SlideShare a Scribd company logo
TSPS/ISPSWORK – S1A1 BWSSB.
Prepared By- Ravikiran Chendake Page 1
TSPS /ISPS WORK IN RAJA CANAL
Project details-
In Bangalore water supply sewerage board project, the combined TSPS/ISPS construction work is in
progress near Raja Canal STP. Its include 40 mld terminal sewage pumping station for Raja canal & 20 mld
Intermediate sewage pumping station for Hormavu Sewage treatment plant.
Hurdles while starting the work-
 Sufficient space was not available for construction of TSPS/ISPS structure. After co-ordination with
the client, Raja Canal drain diverted parallel to the rail track by this way; we got the sufficient space
for construction as per the GFC drawing.
Photo showing the diversion ofexistingSWD drain.
 Location of proposed site is near to the existing Raja canal STP (40 mld ), the admin building & the
laboratory building are just 5 to 10 m away from the proposed TSPS & ISPS structure. Also depth of
excavation is 18 to 20 meter from natural ground level as per the GFC drawings, hence it is very
necessary to do proper planning & take proper precautionary measures before starting the
excavation of the proposed TSPS/ISPS structure.
TSPS/ISPSWORK – S1A1 BWSSB.
Prepared By- Ravikiran Chendake Page 2
Photo showing existing Structures arejust side ofexcavation line.
Hence we change the orientation of the structure as per the site condition to avoid any disturbance to
existing structure after proper approval from design team & client.
 Excavation for TSPS/ISPS –
The depth of excavation is 18 to 20 meter from natural ground level. The adjacent SWD drain and
existing STP admin buildings are very near to the line of excavation, hence we recommended to the
contractor to excavate sloping as well as stepping at an interval of every 2 to 4 m vertically, till the
hard strata found. After hard strata found we did the vertical excavation as shown in the
photograph below.
Photo showing-TSPS excavation work.
Every 2-4 m vertical interval 1-1.5 m horizontal step is provided, as shown in figure. It helped us in
the safety point of view. If any sudden collapse will happen the loose soil will slide gradually and
major quantity of soil will stands on the horizontal step provided, also very less quantity of soil will
reach up to the excavation bottom. Sufficient margin (2m to 2.5 m) has provided in between PCC
outer edge & excavation line (Bottom).
After completion of 50 % excavation suddenly collapse happen from the SWD drain side due to
excessive seepage & refilled soil. Hence we suggested to the contractor to do the sheet piling to
retain the loose soil (towards drain side).
TSPS/ISPSWORK – S1A1 BWSSB.
Prepared By- Ravikiran Chendake Page 3
Also sand bags are placed on the bank of drain for strengthening of drain as well as to minimize the
seepage, as shown in the above photograph.
After the sand bags lining on the bank of the drain we got better relief from the collapse as well as
seepage water.
 PCC & Reinforcement of raft-
After completing of PCC work the next challenging work was reinforcement of raft (ISPS/TSPS). As
sufficient space was not available to install the Crain, there is no any alternate to do the
transportation of steel manually at 18 m. depth below the natural ground level. It was done within
8 working days (Day & night), about 150 MT steel shifted for reinforcement of raft by 100 fitters &
helpers during the raining condition. It was the unbelieving experience for all of us, that we did this
work within such a short period.
The photo showing the reinforcement work is in progress.
After raft reinforcement completed
TSPS/ISPSWORK – S1A1 BWSSB.
Prepared By- Ravikiran Chendake Page 4
Casting of the Raft-
After completion of raft reinforcement the next most challenging work for us was, pouring the
concrete. (Quantity- 750 cum.)
While planning the concreting, it was very difficult to us as site RMC plant capacity is only 25
cum/hr. Also there are lots of obstruction to continuous supply of concrete due to traffic
department no entry for period of 8 am to 12 pm & 4 pm to 8 pm (Every day) , as site location is
inside the city, hence there is no any other alternate to complete the concrete work within 8 pm to
next day morning 8 am (within 12 hrs.).
Hence we planned to take the concrete from three different RMC plant vendors (Approved). As
depth of pouring is 18 m from ground level hence we brought 2 static concrete pumps & 2 boom
concrete placer ( truck mounted.) having boom length 36 & 42 m.
Photos showing the pump arrangement made for concreting.
By proper planning & efforts taken by all of us, we completed the raft concreting work within
12 hrs. at a rate of 62.5 cum / hr. It was amazing experience for all of us that such huge quantity
of concrete we did within the short time.
TSPS/ISPSWORK – S1A1 BWSSB.
Prepared By- Ravikiran Chendake Page 5
After completion of raft concrete.

