SlideShare a Scribd company logo
WELCOMEWELCOME
TOTO
PRESENTATIONPRESENTATION
ONON
PANDOH SPILLWAY REPAIRPANDOH SPILLWAY REPAIR
:-Er HIMANSHU:-Er HIMANSHU
General View of Pandoh Dam & SPILLWAY
General View of Pandoh SPILLWAY
• Pandoh Dam spillway is meant for the release of
water of R-Beas in excess to the requirement at
Pandoh after maintaining the required PRL
during the monsoon season and also for the
continuous release of 15 % water for the rest of
the period during the year. The release of 15 %
water downstream of Pandoh Dam has been
made mandatory by the Hon’ble High court
Shimla (HP) since -2005.
• Pandoh spillway is an orifice type chute
spillway and there are 5 No radial gates
having size 12mt x 13 mt each which are
designed for the maximum release of
3,51,000 cusec of discharge. The width of
the spillway at the crest is 74 mt and the
clear water way is 60 mtr. The overall area
of the spillway from the zero RD to the end
of flip bucket is 93,413 sq ft.
• The total spillway area can be divided into three
parts :-
• 5 No crest blocks,
• 42 No. chute blocks
• 7 No. flip bucket blocks.
• The spillway chute has a slope of 2.5: 1. The
energy dissipater type flip bucket has been
provided at the end of the spillway chute having
50 ft radius and the angle of the flip bucket is 350
• The thickness of the conc. floor of the spillway
chute is 3 ft which increases to 10 ft in the
middle of the flip bucket and 19 ft at the end of
flip bucket. The chute floor has been tied to the
underlying rock by means of 25mm dia
deformed anchors 15 ft deep into the rock and
spaced at 6 ft c/c.
• Reinforcement bars 20mm dia @ 30 Cm c/c
has been provided both in longitudinal & cross
direction on the spillway chute & flip bucket floor
area. A top cover of 6” has been provided to the
steel reinforcement .
Total 0.127x106
m3 of the conc. of various
strengths has been used for the construction of
Pandoh spillway:-
1. 1500 psi - for protective coat
over rock
2. 4000psi - water contact surface for
abrasion resistance
3. 3000psi - for all other sections of spillway
• Every year during the monsoon season the river
discharge carries a huge quantity of silt laden
water, boulders and tree logs which rolls over
the spillway surface and also the frequent
flushing operations which are carried out during
the monsoon season for the exclusion of
deposited silt in the Pandoh reservoir causes
heavy damage to the spillway chute and flip
bucket.
• It has been observed from the past experience
that every year after the monsoon season,
approximately 30,000 sq ft of the spillway area
gets damaged which includes the area of
spillway chute, flip bucket and the area of one
No. gate from sill plate to the end of stop logs,
taken up for major repair during the year
• The extent of the average damage on the
spillway chute and flip bucket is generally found
between 2” to 4 “.
Some times reinforcement bars provided in the
chute surface & flip bucket also gets exposed
due to hit of the heavy tree logs & continuous
rolling of boulders & other material over the
spillway surface during the flushing operations.
The steel plate provided at the end of the flip
bucket also gets eroded at many places due to
continuous passing of silt laden water & rolling
of boulders during the monsoon season.
• The maximum damage to the spillway area
occurred so for after the construction of the
project was observed in the year 1995 when the
historical flood to the tune of 1,61,000 Cs was
passed through the Pandoh spillway.
• The heavy rains of (2480 mm)97” was recorded
during the year in the catchment area upstream
of Pandoh Dam which was much more than the
Av. Annual rain fall of 54” in the catchment area.
• The damage to the spillway observed after the
flood season of 1995 was 58,310 sq ft .
• The year wise area damaged and repair of the
spillway carried out so for since the year 1985-
86 has been summarized as :-
Year wise area damaged & S/wayYear wise area damaged & S/way
Repair Carried OutRepair Carried Out
Year Area Damaged (Sq. Ft( Area Repaired (Sq. Ft(
1985-86 7120 7120
1986-87 22128 22128
1987-88 19353 19353
1988-89 45026 45026
1989-90 29450 29450
1990-91 12000 12000
1991-92 4360 4360
1992-93 29000 29000
1993-94 34840 29800
1994-95 48240 40900
1995-96 58310 43890
Year wise area damaged & S/way RepairYear wise area damaged & S/way Repair
Carried OutCarried Out
Year Area Damaged (Sq. Ft( Area Repaired (Sq. Ft(
1996-97 38550 35700
1997-98 33300 33300
1998-99 40000 40000
1999-2000 34800 34800
2000-01 30800 30800
2001-02 20000 20000
2002-03 20020 20020
2003-04 15898 15898
2004-05 27761 21000
2005-06 33410 33410
2006-07 45332 45332
2007-08 28000 28000
Year wise area damaged & S/way RepairYear wise area damaged & S/way Repair
Carried OutCarried Out
Year Area Damaged (Sq. Ft( Area Repaired (Sq. Ft(
2008-09 36000 36000
2009-10 7000 7000
2010-11 15800 15800
2011-12 6300 14700
2012-13 6000 6000
2013-14 21000 21000
