SlideShare a Scribd company logo
CONSTRUCTION OF
WAFFLE SLABS
What is Waffle Slab?
• A waffle slab or two-way joist slab is a concrete slab made
of reinforced concrete with concrete ribs running in two directions
on its underside.
• The name waffle comes from the grid pattern created by the
reinforcing ribs.
• Waffle slabs are preferred for spans greater than 40 feet (12 m), as
they are much stronger than flat slabs, flat slabs with drop panels,
two-way slabs, one-way slabs, and one-way joist slabs.
• This type of reinforcement is common on concrete, wood and metal
construction. A waffle slab gives a substance significantly more
structural stability without using a lot of additional material.
• This makes a waffle slab perfect for large flat areas like foundations
or floors.
Engineering and Technology Update
Appearance :
• The top of a waffle slab is generally smooth, like a traditional
building surface, but the underside has a shape reminiscent of a
waffle.
• Straight lines run the entire width and length of the slab, generally
raised several inches from the surface.
• These ridges form the namesake square pockets of the entire length
and width of the slab.
Engineering and Technology Update
Where this system is used ?
• Waffle slab can be used as both ceiling and floor slab. They are used in
the areas where less number of columns are provided, i.e. it is basically
used in the areas which has huge spans.
• Waffle slab is not used in typical construction projects. They are used
for specialized projects that involve clean rooms, spaces requiring
seclusion from low frequency vibration or those needing low floor
deflections.
• The concrete waffle slab is often used for industrial and commercial
buildings while wood and metal waffle slabs are used in many other
construction sites.
• This form of construction is used in airports, parking garages,
commercial and industrial buildings, bridges, residences and other
structures requiring extra stability.
• The main purpose of employing this technology is for its strong
foundation characteristics of crack and sagging resistance. Waffle slab
also holds a greater amount of load compared with conventional
concrete slabs.
Engineering and Technology Update
Engineering and Technology Update
Waffle slab characteristics are defined by the following parameters:
• Total slab edge (H)
• Height of the lightening formwork or lightening blocks (h)
• Spacing between rib axes (e)
• Basic thickness of the ribs (b), though in waffle slabs with system
formwork they have a truncated pyramid-shaped core of variable
thickness.
• Thickness of the compression layer (c)
Engineering and Technology Update
Design & Production of Waffle Slab
Production :
• Waffle slabs can be casted by placing he pods on he formwork itself or
they can be available pre-casted.
• Concrete waffle slabs can be purchased and shipped to the
construction site as prefabricated or precast sections, or they can be
poured on-site.
• If prefabricated products are not in the budget, consider purchasing
casts for the concrete waffle slabs.
• The pre-casted pods are then placed directly on the site and then
provided with reinforcement and filled with concrete.
Engineering and Technology Update
Design :
• There are three basic designs for concrete slabs that improve the
strength-to weight ratio. For each design, the top surface is flat while
the underside is modulated with either a corrugated, ribbed or waffle
design.
• Corrugated slabs are created when concrete is poured into a wavy
metal
form. This shape prevents the slab from sagging.
• Ribbed slabs add strength in one direction, while the concrete waffle
slab
design adds strength in perpendicular directions. Concrete slabs
can be
reinforced with rebar for additional strength.
Engineering and Technology Update
Services Provided in Waffle Slab
Due to the holes in the waffle system following services can
be provided:
• Air-conditioning
• Plumbing
• Lighting
• Insulation Materials
• Wiring, etc.
Engineering and Technology Update
Construction Process:
• A waffle slab can be made in different ways but generic forms are
needed to give the waffle shape to the slab. The formwork is made
up of many elements: waffle pods, horizontal supports, vertical
supports, cube junctions, hole plates, clits and steel Bars.
• First the supports are built, then the pods are arranged in place, and
finally the concrete is poured.
• This process may occur in three different approaches, however the
basic method is the same in each:
In situ: Formwork construction and pouring of concrete occur on
site, then the slab is assembled (if required).
Precast: The slabs are made somewhere else and then brought
to the site and assembled.
Pre-fabricated:The reinforcements are integrated into the slab
while being manufactured, without needing to reinforce the
assembly on site. This is the most expensive option.
Engineering and Technology Update
Construction Technique
1. Arranging the 2. Fixing the 3. Fixing the 4.Providing
Formwork connectors framework horizontal connector
5. Placing the pods 6. Fixing pods to the 7. Removing framework
connector
Engineering and Technology Update
Continued..
8. Removing 9. Removing Pods 10. Providing
Connectors Stacking
Engineering and Technology Update
Advantages:
• Waffle slabs are able to carry heavier loads and span
longer distances than flat slabs as these systems are
light in weight.
• Suitable for spans of 7m – 16m ; longer spans may be
possible with post tensioning.
• It is also economical as the amount of concrete and steel
is reduced as compared to flush slabs. Saving 15%
concrete and 10% steel as compared to traditional T
beams.
• These systems are light in weight and hence
considerable saving is ensured in the framework as light
framework is required.
• Coffered underside is usually left exposed for visual
appearance.
Engineering and Technology Update
Disadvantages:
• Construction requires strict supervision and skilled
labour.
• The casting forms or moulds required for precast units
are very costly and hence only economical when large
scale production of similar units are desired.
• Headroom is reduced , hence increased storey height.
• Due to waffle ceiling , it creates problem in lighting
facilities and hanging pipes or ducts.
Engineering and Technology Update
Iconic Landmarks
Metropol Parasol,Italy
It is the world’s largest wooden structure which is
made up of waffle system.
Engineering and Technology Update
Lodytel Communication Development Centre, Spain
It was the first building to use the Hole deck pods for
waffle system.
Engineering and Technology Update
Chattrapati Shivaji Terminal,India
It is recognized for its innovative column design which
also consists waffle design.
Engineering and Technology Update
Case Study – Chattrapati Shivaji International
Airport, Mumbai
• Long span roof of 70,000 square meters
• Roof supported by 30 columns, column distance of 64 meters
in the N-S direction and 34 meters in E-W direction.
• By increasing the depth of trusses near the columns and
running trusses, large spacing of cantilevers of 40 meters along
the perimeter is achieved.
• Total truss depth = 4 meters only
• The columns are also designed to serve as hoist mechanism,
entire roof was constructed without any tower cranes.
• The structure prioritizes modular construction for economy and
also accelerates construction schedule.
Engineering and Technology Update
Thank You!
Engineering and Technology Update

