SlideShare a Scribd company logo
VSM AND WIP WITH
RELATED TO ARENA
SIMULATION SOFTWARE
BY
Md. Asrafuzzaman
IPE, SUST
Objectives
Improve shop floor efficiency and
productivity by examining the
existing WIP scenario and reducing
WIP in the current manufacturing
line.
Background
 We find that in our production floor WIP is
a big problem and root cause of many
other problems.
 These problems are:
• Maintaining 5S,
• Quality issues,
• On time delivery,
• Line Efficiency,
• Learning curves,
• Line layout setup time
Status of one day of Manufacturing flow
Like at statistics at 16-6-2015
• Total cut pieces at = 34602 pieces
WIP= 8564 pieces
• Total input in line at =26038 Pieces
WIP= 103 pieces
• Total output line at = 25935 pieces
WIP= 492 pieces
• Total good pass quantity to finishing at
=25443 pieces
Some pictures of WIP in our production floor
Some picture related to 5S
Steps of the study
 First step: VSM a lean tool for
visualizing the real scenario of the
manufacturing flow
 Second step: Identify the WIP and
find the way of eliminating WIP
 Third step: Simulate the present
situation and proposed improvement
by using Arena simulation software
VSM
A value stream involves all the
steps, both value added and non
value added, required to complete a
product or service from beginning to
end
Overall steps involved in the study
VALUE STREAM & IDENTIFYING WIP
VALUE STREAM
RELAXATION CUTTING SEWING FINISHING
PROCESS PROCESS PROCESS PROCESS
RAW
MATERIALS
FINISHED
PRODUCT
CUSTOMER
WIP WIP WIP
THE STEPS - VALUE STREAMS MAPPING
Product
Family
Current State
drawing
Future State
drawing
Plan &
Implementation
Understanding how the shop floor currently
operates. The foundation for the value state.
Designing Lean Flow
Current state
Improved scenario of VSM
Measurable Metrics & Performance
Metric Current
Estimate
Target from Future
State Map
Process Time 55.26 Min. 55.26 Min.
Lead Time 8.390 Days 3.14 Days
First Time Quality 80% 80%
Data analysis and findings
The data and information was collected
through the observation of the production
floor and some past record from the
industrial engineering and planning
department .
Finally all data has been analyzed by
using various types of tables, some tools
such as cause effect diagram and 5S.
Causes of WIP
 Operator absenteeism
 Machine breakdown
 Improper line balancing in the
beginning of the layout.
 Raw materials supply problem
 Quality issues
Improvement proposal
 Operator skill matrix operation base
 Implementation of TPM ( Total
Productive Maintenance)
 Sewing line Layout analysis and
layout proposal
 Building supplier relationship, its a
long term process and cost and
quality related issues.
 Our IE and Quality team is working
on this, we will work on this issue in
future.
Operators skill matrixq
Implementation of TPM
1. There are 8
pillars of TPM
2. Already we are
practising some
of the pillars
3. Another
1. Autonomous
maintenance
2. Quality
maintenance
3. Planned
maintenance
we can implement
Simulation analysis of Layout
 By using arena
 1. present situation layout
 2. proposed layout result.
Present line in the Arena Simulation
Simulating result
Showing WIP by Arena
Cost related to implementation of
TPM
 To implementation TPM need 3 or 4
man for every unit, but they have to
work extra time or holyday when
production will not running. So have
to pay for extra time duty of the
employee.
 Total man power need = 12 to 16
• Already we have 13 man for
maintenance purpose
Cost related to Buy the Software
 I have no exact purchase related
idea.
 Hear provided contact details of
selling partner of Arena ( RockWell
Automation) Selling partner
China
Beijing EnSky
Contact Name: Zhang Qing
Phone: +86-10-59009377
Email: info@ensky.com.cn
Website: www.ensky.com.cn
https://www.arenasimulation.com/purchasing-options/global-partners-
contact-for-sales
Benefits
 Improve efficiency and productivity
 On time delivery
 Improve 5S
 Reduce new style layout time
Benefits
 Our floor space rent per sq. Ft per month
15.07 Taka, so that if we reduce WIP then
our every sq. Ft of space will be effectively
used
 Total CPM is 0.08$ so that if normal
Layout time is 8 hour more than normal
layout time ( 6 hour ) then extra loss of
taka per month, 19353.6 $ ( extra cost for 1
lay out 537.6 $)
Benefits
 If we miss the shipment schedule then we
have to pay for air shipment, which
manufacturer have to pay for lost the
shipment schedule.
 Cost per kg for Europe: 3$ and 1.6$ for
non Europe air shipment.
 So per container 400 cartoon cost:
• Europe : 24000$ ( per container)
• Non Europe: 12800$
Simulation software related
For improving the running low efficient
line performance usually do:
• Layout change
• More skill and efficient operator involve
• Process improvement
To do these we need around 3 hours to come
out expected results.
If the result will not come then we will loss for
4867.2$ for one month ( on basis of line status of 26-
5-2015, 13 line of that day ware not meet the expected result)
Case study result provided by RockWell
Automation
Challenges:
 Increase
throughput
 Decrease inventory
 Decrease operating
expenses and cycle
time
 Do a better job of
capacity planning
 Gain access to
accurate, timely
information
Results after using Arena:
 The model helped the
manufacturer increase sales by
more than $1 million
 The simulation effort identified
several options to optimize
process performance
 Cycle time was reduced from 5
weeks to 3 days
 Overtime and operating
expenses were lowered
 On-time shipping performance
increased 70% to 95%
Sources:
https://www.arenasimulation.com/resources/Production_simulation.pdf
Recommendation
 Technique such as zero defects, setup
time reduction, and Poka-Yoke can be
applied.
 Arrange schedule training operator
 To reduce absenteeism and to build up
moral and trust:
• Job enrichment,
• Relationship improvement between employee
and management,
• Worker motivation.
WIP running status and proposal
Unit Line Style Name Target Input/Day Total Input Total Output WIP C urrent WIP Target
Our WIP
target
Reduce pcs Reduce %
UNA
SAA Maja Crochet 1040 40165 37542 -2623 1560 1040 -520 35%
SAB Vincent Top 1150 9383 6223 -3160 1725 1150 -575 35%
SAC Vincent Top 1150 4517 1626 -2891 1725 1150 -575 35%
SAD Vincent Top 1150 7583 3916 -3667 1725 1150 -575 35%
SAE Majken dress-CWG 900 28054 25456 -2598 1620 900 -720 35%
SAF Vincent Top 1150 6504 4829 -1675 1725 1150 -575 35%
UNB
SBA Majken dress-CWG 900 20113 18218 -1895 1620 900 -720 35%
SBB Chung Top 1550 32449 30189 -2260 2325 1550 -775 35%
SBC Vincent Top 1150 6468 3731 -2737 1725 1150 -575 35%
SBD Vincent Top 1150 9269 6710 -2559 1725 1150 -575 35%
SBE Chilli tunic 690 5882 4496 -1386 1035 690 -345 35%
SBF Vincent Top 1150 9214 6651 -2563 1725 1150 -575 35%
UNC
SCA Vincent Top 1150 11438 7765 -3673 1725 1150 -575 35%
SCB Vincent Top 1150 11920 10605 -1315 1725 1150 -575 35%
SCC Chilli tunic 690 4885 3224 -1661 1035 690 -345 35%
SCD Majken dress CWH 900 9213 7319 -1894 1620 900 -720 35%
SCE Vincent Top 1150 7312 3620 -3692 1725 1150 -575 35%
SCF Rosie S-2 1590 1480 45 -1435 2385 1590 -795 35%
UND
SDA Chung Top 1550 36133 34272 -1861 2325 1550 -775 35%
SDB Maja Crochet 1040 31066 28910 -2156 1560 1040 -520 35%
SDC Vincent Top 1150 11544 8384 -3160 1725 1150 -575 35%
SDD Majken dress CWH 900 5653 4083 -1570 1620 900 -720 35%
SDE Vincent Top 1150 9342 6970 -2372 1725 1150 -575 35%
SDF Rosie S-2 1590 10698 9417 -1281 2385 1590 -795 35%
G.Total 27140 330285 274201 -56084 41790 27140 -14650 35%
Recommendation Con’t...
 Improve supplier relationship to get
the raw materials on time and
standard quality.
 Arrange the Arena Simulation
commercial version software to save
the dollar in relation with the
interruption of the line due to
experiment for process improvement
Conclusion
 VSM was implemented to find out the
amount of wastes and WIP in cutting,
sewing and finishing section; because the
selected product had a long lead time and
was unable to meet the expected
production rate . Cause effect and was
done to identify the reason of WIP, and
proposing different solution.
Conclusion Con’t...
 As VSM can be drawn in relatively short time with
almost no expenditure of money and as it can
identify wastes with good accuracy, thus it’s very
helpful for managers who are having difficulties
with their low production rate, higher lead time
and high production costs high WIP.
 The simulation software helps to represent the
real problems and analyse the total process and
make scope to improve without interruption the
production process, and after getting appropriate
solution direct implement it in the manufacturing
process.

