SlideShare a Scribd company logo
Key Challenges in Demonstrating Loss
of Productivity Claims Based on
Specialty Industry Studies
Andrew Sargent, Amin Terouhid
Andrew Sargent, EIT Amin Terouhid, PhD, PMP
Goal
Identify challenges when using Specialty Industry
Studies to calculate productivity loss and how to
address them
Agenda
• Overview of productivity loss and
quantification methods
• What is a Specialty Industry Study and when
should you use them?
• Challenges when using these studies and how
to overcome them
What is Productivity?
𝑃𝑟𝑜𝑑𝑢𝑐𝑡𝑖𝑣𝑖𝑡𝑦 =
𝑂𝑢𝑡𝑝𝑢𝑡
𝐼𝑛𝑝𝑢𝑡
𝑂𝑢𝑡𝑝𝑢𝑡 = 1000 𝐿𝐹
𝐼𝑛𝑝𝑢𝑡 = 50 ℎ𝑟𝑠
𝑃𝑟𝑜𝑑𝑢𝑐𝑡𝑖𝑣𝑖𝑡𝑦 =
𝑂𝑢𝑡𝑝𝑢𝑡
𝐼𝑛𝑝𝑢𝑡
=
1000𝐿𝐹
50ℎ𝑟𝑠
= 20 𝐿𝐹 𝑝𝑒𝑟 ℎ𝑜𝑢𝑟
What is Productivity?
𝑂𝑢𝑡𝑝𝑢𝑡
𝐼𝑛𝑝𝑢𝑡
= 𝑃𝑟𝑜𝑑𝑢𝑐𝑡𝑖𝑣𝑖𝑡𝑦
𝑂𝑢𝑡𝑝𝑢𝑡 = 𝑃𝑟𝑜𝑑𝑢𝑐𝑡𝑖𝑣𝑖𝑡𝑦 𝑥 𝐼𝑛𝑝𝑢𝑡
𝑦 = 𝑚𝑥
Key Factors Affecting Productivity
• Acceleration
• Weather
• Scope Changes
• Trade Stacking
• Overtime
Estimating Lost Productivity
• AACE 25R-03 [1]
– Option A: Project Specific Studies
– Option B: Project Comparison Studies
– Option C: Specialty Industry Studies
– Option D: General Industry Studies
– Option E: Cost Basis
Option A – Project Specific Studies
• Project Specific
• Require contemporaneous documentation
Option A – Project Specific Studies
• Measured Mile
• EV Analysis
• Work Sampling Method
• Craftsmen Questionnaire Sampling Method
Option B – Project Comparison Studies
• Comparable Work Study
• Comparable Project Study
Option C – Specialty Industry Studies
• Studies of specific types of problems
– Acceleration
– Changes/Cumulative Impact
– Learning Curve
– Overtime
– Weather
Specialty Industry Studies –
Key Challenges
• Entitlement
1. Liability
2. Causation
• Justification of Method
• Applicability
• Reasonableness of Results
• Other Considerations
Liability
- First step in demonstrating entitlement
- Usually established by a contract provision or
the accused party’s breach of contract
- Key is to use the contract language to your
advantage
Causation
1. Demonstrate the accused party caused the
loss
2. Provide evidence that claimant did not
contribute to the loss
Keys to Entitlement
- Adherence to notice requirements
- Impact was unforeseeable
- Impact was beyond claimant’s control
- Claimant is not responsible
- Damages are recoverable under the contract
- Disruption resulted in changed performance or
increased cost
Justify Calculation Method
- Why couldn’t you use one of the more
preferred methods?
- Opposition may attempt to use a superior
method to demonstrate claimant’s damages
are overvalued
Applicability
- The data used in an industry study applies to a
very specific project environment
- Critical to document the surrounding circumstances
of the claim situation
- When choosing a study ask yourself:
- Why/Where/When was the study performed?
- How closely does the study tie to my scenario?
- In what way does the study differ from the case at
hand?[2]
Applicability
- Project Size
- Project Type
- Similar Trade
- Scope of work
- Circumstances
- Experience of labor force
Applicability - Example
- Leonard Study is only applicable to projects
experiencing greater than 10-15% change
orders (measured by labor hours) and only
until a certain point. [3]
Credibility
• Is the study of objective?
• Does it provide representative value?
• Does the study use recent data?
• Are intervening variables considered?
Credibility
Credibility
• Did not rely on original data
– Relied on flawed data from an earlier study by The
Business Roundtable
• The nature of the work or the trades involved was
not disclosed in the original study
Reasonability
- Demonstrating another quantification yields
similar results will bolster your position
Reasonability - Example
- Specialty Industry Study Analysis  $500,000
- Modified Total Cost “Sanity Check”
- $100,000  BAD
- $525,000  GOOD
Other Considerations
- Contemporaneous Documentation
- Expert Testimony
Summary of Key Challenges
- Demonstrating Entitlement
- Justify Quantification Method
- Applicability of Study
- Credibility
- Reasonableness of Results
Questions?
References
1. Recommended Practice No. 25R-03 “Estimating Lost Labor Productivity in
Construction Claims”, AACE International, 2004
2. Nuhu Braimah, Issaka Ndekugri & Rod Gameson, A Review of Industry Standards
and Publications/Charts for Adjusting Productivity Losses in Construction
Contracts, Presentation at the 22nd Annual ARCOM Conference, Birmingham, UK
at 49, 54 (September 2006).
3. Leonard, Charles A., The Effects of Change Orders on Productivity, Concordia
University, Montreal, Quebec, April 14, 1987.
4. Mosely, W. Alexander, Challenges to Admission of – Or Belief In – Lost
Productivity Claims Based on Industry Studies, American Bar Association, 2013.
5. Brunies, R. and Emir, Z. (2001) Calculating Loss of Productivity Due to Overtime
Using Published Charts – Facts or Fiction. The Revay Report, Vol. 20, No. 3.
6. Mechanical Contractors Association of America, Change Orders Productivity
Overtime – A Primer for the Construction Industry (MCAA 2012).