More Related Content

What's hot

Portal frame construction by Rhythm Murgai
Portal frame construction by Rhythm MurgaiPortal frame construction by Rhythm Murgai
Portal frame construction by Rhythm Murgai
Rhythm Murgai
 
Waffle slab
Waffle slabWaffle slab
Waffle slab
Akshay Raut
 
Folded plates
Folded platesFolded plates
Folded plates
Rohan Narvekar
 
Space frames-modular construction technology
Space frames-modular construction technologySpace frames-modular construction technology
Space frames-modular construction technology
Anjith Augustine
 
Structural systems in high rise buildings
Structural systems in high rise buildingsStructural systems in high rise buildings
Structural systems in high rise buildings
Karthik Suresh
 
Curtain walls - Advanced structural systems
Curtain walls - Advanced structural systemsCurtain walls - Advanced structural systems
Curtain walls - Advanced structural systems
Pratibha Mohan
 
Geodesic Dome - History and Construction
Geodesic Dome - History and ConstructionGeodesic Dome - History and Construction
Geodesic Dome - History and Construction
Azra Maliha
 
Shell structure
Shell structureShell structure
Shell structure
Susmita Paul
 
High rise building construction
High rise building constructionHigh rise building construction
High rise building construction
Construction Tech. and Mgmt., VNIT Nagpur
 
Large span structures
Large span structuresLarge span structures
Large span structures
aduiti
 
Precast-concrete Details
Precast-concrete DetailsPrecast-concrete Details
Precast-concrete Details
Saurav Chaudhary
 
Form active structure system (1)
 Form active structure system (1) Form active structure system (1)
Form active structure system (1)
Prince Pathania
 
NATURAL VENTILATION LITERATURE AND CASE STUDY IN INDIA (DISSERTATION OF THESI...
NATURAL VENTILATION LITERATURE AND CASE STUDY IN INDIA (DISSERTATION OF THESI...NATURAL VENTILATION LITERATURE AND CASE STUDY IN INDIA (DISSERTATION OF THESI...
NATURAL VENTILATION LITERATURE AND CASE STUDY IN INDIA (DISSERTATION OF THESI...
KIRAN DAS VAISHNAV
 
High rise structure & core
High rise  structure & coreHigh rise  structure & core
High rise structure & core
Meer Musabber ali (joyous)
 
Structural systems notes
Structural systems notesStructural systems notes
Structural systems notes
Aaqib Iqbal
 
01-Working details-Partition-Gypsum Board-KNAUF-by Prof Dr. Ehab Ezzat 2018
01-Working details-Partition-Gypsum Board-KNAUF-by Prof Dr. Ehab Ezzat 201801-Working details-Partition-Gypsum Board-KNAUF-by Prof Dr. Ehab Ezzat 2018
01-Working details-Partition-Gypsum Board-KNAUF-by Prof Dr. Ehab Ezzat 2018
Faculty of fine arts -Cairo. Egypt.
 
