SlideShare a Scribd company logo
1 of 22
Download to read offline
Addressing the challenges of
delivering Mega Projects
DR. MOHAMMED ALALSHIKH, PHD, PMP, AVS
CERTIFIED MOR, MSP & PRINCE2 PRACTITIONER
SAUDI MEGA PROJECTS CONFERENCE 2015, RIYADH
1
Outlines
q Introduction,
q Best practices in project management
q Obstacles that hinder deliveringmega projects
q Lessons learnt from mega project management & Recommendations
q The Government’s PMO initiative
q Conclusions
2
Definitions
A project is temporary organisation that is created for the purpose of
delivering one or more business outputs according to a specified business
case.
A mega project is an extremely large-scale investment project, and is
typically defined as costing more than US $1 billion and attracting a lot of
public attention because of substantial impacts on communities, environment
and budgets.
Mega projects can also be defined as "initiatives that are physical, very
expensive, and public”. (Wikipedia,2015)
3
Activities that should be managed in
the project
v Scope: What is the project? And how is it defined?
v Procurement: Which kind of contractual and organisational route will be
used?
v Planning and progress: Analyse the project and set a plan of action to
therefore control its progress.
v Time: Identifya project timetable and how it will be implemented.
v Cost: What is the budget and how will it be managed?
v Quality: Determinationof standards and their observance.
v People: Individual managers and project teams.
v Risk: What are the risks, who carries them, and how can they be avoided or
mitigated? (Woodward, 1997)
4
Ability to change
10/3/2010 5
Client value stair Client values pyramid
Clientsatisfaction
VM/VE
interventions Value steps
Peak of client satisfaction
Project performance
specifications and project brief
Project designs and
technical solutions
Project
construction
Project strategic fit and strategic brief
Abilitytochangedecreases
VE4
VE3
VM2
VM1
Changecostincreases
Ref.:	
  (Alalshikh,	
   2010)
Project failure
6
q According to the Standish CHAOS Report (2009):
q 68% of software projects do not meet time/cost/scope targets.
q Only 32% of projects were completed on time, within budget
and delivered measurable business and stakeholder benefits.
Project failure reasons
q There are many reasons for such failures. As per a PricewaterhouseCoopers
survey of 1,524 organizations:
Ø inadequate project estimating andplanning constitutes 30% of project failures,
Ølack of executive sponsorship constitutes 16% ,
Øand poorly defined goals andobjectives constitutes 12%.
ØAlso it found that using established project management approaches increased
success as measured by a project's key performance indicators of quality, scope,
schedule, budgets and benefits,
ØThe survey indicates that operating an established PMO is one of the top three
reasons that drives successful project delivery.
7
Causes for project failure
1. Ambiguous client objectives and brief.
2. Lack of understanding of team roles, responsibilitiesand competencies.
3. Poorly thought out management structures, lines of authority and communication.
4. Funding and business issues including changing market circumstances.
5. Sub-optimal information release, decision-making in terms of timing and adequacy.
6. Third party influences.
7. Difficulties obtaining satisfactoryplanning and statutory approvals.
8. Troubles during construction suchas site issuesand the weather or ground conditions.
9. Unresolved design issues.
10. Contractor capability and solvency.
11. Operational faultsafter handover.
12. Natural or manmade disasters (force majeure) (Dallas, 2004) .
8
Mega project management
q Projects failure can be attributedto different reasons as mentioned
before. Lack of experience and knowledge in professional project
management is one of the main reasons.
q Abundance of mega projects in Saudi Arabia stipulates:
Ø Initiating PMO in organisations, which will ground the rules for project
management and enhance project managers capabilities.
ØApplication of project management best practices is essential, in order to
deliver success projects. Otherwise, projects will fail to meet client values
and end users requirements.
q The Government’s PMO initiative will contribute in overcoming
these obstacles.
9
Best practices in project management
q Professionalismis crucial to conduct projects successfully
q Examples of best practices:
q Project management using PMI approach (PMP) or APM approach
(PRINCE2),
q Programme management, e.g. MSP (APM approach or PMI methodology),
q Initiating P3O or PMO,
q Etc.
10
Portfolio/ Programme/ Project
Management Office (P3O/ PMO)
q Project management office (PMO) is a group or department that develops, maintains
and promotes project management standards within the organisation. It standardizes
project management processes, tools, techniques, reports, forms and templates.
q It is a strategic driver for organisational excellence,
q It improves organisationproject management capabilities and increasessuccess in
implementing projects,
q It offers continuous improvements of project management infrastructure based on
improving capabilities and changing organisational culture towards project management
maturity model,
q It is the source of documentation, guidanceand metricsin practice of project
management and execution.
11
Benefits achieved using the PMO
q Stronger collaboration between projects and knowledgesharing
q Managing shared resources across all projects
q Developing project management methodology, best practices, policy, and
standards
q Developing and managing project, procedures, tools, techniques,
templates, forms and other shared documentations
q Managing Risk and Issues at a programme level by allocating dedicated
specialist in the PMO to deal with particular risks and Issues – avoids
duplication
q Prototype design approval in one project, is cascaded to other similar
project to speed up the approval process
12
Benefits achieved using PMO
q Share lessons learnt across all projects, to avoid problem repeating other
projects
q Manage dependencies across projects effectively and efficiently, by
implementing a programme schedule
q Compare progress and performance across projects, and investigating
common delays and bottlenecks
q Coordinating communication across projects
q Assigning, qualifying and mentoring project managers through a defined
career path
q Establish a project review function (auditing and health check)
q Save project managers time by supplying them with forms, template, tools
and techniques.
13
14
Portfolio, programme & project
PMO benefits
q Programme Policies & Procedures
q Programme Schedule
q Dependencies Log
15
PMO benefits
q Risks & Issues management
16
Program Issue Register - November 2014
Risk ID# Project
Name
Category Brief Risk Description Risk Impact Mitigation Actions / Risk Response Probability
Level
Impact
Level
Calculated
Risk
(automated
)
Status Entry Date Planned
Resolution
Date
Update / Comments
3 SFMCP	
  -­‐	
  J TIMING
Missing	
  NOC's	
  (leading	
  to	
  missing	
  
building	
  permits	
  and	
  future	
  utility	
  
connections)	
  has	
  prevented	
  
construction	
  start	
  and	
  could	
  delay	
  
project	
  completion
Project	
  Delay
MOI	
  need	
  to	
  issue	
  official	
  letters	
  to	
  
relevant	
  Local	
  Authorities	
  per	
  "NOCs	
  list	
  
included	
  in	
  contractor's	
  monthly	
  report"	
  
,	
  as	
  early	
  as	
  possible
High Very	
  High 20 Open 30-­‐Sep-­‐13 31-­‐Dec-­‐14 Mitigation	
  Plan	
  reviewed	
  on	
  Oct	
  2014
6 SFMCP	
  -­‐	
  J COST
Potentially	
  reduced	
  control	
  over	
  
evaluation	
  of	
  requested	
  changes	
  
due	
  to	
  revisions	
  of	
  original	
  BoQ	
  
during	
  tender
Project	
  Cost	
  Increase
Continual	
  Pressure	
  on	
  SBG	
  to	
  expedite	
  
the	
  submission	
  of	
  BoQ
Very	
  High High 20 Open 30-­‐Sep-­‐13 ASAP
Meeting	
  Minutes	
  22-­‐01-­‐2014,	
  our	
  letters	
  MB0B00-­‐
00LB0240/243/260,	
  dated	
  2/9/2014,	
  11/9/2014,	
  &	
  