More Related Content

What's hot

Lean Process Improvement Techniques
Lean Process Improvement TechniquesLean Process Improvement Techniques
Lean Process Improvement Techniques
Jeremy Jay V. Lim, MBB, PMP
 
Value Stream Mapping: Case Studies
Value Stream Mapping: Case StudiesValue Stream Mapping: Case Studies
Value Stream Mapping: Case Studies
TKMG, Inc.
 
Lean Six Sigma Green Belt Project No-Show Rate Reduction
Lean Six Sigma Green Belt Project No-Show Rate ReductionLean Six Sigma Green Belt Project No-Show Rate Reduction
Lean Six Sigma Green Belt Project No-Show Rate Reduction
John W. McAfee, MHA, PMP, FACHE
 
Spaghetti Diagrams
Spaghetti DiagramsSpaghetti Diagrams
Eliminating the production bottlenecks
Eliminating the production bottlenecksEliminating the production bottlenecks
Eliminating the production bottlenecks
dutconsult
 
Error-Proofing in Office & Service Environments
Error-Proofing in Office & Service Environments Error-Proofing in Office & Service Environments
Error-Proofing in Office & Service Environments
TKMG, Inc.
 
8 WASTES IN LEAN MANUFACUTING & OVERVIEW OF VSM
8 WASTES IN LEAN MANUFACUTING & OVERVIEW OF VSM8 WASTES IN LEAN MANUFACUTING & OVERVIEW OF VSM
8 WASTES IN LEAN MANUFACUTING & OVERVIEW OF VSM
SedhuSiddarth
 
WEBINAR: Introduction to DMAIC
WEBINAR: Introduction to DMAICWEBINAR: Introduction to DMAIC
WEBINAR: Introduction to DMAIC
GoLeanSixSigma.com
 
Simple Process Mapping Techniques
Simple Process Mapping TechniquesSimple Process Mapping Techniques
Simple Process Mapping Techniques
Stephen Deas
 
SMED or Single Minute Exchange of Dies and Set-up Reduction Process
SMED or Single Minute Exchange of Dies and Set-up Reduction ProcessSMED or Single Minute Exchange of Dies and Set-up Reduction Process
SMED or Single Minute Exchange of Dies and Set-up Reduction Process
W3 Group Canada Inc.
 
Apqp fundamentals
Apqp fundamentalsApqp fundamentals
Apqp fundamentals
Jitesh Gaurav
 
Green Belt Project Storyboard Template Example
Green Belt Project Storyboard Template Example Green Belt Project Storyboard Template Example
Green Belt Project Storyboard Template Example
GoLeanSixSigma.com
 
LEAN SPEED vs SIX SIGMA QUALITY by JULIAN KALAC
LEAN SPEED vs SIX SIGMA QUALITY by JULIAN KALAC LEAN SPEED vs SIX SIGMA QUALITY by JULIAN KALAC
LEAN SPEED vs SIX SIGMA QUALITY by JULIAN KALAC
Julian Kalac P.Eng
 
02trainingmaterialformsa (1) 111030062223-phpapp02
02trainingmaterialformsa (1) 111030062223-phpapp0202trainingmaterialformsa (1) 111030062223-phpapp02
02trainingmaterialformsa (1) 111030062223-phpapp02
Junelly Grace Catalan-Tecson
 
Lean Six Sigma Green Belt roadmap poster
Lean Six Sigma Green Belt roadmap posterLean Six Sigma Green Belt roadmap poster
Lean Six Sigma Green Belt roadmap poster
Francisco Pulgar-Vidal, MBA, Lean Six Sigma MBB
 
Value Stream Mapping
Value Stream MappingValue Stream Mapping
Value Stream Mapping
TKMG, Inc.
 
