2. 2
Introduction to Project Scope
Plan Scope Management
Collect Requirements
Define Scope
Create WBS
Control Scope
Validate Scope
KEY TERMS
3. • Product scope :
The features and functions that characterize a product, service, or
result.
• Project scope :
The work performed to deliver a product, service, or result with the
specified features and functions. The term project scope is sometimes
viewed as including product scope.
• Project Scope Management:
Includes the processes required to ensure that the project includes all
the work required, and only the work required, to complete the project
successfully
Product Scope vs. Project Scope
3
4. 5- Project Scope Management
Knowledg
e Area
Process
Initiating Planning Executing
Monitoring &
Control
Closin
g
Scope
1-plan scope management
2-Collect Requirements
3-Define Scope
4-Create WBS
5-Verify Scope
6-Control Scope
Enter phase/
Start project
Exit phase/
End project
Initiating
Processes
Closing
Processes
Planning
Processes
Executing
Processes
Monitoring &
Controlling Processes
4
6. The process of creating a scope management plan that documents how
the project scope will be defined, validated, and controlled.
It provides guidance and direction on scope will be managed.
5.1- Plan Scope Management
6
8. 8
5.1 Plan Scope Management: Inputs
1. Project Management Plan
2. Project Charter
3. EEF
• Organization’s culture,
• Infrastructure,
• Personnel administration, and
• Marketplace conditions.
4. OPA
• Policies and procedures, and
• Historical information and lessons learned
knowledge base.
9. 9
5.1 Plan Scope Management: T & T
1. Expert judgment
2. Meetings
5.1 Plan Scope Management: Outputs
1. Scope Management Plan
2. Requirements Management Plan
11. 11
5.2- Collect Requirements
Requirements can be grouped into classifications including:
Business requirements, describe the high-level needs of the organization as a
whole.
Stakeholder requirements, describe needs of a stakeholder or stakeholder
group.
Solution requirements, describe features, functions and characteristics of the
product, service, or results.
Transition requirements, describe temporary capabilities such as data conversion
& training needs.
Project requirements, which describe the actions, processes, or other conditions
the project needs to meet.
Quality requirements, which capture any condition or criteria needed to validate
the successful completion of a project deliverable or fulfillment of other project
requirements.
12. 12
• The process of defining and documenting stakeholders’
needs to meet the project objective.
5.2- Collect Requirements
14. 14
5.2 Collect Requirements: Inputs
1. Project Scope Management Plan
2. Requirements Management Plan
3. Stakeholder Management Plan
4. Project Charter
5. Stakeholder Register
15. 1. Interviews:
meeting the stakeholders to ask
prepared and spontaneous question
& recording the responses.
Collect Requirements: T & T
15
2. Focus groups:
Bring stakeholders and
subject matter experts together
to learn about their expectations
and attitudes about the project.
16. Collect Requirements: T & T
16
3. Facilitated Workshops :
Focused session with key cross-functional stakeholders to define
product requirements.
JAD Joint application design, in software development industry
bringing business subject matter experts and the development team
together to improve the software development process
QFD Quality function development In the manufacturing industry
Helps determine critical characteristic of new product development
Start by collecting customer need
QFD = VOC: Voice of the Customers
17. Collect Requirements: T & T
17
4. GROUP CREATIVITY TECHNIQUES:
1. Brainstorming
2. Nominal group technique: enhance brainstorming with voting and ranking.
3. Idea/mind mapping individual brainstorming sessions are consolidated
into a single map.
18. Collect Requirements: T & T
18
4- Affinity Diagram: A technique that allows large numbers of ideas to be
classified into groups for review and analysis.
19. Collect Requirements: T & T
19
5- Multi-criteria decision analysis : Establishing criteria, such as risk
levels, uncertainty, and valuation, to evaluate and rank many ideas.
