Activity ID Activity Name Original
Duration
Start Finish
Zewail City of
Zewail City of Science and Technology B4 Contract 577 02-May-15 13-Nov-16
General
General 577 02-May-15 13-Nov-16
ZB4G0010 Letter of Intent 0 02-May-15
ZB4G0020 Receive Final Design Drawings and Specifications 0 03-May-15
ZB4G0030 Down Payment 0 24-May-15
ZB4G0040 Letter of Award 0 24-May-15
ZB4G0060 Full Release Service Tunnel For MEP Works 0 06-Jun-15
ZB4G0062 Release Building B4-A For MEP Work ( Masonry Works ) 0 14-Jun-15
ZB4G0064 Release Building B4-B For MEPWork ( Masonry Works ) 0 14-Jun-15
ZB4G0050 Mobilization 15 30-May-15 15-Jun-15
ZB4G0066 Release Building B4-D For MEPWork ( Masonry Works ) 0 01-Jul-15
ZB4G0068 Release Building B4-E For MEPWork ( Masonry Works ) 0 01-Jul-15
ZB4G0070 Provide Permanent Electrical / Gas / Water / Drainage Sources 0 15-Aug-15
ZB4G0076 Release Building B4-D Finishing Work ( For Equipment Installation ) 0 18-Aug-15
ZB4G0074 Release Building B4-B Finishing Work ( For Equipment Installation ) 0 01-Sep-15
ZB4G0072 Release Building B4-A Finishing Work ( For Equipment Installation ) 0 05-Sep-15
ZB4G0078 Release Building B4-E Finishing Work ( For Equipment Installation ) 0 05-Sep-15
ZB4G0088 Release Site Layout For MEPWork ( MV, LV and SCADA Networks Works
)
0 04-Nov-15
ZB4G0098 Release Site Layout For MEPWork ( Solar LED Exterior Lighting Works ) 0 28-Feb-16
ZB4G0090 Project Hand Over 0 13-Nov-16
ZB4G0080 Project Testing & Commissioning 60 29-Aug-16 13-Nov-16
Engineering
Engineering 261 03-May-15 10-Jan-16
Building B4 -
Building B4 - A (Mechanical Utilities) 177 03-May-15 21-Oct-15
ZB4G000010 Basic Engineering Study 18 03-May-15 26-May-15
Basement F
Basement Floor 90 27-May-15 20-Aug-15
Electrical Sy
Electrical Systems 90 27-May-15 20-Aug-15
Power Syste
Power System 15 01-Jul-15 14-Jul-15
ZB4AEBEPS BASEMENT FLOOR POWER SYSTEM LAYOUT PLAN SUBMITTAL 5 01-Jul-15 07-Jul-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4
2015 2016
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 1 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish
ZB4AEBEPABASEMENT FLOOR POWER SYSTEM LAYOUT PLAN APPROVAL 5 08-Jul-15 14-Jul-15
Lighting Sys
Lighting System 15 27-May-15 09-Jun-15
ZB4AEBELS BASEMENT FLOOR LIGHTING SYSTEM LAYOUT PLAN
SUBMITTAL
5 27-May-15 02-Jun-15
ZB4AEBELABASEMENT FLOOR LIGHTING SYSTEM LAYOUT PLAN APPROVAL 5 03-Jun-15 09-Jun-15
Cable Tray S
Cable Tray System 15 01-Jul-15 14-Jul-15
ZB4AEBECSBASEMENT FLOOR CABLE TRAY SYSTEM LAYOUT PLAN
SUBMITTAL
5 01-Jul-15 07-Jul-15
ZB4AEBECABASEMENT FLOOR CABLE TRAY SYSTEM LAYOUT PLAN
APPROVAL
5 08-Jul-15 14-Jul-15
Earthing Sys
Earthing System 15 08-Jul-15 22-Jul-15
ZB4AEBEES BASEMENT FLOOR EARTHING SYSTEM LAYOUT PLAN
SUBMITTAL
5 08-Jul-15 14-Jul-15
ZB4AEBEEABASEMENT FLOOR EARTHING SYSTEM LAYOUT PLAN
APPROVAL
5 15-Jul-15 22-Jul-15
Light Curren
Light Current Systems 24 27-May-15 17-Jun-15
Fire Alarm S
Fire Alarm System 15 27-May-15 09-Jun-15
ZB4AEBELBASEMENT FLOOR FIRE ALARM SYSTEM LAYOUT PLAN
SUBMITTAL
5 27-May-15 02-Jun-15
ZB4AEBELBASEMENT FLOOR FIRE ALARM SYSTEM LAYOUT PLAN
APPROVAL
5 03-Jun-15 09-Jun-15
Security Sys
Security Systems 15 01-Jun-15 14-Jun-15
ZB4AEBELBASEMENT FLOOR SECURITY SYSTEMS LAYOUT PLAN
SUBMITTAL
5 01-Jun-15 07-Jun-15
ZB4AEBELBASEMENT FLOOR SECURITY SYSTEMS LAYOUT PLAN
APPROVAL
5 08-Jun-15 14-Jun-15
Communica
Communication Systems 15 04-Jun-15 17-Jun-15
ZB4AEBELBASEMENT FLOOR COMMUNICATION SYSTEMS LAYOUT PLAN
SUBMITTAL
5 04-Jun-15 10-Jun-15
ZB4AEBELBASEMENT FLOOR COMMUNICATION SYSTEMS LAYOUT PLAN
APPROVAL
5 11-Jun-15 17-Jun-15
SCADA Syste
SCADA System 14 09-Aug-15 20-Aug-15
ZB4AEBEDSBASEMENT FLOOR SCADA SYSTEM LAYOUT PLAN SUBMITTAL 5 09-Aug-15 13-Aug-15
ZB4AEBEDABASEMENT FLOOR SCADA SYSTEM LAYOUT PLAN APPROVAL 5 16-Aug-15 20-Aug-15
Mechanical
Mechanical Systems 30 27-May-15 23-Jun-15
HVAC System
HVAC System 30 27-May-15 23-Jun-15
ZB4AEBMHSBASEMENT FLOOR HVAC SYSTEM LAYOUT PLAN SUBMITTAL 15 27-May-15 16-Jun-15
ZB4AEBMHSBASEMENT FLOOR HVAC SECTIONS LAYOUT PLAN SUBMITTAL 15 27-May-15 16-Jun-15
ZB4AEBMHA
BASEMENT FLOOR HVAC SYSTEM LAYOUT PLAN APPROVAL 5 17-Jun-15 23-Jun-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4
2015 2016
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 2 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish
ZB4AEBMHA
BASEMENT FLOOR HVAC SYSTEM LAYOUT PLAN APPROVAL 5 17-Jun-15 23-Jun-15
Fire Protectio
Fire Protection Systems 22 27-May-15 16-Jun-15
ZB4AEBMFSBASEMENT FLOOR FIRE PROTECTION SYSTEM LAYOUT PLAN
SUBMITTAL
10 27-May-15 09-Jun-15
ZB4AEBMFABASEMENT FLOOR FIRE PROTECTION SYSTEM LAYOUT PLAN
APPROVAL
5 10-Jun-15 16-Jun-15
Plumbing Sy
Plumbing System 30 27-May-15 23-Jun-15
ZB4AEBMW BASEMENT FLOOR WATER SUPPLY SYSTEM LAYOUT PLAN
SUBMITTAL
5 27-May-15 02-Jun-15
ZB4AEBMDSBASEMENT FLOOR DRAINAGE SYSTEM LAYOUT PLAN
SUBMITTAL
5 27-May-15 02-Jun-15
ZB4AEBMWA
BASEMENT FLOOR WATER SUPPLY SYSTEM LAYOUT PLAN
APPROVAL
5 03-Jun-15 09-Jun-15
ZB4AEBMDA
BASEMENT FLOOR DRAINAGE SYSTEM LAYOUT PLAN
APPROVAL
5 03-Jun-15 09-Jun-15
ZB4AEBMW WATER SUPPLY PUMP ROOM DETAILS & SECTIONS SUBMITTAL 15 27-May-15 16-Jun-15
ZB4AEBMWA
WATER SUPPLY PUMP ROOM DETAILS & SECTIONS APPROVAL 5 17-Jun-15 23-Jun-15
Composite D
Composite Drawing 14 26-Jul-15 06-Aug-15
ZB4AEBCS10 BASEMENT FLOOR COMPOSITE LAYOUT PLAN SUBMITTAL 5 26-Jul-15 30-Jul-15
ZB4AEBCA10 BASEMENT FLOOR COMPOSITE LAYOUT PLAN APPROVAL 5 02-Aug-15 06-Aug-15
Ground Floor
Ground Floor 90 03-Jun-15 27-Aug-15
ZB4AEGGBS10 Ground Floor Builder Work Submittal 5 02-Aug-15 06-Aug-15
ZB4AEGGBA10 Ground Floor Builder Work Approval 5 09-Aug-15 13-Aug-15
Electrical Sy
Electrical Systems 90 03-Jun-15 27-Aug-15
Power Syste
Power System 15 08-Jul-15 22-Jul-15
ZB4AEGEPS GROUND FLOOR POWER SYSTEM LAYOUT PLAN SUBMITTAL 5 08-Jul-15 14-Jul-15
ZB4AEGEPAGROUND FLOOR POWER SYSTEM LAYOUT PLAN APPROVAL 5 15-Jul-15 22-Jul-15
Lighting Sys
Lighting System 15 03-Jun-15 16-Jun-15
ZB4AEGELSGROUND FLOOR LIGHTING SYSTEM LAYOUT PLAN SUBMITTAL 5 03-Jun-15 09-Jun-15
ZB4AEGELAGROUND FLOOR LIGHTING SYSTEM LAYOUT PLAN APPROVAL 5 10-Jun-15 16-Jun-15
Cable Tray S
Cable Tray System 15 08-Jul-15 22-Jul-15
ZB4AEGECSGROUND FLOOR CABLE TRAY SYSTEM LAYOUT PLAN
SUBMITTAL
5 08-Jul-15 14-Jul-15
ZB4AEGECAGROUND FLOOR CABLE TRAY SYSTEM LAYOUT PLAN
APPROVAL
5 15-Jul-15 22-Jul-15
Earthing Sys
Earthing System 15 15-Jul-15 30-Jul-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4
2015 2016
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 3 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish
ZB4AEGEESGROUND FLOOR EARTHING SYSTEM LAYOUT PLAN SUBMITTAL 5 15-Jul-15 22-Jul-15
ZB4AEGEEAGROUND FLOOR EARTHING SYSTEM LAYOUT PLAN APPROVAL 5 26-Jul-15 30-Jul-15
Light Curren
Light Current Systems 24 03-Jun-15 24-Jun-15
Fire Alarm S
Fire Alarm System 15 03-Jun-15 16-Jun-15
ZB4AEGELGROUND FLOOR FIRE ALARM SYSTEM LAYOUT PLAN
SUBMITTAL
5 03-Jun-15 09-Jun-15
ZB4AEGELGROUND FLOOR FIRE ALARM SYSTEM LAYOUT PLAN
APPROVAL
5 10-Jun-15 16-Jun-15
Security Sys
Security Systems 15 08-Jun-15 21-Jun-15
ZB4AEGELGROUND FLOOR SECURITY SYSTEMS LAYOUT PLAN SUBMITTAL 5 08-Jun-15 14-Jun-15
ZB4AEGELGROUND FLOOR SECURITY SYSTEMS LAYOUT PLAN APPROVAL 5 15-Jun-15 21-Jun-15
Communica
Communication Systems 15 11-Jun-15 24-Jun-15
ZB4AEGELGROUND FLOOR COMMUNICATION SYSTEMS LAYOUT PLAN
SUBMITTAL
5 11-Jun-15 17-Jun-15
ZB4AEGELGROUND FLOOR COMMUNICATION SYSTEMS LAYOUT PLAN
APPROVAL
5 18-Jun-15 24-Jun-15
SCADA Syste
SCADA System 14 16-Aug-15 27-Aug-15
ZB4AEGEDSGROUND FLOOR SCADA SYSTEM LAYOUT PLAN SUBMITTAL 5 16-Aug-15 20-Aug-15
ZB4AEGEDAGROUND FLOOR SCADA SYSTEM LAYOUT PLAN APPROVAL 5 23-Aug-15 27-Aug-15
Mechanical
Mechanical Systems 45 03-Jun-15 14-Jul-15
HVAC System
HVAC System 30 17-Jun-15 14-Jul-15
ZB4AEGMHSGROUND FLOOR HVAC SYSTEM LAYOUT PLAN SUBMITTAL 15 17-Jun-15 07-Jul-15
ZB4AEGMHSGROUND FLOOR HVAC SECTIONS LAYOUT PLAN SUBMITTAL 15 17-Jun-15 07-Jul-15
ZB4AEGMHA
GROUND FLOOR HVAC SYSTEM LAYOUT PLAN APPROVAL 5 08-Jul-15 14-Jul-15
ZB4AEGMHA
GROUND FLOOR HVAC SYSTEM LAYOUT PLAN APPROVAL 5 08-Jul-15 14-Jul-15
Fire Protectio
Fire Protection Systems 22 10-Jun-15 30-Jun-15
ZB4AEGMFSGROUND FLOOR FIRE PROTECTION SYSTEM LAYOUT PLAN
SUBMITTAL
5 10-Jun-15 16-Jun-15
ZB4AEGMFAGROUND FLOOR FIRE PROTECTION SYSTEM LAYOUT PLAN
APPROVAL
5 17-Jun-15 23-Jun-15
ZB4AEGMFSFIRE PROTECTION WORK - SPECIAL SYSTEM DETAILS
SUBMITTAL
5 17-Jun-15 23-Jun-15
ZB4AEGMFAFIRE PROTECTION WORK - SPECIAL SYSTEM DETAILS
APPROVAL
5 24-Jun-15 30-Jun-15
Plumbing Sy
Plumbing System 15 03-Jun-15 16-Jun-15
ZB4AEGMWGROUND FLOOR WATER SUPPLY SYSTEM LAYOUT PLAN
SUBMITTAL
5 03-Jun-15 09-Jun-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4
2015 2016
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 4 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish
ZB4AEGMDSGROUND FLOOR DRAINAGE SYSTEM LAYOUT PLAN SUBMITTAL 5 03-Jun-15 09-Jun-15
ZB4AEGMWA
GROUND FLOOR WATER SUPPLY SYSTEM LAYOUT PLAN
APPROVAL
5 10-Jun-15 16-Jun-15
ZB4AEGMDA
GROUND FLOOR DRAINAGE SYSTEM LAYOUT PLAN APPROVAL 5 10-Jun-15 16-Jun-15
Composite D
Composite Drawing 14 02-Aug-15 13-Aug-15
ZB4AEGCS10 GROUND FLOOR COMPOSITE LAYOUT PLAN SUBMITTAL 5 02-Aug-15 06-Aug-15
ZB4AEGCA10 GROUND FLOOR COMPOSITE LAYOUT PLAN APPROVAL 5 09-Aug-15 13-Aug-15
Roof 1
Roof 1 90 10-Jun-15 03-Sep-15
ZB4AERGBS10 Roof 1 Builder Work Submittal 5 09-Aug-15 13-Aug-15
ZB4AERGBA10 Roof 1 Builder Work Approval 5 16-Aug-15 20-Aug-15
Electrical Sy
Electrical Systems 90 10-Jun-15 03-Sep-15
Power Syste
Power System 7 15-Jul-15 22-Jul-15
ZB4AEREPS ROOF 1 FLOOR POWER SYSTEM LAYOUT PLAN SUBMITTAL 5 15-Jul-15 22-Jul-15
ZB4AEREPAROOF 1 FLOOR POWER SYSTEM LAYOUT PLAN APPROVAL 5 15-Jul-15 22-Jul-15
Lighting Sys
Lighting System 15 10-Jun-15 23-Jun-15
ZB4AERELSROOF 1 FLOOR LIGHTING SYSTEM LAYOUT PLAN SUBMITTAL 5 10-Jun-15 16-Jun-15
ZB4AERELAROOF 1 FLOOR LIGHTING SYSTEM LAYOUT PLAN APPROVAL 5 17-Jun-15 23-Jun-15
Cable Tray S
Cable Tray System 15 15-Jul-15 30-Jul-15
ZB4AERECSROOF 1 FLOOR CABLE TRAY SYSTEM LAYOUT PLAN SUBMITTAL 5 15-Jul-15 22-Jul-15
ZB4AERECAROOF 1 FLOOR CABLE TRAY SYSTEM LAYOUT PLAN APPROVAL 5 26-Jul-15 30-Jul-15
Lightning Sy
Lightning System 14 26-Jul-15 06-Aug-15
ZB4AEREHSROOF 1 FLOOR LIGHTNING SYSTEM LAYOUT PLAN SUBMITTAL 5 26-Jul-15 30-Jul-15
ZB4AEREHAROOF 1 FLOOR LIGHTNING SYSTEM LAYOUT PLAN APPROVAL 5 02-Aug-15 06-Aug-15
Light Curren
Light Current Systems 20 10-Jun-15 28-Jun-15
Fire Alarm S
Fire Alarm System 15 10-Jun-15 23-Jun-15
ZB4AERELROOF 1 FLOOR FIRE ALARM SYSTEM LAYOUT PLAN SUBMITTAL 5 10-Jun-15 16-Jun-15
ZB4AERELROOF 1 FLOOR FIRE ALARM SYSTEM LAYOUT PLAN APPROVAL 5 17-Jun-15 23-Jun-15
Security Sys
Security Systems 15 15-Jun-15 28-Jun-15
ZB4AERELROOF 1 FLOOR SECURITY SYSTEMS LAYOUT PLAN SUBMITTAL 5 15-Jun-15 21-Jun-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4
2015 2016
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 5 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish
ZB4AERELROOF 1 FLOOR SECURITY SYSTEMS LAYOUT PLAN APPROVAL 5 22-Jun-15 28-Jun-15
SCADA Syste
SCADA System 14 23-Aug-15 03-Sep-15
ZB4AEREDSROOF 1 FLOOR SCADA SYSTEM LAYOUT PLAN SUBMITTAL 5 23-Aug-15 27-Aug-15
ZB4AEREDAROOF 1 FLOOR SCADA SYSTEM LAYOUT PLAN APPROVAL 5 30-Aug-15 03-Sep-15
Mechanical
Mechanical Systems 60 10-Jun-15 06-Aug-15
HVAC System
HVAC System 30 08-Jul-15 06-Aug-15
ZB4AERMHSROOF 1 FLOOR HVAC SYSTEM LAYOUT PLAN SUBMITTAL 15 08-Jul-15 30-Jul-15
ZB4AERMHSROOF 1 FLOOR HVAC SECTIONS LAYOUT PLAN SUBMITTAL 15 08-Jul-15 30-Jul-15
ZB4AERMHA
ROOF 1 FLOOR HVAC SYSTEM LAYOUT PLAN APPROVAL 5 02-Aug-15 06-Aug-15
ZB4AERMHA
ROOF 1 FLOOR HVAC SECTIONS LAYOUT PLAN APPROVAL 5 02-Aug-15 06-Aug-15
Fire Protectio
Fire Protection Systems 15 17-Jun-15 30-Jun-15
ZB4AERMFSROOF 1 FLOOR FIRE PROTECTION SYSTEM LAYOUT PLAN
SUBMITTAL
5 17-Jun-15 23-Jun-15
ZB4AERMFAROOF 1 FLOOR FIRE PROTECTION SYSTEM LAYOUT PLAN
APPROVAL
5 24-Jun-15 30-Jun-15
Plumbing Sy
Plumbing System 15 10-Jun-15 23-Jun-15
ZB4AERMWROOF 1 FLOOR WATER SUPPLY SYSTEM LAYOUT PLAN
SUBMITTAL
5 10-Jun-15 16-Jun-15
ZB4AERMDSROOF 1 FLOOR DRAINAGE SYSTEM LAYOUT PLAN SUBMITTAL 5 10-Jun-15 16-Jun-15
ZB4AERMWA
ROOF 1 FLOOR WATER SUPPLY SYSTEM LAYOUT PLAN
APPROVAL
5 17-Jun-15 23-Jun-15
ZB4AERMDA
ROOF 1 FLOOR DRAINAGE SYSTEM LAYOUT PLAN APPROVAL 5 17-Jun-15 23-Jun-15
Composite D
Composite Drawing 14 09-Aug-15 20-Aug-15
ZB4AERCS10 ROOF 1 FLOOR COMPOSITE LAYOUT PLAN SUBMITTAL 5 09-Aug-15 13-Aug-15
ZB4AERCA10 ROOF 1 FLOOR COMPOSITE LAYOUT PLAN APPROVAL 5 16-Aug-15 20-Aug-15
Roof 2
Roof 2 90 17-Jun-15 10-Sep-15
ZB4AEUGBS10 Roof 2 Builder Work Submittal 5 30-Aug-15 03-Sep-15
ZB4AEUGBA10 Roof 2 Builder Work Approval 5 06-Sep-15 10-Sep-15
Electrical Sy
Electrical Systems 90 17-Jun-15 10-Sep-15
Power Syste
Power System 15 15-Jul-15 30-Jul-15
ZB4AEUEPS ROOF 2 FLOOR POWER SYSTEM LAYOUT PLAN SUBMITTAL 5 15-Jul-15 22-Jul-15
ZB4AEUEPAROOF 2 FLOOR POWER SYSTEM LAYOUT PLAN APPROVAL 5 26-Jul-15 30-Jul-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4
2015 2016
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 6 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish
Lighting Sys
Lighting System 15 17-Jun-15 30-Jun-15
ZB4AEUELSROOF 2 FLOOR LIGHTING SYSTEM LAYOUT PLAN SUBMITTAL 5 17-Jun-15 23-Jun-15
ZB4AEUELAROOF 2 FLOOR LIGHTING SYSTEM LAYOUT PLAN APPROVAL 5 24-Jun-15 30-Jun-15
Cable Tray S
Cable Tray System 14 26-Jul-15 06-Aug-15
ZB4AEUECSROOF 2 FLOOR CABLE TRAY SYSTEM LAYOUT PLAN SUBMITTAL 5 26-Jul-15 30-Jul-15
ZB4AEUECAROOF 2 FLOOR CABLE TRAY SYSTEM LAYOUT PLAN APPROVAL 5 02-Aug-15 06-Aug-15
Lightning Sy
Lightning System 14 02-Aug-15 13-Aug-15
ZB4AEUEHSROOF 2 FLOOR LIGHTNING SYSTEM LAYOUT PLAN SUBMITTAL 5 02-Aug-15 06-Aug-15
ZB4AEUEHAROOF 2 FLOOR LIGHTNING SYSTEM LAYOUT PLAN APPROVAL 5 09-Aug-15 13-Aug-15
Light Curren
Light Current Systems 20 17-Jun-15 05-Jul-15
Fire Alarm S
Fire Alarm System 15 17-Jun-15 30-Jun-15
ZB4AEUELROOF 2 FLOOR FIRE ALARM SYSTEM LAYOUT PLAN SUBMITTAL 5 17-Jun-15 23-Jun-15
ZB4AEUELROOF 2 FLOOR FIRE ALARM SYSTEM LAYOUT PLAN APPROVAL 5 24-Jun-15 30-Jun-15
Security Sys
Security Systems 15 22-Jun-15 05-Jul-15
ZB4AEUELROOF 2 FLOOR SECURITY SYSTEMS LAYOUT PLAN SUBMITTAL 5 22-Jun-15 28-Jun-15
ZB4AEUELROOF 2 FLOOR SECURITY SYSTEMS LAYOUT PLAN APPROVAL 5 29-Jun-15 05-Jul-15
SCADA Syste
SCADA System 14 30-Aug-15 10-Sep-15
ZB4AEUEDSROOF 2 FLOOR SCADA SYSTEM LAYOUT PLAN SUBMITTAL 5 30-Aug-15 03-Sep-15
ZB4AEUEDAROOF 2 FLOOR SCADA SYSTEM LAYOUT PLAN APPROVAL 5 06-Sep-15 10-Sep-15
Mechanical
Mechanical Systems 75 17-Jun-15 27-Aug-15
HVAC System
HVAC System 29 02-Aug-15 27-Aug-15
ZB4AEUMHSROOF 2 FLOOR HVAC SYSTEM LAYOUT PLAN SUBMITTAL 15 02-Aug-15 20-Aug-15
ZB4AEUMHSROOF 2 FLOOR HVAC SECTIONS LAYOUT PLAN SUBMITTAL 15 02-Aug-15 20-Aug-15
ZB4AEUMHA
ROOF 2 FLOOR HVAC SYSTEM LAYOUT PLAN APPROVAL 5 23-Aug-15 27-Aug-15
ZB4AEUMHA
ROOF 2 FLOOR HVAC SECTIONS LAYOUT PLAN APPROVAL 5 23-Aug-15 27-Aug-15
Fire Protectio
Fire Protection Systems 15 24-Jun-15 07-Jul-15
ZB4AEUMFSROOF 2 FLOOR FIRE PROTECTION SYSTEM LAYOUT PLAN
SUBMITTAL
5 24-Jun-15 30-Jun-15
ZB4AEUMFAROOF 2 FLOOR FIRE PROTECTION SYSTEM LAYOUT PLAN
APPROVAL
5 01-Jul-15 07-Jul-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4
2015 2016
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 7 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish
Plumbing Sy
Plumbing System 15 17-Jun-15 30-Jun-15
ZB4AEUMWROOF 2 FLOOR WATER SUPPLY SYSTEM LAYOUT PLAN
SUBMITTAL
5 17-Jun-15 23-Jun-15
ZB4AEUMDSROOF 2 FLOOR DRAINAGE SYSTEM LAYOUT PLAN SUBMITTAL 5 17-Jun-15 23-Jun-15
ZB4AEUMWA
ROOF 2 FLOOR WATER SUPPLY SYSTEM LAYOUT PLAN
APPROVAL
5 24-Jun-15 30-Jun-15
ZB4AEUMDA
ROOF 2 FLOOR DRAINAGE SYSTEM LAYOUT PLAN APPROVAL 5 24-Jun-15 30-Jun-15
Composite D
Composite Drawing 14 30-Aug-15 10-Sep-15
ZB4AEUCS10 ROOF 2 FLOOR COMPOSITE LAYOUT PLAN SUBMITTAL 5 30-Aug-15 03-Sep-15
ZB4AEUCA10 ROOF 2 FLOOR COMPOSITE LAYOUT PLAN APPROVAL 5 06-Sep-15 10-Sep-15
General Sho
General Shop Drawings 151 27-May-15 21-Oct-15
Electrical Sy
Electrical Systems 151 27-May-15 21-Oct-15
ZB4AETEGS10ELECTRICAL INSTALLATION DETAILS SUBMITTAL 5 27-May-15 02-Jun-15
ZB4AETEGA10ELECTRICAL INSTALLATION DETAILS APPROVAL 5 03-Jun-15 09-Jun-15
Power Syste
Power System 29 02-Aug-15 27-Aug-15
ZB4AETEPS PANEL BOARD SCHEDULE SUBMITTAL 5 02-Aug-15 06-Aug-15
ZB4AETEPAPANEL BOARD SCHEDULE APPROVAL 5 09-Aug-15 13-Aug-15
ZB4AETEPS2
POWER S.L.D SUBMITTAL 5 16-Aug-15 20-Aug-15
ZB4AETEPAPOWER S.L.D APPROVAL 5 23-Aug-15 27-Aug-15
Lighting Sys
Lighting System 114 01-Jul-15 21-Oct-15
ZB4AETELS LIGHTING FIXTURE SCHEDULE SUBMITTAL 5 01-Jul-15 07-Jul-15
ZB4AETELALIGHTING FIXTURE SCHEDULE APPROVAL 5 08-Jul-15 14-Jul-15
ZB4AETELS CENTRAL MONITORING RISER DIAGRAM SUBMITTAL 5 29-Sep-15 05-Oct-15
ZB4AETELS KNX SYSTEM RISER DIAGRAM SUBMITTAL 5 07-Oct-15 13-Oct-15
ZB4AETELACENTRAL MONITORING RISER DIAGRAM APPROVAL 5 07-Oct-15 13-Oct-15
ZB4AETELAKNX SYSTEM RISER DIAGRAM APPROVAL 5 15-Oct-15 21-Oct-15
Light Curren
Light Current Systems 57 27-May-15 20-Jul-15
ZB4AETELGLIGHT CURRENT TYPICAL INSTALLATION DETAILS SUBMITTAL 5 27-May-15 02-Jun-15
ZB4AETELGLIGHT CURRENT TYPICAL INSTALLATION DETAILS APPROVAL 5 03-Jun-15 09-Jun-15
Fire Alarm S
Fire Alarm System 15 01-Jul-15 14-Jul-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4
2015 2016
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 8 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish
ZB4AETELFIRE ALARM RISER DIAGRAM SUBMITTAL 5 01-Jul-15 07-Jul-15
ZB4AETELFIRE ALARM RISER DIAGRAM APPROVAL 5 08-Jul-15 14-Jul-15
Security Sys
Security Systems 15 06-Jul-15 20-Jul-15
ZB4AETELIPCCTV RISER DIAGRAM SUBMITTAL (By Others) 5 06-Jul-15 12-Jul-15
ZB4AETELIPCCTV RISER DIAGRAM APPROVAL (By Others) 5 13-Jul-15 20-Jul-15
Communica
Communication Systems 15 25-Jun-15 08-Jul-15
ZB4AETELSTRUCTURED CABLING RISER DIAGRAM SUBMITTAL (By Others) 5 25-Jun-15 01-Jul-15
ZB4AETELSTRUCTURED CABLING RISER DIAGRAM APPROVAL (By Others) 5 02-Jul-15 08-Jul-15
SCADA Syste
SCADA System 15 13-Sep-15 28-Sep-15
ZB4AETEDSSCADA SYSTEM RISER DIAGRAM SUBMITTAL 5 13-Sep-15 17-Sep-15
ZB4AETEDASCADA SYSTEM RISER DIAGRAM APPROVAL 5 20-Sep-15 28-Sep-15
Mechanical
Mechanical Systems 60 27-May-15 22-Jul-15
HVAC System
HVAC System 15 27-May-15 09-Jun-15
ZB4AETMHSHVAC INSTALLATION DETAILS SUBMITTAL 5 27-May-15 02-Jun-15
ZB4AETMHA
HVAC INSTALLATION DETAILS APPROVAL 5 03-Jun-15 09-Jun-15
Fire Protectio
Fire Protection Systems 60 27-May-15 22-Jul-15
ZB4AETMFSFIRE PROTECTION INSTALLATION DETAILS SUBMITTAL 5 27-May-15 02-Jun-15
ZB4AETMFAFIRE PROTECTION INSTALLATION DETAILS APPROVAL 5 03-Jun-15 09-Jun-15
ZB4AETMFSFIRE PROTECTION RISER DIAGRAM SUBMITTAL 5 08-Jul-15 14-Jul-15
ZB4AETMFAFIRE PROTECTION RISER DIAGRAM APPROVAL 5 15-Jul-15 22-Jul-15
Plumbing Sy
Plumbing System 15 27-May-15 09-Jun-15
ZB4AETMW WATER SUPPLY INSTALLATION DETAILS SUBMITTAL 5 27-May-15 02-Jun-15
ZB4AETMDSDRAINAGE SYSTEM INSTALLATION DETAILS SUBMITTAL 5 27-May-15 02-Jun-15
ZB4AETMWA
WATER SUPPLY INSTALLATION DETAILS APPROVAL 5 03-Jun-15 09-Jun-15
ZB4AETMDA
DRAINAGE SYSTEM INSTALLATION DETAILS APPROVAL 5 03-Jun-15 09-Jun-15
Building B4 -
Building B4 - B (Electrical Services) 144 24-Jun-15 11-Nov-15
Ground Floor
Ground Floor 129 24-Jun-15 28-Oct-15
ZB4BEGGBS10 Ground Floor Builder Work Submittal 5 23-Aug-15 27-Aug-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4
2015 2016
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 9 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish
ZB4BEGGBA10 Ground Floor Builder Work Approval 5 30-Aug-15 03-Sep-15
Electrical Sy
Electrical Systems 82 24-Jun-15 10-Sep-15
Power Syste
Power System 14 26-Jul-15 06-Aug-15
ZB4BEGEPS GROUND FLOOR POWER SYSTEM LAYOUT PLAN SUBMITTAL 5 26-Jul-15 30-Jul-15
ZB4BEGEPAGROUND FLOOR POWER SYSTEM LAYOUT PLAN APPROVAL 5 02-Aug-15 06-Aug-15
Lighting Sys
Lighting System 15 24-Jun-15 07-Jul-15
ZB4BEGELS GROUND FLOOR LIGHTING SYSTEM LAYOUT PLAN SUBMITTAL 5 24-Jun-15 30-Jun-15
ZB4BEGELAGROUND FLOOR LIGHTING SYSTEM LAYOUT PLAN APPROVAL 5 01-Jul-15 07-Jul-15
Cable Tray S
Cable Tray System 22 29-Jul-15 18-Aug-15
ZB4BEGECSGROUND FLOOR CABLE TRAY SYSTEM LAYOUT PLAN
SUBMITTAL
10 29-Jul-15 11-Aug-15
ZB4BEGECAGROUND FLOOR CABLE TRAY SYSTEM LAYOUT PLAN
APPROVAL
5 12-Aug-15 18-Aug-15
Earthing Sys
Earthing System 14 09-Aug-15 20-Aug-15
ZB4BEGEES GROUND FLOOR EARTHING SYSTEM LAYOUT PLAN SUBMITTAL 5 09-Aug-15 13-Aug-15
ZB4BEGEEAGROUND FLOOR EARTHING SYSTEM LAYOUT PLAN APPROVAL 5 16-Aug-15 20-Aug-15
Light Curren
Light Current Systems 60 24-Jun-15 20-Aug-15
Fire Alarm S
Fire Alarm System 15 24-Jun-15 07-Jul-15
ZB4BEGELGROUND FLOOR FIRE ALARM SYSTEM LAYOUT PLAN
SUBMITTAL
5 24-Jun-15 30-Jun-15
ZB4BEGELGROUND FLOOR FIRE ALARM SYSTEM LAYOUT PLAN
APPROVAL
5 01-Jul-15 07-Jul-15
Security Sys
Security Systems 55 29-Jun-15 20-Aug-15
ZB4BEGELGROUND FLOOR SECURITY SYSTEMS LAYOUT PLAN SUBMITTAL 5 29-Jun-15 05-Jul-15
ZB4BEGELGROUND FLOOR SECURITY SYSTEMS LAYOUT PLAN APPROVAL 5 06-Jul-15 12-Jul-15
ZB4BEGELAccess Control System Approval and Approved Submittal (By Others) 0 20-Aug-15
Communica
Communication Systems 15 06-Jul-15 20-Jul-15
ZB4BEGELGROUND FLOOR COMMUNICATION SYSTEMS LAYOUT PLAN
SUBMITTAL
5 06-Jul-15 12-Jul-15
ZB4BEGELGROUND FLOOR COMMUNICATION SYSTEMS LAYOUT PLAN
APPROVAL
5 13-Jul-15 20-Jul-15
SCADA Syste
SCADA System 14 30-Aug-15 10-Sep-15
ZB4BEGEDSGROUND FLOOR SCADA SYSTEM LAYOUT PLAN SUBMITTAL 5 30-Aug-15 03-Sep-15
ZB4BEGEDAGROUND FLOOR SCADA SYSTEM LAYOUT PLAN APPROVAL 5 06-Sep-15 10-Sep-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4
2015 2016
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 10 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish
Mechanical
Mechanical Systems 129 24-Jun-15 28-Oct-15
HVAC System
HVAC System 14 02-Aug-15 13-Aug-15
ZB4BEGMHSGROUND FLOOR HVAC SYSTEM LAYOUT PLAN SUBMITTAL 5 02-Aug-15 06-Aug-15
ZB4BEGMHA
GROUND FLOOR HVAC SYSTEM LAYOUT PLAN APPROVAL 5 09-Aug-15 13-Aug-15
Fire Protectio
Fire Protection Systems 22 07-Oct-15 28-Oct-15
ZB4BEGMFSFIRE PROTECTION WORK - SPECIAL SYSTEM DETAILS
SUBMITTAL
10 07-Oct-15 21-Oct-15
ZB4BEGMFAFIRE PROTECTION WORK - SPECIAL SYSTEM DETAILS
APPROVAL
5 22-Oct-15 28-Oct-15
Plumbing Sy
Plumbing System 15 24-Jun-15 07-Jul-15
ZB4BEGMDSGROUND FLOOR DRAINAGE SYSTEM LAYOUT PLAN SUBMITTAL 5 24-Jun-15 30-Jun-15
ZB4BEGMDA
GROUND FLOOR DRAINAGE SYSTEM LAYOUT PLAN APPROVAL 5 01-Jul-15 07-Jul-15
Composite D
Composite Drawing 14 23-Aug-15 03-Sep-15
ZB4BEGCS10 GROUND FLOOR COMPOSITE LAYOUT PLAN SUBMITTAL 5 23-Aug-15 27-Aug-15
ZB4BEGCA10 GROUND FLOOR COMPOSITE LAYOUT PLAN APPROVAL 5 30-Aug-15 03-Sep-15
Roof 1
Roof 1 82 24-Jun-15 10-Sep-15
ZB4BERGBS10 Roof 1 Builder Work Submittal 5 30-Aug-15 03-Sep-15
ZB4BERGBA10 Roof 1 Builder Work Approval 5 06-Sep-15 10-Sep-15
Electrical Sy
Electrical Systems 65 24-Jun-15 25-Aug-15
Power Syste
Power System 14 02-Aug-15 13-Aug-15
ZB4BEREPS ROOF 1 FLOOR POWER SYSTEM LAYOUT PLAN SUBMITTAL 5 02-Aug-15 06-Aug-15
ZB4BEREPAROOF 1 FLOOR POWER SYSTEM LAYOUT PLAN APPROVAL 5 09-Aug-15 13-Aug-15
Lighting Sys
Lighting System 15 01-Jul-15 14-Jul-15
ZB4BERELS ROOF 1 FLOOR LIGHTING SYSTEM LAYOUT PLAN SUBMITTAL 5 01-Jul-15 07-Jul-15
ZB4BERELAROOF 1 FLOOR LIGHTING SYSTEM LAYOUT PLAN APPROVAL 5 08-Jul-15 14-Jul-15
Cable Tray S
Cable Tray System 15 12-Aug-15 25-Aug-15
ZB4BERECSROOF 1 FLOOR CABLE TRAY SYSTEM LAYOUT PLAN SUBMITTAL 5 12-Aug-15 18-Aug-15
ZB4BERECAROOF 1 FLOOR CABLE TRAY SYSTEM LAYOUT PLAN APPROVAL 5 19-Aug-15 25-Aug-15
Light Curren
Light Current Systems 15 24-Jun-15 07-Jul-15
Fire Alarm S
Fire Alarm System 15 24-Jun-15 07-Jul-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4
2015 2016
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 11 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish
ZB4BERELROOF 1 FLOOR FIRE ALARM SYSTEM LAYOUT PLAN SUBMITTAL 5 24-Jun-15 30-Jun-15
ZB4BERELROOF 1 FLOOR FIRE ALARM SYSTEM LAYOUT PLAN APPROVAL 5 01-Jul-15 07-Jul-15
Mechanical
Mechanical Systems 60 01-Jul-15 27-Aug-15
HVAC System
HVAC System 21 09-Aug-15 27-Aug-15
ZB4BERMHSROOF 1 FLOOR HVAC SYSTEM LAYOUT PLAN SUBMITTAL 10 09-Aug-15 20-Aug-15
ZB4BERMHSROOF 1 FLOOR HVAC SECTIONS LAYOUT PLAN SUBMITTAL 10 09-Aug-15 20-Aug-15
ZB4BERMHA
ROOF 1 FLOOR HVAC SYSTEM LAYOUT PLAN APPROVAL 5 23-Aug-15 27-Aug-15
ZB4BERMHA
ROOF 1 FLOOR HVAC SECTIONS LAYOUT PLAN APPROVAL 5 23-Aug-15 27-Aug-15
Plumbing Sy
Plumbing System 15 01-Jul-15 14-Jul-15
ZB4BERMDSROOF 1 FLOOR DRAINAGE SYSTEM LAYOUT PLAN SUBMITTAL 5 01-Jul-15 07-Jul-15
ZB4BERMDA
ROOF 1 FLOOR DRAINAGE SYSTEM LAYOUT PLAN APPROVAL 5 08-Jul-15 14-Jul-15
Composite D
Composite Drawing 14 30-Aug-15 10-Sep-15
ZB4BERCS10 ROOF 1 FLOOR COMPOSITE LAYOUT PLAN SUBMITTAL 5 30-Aug-15 03-Sep-15
ZB4BERCA10 ROOF 1 FLOOR COMPOSITE LAYOUT PLAN APPROVAL 5 06-Sep-15 10-Sep-15
Roof 2
Roof 2 82 24-Jun-15 10-Sep-15
ZB4BEUGBS10 Roof 2 Builder Work Submittal 5 30-Aug-15 03-Sep-15
ZB4BEUGBA10 Roof 2 Builder Work Approval 5 06-Sep-15 10-Sep-15
Electrical Sy
Electrical Systems 67 24-Jun-15 27-Aug-15
Power Syste
Power System 14 02-Aug-15 13-Aug-15
ZB4BEUEPS ROOF 2 FLOOR POWER SYSTEM LAYOUT PLAN SUBMITTAL 5 02-Aug-15 06-Aug-15
ZB4BEUEPAROOF 2 FLOOR POWER SYSTEM LAYOUT PLAN APPROVAL 5 09-Aug-15 13-Aug-15
Lighting Sys
Lighting System 15 08-Jul-15 22-Jul-15
ZB4BEUELS ROOF 2 FLOOR LIGHTING SYSTEM LAYOUT PLAN SUBMITTAL 5 08-Jul-15 14-Jul-15
ZB4BEUELAROOF 2 FLOOR LIGHTING SYSTEM LAYOUT PLAN APPROVAL 5 15-Jul-15 22-Jul-15
Cable Tray S
Cable Tray System 15 12-Aug-15 25-Aug-15
ZB4BEUECSROOF 2 FLOOR CABLE TRAY SYSTEM LAYOUT PLAN SUBMITTAL 5 12-Aug-15 18-Aug-15
ZB4BEUECAROOF 2 FLOOR CABLE TRAY SYSTEM LAYOUT PLAN APPROVAL 5 19-Aug-15 25-Aug-15
Lightning Sy
Lightning System 14 16-Aug-15 27-Aug-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4
2015 2016
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 12 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish
ZB4BEUEHSROOF 2 FLOOR LIGHTNING SYSTEM LAYOUT PLAN SUBMITTAL 5 16-Aug-15 20-Aug-15
ZB4BEUEHAROOF 2 FLOOR LIGHTNING SYSTEM LAYOUT PLAN APPROVAL 5 23-Aug-15 27-Aug-15
Light Curren
Light Current Systems 7 24-Jun-15 30-Jun-15
Fire Alarm S
Fire Alarm System 7 24-Jun-15 30-Jun-15
ZB4BEUELROOF 2 FLOOR FIRE ALARM SYSTEM LAYOUT PLAN SUBMITTAL 5 24-Jun-15 30-Jun-15
ZB4BEUELROOF 2 FLOOR FIRE ALARM SYSTEM LAYOUT PLAN APPROVAL 5 24-Jun-15 30-Jun-15
Mechanical
Mechanical Systems 52 08-Jul-15 27-Aug-15
HVAC System
HVAC System 21 09-Aug-15 27-Aug-15
ZB4BEUMHSROOF 2 FLOOR HVAC SYSTEM LAYOUT PLAN SUBMITTAL 10 09-Aug-15 20-Aug-15
ZB4BEUMHSROOF 2 FLOOR HVAC SECTIONS LAYOUT PLAN SUBMITTAL 10 09-Aug-15 20-Aug-15
ZB4BEUMHA
ROOF 2 FLOOR HVAC SYSTEM LAYOUT PLAN APPROVAL 5 23-Aug-15 27-Aug-15
ZB4BEUMHA
ROOF 2 FLOOR HVAC SECTIONS LAYOUT PLAN APPROVAL 5 23-Aug-15 27-Aug-15
Plumbing Sy
Plumbing System 15 08-Jul-15 22-Jul-15
ZB4BEUMDSROOF 2 FLOOR DRAINAGE SYSTEM LAYOUT PLAN SUBMITTAL 5 08-Jul-15 14-Jul-15
ZB4BEUMDA
ROOF 2 FLOOR DRAINAGE SYSTEM LAYOUT PLAN APPROVAL 5 15-Jul-15 22-Jul-15
Composite D
Composite Drawing 14 30-Aug-15 10-Sep-15
ZB4BEUCS10 ROOF 2 FLOOR COMPOSITE LAYOUT PLAN SUBMITTAL 5 30-Aug-15 03-Sep-15
ZB4BEUCA10 ROOF 2 FLOOR COMPOSITE LAYOUT PLAN APPROVAL 5 06-Sep-15 10-Sep-15
General Sho
General Shop Drawings 144 24-Jun-15 11-Nov-15
Electrical Sy
Electrical Systems 144 24-Jun-15 11-Nov-15
ZB4BETEGS10ELECTRICAL INSTALLATION DETAILS SUBMITTAL 5 26-Jul-15 30-Jul-15
ZB4BETEGA10ELECTRICAL INSTALLATION DETAILS APPROVAL 5 02-Aug-15 06-Aug-15
Power Syste
Power System 60 13-Sep-15 11-Nov-15
ZB4BETEPS1PANEL BOARD SCHEDULE SUBMITTAL 5 13-Sep-15 17-Sep-15
ZB4BETEPA PANEL BOARD SCHEDULE APPROVAL 5 20-Sep-15 28-Sep-15
ZB4BETEPS2POWER S.L.D SUBMITTAL 5 29-Sep-15 05-Oct-15
ZB4BETEPA POWER S.L.D APPROVAL 5 07-Oct-15 13-Oct-15
ZB4BETEPS3BUILDING POWER S.L.D SUBMITTAL 5 15-Oct-15 21-Oct-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4
2015 2016
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 13 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish
ZB4BETEPA BUILDING POWER S.L.D APPROVAL 5 22-Oct-15 28-Oct-15
ZB4BETEPS4CAMPUS POWER S.L.D SUBMITTAL 5 29-Oct-15 04-Nov-15
ZB4BETEPA CAMPUS POWER S.L.D APPROVAL 5 05-Nov-15 11-Nov-15
Lighting Sys
Lighting System 21 26-Jul-15 13-Aug-15
ZB4BETELS LIGHTING FIXTURE SCHEDULE SUBMITTAL 5 26-Jul-15 30-Jul-15
ZB4BETELALIGHTING FIXTURE SCHEDULE APPROVAL 5 02-Aug-15 06-Aug-15
ZB4BETELS2
KNX SYSTEM RISER DIAGRAM SUBMITTAL 5 02-Aug-15 06-Aug-15
ZB4BETELS3
CENTRAL MONITORING RISER DIAGRAM SUBMITTAL 5 02-Aug-15 06-Aug-15
ZB4BETELAKNX SYSTEM RISER DIAGRAM APPROVAL 5 09-Aug-15 13-Aug-15
ZB4BETELACENTRAL MONITORING RISER DIAGRAM APPROVAL 5 09-Aug-15 13-Aug-15
Light Curren
Light Current Systems 42 24-Jun-15 04-Aug-15
ZB4BETELGLIGHT CURRENT TYPICAL INSTALLATION DETAILS SUBMITTAL 5 24-Jun-15 30-Jun-15
ZB4BETELGLIGHT CURRENT TYPICAL INSTALLATION DETAILS APPROVAL 5 01-Jul-15 07-Jul-15
Fire Alarm S
Fire Alarm System 15 08-Jul-15 22-Jul-15
ZB4BETELFIRE ALARM RISER DIAGRAM SUBMITTAL 5 08-Jul-15 14-Jul-15
ZB4BETELFIRE ALARM RISER DIAGRAM APPROVAL 5 15-Jul-15 22-Jul-15
Security Sys
Security Systems 15 13-Jul-15 28-Jul-15
ZB4BETELIPCCTV RISER DIAGRAM SUBMITTAL (By Others) 5 13-Jul-15 20-Jul-15
ZB4BETELIPCCTV RISER DIAGRAM APPROVAL (By Others) 5 21-Jul-15 28-Jul-15
Communica
Communication Systems 15 21-Jul-15 04-Aug-15
ZB4BETELSTRUCTURED CABLING RISER DIAGRAM SUBMITTAL (By Others) 5 21-Jul-15 28-Jul-15
ZB4BETELSTRUCTURED CABLING RISER DIAGRAM APPROVAL (By Others) 5 29-Jul-15 04-Aug-15
SCADA Syste
SCADA System 15 13-Sep-15 28-Sep-15
ZB4BETEDS SCADA SYSTEM RISER DIAGRAM SUBMITTAL 5 13-Sep-15 17-Sep-15
ZB4BETEDASCADA SYSTEM RISER DIAGRAM APPROVAL 5 20-Sep-15 28-Sep-15
Mechanical
Mechanical Systems 75 24-Jun-15 03-Sep-15
HVAC System
HVAC System 14 23-Aug-15 03-Sep-15
ZB4BETMHSHVAC INSTALLATION DETAILS SUBMITTAL 5 23-Aug-15 27-Aug-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4
2015 2016
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 14 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish
ZB4BETMHA
HVAC INSTALLATION DETAILS APPROVAL 5 30-Aug-15 03-Sep-15
Fire Protectio
Fire Protection Systems 15 01-Jul-15 14-Jul-15
ZB4BETMFSFIRE PROTECTION INSTALLATION DETAILS SUBMITTAL 5 01-Jul-15 07-Jul-15
ZB4BETMFAFIRE PROTECTION INSTALLATION DETAILS APPROVAL 5 08-Jul-15 14-Jul-15
Plumbing Sy
Plumbing System 15 24-Jun-15 07-Jul-15
ZB4BETMPDDRAINAGE SYSTEM INSTALLATION DETAILS SUBMITTAL 5 24-Jun-15 30-Jun-15
ZB4BETMPDDRAINAGE SYSTEM INSTALLATION DETAILS APPROVAL 5 01-Jul-15 07-Jul-15
Building B4 -
Building B4 - D (Fuel Tank) 106 24-Jun-15 05-Oct-15
Ground Floor
Ground Floor 106 24-Jun-15 05-Oct-15
ZB4DEGGBS30 Ground Floor Builder Work Submittal 5 23-Aug-15 27-Aug-15
