SlideShare a Scribd company logo
1 of 17
Spurthi G
Sandhya S
Aadarsh
 THE VIERENDEEL FRAME, or truss as it is more popularly but inappropriately
called, is a series of rectangular frames which achieves stability by the rigid
connection of the vertical web members to the top and bottom chord.
 Contrary to the typical pin-connected truss in which all members are axially
loaded and shear is transferred axially through diagonals, the Vierendeel
transfers shear from the chords by bending moments at the joints and
finally by bending moments in the vertical webs.
 As a result, all members are combined stress members in which axial, shear,
and bending stresses exist.
INTRODUCTION
• Such trusses do not have the usual triangular voids seen in a pin–joint truss bridge, rather
employing rectangular openings and rigid connections in the elements, which (unlike a
conventional truss) must also resist substantial bending forces.
• Owing to a lesser economy of materials and the difficulty of design before the advent of
computers, this truss is rarely used in bridges outside Belgium. The form is more commonly
employed in building structures where large shear walls or diagonal elements would interfere
with the building's aesthetics or functionality.
• The first such bridge was built in steel at Avelgem, Belgium in 1902, following development of
the truss form and a method to calculate its strength in 1896 by Arthur Vierendeel. There are
many more examples in Belgium, also constructed in concrete, mostly designed by Vierendeel's
many students in a long career as professor in civil engineering.
• Despite the structural disadvantages surrounding
the Vierendeel, it was in the area of civil
engineering rather than architecture that it was
first utilized-specifically for short-span bridges.
• The Vierendeel's origin dates to I896. The Belgian
engineer Arthur Vierendeel, then professor at the
University of Louvain, unveiled the concept in his
book Longerons en Treillis et Longerons a Arcades.
At that time steel trusses required extremely large
gusset plates to accommodate rivet groups;
members were generally oversized and rarely did
the center lines of all joined members intersect.
• Therefore, the pin-jointed theory which ignored
moments, due to these eccentricities, led to errors
on the critical side, approaching fifteen percent
when office calculations were compared to field
measurements.
HISTORY
• These discrepancies between simplified analytical methods and
reality are what led Professor Vierendeel to propose the
rectangular rigid-jointed system where these eccentricities could
be eliminated and accuracy between analysis and reality kept in
close accord.
• A smaller factor of safety could be used, due to this improved
accuracy, so that in the early I900s Vierendeel bridges did weigh
less than alternative truss solutions.
• The first Vierendeel bridge was experimental. It spanned 96 feet
and was tested in 1897 at Tervueren with an assimilated railway
loading pattern.
• The riveted framework responded by carrying 2.73 times the
design live load and prompted the Belgian Bridge and Highway
Department to state in their official report that, "In the present
state of the question, the portal frame truss is, generally
speaking, a system nearly equivalent to the triangulated truss.“
• The first actual usage of a Vierendeel bridge occurred in I901
with a 128-foot span of riveted construction at Avelghem,
Belgium, followed by the I36-foot span at Ousselghem in I910,
also riveted.
• Decline Mishaps (cracks and dislocations), primarily due to insufficient knowledge of the ramifications
of welding procedures, poor workmanship, and low steel quality, resulted in increasing skepticism
about the Vierendeel system.
• The collapse of a 245-foot-span bridge at Hasselt in 1938 was the most total and dramatic.
• A Belgian committee assigned to investigate the collapse, together with outside consultants,
concluded that the welded Vierendeel system, although considered to be adequately designed, was
sensitive to external influences, such as cooling, heating, vibration, or impact.
• By reason of its inherent joint rigidity, the system also attracted internal residual stresses and
demanded an extensive knowledge of the art of welding. Similar problems with welded plate girder
bridges were occurring in other countries of Europe.
• It was apparent that welding technology needed to catch up with welding demand
DECLINATION
EXAMPLES
• The Albert Canal was constructed from 1930 through 1939. The German construction
company Hochtief AG worked on the canal between 1930 and 1934, but it was completed by
Belgian companies. The Albert Canal was used for the first time in 1940 but, because of World
War II and the German occupation, intensive use only began later, in 1946.
• During World War II, the Albert Canal functioned as a defense line. The crossing of the canal
by the German forces and the destruction of Fort Eben-Emael on 11 May 1940 was a
milestone in the German invasion of Belgium.
• During the Liberation of Belgium by the Allies in September 1944, the Second Canadian
Division was the first Allied unit to cross the Albert Canal.
• The British Army also crossed the Albert Canal on its way north across Belgium and into The
Netherlands and the U.S. Army entered Belgium further to the east on its way to liberate the
rest of Belgium, and Luxembourg, and then proceed east to invade Nazi Germany. Hence,
Belgium was liberated from the south by three different armies, two of which needed to cross
the Albert Canal.
ALBERT CANAL
• In 2002, the canal carried a record 43 million tons of goods of various kinds,
amounting to more than half the Belgian waterway total.
• The canal is also a popular leisure and cycling destination, with well paved
service roads on both sides traversing picturesque farm land, particularly
around Smeermass, Lanaken and Maasmechelen.
Vierendeel bridge
at Grammene, Belgium
Geneva St. bridge
in Glendale
• The city of Glendale, California has three
Vierendeel truss bridges: the Geneva Street,
Kenilworth Avenue, and Glenoaks Boulevard
bridges, all two-lane bridges spanning 95 feet.
They were built in 1937 as part of the Verdugo
Flood Control Project, the first project of
the United States Army Corps of Engineers after
passage of the Flood Control Act of 1936.
• The double-deck cable-stayed Kap Shui Mun
Bridge in Hong Kong uses a Vierendeel truss.
Opened in 1997, the lower deck carries both rail
and traffic, with the lack of diagonal members in
the cross section allowing vehicles to drive
through the openings provided by the
Vierendeel design.
Gutsav-Heinemann Brucke
BIBLIOGRAPHY
REFERNCES
• The Vierendeel Author(s): David J. Wickersheimer Source: Journal of the Society
of Architectural Historians, Vol. 35, No. 1 (Mar., 1976), pp. 54- 60 Published by:
University of California Press on behalf of the Society of Architectural Historians
Stable URL: http://www.jstor.org/stable/988971 . Accessed: 10/07/2013 10:19
• Book: Building structures
Author: Ching
• www.arch.mcgill.ca
• www.Wikipedia.com
THANK YOU

