Ingredients for success deployment of Earned-Value Management in projects
Culture shift is essential – every Project Team  must understand the working of EVM model Also, culture shift needs to be managed and supported well
Besides  accurate WBS, accurate planning, scheduling and proper costing of work packages(PV) at frequency points of measurement is the first step towards successful EVM implementation. Costing to include all the costs that will be incurred (Direct, Indirect, Fixed and Variable costs covering all resources including human resources )
It is absolutely essential to measure the work completed(earned back ie EV) at each task level and at the project level either in terms of % of work scheduled, or absolute $ value
To get a true picture of all Costs incurred (AC) between two frequency of measurement points, all costs – Direct, Indirect, Fixed and Variable incurred at every task level must be recorded .
Replanning the work at every change is critical. Use of automated tools will ease out this process
Frequency of measurement of PV, EV and AC is critical. It must be optimum suiting the duration of the project, neither low nor high
It is absolutely essential to record all project costs on a daily basis or at an appropriate frequency in line with the Frequency of measurement of EVM values
 

More Related Content

What's hot

Construction Cost Control
Construction Cost ControlConstruction Cost Control
Construction Cost Control
Sunayana Miglani
 
Seven Finance Activities Every Manufacturing Company Needs
Seven Finance Activities Every Manufacturing Company NeedsSeven Finance Activities Every Manufacturing Company Needs
Seven Finance Activities Every Manufacturing Company Needs
3C Software
 
P ex cost management-1
P ex cost management-1P ex cost management-1
P ex cost management-1
AHMED NADIM JILANI
 
Project Management 5 Cost Management
Project Management 5 Cost ManagementProject Management 5 Cost Management
Project Management 5 Cost Management
grmkslideshare
 
Cost analysis
Cost analysisCost analysis
Cost analysis
LahariTummala1
 
Value management presentation
Value management presentationValue management presentation
Value management presentation
Koh Chiun Liang
 
Project cost & control
Project cost & controlProject cost & control
Project cost & control
AMARAYYA
 
Cost
CostCost
Standard costing
Standard costingStandard costing
Standard costing
Studybytech
 
4. project cost management
4. project cost management4. project cost management
4. project cost management
Mohamed Salah Eldien Mohamed Ali
 
Pm0015 summer-2016
Pm0015 summer-2016Pm0015 summer-2016
Pm0015 summer-2016
smumbahelp
 
Cost management
Cost managementCost management
Cost management
Abhi Kalyan
 
factors affecting prodution
factors affecting produtionfactors affecting prodution
factors affecting prodution
aliyashakil
 
Odoo experience 2015 earned value management
Odoo experience 2015   earned value managementOdoo experience 2015   earned value management
Odoo experience 2015 earned value management
Eficent
 
Methods
MethodsMethods
Project cost control system in SAP
Project cost control system in SAPProject cost control system in SAP
Project cost control system in SAP
suxmario
 

What's hot (16)

Construction Cost Control
Construction Cost ControlConstruction Cost Control
Construction Cost Control
 
Seven Finance Activities Every Manufacturing Company Needs
Seven Finance Activities Every Manufacturing Company NeedsSeven Finance Activities Every Manufacturing Company Needs
Seven Finance Activities Every Manufacturing Company Needs
 
P ex cost management-1
P ex cost management-1P ex cost management-1
P ex cost management-1
 
Project Management 5 Cost Management
Project Management 5 Cost ManagementProject Management 5 Cost Management
Project Management 5 Cost Management
 
Cost analysis
Cost analysisCost analysis
Cost analysis
 
Value management presentation
Value management presentationValue management presentation
Value management presentation
 
Project cost & control
Project cost & controlProject cost & control
Project cost & control
 
Cost
CostCost
Cost
 
Standard costing
Standard costingStandard costing
Standard costing
 
4. project cost management
4. project cost management4. project cost management
4. project cost management
 
Pm0015 summer-2016
Pm0015 summer-2016Pm0015 summer-2016
Pm0015 summer-2016
 
Cost management
Cost managementCost management
Cost management
 
factors affecting prodution
factors affecting produtionfactors affecting prodution
factors affecting prodution
 
Odoo experience 2015 earned value management
Odoo experience 2015   earned value managementOdoo experience 2015   earned value management
Odoo experience 2015 earned value management
 
Methods
MethodsMethods
Methods
 
Project cost control system in SAP
Project cost control system in SAPProject cost control system in SAP
Project cost control system in SAP
 