ZB4DEGGBA30 Ground Floor Builder Work Approval 5 30-Aug-15 03-Sep-15
Electrical Sy
Electrical Systems 60 24-Jun-15 20-Aug-15
Power Syste
Power System 14 26-Jul-15 06-Aug-15
ZB4DEGEPS GROUND & ROOF 1 FLOOR POWER SYSTEM LAYOUTS PLAN
SUBMITTAL
5 26-Jul-15 30-Jul-15
ZB4DEGEPAGROUND & ROOF 1 FLOOR POWER SYSTEM LAYOUTS PLAN
APPROVAL
5 02-Aug-15 06-Aug-15
Lighting Sys
Lighting System 15 24-Jun-15 07-Jul-15
ZB4DEGELSGROUND FLOOR LIGHTING SYSTEM LAYOUT PLAN SUBMITTAL 5 24-Jun-15 30-Jun-15
ZB4DEGELAGROUND FLOOR LIGHTING SYSTEM LAYOUT PLAN APPROVAL 5 01-Jul-15 07-Jul-15
Cable Tray S
Cable Tray System 22 29-Jul-15 18-Aug-15
ZB4DEGECSGROUND FLOOR CABLE TRAY SYSTEM LAYOUT PLAN
SUBMITTAL
10 29-Jul-15 11-Aug-15
ZB4DEGECAGROUND FLOOR CABLE TRAY SYSTEM LAYOUT PLAN
APPROVAL
5 12-Aug-15 18-Aug-15
Earthing Sys
Earthing System 14 09-Aug-15 20-Aug-15
ZB4DEGEESGROUND FLOOR EARTHING SYSTEM LAYOUT PLAN SUBMITTAL 5 09-Aug-15 13-Aug-15
ZB4DEGEEAGROUND FLOOR EARTHING SYSTEM LAYOUT PLAN APPROVAL 5 16-Aug-15 20-Aug-15
Light Curren
Light Current Systems 60 24-Jun-15 20-Aug-15
Fire Alarm S
Fire Alarm System 15 24-Jun-15 07-Jul-15
ZB4DEGELGROUND FLOOR FIRE ALARM SYSTEM LAYOUT PLAN
SUBMITTAL
5 24-Jun-15 30-Jun-15
ZB4DEGELGROUND FLOOR FIRE ALARM SYSTEM LAYOUT PLAN
APPROVAL
5 01-Jul-15 07-Jul-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4
2015 2016
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 15 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish
Security Sys
Security Systems 0 20-Aug-15 20-Aug-15
ZB4DEGELAccess Control System Approval and Approved Submittal (By Others) 0 20-Aug-15
Mechanical
Mechanical Systems 106 24-Jun-15 05-Oct-15
HVAC System
HVAC System 14 02-Aug-15 13-Aug-15
ZB4DEGMHSGROUND FLOOR HVAC SYSTEM LAYOUT PLAN SUBMITTAL 5 02-Aug-15 06-Aug-15
ZB4DEGMHA
GROUND FLOOR HVAC SYSTEM LAYOUT PLAN APPROVAL 5 09-Aug-15 13-Aug-15
Fire Protectio
Fire Protection Systems 22 13-Sep-15 05-Oct-15
ZB4DEGMFSFIRE PROTECTION WORK - SPECIAL SYSTEM DETAILS
SUBMITTAL
10 13-Sep-15 28-Sep-15
ZB4DEGMFAFIRE PROTECTION WORK - SPECIAL SYSTEM DETAILS
APPROVAL
5 29-Sep-15 05-Oct-15
Plumbing Sy
Plumbing System 15 24-Jun-15 07-Jul-15
ZB4DEGMDSGROUND FLOOR DRAINAGE SYSTEM LAYOUT PLAN SUBMITTAL 5 24-Jun-15 30-Jun-15
ZB4DEGMDA
GROUND FLOOR DRAINAGE SYSTEM LAYOUT PLAN APPROVAL 5 01-Jul-15 07-Jul-15
Composite D
Composite Drawing 14 23-Aug-15 03-Sep-15
ZB4DEGCS30 GROUND FLOOR COMPOSITE LAYOUT PLAN SUBMITTAL 5 23-Aug-15 27-Aug-15
ZB4DEGCA30 GROUND FLOOR COMPOSITE LAYOUT PLAN APPROVAL 5 30-Aug-15 03-Sep-15
Roof 1
Roof 1 75 24-Jun-15 03-Sep-15
Electrical Sy
Electrical Systems 75 24-Jun-15 03-Sep-15
Light Curren
Light Current Systems 20 24-Jun-15 12-Jul-15
Fire Alarm S
Fire Alarm System 7 24-Jun-15 30-Jun-15
ZB4DEUELROOF 1 FLOOR FIRE ALARM SYSTEM LAYOUT PLAN SUBMITTAL 5 24-Jun-15 30-Jun-15
ZB4DEUELROOF 1 FLOOR FIRE ALARM SYSTEM LAYOUT PLAN APPROVAL 5 24-Jun-15 30-Jun-15
Security Sys
Security Systems 15 29-Jun-15 12-Jul-15
ZB4DEGELROOF 1 FLOOR SECURITY SYSTEMS LAYOUT PLAN SUBMITTAL 5 29-Jun-15 05-Jul-15
ZB4DEGELROOF 1 FLOOR SECURITY SYSTEMS LAYOUT PLAN APPROVAL 5 06-Jul-15 12-Jul-15
Lightning Sy
Lightning System 14 23-Aug-15 03-Sep-15
ZB4DEUEHSROOF 1 FLOOR LIGHTNING SYSTEM LAYOUT PLAN SUBMITTAL 5 23-Aug-15 27-Aug-15
ZB4DEUEHAROOF 1 FLOOR LIGHTNING SYSTEM LAYOUT PLAN APPROVAL 5 30-Aug-15 03-Sep-15
Mechanical
Mechanical Systems 15 01-Jul-15 14-Jul-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4
2015 2016
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 16 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish
Plumbing Sy
Plumbing System 15 01-Jul-15 14-Jul-15
ZB4DERMDSROOF 1 FLOOR DRAINAGE SYSTEM LAYOUT PLAN SUBMITTAL 5 01-Jul-15 07-Jul-15
ZB4DERMDA
ROOF 1 FLOOR DRAINAGE SYSTEM LAYOUT PLAN APPROVAL 5 08-Jul-15 14-Jul-15
General Sho
General Shop Drawings 106 24-Jun-15 05-Oct-15
Electrical Sy
Electrical Systems 106 24-Jun-15 05-Oct-15
ZB4DETEGS30ELECTRICAL INSTALLATION DETAILS SUBMITTAL 5 26-Jul-15 30-Jul-15
ZB4DETEGA30ELECTRICAL INSTALLATION DETAILS APPROVAL 5 02-Aug-15 06-Aug-15
Power Syste
Power System 30 06-Sep-15 05-Oct-15
ZB4DETEPS6
POWER S.L.D SUBMITTAL 15 06-Sep-15 28-Sep-15
ZB4DETEPAPOWER S.L.D APPROVAL 5 29-Sep-15 05-Oct-15
Lighting Sys
Lighting System 22 08-Jul-15 30-Jul-15
ZB4DETELS LIGHTING FIXTURE SCHEDULE SUBMITTAL 5 08-Jul-15 14-Jul-15
ZB4DETELALIGHTING FIXTURE SCHEDULE APPROVAL 5 15-Jul-15 22-Jul-15
ZB4DETELS KNX SYSTEM RISER DIAGRAM SUBMITTAL 5 15-Jul-15 22-Jul-15
ZB4DETELAKNX SYSTEM RISER DIAGRAM APPROVAL 5 26-Jul-15 30-Jul-15
Light Curren
Light Current Systems 35 24-Jun-15 28-Jul-15
ZB4DETELGLIGHT CURRENT TYPICAL INSTALLATION DETAILS SUBMITTAL 5 24-Jun-15 30-Jun-15
ZB4DETELGLIGHT CURRENT TYPICAL INSTALLATION DETAILS APPROVAL 5 01-Jul-15 07-Jul-15
Fire Alarm S
Fire Alarm System 15 08-Jul-15 22-Jul-15
ZB4DETELFIRE ALARM RISER DIAGRAM SUBMITTAL 5 08-Jul-15 14-Jul-15
ZB4DETELFIRE ALARM RISER DIAGRAM APPROVAL 5 15-Jul-15 22-Jul-15
Security Sys
Security Systems 15 13-Jul-15 28-Jul-15
ZB4DETELIPCCTV RISER DIAGRAM SUBMITTAL (By Others) 5 13-Jul-15 20-Jul-15
ZB4DETELIPCCTV RISER DIAGRAM APPROVAL (By Others) 5 21-Jul-15 28-Jul-15
Building B4 -
Building B4 - E (EDC Building) 106 24-Jun-15 05-Oct-15
Ground Floor
Ground Floor 90 24-Jun-15 17-Sep-15
ZB4EEGGBS20 Ground Floor Builder Work Submittal 5 23-Aug-15 27-Aug-15
ZB4EEGGBA20 Ground Floor Builder Work Approval 5 30-Aug-15 03-Sep-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4
2015 2016
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 17 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish
Electrical Sy
Electrical Systems 82 24-Jun-15 10-Sep-15
Power Syste
Power System 14 26-Jul-15 06-Aug-15
ZB4EEGEPS2
GROUND FLOOR POWER SYSTEM LAYOUT PLAN SUBMITTAL 5 26-Jul-15 30-Jul-15
ZB4EEGEPAGROUND FLOOR POWER SYSTEM LAYOUT PLAN APPROVAL 5 02-Aug-15 06-Aug-15
Lighting Sys
Lighting System 15 24-Jun-15 07-Jul-15
ZB4EEGELS GROUND FLOOR LIGHTING SYSTEM LAYOUT PLAN SUBMITTAL 5 24-Jun-15 30-Jun-15
ZB4EEGELAGROUND FLOOR LIGHTING SYSTEM LAYOUT PLAN APPROVAL 5 01-Jul-15 07-Jul-15
Cable Tray S
Cable Tray System 22 29-Jul-15 18-Aug-15
ZB4EEGECSGROUND FLOOR CABLE TRAY SYSTEM LAYOUT PLAN
SUBMITTAL
10 29-Jul-15 11-Aug-15
ZB4EEGECAGROUND FLOOR CABLE TRAY SYSTEM LAYOUT PLAN
APPROVAL
5 12-Aug-15 18-Aug-15
Earthing Sys
Earthing System 14 09-Aug-15 20-Aug-15
ZB4EEGEES GROUND FLOOR EARTHING SYSTEM LAYOUT PLAN SUBMITTAL 5 09-Aug-15 13-Aug-15
ZB4EEGEEAGROUND FLOOR EARTHING SYSTEM LAYOUT PLAN APPROVAL 5 16-Aug-15 20-Aug-15
Light Curren
Light Current Systems 60 24-Jun-15 20-Aug-15
Fire Alarm S
Fire Alarm System 15 24-Jun-15 07-Jul-15
ZB4EEGELGROUND FLOOR FIRE ALARM SYSTEM LAYOUT PLAN
SUBMITTAL
5 24-Jun-15 30-Jun-15
ZB4EEGELGROUND FLOOR FIRE ALARM SYSTEM LAYOUT PLAN
APPROVAL
5 01-Jul-15 07-Jul-15
Security Sys
Security Systems 55 29-Jun-15 20-Aug-15
ZB4EEGELGROUND FLOOR SECURITY SYSTEMS LAYOUT PLAN SUBMITTAL 5 29-Jun-15 05-Jul-15
ZB4EEGELGROUND FLOOR SECURITY SYSTEMS LAYOUT PLAN APPROVAL 5 06-Jul-15 12-Jul-15
ZB4EEGELAccess Control System Approval and Approved Submittal (By Others) 0 20-Aug-15
Communica
Communication Systems 15 06-Jul-15 20-Jul-15
ZB4EEGELGROUND FLOOR COMMUNICATION SYSTEMS LAYOUT PLAN
SUBMITTAL
5 06-Jul-15 12-Jul-15
ZB4EEGELGROUND FLOOR COMMUNICATION SYSTEMS LAYOUT PLAN
APPROVAL
5 13-Jul-15 20-Jul-15
SCADA Syste
SCADA System 14 30-Aug-15 10-Sep-15
ZB4EEGEDSGROUND FLOOR SCADA SYSTEM LAYOUT PLAN SUBMITTAL 5 30-Aug-15 03-Sep-15
ZB4EEGEDAGROUND FLOOR SCADA SYSTEM LAYOUT PLAN APPROVAL 5 06-Sep-15 10-Sep-15
Mechanical
Mechanical Systems 90 24-Jun-15 17-Sep-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4
2015 2016
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 18 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish
HVAC System
HVAC System 14 02-Aug-15 13-Aug-15
ZB4EEGMHSGROUND FLOOR HVAC SYSTEM LAYOUT PLAN SUBMITTAL 5 02-Aug-15 06-Aug-15
ZB4EEGMHA
GROUND FLOOR HVAC SYSTEM LAYOUT PLAN APPROVAL 5 09-Aug-15 13-Aug-15
Fire Protectio
Fire Protection Systems 21 30-Aug-15 17-Sep-15
ZB4EEGMFSFIRE PROTECTION WORK - SPECIAL SYSTEM DETAILS
SUBMITTAL
10 30-Aug-15 10-Sep-15
ZB4EEGMFAFIRE PROTECTION WORK - SPECIAL SYSTEM DETAILS
APPROVAL
5 13-Sep-15 17-Sep-15
Plumbing Sy
Plumbing System 15 24-Jun-15 07-Jul-15
ZB4EEGMDSGROUND FLOOR DRAINAGE SYSTEM LAYOUT PLAN SUBMITTAL 5 24-Jun-15 30-Jun-15
ZB4EEGMDA
GROUND FLOOR DRAINAGE SYSTEM LAYOUT PLAN APPROVAL 5 01-Jul-15 07-Jul-15
Composite D
Composite Drawing 14 23-Aug-15 03-Sep-15
ZB4EEGCS20 GROUND FLOOR COMPOSITE LAYOUT PLAN SUBMITTAL 5 23-Aug-15 27-Aug-15
ZB4EEGCA20 GROUND FLOOR COMPOSITE LAYOUT PLAN APPROVAL 5 30-Aug-15 03-Sep-15
Roof 1
Roof 1 15 01-Jul-15 14-Jul-15
Mechanical
Mechanical Systems 15 01-Jul-15 14-Jul-15
Plumbing Sy
Plumbing System 15 01-Jul-15 14-Jul-15
ZB4EERMDSROOF 1 FLOOR DRAINAGE SYSTEM LAYOUT PLAN SUBMITTAL 5 01-Jul-15 07-Jul-15
ZB4EERMDA
ROOF 1 FLOOR DRAINAGE SYSTEM LAYOUT PLAN APPROVAL 5 08-Jul-15 14-Jul-15
General Sho
General Shop Drawings 106 24-Jun-15 05-Oct-15
Electrical Sy
Electrical Systems 106 24-Jun-15 05-Oct-15
ZB4EETEGS20ELECTRICAL INSTALLATION DETAILS SUBMITTAL 5 26-Jul-15 30-Jul-15
ZB4EETEGA20ELECTRICAL INSTALLATION DETAILS APPROVAL 5 02-Aug-15 06-Aug-15
Power Syste
Power System 30 06-Sep-15 05-Oct-15
ZB4EETEPS5POWER S.L.D SUBMITTAL 15 06-Sep-15 28-Sep-15
ZB4EETEPA POWER S.L.D APPROVAL 5 29-Sep-15 05-Oct-15
Lighting Sys
Lighting System 22 08-Jul-15 30-Jul-15
ZB4EETELS4
LIGHTING FIXTURE SCHEDULE SUBMITTAL 5 08-Jul-15 14-Jul-15
ZB4EETELALIGHTING FIXTURE SCHEDULE APPROVAL 5 15-Jul-15 22-Jul-15
ZB4EETELS5
KNX SYSTEM RISER DIAGRAM SUBMITTAL 5 15-Jul-15 22-Jul-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4
2015 2016
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 19 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish
ZB4EETELAKNX SYSTEM RISER DIAGRAM APPROVAL 5 26-Jul-15 30-Jul-15
Light Curren
Light Current Systems 35 24-Jun-15 28-Jul-15
ZB4EETELGLIGHT CURRENT TYPICAL INSTALLATION DETAILS SUBMITTAL 5 24-Jun-15 30-Jun-15
ZB4EETELGLIGHT CURRENT TYPICAL INSTALLATION DETAILS APPROVAL 5 01-Jul-15 07-Jul-15
Fire Alarm S
Fire Alarm System 15 08-Jul-15 22-Jul-15
ZB4EETELFIRE ALARM RISER DIAGRAM SUBMITTAL 5 08-Jul-15 14-Jul-15
ZB4EETELFIRE ALARM RISER DIAGRAM APPROVAL 5 15-Jul-15 22-Jul-15
Security Sys
Security Systems 15 13-Jul-15 28-Jul-15
ZB4EETELIPCCTV RISER DIAGRAM SUBMITTAL (By Others) 5 13-Jul-15 20-Jul-15
ZB4EETELIPCCTV RISER DIAGRAM APPROVAL (By Others) 5 21-Jul-15 28-Jul-15
SCADA Syste
SCADA System 15 13-Sep-15 28-Sep-15
ZB4EETEDS SCADA SYSTEM RISER DIAGRAM SUBMITTAL 5 13-Sep-15 17-Sep-15
ZB4EETEDASCADA SYSTEM RISER DIAGRAM APPROVAL 5 20-Sep-15 28-Sep-15
Tunnel & Site
Tunnel & Site Layout 235 26-May-15 10-Jan-16
ZB4LEB460 Receive Approved Site Layout (Architecture & Structural & Roads Sections
and Levels)
0 26-May-15
ZB4LEB650 Receive Approved Site Layout (MEP Networks out of Siemens Scope) 0 26-May-15
Service Tun
Service Tunnel 204 26-May-15 09-Dec-15
Electrical Sy
Electrical Systems 204 26-May-15 09-Dec-15
Tunnel Mediu
Tunnel Medium Voltage Network 30 12-Nov-15 09-Dec-15
ZB4TEBEPS3BASEMENT FLOOR MV NETWORK LAYOUT PLAN SUBMITTAL 15 12-Nov-15 02-Dec-15
ZB4TEBEPA BASEMENT FLOOR MV NETWORK LAYOUT PLAN APPROVAL 5 03-Dec-15 09-Dec-15
Tunnel Low V
Tunnel Low Voltage Network 0 26-May-15 26-May-15
ZB4TEBELABASEMENT FLOOR LV NETWORK LAYOUT PLAN APPROVAL (BY
OTHERS)
0 26-May-15
Power Syste
Power System 14 02-Aug-15 13-Aug-15
ZB4TEBEPS2BASEMENT FLOOR POWER SYSTEM LAYOUT PLAN SUBMITTAL 5 02-Aug-15 06-Aug-15
ZB4TEBEPA BASEMENT FLOOR POWER SYSTEM LAYOUT PLAN APPROVAL 5 09-Aug-15 13-Aug-15
Lighting Sys
Lighting System 15 02-Jul-15 15-Jul-15
ZB4TEBELS2
BASEMENT FLOOR LIGHTING SYSTEM LAYOUT PLAN
SUBMITTAL
5 02-Jul-15 08-Jul-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4
2015 2016
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 20 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish
ZB4TEBELABASEMENT FLOOR LIGHTING SYSTEM LAYOUT PLAN APPROVAL 5 09-Jul-15 15-Jul-15
Light Curren
Light Current Systems 83 26-May-15 13-Aug-15
Fire Alarm S
Fire Alarm System 83 26-May-15 13-Aug-15
ZB4TEBELINFRASTRUCTURE FIRE ALARM SERVICE CORRIDOR
APPROVAL (BY OTHERS)
0 26-May-15
ZB4TEBELBASEMENT FLOOR FIRE ALARM SYSTEM PLAN SUBMITTAL 5 02-Aug-15 06-Aug-15
ZB4TEBELBASEMENT FLOOR FIRE ALARM SYSTEM PLAN APPROVAL 5 09-Aug-15 13-Aug-15
Security Sys
Security Systems 0 26-May-15 26-May-15
ZB4TEBELCCTV SYSTEM - SERVICE CORRIDOR APPROVAL (BY OTHERS) 0 26-May-15
Communica
Communication Systems 0 26-May-15 26-May-15
ZB4TEBELTELECOMMUNICATION INFRASTRUCTURE CABLING
APPROVAL (BY OTHERS)
0 26-May-15
SCADA Syste
SCADA System 14 06-Sep-15 17-Sep-15
ZB4TEBEDS BASEMENT FLOOR SCADA SYSTEM LAYOUT PLAN SUBMITTAL 5 06-Sep-15 10-Sep-15
ZB4TEBEDABASEMENT FLOOR SCADA SYSTEM LAYOUT PLAN APPROVAL 5 13-Sep-15 17-Sep-15
Mechanical
Mechanical Systems 60 10-Jun-15 06-Aug-15
HVAC System
HVAC System 47 22-Jun-15 06-Aug-15
ZB4TEBMHSBASEMENT FLOOR HVAC PIPING LAYOUT PLAN SUBMITTAL 15 22-Jun-15 12-Jul-15
ZB4TEBMHA
BASEMENT FLOOR HVAC PIPING LAYOUT PLAN APPROVAL 5 13-Jul-15 20-Jul-15
ZB4TEBMHSBASEMENT FLOOR HVAC DUCT SYSTEM LAYOUT PLAN
SUBMITTAL
10 15-Jul-15 30-Jul-15
ZB4TEBMHA
BASEMENT FLOOR HVAC DUCT SYSTEM LAYOUT PLAN
APPROVAL
5 02-Aug-15 06-Aug-15
Fire Protectio
Fire Protection Systems 22 10-Jun-15 30-Jun-15
ZB4TEBMFSFIRE PROTECTION WORK -SERVICE TUNNEL- OVERALL PLAN
SUBMITTAL
10 10-Jun-15 23-Jun-15
ZB4TEBMFAFIRE PROTECTION WORK -SERVICE TUNNEL- OVERALL PLAN
APPROVAL
5 24-Jun-15 30-Jun-15
Plumbing Sy
Plumbing System 52 17-Jun-15 06-Aug-15
ZB4TEBMWS
BASEMENT FLOOR WATER SUPPLY SYSTEM LAYOUT PLAN
SUBMITTAL
15 17-Jun-15 07-Jul-15
ZB4TEBMDSBASEMENT FLOOR DRAINAGE SYSTEM LAYOUT PLAN
SUBMITTAL
15 17-Jun-15 07-Jul-15
ZB4TEBMWA
BASEMENT FLOOR WATER SUPPLY SYSTEM LAYOUT PLAN
APPROVAL
5 08-Jul-15 14-Jul-15
ZB4TEBMDA
BASEMENT FLOOR DRAINAGE SYSTEM LAYOUT PLAN
APPROVAL
5 08-Jul-15 14-Jul-15
ZB4TEBMWS
SUMP PIT DETAILS & SECTIONS SUBMITTAL 15 08-Jul-15 30-Jul-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4
2015 2016
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 21 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish
ZB4TEBMWA
SUMP PIT DETAILS & SECTIONS APPROVAL 5 02-Aug-15 06-Aug-15
Composite D
Composite Drawing 21 16-Aug-15 03-Sep-15
ZB4TEBCS20 SERVICE TUNNEL COMPOSITE LAYOUT PLAN SUBMITTAL 10 16-Aug-15 27-Aug-15
ZB4TEBCA20 SERVICE TUNNEL COMPOSITE LAYOUT PLAN APPROVAL 5 30-Aug-15 03-Sep-15
General Sho
General Shop Drawings 99 24-Jun-15 28-Sep-15
Electrical Sys
Electrical Systems 99 24-Jun-15 28-Sep-15
ZB4TETEGS ELECTRICAL INSTALLATION DETAILS SUBMITTAL 5 26-Jul-15 30-Jul-15
ZB4TETEGAELECTRICAL INSTALLATION DETAILS APPROVAL 5 02-Aug-15 06-Aug-15
Power Syste
Power System 14 16-Aug-15 27-Aug-15
ZB4TETEPPOWER S.L.D AND PANEL BOARD SCHEDULE SUBMITTAL 5 16-Aug-15 20-Aug-15
ZB4TETEPPOWER S.L.D AND PANEL BOARD SCHEDULE APPROVAL 5 23-Aug-15 27-Aug-15
Lighting Sys
Lighting System 22 08-Jul-15 30-Jul-15
ZB4TETELLIGHTING FIXTURE SCHEDULE SUBMITTAL 5 08-Jul-15 14-Jul-15
ZB4TETELLIGHTING FIXTURE SCHEDULE APPROVAL 5 15-Jul-15 22-Jul-15
ZB4TETELKNX SYSTEM RISER DIAGRAM SUBMITTAL 5 15-Jul-15 22-Jul-15
ZB4TETELKNX SYSTEM RISER DIAGRAM APPROVAL 5 26-Jul-15 30-Jul-15
Light Curren
Light Current Systems 35 24-Jun-15 28-Jul-15
ZB4TETELLIGHT CURRENT TYPICAL INSTALLATION DETAILS SUBMITTAL 5 24-Jun-15 30-Jun-15
ZB4TETELLIGHT CURRENT TYPICAL INSTALLATION DETAILS APPROVAL 5 01-Jul-15 07-Jul-15
Fire Alarm S
Fire Alarm System 15 08-Jul-15 22-Jul-15
ZB4TETE
FIRE ALARM RISER DIAGRAM SUBMITTAL 5 08-Jul-15 14-Jul-15
ZB4TETE
FIRE ALARM RISER DIAGRAM APPROVAL 5 15-Jul-15 22-Jul-15
Security Sy
Security Systems 15 13-Jul-15 28-Jul-15
ZB4TETE
IPCCTV RISER DIAGRAM SUBMITTAL (By Others) 5 13-Jul-15 20-Jul-15
ZB4TETE
IPCCTV RISER DIAGRAM APPROVAL (By Others) 5 21-Jul-15 28-Jul-15
SCADA Sys
SCADA System 15 13-Sep-15 28-Sep-15
ZB4TETEDSCADA SYSTEM RISER DIAGRAM SUBMITTAL 5 13-Sep-15 17-Sep-15
ZB4TETEDSCADA SYSTEM RISER DIAGRAM APPROVAL 5 20-Sep-15 28-Sep-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4
2015 2016
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 22 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish
Site Layout
Site Layout 235 27-May-15 10-Jan-16
Electrical Sy
Electrical Systems 196 27-May-15 02-Dec-15
Tunnel Mediu
Tunnel Medium Voltage Network 22 12-Nov-15 02-Dec-15
ZB4LEBEPS5GROUND FLOOR MV NETWORK LAYOUT PLAN SUBMITTAL 10 12-Nov-15 25-Nov-15
ZB4LEBEPA GROUND FLOOR MV NETWORK LAYOUT PLAN APPROVAL 5 26-Nov-15 02-Dec-15
Tunnel Low V
Tunnel Low Voltage Network 52 27-May-15 14-Jul-15
ZB4LEBELS5
GROUND FLOOR LV NETWORK LAYOUT PLAN SUBMITTAL 25 27-May-15 30-Jun-15
ZB4LEBELAGROUND FLOOR LV NETWORK LAYOUT PLAN APPROVAL 10 01-Jul-15 14-Jul-15
Power Syste
Power System 52 06-Sep-15 28-Oct-15
ZB4LEBEPS4GROUND FLOOR POWER SYSTEM LAYOUT PLAN SUBMITTAL 25 06-Sep-15 13-Oct-15
ZB4LEBEPA GROUND FLOOR POWER SYSTEM LAYOUT PLAN APPROVAL 10 15-Oct-15 28-Oct-15
Lighting Sys
Lighting System 44 26-Jul-15 03-Sep-15
ZB4LEBELS3
GROUND FLOOR LIGHTING SYSTEM LAYOUT PLAN SUBMITTAL 25 26-Jul-15 27-Aug-15
ZB4LEBELAGROUND FLOOR LIGHTING SYSTEM LAYOUT PLAN APPROVAL 5 30-Aug-15 03-Sep-15
SCADA Syste
SCADA System 15 20-Sep-15 05-Oct-15
ZB4LEBEDS GROUND FLOOR SCADA SYSTEM LAYOUT PLAN SUBMITTAL 5 20-Sep-15 28-Sep-15
ZB4LEBEDAGROUND FLOOR SCADA SYSTEM LAYOUT PLAN APPROVAL 5 29-Sep-15 05-Oct-15
Composite D
Composite Drawing 22 03-Dec-15 24-Dec-15
ZB4LEBCS30 SITE LAY OUT COMPOSITE LAYOUT PLAN SUBMITTAL 10 03-Dec-15 16-Dec-15
ZB4LEBCA30 SITE LAY OUT COMPOSITE LAYOUT PLAN APPROVAL 5 17-Dec-15 24-Dec-15
General Sho
General Shop Drawings 190 08-Jul-15 10-Jan-16
Electrical Sys
Electrical Systems 190 08-Jul-15 10-Jan-16
ZB4LETEGS ELECTRICAL INSTALLATION DETAILS SUBMITTAL 25 26-Jul-15 27-Aug-15
ZB4LETEGAELECTRICAL INSTALLATION DETAILS APPROVAL 5 30-Aug-15 03-Sep-15
Power Syste
Power System 15 27-Dec-15 10-Jan-16
ZB4LETEPPOWER S.L.D AND PANEL BOARD SCHEDULE SUBMITTAL 5 27-Dec-15 31-Dec-15
ZB4LETEPPOWER S.L.D AND PANEL BOARD SCHEDULE APPROVAL 5 03-Jan-16 10-Jan-16
Lighting Sys
Lighting System 37 08-Jul-15 13-Aug-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4
2015 2016
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 23 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish
ZB4LETELLIGHTING FIXTURE SCHEDULE SUBMITTAL 10 08-Jul-15 22-Jul-15
ZB4LETELLIGHTING FIXTURE SCHEDULE APPROVAL 5 26-Jul-15 30-Jul-15
ZB4LETELLIGHTING FIXTURES DETAILS ON STREET SECTIONS
SUBMITTAL
10 26-Jul-15 06-Aug-15
ZB4LETELLIGHTING FIXTURES DETAILS ON STREET SECTIONS APPROVAL 5 09-Aug-15 13-Aug-15
SCADA Sys
SCADA System 52 13-Sep-15 04-Nov-15
ZB4LETEDSCADA SYSTEM HAND HOLE LAYOUT SUBMITTAL 25 13-Sep-15 21-Oct-15
ZB4LETEDSCADA SYSTEM HAND HOLE LAYOUTAPPROVAL 10 22-Oct-15 04-Nov-15
Materials
Materials 322 27-May-15 02-Apr-16
Building B4 -
Building B4 - A (Mechanical Utilities) 292 27-May-15 05-Mar-16
Electrical Sy
Electrical Systems 285 03-Jun-15 05-Mar-16
Power Syste
Power System 285 03-Jun-15 05-Mar-16
Material Subm
Material Submittal 144 03-Jun-15 21-Oct-15
ZB4EEMS080EMT Material Submittal 10 03-Jun-15 16-Jun-15
ZB4EEMS090IMC Material Submittal 10 03-Jun-15 16-Jun-15
ZB4EEMS040Cable Trays and Ladders Material Submittal 10 10-Jun-15 23-Jun-15
ZB4EEMS110B4-A Building ERMU Material Submittal 10 21-Jul-15 04-Aug-15
ZB4EEMS050LV Cables Fire Resistant Material Submittal 20 08-Jul-15 06-Aug-15
ZB4EEMS030LV Cables Material Submittal 7 16-Aug-15 24-Aug-15
ZB4EEMS180B4-A Building MCC's Material Submittal 10 12-Aug-15 25-Aug-15
ZB4EEMS120B4-A Building Transformers Material Submittal 20 02-Aug-15 27-Aug-15
ZB4EEMS100B4-A Building UPS Material Submittal 20 09-Aug-15 03-Sep-15
ZB4EEMS070MV Cables Material Submittal 7 30-Aug-15 07-Sep-15
ZB4EEMS150B4-A Building EMDB & EDB Material Submittal 10 30-Aug-15 10-Sep-15
ZB4EEMS160B4-A Building Distribution Panels Material Submittal 10 30-Aug-15 10-Sep-15
ZB4EEMS170B4-A Building Bus Bar Material Submittal 10 30-Aug-15 10-Sep-15
ZB4EEMS060LV Earthing Cables Material Submittal 20 23-Aug-15 17-Sep-15
ZB4EEMS130Disconnecting Switch Material Submittal 20 23-Aug-15 17-Sep-15
ZB4EEMS140Wiring Devices Material Submittal 20 23-Aug-15 17-Sep-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4
2015 2016
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 24 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish
ZB4EEMS190B4-A Building VSD Material Submittal 20 20-Sep-15 21-Oct-15
ZB4EEMS200B4-A Building Soft Starter Material Submittal 20 20-Sep-15 21-Oct-15
Material Appr
Material Approvals 136 17-Jun-15 28-Oct-15
ZB4EEMA08 EMT Material Approval 5 17-Jun-15 23-Jun-15
ZB4EEMA09 IMC Material Approval 5 17-Jun-15 23-Jun-15
ZB4EEMA04 Cable Trays and Ladders Material Approval 5 24-Jun-15 30-Jun-15
ZB4EEMA110
B4-A Building ERMU Material Approval 5 05-Aug-15 11-Aug-15
ZB4EEMA05 LV Cables Fire Resistant Material Approval 5 09-Aug-15 13-Aug-15
ZB4EEMA03 LV Cables Material Approval 5 25-Aug-15 31-Aug-15
ZB4EEMA18 B4-A Building MCC's Material Approval 5 26-Aug-15 01-Sep-15
ZB4EEMA12 B4-A Building Transformers Material Approval 5 30-Aug-15 03-Sep-15
ZB4EEMA10 B4-A Building UPS Material Approval 5 06-Sep-15 10-Sep-15
ZB4EEMA07 MV Cables Material Approval 5 08-Sep-15 14-Sep-15
ZB4EEMA15 B4-A Building EMDB & EDB Material Approval 5 13-Sep-15 17-Sep-15
ZB4EEMA16 B4-A Building Distribution Panels Material Approval 5 13-Sep-15 17-Sep-15
ZB4EEMA17 B4-A Building Bus Bar Material Approval 5 13-Sep-15 17-Sep-15
ZB4EEMA06 LV Earthing Cables Material Approval 5 20-Sep-15 28-Sep-15
ZB4EEMA13 Disconnecting Switch Material Approval 5 20-Sep-15 28-Sep-15
ZB4EEMA14 Wiring Devices Material Approval 5 20-Sep-15 28-Sep-15
ZB4EEMA19 B4-A Building VSD Material Approval 5 22-Oct-15 28-Oct-15
ZB4EEMA20 B4-A Building Soft Starter Material Approval 5 22-Oct-15 28-Oct-15
Material PO's
Material PO's 170 01-Jul-15 13-Dec-15
ZB4EEMP080EMT Material PO 5 01-Jul-15 07-Jul-15
ZB4EEMP090IMC Material PO 5 01-Jul-15 07-Jul-15
ZB4EEMP040Cable Trays and Ladders Material PO 10 15-Jul-15 30-Jul-15
ZB4EEMP110B4-A Building ERMU Material PO 10 12-Aug-15 25-Aug-15
ZB4EEMP030LV Cables Material PO 10 01-Sep-15 14-Sep-15
ZB4EEMP180B4-A Building MCC's Material PO 10 02-Sep-15 15-Sep-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4
2015 2016
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 25 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish
ZB4EEMP050LV Cables Fire Resistant Material PO 10 06-Sep-15 17-Sep-15
ZB4EEMP030Power Circuits Cables and Wires PO 5 13-Sep-15 17-Sep-15
ZB4EEMP150B4-A Building EMDB & EDB Material PO 10 20-Sep-15 05-Oct-15
ZB4EEMP160B4-A Building Distribution Panels Material PO 10 20-Sep-15 05-Oct-15
ZB4EEMP170B4-A Building Bus Bar Material PO 10 20-Sep-15 05-Oct-15
ZB4EEMP130Disconnecting Switch Material PO 10 29-Sep-15 13-Oct-15
ZB4EEMP140Wiring Devices Material PO 10 29-Sep-15 13-Oct-15
ZB4EEMP120B4-A Building Transformers Material PO 10 11-Oct-15 25-Oct-15
ZB4EEMP100B4-A Building UPS Material PO 10 19-Oct-15 01-Nov-15
ZB4EEMP070MV Cables Material PO 10 21-Oct-15 03-Nov-15
ZB4EEMP060LV Earthing Cables Material PO 10 02-Nov-15 15-Nov-15
ZB4EEMP190B4-A Building VSD Material PO 10 30-Nov-15 13-Dec-15
ZB4EEMP200B4-A Building Soft Starter Material PO 10 30-Nov-15 13-Dec-15
Material Deliv
Material Delivery at Site 247 08-Jul-15 05-Mar-16
ZB4EEMD08 EMT Material Delivery 10 08-Jul-15 20-Jul-15
ZB4EEMD09 IMC Material Delivery 10 08-Jul-15 20-Jul-15
ZB4EEMD03 Power Circuits Cables and Wires Partial Delivery 52 19-Sep-15 22-Nov-15
ZB4EEMD03 LV Cables Material Delivery 60 15-Sep-15 28-Nov-15
ZB4EEMD110
B4-A Building ERMU Material Delivery 78 26-Aug-15 29-Nov-15
ZB4EEMD18 B4-A Building MCC's Material Delivery 70 16-Sep-15 10-Dec-15
ZB4EEMD16 B4-A Building Distribution Panels Material Delivery 60 07-Oct-15 16-Dec-15
ZB4EEMD04 Cable Trays and Ladders Material Partial Delivery 120 01-Aug-15 22-Dec-15
ZB4EEMD12 B4-A Building Transformers Material Delivery 60 26-Oct-15 04-Jan-16
ZB4EEMD05 LV Cables Fire Resistant Material Delivery 90 19-Sep-15 06-Jan-16
ZB4EEMD15 B4-A Building EMDB & EDB Material Delivery 78 07-Oct-15 09-Jan-16
ZB4EEMD17 B4-A Building Bus Bar Material Delivery 78 07-Oct-15 09-Jan-16
ZB4EEMD07 MV Cables Material Delivery 60 04-Nov-15 14-Jan-16
ZB4EEMD13 Disconnecting Switch Material Delivery 78 15-Oct-15 16-Jan-16
Q2 Q3 Q4 Q1 Q2 Q3 Q4
2015 2016
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 26 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish
ZB4EEMD14 Wiring Devices Material Delivery 78 15-Oct-15 16-Jan-16
ZB4EEMD06 LV Earthing Cables Material Partial Delivery 60 16-Nov-15 27-Jan-16
ZB4EEMD19 B4-A Building VSD Material Delivery 60 14-Dec-15 24-Feb-16
ZB4EEMD20 B4-A Building Soft Starter Material Delivery 60 14-Dec-15 24-Feb-16
ZB4EEMD10 B4-A Building UPS Material Delivery 104 02-Nov-15 05-Mar-16
Lighting Sys
Lighting System 157 16-Aug-15 16-Jan-16
Material Subm
Material Submittal 36 16-Aug-15 17-Sep-15
ZB4EEMS210B4 Buildings Lighting Fixtures Material Submittal 20 16-Aug-15 10-Sep-15
ZB4EEMS220B4 Buildings CENTRAL MONITORING SYSTEM Material Submittal 20 16-Aug-15 10-Sep-15
ZB4EEMS230B4 Buildings KNX/EIP SYSTEM Material Submittal 20 23-Aug-15 17-Sep-15
Material Appr
Material Approvals 22 13-Sep-15 05-Oct-15
ZB4EEMA21 B4 Buildings Lighting Fixtures Material Approval 10 13-Sep-15 28-Sep-15
ZB4EEMA22 B4 Buildings CENTRAL MONITORING SYSTEM Material Approval 10 13-Sep-15 28-Sep-15
ZB4EEMA23 B4 Buildings KNX/EIP SYSTEM Material Approval 10 20-Sep-15 05-Oct-15
Material PO's
Material PO's 52 13-Sep-15 04-Nov-15
ZB4EEMP240B4A Building Lighting Wires Material PO 10 13-Sep-15 28-Sep-15
ZB4EEMP210B4A Building Lighting Fixtures Material PO 10 08-Oct-15 22-Oct-15
ZB4EEMP220B4A Building CENTRAL MONITORING SYSTEM Material PO 10 15-Oct-15 28-Oct-15
ZB4EEMP230B4A Building KNX/EIP SYSTEM Material PO 10 22-Oct-15 04-Nov-15
Material Deliv
Material Delivery at Site 112 29-Sep-15 16-Jan-16
ZB4EEMD24 B4A Building Lighting Wires Material Partial Delivery 10 29-Sep-15 11-Oct-15
ZB4EEMD21 B4A Building Lighting Fixtures Material Delivery 45 24-Oct-15 14-Dec-15
ZB4EEMD22 B4A Building CENTRAL MONITORING SYSTEM Material Delivery 65 29-Oct-15 14-Jan-16
ZB4EEMD23 B4A Building KNX/EIP SYSTEM Material Delivery 60 05-Nov-15 16-Jan-16
Cable Tray S
Cable Tray System 179 15-Jul-15 05-Jan-16
Material PO's
Material PO's 91 15-Jul-15 13-Oct-15
ZB4EEMP250Cable Trays and Ladders For Equipments Material PO 10 15-Jul-15 30-Jul-15
ZB4EEMP260LV Cables For Equipments Material PO 10 01-Sep-15 14-Sep-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4
2015 2016
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 27 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish
ZB4EEMP270LV Earthing For Equipments Cables Material PO 10 29-Sep-15 13-Oct-15
Material Deliv
Material Delivery at Site 164 01-Aug-15 05-Jan-16
ZB4EEMD25 Cable Trays and Ladders Material Delivery 10 01-Aug-15 11-Aug-15
ZB4EEMD26 LV Cables Material Delivery 60 15-Sep-15 28-Nov-15
ZB4EEMD27 LV Earthing Cables Material Delivery 70 15-Oct-15 05-Jan-16
Earthing Sys
Earthing System 206 10-Jun-15 27-Dec-15
Material Subm
Material Submittal 30 10-Jun-15 07-Jul-15
ZB4EEMS010Earthing System Material Submittal 20 10-Jun-15 07-Jul-15
Material Appr
Material Approvals 15 08-Jul-15 22-Jul-15
ZB4EEMA01 Earthing System Material Approval 10 08-Jul-15 22-Jul-15
Material PO's
Material PO's 15 25-Aug-15 07-Sep-15
ZB4EEMP010Earthing System Material PO 10 25-Aug-15 07-Sep-15
Material Deliv
Material Delivery at Site 112 08-Sep-15 27-Dec-15
ZB4EEMD01 Earthing System Material Delivery 90 08-Sep-15 27-Dec-15
Lightning Sy
Lightning System 205 10-Jun-15 26-Dec-15
Material Subm
Material Submittal 30 10-Jun-15 07-Jul-15
ZB4EEMS020LIGHTNING System Material Submittal 20 10-Jun-15 07-Jul-15
Material Appr
Material Approvals 15 08-Jul-15 22-Jul-15
ZB4EEMA02 LIGHTNING System Material Approval 10 08-Jul-15 22-Jul-15
Material PO's
Material PO's 14 09-Aug-15 20-Aug-15
ZB4EEMP020LIGHTNING System Material PO 10 09-Aug-15 20-Aug-15
Material Deliv
Material Delivery at Site 130 22-Aug-15 26-Dec-15
ZB4EEMD02 LIGHTNING System Material Delivery 104 22-Aug-15 26-Dec-15
Light Curren
Light Current Systems 156 26-Jul-15 22-Dec-15
Fire Alarm Sy
Fire Alarm System 156 26-Jul-15 22-Dec-15
Material Sub
Material Submittal 29 26-Jul-15 20-Aug-15
ZB4EEMS2Fire Alarm System Material Submittal 20 26-Jul-15 20-Aug-15
Material App
Material Approvals 14 23-Aug-15 03-Sep-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4
2015 2016
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 28 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish
ZB4EEMA2Fire Alarm System Material Approval 10 23-Aug-15 03-Sep-15
Material PO'
Material PO's 14 06-Sep-15 17-Sep-15
ZB4EEMP2Fire Alarm System Devices Material PO 10 06-Sep-15 17-Sep-15
ZB4EEMP2Fire Alarm System Fire Alarm Cable Material PO 10 06-Sep-15 17-Sep-15
ZB4EEMP3Fire Alarm System FACP Material PO 10 06-Sep-15 17-Sep-15
Material Del
Material Delivery at Site 97 19-Sep-15 22-Dec-15
ZB4EEMD2Fire Alarm System Devices Material Delivery 78 19-Sep-15 22-Dec-15
ZB4EEMD2Fire Alarm System Fire Alarm Cable Material Delivery 78 19-Sep-15 22-Dec-15
ZB4EEMD3Fire Alarm System FACP Material Delivery 78 19-Sep-15 22-Dec-15
SCADA Sys
SCADA System 120 05-Nov-15 28-Feb-16
Material Subm
Material Submittal 7 05-Nov-15 11-Nov-15
ZB4EEMS250SCADA System Material Submittal 5 05-Nov-15 11-Nov-15
Material Appr
Material Approvals 7 12-Nov-15 18-Nov-15
ZB4EEMA25 SCADA System Material Approval 5 12-Nov-15 18-Nov-15
Material PO's
Material PO's 7 19-Nov-15 25-Nov-15
ZB4EEMP310SCADA System Material PO 5 19-Nov-15 25-Nov-15
Material Deliv
Material Delivery at Site 97 26-Nov-15 28-Feb-16
ZB4EEMD31 SCADA System Material Delivery 78 26-Nov-15 28-Feb-16
Mechanical
Mechanical Systems 265 27-May-15 08-Feb-16
HVAC Syste
HVAC System 260 27-May-15 04-Feb-16
Material Subm
Material Submittal 155 27-May-15 25-Oct-15
ZB4EEMS390Black welded (ERW) steel piping Material Submittal 5 01-Jun-15 07-Jun-15
ZB4EEMS440Variable Air Volume (VAV) Boxes Material Submittal 15 27-May-15 16-Jun-15
ZB4EEMS260Chillers Material Submittal 12 04-Jun-15 21-Jun-15
ZB4EEMS270Cooling Towers Material Submittal 10 28-Jun-15 09-Jul-15
ZB4EEMS310AHU Material Submittal 12 28-Jun-15 13-Jul-15
ZB4EEMS410Chilled Water Valves Material Submittal 22 14-Jun-15 13-Jul-15
ZB4EEMS380Child pipe hangers and support Material Submittal 15 28-Jun-15 19-Jul-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4
2015 2016