Visual Management by Operational Excellence Consulting
Visual Management by Operational Excellence ConsultingVisual Management by Operational Excellence Consulting
Visual Management by Operational Excellence Consulting
Operational Excellence Consulting
 
Six Sigma DMAIC Case Study
Six Sigma DMAIC Case StudySix Sigma DMAIC Case Study
Six Sigma DMAIC Case Study
Nitesh Verma
 
Six sigma case study-a good approach with example
Six sigma case study-a good approach with exampleSix sigma case study-a good approach with example
Six sigma case study-a good approach with example
bhanutomar
 
Six sigma-black-belt-project-sample
Six sigma-black-belt-project-sampleSix sigma-black-belt-project-sample
Six sigma-black-belt-project-sample
Noble Institute of Quality Certification (NIQC)
 

What's hot (20)

Lean Process Improvement Techniques
Lean Process Improvement TechniquesLean Process Improvement Techniques
Lean Process Improvement Techniques
 
Value Stream Mapping: Case Studies
Value Stream Mapping: Case StudiesValue Stream Mapping: Case Studies
Value Stream Mapping: Case Studies
 
Lean Six Sigma Green Belt Project No-Show Rate Reduction
Lean Six Sigma Green Belt Project No-Show Rate ReductionLean Six Sigma Green Belt Project No-Show Rate Reduction
Lean Six Sigma Green Belt Project No-Show Rate Reduction
 
Spaghetti Diagrams
Spaghetti DiagramsSpaghetti Diagrams
Spaghetti Diagrams
 
Eliminating the production bottlenecks
Eliminating the production bottlenecksEliminating the production bottlenecks
Eliminating the production bottlenecks
 
Error-Proofing in Office & Service Environments
Error-Proofing in Office & Service Environments Error-Proofing in Office & Service Environments
Error-Proofing in Office & Service Environments
 
8 WASTES IN LEAN MANUFACUTING & OVERVIEW OF VSM
8 WASTES IN LEAN MANUFACUTING & OVERVIEW OF VSM8 WASTES IN LEAN MANUFACUTING & OVERVIEW OF VSM
8 WASTES IN LEAN MANUFACUTING & OVERVIEW OF VSM
 
WEBINAR: Introduction to DMAIC
WEBINAR: Introduction to DMAICWEBINAR: Introduction to DMAIC
WEBINAR: Introduction to DMAIC
 
Simple Process Mapping Techniques
Simple Process Mapping TechniquesSimple Process Mapping Techniques
Simple Process Mapping Techniques
 
SMED or Single Minute Exchange of Dies and Set-up Reduction Process
SMED or Single Minute Exchange of Dies and Set-up Reduction ProcessSMED or Single Minute Exchange of Dies and Set-up Reduction Process
SMED or Single Minute Exchange of Dies and Set-up Reduction Process
 
Apqp fundamentals
Apqp fundamentalsApqp fundamentals
Apqp fundamentals
 
Green Belt Project Storyboard Template Example
Green Belt Project Storyboard Template Example Green Belt Project Storyboard Template Example
Green Belt Project Storyboard Template Example
 
LEAN SPEED vs SIX SIGMA QUALITY by JULIAN KALAC
LEAN SPEED vs SIX SIGMA QUALITY by JULIAN KALAC LEAN SPEED vs SIX SIGMA QUALITY by JULIAN KALAC
LEAN SPEED vs SIX SIGMA QUALITY by JULIAN KALAC
 
02trainingmaterialformsa (1) 111030062223-phpapp02
02trainingmaterialformsa (1) 111030062223-phpapp0202trainingmaterialformsa (1) 111030062223-phpapp02
02trainingmaterialformsa (1) 111030062223-phpapp02
 
Lean Six Sigma Green Belt roadmap poster
Lean Six Sigma Green Belt roadmap posterLean Six Sigma Green Belt roadmap poster
Lean Six Sigma Green Belt roadmap poster
 
Value Stream Mapping
Value Stream MappingValue Stream Mapping
Value Stream Mapping
 
Visual Management by Operational Excellence Consulting
Visual Management by Operational Excellence ConsultingVisual Management by Operational Excellence Consulting
Visual Management by Operational Excellence Consulting
 
Six Sigma DMAIC Case Study
Six Sigma DMAIC Case StudySix Sigma DMAIC Case Study
Six Sigma DMAIC Case Study
 
Six sigma case study-a good approach with example
Six sigma case study-a good approach with exampleSix sigma case study-a good approach with example
Six sigma case study-a good approach with example
 
Six sigma-black-belt-project-sample
Six sigma-black-belt-project-sampleSix sigma-black-belt-project-sample
Six sigma-black-belt-project-sample
 

Viewers also liked

Value stream mapping using simulation with ARENA
Value stream mapping using simulation with ARENAValue stream mapping using simulation with ARENA
Value stream mapping using simulation with ARENA
hrishik26
 
Guia de usuario arena
Guia de usuario arenaGuia de usuario arena
Guia de usuario arena
Sadamii Rap
 
Simulation Modelling: Costa Coffee (London, UK)
Simulation Modelling: Costa Coffee (London, UK)Simulation Modelling: Costa Coffee (London, UK)
Simulation Modelling: Costa Coffee (London, UK)
Alejandro Duke
 
Simulation Modelling final_project_ganganer
Simulation Modelling final_project_ganganerSimulation Modelling final_project_ganganer
Simulation Modelling final_project_ganganer
Rutuja Gangane
 
Simulation for kfc order counter at rajiv gandhi international airport, hyder...
Simulation for kfc order counter at rajiv gandhi international airport, hyder...Simulation for kfc order counter at rajiv gandhi international airport, hyder...
Simulation for kfc order counter at rajiv gandhi international airport, hyder...
Pankaj Gaurav
 
