Ravi Prakash is a civil engineer with 11 years of experience in India and Qatar. He is currently working as an engineer for Salini Impregilo in Qatar on the Red Line North Underground Metro project. Previously he has worked on tunneling and underground metro projects in India and Qatar. He is seeking new career opportunities in civil engineering with a growth-oriented organization. He has expertise in underground excavation, reinforced concrete works, bridge construction, and project management.
The document summarizes a project to construct an underground service corridor in New Delhi using the top-down construction method. Key points include:
- The corridor will run from B.K.S. Marg to Panchkuian Road to Barakhamba Road to Janpath Lane to provide centralized access for utility lines.
- Top-down construction involves first boring guide walls, then excavating from the top down in stages to place reinforced concrete panels.
- Challenges include working around existing utilities, encroachments, and structurally weak buildings nearby.
- Safety measures include pumps to prevent flooding, fire suppression, and CCTV for surveillance. The corridor is designed to minimize future disruptions
Western Works Construction Liaison Committee Meeting - September 2017Crosstown TO
The document provides updates on ongoing construction works for the Crosstown LRT project in September 2017, including:
1) Works at the Maintenance and Storage Facility, Mount Dennis Station, the railway corridor, West Portal and elevated guideway, Keelesdale Station, and Caledonia Station.
2) Details on concrete pouring for the LRT tunnel invert and fit out, including delivery, laying of rebar, and pouring in stages.
3) Notices of works including pile driving and road/sidewalk closures at specific locations.
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017Crosstown TO
The document provides construction updates for the Crosstown LRT project in the Avenue Road area in October 2017. Key activities include:
- Excavation and tunnel backfilling continuing at Avenue Station.
- Dewatering system installation requiring overnight lane closures on Eglinton Ave W from Braemar to Lascelles in October.
- Sewer lining work requiring overnight work from Braemar to Lascelles in October/November.
- Instrumentation installation continuing from Braemar to Lascelles.
- Watermain lining and valve installation work in October/November requiring some overnight work.
- Tunnel backfilling involving drilling and concrete pouring in the Highbourne area in October/
SC&RA’s Rigging Job of the Year designation is one of the most sought after awards within the crane and rigging industry. This year’s competition included 15 companies from 3 countries vying for this honor. This session showcased the three winning entries which include the removal of 10 platforms on a control tower at McCarran International Airport in Las Vegas, Nevada; the movement of the 87-year old Sellwood Bridge in Portland, Oregon, from its permanent concrete supports to temporary steel piers making way for new bridge construction across the Willamette River; and the recovery of the cruise ship Costa Concordia, which was resting on an underwater rock ledge off the coast of Isola Del Giglio in Italy.
Check out these presentations! They are a testament to the commitment and ingenuity at the heart of our industry!
Under $150,000 - Barnhart Crane & Rigging
Between $150,000 - $750,000 - Omega Morgan
Over $750,000 - Fagioli
Western Works Construction Liaison Committee - November 2017Crosstown TO
The document provides updates on construction progress for various aspects of the Crosstown LRT project, including Caledonia Station, Keelesdale Station, West Portal, the elevated guideway, tunnel fit out, Mount Dennis Station, the railway corridor, and the Eglinton Maintenance and Storage Facility. Work discussed includes dewatering, excavation, tunnel demolition, utility relocation, foundation work, track installation, and structure erection. The agenda covers ongoing construction activities from November to December 2017 and beyond for the Western section of the light rail line.
Chaplin & Avenue Construction Liaison Committee Meeting - November 2017Crosstown TO
The document provides updates on construction activities for the Crosstown LRT project in the Avenue Road area in November and December 2017. Short term activities include connection borehole work, dewatering, sewer bypass and lining, watermain lining, and tunnel backfilling. Long term activities include the start of 24 hour mining at the Avenue Station secondary and main entrances. Renderings and maps show the progress and design of the Avenue Station. The document also provides a Chaplin Station construction update and concept drawing, outlining utility relocation, piling work, and traffic staging changes planned for that area.
Leaside & Laird Stations Construction Liaison Committee - October 2017Crosstown TO
The document provides updates on construction progress at three Crosstown LRT stations - Leaside, EEB3, and Laird - in Q3 and Q4 of 2017. At Leaside Station, stage 1B support of excavation was underway with completion expected in November/December. Wet utility relocations were ongoing. At EEB3, tunnel invert pouring was continuing with concrete delivery. Mining operations were proceeding at the secondary entrance of Laird Station, with mining to continue at both entrances through late 2019. Progress photos from September and October 2017 were also included.
Ravi Prakash is a civil engineer with 11 years of experience in India and Qatar. He is currently working as an engineer for Salini Impregilo in Qatar on the Red Line North Underground Metro project. Previously he has worked on tunneling and underground metro projects in India and Qatar. He is seeking new career opportunities in civil engineering with a growth-oriented organization. He has expertise in underground excavation, reinforced concrete works, bridge construction, and project management.
The document summarizes a project to construct an underground service corridor in New Delhi using the top-down construction method. Key points include:
- The corridor will run from B.K.S. Marg to Panchkuian Road to Barakhamba Road to Janpath Lane to provide centralized access for utility lines.
- Top-down construction involves first boring guide walls, then excavating from the top down in stages to place reinforced concrete panels.
- Challenges include working around existing utilities, encroachments, and structurally weak buildings nearby.
- Safety measures include pumps to prevent flooding, fire suppression, and CCTV for surveillance. The corridor is designed to minimize future disruptions
Western Works Construction Liaison Committee Meeting - September 2017Crosstown TO
The document provides updates on ongoing construction works for the Crosstown LRT project in September 2017, including:
1) Works at the Maintenance and Storage Facility, Mount Dennis Station, the railway corridor, West Portal and elevated guideway, Keelesdale Station, and Caledonia Station.
2) Details on concrete pouring for the LRT tunnel invert and fit out, including delivery, laying of rebar, and pouring in stages.
3) Notices of works including pile driving and road/sidewalk closures at specific locations.
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017Crosstown TO
The document provides construction updates for the Crosstown LRT project in the Avenue Road area in October 2017. Key activities include:
- Excavation and tunnel backfilling continuing at Avenue Station.
- Dewatering system installation requiring overnight lane closures on Eglinton Ave W from Braemar to Lascelles in October.
- Sewer lining work requiring overnight work from Braemar to Lascelles in October/November.