2014-15 22218 22218
2015-16 12288 12288
• CONSTRUCTION OF TEMPORARY
BANDH AND SEPERATOR WALL
To start with the repair work first of all a
temporary bandh is constructed across the flip
bucket & the flip bucket is divided into two parts.
It thus facilitate the repair work to be carried out
in two phases:-
• in the first phase the water is released through
Gate No 5 and the area in front of gate No-1 to
gate No -4 up to the end of flip bucket is
repaired.
• In the second phase the water is released
through Gate No- 1 and the area in front of Gate
No-5 is repaired.
• To start with the work for the construction of
temporary bandh and separator wall first of all
the leakages from all the five no. radial gates is
diverted towards Gate No-5 after getting the
permission for the closure of 15 % discharges
D/stream of Pandoh Dam for at least 15 days
from HP Environment & Pollution Control Board
Shimla.
• The temporary bandh is constructed in the line
of pier of Gate No 4 & 5 in the flip bucket using
jute bags of 50 kg capacity filled with clay.
• A two ft wide Separator Wall consisting of hollow
block masonry is also constructed throughout
the length and height of the bandh
simultaneously with the raising of the bandh.
• Loose clay filled in plastic bags is placed and
compacted in the voids between the gaps of
hollow block masonry wall and temporary bandh.
• One side of the separator wall is plastered to
prevent the leakage of water from the masonry
wall towards the working area in front of Gate No
1 to 4.
• The height of the bandh and masonry is kept 2 ft
above the height of flip bucket so as to ensure
the continuous release of 15 % of water
downstream of Pandoh Dam without spilling into
the working area prepared for carrying out the
repair in front of Gate No 1 to 4.
COLLECTION OF MATERIAL FOR KATCHA BANDH IN FLIP BUCKET
CONSTRUCTION OF KATCHA BANDH IN FLIP BUCKET IN PROGRESS
CONSTRUCTION OF KATCHA BANDH IN FLIP BUCKET IN PROGRESS
CONSTRUCTION OF KATCHA BANDH IN FLIP BUCKET IN PROGRESS
VIEW OF THE COMPLETED KATCHA BANDH IN FLIP BUCKET
VIEW OF THE COMPLETED KATCHA BANDH IN FLIP BUCKET
LIFTING OF MATERIAL AFTER THE COMPLETION OF BANDH
LIFTING OF MATERIAL AFTER THE COMPLETION OF BANDH
RELEASE OF WATER D/S OF S/WAY AFTER THE COMPLETION OF BANDH
• ASSESSMENT OF DAMAGED AREA
• After the construction of the Separator Wall and
making the surface approachable the whole of
the area is surveyed to know the extent of
damage occurred and to make the planning's for
the repairs to be carried out.
• The photography & video-graphy of the
damaged area is also done and kept as record
for future .
DAMAGED AREA OF PANDOH SPILLWAY CHUTE
DAMAGED AREA OF PANDOH SPILLWAY CHUTE
DAMAGED AREA OF PANDOH SPILLWAY CHUTE
DAMAGED AREA OF PANDOH SPILLWAY CHUTE
DAMAGED AREA OF PANDOH SPILLWAY CHUTE & FLIP BUCKET(2007-08)
DAMAGED AREA IN THE FLIP BUCKET
EXPOSED REINFORCEMENT BARS IN THE FLIP BUCKET (2007-08)
EXPOSED REINFORCEMENT BARS IN THE FLIP BUCKET(2007-08)
MEASUREMENT OF DAMAGED AREA
MEASUREMENT OF DAMAGED AREA
SURFACE PREPERATIONS FOR REPAIR
• After assessing the damaged area the work for
the surface preparation is started. The whole of
the area is first washed by air water jet to
remove elegy . The area is then dried & further
cleaning is made by steel wire brushes to
remove the dust.
• The loose concrete if any is removed by nicking
& hammering. Dust particles present in the pot
holes are also removed with the help of steel
wire brushes & compressed air so as to have a
good bond between the old and new area.
WASHING OF SURFACE WITH AIR WATER JET IN FLIP BUCKET
CUTTING OF LOOSE MATERIAL BEFORE REPAIR
• The reinforcement bars which are found
exposed and damaged are repaired &
maintained as per the original design .The
additional bars are provided in place where ever
required and the welding is done through out the
length of the joint between old & new steel bars.
• Additional dowels with split end on one side are
also provided at the junction of longitudinal and
cross reinforcement bars. The dowels are
anchored in the holes with wedge at the end and
are grouted with cement grout. The longitudinal
& cross reinforcement bars are then welded with
these dowels.
• The steel plate provided at the end of the flip
bucket is also maintained as per its original
shape. Pieces of M.S. plate are welded where
ever it is required and the pitting in the plate is
filled up with steel welding.
• Concrete is grouted under the steel plate where
ever a gap is found .The whole of the steel plate
after repair is covered with a protective coat of
epoxy mortar.
DRILLING WORK FOR PROVIDING ANCHORS IN THE FLIP BUCKET
REPAIR OF STEEL PLATE AT THE END OF FLIP BUCKET IN PROGRESS
REPAIR OF PANDOH SPILLWAY
The damaged area is classified into two
categories:-
1. Normal Abrasion i.e. depth of damage up to ½’’.
2. Heavy Abrasion where the depth of damage is
more than 2” & above
• i) For the repair of the normal abrasion up to