More Related Content

What's hot

Business Plan - Project Appraisal
Business Plan - Project AppraisalBusiness Plan - Project Appraisal
Business Plan - Project Appraisal
TICS
 
Projects types
Projects types Projects types
Projects types Ahmed Sakr
 
Novel tool to optimize complext industrial projects
Novel tool to optimize complext industrial projectsNovel tool to optimize complext industrial projects
Novel tool to optimize complext industrial projects
kphodel
 
Scedule feasibility
Scedule feasibilityScedule feasibility
Scedule feasibility
Udara Seneviratne
 
Project formulation (1)
Project formulation (1)Project formulation (1)
Project formulation (1)
Revathy Rajasekaran
 
Technical feasibility ppt
Technical feasibility pptTechnical feasibility ppt
Technical feasibility ppt
Chandan Singh
 
Project appraisal part 1
Project appraisal part  1Project appraisal part  1
Project appraisal part 1
danappadharwad
 
Guide to practical project appraisal en
Guide to practical project appraisal enGuide to practical project appraisal en
Guide to practical project appraisal en
tmelnik
 
FEASIBILITY STUDY
FEASIBILITY STUDYFEASIBILITY STUDY
FEASIBILITY STUDY
pethurusan
 
High Performance Building Management System.Ppt
High Performance Building Management System.PptHigh Performance Building Management System.Ppt
High Performance Building Management System.Ppt
pcholakis30
 
Overview of feasibility
Overview of feasibilityOverview of feasibility
Overview of feasibilityDaniel Bragais
 
Feasibility Analysis - Creative Engineers, Inc.
Feasibility Analysis - Creative Engineers, Inc.Feasibility Analysis - Creative Engineers, Inc.
Feasibility Analysis - Creative Engineers, Inc.
Jay Grassel
 
Detailed project reports
Detailed project reportsDetailed project reports
Detailed project reports
AKANSHA GURELE
 
feasibility study
 feasibility study feasibility study
feasibility study
Primum Nocere
 
Feasibility study ppt
Feasibility study pptFeasibility study ppt
Feasibility study ppt
kunal kishore
 
Feasibility matrix
Feasibility matrixFeasibility matrix
Feasibility matrix
IIUM
 
Feasibility study
Feasibility studyFeasibility study
Feasibility study
saifi1414
 
Detailed project report
Detailed project reportDetailed project report
Detailed project report
Vengadesh Vengadesh
 
Feasibilty Study And Report
Feasibilty Study And Report Feasibilty Study And Report
Feasibilty Study And Report
Ejaz Bhatti
 
Feasibility study
Feasibility studyFeasibility study
Feasibility study
BABYANA CONSTRUCTION SDN BHD
 

What's hot (20)

Business Plan - Project Appraisal
Business Plan - Project AppraisalBusiness Plan - Project Appraisal
Business Plan - Project Appraisal
 
Projects types
Projects types Projects types
Projects types
 
Novel tool to optimize complext industrial projects
Novel tool to optimize complext industrial projectsNovel tool to optimize complext industrial projects
Novel tool to optimize complext industrial projects
 
Scedule feasibility
Scedule feasibilityScedule feasibility
Scedule feasibility
 
Project formulation (1)
Project formulation (1)Project formulation (1)
Project formulation (1)
 
Technical feasibility ppt
Technical feasibility pptTechnical feasibility ppt
Technical feasibility ppt
 
Project appraisal part 1
Project appraisal part  1Project appraisal part  1
Project appraisal part 1
 
Guide to practical project appraisal en
Guide to practical project appraisal enGuide to practical project appraisal en
Guide to practical project appraisal en
 
FEASIBILITY STUDY
FEASIBILITY STUDYFEASIBILITY STUDY
FEASIBILITY STUDY
 
High Performance Building Management System.Ppt
High Performance Building Management System.PptHigh Performance Building Management System.Ppt
High Performance Building Management System.Ppt
 
Overview of feasibility
Overview of feasibilityOverview of feasibility
Overview of feasibility
 
Feasibility Analysis - Creative Engineers, Inc.
Feasibility Analysis - Creative Engineers, Inc.Feasibility Analysis - Creative Engineers, Inc.
Feasibility Analysis - Creative Engineers, Inc.
 
Detailed project reports
Detailed project reportsDetailed project reports
Detailed project reports
 
feasibility study
 feasibility study feasibility study
feasibility study
 
Feasibility study ppt
Feasibility study pptFeasibility study ppt
Feasibility study ppt
 
Feasibility matrix
Feasibility matrixFeasibility matrix
Feasibility matrix
 
Feasibility study
Feasibility studyFeasibility study
Feasibility study
 
Detailed project report
Detailed project reportDetailed project report
Detailed project report
 
Feasibilty Study And Report
Feasibilty Study And Report Feasibilty Study And Report
Feasibilty Study And Report
 
Feasibility study
Feasibility studyFeasibility study
Feasibility study
 

Viewers also liked

Material Management and ABC analysis
Material Management and ABC analysisMaterial Management and ABC analysis
Material Management and ABC analysisDr. Sonal Mandhotra
 
Presentation introduction to six sigma
Presentation   introduction to six sigmaPresentation   introduction to six sigma
Presentation introduction to six sigmajpanchpor
 
Material Management & Inventory Management
Material Management & Inventory ManagementMaterial Management & Inventory Management
Material Management & Inventory Management
HR at VASHI ELECTRICALS PVT. LTD.
 
Material management
Material managementMaterial management
Material management
Saiprasad Bhavsar
 
Six Sigma
Six SigmaSix Sigma
Six Sigma
princegeet17
 
Basic Six Sigma Presentation
Basic Six Sigma PresentationBasic Six Sigma Presentation
Basic Six Sigma Presentationvivekissar
 
Six Sigma the best ppt
Six Sigma the best pptSix Sigma the best ppt
Six Sigma the best ppt
Rabia Sgh S
 

Viewers also liked (9)

Careers in the_supply_chain
Careers in the_supply_chainCareers in the_supply_chain
Careers in the_supply_chain
 
Material Management and ABC analysis
Material Management and ABC analysisMaterial Management and ABC analysis
Material Management and ABC analysis
 
Presentation introduction to six sigma
Presentation   introduction to six sigmaPresentation   introduction to six sigma
Presentation introduction to six sigma
 
Material Management & Inventory Management
Material Management & Inventory ManagementMaterial Management & Inventory Management
Material Management & Inventory Management
 
Material management
Material managementMaterial management
Material management
 
Six Sigma
Six SigmaSix Sigma
Six Sigma
 
Six sigma ppt
Six sigma pptSix sigma ppt
Six sigma ppt
 
Basic Six Sigma Presentation
Basic Six Sigma PresentationBasic Six Sigma Presentation
Basic Six Sigma Presentation
 
Six Sigma the best ppt
Six Sigma the best pptSix Sigma the best ppt
Six Sigma the best ppt
 

