The Woodglen Lake Dredging & Restoration project in Fairfax County, VA removed over 40,000 cubic yards of sediment from Woodglen Lake. The project improved maintenance access and installed a sediment forebay to simplify future dredging. Dredged sediment was disposed of innovatively at the County-owned I-95 Landfill Complex. Stream restoration and landscaping around the lake also enhanced the area. The project reduces annual sediment and nutrient loads in downstream waters.
Leigh Meadow & Towlston Basin (0584DP/0103DP)Fairfax County
Leigh Meadow & Towlston Basin project was substantially completed on October 29, 2021. This project consists of 1,660 feet of stream restoration, a 22,300 cubic foot Regenerative Stormwater Conveyance (RSC) facility and a 28,500 cubic foot sand filter. The scope of work also included grading, excavation, pollution and sediment removal, and restoration planting.
Leigh Meadow & Towlston Basin (0584DP/0103DP)Fairfax County
Leigh Meadow & Towlston Basin project was substantially completed on October 29, 2021. This project consists of 1,660 feet of stream restoration, a 22,300 cubic foot Regenerative Stormwater Conveyance (RSC) facility and a 28,500 cubic foot sand filter. The scope of work also included grading, excavation, pollution and sediment removal, and restoration planting.
The Meadow Run (0273DP) dry pond is located within the Bull Neck Run Watershed. The project replaced a deteriorating control structure and primary spillway, increased the storage volume and incorporated water quality improvements through the use of extended detention, wetland plantings and increased travel time. The project also upgraded the maintenance access.
McLean Hunt Estates Pond Improvement ProjectFairfax County
The McLean Hunt Estates Pond Improvement Project consisted of retrofitting an existing dry pond to an extended detention dry pond. The goals of the project were to stabilize the incoming degraded channel constructing a step pool conveyance system; replace the existing corrugated metal pipe principal spillway pipe with reinforced concrete pipe; install a new riser structure with BMP plate to provide water quality benefits; and upgrade the asphalt trail into an access road to accommodate equipment/vehicles for future maintenance.
The Sully Basins Stormwater Pond Retrofits project was substantially completed on April 19, 2022. The project is located within the Cub Run watershed. The project consisted of repair and enhancement of multiple stormwater basins, 0326DP, 0964DP and 1484DP. The project also included construction of new stone cascades, stone weir basin structures and the construction of wetlands with high and low marsh areas. The project will facilitate improved sediment removal and improve downstream water quality using forebays and micro pools. Aquatic and natural habitat were also added within the three basins.
Accotink Tributary at Oakford Drive Stream RestorationFairfax County
The Accotink Tributary at Oakford Drive Stream Restoration project included restoration of approximately 1,538 linear feet of stream using natural channel design for restoration, enhancing and stabilizing the degraded stream channel, bed and bank to stabilize, enhance and provide water quality benefits, aesthetics, and prevent further erosion.
Hunting Creek at Fairfield Stream RestorationFairfax County
The Hunting Creek at Fairchild Stream Restoration project, Substantially Completed on January 13, 2021, includes restoring, enhancing and stabilizing approximately 1,186 linear feet of stream channel in two segments and 166 linear feet of tributary through natural channel design to provide aquatic benefits, grade control, improve water quality and prevent further erosion. The work also included demolition of a condemned house and accessory structures including obtaining all associated demolition permits and restoration landscaping.
Restore ~4,000 feet by returning the form and function of the channel to dynamic equilibrium and improve the ecological processes of the riparian corridor.
Turkeycock Run at Mason District Park Stream Restoration ProjectFairfax County
The Turkeycock Run at Mason District Park Stream Restoration Project included 1,580 linear feet of stream restoration through natural channel design to enhance/stabilize and restore the stream channel to improve water quality.
Similar to Woodglen Lake Dredging and Restoration (20)
Merrifield Nursery Emergency Gravity Sewer ReplacementFairfax County
During a routine Closed-Circuit Television (CCTV) Camera inspection by Wastewater Collection Division (WCD), it was found that 45 linear feet of 8-inch asbestos reinforced concrete pipe (RCP) between MH-292 to MH-291 was within imminent danger of failing. The bottom of the RCP was missing within the 45 linear feet of repair and the pipe was on the verge of surcharging. After an immediate pre-construction meeting with Merrifield Nursery, it was agreed to work from 6pm-10am everyday of the week to avoid disruption and potentially placing patrons at risk during the biggest time of the year for Merrifield Garden Center. The contractor mobilized to the site and began the 20-foot excavation to replace 45 linear feet of broken gravity sewer. The project started on March 14th, 2022 and was substantially complete on March 23, 2022.