Simulation Project in ARENA
Simulation Project in ARENASimulation Project in ARENA
Simulation Project in ARENA
Aditya Nakate
 
Benzetim modelleme örnekleri - Arena - Examples arena simulation program
Benzetim modelleme örnekleri - Arena - Examples arena simulation programBenzetim modelleme örnekleri - Arena - Examples arena simulation program
Benzetim modelleme örnekleri - Arena - Examples arena simulation program
Kazım Anıl AYDIN
 
Kroger Store Simulation Using Arena
Kroger Store Simulation Using ArenaKroger Store Simulation Using Arena
Kroger Store Simulation Using Arena
Dhivya Rajprasad
 
Simulation Modeling on Campus Starbucks Coffee Center
Simulation Modeling on Campus Starbucks Coffee CenterSimulation Modeling on Campus Starbucks Coffee Center
Simulation Modeling on Campus Starbucks Coffee Center
Niharika Senecha
 
Modeling and Simulation of an electrical micro-grid using MATLAB Simulink Sum...
Modeling and Simulation of an electrical micro-grid using MATLAB Simulink Sum...Modeling and Simulation of an electrical micro-grid using MATLAB Simulink Sum...
Modeling and Simulation of an electrical micro-grid using MATLAB Simulink Sum...
Aodhgan Gleeson
 
Simulation with ARENA - SM Paints
Simulation with ARENA - SM PaintsSimulation with ARENA - SM Paints
Simulation with ARENA - SM Paints
hrishik26
 
Simulation Project Report
Simulation Project ReportSimulation Project Report
Simulation Project Report
Jasmine Sachdeva
 
Simulation with Arena (Dental Clinic project)
Simulation with Arena (Dental Clinic project)Simulation with Arena (Dental Clinic project)
Simulation with Arena (Dental Clinic project)
Kimseng Sok
 
Starbucks Wait Time Analysis
Starbucks Wait Time AnalysisStarbucks Wait Time Analysis
Starbucks Wait Time Analysis
Brandon Theiss, PE
 
Microgrid
MicrogridMicrogrid
Microgrid
Anula Khare
 
Value Stream Mapping -The Concept
Value Stream Mapping -The ConceptValue Stream Mapping -The Concept
Value Stream Mapping -The Concept
Subhrajyoti Parida
 

Viewers also liked (16)

Value stream mapping using simulation with ARENA
Value stream mapping using simulation with ARENAValue stream mapping using simulation with ARENA
Value stream mapping using simulation with ARENA
 
Guia de usuario arena
Guia de usuario arenaGuia de usuario arena
Guia de usuario arena
 
Simulation Modelling: Costa Coffee (London, UK)
Simulation Modelling: Costa Coffee (London, UK)Simulation Modelling: Costa Coffee (London, UK)
Simulation Modelling: Costa Coffee (London, UK)
 
Simulation Modelling final_project_ganganer
Simulation Modelling final_project_ganganerSimulation Modelling final_project_ganganer
Simulation Modelling final_project_ganganer
 
Simulation for kfc order counter at rajiv gandhi international airport, hyder...
Simulation for kfc order counter at rajiv gandhi international airport, hyder...Simulation for kfc order counter at rajiv gandhi international airport, hyder...
Simulation for kfc order counter at rajiv gandhi international airport, hyder...
 
Simulation Project in ARENA
Simulation Project in ARENASimulation Project in ARENA
Simulation Project in ARENA
 
Benzetim modelleme örnekleri - Arena - Examples arena simulation program
Benzetim modelleme örnekleri - Arena - Examples arena simulation programBenzetim modelleme örnekleri - Arena - Examples arena simulation program
Benzetim modelleme örnekleri - Arena - Examples arena simulation program
 
Kroger Store Simulation Using Arena
Kroger Store Simulation Using ArenaKroger Store Simulation Using Arena
Kroger Store Simulation Using Arena
 
Simulation Modeling on Campus Starbucks Coffee Center
Simulation Modeling on Campus Starbucks Coffee CenterSimulation Modeling on Campus Starbucks Coffee Center
Simulation Modeling on Campus Starbucks Coffee Center
 
Modeling and Simulation of an electrical micro-grid using MATLAB Simulink Sum...
Modeling and Simulation of an electrical micro-grid using MATLAB Simulink Sum...Modeling and Simulation of an electrical micro-grid using MATLAB Simulink Sum...
Modeling and Simulation of an electrical micro-grid using MATLAB Simulink Sum...
 
Simulation with ARENA - SM Paints
Simulation with ARENA - SM PaintsSimulation with ARENA - SM Paints
Simulation with ARENA - SM Paints
 
Simulation Project Report
Simulation Project ReportSimulation Project Report
Simulation Project Report
 
Simulation with Arena (Dental Clinic project)
Simulation with Arena (Dental Clinic project)Simulation with Arena (Dental Clinic project)
Simulation with Arena (Dental Clinic project)
 
Starbucks Wait Time Analysis
Starbucks Wait Time AnalysisStarbucks Wait Time Analysis
Starbucks Wait Time Analysis
 
Microgrid
MicrogridMicrogrid
Microgrid
 
Value Stream Mapping -The Concept
Value Stream Mapping -The ConceptValue Stream Mapping -The Concept
Value Stream Mapping -The Concept
 

Similar to Vsm and wip with arena simulation

Project cycle
Project cycleProject cycle
Project cycle
Dema Dias
 
H0432045055
H0432045055H0432045055
H0432045055
theijes
 
Six Sigma Project Charter Attributa Data of Roshan Weeratunga
Six Sigma Project Charter Attributa Data of Roshan   WeeratungaSix Sigma Project Charter Attributa Data of Roshan   Weeratunga
Six Sigma Project Charter Attributa Data of Roshan Weeratunga
Roshan Sujeewa Weeratunga
 
AMO_General_2015
AMO_General_2015AMO_General_2015
AMO_General_2015
Mignon Sweeney
 
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN...
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY  IMPLEMENTING LEAN TOOLS AN...IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY  IMPLEMENTING LEAN TOOLS AN...
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN...
Karina Islam
 
Italy MAG Wire Business case _Scada system Jan 2016 english version
Italy MAG Wire Business case _Scada system Jan 2016 english versionItaly MAG Wire Business case _Scada system Jan 2016 english version
Italy MAG Wire Business case _Scada system Jan 2016 english version
Luizclaudiomatto
 