1/2” depth the repair is carried out with epoxy
mortar using three grades of emery powder Gr.
40,60 & 100 in equal proportion as filler.
• The epoxy mortar is laid over the surface
painted with bonding coat of epoxy paint and
the surface is finished with steel gurmalah at the
end.
• For the repair of heavily damaged area rich
c.conc. 7000 PSI strength was being used since
1993-94 to the year 2006-07 . In the year 2007-
08 the heavy damages of conc. in the flip bucket
to the tune of 6” to 9” were observed. The
reinforcement bars were also found badly
exposed.
• Keeping in view M-50 concrete with steel fiber
and admixtures (FRC) was got designed from
NCCBM Ballabgarh, on the initiation of sh SK
Duggal Technical Expert BBMB & was being
used for repair. Extra dowels 20mm dia with split
end & wedge at the end @ 30 cm C/C spacing
were provided and grouted with cement slurry.
• After preparation of the surface the bonding coat
of epoxy paint was applied over the surface with
painting brush and the FRC concrete was laid
over it to the designed depth and was finished
with trowel at the end.
• As per practice in vogue the area inside the
Gate from sill plate to the end of stop logs is
repaired by using wet epoxy mortar with emery
powder of three grades in equal proportion as
filler. The mortar is laid over the bonding coat of
wet epoxy resins & is finished with trowel.
• FARMULATION OF EPOXY &
CONCRETE USED FOR THE REPAIR
OF PANDOH SPILLWAY
FORMULATION OF EPOXYFORMULATION OF EPOXY
RESINS USEDRESINS USED
• Formulations of Epoxy resins
• 1 For Dry condition
• A. FORMULATION OF DR.BECK’S EPOXY RESINS
• Sr.No Combination Ratio
• 1. Dobeckot-505 C 100 PBW
• 2. Hardener EH-411 50 PBW
• 3. Filler material 800-900 PBW
• 4. Pot life 75 min at 250
C
• B. FORMULATION OF CIBA GEIGY’EPOXY RESINS
• Sr.No Combination Ratio
• 1. Araldite GY-257 100 PBW
• 2. Hardener HY 840 45 PBW
• 3. Hardener HY-960 3 PBW
• 4. Filler material as used 800-900 PBW
• 5. Pot life 90 Min at 300
C
FORMULATION OF EPOXYFORMULATION OF EPOXY
RESINS USEDRESINS USED
• 2 For wet condition
• A. FORMULATION OF CIBA GEIGY’EPOXY RESINS
• Ist Formulation
• Sr.No Combination Ratio
• 1. Araldite GY-250 100 PBW
• 2. Hardener HY 2958 13.5 PBW
• 3. Hardener HY-825 12.5 PBW
• 4. Filler material as used 400-500 PBW
• 5. Pot life 30 Min at 300
C
• 2nd Formulation
• Sr.No Combination Ratio
• 1. Araldite GY-250 100 PBW
• 2. Hardener HY 2958 18 PBW
• 3. Filler material as used 400-500 PBW
• 4. Pot life 20 Min at 300
C
FORMULATION OF EPOXYFORMULATION OF EPOXY
RESINS USEDRESINS USED
• B. FORMULATION OF DR.BECK’S EPOXY RESINS
• Sr.No Combination Ratio
• 1. Dobeckot - 505 C 100 PBW
• 2. Beck Bond UW grout 42 B 34 PBW
• 3. Filler material 700-900 PBW
• 4. Pot life 80 Min at 250
C
Mix Design for 7000 PSI C.ConcMix Design for 7000 PSI C.Conc
• Qty. of material for 7000 PSI mix design:
• Ratio 1: 0.66 : 1.35
• Per bag Per Cum
• i) Cement = 50 Kg = 14.2 bag
• ii) Sand = 33.31 Kg. (0.765 Cft.) = 0.312 cum
• or .022 cum
• iii) Aggregate = 67.60 Kg. (1.683 cft.) = 0.667 cum
• iv) Water cement ratio = 0.31
• V) Slump = 4 “ + 1/2 “
• Box size used for sand = 12 “ X 12 “ X 9 “ = 0.750 cft.
• Box used = 1.021 Box/Bag.
• Box size used for agg. = 12 “ X12 “ X10.5 “ =0.875 cft.
• Box used = 1.923 Box/Bag
RECOMMENDATIONS BY NCCBM BALLABGARH FOR THE CONCRETERECOMMENDATIONS BY NCCBM BALLABGARH FOR THE CONCRETE
MIX DESIGNMIX DESIGN
For M 50 Grade : Workability: 50-75mm Slump.For M 50 Grade : Workability: 50-75mm Slump.
Mix Constituents Per Cu Mtr (Kg)
Cement (43 grade OPC) 454
Micro Silica 39
Water 138
Fine Aggregate 678
Coarse Aggregate
10-20 mm (55%)
< 10mm (45%)
636
520
Admixture @ 1.1% by wt. of cement+
Micro Silica
5.4
VMA @ 0.10% by wt. of cement + Micro
Silica
0.50
Steel Fibre 25.0
Water/ Cement + Micro silica Ratio 0.28
MIXING OF STEEL FIBERIN THE MIXER FOR PREPRATION OF FIBER CONCRETE
WET EPOXY PAINTING BEFORE LAYING M-50 FIBER CONC.
VIEW OF ANCHORS PROVIDED IN THE FLIP BUCKET & LAYING OF CONCRETE
LAYING OF CONCRETE IN THE FLIP BUCKET IN PROGRESS
LAYING OF CONCRETE IN THE FLIP BUCKET IN PROGRESS
FINISHING OF CONCRETE IN THE FLIP BUCKET IN PROGRESS
FINISHED VERTICAL SURFACE WITH EPOXY MORTAR IN GATE NO. 2
VIEW OF THE FINISHED SURFACE WITH EPOXY MORTAR IN GATE NO. 2
CURING OF CONCRETE IN PROGRESS
PREPRATION OF EPOXY PAINTFOR EPOXY MORTAR
PREPERATION OF EPOXY MORTAR
REPAIR WITH EPOXY MORTAR IN THE FLIP BUCKET IN PROGRESS
REPAIR WITH EPOXY MORTAR IN THE FLIP BUCKET IN PROGRESS
FINISHED VIEW OF THE REPAIRED AREA WITH C.CONC. ON S/WAY CHUTE
CONC. JOINTS PAINTED WITH EPOXY PAINT ON S/WAY CHUTE
FILLING OF FLIP BUCKET AFTER COMPETION OF WORK IN BAY NO 1 TO4
FINISHED CONCRETE & EPOXY MORTAR IN FRONT OF GATE NO. 5
FILLING OF FLIP BUCKET AFTER REPAIR IN FRONT GATE NO. 5
VIEW OF THE STEEL GRATING FOR VENT PIPE GROOVES IN THE FLIP BUCKET
PLACING OF STEEL GRATING IN POSITION THE VENT PIPE GROOVES
REPAIR OF THE  SPILLWAY AT PANDOH DAM

