1. To compare the times of performance by alternative methods.
2. To enable realistic schedule of work to be prepared.
3. To arrive at a realistic and fair incentive scheme.
4. To minimise the human effort.
5. To assist in the organisation of labour by daily comparing the actual
time with that of target time.
6. Target time for each job can be scientifically estimated, with this
estimate realistic schedules and manpower requirements can be
prepared.
7. It can lead to proper balancing of the work distribution.
8. To standardise the efficient method of performing operations.
9. To standardise conditions for efficient performance.
PROCEDURE FOR WORK MEASUREMENT
 1. Select the work to be studied, defining the objectives.
 2. After that all the relevant data relating to the circumstances in which
the work is being done, is recorded.
 3. Measurement :each element is measured in terms of time over a
sufficient number of cycles of activity to ensure that are representative
picture has been obtained.
 4. Examine :the recorded data and elements time critically to ensure
that the unproductive and random elements are separated from
productive element.
 5. Compile :the time for the operation which will provide a realistic
standard of performance and will include time allowance to cover
suitable rest, personal need contingencies,etc.
 6. Define : precisely the series of activities and the method of
operation for which the rime has been allowed and issue the time as
standard for the activities and method specified.
TECHNIQUES OF WORK MEASUREMENT
• Time study
• Activity sampling
• Synthesis from standard data
• Predetermined motion time system (PMTS)
• Analytical estimating
• Maynard operation sequence technique(MOST)
1. Time study :- time study is the primary method of work measurement.it is a
technique of recording the times and rates of working for the elements of specified
job carried out under specified conditions.it is also used for analyzing the data for
obtaining the time which is required for carrying out the job at defined level of
performance,
2. Activity sampling:- it is a technique of finding the percentage occurrence of a
certain activity by random observation and statistical sampling .in this technique ,a
sample of observation are made at random ,generally there observation have a
high proximity of reflecting the real situation, plus or minus a certain percentage of
error.
3. Synthesis from standard data:-it is such a technique of work measurement
which is used for non-repetitive work in which elements of work are repeated in
varying sequence , as in drilling and center lathe work. When the stop-watch
studies and activity sampling are not convenient, then we may estimate a
standard arrived at this way are called synthesis.
4. Predetermined motion time system (PMTS)-:it is a work measurement
technique in which times established for basic human motion are used to build
up the time for a job at a defined level of performance .
5. Analytical estimating:- analytical estimating is a technique in which the
time required to carry out element of a job at a defined level of
performance is established from knowledge and practical experience at
the elements concerned. This type of analytical calculation takes into
account the speed ,feed, length of cut,etc.
6. Maynard operating sequence technique (MOST):-this technique was
conceptualized in 1967.it is assumed that displacement of object is the
common denominator to study an overwhelming majority of work.it
concentrates an movement objects in three modes-general move
sequence for movement in air, controlled move sequence for movement
against a surface or attached movement and the tool use sequence for
the use of common hand tools.
Work Measurment

More Related Content

What's hot

Most (Maynard Operation Sequence Technique)
Most (Maynard Operation Sequence Technique)Most (Maynard Operation Sequence Technique)
Most (Maynard Operation Sequence Technique)
Sohit Chauhan
 
Measurment techniques
Measurment techniquesMeasurment techniques
Measurment techniques
Dhruvit Lakhani
 
Time study
Time studyTime study
Time study
Lav Gupta
 
1.1 Work study and method study -Industrial Engineering Basics
1.1 Work study and method study -Industrial Engineering Basics1.1 Work study and method study -Industrial Engineering Basics
1.1 Work study and method study -Industrial Engineering Basics
Dr. Surya Prakash
 
Time And Motion Study
Time And  Motion  StudyTime And  Motion  Study
Time And Motion Study
ahmad bassiouny
 
Work measurement
Work measurementWork measurement
Work measurement
Princess Angela Moranta
 
Basic of work study
Basic of work studyBasic of work study
Basic of work study
rakibul Islam
 
Work Study- Methods Study
Work Study- Methods StudyWork Study- Methods Study
Work Study- Methods Study
Joseph Konnully
 
work measurement_operation management
work measurement_operation managementwork measurement_operation management
work measurement_operation management
Saravanan Murugan
 
UNIT 4 - PRODUCTION SCHEDULING
UNIT 4 - PRODUCTION SCHEDULINGUNIT 4 - PRODUCTION SCHEDULING
Work measurement
Work measurementWork measurement
Work measurement
lokesh Panneer selvam
 