2.IE Presentation.pptx
2.IE Presentation.pptx2.IE Presentation.pptx
2.IE Presentation.pptx
Varun Mehrotra
 
130135794-Training-Outline-for-Management-Trainee.pptx
130135794-Training-Outline-for-Management-Trainee.pptx130135794-Training-Outline-for-Management-Trainee.pptx
130135794-Training-Outline-for-Management-Trainee.pptx
Nittamallik216
 
Renni Consultancy - Introduction
Renni Consultancy - IntroductionRenni Consultancy - Introduction
Renni Consultancy - Introduction
Divakaran Narasimhachari
 
Study on Improving Throughput Time through Value Stream Mapping
Study on Improving Throughput Time through Value Stream MappingStudy on Improving Throughput Time through Value Stream Mapping
Study on Improving Throughput Time through Value Stream Mapping
Alwin Thomas
 
Sip
SipSip
Asq int lss
Asq int lssAsq int lss
Asq int lss
Omnex Inc.
 
Designing and Running Performance Experiments
Designing and Running Performance ExperimentsDesigning and Running Performance Experiments
Designing and Running Performance Experiments
J On The Beach
 
SMC CFT 2012-13-IInd Half.
SMC CFT 2012-13-IInd Half.SMC CFT 2012-13-IInd Half.
SMC CFT 2012-13-IInd Half.
Santhana Bharathi
 
IRJET- Efficiency Enhancement by Reducing Production and Machining Time
IRJET-  	  Efficiency Enhancement by Reducing Production and Machining TimeIRJET-  	  Efficiency Enhancement by Reducing Production and Machining Time
IRJET- Efficiency Enhancement by Reducing Production and Machining Time
IRJET Journal
 
Completed & Current LSS Projects
Completed & Current LSS ProjectsCompleted & Current LSS Projects
Completed & Current LSS Projects
John Smith
 
Gluer project Slough-FINAL DRAFT1
Gluer project Slough-FINAL DRAFT1Gluer project Slough-FINAL DRAFT1
Gluer project Slough-FINAL DRAFT1
Dipl.-Ing. Emmanuel M. MSc., CLSSBB, MBB, LMP
 
PALCO INDUSTRY USING VALUE STREAM MAPPING
PALCO INDUSTRY USING VALUE STREAM MAPPINGPALCO INDUSTRY USING VALUE STREAM MAPPING
PALCO INDUSTRY USING VALUE STREAM MAPPING
FuratAj
 
Lean Manufacturign Simulator
Lean Manufacturign SimulatorLean Manufacturign Simulator
Lean Manufacturign Simulator
Edgar Cardenas Sanchez
 
Assembly Line Balancing | Case Study
Assembly Line Balancing | Case StudyAssembly Line Balancing | Case Study
Assembly Line Balancing | Case Study
Md Abu Bakar Siddique
 

Similar to Vsm and wip with arena simulation (20)

Project cycle
Project cycleProject cycle
Project cycle
 
H0432045055
H0432045055H0432045055
H0432045055
 
Six Sigma Project Charter Attributa Data of Roshan Weeratunga
Six Sigma Project Charter Attributa Data of Roshan   WeeratungaSix Sigma Project Charter Attributa Data of Roshan   Weeratunga
Six Sigma Project Charter Attributa Data of Roshan Weeratunga
 
AMO_General_2015
AMO_General_2015AMO_General_2015
AMO_General_2015
 
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN...
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY  IMPLEMENTING LEAN TOOLS AN...IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY  IMPLEMENTING LEAN TOOLS AN...
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN...
 
Italy MAG Wire Business case _Scada system Jan 2016 english version
Italy MAG Wire Business case _Scada system Jan 2016 english versionItaly MAG Wire Business case _Scada system Jan 2016 english version
Italy MAG Wire Business case _Scada system Jan 2016 english version
 
2.IE Presentation.pptx
2.IE Presentation.pptx2.IE Presentation.pptx
2.IE Presentation.pptx
 
130135794-Training-Outline-for-Management-Trainee.pptx
130135794-Training-Outline-for-Management-Trainee.pptx130135794-Training-Outline-for-Management-Trainee.pptx
130135794-Training-Outline-for-Management-Trainee.pptx
 
Renni Consultancy - Introduction
Renni Consultancy - IntroductionRenni Consultancy - Introduction
Renni Consultancy - Introduction
 
Study on Improving Throughput Time through Value Stream Mapping
Study on Improving Throughput Time through Value Stream MappingStudy on Improving Throughput Time through Value Stream Mapping
Study on Improving Throughput Time through Value Stream Mapping
 
Sip
SipSip
Sip
 
Asq int lss
Asq int lssAsq int lss
Asq int lss
 
Designing and Running Performance Experiments
Designing and Running Performance ExperimentsDesigning and Running Performance Experiments
Designing and Running Performance Experiments
 
SMC CFT 2012-13-IInd Half.
SMC CFT 2012-13-IInd Half.SMC CFT 2012-13-IInd Half.
SMC CFT 2012-13-IInd Half.
 
IRJET- Efficiency Enhancement by Reducing Production and Machining Time
IRJET-  	  Efficiency Enhancement by Reducing Production and Machining TimeIRJET-  	  Efficiency Enhancement by Reducing Production and Machining Time
IRJET- Efficiency Enhancement by Reducing Production and Machining Time
 
Completed & Current LSS Projects
Completed & Current LSS ProjectsCompleted & Current LSS Projects
Completed & Current LSS Projects
 
Gluer project Slough-FINAL DRAFT1
Gluer project Slough-FINAL DRAFT1Gluer project Slough-FINAL DRAFT1
Gluer project Slough-FINAL DRAFT1
 
PALCO INDUSTRY USING VALUE STREAM MAPPING
PALCO INDUSTRY USING VALUE STREAM MAPPINGPALCO INDUSTRY USING VALUE STREAM MAPPING
PALCO INDUSTRY USING VALUE STREAM MAPPING
 
Lean Manufacturign Simulator
Lean Manufacturign SimulatorLean Manufacturign Simulator
Lean Manufacturign Simulator
 
