Capacity Planning
For Products and
Services
5-2
Learning Objectives
 Explain the importance of capacity
planning.
 Discuss ways of defining and measuring
capacity.
 Describe the determinants of effective
capacity.
 Discuss the major considerations related to
developing capacity alternatives.
 Briefly describe approaches that are useful
for evaluating capacity alternatives
5-3
Capacity Planning
 Capacity is the upper limit or ceiling on
the load that an operating unit can
handle.
 Capacity also includes
 Equipment
 Space
 Employee skills
 The basic questions in capacity handling
are:
 What kind of capacity is needed?
 How much is needed?
 When is it needed?
5-4
1. Impacts ability to meet future demands
2. Affects operating costs
3. Major determinant of initial costs
4. Involves long-term commitment
5. Affects competitiveness
6. Affects ease of management
7. Globalization adds complexity
8. Impacts long range planning
Importance of Capacity Decisions
5-5
Capacity
 Design capacity
 …
 Effective capacity
 …
 Actual output
 …
5-6
Efficiency and Utilization
Actual output
Efficiency =
Effective capacity
Actual output
Utilization =
Design capacity
Both measures expressed as percentages
5-7
Actual output = units/day
Efficiency = =
Effective capacity units/ day
Utilization = Actual output = units/day
=
Design capacity units/day
Efficiency/Utilization Example
Design capacity = 50 trucks/day
Effective capacity = 40 trucks/day
Actual output = 36 trucks/day
5-8
Determinants of Effective
Capacity
 Facilities
 Product and service factors
 Process factors
 Human factors
 Policy factors
 Operational factors
 Supply chain factors
 External factors
5-9
Strategy Formulation
 Capacity strategy for long-term demand
 Demand patterns
 Growth rate and variability
 Facilities
 Cost of building and operating
 Technological changes
 Rate and direction of technology changes
 Behavior of competitors
 Availability of capital and other inputs
5-10
Key Decisions of Capacity
Planning
1. Amount of capacity needed
• Capacity cushion (100% - Utilization)
2. Timing of changes
3. Need to maintain balance
4. Extent of flexibility of facilities
Capacity cushion – extra demand intended to offset uncertainty
5-11
Forecasting Capacity
Requirements
 Long-term vs. short-term capacity needs
 Long-term relates to overall level of capacity
such as facility size, trends, and cycles
 Short-term relates to variations from
seasonal, random, and irregular fluctuations
in demand
5-12
Calculating Processing
Requirements
Product
Annual
Demand
Standard
processing time
per unit (hr.)
Processing time
needed (hr.)
#1
#2
#3
Total
400
300
700
5.0
8.0
2.0
Tot
If annual capacity is 2000 hours, then how many machines do we need to
handle the required volume of …. ?
5-13
 Need to be near customers
 Capacity and location are closely tied
 Inability to store services
 Capacity must be matched with timing of
demand
 Degree of volatility of demand
 Peak demand periods
Planning Service Capacity
5-14
In-House or Outsourcing
1. Available capacity
2. Expertise
3. Quality considerations
4. Nature of demand
5. Cost
6. Risk
Outsource: obtain a good or service
from an external provider
5-15
Developing Capacity Alternatives
1.Design flexibility into systems
2.Take stage of life cycle into account
3.Take a “big picture” approach to capacity
changes
4.Prepare to deal with capacity “chunks”
5.Attempt to smooth out capacity
requirements
6.Identify the optimal operating level
5-16
Bottleneck Operation
Figure 5.2
Machine #2
Bottleneck
Operation
Machine #1
Machine #3
Machine #4
10/hr
10/hr
10/hr
10/hr
30/hr
Bottleneck operation: An operation
in a sequence of operations whose
capacity is lower than that of the
other operations
5-17
Bottleneck Operation
Operation 1
20/hr.
Operation 2
10/hr.
Operation 3
15/hr.
?
Which operation is the Bottleneck operation?
Maximum output rate
limited by bottleneck
5-18
Economies of Scale
 Economies of scale
 If the output rate is less than the optimal level,
increasing output rate results in decreasing
average unit costs
 Diseconomies of scale
 If the output rate is more than the optimal
level, increasing the output rate results in
increasing average unit costs
5-19
Optimal Rate of Output
Minimum
cost
Averagecostperunit
0 Rate of output
Production units have an optimal rate of output for minimal cost.
Figure 5.4
Minimum average cost per unit
5-20
Economies of Scale
Minimum cost & optimal operating rate are
functions of size of production unit.Averagecostperunit
0
Small
plant Medium
plant Large
plant
Output rate
Figure 5.5
5-21
Evaluating Alternatives
 Cost-volume analysis
 Break-even point
 Financial analysis
 Cash flow
 Present value
 Decision theory
 Waiting-line analysis
5-22
Cost-Volume Relationships
Amount($)
0
Q (volume in units)
Fixed cost (FC)
Figure 5.6a
5-23
Cost-Volume Relationships
Amount($)
Q (volume in units)
0
Figure 5.6b
5-24
Cost-Volume Relationships
Amount($)
Q (volume in units)
0 BEP units
Figure 5.6c
5-25
Break-Even Problem with Step
Fixed Costs
Quantity
Step fixed costs and variable costs.
1 machine
2 machines
3 machines
Figure 5.7a
5-26
Break-Even Problem with Step
Fixed Costs
$
FC1
FC2
FC3
BEP2
BEP
3
Quantity
1
2
3
Multiple break-even points
Figure 5.7b
TP = (P – VC) Q
5-27
1.One product is involved
2.Everything produced can be sold
3.Variable cost per unit is the same
regardless of volume
4.Fixed costs do not change with volume
5.Revenue per unit constant with volume
6.Revenue per unit exceeds variable cost
per unit
Assumptions of Cost-Volume
Analysis
5-28
Financial Analysis
 Cash Flow - the difference between
cash received from sales and other
sources, and cash outflow for labor,
material, overhead, and taxes.
 Present Value - the sum, in current
value, of all future cash flows of an
investment proposal.
5-29
Waiting-Line Analysis
 Useful for designing or modifying service
systems
 Waiting-lines occur across a wide variety of
service systems
 Waiting-lines are caused by bottlenecks in
the process
 Helps managers plan capacity level that will
be cost-effective by balancing the cost of
having customers wait in line with the cost of
additional capacity