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 29 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish
ZB4EEMS280Child Water Pumps Material Submittal 22 02-Jul-15 04-Aug-15
ZB4EEMS315Expansion Tanks Material Submittal 12 19-Jul-15 04-Aug-15
ZB4EEMS370Black seamless steel piping Material Submittal 15 19-Jul-15 09-Aug-15
ZB4EEMS300Heat Exchangers Material Submittal 22 08-Jul-15 10-Aug-15
ZB4EEMS320Metal Sheet Duct Material Submittal 15 26-Jul-15 13-Aug-15
ZB4EEMS400UPVC piping (16 bar) Material Submittal 22 26-Jul-15 24-Aug-15
ZB4EEMS340Chimney Black Steel Sheet Material Sample Submittal 18 02-Aug-15 25-Aug-15
ZB4EEMS330FD & VD Material Submittal 22 02-Aug-15 31-Aug-15
ZB4EEMS350Fire Smoke Dampers Material Submittal 22 09-Aug-15 07-Sep-15
ZB4EEMS360Duct Insulation Material Submittal 22 11-Aug-15 09-Sep-15
ZB4EEMS430Air Separators Material Submittal 22 16-Aug-15 14-Sep-15
ZB4EEMS420Chilled Water Piping Insulation Material Submittal 22 23-Aug-15 21-Sep-15
ZB4EEMS450Air Outlets Material Submittal 22 30-Aug-15 30-Sep-15
ZB4EEMS460Water Treatment and Chemical Cleaning System Material Submittal 22 06-Sep-15 08-Oct-15
ZB4EEMS470Over Head Crane Material Submittal 22 06-Sep-15 08-Oct-15
ZB4EEMS480Monorail Crane Material Submittal 22 06-Sep-15 08-Oct-15
ZB4EEMS290Testing, Balancing & Commisioning system Third Part Submittal 22 20-Sep-15 25-Oct-15
Material Appr
Material Approvals 150 08-Jun-15 01-Nov-15
ZB4EEMA39 Black welded (ERW) steel piping Material Approval 5 08-Jun-15 14-Jun-15
ZB4EEMA44 Variable Air Volume (VAV) Boxes Material Approval 5 17-Jun-15 23-Jun-15
ZB4EEMA26 Chillers System Material Approval 5 22-Jun-15 28-Jun-15
ZB4EEMA27 Cooling Towers System Material Approval 5 12-Jul-15 19-Jul-15
ZB4EEMA31 AHU System Material Approval 5 14-Jul-15 21-Jul-15
ZB4EEMA41 Chilled Water Valves Material Approval 5 14-Jul-15 21-Jul-15
ZB4EEMA38 Child pipe hangers and support Material Approval 5 20-Jul-15 27-Jul-15
ZB4EEMA28 Child Water Pumps Material Approval 5 05-Aug-15 11-Aug-15
ZB4EEMA31 Expansion Tanks Material Approval 5 05-Aug-15 11-Aug-15
ZB4EEMA37 Black seamless steel piping Material Approval 5 10-Aug-15 16-Aug-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4
2015 2016
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 30 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish
ZB4EEMA30 Heat Exchangers System Material Approval 5 11-Aug-15 17-Aug-15
ZB4EEMA32 Metal Sheet Duct System Material Approval 5 16-Aug-15 20-Aug-15
ZB4EEMA40 UPVC piping (16 bar) Material Approval 5 25-Aug-15 31-Aug-15
ZB4EEMA34 Chimney Black Steel Sheet Material Sample Approval 5 26-Aug-15 01-Sep-15
ZB4EEMA33 FD & VD Material Approval 5 01-Sep-15 07-Sep-15
ZB4EEMA35 Fire Smoke Dampers Material Approval 5 08-Sep-15 14-Sep-15
ZB4EEMA36 Duct Insulation Material Approval 5 10-Sep-15 16-Sep-15
ZB4EEMA43 Air Separators Material Approval 5 15-Sep-15 21-Sep-15
ZB4EEMA42 Chilled Water Piping Insulation Material Approval 5 22-Sep-15 30-Sep-15
ZB4EEMA45 Air Outlets Material Approval 5 01-Oct-15 08-Oct-15
ZB4EEMA46 Water Treatment and Chemical Cleaning System Material Approval 5 11-Oct-15 18-Oct-15
ZB4EEMA47 Over Head Crane Material Approval 5 11-Oct-15 18-Oct-15
ZB4EEMA48 Monorail Crane Material Approval 5 11-Oct-15 18-Oct-15
ZB4EEMA29 Testing, Balancing & Commisioning system Third Part Approval 5 26-Oct-15 01-Nov-15
Material PO's
Material PO's 142 15-Jun-15 01-Nov-15
ZB4EEMP450Black welded (ERW) steel piping Material PO 10 15-Jun-15 28-Jun-15
ZB4EEMP320Chillers System Material PO 10 29-Jun-15 12-Jul-15
ZB4EEMP330Cooling Towers System Material PO 10 20-Jul-15 03-Aug-15
ZB4EEMP370AHU System Material PO 10 22-Jul-15 05-Aug-15
ZB4EEMP470Chilled Water Valves Material PO 10 22-Jul-15 05-Aug-15
ZB4EEMP440Child pipe hangers and support Material PO 10 28-Jul-15 10-Aug-15
ZB4EEMP500Variable Air Volume (VAV) Boxes Material PO 10 28-Jul-15 10-Aug-15
ZB4EEMP340Child Water Pumps Material PO 10 12-Aug-15 25-Aug-15
ZB4EEMP315Expansion Tanks Material PO 10 12-Aug-15 25-Aug-15
ZB4EEMP430Black seamless steel piping Material PO 10 17-Aug-15 30-Aug-15
ZB4EEMP360Heat Exchangers System Material PO 10 18-Aug-15 31-Aug-15
ZB4EEMP380Metal Sheet Duct System Material PO 10 23-Aug-15 03-Sep-15
ZB4EEMP460UPVC piping (16 bar) Material PO 10 01-Sep-15 14-Sep-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4
2015 2016
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 31 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish
ZB4EEMP390FD & VD Material PO 10 08-Sep-15 21-Sep-15
ZB4EEMP410Fire Smoke Dampers Material PO 10 15-Sep-15 30-Sep-15
ZB4EEMP420Duct Insulation Material PO 10 17-Sep-15 04-Oct-15
ZB4EEMP490Air Separators Material PO 10 22-Sep-15 08-Oct-15
ZB4EEMP480Chilled Water Piping Insulation Material PO 10 01-Oct-15 18-Oct-15
ZB4EEMP400Chimney Black Steel Sheet Material PO 10 07-Oct-15 21-Oct-15
ZB4EEMP510Air Outlets Material PO 10 11-Oct-15 25-Oct-15
ZB4EEMP520Water Treatment and Chemical Cleaning System Material PO 10 19-Oct-15 01-Nov-15
ZB4EEMP530Over Head Crane Material PO 10 19-Oct-15 01-Nov-15
ZB4EEMP540Monorail Crane Material PO 10 19-Oct-15 01-Nov-15
Material Deliv
Material Delivery at Site 225 29-Jun-15 04-Feb-16
ZB4EEMD44 Child pipe hangers and support Material ( Partial )Delivery 36 11-Aug-15 21-Sep-15
ZB4EEMD45 Black welded (ERW) steel piping Material ( Partial )Delivery 104 29-Jun-15 03-Nov-15
ZB4EEMD33 Cooling Towers System Material Delivery 78 04-Aug-15 07-Nov-15
ZB4EEMD37 AHU System Material Delivery 78 06-Aug-15 09-Nov-15
ZB4EEMD32 Chillers Material Delivery 104 13-Jul-15 17-Nov-15
ZB4EEMD38 Metal Sheet Duct System Partial Material Delivery / Fabrication 65 05-Sep-15 23-Nov-15
ZB4EEMD31 Expansion Tanks Material Delivery 78 26-Aug-15 29-Nov-15
ZB4EEMD43 Black seamless steel piping Material ( Partial )Delivery 78 31-Aug-15 03-Dec-15
ZB4EEMD42 Duct Insulation Material Delivery 52 05-Oct-15 06-Dec-15
ZB4EEMD47 Chilled Water Valves Material ( Partial )Delivery 104 06-Aug-15 09-Dec-15
ZB4EEMD40 Chimney Material Fabrication / Delivery 45 22-Oct-15 13-Dec-15
ZB4EEMD50 Variable Air Volume (VAV) Boxes Material Delivery 104 11-Aug-15 14-Dec-15
ZB4EEMD36 Heat Exchangers System Material Delivery 90 01-Sep-15 19-Dec-15
ZB4EEMD46 UPVC piping (16 bar) Material ( Partial )Delivery 78 15-Sep-15 19-Dec-15
ZB4EEMD39 FD & VD Material Delivery 80 22-Sep-15 29-Dec-15
ZB4EEMD34 Child Water Pumps Material Delivery 104 26-Aug-15 30-Dec-15
ZB4EEMD41 Fire Smoke Dampers Material Delivery 78 01-Oct-15 03-Jan-16
Q2 Q3 Q4 Q1 Q2 Q3 Q4
2015 2016
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 32 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish
ZB4EEMD52 Water Treatment and Chemical Cleaning System Material Delivery On Site 60 02-Nov-15 12-Jan-16
ZB4EEMD48 Chilled Water Piping Insulation Material ( Partial ) Delivery 75 19-Oct-15 16-Jan-16
ZB4EEMD54 Monorail Crane Material Delivery On Site 65 02-Nov-15 18-Jan-16
ZB4EEMD49 Air Separators Material Delivery 90 10-Oct-15 26-Jan-16
ZB4EEMD51 Air Outlets Material Delivery 78 26-Oct-15 27-Jan-16
ZB4EEMD53 Over Head Crane Material Delivery On Site 78 02-Nov-15 03-Feb-16
ZB4EEMD35 Testing, Balancing & Commisioning system Third Part On Site 0 04-Feb-16
Fire Protect
Fire Protection Systems 245 27-May-15 19-Jan-16
Material Subm
Material Submittal 157 27-May-15 27-Oct-15
ZB4EEMS560Black Seamless Schedule 40 Material Submittal 10 27-May-15 09-Jun-15
ZB4EEMS580Electrical Fire Pump Material Submittal 15 27-May-15 16-Jun-15
ZB4EEMS590Diesel Fire Pump Material Submittal 15 27-May-15 16-Jun-15
ZB4EEMS600Jockey Pump Material Submittal 15 27-May-15 16-Jun-15
ZB4EEMS570VALVES Material Submittal 10 22-Jun-15 05-Jul-15
ZB4EEMS610Water Flow Switches Material Submittal 18 22-Jun-15 15-Jul-15
ZB4EEMS620Upright Sprinkler Heads Material Submittal 18 08-Jul-15 04-Aug-15
ZB4EEMS640Fire Hose Stations Material Submittal 22 02-Aug-15 31-Aug-15
ZB4EEMS650Dry Powder Manual Fire Extinguishers Material Submittal 22 23-Aug-15 21-Sep-15
ZB4EEMS670Roof Manifold Material Submittal 22 23-Aug-15 21-Sep-15
ZB4EEMS630CO2 System Material Submittal 12 11-Oct-15 27-Oct-15
ZB4EEMS660Automatic Dry Powder Fire Extinguishers Material Submittal 12 11-Oct-15 27-Oct-15
Material Appr
Material Approvals 150 10-Jun-15 03-Nov-15
ZB4EEMA56 Black Seamless Schedule 40 Material Approval 5 10-Jun-15 16-Jun-15
ZB4EEMA58 Electrical Fire Pump Material Approval 5 17-Jun-15 23-Jun-15
ZB4EEMA59 Diesel Fire Pump Material Approval 5 17-Jun-15 23-Jun-15
ZB4EEMA60 Jockey Pump Material Approval 5 17-Jun-15 23-Jun-15
ZB4EEMA57 VALVES Material Approval 5 06-Jul-15 12-Jul-15
ZB4EEMA61 Water Flow Switches Material Approval 5 19-Jul-15 26-Jul-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4
2015 2016
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 33 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish
ZB4EEMA62 Upright Sprinkler Heads Material Approval 5 05-Aug-15 11-Aug-15
ZB4EEMA64 Fire Hose Stations Material Approval 5 01-Sep-15 07-Sep-15
ZB4EEMA65 Dry Powder Manual Fire Extinguishers Material Approval 5 22-Sep-15 30-Sep-15
ZB4EEMA67 Roof Manifold Material Approval 5 22-Sep-15 30-Sep-15
ZB4EEMA63 CO2 System Material Approval 5 28-Oct-15 03-Nov-15
ZB4EEMA66 Automatic Dry Powder Fire Extinguishers Material Approval 5 28-Oct-15 03-Nov-15
Material PO's
Material PO's 157 17-Jun-15 17-Nov-15
ZB4EEMP560Black Seamless Schedule 40 Material PO 10 17-Jun-15 30-Jun-15
ZB4EEMP580Electrical Fire Pump Material PO 10 24-Jun-15 07-Jul-15
ZB4EEMP590Diesel Fire Pump Material PO 10 24-Jun-15 07-Jul-15
ZB4EEMP600Jockey Pump Material PO 10 24-Jun-15 07-Jul-15
ZB4EEMP570VALVES Material PO 10 13-Jul-15 28-Jul-15
ZB4EEMP610Water Flow Switches Material PO 10 27-Jul-15 09-Aug-15
ZB4EEMP620Upright Sprinkler Heads Material PO 10 12-Aug-15 25-Aug-15
ZB4EEMP640Fire Hose Stations Material PO 10 08-Sep-15 21-Sep-15
ZB4EEMP650Dry Powder Manual Fire Extinguishers Material PO 10 01-Oct-15 18-Oct-15
ZB4EEMP670Roof Manifold Material PO 10 01-Oct-15 18-Oct-15
ZB4EEMP630CO2 System Material PO 10 04-Nov-15 17-Nov-15
ZB4EEMP660Automatic Dry Powder Fire Extinguishers Material PO 10 04-Nov-15 17-Nov-15
Material Deliv
Material Delivery at Site 207 01-Jul-15 19-Jan-16
ZB4EEMD56 Black Seamless Schedule 40 Material Partial Delivery 52 01-Jul-15 01-Sep-15
ZB4EEMD57 VALVES Material Delivery 52 29-Jul-15 29-Sep-15
ZB4EEMD61 Water Flow Switches Material Delivery 78 10-Aug-15 12-Nov-15
ZB4EEMD62 Upright Sprinkler Heads Material Delivery 78 26-Aug-15 29-Nov-15
ZB4EEMD58 Electrical Fire Pump Material Delivery 130 08-Jul-15 13-Dec-15
ZB4EEMD59 Diesel Fire Pump Material Delivery 130 08-Jul-15 13-Dec-15
ZB4EEMD60 Jockey Pump Material Delivery 130 08-Jul-15 13-Dec-15
ZB4EEMD64 Fire Hose Stations Material Delivery 78 22-Sep-15 27-Dec-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4
2015 2016
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 34 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish
ZB4EEMD63 CO2 System Material Delivery 52 18-Nov-15 19-Jan-16
ZB4EEMD65 Dry Powder Manual Fire Extinguishers Material Delivery 78 19-Oct-15 19-Jan-16
ZB4EEMD66 Automatic Dry Powder Fire Extinguishers Material Delivery 52 18-Nov-15 19-Jan-16
ZB4EEMD67 Roof Manifold Material Delivery 78 19-Oct-15 19-Jan-16
Plumbing Sy
Plumbing System 265 27-May-15 08-Feb-16
Material Subm
Material Submittal 170 27-May-15 08-Nov-15
ZB4EEMS780Domestic Water Booster Pump Material Submittal 15 27-May-15 16-Jun-15
ZB4EEMS790Irrigation Water Booster Pump Material Submittal 15 27-May-15 16-Jun-15
ZB4EEMS800Water Circulating Pumps Material Submittal 15 27-May-15 16-Jun-15
ZB4EEMS810Submersible Waste Water Pump Material Submittal 15 27-May-15 16-Jun-15
ZB4EEMS680Pipes PPR (PN 20) Material Submittal 18 28-Jun-15 22-Jul-15
ZB4EEMS700Pipes UPVC (PN 10) Material Submittal 18 28-Jun-15 22-Jul-15
ZB4EEMS690Pipes HDPE (PN 10) Material Submittal 22 19-Jul-15 18-Aug-15
ZB4EEMS740Roof Drains Material Submittal 15 02-Aug-15 20-Aug-15
ZB4EEMS710Gate Valves Material Submittal 22 02-Aug-15 31-Aug-15
ZB4EEMS760Trench Drain Material Submittal 22 09-Aug-15 07-Sep-15
ZB4EEMS720Water Tank Accessories Material Submittal 22 16-Aug-15 14-Sep-15
ZB4EEMS770Hose Bibs Material Submittal 22 23-Aug-15 21-Sep-15
ZB4EEMS730Pump Room Accessories Material Submittal 22 07-Oct-15 08-Nov-15
ZB4EEMS750Heavy Duty Cast Iron Cover for Inspection Chamber Material Submittal 22 07-Oct-15 08-Nov-15
Material Appr
Material Approvals 162 17-Jun-15 22-Nov-15
ZB4EEMA78 Domestic Water Booster Pump Material Approval 10 17-Jun-15 30-Jun-15
ZB4EEMA79 Irrigation Water Booster Pump Material Approval 10 17-Jun-15 30-Jun-15
ZB4EEMA80 Water Circulating Pumps Material Approval 10 17-Jun-15 30-Jun-15
ZB4EEMA81 Submersible Waste Water Pump Material Approval 10 17-Jun-15 30-Jun-15
ZB4EEMA68 Pipes PPR (PN 20) Material Approval 10 26-Jul-15 06-Aug-15
ZB4EEMA70 Pipes UPVC (PN 10) Material Approval 10 26-Jul-15 06-Aug-15
ZB4EEMA69 Pipes HDPE (PN 10) Material Approval 10 19-Aug-15 01-Sep-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4
2015 2016
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 35 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish
ZB4EEMA74 Roof Drains Material Approval 10 23-Aug-15 03-Sep-15
ZB4EEMA71 Gate Valves Material Approval 10 01-Sep-15 14-Sep-15
ZB4EEMA76 Trench Drain Material Approval 10 08-Sep-15 21-Sep-15
ZB4EEMA72 Water Tank Accessories Material Approval 10 15-Sep-15 30-Sep-15
ZB4EEMA77 Hose Bibs Material Approval 10 22-Sep-15 08-Oct-15
ZB4EEMA73 Pump Room Accessories Material Approval 10 09-Nov-15 22-Nov-15
ZB4EEMA75 Heavy Duty Cast Iron Cover for Inspection Chamber Material Approval 10 09-Nov-15 22-Nov-15
Material PO's
Material PO's 162 01-Jul-15 06-Dec-15
ZB4EEMP780Domestic Water Booster Pump Material PO 10 01-Jul-15 14-Jul-15
ZB4EEMP790Irrigation Water Booster Pump Material PO 10 01-Jul-15 14-Jul-15
ZB4EEMP800Water Circulating Pumps Material PO 10 01-Jul-15 14-Jul-15
ZB4EEMP810Submersible Waste Water Pump Material PO 10 01-Jul-15 14-Jul-15
ZB4EEMP680Pipes PPR (PN 20) Material PO 10 09-Aug-15 20-Aug-15
ZB4EEMP700Pipes UPVC (PN 10) Material PO 10 09-Aug-15 20-Aug-15
ZB4EEMP690Pipes HDPE (PN 10) Material PO 10 02-Sep-15 15-Sep-15
ZB4EEMP740Roof Drains Material PO 10 06-Sep-15 17-Sep-15
ZB4EEMP710Gate Valves Material PO 10 15-Sep-15 30-Sep-15
ZB4EEMP760Trench Drain Material PO 10 22-Sep-15 08-Oct-15
ZB4EEMP720Water Tank Accessories Material PO 10 01-Oct-15 18-Oct-15
ZB4EEMP770Hose Bibs Material PO 10 11-Oct-15 25-Oct-15
ZB4EEMP730Pump Room Accessories Material PO 10 23-Nov-15 06-Dec-15
ZB4EEMP750Heavy Duty Cast Iron Cover for Inspection Chamber Material PO 10 23-Nov-15 06-Dec-15
Material Deliv
Material Delivery at Site 212 15-Jul-15 08-Feb-16
ZB4EEMD74 Roof Drains Material Delivery 22 19-Sep-15 18-Oct-15
ZB4EEMD78 Domestic Water Booster Pump Material Delivery 104 15-Jul-15 19-Nov-15
ZB4EEMD79 Irrigation Water Booster Pump Material Delivery 104 15-Jul-15 19-Nov-15
ZB4EEMD80 Water Circulating Pumps Material Delivery 104 15-Jul-15 19-Nov-15
ZB4EEMD81 Submersible Waste Water Pump Material Delivery 104 15-Jul-15 19-Nov-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4
2015 2016
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 36 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish
ZB4EEMD68 Pipes PPR (PN 20) Material Partial Delivery 78 22-Aug-15 24-Nov-15
ZB4EEMD70 Pipes UPVC (PN 10) Material Partial Delivery 78 22-Aug-15 24-Nov-15
ZB4EEMD76 Trench Drain Material Delivery 52 10-Oct-15 09-Dec-15
ZB4EEMD71 Gate Valves Material Delivery 78 01-Oct-15 03-Jan-16
ZB4EEMD72 Water Tank Accessories Material Delivery 78 19-Oct-15 19-Jan-16
ZB4EEMD69 Pipes HDPE (PN 10) Material Delivery 104 16-Sep-15 21-Jan-16
ZB4EEMD73 Pump Room Accessories Material Delivery 40 07-Dec-15 24-Jan-16
ZB4EEMD77 Hose Bibs Material Delivery 78 26-Oct-15 27-Jan-16
ZB4EEMD75 Heavy Duty Cast Iron Cover for Inspection Chamber Material Delivery 52 07-Dec-15 08-Feb-16
Building B4 -
Building B4 - B (Electrical Services) 271 24-Jun-15 13-Mar-16
Electrical Sy
Electrical Systems 271 24-Jun-15 13-Mar-16
Power Syste
Power System 271 24-Jun-15 13-Mar-16
Material Subm
Material Submittal 82 02-Aug-15 21-Oct-15
ZB4EEMS500B4.B NRMU & B4.B-ERMU Material Submittal 10 02-Aug-15 13-Aug-15
ZB4EEMS520B4.B Distribution Transformers Material Submittal 10 02-Aug-15 13-Aug-15
ZB4EEMS510B4.B Medium Voltage Switch gear (22 KV) Material Submittal 10 09-Aug-15 20-Aug-15
ZB4EEMS490B4.B Building UPS Material Submittal 10 23-Aug-15 03-Sep-15
ZB4EEMS540B4.B Bus bar Trunking Material Submittal 10 23-Aug-15 03-Sep-15
ZB4EEMS820B4.B Emergency Diesel Generator Plant Material Submittal 10 23-Aug-15 03-Sep-15
ZB4EEMS830B4.B Paralleling and Synchronization Switch gear (22 KV) - EMV Material
Submittal
10 06-Sep-15 17-Sep-15
ZB4EEMS550B4.B MCC Panels Material Submittal 10 20-Sep-15 05-Oct-15
ZB4EEMS530B4.B MDB, DB, EDB, LP, PP, ELP, EPP and UPP Material Submittal 5 15-Oct-15 21-Oct-15
Material Appr
Material Approvals 75 16-Aug-15 28-Oct-15
ZB4EEMA50 B4.B-NRMU & B4.B-ERMU Material Approval 10 16-Aug-15 27-Aug-15
ZB4EEMA52 B4.B Distribution Transformers Material Approval 10 16-Aug-15 27-Aug-15
ZB4EEMA51 B4.B Medium Voltage Switch gear (22 KV) Material Approval 10 23-Aug-15 03-Sep-15
ZB4EEMA52 B4.C MDB Material Approval (By Others) 0 03-Sep-15
ZB4EEMA49 B4-B Building UPS Material Approval 10 06-Sep-15 17-Sep-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4
2015 2016
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 37 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish
ZB4EEMA54 B4.B Bus bar Trunking Material Approval 10 06-Sep-15 17-Sep-15
ZB4EEMA82 B4.B Emergency Diesel Generator Plant Material Approval 10 06-Sep-15 17-Sep-15
ZB4EEMA83 B4.B Paralleling and Synchronization Switch gear (22 KV) - EMV Material
Approval
10 20-Sep-15 05-Oct-15
ZB4EEMA55 B4.B MCC Panels Material Approval 10 07-Oct-15 21-Oct-15
ZB4EEMA53 B4.B MDB, DB, EDB, LP, PP, ELP, EPP and UPP Material Approval 5 22-Oct-15 28-Oct-15
Material PO's
Material PO's 159 24-Jun-15 25-Nov-15
ZB4EEMP350EMT Material PO 10 24-Jun-15 07-Jul-15
ZB4EEMP550IMC Material PO 10 24-Jun-15 07-Jul-15
ZB4EEMP920Cable Trays and Ladders Material PO 10 01-Jul-15 14-Jul-15
ZB4EEMP950LV Cables Fire Resistant Material PO 10 16-Aug-15 27-Aug-15
ZB4EEMP830B4.B-NRMU & B4.B-ERMU Material PO 10 30-Aug-15 10-Sep-15
ZB4EEMP850B4.B Distribution Transformers Material PO 10 30-Aug-15 10-Sep-15
ZB4EEMP940LV Cables Material PO 10 01-Sep-15 14-Sep-15
ZB4EEMP840B4.B Medium Voltage Switch gear (22 KV) Material PO 10 06-Sep-15 17-Sep-15
ZB4EEMP093Power Circuits Cables and Wires PO 10 13-Sep-15 28-Sep-15
ZB4EEMP970MV Cables Material PO 10 15-Sep-15 30-Sep-15
ZB4EEMP820B4-B Building UPS Material PO 10 20-Sep-15 05-Oct-15
ZB4EEMP870B4.B Bus bar Trunking Material PO 10 20-Sep-15 05-Oct-15
ZB4EEMP890B4.B Disconnecting Switches Material PO 10 29-Sep-15 13-Oct-15
ZB4EEMP960Wiring Devices Material PO 10 29-Sep-15 13-Oct-15
ZB4EEMP980LV Earthing Cables Material PO 10 29-Sep-15 13-Oct-15
ZB4EEMP910B4.B Paralleling and Synchronization Switch gear (22 KV) - EMV Material
PO
10 07-Oct-15 21-Oct-15
ZB4EEMP860B4.B MDB, DB, EDB, LP, PP, ELP, EPP and UPP Material PO 5 29-Oct-15 04-Nov-15
ZB4EEMP880B4.B MCC Panels Material PO 10 22-Oct-15 04-Nov-15
ZB4EEMP900B4.B Emergency Diesel Generator Plant Material PO 10 12-Nov-15 25-Nov-15
Material Deliv
Material Delivery at Site 256 08-Jul-15 13-Mar-16
ZB4EEMD55 EMT Material Delivery 10 08-Jul-15 20-Jul-15
ZB4EEMD92 IMC Material Delivery 10 08-Jul-15 20-Jul-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4
2015 2016
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 38 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish
ZB4EEMD09 Power Circuits Cables and Wires Partial Delivery 45 29-Sep-15 22-Nov-15
ZB4EEMD94 LV Cables Material Delivery 60 15-Sep-15 28-Nov-15
ZB4EEMD95 Cable Trays and Ladders Material Partial Delivery 120 15-Jul-15 08-Dec-15
ZB4EEMD97 MV Cables Material Partial Delivery 60 01-Oct-15 12-Dec-15
ZB4EEMD83 B4.B-NRMU & B4.B-ERMU Material Delivery 78 12-Sep-15 15-Dec-15
ZB4EEMD85 B4.B Distribution Transformers Material Delivery 78 12-Sep-15 15-Dec-15
ZB4EEMD96 LV Cables Fire Resistant Material Delivery 90 29-Aug-15 15-Dec-15
ZB4EEMD99 LV Earthing Cables Material Partial Delivery 60 15-Oct-15 24-Dec-15
ZB4EEMD88 B4.B MCC Panels Material Delivery 52 05-Nov-15 05-Jan-16
ZB4EEMD87 B4.B Bus bar Trunking Material Delivery 78 07-Oct-15 09-Jan-16
ZB4EEMD89 B4.B Disconnecting Switches Material Delivery 78 15-Oct-15 16-Jan-16
ZB4EEMD98 Wiring Devices Material Delivery 78 15-Oct-15 16-Jan-16
ZB4EEMD86 B4.B MDB, DB, EDB, LP, PP, ELP, EPP and UPP Material Delivery 65 05-Nov-15 21-Jan-16
ZB4EEMD91 B4.B Paralleling and Synchronization Switch gear (22 KV) - EMV Material
Delivery
78 22-Oct-15 23-Jan-16
ZB4EEMD84 B4.B Medium Voltage Switch gear (22 KV) Material Delivery 104 19-Sep-15 24-Jan-16
ZB4EEMD82 B4-B Building UPS Material Delivery 104 07-Oct-15 09-Feb-16
ZB4EEMD90 B4.B Emergency Diesel Generator Plant Material Delivery 90 26-Nov-15 13-Mar-16
Lighting Sys
Lighting System 112 13-Sep-15 31-Dec-15
Material PO's
Material PO's 37 13-Sep-15 21-Oct-15
ZB4EEMP990B4B Building Lighting Wires Material PO 10 13-Sep-15 28-Sep-15
ZB4EEMP100B4B Building Lighting Fixtures Material PO 10 29-Sep-15 13-Oct-15
ZB4EEMP101B4B Building CENTRAL MONITORING SYSTEM Material PO 10 29-Sep-15 13-Oct-15
ZB4EEMP102B4B Building KNX/EIP SYSTEM Material PO 10 07-Oct-15 21-Oct-15
Material Deliv
Material Delivery at Site 97 29-Sep-15 31-Dec-15
ZB4EEMD10 B4B Building Lighting Wires Material Partial Delivery 45 29-Sep-15 22-Nov-15
ZB4EEMD10 B4B Building Lighting Fixtures Material Delivery 45 15-Oct-15 06-Dec-15
ZB4EEMD10 B4B Building CENTRAL MONITORING SYSTEM Material Delivery 65 15-Oct-15 30-Dec-15
ZB4EEMD10 B4B Building KNX/EIP SYSTEM Material Delivery 60 22-Oct-15 31-Dec-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4
2015 2016
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 39 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish
Cable Tray S
Cable Tray System 194 01-Jul-15 05-Jan-16
Material PO's
Material PO's 106 01-Jul-15 13-Oct-15
ZB4EEMP103B4B Cable Trays and Ladders For Equipments Material PO 10 01-Jul-15 14-Jul-15
ZB4EEMP104B4B LV Cables For Equipments Material PO 10 01-Sep-15 14-Sep-15
ZB4EEMP105B4B LV Earthing For Equipments Cables Material PO 10 29-Sep-15 13-Oct-15
Material Deliv
Material Delivery at Site 179 15-Jul-15 05-Jan-16
ZB4EEMD10 B4B Cable Trays and Ladders Material Delivery 10 15-Jul-15 28-Jul-15
ZB4EEMD10 B4B LV Cables Material Delivery 60 15-Sep-15 28-Nov-15
ZB4EEMD10 B4B LV Earthing Cables Material Delivery 70 15-Oct-15 05-Jan-16
Earthing Sys
Earthing System 126 26-Jul-15 24-Nov-15
Material PO's
Material PO's 14 26-Jul-15 06-Aug-15
ZB4EEMP106Earthing System Material PO 10 26-Jul-15 06-Aug-15
Material Deliv
Material Delivery at Site 112 08-Aug-15 24-Nov-15
ZB4EEMD10 Earthing System Material Delivery 90 08-Aug-15 24-Nov-15
Lightning Sy
Lightning System 144 26-Jul-15 10-Dec-15
Material PO's
Material PO's 14 26-Jul-15 06-Aug-15
ZB4EEMP107LIGHTNING System Material PO 10 26-Jul-15 06-Aug-15
Material Deliv
Material Delivery at Site 130 08-Aug-15 10-Dec-15
ZB4EEMD10 LIGHTNING System Material Delivery 104 08-Aug-15 10-Dec-15
Light Curren
Light Current Systems 126 06-Sep-15 06-Jan-16
Fire Alarm Sy
Fire Alarm System 126 06-Sep-15 06-Jan-16
Material PO'
Material PO's 14 06-Sep-15 17-Sep-15
ZB4EEMP1Fire Alarm System Devices Material PO 10 06-Sep-15 17-Sep-15
ZB4EEMP1Fire Alarm System Fire Alarm Cable Material PO 10 06-Sep-15 17-Sep-15
ZB4EEMP1Fire Alarm System FACP Material PO 10 06-Sep-15 17-Sep-15
Material Del
Material Delivery at Site 112 19-Sep-15 06-Jan-16
ZB4EEMD1Fire Alarm System Fire Alarm Cable Material Delivery 78 19-Sep-15 22-Dec-15
ZB4EEMD1Fire Alarm System Devices Material Delivery 90 19-Sep-15 06-Jan-16
Q2 Q3 Q4 Q1 Q2 Q3 Q4
2015 2016
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 40 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish
ZB4EEMD1Fire Alarm System FACP Material Delivery 90 19-Sep-15 06-Jan-16
SCADA Sys
SCADA System 105 19-Nov-15 28-Feb-16
Material PO's
Material PO's 7 19-Nov-15 25-Nov-15
ZB4EEMP111SCADA System Material PO 5 19-Nov-15 25-Nov-15
Material Deliv
Material Delivery at Site 97 26-Nov-15 28-Feb-16
ZB4EEMD112
SCADA System Material Delivery 78 26-Nov-15 28-Feb-16
Mechanical
Mechanical Systems 227 28-Jun-15 04-Feb-16
HVAC Syste
HVAC System 227 28-Jun-15 04-Feb-16
Material Subm
Material Submittal 130 28-Jun-15 02-Nov-15
ZB4EEMS840AHU Material Submittal 12 28-Jun-15 13-Jul-15
ZB4EEMS850Chilled Water Valves Material Submittal 22 19-Jul-15 18-Aug-15
ZB4EEMS860Over Head Crane Material Submittal 22 06-Sep-15 08-Oct-15
ZB4EEMS870Air Cooled DX Split Units Material Submittal 18 07-Oct-15 02-Nov-15
Material Appr
Material Approvals 120 14-Jul-15 09-Nov-15
ZB4EEMA84 AHU System Material Approval 5 14-Jul-15 21-Jul-15
ZB4EEMA85 Chilled Water Valves Material Approval 5 19-Aug-15 25-Aug-15
ZB4EEMA86 Over Head Crane Material Approval 5 11-Oct-15 18-Oct-15
ZB4EEMA87 Air Cooled DX Split Units Material Approval 5 03-Nov-15 09-Nov-15
Material PO's
Material PO's 127 22-Jul-15 23-Nov-15
ZB4EEMP112AHU System Material PO 10 22-Jul-15 05-Aug-15
ZB4EEMP116Child pipe hangers and support Material PO 10 28-Jul-15 10-Aug-15
ZB4EEMP117Black seamless steel piping Material PO 10 17-Aug-15 30-Aug-15
ZB4EEMP118Metal Sheet Duct System Material PO 10 23-Aug-15 03-Sep-15
ZB4EEMP113Chilled Water Valves Material PO 10 26-Aug-15 08-Sep-15
ZB4EEMP119Fire Smoke Dampers Material PO 10 15-Sep-15 30-Sep-15
ZB4EEMP120Duct Insulation Material PO 10 17-Sep-15 04-Oct-15
ZB4EEMP121Chilled Water Piping Insulation Material PO 10 01-Oct-15 18-Oct-15
ZB4EEMP122Air Outlets Material PO 10 11-Oct-15 25-Oct-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4
2015 2016
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 41 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish
ZB4EEMP114Over Head Crane Material PO 10 19-Oct-15 01-Nov-15
ZB4EEMP115Air Cooled DX Split Units Material PO 10 10-Nov-15 23-Nov-15
Material Deliv
Material Delivery at Site 187 06-Aug-15 04-Feb-16
ZB4EEMD117
Child pipe hangers and support Material ( Partial )Delivery 36 11-Aug-15 21-Sep-15
ZB4EEMD113
AHU System Material Delivery 78 06-Aug-15 09-Nov-15
ZB4EEMD118
Metal Sheet Duct System Partial Material Delivery / Fabrication 65 05-Sep-15 23-Nov-15
ZB4EEMD119
Black seamless steel piping Material ( Partial )Delivery 78 31-Aug-15 03-Dec-15
ZB4EEMD12 Duct Insulation Material Delivery 52 05-Oct-15 06-Dec-15
ZB4EEMD12 Fire Smoke Dampers Material Delivery 78 01-Oct-15 03-Jan-16
ZB4EEMD114
Chilled Water Valves Material ( Partial )Delivery 104 09-Sep-15 14-Jan-16
ZB4EEMD12 Chilled Water Piping Insulation Material ( Partial ) Delivery 75 19-Oct-15 16-Jan-16
ZB4EEMD116
Air Cooled DX Split Units Material Material Delivery 52 24-Nov-15 26-Jan-16
ZB4EEMD12 Air Outlets Material Delivery 78 26-Oct-15 27-Jan-16
ZB4EEMD115
Over Head Crane Material Delivery On Site 78 02-Nov-15 03-Feb-16
ZB4EEMD12 Testing, Balancing & Commisioning system Third Part On Site 0 04-Feb-16
Fire Protect
Fire Protection Systems 114 01-Oct-15 19-Jan-16
Material Subm
Material Submittal 19 29-Oct-15 15-Nov-15
ZB4EEMS880CO2 System Material Submittal 12 29-Oct-15 15-Nov-15
ZB4EEMS890Automatic Dry Powder Fire Extinguishers Material Submittal 12 29-Oct-15 15-Nov-15
ZB4EEMS900FOAM FIRE SUPPRESSION SYSTEM Material Submittal 12 29-Oct-15 15-Nov-15
ZB4EEMS910FM-200 CLEAN AGENT EXTINGUISHING SYSTEM Material Submittal 12 29-Oct-15 15-Nov-15
Material Appr
Material Approvals 15 16-Nov-15 29-Nov-15
ZB4EEMA88 CO2 System Material Approval 10 16-Nov-15 29-Nov-15
ZB4EEMA89 Automatic Dry Powder Fire Extinguishers Material Approval 10 16-Nov-15 29-Nov-15
ZB4EEMA90 FOAM FIRE SUPPRESSION SYSTEM Material Approval 10 16-Nov-15 29-Nov-15
ZB4EEMA91 FM-200 CLEAN AGENT EXTINGUISHING SYSTEM Material Approval 10 16-Nov-15 29-Nov-15
Material PO's
Material PO's 76 01-Oct-15 13-Dec-15
ZB4EEMP125Dry Powder Manual Fire Extinguishers Material PO 10 01-Oct-15 18-Oct-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4
2015 2016
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 42 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Activity ID Activity Name Original
Duration
Start Finish
ZB4EEMP123CO2 System Material PO 10 30-Nov-15 13-Dec-15
ZB4EEMP124Automatic Dry Powder Fire Extinguishers Material PO 10 30-Nov-15 13-Dec-15
ZB4EEMP126FOAM FIRE SUPPRESSION SYSTEM Material PO 10 30-Nov-15 13-Dec-15
ZB4EEMP127FM-200 CLEAN AGENT EXTINGUISHING SYSTEM Material PO 10 30-Nov-15 13-Dec-15
Material Deliv
Material Delivery at Site 97 19-Oct-15 19-Jan-16
ZB4EEMD12 Automatic Dry Powder Fire Extinguishers Material Delivery 12 14-Dec-15 28-Dec-15
ZB4EEMD12 CO2 System Material Delivery 26 14-Dec-15 14-Jan-16
ZB4EEMD12 FOAM FIRE SUPPRESSION SYSTEM Material Delivery 26 14-Dec-15 14-Jan-16
ZB4EEMD12 FM-200 CLEAN AGENT EXTINGUISHING SYSTEM Material Delivery 26 14-Dec-15 14-Jan-16
ZB4EEMD12 Dry Powder Manual Fire Extinguishers Material Delivery 78 19-Oct-15 19-Jan-16
Plumbing Sy
Plumbing System 71 09-Aug-15 18-Oct-15
Material PO's
Material PO's 44 09-Aug-15 17-Sep-15
ZB4EEMP128Pipes UPVC (PN 10) Material PO 10 09-Aug-15 20-Aug-15
ZB4EEMP129Roof Drains Material PO 10 06-Sep-15 17-Sep-15
Material Deliv
Material Delivery at Site 57 22-Aug-15 18-Oct-15
ZB4EEMD13 Pipes UPVC (PN 10) Material Partial Delivery 22 22-Aug-15 15-Sep-15
ZB4EEMD13 Roof Drains Material Delivery 22 19-Sep-15 18-Oct-15
Building B4 -
Building B4 - D (Fuel Tank) 217 24-Jun-15 21-Jan-16
Electrical Sy
Electrical Systems 217 24-Jun-15 21-Jan-16
Power Syste
Power System 217 24-Jun-15 21-Jan-16
Material Subm
Material Submittal 25 27-Sep-15 21-Oct-15
ZB4EEMS138B4.D MCC Material Material Submittal 10 27-Sep-15 11-Oct-15
ZB4EEMS137B4.D EPP Material Material Submittal 10 07-Oct-15 21-Oct-15
Material Appr
Material Approvals 17 12-Oct-15 28-Oct-15
ZB4EEMA13 B4.D MCC Material Material Approval 5 12-Oct-15 19-Oct-15
ZB4EEMA13 B4.D EPP Material Material Approval 5 22-Oct-15 28-Oct-15
Material PO's
Material PO's 136 24-Jun-15 04-Nov-15
ZB4EEMP162EMT Material PO 10 24-Jun-15 07-Jul-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4
2015 2016
Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 43 of 98 TASK filter: All Activities
© Primavera Systems, Inc
Date Revision Checked Approved
17-Nov-15 Rev 1
31-Jan-16 Rev 2
Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdf

More Related Content

Similar to Zewail B4 Base Line Schedule All Buildings.pdf

12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...
12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...
12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...Rodger McKinley
 
Torkham Project Work Plan (18-Apr-2019).pdf
Torkham Project Work Plan (18-Apr-2019).pdfTorkham Project Work Plan (18-Apr-2019).pdf
Torkham Project Work Plan (18-Apr-2019).pdfSajidMumtazGurmani
 
ADIB Time Schedule V4.0
ADIB Time Schedule V4.0ADIB Time Schedule V4.0
ADIB Time Schedule V4.0Ahmed Khaled
 
A - Production Operation Maintenance Mechanical Engineering
A - Production Operation Maintenance Mechanical EngineeringA - Production Operation Maintenance Mechanical Engineering
A - Production Operation Maintenance Mechanical EngineeringPT. Wisnu Inter Sains Hakiki
 
Production Operation Maintenance & Mechanical Engineering
Production Operation Maintenance & Mechanical EngineeringProduction Operation Maintenance & Mechanical Engineering
Production Operation Maintenance & Mechanical EngineeringEva Susiani
 
OHL1.pdf ejehejeur iurrrj iiuj4j4i4 jrj4
OHL1.pdf ejehejeur iurrrj iiuj4j4i4 jrj4OHL1.pdf ejehejeur iurrrj iiuj4j4i4 jrj4
OHL1.pdf ejehejeur iurrrj iiuj4j4i4 jrj4AhmedSaidGhonemy
 
-The PERT Chart-The tendering time schedule for Adar Produced Water Re-injec...
-The PERT Chart-The tendering time schedule for Adar Produced  Water Re-injec...-The PERT Chart-The tendering time schedule for Adar Produced  Water Re-injec...
-The PERT Chart-The tendering time schedule for Adar Produced Water Re-injec...yang lu
 
23. CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)
23.  CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)23.  CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)
23. CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)hepemod733
 
HSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activityHSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activityRoumik Mukherjee
 
Gantt chart of Project schedule and management
Gantt chart of Project schedule and managementGantt chart of Project schedule and management
Gantt chart of Project schedule and managementadeel hamid
 
Single Family Gantt Chart-John Mueller
Single Family Gantt Chart-John MuellerSingle Family Gantt Chart-John Mueller
Single Family Gantt Chart-John MuellerJohn Mueller
 
II B.TECH I SEM R07 SUPPLE APRIL/MAY 2013
II B.TECH I SEM R07 SUPPLE APRIL/MAY 2013II B.TECH I SEM R07 SUPPLE APRIL/MAY 2013
II B.TECH I SEM R07 SUPPLE APRIL/MAY 2013P.G.GOPI NATH
 

Similar to Zewail B4 Base Line Schedule All Buildings.pdf (20)

2 l 65z
2 l 65z2 l 65z
2 l 65z
 
12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...
12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...
12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...
 
Torkham Project Work Plan (18-Apr-2019).pdf
Torkham Project Work Plan (18-Apr-2019).pdfTorkham Project Work Plan (18-Apr-2019).pdf
Torkham Project Work Plan (18-Apr-2019).pdf
 
Monthly Progress Report No.13 - September 2011
Monthly Progress Report No.13 - September 2011Monthly Progress Report No.13 - September 2011
Monthly Progress Report No.13 - September 2011
 
Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13
 
ADIB Time Schedule V4.0
ADIB Time Schedule V4.0ADIB Time Schedule V4.0
ADIB Time Schedule V4.0
 
ERUP WBS
ERUP WBSERUP WBS
ERUP WBS
 
A - Production Operation Maintenance Mechanical Engineering
A - Production Operation Maintenance Mechanical EngineeringA - Production Operation Maintenance Mechanical Engineering
A - Production Operation Maintenance Mechanical Engineering
 
Weekly report no 19
Weekly report no 19Weekly report no 19
Weekly report no 19
 
Production Operation Maintenance & Mechanical Engineering
Production Operation Maintenance & Mechanical EngineeringProduction Operation Maintenance & Mechanical Engineering
Production Operation Maintenance & Mechanical Engineering
 
OHL1.pdf ejehejeur iurrrj iiuj4j4i4 jrj4
OHL1.pdf ejehejeur iurrrj iiuj4j4i4 jrj4OHL1.pdf ejehejeur iurrrj iiuj4j4i4 jrj4
OHL1.pdf ejehejeur iurrrj iiuj4j4i4 jrj4
 
ScheduleRev- 6
ScheduleRev- 6ScheduleRev- 6
ScheduleRev- 6
 
-The PERT Chart-The tendering time schedule for Adar Produced Water Re-injec...
-The PERT Chart-The tendering time schedule for Adar Produced  Water Re-injec...-The PERT Chart-The tendering time schedule for Adar Produced  Water Re-injec...
-The PERT Chart-The tendering time schedule for Adar Produced Water Re-injec...
 