Assembly Line Balancing | Case Study
Assembly Line Balancing | Case StudyAssembly Line Balancing | Case Study
Assembly Line Balancing | Case Study
 

Recently uploaded

12 steps to transform your organization into the agile org you deserve
12 steps to transform your organization into the agile org you deserve12 steps to transform your organization into the agile org you deserve
12 steps to transform your organization into the agile org you deserve
Pierre E. NEIS
 
Comparing Stability and Sustainability in Agile Systems
Comparing Stability and Sustainability in Agile SystemsComparing Stability and Sustainability in Agile Systems
Comparing Stability and Sustainability in Agile Systems
Rob Healy
 
The Management Guide: From Projects to Portfolio
The Management Guide: From Projects to PortfolioThe Management Guide: From Projects to Portfolio
The Management Guide: From Projects to Portfolio
Ahmed AbdelMoneim
 
Sethurathnam Ravi: A Legacy in Finance and Leadership
Sethurathnam Ravi: A Legacy in Finance and LeadershipSethurathnam Ravi: A Legacy in Finance and Leadership
Sethurathnam Ravi: A Legacy in Finance and Leadership
Anjana Josie
 
在线办理(Murdoch毕业证书)莫道克大学毕业证电子版成绩单一模一样
在线办理(Murdoch毕业证书)莫道克大学毕业证电子版成绩单一模一样在线办理(Murdoch毕业证书)莫道克大学毕业证电子版成绩单一模一样
在线办理(Murdoch毕业证书)莫道克大学毕业证电子版成绩单一模一样
tdt5v4b
 
Employment Practices Regulation and Multinational Corporations
Employment PracticesRegulation and Multinational CorporationsEmployment PracticesRegulation and Multinational Corporations
Employment Practices Regulation and Multinational Corporations
RoopaTemkar
 
Impact of Effective Performance Appraisal Systems on Employee Motivation and ...
Impact of Effective Performance Appraisal Systems on Employee Motivation and ...Impact of Effective Performance Appraisal Systems on Employee Motivation and ...
Impact of Effective Performance Appraisal Systems on Employee Motivation and ...
Dr. Nazrul Islam
 
Enriching engagement with ethical review processes
Enriching engagement with ethical review processesEnriching engagement with ethical review processes
Enriching engagement with ethical review processes
strikingabalance
 
Stuart Wilson the teams I have led - 2024
Stuart Wilson the teams I have led - 2024Stuart Wilson the teams I have led - 2024
Stuart Wilson the teams I have led - 2024
stuwilson.co.uk
 
Chart--Time Management.pdf How to time is spent
Chart--Time Management.pdf How to time is spentChart--Time Management.pdf How to time is spent
Chart--Time Management.pdf How to time is spent
spandane
 
原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样
原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样
原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样
tdt5v4b
 
原版制作(CDU毕业证书)查尔斯达尔文大学毕业证PDF成绩单一模一样
原版制作(CDU毕业证书)查尔斯达尔文大学毕业证PDF成绩单一模一样原版制作(CDU毕业证书)查尔斯达尔文大学毕业证PDF成绩单一模一样
原版制作(CDU毕业证书)查尔斯达尔文大学毕业证PDF成绩单一模一样
tdt5v4b
 
一比一原版(QU毕业证)皇后大学毕业证如何办理
一比一原版(QU毕业证)皇后大学毕业证如何办理一比一原版(QU毕业证)皇后大学毕业证如何办理
一比一原版(QU毕业证)皇后大学毕业证如何办理
8p28uk6g
 
Addiction to Winning Across Diverse Populations.pdf
Addiction to Winning Across Diverse Populations.pdfAddiction to Winning Across Diverse Populations.pdf
Addiction to Winning Across Diverse Populations.pdf
Bill641377
 
Risk-Management-presentation for cooperatives
Risk-Management-presentation for cooperativesRisk-Management-presentation for cooperatives
Risk-Management-presentation for cooperatives
bernanbumatay1
 
Credit Management training seminar power point presentation
Credit Management training seminar power point presentationCredit Management training seminar power point presentation
Credit Management training seminar power point presentation
bernanbumatay1
 
Colby Hobson: Residential Construction Leader Building a Solid Reputation Thr...
Colby Hobson: Residential Construction Leader Building a Solid Reputation Thr...Colby Hobson: Residential Construction Leader Building a Solid Reputation Thr...
Colby Hobson: Residential Construction Leader Building a Solid Reputation Thr...
dsnow9802
 
Strategy for E-Types - Strategy Formulation.pptx
Strategy for E-Types - Strategy Formulation.pptxStrategy for E-Types - Strategy Formulation.pptx
Strategy for E-Types - Strategy Formulation.pptx
KarthikRaghu8
 
innovation in nursing practice, education and management.pptx
innovation in nursing practice, education and management.pptxinnovation in nursing practice, education and management.pptx
innovation in nursing practice, education and management.pptx
TulsiDhidhi1
 
Ganpati Kumar Choudhary Indian Ethos PPT.pptx
Ganpati Kumar Choudhary Indian Ethos PPT.pptxGanpati Kumar Choudhary Indian Ethos PPT.pptx
Ganpati Kumar Choudhary Indian Ethos PPT.pptx
GanpatiKumarChoudhar
 

Recently uploaded (20)

12 steps to transform your organization into the agile org you deserve
12 steps to transform your organization into the agile org you deserve12 steps to transform your organization into the agile org you deserve
12 steps to transform your organization into the agile org you deserve
 
Comparing Stability and Sustainability in Agile Systems
Comparing Stability and Sustainability in Agile SystemsComparing Stability and Sustainability in Agile Systems
Comparing Stability and Sustainability in Agile Systems
 
The Management Guide: From Projects to Portfolio
The Management Guide: From Projects to PortfolioThe Management Guide: From Projects to Portfolio
The Management Guide: From Projects to Portfolio
 
Sethurathnam Ravi: A Legacy in Finance and Leadership
Sethurathnam Ravi: A Legacy in Finance and LeadershipSethurathnam Ravi: A Legacy in Finance and Leadership
Sethurathnam Ravi: A Legacy in Finance and Leadership
 
在线办理(Murdoch毕业证书)莫道克大学毕业证电子版成绩单一模一样
在线办理(Murdoch毕业证书)莫道克大学毕业证电子版成绩单一模一样在线办理(Murdoch毕业证书)莫道克大学毕业证电子版成绩单一模一样
在线办理(Murdoch毕业证书)莫道克大学毕业证电子版成绩单一模一样
 
Employment Practices Regulation and Multinational Corporations
Employment PracticesRegulation and Multinational CorporationsEmployment PracticesRegulation and Multinational Corporations
Employment Practices Regulation and Multinational Corporations
 
Impact of Effective Performance Appraisal Systems on Employee Motivation and ...
Impact of Effective Performance Appraisal Systems on Employee Motivation and ...Impact of Effective Performance Appraisal Systems on Employee Motivation and ...
Impact of Effective Performance Appraisal Systems on Employee Motivation and ...
 