More Related Content

What's hot

Construction equipment need and factors-nrc
Construction equipment need and factors-nrcConstruction equipment need and factors-nrc
Construction equipment need and factors-nrc
narayanch1979
 
Different Types of Formwork Syetem Used within Indian Construction Industry
Different Types of Formwork Syetem Used within Indian Construction IndustryDifferent Types of Formwork Syetem Used within Indian Construction Industry
Different Types of Formwork Syetem Used within Indian Construction IndustryAbhishek Shah
 
Maintenance and repair strategies - Repair and rehabilitation of structures(RRS)
Maintenance and repair strategies - Repair and rehabilitation of structures(RRS)Maintenance and repair strategies - Repair and rehabilitation of structures(RRS)
Maintenance and repair strategies - Repair and rehabilitation of structures(RRS)
Shanmugasundaram N
 
Repairs and rehabilitation 2012
Repairs and rehabilitation 2012Repairs and rehabilitation 2012
Repairs and rehabilitation 2012
Dhaval Jadhav
 
Reserviors its purpose and there main functions and uses
Reserviors its purpose and there main functions and usesReserviors its purpose and there main functions and uses
Reserviors its purpose and there main functions and uses
ammar gulzar
 
Design of continuous flushing settling basin and powerhouse
Design of continuous flushing settling basin and powerhouseDesign of continuous flushing settling basin and powerhouse
Design of continuous flushing settling basin and powerhouse
Raj Kc
 
10 ensayos del profesor arnold ehret
10 ensayos del profesor arnold ehret10 ensayos del profesor arnold ehret
10 ensayos del profesor arnold ehret
Ivan Francisco MG
 
Pipe Jacking
Pipe JackingPipe Jacking
Pipe Jacking
Himanshu Gupta
 
Method statement tank base concrete pouring
Method statement  tank base concrete pouringMethod statement  tank base concrete pouring
Method statement tank base concrete pouring
Bharatha Rathnayke
 
Design Aspects of Gates of Dam
Design Aspects of Gates of DamDesign Aspects of Gates of Dam
Design Aspects of Gates of Dam
Tushar Dholakia
 
Schedule of Rates
Schedule of RatesSchedule of Rates
Schedule of Rates
Raj Shah
 
Shear, bond bearing,camber & deflection in prestressed concrete
Shear, bond bearing,camber & deflection in prestressed concreteShear, bond bearing,camber & deflection in prestressed concrete
Shear, bond bearing,camber & deflection in prestressed concrete
MAHFUZUR RAHMAN
 
theory of seepage
theory of seepagetheory of seepage
theory of seepage
SANJEEV Wazir
 
Jetties and breakwater.pptx
Jetties and breakwater.pptxJetties and breakwater.pptx
Jetties and breakwater.pptx
DEVNAIK7
 
trouble shooting and remedy of Dam Gates
trouble shooting and remedy of Dam Gatestrouble shooting and remedy of Dam Gates
trouble shooting and remedy of Dam GatesTushar Dholakia
 
Rcc design by working stress method
Rcc design by working stress methodRcc design by working stress method
Rcc design by working stress method
JYOTIRANJAN43
 
Lessons learned from past earthquake - Structural dynamics and Earthquake Eng...
Lessons learned from past earthquake - Structural dynamics and Earthquake Eng...Lessons learned from past earthquake - Structural dynamics and Earthquake Eng...
Lessons learned from past earthquake - Structural dynamics and Earthquake Eng...
Shanmugasundaram N
 
Design of hydraulic structures ce 413
Design of hydraulic structures ce 413Design of hydraulic structures ce 413
Design of hydraulic structures ce 413
Saqib Imran
 
Repair materials.ppt
Repair materials.pptRepair materials.ppt
Repair materials.ppt
Vikash Kumar
 

What's hot (20)

Construction equipment need and factors-nrc
Construction equipment need and factors-nrcConstruction equipment need and factors-nrc
Construction equipment need and factors-nrc
 
Different Types of Formwork Syetem Used within Indian Construction Industry
Different Types of Formwork Syetem Used within Indian Construction IndustryDifferent Types of Formwork Syetem Used within Indian Construction Industry
Different Types of Formwork Syetem Used within Indian Construction Industry
 
Maintenance and repair strategies - Repair and rehabilitation of structures(RRS)
Maintenance and repair strategies - Repair and rehabilitation of structures(RRS)Maintenance and repair strategies - Repair and rehabilitation of structures(RRS)
Maintenance and repair strategies - Repair and rehabilitation of structures(RRS)
 
Repairs and rehabilitation 2012
Repairs and rehabilitation 2012Repairs and rehabilitation 2012
Repairs and rehabilitation 2012
 
Reserviors its purpose and there main functions and uses
Reserviors its purpose and there main functions and usesReserviors its purpose and there main functions and uses
Reserviors its purpose and there main functions and uses
 
Design of continuous flushing settling basin and powerhouse
Design of continuous flushing settling basin and powerhouseDesign of continuous flushing settling basin and powerhouse
Design of continuous flushing settling basin and powerhouse
 
10 ensayos del profesor arnold ehret
10 ensayos del profesor arnold ehret10 ensayos del profesor arnold ehret
10 ensayos del profesor arnold ehret
 
Pipe Jacking
Pipe JackingPipe Jacking
Pipe Jacking
 
Rain water harvesting
Rain water harvestingRain water harvesting
Rain water harvesting
 
Method statement tank base concrete pouring
Method statement  tank base concrete pouringMethod statement  tank base concrete pouring
Method statement tank base concrete pouring
 
Design Aspects of Gates of Dam
Design Aspects of Gates of DamDesign Aspects of Gates of Dam
Design Aspects of Gates of Dam
 
Schedule of Rates
Schedule of RatesSchedule of Rates
Schedule of Rates
 
Shear, bond bearing,camber & deflection in prestressed concrete
Shear, bond bearing,camber & deflection in prestressed concreteShear, bond bearing,camber & deflection in prestressed concrete
Shear, bond bearing,camber & deflection in prestressed concrete
 
theory of seepage
theory of seepagetheory of seepage
theory of seepage
 
Jetties and breakwater.pptx
Jetties and breakwater.pptxJetties and breakwater.pptx
Jetties and breakwater.pptx
 
trouble shooting and remedy of Dam Gates
trouble shooting and remedy of Dam Gatestrouble shooting and remedy of Dam Gates
trouble shooting and remedy of Dam Gates
 
Rcc design by working stress method
Rcc design by working stress methodRcc design by working stress method
Rcc design by working stress method
 
Lessons learned from past earthquake - Structural dynamics and Earthquake Eng...
Lessons learned from past earthquake - Structural dynamics and Earthquake Eng...Lessons learned from past earthquake - Structural dynamics and Earthquake Eng...
Lessons learned from past earthquake - Structural dynamics and Earthquake Eng...
 
