Approved Architecture Shop Drawings 0 01-Apr-15 E Electrical Systems Shop Drawings 69 06-Apr-15 25-Jun-15 Lighting System Shop Drawings 33 06-Apr-15 14-May-15 Lighting System Roof Floor Plan Rev 0 Submittal 5 06-Apr-15 12-Apr-15 Lighting System Roof Floor Plan Rev 0 Reply 14 13-Apr-15 29-Apr-15 Lighting System Roof Floor Plan Rev 1 Submittal 5 30-Apr-15 06-May-15 Jun Jul Aug Sep Oct Nov Dec Qtr 3 Qtr 4 2014 SECON Nile Tower Project MEP Base Line Secon Nile Tower Project Siemens Scope 21-Mar-16 17:19 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 35 of 1076 TASK filter: All Activities © Primavera Systems, Inc
  • 19. Activity ID Activity Name Original Duration Start Finish Lighting System Roof Floor Plan Rev 1 Approval 7 07-May-15 14-May-15 Power System Shop Drawings 32 12-Apr-15 19-May-15 Power System Roof Floor Plan Rev 0 Submittal 5 12-Apr-15 16-Apr-15 Power System Roof Floor Plan Rev 0 Reply 14 18-Apr-15 04-May-15 Power System Roof Floor Plan Rev 1 Submittal 5 05-May-15 11-May-15 Power System Roof Floor Plan Rev 1 Approval 7 12-May-15 19-May-15 Safety Lighting System Shop Drawings 33 19-May-15 25-Jun-15 Safety Lighting System Roof Floor Plan Rev 0 Submittal 5 19-May-15 25-May-15 Safety Lighting System Roof Floor Plan Rev 0 Reply 14 26-May-15 10-Jun-15 Safety Lighting System Roof Floor Plan Rev 1 Submittal 5 11-Jun-15 17-Jun-15 Safety Lighting System Roof Floor Plan Rev 1 Approval 7 18-Jun-15 25-Jun-15 Low Current Systems Shop Drawings 33 06-Apr-15 14-May-15 Fire Alarm System 33 06-Apr-15 14-May-15 Fire Alarm System Roof Floor Plan Rev 0 Submittal 5 06-Apr-15 12-Apr-15 Fire Alarm System Roof Floor Plan Rev 0 Reply 14 13-Apr-15 29-Apr-15 Fire Alarm System Roof Floor Plan Rev 1 Submittal 5 30-Apr-15 06-May-15 Fire Alarm System Roof Floor Plan Rev 1 Approval 7 07-May-15 14-May-15 Sound & Security systems 33 06-Apr-15 14-May-15 Sound & Security Systems Roof Floor Plan Rev 0 Submittal 5 06-Apr-15 12-Apr-15 Sound & Security Systems Roof Floor Plan Rev 0 Reply 14 13-Apr-15 29-Apr-15 Sound & Security Systems Roof Floor Plan Rev 1 Submittal 5 30-Apr-15 06-May-15 Sound & Security Systems Roof Floor Plan Rev 1 Approval 7 07-May-15 14-May-15 Voice,Data,IPTV systems 33 06-Apr-15 14-May-15 Voice, Data, IPTV Systems Roof Floor Plan Rev 0 Submittal 5 06-Apr-15 12-Apr-15 Voice, Data, IPTV Systems Roof Floor Plan Rev 0 Reply 14 13-Apr-15 29-Apr-15 Voice, Data, IPTV Systems Roof Floor Plan Rev 1 Submittal 5 30-Apr-15 06-May-15 Voice, Data, IPTV Systems Roof Floor Plan Rev 1 Approval 7 07-May-15 14-May-15 M Mechanical Systems Shop Drawings 113 06-Apr-15 18-Aug-15 HVAC System Shop Drawings 33 06-Apr-15 14-May-15 HVAC System Roof Floor Plan Rev 0 Submittal 5 06-Apr-15 12-Apr-15 HVAC System Roof Floor Plan Rev 0 Reply 14 13-Apr-15 29-Apr-15 HVAC System Roof Floor Plan Rev 1 Submittal 5 30-Apr-15 06-May-15 HVAC System Roof Floor Plan Rev 1 Approval 7 07-May-15 14-May-15 Fire Fighting System Shop Drawings 33 06-Apr-15 14-May-15 Fire Fighting System Roof Floor Plan Rev 0 Submittal 5 06-Apr-15 12-Apr-15 Fire Fighting System Roof Floor Plan Rev 0 Reply 14 13-Apr-15 29-Apr-15 Fire Fighting System Roof Floor Plan Rev 1 Submittal 5 30-Apr-15 06-May-15 Fire Fighting System Roof Floor Plan Rev 1 Approval 7 07-May-15 14-May-15 Jun Jul Aug Sep Oct Nov Dec Qtr 3 Qtr 4 2014 SECON Nile Tower Project MEP Base Line Secon Nile Tower Project Siemens Scope 21-Mar-16 17:19 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 37 of 1076 TASK filter: All Activities © Primavera Systems, Inc
  • 20. Activity ID Activity Name Original Duration Start Finish Plumbing System Shop Drawings 36 06-Jul-15 18-Aug-15 Water Supply System Roof Floor Plan Rev 0 Submittal 5 06-Jul-15 12-Jul-15 Drainage System Roof Floor Plan Rev 0 Submittal 5 09-Jul-15 15-Jul-15 Water Supply System Roof Floor Plan Rev 0 Reply 14 13-Jul-15 30-Jul-15 Drainage System Roof Floor Plan Rev 0 Reply 14 16-Jul-15 03-Aug-15 Water Supply System Roof Floor Plan Rev 1 Submittal 5 02-Aug-15 06-Aug-15 Drainage System Roof Floor Plan Rev 1 Submittal 5 04-Aug-15 10-Aug-15 Water Supply System Roof Floor Plan Rev 1 Approval 7 08-Aug-15 15-Aug-15 Drainage System Roof Floor Plan Rev 1 Approval 7 11-Aug-15 18-Aug-15 C Composite Shop Drawings 33 19-Aug-15 28-Sep-15 Composite Drawing for Roof Floor Plan Rev 0 Submittal 5 19-Aug-15 25-Aug-15 Composite Drawing for Roof Floor Plan Rev 0 Reply 14 26-Aug-15 10-Sep-15 Composite Drawing for Roof Floor Plan Rev 1 Submittal 5 13-Sep-15 17-Sep-15 Composite Drawing for Roof Floor Plan Rev 1 Approval 7 19-Sep-15 28-Sep-15 Gen General 371 13-Jul-14 28-Sep-15 Ele Electrical 333 13-Jul-14 12-Aug-15 E Electrical Typical Installation Details 303 13-Jul-14 06-Jul-15 Submittal of Lighting System Typical Installation Details Rev 0 5 13-Jul-14 20-Jul-14 Submittal of Low Current Systems Typical Installation Details Rev 0 5 13-Jul-14 20-Jul-14 Submittal of Power System Typical Installation Details Rev 0 5 15-Jul-14 22-Jul-14 Reply of Lighting System Typical Installation Details Rev 0 14 20-Jul-14 06-Aug-14 Reply of Low Current Systems Typical Installation Details Rev 0 14 20-Jul-14 06-Aug-14 Reply of Power System Typical Installation Details Rev 0 14 22-Jul-14 09-Aug-14 Submittal of Lighting System Typical Installation Details Rev 1 5 06-Aug-14 13-Aug-14 Submittal of Low Current Systems Typical Installation Details Rev 1 5 06-Aug-14 13-Aug-14 Submittal of Power System Typical Installation Details Rev 1 5 10-Aug-14 14-Aug-14 Approval of Lighting System Typical Installation Details Rev 1 7 13-Aug-14 21-Aug-14 Approval of Low Current Systems Typical Installation Details Rev 1 7 13-Aug-14 21-Aug-14 Approval of Power System Typical Installation Details Rev 1 7 16-Aug-14 23-Aug-14 Electrical Enlarge Plans 67 19-Apr-15 06-Jul-15 Submittal of Guest Rooms Lighting System Rev 0 5 19-Apr-15 23-Apr-15 Submittal of Guest Rooms IT System Rev 0 5 19-Apr-15 23-Apr-15 Submittal of Guest Rooms Power System Rev 0 5 23-Apr-15 29-Apr-15 Reply of Guest Rooms Lighting System Rev 0 14 26-Apr-15 11-May-15 Reply of Guest Rooms IT System Rev 0 14 26-Apr-15 11-May-15 Reply of Guest Rooms Power System Rev 0 14 30-Apr-15 16-May-15 Submittal of Guest Rooms Lighting System Rev 1 5 12-May-15 18-May-15 Jun Jul Aug Sep Oct Nov Dec Qtr 3 Qtr 4 2014 SECON Nile Tower Project MEP Base Line Secon Nile Tower Project Siemens Scope 21-Mar-16 17:19 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 39 of 1076 TASK filter: All Activities © Primavera Systems, Inc