More Related Content

What's hot

Operation scheduling
Operation schedulingOperation scheduling
Operation scheduling
sai precious
 
Aggregate planning
Aggregate planningAggregate planning
Aggregate planning
Atif Ghayas
 

What's hot (20)

Capacity Management
Capacity ManagementCapacity Management
Capacity Management
 
Capacity planning
Capacity planningCapacity planning
Capacity planning
 
Operation scheduling
Operation schedulingOperation scheduling
Operation scheduling
 
Capacity planning
Capacity planningCapacity planning
Capacity planning
 
Capacity planning
Capacity planningCapacity planning
Capacity planning
 
Facility location
Facility locationFacility location
Facility location
 
Production & operations management
Production & operations managementProduction & operations management
Production & operations management
 
6. process selection and facility layout
6. process selection and facility layout6. process selection and facility layout
6. process selection and facility layout
 
Capacity management
Capacity managementCapacity management
Capacity management
 
Production and Operation Management
Production and Operation ManagementProduction and Operation Management
Production and Operation Management
 
Product Design in Operations Management
Product Design in Operations ManagementProduct Design in Operations Management
Product Design in Operations Management
 
Operation Management
Operation ManagementOperation Management
Operation Management
 
Aggregate planning
Aggregate planningAggregate planning
Aggregate planning
 
Productivity and operation management
Productivity and operation managementProductivity and operation management
Productivity and operation management
 
Process design & steps
Process design & stepsProcess design & steps
Process design & steps
 
Capacity planning ppt @ bec doms
Capacity planning ppt @ bec domsCapacity planning ppt @ bec doms
Capacity planning ppt @ bec doms
 
What is master production schedule
What is master production scheduleWhat is master production schedule
What is master production schedule
 
Aggregate Planning
Aggregate PlanningAggregate Planning
Aggregate Planning
 
Job Design and Work Measurement
Job Design and Work Measurement Job Design and Work Measurement
Job Design and Work Measurement
 