Clarks Crossing Road Improvements 05-13-22Fairfax County
The Clarks Crossing Road Pedestrian Access Improvement project improved the pedestrian and bicycle access along Clarks Crossing Road and was substantially completed on March 23, 2022.
This project completed the missing link between the existing sidewalk at Brookside Lane and the previously constructed sidewalk along Clarks Crossing Road. The scope of this project included construction of asphalt sidewalk, curb ramps, curb and gutter, drainage improvements along Brookside Lane and asphalt mill/overlay on Clarks Crossing and Brookside Lane.
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxFairfax County
Future wastewater flows in northern Fairfax County exceed existing system capacity
Treatment capacity is available in Noman M. Cole Jr. Pollution Control Plant in Lorton, VA
New pipes and pumps are needed to move future flows to treatment plant
NEXT STEPS
Field investigations / surveys
Finalize alignments and pump station layout
Use of open cut excavation
Use of trenchless methods
Easement acquisition needed
Develop traffic control plans
Description:
The project consists of a new, 23,000 square feet, two-story, four-bay fire station facility and associated improvements to the 3.3-acre site including storm water detention, landscaping and parking. The scope also included the demolition of the existing fire station, and a temporary fire station to house the Fire and Rescue Department during construction of the new facility. The key elements of the overall project include:
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationFairfax County
Scotts Run @ Old Meadow Road Stream Restoration was substantially completed on March 30, 2022. The Scotts Run project consisted of restoring, enhancement, and stabilizing of approximately 2,930 linear feet of eroding stream using Natural Channel Design criteria. This project included two phases: Phase I was funded by proffers from a private development and Phase II was County funded. Also included was the removal of invasive non-native plants and the installation of new plantings to stabilize the stream and floodplain.
Riverwood Community Meeting - 04-14-2022- Presentation.pptxFairfax County
The new 4-inch ductile iron force main will serve the surrounding community for the foreseeable future. Replacement of the force main will:
Reduce the level and frequency of maintenance required to keep the force main operating.
Prevent costly emergency repairs.
Provide residents with safe, reliable utility infrastructure.
Enhance the quality of life for residents.
Reduce risks to public health and the environment.
Burke Centre VRE Connector Phase IV project was substantially completed on March 7, 2022. This project enhanced the access to mass transit by creating a more direct connection from the VRE Station to the residential areas west of Premier Court. This project also connects the Oak Bluff community to the Virginia Rail Express (VRE) Burke Station and provides a multi-use shared pedestrian and bicycle trail for outdoor recreation.
Long Branch Public Meeting - FINAL - 04-11-2022Fairfax County
Overarching Project Goals:
-Achieve Long Branch Central TMDL waste load reduction requirements.
-Provide long-term stability and have low maintenance.
-Improve water quality within the Long Branch Central Watershed.
-Improve habitat and environmental health (ecological lift).
Objectives: Share our project understanding with the council and seek input on the unique opportunities and housing goals for this site that could help guide
our master planning process.
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptxFairfax County
4,800 linear feet of stream will be restored using Natural Channel Design methodologies
Pollutant reduction
1,439 lbs/total phosphorus
3,400 lbs/total nitrogen
462.1 tons of total suspended sediment
Protection of private property and public infrastructure
Increased ecological diversity with native vegetation
DEQ has awarded a SLAF grant to this project for these environmental benefits
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT Fairfax County
The Lake Barton Dredging, Restoration, and Riser Modification project was substantially completed on December 29, 2021. The project is located within the Pohick Creek watershed. The project consisted of dredging and removal of approximately 19,100 cubic yards of sediment to restore the sediment trapping capacity and improve water quality. The project also included construction of new sediment forebays, in-lake haul roads, and riser modifications (new mid-level sluice gate and cold-water intake) to facilitate future maintenance, stabilize the shoreline, and improve downstream water quality. Fish habitat was also added within the lake.
Reston Arts Community Center Feasibility - Wrap UpFairfax County
This is the last of 5 engagement meetings. We are excited to report back what we heard from you – your preferences, priorities, questions, hopes, concerns. The information we received will be used to inform the space allocations and cost estimating for discussion of the proffer by Fairfax County.
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Fairfax County
Benefits of Consolidated Facility
Building and Site Efficiencies
Operational Efficiencies
Addresses Space Deficiencies
Addresses Renovations and Capital Renewal Requirements
for WCD
Provides for a Centrally Located Site that Accommodates Program
Consolidates Integrated Services on One Centrally Located Site
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Fairfax County
This is the 4th of 5 engagement meetings. We are excited to hear from you – your preferences, priorities, questions, hopes, concerns. The information we receive today will be used to inform the space allocations and cost estimating for discussion of the proffer by Fairfax County.
