Aggregate planning and MPS
Aggregate planning
It may be defined as an intermediate production plan
which has a range of 2 to 18 months to give an idea
to management as to what quantity of materials and
other resources are to be procured and when, so that
the total cost of operations of the organization is kept
to the minimum over that period..
It has different approaches strategies and objectives
which will be discussed next. . . . . . . .
Definition
 There are certain inputs of aggregate planning that is
to say the factors which should be kept in mind while
planning for aggregate production;
 These are
Inputs of aggregate planning
Workforce
Facilities
Demand forecasts
Policies
Costs
Inputs of aggregate planning
 Total cost of a plan
 Projected levels of inventory
 Inventory
 Output
 Employment
 Subcontracting
 Backordering
Outputs of aggregate planning
 Proactive
 Alter demand to match capacity
 Reactive
 Alter capacity to match demand
 Mixed
 Some of each
Aggregate Planning Strategies
 In a proactive strategy a firm plans to change the
demand by means of advertisements or by means of
offering benefits for a specific product.
Proactive strategy
 A reactive planning strategy has two parts which are;
 Level strategy
 Chase strategy
Reactive strategy
 A level strategy seeks to produce an aggregate plan that
maintains a steady production rate and/or a steady
employment level. In order to satisfy changes in customer
demand, the firm must raise or lower inventory levels in
anticipation of increased or decreased levels of forecast
demand. The firm maintains a level workforce and a steady
rate of output when demand is somewhat low. This allows
the firm to establish higher inventory levels than are
currently needed. As demand increases, the firm is able to
continue a steady production rate/steady employment
level, while allowing the inventory surplus to absorb the
increased demand
Level strategy
 A chase strategy implies matching demand and capacity
period by period. This could result in a considerable
amount of hiring, firing or laying off of employees;
insecure and unhappy employees; increased inventory
carrying costs; problems with labor unions; and erratic
utilization of plant and equipment. It also implies a great
deal of flexibility on the firm's part. The major advantage
of a chase strategy is that it allows inventory to be held to
the lowest level possible, and for some firms this is a
considerable savings. Most firms embracing the just-in-
time production concept utilize a chase strategy approach
to aggregate planning.
Chase strategy
Level strategy
 ADVANTAGES
- Stable output rates and workforce
 DISADVANTAGES
 -greater inventory costs
 -increased over time and idle time
 -resource utilizations vary over time
 ADVANTAGES
 -Investment in inventory is low
 -Labor utilization in high
 DISADVANTAGES
 -The cost of fluctuating work force
 -potential damage to employee morale
Chase strategy
 Linear programming model
 Linear decision rule
 Simulation
Techniques
 Master Production Schedule
 Lists the products to be manufactured, when they should be
completed, and in what quantities
 It is the conversion of the aggregate schedule into a very
specific schedule of individual
 products
 Products listed in the master schedule generally divide into
three categories:
 1. Firm customer orders
 2. Forecasted demand
 3. Spare parts
Master production schedule
 Aggregate planning is a relatively longer term
planning that spans over a period of around 18months
on the other hand MPS is the putting of AP action i.e.
planning individual products for a shorter time span.
 Time unit for aggregate planning is one month while
the time unit for MPS is a week.
Relationship between MPS and
aggregate planning
That’s all what we have today for
you
we could have explained it in more
detail but time constraint didn’t
allow us !!!!!!!!
Credits
 This is a joint effort of
UMAR YAZDANI (D 11 IN 05)
AFSAAR ALI ( D 11 IN 27)
HANIF HAZARA (D 11 IN 39)
TAUQIR HAIDER ( D 11 IN 33)

More Related Content

What's hot

Aggregate planning and mps om
Aggregate planning and mps omAggregate planning and mps om
Aggregate planning and mps omfatuma ahmed
 
Material requirement planning, MRP.
Material requirement planning, MRP. Material requirement planning, MRP.
Material requirement planning, MRP. shoaibzaheer1
 
