Pohick Creek Restoration Project - Phase 1Fairfax County
The document summarizes Phase I of the Pohick Creek Restoration Project in Fairfax County, Virginia. The project involved constructing a rock wall and bench along the creek bank, installing live stakes and native plants, and adding soil lifts for stabilization. The project team from Fairfax County Public Works completed earthworks and bank stabilization along a section of Pohick Creek near the Noman M. Cole Jr. Pollution Control Plant by June 13, 2016.
Public Information Meeting: Realignment of Old Courthouse Road at Besley RoadFairfax County
This document summarizes a public information meeting held by the Fairfax County Department of Transportation regarding the realignment of Old Courthouse Road at Besley Road. The meeting covered project progress updates, revised roadway and bridge designs, hydrologic and hydraulic analysis of the new bridge structure, maintenance of traffic plans during construction, projected costs and schedule, and a question and answer session. Traffic on Besley Road will be detoured for approximately 6 months onto nearby roads. The adjacent communities will be notified of traffic changes through various means with advanced notice.
North Beauregard Street at North Chambliss Street Spot ImprovementFairfax County
This document summarizes a spot improvement project at the intersection of North Beauregard Street and North Chambliss Street in Fairfax County, VA. The project constructed a new concrete island, curb, sidewalk, and pedestrian flashing beacon to reduce the crossing distance and improve pedestrian safety. Construction was completed in October 2021 by contractor M&F Concrete. The project was managed by Fairfax County Department of Transportation and the Construction Division.
Pedestrian Access Improvements: Burke Lake Road at Coffer Woods RoadFairfax County
The Burke Lake Road / Coffer Woods Road Pedestrian Access Improvement project in Fairfax County, VA was substantially completed in March 2017. The project involved constructing 817 linear feet of sidewalk, curb and gutter, handicap ramps, asphalt paving, and storm sewer to provide continuous pedestrian access from Burke Town Court to Burke Lake Road. The project team installed sidewalk, storm sewer, filtration units, and replaced/closed some curb cuts for improved accessibility.
Dead Run at Dominican Retreat- Segment 1 Stream Restoration ProjectFairfax County
The Dead Run at Dominican Retreat - Segment 1 Stream Restoration project restored approximately 2,000 linear feet of Dead Run in Fairfax County, Virginia. The project used natural channel design principles to restore stream morphology, replace bridges and culverts, control invasive species, and add in-stream structures to reduce erosion. It was completed ahead of schedule and on budget in June 2017. The restoration aims to improve water quality and habitat in the tributary of Dead Run that flows into the Potomac River.
Oak Marr Pump Station Rehabilitation – Construction ProjectFairfax County
Neighborhood was built in the 1980s, and the sewer infrastructure has been in operation since.
Aged pump station equipment – pumps, valves, fans, concrete, etc.
This aging equipment has the potential of causing:
Sanitary Sewer Overflows (SSO)
Sewer back-ups into homes
Environmental damages
Maintenance problems
Reston Parkway at Dulles Toll Road Westbound On-Ramp and Eastbound Off-RampFairfax County
Reston Parkway at Dulles Toll Road EB and WB provides pedestrian access improvement at the intersection of Reston Parkway at Dulles Toll Road and to the intersection of Fairfax County Parkway and Sunset Hills Road.
Reston Parkway at Dulles Toll Road EB off-ramp and Reston Parkway at Dulles Toll Road WB on-ramp was substantially completed on October 6, 2021. Due to COVID-19 Pandemic, some of pedestrian signal electrical hardware and software supply delayed and created huge gap from the substantial completion date to the full activation of the project. The scope of this project was construction of concrete median islands, curb ramps, curb and gutter, and full replacement of asphalt trail, asphalt mill/overlay, signs and new pedestrian signals installation.
The Meadow Run (0273DP) Pond Improvement project in Fairfax County, VA was substantially completed on February 25, 2019. The project replaced a deteriorating control structure and primary spillway, increased the storage volume, and incorporated water quality improvements like extended detention and wetland plantings. It also upgraded the maintenance access with a geoblock road. The project aimed to improve water quality in the Bull Neck Run Watershed by accommodating more stormwater runoff and lengthening its flow path through the pond.
Pohick Creek Restoration Project - Phase 1Fairfax County
The document summarizes Phase I of the Pohick Creek Restoration Project in Fairfax County, Virginia. The project involved constructing a rock wall and bench along the creek bank, installing live stakes and native plants, and adding soil lifts for stabilization. The project team from Fairfax County Public Works completed earthworks and bank stabilization along a section of Pohick Creek near the Noman M. Cole Jr. Pollution Control Plant by June 13, 2016.
Public Information Meeting: Realignment of Old Courthouse Road at Besley RoadFairfax County
This document summarizes a public information meeting held by the Fairfax County Department of Transportation regarding the realignment of Old Courthouse Road at Besley Road. The meeting covered project progress updates, revised roadway and bridge designs, hydrologic and hydraulic analysis of the new bridge structure, maintenance of traffic plans during construction, projected costs and schedule, and a question and answer session. Traffic on Besley Road will be detoured for approximately 6 months onto nearby roads. The adjacent communities will be notified of traffic changes through various means with advanced notice.
North Beauregard Street at North Chambliss Street Spot ImprovementFairfax County
This document summarizes a spot improvement project at the intersection of North Beauregard Street and North Chambliss Street in Fairfax County, VA. The project constructed a new concrete island, curb, sidewalk, and pedestrian flashing beacon to reduce the crossing distance and improve pedestrian safety. Construction was completed in October 2021 by contractor M&F Concrete. The project was managed by Fairfax County Department of Transportation and the Construction Division.
Pedestrian Access Improvements: Burke Lake Road at Coffer Woods RoadFairfax County
The Burke Lake Road / Coffer Woods Road Pedestrian Access Improvement project in Fairfax County, VA was substantially completed in March 2017. The project involved constructing 817 linear feet of sidewalk, curb and gutter, handicap ramps, asphalt paving, and storm sewer to provide continuous pedestrian access from Burke Town Court to Burke Lake Road. The project team installed sidewalk, storm sewer, filtration units, and replaced/closed some curb cuts for improved accessibility.
Dead Run at Dominican Retreat- Segment 1 Stream Restoration ProjectFairfax County
The Dead Run at Dominican Retreat - Segment 1 Stream Restoration project restored approximately 2,000 linear feet of Dead Run in Fairfax County, Virginia. The project used natural channel design principles to restore stream morphology, replace bridges and culverts, control invasive species, and add in-stream structures to reduce erosion. It was completed ahead of schedule and on budget in June 2017. The restoration aims to improve water quality and habitat in the tributary of Dead Run that flows into the Potomac River.