More Related Content

What's hot

Leaside & Laird Construction Liaison Committee Meeting - September 2017
Leaside & Laird Construction Liaison Committee Meeting - September 2017Leaside & Laird Construction Liaison Committee Meeting - September 2017
Leaside & Laird Construction Liaison Committee Meeting - September 2017
Crosstown TO
 
Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017
Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017
Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017
Crosstown TO
 
Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018
Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018
Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018
Crosstown TO
 
MANOJ RESUME
MANOJ RESUMEMANOJ RESUME
MANOJ RESUME
MANOJ KUMAR
 
Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...
Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...
Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...
Crosstown TO
 
Eglinton & Mount Pleasant Construction Liaison Committee - November 2017
Eglinton & Mount Pleasant Construction Liaison Committee - November 2017Eglinton & Mount Pleasant Construction Liaison Committee - November 2017
Eglinton & Mount Pleasant Construction Liaison Committee - November 2017
Crosstown TO
 
Leaside & Laird Construction Liaison Committee - November 2017
Leaside & Laird Construction Liaison Committee - November 2017Leaside & Laird Construction Liaison Committee - November 2017
Leaside & Laird Construction Liaison Committee - November 2017
Crosstown TO
 
Eglinton and Mt Pleasant Stations Open House - October 2017
Eglinton and Mt Pleasant Stations Open House - October 2017Eglinton and Mt Pleasant Stations Open House - October 2017
Eglinton and Mt Pleasant Stations Open House - October 2017
Crosstown TO
 
Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017
Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017
Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017
Crosstown TO
 
laos-tj-2016
laos-tj-2016laos-tj-2016
laos-tj-2016
Omar Ferro
 
Surface Water Facilities construction progress 11-2012
Surface Water Facilities construction progress  11-2012Surface Water Facilities construction progress  11-2012
Surface Water Facilities construction progress 11-2012
San Jacinto River Authority
 
Forest Hill Station Open House - June 2017
Forest Hill Station Open House - June 2017Forest Hill Station Open House - June 2017
Forest Hill Station Open House - June 2017
Crosstown TO
 
AAMIR - PROFILE
AAMIR - PROFILEAAMIR - PROFILE
AAMIR - PROFILE
aamir qayyum
 
CV Mirani Sb Color
CV Mirani Sb ColorCV Mirani Sb Color
CV Mirani Sb Color
AMIR BAKHSH MIRANI
 
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017
Crosstown TO
 
Zach Maddox - CV 2016 May 01
Zach Maddox - CV 2016 May 01Zach Maddox - CV 2016 May 01
Zach Maddox - CV 2016 May 01
Zachary Maddox
 
Think Outside The Box
Think Outside The BoxThink Outside The Box
Think Outside The Box
Singapore Power Ltd
 
Ahmd Mahmoud c.v
Ahmd Mahmoud c.vAhmd Mahmoud c.v
Ahmd Mahmoud c.v
Ahmed Mahmoud
 
Western Works - Construction Liaison Committee Meeting - May 2017
Western Works - Construction Liaison Committee Meeting - May 2017Western Works - Construction Liaison Committee Meeting - May 2017
Western Works - Construction Liaison Committee Meeting - May 2017
Crosstown TO
 
Caledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 finalCaledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 final
Crosstown TO
 

What's hot (20)

Leaside & Laird Construction Liaison Committee Meeting - September 2017
Leaside & Laird Construction Liaison Committee Meeting - September 2017Leaside & Laird Construction Liaison Committee Meeting - September 2017
Leaside & Laird Construction Liaison Committee Meeting - September 2017
 
Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017
Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017
Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017
 
Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018
Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018
Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018
 
MANOJ RESUME
MANOJ RESUMEMANOJ RESUME
MANOJ RESUME
 
Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...
Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...
Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...
 