Similar to Vijay Prasad’S Views On Earned Value Management In Project

Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
mohamed elashri
 
Constructiion cost estimating 2017
Constructiion cost estimating 2017Constructiion cost estimating 2017
Constructiion cost estimating 2017
Peter Cholakis
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
Hayat Denzi
 
iEVM (Integrated Earned Value Management) An approach for integrating quality...
iEVM (Integrated Earned Value Management) An approach for integrating quality...iEVM (Integrated Earned Value Management) An approach for integrating quality...
iEVM (Integrated Earned Value Management) An approach for integrating quality...
IRJET Journal
 
03costestimation-140930114902-phpapp01.pdf
03costestimation-140930114902-phpapp01.pdf03costestimation-140930114902-phpapp01.pdf
03costestimation-140930114902-phpapp01.pdf
zohir khellouf
 
Quality metrics in project management
Quality metrics in project managementQuality metrics in project management
Quality metrics in project management
selinasimpson1601
 
A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost management
Imran Jamil
 
T24 Temenos Earned Value Management & Project Planning Presentation
T24 Temenos Earned Value Management & Project Planning PresentationT24 Temenos Earned Value Management & Project Planning Presentation
T24 Temenos Earned Value Management & Project Planning Presentation
Michael Gowlett PMP, Prince 2 Practitioner
 
Introduction to Earned Value Management
Introduction to Earned Value ManagementIntroduction to Earned Value Management
Introduction to Earned Value Management
Unanet
 
7 cost PMBOK
7 cost PMBOK7 cost PMBOK
7 cost PMBOK
Waseem Siddique
 
2.07 cost management 1
2.07 cost management 12.07 cost management 1
2.07 cost management 1
reddvise
 
Agile Project Management Meets Earned Value Management
Agile Project Management Meets Earned Value ManagementAgile Project Management Meets Earned Value Management
Agile Project Management Meets Earned Value Management
Glen Alleman
 
Cost
CostCost
Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement
ignitetribes
 
Day 7 Project Cost Management .pdf
Day 7 Project Cost Management .pdfDay 7 Project Cost Management .pdf
Day 7 Project Cost Management .pdf
Madhusha15
 
Project mgt
Project mgtProject mgt
COST MANAGEMENT REPORT
COST MANAGEMENT REPORT COST MANAGEMENT REPORT
COST MANAGEMENT REPORT
Jo Balucanag - Bitonio
 
Webinar on PMS
Webinar on PMSWebinar on PMS
Webinar on PMS
vaibhavsharma_engg
 
projectcostcontrol-130625012804-phpapp02 (1)
projectcostcontrol-130625012804-phpapp02 (1)projectcostcontrol-130625012804-phpapp02 (1)
projectcostcontrol-130625012804-phpapp02 (1)
Nita Cristian
 
Updated Resume - Veena Kumar
Updated Resume - Veena KumarUpdated Resume - Veena Kumar
Updated Resume - Veena Kumar
Veena Sampath Kumar
 

Similar to Vijay Prasad’S Views On Earned Value Management In Project (20)

Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Constructiion cost estimating 2017
Constructiion cost estimating 2017Constructiion cost estimating 2017
Constructiion cost estimating 2017
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
iEVM (Integrated Earned Value Management) An approach for integrating quality...
iEVM (Integrated Earned Value Management) An approach for integrating quality...iEVM (Integrated Earned Value Management) An approach for integrating quality...
iEVM (Integrated Earned Value Management) An approach for integrating quality...
 
03costestimation-140930114902-phpapp01.pdf
03costestimation-140930114902-phpapp01.pdf03costestimation-140930114902-phpapp01.pdf
03costestimation-140930114902-phpapp01.pdf
 
Quality metrics in project management
Quality metrics in project managementQuality metrics in project management
Quality metrics in project management
 
A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost management
 
T24 Temenos Earned Value Management & Project Planning Presentation
T24 Temenos Earned Value Management & Project Planning PresentationT24 Temenos Earned Value Management & Project Planning Presentation
T24 Temenos Earned Value Management & Project Planning Presentation
 
Introduction to Earned Value Management
Introduction to Earned Value ManagementIntroduction to Earned Value Management
Introduction to Earned Value Management
 