- Instrumentation installation continuing from Braemar to Lascelles.
- Watermain lining and valve installation work in October/November requiring some overnight work.
- Tunnel backfilling involving drilling and concrete pouring in the Highbourne area in October/
SC&RA’s Rigging Job of the Year designation is one of the most sought after awards within the crane and rigging industry. This year’s competition included 15 companies from 3 countries vying for this honor. This session showcased the three winning entries which include the removal of 10 platforms on a control tower at McCarran International Airport in Las Vegas, Nevada; the movement of the 87-year old Sellwood Bridge in Portland, Oregon, from its permanent concrete supports to temporary steel piers making way for new bridge construction across the Willamette River; and the recovery of the cruise ship Costa Concordia, which was resting on an underwater rock ledge off the coast of Isola Del Giglio in Italy.
Check out these presentations! They are a testament to the commitment and ingenuity at the heart of our industry!
Under $150,000 - Barnhart Crane & Rigging
Between $150,000 - $750,000 - Omega Morgan
Over $750,000 - Fagioli
Western Works Construction Liaison Committee - November 2017Crosstown TO
The document provides updates on construction progress for various aspects of the Crosstown LRT project, including Caledonia Station, Keelesdale Station, West Portal, the elevated guideway, tunnel fit out, Mount Dennis Station, the railway corridor, and the Eglinton Maintenance and Storage Facility. Work discussed includes dewatering, excavation, tunnel demolition, utility relocation, foundation work, track installation, and structure erection. The agenda covers ongoing construction activities from November to December 2017 and beyond for the Western section of the light rail line.
Chaplin & Avenue Construction Liaison Committee Meeting - November 2017Crosstown TO
The document provides updates on construction activities for the Crosstown LRT project in the Avenue Road area in November and December 2017. Short term activities include connection borehole work, dewatering, sewer bypass and lining, watermain lining, and tunnel backfilling. Long term activities include the start of 24 hour mining at the Avenue Station secondary and main entrances. Renderings and maps show the progress and design of the Avenue Station. The document also provides a Chaplin Station construction update and concept drawing, outlining utility relocation, piling work, and traffic staging changes planned for that area.
Leaside & Laird Stations Construction Liaison Committee - October 2017Crosstown TO
The document provides updates on construction progress at three Crosstown LRT stations - Leaside, EEB3, and Laird - in Q3 and Q4 of 2017. At Leaside Station, stage 1B support of excavation was underway with completion expected in November/December. Wet utility relocations were ongoing. At EEB3, tunnel invert pouring was continuing with concrete delivery. Mining operations were proceeding at the secondary entrance of Laird Station, with mining to continue at both entrances through late 2019. Progress photos from September and October 2017 were also included.
Leaside & Laird Construction Liaison Committee Meeting - September 2017Crosstown TO
The document provides updates on construction activities at three LRT stations - Leaside, EEB3, and Laird - in Q3 2017. At Leaside Station, stage one support of excavation is underway and will be completed in stages through early 2018. Concrete pouring will begin at the EEB3 site in September for five months to form tracks. Mining operations are ongoing at Laird Station and will continue into late 2019. Sewer lining work with potential odours is also outlined. Progress photos of excavations at Leaside and Laird stations are included.
Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017Crosstown TO
This document provides information about Metrolinx's Crosstown LRT project, including:
- A description of the key aspects being built, such as underground and surface stations, maintenance facility, and route.
- An emphasis on safety as the top priority during construction.
- Details about the project's design principles and focus on sustainability, environment, and community benefits.
- Expected construction milestones and activities in 2017-2018 for various sections, including tunnel fit out, stations, and elevated guideways.
- Plans to minimize impacts on local businesses and support the community during construction.
Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018Crosstown TO
The document provides updates on upcoming construction activities for the Crosstown LRT project in January and February 2018. Short term activities in January include dewatering and trenching work, sewer bypassing and lining, watermain valve installation and lining. Tunnel backfilling work will involve drilling boreholes in late January followed by concrete pouring. Mining operations at the Avenue Station secondary entrance will continue 24 hours per day. At Chaplin Station, guidewall breaking out and utility work will occur in January with traffic changes planned for mid-January and early March.
This curriculum vitae is for Mr. Manoj Kumar, a mechanical engineer with 18 years of experience in steel and oil refineries utility projects. He is currently a Deputy Manager at Jindal Steel & Power Limited, Angul, Orissa, responsible for erection and commissioning of utility projects for RMHS. Previously he has worked on piping erection projects for various companies and has experience managing projects, resources, piping fabrication, erection and commissioning. He holds a Diploma in Mechanical Engineering and is seeking a challenging position that allows him to contribute his skills and experience.
Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...Crosstown TO
The document provides information on Metrolinx's Draft 2041 Regional Transportation Plan and details about the Crosstown LRT project in Toronto. Key points include:
- Metrolinx is updating its Regional Transportation Plan and is seeking public input on the Draft 2041 Plan.
- The Crosstown LRT will be a 19-kilometer light rail line with 25 stations, running mostly underground in Toronto.
- Construction updates are provided for 2017-2018, including tunneling work, track installation, and station construction at sites like Mount Dennis.
- Community benefits of the project include employment opportunities, support for social enterprises and local businesses, and community improvements.
Eglinton & Mount Pleasant Construction Liaison Committee - November 2017Crosstown TO
The document provides updates on construction activities for the Eglinton Crosstown LRT project, including:
1) Eglinton Station updates such as ongoing early morning deliveries and shoring work, and upcoming shoring stage 2 and THESL relocation work.
2) Mount Pleasant Station updates including ongoing support of excavation and launch shaft construction, and upcoming receiving shaft construction and tunneling/storm sewer installation beginning in January 2018.
3) Details on construction staging and progress photos at Mount Pleasant Station showing areas of ongoing work like the launch shaft and upcoming work like the receiving shaft.
Leaside & Laird Construction Liaison Committee - November 2017Crosstown TO
The document provides updates on construction progress for the Crosstown LRT project. It summarizes work underway at Leaside Station including ongoing support of excavation and future traffic staging changes. Tunnel fit out work at EEB3 is also discussed, showing concrete delivery and pouring of the tunnel invert. Updates are given for Laird Station, including 24/7 mining operations and progress photos of the main and secondary entrances. The document concludes with information on marketing support for local businesses through an Experience Eglinton ad campaign and signage during construction.