10. Overall Implementation Programme
10. Overall Implementation Programme10. Overall Implementation Programme
10. Overall Implementation Programme
 
Project Schedule - Level IV Schedule
Project Schedule - Level IV ScheduleProject Schedule - Level IV Schedule
Project Schedule - Level IV Schedule
 
23. CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)
23.  CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)23.  CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)
23. CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)
 
HSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activityHSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activity
 
Gantt chart of Project schedule and management
Gantt chart of Project schedule and managementGantt chart of Project schedule and management
Gantt chart of Project schedule and management
 
Single Family Gantt Chart-John Mueller
Single Family Gantt Chart-John MuellerSingle Family Gantt Chart-John Mueller
Single Family Gantt Chart-John Mueller
 
II B.TECH I SEM R07 SUPPLE APRIL/MAY 2013
II B.TECH I SEM R07 SUPPLE APRIL/MAY 2013II B.TECH I SEM R07 SUPPLE APRIL/MAY 2013
II B.TECH I SEM R07 SUPPLE APRIL/MAY 2013
 

More from Ahmed Mehrem

020614_letter for Ahmed Mehrem Recommendation letter.pdf
020614_letter for Ahmed Mehrem Recommendation letter.pdf020614_letter for Ahmed Mehrem Recommendation letter.pdf
020614_letter for Ahmed Mehrem Recommendation letter.pdfAhmed Mehrem
 
Al aziza jotun products and services 2019 qr
Al aziza jotun products and services 2019 qrAl aziza jotun products and services 2019 qr
Al aziza jotun products and services 2019 qrAhmed Mehrem
 
Al-Aziza for paints and decoration Ahmed Mehrem business card 2
Al-Aziza for paints and decoration Ahmed Mehrem business card 2Al-Aziza for paints and decoration Ahmed Mehrem business card 2
Al-Aziza for paints and decoration Ahmed Mehrem business card 2Ahmed Mehrem
 
Al-Aziza For Paints Ahmed Mehrem business card
Al-Aziza For Paints Ahmed Mehrem business card Al-Aziza For Paints Ahmed Mehrem business card
Al-Aziza For Paints Ahmed Mehrem business card Ahmed Mehrem
 
Mtwara power plant 2007
Mtwara power plant 2007Mtwara power plant 2007
Mtwara power plant 2007Ahmed Mehrem
 
Admin Building For Sphinx Glass Factory In Sadat
Admin Building For Sphinx Glass Factory In SadatAdmin Building For Sphinx Glass Factory In Sadat
Admin Building For Sphinx Glass Factory In SadatAhmed Mehrem
 
Sphinx Glass Factory comp 1-1
Sphinx Glass Factory comp 1-1Sphinx Glass Factory comp 1-1
Sphinx Glass Factory comp 1-1Ahmed Mehrem
 

More from Ahmed Mehrem (10)

020614_letter for Ahmed Mehrem Recommendation letter.pdf
020614_letter for Ahmed Mehrem Recommendation letter.pdf020614_letter for Ahmed Mehrem Recommendation letter.pdf
020614_letter for Ahmed Mehrem Recommendation letter.pdf
 
Al aziza jotun products and services 2019 qr
Al aziza jotun products and services 2019 qrAl aziza jotun products and services 2019 qr
Al aziza jotun products and services 2019 qr
 
Al-Aziza for paints and decoration Ahmed Mehrem business card 2
Al-Aziza for paints and decoration Ahmed Mehrem business card 2Al-Aziza for paints and decoration Ahmed Mehrem business card 2
Al-Aziza for paints and decoration Ahmed Mehrem business card 2
 
Al-Aziza For Paints Ahmed Mehrem business card
Al-Aziza For Paints Ahmed Mehrem business card Al-Aziza For Paints Ahmed Mehrem business card
Al-Aziza For Paints Ahmed Mehrem business card
 
For Our Mothers
For Our MothersFor Our Mothers
For Our Mothers
 
Majarrah data
Majarrah dataMajarrah data
Majarrah data
 
001
001001
001
 
Mtwara power plant 2007
Mtwara power plant 2007Mtwara power plant 2007
Mtwara power plant 2007
 
Admin Building For Sphinx Glass Factory In Sadat
Admin Building For Sphinx Glass Factory In SadatAdmin Building For Sphinx Glass Factory In Sadat
Admin Building For Sphinx Glass Factory In Sadat
 
Sphinx Glass Factory comp 1-1
Sphinx Glass Factory comp 1-1Sphinx Glass Factory comp 1-1
Sphinx Glass Factory comp 1-1
 

Recently uploaded

Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 

Recently uploaded (20)

Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 

Zewail B4 Base Line Schedule All Buildings.pdf

  • 1. Activity ID Activity Name Original Duration Start Finish Zewail City of Zewail City of Science and Technology B4 Contract 577 02-May-15 13-Nov-16 General General 577 02-May-15 13-Nov-16 ZB4G0010 Letter of Intent 0 02-May-15 ZB4G0020 Receive Final Design Drawings and Specifications 0 03-May-15 ZB4G0030 Down Payment 0 24-May-15 ZB4G0040 Letter of Award 0 24-May-15 ZB4G0060 Full Release Service Tunnel For MEP Works 0 06-Jun-15 ZB4G0062 Release Building B4-A For MEP Work ( Masonry Works ) 0 14-Jun-15 ZB4G0064 Release Building B4-B For MEPWork ( Masonry Works ) 0 14-Jun-15 ZB4G0050 Mobilization 15 30-May-15 15-Jun-15 ZB4G0066 Release Building B4-D For MEPWork ( Masonry Works ) 0 01-Jul-15 ZB4G0068 Release Building B4-E For MEPWork ( Masonry Works ) 0 01-Jul-15 ZB4G0070 Provide Permanent Electrical / Gas / Water / Drainage Sources 0 15-Aug-15 ZB4G0076 Release Building B4-D Finishing Work ( For Equipment Installation ) 0 18-Aug-15 ZB4G0074 Release Building B4-B Finishing Work ( For Equipment Installation ) 0 01-Sep-15 ZB4G0072 Release Building B4-A Finishing Work ( For Equipment Installation ) 0 05-Sep-15 ZB4G0078 Release Building B4-E Finishing Work ( For Equipment Installation ) 0 05-Sep-15 ZB4G0088 Release Site Layout For MEPWork ( MV, LV and SCADA Networks Works ) 0 04-Nov-15 ZB4G0098 Release Site Layout For MEPWork ( Solar LED Exterior Lighting Works ) 0 28-Feb-16 ZB4G0090 Project Hand Over 0 13-Nov-16 ZB4G0080 Project Testing & Commissioning 60 29-Aug-16 13-Nov-16 Engineering Engineering 261 03-May-15 10-Jan-16 Building B4 - Building B4 - A (Mechanical Utilities) 177 03-May-15 21-Oct-15 ZB4G000010 Basic Engineering Study 18 03-May-15 26-May-15 Basement F Basement Floor 90 27-May-15 20-Aug-15 Electrical Sy Electrical Systems 90 27-May-15 20-Aug-15 Power Syste Power System 15 01-Jul-15 14-Jul-15 ZB4AEBEPS BASEMENT FLOOR POWER SYSTEM LAYOUT PLAN SUBMITTAL 5 01-Jul-15 07-Jul-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 2015 2016 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 1 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 2. Activity ID Activity Name Original Duration Start Finish ZB4AEBEPABASEMENT FLOOR POWER SYSTEM LAYOUT PLAN APPROVAL 5 08-Jul-15 14-Jul-15 Lighting Sys Lighting System 15 27-May-15 09-Jun-15 ZB4AEBELS BASEMENT FLOOR LIGHTING SYSTEM LAYOUT PLAN SUBMITTAL 5 27-May-15 02-Jun-15 ZB4AEBELABASEMENT FLOOR LIGHTING SYSTEM LAYOUT PLAN APPROVAL 5 03-Jun-15 09-Jun-15 Cable Tray S Cable Tray System 15 01-Jul-15 14-Jul-15 ZB4AEBECSBASEMENT FLOOR CABLE TRAY SYSTEM LAYOUT PLAN SUBMITTAL 5 01-Jul-15 07-Jul-15 ZB4AEBECABASEMENT FLOOR CABLE TRAY SYSTEM LAYOUT PLAN APPROVAL 5 08-Jul-15 14-Jul-15 Earthing Sys Earthing System 15 08-Jul-15 22-Jul-15 ZB4AEBEES BASEMENT FLOOR EARTHING SYSTEM LAYOUT PLAN SUBMITTAL 5 08-Jul-15 14-Jul-15 ZB4AEBEEABASEMENT FLOOR EARTHING SYSTEM LAYOUT PLAN APPROVAL 5 15-Jul-15 22-Jul-15 Light Curren Light Current Systems 24 27-May-15 17-Jun-15 Fire Alarm S Fire Alarm System 15 27-May-15 09-Jun-15 ZB4AEBELBASEMENT FLOOR FIRE ALARM SYSTEM LAYOUT PLAN SUBMITTAL 5 27-May-15 02-Jun-15 ZB4AEBELBASEMENT FLOOR FIRE ALARM SYSTEM LAYOUT PLAN APPROVAL 5 03-Jun-15 09-Jun-15 Security Sys Security Systems 15 01-Jun-15 14-Jun-15 ZB4AEBELBASEMENT FLOOR SECURITY SYSTEMS LAYOUT PLAN SUBMITTAL 5 01-Jun-15 07-Jun-15 ZB4AEBELBASEMENT FLOOR SECURITY SYSTEMS LAYOUT PLAN APPROVAL 5 08-Jun-15 14-Jun-15 Communica Communication Systems 15 04-Jun-15 17-Jun-15 ZB4AEBELBASEMENT FLOOR COMMUNICATION SYSTEMS LAYOUT PLAN SUBMITTAL 5 04-Jun-15 10-Jun-15 ZB4AEBELBASEMENT FLOOR COMMUNICATION SYSTEMS LAYOUT PLAN APPROVAL 5 11-Jun-15 17-Jun-15 SCADA Syste SCADA System 14 09-Aug-15 20-Aug-15 ZB4AEBEDSBASEMENT FLOOR SCADA SYSTEM LAYOUT PLAN SUBMITTAL 5 09-Aug-15 13-Aug-15 ZB4AEBEDABASEMENT FLOOR SCADA SYSTEM LAYOUT PLAN APPROVAL 5 16-Aug-15 20-Aug-15 Mechanical Mechanical Systems 30 27-May-15 23-Jun-15 HVAC System HVAC System 30 27-May-15 23-Jun-15 ZB4AEBMHSBASEMENT FLOOR HVAC SYSTEM LAYOUT PLAN SUBMITTAL 15 27-May-15 16-Jun-15 ZB4AEBMHSBASEMENT FLOOR HVAC SECTIONS LAYOUT PLAN SUBMITTAL 15 27-May-15 16-Jun-15 ZB4AEBMHA BASEMENT FLOOR HVAC SYSTEM LAYOUT PLAN APPROVAL 5 17-Jun-15 23-Jun-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 2015 2016 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 2 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 3. Activity ID Activity Name Original Duration Start Finish ZB4AEBMHA BASEMENT FLOOR HVAC SYSTEM LAYOUT PLAN APPROVAL 5 17-Jun-15 23-Jun-15 Fire Protectio Fire Protection Systems 22 27-May-15 16-Jun-15 ZB4AEBMFSBASEMENT FLOOR FIRE PROTECTION SYSTEM LAYOUT PLAN SUBMITTAL 10 27-May-15 09-Jun-15 ZB4AEBMFABASEMENT FLOOR FIRE PROTECTION SYSTEM LAYOUT PLAN APPROVAL 5 10-Jun-15 16-Jun-15 Plumbing Sy Plumbing System 30 27-May-15 23-Jun-15 ZB4AEBMW BASEMENT FLOOR WATER SUPPLY SYSTEM LAYOUT PLAN SUBMITTAL 5 27-May-15 02-Jun-15 ZB4AEBMDSBASEMENT FLOOR DRAINAGE SYSTEM LAYOUT PLAN SUBMITTAL 5 27-May-15 02-Jun-15 ZB4AEBMWA BASEMENT FLOOR WATER SUPPLY SYSTEM LAYOUT PLAN APPROVAL 5 03-Jun-15 09-Jun-15 ZB4AEBMDA BASEMENT FLOOR DRAINAGE SYSTEM LAYOUT PLAN APPROVAL 5 03-Jun-15 09-Jun-15 ZB4AEBMW WATER SUPPLY PUMP ROOM DETAILS & SECTIONS SUBMITTAL 15 27-May-15 16-Jun-15 ZB4AEBMWA WATER SUPPLY PUMP ROOM DETAILS & SECTIONS APPROVAL 5 17-Jun-15 23-Jun-15 Composite D Composite Drawing 14 26-Jul-15 06-Aug-15 ZB4AEBCS10 BASEMENT FLOOR COMPOSITE LAYOUT PLAN SUBMITTAL 5 26-Jul-15 30-Jul-15 ZB4AEBCA10 BASEMENT FLOOR COMPOSITE LAYOUT PLAN APPROVAL 5 02-Aug-15 06-Aug-15 Ground Floor Ground Floor 90 03-Jun-15 27-Aug-15 ZB4AEGGBS10 Ground Floor Builder Work Submittal 5 02-Aug-15 06-Aug-15 ZB4AEGGBA10 Ground Floor Builder Work Approval 5 09-Aug-15 13-Aug-15 Electrical Sy Electrical Systems 90 03-Jun-15 27-Aug-15 Power Syste Power System 15 08-Jul-15 22-Jul-15 ZB4AEGEPS GROUND FLOOR POWER SYSTEM LAYOUT PLAN SUBMITTAL 5 08-Jul-15 14-Jul-15 ZB4AEGEPAGROUND FLOOR POWER SYSTEM LAYOUT PLAN APPROVAL 5 15-Jul-15 22-Jul-15 Lighting Sys Lighting System 15 03-Jun-15 16-Jun-15 ZB4AEGELSGROUND FLOOR LIGHTING SYSTEM LAYOUT PLAN SUBMITTAL 5 03-Jun-15 09-Jun-15 ZB4AEGELAGROUND FLOOR LIGHTING SYSTEM LAYOUT PLAN APPROVAL 5 10-Jun-15 16-Jun-15 Cable Tray S Cable Tray System 15 08-Jul-15 22-Jul-15 ZB4AEGECSGROUND FLOOR CABLE TRAY SYSTEM LAYOUT PLAN SUBMITTAL 5 08-Jul-15 14-Jul-15 ZB4AEGECAGROUND FLOOR CABLE TRAY SYSTEM LAYOUT PLAN APPROVAL 5 15-Jul-15 22-Jul-15 Earthing Sys Earthing System 15 15-Jul-15 30-Jul-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 2015 2016 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 3 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 4. Activity ID Activity Name Original Duration Start Finish ZB4AEGEESGROUND FLOOR EARTHING SYSTEM LAYOUT PLAN SUBMITTAL 5 15-Jul-15 22-Jul-15 ZB4AEGEEAGROUND FLOOR EARTHING SYSTEM LAYOUT PLAN APPROVAL 5 26-Jul-15 30-Jul-15 Light Curren Light Current Systems 24 03-Jun-15 24-Jun-15 Fire Alarm S Fire Alarm System 15 03-Jun-15 16-Jun-15 ZB4AEGELGROUND FLOOR FIRE ALARM SYSTEM LAYOUT PLAN SUBMITTAL 5 03-Jun-15 09-Jun-15 ZB4AEGELGROUND FLOOR FIRE ALARM SYSTEM LAYOUT PLAN APPROVAL 5 10-Jun-15 16-Jun-15 Security Sys Security Systems 15 08-Jun-15 21-Jun-15 ZB4AEGELGROUND FLOOR SECURITY SYSTEMS LAYOUT PLAN SUBMITTAL 5 08-Jun-15 14-Jun-15 ZB4AEGELGROUND FLOOR SECURITY SYSTEMS LAYOUT PLAN APPROVAL 5 15-Jun-15 21-Jun-15 Communica Communication Systems 15 11-Jun-15 24-Jun-15 ZB4AEGELGROUND FLOOR COMMUNICATION SYSTEMS LAYOUT PLAN SUBMITTAL 5 11-Jun-15 17-Jun-15 ZB4AEGELGROUND FLOOR COMMUNICATION SYSTEMS LAYOUT PLAN APPROVAL 5 18-Jun-15 24-Jun-15 SCADA Syste SCADA System 14 16-Aug-15 27-Aug-15 ZB4AEGEDSGROUND FLOOR SCADA SYSTEM LAYOUT PLAN SUBMITTAL 5 16-Aug-15 20-Aug-15 ZB4AEGEDAGROUND FLOOR SCADA SYSTEM LAYOUT PLAN APPROVAL 5 23-Aug-15 27-Aug-15 Mechanical Mechanical Systems 45 03-Jun-15 14-Jul-15 HVAC System HVAC System 30 17-Jun-15 14-Jul-15 ZB4AEGMHSGROUND FLOOR HVAC SYSTEM LAYOUT PLAN SUBMITTAL 15 17-Jun-15 07-Jul-15 ZB4AEGMHSGROUND FLOOR HVAC SECTIONS LAYOUT PLAN SUBMITTAL 15 17-Jun-15 07-Jul-15 ZB4AEGMHA GROUND FLOOR HVAC SYSTEM LAYOUT PLAN APPROVAL 5 08-Jul-15 14-Jul-15 ZB4AEGMHA GROUND FLOOR HVAC SYSTEM LAYOUT PLAN APPROVAL 5 08-Jul-15 14-Jul-15 Fire Protectio Fire Protection Systems 22 10-Jun-15 30-Jun-15 ZB4AEGMFSGROUND FLOOR FIRE PROTECTION SYSTEM LAYOUT PLAN SUBMITTAL 5 10-Jun-15 16-Jun-15 ZB4AEGMFAGROUND FLOOR FIRE PROTECTION SYSTEM LAYOUT PLAN APPROVAL 5 17-Jun-15 23-Jun-15 ZB4AEGMFSFIRE PROTECTION WORK - SPECIAL SYSTEM DETAILS SUBMITTAL 5 17-Jun-15 23-Jun-15 ZB4AEGMFAFIRE PROTECTION WORK - SPECIAL SYSTEM DETAILS APPROVAL 5 24-Jun-15 30-Jun-15 Plumbing Sy Plumbing System 15 03-Jun-15 16-Jun-15 ZB4AEGMWGROUND FLOOR WATER SUPPLY SYSTEM LAYOUT PLAN SUBMITTAL 5 03-Jun-15 09-Jun-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 2015 2016 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 4 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 5. Activity ID Activity Name Original Duration Start Finish ZB4AEGMDSGROUND FLOOR DRAINAGE SYSTEM LAYOUT PLAN SUBMITTAL 5 03-Jun-15 09-Jun-15 ZB4AEGMWA GROUND FLOOR WATER SUPPLY SYSTEM LAYOUT PLAN APPROVAL 5 10-Jun-15 16-Jun-15 ZB4AEGMDA GROUND FLOOR DRAINAGE SYSTEM LAYOUT PLAN APPROVAL 5 10-Jun-15 16-Jun-15 Composite D Composite Drawing 14 02-Aug-15 13-Aug-15 ZB4AEGCS10 GROUND FLOOR COMPOSITE LAYOUT PLAN SUBMITTAL 5 02-Aug-15 06-Aug-15 ZB4AEGCA10 GROUND FLOOR COMPOSITE LAYOUT PLAN APPROVAL 5 09-Aug-15 13-Aug-15 Roof 1 Roof 1 90 10-Jun-15 03-Sep-15 ZB4AERGBS10 Roof 1 Builder Work Submittal 5 09-Aug-15 13-Aug-15 ZB4AERGBA10 Roof 1 Builder Work Approval 5 16-Aug-15 20-Aug-15 Electrical Sy Electrical Systems 90 10-Jun-15 03-Sep-15 Power Syste Power System 7 15-Jul-15 22-Jul-15 ZB4AEREPS ROOF 1 FLOOR POWER SYSTEM LAYOUT PLAN SUBMITTAL 5 15-Jul-15 22-Jul-15 ZB4AEREPAROOF 1 FLOOR POWER SYSTEM LAYOUT PLAN APPROVAL 5 15-Jul-15 22-Jul-15 Lighting Sys Lighting System 15 10-Jun-15 23-Jun-15 ZB4AERELSROOF 1 FLOOR LIGHTING SYSTEM LAYOUT PLAN SUBMITTAL 5 10-Jun-15 16-Jun-15 ZB4AERELAROOF 1 FLOOR LIGHTING SYSTEM LAYOUT PLAN APPROVAL 5 17-Jun-15 23-Jun-15 Cable Tray S Cable Tray System 15 15-Jul-15 30-Jul-15 ZB4AERECSROOF 1 FLOOR CABLE TRAY SYSTEM LAYOUT PLAN SUBMITTAL 5 15-Jul-15 22-Jul-15 ZB4AERECAROOF 1 FLOOR CABLE TRAY SYSTEM LAYOUT PLAN APPROVAL 5 26-Jul-15 30-Jul-15 Lightning Sy Lightning System 14 26-Jul-15 06-Aug-15 ZB4AEREHSROOF 1 FLOOR LIGHTNING SYSTEM LAYOUT PLAN SUBMITTAL 5 26-Jul-15 30-Jul-15 ZB4AEREHAROOF 1 FLOOR LIGHTNING SYSTEM LAYOUT PLAN APPROVAL 5 02-Aug-15 06-Aug-15 Light Curren Light Current Systems 20 10-Jun-15 28-Jun-15 Fire Alarm S Fire Alarm System 15 10-Jun-15 23-Jun-15 ZB4AERELROOF 1 FLOOR FIRE ALARM SYSTEM LAYOUT PLAN SUBMITTAL 5 10-Jun-15 16-Jun-15 ZB4AERELROOF 1 FLOOR FIRE ALARM SYSTEM LAYOUT PLAN APPROVAL 5 17-Jun-15 23-Jun-15 Security Sys Security Systems 15 15-Jun-15 28-Jun-15 ZB4AERELROOF 1 FLOOR SECURITY SYSTEMS LAYOUT PLAN SUBMITTAL 5 15-Jun-15 21-Jun-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 2015 2016 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 5 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 6. Activity ID Activity Name Original Duration Start Finish ZB4AERELROOF 1 FLOOR SECURITY SYSTEMS LAYOUT PLAN APPROVAL 5 22-Jun-15 28-Jun-15 SCADA Syste SCADA System 14 23-Aug-15 03-Sep-15 ZB4AEREDSROOF 1 FLOOR SCADA SYSTEM LAYOUT PLAN SUBMITTAL 5 23-Aug-15 27-Aug-15 ZB4AEREDAROOF 1 FLOOR SCADA SYSTEM LAYOUT PLAN APPROVAL 5 30-Aug-15 03-Sep-15 Mechanical Mechanical Systems 60 10-Jun-15 06-Aug-15 HVAC System HVAC System 30 08-Jul-15 06-Aug-15 ZB4AERMHSROOF 1 FLOOR HVAC SYSTEM LAYOUT PLAN SUBMITTAL 15 08-Jul-15 30-Jul-15 ZB4AERMHSROOF 1 FLOOR HVAC SECTIONS LAYOUT PLAN SUBMITTAL 15 08-Jul-15 30-Jul-15 ZB4AERMHA ROOF 1 FLOOR HVAC SYSTEM LAYOUT PLAN APPROVAL 5 02-Aug-15 06-Aug-15 ZB4AERMHA ROOF 1 FLOOR HVAC SECTIONS LAYOUT PLAN APPROVAL 5 02-Aug-15 06-Aug-15 Fire Protectio Fire Protection Systems 15 17-Jun-15 30-Jun-15 ZB4AERMFSROOF 1 FLOOR FIRE PROTECTION SYSTEM LAYOUT PLAN SUBMITTAL 5 17-Jun-15 23-Jun-15 ZB4AERMFAROOF 1 FLOOR FIRE PROTECTION SYSTEM LAYOUT PLAN APPROVAL 5 24-Jun-15 30-Jun-15 Plumbing Sy Plumbing System 15 10-Jun-15 23-Jun-15 ZB4AERMWROOF 1 FLOOR WATER SUPPLY SYSTEM LAYOUT PLAN SUBMITTAL 5 10-Jun-15 16-Jun-15 ZB4AERMDSROOF 1 FLOOR DRAINAGE SYSTEM LAYOUT PLAN SUBMITTAL 5 10-Jun-15 16-Jun-15 ZB4AERMWA ROOF 1 FLOOR WATER SUPPLY SYSTEM LAYOUT PLAN APPROVAL 5 17-Jun-15 23-Jun-15 ZB4AERMDA ROOF 1 FLOOR DRAINAGE SYSTEM LAYOUT PLAN APPROVAL 5 17-Jun-15 23-Jun-15 Composite D Composite Drawing 14 09-Aug-15 20-Aug-15 ZB4AERCS10 ROOF 1 FLOOR COMPOSITE LAYOUT PLAN SUBMITTAL 5 09-Aug-15 13-Aug-15 ZB4AERCA10 ROOF 1 FLOOR COMPOSITE LAYOUT PLAN APPROVAL 5 16-Aug-15 20-Aug-15 Roof 2 Roof 2 90 17-Jun-15 10-Sep-15 ZB4AEUGBS10 Roof 2 Builder Work Submittal 5 30-Aug-15 03-Sep-15 ZB4AEUGBA10 Roof 2 Builder Work Approval 5 06-Sep-15 10-Sep-15 Electrical Sy Electrical Systems 90 17-Jun-15 10-Sep-15 Power Syste Power System 15 15-Jul-15 30-Jul-15 ZB4AEUEPS ROOF 2 FLOOR POWER SYSTEM LAYOUT PLAN SUBMITTAL 5 15-Jul-15 22-Jul-15 ZB4AEUEPAROOF 2 FLOOR POWER SYSTEM LAYOUT PLAN APPROVAL 5 26-Jul-15 30-Jul-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 2015 2016 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 6 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 7. Activity ID Activity Name Original Duration Start Finish Lighting Sys Lighting System 15 17-Jun-15 30-Jun-15 ZB4AEUELSROOF 2 FLOOR LIGHTING SYSTEM LAYOUT PLAN SUBMITTAL 5 17-Jun-15 23-Jun-15 ZB4AEUELAROOF 2 FLOOR LIGHTING SYSTEM LAYOUT PLAN APPROVAL 5 24-Jun-15 30-Jun-15 Cable Tray S Cable Tray System 14 26-Jul-15 06-Aug-15 ZB4AEUECSROOF 2 FLOOR CABLE TRAY SYSTEM LAYOUT PLAN SUBMITTAL 5 26-Jul-15 30-Jul-15 ZB4AEUECAROOF 2 FLOOR CABLE TRAY SYSTEM LAYOUT PLAN APPROVAL 5 02-Aug-15 06-Aug-15 Lightning Sy Lightning System 14 02-Aug-15 13-Aug-15 ZB4AEUEHSROOF 2 FLOOR LIGHTNING SYSTEM LAYOUT PLAN SUBMITTAL 5 02-Aug-15 06-Aug-15 ZB4AEUEHAROOF 2 FLOOR LIGHTNING SYSTEM LAYOUT PLAN APPROVAL 5 09-Aug-15 13-Aug-15 Light Curren Light Current Systems 20 17-Jun-15 05-Jul-15 Fire Alarm S Fire Alarm System 15 17-Jun-15 30-Jun-15 ZB4AEUELROOF 2 FLOOR FIRE ALARM SYSTEM LAYOUT PLAN SUBMITTAL 5 17-Jun-15 23-Jun-15 ZB4AEUELROOF 2 FLOOR FIRE ALARM SYSTEM LAYOUT PLAN APPROVAL 5 24-Jun-15 30-Jun-15 Security Sys Security Systems 15 22-Jun-15 05-Jul-15 ZB4AEUELROOF 2 FLOOR SECURITY SYSTEMS LAYOUT PLAN SUBMITTAL 5 22-Jun-15 28-Jun-15 ZB4AEUELROOF 2 FLOOR SECURITY SYSTEMS LAYOUT PLAN APPROVAL 5 29-Jun-15 05-Jul-15 SCADA Syste SCADA System 14 30-Aug-15 10-Sep-15 ZB4AEUEDSROOF 2 FLOOR SCADA SYSTEM LAYOUT PLAN SUBMITTAL 5 30-Aug-15 03-Sep-15 ZB4AEUEDAROOF 2 FLOOR SCADA SYSTEM LAYOUT PLAN APPROVAL 5 06-Sep-15 10-Sep-15 Mechanical Mechanical Systems 75 17-Jun-15 27-Aug-15 HVAC System HVAC System 29 02-Aug-15 27-Aug-15 ZB4AEUMHSROOF 2 FLOOR HVAC SYSTEM LAYOUT PLAN SUBMITTAL 15 02-Aug-15 20-Aug-15 ZB4AEUMHSROOF 2 FLOOR HVAC SECTIONS LAYOUT PLAN SUBMITTAL 15 02-Aug-15 20-Aug-15 ZB4AEUMHA ROOF 2 FLOOR HVAC SYSTEM LAYOUT PLAN APPROVAL 5 23-Aug-15 27-Aug-15 ZB4AEUMHA ROOF 2 FLOOR HVAC SECTIONS LAYOUT PLAN APPROVAL 5 23-Aug-15 27-Aug-15 Fire Protectio Fire Protection Systems 15 24-Jun-15 07-Jul-15 ZB4AEUMFSROOF 2 FLOOR FIRE PROTECTION SYSTEM LAYOUT PLAN SUBMITTAL 5 24-Jun-15 30-Jun-15 ZB4AEUMFAROOF 2 FLOOR FIRE PROTECTION SYSTEM LAYOUT PLAN APPROVAL 5 01-Jul-15 07-Jul-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 2015 2016 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 7 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 8. Activity ID Activity Name Original Duration Start Finish Plumbing Sy Plumbing System 15 17-Jun-15 30-Jun-15 ZB4AEUMWROOF 2 FLOOR WATER SUPPLY SYSTEM LAYOUT PLAN SUBMITTAL 5 17-Jun-15 23-Jun-15 ZB4AEUMDSROOF 2 FLOOR DRAINAGE SYSTEM LAYOUT PLAN SUBMITTAL 5 17-Jun-15 23-Jun-15 ZB4AEUMWA ROOF 2 FLOOR WATER SUPPLY SYSTEM LAYOUT PLAN APPROVAL 5 24-Jun-15 30-Jun-15 ZB4AEUMDA ROOF 2 FLOOR DRAINAGE SYSTEM LAYOUT PLAN APPROVAL 5 24-Jun-15 30-Jun-15 Composite D Composite Drawing 14 30-Aug-15 10-Sep-15 ZB4AEUCS10 ROOF 2 FLOOR COMPOSITE LAYOUT PLAN SUBMITTAL 5 30-Aug-15 03-Sep-15 ZB4AEUCA10 ROOF 2 FLOOR COMPOSITE LAYOUT PLAN APPROVAL 5 06-Sep-15 10-Sep-15 General Sho General Shop Drawings 151 27-May-15 21-Oct-15 Electrical Sy Electrical Systems 151 27-May-15 21-Oct-15 ZB4AETEGS10ELECTRICAL INSTALLATION DETAILS SUBMITTAL 5 27-May-15 02-Jun-15 ZB4AETEGA10ELECTRICAL INSTALLATION DETAILS APPROVAL 5 03-Jun-15 09-Jun-15 Power Syste Power System 29 02-Aug-15 27-Aug-15 ZB4AETEPS PANEL BOARD SCHEDULE SUBMITTAL 5 02-Aug-15 06-Aug-15 ZB4AETEPAPANEL BOARD SCHEDULE APPROVAL 5 09-Aug-15 13-Aug-15 ZB4AETEPS2 POWER S.L.D SUBMITTAL 5 16-Aug-15 20-Aug-15 ZB4AETEPAPOWER S.L.D APPROVAL 5 23-Aug-15 27-Aug-15 Lighting Sys Lighting System 114 01-Jul-15 21-Oct-15 ZB4AETELS LIGHTING FIXTURE SCHEDULE SUBMITTAL 5 01-Jul-15 07-Jul-15 ZB4AETELALIGHTING FIXTURE SCHEDULE APPROVAL 5 08-Jul-15 14-Jul-15 ZB4AETELS CENTRAL MONITORING RISER DIAGRAM SUBMITTAL 5 29-Sep-15 05-Oct-15 ZB4AETELS KNX SYSTEM RISER DIAGRAM SUBMITTAL 5 07-Oct-15 13-Oct-15 ZB4AETELACENTRAL MONITORING RISER DIAGRAM APPROVAL 5 07-Oct-15 13-Oct-15 ZB4AETELAKNX SYSTEM RISER DIAGRAM APPROVAL 5 15-Oct-15 21-Oct-15 Light Curren Light Current Systems 57 27-May-15 20-Jul-15 ZB4AETELGLIGHT CURRENT TYPICAL INSTALLATION DETAILS SUBMITTAL 5 27-May-15 02-Jun-15 ZB4AETELGLIGHT CURRENT TYPICAL INSTALLATION DETAILS APPROVAL 5 03-Jun-15 09-Jun-15 Fire Alarm S Fire Alarm System 15 01-Jul-15 14-Jul-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 2015 2016 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 8 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 9. Activity ID Activity Name Original Duration Start Finish ZB4AETELFIRE ALARM RISER DIAGRAM SUBMITTAL 5 01-Jul-15 07-Jul-15 ZB4AETELFIRE ALARM RISER DIAGRAM APPROVAL 5 08-Jul-15 14-Jul-15 Security Sys Security Systems 15 06-Jul-15 20-Jul-15 ZB4AETELIPCCTV RISER DIAGRAM SUBMITTAL (By Others) 5 06-Jul-15 12-Jul-15 ZB4AETELIPCCTV RISER DIAGRAM APPROVAL (By Others) 5 13-Jul-15 20-Jul-15 Communica Communication Systems 15 25-Jun-15 08-Jul-15 ZB4AETELSTRUCTURED CABLING RISER DIAGRAM SUBMITTAL (By Others) 5 25-Jun-15 01-Jul-15 ZB4AETELSTRUCTURED CABLING RISER DIAGRAM APPROVAL (By Others) 5 02-Jul-15 08-Jul-15 SCADA Syste SCADA System 15 13-Sep-15 28-Sep-15 ZB4AETEDSSCADA SYSTEM RISER DIAGRAM SUBMITTAL 5 13-Sep-15 17-Sep-15 ZB4AETEDASCADA SYSTEM RISER DIAGRAM APPROVAL 5 20-Sep-15 28-Sep-15 Mechanical Mechanical Systems 60 27-May-15 22-Jul-15 HVAC System HVAC System 15 27-May-15 09-Jun-15 ZB4AETMHSHVAC INSTALLATION DETAILS SUBMITTAL 5 27-May-15 02-Jun-15 ZB4AETMHA HVAC INSTALLATION DETAILS APPROVAL 5 03-Jun-15 09-Jun-15 Fire Protectio Fire Protection Systems 60 27-May-15 22-Jul-15 ZB4AETMFSFIRE PROTECTION INSTALLATION DETAILS SUBMITTAL 5 27-May-15 02-Jun-15 ZB4AETMFAFIRE PROTECTION INSTALLATION DETAILS APPROVAL 5 03-Jun-15 09-Jun-15 ZB4AETMFSFIRE PROTECTION RISER DIAGRAM SUBMITTAL 5 08-Jul-15 14-Jul-15 ZB4AETMFAFIRE PROTECTION RISER DIAGRAM APPROVAL 5 15-Jul-15 22-Jul-15 Plumbing Sy Plumbing System 15 27-May-15 09-Jun-15 ZB4AETMW WATER SUPPLY INSTALLATION DETAILS SUBMITTAL 5 27-May-15 02-Jun-15 ZB4AETMDSDRAINAGE SYSTEM INSTALLATION DETAILS SUBMITTAL 5 27-May-15 02-Jun-15 ZB4AETMWA WATER SUPPLY INSTALLATION DETAILS APPROVAL 5 03-Jun-15 09-Jun-15 ZB4AETMDA DRAINAGE SYSTEM INSTALLATION DETAILS APPROVAL 5 03-Jun-15 09-Jun-15 Building B4 - Building B4 - B (Electrical Services) 144 24-Jun-15 11-Nov-15 Ground Floor Ground Floor 129 24-Jun-15 28-Oct-15 ZB4BEGGBS10 Ground Floor Builder Work Submittal 5 23-Aug-15 27-Aug-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 2015 2016 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 9 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 10. Activity ID Activity Name Original Duration Start Finish ZB4BEGGBA10 Ground Floor Builder Work Approval 5 30-Aug-15 03-Sep-15 Electrical Sy Electrical Systems 82 24-Jun-15 10-Sep-15 Power Syste Power System 14 26-Jul-15 06-Aug-15 ZB4BEGEPS GROUND FLOOR POWER SYSTEM LAYOUT PLAN SUBMITTAL 5 26-Jul-15 30-Jul-15 ZB4BEGEPAGROUND FLOOR POWER SYSTEM LAYOUT PLAN APPROVAL 5 02-Aug-15 06-Aug-15 Lighting Sys Lighting System 15 24-Jun-15 07-Jul-15 ZB4BEGELS GROUND FLOOR LIGHTING SYSTEM LAYOUT PLAN SUBMITTAL 5 24-Jun-15 30-Jun-15 ZB4BEGELAGROUND FLOOR LIGHTING SYSTEM LAYOUT PLAN APPROVAL 5 01-Jul-15 07-Jul-15 Cable Tray S Cable Tray System 22 29-Jul-15 18-Aug-15 ZB4BEGECSGROUND FLOOR CABLE TRAY SYSTEM LAYOUT PLAN SUBMITTAL 10 29-Jul-15 11-Aug-15 ZB4BEGECAGROUND FLOOR CABLE TRAY SYSTEM LAYOUT PLAN APPROVAL 5 12-Aug-15 18-Aug-15 Earthing Sys Earthing System 14 09-Aug-15 20-Aug-15 ZB4BEGEES GROUND FLOOR EARTHING SYSTEM LAYOUT PLAN SUBMITTAL 5 09-Aug-15 13-Aug-15 ZB4BEGEEAGROUND FLOOR EARTHING SYSTEM LAYOUT PLAN APPROVAL 5 16-Aug-15 20-Aug-15 Light Curren Light Current Systems 60 24-Jun-15 20-Aug-15 Fire Alarm S Fire Alarm System 15 24-Jun-15 07-Jul-15 ZB4BEGELGROUND FLOOR FIRE ALARM SYSTEM LAYOUT PLAN SUBMITTAL 5 24-Jun-15 30-Jun-15 ZB4BEGELGROUND FLOOR FIRE ALARM SYSTEM LAYOUT PLAN APPROVAL 5 01-Jul-15 07-Jul-15 Security Sys Security Systems 55 29-Jun-15 20-Aug-15 ZB4BEGELGROUND FLOOR SECURITY SYSTEMS LAYOUT PLAN SUBMITTAL 5 29-Jun-15 05-Jul-15 ZB4BEGELGROUND FLOOR SECURITY SYSTEMS LAYOUT PLAN APPROVAL 5 06-Jul-15 12-Jul-15 ZB4BEGELAccess Control System Approval and Approved Submittal (By Others) 0 20-Aug-15 Communica Communication Systems 15 06-Jul-15 20-Jul-15 ZB4BEGELGROUND FLOOR COMMUNICATION SYSTEMS LAYOUT PLAN SUBMITTAL 5 06-Jul-15 12-Jul-15 ZB4BEGELGROUND FLOOR COMMUNICATION SYSTEMS LAYOUT PLAN APPROVAL 5 13-Jul-15 20-Jul-15 SCADA Syste SCADA System 14 30-Aug-15 10-Sep-15 ZB4BEGEDSGROUND FLOOR SCADA SYSTEM LAYOUT PLAN SUBMITTAL 5 30-Aug-15 03-Sep-15 ZB4BEGEDAGROUND FLOOR SCADA SYSTEM LAYOUT PLAN APPROVAL 5 06-Sep-15 10-Sep-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 2015 2016 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 10 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 11. Activity ID Activity Name Original Duration Start Finish Mechanical Mechanical Systems 129 24-Jun-15 28-Oct-15 HVAC System HVAC System 14 02-Aug-15 13-Aug-15 ZB4BEGMHSGROUND FLOOR HVAC SYSTEM LAYOUT PLAN SUBMITTAL 5 02-Aug-15 06-Aug-15 ZB4BEGMHA GROUND FLOOR HVAC SYSTEM LAYOUT PLAN APPROVAL 5 09-Aug-15 13-Aug-15 Fire Protectio Fire Protection Systems 22 07-Oct-15 28-Oct-15 ZB4BEGMFSFIRE PROTECTION WORK - SPECIAL SYSTEM DETAILS SUBMITTAL 10 07-Oct-15 21-Oct-15 ZB4BEGMFAFIRE PROTECTION WORK - SPECIAL SYSTEM DETAILS APPROVAL 5 22-Oct-15 28-Oct-15 Plumbing Sy Plumbing System 15 24-Jun-15 07-Jul-15 ZB4BEGMDSGROUND FLOOR DRAINAGE SYSTEM LAYOUT PLAN SUBMITTAL 5 24-Jun-15 30-Jun-15 ZB4BEGMDA GROUND FLOOR DRAINAGE SYSTEM LAYOUT PLAN APPROVAL 5 01-Jul-15 07-Jul-15 Composite D Composite Drawing 14 23-Aug-15 03-Sep-15 ZB4BEGCS10 GROUND FLOOR COMPOSITE LAYOUT PLAN SUBMITTAL 5 23-Aug-15 27-Aug-15 ZB4BEGCA10 GROUND FLOOR COMPOSITE LAYOUT PLAN APPROVAL 5 30-Aug-15 03-Sep-15 Roof 1 Roof 1 82 24-Jun-15 10-Sep-15 ZB4BERGBS10 Roof 1 Builder Work Submittal 5 30-Aug-15 03-Sep-15 ZB4BERGBA10 Roof 1 Builder Work Approval 5 06-Sep-15 10-Sep-15 Electrical Sy Electrical Systems 65 24-Jun-15 25-Aug-15 Power Syste Power System 14 02-Aug-15 13-Aug-15 ZB4BEREPS ROOF 1 FLOOR POWER SYSTEM LAYOUT PLAN SUBMITTAL 5 02-Aug-15 06-Aug-15 ZB4BEREPAROOF 1 FLOOR POWER SYSTEM LAYOUT PLAN APPROVAL 5 09-Aug-15 13-Aug-15 Lighting Sys Lighting System 15 01-Jul-15 14-Jul-15 ZB4BERELS ROOF 1 FLOOR LIGHTING SYSTEM LAYOUT PLAN SUBMITTAL 5 01-Jul-15 07-Jul-15 ZB4BERELAROOF 1 FLOOR LIGHTING SYSTEM LAYOUT PLAN APPROVAL 5 08-Jul-15 14-Jul-15 Cable Tray S Cable Tray System 15 12-Aug-15 25-Aug-15 ZB4BERECSROOF 1 FLOOR CABLE TRAY SYSTEM LAYOUT PLAN SUBMITTAL 5 12-Aug-15 18-Aug-15 ZB4BERECAROOF 1 FLOOR CABLE TRAY SYSTEM LAYOUT PLAN APPROVAL 5 19-Aug-15 25-Aug-15 Light Curren Light Current Systems 15 24-Jun-15 07-Jul-15 Fire Alarm S Fire Alarm System 15 24-Jun-15 07-Jul-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 2015 2016 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 11 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 12. Activity ID Activity Name Original Duration Start Finish ZB4BERELROOF 1 FLOOR FIRE ALARM SYSTEM LAYOUT PLAN SUBMITTAL 5 24-Jun-15 30-Jun-15 ZB4BERELROOF 1 FLOOR FIRE ALARM SYSTEM LAYOUT PLAN APPROVAL 5 01-Jul-15 07-Jul-15 Mechanical Mechanical Systems 60 01-Jul-15 27-Aug-15 HVAC System HVAC System 21 09-Aug-15 27-Aug-15 ZB4BERMHSROOF 1 FLOOR HVAC SYSTEM LAYOUT PLAN SUBMITTAL 10 09-Aug-15 20-Aug-15 ZB4BERMHSROOF 1 FLOOR HVAC SECTIONS LAYOUT PLAN SUBMITTAL 10 09-Aug-15 20-Aug-15 ZB4BERMHA ROOF 1 FLOOR HVAC SYSTEM LAYOUT PLAN APPROVAL 5 23-Aug-15 27-Aug-15 ZB4BERMHA ROOF 1 FLOOR HVAC SECTIONS LAYOUT PLAN APPROVAL 5 23-Aug-15 27-Aug-15 Plumbing Sy Plumbing System 15 01-Jul-15 14-Jul-15 ZB4BERMDSROOF 1 FLOOR DRAINAGE SYSTEM LAYOUT PLAN SUBMITTAL 5 01-Jul-15 07-Jul-15 ZB4BERMDA ROOF 1 FLOOR DRAINAGE SYSTEM LAYOUT PLAN APPROVAL 5 08-Jul-15 14-Jul-15 Composite D Composite Drawing 14 30-Aug-15 10-Sep-15 ZB4BERCS10 ROOF 1 FLOOR COMPOSITE LAYOUT PLAN SUBMITTAL 5 30-Aug-15 03-Sep-15 ZB4BERCA10 ROOF 1 FLOOR COMPOSITE LAYOUT PLAN APPROVAL 5 06-Sep-15 10-Sep-15 Roof 2 Roof 2 82 24-Jun-15 10-Sep-15 ZB4BEUGBS10 Roof 2 Builder Work Submittal 5 30-Aug-15 03-Sep-15 ZB4BEUGBA10 Roof 2 Builder Work Approval 5 06-Sep-15 10-Sep-15 Electrical Sy Electrical Systems 67 24-Jun-15 27-Aug-15 Power Syste Power System 14 02-Aug-15 13-Aug-15 ZB4BEUEPS ROOF 2 FLOOR POWER SYSTEM LAYOUT PLAN SUBMITTAL 5 02-Aug-15 06-Aug-15 ZB4BEUEPAROOF 2 FLOOR POWER SYSTEM LAYOUT PLAN APPROVAL 5 09-Aug-15 13-Aug-15 Lighting Sys Lighting System 15 08-Jul-15 22-Jul-15 ZB4BEUELS ROOF 2 FLOOR LIGHTING SYSTEM LAYOUT PLAN SUBMITTAL 5 08-Jul-15 14-Jul-15 ZB4BEUELAROOF 2 FLOOR LIGHTING SYSTEM LAYOUT PLAN APPROVAL 5 15-Jul-15 22-Jul-15 Cable Tray S Cable Tray System 15 12-Aug-15 25-Aug-15 ZB4BEUECSROOF 2 FLOOR CABLE TRAY SYSTEM LAYOUT PLAN SUBMITTAL 5 12-Aug-15 18-Aug-15 ZB4BEUECAROOF 2 FLOOR CABLE TRAY SYSTEM LAYOUT PLAN APPROVAL 5 19-Aug-15 25-Aug-15 Lightning Sy Lightning System 14 16-Aug-15 27-Aug-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 2015 2016 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 12 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 13. Activity ID Activity Name Original Duration Start Finish ZB4BEUEHSROOF 2 FLOOR LIGHTNING SYSTEM LAYOUT PLAN SUBMITTAL 5 16-Aug-15 20-Aug-15 ZB4BEUEHAROOF 2 FLOOR LIGHTNING SYSTEM LAYOUT PLAN APPROVAL 5 23-Aug-15 27-Aug-15 Light Curren Light Current Systems 7 24-Jun-15 30-Jun-15 Fire Alarm S Fire Alarm System 7 24-Jun-15 30-Jun-15 ZB4BEUELROOF 2 FLOOR FIRE ALARM SYSTEM LAYOUT PLAN SUBMITTAL 5 24-Jun-15 30-Jun-15 ZB4BEUELROOF 2 FLOOR FIRE ALARM SYSTEM LAYOUT PLAN APPROVAL 5 24-Jun-15 30-Jun-15 Mechanical Mechanical Systems 52 08-Jul-15 27-Aug-15 HVAC System HVAC System 21 09-Aug-15 27-Aug-15 ZB4BEUMHSROOF 2 FLOOR HVAC SYSTEM LAYOUT PLAN SUBMITTAL 10 09-Aug-15 20-Aug-15 ZB4BEUMHSROOF 2 FLOOR HVAC SECTIONS LAYOUT PLAN SUBMITTAL 10 09-Aug-15 20-Aug-15 ZB4BEUMHA ROOF 2 FLOOR HVAC SYSTEM LAYOUT PLAN APPROVAL 5 23-Aug-15 27-Aug-15 ZB4BEUMHA ROOF 2 FLOOR HVAC SECTIONS LAYOUT PLAN APPROVAL 5 23-Aug-15 27-Aug-15 Plumbing Sy Plumbing System 15 08-Jul-15 22-Jul-15 ZB4BEUMDSROOF 2 FLOOR DRAINAGE SYSTEM LAYOUT PLAN SUBMITTAL 5 08-Jul-15 14-Jul-15 ZB4BEUMDA ROOF 2 FLOOR DRAINAGE SYSTEM LAYOUT PLAN APPROVAL 5 15-Jul-15 22-Jul-15 Composite D Composite Drawing 14 30-Aug-15 10-Sep-15 ZB4BEUCS10 ROOF 2 FLOOR COMPOSITE LAYOUT PLAN SUBMITTAL 5 30-Aug-15 03-Sep-15 ZB4BEUCA10 ROOF 2 FLOOR COMPOSITE LAYOUT PLAN APPROVAL 5 06-Sep-15 10-Sep-15 General Sho General Shop Drawings 144 24-Jun-15 11-Nov-15 Electrical Sy Electrical Systems 144 24-Jun-15 11-Nov-15 ZB4BETEGS10ELECTRICAL INSTALLATION DETAILS SUBMITTAL 5 26-Jul-15 30-Jul-15 ZB4BETEGA10ELECTRICAL INSTALLATION DETAILS APPROVAL 5 02-Aug-15 06-Aug-15 Power Syste Power System 60 13-Sep-15 11-Nov-15 ZB4BETEPS1PANEL BOARD SCHEDULE SUBMITTAL 5 13-Sep-15 17-Sep-15 ZB4BETEPA PANEL BOARD SCHEDULE APPROVAL 5 20-Sep-15 28-Sep-15 ZB4BETEPS2POWER S.L.D SUBMITTAL 5 29-Sep-15 05-Oct-15 ZB4BETEPA POWER S.L.D APPROVAL 5 07-Oct-15 13-Oct-15 ZB4BETEPS3BUILDING POWER S.L.D SUBMITTAL 5 15-Oct-15 21-Oct-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 2015 2016 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 13 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 14. Activity ID Activity Name Original Duration Start Finish ZB4BETEPA BUILDING POWER S.L.D APPROVAL 5 22-Oct-15 28-Oct-15 ZB4BETEPS4CAMPUS POWER S.L.D SUBMITTAL 5 29-Oct-15 04-Nov-15 ZB4BETEPA CAMPUS POWER S.L.D APPROVAL 5 05-Nov-15 11-Nov-15 Lighting Sys Lighting System 21 26-Jul-15 13-Aug-15 ZB4BETELS LIGHTING FIXTURE SCHEDULE SUBMITTAL 5 26-Jul-15 30-Jul-15 ZB4BETELALIGHTING FIXTURE SCHEDULE APPROVAL 5 02-Aug-15 06-Aug-15 ZB4BETELS2 KNX SYSTEM RISER DIAGRAM SUBMITTAL 5 02-Aug-15 06-Aug-15 ZB4BETELS3 CENTRAL MONITORING RISER DIAGRAM SUBMITTAL 5 02-Aug-15 06-Aug-15 ZB4BETELAKNX SYSTEM RISER DIAGRAM APPROVAL 5 09-Aug-15 13-Aug-15 ZB4BETELACENTRAL MONITORING RISER DIAGRAM APPROVAL 5 09-Aug-15 13-Aug-15 Light Curren Light Current Systems 42 24-Jun-15 04-Aug-15 ZB4BETELGLIGHT CURRENT TYPICAL INSTALLATION DETAILS SUBMITTAL 5 24-Jun-15 30-Jun-15 ZB4BETELGLIGHT CURRENT TYPICAL INSTALLATION DETAILS APPROVAL 5 01-Jul-15 07-Jul-15 Fire Alarm S Fire Alarm System 15 08-Jul-15 22-Jul-15 ZB4BETELFIRE ALARM RISER DIAGRAM SUBMITTAL 5 08-Jul-15 14-Jul-15 ZB4BETELFIRE ALARM RISER DIAGRAM APPROVAL 5 15-Jul-15 22-Jul-15 Security Sys Security Systems 15 13-Jul-15 28-Jul-15 ZB4BETELIPCCTV RISER DIAGRAM SUBMITTAL (By Others) 5 13-Jul-15 20-Jul-15 ZB4BETELIPCCTV RISER DIAGRAM APPROVAL (By Others) 5 21-Jul-15 28-Jul-15 Communica Communication Systems 15 21-Jul-15 04-Aug-15 ZB4BETELSTRUCTURED CABLING RISER DIAGRAM SUBMITTAL (By Others) 5 21-Jul-15 28-Jul-15 ZB4BETELSTRUCTURED CABLING RISER DIAGRAM APPROVAL (By Others) 5 29-Jul-15 04-Aug-15 SCADA Syste SCADA System 15 13-Sep-15 28-Sep-15 ZB4BETEDS SCADA SYSTEM RISER DIAGRAM SUBMITTAL 5 13-Sep-15 17-Sep-15 ZB4BETEDASCADA SYSTEM RISER DIAGRAM APPROVAL 5 20-Sep-15 28-Sep-15 Mechanical Mechanical Systems 75 24-Jun-15 03-Sep-15 HVAC System HVAC System 14 23-Aug-15 03-Sep-15 ZB4BETMHSHVAC INSTALLATION DETAILS SUBMITTAL 5 23-Aug-15 27-Aug-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 2015 2016 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 14 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 15. Activity ID Activity Name Original Duration Start Finish ZB4BETMHA HVAC INSTALLATION DETAILS APPROVAL 5 30-Aug-15 03-Sep-15 Fire Protectio Fire Protection Systems 15 01-Jul-15 14-Jul-15 ZB4BETMFSFIRE PROTECTION INSTALLATION DETAILS SUBMITTAL 5 01-Jul-15 07-Jul-15 ZB4BETMFAFIRE PROTECTION INSTALLATION DETAILS APPROVAL 5 08-Jul-15 14-Jul-15 Plumbing Sy Plumbing System 15 24-Jun-15 07-Jul-15 ZB4BETMPDDRAINAGE SYSTEM INSTALLATION DETAILS SUBMITTAL 5 24-Jun-15 30-Jun-15 ZB4BETMPDDRAINAGE SYSTEM INSTALLATION DETAILS APPROVAL 5 01-Jul-15 07-Jul-15 Building B4 - Building B4 - D (Fuel Tank) 106 24-Jun-15 05-Oct-15 Ground Floor Ground Floor 106 24-Jun-15 05-Oct-15 