Design of hydraulic structures ce 413
Design of hydraulic structures ce 413Design of hydraulic structures ce 413
Design of hydraulic structures ce 413
 
Repair materials.ppt
Repair materials.pptRepair materials.ppt
Repair materials.ppt
 

Similar to REPAIR OF THE SPILLWAY AT PANDOH DAM

minor and micro irrigation
 minor and micro irrigation minor and micro irrigation
L14 - ONSITE SANITATION.pptx
L14 - ONSITE SANITATION.pptxL14 - ONSITE SANITATION.pptx
L14 - ONSITE SANITATION.pptx
PRACHI DESSAI
 
Hydraulic structures pdf
Hydraulic structures pdfHydraulic structures pdf
Hydraulic structures pdf
Saqib Imran
 
Well Foundation
Well FoundationWell Foundation
Well Foundation
Dave Chinmyee
 
well foundation of six lane new ganga bridge near kacchi dargah in district P...
well foundation of six lane new ganga bridge near kacchi dargah in district P...well foundation of six lane new ganga bridge near kacchi dargah in district P...
well foundation of six lane new ganga bridge near kacchi dargah in district P...
Arman Hashmi
 
Joints.pptx
Joints.pptxJoints.pptx
Joints.pptx
SupreethSP4
 
Penstocks, powerhouse and tailrace
Penstocks, powerhouse and tailracePenstocks, powerhouse and tailrace
Penstocks, powerhouse and tailraceRakesh Sunari Magar
 
Cut and cover_sections
Cut and cover_sectionsCut and cover_sections
Cut and cover_sectionsjuwes
 
Damconstruction 1
Damconstruction 1Damconstruction 1
Damconstruction 1
soenarto soendjaja
 
Construction Sequence.pptx
Construction Sequence.pptxConstruction Sequence.pptx
Construction Sequence.pptx
ssuser480182
 
Shaft sinking 2
Shaft  sinking 2Shaft  sinking 2
Shaft sinking 2
Er.Sunil Wasade
 
Earthen Dams
Earthen DamsEarthen Dams
Earthen Dams
GAURAV. H .TANDON
 
Soil Nailing
Soil NailingSoil Nailing
Soil Nailing
Seminar Links
 
The construction method for surface drainage (housing)
The construction method for surface drainage (housing)The construction method for surface drainage (housing)
The construction method for surface drainage (housing)
Adib Ramli
 
NRCS Pond Construction
NRCS Pond ConstructionNRCS Pond Construction
NRCS Pond Construction
Grant Schultz
 
ppt on sub structure construction.pptx
ppt on sub structure construction.pptxppt on sub structure construction.pptx
ppt on sub structure construction.pptx
RaviUraiya1
 
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptxAsif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
sfQyoom
 
Site Report
Site ReportSite Report
Site Report
ShavneelChand
 
BHUSAN GEOJE FIXED LINK presentation
BHUSAN GEOJE FIXED LINK presentationBHUSAN GEOJE FIXED LINK presentation
BHUSAN GEOJE FIXED LINK presentation
Amir Amdani
 

Similar to REPAIR OF THE SPILLWAY AT PANDOH DAM (20)

minor and micro irrigation
 minor and micro irrigation minor and micro irrigation
minor and micro irrigation
 
L14 - ONSITE SANITATION.pptx
L14 - ONSITE SANITATION.pptxL14 - ONSITE SANITATION.pptx
L14 - ONSITE SANITATION.pptx
 
Hydraulic structures pdf
Hydraulic structures pdfHydraulic structures pdf
Hydraulic structures pdf
 
Well Foundation
Well FoundationWell Foundation
Well Foundation
 
well foundation of six lane new ganga bridge near kacchi dargah in district P...
well foundation of six lane new ganga bridge near kacchi dargah in district P...well foundation of six lane new ganga bridge near kacchi dargah in district P...
well foundation of six lane new ganga bridge near kacchi dargah in district P...
 
Joints.pptx
Joints.pptxJoints.pptx
Joints.pptx
 
Penstocks, powerhouse and tailrace
Penstocks, powerhouse and tailracePenstocks, powerhouse and tailrace
Penstocks, powerhouse and tailrace
 
Cut and cover_sections
Cut and cover_sectionsCut and cover_sections
Cut and cover_sections
 
Damconstruction 1
Damconstruction 1Damconstruction 1
Damconstruction 1
 
Construction Sequence.pptx
Construction Sequence.pptxConstruction Sequence.pptx
Construction Sequence.pptx
 
Shaft sinking 2
Shaft  sinking 2Shaft  sinking 2
Shaft sinking 2
 
Earthen Dams
Earthen DamsEarthen Dams
Earthen Dams
 
Soil Nailing
Soil NailingSoil Nailing
Soil Nailing
 
The construction method for surface drainage (housing)
The construction method for surface drainage (housing)The construction method for surface drainage (housing)
The construction method for surface drainage (housing)
 
NRCS Pond Construction
NRCS Pond ConstructionNRCS Pond Construction
NRCS Pond Construction
 
ppt on sub structure construction.pptx
ppt on sub structure construction.pptxppt on sub structure construction.pptx
ppt on sub structure construction.pptx
 
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptxAsif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
 
Site Report
Site ReportSite Report
Site Report
 
BHUSAN GEOJE FIXED LINK presentation
BHUSAN GEOJE FIXED LINK presentationBHUSAN GEOJE FIXED LINK presentation
BHUSAN GEOJE FIXED LINK presentation
 
Dishant ppt
Dishant pptDishant ppt
Dishant ppt
 

Recently uploaded

一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
zwunae
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
SUTEJAS
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
Technical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prismsTechnical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prisms
heavyhaig
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
aqil azizi
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
SyedAbiiAzazi1
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
ClaraZara1
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
gestioneergodomus
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Soumen Santra
 