Eglinton and Mt Pleasant Stations Open House - October 2017Crosstown TO
The document provides information about Metrolinx's Draft 2041 Regional Transportation Plan and the Eglinton Crosstown LRT project. Metrolinx is updating its Regional Transportation Plan to outline how to build an integrated transportation system across the Greater Toronto and Hamilton Area. The document discusses the Crosstown LRT, including details of its design, safety measures, stations (Mount Pleasant and Eglinton), and community benefits programs. It encourages public review and feedback on the draft transportation plan.
Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017Crosstown TO
The document provides updates on construction activities at the Avenue Station and Chaplin Station sites for the Crosstown LRT project. At Avenue Station, mining will begin in late 2017 and continue through 2019, and various surface works including dewatering, sewer lining, and watermain lining will occur in September/October 2017. Noise reduction plans are in place, and residential responses will be addressed. At Chaplin Station, piling and utility relocation will continue in Q3 2017, with traffic staging and additional works planned for Q4 2017. Overnight work is proposed for sanitary sewer diversions to expedite the work and reduce public odor exposure.
SELI Overseas set a new record of 1,005m of tunnel excavation in a single month using a TBM at the Xe-Pian Xe-Namnoy Hydroelectric Project in Laos. The project involves excavating an 11.5km headrace tunnel through difficult ground conditions. SELI Overseas and TBM manufacturer Terratec have worked closely to overcome challenges through the design, operation, and support of the TBM. Power issues initially slowed progress but were resolved through on-site power generation. Segment production and transport have proceeded without issues to support the TBM advance.
The document provides an update on construction projects for SJRA GRP Surface Water Facilities as of November 2012. It details that total costs so far are $42,874,840 with no change orders, and the total estimated cost is $190,078,395 against a budget of $191,000,000. It also notes that completion is scheduled for June 1, 2015 and includes photos showing progress including steel casing installation, rebar work, concrete pouring, and aerial views of the water treatment plant and pump station work zones as well as the raw water intake bridge connection.
Forest Hill Station Open House - June 2017Crosstown TO
The document provides information about the construction of the Eglinton Crosstown LRT project in Toronto. It discusses Metrolinx's regional transportation plan, the project details including a 19km LRT route with underground and surface stations, and safety and accessibility features. It outlines the construction methods using cut-and-cover and mined tunnels. It highlights 2017 construction milestones and provides renderings and progress updates for the Forest Hill station.
This document provides a summary of the submitter's professional experience and qualifications as a surveyor over 18 years. It details his experience working on infrastructure projects in the UAE and Pakistan, including highrise buildings, substations, pipelines, roads, bridges, and more. It also lists the surveying instruments he is qualified to use, such as total stations.
- Amir Bakhsh Mirani is seeking a managerial position in civil engineering and has over 36 years of experience. His experience includes managing major dam and irrigation projects across Sindh and Balochistan for WAPDA. Some of the key projects he oversaw include the Darawat Dam, Nai Gaj Dam, Jinnah Hydro Power Project, and Right Bank Outfall Drain. He has extensive experience managing all aspects of large civil engineering projects from design to construction and maintenance.
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017Crosstown TO
1) The Crosstown LRT will be a 19-kilometre light rail line running east-west across Toronto, with 15 underground stations and 10 surface stops.
2) Construction involves distinct phases including preliminary works, utility relocations, tunnel excavation, station construction, track installation, and testing.
3) Recent progress includes completing tunnel construction, ongoing station construction activities, and beginning excavation of station boxes in 2017. Upcoming milestones are excavating 1 million tons of material and advancing utility relocations and guideway installation.
Zach Maddox is a 25-year-old site engineer with over 4 years of experience in the construction industry. He has worked on major infrastructure projects in Australia and the UK for tier 1 companies such as Costain Skanska JV, Leightons, and Thiess. Maddox values respect, honesty, integrity, resilience, strong work ethic, initiative, loyalty, and adaptability. His experience includes tunnel construction, concrete works, bridge construction, piling, and roadworks. Maddox has a Bachelor's degree in Civil Engineering from the University of Queensland.
1) The construction of tunnels for the Kallang/Paya Lebar Expressway (KPE) project faced many challenges due to the area's geology and existing infrastructure, with one of the greatest challenges being the construction of tunnels under the Pelton Canal.
2) A half-box tunnel construction method was used to build the tunnels under the Pelton Canal, which involved diverting the canal, installing retaining walls and piles, and excavating each half of the tunnel in stages while ensuring the stability of the temporary diversion structures.
3) The tunnel construction between PIE and Ubi Road 2 is now over 85% complete, with various sections of tunnel and infrastructure works at different stages of progress, and rein
This document contains personal and professional information about Ahmed Mahmoud Ahmed. He is an Egyptian national, married with three children. His qualifications include a BSc in civil engineering from Zigzag University. He has over 15 years of experience managing bridge and road construction projects in Saudi Arabia and Egypt for companies like Advanced Construction Co. and Nahdat Al-Emaar Contracting Co. His roles have included project manager, bridges construction manager, and structural engineer. He is proficient in AutoCAD, Microsoft Office, and speaks Arabic and English.
Western Works - Construction Liaison Committee Meeting - May 2017Crosstown TO
The document provides an overview and progress update of the Eglinton Crosstown LRT project. Key points discussed include the maintenance and storage facility, Mount Dennis Station, tunnel construction, and progress at Keelesdale and Caledonia stations. Updates on concrete pouring in the tunnels and foundation work at various sites are also provided.
Caledonia Fairbank Oakwood Open House Deck October 2017 finalCrosstown TO
The document provides information on Metrolinx's Draft 2041 Regional Transportation Plan, as well as details about the Crosstown LRT project including construction updates and milestones. Key points include:
- Metrolinx is updating its Regional Transportation Plan and is seeking public input on the Draft 2041 Plan.
- The Crosstown LRT will be a 19-kilometer light rail line with underground and surface stations, linking to other transit systems.
- Construction updates are provided for 2017 milestones and activities at various stations along the route.
- Community benefits programs are aimed at positively impacting disadvantaged communities through employment, social procurement, and community investments.
El documento describe las rondas infantiles, juegos tradicionales cantados y bailados en círculo. Ofrecen beneficios como fomentar la unión entre los niños y ayudar a conocer su cuerpo y desarrollar habilidades motrices y sociales. También presenta varias rondas populares con sus letras y movimientos.