Eglinton & Mount Pleasant Construction Liaison Committee - November 2017
Eglinton & Mount Pleasant Construction Liaison Committee - November 2017Eglinton & Mount Pleasant Construction Liaison Committee - November 2017
Eglinton & Mount Pleasant Construction Liaison Committee - November 2017
 
Leaside & Laird Construction Liaison Committee - November 2017
Leaside & Laird Construction Liaison Committee - November 2017Leaside & Laird Construction Liaison Committee - November 2017
Leaside & Laird Construction Liaison Committee - November 2017
 
Eglinton and Mt Pleasant Stations Open House - October 2017
Eglinton and Mt Pleasant Stations Open House - October 2017Eglinton and Mt Pleasant Stations Open House - October 2017
Eglinton and Mt Pleasant Stations Open House - October 2017
 
Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017
Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017
Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017
 
laos-tj-2016
laos-tj-2016laos-tj-2016
laos-tj-2016
 
Surface Water Facilities construction progress 11-2012
Surface Water Facilities construction progress  11-2012Surface Water Facilities construction progress  11-2012
Surface Water Facilities construction progress 11-2012
 
Forest Hill Station Open House - June 2017
Forest Hill Station Open House - June 2017Forest Hill Station Open House - June 2017
Forest Hill Station Open House - June 2017
 
AAMIR - PROFILE
AAMIR - PROFILEAAMIR - PROFILE
AAMIR - PROFILE
 
CV Mirani Sb Color
CV Mirani Sb ColorCV Mirani Sb Color
CV Mirani Sb Color
 
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017
 
Zach Maddox - CV 2016 May 01
Zach Maddox - CV 2016 May 01Zach Maddox - CV 2016 May 01
Zach Maddox - CV 2016 May 01
 
Think Outside The Box
Think Outside The BoxThink Outside The Box
Think Outside The Box
 
Ahmd Mahmoud c.v
Ahmd Mahmoud c.vAhmd Mahmoud c.v
Ahmd Mahmoud c.v
 
Western Works - Construction Liaison Committee Meeting - May 2017
Western Works - Construction Liaison Committee Meeting - May 2017Western Works - Construction Liaison Committee Meeting - May 2017
Western Works - Construction Liaison Committee Meeting - May 2017
 
Caledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 finalCaledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 final
 

Viewers also liked

Rondas
Rondas Rondas
Rondas
isismaria10
 
Presentación SlideShare
Presentación SlideSharePresentación SlideShare
Presentación SlideShare
Mariangelis Rodríguez
 
Presentación SlideShare
Presentación SlideSharePresentación SlideShare
Presentación SlideShare
Mariangelis Rodríguez
 
Best Practices of Objection Handling in AdWords
Best Practices of Objection Handling in AdWordsBest Practices of Objection Handling in AdWords
Best Practices of Objection Handling in AdWords
Adonai Advertising - Digital Marketing Training Hyderabad
 
Nguyên tắc-thiết-kế-logo
Nguyên tắc-thiết-kế-logoNguyên tắc-thiết-kế-logo
Nguyên tắc-thiết-kế-logo
Hoang Anh
 
Conversion Tracking in AdWords
Conversion Tracking in AdWordsConversion Tracking in AdWords

Viewers also liked (6)

Rondas
Rondas Rondas
Rondas
 
Presentación SlideShare
Presentación SlideSharePresentación SlideShare
Presentación SlideShare
 
Presentación SlideShare
Presentación SlideSharePresentación SlideShare
Presentación SlideShare
 
Best Practices of Objection Handling in AdWords
Best Practices of Objection Handling in AdWordsBest Practices of Objection Handling in AdWords
Best Practices of Objection Handling in AdWords
 
Nguyên tắc-thiết-kế-logo
Nguyên tắc-thiết-kế-logoNguyên tắc-thiết-kế-logo
Nguyên tắc-thiết-kế-logo
 
Conversion Tracking in AdWords
Conversion Tracking in AdWordsConversion Tracking in AdWords
Conversion Tracking in AdWords
 

Similar to Tsps

1 sethi
1 sethi1 sethi
injo slip update
injo slip updateinjo slip update
injo slip update
Darren Jnr Warai
 
