SlideShare a Scribd company logo
1 of 20
see attachment:
1. A key objective of change control in configuration
management is to keep track of actions taken in response to
change requests.
[removed]
a. true
[removed]
b. false
Q2. A key weakness of the Benefit-Cost ratio project selection
mechanism is that:
[removed]
a. It only focuses on things that can be measured
[removed]
b. It takes time frame into consideration
[removed]
c. It is too much based on subjective judgment
[removed]
d. It does not entail prioritizing
Q3. Good functional requirements
[removed]
a. Describe how the deliverable should be developed
[removed]
b. Provide detailed technical insights into what the
deliverable will do
[removed]
c. Describe what the deliverable looks like and what it should
do
[removed]
d. Are created after development of the technical
specifications
Q4. A project can be terminated prematurely because the
original objectives may no longer be valid.
[removed]
a. true
[removed]
b. false
Q5. A tool that graphically shows cost variance is:
[removed]
a. A chart of accounts
[removed]
b. A code of accounts
[removed]
c. A histogram (also called a resource loading chart)
[removed]
d. A cumulative cost curve (also called S-curve)
Q6. In resource planning, one of the issues that needs to be
considered is:
[removed]
a. Staff empowerment
[removed]
b. Technical requirements of the project
[removed]
c. Theory X management principles
[removed]
d. Theory Y management principles
Q7. When crashing a project, we typically choose critical path
tasks whose costs of crashing are highest.
[removed]
a. true
[removed]
b. false
Q8. The poor man's hierarchy is a method for:
[removed]
a. Project estimation
[removed]
b. Project scheduling
[removed]
c. WBS construction
[removed]
d. Project selection
Q9. Ensuring a one-to-one correspondence between
specification items and general design items is a feature of:
[removed]
a. Scope statement definition
[removed]
b. WBS construction
[removed]
c. Rapid prototyping
[removed]
d. Configuration management
Q10. The astute project manager typically uses only one
management style in order not to confuse his/her teammates.
[removed]
a. true
[removed]
b. false
Q11. Structured Walk-Through is a methodology used in:
[removed]
a. PERT
[removed]
b. GERT
[removed]
c. VERT
[removed]
d. Project Evaluation
Q12. If EV = $300, AC = $400, and the project budget is
$1,000, what is the estimated final cost of the project (this is
known as EAC, estimate at complete)?
[removed]
a. $750
[removed]
b. $1,000
[removed]
c. $1,250
[removed]
d. $1,333
Q13. If review of a project's status indicates that EV = $400,
AC = $400, and PV = $500, the project is:
[removed]
a. On budget, behind schedule
[removed]
b. On budget, ahead of schedule
[removed]
c. Over budget, behind schedule
[removed]
d. Over budget, ahead of schedule
Q14. In project management, the level of uncertainty plays a
major role in determining the adequacy of a project plan.
[removed]
a. true
[removed]
b. false
Q15. The purpose of mid-project evaluation is:
[removed]
a. Continual monitoring of budget and estimates
[removed]
b. To focus on achievement of individual element of the
project plan
[removed]
c. To determine whether the original objectives are still
relevant
[removed]
d. To re-baseline the project budget
Q16. Confidence in the accuracy of a cost estimate increases
when top-down and bottom-up estimates converge.
[removed]
a. true
[removed]
b. false
Q17. Milestones, like tasks, consume resources.
[removed]
a. true
[removed]
b. false
Q18. A project team structure that closely reflects the physical
structure of the deliverable is known as:
[removed]
a. Egoless
[removed]
b. Specialty
[removed]
c. Surgical
[removed]
d. Isomorphic
Q19. Which of the following is an example of a project?
[removed]
a. Maintaining e-mail addresses
[removed]
b. Capacity planning
[removed]
c. Submitting travel and expense reports
[removed]
d. Sending monthly reports to top management
Q20. The critical path:
[removed]
a. Provides the duration of a project
[removed]
b. Has the shortest duration on a project
[removed]
c. Is the most expensive path to implement
[removed]
d. Contains the project's most significant tasks
Q21. In risk management, insurance is an example of:
[removed]
a. Risk avoidance
[removed]
b. Risk deflection
[removed]
c. Risk acceptance
[removed]
d. Contingency planning
Q22. The bottom-most level of the WBS -- the level at which
project budget and schedule data are captured -- is called:
[removed]
a. Work package
[removed]
b. Code of accounts
[removed]
c. Budget baseline
[removed]
d. Change control level
Q23. What is the function of a change control board (CCB) in
configuration management?
[removed]
a. To assess the management impacts of change requests
[removed]
b. To initiate changes needed on the project
[removed]
c. To focus on the technical implication of change requests
[removed]
d. To approve change requests coming from senior
management
Q24. A major strength of task Gantt charts is that they can:
[removed]
a. Offer a sophisticated model of a project
[removed]
b. Show how many resources will be used on the project
[removed]
c. Show the interdependencies of tasks
[removed]
d. Show actual versus planned schedule status
Q25. Functional requirements provide us with detailed technical
specifications.
[removed]
a. true
[removed]
b. false