More Related Content

What's hot

Vector active systems
Vector active systemsVector active systems
Vector active systemsDanishPathan7
 
Long span structures in Concrete and Steel
Long span structures in Concrete and SteelLong span structures in Concrete and Steel
Long span structures in Concrete and SteelRithika Ravishankar
 
Long span structure
Long span structureLong span structure
Long span structureSakshiGadakh
 
Folded Plate structures
Folded Plate structures Folded Plate structures
Folded Plate structures rohan joshi
 
Long span structures
Long span structures  Long span structures
Long span structures Aroh Thombre
 
High-rise structural systems
High-rise structural systemsHigh-rise structural systems
High-rise structural systemsAkshay Revekar
 
Indian examples of long span structures
Indian examples of long span structuresIndian examples of long span structures
Indian examples of long span structuresAnupama Krishnan
 
Cable systems - form active structure system
Cable systems - form active structure systemCable systems - form active structure system
Cable systems - form active structure systemArchistudent Portal
 
Case Study: High Rise Buildings
Case Study: High Rise BuildingsCase Study: High Rise Buildings
Case Study: High Rise BuildingsPrasad Thanthratey
 
steel roof truss
steel roof trusssteel roof truss
steel roof trussRohit Dutta
 
Folded plates and space truss structures
Folded plates and space truss  structuresFolded plates and space truss  structures
Folded plates and space truss structuresRajesh Kolli
 
Spanning Space, Horizontal-span Building Structures, Wolfgang Schueller
Spanning Space, Horizontal-span Building Structures, Wolfgang SchuellerSpanning Space, Horizontal-span Building Structures, Wolfgang Schueller
Spanning Space, Horizontal-span Building Structures, Wolfgang SchuellerWolfgang Schueller
 
Folded plate structure
Folded plate structureFolded plate structure
Folded plate structureVikas Mehta
 
High-Rise Iconic Buildings
High-Rise Iconic BuildingsHigh-Rise Iconic Buildings
High-Rise Iconic BuildingsDania Abdel-aziz
 
Pneumatic structures
Pneumatic structuresPneumatic structures
Pneumatic structuresKrishnagnr
 

What's hot (20)

Space frames
Space framesSpace frames
Space frames
 
Vector active systems
Vector active systemsVector active systems
Vector active systems
 
Space frame
Space frameSpace frame
Space frame
 
Space frame
Space frameSpace frame
Space frame
 
Long span structures in Concrete and Steel
Long span structures in Concrete and SteelLong span structures in Concrete and Steel
Long span structures in Concrete and Steel
 
Long span structure
Long span structureLong span structure
Long span structure
 
Folded Plate structures
Folded Plate structures Folded Plate structures
Folded Plate structures
 
Long span structures
Long span structures  Long span structures
Long span structures
 