Este documento trata sobre dos tipos de contaminación: la contaminación sónica y la contaminación del suelo. La contaminación sónica se refiere al exceso de ruido producido por la actividad humana como la construcción y el transporte que puede causar problemas de audición, alteraciones del sueño y disminución de la concentración. La contaminación del suelo implica la alteración del estado natural del suelo debido a sustancias como plásticos, solventes o plaguicidas añadidos por el hombre, lo que puede dar lugar a la pérdida de la cub
Leaside & Laird Construction Liaison Committee Meeting - September 2017Crosstown TO
The document provides updates on construction activities at three LRT stations - Leaside, EEB3, and Laird - in Q3 2017. At Leaside Station, stage one support of excavation is underway and will be completed in stages through early 2018. Concrete pouring will begin at the EEB3 site in September for five months to form tracks. Mining operations are ongoing at Laird Station and will continue into late 2019. Sewer lining work with potential odours is also outlined. Progress photos of excavations at Leaside and Laird stations are included.
Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017Crosstown TO
This document provides information about Metrolinx's Crosstown LRT project, including:
- A description of the key aspects being built, such as underground and surface stations, maintenance facility, and route.
- An emphasis on safety as the top priority during construction.
- Details about the project's design principles and focus on sustainability, environment, and community benefits.
- Expected construction milestones and activities in 2017-2018 for various sections, including tunnel fit out, stations, and elevated guideways.
- Plans to minimize impacts on local businesses and support the community during construction.
Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018Crosstown TO
The document provides updates on upcoming construction activities for the Crosstown LRT project in January and February 2018. Short term activities in January include dewatering and trenching work, sewer bypassing and lining, watermain valve installation and lining. Tunnel backfilling work will involve drilling boreholes in late January followed by concrete pouring. Mining operations at the Avenue Station secondary entrance will continue 24 hours per day. At Chaplin Station, guidewall breaking out and utility work will occur in January with traffic changes planned for mid-January and early March.
This curriculum vitae is for Mr. Manoj Kumar, a mechanical engineer with 18 years of experience in steel and oil refineries utility projects. He is currently a Deputy Manager at Jindal Steel & Power Limited, Angul, Orissa, responsible for erection and commissioning of utility projects for RMHS. Previously he has worked on piping erection projects for various companies and has experience managing projects, resources, piping fabrication, erection and commissioning. He holds a Diploma in Mechanical Engineering and is seeking a challenging position that allows him to contribute his skills and experience.
Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...Crosstown TO
The document provides information on Metrolinx's Draft 2041 Regional Transportation Plan and details about the Crosstown LRT project in Toronto. Key points include:
- Metrolinx is updating its Regional Transportation Plan and is seeking public input on the Draft 2041 Plan.
- The Crosstown LRT will be a 19-kilometer light rail line with 25 stations, running mostly underground in Toronto.
- Construction updates are provided for 2017-2018, including tunneling work, track installation, and station construction at sites like Mount Dennis.
- Community benefits of the project include employment opportunities, support for social enterprises and local businesses, and community improvements.
Eglinton & Mount Pleasant Construction Liaison Committee - November 2017Crosstown TO
The document provides updates on construction activities for the Eglinton Crosstown LRT project, including:
1) Eglinton Station updates such as ongoing early morning deliveries and shoring work, and upcoming shoring stage 2 and THESL relocation work.
2) Mount Pleasant Station updates including ongoing support of excavation and launch shaft construction, and upcoming receiving shaft construction and tunneling/storm sewer installation beginning in January 2018.
3) Details on construction staging and progress photos at Mount Pleasant Station showing areas of ongoing work like the launch shaft and upcoming work like the receiving shaft.
Leaside & Laird Construction Liaison Committee - November 2017Crosstown TO
The document provides updates on construction progress for the Crosstown LRT project. It summarizes work underway at Leaside Station including ongoing support of excavation and future traffic staging changes. Tunnel fit out work at EEB3 is also discussed, showing concrete delivery and pouring of the tunnel invert. Updates are given for Laird Station, including 24/7 mining operations and progress photos of the main and secondary entrances. The document concludes with information on marketing support for local businesses through an Experience Eglinton ad campaign and signage during construction.
Eglinton and Mt Pleasant Stations Open House - October 2017Crosstown TO
The document provides information about Metrolinx's Draft 2041 Regional Transportation Plan and the Eglinton Crosstown LRT project. Metrolinx is updating its Regional Transportation Plan to outline how to build an integrated transportation system across the Greater Toronto and Hamilton Area. The document discusses the Crosstown LRT, including details of its design, safety measures, stations (Mount Pleasant and Eglinton), and community benefits programs. It encourages public review and feedback on the draft transportation plan.
Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017Crosstown TO
The document provides updates on construction activities at the Avenue Station and Chaplin Station sites for the Crosstown LRT project. At Avenue Station, mining will begin in late 2017 and continue through 2019, and various surface works including dewatering, sewer lining, and watermain lining will occur in September/October 2017. Noise reduction plans are in place, and residential responses will be addressed. At Chaplin Station, piling and utility relocation will continue in Q3 2017, with traffic staging and additional works planned for Q4 2017. Overnight work is proposed for sanitary sewer diversions to expedite the work and reduce public odor exposure.
SELI Overseas set a new record of 1,005m of tunnel excavation in a single month using a TBM at the Xe-Pian Xe-Namnoy Hydroelectric Project in Laos. The project involves excavating an 11.5km headrace tunnel through difficult ground conditions. SELI Overseas and TBM manufacturer Terratec have worked closely to overcome challenges through the design, operation, and support of the TBM. Power issues initially slowed progress but were resolved through on-site power generation. Segment production and transport have proceeded without issues to support the TBM advance.
The document provides an update on construction projects for SJRA GRP Surface Water Facilities as of November 2012. It details that total costs so far are $42,874,840 with no change orders, and the total estimated cost is $190,078,395 against a budget of $191,000,000. It also notes that completion is scheduled for June 1, 2015 and includes photos showing progress including steel casing installation, rebar work, concrete pouring, and aerial views of the water treatment plant and pump station work zones as well as the raw water intake bridge connection.
Forest Hill Station Open House - June 2017Crosstown TO
The document provides information about the construction of the Eglinton Crosstown LRT project in Toronto. It discusses Metrolinx's regional transportation plan, the project details including a 19km LRT route with underground and surface stations, and safety and accessibility features. It outlines the construction methods using cut-and-cover and mined tunnels. It highlights 2017 construction milestones and provides renderings and progress updates for the Forest Hill station.
