VERTEX Presentation at 2016 AACE Northeast Total Cost Management Symposium - Key Challenges in Demonstrating Loss of Productivity Claims Based on Specialty Industry Studies
A presentation on project formulation submitted at the college level. Data is gathered from different websites including SlideShare itself and book on Entrepreneurship Development Program by S.P.Sukhija and Sangam Kapoor.
A presentation on project formulation submitted at the college level. Data is gathered from different websites including SlideShare itself and book on Entrepreneurship Development Program by S.P.Sukhija and Sangam Kapoor.
Over the years, some of our customers have selected Creative Engineers, Inc. to perform a feasibility analysis for their project to help make good investment decisions. The format shown below is a well-rounded view of the problem that can be used for such an analysis.
Over the years, some of our customers have selected Creative Engineers, Inc. to perform a feasibility analysis for their project to help make good investment decisions. The format shown below is a well-rounded view of the problem that can be used for such an analysis.
Six Sigma is
the powerpoint presentaion that i make during my 3rd yr. The format of
this presentation is truly professional. You can adopt this format for
your future presentations. You too can modify these. Alright.
So just keep going.
Live in flow
~rise and shine~
Episode 27 : Project Management Costs
Cost Method
1. If there is lack of information regarding the existing plant, investment cost can be estimated by using cost factor. It requires the existence of a process concept and the rough layout of the main equipment in order to determine the cost of the main processing unit.
Operating Cost
Consists of (a) Cost of raw material
Utility cost
Labour cost
Maintenance cost
Utility Cost
1. It is quantity based and consisted of electric power, steam and coolant consumption, heating media such as coal and other energy sources like hydrogen.
Service innovation for energy services: how to get from an idea to a service ...Heiko Gebauer
The presentation describes the service innovation process. It describes how to get from a service idea to successful service innovations. We highlight innovation methods for facilitating the creativity and for describing the actual service.
Episode 27 : Project Management Costs
Cost Method
1. If there is lack of information regarding the existing plant, investment cost can be estimated by using cost factor. It requires the existence of a process concept and the rough layout of the main equipment in order to determine the cost of the main processing unit.
Operating Cost
Consists of (a) Cost of raw material
Utility cost
Labour cost
Maintenance cost
Utility Cost
1. It is quantity based and consisted of electric power, steam and coolant consumption, heating media such as coal and other energy sources like hydrogen.
SAJJAD KHUDHUR ABBAS
Chemical Engineering , Al-Muthanna University, Iraq
Oil & Gas Safety and Health Professional – OSHACADEMY
Trainer of Trainers (TOT) - Canadian Center of Human
Development
Innovation pathway for infrastructure solutionsChris Jurewicz
The intent was to provide a high-level pathway for innovation which can be adapted for more specific purposes in different areas of civil engineering. The pathway applies equally to innovation in engineering processes, products and in design.
This presentation is a living document which will be updated as we learn more and gain experience. The main sources for this knowledge were a literature review and practitioner workshops, backed by experience on several projects.
Punjab technical University - scheme and syllabus of Masters in Business Administration (MBA) Batch 2012 onwards, course code MBA 202, production & operation Management. UNIT 1. ch. 2 facility location, ch. 3 production Design and development, ch 4 process selection- Job, project, batch mass & process types of production system.
[Note: This is a partial preview. To download this presentation, visit:
https://www.oeconsulting.com.sg/training-presentations]
Benchmarking is the process of continually searching for the best methods, practices and processes, and either adopting or adapting their good features and implementing them to become the “best of the best.” To become the best-in-class, organizations need to implement the right process to get there.
Based on the world renowned Xerox Benchmarking Process model pioneered by Robert C. Camp, this presentation deck covers the benefits of benchmarking, various types of benchmarking, identifying what to benchmark, and provides a detailed step by step guidance on how to systematically carry out a benchmarking project. It also includes useful tips on benchmarking, benchmarking etiquettes and the critical success factors.
LEARNING OBJECTIVES
1. Gain a broad understanding of the key concepts of benchmarking.
2. Learn how to identify, assess and implement various types of benchmarking projects to meet the your organization’s goals based on the Xerox Benchmarking model.