Capacity planning
Capacity planningCapacity planning
Capacity planningAkhil Lal
 
Aggregate Production Planning
Aggregate Production PlanningAggregate Production Planning
Aggregate Production Planning3abooodi
 
Centre of gravity method of location planning
Centre of gravity method of location planningCentre of gravity method of location planning
Centre of gravity method of location planningGaganjot Kaur
 
Aggregate planning
Aggregate planningAggregate planning
Aggregate planningAtif Ghayas
 
8. chapter 7 work study (time and motion study)
8. chapter 7   work study (time and motion study)8. chapter 7   work study (time and motion study)
8. chapter 7 work study (time and motion study)sundar sivam
 
Work Study: Method Study & Work Measurement
Work Study: Method Study & Work MeasurementWork Study: Method Study & Work Measurement
Work Study: Method Study & Work MeasurementHarinadh Karimikonda
 
Production planning, routing, scheduling, Activating, Monitoring
Production planning, routing, scheduling, Activating, MonitoringProduction planning, routing, scheduling, Activating, Monitoring
Production planning, routing, scheduling, Activating, MonitoringDarshan Shah
 
Method Study
Method StudyMethod Study
Method Studyajithsrc
 
Capacity planning ppt
Capacity planning pptCapacity planning ppt
Capacity planning pptGagan bhati
 
Aggregate production planning
Aggregate production planningAggregate production planning
Aggregate production planningArushi Gupta
 
Inventory management
 Inventory management Inventory management
Inventory managementN M
 
MATERIAL PLANNING PROCESS
MATERIAL PLANNING PROCESSMATERIAL PLANNING PROCESS
MATERIAL PLANNING PROCESSNEHA GAUTAM
 

What's hot (20)

Aggregate planning and mps om
Aggregate planning and mps omAggregate planning and mps om
Aggregate planning and mps om
 
Material requirement planning, MRP.
Material requirement planning, MRP. Material requirement planning, MRP.
Material requirement planning, MRP.
 
Capacity planning
Capacity planningCapacity planning
Capacity planning
 
(Mrp 1) Prsntation Slides
(Mrp 1) Prsntation Slides(Mrp 1) Prsntation Slides
(Mrp 1) Prsntation Slides
 
Aggregate Production Planning
Aggregate Production PlanningAggregate Production Planning
Aggregate Production Planning
 
Centre of gravity method of location planning
Centre of gravity method of location planningCentre of gravity method of location planning
Centre of gravity method of location planning
 
Forecasting Methods
Forecasting MethodsForecasting Methods
Forecasting Methods
 
Aggregate planning
Aggregate planningAggregate planning
Aggregate planning
 
8. chapter 7 work study (time and motion study)
8. chapter 7   work study (time and motion study)8. chapter 7   work study (time and motion study)
8. chapter 7 work study (time and motion study)
 
Work Study: Method Study & Work Measurement
Work Study: Method Study & Work MeasurementWork Study: Method Study & Work Measurement
Work Study: Method Study & Work Measurement
 
Production planning, routing, scheduling, Activating, Monitoring
Production planning, routing, scheduling, Activating, MonitoringProduction planning, routing, scheduling, Activating, Monitoring
Production planning, routing, scheduling, Activating, Monitoring
 
Method Study
Method StudyMethod Study
Method Study
 
CAPACITY PLANNING
CAPACITY PLANNINGCAPACITY PLANNING
CAPACITY PLANNING
 
Capacity planning ppt
Capacity planning pptCapacity planning ppt
Capacity planning ppt
 
Capacity planning
Capacity planning Capacity planning
Capacity planning
 
Aggregate production planning
Aggregate production planningAggregate production planning
Aggregate production planning
 
Reordering point
Reordering pointReordering point
Reordering point
 
Inventory management
 Inventory management Inventory management
Inventory management
 