This document provides a summary of the submitter's professional experience and qualifications as a surveyor over 18 years. It details his experience working on infrastructure projects in the UAE and Pakistan, including highrise buildings, substations, pipelines, roads, bridges, and more. It also lists the surveying instruments he is qualified to use, such as total stations.
- Amir Bakhsh Mirani is seeking a managerial position in civil engineering and has over 36 years of experience. His experience includes managing major dam and irrigation projects across Sindh and Balochistan for WAPDA. Some of the key projects he oversaw include the Darawat Dam, Nai Gaj Dam, Jinnah Hydro Power Project, and Right Bank Outfall Drain. He has extensive experience managing all aspects of large civil engineering projects from design to construction and maintenance.
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017Crosstown TO
1) The Crosstown LRT will be a 19-kilometre light rail line running east-west across Toronto, with 15 underground stations and 10 surface stops.
2) Construction involves distinct phases including preliminary works, utility relocations, tunnel excavation, station construction, track installation, and testing.
3) Recent progress includes completing tunnel construction, ongoing station construction activities, and beginning excavation of station boxes in 2017. Upcoming milestones are excavating 1 million tons of material and advancing utility relocations and guideway installation.
Zach Maddox is a 25-year-old site engineer with over 4 years of experience in the construction industry. He has worked on major infrastructure projects in Australia and the UK for tier 1 companies such as Costain Skanska JV, Leightons, and Thiess. Maddox values respect, honesty, integrity, resilience, strong work ethic, initiative, loyalty, and adaptability. His experience includes tunnel construction, concrete works, bridge construction, piling, and roadworks. Maddox has a Bachelor's degree in Civil Engineering from the University of Queensland.
1) The construction of tunnels for the Kallang/Paya Lebar Expressway (KPE) project faced many challenges due to the area's geology and existing infrastructure, with one of the greatest challenges being the construction of tunnels under the Pelton Canal.
2) A half-box tunnel construction method was used to build the tunnels under the Pelton Canal, which involved diverting the canal, installing retaining walls and piles, and excavating each half of the tunnel in stages while ensuring the stability of the temporary diversion structures.
3) The tunnel construction between PIE and Ubi Road 2 is now over 85% complete, with various sections of tunnel and infrastructure works at different stages of progress, and rein
This document contains personal and professional information about Ahmed Mahmoud Ahmed. He is an Egyptian national, married with three children. His qualifications include a BSc in civil engineering from Zigzag University. He has over 15 years of experience managing bridge and road construction projects in Saudi Arabia and Egypt for companies like Advanced Construction Co. and Nahdat Al-Emaar Contracting Co. His roles have included project manager, bridges construction manager, and structural engineer. He is proficient in AutoCAD, Microsoft Office, and speaks Arabic and English.
Western Works - Construction Liaison Committee Meeting - May 2017Crosstown TO
The document provides an overview and progress update of the Eglinton Crosstown LRT project. Key points discussed include the maintenance and storage facility, Mount Dennis Station, tunnel construction, and progress at Keelesdale and Caledonia stations. Updates on concrete pouring in the tunnels and foundation work at various sites are also provided.
Caledonia Fairbank Oakwood Open House Deck October 2017 finalCrosstown TO
The document provides information on Metrolinx's Draft 2041 Regional Transportation Plan, as well as details about the Crosstown LRT project including construction updates and milestones. Key points include:
- Metrolinx is updating its Regional Transportation Plan and is seeking public input on the Draft 2041 Plan.
- The Crosstown LRT will be a 19-kilometer light rail line with underground and surface stations, linking to other transit systems.
- Construction updates are provided for 2017 milestones and activities at various stations along the route.
- Community benefits programs are aimed at positively impacting disadvantaged communities through employment, social procurement, and community investments.
El documento describe las rondas infantiles, juegos tradicionales cantados y bailados en círculo. Ofrecen beneficios como fomentar la unión entre los niños y ayudar a conocer su cuerpo y desarrollar habilidades motrices y sociales. También presenta varias rondas populares con sus letras y movimientos.
Este documento trata sobre dos tipos de contaminación: la contaminación sónica y la contaminación del suelo. La contaminación sónica se refiere al exceso de ruido producido por la actividad humana como la construcción y el transporte que puede causar problemas de audición, alteraciones del sueño y disminución de la concentración. La contaminación del suelo implica la alteración del estado natural del suelo debido a sustancias como plásticos, solventes o plaguicidas añadidos por el hombre, lo que puede dar lugar a la pérdida de la cub
Este documento trata sobre la contaminación del agua y el aire. Explica que la contaminación ocurre cuando se altera el estado natural del medio ambiente, generalmente como resultado de la actividad humana. Identifica varios tipos de contaminantes del agua y el aire, como agroquímicos, desechos industriales y de vehículos, y describe los efectos negativos que pueden tener en la salud humana y el medio ambiente.
A request for more information.
An excuse.
A buying signal.
A counter tactic to encounter a push.
MOST COMMON OBJECTIONS:
1.Google AdWords is too expensive
2.How can you assure that the ROI is good?
3.Am I competitive with a small budget?
4.No more marketing budget
5.My product / service is very niche
6. Isn’t the market too saturated?
7. I’m already in the Organic Listings
8.Had bad experience earlier
9.Doing it myself, no need to outsource
10.My business is Word of Mouth
11.My business is seasonal, bad time now
12. I want to have the top position
13. I don’t want to pay for irrelevant click
14. I / My customers don’t click on ads
This document provides details on tunnel construction methodology for a tunnel being built between Didwana and Lalsot Railway stations in India. It discusses the local geology, which includes soils, boulders and metamorphic rocks. For the tunnel construction between chainages 38/720 to 40/860, the document outlines the execution plan and engineering considerations. It describes the sequence of excavation using both full-face and heading-and-benching methods depending on ground conditions, and provides details on construction activities like portal establishment, underground excavation with drilling and blasting, rock bolting, shotcreting, steel support installation and concrete lining.
The document provides an update on maintenance work being done on the Injo Slip road. It summarizes that:
1) The first defective 1800mm diameter culvert was replaced with a new 1500mm diameter culvert, though gabion basket headwalls were not yet constructed due to minor delays.
2) Photos document the replacement of the culvert and backfilling of the road with boulders and gravel.
3) Work is still in progress to complete gabion baskets, replace two more culverts, and finish backfilling and drainage work, though the project was delayed a few days due to lack of supervisors on site.