29/10/2014	
  -­‐	
  SBG	
  Letter	
  No	
  BB0B00-­‐00LM0125,	
  dated	
  
6/11/2014
8 SFMCP	
  -­‐	
  JPERFORMANCE/COST
potential	
  Cost	
  implication	
  &	
  poor	
  
equipment's	
  quality	
  due	
  to	
  
Medical	
  equipment	
  list	
  contains	
  
outdated	
  or	
  obsolete	
  equipment,	
  
new	
  models	
  require	
  different	
  built	
  
conditions	
  (regardless	
  of	
  who	
  
buys	
  it)
Poor	
  Equipment	
  Quality/Project	
  
Cost	
  increase
client	
  decided	
  to	
  hire	
  a	
  3rd	
  party	
  to	
  
review	
  &	
  prepare	
  an	
  updated	
  list	
  ,	
  keep	
  
close	
  attention
Medium Medium 9 Open ######## 31-­‐Dec-­‐14
Highlighted	
  in	
  presentation	
  to	
  MOI	
  on	
  19/05/2014,	
  another	
  
presentation	
  on	
  July	
  2014	
  mentioned	
  that	
  deadline	
  to	
  hire	
  the	
  
3rd	
  party	
  is	
  Sept	
  14th	
  2014
9 SFMCP	
  -­‐	
  J TIMING
Contractor's	
  delay	
  in	
  activating	
  
the	
  mobilization	
  and,	
  in	
  particular,	
  
the	
  project	
  control	
  system	
  PCM	
  
can	
  further	
  compromise	
  project	
  
start-­‐up	
  and	
  efficiency.
Project	
  Delay
Continual	
  pressure	
  on	
  the	
  contractors	
  to	
  
accelerate	
  the	
  mobilization
Medium Low 6 Open ######## 31-­‐Dec-­‐14 On	
  18	
  May	
  MT	
  sent	
  another	
  letter	
  to	
  SBG	
  in	
  breech	
  of	
  contract
11 SFMCP	
  -­‐	
  J COORDINATION
Potential	
  Difficult	
  communication	
  
and	
  coordination	
  caused	
  by	
  lack	
  
of	
  collaboration	
  with	
  Engineer's	
  
directions
Delay	
  in	
  completing	
  the	
  activities	
  
on	
  time	
  hence	
  overall	
  project	
  Delay
MT	
  to	
  keep	
  reminding	
  Contractor	
  for	
  his	
  
contractual	
  obligation	
  &	
  must	
  conform	
  
to	
  operating	
  procedures
Medium Medium 9 Open 30-­‐Sep-­‐13 ASAP
Program Issue Register - November 2014
Status Project
name
Project
Risk ID# /
Reference
Category Brief Issue Description Projects
Affected
Impact Description Issue Type Impact Level Mitigation Actions Entry Date Planned
Resolution Date
Current Status / Comments
Open ACC 8 Scope
Quality	
  of	
  Contractor's	
  Submittals	
  is	
  inadequate.	
  	
  Poor	
  
sequencing	
  as	
  in	
  Calculations	
  >	
  Equipment	
  and	
  Materials	
  >	
  
Drawings.	
  	
  Also	
  poor	
  coordination	
  between	
  trades,	
  e.g.	
  
between	
  mechanical,	
  electrical	
  and	
  architectural.	
  Example	
  
is	
  structural	
  drawing	
  approval	
  requested	
  before	
  lift	
  
supplier	
  and	
  equipment	
  specification	
  approved.
WBSL-­‐1 Quality	
  and	
  Time	
  and	
  Impact High Medium
Technical	
  Submissions	
  to	
  agreed	
  
standards,	
  sequence	
  and	
  
demonstrate	
  coordination,	
  
including	
  of	
  utilities	
  trenches	
  and	
  
ducts.
Drawings	
  must	
  be	
  organised	
  ,	
  
listing	
  ,	
  all	
  submission	
  clearly	
  
identified	
  as	
  per	
  Submittal	
  Logs.	
  
The	
  latter	
  should	
  be	
  re-­‐edited	
  and	
  
updated	
  periodically.
22/12/13 6/26/2014
30/10/14-­‐INFO	
  from	
  
MSC-­‐updated:action
Open Program 10 Scope
Changes	
  in	
  Project	
  site	
  locations	
  (see	
  also	
  issues	
  19,	
  33	
  
and	
  39)
104
109
122
Delay	
  in	
  taking	
  over	
  the	
  sites Medium Medium
MOI	
  to	
  finalize	
  master	
  plans	
  with	
  
final	
  project	
  site	
  locations
STC	
  Ar'ar	
  &	
  Aseer/Abha,	
  
Infrastructure	
  Central	
  
District,	
  STC	
  Jeddah
30/11/14-­‐INFO	
  from	
  
MSC-­‐updated:	
  action
Open Program 12 Scope
New	
  Infrastructure	
  Master	
  plan	
  for	
  Eastern	
  Road	
  Land	
  
and	
  Bersha'a
-­‐	
  An	
  integrated	
  storm	
  water	
  protection	
  for	
  various	
  project	
  
sites	
  at	
  Eastern	
  Road	
  Land	
  are	
  required
-­‐	
  Water	
  supply,	
  electricity	
  and	
  Sewerage	
  drainage	
  is	
  
required.	
  Asnd	
  Road	
  network	
  need	
  to	
  be	
  constructed
Zone	
  and	
  PM
Site	
  Utilities	
  and	
  drainage	
  system	
  will	
  not	
  
be	
  adequate	
  for	
  completed	
  buildings.	
  	
  
Affects	
  sites	
  101,	
  102,	
  106,	
  110,	
  111,	
  
112,	
  113,	
  119
High High
MOI	
  to	
  finalize	
  Infrastructure	
  
centralization	
  activities	
  for	
  
Eastern	
  Road	
  Land	
  and	
  Bersha'a	
  
as	
  soon	
  as	
  possible	
  and	
  in	
  the	
  
meanwhile	
  give	
  clear	
  indications
4/9/14-­‐INFO	
  from	
  FCL-­‐
updated:	
  action
Open ACC 15 Scope
Transferable	
  Flooding	
  /	
  Culverts	
  crossing	
  the	
  site
Internal	
  Roads	
  levels	
  for	
  Salboukh	
  Area	
  are	
  required
117
Delay	
  in	
  Design	
  /	
  Construction	
  works
Medium Medium
MOI	
  to	
  decide	
  for	
  external	
  road	
  
elevation
6/26/2014
20/11/14-­‐INFO	
  from	
  
HSA-­‐updated:	
  action
Open ACC 19 Scope
Land	
  deed	
  or	
  Proof	
  document	
  is	
  required	
  and	
  Permit	
  
required	
  for	
  backfilling	
  in	
  sea	
  to	
  confirm	
  location.
122
Delay	
  in	
  taking	
  over	
  the	
  site	
  and	
  finish	
  
date	
  of	
  KAP4
High High
MOI	
  proposed	
  a	
  new	
  location.
Proger	
  submitted	
  an	
  initial	
  
adaptation.
MOI	
  to	
  advise.
4/7/2014 8/9/2014
20/11/14-­‐INFO	
  from	
  
RPE-­‐Updated:action,	
  
RAG
Open PMC 22
Resourcin
g
Missing	
  first	
  line	
  managers	
  for	
  PMC	
  Vice	
  Director	
  to	
  direct	
  
and	
  the	
  PMC	
  employees	
  to	
  do	
  the	
  work.	
  	