MATERIAL PLANNING PROCESS
MATERIAL PLANNING PROCESSMATERIAL PLANNING PROCESS
MATERIAL PLANNING PROCESS
 
Aggregate planning
Aggregate planningAggregate planning
Aggregate planning
 

Similar to Mps vs aggregate planning

aggregateplanningreport-121002061533-phpapp02.pdf
aggregateplanningreport-121002061533-phpapp02.pdfaggregateplanningreport-121002061533-phpapp02.pdf
aggregateplanningreport-121002061533-phpapp02.pdfChunWan
 
A presentation on aggregate planning
A presentation on aggregate planningA presentation on aggregate planning
A presentation on aggregate planningAhelVitsu
 
Production planning techniques- aggregate planning
Production planning techniques- aggregate planningProduction planning techniques- aggregate planning
Production planning techniques- aggregate planningArushi Verma
 
Aggregate planning in supply chain
Aggregate planning in supply chainAggregate planning in supply chain
Aggregate planning in supply chainMoine Iqbal
 
Aggragate planning1
Aggragate planning1Aggragate planning1
Aggragate planning1arathymalz
 
Aggregate Planning.pptx
Aggregate Planning.pptxAggregate Planning.pptx
Aggregate Planning.pptxDr T.Sivakami
 
Sales & Operations Planning
Sales & Operations PlanningSales & Operations Planning
Sales & Operations Planningmubarak2009
 
Operations ppt
Operations pptOperations ppt
Operations pptPritam RW
 
Aggregate planning
Aggregate planningAggregate planning
Aggregate planningPritam RW
 
Operations ppt
Operations pptOperations ppt
Operations pptPritam RW
 
How to Transform your Capacity Planning Process: Step-by-Step Guide
How to Transform your Capacity Planning Process: Step-by-Step GuideHow to Transform your Capacity Planning Process: Step-by-Step Guide
How to Transform your Capacity Planning Process: Step-by-Step GuideShannon Kearns
 
AGGREGATE PRODUCTION PLANNING
AGGREGATE PRODUCTION PLANNING AGGREGATE PRODUCTION PLANNING
AGGREGATE PRODUCTION PLANNING Aqib ali
 

Similar to Mps vs aggregate planning (20)

aggregateplanningreport-121002061533-phpapp02.pdf
aggregateplanningreport-121002061533-phpapp02.pdfaggregateplanningreport-121002061533-phpapp02.pdf
aggregateplanningreport-121002061533-phpapp02.pdf
 
Master planning
Master planningMaster planning
Master planning
 
A presentation on aggregate planning
A presentation on aggregate planningA presentation on aggregate planning
A presentation on aggregate planning
 
Production planning techniques- aggregate planning
Production planning techniques- aggregate planningProduction planning techniques- aggregate planning
Production planning techniques- aggregate planning
 
Aggregate planning in supply chain
Aggregate planning in supply chainAggregate planning in supply chain
Aggregate planning in supply chain
 
Capacity management
Capacity managementCapacity management
Capacity management
 
Aggragate planning1
Aggragate planning1Aggragate planning1
Aggragate planning1
 
Aggregate Planning.pptx
Aggregate Planning.pptxAggregate Planning.pptx
Aggregate Planning.pptx
 
AGGREGATE PLANNING.pptx
AGGREGATE PLANNING.pptxAGGREGATE PLANNING.pptx
AGGREGATE PLANNING.pptx
 
Aggregate planning
Aggregate planningAggregate planning
Aggregate planning
 
435ch14
435ch14435ch14
435ch14
 
Session 4
Session 4Session 4
Session 4
 
Sales & Operations Planning
Sales & Operations PlanningSales & Operations Planning
Sales & Operations Planning
 
Operations ppt
Operations pptOperations ppt
Operations ppt
 
Aggregate planning
Aggregate planningAggregate planning
Aggregate planning
 
Operations ppt
Operations pptOperations ppt
Operations ppt
 
Aggregate Planning
Aggregate  PlanningAggregate  Planning
Aggregate Planning
 
Mrpc final
Mrpc finalMrpc final
Mrpc final
 
How to Transform your Capacity Planning Process: Step-by-Step Guide
How to Transform your Capacity Planning Process: Step-by-Step GuideHow to Transform your Capacity Planning Process: Step-by-Step Guide
How to Transform your Capacity Planning Process: Step-by-Step Guide
 