ZB4DEGGBS30 Ground Floor Builder Work Submittal 5 23-Aug-15 27-Aug-15 ZB4DEGGBA30 Ground Floor Builder Work Approval 5 30-Aug-15 03-Sep-15 Electrical Sy Electrical Systems 60 24-Jun-15 20-Aug-15 Power Syste Power System 14 26-Jul-15 06-Aug-15 ZB4DEGEPS GROUND & ROOF 1 FLOOR POWER SYSTEM LAYOUTS PLAN SUBMITTAL 5 26-Jul-15 30-Jul-15 ZB4DEGEPAGROUND & ROOF 1 FLOOR POWER SYSTEM LAYOUTS PLAN APPROVAL 5 02-Aug-15 06-Aug-15 Lighting Sys Lighting System 15 24-Jun-15 07-Jul-15 ZB4DEGELSGROUND FLOOR LIGHTING SYSTEM LAYOUT PLAN SUBMITTAL 5 24-Jun-15 30-Jun-15 ZB4DEGELAGROUND FLOOR LIGHTING SYSTEM LAYOUT PLAN APPROVAL 5 01-Jul-15 07-Jul-15 Cable Tray S Cable Tray System 22 29-Jul-15 18-Aug-15 ZB4DEGECSGROUND FLOOR CABLE TRAY SYSTEM LAYOUT PLAN SUBMITTAL 10 29-Jul-15 11-Aug-15 ZB4DEGECAGROUND FLOOR CABLE TRAY SYSTEM LAYOUT PLAN APPROVAL 5 12-Aug-15 18-Aug-15 Earthing Sys Earthing System 14 09-Aug-15 20-Aug-15 ZB4DEGEESGROUND FLOOR EARTHING SYSTEM LAYOUT PLAN SUBMITTAL 5 09-Aug-15 13-Aug-15 ZB4DEGEEAGROUND FLOOR EARTHING SYSTEM LAYOUT PLAN APPROVAL 5 16-Aug-15 20-Aug-15 Light Curren Light Current Systems 60 24-Jun-15 20-Aug-15 Fire Alarm S Fire Alarm System 15 24-Jun-15 07-Jul-15 ZB4DEGELGROUND FLOOR FIRE ALARM SYSTEM LAYOUT PLAN SUBMITTAL 5 24-Jun-15 30-Jun-15 ZB4DEGELGROUND FLOOR FIRE ALARM SYSTEM LAYOUT PLAN APPROVAL 5 01-Jul-15 07-Jul-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 2015 2016 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 15 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 16. Activity ID Activity Name Original Duration Start Finish Security Sys Security Systems 0 20-Aug-15 20-Aug-15 ZB4DEGELAccess Control System Approval and Approved Submittal (By Others) 0 20-Aug-15 Mechanical Mechanical Systems 106 24-Jun-15 05-Oct-15 HVAC System HVAC System 14 02-Aug-15 13-Aug-15 ZB4DEGMHSGROUND FLOOR HVAC SYSTEM LAYOUT PLAN SUBMITTAL 5 02-Aug-15 06-Aug-15 ZB4DEGMHA GROUND FLOOR HVAC SYSTEM LAYOUT PLAN APPROVAL 5 09-Aug-15 13-Aug-15 Fire Protectio Fire Protection Systems 22 13-Sep-15 05-Oct-15 ZB4DEGMFSFIRE PROTECTION WORK - SPECIAL SYSTEM DETAILS SUBMITTAL 10 13-Sep-15 28-Sep-15 ZB4DEGMFAFIRE PROTECTION WORK - SPECIAL SYSTEM DETAILS APPROVAL 5 29-Sep-15 05-Oct-15 Plumbing Sy Plumbing System 15 24-Jun-15 07-Jul-15 ZB4DEGMDSGROUND FLOOR DRAINAGE SYSTEM LAYOUT PLAN SUBMITTAL 5 24-Jun-15 30-Jun-15 ZB4DEGMDA GROUND FLOOR DRAINAGE SYSTEM LAYOUT PLAN APPROVAL 5 01-Jul-15 07-Jul-15 Composite D Composite Drawing 14 23-Aug-15 03-Sep-15 ZB4DEGCS30 GROUND FLOOR COMPOSITE LAYOUT PLAN SUBMITTAL 5 23-Aug-15 27-Aug-15 ZB4DEGCA30 GROUND FLOOR COMPOSITE LAYOUT PLAN APPROVAL 5 30-Aug-15 03-Sep-15 Roof 1 Roof 1 75 24-Jun-15 03-Sep-15 Electrical Sy Electrical Systems 75 24-Jun-15 03-Sep-15 Light Curren Light Current Systems 20 24-Jun-15 12-Jul-15 Fire Alarm S Fire Alarm System 7 24-Jun-15 30-Jun-15 ZB4DEUELROOF 1 FLOOR FIRE ALARM SYSTEM LAYOUT PLAN SUBMITTAL 5 24-Jun-15 30-Jun-15 ZB4DEUELROOF 1 FLOOR FIRE ALARM SYSTEM LAYOUT PLAN APPROVAL 5 24-Jun-15 30-Jun-15 Security Sys Security Systems 15 29-Jun-15 12-Jul-15 ZB4DEGELROOF 1 FLOOR SECURITY SYSTEMS LAYOUT PLAN SUBMITTAL 5 29-Jun-15 05-Jul-15 ZB4DEGELROOF 1 FLOOR SECURITY SYSTEMS LAYOUT PLAN APPROVAL 5 06-Jul-15 12-Jul-15 Lightning Sy Lightning System 14 23-Aug-15 03-Sep-15 ZB4DEUEHSROOF 1 FLOOR LIGHTNING SYSTEM LAYOUT PLAN SUBMITTAL 5 23-Aug-15 27-Aug-15 ZB4DEUEHAROOF 1 FLOOR LIGHTNING SYSTEM LAYOUT PLAN APPROVAL 5 30-Aug-15 03-Sep-15 Mechanical Mechanical Systems 15 01-Jul-15 14-Jul-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 2015 2016 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 16 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 17. Activity ID Activity Name Original Duration Start Finish Plumbing Sy Plumbing System 15 01-Jul-15 14-Jul-15 ZB4DERMDSROOF 1 FLOOR DRAINAGE SYSTEM LAYOUT PLAN SUBMITTAL 5 01-Jul-15 07-Jul-15 ZB4DERMDA ROOF 1 FLOOR DRAINAGE SYSTEM LAYOUT PLAN APPROVAL 5 08-Jul-15 14-Jul-15 General Sho General Shop Drawings 106 24-Jun-15 05-Oct-15 Electrical Sy Electrical Systems 106 24-Jun-15 05-Oct-15 ZB4DETEGS30ELECTRICAL INSTALLATION DETAILS SUBMITTAL 5 26-Jul-15 30-Jul-15 ZB4DETEGA30ELECTRICAL INSTALLATION DETAILS APPROVAL 5 02-Aug-15 06-Aug-15 Power Syste Power System 30 06-Sep-15 05-Oct-15 ZB4DETEPS6 POWER S.L.D SUBMITTAL 15 06-Sep-15 28-Sep-15 ZB4DETEPAPOWER S.L.D APPROVAL 5 29-Sep-15 05-Oct-15 Lighting Sys Lighting System 22 08-Jul-15 30-Jul-15 ZB4DETELS LIGHTING FIXTURE SCHEDULE SUBMITTAL 5 08-Jul-15 14-Jul-15 ZB4DETELALIGHTING FIXTURE SCHEDULE APPROVAL 5 15-Jul-15 22-Jul-15 ZB4DETELS KNX SYSTEM RISER DIAGRAM SUBMITTAL 5 15-Jul-15 22-Jul-15 ZB4DETELAKNX SYSTEM RISER DIAGRAM APPROVAL 5 26-Jul-15 30-Jul-15 Light Curren Light Current Systems 35 24-Jun-15 28-Jul-15 ZB4DETELGLIGHT CURRENT TYPICAL INSTALLATION DETAILS SUBMITTAL 5 24-Jun-15 30-Jun-15 ZB4DETELGLIGHT CURRENT TYPICAL INSTALLATION DETAILS APPROVAL 5 01-Jul-15 07-Jul-15 Fire Alarm S Fire Alarm System 15 08-Jul-15 22-Jul-15 ZB4DETELFIRE ALARM RISER DIAGRAM SUBMITTAL 5 08-Jul-15 14-Jul-15 ZB4DETELFIRE ALARM RISER DIAGRAM APPROVAL 5 15-Jul-15 22-Jul-15 Security Sys Security Systems 15 13-Jul-15 28-Jul-15 ZB4DETELIPCCTV RISER DIAGRAM SUBMITTAL (By Others) 5 13-Jul-15 20-Jul-15 ZB4DETELIPCCTV RISER DIAGRAM APPROVAL (By Others) 5 21-Jul-15 28-Jul-15 Building B4 - Building B4 - E (EDC Building) 106 24-Jun-15 05-Oct-15 Ground Floor Ground Floor 90 24-Jun-15 17-Sep-15 ZB4EEGGBS20 Ground Floor Builder Work Submittal 5 23-Aug-15 27-Aug-15 ZB4EEGGBA20 Ground Floor Builder Work Approval 5 30-Aug-15 03-Sep-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 2015 2016 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 17 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 18. Activity ID Activity Name Original Duration Start Finish Electrical Sy Electrical Systems 82 24-Jun-15 10-Sep-15 Power Syste Power System 14 26-Jul-15 06-Aug-15 ZB4EEGEPS2 GROUND FLOOR POWER SYSTEM LAYOUT PLAN SUBMITTAL 5 26-Jul-15 30-Jul-15 ZB4EEGEPAGROUND FLOOR POWER SYSTEM LAYOUT PLAN APPROVAL 5 02-Aug-15 06-Aug-15 Lighting Sys Lighting System 15 24-Jun-15 07-Jul-15 ZB4EEGELS GROUND FLOOR LIGHTING SYSTEM LAYOUT PLAN SUBMITTAL 5 24-Jun-15 30-Jun-15 ZB4EEGELAGROUND FLOOR LIGHTING SYSTEM LAYOUT PLAN APPROVAL 5 01-Jul-15 07-Jul-15 Cable Tray S Cable Tray System 22 29-Jul-15 18-Aug-15 ZB4EEGECSGROUND FLOOR CABLE TRAY SYSTEM LAYOUT PLAN SUBMITTAL 10 29-Jul-15 11-Aug-15 ZB4EEGECAGROUND FLOOR CABLE TRAY SYSTEM LAYOUT PLAN APPROVAL 5 12-Aug-15 18-Aug-15 Earthing Sys Earthing System 14 09-Aug-15 20-Aug-15 ZB4EEGEES GROUND FLOOR EARTHING SYSTEM LAYOUT PLAN SUBMITTAL 5 09-Aug-15 13-Aug-15 ZB4EEGEEAGROUND FLOOR EARTHING SYSTEM LAYOUT PLAN APPROVAL 5 16-Aug-15 20-Aug-15 Light Curren Light Current Systems 60 24-Jun-15 20-Aug-15 Fire Alarm S Fire Alarm System 15 24-Jun-15 07-Jul-15 ZB4EEGELGROUND FLOOR FIRE ALARM SYSTEM LAYOUT PLAN SUBMITTAL 5 24-Jun-15 30-Jun-15 ZB4EEGELGROUND FLOOR FIRE ALARM SYSTEM LAYOUT PLAN APPROVAL 5 01-Jul-15 07-Jul-15 Security Sys Security Systems 55 29-Jun-15 20-Aug-15 ZB4EEGELGROUND FLOOR SECURITY SYSTEMS LAYOUT PLAN SUBMITTAL 5 29-Jun-15 05-Jul-15 ZB4EEGELGROUND FLOOR SECURITY SYSTEMS LAYOUT PLAN APPROVAL 5 06-Jul-15 12-Jul-15 ZB4EEGELAccess Control System Approval and Approved Submittal (By Others) 0 20-Aug-15 Communica Communication Systems 15 06-Jul-15 20-Jul-15 ZB4EEGELGROUND FLOOR COMMUNICATION SYSTEMS LAYOUT PLAN SUBMITTAL 5 06-Jul-15 12-Jul-15 ZB4EEGELGROUND FLOOR COMMUNICATION SYSTEMS LAYOUT PLAN APPROVAL 5 13-Jul-15 20-Jul-15 SCADA Syste SCADA System 14 30-Aug-15 10-Sep-15 ZB4EEGEDSGROUND FLOOR SCADA SYSTEM LAYOUT PLAN SUBMITTAL 5 30-Aug-15 03-Sep-15 ZB4EEGEDAGROUND FLOOR SCADA SYSTEM LAYOUT PLAN APPROVAL 5 06-Sep-15 10-Sep-15 Mechanical Mechanical Systems 90 24-Jun-15 17-Sep-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 2015 2016 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 18 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 19. Activity ID Activity Name Original Duration Start Finish HVAC System HVAC System 14 02-Aug-15 13-Aug-15 ZB4EEGMHSGROUND FLOOR HVAC SYSTEM LAYOUT PLAN SUBMITTAL 5 02-Aug-15 06-Aug-15 ZB4EEGMHA GROUND FLOOR HVAC SYSTEM LAYOUT PLAN APPROVAL 5 09-Aug-15 13-Aug-15 Fire Protectio Fire Protection Systems 21 30-Aug-15 17-Sep-15 ZB4EEGMFSFIRE PROTECTION WORK - SPECIAL SYSTEM DETAILS SUBMITTAL 10 30-Aug-15 10-Sep-15 ZB4EEGMFAFIRE PROTECTION WORK - SPECIAL SYSTEM DETAILS APPROVAL 5 13-Sep-15 17-Sep-15 Plumbing Sy Plumbing System 15 24-Jun-15 07-Jul-15 ZB4EEGMDSGROUND FLOOR DRAINAGE SYSTEM LAYOUT PLAN SUBMITTAL 5 24-Jun-15 30-Jun-15 ZB4EEGMDA GROUND FLOOR DRAINAGE SYSTEM LAYOUT PLAN APPROVAL 5 01-Jul-15 07-Jul-15 Composite D Composite Drawing 14 23-Aug-15 03-Sep-15 ZB4EEGCS20 GROUND FLOOR COMPOSITE LAYOUT PLAN SUBMITTAL 5 23-Aug-15 27-Aug-15 ZB4EEGCA20 GROUND FLOOR COMPOSITE LAYOUT PLAN APPROVAL 5 30-Aug-15 03-Sep-15 Roof 1 Roof 1 15 01-Jul-15 14-Jul-15 Mechanical Mechanical Systems 15 01-Jul-15 14-Jul-15 Plumbing Sy Plumbing System 15 01-Jul-15 14-Jul-15 ZB4EERMDSROOF 1 FLOOR DRAINAGE SYSTEM LAYOUT PLAN SUBMITTAL 5 01-Jul-15 07-Jul-15 ZB4EERMDA ROOF 1 FLOOR DRAINAGE SYSTEM LAYOUT PLAN APPROVAL 5 08-Jul-15 14-Jul-15 General Sho General Shop Drawings 106 24-Jun-15 05-Oct-15 Electrical Sy Electrical Systems 106 24-Jun-15 05-Oct-15 ZB4EETEGS20ELECTRICAL INSTALLATION DETAILS SUBMITTAL 5 26-Jul-15 30-Jul-15 ZB4EETEGA20ELECTRICAL INSTALLATION DETAILS APPROVAL 5 02-Aug-15 06-Aug-15 Power Syste Power System 30 06-Sep-15 05-Oct-15 ZB4EETEPS5POWER S.L.D SUBMITTAL 15 06-Sep-15 28-Sep-15 ZB4EETEPA POWER S.L.D APPROVAL 5 29-Sep-15 05-Oct-15 Lighting Sys Lighting System 22 08-Jul-15 30-Jul-15 ZB4EETELS4 LIGHTING FIXTURE SCHEDULE SUBMITTAL 5 08-Jul-15 14-Jul-15 ZB4EETELALIGHTING FIXTURE SCHEDULE APPROVAL 5 15-Jul-15 22-Jul-15 ZB4EETELS5 KNX SYSTEM RISER DIAGRAM SUBMITTAL 5 15-Jul-15 22-Jul-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 2015 2016 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 19 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 20. Activity ID Activity Name Original Duration Start Finish ZB4EETELAKNX SYSTEM RISER DIAGRAM APPROVAL 5 26-Jul-15 30-Jul-15 Light Curren Light Current Systems 35 24-Jun-15 28-Jul-15 ZB4EETELGLIGHT CURRENT TYPICAL INSTALLATION DETAILS SUBMITTAL 5 24-Jun-15 30-Jun-15 ZB4EETELGLIGHT CURRENT TYPICAL INSTALLATION DETAILS APPROVAL 5 01-Jul-15 07-Jul-15 Fire Alarm S Fire Alarm System 15 08-Jul-15 22-Jul-15 ZB4EETELFIRE ALARM RISER DIAGRAM SUBMITTAL 5 08-Jul-15 14-Jul-15 ZB4EETELFIRE ALARM RISER DIAGRAM APPROVAL 5 15-Jul-15 22-Jul-15 Security Sys Security Systems 15 13-Jul-15 28-Jul-15 ZB4EETELIPCCTV RISER DIAGRAM SUBMITTAL (By Others) 5 13-Jul-15 20-Jul-15 ZB4EETELIPCCTV RISER DIAGRAM APPROVAL (By Others) 5 21-Jul-15 28-Jul-15 SCADA Syste SCADA System 15 13-Sep-15 28-Sep-15 ZB4EETEDS SCADA SYSTEM RISER DIAGRAM SUBMITTAL 5 13-Sep-15 17-Sep-15 ZB4EETEDASCADA SYSTEM RISER DIAGRAM APPROVAL 5 20-Sep-15 28-Sep-15 Tunnel & Site Tunnel & Site Layout 235 26-May-15 10-Jan-16 ZB4LEB460 Receive Approved Site Layout (Architecture & Structural & Roads Sections and Levels) 0 26-May-15 ZB4LEB650 Receive Approved Site Layout (MEP Networks out of Siemens Scope) 0 26-May-15 Service Tun Service Tunnel 204 26-May-15 09-Dec-15 Electrical Sy Electrical Systems 204 26-May-15 09-Dec-15 Tunnel Mediu Tunnel Medium Voltage Network 30 12-Nov-15 09-Dec-15 ZB4TEBEPS3BASEMENT FLOOR MV NETWORK LAYOUT PLAN SUBMITTAL 15 12-Nov-15 02-Dec-15 ZB4TEBEPA BASEMENT FLOOR MV NETWORK LAYOUT PLAN APPROVAL 5 03-Dec-15 09-Dec-15 Tunnel Low V Tunnel Low Voltage Network 0 26-May-15 26-May-15 ZB4TEBELABASEMENT FLOOR LV NETWORK LAYOUT PLAN APPROVAL (BY OTHERS) 0 26-May-15 Power Syste Power System 14 02-Aug-15 13-Aug-15 ZB4TEBEPS2BASEMENT FLOOR POWER SYSTEM LAYOUT PLAN SUBMITTAL 5 02-Aug-15 06-Aug-15 ZB4TEBEPA BASEMENT FLOOR POWER SYSTEM LAYOUT PLAN APPROVAL 5 09-Aug-15 13-Aug-15 Lighting Sys Lighting System 15 02-Jul-15 15-Jul-15 ZB4TEBELS2 BASEMENT FLOOR LIGHTING SYSTEM LAYOUT PLAN SUBMITTAL 5 02-Jul-15 08-Jul-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 2015 2016 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 20 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 21. Activity ID Activity Name Original Duration Start Finish ZB4TEBELABASEMENT FLOOR LIGHTING SYSTEM LAYOUT PLAN APPROVAL 5 09-Jul-15 15-Jul-15 Light Curren Light Current Systems 83 26-May-15 13-Aug-15 Fire Alarm S Fire Alarm System 83 26-May-15 13-Aug-15 ZB4TEBELINFRASTRUCTURE FIRE ALARM SERVICE CORRIDOR APPROVAL (BY OTHERS) 0 26-May-15 ZB4TEBELBASEMENT FLOOR FIRE ALARM SYSTEM PLAN SUBMITTAL 5 02-Aug-15 06-Aug-15 ZB4TEBELBASEMENT FLOOR FIRE ALARM SYSTEM PLAN APPROVAL 5 09-Aug-15 13-Aug-15 Security Sys Security Systems 0 26-May-15 26-May-15 ZB4TEBELCCTV SYSTEM - SERVICE CORRIDOR APPROVAL (BY OTHERS) 0 26-May-15 Communica Communication Systems 0 26-May-15 26-May-15 ZB4TEBELTELECOMMUNICATION INFRASTRUCTURE CABLING APPROVAL (BY OTHERS) 0 26-May-15 SCADA Syste SCADA System 14 06-Sep-15 17-Sep-15 ZB4TEBEDS BASEMENT FLOOR SCADA SYSTEM LAYOUT PLAN SUBMITTAL 5 06-Sep-15 10-Sep-15 ZB4TEBEDABASEMENT FLOOR SCADA SYSTEM LAYOUT PLAN APPROVAL 5 13-Sep-15 17-Sep-15 Mechanical Mechanical Systems 60 10-Jun-15 06-Aug-15 HVAC System HVAC System 47 22-Jun-15 06-Aug-15 ZB4TEBMHSBASEMENT FLOOR HVAC PIPING LAYOUT PLAN SUBMITTAL 15 22-Jun-15 12-Jul-15 ZB4TEBMHA BASEMENT FLOOR HVAC PIPING LAYOUT PLAN APPROVAL 5 13-Jul-15 20-Jul-15 ZB4TEBMHSBASEMENT FLOOR HVAC DUCT SYSTEM LAYOUT PLAN SUBMITTAL 10 15-Jul-15 30-Jul-15 ZB4TEBMHA BASEMENT FLOOR HVAC DUCT SYSTEM LAYOUT PLAN APPROVAL 5 02-Aug-15 06-Aug-15 Fire Protectio Fire Protection Systems 22 10-Jun-15 30-Jun-15 ZB4TEBMFSFIRE PROTECTION WORK -SERVICE TUNNEL- OVERALL PLAN SUBMITTAL 10 10-Jun-15 23-Jun-15 ZB4TEBMFAFIRE PROTECTION WORK -SERVICE TUNNEL- OVERALL PLAN APPROVAL 5 24-Jun-15 30-Jun-15 Plumbing Sy Plumbing System 52 17-Jun-15 06-Aug-15 ZB4TEBMWS BASEMENT FLOOR WATER SUPPLY SYSTEM LAYOUT PLAN SUBMITTAL 15 17-Jun-15 07-Jul-15 ZB4TEBMDSBASEMENT FLOOR DRAINAGE SYSTEM LAYOUT PLAN SUBMITTAL 15 17-Jun-15 07-Jul-15 ZB4TEBMWA BASEMENT FLOOR WATER SUPPLY SYSTEM LAYOUT PLAN APPROVAL 5 08-Jul-15 14-Jul-15 ZB4TEBMDA BASEMENT FLOOR DRAINAGE SYSTEM LAYOUT PLAN APPROVAL 5 08-Jul-15 14-Jul-15 ZB4TEBMWS SUMP PIT DETAILS & SECTIONS SUBMITTAL 15 08-Jul-15 30-Jul-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 2015 2016 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 21 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 22. Activity ID Activity Name Original Duration Start Finish ZB4TEBMWA SUMP PIT DETAILS & SECTIONS APPROVAL 5 02-Aug-15 06-Aug-15 Composite D Composite Drawing 21 16-Aug-15 03-Sep-15 ZB4TEBCS20 SERVICE TUNNEL COMPOSITE LAYOUT PLAN SUBMITTAL 10 16-Aug-15 27-Aug-15 ZB4TEBCA20 SERVICE TUNNEL COMPOSITE LAYOUT PLAN APPROVAL 5 30-Aug-15 03-Sep-15 General Sho General Shop Drawings 99 24-Jun-15 28-Sep-15 Electrical Sys Electrical Systems 99 24-Jun-15 28-Sep-15 ZB4TETEGS ELECTRICAL INSTALLATION DETAILS SUBMITTAL 5 26-Jul-15 30-Jul-15 ZB4TETEGAELECTRICAL INSTALLATION DETAILS APPROVAL 5 02-Aug-15 06-Aug-15 Power Syste Power System 14 16-Aug-15 27-Aug-15 ZB4TETEPPOWER S.L.D AND PANEL BOARD SCHEDULE SUBMITTAL 5 16-Aug-15 20-Aug-15 ZB4TETEPPOWER S.L.D AND PANEL BOARD SCHEDULE APPROVAL 5 23-Aug-15 27-Aug-15 Lighting Sys Lighting System 22 08-Jul-15 30-Jul-15 ZB4TETELLIGHTING FIXTURE SCHEDULE SUBMITTAL 5 08-Jul-15 14-Jul-15 ZB4TETELLIGHTING FIXTURE SCHEDULE APPROVAL 5 15-Jul-15 22-Jul-15 ZB4TETELKNX SYSTEM RISER DIAGRAM SUBMITTAL 5 15-Jul-15 22-Jul-15 ZB4TETELKNX SYSTEM RISER DIAGRAM APPROVAL 5 26-Jul-15 30-Jul-15 Light Curren Light Current Systems 35 24-Jun-15 28-Jul-15 ZB4TETELLIGHT CURRENT TYPICAL INSTALLATION DETAILS SUBMITTAL 5 24-Jun-15 30-Jun-15 ZB4TETELLIGHT CURRENT TYPICAL INSTALLATION DETAILS APPROVAL 5 01-Jul-15 07-Jul-15 Fire Alarm S Fire Alarm System 15 08-Jul-15 22-Jul-15 ZB4TETE FIRE ALARM RISER DIAGRAM SUBMITTAL 5 08-Jul-15 14-Jul-15 ZB4TETE FIRE ALARM RISER DIAGRAM APPROVAL 5 15-Jul-15 22-Jul-15 Security Sy Security Systems 15 13-Jul-15 28-Jul-15 ZB4TETE IPCCTV RISER DIAGRAM SUBMITTAL (By Others) 5 13-Jul-15 20-Jul-15 ZB4TETE IPCCTV RISER DIAGRAM APPROVAL (By Others) 5 21-Jul-15 28-Jul-15 SCADA Sys SCADA System 15 13-Sep-15 28-Sep-15 ZB4TETEDSCADA SYSTEM RISER DIAGRAM SUBMITTAL 5 13-Sep-15 17-Sep-15 ZB4TETEDSCADA SYSTEM RISER DIAGRAM APPROVAL 5 20-Sep-15 28-Sep-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 2015 2016 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 22 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 23. Activity ID Activity Name Original Duration Start Finish Site Layout Site Layout 235 27-May-15 10-Jan-16 Electrical Sy Electrical Systems 196 27-May-15 02-Dec-15 Tunnel Mediu Tunnel Medium Voltage Network 22 12-Nov-15 02-Dec-15 ZB4LEBEPS5GROUND FLOOR MV NETWORK LAYOUT PLAN SUBMITTAL 10 12-Nov-15 25-Nov-15 ZB4LEBEPA GROUND FLOOR MV NETWORK LAYOUT PLAN APPROVAL 5 26-Nov-15 02-Dec-15 Tunnel Low V Tunnel Low Voltage Network 52 27-May-15 14-Jul-15 ZB4LEBELS5 GROUND FLOOR LV NETWORK LAYOUT PLAN SUBMITTAL 25 27-May-15 30-Jun-15 ZB4LEBELAGROUND FLOOR LV NETWORK LAYOUT PLAN APPROVAL 10 01-Jul-15 14-Jul-15 Power Syste Power System 52 06-Sep-15 28-Oct-15 ZB4LEBEPS4GROUND FLOOR POWER SYSTEM LAYOUT PLAN SUBMITTAL 25 06-Sep-15 13-Oct-15 ZB4LEBEPA GROUND FLOOR POWER SYSTEM LAYOUT PLAN APPROVAL 10 15-Oct-15 28-Oct-15 Lighting Sys Lighting System 44 26-Jul-15 03-Sep-15 ZB4LEBELS3 GROUND FLOOR LIGHTING SYSTEM LAYOUT PLAN SUBMITTAL 25 26-Jul-15 27-Aug-15 ZB4LEBELAGROUND FLOOR LIGHTING SYSTEM LAYOUT PLAN APPROVAL 5 30-Aug-15 03-Sep-15 SCADA Syste SCADA System 15 20-Sep-15 05-Oct-15 ZB4LEBEDS GROUND FLOOR SCADA SYSTEM LAYOUT PLAN SUBMITTAL 5 20-Sep-15 28-Sep-15 ZB4LEBEDAGROUND FLOOR SCADA SYSTEM LAYOUT PLAN APPROVAL 5 29-Sep-15 05-Oct-15 Composite D Composite Drawing 22 03-Dec-15 24-Dec-15 ZB4LEBCS30 SITE LAY OUT COMPOSITE LAYOUT PLAN SUBMITTAL 10 03-Dec-15 16-Dec-15 ZB4LEBCA30 SITE LAY OUT COMPOSITE LAYOUT PLAN APPROVAL 5 17-Dec-15 24-Dec-15 General Sho General Shop Drawings 190 08-Jul-15 10-Jan-16 Electrical Sys Electrical Systems 190 08-Jul-15 10-Jan-16 ZB4LETEGS ELECTRICAL INSTALLATION DETAILS SUBMITTAL 25 26-Jul-15 27-Aug-15 ZB4LETEGAELECTRICAL INSTALLATION DETAILS APPROVAL 5 30-Aug-15 03-Sep-15 Power Syste Power System 15 27-Dec-15 10-Jan-16 ZB4LETEPPOWER S.L.D AND PANEL BOARD SCHEDULE SUBMITTAL 5 27-Dec-15 31-Dec-15 ZB4LETEPPOWER S.L.D AND PANEL BOARD SCHEDULE APPROVAL 5 03-Jan-16 10-Jan-16 Lighting Sys Lighting System 37 08-Jul-15 13-Aug-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 2015 2016 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 23 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 24. Activity ID Activity Name Original Duration Start Finish ZB4LETELLIGHTING FIXTURE SCHEDULE SUBMITTAL 10 08-Jul-15 22-Jul-15 ZB4LETELLIGHTING FIXTURE SCHEDULE APPROVAL 5 26-Jul-15 30-Jul-15 ZB4LETELLIGHTING FIXTURES DETAILS ON STREET SECTIONS SUBMITTAL 10 26-Jul-15 06-Aug-15 ZB4LETELLIGHTING FIXTURES DETAILS ON STREET SECTIONS APPROVAL 5 09-Aug-15 13-Aug-15 SCADA Sys SCADA System 52 13-Sep-15 04-Nov-15 ZB4LETEDSCADA SYSTEM HAND HOLE LAYOUT SUBMITTAL 25 13-Sep-15 21-Oct-15 ZB4LETEDSCADA SYSTEM HAND HOLE LAYOUTAPPROVAL 10 22-Oct-15 04-Nov-15 Materials Materials 322 27-May-15 02-Apr-16 Building B4 - Building B4 - A (Mechanical Utilities) 292 27-May-15 05-Mar-16 Electrical Sy Electrical Systems 285 03-Jun-15 05-Mar-16 Power Syste Power System 285 03-Jun-15 05-Mar-16 Material Subm Material Submittal 144 03-Jun-15 21-Oct-15 ZB4EEMS080EMT Material Submittal 10 03-Jun-15 16-Jun-15 ZB4EEMS090IMC Material Submittal 10 03-Jun-15 16-Jun-15 ZB4EEMS040Cable Trays and Ladders Material Submittal 10 10-Jun-15 23-Jun-15 ZB4EEMS110B4-A Building ERMU Material Submittal 10 21-Jul-15 04-Aug-15 ZB4EEMS050LV Cables Fire Resistant Material Submittal 20 08-Jul-15 06-Aug-15 ZB4EEMS030LV Cables Material Submittal 7 16-Aug-15 24-Aug-15 ZB4EEMS180B4-A Building MCC's Material Submittal 10 12-Aug-15 25-Aug-15 ZB4EEMS120B4-A Building Transformers Material Submittal 20 02-Aug-15 27-Aug-15 ZB4EEMS100B4-A Building UPS Material Submittal 20 09-Aug-15 03-Sep-15 ZB4EEMS070MV Cables Material Submittal 7 30-Aug-15 07-Sep-15 ZB4EEMS150B4-A Building EMDB & EDB Material Submittal 10 30-Aug-15 10-Sep-15 ZB4EEMS160B4-A Building Distribution Panels Material Submittal 10 30-Aug-15 10-Sep-15 ZB4EEMS170B4-A Building Bus Bar Material Submittal 10 30-Aug-15 10-Sep-15 ZB4EEMS060LV Earthing Cables Material Submittal 20 23-Aug-15 17-Sep-15 ZB4EEMS130Disconnecting Switch Material Submittal 20 23-Aug-15 17-Sep-15 ZB4EEMS140Wiring Devices Material Submittal 20 23-Aug-15 17-Sep-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 2015 2016 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 24 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 25. Activity ID Activity Name Original Duration Start Finish ZB4EEMS190B4-A Building VSD Material Submittal 20 20-Sep-15 21-Oct-15 ZB4EEMS200B4-A Building Soft Starter Material Submittal 20 20-Sep-15 21-Oct-15 Material Appr Material Approvals 136 17-Jun-15 28-Oct-15 ZB4EEMA08 EMT Material Approval 5 17-Jun-15 23-Jun-15 ZB4EEMA09 IMC Material Approval 5 17-Jun-15 23-Jun-15 ZB4EEMA04 Cable Trays and Ladders Material Approval 5 24-Jun-15 30-Jun-15 ZB4EEMA110 B4-A Building ERMU Material Approval 5 05-Aug-15 11-Aug-15 ZB4EEMA05 LV Cables Fire Resistant Material Approval 5 09-Aug-15 13-Aug-15 ZB4EEMA03 LV Cables Material Approval 5 25-Aug-15 31-Aug-15 ZB4EEMA18 B4-A Building MCC's Material Approval 5 26-Aug-15 01-Sep-15 ZB4EEMA12 B4-A Building Transformers Material Approval 5 30-Aug-15 03-Sep-15 ZB4EEMA10 B4-A Building UPS Material Approval 5 06-Sep-15 10-Sep-15 ZB4EEMA07 MV Cables Material Approval 5 08-Sep-15 14-Sep-15 ZB4EEMA15 B4-A Building EMDB & EDB Material Approval 5 13-Sep-15 17-Sep-15 ZB4EEMA16 B4-A Building Distribution Panels Material Approval 5 13-Sep-15 17-Sep-15 ZB4EEMA17 B4-A Building Bus Bar Material Approval 5 13-Sep-15 17-Sep-15 ZB4EEMA06 LV Earthing Cables Material Approval 5 20-Sep-15 28-Sep-15 ZB4EEMA13 Disconnecting Switch Material Approval 5 20-Sep-15 28-Sep-15 ZB4EEMA14 Wiring Devices Material Approval 5 20-Sep-15 28-Sep-15 ZB4EEMA19 B4-A Building VSD Material Approval 5 22-Oct-15 28-Oct-15 ZB4EEMA20 B4-A Building Soft Starter Material Approval 5 22-Oct-15 28-Oct-15 Material PO's Material PO's 170 01-Jul-15 13-Dec-15 ZB4EEMP080EMT Material PO 5 01-Jul-15 07-Jul-15 ZB4EEMP090IMC Material PO 5 01-Jul-15 07-Jul-15 ZB4EEMP040Cable Trays and Ladders Material PO 10 15-Jul-15 30-Jul-15 ZB4EEMP110B4-A Building ERMU Material PO 10 12-Aug-15 25-Aug-15 ZB4EEMP030LV Cables Material PO 10 01-Sep-15 14-Sep-15 ZB4EEMP180B4-A Building MCC's Material PO 10 02-Sep-15 15-Sep-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 2015 2016 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 25 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 26. Activity ID Activity Name Original Duration Start Finish ZB4EEMP050LV Cables Fire Resistant Material PO 10 06-Sep-15 17-Sep-15 ZB4EEMP030Power Circuits Cables and Wires PO 5 13-Sep-15 17-Sep-15 ZB4EEMP150B4-A Building EMDB & EDB Material PO 10 20-Sep-15 05-Oct-15 ZB4EEMP160B4-A Building Distribution Panels Material PO 10 20-Sep-15 05-Oct-15 ZB4EEMP170B4-A Building Bus Bar Material PO 10 20-Sep-15 05-Oct-15 ZB4EEMP130Disconnecting Switch Material PO 10 29-Sep-15 13-Oct-15 ZB4EEMP140Wiring Devices Material PO 10 29-Sep-15 13-Oct-15 ZB4EEMP120B4-A Building Transformers Material PO 10 11-Oct-15 25-Oct-15 ZB4EEMP100B4-A Building UPS Material PO 10 19-Oct-15 01-Nov-15 ZB4EEMP070MV Cables Material PO 10 21-Oct-15 03-Nov-15 ZB4EEMP060LV Earthing Cables Material PO 10 02-Nov-15 15-Nov-15 ZB4EEMP190B4-A Building VSD Material PO 10 30-Nov-15 13-Dec-15 ZB4EEMP200B4-A Building Soft Starter Material PO 10 30-Nov-15 13-Dec-15 Material Deliv Material Delivery at Site 247 08-Jul-15 05-Mar-16 ZB4EEMD08 EMT Material Delivery 10 08-Jul-15 20-Jul-15 ZB4EEMD09 IMC Material Delivery 10 08-Jul-15 20-Jul-15 ZB4EEMD03 Power Circuits Cables and Wires Partial Delivery 52 19-Sep-15 22-Nov-15 ZB4EEMD03 LV Cables Material Delivery 60 15-Sep-15 28-Nov-15 ZB4EEMD110 B4-A Building ERMU Material Delivery 78 26-Aug-15 29-Nov-15 ZB4EEMD18 B4-A Building MCC's Material Delivery 70 16-Sep-15 10-Dec-15 ZB4EEMD16 B4-A Building Distribution Panels Material Delivery 60 07-Oct-15 16-Dec-15 ZB4EEMD04 Cable Trays and Ladders Material Partial Delivery 120 01-Aug-15 22-Dec-15 ZB4EEMD12 B4-A Building Transformers Material Delivery 60 26-Oct-15 04-Jan-16 ZB4EEMD05 LV Cables Fire Resistant Material Delivery 90 19-Sep-15 06-Jan-16 ZB4EEMD15 B4-A Building EMDB & EDB Material Delivery 78 07-Oct-15 09-Jan-16 ZB4EEMD17 B4-A Building Bus Bar Material Delivery 78 07-Oct-15 09-Jan-16 ZB4EEMD07 MV Cables Material Delivery 60 04-Nov-15 14-Jan-16 ZB4EEMD13 Disconnecting Switch Material Delivery 78 15-Oct-15 16-Jan-16 Q2 Q3 Q4 Q1 Q2 Q3 Q4 2015 2016 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 26 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 27. Activity ID Activity Name Original Duration Start Finish ZB4EEMD14 Wiring Devices Material Delivery 78 15-Oct-15 16-Jan-16 ZB4EEMD06 LV Earthing Cables Material Partial Delivery 60 16-Nov-15 27-Jan-16 ZB4EEMD19 B4-A Building VSD Material Delivery 60 14-Dec-15 24-Feb-16 ZB4EEMD20 B4-A Building Soft Starter Material Delivery 60 14-Dec-15 24-Feb-16 ZB4EEMD10 B4-A Building UPS Material Delivery 104 02-Nov-15 05-Mar-16 Lighting Sys Lighting System 157 16-Aug-15 16-Jan-16 Material Subm Material Submittal 36 16-Aug-15 17-Sep-15 ZB4EEMS210B4 Buildings Lighting Fixtures Material Submittal 20 16-Aug-15 10-Sep-15 ZB4EEMS220B4 Buildings CENTRAL MONITORING SYSTEM Material Submittal 20 16-Aug-15 10-Sep-15 ZB4EEMS230B4 Buildings KNX/EIP SYSTEM Material Submittal 20 23-Aug-15 17-Sep-15 Material Appr Material Approvals 22 13-Sep-15 05-Oct-15 ZB4EEMA21 B4 Buildings Lighting Fixtures Material Approval 10 13-Sep-15 28-Sep-15 ZB4EEMA22 B4 Buildings CENTRAL MONITORING SYSTEM Material Approval 10 13-Sep-15 28-Sep-15 ZB4EEMA23 B4 Buildings KNX/EIP SYSTEM Material Approval 10 20-Sep-15 05-Oct-15 Material PO's Material PO's 52 13-Sep-15 04-Nov-15 ZB4EEMP240B4A Building Lighting Wires Material PO 10 13-Sep-15 28-Sep-15 ZB4EEMP210B4A Building Lighting Fixtures Material PO 10 08-Oct-15 22-Oct-15 ZB4EEMP220B4A Building CENTRAL MONITORING SYSTEM Material PO 10 15-Oct-15 28-Oct-15 ZB4EEMP230B4A Building KNX/EIP SYSTEM Material PO 10 22-Oct-15 04-Nov-15 Material Deliv Material Delivery at Site 112 29-Sep-15 16-Jan-16 ZB4EEMD24 B4A Building Lighting Wires Material Partial Delivery 10 29-Sep-15 11-Oct-15 ZB4EEMD21 B4A Building Lighting Fixtures Material Delivery 45 24-Oct-15 14-Dec-15 ZB4EEMD22 B4A Building CENTRAL MONITORING SYSTEM Material Delivery 65 29-Oct-15 14-Jan-16 ZB4EEMD23 B4A Building KNX/EIP SYSTEM Material Delivery 60 05-Nov-15 16-Jan-16 Cable Tray S Cable Tray System 179 15-Jul-15 05-Jan-16 Material PO's Material PO's 91 15-Jul-15 13-Oct-15 ZB4EEMP250Cable Trays and Ladders For Equipments Material PO 10 15-Jul-15 30-Jul-15 ZB4EEMP260LV Cables For Equipments Material PO 10 01-Sep-15 14-Sep-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 2015 2016 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 27 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 28. Activity ID Activity Name Original Duration Start Finish ZB4EEMP270LV Earthing For Equipments Cables Material PO 10 29-Sep-15 13-Oct-15 Material Deliv Material Delivery at Site 164 01-Aug-15 05-Jan-16 ZB4EEMD25 Cable Trays and Ladders Material Delivery 10 01-Aug-15 11-Aug-15 ZB4EEMD26 LV Cables Material Delivery 60 15-Sep-15 28-Nov-15 ZB4EEMD27 LV Earthing Cables Material Delivery 70 15-Oct-15 05-Jan-16 Earthing Sys Earthing System 206 10-Jun-15 27-Dec-15 Material Subm Material Submittal 30 10-Jun-15 07-Jul-15 ZB4EEMS010Earthing System Material Submittal 20 10-Jun-15 07-Jul-15 Material Appr Material Approvals 15 08-Jul-15 22-Jul-15 ZB4EEMA01 Earthing System Material Approval 10 08-Jul-15 22-Jul-15 Material PO's Material PO's 15 25-Aug-15 07-Sep-15 ZB4EEMP010Earthing System Material PO 10 25-Aug-15 07-Sep-15 Material Deliv Material Delivery at Site 112 08-Sep-15 27-Dec-15 ZB4EEMD01 Earthing System Material Delivery 90 08-Sep-15 27-Dec-15 Lightning Sy Lightning System 205 10-Jun-15 26-Dec-15 Material Subm Material Submittal 30 10-Jun-15 07-Jul-15 ZB4EEMS020LIGHTNING System Material Submittal 20 10-Jun-15 07-Jul-15 Material Appr Material Approvals 15 08-Jul-15 22-Jul-15 ZB4EEMA02 LIGHTNING System Material Approval 10 08-Jul-15 22-Jul-15 Material PO's Material PO's 14 09-Aug-15 20-Aug-15 ZB4EEMP020LIGHTNING System Material PO 10 09-Aug-15 20-Aug-15 Material Deliv Material Delivery at Site 130 22-Aug-15 26-Dec-15 ZB4EEMD02 LIGHTNING System Material Delivery 104 22-Aug-15 26-Dec-15 Light Curren Light Current Systems 156 26-Jul-15 22-Dec-15 Fire Alarm Sy Fire Alarm System 156 26-Jul-15 22-Dec-15 Material Sub Material Submittal 29 26-Jul-15 20-Aug-15 ZB4EEMS2Fire Alarm System Material Submittal 20 26-Jul-15 20-Aug-15 Material App Material Approvals 14 23-Aug-15 03-Sep-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 2015 2016 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 28 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 29. Activity ID Activity Name Original Duration Start Finish ZB4EEMA2Fire Alarm System Material Approval 10 23-Aug-15 03-Sep-15 Material PO' Material PO's 14 06-Sep-15 17-Sep-15 ZB4EEMP2Fire Alarm System Devices Material PO 10 06-Sep-15 17-Sep-15 ZB4EEMP2Fire Alarm System Fire Alarm Cable Material PO 10 06-Sep-15 17-Sep-15 ZB4EEMP3Fire Alarm System FACP Material PO 10 06-Sep-15 17-Sep-15 Material Del Material Delivery at Site 97 19-Sep-15 22-Dec-15 ZB4EEMD2Fire Alarm System Devices Material Delivery 78 19-Sep-15 22-Dec-15 ZB4EEMD2Fire Alarm System Fire Alarm Cable Material Delivery 78 19-Sep-15 22-Dec-15 ZB4EEMD3Fire Alarm System FACP Material Delivery 78 19-Sep-15 22-Dec-15 SCADA Sys SCADA System 120 05-Nov-15 28-Feb-16 Material Subm Material Submittal 7 05-Nov-15 11-Nov-15 ZB4EEMS250SCADA System Material Submittal 5 05-Nov-15 11-Nov-15 Material Appr Material Approvals 7 12-Nov-15 18-Nov-15 ZB4EEMA25 SCADA System Material Approval 5 12-Nov-15 18-Nov-15 Material PO's Material PO's 7 19-Nov-15 25-Nov-15 ZB4EEMP310SCADA System Material PO 5 19-Nov-15 25-Nov-15 Material Deliv Material Delivery at Site 97 26-Nov-15 28-Feb-16 ZB4EEMD31 SCADA System Material Delivery 78 26-Nov-15 28-Feb-16 Mechanical Mechanical Systems 265 27-May-15 08-Feb-16 HVAC Syste HVAC System 260 27-May-15 04-Feb-16 Material Subm Material Submittal 155 27-May-15 25-Oct-15 ZB4EEMS390Black welded (ERW) steel piping Material Submittal 5 01-Jun-15 07-Jun-15 ZB4EEMS440Variable Air Volume (VAV) Boxes Material Submittal 15 27-May-15 16-Jun-15 ZB4EEMS260Chillers Material Submittal 12 04-Jun-15 21-Jun-15 ZB4EEMS270Cooling Towers Material Submittal 10 28-Jun-15 09-Jul-15 ZB4EEMS310AHU Material Submittal 12 28-Jun-15 13-Jul-15 ZB4EEMS410Chilled Water Valves Material Submittal 22 14-Jun-15 13-Jul-15 ZB4EEMS380Child pipe hangers and support Material Submittal 15 28-Jun-15 19-Jul-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 2015 2016 