  • 21. Activity ID Activity Name Original Duration Start Finish Submittal of Guest Rooms IT System Rev 1 5 12-May-15 18-May-15 Submittal of Guest Rooms Power System Rev 1 5 17-May-15 21-May-15 Approval of Guest Rooms Lighting System Rev 1 7 19-May-15 26-May-15 Approval of Guest Rooms IT System Rev 1 7 19-May-15 26-May-15 Approval of Guest Rooms Power System Rev 1 7 23-May-15 30-May-15 Submittal of Room Management System Rev 0 5 31-May-15 04-Jun-15 Reply of Room Management System Rev 0 14 06-Jun-15 21-Jun-15 Submittal of Room Management System Rev 1 5 22-Jun-15 28-Jun-15 Approval of Room Management System Rev 1 7 29-Jun-15 06-Jul-15 E Electrical Single Line Diagrams 97 19-Apr-15 12-Aug-15 Power System 33 20-May-15 27-Jun-15 Power Single Line Diagram Submittal Rev 0 5 20-May-15 26-May-15 LVP, MDB's and Floors Panel Boards Submittal Rev 0 5 20-May-15 26-May-15 Power Risers (Bus Bar Details) Submittal Rev 0 5 20-May-15 26-May-15 Power Single Line Diagram Reply Rev 0 14 27-May-15 11-Jun-15 LVP, MDB's and Floors Panel Boards Reply Rev 0 14 27-May-15 11-Jun-15 Power Risers (Bus Bar Details) Reply Rev 0 14 27-May-15 11-Jun-15 Power Single Line Diagram Submittal Rev 1 5 14-Jun-15 18-Jun-15 LVP, MDB's and Floors Panel Boards Submittal Rev 1 5 14-Jun-15 18-Jun-15 Power Risers (Bus Bar Details) Submittal Rev 1 5 14-Jun-15 18-Jun-15 Power Single Line Diagram Approval Rev 1 7 20-Jun-15 27-Jun-15 LVP, MDB's and Floors Panel Boards Approval Rev 1 7 20-Jun-15 27-Jun-15 Power Risers (Bus Bar Details) Approval Rev 1 7 20-Jun-15 27-Jun-15 Lighting System 91 19-Apr-15 05-Aug-15 Dimming Control Schematic Diagram Submittal Rev 0 5 19-Apr-15 23-Apr-15 Dimming Control Schematic Diagram Reply Rev 0 14 26-Apr-15 11-May-15 Dimming Control Schematic Diagram Submittal Rev 1 5 12-May-15 18-May-15 Dimming Control Schematic Diagram Approval Rev 1 7 19-May-15 26-May-15 Central Battery Schematic Diagram Submittal Rev 0 5 28-Jun-15 02-Jul-15 Central Battery Schematic Diagram Reply Rev 0 14 04-Jul-15 20-Jul-15 Central Battery Schematic Diagram Submittal Rev 1 5 21-Jul-15 28-Jul-15 Central Battery Schematic Diagram Approval Rev 1 7 29-Jul-15 05-Aug-15 Low Current Systems 97 19-Apr-15 12-Aug-15 IPTV, Data , IPTEL S.L.D 32 19-Apr-15 26-May-15 IPTV, Data, IPTEL Single Line Diagram Submittal Rev 0 5 19-Apr-15 23-Apr-15 IPTV, Data, IPTEL Single Line Diagram Reply Rev 0 14 26-Apr-15 11-May-15 IPTV, Data, IPTEL Single Line Diagram Submittal Rev 1 5 12-May-15 18-May-15 IPTV, Data, IPTEL Single Line Diagram Approval Rev 1 7 19-May-15 26-May-15 Jun Jul Aug Sep Oct Nov Dec Qtr 3 Qtr 4 2014 SECON Nile Tower Project MEP Base Line Secon Nile Tower Project Siemens Scope 21-Mar-16 17:19 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 41 of 1076 TASK filter: All Activities © Primavera Systems, Inc
  • 22. Activity ID Activity Name Original Duration Start Finish TEL System S.L.D 32 19-Apr-15 26-May-15 Telephone System Single Line Diagram Submittal Rev 0 5 19-Apr-15 23-Apr-15 Telephone System Single Line Diagram Reply Rev 0 14 26-Apr-15 11-May-15 Telephone System Single Line Diagram Submittal Rev 1 5 12-May-15 18-May-15 Telephone System Single Line Diagram Approval Rev 1 7 19-May-15 26-May-15 MATV System S.L.D 33 19-May-15 25-Jun-15 MATV Single Line Diagram Submittal Rev 0 5 19-May-15 25-May-15 MATV Single Line Diagram Reply Rev 0 14 26-May-15 10-Jun-15 MATV Single Line Diagram Submittal Rev 1 5 11-Jun-15 17-Jun-15 MATV Single Line Diagram Approval Rev 1 7 18-Jun-15 25-Jun-15 Sound System S.L.D 32 17-May-15 22-Jun-15 Sound System Single Line Diagram Submittal Rev 0 5 17-May-15 21-May-15 Sound System Single Line Diagram Reply Rev 0 14 23-May-15 07-Jun-15 Sound System Single Line Diagram Submittal Rev 1 5 08-Jun-15 14-Jun-15 Sound System Single Line Diagram Approval Rev 1 7 15-Jun-15 22-Jun-15 CCTV System S.L.D 33 15-Jun-15 25-Jul-15 CCTV System Single Line Diagram Submittal Rev 0 5 15-Jun-15 21-Jun-15 CCTV System Single Line Diagram Reply Rev 0 14 22-Jun-15 07-Jul-15 CCTV System Single Line Diagram Submittal Rev 1 5 08-Jul-15 14-Jul-15 CCTV System Single Line Diagram Approval Rev 1 7 15-Jul-15 25-Jul-15 Parking System S.L.D 33 27-May-15 04-Jul-15 Parking System Single Line Diagram Submittal Rev 0 5 27-May-15 02-Jun-15 Parking System Single Line Diagram Reply Rev 0 14 03-Jun-15 18-Jun-15 Parking System Single Line Diagram Submittal Rev 1 5 21-Jun-15 25-Jun-15 Parking System Single Line Diagram Approval Rev 1 7 27-Jun-15 04-Jul-15 Audio Video Intercom S.L.D 32 05-Jul-15 12-Aug-15 Audio Video Intercom System Single Line Diagram Submittal Rev 0 5 05-Jul-15 09-Jul-15 Audio Video Intercom System Single Line Diagram Reply Rev 0 14 11-Jul-15 28-Jul-15 Audio Video Intercom System Single Line Diagram Submittal Rev 1 5 29-Jul-15 04-Aug-15 Audio Video Intercom System Single Line Diagram Approval Rev 1 7 05-Aug-15 12-Aug-15 Fire Alarm S.L.D 32 17-May-15 22-Jun-15 Fire Alarm System Single Line Diagram Submittal Rev 0 5 17-May-15 21-May-15 Fire Alarm System Single Line Diagram Reply Rev 0 14 23-May-15 07-Jun-15 Fire Alarm System Single Line Diagram Submittal Rev 1 5 08-Jun-15 14-Jun-15 Fire Alarm System Single Line Diagram Approval Rev 1 7 15-Jun-15 22-Jun-15 E Electrical Rooms / Electrical Equipments Rooms 160 26-Jan-15 03-Aug-15 Electrical Rooms Layout 33 23-Feb-15 02-Apr-15 Submittal of Electrical Rooms Layout Rev 0 5 23-Feb-15 02-Mar-15 Reply of Electrical Rooms Layout Rev 0 14 02-Mar-15 18-Mar-15 Jun Jul Aug Sep Oct Nov Dec Qtr 3 Qtr 4 2014 SECON Nile Tower Project MEP Base Line Secon Nile Tower Project Siemens Scope 21-Mar-16 17:20 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 43 of 1076 TASK filter: All Activities © Primavera Systems, Inc