Q26. A laissez-faire management style may lead to a ship
without rudder syndrome.
[removed]
a. true
[removed]
b. false
Q27. The resource planning tool that enables us to identify who
we need to carry out what tasks is called:
[removed]
a. A resource Gantt chart
[removed]
b. A resource matrix (also called the responsibility chart)
[removed]
c. A resource ogive
[removed]
d. A resource loading chart (also called a resource histogram)
Q28. When we have objective data on the probability of an
event, we are involved with decision making under certainty.
[removed]
a. true
[removed]
b. false
Q29. Which of the following is a scope planning tool?
[removed]
a. Benefit/cost analysis
[removed]
b. WBS
[removed]
c. Earned Value analysis
[removed]
d. Fast tracking
Q30. The Theory X approach to managing workers is a classic
example of a top-down view of how people should be managed.
[removed]
a. true
[removed]
b. false
Q31. Scope creep means:
[removed]
a. Needs emergence and identification
[removed]
b. Uncontrolled changes to a project's requirements during
project execution
[removed]
c. Migration of project needs to requirements
[removed]
d. Imprecise scope statement
Q32. An objective of prototyping is to minimize life-cycle cost.
[removed]
a. true
[removed]
b. false
Q33. Concurrent engineering involves overlapping tasks and
phases to accelerate a project's schedule.
[removed]
a. true
[removed]
b. false
Q34. Bottom-up estimates:
[removed]
a. Are based on historical trends
[removed]
b. Can be derived from the WBS
[removed]
c. Must employ Monte Carlo simulation
[removed]
d. a and c
Q35. Using working time or elapsed time to calculate the time it
will take to complete a task produces the same results.
[removed]
a. true
[removed]
b. false
Q36. There is a definite link between the level of risk an
enterprise encounters and project time frame.
[removed]
a. true
[removed]
b. false
Q37. A modern view in Human Resource Management is that
positive motivation results from an opportunity to achieve and
experience self-actualization.
[removed]
a. true
[removed]
b. false
Q38. The type of management whose focus is on activities
whose variances lie outside the acceptable range is:
[removed]
a. Management by Objectives
[removed]
b. Management by Exception
[removed]
c. Management by Walking Around
[removed]
d. Management by Control Limits
Q39. Which of the following shows resource allocation over
time?
[removed]
a. Resource Gantt chart
[removed]
b. Resource matrix
[removed]
c. S-Curve
[removed]
d. Resource leveling
Q40. Which of the following is a characteristic of an effective
reporting system?
[removed]
a. SMART
[removed]
b. KISS
[removed]
c. MBO
[removed]
d. LOWBALLING
Q41. If the latest time you can start a task is five hours into the
project, and the earliest time is three and a half hours into the
project, how much slack (also called float) does the task have?
[removed]
a. 0.5 hours
[removed]
b. 1.5 hours
[removed]
c. 2.5 hours
[removed]
d. 8.5 hours
Q42. Internal Rate of Return (IRR) is the discount rate that sets
the present value of cash outflow equal to the present value of
cash inflow.
[removed]
a. true
[removed]
b. false
Q43. Configuration management is a:
[removed]
a. Methodology for working closely with customers by
developing and updating requirements for faster response to
changing customer needs
[removed]
b. Methodology for ensuring that requirements evolve with
evolving customer requirements
[removed]
c. Methodology for specifying requirements at the outset and
for controlling very tightly any changes to them
[removed]
d. Methodology for specifying requirements at the outset and
for facilitating any changes to them with minimum customer
input
Q44. According to PMI, a WBS should focus on
[removed]
a. Tasks
[removed]
b. Deliverables
[removed]
c. Interrelationships among activities
[removed]
d. Cost of the project
Q45. Under what conditions may a project manager accept a
change request?
[removed]
a. If the request has no effect on project objectives, deadlines,
or resources
[removed]
b. If the request has no effect on project objectives, although
it has effects on deadlines and resources
[removed]
c. If the request is coming from a valued customer
[removed]
d. If the request is from the Chief Executive Officer
Q46. Which of the following methods involves performing tasks
in parallel?
[removed]
a. Crashing
[removed]
b. Fast tracking
[removed]
c. Leveling
[removed]
d. Hammocking
Q47. Top-down estimates (also called parametric estimates):
[removed]
a. Are based on historical trends
[removed]
b. Can be derived from the WBS
[removed]
c. Can be determined by analyzing work packages
[removed]
d. Provide accurate assessments of project costs
Q48. Under rapid prototyping (also called application
prototyping), the customer actually sees and works with the
deliverable as it evolves.
[removed]
a. true
[removed]
b. false
Q49. Definitive estimates are generally derived from:
[removed]
a. Bottom-up estimates
[removed]
b. Top-down estimates
[removed]
c. Expert judgment cost estimates
[removed]
d. Order of magnitude estimates
Q50. An effective project manager must:
[removed]
a. Tell his team members what to do
[removed]
b. Be the most capable person on the team technically
[removed]
c. Be focused on achieving results
[removed]
d. Not trust his team members to achieve results without his
personal attention to detail