Process selection, design & analysis
Process selection, design & analysisProcess selection, design & analysis
Process selection, design & analysis
 

Viewers also liked

Capacity Planning
Capacity PlanningCapacity Planning
Capacity Planning
MOHD ARISH
 
Process Strategies and Capacity Planning
Process Strategies and Capacity PlanningProcess Strategies and Capacity Planning
Process Strategies and Capacity Planning
Jaisa Gapuz
 
Capacity Requirement Planning
Capacity Requirement PlanningCapacity Requirement Planning
Capacity Requirement Planning
senthil.G
 
Operation strategy at galanze
Operation strategy at galanzeOperation strategy at galanze
Operation strategy at galanze
Niilm-Cms
 

Viewers also liked (20)

Capacity Planning
Capacity PlanningCapacity Planning
Capacity Planning
 
Process Strategies and Capacity Planning
Process Strategies and Capacity PlanningProcess Strategies and Capacity Planning
Process Strategies and Capacity Planning
 
Manufacturing Execution Systems
Manufacturing Execution SystemsManufacturing Execution Systems
Manufacturing Execution Systems
 
MES - Manufacturing Execution System Explained
MES - Manufacturing Execution System ExplainedMES - Manufacturing Execution System Explained
MES - Manufacturing Execution System Explained
 
Manufacturing Execution System
Manufacturing Execution SystemManufacturing Execution System
Manufacturing Execution System
 
Capacity Requirement Planning
Capacity Requirement PlanningCapacity Requirement Planning
Capacity Requirement Planning
 
Aggregate planning and mps om
Aggregate planning and mps omAggregate planning and mps om
Aggregate planning and mps om
 
Product design and development ch4
Product design and development ch4Product design and development ch4
Product design and development ch4
 
Learning Curves in Production Management
Learning Curves in Production ManagementLearning Curves in Production Management
Learning Curves in Production Management
 
MARUTI SUZUKI PRODUCT ANALYSIS REPORT
MARUTI SUZUKI PRODUCT ANALYSIS REPORTMARUTI SUZUKI PRODUCT ANALYSIS REPORT
MARUTI SUZUKI PRODUCT ANALYSIS REPORT
 
Product design and development ch2
Product design and development ch2Product design and development ch2
Product design and development ch2
 
Product design and development ch3
Product design and development ch3Product design and development ch3
Product design and development ch3
 
Learn curve
Learn curveLearn curve
Learn curve
 
operations strategy and competitiveness
operations strategy and competitivenessoperations strategy and competitiveness
operations strategy and competitiveness
 
C5 process & layout
C5 process & layoutC5 process & layout
C5 process & layout
 
Learning Curve Sample Problem
Learning Curve Sample ProblemLearning Curve Sample Problem
Learning Curve Sample Problem
 
Learning curve
Learning curveLearning curve
Learning curve
 
Product design
Product designProduct design
Product design
 
Operation strategy at galanze
Operation strategy at galanzeOperation strategy at galanze
Operation strategy at galanze
 
Product designing strategy
Product designing strategyProduct designing strategy
Product designing strategy
 

Similar to Capacity planning ppt

Process selection and capacity planning
Process selection and capacity planningProcess selection and capacity planning
Process selection and capacity planning
Shankarjyoti Hazarika
 

Similar to Capacity planning ppt (20)

Operation management ppt.ppt
Operation management  ppt.pptOperation management  ppt.ppt
Operation management ppt.ppt
 
Capacity-Planning.ppt
Capacity-Planning.pptCapacity-Planning.ppt
Capacity-Planning.ppt
 
Chapter 5 Capacity Planning.ppt
Chapter 5 Capacity Planning.pptChapter 5 Capacity Planning.ppt
Chapter 5 Capacity Planning.ppt
 
(capacity1).ppt
(capacity1).ppt(capacity1).ppt
(capacity1).ppt
 
CHAPTER 3 System and design Capacity.pptx
CHAPTER 3 System and design Capacity.pptxCHAPTER 3 System and design Capacity.pptx
CHAPTER 3 System and design Capacity.pptx
 