  EG	
  Reviewing	
  
Engineers,	
  Quality	
  Assurance	
  and	
  Control	
  Manager Zone	
  and	
  PM
PMC	
  not	
  controlling	
  program	
  and	
  
causing	
  delays	
  and	
  potential	
  extra	
  costs.
High High
PMC	
  Vice	
  Director	
  on	
  board	
  by	
  
26	
  October	
  2014.	
  Recruitment	
  on-­‐
going	
  for	
  remaining	
  Engineering	
  
and	
  Management	
  staff.
4/7/2014 6/30/2014
20/11/14-­‐INFO	
  from	
  
MSC-­‐updated:	
  action
Open ACC 26 Scope
Existing	
  buildings	
  still	
  occupied	
  by	
  EU
118 Construction	
  schedule	
  may	
  be	
  affected Medium Medium
ACC	
  to	
  finalize	
  the	
  installation	
  of	
  
the	
  temporary	
  EU's	
  building.	
  EU	
  
to	
  move	
  there
4/7/2014
26/9/14-­‐INFO	
  from	
  HSA-­‐
updated:	
  action
PMO benefits
q Reporting
17
PMO success criteria
The research indicated that over 75% of organizations that set up a PMO shut it down
within 3 years becauseit didn't demonstrate any addedvalue(Stanleigh(n. d.)).
PMO success factors:
q Support from senior management,
q It should be carefullyPlannedand designed before a decision is made to establish
one
qClear vision regarding the scope of the PMO
q Success to report the benefits of the PMO to the organisation
q Creating added value for the organisation
qClear and accuratereporting to support seniormanagement decisions
qOvercoming changeresistance
q Conducting regular health check andcontinuous improvements.
18
Project failure reasons according to
Lessons learnt
q Awarding projects to the lowest offer withoutlooking at other factors,
q Ambiguity or conflict in project contract,
q Obstacle on project site or permissions,
q Changes in organisation’s strategy, project objectives or end users
requirements,
q Delaying submittals’ approval either by supervision consultant of the
client,
q Delay in decision making,
q Delay in pending issues resolution,
q Cash flow problems,
qLack of professionalism in project management.
19
Recommendations for managing
mega projects
q Verify that the project is the best solution for the problem in hand,
q Use Value Management (VM) to conduct the strategic brief,
q Carry out stakeholders analysis to identify project stakeholders,
q Structure their requirements,
q Validate these requirements,
q Design according to these requirements,
q Test your designs against clients requirements and get their approvals,
q Use the suitable procurement method,
q Prepare a very clear contract documents, e.g. RFP, drawings,
specifications, conditions, etc.
q Doublecheck your tender documents,
20
Recommendations for managing
mega projects (cont.)
q Compare offers according to fair and clear criteria,
q Review the offers to avoid any wrong assumptions or unacceptable
conditions added by vendors,
q Assign professional supervision consultant and client representative,
q Ground clear rules for all parties with clear roles and responsibilities,
q Insure that the project is managed professionally according to best
practices,
q Nominating Change Control Board helps to manage project scope,
q Initiate a steering committee and schedule a monthly project board meeting
to follow up project progress and resolve high level pending issues,
q Be aware that it could be better to manage it as a programme instead of
project,
q Programme Management Office (PMO) will help strongly to follow up the
previous steps and manage professionally projects and programmes.
21
Thanks!
22

More Related Content

What's hot

Chap 4.1- Develop Project Charter
Chap 4.1- Develop Project CharterChap 4.1- Develop Project Charter
Chap 4.1- Develop Project CharterAnand Bobade
 
Managing Project Resources
Managing Project ResourcesManaging Project Resources
Managing Project ResourcesToyin Osunlaja
 
Project portfolio management - webinar
Project portfolio management - webinarProject portfolio management - webinar
Project portfolio management - webinarAli Zeeshan
 
Project Control- Overview Presentation Tafseer
Project Control- Overview Presentation   TafseerProject Control- Overview Presentation   Tafseer
Project Control- Overview Presentation TafseerKishan Solankimbaccepmp
 
Project Quality Management - PMBOK
Project Quality Management - PMBOKProject Quality Management - PMBOK
Project Quality Management - PMBOKArief Rahmana
 
Chapter 1 Introduction to Project Management.ppt
Chapter 1 Introduction to Project Management.pptChapter 1 Introduction to Project Management.ppt
Chapter 1 Introduction to Project Management.pptAhmadTawfigAlRadaide
 
An Introduction To Project Management
An Introduction To Project ManagementAn Introduction To Project Management
An Introduction To Project ManagementAshish Mittal
 
Project integration management
Project integration managementProject integration management
Project integration managementPrabudh Dhingra
 
PMP selected topics and ideas
PMP selected topics and ideasPMP selected topics and ideas
PMP selected topics and ideasAhmad Hamid
 
Il ruolo del Project Manager
Il ruolo del Project ManagerIl ruolo del Project Manager
Il ruolo del Project ManagerEmanuele Rizzo
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project Managementmovinghats
 
Project Management Office Roles Functions And Benefits
Project Management Office Roles Functions And BenefitsProject Management Office Roles Functions And Benefits
Project Management Office Roles Functions And BenefitsMaria Erland, PMP
 
Project Management
Project ManagementProject Management
Project ManagementMark Roman
 

What's hot (20)

Chap 4.1- Develop Project Charter
Chap 4.1- Develop Project CharterChap 4.1- Develop Project Charter
Chap 4.1- Develop Project Charter
 
Managing Project Resources
Managing Project ResourcesManaging Project Resources
Managing Project Resources
 
Project portfolio management - webinar
Project portfolio management - webinarProject portfolio management - webinar
Project portfolio management - webinar
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
Project management
Project managementProject management
Project management
 
Project Management Overview
Project Management OverviewProject Management Overview
Project Management Overview
 
Project management
Project managementProject management
Project management
 
Project Control- Overview Presentation Tafseer
Project Control- Overview Presentation   TafseerProject Control- Overview Presentation   Tafseer
Project Control- Overview Presentation Tafseer
 
Project Quality Management - PMBOK
Project Quality Management - PMBOKProject Quality Management - PMBOK
Project Quality Management - PMBOK
 
PMO - Delivering Business Results
PMO - Delivering Business ResultsPMO - Delivering Business Results
PMO - Delivering Business Results
 
Chapter 1 Introduction to Project Management.ppt
Chapter 1 Introduction to Project Management.pptChapter 1 Introduction to Project Management.ppt
Chapter 1 Introduction to Project Management.ppt
 