Mahakali Bridge Project Presentation (2077 chaitra 11)
Mahakali Bridge Project Presentation (2077 chaitra 11)Mahakali Bridge Project Presentation (2077 chaitra 11)
Mahakali Bridge Project Presentation (2077 chaitra 11)
Rabindra Shrestha
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
Aditya Mane
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
Aditya Mane
 
bridge design
 bridge design bridge design
PPT seri Nallah 19.10.2023.pptx
PPT seri Nallah 19.10.2023.pptxPPT seri Nallah 19.10.2023.pptx
PPT seri Nallah 19.10.2023.pptx
SaketChandra4
 
PROJECT REPORT ON DESIGN OF A RESIDENTIAL BUILDING
PROJECT REPORT ON DESIGN OF A RESIDENTIAL BUILDINGPROJECT REPORT ON DESIGN OF A RESIDENTIAL BUILDING
PROJECT REPORT ON DESIGN OF A RESIDENTIAL BUILDING
Amritpal Singh
 
PPT CAVITY Tunnel P1 610M--05.02.2021.pptx
PPT CAVITY Tunnel P1 610M--05.02.2021.pptxPPT CAVITY Tunnel P1 610M--05.02.2021.pptx
PPT CAVITY Tunnel P1 610M--05.02.2021.pptx
AGNIVORAY1
 
CV -Sachin Madhukar Chitnis -( Civil Roads, Utility,infra,metro rail ,)
CV  -Sachin Madhukar Chitnis  -( Civil Roads, Utility,infra,metro rail ,)CV  -Sachin Madhukar Chitnis  -( Civil Roads, Utility,infra,metro rail ,)
CV -Sachin Madhukar Chitnis -( Civil Roads, Utility,infra,metro rail ,)
Sachin Chitnis
 
CV -Sachin Madhukar Chitnis -( Civil Roads, Utility,infra,metro rail ,)
CV  -Sachin Madhukar Chitnis  -( Civil Roads, Utility,infra,metro rail ,)CV  -Sachin Madhukar Chitnis  -( Civil Roads, Utility,infra,metro rail ,)
CV -Sachin Madhukar Chitnis -( Civil Roads, Utility,infra,metro rail ,)
Sachin Chitnis
 
REPAIR OF THE SPILLWAY AT PANDOH DAM
REPAIR OF THE  SPILLWAY AT PANDOH DAM REPAIR OF THE  SPILLWAY AT PANDOH DAM
REPAIR OF THE SPILLWAY AT PANDOH DAM
Hemant Thakur
 
20220817 Presentation wapda.pptx
20220817 Presentation wapda.pptx20220817 Presentation wapda.pptx
20220817 Presentation wapda.pptx
AmirShafiq25
 
Chhabra Thermal Power plant ppt by Cm lodha
Chhabra Thermal Power plant ppt by Cm lodhaChhabra Thermal Power plant ppt by Cm lodha
Chhabra Thermal Power plant ppt by Cm lodha
Chandra Mohan Lodha
 
Svp field training report final
Svp field training report finalSvp field training report final
Svp field training report final
Shubham Parab
 
Summer training report
Summer training reportSummer training report
Summer training report
aki8872233
 
SACHIN CIVIL.docx
SACHIN CIVIL.docxSACHIN CIVIL.docx
SACHIN CIVIL.docx
SachinSachi46
 
Pile boring/ Driving Equipment, Concrete Batching plant, Tunnel Boring Machines
Pile boring/ Driving Equipment, Concrete Batching plant, Tunnel Boring MachinesPile boring/ Driving Equipment, Concrete Batching plant, Tunnel Boring Machines
Pile boring/ Driving Equipment, Concrete Batching plant, Tunnel Boring Machines
Prerak Ka.Patel
 
TRAINING REPORT ON COSTRUCTION OF FLYOVER FROM MITHAPUR TO CHIRIYATAND (BIHAR)
TRAINING REPORT ON  COSTRUCTION OF FLYOVER FROM  MITHAPUR TO CHIRIYATAND (BIHAR)TRAINING REPORT ON  COSTRUCTION OF FLYOVER FROM  MITHAPUR TO CHIRIYATAND (BIHAR)
TRAINING REPORT ON COSTRUCTION OF FLYOVER FROM MITHAPUR TO CHIRIYATAND (BIHAR)
vishal prakash
 
Update for pending works
Update for pending worksUpdate for pending works
Update for pending works
Arumugam Rajagopal
 