Capacity-Planning-Report - Measurement of Capacity
Capacity-Planning-Report - Measurement of CapacityCapacity-Planning-Report - Measurement of Capacity
Capacity-Planning-Report - Measurement of Capacity
 
(CAPACITY PLANNIG)
(CAPACITY PLANNIG)(CAPACITY PLANNIG)
(CAPACITY PLANNIG)
 
Chapter 05 Slides.pptx
Chapter 05                                      Slides.pptxChapter 05                                      Slides.pptx
Chapter 05 Slides.pptx
 
Chapter 05 Slides.pptx
Chapter 05                                      Slides.pptxChapter 05                                      Slides.pptx
Chapter 05 Slides.pptx
 
Operations managementppt
Operations managementpptOperations managementppt
Operations managementppt
 
Chapter 06
Chapter 06Chapter 06
Chapter 06
 
Aggregate planning
Aggregate planningAggregate planning
Aggregate planning
 
Facility Laout
Facility LaoutFacility Laout
Facility Laout
 
Process selection and capacity planning
Process selection and capacity planningProcess selection and capacity planning
Process selection and capacity planning
 
capacity planning.pptx
capacity planning.pptxcapacity planning.pptx
capacity planning.pptx
 
Capacity
CapacityCapacity
Capacity
 
Operations Management - Chapter 5.pdf
Operations Management - Chapter 5.pdfOperations Management - Chapter 5.pdf
Operations Management - Chapter 5.pdf
 
OPS 571 GENIUS Inspiring Innovation--ops571genius.com
OPS 571 GENIUS Inspiring Innovation--ops571genius.comOPS 571 GENIUS Inspiring Innovation--ops571genius.com
OPS 571 GENIUS Inspiring Innovation--ops571genius.com
 
OPS 571 GENIUS Education Counseling--ops571genius.com
OPS 571 GENIUS Education Counseling--ops571genius.comOPS 571 GENIUS Education Counseling--ops571genius.com
OPS 571 GENIUS Education Counseling--ops571genius.com
 
OPS 571 HELP Education for Service--ops571help.com
 OPS 571 HELP Education for Service--ops571help.com OPS 571 HELP Education for Service--ops571help.com
OPS 571 HELP Education for Service--ops571help.com
 

Recently uploaded

一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理
一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理
一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理
bd2c5966a56d
 
一比一原版(Griffith毕业证书)格里菲斯大学毕业证如何办理
一比一原版(Griffith毕业证书)格里菲斯大学毕业证如何办理一比一原版(Griffith毕业证书)格里菲斯大学毕业证如何办理
一比一原版(Griffith毕业证书)格里菲斯大学毕业证如何办理
bd2c5966a56d
 
一比一原版(Monash毕业证书)澳洲莫纳什大学毕业证如何办理
一比一原版(Monash毕业证书)澳洲莫纳什大学毕业证如何办理一比一原版(Monash毕业证书)澳洲莫纳什大学毕业证如何办理
一比一原版(Monash毕业证书)澳洲莫纳什大学毕业证如何办理
F La
 
一比一原版(UM毕业证书)密苏里大学毕业证如何办理
一比一原版(UM毕业证书)密苏里大学毕业证如何办理一比一原版(UM毕业证书)密苏里大学毕业证如何办理
一比一原版(UM毕业证书)密苏里大学毕业证如何办理
F La
 
一比一原版(纽大毕业证书)美国纽约大学毕业证如何办理
一比一原版(纽大毕业证书)美国纽约大学毕业证如何办理一比一原版(纽大毕业证书)美国纽约大学毕业证如何办理
一比一原版(纽大毕业证书)美国纽约大学毕业证如何办理
e9733fc35af6
 
Interpretation of statute topics for project
Interpretation of statute topics for projectInterpretation of statute topics for project
Interpretation of statute topics for project
VarshRR
 
一比一原版曼彻斯特城市大学毕业证如何办理
一比一原版曼彻斯特城市大学毕业证如何办理一比一原版曼彻斯特城市大学毕业证如何办理
一比一原版曼彻斯特城市大学毕业证如何办理
Airst S
 