Oak Marr Pump Station Rehabilitation – Construction ProjectFairfax County
Neighborhood was built in the 1980s, and the sewer infrastructure has been in operation since.
Aged pump station equipment – pumps, valves, fans, concrete, etc.
This aging equipment has the potential of causing:
Sanitary Sewer Overflows (SSO)
Sewer back-ups into homes
Environmental damages
Maintenance problems
Reston Parkway at Dulles Toll Road Westbound On-Ramp and Eastbound Off-RampFairfax County
Reston Parkway at Dulles Toll Road EB and WB provides pedestrian access improvement at the intersection of Reston Parkway at Dulles Toll Road and to the intersection of Fairfax County Parkway and Sunset Hills Road.
Reston Parkway at Dulles Toll Road EB off-ramp and Reston Parkway at Dulles Toll Road WB on-ramp was substantially completed on October 6, 2021. Due to COVID-19 Pandemic, some of pedestrian signal electrical hardware and software supply delayed and created huge gap from the substantial completion date to the full activation of the project. The scope of this project was construction of concrete median islands, curb ramps, curb and gutter, and full replacement of asphalt trail, asphalt mill/overlay, signs and new pedestrian signals installation.
The Meadow Run (0273DP) Pond Improvement project in Fairfax County, VA was substantially completed on February 25, 2019. The project replaced a deteriorating control structure and primary spillway, increased the storage volume, and incorporated water quality improvements like extended detention and wetland plantings. It also upgraded the maintenance access with a geoblock road. The project aimed to improve water quality in the Bull Neck Run Watershed by accommodating more stormwater runoff and lengthening its flow path through the pond.
Community Meeting - Indian Run Gravity Sewer Replacement Construction ProjectFairfax County
2019 study evaluated several alternatives for replacement
Selected alternative would:
Eliminate the exposed sewer/stream crossing
Maintain level of sewer services to the community
Provide future access ease to Fairfax County’s wastewater operator
Improve system’s reliability in the area
Reduce future risk of sanitary sewer overflows
Reduce risk to public health and the environment
High Ridge Lakevale Estates Langley Oaks and Weid Pump Stations ProjectFairfax County
The work under this project included provision for the replacement of all pumping, piping, valves, generator, electrical, and mechanical equipment at each pump station. Each pump station also included structural and architectural repairs for the buildings as well as the installation of a security system. Miscellaneous site and civil modifications were also completed. This project was substantially complete on May 27, 2021.
The four pump stations (PS) included, Lakevale PS (10209 Kenbrooke Ct, Vienna), High Ridge PS (3890 Fairfax Ridge Rd, Fairfax), Weid PS (8418A Holly Leaf Drive, McLean), and Langley Oaks PS (6526 Heather Brook Ct, McLean)
Retrofit Facility DP0625 West Potomac High SchoolFairfax County
The West Potomac High School pond retrofit project was completed in October 2017. The project involved regrading the pond to lengthen the flow path and maximize storage volume. Two curb inlets were installed to capture runoff, and the existing riser structure was replaced. Improvements are expected to increase water residence time and provide enhanced water quality benefits by reducing nitrogen by 76.30 lbs/yr, phosphorus by 13.19 lbs/yr, and suspended solids by 12,416.43 lbs/yr. The project team included members from Fairfax County stormwater planning and construction divisions along with a design consultant.
Walton Boulevard Reconstruction, APWA Project of the YearOHM Advisors
http://www.ohm-advisors.com. An APWA award-winning project, reconstructing Walton Boulevard, in the City of Auburn Hills, was no easy task. Start with 1.5 miles of road, an old bridge over a major freeway, and three government owners. Then, throw in high priority federal and state funding deadlines and a five month schedule to complete. No problem. If you're OHM, and you're committed to Advancing Communities!
McLean Hunt Estates Pond Improvement ProjectFairfax County
The McLean Hunt Estates Pond Improvement Project consisted of retrofitting an existing dry pond to an extended detention dry pond. The goals of the project were to stabilize the incoming degraded channel constructing a step pool conveyance system; replace the existing corrugated metal pipe principal spillway pipe with reinforced concrete pipe; install a new riser structure with BMP plate to provide water quality benefits; and upgrade the asphalt trail into an access road to accommodate equipment/vehicles for future maintenance.
Little Pimmit Run at Woodland Terrace Community Meeting 09 30-2020Fairfax County
A community meeting was held on Sept 30, 2020 to inform residents and gather information from them about the stream restoration project at Little Pimmit Run Tributary at Woodland Terrace.
Mount Vernon Memorial Highway Trail Public Information Meeting: March 14, 2018Fairfax County
This document summarizes a public information meeting held by the Fairfax County Department of Transportation regarding plans to complete missing segments of the Potomac Heritage National Scenic Trail between Richmond Highway and Southwood Drive in Mount Vernon, Virginia. The meeting covered the project purpose and description, existing conditions, conceptual design plans featuring a pedestrian bridge over Dogue Creek and potential impacts. Next steps include accepting public feedback until April 8th and further design and environmental review before a follow-up public meeting.
Dead Run Force Main Rehabilitation ProjectFairfax County
The document summarizes a project to rehabilitate an existing 14-inch cast iron force main in Fairfax County, Virginia. The project involved lining the 2,700 linear feet of force main with cured-in-place pipe lining, installing storm culverts under five driveways to improve drainage, replacing an existing concrete culvert, restoring ditches and driveways, and adding safety measures. The project was substantially completed in September 2016 to repair the 60-year old force main running from Dead Run Drive to Dolly Madison Boulevard.
Waynewood l Force Main Rehabilitation Project Jan 8, 2021Fairfax County
The Waynewood I Force Main Rehabilitation Project rehabilitated roughly 700 feet of aging asbestos cement force main piping servicing the Waynewood I pump station through cured-in-place pipe lining. This minimally invasive lining method required only small excavations. The project also installed an emergency bypass vault, relocated overhead utility lines underground, and improved site access. Completed in December 2020, the improvements are expected to increase the force main's lifespan by 50 years and reduce risks of sanitary sewer overflows.
The Herndon Station Metro Garage project provides a new six-level pre-cast parking structure with seven tiers of parking to accommodate over 2,000 added parking spaces. This project addresses the increased parking demand associated with the coming arrival of the Silver Line Metro, and supports the expanded use of public, mass transportation in the area. The project also provides secure bicycle storage for 130 bikes, energy efficient LED lighting fixtures throughout the garage, and vehicular and pedestrian bridge connections to the existing garage. Infrastructure and site improvements include utilities and road widening coordinated with the Silver Line Phase 2 project, direct vehicular garage egress to the Dulles Toll Road to reduce traffic impact on local roads, and enhanced stormwater management serving the site.