More Related Content

Similar to Change Management and Project Tracking

1.            This Project Management concept ensures the various e.pdf
1.            This Project Management concept ensures the various e.pdf1.            This Project Management concept ensures the various e.pdf
1.            This Project Management concept ensures the various e.pdfsuhshbhosale
 
MGT150. PROJECT MANAGEMENT (MGT150) TAKE ASSESSMENT FINAL EXAM.docx
MGT150. PROJECT MANAGEMENT (MGT150)  TAKE ASSESSMENT FINAL EXAM.docxMGT150. PROJECT MANAGEMENT (MGT150)  TAKE ASSESSMENT FINAL EXAM.docx
MGT150. PROJECT MANAGEMENT (MGT150) TAKE ASSESSMENT FINAL EXAM.docxannandleola
 
1440 pmp exam question bank
1440 pmp exam question bank1440 pmp exam question bank
1440 pmp exam question bankBaskar El
 
Mb0049 (2) May 2012 Master of Business Administration - MBA Semester 2 MB0049...
Mb0049 (2) May 2012 Master of Business Administration - MBA Semester 2 MB0049...Mb0049 (2) May 2012 Master of Business Administration - MBA Semester 2 MB0049...
Mb0049 (2) May 2012 Master of Business Administration - MBA Semester 2 MB0049...Devendra Kachhi
 
Introduction to Project Management
Introduction to Project Management Introduction to Project Management
Introduction to Project Management Joshua Miranda
 
Gonzales.matthew
Gonzales.matthewGonzales.matthew
Gonzales.matthewNASAPMC
 
Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800PRIYANSHU KUMAR
 
PROJ 586 RANK Education Counseling--proj586rank.com
PROJ 586 RANK Education Counseling--proj586rank.comPROJ 586 RANK Education Counseling--proj586rank.com
PROJ 586 RANK Education Counseling--proj586rank.comvenkat60045
 
Project Management - Which of the following is not a suggestion for performin...
Project Management - Which of the following is not a suggestion for performin...Project Management - Which of the following is not a suggestion for performin...
Project Management - Which of the following is not a suggestion for performin...Suma Kamadod
 
Project Management - __________________ is a network diagramming technique ...
Project Management -   __________________ is a network diagramming technique ...Project Management -   __________________ is a network diagramming technique ...
Project Management - __________________ is a network diagramming technique ...Suma Kamadod
 
Project Management - Project manager is responsible for a) overseeing change ...
Project Management - Project manager is responsible for a) overseeing change ...Project Management - Project manager is responsible for a) overseeing change ...
Project Management - Project manager is responsible for a) overseeing change ...Suma Kamadod
 
Project Management - _________________ is known for his work on quality con...
Project Management -   _________________ is known for his work on quality con...Project Management -   _________________ is known for his work on quality con...
Project Management - _________________ is known for his work on quality con...Suma Kamadod
 

Similar to Change Management and Project Tracking (20)

1.            This Project Management concept ensures the various e.pdf
1.            This Project Management concept ensures the various e.pdf1.            This Project Management concept ensures the various e.pdf
1.            This Project Management concept ensures the various e.pdf
 
Ganesh
GaneshGanesh
Ganesh
 
Ganesh
GaneshGanesh
Ganesh
 
MGT150. PROJECT MANAGEMENT (MGT150) TAKE ASSESSMENT FINAL EXAM.docx
MGT150. PROJECT MANAGEMENT (MGT150)  TAKE ASSESSMENT FINAL EXAM.docxMGT150. PROJECT MANAGEMENT (MGT150)  TAKE ASSESSMENT FINAL EXAM.docx
MGT150. PROJECT MANAGEMENT (MGT150) TAKE ASSESSMENT FINAL EXAM.docx
 
1440 pmp exam question bank
1440 pmp exam question bank1440 pmp exam question bank
1440 pmp exam question bank
 
150 PMP Questions
150 PMP Questions 150 PMP Questions
150 PMP Questions
 
Outage planning
Outage planningOutage planning
Outage planning
 
PROJ 586 Entire Course NEW
PROJ 586 Entire Course NEWPROJ 586 Entire Course NEW
PROJ 586 Entire Course NEW
 