Enriching engagement with ethical review processes
Enriching engagement with ethical review processesEnriching engagement with ethical review processes
Enriching engagement with ethical review processes
 
Stuart Wilson the teams I have led - 2024
Stuart Wilson the teams I have led - 2024Stuart Wilson the teams I have led - 2024
Stuart Wilson the teams I have led - 2024
 
Chart--Time Management.pdf How to time is spent
Chart--Time Management.pdf How to time is spentChart--Time Management.pdf How to time is spent
Chart--Time Management.pdf How to time is spent
 
原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样
原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样
原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样
 
原版制作(CDU毕业证书)查尔斯达尔文大学毕业证PDF成绩单一模一样
原版制作(CDU毕业证书)查尔斯达尔文大学毕业证PDF成绩单一模一样原版制作(CDU毕业证书)查尔斯达尔文大学毕业证PDF成绩单一模一样
原版制作(CDU毕业证书)查尔斯达尔文大学毕业证PDF成绩单一模一样
 
一比一原版(QU毕业证)皇后大学毕业证如何办理
一比一原版(QU毕业证)皇后大学毕业证如何办理一比一原版(QU毕业证)皇后大学毕业证如何办理
一比一原版(QU毕业证)皇后大学毕业证如何办理
 
Addiction to Winning Across Diverse Populations.pdf
Addiction to Winning Across Diverse Populations.pdfAddiction to Winning Across Diverse Populations.pdf
Addiction to Winning Across Diverse Populations.pdf
 
Risk-Management-presentation for cooperatives
Risk-Management-presentation for cooperativesRisk-Management-presentation for cooperatives
Risk-Management-presentation for cooperatives
 
Credit Management training seminar power point presentation
Credit Management training seminar power point presentationCredit Management training seminar power point presentation
Credit Management training seminar power point presentation
 
Colby Hobson: Residential Construction Leader Building a Solid Reputation Thr...
Colby Hobson: Residential Construction Leader Building a Solid Reputation Thr...Colby Hobson: Residential Construction Leader Building a Solid Reputation Thr...
Colby Hobson: Residential Construction Leader Building a Solid Reputation Thr...
 
Strategy for E-Types - Strategy Formulation.pptx
Strategy for E-Types - Strategy Formulation.pptxStrategy for E-Types - Strategy Formulation.pptx
Strategy for E-Types - Strategy Formulation.pptx
 
innovation in nursing practice, education and management.pptx
innovation in nursing practice, education and management.pptxinnovation in nursing practice, education and management.pptx
innovation in nursing practice, education and management.pptx
 
Ganpati Kumar Choudhary Indian Ethos PPT.pptx
Ganpati Kumar Choudhary Indian Ethos PPT.pptxGanpati Kumar Choudhary Indian Ethos PPT.pptx
Ganpati Kumar Choudhary Indian Ethos PPT.pptx
 