20. Collect Requirements: T & T
20
6- Delphi Technique: A request for information is sent to experts who
participate anonymously. Their responses are collected, and the results are
sent back to the experts mutually for further review until they reach
agreement. anonymous experts answer questionnaire and give feedback
21. Collect Requirements: T & T
21
5- Group Decision Making Techniques
Unanimity,
Majority (>50%),
Plurality,
Dictatorship
6- Questionnaire and Surveys wide number of respondents
7- Observations viewing individual in their environment
8- Prototypes early feedback by providing a working model
22. Collect Requirements: T & T
22
5- Benchmark
Involves comparing actual or planned practices, such as processes
and operations, to those of comparable organizations. The
organizations compared during benchmarking can be internal or
external.
6- Document Analysis
7- Context Diagrams
• Is an example of a scope model.
• Depict the product scope
• how people and other systems interact with it.
• Show inputs to the business system.
• Outputs from system
• Stakeholders receiving outputs.
25. 25
5.2 Collect Requirements: Outputs
2. Requirements Traceability Matrix
• A grid that links product requirements from their origin to the
deliverables that satisfy them.
• Provides a means to track requirements throughout the project
life cycle
34. 34
• Subdividing the project deliverables and project work into smaller
and more manageable components.
• WBS is a deliverable-oriented hierarchical decomposition of project
work.
5.4 Create WBS.
37. Project Name
Deliverable A
Control Account
A1
Work
Package
Work
Package
...
Control Account
A2
Work
Package ...
Deliverable B 2
Control Account
B1
Work
Package
Work
Package
...
Control Account
B2
Work
Package
• Control Account is a tool that allows for the aggregation and
analysis of work performance data regarding costs, schedule, and
scope
• Control Account provides a way to manage and control costs,
schedule, and scope at a higher level than the work package.
• Each work package in the WBS would be assigned to only one
control account.
38
39. • WBS dictionary.
• A document that provides detailed deliverable, activity, and
scheduling information about each component in the WBS.
• A document that supports the WBS. Information in the WBS
dictionary may include, but is not limited to:
○ Code of account identifier,
○ Description of work,
○ Assumptions and constraints,
○ Responsible organization,
○ Schedule milestones,
○ Associated schedule activities,
○ Resources required,
○ Cost estimates,
○ Quality requirements,
○ Acceptance criteria,
○ Technical references, and
○ Agreement information. 40
40. WP Name WBS ID
Description Assumptions
&
Constraints
Milestones
SN. Name Due Date
Activity
SN. Name
Human Resource Non-human Resource Material Line
TotalHours Rate Total Hours Rate Total QTY Rate Total
Quality Requirements Acceptance Criteria
Technical Reference Contractual Info
WPS Dictionary
45. 45
• Reviewing deliverables with the client.
• Formalizing acceptance of the completed project
deliverables from Client .
5.5 Validate Scope.
46. 46
Complete
Deliverables
( Direct & Manage Project Work )
Quality Control
Inspection
Customer
acceptance
(Validate Deliverables)
Change request is
evaluated through
ICC and approved
from CCB
Change
Request
Customer accept
Deliverables
51. 51
• Monitoring the status of the project & products scope
• Managing changes to scope baseline
• Ensure all requested changes and recommended
corrective or preventive actions are processed through the
“Perform Integrated Change Control” process.
5.6 Control Scope.
53. 53
5.6 Control Scope: Inputs
1. Project
Management Plan
Scope baseline
Scope management plan
Change management plan
Configuration management plan
Requirements management plan
2. Requirements Documentation
3. Requirements Traceability Matrix
4. Work Performance Data
5. OPA
54. 54
5.6 Control Scope: T & T
Variance
Analysis
Determining the cause and degree of difference between
the baseline and actual performance
5.6 Control Scope: Outputs
1. Work Performance Information
2. Change Requests
3. Project Management Plan Updates
4. Project Document Updates
5. OPA
55. 55
1. A work breakdown structure numbering system allows
the project team to:
A. Systematically estimate costs of work breakdown
structure elements.
B. Provide project justification.
C. Identify the level at which individual elements are found.
D. Use it in project management software.
Questions
56. 56
1. A work breakdown structure numbering system allows
the project team to:
A. Systematically estimate costs of work breakdown
structure elements.
B. Provide project justification.
C. Identify the level at which individual elements are
found.
D. Use it in project management software.
Answer : C
Questions
57. 57
2. The work breakdown structure can BEST be thought of as
an effective aid for …………….. communications.