Steel & Timber Design according to British Standard
Steel & Timber Design according to British StandardSteel & Timber Design according to British Standard
Steel & Timber Design according to British Standard
AkolbilaEmmanuel1
 
PPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testingPPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testing
anoopmanoharan2
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
symbo111
 

Recently uploaded (20)

一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
Technical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prismsTechnical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prisms
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
 
Steel & Timber Design according to British Standard
Steel & Timber Design according to British StandardSteel & Timber Design according to British Standard
Steel & Timber Design according to British Standard
 
PPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testingPPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testing
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
 

REPAIR OF THE SPILLWAY AT PANDOH DAM

  • 2. General View of Pandoh Dam & SPILLWAY
  • 3. General View of Pandoh SPILLWAY
  • 4.
  • 5. • Pandoh Dam spillway is meant for the release of water of R-Beas in excess to the requirement at Pandoh after maintaining the required PRL during the monsoon season and also for the continuous release of 15 % water for the rest of the period during the year. The release of 15 % water downstream of Pandoh Dam has been made mandatory by the Hon’ble High court Shimla (HP) since -2005.
  • 6. • Pandoh spillway is an orifice type chute spillway and there are 5 No radial gates having size 12mt x 13 mt each which are designed for the maximum release of 3,51,000 cusec of discharge. The width of the spillway at the crest is 74 mt and the clear water way is 60 mtr. The overall area of the spillway from the zero RD to the end of flip bucket is 93,413 sq ft.
  • 7. • The total spillway area can be divided into three parts :- • 5 No crest blocks, • 42 No. chute blocks • 7 No. flip bucket blocks. • The spillway chute has a slope of 2.5: 1. The energy dissipater type flip bucket has been provided at the end of the spillway chute having 50 ft radius and the angle of the flip bucket is 350
  • 8. • The thickness of the conc. floor of the spillway chute is 3 ft which increases to 10 ft in the middle of the flip bucket and 19 ft at the end of flip bucket. The chute floor has been tied to the underlying rock by means of 25mm dia deformed anchors 15 ft deep into the rock and spaced at 6 ft c/c. • Reinforcement bars 20mm dia @ 30 Cm c/c has been provided both in longitudinal & cross direction on the spillway chute & flip bucket floor area. A top cover of 6” has been provided to the steel reinforcement .
  • 9. Total 0.127x106 m3 of the conc. of various strengths has been used for the construction of Pandoh spillway:- 1. 1500 psi - for protective coat over rock 2. 4000psi - water contact surface for abrasion resistance 3. 3000psi - for all other sections of spillway
  • 10. • Every year during the monsoon season the river discharge carries a huge quantity of silt laden water, boulders and tree logs which rolls over the spillway surface and also the frequent flushing operations which are carried out during the monsoon season for the exclusion of deposited silt in the Pandoh reservoir causes heavy damage to the spillway chute and flip bucket.
  • 11. • It has been observed from the past experience that every year after the monsoon season, approximately 30,000 sq ft of the spillway area gets damaged which includes the area of spillway chute, flip bucket and the area of one No. gate from sill plate to the end of stop logs, taken up for major repair during the year • The extent of the average damage on the spillway chute and flip bucket is generally found between 2” to 4 “.
  • 12. Some times reinforcement bars provided in the chute surface & flip bucket also gets exposed due to hit of the heavy tree logs & continuous rolling of boulders & other material over the spillway surface during the flushing operations. The steel plate provided at the end of the flip bucket also gets eroded at many places due to continuous passing of silt laden water & rolling of boulders during the monsoon season.
  • 13. • The maximum damage to the spillway area occurred so for after the construction of the project was observed in the year 1995 when the historical flood to the tune of 1,61,000 Cs was passed through the Pandoh spillway. • The heavy rains of (2480 mm)97” was recorded during the year in the catchment area upstream of Pandoh Dam which was much more than the Av. Annual rain fall of 54” in the catchment area. • The damage to the spillway observed after the flood season of 1995 was 58,310 sq ft .
  • 14. • The year wise area damaged and repair of the spillway carried out so for since the year 1985- 86 has been summarized as :-
  • 15. Year wise area damaged & S/wayYear wise area damaged & S/way Repair Carried OutRepair Carried Out Year Area Damaged (Sq. Ft( Area Repaired (Sq. Ft( 1985-86 7120 7120 1986-87 22128 22128 1987-88 19353 19353 1988-89 45026 45026 1989-90 29450 29450 1990-91 12000 12000 1991-92 4360 4360 1992-93 29000 29000 1993-94 34840 29800 1994-95 48240 40900 1995-96 58310 43890