An Introduction To Project Management
An Introduction To Project ManagementAn Introduction To Project Management
An Introduction To Project Management
 
Project integration management
Project integration managementProject integration management
Project integration management
 
PMP_Project Cost Management
PMP_Project Cost ManagementPMP_Project Cost Management
PMP_Project Cost Management
 
PMP selected topics and ideas
PMP selected topics and ideasPMP selected topics and ideas
PMP selected topics and ideas
 
Il ruolo del Project Manager
Il ruolo del Project ManagerIl ruolo del Project Manager
Il ruolo del Project Manager
 
The PMO journey
The PMO journeyThe PMO journey
The PMO journey
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project Management
 
Project Management Office Roles Functions And Benefits
Project Management Office Roles Functions And BenefitsProject Management Office Roles Functions And Benefits
Project Management Office Roles Functions And Benefits
 
Project Management
Project ManagementProject Management
Project Management
 

Viewers also liked

Hotec me 2013 seminar g wilkinson viability dist
Hotec me 2013 seminar g wilkinson viability dist Hotec me 2013 seminar g wilkinson viability dist
Hotec me 2013 seminar g wilkinson viability dist PCFC Hotels
 
Excellence through collaboration – the delivery of sustainability in mega pr...
Excellence through collaboration  – the delivery of sustainability in mega pr...Excellence through collaboration  – the delivery of sustainability in mega pr...
Excellence through collaboration – the delivery of sustainability in mega pr...Ibrahim Al-Hudhaif
 
MENA Rail Pioneer Innovative Showcase
MENA Rail Pioneer Innovative ShowcaseMENA Rail Pioneer Innovative Showcase
MENA Rail Pioneer Innovative ShowcaseIbrahim Al-Hudhaif
 
Business Case for Green Buildings
Business Case for Green Buildings Business Case for Green Buildings
Business Case for Green Buildings Ibrahim Al-Hudhaif
 
Performance based contracts in railways ibraheem sheerah
Performance based contracts in railways   ibraheem sheerahPerformance based contracts in railways   ibraheem sheerah
Performance based contracts in railways ibraheem sheerahIbrahim Al-Hudhaif
 
Saudi arabia construction report feb. 2016
Saudi arabia construction report   feb. 2016Saudi arabia construction report   feb. 2016
Saudi arabia construction report feb. 2016Ibrahim Al-Hudhaif
 
Energy Efficient Buildings Codes
Energy Efficient Buildings CodesEnergy Efficient Buildings Codes
Energy Efficient Buildings CodesIbrahim Al-Hudhaif
 
Khutbah keagungan kota makkah
Khutbah keagungan kota makkahKhutbah keagungan kota makkah
Khutbah keagungan kota makkahKhutbah
 
Metro & Light Rail Projects in Saudi Arabia
Metro & Light Rail Projects in Saudi ArabiaMetro & Light Rail Projects in Saudi Arabia
Metro & Light Rail Projects in Saudi ArabiaIbrahim Al-Hudhaif
 
Pioneer Innovation Showcase - EY
Pioneer Innovation Showcase - EYPioneer Innovation Showcase - EY
Pioneer Innovation Showcase - EYIbrahim Al-Hudhaif
 
Energy Efficiency and its Transformative Power
Energy Efficiency and its Transformative Power Energy Efficiency and its Transformative Power
Energy Efficiency and its Transformative Power Ibrahim Al-Hudhaif
 
Innovation Showcase – Bentley’s AssetWise Optram
Innovation Showcase – Bentley’s AssetWise OptramInnovation Showcase – Bentley’s AssetWise Optram
Innovation Showcase – Bentley’s AssetWise OptramIbrahim Al-Hudhaif
 
Trimble Advanced Route Optimization Technology - QUANTM
Trimble Advanced Route Optimization  Technology - QUANTM Trimble Advanced Route Optimization  Technology - QUANTM
Trimble Advanced Route Optimization Technology - QUANTM Ibrahim Al-Hudhaif
 
Light & support industries yanbu
Light & support industries   yanbuLight & support industries   yanbu
Light & support industries yanbuIbrahim Al-Hudhaif
 
Jeddah metro full presentation - Briefing Day March, 30th
Jeddah metro full presentation - Briefing Day March, 30th Jeddah metro full presentation - Briefing Day March, 30th
Jeddah metro full presentation - Briefing Day March, 30th Ibrahim Al-Hudhaif
 
Regional Integrated Supply Chain Strategy for Rail
Regional Integrated Supply Chain  Strategy for Rail Regional Integrated Supply Chain  Strategy for Rail
Regional Integrated Supply Chain Strategy for Rail Ibrahim Al-Hudhaif
 
Oman Rail - in-country value strategic approach
Oman Rail -  in-country value strategic approachOman Rail -  in-country value strategic approach
Oman Rail - in-country value strategic approachIbrahim Al-Hudhaif
 

Viewers also liked (20)

Hotec me 2013 seminar g wilkinson viability dist
Hotec me 2013 seminar g wilkinson viability dist Hotec me 2013 seminar g wilkinson viability dist
Hotec me 2013 seminar g wilkinson viability dist
 
Excellence through collaboration – the delivery of sustainability in mega pr...
Excellence through collaboration  – the delivery of sustainability in mega pr...Excellence through collaboration  – the delivery of sustainability in mega pr...
Excellence through collaboration – the delivery of sustainability in mega pr...
 
Kuwait PPP Transport Projects
Kuwait PPP Transport ProjectsKuwait PPP Transport Projects
Kuwait PPP Transport Projects
 
Gcc railway-plan
Gcc railway-planGcc railway-plan
Gcc railway-plan
 
MENA Rail Pioneer Innovative Showcase
MENA Rail Pioneer Innovative ShowcaseMENA Rail Pioneer Innovative Showcase
MENA Rail Pioneer Innovative Showcase
 
Business Case for Green Buildings
Business Case for Green Buildings Business Case for Green Buildings
Business Case for Green Buildings
 
Performance based contracts in railways ibraheem sheerah
Performance based contracts in railways   ibraheem sheerahPerformance based contracts in railways   ibraheem sheerah
Performance based contracts in railways ibraheem sheerah
 
Agenda
AgendaAgenda
Agenda
 
Saudi arabia construction report feb. 2016
Saudi arabia construction report   feb. 2016Saudi arabia construction report   feb. 2016
Saudi arabia construction report feb. 2016
 
Energy Efficient Buildings Codes
Energy Efficient Buildings CodesEnergy Efficient Buildings Codes
Energy Efficient Buildings Codes
 
Khutbah keagungan kota makkah
Khutbah keagungan kota makkahKhutbah keagungan kota makkah
Khutbah keagungan kota makkah
 
Metro & Light Rail Projects in Saudi Arabia
Metro & Light Rail Projects in Saudi ArabiaMetro & Light Rail Projects in Saudi Arabia
Metro & Light Rail Projects in Saudi Arabia
 
Pioneer Innovation Showcase - EY
Pioneer Innovation Showcase - EYPioneer Innovation Showcase - EY
Pioneer Innovation Showcase - EY
 