High-rise structural systems
High-rise structural systemsHigh-rise structural systems
High-rise structural systems
 
Indian examples of long span structures
Indian examples of long span structuresIndian examples of long span structures
Indian examples of long span structures
 
Cable systems - form active structure system
Cable systems - form active structure systemCable systems - form active structure system
Cable systems - form active structure system
 
Case Study: High Rise Buildings
Case Study: High Rise BuildingsCase Study: High Rise Buildings
Case Study: High Rise Buildings
 
steel roof truss
steel roof trusssteel roof truss
steel roof truss
 
Folded plates and space truss structures
Folded plates and space truss  structuresFolded plates and space truss  structures
Folded plates and space truss structures
 
Spanning Space, Horizontal-span Building Structures, Wolfgang Schueller
Spanning Space, Horizontal-span Building Structures, Wolfgang SchuellerSpanning Space, Horizontal-span Building Structures, Wolfgang Schueller
Spanning Space, Horizontal-span Building Structures, Wolfgang Schueller
 
Space frame
Space frameSpace frame
Space frame
 
Folded plate structure
Folded plate structureFolded plate structure
Folded plate structure
 
High-Rise Iconic Buildings
High-Rise Iconic BuildingsHigh-Rise Iconic Buildings
High-Rise Iconic Buildings
 
FOLDED PLATES TYPES
FOLDED PLATES TYPES FOLDED PLATES TYPES
FOLDED PLATES TYPES
 
Pneumatic structures
Pneumatic structuresPneumatic structures
Pneumatic structures
 

Similar to Vierendeel truss bs5

Suspension bridge
Suspension bridgeSuspension bridge
Suspension bridgeMohit Kumar
 
California Orthotropic-October-2005 & Millau Normandie France Mangus LinkedIn
California Orthotropic-October-2005 & Millau Normandie France Mangus LinkedInCalifornia Orthotropic-October-2005 & Millau Normandie France Mangus LinkedIn
California Orthotropic-October-2005 & Millau Normandie France Mangus LinkedInAlfred Mangus
 
Millau via duct presentation full analysis
Millau via duct presentation full analysisMillau via duct presentation full analysis
Millau via duct presentation full analysisMohammad Ali
 
Seminar on cable stayed bridge
Seminar on cable stayed bridgeSeminar on cable stayed bridge
Seminar on cable stayed bridgeSujeet Rajput
 
bailey bridges: circular economy in WorldWarII by BLIEBERG architects of a c...
bailey bridges:  circular economy in WorldWarII by BLIEBERG architects of a c...bailey bridges:  circular economy in WorldWarII by BLIEBERG architects of a c...
bailey bridges: circular economy in WorldWarII by BLIEBERG architects of a c...Kris Blykers
 
Slab & Vault
Slab & VaultSlab & Vault
Slab & Vaultwinner
 
Eiffle Tower | Elevator | History of Architecture
Eiffle Tower | Elevator | History of ArchitectureEiffle Tower | Elevator | History of Architecture
Eiffle Tower | Elevator | History of ArchitectureAkshit Charan
 
bailey bridges: circular economy in WorldWar2 by BLIEBERG architects of a cir...
bailey bridges: circular economy in WorldWar2 by BLIEBERG architects of a cir...bailey bridges: circular economy in WorldWar2 by BLIEBERG architects of a cir...
bailey bridges: circular economy in WorldWar2 by BLIEBERG architects of a cir...Kris Blykers
 
Engineering Landmarks in London
Engineering Landmarks in LondonEngineering Landmarks in London
Engineering Landmarks in LondonTristan Robinson
 
Analysis of Construction Criteria on Suspension Bridge A Perspective View
Analysis of Construction Criteria on Suspension Bridge A Perspective ViewAnalysis of Construction Criteria on Suspension Bridge A Perspective View
Analysis of Construction Criteria on Suspension Bridge A Perspective Viewijtsrd
 
Submerged floating tunnel
Submerged floating tunnelSubmerged floating tunnel
Submerged floating tunnelShaikh Ismail
 
industrial revolution Eiffel Tower
industrial revolution  Eiffel Tower industrial revolution  Eiffel Tower
industrial revolution Eiffel Tower MADHUKANT SINGH
 
Tensile structures for architects
Tensile structures for architectsTensile structures for architects
Tensile structures for architectsDeepak KUMAR
 

Similar to Vierendeel truss bs5 (20)