3. Gain awareness of the code of conduct for benchmarking and make preparations to get the most out of a site visit.
4. Define the critical success factors in benchmarking implementation.
5. Kick-start benchmarking projects that are aligned to your company’s strategic goals.
CONTENTS
Introduction to Benchmarking
The Xerox Benchmarking Process
Step 1: What to benchmark?
Step 2: Whom to benchmark?
Step 3: Data collection
Step 4: Determine current performance “gap”
Step 5: Project future performance levels
Step 6: Communicate findings and gain acceptance
Step 7: Establish goals
Step 8: Develop action plans
Step 9: Implement actions and monitor progress
Step 10: Re-calibrate benchmarks
Benchmarking Roles and Responsibilities
Benchmarking Inspection Checklist (Toll-gate Review)
Benchmarking Etiquette
Benchmarking Site Visit
Benchmarking Pitfalls & Success
To download this complete presentation, please visit: http://www.oeconsulting.com.sg
Construction of Manufactured Homes - Understanding the Hazards & RisksLisa Dehner
VERTEX's Dr. Seyyed Amin Terouhid, Senior PM, co-authored "Construction of Manufactured Homes - Understanding the Hazards & Risks", which was published with American Society of Safety Engineers (www.asse.org)
VERTEX's Bill McConnell, JD, PE, and Dr. Ibrahim Odeh, MBA, co-author 'Lifecycles of Large AEC Companies'. The article is published in Fall 2016 ABA Committee News.
Sharing Well with Others - New Office Construction in Uptown Dallas. Tenant Improvement Services are provided by The Vertex Companies, Inc. for Regus Corporation
Bill McConnell's State of the Surety Industry in 2016Lisa Dehner
VERTEX’s Bill McConnell, CEO, will speak as a guest lecturer at Construction Management program, sponsored by Columbia and Stanford University. The lecture, taking place on August 16th, 2016, is on the topic of Surety Bonds.
Past, Present, and Future Analysis of the Architectural & Engineering Design ...Lisa Dehner
This report provides a macro view of the architectural and engineering design industry in the U.S. in order to understand strategies employed by both successful and unsuccessful firms over the past 50 years. It also evaluates technological trends that design firms must embrace in order to maintain a competitive edge moving forward into the future.
Legionnaires' Disease - How to Comply with Rapidly Developing Cooling Tower R...Lisa Dehner
The slide presentation reviews some facts about Legionnaires’ disease and how VERTEX can help you comply with rapidly developing cooling tower regulations.
Mr. William McConnell evaluates the 2016 economic conditions, concluding that real growth is at a stall despite full employment. This white paper is part of a three part series. William McConnell will publish a white paper focused on the state of the construction industry next month, followed by the state of the surety industry in July, 2016.
VERTEX, hace una extensiva invitación a todos los interesados en la compra, construcción o renta de Naves Industriales, gestoría y temas afines, a la Expo Naves y Parques Industriales, en la cual VERTEX participara del 12 al 14 de Abril en el WTC de la Ciudad de México.
Car Accident Injury Do I Have a Case....Knowyourright
Every year, thousands of Minnesotans are injured in car accidents. These injuries can be severe – even life-changing. Under Minnesota law, you can pursue compensation through a personal injury lawsuit.
In 2020, the Ministry of Home Affairs established a committee led by Prof. (Dr.) Ranbir Singh, former Vice Chancellor of National Law University (NLU), Delhi. This committee was tasked with reviewing the three codes of criminal law. The primary objective of the committee was to propose comprehensive reforms to the country’s criminal laws in a manner that is both principled and effective.
The committee’s focus was on ensuring the safety and security of individuals, communities, and the nation as a whole. Throughout its deliberations, the committee aimed to uphold constitutional values such as justice, dignity, and the intrinsic value of each individual. Their goal was to recommend amendments to the criminal laws that align with these values and priorities.
Subsequently, in February, the committee successfully submitted its recommendations regarding amendments to the criminal law. These recommendations are intended to serve as a foundation for enhancing the current legal framework, promoting safety and security, and upholding the constitutional principles of justice, dignity, and the inherent worth of every individual.
WINDING UP of COMPANY, Modes of DissolutionKHURRAMWALI
Winding up, also known as liquidation, refers to the legal and financial process of dissolving a company. It involves ceasing operations, selling assets, settling debts, and ultimately removing the company from the official business registry.