Energy Efficiency and its Transformative Power
Energy Efficiency and its Transformative Power Energy Efficiency and its Transformative Power
Energy Efficiency and its Transformative Power
 
Innovation Showcase – Bentley’s AssetWise Optram
Innovation Showcase – Bentley’s AssetWise OptramInnovation Showcase – Bentley’s AssetWise Optram
Innovation Showcase – Bentley’s AssetWise Optram
 
Trimble Advanced Route Optimization Technology - QUANTM
Trimble Advanced Route Optimization  Technology - QUANTM Trimble Advanced Route Optimization  Technology - QUANTM
Trimble Advanced Route Optimization Technology - QUANTM
 
Light & support industries yanbu
Light & support industries   yanbuLight & support industries   yanbu
Light & support industries yanbu
 
Jeddah metro full presentation - Briefing Day March, 30th
Jeddah metro full presentation - Briefing Day March, 30th Jeddah metro full presentation - Briefing Day March, 30th
Jeddah metro full presentation - Briefing Day March, 30th
 
Regional Integrated Supply Chain Strategy for Rail
Regional Integrated Supply Chain  Strategy for Rail Regional Integrated Supply Chain  Strategy for Rail
Regional Integrated Supply Chain Strategy for Rail
 
Oman Rail - in-country value strategic approach
Oman Rail -  in-country value strategic approachOman Rail -  in-country value strategic approach
Oman Rail - in-country value strategic approach
 

Similar to Addressing the challenges of delivering Mega Projects

The role of time, cost and quality in project management
The role of time, cost and quality in project managementThe role of time, cost and quality in project management
The role of time, cost and quality in project managementIRJET Journal
 
60 minutes to pm
60 minutes to pm60 minutes to pm
60 minutes to pmbhashem007
 
PMO and Tollgate Process
PMO and Tollgate Process PMO and Tollgate Process
PMO and Tollgate Process Bob Prieto
 
Basics in Project Management
Basics in Project ManagementBasics in Project Management
Basics in Project Managementchaitanyakrsk
 
Project Life Cycle.pptx
Project Life Cycle.pptxProject Life Cycle.pptx
Project Life Cycle.pptxFawadAfridi6
 
Project Management Methodology
Project Management MethodologyProject Management Methodology
Project Management MethodologyMohammed Al-Taee
 
Project Development Routemap - Infrastructure Foundation Masterclass
Project Development Routemap - Infrastructure Foundation  MasterclassProject Development Routemap - Infrastructure Foundation  Masterclass
Project Development Routemap - Infrastructure Foundation MasterclassCaribbean Development Bank
 
PMO Services Client Annual Review 2015
PMO Services Client Annual Review 2015PMO Services Client Annual Review 2015
PMO Services Client Annual Review 2015Owen Grant
 
Project M&E (unit 1-4)
Project M&E (unit 1-4)Project M&E (unit 1-4)
Project M&E (unit 1-4)Regmi Milan
 
BPP Training on Project Management - Day 1
BPP Training on Project Management - Day 1BPP Training on Project Management - Day 1
BPP Training on Project Management - Day 1Imoh Etuk
 
@CIOBRODY PMO Methodology Overview
@CIOBRODY PMO Methodology Overview@CIOBRODY PMO Methodology Overview
@CIOBRODY PMO Methodology OverviewDaniel Brody
 
Observation Report-CRP-22July-2014
Observation Report-CRP-22July-2014Observation Report-CRP-22July-2014
Observation Report-CRP-22July-2014Rahmat Hashim, PMP
 

Similar to Addressing the challenges of delivering Mega Projects (20)

The role of time, cost and quality in project management
The role of time, cost and quality in project managementThe role of time, cost and quality in project management
The role of time, cost and quality in project management
 
60 minutes to pm
60 minutes to pm60 minutes to pm
60 minutes to pm
 
Project planning: A career path
Project planning: A career pathProject planning: A career path
Project planning: A career path
 
PMO and Tollgate Process
PMO and Tollgate Process PMO and Tollgate Process
PMO and Tollgate Process
 
Pmo
PmoPmo
Pmo
 
Basics in Project Management
Basics in Project ManagementBasics in Project Management
Basics in Project Management
 
Project Life Cycle.pptx
Project Life Cycle.pptxProject Life Cycle.pptx
Project Life Cycle.pptx
 
1 ch1
1 ch11 ch1
1 ch1
 
Project Management Methodology
Project Management MethodologyProject Management Methodology
Project Management Methodology
 
Project Development Routemap - Infrastructure Foundation Masterclass
Project Development Routemap - Infrastructure Foundation  MasterclassProject Development Routemap - Infrastructure Foundation  Masterclass
Project Development Routemap - Infrastructure Foundation Masterclass
 
PMO Services Client Annual Review 2015
PMO Services Client Annual Review 2015PMO Services Client Annual Review 2015
PMO Services Client Annual Review 2015
 
Program management-steps
Program management-stepsProgram management-steps
Program management-steps
 
Project M&E (unit 1-4)
Project M&E (unit 1-4)Project M&E (unit 1-4)
Project M&E (unit 1-4)
 
BPP Training on Project Management - Day 1
BPP Training on Project Management - Day 1BPP Training on Project Management - Day 1
BPP Training on Project Management - Day 1
 
Project mangment
Project mangmentProject mangment
Project mangment
 
UNIT-1.pptx
UNIT-1.pptxUNIT-1.pptx
UNIT-1.pptx
 
@CIOBRODY PMO Methodology Overview
@CIOBRODY PMO Methodology Overview@CIOBRODY PMO Methodology Overview
@CIOBRODY PMO Methodology Overview
 
Observation Report-CRP-22July-2014
Observation Report-CRP-22July-2014Observation Report-CRP-22July-2014
Observation Report-CRP-22July-2014
 
Project managment 1
Project managment 1Project managment 1
Project managment 1
 
Certified Planning Engineer CPE
Certified Planning Engineer CPE Certified Planning Engineer CPE
Certified Planning Engineer CPE
 

More from Ibrahim Al-Hudhaif

Total contract control for rail projects mounir boemond
Total contract control for rail projects   mounir boemondTotal contract control for rail projects   mounir boemond
Total contract control for rail projects mounir boemondIbrahim Al-Hudhaif
 
Understanding the digital commuter etienne chevreau
Understanding the digital commuter   etienne chevreauUnderstanding the digital commuter   etienne chevreau
Understanding the digital commuter etienne chevreauIbrahim Al-Hudhaif
 
Saudi Arabia’s Sustainable Construction Limitations: The Experts’ Views
Saudi Arabia’s Sustainable Construction Limitations:  The Experts’ Views Saudi Arabia’s Sustainable Construction Limitations:  The Experts’ Views
Saudi Arabia’s Sustainable Construction Limitations: The Experts’ Views Ibrahim Al-Hudhaif
 
Current and future Mega Projects in Jubail and Ras Al-Khair Industrial Cities
Current and future Mega Projects in Jubail and Ras Al-Khair Industrial CitiesCurrent and future Mega Projects in Jubail and Ras Al-Khair Industrial Cities
Current and future Mega Projects in Jubail and Ras Al-Khair Industrial CitiesIbrahim Al-Hudhaif
 