Presentation about Under-construction Mahakali Bridge Project in 3 days Training Program on Construction and Quality Control of PSC Bridges चैत्र ११,१२,१३ ,२०७७ organized by
Federal Road Supervision and Monitoring Office, Surkhet
The document provides an overview of the Atal Tunnel project in India. It discusses the key details of the project including its location in the Himalayas, length of 9.02km, cost of 3200 crore, and connectivity between Lahaul Spiti valley and other tourist areas. It also summarizes the major construction challenges like the Seri Nala fault zone, high overburden pressures, and extreme weather conditions. Safety features of the tunnel including telephone connections every 150m and fire hydrants every 60m are highlighted.
The document provides an overview of the Atal Tunnel project in India. It discusses the key details of the project including its location in the Himalayas, length of 9.02km, cost of 3200 crore, and ability to handle 3000 cars and 1500 trucks per day. It also summarizes the major construction challenges like dealing with the Seri Nala fault zone, ensuring alignment precision, and addressing extreme weather conditions. Safety features of the tunnel are highlighted such as telephone connections every 150 meters and fire hydrants every 60 meters.
The document summarizes the construction of a box-type slab bridge near Palaya village. The existing drainage pipe bridge was insufficient and damaged, flooding the village during rains. The solution was to remove the pipes and construct a reinforced concrete box bridge instead. Foundation work was done to a depth of 3 meters. A concrete bed was laid and bottom slab with steel reinforcement was constructed. Profile walls and slab will complete the bridge, allowing easy drainage of water from the village farms.
The document summarizes the diversion of Seri Nallah away from the Atal Tunnel alignment in Himachal Pradesh. During construction of the Atal Tunnel, a fault zone was encountered at Seri Nallah, leading to an expert committee recommendation to seal the tunnel lining, divert the nallah, and construct a drainage tunnel. Work began in September 2022 but was stopped due to forest clearance issues. The diversion project involves treating the nallah bed, constructing a drainage tunnel and trench weir, and laying pipes to redirect water flow. Physical progress has been slowed by delays in site handover and material supply issues. Completion is planned for October 2024 after the monsoon season.
PROJECT REPORT ON DESIGN OF A RESIDENTIAL BUILDINGAmritpal Singh
The document provides details of a project report for the design of a residential building in India. It includes an introduction, study area details, floor plans for 1BHK, 2BHK and 3BHK units, specifications, construction process and materials used such as cement, coarse aggregate, fine aggregate, and bricks. The summary is as follows:
The document is a project report for the design of a residential building in India that includes details of the site location, floor plans for different unit types (1BHK, 2BHK, 3BHK), building specifications, construction process, and materials used such as cement, aggregates, and bricks.
The excavation of Tunnel T1 in Sivok-Rangpo Rail Link Project encountered a cavity formation due to a sudden shear zone at chainage 610.8 meters. The cavity initially extended to 608.6 meters before remedial measures were taken to backfill the face and install temporary supports. Further collapses occurred despite efforts to control the cavity, eventually extending it to the surface and creating a ditch approximately 7x7 meters. Monitoring shows the tunnel deformations remain within safe limits. The unexpected shear zone in the complex Himalayan geology was determined to be the cause of the cavity.
Sachin Chitnis has over 25 years of experience as a civil engineer working on infrastructure projects in Gulf and Africa regions. He has extensive experience in areas such as foundations, reinforced concrete, structural steel, drainage, roads, bridges, and land development. His most recent roles include serving as Site Engineer for a large economic zone development project in Qatar from 2015-2016 and working on road projects and bridges in Tanzania from 2013-2015.
Sachin Chitnis has over 25 years of experience as a civil engineer working on infrastructure projects in India, the Middle East, and Africa. He has extensive experience supervising construction of foundations, pipelines, buildings, bridges, and more. His background includes roles as a site engineer on projects in Qatar, Tanzania, Oman, Dubai, and India with budgets up to $900 million.
This presentation provides an overview of repairs being conducted on the Pandoh spillway in Himachal Pradesh. Some key points:
- The spillway experiences significant damage every monsoon season from debris carried by flood waters. Approximately 30,000 square feet is damaged annually.
- A temporary barrier wall is constructed to separate the spillway into sections so repair work can be conducted safely in phases while continuing to release water.
- The damaged areas are assessed and prepared for repair work by cleaning surfaces and reinforcing any exposed rebar.
- Repairs use epoxy mortar and concrete matching the original specifications. Deeper damage over 2 inches is repaired with concrete.
- Over 30 years,
The presentation provided an overview of the Mohmand Dam Hydropower Project, including project details, progress, challenges, and issues delaying completion. Key points included: the project involves constructing a 213m dam, diversion tunnels, and powerhouse; major challenges include complex geology and large rockfill quantities; delays have been caused by COVID impacts, tunnel convergence, and contractor performance issues like inadequate planning and resources; critical activities requiring focus are quarry development and tunnel completion; contractual actions may be needed to improve progress.
The document is a field training report submitted by Parab Shubham Vilas to the Department of Civil Engineering at Rajarambapu Institute of Technology. It provides details of the 21-day field training completed at Omkar Constructions Pvt. Ltd. from December 1-21, 2014. The report includes information about the trainee, company, and Crystal Tower project where training took place. It describes various construction works witnessed including casting of PCC, footing, columns, slabs, and beams. Daily schedules outline activities like formwork, shuttering, and quality control measures.
This document provides details about the summer training project undertaken by the author at a construction site of GEE INTERNATIONALS. It summarizes the key aspects of the project which involved construction of government senior secondary school. The project details shared include the EHS safety protocols followed, quality management processes, site planning through drawings and bar charts, and sequencing of construction activities from site clearance to project completion. The summary focuses on the high-level overview and essential details provided in the document.
This document is a project report on ready mix concrete submitted by a group of civil engineering students at their university. It includes an introduction to ready mix concrete, discussing how it provides a precise concrete mixture that is mixed off-site and delivered. The report then covers the history of ready mix concrete, highlighting some key developments. It also discusses the scope and applications of ready mix concrete in construction projects.
The document summarizes information about various construction equipment and methods, including pile driving equipment, concrete batching plants, and tunnel boring machines. It describes different types of piles and pile driving hammers. It provides details on the components and functioning of concrete batching plants and tunnel boring machines. The key methods of tunnel construction discussed are tunnel boring machine (TBM) method and drill-and-blast method.