一比一原版(Carleton毕业证书)加拿大卡尔顿大学毕业证如何办理
一比一原版(Carleton毕业证书)加拿大卡尔顿大学毕业证如何办理一比一原版(Carleton毕业证书)加拿大卡尔顿大学毕业证如何办理
一比一原版(Carleton毕业证书)加拿大卡尔顿大学毕业证如何办理
e9733fc35af6
 
一比一原版赫瑞瓦特大学毕业证如何办理
一比一原版赫瑞瓦特大学毕业证如何办理一比一原版赫瑞瓦特大学毕业证如何办理
一比一原版赫瑞瓦特大学毕业证如何办理
Airst S
 
一比一原版(ECU毕业证书)埃迪斯科文大学毕业证如何办理
一比一原版(ECU毕业证书)埃迪斯科文大学毕业证如何办理一比一原版(ECU毕业证书)埃迪斯科文大学毕业证如何办理
一比一原版(ECU毕业证书)埃迪斯科文大学毕业证如何办理
Airst S
 
一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理
一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理
一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理
Airst S
 

Recently uploaded (20)

一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理
一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理
一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理
 
Elective Course on Forensic Science in Law
Elective Course on Forensic Science  in LawElective Course on Forensic Science  in Law
Elective Course on Forensic Science in Law
 
一比一原版(Griffith毕业证书)格里菲斯大学毕业证如何办理
一比一原版(Griffith毕业证书)格里菲斯大学毕业证如何办理一比一原版(Griffith毕业证书)格里菲斯大学毕业证如何办理
一比一原版(Griffith毕业证书)格里菲斯大学毕业证如何办理
 
ARTICLE 370 PDF about the indian constitution.
ARTICLE 370 PDF about the  indian constitution.ARTICLE 370 PDF about the  indian constitution.
ARTICLE 370 PDF about the indian constitution.
 
Sangyun Lee, Duplicate Powers in the Criminal Referral Process and the Overla...
Sangyun Lee, Duplicate Powers in the Criminal Referral Process and the Overla...Sangyun Lee, Duplicate Powers in the Criminal Referral Process and the Overla...
Sangyun Lee, Duplicate Powers in the Criminal Referral Process and the Overla...
 
一比一原版(Monash毕业证书)澳洲莫纳什大学毕业证如何办理
一比一原版(Monash毕业证书)澳洲莫纳什大学毕业证如何办理一比一原版(Monash毕业证书)澳洲莫纳什大学毕业证如何办理
一比一原版(Monash毕业证书)澳洲莫纳什大学毕业证如何办理
 
Navigating Employment Law - Term Project.pptx
Navigating Employment Law - Term Project.pptxNavigating Employment Law - Term Project.pptx
Navigating Employment Law - Term Project.pptx
 
一比一原版(UM毕业证书)密苏里大学毕业证如何办理
一比一原版(UM毕业证书)密苏里大学毕业证如何办理一比一原版(UM毕业证书)密苏里大学毕业证如何办理
一比一原版(UM毕业证书)密苏里大学毕业证如何办理
 
一比一原版(纽大毕业证书)美国纽约大学毕业证如何办理
一比一原版(纽大毕业证书)美国纽约大学毕业证如何办理一比一原版(纽大毕业证书)美国纽约大学毕业证如何办理
一比一原版(纽大毕业证书)美国纽约大学毕业证如何办理
 
Interpretation of statute topics for project
Interpretation of statute topics for projectInterpretation of statute topics for project
Interpretation of statute topics for project
 
一比一原版曼彻斯特城市大学毕业证如何办理
一比一原版曼彻斯特城市大学毕业证如何办理一比一原版曼彻斯特城市大学毕业证如何办理
一比一原版曼彻斯特城市大学毕业证如何办理
 
It’s Not Easy Being Green: Ethical Pitfalls for Bankruptcy Novices
It’s Not Easy Being Green: Ethical Pitfalls for Bankruptcy NovicesIt’s Not Easy Being Green: Ethical Pitfalls for Bankruptcy Novices
It’s Not Easy Being Green: Ethical Pitfalls for Bankruptcy Novices
 