Vsm and wip with arena simulation

  • 1. VSM AND WIP WITH RELATED TO ARENA SIMULATION SOFTWARE BY Md. Asrafuzzaman IPE, SUST
  • 2. Objectives Improve shop floor efficiency and productivity by examining the existing WIP scenario and reducing WIP in the current manufacturing line.
  • 3. Background  We find that in our production floor WIP is a big problem and root cause of many other problems.  These problems are: • Maintaining 5S, • Quality issues, • On time delivery, • Line Efficiency, • Learning curves, • Line layout setup time
  • 4. Status of one day of Manufacturing flow Like at statistics at 16-6-2015 • Total cut pieces at = 34602 pieces WIP= 8564 pieces • Total input in line at =26038 Pieces WIP= 103 pieces • Total output line at = 25935 pieces WIP= 492 pieces • Total good pass quantity to finishing at =25443 pieces
  • 5. Some pictures of WIP in our production floor
  • 7. Steps of the study  First step: VSM a lean tool for visualizing the real scenario of the manufacturing flow  Second step: Identify the WIP and find the way of eliminating WIP  Third step: Simulate the present situation and proposed improvement by using Arena simulation software
  • 8. VSM A value stream involves all the steps, both value added and non value added, required to complete a product or service from beginning to end
  • 9. Overall steps involved in the study
  • 10. VALUE STREAM & IDENTIFYING WIP VALUE STREAM RELAXATION CUTTING SEWING FINISHING PROCESS PROCESS PROCESS PROCESS RAW MATERIALS FINISHED PRODUCT CUSTOMER WIP WIP WIP
  • 11. THE STEPS - VALUE STREAMS MAPPING Product Family Current State drawing Future State drawing Plan & Implementation Understanding how the shop floor currently operates. The foundation for the value state. Designing Lean Flow
  • 14. Measurable Metrics & Performance Metric Current Estimate Target from Future State Map Process Time 55.26 Min. 55.26 Min. Lead Time 8.390 Days 3.14 Days First Time Quality 80% 80%
  • 15. Data analysis and findings The data and information was collected through the observation of the production floor and some past record from the industrial engineering and planning department . Finally all data has been analyzed by using various types of tables, some tools such as cause effect diagram and 5S.
  • 16. Causes of WIP  Operator absenteeism  Machine breakdown  Improper line balancing in the beginning of the layout.  Raw materials supply problem  Quality issues
  • 17. Improvement proposal  Operator skill matrix operation base  Implementation of TPM ( Total Productive Maintenance)  Sewing line Layout analysis and layout proposal  Building supplier relationship, its a long term process and cost and quality related issues.  Our IE and Quality team is working on this, we will work on this issue in future.
  • 19. Implementation of TPM 1. There are 8 pillars of TPM 2. Already we are practising some of the pillars 3. Another 1. Autonomous maintenance 2. Quality maintenance 3. Planned maintenance we can implement
  • 20. Simulation analysis of Layout  By using arena  1. present situation layout  2. proposed layout result.
  • 21. Present line in the Arena Simulation
  • 23. Showing WIP by Arena
  • 24. Cost related to implementation of TPM  To implementation TPM need 3 or 4 man for every unit, but they have to work extra time or holyday when production will not running. So have to pay for extra time duty of the employee.  Total man power need = 12 to 16 • Already we have 13 man for maintenance purpose
  • 25. Cost related to Buy the Software  I have no exact purchase related idea.  Hear provided contact details of selling partner of Arena ( RockWell Automation) Selling partner China Beijing EnSky Contact Name: Zhang Qing Phone: +86-10-59009377 Email: info@ensky.com.cn Website: www.ensky.com.cn https://www.arenasimulation.com/purchasing-options/global-partners- contact-for-sales
  • 26. Benefits  Improve efficiency and productivity  On time delivery  Improve 5S  Reduce new style layout time
  • 27. Benefits  Our floor space rent per sq. Ft per month 15.07 Taka, so that if we reduce WIP then our every sq. Ft of space will be effectively used  Total CPM is 0.08$ so that if normal Layout time is 8 hour more than normal layout time ( 6 hour ) then extra loss of taka per month, 19353.6 $ ( extra cost for 1 lay out 537.6 $)
  • 28. Benefits  If we miss the shipment schedule then we have to pay for air shipment, which manufacturer have to pay for lost the shipment schedule.  Cost per kg for Europe: 3$ and 1.6$ for non Europe air shipment.  So per container 400 cartoon cost: • Europe : 24000$ ( per container) • Non Europe: 12800$
  • 29. Simulation software related For improving the running low efficient line performance usually do: • Layout change • More skill and efficient operator involve • Process improvement To do these we need around 3 hours to come out expected results. If the result will not come then we will loss for 4867.2$ for one month ( on basis of line status of 26- 5-2015, 13 line of that day ware not meet the expected result)
  • 30. Case study result provided by RockWell Automation Challenges:  Increase throughput  Decrease inventory  Decrease operating expenses and cycle time  Do a better job of capacity planning  Gain access to accurate, timely information Results after using Arena:  The model helped the manufacturer increase sales by more than $1 million  The simulation effort identified several options to optimize process performance  Cycle time was reduced from 5 weeks to 3 days  Overtime and operating expenses were lowered  On-time shipping performance increased 70% to 95% Sources: https://www.arenasimulation.com/resources/Production_simulation.pdf
  • 31. Recommendation  Technique such as zero defects, setup time reduction, and Poka-Yoke can be applied.  Arrange schedule training operator  To reduce absenteeism and to build up moral and trust: • Job enrichment, • Relationship improvement between employee and management, • Worker motivation.
  • 32. WIP running status and proposal Unit Line Style Name Target Input/Day Total Input Total Output WIP C urrent WIP Target Our WIP target Reduce pcs Reduce % UNA SAA Maja Crochet 1040 40165 37542 -2623 1560 1040 -520 35% SAB Vincent Top 1150 9383 6223 -3160 1725 1150 -575 35% SAC Vincent Top 1150 4517 1626 -2891 1725 1150 -575 35% SAD Vincent Top 1150 7583 3916 -3667 1725 1150 -575 35% SAE Majken dress-CWG 900 28054 25456 -2598 1620 900 -720 35% SAF Vincent Top 1150 6504 4829 -1675 1725 1150 -575 35% UNB SBA Majken dress-CWG 900 20113 18218 -1895 1620 900 -720 35% SBB Chung Top 1550 32449 30189 -2260 2325 1550 -775 35% SBC Vincent Top 1150 6468 3731 -2737 1725 1150 -575 35% SBD Vincent Top 1150 9269 6710 -2559 1725 1150 -575 35% SBE Chilli tunic 690 5882 4496 -1386 1035 690 -345 35% SBF Vincent Top 1150 9214 6651 -2563 1725 1150 -575 35% UNC SCA Vincent Top 1150 11438 7765 -3673 1725 1150 -575 35% SCB Vincent Top 1150 11920 10605 -1315 1725 1150 -575 35% SCC Chilli tunic 690 4885 3224 -1661 1035 690 -345 35% SCD Majken dress CWH 900 9213 7319 -1894 1620 900 -720 35% SCE Vincent Top 1150 7312 3620 -3692 1725 1150 -575 35% SCF Rosie S-2 1590 1480 45 -1435 2385 1590 -795 35% UND SDA Chung Top 1550 36133 34272 -1861 2325 1550 -775 35% SDB Maja Crochet 1040 31066 28910 -2156 1560 1040 -520 35% SDC Vincent Top 1150 11544 8384 -3160 1725 1150 -575 35% SDD Majken dress CWH 900 5653 4083 -1570 1620 900 -720 35% SDE Vincent Top 1150 9342 6970 -2372 1725 1150 -575 35% SDF Rosie S-2 1590 10698 9417 -1281 2385 1590 -795 35% G.Total 27140 330285 274201 -56084 41790 27140 -14650 35%
  • 33. Recommendation Con’t...  Improve supplier relationship to get the raw materials on time and standard quality.  Arrange the Arena Simulation commercial version software to save the dollar in relation with the interruption of the line due to experiment for process improvement
  • 34. Conclusion  VSM was implemented to find out the amount of wastes and WIP in cutting, sewing and finishing section; because the selected product had a long lead time and was unable to meet the expected production rate . Cause effect and was done to identify the reason of WIP, and proposing different solution.
  • 35. Conclusion Con’t...  As VSM can be drawn in relatively short time with almost no expenditure of money and as it can identify wastes with good accuracy, thus it’s very helpful for managers who are having difficulties with their low production rate, higher lead time and high production costs high WIP.  The simulation software helps to represent the real problems and analyse the total process and make scope to improve without interruption the production process, and after getting appropriate solution direct implement it in the manufacturing process.