Oak Marr Pump Station Rehabilitation – Construction ProjectFairfax County
Neighborhood was built in the 1980s, and the sewer infrastructure has been in operation since.
Aged pump station equipment – pumps, valves, fans, concrete, etc.
This aging equipment has the potential of causing:
Sanitary Sewer Overflows (SSO)
Sewer back-ups into homes
Environmental damages
Maintenance problems
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Fairfax County
Identify and evaluate house flooding and public safety concerns
Improve drainage conditions to convey 100-year storm if feasible
Reduce and treat stormwater runoff at the source
Improve water quality and stream protection
Use resilient & functional designs
Make improvements compatible with characteristics of neighborhood
Partner with community to develop sound, cost effective solutions that can be collaboratively implemented and maintained
Build on lessons learned to help improve site development process for infill development
Reston Arts Center Feasibility - Focus Group Visual ArtsFairfax County
These community outreach meetings are being conducted to understand community needs for a proposed arts venue in the Reston Town Center.
The proposed arts center would be a result of a proffer from Boston Properties in the next phase of Reston Town Center development (Block J).
The proffer would provide for an approximately 60,000 gross square foot facility to house a stage suitable for large-scale music and dance performances, as well as other arts-related amenities.
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022Fairfax County
These community outreach meetings are being conducted to understand community needs for a proposed arts venue in the Reston Town Center.
The proposed arts center would be a result of a proffer from Boston Properties in the next phase of Reston Town Center development (Block J).
The proffer would provide for an approximately 60,000 gross square foot facility to house a stage suitable for large-scale music and dance performances, as well as other arts-related amenities.
31052024_First India Newspaper Jaipur.pdfFIRST INDIA
Find Latest India News and Breaking News these days from India on Politics, Business, Entertainment, Technology, Sports, Lifestyle and Coronavirus News in India and the world over that you can't miss. For real time update Visit our social media handle. Read First India NewsPaper in your morning replace. Visit First India.
CLICK:- https://firstindia.co.in/
#First_India_NewsPaper
role of women and girls in various terror groupssadiakorobi2
Women have three distinct types of involvement: direct involvement in terrorist acts; enabling of others to commit such acts; and facilitating the disengagement of others from violent or extremist groups.
‘वोटर्स विल मस्ट प्रीवेल’ (मतदाताओं को जीतना होगा) अभियान द्वारा जारी हेल्पलाइन नंबर, 4 जून को सुबह 7 बजे से दोपहर 12 बजे तक मतगणना प्रक्रिया में कहीं भी किसी भी तरह के उल्लंघन की रिपोर्ट करने के लिए खुला रहेगा।
01062024_First India Newspaper Jaipur.pdfFIRST INDIA
Find Latest India News and Breaking News these days from India on Politics, Business, Entertainment, Technology, Sports, Lifestyle and Coronavirus News in India and the world over that you can't miss. For real time update Visit our social media handle. Read First India NewsPaper in your morning replace. Visit First India.
CLICK:- https://firstindia.co.in/
#First_India_NewsPaper
03062024_First India Newspaper Jaipur.pdfFIRST INDIA
Find Latest India News and Breaking News these days from India on Politics, Business, Entertainment, Technology, Sports, Lifestyle and Coronavirus News in India and the world over that you can't miss. For real time update Visit our social media handle. Read First India NewsPaper in your morning replace. Visit First India.
CLICK:- https://firstindia.co.in/
#First_India_NewsPaper
In a May 9, 2024 paper, Juri Opitz from the University of Zurich, along with Shira Wein and Nathan Schneider form Georgetown University, discussed the importance of linguistic expertise in natural language processing (NLP) in an era dominated by large language models (LLMs).
The authors explained that while machine translation (MT) previously relied heavily on linguists, the landscape has shifted. “Linguistics is no longer front and center in the way we build NLP systems,” they said. With the emergence of LLMs, which can generate fluent text without the need for specialized modules to handle grammar or semantic coherence, the need for linguistic expertise in NLP is being questioned.
हम आग्रह करते हैं कि जो भी सत्ता में आए, वह संविधान का पालन करे, उसकी रक्षा करे और उसे बनाए रखे।" प्रस्ताव में कुल तीन प्रमुख हस्तक्षेप और उनके तंत्र भी प्रस्तुत किए गए। पहला हस्तक्षेप स्वतंत्र मीडिया को प्रोत्साहित करके, वास्तविकता पर आधारित काउंटर नैरेटिव का निर्माण करके और सत्तारूढ़ सरकार द्वारा नियोजित मनोवैज्ञानिक हेरफेर की रणनीति का मुकाबला करके लोगों द्वारा निर्धारित कथा को बनाए रखना और उस पर कार्यकरना था।
1. A Fairfax County, VA, publication
Department of Public Works and Environmental Services
Working for You!