  • 16. Year wise area damaged & S/way RepairYear wise area damaged & S/way Repair Carried OutCarried Out Year Area Damaged (Sq. Ft( Area Repaired (Sq. Ft( 1996-97 38550 35700 1997-98 33300 33300 1998-99 40000 40000 1999-2000 34800 34800 2000-01 30800 30800 2001-02 20000 20000 2002-03 20020 20020 2003-04 15898 15898 2004-05 27761 21000 2005-06 33410 33410 2006-07 45332 45332 2007-08 28000 28000
  • 17. Year wise area damaged & S/way RepairYear wise area damaged & S/way Repair Carried OutCarried Out Year Area Damaged (Sq. Ft( Area Repaired (Sq. Ft( 2008-09 36000 36000 2009-10 7000 7000 2010-11 15800 15800 2011-12 6300 14700 2012-13 6000 6000 2013-14 21000 21000 2014-15 22218 22218 2015-16 12288 12288
  • 18. • CONSTRUCTION OF TEMPORARY BANDH AND SEPERATOR WALL
  • 19. To start with the repair work first of all a temporary bandh is constructed across the flip bucket & the flip bucket is divided into two parts. It thus facilitate the repair work to be carried out in two phases:- • in the first phase the water is released through Gate No 5 and the area in front of gate No-1 to gate No -4 up to the end of flip bucket is repaired. • In the second phase the water is released through Gate No- 1 and the area in front of Gate No-5 is repaired.
  • 20. • To start with the work for the construction of temporary bandh and separator wall first of all the leakages from all the five no. radial gates is diverted towards Gate No-5 after getting the permission for the closure of 15 % discharges D/stream of Pandoh Dam for at least 15 days from HP Environment & Pollution Control Board Shimla. • The temporary bandh is constructed in the line of pier of Gate No 4 & 5 in the flip bucket using jute bags of 50 kg capacity filled with clay.
  • 21. • A two ft wide Separator Wall consisting of hollow block masonry is also constructed throughout the length and height of the bandh simultaneously with the raising of the bandh. • Loose clay filled in plastic bags is placed and compacted in the voids between the gaps of hollow block masonry wall and temporary bandh. • One side of the separator wall is plastered to prevent the leakage of water from the masonry wall towards the working area in front of Gate No 1 to 4.
  • 22. • The height of the bandh and masonry is kept 2 ft above the height of flip bucket so as to ensure the continuous release of 15 % of water downstream of Pandoh Dam without spilling into the working area prepared for carrying out the repair in front of Gate No 1 to 4.
  • 23. COLLECTION OF MATERIAL FOR KATCHA BANDH IN FLIP BUCKET
  • 24. CONSTRUCTION OF KATCHA BANDH IN FLIP BUCKET IN PROGRESS
  • 25. CONSTRUCTION OF KATCHA BANDH IN FLIP BUCKET IN PROGRESS
  • 26. CONSTRUCTION OF KATCHA BANDH IN FLIP BUCKET IN PROGRESS
  • 27. VIEW OF THE COMPLETED KATCHA BANDH IN FLIP BUCKET
  • 28. VIEW OF THE COMPLETED KATCHA BANDH IN FLIP BUCKET
  • 29. LIFTING OF MATERIAL AFTER THE COMPLETION OF BANDH
  • 30. LIFTING OF MATERIAL AFTER THE COMPLETION OF BANDH
  • 31. RELEASE OF WATER D/S OF S/WAY AFTER THE COMPLETION OF BANDH
  • 32. • ASSESSMENT OF DAMAGED AREA
  • 33. • After the construction of the Separator Wall and making the surface approachable the whole of the area is surveyed to know the extent of damage occurred and to make the planning's for the repairs to be carried out. • The photography & video-graphy of the damaged area is also done and kept as record for future .
  • 34. DAMAGED AREA OF PANDOH SPILLWAY CHUTE
  • 35. DAMAGED AREA OF PANDOH SPILLWAY CHUTE
  • 36. DAMAGED AREA OF PANDOH SPILLWAY CHUTE
  • 37. DAMAGED AREA OF PANDOH SPILLWAY CHUTE
  • 38. DAMAGED AREA OF PANDOH SPILLWAY CHUTE & FLIP BUCKET(2007-08)
  • 39. DAMAGED AREA IN THE FLIP BUCKET
  • 40. EXPOSED REINFORCEMENT BARS IN THE FLIP BUCKET (2007-08)
  • 41. EXPOSED REINFORCEMENT BARS IN THE FLIP BUCKET(2007-08)
  • 45. • After assessing the damaged area the work for the surface preparation is started. The whole of the area is first washed by air water jet to remove elegy . The area is then dried & further cleaning is made by steel wire brushes to remove the dust. • The loose concrete if any is removed by nicking & hammering. Dust particles present in the pot holes are also removed with the help of steel wire brushes & compressed air so as to have a good bond between the old and new area.
  • 46. WASHING OF SURFACE WITH AIR WATER JET IN FLIP BUCKET
  • 47. CUTTING OF LOOSE MATERIAL BEFORE REPAIR
  • 48. • The reinforcement bars which are found exposed and damaged are repaired & maintained as per the original design .The additional bars are provided in place where ever required and the welding is done through out the length of the joint between old & new steel bars. • Additional dowels with split end on one side are also provided at the junction of longitudinal and cross reinforcement bars. The dowels are anchored in the holes with wedge at the end and are grouted with cement grout. The longitudinal & cross reinforcement bars are then welded with these dowels.
  • 49. • The steel plate provided at the end of the flip bucket is also maintained as per its original shape. Pieces of M.S. plate are welded where ever it is required and the pitting in the plate is filled up with steel welding. • Concrete is grouted under the steel plate where ever a gap is found .The whole of the steel plate after repair is covered with a protective coat of epoxy mortar.
  • 50. DRILLING WORK FOR PROVIDING ANCHORS IN THE FLIP BUCKET