The Indian Run Restoration Project restored sections of Indian Run in Fairfax County, VA by stabilizing stream banks, installing structures like plunge pools and rock walls, and planting native vegetation. The project also included eight low impact development facilities and improved stormwater outfalls. Completed in September 2014, the project enhanced water quality and protected the channel while coming in under budget.
The Oakton Community Park Phase 2A project consisted of a new reinforced concrete roundabout, concrete and asphalt sidewalks, curb ramps, concrete medians, and curb and gutter. The scope of work also included storm drainage, site improvements, asphalt restoration, pavement markings and other associated work.
The Huntsman Lake Dredging project in Fairfax County, VA involved removing over 43,000 cubic yards of sediment from Huntsman Lake to increase its sediment storage capacity to over 100 years. It also included restoring the shoreline, improving aquatic habitat, and upgrading access and maintenance of the lake. The project enhances sediment and nutrient removal to improve water quality downstream.
Potomac Meadow Water Quality Improvement July 2016Fairfax County
The Potomac Meadow Water Quality Improvements Project retrofitted an existing stormwater pond in Fairfax County, VA to improve water quality. The project included installing bioswales, replacing culverts, constructing stormwater wetlands, and modifying the pond structure. The project was completed on time and within budget in March 2016 to treat stormwater runoff from surrounding residential areas and reduce pollution entering Pond Branch Watershed.
The document provides an agenda and updates for a meeting of the Murch ES School Improvement Team (SIT) regarding the building project at Murch Elementary School. It summarizes design concerns heard from the SIT and community and reviews proposed updates to address those concerns, including changes to the cafeteria, gym, media center, classrooms, and site layout. It also reviews renderings of the proposed design and provides an overview of the project schedule, including plans for swing space during construction.
Scotts Run Tributary at Windy Hill Road Stream StabilizationFairfax County
This stream stabilization is located within the Scotts Run Watershed in McLean, Va. The project restored 600 feet of intermittent stream using natural channel design, installed a new drop inlet, 32 linear feet of 36-inch diameter reinforced concrete pipe, an end wall at Box Elder Court, and installation of instream structures such as rock weir, imbricated toe protection, step pools, reinforced bed material.
Lake Accotink Dredge Public Meeting Combined Presentation July 29 & aug 5...Fairfax County
This document provides information about alternatives being considered for dredging Lake Accotink in Fairfax County, VA. It summarizes the project background, including previous dredging events and sediment deposition rates. It then discusses the development and screening of various dredging, dewatering, disposal location, and pipeline route alternatives. Key factors like impacts to the community, environment, and costs were considered. The document retains several processing area, dewatering location, and pipeline route alternatives for further analysis to identify a preferred alternative for dredging Lake Accotink.
Workhouse Arts Foundation Cross-County TrailFairfax County
The document summarizes a project to construct pedestrian and bicycle trails at the Workhouse Arts Foundation Center in Fairfax County, VA. The project included building 2,850 feet of asphalt trail and 450 feet of stone dust trail, along with curb cuts, signage, and other safety improvements. The project was completed on June 26, 2018 and involved the Department of Transportation, Utilities Design and Construction Division, and other county teams and branches. Photos document the construction process and final results of the new trails.
PowerPoint Westmoreland Street Bike Lanes - substantial completionFairfax County
Westmoreland Street bike lanes project was substantially completed on April 12, 2021. The project scope was the extension of road bike lanes along both sides of Westmoreland Street north of Rosemont Drive toward Old Chesterbrook Road. Works on the project included roadway widening, approximately 400 feet long concrete variable width sidewalk, curb and gutters, driveway entrances, bus stop loading pad, milling and paving, pavement marking and signs.
Accotink Creek Watershed Project Wakefield Park NorthFairfax County
The Wakefield Park North Stream Restoration project in Fairfax County, Virginia was completed ahead of schedule and under budget. The project restored 900 linear feet of an unnamed tributary to Accotink Creek using natural channel design techniques. This included establishing a stable channel, reconnecting it to the floodplain, adding grade control structures, and creating wetland areas to improve habitat and reduce pollution entering Accotink Creek.
Franklin Park and Chesterbrook Neighborhood Stormwater Improvement ProjectFairfax County
The Fairfax County Department of Public Works and Environmental Services upgraded over 3000 linear feet of stormwater infrastructure in the Franklin Park and Chesterbrook neighborhoods to reduce flooding, improve stormwater flow and water quality. The project was completed on time and on budget in December 2016 through the construction of swales, infiltration trenches, underground storage chambers and permeable surfaces. The project is estimated to reduce nitrogen, phosphorus and sediment runoff into local waterways.
Community Meeting - Indian Run Gravity Sewer Replacement Construction ProjectFairfax County
2019 study evaluated several alternatives for replacement
Selected alternative would:
Eliminate the exposed sewer/stream crossing
Maintain level of sewer services to the community
Provide future access ease to Fairfax County’s wastewater operator
Improve system’s reliability in the area
Reduce future risk of sanitary sewer overflows
Reduce risk to public health and the environment
High Ridge Lakevale Estates Langley Oaks and Weid Pump Stations ProjectFairfax County
The work under this project included provision for the replacement of all pumping, piping, valves, generator, electrical, and mechanical equipment at each pump station. Each pump station also included structural and architectural repairs for the buildings as well as the installation of a security system. Miscellaneous site and civil modifications were also completed. This project was substantially complete on May 27, 2021.
The four pump stations (PS) included, Lakevale PS (10209 Kenbrooke Ct, Vienna), High Ridge PS (3890 Fairfax Ridge Rd, Fairfax), Weid PS (8418A Holly Leaf Drive, McLean), and Langley Oaks PS (6526 Heather Brook Ct, McLean)
Retrofit Facility DP0625 West Potomac High SchoolFairfax County
The West Potomac High School pond retrofit project was completed in October 2017. The project involved regrading the pond to lengthen the flow path and maximize storage volume. Two curb inlets were installed to capture runoff, and the existing riser structure was replaced. Improvements are expected to increase water residence time and provide enhanced water quality benefits by reducing nitrogen by 76.30 lbs/yr, phosphorus by 13.19 lbs/yr, and suspended solids by 12,416.43 lbs/yr. The project team included members from Fairfax County stormwater planning and construction divisions along with a design consultant.