Similar to VERTEX - AACE Northeast Total Cost Management Symposium 2016

Day 1 Review Industrial Codes and Standards.pptx
Day 1 Review Industrial Codes and Standards.pptxDay 1 Review Industrial Codes and Standards.pptx
Day 1 Review Industrial Codes and Standards.pptx
musaabdalla3
 
Episode 27 : Project Management Costs
Episode 27 : Project Management Costs Episode 27 : Project Management Costs
Episode 27 : Project Management Costs
SAJJAD KHUDHUR ABBAS
 
Service innovation for energy services: how to get from an idea to a service ...
Service innovation for energy services: how to get from an idea to a service ...Service innovation for energy services: how to get from an idea to a service ...
Service innovation for energy services: how to get from an idea to a service ...
Heiko Gebauer
 
q-Maxim’s approach to waste reduction in foundry application using Taguchi ...
q-Maxim’s approach to waste reduction in  foundry application  using Taguchi ...q-Maxim’s approach to waste reduction in  foundry application  using Taguchi ...
q-Maxim’s approach to waste reduction in foundry application using Taguchi ...
q-Maxim
 
Episode 27 : Project Management Costs
Episode 27 : Project Management Costs Episode 27 : Project Management Costs
Episode 27 : Project Management Costs
SAJJAD KHUDHUR ABBAS
 
Innovation pathway for infrastructure solutions
Innovation pathway for infrastructure solutionsInnovation pathway for infrastructure solutions
Innovation pathway for infrastructure solutions
Chris Jurewicz
 
Facility Location/Prduction Design & Development/Process Selection
Facility Location/Prduction Design & Development/Process SelectionFacility Location/Prduction Design & Development/Process Selection
Facility Location/Prduction Design & Development/Process Selection
viveksangwan007
 
project management
project managementproject management
project management
KomalaselvanV1
 
2.requirements management
2.requirements management2.requirements management
2.requirements management
Panos Fitsilis
 
Chapter 3.pptx
Chapter 3.pptxChapter 3.pptx
Chapter 3.pptx
shamirmahmud1
 
Value Propositions - CDMA meeting 2006
Value Propositions - CDMA meeting 2006Value Propositions - CDMA meeting 2006
Value Propositions - CDMA meeting 2006Sudhir Hublikar
 
Topic 7 Evaluation
Topic 7 EvaluationTopic 7 Evaluation
Topic 7 Evaluationguest5dc00b
 
Construction productivity
Construction productivityConstruction productivity
Construction productivity
Sunil Manjeri
 
Tech connect fall 2015 value proposition to encouraging adoption
Tech connect fall 2015   value proposition to encouraging adoption Tech connect fall 2015   value proposition to encouraging adoption
Tech connect fall 2015 value proposition to encouraging adoption
Lassonde School of Engineering
 
Benchmarking for Superior Performance
Benchmarking for Superior PerformanceBenchmarking for Superior Performance
Benchmarking for Superior Performance
Operational Excellence Consulting
 
Operations strategy
Operations strategy Operations strategy
Operations strategy
Petre Vane
 
2.1 Product_Specifications.ppt
2.1 Product_Specifications.ppt2.1 Product_Specifications.ppt
2.1 Product_Specifications.ppt
girilogu2
 

Similar to VERTEX - AACE Northeast Total Cost Management Symposium 2016 (20)

Day 1 Review Industrial Codes and Standards.pptx
Day 1 Review Industrial Codes and Standards.pptxDay 1 Review Industrial Codes and Standards.pptx
Day 1 Review Industrial Codes and Standards.pptx
 
Episode 27 : Project Management Costs
Episode 27 : Project Management Costs Episode 27 : Project Management Costs
Episode 27 : Project Management Costs
 
Service innovation for energy services: how to get from an idea to a service ...
Service innovation for energy services: how to get from an idea to a service ...Service innovation for energy services: how to get from an idea to a service ...
Service innovation for energy services: how to get from an idea to a service ...
 
q-Maxim’s approach to waste reduction in foundry application using Taguchi ...
q-Maxim’s approach to waste reduction in  foundry application  using Taguchi ...q-Maxim’s approach to waste reduction in  foundry application  using Taguchi ...
q-Maxim’s approach to waste reduction in foundry application using Taguchi ...
 
Episode 27 : Project Management Costs
Episode 27 : Project Management Costs Episode 27 : Project Management Costs
Episode 27 : Project Management Costs
 
Innovation pathway for infrastructure solutions
Innovation pathway for infrastructure solutionsInnovation pathway for infrastructure solutions
Innovation pathway for infrastructure solutions
 
Facility Location/Prduction Design & Development/Process Selection
Facility Location/Prduction Design & Development/Process SelectionFacility Location/Prduction Design & Development/Process Selection
Facility Location/Prduction Design & Development/Process Selection
 
Unit2
Unit2Unit2
Unit2
 
project management
project managementproject management
project management
 
2.requirements management
2.requirements management2.requirements management
2.requirements management
 
Chapter 3.pptx
Chapter 3.pptxChapter 3.pptx
Chapter 3.pptx
 
Value Propositions - CDMA meeting 2006
Value Propositions - CDMA meeting 2006Value Propositions - CDMA meeting 2006
Value Propositions - CDMA meeting 2006
 
Topic 7 Evaluation
Topic 7 EvaluationTopic 7 Evaluation
Topic 7 Evaluation
 
Koncept Analytics Brochure
Koncept Analytics BrochureKoncept Analytics Brochure
Koncept Analytics Brochure
 
Construction productivity
Construction productivityConstruction productivity
Construction productivity
 
Tech connect fall 2015 value proposition to encouraging adoption
Tech connect fall 2015   value proposition to encouraging adoption Tech connect fall 2015   value proposition to encouraging adoption
Tech connect fall 2015 value proposition to encouraging adoption
 
Engineering
EngineeringEngineering
Engineering
 
Benchmarking for Superior Performance
Benchmarking for Superior PerformanceBenchmarking for Superior Performance
Benchmarking for Superior Performance
 
Operations strategy
Operations strategy Operations strategy
Operations strategy
 
2.1 Product_Specifications.ppt
2.1 Product_Specifications.ppt2.1 Product_Specifications.ppt
2.1 Product_Specifications.ppt
 

More from Lisa Dehner

VERTEX Annual State of the Construction Industry 2018
VERTEX Annual State of the Construction Industry 2018VERTEX Annual State of the Construction Industry 2018
VERTEX Annual State of the Construction Industry 2018
Lisa Dehner
 