7 cost PMBOK
7 cost PMBOK7 cost PMBOK
7 cost PMBOK
 
2.07 cost management 1
2.07 cost management 12.07 cost management 1
2.07 cost management 1
 
Agile Project Management Meets Earned Value Management
Agile Project Management Meets Earned Value ManagementAgile Project Management Meets Earned Value Management
Agile Project Management Meets Earned Value Management
 
Cost
CostCost
Cost
 
Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement
 
Day 7 Project Cost Management .pdf
Day 7 Project Cost Management .pdfDay 7 Project Cost Management .pdf
Day 7 Project Cost Management .pdf
 
Project mgt
Project mgtProject mgt
Project mgt
 
COST MANAGEMENT REPORT
COST MANAGEMENT REPORT COST MANAGEMENT REPORT
COST MANAGEMENT REPORT
 
Webinar on PMS
Webinar on PMSWebinar on PMS
Webinar on PMS
 
projectcostcontrol-130625012804-phpapp02 (1)
projectcostcontrol-130625012804-phpapp02 (1)projectcostcontrol-130625012804-phpapp02 (1)
projectcostcontrol-130625012804-phpapp02 (1)
 
Updated Resume - Veena Kumar
Updated Resume - Veena KumarUpdated Resume - Veena Kumar
Updated Resume - Veena Kumar
 

Recently uploaded

Fueling AI with Great Data with Airbyte Webinar
Fueling AI with Great Data with Airbyte WebinarFueling AI with Great Data with Airbyte Webinar
Fueling AI with Great Data with Airbyte Webinar
Zilliz
 
Cosa hanno in comune un mattoncino Lego e la backdoor XZ?
Cosa hanno in comune un mattoncino Lego e la backdoor XZ?Cosa hanno in comune un mattoncino Lego e la backdoor XZ?
Cosa hanno in comune un mattoncino Lego e la backdoor XZ?
Speck&Tech
 
GraphRAG for Life Science to increase LLM accuracy
GraphRAG for Life Science to increase LLM accuracyGraphRAG for Life Science to increase LLM accuracy
GraphRAG for Life Science to increase LLM accuracy
Tomaz Bratanic
 
Let's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with Slack
Let's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with SlackLet's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with Slack
Let's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with Slack
shyamraj55
 
Presentation of the OECD Artificial Intelligence Review of Germany
Presentation of the OECD Artificial Intelligence Review of GermanyPresentation of the OECD Artificial Intelligence Review of Germany
Presentation of the OECD Artificial Intelligence Review of Germany
innovationoecd
 
National Security Agency - NSA mobile device best practices
National Security Agency - NSA mobile device best practicesNational Security Agency - NSA mobile device best practices
National Security Agency - NSA mobile device best practices
Quotidiano Piemontese
 
Choosing The Best AWS Service For Your Website + API.pptx
Choosing The Best AWS Service For Your Website + API.pptxChoosing The Best AWS Service For Your Website + API.pptx
Choosing The Best AWS Service For Your Website + API.pptx
Brandon Minnick, MBA
 
Serial Arm Control in Real Time Presentation
Serial Arm Control in Real Time PresentationSerial Arm Control in Real Time Presentation
Serial Arm Control in Real Time Presentation
tolgahangng
 
Columbus Data & Analytics Wednesdays - June 2024
Columbus Data & Analytics Wednesdays - June 2024Columbus Data & Analytics Wednesdays - June 2024
Columbus Data & Analytics Wednesdays - June 2024
Jason Packer
 
みなさんこんにちはこれ何文字まで入るの?40文字以下不可とか本当に意味わからないけどこれ限界文字数書いてないからマジでやばい文字数いけるんじゃないの?えこ...
みなさんこんにちはこれ何文字まで入るの?40文字以下不可とか本当に意味わからないけどこれ限界文字数書いてないからマジでやばい文字数いけるんじゃないの?えこ...みなさんこんにちはこれ何文字まで入るの?40文字以下不可とか本当に意味わからないけどこれ限界文字数書いてないからマジでやばい文字数いけるんじゃないの?えこ...
みなさんこんにちはこれ何文字まで入るの?40文字以下不可とか本当に意味わからないけどこれ限界文字数書いてないからマジでやばい文字数いけるんじゃないの?えこ...
名前 です男
 
June Patch Tuesday
June Patch TuesdayJune Patch Tuesday
June Patch Tuesday
Ivanti
 