Work study
Work studyWork study
Work study
MohanKirthik
 
Work Study & Productivity
Work Study & ProductivityWork Study & Productivity
Work Study & Productivity
ahmad bassiouny
 
Production planning & control
Production planning & controlProduction planning & control
Production planning & control
Faizan Akhtar
 
3 work measurement ppt
3 work measurement ppt3 work measurement ppt
3 work measurement pptLizzette Danan
 
Work Sampling
Work Sampling Work Sampling
Work Sampling
Mayank Agarwal
 
Motion and time study
Motion and time studyMotion and time study
Motion and time study
Seta Wicaksana
 

What's hot (20)

Most (Maynard Operation Sequence Technique)
Most (Maynard Operation Sequence Technique)Most (Maynard Operation Sequence Technique)
Most (Maynard Operation Sequence Technique)
 
Measurment techniques
Measurment techniquesMeasurment techniques
Measurment techniques
 
Time study
Time studyTime study
Time study
 
1.1 Work study and method study -Industrial Engineering Basics
1.1 Work study and method study -Industrial Engineering Basics1.1 Work study and method study -Industrial Engineering Basics
1.1 Work study and method study -Industrial Engineering Basics
 
Time And Motion Study
Time And  Motion  StudyTime And  Motion  Study
Time And Motion Study
 
3...work study
3...work study3...work study
3...work study
 
Work measurement
Work measurementWork measurement
Work measurement
 
Basic of work study
Basic of work studyBasic of work study
Basic of work study
 
Work Study- Methods Study
Work Study- Methods StudyWork Study- Methods Study
Work Study- Methods Study
 
work measurement_operation management
work measurement_operation managementwork measurement_operation management
work measurement_operation management
 
Work measurement (1)
Work measurement (1)Work measurement (1)
Work measurement (1)
 
UNIT 4 - PRODUCTION SCHEDULING
UNIT 4 - PRODUCTION SCHEDULINGUNIT 4 - PRODUCTION SCHEDULING
UNIT 4 - PRODUCTION SCHEDULING
 
Work measurement
Work measurementWork measurement
Work measurement
 
Work study
Work studyWork study
Work study
 
Work Study & Productivity
Work Study & ProductivityWork Study & Productivity
Work Study & Productivity
 
Work measurement
Work measurementWork measurement
Work measurement
 
Production planning & control
Production planning & controlProduction planning & control
Production planning & control
 
3 work measurement ppt
3 work measurement ppt3 work measurement ppt
3 work measurement ppt
 
Work Sampling
Work Sampling Work Sampling
Work Sampling
 
Motion and time study
Motion and time studyMotion and time study
Motion and time study
 

Similar to Work Measurment

Industrial egineering
Industrial egineeringIndustrial egineering
Industrial egineeringRajeev Sharan
 
PREDETERMINED MOTION TIME SYSTEM (PMTS).pptx
PREDETERMINED MOTION TIME SYSTEM (PMTS).pptxPREDETERMINED MOTION TIME SYSTEM (PMTS).pptx
PREDETERMINED MOTION TIME SYSTEM (PMTS).pptx
LakshayKumar504432
 
Management tools
Management toolsManagement tools
Management tools
Paritosh Kasaudhan
 
Work Study & Productivity
Work Study & ProductivityWork Study & Productivity
Work Study & Productivity
ahmad bassiouny
 
Unit 3 iem part 2
Unit 3  iem part  2Unit 3  iem part  2
Unit 3 iem part 2
Sarravanan R
 
4th-IE-BSS.pptx.pptx
4th-IE-BSS.pptx.pptx4th-IE-BSS.pptx.pptx
4th-IE-BSS.pptx.pptx
shiwakantmaurya
 
Time & motion study
Time & motion studyTime & motion study
Time & motion study
Muhammad Hassan
 
Work study method study-work measurement
Work study method study-work measurementWork study method study-work measurement
Work study method study-work measurement
Er. Vaibhav Agarwal
 
PRODUCTION PLANNING AND CONTROL-WORK STUDY
PRODUCTION  PLANNING AND CONTROL-WORK STUDYPRODUCTION  PLANNING AND CONTROL-WORK STUDY
PRODUCTION PLANNING AND CONTROL-WORK STUDY
AttiMurugan
 