Walton Boulevard Reconstruction, APWA Project of the YearOHM Advisors
http://www.ohm-advisors.com. An APWA award-winning project, reconstructing Walton Boulevard, in the City of Auburn Hills, was no easy task. Start with 1.5 miles of road, an old bridge over a major freeway, and three government owners. Then, throw in high priority federal and state funding deadlines and a five month schedule to complete. No problem. If you're OHM, and you're committed to Advancing Communities!
McLean Hunt Estates Pond Improvement ProjectFairfax County
The McLean Hunt Estates Pond Improvement Project consisted of retrofitting an existing dry pond to an extended detention dry pond. The goals of the project were to stabilize the incoming degraded channel constructing a step pool conveyance system; replace the existing corrugated metal pipe principal spillway pipe with reinforced concrete pipe; install a new riser structure with BMP plate to provide water quality benefits; and upgrade the asphalt trail into an access road to accommodate equipment/vehicles for future maintenance.
Little Pimmit Run at Woodland Terrace Community Meeting 09 30-2020Fairfax County
A community meeting was held on Sept 30, 2020 to inform residents and gather information from them about the stream restoration project at Little Pimmit Run Tributary at Woodland Terrace.
Mount Vernon Memorial Highway Trail Public Information Meeting: March 14, 2018Fairfax County
This document summarizes a public information meeting held by the Fairfax County Department of Transportation regarding plans to complete missing segments of the Potomac Heritage National Scenic Trail between Richmond Highway and Southwood Drive in Mount Vernon, Virginia. The meeting covered the project purpose and description, existing conditions, conceptual design plans featuring a pedestrian bridge over Dogue Creek and potential impacts. Next steps include accepting public feedback until April 8th and further design and environmental review before a follow-up public meeting.
Dead Run Force Main Rehabilitation ProjectFairfax County
The document summarizes a project to rehabilitate an existing 14-inch cast iron force main in Fairfax County, Virginia. The project involved lining the 2,700 linear feet of force main with cured-in-place pipe lining, installing storm culverts under five driveways to improve drainage, replacing an existing concrete culvert, restoring ditches and driveways, and adding safety measures. The project was substantially completed in September 2016 to repair the 60-year old force main running from Dead Run Drive to Dolly Madison Boulevard.
Waynewood l Force Main Rehabilitation Project Jan 8, 2021Fairfax County
The Waynewood I Force Main Rehabilitation Project rehabilitated roughly 700 feet of aging asbestos cement force main piping servicing the Waynewood I pump station through cured-in-place pipe lining. This minimally invasive lining method required only small excavations. The project also installed an emergency bypass vault, relocated overhead utility lines underground, and improved site access. Completed in December 2020, the improvements are expected to increase the force main's lifespan by 50 years and reduce risks of sanitary sewer overflows.
The Herndon Station Metro Garage project provides a new six-level pre-cast parking structure with seven tiers of parking to accommodate over 2,000 added parking spaces. This project addresses the increased parking demand associated with the coming arrival of the Silver Line Metro, and supports the expanded use of public, mass transportation in the area. The project also provides secure bicycle storage for 130 bikes, energy efficient LED lighting fixtures throughout the garage, and vehicular and pedestrian bridge connections to the existing garage. Infrastructure and site improvements include utilities and road widening coordinated with the Silver Line Phase 2 project, direct vehicular garage egress to the Dulles Toll Road to reduce traffic impact on local roads, and enhanced stormwater management serving the site.
The Indian Run Restoration Project restored sections of Indian Run in Fairfax County, VA by stabilizing stream banks, installing structures like plunge pools and rock walls, and planting native vegetation. The project also included eight low impact development facilities and improved stormwater outfalls. Completed in September 2014, the project enhanced water quality and protected the channel while coming in under budget.
The Oakton Community Park Phase 2A project consisted of a new reinforced concrete roundabout, concrete and asphalt sidewalks, curb ramps, concrete medians, and curb and gutter. The scope of work also included storm drainage, site improvements, asphalt restoration, pavement markings and other associated work.
The Huntsman Lake Dredging project in Fairfax County, VA involved removing over 43,000 cubic yards of sediment from Huntsman Lake to increase its sediment storage capacity to over 100 years. It also included restoring the shoreline, improving aquatic habitat, and upgrading access and maintenance of the lake. The project enhances sediment and nutrient removal to improve water quality downstream.
Potomac Meadow Water Quality Improvement July 2016Fairfax County
The Potomac Meadow Water Quality Improvements Project retrofitted an existing stormwater pond in Fairfax County, VA to improve water quality. The project included installing bioswales, replacing culverts, constructing stormwater wetlands, and modifying the pond structure. The project was completed on time and within budget in March 2016 to treat stormwater runoff from surrounding residential areas and reduce pollution entering Pond Branch Watershed.
The document provides an agenda and updates for a meeting of the Murch ES School Improvement Team (SIT) regarding the building project at Murch Elementary School. It summarizes design concerns heard from the SIT and community and reviews proposed updates to address those concerns, including changes to the cafeteria, gym, media center, classrooms, and site layout. It also reviews renderings of the proposed design and provides an overview of the project schedule, including plans for swing space during construction.
Scotts Run Tributary at Windy Hill Road Stream StabilizationFairfax County
This stream stabilization is located within the Scotts Run Watershed in McLean, Va. The project restored 600 feet of intermittent stream using natural channel design, installed a new drop inlet, 32 linear feet of 36-inch diameter reinforced concrete pipe, an end wall at Box Elder Court, and installation of instream structures such as rock weir, imbricated toe protection, step pools, reinforced bed material.
Lake Accotink Dredge Public Meeting Combined Presentation July 29 & aug 5...Fairfax County
This document provides information about alternatives being considered for dredging Lake Accotink in Fairfax County, VA. It summarizes the project background, including previous dredging events and sediment deposition rates. It then discusses the development and screening of various dredging, dewatering, disposal location, and pipeline route alternatives. Key factors like impacts to the community, environment, and costs were considered. The document retains several processing area, dewatering location, and pipeline route alternatives for further analysis to identify a preferred alternative for dredging Lake Accotink.
Workhouse Arts Foundation Cross-County TrailFairfax County
The document summarizes a project to construct pedestrian and bicycle trails at the Workhouse Arts Foundation Center in Fairfax County, VA. The project included building 2,850 feet of asphalt trail and 450 feet of stone dust trail, along with curb cuts, signage, and other safety improvements. The project was completed on June 26, 2018 and involved the Department of Transportation, Utilities Design and Construction Division, and other county teams and branches. Photos document the construction process and final results of the new trails.