Here's a breakdown of the key aspects of winding up:
Reasons for Winding Up:
Insolvency: This is the most common reason, where the company cannot pay its debts. Creditors may initiate a compulsory winding up to recover their dues.
Voluntary Closure: The owners may decide to close the company due to reasons like reaching business goals, facing losses, or merging with another company.
Deadlock: If shareholders or directors cannot agree on how to run the company, a court may order a winding up.
Types of Winding Up:
Voluntary Winding Up: This is initiated by the company's shareholders through a resolution passed by a majority vote. There are two main types:
Members' Voluntary Winding Up: The company is solvent (has enough assets to pay off its debts) and shareholders will receive any remaining assets after debts are settled.
Creditors' Voluntary Winding Up: The company is insolvent and creditors will be prioritized in receiving payment from the sale of assets.
Compulsory Winding Up: This is initiated by a court order, typically at the request of creditors, government agencies, or even by the company itself if it's insolvent.
Process of Winding Up:
Appointment of Liquidator: A qualified professional is appointed to oversee the winding-up process. They are responsible for selling assets, paying off debts, and distributing any remaining funds.
Cease Trading: The company stops its regular business operations.
Notification of Creditors: Creditors are informed about the winding up and invited to submit their claims.
Sale of Assets: The company's assets are sold to generate cash to pay off creditors.
Payment of Debts: Creditors are paid according to a set order of priority, with secured creditors receiving payment before unsecured creditors.
Distribution to Shareholders: If there are any remaining funds after all debts are settled, they are distributed to shareholders according to their ownership stake.
Dissolution: Once all claims are settled and distributions made, the company is officially dissolved and removed from the business register.
Impact of Winding Up:
Employees: Employees will likely lose their jobs during the winding-up process.
Creditors: Creditors may not recover their debts in full, especially if the company is insolvent.
Shareholders: Shareholders may not receive any payout if the company's debts exceed its assets.
Winding up is a complex legal and financial process that can have significant consequences for all parties involved. It's important to seek professional legal and financial advice when considering winding up a company.
Military Commissions details LtCol Thomas Jasper as Detailed Defense CounselThomas (Tom) Jasper
Military Commissions Trial Judiciary, Guantanamo Bay, Cuba. Notice of the Chief Defense Counsel's detailing of LtCol Thomas F. Jasper, Jr. USMC, as Detailed Defense Counsel for Abd Al Hadi Al-Iraqi on 6 August 2014 in the case of United States v. Hadi al Iraqi (10026)
3. Goal
Identify challenges when using Specialty Industry
Studies to calculate productivity loss and how to
address them
4. Agenda
• Overview of productivity loss and
quantification methods
• What is a Specialty Industry Study and when
should you use them?
• Challenges when using these studies and how
to overcome them
9. Estimating Lost Productivity
• AACE 25R-03 [1]
– Option A: Project Specific Studies
– Option B: Project Comparison Studies
– Option C: Specialty Industry Studies
– Option D: General Industry Studies
– Option E: Cost Basis
10. Option A – Project Specific Studies
• Project Specific
• Require contemporaneous documentation
11. Option A – Project Specific Studies
• Measured Mile
• EV Analysis
• Work Sampling Method
• Craftsmen Questionnaire Sampling Method
12. Option B – Project Comparison Studies
• Comparable Work Study
• Comparable Project Study
13. Option C – Specialty Industry Studies
• Studies of specific types of problems
– Acceleration
– Changes/Cumulative Impact
– Learning Curve
– Overtime
– Weather
14. Specialty Industry Studies –
Key Challenges
• Entitlement
1. Liability
2. Causation
• Justification of Method
• Applicability
• Reasonableness of Results
• Other Considerations
15. Liability
- First step in demonstrating entitlement
- Usually established by a contract provision or
the accused party’s breach of contract
- Key is to use the contract language to your
advantage
16. Causation
1. Demonstrate the accused party caused the
loss
2. Provide evidence that claimant did not
contribute to the loss
17. Keys to Entitlement
- Adherence to notice requirements
- Impact was unforeseeable
- Impact was beyond claimant’s control
- Claimant is not responsible
- Damages are recoverable under the contract
- Disruption resulted in changed performance or
increased cost
18. Justify Calculation Method
- Why couldn’t you use one of the more
preferred methods?