Similar to Tsps (20)

1 sethi
1 sethi1 sethi
1 sethi
 
injo slip update
injo slip updateinjo slip update
injo slip update
 
Mahakali Bridge Project Presentation (2077 chaitra 11)
Mahakali Bridge Project Presentation (2077 chaitra 11)Mahakali Bridge Project Presentation (2077 chaitra 11)
Mahakali Bridge Project Presentation (2077 chaitra 11)
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
 
bridge design
 bridge design bridge design
bridge design
 
PPT seri Nallah 19.10.2023.pptx
PPT seri Nallah 19.10.2023.pptxPPT seri Nallah 19.10.2023.pptx
PPT seri Nallah 19.10.2023.pptx
 
PROJECT REPORT ON DESIGN OF A RESIDENTIAL BUILDING
PROJECT REPORT ON DESIGN OF A RESIDENTIAL BUILDINGPROJECT REPORT ON DESIGN OF A RESIDENTIAL BUILDING
PROJECT REPORT ON DESIGN OF A RESIDENTIAL BUILDING
 
PPT CAVITY Tunnel P1 610M--05.02.2021.pptx
PPT CAVITY Tunnel P1 610M--05.02.2021.pptxPPT CAVITY Tunnel P1 610M--05.02.2021.pptx
PPT CAVITY Tunnel P1 610M--05.02.2021.pptx
 
CV -Sachin Madhukar Chitnis -( Civil Roads, Utility,infra,metro rail ,)
CV  -Sachin Madhukar Chitnis  -( Civil Roads, Utility,infra,metro rail ,)CV  -Sachin Madhukar Chitnis  -( Civil Roads, Utility,infra,metro rail ,)
CV -Sachin Madhukar Chitnis -( Civil Roads, Utility,infra,metro rail ,)
 
CV -Sachin Madhukar Chitnis -( Civil Roads, Utility,infra,metro rail ,)
CV  -Sachin Madhukar Chitnis  -( Civil Roads, Utility,infra,metro rail ,)CV  -Sachin Madhukar Chitnis  -( Civil Roads, Utility,infra,metro rail ,)
CV -Sachin Madhukar Chitnis -( Civil Roads, Utility,infra,metro rail ,)
 
REPAIR OF THE SPILLWAY AT PANDOH DAM
REPAIR OF THE  SPILLWAY AT PANDOH DAM REPAIR OF THE  SPILLWAY AT PANDOH DAM
REPAIR OF THE SPILLWAY AT PANDOH DAM
 
20220817 Presentation wapda.pptx
20220817 Presentation wapda.pptx20220817 Presentation wapda.pptx
20220817 Presentation wapda.pptx
 
Chhabra Thermal Power plant ppt by Cm lodha
Chhabra Thermal Power plant ppt by Cm lodhaChhabra Thermal Power plant ppt by Cm lodha
Chhabra Thermal Power plant ppt by Cm lodha
 
Svp field training report final
Svp field training report finalSvp field training report final
Svp field training report final
 
Summer training report
Summer training reportSummer training report
Summer training report
 
SACHIN CIVIL.docx
SACHIN CIVIL.docxSACHIN CIVIL.docx
SACHIN CIVIL.docx
 
Pile boring/ Driving Equipment, Concrete Batching plant, Tunnel Boring Machines
Pile boring/ Driving Equipment, Concrete Batching plant, Tunnel Boring MachinesPile boring/ Driving Equipment, Concrete Batching plant, Tunnel Boring Machines
Pile boring/ Driving Equipment, Concrete Batching plant, Tunnel Boring Machines
 
TRAINING REPORT ON COSTRUCTION OF FLYOVER FROM MITHAPUR TO CHIRIYATAND (BIHAR)
TRAINING REPORT ON  COSTRUCTION OF FLYOVER FROM  MITHAPUR TO CHIRIYATAND (BIHAR)TRAINING REPORT ON  COSTRUCTION OF FLYOVER FROM  MITHAPUR TO CHIRIYATAND (BIHAR)
TRAINING REPORT ON COSTRUCTION OF FLYOVER FROM MITHAPUR TO CHIRIYATAND (BIHAR)
 
Update for pending works
Update for pending worksUpdate for pending works
Update for pending works
 