Salesforce Integration for Bonterra Impact Management (fka Social Solutions A...
Salesforce Integration for Bonterra Impact Management (fka Social Solutions A...Salesforce Integration for Bonterra Impact Management (fka Social Solutions A...
Salesforce Integration for Bonterra Impact Management (fka Social Solutions A...
Jeffrey Haguewood
 
Programming Foundation Models with DSPy - Meetup Slides
Programming Foundation Models with DSPy - Meetup SlidesProgramming Foundation Models with DSPy - Meetup Slides
Programming Foundation Models with DSPy - Meetup Slides
Zilliz
 
HCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAU
HCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAUHCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAU
HCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAU
panagenda
 
Generating privacy-protected synthetic data using Secludy and Milvus
Generating privacy-protected synthetic data using Secludy and MilvusGenerating privacy-protected synthetic data using Secludy and Milvus
Generating privacy-protected synthetic data using Secludy and Milvus
Zilliz
 
Taking AI to the Next Level in Manufacturing.pdf
Taking AI to the Next Level in Manufacturing.pdfTaking AI to the Next Level in Manufacturing.pdf
Taking AI to the Next Level in Manufacturing.pdf
ssuserfac0301
 
TrustArc Webinar - 2024 Global Privacy Survey
TrustArc Webinar - 2024 Global Privacy SurveyTrustArc Webinar - 2024 Global Privacy Survey
TrustArc Webinar - 2024 Global Privacy Survey
TrustArc
 
Nordic Marketo Engage User Group_June 13_ 2024.pptx
Nordic Marketo Engage User Group_June 13_ 2024.pptxNordic Marketo Engage User Group_June 13_ 2024.pptx
Nordic Marketo Engage User Group_June 13_ 2024.pptx
MichaelKnudsen27
 
How to Interpret Trends in the Kalyan Rajdhani Mix Chart.pdf
How to Interpret Trends in the Kalyan Rajdhani Mix Chart.pdfHow to Interpret Trends in the Kalyan Rajdhani Mix Chart.pdf
How to Interpret Trends in the Kalyan Rajdhani Mix Chart.pdf
Chart Kalyan
 
AI 101: An Introduction to the Basics and Impact of Artificial Intelligence
AI 101: An Introduction to the Basics and Impact of Artificial IntelligenceAI 101: An Introduction to the Basics and Impact of Artificial Intelligence
AI 101: An Introduction to the Basics and Impact of Artificial Intelligence
IndexBug
 

Recently uploaded (20)

Fueling AI with Great Data with Airbyte Webinar
Fueling AI with Great Data with Airbyte WebinarFueling AI with Great Data with Airbyte Webinar
Fueling AI with Great Data with Airbyte Webinar
 
Cosa hanno in comune un mattoncino Lego e la backdoor XZ?
Cosa hanno in comune un mattoncino Lego e la backdoor XZ?Cosa hanno in comune un mattoncino Lego e la backdoor XZ?
Cosa hanno in comune un mattoncino Lego e la backdoor XZ?
 
GraphRAG for Life Science to increase LLM accuracy
GraphRAG for Life Science to increase LLM accuracyGraphRAG for Life Science to increase LLM accuracy
GraphRAG for Life Science to increase LLM accuracy
 
Let's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with Slack
Let's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with SlackLet's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with Slack
Let's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with Slack
 
Presentation of the OECD Artificial Intelligence Review of Germany
Presentation of the OECD Artificial Intelligence Review of GermanyPresentation of the OECD Artificial Intelligence Review of Germany
Presentation of the OECD Artificial Intelligence Review of Germany
 
National Security Agency - NSA mobile device best practices
National Security Agency - NSA mobile device best practicesNational Security Agency - NSA mobile device best practices
National Security Agency - NSA mobile device best practices
 
Choosing The Best AWS Service For Your Website + API.pptx
Choosing The Best AWS Service For Your Website + API.pptxChoosing The Best AWS Service For Your Website + API.pptx
Choosing The Best AWS Service For Your Website + API.pptx
 
Serial Arm Control in Real Time Presentation
Serial Arm Control in Real Time PresentationSerial Arm Control in Real Time Presentation
Serial Arm Control in Real Time Presentation
 
Columbus Data & Analytics Wednesdays - June 2024
Columbus Data & Analytics Wednesdays - June 2024Columbus Data & Analytics Wednesdays - June 2024
Columbus Data & Analytics Wednesdays - June 2024
 