Hail Damage to Termoset and Thermoplastic Roofing Membranes
Hail Damage to Termoset and Thermoplastic Roofing MembranesHail Damage to Termoset and Thermoplastic Roofing Membranes
Hail Damage to Termoset and Thermoplastic Roofing Membranes
Lisa Dehner
 
Construction of Manufactured Homes - Understanding the Hazards & Risks
Construction of Manufactured Homes - Understanding the Hazards & RisksConstruction of Manufactured Homes - Understanding the Hazards & Risks
Construction of Manufactured Homes - Understanding the Hazards & Risks
Lisa Dehner
 
2015 State of the Construction Industry
2015 State of the Construction Industry 2015 State of the Construction Industry
2015 State of the Construction Industry
Lisa Dehner
 
State of the Construction and Surety Industry Report (2008)
State of the Construction and Surety Industry Report (2008)State of the Construction and Surety Industry Report (2008)
State of the Construction and Surety Industry Report (2008)
Lisa Dehner
 
State of the construction industry (2006 2007)
State of the construction industry (2006 2007)State of the construction industry (2006 2007)
State of the construction industry (2006 2007)
Lisa Dehner
 
State of the Construction and Surety Industry Report (2010)
State of the Construction and Surety Industry Report (2010)State of the Construction and Surety Industry Report (2010)
State of the Construction and Surety Industry Report (2010)
Lisa Dehner
 
State of the Construction and Surety Industry Report (2009)
State of the Construction and Surety Industry Report (2009)State of the Construction and Surety Industry Report (2009)
State of the Construction and Surety Industry Report (2009)
Lisa Dehner
 
Environmental Business Journal - VERTEX Growth
Environmental Business Journal - VERTEX GrowthEnvironmental Business Journal - VERTEX Growth
Environmental Business Journal - VERTEX Growth
Lisa Dehner
 
ABA Committee News - Fall 2016
ABA Committee News - Fall 2016ABA Committee News - Fall 2016
ABA Committee News - Fall 2016
Lisa Dehner
 
Business Journal - Dallas
Business Journal - DallasBusiness Journal - Dallas
Business Journal - Dallas
Lisa Dehner
 
Department of Health 5222
Department of Health 5222Department of Health 5222
Department of Health 5222
Lisa Dehner
 
Bill McConnell's State of the Surety Industry in 2016
Bill McConnell's State of the Surety Industry in 2016Bill McConnell's State of the Surety Industry in 2016
Bill McConnell's State of the Surety Industry in 2016
Lisa Dehner
 
Past, Present, and Future Analysis of the Architectural & Engineering Design ...
Past, Present, and Future Analysis of the Architectural & Engineering Design ...Past, Present, and Future Analysis of the Architectural & Engineering Design ...
Past, Present, and Future Analysis of the Architectural & Engineering Design ...
Lisa Dehner
 
Legionnaires' Disease - How to Comply with Rapidly Developing Cooling Tower R...
Legionnaires' Disease - How to Comply with Rapidly Developing Cooling Tower R...Legionnaires' Disease - How to Comply with Rapidly Developing Cooling Tower R...
Legionnaires' Disease - How to Comply with Rapidly Developing Cooling Tower R...
Lisa Dehner
 
2016 State of the U.S. Economy
2016 State of the U.S. Economy2016 State of the U.S. Economy
2016 State of the U.S. Economy
Lisa Dehner
 
Boletin vertex abril 2016
Boletin vertex   abril 2016Boletin vertex   abril 2016
Boletin vertex abril 2016
Lisa Dehner
 
VERTEX Construction Claim Visuals - AACE Northeast Total Cost Management Sym...
VERTEX Construction Claim Visuals  - AACE Northeast Total Cost Management Sym...VERTEX Construction Claim Visuals  - AACE Northeast Total Cost Management Sym...
VERTEX Construction Claim Visuals - AACE Northeast Total Cost Management Sym...
Lisa Dehner
 
The Vertex Companies, Inc. - Time Impact Analysis
The Vertex Companies, Inc. - Time Impact AnalysisThe Vertex Companies, Inc. - Time Impact Analysis
The Vertex Companies, Inc. - Time Impact Analysis
Lisa Dehner
 

More from Lisa Dehner (19)

VERTEX Annual State of the Construction Industry 2018
VERTEX Annual State of the Construction Industry 2018VERTEX Annual State of the Construction Industry 2018
VERTEX Annual State of the Construction Industry 2018
 
Hail Damage to Termoset and Thermoplastic Roofing Membranes
Hail Damage to Termoset and Thermoplastic Roofing MembranesHail Damage to Termoset and Thermoplastic Roofing Membranes
Hail Damage to Termoset and Thermoplastic Roofing Membranes
 
Construction of Manufactured Homes - Understanding the Hazards & Risks
Construction of Manufactured Homes - Understanding the Hazards & RisksConstruction of Manufactured Homes - Understanding the Hazards & Risks
Construction of Manufactured Homes - Understanding the Hazards & Risks
 
2015 State of the Construction Industry
2015 State of the Construction Industry 2015 State of the Construction Industry
2015 State of the Construction Industry
 
State of the Construction and Surety Industry Report (2008)
State of the Construction and Surety Industry Report (2008)State of the Construction and Surety Industry Report (2008)
State of the Construction and Surety Industry Report (2008)
 
State of the construction industry (2006 2007)
State of the construction industry (2006 2007)State of the construction industry (2006 2007)
State of the construction industry (2006 2007)
 
State of the Construction and Surety Industry Report (2010)
State of the Construction and Surety Industry Report (2010)State of the Construction and Surety Industry Report (2010)
State of the Construction and Surety Industry Report (2010)
 
State of the Construction and Surety Industry Report (2009)
State of the Construction and Surety Industry Report (2009)State of the Construction and Surety Industry Report (2009)
State of the Construction and Surety Industry Report (2009)
 
Environmental Business Journal - VERTEX Growth
Environmental Business Journal - VERTEX GrowthEnvironmental Business Journal - VERTEX Growth
Environmental Business Journal - VERTEX Growth
 
ABA Committee News - Fall 2016
ABA Committee News - Fall 2016ABA Committee News - Fall 2016
ABA Committee News - Fall 2016
 
Business Journal - Dallas
Business Journal - DallasBusiness Journal - Dallas
Business Journal - Dallas
 
Department of Health 5222
Department of Health 5222Department of Health 5222
Department of Health 5222
 
Bill McConnell's State of the Surety Industry in 2016
Bill McConnell's State of the Surety Industry in 2016Bill McConnell's State of the Surety Industry in 2016
Bill McConnell's State of the Surety Industry in 2016
 
Past, Present, and Future Analysis of the Architectural & Engineering Design ...
Past, Present, and Future Analysis of the Architectural & Engineering Design ...Past, Present, and Future Analysis of the Architectural & Engineering Design ...
Past, Present, and Future Analysis of the Architectural & Engineering Design ...
 