Cost studies model_answers_2014_jan
Cost studies model_answers_2014_janCost studies model_answers_2014_jan
Cost studies model_answers_2014_jan
 
Session 6 gdas pmp study group presentation
Session 6   gdas pmp study group presentationSession 6   gdas pmp study group presentation
Session 6 gdas pmp study group presentation
 
Chap03
Chap03Chap03
Chap03
 
Mb0049 (2) May 2012 Master of Business Administration - MBA Semester 2 MB0049...
Mb0049 (2) May 2012 Master of Business Administration - MBA Semester 2 MB0049...Mb0049 (2) May 2012 Master of Business Administration - MBA Semester 2 MB0049...
Mb0049 (2) May 2012 Master of Business Administration - MBA Semester 2 MB0049...
 
Introduction to Project Management
Introduction to Project Management Introduction to Project Management
Introduction to Project Management
 
Gonzales.matthew
Gonzales.matthewGonzales.matthew
Gonzales.matthew
 
Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800
 
PROJ 586 RANK Education Counseling--proj586rank.com
PROJ 586 RANK Education Counseling--proj586rank.comPROJ 586 RANK Education Counseling--proj586rank.com
PROJ 586 RANK Education Counseling--proj586rank.com
 
Project Management - Which of the following is not a suggestion for performin...
Project Management - Which of the following is not a suggestion for performin...Project Management - Which of the following is not a suggestion for performin...
Project Management - Which of the following is not a suggestion for performin...
 
Project Management - __________________ is a network diagramming technique ...
Project Management -   __________________ is a network diagramming technique ...Project Management -   __________________ is a network diagramming technique ...
Project Management - __________________ is a network diagramming technique ...
 
Project Management - Project manager is responsible for a) overseeing change ...
Project Management - Project manager is responsible for a) overseeing change ...Project Management - Project manager is responsible for a) overseeing change ...
Project Management - Project manager is responsible for a) overseeing change ...
 
Project Management - _________________ is known for his work on quality con...
Project Management -   _________________ is known for his work on quality con...Project Management -   _________________ is known for his work on quality con...
Project Management - _________________ is known for his work on quality con...
 

More from kaylee7wsfdubill

Seeking a complete Excel spreadsheet with cell equations, and answer.docx
Seeking a complete Excel spreadsheet with cell equations, and answer.docxSeeking a complete Excel spreadsheet with cell equations, and answer.docx
Seeking a complete Excel spreadsheet with cell equations, and answer.docxkaylee7wsfdubill
 
see the attachmentA. Describe each of the three components in th.docx
see the attachmentA. Describe each of the three components in th.docxsee the attachmentA. Describe each of the three components in th.docx
see the attachmentA. Describe each of the three components in th.docxkaylee7wsfdubill
 
See the questions belowA. As you choose a culture or cultu.docx
See the questions belowA. As you choose a culture or cultu.docxSee the questions belowA. As you choose a culture or cultu.docx
See the questions belowA. As you choose a culture or cultu.docxkaylee7wsfdubill
 
Security of Health Care RecordsWith the increase of health informa.docx
Security of Health Care RecordsWith the increase of health informa.docxSecurity of Health Care RecordsWith the increase of health informa.docx
Security of Health Care RecordsWith the increase of health informa.docxkaylee7wsfdubill
 
See attached document for additional guidance How are your two phi.docx
See attached document for additional guidance How are your two phi.docxSee attached document for additional guidance How are your two phi.docx
See attached document for additional guidance How are your two phi.docxkaylee7wsfdubill
 
Security SolutionThe weekly assignment for the course is a compreh.docx
Security SolutionThe weekly assignment for the course is a compreh.docxSecurity SolutionThe weekly assignment for the course is a compreh.docx
Security SolutionThe weekly assignment for the course is a compreh.docxkaylee7wsfdubill
 
Security PaperResearch one of the following topicsA couple of t.docx
Security PaperResearch one of the following topicsA couple of t.docxSecurity PaperResearch one of the following topicsA couple of t.docx
Security PaperResearch one of the following topicsA couple of t.docxkaylee7wsfdubill
 
Security and Privacy in the 21st CenturyRead the following article.docx
Security and Privacy in the 21st CenturyRead the following article.docxSecurity and Privacy in the 21st CenturyRead the following article.docx
Security and Privacy in the 21st CenturyRead the following article.docxkaylee7wsfdubill
 
See attached file. Your work should be submitted in a Word docume.docx
See attached file. Your work should be submitted in a Word docume.docxSee attached file. Your work should be submitted in a Word docume.docx
See attached file. Your work should be submitted in a Word docume.docxkaylee7wsfdubill
 