Video analytics for public safety solutions - Hitachi
Video analytics for public safety solutions - HitachiVideo analytics for public safety solutions - Hitachi
Video analytics for public safety solutions - HitachiIbrahim Al-Hudhaif
 
Makkah Metro - Makkah Mass Rail Project (MMRP)
Makkah Metro - Makkah Mass Rail Project (MMRP)Makkah Metro - Makkah Mass Rail Project (MMRP)
Makkah Metro - Makkah Mass Rail Project (MMRP)Ibrahim Al-Hudhaif
 
meed projects - gcc mainline network projects
meed projects - gcc mainline network projectsmeed projects - gcc mainline network projects
meed projects - gcc mainline network projectsIbrahim Al-Hudhaif
 
cit- cross-border passenger and freight traffic legal interoperability - Cesa...
cit- cross-border passenger and freight traffic legal interoperability - Cesa...cit- cross-border passenger and freight traffic legal interoperability - Cesa...
cit- cross-border passenger and freight traffic legal interoperability - Cesa...Ibrahim Al-Hudhaif
 
URBAN TRANSPORT, SUSTAINABILITY AND THE ECONOMY
URBAN TRANSPORT,  SUSTAINABILITY AND THE ECONOMY URBAN TRANSPORT,  SUSTAINABILITY AND THE ECONOMY
URBAN TRANSPORT, SUSTAINABILITY AND THE ECONOMY Ibrahim Al-Hudhaif
 
Hitachi Rail - Alistair Dormer
Hitachi Rail - Alistair DormerHitachi Rail - Alistair Dormer
Hitachi Rail - Alistair DormerIbrahim Al-Hudhaif
 
Jordan Hejaz Rail - Abdullah malkawi
Jordan Hejaz Rail - Abdullah malkawi  Jordan Hejaz Rail - Abdullah malkawi
Jordan Hejaz Rail - Abdullah malkawi Ibrahim Al-Hudhaif
 
AL ARRAB CONTRACTING COMPANY PROFILE 2015 English
AL ARRAB CONTRACTING COMPANY PROFILE 2015 English AL ARRAB CONTRACTING COMPANY PROFILE 2015 English
AL ARRAB CONTRACTING COMPANY PROFILE 2015 English Ibrahim Al-Hudhaif
 
AL ARRAB CONTRACTING COMPANY PROFILE 2015 Arabic
AL ARRAB CONTRACTING COMPANY PROFILE 2015 Arabic AL ARRAB CONTRACTING COMPANY PROFILE 2015 Arabic
AL ARRAB CONTRACTING COMPANY PROFILE 2015 Arabic Ibrahim Al-Hudhaif
 
Public services yanbu industrial city
Public services   yanbu industrial cityPublic services   yanbu industrial city
Public services yanbu industrial cityIbrahim Al-Hudhaif
 

More from Ibrahim Al-Hudhaif (17)

Total contract control for rail projects mounir boemond
Total contract control for rail projects   mounir boemondTotal contract control for rail projects   mounir boemond
Total contract control for rail projects mounir boemond
 
Understanding the digital commuter etienne chevreau
Understanding the digital commuter   etienne chevreauUnderstanding the digital commuter   etienne chevreau
Understanding the digital commuter etienne chevreau
 
Saudi Arabia’s Sustainable Construction Limitations: The Experts’ Views
Saudi Arabia’s Sustainable Construction Limitations:  The Experts’ Views Saudi Arabia’s Sustainable Construction Limitations:  The Experts’ Views
Saudi Arabia’s Sustainable Construction Limitations: The Experts’ Views
 
Current and future Mega Projects in Jubail and Ras Al-Khair Industrial Cities
Current and future Mega Projects in Jubail and Ras Al-Khair Industrial CitiesCurrent and future Mega Projects in Jubail and Ras Al-Khair Industrial Cities
Current and future Mega Projects in Jubail and Ras Al-Khair Industrial Cities
 
Saudi Talent in Mega Projects
Saudi Talent in Mega ProjectsSaudi Talent in Mega Projects
Saudi Talent in Mega Projects
 
Video analytics for public safety solutions - Hitachi
Video analytics for public safety solutions - HitachiVideo analytics for public safety solutions - Hitachi
Video analytics for public safety solutions - Hitachi
 
Makkah Metro - Makkah Mass Rail Project (MMRP)
Makkah Metro - Makkah Mass Rail Project (MMRP)Makkah Metro - Makkah Mass Rail Project (MMRP)
Makkah Metro - Makkah Mass Rail Project (MMRP)
 
meed projects - gcc mainline network projects
meed projects - gcc mainline network projectsmeed projects - gcc mainline network projects
meed projects - gcc mainline network projects
 
cit- cross-border passenger and freight traffic legal interoperability - Cesa...
cit- cross-border passenger and freight traffic legal interoperability - Cesa...cit- cross-border passenger and freight traffic legal interoperability - Cesa...
cit- cross-border passenger and freight traffic legal interoperability - Cesa...
 
URBAN TRANSPORT, SUSTAINABILITY AND THE ECONOMY
URBAN TRANSPORT,  SUSTAINABILITY AND THE ECONOMY URBAN TRANSPORT,  SUSTAINABILITY AND THE ECONOMY
URBAN TRANSPORT, SUSTAINABILITY AND THE ECONOMY
 
Hitachi Rail - Alistair Dormer
Hitachi Rail - Alistair DormerHitachi Rail - Alistair Dormer
Hitachi Rail - Alistair Dormer
 
Jordan Hejaz Rail - Abdullah malkawi
Jordan Hejaz Rail - Abdullah malkawi  Jordan Hejaz Rail - Abdullah malkawi
Jordan Hejaz Rail - Abdullah malkawi
 
AL ARRAB CONTRACTING COMPANY PROFILE 2015 English
AL ARRAB CONTRACTING COMPANY PROFILE 2015 English AL ARRAB CONTRACTING COMPANY PROFILE 2015 English
AL ARRAB CONTRACTING COMPANY PROFILE 2015 English
 
AL ARRAB CONTRACTING COMPANY PROFILE 2015 Arabic
AL ARRAB CONTRACTING COMPANY PROFILE 2015 Arabic AL ARRAB CONTRACTING COMPANY PROFILE 2015 Arabic
AL ARRAB CONTRACTING COMPANY PROFILE 2015 Arabic
 
Yanbu industrial city plan
Yanbu industrial city planYanbu industrial city plan
Yanbu industrial city plan
 
Real Estate Development Yanbu
Real Estate Development YanbuReal Estate Development Yanbu
Real Estate Development Yanbu
 
Public services yanbu industrial city
Public services   yanbu industrial cityPublic services   yanbu industrial city
Public services yanbu industrial city
 

Recently uploaded

High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 

Recently uploaded (20)