Legionnaires' Disease - How to Comply with Rapidly Developing Cooling Tower R...
Legionnaires' Disease - How to Comply with Rapidly Developing Cooling Tower R...Legionnaires' Disease - How to Comply with Rapidly Developing Cooling Tower R...
Legionnaires' Disease - How to Comply with Rapidly Developing Cooling Tower R...
 
2016 State of the U.S. Economy
2016 State of the U.S. Economy2016 State of the U.S. Economy
2016 State of the U.S. Economy
 
Boletin vertex abril 2016
Boletin vertex   abril 2016Boletin vertex   abril 2016
Boletin vertex abril 2016
 
VERTEX Construction Claim Visuals - AACE Northeast Total Cost Management Sym...
VERTEX Construction Claim Visuals  - AACE Northeast Total Cost Management Sym...VERTEX Construction Claim Visuals  - AACE Northeast Total Cost Management Sym...
VERTEX Construction Claim Visuals - AACE Northeast Total Cost Management Sym...
 
The Vertex Companies, Inc. - Time Impact Analysis
The Vertex Companies, Inc. - Time Impact AnalysisThe Vertex Companies, Inc. - Time Impact Analysis
The Vertex Companies, Inc. - Time Impact Analysis
 

Recently uploaded

The Reserve Bank of India Act, 1934.pptx
The Reserve Bank of India Act, 1934.pptxThe Reserve Bank of India Act, 1934.pptx
The Reserve Bank of India Act, 1934.pptx
nehatalele22st
 
定制(nus毕业证书)新加坡国立大学毕业证学位证书实拍图原版一模一样
定制(nus毕业证书)新加坡国立大学毕业证学位证书实拍图原版一模一样定制(nus毕业证书)新加坡国立大学毕业证学位证书实拍图原版一模一样
定制(nus毕业证书)新加坡国立大学毕业证学位证书实拍图原版一模一样
9ib5wiwt
 
Car Accident Injury Do I Have a Case....
Car Accident Injury Do I Have a Case....Car Accident Injury Do I Have a Case....
Car Accident Injury Do I Have a Case....
Knowyourright
 
Daftar Rumpun, Pohon, dan Cabang Ilmu (28 Mei 2024).pdf
Daftar Rumpun, Pohon, dan Cabang Ilmu (28 Mei 2024).pdfDaftar Rumpun, Pohon, dan Cabang Ilmu (28 Mei 2024).pdf
Daftar Rumpun, Pohon, dan Cabang Ilmu (28 Mei 2024).pdf
akbarrasyid3
 
Highlights_of_Bhartiya_Nyaya_Sanhita.pptx
Highlights_of_Bhartiya_Nyaya_Sanhita.pptxHighlights_of_Bhartiya_Nyaya_Sanhita.pptx
Highlights_of_Bhartiya_Nyaya_Sanhita.pptx
anjalidixit21
 
VIETNAM - DIRECT POWER PURCHASE AGREEMENTS (DPPA) - Latest development - What...
VIETNAM - DIRECT POWER PURCHASE AGREEMENTS (DPPA) - Latest development - What...VIETNAM - DIRECT POWER PURCHASE AGREEMENTS (DPPA) - Latest development - What...
VIETNAM - DIRECT POWER PURCHASE AGREEMENTS (DPPA) - Latest development - What...
Dr. Oliver Massmann
 
Rokita Releases Soccer Stadium Legal Opinion
Rokita Releases Soccer Stadium Legal OpinionRokita Releases Soccer Stadium Legal Opinion
Rokita Releases Soccer Stadium Legal Opinion
Abdul-Hakim Shabazz
 
Notes-on-Prescription-Obligations-and-Contracts.doc
Notes-on-Prescription-Obligations-and-Contracts.docNotes-on-Prescription-Obligations-and-Contracts.doc
Notes-on-Prescription-Obligations-and-Contracts.doc
BRELGOSIMAT
 
ADR in criminal proceeding in Bangladesh with global perspective.
ADR in criminal proceeding in Bangladesh with global perspective.ADR in criminal proceeding in Bangladesh with global perspective.
ADR in criminal proceeding in Bangladesh with global perspective.
Daffodil International University
 
The Main Procedures for Obtaining Cypriot Citizenship
The Main Procedures for Obtaining Cypriot CitizenshipThe Main Procedures for Obtaining Cypriot Citizenship
The Main Procedures for Obtaining Cypriot Citizenship
BridgeWest.eu
 
Donald_J_Trump_katigoritirio_stormi_daniels.pdf
Donald_J_Trump_katigoritirio_stormi_daniels.pdfDonald_J_Trump_katigoritirio_stormi_daniels.pdf
Donald_J_Trump_katigoritirio_stormi_daniels.pdf
ssuser5750e1
 
Abdul Hakim Shabazz Deposition Hearing in Federal Court
Abdul Hakim Shabazz Deposition Hearing in Federal CourtAbdul Hakim Shabazz Deposition Hearing in Federal Court
Abdul Hakim Shabazz Deposition Hearing in Federal Court
Gabe Whitley
 
Bharatiya Nagarik Suraksha Sanhita power.pptx
Bharatiya Nagarik Suraksha Sanhita power.pptxBharatiya Nagarik Suraksha Sanhita power.pptx
Bharatiya Nagarik Suraksha Sanhita power.pptx
ShivkumarIyer18
 
Business and Corporate Case Update (2024)
Business and Corporate Case Update (2024)Business and Corporate Case Update (2024)
Business and Corporate Case Update (2024)
Wendy Couture
 
VAWA - Violence Against Women Act Presentation
VAWA - Violence Against Women Act PresentationVAWA - Violence Against Women Act Presentation
VAWA - Violence Against Women Act Presentation
FernandoSimesBlanco1
 
Roles of a Bankruptcy Lawyer John Cavitt
Roles of a Bankruptcy Lawyer John CavittRoles of a Bankruptcy Lawyer John Cavitt
Roles of a Bankruptcy Lawyer John Cavitt
johncavitthouston
 