Motion & time study
Motion & time studyMotion & time study
Motion & time study
Ahmad Alzbeidat
 
Work study Training Manual
Work study Training ManualWork study Training Manual
Cu mba operation managment module 4 calicut university
Cu mba operation managment module 4 calicut universityCu mba operation managment module 4 calicut university
Cu mba operation managment module 4 calicut university
ChathamkulamInstitut
 
Work study work measurement
Work study   work measurementWork study   work measurement
Work study work measurement
Joseph Konnully
 
presentation group 5.pptx
presentation group 5.pptxpresentation group 5.pptx
presentation group 5.pptx
DouglassRasuh1
 
work-measurement-ppt.pptx
work-measurement-ppt.pptxwork-measurement-ppt.pptx
work-measurement-ppt.pptx
RDTCPOLYTECHNICMECHD
 
Good work measurement
Good work measurementGood work measurement
Good work measurement
kishorereddy_btech
 

Similar to Work Measurment (20)

Industrial egineering
Industrial egineeringIndustrial egineering
Industrial egineering
 
PREDETERMINED MOTION TIME SYSTEM (PMTS).pptx
PREDETERMINED MOTION TIME SYSTEM (PMTS).pptxPREDETERMINED MOTION TIME SYSTEM (PMTS).pptx
PREDETERMINED MOTION TIME SYSTEM (PMTS).pptx
 
Management tools
Management toolsManagement tools
Management tools
 
Work Study & Productivity
Work Study & ProductivityWork Study & Productivity
Work Study & Productivity
 
Garments
Garments Garments
Garments
 
Unit 3 iem part 2
Unit 3  iem part  2Unit 3  iem part  2
Unit 3 iem part 2
 
4th-IE-BSS.pptx.pptx
4th-IE-BSS.pptx.pptx4th-IE-BSS.pptx.pptx
4th-IE-BSS.pptx.pptx
 
Time & motion study
Time & motion studyTime & motion study
Time & motion study
 
Work measurement
Work measurementWork measurement
Work measurement
 
Work study method study-work measurement
Work study method study-work measurementWork study method study-work measurement
Work study method study-work measurement
 
PRODUCTION PLANNING AND CONTROL-WORK STUDY
PRODUCTION  PLANNING AND CONTROL-WORK STUDYPRODUCTION  PLANNING AND CONTROL-WORK STUDY
PRODUCTION PLANNING AND CONTROL-WORK STUDY
 
Motion & time study
Motion & time studyMotion & time study
Motion & time study
 
Work study Training Manual
Work study Training ManualWork study Training Manual
Work study Training Manual
 
Time and motion study
Time and motion study Time and motion study
Time and motion study
 
Cu mba operation managment module 4 calicut university
Cu mba operation managment module 4 calicut universityCu mba operation managment module 4 calicut university
Cu mba operation managment module 4 calicut university
 
Work study work measurement
Work study   work measurementWork study   work measurement
Work study work measurement
 
presentation group 5.pptx
presentation group 5.pptxpresentation group 5.pptx
presentation group 5.pptx
 
work-measurement-ppt.pptx
work-measurement-ppt.pptxwork-measurement-ppt.pptx
work-measurement-ppt.pptx
 
Work
WorkWork
Work
 
Good work measurement
Good work measurementGood work measurement
Good work measurement
 

Recently uploaded

falcon-invoice-discounting-a-premier-platform-for-investors-in-india
falcon-invoice-discounting-a-premier-platform-for-investors-in-indiafalcon-invoice-discounting-a-premier-platform-for-investors-in-india
falcon-invoice-discounting-a-premier-platform-for-investors-in-india
Falcon Invoice Discounting
 
CADAVER AS OUR FIRST TEACHER anatomt in your.pptx
CADAVER AS OUR FIRST TEACHER anatomt in your.pptxCADAVER AS OUR FIRST TEACHER anatomt in your.pptx
CADAVER AS OUR FIRST TEACHER anatomt in your.pptx
fakeloginn69
 
What are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdfWhat are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdf
HumanResourceDimensi1
 
PriyoShop Celebration Pohela Falgun Mar 20, 2024
PriyoShop Celebration Pohela Falgun Mar 20, 2024PriyoShop Celebration Pohela Falgun Mar 20, 2024
PriyoShop Celebration Pohela Falgun Mar 20, 2024
PriyoShop.com LTD
 
Affordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n PrintAffordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n Print
Navpack & Print
 
Skye Residences | Extended Stay Residences Near Toronto Airport
Skye Residences | Extended Stay Residences Near Toronto AirportSkye Residences | Extended Stay Residences Near Toronto Airport
Skye Residences | Extended Stay Residences Near Toronto Airport
marketingjdass
 
Cracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptxCracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptx
Workforce Group
 
Improving profitability for small business
Improving profitability for small businessImproving profitability for small business
Improving profitability for small business
Ben Wann
 
Brand Analysis for an artist named Struan
Brand Analysis for an artist named StruanBrand Analysis for an artist named Struan
Brand Analysis for an artist named Struan
sarahvanessa51503
 
anas about venice for grade 6f about venice
anas about venice for grade 6f about veniceanas about venice for grade 6f about venice
anas about venice for grade 6f about venice
anasabutalha2013
 
Memorandum Of Association Constitution of Company.ppt
Memorandum Of Association Constitution of Company.pptMemorandum Of Association Constitution of Company.ppt
Memorandum Of Association Constitution of Company.ppt
seri bangash
 
Digital Transformation in PLM - WHAT and HOW - for distribution.pdf
Digital Transformation in PLM - WHAT and HOW - for distribution.pdfDigital Transformation in PLM - WHAT and HOW - for distribution.pdf
Digital Transformation in PLM - WHAT and HOW - for distribution.pdf
Jos Voskuil
 
Global Interconnection Group Joint Venture[960] (1).pdf
Global Interconnection Group Joint Venture[960] (1).pdfGlobal Interconnection Group Joint Venture[960] (1).pdf
Global Interconnection Group Joint Venture[960] (1).pdf
Henry Tapper
 
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
BBPMedia1
 
Set off and carry forward of losses and assessment of individuals.pptx
Set off and carry forward of losses and assessment of individuals.pptxSet off and carry forward of losses and assessment of individuals.pptx
Set off and carry forward of losses and assessment of individuals.pptx
HARSHITHV26
 
3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx
tanyjahb
 
Pitch Deck Teardown: RAW Dating App's $3M Angel deck
Pitch Deck Teardown: RAW Dating App's $3M Angel deckPitch Deck Teardown: RAW Dating App's $3M Angel deck
Pitch Deck Teardown: RAW Dating App's $3M Angel deck
HajeJanKamps
 
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdfSearch Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Arihant Webtech Pvt. Ltd
 
Project File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdfProject File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdf
RajPriye
 
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBdCree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
creerey
 

Recently uploaded (20)

falcon-invoice-discounting-a-premier-platform-for-investors-in-india
falcon-invoice-discounting-a-premier-platform-for-investors-in-indiafalcon-invoice-discounting-a-premier-platform-for-investors-in-india
falcon-invoice-discounting-a-premier-platform-for-investors-in-india
 
CADAVER AS OUR FIRST TEACHER anatomt in your.pptx
CADAVER AS OUR FIRST TEACHER anatomt in your.pptxCADAVER AS OUR FIRST TEACHER anatomt in your.pptx
CADAVER AS OUR FIRST TEACHER anatomt in your.pptx
 
What are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdfWhat are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdf
 
PriyoShop Celebration Pohela Falgun Mar 20, 2024
PriyoShop Celebration Pohela Falgun Mar 20, 2024PriyoShop Celebration Pohela Falgun Mar 20, 2024
PriyoShop Celebration Pohela Falgun Mar 20, 2024
 
Affordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n PrintAffordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n Print
 
Skye Residences | Extended Stay Residences Near Toronto Airport
Skye Residences | Extended Stay Residences Near Toronto AirportSkye Residences | Extended Stay Residences Near Toronto Airport
Skye Residences | Extended Stay Residences Near Toronto Airport
 
Cracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptxCracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptx
 
Improving profitability for small business
Improving profitability for small businessImproving profitability for small business
Improving profitability for small business
 
Brand Analysis for an artist named Struan
Brand Analysis for an artist named StruanBrand Analysis for an artist named Struan
Brand Analysis for an artist named Struan
 
anas about venice for grade 6f about venice
anas about venice for grade 6f about veniceanas about venice for grade 6f about venice
anas about venice for grade 6f about venice
 
Memorandum Of Association Constitution of Company.ppt
Memorandum Of Association Constitution of Company.pptMemorandum Of Association Constitution of Company.ppt
Memorandum Of Association Constitution of Company.ppt
 