Suspension bridge
Suspension bridgeSuspension bridge
Suspension bridge
 
California Orthotropic-October-2005 & Millau Normandie France Mangus LinkedIn
California Orthotropic-October-2005 & Millau Normandie France Mangus LinkedInCalifornia Orthotropic-October-2005 & Millau Normandie France Mangus LinkedIn
California Orthotropic-October-2005 & Millau Normandie France Mangus LinkedIn
 
Millau via duct presentation full analysis
Millau via duct presentation full analysisMillau via duct presentation full analysis
Millau via duct presentation full analysis
 
Bridge and its types
Bridge and its types Bridge and its types
Bridge and its types
 
Millau viaduct
Millau viaductMillau viaduct
Millau viaduct
 
Seminar on cable stayed bridge
Seminar on cable stayed bridgeSeminar on cable stayed bridge
Seminar on cable stayed bridge
 
bailey bridges: circular economy in WorldWarII by BLIEBERG architects of a c...
bailey bridges:  circular economy in WorldWarII by BLIEBERG architects of a c...bailey bridges:  circular economy in WorldWarII by BLIEBERG architects of a c...
bailey bridges: circular economy in WorldWarII by BLIEBERG architects of a c...
 
Cable Structures.pdf
 Cable Structures.pdf Cable Structures.pdf
Cable Structures.pdf
 
Suspension bridge
Suspension bridgeSuspension bridge
Suspension bridge
 
Slab & Vault
Slab & VaultSlab & Vault
Slab & Vault
 
Tress
TressTress
Tress
 
Eiffle Tower | Elevator | History of Architecture
Eiffle Tower | Elevator | History of ArchitectureEiffle Tower | Elevator | History of Architecture
Eiffle Tower | Elevator | History of Architecture
 
bailey bridges: circular economy in WorldWar2 by BLIEBERG architects of a cir...
bailey bridges: circular economy in WorldWar2 by BLIEBERG architects of a cir...bailey bridges: circular economy in WorldWar2 by BLIEBERG architects of a cir...
bailey bridges: circular economy in WorldWar2 by BLIEBERG architects of a cir...
 
Engineering Landmarks in London
Engineering Landmarks in LondonEngineering Landmarks in London
Engineering Landmarks in London
 
Suspension Bridges
Suspension BridgesSuspension Bridges
Suspension Bridges
 
Analysis of Construction Criteria on Suspension Bridge A Perspective View
Analysis of Construction Criteria on Suspension Bridge A Perspective ViewAnalysis of Construction Criteria on Suspension Bridge A Perspective View
Analysis of Construction Criteria on Suspension Bridge A Perspective View
 
Submerged floating tunnel
Submerged floating tunnelSubmerged floating tunnel
Submerged floating tunnel
 
industrial revolution Eiffel Tower
industrial revolution  Eiffel Tower industrial revolution  Eiffel Tower
industrial revolution Eiffel Tower
 
Millau viaduct
Millau viaductMillau viaduct
Millau viaduct
 
Tensile structures for architects
Tensile structures for architectsTensile structures for architects
Tensile structures for architects
 

Recently uploaded

Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxhumanexperienceaaa
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAbhinavSharma374939
 

Recently uploaded (20)

Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog Converter
 

Vierendeel truss bs5

  • 2.  THE VIERENDEEL FRAME, or truss as it is more popularly but inappropriately called, is a series of rectangular frames which achieves stability by the rigid connection of the vertical web members to the top and bottom chord.  Contrary to the typical pin-connected truss in which all members are axially loaded and shear is transferred axially through diagonals, the Vierendeel transfers shear from the chords by bending moments at the joints and finally by bending moments in the vertical webs.  As a result, all members are combined stress members in which axial, shear, and bending stresses exist. INTRODUCTION
  • 3. • Such trusses do not have the usual triangular voids seen in a pin–joint truss bridge, rather employing rectangular openings and rigid connections in the elements, which (unlike a conventional truss) must also resist substantial bending forces. • Owing to a lesser economy of materials and the difficulty of design before the advent of computers, this truss is rarely used in bridges outside Belgium. The form is more commonly employed in building structures where large shear walls or diagonal elements would interfere with the building's aesthetics or functionality. • The first such bridge was built in steel at Avelgem, Belgium in 1902, following development of the truss form and a method to calculate its strength in 1896 by Arthur Vierendeel. There are many more examples in Belgium, also constructed in concrete, mostly designed by Vierendeel's many students in a long career as professor in civil engineering.
  • 4. • Despite the structural disadvantages surrounding the Vierendeel, it was in the area of civil engineering rather than architecture that it was first utilized-specifically for short-span bridges. • The Vierendeel's origin dates to I896. The Belgian engineer Arthur Vierendeel, then professor at the University of Louvain, unveiled the concept in his book Longerons en Treillis et Longerons a Arcades. At that time steel trusses required extremely large gusset plates to accommodate rivet groups; members were generally oversized and rarely did the center lines of all joined members intersect. • Therefore, the pin-jointed theory which ignored moments, due to these eccentricities, led to errors on the critical side, approaching fifteen percent when office calculations were compared to field measurements. HISTORY
  • 5. • These discrepancies between simplified analytical methods and reality are what led Professor Vierendeel to propose the rectangular rigid-jointed system where these eccentricities could be eliminated and accuracy between analysis and reality kept in close accord. • A smaller factor of safety could be used, due to this improved accuracy, so that in the early I900s Vierendeel bridges did weigh less than alternative truss solutions. • The first Vierendeel bridge was experimental. It spanned 96 feet and was tested in 1897 at Tervueren with an assimilated railway loading pattern. • The riveted framework responded by carrying 2.73 times the design live load and prompted the Belgian Bridge and Highway Department to state in their official report that, "In the present state of the question, the portal frame truss is, generally speaking, a system nearly equivalent to the triangulated truss.“ • The first actual usage of a Vierendeel bridge occurred in I901 with a 128-foot span of riveted construction at Avelghem, Belgium, followed by the I36-foot span at Ousselghem in I910, also riveted.
  • 6. • Decline Mishaps (cracks and dislocations), primarily due to insufficient knowledge of the ramifications of welding procedures, poor workmanship, and low steel quality, resulted in increasing skepticism about the Vierendeel system. • The collapse of a 245-foot-span bridge at Hasselt in 1938 was the most total and dramatic. • A Belgian committee assigned to investigate the collapse, together with outside consultants, concluded that the welded Vierendeel system, although considered to be adequately designed, was sensitive to external influences, such as cooling, heating, vibration, or impact. • By reason of its inherent joint rigidity, the system also attracted internal residual stresses and demanded an extensive knowledge of the art of welding. Similar problems with welded plate girder bridges were occurring in other countries of Europe. • It was apparent that welding technology needed to catch up with welding demand DECLINATION
  • 7.
  • 8.
  • 10. • The Albert Canal was constructed from 1930 through 1939. The German construction company Hochtief AG worked on the canal between 1930 and 1934, but it was completed by Belgian companies. The Albert Canal was used for the first time in 1940 but, because of World War II and the German occupation, intensive use only began later, in 1946. • During World War II, the Albert Canal functioned as a defense line. The crossing of the canal by the German forces and the destruction of Fort Eben-Emael on 11 May 1940 was a milestone in the German invasion of Belgium. • During the Liberation of Belgium by the Allies in September 1944, the Second Canadian Division was the first Allied unit to cross the Albert Canal. • The British Army also crossed the Albert Canal on its way north across Belgium and into The Netherlands and the U.S. Army entered Belgium further to the east on its way to liberate the rest of Belgium, and Luxembourg, and then proceed east to invade Nazi Germany. Hence, Belgium was liberated from the south by three different armies, two of which needed to cross the Albert Canal. ALBERT CANAL
  • 11. • In 2002, the canal carried a record 43 million tons of goods of various kinds, amounting to more than half the Belgian waterway total. • The canal is also a popular leisure and cycling destination, with well paved service roads on both sides traversing picturesque farm land, particularly around Smeermass, Lanaken and Maasmechelen.
  • 12.
  • 14. Geneva St. bridge in Glendale • The city of Glendale, California has three Vierendeel truss bridges: the Geneva Street, Kenilworth Avenue, and Glenoaks Boulevard bridges, all two-lane bridges spanning 95 feet. They were built in 1937 as part of the Verdugo Flood Control Project, the first project of the United States Army Corps of Engineers after passage of the Flood Control Act of 1936. • The double-deck cable-stayed Kap Shui Mun Bridge in Hong Kong uses a Vierendeel truss. Opened in 1997, the lower deck carries both rail and traffic, with the lack of diagonal members in the cross section allowing vehicles to drive through the openings provided by the Vierendeel design.
  • 16. BIBLIOGRAPHY REFERNCES • The Vierendeel Author(s): David J. Wickersheimer Source: Journal of the Society of Architectural Historians, Vol. 35, No. 1 (Mar., 1976), pp. 54- 60 Published by: University of California Press on behalf of the Society of Architectural Historians Stable URL: http://www.jstor.org/stable/988971 . Accessed: 10/07/2013 10:19 • Book: Building structures Author: Ching • www.arch.mcgill.ca • www.Wikipedia.com