Tensile structures
Tensile structuresTensile structures
Tensile structures
Kiruthika Selvi K J
 

What's hot (20)

Portal frame construction by Rhythm Murgai
Portal frame construction by Rhythm MurgaiPortal frame construction by Rhythm Murgai
Portal frame construction by Rhythm Murgai
 
Waffle slab
Waffle slabWaffle slab
Waffle slab
 
Folded plates
Folded platesFolded plates
Folded plates
 
Space frames-modular construction technology
Space frames-modular construction technologySpace frames-modular construction technology
Space frames-modular construction technology
 
Structural systems in high rise buildings
Structural systems in high rise buildingsStructural systems in high rise buildings
Structural systems in high rise buildings
 
Curtain walls - Advanced structural systems
Curtain walls - Advanced structural systemsCurtain walls - Advanced structural systems
Curtain walls - Advanced structural systems
 
Steel trusses
Steel trussesSteel trusses
Steel trusses
 
Geodesic Dome - History and Construction
Geodesic Dome - History and ConstructionGeodesic Dome - History and Construction
Geodesic Dome - History and Construction
 
Shell structure
Shell structureShell structure
Shell structure
 
Filler slab
Filler slabFiller slab
Filler slab
 
High rise building construction
High rise building constructionHigh rise building construction
High rise building construction
 
Large span structures
Large span structuresLarge span structures
Large span structures
 
Precast-concrete Details
Precast-concrete DetailsPrecast-concrete Details
Precast-concrete Details
 
Form active structure system (1)
 Form active structure system (1) Form active structure system (1)
Form active structure system (1)
 
Partition walls
Partition wallsPartition walls
Partition walls
 
NATURAL VENTILATION LITERATURE AND CASE STUDY IN INDIA (DISSERTATION OF THESI...
NATURAL VENTILATION LITERATURE AND CASE STUDY IN INDIA (DISSERTATION OF THESI...NATURAL VENTILATION LITERATURE AND CASE STUDY IN INDIA (DISSERTATION OF THESI...
NATURAL VENTILATION LITERATURE AND CASE STUDY IN INDIA (DISSERTATION OF THESI...
 
High rise structure & core
High rise  structure & coreHigh rise  structure & core
High rise structure & core
 
Structural systems notes
Structural systems notesStructural systems notes
Structural systems notes
 
01-Working details-Partition-Gypsum Board-KNAUF-by Prof Dr. Ehab Ezzat 2018
01-Working details-Partition-Gypsum Board-KNAUF-by Prof Dr. Ehab Ezzat 201801-Working details-Partition-Gypsum Board-KNAUF-by Prof Dr. Ehab Ezzat 2018
01-Working details-Partition-Gypsum Board-KNAUF-by Prof Dr. Ehab Ezzat 2018
 
Tensile structures
Tensile structuresTensile structures
Tensile structures
 

Similar to WAFFLE SLAB.pptx

Grid waffle slab
Grid waffle slabGrid waffle slab
Grid waffle slab
Vikas Mehta
 
Precast concrete
Precast concretePrecast concrete
Precast concrete
SnehaKothari13
 
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVEMODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
Dr K M SONI
 
Chapters-3,4,5.pptx
Chapters-3,4,5.pptxChapters-3,4,5.pptx
Chapters-3,4,5.pptx
ssuserc0bf9b
 
115659118 pre-engineered-buildings
115659118 pre-engineered-buildings115659118 pre-engineered-buildings
115659118 pre-engineered-buildingshlksd
 
Reinforced Concrete Structure and Detailing Module
Reinforced Concrete Structure and Detailing ModuleReinforced Concrete Structure and Detailing Module
Reinforced Concrete Structure and Detailing Module
Bahzad5
 