Recently uploaded

2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
Yasser Mahgoub
 
Welding Metallurgy Ferrous Materials.pdf
Welding Metallurgy Ferrous Materials.pdfWelding Metallurgy Ferrous Materials.pdf
Welding Metallurgy Ferrous Materials.pdf
AjmalKhan50578
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
Madan Karki
 
CompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURS
CompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURSCompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURS
CompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURS
RamonNovais6
 
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
ecqow
 
International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...
gerogepatton
 
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have oneISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
Las Vegas Warehouse
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
kandramariana6
 
Null Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAMNull Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAM
Divyanshu
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
KrishnaveniKrishnara1
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
IJECEIAES
 
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
IJECEIAES
 
CEC 352 - SATELLITE COMMUNICATION UNIT 1
CEC 352 - SATELLITE COMMUNICATION UNIT 1CEC 352 - SATELLITE COMMUNICATION UNIT 1
CEC 352 - SATELLITE COMMUNICATION UNIT 1
PKavitha10
 
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
171ticu
 
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
jpsjournal1
 
cnn.pptx Convolutional neural network used for image classication
cnn.pptx Convolutional neural network used for image classicationcnn.pptx Convolutional neural network used for image classication
cnn.pptx Convolutional neural network used for image classication
SakkaravarthiShanmug
 
官方认证美国密歇根州立大学毕业证学位证书原版一模一样
官方认证美国密歇根州立大学毕业证学位证书原版一模一样官方认证美国密歇根州立大学毕业证学位证书原版一模一样
官方认证美国密歇根州立大学毕业证学位证书原版一模一样
171ticu
 
Hematology Analyzer Machine - Complete Blood Count
Hematology Analyzer Machine - Complete Blood CountHematology Analyzer Machine - Complete Blood Count
Hematology Analyzer Machine - Complete Blood Count
shahdabdulbaset
 
Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...
bijceesjournal
 
BRAIN TUMOR DETECTION for seminar ppt.pdf
BRAIN TUMOR DETECTION for seminar ppt.pdfBRAIN TUMOR DETECTION for seminar ppt.pdf
BRAIN TUMOR DETECTION for seminar ppt.pdf
LAXMAREDDY22
 

Recently uploaded (20)

2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
 
Welding Metallurgy Ferrous Materials.pdf
Welding Metallurgy Ferrous Materials.pdfWelding Metallurgy Ferrous Materials.pdf
Welding Metallurgy Ferrous Materials.pdf
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
 
CompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURS
CompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURSCompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURS
CompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURS
 
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
 
International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...
 
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have oneISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
 
Null Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAMNull Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAM
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
 
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
 
CEC 352 - SATELLITE COMMUNICATION UNIT 1
CEC 352 - SATELLITE COMMUNICATION UNIT 1CEC 352 - SATELLITE COMMUNICATION UNIT 1
CEC 352 - SATELLITE COMMUNICATION UNIT 1
 
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
 
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
 
cnn.pptx Convolutional neural network used for image classication
cnn.pptx Convolutional neural network used for image classicationcnn.pptx Convolutional neural network used for image classication
cnn.pptx Convolutional neural network used for image classication
 
官方认证美国密歇根州立大学毕业证学位证书原版一模一样
官方认证美国密歇根州立大学毕业证学位证书原版一模一样官方认证美国密歇根州立大学毕业证学位证书原版一模一样
官方认证美国密歇根州立大学毕业证学位证书原版一模一样
 
Hematology Analyzer Machine - Complete Blood Count
Hematology Analyzer Machine - Complete Blood CountHematology Analyzer Machine - Complete Blood Count
Hematology Analyzer Machine - Complete Blood Count
 
Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...
 