AGGREGATE PRODUCTION PLANNING
AGGREGATE PRODUCTION PLANNING AGGREGATE PRODUCTION PLANNING
AGGREGATE PRODUCTION PLANNING
 

Recently uploaded

CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduitsrknatarajan
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 

Recently uploaded (20)

CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 

Mps vs aggregate planning

  • 1.
  • 4. It may be defined as an intermediate production plan which has a range of 2 to 18 months to give an idea to management as to what quantity of materials and other resources are to be procured and when, so that the total cost of operations of the organization is kept to the minimum over that period.. It has different approaches strategies and objectives which will be discussed next. . . . . . . . Definition
  • 5.  There are certain inputs of aggregate planning that is to say the factors which should be kept in mind while planning for aggregate production;  These are Inputs of aggregate planning
  • 7.  Total cost of a plan  Projected levels of inventory  Inventory  Output  Employment  Subcontracting  Backordering Outputs of aggregate planning
  • 8.  Proactive  Alter demand to match capacity  Reactive  Alter capacity to match demand  Mixed  Some of each Aggregate Planning Strategies
  • 9.  In a proactive strategy a firm plans to change the demand by means of advertisements or by means of offering benefits for a specific product. Proactive strategy
  • 10.  A reactive planning strategy has two parts which are;  Level strategy  Chase strategy Reactive strategy
  • 11.  A level strategy seeks to produce an aggregate plan that maintains a steady production rate and/or a steady employment level. In order to satisfy changes in customer demand, the firm must raise or lower inventory levels in anticipation of increased or decreased levels of forecast demand. The firm maintains a level workforce and a steady rate of output when demand is somewhat low. This allows the firm to establish higher inventory levels than are currently needed. As demand increases, the firm is able to continue a steady production rate/steady employment level, while allowing the inventory surplus to absorb the increased demand Level strategy
  • 12.
  • 13.  A chase strategy implies matching demand and capacity period by period. This could result in a considerable amount of hiring, firing or laying off of employees; insecure and unhappy employees; increased inventory carrying costs; problems with labor unions; and erratic utilization of plant and equipment. It also implies a great deal of flexibility on the firm's part. The major advantage of a chase strategy is that it allows inventory to be held to the lowest level possible, and for some firms this is a considerable savings. Most firms embracing the just-in- time production concept utilize a chase strategy approach to aggregate planning. Chase strategy
  • 14.
  • 15. Level strategy  ADVANTAGES - Stable output rates and workforce  DISADVANTAGES  -greater inventory costs  -increased over time and idle time  -resource utilizations vary over time
  • 16.  ADVANTAGES  -Investment in inventory is low  -Labor utilization in high  DISADVANTAGES  -The cost of fluctuating work force  -potential damage to employee morale Chase strategy
  • 17.  Linear programming model  Linear decision rule  Simulation Techniques
  • 18.  Master Production Schedule  Lists the products to be manufactured, when they should be completed, and in what quantities  It is the conversion of the aggregate schedule into a very specific schedule of individual  products  Products listed in the master schedule generally divide into three categories:  1. Firm customer orders  2. Forecasted demand  3. Spare parts Master production schedule
  • 19.  Aggregate planning is a relatively longer term planning that spans over a period of around 18months on the other hand MPS is the putting of AP action i.e. planning individual products for a shorter time span.  Time unit for aggregate planning is one month while the time unit for MPS is a week. Relationship between MPS and aggregate planning
  • 20. That’s all what we have today for you we could have explained it in more detail but time constraint didn’t allow us !!!!!!!!
  • 21. Credits  This is a joint effort of UMAR YAZDANI (D 11 IN 05) AFSAAR ALI ( D 11 IN 27) HANIF HAZARA (D 11 IN 39) TAUQIR HAIDER ( D 11 IN 33)