The document summarizes pending development works and civic issues in the HBR layout, 5th block, 1st stage area. Key points include:
1) Roads and vacant sites need repair and maintenance, including asphalting roads, clearing overgrown vacant lots.
2) Storm water drainage work like fencing and retaining walls is incomplete and drainage is blocked with debris.
3) Other issues include need for bus shelters, street lights, converting an empty lot to a park, and addressing sewage system problems like blocked pipes.
International Conference on NLP, Artificial Intelligence, Machine Learning an...gerogepatton
International Conference on NLP, Artificial Intelligence, Machine Learning and Applications (NLAIM 2024) offers a premier global platform for exchanging insights and findings in the theory, methodology, and applications of NLP, Artificial Intelligence, Machine Learning, and their applications. The conference seeks substantial contributions across all key domains of NLP, Artificial Intelligence, Machine Learning, and their practical applications, aiming to foster both theoretical advancements and real-world implementations. With a focus on facilitating collaboration between researchers and practitioners from academia and industry, the conference serves as a nexus for sharing the latest developments in the field.
Null Bangalore | Pentesters Approach to AWS IAMDivyanshu
#Abstract:
- Learn more about the real-world methods for auditing AWS IAM (Identity and Access Management) as a pentester. So let us proceed with a brief discussion of IAM as well as some typical misconfigurations and their potential exploits in order to reinforce the understanding of IAM security best practices.
- Gain actionable insights into AWS IAM policies and roles, using hands on approach.
#Prerequisites:
- Basic understanding of AWS services and architecture
- Familiarity with cloud security concepts
- Experience using the AWS Management Console or AWS CLI.
- For hands on lab create account on [killercoda.com](https://killercoda.com/cloudsecurity-scenario/)
# Scenario Covered:
- Basics of IAM in AWS
- Implementing IAM Policies with Least Privilege to Manage S3 Bucket
- Objective: Create an S3 bucket with least privilege IAM policy and validate access.
- Steps:
- Create S3 bucket.
- Attach least privilege policy to IAM user.
- Validate access.
- Exploiting IAM PassRole Misconfiguration
-Allows a user to pass a specific IAM role to an AWS service (ec2), typically used for service access delegation. Then exploit PassRole Misconfiguration granting unauthorized access to sensitive resources.
- Objective: Demonstrate how a PassRole misconfiguration can grant unauthorized access.
- Steps:
- Allow user to pass IAM role to EC2.
- Exploit misconfiguration for unauthorized access.
- Access sensitive resources.
- Exploiting IAM AssumeRole Misconfiguration with Overly Permissive Role
- An overly permissive IAM role configuration can lead to privilege escalation by creating a role with administrative privileges and allow a user to assume this role.
- Objective: Show how overly permissive IAM roles can lead to privilege escalation.
- Steps:
- Create role with administrative privileges.
- Allow user to assume the role.
- Perform administrative actions.
- Differentiation between PassRole vs AssumeRole
Try at [killercoda.com](https://killercoda.com/cloudsecurity-scenario/)
Introduction- e - waste – definition - sources of e-waste– hazardous substances in e-waste - effects of e-waste on environment and human health- need for e-waste management– e-waste handling rules - waste minimization techniques for managing e-waste – recycling of e-waste - disposal treatment methods of e- waste – mechanism of extraction of precious metal from leaching solution-global Scenario of E-waste – E-waste in India- case studies.
Embedded machine learning-based road conditions and driving behavior monitoringIJECEIAES
Car accident rates have increased in recent years, resulting in losses in human lives, properties, and other financial costs. An embedded machine learning-based system is developed to address this critical issue. The system can monitor road conditions, detect driving patterns, and identify aggressive driving behaviors. The system is based on neural networks trained on a comprehensive dataset of driving events, driving styles, and road conditions. The system effectively detects potential risks and helps mitigate the frequency and impact of accidents. The primary goal is to ensure the safety of drivers and vehicles. Collecting data involved gathering information on three key road events: normal street and normal drive, speed bumps, circular yellow speed bumps, and three aggressive driving actions: sudden start, sudden stop, and sudden entry. The gathered data is processed and analyzed using a machine learning system designed for limited power and memory devices. The developed system resulted in 91.9% accuracy, 93.6% precision, and 92% recall. The achieved inference time on an Arduino Nano 33 BLE Sense with a 32-bit CPU running at 64 MHz is 34 ms and requires 2.6 kB peak RAM and 139.9 kB program flash memory, making it suitable for resource-constrained embedded systems.
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...IJECEIAES
Medical image analysis has witnessed significant advancements with deep learning techniques. In the domain of brain tumor segmentation, the ability to
precisely delineate tumor boundaries from magnetic resonance imaging (MRI)
scans holds profound implications for diagnosis. This study presents an ensemble convolutional neural network (CNN) with transfer learning, integrating
the state-of-the-art Deeplabv3+ architecture with the ResNet18 backbone. The
model is rigorously trained and evaluated, exhibiting remarkable performance
metrics, including an impressive global accuracy of 99.286%, a high-class accuracy of 82.191%, a mean intersection over union (IoU) of 79.900%, a weighted
IoU of 98.620%, and a Boundary F1 (BF) score of 83.303%. Notably, a detailed comparative analysis with existing methods showcases the superiority of
our proposed model. These findings underscore the model’s competence in precise brain tumor localization, underscoring its potential to revolutionize medical
image analysis and enhance healthcare outcomes. This research paves the way
for future exploration and optimization of advanced CNN models in medical
imaging, emphasizing addressing false positives and resource efficiency.
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTjpsjournal1
The rivalry between prominent international actors for dominance over Central Asia's hydrocarbon
reserves and the ancient silk trade route, along with China's diplomatic endeavours in the area, has been
referred to as the "New Great Game." This research centres on the power struggle, considering
geopolitical, geostrategic, and geoeconomic variables. Topics including trade, political hegemony, oil
politics, and conventional and nontraditional security are all explored and explained by the researcher.
Using Mackinder's Heartland, Spykman Rimland, and Hegemonic Stability theories, examines China's role
in Central Asia. This study adheres to the empirical epistemological method and has taken care of
objectivity. This study analyze primary and secondary research documents critically to elaborate role of
china’s geo economic outreach in central Asian countries and its future prospect. China is thriving in trade,
pipeline politics, and winning states, according to this study, thanks to important instruments like the
Shanghai Cooperation Organisation and the Belt and Road Economic Initiative. According to this study,
China is seeing significant success in commerce, pipeline politics, and gaining influence on other
governments. This success may be attributed to the effective utilisation of key tools such as the Shanghai
Cooperation Organisation and the Belt and Road Economic Initiative.