- Opposition may attempt to use a superior
method to demonstrate claimant’s damages
are overvalued
19. Applicability
- The data used in an industry study applies to a
very specific project environment
- Critical to document the surrounding circumstances
of the claim situation
- When choosing a study ask yourself:
- Why/Where/When was the study performed?
- How closely does the study tie to my scenario?
- In what way does the study differ from the case at
hand?[2]
21. Applicability - Example
- Leonard Study is only applicable to projects
experiencing greater than 10-15% change
orders (measured by labor hours) and only
until a certain point. [3]
22. Credibility
• Is the study of objective?
• Does it provide representative value?
• Does the study use recent data?
• Are intervening variables considered?
24. Credibility
• Did not rely on original data
– Relied on flawed data from an earlier study by The
Business Roundtable
• The nature of the work or the trades involved was
not disclosed in the original study
30. References
1. Recommended Practice No. 25R-03 “Estimating Lost Labor Productivity in
Construction Claims”, AACE International, 2004
2. Nuhu Braimah, Issaka Ndekugri & Rod Gameson, A Review of Industry Standards
and Publications/Charts for Adjusting Productivity Losses in Construction
Contracts, Presentation at the 22nd Annual ARCOM Conference, Birmingham, UK
at 49, 54 (September 2006).
3. Leonard, Charles A., The Effects of Change Orders on Productivity, Concordia
University, Montreal, Quebec, April 14, 1987.
4. Mosely, W. Alexander, Challenges to Admission of – Or Belief In – Lost
Productivity Claims Based on Industry Studies, American Bar Association, 2013.
5. Brunies, R. and Emir, Z. (2001) Calculating Loss of Productivity Due to Overtime
Using Published Charts – Facts or Fiction. The Revay Report, Vol. 20, No. 3.
6. Mechanical Contractors Association of America, Change Orders Productivity
Overtime – A Primer for the Construction Industry (MCAA 2012).
Editor's Notes
This slide will cover what we will be covering in the entire presentation:
BRIEF overview of what productivity is and some common factors that negatively impact productivity
Go over the various methods used to calculate productivity loss
We will focus on Specialty Industry Studies
When are they appropriate?
What are some key considerations when using them?
After identifying the major challenges one faces when using Specialty Industry Studies we will discuss methods to overcome these challenges
I am sure most of you are familiar with the concept of Productivity
Productivity is basically a measure of how much you get out for how much you put in
Output is generally measured in physical units
Input is usually measured in labor hours
EXAMPLE
Lets say a project requires us to lay 1000 ft of pipe and I estimate my company can do this in 50 labor hours.
Output = 1000 ft
Input = 50 labor hours
Productivity = (1000 ft / 50 labor hours) = 20 ft per labor hour
Now lets transform the equation a bit
We all remember y = mx +b from algebra
We have m = y/x
Y = mx
Slope is your productivity
Our output is constant (unless there are design changes)
If our Productivity goes down, we need to increase our input to achieve the output required by the Project.
More input = more cost $$$$$
Steeper slope = greater productivity
What are some factors that cause a loss in productivity?
There are MANY different factors that can affect productivity – some of the more prominent ones are:
Acceleration
Weather
Scope Changes
Trade Stacking
Overtime
There is no consensus in the industry as to the absolute best way to calculate lost productivity
However, AACE 25R-03 provides a list of the various calculation methods and lists them in order of preference
Option A>Option B>Option C and so forth.
Methods to calculate productivity loss
Project Specific Studies (Tier 1)
Measured Mile - Gold Standard (1A)
Earned Value Analysis (1B)
Work Sampling Method (1C)
Craftsmen Questionnaire Sampling Method (1D)
Project Comparison Studies (Tier 2)
Comparable Work Study (2A)
Comparable Project Study (2B)
Specialty Industry Studies (Tier 3)
Project Specific Studies are (as the name says) project specific
Supported with documentation directly related to the dispute
To use project specific studies you need reliable contemporaneous project documentation.
Using Project Specific Studies is the preferred way to quantify loss of productivity
The gold standard is the measured mile
But this may not be available for a number of reasons
ASK AUDIENCE: Has anyone here every seen a productivity claim using work sampling methods?