Portal Frame Construction & Pre Engineered Building System
Portal Frame Construction & Pre Engineered Building SystemPortal Frame Construction & Pre Engineered Building System
Portal Frame Construction & Pre Engineered Building System
Ian Toisa
 
Form-woks-additional.pptx
Form-woks-additional.pptxForm-woks-additional.pptx
Form-woks-additional.pptx
ssuserc0bf9b
 
Floor and slab system design and construction
Floor and slab system design and constructionFloor and slab system design and construction
Floor and slab system design and construction
EyobAlene1
 
Type of high rise building
Type of high rise buildingType of high rise building
Type of high rise building
Zabihullah Nasiri
 
Formwork
FormworkFormwork
Formwork
kajol panchal
 
TALL BUILDINGS
TALL BUILDINGSTALL BUILDINGS
TALL BUILDINGS
Abhijit Pal
 
Oldcastle Precast Spokane - Urban Modular Construction - The Grand Hotel
Oldcastle Precast Spokane - Urban Modular Construction - The Grand HotelOldcastle Precast Spokane - Urban Modular Construction - The Grand Hotel
Oldcastle Precast Spokane - Urban Modular Construction - The Grand HotelBlake Johnson
 
Pre Engineered buildings
Pre Engineered buildingsPre Engineered buildings
Pre Engineered buildings
Yamini K
 
Industrial buildings
Industrial buildingsIndustrial buildings
Industrial buildings
AkshataFarakate
 
115659118 pre-engineered-buildings (1)
115659118 pre-engineered-buildings (1)115659118 pre-engineered-buildings (1)
115659118 pre-engineered-buildings (1)hlksd
 
115659118 pre-engineered-buildings
115659118 pre-engineered-buildings115659118 pre-engineered-buildings
115659118 pre-engineered-buildingshlksd
 
Slipform construction
Slipform constructionSlipform construction
Slipform construction
ErankajKumar
 
Tilt up concrete structures
Tilt up concrete structuresTilt up concrete structures
Tilt up concrete structures
MECandPMV
 

Similar to WAFFLE SLAB.pptx (20)

Grid waffle slab
Grid waffle slabGrid waffle slab
Grid waffle slab
 
Master template for MEC 2014 Workshop
Master template for MEC 2014 WorkshopMaster template for MEC 2014 Workshop
Master template for MEC 2014 Workshop
 
Precast concrete
Precast concretePrecast concrete
Precast concrete
 
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVEMODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
 
Chapters-3,4,5.pptx
Chapters-3,4,5.pptxChapters-3,4,5.pptx
Chapters-3,4,5.pptx
 
115659118 pre-engineered-buildings
115659118 pre-engineered-buildings115659118 pre-engineered-buildings
115659118 pre-engineered-buildings
 
Reinforced Concrete Structure and Detailing Module
Reinforced Concrete Structure and Detailing ModuleReinforced Concrete Structure and Detailing Module
Reinforced Concrete Structure and Detailing Module
 
Portal Frame Construction & Pre Engineered Building System
Portal Frame Construction & Pre Engineered Building SystemPortal Frame Construction & Pre Engineered Building System
Portal Frame Construction & Pre Engineered Building System
 
Form-woks-additional.pptx
Form-woks-additional.pptxForm-woks-additional.pptx
Form-woks-additional.pptx
 
Floor and slab system design and construction
Floor and slab system design and constructionFloor and slab system design and construction
Floor and slab system design and construction
 
Type of high rise building
Type of high rise buildingType of high rise building
Type of high rise building
 
Formwork
FormworkFormwork
Formwork
 
TALL BUILDINGS
TALL BUILDINGSTALL BUILDINGS
TALL BUILDINGS
 
Oldcastle Precast Spokane - Urban Modular Construction - The Grand Hotel
Oldcastle Precast Spokane - Urban Modular Construction - The Grand HotelOldcastle Precast Spokane - Urban Modular Construction - The Grand Hotel
Oldcastle Precast Spokane - Urban Modular Construction - The Grand Hotel
 
Pre Engineered buildings
Pre Engineered buildingsPre Engineered buildings
Pre Engineered buildings
 
Industrial buildings
Industrial buildingsIndustrial buildings
Industrial buildings
 
115659118 pre-engineered-buildings (1)
115659118 pre-engineered-buildings (1)115659118 pre-engineered-buildings (1)
115659118 pre-engineered-buildings (1)
 