See discussions, stats, and author profiles for this publicati.docx
See discussions, stats, and author profiles for this publicati.docxSee discussions, stats, and author profiles for this publicati.docx
See discussions, stats, and author profiles for this publicati.docxkaylee7wsfdubill
 
See attached file or belowSuppose that there are two (.docx
See attached file or belowSuppose that there are two (.docxSee attached file or belowSuppose that there are two (.docx
See attached file or belowSuppose that there are two (.docxkaylee7wsfdubill
 
Security Support Responsibilities Please respond to the following.docx
Security Support Responsibilities Please respond to the following.docxSecurity Support Responsibilities Please respond to the following.docx
Security Support Responsibilities Please respond to the following.docxkaylee7wsfdubill
 
see attached fact sheetObviously, Michelle is upset and would l.docx
see attached fact sheetObviously, Michelle is upset and would l.docxsee attached fact sheetObviously, Michelle is upset and would l.docx
see attached fact sheetObviously, Michelle is upset and would l.docxkaylee7wsfdubill
 
Security Monitoring  Please respond to the followingConsidering.docx
Security Monitoring  Please respond to the followingConsidering.docxSecurity Monitoring  Please respond to the followingConsidering.docx
Security Monitoring  Please respond to the followingConsidering.docxkaylee7wsfdubill
 
Section 5 Controlling RiskThis final section combines all of the .docx
Section 5 Controlling RiskThis final section combines all of the .docxSection 5 Controlling RiskThis final section combines all of the .docx
Section 5 Controlling RiskThis final section combines all of the .docxkaylee7wsfdubill
 
Section 1–Organizational DescriptionAssignment Length 2–3 pages.docx
Section 1–Organizational DescriptionAssignment Length 2–3 pages.docxSection 1–Organizational DescriptionAssignment Length 2–3 pages.docx
Section 1–Organizational DescriptionAssignment Length 2–3 pages.docxkaylee7wsfdubill
 
Section 1 MS Project Exercise1. Develop a multilevel work breakdo.docx
Section 1 MS Project Exercise1. Develop a multilevel work breakdo.docxSection 1 MS Project Exercise1. Develop a multilevel work breakdo.docx
Section 1 MS Project Exercise1. Develop a multilevel work breakdo.docxkaylee7wsfdubill
 
Second Wave Feminism, gained strength during the 1970s. For this .docx
Second Wave Feminism, gained strength during the 1970s. For this .docxSecond Wave Feminism, gained strength during the 1970s. For this .docx
Second Wave Feminism, gained strength during the 1970s. For this .docxkaylee7wsfdubill
 
Search the Internet for pertinent information that supports the inte.docx
Search the Internet for pertinent information that supports the inte.docxSearch the Internet for pertinent information that supports the inte.docx
Search the Internet for pertinent information that supports the inte.docxkaylee7wsfdubill
 
Section 404 of the Sarbanes-Oxley Act of 2002 (SOX) directs the SE.docx
Section 404 of the Sarbanes-Oxley Act of 2002 (SOX) directs the SE.docxSection 404 of the Sarbanes-Oxley Act of 2002 (SOX) directs the SE.docx
Section 404 of the Sarbanes-Oxley Act of 2002 (SOX) directs the SE.docxkaylee7wsfdubill
 

More from kaylee7wsfdubill (20)

Seeking a complete Excel spreadsheet with cell equations, and answer.docx
Seeking a complete Excel spreadsheet with cell equations, and answer.docxSeeking a complete Excel spreadsheet with cell equations, and answer.docx
Seeking a complete Excel spreadsheet with cell equations, and answer.docx
 
see the attachmentA. Describe each of the three components in th.docx
see the attachmentA. Describe each of the three components in th.docxsee the attachmentA. Describe each of the three components in th.docx
see the attachmentA. Describe each of the three components in th.docx
 
See the questions belowA. As you choose a culture or cultu.docx
See the questions belowA. As you choose a culture or cultu.docxSee the questions belowA. As you choose a culture or cultu.docx
See the questions belowA. As you choose a culture or cultu.docx
 
Security of Health Care RecordsWith the increase of health informa.docx
Security of Health Care RecordsWith the increase of health informa.docxSecurity of Health Care RecordsWith the increase of health informa.docx
Security of Health Care RecordsWith the increase of health informa.docx
 
See attached document for additional guidance How are your two phi.docx
See attached document for additional guidance How are your two phi.docxSee attached document for additional guidance How are your two phi.docx
See attached document for additional guidance How are your two phi.docx
 
Security SolutionThe weekly assignment for the course is a compreh.docx
Security SolutionThe weekly assignment for the course is a compreh.docxSecurity SolutionThe weekly assignment for the course is a compreh.docx
Security SolutionThe weekly assignment for the course is a compreh.docx
 