A. Team
B. Project manager
C. Customer
D. Stakeholder
Questions
58. 58
2. The work breakdown structure can BEST be thought of as
an effective aid for …………….. communications.
A. Team
B. Project manager
C. Customer
D. Stakeholder
Answer : D
Questions
59. 59
3. Which of the following is a KEY output of the Validate
Scope process?
A. A more complete scope management plan
B. Customer acceptance of project deliverables
C. Improved schedule estimates
D. An improved project management information system
Questions
60. 60
3. Which of the following is a KEY output of the Validate
Scope process?
A. A more complete scope management plan
B. Customer acceptance of project deliverables
C. Improved schedule estimates
D. An improved project management information system
Answer : B
Questions
61. 61
4. During project executing, a team member comes to the
project manager because he is not sure what work he needs
to accomplish on the project. Which of the following
documents contains detailed descriptions of work packages?
A. WBS dictionary
B. Activity list
C. Project scope statement
D. Scope management plan
Questions
62. 62
4. During project executing, a team member comes to the
project manager because he is not sure what work he needs
to accomplish on the project. Which of the following
documents contains detailed descriptions of work packages?
A. WBS dictionary
B. Activity list
C. Project scope statement
D. Scope management plan
Answer : A
Questions
63. 63
5. A project manager may use ___ to make sure the team
members clearly know what work is included in each of their
work packages.
A. The project scope statement
B. The product scope
C. The WBS dictionary
D. The schedule
Questions
64. 64
5. A project manager may use ___ to make sure the team
members clearly know what work is included in each of their
work packages.
A. The project scope statement
B. The product scope
C. The WBS dictionary
D. The schedule
Answer : C
Questions
65. 65
6. All of the following are parts of the scope baseline
EXCEPT the:
A. Scope management plan.
B. Project scope statement.
C. Work breakdown structure.
D. WBS dictionary.
Questions
66. 66
6. All of the following are parts of the scope baseline
EXCEPT the:
A. Scope management plan.
B. Project scope statement.
C. Work breakdown structure.
D. WBS dictionary.
Answer : A
Questions
67. 67
7. The development of the scope baseline can BEST be
described involving ……..
A. The functional managers.
B. The project team.
C All the stakeholders.
D. The project expediter
Questions
68. 68
7. The development of the scope baseline can BEST be
described involving ……..
A. The functional managers.
B. The project team.
C All the stakeholders.
D. The project expediter
Answer : B
Questions
69. 69
8 . Validate Scope is closely related to:
A. Control Quality.
B. Sequence Activities.
C. Perform Quality Assurance.
D. Time Management.
Questions
70. 70
8 . Validate Scope is closely related to:
A. Control Quality.
B. Sequence Activities.
C. Perform Quality Assurance.
D. Time Management.
Answer : A
Questions
71. 71
9. Which of the following can create the MOST
misinterpretation of the project scope statement?
A. Imprecise language
B. Poor pattern, structure, and chronological order
C. Small variations in size of work packages or detail of work
D. Too much detail
Questions
72. 72
9. Which of the following can create the MOST
misinterpretation of the project scope statement?
A. Imprecise language
B. Poor pattern, structure, and chronological order
C. Small variations in size of work packages or detail of work
D. Too much detail
Answer : A
Questions
73. 73
10. A scope change has been suggested by one of the
stakeholders on the project. After careful consideration and a
lot of arguing, the change control board has decided to reject
the change. What should the project manager do?
A. Support the stakeholder by asking the board for the reason for the
rejection.
B. Suggest to the stakeholder that the next change they request will be
approved.
C. Document the outcome of the change request.
D. Advise the change control board to make sure they create approval
processes before the next change is proposed.
Questions
74. 74
10. A scope change has been suggested by one of the
stakeholders on the project. After careful consideration and a
lot of arguing, the change control board has decided to reject
the change. What should the project manager do?
A. Support the stakeholder by asking the board for the reason for the
rejection.
B. Suggest to the stakeholder that the next change they request will be
approved.
C. Document the outcome of the change request.
D. Advise the change control board to make sure they create approval
processes before the next change is proposed.
Answer : C
Questions