Digital Transformation in PLM - WHAT and HOW - for distribution.pdf
Digital Transformation in PLM - WHAT and HOW - for distribution.pdfDigital Transformation in PLM - WHAT and HOW - for distribution.pdf
Digital Transformation in PLM - WHAT and HOW - for distribution.pdf
 
Global Interconnection Group Joint Venture[960] (1).pdf
Global Interconnection Group Joint Venture[960] (1).pdfGlobal Interconnection Group Joint Venture[960] (1).pdf
Global Interconnection Group Joint Venture[960] (1).pdf
 
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
 
Set off and carry forward of losses and assessment of individuals.pptx
Set off and carry forward of losses and assessment of individuals.pptxSet off and carry forward of losses and assessment of individuals.pptx
Set off and carry forward of losses and assessment of individuals.pptx
 
3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx
 
Pitch Deck Teardown: RAW Dating App's $3M Angel deck
Pitch Deck Teardown: RAW Dating App's $3M Angel deckPitch Deck Teardown: RAW Dating App's $3M Angel deck
Pitch Deck Teardown: RAW Dating App's $3M Angel deck
 
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdfSearch Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdf
 
Project File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdfProject File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdf
 
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBdCree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
 

Work Measurment

  • 1.
  • 2.
  • 3.  Introduction  Meaning  Objectives  Procedure of WM  Techniques of WM
  • 4.
  • 5.
  • 6. 1. To compare the times of performance by alternative methods. 2. To enable realistic schedule of work to be prepared. 3. To arrive at a realistic and fair incentive scheme. 4. To minimise the human effort. 5. To assist in the organisation of labour by daily comparing the actual time with that of target time. 6. Target time for each job can be scientifically estimated, with this estimate realistic schedules and manpower requirements can be prepared. 7. It can lead to proper balancing of the work distribution. 8. To standardise the efficient method of performing operations. 9. To standardise conditions for efficient performance.
  • 7. PROCEDURE FOR WORK MEASUREMENT  1. Select the work to be studied, defining the objectives.  2. After that all the relevant data relating to the circumstances in which the work is being done, is recorded.  3. Measurement :each element is measured in terms of time over a sufficient number of cycles of activity to ensure that are representative picture has been obtained.  4. Examine :the recorded data and elements time critically to ensure that the unproductive and random elements are separated from productive element.  5. Compile :the time for the operation which will provide a realistic standard of performance and will include time allowance to cover suitable rest, personal need contingencies,etc.  6. Define : precisely the series of activities and the method of operation for which the rime has been allowed and issue the time as standard for the activities and method specified.
  • 8. TECHNIQUES OF WORK MEASUREMENT • Time study • Activity sampling • Synthesis from standard data • Predetermined motion time system (PMTS) • Analytical estimating • Maynard operation sequence technique(MOST)
  • 9. 1. Time study :- time study is the primary method of work measurement.it is a technique of recording the times and rates of working for the elements of specified job carried out under specified conditions.it is also used for analyzing the data for obtaining the time which is required for carrying out the job at defined level of performance, 2. Activity sampling:- it is a technique of finding the percentage occurrence of a certain activity by random observation and statistical sampling .in this technique ,a sample of observation are made at random ,generally there observation have a high proximity of reflecting the real situation, plus or minus a certain percentage of error. 3. Synthesis from standard data:-it is such a technique of work measurement which is used for non-repetitive work in which elements of work are repeated in varying sequence , as in drilling and center lathe work. When the stop-watch studies and activity sampling are not convenient, then we may estimate a standard arrived at this way are called synthesis. 4. Predetermined motion time system (PMTS)-:it is a work measurement technique in which times established for basic human motion are used to build up the time for a job at a defined level of performance .
  • 10. 5. Analytical estimating:- analytical estimating is a technique in which the time required to carry out element of a job at a defined level of performance is established from knowledge and practical experience at the elements concerned. This type of analytical calculation takes into account the speed ,feed, length of cut,etc. 6. Maynard operating sequence technique (MOST):-this technique was conceptualized in 1967.it is assumed that displacement of object is the common denominator to study an overwhelming majority of work.it concentrates an movement objects in three modes-general move sequence for movement in air, controlled move sequence for movement against a surface or attached movement and the tool use sequence for the use of common hand tools.