  • 23. Activity ID Activity Name Original Duration Start Finish Submittal of Electrical Rooms Layout Rev 1 5 18-Mar-15 25-Mar-15 Approval of Electrical Rooms Layout Rev 1 7 25-Mar-15 02-Apr-15 RMU Room Layout 33 23-Feb-15 02-Apr-15 Submittal of RMU Room Layout Rev 0 5 23-Feb-15 02-Mar-15 Reply of RMU Room Layout Rev 0 14 02-Mar-15 18-Mar-15 Submittal of RMU Room Layout Rev 1 5 18-Mar-15 25-Mar-15 Approval of RMU Room Layout Rev 1 7 25-Mar-15 02-Apr-15 Medium Voltage Distributor (MVSG) Room Layout 33 23-Feb-15 02-Apr-15 Submittal of MVSG Room Layout Rev 0 5 23-Feb-15 02-Mar-15 Reply of MVSG Room Layout Rev 0 14 02-Mar-15 18-Mar-15 Submittal of MVSG Room Layout Rev 1 5 18-Mar-15 25-Mar-15 Approval of MVSG Room Layout Rev 1 7 25-Mar-15 02-Apr-15 Transformers Room Layout 33 26-Jan-15 04-Mar-15 Submittal of Transformers Room Layout Rev 0 5 26-Jan-15 01-Feb-15 Reply of Transformers Room Layout Rev 0 14 02-Feb-15 17-Feb-15 Submittal of Transformers Room Layout Rev 1 5 18-Feb-15 24-Feb-15 Approval of Transformers Room Layout Rev 1 7 25-Feb-15 04-Mar-15 Generator Room Layout 33 10-Mar-15 16-Apr-15 Submittal of Generator Room Layout Rev 0 5 10-Mar-15 16-Mar-15 Reply of Generator Room Layout Rev 0 14 17-Mar-15 01-Apr-15 Submittal of Generator Room Layout Rev 1 5 02-Apr-15 08-Apr-15 Approval of Generator Room Layout Rev 1 7 09-Apr-15 16-Apr-15 IT Rooms (IDF) Layout 33 26-Jan-15 04-Mar-15 Submittal of IT Rooms Layout Rev 0 5 26-Jan-15 01-Feb-15 Reply of IT Rooms Layout Rev 0 14 02-Feb-15 17-Feb-15 Submittal of IT Rooms Layout Rev 1 5 18-Feb-15 24-Feb-15 Approval of IT Rooms Layout Rev 1 7 25-Feb-15 04-Mar-15 Security Room Layout 34 23-Jun-15 03-Aug-15 Submittal of Security Room Layout Rev 0 5 23-Jun-15 29-Jun-15 Reply of Security Room Layout Rev 0 14 30-Jun-15 15-Jul-15 Submittal of Security Room Layout Rev 1 5 19-Jul-15 26-Jul-15 Approval of Security Room Layout Rev 1 7 27-Jul-15 03-Aug-15 Me Mechanical 371 13-Jul-14 28-Sep-15 M Mechanical Typical Installation Details 35 13-Jul-14 23-Aug-14 HVAC Typical Installation Details 33 13-Jul-14 21-Aug-14 Submittal of HVAC System Typical Installation Details Rev 0 5 13-Jul-14 20-Jul-14 Reply of HVAC System Typical Installation Details Rev 0 14 20-Jul-14 06-Aug-14 Submittal of HVAC System Typical Installation Details Rev 1 5 06-Aug-14 13-Aug-14 Jun Jul Aug Sep Oct Nov Dec Qtr 3 Qtr 4 2014 SECON Nile Tower Project MEP Base Line Secon Nile Tower Project Siemens Scope 21-Mar-16 17:20 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 45 of 1076 TASK filter: All Activities © Primavera Systems, Inc
  • 24. Activity ID Activity Name Original Duration Start Finish Approval of HVAC System Typical Installation Details Rev 1 7 13-Aug-14 21-Aug-14 Fire Fighting Typical Installation Details 33 13-Jul-14 21-Aug-14 Submittal of Fire Fighting System Typical Installation Details Rev 0 5 13-Jul-14 20-Jul-14 Reply of Fire Fighting System Typical Installation Details Rev 0 14 20-Jul-14 06-Aug-14 Submittal of Fire Fighting System Typical Installation Details Rev 1 5 06-Aug-14 13-Aug-14 Approval of Fire Fighting System Typical Installation Details Rev 1 7 13-Aug-14 21-Aug-14 Plumbing Typical Installation Details 35 13-Jul-14 23-Aug-14 Submittal of Water Supply System Typical Installation Details Rev 0 5 13-Jul-14 20-Jul-14 Submittal of Drainage System Typical Installation Details Rev 0 5 15-Jul-14 22-Jul-14 Reply of Water Supply System Typical Installation Details Rev 0 14 20-Jul-14 06-Aug-14 Reply of Drainage System Typical Installation Details Rev 0 14 22-Jul-14 09-Aug-14 Submittal of Water Supply System Typical Installation Details Rev 1 5 06-Aug-14 13-Aug-14 Submittal of Drainage System Typical Installation Details Rev 1 5 10-Aug-14 14-Aug-14 Approval of Water Supply System Typical Installation Details Rev 1 7 13-Aug-14 21-Aug-14 Approval of Drainage System Typical Installation Details Rev 1 7 16-Aug-14 23-Aug-14 M Mechanical Risers 112 17-May-15 28-Sep-15 HVAC Risers 32 17-May-15 22-Jun-15 Chilled Water Riser Diagram Submittal Rev 0 5 17-May-15 21-May-15 Fresh Air Riser Diagram Submittal Rev 0 5 17-May-15 21-May-15 Exhaust Air Riser Diagram Submittal Rev 0 5 17-May-15 21-May-15 A.H.U Riser Diagram Submittal Rev 0 5 17-May-15 21-May-15 Chilled Water Riser Diagram Reply Rev 0 14 23-May-15 07-Jun-15 Fresh Air Riser Diagram Reply Rev 0 14 23-May-15 07-Jun-15 Exhaust Air Riser Diagram Reply Rev 0 14 23-May-15 07-Jun-15 A.H.U Riser Diagram Reply Rev 0 14 23-May-15 07-Jun-15 Chilled Water Riser Diagram Submittal Rev 1 5 08-Jun-15 14-Jun-15 Fresh Air Riser Diagram Submittal Rev 1 5 08-Jun-15 14-Jun-15 Exhaust Air Riser Diagram Submittal Rev 1 5 08-Jun-15 14-Jun-15 A.H.U Riser Diagram Submittal Rev 1 5 08-Jun-15 14-Jun-15 Chilled Water Riser Diagram Approval Rev 1 7 15-Jun-15 22-Jun-15 Fresh Air Riser Diagram Approval Rev 1 7 15-Jun-15 22-Jun-15 Exhaust Air Riser Diagram Approval Rev 1 7 15-Jun-15 22-Jun-15 A.H.U Riser Diagram Approval Rev 1 7 15-Jun-15 22-Jun-15 Fire Fighting Risers 32 17-May-15 22-Jun-15 Fire Fighting Riser Diagram Submittal Rev 0 5 17-May-15 21-May-15 Fire Fighting Riser Diagram Reply Rev 0 14 23-May-15 07-Jun-15 Fire Fighting Riser Diagram Submittal Rev 1 5 08-Jun-15 14-Jun-15 Fire Fighting Riser Diagram Approval Rev 1 7 15-Jun-15 22-Jun-15 Jun Jul Aug Sep Oct Nov Dec Qtr 3 Qtr 4 2014 SECON Nile Tower Project MEP Base Line Secon Nile Tower Project Siemens Scope 21-Mar-16 17:20 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 47 of 1076 TASK filter: All Activities © Primavera Systems, Inc