High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 

Addressing the challenges of delivering Mega Projects

  • 1. Addressing the challenges of delivering Mega Projects DR. MOHAMMED ALALSHIKH, PHD, PMP, AVS CERTIFIED MOR, MSP & PRINCE2 PRACTITIONER SAUDI MEGA PROJECTS CONFERENCE 2015, RIYADH 1
  • 2. Outlines q Introduction, q Best practices in project management q Obstacles that hinder deliveringmega projects q Lessons learnt from mega project management & Recommendations q The Government’s PMO initiative q Conclusions 2
  • 3. Definitions A project is temporary organisation that is created for the purpose of delivering one or more business outputs according to a specified business case. A mega project is an extremely large-scale investment project, and is typically defined as costing more than US $1 billion and attracting a lot of public attention because of substantial impacts on communities, environment and budgets. Mega projects can also be defined as "initiatives that are physical, very expensive, and public”. (Wikipedia,2015) 3
  • 4. Activities that should be managed in the project v Scope: What is the project? And how is it defined? v Procurement: Which kind of contractual and organisational route will be used? v Planning and progress: Analyse the project and set a plan of action to therefore control its progress. v Time: Identifya project timetable and how it will be implemented. v Cost: What is the budget and how will it be managed? v Quality: Determinationof standards and their observance. v People: Individual managers and project teams. v Risk: What are the risks, who carries them, and how can they be avoided or mitigated? (Woodward, 1997) 4
  • 5. Ability to change 10/3/2010 5 Client value stair Client values pyramid Clientsatisfaction VM/VE interventions Value steps Peak of client satisfaction Project performance specifications and project brief Project designs and technical solutions Project construction Project strategic fit and strategic brief Abilitytochangedecreases VE4 VE3 VM2 VM1 Changecostincreases Ref.:  (Alalshikh,   2010)
  • 6. Project failure 6 q According to the Standish CHAOS Report (2009): q 68% of software projects do not meet time/cost/scope targets. q Only 32% of projects were completed on time, within budget and delivered measurable business and stakeholder benefits.
  • 7. Project failure reasons q There are many reasons for such failures. As per a PricewaterhouseCoopers survey of 1,524 organizations: Ø inadequate project estimating andplanning constitutes 30% of project failures, Ølack of executive sponsorship constitutes 16% , Øand poorly defined goals andobjectives constitutes 12%. ØAlso it found that using established project management approaches increased success as measured by a project's key performance indicators of quality, scope, schedule, budgets and benefits, ØThe survey indicates that operating an established PMO is one of the top three reasons that drives successful project delivery. 7
  • 8. Causes for project failure 1. Ambiguous client objectives and brief. 2. Lack of understanding of team roles, responsibilitiesand competencies. 3. Poorly thought out management structures, lines of authority and communication. 4. Funding and business issues including changing market circumstances. 5. Sub-optimal information release, decision-making in terms of timing and adequacy. 6. Third party influences. 7. Difficulties obtaining satisfactoryplanning and statutory approvals. 8. Troubles during construction suchas site issuesand the weather or ground conditions. 9. Unresolved design issues. 10. Contractor capability and solvency. 11. Operational faultsafter handover. 12. Natural or manmade disasters (force majeure) (Dallas, 2004) . 8
  • 9. Mega project management q Projects failure can be attributedto different reasons as mentioned before. Lack of experience and knowledge in professional project management is one of the main reasons. q Abundance of mega projects in Saudi Arabia stipulates: Ø Initiating PMO in organisations, which will ground the rules for project management and enhance project managers capabilities. ØApplication of project management best practices is essential, in order to deliver success projects. Otherwise, projects will fail to meet client values and end users requirements. q The Government’s PMO initiative will contribute in overcoming these obstacles. 9
  • 10. Best practices in project management q Professionalismis crucial to conduct projects successfully q Examples of best practices: q Project management using PMI approach (PMP) or APM approach (PRINCE2), q Programme management, e.g. MSP (APM approach or PMI methodology), q Initiating P3O or PMO, q Etc. 10
  • 11. Portfolio/ Programme/ Project Management Office (P3O/ PMO) q Project management office (PMO) is a group or department that develops, maintains and promotes project management standards within the organisation. It standardizes project management processes, tools, techniques, reports, forms and templates. q It is a strategic driver for organisational excellence, q It improves organisationproject management capabilities and increasessuccess in implementing projects, q It offers continuous improvements of project management infrastructure based on improving capabilities and changing organisational culture towards project management maturity model, q It is the source of documentation, guidanceand metricsin practice of project management and execution. 11
  • 12. Benefits achieved using the PMO q Stronger collaboration between projects and knowledgesharing q Managing shared resources across all projects q Developing project management methodology, best practices, policy, and standards q Developing and managing project, procedures, tools, techniques, templates, forms and other shared documentations q Managing Risk and Issues at a programme level by allocating dedicated specialist in the PMO to deal with particular risks and Issues – avoids duplication q Prototype design approval in one project, is cascaded to other similar project to speed up the approval process 12
  • 13. Benefits achieved using PMO q Share lessons learnt across all projects, to avoid problem repeating other projects q Manage dependencies across projects effectively and efficiently, by implementing a programme schedule q Compare progress and performance across projects, and investigating common delays and bottlenecks q Coordinating communication across projects q Assigning, qualifying and mentoring project managers through a defined career path q Establish a project review function (auditing and health check) q Save project managers time by supplying them with forms, template, tools and techniques. 13
  • 15. PMO benefits q Programme Policies & Procedures q Programme Schedule q Dependencies Log 15