Career As Legal Reporters for Law Students
Career As Legal Reporters for Law StudentsCareer As Legal Reporters for Law Students
Career As Legal Reporters for Law Students
 
一比一原版(Carleton毕业证书)加拿大卡尔顿大学毕业证如何办理
一比一原版(Carleton毕业证书)加拿大卡尔顿大学毕业证如何办理一比一原版(Carleton毕业证书)加拿大卡尔顿大学毕业证如何办理
一比一原版(Carleton毕业证书)加拿大卡尔顿大学毕业证如何办理
 
一比一原版赫瑞瓦特大学毕业证如何办理
一比一原版赫瑞瓦特大学毕业证如何办理一比一原版赫瑞瓦特大学毕业证如何办理
一比一原版赫瑞瓦特大学毕业证如何办理
 
Performance of contract-1 law presentation
Performance of contract-1 law presentationPerformance of contract-1 law presentation
Performance of contract-1 law presentation
 
Cyber Laws : National and International Perspective.
Cyber Laws : National and International Perspective.Cyber Laws : National and International Perspective.
Cyber Laws : National and International Perspective.
 
一比一原版(ECU毕业证书)埃迪斯科文大学毕业证如何办理
一比一原版(ECU毕业证书)埃迪斯科文大学毕业证如何办理一比一原版(ECU毕业证书)埃迪斯科文大学毕业证如何办理
一比一原版(ECU毕业证书)埃迪斯科文大学毕业证如何办理
 
一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理
一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理
一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理
 
Smarp Snapshot 210 -- Google's Social Media Ad Fraud & Disinformation Strategy
Smarp Snapshot 210 -- Google's Social Media Ad Fraud & Disinformation StrategySmarp Snapshot 210 -- Google's Social Media Ad Fraud & Disinformation Strategy
Smarp Snapshot 210 -- Google's Social Media Ad Fraud & Disinformation Strategy
 