  • 25. Activity ID Activity Name Original Duration Start Finish Drainage Risers 33 19-Aug-15 28-Sep-15 Drainage Riser Diagram Submittal Rev 0 5 19-Aug-15 25-Aug-15 Drainage Riser Diagram Reply Rev 0 14 26-Aug-15 10-Sep-15 Drainage Riser Diagram Submittal Rev 1 5 13-Sep-15 17-Sep-15 Drainage Riser Diagram Approval Rev 1 7 19-Sep-15 28-Sep-15 Water Supply Risers 32 16-Aug-15 21-Sep-15 Water Supply Riser Diagram Submittal Rev 0 5 16-Aug-15 20-Aug-15 Water Supply Riser Diagram Reply Rev 0 14 22-Aug-15 06-Sep-15 Water Supply Riser Diagram Submittal Rev 1 5 07-Sep-15 13-Sep-15 Water Supply Riser Diagram Approval Rev 1 7 14-Sep-15 21-Sep-15 M Mechanical Equipments Rooms & Calcluations 184 17-Sep-14 23-Apr-15 HVAC System Calculations 109 22-Sep-14 31-Jan-15 Chilled Water Pumps Head Calculations Submittal Rev 0 15 22-Sep-14 14-Oct-14 F.C.U Static Head Calculations Submittal Rev 0 15 02-Oct-14 26-Oct-14 Chilled Water Pumps Head Calculations Reply Rev 0 14 14-Oct-14 30-Oct-14 Cooling Tower Capacity & Pumps Head Calculations Submittal Rev 0 15 13-Oct-14 03-Nov-14 F.C.U Static Head Calculations Reply Rev 0 14 26-Oct-14 11-Nov-14 Expansion Tank Calculations Submittal Rev 0 15 27-Oct-14 17-Nov-14 Cooling Tower Capacity & Pumps Head Calculations Reply Rev 0 14 03-Nov-14 19-Nov-14 Chilled Water Pumps Head Calculations Submittal Rev 1 15 30-Oct-14 20-Nov-14 Chilled Water Pumps Head Calculations Approval Rev 1 7 20-Nov-14 29-Nov-14 F.C.U Static Head Calculations Submittal Rev 1 15 11-Nov-14 02-Dec-14 Expansion Tank Calculations Reply Rev 0 14 17-Nov-14 03-Dec-14 Cooling Tower Capacity & Pumps Head Calculations Submittal Rev 1 15 19-Nov-14 10-Dec-14 F.C.U Static Head Calculations Approval Rev 1 7 02-Dec-14 10-Dec-14 Supply & Exhaust Fans Static Head Calculations Submittal Rev 0 15 23-Nov-14 14-Dec-14 A.H.U Static Head Calculations Submittal Rev 0 15 23-Nov-14 14-Dec-14 Cooling Tower Capacity & Pumps Head Calculations Approval Rev 1 7 10-Dec-14 18-Dec-14 Expansion Tank Calculations Submittal Rev 1 15 03-Dec-14 24-Dec-14 Supply & Exhaust Fans Static Head Calculations Reply Rev 0 14 14-Dec-14 30-Dec-14 A.H.U Static Head Calculations Reply Rev 0 14 14-Dec-14 30-Dec-14 Expansion Tank Calculations Approval Rev 1 7 24-Dec-14 01-Jan-15 Supply & Exhaust Fans Static Head Calculations Submittal Rev 1 15 30-Dec-14 21-Jan-15 A.H.U Static Head Calculations Submittal Rev 1 15 30-Dec-14 21-Jan-15 Supply & Exhaust Fans Static Head Calculations Approval Rev 1 7 21-Jan-15 31-Jan-15 A.H.U Static Head Calculations Approval Rev 1 7 21-Jan-15 31-Jan-15 HVAC System Equipments 60 30-Nov-14 10-Feb-15 Chiller Plant & AHU Sections and Details Submittal Rev. 0 10 30-Nov-14 11-Dec-14 Jun Jul Aug Sep Oct Nov Dec Qtr 3 Qtr 4 2014 SECON Nile Tower Project MEP Base Line Secon Nile Tower Project Siemens Scope 21-Mar-16 17:20 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 49 of 1076 TASK filter: All Activities © Primavera Systems, Inc
  • 26. Activity ID Activity Name Original Duration Start Finish Chiller Plant & AHU Sections and Details Approval Rev. 0 10 13-Dec-14 23-Dec-14 Cooling Tower Plant Sections and Details Submittal Rev.0 10 18-Dec-14 01-Jan-15 Chiller Plant & AHU Sections and Details Submittal Rev. 1 10 24-Dec-14 06-Jan-15 Cooling Tower Plant Sections and Details Approval Rev.0 10 01-Jan-15 14-Jan-15 Chiller Plant & AHU Sections and Details Approval Rev. 1 10 08-Jan-15 19-Jan-15 Cooling Tower Plant Sections and Details Submittal Rev.1 10 14-Jan-15 29-Jan-15 Cooling Tower Plant Sections and Details Approval Rev.1 10 29-Jan-15 10-Feb-15 FF System Calculations 57 01-Oct-14 08-Dec-14 Fire Fighting Pumps Head Calculations Submittal Rev 0 15 01-Oct-14 23-Oct-14 Fire Fighting Pumps Head Calculations Reply Rev 0 14 23-Oct-14 09-Nov-14 Fire Fighting Pumps Head Calculations Submittal Rev 1 15 09-Nov-14 30-Nov-14 Fire Fighting Pumps Head Calculations Approval Rev 1 7 30-Nov-14 08-Dec-14 FF System Equipments 44 22-Dec-14 14-Feb-15 Fire Fighting Pumps Plant Sections and Details Submittal Rev.0 10 22-Dec-14 05-Jan-15 Fire Fighting Pumps Plant Sections and Details Approval Rev.0 10 05-Jan-15 18-Jan-15 Fire Fighting Pumps Plant Sections and Details Submittal Rev.1 10 18-Jan-15 02-Feb-15 Fire Fighting Pumps Plant Sections and Details Approval Rev.1 10 02-Feb-15 14-Feb-15 Plumbing System Calculations 121 17-Sep-14 09-Feb-15 Plumbing Pumps Head Calculations Approval Rev 1 7 17-Sep-14 25-Sep-14 Plumbing Pumps Head Calculations Submittal Rev 0 15 10-Dec-14 31-Dec-14 Plumbing Pumps Head Calculations Reply Rev 0 14 31-Dec-14 18-Jan-15 Plumbing Pumps Head Calculations Submittal Rev 1 15 18-Jan-15 09-Feb-15 Plumbing System Equipments 44 03-Mar-15 23-Apr-15 Plumbing Pumps Plant Sections and Details Submittal Rev.0 10 03-Mar-15 17-Mar-15 Plumbing Pumps Plant Sections and Details Approval Rev.0 10 17-Mar-15 29-Mar-15 Plumbing Pumps Plant Sections and Details Submittal Rev.1 10 29-Mar-15 12-Apr-15 Plumbing Pumps Plant Sections and Details Approval Rev.1 10 12-Apr-15 23-Apr-15 B BMS System 137 31-Dec-14 13-Jun-15 Boiler Plant Sections and Details Submittal Rev.0 10 08-Feb-15 19-Feb-15 Boiler Pumps Plant Sections and Details Approval Rev.0 10 21-Feb-15 03-Mar-15 Boiler Pumps Plant Sections and Details Submittal Rev.1 10 04-Mar-15 17-Mar-15 Boiler Pumps Plant Sections and Details Approval Rev.1 10 18-Mar-15 29-Mar-15 BMS S.L.D 45 31-Dec-14 24-Feb-15 BMS S.L.D Submittal Rev 0 10 31-Dec-14 15-Jan-15 BMS S.L.D Reply Rev 0 14 15-Jan-15 02-Feb-15 BMS S.L.D Submittal Rev 1 10 02-Feb-15 16-Feb-15 BMS S.L.D Approval Rev 1 7 16-Feb-15 24-Feb-15 BMS For Floors 92 24-Feb-15 13-Jun-15 Jun Jul Aug Sep Oct Nov Dec Qtr 3 Qtr 4 2014 SECON Nile Tower Project MEP Base Line Secon Nile Tower Project Siemens Scope 21-Mar-16 17:20 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 51 of 1076 TASK filter: All Activities © Primavera Systems, Inc