EMPLOYMENT LAW AN OVERVIEW in Malawi.pptx
EMPLOYMENT LAW  AN OVERVIEW in Malawi.pptxEMPLOYMENT LAW  AN OVERVIEW in Malawi.pptx
EMPLOYMENT LAW AN OVERVIEW in Malawi.pptx
MwaiMapemba
 
WINDING UP of COMPANY, Modes of Dissolution
WINDING UP of COMPANY, Modes of DissolutionWINDING UP of COMPANY, Modes of Dissolution
WINDING UP of COMPANY, Modes of Dissolution
KHURRAMWALI
 
办理(waikato毕业证书)新西兰怀卡托大学毕业证双学位证书原版一模一样
办理(waikato毕业证书)新西兰怀卡托大学毕业证双学位证书原版一模一样办理(waikato毕业证书)新西兰怀卡托大学毕业证双学位证书原版一模一样
办理(waikato毕业证书)新西兰怀卡托大学毕业证双学位证书原版一模一样
9ib5wiwt
 
Military Commissions details LtCol Thomas Jasper as Detailed Defense Counsel
Military Commissions details LtCol Thomas Jasper as Detailed Defense CounselMilitary Commissions details LtCol Thomas Jasper as Detailed Defense Counsel
Military Commissions details LtCol Thomas Jasper as Detailed Defense Counsel
Thomas (Tom) Jasper
 

Recently uploaded (20)

The Reserve Bank of India Act, 1934.pptx
The Reserve Bank of India Act, 1934.pptxThe Reserve Bank of India Act, 1934.pptx
The Reserve Bank of India Act, 1934.pptx
 
定制(nus毕业证书)新加坡国立大学毕业证学位证书实拍图原版一模一样
定制(nus毕业证书)新加坡国立大学毕业证学位证书实拍图原版一模一样定制(nus毕业证书)新加坡国立大学毕业证学位证书实拍图原版一模一样
定制(nus毕业证书)新加坡国立大学毕业证学位证书实拍图原版一模一样
 
Car Accident Injury Do I Have a Case....
Car Accident Injury Do I Have a Case....Car Accident Injury Do I Have a Case....
Car Accident Injury Do I Have a Case....
 
Daftar Rumpun, Pohon, dan Cabang Ilmu (28 Mei 2024).pdf
Daftar Rumpun, Pohon, dan Cabang Ilmu (28 Mei 2024).pdfDaftar Rumpun, Pohon, dan Cabang Ilmu (28 Mei 2024).pdf
Daftar Rumpun, Pohon, dan Cabang Ilmu (28 Mei 2024).pdf
 
Highlights_of_Bhartiya_Nyaya_Sanhita.pptx
Highlights_of_Bhartiya_Nyaya_Sanhita.pptxHighlights_of_Bhartiya_Nyaya_Sanhita.pptx
Highlights_of_Bhartiya_Nyaya_Sanhita.pptx
 
VIETNAM - DIRECT POWER PURCHASE AGREEMENTS (DPPA) - Latest development - What...
VIETNAM - DIRECT POWER PURCHASE AGREEMENTS (DPPA) - Latest development - What...VIETNAM - DIRECT POWER PURCHASE AGREEMENTS (DPPA) - Latest development - What...
VIETNAM - DIRECT POWER PURCHASE AGREEMENTS (DPPA) - Latest development - What...
 
Rokita Releases Soccer Stadium Legal Opinion
Rokita Releases Soccer Stadium Legal OpinionRokita Releases Soccer Stadium Legal Opinion
Rokita Releases Soccer Stadium Legal Opinion
 
Notes-on-Prescription-Obligations-and-Contracts.doc
Notes-on-Prescription-Obligations-and-Contracts.docNotes-on-Prescription-Obligations-and-Contracts.doc
Notes-on-Prescription-Obligations-and-Contracts.doc
 
ADR in criminal proceeding in Bangladesh with global perspective.
ADR in criminal proceeding in Bangladesh with global perspective.ADR in criminal proceeding in Bangladesh with global perspective.
ADR in criminal proceeding in Bangladesh with global perspective.
 
The Main Procedures for Obtaining Cypriot Citizenship
The Main Procedures for Obtaining Cypriot CitizenshipThe Main Procedures for Obtaining Cypriot Citizenship
The Main Procedures for Obtaining Cypriot Citizenship
 
Donald_J_Trump_katigoritirio_stormi_daniels.pdf
Donald_J_Trump_katigoritirio_stormi_daniels.pdfDonald_J_Trump_katigoritirio_stormi_daniels.pdf
Donald_J_Trump_katigoritirio_stormi_daniels.pdf
 
Abdul Hakim Shabazz Deposition Hearing in Federal Court
Abdul Hakim Shabazz Deposition Hearing in Federal CourtAbdul Hakim Shabazz Deposition Hearing in Federal Court
Abdul Hakim Shabazz Deposition Hearing in Federal Court
 
Bharatiya Nagarik Suraksha Sanhita power.pptx
Bharatiya Nagarik Suraksha Sanhita power.pptxBharatiya Nagarik Suraksha Sanhita power.pptx
Bharatiya Nagarik Suraksha Sanhita power.pptx
 
Business and Corporate Case Update (2024)
Business and Corporate Case Update (2024)Business and Corporate Case Update (2024)
Business and Corporate Case Update (2024)
 
VAWA - Violence Against Women Act Presentation
VAWA - Violence Against Women Act PresentationVAWA - Violence Against Women Act Presentation
VAWA - Violence Against Women Act Presentation
 
Roles of a Bankruptcy Lawyer John Cavitt
Roles of a Bankruptcy Lawyer John CavittRoles of a Bankruptcy Lawyer John Cavitt
Roles of a Bankruptcy Lawyer John Cavitt
 
EMPLOYMENT LAW AN OVERVIEW in Malawi.pptx
EMPLOYMENT LAW  AN OVERVIEW in Malawi.pptxEMPLOYMENT LAW  AN OVERVIEW in Malawi.pptx
EMPLOYMENT LAW AN OVERVIEW in Malawi.pptx
 
WINDING UP of COMPANY, Modes of Dissolution
WINDING UP of COMPANY, Modes of DissolutionWINDING UP of COMPANY, Modes of Dissolution
WINDING UP of COMPANY, Modes of Dissolution
 