PowerPoint Westmoreland Street Bike Lanes - substantial completionFairfax County
Westmoreland Street bike lanes project was substantially completed on April 12, 2021. The project scope was the extension of road bike lanes along both sides of Westmoreland Street north of Rosemont Drive toward Old Chesterbrook Road. Works on the project included roadway widening, approximately 400 feet long concrete variable width sidewalk, curb and gutters, driveway entrances, bus stop loading pad, milling and paving, pavement marking and signs.
Accotink Creek Watershed Project Wakefield Park NorthFairfax County
The Wakefield Park North Stream Restoration project in Fairfax County, Virginia was completed ahead of schedule and under budget. The project restored 900 linear feet of an unnamed tributary to Accotink Creek using natural channel design techniques. This included establishing a stable channel, reconnecting it to the floodplain, adding grade control structures, and creating wetland areas to improve habitat and reduce pollution entering Accotink Creek.
Franklin Park and Chesterbrook Neighborhood Stormwater Improvement ProjectFairfax County
The Fairfax County Department of Public Works and Environmental Services upgraded over 3000 linear feet of stormwater infrastructure in the Franklin Park and Chesterbrook neighborhoods to reduce flooding, improve stormwater flow and water quality. The project was completed on time and on budget in December 2016 through the construction of swales, infiltration trenches, underground storage chambers and permeable surfaces. The project is estimated to reduce nitrogen, phosphorus and sediment runoff into local waterways.
The Wakefield Park South Stream Restoration project in Fairfax County, VA was completed ahead of schedule and on budget. The project restored 2,700 linear feet of streams that feed into Accotink Creek using natural channel design techniques. This included establishing stable channels and floodplains, installing structures to reduce erosion and improve habitat, and reducing nitrogen, phosphorus, and sediment runoff into Accotink Creek. The project was a collaboration between Fairfax County agencies and private contractors.
Quander Road Outfall and Stream RestorationFairfax County
The Quander Road Stream Restoration project restored approximately 775 linear feet of a highly eroded storm drainage channel and 225 linear feet of an associated tributary using natural channel design techniques. This included installing structures like boulder pools, step pools, and rock sills to prevent future erosion and planting native vegetation to improve water quality. The project reduced nitrogen by over 3,000 pounds per year, phosphorus by over 1,300 pounds per year, and suspended solids by over 230 tons per year. Before the project, the stream banks were very steep and highly eroded, and the restoration efforts reconnected the channel to the floodplain and re-established natural flow dynamics.
The Woodglen Lake Dredging & Restoration project in Fairfax County, VA removed over 40,000 cubic yards of sediment from Woodglen Lake. The project improved maintenance access and installed a sediment forebay to simplify future dredging. Dredged sediment was disposed of innovatively at the County-owned I-95 Landfill Complex. Stream restoration and landscaping around the lake also enhanced the area. The project reduces annual sediment and nutrient loads in downstream waters.
Turkeycock Run at Mason District Park Stream Restoration ProjectFairfax County
The Turkeycock Run at Mason District Park Stream Restoration Project included 1,580 linear feet of stream restoration through natural channel design to enhance/stabilize and restore the stream channel to improve water quality.
Banks Property Stream Restoration (DC9218)Fairfax County
The Banks Property Stream Restoration project restored 1,150 linear feet of degraded stream tributary. The project established a stable channel geometry, reconnected the stream to its floodplain, stabilized the stream bed and banks with structures like rock sills and cross-vanes, daylighted piped sections, and replanted the site with native vegetation. The restoration is estimated to reduce nitrogen, phosphorus, and sediment loads to the stream. The project involved several Fairfax County departments and private organizations and was substantially completed in November 2014.
This document provides details about a pond retrofit project in Fairfax County, VA called Towlston Meadows Sec 3 Pond 1. The purpose of the project was to increase water quality and add an access road for maintenance. Work included regrading the pond, adding micro pools, increasing storage volume, and constructing an all-weather access road. Native plants were also installed to restore the landscape. The project was completed on time and on budget in April 2014.
Flatlick Branch-Phase 1 Stream RestorationFairfax County
The Flatlick Branch - Phase I Stream Restoration project involved restoring over 1,850 linear feet of stream and tributaries. It upgraded an existing stormwater basin to a constructed wetland, replaced a failed stream crossing, and sewer main. Native plants were installed, and the project provides pollutant removal and water quality benefits. Completed in December 2016, it enhanced the stream valley through inter-agency cooperation between Fairfax County agencies and the Park Authority.
Flatlick Branch - Phase 1 Stream RestorationFairfax County
The Flatlick Branch - Phase I Stream Restoration project involved restoring over 1,850 linear feet of stream and tributaries. It upgraded an existing stormwater basin to a constructed wetland, replaced a failed stream crossing, and sewer main. Native plants were installed, and the project provides pollutant removal and water quality benefits. Substantially completed in December 2016, it was a partnership between Fairfax County agencies and the Park Authority.
Rabbit Branch Tributary Restoration ProjectFairfax County
The Rabbit Branch Tributary project restored over 1,500 linear feet of degraded stream channel using natural channel design techniques. The project established a stable channel geometry, reconnected the stream to its floodplain, installed in-stream structures to reduce erosion and improve habitat, and planted native vegetation. The restoration is expected to reduce nitrogen, phosphorus, and sediment pollution entering Pohick Creek on an annual basis. The project involved teams from Fairfax County and private environmental firms.
Intersection Sight Distance Improvement: Old Dominion Drive at Bellview RoadFairfax County
The Old Dominion Drive at Bellview Road Project in Fairfax County, VA was substantially completed in December 2015. The project involved removing existing embankments and trees along Old Dominion Drive to improve sight distance at the intersection, and installing concrete pipes to improve runoff. The project team removed embankments and vegetation, installed reinforced concrete pipes, implemented soil stabilization techniques, and graded ditches to complete the work.
The Bradley Acres Pond Retrofit project in Fairfax County, VA converted an existing dry pond into a constructed wetland pond. The project removed the existing trickle ditch, excavated three shallow marshes, constructed a step pool conveyance channel and plunge pool, and installed two stone weir structures. Native plants were seeded and trees/plugs were replanted. The project provides improved downstream water quality by removing nutrients and suspended solids from stormwater runoff.
Accotink Creek at Wakefield Park Stream Restoration ProjectFairfax County
Accotink Creek at Wakefield Park Stream Restoration project was substantially completed on November 23, 2021. This project consists of restoring, enhancing, and stabilizing of approximately 4,900 linear feet of stream channel through the installation of four Newbury Riffles within the main channel of Accotink Creek and one Newbury Riffle within a side channel to provide aquatic benefits, grade control, improve water quality and prevent further erosion.