  • 27. Activity ID Activity Name Original Duration Start Finish BMS Submittal Rev. 0 65 24-Feb-15 12-May-15 BMS Submittal For Lower Basement Floor Rev 0 5 24-Feb-15 03-Mar-15 BMS Submittal For Upper Basement Floor Rev 0 5 03-Mar-15 10-Mar-15 BMS Submittal For Lower Ground Floor Rev 0 5 10-Mar-15 17-Mar-15 BMS Submittal For Ground Floor Rev 0 5 17-Mar-15 24-Mar-15 BMS Submittal For First Floor Rev 0 5 24-Mar-15 31-Mar-15 BMS Submittal For Second Floor Rev 0 5 31-Mar-15 07-Apr-15 BMS Submittal For Third Floor Rev 0 5 07-Apr-15 14-Apr-15 BMS Submittal For Typical Floors (4:20) Rev 0 5 14-Apr-15 21-Apr-15 BMS Submittal For Twenty First Floor Rev 0 5 21-Apr-15 28-Apr-15 BMS Submittal For Twenty Second Floor Rev 0 5 28-Apr-15 05-May-15 BMS Submittal For Roof Floor Rev 0 5 05-May-15 12-May-15 BMS Submittal Rev. 1 65 19-Mar-15 04-Jun-15 BMS Submittal For Lower Basement Floor Rev 1 5 19-Mar-15 26-Mar-15 BMS Submittal For Upper Basement Floor Rev 1 5 26-Mar-15 02-Apr-15 BMS Submittal For Lower Ground Floor Rev 1 5 02-Apr-15 09-Apr-15 BMS Submittal For Ground Floor Rev 1 5 09-Apr-15 16-Apr-15 BMS Submittal For First Floor Rev 1 5 16-Apr-15 23-Apr-15 BMS Submittal For Second Floor Rev 1 5 23-Apr-15 30-Apr-15 BMS Submittal For Third Floor Rev 1 5 03-May-15 07-May-15 BMS Submittal For Typical Floors (4:20) Rev 1 5 10-May-15 14-May-15 BMS Submittal For Twenty First Floor Rev 1 5 14-May-15 21-May-15 BMS Submittal For Twenty Second Floor Rev 1 5 21-May-15 28-May-15 BMS Submittal For Roof Floor Rev 1 5 28-May-15 04-Jun-15 BMS Approval Rev. 0 73 03-Mar-15 28-May-15 BMS Reply For Lower Basement Floor Rev 0 14 03-Mar-15 19-Mar-15 BMS Reply For Upper Basement Floor Rev 0 14 10-Mar-15 26-Mar-15 BMS Reply For Lower Ground Floor Rev 0 14 17-Mar-15 02-Apr-15 BMS Reply For Ground Floor Rev 0 14 24-Mar-15 09-Apr-15 BMS Reply For First Floor Rev 0 14 31-Mar-15 16-Apr-15 BMS Reply For Second Floor Rev 0 14 07-Apr-15 23-Apr-15 BMS Reply For Third Floor Rev 0 14 14-Apr-15 02-May-15 BMS Reply For Typical Floors (4:20) Rev 0 14 21-Apr-15 09-May-15 BMS Reply For Twenty First Floor Rev 0 14 28-Apr-15 14-May-15 BMS Reply For Twenty Second Floor Rev 0 14 05-May-15 21-May-15 BMS Reply For Roof Floor Rev 0 14 12-May-15 28-May-15 BMS Approval Rev. 1 66 26-Mar-15 13-Jun-15 BMS Approval For Lower Basement Floor Rev 1 7 26-Mar-15 04-Apr-15 BMS Approval For Upper Basement Floor Rev 1 7 02-Apr-15 11-Apr-15 Jun Jul Aug Sep Oct Nov Dec Qtr 3 Qtr 4 2014 SECON Nile Tower Project MEP Base Line Secon Nile Tower Project Siemens Scope 21-Mar-16 17:20 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 53 of 1076 TASK filter: All Activities © Primavera Systems, Inc
  • 28. Activity ID Activity Name Original Duration Start Finish BMS Approval For Lower Ground Floor Rev 1 7 09-Apr-15 18-Apr-15 BMS Approval For Ground Floor Rev 1 7 16-Apr-15 26-Apr-15 BMS Approval For First Floor Rev 1 7 23-Apr-15 03-May-15 BMS Approval For Second Floor Rev 1 7 30-Apr-15 09-May-15 BMS Approval For Third Floor Rev 1 7 09-May-15 16-May-15 BMS Approval For Typical Floors (4:20) Rev 1 7 16-May-15 23-May-15 BMS Approval For Twenty First Floor Rev 1 7 21-May-15 30-May-15 BMS Approval For Twenty Second Floor Rev 1 7 28-May-15 06-Jun-15 BMS Approval For Roof Floor Rev 1 7 04-Jun-15 13-Jun-15 As B As Built Drawings And Operation Manuals 0 Procu Procurement 378 08-Jul-14 01-Oct-15 Elec Electrical Systems 378 08-Jul-14 01-Oct-15 SSM Siemens Receive Final Electrical Specifications Including MCC's 0 08-Jul-14 SSM Siemens Receive Final Electrical Vendor List 0 08-Jul-14 Po Power System 378 08-Jul-14 01-Oct-15 M Material Submittal 199 08-Jul-14 02-Mar-15 Rev 0 178 08-Jul-14 05-Feb-15 CABLE TRAYS MATERIAL SUBMITTAL REV 0 10 08-Jul-14 22-Jul-14 PVC Conduits & Back Boxes Material Submittal Rev 0 10 08-Jul-14 22-Jul-14 MEDIUM VOLTAGE CABLES MATERIAL SUBMITTAL REV 0 20 07-Sep-14 05-Oct-14 LOW VOLTAGE CABLES MATERIAL SUBMITTAL REV 0 20 07-Sep-14 05-Oct-14 Fire Resistance Cables Material Submittal Rev 0 20 07-Sep-14 05-Oct-14 Copper Wires For Sockets and Lighting Outlets Material Submittal Rev 0 20 07-Sep-14 05-Oct-14 Cooper Cables For Small Power Outlets Material Submittal Rev 0 20 07-Sep-14 05-Oct-14 Cable Accessories Material Submittal Rev 0 20 07-Sep-14 05-Oct-14 UPS Material Submittal Rev 0 20 23-Sep-14 22-Oct-14 BUS BAR TRUNKING MATERIAL SUBMITTAL REV 0 20 09-Oct-14 06-Nov-14 DISTRIBUTION TRANSFORMER MATERIAL SUBMITTAL REV 0 20 23-Nov-14 21-Dec-14 Disconnect Switches & Power Accessories Material Submittal Rev 0 20 07-Dec-14 04-Jan-15 Floor Mounted Skirting Box Material Submittal Rev 0 20 07-Dec-14 04-Jan-15 MV RING MAIN UNIT MATERIAL SUBMITTAL REV 0 20 21-Dec-14 19-Jan-15 MV DISTRIBUTOR MATERIAL SUBMITTAL REV 0 20 21-Dec-14 19-Jan-15 LOW VOLTAGE SWITCH GEAR & SWITCH BOARDS MATERIAL SUBMITTAL REV 0 20 21-Dec-14 19-Jan-15 DISTRIBUTION AND SUB DISTRIBUTION PANEL BOARD MATERIAL SUBMITTAL REV 0 20 21-Dec-14 19-Jan-15 STANDBY GENERATOR SET MATERIAL SUBMITTAL REV 0 20 05-Jan-15 04-Feb-15 Jun Jul Aug Sep Oct Nov Dec Qtr 3 Qtr 4 2014 SECON Nile Tower Project MEP Base Line Secon Nile Tower Project Siemens Scope 21-Mar-16 17:20 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 55 of 1076 TASK filter: All Activities © Primavera Systems, Inc
