Turnkey Solutions – Case Study Refurbishment of ø20m fixed half bridge column mounted primary settlement tank scrapers
Introduction Scottish Water urgently needed to replace two scrapers that had fallen into disrepair at a sewage treatment works near Glasgow. A main contract was awarded to GMJV who sourced tenders from the marketplace for the refurbishment of the scrapers. As a result Xm Services became involved in the tendering process and was eventually awarded a contract to undertake the refurbishment.
Poorly performing primary settlement tank scraper
Primary settlement tank scraper with collapsed scum skimming device Sep Oct Nov Dec Jan Feb
The root cause of poor performance in primary treatment process was the use of peripheral rollers and scum board to support scum skimming arrangement. The peripheral rollers derailed from the scum board generating excessive forces at the point where the scum skimmer arrangement was fixed to the centrally located diffuser drum causing it to collapse.
Detailed Design In order to improve the robustness of the scraper the scum skimming arrangement was designed so that it is supported by the rotating scraper arm
Manufacture of Scrapers Xm Services worked closely with both its suppliers and GMJV throughout the manufacturing phase: Conducting regular project schedule reviews and updates to monitor and control the manufacturing process Perform factory acceptance tests to ensure conformance with: design documentation WIMES 2.01 data sheets EC standards
Manufacture of Scrapers
Scraper Refurbishment Decommissioning, removal and disposal of existing scrapers: Preparation of site risk assessments, method statements and lift plan for inclusion within the contract H&S file Site supervision and induction of all personnel Provision of confined space qualified personnel to work inside the settlement tank Provision of qualified first aider Conducting daily toolbox talks Daily issuing and closure of permits to work Cranage and execution of contract lift Scrap disposal
Sep Oct Nov Dec Jan Feb
Sep Oct Nov Dec Jan Feb
Sep Oct Nov Dec Jan Feb
Sep Oct- Nov- Dec Jan Feb
Scraper Refurbishment Installation and commissioning new scrapers: Unloading, unpacking and storage of equipment Assembly Installation No load site acceptance tests Full load commissioning tests Customer acceptance and handover
Sep Oct- Nov- Dec Jan Feb
Sep Oct- Nov- Dec Jan Feb
Sep Oct- Nov- Dec Jan Feb
Sep Oct- Nov- Dec Jan Feb
Sep Oct- Nov- Dec Jan Feb
Sep Oct- Nov- Dec Jan Feb
Sep Oct- Nov- Dec Jan Feb

Turnkey M&E Installation Ww Tw

  • 1.
    Turnkey Solutions –Case Study Refurbishment of ø20m fixed half bridge column mounted primary settlement tank scrapers
  • 2.
    Introduction Scottish Waterurgently needed to replace two scrapers that had fallen into disrepair at a sewage treatment works near Glasgow. A main contract was awarded to GMJV who sourced tenders from the marketplace for the refurbishment of the scrapers. As a result Xm Services became involved in the tendering process and was eventually awarded a contract to undertake the refurbishment.
  • 3.
    Poorly performing primarysettlement tank scraper
  • 4.
    Primary settlement tankscraper with collapsed scum skimming device Sep Oct Nov Dec Jan Feb
  • 5.
    The root causeof poor performance in primary treatment process was the use of peripheral rollers and scum board to support scum skimming arrangement. The peripheral rollers derailed from the scum board generating excessive forces at the point where the scum skimmer arrangement was fixed to the centrally located diffuser drum causing it to collapse.
  • 6.
    Detailed Design Inorder to improve the robustness of the scraper the scum skimming arrangement was designed so that it is supported by the rotating scraper arm
  • 7.
    Manufacture of ScrapersXm Services worked closely with both its suppliers and GMJV throughout the manufacturing phase: Conducting regular project schedule reviews and updates to monitor and control the manufacturing process Perform factory acceptance tests to ensure conformance with: design documentation WIMES 2.01 data sheets EC standards
  • 8.
  • 9.
    Scraper Refurbishment Decommissioning,removal and disposal of existing scrapers: Preparation of site risk assessments, method statements and lift plan for inclusion within the contract H&S file Site supervision and induction of all personnel Provision of confined space qualified personnel to work inside the settlement tank Provision of qualified first aider Conducting daily toolbox talks Daily issuing and closure of permits to work Cranage and execution of contract lift Scrap disposal
  • 10.
    Sep Oct NovDec Jan Feb
  • 11.
    Sep Oct NovDec Jan Feb
  • 12.
    Sep Oct NovDec Jan Feb
  • 13.
    Sep Oct- Nov-Dec Jan Feb
  • 14.
    Scraper Refurbishment Installationand commissioning new scrapers: Unloading, unpacking and storage of equipment Assembly Installation No load site acceptance tests Full load commissioning tests Customer acceptance and handover
  • 15.
    Sep Oct- Nov-Dec Jan Feb
  • 16.
    Sep Oct- Nov-Dec Jan Feb
  • 17.
    Sep Oct- Nov-Dec Jan Feb
  • 18.
    Sep Oct- Nov-Dec Jan Feb
  • 19.
    Sep Oct- Nov-Dec Jan Feb
  • 20.
    Sep Oct- Nov-Dec Jan Feb
  • 21.
    Sep Oct- Nov-Dec Jan Feb