办理(waikato毕业证书)新西兰怀卡托大学毕业证双学位证书原版一模一样
办理(waikato毕业证书)新西兰怀卡托大学毕业证双学位证书原版一模一样办理(waikato毕业证书)新西兰怀卡托大学毕业证双学位证书原版一模一样
办理(waikato毕业证书)新西兰怀卡托大学毕业证双学位证书原版一模一样
 
Military Commissions details LtCol Thomas Jasper as Detailed Defense Counsel
Military Commissions details LtCol Thomas Jasper as Detailed Defense CounselMilitary Commissions details LtCol Thomas Jasper as Detailed Defense Counsel
Military Commissions details LtCol Thomas Jasper as Detailed Defense Counsel
 

VERTEX - AACE Northeast Total Cost Management Symposium 2016

  • 1. Key Challenges in Demonstrating Loss of Productivity Claims Based on Specialty Industry Studies Andrew Sargent, Amin Terouhid
  • 2. Andrew Sargent, EIT Amin Terouhid, PhD, PMP
  • 3. Goal Identify challenges when using Specialty Industry Studies to calculate productivity loss and how to address them
  • 4. Agenda • Overview of productivity loss and quantification methods • What is a Specialty Industry Study and when should you use them? • Challenges when using these studies and how to overcome them
  • 5. What is Productivity? 𝑃𝑟𝑜𝑑𝑢𝑐𝑡𝑖𝑣𝑖𝑡𝑦 = 𝑂𝑢𝑡𝑝𝑢𝑡 𝐼𝑛𝑝𝑢𝑡 𝑂𝑢𝑡𝑝𝑢𝑡 = 1000 𝐿𝐹 𝐼𝑛𝑝𝑢𝑡 = 50 ℎ𝑟𝑠 𝑃𝑟𝑜𝑑𝑢𝑐𝑡𝑖𝑣𝑖𝑡𝑦 = 𝑂𝑢𝑡𝑝𝑢𝑡 𝐼𝑛𝑝𝑢𝑡 = 1000𝐿𝐹 50ℎ𝑟𝑠 = 20 𝐿𝐹 𝑝𝑒𝑟 ℎ𝑜𝑢𝑟
  • 6. What is Productivity? 𝑂𝑢𝑡𝑝𝑢𝑡 𝐼𝑛𝑝𝑢𝑡 = 𝑃𝑟𝑜𝑑𝑢𝑐𝑡𝑖𝑣𝑖𝑡𝑦 𝑂𝑢𝑡𝑝𝑢𝑡 = 𝑃𝑟𝑜𝑑𝑢𝑐𝑡𝑖𝑣𝑖𝑡𝑦 𝑥 𝐼𝑛𝑝𝑢𝑡 𝑦 = 𝑚𝑥
  • 7.
  • 8. Key Factors Affecting Productivity • Acceleration • Weather • Scope Changes • Trade Stacking • Overtime
  • 9. Estimating Lost Productivity • AACE 25R-03 [1] – Option A: Project Specific Studies – Option B: Project Comparison Studies – Option C: Specialty Industry Studies – Option D: General Industry Studies – Option E: Cost Basis
  • 10. Option A – Project Specific Studies • Project Specific • Require contemporaneous documentation
  • 11. Option A – Project Specific Studies • Measured Mile • EV Analysis • Work Sampling Method • Craftsmen Questionnaire Sampling Method
  • 12. Option B – Project Comparison Studies • Comparable Work Study • Comparable Project Study
  • 13. Option C – Specialty Industry Studies • Studies of specific types of problems – Acceleration – Changes/Cumulative Impact – Learning Curve – Overtime – Weather
  • 14. Specialty Industry Studies – Key Challenges • Entitlement 1. Liability 2. Causation • Justification of Method • Applicability • Reasonableness of Results • Other Considerations
  • 15. Liability - First step in demonstrating entitlement - Usually established by a contract provision or the accused party’s breach of contract - Key is to use the contract language to your advantage
  • 16. Causation 1. Demonstrate the accused party caused the loss 2. Provide evidence that claimant did not contribute to the loss
  • 17. Keys to Entitlement - Adherence to notice requirements - Impact was unforeseeable - Impact was beyond claimant’s control - Claimant is not responsible - Damages are recoverable under the contract - Disruption resulted in changed performance or increased cost
  • 18. Justify Calculation Method - Why couldn’t you use one of the more preferred methods? - Opposition may attempt to use a superior method to demonstrate claimant’s damages are overvalued
  • 19. Applicability - The data used in an industry study applies to a very specific project environment - Critical to document the surrounding circumstances of the claim situation - When choosing a study ask yourself: - Why/Where/When was the study performed? - How closely does the study tie to my scenario? - In what way does the study differ from the case at hand?[2]
  • 20. Applicability - Project Size - Project Type - Similar Trade - Scope of work - Circumstances - Experience of labor force
  • 21. Applicability - Example - Leonard Study is only applicable to projects experiencing greater than 10-15% change orders (measured by labor hours) and only until a certain point. [3]
  • 22. Credibility • Is the study of objective? • Does it provide representative value? • Does the study use recent data? • Are intervening variables considered?
  • 24. Credibility • Did not rely on original data – Relied on flawed data from an earlier study by The Business Roundtable • The nature of the work or the trades involved was not disclosed in the original study
  • 25. Reasonability - Demonstrating another quantification yields similar results will bolster your position
  • 26. Reasonability - Example - Specialty Industry Study Analysis  $500,000 - Modified Total Cost “Sanity Check” - $100,000  BAD - $525,000  GOOD
  • 27. Other Considerations - Contemporaneous Documentation - Expert Testimony
  • 28. Summary of Key Challenges - Demonstrating Entitlement - Justify Quantification Method - Applicability of Study - Credibility - Reasonableness of Results
  • 30. References 1. Recommended Practice No. 25R-03 “Estimating Lost Labor Productivity in Construction Claims”, AACE International, 2004 2. Nuhu Braimah, Issaka Ndekugri & Rod Gameson, A Review of Industry Standards and Publications/Charts for Adjusting Productivity Losses in Construction Contracts, Presentation at the 22nd Annual ARCOM Conference, Birmingham, UK at 49, 54 (September 2006). 3. Leonard, Charles A., The Effects of Change Orders on Productivity, Concordia University, Montreal, Quebec, April 14, 1987. 4. Mosely, W. Alexander, Challenges to Admission of – Or Belief In – Lost Productivity Claims Based on Industry Studies, American Bar Association, 2013. 5. Brunies, R. and Emir, Z. (2001) Calculating Loss of Productivity Due to Overtime Using Published Charts – Facts or Fiction. The Revay Report, Vol. 20, No. 3. 6. Mechanical Contractors Association of America, Change Orders Productivity Overtime – A Primer for the Construction Industry (MCAA 2012).