  • 29. Activity ID Activity Name Original Duration Start Finish ATS MATERIAL SUBMITTAL REV 0 20 05-Jan-15 04-Feb-15 Guest Room Management System Material Submittal Rev 0 20 06-Jan-15 05-Feb-15 Rev 1 172 10-Aug-14 02-Mar-15 CABLE TRAYS MATERIAL SUBMITTAL REV 1 6 10-Aug-14 17-Aug-14 PVC Conduits & Back Boxes Material Submittal Rev 1 6 10-Aug-14 18-Aug-14 MEDIUM VOLTAGE CABLES MATERIAL SUBMITTAL REV 1 6 22-Oct-14 30-Oct-14 LOW VOLTAGE CABLES MATERIAL SUBMITTAL REV 1 6 22-Oct-14 30-Oct-14 Fire Resistance Cables Material Submittal Rev 1 6 22-Oct-14 30-Oct-14 Copper Wires Material Submittal Rev 1 6 22-Oct-14 30-Oct-14 Cooper Cables For Small Power Outlets Material Submittal Rev 1 6 22-Oct-14 30-Oct-14 Cable Accessories Material Submittal Rev 1 6 22-Oct-14 30-Oct-14 UPS Material Submittal Rev 1 6 09-Nov-14 16-Nov-14 BUS BAR TRUNKING MATERIAL SUBMITTAL REV 1 6 23-Nov-14 01-Dec-14 DISTRIBUTION TRANSFORMER MATERIAL SUBMITTAL REV 1 6 06-Jan-15 15-Jan-15 Disconnect Switches & Power Accessories Material Submittal Rev 1 6 21-Jan-15 01-Feb-15 Floor Mounted Skirting Box Material Submittal Rev 1 6 21-Jan-15 01-Feb-15 MV RING MAIN UNIT MATERIAL SUBMITTAL REV 1 6 05-Feb-15 15-Feb-15 MV DISTRIBUTOR MATERIAL SUBMITTAL REV 1 6 05-Feb-15 15-Feb-15 LOW VOLTAGE SWITCH GEAR & SWITCH BOARDS MATERIAL SUBMITTAL REV 1 6 05-Feb-15 15-Feb-15 DISTRIBUTION AND SUB DISTRIBUTION PANEL BOARD MATERIAL SUBMITTAL REV 1 6 05-Feb-15 15-Feb-15 STANDBY GENERATOR SET MATERIAL SUBMITTAL REV 1 6 22-Feb-15 01-Mar-15 ATS MATERIAL SUBMITTAL REV 1 6 22-Feb-15 01-Mar-15 Guest Room Management System Material Submittal Rev 1 6 22-Feb-15 02-Mar-15 M Material Approvals 194 22-Jul-14 10-Mar-15 Rev 0 180 22-Jul-14 22-Feb-15 CABLE TRAYS MATERIAL REPLY REV 0 14 22-Jul-14 09-Aug-14 PVC Conduits & Back Boxes Material Reply Rev 0 14 22-Jul-14 09-Aug-14 MEDIUM VOLTAGE CABLES MATERIAL REPLY REV 0 14 05-Oct-14 22-Oct-14 LOW VOLTAGE CABLES MATERIAL REPLY REV 0 14 05-Oct-14 22-Oct-14 Fire Resistance Cables Material Reply Rev 0 14 05-Oct-14 22-Oct-14 Copper Wires Material Reply Rev 0 14 05-Oct-14 22-Oct-14 Cooper Cables For Small Power Outlets Material Reply Rev 0 14 05-Oct-14 22-Oct-14 Cable Accessories Material Reply Rev 0 14 05-Oct-14 22-Oct-14 UPS Material Reply Rev 0 14 22-Oct-14 08-Nov-14 BUS BAR TRUNKING MATERIAL REPLY REV 0 14 06-Nov-14 23-Nov-14 DISTRIBUTION TRANSFORMER MATERIAL REPLY REV 0 14 21-Dec-14 06-Jan-15 Disconnect Switches & Power Accessories Material Reply Rev 0 14 04-Jan-15 21-Jan-15 Jun Jul Aug Sep Oct Nov Dec Qtr 3 Qtr 4 2014 SECON Nile Tower Project MEP Base Line Secon Nile Tower Project Siemens Scope 21-Mar-16 17:20 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 57 of 1076 TASK filter: All Activities © Primavera Systems, Inc
  • 30. Activity ID Activity Name Original Duration Start Finish Floor Mounted Skirting Box Material Reply Rev 0 14 04-Jan-15 21-Jan-15 MV RING MAIN UNIT MATERIAL REPLY REV 0 14 19-Jan-15 05-Feb-15 MV DISTRIBUTOR MATERIAL REPLY REV 0 14 19-Jan-15 05-Feb-15 LOW VOLTAGE SWITCH GEAR & SWITCH BOARDS MATERIAL REPLY REV 0 14 19-Jan-15 05-Feb-15 DISTRIBUTION AND SUB DISTRIBUTION PANEL BOARD MATERIAL REPLY REV 0 14 19-Jan-15 05-Feb-15 STANDBY GENERATOR SET MATERIAL REPLY REV 0 14 04-Feb-15 21-Feb-15 ATS MATERIAL REPLY REV 0 14 04-Feb-15 21-Feb-15 Guest Room Management System Material Reply Rev 0 14 05-Feb-15 22-Feb-15 Rev 1 172 18-Aug-14 10-Mar-15 CABLE TRAYS MATERIALAPPROVAL REV 1 7 18-Aug-14 25-Aug-14 PVC Conduits & Back Boxes Material Approval Rev 1 7 18-Aug-14 26-Aug-14 MEDIUM VOLTAGE CABLES MATERIALAPPROVAL REV 1 7 30-Oct-14 08-Nov-14 LOW VOLTAGE CABLES MATERIAL APPROVAL REV 1 7 30-Oct-14 08-Nov-14 Fire Resistance Cables Material Approval Rev 1 7 30-Oct-14 08-Nov-14 Copper Wires Material Approval Rev 1 7 30-Oct-14 08-Nov-14 Cooper Cables For Small Power Outlets Material Approval Rev 1 7 30-Oct-14 08-Nov-14 Cable Accessories Material Approval Rev 1 7 30-Oct-14 08-Nov-14 UPS Material Approval Rev 1 7 17-Nov-14 24-Nov-14 BUS BAR TRUNKING MATERIALAPPROVAL REV 1 7 01-Dec-14 09-Dec-14 DISTRIBUTION TRANSFORMER MATERIALAPPROVAL REV 1 7 15-Jan-15 24-Jan-15 Disconnect Switches & Power Accessories Material Approval Rev 1 7 01-Feb-15 09-Feb-15 Floor Mounted Skirting Box Material Approval Rev 1 7 01-Feb-15 09-Feb-15 MV RING MAIN UNIT MATERIAL APPROVAL REV 1 7 15-Feb-15 23-Feb-15 MV DISTRIBUTOR MATERIAL APPROVAL REV 1 7 15-Feb-15 23-Feb-15 LOW VOLTAGE SWITCH GEAR & SWITCH BOARDS MATERIAL APPROVAL 7 15-Feb-15 23-Feb-15 DISTRIBUTION AND SUB DISTRIBUTION PANEL BOARD MATERIAL APPROVAL REV 1 7 15-Feb-15 23-Feb-15 STANDBY GENERATOR SET MATERIAL APPROVAL REV 1 7 02-Mar-15 09-Mar-15 ATS MATERIALAPPROVAL REV 1 7 02-Mar-15 09-Mar-15 Guest Room Management System Material Approval Rev 1 7 02-Mar-15 10-Mar-15 M Material PO's 221 26-Aug-14 14-May-15 PVC Conduits & Back Boxes Material PO 25 26-Aug-14 30-Sep-14 CABLE TRAYS MATERIAL PO 25 10-Sep-14 15-Oct-14 MEDIUM VOLTAGE CABLES MATERIAL PO 25 10-Nov-14 15-Dec-14 LOW VOLTAGE CABLES MATERIAL PO 25 10-Nov-14 15-Dec-14 Fire Resistance Cables Material PO 25 10-Nov-14 15-Dec-14 Copper Wires Material PO 25 10-Nov-14 15-Dec-14 Cooper Cables For Small Power Outlets Material PO 25 10-Nov-14 15-Dec-14 Jun Jul Aug Sep Oct Nov Dec Qtr 3 Qtr 4 2014 SECON Nile Tower Project MEP Base Line Secon Nile Tower Project Siemens Scope 21-Mar-16 17:20 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 59 of 1076 TASK filter: All Activities © Primavera Systems, Inc