Colvin Run Phase I Lake Fairfax Park Stream Restoration ProjectFairfax County
The Colvin Run Phase I Lake Fairfax Park Stream Restoration Project restored 2,220 feet of Colvin Run Branch in Fairfax County, VA through natural channel design. This included improving stream morphology, reducing erosion, re-aligning the stream, creating wetlands, replacing a culvert, and landscaping with native plants. The project team included various Fairfax County departments and was completed in August 2017. It is estimated to reduce pollution in the stream annually.
Oakton Swim and Racquet Water Quality RetrofitFairfax County
The Oakton Swim & Racquet Water Quality Retrofit Project in Fairfax County, VA involved retrofitting three stormwater inlet areas with rain gardens to improve water quality. The project was completed in April 2015. It installed rain gardens to remove sediment and pollutants from stormwater runoff, reducing nitrogen, phosphorus, and sediment levels in nearby waterways. The project team included members from the county's Stormwater Planning Division, Urban Forest Management Division, and Utilities Design and Construction Division.
Pohick Creek Tributary Stream Restoration ProjectFairfax County
The Fairfax County Department of Public Works and Environmental Services restored over 1,300 linear feet of degraded tributary of Pohick Creek using natural channel design techniques. This included establishing a stable channel geometry, reconnecting the channel to its floodplain, installing in-stream structures, and replanting native vegetation. The project aims to reduce erosion and improve habitat while also decreasing nitrogen, phosphorus, and sediment runoff into Pohick Creek. Construction involved excavating the existing channel, installing grade control structures, and cleaning out the existing stormwater pond.
The Peppercorn Drive Outfall Restoration project in Fairfax County, VA was completed in August 2015. The project involved installing a drop inlet structure, extending the storm sewer pipe, and adding a concrete end wall and step pool system to stabilize an eroded outfall between two properties on Peppercorn Drive. The project team extended the existing storm pipe, constructed a plunge pool and two step pool structures using stone, and stabilized the channel banks with grading and coir matting.
Long Branch Tributary at Long Branch Falls ParkFairfax County
The Long Branch Tributary at Long Branch Falls Park project restored approximately 670 linear feet of stream within the Accotink Creek watershed. The stream channel was enhanced and stabilized using natural channel design elements. Existing erosion damage was repaired and future water quality has been improved. The project included channel realignment, in-stream rock structures, log structures, constructed wetlands, wood habitat clusters, deer exclusion fence, removal of invasive plants and the re-establishment of the riparian buffer with native species.
Franklin Park Chesterbrook Neighborhood Project HighlightsFairfax County
This project included 3,000 linear feet of stormwater improvements that promote infiltration, improve water quality, and safely convey stormwater through the neighborhood to a stream.
Similar to Brookfield Park Wet Pond Construction (20)
Merrifield Nursery Emergency Gravity Sewer ReplacementFairfax County
During a routine Closed-Circuit Television (CCTV) Camera inspection by Wastewater Collection Division (WCD), it was found that 45 linear feet of 8-inch asbestos reinforced concrete pipe (RCP) between MH-292 to MH-291 was within imminent danger of failing. The bottom of the RCP was missing within the 45 linear feet of repair and the pipe was on the verge of surcharging. After an immediate pre-construction meeting with Merrifield Nursery, it was agreed to work from 6pm-10am everyday of the week to avoid disruption and potentially placing patrons at risk during the biggest time of the year for Merrifield Garden Center. The contractor mobilized to the site and began the 20-foot excavation to replace 45 linear feet of broken gravity sewer. The project started on March 14th, 2022 and was substantially complete on March 23, 2022.
The Sully Basins Stormwater Pond Retrofits project was substantially completed on April 19, 2022. The project is located within the Cub Run watershed. The project consisted of repair and enhancement of multiple stormwater basins, 0326DP, 0964DP and 1484DP. The project also included construction of new stone cascades, stone weir basin structures and the construction of wetlands with high and low marsh areas. The project will facilitate improved sediment removal and improve downstream water quality using forebays and micro pools. Aquatic and natural habitat were also added within the three basins.
Clarks Crossing Road Improvements 05-13-22Fairfax County
This document summarizes a pedestrian access improvement project along Clarks Crossing Road in Fairfax County, Virginia. The project improved pedestrian and bicycle access by constructing a missing link of sidewalk between Brookside Lane and an existing sidewalk further along Clarks Crossing Road. Work included installing sidewalk, curb ramps, drainage improvements, and milling and overlaying asphalt. The project was substantially completed in March 2022 and provides approximately 200 feet of new pedestrian access along Clarks Crossing Road.
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxFairfax County
Future wastewater flows in northern Fairfax County exceed existing system capacity
Treatment capacity is available in Noman M. Cole Jr. Pollution Control Plant in Lorton, VA
New pipes and pumps are needed to move future flows to treatment plant
NEXT STEPS
Field investigations / surveys
Finalize alignments and pump station layout
Use of open cut excavation
Use of trenchless methods
Easement acquisition needed
Develop traffic control plans
Description:
The project consists of a new, 23,000 square feet, two-story, four-bay fire station facility and associated improvements to the 3.3-acre site including storm water detention, landscaping and parking. The scope also included the demolition of the existing fire station, and a temporary fire station to house the Fire and Rescue Department during construction of the new facility. The key elements of the overall project include:
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationFairfax County
Scotts Run @ Old Meadow Road Stream Restoration was substantially completed on March 30, 2022. The Scotts Run project consisted of restoring, enhancement, and stabilizing of approximately 2,930 linear feet of eroding stream using Natural Channel Design criteria. This project included two phases: Phase I was funded by proffers from a private development and Phase II was County funded. Also included was the removal of invasive non-native plants and the installation of new plantings to stabilize the stream and floodplain.
Sully Community Center Construction ProgressFairfax County
This document provides construction progress photos of the Sully Community Center in Fairfax County, Virginia. The photos show the ongoing construction of the building's exterior, interior spaces like the lobby, corridors, multi-purpose rooms, game room, gym, exercise room, and healthcare suite. The document was published by the Fairfax County Department of Public Works and Environmental Services to share updates on the construction of the new community center, which is scheduled to open in summer 2022.
Riverwood Community Meeting - 04-14-2022- Presentation.pptxFairfax County
The new 4-inch ductile iron force main will serve the surrounding community for the foreseeable future. Replacement of the force main will:
Reduce the level and frequency of maintenance required to keep the force main operating.