Woodglen Lake Dredging and Restoration
Contract Number CN14125106
Project Number SD-000033-021
Braddock District
March 25, 2016
2. Woodglen Lake Dredging and Restoration
Capital Facilities / Utilities Design and Construction Division / Transportation and Stormwater Construction Branch
3. Project Details
Woodglen Lake Dredging and Restoration
Capital Facilities / Utilities Design and Construction Division / Transportation and Stormwater Construction Branch
Description:
The Woodglen Lake Dredging & Restoration project was substantially completed on November 18, 2015. The
project consisted of removing sediment from the lake; stream restoration above the lake, improving an existing
access road to the lake, landscape planting and trail modifications around the lake, constructing a staging area
and sediment forebay to simplify future dredging operations, and modifications and repairs for the lake’s
principal spillway. Additionally, this project demonstrated the feasibility of spreading dredged sediment as
topsoil at the County-Owned I-95 Landfill Complex rather than paying disposal fees to dump this material in other
landfills – a significant cost saving to the County.
Project Overview:
• Remove sediment from a stormwater management lake constructed in 1981, in the Braddock District of
Fairfax County, Virginia
• Worked with the I-95 Landfill Complex staff to provide an innovative sediment disposal method
• Worked with the Fairfax County Park Authority staff to improve the landscaping and public access to the lake
Project Team:
• Stormwater Planning Division - Dipmani Kumar
• I-95 Landfill Complex – John Kellas
• Maintenance & Stormwater Management Division - Don Lacquement
• Fairfax County Park Authority - Ed. Richardson
• Land Acquisition Division - Carol Kresge
• Utilities Design and Construction Division (UDCD) - James Horstman
• Project Inspector, UDCD - Paul Thaler
• Survey Analyst, UDCD - Gregory Harper
4. Woodglen Lake Dredging and Restoration
Project Benefits
• Removed over 40,000 CY of sediment
• Facilitated future maintenance dredging operations by:
• Providing a 9,000 CY sediment forebay
• Improving the existing access road
• Providing truck staging areas
• Provided improvements and repairs for the principal spillway riser
• Installed fish habitat structures within the lake
• Provides the following annual (estimated ) reductions in the downstream
sediment and nutrient loadings:
• Total Suspended Solids (TSS) 14.6 tons/year
• Total Nitrogen (TN) 1,075 lbs/year
• Total Phosphorus (TP) 67 lbs/year
5. Woodglen Lake Dredging and Restoration
Capital Facilities / Utilities Design and Construction Division / Transportation and Stormwater Construction Branch
Tax Map 68-3 and 77-1
PROJECT LOCATION
6. Woodglen Lake Dredging and Restoration
Capital Facilities / Utilities Design and Construction Division / Transportation and Stormwater Construction Branch
The Lake After Draining
7. Woodglen Lake Dredging and Restoration
Capital Facilities / Utilities Design and Construction Division / Transportation and Stormwater Construction Branch
Sediment Near the Forebay – To Be Removed
8. Woodglen Lake Dredging and Restoration
Capital Facilities / Utilities Design and Construction Division / Transportation and Stormwater Construction Branch
Sediment Being Loaded
9. Woodglen Lake Dredging and Restoration
Capital Facilities / Utilities Design and Construction Division / Transportation and Stormwater Construction Branch
Forebay Separation Dike
10. Woodglen Lake Dredging and Restoration
Capital Facilities / Utilities Design and Construction Division / Transportation and Stormwater Construction Branch
Modifications & Repairs – Principal Spillway Riser
11. Woodglen Lake Dredging and Restoration
Capital Facilities / Utilities Design and Construction Division / Transportation and Stormwater Construction Branch
Stream Restoration Work – Lake Inlet
12. Woodglen Lake Dredging and Restoration
Capital Facilities / Utilities Design and Construction Division / Transportation and Stormwater Construction Branch
Planting
13. Additional Information
For additional Information, please call
www.fairfaxcounty.gov/dpwes
Woodglen Lake Dredging and Restoration
Capital Facilities / Utilities Design and Construction Division / Transportation and Stormwater Construction Branch
Irene Haske, Public Information Officer
703-324-5821, TTY 711
SWPDmail@fairfaxcounty.gov