  • 31. Activity ID Activity Name Original Duration Start Finish Cable Accessories Material PO 25 10-Nov-14 15-Dec-14 UPS Material PO 25 11-Dec-14 15-Jan-15 BUS BAR TRUNKING MATERIAL PO 25 24-Dec-14 01-Feb-15 DISTRIBUTION TRANSFORMER MATERIAL PO 25 08-Feb-15 15-Mar-15 Disconnect Switches & Power Accessories Material PO 25 25-Feb-15 01-Apr-15 Floor Mounted Skirting Box Material PO 25 25-Feb-15 01-Apr-15 MV RING MAIN UNIT MATERIAL PO 25 11-Mar-15 15-Apr-15 MV DISTRIBUTOR MATERIAL PO 25 11-Mar-15 15-Apr-15 LOW VOLTAGE SWITCH GEAR & SWITCH BOARDS MATERIAL PO 25 11-Mar-15 15-Apr-15 DISTRIBUTION AND SUB DISTRIBUTION PANEL BOARD MATERIAL PO 25 11-Mar-15 15-Apr-15 STANDBY GENERATOR SET MATERIAL PO 25 29-Mar-15 30-Apr-15 ATS MATERIAL PO 25 29-Mar-15 30-Apr-15 Guest Room Management System Material PO 25 12-Apr-15 14-May-15 M Material Delivery at Site 307 30-Sep-14 01-Oct-15 PVC Conduits & Back Boxes Material Delivery 14 30-Sep-14 18-Oct-14 CABLE TRAYS MATERIAL DELIVERY 40 16-Oct-14 01-Dec-14 MEDIUM VOLTAGE CABLES MATERIAL DELIVERY 75 15-Dec-14 15-Mar-15 LOW VOLTAGE CABLES MATERIAL DELIVERY 75 15-Dec-14 15-Mar-15 Fire Resistance Cables Material Delivery 75 15-Dec-14 15-Mar-15 Copper Wires Material Delivery 75 15-Dec-14 15-Mar-15 Cooper Cables For Small Power Outlets Material Delivery 75 15-Dec-14 15-Mar-15 Cable Accessories Material Delivery 75 15-Dec-14 15-Mar-15 UPS Material Delivery 76 17-Jan-15 15-Apr-15 BUS BAR TRUNKING MATERIAL DELIVERY 102 01-Feb-15 01-Jun-15 Disconnect Switches & Power Accessories Material Delivery 51 01-Apr-15 01-Jun-15 Floor Mounted Skirting Box Material Delivery 51 01-Apr-15 01-Jun-15 DISTRIBUTION TRANSFORMER MATERIAL DELIVERY 104 15-Mar-15 15-Jul-15 Guest Room Management System Material Delivery 77 16-May-15 15-Aug-15 MV RING MAIN UNIT MATERIAL DELIVERY 114 15-Apr-15 30-Aug-15 MV DISTRIBUTOR MATERIAL DELIVERY 114 15-Apr-15 30-Aug-15 LOW VOLTAGE SWITCH GEAR & SWITCH BOARDS MATERIAL DELIVERY 114 15-Apr-15 30-Aug-15 DISTRIBUTION AND SUB DISTRIBUTION PANEL BOARD MATERIAL DELIV 114 15-Apr-15 30-Aug-15 STANDBY GENERATOR SET MATERIAL DELIVERY 128 02-May-15 01-Oct-15 ATS MATERIAL DELIVERY 128 02-May-15 01-Oct-15 Lig Lighting System 281 02-Oct-14 02-Sep-15 M Material Submittal 126 02-Oct-14 02-Mar-15 Rev 0 105 02-Oct-14 05-Feb-15 Lighting Switches (Wiring Devices) Material Submittal Rev 0 20 02-Oct-14 02-Nov-14 Jun Jul Aug Sep Oct Nov Dec Qtr 3 Qtr 4 2014 SECON Nile Tower Project MEP Base Line Secon Nile Tower Project Siemens Scope 21-Mar-16 17:20 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 61 of 1076 TASK filter: All Activities © Primavera Systems, Inc
  • 32. Activity ID Activity Name Original Duration Start Finish Dimming System Material Submittal Rev 0 20 09-Oct-14 06-Nov-14 Lighting Fixtures Material Submittal Rev 0 20 10-Nov-14 08-Dec-14 Emergency Lighting Fixtures Material Submittal Rev 0 20 10-Nov-14 08-Dec-14 Addressable Central Battery Material Submittal Rev 0 20 06-Jan-15 05-Feb-15 Rev 1 87 18-Nov-14 02-Mar-15 Lighting Switches (Wiring Devices) Material Submittal Rev 1 6 18-Nov-14 26-Nov-14 Dimming System Material Submittal Rev 1 6 23-Nov-14 01-Dec-14 Lighting Fixtures Material Submittal Rev 1 6 24-Dec-14 01-Jan-15 Emergency Lighting Fixtures Material Submittal Rev 1 6 24-Dec-14 01-Jan-15 Addressable Central Battery Material Submittal Rev 1 6 22-Feb-15 02-Mar-15 M Material Approvals 108 02-Nov-14 10-Mar-15 Rev 0 94 02-Nov-14 22-Feb-15 Lighting Switches (Wiring Devices) Material Reply Rev 0 14 02-Nov-14 18-Nov-14 Dimming System Material Reply Rev 0 14 06-Nov-14 23-Nov-14 Lighting Fixtures Material Reply Rev 0 14 08-Dec-14 24-Dec-14 Emergency Lighting Fixtures Material Reply Rev 0 14 08-Dec-14 24-Dec-14 Addressable Central Battery Material Reply Rev 0 14 05-Feb-15 22-Feb-15 Rev 1 87 26-Nov-14 10-Mar-15 Lighting Switches (Wiring Devices) Material Approval Rev 1 7 26-Nov-14 04-Dec-14 Dimming System Material Approval Rev 1 7 01-Dec-14 09-Dec-14 Lighting Fixtures Material Approval Rev 1 7 01-Jan-15 11-Jan-15 Emergency Lighting Fixtures Material Approval Rev 1 7 01-Jan-15 11-Jan-15 Addressable Central Battery Material Approval Rev 1 7 02-Mar-15 10-Mar-15 M Material PO's 108 24-Dec-14 03-May-15 Dimming System Material PO 25 24-Dec-14 01-Feb-15 Lighting Fixtures Material PO 25 26-Jan-15 01-Mar-15 Emergency Lighting Fixtures Material PO 25 26-Jan-15 01-Mar-15 Lighting Switches (Wiring Devices) Material PO 25 25-Feb-15 01-Apr-15 Addressable Central Battery Material PO 25 29-Mar-15 03-May-15 M Material Delivery at Site 180 01-Feb-15 02-Sep-15 Lighting Switches (Wiring Devices) Material Delivery 51 01-Apr-15 01-Jun-15 Dimming System Material Delivery 102 01-Feb-15 01-Jun-15 Lighting Fixtures Material Delivery 78 02-Mar-15 01-Jun-15 Emergency Lighting Fixtures Material Delivery 78 02-Mar-15 01-Jun-15 Addressable Central Battery Material Delivery 103 03-May-15 02-Sep-15 Lig Light Current Systems 338 08-Jul-14 15-Aug-15 F Fire Alarm System 217 17-Sep-14 01-Jun-15 Jun Jul Aug Sep Oct Nov Dec Qtr 3 Qtr 4 2014 SECON Nile Tower Project MEP Base Line Secon Nile Tower Project Siemens Scope 21-Mar-16 17:20 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 63 of 1076 TASK filter: All Activities © Primavera Systems, Inc
  • 33. Activity ID Activity Name Original Duration Start Finish Material Submittal 75 17-Sep-14 15-Dec-14 Rev 0 36 17-Sep-14 30-Oct-14 Fire Alarm System Material Submittal Rev 0 20 17-Sep-14 16-Oct-14 Fire Alarm Wiring Material Submittal Rev 0 20 01-Oct-14 30-Oct-14 Rev 1 36 03-Nov-14 15-Dec-14 Fire Alarm System Material Submittal Rev 1 20 03-Nov-14 01-Dec-14 Fire Alarm Wiring Material Submittal Rev 1 20 17-Nov-14 15-Dec-14 Material Approvals 58 16-Oct-14 23-Dec-14 Rev 0 26 16-Oct-14 16-Nov-14 Fire Alarm System Material Reply Rev 0 14 16-Oct-14 02-Nov-14 Fire Alarm Wiring Material Reply Rev 0 14 30-Oct-14 16-Nov-14 Rev 1 19 01-Dec-14 23-Dec-14 Fire Alarm System Material Approval Rev 1 7 01-Dec-14 09-Dec-14 Fire Alarm Wiring Material Approval Rev 1 7 15-Dec-14 23-Dec-14 Material PO's 56 24-Dec-14 01-Mar-15 Fire Alarm Wiring Material PO 25 24-Dec-14 01-Feb-15 Fire Alarm System Material PO 25 26-Jan-15 01-Mar-15 Material Delivery at Site 103 01-Feb-15 01-Jun-15 Fire Alarm