1) The document discusses the selection of the optimal site for Temponi Controls installation out of four locations - Akron, Bilaxi, Carthage, and Denver - based on factors like availability, infrastructure quality, costs, incentives, and labor costs. Carthage, Texas was identified as the favorable site.
2) It presents the distances between different stations in a process layout and calculates the "load x distance" or cost as 2350 units over 7500 units for the layout.
3) It draws a precedence diagram for a process, assigns tasks to minimum number of stations, and calculates the process efficiency as 67.5% with a cycle idle time of 13 minutes.
3. Factor Akron Bilaxi Carthage Denver
OH Ms Tex CO
Disponibilidad
13,5 12 13,5 12
M. Obra
Calidad de los
9,5 7,5 6,5 8,5
Centros Formación
Costos de Terrenos
9 12 13,5 10,5
Y Construcción
Costos de Operación 24 25,5 28,5 25,5
Incentivos 18 15 17 12
Costos Laborales 7,5 8 8,5 7,5
Totales 81,5 80 87,5 76
b) ¿Qué sitio elegiría?
De acuerdo a los resultados obtenidos el sitio favorable
para la instalación de Temponi Controls es en Carthage
Texas
8. Ejercicio 3
a) Dibuje el diagrama de precedencias. b) Asigne tareas al mínimo
número posible de estaciones de trabajo. c) ¿Cuál es la eficiencia
del proceso? d) ¿Cuál es el tiempo muerto por ciclo?
10. a) Asigne tareas al mínimo número posible de estaciones
de trabajo.
Estación Elemento Tiempo Cantidad Tiempo Asignado Tiempo
del elemento operarios estación ocio
1
A 1
1 4 2,67
B 3
2
F 3
1 5 1,67
G 2
3 C 4 1 4 2,67
4
D 4
1 5 1,67
E 1
5
H 5
1 6 0,67
I 1
6 J 3 1 3 3,67
Total 13,02