Security PaperResearch one of the following topicsA couple of t.docx
Security PaperResearch one of the following topicsA couple of t.docxSecurity PaperResearch one of the following topicsA couple of t.docx
Security PaperResearch one of the following topicsA couple of t.docx
 
Security and Privacy in the 21st CenturyRead the following article.docx
Security and Privacy in the 21st CenturyRead the following article.docxSecurity and Privacy in the 21st CenturyRead the following article.docx
Security and Privacy in the 21st CenturyRead the following article.docx
 
See attached file. Your work should be submitted in a Word docume.docx
See attached file. Your work should be submitted in a Word docume.docxSee attached file. Your work should be submitted in a Word docume.docx
See attached file. Your work should be submitted in a Word docume.docx
 
See discussions, stats, and author profiles for this publicati.docx
See discussions, stats, and author profiles for this publicati.docxSee discussions, stats, and author profiles for this publicati.docx
See discussions, stats, and author profiles for this publicati.docx
 
See attached file or belowSuppose that there are two (.docx
See attached file or belowSuppose that there are two (.docxSee attached file or belowSuppose that there are two (.docx
See attached file or belowSuppose that there are two (.docx
 
Security Support Responsibilities Please respond to the following.docx
Security Support Responsibilities Please respond to the following.docxSecurity Support Responsibilities Please respond to the following.docx
Security Support Responsibilities Please respond to the following.docx
 
see attached fact sheetObviously, Michelle is upset and would l.docx
see attached fact sheetObviously, Michelle is upset and would l.docxsee attached fact sheetObviously, Michelle is upset and would l.docx
see attached fact sheetObviously, Michelle is upset and would l.docx
 
Security Monitoring  Please respond to the followingConsidering.docx
Security Monitoring  Please respond to the followingConsidering.docxSecurity Monitoring  Please respond to the followingConsidering.docx
Security Monitoring  Please respond to the followingConsidering.docx
 
Section 5 Controlling RiskThis final section combines all of the .docx
Section 5 Controlling RiskThis final section combines all of the .docxSection 5 Controlling RiskThis final section combines all of the .docx
Section 5 Controlling RiskThis final section combines all of the .docx
 
Section 1–Organizational DescriptionAssignment Length 2–3 pages.docx
Section 1–Organizational DescriptionAssignment Length 2–3 pages.docxSection 1–Organizational DescriptionAssignment Length 2–3 pages.docx
Section 1–Organizational DescriptionAssignment Length 2–3 pages.docx
 
Section 1 MS Project Exercise1. Develop a multilevel work breakdo.docx
Section 1 MS Project Exercise1. Develop a multilevel work breakdo.docxSection 1 MS Project Exercise1. Develop a multilevel work breakdo.docx
Section 1 MS Project Exercise1. Develop a multilevel work breakdo.docx
 
Second Wave Feminism, gained strength during the 1970s. For this .docx
Second Wave Feminism, gained strength during the 1970s. For this .docxSecond Wave Feminism, gained strength during the 1970s. For this .docx
Second Wave Feminism, gained strength during the 1970s. For this .docx
 
Search the Internet for pertinent information that supports the inte.docx
Search the Internet for pertinent information that supports the inte.docxSearch the Internet for pertinent information that supports the inte.docx
Search the Internet for pertinent information that supports the inte.docx
 
Section 404 of the Sarbanes-Oxley Act of 2002 (SOX) directs the SE.docx
Section 404 of the Sarbanes-Oxley Act of 2002 (SOX) directs the SE.docxSection 404 of the Sarbanes-Oxley Act of 2002 (SOX) directs the SE.docx
Section 404 of the Sarbanes-Oxley Act of 2002 (SOX) directs the SE.docx
 

Recently uploaded

Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDThiyagu K
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfJayanti Pande
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxiammrhaywood
 
The byproduct of sericulture in different industries.pptx
The byproduct of sericulture in different industries.pptxThe byproduct of sericulture in different industries.pptx
The byproduct of sericulture in different industries.pptxShobhayan Kirtania
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...
JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...
JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...anjaliyadav012327
 
9548086042 for call girls in Indira Nagar with room service
9548086042  for call girls in Indira Nagar  with room service9548086042  for call girls in Indira Nagar  with room service
9548086042 for call girls in Indira Nagar with room servicediscovermytutordmt
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingTechSoup
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxSayali Powar
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdfQucHHunhnh
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Celine George
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdfQucHHunhnh
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Sapana Sha
 

Recently uploaded (20)

Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SD
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdf
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
The byproduct of sericulture in different industries.pptx
The byproduct of sericulture in different industries.pptxThe byproduct of sericulture in different industries.pptx
The byproduct of sericulture in different industries.pptx
 
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...
JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...
JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...
 