Wiring Material Delivery 36 01-Feb-15 15-Mar-15 Fire Alarm System Material Delivery 78 02-Mar-15 01-Jun-15 S Sound System Rack SSR 178 02-Nov-14 01-Jun-15 Material Submittal 71 02-Nov-14 26-Jan-15 Rev 0 31 02-Nov-14 08-Dec-14 Sound System Material Submittal Rev 0 20 02-Nov-14 30-Nov-14 Sound Wiring Material Submittal Rev 0 20 10-Nov-14 08-Dec-14 Rev 1 32 17-Dec-14 26-Jan-15 Sound System Material Submittal Rev 1 20 17-Dec-14 15-Jan-15 Sound Wiring Material Submittal Rev 1 20 25-Dec-14 26-Jan-15 Material Approvals 54 30-Nov-14 03-Feb-15 Rev 0 21 30-Nov-14 24-Dec-14 Sound System Material Reply Rev 0 14 30-Nov-14 16-Dec-14 Sound Wiring Material Reply Rev 0 14 08-Dec-14 24-Dec-14 Rev 1 15 15-Jan-15 03-Feb-15 Sound System Material Approval Rev 1 7 15-Jan-15 24-Jan-15 Sound Wiring Material Approval Rev 1 7 26-Jan-15 03-Feb-15 Material PO's 45 08-Feb-15 01-Apr-15 Sound System Material PO 25 08-Feb-15 15-Mar-15 Sound Wiring Material PO 25 25-Feb-15 01-Apr-15 Material Delivery at Site 65 16-Mar-15 01-Jun-15 Jun Jul Aug Sep Oct Nov Dec Qtr 3 Qtr 4 2014 SECON Nile Tower Project MEP Base Line Secon Nile Tower Project Siemens Scope 21-Mar-16 17:20 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 65 of 1076 TASK filter: All Activities © Primavera Systems, Inc
  • 34. Activity ID Activity Name Original Duration Start Finish Sound Wiring Material Delivery 35 02-Apr-15 14-May-15 Sound System Material Delivery 65 16-Mar-15 01-Jun-15 A Audio Visual system for Multi Purpose Hall 176 18-Nov-14 15-Jun-15 Material Submittal 63 18-Nov-14 02-Feb-15 Rev 0 24 18-Nov-14 16-Dec-14 Audio Visual system Material Submittal Rev 0 20 18-Nov-14 16-Dec-14 Rev 1 25 01-Jan-15 02-Feb-15 Audio Visual system Material Submittal Rev 1 20 01-Jan-15 02-Feb-15 Material Approvals 46 16-Dec-14 10-Feb-15 Rev 0 14 16-Dec-14 01-Jan-15 Audio Visual system Material Reply Rev 0 14 16-Dec-14 01-Jan-15 Rev 1 7 02-Feb-15 10-Feb-15 Audio Visual system Material Approval Rev 1 7 02-Feb-15 10-Feb-15 Material PO's 30 25-Feb-15 01-Apr-15 Audio Visual system Material PO 25 25-Feb-15 01-Apr-15 Material Delivery at Site 62 02-Apr-15 15-Jun-15 Audio Visual system Material Delivery 62 02-Apr-15 15-Jun-15 C CCTV System 178 02-Nov-14 01-Jun-15 Material Submittal 71 02-Nov-14 26-Jan-15 Rev 0 32 02-Nov-14 09-Dec-14 CCTV System Material Submittal Rev 0 20 02-Nov-14 30-Nov-14 CCTV Wiring Material Submittal Rev 0 20 11-Nov-14 09-Dec-14 Rev 1 33 16-Dec-14 26-Jan-15 CCTV System Material Submittal Rev 1 20 16-Dec-14 14-Jan-15 CCTV Wiring Material Submittal Rev 1 20 25-Dec-14 26-Jan-15 Material Approvals 54 30-Nov-14 03-Feb-15 Rev 0 22 30-Nov-14 25-Dec-14 CCTV System Material Reply Rev 0 14 30-Nov-14 16-Dec-14 CCTV Wiring Material Reply Rev 0 14 09-Dec-14 25-Dec-14 Rev 1 16 14-Jan-15 03-Feb-15 CCTV System Material Approval Rev 1 7 14-Jan-15 22-Jan-15 CCTV Wiring Material Approval Rev 1 7 26-Jan-15 03-Feb-15 Material PO's 30 08-Feb-15 15-Mar-15 CCTV System Material PO 25 08-Feb-15 15-Mar-15 CCTV Wiring Material PO 25 08-Feb-15 15-Mar-15 Material Delivery at Site 65 16-Mar-15 01-Jun-15 CCTV System Material Delivery 65 16-Mar-15 01-Jun-15 CCTV Wiring Material Delivery 65 16-Mar-15 01-Jun-15 Jun Jul Aug Sep Oct Nov Dec Qtr 3 Qtr 4 2014 SECON Nile Tower Project MEP Base Line Secon Nile Tower Project Siemens Scope 21-Mar-16 17:20 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 67 of 1076 TASK filter: All Activities © Primavera Systems, Inc
  • 35. Activity ID Activity Name Original Duration Start Finish L Light Current Cable Tray 124 08-Jul-14 01-Dec-14 Material Submittal 34 08-Jul-14 17-Aug-14 Rev 0 12 08-Jul-14 22-Jul-14 Light Current Cable Tray Material Submittal Rev 0 10 08-Jul-14 22-Jul-14 Rev 1 7 10-Aug-14 17-Aug-14 Light Current Cable Tray Material Submittal Rev 1 6 10-Aug-14 17-Aug-14 Material Approvals 29 22-Jul-14 25-Aug-14 Rev 0 14 22-Jul-14 09-Aug-14 Light Current Cable Tray Material Reply Rev 0 14 22-Jul-14 09-Aug-14 Rev 1 7 18-Aug-14 25-Aug-14 Light Current Cable Tray Material Approval Rev 1 7 18-Aug-14 25-Aug-14 Material PO's 30 10-Sep-14 15-Oct-14 Light Current Cable Tray Material PO 25 10-Sep-14 15-Oct-14 Material Delivery at Site 40 16-Oct-14 01-Dec-14 Light Current Cable Tray Material Delivery 40 16-Oct-14 01-Dec-14 S Structured Cabling system 173 22-Oct-14 14-May-15 Material Submittal 71 22-Oct-14 14-Jan-15 Rev 0 33 22-Oct-14 30-Nov-14 Structured Cabling System Material Submittal Rev 0 20 22-Oct-14 19-Nov-14 Structured Cabling Wiring Material Submittal Rev 0 20 02-Nov-14 30-Nov-14 Rev 1 32 07-Dec-14 14-Jan-15 Structured Cabling System Material Submittal Rev 1 20 07-Dec-14 01-Jan-15 Structured Cabling Wiring Material Submittal Rev 1 20 16-Dec-14 14-Jan-15 Material Approvals 54 19-Nov-14 22-Jan-15 Rev 0 23 19-Nov-14 16-Dec-14 Structured Cabling System Material Reply Rev 0 14 19-Nov-14 06-Dec-14 Structured Cabling Wiring Material Reply Rev 0 14 30-Nov-14 16-Dec-14 Rev 1 16 03-Jan-15 22-Jan-15 Structured Cabling System Material Approval Rev 1 7 03-Jan-15 11-Jan-15 Structured Cabling Wiring Material Approval Rev 1 7 14-Jan-15 22-Jan-15 Material PO's 44 22-Jan-15 15-Mar-15 Structured Cabling Wiring Material PO 25 22-Jan-15 01-Mar-15 Structured Cabling System Material PO 25 09-Feb-15 15-Mar-15 Material Delivery at Site 63 02-Mar-15 14-May-15 Structured Cabling Wiring Material Delivery 26 02-Mar-15 01-Apr-15 Structured Cabling System Material Delivery 50 17-Mar-15 14-May-15 T Telephone system for Residential Building 213 03-Sep-14 14-May-15 Material Submittal 76 03-Sep-14 02-Dec-14 Jun Jul Aug Sep Oct Nov Dec Qtr 3 Qtr 4 2014 SECON Nile Tower Project MEP Base Line Secon Nile Tower Project Siemens Scope 21-Mar-16 17:20 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 69 of 1076 TASK filter: All Activities © Primavera Systems, Inc