The CBC machine is a common diagnostic tool used by doctors to measure a patient's red blood cell count, white blood cell count and platelet count. The machine uses a small sample of the patient's blood, which is then placed into special tubes and analyzed. The results of the analysis are then displayed on a screen for the doctor to review. The CBC machine is an important tool for diagnosing various conditions, such as anemia, infection and leukemia. It can also help to monitor a patient's response to treatment.
Comparative analysis between traditional aquaponics and reconstructed aquapon...bijceesjournal
The aquaponic system of planting is a method that does not require soil usage. It is a method that only needs water, fish, lava rocks (a substitute for soil), and plants. Aquaponic systems are sustainable and environmentally friendly. Its use not only helps to plant in small spaces but also helps reduce artificial chemical use and minimizes excess water use, as aquaponics consumes 90% less water than soil-based gardening. The study applied a descriptive and experimental design to assess and compare conventional and reconstructed aquaponic methods for reproducing tomatoes. The researchers created an observation checklist to determine the significant factors of the study. The study aims to determine the significant difference between traditional aquaponics and reconstructed aquaponics systems propagating tomatoes in terms of height, weight, girth, and number of fruits. The reconstructed aquaponics system’s higher growth yield results in a much more nourished crop than the traditional aquaponics system. It is superior in its number of fruits, height, weight, and girth measurement. Moreover, the reconstructed aquaponics system is proven to eliminate all the hindrances present in the traditional aquaponics system, which are overcrowding of fish, algae growth, pest problems, contaminated water, and dead fish.
1. TSPS/ISPSWORK – S1A1 BWSSB.
Prepared By- Ravikiran Chendake Page 1
TSPS /ISPS WORK IN RAJA CANAL
Project details-
In Bangalore water supply sewerage board project, the combined TSPS/ISPS construction work is in
progress near Raja Canal STP. Its include 40 mld terminal sewage pumping station for Raja canal & 20 mld
Intermediate sewage pumping station for Hormavu Sewage treatment plant.
Hurdles while starting the work-
Sufficient space was not available for construction of TSPS/ISPS structure. After co-ordination with
the client, Raja Canal drain diverted parallel to the rail track by this way; we got the sufficient space
for construction as per the GFC drawing.
Photo showing the diversion ofexistingSWD drain.
Location of proposed site is near to the existing Raja canal STP (40 mld ), the admin building & the
laboratory building are just 5 to 10 m away from the proposed TSPS & ISPS structure. Also depth of
excavation is 18 to 20 meter from natural ground level as per the GFC drawings, hence it is very
necessary to do proper planning & take proper precautionary measures before starting the
excavation of the proposed TSPS/ISPS structure.
2. TSPS/ISPSWORK – S1A1 BWSSB.
Prepared By- Ravikiran Chendake Page 2
Photo showing existing Structures arejust side ofexcavation line.
Hence we change the orientation of the structure as per the site condition to avoid any disturbance to
existing structure after proper approval from design team & client.
Excavation for TSPS/ISPS –
The depth of excavation is 18 to 20 meter from natural ground level. The adjacent SWD drain and
existing STP admin buildings are very near to the line of excavation, hence we recommended to the
contractor to excavate sloping as well as stepping at an interval of every 2 to 4 m vertically, till the
hard strata found. After hard strata found we did the vertical excavation as shown in the
photograph below.
Photo showing-TSPS excavation work.
Every 2-4 m vertical interval 1-1.5 m horizontal step is provided, as shown in figure. It helped us in
the safety point of view. If any sudden collapse will happen the loose soil will slide gradually and
major quantity of soil will stands on the horizontal step provided, also very less quantity of soil will
reach up to the excavation bottom. Sufficient margin (2m to 2.5 m) has provided in between PCC
outer edge & excavation line (Bottom).
After completion of 50 % excavation suddenly collapse happen from the SWD drain side due to
excessive seepage & refilled soil. Hence we suggested to the contractor to do the sheet piling to
retain the loose soil (towards drain side).
3. TSPS/ISPSWORK – S1A1 BWSSB.
Prepared By- Ravikiran Chendake Page 3
Also sand bags are placed on the bank of drain for strengthening of drain as well as to minimize the
seepage, as shown in the above photograph.
After the sand bags lining on the bank of the drain we got better relief from the collapse as well as
seepage water.
PCC & Reinforcement of raft-
After completing of PCC work the next challenging work was reinforcement of raft (ISPS/TSPS). As
sufficient space was not available to install the Crain, there is no any alternate to do the
transportation of steel manually at 18 m. depth below the natural ground level. It was done within
8 working days (Day & night), about 150 MT steel shifted for reinforcement of raft by 100 fitters &
helpers during the raining condition. It was the unbelieving experience for all of us, that we did this
work within such a short period.
The photo showing the reinforcement work is in progress.
After raft reinforcement completed
4. TSPS/ISPSWORK – S1A1 BWSSB.
Prepared By- Ravikiran Chendake Page 4
Casting of the Raft-
After completion of raft reinforcement the next most challenging work for us was, pouring the
concrete. (Quantity- 750 cum.)
While planning the concreting, it was very difficult to us as site RMC plant capacity is only 25
cum/hr. Also there are lots of obstruction to continuous supply of concrete due to traffic
department no entry for period of 8 am to 12 pm & 4 pm to 8 pm (Every day) , as site location is
inside the city, hence there is no any other alternate to complete the concrete work within 8 pm to
next day morning 8 am (within 12 hrs.).
Hence we planned to take the concrete from three different RMC plant vendors (Approved). As
depth of pouring is 18 m from ground level hence we brought 2 static concrete pumps & 2 boom
concrete placer ( truck mounted.) having boom length 36 & 42 m.
Photos showing the pump arrangement made for concreting.
By proper planning & efforts taken by all of us, we completed the raft concreting work within
12 hrs. at a rate of 62.5 cum / hr. It was amazing experience for all of us that such huge quantity
of concrete we did within the short time.
5. TSPS/ISPSWORK – S1A1 BWSSB.
Prepared By- Ravikiran Chendake Page 5
After completion of raft concrete.