Prevent costly emergency repairs.
Provide residents with safe, reliable utility infrastructure.
Enhance the quality of life for residents.
Reduce risks to public health and the environment.
Burke Centre VRE Connector Phase IV project was substantially completed on March 7, 2022. This project enhanced the access to mass transit by creating a more direct connection from the VRE Station to the residential areas west of Premier Court. This project also connects the Oak Bluff community to the Virginia Rail Express (VRE) Burke Station and provides a multi-use shared pedestrian and bicycle trail for outdoor recreation.
Long Branch Public Meeting - FINAL - 04-11-2022Fairfax County
Overarching Project Goals:
-Achieve Long Branch Central TMDL waste load reduction requirements.
-Provide long-term stability and have low maintenance.
-Improve water quality within the Long Branch Central Watershed.
-Improve habitat and environmental health (ecological lift).
Objectives: Share our project understanding with the council and seek input on the unique opportunities and housing goals for this site that could help guide
our master planning process.
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptxFairfax County
4,800 linear feet of stream will be restored using Natural Channel Design methodologies
Pollutant reduction
1,439 lbs/total phosphorus
3,400 lbs/total nitrogen
462.1 tons of total suspended sediment
Protection of private property and public infrastructure
Increased ecological diversity with native vegetation
DEQ has awarded a SLAF grant to this project for these environmental benefits
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT Fairfax County
The Lake Barton Dredging, Restoration, and Riser Modification project was substantially completed on December 29, 2021. The project is located within the Pohick Creek watershed. The project consisted of dredging and removal of approximately 19,100 cubic yards of sediment to restore the sediment trapping capacity and improve water quality. The project also included construction of new sediment forebays, in-lake haul roads, and riser modifications (new mid-level sluice gate and cold-water intake) to facilitate future maintenance, stabilize the shoreline, and improve downstream water quality. Fish habitat was also added within the lake.
Reston Arts Community Center Feasibility - Wrap UpFairfax County
This document summarizes a meeting about a proposed arts center in Reston, Virginia that would result from a proffer from Boston Properties for development of an area known as Block J. The meeting covered the background and objectives of community outreach efforts to understand needs for the arts venue. Feedback was shared from previous focus group meetings on performing arts, visual arts, and other topics. Key spaces discussed included a 500-seat theater, art studios, galleries, and support spaces. Next steps include further programming, cost estimating, and community input before potential design and construction.
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Fairfax County
Benefits of Consolidated Facility
Building and Site Efficiencies
Operational Efficiencies
Addresses Space Deficiencies
Addresses Renovations and Capital Renewal Requirements
for WCD
Provides for a Centrally Located Site that Accommodates Program
Consolidates Integrated Services on One Centrally Located Site
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Fairfax County
This is the 4th of 5 engagement meetings. We are excited to hear from you – your preferences, priorities, questions, hopes, concerns. The information we receive today will be used to inform the space allocations and cost estimating for discussion of the proffer by Fairfax County.
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Fairfax County
Identify and evaluate house flooding and public safety concerns
Improve drainage conditions to convey 100-year storm if feasible
Reduce and treat stormwater runoff at the source
Improve water quality and stream protection
Use resilient & functional designs
Make improvements compatible with characteristics of neighborhood
Partner with community to develop sound, cost effective solutions that can be collaboratively implemented and maintained
Build on lessons learned to help improve site development process for infill development
Reston Arts Center Feasibility - Focus Group Visual ArtsFairfax County
This document summarizes a focus group meeting to discuss needs and ideas for a proposed new arts center in Reston, Virginia. The meeting covered background on the proposed project, which would result from a development proffer. Attendees provided input through polls and discussion on desired visual arts programming, spaces, and amenities. Key priorities identified included studio space, galleries, classrooms, digital media facilities, and ensuring the center is diverse, equitable and accessible. The project team will take this community feedback into account as they continue planning.
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022Fairfax County
These community outreach meetings are being conducted to understand community needs for a proposed arts venue in the Reston Town Center.
The proposed arts center would be a result of a proffer from Boston Properties in the next phase of Reston Town Center development (Block J).
The proffer would provide for an approximately 60,000 gross square foot facility to house a stage suitable for large-scale music and dance performances, as well as other arts-related amenities.
POPE FRANCIS 2ND ENCYCLICAL "Laudato Si" is the second encyclical of Pope Fra...AdelinePdelaCruz
"Laudato Si" is the second encyclical of Pope Francis, released on May 24, 2015. Its title comes from the opening words of the encyclical in Latin, which mean "Praise Be to You." The document focuses on the theme of care for our common home, urging humanity to take action to address environmental degradation, climate change, and social inequality. Pope Francis calls for an integral ecology that considers the interconnectedness of environmental, social, economic, and spiritual dimensions.
Exploring low emissions development opportunities in food systemsCIFOR-ICRAF
Presented by Christopher Martius (CIFOR-ICRAF) at "Side event 60th sessions of the UNFCCC Subsidiary Bodies - Sustainable Bites: Innovating Low Emission Food Systems One Country at a Time" on 13 June 2024
The modification of an existing product or the formulation of a new product to fill a newly identified market niche or customer need are both examples of product development. This study generally developed and conducted the formulation of aramang baked products enriched with malunggay conducted by the researchers. Specifically, it answered the acceptability level in terms of taste, texture, flavor, odor, and color also the overall acceptability of enriched aramang baked products. The study used the frequency distribution for evaluators to determine the acceptability of enriched aramang baked products enriched with malunggay. As per sensory evaluation conducted by the researchers, it was proven that aramang baked products enriched with malunggay was acceptable in terms of Odor, Taste, Flavor, Color, and Texture. Based on the results of sensory evaluation of enriched aramang baked products proven that three (3) treatments were all highly acceptable in terms of variable Odor, Taste, Flavor, Color and Textures conducted by the researchers.
Download the Latest OSHA 10 Answers PDF : oyetrade.comNarendra Jayas
Latest OSHA 10 Test Question and Answers PDF for Construction and General Industry Exam.
Download the full set of 390 MCQ type question and answers - https://www.oyetrade.com/OSHA-10-Answers-2021.php
To Help OSHA 10 trainees to pass their pre-test and post-test we have prepared set of 390 question and answers called OSHA 10 Answers in downloadable PDF format. The OSHA 10 Answers question bank is prepared by our in-house highly experienced safety professionals and trainers. The OSHA 10 Answers document consists of 390 MCQ type question and answers updated for year 2024 exams.