Editor's Notes

  1. This slide will cover what we will be covering in the entire presentation: BRIEF overview of what productivity is and some common factors that negatively impact productivity Go over the various methods used to calculate productivity loss We will focus on Specialty Industry Studies When are they appropriate? What are some key considerations when using them? After identifying the major challenges one faces when using Specialty Industry Studies we will discuss methods to overcome these challenges
  2. I am sure most of you are familiar with the concept of Productivity Productivity is basically a measure of how much you get out for how much you put in Output is generally measured in physical units Input is usually measured in labor hours EXAMPLE Lets say a project requires us to lay 1000 ft of pipe and I estimate my company can do this in 50 labor hours. Output = 1000 ft Input = 50 labor hours Productivity = (1000 ft / 50 labor hours) = 20 ft per labor hour
  3. Now lets transform the equation a bit We all remember y = mx +b from algebra We have m = y/x Y = mx Slope is your productivity
  4. Our output is constant (unless there are design changes) If our Productivity goes down, we need to increase our input to achieve the output required by the Project. More input = more cost $$$$$ Steeper slope = greater productivity
  5. What are some factors that cause a loss in productivity? There are MANY different factors that can affect productivity – some of the more prominent ones are: Acceleration Weather Scope Changes Trade Stacking Overtime
  6. There is no consensus in the industry as to the absolute best way to calculate lost productivity However, AACE 25R-03 provides a list of the various calculation methods and lists them in order of preference Option A>Option B>Option C and so forth. Methods to calculate productivity loss Project Specific Studies (Tier 1) Measured Mile - Gold Standard (1A) Earned Value Analysis (1B) Work Sampling Method (1C) Craftsmen Questionnaire Sampling Method (1D) Project Comparison Studies (Tier 2) Comparable Work Study (2A) Comparable Project Study (2B) Specialty Industry Studies (Tier 3)
  7. Project Specific Studies are (as the name says) project specific Supported with documentation directly related to the dispute To use project specific studies you need reliable contemporaneous project documentation.
  8. Using Project Specific Studies is the preferred way to quantify loss of productivity The gold standard is the measured mile But this may not be available for a number of reasons ASK AUDIENCE: Has anyone here every seen a productivity claim using work sampling methods?
  9. Comparable Work Studies compare two similar activities on the project Require similar work on the same project EXAMPLE – electrical conduit and sprinkler piping Comparable Project Studies require similar projects If the project is very unique this option is not usually available.
  10. If there is insufficient contemporaneous project documentation to use the Project Specific or Project Comparison Study methodologies, recommended practice is to perform your productivity loss estimate using specialty industry studies Studies of specific types of problems that are based on some number of actual construction projects
  11. The first step in any productivity claim (or any claim for that matter) is to establish liability If you cannot identify a contract provision to help establish liability then your claim may be in trouble.
  12. Causation is a little more difficult Two equally important parts: - Proof that the accused party caused the loss - Proof that claimant did not contribute to the loss. If the claimant is partially responsible for the loss, it is crucial that the claim address apportionment of damages. Claimant should be able to apportion liability based on findings of causation. ****Discuss apportionment
  13. As with all productivity loss calculation methods, the claimant will have to establish entitlement and causation of the alleged productivity impact. Not unique to specialty industry studies No point in reviewing damage calculations if claimant cannot establish it is entitle to recover anything. To demonstrate entitlement a claimant must document the following: Notice Requirements Key is to familiarize your project management team and field team with the contract requirements early on in the project. This ensures that when a dispute arises, the team is aware to the notice requirements. Key is to ensure your narrative adequately addresses each of the items listed on the slide. *****
  14. Given the preference for the measure mile or more desirable quantification methods, it is good practice to address why a certain method was chosen Why couldn’t you use Project Specific or Project Comparison Studies? In the case of specialty industry studies, a claimant should address why the Project Specific or Project Comparison Studies could not be used. Maybe there was no impacted period or there wasn’t adequate contemporaneous documentation to use one of the preferred methods. The Opposition may try to discredit your findings by either: noting you didn’t follow recommended practice by using a preferred (and demonstrably available) method Performing its own analysis using a preferred method which yields a small damage value.
  15. Demonstrating the study used to calculate the productivity loss is appropriate for the applied situation is critical
  16. Key is to make sure your claim narrative outlines why you feel the study used in your quantification is applicable to the given disruption
  17. The Defendant will likely try to discredit the study the claim relies on to prepare its estimate To document that the utilized study is credible the claimant should address the following; Objectivity The studies are usually developed by parties with vested interests and without the tempering perspective of the other project party Representative value Is there a strong correlation between what is measured in the study and the nature of the claim? Addressed in applicability section Timeliness If the data used in the study is very old it may be unreliable. Intervening variables If the study ignores experience, project size or scope then it may not be credible to the applied situation
  18. BLS 1940’s study Based on the manufacturing industry; not construction Highly repetitive work and required little decision making MCAA used this data when it issued bulletin 18A in 1968 which is also listed in Appendix D ***Request copyright *****
  19. The BRT data was from a single project Also, The USACE Modification Impact Evaluation Guide is also listed in Appendix D; however it was rescinded in 1996.
  20. Because the studies can be extremely specific, it is important to substantiate your calculation every way possible. The best way is to compare your calculations using another quantification method. MCAA recommends a claim prepare a modified total cost method analysis of productivity loss as a sanity check on the estimate loss resulting from using the MCAA factors. Source: Change Orders Productivity Overtime – A Primer for the Construction Industry (MCAA 2012) Id. At 99. Lets look at an example…. NEXT SLIDE
  21. Fairly simple concept but lets run through an example: EXAMPLE: Specialty Industry Study  $500K Modified Total Cost  $100K BAD Modified Total Cost $525K GOOD No matter the outcome, you should check your results with another method of quantification and analyze the results.
  22. Contemporaneous Documentation The more the better. If you can provide detailed project records for the period during which the disruption occurs then your job gets much easier Also improves the likelihood you will be able to use one of the preferred quantification methods Expert Testimony Will probably be required if dispute is escalated
  23. As with all productivity loss calculation methods, the absolute top priority is that the claimant demonstrates entitlement Justify method of quantification Demonstrate the study used is applicable to the given situation Demonstrates representative value Establish that the study is credible Show the resultant calculates are reasonable by comparing them with a less-preferred method