BRAIN TUMOR DETECTION for seminar ppt.pdf
BRAIN TUMOR DETECTION for seminar ppt.pdfBRAIN TUMOR DETECTION for seminar ppt.pdf
BRAIN TUMOR DETECTION for seminar ppt.pdf
 

Tsps

  • 1. TSPS/ISPSWORK – S1A1 BWSSB. Prepared By- Ravikiran Chendake Page 1 TSPS /ISPS WORK IN RAJA CANAL Project details- In Bangalore water supply sewerage board project, the combined TSPS/ISPS construction work is in progress near Raja Canal STP. Its include 40 mld terminal sewage pumping station for Raja canal & 20 mld Intermediate sewage pumping station for Hormavu Sewage treatment plant. Hurdles while starting the work-  Sufficient space was not available for construction of TSPS/ISPS structure. After co-ordination with the client, Raja Canal drain diverted parallel to the rail track by this way; we got the sufficient space for construction as per the GFC drawing. Photo showing the diversion ofexistingSWD drain.  Location of proposed site is near to the existing Raja canal STP (40 mld ), the admin building & the laboratory building are just 5 to 10 m away from the proposed TSPS & ISPS structure. Also depth of excavation is 18 to 20 meter from natural ground level as per the GFC drawings, hence it is very necessary to do proper planning & take proper precautionary measures before starting the excavation of the proposed TSPS/ISPS structure.
  • 2. TSPS/ISPSWORK – S1A1 BWSSB. Prepared By- Ravikiran Chendake Page 2 Photo showing existing Structures arejust side ofexcavation line. Hence we change the orientation of the structure as per the site condition to avoid any disturbance to existing structure after proper approval from design team & client.  Excavation for TSPS/ISPS – The depth of excavation is 18 to 20 meter from natural ground level. The adjacent SWD drain and existing STP admin buildings are very near to the line of excavation, hence we recommended to the contractor to excavate sloping as well as stepping at an interval of every 2 to 4 m vertically, till the hard strata found. After hard strata found we did the vertical excavation as shown in the photograph below. Photo showing-TSPS excavation work. Every 2-4 m vertical interval 1-1.5 m horizontal step is provided, as shown in figure. It helped us in the safety point of view. If any sudden collapse will happen the loose soil will slide gradually and major quantity of soil will stands on the horizontal step provided, also very less quantity of soil will reach up to the excavation bottom. Sufficient margin (2m to 2.5 m) has provided in between PCC outer edge & excavation line (Bottom). After completion of 50 % excavation suddenly collapse happen from the SWD drain side due to excessive seepage & refilled soil. Hence we suggested to the contractor to do the sheet piling to retain the loose soil (towards drain side).
  • 3. TSPS/ISPSWORK – S1A1 BWSSB. Prepared By- Ravikiran Chendake Page 3 Also sand bags are placed on the bank of drain for strengthening of drain as well as to minimize the seepage, as shown in the above photograph. After the sand bags lining on the bank of the drain we got better relief from the collapse as well as seepage water.  PCC & Reinforcement of raft- After completing of PCC work the next challenging work was reinforcement of raft (ISPS/TSPS). As sufficient space was not available to install the Crain, there is no any alternate to do the transportation of steel manually at 18 m. depth below the natural ground level. It was done within 8 working days (Day & night), about 150 MT steel shifted for reinforcement of raft by 100 fitters & helpers during the raining condition. It was the unbelieving experience for all of us, that we did this work within such a short period. The photo showing the reinforcement work is in progress. After raft reinforcement completed
  • 4. TSPS/ISPSWORK – S1A1 BWSSB. Prepared By- Ravikiran Chendake Page 4 Casting of the Raft- After completion of raft reinforcement the next most challenging work for us was, pouring the concrete. (Quantity- 750 cum.) While planning the concreting, it was very difficult to us as site RMC plant capacity is only 25 cum/hr. Also there are lots of obstruction to continuous supply of concrete due to traffic department no entry for period of 8 am to 12 pm & 4 pm to 8 pm (Every day) , as site location is inside the city, hence there is no any other alternate to complete the concrete work within 8 pm to next day morning 8 am (within 12 hrs.). Hence we planned to take the concrete from three different RMC plant vendors (Approved). As depth of pouring is 18 m from ground level hence we brought 2 static concrete pumps & 2 boom concrete placer ( truck mounted.) having boom length 36 & 42 m. Photos showing the pump arrangement made for concreting. By proper planning & efforts taken by all of us, we completed the raft concreting work within 12 hrs. at a rate of 62.5 cum / hr. It was amazing experience for all of us that such huge quantity of concrete we did within the short time.
  • 5. TSPS/ISPSWORK – S1A1 BWSSB. Prepared By- Ravikiran Chendake Page 5 After completion of raft concrete.