Monitor indicators of genetic diversity from space using Earth Observation dataSpatial Genetics
Genetic diversity within and among populations is essential for species persistence. While targets and indicators for genetic diversity are captured in the Kunming-Montreal Global Biodiversity Framework, assessing genetic diversity across many species at national and regional scales remains challenging. Parties to the Convention on Biological Diversity (CBD) need accessible tools for reliable and efficient monitoring at relevant scales. Here, we describe how Earth Observation satellites (EO) make essential contributions to enable, accelerate, and improve genetic diversity monitoring and preservation. Specifically, we introduce a workflow integrating EO into existing genetic diversity monitoring strategies and present a set of examples where EO data is or can be integrated to improve assessment, monitoring, and conservation. We describe how available EO data can be integrated in innovative ways to support calculation of the genetic diversity indicators of the GBF monitoring framework and to inform management and monitoring decisions, especially in areas with limited research infrastructure or access. We also describe novel, integrative approaches to improve the indicators that can be implemented with the coming generation of EO data, and new capabilities that will provide unprecedented detail to characterize the changes to Earth’s surface and their implications for biodiversity, on a global scale.
Emerging Earth Observation methods for monitoring sustainable food productionCIFOR-ICRAF
Presented by Daniela Requena Suarez, Helmholtz GeoResearch Center Potsdam (GFZ) at "Side event 60th sessions of the UNFCCC Subsidiary Bodies - Sustainable Bites: Innovating Low Emission Food Systems One Country at a Time" on 13 June 2024
Trichogramma spp. is an efficient egg parasitoids that potentially assist to manage the insect-pests from the field condition by parasiting the host eggs. To mass culture this egg parasitoids effectively, we need to culture another stored grain pest- Rice Meal Moth (Corcyra Cephalonica). After rearing this pest, the eggs of Corcyra will carry the potential Trichogramma spp., which is an Hymenopteran Wasp. The detailed Methodologies of rearing both Corcyra Cephalonica and Trichogramma spp. have described on this ppt.
1. A Fairfax County, VA, publication
Department of Public Works and Environmental Services
Working for You!
Brookfield Park Wet Pond Construction
CN13125072
SD-000031-078
Lee District
December 1, 2014
2. Brookfield Park Wet Pond Construction
Utilities Design & Construction Division- Transportation and Stormwater Construction Branch
3. Project Details
Brookfield Park Wet Pond Construction
Utilities Design & Construction Division- Transportation and Stormwater Construction Branch
Description:
The Brookfield Park Wet Pond Construction project was substantially completed on November 14, 2014. The project
consisted of rebuilding a failing wet pond to meet present day standards for stormwater detention and water quality.
Project Overview:
• Reconstruction of existing leaky & eroded dam (35 ft. high)
• Installation of a new semi circular riser structure with an observation deck
• Installation of a wetland forebay system and sediment removal
• Installation of grasscrete access road and restoration of parking lot with permeable pavement
• Restoration of two stormwater outfalls
• Incorporation of native landscaping to include vegetated floating wetlands
• Reduction of 147.1 lbs. of total nitrogen per year, 32.2 lbs. of total phosphorus per year, and 3.2 tons of sediment per
year leading to the Accotink Creek.
Project Team:
• Stormwater Planning Division – Sajan Pokharel, Suzanne Foster, Chad Crawford
• UDCD Transportation and Stormwater Construction Branch – Yudhie Brownson, Paul Thaler, Mannan Qureshi, Tammy Michelli
• UDCD Land Survey Branch – Greg Harper, Pat Gallahan, Matthias Strecker, Mike Perry, Gregg Housley
• Fairfax County Park Authority – Isabel Villarroel, Ed Richardson
• Maintenance and Stormwater Management Division – Don Lacquement, Carolyn Weber
• Urban Forestry Management Division – Hugh Whitehead, Samantha Wangsgard
• Corinthian Contractors, Inc. – William Boyland, Gary Keller, Declan Munslow, Warren Teague
• Dewberry – Geoffrey Cowan, Nicholas Shimmer, Jim Davidson, Mark Unterkofler
• ECS Limited – Scott Nelson, Prem Dhungana
4. Brookfield Park Wet Pond Construction
Utilities Design & Construction Division- Transportation and Stormwater Construction Branch
Dickenson St. & Floyd Ave. (Springfield, VA) – Tax Map No. 80-3
Project Site
5. Brookfield Park Wet Pond Construction
Utilities Design & Construction Division- Transportation and Stormwater Construction Branch
Existing Condition – Pond
6. Brookfield Park Dam Construction
Utilities Design & Construction Division- Transportation and Stormwater Construction Branch
Existing Condition – Dam Embankment
7. Brookfield Park Wet Pond Construction
Utilities Design & Construction Division- Transportation and Stormwater Construction Branch
Existing Condition – Dam Embankment
8. Brookfield Park Wet Pond Construction
Utilities Design & Construction Division- Transportation and Stormwater Construction Branch
Existing Condition – Dam Embankment
9. Brookfield Park Wet Pond Construction
Utilities Design & Construction Division- Transportation and Stormwater Construction Branch
Construction – Dam Embankment & Riser Structure
10. Brookfield Park Wet Pond Construction
Utilities Design & Construction Division- Transportation and Stormwater Construction Branch
Construction – Dam Embankment & Riser Structure
11. Brookfield Park Wet Pond Construction
Utilities Design & Construction Division- Transportation and Stormwater Construction Branch
Post Construction
12. Brookfield Park Wet Pond Construction
Utilities Design & Construction Division- Transportation and Stormwater Construction Branch
Post Construction
13. Brookfield Park Wet Pond Construction
Utilities Design & Construction Division- Transportation and Stormwater Construction Branch
Post Construction
14. Brookfield Park Wet Pond Construction
Utilities Design & Construction Division- Transportation and Stormwater Construction Branch
Post Condition – Forebay pond & Grasscrete access road
15. Brookfield Park Wet Pond Construction
Utilities Design & Construction Division- Transportation and Stormwater Construction Branch
Post Condition – Parking lot with permeable pavement
16. Brookfield Park Wet Pond Construction
Utilities Design & Construction Division- Transportation and Stormwater Construction Branch
Post Condition– Coastal Plain Outfall System
17. Before After
Brookfield Park Wet Pond Construction
Utilities Design & Construction Division- Transportation and Stormwater Construction Branch
18. Additional Information
For additional Information, please call
www.fairfaxcounty.gov/dpwes
Brookfield Park Wet Pond Construction
Utilities Design & Construction Division- Transportation and Stormwater Construction Branch
Irene Haske, Public Information Officer
703-324-5821, TTY 711
SWPDmail@fairfaxcounty.gov