Capacity planning ppt

  • 1. McGraw-Hill/Irwin Copyright © 2007 by The McGraw-Hill Companies, Inc. All rights reserved. 5 Capacity Planning For Products and Services
  • 2. 5-2 Learning Objectives  Explain the importance of capacity planning.  Discuss ways of defining and measuring capacity.  Describe the determinants of effective capacity.  Discuss the major considerations related to developing capacity alternatives.  Briefly describe approaches that are useful for evaluating capacity alternatives
  • 3. 5-3 Capacity Planning  Capacity is the upper limit or ceiling on the load that an operating unit can handle.  Capacity also includes  Equipment  Space  Employee skills  The basic questions in capacity handling are:  What kind of capacity is needed?  How much is needed?  When is it needed?
  • 4. 5-4 1. Impacts ability to meet future demands 2. Affects operating costs 3. Major determinant of initial costs 4. Involves long-term commitment 5. Affects competitiveness 6. Affects ease of management 7. Globalization adds complexity 8. Impacts long range planning Importance of Capacity Decisions
  • 5. 5-5 Capacity  Design capacity  …  Effective capacity  …  Actual output  …
  • 6. 5-6 Efficiency and Utilization Actual output Efficiency = Effective capacity Actual output Utilization = Design capacity Both measures expressed as percentages
  • 7. 5-7 Actual output = units/day Efficiency = = Effective capacity units/ day Utilization = Actual output = units/day = Design capacity units/day Efficiency/Utilization Example Design capacity = 50 trucks/day Effective capacity = 40 trucks/day Actual output = 36 trucks/day
  • 8. 5-8 Determinants of Effective Capacity  Facilities  Product and service factors  Process factors  Human factors  Policy factors  Operational factors  Supply chain factors  External factors
  • 9. 5-9 Strategy Formulation  Capacity strategy for long-term demand  Demand patterns  Growth rate and variability  Facilities  Cost of building and operating  Technological changes  Rate and direction of technology changes  Behavior of competitors  Availability of capital and other inputs
  • 10. 5-10 Key Decisions of Capacity Planning 1. Amount of capacity needed • Capacity cushion (100% - Utilization) 2. Timing of changes 3. Need to maintain balance 4. Extent of flexibility of facilities Capacity cushion – extra demand intended to offset uncertainty
  • 11. 5-11 Forecasting Capacity Requirements  Long-term vs. short-term capacity needs  Long-term relates to overall level of capacity such as facility size, trends, and cycles  Short-term relates to variations from seasonal, random, and irregular fluctuations in demand
  • 12. 5-12 Calculating Processing Requirements Product Annual Demand Standard processing time per unit (hr.) Processing time needed (hr.) #1 #2 #3 Total 400 300 700 5.0 8.0 2.0 Tot If annual capacity is 2000 hours, then how many machines do we need to handle the required volume of …. ?
  • 13. 5-13  Need to be near customers  Capacity and location are closely tied  Inability to store services  Capacity must be matched with timing of demand  Degree of volatility of demand  Peak demand periods Planning Service Capacity
  • 14. 5-14 In-House or Outsourcing 1. Available capacity 2. Expertise 3. Quality considerations 4. Nature of demand 5. Cost 6. Risk Outsource: obtain a good or service from an external provider
  • 15. 5-15 Developing Capacity Alternatives 1.Design flexibility into systems 2.Take stage of life cycle into account 3.Take a “big picture” approach to capacity changes 4.Prepare to deal with capacity “chunks” 5.Attempt to smooth out capacity requirements 6.Identify the optimal operating level
  • 16. 5-16 Bottleneck Operation Figure 5.2 Machine #2 Bottleneck Operation Machine #1 Machine #3 Machine #4 10/hr 10/hr 10/hr 10/hr 30/hr Bottleneck operation: An operation in a sequence of operations whose capacity is lower than that of the other operations
  • 17. 5-17 Bottleneck Operation Operation 1 20/hr. Operation 2 10/hr. Operation 3 15/hr. ? Which operation is the Bottleneck operation? Maximum output rate limited by bottleneck
  • 18. 5-18 Economies of Scale  Economies of scale  If the output rate is less than the optimal level, increasing output rate results in decreasing average unit costs  Diseconomies of scale  If the output rate is more than the optimal level, increasing the output rate results in increasing average unit costs
  • 19. 5-19 Optimal Rate of Output Minimum cost Averagecostperunit 0 Rate of output Production units have an optimal rate of output for minimal cost. Figure 5.4 Minimum average cost per unit
  • 20. 5-20 Economies of Scale Minimum cost & optimal operating rate are functions of size of production unit.Averagecostperunit 0 Small plant Medium plant Large plant Output rate Figure 5.5
  • 21. 5-21 Evaluating Alternatives  Cost-volume analysis  Break-even point  Financial analysis  Cash flow  Present value  Decision theory  Waiting-line analysis
  • 22. 5-22 Cost-Volume Relationships Amount($) 0 Q (volume in units) Fixed cost (FC) Figure 5.6a
  • 24. 5-24 Cost-Volume Relationships Amount($) Q (volume in units) 0 BEP units Figure 5.6c
  • 25. 5-25 Break-Even Problem with Step Fixed Costs Quantity Step fixed costs and variable costs. 1 machine 2 machines 3 machines Figure 5.7a
  • 26. 5-26 Break-Even Problem with Step Fixed Costs $ FC1 FC2 FC3 BEP2 BEP 3 Quantity 1 2 3 Multiple break-even points Figure 5.7b TP = (P – VC) Q
  • 27. 5-27 1.One product is involved 2.Everything produced can be sold 3.Variable cost per unit is the same regardless of volume 4.Fixed costs do not change with volume 5.Revenue per unit constant with volume 6.Revenue per unit exceeds variable cost per unit Assumptions of Cost-Volume Analysis
  • 28. 5-28 Financial Analysis  Cash Flow - the difference between cash received from sales and other sources, and cash outflow for labor, material, overhead, and taxes.  Present Value - the sum, in current value, of all future cash flows of an investment proposal.
  • 29. 5-29 Waiting-Line Analysis  Useful for designing or modifying service systems  Waiting-lines occur across a wide variety of service systems  Waiting-lines are caused by bottlenecks in the process  Helps managers plan capacity level that will be cost-effective by balancing the cost of having customers wait in line with the cost of additional capacity