115659118 pre-engineered-buildings
115659118 pre-engineered-buildings115659118 pre-engineered-buildings
115659118 pre-engineered-buildings
 
Slipform construction
Slipform constructionSlipform construction
Slipform construction
 
Tilt up concrete structures
Tilt up concrete structuresTilt up concrete structures
Tilt up concrete structures
 

More from Amol Pawar

Grout.pptx
Grout.pptxGrout.pptx
Grout.pptx
Amol Pawar
 
Shear walls
Shear wallsShear walls
Shear walls
Amol Pawar
 
Session 2 water proofing
Session 2 water proofingSession 2 water proofing
Session 2 water proofingAmol Pawar
 
Session 3 low cost housing
Session 3 low cost housingSession 3 low cost housing
Session 3 low cost housing
Amol Pawar
 
LOW COST HOUSING
LOW COST HOUSING LOW COST HOUSING
LOW COST HOUSING
Amol Pawar
 
Corrosion session 11 july 14
Corrosion session 11 july 14Corrosion session 11 july 14
Corrosion session 11 july 14Amol Pawar
 
Safety in Excavations
Safety in Excavations Safety in Excavations
Safety in Excavations
Amol Pawar
 
Pavements PPT
 Pavements PPT  Pavements PPT
Pavements PPT
Amol Pawar
 

More from Amol Pawar (9)

Grout.pptx
Grout.pptxGrout.pptx
Grout.pptx
 
Shear walls
Shear wallsShear walls
Shear walls
 
Geopolymers
GeopolymersGeopolymers
Geopolymers
 
Session 2 water proofing
Session 2 water proofingSession 2 water proofing
Session 2 water proofing
 
Session 3 low cost housing
Session 3 low cost housingSession 3 low cost housing
Session 3 low cost housing
 
LOW COST HOUSING
LOW COST HOUSING LOW COST HOUSING
LOW COST HOUSING
 
Corrosion session 11 july 14
Corrosion session 11 july 14Corrosion session 11 july 14
Corrosion session 11 july 14
 
Safety in Excavations
Safety in Excavations Safety in Excavations
Safety in Excavations
 
Pavements PPT
 Pavements PPT  Pavements PPT
Pavements PPT
 

Recently uploaded

Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
Kamal Acharya
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
MuhammadTufail242431
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
Vaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdfVaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdf
Kamal Acharya
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
Kamal Acharya
 
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdfCOLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
Kamal Acharya
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
ssuser9bd3ba
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
abh.arya
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 

Recently uploaded (20)

Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
Vaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdfVaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdf
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
 
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdfCOLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 