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 29 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 30. Activity ID Activity Name Original Duration Start Finish ZB4EEMS280Child Water Pumps Material Submittal 22 02-Jul-15 04-Aug-15 ZB4EEMS315Expansion Tanks Material Submittal 12 19-Jul-15 04-Aug-15 ZB4EEMS370Black seamless steel piping Material Submittal 15 19-Jul-15 09-Aug-15 ZB4EEMS300Heat Exchangers Material Submittal 22 08-Jul-15 10-Aug-15 ZB4EEMS320Metal Sheet Duct Material Submittal 15 26-Jul-15 13-Aug-15 ZB4EEMS400UPVC piping (16 bar) Material Submittal 22 26-Jul-15 24-Aug-15 ZB4EEMS340Chimney Black Steel Sheet Material Sample Submittal 18 02-Aug-15 25-Aug-15 ZB4EEMS330FD & VD Material Submittal 22 02-Aug-15 31-Aug-15 ZB4EEMS350Fire Smoke Dampers Material Submittal 22 09-Aug-15 07-Sep-15 ZB4EEMS360Duct Insulation Material Submittal 22 11-Aug-15 09-Sep-15 ZB4EEMS430Air Separators Material Submittal 22 16-Aug-15 14-Sep-15 ZB4EEMS420Chilled Water Piping Insulation Material Submittal 22 23-Aug-15 21-Sep-15 ZB4EEMS450Air Outlets Material Submittal 22 30-Aug-15 30-Sep-15 ZB4EEMS460Water Treatment and Chemical Cleaning System Material Submittal 22 06-Sep-15 08-Oct-15 ZB4EEMS470Over Head Crane Material Submittal 22 06-Sep-15 08-Oct-15 ZB4EEMS480Monorail Crane Material Submittal 22 06-Sep-15 08-Oct-15 ZB4EEMS290Testing, Balancing & Commisioning system Third Part Submittal 22 20-Sep-15 25-Oct-15 Material Appr Material Approvals 150 08-Jun-15 01-Nov-15 ZB4EEMA39 Black welded (ERW) steel piping Material Approval 5 08-Jun-15 14-Jun-15 ZB4EEMA44 Variable Air Volume (VAV) Boxes Material Approval 5 17-Jun-15 23-Jun-15 ZB4EEMA26 Chillers System Material Approval 5 22-Jun-15 28-Jun-15 ZB4EEMA27 Cooling Towers System Material Approval 5 12-Jul-15 19-Jul-15 ZB4EEMA31 AHU System Material Approval 5 14-Jul-15 21-Jul-15 ZB4EEMA41 Chilled Water Valves Material Approval 5 14-Jul-15 21-Jul-15 ZB4EEMA38 Child pipe hangers and support Material Approval 5 20-Jul-15 27-Jul-15 ZB4EEMA28 Child Water Pumps Material Approval 5 05-Aug-15 11-Aug-15 ZB4EEMA31 Expansion Tanks Material Approval 5 05-Aug-15 11-Aug-15 ZB4EEMA37 Black seamless steel piping Material Approval 5 10-Aug-15 16-Aug-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 2015 2016 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 30 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 31. Activity ID Activity Name Original Duration Start Finish ZB4EEMA30 Heat Exchangers System Material Approval 5 11-Aug-15 17-Aug-15 ZB4EEMA32 Metal Sheet Duct System Material Approval 5 16-Aug-15 20-Aug-15 ZB4EEMA40 UPVC piping (16 bar) Material Approval 5 25-Aug-15 31-Aug-15 ZB4EEMA34 Chimney Black Steel Sheet Material Sample Approval 5 26-Aug-15 01-Sep-15 ZB4EEMA33 FD & VD Material Approval 5 01-Sep-15 07-Sep-15 ZB4EEMA35 Fire Smoke Dampers Material Approval 5 08-Sep-15 14-Sep-15 ZB4EEMA36 Duct Insulation Material Approval 5 10-Sep-15 16-Sep-15 ZB4EEMA43 Air Separators Material Approval 5 15-Sep-15 21-Sep-15 ZB4EEMA42 Chilled Water Piping Insulation Material Approval 5 22-Sep-15 30-Sep-15 ZB4EEMA45 Air Outlets Material Approval 5 01-Oct-15 08-Oct-15 ZB4EEMA46 Water Treatment and Chemical Cleaning System Material Approval 5 11-Oct-15 18-Oct-15 ZB4EEMA47 Over Head Crane Material Approval 5 11-Oct-15 18-Oct-15 ZB4EEMA48 Monorail Crane Material Approval 5 11-Oct-15 18-Oct-15 ZB4EEMA29 Testing, Balancing & Commisioning system Third Part Approval 5 26-Oct-15 01-Nov-15 Material PO's Material PO's 142 15-Jun-15 01-Nov-15 ZB4EEMP450Black welded (ERW) steel piping Material PO 10 15-Jun-15 28-Jun-15 ZB4EEMP320Chillers System Material PO 10 29-Jun-15 12-Jul-15 ZB4EEMP330Cooling Towers System Material PO 10 20-Jul-15 03-Aug-15 ZB4EEMP370AHU System Material PO 10 22-Jul-15 05-Aug-15 ZB4EEMP470Chilled Water Valves Material PO 10 22-Jul-15 05-Aug-15 ZB4EEMP440Child pipe hangers and support Material PO 10 28-Jul-15 10-Aug-15 ZB4EEMP500Variable Air Volume (VAV) Boxes Material PO 10 28-Jul-15 10-Aug-15 ZB4EEMP340Child Water Pumps Material PO 10 12-Aug-15 25-Aug-15 ZB4EEMP315Expansion Tanks Material PO 10 12-Aug-15 25-Aug-15 ZB4EEMP430Black seamless steel piping Material PO 10 17-Aug-15 30-Aug-15 ZB4EEMP360Heat Exchangers System Material PO 10 18-Aug-15 31-Aug-15 ZB4EEMP380Metal Sheet Duct System Material PO 10 23-Aug-15 03-Sep-15 ZB4EEMP460UPVC piping (16 bar) Material PO 10 01-Sep-15 14-Sep-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 2015 2016 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 31 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 32. Activity ID Activity Name Original Duration Start Finish ZB4EEMP390FD & VD Material PO 10 08-Sep-15 21-Sep-15 ZB4EEMP410Fire Smoke Dampers Material PO 10 15-Sep-15 30-Sep-15 ZB4EEMP420Duct Insulation Material PO 10 17-Sep-15 04-Oct-15 ZB4EEMP490Air Separators Material PO 10 22-Sep-15 08-Oct-15 ZB4EEMP480Chilled Water Piping Insulation Material PO 10 01-Oct-15 18-Oct-15 ZB4EEMP400Chimney Black Steel Sheet Material PO 10 07-Oct-15 21-Oct-15 ZB4EEMP510Air Outlets Material PO 10 11-Oct-15 25-Oct-15 ZB4EEMP520Water Treatment and Chemical Cleaning System Material PO 10 19-Oct-15 01-Nov-15 ZB4EEMP530Over Head Crane Material PO 10 19-Oct-15 01-Nov-15 ZB4EEMP540Monorail Crane Material PO 10 19-Oct-15 01-Nov-15 Material Deliv Material Delivery at Site 225 29-Jun-15 04-Feb-16 ZB4EEMD44 Child pipe hangers and support Material ( Partial )Delivery 36 11-Aug-15 21-Sep-15 ZB4EEMD45 Black welded (ERW) steel piping Material ( Partial )Delivery 104 29-Jun-15 03-Nov-15 ZB4EEMD33 Cooling Towers System Material Delivery 78 04-Aug-15 07-Nov-15 ZB4EEMD37 AHU System Material Delivery 78 06-Aug-15 09-Nov-15 ZB4EEMD32 Chillers Material Delivery 104 13-Jul-15 17-Nov-15 ZB4EEMD38 Metal Sheet Duct System Partial Material Delivery / Fabrication 65 05-Sep-15 23-Nov-15 ZB4EEMD31 Expansion Tanks Material Delivery 78 26-Aug-15 29-Nov-15 ZB4EEMD43 Black seamless steel piping Material ( Partial )Delivery 78 31-Aug-15 03-Dec-15 ZB4EEMD42 Duct Insulation Material Delivery 52 05-Oct-15 06-Dec-15 ZB4EEMD47 Chilled Water Valves Material ( Partial )Delivery 104 06-Aug-15 09-Dec-15 ZB4EEMD40 Chimney Material Fabrication / Delivery 45 22-Oct-15 13-Dec-15 ZB4EEMD50 Variable Air Volume (VAV) Boxes Material Delivery 104 11-Aug-15 14-Dec-15 ZB4EEMD36 Heat Exchangers System Material Delivery 90 01-Sep-15 19-Dec-15 ZB4EEMD46 UPVC piping (16 bar) Material ( Partial )Delivery 78 15-Sep-15 19-Dec-15 ZB4EEMD39 FD & VD Material Delivery 80 22-Sep-15 29-Dec-15 ZB4EEMD34 Child Water Pumps Material Delivery 104 26-Aug-15 30-Dec-15 ZB4EEMD41 Fire Smoke Dampers Material Delivery 78 01-Oct-15 03-Jan-16 Q2 Q3 Q4 Q1 Q2 Q3 Q4 2015 2016 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 32 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 33. Activity ID Activity Name Original Duration Start Finish ZB4EEMD52 Water Treatment and Chemical Cleaning System Material Delivery On Site 60 02-Nov-15 12-Jan-16 ZB4EEMD48 Chilled Water Piping Insulation Material ( Partial ) Delivery 75 19-Oct-15 16-Jan-16 ZB4EEMD54 Monorail Crane Material Delivery On Site 65 02-Nov-15 18-Jan-16 ZB4EEMD49 Air Separators Material Delivery 90 10-Oct-15 26-Jan-16 ZB4EEMD51 Air Outlets Material Delivery 78 26-Oct-15 27-Jan-16 ZB4EEMD53 Over Head Crane Material Delivery On Site 78 02-Nov-15 03-Feb-16 ZB4EEMD35 Testing, Balancing & Commisioning system Third Part On Site 0 04-Feb-16 Fire Protect Fire Protection Systems 245 27-May-15 19-Jan-16 Material Subm Material Submittal 157 27-May-15 27-Oct-15 ZB4EEMS560Black Seamless Schedule 40 Material Submittal 10 27-May-15 09-Jun-15 ZB4EEMS580Electrical Fire Pump Material Submittal 15 27-May-15 16-Jun-15 ZB4EEMS590Diesel Fire Pump Material Submittal 15 27-May-15 16-Jun-15 ZB4EEMS600Jockey Pump Material Submittal 15 27-May-15 16-Jun-15 ZB4EEMS570VALVES Material Submittal 10 22-Jun-15 05-Jul-15 ZB4EEMS610Water Flow Switches Material Submittal 18 22-Jun-15 15-Jul-15 ZB4EEMS620Upright Sprinkler Heads Material Submittal 18 08-Jul-15 04-Aug-15 ZB4EEMS640Fire Hose Stations Material Submittal 22 02-Aug-15 31-Aug-15 ZB4EEMS650Dry Powder Manual Fire Extinguishers Material Submittal 22 23-Aug-15 21-Sep-15 ZB4EEMS670Roof Manifold Material Submittal 22 23-Aug-15 21-Sep-15 ZB4EEMS630CO2 System Material Submittal 12 11-Oct-15 27-Oct-15 ZB4EEMS660Automatic Dry Powder Fire Extinguishers Material Submittal 12 11-Oct-15 27-Oct-15 Material Appr Material Approvals 150 10-Jun-15 03-Nov-15 ZB4EEMA56 Black Seamless Schedule 40 Material Approval 5 10-Jun-15 16-Jun-15 ZB4EEMA58 Electrical Fire Pump Material Approval 5 17-Jun-15 23-Jun-15 ZB4EEMA59 Diesel Fire Pump Material Approval 5 17-Jun-15 23-Jun-15 ZB4EEMA60 Jockey Pump Material Approval 5 17-Jun-15 23-Jun-15 ZB4EEMA57 VALVES Material Approval 5 06-Jul-15 12-Jul-15 ZB4EEMA61 Water Flow Switches Material Approval 5 19-Jul-15 26-Jul-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 2015 2016 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 33 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 34. Activity ID Activity Name Original Duration Start Finish ZB4EEMA62 Upright Sprinkler Heads Material Approval 5 05-Aug-15 11-Aug-15 ZB4EEMA64 Fire Hose Stations Material Approval 5 01-Sep-15 07-Sep-15 ZB4EEMA65 Dry Powder Manual Fire Extinguishers Material Approval 5 22-Sep-15 30-Sep-15 ZB4EEMA67 Roof Manifold Material Approval 5 22-Sep-15 30-Sep-15 ZB4EEMA63 CO2 System Material Approval 5 28-Oct-15 03-Nov-15 ZB4EEMA66 Automatic Dry Powder Fire Extinguishers Material Approval 5 28-Oct-15 03-Nov-15 Material PO's Material PO's 157 17-Jun-15 17-Nov-15 ZB4EEMP560Black Seamless Schedule 40 Material PO 10 17-Jun-15 30-Jun-15 ZB4EEMP580Electrical Fire Pump Material PO 10 24-Jun-15 07-Jul-15 ZB4EEMP590Diesel Fire Pump Material PO 10 24-Jun-15 07-Jul-15 ZB4EEMP600Jockey Pump Material PO 10 24-Jun-15 07-Jul-15 ZB4EEMP570VALVES Material PO 10 13-Jul-15 28-Jul-15 ZB4EEMP610Water Flow Switches Material PO 10 27-Jul-15 09-Aug-15 ZB4EEMP620Upright Sprinkler Heads Material PO 10 12-Aug-15 25-Aug-15 ZB4EEMP640Fire Hose Stations Material PO 10 08-Sep-15 21-Sep-15 ZB4EEMP650Dry Powder Manual Fire Extinguishers Material PO 10 01-Oct-15 18-Oct-15 ZB4EEMP670Roof Manifold Material PO 10 01-Oct-15 18-Oct-15 ZB4EEMP630CO2 System Material PO 10 04-Nov-15 17-Nov-15 ZB4EEMP660Automatic Dry Powder Fire Extinguishers Material PO 10 04-Nov-15 17-Nov-15 Material Deliv Material Delivery at Site 207 01-Jul-15 19-Jan-16 ZB4EEMD56 Black Seamless Schedule 40 Material Partial Delivery 52 01-Jul-15 01-Sep-15 ZB4EEMD57 VALVES Material Delivery 52 29-Jul-15 29-Sep-15 ZB4EEMD61 Water Flow Switches Material Delivery 78 10-Aug-15 12-Nov-15 ZB4EEMD62 Upright Sprinkler Heads Material Delivery 78 26-Aug-15 29-Nov-15 ZB4EEMD58 Electrical Fire Pump Material Delivery 130 08-Jul-15 13-Dec-15 ZB4EEMD59 Diesel Fire Pump Material Delivery 130 08-Jul-15 13-Dec-15 ZB4EEMD60 Jockey Pump Material Delivery 130 08-Jul-15 13-Dec-15 ZB4EEMD64 Fire Hose Stations Material Delivery 78 22-Sep-15 27-Dec-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 2015 2016 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 34 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 35. Activity ID Activity Name Original Duration Start Finish ZB4EEMD63 CO2 System Material Delivery 52 18-Nov-15 19-Jan-16 ZB4EEMD65 Dry Powder Manual Fire Extinguishers Material Delivery 78 19-Oct-15 19-Jan-16 ZB4EEMD66 Automatic Dry Powder Fire Extinguishers Material Delivery 52 18-Nov-15 19-Jan-16 ZB4EEMD67 Roof Manifold Material Delivery 78 19-Oct-15 19-Jan-16 Plumbing Sy Plumbing System 265 27-May-15 08-Feb-16 Material Subm Material Submittal 170 27-May-15 08-Nov-15 ZB4EEMS780Domestic Water Booster Pump Material Submittal 15 27-May-15 16-Jun-15 ZB4EEMS790Irrigation Water Booster Pump Material Submittal 15 27-May-15 16-Jun-15 ZB4EEMS800Water Circulating Pumps Material Submittal 15 27-May-15 16-Jun-15 ZB4EEMS810Submersible Waste Water Pump Material Submittal 15 27-May-15 16-Jun-15 ZB4EEMS680Pipes PPR (PN 20) Material Submittal 18 28-Jun-15 22-Jul-15 ZB4EEMS700Pipes UPVC (PN 10) Material Submittal 18 28-Jun-15 22-Jul-15 ZB4EEMS690Pipes HDPE (PN 10) Material Submittal 22 19-Jul-15 18-Aug-15 ZB4EEMS740Roof Drains Material Submittal 15 02-Aug-15 20-Aug-15 ZB4EEMS710Gate Valves Material Submittal 22 02-Aug-15 31-Aug-15 ZB4EEMS760Trench Drain Material Submittal 22 09-Aug-15 07-Sep-15 ZB4EEMS720Water Tank Accessories Material Submittal 22 16-Aug-15 14-Sep-15 ZB4EEMS770Hose Bibs Material Submittal 22 23-Aug-15 21-Sep-15 ZB4EEMS730Pump Room Accessories Material Submittal 22 07-Oct-15 08-Nov-15 ZB4EEMS750Heavy Duty Cast Iron Cover for Inspection Chamber Material Submittal 22 07-Oct-15 08-Nov-15 Material Appr Material Approvals 162 17-Jun-15 22-Nov-15 ZB4EEMA78 Domestic Water Booster Pump Material Approval 10 17-Jun-15 30-Jun-15 ZB4EEMA79 Irrigation Water Booster Pump Material Approval 10 17-Jun-15 30-Jun-15 ZB4EEMA80 Water Circulating Pumps Material Approval 10 17-Jun-15 30-Jun-15 ZB4EEMA81 Submersible Waste Water Pump Material Approval 10 17-Jun-15 30-Jun-15 ZB4EEMA68 Pipes PPR (PN 20) Material Approval 10 26-Jul-15 06-Aug-15 ZB4EEMA70 Pipes UPVC (PN 10) Material Approval 10 26-Jul-15 06-Aug-15 ZB4EEMA69 Pipes HDPE (PN 10) Material Approval 10 19-Aug-15 01-Sep-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 2015 2016 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 35 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 36. Activity ID Activity Name Original Duration Start Finish ZB4EEMA74 Roof Drains Material Approval 10 23-Aug-15 03-Sep-15 ZB4EEMA71 Gate Valves Material Approval 10 01-Sep-15 14-Sep-15 ZB4EEMA76 Trench Drain Material Approval 10 08-Sep-15 21-Sep-15 ZB4EEMA72 Water Tank Accessories Material Approval 10 15-Sep-15 30-Sep-15 ZB4EEMA77 Hose Bibs Material Approval 10 22-Sep-15 08-Oct-15 ZB4EEMA73 Pump Room Accessories Material Approval 10 09-Nov-15 22-Nov-15 ZB4EEMA75 Heavy Duty Cast Iron Cover for Inspection Chamber Material Approval 10 09-Nov-15 22-Nov-15 Material PO's Material PO's 162 01-Jul-15 06-Dec-15 ZB4EEMP780Domestic Water Booster Pump Material PO 10 01-Jul-15 14-Jul-15 ZB4EEMP790Irrigation Water Booster Pump Material PO 10 01-Jul-15 14-Jul-15 ZB4EEMP800Water Circulating Pumps Material PO 10 01-Jul-15 14-Jul-15 ZB4EEMP810Submersible Waste Water Pump Material PO 10 01-Jul-15 14-Jul-15 ZB4EEMP680Pipes PPR (PN 20) Material PO 10 09-Aug-15 20-Aug-15 ZB4EEMP700Pipes UPVC (PN 10) Material PO 10 09-Aug-15 20-Aug-15 ZB4EEMP690Pipes HDPE (PN 10) Material PO 10 02-Sep-15 15-Sep-15 ZB4EEMP740Roof Drains Material PO 10 06-Sep-15 17-Sep-15 ZB4EEMP710Gate Valves Material PO 10 15-Sep-15 30-Sep-15 ZB4EEMP760Trench Drain Material PO 10 22-Sep-15 08-Oct-15 ZB4EEMP720Water Tank Accessories Material PO 10 01-Oct-15 18-Oct-15 ZB4EEMP770Hose Bibs Material PO 10 11-Oct-15 25-Oct-15 ZB4EEMP730Pump Room Accessories Material PO 10 23-Nov-15 06-Dec-15 ZB4EEMP750Heavy Duty Cast Iron Cover for Inspection Chamber Material PO 10 23-Nov-15 06-Dec-15 Material Deliv Material Delivery at Site 212 15-Jul-15 08-Feb-16 ZB4EEMD74 Roof Drains Material Delivery 22 19-Sep-15 18-Oct-15 ZB4EEMD78 Domestic Water Booster Pump Material Delivery 104 15-Jul-15 19-Nov-15 ZB4EEMD79 Irrigation Water Booster Pump Material Delivery 104 15-Jul-15 19-Nov-15 ZB4EEMD80 Water Circulating Pumps Material Delivery 104 15-Jul-15 19-Nov-15 ZB4EEMD81 Submersible Waste Water Pump Material Delivery 104 15-Jul-15 19-Nov-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 2015 2016 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 36 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 37. Activity ID Activity Name Original Duration Start Finish ZB4EEMD68 Pipes PPR (PN 20) Material Partial Delivery 78 22-Aug-15 24-Nov-15 ZB4EEMD70 Pipes UPVC (PN 10) Material Partial Delivery 78 22-Aug-15 24-Nov-15 ZB4EEMD76 Trench Drain Material Delivery 52 10-Oct-15 09-Dec-15 ZB4EEMD71 Gate Valves Material Delivery 78 01-Oct-15 03-Jan-16 ZB4EEMD72 Water Tank Accessories Material Delivery 78 19-Oct-15 19-Jan-16 ZB4EEMD69 Pipes HDPE (PN 10) Material Delivery 104 16-Sep-15 21-Jan-16 ZB4EEMD73 Pump Room Accessories Material Delivery 40 07-Dec-15 24-Jan-16 ZB4EEMD77 Hose Bibs Material Delivery 78 26-Oct-15 27-Jan-16 ZB4EEMD75 Heavy Duty Cast Iron Cover for Inspection Chamber Material Delivery 52 07-Dec-15 08-Feb-16 Building B4 - Building B4 - B (Electrical Services) 271 24-Jun-15 13-Mar-16 Electrical Sy Electrical Systems 271 24-Jun-15 13-Mar-16 Power Syste Power System 271 24-Jun-15 13-Mar-16 Material Subm Material Submittal 82 02-Aug-15 21-Oct-15 ZB4EEMS500B4.B NRMU & B4.B-ERMU Material Submittal 10 02-Aug-15 13-Aug-15 ZB4EEMS520B4.B Distribution Transformers Material Submittal 10 02-Aug-15 13-Aug-15 ZB4EEMS510B4.B Medium Voltage Switch gear (22 KV) Material Submittal 10 09-Aug-15 20-Aug-15 ZB4EEMS490B4.B Building UPS Material Submittal 10 23-Aug-15 03-Sep-15 ZB4EEMS540B4.B Bus bar Trunking Material Submittal 10 23-Aug-15 03-Sep-15 ZB4EEMS820B4.B Emergency Diesel Generator Plant Material Submittal 10 23-Aug-15 03-Sep-15 ZB4EEMS830B4.B Paralleling and Synchronization Switch gear (22 KV) - EMV Material Submittal 10 06-Sep-15 17-Sep-15 ZB4EEMS550B4.B MCC Panels Material Submittal 10 20-Sep-15 05-Oct-15 ZB4EEMS530B4.B MDB, DB, EDB, LP, PP, ELP, EPP and UPP Material Submittal 5 15-Oct-15 21-Oct-15 Material Appr Material Approvals 75 16-Aug-15 28-Oct-15 ZB4EEMA50 B4.B-NRMU & B4.B-ERMU Material Approval 10 16-Aug-15 27-Aug-15 ZB4EEMA52 B4.B Distribution Transformers Material Approval 10 16-Aug-15 27-Aug-15 ZB4EEMA51 B4.B Medium Voltage Switch gear (22 KV) Material Approval 10 23-Aug-15 03-Sep-15 ZB4EEMA52 B4.C MDB Material Approval (By Others) 0 03-Sep-15 ZB4EEMA49 B4-B Building UPS Material Approval 10 06-Sep-15 17-Sep-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 2015 2016 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 37 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 38. Activity ID Activity Name Original Duration Start Finish ZB4EEMA54 B4.B Bus bar Trunking Material Approval 10 06-Sep-15 17-Sep-15 ZB4EEMA82 B4.B Emergency Diesel Generator Plant Material Approval 10 06-Sep-15 17-Sep-15 ZB4EEMA83 B4.B Paralleling and Synchronization Switch gear (22 KV) - EMV Material Approval 10 20-Sep-15 05-Oct-15 ZB4EEMA55 B4.B MCC Panels Material Approval 10 07-Oct-15 21-Oct-15 ZB4EEMA53 B4.B MDB, DB, EDB, LP, PP, ELP, EPP and UPP Material Approval 5 22-Oct-15 28-Oct-15 Material PO's Material PO's 159 24-Jun-15 25-Nov-15 ZB4EEMP350EMT Material PO 10 24-Jun-15 07-Jul-15 ZB4EEMP550IMC Material PO 10 24-Jun-15 07-Jul-15 ZB4EEMP920Cable Trays and Ladders Material PO 10 01-Jul-15 14-Jul-15 ZB4EEMP950LV Cables Fire Resistant Material PO 10 16-Aug-15 27-Aug-15 ZB4EEMP830B4.B-NRMU & B4.B-ERMU Material PO 10 30-Aug-15 10-Sep-15 ZB4EEMP850B4.B Distribution Transformers Material PO 10 30-Aug-15 10-Sep-15 ZB4EEMP940LV Cables Material PO 10 01-Sep-15 14-Sep-15 ZB4EEMP840B4.B Medium Voltage Switch gear (22 KV) Material PO 10 06-Sep-15 17-Sep-15 ZB4EEMP093Power Circuits Cables and Wires PO 10 13-Sep-15 28-Sep-15 ZB4EEMP970MV Cables Material PO 10 15-Sep-15 30-Sep-15 ZB4EEMP820B4-B Building UPS Material PO 10 20-Sep-15 05-Oct-15 ZB4EEMP870B4.B Bus bar Trunking Material PO 10 20-Sep-15 05-Oct-15 ZB4EEMP890B4.B Disconnecting Switches Material PO 10 29-Sep-15 13-Oct-15 ZB4EEMP960Wiring Devices Material PO 10 29-Sep-15 13-Oct-15 ZB4EEMP980LV Earthing Cables Material PO 10 29-Sep-15 13-Oct-15 ZB4EEMP910B4.B Paralleling and Synchronization Switch gear (22 KV) - EMV Material PO 10 07-Oct-15 21-Oct-15 ZB4EEMP860B4.B MDB, DB, EDB, LP, PP, ELP, EPP and UPP Material PO 5 29-Oct-15 04-Nov-15 ZB4EEMP880B4.B MCC Panels Material PO 10 22-Oct-15 04-Nov-15 ZB4EEMP900B4.B Emergency Diesel Generator Plant Material PO 10 12-Nov-15 25-Nov-15 Material Deliv Material Delivery at Site 256 08-Jul-15 13-Mar-16 ZB4EEMD55 EMT Material Delivery 10 08-Jul-15 20-Jul-15 ZB4EEMD92 IMC Material Delivery 10 08-Jul-15 20-Jul-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 2015 2016 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 38 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 39. Activity ID Activity Name Original Duration Start Finish ZB4EEMD09 Power Circuits Cables and Wires Partial Delivery 45 29-Sep-15 22-Nov-15 ZB4EEMD94 LV Cables Material Delivery 60 15-Sep-15 28-Nov-15 ZB4EEMD95 Cable Trays and Ladders Material Partial Delivery 120 15-Jul-15 08-Dec-15 ZB4EEMD97 MV Cables Material Partial Delivery 60 01-Oct-15 12-Dec-15 ZB4EEMD83 B4.B-NRMU & B4.B-ERMU Material Delivery 78 12-Sep-15 15-Dec-15 ZB4EEMD85 B4.B Distribution Transformers Material Delivery 78 12-Sep-15 15-Dec-15 ZB4EEMD96 LV Cables Fire Resistant Material Delivery 90 29-Aug-15 15-Dec-15 ZB4EEMD99 LV Earthing Cables Material Partial Delivery 60 15-Oct-15 24-Dec-15 ZB4EEMD88 B4.B MCC Panels Material Delivery 52 05-Nov-15 05-Jan-16 ZB4EEMD87 B4.B Bus bar Trunking Material Delivery 78 07-Oct-15 09-Jan-16 ZB4EEMD89 B4.B Disconnecting Switches Material Delivery 78 15-Oct-15 16-Jan-16 ZB4EEMD98 Wiring Devices Material Delivery 78 15-Oct-15 16-Jan-16 ZB4EEMD86 B4.B MDB, DB, EDB, LP, PP, ELP, EPP and UPP Material Delivery 65 05-Nov-15 21-Jan-16 ZB4EEMD91 B4.B Paralleling and Synchronization Switch gear (22 KV) - EMV Material Delivery 78 22-Oct-15 23-Jan-16 ZB4EEMD84 B4.B Medium Voltage Switch gear (22 KV) Material Delivery 104 19-Sep-15 24-Jan-16 ZB4EEMD82 B4-B Building UPS Material Delivery 104 07-Oct-15 09-Feb-16 ZB4EEMD90 B4.B Emergency Diesel Generator Plant Material Delivery 90 26-Nov-15 13-Mar-16 Lighting Sys Lighting System 112 13-Sep-15 31-Dec-15 Material PO's Material PO's 37 13-Sep-15 21-Oct-15 ZB4EEMP990B4B Building Lighting Wires Material PO 10 13-Sep-15 28-Sep-15 ZB4EEMP100B4B Building Lighting Fixtures Material PO 10 29-Sep-15 13-Oct-15 ZB4EEMP101B4B Building CENTRAL MONITORING SYSTEM Material PO 10 29-Sep-15 13-Oct-15 ZB4EEMP102B4B Building KNX/EIP SYSTEM Material PO 10 07-Oct-15 21-Oct-15 Material Deliv Material Delivery at Site 97 29-Sep-15 31-Dec-15 ZB4EEMD10 B4B Building Lighting Wires Material Partial Delivery 45 29-Sep-15 22-Nov-15 ZB4EEMD10 B4B Building Lighting Fixtures Material Delivery 45 15-Oct-15 06-Dec-15 ZB4EEMD10 B4B Building CENTRAL MONITORING SYSTEM Material Delivery 65 15-Oct-15 30-Dec-15 ZB4EEMD10 B4B Building KNX/EIP SYSTEM Material Delivery 60 22-Oct-15 31-Dec-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 2015 2016 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 39 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 40. Activity ID Activity Name Original Duration Start Finish Cable Tray S Cable Tray System 194 01-Jul-15 05-Jan-16 Material PO's Material PO's 106 01-Jul-15 13-Oct-15 ZB4EEMP103B4B Cable Trays and Ladders For Equipments Material PO 10 01-Jul-15 14-Jul-15 ZB4EEMP104B4B LV Cables For Equipments Material PO 10 01-Sep-15 14-Sep-15 ZB4EEMP105B4B LV Earthing For Equipments Cables Material PO 10 29-Sep-15 13-Oct-15 Material Deliv Material Delivery at Site 179 15-Jul-15 05-Jan-16 ZB4EEMD10 B4B Cable Trays and Ladders Material Delivery 10 15-Jul-15 28-Jul-15 ZB4EEMD10 B4B LV Cables Material Delivery 60 15-Sep-15 28-Nov-15 ZB4EEMD10 B4B LV Earthing Cables Material Delivery 70 15-Oct-15 05-Jan-16 Earthing Sys Earthing System 126 26-Jul-15 24-Nov-15 Material PO's Material PO's 14 26-Jul-15 06-Aug-15 ZB4EEMP106Earthing System Material PO 10 26-Jul-15 06-Aug-15 Material Deliv Material Delivery at Site 112 08-Aug-15 24-Nov-15 ZB4EEMD10 Earthing System Material Delivery 90 08-Aug-15 24-Nov-15 Lightning Sy Lightning System 144 26-Jul-15 10-Dec-15 Material PO's Material PO's 14 26-Jul-15 06-Aug-15 ZB4EEMP107LIGHTNING System Material PO 10 26-Jul-15 06-Aug-15 Material Deliv Material Delivery at Site 130 08-Aug-15 10-Dec-15 ZB4EEMD10 LIGHTNING System Material Delivery 104 08-Aug-15 10-Dec-15 Light Curren Light Current Systems 126 06-Sep-15 06-Jan-16 Fire Alarm Sy Fire Alarm System 126 06-Sep-15 06-Jan-16 Material PO' Material PO's 14 06-Sep-15 17-Sep-15 ZB4EEMP1Fire Alarm System Devices Material PO 10 06-Sep-15 17-Sep-15 ZB4EEMP1Fire Alarm System Fire Alarm Cable Material PO 10 06-Sep-15 17-Sep-15 ZB4EEMP1Fire Alarm System FACP Material PO 10 06-Sep-15 17-Sep-15 Material Del Material Delivery at Site 112 19-Sep-15 06-Jan-16 ZB4EEMD1Fire Alarm System Fire Alarm Cable Material Delivery 78 19-Sep-15 22-Dec-15 ZB4EEMD1Fire Alarm System Devices Material Delivery 90 19-Sep-15 06-Jan-16 Q2 Q3 Q4 Q1 Q2 Q3 Q4 2015 2016 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 40 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 41. Activity ID Activity Name Original Duration Start Finish ZB4EEMD1Fire Alarm System FACP Material Delivery 90 19-Sep-15 06-Jan-16 SCADA Sys SCADA System 105 19-Nov-15 28-Feb-16 Material PO's Material PO's 7 19-Nov-15 25-Nov-15 ZB4EEMP111SCADA System Material PO 5 19-Nov-15 25-Nov-15 Material Deliv Material Delivery at Site 97 26-Nov-15 28-Feb-16 ZB4EEMD112 SCADA System Material Delivery 78 26-Nov-15 28-Feb-16 Mechanical Mechanical Systems 227 28-Jun-15 04-Feb-16 HVAC Syste HVAC System 227 28-Jun-15 04-Feb-16 Material Subm Material Submittal 130 28-Jun-15 02-Nov-15 ZB4EEMS840AHU Material Submittal 12 28-Jun-15 13-Jul-15 ZB4EEMS850Chilled Water Valves Material Submittal 22 19-Jul-15 18-Aug-15 ZB4EEMS860Over Head Crane Material Submittal 22 06-Sep-15 08-Oct-15 ZB4EEMS870Air Cooled DX Split Units Material Submittal 18 07-Oct-15 02-Nov-15 Material Appr Material Approvals 120 14-Jul-15 09-Nov-15 ZB4EEMA84 AHU System Material Approval 5 14-Jul-15 21-Jul-15 ZB4EEMA85 Chilled Water Valves Material Approval 5 19-Aug-15 25-Aug-15 ZB4EEMA86 Over Head Crane Material Approval 5 11-Oct-15 18-Oct-15 ZB4EEMA87 Air Cooled DX Split Units Material Approval 5 03-Nov-15 09-Nov-15 Material PO's Material PO's 127 22-Jul-15 23-Nov-15 ZB4EEMP112AHU System Material PO 10 22-Jul-15 05-Aug-15 ZB4EEMP116Child pipe hangers and support Material PO 10 28-Jul-15 10-Aug-15 ZB4EEMP117Black seamless steel piping Material PO 10 17-Aug-15 30-Aug-15 ZB4EEMP118Metal Sheet Duct System Material PO 10 23-Aug-15 03-Sep-15 ZB4EEMP113Chilled Water Valves Material PO 10 26-Aug-15 08-Sep-15 ZB4EEMP119Fire Smoke Dampers Material PO 10 15-Sep-15 30-Sep-15 ZB4EEMP120Duct Insulation Material PO 10 17-Sep-15 04-Oct-15 ZB4EEMP121Chilled Water Piping Insulation Material PO 10 01-Oct-15 18-Oct-15 ZB4EEMP122Air Outlets Material PO 10 11-Oct-15 25-Oct-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 2015 2016 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 41 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 42. Activity ID Activity Name Original Duration Start Finish ZB4EEMP114Over Head Crane Material PO 10 19-Oct-15 01-Nov-15 ZB4EEMP115Air Cooled DX Split Units Material PO 10 10-Nov-15 23-Nov-15 Material Deliv Material Delivery at Site 187 06-Aug-15 04-Feb-16 ZB4EEMD117 Child pipe hangers and support Material ( Partial )Delivery 36 11-Aug-15 21-Sep-15 ZB4EEMD113 AHU System Material Delivery 78 06-Aug-15 09-Nov-15 ZB4EEMD118 Metal Sheet Duct System Partial Material Delivery / Fabrication 65 05-Sep-15 23-Nov-15 ZB4EEMD119 Black seamless steel piping Material ( Partial )Delivery 78 31-Aug-15 03-Dec-15 ZB4EEMD12 Duct Insulation Material Delivery 52 05-Oct-15 06-Dec-15 ZB4EEMD12 Fire Smoke Dampers Material Delivery 78 01-Oct-15 03-Jan-16 ZB4EEMD114 Chilled Water Valves Material ( Partial )Delivery 104 09-Sep-15 14-Jan-16 ZB4EEMD12 Chilled Water Piping Insulation Material ( Partial ) Delivery 75 19-Oct-15 16-Jan-16 ZB4EEMD116 Air Cooled DX Split Units Material Material Delivery 52 24-Nov-15 26-Jan-16 ZB4EEMD12 Air Outlets Material Delivery 78 26-Oct-15 27-Jan-16 ZB4EEMD115 Over Head Crane Material Delivery On Site 78 02-Nov-15 03-Feb-16 ZB4EEMD12 Testing, Balancing & Commisioning system Third Part On Site 0 04-Feb-16 Fire Protect Fire Protection Systems 114 01-Oct-15 19-Jan-16 Material Subm Material Submittal 19 29-Oct-15 15-Nov-15 ZB4EEMS880CO2 System Material Submittal 12 29-Oct-15 15-Nov-15 ZB4EEMS890Automatic Dry Powder Fire Extinguishers Material Submittal 12 29-Oct-15 15-Nov-15 ZB4EEMS900FOAM FIRE SUPPRESSION SYSTEM Material Submittal 12 29-Oct-15 15-Nov-15 ZB4EEMS910FM-200 CLEAN AGENT EXTINGUISHING SYSTEM Material Submittal 12 29-Oct-15 15-Nov-15 Material Appr Material Approvals 15 16-Nov-15 29-Nov-15 ZB4EEMA88 CO2 System Material Approval 10 16-Nov-15 29-Nov-15 ZB4EEMA89 Automatic Dry Powder Fire Extinguishers Material Approval 10 16-Nov-15 29-Nov-15 ZB4EEMA90 FOAM FIRE SUPPRESSION SYSTEM Material Approval 10 16-Nov-15 29-Nov-15 ZB4EEMA91 FM-200 CLEAN AGENT EXTINGUISHING SYSTEM Material Approval 10 16-Nov-15 29-Nov-15 Material PO's Material PO's 76 01-Oct-15 13-Dec-15 ZB4EEMP125Dry Powder Manual Fire Extinguishers Material PO 10 01-Oct-15 18-Oct-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 2015 2016 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 42 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2
  • 43. Activity ID Activity Name Original Duration Start Finish ZB4EEMP123CO2 System Material PO 10 30-Nov-15 13-Dec-15 ZB4EEMP124Automatic Dry Powder Fire Extinguishers Material PO 10 30-Nov-15 13-Dec-15 ZB4EEMP126FOAM FIRE SUPPRESSION SYSTEM Material PO 10 30-Nov-15 13-Dec-15 ZB4EEMP127FM-200 CLEAN AGENT EXTINGUISHING SYSTEM Material PO 10 30-Nov-15 13-Dec-15 Material Deliv Material Delivery at Site 97 19-Oct-15 19-Jan-16 ZB4EEMD12 Automatic Dry Powder Fire Extinguishers Material Delivery 12 14-Dec-15 28-Dec-15 ZB4EEMD12 CO2 System Material Delivery 26 14-Dec-15 14-Jan-16 ZB4EEMD12 FOAM FIRE SUPPRESSION SYSTEM Material Delivery 26 14-Dec-15 14-Jan-16 ZB4EEMD12 FM-200 CLEAN AGENT EXTINGUISHING SYSTEM Material Delivery 26 14-Dec-15 14-Jan-16 ZB4EEMD12 Dry Powder Manual Fire Extinguishers Material Delivery 78 19-Oct-15 19-Jan-16 Plumbing Sy Plumbing System 71 09-Aug-15 18-Oct-15 Material PO's Material PO's 44 09-Aug-15 17-Sep-15 ZB4EEMP128Pipes UPVC (PN 10) Material PO 10 09-Aug-15 20-Aug-15 ZB4EEMP129Roof Drains Material PO 10 06-Sep-15 17-Sep-15 Material Deliv Material Delivery at Site 57 22-Aug-15 18-Oct-15 ZB4EEMD13 Pipes UPVC (PN 10) Material Partial Delivery 22 22-Aug-15 15-Sep-15 ZB4EEMD13 Roof Drains Material Delivery 22 19-Sep-15 18-Oct-15 Building B4 - Building B4 - D (Fuel Tank) 217 24-Jun-15 21-Jan-16 Electrical Sy Electrical Systems 217 24-Jun-15 21-Jan-16 Power Syste Power System 217 24-Jun-15 21-Jan-16 Material Subm Material Submittal 25 27-Sep-15 21-Oct-15 ZB4EEMS138B4.D MCC Material Material Submittal 10 27-Sep-15 11-Oct-15 ZB4EEMS137B4.D EPP Material Material Submittal 10 07-Oct-15 21-Oct-15 Material Appr Material Approvals 17 12-Oct-15 28-Oct-15 ZB4EEMA13 B4.D MCC Material Material Approval 5 12-Oct-15 19-Oct-15 ZB4EEMA13 B4.D EPP Material Material Approval 5 22-Oct-15 28-Oct-15 Material PO's Material PO's 136 24-Jun-15 04-Nov-15 ZB4EEMP162EMT Material PO 10 24-Jun-15 07-Jul-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 2015 2016 Zewail City of Science and Technology B4 Contract Zewail Detailed Schedule All Buildings 27-Jan-16 16:09 Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 43 of 98 TASK filter: All Activities © Primavera Systems, Inc Date Revision Checked Approved 17-Nov-15 Rev 1 31-Jan-16 Rev 2