みなさんこんにちはこれ何文字まで入るの?40文字以下不可とか本当に意味わからないけどこれ限界文字数書いてないからマジでやばい文字数いけるんじゃないの?えこ...
みなさんこんにちはこれ何文字まで入るの?40文字以下不可とか本当に意味わからないけどこれ限界文字数書いてないからマジでやばい文字数いけるんじゃないの?えこ...みなさんこんにちはこれ何文字まで入るの?40文字以下不可とか本当に意味わからないけどこれ限界文字数書いてないからマジでやばい文字数いけるんじゃないの?えこ...
みなさんこんにちはこれ何文字まで入るの?40文字以下不可とか本当に意味わからないけどこれ限界文字数書いてないからマジでやばい文字数いけるんじゃないの?えこ...
 
June Patch Tuesday
June Patch TuesdayJune Patch Tuesday
June Patch Tuesday
 
Salesforce Integration for Bonterra Impact Management (fka Social Solutions A...
Salesforce Integration for Bonterra Impact Management (fka Social Solutions A...Salesforce Integration for Bonterra Impact Management (fka Social Solutions A...
Salesforce Integration for Bonterra Impact Management (fka Social Solutions A...
 
Programming Foundation Models with DSPy - Meetup Slides
Programming Foundation Models with DSPy - Meetup SlidesProgramming Foundation Models with DSPy - Meetup Slides
Programming Foundation Models with DSPy - Meetup Slides
 
HCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAU
HCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAUHCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAU
HCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAU
 
Generating privacy-protected synthetic data using Secludy and Milvus
Generating privacy-protected synthetic data using Secludy and MilvusGenerating privacy-protected synthetic data using Secludy and Milvus
Generating privacy-protected synthetic data using Secludy and Milvus
 
Taking AI to the Next Level in Manufacturing.pdf
Taking AI to the Next Level in Manufacturing.pdfTaking AI to the Next Level in Manufacturing.pdf
Taking AI to the Next Level in Manufacturing.pdf
 
TrustArc Webinar - 2024 Global Privacy Survey
TrustArc Webinar - 2024 Global Privacy SurveyTrustArc Webinar - 2024 Global Privacy Survey
TrustArc Webinar - 2024 Global Privacy Survey
 
Nordic Marketo Engage User Group_June 13_ 2024.pptx
Nordic Marketo Engage User Group_June 13_ 2024.pptxNordic Marketo Engage User Group_June 13_ 2024.pptx
Nordic Marketo Engage User Group_June 13_ 2024.pptx
 
How to Interpret Trends in the Kalyan Rajdhani Mix Chart.pdf
How to Interpret Trends in the Kalyan Rajdhani Mix Chart.pdfHow to Interpret Trends in the Kalyan Rajdhani Mix Chart.pdf
How to Interpret Trends in the Kalyan Rajdhani Mix Chart.pdf
 
AI 101: An Introduction to the Basics and Impact of Artificial Intelligence
AI 101: An Introduction to the Basics and Impact of Artificial IntelligenceAI 101: An Introduction to the Basics and Impact of Artificial Intelligence
AI 101: An Introduction to the Basics and Impact of Artificial Intelligence
 

Vijay Prasad’S Views On Earned Value Management In Project

  • 1. Ingredients for success deployment of Earned-Value Management in projects
  • 2. Culture shift is essential – every Project Team must understand the working of EVM model Also, culture shift needs to be managed and supported well
  • 3. Besides accurate WBS, accurate planning, scheduling and proper costing of work packages(PV) at frequency points of measurement is the first step towards successful EVM implementation. Costing to include all the costs that will be incurred (Direct, Indirect, Fixed and Variable costs covering all resources including human resources )
  • 4. It is absolutely essential to measure the work completed(earned back ie EV) at each task level and at the project level either in terms of % of work scheduled, or absolute $ value
  • 5. To get a true picture of all Costs incurred (AC) between two frequency of measurement points, all costs – Direct, Indirect, Fixed and Variable incurred at every task level must be recorded .
  • 6. Replanning the work at every change is critical. Use of automated tools will ease out this process
  • 7. Frequency of measurement of PV, EV and AC is critical. It must be optimum suiting the duration of the project, neither low nor high
  • 8. It is absolutely essential to record all project costs on a daily basis or at an appropriate frequency in line with the Frequency of measurement of EVM values
  • 9.