WAFFLE SLAB.pptx

  • 2. What is Waffle Slab? • A waffle slab or two-way joist slab is a concrete slab made of reinforced concrete with concrete ribs running in two directions on its underside. • The name waffle comes from the grid pattern created by the reinforcing ribs. • Waffle slabs are preferred for spans greater than 40 feet (12 m), as they are much stronger than flat slabs, flat slabs with drop panels, two-way slabs, one-way slabs, and one-way joist slabs. • This type of reinforcement is common on concrete, wood and metal construction. A waffle slab gives a substance significantly more structural stability without using a lot of additional material. • This makes a waffle slab perfect for large flat areas like foundations or floors. Engineering and Technology Update
  • 3. Appearance : • The top of a waffle slab is generally smooth, like a traditional building surface, but the underside has a shape reminiscent of a waffle. • Straight lines run the entire width and length of the slab, generally raised several inches from the surface. • These ridges form the namesake square pockets of the entire length and width of the slab. Engineering and Technology Update
  • 4. Where this system is used ? • Waffle slab can be used as both ceiling and floor slab. They are used in the areas where less number of columns are provided, i.e. it is basically used in the areas which has huge spans. • Waffle slab is not used in typical construction projects. They are used for specialized projects that involve clean rooms, spaces requiring seclusion from low frequency vibration or those needing low floor deflections. • The concrete waffle slab is often used for industrial and commercial buildings while wood and metal waffle slabs are used in many other construction sites. • This form of construction is used in airports, parking garages, commercial and industrial buildings, bridges, residences and other structures requiring extra stability. • The main purpose of employing this technology is for its strong foundation characteristics of crack and sagging resistance. Waffle slab also holds a greater amount of load compared with conventional concrete slabs. Engineering and Technology Update
  • 6. Waffle slab characteristics are defined by the following parameters: • Total slab edge (H) • Height of the lightening formwork or lightening blocks (h) • Spacing between rib axes (e) • Basic thickness of the ribs (b), though in waffle slabs with system formwork they have a truncated pyramid-shaped core of variable thickness. • Thickness of the compression layer (c) Engineering and Technology Update
  • 7. Design & Production of Waffle Slab Production : • Waffle slabs can be casted by placing he pods on he formwork itself or they can be available pre-casted. • Concrete waffle slabs can be purchased and shipped to the construction site as prefabricated or precast sections, or they can be poured on-site. • If prefabricated products are not in the budget, consider purchasing casts for the concrete waffle slabs. • The pre-casted pods are then placed directly on the site and then provided with reinforcement and filled with concrete. Engineering and Technology Update
  • 8. Design : • There are three basic designs for concrete slabs that improve the strength-to weight ratio. For each design, the top surface is flat while the underside is modulated with either a corrugated, ribbed or waffle design. • Corrugated slabs are created when concrete is poured into a wavy metal form. This shape prevents the slab from sagging. • Ribbed slabs add strength in one direction, while the concrete waffle slab design adds strength in perpendicular directions. Concrete slabs can be reinforced with rebar for additional strength. Engineering and Technology Update
  • 9. Services Provided in Waffle Slab Due to the holes in the waffle system following services can be provided: • Air-conditioning • Plumbing • Lighting • Insulation Materials • Wiring, etc. Engineering and Technology Update
  • 10. Construction Process: • A waffle slab can be made in different ways but generic forms are needed to give the waffle shape to the slab. The formwork is made up of many elements: waffle pods, horizontal supports, vertical supports, cube junctions, hole plates, clits and steel Bars. • First the supports are built, then the pods are arranged in place, and finally the concrete is poured. • This process may occur in three different approaches, however the basic method is the same in each: In situ: Formwork construction and pouring of concrete occur on site, then the slab is assembled (if required). Precast: The slabs are made somewhere else and then brought to the site and assembled. Pre-fabricated:The reinforcements are integrated into the slab while being manufactured, without needing to reinforce the assembly on site. This is the most expensive option. Engineering and Technology Update
  • 11. Construction Technique 1. Arranging the 2. Fixing the 3. Fixing the 4.Providing Formwork connectors framework horizontal connector 5. Placing the pods 6. Fixing pods to the 7. Removing framework connector Engineering and Technology Update
  • 12. Continued.. 8. Removing 9. Removing Pods 10. Providing Connectors Stacking Engineering and Technology Update
  • 13. Advantages: • Waffle slabs are able to carry heavier loads and span longer distances than flat slabs as these systems are light in weight. • Suitable for spans of 7m – 16m ; longer spans may be possible with post tensioning. • It is also economical as the amount of concrete and steel is reduced as compared to flush slabs. Saving 15% concrete and 10% steel as compared to traditional T beams. • These systems are light in weight and hence considerable saving is ensured in the framework as light framework is required. • Coffered underside is usually left exposed for visual appearance. Engineering and Technology Update
  • 14. Disadvantages: • Construction requires strict supervision and skilled labour. • The casting forms or moulds required for precast units are very costly and hence only economical when large scale production of similar units are desired. • Headroom is reduced , hence increased storey height. • Due to waffle ceiling , it creates problem in lighting facilities and hanging pipes or ducts. Engineering and Technology Update
  • 15. Iconic Landmarks Metropol Parasol,Italy It is the world’s largest wooden structure which is made up of waffle system. Engineering and Technology Update
  • 16. Lodytel Communication Development Centre, Spain It was the first building to use the Hole deck pods for waffle system. Engineering and Technology Update
  • 17. Chattrapati Shivaji Terminal,India It is recognized for its innovative column design which also consists waffle design. Engineering and Technology Update
  • 18. Case Study – Chattrapati Shivaji International Airport, Mumbai • Long span roof of 70,000 square meters • Roof supported by 30 columns, column distance of 64 meters in the N-S direction and 34 meters in E-W direction. • By increasing the depth of trusses near the columns and running trusses, large spacing of cantilevers of 40 meters along the perimeter is achieved. • Total truss depth = 4 meters only • The columns are also designed to serve as hoist mechanism, entire roof was constructed without any tower cranes. • The structure prioritizes modular construction for economy and also accelerates construction schedule. Engineering and Technology Update
  • 19. Thank You! Engineering and Technology Update