9548086042 for call girls in Indira Nagar with room service
9548086042  for call girls in Indira Nagar  with room service9548086042  for call girls in Indira Nagar  with room service
9548086042 for call girls in Indira Nagar with room service
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy Consulting
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
 
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptxINDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
 
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
 

Change Management and Project Tracking

  • 1. see attachment: 1. A key objective of change control in configuration management is to keep track of actions taken in response to change requests. [removed] a. true [removed] b. false Q2. A key weakness of the Benefit-Cost ratio project selection mechanism is that: [removed] a. It only focuses on things that can be measured [removed] b. It takes time frame into consideration [removed] c. It is too much based on subjective judgment [removed] d. It does not entail prioritizing Q3. Good functional requirements [removed] a. Describe how the deliverable should be developed [removed] b. Provide detailed technical insights into what the
  • 2. deliverable will do [removed] c. Describe what the deliverable looks like and what it should do [removed] d. Are created after development of the technical specifications Q4. A project can be terminated prematurely because the original objectives may no longer be valid. [removed] a. true [removed] b. false Q5. A tool that graphically shows cost variance is: [removed] a. A chart of accounts [removed] b. A code of accounts [removed] c. A histogram (also called a resource loading chart) [removed] d. A cumulative cost curve (also called S-curve)
  • 3. Q6. In resource planning, one of the issues that needs to be considered is: [removed] a. Staff empowerment [removed] b. Technical requirements of the project [removed] c. Theory X management principles [removed] d. Theory Y management principles Q7. When crashing a project, we typically choose critical path tasks whose costs of crashing are highest. [removed] a. true [removed] b. false Q8. The poor man's hierarchy is a method for: [removed] a. Project estimation [removed] b. Project scheduling [removed] c. WBS construction
  • 4. [removed] d. Project selection Q9. Ensuring a one-to-one correspondence between specification items and general design items is a feature of: [removed] a. Scope statement definition [removed] b. WBS construction [removed] c. Rapid prototyping [removed] d. Configuration management Q10. The astute project manager typically uses only one management style in order not to confuse his/her teammates. [removed] a. true [removed] b. false Q11. Structured Walk-Through is a methodology used in: [removed] a. PERT
  • 5. [removed] b. GERT [removed] c. VERT [removed] d. Project Evaluation Q12. If EV = $300, AC = $400, and the project budget is $1,000, what is the estimated final cost of the project (this is known as EAC, estimate at complete)? [removed] a. $750 [removed] b. $1,000 [removed] c. $1,250 [removed] d. $1,333 Q13. If review of a project's status indicates that EV = $400, AC = $400, and PV = $500, the project is: [removed] a. On budget, behind schedule [removed] b. On budget, ahead of schedule
  • 6. [removed] c. Over budget, behind schedule [removed] d. Over budget, ahead of schedule Q14. In project management, the level of uncertainty plays a major role in determining the adequacy of a project plan. [removed] a. true [removed] b. false Q15. The purpose of mid-project evaluation is: [removed] a. Continual monitoring of budget and estimates [removed] b. To focus on achievement of individual element of the project plan [removed] c. To determine whether the original objectives are still relevant [removed] d. To re-baseline the project budget Q16. Confidence in the accuracy of a cost estimate increases when top-down and bottom-up estimates converge.
  • 7. [removed] a. true [removed] b. false Q17. Milestones, like tasks, consume resources. [removed] a. true [removed] b. false Q18. A project team structure that closely reflects the physical structure of the deliverable is known as: [removed] a. Egoless [removed] b. Specialty [removed] c. Surgical [removed] d. Isomorphic Q19. Which of the following is an example of a project? [removed]
  • 8. a. Maintaining e-mail addresses [removed] b. Capacity planning [removed] c. Submitting travel and expense reports [removed] d. Sending monthly reports to top management Q20. The critical path: [removed] a. Provides the duration of a project [removed] b. Has the shortest duration on a project [removed] c. Is the most expensive path to implement [removed] d. Contains the project's most significant tasks Q21. In risk management, insurance is an example of: [removed] a. Risk avoidance [removed] b. Risk deflection [removed]
  • 9. c. Risk acceptance [removed] d. Contingency planning Q22. The bottom-most level of the WBS -- the level at which project budget and schedule data are captured -- is called: [removed] a. Work package [removed] b. Code of accounts [removed] c. Budget baseline [removed] d. Change control level Q23. What is the function of a change control board (CCB) in configuration management? [removed] a. To assess the management impacts of change requests [removed] b. To initiate changes needed on the project [removed] c. To focus on the technical implication of change requests [removed] d. To approve change requests coming from senior