  • 16. PMO benefits q Risks & Issues management 16 Program Issue Register - November 2014 Risk ID# Project Name Category Brief Risk Description Risk Impact Mitigation Actions / Risk Response Probability Level Impact Level Calculated Risk (automated ) Status Entry Date Planned Resolution Date Update / Comments 3 SFMCP  -­‐  J TIMING Missing  NOC's  (leading  to  missing   building  permits  and  future  utility   connections)  has  prevented   construction  start  and  could  delay   project  completion Project  Delay MOI  need  to  issue  official  letters  to   relevant  Local  Authorities  per  "NOCs  list   included  in  contractor's  monthly  report"   ,  as  early  as  possible High Very  High 20 Open 30-­‐Sep-­‐13 31-­‐Dec-­‐14 Mitigation  Plan  reviewed  on  Oct  2014 6 SFMCP  -­‐  J COST Potentially  reduced  control  over   evaluation  of  requested  changes   due  to  revisions  of  original  BoQ   during  tender Project  Cost  Increase Continual  Pressure  on  SBG  to  expedite   the  submission  of  BoQ Very  High High 20 Open 30-­‐Sep-­‐13 ASAP Meeting  Minutes  22-­‐01-­‐2014,  our  letters  MB0B00-­‐ 00LB0240/243/260,  dated  2/9/2014,  11/9/2014,  &   29/10/2014  -­‐  SBG  Letter  No  BB0B00-­‐00LM0125,  dated   6/11/2014 8 SFMCP  -­‐  JPERFORMANCE/COST potential  Cost  implication  &  poor   equipment's  quality  due  to   Medical  equipment  list  contains   outdated  or  obsolete  equipment,   new  models  require  different  built   conditions  (regardless  of  who   buys  it) Poor  Equipment  Quality/Project   Cost  increase client  decided  to  hire  a  3rd  party  to   review  &  prepare  an  updated  list  ,  keep   close  attention Medium Medium 9 Open ######## 31-­‐Dec-­‐14 Highlighted  in  presentation  to  MOI  on  19/05/2014,  another   presentation  on  July  2014  mentioned  that  deadline  to  hire  the   3rd  party  is  Sept  14th  2014 9 SFMCP  -­‐  J TIMING Contractor's  delay  in  activating   the  mobilization  and,  in  particular,   the  project  control  system  PCM   can  further  compromise  project   start-­‐up  and  efficiency. Project  Delay Continual  pressure  on  the  contractors  to   accelerate  the  mobilization Medium Low 6 Open ######## 31-­‐Dec-­‐14 On  18  May  MT  sent  another  letter  to  SBG  in  breech  of  contract 11 SFMCP  -­‐  J COORDINATION Potential  Difficult  communication   and  coordination  caused  by  lack   of  collaboration  with  Engineer's   directions Delay  in  completing  the  activities   on  time  hence  overall  project  Delay MT  to  keep  reminding  Contractor  for  his   contractual  obligation  &  must  conform   to  operating  procedures Medium Medium 9 Open 30-­‐Sep-­‐13 ASAP Program Issue Register - November 2014 Status Project name Project Risk ID# / Reference Category Brief Issue Description Projects Affected Impact Description Issue Type Impact Level Mitigation Actions Entry Date Planned Resolution Date Current Status / Comments Open ACC 8 Scope Quality  of  Contractor's  Submittals  is  inadequate.    Poor   sequencing  as  in  Calculations  >  Equipment  and  Materials  >   Drawings.    Also  poor  coordination  between  trades,  e.g.   between  mechanical,  electrical  and  architectural.  Example   is  structural  drawing  approval  requested  before  lift   supplier  and  equipment  specification  approved. WBSL-­‐1 Quality  and  Time  and  Impact High Medium Technical  Submissions  to  agreed   standards,  sequence  and   demonstrate  coordination,   including  of  utilities  trenches  and   ducts. Drawings  must  be  organised  ,   listing  ,  all  submission  clearly   identified  as  per  Submittal  Logs.   The  latter  should  be  re-­‐edited  and   updated  periodically. 22/12/13 6/26/2014 30/10/14-­‐INFO  from   MSC-­‐updated:action Open Program 10 Scope Changes  in  Project  site  locations  (see  also  issues  19,  33   and  39) 104 109 122 Delay  in  taking  over  the  sites Medium Medium MOI  to  finalize  master  plans  with   final  project  site  locations STC  Ar'ar  &  Aseer/Abha,   Infrastructure  Central   District,  STC  Jeddah 30/11/14-­‐INFO  from   MSC-­‐updated:  action Open Program 12 Scope New  Infrastructure  Master  plan  for  Eastern  Road  Land   and  Bersha'a -­‐  An  integrated  storm  water  protection  for  various  project   sites  at  Eastern  Road  Land  are  required -­‐  Water  supply,  electricity  and  Sewerage  drainage  is   required.  Asnd  Road  network  need  to  be  constructed Zone  and  PM Site  Utilities  and  drainage  system  will  not   be  adequate  for  completed  buildings.     Affects  sites  101,  102,  106,  110,  111,   112,  113,  119 High High MOI  to  finalize  Infrastructure   centralization  activities  for   Eastern  Road  Land  and  Bersha'a   as  soon  as  possible  and  in  the   meanwhile  give  clear  indications 4/9/14-­‐INFO  from  FCL-­‐ updated:  action Open ACC 15 Scope Transferable  Flooding  /  Culverts  crossing  the  site Internal  Roads  levels  for  Salboukh  Area  are  required 117 Delay  in  Design  /  Construction  works Medium Medium MOI  to  decide  for  external  road   elevation 6/26/2014 20/11/14-­‐INFO  from   HSA-­‐updated:  action Open ACC 19 Scope Land  deed  or  Proof  document  is  required  and  Permit   required  for  backfilling  in  sea  to  confirm  location. 122 Delay  in  taking  over  the  site  and  finish   date  of  KAP4 High High MOI  proposed  a  new  location. Proger  submitted  an  initial   adaptation. MOI  to  advise. 4/7/2014 8/9/2014 20/11/14-­‐INFO  from   RPE-­‐Updated:action,   RAG Open PMC 22 Resourcin g Missing  first  line  managers  for  PMC  Vice  Director  to  direct   and  the  PMC  employees  to  do  the  work.    EG  Reviewing   Engineers,  Quality  Assurance  and  Control  Manager Zone  and  PM PMC  not  controlling  program  and   causing  delays  and  potential  extra  costs. High High PMC  Vice  Director  on  board  by   26  October  2014.  Recruitment  on-­‐ going  for  remaining  Engineering   and  Management  staff. 4/7/2014 6/30/2014 20/11/14-­‐INFO  from   MSC-­‐updated:  action Open ACC 26 Scope Existing  buildings  still  occupied  by  EU 118 Construction  schedule  may  be  affected Medium Medium ACC  to  finalize  the  installation  of   the  temporary  EU's  building.  EU   to  move  there 4/7/2014 26/9/14-­‐INFO  from  HSA-­‐ updated:  action
  • 18. PMO success criteria The research indicated that over 75% of organizations that set up a PMO shut it down within 3 years becauseit didn't demonstrate any addedvalue(Stanleigh(n. d.)). PMO success factors: q Support from senior management, q It should be carefullyPlannedand designed before a decision is made to establish one qClear vision regarding the scope of the PMO q Success to report the benefits of the PMO to the organisation q Creating added value for the organisation qClear and accuratereporting to support seniormanagement decisions qOvercoming changeresistance q Conducting regular health check andcontinuous improvements. 18
  • 19. Project failure reasons according to Lessons learnt q Awarding projects to the lowest offer withoutlooking at other factors, q Ambiguity or conflict in project contract, q Obstacle on project site or permissions, q Changes in organisation’s strategy, project objectives or end users requirements, q Delaying submittals’ approval either by supervision consultant of the client, q Delay in decision making, q Delay in pending issues resolution, q Cash flow problems, qLack of professionalism in project management. 19
  • 20. Recommendations for managing mega projects q Verify that the project is the best solution for the problem in hand, q Use Value Management (VM) to conduct the strategic brief, q Carry out stakeholders analysis to identify project stakeholders, q Structure their requirements, q Validate these requirements, q Design according to these requirements, q Test your designs against clients requirements and get their approvals, q Use the suitable procurement method, q Prepare a very clear contract documents, e.g. RFP, drawings, specifications, conditions, etc. q Doublecheck your tender documents, 20
  • 21. Recommendations for managing mega projects (cont.) q Compare offers according to fair and clear criteria, q Review the offers to avoid any wrong assumptions or unacceptable conditions added by vendors, q Assign professional supervision consultant and client representative, q Ground clear rules for all parties with clear roles and responsibilities, q Insure that the project is managed professionally according to best practices, q Nominating Change Control Board helps to manage project scope, q Initiate a steering committee and schedule a monthly project board meeting to follow up project progress and resolve high level pending issues, q Be aware that it could be better to manage it as a programme instead of project, q Programme Management Office (PMO) will help strongly to follow up the previous steps and manage professionally projects and programmes. 21