  • 51. REPAIR OF STEEL PLATE AT THE END OF FLIP BUCKET IN PROGRESS
  • 52. REPAIR OF PANDOH SPILLWAY
  • 53. The damaged area is classified into two categories:- 1. Normal Abrasion i.e. depth of damage up to ½’’. 2. Heavy Abrasion where the depth of damage is more than 2” & above
  • 54. • i) For the repair of the normal abrasion up to 1/2” depth the repair is carried out with epoxy mortar using three grades of emery powder Gr. 40,60 & 100 in equal proportion as filler. • The epoxy mortar is laid over the surface painted with bonding coat of epoxy paint and the surface is finished with steel gurmalah at the end.
  • 55. • For the repair of heavily damaged area rich c.conc. 7000 PSI strength was being used since 1993-94 to the year 2006-07 . In the year 2007- 08 the heavy damages of conc. in the flip bucket to the tune of 6” to 9” were observed. The reinforcement bars were also found badly exposed. • Keeping in view M-50 concrete with steel fiber and admixtures (FRC) was got designed from NCCBM Ballabgarh, on the initiation of sh SK Duggal Technical Expert BBMB & was being used for repair. Extra dowels 20mm dia with split end & wedge at the end @ 30 cm C/C spacing were provided and grouted with cement slurry.
  • 56. • After preparation of the surface the bonding coat of epoxy paint was applied over the surface with painting brush and the FRC concrete was laid over it to the designed depth and was finished with trowel at the end. • As per practice in vogue the area inside the Gate from sill plate to the end of stop logs is repaired by using wet epoxy mortar with emery powder of three grades in equal proportion as filler. The mortar is laid over the bonding coat of wet epoxy resins & is finished with trowel.
  • 57. • FARMULATION OF EPOXY & CONCRETE USED FOR THE REPAIR OF PANDOH SPILLWAY
  • 58. FORMULATION OF EPOXYFORMULATION OF EPOXY RESINS USEDRESINS USED • Formulations of Epoxy resins • 1 For Dry condition • A. FORMULATION OF DR.BECK’S EPOXY RESINS • Sr.No Combination Ratio • 1. Dobeckot-505 C 100 PBW • 2. Hardener EH-411 50 PBW • 3. Filler material 800-900 PBW • 4. Pot life 75 min at 250 C • B. FORMULATION OF CIBA GEIGY’EPOXY RESINS • Sr.No Combination Ratio • 1. Araldite GY-257 100 PBW • 2. Hardener HY 840 45 PBW • 3. Hardener HY-960 3 PBW • 4. Filler material as used 800-900 PBW • 5. Pot life 90 Min at 300 C
  • 59. FORMULATION OF EPOXYFORMULATION OF EPOXY RESINS USEDRESINS USED • 2 For wet condition • A. FORMULATION OF CIBA GEIGY’EPOXY RESINS • Ist Formulation • Sr.No Combination Ratio • 1. Araldite GY-250 100 PBW • 2. Hardener HY 2958 13.5 PBW • 3. Hardener HY-825 12.5 PBW • 4. Filler material as used 400-500 PBW • 5. Pot life 30 Min at 300 C • 2nd Formulation • Sr.No Combination Ratio • 1. Araldite GY-250 100 PBW • 2. Hardener HY 2958 18 PBW • 3. Filler material as used 400-500 PBW • 4. Pot life 20 Min at 300 C
  • 60. FORMULATION OF EPOXYFORMULATION OF EPOXY RESINS USEDRESINS USED • B. FORMULATION OF DR.BECK’S EPOXY RESINS • Sr.No Combination Ratio • 1. Dobeckot - 505 C 100 PBW • 2. Beck Bond UW grout 42 B 34 PBW • 3. Filler material 700-900 PBW • 4. Pot life 80 Min at 250 C
  • 61. Mix Design for 7000 PSI C.ConcMix Design for 7000 PSI C.Conc • Qty. of material for 7000 PSI mix design: • Ratio 1: 0.66 : 1.35 • Per bag Per Cum • i) Cement = 50 Kg = 14.2 bag • ii) Sand = 33.31 Kg. (0.765 Cft.) = 0.312 cum • or .022 cum • iii) Aggregate = 67.60 Kg. (1.683 cft.) = 0.667 cum • iv) Water cement ratio = 0.31 • V) Slump = 4 “ + 1/2 “ • Box size used for sand = 12 “ X 12 “ X 9 “ = 0.750 cft. • Box used = 1.021 Box/Bag. • Box size used for agg. = 12 “ X12 “ X10.5 “ =0.875 cft. • Box used = 1.923 Box/Bag
  • 62. RECOMMENDATIONS BY NCCBM BALLABGARH FOR THE CONCRETERECOMMENDATIONS BY NCCBM BALLABGARH FOR THE CONCRETE MIX DESIGNMIX DESIGN For M 50 Grade : Workability: 50-75mm Slump.For M 50 Grade : Workability: 50-75mm Slump. Mix Constituents Per Cu Mtr (Kg) Cement (43 grade OPC) 454 Micro Silica 39 Water 138 Fine Aggregate 678 Coarse Aggregate 10-20 mm (55%) < 10mm (45%) 636 520 Admixture @ 1.1% by wt. of cement+ Micro Silica 5.4 VMA @ 0.10% by wt. of cement + Micro Silica 0.50 Steel Fibre 25.0 Water/ Cement + Micro silica Ratio 0.28
  • 63. MIXING OF STEEL FIBERIN THE MIXER FOR PREPRATION OF FIBER CONCRETE
  • 64. WET EPOXY PAINTING BEFORE LAYING M-50 FIBER CONC.
  • 65. VIEW OF ANCHORS PROVIDED IN THE FLIP BUCKET & LAYING OF CONCRETE
  • 66. LAYING OF CONCRETE IN THE FLIP BUCKET IN PROGRESS
  • 67. LAYING OF CONCRETE IN THE FLIP BUCKET IN PROGRESS
  • 68. FINISHING OF CONCRETE IN THE FLIP BUCKET IN PROGRESS
  • 69. FINISHED VERTICAL SURFACE WITH EPOXY MORTAR IN GATE NO. 2
  • 70. VIEW OF THE FINISHED SURFACE WITH EPOXY MORTAR IN GATE NO. 2
  • 71. CURING OF CONCRETE IN PROGRESS
  • 72. PREPRATION OF EPOXY PAINTFOR EPOXY MORTAR
  • 73.
  • 75. REPAIR WITH EPOXY MORTAR IN THE FLIP BUCKET IN PROGRESS
  • 76. REPAIR WITH EPOXY MORTAR IN THE FLIP BUCKET IN PROGRESS
  • 77. FINISHED VIEW OF THE REPAIRED AREA WITH C.CONC. ON S/WAY CHUTE
  • 78. CONC. JOINTS PAINTED WITH EPOXY PAINT ON S/WAY CHUTE
  • 79. FILLING OF FLIP BUCKET AFTER COMPETION OF WORK IN BAY NO 1 TO4
  • 80. FINISHED CONCRETE & EPOXY MORTAR IN FRONT OF GATE NO. 5
  • 81. FILLING OF FLIP BUCKET AFTER REPAIR IN FRONT GATE NO. 5
  • 82. VIEW OF THE STEEL GRATING FOR VENT PIPE GROOVES IN THE FLIP BUCKET
  • 83. PLACING OF STEEL GRATING IN POSITION THE VENT PIPE GROOVES