  • 10. management Q24. A major strength of task Gantt charts is that they can: [removed] a. Offer a sophisticated model of a project [removed] b. Show how many resources will be used on the project [removed] c. Show the interdependencies of tasks [removed] d. Show actual versus planned schedule status Q25. Functional requirements provide us with detailed technical specifications. [removed] a. true [removed] b. false Q26. A laissez-faire management style may lead to a ship without rudder syndrome. [removed] a. true [removed] b. false
  • 11. Q27. The resource planning tool that enables us to identify who we need to carry out what tasks is called: [removed] a. A resource Gantt chart [removed] b. A resource matrix (also called the responsibility chart) [removed] c. A resource ogive [removed] d. A resource loading chart (also called a resource histogram) Q28. When we have objective data on the probability of an event, we are involved with decision making under certainty. [removed] a. true [removed] b. false Q29. Which of the following is a scope planning tool? [removed] a. Benefit/cost analysis [removed] b. WBS
  • 12. [removed] c. Earned Value analysis [removed] d. Fast tracking Q30. The Theory X approach to managing workers is a classic example of a top-down view of how people should be managed. [removed] a. true [removed] b. false Q31. Scope creep means: [removed] a. Needs emergence and identification [removed] b. Uncontrolled changes to a project's requirements during project execution [removed] c. Migration of project needs to requirements [removed] d. Imprecise scope statement Q32. An objective of prototyping is to minimize life-cycle cost. [removed]
  • 13. a. true [removed] b. false Q33. Concurrent engineering involves overlapping tasks and phases to accelerate a project's schedule. [removed] a. true [removed] b. false Q34. Bottom-up estimates: [removed] a. Are based on historical trends [removed] b. Can be derived from the WBS [removed] c. Must employ Monte Carlo simulation [removed] d. a and c Q35. Using working time or elapsed time to calculate the time it will take to complete a task produces the same results. [removed] a. true
  • 14. [removed] b. false Q36. There is a definite link between the level of risk an enterprise encounters and project time frame. [removed] a. true [removed] b. false Q37. A modern view in Human Resource Management is that positive motivation results from an opportunity to achieve and experience self-actualization. [removed] a. true [removed] b. false Q38. The type of management whose focus is on activities whose variances lie outside the acceptable range is: [removed] a. Management by Objectives [removed] b. Management by Exception [removed]
  • 15. c. Management by Walking Around [removed] d. Management by Control Limits Q39. Which of the following shows resource allocation over time? [removed] a. Resource Gantt chart [removed] b. Resource matrix [removed] c. S-Curve [removed] d. Resource leveling Q40. Which of the following is a characteristic of an effective reporting system? [removed] a. SMART [removed] b. KISS [removed] c. MBO [removed] d. LOWBALLING
  • 16. Q41. If the latest time you can start a task is five hours into the project, and the earliest time is three and a half hours into the project, how much slack (also called float) does the task have? [removed] a. 0.5 hours [removed] b. 1.5 hours [removed] c. 2.5 hours [removed] d. 8.5 hours Q42. Internal Rate of Return (IRR) is the discount rate that sets the present value of cash outflow equal to the present value of cash inflow. [removed] a. true [removed] b. false Q43. Configuration management is a: [removed] a. Methodology for working closely with customers by developing and updating requirements for faster response to changing customer needs
  • 17. [removed] b. Methodology for ensuring that requirements evolve with evolving customer requirements [removed] c. Methodology for specifying requirements at the outset and for controlling very tightly any changes to them [removed] d. Methodology for specifying requirements at the outset and for facilitating any changes to them with minimum customer input Q44. According to PMI, a WBS should focus on [removed] a. Tasks [removed] b. Deliverables [removed] c. Interrelationships among activities [removed] d. Cost of the project Q45. Under what conditions may a project manager accept a change request? [removed] a. If the request has no effect on project objectives, deadlines, or resources
  • 18. [removed] b. If the request has no effect on project objectives, although it has effects on deadlines and resources [removed] c. If the request is coming from a valued customer [removed] d. If the request is from the Chief Executive Officer Q46. Which of the following methods involves performing tasks in parallel? [removed] a. Crashing [removed] b. Fast tracking [removed] c. Leveling [removed] d. Hammocking Q47. Top-down estimates (also called parametric estimates): [removed] a. Are based on historical trends [removed] b. Can be derived from the WBS
  • 19. [removed] c. Can be determined by analyzing work packages [removed] d. Provide accurate assessments of project costs Q48. Under rapid prototyping (also called application prototyping), the customer actually sees and works with the deliverable as it evolves. [removed] a. true [removed] b. false Q49. Definitive estimates are generally derived from: [removed] a. Bottom-up estimates [removed] b. Top-down estimates [removed] c. Expert judgment cost estimates [removed] d. Order of magnitude estimates Q50. An effective project manager must: [removed]
  • 20. a. Tell his team members what to do [removed] b. Be the most capable person on the team technically [removed] c. Be focused on achieving results [removed] d. Not trust his team members to achieve results without his personal attention to detail