Comparable Work Studies compare two similar activities on the project
Require similar work on the same project
EXAMPLE – electrical conduit and sprinkler piping
Comparable Project Studies require similar projects
If the project is very unique this option is not usually available.
If there is insufficient contemporaneous project documentation to use the Project Specific or Project Comparison Study methodologies, recommended practice is to perform your productivity loss estimate using specialty industry studies
Studies of specific types of problems that are based on some number of actual construction projects
The first step in any productivity claim (or any claim for that matter) is to establish liability
If you cannot identify a contract provision to help establish liability then your claim may be in trouble.
Causation is a little more difficult
Two equally important parts:
- Proof that the accused party caused the loss
- Proof that claimant did not contribute to the loss.
If the claimant is partially responsible for the loss, it is crucial that the claim address apportionment of damages.
Claimant should be able to apportion liability based on findings of causation.
****Discuss apportionment
As with all productivity loss calculation methods, the claimant will have to establish entitlement and causation of the alleged productivity impact.
Not unique to specialty industry studies
No point in reviewing damage calculations if claimant cannot establish it is entitle to recover anything.
To demonstrate entitlement a claimant must document the following:
Notice Requirements
Key is to familiarize your project management team and field team with the contract requirements early on in the project.
This ensures that when a dispute arises, the team is aware to the notice requirements.
Key is to ensure your narrative adequately addresses each of the items listed on the slide. *****
Given the preference for the measure mile or more desirable quantification methods, it is good practice to address why a certain method was chosen
Why couldn’t you use Project Specific or Project Comparison Studies?
In the case of specialty industry studies, a claimant should address why the Project Specific or Project Comparison Studies could not be used.
Maybe there was no impacted period or there wasn’t adequate contemporaneous documentation to use one of the preferred methods.
The Opposition may try to discredit your findings by either:
noting you didn’t follow recommended practice by using a preferred (and demonstrably available) method
Performing its own analysis using a preferred method which yields a small damage value.
Demonstrating the study used to calculate the productivity loss is appropriate for the applied situation is critical
Key is to make sure your claim narrative outlines why you feel the study used in your quantification is applicable to the given disruption
The Defendant will likely try to discredit the study the claim relies on to prepare its estimate
To document that the utilized study is credible the claimant should address the following;
Objectivity
The studies are usually developed by parties with vested interests and without the tempering perspective of the other project party
Representative value
Is there a strong correlation between what is measured in the study and the nature of the claim?
Addressed in applicability section
Timeliness
If the data used in the study is very old it may be unreliable.
Intervening variables
If the study ignores experience, project size or scope then it may not be credible to the applied situation
BLS 1940’s study
Based on the manufacturing industry; not construction
Highly repetitive work and required little decision making
MCAA used this data when it issued bulletin 18A in 1968 which is also listed in Appendix D
***Request copyright *****
The BRT data was from a single project
Also, The USACE Modification Impact Evaluation Guide is also listed in Appendix D; however it was rescinded in 1996.
Because the studies can be extremely specific, it is important to substantiate your calculation every way possible. The best way is to compare your calculations using another quantification method.
MCAA recommends a claim prepare a modified total cost method analysis of productivity loss as a sanity check on the estimate loss resulting from using the MCAA factors.
Source:
Change Orders Productivity Overtime – A Primer for the Construction Industry (MCAA 2012) Id. At 99.
Lets look at an example…. NEXT SLIDE
Fairly simple concept but lets run through an example:
EXAMPLE:
Specialty Industry Study $500K
Modified Total Cost $100K
BAD
Modified Total Cost $525K
GOOD
No matter the outcome, you should check your results with another method of quantification and analyze the results.
Contemporaneous Documentation
The more the better.
If you can provide detailed project records for the period during which the disruption occurs then your job gets much easier
Also improves the likelihood you will be able to use one of the preferred quantification methods
Expert Testimony
Will probably be required if dispute is escalated
As with all productivity loss calculation methods, the absolute top priority is that the claimant demonstrates entitlement
Justify method of quantification
Demonstrate the study used is applicable to the given situation
Demonstrates representative value
Establish that the study is credible
Show the resultant calculates are reasonable by comparing them with a less-preferred method